Science.gov

Sample records for lepreau refurbishment project

  1. Container Refurbishment Cycle Time Reduction (CTR) Project

    SciTech Connect

    Aloi, t.; anthony, p; blair, t; forester, c; hall, k; hawk, t; gordon, b; johnsen, s; keck, g; clifford, m; reichert, d; rogers, p; richards, w; smallen, p; tilley, e

    2000-05-15

    In mid-1999, a Cycle Time Reduction (CTR) project was initiated by senior management to improve the overall efficiency of the Container Refurbishment process. A cross-functional team was formed by the Industrial Engineering Services group within Product Certification Organization to evaluate the current process and to propose necessary changes for improvement. The CTR team efforts have resulted in increased productivity equaling approximately $450K per year. The effort also significantly reduced the wait time required necessary to start assembly work on the shop floor. Increasing daily production time and identifying delays were key team goals. Following is a brief summary of accomplishments: (A) Productivity Improvements: (1) Reduced Radcon survey time for empty containers: (i) 50% at 9720-3 (ii) 67% at 9204-2 and (iii) 100% at 9212; (2) Eliminated container inspections at 9720-3; (3) Reduced charged time (includes hands-on labor and support functions) per empty container by 25%; (4) Reduced cycle time to refurbish a container by 25%. (Dramatic wait time reduction -Assembly); (5) Reduced the time for 9212 to receive empty, refurbished containers by 67-80%; (6) Reduced the time for 9204-2E to receive empty, refurbished containers from 1 day to immediate; (7) Implemented software to track time charged per container for continuous improvement; (8) Initiated continuous improvement efforts between Workstream experts and Refurbishment personnel, reworded complex Workstream prompts to allow worker data corrections, and reduces time of support groups, Workstream personnel, and Refurbishment personnel; (9) Consolidated refurbished, container warehousing areas, eliminated long travel times to areas outside the protected area portals to an area in the vicinity of the refurbishment area and a process area, benefits are improved container flow and better housekeeping; and (10) improved overall communication of team by flowcharting entire process. B. Annual Cost Savings: $453K

  2. Project Plan Remote Target Fabrication Refurbishment Project

    SciTech Connect

    Bell, Gary L; Taylor, Robin D

    2009-08-01

    authorization for the work was received in July 2009 under the Remote Target Fabrication Refurbishment Task of the Enhanced Utilization of Isotope Facilities project (Project Identification Code 2005230) funded by the American Recovery and Reinvestment Act of 2009. The goal of this project is to recover the capability to produce 4-5 curium targets for the irradiation period starting with HFIR cycle 427, currently scheduled to begin 2/17/10. Assuming success, the equipment would then be used to fabricate 6-7 additional targets to hold for the next irradiation campaign specified by the program. Specific objectives are the return to functionality of the Cubicle 3 Pellet Fabrication Line; Cubicle 2 Target Assembly equipment; and Cubicle 1 Target Inspection and Final Assembly system.

  3. Status of the LANSCE refurbishment project

    SciTech Connect

    Erickson, John L; Jones, Kevin W; Prince, Peter P

    2010-01-01

    The Los Alamos Neutron Science Center (LANSCE) accelerator is an 800-MeV proton linac that drives user facilities for isotope production, proton radiography, ultra-cold neutrons, weapons neutron research and various sciences using neutron scattering. The LANSCE Refurbishment Project (LANSCE-R) is an ambitious project to refurbish key elements of the LANSCE accelerator that are becoming obsolete or nearing end-of-life. The preliminary design phase for the project is funded and underway. The 6 year, $150M (US) project will enable future decades of reliable, high-performance operation. It will replace a substantial fraction of the radio-frequency power systems (gridded tubes and klystrons) with modern systems, completely refurbish the original accelerator control and timing systems, replace obsolete diagnostic devices, and modernize other ancillary systems. An overview of the LANSCE-R project will be presented. The project requirements will be discussed, the preliminary technical solutions presented, and the plan for successful project execution while meeting annual customer expectations for beam delivery will be reviewed.

  4. LANSCE beam instrumentation and the LANSCE refurbishment project

    SciTech Connect

    Mccrady, Rodney C; Blind, Barbara; Gilpatrick, John D; Pillai, Chandra; Power, John F; Rybarcyk, Lawrence J; Sedillo, James D; Gruchalla, Michael E

    2010-01-01

    The heart of the LANSCE accelerator complex consists of Cockroft-Walton-type injectors, a drift-tube linac (DTL) and a side-coupled linac (CCL). These systems are approaching 40 years of age and a project to re-establish high-power capability and to extend the lifetime is underway. Many of the present beam diagnostic systems are difficult to maintain, and the original beam position monitors don't provide any data at all. These deficiencies hamper beam tuning and trouble-shooting efforts. One thrust of the refurbishment project is to restore reliable operation of the diagnostic systems. This paper describes the present diagnostics systems and their limitations and the envisaged next-generation systems. The emphasis will be on the uses and requirements for the systems rather than the solutions and engineering aspects of the refurbishment.

  5. Update of the Z Refurbishment project (ZR) at Sandia National Laboratories.

    SciTech Connect

    Moncayo, Carla; Bloomquist, Douglas D.; Weed, John Woodruff; Tabor, Debra Ann; Donovan, Guy Louis; McKee, G. Randall; Weinbrecht, Edward A.; Faturos, Thomas V.; McDaniel, Dillon Heirman

    2007-08-01

    Sandia's Z Refurbishment (ZR) Project formally began in February 2002 to increase the Z Accelerator's utilization by providing the capability to perform more shots, improve precision and pulse shape variability, and increase delivered current. A project update was provided at the 15th International Pulsed Power Conference in 2005. The Z facility was shut down in July 2006 for structural/infrastructure modifications and installation of new pulsed power systems. The refurbishment will conclude in 2007. This paper provides a status update of the project covering the past 2 years of activities.

  6. Systems engineering aspects to installation of the phased multi-year LANSCE-refurbishment project

    SciTech Connect

    Pieck, Martin; Erickson, John E; Gulley, Mark S; Jones, Kevin W; Rybarcyk, Larry J

    2009-01-01

    The LANSCE Refurbishment Project (LANSCE-R) is a phased, multiyear project. The project is scheduled to start refurbishment in the 2nd quarter of fiscal year 2011. Closeout will occur during the 4th quarter of FY2016. During the LANSCE-R project, installation of project components must be scheduled during six annual 6-month maintenance-outages and not conflict with annual LANSCE operational commitments to its user facilities. The project and operations schedules must be synchronized carefully. Therefore, the scheduled maintenance outages, functional testing (with beam off, by primarily project personnel) and commissioning (with beam on, by primarily Accelerator Operation Technology (AOT) personnel) must be managed to accommodate operation. Active and effective coordination and communication between the project and AOT personnel must be encouraged to identify, as early as possible, any operational issues. This paper will report on the systems engineering approach to the integration and control of engineering activities.

  7. EHS and FME Lend Their Expertise to NCI Campus Refurbishment Project | Poster

    Cancer.gov

    In October 2015, the NCI executive officer and the director of NCI’s Office of Space and Facilities Management (OSFM) announced a wide-ranging refurbishment plan for NCI at Frederick. Since then, a project team comprising members from the Office of Scientific Operations, the Management Operations Support Branch, OSFM, the Center for Cancer Research, the Environment, Health, and Safety (EHS) directorate, and the Facilities Maintenance and Engineering (FME) directorate have met regularly with the laboratory groups affected by the refurbishment plan. Read more...

  8. Status of the Z Refurbishment project (ZR) at Sandia National Laboratories.

    SciTech Connect

    Weinbrecht, Edward A.; Bloomquist, Douglas D.; Warner, Peggy Jean; McDaniel, Dillon Heirman; Faturos, Thomas V.; Tabor, Debra Ann; McKee, G. Randall; Weed, John Woodruff

    2005-06-01

    Sandia National Laboratories Z Refurbishment (ZR) Project formally began in August 2002 to increase the Z Accelerator's utilization by providing the capability to perform more shots, improve precision and pulse shape variability, increase delivered current, and accomplish the improvements with minimal disruption to Z's ongoing programs. A project overview was provided at the 14th International Pulsed Power Conference in 2003. This paper provides an update of the project including architectural changes over the past two years, timeframe for completion, and overall design and fabrication status.

  9. Leveraging the LEDA high voltage power supply systems for the LANSCE refurbishment project

    SciTech Connect

    Bradley Iii, Joseph Thomas; Rees, Daniel E; Roybal, William T; Young, Karen A

    2008-01-01

    The LANSCE Refurbishment Project (LANSCE-R) will revitalize the LANSCE accelerator infrastructure. Much of the equipment has been in use for over 39 years and is approaching the end of its design lifetime. As obsolescence issues make like-for-like replacements increasingly more expensive, modern systems with lower costs become a reasonable alternative. As part of the LANSCE-R project, four of the seven HV power supplies for the 805 MHz RF klystrons will be replaced. The present and future requirements for these power supplies influence the selection of replacement options. Details of the HV power supply replacement requirements and the different replacement options will be discussed. One option is to use four 95 kV, 21 A DC power supplies originally installed nearby as part of the Low Energy Demonstration Accelerator (LEDA) project. Significant material and labor cost savings can be achieved by leaving these supplies installed where they are and building a HV transport system to bring high voltage power from the existing LEDA facility to the LANSCE facility. The different replacement options will be compared based on material and labor costs as offset by long-term energy savings.

  10. Molten-Caustic-Leaching (Gravimelt) System Integration Project, Phase 2. Topical report for test circuit maintenance, refurbishment, modification, and off-line operation

    SciTech Connect

    Not Available

    1993-03-01

    This is a report of the maintenance, refurbishment, modifications, and off-line circuit component testing of the integrated test circuit of the Molten-Caustic-Leaching (MCL or Gravimelt) process for the desulfurization and demineralization of coal. The project is sponsored by the Pittsburgh Energy Technology Center of the US Department of Energy under Contract No. DE-AC22-86-PC91257.

  11. Large, live line rehab project requires detailed planning: Part 1. [Refurbishing in-service oil and gas pipelines

    SciTech Connect

    Leeds, J.M. ); Catley, M.G. )

    1994-02-01

    Detailed planning and organization has resulted in a smoothly executed six-year coating refurbishment program on 373 mi of live, high-pressure pipe in South Australia. Production of oil and gas in north-east South Australia. Production of oil and gas in north-east South Australia began in 1969 using pipe lines coated in single wrap polyethylene (PE) tape that, over time, has undergone severe degradation due to poor construction practices, severe soil stresses and, in some cases, high temperatures in transported fluids. In the late 70s, a massive expansion of natural gas production was planned. Given known problems with PE tapes, an alternative coating, flake-filled isophthalic polyester, was selected for high-temperature lines. When this subsequently failed, the polyester was replaced by fusion bonded epoxy (FBE). To date, only minor problems have been experienced with FBE. In the early 80s, about 373 mi were coated with suspect materials, either tape or polyester. In addition to corrosion leaks, there had been five failures due to stress corrosion cracking (SCC). Two of the most severe were in a 20-in. OD trunkline. Problems were somewhat exacerbated by the pipe lines being buried in some of the most corrosive soils in existence. To ameliorate the situation, a massive coating refurbishment program, the largest in the southern hemisphere, was undertaken. Because few of the lines initially were looped, it was decided to repair lines, where possible, live and operating at their normal 1,250 psi. Only concession was shut-down of lines with a history of SCC. In initiating a comprehensive refurbishment program, a strategy was developed to identify key points and objectives.

  12. Dan jiang kou hydropower station turbine refurbishment

    NASA Astrophysics Data System (ADS)

    Zhang, R. Y.; Nie, S. Q.; Bazin, D.; Cheng, J. H.

    2012-11-01

    Dan jiangkou hydropower station refurbished project, isan important project of Chinese refurbishment market. Tianjin Alstom Hydro Co., ltd won this contract by right of good performance and design technology,Its design took into account all the constraints linked to the existing frame. It results in a specific and highly advanced shape.The objective of this paper is to introduce the successful turbine hydraulic design, model test and mechanical design of Dan jiangkou project; and also analyze the cavitation phenomena occurred on runner band surface of Unit 4 after putting into commercial operation. These technology and feedback shall be a good reference and experience for other similar projects

  13. Waste drum refurbishment

    SciTech Connect

    Whitmill, L.J.

    1996-10-18

    Low-carbon steel, radioactive waste containers (55-gallon drums) are experiencing degradation due to moisture and temperature fluctuations. With thousands of these containers currently in use; drum refurbishment becomes a significant issue for the taxpayer and stockholders. This drum refurbishment is a non-intrusive, portable process costing between 1/2 and 1/25 the cost of repackaging, depending on the severity of degradation. At the INEL alone, there are an estimated 9,000 drums earmarked for repackaging. Refurbishing drums rather than repackaging can save up to $45,000,000 at the INEL. Based on current but ever changing WIPP Waste Acceptance Criteria (WAC), this drum refurbishment process will restore drums to a WIPP acceptable condition plus; drums with up to 40% thinning o the wall can be refurbished to meet performance test requirements for DOT 7A Type A packaging. A refurbished drum provides a tough, corrosion resistant, waterproof container with longer storage life and an additional containment barrier. Drums are coated with a high-pressure spray copolymer material approximately .045 inches thick. Increase in internal drum temperature can be held to less than 15 F. Application can be performed hands-on or the equipment is readily adaptable and controllable for remote operations. The material dries to touch in seconds, is fully cured in 48 hours and has a service temperature of {minus}60 to 500 F. Drums can be coated with little or no surface preparation. This research was performed on drums however research results indicate the coating is very versatile and compatible with most any material and geometry. It could be used to provide abrasion resistance, corrosion protection and waterproofing to almost anything.

  14. Surface purity control during XMASS detector refurbishment

    SciTech Connect

    Kobayashi, Kazuyoshi

    2015-08-17

    The XMASS project aims at detecting dark matter, pp and {sup 7}Be solar neutrinos, and neutrino less double beta decay using large volume of pure liquid xenon. The first physics target of the XMASS project is to detect dark matter with 835 kg liquid xenon. After the commissioning runs, XMASS detector was refurbished to minimize the background contribution mainly from PMT sealing material and we restarted data taking in November 2013. We report how we control surface purity, especially how we prevent radon daughter accumulation on the detector copper surface, during XMASS detector refurbishment. The result and future plan of XMASS are also reported.

  15. LANDSAT-D refurbishment study

    NASA Technical Reports Server (NTRS)

    1980-01-01

    Requirements for refurbishing the LANDSAT-D spacecraft after its recovery from orbit at the end of a 3-year mission in order to reuse the spacecraft on a second 3-year mission were studied. A schedule of the time required for the refurbishment including the procurement cycle for long lead-time items is developed. The costs of refurbishing and of procuring an entirely new LANDSAT-D spacecraft are compared.

  16. Innovative Solutions for Energetic Refurbishment of Historic Brick Buildings

    NASA Astrophysics Data System (ADS)

    Zagorskas, Jurgis; Burinskienė, Marija; Paliulis, Gražvydas Mykolas; Venckauskaitė, Jūratė

    Building standards for energy effectiveness are increasing constantly and market follows these changes by construction of new buildings in accordance with standards and refurbishment of existing housing stock. Comprehensive trends of European construction market show tremendous increase in building retrofit works. It can be predicted that after this decade more than half of construction works in European cities will be taking place in existing buildings, pushing the construction of new buildings to the less important role. Such a growth in building refurbishment works is creating a demand for suitable materials, retrofitting techniques and research. The differences between refurbishment of new-build projects and historical or valuable buildings are insufficiently recognized—mostly the buildings without further cultural preservation requirements are studied. This article covers the theme of refurbishment measures in the historical buildings—the specific measures like inside insulation which is allowed due to the valuable façade or other heritage preservation requirements. An overview of other innovative methods for energy saving in existing buildings and their potential is given.

  17. Energetic Refurbishment of Historic Brick Buildings: Problems and Opportunities

    NASA Astrophysics Data System (ADS)

    Zagorskas, Jurgis; Paliulis, Gražvydas Mykolas; Burinskienė, Marija; Venckauskaitė, Jūratė

    2013-12-01

    Building standards for energy effectiveness are increasing constantly and the market follows these changes by constructing new buildings in accordance with standards and refurbishment of the existing housing stock. Comprehensive trends in European construction market show tremendous increase in building retrofit works. It can be predicted that after the end of this decade, more than half of the construction works in European cities will be taking place in existing buildings, pushing the construction of new buildings to a less important role. Such a growth in building refurbishment works is creating a demand for suitable materials, retrofitting techniques and research. The differences between refurbishment of new-build projects and historical or valuable buildings are insufficiently recognized - mostly the buildings without further cultural preservation requirements are studied. This article covers the theme of refurbishment measures in historical buildings - the specific measures like inside insulation which are allowed due to the valuable façade or other heritage preservation requirements. An overview of other innovative methods for energy saving in existing buildings and their potential is given.

  18. Teaching and Learning Spaces; Refurbishment of the W. K. Hancock Science Library at the Australian National University 2011

    ERIC Educational Resources Information Center

    McNamara, Paul

    2012-01-01

    Two floors of the W. K. Hancock Library at the Australian National University (ANU) were refurbished in 2011 as part of a cooperative project between the library and the College of Science. The refurbishment, costing $5 million, was part of a much larger exercise involving the construction of four new science buildings around the Hancock Library.…

  19. Space Telescope maintenance and refurbishment

    NASA Technical Reports Server (NTRS)

    Trucks, H. F.

    1983-01-01

    The Space Telescope (ST) represents a new concept regarding spaceborne astronomical observatories. Maintenance crews will be brought to the orbital worksite to make repairs and replace scientific instruments. For major overhauls the telescope can be temporarily returned to earth with the aid of the Shuttle. It will, thus, be possible to conduct astronomical studies with the ST for two decades or more. The five first-generation scientific instruments used with the ST include a wide field/planetary camera, a faint object camera, a faint object spectrograph, a high resolution spectrograph, and a high speed photometer. Attention is given to the optical telescope assembly, the support systems module, aspects of mission and science operations, unscheduled maintenance, contingency orbital maintenance, planned on-orbit maintenance, ground maintenance, ground refurbishment, and ground logistics.

  20. The refurbished Z facility : capabilities and recent experiments.

    SciTech Connect

    Leeper, Ramon Joe; Long, Finis W.; Leifeste, Gordon T.; Hall, Clint Allen; Atherton, Briggs W.; Herrmann, Mark C.; Donovan, Guy Louis; McKee, G. Randall; Weinbrecht, Edward A.; Porter, John Larry, Jr.; Mehlhorn, Thomas Alan; Cuneo, Michael Edward; Struve, Kenneth William; Stygar, William A.; Kiefer, Mark Linden; Matzen, Maurice Keith; Schneider, Larry X.

    2008-09-01

    The Z Refurbishment Project was completed in September 2007. Prior to the shutdown of the Z facility in July 2006 to install the new hardware, it provided currents of {le} 20 MA to produce energetic, intense X-ray sources ({approx} 1.6 MJ, > 200 TW) for performing high energy density science experiments and to produce high magnetic fields and pressures for performing dynamic material property experiments. The refurbishment project doubled the stored energy within the existing tank structure and replaced older components with modern, conventional technology and systems that were designed to drive both short-pulse Z-pinch implosions and long-pulse dynamic material property experiments. The project goals were to increase the delivered current for additional performance capability, improve overall precision and pulse shape flexibility for better reproducibility and data quality, and provide the capacity to perform more shots. Experiments over the past year have been devoted to bringing the facility up to full operating capabilities and implementing a refurbished suite of diagnostics. In addition, we have enhanced our X-ray backlighting diagnostics through the addition of a two-frame capability to the Z-Beamlet system and the addition of a high power laser (Z-Petawatt). In this paper, we will summarize the changes made to the Z facility, highlight the new capabilities, and discuss the results of some of the early experiments.

  1. Field refurbishment of recoverable sounding rocket payloads.

    NASA Technical Reports Server (NTRS)

    Needleman, H. C.; Tackett, C. D.

    1973-01-01

    Sounding rocket payload field refurbishment has been shown to be an effective means for obtaining additional scientific data with substantial time and monetary savings. In a recent campaign three successful missions were flown using two payloads. Field refurbished hardware from two previously flown and recovered payloads were field integrated to form a third payload. Although this operational method may result in compromises in the refurbished system, it allows for quick turn around when the mission requires it. This paper describes the recent success of this approach with the Dudley Observatory Nike-Apache micrometeorite collection experiments launched from Kiruna, Sweden, in October 1972.

  2. The Oak Ridge Isochronous Cyclotron Refurbishment Project

    SciTech Connect

    Mendez, II, Anthony J; Ball, James B; Dowling, Darryl T; Mosko, Sigmund W; Tatum, B Alan

    2011-01-01

    The Oak Ridge Isochronous Cyclotron (ORIC) has been in operation for nearly fifty years at the Oak Ridge National Laboratory (ORNL). Presently, it serves as the driver accelerator for the ORNL Holifield Radioactive Ion Beam Facility (HRIBF), where radioactive ion beams are produced using the Isotope Separation Online (ISOL) technique for post-acceleration by the 25URC tandem electrostatic accelerator. Operability and reliability of ORIC are critical issues for the success of HRIBF and have presented increasingly difficult operational challenges for the facility in recent years. In February 2010, a trim coil failure rendered ORIC inoperable for several months. This presented HRIBF with the opportunity to undertake various repairs and maintenance upgrades aimed at restoring the full functionality of ORIC and improving the reliability to a level better than what had been typical over the previous decade. In this paper, we present details of these efforts, including the replacement of the entire trim coil set and measurements of their radial field profile. Comparison of measurements and operating tune parameters with setup code predictions will also be presented.

  3. Refurbishment program of HANARO control computer system

    SciTech Connect

    Kim, H. K.; Choe, Y. S.; Lee, M. W.; Doo, S. K.; Jung, H. S.

    2012-07-01

    HANARO, an open-tank-in-pool type research reactor with 30 MW thermal power, achieved its first criticality in 1995. The programmable controller system MLC (Multi Loop Controller) manufactured by MOORE has been used to control and regulate HANARO since 1995. We made a plan to replace the control computer because the system supplier no longer provided technical support and thus no spare parts were available. Aged and obsolete equipment and the shortage of spare parts supply could have caused great problems. The first consideration for a replacement of the control computer dates back to 2007. The supplier did not produce the components of MLC so that this system would no longer be guaranteed. We established the upgrade and refurbishment program in 2009 so as to keep HANARO up to date in terms of safety. We designed the new control computer system that would replace MLC. The new computer system is HCCS (HANARO Control Computer System). The refurbishing activity is in progress and will finish in 2013. The goal of the refurbishment program is a functional replacement of the reactor control system in consideration of suitable interfaces, compliance with no special outage for installation and commissioning, and no change of the well-proved operation philosophy. HCCS is a DCS (Discrete Control System) using PLC manufactured by RTP. To enhance the reliability, we adapt a triple processor system, double I/O system and hot swapping function. This paper describes the refurbishment program of the HANARO control system including the design requirements of HCCS. (authors)

  4. Steam generators secondary side chemical cleaning at Point Lepreau using the Siemens high temperature process

    SciTech Connect

    Verma, K.; MacNeil, C.; Odar, S.; Kuhnke, K.

    1997-02-01

    This paper describes the chemical cleaning of the four steam generators at the Point Lepreau facility, which was accomplished as a part of a normal service outage. The steam generators had been in service for twelve years. Sludge samples showed the main elements were Fe, P and Na, with minor amounts of Ca, Mg, Mn, Cr, Zn, Cl, Cu, Ni, Ti, Si, and Pb, 90% in the form of Magnetite, substantial phosphate, and trace amounts of silicates. The steam generators were experiencing partial blockage of broached holes in the TSPs, and corrosion on tube ODs in the form of pitting and wastage. In addition heat transfer was clearly deteriorating. More than 1000 kg of magnetite and 124 kg of salts were removed from the four steam generators.

  5. Water electrolysis system refurbishment and testing

    NASA Technical Reports Server (NTRS)

    Greenough, B. M.

    1972-01-01

    The electrolytic oxygen generator for the back-up water electrolysis system in a 90-day manned test was refurbished, improved and subjected to a 182-day bench test. The performance of the system during the test demonstrated the soundness of the basic electrolysis concept, the high development status of the automatic controls which allowed completely hands-off operation, and the capability for orbital operation. Some design improvements are indicated.

  6. Evaluation of three refurbished Guralp CMG-3TB seismometers.

    SciTech Connect

    Hart, Darren M.; Merchant, Bion J.

    2014-05-01

    The overall objective of testing the Guralp CMG-3TB refurbished seismometers is to determine whether or not the refurbished sensors exhibit better data quality and require less maintenance when deployed than the original Guralp CMG-3TBs. SNL will test these 3 refurbished Guralps to verify performance specifications. The specifications that will be evaluated are sensitivity, bandwidth, self-noise, output impedance, clip-level, dynamic range over application passband, verify mathematical response and calibration response parameters for amplitude and phase.

  7. United Space Alliance LLC Parachute Refurbishment Facility Model

    NASA Technical Reports Server (NTRS)

    Esser, Valerie; Pessaro, Martha; Young, Angela

    2007-01-01

    The Parachute Refurbishment Facility Model was created to reflect the flow of hardware through the facility using anticipated start and delivery times from a project level IV schedule. Distributions for task times were built using historical build data for SFOC work and new data generated for CLV/ARES task times. The model currently processes 633 line items from 14 SFOC builds for flight readiness, 16 SFOC builds returning from flight for defoul, wash, and dry operations, 12 builds for CLV manufacturing operations, and 1 ARES 1X build. Modeling the planned workflow through the PRF is providing a reliable way to predict the capability of the facility as well as the manpower resource need. Creating a real world process allows for real world problems to be identified and potential workarounds to be implemented in a safe, simulated world before taking it to the next step, implementation in the real world.

