Science.gov

Sample records for stabilization project environmental

  1. Draft environmental assessment -- Test Area North pool stabilization project update

    SciTech Connect

    1997-06-01

    The purpose of this Environmental Assessment (EA) is to update the ``Test Area North Pool Stabilization Project`` EA (DOE/EA-1050) and finding of no significant impact (FONSI) issued May 6, 1996. This update analyzes the environmental and health impacts of a drying process for the Three Mile Island (TMI) nuclear reactor core debris canisters now stored underwater in a facility on the Idaho National Engineering and Environmental Laboratory (INEEL). A drying process was analyzed in the predecision versions of the EA released in 1995 but that particular process was determined to be ineffective and dropped form the Ea/FONSI issued May 6, 1996. The origin and nature of the TMI core debris and the proposed drying process are described and analyzed in detail in this EA. As did the 1996 EA, this update analyzes the environmental and health impacts of removing various radioactive materials from underwater storage, dewatering these materials, constructing a new interim dry storage facility, and transporting and placing the materials into the new facility. Also, as did the 1996 EA, this EA analyzes the removal, treatment and disposal of water from the pool, and placement of the facility into a safe, standby condition. The entire action would take place within the boundaries of the INEEL. The materials are currently stored underwater in the Test Area North (TAN) building 607 pool, the new interim dry storage facility would be constructed at the Idaho Chemical Processing Plant (ICPP) which is about 25 miles south of TAN.

  2. Environmental Assessment -- Test Area North pool stabilization project update

    SciTech Connect

    1997-08-01

    The purpose of this Environmental Assessment (EA) is to update the ``Test Area North Pool Stabilization Project`` EA (DOE/EA-1050) and finding of no significant impact (FONSI) issued May 6, 1996. This update analyzes the environmental and health impacts of a drying process for the Three Mile Island (TMI) nuclear reactor core debris canisters now stored underwater in a facility on the Idaho National Engineering and Environmental Laboratory (INEEL). A drying process was analyzed in the predecision versions of the EA released in 1995 but that particular process was determined to be ineffective and dropped from the EA/FONSI issued May 6, 1996. A new drying process was subsequently developed and is analyzed in Section 2.1.2 of this document. As did the 1996 EA, this update analyzes the environmental and health impacts of removing various radioactive materials from underwater storage, dewatering these materials, constructing a new interim dry storage facility, and transporting and placing the materials into the new facility. Also, as did the 1996 EA, this EA analyzes the removal, treatment and disposal of water from the pool, and placement of the facility into a safe, standby condition. The entire action would take place within the boundaries of the INEEL. The materials are currently stored underwater in the Test Area North (TAN) building 607 pool, the new interim dry storage facility would be constructed at the Idaho Chemical Processing Plant (ICPP) which is about 25 miles south of TAN.

  3. Test Area North Pool Stabilization Project: Environmental assessment

    SciTech Connect

    1996-05-01

    The Test Area North (TAN) Pool is located within the fenced TAN facility boundaries on the Idaho National Engineering Laboratory (INEL). The TAN pool stores 344 canisters of core debris from the March, 1979, Three Mile Island (TMI) Unit 2 reactor accident; fuel assemblies from Loss-of-Fluid Tests (LOFT); and Government-owned commercial fuel rods and assemblies. The LOFT and government owned commercial fuel rods and assemblies are hereafter referred to collectively as {open_quotes}commercial fuels{close_quotes} except where distinction between the two is important to the analysis. DOE proposes to remove the canisters of TMI core debris and commercial fuels from the TAN Pool and transfer them to the Idaho Chemical Processing Plant (ICPP) for interim dry storage until an alternate storage location other than at the INEL, or a permanent federal spent nuclear fuel (SNF) repository is available. The TAN Pool would be drained and placed in an industrially and radiologically safe condition for refurbishment or eventual decommissioning. This environmental assessment (EA) identifies and evaluates environmental impacts associated with (1) constructing an Interim Storage System (ISS) at ICPP; (2) removing the TMI and commercial fuels from the pool and transporting them to ICPP for placement in an ISS, and (3) draining and stabilizing the TAN Pool. Miscellaneous hardware would be removed and decontaminated or disposed of in the INEL Radioactive Waste Management Complex (RWMC). This EA also describes the environmental consequences of the no action alternative.

  4. Spray combustion stability project

    NASA Technical Reports Server (NTRS)

    Jeng, San-Mou; Litchford, Ron J.

    1992-01-01

    This report summarizes research activity on the Spray Combustion Stability Project, characterizes accomplishments and current status, and discusses projected future work. The purpose is to provide a concise conceptual overview of the research effort to date so the reader can quickly assimilate the gist of the research results and place them within the context of their potential impact on liquid rocket engine design technology.

  5. Spray combustion stability project

    NASA Technical Reports Server (NTRS)

    Jeng, San-Mou; Litchford, Ron J.

    1990-01-01

    This report summarizes research activity on the Spray Combustion Stability Project, characterizes accomplishments and current status, and discusses projected future work. The purpose is to provide a concise conceptual overview of the research effort so the reader can quickly assimilate the gist of the research results and place them within the context of their potential impact on liquid rocket engine design technology. Therefore, this report does not elaborate on many of the detailed technical aspects of the research program.

  6. Controlled Landfill Project in Yolo County, California for Environmental Benefits of Waste Stabilization and Minimization of Greenhouse Gas Emissions

    NASA Astrophysics Data System (ADS)

    Yazdani, R.; Augenstein, D.; Kieffer, J.; Cohen, K.

    2003-12-01

    The Department of Public Works of Yolo County, California, USA has been testing an advanced approach to landfill bioreactors, controlled (or "enhanced") landfilling, at its Yolo County Central Landfill site near Davis, CA, since 1994. Overall objectives have been the management of waste landfilling for: (1) rapid completion of total gas generation; (2) maximum, high-efficiency gas capture; (3) waste volume reduction; and (4) maximum greenhouse gas and carbon sequestration benefits. Methane generation is controlled and enhanced through carefully managed moisture additions, and by taking advantage of landfill temperature elevation. The generated landfill methane, an important greenhouse gas, is recovered with high efficiency through extraction from a porous recovery layer beneath a surface geomembrane cover. Instrumentation included a total of 56 moisture and 15 temperature sensors in the two cells, gas flow monitoring by positive displacement gas meters, and accurate quantification of liquid inputs and outputs. Gas composition, waste volume reduction, base hydrostatic head, and a range of environmental compliance parameters has been monitored since 1995. Partitioning gas tracer tests using the injection of two gases at dilute concentrations in the landfill have also been initiated to compute the fraction of pore space occupied by water between the points of tracer injection and tracer measurement. There has been rapid waste volume reduction in the enhanced cell that corresponds to the solids' reduction to gas. Monitoring is planned for the next several years, until stabilization parameters are determined complete. Encouraging performance is indicated by: (1) sensor data; (2) gas generation results; (3) data from landfill cores; and (4) decomposition-related indicators including rapid volume reduction. When data are synthesized, project results have attractive implications for new approaches to landfill management. Over seven-years, methane recoveries have averaged

  7. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-02-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demography, food consumption, and agriculture; environmental pathways and dose estimates.

  8. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1992-10-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The independent Technical Steering Panel (TSP) provides technical direction. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates):Source Terms, Environmental Transport, Environmental Monitoring Data, Demography, Food Consumption, and Agriculture, and Environmental Pathways and Dose Estimates.

  9. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-01-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source Terms, Environmental Transport, Environmental Monitoring Data, Demography, Food Consumption, and Agriculture, and Environmental Pathways and Dose Estimates.

  10. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1991-01-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source terms; environmental transport environmental monitoring data; demographics, agriculture, food habits; environmental pathways and dose estimates.

  11. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-06-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Battelle Pacific Northwest Laboratories under contract with the Centers for Disease Control. The independent Technical Steering Panel (TSP) provides technical direction. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demography, food consumption, and agriculture; environmental pathways and dose estimates.

  12. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Finch, S.M.

    1990-09-01

    This monthly report summarizes the technical progress and project status for the Hanford Environmental Dose Reconstruction (HEDR) Project being conducted at the Pacific Northwest Laboratory (PNL) under the direction of a Technical Steering Panel (TSP). The TSP is composed of experts in numerous technical fields related to this project and represents the interests of the public. The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms, environmental transport, environmental monitoring data, demographics, agriculture, food habits, environmental pathways and dose estimates. 3 figs.

  13. ENVIRONMENTAL EVALUATION FOR UTILIZATION OF ASH IN SOIL STABILIZATION

    SciTech Connect

    David J. Hassett; Loreal V. Heebink

    2001-08-01

    The Minnesota Pollution Control Agency (MPCA) approved the use of coal ash in soil stabilization, indicating that environmental data needed to be generated. The overall project goal is to evaluate the potential for release of constituents into the environment from ash used in soil stabilization projects. Supporting objectives are: (1) To ensure sample integrity through implementation of a sample collection, preservation, and storage protocol to avoid analyte concentration or loss. (2) To evaluate the potential of each component (ash, soil, water) of the stabilized soil to contribute to environmental release of analytes of interest. (3) To use laboratory leaching methods to evaluate the potential for release of constituents to the environment. (4) To facilitate collection of and to evaluate samples from a field runoff demonstration effort. The results of this study indicated limited mobility of the coal combustion fly ash constituents in laboratory tests and the field runoff samples. The results presented support previous work showing little to negligible impact on water quality. This and past work indicates that soil stabilization is an environmentally beneficial CCB utilization application as encouraged by the U.S. Environmental Protection Agency. This project addressed the regulatory-driven environmental aspect of fly ash use for soil stabilization, but the demonstrated engineering performance and economic advantages also indicate that the use of CCBs in soil stabilization can and should become an accepted engineering option.

  14. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1991-01-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The TSP consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included are appointed technical members representing the states of Oregon and Washington, a representative of Native American tribes, and an individual representing the public. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on human (dose estimates): Source Terms; Environmental Transport; Environmental Monitoring Data; Demographics, Agriculture, Food Habits and; Environmental Pathways and Dose Estimates.

  15. Environmental Assessment Lakeview Geothermal Project

    SciTech Connect

    Treis, Tania

    2012-04-30

    The Town of Lakeview is proposing to construct and operate a geothermal direct use district heating system in Lakeview, Oregon. The proposed project would be in Lake County, Oregon, within the Lakeview Known Geothermal Resources Area (KGRA). The proposed project includes the following elements: Drilling, testing, and completion of a new production well and geothermal water injection well; construction and operation of a geothermal production fluid pipeline from the well pad to various Town buildings (i.e., local schools, hospital, and Lake County Industrial Park) and back to a geothermal water injection well. This EA describes the proposed project, the alternatives considered, and presents the environmental analysis pursuant to the National Environmental Policy Act. The project would not result in adverse effects to the environment with the implementation of environmental protection measures.

  16. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    McMakin, A.H.; Cannon, S.D.; Finch, S.M.

    1992-07-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The TSP consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included are appointed technical members representing the states of Oregon, Washington, and Idaho, a representative of Native American tribes, and an individual representing the public. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): Source terms, environmental transport, environmental monitoring data, demography, food consumption, and agriculture, and environmental pathways and dose estimates. Progress is discussed.

  17. Summation by parts, projections, and stability

    NASA Technical Reports Server (NTRS)

    Olsson, Pelle

    1993-01-01

    We have derived stability results for high-order finite difference approximations of mixed hyperbolic-parabolic initial-boundary value problems (IBVP). The results are obtained using summation by parts and a new way of representing general linear boundary conditions as an orthogonal projection. By slightly rearranging the analytic equations, we can prove strict stability for hyperbolic-parabolic IBVP. Furthermore, we generalize our technique so as to yield strict stability on curvilinear non-smooth domains in two space dimensions. Finally, we show how to incorporate inhomogeneous boundary data while retaining strict stability. Using the same procedure one can prove strict stability in higher dimensions as well.

  18. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Finch, S. M.; McMakin, A. H.

    1991-09-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation dose that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into five technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (i.e., dose estimates). The Source Terms Task develops estimates of radioactive emissions from Hanford facilities since 1944. The Environmental Transport Task reconstructs the movements of radioactive particles from the areas of release to populations. The Environmental Monitoring Data Task assemblies, evaluates and reports historical environmental monitoring data. The Demographics, Agriculture and Food Habits Task develops the data needed to identify the populations that could have been affected by the releases. The Environmental Pathways and Dose Estimates Task used the information derived from the other Tasks to estimate the radiation doses individuals could have received from Hanford radiation. This document lists the progress on this project as of September 1991. 3 figs., 2 tabs.

  19. Environmental Noise: An Undergraduate Research Project

    ERIC Educational Resources Information Center

    Mahajan, Sukhbir; And Others

    1977-01-01

    Describes an undergraduate project of measuring environmental noise. Includes a discussion of current methodologies used in environmental noise assessment and the usefulness of projects which involve the physics profession with local governmental agencies and the community. (SL)

  20. Environmental mitigation at hydroelectric projects

    SciTech Connect

    Sale, M.J.; Cada, G.F.; Chang, L.H.; Christensen, S.W.; Railsback, S.F. ); Francfort, J.E.; Rinehart, B.N.; Sommers, G.L. )

    1991-12-01

    Current environmental mitigation practices at nonfederal hydropower projects were analyzed. Information about instream flows, dissolved oxygen (DO) mitigation, and upstream and downstream fish passage facilities was obtained from project operators, regulatory and resource agencies, and literature reviews. Information provided by the operators includes the specific mitigation requirements imposed on each project, specific objectives or purposes of mitigation, mitigation measures chosen to meet the requirement, the kinds of post-project monitoring conducted, and the costs of mitigation. Costs are examined for each of the four mitigation methods, segmented by capital, study, operations and maintenance, and annual reporting costs. Major findings of the study include: the dominant role of the Instream Flow Incremental Methodology, in conjunction with professional judgment by agency biologists, to set instream flow requirements; reliance on spill flows for DO enhancement; and the widespread use of angled bar racks for downstream fish protection. All of these measures can have high costs and, with few exceptions, there are few data available from nonfederal hydropower projects with which to judge their effectiveness. 100 refs.

  1. PLUTONIUM FINISHING PLANT (PFP) STABILIZATION & PACKAGING PROJECT

    SciTech Connect

    GERBER, M.S.

    2004-01-14

    Fluor Hanford is pleased to submit the Plutonium Finishing Plant (PFP) Stabilization and Packaging Project (SPP) for consideration by the Project Management Institute as Project of the Year for 2004. The SPP thermally stabilized and/or packaged nearly 18 metric tons (MT) of plutonium and plutonium-bearing materials left in PFP facilities from 40 years of nuclear weapons production and experimentation. The stabilization of the plutonium-bearing materials substantially reduced the radiological risk to the environment and security concerns regarding the potential for terrorists to acquire the non-stabilized plutonium products for nefarious purposes. The work was done In older facilities which were never designed for the long-term storage of plutonium, and required working with materials that were extremely radioactive, hazardous, pyrophoric, and In some cases completely unique. I n some Instances, one-of-a-kind processes and equipment were designed, installed, and started up. The SPP was completed ahead of schedule, substantially beating all Interim progress milestone dates set by the Defense Nuclear Facilities Safety Board (DNFSB) and in the Hanford Site's Federal Facility Agreement and Consent Order (Tri-Party Agreement or TPA), and finished $1-million under budget.

  2. The Environmental Education through Filmmaking Project

    ERIC Educational Resources Information Center

    Harness, Hallie; Drossman, Howard

    2011-01-01

    The environmental education through filmmaking project, a case study at an alternative US public high school, investigates environmental literacies of "at-risk" students who produced two short documentary films, one on recycling and one on water conservation. The filmmaking project sought to promote students' awareness of environmental issues and…

  3. Environmental stability of intercalated graphite fibers

    NASA Technical Reports Server (NTRS)

    Gaier, J. R.; Jaworske, D. A.

    1985-01-01

    Graphite fibers intercalated with bromine, iodine monochloride, ferric chloride, and cupric chloride were subjected to stability tests under four environments which are encountered by engineering materials in the aerospace industry: ambient laboratory conditions, as would be experienced during handling operations and terrestrial applications; high vacuum, as would be experienced in space applications; high humidity, as would be experienced in marine applications; and high temperature, as would be experienced in some processing steps and applications. Monitoring the resistance of the fibers at ambient laboratory conditions revealed that only the ferric chloride intercalated fibers were unstable, due to absorption of water from the air. All four types of intercalated fibers were unstable, due to absorption of water from the air. All four types of intercalated fibers were stable for long periods under high vacuum. Ferric chloride, cupric chloride, and iodine monochloride intercalated fibers were sensitive to high humidity conditions. All intercalated fibers began to degrade above 250 C. The order of their thermal stability, from lowest to highest, was cupric chloride, iodine monochloride, bromine, and ferric chloride. Of the four types of intercalated fibers tested, the bromine intercalated fibers appear to have the most potential for application, based on environmental stability.

  4. Environmental assessment: The Eden project

    NASA Astrophysics Data System (ADS)

    Roza, Christodoulaki

    Non domestic buildings account for about one-sixth of the U.K.'s entire C02 emissions and one-third of the building related ones 2 . Their proportion of energy consumption, particularly electricity, has also been growing 2 . New buildings are not necessarily better, with energy use often proving to be much higher than their designers anticipated 2 . Annual C02 emissions of two- and sometimes three- times design expectations are far from unusual, leaving a massive credibility gap 2 . These and other global environmental and human health related concerns have motivated an increasing number of designers, developers and building users to pursue more environmentally sustainable designs and construction strategies 5 . However, these buildings can be difficult to evaluate, since they are large in scale, complex in materials and function and temporally dynamic due to limited service life of building components and changing user requirements 5 . All of these factors make environmental assessment of the buildings challenging. Previous Post Occupancy Review of Buildings and their Engineering (PROBE) building investigations have uncovered serious shortcomings in facilities management, or at least mismatches between a building's management needs and the ability of the occupiers to provide the right level of management 1 . Consequently, large differences between energy performance expectations and outcomes can occur virtually unnoticed, while designers continue to repeat flawed descriptions 2 . This investigation attempts to evaluate the building's operation and to help achieving demonstrable improvements in terms of energy efficiency and occupant satisfaction. The scope of this study is to evaluate the actual environmental performance of a building notable for its advanced design. The Education Resource Centre at the Eden Project was selected to compare design expectations with post occupancy performance. This report contains a small-scale survey of user satisfaction with the

  5. Hanford Environmental Dose Reconstruction Project. Monthly report

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-02-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demography, food consumption, and agriculture; environmental pathways and dose estimates.

  6. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-03-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source Terms, Environmental Transport, Environmental Monitoring Data, Demography, Food Consumption, and Agriculture, and Environmental Pathways and Dose Estimates.

  7. Hanford Environmental Dose Reconstruction Project. Monthly report

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1992-10-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The independent Technical Steering Panel (TSP) provides technical direction. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates):Source Terms, Environmental Transport, Environmental Monitoring Data, Demography, Food Consumption, and Agriculture, and Environmental Pathways and Dose Estimates.

  8. Hanford Environmental Dose Reconstruction Project. Monthly report

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-04-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source terms, environmental transport, environmental monitoring data, demography, food consumption, and agriculture, and environmental pathways and dose estimates.

  9. Hanford Environmental Dose Reconstruction Project monthly report

    SciTech Connect

    Finch, S.M.

    1991-10-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doeses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source terms; environmental transport; environmental monitoring data; demographics, agriculture, food habits; environmental pathways and dose estimates.

  10. Hanford Environmental Dose Reconstruction Project. Monthly report

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-03-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source Terms, Environmental Transport, Environmental Monitoring Data, Demography, Food Consumption, and Agriculture, and Environmental Pathways and Dose Estimates.

  11. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.

    1990-10-01

    This monthly report summarizes the technical progress and project status for the Hanford Environmental Dose Reconstruction (HEDR) Project being conducted at the Pacific Northwest Laboratory (PNL) under the direction of a Technical Steering Panel (TSP). The TSP is composed of experts in numerous technical fields related to this project and represents the interests of the public. The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms, environmental transport, environmental monitoring data, demographics, agriculture, food habits, and environmental pathways and dose estimates. 3 figs., 3 tabs.

  12. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.

    1990-05-01

    This monthly report summarizes the technical progress and project status for the Hanford Environmental Dose Reconstruction (HEDR) Project being conducted at Pacific Northwest Laboratory (PNL) under the direction of a Technical Steering Panel (TSP). The TSP is composed of experts in numerous technical fields related to this project and represents the interests of the public. The US Department of Energy (DOE) funds the project. The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks address each of the primary steps in the path from radioactive releases to dose estimates source terms, environmental transport, environmental monitoring data, demographics, agriculture, and food habits, and environmental pathways and dose estimates.

  13. Environmental projects. Volume 7: Environmental resources document

    NASA Technical Reports Server (NTRS)

    Kushner, Len; Kroll, Glenn

    1988-01-01

    The Goldstone Deep Space Communications Complex (GDSCC) in Barstow, California, is part of the NASA Deep Space Network, one of the world's largest and most sensitive scientific telecommunications and radio navigation networks. Goldstone is managed, directed and operated by the Jet Propulsion Laboratory of Pasadena, California. The GDSCC includes five distinct operational sites: Echo, Venus, Mars, Apollo, and Mojave Base. Within each site is a Deep Space Station (DPS), consisting of a large dish antenna and its support facilities. As required by NASA directives concerning the implementation of the National Environmental Policy Act, each NASA field installation is to publish an Environmental Resources Document describing the current environment at the installation, including any adverse effects that NASA operations may have on the local environment.

  14. Energy conservation, ecological stability and environmental quality

    SciTech Connect

    Bourodimos, E.L.

    1980-12-01

    Energy is the lifeblood of the ecosystem and, therefore, of the human-social enterprise as well. The ecological stability in all levels of biosphere functions is a problem of environmental quality and ultimately of public health, economy and life styles: the impact of energy availability, its use and abuse. In the age of energy and natural resource scarcity with all sorts of disruptions in the industrial-economic fabric, the perilous energy crisis and the threat of ecological breakdown, a hard new look and evaluation of energy use and conservation potential is urgently needed. The following scheme of pertinent questions is in order: a. Energy and Mass Flow in the Ecosystems: Energy and the determinants of ecosystem structure and dynamics. Food chain and food webs. How much is needed. How much is wasted. What is an optimum ecological efficiency within conservation planning systems analysis. b. Energy and Mass Flow in the Human Environment: Human ecosystem adaptability. Environmental stresses and ecological instability. Biological control: energy conservation and the re-establishment of a tolerable stable state. c. Energy Conservation Planning: How much energy do we use and waste. How can energy use and waste be reduced in developed and developing countries within the context of enhancing ecological balance and economic-social growth.

  15. Does environmental stability stimulate species renovation?

    NASA Astrophysics Data System (ADS)

    Casellato, C.; Erba, E.

    2009-04-01

    The Tithonian-Berriasian time interval is characterized by a major calcareous nannoplankton speciation episode: several coccolith and nannolith genera and species first appear and rapidly evolve, reaching a high diversity, abundance, and calcification degree. The history of calcareous nannoplankton indicates that times of accelerated rates of radiations (or extinctions) generally correlate with global changes in the geosphere, hydrosphere and atmosphere suggesting that evolutionary patterns are intimately linked to environmental modifications (Roth, 1989; Bown et al., 2004; Erba, 2006). Nevertheless, the Tithonian-Berriasian interval provides examples of intra- and intergeneric accelerated evolutionary rates (an origination event) during a time period of general environmental stability, in absence of coeval environmental change evidence. The Tithonian - Early Berriasian can be regarded as a "quiet" interval as far as the C cycle is concerned; the _13C curve shows a gradual minor decline after the Oxfordian anomalies and prior to the Valanginian event. The Tithonian-Berriasian speciation episode provides an excellent opportunity to study modo and tempo of calcareous nannoplankton evolution relative to absent environmental change, which is believed to be instrumental for driving biological evolution. Nannofossils have been investigated in sections from the Tethys and Atlantic oceans in order to discriminate among local, regional or global causes, and to verify possible diachroneity in calcareous phytoplankton evolution and/or in response to global changes. Calcareous nannofossil species richness, first and last occurrences and relative abundance were achieved. Different evolution modes have been proposed since Darwin's Evolutionary Theory: Phyletic Gradualism (Darwin, 1859), Punctuated Equilibrium (Gould & Eldredge, 1977) and Punctuated Gradualism (Malmgren et al., 1984). Phyletic gradualism holds that new species arise from slow, steady transformation of populations

  16. Hanford Environmental Dose Reconstruction Project monthly report

    SciTech Connect

    Finch, S.M.

    1990-12-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have been have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demographics, agriculture, food habits; and environmental pathways and dose estimates. 3 figs., 3 tabs.

  17. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.

