Science.gov

Sample records for accelerator facility cebaf

  1. CEBAF accelerator achievements

    SciTech Connect

    Y.C. Chao, M. Drury, C. Hovater, A. Hutton, G.A. Krafft, M. Poelker, C. Reece, M. Tiefenback

    2011-06-01

    In the past decade, nuclear physics users of Jefferson Lab's Continuous Electron Beam Accelerator Facility (CEBAF) have benefited from accelerator physics advances and machine improvements. As of early 2011, CEBAF operates routinely at 6 GeV, with a 12 GeV upgrade underway. This article reports highlights of CEBAF's scientific and technological evolution in the areas of cryomodule refurbishment, RF control, polarized source development, beam transport for parity experiments, magnets and hysteresis handling, beam breakup, and helium refrigerator operational optimization.

  2. The Continuous Electron Beam Accelerator Facility: CEBAF at the Jefferson Laboratory

    SciTech Connect

    Leemann, Chrisoph; Douglas, David R; Krafft, Geoffrey A

    2001-08-01

    The Jefferson Laboratory's superconducting radiofrequency (srf) Continuous Electron Beam Accelerator Facility (CEBAF) provides multi-GeV continuous-wave (cw) beams for experiments at the nuclear and particle physics interface. CEBAF comprises two antiparallel linacs linked by nine recirculation beam lines for up to five passes. By the early 1990s, accelerator installation was proceeding in parallel with commissioning. By the mid-1990s, CEBAF was providing simultaneous beams at different but correlated energies up to 4 GeV to three experimental halls. By 2000, with srf development having raised the average cavity gradient up to 7.5 MV/m, energies up to nearly 6 GeV were routine, at 1-150 muA for two halls and 1-100 nA for the other. Also routine are beams of >75% polarization. Physics results have led to new questions about the quark structure of nuclei, and therefore to user demand for a planned 12 GeV upgrade. CEBAF's enabling srf technology is also being applied in other projects.

  3. The CEBAF (Continuous Electron Beam Accelerator Facility) fast shutdown system

    SciTech Connect

    Perry, J.; Woodworth, E.

    1990-09-01

    Because of the high power in the CEBAF beam, equipment must be protected in the event of beam loss. The policy that has been adopted is to require a positive permissive signal from each of several inputs in order to operate the gun that starts the beam. If the permissive is removed, the gun shuts off within 20 {mu}s. The inputs that are now monitored include radiation monitors that detect beam loss directly, vacuum monitors (which also observe the status of various in-line valves), and general input from the rf system, which combines detection of klystron failure, arcs, and rf window high temperature. The system is expandable, so other fault detectors can be added if experience shows their necessity.

  4. Environmental Management Assessment of the Continuous Electron Beam Accelerator Facility (CEBAF)

    SciTech Connect

    Not Available

    1993-03-01

    This report documents the results of the Environmental Management Assessment performed at the Continuous Electron Beam Accelerator Facility (CEBAF) in Newport News, Virginia. During this assessment, activities and records were reviewed and interviews were conducted with personnel from the CEBAF Site Office; the CEBAF management and operating contractor (M&O), Southeastern Universities Research Association, Inc. (SURA); the Oak Ridge Field Office (OR); and the responsible DOE Headquarters Program Office, the Office of Energy Research (ER). The onsite portion of the assessment was conducted from March 8 through March 19, 1993, by the US Department of Energy`s (DOE`s) Office of Environmental Audit (EH-24) located within the office of Environment, Safety and Health (EH). DOE 5482.1 B, ``Environment, Safety and Health Appraisal Program,`` and Secretary of Energy Notice (SEN)-6E-92, ``Departmental Organizational and Management Arrangements,`` establish the mission of EH-24 to provide comprehensive, independent oversight of Department-wide environmental programs on behalf of the Secretary of Energy. The ultimate goal of EH-24 is enhancement of environmental protection and minimization of risk to public health and the environment. EH-24 accomplishes its mission utilizing systematic and periodic evaluations of the Department`s environmental programs within line organizations, and through use of supplemental activities which serve to strengthen self-assessment and oversight functions within program, field, and contractor organizations.

  5. Multipass beam breakup in the CEBAF (Continuous Electron Beam Accelerator Facility) superconducting linac

    SciTech Connect

    Bisognano, J.J.; Krafft, G.A.

    1986-06-02

    Multipass beam breakup can severely limit current in superconducting linear accelerators due to the inherently high Q's of transverse deflecting modes of the rf cavities. The success of higher-order-mode damping in increasing threshold currents for the 4-pass CEBAF SRF linac design is investigated with computer modeling. This simulation is shown to be in agreement with theoretical analyses which have successfully described beam breakup in the Stanford superconducting, recirculating linac. Numerical evaluation of an analytic treatment by Gluckstern of multipass beam breakup with distributed cavities is also found to be consistent with the computer model. Application of the simulation to the design array of 400 five-cell CEBAF/Cornell cavities with measured higher-order-mode damping indicates that the beam breakup threshold current is at least an order of magnitude above the CEBAF design current of 200 ..mu..A.

  6. New challenges for HEP computing: RHIC (Relativistic Heavy Ion Collider) and CEBAF (Continuous Electron Beam Accelerator Facility)

    SciTech Connect

    LeVine, M.J. Frankfurt Univ. )

    1990-01-01

    We will look at two facilities; RHIC and CEBF. CEBF is in the construction phase, RHIC is about to begin construction. For each of them, we examine the kinds of physics measurements that motivated their construction, and the implications of these experiments for computing. Emphasis will be on on-line requirements, driven by the data rates produced by these experiments.

  7. Thomas Jefferson National Accelerator Facility

    SciTech Connect

    Joseph Grames, Douglas Higinbotham, Hugh Montgomery

    2010-09-01

    The Thomas Jefferson National Accelerator Facility (Jefferson Lab) in Newport News, Virginia, USA, is one of ten national laboratories under the aegis of the Office of Science of the U.S. Department of Energy (DOE). It is managed and operated by Jefferson Science Associates, LLC. The primary facility at Jefferson Lab is the Continuous Electron Beam Accelerator Facility (CEBAF) as shown in an aerial photograph in Figure 1. Jefferson Lab was created in 1984 as CEBAF and started operations for physics in 1995. The accelerator uses superconducting radio-frequency (srf) techniques to generate high-quality beams of electrons with high-intensity, well-controlled polarization. The technology has enabled ancillary facilities to be created. The CEBAF facility is used by an international user community of more than 1200 physicists for a program of exploration and study of nuclear, hadronic matter, the strong interaction and quantum chromodynamics. Additionally, the exceptional quality of the beams facilitates studies of the fundamental symmetries of nature, which complement those of atomic physics on the one hand and of high-energy particle physics on the other. The facility is in the midst of a project to double the energy of the facility and to enhance and expand its experimental facilities. Studies are also pursued with a Free-Electron Laser produced by an energy-recovering linear accelerator.

  8. Survey and analysis of line-frequency interference in the CEBAF accelerator

    SciTech Connect

    Tiefenback, M.G.; Li, Rui

    1995-12-31

    Feedthrough of interference from the AC power line into accelerator components is a problem which in pulsed accelerators can be reduced by operation synchronous with the AC line. This means of avoiding line-frequency effects is ineffective for continuous wave machines such as the CEBAF accelerator. We have measured line-frequency perturbations at CEBAF both in beam position and energy by using the beam position monitor system as a multiple-channel sampling oscilloscope. Comparing these data against the measured static optics (taken synchronously with the AC line) we have been able to identify point sources of interference, and resolve line-synchronous variations in the beam energy at a level near 0.001%. 3 refs., 2 figs., 1 tab.

  9. Field Emission in CEBAF's SRF Cavities and Implications for Future Accelerators

    SciTech Connect

    Jay Benesch

    2006-02-15

    Field emission is one of the key issues in superconducting RF for particle accelerators. When present, it limits operating gradient directly or via induced heat load at 2K. In order to minimize particulate contamination of and thus field emission in the CEBAF SRF cavities during assembly, a cold ceramic RF window was placed very close to the accelerating cavity proper. As an unintended consequence of this, the window is charged by field-emitted electrons, making it possible to monitor and model field emission in the CEBAF cavities since in-tunnel operation began. From January 30, 1995, through February 10, 2003, there were 64 instances of spontaneous onset or change in cavity field emission with a drop in usable gradient averaging 1.4 ({sigma} 0.8) MV/m at each event. Fractional loss averaged 0.18 ({sigma} 0.12) of pre-event gradient. This event count corresponds to 2.4 events per century per cavity, or 8 per year in CEBAF. It is hypothesized that changes in field emission are due to adsorbed gas accumulation. The possible implications of this and other observations for the International Linear Collider (ILC) and other future accelerators will be discussed.

  10. CEBAF - environmental protection program plan

    SciTech Connect

    1995-10-01

    An important objective in the successful operation of the Continuous Electron Beam Accelerator Facility (CEBAF) is to ensure protection of the public and the environment. To meet this objective, the Southeastern Universities Research Association, Inc., (SURA) is committed to working with the US Department of Energy (DOE) to develop, implement, and manage a sound and workable environmental protection program at CEBAF. This environmental protection plan includes information on environmental monitoring, long-range monitoring, groundwater protection, waste minimization, and pollution prevention awareness program plan.

  11. CEBAF Distributed Data Acquisition System

    SciTech Connect

    Trent Allison; Thomas Powers

    2005-05-01

    There are thousands of signals distributed throughout Jefferson Lab's Continuous Electron Beam Accelerator Facility (CEBAF) that are useful for troubleshooting and identifying instabilities. Many of these signals are only available locally or monitored by systems with small bandwidths that cannot identify fast transients. The Distributed Data Acquisition (Dist DAQ) system will sample and record these signals simultaneously at rates up to 40 Msps. Its primary function will be to provide waveform records from signals throughout CEBAF to the Experimental Physics and Industrial Control System (EPICS). The waveforms will be collected after the occurrence of an event trigger. These triggers will be derived from signals such as periodic timers or accelerator faults. The waveform data can then be processed to quickly identify beam transport issues, thus reducing down time and increasing CEBAF performance. The Dist DAQ system will be comprised of multiple standalone chassis distributed throughout CEBAF. They will be interconnected via a fiber optic network to facilitate the global triggering of events. All of the chassis will also be connected directly to the CEBAF Ethernet and run EPICS locally. This allows for more flexibility than the typical configuration of a single board computer and other custom printed circuit boards (PCB) installed in a card cage.

  12. Correction of dispersion and the betatron functions in the CEBAF accelerator

    SciTech Connect

    Lebedev, V.A.; Bickley, M.; Schaffner, S.; Zeijts, J. van; Krafft, G.A.; Watson, C.

    1996-10-01

    During the commissioning of the CEBAF accelerator, correction of dispersion and momentum compaction, and, to a lesser extent, transverse transfer matrices were essential for robust operation. With changing machine conditions, repeated correction was found necessary. To speed the diagnostic process the authors developed a method which allows one to rapidly track the machine optics. The method is based on measuring the propagation of 30 Hz modulated betatron oscillations downstream of a point of perturbation. Compared to the usual methods of dispersion or difference orbit measurement, synchronous detection of the beam displacement, as measured by beam position monitors, offers significantly improved speed and accuracy of the measurements. The beam optics of the accelerator was altered to decrease lattice sensitivity at critical points and to simplify control of the betatron function match. The calculation of the Courant-Snyder invariant from signals of each pair of nearby beam position monitors has allowed one to perform on-line measurement and correction of the lattice properties.

  13. JEFFERSON LAB 12 GEV CEBAF UPGRADE

    SciTech Connect

    Rode, C. H.

    2010-04-09

    The existing continuous electron beam accelerator facility (CEBAF) at Thomas Jefferson National Accelerator Facility (TJNAF) is a 5-pass, recirculating cw electron Linac operating at approx6 GeV and is devoted to basic research in nuclear physics. The 12 GeV CEBAF Upgrade is a $310 M project, sponsored by the Department of Energy (DOE) Office of Nuclear Physics, that will expand its research capabilities substantially by doubling the maximum energy and adding major new experimental apparatus. The project received construction approval in September 2008 and has started the major procurement process. The cryogenic aspects of the 12 GeV CEBAF Upgrade includes: doubling the accelerating voltages of the Linacs by adding ten new high-performance, superconducting radiofrequency (SRF) cryomodules (CMs) to the existing 42 1/4 cryomodules; doubling of the 2 K cryogenics plant; and the addition of eight superconducting magnets.

  14. The Science and Experimental Equipment for the 12 GeV Upgrade of CEBAF

    SciTech Connect

    Arrington, John; Bernstein, Aron; Brooks, William; Burker, Volker; Cardman, Lawrence; Carlson, Carl; Cates, Gordon; Chen, Jian-Ping; Dzierba, Alex; Ent, Rolf; Elouadrhiri, Latifa; Fenker, Howard; Gao, Haiyan; Gasparian, Ashot; Goity, Jose; Higinbotham, Douglas; Holt, Roy; Hyde, Charles; De Jager, Cornelis; Jeschonnek, Sabine; Ji, Xiangdong; Jiang, Xiangdong; Jones, Mark; Keppel, Cynthia; Kuhn, Sebastian; Kumar, Krishna; Laget, Jean; Mack, David; Meyer, Curtis; Melnitchouk, Wolodymyr; Meziani, Zein-Eddine; Radyushkin, Anatoly; Ramsey-Musolf, Mike; Reimer, Paul; Richards, David; Rondon-Aramayo, Oscar; Salgado, Carlos; Smith, Elton; Schiavilla, Rocco; Souder, Paul; Stoler, Paul; Thomas, Anthony; Ulmer, Paul; Weinstein, Lawrence; Weiss, Christian

    2005-01-10

    This Conceptual Design Report (CDR) presents the compelling scientific case for upgrading the Continuous Electron Beam Accelerator Facility (CEBAF) at Jefferson Lab to 12 GeV. Such a facility will make profound contributions to the study of hadronic matter.

  15. CEBAF Control Room Renovation

    SciTech Connect

    Michael Spata; Thomas Oren

    2005-05-01

    The Machine Control Center (MCC) at Jefferson Lab's Continuous Electron Beam Accelerator Facility (CEBAF) was initially constructed in the early 1990s and based on proven technology of that era. Through our experience over the last 15 years and in our planning for the facility's 12 GeV upgrade we reevaluated the control room environment to capitalize on emerging visualization and display technologies and improve workflow processes and ergonomic attributes. This effort also sets the foundation for the redevelopment of the accelerator's control system to deliver high reliability performance with improvements in beam specifications management and information flow. The complete renovation was performed over a three-week maintenance period with no interruption to beam operations. We present the results of this effort.

  16. CEBAF Control Room Renovation

    SciTech Connect

    Michael Spata; Anthony Cuffe; Thomas Oren

    2005-03-22

    The Machine Control Center (MCC) at Jefferson Lab's Continuous Electron Beam Accelerator Facility (CEBAF) was constructed in the early 1990s and based on proven technology of that era. Through our experience over the last 15 years and in our planning for the facilities 12 GeV upgrade we reevaluated the control room environment to capitalize on emerging visualization and display technologies and improve on work-flow processes and ergonomic attributes. The renovation was performed in two phases during the summer of 2004, with one phase occurring during machine operations and the latter, more extensive phase, occurring during our semi-annual shutdown period. The new facility takes advantage of advances in display technology, analog and video signal management, server technology, ergonomic workspace design, lighting engineering, acoustic ceilings and raised flooring solutions to provide a marked improvement in the overall environment of machine operations.

  17. Admittance Test and Conceptual Study of a CW Positron Source for CEBAF

    SciTech Connect

    Golge, Serkan; Hyde, Charles E.; Freyberger, Arne

    2009-09-02

    A conceptual study of a Continuous Wave (CW) positron production is presented in this paper. The Continuous Electron Beam Accelerator Facility (CEBAF) at Jefferson Lab (JLAB) operates with a CW electron beam with a well-defined emittance, time structure and energy spread. Positrons created via bremsstrahlung photons in a high-Z target emerge with a large emittance compared to incoming electron beam. An admittance study has been performed at CEBAF to estimate the maximum beam phase space area that can be transported in the LINAC and in the Arcs. A positron source is described utilizing the CEBAF injector electron beam, and directly injecting the positrons into the CEBAF LINAC.

  18. CEBAF Progress Report

    SciTech Connect

    Christoph Leemann

    1992-06-15

    At the Continuous Electron Beam Accelerator Facility (CEBAF), under construction in Newport News, Virginia, a superconducting, recirculating, cw linac will provide a nominal 4 GeV, 200 ¿A electron beam for distribution to simultaneous nuclear physics experiments in three end stations. As of August 1992, the 45 MeV injector with 18 supeconducting cavities in 21/4 cryomodules identical to those being installed in the main accelerator has completed its initial commisisioning stage and has validated systems design by meeting specifications in energy, current, and beam quality.Cryomodule production has reached a rate of two/month, 12 (of 40) linac cryomodules are installed in the 1300-m-circumference tunnel, and low-power linac tests are being initiated. High-power rf amplifiers and power supplies are installed, and checkout is proceeding.

  19. New RF control system for the 12 GeV energy upgrade of the CEBAF accelerator at Jefferson Lab

    NASA Astrophysics Data System (ADS)

    Plawski, T.; Allison, T.; Bachimanchi, R.; Dong, H.; Hovater, C.; Musson, J.

    2008-11-01

    The CEBAF Accelerator at Jefferson Lab presently consists of 50 MeV injector, two anti-parallel superconducting linacs and two arcs for transporting beam between the linacs. By the mid-1990s, the accelerator was providing electrons up to 5.75 GeV. The 12 GeV Upgrade is a major accelerator project aimed at doubling the energy by adding 10 (five per linac) new high gradient cryomodules, each providing 100 MV of field. The new cryomodule will consist of eight 7-cell superconducting cavities operating at an average accelerating gradient of 19.5 mv/m and with an external Q = 3.2 x 107 The high gradient, very high quality factor and large Lorentz detuning coefficient (KL up to 4) pose significant challenges beyond what the present analog low level RF (LLRF) control systems can handle reliably; therefore, a new digital LLRF control system has been developed. The main highlights of the new RF Control system include: a RF frontend with low temperature drift and good linearity, a large FPGA platform for digital signal processing, an EPICS Input Output Computer (IOC) using a PC-104 and a digital Self Exciting Loop (SEL) based algorithm. This paper provides an overview of the 6 GeV and 12 GeV Upgrade CEBAF machines, a summary of sources of cavity field variation that drive LLRF system performance, and discusses recent developments and progress in Jefferson Lab's new LLRF system design.

  20. CEBAF Commissioning and Future Plans

    SciTech Connect

    Grunder, Hermann A.

    1996-01-01

    With first beam on target in July 1994 , the Continuous Electron Beam Accelerator Facility (CEBAF) in Newport News, Virginia began capitalizing on years of planning and work to create a laboratory devoted to the exploration of matter that interacts through the strong force, which holds the quarks inside the proton and binds protons and neutrons into the nucleus. This event is made more remarkable in that the accelerator is available to physicists on schedule and within cost. The success of the project is due largely to a reasoned approach to its planning and the extraordinary work of scores of talented and motivated individuals.

  1. LLRF System for the CEBAF Separator Upgrade

    SciTech Connect

    Plawski, Tomasz E.; Bachimanchi, Ramakrishna; Hovater, J. Curt; Seidman, David J.; Wissmann, Mark J.

    2014-12-01

    The Continuous Electron Beam Accelerator Facility (CEBAF) energy upgrade from 6 GeV to 12 GeV includes the installation of four new 748.5 MHz normal conducting deflecting cavities in the 5th pass extraction region. This system will work together with the existing 499 MHz RF Separator in order to allow simultaneous delivery of the beam to four CEBAF experimental halls. The RF system employs two digital LLRF systems controlling four cavities in a vector sum. Cavity tune information of the individual cavities is also obtained using a multiplexing scheme of the forward and reflected RF signals. In this paper we will present detailed LLRF design and the current status of the CEBAF 748.5/499 MHz beam extraction system.

  2. Report on CEBAF

    SciTech Connect

    Christoph Leemann

    1992-06-20

    At the Continuous Electron Beam Accelerator Facility (CEBAF), under construction in Newport News, Virginia, a superconducting, recirculating, cw linac will provide a nominal 4GeV, 200 muA electron beam for distribution to simultaneous nuclear physics experiments in three end stations. As of August, 1992, the 45 MeV injector - with 18 superconducting cavities in 2-1/4 cryomodules identical to those being installed in the main accelerator - has completed initial commissioning and has validated systems design by meeting energy, current and beam quality specifications. Cryomodule production has reached a rate of two/month, 12 (of 40) linac cryomodules are installed in the 1300-m-circumference tunnel, and low-power linac tests are being initiated. High-power rf amplifiers and power supplies have been installed, and checkout is proceeding. The 4800 W helium refrigeration plant is in commissioning and supports injector operations. Helium transfer line installation is nearing completion. East arc dipoles are installed. The control system is operational for the injector and being installed in the accelerator. Preparations are under way for preliminary linac beam tests. All major experimental equipment components are in industrial production, initial spectrometer carriage mechanical installation is proceeding in one end station, and scientific program planning is well advanced. Accelerator completion is scheduled for the first quarter of 1994, with first physics operations in the second quarter. Recent evaluation of energy potential shows the likelihood of ~6 GeV at turn-on, with evolutionary change to 8-10 GeV thereafter. A CEBAF R&D program for high-power IR and UV free electron lasers based on superconducting rf technology is being proposed.