  8. SST-1 Refurbishment Progress: an Update

    NASA Astrophysics Data System (ADS)

    Subrata, Pradhan; SST-1 Mission Team

    2013-02-01

    Refurbishment of steady state tokamak (SST-1) primarily focused at addressing the issues and bottle-necks involving various subsystems of SST-1 as observed during earlier commissioning attempts, have progressed significantly. Under the refurbishment spectrum, all joints in the superconducting magnet system have been re-fabricated as low DC leak tight joint resistances, all toroidal field (TF) magnets have been equipped with 5 K radiation shields on the inner side and successfully tested for their rated parameters in cold under nominal currents, all vessel sectors and modules have been baked and tested under representative conditions, supporting helium and nitrogen cryogenic facilities have been made > 99% reliable in various envisaged operating scenarios of SST-1. The reassemblies of the critical subsystems of the SST-1 machine shell have progressed aggressively and are nearing completion. Auxiliaries such as the baking facility for the vacuum vessel and first wall components, current leads assembly distributions, synchronized timing system, reliable data acquisition and plasma control systems as well as essential diagnostics have also been readied towards the first plasma. A detailed engineering validation of the assembled SST-1 machine shell including field error measurements has been planned prior to first plasma attempts.

  9. Life analysis of restored and refurbished bearings

    NASA Technical Reports Server (NTRS)

    Coy, J. J.; Zaretsky, E. V.; Cowgill, G. R.

    1977-01-01

    An analysis of the potential life of refurbished and restored bearings was performed. The sensitivity of 10-percent life and mean-time-between-failure to the effects of cumulative fatigue damage and the amount of stressed volume removed in the restoration process were examined. A modified Lundberg-Palmgren theory was used to predict that the expected 10-percent life of a restored bearing, which is dependent on the previous service time and the volume of material removed from the race surfaces, can be between 74 and 100 percent of the new bearing life. Using renewal theory, it is found that the mean time between failure ranged from 90 to 100 percent of that for a new bearing.

  10. System for refurbishing and processing parachutes

    NASA Technical Reports Server (NTRS)

    Crowell, Russell T. (Inventor)

    1980-01-01

    A system and method for refurbishing and processing parachutes is disclosed including an overhead monorail conveyor system on which the parachute is suspended for horizontal conveyance. The parachute is first suspended in partially open tented configuration wherein open inspection of the canopy is permitted to remove debris and inspect all areas. Following inspection, the parachute is transported by the monorail conveyor to a washing and drying station with the parachute canopy mounted on the conveyor in a systematic arrangement which permits water and air to pass through the ribbon-like material of the canopy. Following drying of the parachute, the parachute is conveyed into an interior space where it is finally inspected and removed from the monorail conveyor and laid upon a table for folding. Following folding operations, the parachute is once again mounted on the conveyor in an elongated horizontal configuration and conveyed to a packing area for stowing the parachute in a deployment bag.

  11. Method for refurbishing and processing parachutes

    NASA Technical Reports Server (NTRS)

    Crowell, R. T. (Inventor)

    1982-01-01

    A system and method for refurbishing and processing parachutes is discussed including an overhead monorail conveyor system on which the parachute is suspended for horizontal conveyance. The parachute is first suspended in partially open tented configuration wherein open inspection of the canopy is permitted to remove debris and inspect all areas. Following inspection, the parachute is transported by the monorail conveyor to a washing and drying station with the parachute canopy mounted on the conveyor ina systematic arrangement which permits water and air to pass through the ribbonlike material of the canopy. Following drying of the parachute, the parachute is conveyed into an interior space where it is finally inspected and removed from the monorail conveyor and laid upon a table for folding.

  12. 77 FR 6122 - Providing Refurbishment Services to Federal Agencies

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-02-07

    ... process for disposing and recycling of failed equipment. Have all facilities in your recycling and... refurbishment services, including those developed specifically for recycling facilities (e.g., R2 and...

  13. Source Recertification, Refurbishment, and Transfer Logistics

    SciTech Connect

    Gastelum, Zoe N.; Duckworth, Leesa L.; Greenfield, Bryce A.; Doll, Stephanie R.

    2013-09-01

    The 2012 Gap Analysis of Department of Energy Radiological Sealed Sources, Standards, and Materials for Safeguards Technology Development [1] report, and the subsequent Reconciliation of Source Needs and Surpluses across the U.S. Department of Energy National Laboratory Complex [2] report, resulted in the identification of 33 requests for nuclear or radiological sealed sources for which there was potentially available, suitable material from within the U.S. Department of Energy (DOE) complex to fill the source need. Available, suitable material was defined by DOE laboratories as material slated for excess, or that required recertification or refurbishment before being used for safeguards technology development. This report begins by outlining the logistical considerations required for the shipment of nuclear and radiological materials between DOE laboratories. Then, because of the limited need for transfer of matching sources, the report also offers considerations for an alternative approach – the shipment of safeguards equipment between DOE laboratories or technology testing centers. Finally, this report addresses repackaging needs for the two source requests for which there was available, suitable material within the DOE complex.

  14. RSRM Case Acceptance and Refurbishment Requirements

    NASA Technical Reports Server (NTRS)

    Brinkerhoff, Gary Z.

    2003-01-01

    The RSRM (Reuseable Solid Rocket Motor) Program has been developed and implemented to support manned flight space travel. The Space Shuttle Vehicle utilizes two SRBs (Solid Rocket Boosters) to assist during the launch sequence and achieve the predefined orbit and mission objectives. A critical feature of this program involves post- flight SRB retrieval, disassembly and reuse of case structural components to manufacture future RSRM motors. To ensure these components can be safely reused, inspection criteria based on dimensional, structural and fracture requirements, has been established in the form of Engineering specifications and drawings. These criteria originated from actual hardware testing (both subscale and full scale) coupled with conventional Engineering hand calculations and computerized Finite Element Analyses (FEA). The intent of this paper is to provide an overview of the RSRM Case component refurbishment requirements and the associated case hardware inspection and evaluation processes that has been established to satisfy these requirements. Many of these processes have been recently upgraded to comply with environmental regulations, obsolescence concerns and technological advancements. Qualification of these process changes has been closely monitored and documented through test plans and reports.

  15. LANSCE Drift Tube Linac Water Control System Refurbishment

    SciTech Connect

    Marroquin, Pilar S.

    2011-01-01

    There are several refurbishment projects underway at the Los Alamos National Laboratory LANSCE linear accelerator. Systems involved are: RF, water cooling, networks, diagnostics, timing, controls, etc. The Drift Tube Linac (DTL) portion of the accelerator consists of four DTL tanks, each with three independent water control systems. The systems are about 40 years old, use outdated and non-replaceable equipment and NIM bin control modules, are beyond their design life and provide unstable temperature control. Insufficient instrumentation and documentation further complicate efforts at maintaining system performance. Detailed design of the replacement cooling systems is currently in progress. Previous design experience on the SNS accelerator water cooling systems will be leveraged, see the SNS DTL FDR. Plans call for replacement of water piping, manifolds, pumps, valves, mix tanks, instrumentation (flow, pressure and temperature) and control system hardware and software. This presentation will focus on the control system design with specific attention on planned use of the National Instruments Compact RIO platform with the Experimental Physics and Industrial Control system (EPICS) software toolkit.

  16. INFORMATION: Audit Report on The Office of Secure Transportation DC-9 Aircraft Refurbishment

    SciTech Connect

    2009-05-01

    The National Nuclear Security Administration's (NNSA) Office of Secure Transportation (OST) maintains a fleet of seven aircraft to transport sensitive items, equipment and security personnel. Based on increasing requirements for transporting components and security personnel, OST decided to add a heavy transport aircraft to meet the Department's weapons surety and emergency response missions. In 2004, as a replacement following the sale of a portion of its fleet, OST acquired a DC-9 cargo aircraft that had been excessed by the U.S. military. Prior to integrating the DC-9 into its fleet, NNSA ordered a refurbishment of the aircraft. This refurbishment project was to permit the aircraft to be certified to civil air standards so that it could transport passengers for site visits, training and other travel. The NNSA Service Center (Service Center) awarded a contract for the refurbishment of the aircraft in December 2004. In recent years, the Office of Inspector General has addressed a number of issues relating to the Department's aircraft management activities and services. As part of our ongoing review process and because of the national security importance of its fleet of aircraft, we conducted this review to determine whether OST had an effective and efficient aviation management program.

  17. Four rigs refurbished for West Africa drilling

    SciTech Connect

    Not Available

    1991-06-10

    In April and May 1990, Shell Petroleum Development Co. of Nigeria Ltd. awarded Noble Drilling West Africa Inc. four separate contracts to drill oil and gas wells in the inland waterways of Nigeria. The contracted rigs included a shallow water jack up, the NN-1, and three posted barges, the Gene Rosser, the Chuck Syring, and the Lewis Dugger. The jack up was built in 1978, and the three posted barges are 1980s vintage. Three of the rigs have been idle for a number of years. The Shell Nigeria contracts required major modifications to the rigs before putting them into international service. Noble replaced or refurbished all major pieces of equipment in the drilling, power, and service systems on the rigs. Rig crews serviced all other equipment. A significant amount of general service piping and electrical wiring was replaced. Each rig also required additional motor control centers to support the new drilling and mud processing equipment. Alfa-Laval waste-heat water desalination plants and new sewage treatment units were installed on all four rigs. Because of the tidal variances and high silt conditions expected in the African waterways, all engine cooling systems were converted from heat exchangers to radiators. Rotary tables were made common on all rigs at 37 1/2 in. Noble had all traveling equipment completely inspected and modified as necessary. Strict attention was paid to certification and documentation of all equipment. Safety upgrades conformed to both Shell and Noble standards. Fire and gas detection systems were installed throughout each rig. Water and foam deluge systems were installed in the wellhead areas, and new foam systems and monitors were installed on the helldecks.

  18. Refurbishment of the Jet Propulsion Laboratory's Large Space Simulator

    NASA Technical Reports Server (NTRS)

    Harrell, J.; Johnson, K.

    1993-01-01

    The JPL large space simulator has recently undergone a major refurbishment to restore and enhance its capabilities to provide high fidelity space simulation. The nearly completed refurbishment has included upgrading the vacuum pumping system by replacing old oil diffusion pumps with new cryogenic and turbomolecular pumps; modernizing the entire control system to utilize computerized, distributed control technology; replacing the Xenon arc lamp power supplies with new upgraded units; refinishing the primary collimating mirror; and replacing the existing integrating lens unit and the fused quartz penetration window.

  19. Evaluation of pressurized water cleaning systems for hardware refurbishment

    NASA Technical Reports Server (NTRS)

    Dillard, Terry W.; Deweese, Charles D.; Hoppe, David T.; Vickers, John H.; Swenson, Gary J.; Hutchens, Dale E.

    1995-01-01

    Historically, refurbishment processes for RSRM motor cases and components have employed environmentally harmful materials. Specifically, vapor degreasing processes consume and emit large amounts of ozone depleting compounds. This program evaluates the use of pressurized water cleaning systems as a replacement for the vapor degreasing process. Tests have been conducted to determine if high pressure water washing, without any form of additive cleaner, is a viable candidate for replacing vapor degreasing processes. This paper discusses the findings thus far of Engineering Test Plan - 1168 (ETP-1168), 'Evaluation of Pressurized Water Cleaning Systems for Hardware Refurbishment.'

  20. Refurbishment and Automation of the Thermal/Vacuum Facilities at the Goddard Space Flight Center

    NASA Technical Reports Server (NTRS)

    Donohue, John T.; Johnson, Chris; Ogden, Rick; Sushon, Janet

    1998-01-01

    The thermal/vacuum facilities located at the Goddard Space Flight Center (GSFC) have supported both manned and unmanned space flight since the 1960s. Of the 11 facilities, currently 10 of the systems are scheduled for refurbishment and/or replacement as part of a 5-year implementation. Expected return on investment includes the reduction in test schedules, improvements in the safety of facility operations, reduction in the complexity of a test and the reduction in personnel support required for a test. Additionally, GSFC will become a global resource renowned for expertise in thermal engineering, mechanical engineering and for the automation of thermal/vacuum facilities and thermal/vacuum tests. Automation of the thermal/vacuum facilities includes the utilization of Programmable Logic Controllers (PLCs) and the use of Supervisory Control and Data Acquisition (SCADA) systems. These components allow the computer control and automation of mechanical components such as valves and pumps. In some cases, the chamber and chamber shroud require complete replacement while others require only mechanical component retrofit or replacement. The project of refurbishment and automation began in 1996 and has resulted in the computer control of one Facility (Facility #225) and the integration of electronically controlled devices and PLCs within several other facilities. Facility 225 has been successfully controlled by PLC and SCADA for over one year. Insignificant anomalies have occurred and were resolved with minimal impact to testing and operations. The amount of work remaining to be performed will occur over the next four to five years. Fiscal year 1998 includes the complete refurbishment of one facility, computer control of the thermal systems in two facilities, implementation of SCADA and PLC systems to support multiple facilities and the implementation of a Database server to allow efficient test management and data analysis.

  1. REMOTE REFURBISHMENT OF THE METALLOGRAPHY PREPARATION BOX AT THE INL

    SciTech Connect

    Adam B. Robinson; R. Paul Lind

    2010-09-01

    One of the most utilized hot cell capabilities at the Idaho National Laboratory is referred to as the containment box. This is where all destructive examination samples are prepared for analysis. This one window box is contained within the much larger Hot Fuels Examination Facility which consists of a 21x10x8 meter hot cell with an inert argon atmosphere. The refurbishment of this box entailed removing of all sample preparation equipment and support systems, as well as the design and installation of new preparation equipment. The new equipment consists of low and high speed saws, grinding and polishing equipment, water recirculation systems, and sample storage units. This paper includes the details of this refurbishment.

  2. BIM applied in historical building documentation and refurbishing

    NASA Astrophysics Data System (ADS)

    Cheng, H.-M.; Yang, W.-B.; Yen, Y.-N.

    2015-08-01

    Historical building conservation raises two important issues which are documentation and refurbishing. For the recording and documentation, we already have developed 3d laser scanner and such photogrammetry technology those represent a freeze object of virtual reality by digital documentation. On the other hand, the refurbished engineering of historic building is a challenge for conservation heritage which are not only reconstructing the damage part but also restoring tangible cultural heritage. 3D digital cultural heritage models has become a topic of great interest in recent years. One reason for this is the more widespread use of laser scanning and photogrammetry for recording cultural heritage sites. These technologies have made it possible to efficiently and accurately record complex structures remotely that would not have been possible with previous survey methods. In addition to these developments, digital information systems are evolving for the presentation, analysis and archival of heritage documentation.

  3. Refurbishment of the CASSIS code for channeling simulations

    NASA Astrophysics Data System (ADS)

    Kling, A.

    2012-02-01

    Channeling is a powerful method for the investigation of the properties of crystalline materials (e.g. lattice site location, defect structures, etc.). More than a decade ago the program code CASSIS has been developed to extend the possible simulation of channeling phenomena to non-cubic crystal lattices, high foreign atom concentrations and PIXE-channeling. Due to the rapid progress in computer technology it is necessary to review and refurbish the existing code by substituting calculation procedures by more sophisticated and more precise ones. Another topic addressed during this refurbishment was the lack of user-friendliness of the old code. The introduction of a simplified input scheme and automatic procedures for the calculation of necessary secondary inputs resolved this situation. As an example and demonstration of possible applications a detailed large-dimension 2-D scan of silicon is presented and discussed.

  4. Refurbishment of an Analytical Laboratory Hot Cell Facility

    SciTech Connect

    Rosenberg, K.E.; Henslee, S.P.; Michelbacher, J.A.; Coleman, R.M.

    1996-08-01

    An Analytical Laboratory Hot Cell (ALHC) Facility at Argonne National Laboratory-West (ANL-W) was in service for nearly thirty years. In order to comply with DOE regulations governing such facilities and meet ANL-W programmatic requirements, a major refurbishment effort was undertaken. To place the facility in compliance with current regulations, all penetrations within the facility were sealed, the ventilation system was redesigned, upgraded and replaced, the master-slave manipulators were replaced, the hot cell windows were removed, refurbished, and reinstalled, all hot cell utilities were replaced, a lead-shielded glovebox housing an Inductive Coupled Plasma - Atomic Emission Spectrometer (ICP-AES) System was interfaced with the hot cells, and a new CO{sub 2} fire suppression system and other ALHC support equipment were installed.

  5. Refurbishment and Automation of Thermal Vacuum Facilities at NASA/GSFC

    NASA Technical Reports Server (NTRS)

    Dunn, Jamie; Gomez, Carlos; Donohue, John; Johnson, Chris; Palmer, John; Sushon, Janet

    1998-01-01

    The thermal vacuum facilities located at the Goddard Space Flight Center (GSFC) have supported both manned and unmanned space flight since the 1960s. Of the eleven facilities, currently ten of the systems are scheduled for refurbishment or replacement as part of a five-year implementation. Expected return on investment includes the reduction in test schedules, improvements in safety of facility operations, and reduction in the personnel support required for a test. Additionally, GSFC will become a global resource renowned for expertise in thermal engineering, mechanical engineering, and for the automation of thermal vacuum facilities and tests. Automation of the thermal vacuum facilities includes the utilization of Programmable Logic Controllers (PLCs), the use of Supervisory Control and Data Acquisition (SCADA) systems, and the development of a centralized Test Data Management System. These components allow the computer control and automation of mechanical components such as valves and pumps. The project of refurbishment and automation began in 1996 and has resulted in complete computer control of one facility (Facility 281), and the integration of electronically controlled devices and PLCs in multiple others.

  6. Refurbishment and Automation of Thermal Vacuum Facilities at NASA/GSFC

    NASA Technical Reports Server (NTRS)

    Dunn, Jamie; Gomez, Carlos; Donohue, John; Johnson, Chris; Palmer, John; Sushon, Janet

    1999-01-01

    The thermal vacuum facilities located at the Goddard Space Flight Center (GSFC) have supported both manned and unmanned space flight since the 1960s. Of the eleven facilities, currently ten of the systems are scheduled for refurbishment or replacement as part of a five-year implementation. Expected return on investment includes the reduction in test schedules, improvements in safety of facility operations, and reduction in the personnel support required for a test. Additionally, GSFC will become a global resource renowned for expertise in thermal engineering, mechanical engineering, and for the automation of thermal vacuum facilities and tests. Automation of the thermal vacuum facilities includes the utilization of Programmable Logic Controllers (PLCs), the use of Supervisory Control and Data Acquisition (SCADA) systems, and the development of a centralized Test Data Management System. These components allow the computer control and automation of mechanical components such as valves and pumps. The project of refurbishment and automation began in 1996 and has resulted in complete computer control of one facility (Facility 281), and the integration of electronically controlled devices and PLCs in multiple others.

  7. Design of multiple-shell gas nozzles for refurbished Z.

    SciTech Connect

    Giuliani, J. L.; Waisman, Eduardo Mario; Velikovich, Aleksandr Lazarevich; Madden, R.; Thornhill, W.; Ampleford, David J.; Krishnan, Mahadevan; Coleman, P. L.; Cuneo, Michael Edward; Wilson Elliott, Kristi; Coverdale, Christine Anne; Clark, R.; Jones, Brent Manley

    2010-06-01

    This paper presents initial designs of multiple-shell gas puff imploding loads for the refurbished Z generator. The nozzle has three independent drivers for three independent plena. The outer and middle plena may be charged to 250psia whilst the central jet can be charged to 1000psia. 8-cm and 12-cm outer diameter nozzles have been built and tested on the bench. The unique valve design provides a very fast opening, hence the amount of stray gas outside the core nozzle flow is minimized. A similar 8-cm nozzle was characterized earlier using a fiber optic interferometer, but at lower pressures and without the central jet. Those data have been scaled to the higher pressures required for refurbished Z and used to estimate performance. The use of three independent plena allows variation of the pressure (hence mass distribution) in the nozzle flow, allowing optimization of implosion stability and the on-axis mass that most contributes to K-shell emission. Varying the outer/middle mass ratios influences the implosion time and should affect the details of the assembly on axis as well as the radiation physics. Varying the central jet pressure will have a minor effect on implosion dynamics, but a strong effect on pinch conditions and radiation physics. Optimum mass distributions for planned initial Ar shots on refurbished Z are described. Additional interferometer data including the central jet and at higher pressures will also be presented.

  8. Hubble refurbished and ready for release

    NASA Astrophysics Data System (ADS)

    1993-12-01

    The deployment of the solar arrays came at the end of the fifth and final spacewalk of the mission. Story Musgrave and Jeff Hoffman spent seven-hours in the cargo bay fitting new electrical systems and installing covers over the telescope's old magnetometers. The first task was the installation of "SADE", a new ESA- supplied Solar Array Drive Electronics box. The box directs the twin solar panels at the Sun. The astronauts then lent a helping hand to lower the masts holding the solar arrays to their deployment position. Flight controllers decided to crank the masts out manually because of minor trouble with the latches. The next job was the installation of the Goddard High Resolution Spectrograph (GHRS) Redundancy Kit, a device that provides an alternate power and data route for the instrument. The ESA supplied solar blankets rolled off their canisters without incident between 4 and 4h35 a.m. CST (11 and 11h35 a.m. CET). An hour later the new SADE system turned the arrays towards the sun. "It is a tribute to the whole team, from the designers to the astronauts, that everything has gone so well", said Derek Eaton, ESA's HST project manager. "I only hope that the array will look so good when the shuttle returns to the telescope in 1997". The telescope's first set of solar arrays flexed in orbit because of the sudden swing in temperature as the telescope moved in and out of sunlight. The movement, known as jitter, affected the telescope's pointing system and disrupted observations at certain times. Special software compensated largely for the problem but this occupied a large amount of computer memory. The design of the new arrays was modified to eliminate the problem. Eaton said he was "101 per cent" confident that jitter from the arrays would no longer affect the work of the telescope. The deployment of the power-generating wings brought the servicing work to a close. If all goes according to plan, the telescope will return to orbital at 1.08 a.m. CST (8.08 a.m. CET

  9. 40 CFR 1033.640 - Provisions for repowered and refurbished locomotives.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ...) Prior to January 1, 2015, remanufactured Tier 0 switch locomotives that are deemed to be refurbished are... standards. (ii) Beginning January 1, 2015, remanufactured Tier 3 and earlier switch locomotives that are... 3000 hp that are refurbished before January 1, 2015 are subject to the same standards as...

  10. Observing supernova 1987A with the refurbished Hubble Space Telescope.

    PubMed

    France, Kevin; McCray, Richard; Heng, Kevin; Kirshner, Robert P; Challis, Peter; Bouchet, Patrice; Crotts, Arlin; Dwek, Eli; Fransson, Claes; Garnavich, Peter M; Larsson, Josefin; Lawrence, Stephen S; Lundqvist, Peter; Panagia, Nino; Pun, Chun S J; Smith, Nathan; Sollerman, Jesper; Sonneborn, George; Stocke, John T; Wang, Lifan; Wheeler, J Craig

    2010-09-24

    Observations with the Hubble Space Telescope (HST), conducted since 1990, now offer an unprecedented glimpse into fast astrophysical shocks in the young remnant of supernova 1987A. Comparing observations taken in 2010 with the use of the refurbished instruments on HST with data taken in 2004, just before the Space Telescope Imaging Spectrograph failed, we find that the Lyα and Hα lines from shock emission continue to brighten, whereas their maximum velocities continue to decrease. We observe broad, blueshifted Lyα, which we attribute to resonant scattering of photons emitted from hot spots on the equatorial ring. We also detect N v λλ1239, 1243 angstrom line emission, but only to the red of Lyα. The profiles of the N v lines differ markedly from that of Hα, suggesting that the N4+ ions are scattered and accelerated by turbulent electromagnetic fields that isotropize the ions in the collisionless shock. PMID:20813921

  11. Refurbishment of fatigue-cracked generator rotor forgings

    SciTech Connect

    Roberts, B.W.; Zielke, W.; Puri, A.

    1996-12-31

    In a paper presented at the 1994 IJPGC in Phoenix, AZ, TVA discussed the management of a fleet of fourteen generator rotors which had developed cracks in the axial cooling holes under the retaining rings and in the radial cooling holes in the rotor body. The management consisted of establishing the root cause of the crack initiation and propagation, initially establishing the flaw size distribution by eddy-current testing (ECT), performing reinspection at appropriate intervals, preheating the rotor prior to startup, lowering overspeed trip settings to 105%, confirming overspeed trip response by simulation rather than actual overspeed, and maintaining a spare generator rotor. Since the 1994 paper, one of the rotors developed an electrical liability, forcing its removal from service. While a replacement rotor which was on hand resolved the immediate crisis, the long term options were: (1) operate without a spare, (b) procure a new rotor with substantially improved mechanical properties and slightly improved electrical performance, or (c) refurbish the existing forging. After an exhaustive economic analysis, option C was identified as the most cost effective solution. This paper addresses the 43-inch rotor rehabilitation and rewind that has been successfully executed for less than half the cost of a new replacement rotor, without loss in operating flexibility.

  12. Acoustical qualification of Teatro Nuovo in Spoleto before refurbishing works

    NASA Astrophysics Data System (ADS)

    Cocchi, Alessandro; Cesare Consumi, Marco; Shimokura, Ryota

    2001-05-01

    To qualify the acoustical quality of an opera house two different approaches are now available: one is based on responses of qualified listeners (subjective judgments) compared with objective values of selected parameters, the other on comparison tests conducted in suited rooms and on a model of the auditory brain system (preference). In the occasion of the refurbishment of an opera house known for the Two Worlds Festival edited yearly by the Italian Composer G. C. Menotti, a large number of measurements were taken with different techniques, so it is possible to compare the different methods and also the results with some geometrical criterion, based on the most simple rules of musical harmony, now neglected as our attention is attracted to computer simulations, computer aided measurement techniques and similar modern methods. From this work some link between well known acoustical parameters (not known at the time when architects sketched the shape of ancient opera houses) and geometrical criteria (well known at the time when ancient opera houses were built) will be shown.

  13. Seabrook Station service water piping refurbishment using the joint seal method

    SciTech Connect

    Veilleux, J.E.; Kodal, A.S.

    1996-12-31

    The Seabrook Station service water system is fabricated from butt welded, cement lined, carbon steel piping. The service water system fluid is sea water from the Atlantic Ocean and/or potable water from a backup evaporative cooling tower. Joint compound was applied at field welds to seal cement liner crevices. Inspections of 24 inch (61 cm) above ground piping during a refueling outage revealed that the joint compound was degrading in a small percentage of the weld joints. At these locations, sea water was allowed to contact the piping substrate and initiate pitting corrosion. This paper discusses the refurbishment project conducted at Seabrook Station in which Miller Pipeline Corp. AMEX-10/WEKO Seals were installed in safety related service water piping at field weld joint cement liner crevices. This joint seal system utilizes an elastomer boot seal with 6% molybdenum stainless steel circumferential retaining bands on each side of the joint to secure the boot in place. This joint seal design provides a pressure tight seal in order to prevent further sea water intrusion into field weld joints due to degraded joint compound. Isolation of joints from the bulk oxygenated service water flow and high chlorides will arrest any current corrosion and prevent future degradation of these welded joints.