    1990-01-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demographics; agriculture; food habits; and environmental pathways and dose estimates. 3 figs.

  18. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Dennis, B.S.

    1990-04-01

    This monthly report summarizes the technical progress and project status for the Hanford Environmental Dose Reconstruction (HEDR) Project being conducted at Pacific Northwest Laboratory (PNL) under the direction of a Technical Steering Panel (TSP). The project is divided into the following technical tasks. These tasks address each of the primary steps in the path from radioactive releases to dose estimates: source terms, environmental transport, environmental monitoring data, demographics, agriculture, and food habits, and environmental pathways and dose estimates. The source terms task will develop estimates for radioactive emissions from Hanford facilities since 1944. These estimates will be based on historical measurements and production information. 1 fig., 1 tab.

  19. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.

    1990-06-01

    This monthly report summarizes the technical progress and project status for the Hanford Environmental Dose Reconstruction (HEDR) Project being conducted at Pacific Northwest Laboratory (PNL) under the direction of a Technical Steering Panel (TSP). The TSP is composed of experts in numerous technical fields related to this project and represents the interests of the public. The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is divided into technical tasks which address each of the primary steps in the path from radioactive releases to dose estimates: source terms, environmental transport, environmental monitoring data, demographics, agriculture, and food habits, and environmental pathways and dose estimates.

  20. Environmental projects. Volume 3: Environmental compliance audit

    NASA Technical Reports Server (NTRS)

    1987-01-01

    The Goldstone Deep Space Communications Complex is part of NASA's Deep Space Network, one of the world's largest and most sensitive scientific telecommunications and radio navigation networks. Activities at Goldstone are carried out in support of six large parabolic dish antennas. In support of the national goal of the preservation of the environment and the protection of human health and safety, NASA, JPL and Goldstone have adopted a position that their operating installations shall maintain a high level of compliance with Federal, state, and local laws governing the management of hazardous substances, abestos, and underground storage tanks. A JPL version of a document prepared as an environmental audit of Goldstone operations is presented. Both general and specific items of noncompliance at Goldstone are identified and recommendations are provided for corrective actions.

  1. Environmental Education Study Projects for College Students.

    ERIC Educational Resources Information Center

    Wert, Jonathan M.

    This publication concerns three environmental education study projects designed to help the college instructor, student, or group of students in identifying environmental problems at the community level and helping to find solutions to them. It discusses the need for and use of environmental problem solving and includes some factors involved with…

  2. Project Management Plan for the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Shipler, D.B.

    1992-03-01

    This Project Management Plan (PMP) describes the approach that will be used to manage the Hanford Environmental Dose Reconstruction (HEDR) Project. The plan describes the management structure and the technical and administrative control systems that will be used to plan and control the HEDR Project performance. The plan also describes the relationship among key project participants: Battelle, the Centers for Disease Control (CDC), and the Technical Steering Panel (TSP).

  3. Environmental Control Unit Harness Project

    NASA Technical Reports Server (NTRS)

    Oliva-Buisson, Yvette J.

    2014-01-01

    Testing four new Environmental Control Unit Harnesses for improved user comfort during SCAPE operations. Phase I, testing in a lab environment, Phase II will continue testing the best candidates in a field environment.

  4. School Yard Environmental Projects: A Planning Primer.

    ERIC Educational Resources Information Center

    Megalos, Mark A.; And Others

    This guide describes how to establish successful trails, outdoor classrooms, or other environmental education improvements on rural and urban school grounds. Teachers are encouraged to promote the environmental project as a solution to an existing problem and to include all parties and stakeholders that can benefit from a coordinated environmental…

  5. River Protection Project (RPP) Environmental Program Plan

    SciTech Connect

    POWELL, P.A.

    2000-03-29

    This Environmental Program Plan was developed in support of the Integrated Environment, Safety, and Health Management System Plan (ISMS) (RPP-MP-003), which establishes a single, defined environmental, safety, and health management system that integrates requirements into the work planning and execution processes to protect workers, the public, and the environment. The ISMS also provides mechanisms for increasing worker involvement in work planning, including hazard and environmental impact identification, analysis, and control; work execution; and feedback/improvement processes. The ISMS plan consists of six core functions. Each section of this plan describes the activities of the River Protection Project (RPP) (formerly known as the Tank Waste Remediation System) Environmental organization according to the following core functions: Establish Environmental Policy; Define the Scope of Work; Identify Hazards, Environmental Impacts, and Requirements; Analyze Hazards and Environmental Impacts and Implement Controls; Perform Work within Controls; and Provide Feedback and Continuous Improvement.

  6. Integrating TQM into environmental restoration projects

    SciTech Connect

    Caldwell, J.A.

    1992-12-31

    Responsible and cost-effective waste management and environmental restoration are best achieved when the principles and procedures of Total Quality Management are made an integral part of the process. By describing three case histories, we explore and explain techniques for using TQM in environmental projects. Key aspects considered include: quality measurement systems; establishing and maintaining standard operating procedures; management and technical peer review; the use of Quality Improvement Teams; Roadmapping (a new procedure that the US Department of Energy is incorporating into environmental restoration programs); and the role of audit teams in document production. The three case histories covered include: The Department of Energy`s Uranium Mill Tailings Remedial Action Project on which Roadmapping and Quality Improvement Teams have led to significant changes in procedures; the EPA ARCS program on which adoption of project management Standard Operating Procedures enhanced cost and schedule control; the Jacobs Engineering TQM program that emphasizes performance measurement and management and project technical peer review.

  7. Hanford Environmental Dose Reconstruction Project. Monthly report

    SciTech Connect

    McMakin, A.H.; Cannon, S.D.; Finch, S.M.

    1992-07-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The TSP consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included are appointed technical members representing the states of Oregon, Washington, and Idaho, a representative of Native American tribes, and an individual representing the public. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): Source terms, environmental transport, environmental monitoring data, demography, food consumption, and agriculture, and environmental pathways and dose estimates. Progress is discussed.

  8. Environmental Management Assessment of the Fernald Environmental Management Project (FEMP)

    SciTech Connect

    Not Available

    1993-04-01

    This report documents the results of the Environmental Management Assessment performed at the Fernald Environmental Management Project (FEMP) in Fernald, Ohio. During this assessment, the activities conducted by the assessment team included review of internal documents and reports from previous audits and assessments; interviews with US Department of Energy (DOE) and FEMP contractor personnel; and inspection and observation of selected facilities and operations. The onsite portion of the assessment was conducted from March 15 through April 1, 1993, by DOE`s Office of Environmental Audit (EH-24) located within the Office of the Assistant Secretary for Environment, Safety, and Health (EH-1). EH-24 carries out independent assessments of DOE facilities and activities as part of the EH-1 Environment, Safety, and Health (ES&H) Oversight Audit Program. The EH-24 program is designed to evaluate the status of DOE facilities and activities with respect to compliance with Federal, state, and local environmental laws and regulations; compliance with DOE Orders, Guidance and Directives; conformance with accepted industry practices and standards of performance; and the status and adequacy of management systems developed to address environmental requirements. The Environmental Management Assessment of FEMP focused on the adequacy of environmental management systems. Further, in response to requests by the Office of Environmental Restoration and Waste Management (EM) and Fernald Field Office (FN), Quality Assurance and Environmental Radiation activities at FEMP were evaluated from a programmatic standpoint. The results of the evaluation of these areas are contained in the Environmental Protection Programs section in this report.

  9. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.

    1991-02-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The TSP consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included are appointed technical members representing the states of Oregon and Washington, cultural and technical experts nominated by the regional Native American tribes, and an individual representing the public. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demographics, agriculture, food habits; and environmental pathways and dose estimates. Project reports and references used in the reports are made available to the public in a public reading room. Project progress is documented in this monthly report, which is available to the public. 3 figs., 3 tabs.

  10. Project Management Plan for the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Shipler, D.B.; McMakin, A.H.; Finch, S.M.

    1992-09-01

    This Project Management Plan (PMP) describes the approach being used to manage the Hanford Environmental Dose Reconstruction (HEDR) Project. The plan describes the management structure and the technical and administrative control systems used to plan and control HEDR Project performance. The plan also describes the relationship among key project participants: Battelle, the Centers for Disease control (CDC), and the Technical Steering Panel (TSP). Battelle's contract with CDC only extends through May 1994 when the key technical work will be completed. There-fore, this plan is focused only on the period during which Battelle is a participant.

  11. Project Management Plan for the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Shipler, D.B.; McMakin, A.H.; Finch, S.M.

    1992-09-01

    This Project Management Plan (PMP) describes the approach being used to manage the Hanford Environmental Dose Reconstruction (HEDR) Project. The plan describes the management structure and the technical and administrative control systems used to plan and control HEDR Project performance. The plan also describes the relationship among key project participants: Battelle, the Centers for Disease control (CDC), and the Technical Steering Panel (TSP). Battelle`s contract with CDC only extends through May 1994 when the key technical work will be completed. There-fore, this plan is focused only on the period during which Battelle is a participant.

  12. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Dennis, B.S.

    1990-02-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is divided into technical tasks which address each of the primary steps in the path from radioactive releases to dose estimates. Included are source terms, environmental transport, environmental monitoring data, demographics, agriculture, and food habits, and environmental pathways and dose estimates. The source terms task will develop estimates of radioactive emissions from Hanford facilities since 1944. The environmental transport task will reconstruct the movement of radioactive materials from the areas of release to populations via the atmosphere, surface water, and ground water. The environmental monitoring task will assemble, evaluate, and report historical environmental monitoring data. The demographics, agriculture, and food habits task will develop the data needed to determine the populations that could have been affected by the releases. Population and demographic information will be developed for the general population within the study area. In addition to population and demographic data, the food and water consumption patterns and sources of food and water for these populations must be estimated since these provide a primary pathway for the intake of radionuclides. The environmental pathways and dose estimates task will use the information produced by the other tasks to estimate the radiation doses populations could have received from Hanford. 1 tab., 1 fig.

  13. Hanford Environmental Dose Reconstruction Project monthly report

    SciTech Connect

    McMakin, A.H., Cannon, S.D.; Finch, S.M.

    1992-09-01

    The objective of the Hanford Environmental Dose Reconstruction MDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The TSP consists of experts in envirorunental pathways. epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering. radiation dosimetry. and cultural anthropology. Included are appointed members representing the states of Oregon, Washington, and Idaho, a representative of Native American tribes, and an individual representing the public. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): Source Terms; Environmental Transport; Environmental Monitoring Data Demography, Food Consumption, and Agriculture; and Environmental Pathways and Dose Estimates.

  14. 1995 project of the year Hanford Environmental compliance project nomination

    SciTech Connect

    Kelly, J.R.

    1996-02-01

    The completion of the Hanford Environmental Compliance (HEC) Project in December 1995 brought to a successful close a long line of major contributions to environmental cleanup. Not since the early days of the Hanford Site during and shortly after World War 11 had such a large group of diverse construction activities, with a common goal, been performed at Hanford. Key to this success was the unique combination of 14 subprojects under the HEC Project which afforded the flexibility to address evolving subproject requirements. This strategy resulted in the accomplishment of the HEC Project stakeholders` objectives on an aggressive schedule, at a $33 million cost savings to the customer. The primary objectives of the HEC Project were to upgrade selected Hanford Site facilities and systems to bring them into compliance with current environmental standards and regulations. The HEC Project contributed significantly towards the Hanford site compliance with Clean Water Act, Resource Conservation and Recovery Act (RCRA) and Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) requirements. It provided, in part, those construction activities required to comply with those requirements in the areas of liquid and solid waste treatment and disposal, waste characterization, and groundwater monitoring.

  15. 15 CFR 291.2 - Environmental integration projects.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... environmental issues; and the extent of environmentally related information and expert resources which will be... 15 Commerce and Foreign Trade 1 2012-01-01 2012-01-01 false Environmental integration projects... MANUFACTURING EXTENSION PARTNERSHIP; ENVIRONMENTAL PROJECTS § 291.2 Environmental integration projects....

  16. 15 CFR 291.2 - Environmental integration projects.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... environmental issues; and the extent of environmentally related information and expert resources which will be... 15 Commerce and Foreign Trade 1 2014-01-01 2014-01-01 false Environmental integration projects... MANUFACTURING EXTENSION PARTNERSHIP; ENVIRONMENTAL PROJECTS § 291.2 Environmental integration projects....

  17. 15 CFR 291.2 - Environmental integration projects.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... environmental issues; and the extent of environmentally related information and expert resources which will be... 15 Commerce and Foreign Trade 1 2013-01-01 2013-01-01 false Environmental integration projects... MANUFACTURING EXTENSION PARTNERSHIP; ENVIRONMENTAL PROJECTS § 291.2 Environmental integration projects....

  18. Plant ecology. Anthropogenic environmental changes affect ecosystem stability via biodiversity.

    PubMed

    Hautier, Yann; Tilman, David; Isbell, Forest; Seabloom, Eric W; Borer, Elizabeth T; Reich, Peter B

    2015-04-17

    Human-driven environmental changes may simultaneously affect the biodiversity, productivity, and stability of Earth's ecosystems, but there is no consensus on the causal relationships linking these variables. Data from 12 multiyear experiments that manipulate important anthropogenic drivers, including plant diversity, nitrogen, carbon dioxide, fire, herbivory, and water, show that each driver influences ecosystem productivity. However, the stability of ecosystem productivity is only changed by those drivers that alter biodiversity, with a given decrease in plant species numbers leading to a quantitatively similar decrease in ecosystem stability regardless of which driver caused the biodiversity loss. These results suggest that changes in biodiversity caused by drivers of environmental change may be a major factor determining how global environmental changes affect ecosystem stability. PMID:25883357

  19. Annual progress Report on research related to our research projectStabilization of Plutonium in Subsurface Environments via Microbial Reduction and Biofilm Formation” funded by the Environmental Remediation Sciences Division (ERSD)

    SciTech Connect

    New, Mary

    2006-06-01

    The overarching goal of this research project is to investigate and optimize the mechanisms for in situ immobilization of Pu species by naturally-occurring bacteria. Specific research objectives are: (a) investigate the mechanism of bacterial accumulation and immobilization of plutonium species by biofilm formation under aerobic conditions and (b) to demonstrate the direct and indirect stabilization of Pu via dissimilatory reduction by Geobacter metallireducens.

  20. 15 CFR 291.3 - Environmental tools and techniques projects.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... MANUFACTURING EXTENSION PARTNERSHIP; ENVIRONMENTAL PROJECTS § 291.3 Environmental tools and techniques projects... initial development and implementation of tools or techniques which will aide manufacturing extension..., manufacturing assessment tools, environmental benchmarking tools, training delivery programs,...

  1. Environmental Assessment : Happy Valley [Substation Project].

    SciTech Connect

    United States. Bonneville Power Administration.

    1982-05-01

    The proposed Happy Valley project consists of construction of a new BPA customer service 69-kV substation south of Sequim in Clallam County, Washington. A tie line, to be constructed by the customer as part of this project, will link the new BPA facility to the existing customer's transmission system in the area. This project responds to rapid load growth in the Olympic Peninsula, and will strengthen the existing BPA system and interconnected utility systems. It will reduce transmission losses presently incurred, especially on the BPA system supplying power to the Olympic Peninsula. This report describes the potential environmental impact of the proposed actions. 2 figs., 1 tab.

  2. NPOESS Preparatory Project (NPP) Environmental Products

    NASA Astrophysics Data System (ADS)

    Grant, K. D.; Smith, D. C.

    2011-12-01

    The National Oceanic and Atmospheric Administration (NOAA) and National Aeronautics and Space Administration (NASA) are jointly acquiring the next-generation civilian weather and environmental satellite system: the Joint Polar Satellite System (JPSS). The Joint Polar Satellite System will contribute the afternoon orbit component and ground processing system of the restructured National Polar-orbiting Operational Environmental Satellite System (NPOESS). As such, the Joint Polar Satellite System replaces the current Polar-orbiting Operational Environmental Satellites (POES) managed by NOAA and the ground processing component of both POES and the Defense Meteorological Satellite Program (DMSP) replacement, known as the Defense Weather Satellite System (DWSS), managed by the Department of Defense (DoD). The Joint Polar Satellite System satellite will carry a suite of sensors designed to collect meteorological, oceanographic, climatological, and solar-geophysical observations of the earth, atmosphere, and space. The ground processing system for the Joint Polar Satellite System is known as the Common Ground System (JPSS CGS), and consists of a Command, Control, and Communications Segment (C3S) and the Interface Data Processing Segment (IDPS). Both are developed by Raytheon Intelligence and Information Systems (IIS). The Interface Data Processing Segment will process Joint Polar Satellite System and Defense Weather Satellite System satellite data to provide environmental data products (aka, Environmental Data Records or EDRs) to the National Oceanic and Atmospheric Administration and Department of Defense processing centers operated by the United States government. The Interface Data Processing Segment will process Environmental Data Records beginning with the NPOESS Preparatory Project (NPP) and continue through the lifetime of the Joint Polar Satellite System and Defense Weather Satellite System programs. Under the National Polar-orbiting Operational Environmental

  3. Workplace Environmental Literacy Project (WELP). Final Report.

    ERIC Educational Resources Information Center

    North Orange County Community Coll. District, Fullerton, CA.

    A project was conducted to determine formal and informal competencies based on an expanded definition of workplace environmental literacy. A secondary goal was to develop a compact between employers and training program graduates whereby graduates would have preferential access to employment opportunities. Issues that arose during the…

  4. Environmental Science Projects. LC Science Tracer Bullet.

    ERIC Educational Resources Information Center

    Carter, Constance, Comp.

    This bibliography cites sources to assist middle, junior, and senior high school students and teachers in planning, preparing, and executing science fair projects in the environmental sciences. In addition, a few books with experiments suitable for elementary grade students are included. The listing includes: (1) 5 introductory texts; (2) 31…

  5. Mounds View Environmental Education Project, Report #1.

    ERIC Educational Resources Information Center

    Budde, Duane

    Prepared for the 1971 National Science Teachers Association (NSTA) Annual Meeting, this collection of ideas, activities, and unit plans from the Mounds View Environmental Education Project would be useful for junior and senior high school teachers and curriculum planners. Content includes: (1) a senior high course outline and daily lesson plans…

  6. Project Approval, Environmental Assessment and Public Participation.

    ERIC Educational Resources Information Center

    Elder, P. S.

    1982-01-01

    Presents a case study of a heavy oil project proposed by Esso Resources Canada Limited at Cold Lake, Alberta, Canada. Focuses on the approval process, environmental and social impact assessments, and public participation. Evaluates the case and makes recommendations concerning the approval process. (DC)

  7. Environmental Science Projects. LC Science Tracer Bullet.

    ERIC Educational Resources Information Center

    Carter, Constance, Comp.

    Sources to assist junior and senior high school students and teachers in planning, preparing, and executing science fair projects in the environmental sciences are cited in this bibliography that includes a few books with experiments suitable for elementary grade students. Information and/or citations are provided under the following headings: (1)…

  8. Hanford Environmental Dose Reconstruction Project. Monthly report

    SciTech Connect

    Finch, S. M.; McMakin, A. H.

    1991-09-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation dose that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into five technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (i.e., dose estimates). The Source Terms Task develops estimates of radioactive emissions from Hanford facilities since 1944. The Environmental Transport Task reconstructs the movements of radioactive particles from the areas of release to populations. The Environmental Monitoring Data Task assemblies, evaluates and reports historical environmental monitoring data. The Demographics, Agriculture and Food Habits Task develops the data needed to identify the populations that could have been affected by the releases. The Environmental Pathways and Dose Estimates Task used the information derived from the other Tasks to estimate the radiation doses individuals could have received from Hanford radiation. This document lists the progress on this project as of September 1991. 3 figs., 2 tabs.

  9. 15 CFR 291.2 - Environmental integration projects.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... MANUFACTURING EXTENSION PARTNERSHIP; ENVIRONMENTAL PROJECTS § 291.2 Environmental integration projects. (a) Eligibility criteria. Eligible applicants for these projects are manufacturing extension centers or state... contracts with the NIST Manufacturing Extension Partnership. Only one proposal per organization...

  10. Klickitat Cogeneration Project : Final Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration; Klickitat Energy Partners

    1994-09-01

    To meet BPA`s contractual obligation to supply electrical power to its customers, BPA proposes to acquire power generated by Klickitat Cogeneration Project. BPA has prepared an environmental assessment evaluating the proposed project. Based on the EA analysis, BPA`s proposed action is not a major Federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act of 1969 for the following reasons: (1)it will not have a significant impact land use, upland vegetation, wetlands, water quality, geology, soils, public health and safety, visual quality, historical and cultural resources, recreation and socioeconomics, and (2) impacts to fisheries, wildlife resources, air quality, and noise will be temporary, minor, or sufficiently offset by mitigation. Therefore, the preparation of an environmental impact statement is not required and BPA is issuing this FONSI (Finding of No Significant Impact).

  11. HISPANIC ENVIRONMENTAL AND WASTE MANAGEMENT OUTREACH PROJECT

    SciTech Connect

    Sebastian Puente

    1998-07-25

    The Department of Energy Office of Environmental Management (DOE-EM) in cooperation with the Self Reliance Foundation (SRF) is conducting the Hispanic Environmental and Waste Management Outreach Project (HEWMO) to increase science and environmental literacy, specifically that related to nuclear engineering and waste management in the nuclear industry, among the US Hispanic population. The project will encourage Hispanic youth and young adults to pursue careers through the regular presentation of Spanish-speaking scientists and engineers and other role models, as well as career information on nationally broadcast radio programs reaching youth and parents. This project will encourage making science, mathematics, and technology a conscious part of the everyday life experiences of Hispanic youth and families. The SRF in collaboration with the Hispanic Radio Network (HRN) produces and broadcasts radio programs to address the topics and meet the objectives as outlined in the Environmental Literacy Plan and DOE-EM Communications Plan in this document. The SRF has in place a toll-free ''800'' number Information and Resource Referral (I and RR) service that national radio program listeners can call to obtain information and resource referrals as well as give their reactions to the radio programs that will air. HRN uses this feature to put listeners in touch with local organizations and resources that can provide them with further information and assistance on the related program topics.

  12. Hanford environmental dose reconstruction project: Monthly report

    SciTech Connect

    Dennis, B.S.

    1989-02-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The Technical Steering Panel consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included among the members are appointed technical members representing the States of Oregon and Washington, cultural and technical experts nominated by the Indian tribes in the region, and an individual representing the public.

  13. A Project-Based Model for Professional Environmental Experience

    ERIC Educational Resources Information Center

    Meehan, Barry; Thomas, Ian

    2006-01-01

    The projects described in this article were designed to provide a real world situation akin to the work of environmental professionals. The projects were conducted with Australian students working on environmental issues in Vietnam. The projects demonstrated that multi-disciplinary teamwork fits well into environmental projects, and importantly…

  14. Promoting Student Investigation of Local Environmental Issues through the Southern Highlands Environmental Project: Project Report.

    ERIC Educational Resources Information Center

    Bousquet, Woodward S.

    This report of the Southern Highlands Environmental Project (SHEP) in North Carolina describes its initiation, needs assessment, teacher institute, classroom implementation, outcomes, and dissemination. The purpose of this project was to prepare and support Appalachian teachers in leading their students in investigations of local and regional…

  15. Antelope-Fossil Rebuild Project : Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration.

    1992-04-01

    The Columbia Power Cooperative Association (CPCA), Monument, Oregon, proposes to upgrade a 69-kV transmission line in Wasco and Wheeler Counties, Oregon, between the Antelope Substation and the Bonneville Power Administration`s (BPA) Fossil Substation. The project involves rebuilding and reconductoring 23.2 miles of transmission line, including modifying it for future use at 115 kV. Related project activities will include setting new wood pole structures, removing and disposing of old structures, conductors, and insulators, and stringing new conductor, all within the existing right-of-way. No new access roads will be required. A Borrower`s Environmental Report was prepared for the 1992--1993 Work Plan for Columbia Power Cooperative Association in March 1991. This report investigated cultural resources, threatened or endangered species, wetlands, and floodplains, and other environmental issues, and included correspondence with appropriate Federal, state, and local agencies. The report was submitted to the Rural Electrification Administration for their use in preparing their environmental documentation for the project.

  16. Antelope-Fossil Rebuild Project : Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration.

    1992-04-01

    The Columbia Power Cooperative Association (CPCA), Monument, Oregon, proposes to upgrade a 69-kV transmission line in Wasco and Wheeler Counties, Oregon, between the Antelope Substation and the Bonneville Power Administration's (BPA) Fossil Substation. The project involves rebuilding and reconductoring 23.2 miles of transmission line, including modifying it for future use at 115 kV. Related project activities will include setting new wood pole structures, removing and disposing of old structures, conductors, and insulators, and stringing new conductor, all within the existing right-of-way. No new access roads will be required. A Borrower's Environmental Report was prepared for the 1992--1993 Work Plan for Columbia Power Cooperative Association in March 1991. This report investigated cultural resources, threatened or endangered species, wetlands, and floodplains, and other environmental issues, and included correspondence with appropriate Federal, state, and local agencies. The report was submitted to the Rural Electrification Administration for their use in preparing their environmental documentation for the project.

