Science.gov

Sample records for projects office remedial

  1. Grand Junction Projects Office Remedial Action Project Building 2 public dose evaluation. Final report

    SciTech Connect

    Morris, R.

    1996-05-01

    Building 2 on the U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) site, which is operated by Rust Geotech, is part of the GJPO Remedial Action Program. This report describes measurements and modeling efforts to evaluate the radiation dose to members of the public who might someday occupy or tear down Building 2. The assessment of future doses to those occupying or demolishing Building 2 is based on assumptions about future uses of the building, measured data when available, and predictive modeling when necessary. Future use of the building is likely to be as an office facility. The DOE sponsored program, RESRAD-BUILD, Version. 1.5 was chosen for the modeling tool. Releasing the building for unrestricted use instead of demolishing it now could save a substantial amount of money compared with the baseline cost estimate because the site telecommunications system, housed in Building 2, would not be disabled and replaced. The information developed in this analysis may be used as part of an as low as reasonably achievable (ALARA) cost/benefit determination regarding disposition of Building 2.

  2. [Uranium Mill Tailings Remedial Action Project Office Quality Assurance Program Plan]. Revision 4

    SciTech Connect

    Not Available

    1992-06-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project was established to accomplish remedial actions at inactive uranium mill tailings sites in accordance with Public Law 95-604, the Uranium Mill Tailings Radiation Control Act of 1978 (UMTRCA). The UMTRA Project`s mission is to stabilize and control the residual radioactive materials at designated sites in a safe and environmentally sound manner so as to minimize or eliminate radiation health hazards to the public. The US Department of Energy (DOE) UMTRA Project Office (UMTRA PO) directs the overall project. Since these efforts may involve possible risks to public health and safety, a quality assurance (QA) program that conforms to the applicable criteria (set forth in the reference documents) has been established to control the quality of the work. This document, the Quality Assurance Program Plan (QAPP), brings into one document the essential criteria to be applied on a selective basis, depending upon the nature of the activity being conducted, and describes how those criteria shall be applied to the UMTRA Project. The UMTRA PO shall require each Project contractor to prepare and submit for approval a more detailed QAPP that is based on the applicable criteria of this QAPP and the referenced documents. All QAPPs on the UMTRA Project shall fit within the framework of this plan.

  3. [Uranium Mill Tailings Remedial Action Project Office Quality Assurance Program Plan

    SciTech Connect

    Not Available

    1992-06-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project was established to accomplish remedial actions at inactive uranium mill tailings sites in accordance with Public Law 95-604, the Uranium Mill Tailings Radiation Control Act of 1978 (UMTRCA). The UMTRA Project's mission is to stabilize and control the residual radioactive materials at designated sites in a safe and environmentally sound manner so as to minimize or eliminate radiation health hazards to the public. The US Department of Energy (DOE) UMTRA Project Office (UMTRA PO) directs the overall project. Since these efforts may involve possible risks to public health and safety, a quality assurance (QA) program that conforms to the applicable criteria (set forth in the reference documents) has been established to control the quality of the work. This document, the Quality Assurance Program Plan (QAPP), brings into one document the essential criteria to be applied on a selective basis, depending upon the nature of the activity being conducted, and describes how those criteria shall be applied to the UMTRA Project. The UMTRA PO shall require each Project contractor to prepare and submit for approval a more detailed QAPP that is based on the applicable criteria of this QAPP and the referenced documents. All QAPPs on the UMTRA Project shall fit within the framework of this plan.

  4. Confirmatory radiological survey of the Grand Junction Projects Office Remedial Action Project exterior portions, 1989-1995

    SciTech Connect

    Forbes, G.H.; Egidi, P.V.

    1997-04-01

    The purpose of this independent assessment was to provide the U.S. Department of Energy (DOE) with an independent verification (IV) that the soil at the Grand Junction Projects Office (GJPO) complies with applicable DOE guidelines. Oak Ridge National Laboratory/ Environmental Technology Section (ORNL/ETS) which is also located at the GJPO, was assigned by DOE as the Independent Verification Contractor (IVC). The assessment included reviews of the decontamination and decommissioning plan, annual environmental monitoring reports, data in the pre- and post-remedial action reports, reassessment reports and IV surveys. Procedures and field methods used during the remediation were reviewed, commented on, and amended as needed. The IV surveys included beta-gamma and gamma radiation scans, soil sampling and analyses. Based on the data presented in the post-remedial action report and the results of the IV surveys, the remediation of the outdoor portions of the GJPO has achieved the objectives. Residual deposits of uranium contamination may exist under asphalt because the original characterization was not designed to identify uranium and subsequent investigations were limited. The IVC recommends that this be addressed with the additional remediation. The IVC is working with the remedial action contractor (RAC) to assure that final documentation WM be sufficient for certification. The IVC will address additional remediation of buildings, associated utilities, and groundwater in separate reports. Therefore, this is considered a partial verification.

  5. US Department of Energy Grand Junction Projects Office Remedial Action Project. Final report of the decontamination and decommissioning of Building 52 at the Grand Junction Projects Office Facility

    SciTech Connect

    Krabacher, J.E.

    1996-08-01

    The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also was the remedial action contractor. Building 52 was found to be radiologically contaminated and was demolished in 1994. The soil area within the footprint of the building has been remediated in accordance with the identified standards and the area can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.

  6. Documenting cost and performance for environmental remediation projects: Department of Energy Office of Environmental Management

    SciTech Connect

    1996-08-08

    The purpose of this DOE guide is to facilitate the use of consistent procedures to document cost and performance information for projects involving the remediation of media contaminated with hazardous and radioactive wastes. It provides remedial action project managers with a standardized set of data to document completed remediation projects. Standardized reporting of data will broaden the utility of the information, increase confidence in the effectiveness of future remedial technologies, and enhance the organization, storage and retrieval of relevant information for future cleanup projects. The foundation for this guide was laid down by the Federal Remediation Technologies Roundtable (FRTR) in their publication, Guide to Documenting Cost and Performance for Remediation Projects, EPA-542-B- 95-002. Member agencies of the FRTR include the US EPA, the US DOD, the US DOE, and the US DOI. All the member agencies are involved in site remediation projects and anticipate following the guidance provided in the above reference. Therefore, there is much to be gained for DOE to be consistent with the other member agencies as it will be easier to compare projects across different agencies and also to learn from the experiences of a wider spectrum of prior completed projects.

  7. Saxton soil remediation project

    SciTech Connect

    Holmes, R.D.

    1995-12-31

    The Saxton Nuclear Experimental Facility (SNEF) consists of a 23-MW(thermal) pressurized light water thermal reactor located in south central Pennsylvania. The Saxton Nuclear Experimental Corporation (SNEC), a wholly owned subsidiary of the General Public Utilities (GPU) Corporation, is the licensee for the SNEF. Maintenance and decommissioning activities at the site are conducted by GPU Nuclear, also a GPU subsidiary and operator of the Three Mile Island and Oyster Creek nuclear facilities. The remediation and radioactive waste management of contaminated soils is described.

  8. Uranium Mill Tailings Remedial Action Project 1993 Environmental Report

    SciTech Connect

    Not Available

    1994-10-01

    This annual report documents the Uranium Mill Tailing Remedial Action (UMTRA) Project environmental monitoring and protection program. The UMTRA Project routinely monitors radiation, radioactive residual materials, and hazardous constituents at associated former uranium tailings processing sites and disposal sites. At the end of 1993, surface remedial action was complete at 10 of the 24 designated UMTRA Project processing sites. In 1993 the UMTRA Project office revised the UMTRA Project Environmental Protection Implementation Plan, as required by the US DOE. Because the UMTRA Project sites are in different stages of remedial action, the breadth of the UMTRA environmental protection program differs from site to site. In general, sites actively undergoing surface remedial action have the most comprehensive environmental programs for sampling media. At sites where surface remedial action is complete and at sites where remedial action has not yet begun, the environmental program consists primarily of surface water and ground water monitoring to support site characterization, baseline risk assessments, or disposal site performance assessments.

  9. Projects at the Western Environmental Technology Office. Quarterly technical progress report, April 1--June 30, 1995

    SciTech Connect

    1995-08-01

    This report contains brief outlines of the multiple projects under the responsibility of the Western Environmental Technology Office in Butte Montana. These projects include biomass remediation, remediation of contaminated soils, mine waste technology, and several other types of remediation.

  10. The 100-C-7 Remediation Project. An Overview of One of DOE's Largest Remediation Projects - 13260

    SciTech Connect

    Post, Thomas C.; Strom, Dean; Beulow, Laura

    2013-07-01

    The U.S. Department of Energy Richland Operations Office (RL), U.S. Environmental Protection Agency (EPA) and Washington Closure Hanford LLC (WCH) completed remediation of one of the largest waste sites in the U.S. Department of Energy complex. The waste site, 100-C-7, covers approximately 15 football fields and was excavated to a depth of 85 feet (groundwater). The project team removed a total of 2.3 million tons of clean and contaminated soil, concrete debris, and scrap metal. 100-C-7 lies in Hanford's 100 B/C Area, home to historic B and C Reactors. The waste site was excavated in two parts as 100-C-7 and 100-C-7:1. The pair of excavations appear like pit mines. Mining engineers were hired to design their tiered sides, with safety benches every 17 feet and service ramps which allowed equipment access to the bottom of the excavations. The overall cleanup project was conducted over a span of almost 10 years. A variety of site characterization, excavation, load-out and sampling methodologies were employed at various stages of remediation. Alternative technologies were screened and evaluated during the project. A new method for cost effectively treating soils was implemented - resulting in significant cost savings. Additional opportunities for minimizing waste streams and recycling were identified and effectively implemented by the project team. During the final phase of cleanup the project team applied lessons learned throughout the entire project to address the final, remaining source of chromium contamination. The C-7 cleanup now serves as a model for remediating extensive deep zone contamination sites at Hanford. (authors)

  11. Uranium Mill Tailings Remedial Action (UMTRA) Surface Project: Project plan. Revision 1

    SciTech Connect

    Not Available

    1993-08-11

    The Uranium Mill Tailings Radiation Control Act of 1978 (UMTRCA) [Public Law (PL) 95-604, 42 United States Code (USC) 7901], hereinafter referred to as the ``Act,`` authorizes the US Department of Energy (DOE) to stabilize and control surface tailings and ground water contamination. To fulfill this mission, the DOE has established two projects under the Uranium Mill Tailings Remedial Action (UMTRA) Project Office. The Ground Water Project was established in April 1991 as a major project and a separate project plan will be prepared for that portion of the mission. This project plan covers the UMTRA Surface Project, a major system acquisition (MSA).

  12. Uranium Mill Tailings Remedial Action Project surface project management plan

    SciTech Connect

    Not Available

    1994-09-01

    This Project Management Plan describes the planning, systems, and organization that shall be used to manage the Uranium Mill Tailings Remedial Action Project (UMTRA). US DOE is authorized to stabilize and control surface tailings and ground water contamination at 24 inactive uranium processing sites and associated vicinity properties containing uranium mill tailings and related residual radioactive materials.

  13. Uranium Mill Tailings Remedial Action Project: Cost Reduction and Productivity Improvement Program Project Plan

    SciTech Connect

    Not Available

    1991-11-01

    The purpose of the Cost Reduction/Productivity Improvement Program Plan is to formalize and improve upon existing efforts to control costs which have been underway since project inception. This program plan has been coordinated with the Department of Energy (DOE) Office of Environmental Management (EM) and the DOE Field Office, Albuquerque (AL). It incorporates prior Uranium Mill Tallings Remedial Action (UMTRA) Project Office guidance issued on the subject. The opportunities for reducing cosh and improving productivity are endless. The CR/PIP has these primary objectives: Improve productivity and quality; heighten the general cost consciousness of project participants, at all levels of their organizations; identify and implement specific innovative employee ideas that extend beyond what is required through existing processes and procedures; emphasize efforts that create additional value for the money spent by maintaining the project Total Estimated Cost (TEC) at the lowest possible level.

  14. Uranium Mill Tailings Remedial Action Project: Cost Reduction and Productivity Improvement Program Project Plan. Revised

    SciTech Connect

    Not Available

    1991-11-01

    The purpose of the Cost Reduction/Productivity Improvement Program Plan is to formalize and improve upon existing efforts to control costs which have been underway since project inception. This program plan has been coordinated with the Department of Energy (DOE) Office of Environmental Management (EM) and the DOE Field Office, Albuquerque (AL). It incorporates prior Uranium Mill Tallings Remedial Action (UMTRA) Project Office guidance issued on the subject. The opportunities for reducing cosh and improving productivity are endless. The CR/PIP has these primary objectives: Improve productivity and quality; heighten the general cost consciousness of project participants, at all levels of their organizations; identify and implement specific innovative employee ideas that extend beyond what is required through existing processes and procedures; emphasize efforts that create additional value for the money spent by maintaining the project Total Estimated Cost (TEC) at the lowest possible level.

  15. Project Charter (MSA-143). [Uranium Mill Tailings Remedial Action (UMTRA) Project

    SciTech Connect

    Not Available

    1986-07-01

    Public Law 95-604, The Uranium Mill Tailings Radiation Control Act of 1978'' as amended assigns to DOE, other Federal agencies, and involved States and Indian tribes, responsibilities for remedial actions at 22 inactive uranium mill tailings sites listed in the Act, and for any other sites designated by the Secretary prior to November 8, 1979. The objective of the UMTRA Project is to provide remedial action at the mill tailings sites and associated vicinity properties in order to stabilize and control the tailings in a safe and environmentally sound manner and to eliminate potential health hazards caused by residual levels of uranium decay products that exceed EPA standards. A total of 24 uranium mill tailings sites. This Project Charter delineates the respective responsibilities and authorities of (The Office of Nuclear Energy) (NE) and (Albuquerque Operations Office) (AL), and defines the terms and conditions for management of the UMTRA Project. Supplementary Project management documents which have been and are being developed pursuant to this Charter include a Project Plan (PP), a Project Management Plan (PMP) and other plans governing the accomplishment of the Project mission Evolution of the program will require updates of the Project Plan and Project Management Plan.

  16. Uranium Mill Tailings Remedial Action (UMTRA) Project. [UMTRA project

    SciTech Connect

    Not Available

    1989-09-01

    The mission of the Uranium Mill Tailings Remedial Action (UMTRA) Project is explicitly stated and directed in the Uranium Mill Tailings Radiation Control Act of 1978, hereinafter referred to as the Act.'' Title I of the Act authorizes the Department of Energy (DOE) to undertake remedial action at designated inactive uranium processing sites (Attachment 1 and 2) and associated vicinity properties containing uranium mill tailings and other residual radioactive materials derived from the processing site. The purpose of the remedial actions is to stabilize and control such uranium mill tailings and other residual radioactive materials in a safe and environmentally sound manner to minimize radiation health hazards to the public. The principal health hazards and environmental concerns are: the inhalation of air particulates contaminated as a result of the emanation of radon from the tailings piles and the subsequent decay of radon daughters; and the contamination of surface and groundwaters with radionuclides or other chemically toxic materials. This UMTRA Project Plan identifies the mission and objectives of the project, outlines the technical and managerial approach for achieving them, and summarizes the performance, cost, and schedule baselines which have been established to guide operational activity. Estimated cost increases by 15 percent, or if the schedule slips by six months. 4 refs.

  17. Volatile organic compound remedial action project

    SciTech Connect

    1991-12-01

    This Environmental Assessment (EA) reviews a proposed project that is planned to reduce the levels of volatile organic compound (VOC) contaminants present in the Mound domestic water supply. The potable and industrial process water supply for Mound is presently obtained from a shallow aquifer via on-site production wells. The present levels of VOCs in the water supply drawn from the on-site wells are below the maximum contaminant levels (MCLs) permissible for drinking water under Safe Drinking Water Act (SDWA; 40 CFR 141); however, Mound has determined that remedial measures should be taken to further reduce the VOC levels. The proposed project action is the reduction of the VOC levels in the water supply using packed tower aeration (PTA). This document is intended to satisfy the requirements of the National Environmental Policy Act (NEPA) of 1969 and associated Council on Environmental Quality regulations (40 CFR parts 1500 through 1508) as implemented through U.S. Department of Energy (DOE) Order 5440.1D and supporting DOE NEPA Guidelines (52 FR 47662), as amended (54 FR 12474; 55 FR 37174), and as modified by the Secretary of Energy Notice (SEN) 15-90 and associated guidance. As required, this EA provides sufficient information on the probable environmental impacts of the proposed action and alternatives to support a DOE decision either to prepare an Environmental Impact Statement (EIS) or issue a Finding of No Significant Impact (FONSI).

  18. Uranium Mill Tailings Remedial Action Project 1994 environmental report

    SciTech Connect

    1995-08-01

    This annual report documents the Uranium Mill Tailings Remedial Action (UMTRA) Project environmental monitoring and protection program. The UMTRA Project routinely monitors radiation, radioactive residual materials, and hazardous constituents at associated former uranium tailings processing sites and disposal sites. At the end of 1994, surface remedial action was complete at 14 of the 24 designated UMTRA Project processing sites: Canonsburg, Pennsylvania; Durango, Colorado; Grand Junction, Colorado; Green River Utah, Lakeview, Oregon; Lowman, Idaho; Mexican Hat, Utah; Riverton, Wyoming; Salt Lake City, Utah; Falls City, Texas; Shiprock, New Mexico; Spook, Wyoming, Tuba City, Arizona; and Monument Valley, Arizona. Surface remedial action was ongoing at 5 sites: Ambrosia Lake, New Mexico; Naturita, Colorado; Gunnison, Colorado; and Rifle, Colorado (2 sites). Remedial action has not begun at the 5 remaining UMTRA Project sites that are in the planning stage. Belfield and Bowman, North Dakota; Maybell, Colorado; and Slick Rock, Colorado (2 sites). The ground water compliance phase of the UMTRA Project started in 1991. Because the UMTRA Project sites are.` different stages of remedial action, the breadth of the UMTRA environmental protection program differs from site to site. In general, sites actively undergoing surface remedial action have the most comprehensive environmental programs for sampling media. At sites where surface remedial action is complete and at sites where remedial action has not yet begun, the environmental program consists primarily of surface water and ground water monitoring to support site characterization, baseline risk assessments, or disposal site performance assessments.

  19. UMTRA Project Office Quality Assurance Program Plan. Revision 5

    SciTech Connect

    Not Available

    1993-11-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project was established to accomplish remedial actions at inactive uranium mill tailings sites in accordance with Public Law 95-604, the Uranium Mill Tailings Radiation Control Act of 1978 (UMTRCA). The UMTRA Project`s mission is to stabilize and control the residual radioactive materials at designated sites in a safe and environmentally sound manner so as to minimize or eliminate radiation health hazards to the public. The US Department of Energy (DOE) UMTRA Project Office directs the overall Project. Because these efforts may involve possible risks to public health and safety, a quality assurance (QA) program that conforms to the applicable criteria (set forth in the reference documents) has been established to control the quality of the work. This document, the Quality Assurance Program Plan (QAPP), brings into one document the essential criteria to be applied on a selective basis, depending upon the nature of the activity being conducted, and describes how those criteria shall be applied to the UMTRA Project. The UMTRA Project Office shall require each Project contractor to prepare and submit for approval a more detailed QAPP that is based on the applicable criteria of this QAPP and the referenced documents. All QAPPs on the UMTRA Project shall fit within the framework of this plan or an industry standard format that has been approved by the DOE Project Office.

  20. Tank waste remediation system characterization project quality policies. Revision 1

    SciTech Connect

    Trimble, D.J.

    1995-10-02

    These Quality Policies (QPs) describe the Quality Management System of the Tank Waste Characterization Project (hereafter referred to as the Characterization Project), Tank Waste Remediation System (TWRS), Westinghouse Hanford Company (WHC). The Quality Policies and quality requirements described herein are binding on all Characterization Project organizations. To achieve quality, the Characterization Project management team shall implement this Characterization Project Quality Management System.

  1. COST ESTIMATING SYSTEMS FOR REMEDIAL ACTION PROJECTS

    EPA Science Inventory

    This paper details the ongoing collaboration between the U.S. EPA and the U.S. Army Corps of Engineers in the development of complementary micro-computer based cost estimating systems for hazardous waste remediations. he U.S. EPA system, "Remedial Action Cost Estimating System" (...

  2. UMTRA Project Office quality assurance program plan. Revision 6

    SciTech Connect

    Not Available

    1994-09-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project was established to accomplish remedial actions at inactive uranium mill tailings sites. The UMTRA Project`s mission is to stabilize and control the residual radioactive materials at designated sites in a safe and environmentally sound manner so as to minimize or eliminate radiation health hazards to the public. Because these efforts may involve possible risks to public health and safety, a quality assurance (QA) program that conforms to the applicable criteria has been established to control the quality of the work. This document, the Quality Assurance Program Plan (QAPP), brings into one document the essential criteria to be applied on a selective basis, depending upon the nature of the activity being conducted, and describes how those criteria shall be applied to the UMTRA Project. QA requirements contained in this QAPP shall apply to all personnel, processes, and activities, including planning, scheduling, and cost control, performed by the UMTRA Project Office and its contractors.

  3. Final 2014 Remedial Action Report Project Chariot, Cape Thompson, Alaska

    SciTech Connect

    None, None

    2015-03-01

    This report was prepared to document remedial action (RA) work performed at the former Project Chariot site located near Cape Thompson, Alaska during 2014. The work was managed by the U.S. Army Corps of Engineers (USACE) Alaska District for the U.S. Department of Energy (DOE) Office of Legacy Management (LM). Due to the short field season and the tight barge schedule, all field work was conducted at the site July 6 through September 12, 2014. Excavation activities occurred between July 16 and August 26, 2014. A temporary field camp was constructed at the site prior to excavation activities to accommodate the workers at the remote, uninhabited location. A total of 785.6 tons of petroleum, oil, and lubricants (POL)-contaminated soil was excavated from four former drill sites associated with test holes installed circa 1960. Diesel was used in the drilling process during test hole installations and resulted in impacts to surface and subsurface soils at four of the five sites (no contamination was identified at Test Hole Able). Historic information is not definitive as to the usage for Test Hole X-1; it may have actually been a dump site and not a drill site. In addition to the contaminated soil, the steel test hole casings were decommissioned and associated debris was removed as part of the remedial effort.

  4. UMTRA Project Office Records Management Plan

    SciTech Connect

    Not Available

    1993-06-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project Office maintains two distinct records handling areas. One of the areas is maintained by a Technical Assistance Contractor (TAC), and is referred to as the UMTRA Project Document Control Center (UPDCC). The UPDCC manages all UMTRA records except those dealing with contracts, personnel, budgeting, finance, and any other documents which are of a purely administrative nature. The second area, the UMTRA Project Administrative Files Collection (UPAFC), contains all those records listed above that are not managed by the UPDCC. This Records Management Plan (RMP) for the UPAFC will be the framework for identifying the elements and activities that relate to the management and operational aspects involved in the handling of UPAFC. Guidelines for the program will be obtained from US Department of Energy (DOE) Orders. DOE Orders implement the guidelines issued by the National Archives and Records Administration (NARA), the final authority for records management. The RMP will address the life cycle of records, including their creation, maintenance, use, and disposition.

  5. NASA Remediation Technology Collaboration Development Task, Overview and Project Summaries

    NASA Technical Reports Server (NTRS)

    Romeo, James G.

    2014-01-01

    An overview presentation of NASA's Remediation Technology Collaboration Development Task including the following project summaries: in situ groundwater monitor, in situ chemical oxidation, in situ bioremediation, horizontal multi-port well, and high resolution site characterization.

  6. Fiscal Year 2010 Program of the U.S. DOE Office of Groundwater and Soil Remediation

    SciTech Connect

    Chamberlain, G. M.; Skubal, Karen L.; Wellman, Dawn M.

    2011-03-07

    The mission of the Office of Groundwater and Soil Remediation (EM-32) is to perform assessments, establish technical criteria and promote cross-site integration. The Office provides guidance for the development and implementation of plans for remediation of groundwater and is responsible for development of technologies needed to reduce risk from groundwater contamination. It is also responsible for providing technical direction and/or assistance to sites in resolving difficult technical groundwater and soil remediation problems. This paper discusses the activities funded by EM-32 for FY-2010.

  7. USING PLANTS TO REMEDIATE PETROLEUM-CONTAMINATED SOIL: PROJECT CONTINUATION

    EPA Science Inventory

    Crude oil contamination of soil often occurs adjacent to wellheads and storage facilities. Phytoremediation is a promising tool that can be used to remediate such sites and uses plants and agronomic techniques to enhance biodegradation of hydrocarbons. This project has conduct...

  8. The Office of Groundwater & Soil Remediation Fiscal Year 2011 Research & Development Program

    SciTech Connect

    Gerdes, Kurt D.; Chamberlain, Grover S.; Aylward, R. S.; Cercy, Mike; Seitz, Roger; Ramirez, Rosa; Skubal, Karen L.; Marble, Justin; Wellman, Dawn M.; Bunn, Amoret L.; Liang, Liyuan; Pierce, Eric M.

    2011-12-02

    The U.S. Department of Energy’s (DOE) Office of Groundwater and Soil Remediation supports applied research and technology development (AR&TD) for remediation of environments contaminated by legacy nuclear waste. The program centers on delivering advanced scientific approaches and technologies from highly-leveraged, strategic investments that maximize impact to reduce risk and life-cycle cleanup costs. The current groundwater and soil remediation program consists of four applied programmatic areas: • Deep Vadose Zone – Applied Field Research Initiative • Attenuation Based Remedies – Applied Field Research Initiative • Remediation of Mercury and Industrial Contaminants – Applied Field Research Initiative • Advanced Simulation Capability for Environmental Management. This paper provides an overview of the applied programmatic areas, fiscal year 11 accomplishments, and their near-term technical direction.

  9. Flight Projects Office Information Systems Testbed (FIST)

    NASA Technical Reports Server (NTRS)

    Liggett, Patricia

    1991-01-01

    Viewgraphs on the Flight Projects Office Information Systems Testbed (FIST) are presented. The goal is to perform technology evaluation and prototyping of information systems to support SFOC and JPL flight projects in order to reduce risk in the development of operational data systems for such projects.

  10. Management and overview Quality Assurance Program Plan. [Uranium Mill Tailings Remedial Action (UMTRA) Project

    SciTech Connect

    Not Available

    1986-08-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project Office (DOE/ UMTRA-PO) is the US Department of Energy (DOE) Albuquerque Operations Office (AL) organization charged with the responsibility of managing and coordinating the activities of the various participating organizations and support contractors working on the UMTRA Project. This Quality Assurance Program Plan (QAPP) describes how the DOE/UMTRA-PO, as assisted by the Technical Assistance Contractor (TAC), performs the quality assurance (QA) aspects of managing and coordinating UMTRA Project activities. This QAPP was developed to comply with DOE Order 5700.6A, August, 1981, and AL Order 5700.6B, April, 1984, which contain the criteria applicable to Project QA activities.

  11. Shuttle Small Payloads Project Office: Overview

    NASA Technical Reports Server (NTRS)

    Dunker, S. Chris

    1999-01-01

    This viewgraph presentation gives an overview of the Shuttle Small Payload Project Office activities. Information is given on the Hitchhiker and Hitchhiker-Junior programs, the Get Away Special program, space experiment module program, program costs, and future enhancements.

  12. Final audit report of remedial action construction at the UMTRA project site Rifle, Colorado. Rev. 1

    SciTech Connect

    1997-01-01

    This final audit report summarizes the assessments performed by the U.S. Department of Energy (DOE) Environmental Restoration Division (ERD) and its Technical Assistance Contractor (TAC) of remedial action compliance with approved plans, specifications, standards, and 40 CFR Part 192 at the Rifle, Colorado, Uranium Mill Tailings Remedial Action (UMTRA) Project site. Remedial action construction was directed by the Remedial Action Contractor (RAC).