  14. Power Reactant Storage Assembly (PRSA) (Space Shuttle). PRSA hydrogen and oxygen DVT tank refurbishment

    NASA Astrophysics Data System (ADS)

    1993-07-01

    The Power Reactant Storage Assembly (PRSA) liquid hydrogen Development Verification Test (H2 DVT) tank assembly (Beech Aircraft Corporation P/N 15548-0116-1, S/N 07399000SHT0001) and liquid oxygen (O2) DVT tank assembly (Beech Aircraft Corporation P/N 15548-0115-1, S/N 07399000SXT0001) were refurbished by Ball Electro-Optics and Cryogenics Division to provide NASA JSC, Propulsion and Power Division, the capability of performing engineering tests. The refurbishments incorporated the latest flight configuration hardware and avionics changes necessary to make the tanks function like flight articles. This final report summarizes these refurbishment activities. Also included are up-to-date records of the pressure time and cycle histories.

  15. Power Reactant Storage Assembly (PRSA) (Space Shuttle). PRSA hydrogen and oxygen DVT tank refurbishment

    NASA Technical Reports Server (NTRS)

    1993-01-01

    The Power Reactant Storage Assembly (PRSA) liquid hydrogen Development Verification Test (H2 DVT) tank assembly (Beech Aircraft Corporation P/N 15548-0116-1, S/N 07399000SHT0001) and liquid oxygen (O2) DVT tank assembly (Beech Aircraft Corporation P/N 15548-0115-1, S/N 07399000SXT0001) were refurbished by Ball Electro-Optics and Cryogenics Division to provide NASA JSC, Propulsion and Power Division, the capability of performing engineering tests. The refurbishments incorporated the latest flight configuration hardware and avionics changes necessary to make the tanks function like flight articles. This final report summarizes these refurbishment activities. Also included are up-to-date records of the pressure time and cycle histories.

  16. Refurbishment of ballast water system of the gravity base structure - Beryl 'A'

    SciTech Connect

    Seume, K.; Gilchrist, J.M.

    1987-01-01

    The Beryl Alpha Gravity Base Platform has operated satisfactorily for the past 11 years and is expected to stay in operation until the year 2017. The Ballast Water System is a vital part of the platform's oil storage and export equipment. In 1986, during routine pipe inspections in the lower part of the utility shaft, significant defects were discovered which resulted in major refurbishment work. Innovative designs and working procedures were employed for replacement and reinforced grout encasement of line pipe sections. This paper details the important aspects of this refurbishment work.

  17. Refurbishment cost study of the thermal protection system of a space shuttle vehicle, phase 2

    NASA Technical Reports Server (NTRS)

    Haas, D. W.

    1972-01-01

    The labor costs and techniques associated with the refurbishment and maintenance of representative thermal protection system (TPS) components and their attachment concepts suitable for space shuttle application are defined, characterized, and evaluated from the results of an experimental test program. This program consisted of designing selected TPS concepts, fabricating and assembling test hardware, and performing a time and motion study of specific maintenance functions of the test hardware on a full-scale- mockup. Labor requirements and refurbishment techniques, as they relate to the maintenance functions of inspection, repair, removal, and replacement were identified.

  18. A Guide to Energy Efficient Refurbishment. Maintenance and Renewal in Educational Buildings. Building Bulletin 73.

    ERIC Educational Resources Information Center

    Department for Education and Employment, London (England). Architects and Building Branch.

    With little or relatively modest investment, schools being refurbished or undergoing maintenance can make disproportionately large gains in energy efficiency that can also result in large financial savings. This document offers guidance on the selection of appropriate measures that can improve a facility's energy efficiency, depending on the type…

  19. The refurbished 1.3-m Robotically Controlled Telescope at Kitt Peak

    NASA Astrophysics Data System (ADS)

    Gelderman, R.; Guinan, E.; Howell, S.; Mattox, J. R.; McGruder, C. H.; Walter, D. K.; Davis, D. R.; Everett, M.

    2003-05-01

    In 1999, the National Optical Astronomy Observatories (NOAO) announced the opportunity to "assume responsibility for operation of the Kitt Peak 1.3-m telescope." A group of astronomers/educators from institutions across the USA successfully proposed to refurbish and automate the observatory and operate it as the Robotically Controlled Telescope (RCT). The RCT Consortium has been established between Francis Marion University, the Planetary Science Institute, South Carolina State University, Villanova University, and Western Kentucky University to oversee the refurbishment and automation, and operate the telescope to successfully achieve its research and education goals. The RCT was commissioned in 1964 as the Remotely Controlled Telescope and utilized that epoch's computing and communication technology to provide unattended operation from NOAO headquarters in Tucson, about 90 km distant. The original incarnation of the RCT allowed astronomers to gain experience in the remote operation of observatories in order to both develop techniques for operating space-based telescopes and to increase the productivity of ground-based telescopes (Maran 1967 Science 158, 867). While these tests worked as well as could be expected given the technology of the time, the telescope and observatory were refitted in 1969 for classical, attended operations. The second life of the 1.3-m was as a heavily subscribed KPNO visitor facility, first with photoelectric photometers and later as an important testbed for the newest infrared instrumentation. In 1996 the telescope was removed from the list of available KPNO facilities and stood idle until the RCT Consortium hired EOS Technologies, Inc. to refurbish and automate the observatory. In winter 2003 most of the observatory systems have been refurbished and the commissioning has begun. Refurbishment of the RCT has been made possible by NASA grant NAG58762.

  20. WASTE MINIMIZATION ASSESSMENT FOR A MANUFACTURER OF REFURBISHED RAILCAR ASSEMBLIES

    EPA Science Inventory

    The U.S. Environmental Protection Agency (EPA) has funded a pilot project to assist small- and medium-size manufacturers who want to minimize their generation of waste but who lack the expertise to do so. Waste Minimization Assessment Centers (WMACs) were established at selected ...

  1. Lessons Learned During the Refurbishment and Testing of an Observatory After Long-Term Storage

    NASA Technical Reports Server (NTRS)

    Hawk, John; Peabody, Sharon; Stavely, Richard

    2015-01-01

    Thermal Fluids Analysis Workshop (TFAWS) 2015, Silver Spring, MD NCTS 21070-15. This paper addresses the lessons learned during the refurbishment and testing of the thermal control system for a spacecraft which was placed into long-term storage. The DSCOVR (Deep Space Climate Observatory) Observatory (formerly known as Triana) was originally scheduled to launch on the Space Shuttle in 2002. With the Triana spacecraft nearly complete, the mission was canceled and the satellite was abruptly put into storage in 2001. In 2008 the observatory was removed from storage to begin refurbishment and testing. Problems arose associated with hardware that was not currently manufactured, coatings degradation, and a significant lack of documentation. Also addressed is the conversion of the thermal and geometric math models for use with updated thermal analysis software tools.

  2. BEO-Life, a Test and Refurbishment Support for Biological Research Facilities

    NASA Astrophysics Data System (ADS)

    Engeln, I.; Hueser, D.; Reese, C.; Schoenfeld, R.

    Since the ISS commenced its operational phase, the need of ground based test and refurbishment support, facilitating the utilisation of the station and especially its facilities for biological research, becomes increasingly important.. The onboard biological research facilities (e.g. BIOLAB) are designed and built for a life time of 10 years, requiring the regular exchange of the integrated life support systems. The exact conditioning of the atmosphere in these systems plays an important role for the scientific outcome. The composition of the air (O2, N2 and CO2) as well as the humidity and the temperature inside the experiment chambers containing the plants and cell-cultures needs to be adjustable for various types of experiments. Since the various ingredients for a life support system are consumables, which consumption depends on the number of performed experiments, the life support systems needs to be refurbished from time to time. Our contribution to this challenge is BEO- Life, which offers a unique test, refurbishment and qualification environment for maintenance and re-supply for life support systems of the ISS onboard biological facilities. BEO-Life provides the ground support for all these tasks, such as tests, maintenance, verification and procedures. To fulfil the demanding requirements for the automatic and stable conditioning of the life support system, a complex arrangement of pumps, valves, sensors and an electronic system including software with exact control algorithms is provided. Beside the refurbishment activities, BEO-Life will support preliminary ground-based investigations of scientists before utilisation of the ISS biological research facilities, too. In conclusion, we offer a novel service element for the ground-based maintenance of biological research facilities onboard the ISS. This service can be easily adapted to the needs of users for preparatory work.

  3. Refurbishment of SRB aluminum components by walnut hull blast removal of protective coatings

    NASA Technical Reports Server (NTRS)

    Colberg, W. R.; Gordon, G. H.; Jackson, C. H.

    1982-01-01

    A test program was conducted to develop, optimize, and scale up an abrasive blasting procedure was developed for refurbishment of specific SRB components: aft skirt, forward skirt, frustrum, and painted piece parts. Test specimens utilizing 2219 T87 aluminum substrate of varying thicknesses were prepared and blasted at progressively increasing pressures with selected abrasives. Specimens were analyzed for material response. The optimum blasting parameters were determined on panel specimens and verified on a large cylindrical integrated test bed.

  4. Ingham County Geriatric Medical Care Facility solar water-heating system refurbishments. Final technical report

    SciTech Connect

    Not Available

    1983-07-01

    The tasks of the refurbishment of a damaged solar water heating system are outlined. The system is a closed loop, 50% glycol antifreeze system consisting of 14 rows of 6 series manifolds each containing 6 solar collectors connected in parallel for a total of 504 modules. The Wyle Laboratories' test report for the Revere Model 132 flat plate collector is appended. A collector test plan and photographs are also appended. Reference CAPE-2834. (LS)

  5. Refurbishment of a 39 foot thermal vacuum chamber

    NASA Technical Reports Server (NTRS)

    Edwards, Arthur A.

    1994-01-01

    The 39' thermal vacuum chamber at Space Systems/Loral has been used to test numerous spacecraft including those of the GOES, Intelsat, Insat, Superbird, N-Star, NATO and other programs. Ten years ago, the aluminum LN2 shroud experienced serious fatigue failures in the field welded jumper tubing, effectively shutting down the chamber for vacuum testing. The problem was repaired at the time, but new failures began to reappear a few months ago and are now occurring at a rate that suggests that the shroud may again become inoperable. Consequently, Space Systems/Loral is spending in excess of $6 million to replace the shroud and the existing LN2 equipment with a new, state of the art cryogenic system. In May, 1994, a contract was awarded to remove the existing shroud and LN2 pumping system and replace it with a gravity fed shroud and distribution system. Included in the contract are eight skid mounted gaseous nitrogen pumping systems capable of controlling shroud zone temperatures between +150 C and -180 C. The project is scheduled to be completed in April 1995.

  6. A novel method for refurbishing used hot section gas turbine blades

    SciTech Connect

    Kempster, A.; Czech, N.

    1995-01-01

    During the normal operation of a land-based gas turbine, attack will occur of the gas-washed surfaces of the rotating stationary blades in the turbine hot section. This attack and its intensity can be variable depending on the blade`s position in the turbine hot section. This attack will progressively degrade these gas-washed surfaces even if these surfaces have been previously coated with a protective layer. During the service period of the turbine, it will be necessary to refurbish the blades from the hotter section of the turbine. One of the refurbishment steps will be to provide the blades with a suitable replacement coating to afford protection until the next service period. conventional refurbishment techniques used to clean the blade surface rely on abrasive cleaning and/or chemical pickling. These processes may be capable of removing superficial oxidation and any residual coating but are not able consistently to remove the substrate material that has suffered from corrosive attack. It is important that this attached substrate layer be removed completely, otherwise any residual corrosion products, particularly the presence of deeply penetrated sulfides in grain boundaries, could significantly reduce the life of any subsequent coating. The technique described in this paper essentially activates the surface layer of the substrate that is corroded, thus rendering it more easily removed by chemical and physical means. It is possible by this method to remove up to 400 {mu}m of the substrate material and provided that all the corrosion products are contained within this zone, it is demonstrated how this produces a clean unattacked surface that is necessary for any subsequent welding, brazing, or recoating operation.

  7. The T55-L-712 turbine engine compressor housing refurbishment project

    NASA Technical Reports Server (NTRS)

    Leissler, George W.; Darling, Cliff; Gilchrist, George

    1987-01-01

    A study was conducted to access the feasibility of reclaiming T55-L-712 turbine engine compressor housings with an 88 wt % aluminum -- 12 wt % silicon alloy applied by the plasma spray processes. Tensile strength testing was conducted on as-sprayed and thermally cycled test specimens which were plasma sprayed from 0.020 to 0.100 in. Satisfactory tensile strength valves were observed in the as-sprayed tensile specimens. There was essentially no decrease in tensile strength after thermally cycling the tensile specimens.

  8. T55-L-712 turbine engine compressor housing refurbishment-plasma spray project

    NASA Technical Reports Server (NTRS)

    Leissler, George W.; Yuhas, John S.

    1988-01-01

    A study was conducted to assess the feasibility of reclaiming T55-L-712 turbine engine compressor housings with an 88 wt percent aluminum to 12 wt percent silicon alloy applied by a plasma spray process. Tensile strength testing was conducted on as-sprayed and thermally cycled test specimens which were plasma sprayed with 0.020 to 0.100 in. coating thicknesses. Satisfactory tensile strength values were observed in the as-sprayed tensile specimens. There was essentially no decrease in tensile strength after thermally cycling the tensile specimens. Furthermore, compressor housings were plasma sprayed and thermally cycled in a 150-hr engine test and a 200-hr actual flight test during which the turbine engine was operated at a variety of loads, speeds and torques. The plasma sprayed coating system showed no evidence of degradation or delamination from the compressor housings. As a result of these tests, a procedure was designed and developed for the application of an aluminum-silicon alloy in order to reclaim T55-L-712 turbine engine compressor housings.

  9. One laptop per child, local refurbishment or overseas donations? Sustainability assessment of computer supply scenarios for schools in Colombia.

    PubMed

    Streicher-Porte, Martin; Marthaler, Christian; Böni, Heinz; Schluep, Mathias; Camacho, Angel; Hilty, Lorenz M

    2009-08-01

    With the intention of bridging the 'digital divide' many programmes have been launched to provide computers for educational institutions, ranging from refurbishing second hand computers to delivering low cost new computers. The fast and economical provision of large quantities of equipment is one of the many challenges faced by such programmes. If an increase is to be achieved in the sustainability of computer supplies for schools, not only must equipment be provided, but also suitable training and maintenance delivered. Furthermore, appropriate recycling has to be ensured, so that end-of-life equipment can be dealt with properly. This study has evaluated the suitability of three computer supply scenarios to schools in Colombia: (i) 'Colombian refurbishment', -refurbishment of computers donated in Colombia, (ii) 'Overseas refurbishment', -import of computers which were donated and refurbished abroad, and (iii) 'XO Laptop', -purchase of low cost computers manufactured in Korea. The methods applied were: Material Flow Assessment, -to assess the quantities-, Life Cycle Assessment, -to assess the environmental impacts, and the application of the Multiple Attribute Utility Theory, -to analyse, evaluate and compare different scenarios. The most sustainable solution proved to be the local refurbishment of second hand computers of Colombian origin to an appropriate technical standard. The environmental impacts of such practices need to be evaluated carefully, as second hand appliances have to be maintained, require spare parts and sometimes use more energy than newer equipment. Providing schools with second hand computers from overseas and through programmes such as 'One Laptop Per Child' has the disadvantage that the potential for social improvements - such as creation of jobs and local industry involvement - is very low. PMID:19564072

  10. Refurbishment and modification of existing protective shipping packages (for 30-inch UF{sub 6} cylinders) per USDOT specification No. USA-DOT-21PF-1A

    SciTech Connect

    Housholder, W.R.

    1991-12-31

    This paper addresses the refurbishment procedures for existing shipping containers for 30-inch diameter UF{sub 6} cylinders in accordance with DOT Specification 21PF-1 and the criteria used to determine rejection when such packages are unsuitable for refurbishment.

  11. Key points of condenser refurbishment illustrated by our experience on Russian technology nuclear power stations

    SciTech Connect

    Somville, C.

    1998-07-01

    In 1990, the refurbishment of the condensers of the VVER 440 MW LOVIISA 2 Finnish power station was the first reference of GEC ALSTHOM Delas on a Russian type nuclear power station, covering the optimization studies, technical and-economical choices, manufacture and site operations. The current contract for the condenser renovation of the 4 units of the VVER 440 MW PAKS Hungarian power station goes even further through an investment of this company in a local manufacturing installation and a significant participation of the local industry. Their expertise has helped reducing site operation times from 28 days for one condenser of one Loviisa unit, to 26 days for two condensers of one Paks unit. This paper describes the various aspects and the improvements brought for both operations and highlights the technical and economical key advantages of a condenser renovation (quick return on investment, better performances, reliability and life extension of the power station).

  12. Refurbishment and Testing of the 1970's Era LASS Solenoid Coils for JLab's Hall D

    SciTech Connect

    Anumagalla, Ravi; Biallas, George; Brindza, Paul; Carstens, Thomas; Creel, Jonathan; Egiyan, Hovanes; Martin, Floyd; Qiang, Yi; Spiegel, Scot; Stevens, Mark; Wissmann, Mark; Wolin, Elliott

    2012-07-01

    JLab refurbished the LASS1, 1.85 m bore Solenoid, consisting of four superconducting coils to act as the principal analysis magnet for nuclear physics in the newly constructed, Hall D at Jefferson Lab. The coils, built in 1971 at Stanford Linier Accelerator Center and used a second time at the MEGA Experiment at Los Alamos, had electrical shorts and leaks to the insulating vacuum along with deteriorated superinsulation & instrumentation. Root cause diagnosis of the problems and the repair methods are described along with the measures used to qualify the vessels and piping within the Laboratory's Pressure Safety Program (mandated by 10CFR851). The extraordinary refrigerator operational methods used to utilize the obsolete cryogenic apparatus gathered for the off-line, single coil tests are described.

  13. System and method for refurbishing and processing parachutes. [monorial conveyor system

    NASA Technical Reports Server (NTRS)

    Crowell, R. T. (Inventor)

    1980-01-01

    A system and method for refurbishing and processing parachutes is disclosed including an overhead monorail conveyor system on which the parachute is suspended for horizontal conveyance. The parachute is first suspended in a partially opened tented configuration wherein open inspection of the canopy is permitted to remove debris and inspect all areas. Following inspection, the parachute is transported by the monorail conveyor to a washing and drying station with the parachute canopy mounted on the conveyor in a systematic arrangement which permits water and air to pass through the ribbon-like materials of the canopy. Following drying, the chute is conveyed into an interior space where it is finally inspected and removed from the monorial conveyor for folding. The chute is once again mounted on the conveyor and conveyed to a packing area.

  14. Decontamination, Dismantling and Refurbishing of the PETRA Glove Box at the Tritium Laboratory, Karlsruhe

    SciTech Connect

    Caldwell-Nichols, C.J.; Glugla, M.; Doerr, L.; Berndt, U.

    2005-07-15

    The PETRA facility at the Tritium Laboratory Karlsruhe (TLK) has finished its useful life and the glove box and auxiliary systems are being refurbished. During the lifetime of PETRA the glove box became contaminated with a small amount of tritium but the source has not been positively identified. Removing large redundant components would be hazardous as this would require removing the glove box panels and thus exposing the inner surfaces to moist air which would release tritium. Over several months defined amounts of water have been introduced into the glove box daily which has liberated significant quantities of tritium which has subsequently been absorbed by the in-built tritium retention system. This technique has slowly reduced the tritium liberated at each step. The large components, such as a getter bed, catalyst bed and a permeator, have been detritiated as far as possible in-situ in readiness for disposal once it is safe to remove them from the glove box.

  15. Wiltech Component Cleaning and Refurbishment Facility CFC Elimination Plan at NASA Kennedy Space Center

    NASA Technical Reports Server (NTRS)

    Williamson, Steve; Aman, Bob; Aurigema, Andrew; Melendez, Orlando

    1999-01-01

    The Wiltech Component Cleaning & Refurbishment Facility (WT-CCRF) at NASA Kennedy Space Center performs precision cleaning on approximately 200,000 metallic and non metallic components every year. WT-CCRF has developed a CFC elimination plan consisting of aqueous cleaning and verification and an economical dual solvent strategy for alternative solvent solution. Aqueous Verification Methodologies were implemented two years ago on a variety of Ground Support Equipment (GSE) components and sampling equipment. Today, 50% of the current workload is verified using aqueous methods and 90% of the total workload is degreased aqueously using, Zonyl and Brulin surfactants in ultrasonic baths. An additional estimated 20% solvent savings could be achieved if the proposed expanded use of aqueous methods are approved. Aqueous cleaning has shown to be effective, environmentally friendly and economical (i.e.. cost of materials, equipment, facilities and labor).

  16. Preparation for Retrievals from Sellafield Legacy Ponds Installation of the Gantry Refurbishment System

    SciTech Connect

    Ellison, M.

    2008-07-01

    Retrieval of sludge and fuel from the First Generation Magnox Fuel Storage Pond, and its safe long term storage is one of the NDA's top priorities in the UK clean up programme. The plant is currently undergoing a series of major modifications in preparation for the retrievals operations. The most visible example of these modifications is the Gantry Refurbishment System (GRS), a major work platform which has recently been lifted onto the pond long travel girders used by the Skip Handler. This paper describes the design, manufacture, works test, and site installation of this major piece of equipment. The installation lift, involving the use of an 800Te crane was one of the largest lifts undertaken at Sellafield. The GRS is a mobile platform structure which is designed to be pushed or pulled along the long travel girders by the Skip Handler. Its principle function is to provide a safe and shielded working platform from which to undertake refurbishment of the Skip Handler long travel girders and support structure. The potential hazards and consequences resulting from the modification were fully understood and controls were put in place to ensure that the risk of carrying out the work was as low as reasonably practicable. The work was authorised by the NII, Sellafield Nuclear Safety Committee and an independent readiness review panel. Despite less than perfect weather in the run up to the lift, the GRS was successfully and safely lifted onto the pond on 18 October 2006, the culmination of three years of planning, engineering and construction. (authors)

  17. Neutron production in deuterium gas-puff implosions on the refurbished Z accelerator.

    SciTech Connect

    Flicker, Dawn G.; Coverdale, Christine Anne; Velikovich, Aleksandr Lazarevich; Clark, R. W.; Chong, Y. K.; Davis, J.; Giuliani, J. L.

    2010-06-01

    It has been experimentally demonstrated that deuterium gas-puff implosions at >15 MA are powerful sources of fusion neutrons. Analysis of these experiments indicates that a substantial fraction of the obtained DD fusion neutron yields {approx} 3 x 10{sup 13}, about 50%, might have been of thermonuclear origin. The goal of our study is to estimate the scaling of the thermonuclear neutron yield from deuterium gas-puff implosions with higher load currents available after the refurbishment of Z, both in the short-pulse ({approx}100 ns) and in the long-pulse ({approx}300 ns) implosion regimes. We report extensive ID and 2D radiation-hydrodynamic simulations of such implosions. The mechanisms of ion heating to the fusion temperatures of 7-10 keV are essentially the same as used in structured gas-puff loads to generate high Ar K-shell yields: shock thermalization of the implosion kinetic energy and subsequent adiabatic heating of the on-axis plasma. We investigate the role of high-atomic-number gas that can be added to the outer shell to improve both energy coupling of the imploded mass to the generator and energy transfer to the inner part of the load, due to radiative losses that make the outer shell thin. We analyze the effect of imposed axial magnetic field {approx}30-100 kG, which can contribute both to stabilization of the implosion and to Joule heating of the imploded plasma. Our estimates indicate that thermonuclear DD neutron yields approaching 10 are within the reach on refurbished Z.

  18. Solid radioactive waste management facility design for managing CANDU{sup R} 600 MW nuclear generating station re-tube/refurbishment Waste Streams

    SciTech Connect

    Pontikakis, N.; Hopkins, J.; Scott, D.; Bajaj, V.; Nosella, L.

    2007-07-01

    The main design features of the re-tube canisters, waste handling equipment and waste containers designed by Atomic Energy of Canada Limited (AECL{sup R}) and implemented in support of the re-tube/refurbishment activities for Candu 600 MW nuclear generating stations are described in this paper. The re-tube/refurbishment waste characterization and the waste management principles, which form the basis of the design activities, are also briefly outlined. (authors)

  19. Earth Science Instrument Refurbishment, Testing and Recalibration for the Deep Space Climate Observatory (DSCOVR)

    NASA Astrophysics Data System (ADS)

    Smith, R. C.; Lorentz, S. R.; Mobilia, J.; Sawyer, K.; Hertzberg, E.; Demroff, H.; Rice, J. P.

    2011-12-01

    The Deep Space Climate Observer (DSCOVR) mission began in 1998 as Triana, the first Earth observing spacecraft mission to be stationed at the Earth-Sun first Lagrange point. From L1, Triana would image the entire sunlit side of the earth giving unprecedented temporal and spatial coverage of phenomena in Earth's atmosphere and on its surface. Following the environmental testing of the observatory, the mission was placed into stable suspension in November of 2001 while waiting to be manifested on a launch vehicle. Recently, NOAA has become interested in using the now named DSCOVR observatory to replace the aging Advanced Composition Explorer (ACE) spacecraft to provide an early warning for potentially damaging space weather events which can disrupt communications, degrade navigation signals and damage spacecraft and power grids. In addition to the Plasma-Magnetometer (PLASMAG) instrument suite, DSCOVR carried two Earth science instruments. The Earth Poly-Chromatic imaging Camera (EPIC) and the NIST advanced Radiometer (NISTAR). In early 2009, NASA was given direction to remove these two instruments from the DSCOVR spacecraft bus and perform a recalibration of the NISTAR and to perform a refurbishment of the EPIC instrument. This paper will describe these recent efforts to prepare EPIC and NISTAR for launch on the DSCOVR mission.

  20. Saving money on rig refurbishments through foreign trade zones or duty-drawback

    SciTech Connect

    Ward, R.J. Jr.