  17. Single-shell tank interim stabilization project plan

    SciTech Connect

    Ross, W.E.

    1998-05-11

    This project plan establishes the management framework for conduct of the TWRS Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organizational structure, roles, responsibilities, and interfaces; and operational methods. This plan serves as the project executional baseline.

  18. Stabilizing a Bicycle: A Modeling Project

    ERIC Educational Resources Information Center

    Pennings, Timothy J.; Williams, Blair R.

    2010-01-01

    This article is a project that takes students through the process of forming a mathematical model of bicycle dynamics. Beginning with basic ideas from Newtonian mechanics (forces and torques), students use techniques from calculus and differential equations to develop the equations of rotational motion for a bicycle-rider system as it tips from…

  19. UMTRA Project environmental, health, and safety plan

    SciTech Connect

    Not Available

    1989-02-01

    The basic health and safety requirements established in this plan are designed to provide guidelines to be applied at all Uranium Mill Tailings Remedial Action (UMTRA) Project sites. Specific restrictions are given where necessary. However, an attempt has been made to provide guidelines which are generic in nature, and will allow for evaluation of site-specific conditions. Health and safety personnel are expected to exercise professional judgment when interpreting these guidelines to ensure the health and safety of project personnel and the general population. This UMTRA Project Environmental, Health, and Safety (EH S) Plan specifies the basic Federal health and safety standards and special DOE requirements applicable to this program. In addition, responsibilities in carrying out this plan are delineated. Some guidance on program requirements and radiation control and monitoring is also included. An Environmental, Health, and Safety Plan shall be developed as part of the remedial action plan for each mill site and associated disposal site. Special conditions at the site which may present potential health hazards will be described, and special areas that should should be addressed by the Remedial Action Contractor (RAC) will be indicated. Site-specific EH S concerns will be addressed by special contract conditions in RAC subcontracts. 2 tabs.

  20. Single-shell tank interim stabilization project plan

    SciTech Connect

    Ross, W.E.

    1998-03-27

    Solid and liquid radioactive waste continues to be stored in 149 single-shell tanks at the Hanford Site. To date, 119 tanks have had most of the pumpable liquid removed by interim stabilization. Thirty tanks remain to be stabilized. One of these tanks (C-106) will be stabilized by retrieval of the tank contents. The remaining 29 tanks will be interim stabilized by saltwell pumping. In the summer of 1997, the US Department of Energy (DOE) placed a moratorium on the startup of additional saltwell pumping systems because of funding constraints and proposed modifications to the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) milestones to the Washington State Department of Ecology (Ecology). In a letter dated February 10, 1998, Final Determination Pursuant to Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) in the Matter of the Disapproval of the DOE`s Change Control Form M-41-97-01 (Fitzsimmons 1998), Ecology disapproved the DOE Change Control Form M-41-97-01. In response, Fluor Daniel Hanford, Inc. (FDH) directed Lockheed Martin Hanford Corporation (LNMC) to initiate development of a project plan in a letter dated February 25, 1998, Direction for Development of an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan in Support of Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement). In a letter dated March 2, 1998, Request for an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan, the DOE reaffirmed the need for an aggressive SST interim stabilization completion project plan to support a finalized Tri-Party Agreement Milestone M-41 recovery plan. This project plan establishes the management framework for conduct of the TWRS Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organizational structure, roles, responsibilities

  1. NPOESS Preparatory Project (NPP) Environmental Products

    NASA Astrophysics Data System (ADS)

    Grant, K. D.; Hughes, R.; Andreas, N. S.

    2010-12-01

    The National Oceanic and Atmospheric Administration (NOAA), Department of Defense (DoD), and National Aeronautics and Space Administration (NASA) are jointly acquiring the next-generation weather and environmental satellite system; the National Polar-orbiting Operational Environmental Satellite System (NPOESS). NPOESS replaces the current Polar-orbiting Operational Environmental Satellites (POES) managed by NOAA and the Defense Meteorological Satellite Program (DMSP) managed by the DoD. The NPOESS satellites carry a suite of sensors that collect meteorological, oceanographic, climatological, and solar-geophysical observations of the earth, atmosphere, and space. The ground data processing segment for NPOESS is the Interface Data Processing Segment (IDPS), developed by Raytheon Intelligence and Information Systems. The IDPS processes NPOESS satellite data to provide environmental data products (aka, Environmental Data Records or EDRs) to NOAA and DoD processing centers operated by the United States government. The IDPS will process EDRs beginning with the NPOESS Preparatory Project (NPP) and continuing through the lifetime of the NPOESS system. Northrop Grumman Aerospace Systems Algorithms and Data Products (A&DP) organization is responsible for the algorithms that produce the EDRs, including their quality aspects. Given a launch date for the NPP spacecraft on the near horizon and the need for users to become familiar with NPP environmental products, this paper will provide an overview of all the products generated by the IDPS and provided to NOAA’s Comprehensive Large Array-data Stewardship System (CLASS) for public distribution. It will discuss each of the 25 NPP EDRs in detail, including a description of the EDR, its size, coverage, measurement range, and expected uses.

  2. Fundamental Fluidization Research Project. Environmental Assessment

    SciTech Connect

    Not Available

    1994-01-01

    Morgantown Energy Technology Center proposes to conduct fundamental research on fluidization technology by designing, constructing, and operating a 2-foot diameter, 50-foot high, pressurized fluidized-bed unit. The anticipated result of the proposed project would be a better, understanding of fluidization phenomena under pressurized and high velocity conditions. This improved understanding would, provide a sound basis for design and scale-up of pressurized circulating fluidized-bed combustion (PCFBC) processes for fossil energy applications. Based on the analysis in the EA, DOE has determined that the proposed action is not a major, Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act (NEPA) of 1969. Therefore, the preparation of an Environmental Impact Statement is not required and the Department is issuing this FONSI.

  3. Genetic and environmental stability differs in reactive and proactive aggression.

    PubMed

    Tuvblad, Catherine; Raine, Adrian; Zheng, Mo; Baker, Laura A

    2009-01-01

    The aim of this study was to examine stability and change in genetic and environmental influences on reactive (impulsive and affective) and proactive (planned and instrumental) aggression from childhood to early adolescence. The sample was drawn from an ongoing longitudinal twin study of risk factors for antisocial behavior at the University of Southern California (USC). The twins were measured on two occasions: ages 9-10 years (N=1,241) and 11-14 years (N=874). Reactive and proactive aggressive behaviors were rated by parents. The stability in reactive aggression was due to genetic and nonshared environmental influences, whereas the continuity in proactive aggression was primarily genetically mediated. Change in both reactive and proactive aggression between the two occasions was mainly explained by nonshared environmental influences, although some evidence for new genetic variance at the second occasion was found for both forms of aggression. These results suggest that proactive and reactive aggression differ in their genetic and environmental stability, and provide further evidence for some distinction between reactive and proactive forms of aggression. PMID:19688841

  4. Final rapid reactivation project environmental assessment

    SciTech Connect

    1999-02-10

    The US Department of Energy (DOE) has prepared an environmental assessment (EA) for the Rapid Reactivation Project at Sandia National Laboratories, New Mexico. The EA analyzes the potential effects of a proposal to increase production of neutron generators from the current capability of 600 units per year up to 2,000 units per year. The project would use existing buildings and infrastructure to the maximum extent possible to meet the additional production needs. The increased production levels would necessitate modifications and additions involving a total area of approximately 26,290 gross square feet at Sandia National Laboratories, New Mexico, Technical Area 1. Additional production equipment would be procured and installed. The no-action alternative would be to continue production activities at the current capability of 600 units per year. The EA analyzes effects on health, safety, and air quality, resulting from construction and operation and associated cumulative effects. A detailed description of the proposed action and its environmental consequences is presented in the EA.

  5. UMTRA Project value engineering plan. [Design and construction of stabilized tailings embankments

    SciTech Connect

    Not Available

    1990-06-01

    The objective of value engineering (VE) on the Uranium MILL Tailings Remedial Action (UMTRA) Project is to ensure that remedial action at the UMTRA Project sites is performed to meet the US Environmental Protection Agency (EPA) standards for inactive uranium mill tailings sites at the lowest cost, while maintaining a high quality of work. Through review of designs and consideration of reasonable, less expensive alternatives, VE can be an effective cost reduction tool and a means to improve the design. The UMTRA Project products are the design and construction of stabilized tailings embankments.

  6. Longitudinal Stability of Cognitive Ability in the Colorado Adoption Project.

    ERIC Educational Resources Information Center

    Baker, Laura A.; And Others

    1983-01-01

    Measures of general cognitive ability in one- and two-year-old adopted and nonadopted infants and their parents were subjected to path analysis to estimate the contribution of genetic and environmental factors to short-term stability of mental ability. (Author/RH)

  7. Environmental impact assessment of the Dulang oilfield development project

    SciTech Connect

    Hasan, M.N. ); ))

    1988-01-01

    The authors discuss an environmental impact assessment (EIA) of the Dulang Oilfield Development Project, conducted to determine whether the project could proceed in a safe and environmentally acceptable manner. This is the first EIA for an offshore oilfield in Malaysian waters, and was conducted in anticipation of the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment Order(1987)) which requires an EIA to be conducted for major oil and gas field development projects.

  8. Bangladesh Agro-Climatic Environmental Monitoring Project

    NASA Technical Reports Server (NTRS)

    Vermillion, C.; Maurer, H.; Williams, M.; Kamowski, J.; Moore, T.; Maksimovich, W.; Obler, H.; Gilbert, E.

    1988-01-01

    The Agro-Climatic Environmental Monitoring Project (ACEMP) is based on a Participating Agency Service Agreement (PASA) between the Agency for International Development (AID) and the National Oceanic and Atmospheric Administration (NOAA). In FY80, the Asia Bureau and Office of Federal Disaster Assistance (OFDA), worked closely to develop a funding mechanism which would meet Bangladesh's needs both for flood and cyclone warning capability and for application of remote sensing data to development problems. In FY90, OFDA provided for a High Resolution Picture Transmission (HRPT) receiving capability to improve their forecasting accuracy for cyclones, flooding and storm surges. That equipment is primarily intended as a disaster prediction and preparedness measure. The ACEM Project was designed to focus on the development applications of remote sensing technology. Through this Project, AID provided to the Bangladesh Government (BDG) the equipment, technical assistance, and training necessary to collect and employ remote sensing data made available by satellites as well as hydrological data obtained from data collection platforms placed in major rivers. The data collected will enable the BDG to improve the management of its natural resources.

  9. 15 CFR 291.3 - Environmental tools and techniques projects.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 15 Commerce and Foreign Trade 1 2013-01-01 2013-01-01 false Environmental tools and techniques... MANUFACTURING EXTENSION PARTNERSHIP; ENVIRONMENTAL PROJECTS § 291.3 Environmental tools and techniques projects... initial development and implementation of tools or techniques which will aide manufacturing...

  10. 15 CFR 291.3 - Environmental tools and techniques projects.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 15 Commerce and Foreign Trade 1 2014-01-01 2014-01-01 false Environmental tools and techniques... MANUFACTURING EXTENSION PARTNERSHIP; ENVIRONMENTAL PROJECTS § 291.3 Environmental tools and techniques projects... initial development and implementation of tools or techniques which will aide manufacturing...

  11. 15 CFR 291.3 - Environmental tools and techniques projects.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 15 Commerce and Foreign Trade 1 2012-01-01 2012-01-01 false Environmental tools and techniques... MANUFACTURING EXTENSION PARTNERSHIP; ENVIRONMENTAL PROJECTS § 291.3 Environmental tools and techniques projects... initial development and implementation of tools or techniques which will aide manufacturing...

  12. Integrated project management plan for the Plutonium Finishing Plant stabilization and deactivation project

    SciTech Connect

    SINCLAIR, J.C.

    1999-05-03

    This document sets forth the plans, organization, and control systems for managing the PFP Stabilization and Deactivation Project, and includes the top level cost and schedule baselines. The project includes the stabilization of Pu-bearing materials, storage, packaging, and transport of these and other nuclear materials, surveillance and maintenance of facilities and systems relied upon for storage of the materials, and transition of the facilities in the PFP Complex.

  13. ENVIRONMENTAL MANAGEMENT SCIENCE PROGRAM PROJECT NUMBER 87016 CO-PRECIPITATION OF TRACE METALS IN GROUNDWATER AND VADOSE ZONE CALCITE: IN SITU CONTAINMENT AND STABILIZATION OF STRONTIUM-90 AND OTHER DIVALENT METALS AND RADIONUCLIDES AT ARID WESTERN DOE SITES

    SciTech Connect

    Ferris, F. Grant; Fujita, Yoshiko; Smith, Robert W.

    2004-06-15

    Radionuclide and metal contaminants are present in the vadose zone and groundwater throughout the U.S. Department of Energy (DOE) weapons complex. In situ containment and stabilization of these contaminants in vadose zones or groundwater is a cost-effective treatment strategy. Our facilitated approach relies upon the hydrolysis of introduced urea to cause the acceleration of calcium carbonate precipitation (and trace metal coprecipitation) by increasing groundwater pH and alkalinity (Fujita et al., 2000; Warren et al., 2001). Subsurface urea hydrolysis is catalyzed by the urease enzyme, which may be either introduced with the urea or produced in situ by ubiquitous subsurface urea hydrolyzing microorganisms. Because the precipitation processes are irreversible and many western aquifers are saturated with respect to calcite, the co-precipitated metals and radionuclides will be effectively removed from groundwater. The rate at which trace metals are incorporated into calcite is a function of calcite precipitation kinetics, adsorption interactions between the calcite surface and the trace metal in solution (Zachara et al., 1991), solid solution properties of the trace metal in calcite (Tesoriero and Pankow, 1996), and also the surfaces upon which the calcite is precipitating. A fundamental understanding of the coupling of calcite precipitation and trace metal partitioning, and how this occurs in aquifers and vadose environments is lacking. This report summarizes work undertaken during the second year of this project.

  14. Public Scholarship Student Projects for Introductory Environmental Courses

    ERIC Educational Resources Information Center

    Baum, Seth D.; Aman, Destiny D.; Israel, Andrei L.

    2012-01-01

    This paper presents a model project for introductory undergraduate courses that develops students as citizens contributing scholarship to public discussions of environmental issues. In this field-based project, students actively and independently engage with an environmental issue and present their project experience to a relevant public forum. In…

  15. Environmentally Preferable Coatings for Structural Steel Project

    NASA Technical Reports Server (NTRS)

    Lewis, Pattie L. (Editor)

    2014-01-01

    The Ground Systems Development and Operations (GSDO) Program at NASA John F. Kennedy Space Center (KSC) has the primary objective of modernizing and transforming the launch and range complex at KSC to benefit current and future NASA programs along with other emerging users. Described a the "launch support and infrastructure modernization program" in the NASA Authorization Act of 2010, the GSDO Program will develop and implement shared infrastructure and process improvements to provide more flexible, affordable, and responsive capabilities to a multi-user community. In support of the GSDO Program, the objective of this project is to determine the feasibility of environmentally friendly corrosion resistant coatings for launch facilities and ground support equipment. The focus of the project is corrosion resistance and survivability with the goal to reduce the amount of maintenance required to preserve the performance of launch facilities while reducing mission risk. Number of facilities/structures with metallic structural and non-structural components in a highly corrosive environment. Metals require periodic maintenance activity to guard against the insidious effects of corrosion and thus ensure that structures meet or exceed design or performance life. The standard practice for protecting metallic substrates in atmospheric environments is the application of corrosion protective coating system.

  16. Environmental stability and morphologic variation in the bryozoan Homotrypa obliqua

    SciTech Connect

    Key, M.M. Jr

    1985-01-01

    Bryozoans as colonial organisms permit the separation of environmental and genetic contributions to morphologic variation. Previous analyses attempted to establish the effects of environmental stability on the partitioning of morphologic variation. Regrettably they utilized multiple species in different environments. To test this model definitively, colonies of the Ordovician bryozoan Homotrypa obliqua were sampled from paleoenvironments of different stabilities from Cincinnati. The Corryville and Fairmount beds provided ten colonies on which measures of zooecial shape and spacing on and between monticules were made. ANOVA and discriminant function analysis revealed that colonies from the deeper more stable environment of the Corryville beds exhibit more between colony variation. Colonies from the less stable Fairmount beds show relatively more within colony variation. This difference most likely results from less microenvironmental perturbation and/or greater within genotype developmental regulation in colonies from more stable environments. This is confirmed by correlation coefficient matrices that show biologically expected interdependence between characters only in the Corryville colonies. Thus, the partitioning of morphologic variation is a useful tool for predicting paleoenvironmental stability.

  17. Environmental Science: 49 Science Fair Projects. Science Fair Projects Series.

    ERIC Educational Resources Information Center

    Bonnet, Robert L.; Keen, G. Daniel

    This book contains 49 science fair projects designed for 6th to 9th grade students. Projects are organized by the topics of soil, ecology (projects in habitat and life cycles), pests and controls (projects in weeds and insects), recycling (projects in resources and conservation), waste products (projects in decomposition), microscopic organisms,…

  18. 78 FR 26063 - Central Utah Project Completion Act; East Hobble Creek Restoration Project Final Environmental...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-05-03

    ... Hobble Creek Restoration Project Final Environmental Assessment AGENCY: Office of the Assistant Secretary... with the Final Environmental Assessment--East Hobble Creek Restoration Project. These two agencies have... Restoration Project. The Final Environmental Assessment has been completed in conjunction with the June...

  19. Technology integration project: Environmental Restoration Technologies Department Sandia National Laboratories

    SciTech Connect

    Williams, C.V.; Burford, T.D.; Allen, C.A.

    1996-08-01

    Sandia National Laboratories Environmental Restoration Technologies Department is developing environmental restoration technologies through funding form the US Department of Energy`s (DOE`s) Office of Science and Technology. Initially, this technology development has been through the Mixed Waste Landfill Integrated Demonstration (MWLID). It is currently being developed through the Contaminant Plume containment and Remediation Focus Area, the Landfill Stabilization Focus Area, and the Characterization, Monitoring, and Sensor Cross-Cutting Program. This Technology Integration Project (TIP) was responsible for transferring MWLID-developed technologies for routine use by environmental restoration groups throughout the DOE complex and commercializing these technologies to the private sector. The MWLID`s technology transfer/commercialization successes were achieved by involving private industry in development, demonstration, and technology transfer/commercialization activities; gathering and disseminating information about MWLID activities and technologies; and promoting stakeholder and regulatory involvement. From FY91 through FY95, 30 Technical Task Plans (TTPs) were funded. From these TTPs, the MWLID can claim 15 technology transfer/commercialization successes. Another seven technology transfer/commercialization successes are expected. With the changeover to the focus areas, the TIP continued the technology transfer/commercialization efforts begun under the MWLID.

  20. Hanford Environmental Dose Reconstruction Project monthly report, August 1992

    SciTech Connect

    McMakin, A.H.; Cannon, S.D.; Finch, S.M.

    1992-09-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demography; food consumption; and agriculture; and environmental pathway and dose estimates.

  1. Hanford Environmental Dose Reconstruction Project monthly report, August 1992

    SciTech Connect

    McMakin, A.H.; Cannon, S.D.; Finch, S.M.

    1992-01-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demography; food consumption; and agriculture; and environmental pathway and dose estimates.

  2. Hanford Environmental Dose Reconstruction Project monthly report, February 1993

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1993-03-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project Is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): Source Terms; Environmental Transport; Environmental Monitoring Data; Demography, Food Consumption, and Agriculture; and Environmental Pathways and Dose Estimates.

  3. Hanford Environmental Dose Reconstruction Project monthly report, February 1993

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1993-01-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project Is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): Source Terms; Environmental Transport; Environmental Monitoring Data; Demography, Food Consumption, and Agriculture; and Environmental Pathways and Dose Estimates.

  4. Hanford Environmental Dose Reconstruction Project. Monthly report, November 1991

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1991-12-31

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source terms; environmental transport environmental monitoring data; demographics, agriculture, food habits; environmental pathways and dose estimates.

  5. Hanford Environmental Dose Reconstruction Project. Monthly report, January 1992

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-05-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source Terms, Environmental Transport, Environmental Monitoring Data, Demography, Food Consumption, and Agriculture, and Environmental Pathways and Dose Estimates.

  6. Hanford Environmental Dose Reconstruction Project monthly report, March 1993

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1993-03-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): Source Terms, Environmental Transport, Environmental Monitoring Data, Demography, Food Consumption, and Agriculture and Environmental Pathways and Dose Estimates.

  7. Hanford Environmental Dose Reconstruction Project monthly report, January 1993

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1993-01-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944.The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): Source Terms; Environmental Transport; Environmental Monitoring Data; Demography, Food Consumption, and Agriculture; and Environmental Pathways and Dose Estimates.

  8. Hanford Environmental Dose Reconstruction Project monthly report, January 1993

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1993-03-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944.The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): Source Terms; Environmental Transport; Environmental Monitoring Data; Demography, Food Consumption, and Agriculture; and Environmental Pathways and Dose Estimates.

  9. Hanford Environmental Dose Reconstruction Project monthly report, May 1992

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-01-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These task correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source terms, environmental transport, environmental monitoring data, demography, food consumption, and agriculture, and environmental pathways and dose estimates.

  10. Hanford Environmental Dose Reconstruction Project monthly report, May 1992

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-08-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These task correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source terms, environmental transport, environmental monitoring data, demography, food consumption, and agriculture, and environmental pathways and dose estimates.

  11. Environmental Effects on Vertebrate Species Richness: Testing the Energy, Environmental Stability and Habitat Heterogeneity Hypotheses

    PubMed Central

    Luo, Zhenhua; Tang, Songhua; Li, Chunwang; Fang, Hongxia; Hu, Huijian; Yang, Ji; Ding, Jingjing; Jiang, Zhigang

    2012-01-01

    Background Explaining species richness patterns is a central issue in biogeography and macroecology. Several hypotheses have been proposed to explain the mechanisms driving biodiversity patterns, but the causes of species richness gradients remain unclear. In this study, we aimed to explain the impacts of energy, environmental stability, and habitat heterogeneity factors on variation of vertebrate species richness (VSR), based on the VSR pattern in China, so as to test the energy hypothesis, the environmental stability hypothesis, and the habitat heterogeneity hypothesis. Methodology/Principal Findings A dataset was compiled containing the distributions of 2,665 vertebrate species and eleven ecogeographic predictive variables in China. We grouped these variables into categories of energy, environmental stability, and habitat heterogeneity and transformed the data into 100×100 km quadrat systems. To test the three hypotheses, AIC-based model selection was carried out between VSR and the variables in each group and correlation analyses were conducted. There was a decreasing VSR gradient from the southeast to the northwest of China. Our results showed that energy explained 67.6% of the VSR variation, with the annual mean temperature as the main factor, which was followed by annual precipitation and NDVI. Environmental stability factors explained 69.1% of the VSR variation and both temperature annual range and precipitation seasonality had important contributions. By contrast, habitat heterogeneity variables explained only 26.3% of the VSR variation. Significantly positive correlations were detected among VSR, annual mean temperature, annual precipitation, and NDVI, whereas the relationship of VSR and temperature annual range was strongly negative. In addition, other variables showed moderate or ambiguous relations to VSR. Conclusions/Significance The energy hypothesis and the environmental stability hypothesis were supported, whereas little support was found for the

  12. Hanford Environmental Dose Reconstruction Project. Monthly Technical Report, November 1987

    SciTech Connect

    Haerer, H. A.

    1987-11-01

    This monthly report for November 1987 summarizes the technical progress and project status for the Hanford Environmental Dose Reconstruction Project being conducted at Pacific Northwest Laboratory (PNL) under the direction of a Technical Steering Panel (TSP).

  13. Uranium Mill Tailings Remedial Action Project 1993 Environmental Report

    SciTech Connect

    Not Available

    1994-10-01

    This annual report documents the Uranium Mill Tailing Remedial Action (UMTRA) Project environmental monitoring and protection program. The UMTRA Project routinely monitors radiation, radioactive residual materials, and hazardous constituents at associated former uranium tailings processing sites and disposal sites. At the end of 1993, surface remedial action was complete at 10 of the 24 designated UMTRA Project processing sites. In 1993 the UMTRA Project office revised the UMTRA Project Environmental Protection Implementation Plan, as required by the US DOE. Because the UMTRA Project sites are in different stages of remedial action, the breadth of the UMTRA environmental protection program differs from site to site. In general, sites actively undergoing surface remedial action have the most comprehensive environmental programs for sampling media. At sites where surface remedial action is complete and at sites where remedial action has not yet begun, the environmental program consists primarily of surface water and ground water monitoring to support site characterization, baseline risk assessments, or disposal site performance assessments.