  3. Jefferson Lab 12 GeV CEBAF Upgrade

    SciTech Connect

    Claus Rode

    2010-04-01

    The existing continuous electron beam accelerator facility (CEBAF) at Thomas Jefferson National Accelerator Facility (TJNAF) is a 5-pass, recirculating cw electron Linac operating at ~6 GeV and is devoted to basic research in nuclear physics. The 12 GeV CEBAF Upgrade is a $310 M project, sponsored by the Department of Energy (DOE) Office of Nuclear Physics, that will expand its research capabilities substantially by doubling the maximum energy and adding major new experimental apparatus. The project received construction approval in September 2008 and has started the major procurement process. The cryogenic aspects of the 12 GeV CEBAF Upgrade includes: doubling the accelerating voltages of the Linacs by adding ten new high-performance, superconducting radiofrequency (SRF) cryomodules (CMs) to the existing 42 1/4 cryomodules; doubling of the 2 K cryogenics plant; and the addition of eight superconducting magnets.

  4. CEBAF energy upgrade program including re-work of CEBAF cavities

    SciTech Connect

    Joseph Preble

    2008-02-12

    The Thomas Jefferson National Accelerator Facility, Jefferson Lab, is planning an upgrade of the CEBAF accelerator from a maximum energy of 6 GeV to 12 GeV and from 3 to 4 experimental halls. This paper will discuss the plans for upgrading the energy of the machine which requires improvements of the existing Super Conducting Radio Frequency (SRF) cryomodules and the additions of ten newly designed high performance SRF cryomodules.

  5. CEBAF beam loss accounting

    SciTech Connect

    Ursic, R.; Mahoney, K.; Hovater, C.; Hutton, A.; Sinclair, C.

    1995-12-31

    This paper describes the design and implementation of a beam loss accounting system for the CEBAF electron accelerator. This system samples the beam curent throughout the beam path and measures the beam current accurately. Personnel Safety and Machine Protection systems use this system to turn off the beam when hazardous beam losses occur.

  6. CEBAF - Design Overview and Project Status

    SciTech Connect

    Christoph Leemann

    1987-12-01

    The Continuous Electron Beam Accelerator Facility (CEBAF) will be an electron accelerator facility for nuclear physics research providing continuous beams with energies up to at least 4 GeV and currents up to 22 {micro}A. The Vogt Subcommittee of the Nuclear Science Advisory Committee has stated the physics objective of this new accelerator: The search for new nuclear degrees of freedom and the relationship of nucleon-meson degrees of freedom to quark-gluon degrees of freedom in nuclei is one of the most challenging and fundamental questions of physics. CEBAF's purpose thus is to study the structure of the nuclear many-body system, its quark substructure, and the strong and electroweak interactions governing the behavior of nuclear matter. This requires electron beams of sufficient: (1) energy to provide the kinematic flexibility required to study the transition region; (2) intensity (current) to allow precise measurement of relatively small electromagnetic cross sections; (3) duty factor to allow coincidence experiments; and (4) beam quality to allow high-resolution experiments. This combination of characteristics--high energy, high current, high duty factor, high beam quality--makes CEBAF a unique tool for nuclear physics research.

  7. CEBAF at higher energies and the kaon electromagnetic form factor

    SciTech Connect

    Baker, O.K.

    1994-04-01

    The electromagnetic production of strangeness, the physics of exciting systems having strangeness degrees of freedom (production of hadrons with one or more strange constituent quarks) using electromagnetic probes (real or virtual photons), is one of the frontier areas of research which will be investigated at the Continuous Electron Beam Accelerator Facility (CEBAF) when it becomes operational. CEBAF is expected to have an important impact upon this field of research using its specialized set of detection instruments and high quality electron beam. This paper focusses upon one aspect of the associated production of strangeness - the determination of the kaon electromagnetic form factor at high squared momentum transfers.

  8. Beam Loading Studies at CEBAF

    SciTech Connect

    G.A. Krafft; S.N. Simrock; K.L. Mahoney

    1990-09-10

    When the CEBAF accelerator operates at 200 {mu}A beam current, the superconducting cavities run with high beam loading. The CEBAF RF system (including the cavities, klystrons, and control systems) has been measured to obtain the response to low frequency current fluctuations and to obtain the transient response to rapid changes in the beam current. The data were collected both through RF tests where beam pulses are simulated by RF pulses and through beam tests. Both closed loop and open loop measurements were made, and the results are compared to detailed SPICE numerical simulations. It is concluded that CEBAF will operate with high control under a wide variety of loads.

  9. Conceptual design report, CEBAF basic experimental equipment

    SciTech Connect

    1990-04-13

    The Continuous Electron Beam Accelerator Facility (CEBAF) will be dedicated to basic research in Nuclear Physics using electrons and photons as projectiles. The accelerator configuration allows three nearly continuous beams to be delivered simultaneously in three experimental halls, which will be equipped with complementary sets of instruments: Hall A--two high resolution magnetic spectrometers; Hall B--a large acceptance magnetic spectrometer; Hall C--a high-momentum, moderate resolution, magnetic spectrometer and a variety of more dedicated instruments. This report contains a short description of the initial complement of experimental equipment to be installed in each of the three halls.

  10. The CEBAF Element Database and Related Operational Software

    SciTech Connect

    Larrieu, Theodore; Slominski, Christopher; Keesee, Marie; Turner, Dennison; Joyce, Michele

    2015-09-01

    The newly commissioned 12GeV CEBAF accelerator relies on a flexible, scalable and comprehensive database to define the accelerator. This database delivers the configuration for CEBAF operational tools, including hardware checkout, the downloadable optics model, control screens, and much more. The presentation will describe the flexible design of the CEBAF Element Database (CED), its features and assorted use case examples.

  11. Commissioning and Operation of 12 GeV CEBAF

    SciTech Connect

    Freyberger, Arne P.

    2015-09-01

    The Continuous Electron Beam Accelerator Facility (CEBAF) located at the Thomas Jefferson National Accelerator Laboratory (JLab) has been recently upgraded to deliver continuous electron beams to the experimental users at a maximum energy of 12 GeV, three times the original design energy of 4 GeV. This paper will present an overview of the upgrade, referred to as the 12GeV upgrade, and highlights from recent beam commissioning results.

  12. The Upgrade of CEBAF to 12 GeV: Physics Motivations and Technical Aspects

    SciTech Connect

    Bernhard Mecking; Larry Cardman

    2002-08-01

    The Continuous Electron Beam Accelerator Facility, CEBAF, makes use of electron and photon beams with an energy up to 6 GeV to investigate the electromagnetic structure of mesons, nucleons, and nuclei. We discuss the physics motivation for upgrading the facility to a maximum energy of 12 GeV and some of the key technological aspects of the upgrade.

  13. COMMISSIONING AND OPERATION OF THE CEBAF 100 MV CRYOMODULES

    SciTech Connect

    Allison, Trent; Davis, G; Drury, Michael; Harwood, Leigh; Hogan, John; Kimber, Andrew; Lahti, George; Merz, William; Nelson, Richard; Plawski, Tomasz; Seidman, David; Spata, Michael; Wilson, Michael; Hovater, J

    2012-07-01

    The Continuous Electron Beam Accelerator Facility (CEBAF) energy upgrade from 6 GeV to 12 GeV includes the installation of ten new 100 MV cryomodules and RF systems. The superconducting RF cavities are designed to operate CW at a maximum accelerating gradient of 19.3 MV/m. To support the higher gradients and higher Q{sub L} ({approx} 3 x 10{sup 7}), a new RF system has been developed and is being installed to power and control the cavities. The RF system employs digital control and 13 kW klystrons. Recently, two of these cryomodules and associated RF hardware and software have been installed and commissioned in the CEBAF accelerator. Electrons at linac currents up to 540 {micro}A have been successfully accelerated and used for nuclear physics experiments. This paper reports on the commissioning and operation of the RF system and cryomodules.

  14. Accelerator Facilities for Radiation Research

    NASA Technical Reports Server (NTRS)

    Cucinotta, Francis A.

    1999-01-01

    HSRP Goals in Accelerator Use and Development are: 1.Need for ground-based heavy ion and proton facility to understand space radiation effects discussed most recently by NAS/NRC Report (1996). 2. Strategic Program Goals in facility usage and development: -(1) operation of AGS for approximately 600 beam hours/year; (2) operation of Loma Linda University (LLU) proton facility for approximately 400 beam hours/year; (3) construction of BAF facility; and (4) collaborative research at HIMAC in Japan and with other existing or potential international facilities. 3. MOA with LLU has been established to provide proton beams with energies of 40-250 important for trapped protons and solar proton events. 4. Limited number of beam hours available at Brookhaven National Laboratory's (BNL) Alternating Gradient Synchrotron (AGS).

  15. The CEBAF Energy Recovery Experiment: Update and Future Plans

    SciTech Connect

    Arne Freyberger; Kevin Beard; S. Bogacz; Yu-Chiu Chao; Swapan Chattopadhyay; David Douglas; Andrew Hutton; Nikolitsa Merminga; Christopher Tennant; Michael Tiefenback

    2004-07-01

    A successful GeV scale energy recovery demonstration with a high ratio of peak-to-injection energies (50:1) was carried out on the CEBAF (Continuous Electron Beam Accelerator Facility) recirculating superconducting linear accelerator in the spring of 2003. To gain a quantitative understanding of the beam behavior through the machine, data was taken to characterize the 6D phase space during the CEBAF-ER (CEBAF with Energy Recovery) experimental run. The transverse emittance of the accelerating and energy recovered beams was measured in several locations to ascertain the beam quality preservation during energy recovery. Measurements also included the RF system's response to the energy recovery process and transverse beam profile of the energy recovered beam. One of the salient conclusions from the experiment is that the energy recovery process does not contribute significantly to the emittance degradation. The current status of the data analysis will be presented as well as plans for a GeV scale energy recovery experimental run with current doubling.

  16. The Radiological Research Accelerator Facility

    SciTech Connect

    Hall, E.J.; Marino, S.A.

    1993-05-01

    The Radiological Research Accelerator Facility (RARAF) is based on a 4-MV Van de Graaff accelerator, which is used to generate a variety of well-characterized radiation beams for research in radiobiology, radiological physics, and radiation chemistry. It is part of the Center for Radiological Research (CRR) - formerly the Radiological Research Laboratory of Columbia University, and its operation is supported as a National Facility by the US Department of Energy (DOE). As such, RARAF is available to all potential users on an equal basis and scientists outside the CRR are encouraged to submit proposals for experiments at RARAF. The operation of the Van de Graaff is supported by the DOE, but the research projects themselves must be supported separately. This report provides a listing and brief description of experiments performed at RARAF during the May 1, 1992 through April 30, 1993.

  17. Nucleon spin physics using CEBAF at 11 GeV

    SciTech Connect

    Zein-Eddine Meziani

    2003-03-01

    We discuss key experiments that address some of the nucleon spin physics questions as part of the 12 GeV planning for the energy upgrade of the Continuous Electron Beam Accelerator Facility (CEBAF) at Jefferson Lab. These experiments take advantage of a highly polarized beam and the availability of polarized target namely {sup 3}He combined with a Medium Acceptance Spectrometer (MAD) in Hall A.

  18. Fabrication and Testing Status of CEBAF 12 GeV Upgrade Cavities

    SciTech Connect

    Marhauser, F; Davis, G K; Forehand, D; Grenoble, C; Hogan, J; Overton, R B; Reilly, A V; Rimmer, R A; Stirbet, M

    2011-09-01

    The 12 GeV upgrade of the Continuous Electron Beam Accelerator Facility (CEBAF) at Jefferson Laboratory (JLab) is under way. All cavities have been built by industry and are presently undergoing post-processing and final low and high power qualification before cryomodule assembly. The status is reported including fabrication-related experiences, observations and issues throughout production, post-processing and qualification.

  19. CEBAF Upgrade: Cryomodule Performance And Lessons Learned

    SciTech Connect

    Drury, Michael A.; Davis, G. Kirk; Hogan, John P.; Hovater, J. Curt; King, Lawrence; Marhauser, Frank; Park, HyeKyoung; Preble, Joe; Reece, Charles E.; Rimmer, Robert A.; Wang, Haipeng; Wiseman, Mark A.

    2014-02-01

    The Thomas Jefferson National Accelerator Facility is currently engaged in the 12 GeV Upgrade Project. The goal of the 12 GeV Upgrade is a doubling of the available beam energy of the Continuous Electron Beam Accelerator Facility (CEBAF) from 6 GeV to 12 GeV. This increase in beam energy will be due in large part to the addition of ten C100 cryomodules plus associated new RF in the CEBAF linacs. The C100 cryomodules are designed to deliver 100 MeV per installed cryomodule. Each C100 cryomodule is built around a string of eight seven-cell, electro-polished, superconducting RF cavities. While an average performance of 100MV per cryomodule is needed to achieve the overall 12 GeV beam energy goal, the actual performance goal for the cryomodules is an average energy gain of 108 MV to provide operational headroom. Cryomodule production started in December 2010. All ten of the C100 cryomodules are installed in the linac tunnels and are on schedule to complete commissioning by September 2013. Performance during Commissioning has ranged from 104 MV to 118 MV. In May, 2012 a test of an early C100 achieved 108 MV with full beam loading. This paper will discuss the performance of the C100 cryomodules along with operational challenges and lessons learned for future designs.

  20. CEBAF SRF Performance during Initial 12 GeV Commissioning

    SciTech Connect

    Bachimanchi, Ramakrishna; Allison, Trent; Daly, Edward; Drury, Michael; Hovater, J; Lahti, George; Mounts, Clyde; Nelson, Richard; Plawski, Tomasz

    2015-09-01

    The Continuous Electron Beam Accelerator Facility (CEBAF) energy upgrade from 6 GeV to 12 GeV includes the installation of eleven new 100 MV cryomodules (88 cavities). The superconducting RF cavities are designed to operate CW at an accelerating gradient of 19.3 MV/m with a QL of 3×107. Not all the cavities were operated at the minimum gradient of 19.3 MV/m with the beam. Though the initial 12 GeV milestones were achieved during the initial commissioning of CEBAF, there are still some issues to be addressed for long term reliable operation of these modules. This paper reports the operational experiences during the initial commissioning and the path forward to improve the performance of C100 (100 MV) modules.

  1. UPGRADING THE CEBAF INJECTOR WITH A NEW BOOSTER, HIGHER VOLTAGE GUN, AND HIGHER FINAL ENERGY

    SciTech Connect

    Reza Kazimi, Arne Freyberger, Alicia Hofler, Andrew Hutton, Fay Hannon

    2012-07-01

    The Continuous Electron Beam Accelerator Facility (CEBAF) accelerator at Jefferson Lab will be upgraded from 6 GeV to 12 GeV in the next few years. To meet the requirement of the new machine and to take the opportunity to improve the beam quality, the CEBAF injector will be upgraded with a higher voltage gun, a new booster, and a new accelerating RF module. The CEBAF injector creates and accelerates three beams at different currents simultaneously. The beams are interleaved, each at one third of the RF frequency, traveling through the same beam line. The higher voltage gun will lower the space charge effects. The new booster with optimized beam dynamics will complete the bunching process and provide initial acceleration matched to the new gun voltage. Using our latest SRF design, the new booster has significantly lower x/y coupling effects that should improve our beam setup and operation for the highly sensitive parity experiments scheduled for the CEBAF's future. Finally, the new accelerating RF module will roughly double the injector final energy to match the rest of the 12 GeV accelerator. In this paper we will provide more detail about this upgrade.

  2. Fabrication and Measurement of 12 GeV Prototype Quadrupoles at Thomas Jefferson National Accelerator Facility

    SciTech Connect

    Tommy Hiatt, Mark Wiseman, Kenneth Baggett, J. Beck, Leigh Harwood, Joseph Meyers, Jeffrey Dail

    2009-05-01

    Jefferson Lab's Continuous Electron Beam Accelerator Facility (CEBAF) currently has a maximum beam energy of 6 GeV. The 12 GeV Upgrade Project will double the existing energy and is currently scheduled for completion in 2014. This doubling of energy requires modifications to the beam transport system which includes the addition of several new magnet designs and modifications to many existing designs. Prototyping efforts have been concluded for two different designs of quadrupole magnets required for the upgrade. The design, fabrication and measurement will be discussed.

  3. Chapter in book "Many Body Structure of Strongly Interacting Systems, Refereed and Selected Contributions from the Symposium '20 Years of Physics at the Mainz Microtron MAMI,'" Part I, Editors: Arenhövel, H.; Backe, H.; Drechsel, D.; Friedrich, J.; Kaiser, K.-H.; Walcher, Th., p.7-17 (contribution entitled Physics at the Thomas Jefferson National Accelerator Facility)

    SciTech Connect

    Lawrence Cardman

    2006-09-01

    The Continuous Electron Accelerator Facility, CEBAF, located at the Thomas Jefferson National Accelerator Facility, is devoted to the investigation of the electromagnetic structure of mesons, nucleons, and nuclei using high energy, high duty-cycle electron and photon beams. Selected experimental results of particular interest to the MAMI community are presented.

  4. Future Fixed Target Facilities

    SciTech Connect

    Melnitchouk, Wolodymyr

    2009-01-01

    We review plans for future fixed target lepton- and hadron-scattering facilities, including the 12 GeV upgraded CEBAF accelerator at Jefferson Lab, neutrino beam facilities at Fermilab, and the antiproton PANDA facility at FAIR. We also briefly review recent theoretical developments which will aid in the interpretation of the data expected from these facilities.

  5. LEP and CEBAF Polarimeters

    SciTech Connect

    Rossmanith, Robert; Burkert, Volker; Placidi, Massimo

    1988-09-01

    This paper gives an overview on high energy electron (positron) polarimeters by describing in more detail the plans for the LEP polarimeter and the CEBAF polarimeters. Both LEP and CEBAF will have laser polarimeters. In addition CEBAF will be equipped with a Moller polarimeter (for currents below 1 micro-amp).

  6. HOM Survey of the First CEBAF Upgrade Style Cavity Pair

    SciTech Connect

    Marhauser, Frank; Davis, G; Drury, Michael; Grenoble, Christiana; Hogan, John; Manus, Robert; Preble, Joseph; Reece, Charles; Rimmer, Robert; Tian, Kai; Wang, Haipeng

    2009-05-01

    The planned upgrade of the Continuous Electron Beam Accelerator Facility (CEBAF) at the Thomas Jefferson National Accelerator Laboratory (JLab) requires ten new superconducting rf (SRF) cavity cryomodules to double the beam energy to the envisaged 12 GeV. Adequate cavity Higher Order Mode (HOM) suppression is essential to avoid multipass, multibunch beam break-up (BBU) instabilities of the recirculating beam. We report on detailed HOM surveys performed for the first two upgrade style cavities tested in a dedicated cavity pair cryomodule at 2K. The safety margin to the BBU threshold budget at 12 GeV has been assessed.

  7. Techniques used in the alignment of TJNAF's accelerators and experimental halls

    SciTech Connect

    C.J. Curtis; J.C. Dahlberg; W.A. Oren; K.J. Tremblay

    1997-10-13

    With the successful completion of the main accelerator in 1994 the alignment emphasis at the Thomas Jefferson National Accelerator Facility (formerly CEBAF) switched to the continuing installation and upgrades in the three experimental halls. This presentation examines the techniques used in completing the CEBAF machine and also gives an update on the alignment of the new accelerator, a 1 kW free-electron laser, currently being built at the facility.

  8. Device control at CEBAF

    SciTech Connect

    Schaffner, S.; Barker, D.; Bookwalter, V.

    1996-08-01

    CEBAF has undergone a major conversion of its accelerator control system from TACL to EPICS, affecting device control for the RF system, magnets, the machine protection system, the vacuum and valves, and the diagnostic systems including beam position monitors, harps, and the camera and solenoid devices (beam viewers, faraday cups, optical transition radiation viewers, synchrotron radiation monitor, etc.). Altogether these devices require approximately 125,000 EPICS database records. The majority of these devices are controlled through CAMAC; some use embedded microprocessors (RF and magnets), and newer interfaces are in VME. The standard EPICS toolkit was extended to include a driver for CAMAC which supports dual processors on one serial highway, custom database records for magnets and BPMs, and custom data acquisition tasks for the BPMs. 2 refs., 1 tab.