    1997-02-01

    The recent boom in day rates for rigs capable of drilling in deep water and harsh environments has created a frenzy of rig refurbishment activity in shipyards located in US Gulf states. In most instances, the destination for the rigs upon completion is the US Outer Continental Shelf (USOCS) in the Gulf of Mexico. The problem faced by contractors/operators planning to use US shipyards is that this circumstance has caused difficulty in shielding rigs and their foreign-sourced components from US Customs duties. Under US Customs law, a bona fide exportation requires severance from US commerce and joining to the commerce of some foreign country or, in the case of a vessel supply, a qualifying international voyage. The USOCS does not qualify as an exportation, nor do movements to drilling sites located on it qualify as an international voyage. Described here are two possible solutions to this economic dilemma and an example of how the foreign trade zone solution was applied by Global marine in its plans for upgrading some of its semisubmersible drilling rigs for deepwater USOCS work.

  1. In-Space Repair and Refurbishment of Thermal Protection System Structures for Reusable Launch Vehicles

    NASA Technical Reports Server (NTRS)

    Singh, M.

    2007-01-01

    Advanced repair and refurbishment technologies are critically needed for the thermal protection system of current space transportation systems as well as for future launch and crew return vehicles. There is a history of damage to these systems from impact during ground handling or ice during launch. In addition, there exists the potential for in-orbit damage from micrometeoroid and orbital debris impact as well as different factors (weather, launch acoustics, shearing, etc.) during launch and re-entry. The GRC developed GRABER (Glenn Refractory Adhesive for Bonding and Exterior Repair) material has shown multiuse capability for repair of small cracks and damage in reinforced carbon-carbon (RCC) material. The concept consists of preparing an adhesive paste of desired ceramic with appropriate additives and then applying the paste to the damaged/cracked area of the RCC composites with an adhesive delivery system. The adhesive paste cures at 100-120 C and transforms into a high temperature ceramic during reentry conditions. A number of plasma torch and ArcJet tests were carried out to evaluate the crack repair capability of GRABER materials for Reinforced Carbon-Carbon (RCC) composites. For the large area repair applications, Integrated Systems for Tile and Leading Edge Repair (InSTALER) have been developed and evaluated under various ArcJet testing conditions. In this presentation, performance of the repair materials as applied to RCC is discussed. Additionally, critical in-space repair needs and technical challenges are reviewed.

  2. Refurbishment of uranium hexafluoride cylinder storage yards C-745-K, L, M, N, and P and construction of a new uranium hexafluoride cylinder storage yard (C-745-T) at the Paducah Gaseous Diffusion Plant, Paducah, Kentucky

    SciTech Connect

    1996-07-01

    The Paducah Gaseous Diffusion Plant (PGDP) is a uranium enrichment facility owned by the US Department of Energy (DOE). A residual of the uranium enrichment process is depleted uranium hexafluoride (UF6). Depleted UF6, a solid at ambient temperature, is stored in 32,200 steel cylinders that hold a maximum of 14 tons each. Storage conditions are suboptimal and have resulted in accelerated corrosion of cylinders, increasing the potential for a release of hazardous substances. Consequently, the DOE is proposing refurbishment of certain existing yards and construction of a new storage yard. This environmental assessment (EA) evaluates the impacts of the proposed action and no action and considers alternate sites for the proposed new storage yard. The proposed action includes (1) renovating five existing cylinder yards; (2) constructing a new UF6 storage yard; handling and onsite transport of cylinders among existing yards to accommodate construction; and (4) after refurbishment and construction, restacking of cylinders to meet spacing and inspection requirements. Based on the results of the analysis reported in the EA, DOE has determined that the proposed action is not a major Federal action that would significantly affect the quality of the human environment within the context of the National Environmental Policy Act of 1969. Therefore, DOE is issuing a Finding of No Significant Impact. Additionally, it is reported in this EA that the loss of less than one acre of wetlands at the proposed project site would not be a significant adverse impact.

  3. Shuttle Atlantis Returning to Kennedy Space Center after 10 Month Refurbishment

    NASA Technical Reports Server (NTRS)

    1998-01-01

    The Space Shuttle orbiter Atlantis is seen here in flight on the back of one of NASA's Boeing 747 Shuttle Carrier Aircraft (SCA) as it departs California for the Kennedy Space Center, Florida. Space Shuttles are the main element of America's Space Transportation System and are used for space research and other space applications. The shuttles are the first vehicles capable of being launched into space and returning to Earth on a routine basis. Space Shuttles are used as orbiting laboratories in which scientists and mission specialists conduct a wide variety of scientific experiments. Crews aboard shuttles place satellites in orbit, rendezvous with satellites to carry out repair missions and return them to space, and retrieve satellites and return them to Earth for refurbishment and reuse. Space Shuttles are true aerospace vehicles. They leave Earth and its atmosphere under rocket power provided by three liquid-propellant main engines with two solid-propellant boosters attached plus an external liquid-fuel tank. After their orbital missions, they streak back through the atmosphere and land like airplanes. The returning shuttles, however, land like gliders, without power and on runways. Other rockets can place heavy payloads into orbit, but, they can only be used once. Space Shuttles are designed to be continually reused. When Space Shuttles are used to transport complete scientific laboratories into space, the laboratories remain inside the payload bay throughout the mission. They are then removed after the Space Shuttle returns to Earth and can be reused on future flights. Some of these orbital laboratories, like the Spacelab, provide facilities for several specialists to conduct experiments in such fields as medicine, astronomy, and materials manufacturing. Some types of satellites deployed by Space Shuttles include those involved in environmental and resources protection, astronomy, weather forecasting, navigation, oceanographic studies, and other scientific

  4. Shuttle Atlantis Returning to Kennedy Space Center after 10 Month Refurbishment

    NASA Technical Reports Server (NTRS)

    1998-01-01

    A look-down view on the Space Shuttle orbiter Atlantis piggy-backed on top of one of NASA's Boeing 747 Shuttle Carrier Aircraft (SCA) as it departs California for the Kennedy Space Center, Florida in September 1998. Space Shuttles are the main element of America's Space Transportation System and are used for space research and other space applications. The shuttles are the first vehicles capable of being launched into space and returning to Earth on a routine basis. Space Shuttles are used as orbiting laboratories in which scientists and mission specialists conduct a wide variety of scientific experiments. Crews aboard shuttles place satellites in orbit, rendezvous with satellites to carry out repair missions and return them to space, and retrieve satellites and return them to Earth for refurbishment and reuse. Space Shuttles are true aerospace vehicles. They leave Earth and its atmosphere under rocket power provided by three liquid-propellant main engines with two solid-propellant boosters attached plus an external liquid-fuel tank. After their orbital missions, they streak back through the atmosphere and land like airplanes. The returning shuttles, however, land like gliders, without power and on runways. Other rockets can place heavy payloads into orbit, but, they can only be used once. Space Shuttles are designed to be continually reused. When Space Shuttles are used to transport complete scientific laboratories into space, the laboratories remain inside the payload bay throughout the mission. They are then removed after the Space Shuttle returns to Earth and can be reused on future flights. Some of these orbital laboratories, like the Spacelab, provide facilities for several specialists to conduct experiments in such fields as medicine, astronomy, and materials manufacturing. Some types of satellites deployed by Space Shuttles include those involved in environmental and resources protection, astronomy, weather forecasting, navigation, oceanographic studies

  5. Shuttle Atlantis Returning to Kennedy Space Center after 10-Month Refurbishment

    NASA Technical Reports Server (NTRS)

    1998-01-01

    The Space Shuttle Atlantis rides on the back of one of NASA's Boeing 747 Shuttle Carrier Aircraft en route from California to the Kennedy Space Center, Florida. Space Shuttles are the main element of America's Space Transportation System and are used for space research and other space applications. The shuttles are the first vehicles capable of being launched into space and returning to Earth on a routine basis. Space Shuttles are used as orbiting laboratories in which scientists and mission specialists conduct a wide variety of scientific experiments. Crews aboard shuttles place satellites in orbit, rendezvous with satellites to carry out repair missions and return them to space, and retrieve satellites and return them to Earth for refurbishment and reuse. Space Shuttles are true aerospace vehicles. They leave Earth and its atmosphere under rocket power provided by three liquid-propellant main engines with two solid-propellant boosters attached plus an external liquid-fuel tank. After their orbital missions, they streak back through the atmosphere and land like airplanes. The returning shuttles, however, land like gliders, without power and on runways. Other rockets can place heavy payloads into orbit, but, they can only be used once. Space Shuttles are designed to be continually reused. When Space Shuttles are used to transport complete scientific laboratories into space, the laboratories remain inside the payload bay throughout the mission. They are then removed after the Space Shuttle returns to Earth and can be reused on future flights. Some of these orbital laboratories, like the Spacelab, provide facilities for several specialists to conduct experiments in such fields as medicine, astronomy, and materials manufacturing. Some types of satellites deployed by Space Shuttles include those involved in environmental and resources protection, astronomy, weather forecasting, navigation, oceanographic studies, and other scientific fields. The Space Shuttles can also

  6. Shuttle Atlantis Returning to Kennedy Space Center after 10-Month Refurbishment

    NASA Technical Reports Server (NTRS)

    1998-01-01

    The Space Shuttle orbiter Atlantis, framed by the California mountains, as it rides on the back of one of NASA's Boeing 747 Shuttle Carrier Aircraft (SCA) en route from California to the Kennedy Space Center, Florida. Space Shuttles are the main element of America's Space Transportation System and are used for space research and other space applications. The shuttles are the first vehicles capable of being launched into space and returning to Earth on a routine basis. Space Shuttles are used as orbiting laboratories in which scientists and mission specialists conduct a wide variety of scientific experiments. Crews aboard shuttles place satellites in orbit, rendezvous with satellites to carry out repair missions and return them to space, and retrieve satellites and return them to Earth for refurbishment and reuse. Space Shuttles are true aerospace vehicles. They leave Earth and its atmosphere under rocket power provided by three liquid-propellant main engines with two solid-propellant boosters attached plus an external liquid-fuel tank. After their orbital missions, they streak back through the atmosphere and land like airplanes. The returning shuttles, however, land like gliders, without power and on runways. Other rockets can place heavy payloads into orbit, but, they can only be used once. Space Shuttles are designed to be continually reused. When Space Shuttles are used to transport complete scientific laboratories into space, the laboratories remain inside the payload bay throughout the mission. They are then removed after the Space Shuttle returns to Earth and can be reused on future flights. Some of these orbital laboratories, like the Spacelab, provide facilities for several specialists to conduct experiments in such fields as medicine, astronomy, and materials manufacturing. Some types of satellites deployed by Space Shuttles include those involved in environmental and resources protection, astronomy, weather forecasting, navigation, oceanographic studies

  7. Summary Report for the C50 Cryomodule Project

    SciTech Connect

    Drury, Michael; Davis, G; Fischer, John; Grenoble, Christiana; Hogan, John; King, Lawrence; Preble, Joseph; Wang, Haipeng; Reilly, Anthony; Mammosser, John; Saunders, Jeffrey; Macha, Kurt; Reece, Charles

    2011-03-01

    The Thomas Jefferson National Accelerator Facility has recently completed the C50 cryomodule refurbishment project. The goal of this project was to enable robust 6 GeV, 5 pass operation of the Continuous Electron Beam Accelerator Facility (CEBAF). The scope of the project included removal, refurbishment and reinstallation of ten CEBAF cryomodules at a rate of three per year. The refurbishment process included reprocessing of SRF cavities to eliminate field emission and to increase the nominal gradient from the original 5 MV/m to 12.5 MV/m. New 'dogleg' couplers were installed between the cavity and helium vessel flanges to intercept secondary electrons that produce arcing in the fundamental Power Coupler (FPC). Other changes included new ceramic RF windows for the air to vacuum interface of the FPC and improvements to the mechanical tuner. Damaged or worn components were replaced as well. All ten of the refurbished cryomodules are now installed in CEBAF and are currently operational. This paper will summarize the performance of the cryomodules.

  8. Suggestions for the refurbishment of a Greek lignite-fired power plant -- Efficiency, costs, and operation aspects

    SciTech Connect

    Stamatelopoulos, G.N.; Kakaras, E.K.; Bergeles, G.; Georgoulis, L.

    1998-07-01

    The present paper outlines measures for the refurbishment of the Greek lignite-fired power plant Kardia and discusses their impact on the efficiency, the electricity generation costs and the operation of the plant. The power plants Kardia III and IV with an installed capacity of 300 NW{sub el} each were constructed in the late 70's in Northern Greece and still operate as base load units for the Public Power Corporation (PPC) of Greece. Several problems are detected during the operation of these two units concerning high flue gas outlet temperature--and consequently low boiler efficiency, poor electrostatic precipitator performance, high slagging tendency, fluctuating temperature field resulting unstable steam temperatures and a high percentage of leakage air. To improve the current situation PPC in collaboration with the National Technical University of Athens (NTUA) conducted a feasibility study to set the priorities and to select the most suitable measures for the refurbishment of these two units. Taking advantage of the international experience, the possible measures applicable in the case of brown coal fired units upgrade were collected, categorized and presented to PPC's management. The proposed measures were evaluated for the specific case of Kardia and then it was decided to further examine the following actions: Sealing of the boiler in order to minimize the amount of the leakage air, extension of the economizer followed by the replacement of one bled steam feed water preheater aiming at the decrease of the flue gas outlet temperature and optimization of the soot blowers operation. For these actions and using the process simulation program ENBIPRO, the expected benefits in terms of efficiency as well as the dimensions of the necessary additional heating surface and the influence of the rearrangement of the heating surfaces in the boiler on the water/steam cycle were calculated. The costs of the suggested actions were estimated together with the time frame

  9. P-23 Highlights 6/10/12: Cygnus Dual Beam Radiographic Facility Refurbishment completed at U1A tunnel in Nevada NNSS meeting Level 2 milestone

    SciTech Connect

    Deyoung, Anemarie; Smith, John R.

    2012-05-03

    were delayed due to programmatic requirements. It is anticipated that Cygnus will be in service at U1a for another 5 years. With this assumption, it was realized that significant resources and effort should be allotted to bring the hardware back to its original condition, or even to improve elements when appropriate. The Cygnus Refurbishment and Enhancement Project started in April, 2011 with the intent to encompass a major overhaul of Cygnus.

  10. Visual documentation process of historic building refurbishment "Improving energy efficiency by insulating wall cavity"

    NASA Astrophysics Data System (ADS)

    Bennadji, A.

    2013-07-01

    The North East of Scotland's construction method is similar to most popular building typologies in the UK. This typology can vary in term of external material (Granite, brick or stone) but with a secondary, usually timber sub frame with a lining on its interior. Insulation was seldom a consideration when such buildings were completed. Statistics shows that 80% of existing buildings in the UK will need to be upgraded. The lack of knowledge in dealing with old building fabric's manipulation has a negative impact on buildings' integrity. The documentation of such process seems to be an important step that buildings' actors should undertake to communicate a practical knowledge that is still at incubation stage. We wanted for this documentation to be visual, as descriptions might mislead none specialised and specialised in the field due to the innovative approach our method was conducted with. For the Scottish context this research/experiment will concentrate on existing granite wall buildings with plastered lath internal wall. It is unfortunate to see the commonly beautiful interiors of Scottish buildings disappearing, when the internal linings are removed. Skips are filled with old Plaster and Lath and new linings have to be supplied and fitted. Excessive waste is created in this change. This paper is based on a historic building energy improvement case study financed by the European commission and the Scottish Government. The pilot study consists of insulating an 18th century house using an innovative product and method. The project was a response to a call by the CIC start (Construction Innovation Club), aiming to establish a link between SMEs and the Universities. The project saw the day in collaboration with Icynene Canada, KDL Kishorn (see full list in the acknowledgment). This paper describes the process through which the team went through to improve the building envelope without damaging the buildings original features (Loveday et all). The energy efficiency

  11. Molten-Caustic-Leaching (Gravimelt) System Integration Project, Phase 2

    SciTech Connect

    Not Available

    1993-03-01

    This is a report of the maintenance, refurbishment, modifications, and off-line circuit component testing of the integrated test circuit of the Molten-Caustic-Leaching (MCL or Gravimelt) process for the desulfurization and demineralization of coal. The project is sponsored by the Pittsburgh Energy Technology Center of the US Department of Energy under Contract No. DE-AC22-86-PC91257.

  12. Project W-314 Polyurea Special Protective Coating (SPC) Test Report Chemical Compatibility and Physical Characteristics Testing

    SciTech Connect

    MAUSER, R.W.

    2001-04-09

    This Engineering Test report outlines the results obtained from testing polyurea on its decon factor, tank waste compatibility, and adhesion strength when subjected to a high level of gamma radiation. This report is used in conjunction with RPP-7187 Project W-314 Pit Coatings Repair Requirements Analysis, to document the fact polyurea meets the project W-314 requirements contained in HNF-SD-W314-PDS-005 and is therefore an acceptable SPC for use in W-314 pit refurbishments.

  13. Indoor PM2.5 exposure in London's domestic stock: Modelling current and future exposures following energy efficient refurbishment

    NASA Astrophysics Data System (ADS)

    Shrubsole, C.; Ridley, I.; Biddulph, P.; Milner, J.; Vardoulakis, S.; Ucci, M.; Wilkinson, P.; Chalabi, Z.; Davies, M.

    2012-12-01

    Simulations using CONTAM (a validated multi-zone indoor air quality (IAQ) model) are employed to predict indoor exposure to PM2.5 in London dwellings in both the present day housing stock and the same stock following energy efficient refurbishments to meet greenhouse gas emissions reduction targets for 2050. We modelled interventions that would contribute to the achievement of these targets by reducing the permeability of the dwellings to 3 m3 m-2 h-1 at 50 Pa, combined with the introduction of mechanical ventilation and heat recovery (MVHR) systems. It is assumed that the current mean outdoor PM2.5 concentration of 13 μg m-3 decreased to 9 μg m-3 by 2050 due to emission control policies. Our primary finding was that installation of (assumed perfectly functioning) MVHR systems with permeability reduction are associated with appreciable reductions in PM2.5 exposure in both smoking and non-smoking dwellings. Modelling of the future scenario for non-smoking dwellings show a reduction in annual average indoor exposure to PM2.5 of 18.8 μg m-3 (from 28.4 to 9.6 μg m-3) for a typical household member. Also of interest is that a larger reduction of 42.6 μg m-3 (from 60.5 to 17.9 μg m-3) was shown for members exposed primarily to cooking-related particle emissions in the kitchen (cooks). Reductions in envelope permeability without mechanical ventilation produced increases in indoor PM2.5 concentrations; 5.4 μg m-3 for typical household members and 9.8 μg m-3 for cooks. These estimates of changes in PM2.5 exposure are sensitive to assumptions about occupant behaviour, ventilation system usage and the distributions of input variables (±72% for non-smoking and ±107% in smoking residences). However, if realised, they would result in significant health benefits.

  14. Refurbishing steam turbines

    SciTech Connect

    Valenti, M.

    1997-12-01

    Power-plant operators are reducing maintenance costs of their aging steam turbines by using wire-arc spray coating and shot peening to prolong the service life of components, and by replacing outmoded bearings and seals with newer designs. Steam-turbine operators are pressed with the challenge of keeping their aging machines functioning in the face of wear problems that are exacerbated by the demand for higher efficiencies. These problems include intense thermal cycling during both start-up and shutdown, water particles in steam and solid particles in the air that pit smooth surfaces, and load changes that cause metal fatigue.

  15. Oak Ridge National Laboratory Facilities Revitalization Project - Project Management Plan

    SciTech Connect

    Myrick, T.E.

    2000-06-06

    The Facilities Revitalization Project (FRP) has been established at Oak Ridge National Laboratory (ORNL) to provide new and/or refurbished research and support facilities for the Laboratory's science mission. The FRP vision is to provide ORNL staff with world-class facilities, consolidated at the X-10 site, with the first phase of construction to be completed within five years. The project will utilize a combination of U.S. Department of Energy (DOE), State of Tennessee, and private-sector funds to accomplish the new construction, with the facilities requirements to be focused on support of the ORNL Institutional Plan. This FRP Project Management Plan has been developed to provide the framework under which the project will be conducted. It is intended that the FRP will be managed as a programmatic office, with primary resources for execution of the project to be obtained from the responsible organizations within ORNL (Engineering, Procurement, Strategic Planning, etc.). The FRP Project Management Plan includes a definition of the project scope, the organizational responsibilities, and project approach, including detailed Work Breakdown Structure (WBS), followed by more detailed discussions of each of the main WBS elements: Project Planning Basis, Facility Deactivation and Consolidation, and New Facilities Development. Finally, a general discussion of the overall project schedule and cost tracking approach is provided.

  16. Thermal Nondestructive Evaluation Report: Inspection of the Refurbished Manipulator Arm System in the Manipulator Development Facility at Johnson Space Center 10-12 January 2001

    NASA Technical Reports Server (NTRS)

    Cramer, K. Elliott

    2002-01-01

    On 4 December 2002, a failure of the Refurbished Manipulator Arm System (RMAS) occurred in the Manipulator Development Facility (MDF) at Johnson Space Center. When the Test Director commanded a should pitch maneuver to lift the arm from its payload bay pedestal, the yaw controls failed. This, coupled with a gravitational forces (due to the angle of the shoulder joint with respect to vertical), resulted in uncontrolled arm motion. The shoulder yaw joint moved approximately 20 degrees, causing the extended arm to strike and severely damage the port side MDF catwalk handrails. The arm motion stopped after impact with the handrails. On 10-12 January 2001, inspections were performed on the port face of the lower and upper arms of the RMAS using a infrared thermography developed at Langley Research Center. This paper presents the results of those nondestructive inspections and provides a complete description of the anomalies found and their locations.

  17. Tidd PFBC demonstration project

    SciTech Connect

    Marrocco, M.

    1997-12-31

    The Tidd project was one of the first joint government-industry ventures to be approved by the US Department of Energy (DOE) in its Clean Coal Technology Program. In March 1987, DOE signed an agreement with the Ohio Power Company, a subsidiary of American Electric Power, to refurbish the then-idle Tidd plant on the banks of the Ohio River with advanced pressurized fluidized bed technology. Testing ended after 49 months of operation, 100 individual tests, and the generation of more than 500,000 megawatt-hours of electricity. The demonstration plant has met its objectives. The project showed that more than 95 percent of sulfur dioxide pollutants could be removed inside the advanced boiler using the advanced combustion technology, giving future power plants an attractive alternative to expensive, add-on scrubber technology. In addition to its sulfur removal effectiveness, the plant`s sustained periods of steady-state operation boosted its availability significantly above design projections, heightening confidence that pressurized fluidized bed technology will be a reliable, baseload technology for future power plants. The technology also controlled the release of nitrogen oxides to levels well below the allowable limits set by federal air quality standards. It also produced a dry waste product that is much easier to handle than wastes from conventional power plants and will likely have commercial value when produced by future power plants.

  18. Project: "Project!"

    ERIC Educational Resources Information Center

    Grayson, Katherine

    2007-01-01

    In November 2006, the editors of "Campus Technology" launched their first-ever High-Resolution Projection Study, to find out if the latest in projector technology could really make a significant difference in teaching, learning, and educational innovation on US campuses. The author and her colleagues asked campus educators, technologists, and…

  19. Near-Site Transportation Infrastructure Project

    SciTech Connect

    Viebrock, J.M.; Mote, N. )

    1992-02-01

    There are 122 commercial nuclear facilities from which spent nuclear fuel will be accepted by the Federal Waste Management System (FWMS). Since some facilities share common sites and some facilities are on adjacent sites, 76 sites were identified for the Near-Site Transportation Infrastructure (NSTI) project. The objective of the NSTI project was to identify the options available for transportation of spent-fuel casks from each of these commercial nuclear facility sites to the main transportation routes -- interstate highways, commercial rail lines and navigable waterways available for commercial use. The near-site transportation infrastructure from each site was assessed, based on observation of technical features identified during a survey of the routes and facilities plus data collected from referenced information sources. The potential for refurbishment of transportation facilities which are not currently operational was also assessed, as was the potential for establishing new transportation facilities.

  20. Advanced turbofan blade refurbishment technique

    SciTech Connect

    Roberts, W.B.

    1995-10-01

    The purpose of the work reported here is to investigate whether the lessons learned from the work of Suder et al. can be used to reduce the in-service performance deterioration of a fan on a high bypass ratio turbofan engine. To this end, a back-to-back test was done on the fan of an RB211-22B engine with the cooperation of Delta Airlines. The fan and engine were first overhauled per normal airline practice and cell-tested to establish that the engine performance met flight acceptance standards. This test, which the engine passed, also established a performance baseline for the overhauled engine. At this point the fan blade leading edge had not been filed or scraped and the blade surfaces had not been polished because the leading edge damage and blade surface roughness fell within the acceptable limits specified by the manufacturer for normal overhaul practice. After the cell test, the fan was removed from the engine and sent to Sermatech International where the following additional operations were performed: (1) the blade surfaces were polished to a finish of 20 rms {micro}in; (2) leading edge roughness due to particle impact damage was removed and the leading edge was polished to a finish of 20 rms {micro}in; (3) the leading edge shape was rounded and the leading edge thickness was reduced over the first 5--10% of chord. Test results indicated a 0.7% drop in thrust specific fuel consumption (lb fuel/lb thrust/hr) relative to the baseline engine after the enhanced fan overhaul. Based on the results of Suder et al. (1995) it appears that 70--80% of this performance gain is due to the thin smooth leading edge and the remainder to the highly polished finish of the blade.

  1. Refurbished extensometer sites improve the quality and frequency of aquifer-system compaction and groundwater-level measurements, San Joaquin Valley, California, USA

    NASA Astrophysics Data System (ADS)

    Sneed, M.; Brandt, J.; Solt, M.