  14. Kalispell Maintenance Headquarters Project : Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration.

    1991-01-01

    The facilities needed to maintain and repair Bonneville Power Administration (BPA's) electrical equipment in northwest Montana are currently in two locations: A maintenance headquarters at the Kalispell Substation, and a temporary leased facility south of Kalispell. The present situation is not efficient. There is not enough space to accommodate the equipment needed at each site, and coordination and communication between the two sites is difficult. Also, two sites means duplication of equipment and facilities. BPA needs a single, centralized facility that would efficiently accommodate all the area's maintenance activities and equipment. BPA proposes to build a maintenance headquarters facility consisting of 2 to 4 single-story buildings totaling about 35,000 square feet (office spaces and workshop areas); an open-ended vehicle storage building (carport style); a fenced-in storage year; a storage building for flammables, herbicides, and hazardous wastes; and a parking lot. The facility would require developing about 6 to 10 acres of land. Two sites are being considered for the proposed project (see the attached map for locations). This report is the environmental assessment of the two options.

  15. Fernald Environmental Management Project 1995 site environmental report summary

    SciTech Connect

    1996-06-01

    This report summarizes the 1995 Site Environmental Report for the Fernald site. It describes the Fernald site mission, exposure pathways, and environmental standards and guidelines. An overview is presented of the impact these activities have on the local environment and public health. Environmental monitoring activities measure and estimate the amount of radioactive and nonradioactive materials that may leave the site and enter the surrounding environment.

  16. South Carolina Course Alignment Project: Environmental Scan

    ERIC Educational Resources Information Center

    Educational Policy Improvement Center (NJ1), 2007

    2007-01-01

    An "environmental scan" is designed to identify key issues of policy and practice in an area of interest so that action can be taken. By definition, an environmental scan focuses upon areas of concern. However, the results of an environmental scan are not designed to be either an indictment or endorsement of the current way of doing business since…

  17. Hanford Environmental Dose Reconstruction Project. Monthly report, June 1992

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-06-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Battelle Pacific Northwest Laboratories under contract with the Centers for Disease Control. The independent Technical Steering Panel (TSP) provides technical direction. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demography, food consumption, and agriculture; environmental pathways and dose estimates.

  18. Environmental stability of PAH source indices in pyrogenic tars

    SciTech Connect

    Uhler, A.D.; Emsbo-Mattingly, S.D.

    2006-04-15

    Polycyclic aromatic hydrocarbons (PAHs) are widespread environmental contaminants found in soil, sediments, and airborne particulates. The majority of PAHs found in modern soils and sediments arise from myriad anthropogenic petrogenic and pyrogenic sources. Tars and tar products such as creosote produced from the industrial pyrolysis of coal or oil at former manufactured gas plants (MGPs) or in coking retorts are viscous, oily substances that contain significant concentrations of PAH, usually in excess of 30% w/w. Pyrogenic tars and tar products have unique PAH patterns (source signatures) that are a function of their industrial production. Among pyrogenic materials, certain diagnostic ratios of environmentally recalcitrant 4-, 5- and 6-ring PAHs have been identified as useful environmental markers for tracking the signature of tars and petroleum in the environment. The use of selected PAH source ratios is based on the concept that PAHs with similar properties (i.e., molecular weight, partial pressure, solubility, partition coefficients, and biotic/abiotic degradation) will weather at similar rates in the environment thereby yielding stable ratios. The stability of more than 30 high molecular weight PAH ratios is evaluated during controlled studies of tar evaporation and aerobic biodegradation. The starting materials in these experiments consisted of relatively unweathered tars derived from coal and petroleum, respectively. The PAH ratios from these laboratory studies are compared to those measured in PAH residues found in tar-contaminated soils at a former MGP that operated with a carburetted water gas process.

  19. Operational Environmental Monitoring Program Quality Assurance Project Plan

    SciTech Connect

    Perkins, C.J.

    1994-08-01

    This Quality Assurance Project Plan addresses the quality assurance requirements for the activities associated with the preoperational and operational environmental monitoring performed by Westinghouse Hanford Company as it implements the Operational Environmental Monitoring program. This plan applies to all sampling and monitoring activities performed by Westinghouse Hanford Company in implementing the Operational Environmental Monitoring program at the Hanford Site.

  20. Engaging Citizens in Environmental Decision Making: Burlington, Vermont's EMPACT Project

    ERIC Educational Resources Information Center

    Wang, Deane

    2002-01-01

    In 1998 a Burlington, Vermont partnership of a branch of city government and several educational and environmental organizations received a "metro-grant" to develop a project for the U.S. Environmental Protection Agency (EPA) under its Environmental Monitoring for Public Access and Community Tracking (EMPACT) Program. One goal was to develop…

  1. Hanford Environmental Dose Reconstruction Project monthly report, November 1992

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1992-12-31

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The TSP consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included are appointed members representing the states of Oregon, Washington. and Idaho, a representative of Native American tribes, and an individual representing the public. The project is divided into the following technical tasks: Source terms; environmental transport; environmental monitoring data; demography, food consumption and agriculture; environmental pathways and dose estimates.

  2. Hanford Environmental Dose Reconstruction Project monthly report, November 1992

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1992-01-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The TSP consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included are appointed members representing the states of Oregon, Washington. and Idaho, a representative of Native American tribes, and an individual representing the public. The project is divided into the following technical tasks: Source terms; environmental transport; environmental monitoring data; demography, food consumption and agriculture; environmental pathways and dose estimates.

  3. 78 FR 2685 - Central Utah Project Completion Act; East Hobble Creek Restoration Project Draft Environmental...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-01-14

    ... Office of the Secretary Central Utah Project Completion Act; East Hobble Creek Restoration Project Draft... impacts of the proposed East Hobble Creek Restoration project. The draft environmental assessment, being...: Notice of availability. SUMMARY: The draft environmental assessment for the East Hobble Creek...

  4. Richland Environmental Restoration Project management action process document

    SciTech Connect

    1996-04-01

    This document is the prescribed means for providing direct input to the US Department of Energy Headquarters regarding the status, accomplishments, strategy, and issues of the Richland Environmental Restoration Project. The project mission, organizational interfaces, and operational history of the Hanford Site are provided. Remediation strategies are analyzed in detail. The document includes a status of Richland Environmental Restoration project activities and accomplishments, and it presents current cost summaries, schedules, and technical baselines.

  5. Stability of explosives in environmental water and soil samples

    SciTech Connect

    Maskarinec, M.P.; Bayne, C.K.; Johnson, L.H.; Holladay, S.K.; Jenkins, R.A.; Tomkins, B.A.

    1991-01-01

    This report focuses on data generated for the purpose of establishing the stability of HMX, RDX, TNT, and DNT explosives in environmental water and soil samples. The study was carried out over a one year time frame and took into account as many variables as possible within the constraints of budget and time. The objectives of the study were: (1) to provide a data base which could be used to provide guidance on pre-analytical holding times for regulatory purposes; and (2) and to provide a basis for the evaluation of data which is generated outside of the currently allowable holding times for quality assurance purposes. The experimental design consisted of three water samples and three soil samples. The water samples were distilled-in-glass water, a ground water, and surface water. The soil samples were a US Army Toxic and Hazardous Materials Agency soil, a Captina silt loam from Roane County, Tennessee, and a McLaurin sandy loam from Stone County, Mississippi. The analytes consisted of four explosives HMX, RDX, TNT and DNT. Several approaches were taken to estimate the MHTs for each explosive because a standard definition for MHT has not been adopted by the Environmental Protection Agency (EPA). First, a procedure recommended by the American Society for Testing and Materials (ASTM) was modified and applied to the data base. Secondly, a procedure developed by Environmental Science and Engineering (ESE) for the analysis of a similar data base was applied. This report is intended to summarize the findings of the study in such a way as to allow individual decisions to be made regarding the quality of environmental data. The use of the data base may well be different for analyses conducted under RCRA, for example, than for those conducted under NPDES permit requirements. For this reason, the summary statistics for each replicate analysis is presented in the appendices of this report. 18 refs., 4 figs., 14 tabs.

  6. Fernald Environmental Management Project 1995 site environmental report

    SciTech Connect

    1996-06-01

    The Fernald site continues to examine the air and liquid pathways as possible routes through which pollutants from past operations and current remedial activities may leave the site. This 1995 Site Environmental Report provides the general public as well as scientists and engineers with the results from the site`s ongoing Environmental Monitoring Program. Also included in this report is information concerning the site`s progress toward achieving full compliance with requirements set forth by DOE, US Environmental Protection Agency (USEPA), and Ohio EPA.

  7. Effect of environmental humidity on static foam stability.

    PubMed

    Li, Xueliang; Karakashev, Stoyan I; Evans, Geoffrey M; Stevenson, Paul

    2012-03-01

    The quality of foaming products (such as beer and shampoo) and the performance of industrial processes that harness foam (such as the froth flotation of minerals or the foam fractionation of proteins) depend upon foam stability. In this study, experiments are performed to study the effect of environmental humidity on the collapse of static foams. The dependency of the rate at which a foam collapses upon humidity is demonstrated, and we propose a hypothesis for bubble bursting due to Marangoni instability induced by nonuniform evaporation to help explain the dependency. This hypothesis is supported by direct experimental observations of the bursting process of isolated bubbles by high speed video recording and the thinning of isolated foam films under different values of humidity and temperature by microinterferometric methods. PMID:22303917

  8. The Field Project as a Tool for Teaching Environmental Psychology.

    ERIC Educational Resources Information Center

    Howells, Gary N.

    1978-01-01

    Describes a university class project designed to enable students to translate environmental research into action. Students focused on a conflict between state and county government over solid waste management. Outlines steps involved in such a project and discusses student involvement and the success of the project. (KC)

  9. Plume Mitigation for Mars Terminal Landing: Soil Stabilization Project

    NASA Technical Reports Server (NTRS)

    Hintze, Paul E.

    2014-01-01

    Kennedy Space Center (KSC) has led the efforts for lunar and Martian landing site preparation, including excavation, soil stabilization, and plume damage prediction. There has been much discussion of sintering but until our team recently demonstrated it for the lunar case there was little understanding of the serious challenges. Simplistic sintering creates a crumbly, brittle, weak surface unsuitable for a rocket exhaust plume. The goal of this project is to solve those problems and make it possible to land a human class lander on Mars, making terminal landing of humans on Mars possible for the first time.

  10. Environmental Report Utah State Prison Geothermal Project

    SciTech Connect

    1980-03-01

    This environmental report assesses the potential impact of developing a geothermal resource for space heating at the Utah State Prison. Wells will be drilled on prison property for production and for injection to minimize reservoir depletion and provide for convenient disposal of cooled fluid. The most significant environmental concerns are the proper handling of drilling muds during well drilling and the disposal of produced water during well testing. These problems will be handled by following currently accepted practices to reduce the potential risks.

  11. Acid Pit Stabilization Project (Volume 1 - Cold Testing) and (Volume 2 - Hot Testing)

    SciTech Connect

    G. G. Loomis; A. P. Zdinak; M. A. Ewanic; J. J. Jessmore

    1998-01-01

    During the summer and fall of Fiscal Year 1997, a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Treatability Study was performed at the Idaho National Engineering and Environmental Laboratory. The study involved subsurface stabilization of a mixed waste contaminated soil site called the Acid Pit. This study represents the culmination of a successful technology development effort that spanned Fiscal Years 1994-1996. Research and development of the in situ grout stabilization technique was conducted. Hardware and implementation techniques are currently documented in a patent pending with the United States Patent and Trademark Office. The stabilization technique involved using jet grouting of an innovative grouting material to form a monolith out of the contamination zone. The monolith simultaneously provides a barrier to further contaminant migration and closes voids in the soil structure against further subsidence. This is accomplished by chemical incorporation of contaminants into less soluble species and achieving a general reduction in hydraulic conductivity within the monolith. The grout used for this study was TECT-HG, a relatively dense iron oxide-based cementitious grout. The treatability study involved cold testing followed by in situ stabilization of the Acid Pit. Volume 1 of this report discusses cold testing, performed as part of a ''Management Readiness Assessment'' in preparation for going hot. Volume 2 discusses the results of the hot Acid Pit Stabilization phase of this project. Drilling equipment was specifically rigged to reduce the spread of contamination, and all grouting was performed under a concrete block containing void space to absorb any grout returns. Data evaluation included examination of implementability of the grouting process and an evaluation of the contaminant spread during grouting. Following curing of the stabilized pit, cores were obtained and evaluated for toxicity characteristic leach ing

  12. Criticality accident alarm system at the Fernald Environmental Management Project

    SciTech Connect

    Marble, R.C.; Brown, T.D.; Wooldridge, J.C.

    1994-12-31

    This paper describes the staus of the Fernald Environmental Management Project (FEMP) criticality alarm system. A new radiation detection alarm system was installed in 1990. The anunciation system, calibration and maintenance, and detector placement is described.

  13. Hanford Environmental Dose Reconstruction Project. Monthly report, December 1991

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1991-12-31

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The TSP consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included are appointed technical members representing the states of Oregon and Washington, a representative of Native American tribes, and an individual representing the public. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on human (dose estimates): Source Terms; Environmental Transport; Environmental Monitoring Data; Demographics, Agriculture, Food Habits and; Environmental Pathways and Dose Estimates.

  14. Uranium Mill Tailings Remedial Action Project Environmental Protection Implementation Plan

    SciTech Connect

    Vollmer, A.T.

    1993-10-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project Environmental Protection Implementation Plan (EPIP) has been prepared in accordance with the requirements of the US Department of Energy (DOE) Order 5400.1. The UMTRA EPIP covers the time period of November 9, 1993, through November 8, 1994. It will be updated annually. Its purpose is to provide management direction to ensure that the UMTRA Project is operated and managed in a manner that will protect, maintain, and where necessary, restore environmental quality, minimize potential threats to public health and the environment, and comply with environmental regulations and DOE policies. Contents of this report are: (1) general description of the UMTRA project environmental protection program; (2) notifications; (3) planning and reporting; (4) special programs; (5) environmental monitoring programs; (6) quality assurance and data verification; and (7) references.

  15. Environmental Technology (Laboratory Analysis and Environmental Sampling) Curriculum Development Project. Final Report.

    ERIC Educational Resources Information Center

    Hinojosa, Oscar V.; Guillen, Alfonso

    A project assessed the need and developed a curriculum for environmental technology (laboratory analysis and environmental sampling) in the emerging high technology centered around environmental safety and health in Texas. Initial data were collected through interviews by telephone and in person and through onsite visits. Additional data was…

  16. Hellsgate Winter Range : Wildlife Mitigation Project. Preliminary Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration.

    1995-01-01

    The Bonneville Power Administration proposes funding the Hellsgate Winter Range Wildlife Mitigation Project in cooperation with the Colville Convederated Tribes and Bureau of Indian Affairs. This Preliminary Environmental Assessment examines the potential environmental effects of acquiring and managing property for wildlife and wildlife habitat within a large project area. The Propose action is intended to meet the need for mitigation of wildlife and wild life habitat that was adversely affected by the construction of Grand Coulee and Chief Joseph Dams and their reservoirs.

  17. Environmental Studies: Five Miscellaneous Reports. Project Reports, Volume 7, The Rachel Carson Project.

    ERIC Educational Resources Information Center

    Tanner, R. Thomas

    This document is the last of seven volumes included in the Rachel Carson Project. The project attempts to introduce environmental education lessons and units into existing courses of study within a high school curriculum rather than to implement environmental education through the introduction of new courses. Included in this volume is a report…

  18. Environmental Studies in Several Science Courses. Project Reports, Volume 4, The Rachel Carson Project.

    ERIC Educational Resources Information Center

    Tanner, R. Thomas

    This document is the fourth of seven accompanying volumes included in the Rachel Carson Project. The project attempts to introduce environmental education lessons and units into existing courses of study within a high school curriculum rather than to implement environmental education through the introduction of new courses. This volume reports the…

  19. Environmental Studies in the Physical Sciences. Project Reports, Volume 3, The Rachel Carson Project.

    ERIC Educational Resources Information Center

    Tanner, R. Thomas

    This document is the third of seven accompanying volumes included in the Rachel Carson Project. The project attempts to introduce environmental education lessons and units into existing courses of study within a high school rather than to implement environmental education through the introduction of new courses. This volume reports the…

  20. Environmentally Sound Small-Scale Energy Projects. Guidelines for Planning.

    ERIC Educational Resources Information Center

    Bassan, Elizabeth Ann; Wood, Timothy S., Ed.

    This manual is the fourth volume in a series of publications that provide information for the planning of environmentally sound small-scale projects. Programs that aim to protect the renewable natural resources that supply most of the energy used in developing nations are suggested. Considerations are made for physical environmental factors as…

  1. Trade-off analysis for environmental projects: An annotated bibliography

    SciTech Connect

    Feather, T.D.; Harrington, K.W.; Capan, D.T.

    1995-08-01

    This is a report with an attached annotated bibliography. This study explores the literature for analytical techniques that can support the complex decision-making process associated with Corps of Engineers environmental projects. The literature review focuses on opportunities for using trade-off methodologies and group processes in environmental plan formulation and evaluation. The work was conducted under the Evaluation Framework Work Unit within the Evaluation of Environmental Investments Research Program.

  2. Environmental Projects. Volume 9: Construction of hazardous materials storage facilities

    NASA Technical Reports Server (NTRS)

    1989-01-01

    Activities at the Goldstone Deep Space Communications Complex (GDSCC) are carried out in support of seven parabolic dish antennas. These activities may give rise to environmental hazards. This report is one in a series of reports describing environmental projects at GDSCC. The construction of two hazardous materials and wastes storage facilities and an acid-wash facility is described. An overview of the Goldstone complex is also presented along with a description of the environmental aspects of the GDSCC site.

  3. Environmental stability and the evolution of cooperative breeding in hornbills

    PubMed Central

    Gonzalez, Juan-Carlos T.; Sheldon, Ben C.; Tobias, Joseph A.

    2013-01-01

    Reproductive cooperation in social animals has been the focus of intensive research, yet the role of environmental factors in promoting such cooperation remains uncertain. A recent global analysis suggested that cooperative breeding in birds is a ‘bet-hedging’ strategy associated with climatic uncertainty, but it is unclear whether this mechanism applies generally or is restricted to the insectivorous passerines that predominate as cooperative breeders at the global scale. Here, we use a phylogenetic framework to assess the effect of climate on the evolution of cooperation in hornbills (Bucerotidae), an avian family characterized by frugivory and carnivory. We show that, in contrast to the global pattern, cooperative reproduction is positively associated with both inter- and intra-annual climatic stability. This reversed relationship implies that hornbills are relatively insensitive to climatic fluctuations, perhaps because of their dietary niche or increased body mass, both of which may remove the need for bet-hedging. We conclude that the relationship between climatic variability and cooperative breeding is inconsistent across taxa, and potentially mediated by life-history variation. These findings help to explain the mixed results of previous studies and highlight the likely shortcomings of global datasets inherently biased towards particular categories. PMID:23926149

  4. The Project-Based Learning Approach in Environmental Education

    ERIC Educational Resources Information Center

    Genc, Murat

    2015-01-01

    The purpose of this study is to investigate the effect of project-based learning on students' attitudes toward the environment. In the study that was performed with 39 students who take the "Environmental Education" course, attitude changes toward the environment were investigated in students who developed projects on environmental…

  5. Environmentally Sound Small-Scale Water Projects. Guidelines for Planning.

    ERIC Educational Resources Information Center

    Tillman, Gus

    This manual is the second volume in a series of publications on community development programs. Guidelines are suggested for small-scale water projects that would benefit segments of the world's urban or rural poor. Strategies in project planning, implementation and evaluation are presented that emphasize environmental conservation and promote…

  6. Project Canada West. Canadian Environmental Concepts.

    ERIC Educational Resources Information Center

    Western Curriculum Project on Canada Studies, Edmonton (Alberta).

    The overall objective of the curriculum development project is to develop a general high school level interdisciplinary course on environment studies. This potential five to ten month course is outlined as follows: ecology, water pollution, air pollution, noise pollution, population, socioeconomic implications, and resource management. The general…

  7. Managing environmental issues during international electric power project development

    SciTech Connect

    Cooper, H.W.

    1998-07-01

    Responsible international project developers most often view environmental matters with quite mixed emotions. Those with whom Dynalytics has worked would certainly never contemplate jeopardizing the health of anyone in the world. But while they want their projects realized, and are willing to implement reasonable requirements, they are often asked to do more than is appropriate, more than is technologically possible, and more than is financially possible. The paper discusses the following: who is in charge of environmental matters; whose environmental standards apply; the role of technology; accelerating timetables and reducing costs; documentation and applications; and post-construction requirements.

  8. Project W-314 phase I environmental permits and approvals plan

    SciTech Connect

    TOLLEFSON, K.S.

    1999-02-24

    This document describes the range of environmental actions, including required permits and other agency approvals, for Project W-314 activities in the Hanford Site's Tank Waste Remediation System. This document outlines alternative approaches to satisfying applicable environmental standards, and describes selected strategies for acquiring permits and other approvals needed for waste feed delivery to proceed. This document also includes estimated costs and schedule to obtain the required permits and approvals based on the selected strategy. It also provides estimated costs for environmental support during design and construction based on the preliminary project schedule provided.

  9. Uranium Mill Tailings Remedial Action Project environmental protection implementation plan

    SciTech Connect

    Not Available

    1994-10-01

    The Uranium Mill Tailings Remedial Action (UMTRA) Project Environmental Protection Implementation Plan (EPIP) has been prepared in accordance with the requirements of the U.S. Department of Energy (DOE) Order 5400.1. The UMTRA EPIP is updated annually. This version covers the time period of 9 November 1994, through 8 November 1995. Its purpose is to provide management direction to ensure that the UMTRA Project is operated and managed in a manner that will protect, maintain, and where necessary, restore environmental quality, minimize potential threats to public health and the environment, and comply with environmental regulations and DOE policies.

  10. Uranium Mill Tailings Remedial Action Project Environmental Protection Implementation Plan

    SciTech Connect

    Not Available

    1992-10-01

    The Uranium Mill Tallings Remedial Action (UMTRA) Project Environmental Protection Implementation Plan (EPIP) has been prepared in accordance with the requirements of the US Department of Energy (DOE) Order 5400.1 (Chapter 3, paragraph 2). The UMTRA EPIP covers the time period of November 9, 1992, through November 8, 1993. It will be updated annually. Its purpose is to provide management direction to ensure that the UMTRA Project is operated and managed in a manner that will protect, maintain, and where necessary, restore environmental quality, minimize potential threats to public health and the environment, and comply with environmental regulations and DOE policies.

  11. Environmental training research project. Final report

    SciTech Connect

    1996-04-01

    Santa Fe Community College serves an area including the city and county of Santa Fe. The population has a high percentage of Hispanics and a Native American population of about 3%. The student body at the college generally reflects that of the service district. The college strives to recruit students from all segments of the population so there is representation among all ethnic and economic groups. The college strives to serve students and the community by offering educational opportunities that meet the needs of both elements and which will lead to gainful employment. Instruction is also offered to meets needs for retraining, upgrades, and personal enlightenment. The college started a hazardous materials management program in the fall of 1991 which has since been renamed environmental management. The purpose of this program is to prepare students for environmental careers, to provide required training such as OSHA HAZWOPER and refresher courses, and to provide educational opportunities that would make the public more environmentally aware. The program content needs to be studied to ensure we`re meeting the needs of the students and the business community. There had not been a significant opportunity to conduct this research.

  12. Interferometric Testbed for Nanometer Level Stabilization of Environmental Motion Over Long Timescales

    NASA Technical Reports Server (NTRS)

    Numata, Kenji; Camp, Jordan

    2008-01-01

    We developed an interferometric testbed to stabilize environmental motions over timescales of several hours and a lengthscale of 1m. Typically, thermal and seismic motions on the ground are larger than 1 micron over these scales, affecting the precision of more sensitive measurements. To suppress such motions, we built an active stabilization system composed of interferometric sensors, a hexapod actuator, and a frequency stabilized laser. With this stabilized testbed, environmental motions were suppressed down to nm level. This system will allow us to perform sensitive measurements, such as ground testing of LISA (Laser Interferometer Space Antenna), in the presence of environmental noise.

  13. International environmental issues and requirements for new power projects

    SciTech Connect

    Newman, J.R.; Maltby, J.H.

    1997-12-31

    The purpose of this presentation was to discuss the emerging role of financial entities in determining environmental requirements for international power projects. The paper outlines the following: emerging conditions; examples of announced privatization energy projects by country; types of government and international financial entity sources; problems for IPPs; similarity and differences between the World Bank and the USEPA; comparison of the international standards and regulations for power plants; recent trends/issues involving international power project approval; and recommendations for understanding/expediting the financial entities` environmental approval process and how to expedite this process.