  13. Preliminary remediation goals for use at the US Department of Energy Oak Ridge Operations Office. Revision 1

    SciTech Connect

    1996-05-01

    This technical memorandum presents Preliminary Remediation Goals (PRGs) for use in human health risk assessment efforts under the United States Department of Energy, Oak Ridge Operations Office Environmental Restoration (ER) Division. This document provides the ER Division with standardized PRGs which are integral to the Remedial Investigation/Feasibility Study process. They are used during project scooping (Data Quality Objectives development), in screening level risk assessments to support early action or No Further Investigation decisions, and in the baselines risk assessment where they are employed in the selection of chemicals of potential concern. The primary objective of this document is to standardize these values and eliminate any duplication of effort by providing PRGs to all contractors involved in risk activities. In addition, by managing the assumptions and systems used in PRG derivation, the ER Risk Assessment Program will be able to control the level of quality assurance associated with these risk-based guideline values.

  14. DSN Aperture Enhancement Project Office

    NASA Technical Reports Server (NTRS)

    Marina, Miguel

    2012-01-01

    All contracts are underway for antennas, associated facilities modifications and new transmitters. High risk CPI 100kW klystron and JPL high power uplink microwave components have been designed, prototyped and successfully tested at GDSCC to support the 80kW transmitter implementation and testing at vendor facility. Open issues, which might affect project delivery date, have plans in place or are being created, to maintain DSS-35 Operational Date. There are no known open issues that affect performance. Overall good progress has been made in all areas (procurements, contracts, design and development) and the project is confident that DSS-35 & 36 antennas and the three 80kW Uplink systems will be delivered according to plan.

  15. Environmental Audit of the Grand Junction Projects Office

    SciTech Connect

    Not Available

    1991-08-01

    The Grand Junction Projects Office (GJPO) is located in Mesa County, Colorado, immediately south and west of the Grand Junction city limits. The US Atomic Energy Commission (AEC) established the Colorado Raw Materials Office at the present-day Grand Junction Projects Office in 1947, to aid in the development of a viable domestic uranium industry. Activities at the site included sampling uranium concentrate; pilot-plant milling research, including testing and processing of uranium ores; and operation of a uranium mill pilot plant from 1954 to 1958. The last shipment of uranium concentrate was sent from GJPO in January, 1975. Since that time the site has been utilized to support various DOE programs, such as the former National Uranium Resource Evaluation (NURE) Program, the Uranium Mill Tailings Remedial Action Project (UMTRAP), the Surplus Facilities Management Program (SFMP), and the Technical Measurements Center (TMC). All known contamination at GJPO is believed to be the result of the past uranium milling, analyses, and storage activities. Hazards associated with the wastes impounded at GJPO include surface and ground-water contamination and potential radon and gamma-radiation exposure. This report documents the results of the Baseline Environmental Audit conducted at Grand Junction Projects Office (GJPO) located in Grand Junction, Colorado. The Grand Junction Baseline Environmental Audit was conducted from May 28 to June 12, 1991, by the Office of Environmental Audit (EH-24). This Audit evaluated environmental programs and activities at GJPO, as well as GJPO activities at the State-Owned Temporary Repository. 4 figs., 12 tabs.

  16. Uranium Mill Tailings Remedial Action Project environmental protection implementation plan

    SciTech Connect

    Not Available

    1994-10-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project Environmental Protection Implementation Plan (EPIP) has been prepared in accordance with the requirements of the U.S. Department of Energy (DOE) Order 5400.1. The UMTRA EPIP is updated annually. This version covers the time period of 9 November 1994, through 8 November 1995. Its purpose is to provide management direction to ensure that the UMTRA Project is operated and managed in a manner that will protect, maintain, and where necessary, restore environmental quality, minimize potential threats to public health and the environment, and comply with environmental regulations and DOE policies.

  17. Uranium Mill Tailings Remedial Action Project Environmental Protection Implementation Plan

    SciTech Connect

    Not Available

    1992-10-01

    The Uranium Mill Tallings Remedial Action (UMTRA) Project Environmental Protection Implementation Plan (EPIP) has been prepared in accordance with the requirements of the US Department of Energy (DOE) Order 5400.1 (Chapter 3, paragraph 2). The UMTRA EPIP covers the time period of November 9, 1992, through November 8, 1993. It will be updated annually. Its purpose is to provide management direction to ensure that the UMTRA Project is operated and managed in a manner that will protect, maintain, and where necessary, restore environmental quality, minimize potential threats to public health and the environment, and comply with environmental regulations and DOE policies.

  18. Uranium Mill Tailings Remedial Action Project. 1995 Environmental Report

    SciTech Connect

    1996-06-01

    In accordance with U.S. Department of Energy (DOE) Order 23 1. 1, Environment, Safety and Health Reporting, the DOE prepares an annual report to document the activities of the Uranium Mill Tailings Remedial Action (UMTRA) Project environmental monitoring program. This monitoring must comply with appropriate laws, regulations, and standards, and it must identify apparent and meaningful trends in monitoring results. The results of all monitoring activities must be communicated to the public. The UMTRA Project has prepared annual environmental reports to the public since 1989.

  19. Programmatic Environmental Report for remedial actions at UMTRA (Uranium Mill Tailings Remedial Action) Project vicinity properties

    SciTech Connect

    Not Available

    1985-03-01

    This Environmental Report (ER) examines the environmental consequences of implementing a remedial action that would remove radioactive uranium mill tailings and associated contaminated materials from 394 vicinity properties near 14 inactive uranium processing sites included in the Uranium Mill Tailings Remedial Action (UMTRA) Project pursuant to Public Law 95--604, the Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978. Vicinity properties are those properties in the vicinity of the UMTRA Project inactive mill sites, either public or private, that are believed to be contaminated by residual radioactive material originating from one of the 14 inactive uranium processing sites, and which have been designated under Section 102(a)(1) of UMTRCA. The principal hazard associated with the contaminated properties results from the production of radon, a radioactive decay product of the radium contained in the tailings. Radon, a radioactive gas, can diffuse through the contaminated material and be released into the atmosphere where it and its radioactive decay products may be inhaled by humans. A second radiation exposure pathway results from the emission of gamma radiation from uranium decay products contained in the tailings. Gamma radiation emitted from contaminated material delivers an external exposure to the whole body. If the concentration of radon and its decay products is high enough and the exposure time long enough, or if the exposure to direct gamma radiation is long enough, cancers (i.e., excess health effects) may develop in persons living and working at the vicinity properties. 3 refs., 7 tabs.

  20. The Office of Groundwater & Soil Remediation Fiscal Year 2011 Research & Development Program

    SciTech Connect

    Pierce, Eric M

    2011-01-01

    The U.S. Department of Energy s (DOE) Office of Groundwater and Soil Remediation supports technology development and technical assistance for the remediation of environments contaminated by legacy nuclear waste. The core of the program is centered on delivering proactive, responsive expertise and technologies with highly-leveraged, carefully selected investments that maximize impact on life-cycle cleanup costs and risks across the DOE complex. The program currently focuses on four main priorities: improved sampling and characterization strategies, advanced predictive capabilities, enhanced remediation methods, and improved long-term performance evaluation and monitoring. In FY 2010, the program developed a detailed research and development (R&D) plan in support of a larger initiative to integrate R&D efforts across EM. This paper provides an overview of the high priority action areas and the program s near-term technical direction.

  1. The Office of Groundwater & Soil Remediation Fiscal Year 2011 Research & Development Program

    SciTech Connect

    Gerdes, Kurt D.; Chamberlain, Skip; Aylward, R. S.; Cercy, Mike; Seitz, Roger; Ramirez, Rosa; Skubal, Karen L.; Marble, Justin; Wellman, Dawn M.; Bunn, Amoret L.; Liang, Liyuan; Pierce, Eric M.

    2011-03-02

    The U.S. Department of Energy's (DOE) Office of Groundwater and Soil Remediation supports technology development and technical assistance for the remediation of environments contaminated by legacy nuclear waste. The core of the program is centered on delivering proactive, responsive expertise and technologies with highly-leveraged, carefully selected investments that maximum impact on life-cycle cleanup costs and risks across the DOE complex. The program currently focuses on four main priorities: improved sampling and characterization strategies, advanced predictive capabilities, enhanced remediation methods, and improved long-term performance evaluation and monitoring. In FY 2010, the program developed a detailed research and development (R and D) plan in support of a larger initiative to integrate R and D efforts across EM. This paper provides an overview of the priority action areas and the program's near-term technical direction.

  2. Office of Technology Development integrated program for development of in situ remediation technologies

    SciTech Connect

    Peterson, M.

    1992-08-01

    The Department of Energy's Office of Technology Development has instituted an integrated program focused on development of in situ remediation technologies. The development of in situ remediation technologies will focus on five problem groups: buried waste, contaminated soils, contaminated groundwater, containerized wastes and underground detonation sites. The contaminants that will be included in the development program are volatile and non volatile organics, radionuclides, inorganics and highly explosive materials as well as mixtures of these contaminants. The In Situ Remediation Integrated Program (ISR IP) has defined the fiscal year 1993 research and development technology areas for focusing activities, and they are described in this paper. These R D topical areas include: nonbiological in situ treatment, in situ bioremediation, electrokinetics, and in situ containment.

  3. Office of Technology Development integrated program for development of in situ remediation technologies

    SciTech Connect

    Peterson, M.

    1992-08-01

    The Department of Energy`s Office of Technology Development has instituted an integrated program focused on development of in situ remediation technologies. The development of in situ remediation technologies will focus on five problem groups: buried waste, contaminated soils, contaminated groundwater, containerized wastes and underground detonation sites. The contaminants that will be included in the development program are volatile and non volatile organics, radionuclides, inorganics and highly explosive materials as well as mixtures of these contaminants. The In Situ Remediation Integrated Program (ISR IP) has defined the fiscal year 1993 research and development technology areas for focusing activities, and they are described in this paper. These R&D topical areas include: nonbiological in situ treatment, in situ bioremediation, electrokinetics, and in situ containment.

  4. Archiving Methodology. Volume I: Project Officer's Guide.

    ERIC Educational Resources Information Center

    Leinwand (C.M.) Associates, Inc., Newton, MA.

    Recently, to encourage secondary analysis, the federal government has begun to arrange for public policy data to be documented, archived and released to the public. The purpose of this document is to provide government project officers with guidelines for archiving government-sponsored data files. The guidelines represent a model for…

  5. Uranium Mill Tailings Remedial Action Project Environmental Protection Implementation Plan

    SciTech Connect

    Vollmer, A.T.

    1993-10-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project Environmental Protection Implementation Plan (EPIP) has been prepared in accordance with the requirements of the US Department of Energy (DOE) Order 5400.1. The UMTRA EPIP covers the time period of November 9, 1993, through November 8, 1994. It will be updated annually. Its purpose is to provide management direction to ensure that the UMTRA Project is operated and managed in a manner that will protect, maintain, and where necessary, restore environmental quality, minimize potential threats to public health and the environment, and comply with environmental regulations and DOE policies. Contents of this report are: (1) general description of the UMTRA project environmental protection program; (2) notifications; (3) planning and reporting; (4) special programs; (5) environmental monitoring programs; (6) quality assurance and data verification; and (7) references.

  6. Uranium Mill Tailings Remedial Action Project (UMTRAP) Public Participation Plan

    SciTech Connect

    1981-05-01

    The purpose of this Public Participation Plan is to explain the Department of Energy`s plan for involving the public in the decision-making process related to the Uranium Mill Tailings Remedial Action (UMTRA) Project. This project was authorized by Congress in the Uranium Mill Tailings Radiation Control Act of 1978. The Act provides for a cooperative effort with affected states and Indian tribes for the eventual cleanup of abandoned or inactive uranium mill tailings sites, which are located in nine western states and in Pennsylvania. Section 111 of the Act states, ``in carrying out the provisions of this title, including the designation of processing sites, establishing priorities for such sites, the selection of remedial actions and the execution of cooperative agreements, the Secretary (of Energy), the Administrator (of the Environmental Protection Agency), and the (Nuclear Regulatory) Commission shall encourage public participation and, where appropriate, the Secretary shall hold public hearings relative to such matters in the States where processing sites and disposal sites are located.`` The objective of this document is to show when, where, and how the public will be involved in this project.

  7. Support of US CLIVAR Project Office 2012

    SciTech Connect

    Cummings, Donna

    2013-11-21

    SUBJECT: CLOSEOUT OF AWARD NO DE-SC0008494 FINAL REPORT: SUPPORT OF US CLIVAR PROJECT OFFICE 2012 UNIVERSITY CORPORATION FOR ATMOSPHERIC RESEARCH Director of JOSS, supervised the U.S. CLIVAR Project Office Director and helped direct the officer to enhance the goals and objectives of the U.S. CLIVAR Project and budget. Financial Manager of JOSS, worked to complete proposals and monitor compliance with award requirements and funding limitations and ensure the U.S. CLIVAR Project Office complied with UCAR policies and procedures. Project Coordinator administered the funding for the U.S. CLIVAR Project Office and was responsible for coordinating special projects that required additional support from JOSS technical staff. These projects included activities such as website updates, technology upgrades, production of printed reports, and development of graphic elements like logos. Web Developer worked both on web development and graphic work and the work consisted of the following: Maintaining the site ? installing updates to Drupal CMS (Content Management System). Creating new templates for webpages and styling them with CSS and JavaScript/jQuery code. Fixing the styling on webpages that the content contributor/manager (Jenn Mays) created and has had trouble with. Creating new web forms for abstract uploading, subscriptions, and meeting registrations. Created 4 webpages for the ?ASP: Key Uncertainties in the Global Carbon-Cycle? meeting. Developed a document review form, instruction webpages, login redirect, dynamic table with form submissions for the US CLIVAR SSC Science Plan Document Review. This was open to the public from June 12, 2013 until July 10, 2013. During this time the user accounts had to be checked (daily) that were created by the public, to delete any spam ones. Graphics work: preparing images for general use on webpages, webpage banners, and for meeting name badges, creating a US CLIVAR letterhead, redesigning the US AMOC logo. System Administrator spent

  8. UMTRA Project Office Federal Employee Occupational Safety and Health Program Plan. Final draft

    SciTech Connect

    Young, B.H.

    1994-02-01

    This document establishes the Federal Employee Occupational Safety and Health (FEOSH) Program for the US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project Office. This program will ensure compliance with the applicable requirements of DOE Order 3790.1 B and DOE Albuquerque Operations Office (AL) Order 3790.1A. FEOSH Program responsibilities delegated by the DOE-AL to the UMTRA Project Office by AL Order 3790.1A also are assigned. The UMTRA Project Office has developed the UMTRA Project Environmental, Safety, and Health (ES&H) Plan (DOE, 1992), which establishes the basic programmatic ES&H requirements for all participants on the UMTRA Project. The ES&H plan is designed primarily to cover remedial action activities at UMTRA sites, and defines the ES&H responsibilities of both the UMTRA Project Office and its contractors. The UMTRA FEOSH Program described herein is a subset of the overall UMTRA ES&H program and covers only the federal employees working on the UMTRA Project.

  9. UMTRA project office federal employee occupational safety and health program plan. Revision 1

    SciTech Connect

    Not Available

    1994-06-01

    This document establishes the Federal Employee Occupational Safety and Health (FEOSH) Program for the US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project Office. This program will ensure compliance with applicable requirements of DOE Order 3790.1B and DOE Albuquerque Operations Office (AL) Order 3790.lA. FEOSH Program responsibilities delegated by the DOE-AL to the UMTRA Project Office by AL Order 3790.1A also are assigned. The UMTRA Project Office has developed the UMTRA Project Environmental, Safety, and Health (ES&H) Plan (DOE, 1992), which establishes the basic programmatic ES&H requirements for all participants on the UMTRA Project. The ES&H plan is designed primarily to cover remedial action activities at UMTRA sites and defines the ES&H responsibilities of both the UMTRA Project Office and its contractors. The UMTRA FEOSH Program described herein is a subset of the overall UMTRA ES&H program and covers only federal employees working on the UMTRA Project.

  10. 48 CFR 2052.215-71 - Project officer authority.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 48 Federal Acquisition Regulations System 6 2014-10-01 2014-10-01 false Project officer authority... Project officer authority. As prescribed in 2015.209-70(a)(2)(i), the contracting officer shall insert the... may be altered to delete duties where appropriate: Project Officer Authority (OCT 1999) (a)...

  11. 48 CFR 2052.215-71 - Project officer authority.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 48 Federal Acquisition Regulations System 6 2012-10-01 2012-10-01 false Project officer authority... Project officer authority. As prescribed in 2015.209-70(a)(2)(i), the contracting officer shall insert the... may be altered to delete duties where appropriate: Project Officer Authority (OCT 1999) (a)...

  12. 48 CFR 2052.215-71 - Project officer authority.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 48 Federal Acquisition Regulations System 6 2011-10-01 2011-10-01 false Project officer authority... Project officer authority. As prescribed in 2015.209-70(a)(2)(i), the contracting officer shall insert the... may be altered to delete duties where appropriate: Project Officer Authority (OCT 1999) (a)...

  13. 48 CFR 2052.215-71 - Project officer authority.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 48 Federal Acquisition Regulations System 6 2013-10-01 2013-10-01 false Project officer authority... Project officer authority. As prescribed in 2015.209-70(a)(2)(i), the contracting officer shall insert the... may be altered to delete duties where appropriate: Project Officer Authority (OCT 1999) (a)...

  14. DATA ACQUISITION FOR ENVIRONMENTAL TRANSPORT AND FATE SCREENING FOR COMPOUNDS OF INTEREST TO THE OFFICE OF EMERGENCY AND REMEDIAL RESPONSE

    EPA Science Inventory

    Physical properties, equilibrium, and kinetic constants for evaluating the transformation and transport in aquatic systems for organic chemicals of interest to the U.S. Environmental Protection Agency's Office of Emergency and Remedial Response have been obtained from the literat...

  15. Groundwater protection management program plan. [Uranium Mill Tailings Remedial Action (UMTRA) Project

    SciTech Connect

    Not Available

    1992-06-01

    US Department of Energy (DOE) Order 5400.1 requires the establishment of a groundwater protection management program to ensure compliance with DOE requirements and applicable Federal, state, and local laws and regulations. The Uranium Mill Tailings Remedial Action (UMTRA) Project Office has prepared a Groundwater Protection Management Program Plan'' (groundwater protection plan) of sufficient scope and detail to reflect the program's significance and address the seven activities required in DOE Order 5400.1, Chapter 3, for special program planning. The groundwater protection plan highlights the methods designed to preserve, protect, and monitor groundwater resources at UMTRA Project processing and disposal sites. The plan includes an overview of the remedial action status at the 24 designated processing sites and identifies project technical guidance documents and site-specific documents for the UMTRA groundwater protection management program. In addition, the groundwater protection plan addresses the general information required to develop a water resources protection strategy at the permanent disposal sites. Finally, the plan describes ongoing activities that are in various stages of development at UMTRA sites (long-term care at disposal sites and groundwater restoration at processing sites). This plan will be reviewed annually and updated every 3 years in accordance with DOE Order 5400.1.

  16. [Earth Science Technology Office's Computational Technologies Project

    NASA Technical Reports Server (NTRS)

    Fischer, James (Technical Monitor); Merkey, Phillip

    2005-01-01

    This grant supported the effort to characterize the problem domain of the Earth Science Technology Office's Computational Technologies Project, to engage the Beowulf Cluster Computing Community as well as the High Performance Computing Research Community so that we can predict the applicability of said technologies to the scientific community represented by the CT project and formulate long term strategies to provide the computational resources necessary to attain the anticipated scientific objectives of the CT project. Specifically, the goal of the evaluation effort is to use the information gathered over the course of the Round-3 investigations to quantify the trends in scientific expectations, the algorithmic requirements and capabilities of high-performance computers to satisfy this anticipated need.

  17. Uranium Mill Tailings Remedial Action Project, Surface Project Management Plan. Revision 1

    SciTech Connect

    Not Available

    1994-12-01

    Title I of the Uranium Mill Tailings Radiation Control Act (UMTRCA) authorizes the US Department of Energy (DOE) to undertake remedial action at 24 designated inactive uranium processing sites and associated vicinity properties (VP) containing uranium mill tailings and related residual radioactive materials. The purpose of the Uranium Mill Tailings Remedial Action (UMTRA) Surface Project is to minimize or eliminate radiation health hazards to the public and the environment at the 24 sites and related VPs. This document describes the management organization, system, and methods used to manage the design, construction, and other activities required to clean up the designated sites and associated VPs, in accordance with the UMTRCA.

  18. National Unmanned Aircraft Systems Project Office

    USGS Publications Warehouse

    Goplen, Susan E.; Sloan, Jeff L.

    2015-01-01

    The U.S. Geological Survey (USGS) National Unmanned Aircraft Systems (UAS) Project Office leads the implementation of UAS technology in the Department of the Interior (DOI). Our mission is to support the transition of UAS into DOI as a new cost-effective tool for collecting remote-sensing data to monitor environmental conditions, respond to natural hazards, recognize the consequences and benefits of land and climate change and conduct wildlife inventories. The USGS is teaming with all DOI agencies and academia as well as local, State, and Tribal governments with guidance from the Federal Aviation Administration and the DOI Office of Aviation Services (OAS) to lead the safe, efficient, costeffective and leading-edge adoption of UAS technology into the scientific research and operational activities of the DOI.

  19. Sustainable geoengineering projects for the remediation of mine site

    NASA Astrophysics Data System (ADS)

    Martínez-Sanchez, Maria Jose; Perez-Sirvent, Carmen; Garcia-Lorenzo, Maria Luz; Martinez-Lopez, Salvadora; Gonzalez, Eva; Perez-Espinosa, Victor; Molina-Ruiz, Jose; Belen Martinez, Lucia; Hernandez, Carmen; Bech, Jaime; Hernandez-Cordoba, Manuel

    2015-04-01

    A large number of soils are contaminated by heavy metals due to mining activities, generating adverse effects on human health and the environment. In response to these negative effects, a variety of technologies have been developed. In situ immobilization by means of soil amendment is a non-intrusive and cost effective alternative that transforms the highly mobile toxic heavy metals to physico-chemically stable forms. Limestone filler is a good selection for such a purpose, because of its characteristics. In addition, the use of this amendment could revalorize the residues, reducing the costs of the process. The objective of this work was to evaluate the effectiveness of an immobilization technique in sediments contaminated by heavy metals. Two experimental areas, approximately 1 Ha each one, were selected, and technosols were developed as follows: original sediments, sediments mixed with limestone filler in a 1:1 proportion, gravel to avoid capillary and natural soil to allow plant growth. After the remediation technique was applied, monitoring was done in 18 points collecting samples (sediment and water) during a 4 years period at two month intervals. The pH and electrical conductivity as well as the heavy metal (Zn, Pb, Cd, Cu and As) contents were measured. Microtox bioassay was also applied. Sediments before the remediation technique showed acidic pH, high EC values and high trace elements content. The results obtained after the immobilization showed that sediment samples had neutral pH (average value of 8.3) low electrical conductivity (1.32 dS m-1) and low trace elements concentration. It can be concluded that the use of limestone filler is an excellent option in sediments polluted because of the risk for human health or ecosystem disappears or is decreased in a large extent. In addition, the designed experience allows stabilizer proportion to be optimized and may suppose a big cost-saving in the project in areas affected by mining activities.

  20. Uranium Mill Tailings Remedial Action Project Safety Advancement Field Effort (SAFE) Program

    SciTech Connect

    Not Available

    1994-02-01

    In 1992, the Uranium Mill Tailings Remedial Action (UMTRA) Project experienced several health and safety related incidents at active remediation project sites. As a result, the U.S. Department of Energy (DOE) directed the Technical Assistance Contractor (TAC) to establish a program increasing the DOE`s overall presence at operational remediation sites to identify and minimize risks in operations to the fullest extent possible (Attachments A and B). In response, the TAC, in cooperation with the DOE and the Remedial Action Contractor (RAC), developed the Safety Advancement Field Effort (SAFE) Program.

  1. 48 CFR 2052.215-71 - Project officer authority.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 6 2010-10-01 2010-10-01 true Project officer authority. 2052.215-71 Section 2052.215-71 Federal Acquisition Regulations System NUCLEAR REGULATORY COMMISSION... Project officer authority. As prescribed in 2015.209-70(a)(2)(i), the contracting officer shall insert...

  2. Remediation activities at the Fernald Environmental Management Project (FEMP)

    SciTech Connect

    Walsh, T.J.; Danner, R.

    1996-07-01

    The Fernald Environmental Management Project (FEMP) is a United States Department of Energy (DOE) facility located in southwestern Ohio. The facility began manufacturing uranium products in the early 1950`s and continued processing uranium ore concentrates until 1989. The facility used a variety of chemical and metallurgical processes to produce uranium metals for use at other DOE sites across the country. Since the facility manufactured uranium metals for over thirty years, various amounts of radiological contamination exists at the site. Because of the chemical and metallurgical processes employed at the site, some hazardous wastes as defined by the Resource Conservation and Recovery Act (RCRA) were also generated at the site. In 1989. the FEMP was placed on the National Priorities List (NPL) requiring cleanup of the facility`s radioactive and chemical contamination under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA). This paper discusses the proposed remediation activities at the five Operable Units (OUs) designated at the FEMP. In addition, the paper also examines the ongoing CERCLA response actions and RCRA closure activities at the facility.

  3. Women Traffic Officer Project. Final Report.

    ERIC Educational Resources Information Center

    Department of California Highway Patrol, Sacramento, CA.

    To determine the feasibility of employing women as state traffic officers (STOs), the California Highway Patrol (CHP) conducted a two-year study. The CHP employed forty-one women and forty-two men as traffic officers and gave them the standard sixteen-week training given all new officers. After graduation, the officers were assigned to highway…

  4. Grand Junction Projects Office site environmental report for calendar year 1992

    SciTech Connect

    Not Available

    1993-05-01

    This report presents information pertaining to environmental activities conducted during calendar year 1992 at the US Department of Energy Grand Junction Projects Office (DOE-GJPO) facility in Colorado. Environmental activities conducted at the GJPO facility during 1992 included those associated with environmental compliance, site remediation, off-site dose modeling, and radiological and nonradiological monitoring. Four phases of the on-site Grand Junction Projects Office Remedial Action Project were completed in 1992. Remediation activities, which included the removal of 161,589 tons of uranium-mill-tailings-contaminated material from the facility, were conducted in compliance with all applicable permits. Off-site dose modeling for the GJPO was conducted to determine compliance with current National Emission Standards for Hazardous Air Pollutants, Subpart H, and applicable DOE Orders (5400.1 and 5400.5). The total off-site EDE to the public from all sources of radiation emanating from the facility (radon, air particulates, gamma) was calculated as 9 mrem/yr, which is well below the DOE dose limit of 100 mrem/yr above background. The radiological and nonradiological monitoring program at the GJPO facility included monitoring of activities that generate potentially hazardous or toxic wastes and monitoring of ambient air, surface water, and ground water.

  5. 1991 New Mexico economic impact study for the Uranium Mill Tailings Remedial Action Project, Ambrosia Lake, New Mexico, site

    SciTech Connect

    Not Available

    1991-06-01

    The University of New Mexico Bureau of Business and Economic Research completed an abbreviated cost-benefit analysis of the income and employment impact of the US Department of Energy (DOE) and contractor offices in Albuquerque. Since the Project Office will have a significant positive impact on the State`s economy (shown on Table 8), the impact is combined with the impact of remedial actions at the Ambrosia Lake site to highlight the cost-benefit of the entire Uranium Mill Tailings Remedial Action (UMTRA) Project. The UMTRA Project at the Ambrosia Lake site will generate $12.509 million in gross labor income in New Mexico between 1989 and 1994. This includes $1.161 million in federal tax revenue, $1.015 million in State personal income tax revenue, and seven thousand in local tax revenue. The UMTRA Project will generate the equivalent of 84 full-time jobs during the peak year of remedial action at Ambrosia Lake site. New Mexico`s total funding requirement for the UMTRA Project is estimated to be $2.963 million. The net economic benefit of the Ambrosia Lake portion of the UMTRA Project to New Mexico after the State`s share of the project`s cost, the federal income tax, and the $0.936 million income impact of the alternate use of the State funding are subtracted, will be $7.451 million between 1990 and 1994. In Fiscal Year 1990 the UMTRA Project DOE and contractor offices in Albuquerque directly employed 163 people. Another 78 jobs were also maintained in support of the industry sector and 166 jobs were also maintained in other sections of the New Mexico economy. It is estimated that $19 million dollars of income was generated and 1.949 million of State and local taxes were collected. The University of New Mexico study shows that for every dollar the State of New Mexico invests in the UMTRA Project, it will realize $95.05 in gross labor income. This corresponds to a net return on the States investment in the Project of $97.20 for every dollar invested.