    2012-12-01

    Extensive groundwater withdrawal from unconsolidated deposits in the San Joaquin Valley caused widespread aquifer-system compaction and land subsidence locally exceeding 8 meters (m) between 1926 and 1970. To identify the extent of subsidence, a network of 31 extensometers was installed in the 1960s. Importation of surface water in the early 1970s resulted in decreased groundwater pumping, a steady water-level recovery, and a reduced rate of compaction; consequently, data collection was sharply reduced. However, reduced surface-water availability during 1976-77, 1987-92, and 2007-09 caused increased groundwater pumping, lowered water levels, and renewed compaction. The resulting land subsidence has reduced freeboard and flow capacity of the Delta-Mendota Canal (DMC), the California Aqueduct (AQ), and other canals. Four deep (>300-m) cable-type extensometers from the old network, located along the DMC and AQ, were refurbished to identify existing and future subsidence, and to improve the quality and frequency of compaction measurements. Measurement quality was improved at three of these sites by replacing the existing reference tables, which sit atop concrete pads, with new reference tables cemented in 5.5-m boreholes and decoupled from the concrete pads to minimize the measurement of near-surface deformation. A new reference table could not be constructed at the fourth site due to restrictive drill-rig access. Insulated metal shelters were constructed to protect the equipment against environmental exposure at all sites. The frequencies of compaction and water-level measurements at the extensometer sites were improved by instrumenting each with a linear potentiometer and one or more submersible pressure transducers, respectively. An analog dial gauge was installed on each extensometer to provide data continuity in cases of electronic data interruption and to provide verification of potentiometer data. Aquifer-system compaction data from all four sites show

  2. A summary of 1988 summer student research projects in wind energy

    SciTech Connect

    Sims, J.D.; Wright, J.R.

    1988-09-01

    During the summer of 1988, the Wind Energy Research Division hosted Jesse Sims and Jocelyn Wright under the auspices of the Sandia Historically Black Colleges and Universities (HBCU) Summer Student Program. The research projects that they conducted during their tenure at Sandia are reported here. In the first chapter of this report, the development of a software package to determine the calibration constants for a group of aerodynamic sensors is detailed. In the second chapter, the refurbishment activities on the Sandia 5-m VAWT are discussed. 26 refs., 17 figs.

  3. Near-Site Transportation Infrastructure Project. Final report

    SciTech Connect

    Viebrock, J.M.; Mote, N.

    1992-02-01

    There are 122 commercial nuclear facilities from which spent nuclear fuel will be accepted by the Federal Waste Management System (FWMS). Since some facilities share common sites and some facilities are on adjacent sites, 76 sites were identified for the Near-Site Transportation Infrastructure (NSTI) project. The objective of the NSTI project was to identify the options available for transportation of spent-fuel casks from each of these commercial nuclear facility sites to the main transportation routes -- interstate highways, commercial rail lines and navigable waterways available for commercial use. The near-site transportation infrastructure from each site was assessed, based on observation of technical features identified during a survey of the routes and facilities plus data collected from referenced information sources. The potential for refurbishment of transportation facilities which are not currently operational was also assessed, as was the potential for establishing new transportation facilities.

  4. Medical devices; refurbishers, rebuilders, reconditioners, servicers, and "as is" remarketers of medical devices; review and revision of compliance policy guides and regulatory requirements; request for comments and information--FDA. Advance notice of proposed rulemaking.

    PubMed

    1997-12-23

    The Food and Drug Administration (FDA) is announcing its intention to review and, as necessary, to revise or to amend its compliance policy guides and regulatory requirements relating to the remarketing of used medical devices and the persons who refurbish, recondition, rebuild, service, or remarket such devices. The agency is considering these actions because it believes evolving industry practices warrant reevaluation of current policy and the application of certain regulatory requirements in order to ensure that particular remarketed devices meet suitable performance requirements for their intended uses, and are as safe as the originally marketed finished device. FDA is soliciting comments, proposals for alternative regulatory approaches, and information on these issues. In a future issue of the Federal Register, FDA will announce an open meeting of the Good Manufacturing Practices (GMP) Advisory Committee concerning these matters. PMID:10179309

  5. CA la electricidad de caracas: Arrecifes repowering project. Feasibility study report. Export trade information

    SciTech Connect

    1993-10-01

    The study, conducted by Raytheon Engineers & Constructors, was funded by the U.S. Trade and Development agency on behalf of C.A. La Electricidad de Caracas. The report shows the results of a feasibility study conducted to evaluate the repowering of the Arrecifes Power Plant. The study focuses on capital cost for the project, refurbishment of existing equipment, and the installation of new repowering equipment. The study also evaluates combustion turbine generators of different manufacturers and sizes to determine the most beneficial configuration. The report is divided into the following sections: (1) Introduction; (2) Conclusions and Recommendations; (3) Study Basis; (4) Alternatives Analysis; (5) Layout and Equipment Issues; (6) Performance and Economic Analysis; (7) Repowered Facility Description; (8) Mechanical Systems; (9) Civil/Structural/Architectural; (10) Electrical Systems; (11) Instrumentation and Controls; (12) Environmental Overview; (13) Project Implementation Plan; (14) Project Conceptual Cost Estimate.

  6. Project Wild (Project Tame).

    ERIC Educational Resources Information Center

    Siegenthaler, David

    For 37 states in the United States, Project Wild has become an officially sanctioned, distributed and funded "environemtnal and conservation education program." For those who are striving to implement focused, sequential, learning programs, as well as those who wish to promote harmony through a non-anthropocentric world view, Project Wild may…

  7. City of New York preparing of a district heating and cooling systems Project (Phase II)

    SciTech Connect

    Not Available

    1982-08-27

    The project with the greatest, and most immediate potential, is the Brooklyn Navy Yard Complex, which included the Brooklyn Navy Yard Industrial Complex, nearby public housing apartments, Brooklyn Hospital, Cumberland Hospital, the Red Hook Sewage Treatment Plant and Pratt Institute. Initial engineering investigation indicates that five, and probably six, of the 160,000 lb/hr, 500 psi boilers in the generating plant at the Navy Yard can be economically refurbished, and could produce up to 900,000 lbs/hr of steam. Further, at least two of the on site turbines appear to be refurbishable, making possible cogeneration of electricity with district heating and/or cooling. The NYCEO research has shown that an innovative system, using pressurized hot water and heat exchangers (to generate low pressure steam for individual apartment houses) is an effective means to satisfy the heating requirements of New York City's apartment buildings, many of which are already steam heated, while reducing their energy costs and oil consumption. This approach takes advantage of a modern hot water system, while avoiding the disadvantage of expensive building retrofit. Preliminary studies have shown that thermal energy costs to Yard tenants, among the highest anywhere in the USA, will be reduced. These savings will increase long term tenant occupancy as well as ability to create and hold jobs in the area.

  8. Projects Work!

    ERIC Educational Resources Information Center

    Textor, Martin R.

    2005-01-01

    The great educational value of projects is emphasized by contrasting negative aspects of the life of today's children with the goals of project work. This is illustrated by a project "Shopping." It is shown what children are learning in such projects and what the advantages of project work are. Relevant topic areas, criteria for selecting a…

  9. Shop Projects.

    ERIC Educational Resources Information Center

    Patton, Bob

    Vocational agriculture teachers in Oklahoma prepared the shop project drawings which comprise the document. Seventy-one projects, with lists of required materials, diagrams, and measurements, are included. Construction projects fall into six categories (number of projects in parentheses): Trailers (5), racks (3), livestock production projects…

  10. Stacked rig refurbished for ultradeep gas drilling

    SciTech Connect

    Noevig, T.; Gutsche, W. )

    1995-01-09

    A heavy drilling rig, cold stacked for several years, recently underwent numerous structural, equipment, and computer upgrades for drilling ultradeep (8,000 m) gas wells in Germany. The technical improvements on the rig included supplementary installations and modifications to safety, quality, engineering, noise abatement, and environmental protection systems. With a maximal hook load of 700 tons, the drilling rig is one of the heaviest of its kind in Europe. The rig has a drilling depth range of 7,000--8,000 m, and the top drive system enables horizontal drilling. The paper describes the rig site, mast, top drive, substructure, draw works, power station, mud system, instrumentation, and other equipment.

  11. Cutting Technology Costs with Refurbished Computers

    ERIC Educational Resources Information Center

    Dessoff, Alan

    2010-01-01

    Many district administrators are finding that they can save money on computers by buying preowned ones instead of new ones. The practice has other benefits as well: It allows districts to give more computers to more students who need them, and it also promotes good environmental practices by keeping the machines out of landfills, where they…

  12. The SILEX project - The first European optical intersatellite link experiment

    NASA Astrophysics Data System (ADS)

    Laurent, B.; Duchmann, O.

    1991-06-01

    The SILEX concept, based on 0.8-micron diodes, is summarized, and the key features of the mission and its technical definition are described. The SILEX project is at the beginning of its development phase. The two optical payloads will be ready for launch in 1994-1995 so as to allow a flight demonstration from 1996 on, depending on the satellite launch dates, which are to be decided as a function of the operation of SPOT 3 in orbit. The SILEX general schedule is given. One of the aims of the engineering phase has been to develop a complete system test bed which has made it possible to reinforce the overall selected concept and verify the expected performances. This test bed is to be refurbished to become an essential integration and verification tool during the hardware development and integration phase. Present technological perspectives on components confirm the selection of the wavelength range and its suitability to a longer-term application: optical power and reliability for the laser diodes, and very low noise performance for the detectors.

  13. Project SEED.

    ERIC Educational Resources Information Center

    Chemical and Engineering News, 1986

    1986-01-01

    Reports on Project SEED (Summer Educational Experience for the Disadvantaged) a project in which high school students from low-income families work in summer jobs in a variety of academic, industrial, and government research labs. The program introduces the students to career possibilities in chemistry and to the advantages of higher education.…

  14. Project Success.

    ERIC Educational Resources Information Center

    Meredith, Larry D.

    Project Success consists of after-school, weekend, and summer educational programs geared toward minority and disadvantaged students to increase their numbers seeking postsecondary education from the Meadville, Pennsylvania area. The project is funded primarily through the Edinboro University of Pennsylvania, whose administration is committed to…

  15. Project FAST.

    ERIC Educational Resources Information Center

    Essexville-Hampton Public Schools, MI.

    Described are components of Project FAST (Functional Analysis Systems Training) a nationally validated project to provide more effective educational and support services to learning disordered children and their regular elementary classroom teachers. The program is seen to be based on a series of modules of delivery systems ranging from mainstream…

  16. Project EASIER.

    ERIC Educational Resources Information Center

    Alvord, David J.; Tack, Leland R.; Dallam, Jerald W.

    1998-01-01

    Describes the development of Project EASIER, a collaborative electronic-data interchange for networking Iowa local school districts, education agencies, community colleges, universities, and the Department of Education. The primary goal of this project is to develop and implement a system for collection of student information for state and federal…

  17. Geodynamics Project

    ERIC Educational Resources Information Center

    Drake, Charles L.

    1977-01-01

    Describes activities of Geodynamics Project of the Federal Council on Science and Technology, such as the application of multichannel seismic-reflection techniques to study the nature of the deep crust and upper mantle. (MLH)

  18. Project Soar.

    ERIC Educational Resources Information Center

    Austin, Marion

    1982-01-01

    Project Soar, a Saturday enrichment program for gifted students (6-14 years old), allows students to work intensively in a single area of interest. Examples are cited of students' work in crewel embroidery, creative writing, and biochemistry. (CL)

  19. Project Reptile!

    ERIC Educational Resources Information Center

    Diffily, Deborah

    2001-01-01

    Integrating curriculum is important in helping children make connections within and among areas. Presents a class project for kindergarten children which came out of the students' interests and desire to build a reptile exhibit. (ASK)

  20. Projection displays

    NASA Astrophysics Data System (ADS)

    Chiu, George L.; Yang, Kei H.

    1998-08-01

    Projection display in today's market is dominated by cathode ray tubes (CRTs). Further progress in this mature CRT projector technology will be slow and evolutionary. Liquid crystal based projection displays have gained rapid acceptance in the business market. New technologies are being developed on several fronts: (1) active matrix built from polysilicon or single crystal silicon; (2) electro- optic materials using ferroelectric liquid crystal, polymer dispersed liquid crystals or other liquid crystal modes, (3) micromechanical-based transducers such as digital micromirror devices, and grating light valves, (4) high resolution displays to SXGA and beyond, and (5) high brightness. This article reviews the projection displays from a transducer technology perspective along with a discussion of markets and trends.

  1. Cloudnet Project

    DOE Data Explorer

    Hogan, Robin

    2008-01-15

    Cloudnet is a research project supported by the European Commission. This project aims to use data obtained quasi-continuously for the development and implementation of cloud remote sensing synergy algorithms. The use of active instruments (lidar and radar) results in detailed vertical profiles of important cloud parameters which cannot be derived from current satellite sensing techniques. A network of three already existing cloud remote sensing stations (CRS-stations) will be operated for a two year period, activities will be co-ordinated, data formats harmonised and analysis of the data performed to evaluate the representation of clouds in four major european weather forecast models.

  2. LLAMA Project

    NASA Astrophysics Data System (ADS)

    Arnal, E. M.; Abraham, Z.; Giménez de Castro, G.; de Gouveia dal Pino, E. M.; Larrarte, J. J.; Lepine, J.; Morras, R.; Viramonte, J.

    2014-10-01

    The project LLAMA, acronym of Long Latin American Millimetre Array is very briefly described in this paper. This project is a joint scientific and technological undertaking of Argentina and Brazil on the basis of an equal investment share, whose mail goal is both to install and to operate an observing facility capable of exploring the Universe at millimetre and sub/millimetre wavelengths. This facility will be erected in the argentinean province of Salta, in a site located at 4830m above sea level.

  3. Maximum Capital Project Management.

    ERIC Educational Resources Information Center

    Adams, Matt

    2002-01-01

    Describes the stages of capital project planning and development: (1) individual capital project submission; (2) capital project proposal assessment; (3) executive committee; and (4) capital project execution. (EV)

  4. Thanksgiving Project

    ERIC Educational Resources Information Center

    Hilden, Pauline

    1976-01-01

    A teacher describes a Thanksgiving project in which 40 educable mentally retarded students (6-13 years old) made and served their own dinner of stew, butter, bread, ice cream, and pie, and in the process learned about social studies, cooking, and proper meal behavior. (CL)

  5. PROJECT RESPECT

    EPA Science Inventory

    Project RESPECT was a national study evaluating the efficacy of HIV prevention counseling in changing high risk sexual behaviors and preventing new sexually transmitted diseases (STDs) and HIV. The trial enrolled men and women who came for diagnosis and treatment of an STD to one...

  6. Project CLASS.

    ERIC Educational Resources Information Center

    McBain, Susan L.; And Others

    Project CLASS (Competency-Based Live-Ability Skills) uses a series of 60 modules to teach life survival skills to adults with low-level reading ability--especially Adult Basic Education/English as a Second Language students. Two versions of the modules have been developed: one for use with teacher-directed instruction and another for independent…

  7. Limnological Projects.

    ERIC Educational Resources Information Center

    Hambler, David J.; Dixon, Jean M.

    1982-01-01

    Describes collection of quantitative samples of microorganisms and accumulation of physical data from a pond over a year. Provides examples of how final-year degree students have used materials and data for ecological projects (involving mainly algae), including their results/conclusions. Also describes apparatus and reagents used in the student…

  8. Project Schoolflight

    ERIC Educational Resources Information Center

    Owen, Ben

    1975-01-01

    Describes "Project School Flight" which is an idea originated by the Experimental Aircraft Association to provide the opportunity for young people to construct a light aircraft in the schools as part of a normal class. Address included of Experimental Aircraft Association for interested persons. (BR)

  9. Project Boomerang

    ERIC Educational Resources Information Center

    King, Allen L.

    1975-01-01

    Describes an experimental project on boomerangs designed for an undergraduate course in classical mechanics. The students designed and made their own boomerangs, devised their own procedures, and carried out suitable measurements. Presents some of their data and a simple analysis for the two-bladed boomerang. (Author/MLH)

  10. Project COLD.

    ERIC Educational Resources Information Center

    Kazanjian, Wendy C.

    1982-01-01

    Describes Project COLD (Climate, Ocean, Land, Discovery) a scientific study of the Polar Regions, a collection of 35 modules used within the framework of existing subjects: oceanography, biology, geology, meterology, geography, social science. Includes a partial list of topics and one activity (geodesic dome) from a module. (Author/SK)

  11. Project Documerica

    ERIC Educational Resources Information Center

    Journal of College Science Teaching, 1972

    1972-01-01

    The Environmental Protection Agency has started a project to actually picture the environmental movement in the United States. This is an attempt to make the public aware of the air pollution in their area or state and to acquaint them with the effects of air cleaning efforts. (PS)

  12. Tedese Project

    NASA Astrophysics Data System (ADS)

    Buforn, E.; Davila, J. Martin; Bock, G.; Pazos, A.; Udias, A.; Hanka, W.

    The TEDESE (Terremotos y Deformacion Cortical en el Sur de España) project is a joint project of the Universidad Complutense de Madrid (UCM) and Real Instituto y Observatorio de la Armada de San Fernando, Cadiz (ROA) supported by the Spanish Ministerio de Ciencia y Tecnologia with the participation of the GeoforschungZen- trum, Potsdam (GFZ). The aim is to carry out a study of the characteristics of the oc- currence and mechanism of earthquakes together with measurements of crustal struc- ture and deformations in order to obtain an integrated evaluation of seismic risk in southern Spain from. As part of this project a temporal network of 10 broad-band seismological stations, which will complete those already existing in the zone, have been installed in southern Spain and northern Africa for one year beginning in October 2001. The objectives of the project are the study in detail of the focal mechanisms of earthquakes in this area, of structural in crust and upper mantle, of seismic anisotropy in crust and mantle as indicator for tectonic deformation processed and the measure- ments of crustal deformations using techniques with permanent GPS and SLR stations and temporary GPS surveys. From these studies, seismotectonic models and maps will be elaborated and seismic risk in the zone will be evaluated.

  13. Project Reconstruct.

    ERIC Educational Resources Information Center

    Helisek, Harriet; Pratt, Donald

    1994-01-01

    Presents a project in which students monitor their use of trash, input and analyze information via a database and computerized graphs, and "reconstruct" extinct or endangered animals from recyclable materials. The activity was done with second-grade students over a period of three to four weeks. (PR)

  14. Projected Identities

    ERIC Educational Resources Information Center

    Anderson, Mark Alan

    2006-01-01

    This article presents the idea behind Projected Identities, an art activity wherein students fuse art-making processes and digital image manipulations in a series of exploratory artistic self-examinations. At some point in every person's life they've been told something hard to forget. Students might, for example, translate phrases like, "Good…

  15. Project Succeed.

    ERIC Educational Resources Information Center

    Patterson, John

    Project Succeed is a program for helping failure- and dropout-oriented pupils to improve their school achievement. Attendance and assignment completion are the key behaviors for enhancing achievement. Behavior modification and communications procedures are used to bring about the desired changes. Treatment procedures include current assessment…

  16. Project Narrative

    SciTech Connect

    Driscoll, Mary C.

    2012-07-12

    The Project Narrative describes how the funds from the DOE grant were used to purchase equipment for the biology, chemistry, physics and mathematics departments. The Narrative also describes how the equipment is being used. There is also a list of the positive outcomes as a result of having the equipment that was purchased with the DOE grant.

  17. Project Notes.

    ERIC Educational Resources Information Center

    School Science Review, 1979

    1979-01-01

    Listed are 32 biology A-level projects, categorized by organisms studied as follows: algae (1), bryophytes (1), angiosperms (14), fungi (1), flatworms (1), annelids (2), molluscs (1), crustaceans (2), insects (4), fish (2), mammals (1), humans (1); and one synecological study. (CS)

  18. Project SUCCEED.

    ERIC Educational Resources Information Center

    Yarger, Sam; Klingner, Janette

    This paper describes Project SUCCEED (School University Community Coalition for Excellence in Education). The coalition includes the University of Miami School of Education, the University of Miami College of Arts and Sciences, Miami-Dade County Public Schools, and the Miami Museum of Science. The goal is to provide a comprehensive approach to…

  19. Project Paiute

    ERIC Educational Resources Information Center

    Dearmin, Evalyn Titus

    1977-01-01

    Working with the Humboldt County School District, the Fort McDermitt Indian Education Committee, and four Paiute Teacher aides, the University of Nevada developed a three-component project: a bilingual/bicultural reading text for K-4 Paiutes; an in-service training program in Native American education; and a pilot bilingual curriculum. (JC)

  20. Project Notes

    ERIC Educational Resources Information Center

    School Science Review, 1977

    1977-01-01

    Listed and described are student A-level biology projects in the following areas: Angiosperm studies (e.g., factors affecting growth of various plants), 7; Bacterial studies, 1; Insect studies, 2; Fish studies, 1; Mammal studies, 1; Human studies, 1; Synecology studies, 2; Environmental studies, 2; and Enzyme studies, 1. (CS)

  1. Project Katrina

    ERIC Educational Resources Information Center

    Aghayan, Carol; Schellhaas, Andree; Wayne, Angela; Burts, Diane C.; Buchanan, Teresa K.; Benedict, Joan

    2005-01-01

    This article describes a spontaneous project that emerged from a group of 3- and 4-year-old children in Louisiana after Hurricane Katrina. The article describes how the teachers adapted the classroom and curriculum to meet the diverse needs of children who were evacuees, as well as those children who were affected in other ways by the…

  2. Project CAST.

    ERIC Educational Resources Information Center

    Charles County Board of Education, La Plata, MD. Office of Special Education.

    The document outlines procedures for implementing Project CAST (Community and School Together), a community-based career education program for secondary special education students in Charles County, Maryland. Initial sections discuss the role of a learning coordinator, (including relevant travel reimbursement and mileage forms) and an overview of…

  3. Spent Nuclear Fuel project, project management plan

    SciTech Connect

    Fuquay, B.J.

    1995-10-25

    The Hanford Spent Nuclear Fuel Project has been established to safely store spent nuclear fuel at the Hanford Site. This Project Management Plan sets forth the management basis for the Spent Nuclear Fuel Project. The plan applies to all fabrication and construction projects, operation of the Spent Nuclear Fuel Project facilities, and necessary engineering and management functions within the scope of the project

  4. Cognitive Education Project. Summary Project.

    ERIC Educational Resources Information Center

    Mulcahy, Robert; And Others

    The Cognitive Education Project conducted a 3-year longitudinal evaluation of two cognitive education programs that were aimed at teaching thinking skills. The critical difference between the two experimental programs was that one, Feuerstein's Instrumental Enrichment (IE) method, was taught out of curricular content, while the other, the…

  5. Project Prometheus

    NASA Technical Reports Server (NTRS)

    Johnson, Steve

    2003-01-01

    Project Prometheus will enable a new paradigm in the scientific exploration of the Solar System. The proposed JIMO mission will start a new generation of missions characterized by more maneuverability, flexibility, power and lifetime. Project Prometheus organization is established at NASA Headquarters: 1.Organization established to carry out development of JIMO, nuclear power (radioisotope), and nuclear propulsion research. 2.Completed broad technology and national capacity assessments to inform decision making on planning and technology development. 3.Awarded five NRA s for nuclear propulsion research. 4.Radioisotope power systems in development, and Plutonium-238 being purchased from Russia. 5.Formulated science driven near-term and long-term plan for the safe utilization of nuclear propulsion based missions. 6.Completed preliminary studies (Pre-Phase A) of JIMO and other missions. 7.Initiated JIMO Phase A studies by Contractors and NASA.

  6. SIMBIOS Project

    NASA Technical Reports Server (NTRS)

    Fargion, Giulietta S.; McClain, Charles R.; Busalacchi, Antonio J. (Technical Monitor)

    2001-01-01

    The purpose of this technical report is to provide current documentation of the Sensor Intercomparison and Merger for Biological and Interdisciplinary Oceanic Studies (SIMBIOS) Project activities, NASA Research Announcement (NRAI) research status, satellite data processing, data product validation, and field calibration. This documentation is necessary to ensure that critical information is related to the scientific community and NASA management. This critical information includes the technical difficulties and challenges of validating and combining ocean color data from an array of independent satellite systems to form consistent and accurate global bio-optical time series products. This technical report is not meant as a substitute for scientific literature. Instead, it will provide a ready and responsive vehicle for the multitude of technical reports issued by an operational project.

  7. Project summaries

    NASA Technical Reports Server (NTRS)

    1990-01-01

    Lunar base projects, including a reconfigurable lunar cargo launcher, a thermal and micrometeorite protection system, a versatile lifting machine with robotic capabilities, a cargo transport system, the design of a road construction system for a lunar base, and the design of a device for removing lunar dust from material surfaces, are discussed. The emphasis on the Gulf of Mexico project was on the development of a computer simulation model for predicting vessel station keeping requirements. An existing code, used in predicting station keeping requirements for oil drilling platforms operating in North Shore (Alaska) waters was used as a basis for the computer simulation. Modifications were made to the existing code. The input into the model consists of satellite altimeter readings and water velocity readings from buoys stationed in the Gulf of Mexico. The satellite data consists of altimeter readings (wave height) taken during the spring of 1989. The simulation model predicts water velocity and direction, and wind velocity.

  8. Hydropower Projects

    SciTech Connect

    2015-04-02

    The Water Power Program helps industry harness this renewable, emissions-free resource to generate environmentally sustainable and cost-effective electricity. Through support for public, private, and nonprofit efforts, the Water Power Program promotes the development, demonstration, and deployment of advanced hydropower devices and pumped storage hydropower applications. These technologies help capture energy stored by diversionary structures, increase the efficiency of hydroelectric generation, and use excess grid energy to replenish storage reserves for use during periods of peak electricity demand. In addition, the Water Power Program works to assess the potential extractable energy from domestic water resources to assist industry and government in planning for our nation’s energy future. From FY 2008 to FY 2014, DOE’s Water Power Program announced awards totaling approximately $62.5 million to 33 projects focused on hydropower. Table 1 provides a brief description of these projects.

  9. Project MEDSAT

    NASA Astrophysics Data System (ADS)

    During the winter term of 1991, two design courses at the University of Michigan worked on a joint project, MEDSAT. The two design teams consisted of the Atmospheric, Oceanic, and Spacite System Design and Aerospace Engineering 483 (Aero 483) Aerospace System Design. In collaboration, they worked to produce MEDSAT, a satellite and scientific payload whose purpose was to monitor environmental conditions over Chiapas, Mexico. Information gained from the sensing, combined with regional data, would be used to determine the potential for malaria occurrence in that area. The responsibilities of AOSS 605 consisted of determining the remote sensing techniques, the data processing, and the method to translate the information into a usable output. Aero 483 developed the satellite configuration and the subsystems required for the satellite to accomplish its task. The MEDSAT project is an outgrowth of work already being accomplished by NASA's Biospheric and Disease Monitoring Program and Ames Research Center. NASA's work has been to develop remote sensing techniques to determine the abundance of disease carriers and now this project will place the techniques aboard a satellite. MEDSAT will be unique in its use of both a Synthetic Aperture Radar and visual/IR sensor to obtain comprehensive monitoring of the site. In order to create a highly feasible system, low cost was a high priority. To obtain this goal, a light satellite configuration launched by the Pegasus launch vehicle was used.