  9. Commissioning of CEBAF

    SciTech Connect

    Andrew Hutton

    1994-06-01

    Construction of the CEBAF accelerator, a 4 GeV CW recirculating linac, is virtually complete. The 338 power sources and superconducting RF cavities, which have all run above nominal operating gradient in vertical tests (average 10.7 MeV/m), are installed. All the major components of the nine recirculation arcs are installed and aligned. Pre-commissioning was performed in parallel with construction. Ninety-nine superconducting cavities were operated simultaneously at the nominal gradient of 5 MeV/m. A maximum beam current of 110 PA CW (ZOO PA design) was reached. A cryomodule with eight cavities has operated at 8 MeV/m. Commissioning of the entire machine began in May 94. Results obtained during commissioning of the two linacs and the first arc are presented. 600 MeV beam is ready to be brought to the first experimental hall meeting a DOE milestone established in 1988.

  10. Radiation safety training for accelerator facilities

    SciTech Connect

    Trinoskey, P.A.

    1997-02-01

    In November 1992, a working group was formed within the U.S. Department of Energy`s (DOE`s) accelerator facilities to develop a generic safety training program to meet the basic requirements for individuals working in accelerator facilities. This training, by necessity, includes sections for inserting facility-specific information. The resulting course materials were issued by DOE as a handbook under its technical standards in 1996. Because experimenters may be at a facility for only a short time and often at odd times during the day, the working group felt that computer-based training would be useful. To that end, Lawrence Livermore National Laboratory (LLNL) and Argonne National Laboratory (ANL) together have developed a computer-based safety training program for accelerator facilities. This interactive course not only enables trainees to receive facility- specific information, but time the training to their schedule and tailor it to their level of expertise.

  11. CEBAF UV/IR FEL subsystem testing and validation program

    SciTech Connect

    G.R. Neil; S.V. Benson; H.F. Dylla; H. Liu

    1995-01-01

    A design has been established for IR and UV FELs within the Laser Processing Consortium's (LPC) program for development and application of high-average-power FELs for materials processing. Hardware prototyping and testing for the IR portion of the system are underway. The driver portion has been designed based on the superconducting radio-frequency (SRF) technology now seeing large-scale application in the commissioning of CEBAF, the Continuous Electron Beam Accelerator Facility, where LPC activities are centered. As of July 1994, measurements of beam performance confirm SRF's benefits in beam quality and stability, which are applicable to high-average-power FELs.

  12. Radiation Safety Systems for Accelerator Facilities

    SciTech Connect

    Liu, James C

    2001-10-17

    The Radiation Safety System (RSS) of an accelerator facility is used to protect people from prompt radiation hazards associated with accelerator operation. The RSS is a fully interlocked, engineered system with a combination of passive and active elements that are reliable, redundant, and fail-safe. The RSS consists of the Access Control System (ACS) and the Radiation Containment System (RCS). The ACS is to keep people away from the dangerous radiation inside the shielding enclosure. The RCS limits and contains the beam/radiation conditions to protect people from the prompt radiation hazards outside the shielding enclosure in both normal and abnormal operations. The complexity of a RSS depends on the accelerator and its operation, as well as associated hazard conditions. The approaches of RSS among different facilities can be different. This report gives a review of the RSS for accelerator facilities.

  13. Radiation Safety Systems for Accelerator Facilities

    SciTech Connect

    James C. Liu; Jeffrey S. Bull; John Drozdoff; Robert May; Vaclav Vylet

    2001-10-01

    The Radiation Safety System (RSS) of an accelerator facility is used to protect people from prompt radiation hazards associated with accelerator operation. The RSS is a fully interlocked, engineered system with a combination of passive and active elements that are reliable, redundant, and fail-safe. The RSS consists of the Access Control System (ACS) and the Radiation Containment System (RCS). The ACS is to keep people away from the dangerous radiation inside the shielding enclosure. The RCS limits and contains the beam/radiation conditions to protect people from the prompt radiation hazards outside the shielding enclosure in both normal and abnormal operations. The complexity of a RSS depends on the accelerator and its operation, as well as associated hazard conditions. The approaches of RSS among different facilities can be different. This report gives a review of the RSS for accelerator facilities.

  14. The founding of CEBAF, 1979 to 1987

    SciTech Connect

    C. Westfall

    1995-02-01

    -nuclear physics had attracted a considerable following. The growing electro-nuclear physics community was eager to find a scheme to permit virtually continuous acceleration, which would greatly improve the capability of performing coincidence experiments. In the words of the UVa conference proceedings, this experimental capability promised to open entire new areas of nuclear physics. Convinced that he could be the one to design the necessary groundbreaking machine after hearing the ideas of Loew and Servranckx, McCarthy began gathering a small accelerator building team. Against all odds, McCarthy's pipe dream resulted in the construction of a major accelerator laboratory, the Continuous Electron Beam Accelerator Facility (CEBAF). The founding of CEBAF is a tale of luck, perseverance, the triumph of flexible amateurism over rigid professionalism, and ironically, the potential of amateurs when supported by a thoroughly professional international network with well-defined methods for organizing and building accelerators. The CEBAF tale also has a surprise ending, for at the last minute, McCarthy's pipe dream was radically transformed by Hermann Grunder, who would direct the construction of the project. The twists and turns of this tale reveal many lessons about what aids and what detracts from the success of a large, federally sponsored scientific project.

  15. Radiation safety at accelerator facilities NCRP activities

    NASA Astrophysics Data System (ADS)

    Kase, Kenneth R.

    1997-02-01

    The National Council on Radiation Protection and Measurements (NCRP) has issued 13 reports, dating back to 1949, giving guidance and recommendations for radiation protection at accelerator facilities. There are six current reports on the topics of neutron radiation; facility and shielding design; alarms and access control systems; and equipment design, performance, and use. Scientific Committee 46 (SC 46) is currently overseeing the development of two reports that will provide up-to-date guidance for the design of medical accelerator facilities and shielding. SC 46 has also proposed that a report be written to provide guidance for the design and shielding of industrial accelerator and large irradiator facilities. This paper describes the status and contents of these reports.

  16. UCLA Neptune Facility for Advanced Accelerator Studies

    SciTech Connect

    Tochitsky, Sergei Ya.; Clayton, Christopher E.; Marsh, Kenneth A.; Joshi, Chandrashekhar; Rosenzweig, James B.; Pellegrini, Claudio

    2004-12-07

    The Neptune Laboratory at UCLA is being used for exploring concepts useful for advanced accelerators. This facility hosts a TW-class CO2 laser system and a high-brightness photoinjector producing a 14 MeV electron beam. The goal for the laboratory is to carry out experiments on high-gradient acceleration of externally injected electrons in both laser-driven relativistic plasma waves and EM laser field in vacuum. Experiments on plasma beat-wave acceleration using a prebunched electron beam, a high-energy gain 10-{mu}m inverse free electron laser accelerator, longitudinal electron beam shaping and laser based light-sources are planned.

  17. Magnetic field error measurement of the CEBAF (NIST) wiggler using the pulsed wire method

    SciTech Connect

    Wallace, Stephen; Colson, William; Neil, George; Harwood, Leigh

    1993-07-01

    The National Institute for Science and Technology (NIST) wiggler has been loaded to the Continuous Electron Beam Accelerator Facility (CEBAF). The pulsed wire method [R.W. Warren, Nucl. Instr. and Meth. A272 (1988) 267] has been used to measure the field errors of the entrance wiggler half, and the net path deflection was calculated to be Δx ≈ 5.2 m.

  18. Asynchronous inputs and flip-flop metastability in the CLAS trigger at CEBAF

    SciTech Connect

    Dave Doughty; S. Lemon; P. Bonneau

    1992-10-01

    The impact of flip-flop metastability on the pipelined trigger for the CLAS detector at CEBAF (Continuous Electron Beam Accelerator Facility) has been studied. It is found that the newest ECL (emitter coupled logic) flip-flops (ECLinPS) are much faster than older families at resolving the metastable condition. This will allow their use in systems with asynchronous inputs without an extra stage of synchronizing flip-flops.

  19. The CEBAF Element Database

    SciTech Connect

    Theodore Larrieu, Christopher Slominski, Michele Joyce

    2011-03-01

    With the inauguration of the CEBAF Element Database (CED) in Fall 2010, Jefferson Lab computer scientists have taken a step toward the eventual goal of a model-driven accelerator. Once fully populated, the database will be the primary repository of information used for everything from generating lattice decks to booting control computers to building controls screens. A requirement influencing the CED design is that it provide access to not only present, but also future and past configurations of the accelerator. To accomplish this, an introspective database schema was designed that allows new elements, types, and properties to be defined on-the-fly with no changes to table structure. Used in conjunction with Oracle Workspace Manager, it allows users to query data from any time in the database history with the same tools used to query the present configuration. Users can also check-out workspaces to use as staging areas for upcoming machine configurations. All Access to the CED is through a well-documented Application Programming Interface (API) that is translated automatically from original C++ source code into native libraries for scripting languages such as perl, php, and TCL making access to the CED easy and ubiquitous.

  20. Redetermining CEBAF's Absolute Energy

    NASA Astrophysics Data System (ADS)

    Su, Tong; Jlab Marathon Collaboration

    2015-04-01

    With the upgrade of the Jefferson Lab accelerator (CEBAF) from 6 GeV max energy to 12 GeV, all the dipole magnets in the machine were refurbished. Most of them were switched from open c-shaped to closed h-shaped by adding extra iron. With these upgraded magnets, the energy calibration of the accelerator needed to be redetermined. We will show how an extra external dipole, which is run in series with those in the machine, helps us cross check the current in the magnets as well as precisely map out the integral field for any machine setting. Using knowledge of the relative performance of the dipoles as well as the bend angle into the Hall, has allowed us to already determine a 4th pass 7 GeV beam to better than 7 MeV. In the future, we will use g-2 spin precession as a second independent energy determination. This work is supported by Kent State University, NSF Grant PHY-1405814, and DOE Contract DE-AC05-06OR23177 (JLab).

  1. Laser spectroscopy at accelerator facilities

    SciTech Connect

    Berry, H.G.

    1989-01-01

    The use of lasers in exciting fast atomic and molecular ions produced in accelerators is discussed. Collinear excitation of the ions is most efficient, and several examples of laser-induced fluorescence are given. These include tests of relativistic atomic structure, and atomic and molecular hyperfine measurements. Higher precision can be attained using rf double-resonance techniques in some cases. A variant of this technique, the raman double-resonance technique, is also introduced. The production of an optically-pumped polarized target is also described, together with an experiment on polarized electron pick-up in a fast heavy-ion beam. 16 refs., 19 figs., 1 tab.

  2. Performance of First C100 Cryomodules for the CEBAF 12 GeV Upgrade Project

    SciTech Connect

    Drury, Michael A.; Burrill, Andrew B.; Davis, G. Kirk; Hogan, John P.; King, Lawrence; Marhauser, Frank; Park, HyeKyoung; Preble, Joseph; Reece, Charles E.; Reilly, Anthony V.; Rimmer, Robert A.; Wang, Haipeng; Wiseman, Mark A.

    2012-09-01

    The Thomas Jefferson National Accelerator Facility is currently engaged in the 12 GeV Upgrade Project. The goal of the project is a doubling of the available beam energy of CEBAF from 6 GeV to 12 GeV. This increase in beam energy will be due primarily to the construction and installation of ten "C100" cryomodules in the CEBAF linacs. The C100 cryomodules are designed to deliver an average 108 MV each from a string of eight seven-cell, electropolished superconducting RF cavities operating at an average accelerating gradient of 19.2 MV/m. The new cryomodules fit in the same available linac space as the original CEBAF 20 MV cryomodules. Cryomodule production started in September 2010. Initial acceptance testing started in June 2011. The first two C100 cryomodules were installed and tested from August 2011 through October 2011, and successfully operated during the last period of the CEBAF 6 GeV era, which ended in May 2012. This paper will present the results of acceptance testing and commissioning of the C100 style cryomodules to date.

  3. CEBAF celebrates seven years of physics

    SciTech Connect

    Douglas Higinbotham

    2003-11-01

    Jefferson Lab in Newport News, Virginia, recently celebrated the first seven years of physics with the Continuous Electron Beam Accelerator Facility, CEBAF. The unique design of this electron accelerator allows three experimental halls to be operated simultaneously, with a total beam current of 200 {micro}A and a beam polarization of up to 80%. With this facility, a user community of more than 1000 scientists from 187 institutions in 20 countries has completed 81 nuclear-physics experiments, with substantial data taken on 23 more. From the data obtained in these experiments, more than 250 refereed journal articles have been published and 146 doctoral degrees have been awarded. In the near future more than 60 experiments are planned, and there are currently 128 PhD theses in progress. To celebrate and review these accomplishments, while also looking toward the future, the Jefferson Lab user group board of directors organized a symposium, which was held on 11-13 June and dedicated to the memory of Nathan Isgur, Jefferson Lab's first chief scientist. The meeting was divided into eight physics topics: nucleon form factors, few-body physics, reactions involving nuclei, strangeness production, structure functions, parity violation, deep exclusive reactions and hadron spectroscopy. Each topic was presented by one experimentalist and one theorist.

  4. The BNL Accelerator Test Facility control system

    SciTech Connect

    Malone, R.; Bottke, I.; Fernow, R.; Ben-Zvi, I.

    1993-01-01

    Described is the VAX/CAMAC-based control system for Brookhaven National Laboratory's Accelerator Test Facility, a laser/linac research complex. Details of hardware and software configurations are presented along with experiences of using Vsystem, a commercial control system package.

  5. ORION: An Advanced Accelerator Facility at SLAC

    SciTech Connect

    Palmer, Dennis

    2002-08-20

    Extending the center-of-mass energy frontier for high-energy physics depends on the research and development that is conducted now in the area of advanced accelerator physics and technology. In this article, we present the design and beam dynamics simulations for the emittance-compensated, RF photoinjector of the ORION Facility.

  6. Petabyte Class Storage at Jefferson Lab (CEBAF)

    NASA Technical Reports Server (NTRS)

    Chambers, Rita; Davis, Mark

    1996-01-01

    By 1997, the Thomas Jefferson National Accelerator Facility will collect over one Terabyte of raw information per day of Accelerator operation from three concurrently operating Experimental Halls. When post-processing is included, roughly 250 TB of raw and formatted experimental data will be generated each year. By the year 2000, a total of one Petabyte will be stored on-line. Critical to the experimental program at Jefferson Lab (JLab) is the networking and computational capability to collect, store, retrieve, and reconstruct data on this scale. The design criteria include support of a raw data stream of 10-12 MB/second from Experimental Hall B, which will operate the CEBAF (Continuous Electron Beam Accelerator Facility) Large Acceptance Spectrometer (CLAS). Keeping up with this data stream implies design strategies that provide storage guarantees during accelerator operation, minimize the number of times data is buffered allow seamless access to specific data sets for the researcher, synchronize data retrievals with the scheduling of postprocessing calculations on the data reconstruction CPU farms, as well as support the site capability to perform data reconstruction and reduction at the same overall rate at which new data is being collected. The current implementation employs state-of-the-art StorageTek Redwood tape drives and robotics library integrated with the Open Storage Manager (OSM) Hierarchical Storage Management software (Computer Associates, International), the use of Fibre Channel RAID disks dual-ported between Sun Microsystems SMP servers, and a network-based interface to a 10,000 SPECint92 data processing CPU farm. Issues of efficiency, scalability, and manageability will become critical to meet the year 2000 requirements for a Petabyte of near-line storage interfaced to over 30,000 SPECint92 of data processing power.

  7. BNL ACCELERATOR TEST FACILITY CONTROL SYSTEM UPGRADE.

    SciTech Connect

    MALONE,R.; BEN-ZVI,I.; WANG,X.; YAKIMENKO,V.

    2001-06-18

    Brookhaven National Laboratory's Accelerator Test Facility (ATF) has embarked on a complete upgrade of its decade old computer system. The planned improvements affect every major component: processors (Intel Pentium replaces VAXes), operating system (Linux/Real-Time Linux supplants OpenVMS), and data acquisition equipment (fast Ethernet equipment replaces CAMAC serial highway.) This paper summarizes the strategies and progress of the upgrade along with plans for future expansion.

  8. Accelerating tube of Gamma-4 facility module

    NASA Astrophysics Data System (ADS)

    Zav'yalov, N. V.; Gordeev, V. S.; Puchagin, S. Yu.; Grishin, A. V.; Strabykin, K. V.; Berdnikov, E. S.; Nazarenko, S. T.; Pavlov, V. S.; Demanov, V. A.

    2015-01-01

    The accelerating tube of Gamma-4 electrophysical facility standard module is presented. This accelerating tube is a component part of the energy transmission system of the module which provides delivery of the high-voltage electric pulse from the forming system output to the load unit. A specific feature of the tube design is the use of a dielectric lens to equalize the potential over the surface of the sectioned insulator. The lens made it possible to lower the electric field strength by 30% in the region of the most stressed dielectric rings, thus reducing the probability of the insulator breakdown. To increase the resource of the tube, its dimensions were selected based on the calculated average electric field intensity over the insulator surface equal to 55 kV/cm. The inductance of the tube was 87 nH. 230 shots of the Gamma-1 accelerator were performed using the proposed accelerating tube with an insulator voltage of 2.7 MV. No electrical breakdowns of the insulator were observed in these shots.

  9. A PARMELA model of the CEBAF injector valid over a wide range of beam parameters

    SciTech Connect

    Yuhong Zhang; Kevin Beard; Jay Benesch; Yu-Chiu Chao; Arne Freyberger; Joseph Grames; Reza Kazimi; Geoffrey Krafft; Rui Li; Nikolitsa Merminga; Benard Poelker; Byung Yunn

    2004-07-01

    A PARMELA model of the CEBAF injector valid over a wide range of beam parameters Yuhong Zhang, Kevin Beard, Jay Benesch, Yu-Chiu Chao, Arne Freyberger, Joseph Grames, Reza Kazimi, Geoff Krafft, Rui Li, Lia Merminga, Matt Poelker, Michael Tiefenback, Byung Yunn Thomas Jefferson National Accelerator Facility 12000 Jefferson Avenue, Newport News, VA 23606 USA An earlier PARMELA model of the Jefferson Lab CEBAF photoinjector was recently revised. The initial phase space distribution of an electron bunch was determined by measuring spot size and pulselength of the driver laser and by beam emittance measurements. The improved model has been used for simulations of the simultaneous delivery of the Hall A beam required for a hypernuclear experiment, and the Hall C beam required for the G0 parity violation experiment.

  10. Accelerator Design Concept for Future Neutrino Facilities

    SciTech Connect

    ISS Accelerator Working Group; Zisman, Michael S; Berg, J. S.; Blondel, A.; Brooks, S.; Campagne, J.-E.; Caspar, D.; Cevata, C.; Chimenti, P.; Cobb, J.; Dracos, M.; Edgecock, R.; Efthymiopoulos, I.; Fabich, A.; Fernow, R.; Filthaut, F.; Gallardo, J.; Garoby, R.; Geer, S.; Gerigk, F.; Hanson, G.; Johnson, R.; Johnstone, C.; Kaplan, D.; Keil, E.; Kirk, H.; Klier, A.; Kurup, A.; Lettry, J.; Long, K.; Machida, S.; McDonald, K.; Meot, F.; Mori, Y.; Neuffer, D.; Palladino, V.; Palmer, R.; Paul, K.; Poklonskiy, A.; Popovic, M.; Prior, C.; Rees, G.; Rossi, C.; Rovelli, T.; Sandstrom, R.; Sevior, R.; Sievers, P.; Simos, N.; Torun, Y.; Vretenar, M.; Yoshimura, K.; Zisman, Michael S

    2008-02-03

    This document summarizes the findings of the Accelerator Working Group (AWG) of the International Scoping Study (ISS) of a Future Neutrino Factory and Superbeam Facility. The work of the group took place at three plenary meetings along with three workshops, and an oral summary report was presented at the NuFact06 workshop held at UC-Irvine in August, 2006. The goal was to reach consensus on a baseline design for a Neutrino Factory complex. One aspect of this endeavor was to examine critically the advantages and disadvantages of the various Neutrino Factory schemes that have been proposed in recent years.

  11. The rare isotope accelerator (RIA) facility project

    SciTech Connect

    Christoph Leemann

    2000-08-01

    The envisioned Rare-Isotope Accelerator (RIA) facility would add substantially to research opportunities for nuclear physics and astrophysics by combining increased intensities with a greatly expanded variety of high-quality rare-isotope beams. A flexible superconducting driver linac would provide 100 kW, 400 MeV/nucleon beams of any stable isotope from hydrogen to uranium onto production targets. Combinations of projectile fragmentation, target fragmentation, fission, and spallation would produce the needed broad assortment of short-lived secondary beams. This paper describes the project's background, purpose, and status, the envisioned facility, and the key subsystem, the driver linac. RIA's scientific purposes are to advance current theoretical models, reveal new manifestations of nuclear behavior, and probe the limits of nuclear existence [3]. Figures 1 and 2 show, respectively, examples of RIA research opportunities and the yields projected for pursuing them. Figure 3 outlines a conceptual approach for delivering the needed beams.

  12. Flame acceleration studies in the MINIFLAME facility

    SciTech Connect

    Tieszen, S.R.; Sherman, M.P.; Benedick, W.B.