  6. Scheduling the Remediation of Port Hope: Logistical and Regulatory Challenges of a Multiple Site Urban Remediation Project - 13119

    SciTech Connect

    Ferguson Jones, Andrea; Lee, Angela; Palmeter, Tim

    2013-07-01

    The Port Hope Project is part of the larger CAN$1.28 billion Port Hope Area Initiative (PHAI), a community-based program for the development and implementation of a safe, local, long-term management solution for historic Low-Level Radioactive Waste (LLRW) in the Municipalities of Port Hope and Clarington, Ontario, Canada. Atomic Energy of Canada (AECL) is the Project Proponent, Public Works and Government Services (PWGSC) is managing the procurement of services and the MMM Group Limited - Conestoga Rovers and Associates Joint Venture (MMM-CRA Joint Venture) is providing detailed design and construction oversight and administration services for the Project. The Port Hope Project includes the construction of a long-term waste management facility (LTWMF) in the Municipality of Port Hope and the remediation of 18 (eighteen) large-scale LLRW, numerous small-scale sites still being identified and industrial sites within the Municipality. The total volume to be remediated is over one million cubic metres and will come from sites that include temporary storage sites, ravines, beaches, parks, private commercial and residential properties and vacant industrial sites all within the urban area of Port Hope. Challenges that will need to be overcome during this 10 year project include: - Requirements stipulated by the Environmental Assessment (EA) that affect Project logistics and schedule. - Coordination of site remediation with the construction schedule at the LTWMF. - Physical constraints on transport routes and at sites affecting production rates. - Despite being an urban undertaking, seasonal constrains for birds and fish (i.e., nesting and spawning seasons). - Municipal considerations. - Site-specific constraints. - Site interdependencies exist requiring consideration in the schedule. Several sites require the use of an adjacent site for staging. (authors)

  7. QUALITY ASSURANCE GUIDELINES FOR IERL-CI PROJECT OFFICERS

    EPA Science Inventory

    The document provides guidelines to Industrial Environmental Research Laboratory-Cincinnati (IERL-Ci) Project Officers for (1) incorporating quality assurance (QA) criteria in contract procurement and grant awards; (2) monitoring quality assurance of extramural projects; and (3) ...

  8. Cost-estimating systems for remedial-action projects

    SciTech Connect

    Evans, G.M.; Peterson, J.

    1991-01-01

    The paper details the ongoing collaboration between the U.S. EPA and the U.S. Army Corps of Engineers in the development of complementary microcomputer based cost estimating systems for hazardous waste remediations. The U.S. EPA system, Remedial Action Cost Estimating System (RACES), is a technology based application. Estimates generated by RACES are based upon cost engineering relationships. The estimates are designed for use in the early stages of remediation design. The U.S. Army Corps of Engineers system, Micro-Computer Aided Cost Engineering System (M-CACES), is a bottoms-up system for use in situations where detailed design information is available. While both systems will stand alone, they have been designed to allow the transfer of estimates generated by RACES directly into the M-CACES system.

  9. Final report of the decontamination and decommissioning of the exterior land areas at the Grand Junction Projects Office facility

    SciTech Connect

    Widdop, M.R.

    1995-09-01

    The US Department of Energy (DOE) Grand Junction Projects Office (GJPO) facility occupies approximately 56.4 acres (22.8 hectares) along the Gunnison River near Grand Junction, Colorado. The site was contaminated with uranium ore and mill tailings during uranium-refining activities conducted by the Manhattan Engineer District and during pilot-milling experiments conducted for the US Atomic Energy Commission`s (AEC`s) domestic uranium procurement program. The GJPO facility was the collection and assay point for AEC uranium and vanadium oxide purchases until the early 1970s. The DOE Decontamination and Decommissioning Program sponsored the Grand Junction Projects Office Remedial Action Project (GJPORAP) to remediate the facility lands, site improvements, and the underlying aquifer. The site contractor, Rust Geotech, was the Remedial Action Contractor for GJPORAP. The exterior land areas of the facility assessed as contaminated have been remediated in accordance with identified standards and can be released for unrestricted use. Restoration of the aquifer will be accomplished through the natural flushing action of the aquifer during the next 50 to 80 years. The remediation of the DOE-GJPO facility buildings is ongoing and will be described in a separate report.

  10. ISS Internal Active Thermal Control System (IATCS) Coolant Remediation Project

    NASA Technical Reports Server (NTRS)

    Morrison, Russell H.; Holt, Mike

    2005-01-01

    The IATCS coolant has experienced a number of anomalies in the time since the US Lab was first activated on Flight 5A in February 2001. These have included: 1) a decrease in coolant pH, 2) increases in inorganic carbon, 3) a reduction in phosphate buffer concentration, 4) an increase in dissolved nickel and precipitation of nickel salts, and 5) increases in microbial concentration. These anomalies represent some risk to the system, have been implicated in some hardware failures and are suspect in others. The ISS program has conducted extensive investigations of the causes and effects of these anomalies and has developed a comprehensive program to remediate the coolant chemistry of the on-orbit system as well as provide a robust and compatible coolant solution for the hardware yet to be delivered. The remediation steps include changes in the coolant chemistry specification, development of a suite of new antimicrobial additives, and development of devices for the removal of nickel and phosphate ions from the coolant. This paper presents an overview of the anomalies, their known and suspected system effects, their causes, and the actions being taken to remediate the coolant.

  11. Final audit report of remedial action construction at the UMTRA Project Mexican Hat, Utah -- Monument Valley, Arizona, sites

    SciTech Connect

    1995-10-01

    The final audit report for remedial action at the Mexican Hat, Utah, Monument Valley, Arizona, Uranium Mill Tailings Remedial Action (UMTRA) Project sites consists of a summary of the radiological surveillances/audits, quality assurance (QA) in-process surveillances, and QA remedial action close-out inspections performed by the US Department of Energy (DOE) and the Technical Assistance Contractor (TAC); on-site construction reviews (OSCR) performed by the US Nuclear Regulatory Commission (NRC); and a surveillance performed by the Navajo Nation. This report refers to remedial action activities performed at the Mexican Hat, Utah--Monument Valley, Arizona, Uranium Mill Tailings Remedial Action (UMTRA) Project sites.

  12. Status of activities on the inactive uranium mill tailings sites remedial action program. Office of the Assistant Secretary for Environment

    SciTech Connect

    Not Available

    1981-04-01

    This report on the status of the Office of Environment's program for inactive uranium mill tailings sites is an analysis of the current status and a forecast of future activities of the Office of Environment. The termination date for receipt of information was September 30, 1980. Aerial radiological surveys and detailed ground radiological assessments of properties within the communities in the vicinity of the designated processing sites in Canonsburg, Pennsylvania, Salt Lake City, Utah, and Boise, Idaho led to the designation of an initial group of vicinity properties for remedial action. The potential health effects of the residual radioactive materials on or near these properties were estimated, and the Assistant Secretary for Environment recommended priorities for performing remedial action to the Department's Assistant Secretary for Nuclear Energy. In designating these properties and establishing recommended priorities for performing remedial action, the Office of Environment consulted with the Environmental Protection Agency, the Nuclear Regulatory Commission, representatives from the affected State and local governments, and individual property owners. After notifying the Governors of each of the affected States and the Navajo Nation of the Secretary of Energy's designation of processing sites within their areas of jurisdiction and establishment of remedial action priorities, a Sample Cooperative Agreement was developed by the Department in consultation with the Nuclear Regulatory Commission and provided to the affected States and the Navajo Nation for comments. During September 1980, a Cooperative Agreement with the Commonwealth of Pennsylvania for the designated Canonsburg processing site was executed by the Department. It is anticipated that a Cooperative Agreement between the State of Utah and the Department to perform remedial actions at the designated Salt Lake City site will be executed in the near future.

  13. Quality Assurance Program Plan for the radiological survey activities program --- Uranium Mill Tailings Remedial Action Project

    SciTech Connect

    Knott, R.R.; Little, C.A.

    1991-08-01

    The Pollutant Assessments Group (PAG) at the Grand Junction Office (GJO), Colorado, of Oak Ridge National Laboratory (ORNL) is responsible for surveying designated sites in the vicinity of 24 inactive mill sites involved in the Department of Energy's (DOE) Uranium Mill Tailings Remedial Action Project (UMTRAP). The purpose of these surveys is to provide a recommendation to DOE whether to include or exclude these sites from UMTRAP based on whether the on-site residual radioactive material (if any) originated from the former mill sites, and radiation levels on-site are in excess of appropriate Environmental Protection Agency (EPA) criteria. This report describes the Quality Assurance Plan (QAP) for the PAG in conducting all activities related to UMTRAP. All quality assurance provisions given by the DOE, DOE/UMTRA and ORNL organizations are integrated into this plan. Specifically, this report identifies the policies and procedures followed in accomplishing the PAG/UMTRA QA program, identifies those organizational units involved in the implementation of these procedures, and outlines the respective responsibilities of those groups. 11 refs., 6 figs., 3 tabs.

  14. U.S. Department of Energy Grand Junction Projects Office site environmental report for calendar year 1995

    SciTech Connect

    1996-05-01

    This report presents information pertaining to environmental activities conducted during calendar year 1995 at the US Department of Energy (DOE) Grand Junction Projects Office (GJPO) facility in Grand Junction, Colorado. Environmental activities conducted at the GJPO facility during 1995 were associated with mixed-waste treatment, site remediation, off-site dose modeling, and radiological and nonradiological monitoring. As part of the GJPO Mixed-Waste Treatment Program, on-site treatability studies were conducted in 1995 that made use of pilot-scale evaporative-oxidation and thermal-desorption units and bench-scale stabilization. DOE-GJPO used some of its own mixed-waste as well as samples received from other DOE sites for these treatability studies. These studies are expected to conclude in 1996. Removal of radiologically contaminated materials from GJPO facility buildings was conducted under the provisions of the Grand Junction Projects Office Remedial Action Project. Remediation activities included the removal of 394 metric tons of contaminated material from Buildings 18 and 28 and revegetation activities on the GJPO site; remediation was conducted in compliance with applicable permits.

  15. Uranium mill tailings remedial action project real estate management plan

    SciTech Connect

    Not Available

    1994-09-01

    This plan summarizes the real estate requirements of the US Department of Energy`s (DOE) Uranium Mill Tailings Action (UMTRA) Project, identifies the roles and responsibilities of project participants involved in real estate activities, and describes the approaches used for completing these requirements. This document is intended to serve as a practical guide for all project participants. It is intended to be consistent with all formal agreements, but if a conflict is identified, the formal agreements will take precedence.

  16. Projects at the Western Environmental Technology Office. Quarterly technical progress report, January 1--March 31, 1995

    SciTech Connect

    1995-06-01

    This quarterly report briefly describes recent progress in eight projects. The projects are entitled Biomass Remediation Project; Heavy Metal-Contaminated Soil Project; MHD Shutdown; Mine Waste Technology Program; Plasma Projects; Resource Recovery Project; Spray Casting Project; and Watervliet Arsenal Project.

  17. Decontamination Technologies, Task 3, Urban Remediation and Response Project

    SciTech Connect

    Heiser,J.; Sullivan, T.

    2009-06-30

    In the aftermath of a Radiological Dispersal Device (RDD, also known as a dirty bomb) it will be necessary to remediate the site including building exteriors and interiors, equipment, pavement, vehicles, personal items etc. Remediation will remove or reduce radioactive contamination from the area using a combination of removing and disposing of many assets (including possible demolition of buildings), decontaminating and returning to service other assets, and fixing in place or leaving in place contamination that is deemed 'acceptable'. The later will require setting acceptable dose standards, which will require negotiation with all involved parties and a balance of risk and cost to benefit. To accomplish the first two, disposal or decontamination, a combination of technologies will be deployed that can be loosely classified as: Decontamination; Equipment removal and size reduction; and Demolition. This report will deal only with the decontamination technologies that will be used to return assets to service or to reduce waste disposal. It will not discuss demolition, size reduction or removal technologies or equipment (e.g., backhoe mounted rams, rock splitter, paving breakers and chipping hammers, etc.). As defined by the DOE (1994), decontamination is removal of radiological contamination from the surfaces of facilities and equipment. Expertise in this field comes primarily from the operation and decommissioning of DOE and commercial nuclear facilities as well as a small amount of ongoing research and development closely related to RDD decontamination. Information related to decontamination of fields, buildings, and public spaces resulting from the Goiania and Chernobyl incidents were also reviewed and provide some meaningful insight into decontamination at major urban areas. In order to proceed with decontamination, the item being processed needs to have an intrinsic value that exceeds the cost of the cleaning and justifies the exposure of any workers during the

  18. Senior Officer Oral History Program Project Handlist.

    ERIC Educational Resources Information Center

    Army War Coll., Carlisle Barracks, PA.

    This publication contains a project list of taped interviews and transcribed work covering approximately 900 personalities and special topics in military history. The historical material was given by various associations and individuals who donated oral histories to the U.S. Army Military History Institute for use by researchers. Each project…

  19. 40 CFR 300.120 - On-scene coordinators and remedial project managers: general responsibilities.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 40 Protection of Environment 29 2012-07-01 2012-07-01 false On-scene coordinators and remedial project managers: general responsibilities. 300.120 Section 300.120 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) SUPERFUND, EMERGENCY PLANNING, AND COMMUNITY RIGHT-TO-KNOW PROGRAMS NATIONAL OIL AND HAZARDOUS SUBSTANCES...

  20. 48 CFR 301.607-78 - Contracting Officer designation of a Program/Project Manager as the Contracting Officer's...

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... designation of a Program/Project Manager as the Contracting Officer's Technical Representative. 301.607-78... Contracting Officer designation of a Program/Project Manager as the Contracting Officer's Technical... acquisition. However, for those individuals serving as a Program or Project Manager under a...

  1. Scoping session of the programmatic environmental impact statement for the Uranium Mill Tailings Remedial Action Project

    SciTech Connect

    1992-12-31

    This document is about the scoping session which was held at the Community Center in Falls City, Texas. The purpose was to obtain public comment on the Programmatic Environmental Impact Statement for the Uranium Mill Tailings Remedial Action Project (UMTRA), specifically on the ground water project. Presentations made by the manager for the entire UMTRA program, manager of the site and ground water program, comments made by two residents of Fall City are included in this document.

  2. TANK FARM REMEDIATION TECHNOLOGY DEVELOPMENT PROJECT AN EXERCISE IN TECHNICAL & REGULATORY COLLABORATION

    SciTech Connect

    JARAYSI, M.N.

    2007-01-08

    The Tank Farm Remediation Technology Development Project at the Hanford Site focuses on waste storage tanks, pipelines and associated ancillary equipment that are part of the C-200 single-shell tank (SST) farm system located in the C Tank Farm. The purpose of the project is to obtain information on the implementation of a variety of closure activities and to answer questions on technical, operational and regulatory issues associated with closure.

  3. Preliminary remediation goals for use at the U.S. Department of Energy Oak Ridge Operations Office

    SciTech Connect

    1995-06-01

    This report presents Preliminary Remediation Goals (PRGs) for use in human health risk assessment efforts under the United States Department of Energy, Oak Ridge Operations Office Environmental Restoration (ER) Division. Chemical-specific PRGs are concentration goals for individual chemicals for specific medium and land use combinations. The PRGs are referred to as risk-based because they have been calculated using risk assessment procedures. Risk-based calculations set concentration limits using both carcinogenic or noncarcinogenic toxicity values under specific exposure pathways. The PRG is a concentration that is derived from a specified excess cancer risk level or hazard quotient. This report provides the ER Division with standardized PRGs which are integral to the Remedial Investigation/Feasibility Study process. By managing the assumptions and systems used in PRG derivation, the Environmental Restoration Risk Assessment Program will be able to control the level of quality assurance associated with these risk-based guideline values.

  4. Report on game species of concern associated with the Gunnison Remedial Action Project, Gunnison, Colorado. [Uranium Mill Tailings Remedial Action (UMTRA) Project

    SciTech Connect

    Not Available

    1991-09-01

    This report provides background information and data used in the analysis of potential impacts to game species reported in the Environmental Assessment of the Proposed Remedial Action at the Gunnison Uranium Mill Tailings Site, Gunnison, Colorado. That environmental assessment provides details regarding proposed remedial action at the Gunnison site along with a description of existing conditions and projected environmental impacts. A summary of the proposed action is provided. The uranium mill tailings and other contaminated materials at the Gunnison processing site would be transported to the Landfill disposal site via the Tenderfoot Mountain (TM) haul route. The remedial action would take place over a three-year period with two six-month winter shutdowns. The first year would consist of site preparation and haul road construction. The second year would consist of moving the tailings. Movement of the radon/infiltration barrier cover material and erosion protection material would take place during the third construction year. The material used to cover the pile is fine-grained material for the radon/infiltration barrier (Sixmile Lane borrow site) and rock for erosion protection from the Chance Gulch borrow site. The location of the borrow sites used to obtain these materials and the associated haul roads is shown.

  5. Tank waste remediation system characterization project quality policies

    SciTech Connect

    Trible, T.C., Westinghouse Hanford

    1996-07-31

    This quality plan describes the system used by Characterization Project management to achieve quality. This plan is comprised on eleven quality policies which, when taken together, form a management system deployed to achieve quality. This quality management system is based on the customer`s quality requirements known as the `RULE`, 10 CFR 830.120, Quality Assurance.

  6. Tank waste remediation system characterization project quality policies

    SciTech Connect

    Board, D.C.

    1997-09-24

    This quality plan describes the system used by Characterization Project management to achieve quality. This plan is comprised of eleven quality policies which, when taken together, form a management system deployed to achieve quality. This quality management system is based on the customer`s quality requirements known as the `RULE`, 10 CFR 830.120, Quality Assurance.

  7. Causes and remedies for the dominant risk factors in Enterprise System implementation projects: the consultants' perspective.

    PubMed

    Lech, Przemysław

    2016-01-01

    The purpose of this research was to investigate the causes of the dominant risk factors, affecting Enterprise System implementation projects and propose remedies for those risk factors from the perspective of implementation consultants. The study used a qualitative research strategy, based on e-mail interviews, semi-structured personal interviews with consultants and participant observation during implementation projects. The main contribution of this paper is that it offers viable indications of how to mitigate the dominant risk factors. These indications were grouped into the following categories: stable project scope, smooth communication supported by the project management, dedicated, competent and decision-making client team, competent and engaged consultant project manager, schedule and budget consistent with the project scope, use of methodology and procedures, enforced and enabled by the project managers, competent and dedicated consultants. A detailed description is provided for each category. PMID:27026932

  8. Modern Sorters for Soil Segregation on Large Scale Remediation Projects

    SciTech Connect

    Shonka, J.J.; Kelley, J.E.; O'Brien, J.M.

    2008-01-15

    volume is 50 kilograms or less. Smaller sorting volumes can be obtained with lower throughput or by re-sorting the diverted material. This equipment can also handle large objects. The use of spectroscopy systems allows several regions of- interest to be set. Super-Sorters can bring waste processing charges down to less than $30/ metric ton on smaller jobs and can save hundreds of dollars per metric ton in disposal charges. The largest effect on the overall project cost occurs during planning and implementation. The overall goal is reduction of the length of the project, which dictates the most efficient soil processing. With all sorting systems the parameters that need to be accounted for are matrix type, soil feed rate, soil pre-processing, site conditions, and regulatory issues. The soil matrix and its ability to flow are extremely crucial to operations. It is also important to consider that as conditions change (i.e., moisture), the flowability of the soil matrix will change. Many soil parameters have to be considered: cohesive strength, internal and wall friction, permeability, and bulk density as a function of consolidating pressure. Clay bearing soils have very low permeability and high cohesive strength which makes them difficult to process, especially when wet. Soil feed speed is dependent on the equipment present and the ability to move the soil in the Super-Sorter processing area. When a Super-Sorter is running at 400 metric tons per hour it is difficult to feed the system. As an example, front-end loaders with large buckets would move approximately 5-10 metric tons of material, and 400 metric tons per hour would require 50-100 bucket-loads per hour to attain. Because the flowability of the soil matrix is important, poor material is often pre-processed before it is added to the feed hopper of the 'survey' conveyor. This pre-processing can consist of a 'grizzly' to remove large objects from the soil matrix, followed screening plant to prepare the soil so that it

  9. Support to 2nd Generation RLV Propulsion Project Office

    NASA Technical Reports Server (NTRS)

    Lee, Thomas J.

    2002-01-01

    In this final report regarding support to the second generation RLV (Reusable Launch Vehicle) propulsion project office, a list of tasks accomplished is presented. During this period, Lee & Associates, LLC participated in numerous Systems Requirements Reviews (SRR) related to the Cobra development program.

  10. 48 CFR 301.606 - Training requirements for Project Officers.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 48 Federal Acquisition Regulations System 4 2011-10-01 2011-10-01 false Training requirements for Project Officers. 301.606 Section 301.606 Federal Acquisition Regulations System HEALTH AND HUMAN SERVICES GENERAL HHS ACQUISITION REGULATION SYSTEM Career Development, Contracting Authority, and...

  11. 48 CFR 301.606-71 - Project Officer training.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 48 Federal Acquisition Regulations System 4 2012-10-01 2012-10-01 false Project Officer training. 301.606-71 Section 301.606-71 Federal Acquisition Regulations System HEALTH AND HUMAN SERVICES GENERAL HHS ACQUISITION REGULATION SYSTEM Career Development, Contracting Authority, and Responsibilities...

  12. 48 CFR 301.606-71 - Project Officer training.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 48 Federal Acquisition Regulations System 4 2011-10-01 2011-10-01 false Project Officer training. 301.606-71 Section 301.606-71 Federal Acquisition Regulations System HEALTH AND HUMAN SERVICES GENERAL HHS ACQUISITION REGULATION SYSTEM Career Development, Contracting Authority, and Responsibilities...

  13. 48 CFR 301.606 - Training requirements for Project Officers.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 48 Federal Acquisition Regulations System 4 2012-10-01 2012-10-01 false Training requirements for Project Officers. 301.606 Section 301.606 Federal Acquisition Regulations System HEALTH AND HUMAN SERVICES GENERAL HHS ACQUISITION REGULATION SYSTEM Career Development, Contracting Authority, and...

  14. 48 CFR 301.606 - Training requirements for Project Officers.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 4 2010-10-01 2010-10-01 false Training requirements for Project Officers. 301.606 Section 301.606 Federal Acquisition Regulations System HEALTH AND HUMAN SERVICES GENERAL HHS ACQUISITION REGULATION SYSTEM Career Development, Contracting Authority, and...

  15. Interface control document for tank waste remediation system privatization phase 1 infrastructure support Project W-519

    SciTech Connect

    Parazin, R.J.

    1998-04-23

    This document describes the functional and physical interfaces between the Tank Waste Remediation System (TWRS) Privatization Phase 1 Infrastructure Project W-519 and the various other projects (i.e., Projects W-314, W-464, W-465, and W-520) supporting Phase 1 that will require the allocation of land in and about the Privatization Phase 1 Site and/or interface with the utilities extended by Project W-519. Project W-519 will identify land use allocations and upgrade/extend several utilities in the 200-East Area into the Privatization Phase 1 Site (formerly the Grout Disposal Compound) in preparation for the Privatization Contractors (PC) to construct treatment facilities. The project will upgrade/extend: Roads, Electrical Power, Raw Water (for process and fire suppression), Potable Water, and Liquid Effluent collection. The replacement of an existing Sanitary Sewage treatment system that may be displaced by Phase 1 site preparation activities may also be included.

  16. Uranium Mill Tailings remedial action project waste minimization and pollution prevention awareness program plan

    SciTech Connect

    Not Available

    1994-07-01

    The purpose of this plan is to establish a waste minimization and pollution prevention awareness (WM/PPA) program for the U.S. Department of Energy`s (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project. The program satisfies DOE requirements mandated by DOE Order 5400.1. This plan establishes planning objectives and strategies for conserving resources and reducing the quantity and toxicity of wastes and other environmental releases.

  17. Technical framework for groundwater restoration. [Uranium Mill Tailings Remedial Action (UMTRA) Project

    SciTech Connect

    Not Available

    1991-04-01

    This document provides the technical framework for groundwater restoration under Phase II of the Uranium Mill Tailings Remedial Action (UMTRA) Project. A preliminary management plan for Phase II has been set forth in a companion document titled Preplanning Guidance Document for Groundwater Restoration''. General principles of site characterization for groundwater restoration, restoration methods, and treatment are discussed in this document to provide an overview of standard technical approaches to groundwater restoration.

  18. Remedial Action Contacts Directory - 1997

    SciTech Connect

    1997-05-01

    This document, which was prepared for the US Department of Energy (DOE) Office of Environmental Restoration (ER), is a directory of 2628 individuals interested or involved in environmental restoration and/or remedial actions at radioactively contaminated sites. This directory contains a list of mailing addresses and phone numbers of DOE operations, area, site, project, and contractor offices; an index of DOE operations, area, site, project, and contractor office sorted by state; a list of individuals, presented by last name, facsimile number, and e-mail address; an index of affiliations presented alphabetically, with individual contacts appearing below each affiliation name; and an index of foreign contacta sorted by country and affiliation. This document was generated from the Remedial Action Contacts Database, which is maintained by the Remedial Action Program Information Center (RAPIC).

  19. Integrating removal actions and remedial actions: Soil and debris management at the Fernald Environmental Management Project

    SciTech Connect

    Goidell, L.C.; Hagen, T.D.; Strimbu, M.J.; Dupuis-Nouille, E.M.; Taylor, A.C.; Weese, T.E.; Yerace, P.J.

    1996-02-01

    Since 1991, excess soil and debris generated at the Fernald Environmental management Project (FEMP) have been managed in accordance with the principles contained in a programmatic Removal Action (RvA) Work Plan (WP). This plan provides a sitewide management concept and implementation strategy for improved storage and management of excess soil and debris over the period required to design and construct improved storage facilities. These management principles, however, are no longer consistent with the directions in approved and draft Records of Decision (RODs) and anticipated in draft RODs other decision documents. A new approach has been taken to foster improved management techniques for soil and debris that can be readily incorporated into remedial design/remedial action plans. Response, Compensation and Liability Act (CERCLA) process. This paper describes the methods that were applied to address the issues associated with keeping the components of the new work plan field implementable and flexible; this is especially important as remedial design is either in its initial stages or has not been started and final remediation options could not be precluded.

  20. Consensus implementation of a groundwater remediation project at the Idaho National Engineering Laboratory

    SciTech Connect

    Hastings, K.R.; Carlson, D.S.

    1996-12-31

    Because of significant characterization uncertainties existing when the Record of Decision was signed and the unfavorable national reputation of groundwater pump and treat remediation projects, the Test Area North (TAN) groundwater ROD includes the evaluation of five emerging technologies that show potential for treating the organic contamination in situ or reducing the toxicity of contaminants above ground. Treatability studies will be conducted to ascertain whether any may be suitable for implementation at TAN to yield more timely or cost effective restoration of the aquifer. The implementation approach established for the TAN groundwater project is a consensus approach, maximizing a partnership relation with stakeholders in constant, iterative implementation decision making.

  1. WSSRAP chemical plant geotechnical investigations for the Weldon Spring Site Remedial Action Project, Weldon Spring, Missouri

    SciTech Connect

    Not Available

    1990-12-01

    This document has been prepared for the United states Department of Energy (DOE) Weldon Spring Site Remedial Action Project (WSSRAP) by the Project Management Contractor (PMC), which consists of MK-Ferguson Company (MKF) and Morrison Knudsen Corporation Environmental Services Group (MKES) with Jacobs Engineering Group (JEG) as MKF's predesignated subcontractor. This report presents the results of site geotechnical investigations conducted by the PMC in the vicinity of the Weldon Spring chemical plant and raffinate pits (WSCP/RP) and in potential on-site and off-site clayey material borrow sources. The WSCP/RP is the proposed disposal cell (DC) site. 39 refs., 24 figs., 12 tabs.