  10. Project MEDSAT

    NASA Technical Reports Server (NTRS)

    1991-01-01

    During the winter term of 1991, two design courses at the University of Michigan worked on a joint project, MEDSAT. The two design teams consisted of the Atmospheric, Oceanic, and Spacite System Design and Aerospace Engineering 483 (Aero 483) Aerospace System Design. In collaboration, they worked to produce MEDSAT, a satellite and scientific payload whose purpose was to monitor environmental conditions over Chiapas, Mexico. Information gained from the sensing, combined with regional data, would be used to determine the potential for malaria occurrence in that area. The responsibilities of AOSS 605 consisted of determining the remote sensing techniques, the data processing, and the method to translate the information into a usable output. Aero 483 developed the satellite configuration and the subsystems required for the satellite to accomplish its task. The MEDSAT project is an outgrowth of work already being accomplished by NASA's Biospheric and Disease Monitoring Program and Ames Research Center. NASA's work has been to develop remote sensing techniques to determine the abundance of disease carriers and now this project will place the techniques aboard a satellite. MEDSAT will be unique in its use of both a Synthetic Aperture Radar and visual/IR sensor to obtain comprehensive monitoring of the site. In order to create a highly feasible system, low cost was a high priority. To obtain this goal, a light satellite configuration launched by the Pegasus launch vehicle was used.

  11. Burnet Project

    PubMed Central

    Masellis, A.; Atiyeh, B.

    2009-01-01

    Summary The BurNet project, a pilot project of the Eumedis initiative, has become true. The Eumedis (EUro MEDiterranean Information Society) initiative is part of the MEDA programme of the EU to develop the Information Society in the Mediterranean area. In the health care sector, the objective of Eumedis is: the deployment of network-based solutions to interconnect - using userfriendly and affordable solutions - the actors at all levels of the "health care system" of the Euro-Mediterranean region. The Bur Net project interconnects 17 Burn Centres (BC) in the Mediterranean Area through an information network both to standardize courses of action in the field of prevention, treatment, and functional and psychological rehabilitation of burn patients and to coordinate interactions between BC and emergency rooms in peripheral hospitals using training/information activities and telemedicine to optimize first aid provided to burn patients before referral to a BC. Shared procedure protocols for prevention and the care and rehabilitation of patients, both at individual and mass level, will help to create an international specialized database and a Webbased teleconsultation system. PMID:21991176

  12. Project Exodus

    NASA Technical Reports Server (NTRS)

    1990-01-01

    Project Exodus is an in-depth study to identify and address the basic problems of a manned mission to Mars. The most important problems concern propulsion, life support, structure, trajectory, and finance. Exodus will employ a passenger ship, cargo ship, and landing craft for the journey to Mars. These three major components of the mission design are discussed separately. Within each component the design characteristics of structures, trajectory, and propulsion are addressed. The design characteristics of life support are mentioned only in those sections requiring it.

  13. Project Explorer

    NASA Technical Reports Server (NTRS)

    Dannenberg, K. K.; Henderson, A.; Lee, J.; Smith, G.; Stluka, E.

    1984-01-01

    PROJECT EXPLORER is a program that will fly student-developed experiments onboard the Space Shuttle in NASA's Get-Away Special (GAS) containers. The program is co-sponsored by the Alabama Space and Rocket Center, the Alabama-Mississippi Section of the American Institute of Aeronautics and Astronautics, Alabama A&M University and requires extensive support by the University of Alabama in Huntsville. A unique feature of this project will demonstrate transmissions to ground stations on amateur radio frequencies in English language. Experiments Nos. 1, 2, and 3 use the microgravity of space flight to study the solidification of lead-antimony and aluminum-copper alloys, the growth of potassium-tetracyanoplatinate hydrate crystals in an aqueous solution, and the germination of radish seeds. Flight results will be compared with Earth-based data. Experiment No. 4 features radio transmission and will also provide timing for the start of all other experiments. A microprocessor will obtain real-time data from all experiments as well as temperature and pressure measurements taken inside the canister. These data will be transmitted on previously announced amateur radio frequencies after they have been converted into the English language by a digitalker for general reception.

  14. SIMBIOS Project

    NASA Technical Reports Server (NTRS)

    Fargion, Giulietta S.; McClain, Charles R.

    2002-01-01

    The purpose of this technical report is to provide current documentation of the Sensor Intercomparison and Merger for Biological and Interdisciplinary Oceanic Studies (SIMBIOS) Project activities, NASA Research Announcement (NRA) research status, satellite data processing, data product validation, and field calibration. This documentation is necessary to ensure that critical information is related to the scientific community and NASA management. This critical information includes the technical difficulties and challenges of validating and combining ocean color data from an array of independent satellite systems to form consistent and accurate global bio-optical time series products. This technical report is not meant as a substitute for scientific literature. Instead, it will provide a ready and responsive vehicle for the multitude of technical reports issued by an operational project. The SIMBIOS Science Team Principal Investigators' (PIs) original contributions to this report are in chapters four and above. The purpose of these contributions is to describe the current research status of the SIMBIOS-NRA-96 funded research. The contributions are published as submitted, with the exception of minor edits to correct obvious grammatical or clerical errors.

  15. PORTNUS Project

    SciTech Connect

    Loyal, Rebecca E.

    2015-07-14

    The objective of the Portunus Project is to create large, automated offshore ports that will the pace and scale of international trade. Additionally, these ports would increase the number of U.S. domestic trade vessels needed, as the imported goods would need to be transported from these offshore platforms to land-based ports such as Boston, Los Angeles, and Newark. Currently, domestic trade in the United States can only be conducted by vessels that abide by the Merchant Marine Act of 1920 – also referred to as the Jones Act. The Jones Act stipulates that vessels involved in domestic trade must be U.S. owned, U.S. built, and manned by a crew made up of U.S. citizens. The Portunus Project would increase the number of Jones Act vessels needed, which raises an interesting economic concern. Are Jones Act ships more expensive to operate than foreign vessels? Would it be more economically efficient to modify the Jones Act and allow vessels manned by foreign crews to engage in U.S. domestic trade? While opposition to altering the Jones Act is strong, it is important to consider the possibility that ship-owners who employ foreign crews will lobby for the chance to enter a growing domestic trade market. Their success would mean potential job loss for thousands of Americans currently employed in maritime trade.

  16. Project Exodus

    NASA Technical Reports Server (NTRS)

    Bryant, Rodney (Compiler); Dillon, Jennifer (Compiler); Grewe, George (Compiler); Mcmorrow, Jim (Compiler); Melton, Craig (Compiler); Rainey, Gerald (Compiler); Rinko, John (Compiler); Singh, David (Compiler); Yen, Tzu-Liang (Compiler)

    1990-01-01

    A design for a manned Mars mission, PROJECT EXODUS is presented. PROJECT EXODUS incorporates the design of a hypersonic waverider, cargo ship and NIMF (nuclear rocket using indigenous Martian fuel) shuttle lander to safely carry out a three to five month mission on the surface of Mars. The cargo ship transports return fuel, return engine, surface life support, NIMF shuttle, and the Mars base to low Mars orbit (LMO). The cargo ship is powered by a nuclear electric propulsion (NEP) system which allows the cargo ship to execute a spiral trajectory to Mars. The waverider transports ten astronauts to Mars and back. It is launched from the Space Station with propulsion provided by a chemical engine and a delta velocity of 9 km/sec. The waverider performs an aero-gravity assist maneuver through the atmosphere of Venus to obtain a deflection angle and increase in delta velocity. Once the waverider and cargo ship have docked the astronauts will detach the landing cargo capsules and nuclear electric power plant and remotely pilot them to the surface. They will then descend to the surface aboard the NIMF shuttle. A dome base will be quickly constructed on the surface and the astronauts will conduct an exploratory mission for three to five months. They will return to Earth and dock with the Space Station using the waverider.

  17. SISCAL project

    NASA Astrophysics Data System (ADS)

    Santer, Richard P.; Fell, Frank

    2003-05-01

    The first "ocean colour" sensor, Coastal Zone Color Scanner (CZCS), was launched in 1978. Oceanographers learnt a lot from CZCS but it remained a purely scientific sensor. In recent years, a new generation of satellite-borne earth observation (EO) instruments has been brought into space. These instruments combine high spectral and spatial resolution with revisiting rates of the order of one per day. More instruments with further increased spatial, spectral and temporal resolution will be available within the next years. In the meantime, evaluation procedures taking advantage of the capabilities of the new instruments were derived, allowing the retrieval of ecologically important parameters with higher accuracy than before. Space agencies are now able to collect and to process satellite data in real time and to disseminate them via the Internet. It is therefore meanwhile possible to envisage using EO operationally. In principle, a significant demand for EO data products on terrestrial or marine ecosystems exists both with public authorities (environmental protection, emergency management, natural resources management, national parks, regional planning, etc) and private companies (tourist industry, insurance companies, water suppliers, etc). However, for a number of reasons, many data products that can be derived from the new instruments and methods have not yet left the scientific community towards public or private end users. It is the intention of the proposed SISCAL (Satellite-based Information System on Coastal Areas and Lakes) project to contribute to the closure of the existing gap between space agencies and research institutions on one side and end users on the other side. To do so, we intend to create a data processor that automatically derives and subsequently delivers over the Internet, in Near-Real-Time (NRT), a number of data products tailored to individual end user needs. The data products will be generated using a Geographical Information System (GIS

  18. SISCAL project

    NASA Astrophysics Data System (ADS)

    Santer, Richard P.; Fell, Frank

    2003-05-01

    The first "ocean colour" sensor, Coastal Zone Color Scanner (CZCS), was launched in 1978. Oceanographers learnt a lot from CZCS but it remained a purely scientific sensor. In recent years, a new generation of satellite-borne earth observation (EO) instruments has been brought into space. These instruments combine high spectral and spatial resolution with revisiting rates of the order of one per day. More instruments with further increased spatial, spectral and temporal resolution will be available within the next years. In the meantime, evaluation procedures taking advantage of the capabilities of the new instruments were derived, allowing the retrieval of ecologically important parameters with higher accuracy than before. Space agencies are now able to collect and to process satellite data in real time and to disseminate them via the Internet. It is therefore meanwhile possible to envisage using EO operationally. In principle, a significant demand for EO data products on terrestrial or marine ecosystems exists both with public authorities (environmental protection, emergency management, natural resources management, national parks, regional planning, etc) and private companies (tourist industry, insurance companies, water suppliers, etc). However, for a number of reasons, many data products that can be derived from the new instruments and methods have not yet left the scientific community towards public or private end users. It is the intention of the proposed SISCAL (Satellite-based Information System on Coastal Areas and Lakes) project to contribute to the closure of the existing gap between space agencies and research institutions on one side and end users on the other side. To do so, we intend to create a data processor that automatically derives and subsequently delivers over the Internet, in Near-Real-Time (NRT), a number of data products tailored to individual end user needs. The data products will be generated using a Geographical Information System (GIS

  19. Apollo Project

    NASA Technical Reports Server (NTRS)

    1966-01-01

    From Spaceflight Revolution: 'Top NASA officials listen to a LOPO briefing at Langley in December 1966. Sitting to the far right with his hand on his chin is Floyd Thompson. To the left sits Dr. George Mueller, NASA associate administrator for Manned Space Flight. On the wall is a diagram of the sites selected for the 'concentrated mission.' 'The most fundamental issue in the pre-mission planning for Lunar Orbiter was how the moon was to be photographed. Would the photography be 'concentrated' on a predetermined single target, or would it be 'distributed' over several selected targets across the moon's surface? On the answer to this basic question depended the successful integration of the entire mission plan for Lunar Orbiter.' The Lunar Orbiter Project made systematic photographic maps of the lunar landing sites. Published in James R. Hansen, Spaceflight Revolution: NASA Langley Research Center From Sputnik to Apollo, (Washington: NASA, 1995), p. 337.

  20. Project Grandmaster

    SciTech Connect

    None, None

    2013-09-16

    The purpose of the Project Grandmaster Application is to allow individuals to opt-in and give the application access to data sources about their activities on social media sites. The application will cross-reference these data sources to build up a picture of each individual activities they discuss, either at present or in the past, and place this picture in reference to groups of all participants. The goal is to allow an individual to place themselves in the collective and to understand how their behavior patterns fit with the group and potentially find changes to make, such as activities they weren’t already aware of or different groups of interest they might want to follow.

  1. Project Grandmaster

    Energy Science and Technology Software Center (ESTSC)

    2013-09-16

    The purpose of the Project Grandmaster Application is to allow individuals to opt-in and give the application access to data sources about their activities on social media sites. The application will cross-reference these data sources to build up a picture of each individual activities they discuss, either at present or in the past, and place this picture in reference to groups of all participants. The goal is to allow an individual to place themselves inmore » the collective and to understand how their behavior patterns fit with the group and potentially find changes to make, such as activities they weren’t already aware of or different groups of interest they might want to follow.« less

  2. Apollo Project

    NASA Technical Reports Server (NTRS)

    1964-01-01

    Artists used paintbrushes and airbrushes to recreate the lunar surface on each of the four models comprising the LOLA simulator. Project LOLA or Lunar Orbit and Landing Approach was a simulator built at Langley to study problems related to landing on the lunar surface. It was a complex project that cost nearly $2 million dollars. James Hansen wrote: 'This simulator was designed to provide a pilot with a detailed visual encounter with the lunar surface; the machine consisted primarily of a cockpit, a closed-circuit TV system, and four large murals or scale models representing portions of the lunar surface as seen from various altitudes. The pilot in the cockpit moved along a track past these murals which would accustom him to the visual cues for controlling a spacecraft in the vicinity of the moon. Unfortunately, such a simulation--although great fun and quite aesthetic--was not helpful because flight in lunar orbit posed no special problems other than the rendezvous with the LEM, which the device did not simulate. Not long after the end of Apollo, the expensive machine was dismantled.' (p. 379) Ellis J. White further described LOLA in his paper 'Discussion of Three Typical Langley Research Center Simulation Programs,' 'Model 1 is a 20-foot-diameter sphere mounted on a rotating base and is scaled 1 in. = 9 miles. Models 2,3, and 4 are approximately 15x40 feet scaled sections of model 1. Model 4 is a scaled-up section of the Crater Alphonsus and the scale is 1 in. = 200 feet. All models are in full relief except the sphere.' Published in James R. Hansen, Spaceflight Revolution: NASA Langley Research Center From Sputnik to Apollo, (Washington: NASA, 1995), p. 379; From Ellis J. White, 'Discussion of Three Typical Langley Research Center Simulation Programs,' Paper presented at the Eastern Simulation Council (EAI's Princeton Computation Center), Princeton, NJ, October 20, 1966.

  3. Apollo Project

    NASA Technical Reports Server (NTRS)

    1965-01-01

    Artists used paintbrushes and airbrushes to recreate the lunar surface on each of the four models comprising the LOLA simulator. Project LOLA or Lunar Orbit and Landing Approach was a simulator built at Langley to study problems related to landing on the lunar surface. It was a complex project that cost nearly $2 million dollars. James Hansen wrote: 'This simulator was designed to provide a pilot with a detailed visual encounter with the lunar surface; the machine consisted primarily of a cockpit, a closed-circuit TV system, and four large murals or scale models representing portions of the lunar surface as seen from various altitudes. The pilot in the cockpit moved along a track past these murals which would accustom him to the visual cues for controlling a spacecraft in the vicinity of the moon. Unfortunately, such a simulation--although great fun and quite aesthetic--was not helpful because flight in lunar orbit posed no special problems other than the rendezvous with the LEM, which the device did not simulate. Not long after the end of Apollo, the expensive machine was dismantled.' (p. 379) Ellis J. White described the simulator as follows: 'Model 1 is a 20-foot-diameter sphere mounted on a rotating base and is scaled 1 in. = 9 miles. Models 2,3, and 4 are approximately 15x40 feet scaled sections of model 1. Model 4 is a scaled-up section of the Crater Alphonsus and the scale is 1 in. = 200 feet. All models are in full relief except the sphere.' Published in James R. Hansen, Spaceflight Revolution: NASA Langley Research Center From Sputnik to Apollo, (Washington: NASA, 1995), p. 379; Ellis J. White, 'Discussion of Three Typical Langley Research Center Simulation Programs,' Paper presented at the Eastern Simulation Council (EAI's Princeton Computation Center), Princeton, NJ, October 20, 1966.

  4. Apollo Project

    NASA Technical Reports Server (NTRS)

    1963-01-01

    Track, Model 2 and Model 1, the 20-foot sphere. Project LOLA or Lunar Orbit and Landing Approach was a simulator built at Langley to study problems related to landing on the lunar surface. It was a complex project that cost nearly $2 million dollars. James Hansen wrote: 'This simulator was designed to provide a pilot with a detailed visual encounter with the lunar surface; the machine consisted primarily of a cockpit, a closed-circuit TV system, and four large murals or scale models representing portions of the lunar surface as seen from various altitudes. The pilot in the cockpit moved along a track past these murals which would accustom him to the visual cues for controlling a spacecraft in the vicinity of the moon. Unfortunately, such a simulation--although great fun and quite aesthetic--was not helpful because flight in lunar orbit posed no special problems other than the rendezvous with the LEM, which the device did not simulate. Not long after the end of Apollo, the expensive machine was dismantled.' (p. 379) From Ellis J. White, 'Discussion of Three Typical Langley Research Center Simulation Programs,' Paper presented at the Eastern Simulation Council (EAI's Princeton Computation Center), Princeton, NJ, October 20, 1966. 'The model system is designed so that a television camera is mounted on a camera boom on each transport cart and each cart system is shared by two models. The cart's travel along the tracks represents longitudinal motion along the plane of a nominal orbit, vertical travel of the camera boom represents latitude on out-of-plane travel, and horizontal travel of the camera boom represents altitude changes.' Published in James R. Hansen, Spaceflight Revolution: NASA Langley Research Center From Sputnik to Apollo, (Washington: NASA, 1995), p. 379.

  5. Apollo Project

    NASA Technical Reports Server (NTRS)

    1964-01-01

    Artists used paintbrushes and airbrushes to recreate the lunar surface on each of the four models comprising the LOLA simulator. Project LOLA or Lunar Orbit and Landing Approach was a simulator built at Langley to study problems related to landing on the lunar surface. It was a complex project that cost nearly $2 million dollars. James Hansen wrote: 'This simulator was designed to provide a pilot with a detailed visual encounter with the lunar surface; the machine consisted primarily of a cockpit, a closed-circuit TV system, and four large murals or scale models representing portions of the lunar surface as seen from various altitudes. The pilot in the cockpit moved along a track past these murals which would accustom him to the visual cues for controlling a spacecraft in the vicinity of the moon. Unfortunately, such a simulation--although great fun and quite aesthetic--was not helpful because flight in lunar orbit posed no special problems other than the rendezvous with the LEM, which the device did not simulate. Not long after the end of Apollo, the expensive machine was dismantled.' (p. 379) Ellis J. White further described LOLA in his paper 'Discussion of Three Typical Langley Research Center Simulation Programs,' 'Model 1 is a 20-foot-diameter sphere mounted on a rotating base and is scaled 1 in. = 9 miles. Models 2,3, and 4 are approximately 15x40 feet scaled sections of model 1. Model 4 is a scaled-up section of the Crater Alphonsus and the scale is 1 in. = 200 feet. All models are in full relief except the sphere.' Published in James R. Hansen, Spaceflight Revolution: NASA Langley Research Center From Sputnik to Apollo, (Washington: NASA, 1995), p. 379; Ellis J. White, 'Discussion of Three Typical Langley Research Center Simulation Programs,' Paper presented at the Eastern Simulation Council (EAI's Princeton Computation Center), Princeton, NJ, October 20, 1966.

  6. Apollo Project

    NASA Technical Reports Server (NTRS)

    1964-01-01

    Construction of Model 1 used in the LOLA simulator. This was a twenty-foot sphere which simulated for the astronauts what the surface of the moon would look like from 200 miles up. Project LOLA or Lunar Orbit and Landing Approach was a simulator built at Langley to study problems related to landing on the lunar surface. It was a complex project that cost nearly $2 million dollars. James Hansen wrote: 'This simulator was designed to provide a pilot with a detailed visual encounter with the lunar surface; the machine consisted primarily of a cockpit, a closed-circuit TV system, and four large murals or scale models representing portions of the lunar surface as seen from various altitudes. The pilot in the cockpit moved along a track past these murals which would accustom him to the visual cues for controlling a spacecraft in the vicinity of the moon. Unfortunately, such a simulation--although great fun and quite aesthetic--was not helpful because flight in lunar orbit posed no special problems other than the rendezvous with the LEM, which the device did not simulate. Not long after the end of Apollo, the expensive machine was dismantled.' (p. 379) Ellis J. White wrote: 'Model 1 is a 20-foot-diameter sphere mounted on a rotating base and is scaled 1 in. = 9 miles. Models 2,3, and 4 are approximately 15x40 feet scaled sections of model 1. Model 4 is a scaled-up section of the Crater Alphonsus and the scale is 1 in. = 200 feet. All models are in full relief except the sphere.' Published in James R. Hansen, Spaceflight Revolution: NASA Langley Research Center From Sputnik to Apollo, (Washington: NASA, 1995), p. 379; Ellis J. White, 'Discussion of Three Typical Langley Research Center Simulation Programs,' Paper presented at the Eastern Simulation Council (EAI's Princeton Computation Center), Princeton, NJ, October 20, 1966.

  7. Apollo Project

    NASA Technical Reports Server (NTRS)

    1964-01-01

    Artists used paintbrushes and airbrushes to recreate the lunar surface on each of the four models comprising the LOLA simulator. Project LOLA or Lunar Orbit and Landing Approach was a simulator built at Langley to study problems related to landing on the lunar surface. It was a complex project that cost nearly $2 million dollars. James Hansen wrote: 'This simulator was designed to provide a pilot with a detailed visual encounter with the lunar surface; the machine consisted primarily of a cockpit, a closed-circuit TV system, and four large murals or scale models representing portions of the lunar surface as seen from various altitudes. The pilot in the cockpit moved along a track past these murals which would accustom him to the visual cues for controlling a spacecraft in the vicinity of the moon. Unfortunately, such a simulation--although great fun and quite aesthetic--was not helpful because flight in lunar orbit posed no special problems other than the rendezvous with the LEM, which the device did not simulate. Not long after the end of Apollo, the expensive machine was dismantled.' (p. 379) Ellis J. White further described LOLA in his paper 'Discussion of Three Typical Langley Research Center Simulation Programs,' 'Model 1 is a 20-foot-diameter sphere mounted on a rotating base and is scaled 1 in. = 9 miles. Models 2,3, and 4 are approximately 15x40 feet scaled sections of model 1. Model 4 is a scaled-up section of the Crater Alphonsus and the scale is 1 in. = 200 feet. All models are in full relief except the sphere.' Published in James R. Hansen, Spaceflight Revolution, NASA SP-4308, p. 379; Ellis J. White, 'Discussion of Three Typical Langley Research Center Simulation Programs,' Paper presented at the Eastern Simulation Council (EAI's Princeton Computation Center), Princeton, NJ, October 20, 1966.

  8. VIPER project

    NASA Technical Reports Server (NTRS)

    Kershaw, John

    1990-01-01

    The VIPER project has so far produced a formal specification of a 32 bit RISC microprocessor, an implementation of that chip in radiation-hard SOS technology, a partial proof of correctness of the implementation which is still being extended, and a large body of supporting software. The time has now come to consider what has been achieved and what directions should be pursued in the future. The most obvious lesson from the VIPER project was the time and effort needed to use formal methods properly. Most of the problems arose in the interfaces between different formalisms, e.g., between the (informal) English description and the HOL spec, between the block-level spec in HOL and the equivalent in ELLA needed by the low-level CAD tools. These interfaces need to be made rigorous or (better) eliminated. VIPER 1A (the latest chip) is designed to operate in pairs, to give protection against breakdowns in service as well as design faults. We have come to regard redundancy and formal design methods as complementary, the one to guard against normal component failures and the other to provide insurance against the risk of the common-cause failures which bedevil reliability predictions. Any future VIPER chips will certainly need improved performance to keep up with increasingly demanding applications. We have a prototype design (not yet specified formally) which includes 32 and 64 bit multiply, instruction pre-fetch, more efficient interface timing, and a new instruction to allow a quick response to peripheral requests. Work is under way to specify this device in MIRANDA, and then to refine the spec into a block-level design by top-down transformations. When the refinement is complete, a relatively simple proof checker should be able to demonstrate its correctness. This paper is presented in viewgraph form.

  9. Ace Project as a Project Management Tool

    ERIC Educational Resources Information Center

    Cline, Melinda; Guynes, Carl S.; Simard, Karine

    2010-01-01

    The primary challenge of project management is to achieve the project goals and objectives while adhering to project constraints--usually scope, quality, time and budget. The secondary challenge is to optimize the allocation and integration of resources necessary to meet pre-defined objectives. Project management software provides an active…

  10. Project Longshot

    NASA Technical Reports Server (NTRS)

    West, J. Curtis; Chamberlain, Sally A.; Stevens, Robert; Pagan, Neftali

    1989-01-01

    Project Longshot is an unmanned probe to our nearest star system, Alpha Centauri, 4.3 light years away. The Centauri system is a trinary system consisting of two central stars (A and B) orbiting a barycenter, and a third (Proxima Centauri) orbiting the two. The system is a declination of -67 degrees. The goal is to reach the Centauri system in 50 years. This time space was chosen because any shorter time would be impossible of the relativistic velocities involved, and any greater time would be impossible because of the difficulty of creating a spacecraft with such a long lifetime. Therefore, the following mission profile is proposed: (1) spacecraft is assembled in Earth orbit; (2) spacecraft escapes Earth and Sun in the ecliptic with a single impulse maneuver; (3) spacecraft changed declination to point toward Centauri system; (4) spacecraft accelerates to 0.1c; (5) spacecraft coasts at 0.1c for 41 years; (6) spacecraft decelerates upon reaching Centauri system; and (7) spacecraft orbits Centauri system, conducts investigations, and relays data to Earth. The total time to reach the Centauri system, taking into consideration acceleration and deceleration, will be approximately 50 years.