  14. Application of quality assurance standards to environmental projects

    SciTech Connect

    Richardson, T.L.; Lynch, J.E.; Chaudhary, T.B.

    1994-12-31

    Quality assurance (QA) is critical to every environmental project undertaken. While QA appears to be a cut-and-dried subject, it is actually an evolving issue. Environmental projects need high QA standards. The needs of the nuclear industry have driven most QA programs for the last several decades. Mom recently, the internationally accepted ISO-9000 standard, and the more recent E-4 standard (in draft), have been suggested as alternatives to achieving QA for environmental firms. These standards can be successfully integrated and implemented. However, this requires good up-front planning of the program`s purpose and function and commitments by management and staff to make it work. The purpose of this paper is to discuss how various QA standards can be appropriately applied to the demands of environmental projects.

  15. Advanced Coal Conversion Process Demonstration Project. Environmental Monitoring Plan

    SciTech Connect

    Not Available

    1992-04-01

    Western Energy Company (WECO) was selected by the Department of Energy (DOE) to demonstrate the Advanced Coal Conversion Process (ACCP) which upgrades low rank coals into high Btu, low sulfur, synthetic bituminous coal. As specified in the Corporate Agreement, RSCP is required to develop an Environmental Monitoring Plan (EMP) which describes in detail the environmental monitoring activities to be performed during the project execution. The purpose of the EMP is to: (1) identify monitoring activities that will be undertaken to show compliance to applicable regulations, (2) confirm the specific environmental impacts predicted in the National Environmental Policy Act documentation, and (3) establish an information base of the assessment of the environmental performance of the technology demonstrated by the project. The EMP specifies the streams to be monitored (e.g. gaseous, aqueous, and solid waste), the parameters to be measured (e.g. temperature, pressure, flow rate), and the species to be analyzed (e.g. sulfur compounds, nitrogen compounds, trace elements) as well as human health and safety exposure levels. The operation and frequency of the monitoring activities is specified, as well as the timing for the monitoring activities related to project phase (e.g. preconstruction, construction, commissioning, operational, post-operational). The EMP is designed to assess the environmental impacts and the environmental improvements resulting from construction and operation of the project.

  16. Healy Clean Coal Project, Healy, Alaska final Environmental Monitoring Plan

    SciTech Connect

    Not Available

    1994-06-14

    This Environmental Monitoring Plan (EMP) provides the mechanism to evaluate the integrated coal combustion/emission control system being demonstrated by the Healy Clean Coal Project (HCCP) as part-of the third solicitation of the US Department of Energy (DOE) Clean Coal Technology Demonstration Program (CCT-III). The EMP monitoring is intended to satisfy two objectives: (1) to develop the information base necessary for identification, assessment, and mitigation of potential environmental problems arising from replication of the technology and (2) to identify and quantify project-specific and site-specific environmental impacts predicted in the National Environmental Policy Act (NEPA) documents (Environmental Impact Statement and Record of Decision). The EMP contains a description of the background and history of development of the project technologies and defines the processes that will take place in the combustion and spray dryer absorber systems, including the formation of flash-calcined material (FCM) and its use in sulfur dioxide (SO{sub 2}) removal from the flue gases. It also contains a description of the existing environmental resources of the project area. The EMP includes two types of environmental monitoring that are to be used to demonstrate the technologies of the HCCP: compliance monitoring and supplemental monitoring. Compliance monitoring activities include air emissions, wastewater effluents, and visibility. Monitoring of these resources provide the data necessary to demonstrate that the power plant can operate under the required state and federal statutes, regulations, and permit requirements.

  17. Environmental mitigation and the Upper Yazoo Projects

    NASA Astrophysics Data System (ADS)

    Dardeau, E. A.; Fischenich, J. C.

    1995-02-01

    The US Army Engineer District, Vicksburg (CELMK), evaluated an array of flood control alternatives, which included up to 167 water control structures, 52 confined disposal facilities, and 47 borrow pits as part of a major flood control effort known as the Upper Yazoo Projects (UYP). Many of these project features are capable of ponding water and thus can be managed to mitigate for aquatic, terrestrial, waterfowl, and wetland resource losses expected to occur as a result of the UYP. The benefits to be derived will depend upon the land uses and management of the ponded areas. The US Army Engineer Waterways Experiment Station developed procedures to quantify the cost and habitat benefits of the many management options for these sites. The mitigation strategy was derived by optimizing various combinations of land acquisition, reforestation, land-use change, and site hydrology so that the least-cost mitigation plan could be selected.

  18. Griffith Energy Project Final Environmental Impact Statement

    SciTech Connect

    N /A

    1999-04-02

    Griffith Energy Limited Liability Corporation (Griffith) proposes to construct and operate the Griffith Energy Project (Project), a natural gas-fuel, combined cycle power plant, on private lands south of Kingman, Ariz. The Project would be a ''merchant plant'' which means that it is not owned by a utility and there is currently no long-term commitment or obligation by any utility to purchase the capacity and energy generated by the power plant. Griffith applied to interconnect its proposed power plant with the Western Area Power Administration's (Western) Pacific Northwest-Pacific Southwest Intertie and Parker-Davis transmission systems. Western, as a major transmission system owner, needs to provide access to its transmission system when it is requested by an eligible organization per existing policies, regulations and laws. The proposed interconnection would integrate the power generated by the Project into the regional transmission grid and would allow Griffith to supply its power to the competitive electric wholesale market. Based on the application, Western's proposed action is to enter into an interconnection and construction agreement with Griffith for the requested interconnections. The proposed action includes the power plant, water wells and transmission line, natural gas pipelines, new electrical transmission lines and a substation, upgrade of an existing transmission line, and access road to the power plant. Construction of segments of the transmission lines and a proposed natural gas pipeline also require a grant of right-of-way across Federal lands administered by the Bureau of Land Management. Public comments on the Draft EIS are addressed in the Final EIS, including addenda and modifications made as a result of the comments and/or new information.

  19. The Environmental Management Project Manager`s Handbook for improved project definition

    SciTech Connect

    1995-02-01

    The United States Department of Energy (DOE) is committed to providing high quality products that satisfy customer needs and are the associated with this goal, DOE personnel must possess the knowledge, skills, and abilities to ensure successful job performance. In addition, there must be recognition that the greatest obstacle to proper project performance is inadequate project definition. Without strong project definition, DOE environmental management efforts are vulnerable to fragmented solutions, duplication of effort, and wastes resources. The primary means of ensuring environmental management projects meet cost and schedule milestones is through a structured and graded approach to project definition, which is the focus of this handbook.

  20. Domestic environmental requirements, new and projected

    SciTech Connect

    McLean, B.J.

    1997-12-31

    The paper outlines and/or gives data on the following: environmental concerns; goal of Title IV; national SO{sub 2} emissions; reductions in wet sulfate deposition; SO{sub 2} allowance program--benefits and costs; utility NO{sub x} emissions; NO{sub x} compliance options; cost effectiveness of NO{sub x} control; electric power regulations timeline; Clean Air power initiative; what a new approach would look like; and an analysis of NO{sub x} and SO{sub 2} cap and trade scenarios.

  1. Quality assurance project plan for the Chestnut Ridge Fly Ash Pond Stabilization Project at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    SciTech Connect

    1996-07-01

    The Chestnut Ridge Fly Ash Pond Stabilization (CRFAPS) Project will stabilize a 19-m-high (62-ft-high) earthen embankment across Upper McCoy Branch situated along the southern slope of Chestnut Ridge. This task will be accomplished by raising the crest of the embankment, reinforcing the face of the embankment, removing trees from the face and top of the embankment, and repairing the emergency spillway. The primary responsibilities of the team members are: Lockheed Martin Energy Systems, Inc., (Energy Systems) will be responsible for project integration, technical support, Title 3 field support, environmental oversight, and quality assurance (QA) oversight of the project; Foster Wheeler Environmental Corporation (FWENC) will be responsible for design and home office Title 3 support; MK-Ferguson of Oak Ridge Company (MK-F) will be responsible for health and safety, construction, and procurement of construction materials. Each of the team members has a QA program approved by the US Department of Energy (DOE) Oak Ridge Operations. This project-specific QA project plan (QAPP), which is applicable to all project activities, identifies and integrates the specific QA requirements from the participant`s QA programs that are necessary for this project.

  2. Near Facility Environmental Monitoring Quality Assurance Project Plan

    SciTech Connect

    MCKINNEY, S.M.

    2000-05-01

    This Quality Assurance Project Plan addresses the quality assurance requirements for the activities associated with the preoperational and near-facility environmental monitoring directed by Waste Management Technical Services and supersedes HNF-EP-0538-4. This plan applies to all sampling and monitoring activities performed by Waste Management Technical Services in implementing near-facility environmental monitoring at the Hanford Site. This Quality Assurance Project Plan is required by U.S. Department of Energy Order 5400.1 (DOE 1990) as a part of the Environmental Monitoring Plan (DOE-RL 1997) and is used to define: Environmental measurement and sampling locations used to monitor environmental contaminants near active and inactive facilities and waste storage and disposal sites; Procedures and equipment needed to perform the measurement and sampling; Frequency and analyses required for each measurement and sampling location; Minimum detection level and accuracy; Quality assurance components; and Investigation levels. Near-facility environmental monitoring for the Hanford Site is conducted in accordance with the requirements of U.S. Department of Energy Orders 5400.1 (DOE 1990), 5400.5 (DOE 1993), 5484.1 (DOE 1990), and 435.1 (DOE 1999), and DOE/EH-O173T (DOE 1991). It is Waste Management Technical Services' objective to manage and conduct near-facility environmental monitoring activities at the Hanford Site in a cost-effective and environmentally responsible manner that is in compliance with the letter and spirit of these regulations and other environmental regulations, statutes, and standards.

  3. Environmental planning for oil and gas projects in alliance organizations

    SciTech Connect

    Hanley, P.T.; Campbell, G.R.B.; Wuestenfield, K.S.

    1996-12-31

    Oil companies are increasingly adopting the {open_quotes}alliance{close_quotes} organization to develop innovative engineering solutions to make projects economic in an industry characterized by global opportunities and competition for investment dollars. This structure involves strategic contractual relationships between companies and contractors. On Alaska`s North Slope, BP Exploration (Alaska) Inc. has formed alliances to engineer and develop its Badami and Northstar oil fields. These fields are small in comparison to Prudhoe Bay and Endicott and their economics cannot support high capital and operating costs. Costs, reserves, and permits are the three major building blocks of a successful oil development project. The alliance structure presents some special challenges and opportunities in successfully designing an environmentally sensitive project rd obtaining permits. On the Badami project, permitting has required that alliance members, the regulators, and BPXA environmental personnel develop a mutual understanding and reaction of engineering and environmental constraints and opportunities. Part of the communications challenge has resulted from the differing mandates and boundaries of the alliance and the external requirements of environmental laws and regulations. The lessons learned on Badami have been adopted in environmental planning and permitting the Northstar project.

  4. Uranium Mill Tailings Remedial Action Project 1994 environmental report

    SciTech Connect

    1995-08-01

    This annual report documents the Uranium Mill Tailings Remedial Action (UMTRA) Project environmental monitoring and protection program. The UMTRA Project routinely monitors radiation, radioactive residual materials, and hazardous constituents at associated former uranium tailings processing sites and disposal sites. At the end of 1994, surface remedial action was complete at 14 of the 24 designated UMTRA Project processing sites: Canonsburg, Pennsylvania; Durango, Colorado; Grand Junction, Colorado; Green River Utah, Lakeview, Oregon; Lowman, Idaho; Mexican Hat, Utah; Riverton, Wyoming; Salt Lake City, Utah; Falls City, Texas; Shiprock, New Mexico; Spook, Wyoming, Tuba City, Arizona; and Monument Valley, Arizona. Surface remedial action was ongoing at 5 sites: Ambrosia Lake, New Mexico; Naturita, Colorado; Gunnison, Colorado; and Rifle, Colorado (2 sites). Remedial action has not begun at the 5 remaining UMTRA Project sites that are in the planning stage. Belfield and Bowman, North Dakota; Maybell, Colorado; and Slick Rock, Colorado (2 sites). The ground water compliance phase of the UMTRA Project started in 1991. Because the UMTRA Project sites are.` different stages of remedial action, the breadth of the UMTRA environmental protection program differs from site to site. In general, sites actively undergoing surface remedial action have the most comprehensive environmental programs for sampling media. At sites where surface remedial action is complete and at sites where remedial action has not yet begun, the environmental program consists primarily of surface water and ground water monitoring to support site characterization, baseline risk assessments, or disposal site performance assessments.

  5. Improving Environmental Projections in Nonboreal Eastern Europe

    NASA Astrophysics Data System (ADS)

    Groisman, Pavel; Ivanov, Sergiy; Gutman, Garik; Simmer, Clemens

    2009-02-01

    Regional Aspects of Climate-Terrestrial-Hydrologic Interactions in Non-boreal Eastern Europe; Odessa, Ukraine, 23-28 August 2008; Ecosystems in Eastern Europe, in particular environments such as grasslands and semiarid regions, have undergone significant changes during the entire twentieth century due to warming climate and socioeconomic impacts. As a result, the biome boundaries between forests and steppes and between steppes and semideserts have become increasingly volatile, with dramatic changes in phenology and land fertility. Compounding these problems is a dense rural population engaging in intense land use, a population that suffers socioeconomic hardships resulting from recent and still unsettled political changes. Such political problems combined with a lack of local funds have limited the amount of observational data collected in Eastern Europe, leaving climate modelers unable to validate regional climate projections.

  6. Yakima Fisheries Project : Final Environmental Impact Statement.

    SciTech Connect

    United States. Bonneville Power Administration; Washington . Dept. of Fish and Wildlife; Confederated Tribes and Bands of the Yakama Nation, Washington.

    1996-01-01

    BPA proposes to fund several fishery-related activities in the Yakima River Basin. These activities, known as the Yakima Fisheries Project (YFP), would be jointly managed by the State of Washington and the Yakima Indian Nation. The YFP is included in the Northwest Power Planning Council`s (Council`s) fish and wildlife program. The Council selected the Yakima River system for attention because fisheries resources are severely reduced from historical levels and because there is a significant potential for enhancement of these resources. BPA`s proposed action is to fund (1) information gathering on the implementation of supplementation techniques and on feasibility of reintroducing coho salmon in an environment where native populations have become extinct; (2) research activities based on continuous assessment, feedback and improvement of research design and activities ({open_quotes}adaptive management{close_quotes}); and (3) die construction, operation, and maintenance of facilities for supplementing populations of upper Yakima spring chinook salmon. Examined in addition to No Action are two alternatives for action: (1) supplementation of depressed natural populations of upper Yakima spring chinook and (2) that same supplementation plus a study to determine the feasibility of reestablishing naturally spawning population and a significant fall fishery for coho in the Yakima Basin. Alternative 2 is the preferred action. A central hatchery would be built for either alternative, as well as three sites with six raceways each for acclimation and release of spring chinook smolts. Major issues examined in the Revised Draft EIS include potential impacts of the project on genetic and ecological resources of existing fish populations, on water quality and quantity, on threatened and endangered species listed under the Endangered Species Act, and on the recreational fishery.

  7. Environmental projects. Volume 16: Waste minimization assessment

    NASA Technical Reports Server (NTRS)

    1994-01-01

    The Goldstone Deep Space Communications Complex (GDSCC), located in the MoJave Desert, is part of the National Aeronautics and Space Administration's (NASA's) Deep Space Network (DSN), the world's largest and most sensitive scientific telecommunications and radio navigation network. The Goldstone Complex is operated for NASA by the Jet Propulsion Laboratory. At present, activities at the GDSCC support the operation of nine parabolic dish antennas situated at five separate locations known as 'sites.' Each of the five sites at the GDSCC has one or more antennas, called 'Deep Space Stations' (DSS's). In the course of operation of these DSS's, various hazardous and non-hazardous wastes are generated. In 1992, JPL retained Kleinfelder, Inc., San Diego, California, to quantify the various streams of hazardous and non-hazardous wastes generated at the GDSCC. In June 1992, Kleinfelder, Inc., submitted a report to JPL entitled 'Waste Minimization Assessment.' This present volume is a JPL-expanded version of the Kleinfelder, Inc. report. The 'Waste Minimization Assessment' report did not find any deficiencies in the various waste-management programs now practiced at the GDSCC, and it found that these programs are being carried out in accordance with environmental rules and regulations.

  8. The Effect of Environmental Science Projects on Students' Environmental Knowledge and Science Attitudes

    ERIC Educational Resources Information Center

    Al-Balushi, Sulaiman M.; Al-Aamri, Shamsa S.

    2014-01-01

    The current study explores the effectiveness of involving students in environmental science projects for their environmental knowledge and attitudes towards science. The study design is a quasi-experimental pre-post control group design. The sample was 62 11th-grade female students studying at a public school in Oman. The sample was divided into…

  9. Ashtabula Environmental Management Project Main Extrusion Plant Demolition Project. Demolition of the Ashtabula Environmental Management Project's Main Extrusion Plant

    SciTech Connect

    Colborn, Kurt; Johnson, Kathryn K.

    2003-02-27

    Significant progress was made this year toward closure of the Department of Energy's Ashtabula Environmental Management Project (AEMP) with the demolition of the 9-building Main Extrusion Plant Complex. The 44,000 square foot building complex formerly housed uranium extrusion facilities and equipment. At the start of the project in October of 2001, the buildings still contained a RCRA Part B storage area, operating mixed waste treatment facilities, active waste shredding and compacting process areas, and a state EPA permitted HEPA ventilation system. This paper presents a discussion of the multidisciplinary effort to bring the building to a safe shutdown condition in just six months, including relocation of existing process areas, utility isolation, and preliminary decontamination. Also discussed is the demolition strategy in which portions of the facility remained active while demolition was proceeding in other areas. Other details of the technical approach to the demolition are also discussed, including innovative techniques for demolition, galbestos removal, contamination control, and waste minimization. These techniques contributed to the early completion of demolition in July of 2002, fully two months ahead of schedule and $1.5 million under budget.

  10. Near-facility environmental monitoring quality assurance project plan

    SciTech Connect

    McKinney, S.M.

    1997-11-24

    This Quality Assurance Project Plan addresses the quality assurance requirements for the activities associated with the preoperational and near facility environmental monitoring performed by Waste Management Federal Services, Inc., Northwest Operations and supersedes WHC-EP-0538-2. This plan applies to all sampling and monitoring activities performed by waste management Federal Services, Inc., Northwest Operations in implementing facility environmental monitoring at the Hanford Site.

  11. Hanford Environmental Dose Reconstruction Project: Monthly report, May 1989

    SciTech Connect

    Dennis, B.S.

    1989-01-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by Pacific Northwest Laboratory under the direction of independent Technical Steering Panel. The Technical Steering Panel consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included among the members are appointed technical members representing the States of Oregon and Washington, cultural and technical experts nominated by the Indian tribes in the region, and an individual representing the public.

  12. Uranium Mill Tailings Remedial Action Project. 1995 Environmental Report

    SciTech Connect

    1996-06-01

    In accordance with U.S. Department of Energy (DOE) Order 23 1. 1, Environment, Safety and Health Reporting, the DOE prepares an annual report to document the activities of the Uranium Mill Tailings Remedial Action (UMTRA) Project environmental monitoring program. This monitoring must comply with appropriate laws, regulations, and standards, and it must identify apparent and meaningful trends in monitoring results. The results of all monitoring activities must be communicated to the public. The UMTRA Project has prepared annual environmental reports to the public since 1989.

  13. Environmental assessment, expanded Ponnequin wind energy project, Weld County, Colorado

    SciTech Connect

    1999-02-01

    The US Department of Energy (DOE) has considered a proposal from the State of Colorado, Office of Energy Conservation (OEC), for funding construction of the Expanded Ponnequin Wind Project in Weld County, Colorado. OEC plans to enter into a contracting arrangement with Public Service Company of Colorado (PSCo) for the completion of these activities. PSCo, along with its subcontractors and business partners, are jointly developing the Expanded Ponnequin Wind Project. The purpose of this Final Environmental Assessment (EA) is to provide DOE and the public with information on potential environmental impacts associated with the Expanded Ponnequin Wind Energy Project. This EA, and public comments received on it, were used in DOE`s deliberations on whether to release funding for the expanded project under the Commercialization Ventures Program.

  14. Networking environmental metadata: a pilot project for the Mediterranean Region

    NASA Astrophysics Data System (ADS)

    Bonora, N.; Benito, M.; Abou El-Magd, I.; Mazzetti, P.; Ndong, C.

    2012-04-01

    To better exploit any environmental dataset it is necessary to provide detailed information (metadata) capable to furnish the best data description. Operating environmental data and information networking requires the long-term investment of financial and human resources. As these resources are scarce, ensuring sustainability can be a struggle. Then, to use more effectively human and economic resources and to avoid duplication, it is essential to test existing models and, where appropriate, replicate strategies and experiences. For the above reasons, it has been programmed to pilot a project to implement and test a metadata catalogue's networking, involving Countries afferent the Mediterranean Region, to demonstrate that the adoption of open source and free software and international interoperability standards can contribute to the alignment of I&TC resources to achieve environmental information sharing. This pilot, planned in the frame of the EGIDA FP7 European Project, aims to support the implementation of a replication methodology for the establishment of national/regional environmental information nodes on the bases of the System of Systems architecture concept, to support the exchange of environmental information in the frame of the Barcelona Convention and to incept a Mediterranean scale joint contribution to GEOSS focusing on partnership, infrastructures and products. To establish the partnership and to conduce interoperability tests, this pilot project build on the Info-RAC (Information and Communication Activity Centre of the United Nation Environmental Programme - Mediterranean Action Plan) and GEO (Group on Earth Observations) networks.

  15. HEDR model validation plan. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Napier, B.A.; Gilbert, R.O.; Simpson, J.C.; Ramsdell, J.V. Jr.; Thiede, M.E.; Walters, W.H.

    1993-06-01

    The Hanford Environmental Dose Reconstruction (HEDR) Project has developed a set of computational ``tools`` for estimating the possible radiation dose that individuals may have received from past Hanford Site operations. This document describes the planned activities to ``validate`` these tools. In the sense of the HEDR Project, ``validation`` is a process carried out by comparing computational model predictions with field observations and experimental measurements that are independent of those used to develop the model.

  16. Lower Columbia River Terminal Fisheries Research Project : Final Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration.

    1995-04-01

    This notice announces BPA`S`s decision to fund the Oregon Department of Fish and Wildlife (ODFW), the Washington Department of Fish and Wildlife (WDFW), and the Clatsop Economic Development Committee for the Lower Columbia River Terminal Fisheries Research Project (Project). The Project will continue the testing of various species/stocks, rearing regimes, and harvest options for terminal fisheries, as a means to increase lower river sport and commercial harvest of hatchery fish, while providing both greater protection of weaker wild stocks and increasing the return of upriver salmon runs to potential Zone 6 Treaty fisheries. The Project involves relocating hatchery smolts to new, additional pen locations in three bays/sloughs in the lower Columbia River along both the Oregon and Washington sides. The sites are Blind Slough and Tongue Point in Clatsop County, Oregon, and Grays Bay/Deep River, Wahkiakum County, Washington. The smolts will be acclimated for various lengths of time in the net pens and released from these sites. The Project will expand upon an existing terminal fisheries project in Youngs Bay, Oregon. The Project may be expanded to other sites in the future, depending on the results of this initial expansion. BPA`S has determined the project is not a major Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act (NEPA) of 1969. Therefore, the preparation of an environmental impact statement is not required, and BPA`S is issuing this FONSI.

  17. West Valley Demonstration Project site environmental report, calendar year 1997

    SciTech Connect

    1998-06-01

    This report represents a single, comprehensive source of off-site and on-site environmental monitoring data collected during 1997 by environmental monitoring personnel for the West Valley Demonstration Project (WVDP), West Valley, New York. The environmental monitoring program and results are discussed in the body of this report. The monitoring data are presented in the appendices. The data collected provide an historical record of radionuclide and radiation levels from natural and manmade sources in the survey area and document the quality of the groundwater on and around the WVDP and the quality of the air and water discharged by the WVDP.

  18. West Valley Demonstration Project site environmental report, calendar year 1999

    SciTech Connect

    None Available

    2000-06-01

    This report represents a single, comprehensive source of off-site and on-site environmental monitoring data collected during 1999 by environmental monitoring personnel for the West Valley Demonstration Project (WVDP), West Valley, New York. The environmental monitoring program and results are discussed in the body of this report. The monitoring data are presented in the appendices. The data collected provide an historical record of radionuclide and radiation levels from natural and manmade sources in the survey area and document the quality of the groundwater on and around the WVDP and the quality of the air and water discharged by the WVDP.