  2. US Department of Energy Uranium Mill Tailings Remedial Action ground water Project. Revision 1, Version 1: Final project plan

    SciTech Connect

    Not Available

    1993-12-21

    The scope of the Project is to develop and implement a ground water compliance strategy for all 24 UMTRA processing sites. The compliance strategy for the processing sites must satisfy requirements of the proposed EPA ground water cleanup standards in 40 CFR Part 192, Subparts B and C (1988). This scope of work will entail the following activities, on a site-specific basis: Development of a compliance strategy based upon modification of the UMTRA Surface Project remedial action plans (RAP) or development of Ground Water Project RAPs with NRC and state or tribal concurrence on the RAP; implementation of the RAP to include establishment of institutional controls, where appropriate; institution of long-term verification monitoring for transfer to a separate DOE program on or before the Project end date; and preparation of completion reports and final licensing on those sites that will be completed prior to the Project end date.

  3. THE POSITIVE IMPACTS OF AMERICAN REINVESTMENT AND RECOVERY ACT (ARRA) FUNDING TO THE WASTE MANAGEMENT PROGRAM ON HANFORD'S PLATEAU REMEDIATION PROJECT

    SciTech Connect

    BLACKFORD LT

    2010-01-19

    In April 2009, the Department of Energy (DOE) Richland Operations Office (RL) was allocated $1.6 billion (B) in ARRA funding to be applied to cleanup projects at the Hanford Site. DOE-RL selected projects to receive ARRA funding based on 3-criteria: creating/saving jobs, reducing the footprint of the Hanford Site, and reducing life-cycle costs for cleanup. They further selected projects that were currently covered under regulatory documents and existing prime contracts, which allowed work to proceed quickly. CH2M HILL Plateau Remediation Company (CHPRC) is a prime contractor to the DOE focused on the environmental cleanup of the DOE Hanford Site Central Plateau. CHPRC was slated to receive $1.36B in ARRA funding. As of January, 2010, CHPRC has awarded over $200 million (M) in subcontracts (64% to small businesses), created more that 1,100 jobs, and touched more than 2,300 lives - all in support of long-term objectives for remediation of the Central Plateau, on or ahead of schedule. ARRA funding is being used to accelerate and augment cleanup activities already underway under the baseline Plateau Remediation Contract (PRC). This paper details challenges and accomplishments using ARRA funding to meet DOE-RL objectives of creating/saving jobs, expediting cleanup, and reducing lifecycle costs for cleanup during the first months of implementation.

  4. Weldon Spring Site Remedial Action Project approach to building dismantlement and demolition

    SciTech Connect

    Spittler, F.J.

    1996-01-01

    When remediation began at the Weldon Spring Site Remedial Action Project (WSSRAP), there were 41 buildings on site. Twenty-nine of these buildings were ancillary structures and were not used for processing radioactive material. Most of these have been torn down. The remaining 12 buildings were used for uranium and thorium processing or were major support structures, such as the laboratory. Two of the buildings were major processing operations occurred were successfully demolished in February of this year. Demolition of all structures will be complete in September of this year. To give an understanding of the magnitude of the work, the following is a description of the physical characteristics of the green salt building. This building was used to convert brown oxide (UO3) to green salt (UF4), which is the last intermediate step in purifying the mostly yellow cake feed material into uranium metal.

  5. Uranium Mill Tailings Remedial Action Project fiscal year 1997 annual report to stakeholders

    SciTech Connect

    1997-12-31

    The fiscal year (FY) 1997 annual report is the 19th report on the status of the US Department of Energy`s (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project. In 1978, Congress directed the DOE to assess and clean up contamination at 24 designated former uranium processing sites. The DOE is also responsible for cleaning up properties in the vicinity of the sites where wind and water erosion deposited tailings or people removed them from the site for use in construction or landscaping. Cleanup has been undertaken in cooperation with state governments and Indian tribes within whose boundaries the sites are located. It is being conducted in two phases: the surface project and the groundwater project. This report addresses specifics about the UMTRA surface project.

  6. Fiscal year 1996 annual report to stakeholders, Uranium Mill Tailings Remedial Action Project

    SciTech Connect

    1996-10-01

    This is the Fiscal Year (FY) 1996 annual report on the status of the US Department of Energy`s (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project. In 1978, Congress directed the DOE to assess and clean up contamination at 24 designated former uranium processing sites. The DOE is also responsible for cleaning up properties in the vicinity of the sites where wind and water erosion deposited tailings or people removed them from the site for use in construction of landscaping. Cleanup is being undertaken in cooperation with state governments and Indian tribes within whose boundaries the sites are located. It is being conducted in two phases: the surface project and the ground water project. This report addresses specifics about the surface phase of the UMTRA Project.

  7. Oppenheimer's Box of Chocolates: Remediation of the Manhattan Project Landfill at Los Alamos National Laboratory - 12283

    SciTech Connect

    Allen, Donald L.; Ramsey, Susan S.; Finn, Kevin P.; Chaloupka, Allan B.

    2012-07-01

    Material Disposal Area B (MDA B) is the oldest radioactive waste disposal facility at Los Alamos National Laboratory. Operated from 1944-48, MDA B was the disposal facility for the Manhattan Project. Recognized as one of the most challenging environmental remediation projects at Los Alamos, the excavation of MDA B received $110 million from the American Recovery and Reinvestment Act of 2009 to accelerate this complex remediation work. Several factors combined to create significant challenges to remediating the landfill known in the 1940's as the 'contaminated dump'. The secrecy surrounding the Manhattan Project meant that no records were kept of radiological materials and chemicals disposed or of the landfill design. An extensive review of historical documents and interviews with early laboratory personnel resulted in a list of hundreds of hazardous chemicals that could have been buried in MDA B. Also, historical reports of MDA B spontaneously combusting on three occasions -with 50-foot flames and pink smoke spewing across the mesa during the last incident in 1948-indicated that hazardous materials were likely present in MDA B. To complicate matters further, though MDA B was located on an isolated mesa in the 1940's, the landfill has since been surrounded by a Los Alamos commercial district. The local newspaper, hardware store and a number of other businesses are located directly across the street from MDA B. This close proximity to the public and the potential for hazardous materials in MDA B necessitated conducting remediation work within protective enclosures. Potential chemical hazards and radiological inventory were better defined using a minimally intrusive sampling method called direct push technology (DPT) prior to excavation. Even with extensive sampling and planning the project team encountered many surprises and challenges during the project. The one area where planning did not fail to meet reality was safety. There were no serious worker injuries and

  8. Economic impact study of the Uranium Mill Tailings Remedial Action Project in Colorado: Colorado state fiscal year 1993

    SciTech Connect

    Not Available

    1993-12-01

    The Colorado economic impact study summarizes employment and economic benefits to the state from activities associated with the Uranium Mill Tailings Remedial Action (UMTRA) Project during Colorado state fiscal year 1993 (July 1, 1992, through June 30, 1993). To capture employment benefits, a questionnaire was distributed to subcontractor employees at the active UMTRA Project sites of Grand Junction, Rifle, and Gunnison, Colorado. An estimated 52 percent of the employees working on the UMTRA Project responded to this information request. Economic data were requested from each site prime subcontractor, as well as from the Remedial Action Contractor. The most significant benefits associated with the UMTRA Project in Colorado are summarized.

  9. Report on game species of concern associated with the Gunnison Remedial Action Project, Gunnison, Colorado

    SciTech Connect

    Not Available

    1991-09-01

    This report provides background information and data used in the analysis of potential impacts to game species reported in the Environmental Assessment of the Proposed Remedial Action at the Gunnison Uranium Mill Tailings Site, Gunnison, Colorado. That environmental assessment provides details regarding proposed remedial action at the Gunnison site along with a description of existing conditions and projected environmental impacts. A summary of the proposed action is provided. The uranium mill tailings and other contaminated materials at the Gunnison processing site would be transported to the Landfill disposal site via the Tenderfoot Mountain (TM) haul route. The remedial action would take place over a three-year period with two six-month winter shutdowns. The first year would consist of site preparation and haul road construction. The second year would consist of moving the tailings. Movement of the radon/infiltration barrier cover material and erosion protection material would take place during the third construction year. The material used to cover the pile is fine-grained material for the radon/infiltration barrier (Sixmile Lane borrow site) and rock for erosion protection from the Chance Gulch borrow site. The location of the borrow sites used to obtain these materials and the associated haul roads is shown.

  10. The Gunite and Associated Tanks Remediation Project Tank Waste Retrieval Performance and Lessons Learned, vol. 1 [of 2

    SciTech Connect

    Lewis, BE

    2003-10-07

    The Gunite and Associated Tanks (GAAT) Remediation Project was the first of its kind performed in the United States. Robotics and remotely operated equipment were used to successfully transfer almost 94,000 gal of remote-handled transuranic sludge containing over 81,000 Ci of radioactive contamination from nine large underground storage tanks at the Oak Ridge National Laboratory (ORNL). The sludge was transferred with over 439,000 gal of radioactive waste supernatant and {approx}420,500 gal of fresh water that was used in sluicing operations. The GAATs are located in a high-traffic area of ORNL near a main thoroughfare. A phased and integrated approach to waste retrieval operations was used for the GAAT Remediation Project. The project promoted safety by obtaining experience from low-risk operations in the North Tank Farm before moving to higher-risk operations in the South Tank Farm. This approach allowed project personnel to become familiar with the tanks and waste, as well as the equipment, processes, procedures, and operations required to perform successful waste retrieval. By using an integrated approach to tank waste retrieval and tank waste management, the project was completed years ahead of the original baseline schedule, which resulted in avoiding millions of dollars in associated costs. This report is organized in two volumes. Volume 1 provides information on the various phases of the GAAT Remediation Project. It also describes the different types of equipment and how they were used. The emphasis of Volume 1 is on the description of the tank waste retrieval performance and the lessons learned during the GAAT Remediation Project. Volume 2 provides the appendixes for the report, which include the following information: (A) Background Information for the Gunite and Associated Tanks Operable Unit; (B) Annotated Bibliography; (C) Comprehensive Listing of the Sample Analysis Data from the GAAT Remediation Project; (D) GAAT Equipment Matrix; and (E) Vendor List

  11. Weldon Spring Site Remedial Action Project quarterly environmental data summary (QEDS) for fourth quarter 1998

    SciTech Connect

    1999-02-01

    This report contains the Quarterly Environmental Data Summary (QEDS) for the fourth quarter of 1998 in support of the Weldon Spring Site Remedial Action Project Federal Facilities Agreement. The data, except for air monitoring data and site KPA generated data (uranium analyses) were received from the contract laboratories, verified by the Weldon Spring Site verification group, and merged into the database during the fourth quarter of 1998. KPA results for on-site total uranium analyses performed during fourth quarter 1998 are included. Air monitoring data presented are the most recent complete sets of quarterly data.

  12. Final report of the decontamination and decommissioning of Building 34 at the Grand Junction Projects Office Facility

    SciTech Connect

    Widdop, M.R.

    1996-08-01

    The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7 acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the Grand Junction Projects Office Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, was also the remedial action contractor. Building 34 was radiologically contaminated and the building was demolished in 1996. The soil area within the footprint of the building was analyzed and found to be not contaminated. The area can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual closeout report for each contaminated GJPO building.

  13. The Gunite and Associated Tanks Remediation Project Tank Waste Retrieval Performance and Lessons Learned, vol. 2 [of 2

    SciTech Connect

    Lewis, BE

    2003-10-07

    The Gunite and Associated Tanks (GAAT) Remediation Project was the first of its kind performed in the United States. Robotics and remotely operated equipment were used to successfully transfer almost 94,000 gal of remote-handled transuranic sludge containing over 81,000 Ci of radioactive contamination from nine large underground storage tanks at the Oak Ridge National Laboratory (ORNL). The sludge was transferred with over 439,000 gal of radioactive waste supernatant and {approx}420,500 gal of fresh water that was used in sluicing operations. The GAATs are located in a high-traffic area of ORNL near a main thoroughfare. Volume 1 provides information on the various phases of the project and describes the types of equipment used. Volume 1 also discusses the tank waste retrieval performance and the lessons learned during the remediation effort. Volume 2 consists of the following appendixes, which are referenced in Vol. 1: A--Background Information for the Gunite and Associated Tanks Operable Unit; B--Annotated Bibliography; C--GAAT Equipment Matrix; D--Comprehensive Listing of the Sample Analysis Data from the GAAT Remediation Project; and E--Vendor List for the GAAT Remediation Project. The remediation of the GAATs was completed {approx}5.5 years ahead of schedule and {approx}$120,435K below the cost estimated in the Remedial Investigation/Feasibility Study for the project. These schedule and cost savings were a direct result of the selection and use of state-of-the-art technologies and the dedication and drive of the engineers, technicians, managers, craft workers, and support personnel that made up the GAAT Remediation Project Team.

  14. Economic impact study of the Uranium Mill Tailings Remedial Action project in Colorado: Colorado state fiscal year 1995

    SciTech Connect

    1995-12-01

    This Colorado economic impact study summarizes employment and economic benefits to the state from activities associated with the Uranium Mill Tailings Remedial Action (UMTRA) Project during Colorado state fiscal year (FY) 1995 (1 July 1994 through 30 June 1995). To capture employment information, a questionnaire was distributed to subcontractor employees at the active UMTRA Project sites of Grand Junction, Gunnison, Maybell, Naturita, Rifle, and Slick Rock, Colorado. Economic data were requested from the Remedial Action Contractor (RAC), the Technical Assistance Contractor (TAC) and the US Department of Energy (DOE). The most significant benefits associated with the UMTRA Project in Colorado are summarized.

  15. Tank waste remediation system privatization phase 1 infrastructure project W-519, project execution plan

    SciTech Connect

    Parazin, R.J.

    1998-08-28

    This Project Execution Plan (PEP) defines the overall strategy, objectives, and contractor management requirements for the execution phase of Project W-519 (98-D403), Privatization Phase 1 Infrastructure Support, whose mission is to effect the required Hanford site infrastructure physical changes to accommodate the Privatization Contractor facilities. This plan provides the project scope, project objectives and method of performing the work scope and achieving objectives. The plan establishes the work definitions, the cost goals, schedule constraints and roles and responsibilities for project execution. The plan also defines how the project will be controlled and documented.

  16. Unique Regulatory Approach for Licensing the Port Hope Remediation Project in Canada - 13315

    SciTech Connect

    Kostova, M.; Howard, D.; Elder, P.

    2013-07-01

    The Port Hope remediation project is a part of a larger initiative of the Canadian Federal Government the Port Hope Area Initiative (PHAI) which is based upon a community proposal. The Government of Canada, through Natural Resources Canada (NRCan) is investing $1.28 billion over 10 years to clean up historic low-level radioactive waste in the Port Hope Area and to provide long-term safe management of the low-level radioactive wastes in the Port Hope Area. These wastes arose from the activities of a former Federal Crown Corporation (Eldorado Nuclear) and its private sector predecessors. In Canada, historic waste are defined as low-level radioactive waste that was managed in a manner no longer considered acceptable, but for which the original producer cannot reasonably be held responsible or no longer exists and for which the Federal Government has accepted responsibility. In Canada, under the current regulatory framework, the environmental remediation is not considered as a distinct phase of the nuclear cycle. The regulatory approach for dealing with existing sites contaminated with radioactive residues is defined on the basis of risk and application of existing regulations. A unique regulatory approach was taken by the Canadian Nuclear Safety Commission (CNSC) to address the various licensing issues and to set out the requirements for licensing of the Port Hope Project within the current regulatory framework. (authors)

  17. The Gunite Tanks Remediation Project at Oak Ridge National Laboratory; Successful Integration & Deployment of Technologies Results in Remediated Underground Storage Tanks

    SciTech Connect

    Billingsley, K.; Bolling, D.

    2002-02-27

    This paper presents an overview of the underground technologies deployed during the cleanup of nine large underground storage tanks (USTs) that contained residual radioactive sludge, liquid low-level waste (LLLW), and other debris. The Gunite Tanks Remediation Project at Oak Ridge National Laboratory (ORNL) was successfully completed in 2001, ending with the stabilization of the USTs and the cleanup of the South Tank Farm. This U.S. Department of Energy (DOE) project was the first of its kind completed in the United States of America. The Project integrated robotic and remotely operated technologies into an effective tank waste retrieval system that safely retrieved more than 348 m3 (92,000 gal) of radioactive sludge and 3.15E+15 Bq (85,000 Ci) of radioactive contamination from the tanks. The Project successfully transferred over 2,385 m3 (630,000 gal) of waste slurry to ORNL's active tank waste management system. The project team avoided over $120 Million in costs and shortened the original baseline schedule by over 10 years. Completing the Gunite Tanks Remediation Project eliminated the risks posed by the aging USTs and the waste they contained, and avoid the $400,000 annual costs associated with maintaining and monitoring the tanks.

  18. Final report of the decontamination and decommissioning of Building 18 at the Grand Junction Projects Office Facility

    SciTech Connect

    Widdop, M.R.

    1996-08-01

    The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also is the remedial action contractor. The soil beneath Building 18 was found to be radiologically contaminated; the building was not contaminated. The soil was remediated in accordance with identified standards. Building 18 and the underlying soil can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.

  19. Quarry geotechnical report for the Weldon Spring Site Remedial Action Project, Weldon Spring, Missouri

    SciTech Connect

    Not Available

    1990-11-01

    This report has been prepared for the United States Department of Energy's (DOE) Weldon Spring Site Remedial Action Project (WSSRAP) by the Project Management Contractor (PMC), which is MK-Ferguson Company (MK-Ferguson) with Jacobs Engineering Group (JEG) as its designated subcontractor. The Weldon Spring site (WSS) comprises the Weldon Spring quarry area and the Weldon Spring chemical plant and raffinate pit areas. This report presents the results of geotechnical investigations conducted during 1989--1990 at the proposed Weldon Spring quarry staging and water treatment facilities in the quarry area. The facilities are intended for treatment of water removed from the quarry area. An access road and a decontamination pad will be necessary for handling and transportation of bulk waste. Results of previous geotechnical investigations performed by other geoscience and environmental engineering firms in the quarry area, were reviewed, summarized and incorporated into this report. Well logging, stratigraphy data, piezometer data, elevations, and soil characteristics are also included.

  20. Oak Ridge background soils project provides data for remedial action evaluation

    SciTech Connect

    Watkins, D.R.; Lee, S.Y.; Hatmaker, T.L.; McGinn, C.W.; Nourse, B.D.; Schmoyer, R.L.; Burgoa, B.B.; Lietzke, D.A.

    1994-09-01

    Many constituents of potential concern for human health occur naturally at low concentrations in soils. The primary objective of the Background Soil Characterization Project (BSCP) was to provide fully validated and defensible, reservation-wide background concentration data on significant potential contaminants of concern (organics, inorganics, and radionuclides) in natural soils on the Oak Ridge Reservation (ORR). The data are particularly significant for remedial action projects; the data can be used to establish technical guidance and the basis for realistic cleanup requirements at hazardous waste sites on the reservation. Other objectives included providing baseline data for conducting contaminated site assessments and quantifying estimates of human health risk associated with background levels of potentially hazardous constituents in soils.

  1. Final audit report of remedial action construction at the UMTRA Project Falls City, Texas, site

    SciTech Connect

    1995-05-01

    This final audit report for the Falls City, Texas, Uranium Mill Tailings Remedial Action Project site summarizes the radiological audits and the quality assurance (QA) in-process surveillances, audits, and final close-out inspection performed by the U.S. Department of Energy (DOE) and Technical Assistance Contractor (TAC). It also summarizes U.S. Nuclear Regulatory Commission (NRC) surveillances. One radiological audit and three radiological surveillances were performed at the Falls City site. These surveillances and audit, which resulted in 31 observations, focused primarily on processing site activities and were performed on the following dates: 3-6 August 1992, 29-30 October 1992, 22-26 March 1993, and 1-3 November 1993. All outstanding radiological issues were closed out at the completion of the construction activities. Six QA in-process surveillances, which resulted in 71 observations, were performed at the Falls City site on the following dates: 22-24 July 1992, 23-25 November 1992, 17-19 May 1993, 16-18 August 1993, 13-15 October 1993, and 2-4 February 1994. All outstanding issues were closed out with the February surveillance on 3 March 1994. The DOE/TAC remedial action close-out inspections of the Falls City site, which resulted in 56 observations, were conducted 9-10 June 1994 and 26 July 1994. The inspections were closed out on 26 January 1995. The NRC performed three on-site construction reviews (OSCR), resulting in seven observations of remedial action construction activities that occurred during site visits. The OSCRs were performed 9 December 1992, 12 May 1993, and 25 October 1993. Since all audit and surveillance observations and recommendations have been closed out, this final audit report segment of the site certification process is complete.

  2. Final audit report of remedial action construction at the UMTRA Project Ambrosia Lake, New Mexico, site

    SciTech Connect

    1995-09-01

    The final audit report for remedial action at the Ambrosia Lake, New Mexico, Uranium Mill Tailings Remedial Action (UMTRA) Project site consists of a summary of the radiological surveillances/audits, quality assurance (QA) in-process surveillances, and a QA final closeout inspection performed by the US Department of Energy (DOE) and the Technical Assistance Contractor (TAC). One radiological surveillance and three radiological audits were performed at the Ambrosia Lake site. The surveillance was performed on 12--16 April 1993 (DOE, 1993d). The audits were performed on 26--29 July 1993 (DOE, 1993b); 21--23 March 1994 (DOE, 1994d); and 1--2 August 1994 (DOE, 1994d). The surveillance and audits resulted in 47 observations. Twelve of the observations raised DOE concerns that were resolved on site or through subsequent corrective action. All outstanding issues were satisfactorily closed out on 28 December 1994. The radiological surveillance and audits are discussed in this report. A total of seven QA in-process surveillances were performed at the Ambrosia Lake UMTRA site are discussed. The DOE/TAC Ambrosia Lake final remedial action close-out inspection was conducted on 26 July 1995 (DOE, 1995a). To summarize, a total of 155 observations were noted during DOE/TAC audit and surveillance activities. Follow-up to responses required from the RAC for the DOE/TAC surveillance and audit observations indicated that all issues related to the Ambrosia Lake site were resolved and closed to the satisfaction of the DOE.

  3. Radiation Protection Considerations at USACE Formerly Utilized Sites Remedial Action Program (FUSRAP) Projects

    SciTech Connect

    Brown, S.H.

    2008-07-01

    The Formerly Utilized Sites Remedial Action Program (FUSRAP) was initially authorized by Congress in 1974. FUSRAP was enacted to address residual radioactive contamination associated with numerous sites across the U.S. at which radioactive material (primarily Uranium ores and related milling products) had been processed in support of the nation's nuclear weapons program dating back to the Manhattan Project and the period immediately following World War II. In October 1997, Congress transferred the management of this program from the Department of Energy to the United States Corp of Engineers. Through this program, the Corps addresses the environmental remediation of certain sites once used by DOE's predecessor agencies, the Manhattan Engineer District and the Atomic Energy Commission. The waste at FUSRAP sites consists mainly of low levels of uranium, thorium and radium, along with some mixed wastes. Upon completion of remedial activities, these sites are transferred to DOE for long-term stewardship activities. This paper presents and contrasts the radiological conditions and recent monitoring results associated with five large ongoing FUSRAP projects including Maywood, N.J.; the Linde site near Buffalo, N.Y.; Colonie in Albany N.Y. and the St Louis, Mo. airport and downtown sites. The radiological characteristics of soil and debris at each site and respective regulatory clean up criteria is presented and contrasted. Some differences are discussed in the radiological characteristics of material at some sites that result in variations in radiation protection monitoring programs. Additionally, summary data for typical personnel radiation exposure monitoring results are presented. In summary: 1. The FUSRAP projects for which data and observations are reported in this paper are considered typical of the radiological nature of FUSRAP sites in general. 2. These sites are characterized by naturally occurring uranium and thorium series radionuclides in soil and debris, at

  4. Final audit report of remedial action construction at the UMTRA Project, Grand Junction, Colorado, processing site

    SciTech Connect

    1995-02-01

    This final audit report (FAR) for remedial action at the Grand Junction, Colorado, Uranium Mill Tailings Remedial Action (UMTRA) Project processing site consists of a summary of the radiological surveillances/ audits, the quality assurance (QA) in-process surveillances, and the QA final close-out inspection performed by the US Department of Energy (DOE) and Technical Assistance Contractor (TAC). The FAR also summarizes other surveillances performed by the US Nuclear Regulatory Commission (NRC). To summarize, a total of one finding and 127 observations were noted during DOE/TAC audit and surveillance activities. The NRC noted general site-related observations during the OSCRs. Follow-up to responses required from MK-Ferguson for the DOE/TAC finding and observations indicated that all issues related to the Grand Junction processing site were resolved and closed out to the DOE`s satisfaction. The NRC OSCRs resulted in no issues related to the Grand Junction processing site requiring a response from MK-Ferguson.

  5. 48 CFR 301.607-78 - Contracting Officer designation of a Program/Project Manager as the Contracting Officer's...

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 48 Federal Acquisition Regulations System 4 2012-10-01 2012-10-01 false Contracting Officer designation of a Program/Project Manager as the Contracting Officer's Technical Representative. 301.607-78 Section 301.607-78 Federal Acquisition Regulations System HEALTH AND HUMAN SERVICES GENERAL...

  6. 48 CFR 301.607-78 - Contracting Officer designation of a Program/Project Manager as the Contracting Officer's...

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 48 Federal Acquisition Regulations System 4 2011-10-01 2011-10-01 false Contracting Officer designation of a Program/Project Manager as the Contracting Officer's Technical Representative. 301.607-78 Section 301.607-78 Federal Acquisition Regulations System HEALTH AND HUMAN SERVICES GENERAL...

  7. Recommendations for improving the home office project licence abstracts.

    PubMed

    Hudson, Michelle

    2006-05-01

    The Freedom of Information Act 2000 prompted the Government to evaluate how public understanding about the use of animals in scientific research can be improved and how animal experimentation is regulated within the UK. This resulted in the publication of anonymous project licence abstracts. Here, the abstracts published between December 2004 and October 2005 have been evaluated, by using a scoring system which takes into account their content and format, in order to assess whether they provide information that will facilitate the increased implementation of reduction, refinement and replacement strategies. The potential impact of freely-available Home Office project licence abstracts on public attitudes to animal testing and on the quality of animal-based research, is also discussed. Although some abstracts scored well, in general, the abstracts were found to be severely lacking in detail about the welfare of experimental animals. Thus, the abstracts tend to present a distorted picture of animal-based research. Many abstracts lack the details which would reveal how the licensing criteria had been met. It is concluded that, in their current form, the project abstracts are not sufficiently informative. A number of recommendations are made, which address this problem. PMID:16704294

  8. Key programmatic steps and activities for implementing the Uranium Mill Tailings Remedial Action Project. [UMTRA Project

    SciTech Connect

    Not Available

    1985-07-01

    The Uranium Mill Tailings Radiation Control Act of 1978 (UMTRCA) was enacted based upon findings by Congress that uranium mill tailings located at active and inactive hazard to the public, and that protection of the public health, safety and welfare, and the regulations of interstate commerce, require that every reasonable effort be made to provide for the stabilization, disposal, and control in a safe and environmentally sound manner of such tailings in order to prevent or minimize radon diffusion into the environment and to prevent or minimize other environmental hazards from such tailings.'' A general understanding of the steps leading to elimination of the hazards associated with designated uranium mill tailings sites, and the parties involved in that effort, are presented in this document. A representative schedule is also presented in this document to show both program sequence and activity interdependence. Those activities that have the most potential to influence program duration, because of the significant amount of additional time that may be required, include identification and selection of a suitable site, field data collection delays due to weather, actual acquisition of the designated or alternate disposal site, construction delays due to weather, and site licensing. This document provides an understanding of the steps, the sequence, the parties involved, and a representative duration of activities leading to remedial action and cleanup at the designated inactive uranium mill tailings sites. 10 refs., 5 figs., 1 tab.