  11. Project LASER

    NASA Technical Reports Server (NTRS)

    1990-01-01

    NASA formally launched Project LASER (Learning About Science, Engineering and Research) in March 1990, a program designed to help teachers improve science and mathematics education and to provide 'hands on' experiences. It featured the first LASER Mobile Teacher Resource Center (MTRC), is designed to reach educators all over the nation. NASA hopes to operate several MTRCs with funds provided by private industry. The mobile unit is a 22-ton tractor-trailer stocked with NASA educational publications and outfitted with six work stations. Each work station, which can accommodate two teachers at a time, has a computer providing access to NASA Spacelink. Each also has video recorders and photocopy/photographic equipment for the teacher's use. MTRC is only one of the five major elements within LASER. The others are: a Space Technology Course, to promote integration of space science studies with traditional courses; the Volunteer Databank, in which NASA employees are encouraged to volunteer as tutors, instructors, etc; Mobile Discovery Laboratories that will carry simple laboratory equipment and computers to provide hands-on activities for students and demonstrations of classroom activities for teachers; and the Public Library Science Program which will present library based science and math programs.

  12. Project Information Packages Kit.

    ERIC Educational Resources Information Center

    RMC Research Corp., Mountain View, CA.

    Presented are an overview booklet, a project selection guide, and six Project Information Packages (PIPs) for six exemplary projects serving underachieving students in grades k through 9. The overview booklet outlines the PIP projects and includes a chart of major project features. A project selection guide reviews the PIP history, PIP contents,…

  13. Results of the Boeing/DOE DECC Phase 1 stirling engine project

    SciTech Connect

    STONE,KENNETH W.; CLARK,TERRY; NELVING,HANS; DIVER JR.,RICHARD B.

    2000-03-02

    Phase I of Boeing Company/DOE Dish Engine Critical Component (DECC) Project started in April of 1998 and was completed in 1999. The Phase I objectives, schedule, and test results are presented in this paper. These data shows the power, energy, and mirror performance are comparable to that when the hardware was first manufactured 15 years ago. During the Phase I and initial Phase II test period the on-sun system accumulated over 3,800 hours of solar-powered operating time, accumulated over 4,500 hours of concentrator solar tracking time, and generated over 50,000 kWh of grid-compatible electrical energy. The data also shows that the system was available 95 {percent} of the time when the sun's insolation level was above approximately 300 w/m{sup 2}, and achieved a daily energy efficiency between 20{percent} and 26{percent}. A second concentrator was refurbished during Phase I and accumulated over 2,200 hours of solar track time. A second Stirling engine operated 24 hours a day in a test cell in Sweden and accumulated over 6,000 test hours. Discussion of daily operation shows no major problems encountered during the testing that would prevent commercialization of the technology. Further analysis of the test data shows that system servicing with hydrogen, coolant and lubricating oil should not be a major O and M cost.

  14. RESOLVE Project

    NASA Technical Reports Server (NTRS)

    Parker, Ray; Coan, Mary; Cryderman, Kate; Captain, Janine

    2013-01-01

    The RESOLVE project is a lunar prospecting mission whose primary goal is to characterize water and other volatiles in lunar regolith. The Lunar Advanced Volatiles Analysis (LAVA) subsystem is comprised of a fluid subsystem that transports flow to the gas chromatograph - mass spectrometer (GC-MS) instruments that characterize volatiles and the Water Droplet Demonstration (WDD) that will capture and display water condensation in the gas stream. The LAVA Engineering Test Unit (ETU) is undergoing risk reduction testing this summer and fall within a vacuum chamber to understand and characterize component and integrated system performance. Testing of line heaters, printed circuit heaters, pressure transducers, temperature sensors, regulators, and valves in atmospheric and vacuum environments was done. Test procedures were developed to guide experimental tests and test reports to analyze and draw conclusions from the data. In addition, knowledge and experience was gained with preparing a vacuum chamber with fluid and electrical connections. Further testing will include integrated testing of the fluid subsystem with the gas supply system, near-infrared spectrometer, WDD, Sample Delivery System, and GC-MS in the vacuum chamber. This testing will provide hands-on exposure to a flight forward spaceflight subsystem, the processes associated with testing equipment in a vacuum chamber, and experience working in a laboratory setting. Examples of specific analysis conducted include: pneumatic analysis to calculate the WDD's efficiency at extracting water vapor from the gas stream to form condensation; thermal analysis of the conduction and radiation along a line connecting two thermal masses; and proportional-integral-derivative (PID) heater control analysis. Since LAVA is a scientific subsystem, the near-infrared spectrometer and GC-MS instruments will be tested during the ETU testing phase.

  15. Read with Me: A Children's Shared Literacy Project.

    ERIC Educational Resources Information Center

    Cooper, Linda Z.

    2003-01-01

    Describes a program that distributed refurbished books to children who might not have a book of their own. Discusses collaboration among school library media specialists, administration, teachers, parents, and community agencies; information literacy standards; empowering elementary students to help less fortunate children; and multiple learning…

  16. Supporting Multiple Programs and Projects at NASA's Kennedy Space Center

    NASA Technical Reports Server (NTRS)

    Stewart, Camiren L.

    2014-01-01

    With the conclusion of the shuttle program in 2011, the National Aeronautics and Space Administration (NASA) had found itself at a crossroads for finding transportation of United States astronauts and experiments to space. The agency would eventually hand off the taxiing of American astronauts to the International Space Station (ISS) that orbits in Low Earth Orbit (LEO) about 210 miles above the earth under the requirements of the Commercial Crew Program (CCP). By privatizing the round trip journey from Earth to the ISS, the space agency has been given the additional time to focus funding and resources to projects that operate beyond LEO; however, adding even more stress to the agency, the premature cancellation of the program that would succeed the Shuttle Program - The Constellation Program (CxP) -it would inevitably delay the goal to travel beyond LEO for a number of years. Enter the Space Launch System (SLS) and the Orion Multipurpose Crew Vehicle (MPCV). Currently, the SLS is under development at NASA's Marshall Spaceflight Center in Huntsville, Alabama, while the Orion Capsule, built by government contractor Lockheed Martin Corporation, has been assembled and is currently under testing at the Kennedy Space Center (KSC) in Florida. In its current vision, SLS will take Orion and its crew to an asteroid that had been captured in an earlier mission in lunar orbit. Additionally, this vehicle and its configuration is NASA's transportation to Mars. Engineers at the Kennedy Space Center are currently working to test the ground systems that will facilitate the launch of Orion and the SLS within its Ground Services Development and Operations (GSDO) Program. Firing Room 1 in the Launch Control Center (LCC) has been refurbished and outfitted to support the SLS Program. In addition, the Spaceport Command and Control System (SCCS) is the underlying control system for monitoring and launching manned launch vehicles. As NASA finds itself at a junction, so does all of its

  17. Project summary

    NASA Technical Reports Server (NTRS)

    1991-01-01

    California Polytechnic State University's design project for the 1990-91 school year was the design of a close air support aircraft. There were eight design groups that participated and were given requests for proposals. These proposals contained mission specifications, particular performance and payload requirements, as well as the main design drivers. The mission specifications called for a single pilot weighing 225 lb with equipment. The design mission profile consisted of the following: (1) warm-up, taxi, take off, and accelerate to cruise speed; (2) dash at sea level at 500 knots to a point 250 nmi from take off; (3) combat phase, requiring two combat passes at 450 knots that each consist of a 360 deg turn and an energy increase of 4000 ft. - at each pass, half of air-to-surface ordnance is released; (4) dash at sea level at 500 knots 250 nmi back to base; and (5) land with 20 min of reserve fuel. The request for proposal also specified the following performance requirements with 50 percent internal fuel and standard stores: (1) the aircraft must be able to accelerate from Mach 0.3 to 0.5 at sea level in less than 20 sec; (2) required turn rates are 4.5 sustained g at 450 knots at sea level; (3) the aircraft must have a reattack time of 25 sec or less (reattack time was defined as the time between the first and second weapon drops); (4) the aircraft is allowed a maximum take off and landing ground roll of 2000 ft. The payload requirements were 20 Mk 82 general-purpose free-fall bombs and racks; 1 GAU-8A 30-mm cannon with 1350 rounds; and 2 AIM-9L Sidewinder missiles and racks. The main design drivers expressed in the request for proposal were that the aircraft should be survivable and maintainable. It must be able to operate in remote areas with little or no maintenance. Simplicity was considered the most important factor in achieving the former goal. In addition, the aircraft must be low cost both in acquisition and operation. The summaries of the aircraft

  18. RESOLVE Project

    NASA Technical Reports Server (NTRS)

    Parker, Ray O.

    2012-01-01

    The RESOLVE project is a lunar prospecting mission whose primary goal is to characterize water and other volatiles in lunar regolith. The Lunar Advanced Volatiles Analysis (LAVA) subsystem is comprised of a fluid subsystem that transports flow to the gas chromatograph- mass spectrometer (GC-MS) instruments that characterize volatiles and the Water Droplet Demonstration (WDD) that will capture and display water condensation in the gas stream. The LAVA Engineering Test Unit (ETU) is undergoing risk reduction testing this summer and fall within a vacuum chamber to understand and characterize C!Jmponent and integrated system performance. Ray will be assisting with component testing of line heaters, printed circuit heaters, pressure transducers, temperature sensors, regulators, and valves in atmospheric and vacuum environments. He will be developing procedures to guide these tests and test reports to analyze and draw conclusions from the data. In addition, he will gain experience with preparing a vacuum chamber with fluid and electrical connections. Further testing will include integrated testing of the fluid subsystem with the gas supply system, near-infrared spectrometer, WDD, Sample Delivery System, and GC-MS in the vacuum chamber. This testing will provide hands-on exposure to a flight forward spaceflight subsystem, the processes associated with testing equipment in a vacuum chamber, and experience working in a laboratory setting. Examples of specific analysis Ray will conduct include: pneumatic analysis to calculate the WOO's efficiency at extracting water vapor from the gas stream to form condensation; thermal analysis of the conduction and radiation along a line connecting two thermal masses; and proportional-integral-derivative (PID) heater control analysis. In this Research and Technology environment, Ray will be asked to problem solve real-time as issues arise. Since LAVA is a scientific subsystem, Ray will be utilizing his chemical engineering background to

  19. Integrated Project Management System description. [UMTRAP Project

    SciTech Connect

    Not Available

    1987-03-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project is a Department of Energy (DOE) designated Major System Acquisition (MSA). To execute and manage the Project mission successfully and to comply with the MSA requirements, the UMTRA Project Office ( Project Office'') has implemented and operates an Integrated Project Management System (IPMS). The Project Office is assisted by the Technical Assistance Contractor's (TAC) Project Integration and Control (PIC) Group in system operation. Each participant, in turn, provides critical input to system operation and reporting requirements. The IPMS provides a uniform structured approach for integrating the work of Project participants. It serves as a tool for planning and control, workload management, performance measurement, and specialized reporting within a standardized format. This system description presents the guidance for its operation. Appendices 1 and 2 contain definitions of commonly used terms and abbreviations and acronyms, respectively. 17 figs., 5 tabs.

  20. The Hairy Head Project.

    ERIC Educational Resources Information Center

    Gallick, Barbara

    A class of 3- to 6-year-old children in a Midwestern child care center chose to study hair and hairstyling salons as a group project. This article discusses how the project evolved, describes the three phases of the project, and provides the teacher's reflections on the project. Photos taken during the project are included. (Author)

  1. Project Panama: An International Service Project

    ERIC Educational Resources Information Center

    Aydlett, Lydia; Randolph, Mickey; Wells, Gayle

    2010-01-01

    Participation in service learning projects is a growing phenomenon at universities and colleges. Research indicates service projects are beneficial for college students and adults. There is little data investigating developmental differences in how younger versus older participants perceive the service learning process. In this project, older…

  2. Project CREST, Gainesville, Florida. An Exemplary Project.

    ERIC Educational Resources Information Center

    DeJong, William; Stewart, Carolyn

    This manual describes Project CREST (Clinical Regional Support Teams), a community project established in Gainesville, Florida, to supplement State probation services by providing professional counseling to delinquent youth. The project uses a dual treatment approach in which, on the one hand, probation officers impose restrictions, while on the…

  3. Managing Projects for Change: Contextualised Project Management

    ERIC Educational Resources Information Center

    Tynan, Belinda; Adlington, Rachael; Stewart, Cherry; Vale, Deborah; Sims, Rod; Shanahan, Peter

    2010-01-01

    This paper will detail three projects which focussed on enhancing online learning at a large Australian distance education University within a School of Business, School of Health and School of Education. Each project had special funding and took quite distinctive project management approaches, which reflect the desire to embed innovation and…

  4. Elementary School Projects.

    ERIC Educational Resources Information Center

    Learning By Design, 2001

    2001-01-01

    Highlights elementary school construction projects that have won the Learning By Design Awards for 2001. Projects covered involve new school construction; and renovation, additions, and restoration. (GR)

  5. Korea's School Grounds Projects

    ERIC Educational Resources Information Center

    Park, Joohun

    2003-01-01

    This article describes two projects which Korea has undertaken to improve its school grounds: (1) the Green School Project; and (2) the School Forest Pilot Project. The Korean Ministry of Education and Human Resources Development (MOE&HRI) recently launched the Green School Project centred on existing urban schools with poor outdoor environments.…

  6. Project Follow Through.

    ERIC Educational Resources Information Center

    Illinois State Office of the Superintendent of Public Instruction, Springfield. Dept. for Exceptional Children.

    The four Follow Through projects in Illinois are described and evaluated. These projects involve approximately 1,450 children in K-3 in Mounds, East Saint Louis, Waukegan, and Chicago. The Chicago project is subdivided into three individual projects and is trying three experimental programs. Emphasis is given to the nature of the environmental…

  7. eProject Builder

    Energy Science and Technology Software Center (ESTSC)

    2014-06-01

    eProject Builder enables Energy Services Companies (ESCOs) and their contracting agencies to: 1. upload and track project-level Information 2. generate basic project reports required by local, state, and/or federal agencies 3. benchmark new Energy Savings Performance Contract (ESPC) projects against historical data

  8. The 100 People Project

    ERIC Educational Resources Information Center

    McLeod, Keri

    2007-01-01

    This article describes the 100 People Project and how the author integrates the project in her class. The 100 People Project is a nonprofit organization based in New York City. The organization poses the question: If there were only 100 people in the world, what would the world look like? Through the project, students were taught about ethics in…

  9. Determinants of project success

    NASA Technical Reports Server (NTRS)

    Murphy, D. C.; Baker, B. N.; Fisher, D.

    1974-01-01

    The interactions of numerous project characteristics, with particular reference to project performance, were studied. Determinants of success are identified along with the accompanying implications for client organization, parent organization, project organization, and future research. Variables are selected which are found to have the greatest impact on project outcome, and the methodology and analytic techniques to be employed in identification of those variables are discussed.

  10. Earth System Science Project

    ERIC Educational Resources Information Center

    Rutherford, Sandra; Coffman, Margaret

    2004-01-01

    For several decades, science teachers have used bottles for classroom projects designed to teach students about biology. Bottle projects do not have to just focus on biology, however. These projects can also be used to engage students in Earth science topics. This article describes the Earth System Science Project, which was adapted and developed…

  11. Project Lodestar Special Report.

    ERIC Educational Resources Information Center

    Brown, Peggy, Ed.

    1981-01-01

    The Association of American Colleges' (AAC) Project Lodestar is addressed in an article and descriptions of the pilot phase of the project at 13 institutions. In "Project Lodestar: Realistically Assessing the Future," Peggy Brown provides an overview of the project, which is designed to help colleges and universities in assessment of institutional…

  12. NCMS ESS 2000 Project

    NASA Technical Reports Server (NTRS)

    Gibbel, Mark; Bellamy, Marvin; DeSantis, Charlie; Hess, John; Pattok, Tracy; Quintero, Andrew; Silver, R.

    1996-01-01

    ESS 2000 has the vision of enhancing the knowledge necessary to implement cost-effective, leading-edge ESS technologies and procedures in order to increase U.S. electronics industry competitiveness. This paper defines EES and discusses the factors driving the project, the objectives of the project, its participants, the three phases of the project, the technologies involved, and project deliverables.

  13. Guidelines for Project Management

    NASA Technical Reports Server (NTRS)

    Ben-Arieh, David

    2001-01-01

    Project management is an important part of the professional activities at Kennedy Space Center (KSC). Project management is the means by which many of the operations at KSC take shape. Moreover, projects at KSC are implemented in a variety of ways in different organizations. The official guidelines for project management are provided by NASA headquarters and are quite general. The project reported herein deals with developing practical and detailed project management guidelines in support of the project managers. This report summarizes the current project management effort in the Process Management Division and presents a new modeling approach of project management developed by the author. The report also presents the Project Management Guidelines developed during the summer.

  14. Grover Cleveland School, Boston, Massachusetts. Refurbishment and Status Report.

    ERIC Educational Resources Information Center

    General Electric Co., Philadelphia, PA.

    The solar heating system is a retrofit installation on the roof of the Grover Cleveland Middle School in Boston. The system includes 4,600 square feet of flat plate collectors, a 2,000 gallon solar energy storage tank, plus the required structural steel, piping, insulation, pumps, heat exchangers, and controls to heat the air supplied by two…

  15. Observing Supernova 1987A with the Refurbished Hubble Space Telescope

    NASA Technical Reports Server (NTRS)

    France, Kevin; McCray, Richard; Heng, Kevin; Kirshner, Robert P.; Challis, Peter; Bouchet, Patrice; Crotts, Arlin; Dwek, Eli; Fransson, Claes; Garnavich, Peter M.; Larsson, Josefin; Lundqvist, Peter; Panagia, Nino; Pun, Chun S. J.; Smith, Nathan; Sollerman, Jesper; Sonneborn, George; Stocke, John T.; Wheeler, J. Craig

    2010-01-01

    The young remnant of supernova 1987A (SN 1987A) offers an unprecedented glimpse into the hydrodynamics and kinetics of fast astrophysical shocks. We have been monitoring SN 1987A with the Hubble Space Telescope (HST) since it was launched. The recent repair of the Space Telescope Imaging Spectrograph (STIS) allows us to compare observations in 2004, just before its demise, with those in 2010, shortly after its resuscitation by NASA astronauts. We find that the Ly-alpha and H-alpha lines from shock emission continue to brighten, while their maximum velocities continue to decrease. We report evidence for nearly coherent, resonant scattering of Lya photons (to blueshifts approximately -12,000 km /s) from hotspots on the equatorial ring. We also report emission to the red of Ly-alpha that we attribute to N v lambda lambda 1239,1243 Angstrom line emission. These lines are detectable because, unlike hydrogen atoms, N4+ ions emit hundreds of photons before they are ionized. The profiles of the N v lines differ markedly from that of H-alpha. We attribute this to scattering of N4+ ions by magnetic fields in the ionized plasma. Thus, N v emission provides a unique probe of the isotropization zone of the collisionless shock. Observations with the recently installed Cosmic Origins Spectrograph (COS) will enable us to observe the N v lambda lambda 1239,1243 Angstrom line profiles with much higher signal-to-noise ratios than possible with STIS and may reveal lines of other highly ionized species (such as C IVlambda lambda 1548,1551 Angstrom) that will test our explanation for the N v emission

  16. Hubble Space Telescope maintenance and refurbishment planning analysis

    NASA Technical Reports Server (NTRS)

    Pizzano, F.; Kincade, R. S.

    1989-01-01

    This paper presents an updated analytical approach toward the identification of Hubble Space Telescope system failures and downstates, maintenance requirements, and overall support to maintenance mission planning. Different sparing options of Orbital Replacement Units are evaluated, and the optimum spares complement that satisfies the expected servicing requirements is identified. Specific Space Telescope Reliability and maintenance Simulation Computer Program (SPATEL) updates and refinements are reported, and input data updates relevant to failure rates, downstate ground rules, and maintenance policy are addressed. A summary of the latest SPATEL outputs is provided along with maintenance analysis results.

  17. Replacement/Refurbishment of JSC/NASA POD Specimens

    NASA Technical Reports Server (NTRS)

    Castner, Willard L.

    2010-01-01

    The NASA Special NDE certification process requires demonstration of NDE capability by test per NASA-STD-5009. This test is performed with fatigue cracked specimens containing very small cracks. The certification test results are usually based on binomial statistics and must meet a 90/95 Probability of Detection (POD). The assumption is that fatigue cracks are tightly closed, difficult to detect, and inspectors and processes passing such a test are well qualified for inspecting NASA fracture critical hardware. The JSC NDE laboratory has what may be the largest inventory that exists of such fatigue cracked NDE demonstration specimens. These specimens were produced by the hundreds in the late 1980s and early 1990s. None have been produced since that time and the condition and usability of the specimens are questionable.

  18. NSF Funded Projects: Perspectives of Project Leaders.

    ERIC Educational Resources Information Center

    Custer, Rodney L.; Loepp, Franzie; Martin, G. Eugene

    2000-01-01

    A survey of 23 principal investigators of National Science Foundation-funded projects identified the chief facilitating factor to be direct contact with program officers. They had difficulties conceptualizing and envisioning their projects, finding time and confidence for writing proposals, and dealing with the complexity of the guidelines and the…

  19. Canadian Urban Dynamics Project. Project Canada West.

    ERIC Educational Resources Information Center

    Western Curriculum Project on Canada Studies, Edmonton (Alberta).

    This is a progress report of a curriculum development project aimed at involving students in community and regional development by creating an awareness of urban problems and instilling a sense of positive self worth and capability which will stimulate active community participation. Initial planning of the project is reported in ED 055 017. The…

  20. Project Argo: The design and analysis of an all-propulsive and an aeroassisted version of a manned space transportation vehicle

    NASA Technical Reports Server (NTRS)

    1989-01-01

    Project Argo is the design of a manned Space Transportation Vehicle (STV) that would transport payloads between LEO (altitude lying between 278 to 500 km above the Earth) and GEO (altitude is approximately 35,800 km above the Earth) and would be refueled and refurbished at the Space Station Freedom. Argo would be man's first space-based manned vehicle and would provide a crucial link to geosynchronous orbit where the vast majority of satellites are located. The vehicle could be built and launched shortly after the space station and give invaluable space experience while serving as a workhorse to deliver and repair satellites. Eventually, if a manned space station is established in GEO, then Argo could serve as the transport between the Space Station Freedom and a Geostation. If necessary, modifications could be made to allow the vehicle to reach the moon or possibly Mars. Project Argo is unique in that it consists of the design and comparison of two different concepts to accomplish the same mission. The first is an all-propulsive vehicle which uses chemical propulsion for all of its major maneuvers between LEO and GEO. The second is a vehicle that uses aeroassisted braking during its return from GEO to LEO by passing through the upper portions of the atmosphere.

  1. The Alzheimer's Project

    MedlinePlus

    ... Bar Home Current Issue Past Issues The Alzheimer's Project Past Issues / Spring 2009 Table of Contents For ... this page please turn Javascript on. The Alzheimer's Project A 4-Part Documentary Series Starting May 10 ...

  2. Elective Program Projects

    ERIC Educational Resources Information Center

    Estrada, Christelle

    1976-01-01

    Outlined is an interdisciplinary program in Ecology and Oceanography for grades six through eight. Numerous student projects are suggested in the outline and the course requirements and the project system are explained. (MA)

  3. The Alzheimer's Project

    MedlinePlus

    ... Navigation Bar Home Current Issue Past Issues The Alzheimer's Project Past Issues / Spring 2009 Table of Contents ... of this page please turn Javascript on. The Alzheimer's Project A 4-Part Documentary Series Starting May ...

  4. Venezuela's Bolivarian Schools Project.

    ERIC Educational Resources Information Center

    Diaz, Maria Magnolia Santamaria

    2002-01-01

    Discusses efforts by the Venezuelan government to improve the nation's school infrastructure through the Bolivarian Schools Project administered by the Ministry of Education, Culture and Sport. The project set educational principles which are guiding current school building efforts. (EV)

  5. GHPsRUS Project

    DOE Data Explorer

    Battocletti, Liz

    2013-07-09

    The GHPsRUS Project's full name is "Measuring the Costs and Benefits of Nationwide Geothermal Heat Pump Deployment." The dataset contains employment and installation price data collected by four economic surveys: (1)GHPsRUS Project Manufacturer & OEM Survey, (2) GHPsRUS Project Geothermal Loop Survey, (3) GHPsRUS Project Mechanical Equipment Installation Survey, and (4) GHPsRUS Geothermal Heat Pump Industry Survey

  6. Ideas for Science Projects.

    ERIC Educational Resources Information Center

    Showalter, Victor; Slesnick, Irwin

    This booklet was written for students as a source of ideas for research type science projects. Part One shows how three high school students developed individual projects a s a result of asking questions about the same natural phenomena. Part Two contains project suggestions and sample questions designed to stimulate student thinking along…

  7. Toll Gate Metrication Project

    ERIC Educational Resources Information Center

    Izzi, John

    1974-01-01

    The project director of the Toll Gate Metrication Project describes the project as the first structured United States public school educational experiment in implementing change toward the adoption of the International System of Units. He believes the change will simplify, rather than complicate, the educational task. (AG)

  8. Visible Human Project

    MedlinePlus

    ... Mobile Gallery Site Navigation Home The Visible Human Project ® Overview The Visible Human Project ® is an outgrowth of the NLM's 1986 Long- ... The long-term goal of the Visible Human Project ® is to produce a system of knowledge structures ...

  9. THE ATLANTA SUPERSITE PROJECT

    EPA Science Inventory

    The Atlanta Supersites project is the first of two Supersites projects to be established during Phase I of EPA's Supersites Program; Phase 11 is being established through a Request for Assistance. The other initial project is in Fresno, California. The Supersites Program is par...

  10. Of Principals and Projects.

    ERIC Educational Resources Information Center

    Wyant, Spencer H.; And Others

    Principals play an important role in the success of externally funded change projects in their schools. Interviews exploring the participation of principals in such projects in 14 Oregon elementary and secondary schools provided 11 case studies illustrating helpful and unhelpful behaviors. The projects were found to have life cycles of their own,…

  11. The Proposal Project

    ERIC Educational Resources Information Center

    Pierce, Elizabeth

    2007-01-01

    The proposal project stretches over a significant portion of the semester-long sophomore course Professional Communication (ENG 250) at Monroe Community College. While developing their proposal project, students need to use time management skills to successfully complete a quality project on time. In addition, excellent oral and written…

  12. Kansas Advanced Semiconductor Project

    SciTech Connect

    Baringer, P.; Bean, A.; Bolton, T.; Horton-Smith, G.; Maravin, Y.; Ratra, B.; Stanton, N.; von Toerne, E.; Wilson, G.