  19. West Valley Demonstration Project site environmental report calendar year 1998

    SciTech Connect

    1999-06-01

    This report represents a single, comprehensive source of off-site and on-site environmental monitoring data collected during 1998 by environmental monitoring personnel for the West Valley Demonstration Project (WVDP), West Valley, New York. The environmental monitoring program and results are discussed in the body of this report. The monitoring data are presented in the appendices. The data collected provide an historical record of radionuclide and radiation levels from natural and manmade sources in the survey area and document the quality of the groundwater on and around the WVDP and the quality of the air and water discharged by the WVDP.

  20. SOLIDIFICATION/STABILIZATION - US ENVIRONMENTAL PROTECTION AGENCY SUPERFUND PROGRAM

    EPA Science Inventory

    This presentation outlines the Superfund program approach to site cleanup, then provides information from actual insitu and exsitu solidification/stabilization remediations to illustrate technology, equipment, field implementation, performance evaluation, cleanup specifications, ...

  1. Environmental cost of using poor decision metrics to prioritize environmental projects.

    PubMed

    Pannell, David J; Gibson, Fiona L

    2016-04-01

    Conservation decision makers commonly use project-scoring metrics that are inconsistent with theory on optimal ranking of projects. As a result, there may often be a loss of environmental benefits. We estimated the magnitudes of these losses for various metrics that deviate from theory in ways that are common in practice. These metrics included cases where relevant variables were omitted from the benefits metric, project costs were omitted, and benefits were calculated using a faulty functional form. We estimated distributions of parameters from 129 environmental projects from Australia, New Zealand, and Italy for which detailed analyses had been completed previously. The cost of using poor prioritization metrics (in terms of lost environmental values) was often high--up to 80% in the scenarios we examined. The cost in percentage terms was greater when the budget was smaller. The most costly errors were omitting information about environmental values (up to 31% loss of environmental values), omitting project costs (up to 35% loss), omitting the effectiveness of management actions (up to 9% loss), and using a weighted-additive decision metric for variables that should be multiplied (up to 23% loss). The latter 3 are errors that occur commonly in real-world decision metrics, in combination often reducing potential benefits from conservation investments by 30-50%. Uncertainty about parameter values also reduced the benefits from investments in conservation projects but often not by as much as faulty prioritization metrics. PMID:26365219

  2. 15 CFR 291.2 - Environmental integration projects.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 15 Commerce and Foreign Trade 1 2010-01-01 2010-01-01 false Environmental integration projects. 291.2 Section 291.2 Commerce and Foreign Trade Regulations Relating to Commerce and Foreign Trade NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY, DEPARTMENT OF COMMERCE NIST EXTRAMURAL PROGRAMS MANUFACTURING EXTENSION PARTNERSHIP;...

  3. Environmentally Sound Small-Scale Agricultural Projects. Guidelines for Planning.

    ERIC Educational Resources Information Center

    Mohonk Trust, New Paltz, NY.

    This publication is the first of a series of manuals that present environmental guidelines for planning and implementing ecologically sustainable projects. Attention is particularly directed to the agricultural situation and needs of developing nations. Subject areas discussed include: (1) users and uses (identifying the major purposes of the…

  4. Environmentally Responsible Aviation Project: Infrastructure Enhancements and New Capabilities

    NASA Technical Reports Server (NTRS)

    Bezos-OConnor, Gaudy M.

    2015-01-01

    This oral presentation highlights the technical investments the NASA Environmentally Responsible Aviation Project under the Integrated Systems Research Program within ARMD made during FY10-FY14 to upgrade/enhance the NASA infrastructure/testing assets and new capabilities required to mature the ERA N=2 Portfolio of airframe and propulsion technologies to TRL 5/6.

  5. Environmental Assessment Expanded Ponnequin Wind Energy Project Weld County, Colorado

    SciTech Connect

    N /A

    1999-03-02

    The U.S.Department of Energy (DOE) has considered a proposal from the State of Colorado, Office of Energy Conservation (OEC), for funding construction of the Expanded Ponnequin Wind Project in Weld County, Colorado. OEC plans to enter into a contracting arrangement with Public Service Company of Colorado (PSCO) for the completion of these activities. PSCo, along with its subcontractors and business partners, are jointly developing the Expanded Ponnequin Wind Project. DOE completed an environmental assessment of the original proposed project in August 1997. Since then, the geographic scope and the design of the project changed, necessitating additional review of the project under the National Environmental Policy Act. The project now calls for the possible construction of up to 48 wind turbines on State and private lands. PSCo and its partners have initiated construction of the project on private land in Weld County, Colorado. A substation, access road and some wind turbines have been installed. However, to date, DOE has not provided any funding for these activities. DOE, through its Commercialization Ventures Program, has solicited applications for financial assistance from state energy offices, in a teaming arrangement with private-sector organizations, for projects that will accelerate the commercialization of emerging renewable energy technologies. The Commercialization Ventures Program was established by the Renewable Energy and Energy Efficiency Technology Competitiveness Act of 1989 (P.L. 101-218) as amended by the Energy Policy Act of 1992 (P.L. 102-486). The Program seeks to assist entry into the marketplace of newly emerging renewable energy technologies, or of innovative applications of existing technologies. In short, an emerging renewable energy technology is one which has already proven viable but which has had little or no operational experience. The Program is managed by the Department of Energy, Office of Energy Efficiency and Renewable Energy. The

  6. INEL Waste and Environmental Information Integration Project approach and concepts

    SciTech Connect

    Dean, L.A.; Fairbourn, P.J.; Randall, V.C.; Riedesel, A.M.

    1994-06-01

    The Idaho National Engineering, Laboratory (INEL) Waste and Environmental Information integration Project (IWEIIP) was established in December 1993 to address issues related to INEL waste and environmental information including: Data quality; Data redundancy; Data accessibility; Data integration. This effort includes existing information, new development, and acquisition activities. Existing information may not be a database record; it may be an entire document (electronic, scanned, or hard-copy), a video clip, or a file cabinet of information. The IWEIIP will implement an effective integrated information framework to manage INEL waste and environmental information as an asset. This will improve data quality, resolve data redundancy, and increase data accessibility; therefore, providing more effective utilization of the dollars spent on waste and environmental information.

  7. Management of the Atmosphere Resource Recovery and Environmental Monitoring Project

    NASA Technical Reports Server (NTRS)

    Roman, Monsi; Perry, Jay; Howard, David

    2013-01-01

    The Advanced Exploration Systems Program's Atmosphere Resource Recovery and Environmental Monitoring (ARREM) project is working to further optimize atmosphere revitalization and environmental monitoring system architectures. This paper discusses project management strategies that tap into skill sets across multiple engineering disciplines, projects, field centers, and industry to achieve the project success. It is the project's objective to contribute to system advances that will enable sustained exploration missions beyond Lower Earth Orbit (LEO) and improve affordability by focusing on the primary goals of achieving high reliability, improving efficiency, and reducing dependence on ground-based logistics resupply. Technology demonstrations are achieved by infusing new technologies and concepts with existing developmental hardware and operating in a controlled environment simulating various crewed habitat scenarios. The ARREM project's strengths include access to a vast array of existing developmental hardware that perform all the vital atmosphere revitalization functions, exceptional test facilities to fully evaluate system performance, and a well-coordinated partnering effort among the NASA field centers and industry partners to provide the innovative expertise necessary to succeed.

  8. 78 FR 52819 - Environmental Impact Statement: Interstate 81 Viaduct Project (Onondaga County, New York)

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-08-26

    ... Federal Highway Administration Environmental Impact Statement: Interstate 81 Viaduct Project (Onondaga... the public that an Environmental Impact Statement (EIS) will be prepared for the proposed... Environmental Impact Statement (EIS) in accordance with the National Environmental Policy Act (NEPA) on...

  9. Designing of an environmental assessment algorithm for surface mining projects.

    PubMed

    Mirmohammadi, Mirsaleh; Gholamnejad, Javad; Fattahpour, Vahidoddin; Seyedsadri, Pejman; Ghorbani, Yousef

    2009-06-01

    This paper depicts the method used to quantify the environmental impact of mining activities in surface mine projects. The affected environment was broken down into thirteen components, such as Human health and immunity, Surface water, Air quality, etc. The effect of twenty impacting factors from the mining and milling activities was then calculated for each Environmental Component. Environmental assessments are often performed by using matrix methods in which one dimension of the matrix is the "Impacting Factor" and the other one is the "Environmental Components". For the presented matrix method, each Impacting Factor was first given a magnitude between -10 and 10. These factors are used to set up a matrix named Impacting Factor Matrix, whose elements represent the Impacting Factor values. The effects of each Impacting Factor on each Environmental Component were then quantified by multiplying the Impacting Factor Matrix by Weighting Factor Matrix. The elements of the weighting factors matrix reflect the effects of each Impacting Factor on each Environmental Component. The outlined method was originally developed for a mining and milling operation in Iran, but it can successfully be used for mining ventures and more general industrial activities in other countries in accordance to their environmental regulations and laws. PMID:19286301

  10. Influence of Animation-Supported Project-Based Instruction Method on Environmental Literacy and Self-Efficacy in Environmental Education

    ERIC Educational Resources Information Center

    Aslan Efe, Hulya; Yucel, Sait; Baran, Medine; Oner Sunkur, Meral

    2012-01-01

    The present study conducted to establish effective environmental education investigated the influence of the project-based environmental education method supported with computer animations and of the traditional environmental education method on students' environmental literacy and on their self-efficacy beliefs in giving environmental education.…

  11. Work plan for the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Not Available

    1989-12-01

    The primary objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that populations could have received from nuclear operations at the Hanford Site since 1944, with descriptions of uncertainties inherent in such estimates. The secondary objective is to make project records--information that HEDR staff members used to estimate radiation doses--available to the public. Preliminary dose estimates for a limited geographic area and time period, certain radionuclides, and certain populations are planned to be available in 1990; complete results are planned to be reported in 1993. Project reports and references used in the reports are available to the public in the DOE Public Reading Room in Richland, Washington. Project progress is documented in monthly reports, which are also available to the public in the DOE Public Reading Room.

  12. QA program plan plutonium stabilization and handling project W-460

    SciTech Connect

    SCHULTZ, J.W.

    1999-09-02

    This Quality Assurance Program Plan (QAPP) identifies Project Quality Assurance (QA) program requirements for all parties participating in the design, procurement, demolition, construction, installation, inspection and testing for Project W-460.

  13. Environmental benefits of Boston Harbor clean-up projects

    SciTech Connect

    Connor, M.S.; Smith, W.M. )

    1990-01-09

    The Massachusetts Water Resources Authority has undertaken one of the largest public works projects in the country to control the pollution of Boston Harbor. The project includes construction of a new primary and secondary treatment plant and sludge treatment facilities, excavation of a long ocean outfall and diffuser, and a solution to the overflow of mixed sewage and stormwater during storms; it will take over twenty years and billions of dollars to construct. A comparison of the relative costs and environmental benefits of relative costs and environmental benefits of the various construction projects, and other pollution control strategies, shows that some projects are more cost-effective than others for solving specific pollution problems. The capture and treatment of combined sewer overflow (CSO) will result in a more dramatic reduction of pathogen contamination than will completion of the primary and secondary treatment plants. Although the flow of raw sewage is intermittent and relatively small, it has high concentrations of bacteria and viruses. On the other hand, the new treatment plants will be more important in reducing toxic contamination of fish and shellfish. In summary, all the planned clean-up projects appear to be necessary to reach the goal of a swimmable, fishable Boston Harbor.

  14. Summary of Session Activities: Coordination of Environmental Education Projects

    NASA Technical Reports Server (NTRS)

    Keeler, Michael; Mahootian, Farzad

    1995-01-01

    In this session, we address four fundamental questions related to environmental fields with emphasis on education. These are: What are the goals, objectives, and practical opportunities for coordinating our projects? How can we improve awareness of, interest in, access to, and support the products of our work? How can we build relationships between projects for scientific, educational, technical, and programmatic benefit? How can we evaluate the effectiveness of coordination efforts. In this working session, we produced answers to these questions and proposed a structure for future collaboration.

  15. Validation of HEDR models. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Napier, B.A.; Simpson, J.C.; Eslinger, P.W.; Ramsdell, J.V. Jr.; Thiede, M.E.; Walters, W.H.

    1994-05-01

    The Hanford Environmental Dose Reconstruction (HEDR) Project has developed a set of computer models for estimating the possible radiation doses that individuals may have received from past Hanford Site operations. This document describes the validation of these models. In the HEDR Project, the model validation exercise consisted of comparing computational model estimates with limited historical field measurements and experimental measurements that are independent of those used to develop the models. The results of any one test do not mean that a model is valid. Rather, the collection of tests together provide a level of confidence that the HEDR models are valid.

  16. Trace Metals in Groundwater and Vadose Zone Calcite: In Situ Containment and Stabilization of Stronthium-90 and Other Divalent Metals and Radionuclides at Arid Western DOE Sites: Final Report for Award Number DE-FG07-02ER63486 to the University of Idaho (RW Smith) Environmental Management Science Program Project Number 87016

    SciTech Connect

    Smith, Robert W.; Fujita, Yoshiko

    2007-11-07

    Radionuclide and metal contaminants are present in the vadose zone and groundwater throughout the U.S. Department of Energy (DOE) energy research and weapons complex. In situ containment and stabilization of these contaminants represents a cost-effective treatment strategy that minimizes workers’ exposure to hazardous substances, does not require removal or transport of contaminants, and generally does not generate a secondary waste stream. We have investigated an in situ bioremediation approach that immobilizes radionuclides or contaminant metals (e.g., strontium-90) by their microbially facilitated co-precipitation with calcium carbonate in groundwater and vadose zone systems. Calcite, a common mineral in many aquifers and vadose zones in the arid west, can incorporate divalent metals such as strontium, cadmium, lead, and cobalt into its crystal structure by the formation of a solid solution. Collaborative research undertaken by the Idaho National Laboratory (INL), University of Idaho, and University of Toronto as part of this Environmental Management Science Program project has focused on in situ microbially-catalyzed urea hydrolysis, which results in an increase in pH, carbonate alkalinity, ammonium, calcite precipitation, and co-precipitation of divalent cations. In calcite-saturated aquifers, microbially facilitated co-precipitation with calcium carbonate represents a potential long-term contaminant sequestration mechanism. Key results of the project include: **Demonstrating the linkage between urea hydrolysis and calcite precipitation in field and laboratory experiments **Observing strontium incorporation into calcite precipitate by urea hydrolyzers with higher distribution coefficient than in abiotic **Developing and applying molecular methods for characterizing microbial urease activity in groundwater including a quantitative PCR method for enumerating ureolytic bacteria **Applying the suite of developed molecular methods to assess the feasibility of the

  17. Statistical analysis of real-time, environmental radon monitoring results at the Fernald Environmental Management Project.

    PubMed

    Liu, N; Spitz, H B; Tomczak, L

    1996-02-01

    A comprehensive real-time, environmental radon monitoring program is being conducted at the Fernald Environmental Management Project, where a large quantity of radium-bearing residues have been stored in two covered earth-bermed silos. Statistical analyses of radon measurement results were conducted to determine what impact, if any, radon emitted by the radium bearing materials contained in the silos has on the ambient radon concentration at the Fernald Environmental Management Project site. The distribution that best describes the outdoor radon monitoring data was determined before statistical analyses were conducted. Random effects associated with the selection of radon monitoring locations were accommodated by using nested and nested factorial classification models. The Fernald Environmental Management Project site was divided into four general areas according to their characteristics and functions: 1) the silo area, where the radium-bearing waste is stored; 2) the production/administration area; 3) the perimeter area, or fence-line, of the Fernald Environmental Management Project site; and 4) a background area, located approximately 13 km from the Fernald Environmental Management Project site, representing the naturally-occurring radon concentration. A total of 15 continuous, hourly readout radon monitors were installed in these 4 areas to measure the outdoor radon concentration. Measurement results from each individual monitor were found to be log-normally distributed. A series of contrast tests, which take random effects into account, were performed to compare the radon concentration between different areas of the site. These comparisons demonstrate that the radon concentrations in the production/administration area and the perimeter area are statistically equal to the natural background, whereas the silo area is significantly higher than background. The study also showed that the radon concentration in the silo area was significantly reduced after a sealant

  18. Rebaselining of the plutonium residue elimination project at Rocky Flats Environmental Technology Site

    SciTech Connect

    Sailor, W.C.; Catlett, D.S.; Burns, T.P.

    1997-03-01

    Systems Engineering and Value Engineering principles were put into practice in rebaselining the Pu Residue Stabilization and Elimination Project at the Rocky Flats Environmental Technology Site. Tradeoff studies were conducted as to how to best rebaseline the system under the new Safeguards Termination Limits (STSs) issued by the Department of Energy. Through the use of a computerized database, the means by which Stakeholder values and other high-level requirements have been included in the tradeoff studies were documented. 13 refs., 2 figs., 1 tab.

  19. Environmental Audit of the Grand Junction Projects Office

    SciTech Connect

    Not Available

    1991-08-01

    The Grand Junction Projects Office (GJPO) is located in Mesa County, Colorado, immediately south and west of the Grand Junction city limits. The US Atomic Energy Commission (AEC) established the Colorado Raw Materials Office at the present-day Grand Junction Projects Office in 1947, to aid in the development of a viable domestic uranium industry. Activities at the site included sampling uranium concentrate; pilot-plant milling research, including testing and processing of uranium ores; and operation of a uranium mill pilot plant from 1954 to 1958. The last shipment of uranium concentrate was sent from GJPO in January, 1975. Since that time the site has been utilized to support various DOE programs, such as the former National Uranium Resource Evaluation (NURE) Program, the Uranium Mill Tailings Remedial Action Project (UMTRAP), the Surplus Facilities Management Program (SFMP), and the Technical Measurements Center (TMC). All known contamination at GJPO is believed to be the result of the past uranium milling, analyses, and storage activities. Hazards associated with the wastes impounded at GJPO include surface and ground-water contamination and potential radon and gamma-radiation exposure. This report documents the results of the Baseline Environmental Audit conducted at Grand Junction Projects Office (GJPO) located in Grand Junction, Colorado. The Grand Junction Baseline Environmental Audit was conducted from May 28 to June 12, 1991, by the Office of Environmental Audit (EH-24). This Audit evaluated environmental programs and activities at GJPO, as well as GJPO activities at the State-Owned Temporary Repository. 4 figs., 12 tabs.

  20. Environmental management compliance reengineering project, FY 1997 report

    SciTech Connect

    VanVliet, J.A.; Davis, J.N.

    1997-09-01

    Through an integrated reengineering effort, the Idaho National Engineering and Environmental Laboratory (INEEL) is successfully implementing process improvements that will permit safe and compliant operations to continue during the next 5 years, even though $80 million was removed from the Environmental Management (EM) program budget. A 2-year analysis, design, and implementation project will reengineer compliance-related activities and reduce operating costs by approximately $17 million per year from Fiscal Year (FY) 1998 through 2002, while continuing to meet the INEEL`s environment, safety, and health requirements and milestone commitments. Compliance reengineer`s focus is improving processes, not avoiding full compliance with environmental, safety, and health laws. In FY 1997, compliance reengineering used a three-phase approach to analyze, design, and implement the changes that would decrease operating costs. Implementation for seven specific improvement projects was completed in FY 1997, while five projects will complete implementation in FY 1998. During FY 1998, the three-phase process will be repeated to continue reengineering the INEEL.

  1. Willow Creek Wildlife Mitigation Project. Final Environmental Assessment.

    SciTech Connect

    1995-04-01

    Today`s notice announces BPA`s proposal to fund land acquisition or acquisition of a conservation easement and a wildlife management plan to protect and enhance wildlife habitat at the Willow Creek Natural Area in Eugene, Oregon. This action would provide partial mitigation for wildlife and wildlife habitat lost by the development of Federal hydroelectric projects in the Willamette River Basin. The project is consistent with BPA`s obligations under provisions of the Pacific Northwest Electric Power Planning and Conservation Act of 1980 as outlined by the Northwest Power Planning Council`s 1994 Columbia River Basin Fish and Wildlife Program. BPA has prepared an environmental assessment (DOE/EA-1023) evaluating the proposed project. Based on the analysis in the EA, BPA has determined that the proposed action is not a major Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act (NEPA) of 1969. Therefore, the preparation of an environmental impact statement (EIS) is not required and BPA is issuing this FONSI.

  2. Tiering strategic environmental assessment and project environmental impact assessment in highway planning in Sao Paulo, Brazil

    SciTech Connect

    Sanchez, Luis E. Silva-Sanchez, Solange S.

    2008-10-15

    Constructing highways in dense urban areas is always a challenge. In Sao Paulo Metropolitan Region, heavy truck traffic contributes to clog streets and expressways alike. As part of the traffic neither originates nor head to the region, a peripheral highway has been proposed to reduce traffic problems. This project, called Rodoanel, is an expressway approximately 175 km long. The fact that the projected south and north sections would cross catchments that supply most of the metropolis water demand was strongly disputed and made the environmental permitting process particularly difficult. The agency in charge commissioned a strategic environmental assessment (SEA) of a revamped project, and called it the Rodoanel Programme. However, the SEA report failed to satisfactorily take account of significant strategic issues. Among these, the highway potential effect of inducing urban sprawl over water protection zones is the most critical issue, as it emerged later as a hurdle to project licensing. Conclusion is that, particularly where no agreed-upon framework for SEA exists, when vertical tiering with downstream project EIA is sought, then a careful scoping of strategic issues is more than necessary. If an agreement on 'what is strategic' is not reached and not recognized by influential stakeholders, then the unsettled conflicts will be transferred to project EIA. In such a context, SEA will have added another loop to the usually long road to project approval.

  3. TECHNICAL RISK RATING OF DOE ENVIRONMENTAL PROJECTS - 9153

    SciTech Connect

    Cercy, M; Ronald Fayfich, R; Steven P Schneider, S

    2008-12-12

    The U.S. Department of Energy's Office of Environmental Management (DOE-EM) was established to achieve the safe and compliant disposition of legacy wastes and facilities from defense nuclear applications. The scope of work is diverse, with projects ranging from single acquisitions to collections of projects and operations that span several decades and costs from hundreds of millions to billions US$. The need to be able to manage and understand the technical risks from the project to senior management level has been recognized as an enabler to successfully completing the mission. In 2008, DOE-EM developed the Technical Risk Rating as a new method to assist in managing technical risk based on specific criteria. The Technical Risk Rating, and the criteria used to determine the rating, provides a mechanism to foster open, meaningful communication between the Federal Project Directors and DOE-EM management concerning project technical risks. Four indicators (technical maturity, risk urgency, handling difficulty and resolution path) are used to focus attention on the issues and key aspects related to the risks. Pressing risk issues are brought to the forefront, keeping DOE-EM management informed and engaged such that they fully understand risk impact. Use of the Technical Risk Rating and criteria during reviews provides the Federal Project Directors the opportunity to openly discuss the most significant risks and assists in the management of technical risks across the portfolio of DOE-EM projects. Technical Risk Ratings can be applied to all projects in government and private industry. This paper will present the methodology and criteria for Technical Risk Ratings, and provide specific examples from DOE-EM projects.

  4. Technical Risk Rating of DOE Environmental Projects - 9153

    SciTech Connect

    Cercy, Michael; Fayfich, Ronald; Schneider, Steven

    2009-02-11

    The U.S. Department of Energy's Office of Environmental Management (DOE-EM) was established to achieve the safe and compliant disposition of legacy wastes and facilities from defense nuclear applications. The scope of work is diverse, with projects ranging from single acquisitions to collections of projects and operations that span several decades and costs from hundreds of millions to billions US$. The need to be able to manage and understand the technical risks from the project to senior management level has been recognized as an enabler to successfully completing the mission. In 2008, DOE-EM developed the Technical Risk Rating as a new method to assist in managing technical risk based on specific criteria. The Technical Risk Rating, and the criteria used to determine the rating, provides a mechanism to foster open, meaningful communication between the Federal Project Directors and DOE-EM management concerning project technical risks. Four indicators (technical maturity, risk urgency, handling difficulty and resolution path) are used to focus attention on the issues and key aspects related to the risks. Pressing risk issues are brought to the forefront, keeping DOE-EM management informed and engaged such that they fully understand risk impact. Use of the Technical Risk Rating and criteria during reviews provides the Federal Project Directors the opportunity to openly discuss the most significant risks and assists in the management of technical risks across the portfolio of DOE-EM projects. Technical Risk Ratings can be applied to all projects in government and private industry. This paper will present the methodology and criteria for Technical Risk Ratings, and provide specific examples from DOE-EM projects.

  5. Hellsgate Winter Range : Wildlife Mitigation Project. Final Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration.