  9. OPTIMIZATION OF IN-SITU THERMAL REMEDIATION: THE LORING AFB STEAM INJECTION PROJECT EXAMPLE

    EPA Science Inventory

    Environmental remediation programs require that adequate planning be done before field work for characterization or remediation is undertaken. However, the heterogeneous nature of the subsurface can often thwart our best planning efforts. More recently, dynamic work plans which...

  10. Tank waste remediation system year 2000 dedicated file server project HNF-3418 project plan

    SciTech Connect

    SPENCER, S.G.

    1999-04-26

    The Server Project is to ensure that all TWRS supporting hardware (fileservers and workstations) will not cause a system failure because of the BIOS or Operating Systems cannot process Year 2000 dates.

  11. U.S. Department of Energy Uranium Mill Tailings Remedial Action Ground Water Project: Project plan

    SciTech Connect

    Not Available

    1994-09-01

    The scope of the Project is to develop and implement a ground water compliance strategy for all 24 UMTRA Project processing sites. The compliance strategy for the processing sites must satisfy the proposed EPA ground water cleanup standards in 40 CFR Part 192, Subparts B and C (1987). This scope of work will entail the following activities on a site-specific basis: Develop a compliance strategy based on modification of the UMTRA Surface Project RAPs or develop Ground Water Project RAPs with NRC concurrence on the RAP and full participation of the affected states and tribes. Implement the RAP to include institutional controls, where appropriate, as an interim measure until compliance with the standards is achieved. Institute long-term verification monitoring for transfer to a separate long-term surveillance program on or before the Project end date. Prepare certification or confirmation reports and modify the long-term surveillance plan (LTSP), where needed, on those sites completed prior to the Project end date.

  12. Constellation Program Mission Operations Project Office Status and Support Philosophy

    NASA Technical Reports Server (NTRS)

    Smith, Ernest; Webb, Dennis

    2007-01-01

    The Constellation Program Mission Operations Project Office (CxP MOP) at Johnson Space Center in Houston Texas is preparing to support the CxP mission operations objectives for the CEV/Orion flights, the Lunar Lander, and and Lunar surface operations. Initially the CEV will provide access to the International Space Station, then progress to the Lunar missions. Initial CEV mission operations support will be conceptually similar to the Apollo missions, and we have set a challenge to support the CEV mission with 50% of the mission operations support currently required for Shuttle missions. Therefore, we are assessing more efficient way to organize the support and new technologies which will enhance our operations support. This paper will address the status of our preparation for these CxP missions, our philosophical approach to CxP operations support, and some of the technologies we are assessing to streamline our mission operations infrastructure.

  13. SAFETY IMPROVES DRAMATICALLY IN FLUOR HANFORD SOIL AND GROUNDWATER REMEDIATION PROJECT

    SciTech Connect

    GERBER MS

    2007-12-05

    This paper describes dramatic improvements in the safety record of the Soil and Groundwater Remediation Project (SGRP) at the Hanford Site in southeast Washington state over the past four years. During a period of enormous growth in project work and scope, contractor Fluor Hanford reduced injuries, accidents, and other safety-related incidents and enhanced a safety culture that earned the SGRP Star Status in the Department of Energy's (DOE's) Voluntary Protection Program (VPP) in 2007. This paper outlines the complex and multi-faceted work of Fluor Hanford's SGRP and details the steps taken by the project's Field Operations and Safety organizations to improve safety. Holding field safety meetings and walkdowns, broadening safety inspections, organizing employee safety councils, intensively flowing down safety requirements to subcontractors, and adopting other methods to achieve remarkable improvement in safety are discussed. The roles of management, labor and subcontractors are detailed. Finally, SGRP's safety improvements are discussed within the context of overall safety enhancements made by Fluor Hanford in the company's 11 years of managing nuclear waste cleanup at the Hanford Site.

  14. Safety Improves Dramatically In Fluor Hanford Soil and Groundwater Remediation Project

    SciTech Connect

    Foster, A.L.; Gerber, M.S.; VonBargen, B.H.

    2008-07-01

    This paper describes dramatic improvements in the safety record of the Soil and Groundwater Remediation Project (SGRP) at the Hanford Site in southeast Washington state over the past four years. During a period of enormous growth in project work and scope, contractor Fluor Hanford reduced injuries, accidents, and other safety-related incidents and enhanced a safety culture that earned the SGRP Star Status in the Department of Energy's (DOE's) Voluntary Protection Program (VPP) in 2007. This paper outlines the complex and multi-faceted work of Fluor Hanford's SGRP and details the steps taken by the project's Field Operations and Safety organizations to improve safety. Holding field safety meetings and walk-downs, broadening safety inspections, organizing employee safety councils, intensively flowing down safety requirements to subcontractors, and adopting other methods to achieve remarkable improvement in safety are discussed. The roles of management, labor and subcontractors are detailed. Finally, SGRP's safety improvements are discussed within the context of overall safety enhancements made by Fluor Hanford in the company's 11 years of managing nuclear waste cleanup at the Hanford Site. (authors)

  15. Vicinity Property Assessments at Formerly Utilized Sites Remedial Action Program Project Sites in the New York District - 13420

    SciTech Connect

    Ewy, Ann; Hays, David

    2013-07-01

    The Formerly Utilized Sites Remedial Action Program (FUSRAP) has addressed sites across the nation for almost 4 decades. Multiple stake holder pressures, multiple regulations, and process changes occur over such long time periods. These result in many challenges to the FUSRAP project teams. Initial FUSRAP work was not performed under Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Records of Decision (ROD). The ROD identifies the remedy decision and ultimately the criteria to be used to release a site. Early FUSRAP projects used DOE Orders or the Uranium Mill Tailings Radiation Control Act (UMTRCA) standards. Under current RODs, regulations may differ, resulting in different cleanup criteria than that used in prior Vicinity Property (VP) remediation. The USACE, in preparation for closeout of Sites, conducts reviews to evaluate whether prior actions were sufficient to meet the cleanup criteria specified in the current ROD. On the basis of these reviews, USACE has conducted additional sampling, determined that prior actions were sufficient, or conducted additional remediation consistent with the selected remedy in the ROD. As the public pressures, regulations, and processes that the FUSRAP encounters continue to change, the program itself continues to evolve. Assessment of VPs at FUSRAP sites is a necessary step in the life cycle of our site management. (authors)

  16. Investigation of the Use of "Cucumis Sativus" for Remediation of Chromium from Contaminated Environmental Matrices: An Interdisciplinary Instrumental Analysis Project

    ERIC Educational Resources Information Center

    Butler, Lynsey R.; Edwards, Michael R.; Farmer, Russell; Greenly, Kathryn J.; Hensler, Sherri; Jenkins, Scott E.; Joyce, J. Michael; Mann, Jason A.; Prentice, Boone M.; Puckette, Andrew E.; Shuford, Christopher M.; Porter, Sarah E. G.; Rhoten, Melissa C.

    2009-01-01

    An interdisciplinary, semester-long project is presented in which students grow Cucumis sativus (cucumber) plants from seeds and study the ability of the plants to remediate a heavy metal from contaminated soil or water or both. Phytoremediation strategies for environmental cleanup are presented as possible alternatives to chemical based clean-up…

  17. Economic impact study of the Uranium Mill Tailings Remedial Action project in Colorado: Colorado state fiscal year 1995. Revision 1

    SciTech Connect

    1995-12-01

    As required by the Romer-Twining Agreement of 1990, the US Department of Energy (DOE) has prepared this annual economic impact study for the state of Colorado. This report assesses the economic impacts related to the DOE Uranium Mill Tailings Remedial Action (UMTRA) Project in Colorado during the state fiscal year (FY) between 1 July 1994 and 30 June 1995. To estimate net economic benefit, employment, salaries and wages, and other related economic benefits are discussed, quantified, and then compared to the state`s 10 percent share of the remedial action costs. Actual data obtained from sites currently undergoing remedial action were used as the basis for analyses. If data were not available, estimates were used to derive economic indicators. This study describes the types of employment associated with the UMTRA Project and estimates of the numbers of people employed by UMTRA Project subcontractors in Colorado during state FY 1995. Employment totals are reported in estimated average annual jobs; however, the actual number of workers at the site fluctuates depending on weather and on the status of remedial action activities. In addition, the actual number of people employed on the Project during the year may be higher than the average annual employment reported due to the temporary nature of some of the jobs.

  18. Project licensing plan for UMTRA (Uranium Mill Tailings Remedial Action) sites

    SciTech Connect

    Not Available

    1984-07-01

    The purpose of the Uranium Mill Tailings Remedial Action (UMTRA) Project Licensing Plan is to establish how a disposal site will be licensed, and to provide responsibilities of participatory agencies as legislated by the Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978 (Public Law 95-604). This Plan has been developed to ensure that the objectives of licensing are met by identifying the necessary institutional controls, participatory agency responsibilities, and key milestones in the licensing process. The Plan contains the legislative basis for and a description of the licensing process ( Process'') for UMTRA sites. This is followed by a discussion of agency responsibilities, and milestones in the Process. The Plan concludes with a generic timeline of this Process. As discussed in Section 2.1, a custodial maintenance and surveillance plan will constitute the basis for a site license. The details of maintenance and surveillance are discussed in the Project Maintenance and Surveillance Plan (AL-350124.0000). 5 refs., 4 figs.

  19. Low Emissions Alternative Power (LEAP) Project Office Business Team of the Aeropropulsion Research Program Office (ARPO) Org. 0140

    NASA Technical Reports Server (NTRS)

    Buttler, Jennifer A.

    2004-01-01

    The program for which I am working at this summer is Propulsion and Power/Low Emissions Alternative Power (P&P/LEAP). It invests in a fundamental TRL 1-6 research and technology portfolio that will enable the future of: Alternative fuels and/or alternative propulsion systems, non-combustion (electric) propulsion systems. P&P/LEAP will identify and capitalize on the highest potential concepts generated both internal and external to the Agency. During my 2004 summer at NASA Glenn Research Center, I worked with my mentor Barbara Mader, in the Project Office with the Business Team completing various tasks for the project and personnel. The LEAP project is a highly matrixed organization. The Project Office is responsible for the goals advocacy and dollar (budget) of the LEAP project. The objectives of the LEAP Project are to discover new energy sources and develop unconventional engines and power systems directed towards greatly reduced emissions, enable new vehicle concepts for public mobility, new science missions and national security. The Propulsion and PowerLow Emissions Alternative Power directly supports the environmental, mobility, national security objectives of the Vehicle Systems Program and the Aeronautics Technology Theme. Technology deliverables include the demonstration through integrated ground tests, a constant volume combustor in an engine system, and UAV/small transport aircraft all electric power system. My mentor serves as a key member of the management team for the Aeropropulsion Research Program Office (ARPO). She has represented the office on numerous occasions, and is a member of a number of center-wide panels/teams, such as the Space management Committee and is chair to the Business Process Consolidation Team. She is responsible for the overall coordination of resources for the Propulsion and Power Project - from advocacy to implementation. The goal for my summer at NASA was to document processes and archive program documents from the past

  20. Economic impact study of the Uranium Mill Tailings Remedial Action Project in Colorado: Colorado state fiscal year 1994

    SciTech Connect

    Not Available

    1994-11-01

    The Colorado economic impact study summarizes employment and economic benefits to the state from activities associated with the Uranium Mill Tailings Remedial Action (UMTRA) Project during Colorado state fiscal year 1994. To capture employment information, a questionnaire was distributed to subcontractor employees at the active UMTRA Project sites of Grand Junction, Naturita, Gunnison, and Rifle, Colorado. Economic data were requested from each site prime subcontractor, as well as from the Remedial Action Contractor. The most significant benefits associated with the UMTRA Project in Colorado are summarized. This study assesses benefits associated with the Grand Junction, Gunnison, Naturita, and Rifle UMTRA Projects sites for the 1-year period under study. Work at the Naturita site was initiated in April 1994 and involved demolition of buildings at the processing site. Actual start-up of remediation of Naturita is planned to begin in the spring of 1995. Work at the Slick Rock and Maybell sites is expected to begin in 1995. The only current economic benefits associated with these sites are related to UMTRA Project support work.

  1. The software analysis project for the Office of Human Resources

    NASA Technical Reports Server (NTRS)

    Tureman, Robert L., Jr.

    1994-01-01

    There were two major sections of the project for the Office of Human Resources (OHR). The first section was to conduct a planning study to analyze software use with the goal of recommending software purchases and determining whether the need exists for a file server. The second section was analysis and distribution planning for retirement planning computer program entitled VISION provided by NASA Headquarters. The software planning study was developed to help OHR analyze the current administrative desktop computing environment and make decisions regarding software acquisition and implementation. There were three major areas addressed by the study: current environment new software requirements, and strategies regarding the implementation of a server in the Office. To gather data on current environment, employees were surveyed and an inventory of computers were produced. The surveys were compiled and analyzed by the ASEE fellow with interpretation help by OHR staff. New software requirements represented a compilation and analysis of the surveyed requests of OHR personnel. Finally, the information on the use of a server represents research done by the ASEE fellow and analysis of survey data to determine software requirements for a server. This included selection of a methodology to estimate the number of copies of each software program required given current use and estimated growth. The report presents the results of the computing survey, a description of the current computing environment, recommenations for changes in the computing environment, current software needs, management advantages of using a server, and management considerations in the implementation of a server. In addition, detailed specifications were presented for the hardware and software recommendations to offer a complete picture to OHR management. The retirement planning computer program available to NASA employees will aid in long-range retirement planning. The intended audience is the NASA civil

  2. The Detection and Remediation of Learning Disabilities. Child Welfare Research and Demonstration Project. Final Report.

    ERIC Educational Resources Information Center

    Bechtel, Leland P.

    Reported are the final 2 years of a program which provided identification and remediation services for 60 potentially dyslexic preschool children and 45 dyslexic elementary grade children. Described for the preschool program are materials and evaluative devices and methods of remediation which stressed development of perceptual motor skills,…

  3. 40 CFR 300.120 - On-scene coordinators and remedial project managers: general responsibilities.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ..., and the CERCLA cost recovery activity. When a removal and remedial action occur at the same site, the... through design and remedial action and the CERCLA cost recovery activity. The OSC and RPM shall ensure... ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) SUPERFUND, EMERGENCY PLANNING, AND COMMUNITY RIGHT-TO-KNOW...

  4. 40 CFR 300.120 - On-scene coordinators and remedial project managers: general responsibilities.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 40 Protection of Environment 29 2013-07-01 2013-07-01 false On-scene coordinators and remedial... of responsibility begins prior to initiation of the remedial investigation/feasibility study (RI/FS... period of responsibility begins prior to initiation of the RI/FS, described in § 300.430, and...

  5. SETTING DATA QUALITY OBJECTIVES FOR THERMALLY ENHANCED, IN SITU REMEDIATION PROJECTS

    EPA Science Inventory

    The design and implementation of an in-situ technology requires an up-front and clear understanding of the remedial objectives of the technology application and the data that will be collected to track the progress of remediation and to assess the ultimate success of in-sit...

  6. Weldon Spring Site Remedial Action Project quarterly environmental data summary for second quarter 1998

    SciTech Connect

    1998-08-11

    In support of the Weldon Spring Site Remedial Action Project Federal Facilities Agreement, a copy of the Quarterly Environmental Data Summary (QEDS) for the second quarter of 1998 is enclosed. The data presented constitutes the QEDS. The data were received from the contract laboratories, verified by the Weldon Spring Site verification group and, except for air monitoring data and site KPA generated data (uranium analyses), merged into the database during the second quarter of 1998. Air monitoring data presented are the most recent complete sets of quarterly data. Air data are not stored in the database and KPA data are not merged into the regular database. All data received and verified during the second quarter were within a permissible range of variability, except for those listed. Above normal occurrences are cited for groundwater, air, and NPDES data. There were no above normal occurrences for springs or surface water. The attached tables present the most recent data for air and the data merged into the database during the second quarter 1998 for groundwater, NPDES, surface water, and springs.

  7. Weldon Spring Site environmental report for calendar year 1993. Weldon Springs Site Remedial Action Project

    SciTech Connect

    Not Available

    1994-05-01

    This Site Environmental Report for Calendar Year 1993 describes the environmental monitoring programs at the Weldon Spring Site Remedial Action Project (WSSRAP). The objectives of these programs are to assess actual or potential exposure to contaminant effluents from the project area by providing public use scenarios and dose estimates, to demonstrate compliance with Federal and State permitted levels, and to summarize trends and/or changes in contaminant concentrations from environmental monitoring program. In 1993, the maximum committed dose to a hypothetical individual at the chemical plant site perimeter was 0.03 mrem (0.0003 mSv). The maximum committed dose to a hypothetical individual at the boundary of the Weldon Spring Quarry was 1.9 mrem (0.019 mSv). These scenarios assume an individual walking along the perimeter of the site-once a day at the chemical plant/raffinate pits and twice a day at the quarry-250 days per year. This hypothetical individual also consumes fish, sediment, and water from lakes and other bodies of water in the area. The collective dose, based on an effected population of 112,000 was 0.12 person-rem (0.0012 person-Sv). This calculation is based on recreational use of the August A. Busch Memorial Conservation Area and the Missouri Department of Conservation recreational trail (the Katy Trail) near the quarry. These estimates are below the U.S. Department of Energy requirement of 100 mrem (I mSv) annual committed effective dose equivalent for all exposure pathways. Results from air monitoring for the National Emission Standards for Hazardous Air Pollutants (NESHAPs) program indicated that the estimated dose was 0.38 mrem, which is below the U.S. Environmental Protection Agency (EPA) standard of 10 mrem per year.

  8. The office of real soon now, western pilot (projectors in offices project)

    SciTech Connect

    Uselton, S L

    2002-03-11

    The ASCI VIEWS program at Lawrence Livermore National Laboratory (LLNL) has been investigating a variety of display technologies, motivated by the large size, high resolution and complexity of some data sets that ASCI users explore and analyze. The purpose of this report is to describe the design, deployment and initial user reactions to one display system. The inspiration for the system comes from a similar experimental deployment at the University of North Carolina at Chapel Hill (UNC), one of the VIEWS program's academic partners. The display system features the use of multiple projectors in individual offices creating oversized displays to replace standard monitors. Some discussion on alternative multi-projector display systems provides context for this description.The VIEWS program began exploring the possibilities of alternative displays by building large, tiled displays and supporting the development of extremely high-pixel density LCD panels [ASCI]. The same considerations have led to partnerships with several groups of researchers working on various aspects of multi-projector display systems including groups at UNC, Stanford University, Princeton University, the University of Utah, Argonne National Lab, and the two NSF supercomputer centers, NCSA and SDSC. This report is divided into eight sections. The following section describes the background for the development of this multi-projector display system, including brief descriptions of other large-format and high-resolution display projects, and provides some LLNL motivations for exploring further. Section III covers the evolution of the design intended specifically for LLNL and explains some of the factors that influenced the decisions made. Section IV provides a detailed description of the two installations, including materials and resources involved. After a few weeks of experience with the systems, the users were interviewed and their reactions and comments are summarized in Section V. Conclusions

  9. Economic impact study of the Uranium Mill Tailings Remedial Action Project in Colorado: Colorado State fiscal year 1994. Revision 1

    SciTech Connect

    Not Available

    1994-12-01

    The Colorado economic impact study summarizes employment and economic benefits to the state from activities associated with the Uranium Mill Tailings Remedial Action (UMTRA) Project during Colorado state fiscal year 1994 (1 July 1993 through 30 June 1994). To capture employment information, a questionnaire was distributed to subcontractor employees at the active UMTRA Project sites of Grand Junction, Naturita, Gunnison, and Rifle, Colorado. Economic data were requested from each site prime subcontractor, as well as from the Remedial Action Contractor. Information on wages, taxes, and subcontract expenditures in combination with estimates and economic multipliers is used to estimate the dollar economic benefits to Colorado during the state fiscal year. Finally, the fiscal year 1994 estimates are compared to fiscal year 1993 employment and economic information.

  10. Colorado economic impact study on the Uranium Mill Tailings Remedial Action Project in Colorado: Colorado state fiscal year 1993

    SciTech Connect

    Not Available

    1993-11-12

    The Colorado economic impact study summarizes employment and economic benefits to the state from activities associated with the Uranium Mill Tailings Remedial Action (UMTRA) Project during Colorado state fiscal year (FY) 1993. To capture employment benefits, a questionnaire was distributed to subcontractor employees at the active UMTRA Project sites of Grand Junction, Rifle, and Gunnison, Colorado. An estimated 52 percent of the employees working on the UMTRA Project responded to this information request. Economic data were requested from each prime subcontractor, as well as from the Remedial Action Contractor. The most significant benefits associated with the UMTRA Project in Colorado are: Direct employment was estimated at 894 workers; An estimated 89 percent of all direct employment was local; Secondary employment resulting from remedial action at the active Colorado UMTRA Project sites and the Grand Junction vicinity property program is estimated at 546 workers. Total employment (direct and secondary) is estimated at 1440 workers for the period of study (July 1, 1992, to June 30, 1993). An estimated $24.1 million was paid in wages to UMTRA workers in Colorado during FY1993; Direct and secondary wage earnings were estimated at $39.9 million; Income tax payments to the state of Colorado were estimated at $843,400 during FY1993; The gross economic impact of UMTRA Project activities in the state of Colorado is estimated at $70 million during the 1-year study period; and the net economic benefit to the state of Colorado was estimated at $57.5 million, or $5.90 per dollar of funding provided by Colorado. This figure includes both direct and secondary benefits but does not include the impact of alternative uses of the state funding.

  11. Plutonium immobilization project development and testing technical project office quality assurance program description

    SciTech Connect

    Gould, T H; MacLean, L M; Ziemba, J M

    1999-07-08

    The Plutonium Immobilization Project (PIP) is one of several fissile materials disposition projects managed by the Department of Energy (DOE) Office of Fissile Materials Disposition (OFMD). The PIP is expected to evolve from the current Development and Testing (D and T) effort, to design, to construction, and finally to operations. Overall management and technical management of the D and T effort resides at the Lead Laboratory, Lawrence Livermore National Laboratory (LLNL), through the LLNL Manager, Fissile Materials Disposition Program (FMDP). Day to day project activities are managed by the D and T Technical Project Office (TPO), which reports to the LLNL Manager, FMDP. The D and T TPO consists of the Technical Manager, the TPO Quality Assurance (QA) Program Manager, and TPO Planning and Support Staff. This Quality Assurance Program Description (QAPD) defines the QA policies and controls that will be implemented by these TPO personnel in their management of D and T activities. This QAPD is consistent with and responsive to the Department of Energy Fissile Materials Disposition Program Quality Assurance Requirements Document (FMDP QARD). As the Project and upper level requirement's documents evolve, this QAPD will be updated as necessary to accurately define and describe the QA Program and Management of the PIP. The TPO has a policy that all development and testing activities be planned, performed and assessed in accordance with its customer's requirements, needs and expectations, and with a commitment to excellence and continuous improvement. The TPO QAPD describes implementation requirements which, when completed, will ensure that the project development and testing activities conform to the appropriate QA requirements. For the program to be effective, the TPO QA Program Manager will ensure that each site participating in D and T activities has developed a QAPD, which meets the customer's requirements, and has a designated quality leader in place. These customer

  12. Identification of remediation needs and technology development focus areas for the Environmental Restoration (ER) Project at Sandia National Laboratories/New Mexico (SNL/NM)

    SciTech Connect

    Tucker, M.D.; Valdez, J.M.; Khan, M.A.

    1995-06-01

    The Environmental Restoration (ER) Project has been tasked with the characterization, assessment, remediation and long-term monitoring of contaminated waste sites at Sandia National Laboratories/New Mexico (SNL/NM). Many of these sites will require remediation which will involve the use of baseline technologies, innovative technologies that are currently under development, and new methods which will be developed in the near future. The Technology Applications Program (TAP) supports the ER Project and is responsible for development of new technologies for use at the contaminated waste sites, including technologies that will be used for remediation and restoration of these sites. The purpose of this report is to define the remediation needs of the ER Project and to identify those remediation needs for which the baseline technologies and the current development efforts are inadequate. The area between the remediation needs and the existing baseline/innovative technology base represents a technology gap which must be filled in order to remediate contaminated waste sites at SNL/NM economically and efficiently. In the first part of this report, the remediation needs of the ER Project are defined by both the ER Project task leaders and by TAP personnel. The next section outlines the baseline technologies, including EPA defined Best Demonstrated Available Technologies (BDATs), that are applicable at SNL/NM ER sites. This is followed by recommendations of innovative technologies that are currently being developed that may also be applicable at SNL/NM ER sites. Finally, the gap between the existing baseline/innovative technology base and the remediation needs is identified. This technology gap will help define the future direction of technology development for the ER Project.

  13. Office of Maternal and Child Health Active Projects FY 1989. An Annotated Listing.

    ERIC Educational Resources Information Center

    National Center for Education in Maternal and Child Health, Washington, DC.

    An annotated listing is presented of projects offering maternal and child health care services. These projects, referred to as special projects of regional and national significance (SPRANS), are supported by the Office of Maternal and Child Health of the Department of Health and Human Services. The first section provides information on services…

  14. State of Nevada, Agency for Nuclear Projects/Nuclear Waste Project Office narrative report, January 1992

    SciTech Connect

    1992-12-31

    The Agency for Nuclear Projects/Nuclear Waste Project Office (NWPO) is the State of Nevada agency designated by State law to monitor and oversee US Department of Energy (DOE) activities relative to the possible siting, construction, operation and closure of a high-level nuclear waste repository at Yucca Mountain and to carry out the State of Nevada`s responsibilities under the Nuclear Waste Policy Act of 1982. During the reporting period the NWPO continued to work toward the five objectives designed to implement the Agency`s oversight responsibilities: (1) Assure that the health and safety of Nevada`s citizens are adequately protected with regard to any federal high-level radioactive waste program within the State; (2) Take the responsibilities and perform the duties of the State of Nevada as described in the Nuclear Waste Policy Act of 1982 (Public Law 97-425) and the Nuclear Waste Policy Amendments Act of 1987; (3) Advise the Governor, the State Commission on Nuclear Projects and the Nevada State Legislature on matters concerning the potential disposal of high-level radioactive waste in the State; (4) Work closely and consult with affected local governments and State agencies; (5) Monitor and evaluate federal planning and activities regarding high-level radioactive waste disposal. Plan and conduct independent State studies regarding the proposed repository.

  15. Sour gas plant remediation technology research and demonstration project, Task 7.53. Topical report, January--December 1993

    SciTech Connect

    Stepan, D.J.; Kuehnel, V.; Schmit, C.R.

    1994-02-01

    Recognizing the potential impacts of sour gas plant operations on the subsurface environment, the Canadian Association of Petroleum Producers (CAPP) and Environment Canada initiated a multiphase study focusing on research related to the development and demonstration of remedial technologies for soil and groundwater contamination at these facilities. Research performed under this project was designed to supplement and be coordinated with research activities being conducted at an operational sour gas plant located in Rocky Mountain House, Alberta, Canada. These research tasks included hydrogeological site characterization, subsurface contaminant characterization, ex situ treatment of groundwater, and subsurface remediation of residual contamination in the unsaturated zone. Ex situ treatment of groundwater included evaluations of air stripping, steam stripping, advanced oxidation, and biological treatment, as well as the development of an artificial freeze crystallization process. Soil vapor extraction was evaluated as a technique to address residual contamination in the unsaturated zone.

  16. View of rear façade of office building; note projecting bay, ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    View of rear façade of office building; note projecting bay, above the basement level, which commanded a view of the iron works - Everett Iron Company, Office Building, 0.25 mile Southwest of Everett, Earlston, Bedford County, PA

  17. Savannah River National Laboratory (SRNL) evaluations of absorbents for the TRU Remediation Project

    SciTech Connect

    Carraway, Anthony C.; Hill, Larry

    2005-10-17

    SRNL has been preparing to receive transuranic (TRU) waste drums from the Solid Waste Management Facility (SWMF) to aid in the remediation of Waste Acceptance Criteria prohibited items in SRS TRU waste drums. These prohibited items are primarily containerized liquids and aerosol cans which are easily identified using radiography. The remediation of these drums requires the use of an approved absorbent that is acceptable to the SWMF and Waste Isolation Pilot Plan (WIPP) for disposal. The goal of this document is to help establish guidelines that should be met to produce a final waste product that will be acceptable at the WIPP facility.