    1989-07-01

    Flame acceleration and deflagration-to-detonation transition (DDT) studies have been conducted in a 19.4-cm high, 14.5-cm wide, and 2. 242-m long channel (MINIFLAME) that is a 1:12.6 scale model of the 136-m{sup 3} FLAME facility. Tests were conducted with two levels of hydrogen concentration -- 20% and 30%, with and without obstacles in the channel, and with three levels of transverse top venting -- 0%, 13%, and 50%. The flame acceleration results in MINIFLAME are qualitatively similar to those in FLAME; however, the small-scale results are more benign quantitatively. The results show that insufficient venting, 13% venting in this case, can promote flame acceleration due to turbulence produced by the flow through the vents in smooth channels. However, with obstacle-generated turbulence in the channel, 13% top venting was found to be beneficial. Flame acceleration resulting in DDT was shown to occur in as little as 35 liters of mixture. Comparison of the DDT data with obstacles in MINIFLAME and FLAME supports d/{lambda} scaling of DDT, where {lambda} is the detonation cell width of the mixture and d is the characteristic open diameter of the channel. In the MINIFLAME and FLAME tests, DDT occurred for d/{lambda} greater than approximately three. Comparison with other experiments shows that the value of d/{lambda} for DDT is not constant but depends on the obstacle type, spacing, and channel geometry. The comparison of MINIFLAME and FLAME experiments extends the use of d/{lambda} scaling to different geometries and larger scales than previous studies. Small-scale-model testing of flame acceleration and DDT with the same combustible mixture as the full-scale prototype underpredicts flame speeds, overpressures, and the possibility of DDT. 18 refs., 16 figs.

  13. The CEBAF large acceptance spectrometer (CLAS)

    NASA Astrophysics Data System (ADS)

    Mecking, B. A.; Adams, G.; Ahmad, S.; Anciant, E.; Anghinolfi, M.; Asavapibhop, B.; Asryan, G.; Audit, G.; Auger, T.; Avakian, H.; Ball, J. P.; Barbosa, F. J.; Barrow, S.; Battaglieri, M.; Beard, K.; Berman, B. L.; Bianchi, N.; Boiarinov, S.; Bonneau, P.; Briscoe, W. J.; Brooks, W. K.; Burkert, V. D.; Carman, D. S.; Carstens, T.; Cetina, C.; Christo, S. B.; Cole, P. L.; Coleman, A.; Connelly, J.; Cords, D.; Corvisiero, P.; Crabb, D.; Crannell, H.; Cuevas, R. C.; Degtyarenko, P. V.; Dennis, L.; DeSanctis, E.; DeVita, R.; Distelbrink, J.; Dodge, G. E.; Dodge, W.; Doolittle, G.; Doughty, D.; Dugger, M.; Duncan, W. S.; Dytman, S.; Egiyan, H.; Egiyan, K. S.; Elouadrhiri, L.; Feuerbach, R. J.; Ficenec, J.; Frolov, V.; Funsten, H.; Gilfoyle, G. P.; Giovanetti, K. L.; Golovatch, E.; Gram, J.; Guidal, M.; Gyurjyan, V.; Heddle, D.; Hemler, P.; Hersman, F. W.; Hicks, K.; Hicks, R. S.; Holtrop, M.; Hyde-Wright, C. E.; Insley, D.; Ito, M. M.; Jacobs, G.; Jenkins, D.; Joo, K.; Joyce, D.; Kashy, D.; Khandaker, M.; Kim, W.; Klein, A.; Klein, F. J.; Klusman, M.; Kossov, M.; Kramer, L.; Koubarovski, V.; Kuhn, S. E.; Lake, A.; Lawrence, D.; Longhi, A.; Lukashin, K.; Lachniet, J.; Magahiz, R. A.; Major, W.; Manak, J. J.; Marchand, C.; Martin, C.; Matthews, S. K.; McMullen, M.; McNabb, J. W. C.; Mestayer, M. D.; Minehart, R.; Mirazita, M.; Miskimen, R.; Muccifora, V.; Mueller, J.; Murphy, L. Y.; Mutchler, G. S.; Napolitano, J.; Niculescu, I.; Niczyporuk, B. B.; Nozar, M.; O'Brien, J. T.; Opper, A. K.; O'Meara, J. E.; Pasyuk, E.; Philips, S. A.; Polli, E.; Price, J. W.; Pozdniakov, S.; Qin, L. M.; Raue, B. A.; Riccardi, G.; Ricco, G.; Riggs, C.; Ripani, M.; Ritchie, B. G.; Robb, J.; Ronchetti, F.; Rossi, P.; Roudot, F.; Salgado, C.; Sapunenko, V.; Schumacher, R. A.; Serov, V. S.; Sharabian, Y. G.; Smith, E. S.; Smith, L. C.; Smith, T.; Sober, D. I.; Stavinsky, A.; Stepanyan, S.; Stoler, P.; Taiuti, M.; Taylor, W. M.; Taylor, S.; Tedeschi, D. J.; Thoma, U.; Thompson, R.; Tilles, D.; Todor, L.; Tung, T. Y.; Tuzel, W.; Vineyard, M. F.; Vlassov, A. V.; Weinstein, L. B.; Welsh, R. E.; Weygand, D. P.; Wilkin, G. R.; Witkowski, M.; Wolin, E.; Yegneswaran, A.; Yergin, P.; Yun, J.

    2003-05-01

    The CEBAF large acceptance spectrometer (CLAS) is used to study photo- and electro-induced nuclear and hadronic reactions by providing efficient detection of neutral and charged particles over a good fraction of the full solid angle. A collaboration of about 30 institutions has designed, assembled, and commissioned CLAS in Hall B at the Thomas Jefferson National Accelerator Facility. The CLAS detector is based on a novel six-coil toroidal magnet which provides a largely azimuthal field distribution. Trajectory reconstruction using drift chambers results in a momentum resolution of 0.5% at forward angles. Cherenkov counters, time-of-flight scintillators, and electromagnetic calorimeters provide good particle identification. Fast triggering and high data-acquisition rates allow operation at a luminosity of 10 34 nucleon cm -2 s-1. These capabilities are being used in a broad experimental program to study the structure and interactions of mesons, nucleons, and nuclei using polarized and unpolarized electron and photon beams and targets. This paper is a comprehensive and general description of the design, construction and performance of CLAS.

  14. Construction of the CEBAF RF Separator

    SciTech Connect

    A. Krycuk; J. Fugitt; A. Johnson; R. Kazimi; L. Turlington

    1993-05-01

    The CEBAF accelerator is designed in a multipass racetrack configuration, with two 1497 MHz linear accelerator sections joined by independent magnetic transport arcs. Room temperature subharmonic rf separator cavities will be used on each independent arc to extract a portion of the recirculating beam, and one additional cavity will be used to divide the final full-energy beam between CEBAF's three experimental end stations. A single-cell prototype cavity has already been built and tested a low power levels. The next stage of the design process is the construction of a cavity capable of operation at full power, i.e. at a gradient sufficient to provide the required mu-rad bend to a 6 GeV beam. The paper will discuss both the electrical and mechanical design of the cavity, construction techniques employed, and preliminary test results.

  15. Design considerations and test facilities for accelerated radiation effects testing

    NASA Technical Reports Server (NTRS)

    Price, W. E.; Miller, C. G.; Parker, R. H.

    1972-01-01

    Test design parameters for accelerated dose rate radiation effects tests for spacecraft parts and subsystems used in long term mission (years) are detailed. A facility for use in long term accelerated and unaccelerated testing is described.

  16. CEBAF Control Room Renovation

    SciTech Connect

    Michael Spata; Thomas Oren

    2005-05-01

    The Machine Control Center at Jefferson Lab's Continuous Electron Beam Accelerator Facility was initially constructed in the early 1990s and based on proven technology of that era. Through our experience over the last 15 years and in our planning for the facilities 12 GeV upgrade we reevaluated the control room environment to capitalize on emerging visualization and display technologies and improve on workflow processes and ergonomic attributes. This effort also sets the foundation for the redevelopment of the accelerator's control system to deliver high reliability performance with improvements in beam specifications management and information flow. The complete renovation was performed over a three-week period with no interruption to beam operations. We present the results of this effort.

  17. Commissioning of the 123 MeV injector for 12 GeV CEBAF

    SciTech Connect

    Wang, Yan; Hofler, Alicia S.; Kazimi, Reza

    2015-09-01

    The upgrade of CEBAF to 12GeV included modifications to the injector portion of the accelerator. These changes included the doubling of the injection energy and relocation of the final transport elements to accommodate changes in the CEBAF recirculation arcs. This paper will describe the design changes and the modelling of the new 12GeV CEBAF injector. Stray magnetic fields have been a known issue for the 6 GeV CEBAF injector, the results of modelling the new 12GeV injector and the resulting changes implemented to mitigate this issue are described in this paper. The results of beam commissioning of the injector are also presented.

  18. Superconducting cavity tuner performance at CEBAF

    SciTech Connect

    Marshall, J.; Preble, J.; Schneider, W.

    1993-06-01

    At the Continuous Electron Beam Accelerator Facility (CEBAF), a 4 GeV, multipass CW electron beam is to be accelerated by 338 SRF, 5-cell niobium cavities operating at a resonant frequency of 1497 MHz. Eight cavities arranged as four pairs comprise a cyromodule, a croygenically isolated linac subdivision. The frequency is controlled by a mechanical tune attached to the first and fifth cell of the cavity which elastically deforms the cavity and thereby alters its resonant frequency. The tuner is driven by a stepper motor mounted external to the cryomodule that transfers torque through two rotary feedthroughs. A linear variable differential transducer (LVDT) mounted on the tuner monitors the displacement, and two limit switches interlock the movement beyond a 400 kHz bandwidth. Since the cavity has a loaded Q of 6.6 {center_dot} 10{sup 6}, the control system must maintain the frequency of the cavity to within {plus_minus} 50 Hz of the drive frequency for efficient coupling. This requirement is somewhat difficult to achieve since the difference in thermal contractions of the cavity and the tuner creates a frequency hystersis of approximately 10 kHz. The cavity is also subject to frequency shifts due to pressure fluctuations of the helium bath as well as radiation pressure. This requires that each cavity be characterized in terms of frequency change as a function of applied motor steps to allow proper tuning operations. This paper describes the electrical and mechanical performance of the cavity tuner during the commissioning and operation of the cryomodulus manufactured to date.

  19. Petabyte class storage at Jefferson Lab (CEBAF)

    SciTech Connect

    Chambers, R.; Davis, M.

    1996-08-01

    By 1997, this facility will collect over 1 Terabyte of raw information/day accelerator operation from three concurrently operating experimental halls. With post-processing, it means that about 250 TB raw and formatted experimental data will be generated each year. By the year 2000, a total of one Petabyte will be stored on-line. Critical to the program is the networking and computational capability to collect, store, retrieve, and reconstruct data on this scale. Design criteria include support of a raw data stream of 10-12 MB/second from Experimental Hall B, which will operate the CEBAF Large Acceptance Spectrometer. Keeping up with this data stream implies design strategies that provide storage guarantees during accelerator operation, minimize the number of times data is buffered, allow seamless access to specific data sets for the researcher, synchronize data retrievals with scheduling of postprocessing calculations on the data reconstruction CPU farms, as well as support the site capability for data reconstruction and reduction at same overall rate that new data is being collected. Current implementation uses state of the art StorageTek Redwood tape drives and robotics library integrated with the Open Storage Manager Hierarchical Storage Management software (Computer Associates, International), the use of Fibre Channel RAID disks dual-ported between Sun Microsystems SMP servers, and a network-based interface to a 10,000 SPECint92 data processing CPU farm. Issues of efficiency, scaleability, and manageability will become critical to meet the year 2000 requirements for a Petabyte of near-line storage interfaced to over 30,000 SPECint92 of data processing power.

  20. Mechanical and thermal design of the CEBAF Hall a beam calorimeter

    SciTech Connect

    M. Bevins; A. Day; P. Degtiarenko; L.A. Dillon-Townes; A. Freyberger; R. Gilman; A. Saha; S. Slachtouski

    2005-05-16

    A calorimeter is being fabricated to provide 0.5% - 1.0% absolute measurement of the beam current in the Hall A end station of the Continuous Electron Beam Accelerator Facility (CEBAF) at Jefferson Lab (JLAB). Modern powder metallurgy processes have produced high density, high thermal conductivity tungsten-copper composite materials that minimize electromagnetic and hadronic energy loss while maintaining a rapid thermal response time. Heat leaks are minimized by mounting the mass in vacuum on glass ceramic mounts. A conduction cooling scheme utilizes an advanced carbon fiber compliant thermal interface material. Transient finite difference and finite element models were developed to estimate heat leaks and thermal response times.

  1. Operational experience on the Brookhaven National Laboratory Accelerator Test Facility

    SciTech Connect

    Batchelor, K.; Babzien, M.; Ben-Zvi, I.

    1994-09-01

    Brookhaven National Laboratory Accelerator Test Facility is a laser-electron linear accelerator complex designed to provide high brightness beams for testing of advanced acceleration concepts and high power pulsed photon sources. Results of electron beam parameters attained during the commissioning of the nominally 45 MeV energy machine are presented.

  2. AREAL test facility for advanced accelerator and radiation source concepts

    NASA Astrophysics Data System (ADS)

    Tsakanov, V. M.; Amatuni, G. A.; Amirkhanyan, Z. G.; Aslyan, L. V.; Avagyan, V. Sh.; Danielyan, V. A.; Davtyan, H. D.; Dekhtiarov, V. S.; Gevorgyan, K. L.; Ghazaryan, N. G.; Grigoryan, B. A.; Grigoryan, A. H.; Hakobyan, L. S.; Haroutiunian, S. G.; Ivanyan, M. I.; Khachatryan, V. G.; Laziev, E. M.; Manukyan, P. S.; Margaryan, I. N.; Markosyan, T. M.; Martirosyan, N. V.; Mehrabyan, Sh. A.; Mkrtchyan, T. H.; Muradyan, L. Kh.; Nikogosyan, G. H.; Petrosyan, V. H.; Sahakyan, V. V.; Sargsyan, A. A.; Simonyan, A. S.; Toneyan, H. A.; Tsakanian, A. V.; Vardanyan, T. L.; Vardanyan, A. S.; Yeremyan, A. S.; Zakaryan, S. V.; Zanyan, G. S.

    2016-09-01

    Advanced Research Electron Accelerator Laboratory (AREAL) is a 50 MeV electron linear accelerator project with a laser driven RF gun being constructed at the CANDLE Synchrotron Research Institute. In addition to applications in life and materials sciences, the project aims as a test facility for advanced accelerator and radiation source concepts. In this paper, the AREAL RF photoinjector performance, the facility design considerations and its highlights in the fields of free electron laser, the study of new high frequency accelerating structures, the beam microbunching and wakefield acceleration concepts are presented.

  3. Accelerator development for a radioactive beam facility based on ATLAS.

    SciTech Connect

    Shepard, K. W.

    1998-01-08

    The existing superconducting linac ATLAS is in many respects an ideal secondary beam accelerator for an ISOL (Isotope separator on-line) type radioactive beam facility. Such a facility would require the addition of two major accelerator elements: a low charge state injector for the existing heavy ion linac, and a primary beam accelerator providing 220 MV of acceleration for protons and light ions. Development work for both of these elements, including the option of superconducting cavities for the primary beam accelerator is discussed.

  4. Environmental Assessment and Finding of No Significant Impact: Proposed Improvements at the Thomas Jefferson National Accelerator Facility Newport News, Virginia

    SciTech Connect

    N /A

    2002-07-13

    The U. S. Department of Energy (DOE), in this Environmental Assessment (EA), reports the results of an analysis of the potential environmental impacts from the proposed construction of various site improvements and the proposed installation and operation of the Helios light source at the Thomas Jefferson National Accelerator Facility (Jefferson Lab) in Newport News, Virginia. Jefferson Lab is operated by the Southeastern Universities Research Association, Inc. (SURA) under contract to DOE. With this proposal, DOE intends to construct no more than four major two or three story additions totaling about 151,000 sq. ft. (square feet) to CEBAF Center, the main facility administration building, and the addition of three new single story and one two story operations support structures on the accelerator site. The structures are a 28,000 sq. ft. storage building, a 15,100 sq. ft. technical support building, a 3,500 sq. ft. refrigeration service building, and a two-story 22,600 sq. ft addition to the Free Electron Laser (FEL) facility. The proposed action also involves the installation and operation of the Helios (High-Energy Lithography Source) accelerator in the FEL Addition. DOE proposes to take this action to provide Jefferson Lab with improved staff and operations support facilities that, along with the operation of Helios, will provide an increased capability to facilitate accelerator and physics program operations. Support activities necessary to effect the installation and operation of Helios would begin in Fiscal Year (FY) 03. It is expected that the Helios machine should be available to serve developmental and operational activities in support of the physics program later in FY 04. In this EA, DOE presents the no action alternative, alternatives considered and dismissed, and the proposed action alternative. It also evaluates the impacts of each.

  5. New Control Software for CEBAF Wire Scanners

    SciTech Connect

    Pavel Chevtsov

    2005-03-01

    Wire scanners (WS) are the most popular beam profile measurement devices at Jefferson Lab. The WS for the CEBAF accelerator and beam extraction lines were created and supported by different user groups. As a result, they are not only implemented in different hardware standards (CAMAC and VME) but until recently also had different control functions that made them very difficult to use for accelerator beam diagnostic applications. To integrate all WS into one homogeneous system that is very easy to support and use for accelerator operations, new WS control software has been created. The software is implemented as a library of WS control and status modules. The control modules handle the WS hardware components and make their data available for beam diagnostic applications. The status modules monitor data communication channels between WS components and control computers and generate alarms in case of hardware failures. The paper presents the functionality of the new WS control software a nd its positive impact on accelerator operations.

  6. Field Emission and Consequences as Observed and Simulated for CEBAF Upgrade Cryomodules

    SciTech Connect

    Marhauser, Frank; Johnson, Rolland; Rodriguez, Rodolfo; Degtiarenko, Pavel; Hutton, Andrew; Kharashvili, George; Reece, Charles; Rimmer, Robert

    2013-09-01

    High gamma and neutron radiation levels were monitored at the Continuous Electron Beam Accelerator Facility (CEBAF) at Jefferson Laboratory (JLab) after installation of new cavity cryomodules and initial test runs in the frame of the ongoing 12 GeV upgrade program. The dose rates scaled exponentially with cavity accelerating fields, but were independent of the presence of an electron beam in the accelerator. Hence, field emission (FE) is the source of origin. This has led to concerns regarding the high field operation (100 MV per cryomodule) in the future 12 GeV era. Utilizing supercomputing, novel FE studies have been performed with electrons tracked through a complete cryomodule. It provides a principal understanding of experimental observations as well as ways to mitigate FE as best as practicable by identification of problematic cavities.

  7. Plasma wakefield acceleration at CLARA facility in Daresbury Laboratory

    NASA Astrophysics Data System (ADS)

    Xia, G.; Nie, Y.; Mete, O.; Hanahoe, K.; Dover, M.; Wigram, M.; Wright, J.; Zhang, J.; Smith, J.; Pacey, T.; Li, Y.; Wei, Y.; Welsch, C.

    2016-09-01

    A plasma accelerator research station (PARS) has been proposed to study the key issues in electron driven plasma wakefield acceleration at CLARA facility in Daresbury Laboratory. In this paper, the quasi-nonlinear regime of beam driven plasma wakefield acceleration is analysed. The wakefield excited by various CLARA beam settings are simulated by using a 2D particle-in-cell (PIC) code. For a single drive beam, an accelerating gradient up to 3 GV/m can be achieved. For a two bunch acceleration scenario, simulation shows that a witness bunch can achieve a significant energy gain in a 10-50 cm long plasma cell.

  8. Recirculating Linac Accelerators For Future Muon Facilities

    SciTech Connect

    Yves Roblin, Alex Bogacz, Vasiliy Morozov, Kevin Beard

    2012-04-01

    Neutrino Factories (NF) and Muon Colliders (MC) require rapid acceleration of shortlived muons to multi-GeV and TeV energies. A Recirculating Linear Accelerator (RLA) that uses superconducting RF structures can provide exceptionally fast and economical acceleration to the extent that the focusing range of the RLA quadrupoles allows each muon to pass several times through each high-gradient cavity. A new concept of rapidly changing the strength of the RLA focusing quadrupoles as the muons gain energy is being developed to increase the number of passes that each muon will make in the RF cavities, leading to greater cost effectiveness. We discuss the optics and technical requirements for RLA designs, using RF cavities capable of simultaneous acceleration of both m+ and m- species. The design will include the optics for the multi-pass linac and droplet-shaped return arcs.