    1995-03-01

    Bonneville Power Administration (BPA) proposes to fund the Hellsgate Winter Range Wildlife Mitigation Project (Project) in a cooperative effort with the Colville Confederated Tribes and the Bureau of Indian Affairs (BIA). The proposed action would allow the sponsors to secure property and conduct wildlife management activities within the boundaries of the Colville Indian Reservation. This Final Environmental Assessment (EA) examines the potential environmental effects of acquiring and managing property for wildlife and wildlife habitat within a large project area. This area consists of several separated land parcels, of which 2,000 hectares (4,943 acres) have been purchased by BPA and an additional 4,640 hectares (11,466 acres) have been identified by the Colville Confederated Tribes for inclusion in the Project. Four proposed activities (habitat protection, habitat enhancement, operation and maintenance, and monitoring and evaluation) are analyzed. The proposed action is intended to meet the need for mitigation of wildlife and wildlife habitat that was adversely affected by the construction of Grand Coulee and Chief Joseph Dams and their reservoirs.

  6. Estimation of food consumption. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Callaway, J.M. Jr.

    1992-04-01

    The research reported in this document was conducted as a part of the Hanford Environmental Dose Reconstruction (HEDR) Project. The objective of the HEDR Project is to estimate the radiation doses that people could have received from operations at the Hanford Site. Information required to estimate these doses includes estimates of the amounts of potentially contaminated foods that individuals in the region consumed during the study period. In that general framework, the objective of the Food Consumption Task was to develop a capability to provide information about the parameters of the distribution(s) of daily food consumption for representative groups in the population for selected years during the study period. This report describes the methods and data used to estimate food consumption and presents the results developed for Phase I of the HEDR Project.

  7. Phase 1 of the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Not Available

    1990-07-20

    This report summarizes the water pathway portion of the first phase of the Hanford Environmental Dose Reconstruction (HEDR) Project, conducted by Battelle staff at the Pacific Northwest Laboratory under the direction of an independent Technical Steering Panel. The HEDR Project is estimating radiation doses that could have been received by the public from the Department of Energy's Hanford Site, in southeastern Washington State. Phase 1 of the water-pathway dose reconstruction sought to determine whether dose estimates could be calculated for populations in the area from above the Hanford Site at Priest Rapids Dam to below the site at McNary Dam from January 1964 to December 1966. Of the potential sources of radionuclides from the river, fish consumption was the most important. Later phases of the HEDR Project will address dose estimates for periods other than 1964--1966 and for populations downstream of McNary Dam. 17 refs., 20 figs., 1 tab.

  8. Project Execution Plan Project 98L-EWW-460 Plutonium Stabilization and Handling DOE 98-D-453

    SciTech Connect

    MCGRATH, G.M.

    2000-06-21

    This Project Execution Plan (PEP) describes the management methods and responsibilities of the project participants. Project W-460 is sufficiently large to warrant a stand alone PEP. This project specific PEP describes the relationships and responsibilities of the project team and identifies the technical, schedule, and cost baselines that have been established for the project. The Department of Energy (DOE), Hanford Works (Hanford), at Richland, Wa. currently does not have a system capable of stabilizing or packaging large quantities of plutonium-bearing solids to meet DOE technical standard DOE-STD-3013-99. This project will allow Hanford to meet this standard by installing stabilization and packaging equipment (SPE). The SPE is capable of stabilizing and packaging the current inventory of greater than 30 percent plutonium-bearing materials currently stored in the Plutonium Finishing Plant's (PFP) vaults into 3013 storage containers. The scope of this project is to procure and install the SPE via a Hanford contract and coordination with the Savannah River Site. In addition, the project will modify PFP vaults and upgrade the PFP Laboratory measurement systems. The Facility infrastructure will be modified to support the new SPE system and the new standardized storage container configuration.

  9. Project Execution Plan Project 98L-EWW-460 Plutonium Stabilization and Handling DOE 98-D-453

    SciTech Connect

    HOLSTEIN, W.A.

    1999-08-01

    This Project Execution Plan (PEP) describes the management methods and responsibilities of the project participants. Project W-460 is sufficiently large to warrant a stand alone PEP. This project specific PEP describes the relationships and responsibilities of the project team and identifies the technical, schedule, and cost baselines that have been established for the project. The Department of Energy (DOE), Hanford Works (Hanford), at Richland Wa. currently does not have a system capable of stabilizing or packaging large quantities of plutonium-bearing solids to meet DOE technical standard DOE-STD-3013-96. This project will allow Hanford to meet this standard by installing stabilization and packaging equipment (SPE). The SPE is capable of stabilizing and packaging the current inventory of greater than 50 percent plutonium-bearing materials currently stored in the Plutonium Finishing Plant's (PFP) vaults into 3013 storage containers. The scope of this project is to procure and install the SPE via a Hanford contract and coordination with the Savannah River Site. In addition, the project will modify PFP vaults and upgrade the PFP Laboratory measurement systems. The Facility infrastructure will be modified to support the new SPE system and the new standardized storage container configuration.

  10. Environmental monitoring and assessment program forest health monitoring quality assurance project plan for detection monitoring project

    SciTech Connect

    Cline, S.P.; Alexander, S.A.; Barnard, J.E.

    1995-05-01

    The Quality Assurance Project Plan (QAP) is written specifically for the Detection Minitoring project of the interagency Forest Health Monitoring (FHM) program. Sections 1 through 3 briefly explain key features of the Environmental Monitoring and Assessment Program (EMAP), the FHM program, and their interrelationship, respectively. Section 4 describes the general quality assurance (QA) requirements for the FHM Detection Monitoring project. Section 5 contains the separate QAPs for each forest condition indicator: site condition and tree growth and regeneration, tree crown condition, tree damage assessment, photosynthetically active radiation (PAR), vegetation structure, ozone bioindicator plants, and lichen communities.

  11. Final report for SNL/NM environmental drilling project

    SciTech Connect

    Wemple, R.P.; Meyer, R.D.; Staller, G.E.; Layne, R.R.

    1994-11-01

    Concern for the environment and cost reduction are driving forces for a broad effort in government and the private sector to develop new, more cost-effective technologies for characterizing, monitoring and remediating environmental sites. Secondary goals of the characterization, monitoring and remediation (CMR) activity are: minimize secondary waste generation, minimize site impact, protect water tables, and develop methods/strategies to apply new technologies. The Sandia National Laboratories (SNL) project in directional boring for CMR of waste sites with enhanced machinery from the underground utility installation industry was initiated in 1990. The project has tested a variety of prototype machinery and hardware built by the industrial partner, Charles Machine Works (CMW), and SNL at several sites (Savannah River Site (SRS), Hanford, SNL, Kirtland AFB (KAFB), CMW), successfully installed usable horizontal environmental test wells at SRS and SNL/KAFB, and functioned as a clearing house for information regarding application of existing commercial machinery to a variety of governmental and commercial sites. The project has continued to test and develop machinery in FY 94. The original goal of cost-effectiveness is being met through innovation, adaptation, and application of fundamental concepts. Secondary goals are being met via a basic philosophy of {open_quotes}cut/thrust and compact cuttings without adding large quantities of fluid{close_quotes} to an environmental problem site. This technology will be very cost-effective where applicable. Technology transfer and commercialization by CMW is ongoing and will continue into FY 95. Technology transfer to the private sector is ongoing and reflected in increasing machinery sales to environmental contractors. Education of regulatory agencies resulting in restructuring of appropriate regulatory standards for specification of the horizontal drilling techniques continues to be a long-range goal.

  12. Environmental assessment of USAID housing projects in the Russian Federation

    SciTech Connect

    Loran, B.; Miller, C.

    1995-12-01

    Parsons was selected by the United States Agency for International Development (USAID) as the general contractor for construction management for the construction of 2,500 housing units within the Russian Federation. These housing units, to be occupied by Russian officers returning from the Baltic States, are under construction on 15 sites, selected from an initial list of 200, based on habitability, capability of successful final construction. Cost meeting USAID guidelines, and impacts on the environment. USAID fulfilled NEPA requirements by preparing, with assistance of Parsons Engineering Science, a Programmatic Environmental Assessment and 15 site specific Environmental Assessments for the project. The sites were scattered over the entire Russian Federation west of the Ural Mountains. The site offerors completed an environmental checklist covering a broad range of possible impacts. Significant environmental issues and concerns were further identified during scoping meetings held at the site locations. The most important issues discussed were: soil contamination; gaseous, liquid, and solid pollutants to which the site may be exposed; incompatible adjacent land uses; ready access to utilities and social services; and socioeconomic situation favorable to resettlement of Russian military officers. No major environmental issues or concerns were identified for the 15 selected sites. Certificates indicating the absence of chemical and radiological surface and subsurface contamination at the proposed sites were provided by the local environmental officers. Polynuclear aromatic hydrocarbons were found present at one of the sites considered in a preliminary selection, and later rejected due to the failure of contractual negotiations. The environmental assessments included mitigation and monitoring measures for construction and operation (occupancy) impacts.

  13. Interim report for SNL/NM environmental drilling project

    SciTech Connect

    Wemple, R.P.; Meyer, R.D.; Layne, R.R.

    1994-02-01

    Concern for the environment and cost reduction are the driving forces for a broad effort in government and the private sector to develop new, more cost-effective technologies for characterizing, monitoring and remediating environmental sites. Secondary goals of the characterization, monitoring and remediation (CMR) activity are: minimize secondary waste generation, minimize site impact, protect water tables, and develop methods/strategies to apply new technologies. The Sandia National Laboratories (SNL) project in directional boring for CMR of waste sites with enhanced machinery from the underground utility installation industry was initiated in 1990. Preliminary activities included surveying the directional drilling access needs of various DOE sites, identifying an existing class of machinery that could be enhanced for environmental work through development, and establishing a mutually beneficial working relationship with an industry partner. Since that time the project has tested a variety of prototype machinery and hardware built by the industrial partner, and SNL. The project continues to test and develop the machinery and technique refinements needed for future applications at DOE, DOD, and private sector sites. The original goal of cost-effectiveness is being met through innovation, adaptation, and application of fundamental concepts. Secondary goals are being met via a basic philosophy of ``cut/thrust and compact cuttings without adding large quantities of fluid`` to an environmental problem site. Technology transfer to the private sector is ongoing and ultimately should result in commercial availability of the machinery. Education of regulatory agencies resulting in restructuring appropriate regulatory standards for specification of the horizontal drilling techniques will be a final project goal.

  14. Environmental impacts of dispersed development from federal infrastructure projects.

    PubMed

    Southerland, Mark T

    2004-06-01

    Dispersed development, also referred to as urban growth or sprawl, is a pattern of low-density development spread over previously rural landscapes. Such growth can result in adverse impacts to air quality, water quality, human health, aquatic and terrestrial ecosystems, agricultural land, military training areas, water supply and wastewater treatment, recreational resources, viewscapes, and cultural resources. The U.S. Environmental Protection Agency (U.S. EPA) is charged with protecting public health and the environment, which includes consideration of impacts from dispersed development. Specifically, because federal infrastructure projects can affect the progress of dispersed development, the secondary impacts resulting from it must be assessed in documents prepared under the National Environmental Policy Act (NEPA). The Council on Environmental Quality (CEQ) has oversight for NEPA and Section 309 of the Clean Air Act requires that U.S. EPA review and comment on federal agency NEPA documents. The adverse effects of dispersed development can be induced by federal infrastructure projects including transportation, built infrastructure, modifications in natural infrastructure, public land conversion and redevelopment of properties, construction of federal facilities, and large traffic or major growth generation developments requiring federal permits. This paper presents an approach that U.S. EPA reviewers and NEPA practitioners can use to provide accurate, realistic, and consistent analysis of secondary impacts of dispersed development resulting from federal infrastructure projects. It also presents 24 measures that can be used to mitigate adverse impacts from dispersed development by modifying project location and design, participating in preservation or restoration activities, or informing and supporting local communities in planning. PMID:15141453

  15. Student Project Work and Abstracts. Beaufort, North Carolina Environmental Studies Project, No. 2.

    ERIC Educational Resources Information Center

    Carteret County Board of Education, Beaufort, NC.

    This document contains reports of 11 environmental study projects conducted by junior and senior students in a North Carolina high school. Topics range from the construction of an artificial reef and a survey of seashore changes to surveys of past and present development of various facets of the county ecology. The emphasis is on student…

  16. West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2004

    SciTech Connect

    West Valley Nuclear Services Company and URS Group, Inc.

    2005-09-30

    Annual Site Environmental Report for the West Valley Demonstration Project (WVDP) for Calendar Year 2004. The report summarizes the environmental protection program at the West Valley Demonstration Project for CY 2004.

  17. Anticipated Radiological Dose to Worker for Plutonium Stabilization and Handling at PFP Project W-460

    SciTech Connect

    WEISS, E.V.

    2000-03-06

    This report provides estimates of the expected whole body and extremity radiological dose, expressed as dose equivalent (DE), to workers conducting planned plutonium (Pu) stabilization processes at the Hanford Site Plutonium Finishing Plant (PFP). The report is based on a time and motion dose study commissioned for Project W-460, Plutonium Stabilization and Handling, to provide personnel exposure estimates for construction work in the PFP storage vault area plus operation of stabilization and packaging equipment at PFP.

  18. BP Cherry Point Cogeneration Project, Draft Environmental Impact Statement

    SciTech Connect

    N /A

    2003-09-19

    BP West Coast Products, LLC (BP or the Applicant) proposes to construct and operate a nominal 720-megawatt (MW), natural-gas-fired, combined-cycle cogeneration facility next to the existing BP Cherry Point Refinery in Whatcom County, Washington. The Applicant also owns and operates the refinery, but the cogeneration facility and the refinery would be operated as separate business units. The cogeneration facility and its ancillary infrastructure would provide steam and 85 MW of electricity to meet the operating needs of the refinery and 635 MW of electrical power for local and regional consumption. The proposed cogeneration facility would be located between Ferndale and Blaine in northwestern Whatcom County, Washington. The Canadian border is approximately 8 miles north of the proposed project site. The Washington State Energy Facility Site Evaluation Council (EFSEC) has jurisdiction over the evaluation of major energy facilities including the proposed project. As such, EFSEC will recommend approval or denial of the proposed cogeneration facility to the governor of Washington after an environmental review. On June 3, 2002, the Applicant filed an Application for Site Certification (ASC No. 2002-01) with EFSEC in accordance with Washington Administrative Code (WAC) 463-42. On April 22, 2003, the Applicant submitted an amended ASC that included, among other things, a change from air to water cooling. With the submission of the ASC and in accordance with the State Environmental Policy Act (SEPA) (WAC 463-47), EFSEC is evaluating the siting of the proposed project and conducting an environmental review with this Environmental Impact Statement (EIS). Because the proposed project requires federal agency approvals and permits, this EIS is intended to meet the requirements under both SEPA and the National Environmental Policy Act (NEPA). The Bonneville Power Administration (Bonneville) and U.S. Army Corps of Engineers (Corps) also will use this EIS as part of their

  19. Environmental inactivation of Cryptosporidium parvum oocysts in waste stabilization ponds.

    PubMed

    Reinoso, Roberto; Bécares, Eloy

    2008-11-01

    The survival of Cryptosporidium parvum oocysts in a waste stabilization pond system in northwestern Spain and the effects of sunlight and the depth and type of pond on oocyst viability were evaluated using an assay based on the exclusion or inclusion of two fluorogenic vital dyes, 4',6-diamidino-2-phenylindole (DAPI) and propidium iodide (PI). All tested factors had significant effects (P < 0.01) over time on C. parvum oocyst viability. Sunlight exposure was the most influential factor for oocyst inactivation. A 40% reduction was observed after 4 days exposure to sunlight conditions compared with dark conditions. The type of pond also caused a significant reduction in C. parvum oocyst viability (P < 0.01). Inactivation rates reflected that the facultative pond was the most aggressive environment for oocysts placed both at the surface (presence of sunlight) and at the bottom (absence of sunlight) of the pond, followed by the maturation pond and the anaerobic pond. The mean inactivation rates of oocysts in the ponds ranged from 0.0159 to 0.3025 day(-1). PMID:18345476

  20. Blue Creek Winter Range : Wildlife Mitigation Project : Final Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration; United States. Bureau of Indian Affairs; Spokane Tribe of the Spokane Reservation, Washington

    1994-11-01

    Bonneville Power Administration (BPA) proposes to fund that portion of the Washington Wildlife Agreement pertaining to the Blue Creek Winter Range Wildlife Mitigation Project (Project) in a cooperative effort with the Spokane Tribe, Upper Columbia United Tribes, and the Bureau of Indian Affairs (BIA). If fully implemented, the proposed action would allow the sponsors to protect and enhance 2,631 habitat units of big game winter range and riparian shrub habitat on 2,185 hectares (5,400 acres) of Spokane Tribal trust lands, and to conduct long term wildlife management activities within the Spokane Indian Reservation project area. This Final Environmental Assessment (EA) examines the potential environmental effects of securing land and conducting wildlife habitat enhancement and long term management activities within the boundaries of the Spokane Indian Reservation. Four proposed activities (habitat protection, habitat enhancement, operation and maintenance, and monitoring and evaluation) are analyzed. The proposed action is intended to meet the need for mitigation of wildlife and wildlife habitat adversely affected by the construction of Grand Coulee Dam and its reservoir.

  1. Impact of uncertainty in economic projections for stabilization scenarios

    NASA Astrophysics Data System (ADS)

    Krakauer, N. Y.

    2008-12-01

    Scenarios for the stabilization of greenhouse gas emissions and/or atmospheric concentrations typically take economic and technological growth, and thus the 'background', no-controls emissions trajectory, as essentially given, most commonly based on one or more of the IPCC SRES scenarios. One limitation of this set of scenarios is that they postulate a rather small range of future economic growth rates, based on extrapolation from recent experience as well as assumed tendencies such as international 'convergence'. Because there is no validated theoretical or empirical method to reliably predict long-term (decade to century) changes in the size and composition of the world economy, the uncertainty in economic path is large and likely understated by any measure derived from the ensemble of SRES scenarios. Considering a wider range of economic trajectories complicates stabilization scenarios. In particular, slow economic growth would imply that future generations will be relatively less able to invest in emissions controls or adapt to detrimental impacts of climate change. I show with a simple integrated assessment model that taking into consideration the possibility of economic slowdown generally heightens the urgency of reducing greenhouse gas emissions now, rather than in future decades, for stabilizing radiative forcing or welfare damage at a given target.

  2. Environmental Project of I.E.S. Antoni Maura

    NASA Astrophysics Data System (ADS)

    Crespi Salom, Pere

    2010-05-01

    Environmental Project of I.E.S. Antoni Maura Author(s): Pere Crespí i Salom Teacher of Department of Biology and Geology and Environmental Coordinator (2009-2010) from I.E.S. Antoni Maura . Mallorca. Illes Balears. Spain Teachers participating in the project : Myriam Fuentes Milani, Olga Ballester Nebot, Antoni Salom Ruiz, Julio René Loayza Casanova, Puy Aguirre Rémirez, Yolanda Martínez Laserna, Jaume Puppo Lama, Carme Arrom , Dolors Aguiló Segura, Marga Ordinas Boter, Angel Fernàndez Albertí , Immaculada Suau López, Antònia Florit Torrandell, Isabel Mateu Arcos, Román Piña Valls i Pere Crespí Salom. Our institute takes part since 2004 in adapting environmentally the schools in the Balearics which consists of developing activities which aim is that both teachers and students acquire habits so as to apply to their ordinary lives though different participative commissions ( 10-15 teachers): 1st commission: recycling and reusing materials. Enough bins in the classrooms and floors: yellow for plastic, blue for paper, and green for the other. We tend to use recycled materials in different celebrations such as Carnival, Christmas, Saint Jordi and Environmental day. We also organise workshops for the teachers to develop afterwards with the students and nature of environmental exposures. 2nd commission: Scatter information ( MonMaura, Maurifull, Green window and website).Throughout different means we inform the teachers and students about all the school activities and where to consult.( www.iesantonimaura.net, Playful area , environmental project ). 3rd commission: Reusing text books.( there is a students service of borrowing books and giving them back at the end of the school year if the book is in good use.) 4th commission: Improving the school surroundings, the back garden and garden with native plants. Department of Biology and Geology is responsible for caring for an organic garden and in turn improve the center's garden with native plants within the

  3. An overview of the Environmental Monitoring Computer Automation Project

    SciTech Connect

    Johnson, S.M.; Lorenz, R.

    1992-12-31

    The Savannah River Site (SRS) was bulk to produce plutonium and tritium for national defense. As a result of site operations, routine and accidental releases of radionuclides have occurred. The effects these releases have on the k>cal population and environment are of concern to the Department of Energy (DOE) and SRS personnel. Each year, approximately 40,000 environmental samples are collected. The quality of the samples, analytical methods and results obtained are important to site personnel. The Environmental Monitoring Computer Automation Project (EMCAP) was developed to better manage scheduling, log-in, tracking, analytical results, and report generation. EMCAP can be viewed as a custom Laboratory Information Management System (LIMS) with the ability to schedule samples, generate reports, and query data. The purpose of this paper is to give an overview of the SRS environmental monitoring program, describe the development of EMCAP software and hardware, discuss the different software modules, show how EMCAP improved the Environmental Monitoring Section program, and examine the future of EMCAP at SRS.

  4. An overview of the Environmental Monitoring Computer Automation Project

    SciTech Connect

    Johnson, S.M.; Lorenz, R.

    1992-01-01

    The Savannah River Site (SRS) was bulk to produce plutonium and tritium for national defense. As a result of site operations, routine and accidental releases of radionuclides have occurred. The effects these releases have on the k>cal population and environment are of concern to the Department of Energy (DOE) and SRS personnel. Each year, approximately 40,000 environmental samples are collected. The quality of the samples, analytical methods and results obtained are important to site personnel. The Environmental Monitoring Computer Automation Project (EMCAP) was developed to better manage scheduling, log-in, tracking, analytical results, and report generation. EMCAP can be viewed as a custom Laboratory Information Management System (LIMS) with the ability to schedule samples, generate reports, and query data. The purpose of this paper is to give an overview of the SRS environmental monitoring program, describe the development of EMCAP software and hardware, discuss the different software modules, show how EMCAP improved the Environmental Monitoring Section program, and examine the future of EMCAP at SRS.

  5. Patterns of developmental stability of Chrysopa perla L. (Neuroptera: Chrysopidae) in response to environmental pollution

    SciTech Connect

    Clarke, G.M. )

    1993-12-01

    The level of developmental stability of Chrysopa perla L. (Neuroptera: Chrysopidae) collected from control and contaminated sites in the vicinity of an agrochemical manufacturing facility was assessed using fluctuating asymmetry and phenodeviant analysis. There were no significant differences in the level of asymmetry between control and contaminated sites for four characters. The number of phenodeviants for two characters was significantly greater at sites located in close proximity to the facility compared with a control site. Results are discussed with reference to the relationship between asymmetry and phenodeviants as indicators of stability and the use of development stability as a means of assessing environmental quality.

  6. Conceptual design report, plutonium stabilization and handling,project W-460

    SciTech Connect

    Weiss, E.V.

    1997-03-06

    Project W-460, Plutonium Stabilization and Handling, encompasses procurement and installation of a Stabilization and Packaging System (SPS) to oxidize and package for long term storage remaining plutonium-bearing special nuclear materials currently in inventory at the Plutonium Finishing Plant (PFP), and modification of vault equipment to allow storage of resulting packages of stabilized SNM for up to fifty years. This Conceptual Design Report (CDR) provides conceptual design details for the vault modification, site preparation and site interface with the purchased SPS. Two concepts are described for vault configuration; acceleration of this phase of the project did not allow completion of analysis which would clearly identify a preferred approach.

  7. Influence of environmental conditions on the stability of oil in water emulsions containing droplets stabilized by lecithin-chitosan membranes.

    PubMed

    Ogawa, Satoshi; Decker, Eric A; McClements, D Julian

    2003-08-27

    Oil-in-water emulsions containing cationic droplets stabilized by lecithin-chitosan membranes were produced using a two-stage process. A primary emulsion containing anionic lecithin-coated droplets was prepared by homogenizing oil and emulsifier solution using a high-pressure valve homogenizer (5 wt % corn oil, 1 wt % lecithin, 100 mM acetic acid, pH 3.0). A secondary emulsion containing cationic lecithin-chitosan-coated droplets was formed by diluting the primary emulsion with an aqueous chitosan solution (1 wt % corn oil, 0.2 wt % lecithin, 100 mM acetic acid, and 0.036 wt % chitosan). The stabilities of the primary and secondary emulsions with the same oil concentration to thermal processing, freeze-thaw cycling, high calcium chloride concentrations, and lipid oxidation were determined. The results showed that the secondary emulsions had better stability to droplet aggregation during thermal processing (30-90 degrees C for 30 min), freeze-thaw cycling (-10 degrees C for 22 h/30 degrees C for 2 h), and high calcium chloride contents (stability to environmental stresses. PMID:12926908

  8. Environmental and Mechanical Stability of Environmental Barrier Coated SA Tyrannohex SiC Composites Under Simulated Turbine Engine Environments

    NASA Technical Reports Server (NTRS)

    Zhu, Dongming; Halbig, Michael Charles; Sing, Mrityunjay

    2014-01-01

    The environmental stability and thermal gradient cyclic durability performance of SA Tyrannohex composites were investigated for turbine engine component applications. The work has been focused on investigating the combustion rig recession, cyclic thermal stress resistance and thermomechanical low cycle fatigue of uncoated and environmental barrier coated Tyrannohex SiC SA composites in simulated turbine engine combustion water vapor, thermal gradients, and mechanical loading conditions. Flexural strength degradations have been evaluated, and the upper limits of operating temperature conditions for the SA composite material systems are discussed based on the experimental results.