  18. Agency for Nuclear Projects/Nuclear Waste Project Office final progress report

    SciTech Connect

    1992-12-31

    The Nevada Agency for Nuclear Projects/Nuclear Waste Project Office (NWPO) was formally established by Executive Policy in 1983 following passage of the federal Nuclear Waste Policy Act of 1982 (Act). That Act provides for the systematic siting, construction, operation, and closure of high-level radioactive defense and research by-products and other forms of high-level radioactive waste from around the country which will be stored at such repositories. In 1985 the Nevada legislature formally established the NWPO as a distinct and statutorily authorized agency to provide support to the Governor and State Legislature on matters concerning the high-level nuclear waste programs. The NWPO utilized a small, central staff supplemented by contractual services for needed technical and specialized expertise in order to provide high quality oversight and monitoring of federal activities, to conduct necessary independent studies, and to avoid unnecessary duplication of efforts. This report summarizes the results of this ongoing program to ensure that risks to the environment and to human safety are minimized. It includes findings in the areas of hydrogeology, geology, quality assurance activities, repository engineering, legislature participation, socioeconomic affects, risk assessments, monitoring programs, public information dissemination, and transportation activities. The bulk of the reporting deals with the Yucca Mountain facility.

  19. 40 CFR 300.120 - On-scene coordinators and remedial project managers: general responsibilities.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... hazardous waste management facilities or in similarly chronic incidents. The USCG shall provide an initial response to discharges or releases from hazardous waste management facilities within the coastal zone in... funded remedial actions, except in the case of state-lead federally funded response and as provided...

  20. SYNTHESIS REPORT ON FIVE DENSE, NONAQUEOUS-PHASE LIQUID (DNAPL) REMEDIATION PROJECTS

    EPA Science Inventory

    Dense non-aqueous phase liquid (DNAPL) poses a difficult problem for subsurface remediation because it serves as a continuing source to dissolved phase ground water contamination and is difficult to remove from interstitial pore space or bedrock fractures in the subsurface. Numer...

  1. Uranium Mill Tailings Remedial Action Project (UMTRAP), Rifle, Colorado: Phase 2, Construction drawings [Engineering Materials

    SciTech Connect

    Not Available

    1991-05-13

    This document consists of engineering drawings related to the remedial action of the Old Rifle Processing site, the New Rifle Processing site, and the Estes Gulch disposal site. This report is intended to accompany report DOE/UMTRA--050506 volume 3, appendix F.

  2. Executive summary: Weldon Spring Site Environmental Report for calendar year 1992. Weldon Spring Site Remedial Action Project, Weldon Spring, Missouri

    SciTech Connect

    Not Available

    1993-06-01

    This report has been prepared to provide information about the public safety and environmental protection programs conducted by the Weldon Spring Site Remedial Action Project. The Weldon Spring site is located in southern St. Charles County, Missouri, approximately 48 km (30 mi) west of St. Louis. The site consists of two main areas, the Weldon Spring Chemical Plant and raffinate pits and the Weldon Spring Quarry. The objectives of the Site Environmental Report are to present a summary of data from the environmental monitoring program, to characterize trends and environmental conditions at the site, and to confirm compliance with environmental and health protection standards and requirements. The report also presents the status of remedial activities and the results of monitoring these activities to assess their impacts on the public and environment. The scope of the environmental monitoring program at the Weldon Spring site has changed since it was initiated. Previously, the program focused on investigations of the extent and level of contaminants in the groundwater, surface waters, buildings, and air at the site. In 1992, the level of remedial activities required monitoring for potential impacts of those activities, particularly on surface water runoff and airborne effluents. This report includes monitoring data from routine radiological and nonradiological sampling activities. These data include estimates of dose to the public from the Weldon Spring site; estimates of effluent releases; and trends in groundwater contaminant levels. Also, applicable compliance requirements, quality assurance programs, and special studies conducted in 1992 to support environmental protection programs are reviewed.

  3. Waste minimization opportunities at the U.S. Uranium Mill Tailings Remedial Action (UMTRA) Project, Rifle, Colorado, site

    SciTech Connect

    Hartmann, G.L.; Arp, S.; Hempill, H.

    1993-12-31

    At two uranium mill sites in Rifle, Colorado, the US Department of Energy (DOE) Uranium Mill Tailings Remedial Action (UMTRA) Project is removing uranium mill tailings and contaminated subgrade soils. This remediation activity will result in the production of groundwater contaminated with uranium, heavy metals, ammonia, sulfates, and total dissolved solids (TDS). The initial remediation plan called for a wastewater treatment plant for removal of the uranium, heavy metals, and ammonia, with disposal of the treated water, which still includes the sulfates and TDSS, to the Colorado River. The National Pollutant Discharge Elimination (NPDES) permit issued by the Colorado Department of Health for the two Rifle sites contained more restrictive discharge limits than originally anticipated. During the detailed review of alternate treatment systems to meet these more restrictive limits, the proposed construction procedures were reviewed emphasizing the methods to minimize groundwater production to reduce the size of the water treatment facility, or to eliminate it entirely. It was determined that with changes to the excavation procedures and use of the contaminated groundwater for use in dust suppression at the disposal site, discharge to the river could be eliminated completely.

  4. The ultrasonic ranging and data system for radiological surveys in the UMTRA (Uranium Mill Tailings Remedial Action) Project

    SciTech Connect

    Little, C.A.; Berven, B.A.; Blair, M.S.; Dickerson, K.S.; Pickering, D.A.

    1988-01-01

    The Ultrasonic Ranging and Data System (USRADS) was developed to allow radiation exposure data and positional information to be collected, stored and analyzed in a more efficient manner than currently employed on the (Uranium Mill Tailings Remedial Action (UMTRA) project. USRADS is a portable unit which employs ultrasonics, radio frequency transmissions, and a personal computer. Operational experience indicates that the system results in increased information about the property with decreased data analysis and transcription effort and only slightly more field effort. 5 refs., 3 figs., 2 tabs.

  5. Building Bridges: Using the Office Consultation Project to Connect Students to Theory and Practice

    ERIC Educational Resources Information Center

    Wawrzynski, Korine Steinke; Jessup-Anger, Jody E.

    2014-01-01

    The Office Consultation Project is an innovative capstone project that partners graduate students in student affairs preparation programs with academic and student affairs practitioners. It provides an opportunity for students to apply research and scholarship to practical settings, while giving practitioners new insight into their units,…

  6. Weldon Spring quarry construction staging area and water treatment plant site remedial action characterization report for the Weldon Spring Site Remedial Action Project, Weldon Spring, Missouri

    SciTech Connect

    Not Available

    1991-09-01

    The quarry construction staging area (QCSA) and water treatment plant (WTP) are located in the areas that border the western edge of the Weldon Spring quarry (WSQ). These facilities were constructed to support bulk waste removal from the WSQ. This area was contaminated with U-238, Ra-226, and Th-230 and was remediated prior to construction in order to allow release of the area for use without radiological restrictions. This report documents the methods of characterization, the remediation activities, and the post remedial action sampling methods and analytical results. 4 refs., 6 figs., 4 tabs.

  7. Mitigation and monitoring plan for impacted wetlands at the Gunnison UMTRA Project site, Gunnison, Colorado. [Uranium Mill Tailings Remedial Action (UMTRA) Project

    SciTech Connect

    Not Available

    1992-06-01

    The U.S Department of Energy (DOE) administers the Uranium Mill Tailings Remedial Action (UMTRA) Project. The UMTRA Project is the result of the Uranium Mill Tailings Radiation Control Act(UMTRA) which was passed in response to the public's concern over the potential public health hazards related to uranium mill tailings and associated contaminated material at abandoned or otherwise uncontrolled inactive processing sites throughout the United States. The Gunnison, Colorado abandoned uranium mill site is one of the sites slated for cleanup by the DOE under authority of UMTRA. The contaminated material at this site will be transported to a disposal site on US Bureau of Land Management (BLM) land east of Gunnison. Remedial action activities will temporarily disturb 0.8 acre and permanently eliminate 5.1 acres of wetlands. This report describes the proposed mitigation plan for the 5.9 acres of impacted wetlands. In conjunction with the mitigation of the permanently impacted wetlands through the enhancement of wetland and adjacent riparian areas, impacts to wildlife as a result of this project will also be mitigated. However, wildlife mitigation is not the focus of this document and is covered in relevant BLM permits for this project. This plan proposes the enhancement of a 3:1 ratio of impacted wetlands in accordance with US Environmental Protection Agency guidelines, plus the enhancement of riparian areas for wildlife mitigation. Included in this mitigation plan is a monitoring plan to ensure that the proposed measures are working and being maintained.

  8. Cancer Genome Anatomy Project | Office of Cancer Genomics

    Cancer.gov

    The National Cancer Institute (NCI) Cancer Genome Anatomy Project (CGAP) is an online resource designed to provide the research community access to biological tissue characterization data. Request a free copy of the CGAP Website Virtual Tour CD from ocg@mail.nih.gov.

  9. Evaluation of Project Components: 1973-74, Maui District Office.

    ERIC Educational Resources Information Center

    Hawaii Univ., Honolulu. Social Welfare Development and Research Center.

    The Elementary and Secondary (ESEA) Title I project components for Hawaii's Maui District are evaluated in this document. The first section reviews the following: the reading resource rooms, the preschools, and the measurement of academic gain as shown by the Peabody Individual Achievement Test. The second section presents a school-by-school…

  10. SF Box--a tool for evaluating the effects on soil functions in remediation projects.

    PubMed

    Volchko, Yevheniya; Norrman, Jenny; Rosén, Lars; Norberg, Tommy

    2014-10-01

    Although remediation is usually aimed at reducing the risks posed by contaminants to human health and the environment, it is also desirable that the remediated soil within future green spaces is capable of providing relevant ecological functions, e.g., basis for primary production. Yet while addressing a contamination problem by reducing contaminant concentration and/or amounts in the soil, the remedial action itself can lead to soil structure disturbances, decline in organic matter and nutrient deficiencies, and in turn affect a soil's capacity to carry out its ecological soil functions. This article presents the Soil Function Box (SF Box) tool that is aimed to facilitate integration of information from suggested soil quality indicators (SQIs) into a management process in remediation using a scoring method. The scored SQIs are integrated into a soil quality index corresponding to 1 of 5 classes. SF Box is applied to 2 cases from Sweden (Kvillebäcken and Hexion), explicitly taking into consideration uncertainties in the results by means of Monte Carlo simulations. At both sites the generated soil quality indices corresponded to a medium soil performance (soil class 3) with a high certainty. The main soil constraints at both Kvillebäcken and Hexion were associated with biological activity in the soil, as soil organisms were unable to supply plant-available N. At the Kvillebäcken site the top layer had a content of coarse fragment (ø > 2 mm) higher than 35%, indicating plant rooting limitations. At the Hexion site, the soil had limited amount of organic matter, thus poor aggregate stability and nutrient cycling potential. In contrast, the soil at Kvillebäcken was rich in organic matter. The soils at both sites were capable of storing a sufficient amount of water for soil organisms between precipitation events. PMID:24903441

  11. Environmental assessment of remedial action at the Gunnison Uranium Mill Tailings Site, Gunnison, Colorado. [UMTRA Project

    SciTech Connect

    Bachrach, A.; Hoopes, J.; Morycz, D. ); Bone, M.; Cox, S.; Jones, D.; Lechel, D.; Meyer, C.; Nelson, M.; Peel, R.; Portillo, R.; Rogers, L.; Taber, B.; Zelle, P. , Inc., Washington, DC ); Rice, G. )

    1984-12-01

    This document assesses and compares the environmental impacts of various alternatives for remedial action at the Gunnison uranium of mill tailings site located 0.5 miles south of Gunnison, Colorado. The site covers 56 acres and contains 35 acres of tailings, 2 of the original mill buildings and a water tower. The Uranium Mill Tailings Radiation Control of Act of 1978 (UMTRCA), Public Law 95-604, authorizes the US Department of Energy to clean up the site to reduce the potential health impacts associated with the residual radioactive materials remaining at the site and at associated (vicinity) properties off the site. The US Environmental Protection Agency promulgated standards for the remedial actions (40 CFR 192). Remedial actions must be performed in accordance with these standards and with the occurrence of the Nuclear Regulatory Commission. Four alternatives have been addressed in this document. The first alternative is to consolidate the tailings and associated contaminated soils into a recontoured pile on the southern portion of the existing site. A radon barrier of silty clay would be constructed over the pile and various erosion control measures would be taken to assure the long-term integrity of the pile. Two other alternatives which involve moving the tailings to new locations are assessed in this document. These alternatives generally involve greater short-term impacts and are more costly but would result in the tailings being stabilized in a location farther from the city of Gunnison. The no action alternative is also assessed.

  12. Space Launch Initiative Propulsion Projects Office Overview Briefing

    NASA Technical Reports Server (NTRS)

    Lyles, Garry; Richards, Steve

    2001-01-01

    The goal of this Space Launch Initiative is for NASA to meet its future space flight needs, including human access to space, using commercial launch vehicles that will improve safety and reliability and reduce cost. The topics include: 1) Second Generation RLV Program Overview; 2) Space Launch Initiative (SLI) Investment Areas; 3) SLI Organizational Summary; 4) Propulsion Projects Overview; 5) Current Propulsion Content; and 6) Critical Needs Roadmap. This paper is presented in viewgraph form.

  13. Chemical Research Projects Office: Functions, accomplishments, and programs

    NASA Technical Reports Server (NTRS)

    Kourtides, D. A.; Parker, J. A.

    1972-01-01

    The purpose, technical accomplishments, and related activities of the Chemical Research Project Group are outlined. Data cover efforts made to: (1) identify chemical research and technology required for solutions to problems of national urgency, synchronous with aeronautics and space effort; (2) conduct basic and applied interdisciplinary research on chemical problems in the areas of macromolecular science and fire research, and (3) provide productive liason with the engineering community and effective transfer of technology to other agencies and industry.

  14. Project ExPreSS: Social studies and science remediation program for the Georgia High School Graduation Test

    NASA Astrophysics Data System (ADS)

    Shearouse, Randy

    Over half of the states now require students to pass a high stakes exit exam before being allowed to graduate from high school. No Child Left Behind requires that standardized testing be included to determine whether or not a school makes Adequate Yearly Progress (AYP). The purpose of this study is to examine the results of the Georgia High School Graduation Test (GHSGT) of students who participated in the remedial program Project ExPreSS with those students who did not participate. Using a quantitative research design, the question that will be answered is whether Project ExPreSS makes a difference in passing the GHSGT in science and social studies among three groups: all Georgia students, African American students in one Georgia school system, and all students in one Georgia school system. A chi-square test was conducted and a determination was made that there is a statistically significant relationship between project participation and pass-fail status in all but one area. The majority of students in this study were 17--18 years of age and were taking the science or social studies section of the GHSGT for the second time. The findings of this study will be important not only for Georgia and the school system examined, but also for other states and systems that give High Stakes Exit Exams (HSEEs). The results indicate that highly focused remedial programs like Project ExPreSS make a difference for students who may not be successful on their first attempt at passing a HSEE.

  15. Chemical research projects office: An overview and bibliography, 1975-1980

    NASA Technical Reports Server (NTRS)

    Kourtides, D. A.; Heimbuch, A. H.; Parker, J. A.

    1980-01-01

    The activities of the Chemical Research Projects Office at Ames Research Center, Moffett Field, California are reported. The office conducts basic and applied research in the fields of polymer chemistry, computational chemistry, polymer physics, and physical and organic chemistry. It works to identify the chemical research and technology required for solutions to problems of national urgency, synchronous with the aeronautic and space effort. It conducts interdisciplinary research on chemical problems, mainly in areas of macromolecular science and fire research. The office also acts as liaison with the engineering community and assures that relevant technology is made available to other NASA centers, agencies, and industry. Recent accomplishments are listed in this report. Activities of the three research groups, Polymer Research, Aircraft Operating and Safety, and Engineering Testing, are summarized. A complete bibliography which lists all Chemical Research Projects Office publications, contracts, grants, patents, and presentations from 1975 to 1980 is included.

  16. Uranium Mill Tailings Remedial Action Project Annual Environmental Monitoring Report calendar year 1992: Volume 1

    SciTech Connect

    Not Available

    1993-12-31

    This report describes environmental monitoring and compliance at eight UMTRA sites where remedial action was underway during 1992 and at the ten sites that were complete at the end of 1992. Volume I contains information for Ambrosia Lake, NM; Cannonsburg/Burrell, PA; Durango, CO; Falls City, TX; Grand Junction, CO; Green River, UT; and Gunnison, CO. Each site report contains a site description, compliance summary, environmental program information, environmental radiological and non-radiological program information, water resources protection, and quality assurance information.

  17. Process challenges in rotary kiln-based incinerators in soil remediation projects

    SciTech Connect

    Acharya, P.; Fogo, D.; McBride, C.

    1996-12-31

    Most Superfund sites undergoing thermal remediation consist of high-moisture content (15 to 40 percent) soils having light organic contamination (low-heat content). In the early 1980s, the rotary kiln incinerators employed at these Superfund sites were relatively small mobile hazardous waste incinerators (HWI) built on standard-size semi-trailers. As the industry matured over the past ten years, competition has driven the industry to larger and more efficient rotary kiln systems that minimize the cost per ton of soil treated by increasing the throughput rates and shortening on-site processing time. Because these units are transported from site to site by truck or a combination of rail and truck, the rotary kiln outside shell diameters have peaked to approximately 13.5 feet. Now the focus has shifted to increasing the processing capacity of these existing, maximized fixed-sized systems. Such actions include the use of oxygen-based combustion systems, which increase the throughput and efficiency by improving heat transfer and reducing the volume of combustion gas requiring treatment. However, despite the experience and expertise gained by the participants in the thermal remediation industry, many of the same process challenges still remain. This article discusses these process challenges facing the industry and potential solutions, based on data from IT`s Hybrid Thermal Treatment System{reg_sign} HTTS{reg_sign} and other sources. 10 refs., 2 figs., 3 tabs.

  18. ISS Internal Active Thermal Control System (IATCS) Coolant Remediation Project -2006 Update

    NASA Technical Reports Server (NTRS)

    Morrison, Russell H.; Holt, Mike

    2006-01-01

    The IATCS coolant has experienced a number of anomalies in the time since the US Lab was first activated on Flight 5A in February 2001. These have included: 1) a decrease in coolant pH, 2) increases in inorganic carbon, 3) a reduction in phosphate concentration, 4) an increase in dissolved nickel and precipitation of nickel salts, and 5) increases in microbial concentration. These anomalies represent some risk to the system, have been implicated in some hardware failures and are suspect in others. The ISS program has conducted extensive investigations of the causes and effects of these anomalies and has developed a comprehensive program to remediate the coolant chemistry of the on-orbit system as well as provide a robust and compatible coolant solution for the hardware yet to be delivered. This paper presents a status of the coolant stability over the past year as well as results from destructive analyses of hardware removed from the on-orbit system and the current approach to coolant remediation.

  19. EVALUATION OF THOR MINERALIZED WASTE FORMS FOR THE DOE ADVANCED REMEDIATION TECHNOLOGIES PHASE 2 PROJECT

    SciTech Connect

    Crawford, C.; Jantzen, C.

    2012-02-02

    The U.S. Department of Energy's (DOE) Office of River Protection (ORP) is responsible for the retrieval, treatment, immobilization, and disposal of Hanford's tank waste. Currently there are approximately 56 million gallons of highly radioactive mixed wastes awaiting treatment. A key aspect of the River Protection Project (RPP) cleanup mission is to construct and operate the Waste Treatment and Immobilization Plant (WTP). The WTP will separate the tank waste into high-level and low-activity waste (LAW) fractions, both of which will subsequently be vitrified. The projected throughput capacity of the WTP LAW Vitrification Facility is insufficient to complete the RPP mission in the time frame required by the Hanford Federal Facility Agreement and Consent Order, also known as the Tri-Party Agreement (TPA), i.e. December 31, 2047. Therefore, Supplemental Treatment is required both to meet the TPA treatment requirements as well as to more cost effectively complete the tank waste treatment mission. The Supplemental Treatment chosen will immobilize that portion of the retrieved LAW that is not sent to the WTP's LAW Vitrification facility into a solidified waste form. The solidified waste will then be disposed on the Hanford site in the Integrated Disposal Facility (IDF). In addition, the WTP LAW Vitrification facility off-gas condensate known as WTP Secondary Waste (WTP-SW) will be generated and enriched in volatile components such as Cs-137, I-129, Tc-99, Cl, F, and SO{sub 4} that volatilize at the vitrification temperature of 1150 C in the absence of a continuous cold cap. The current waste disposal path for the WTP-SW is to recycle it to the supplemental LAW treatment to avoid a large steady state accumulation in the pretreatment-vitrification loop. Fluidized Bed Steam Reforming (FBSR) offers a moderate temperature (700-750 C) continuous method by which LAW and/or WTP-SW wastes can be processed irrespective of whether they contain organics, nitrates, sulfates

  20. Independent Verification Survey of the Clean Coral Storage Pile at the Johnston Atoll Plutonium Contaminated Soil Remediation Project

    SciTech Connect

    Wilson-Nichols, M.J.; Egidi, P.V.; Roemer, E.K.; Schlosser, R.M.

    2000-09-01

    f I The Oak Ridge National Laboratory (ORNL) Environmental Technology Section conducted an independent verification (IV) survey of the clean storage pile at the Johnston Atoll Plutonium Contaminated Soil Remediation Project (JAPCSRP) from January 18-25, 1999. The goal of the JAPCSRP is to restore a 24-acre area that was contaminated with plutonium oxide particles during nuclear testing in the 1960s. The selected remedy was a soil sorting operation that combined radiological measurements and mining processes to identify and sequester plutonium-contaminated soil. The soil sorter operated from about 1990 to 1998. The remaining clean soil is stored on-site for planned beneficial use on Johnston Island. The clean storage pile currently consists of approximately 120,000 m3 of coral. ORNL conducted the survey according to a Sampling and Analysis Plan, which proposed to provide an IV of the clean pile by collecting a minimum number (99) of samples. The goal was to ascertain wi th 95% confidence whether 97% of the processed soil is less than or equal to the accepted guideline (500-Bq/kg or 13.5-pCi/g) total transuranic (TRU) activity.

  1. INDEPENDENT TECHNICAL REVIEW OF THE C-400 INTERIM REMEDIAL PROJECT PHASE I RESULTS, PADUCAH, KENTUCKY

    SciTech Connect

    Looney, B.; Rossabi, J.; Stewart,L.; Richards, W.

    2010-10-29

    The groundwater and soil in the vicinity of the C-400 Building at the Paducah Gaseous Diffusion Plant (PGDP), is contaminated with substantial quantities of industrial solvents, primarily trichoroethene (TCE). This solvent 'source' is recognized as a significant challenge and an important remediation target in the overall environmental cleanup strategy for PGDP. Thus, the cleanup of the C-400 TCE Source is a principal focus for the Department of Energy (DOE) and its contractors, and for PGDP regulators and stakeholders. Using a formal investigation, feasibility study and decision process, Electrical Resistance Heating (ERH) was selected for the treatment of the soil and groundwater in the vicinity of C-400. ERH was selected as an interim action to remove 'a significant portion of the contaminant mass of TCE at the C-400 Cleaning Building area through treatment' with the longer term goal of reducing 'the period the TCE concentration in groundwater remains above its Maximum Contaminant Level (MCL).' ERH is a thermal treatment that enhances the removal of TCE and related solvents from soil and groundwater. The heterogeneous conditions at PGDP, particularly the high permeability regional gravel aquifer (RGA), are challenging to ERH. Thus, a phased approach is being followed to implement this relatively expensive and complex remediation technology. Conceptually, the phased approach encourages safety and efficiency by providing a 'lessons learned' process and allowing appropriate adjustments to be identified and implemented prior to follow-on phase(s) of treatment. More specifically, early deployment targeted portions of the challenging RGA treatment zone with relatively little contamination reducing the risk of adverse collateral impacts from underperformance in terms of heating and capture. Because of the importance and scope of the C-400 TCE source remediation activities, DOE chartered an Independent Technical Review (ITR) in 2007 to assess the C-400 ERH plans prior

  2. Quarry Haul Road Ecological Survey. Weldon Spring Site Remedial Action Project, Weldon Spring, Missouri: Revision 1

    SciTech Connect

    Not Available

    1992-09-01

    This biological survey was performed to document the summer flora and fauna found along the haul road constructed as part of the remedial action for the quarry bulk waste. State and Federal species listed as threatened or endangered were noted if encountered while surveying. Sampling locations were equally spaced along the quarry haul road, and a survey for vegetation and birds conducted at each location. Bird observations were conducted as breeding bird surveys once in June of 1991, and again in June of 1992. Each year`s survey includes two observations in the early morning and one late in the evening. Vegetation surveys were conducted in 1991 using quadrants and transects. mammal, reptile, and amphibian sightings were noted as encountered.

  3. Weldon Spring Site Remedial Action Project Federal Facilities Agreement: Quarterly environmental data summary for third quarter 1998

    SciTech Connect

    1998-11-06

    In support of the Weldon Spring Site Remedial Action Project Federal Facilities Agreement, a copy of the Quarterly Environmental Data Summary (QEDS) for the third quarter of 1998 is enclosed. The data presented in this letter and attachment constitute the QEDS. The data, except for air monitoring data and site KPA generated data (uranium analyses), were received from the contract laboratories, verified by the Weldon Spring Site verification group, and merged into the database during the third quarter of 1998. Air monitoring data presented are the most recent complete sets of quarterly data. Significant data, defined as data values that have exceeded defined above normal Level 2 values, are discussed in this letter for Environmental Monitoring Plan (EMP) generated data only. Above normal Level 2 values are based, in ES and H procedures, on historical high values, DOE Derived Concentration Guides (DCGs), NPDES limits, and other guidelines. The procedures also establish actions to be taken in the event that above normal data occur.

  4. Missouri Department of Natural Resources Hazardous Waste Program Weldon Spring site remedial action project - status to date January 1998

    SciTech Connect

    1998-04-01

    This document describes the progress made by the Missouri Department of Natural Resources (MDNR) during the fifth year (1997) of the Agreement in Support (AIS) in its oversight role of the Weldon Springs Site Remedial Action Project (WSSRAP). Staffing issues this year have been a challenge with the resignation of an Environmental Specialist (ES) in June 1997, and the death of Robert Stovall, an Environmental Engineer (EE) II in August 1997. Progress made during this period includes securing a contract laboratory, participation in several workgroup meetings for activities at the site, oversight of the Feasibility Study/Proposed Plan (FS/PP), coordination between the US Department of Energy and the various State regulatory programs and interactions with the local public drinking water supply agency and health departments.

  5. Remedial Action Plan and site design for stabilization of the inactive uranium mill tailings site at Falls City, Texas. [Uranium Mill Tailings Remedial Action (UMTRA) Project

    SciTech Connect

    Chernoff, A.R. . Uranium Mill Tailings Remedial Action Project Office); Lacker, D.K. . Bureau of Radiation Control)

    1992-09-01

    The uranium processing site near Falls City, Texas, was one of 24 inactive uranium mill sites designated to be remediated by the US Department of Energy (DOE) under Title I of the Uranium Mill Tailings Radiation Control Act of 1978 (UMTRCA). The UMTRCA requires that the US Nuclear Regulatory Commission (NRC) concur with the DOE's remedial action plan (RAP) and certify that the remedial action conducted at the site complies with the standards promulgated by the US Environmental Protection Agency (EPA). The RAP, which includes this summary remedial action selection report (RAS), serves a two-fold purpose. First, it describes the activities proposed by the DOE to accomplish long-term stabilization and control of the residual radioactive materials at the inactive uranium processing site near Falls City, Texas. Second, this document and the remainder of the RAP, upon concurrence and execution by the DOE, the State of Texas, and the NRC, becomes Appendix B of the Cooperative Agreement between the DOE and the State of Texas.