  9. The CEBAF RF Separator System Upgrade

    SciTech Connect

    J. Hovater; Mark Augustine; Al Guerra; Richard Nelson; Robert Terrell; Mark Wissmann

    2004-08-01

    The CEBAF accelerator uses RF deflecting cavities operating at the third sub-harmonic (499 MHz) of the accelerating frequency (1497 MHz) to ''kick'' the electron beam to the experimental halls. The cavities operate in a TEM dipole mode incorporating mode enhancing rods to increase the cavity's transverse shunt impedance [1]. As the accelerators energy has increased from 4 GeV to 6 GeV the RF system, specifically the 1 kW solid-state amplifiers, have become problematic, operating in saturation because of the increased beam energy demands. Two years ago we began a study to look into replacement for the RF amplifiers and decided to use a commercial broadcast Inductive Output Tube (IOT) capable of 30 kW. The new RF system uses one IOT amplifier on multiple cavities as opposed to one amplifier per cavity as was originally used. In addition, the new RF system supports a proposed 12 GeV energy upgrade to CEBAF. We are currently halfway through the upgrade with three IOTs in operation and the remaining one nearly installed. This paper reports on the new RF system and the IOT performance.

  10. Future directions of accelerator-based NP and HEP facilities

    SciTech Connect

    Roser, T.

    2011-07-24

    Progress in particle and nuclear physics has been closely connected to the progress in accelerator technologies - a connection that is highly beneficial to both fields. This paper presents a review of the present and future facilities and accelerator technologies that will push the frontiers of high-energy particle interactions and high intensity secondary particle beams.

  11. Future directions of accelerator-based NP and HEP facilities

    NASA Astrophysics Data System (ADS)

    Roser, Thomas

    2012-09-01

    Progress in particle and nuclear physics has been closely connected to the progress in accelerator technologies - a connection that is highly beneficial to both fields. This paper presents a review of the present and future facilities and accelerator technologies that will push the frontiers of high-energy particle interactions and high intensity secondary particle beams.

  12. Fermilab accelerator control system: Analog monitoring facilities

    SciTech Connect

    Seino, K.; Anderson, L.; Smedinghoff, J.

    1987-10-01

    Thousands of analog signals are monitored in different areas of the Fermilab accelerator complex. For general purposes, analog signals are sent over coaxial or twinaxial cables with varying lengths, collected at fan-in boxes and digitized with 12 bit multiplexed ADCs. For higher resolution requirements, analog signals are digitized at sources and are serially sent to the control system. This paper surveys ADC subsystems that are used with the accelerator control systems and discusses practical problems and solutions, and it describes how analog data are presented on the console system.

  13. The Dust Accelerator Facility at CCLDAS

    NASA Astrophysics Data System (ADS)

    Shu, A. J.; Collette, A.; Drake, K.; Gruen, E.; Horanyi, M.; Leblanc, S.; Munsat, T.; Northway, P.; Robertson, S. H.; Srama, R.; Sternovsky, Z.; Thomas, E.; Wagner, M.; Colorado CenterLunar Dust; Atmospheric Studies

    2010-12-01

    At the Colorado Center for Lunar Dust and Atmospheric Science (CCLDAS) we are in the process of assembling a 3MV macroscopic (~1um) dust particle accelerator. The acceleration unit is being made by the National Electrostatics Corporation (NEC). The accelerator consists of a pelletron generator and potential rings encased in an enclosure held at 6 atm of SF6. A pulsed dust source is used to inject particles into the accelerator. Here we describe advancements in dust accelerator technology at CCLDAS to allow more functionality and ease of use, focusing primarily on dust source control, and the capability to select a precise range in dust mass and velocity. Previously, the dust source was controlled by long plastic rods turning potentiometers inside the SF6 environment providing little to no feedback and repeatability. We describe a fiber optic control system that allows full control of the pulse characteristics being sent to the dust source using a LabVIEW control program to increase usability. An electrostatic Einzel lens is being designed using the ion-optics code SIMION to determine the properties of the electrodes needed for the optimum focusing of the dust beam. Our simulations studies indicate that the dust beam can be directed into a 0.5mm diameter spot. Our planned experiments require a high degree of control over particles size, speed, charge and other characteristics. In order to ensure that only particles of the desired characteristics are allowed to pass into the target chamber, two deflection plates are used to eliminate unwanted particles from the beam. Further simulations are being done to determine the possibility of bending the beamline to allow active selection of particles. The current design of the selection unit uses nuclear accelerator techniques to determine the velocity and charge of each particle and digital timing and logic to choose particles that will be allowed to pass. This requires a high signal to noise ratio due to the need for a well

  14. High Intensity heavy ion Accelerator Facility (HIAF) in China

    NASA Astrophysics Data System (ADS)

    Yang, J. C.; Xia, J. W.; Xiao, G. Q.; Xu, H. S.; Zhao, H. W.; Zhou, X. H.; Ma, X. W.; He, Y.; Ma, L. Z.; Gao, D. Q.; Meng, J.; Xu, Z.; Mao, R. S.; Zhang, W.; Wang, Y. Y.; Sun, L. T.; Yuan, Y. J.; Yuan, P.; Zhan, W. L.; Shi, J.; Chai, W. P.; Yin, D. Y.; Li, P.; Li, J.; Mao, L. J.; Zhang, J. Q.; Sheng, L. N.

    2013-12-01

    HIAF (High Intensity heavy ion Accelerator Facility), a new facility planned in China for heavy ion related researches, consists of two ion sources, a high intensity Heavy Ion Superconducting Linac (HISCL), a 45 Tm Accumulation and Booster Ring (ABR-45) and a multifunction storage ring system. The key features of HIAF are unprecedented high pulse beam intensity and versatile operation mode. The HIAF project aims to expand nuclear and related researches into presently unreachable region and give scientists possibilities to conduct cutting-edge researches in these fields. The general description of the facility is given in this article with a focus on the accelerator design.

  15. The CEBAF Master Oscillator and Distribution Remodeling

    SciTech Connect

    Tomasz Plawski, J. Hovater, John Musson, Ramakrishna Bachimanchi

    2009-05-01

    Jefferson Lab's CEBAF accelerator operation requires various frequency references to be distributed along the site. Three signals: 10 MHz, 70 MHz and 499 MHz are synthesized in the Machine Control Center (MCC) while 1427 MHz and 429 MHz are derived from 499 MHz and 70 MHz signals in four separate locations. We are replacing our obsolete 10 MHz, 70 MHz and 499 MHz sources with new sources that will incorporate a GPS receiver to discipline a 10 MHz reference. In addition the MO (Master Oscillator) system will be redundant (duplicate MO) and a third signal source will be used as a system diagnostic. Moreover, the 12 GeV Energy Upgrade for CEBAF accelerator will be adding 80 new RF systems. To support them the distribution of 1427 MHz and 70 MHz signals has to be extended and be able to deliver enough LO (Local Oscillator) and IF (Intermediate Frequency) power to 320 old and 80 new 80 RF systems. This paper discusses the new MO and the drive line extension.

  16. BNL ACCELERATOR-BASED RADIOBIOLOGY FACILITIES

    SciTech Connect

    LOWENSTEIN,D.I.

    2000-05-28

    For the past several years, the Alternating Gradient Synchrotron (AGS) at Brookhaven National Laboratory (USA) has provided ions of iron, silicon and gold, at energies from 600 MeV/nucleon to 10 GeV/nucleon, for the US National Aeronautics and Space Administration (NASA) radiobiology research program. NASA has recently funded the construction of a new dedicated ion facility, the Booster Applications Facility (BAF). The Booster synchrotron will supply ion beams ranging from protons to gold, in an energy range from 40--3,000 MeV/nucleon with maximum beam intensities of 10{sup 10} to 10{sup 11} ions per pulse. The BAF Project is described and the future AGS and BAF operation plans are presented.

  17. Proton and heavy ion acceleration facilities for space radiation research

    NASA Technical Reports Server (NTRS)

    Miller, Jack

    2003-01-01

    The particles and energies commonly used for medium energy nuclear physics and heavy charged particle radiobiology and radiotherapy at particle accelerators are in the charge and energy range of greatest interest for space radiation health. In this article we survey some of the particle accelerator facilities in the United States and around the world that are being used for space radiation health and related research, and illustrate some of their capabilities with discussions of selected accelerator experiments applicable to the human exploration of space.

  18. Proton and heavy ion acceleration facilities for space radiation research.

    PubMed

    Miller, Jack

    2003-06-01

    The particles and energies commonly used for medium energy nuclear physics and heavy charged particle radiobiology and radiotherapy at particle accelerators are in the charge and energy range of greatest interest for space radiation health. In this article we survey some of the particle accelerator facilities in the United States and around the world that are being used for space radiation health and related research, and illustrate some of their capabilities with discussions of selected accelerator experiments applicable to the human exploration of space. PMID:12959128

  19. A review of accelerator concepts for the Advanced Hydrotest Facility

    SciTech Connect

    Toepfer, A.J.

    1998-08-01

    The Advanced Hydrotest Facility (AHF) is a facility under consideration by the Department of Energy (DOE) for conducting explosively-driven hydrodynamic experiments. The major diagnostic tool at AHF will be a radiography accelerator having radiation output capable of penetrating very dense dynamic objects on multiple viewing axes with multiple pulses on each axis, each pulse having a time resolution capable of freezing object motion ({approx}50-ns) and achieving a spatial resolution {approx}1 mm at the object. Three accelerator technologies are being considered for AHF by the DOE national laboratories at Los Alamos (LANL), Livermore (LLNL), and Sandia (SNL). Two of these are electron accelerators that will produce intense x-ray pulses from a converter target yielding a dose {approx}1,000--2,000 Rads {at} 1 meter. LLNL has proposed a 16--20 MeV, 3--6 kA linear induction accelerator (LIA) driven by FET-switched modulators driving metglas loaded cavities. SNL has proposed a 12-MeV, 40-kA Inductive Voltage Adder (IVA) accelerator based on HERMES III pulsed power technology. The third option is a 25--50-GeV proton accelerator capable of {approx}10{sup 13} protons/pulse proposed by LANL. This paper will review the current status of the three accelerator concepts for AHF.

  20. Studies of multipass beam breakup and energy recovery using the CEBAF injector linac

    SciTech Connect

    Sereno, N.S.; Cardman, L.S.; Krafft, G.A.; Sinclair, C.K.; Bisognano, J.J.

    1993-06-01

    Beam breakup (BBU) instabilities in superconducting linacs are a significant issue due to the potentially high Q values of the cavity higher order modes (HOMs). The CEBAF accelerator, which employs high CW current and 5-pass recirculation through two superconducting linacs, poses unique instability problems. An experimental investigation of multipass BBU along with energy recovery has been completed using a single recirculation through the CEBAF injector linac. Experimental results are compared with computer simulation of multipass BBU.

  1. View of new centrifuge at Flight Acceleration Facility

    NASA Technical Reports Server (NTRS)

    1966-01-01

    View of the new centrifuge at the Manned Spacecraft Center (MSC), located in the Flight Acceleration Facility, bldg 29. The 50-ft. arm can swing the three man gondola to create g-forces astronauts will experience during controlled flight and during reentry. The centrifuge was designed primarily for training Apollo astronauts.

  2. Data handling facility for the Sandia Particle Beam Fusion Accelerator

    SciTech Connect

    Boyer, W. B.; Neau, E. L.

    1980-01-01

    This paper describes an on-line data handling facility for Sandia's Particle Beam Fusion Accelerator, PBFA-I, and the upgrade prototype machine Supermite. These accelerators are used for research on inertial confinement fusion (ICF) using particle beams. The main objectives in designing the data acquisition system were: (1) process both experiment and machine performance diagnostic signals, (2) record high signal-to-noise ratio, wideband waveforms in a severe EMP environment, (3) support multiple users recording and analyzing data simultaneously, and (4) provide fast turnaround for experimental results. Commercially available equipment is used wherever possible. However, several special purpose devices were developed. This data handling facility is a significant upgrade of an existing system that supports other Sandia particle beam fusion research accelerators.

  3. Commissioning of the Digital LLRF for CEBAF Injector/Separator

    SciTech Connect

    Tomasz Plawski; Hai Dong; J. Hovater; George Lahti; Lawrence King; John Musson

    2006-08-16

    The design and production of the 499 MHz digital Low-Level RF control system for the CEBAF accelerator has been completed. The first five systems have been installed for use with the CEBAF Separator RF deflecting cavities operating at 499 MHz. The next four systems were installed in the injector on the chopping cavities (also 499 MHz deflecting cavities). The new LLRF system replaced an analog system that was over 15 years old. For initial testing, an extensive acceptance plan along with a LLRF test stand was developed and incorporated to assure system performance as well as reliability. Various VHDL firmware was developed to support operation of this system and included specific operational diagnostics. Once the acceptance tests were completed, the new systems were installed in the accelerator in parallel with the existing analog LLRF for extensive in-situ testing and comparison. Once commissioned,, the new RF systems were assigned to the CEBAF accelerator and turned over to Accelerator Operations. This paper will address the VHDL firmware evolution, the automated tests, and the performance measurements made throughout the installation and commissioning process.

  4. The BNL Accelerator Test Facility and experimental program

    SciTech Connect

    Ben-Zvi, I. |

    1992-09-01

    The Accelerator Test Facility (ATF) at BNL is a users` facility for experiments in Accelerator and Beam Physics. The ATF provides high brightness electron beams and high-power laser pulses synchronized to the electron beam, suitable for studies of new methods of high-gradient acceleration and state-of-the-art Free-Electron Lasers. The electrons are produced by a laser photocathode rf gun and accelerated to 50 MeV by two traveling wave accelerator sections. The lasers include a 10 mJ, 10 ps ND:YAG laser and a 500 mJ, 10 to 100 ps C0{sub 2} laser. A number of users from National Laboratories, universities and industry take part in experiments at the ATF. The experimental program includes various laser acceleration schemes, Free-Electron Laser experiments and a program on the development of high-brightness electron beams. The ATF`s experimental program commenced in early 1991 at an energy of about 4 MeV. The full program, with 50 MeV and the high-power laser will begin operation this year.

  5. The BNL Accelerator Test Facility and experimental program

    SciTech Connect

    Ben-Zvi, I. State Univ. of New York, Stony Brook, NY . Dept. of Physics)

    1992-01-01

    The Accelerator Test Facility (ATF) at BNL is a users' facility for experiments in Accelerator and Beam Physics. The ATF provides high brightness electron beams and high-power laser pulses synchronized to the electron beam, suitable for studies of new methods of high-gradient acceleration and state-of-the-art Free-Electron Lasers. The electrons are produced by a laser photocathode rf gun and accelerated to 50 MeV by two traveling wave accelerator sections. The lasers include a 10 mJ, 10 ps ND:YAG laser and a 500 mJ, 10 to 100 ps C0{sub 2} laser. A number of users from National Laboratories, universities and industry take part in experiments at the ATF. The experimental program includes various laser acceleration schemes, Free-Electron Laser experiments and a program on the development of high-brightness electron beams. The ATF's experimental program commenced in early 1991 at an energy of about 4 MeV. The full program, with 50 MeV and the high-power laser will begin operation this year.

  6. RF Power Upgrade for CEBAF at Jefferson Laboratory

    SciTech Connect

    Andrew Kimber,Richard Nelson

    2011-03-01

    Jefferson Laboratory (JLab) is currently upgrading the 6GeV Continuous Electron Beam Accelerator Facility (CEBAF) to 12GeV. As part of the upgrade, RF systems will be added, bringing the total from 340 to 420. Existing RF systems can provide up to 6.5 kW of CW RF at 1497 MHZ. The 80 new systems will provide increased RF power of up to 13 kW CW each. Built around a newly designed and higher efficiency 13 kW klystron developed for JLab by L-3 Communications, each new RF chain is a completely revamped system using hardware different than our present installations. This paper will discuss the main components of the new systems including the 13 kW klystron, waveguide isolator, and HV power supply using switch-mode technology. Methodology for selection of the various components and results of initial testing will also be addressed. Notice: Authored by Jefferson Science Associates, LLC under U.S. DOE Contract No. DE-AC05-06OR23177. The U.S. Government retains a non-exclusive, paid-up, irrevocable, world-wide license to publish or reproduce this manuscript for U.S. Government purposes.

  7. The (. gamma. ,K) program: A new CEBAF initiative for the study of nuclear strangeness

    SciTech Connect

    Chrien, R.E.; Hungerford, E.V.

    1987-06-01

    This paper is a summary of the CEBAF working group discussions on electromagnetic production of strangeness in nuclear systems. A review of the recent BNL results in (..pi..,K) is presented as representative of the physics questions that could be addressed with the CEBAF facility. Recommendations of the working group concerning the necessary experimental apparatus for a (e,e',K) program are presented. 13 figs., 2 tabs.

  8. Baseline measurements of terrestrial gamma radioactivity at the CEBAF site

    SciTech Connect

    Wollenberg, H.A.; Smith, A.R.

    1991-10-01

    A survey of the gamma radiation background from terrestrial sources was conducted at the CEBAF site, Newport News, Virginia, on November 12--16, 1990, to provide a gamma radiation baseline for the site prior to the startup of the accelerator. The concentrations and distributions of the natural radioelements in exposed soil were measured, and the results of the measurements were converted into gamma-ray exposure rates. Concurrently, samples were collected for laboratory gamma spectral analyses.

  9. Los Alamos High-Brightness Accelerator FEL (HIBAF) facility

    SciTech Connect

    Cornelius, W.D.; Bender, S.; Meier, K.; Thode, L.E.; Watson, J.M.

    1989-01-01

    The 10-/mu/m Los Alamos free-electron laser (FEL) facility is being upgraded. The conventional electron gun and bunchers have been replaced with a much more compact 6-MeV photoinjector accelerator. By adding existing parts from previous experiments, the primary beam energy will be doubled to 40 MeV. With the existing 1-m wiggler (/lambda//sub w/ = 2.7 cm) and resonator, the facility can produce photons with wavelengths from 3 to 100 /mu/m when lasing on the fundamental mode and produce photons in the visible spectrum with short-period wigglers or harmonic operation. After installation of a 150/degree/ bend, a second wiggler will be added as an amplifier. The installation of laser transport tubes between the accelerator vault and an upstairs laboratory will provide experimenters with a radiation-free environment for experiments. Although the initial experimental program of the upgraded facility will be to test the single accelerator-master oscillator/power amplifier configuration, some portion of the operational time of the facility can be dedicated to user experiments. 13 refs., 5 figs., 6 tabs.

  10. Overview and Lessons Learned of the Jefferson Lab Cryomodule Production for the CEBAF 12 GeV Upgrade

    SciTech Connect

    Hogan, John P.; Burrill, Andrew B.; Drury, Michael A.; Harwood, Leigh H.; Hovater, J. Curt; Reece, Charles E.; Wiseman, Mark A.

    2013-12-01

    The Continuous Electron Beam Accelerator Facility (CEBAF) at Jefferson Lab is nearing completion of an energy upgrade from 6 to 12 GeV. An integral part of the upgrade is the addition of ten new cryomodules, each consisting of eight seven-cell superconducting radio-frequency (SRF) cavities. An average performance of 100+MV of acceleration per cryomodule is needed to achieve the 12 GeV beam energy goal. The production methodology was for industry to provide and deliver the major components to Jefferson Lab, where they were tested and assembled into cryomodules. The production process begins with an inspection upon receiving of all major components followed by individual performance qualification testing. The SRF cavities received their final chemical processing and cleaning at Jefferson Lab. The qualified components along with all associated hardware and instrumentation are assembled, tested, installed into CEBAF and run through an integrated system checkout in preparation for beam operations. The production process is complete and one of the first completed cryomodules has successfully produced 108 MV of acceleration with a linac beam current of 465 {micro}A.

  11. The Brookhaven National Laboratory (BNL) Accelerator Test Facility

    SciTech Connect

    Batchelor, K.

    1990-01-01

    The design of the Brookhaven National Laboratory Accelerator Test Facility is presented including the design goals and computational results. The heart of the system is a radiofrequency electron gun utilizing a photo-excited metal cathode followed by a conventional electron linac. The Nd:YAG laser used to drive the cathode with 6 ps long pulses can be synchronized to a high peak power CO{sub 2} laser in order to study laser acceleration of electrons. Current operational status of the project will be presented along with early beam tests.

  12. TAC Proton Accelerator Facility: The Status and Road Map

    SciTech Connect

    Algin, E.; Akkus, B.; Caliskan, A.; Yilmaz, M.; Sahin, L.

    2011-06-28

    Proton Accelerator (PA) Project is at a stage of development, working towards a Technical Design Report under the roof of a larger-scale Turkish Accelerator Center (TAC) Project. The project is supported by the Turkish State Planning Organization. The PA facility will be constructed in a series of stages including a 3 MeV test stand, a 55 MeV linac which can be extended to 100+ MeV, and then a full 1-3 GeV proton synchrotron or superconducting linac. In this article, science applications, overview, and current status of the PA Project will be given.

  13. Upgrade of CEBAF from 6 Gev To 12 Gev: Status

    SciTech Connect

    Harwood, Leigh

    2013-04-19

    The CEBAF accelerator is being upgraded from 6 GeV to 12 GeV by the US Department of Energy. The accelerator upgrade is being done within the existing tunnel footprint. The accelerator upgrade includes: 10 new srfbased high-performance cryomodules plus RF systems, doubling the 2K helium plant's capability, upgrading the existing beamlines to operate at nearly double the original performance envelope, and adding a beamline to a new experimental area. Construction is over 75% complete with final completion projected for late FY13. Details of the upgrade and status of the work will be presented.