  9. Exploiting environmental torques for attitude control and determination of spin stabilized satellites

    NASA Technical Reports Server (NTRS)

    Gluck, R.

    1974-01-01

    Design techniques are presented which exploit environmental torques for attitude control and determination of spin stabilized satellites. The techniques are applicable to satellite missions where the dominant environmental torques are well understood and lend themselves to accurate analytical modeling. The techniques were applied to the Particles and Fields subsatellites of the Apollo 15 and 16 spacecraft and the flight results show good agreement with the attitude determination estimates obtained.

  10. The Rocky Flats Environmental Technology Site beryllium characterization project

    SciTech Connect

    Morrell, D.M.; Miller, J.R.; Allen, D.F.

    1999-06-01

    A site beryllium characterization project was completed at the Rocky Flats Environmental Technology Site (RFETS) in 1997. Information from historical reviews, previous sampling surveys, and a new sampling survey were used to establish a more comprehensive understanding of the locations and levels of beryllium contamination in 35 buildings. A feature of the sampling strategy was to test if process knowledge was a good predictor of where beryllium contamination could be found. Results revealed that this technique was effective at identifying where surface contamination levels might exceed the RFETS smear control level but that it was not effective in identifying where low concentrations of beryllium might be found.

  11. [Nuclear energy and environment: review of the IAEA environmental projects].

    PubMed

    Fesenko, S; Fogt, G

    2012-01-01

    The review of the environmental projects of the International Atomic Energy Agency is presented. Basic IAEA documents intended to protect humans and the Environment are considered and their main features are discussed. Some challenging issues in the area of protection of the Environment and man, including the impact of nuclear facilities on the environment, radioactive waste management, and remediation of the areas affected by radiological accidents, nuclear testing and sites of nuclear facilities are also discussed. The need to maintain the existing knowledge in radioecology and protection of the environment is emphasised. PMID:23516895

  12. Environmental information volume: Liquid Phase Methanol (LPMEOH{trademark}) project

    SciTech Connect

    1996-05-01

    The purpose of this project is to demonstrate the commercial viability of the Liquid Phase Methanol Process using coal-derived synthesis gas, a mixture of hydrogen and carbon monoxide. This report describes the proposed actions, alternative to the proposed action, the existing environment at the coal gasification plant at Kingsport, Tennessee, environmental impacts, regulatory requirements, offsite fuel testing, and DME addition to methanol production. Appendices include the air permit application, solid waste permits, water permit, existing air permits, agency correspondence, and Eastman and Air Products literature.

  13. HEDR modeling approach. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Shipler, D.B.; Napier, B.A.

    1992-07-01

    This report details the conceptual approaches to be used in calculating radiation doses to individuals throughout the various periods of operations at the Hanford Site. The report considers the major environmental transport pathways--atmospheric, surface water, and ground water--and projects and appropriate modeling technique for each. The modeling sequence chosen for each pathway depends on the available data on doses, the degree of confidence justified by such existing data, and the level of sophistication deemed appropriate for the particular pathway and time period being considered.

  14. Environmental Restoration Disposal Facility (Project W-296) Safety Assessment

    SciTech Connect

    Armstrong, D.L.

    1994-08-01

    This Safety Assessment is based on information derived from the Conceptual Design Report for the Environmental Restoration Disposal Facility (DOE/RL 1994) and ancillary documentation developed during the conceptual design phase of Project W-296. The Safety Assessment has been prepared to support the Solid Waste Burial Ground Interim Safety Basis document. The purpose of the Safety Assessment is to provide an evaluation of the design to determine if the process, as proposed, will comply with US Department of Energy (DOE) Limits for radioactive and hazardous material exposures and be acceptable from an overall health and safety standpoint. The evaluation considered affects on the worker, onsite personnel, the public, and the environment.

  15. Idaho National Engineering Laboratory Sewer System Upgrade Project. Environmental Assessment

    SciTech Connect

    Not Available

    1994-04-01

    The Department of Energy (DOE) has prepared an environmental assessment for a proposed Sewer System Upgrade Project at the Idaho National Engineering Laboratory (INEL) near Idaho Falls, Idaho. The proposed action would include activities conducted at the Central Facilities Area, Test Reactor Area, and the Containment Test Facility at the Test Area North at INEL. The proposed action would consist of replacing or remodeling the existing sewage treatment plants at the Central Facilities Area, Test Reactor Area, and Containment Test Facility. Also, a new sewage testing laboratory would be constructed at the Central Facilities Area. Finally, the proposed action would include replacing, repairing, and/or adding sewer lines in areas where needed.

  16. Enhancement of stability of various nZVI suspensions used in groundwater remediation with environmentally friendly organic stabilizers

    NASA Astrophysics Data System (ADS)

    Schmid, Doris; Wagner, Stephan; Velimirović, Milica; Laumann, Susanne; Micić, Vesna; Hofmann, Thilo

    2014-05-01

    The use of nanoscale zero-valent iron (nZVI) particles for in situ remediation of polluted soil and groundwater has been shown as one of the most promising techniques [1]. The success of this technology depends on the mobility, reactivity, and longevity of nZVI particles. The mobility of nZVI particles depends on the properties of the single particles, stability of the particle suspension, and the aquifer material [1,2]. In order to enhance the mobility of nZVI, the mobility-decisive properties of the nZVI particles in suspension such as concentration, size distribution, surface charge, and sedimentation rate have to be investigated and optimized. Previous studies showed that pristine nZVI particles aggregate rapidly in water, reducing the particles radius of influence after injection [3]. In order to prevent aggregation and sedimentation of the nZVI particles, and consequently improve the stability of nZVI suspension and therefore the mobility of the nZVI particles, surface stabilizers can be used to provide electrostatic repulsion and steric or electrosteric stabilization [3,4]. The objective of this lab-scale study is to investigate the potential for enhancing the stability of different nZVI suspensions by means of environmentally friendly organic stabilizers, including carboxymethyl cellulose, pectin, alginate, xanthan, and guar gum. The different nZVI particles used included pristine and polyacrylic acid-coated nZVI particles provided in suspension (Nanofer 25 and Nanofer 25S, respectively, NANOIRON s.r.o., Czech Republic), air-stable nZVI particles (Nanofer Star, (NANOIRON s.r.o., Czech Republic), and milled iron flakes (UVR-FIA, Germany). In order to study the enhancement of nZVI stability (1 g L-1 total iron) different concentrations of organic stabilizers (1-20 wt.%) were applied in these nZVI suspensions. Each nZVI suspension was freshly prepared and treated for 10 minutes with Ultra-Turrax (15 000 rpm) and 10 minutes ultrasonic bath prior to

  17. Accelerated aging studies and environmental stability of prototype tamper tapes

    SciTech Connect

    Wright, B.W.; Wright, C.W.; Bunk, A.R.

    1995-05-01

    This report describes the results of accelerated aging experiments (weathering) conducted on prototype tamper tapes bonded to a variety of surface materials. The prototype tamper tapes were based on the patented Confirm{reg_sign} tamper-indicating technology developed and produced by 3M Company. Tamper tapes bonded to surfaces using pressure sensitive adhesive (PSA) and four rapid-set adhesives were evaluated. The configurations of the PSA-bonded tamper tapes were 1.27-cm-wide Confirm{reg_sign} 1700 windows with vinyl underlay and 2.54-cm-wide Confirm{reg_sign} 1700 windows with vinyl and polyester underlays. The configurations of the rapid-set adhesive-bonded tamper tapes were 2.54-cm-wide Confirm{reg_sign} (1700, 1500 with and without primer, and 1300) windows with vinyl underlay. Surfaces used for bonding included aluminum, steel, stainless steel, Kevlar{reg_sign}, brass, copper, fiberglass/resin with and without gel coat, polyurethane-painted steel, acrylonitrile:butadiene:styrene plastic, polyester fiberglass board, Lexan polycarbonate, and cedar wood. Weathering conditions included a QUV cabinet (ultraviolet light at 60{degrees}C, condensing humidity at 40{degrees}C), a thermal cycling cabinet (-18{degrees}C to 46{degrees}C), a Weather-O-Meter (Xenon lamp), and exposure outdoors in Daytona Beach, Florida. Environmental aging exposures lasted from 7 weeks to 5 months. After exposure, the tamper tapes were visually examined and tested for transfer resistance. Tamper tapes were also exposed to a variety of chemical liquids (including organic solvents, acids, bases, and oxidizing liquids) to determine chemical resistance and to sand to determine abrasion resistance.

  18. User instructions for the DESCARTES environmental accumulation code. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Miley, T.B.; Eslinger, P.W.; Nichols, W.E.; Lessor, K.S.; Ouderkirk, S.J.

    1994-05-01

    The purpose of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation dose that individuals could have received as a result of emissions since 1944 from the Hanford Site near Richland, Washington. The HEDR Project work is conducted under several technical and administrative tasks, among which is the Environmental Pathways and Dose Estimates task. The staff on this task have developed a suite of computer codes which are used to estimate doses to individuals in the public. This document contains the user instructions for the DESCARTES (Dynamic estimates of concentrations and Accumulated Radionuclides in Terrestrial Environments) suite of codes. In addition to the DESCARTES code, this includes two air data preprocessors, a database postprocessor, and several utility routines that are used to format input data needed for DESCARTES.

  19. Environmental Assessment for the Accelerated Tank Closure Demonstration Project

    SciTech Connect

    N /A

    2003-06-16

    The U.S. Department of Energy's (DOE) Office of River Protection (ORP) needs to collect engineering and technical information on (1) the physical response and behavior of a Phase I grout fill in an actual tank, (2) field deployment of grout production equipment and (3) the conduct of component closure activities for single-shell tank (SST) 241-C-106 (C-106). Activities associated with this Accelerated Tank Closure Demonstration (ATCD) project include placement of grout in C-106 following retrieval, and associated component closure activities. The activities will provide information that will be used in determining future closure actions for the remaining SSTs and tank farms at the Hanford Site. This information may also support preparation of the Environmental Impact Statement (EIS) for Retrieval, Treatment, and Disposal of Tank Waste and Closure of Single-Shell Tanks at the Hanford Site, Richland, Washington (Tank Closure EIS). Information will be obtained from the various activities associated with the component closure activities for C-106 located in the 241-C tank farm (C tank farm) under the ''Resource Conservation and Recovery Act of 1976'' (RCRA) and the Hanford Federal Facility Agreement and Consent Order (HFFACO) (Ecology et al. 1989). The impacts of retrieving waste from C-106 are bounded by the analysis in the Tank Waste Remediation System (TWRS) EIS (DOE/EIS-0189), hereinafter referred to as the TWRS EIS. DOE has conducted and continues to conduct retrieval activities at C-106 in preparation for the ATCD Project. For major federal actions significantly affecting the quality of the human environment, the ''National Environmental Policy Act of 1969'' (NEPA) requires that federal agencies evaluate the environmental effects of their proposed and alternative actions before making decisions to take action. The President's Council on Environmental Quality (CEQ) has developed regulations for implementing NEPA. These regulations are found in Title 40 of the Code

  20. WEST VALLEY DEMONSTRATION PROJECT ANNUAL SITE ENVIRONMENTAL REPORT CALENDAR YEAR 2002

    SciTech Connect

    2003-09-12

    This annual environmental monitoring report for the West Valley Demonstration Project (WVDP or Project) is published to inform those with interest about environmental conditions at the WVDP. In accordance with U.S. Department of Energy (DOE) Order 231.1, Environment, Safety, and Health Reporting, the report summarizes calendar year (CY) 2002 environmental monitoring data so as to describe the performance of the WVDP's environmental management system, confirm compliance with standards and regulations, and highlight important programs. In 2002, the West Valley Demonstration Project, the site of a DOE environmental cleanup activity operated by West Valley Nuclear Services Co. (WVNSCO), was in the final stages of stabilizing high-level radioactive waste (HLW) that remained at the site after commercial nuclear fuel reprocessing had been discontinued in the early 1970s. The Project is located in western New York State, about 30 miles south of Buffalo, within the New York State-owned Western New York Nuclear Service Center (WNYNSC). The WVDP is being conducted in cooperation with the New York State Energy Research and Development Authority (NYSERDA). Ongoing work activities at the WVDP during 2002 included: (1) completing HLW solidification and melter shutdown; (2) shipping low-level radioactive waste off-site for disposal; (3) constructing a facility where large high-activity components can be safely packaged for disposal; (4) packaging and removing spent materials from the vitrification facility; (5) preparing environmental impact statements for future activities; (6) removing as much of the waste left behind in waste tanks 8D-1 and 8D-2 as was reasonably possible; (7) removing storage racks, canisters, and debris from the fuel receiving and storage pool, decontaminating pool walls, and beginning shipment of debris for disposal; (8) ongoing decontamination in the general purpose cell and the process mechanical cell (also referred to as the head end cells); (9) planning

  1. A guide to environmental monitoring data, 1945--1972: Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Thiede, M.E.; Bates, D.J.; Mart, E.I.; Hanf, R.W.

    1994-03-01

    This report is a guide to the work accomplished by the Environmental Monitoring Data Task, which is one of the tasks in the Hanford Environmental Dose Reconstruction (HEDR) Project. The objective of the Environmental Monitoring Data Task was to recover, evaluate, process, and/or reconstruct the environmental monitoring data for the period 1945--1972. The period of time for which environmental monitoring data were sought was determined by the start-up and shut-down dates of the Hanford facilities that emitted the majority of radionuclides to the two major pathways: air and the Columbia River. Radionuclide emissions to the air were mainly the result of the operation of the chemical separations plants from 1944--1972 (Heeb 1994). Radionuclide emissions to the Columbia River were mainly the result of the operation of the single-pass production reactors from 1944--1971 (Heeb and Bates 1994). Therefore, the historical environmental monitoring data sought were for the period 1945--1972. Within the period of 1945--1972, specific periods of interest to the HEDR Project vary depending on the pathway. For example, 1945--1951 was the peak period for radionuclide emissions to the air and hence vegetation uptake of radionuclides, while 1956--1965 was the peak period for radionuclide emissions to the Columbia River and hence fish uptake of radionuclides. However, adequate historical data were not always available for the periods of interest. In the case of vegetation measurements, conversion and correction factors had to be developed to convert the historical measurements to modern standard measurements. Table S.1 lists the reports that explain these conversion and correction factors. In the case of Columbia River fish and waterfowl, bioconcentration factors were developed for use in any year where the river pathway data are insufficient.

  2. Susitna Hydroelectric Project: terrestrial environmental workshop and preliminary simulation model

    USGS Publications Warehouse

    Everitt, Robert R.; Sonntag, Nicholas C.; Auble, Gregory T.; Roelle, James E.; Gazey, William

    1982-01-01

    The technical feasibility, economic viability, and environmental impacts of a hydroelectric development project in the Susitna River Basin are being studied by Acres American, Inc. on behalf of the Alaska Power Authority. As part of these studies, Acres American recently contracted LGL Alaska Research Associates, Inc. to coordinate the terrestrial environmental studies being performed by the Alaska Department of Fish and Game and, as subcontractors to LGL, several University of Alaska research groups. LGL is responsible for further quantifying the potential impacts of the project on terrestrial wildlife and vegetation, and for developing a plan to mitigate adverse impacts on the terrestrial environment. The impact assessment and mitigation plan will be included as part of a license application to the Federal Energy Regulatory Commission (FERC) scheduled for the first quarter of 1983. The quantification of impacts, mitigation planning, and design of future research is being organized using a computer simulation modelling approach. Through a series of workshops attended by researchers, resource managers, and policy-makers, a computer model is being developed and refined for use in the quantification of impacts on terrestrial wildlife and vegetation, and for evaluating different mitigation measures such as habitat enhancement and the designation of replacement lands to be managed by wildlife habitat. This report describes the preliminary model developed at the first workshop held August 23 -27, 1982 in Anchorage.

  3. Ebola Virus RNA Stability in Human Blood and Urine in West Africa’s Environmental Conditions

    PubMed Central

    Delaune, Deborah; Poyot, Thomas; Valade, Eric; Mérens, Audrey; Rollin, Pierre E.; Foissaud, Vincent

    2016-01-01

    We evaluated RNA stability of Ebola virus in EDTA blood and urine samples collected from infected patients and stored in West Africa’s environmental conditions. In blood, RNA was stable for at least 18 days when initial cycle threshold values were <30, but in urine, RNA degradation occurred more quickly. PMID:26812135

  4. UNITED STATES ENVIRONMENTAL PROTECTION AGENCY MUNICIPAL WASTE COMBUSTION RESIDUE SOLIDIFICATION/STABILIZATION EVALUATION PROGRAM

    EPA Science Inventory

    Vendors of solidification/stabilization (S/S) and other technologies are cooperating with the U.S. Environmental Protection Agency's (U.S. EPA's) Office of Research and Development (ORD), Risk Reduction Engineering Laboratory to demonstrate and evaluate the performance of the tec...

  5. Genetic and Environmental Stability in Attention Problems across the Lifespan: Evidence from the Netherlands Twin Register

    ERIC Educational Resources Information Center

    Kan, Kees-Jan; Dolan, Conor V.; Nivard, Michel G.; Middeldorp, Christel M.; van Beijsterveldt, Catharina E. M.; Willemsen, Gonneke; Boomsma, Dorret I.

    2013-01-01

    Objective: To review findings on attention-deficit/hyperactivity disorder and attention problems (AP) in children, adolescents, and adults, as established in the database of the Netherlands Twin Register and increase the understanding of stability in AP across the lifespan as a function of genetic and environmental influences. Method: A…

  6. Bacterial lipopolysaccharide binding enhances virion stability and promotes environmental fitness of an enteric virus

    PubMed Central

    Robinson, Christopher M.; Jesudhasan, Palmy R.; Pfeiffer, Julie K.

    2014-01-01

    Summary Enteric viruses, including poliovirus and reovirus, encounter a vast microbial community in the mammalian gastrointestinal tract, which has been shown to promote virus replication and pathogenesis. Investigating the underlying mechanisms, we find that poliovirus binds bacterial surface polysaccharides, which enhances virion stability and cell attachment by increasing binding to the viral receptor. Additionally, we identified a poliovirus mutant, VP1-T99K, with reduced lipopolysaccharide (LPS) binding. Although T99K and WT poliovirus cell attachment, replication and pathogenesis in mice are equivalent, following peroral inoculation of mice, VP1-T99K poliovirus was unstable in feces. Consequently, the ratio of mutant virus in feces is reduced following additional cycles of infection in mice. Thus, the mutant virus incurs a fitness cost when environmental stability is a factor. These data suggest that poliovirus binds bacterial surface polysaccharides, enhancing cell attachment and environmental stability, potentially promoting transmission to a new host. PMID:24439896

  7. CNR LARA project, Italy: Airborne laboratory for environmental research

    NASA Technical Reports Server (NTRS)

    Bianchi, R.; Cavalli, R. M.; Fiumi, L.; Marino, C. M.; Pignatti, S.

    1995-01-01

    The increasing interest for the environmental problems and the study of the impact on the environment due to antropic activity produced an enhancement of remote sensing applications. The Italian National Research Council (CNR) established a new laboratory for airborne hyperspectral imaging, the LARA Project (Laboratorio Aero per Ricerche Ambientali - Airborne Laboratory for Environmental Research), equipping its airborne laboratory, a CASA-212, mainly with the Daedalus AA5000 MIVIS (Multispectral Infrared and Visible Imaging Spectrometer) instrument. MIVIS's channels, spectral bandwidths, and locations are chosen to meet the needs of scientific research for advanced applications of remote sensing data. MIVIS can make significant contributions to solving problems in many diverse areas such as geologic exploration, land use studies, mineralogy, agricultural crop studies, energy loss analysis, pollution assessment, volcanology, forest fire management and others. The broad spectral range and the many discrete narrow channels of MIVIS provide a fine quantization of spectral information that permits accurate definition of absorption features from a variety of materials, allowing the extraction of chemical and physical information of our environment. The availability of such a hyperspectral imager, that will operate mainly in the Mediterranean area, at the present represents a unique opportunity for those who are involved in environmental studies and land-management to collect systematically large-scale and high spectral-spatial resolution data of this part of the world. Nevertheless, MIVIS deployments will touch other parts of the world, where a major interest from the international scientific community is present.

  8. Environmental Field Surveys, EMF Rapid Program, Engineering Project No.3

    SciTech Connect

    Enertech Consultants

    1996-04-01

    The EMF Research and Public Information Dissemination Program (RAPID) includes several engineering research in the area of exposure assessment and source characterization. RAPID engineering project No. 3: ''Environmental Field Surveys'' was performed to obtain information on the levels and characteristics of different environments, for which only limited data were available, especially in comparison to magnetic field data for the residential environment and for electric utility facilities, such as power lines and substations. This project was also to provide information on the contribution of various field sources in the surveyed environments. Magnetic field surveys were performed at four sites for each of five environments: schools, hospitals, office buildings, machine shops, and grocery stores. Of the twenty sites surveyed, 11 were located in the San Francisco Bay Area and 9 in Massachusetts. The surveys used a protocol based on magnetic field measurements and observation of activity patterns, designed to provide estimates of magnetic field exposure by type of people and by type of sources. The magnetic field surveys conducted by this project produced a large amount of data which will form a part of the EMF measurement database Field and exposure data were obtained separately for ''area exposure'' and ''at exposure points''. An exposure point is a location where persons engage in fixed, site specific activities near a local source that creates a significant increase in the area field. The area field is produced by ''area sources'', whose location and field distribution is in general not related to the location of the people in the area.

  9. Environmental Assessment: geothermal direct heat project, Marlin, Texas

    SciTech Connect

    Not Available

    1980-08-01

    The Federal action addressed by this Environmental Assessment (EA) is joint funding the retrofitting of a heating and hot water system in a hospital at Marlin, Texas, with a geothermal preheat system. The project will be located within the existing hospital boiler room. One supply well was drilled in an existing adjacent parking lot. It was necessary to drill the well prior to completion of this environmental assessment in order to confirm the reservoir and to obtain fluids for analysis in order to assess the environmental effects of fluid disposal. Fluid from operation will be disposed of by discharging it directly into existing street drains, which will carry the fluid to Park Lake and eventually the Brazos River. Fluid disposal activities are regulated by the Texas Railroad Commission. The local geology is determined by past displacements in the East Texas Basin. Boundaries are marked by the Balcones and the Mexia-Talco fault systems. All important water-bearing formations are in the cretaceous sedimentary rocks and are slightly to highly saline. Geothermal fluids are produced from the Trinity Group; they range from approximately 3600 to 4000 ppM TDS. Temperatures are expected to be above 64/sup 0/C (147/sup 0/F). Surface water flows southeastward as a part of the Brazos River Basin. The nearest perennial stream is the Brazos River 5.6 km (3.5 miles) away, to which surface fluids will eventually discharge. Environmental impacts of construction were small because of the existing structures and paved areas. Construction run-off and geothermal flow-test fluid passed through a small pond in the city park, lowering its water quality, at least temporarily. Construction noise was not out of character with existing noises around the hospital.

  10. SAS applications for Tai's stability analysis and AMMI model in genotype x environmental interaction (GEI) effects.

    PubMed

    Thillainathan, M; Fernandez, G C

    2001-01-01

    A user-friendly graphical data analysis to perform stability analysis of genotype x environmental interactions, using Tai's stability model and additive main effects and multiplicative interaction (AMMI) biplots, are presented here. This practical approach integrates statistical and graphical analysis tools available in SAS systems and provides user-friendly applications to perform complete stability analyses without writing SAS program statements or using pull-down menu interfaces by running the SAS macros in the background. By using this macro approach, the agronomists and plant breeders can effectively perform stability analysis and spend more time in data exploration, interpretation of graphs, and output, rather than debugging their program errors. The necessary MACRO-CALL files can be downloaded from the author's home page at http://www.ag.unr.edu/gf. The nature and the distinctive features of the graphics produced by these applications are illustrated by using published data. PMID:11535655