  6. The Parole Officer Aide Program in Ohio. An Exemplary Project. Criminal Justice System Series Number 42.

    ERIC Educational Resources Information Center

    Allen, Harry E.; Priestino, Ramon R.

    The report represents an external evaluation of a three-year project designed to use ex-offenders as paraprofessional parole officer aides in Ohio. The report includes the results of a 1974 national survey of States' use of ex-offenders in parole work as background of the study. The program is described in terms of selection and assignment, duties…

  7. 18 CFR 375.308 - Delegations to the Director of the Office of Energy Projects.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... the List of CFR Sections Affected, which appears in the Finding Aids section of the printed volume and... Director of the Office of Energy Projects. 375.308 Section 375.308 Conservation of Power and Water Resources FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY REVISED GENERAL RULES THE...

  8. 18 CFR 375.308 - Delegations to the Director of the Office of Energy Projects.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... the List of CFR Sections Affected, which appears in the Finding Aids section of the printed volume and... Director of the Office of Energy Projects. 375.308 Section 375.308 Conservation of Power and Water Resources FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY REVISED GENERAL RULES THE...

  9. 18 CFR 375.308 - Delegations to the Director of the Office of Energy Projects.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... the List of CFR Sections Affected, which appears in the Finding Aids section of the printed volume and... Director of the Office of Energy Projects. 375.308 Section 375.308 Conservation of Power and Water Resources FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY REVISED GENERAL RULES THE...

  10. 18 CFR 375.308 - Delegations to the Director of the Office of Energy Projects.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... the List of CFR Sections Affected, which appears in the Finding Aids section of the printed volume and... Director of the Office of Energy Projects. 375.308 Section 375.308 Conservation of Power and Water Resources FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY REVISED GENERAL RULES THE...

  11. 18 CFR 375.308 - Delegations to the Director of the Office of Energy Projects.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... the List of CFR Sections Affected, which appears in the Finding Aids section of the printed volume and... Director of the Office of Energy Projects. 375.308 Section 375.308 Conservation of Power and Water Resources FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY REVISED GENERAL RULES THE...

  12. Project Management Series Case Study: The Office of Registration and Records

    ERIC Educational Resources Information Center

    Burgher, Karl E.; Snyder, Michael

    2012-01-01

    This is the third in a series of eight articles on project management (PM) in the academy. In this article, the authors describe the step-by-step implementation of a structural change to Indiana State University's (ISU's) Office of Registration and Records (ORR). The process described may vary as it is implemented elsewhere, but the authors…

  13. 48 CFR 301.606-75 - Additional Project Officer training requirements.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 48 Federal Acquisition Regulations System 4 2011-10-01 2011-10-01 false Additional Project Officer training requirements. 301.606-75 Section 301.606-75 Federal Acquisition Regulations System HEALTH AND HUMAN SERVICES GENERAL HHS ACQUISITION REGULATION SYSTEM Career Development, Contracting Authority,...

  14. 48 CFR 301.606-75 - Additional Project Officer training requirements.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 48 Federal Acquisition Regulations System 4 2012-10-01 2012-10-01 false Additional Project Officer training requirements. 301.606-75 Section 301.606-75 Federal Acquisition Regulations System HEALTH AND HUMAN SERVICES GENERAL HHS ACQUISITION REGULATION SYSTEM Career Development, Contracting Authority,...

  15. Information Retrieval in an Office Filing Facility and Future Work in Project Minstrel.

    ERIC Educational Resources Information Center

    Smeaton, A. F.; van Rijsbergen, C. J.

    1986-01-01

    Review of office filing facility filing and retrieval mechanisms for unstructured and mixed media information focuses on free text methods. Also discussed are the state of the art in handling voice and image data, problems with searching text surrogates to implement free text content retrieval, and work of Project Minstrel. (Author/MBR)

  16. 48 CFR 301.606-75 - Additional Project Officer training requirements.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 4 2010-10-01 2010-10-01 false Additional Project Officer training requirements. 301.606-75 Section 301.606-75 Federal Acquisition Regulations System HEALTH AND HUMAN SERVICES GENERAL HHS ACQUISITION REGULATION SYSTEM Career Development, Contracting Authority,...

  17. Uranium Mill Tailings Remedial Action Project, fiscal year 1995 annual report to stakeholders

    SciTech Connect

    1995-09-30

    In 1978, Congress authorized the DOE to assess and clean up contamination at 24 designated former uranium processing sites. The DOE is also responsible for cleaning up properties in the vicinity of the sites where wind and water erosion deposited tailings or people removed them from the site for use in construction or landscaping projects. Cleanup is being undertaken in cooperation with state governments and Indian tribes within whose boundaries the sites are located. It is being conducted in two phases: the surface project and the ground water project. This report addresses specifics about both phases of the UMTRA Project. DOE`s UMTRA Project is the world`s largest materials management project ever undertaken to reduce or eliminate risk to the general public from exposure to potentially hazardous and radioactive materials. With an estimated cost at completion of nearly $2 billion for both phases of the UMTRA Project, and with the responsibility for encapsulating and isolating almost one-fourth of all the uranium mill tailings generated across the entire US (more than 44 million cubic yards), the UMTRA Project and its people have achieved a long record of safely and effectively completing its mission. It continually enhances its national reputation through its diligent process and cost efficiency as well as its international recognition for its technological innovation.

  18. The Role of the Project Management Office on Information Technology Project Success

    ERIC Educational Resources Information Center

    Stewart, Jacob S.

    2010-01-01

    The rate of failed and challenged Information Technology (IT) projects is too high according to the CHAOS Studies by the Standish Group and the literature on project management (Standish Group, 2008). The CHAOS Studies define project success as meeting the triple constraints of scope, time, and cost. Assessing critical success factors is another…

  19. Tank waste remediation system privatization phase I infrastructure and project W-519 and QA implementation plan

    SciTech Connect

    HUSTON, J.J.

    1999-08-19

    This document has been prepared to identify the quality requirements for all products/activities developed by or for Project W-519. This plan is responsive to the Numatec Hanford Corporation, Quality Assurance Program Plan, NHC-MP-001.

  20. Status Report for Remediation Decision Support Project, Task 1, Activity 1.B – Physical and Hydraulic Properties Database and Interpretation

    SciTech Connect

    Rockhold, Mark L.

    2008-09-26

    The objective of Activity 1.B of the Remediation Decision Support (RDS) Project is to compile all available physical and hydraulic property data for sediments from the Hanford Site, to port these data into the Hanford Environmental Information System (HEIS), and to make the data web-accessible to anyone on the Hanford Local Area Network via the so-called Virtual Library. In past years efforts were made by RDS project staff to compile all available physical and hydraulic property data for Hanford sediments and to transfer these data into SoilVision{reg_sign}, a commercial geotechnical software package designed for storing, analyzing, and manipulating soils data. Although SoilVision{reg_sign} has proven to be useful, its access and use restrictions have been recognized as a limitation to the effective use of the physical and hydraulic property databases by the broader group of potential users involved in Hanford waste site issues. In order to make these data more widely available and useable, a decision was made to port them to HEIS and to make them web-accessible via a Virtual Library module. In FY08 the objectives of Activity 1.B of the RDS Project were to: (1) ensure traceability and defensibility of all physical and hydraulic property data currently residing in the SoilVision{reg_sign} database maintained by PNNL, (2) transfer the physical and hydraulic property data from the Microsoft Access database files used by SoilVision{reg_sign} into HEIS, which has most recently been maintained by Fluor-Hanford, Inc., (3) develop a Virtual Library module for accessing these data from HEIS, and (4) write a User's Manual for the Virtual Library module. The development of the Virtual Library module was to be performed by a third party under subcontract to Fluor. The intent of these activities is to make the available physical and hydraulic property data more readily accessible and useable by technical staff and operable unit managers involved in waste site assessments and

  1. Process Knowledge Characterization of Radioactive Waste at the Classified Waste Landfill Remediation Project Sandia National Laboratories, Albuquerque, New Mexico

    SciTech Connect

    DOTSON,PATRICK WELLS; GALLOWAY,ROBERT B.; JOHNSON JR,CARL EDWARD

    1999-11-03

    This paper discusses the development and application of process knowledge (PK) to the characterization of radioactive wastes generated during the excavation of buried materials at the Sandia National Laboratories/New Mexico (SNL/NM) Classified Waste Landfill (CWLF). The CWLF, located in SNL/NM Technical Area II, is a 1.5-acre site that received nuclear weapon components and related materials from about 1950 through 1987. These materials were used in the development and testing of nuclear weapon designs. The CWLF is being remediated by the SNL/NM Environmental Restoration (ER) Project pursuant to regulations of the New Mexico Environment Department. A goal of the CWLF project is to maximize the amount of excavated materials that can be demilitarized and recycled. However, some of these materials are radioactively contaminated and, if they cannot be decontaminated, are destined to require disposal as radioactive waste. Five major radioactive waste streams have been designated on the CWLF project, including: unclassified soft radioactive waste--consists of soft, compatible trash such as paper, plastic, and plywood; unclassified solid radioactive waste--includes scrap metal, other unclassified hardware items, and soil; unclassified mixed waste--contains the same materials as unclassified soft or solid radioactive waste, but also contains one or more Resource Conservation and Recovery Act (RCRA) constituents; classified radioactive waste--consists of classified artifacts, usually weapons components, that contain only radioactive contaminants; and classified mixed waste--comprises radioactive classified material that also contains RCRA constituents. These waste streams contain a variety of radionuclides that exist both as surface contamination and as sealed sources. To characterize these wastes, the CWLF project's waste management team is relying on data obtained from direct measurement of radionuclide activity content to the maximum extent possible and, in cases where

  2. Remedial investigation sampling and analysis plan for J-Field, Aberdeen Proving Ground, Maryland: Volume 2, Quality Assurance Project Plan

    SciTech Connect

    Prasad, S.; Martino, L.; Patton, T.

    1995-03-01

    J-Field encompasses about 460 acres at the southern end of the Gunpowder Neck Peninsula in the Edgewood Area of APG (Figure 2.1). Since World War II, the Edgewood Area of APG has been used to develop, manufacture, test, and destroy chemical agents and munitions. These materials were destroyed at J-Field by open burning and open detonation (OB/OD). For the purposes of this project, J-Field has been divided into eight geographic areas or facilities that are designated as areas of concern (AOCs): the Toxic Burning Pits (TBP), the White Phosphorus Burning Pits (WPP), the Riot Control Burning Pit (RCP), the Robins Point Demolition Ground (RPDG), the Robins Point Tower Site (RPTS), the South Beach Demolition Ground (SBDG), the South Beach Trench (SBT), and the Prototype Building (PB). The scope of this project is to conduct a remedial investigation/feasibility study (RI/FS) and ecological risk assessment to evaluate the impacts of past disposal activities at the J-Field site. Sampling for the RI will be carried out in three stages (I, II, and III) as detailed in the FSP. A phased approach will be used for the J-Field ecological risk assessment (ERA).

  3. An assessment of plant biointrusion at the Uranium Mill Tailings Remedial Action Project rock-covered disposal cells

    SciTech Connect

    Not Available

    1990-10-01

    This study is one of a number of special studies that have been conducted regarding various aspects of the Uranium Mill Tailings Remedial Action (UMTRA) Project. This special study was proposed following routine surveillance and maintenance surveys and observations reported in a special study of vegetative covers (DOE, 1988), in which plants were observed growing up through the rock erosion layer at recently completed disposal cells. Some of the plants observed were deep-rooted woody species, and questions concerning root intrusion into disposal cells and the need to control plant growth were raised. The special study discussed in this report was designed to address some of the ramifications of plant growth on disposal cells that have rock covers. The NRC has chosen rock covers over vegetative covers in the arid western United States because licenses cannot substantiate that the vegetative covers will be significantly greater than 30 percent and preferably 70 percent,'' which is the amount of vegetation required to reduce flow to a point of stability.'' The potential impacts of vegetation growing in rock covers are not addressed by the NRC (1990). The objectives, then, of this study were to determine the species of plants growing on two rock-covered disposal cells, study the rooting pattern of plants on these cells, and identify possible impacts of plant root penetration on these and other UMTRA Project rock-covered cells.

  4. Gunite and associated tanks remediation project recycling and waste minimization effort

    SciTech Connect

    Van Hoesen, S.D.; Saunders, A.D.

    1998-05-01

    The Department of Energy`s Environmental Management Program at Oak Ridge National Laboratory has initiated clean up of legacy waste resulting from the Manhattan Project. The gunite and associated tanks project has taken an active pollution prevention role by successfully recycling eight tons of scrap metal, reusing contaminated soil in the Area of Contamination, using existing water (supernate) to aid in sludge transfer, and by minimizing and reusing personal protective equipment (PPE) and on-site equipment as much as possible. Total cost savings for Fiscal Year 1997 activities from these efforts are estimated at $4.2 million dollars.

  5. Examples of Department of Energy Successes for Remediation of Contaminated Groundwater: Permeable Reactive Barrier and Dynamic Underground Stripping ASTD Projects

    SciTech Connect

    Purdy, C.; Gerdes, K.; Aljayoushi, J.; Kaback, D.; Ivory, T.

    2002-02-27

    Since 1998, the Department of Energy's (DOE) Office of Environmental Management has funded the Accelerated Site Technology Deployment (ASTD) Program to expedite deployment of alternative technologies that can save time and money for the environmental cleanup at DOE sites across the nation. The ASTD program has accelerated more than one hundred deployments of new technologies under 76 projects that focus on a broad spectrum of EM problems. More than 25 environmental restoration projects have been initiated to solve the following types of problems: characterization of the subsurface using chemical, radiological, geophysical, and statistical methods; treatment of groundwater contaminated with DNAPLs, metals, or radionuclides; and other projects such as landfill covers, purge water management systems, and treatment of explosives-contaminated soils. One of the major goals of the ASTD Program is to deploy a new technology or process at multiple DOE sites. ASTD projects are encouraged to identify subsequent deployments at other sites. Some of the projects that have successfully deployed technologies at multiple sites focusing on cleanup of contaminated groundwater include: Permeable Reactive Barriers (Monticello, Rocky Flats, and Kansas City), treating uranium and organics in groundwater; and Dynamic Underground Stripping (Portsmouth, and Savannah River), thermally treating DNAPL source zones. Each year more and more new technologies and approaches are being used at DOE sites due to the ASTD program. DOE sites are sharing their successes and communicating lessons learned so that the new technologies can replace the baseline or standard approaches at DOE sites, thus expediting cleanup and saving money.

  6. Grand challenge problems in environmental modeling and remediation: Groundwater contaminant transport. Final project report 1998

    SciTech Connect

    1998-04-01

    The over-reaching goal of the Groundwater Grand Challenge component of the Partnership in Computational Science (PICS) was to develop and establish the massively parallel approach for the description of groundwater flow and transport and to address the problem of uncertainties in the data and its interpretation. This necessitated the development of innovative algorithms and the implementation of massively parallel computational tools to provide a suite of simulators for groundwater flow and transport in heterogeneous media. This report summarizes the activities and deliverables of the Groundwater Grand Challenge project funded through the High Performance Computing grand challenge program of the Department of Energy from 1995 through 1997.

  7. Environmental summary of the F- and H-area seepage basins groundwater remediation project, Savannah River site

    SciTech Connect

    Friday, G.P.

    1997-12-31

    This report summarizes the results of nearly 70 investigations of the baseline environment, describes the remedial action, and identifies constituents of interest that pose potential risk to human health and the environment. It also proposes an approach for evaluating the effectiveness of the remedial action.

  8. Environmental analysis and data report prepared for the environmental assessment of remedial action at the inactive uranium mill tailings site near Falls City, Texas. [Uranium Mill Tailings Remedial Action (UMTRA) Project

    SciTech Connect

    Not Available

    1991-12-01

    This document contains information and data gathered in support of the preparation of the environmental assessment (EA) of the proposed remedial action at the Uranium Mill Tailings Remedial Action (UMTRA) Project site near Falls City, Texas. The Falls City EA was prepared pursuant to the National Environmental Policy Act (NEPA), which requires Federal agencies to assess the impacts of their actions on the environment. It examines the short- and long-term effects of the US Department of Energy's (DOE) remedial action for the Falls City site as well as the no action alternative. The DOE will use the information and analyses presented in the EA to determine whether the proposed action would have a significant impact on the environment. If the impacts are determined to be significant, an environmental impact statement (EIS) will be prepared. If the impacts are not determined to be significant, the DOE may issue a Finding of No Significant Impact (FONSI) and implement the proposed action. The information and data presented in this report are for background purposes only and are not required as part of the NEPA decision-making process.

  9. GLASS FORMULATION DEVELOPMENT AND TESTING FOR COLD CRUCIBLE INDUCTION MELTER (CCIM) ADVANCED REMEDIATION TECHNOLOGIES DEMONSTRATION PROJECT - 9208

    SciTech Connect

    Marra, J; Amanda Billings, A; David Peeler, D; Michael Stone, M; Tommy Edwards, T

    2008-08-27

    Over the past few years, Cold Crucible Induction Melter (CCIM) demonstrations have been completed using SRS sludge batches 2, 3 and 4 (SB2, SB3 and SB4) simulant compositions. These campaigns demonstrated the ability of the CCIM to effectively produce quality glasses at high waste loadings. The current Advanced Remediation Technology (ART) Phase II-A Project is aimed at demonstrating the CCIM technology under representative DWPF flowsheet conditions and to demonstrate extended operations of the melter. A glass composition development effort was completed to identify and recommend a frit composition and sludge batch 4 (SB4) simulant waste loading target for subsequent ART-Phase II-A CCIM demonstration testing. Based on the results of the glass formulation testing, it was recommended that the Frit 503-R6 composition (B{sub 2}O{sub 3} = 14 wt %; Li{sub 2}O = 9 wt %; Na{sub 2}O = 3 wt %; and SiO{sub 2} = 74 wt %) be utilized for the demonstration. Furthermore, a waste loading of 46 wt % was recommended. The recommended frit and waste loading would produce a glass with acceptable durability with a liquidus temperature adequately below the 1250 C nominal CCIM operating temperature. This frit composition and waste loading was found to result in a glass that met CCIM processing requirements for viscosity, electrical conductivity and thermal conductivity. The recommended frit and waste loading level should also provide a buffer for sludge product compositional variation to support the Phase II-A CCIM demonstration.

  10. Weldon Spring Site Remedial Action Project: Report from the DOE voluntary protection program onsite review, November 17--21, 1997

    SciTech Connect

    1998-01-28

    This report summarizes the Department of Energy Voluntary Protection Program (DOE-VPP) Review Team`s findings from the five-day onsite evaluation of the Weldon Spring Site Remedial Action Project (WSSRAP), conducted November 17--21, 1997. The site was evaluated against the program requirements contained in ``US Department of Energy Voluntary Protection Program, Part 1: Program Elements`` to determine its success in implementing the five tenets of DOE-VPP. DOE-VPP consists of three programs, with names and functions similar to those in OSHA`s VPP. These programs are STAR, MERIT, and DEMONSTRATION. The STAR program is the core of DOE-VPP. The program is aimed at truly outstanding protectors of employee safety and health. The MERIT program is a steppingstone for contractors and subcontractors that have good safety and health programs but need time and DOE guidance to achieve STAR status. The DEMONSTRATION program is rarely used; it allows DOE to recognize achievements in unusual situations about which DOE needs to learn more before determining approval requirements for the STAR status.

  11. UMTRA Project remedial action planning and disposal cell design to comply with the proposed EPA (Environmental Protection Agency) standards (40 CFR Part 192)

    SciTech Connect

    Not Available

    1989-01-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project involves stabilizing 24 inactive uranium mill tailings piles in 10 states. Remedial work must meet standards established by the US Environmental Protection Agency (EPA). Remedial action must be designed and constructed to prevent dispersion of the tailings and other contaminated materials, and must prevent the inadvertent use of the tailings by man. This report is prepared primarily for distribution to parties involved in the UMTRA Project, including the US Nuclear Regulatory Commission (NRC), and states and tribes. It is intended to record the work done by the DOE since publication of the proposed EPA groundwater protection standards, and to show how the DOE has attempted to respond and react in a positive way to the new requirements that result from the proposed standards. This report discusses the groundwater compliance strategies now being defined and implemented by the DOE, and details the changes in disposal cell designs that result from studies to evaluate ways to facilitate compliance with the proposed EPA groundwater protection standards. This report also serves to record the technical advances, planning, and progress made on the UMTRA Project since the appearance of the proposed EPA groundwater protection standards. The report serves to establish, document, and disseminate technical approaches and engineering and groundwater information to people who may be interested or involved in similar or related projects. 24 refs., 27 figs., 8 tabs.

  12. Final programmatic environmental impact statement for the uranium mill tailings remedial action ground water project. Volume I

    SciTech Connect

    1996-10-01

    This programmatic environmental impact statement (PElS) was prepared for the Uranium Mill Tailings Remedial Action (UMTRA) Ground Water Project to comply with the National Environmental Policy Act (NEPA). This PElS provides an analysis of the potential impacts of the alternatives and ground water compliance strategies as well as potential cumulative impacts. On November 8, 1978, Congress enacted the Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978, Public Law, codified at 42 USC §7901 et seq. Congress found that uranium mill tailings " ... may pose a potential and significant radiation health hazard to the public, and that every reasonable effort should be made to provide for stabilization, disposal, and control in a safe, and environmentally sound manner of such tailings in order to prevent or minimize other environmental hazards from such tailings." Congress authorized the Secretary of Energy to designate inactive uranium processing sites for remedial action by the U.S. Department of Energy (DOE). Congress also directed the U.S. Environmental Protection Agency (EPA) to set the standards to be followed by the DOE for this process of stabilization, disposal, and control. On January 5, 1983, EPA published standards (40 CFR Part 192) for the disposal and cleanup of residual radioactive materials. On September 3, 1985, the U.S. Court of Appeals for the Tenth Circuit set aside and remanded to EPA the ground water provisions of the standards. The EPA proposed new standards to replace remanded sections and changed other sections of 40 CFR Part 192. These proposed standards were published in the Federal Register on September 24, 1987 (52 FR 36000). Section 108 of the UMTRCA requires that DOE comply with EPA's proposed standards in the absence of final standards. The Ground Water Project was planned under the proposed standards. On January 11, 1995, EPA published the final rule, with which the DOE must now comply. The PElS and the Ground Water Project are in

  13. Air-Based Remediation Workshop - Section 8 Air-Based Remediation Technology Selection Logic

    EPA Science Inventory

    Pursuant to the EPA-AIT Implementing Arrangement 7 for Technical Environmental Collaboration, Activity 11 "Remediation of Contaminated Sites," the USEPA Office of International Affairs Organized a Forced Air Remediation Workshop in Taipei to deliver expert training to the Environ...

  14. Air-Based Remediation Workshop - Section 7 Sustainable Remediation And Air-Based Technologies

    EPA Science Inventory

    Pursuant to the EPA-AIT Implementing Arrangement 7 for Technical Environmental Collaboration, Activity 11 "Remediation of Contaminated Sites, " the USEPA Office of International Affairs Organized a Forced Air Remediation Workshop in Taipei to deliver expert training to the Enviro...

  15. The DuPont, Monsanto, General Electric {open_quotes}Lasagna{close_quotes} Remediation Project - joint R&D and financing

    SciTech Connect

    Palmer, P.A.

    1995-03-01

    The Lasagna project is the first of what we expect will be several large cooperative projects between industry consortia and government to develop improved remediation technologies. In 1992, Monsanto Company began contacting other major corporations to see if they were experiencing similar difficulties in applying cost-effective, or even workable technologies for industrial site remediation. Both General Electric and DuPont were early participants in the effort to develop a meeting with the EPA to discuss technical problems faced in cleanup, research needs, and ways to accelerate development of more cost-effective techniques. This paper provides some background on how this cooperative process came to reality, what the Lasagna process is and how the cooperative arrangements and financing are structured.

  16. Capital assets management process (CAMP) prioritization exercise for FY 1994 and FY 1995 projects at Field Office, Albuquerque

    SciTech Connect

    1992-01-16

    This report presents figures derived from a rating process to determine budget needs for projects for 1994 and 1995 at the Albuquerque Field Office. Projects for 1994 include plant life safety code upgrades, roads and parking lot upgrades, and emergency system notification replacement. Projects for 1995 include reconfiguration of inert operations, steam and condensate system upgrades, and site drainage control.

  17. Change of the layout of an office of a metallurgical company: simple projects, big solutions.

    PubMed

    Duarte, Luiz Carlos da Silva; Eckhardt, Moacir; da Motta, Giordano Paulo

    2012-01-01

    The posture, a good organization and the proper layout of the environment and workplaces have a positive influence on the income of an employee. To develop the work it is used a methodology that addressed the study phases of the theory involving the subject, description of the current situation, preparation of conceptions, choice of design, implementation and reporting of results. Through the project of "Change of the layout of an office of a metallurgical company" there was an intervention in these reported aspects providing improvements in the office, regarding ergonomic, layout, workplace and lighting issues, bringing welfare to the official, with the intent to improve its performance within the company and facilitating its actions, as the company's customer service. The results provided improvements in layout, in the workplace and especially in comfort for the human resources that perform their activities. PMID:22316917

  18. The healthy workplace project: Reduced viral exposure in an office setting.

    PubMed

    Reynolds, Kelly A; Beamer, Paloma I; Plotkin, Kevin R; Sifuentes, Laura Y; Koenig, David W; Gerba, Charles P

    2016-05-01

    Viral illnesses such as gastroenteritis and the common cold create a substantial burden in the workplace due to reduced productivity, increased absenteeism, and increased health care costs. Behaviors in the workplace contribute to the spread of human viruses via direct contact between hands, contaminated surfaces, and the mouth, eyes, and/or nose. This study assessed whether implementation of the Healthy Workplace Project (HWP) (providing hand sanitizers, disinfecting wipes, facial tissues, and use instructions) would reduce viral loads in an office setting of approximately 80 employees after seeding fomites and the hands of volunteer participants with an MS-2 phage tracer. The HWP significantly reduced viable phage detected on participants' hands, communal fomites, and personal fomites (p ≤ .010) in office environments and presents a cost-effective method for reducing the health and economic burden associated with viral illnesses in the workplace. PMID:26066784

  19. COST OF MTBE REMEDIATION

    EPA Science Inventory

    Widespread contamination of methyl tert-butyl ether (MTBE) in ground water has raised concerns about the increased cost of remediation of MTBE releases compared to BTEX-only sites. To evaluate these cost, cost information for 311 sites was furnished by U.S. EPA Office of Undergr...

  20. Integrated Project Management System description. [UMTRAP Project

    SciTech Connect

    Not Available

    1987-03-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project is a Department of Energy (DOE) designated Major System Acquisition (MSA). To execute and manage the Project mission successfully and to comply with the MSA requirements, the UMTRA Project Office ( Project Office'') has implemented and operates an Integrated Project Management System (IPMS). The Project Office is assisted by the Technical Assistance Contractor's (TAC) Project Integration and Control (PIC) Group in system operation. Each participant, in turn, provides critical input to system operation and reporting requirements. The IPMS provides a uniform structured approach for integrating the work of Project participants. It serves as a tool for planning and control, workload management, performance measurement, and specialized reporting within a standardized format. This system description presents the guidance for its operation. Appendices 1 and 2 contain definitions of commonly used terms and abbreviations and acronyms, respectively. 17 figs., 5 tabs.

  1. Operation Dominic, Shot Sword Fish. Project Officers report - project 1. 2 surface phenomena

    SciTech Connect

    Young, G.A.; Phillips, D.E.

    1985-04-01

    Shot Sword Fish was an operational test of the ASROC antisubmarine weapon system. The general objectives of the project were (1) to record and measure the formation, growth, and dissipation of the visible surface phenomena, including slicks, spray domes, plumes, fallout, base surge, and foam patch resulting from the underwater detonation of an ASROC weapon; (2) to use the data obtained to estimate the actual depth of burst, position of burst, yield, and bubble period; (3) to determine the location of ships and platforms in the experimental array before, during, and after the test; (4) to provide surface-phenomena time-of-arrival data at platforms and ships in the array for use by other projects; and 85) to make the results available for improving the surface-phenomena scaling and prediction techniques employed f,r establishing delivery and lethal ranges for fleet nuclear weapons. In general, there was good agreement between the observed dimensions of the Sword Fish phenomena and the predictions.