    2007-09-21

    KASP (Kansas Advanced Semiconductor Project) completed the new Layer 0 upgrade for D0, assumed key electronics projects for the US CMS project, finished important new physics measurements with the D0 experiment at Fermilab, made substantial contributions to detector studies for the proposed e+e- international linear collider (ILC), and advanced key initiatives in non-accelerator-based neutrino physics.

  13. Library Digitisation Project Management.

    ERIC Educational Resources Information Center

    Middleton, Michael

    Supervision of library digitization is the focus of this paper. First outlined are the definition, formalization, implementation, and completion phases of project management. Descriptions of management decisions involved in digitization projects follow on matters such as: collection analysis, resourcing, project personnel, production, access and…

  14. The Sidewalk Project

    ERIC Educational Resources Information Center

    Church, William

    2005-01-01

    In this article, the author features "the sidewalk project" in Littleton High School. The sidewalk project is a collaboration of more than 40 high school physics students, 10 local mentors, and a few regional and national organizations who worked together to invent a way to heat a sidewalk with an alternative energy source. The project, which…

  15. Project ASTRO: A Partnership.

    ERIC Educational Resources Information Center

    Rothenberger, Lisa

    2001-01-01

    Describes a project that enriches astronomy lessons with hands-on activities facilitated by an astronomer. The project links professional and amateur astronomers with middle-level classroom teachers and informal educators. Families and community organizations are also involved in the project. Provides information on how to join the ASTRO network.…

  16. Projection: A Bibliography.

    ERIC Educational Resources Information Center

    Pedrini, D. T.; Pedrini, Bonnie C.

    Sigmund Freud and his associates did much clinical work with the dynamic of projection, especially with regard to paranoid symptoms and syndromes. Much experimental work has also been done with projection. Sears evaluated the results of some of those studies. Murstein and Pryer sub-classified projection and reviewed typical studies. The…

  17. The Illinois Rivers Project.

    ERIC Educational Resources Information Center

    Williams, Robert A.; And Others

    The Illinois Rivers Project was developed as an integrated, multidimensional science/technology/society pilot project designed to introduce water quality dimensions into Illinois high schools. The project involved high school science, social science, and English teachers in an integrated study of their local river and community. Science students…

  18. The Eggen Card Project

    NASA Astrophysics Data System (ADS)

    Silvis, G.

    2014-06-01

    (Abstract only) Olin Eggen, noted astronomer (1919-1998), left to us all his raw observation records recorded on 3x5 cards. This project is to make all this data available as an online resource. History and progress of the project will be presented. Project details available at: https://sites.google.com/site/eggencards/home.

  19. Humane Education Projects Handbook.

    ERIC Educational Resources Information Center

    Junior League of Ogden, UT.

    This handbook was developed to promote interest in humane education and to encourage the adoption of humane education projects. Although specifically designed to assist Junior Leagues in developing such projects, the content should prove valuable to animal welfare organizations, zoos, aquariums, nature centers, and other project-oriented groups…

  20. Underestimation of Project Costs

    NASA Technical Reports Server (NTRS)

    Jones, Harry W.

    2015-01-01

    Large projects almost always exceed their budgets. Estimating cost is difficult and estimated costs are usually too low. Three different reasons are suggested: bad luck, overoptimism, and deliberate underestimation. Project management can usually point to project difficulty and complexity, technical uncertainty, stakeholder conflicts, scope changes, unforeseen events, and other not really unpredictable bad luck. Project planning is usually over-optimistic, so the likelihood and impact of bad luck is systematically underestimated. Project plans reflect optimism and hope for success in a supposedly unique new effort rather than rational expectations based on historical data. Past project problems are claimed to be irrelevant because "This time it's different." Some bad luck is inevitable and reasonable optimism is understandable, but deliberate deception must be condemned. In a competitive environment, project planners and advocates often deliberately underestimate costs to help gain project approval and funding. Project benefits, cost savings, and probability of success are exaggerated and key risks ignored. Project advocates have incentives to distort information and conceal difficulties from project approvers. One naively suggested cure is more openness, honesty, and group adherence to shared overall goals. A more realistic alternative is threatening overrun projects with cancellation. Neither approach seems to solve the problem. A better method to avoid the delusions of over-optimism and the deceptions of biased advocacy is to base the project cost estimate on the actual costs of a large group of similar projects. Over optimism and deception can continue beyond the planning phase and into project execution. Hard milestones based on verified tests and demonstrations can provide a reality check.

  1. Managing Projects with KPRO

    NASA Technical Reports Server (NTRS)

    Braden, Barry M.

    2004-01-01

    How does a Project Management Office provide: Consistent, familiar, easily used scheduling tools to Project Managers and project team members? Provide a complete list of organization resources available for use on the project? Facilitate resource tracking and visibility? Provide the myriad reports that the organization requires? Facilitate consistent budget planning and cost performance information? Provide all of this to the entire organization? Provide for the unique requirement of the organization? and get people to use it? Answer: Implementation of the Kennedy space Center Projects and Resources Online (KPRO), a modified COTS solution.

  2. Molten-Caustic-Leaching (Gravimelt) System Integration Project, Phase 2

    SciTech Connect

    Not Available

    1993-02-01

    The objective of the task (Task 6) covered in this document was to operate the refurbished/modified test circuit of the Gravimeh Process in a continuous integrated manner to obtain the engineering and operational data necessary to assess the technical performance and reliability of the circuit. This data is critical to the development of this technology as a feasible means of producing premium clean burning fuels that meet New Source Performance Standards (NSPS). Significant refurbishments and design modifications had been made to the facility (in particular to the vacuum filtration and evaporation units) during Tasks 1 and 2, followed by off-line testing (Task 3). Two weeks of continuous around-the-clock operation of the refurbished/modified MCL test circuit were performed. During the second week of testing, all sections of the plant were operated in an integrated fashion for an extended period of time, including a substantial number of hours of on-stream time for the vacuum filters and the caustic evaporation unit. A new process configuration was tested in which centrate from the acid wash train (without acid addition) was used as the water makeup for the water wash train, thus-eliminating the one remaining process waste water stream. A 9-inch centrifuge was tested at various solids loadings and at flow rates up to 400 lbs/hr of coal feed to obtain a twenty-fold scaleup factor over the MCL integrated test facility centrifuge performance data.

  3. ALS Project Management Manual

    SciTech Connect

    Krupnick, Jim; Harkins, Joe

    2000-05-01

    This manual has been prepared to help establish a consistent baseline of management practices across all ALS projects. It describes the initial process of planning a project, with a specific focus on the production of a formal project plan. We feel that the primary weakness in ALS project management efforts to date stems from a failure to appreciate the importance of ''up-front'' project planning. In this document, we present a guide (with examples) to preparing the documents necessary to properly plan, monitor, and control a project's activities. While following the manual will certainly not guarantee good project management, failure to address the issues we raise will dramatically reduce the chance of success. Here we define success as meeting the technical goals on schedule and within the prescribed budget.

  4. Development of analytical cell support for vitrification at the West Valley Demonstration Project. Topical report

    SciTech Connect

    Barber, F.H.; Borek, T.T.; Christopher, J.Z.

    1997-12-01

    Analytical and Process Chemistry (A&PC) support is essential to the high-level waste vitrification campaign at the West Valley Demonstration Project (WVDP). A&PC characterizes the waste, providing information necessary to formulate the recipe for the target radioactive glass product. High-level waste (HLW) samples are prepared and analyzed in the analytical cells (ACs) and Sample Storage Cell (SSC) on the third floor of the main plant. The high levels of radioactivity in the samples require handling them in the shielded cells with remote manipulators. The analytical hot cells and third floor laboratories were refurbished to ensure optimal uninterrupted operation during the vitrification campaign. New and modified instrumentation, tools, sample preparation and analysis techniques, and equipment and training were required for A&PC to support vitrification. Analytical Cell Mockup Units (ACMUs) were designed to facilitate method development, scientist and technician training, and planning for analytical process flow. The ACMUs were fabricated and installed to simulate the analytical cell environment and dimensions. New techniques, equipment, and tools could be evaluated m in the ACMUs without the consequences of generating or handling radioactive waste. Tools were fabricated, handling and disposal of wastes was addressed, and spatial arrangements for equipment were refined. As a result of the work at the ACMUs the remote preparation and analysis methods and the equipment and tools were ready for installation into the ACs and SSC m in July 1995. Before use m in the hot cells, all remote methods had been validated and four to eight technicians were trained on each. Fine tuning of the procedures has been ongoing at the ACs based on input from A&PC technicians. Working at the ACs presents greater challenges than had development at the ACMUs. The ACMU work and further refinements m in the ACs have resulted m in a reduction m in analysis turnaround time (TAT).

  5. Project Surveillance and Maintenance Plan. [UMTRA Project

    SciTech Connect

    Not Available

    1985-09-01

    The Project Surveillance and Maintenance Plan (PSMP) describes the procedures that will be used by the US Department of Energy (DOE), or other agency as designated by the President to verify that inactive uranium tailings disposal facilities remain in compliance with licensing requirements and US Environmental Protection Agency (EPA) standards for remedial actions. The PSMP will be used as a guide for the development of individual Site Surveillance and Maintenance Plans (part of a license application) for each of the UMTRA Project sites. The PSMP is not intended to provide minimum requirements but rather to provide guidance in the selection of surveillance measures. For example, the plan acknowledges that ground-water monitoring may or may not be required and provides the (guidance) to make this decision. The Site Surveillance and Maintenance Plans (SSMPs) will form the basis for the licensing of the long-term surveillance and maintenance of each UMTRA Project site by the NRC. Therefore, the PSMP is a key milestone in the licensing process of all UMTRA Project sites. The Project Licensing Plan (DOE, 1984a) describes the licensing process. 11 refs., 22 figs., 8 tabs.

  6. River Protection Project (RPP) Project Management Plan

    SciTech Connect

    SEEMAN, S.E.

    2000-04-01

    The U.S. Department of Energy (DOE), in accordance with the Strom Thurmond National Defense Authorization Act for Fiscal Year 1999, established the Office of River Protection (ORP) to successfully execute and manage the River Protection Project (RPP), formerly known as the Tank Waste Remediation System (TWRS). The mission of the RPP is to store, retrieve, treat, and dispose of the highly radioactive Hanford tank waste in an environmentally sound, safe, and cost-effective manner. The team shown in Figure 1-1 is accomplishing the project. The ORP is providing the management and integration of the project; the Tank Farm Contractor (TFC) is responsible for providing tank waste storage, retrieval, and disposal; and the Privatization Contractor (PC) is responsible for providing tank waste treatment.

  7. Pine Hollow Watershed Project : FY 2000 Projects.

    SciTech Connect

    Sherman County Soil and Water Conservation District

    2001-06-01

    The Pine Hollow Project (1999-010-00) is an on-going watershed restoration effort administered by Sherman County Soil and Water Conservation District and spearheaded by Pine Hollow/Jackknife Watershed Council. The headwaters are located near Shaniko in Wasco County, and the mouth is in Sherman County on the John Day River. Pine Hollow provides more than 20 miles of potential summer steelhead spawning and rearing habitat. The watershed is 92,000 acres. Land use is mostly range, with some dryland grain. There are no water rights on Pine Hollow. Due to shallow soils, the watershed is prone to rapid runoff events which scour out the streambed and the riparian vegetation. This project seeks to improve the quality of upland, riparian and in-stream habitat by restoring the natural hydrologic function of the entire watershed. Project implementation to date has consisted of construction of water/sediment control basins, gradient terraces on croplands, pasture cross-fences, upland water sources, and grass seeding on degraded sites, many of which were crop fields in the early part of the century. The project is expected to continue through about 2007. From March 2000 to June 2001, the Pine Hollow Project built 6 sediment basins, 1 cross-fence, 2 spring developments, 1 well development, 1 solar pump, 50 acres of native range seeding and 1 livestock waterline. FY2000 projects were funded by BPA, Oregon Watershed Enhancement Board, US Fish and Wildlife Service and landowners. In-kind services were provided by Sherman County Soil and Water Conservation District, USDA Natural Resources Conservation Service, USDI Bureau of Land Management, Oregon Department of Fish and Wildlife, Pine Hollow/Jackknife Watershed Council, landowners and Wasco County Soil and Water Conservation District.

  8. Environmental Science: 49 Science Fair Projects. Science Fair Projects Series.

    ERIC Educational Resources Information Center

    Bonnet, Robert L.; Keen, G. Daniel

    This book contains 49 science fair projects designed for 6th to 9th grade students. Projects are organized by the topics of soil, ecology (projects in habitat and life cycles), pests and controls (projects in weeds and insects), recycling (projects in resources and conservation), waste products (projects in decomposition), microscopic organisms,…

  9. Battleground Energy Recovery Project

    SciTech Connect

    Bullock, Daniel

    2011-12-31

    In October 2009, the project partners began a 36-month effort to develop an innovative, commercial-scale demonstration project incorporating state-of-the-art waste heat recovery technology at Clean Harbors, Inc., a large hazardous waste incinerator site located in Deer Park, Texas. With financial support provided by the U.S. Department of Energy, the Battleground Energy Recovery Project was launched to advance waste heat recovery solutions into the hazardous waste incineration market, an area that has seen little adoption of heat recovery in the United States. The goal of the project was to accelerate the use of energy-efficient, waste heat recovery technology as an alternative means to produce steam for industrial processes. The project had three main engineering and business objectives: Prove Feasibility of Waste Heat Recovery Technology at a Hazardous Waste Incinerator Complex; Provide Low-cost Steam to a Major Polypropylene Plant Using Waste Heat; and Create a Showcase Waste Heat Recovery Demonstration Project.

  10. Orion Project Status Report

    NASA Astrophysics Data System (ADS)

    Stiewing, Albert; Hopkins, Jeffrey L.

    2015-05-01

    Originally started in 2012 as the Betelgeuse Project, interest in the other bright stars of Orion soon expanded the Project stars to include a total of six of the brightest stars in Orion. The name was then changed to the Orion Project. Orion is one of the most famous constellations. Its declination along the celestial equator is such that it is visible from most of northern and southern hemispheres. In addition, the stars of Orion are very bright and interesting. The Orion Project now includes the stars Betelgeuse, Rigel, Saiph and the three stars of Orion's belt, Mintaka, Alnilam and Alnitak. The projects objectives are both to help the observer produce quality photometric and spectroscopic data and to produce archival quality photometric (BVRIJH bands) and spectroscopy (low, mid and high-resolution) data. This paper is a summary of the Orion Project status.

  11. Project GlobWave

    NASA Astrophysics Data System (ADS)

    Busswell, Geoff; Ash, Ellis; Piolle, Jean-Francois; Poulter, David J. S.; Snaith, Helen; Collard, Fabrice; Sheera, Harjit; Pinnock, Simon

    2010-12-01

    The ESA GlobWave project is a three year initiative, funded by ESA and CNES, to service the needs of satellite wave product users across the globe. Led by Logica UK, with support from CLS, IFREMER, SatOC and NOCS, the project will provide free access to satellite wave data and products in a common format, both historical and in near real time, from various European and American SAR and altimeter missions. Building on the successes of similar projects for Sea Surface Temperature and ocean colour, the project aims to stimulate increased use and analysis of satellite wave products. In addition to common-format satellite data the project will provide comparisons with in situ measurements, interactive data analysis tools and a pilot spatial wave forecast verification scheme for operational forecast production centres. The project will begin operations in January 2010, with direction from regular structured user consultation.

  12. Spin projection chromatography

    NASA Astrophysics Data System (ADS)

    Danieli, E. P.; Pastawski, H. M.; Levstein, P. R.

    2004-01-01

    We formulate the many-body spin dynamics at high temperature within the non-equilibrium Keldysh formalism. For the simplest XY interaction, analytical expressions in terms of the one particle solutions are obtained for linear and ring configurations. For small rings of even spin number, the group velocities of excitations depend on the parity of the total spin projection. This should enable a dynamical filtering of spin projections with a given parity i.e., a spin projection chromatography.

  13. Microwave solidification project overview

    SciTech Connect

    Sprenger, G.

    1993-01-01

    The Rocky Flats Plant Microwave Solidification Project has application potential to the Mixed Waste Treatment Project and the The Mixed Waste Integrated Program. The technical areas being addressed include (1) waste destruction and stabilization; (2) final waste form; and (3) front-end waste handling and feed preparation. This document covers need for such a program; technology description; significance; regulatory requirements; and accomplishments to date. A list of significant reports published under this project is included.

  14. KSC History Project

    NASA Technical Reports Server (NTRS)

    Snaples, Lee

    2001-01-01

    The project is a joint endeavor between Dr. Henry Dethloff and myself and is producing a number of products related to KSC history. This report is a summary of those projects. First, there is an overview monograph covering KSC history. Second, there is a chapter outline for an eventual book-length history. Third, there is monograph on safety at KSC. Finally, there is a web page and database dedicated to the KSC oral history project.

  15. Operational waste volume projection

    SciTech Connect

    Koreski, G.M.; Strode, J.N.

    1995-06-01

    Waste receipts to the double-shell tank system are analyzed and wastes through the year 2015 are projected based on generation trends of the past 12 months. A computer simulation of site operations is performed, which results in projections of tank fill schedules, tank transfers, evaporator operations, tank retrieval, and aging waste tank usage. This projection incorporates current budget planning and the clean-up schedule of the tri-party agreement. Assumptions are current as of June 1995.

  16. Operational Waste Volume Projection

    SciTech Connect

    STRODE, J.N.

    1999-08-24

    Waste receipts to the double-shell tank system are analyzed and wastes through the year 2018 are projected based on assumption as of July 1999. A computer simulation of site operations is performed, which results in projections of tank fill schedules, tank transfers, evaporator operations, tank retrieval, and aging waste tank usage. This projection incorporates current budget planning and the clean-up schedule of the Tri-Party Agreement.

  17. Computer Assets Recovery Project

    NASA Technical Reports Server (NTRS)

    CortesPena, Aida Yoguely

    2010-01-01

    This document reports on the project that was performed during the internship of the author. The project involved locating and recovering machines in various locations that Boeing has no need for, and therefore requires that they be transferred to another user or transferred to a non-profit organization. Other projects that the author performed was an inventory of toner and printers, loading new computers and connecting them to the network.

  18. The CHPRC Columbia River Protection Project Quality Assurance Project Plan

    SciTech Connect

    Fix, N. J.

    2008-11-30

    Pacific Northwest National Laboratory researchers are working on the CHPRC Columbia River Protection Project (hereafter referred to as the Columbia River Project). This is a follow-on project, funded by CH2M Hill Plateau Remediation Company, LLC (CHPRC), to the Fluor Hanford, Inc. Columbia River Protection Project. The work scope consists of a number of CHPRC funded, related projects that are managed under a master project (project number 55109). All contract releases associated with the Fluor Hanford Columbia River Project (Fluor Hanford, Inc. Contract 27647) and the CHPRC Columbia River Project (Contract 36402) will be collected under this master project. Each project within the master project is authorized by a CHPRC contract release that contains the project-specific statement of work. This Quality Assurance Project Plan provides the quality assurance requirements and processes that will be followed by the Columbia River Project staff.

  19. Project Risk Management

    NASA Technical Reports Server (NTRS)

    Jr., R. F. Miles

    1995-01-01

    Project risk management is primarily concerned with performance, reliability, cost, and schedule. Environmental risk management is primarily concerned with human health and ecological hazards and likelihoods. This paper discusses project risk management and compares it to environmental risk management, both with respect to goals and implementation. The approach of the Jet Propulsion Laboratory to risk management is presented as an example of a project risk management approach that is an extension to NASA NHB 7120.5: Management of Major System Programs and Projects.

  20. FLEXI Project Management Survey

    NASA Astrophysics Data System (ADS)

    Rohunen, Anna; Krzanik, Lech; Kuvaja, Pasi; Similä, Jouni; Rodriguez, Pilar; Hyysalo, Jarkko; Linna, Tommi

    FLEXI Project Management Survey (FLEXI PMS) has been established to gain detailed knowledge on how the software industry - in particular successful companies - manages agile software development. FLEXI PMS investigates the actual agile values, principles, practices and contexts. The survey is supported by a careful literature review and analysis of existing studies. Special attention is attached to large, multi-site, multi-company and distributed projects - the target area of FLEXI project. The survey is intended to provide solid data for further knowledge acquisition and project/company positioning with regard to feasible agile management practices.

  1. KSC History Project

    NASA Technical Reports Server (NTRS)

    Dethloff, Henry C.

    2001-01-01

    The KSC History Project focuses on archival research and oral history interviews on the history of Kennedy Space Center (KSC). Related projects include the preparation of a precis and chapter outline for a proposed book-length narrative history, a bibliography of key primary and secondary resources, a brief monograph overview of the history of KSC, and a monograph on the history of safety at the Center. Finally, there is work on the development of a web page and a personal history data base associated with the oral history project. The KSC History Project has been a joint endeavor between Henry C. Dethloff and Dr. Noble Lee Snaples, Jr.

  2. Project Worm Bin.

    ERIC Educational Resources Information Center

    McGuire, Daniel C.

    1987-01-01

    Describes a project centering around earthworm activity in a compost bin. Includes suggestions for exercises involving biological and conservation concepts, gardening skills, and dramatical presentations. (ML)

  3. Manpower and project planning

    NASA Technical Reports Server (NTRS)

    Johnson, David W.

    1991-01-01

    The purpose was to study how manpower and projects are planned at the Facilities Engineering Division (FENGD) within the Systems Engineering and Operations Directorate of the LaRC and to make recommendations for improving the effectiveness and productivity ot the tools that are used. The existing manpower and project planning processes (including the management plan for the FENGD, existing manpower planning reports, project reporting to LaRC and NASA Headquarters, employee time reporting, financial reporting, and coordination/tracking reports for procurement) were discussed with several people, and project planning software was evaluated.

  4. Other School Projects.

    ERIC Educational Resources Information Center

    Learning By Design, 2001

    2001-01-01

    Highlights selected construction projects for learning centers, early childhood and development schools, and special purpose educational facilities that have won the Learning By Design Awards for 2001.(GR)

  5. River Protection Project (RPP) Project Management Plan

    SciTech Connect

    NAVARRO, J.E.

    2001-03-07

    The Office of River Protection (ORP) Project Management Plan (PMP) for the River Protection Project (RPP) describes the process for developing and operating a Waste Treatment Complex (WTC) to clean up Hanford Site tank waste. The Plan describes the scope of the project, the institutional setting within which the project must be completed, and the management processes and structure planned for implementation. The Plan is written from the perspective of the ORP as the taxpayers' representative. The Hanford Site, in southeastern Washington State, has one of the largest concentrations of radioactive waste in the world, as a result of producing plutonium for national defense for more than 40 years. Approximately 53 million gallons of waste stored in 177 aging underground tanks represent major environmental, social, and political challenges for the U.S. Department of Energy (DOE). These challenges require numerous interfaces with state and federal environmental officials, Tribal Nations, stakeholders, Congress, and the US Department of Energy-Headquarters (DOE-HQ). The cleanup of the Site's tank waste is a national issue with the potential for environmental and economic impacts to the region and the nation.

  6. Basalt Waste Isolation Project Reclamation Support Project:

    SciTech Connect

    Brandt, C.A.; Rickard, W.H. Jr.; Cadoret, N.A.

    1992-06-01

    The Basalt Waste Isolation Project (BWIP) Reclamation Support Project began in the spring of 1988 by categorizing sites distributed during operations of the BWIP into those requiring revegetation and those to be abandoned or transferred to other programs. The Pacific Northwest Laboratory's role in this project was to develop plans for reestablishing native vegetation on the first category of sites, to monitor the implementation of these plans, to evaluate the effectiveness of these efforts, and to identify remediation methods where necessary. The Reclamation Support Project focused on three major areas: geologic hydrologic boreholes, the Exploratory Shaft Facility (ESF), and the Near-Surface Test Facility (NSTF). A number of BWIP reclamation sites seeded between 1989 and 1990 were found to be far below reclamation objectives. These sites were remediated in 1991 using various seedbed treatments designed to rectify problems with water-holding capacity, herbicide activity, surficial crust formation, and nutrient imbalances. Remediation was conducted during November and early December 1991. Sites were examined on a monthly basis thereafter to evaluate plant growth responses to these treatments. At all remediation sites early plant growth responses to these treatments. At all remediation sites, early plant growth far exceeded any previously obtained using other methods and seedbed treatments. Seeded plants did best where amendments consisted of soil-plus-compost or fertilizer-only. Vegetation growth on Gable Mountain was less than that found on other areas nearby, but this difference is attributed primarily to the site's altitude and north-facing orientation.

  7. Alternatives: Project Description.

    ERIC Educational Resources Information Center

    Brier, Norman

    Alternatives is a project designed for youngsters, ages 11-15, who display serious conduct problems and severe learning deficiencies. The primary goal of the project is to prevent the development of a chronic antisocial orientation among youngsters who are at high risk for such an outcome. The interventions employed at Alternatives are based on…

  8. Metadata: Projects & Standards.

    ERIC Educational Resources Information Center

    Milstead, Jessica; Feldman, Susan

    1999-01-01

    Describes efforts of three official metadata standards-setting bodies. Discusses the three categories of metadata formats; metadata registries; the Dublin Core and its relatives; several geospatial and biological metadata projects; and vocabularies/data element content. Provides a list of links to metadata projects and resources. (AEF)

  9. Fundred Dollar Bill Project

    ERIC Educational Resources Information Center

    Rubin, Mary

    2009-01-01

    This article describes the Fundred Dollar Bill Project which is an innovative artwork made of millions of drawings. This creative collective action is intended to support Operation Paydirt, an extraordinary art/science project uniting three million children with educators, scientists, healthcare professionals, designers, urban planners, engineers,…

  10. The Paint Creek Project.

    ERIC Educational Resources Information Center

    Northrop, David; Vonck, Beth

    1998-01-01

    Describes a summer program project designed and conducted by a mixed-age group of elementary children. Students collected data to determine whether a local stream was polluted, and interpretations of the data varied. An informational video about the project and the creek was produced. (PVD)