  14. A new electron accelerator facility for commercial and educational uses

    NASA Astrophysics Data System (ADS)

    Uribe, R. M.; Vargas-Aburto, C.

    2001-07-01

    A 5 MeV 150 kW electron accelerator facility (NEO Beam Alliance Inc.) has recently initiated operations in Ohio. NEO Beam is the result of a "partnership" between Kent State University (KSU) and a local plastics company (Mercury Plastics, Inc.). The accelerator will be used for electron beam processing, and for educational activities. KSU has created a university-wide Program on Electron Beam Technology (EBT) to address both instructional (including workforce training and development) and research opportunities. In this work, a description is made of the facility and its genesis. Present curricular initiatives are described. Preliminary dosimetry measurements performed with radiochromic (RC) dye films, calorimeters, and alanine pellets are presented and discussed.

  15. Vibrational measurement for commissioning SRF Accelerator Test Facility at Fermilab

    SciTech Connect

    McGee, M.W.; Leibfritz, J.; Martinez, A.; Pischalnikov, Y.; Schappert, W.; /Fermilab

    2011-03-01

    The commissioning of two cryomodule components is underway at Fermilab's Superconducting Radio Frequency (SRF) Accelerator Test Facility. The research at this facility supports the next generation high intensity linear accelerators such as the International Linear Collider (ILC), a new high intensity injector (Project X) and other future machines. These components, Cryomodule No.1 (CM1) and Capture Cavity II (CC2), which contain 1.3 GHz cavities are connected in series in the beamline and through cryogenic plumbing. Studies regarding characterization of ground motion, technical and cultural noise continue. Mechanical transfer functions between the foundation and critical beamline components have been measured and overall system displacement characterized. Baseline motion measurements given initial operation of cryogenic, vacuum systems and other utilities are considered.

  16. The target laboratory of the Pelletron Accelerator's facilities

    SciTech Connect

    Ueta, Nobuko; Pereira Engel, Wanda Gabriel

    2013-05-06

    A short report on the activities developed in the Target Laboratory, since 1970, will be presented. Basic target laboratory facilities were provided to produce the necessary nuclear targets as well as the ion beam stripper foils. Vacuum evaporation units, a roller, a press and an analytical balance were installed in the Oscar Sala building. A brief historical report will be presented in commemoration of the 40{sup th} year of the Pelletron Accelerator.

  17. The target laboratory of the Pelletron Accelerator's facilities

    NASA Astrophysics Data System (ADS)

    Ueta, Nobuko; Pereira Engel, Wanda Gabriel

    2013-05-01

    A short report on the activities developed in the Target Laboratory, since 1970, will be presented. Basic target laboratory facilities were provided to produce the necessary nuclear targets as well as the ion beam stripper foils. Vacuum evaporation units, a roller, a press and an analytical balance were installed in the Oscar Sala building. A brief historical report will be presented in commemoration of the 40th year of the Pelletron Accelerator.

  18. Dielectric Wakefield Accelerator Experiments at the SABER Facility

    SciTech Connect

    Kanareykin, A.; Thompson, M.C.; Berry, M.K.; Blumenfeld, I.; Decker, F.J.; Hogan, M.J.; Ischebeck, R.; Iverson, R.H.; Kirby, N.A.; Siemann, Robert H.; Walz, D.R.; Badakov, H.; Cook, A.M.; Rosenzweig, J.B.; Tikhoplav, R.; Travish, G.; Muggli, P.; /Southern California U.

    2008-01-28

    Electron bunches with the unparalleled combination of high charge, low emittances, and short time duration, as first produced at the SLAC Final Focus Test Beam (FFTB), are foreseen to be produced at the SABER facility. These types of bunches have enabled wakefield driven accelerating schemes of multi-GV/m in plasmas. In the context of the Dielectric Wakefield Accelerators (DWA) such beams, having rms bunch length as short as 20 um, have been used to drive 100 um and 200 um ID hollow tubes above 20 GV/m surface fields. These FFTB tests enabled the measurement of a breakdown threshold in fused silica (with full data analysis still ongoing) [1]. With the construction and commissioning of the SABER facility at SLAC, new experiments would be made possible to test further aspects of DWAs including materials, tube geometrical variations, direct measurements of the Cerenkov fields, and proof of acceleration in tubes >10 cm in length. This collaboration will investigate breakdown thresholds and accelerating fields in new materials including CVD diamond. Here we describe the experimental plans, beam parameters, simulations, and progress to date as well as future prospects for machines based of DWA structures.

  19. Vibrational Stability of SRF Accelerator Test Facility at Fermilab

    SciTech Connect

    McGee, M.W.; Volk, J.T.; /Fermilab

    2009-05-01

    Recently developed, the Superconducting Radio Frequency (SRF) Accelerator Test Facilities at Fermilab support the International Linear Collider (ILC), High Intensity Neutrino Source (HINS), a new high intensity injector (Project X) and other future machines. These facilities; Meson Detector Building (MDB) and New Muon Lab (NML) have very different foundations, structures, relative elevations with respect to grade level and surrounding soil composition. Also, there are differences in the operating equipment and their proximity to the primary machine. All the future machines have stringent operational stability requirements. The present study examines both near-field and ambient vibration in order to develop an understanding of the potential contribution of near-field sources (e.g. compressors, ultra-high and standard vacuum equipment, klystrons, modulators, utility fans and pumps) and distant noise sources to the overall system displacements. Facility vibration measurement results and methods of possible isolation from noise sources are presented and discussed.

  20. RF Design Optimization for New Injector Cryounit at CEBAF

    SciTech Connect

    Wang, Haipeng; Cheng, Guangfeng; Hannon, Fay E.; Hofler, Alicia S.; Kazimi, Reza; Preble, Joe; Rimmer, Robert A.

    2013-06-01

    A new injector superconducting RF (SRF) cryounit with one new 2-cell, B=0.6 cavity plus one refurbished 7-cell, B=0.97, C100 style cavity has been re-designed and optimized for the engineering compatibility of existing module for CEBAF operation. The optimization of 2-cell cavity shape for longitudinal beam dynamic of acceleration from 200keV to 533keV and the minimization of transverse kick due to the waveguide couplers to less than 1 mrad have been considered. Operating at 1497MHz, two cavities has been designed into a same footprint of CEBAF original quarter cryomodule to deliver an injection beam energy of 5MeV in less than 0.27{degree} rms bunch length and a maximum energy spread of 5keV.

  1. The Stanford Linear Accelerator Center pulsed x-ray facility.

    PubMed

    Ipe, N E; McCall, R C; Baker, E D

    1987-04-01

    The Stanford Linear Accelerator Center (SLAC) operates a high-energy (up to 33 GeV) linear accelerator delivering pulses up to a few microseconds wide. The pulsed nature of the electron beam creates problems in the detection and measurement of radiation both from the accelerator beam and the klystrons that provide the radio-frequency power for the accelerator. Hence, a pulsed x-ray facility has been built at SLAC mainly for testing the response of different radiation detection instruments to pulsed radiation fields. The x-ray tube consists of an electron gun with a control grid. This provides a stream of pulsed electrons that can be accelerated towards a confined target window. The window consists of Al 0.051 cm (20 mils) thick, plated on the vacuum side with a layer of Au 0.0006 cm (1/4 mil) thick. The frequency of electron pulses can be varied by an internal pulser from 60 to 360 pulses per second with pulse widths of 360 ns to 5 microseconds. The pulse amplitude can be varied over a wide range of currents. An external pulser can be used to obtain other frequencies or special pulse shapes. The voltage across the gun can be varied from 0 to 100 kV. The maximum absorbed dose rate obtained at 6.35 cm below the target window as measured by an ionization chamber is 258 Gy/h. The major part of the x-ray tube is enclosed in a large walk-in cabinet made of 1.9-cm-thick (3/4-inch-thick) plywood and lined with 0.32-cm-thick (1/8-inch-thick) Pb to make a very versatile facility. PMID:3570789

  2. Workshop on CEBAF at higher energies

    SciTech Connect

    Isgur, N.; Stoler, P.

    1994-04-01

    Since the current parameters of CEBAF were defined almost a decade ago, there has been a remarkably fruitful evolution of our picture of the behavior of strongly interacting matter that apparently could be addressed by CEBAF at higher energies. Favorable technical developments coupled with foresight in initial laboratory planning have now made it feasible to consider approximately doubling CEBAF`s current design energy of 4 GeV to approach 10 GeV at rather modest cost. The purpose of the workshop, sponsored by the CEBAF User Group, was to begin to develop the next phase of CEBAF`s program by giving the entire community the opportunity to participate in defining the future of our field, and in particular the physics accessible with an upgraded CEBAF energy. It is intended that this report mark the first step toward an ultimate goal of defining a physics program that will form the basis for an upgrade of CEBAF. The report begins with a brief overview of the workshop`s conclusions. Its body consists of sections corresponding to the workshop`s Working Groups on Hadron Spectroscopy and Production, High Q{sup 2} Form Factors and Exclusive Reactions, Inclusive and Semi-Inclusive Processes, and Hadrons in the Nuclear Medium. Each section begins with the working group summaries and is followed by associated plenary talks summarizing the outstanding physics issues addressable by an upgrade, which are in turn followed by individual contributions presenting specific physics programs. An appendix describes capabilities of CEBAF`s current experimental equipment at higher energies; another appendix lists workshop participants. Selected papers have been processed separately for inclusion in the Energy Science and Technology Database.

  3. Novel neutron sources at the Radiological Research Accelerator Facility.

    PubMed

    Xu, Yanping; Garty, Guy; Marino, Stephen A; Massey, Thomas N; Randers-Pehrson, Gerhard; Johnson, Gary W; Brenner, David J

    2012-03-16

    Since the 1960s, the Radiological Research Accelerator Facility (RARAF) has been providing researchers in biology, chemistry and physics with advanced irradiation techniques, using charged particles, photons and neutrons.We are currently developing a unique facility at RARAF, to simulate neutron spectra from an improvised nuclear device (IND), based on calculations of the neutron spectrum at 1.5 km from the epicenter of the Hiroshima atom bomb. This is significantly different from a standard fission spectrum, because the spectrum changes as the neutrons are transported through air, and is dominated by neutron energies between 0.05 and 8 MeV. This facility will be based on a mixed proton/deuteron beam impinging on a thick beryllium target.A second, novel facility under development is our new neutron microbeam. The neutron microbeam will, for the first time, provide a kinematically collimated neutron beam, 10-20 micron in diameter. This facility is based on a Proton Microbeam, impinging on a thin lithium target near the threshold of the (7)Li(p,n)(7)Be reaction. This novel neutron microbeam will enable studies of neutron damage to small targets, such as single cells, individual organs within small animals or microelectronic components. PMID:22545061

  4. Novel neutron sources at the Radiological Research Accelerator Facility

    DOE PAGESBeta

    Xu, Yanping; Garty, G.; Marino, S. A.; Massey, Thomas Neal; Johnson, G. W.; Randers-Pehrson, Gerhard; Brenner, D. J.

    2012-03-16

    Since the 1960s, the Radiological Research Accelerator Facility (RARAF) has been providing researchers in biology, chemistry and physics with advanced irradiation techniques, using charged particles, photons and neutrons. We are currently developing a unique facility at RARAF, to simulate neutron spectra from an improvised nuclear device (IND), based on calculations of the neutron spectrum at 1.5 km from the epicenter of the Hiroshima atom bomb. This is significantly different from a standard fission spectrum, because the spectrum changes as the neutrons are transported through air, and is dominated by neutron energies between 0.05 and 8 MeV. This facility will bemore » based on a mixed proton/deuteron beam impinging on a thick beryllium target. A second, novel facility under development is our new neutron microbeam. The neutron microbeam will, for the first time, provide a kinematically collimated neutron beam, 10-20 micron in diameter. This facility is based on a proton microbeam, impinging on a thin lithium target near the threshold of the Li-7(p,n)Be-7 reaction. Lastly, this novel neutron microbeam will enable studies of neutron damage to small targets, such as single cells, individual organs within small animals or microelectronic components.« less

  5. Novel neutron sources at the Radiological Research Accelerator Facility

    PubMed Central

    Xu, Yanping; Garty, Guy; Marino, Stephen A.; Massey, Thomas N.; Randers-Pehrson, Gerhard; Johnson, Gary W.; Brenner, David J.

    2012-01-01

    Since the 1960s, the Radiological Research Accelerator Facility (RARAF) has been providing researchers in biology, chemistry and physics with advanced irradiation techniques, using charged particles, photons and neutrons. We are currently developing a unique facility at RARAF, to simulate neutron spectra from an improvised nuclear device (IND), based on calculations of the neutron spectrum at 1.5 km from the epicenter of the Hiroshima atom bomb. This is significantly different from a standard fission spectrum, because the spectrum changes as the neutrons are transported through air, and is dominated by neutron energies between 0.05 and 8 MeV. This facility will be based on a mixed proton/deuteron beam impinging on a thick beryllium target. A second, novel facility under development is our new neutron microbeam. The neutron microbeam will, for the first time, provide a kinematically collimated neutron beam, 10–20 micron in diameter. This facility is based on a Proton Microbeam, impinging on a thin lithium target near the threshold of the 7Li(p,n)7Be reaction. This novel neutron microbeam will enable studies of neutron damage to small targets, such as single cells, individual organs within small animals or microelectronic components. PMID:22545061

  6. Novel neutron sources at the Radiological Research Accelerator Facility

    SciTech Connect

    Xu, Yanping; Garty, G.; Marino, S. A.; Massey, Thomas Neal; Johnson, G. W.; Randers-Pehrson, Gerhard; Brenner, D. J.

    2012-03-16

    Since the 1960s, the Radiological Research Accelerator Facility (RARAF) has been providing researchers in biology, chemistry and physics with advanced irradiation techniques, using charged particles, photons and neutrons. We are currently developing a unique facility at RARAF, to simulate neutron spectra from an improvised nuclear device (IND), based on calculations of the neutron spectrum at 1.5 km from the epicenter of the Hiroshima atom bomb. This is significantly different from a standard fission spectrum, because the spectrum changes as the neutrons are transported through air, and is dominated by neutron energies between 0.05 and 8 MeV. This facility will be based on a mixed proton/deuteron beam impinging on a thick beryllium target. A second, novel facility under development is our new neutron microbeam. The neutron microbeam will, for the first time, provide a kinematically collimated neutron beam, 10-20 micron in diameter. This facility is based on a proton microbeam, impinging on a thin lithium target near the threshold of the Li-7(p,n)Be-7 reaction. Lastly, this novel neutron microbeam will enable studies of neutron damage to small targets, such as single cells, individual organs within small animals or microelectronic components.

  7. Novel neutron sources at the Radiological Research Accelerator Facility

    NASA Astrophysics Data System (ADS)

    Xu, Y.; Garty, G.; Marino, S. A.; Massey, T. N.; Randers-Pehrson, G.; Johnson, G. W.; Brenner, D. J.

    2012-03-01

    Since the 1960s, the Radiological Research Accelerator Facility (RARAF) has been providing researchers in biology, chemistry and physics with advanced irradiation techniques, using charged particles, photons and neutrons. We are currently developing a unique facility at RARAF, to simulate neutron spectra from an improvised nuclear device (IND), based on calculations of the neutron spectrum at 1.5 km from the epicenter of the Hiroshima atom bomb. This is significantly different from a standard fission spectrum, because the spectrum changes as the neutrons are transported through air, and is dominated by neutron energies between 0.05 and 8 MeV. This facility will be based on a mixed proton/deuteron beam impinging on a thick beryllium target. A second, novel facility under development is our new neutron microbeam. The neutron microbeam will, for the first time, provide a kinematically collimated neutron beam, 10-20 micron in diameter. This facility is based on a proton microbeam, impinging on a thin lithium target near the threshold of the 7Li(p,n)7Be reaction. This novel neutron microbeam will enable studies of neutron damage to small targets, such as single cells, individual organs within small animals or microelectronic components.

  8. Commissioning and operation of the CEBAF end station refrigeration system

    SciTech Connect

    Arenius, D.; Bevins, B.; Chronis, W.C.; Ganni, V.; Kashy, D.; Keesee, M.; Wilson, J. Jr.

    1996-08-01

    The CEBAF End Station Helium Refrigerator (ESR) System provides refrigeration at 80 K, 20 K and 4.5 K to three End Station experimental halls. The facility consists of a two stage helium screw compressor system, 4.5 K refrigerator, cryogen distribution valve box, and transfer lines to the individual experimental halls. The 4.5 K cold box and compressors were originally part of the ESCAR 1,500 W, 4 K refrigeration system at Lawrence Berkeley Laboratory which was first commissioned fin 1977. The compressors, 4.5 K cold box, and control system design were modified to adapt the plant for the requirements of the CEBAF experimental halls. Additional subsystems of cryogen distribution, transfer lines, warm gas management, and computer control interface were added. This paper describes the major plant subsystems, modifications, operational experiences and performance.

  9. A Tau-Charm Factory at CEBAF

    SciTech Connect

    Seth, K.K.

    1994-04-01

    It is proposed that a Tau Charm Factory represents a natural extension of CEBAF into higher energy domains. The exciting nature of the physics of charm quarks and tau leptons is briefly reviewed and it is suggested that the concept of a linac-ring collider as a Tau Charm Factory at CEBAF should be seriously studied.

  10. SATIF-2 shielding aspects of accelerators, targets and irradiation facilities

    SciTech Connect

    1995-12-31

    Particle accelerators have evolved over the last 50 years from simple devices to powerful machines, and will continue to have an important impact on research, technology and lifestyle. Today they cover a wide range of applications, from television and computer displays in households to the investigation of the origin and structure of matter. It has become common practice to use them for material science and medical applications. In recent years, requirements from new technological and research applications have emerged, such as increased particle beams intensities, higher flexibility, etc., giving rise to new radiation shielding aspects and problems. These proceedings review recent progress in radiation shielding of accelerator facilities, and evaluate advancements with respect to international co-operation in this field.

  11. Environment, safety, and health considerations for a new accelerator facility

    SciTech Connect

    J. Donald Cossairt

    2001-04-23

    A study of siting considerations for possible future accelerators at Fermilab is underway. Each candidate presents important challenges in environment, safety, and health (ES&H) that are reviewed generically in this paper. Some of these considerations are similar to those that have been encountered and solved during the construction and operation of other accelerator facilities. Others have not been encountered previously on the same scale. The novel issues will require particular attention coincident with project design efforts to assure their timely cost-effective resolution. It is concluded that with adequate planning, the issues can be addressed in a manner that merits the support of the Laboratory, the US Department of Energy (DOE), and the public.

  12. Multi-Objective Optimization of Heat Load and Run Time for CEBAF Linacs Using Genetic Algorithms

    NASA Astrophysics Data System (ADS)

    Reeves, Cody; Terzic, Balsa; Hofler, Alicia

    2014-09-01

    The Continuous Electron Beam Accelerator Facility (CEBAF) consists of two linear accelerators (Linacs) connected by arcs. Within each Linac, there are 200 niobium cavities that use superconducting radio frequency (SRF) to accelerate electrons. The gradients for the cavities are selected to optimize two competing objectives: heat load (the energy required to cool the cavities) and trip rate (how often the beam turns off within an hour). This results in a multidimensional, multi-objective, nonlinear system of equations that is not readily solved by analytical methods. This study improved a genetic algorithm (GA), which applies the concept of natural selection. The primary focus was making this GA more efficient to allow for more cost-effective solutions in the same amount of computation time. Two methods used were constraining the maximum value of the ob-jectives and also utilizing previously simulated solutions as the initial generation. A third method of interest involved refining the GA by combining the two objectives into a single weighted-sum objective, which collapses the set of optimal solutions into a single point. By combining these methods, the GA can be made 128 times as effective, reducing computation time from 30 min to 12 sec. This is crucial for when a cavity must be turned off, a new solution needs to be computed quickly. This work is of particular interest since it provides an efficient algorithm that can be easily adapted to any Linac facility.

  13. Performance Evaluation Of An Irradiation Facility Using An Electron Accelerator

    NASA Astrophysics Data System (ADS)

    Uribe, R. M.; Filppi, E.; Hullihen, K.

    2011-06-01

    Irradiation parameters over a period of seven years have been evaluated for a radiation processing electron accelerator facility. The parameters monitored during this time were the electron beam energy, linearity of beam current, linearity of dose with the reciprocal value of the samples speed, and dose uniformity along the scanning area after a maintenance audit performed by the electron accelerator manufacturer. The electron energy was determined from the depth-dose curve by using a two piece aluminum wedge and measuring the practical range from the obtained curves. The linearity of dose with beam current, and reciprocal value of the speed and dose uniformity along the scanning area of the electron beam were determined by measuring the dose under different beam current and cart conveyor speed conditions using film dosimetry. The results of the experiments have shown that the energy in the range from 1 to 5 MeV has not changed by more than 15% from the High Voltage setting of the machine over the evaluation period, and dose linearity with beam current and cart conveyor speed has not changed. The dose uniformity along the scanning direction of the beam showed a dose uniformity of 90% or better for energies between 2 and 5 MeV, however for 1 MeV electrons this value was reduced to 80%. This parameter can be improved by changing the beam optics settings in the control console of the accelerator though.