  2. Remediation technologies for contaminated sediments

    SciTech Connect

    Swanson, L.M.

    1995-09-01

    Although soil and groundwater remediation has been conducted for many years, sediment remediation is still in its infancy. Regulatory agencies are now beginning to identify areas where contaminated sediments exist and evaluate their environmental impact. As these evaluations are completed, the projects must shift focus to how these sediments can be remediated. Also as the criteria for aquatic disposal of dredged sediments become more stringent, remediation technologies must be developed to address contaminated sediments generated by maintenance dredging.This report describes the various issues and possible technologies for sediment remediation.

  3. Implementation of UMTRA Project Environmental Audit Action Plan status report for period ending September 30, 1992. [Uranium Mill Tailings Remedial Action (UMTRA) Project

    SciTech Connect

    Not Available

    1992-09-01

    This report provides the status of implementation of corrective actions for findings made in an Environmental Audit conducted by DOE Headquarters, Office of Environmental Audit, in June 1991. An Action Plan, dated December 1991, was developed to address the findings. The Action Plan was approved by DOE Headquarters, Office of Environment, Safety and Health, in July 1992. This report provides status for each activity listed in the approved Action Plan. Of 48 findings identified in the August 1991 Environmental Audit Report, 4 required no action, 5 were combined with others and actions to correct 19 are complete. Although it appears no progress has been made since the last status report was issued, UMTRA has completed 89% of the findings identified, compared to 72% identified in the last status report. The table below lists the 20 findings where actions are still underway, the current projected completion date, the organization(s) responsible for taking action on the finding, and the UMTRA Project Off ice staff member assigned responsibility for the finding.

  4. Operation Sun Beam, Shot Small Boy. Project Officers report. Project 1. 4. Shock photography

    SciTech Connect

    Hanlon, P.; Dieter, C.F.

    1985-09-01

    The objective of this project was to measure the shock position as a function of time from which shock velocities and pressures in limited regions could be calculated, and any asymmetric growth both along along and above the surface could be detected. An outgrowth of the fireball along the surface was observed, and it was attributed to surface heating. The rate of growth along the surface was asymmetric. The growth along the 113 deg azimuth was markedly greater than in any of the other directions measured. Contrary to previous experience with surface shots, the peak pressures obtained above ground zero were less than those obtained along the surface at the same distances. there is some evidence to suggest that the focusing noted on previous shots did not occur or was very much reduced. Scaled Small Boy peak pressure-distance data are in agreement with the composite surface-burst pressure-distance curve.

  5. Operation Sun Beam, Shot Small Boy. Project Officers report. Project 1. 9. Crater measurements

    SciTech Connect

    Rooke, A.D.; Davis, L.K.; Strange, J.N.

    1985-09-01

    The objectives of Project 1.9 were to obtain the dimensions of the apparent and true craters formed by the Small Boy event and to measure the permanent earth deformation occurring beyond the true crater boundary. Measurements were made of the apparent crater by aerial stereophotography and ground survey and of the true crater and subsurface zones of residual deformation by the excavation and mapping of an array of vertical, colored sand columns which were placed along one crater diameter prior to the shot. The results of the crater exploration are discussed, particularly the permanent compression of the medium beneath the true crater which was responsible for the major portion of the apparent and true crater volumes. Apparent and true crater dimensions are compared with those of previous cratering events.

  6. Independent Verification Survey of the Clean Coral Storage Pile at the Johnston Atoll Plutonium-Contaminated Soil Remediation Project

    SciTech Connect

    Wilson-Nichols, M.J.

    2000-12-07

    The Oak Ridge National Laboratory (ORNL) Environmental Technology Section conducted an independent verification (IV) survey of the clean storage pile at the Johnston Atoll Plutonium Contaminated Soil Remediation Project (JAPCSRP) from January 18-25, 1999. The goal of the JAPCSRP is to restore a 24-acre area that was contaminated with plutonium oxide particles during nuclear testing in the 1960s. The selected remedy was a soil sorting operation that combined radiological measurements and mining processes to identify and sequester plutonium-contaminated soil. The soil sorter operated from about 1990 to 1998. The remaining clean soil is stored on-site for planned beneficial use on Johnston Island. The clean storage pile currently consists of approximately 120,000 m{sup 3} of coral. ORNL conducted the survey according to a Sampling and Analysis Plan, which proposed to provide an IV of the clean pile by collecting a minimum number (99) of samples. The goal was to ascertain with 95% confidence whether 97% of the processed soil is less than or equal to the accepted guideline (500-Bq/kg or 13.5-pCi/g) total transuranic (TRU) activity. In previous IV tasks, ORNL has (1) evaluated and tested the soil sorter system software and hardware and (2) evaluated the quality control (QC) program used at the soil sorter plant. The IV has found that the soil sorter decontamination was effective and significantly reduced plutonium contamination in the soil processed at the JA site. The Field Command Defense Threat Reduction Agency currently plans to re-use soil from the clean pile as a cover to remaining contamination in portions of the radiological control area. Therefore, ORNL was requested to provide an IV. The survey team collected samples from 103 random locations within the top 4 ft of the clean storage pile. The samples were analyzed in the on-site radioanalytical counting laboratory with an American Nuclear Systems (ANS) field instrument used for the detection of low

  7. Implementing Earned Value Management in the CxP EVA Systems Project Office

    NASA Technical Reports Server (NTRS)

    Sorge, Les L.

    2009-01-01

    Earned Value Management (EVM), like project management, is as much art as it is science to develop an implementation plan for a project. This presentation will cover issues that were overcome and the implementation strategy to deploy Earned Value Management (EVM) within the Constellation Program (CxP), EVA Systems Project Office (ESPO), as well as discuss additional hurdles that currently prevent the organization from optimizing EVM. Each organization and each project within an organization needs to mold an EVM implementation plan around existing processes and tools, while at the same time revising those existing processes and tools as necessary to make them compatible with EVM. The ESPO EVM implementation covers work breakdown structure, organizational breakdown structure, control account, work/planning package development; integrated master schedule development using an integrated master plan; incorporating reporting requirements for existing funding process such as Planning, Programming, Budgeting, and Execution (PPBE) and JSC Internal Task Agreements (ITA); and interfacing with other software tools such as the Systems Applications and Products (SAP) accounting system and the CxP wInsight EVM analysis tool. However, there are always areas for improvement and EVM is no exception. As EVM continues to mature within the NASA CxP, these areas will continue to be worked to resolution to provide the Program Managers, Project Managers, and Control Account Managers the best EVM data possible to make informed decisions.

  8. Department of Energy hazardous waste remedial actions program: Quality assurance program

    SciTech Connect

    Horne, T.E.

    1988-01-01

    This paper describes the Quality Assurance Program developed for the Hazardous Waste Remedial Actions Program Support Contractor Office (HAZWRAP SCO). Key topics discussed include an overview of the HAZWRAP SCO mission and organization, the basic quality assurance program requirements and the requirements for the control of quality for the Department of Energy and Work for Others hazardous waste management programs, and the role of ensuring quality through the project team concept for the management of remedial response actions. The paper focuses on planning for quality assurance for this remedial waste management process from preliminary assessments of remedial sites to feasibility studies. Some observations concerning the control of quality during the implementation of remedial actions are presented. (2 refs.)

  9. Office of Inspector General audit report on credit card usage at the Ohio Field Office and the Fernald and Miamisburg Environmental Management Projects

    SciTech Connect

    1999-03-01

    In 1994 the Department of Energy (Department) obtained the services of Rocky Mountain BankCard System, through the use of a General Services Administration contract, as a means for the Department and its contractors to make small purchases. The use of credit cards was expected to simplify small purchase procedures and improve cash management. The Ohio Field Office (Field Office) uses the credit card system and oversees usage by its area offices. Contractors under the Field Office also use the credit card system to make small purchases. The Office of Inspector General (OIG) has issued one audit report concerning the use of credit cards. In April 1996, the OIG issued Report WR-B-96-06, Audit of Bonneville Power Administration`s Management of Information Resources. The audit concluded that improvements could be made in implementing credit card and property procedures in Bonneville`s management of computer-related equipment. Specifically, many credit card purchases were made by employees whose authority to buy was not properly documented, and the purchasing files often lacked invoices that would show what was purchased. Additionally, some cardholders split purchases to avoid credit card limits. The objective of this audit was to determine whether the Field Office, Fernald and Miamisburg Environmental Management Projects, Fluor Daniel, and B and W were using credit cards for the appropriate purposes and within the limitations established by Federal and Departmental regulations.

  10. Office of Legacy Management Decision Tree for Solar Photovoltaic Projects - 13317

    SciTech Connect

    Elmer, John; Butherus, Michael; Barr, Deborah L.

    2013-07-01

    To support consideration of renewable energy power development as a land reuse option, the DOE Office of Legacy Management (LM) and the National Renewable Energy Laboratory (NREL) established a partnership to conduct an assessment of wind and solar renewable energy resources on LM lands. From a solar capacity perspective, the larger sites in the western United States present opportunities for constructing solar photovoltaic (PV) projects. A detailed analysis and preliminary plan was developed for three large sites in New Mexico, assessing the costs, the conceptual layout of a PV system, and the electric utility interconnection process. As a result of the study, a 1,214-hectare (3,000-acre) site near Grants, New Mexico, was chosen for further study. The state incentives, utility connection process, and transmission line capacity were key factors in assessing the feasibility of the project. LM's Durango, Colorado, Disposal Site was also chosen for consideration because the uranium mill tailings disposal cell is on a hillside facing south, transmission lines cross the property, and the community was very supportive of the project. LM worked with the regulators to demonstrate that the disposal cell's long-term performance would not be impacted by the installation of a PV solar system. A number of LM-unique issues were resolved in making the site available for a private party to lease a portion of the site for a solar PV project. A lease was awarded in September 2012. Using a solar decision tree that was developed and launched by the EPA and NREL, LM has modified and expanded the decision tree structure to address the unique aspects and challenges faced by LM on its multiple sites. The LM solar decision tree covers factors such as land ownership, usable acreage, financial viability of the project, stakeholder involvement, and transmission line capacity. As additional sites are transferred to LM in the future, the decision tree will assist in determining whether a solar

  11. 76 FR 56973 - Office of National Marine Sanctuaries Final Policy and Permit Guidance for Submarine Cable Projects

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-09-15

    ... Policy and Permit Guidance for Submarine Cable Projects AGENCY: Office of National Marine Sanctuaries...) has developed final policy and permitting guidance for submarine cable projects proposed in national... install and maintain submarine cables in sanctuaries are reviewed consistently and in a manner...

  12. The Curriculum Improvement Project in Business Careers Programs: Business Manager, Officer Administrator, Real Estate Agent, Real Estate Broker.

    ERIC Educational Resources Information Center

    College of the Mainland, Texas City, TX.

    In 1987, the College of the Mainland undertook a project to update curricula in real estate, business management, and office technology. The project entailed a survey of the labor market to clarify personnel needs in selected fields; the use of the DACUM (Developing a Curriculum) process, which involved expert workers in the creation of task…

  13. The Inventive Thinking Curriculum Project. An Outreach Program of the United States Patent and Trademark Office. Third Edition.

    ERIC Educational Resources Information Center

    Department of Commerce, Washington, DC.

    The Inventive Thinking Curriculum Project is one of the many projects included in the national outreach program of the U.S. Patent and Trademark Office. It is designed to be used in conjunction with a thinking skills program as a means of applying critical and creative thinking and problem-solving skills through the activity of creating an…

  14. Environmental compliance plan for the Lower East Fork Poplar Creek Remedial Action Project at Oak Ridge, Tennessee

    SciTech Connect

    1996-07-01

    Remedial action for Lower East Fork Poplar Creek, as defined by the Record of Decision, requires that soil contaminated with >400 ppM mercury be excavated and disposed. Based on the remediation goal, soil will be excavated from areas located at the NOAA site and the Bruner site and disposed at the Industrial Landfill V at the Y-12 Plant. Objective is to minimize the risk to human health and the environment from contaminated soil in the lower EFPC floodplain pursuant to CERCLA and the Federal Facility Agreement (DOE 1992).

  15. CENTRAL PLATEAU REMEDIATION OPTIMIZATION STUDY

    SciTech Connect

    BERGMAN, T. B.; STEFANSKI, L. D.; SEELEY, P. N.; ZINSLI, L. C.; CUSACK, L. J.

    2012-09-19

    THE CENTRAL PLATEAU REMEDIATION OPTIMIZATION STUDY WAS CONDUCTED TO DEVELOP AN OPTIMAL SEQUENCE OF REMEDIATION ACTIVITIES IMPLEMENTING THE CERCLA DECISION ON THE CENTRAL PLATEAU. THE STUDY DEFINES A SEQUENCE OF ACTIVITIES THAT RESULT IN AN EFFECTIVE USE OF RESOURCES FROM A STRATEGIC PERSPECTIVE WHEN CONSIDERING EQUIPMENT PROCUREMENT AND STAGING, WORKFORCE MOBILIZATION/DEMOBILIZATION, WORKFORCE LEVELING, WORKFORCE SKILL-MIX, AND OTHER REMEDIATION/DISPOSITION PROJECT EXECUTION PARAMETERS.

  16. Caresoil: A multidisciplinar Project to characterize, remediate, monitor and evaluate the risk of contaminated soils in Madrid (Spain)

    NASA Astrophysics Data System (ADS)

    Muñoz-Martín, Alfonso; Antón, Loreto; Granja, Jose Luis; Villarroya, Fermín; Montero, Esperanza; Rodríguez, Vanesa

    2016-04-01

    Soil contamination can come from diffuse sources (air deposition, agriculture, etc.) or local sources, these last being related to anthropogenic activities that are potentially soil contaminating activities. According to data from the EU, in Spain, and particularly for the Autonomous Community of Madrid, it can be considered that heavy metals, toxic organic compounds (including Non Aqueous Phases Liquids, NAPLs) and combinations of both are the main problem of point sources of soil contamination in our community. The five aspects that will be applied in Caresoil Program (S2013/MAE-2739) in the analysis and remediation of a local soil contamination are: 1) the location of the source of contamination and characterization of soil and aquifer concerned, 2) evaluation of the dispersion of the plume, 3) application of effective remediation techniques, 4) monitoring the evolution of the contaminated soil and 5) risk analysis throughout this process. These aspects involve advanced technologies (hydrogeology, geophysics, geochemistry,...) that require new developing of knowledge, being necessary the contribution of several researching groups specialized in the fields previously cited, as they are those integrating CARESOIL Program. Actually two cases concerning hydrocarbon spills, as representative examples of soil local contamination in Madrid area, are being studied. The first is being remediated and we are monitoring this process to evaluate its effectiveness. In the second location we are defining the extent of contamination in soil and aquifer to define the most effective remediation technique.

  17. Remedial Action Plan and site design for stabilization of the inactive uranium mill tailings site at Gunnison, Colorado: Remedial action selection report. [Uranium Mill Tailings Remedial Action (UMTRA) Project

    SciTech Connect

    Not Available

    1992-10-01

    The Gunnison uranium mill tailings site is just south of the city limits of Gunnison, Colorado, in the south-central part of the state. The entire site covers 61 acres in the valley of the Gunnison River and Tomichi Creek. Contaminated materials at the Gunnison processing site include the tailings pile, covering about 35 acres to an average depth of nine feet and containing 459,000 cubic yards. Ore storage areas and the former mill processing area cover about 20 acres on the south side of the site. The volume of contaminated materials to be disposed of as part of the remedial action is estimated to be 718,900 cubic yards. An interim action was approved by the US Department of Energy to eliminate existing safety hazards to the Gunnison community. These actions, started in September 1991, included demolition of mill buildings and related processing facilities, excavation of two underground storage tanks, removal of asbestos and other hazardous materials from buildings, storage of those materials in a secured area on the site, and improvements of site security.

  18. DISSS/PSDB - Personnel Security Database Modernization Project: Compilation of data gathered from DOE Operations Office`s site visits

    SciTech Connect

    Carpenter, R.; Sweeney, D.

    1995-03-15

    This document is a compilation of the information gathered from visits to the DOE Operations Offices. The purpose of these visits was to gather requirements for the modernization of the personnel security database. The initial phase of visits were to sites which had known local systems to augment CPCI. They were; Rocky Flats, Richland, Las Vegas, Savannah River, Oak Ridge, and Oakland. The second phase of site visits were to; Headquarters, Schenectady, Pittsburgh, Idaho Falls, Chicago, and Albuquerque. We also visited the NRC. At each site we reviewed the current clearance process in use at the field office. If the site had a local personnel security database (PSDB), we also reviewed the current PSDB processing. Each meeting was began with the a discussion on the purpose of the meeting and the background of the redesign effort.

  19. Remediating while preserving wetland habitat at an LLR waste site in Canada

    SciTech Connect

    Kleb, H.R.; Zelmer, R.L.

    2007-07-01

    The Low-Level Radioactive Waste Management Office was established in 1982 to carry out the federal government's responsibilities for low-level radioactive (LLR) waste management in Canada. The Office operates programs to characterize, delineate, decontaminate and consolidate historic LLR waste for interim and long-term storage. In this capacity, the Office is currently considering the remediation of 9,000 cubic metres of contaminated sediment in a coastal marsh in the context of a major remediation project involving multiple urban sites. The marsh is situated between the Lake Ontario shoreline and the urban fringe of the Town of Port Hope. The marsh is designated a Cattail Mineral Shallow Marsh under the Ecological Land Classification system for Southern Ontario and was recently named the A.K. Sculthorpe Marsh in memory of a local community member. The marsh remediation will therefore require trade off between the disruption of a sensitive wetland and the removal of contaminated sediment. This paper discusses the issues and trade-off relating to the waste characterization, environmental assessment and regulatory findings and thus the remediation objectives for the marsh. Considerations include the spatial distribution of contaminated sediment, the bioavailability of contaminants, the current condition of the wetland and the predicted effects of remediation. Also considered is the significance of the wetland from provincial and municipal regulatory perspectives and the resulting directives for marsh remediation. (authors)

  20. Environmental assessment of remedial action at the inactive uraniferous lignite processing sites at Belfield and Bowman, North Dakota. [UMTRA Project

    SciTech Connect

    Beranich, S.; Berger, N.; Bierley, D.; Bond, T.M.; Burt, C.; Caldwell, J.A.; Dery, V.A.; Dutcher, A.; Glover, W.A.; Heydenburg, R.J.; Larson, N.B.; Lindsey, G.; Longley, J.M.; Millard, J.B.; Miller, M.; Peel, R.C.; Persson-Reeves, C.H.; Titus, F.B.; Wagner, L.

    1989-09-01

    The Uranium Mill Tailings Radiation Control Act of 1978 (UMTRCA), to clean up the Belfield and Bowman, North Dakota, uraniferous lignite processing sites to reduce the potential health impacts associated with the residual radioactive materials remaining at these sites. Remedial action at these sites must be performed in accordance with the US Environmental Protection Agency's (EPA) standards promulgated for the remedial action and with the concurrence of the US Nuclear Regulatory Commission (NRC) and the state of North Dakota. The inactive Belfield uraniferous lignite processing site is one mile southeast of Belfield, North Dakota. The inactive Bowman uraniferous lignite processing site at the former town of Griffin, is seven miles northwest of Bowman, North Dakota and 65 road miles south of Belfield. Lignite ash from the processing operations has contaminated the soils over the entire 10.7-acre designated Belfield site and the entire 12.1-acre designated Bowman site. Dispersion of the ash has contaminated an additional 20.6 acres surrounding the Belfield processing site and an additional 59.2 acres surrounding the Bowman processing site. The proposed remedial action is to relocate the contaminated materials at the Belfield processing site to the Bowman processing/disposal site for codisposal with the Bowman contaminated soils. The environmental impacts assessed in this EA were evaluated for the proposed remedial action and the no action alternative and demonstrate that the proposed action would not significantly affect the quality of the human environment and would be performed in compliance with applicable environmental laws. The no action alternative would not be consistent with the intent of Public Law 95-604 and would not comply with the EPA standards. 48 refs., 10 figs., 7 tabs.

  1. Remedial design/remedial action strategy report

    SciTech Connect

    Dieffenbacher, R.G.

    1994-06-30

    This draft Regulatory Compliance Strategy (RCS) report will aid the ER program in developing and implementing Remedial Design/Remedial Action (RD/RA) projects. The intent of the RCS is to provide guidance for the implementation of project management requirements and to allow the implementation of a flexible, graded approach to design requirements depending on the complexity, magnitude, schedule, risk, and cost for any project. The RCS provides a functional management-level guidance document for the identification, classification, and implementation of the managerial and regulatory aspects of an ER project. The RCS has been written from the perspective of the ER Design Manager and provides guidance for the overall management of design processes and elements. The RCS does not address the project engineering or specification level of detail. Topics such as project initiation, funding, or construction are presented only in the context in which these items are important as sources of information or necessary process elements that relate to the design project phases.

  2. Utilizing geochemical, hydrologic, and boron isotopic data to assess the success of a salinity and selenium remediation project, Upper Colorado River Basin, Utah

    USGS Publications Warehouse

    Naftz, D.L.; Bullen, T.D.; Stolp, B.J.; Wilkowske, C.D.

    2008-01-01

    Stream discharge and geochemical data were collected at two sites along lower Ashley Creek, Utah, from 1999 to 2003, to assess the success of a site specific salinity and Se remediation project. The remediation project involved the replacement of a leaking sewage lagoon system that was interacting with Mancos Shale and increasing the dissolved salinity and Se load in Ashley Creek. Regression modeling successfully simulated the mean daily dissolved salinity and Se loads (R2 values ranging from 0.82 to 0.97) at both the upstream (AC1) and downstream (AC2/AC2A) sites during the study period. Prior to lagoon closure, net gain in dissolved-salinity load exceeded 2177??metric tons/month and decreased after remediation to less than 590??metric tons/month. The net gain in dissolved Se load during the same pre-closure period exceeded 120??kg/month and decreased to less than 18??kg/month. Sen's slope estimator verified the statistical significance of the modeled reduction in monthly salinity and Se loads. Measured gain in dissolved constituent loads during seepage tests conducted during September and November 2003 ranged from 0.334 to 0.362??kg/day for dissolved Se and 16.9 to 26.1??metric tons/day for dissolved salinity. Stream discharge and changes in the isotopic values of delta boron-11 (??11B) were used in a mixing model to differentiate between constituent loadings contributed by residual sewage effluent and naturally occurring ground-water seepage entering Ashley Creek. The majority of the modeled ??11B values of ground-water seepage were positive, indicative of minimal seepage contributions from sewage effluent. The stream reach between sites S3 and AC2A contained a modeled ground-water seepage ??11B value of - 2.4???, indicative of ground-water seepage composed of remnant water still draining from the abandoned sewage lagoons.

  3. Utilizing geochemical, hydrologic, and boron isotopic data to assess the success of a salinity and selenium remediation project, Upper Colorado River Basin, Utah.

    PubMed

    Naftz, David L; Bullen, Thomas D; Stolp, Bert J; Wilkowske, Christopher D

    2008-03-15

    Stream discharge and geochemical data were collected at two sites along lower Ashley Creek, Utah, from 1999 to 2003, to assess the success of a site specific salinity and Se remediation project. The remediation project involved the replacement of a leaking sewage lagoon system that was interacting with Mancos Shale and increasing the dissolved salinity and Se load in Ashley Creek. Regression modeling successfully simulated the mean daily dissolved salinity and Se loads (R(2) values ranging from 0.82 to 0.97) at both the upstream (AC1) and downstream (AC2/AC2A) sites during the study period. Prior to lagoon closure, net gain in dissolved-salinity load exceeded 2177 metric tons/month and decreased after remediation to less than 590 metric tons/month. The net gain in dissolved Se load during the same pre-closure period exceeded 120 kg/month and decreased to less than 18 kg/month. Sen's slope estimator verified the statistical significance of the modeled reduction in monthly salinity and Se loads. Measured gain in dissolved constituent loads during seepage tests conducted during September and November 2003 ranged from 0.334 to 0.362 kg/day for dissolved Se and 16.9 to 26.1 metric tons/day for dissolved salinity. Stream discharge and changes in the isotopic values of delta boron-11 (delta(11)B) were used in a mixing model to differentiate between constituent loadings contributed by residual sewage effluent and naturally occurring ground-water seepage entering Ashley Creek. The majority of the modeled delta(11)B values of ground-water seepage were positive, indicative of minimal seepage contributions from sewage effluent. The stream reach between sites S3 and AC2A contained a modeled ground-water seepage delta(11)B value of -2.4 per thousand, indicative of ground-water seepage composed of remnant water still draining from the abandoned sewage lagoons. PMID:18068216

  4. Overview of Science and Technology Improvements at Office of Legacy Management Sites

    SciTech Connect

    Morrison, S.; Bartlett, T.; Boylan, J.; Carpenter, C.; Miller, D.; Kothari, V.

    2007-07-01

    The U.S. Department of Energy Office of Legacy Management (LM) supports science and technology (S and T) initiatives to more effectively manage LM sites, help protect human health and the environment, and reduce long-term costs of site maintenance and remediation by ensuring that sound engineering and scientific principles are used. Through the use of telemetry, LM's SOARS (System Operation and Analysis of Remote Sites) project provides project scientists and engineers with timely information needed to evaluate, maintain, and optimize remediation systems, while limiting the amount of required travel. This paper presents three recent S and T activities focused on enhancing remediation of ground water at LM sites. (authors)

  5. Air-Based Remediation Workshop - Section 6 Thermal Systems

    EPA Science Inventory

    Pursuant to the EPA-AIT Implementing Arrangement 7 for Technical Environmental Collaboration, Activity 11 "Remediation of Contaminated Sites," the USEPA Office of International Affairs Organized a Forced Air Remediation Workshop in Taipei to deliver expert training to the Environ...

  6. Air-Based Remediation Workshop - Section 2 Soil Vapor Extraction

    EPA Science Inventory

    Pursuant to the EPA-AIT Implementing Arrangement 7 for Technical Environmental Collaboration, Activity 11 "Remediation of Contaminated Sties," the USEPA Office of International Affairs Organized a Forced Air Remediation Workshop in Taipei to deliver expert training to the Environ...

  7. Air-Base Remediation Workshop - Section 3 Bioventig

    EPA Science Inventory

    Pursuant to the EPA-AIT Implementing Arrangement 7 for Technical Environmental Collaboration, Activity 11 "Remediation of Contaminated Sites," the USEPA Office of International Affairs Organized a Forced Air Remediation Workshop in Taipei to deliver expert training to the Environ...

  8. Air-Based Remediation Workshop - Section 1 Sampling And Analysis Revelant To Air-Based Remediation Technologies

    EPA Science Inventory

    Pursant to the EPA-AIT Implementing Arrangement 7 for Technical Environmental Collaboration, Activity 11 "Remediation of Contaminated Sites," the USEPA Office of International Affairs Organized a Force Air Remediation Workshop in Taipei to deliver expert training to the Environme...

  9. Project Execution Plan, Waste Management Division, Nevada Operations Office, U.S. Department of Energy, April 2000

    SciTech Connect

    DOE /NV

    2000-04-01

    This plan addresses project activities encompassed by the U.S. Department of Energy/Nevada Operations Office Waste Management Division and conforms to the requirements contained in the ''Life Cycle Asset Management,'' U.S. Department of Energy Order O430.1A; the Joint Program Office Policy on Project Management in Support of DOE Order O430.1, and the Project Execution and Engineering Management Planning Guide. The plan also reflects the milestone philosophies of the Federal Facility Agreement and Consent Order, as agreed to by the state of Nevada; and traditional project management philosophies such as the development of life cycle costs, schedules, and work scope; identification of roles and responsibilities; and baseline management and controls.

  10. 48 CFR 301.607-78 - Contracting Officer designation of a Program/Project Manager as the Contracting Officer's...

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... Representative. Personnel who are FAC-P/PM certified, at any level, meet the requirements for FAC-COTR certification and are, therefore, not required to obtain FAC-COTR certification to serve as a COTR for an HHS acquisition. However, for those individuals serving as a Program or Project Manager under a...