  14. Accelerator shield design of KIPT neutron source facility

    SciTech Connect

    Zhong, Z.; Gohar, Y.

    2013-07-01

    Argonne National Laboratory (ANL) of the United States and Kharkov Institute of Physics and Technology (KIPT) of Ukraine have been collaborating on the design development of a neutron source facility at KIPT utilizing an electron-accelerator-driven subcritical assembly. Electron beam power is 100 kW, using 100 MeV electrons. The facility is designed to perform basic and applied nuclear research, produce medical isotopes, and train young nuclear specialists. The biological shield of the accelerator building is designed to reduce the biological dose to less than 0.5-mrem/hr during operation. The main source of the biological dose is the photons and the neutrons generated by interactions of leaked electrons from the electron gun and accelerator sections with the surrounding concrete and accelerator materials. The Monte Carlo code MCNPX serves as the calculation tool for the shield design, due to its capability to transport electrons, photons, and neutrons coupled problems. The direct photon dose can be tallied by MCNPX calculation, starting with the leaked electrons. However, it is difficult to accurately tally the neutron dose directly from the leaked electrons. The neutron yield per electron from the interactions with the surrounding components is less than 0.01 neutron per electron. This causes difficulties for Monte Carlo analyses and consumes tremendous computation time for tallying with acceptable statistics the neutron dose outside the shield boundary. To avoid these difficulties, the SOURCE and TALLYX user subroutines of MCNPX were developed for the study. The generated neutrons are banked, together with all related parameters, for a subsequent MCNPX calculation to obtain the neutron and secondary photon doses. The weight windows variance reduction technique is utilized for both neutron and photon dose calculations. Two shielding materials, i.e., heavy concrete and ordinary concrete, were considered for the shield design. The main goal is to maintain the total

  15. Large-Volume Resonant Microwave Discharge for Plasma Cleaning of a CEBAF 5-Cell SRF Cavity

    SciTech Connect

    J. Mammosser, S. Ahmed, K. Macha, J. Upadhyay, M. Nikoli, S. Popovi, L. Vuakovi

    2012-07-01

    We report the preliminary results on plasma generation in a 5-cell CEBAF superconducting radio-frequency (SRF) cavity for the application of cavity interior surface cleaning. CEBAF currently has {approx}300 of these five cell cavities installed in the Jefferson Lab accelerator which are mostly limited by cavity surface contamination. The development of an in-situ cavity surface cleaning method utilizing a resonant microwave discharge could lead to significant CEBAF accelerator performance improvement. This microwave discharge is currently being used for the development of a set of plasma cleaning procedures targeted to the removal of various organic, metal and metal oxide impurities. These contaminants are responsible for the increase of surface resistance and the reduction of RF performance in installed cavities. The CEBAF five cell cavity volume is {approx} 0.5 m2, which places the discharge in the category of large-volume plasmas. CEBAF cavity has a cylindrical symmetry, but its elliptical shape and transversal power coupling makes it an unusual plasma application, which requires special consideration of microwave breakdown. Our preliminary study includes microwave breakdown and optical spectroscopy, which was used to define the operating pressure range and the rate of removal of organic impurities.

  16. Defocusing beam line design for an irradiation facility at the TAEA SANAEM Proton Accelerator Facility

    NASA Astrophysics Data System (ADS)

    Gencer, A.; Demirköz, B.; Efthymiopoulos, I.; Yiğitoğlu, M.

    2016-07-01

    Electronic components must be tested to ensure reliable performance in high radiation environments such as Hi-Limu LHC and space. We propose a defocusing beam line to perform proton irradiation tests in Turkey. The Turkish Atomic Energy Authority SANAEM Proton Accelerator Facility was inaugurated in May 2012 for radioisotope production. The facility has also an R&D room for research purposes. The accelerator produces protons with 30 MeV kinetic energy and the beam current is variable between 10 μA and 1.2 mA. The beam kinetic energy is suitable for irradiation tests, however the beam current is high and therefore the flux must be lowered. We plan to build a defocusing beam line (DBL) in order to enlarge the beam size, reduce the flux to match the required specifications for the irradiation tests. Current design includes the beam transport and the final focusing magnets to blow up the beam. Scattering foils and a collimator is placed for the reduction of the beam flux. The DBL is designed to provide fluxes between 107 p /cm2 / s and 109 p /cm2 / s for performing irradiation tests in an area of 15.4 cm × 21.5 cm. The facility will be the first irradiation facility of its kind in Turkey.

  17. The Status of Turkish Accelerator Center Test Facility

    SciTech Connect

    Yavas, Oe.

    2007-04-23

    Recently, conceptual design of Turkic Accelerator Center (TAC) proposal was completed. Main goal of this proposal is a charm factory that consists of a linac-ring type electron-positron collider. In addition, synchrotron radiation from the positron ring and free electron laser from the electron linac are proposed. The project related with this proposal has been accepted by Turkish government. It is planned that the Technical Design Report of TAC will have been written in next three years. In this period, an infrared oscillator free electron laser (IR FEL) will be constructed as a test facility for TAC. 20 and 50 MeV electron energies will be used to obtain infra red free electron laser. The main parameters of the electron linac, the optical cavities and the free electron laser were determined. The possible use of obtained laser beam in basic and applied research areas such as biotechnology, nanotechnology, semiconductors and photo chemistry were stated.

  18. CEBAF NEW DIGITAL LLRF SYSTEM EXTENDED FUNCTIONALITY

    SciTech Connect

    T. Allison; K. Davis; H. Dong; C. Hovater; L. King; J. Musson; T. Plawski

    2007-06-18

    The new digital LLRF system for the CEBAF 12GeV accelerator will perform a variety of tasks, beyond field control [1]. In this paper we present the superconducting cavity resonance control system designed to minimize RF power during gradient ramp and to minimize RF power during steady state operation. Based on the calculated detuning angle, which represents the difference between reference and cavity resonance frequency, the cavity length will be adjusted with a mechanical tuner. The tuner has two mechanical driving devices, a stepper motor and a piezo-tuner, to yield a combination of coarse and fine control. Although LLRF piezo processing speed can achieve 10 kHz bandwidth, only 10 Hz speed is needed for 12 GeV upgrade. There will be a number of additional functions within the LLRF system; heater controls to maintain cryomodule's heat load balance, ceramic window temperature monitoring, waveguide vacuum interlocks, ARC detector interlock and quench detection. The additional functions will be divided between the digital board, incorporating an Altera FPGA and an embedded EPICS IOC. This paper will also address hardware evolution and test results performed with different SC cavities.

  19. CEBAF at higher energies: Working group report on hadron spectroscopy and production

    SciTech Connect

    Barnes, T. |; Napolitano, J.

    1994-04-01

    This report summarizes topics in hadron spectroscopy and production which could be addressed at CEBAF with an energy upgrade to E{sub {gamma}} = 8 GeV and beyond. The topics discussed include conventional meson and baryon spectrocopy, spectroscopy of exotica (especially molecules and hybrids), CP and CPT tests using {phi} mesons, and new detector and accelerator options.

  20. Treatment Facility F: Accelerated Removal and Validation Project

    SciTech Connect

    Sweeney, J.J.; Buettner, M.H.; Carrigan, C.R.

    1994-04-01

    The Accelerated Removal and Validation (ARV) phase of remediation at the Treatment Facility F (TFF) site at Lawrence Livermore National Laboratory (LLNL) was designed to accelerate removal of gasoline from the site when compared to normal, single shift, pump-and-treat operations. The intent was to take advantage of the in-place infrastructure plus the increased underground temperatures resulting from the Dynamic Underground Stripping Demonstration Project (DUSDP). Operations continued 24-hours (h) per day between October 4 and December 12, 1993. Three contaminant removal rate enhancement approaches were explored during the period of continuous operation. First, we tried several configurations of the vapor pumping system to maximize the contaminant removal rate. Second, we conducted two brief trials of air injection into the lower steam zone. Results were compared with computer models, and the process was assessed for contaminant removal rate enhancement. Third, we installed equipment to provide additional electrical heating of contaminated low-permeability soil. Four new electrodes were connected into the power system. Diagnostic capabilities at the TFF site were upgraded so that we could safely monitor electrical currents, soil temperatures, and water treatment system processes while approximately 300 kW of electrical energy was being applied to the subsurface.

  1. PHYSICS WITH A FOCAL PLANE PROTON POLARIMETER FOR HALL A AT CEBAF

    SciTech Connect

    Ron Gilman; F.T. Baker; Louis Bimbot; Ed Brash; Charles Glashausser; Mark Jones; Gerfried Kumbartzki; Sirish Nanda; Charles F. Perdrisat; Vina Punjabi; Ronald Ransome; Paul Rutt

    1994-09-01

    A focal plane polarimeter intended for the CEBAF Hall A high resolution hadron spectrometer is under construction at Rutgers University and the College of William and Mary. Experiments with focal plane polarimeters are only now beginning at electron accelerators; they play a prominent role in the list of approved experiments for Hall A. Construction of the polarimeter is in progress, it is expected to be brought to CEBAF in spring 1995. Several coincidence (e,e'p) and singles (gamma, p) measurements by the Hall A Collaboration are expected to start in 1996. In this paper we describe the polarimeter and the physics program planned for it.

  2. Performance Evaluation of Undulator Radiation at CEBAF

    SciTech Connect

    Chuyu Liu, Geoffrey Krafft, Guimei Wang

    2010-05-01

    The performance of undulator radiation (UR) at CEBAF with a 3.5 m helical undulator is evaluated and compared with APS undulator-A radiation in terms of brilliance, peak brilliance, spectral flux, flux density and intensity distribution.

  3. Proposed Dark Current Studies at the Argonne Wakefield Accelerator Facility

    SciTech Connect

    Antipov, S.P.; Conde, Manoel Eduardo; Gai, Wei; Power, John Gorham; Yusof, Z.M.; Spentzouris, L.K.; Dolgashev, V.A.; /SLAC

    2008-01-18

    A study of dark currents has been initiated at the Argonne Wakefield Accelerator Facility (AWA). Emission of dark current is closely related to a breakdown. Breakdown may include several factors such as local field enhancement, explosive electron emission, Ohmic heating, tensile stress produced by electric field, and others. The AWA is building a dedicated facility to test various models for breakdown mechanisms and to determine the roles of different factors in the breakdown. An imaging system is being put together to identify single emitters on the cathode surface. This will allow us to study dark current properties in the gun. We also plan to trigger breakdown events with a high-powered laser at various wavelengths (IR to UV). Another experimental idea follows from the recent work on a Schottky-enabled photoemission in an RF photoinjector that allows us to determine in situ the field enhancement factor on a cathode surface. Monitoring the field enhancement factor before and after can shed some light on a modification of metal surface after the breakdown.

  4. A New RF System for the CEBAF Normal Conducting Cavities

    SciTech Connect

    Curt Hovater; Hai Dong; Alicia Hofler; George Lahti; John Musson; Tomasz Plawski

    2004-08-01

    The CEBAF Accelerator at Jefferson Lab is a 6 GeV five pass electron accelerator consisting of two superconducting linacs joined by independent magnetic transport arcs. CEBAF also has numerous normal conducting cavities for beam conditioning in the injector and for RF extraction to the experimental halls. The RF systems that presently control these cavities are becoming expensive to maintain, therefore a replacement RF control system is now being developed. For the new RF system, cavity field control is maintained digitally using an FPGA which contains the feedback algorithm. The system incorporates digital down conversion, using quadrature under-sampling at an IF frequency of 70 MHz. The VXI bus-crate was chosen as the operating platform because of its excellent RFI/EMI properties and its compatibility with the EPICS control system. The normal conducting cavities operate at both the 1497 MHz accelerating frequency and the sub-harmonic frequency of 499 MHz. To accommodate this, the ne w design will use different receiver-transmitter daughter cards for each frequency. This paper discusses the development of the new RF system and reports on initial results.

  5. Accelerated radiation damage test facility using a 5 MV tandem ion accelerator

    NASA Astrophysics Data System (ADS)

    Wady, P. T.; Draude, A.; Shubeita, S. M.; Smith, A. D.; Mason, N.; Pimblott, S. M.; Jimenez-Melero, E.

    2016-01-01

    We have developed a new irradiation facility that allows to perform accelerated damage tests of nuclear reactor materials at temperatures up to 400 °C using the intense proton (<100 μA) and heavy ion (≈10 μA) beams produced by a 5 MV tandem ion accelerator. The dedicated beam line for radiation damage studies comprises: (1) beam diagnosis and focusing optical components, (2) a scanning and slit system that allows uniform irradiation of a sample area of 0.5-6 cm2, and (3) a sample stage designed to be able to monitor in-situ the sample temperature, current deposited on the sample, and the gamma spectrum of potential radio-active nuclides produced during the sample irradiation. The beam line capabilities have been tested by irradiating a 20Cr-25Ni-Nb stabilised stainless steel with a 3 MeV proton beam to a dose level of 3 dpa. The irradiation temperature was 356 °C, with a maximum range in temperature values of ±6 °C within the first 24 h of continuous irradiation. The sample stage is connected to ground through an electrometer to measure accurately the charge deposited on the sample. The charge can be integrated in hardware during irradiation, and this methodology removes uncertainties due to fluctuations in beam current. The measured gamma spectrum allowed the identification of the main radioactive nuclides produced during the proton bombardment from the lifetimes and gamma emissions. This dedicated radiation damage beam line is hosted by the Dalton Cumbrian Facility of the University of Manchester.

  6. A new AMS facility at Inter University Accelerator Centre, New Delhi

    NASA Astrophysics Data System (ADS)

    Kumar, Pankaj; Chopra, S.; Pattanaik, J. K.; Ojha, S.; Gargari, S.; Joshi, R.; Kanjilal, D.

    2015-10-01

    Inter University Accelerator Centre (IUAC), a national facility of government of India, is having a 15UD Pelletron accelerator for multidisciplinary ion beam based research programs. Recently, a new accelerator mass spectrometry (AMS) facility has been developed after incorporating many changes in the existing 15UD Pelletron accelerator. A clean chemistry laboratory for 10Be and 26Al with all the modern facilities has also been developed for the chemical processing of samples. 10Be measurements on sediment samples, inter laboratory comparison results and 26Al measurements on standard samples are presented in this paper. In addition to the 10Be and 26Al AMS facilities, a new 14C AMS facility based on a dedicated 500 kV tandem ion accelerator with two cesium sputter ion sources, is also being setup at IUAC.

  7. Laser Plasma Particle Accelerators: Large Fields for Smaller Facility Sources

    SciTech Connect

    Geddes, Cameron G.R.; Cormier-Michel, Estelle; Esarey, Eric H.; Schroeder, Carl B.; Vay, Jean-Luc; Leemans, Wim P.; Bruhwiler, David L.; Cary, John R.; Cowan, Ben; Durant, Marc; Hamill, Paul; Messmer, Peter; Mullowney, Paul; Nieter, Chet; Paul, Kevin; Shasharina, Svetlana; Veitzer, Seth; Weber, Gunther; Rubel, Oliver; Ushizima, Daniela; Bethel, Wes; Wu, John

    2009-03-20

    Compared to conventional particle accelerators, plasmas can sustain accelerating fields that are thousands of times higher. To exploit this ability, massively parallel SciDAC particle simulations provide physical insight into the development of next-generation accelerators that use laser-driven plasma waves. These plasma-based accelerators offer a path to more compact, ultra-fast particle and radiation sources for probing the subatomic world, for studying new materials and new technologies, and for medical applications.

  8. Plasma Wakefield Acceleration and FACET - Facilities for Accelerator Science and Experimental Test Beams at SLAC

    ScienceCinema

    Andrei Seryi

    2010-01-08

    Plasma wakefield acceleration is one of the most promising approaches to advancing accelerator technology. This approach offers a potential 1,000-fold or more increase in acceleration over a given distance, compared to existing accelerators.  FACET, enabled by the Recovery Act funds, will study plasma acceleration, using short, intense pulses of electrons and positrons. In this lecture, the physics of plasma acceleration and features of FACET will be presented.  

  9. Plasma Wakefield Acceleration and FACET - Facilities for Accelerator Science and Experimental Test Beams at SLAC

    SciTech Connect

    Andrei Seryi

    2009-09-09

    Plasma wakefield acceleration is one of the most promising approaches to advancing accelerator technology. This approach offers a potential 1,000-fold or more increase in acceleration over a given distance, compared to existing accelerators.  FACET, enabled by the Recovery Act funds, will study plasma acceleration, using short, intense pulses of electrons and positrons. In this lecture, the physics of plasma acceleration and features of FACET will be presented.  

  10. Application of the National Ignition Facility distinguishable-from-background program to accelerator facilities at Lawrence Livermore National Laboratory.

    PubMed

    Packard, Eric D; Mac Kenzie, Carolyn

    2013-06-01

    Lawrence Livermore National Laboratory must control potentially activated materials and equipment in accordance with U.S. Department of Energy (DOE) Order 458.1, Radiation Protection of the Public and the Environment, which requires DOE approval of the process used to release volumetrically contaminated personal property and establishes a dose constraint of 10 µSv y(-1) (1 mrem y(-1)) for clearance of such property. The National Ignition Facility at Lawrence Livermore National Laboratory developed a technical basis document and protocol for determining the radiological status of property that is potentially activated from exposure to neutron radiation produced via fusion of tritium and deuterium. The technical basis included assessment of the neutron energy, the type of materials potentially exposed and the likely activation products, and the sensitivity of radiation detectors used to survey the property. This paper evaluates the National Ignition Facility technical basis document for applicability to the release of property from Lawrence Livermore National Laboratory's various accelerator facilities considering the different types of particles accelerated, radiations produced, and resultant activation products. Extensive process knowledge regarding the accelerators' operations, accompanied by years of routine surveys, provides an excellent characterization of these facilities. Activation studies conducted at the Stanford Linear Accelerator and the High Energy Accelerator Research Organization in Japan corroborate that the long-lived radionuclides produced at accelerator facilities are of the same variety produced at the National Ignition Facility. Consequently, Lawrence Livermore National Laboratory concludes that the release protocol developed for the National Ignition Facility can be used appropriately at all its accelerator facilities. PMID:23629069

  11. Qualification and cryogenic performance of cryomodule components at CEBAF

    SciTech Connect

    Heckman, J.; Macha, K.; Fischer, J.; Folts, E.

    1996-12-31

    At CEBAF an electron beam is accelerated by superconducting resonant niobium cavities which are operated submerged in superfluid helium. The accelerator has 42 1/4 cryomodules, each containing eight cavities. The qualification and design of components for the cryomodules under went stringent testing and evaluation for acceptance. Indium wire seals are used between the cavity and helium vessel interface to make a superfluid helium leak tight seal. Each cavity is equipped with a mechanical tuner assembly designed to stretch and compress the cavities. Two rotary feedthroughs are used to operate each mechanical tuner assembly. Ceramic feedthroughs not designed for super-fluid were qualified for tuner and cryogenic instrumentation. To ensure long term integrity of the machine special attention is required for material specifications and machine processes. The following is to share the qualification methods, design and performance of the cryogenic cryomodule components.

  12. Injection Options for 12 GeV CEBAF Upgrade

    SciTech Connect

    Reza Kazimi; Jay Benesch; Yu-Chiu Chao; Joseph Grames; Geoffrey Krafft; Michael Tiefenback; Byung Yunn; Yuhong Zhang

    2005-05-01

    Jefferson Lab is planning a major upgrade of CEBAF accelerator from 6 to 12 GeV. The injection energy needs to be increased accordingly from 67 MeV to 123 MeV. While the present 100 keV electron gun and beam formation up to 5 MeV would remain unchanged, the accelerating SRF modules in the current injector cannot provide the desired energy increase. Two options for attaining the energy increase have been considered: (1) replacing the present injector SRF modules with new, higher gradient modules, or (2) re-circulating the electron beam through the existing cryomodules to achieve the necessary energy gain in two passes. In this paper we present computer simulation studies for these two options of the injector upgrade and list their advantages and disadvantages.

  13. PERFORMANCE OF THE CEBAF PROTOTYPE CRYOMODULE RENASCENCE

    SciTech Connect

    Charles Reece; Edward Daly; G. Davis; Michael Drury; William Hicks; Joseph Preble; Haipeng Wang

    2008-02-12

    The prototype cryomodule Renascence was constructed as an energy building block for securing 6 GeV operation of CEBAF and to validate design elements for future CEBAF upgrade modules. These elements include the new “HG” and “LL” 7-cell cavity designs and a new tuner design.[1,2] Issues were identified during initial testing in 2005. The module has been reworked to address the issues with thermal stability, component breakage, and tuner motion. In addition, opportunity was taken to employ upgraded cleaning and assembly techniques for the cavity string. The HOM coupler heating issue was resolved, and seven of the eight cavities in the cryomodule have run stably at an average of 20 MV/m CW. The cryogenic, rf, and mechanical performance of the cryomodule are presented. Commissioning in CEBAF has just been completed in October 2007.

  14. Status and Plans for an SRF Accelerator Test Facility at Fermilab

    SciTech Connect

    Church, M.; Leibfritz, J.; Nagaitsev, S.; /Fermilab

    2011-07-29

    A superconducting RF accelerator test facility is currently under construction at Fermilab. The accelerator will consist of an electron gun, 40 MeV injector, beam acceleration section consisting of 3 TTF-type or ILC-type cryomodules, and multiple downstream beam lines for testing diagnostics and performing beam experiments. With 3 cryomodules installed this facility will initially be capable of generating an 810 MeV electron beam with ILC beam intensity. The facility can accommodate up to 6 cryomodules for a total beam energy of 1.5 GeV. This facility will be used to test SRF cryomodules under high intensity beam conditions, RF power equipment, instrumentation, and LLRF and controls systems for future SRF accelerators such as the ILC and Project-X. This paper describes the current status and overall plans for this facility.

  15. Numerical simulations at CEBAF using PARMELA

    NASA Astrophysics Data System (ADS)

    Liu, H.

    1993-12-01

    PARMELA has been used at CEBAF for numerical modeling of the nuclear physics injector chopping system, a possible FEL laser gun injector, and the rf steering and focusing effects of the standard CEBAF SRF cavities. These applications call for the code to input field data consistently from SUPERFISH, POISSON, and MAFIA, to properly treat a focusing solenoidal lens having an actual field profile either individually or together with its adjacent rf cavity, to deal with the space charge forces, to model the longitudinal phase space matching required for bunching electrons using a phase-compressor chicane, etc. In this paper, we describe in detail these issues of general interest.

  16. Accelerated radioactive nuclear beams: Existing and planned facilities

    SciTech Connect

    Nitschke, J.M.

    1992-07-01

    An over-view of existing and planned radioactive nuclear beam facilities world-wide. Two types of production methods are distinguished: projectile fragmentation and the on-line isotope separator (ISOL) method. While most of the projectile fragmentation facilities are already in operation, almost all the ISOL-based facilities are in still the planning stage.

  17. STANDARDIZATION OF CEBAF 12 GEV UPGRADE CAVITY TESTING

    SciTech Connect

    Tiffany Bass, G. Davis, Christiana Wilson, Mircea Stirbet

    2012-07-01

    CEBAF 12GeV upgrade project includes 80 new 7-cell cavities to form 10 cryomodules. Each cavity underwent RF qualification at 2.07K using a high power accelerating gradient test and an HOM survey in Jefferson Lab's Vertical Testing Area (VTA) before cavity string assembly. In order to ensure consistently high quality data, updated cavity testing procedures and analysis were implemented and used by a group of VTA operators. For high power tests, a cavity testing procedure was developed and used in conjunction with a LabVIEW program to collect the test data. Additionally while the cavity was at 2.07K, an HOM survey was performed using a network analyzer and a combination of Excel and Mathematica programs. Data analysis was standardized and an online logbook, Pansophy, was used for data storage and mining. The Pansophy system allowed test results to be easily summarized and searchable across all cavity tests. In this presentation, the CEBAF 12GeV upgrade cavity testing procedure, method for data analysis, and results reporting results will be discussed.

  18. A facility for accelerator research and education at Fermilab

    SciTech Connect

    Church, Mike; Nagaitsev, Sergei; /Fermilab

    2009-01-01

    Fermilab is currently constructing the 'SRF Test Accelerator at the New Muon Lab' (NML). NML consists of a photo-emitted RF electron gun, followed by a bunch compressor, low energy test beamlines, SCRF accelerating structures, and high energy test beamlines. The initial primary purpose of NML will be to test superconducting RF accelerating modules for the ILC and for Fermilab's 'Project X' - a proposal for a high intensity proton source. The unique capability of NML will be to test these modules under conditions of high intensity electron beams with ILC-like beam parameters. In addition NML incorporates a photoinjector which offers significant tunability and especially the possibility to generate a bright electron beam with brightness comparable to state-of-the-art accelerators. This opens the exciting possibility of also using NML for fundamental beams research and tests of new concepts in beam manipulations and acceleration, instrumentation, and the applications of beams.

  19. The Radiological Research Accelerator Facility. Progress report, December 1, 1993--November 30, 1994

    SciTech Connect

    Hall, E.J.; Marino, S.A.

    1994-04-01

    This document begins with a general description of the facility to include historical and up-to-date aspects of design and operation. A user`s guide and a review of research using the facility follows. Next the accelerator utilization and operation and the development of the facilities is given. Personnel currently working at the facility are listed. Lastly, recent publications and literature cited are presented.

  20. Propagation characteristics of neutrons leaking from the accelerator facilities.

    PubMed

    Kitaichi, Masatoshi; Sawamura, Sadashi; Wakisaka, Masashi; Kaneko, Junichi H; Ochiai, Kentaro; Nishitani, Takeo; Sawamura, Teruko

    2004-01-01

    In this study spatial and time distribution of neutrons leaking from Hokkaido University 45 MeV Electron Linac facility have measured and compared with the Monte Carlo simulations. The neutron transport processes inside and outside the facility building has been simulated using MCNP. The neutrons have measured by BF3 counters and 3He counters with polyethylene moderators up to the distance of 330 m from the facility. The spatial distribution of ambient dose equivalent converted from the counts has been compared with the simulation. The distribution estimated from the counts by the BF3 counter has been shown fairly good agreement with the calculation. The spatial distribution of counts obtained at the 45 MeV Electron Linac facility has been compared with that obtained at the Fusion Neutronics Source (FNS) facility of JAERI. The difference between the propagation characteristics of neutrons leaking from those facilities has been discussed. PMID:15353739

  1. Status and Plans for a Superconducting RF Accelerator Test Facility at Fermilab

    SciTech Connect

    Leibfritz, J.; Andrews, R.; Baffes, C.M.; Carlson, K.; Chase, B.; Church, M.D.; Harms, E.R.; Klebaner, A.L.; Kucera, M.; Martinez, A.; Nagaitsev, S.; /Fermilab

    2012-05-01

    The Advanced Superconducting Test Accelerator (ASTA) is being constructed at Fermilab. The existing New Muon Lab (NML) building is being converted for this facility. The accelerator will consist of an electron gun, injector, beam acceleration section consisting of 3 TTF-type or ILC-type cryomodules, multiple downstream beam lines for testing diagnostics and conducting various beam tests, and a high power beam dump. When completed, it is envisioned that this facility will initially be capable of generating a 750 MeV electron beam with ILC beam intensity. An expansion of this facility was recently completed that will provide the capability to upgrade the accelerator to a total beam energy of 1.5 GeV. Two new buildings were also constructed adjacent to the ASTA facility to house a new cryogenic plant and multiple superconducting RF (SRF) cryomodule test stands. In addition to testing accelerator components, this facility will be used to test RF power systems, instrumentation, and control systems for future SRF accelerators such as the ILC and Project-X. This paper describes the current status and overall plans for this facility.

  2. Design of the Trigger Interface and Distribution Board for CEBAF 12 GeV Upgrade

    SciTech Connect

    Gu, Jianhui; Dong, Hai; Cuevas, R; Gyurjyan, Vardan; Heyes, William; Jastrzembski, Edward; Kaneta, Scott; Nganga, Nicholas; Moffit, Bryan; Raydo, Benjamin; Timmer, Carl

    2012-10-01

    The design of the Trigger Interface and Distribution (TID) board for the 12 GeV Upgrade at the Continuous Electron Beam Accelerator Facility (CEBAF) at TJNAL is described. The TID board distributes a low jitter system clock, synchronized trigger, and synchronized multi-purpose SYNC signal. The TID also initiates data acquisition for the crate. With the TID boards, a multi-crate system can be setup for experiment test and commissioning. The TID board can be selectively populated as a Trigger Interface (TI) board, or a Trigger Distribution (TD) board for the 12 GeV upgrade experiments. When the TID is populated as a TI, it can be located in the VXS crate and distribute the CLOCK/TRIGGER/SYNC through the VXS P0 connector; it can also be located in the standard VME64 crate, and distribute the CLOCK/TRIGGER/SYNC through the VME P2 connector or front panel. It initiates the data acquisition for the front crate where the TI is positioned in. When the TID is populated as a TD, it fans out the CLOCK/TRIGGER/SYNC from trigger supervisor to the front end crates through optical fibres. The TD monitors the trigger processing on the TIs, and gives feedback to the TS for trigger flow control. Field Programmable Gate Arrays (FPGA) is utilised on TID board to provide programmability. The TID boards were intensively tested on the bench, and various setups.

  3. Experiments and simulation of high current operation at CEBAF

    SciTech Connect

    Merminga, L.; Crawford, K.; Delayen, J.R.; Doolittle, L.; Hovater, C.; Kazimi, R.; Krafft, G.; Reece, C.; Simrock, S.; Tiefenback, M.; Wang, D.X.

    1996-07-01

    The superconducting rf, cw electron accelerator at CEBAF has achieved the design energy of 4 GeV using 5-pass recirculation through a pair of 400 MeV linacs. Stable beam current of 35 {mu}A has been delivered to the Experimental Hall C. The total beam current that has been recirculated so far is 248 {mu}A. Measurements of the performance of the rf control system have been made in both pulsed and cw mode, and a numerical model has been developed which describes the beam-cavity interaction, includes a realistic representation of low level controls, klystron characteristics and microphonic noise. Experimental data and simulation results on transient beam loading, klystron saturation, a new technique for cavity phasing, and heavy beam loading tests are described; in conclusion, an outlook on full current operation is presented.

  4. DEVICE CONTROL TOOL FOR CEBAF BEAM DIAGNOSTICS SOFTWARE

    SciTech Connect

    Pavel Chevtsov

    2008-02-11

    Continuously monitoring the beam quality in the CEBAF accelerator, a variety of beam diagnostics software created at Jefferson Lab makes a significant contribution to very high availability of the machine for nuclear physics experiments. The interface between this software and beam instrumentation hardware components is provided by a device control tool, which is optimized for beam diagnostics tasks. As a part of the device/driver development framework at Jefferson Lab, this tool is very easy to support and extend to integrate new beam instrumentation components. All device control functions are based on the configuration (ASCII text) files that completely define the used hardware interface standards (CAMAC, VME, RS-232, GPIB, etc.) and communication protocols. The paper presents the main elements of the device control tool for beam diagnostics software at Jefferson Lab.

  5. Precision intercomparison of beam current monitors at CEBAF

    SciTech Connect

    Kazimi, R.; Dunham, B.; Krafft, G.A.; Legg, r.; Liang, C.; Sinclair, C.; Mamosser, J.

    1995-12-31

    The CEBAF accelerator delivers a CW electron beam at fundamental 1497 MHz, with average beam current up to 200 {mu}A. Accurate, stable nonintercepting beam current monitors are required for: setup/control, monitoring of beam current and beam losses for machine protection and personnel safety, and providing beam current information to experimental users. Fundamental frequency stainless steel RF cavities have been chosen for these beam current monitors. This paper reports on precision intercomparison between two such RF cavities, an Unser monitor, and two Faraday cups, all located in the injector area. At the low beam energy in the injector, it is straightforward to verify the high efficiency of the Faraday cups, and the Unser monitor included a wire through it to permit an absolute calibration. The cavity intensity monitors have proven capable of stable, high precision monitoring of the beam current.

  6. eDT and Model-based Configuration of 12GeV CEBAF

    SciTech Connect

    Turner, Dennison L.

    2015-09-01

    This poster will discuss model-driven setup of CEBAF for the 12GeV era, focusing on the elegant Download Tool (eDT). eDT is a new operator tool that generates magnet design setpoints for various machine energies and pass configurations. eDT was developed in the effort towards a process for reducing machine configuration time and reproducibility by way of an accurate accelerator model.

  7. Berkeley Accelerator Space Effects (BASE) Light Ion FacilityUpgrade

    SciTech Connect

    Johnson, Michael B.; McMahan, Margaret A.; Gimpel, Thomas L.; Tiffany, William S.

    2006-07-07

    The BASE Light Ion Facility upgrades have been completed. All proton beams are now delivered to Cave 4A. New control software, a larger diameter beam window, and improved quality assurance measures have been added.

  8. FAIR - An International Accelerator Facility for Research with Ions and Antiprotons

    SciTech Connect

    Henning, Walter

    2005-06-08

    An overview is given on the international Facility for Antiproton and Ion Research (FAIR) at GSI, its science motivation and goals, the facility lay-out and characteristics, the accelerator design challenges, the schedule for construction, and the international interest/participation in the project.

  9. Accelerated field facility development for hot sour gas

    SciTech Connect

    Kuntz, L.K.

    1983-10-01

    This paper presents the chronological plan by which a grass roots sweetening facility was constructed in a minimum amount of time. The facility design was based on production with 9% carbon dioxide and 40 ppm hydrogen sulfide. Flowing wellhead temperatures were predicted to be approximately 300/sup 0/F with flowing wellhead pressures to 11,500 psi. The production facility, with a current total nominal capacity of 100 MMcf/D, was installed as five separate parallel sweetening units. The units were put on-stream in phases in order to maintain a sweetening capacity schedule compatible with wells being put on production. The first units were available for service in three months. All five units were complete in nine months, and a permanent facility installation was commissioned three months later. The process design, equipment procurement, and installation phases of the project were pursued concurrently. Three different sweetening systems were operated during the facility development. A conventional DEA (diethanolamine) system was used because of its simple operation. Conversions were made to a proprietary MDEA (methyldiethanolamine) system in order to increase capacity. A proprietary activated MDEA was tested and operated in order to determine sweetening system selection for future facility capacity and for other applications. Included is a discussion of the project development procedure and key considerations that led to minimal development time. General comparisons are made concerning the performance of several sweetening systems.

  10. Design and Implementation of the CEBAF Element Database

    SciTech Connect

    Theodore Larrieu, Christopher Slominski, Michele Joyce

    2011-10-01

    With inauguration of the CEBAF Element Database (CED) in Fall 2010, Jefferson Lab computer scientists have taken a first step toward the eventual goal of a model-driven accelerator. Once fully populated, the database will be the primary repository of information used for everything from generating lattice decks to booting front-end computers to building controls screens. A particular requirement influencing the CED design is that it must provide consistent access to not only present, but also future, and eventually past, configurations of the CEBAF accelerator. To accomplish this, an introspective database schema was designed that allows new elements, element types, and element properties to be defined on-the-fly without changing table structure. When used in conjunction with the Oracle Workspace Manager, it allows users to seamlessly query data from any time in the database history with the exact same tools as they use for querying the present configuration. Users can also check-out workspaces and use them as staging areas for upcoming machine configurations. All Access to the CED is through a well-documented API that is translated automatically from original C++ into native libraries for script languages such as perl, php, and TCL making access to the CED easy and ubiquitous. Notice: Authored by Jefferson Science Associates, LLC under U.S. DOE Contract No. DE-AC05-06OR23177. The U.S. Government retains a non-exclusive, paid-up, irrevocable, world-wide license to publish or reproduce this manuscript for U.S. Government purposes.

  11. Upgrade of CEBAF from 6-GeV To 12-GeV: Status

    SciTech Connect

    Harwood, Leigh H.

    2013-04-01

    The CEBAF accelerator is being upgraded from 6 GeV to 12 GeV by the US Department of Energy. The accelerator upgrade is being done within the existing tunnel footprint. The accelerator upgrade includes: 10 new srfbased high-performance cryomodules plus RF systems, doubling the 2K helium plants capability, upgrading the existing beamlines to operate at nearly double the original performance envelope, and adding a beamline to a new experimental area. Construction is over 75% complete with final completion projected for late FY13. Details of the upgrade and status of the work will be presented.

  12. Sensitivity and alternative operating point studies on a high charge CW FEL injector test stand at CEBAF

    SciTech Connect

    Liu, H.; Kehne, D.; Benson, S.

    1995-12-31

    A high charge CW FEL injector test stand is being built at CEBAF based on a 500 kV DC laser gun, a 1500 MHz room-temperature buncher, and a high-gradient ({approx}10 MV/m) CEBAF cryounit containing two 1500 MHz CEBAF SRF cavities. Space-charge-dominated beam dynamics simulations show that this injector should be an excellent high-brightness electron beam source for CW UV FELs if the nominal parameters assigned to each component of the system are experimentally achieved. Extensive sensitivity and alternative operating point studies have been conducted numerically to establish tolerances on the parameters of various injector system components. The consequences of degraded injector performance, due to failure to establish and/or maintain the nominal system design parameters, on the performance of the main accelerator and the FEL itself are discussed.

  13. Development of a 20-MeV Dielectric-Loaded Accelerator Test Facility

    SciTech Connect

    Gold, S.H.; Kinkead, A.K.; Gai, W.; Power, J.G.; Konecny, R.; Jing, C.G.; Tantawi, S.G.; Nantista, C.D.; Hu, Y.; Chen, H.; Tang, C.; Lin, Y.; Bruce, R.W.; Bruce, R.L.; Fliflet, A.W.; Lewis, D.; /Naval Research Lab, Wash., D.C. /LET Corp., Washington /Argonne /SLAC /Tsinghua U., Beijing

    2005-06-22

    This paper describes a joint project by the Naval Research Laboratory (NRL) and Argonne National Laboratory (ANL), in collaboration with the Stanford Linear Accelerator Center (SLAC), to develop a dielectric-loaded accelerator (DLA) test facility powered by a high-power 11.424-GHz magnicon amplifier. The magnicon can presently produce 25 MW of output power in a 250-ns pulse at 10 Hz, and efforts are in progress to increase this to 50 MW. The facility will include a 5 MeV electron inector being developed by the Accelerator Laboratory of Tsinghua University in Beijing, China. The DLA test structures are being developed by ANL, and some have undergone testing at NRL at gradients up to {approx} 8 MV/m. SLAC is developing a means to combine the two magnicon output arms, and to drive an injector and accelerator with separate control of the power ratio and relative phase. RWBruce Associates, Inc., working with NRl, is developing a means to join short ceramic sections into a continuous accelerator tube by ceramic brazing using an intense millimeter-wave beam. The installation and testing of the first dielectric-loaded test accelerator, including injector, DLA structure, and spectrometer, should take place within the next year. The facility will be used for testing DLA structures using a variety of materials and configurations, and also for testing other X-band accelerator concepts. The initial goal is to produce a compact 20 MeV dielectric-loaded test accelerator.

  14. Survey of Electronic Safety Systems in Accelerator Applications

    NASA Astrophysics Data System (ADS)

    Mahoney, K.

    1997-05-01

    This paper presents the preliminary results and analysis of a comprehensive survey of the implementation of accelerator safety interlock systems at over 20 international labs. At the present time there is not a self consistent means to evaluate both the experience and level of protection provided by electronic safety interlock systems. This research is intended to analyze the strengths and weaknesses of several different types of interlock system implementation methodologies. Research, medical, and industrial accelerators are compared. The CEBAF accelerator at Thomas Jefferson National Accelerator Facility (Jefferson Lab) was one of the first large particle accelerators to implement a safety interlock system using programmable logic controllers. Since that time all of the major new U.S. accelerator construction projects plan to use some form of programmable electronics as part of a safety interlock system in some capacity. To the author's knowledge such a compilation has not been presented before.

  15. A facility to test short superconducting accelerator magnets at Fermilab

    SciTech Connect

    Lamm, M.J.; Hess, C.; Lewis, D.; Jaffery, T.; Kinney, W.; Ozelis, J.P.; Strait, J.; Butteris, J.; McInturff, A.D.; Coulter, K.J.

    1992-10-01

    During the past four years the Superconducting Magnet R&D facility at Fermilab (Lab 2) has successfully tested superconducting dipole, quadrupole, and correction coil magnets less than 2 meters in length for the SSC project and the Tevatron D0/B0 Low-{beta} Insertion. During this time several improvements have been made to the facility that have greatly enhanced its magnet testing capabilities. Among the upgrades have been a new rotating coil and data acquisition system for measuring magnetic fields, a controlled flow liquid helium transfer line using an electronically actuated cryo valve, and stand-alone systems for measuring AC loss and training low current Tevatron correction coil packages. A description of the Lab 2 facilities is presented.

  16. A facility to test short superconducting accelerator magnets at Fermilab

    SciTech Connect

    Lamm, M.J.; Hess, C.; Lewis, D.; Jaffery, T.; Kinney, W.; Ozelis, J.P.; Strait, J. ); Butteris, J.; McInturff, A.D. ); Coulter, K.J. )

    1992-10-01

    During the past four years the Superconducting Magnet R D facility at Fermilab (Lab 2) has successfully tested superconducting dipole, quadrupole, and correction coil magnets less than 2 meters in length for the SSC project and the Tevatron D0/B0 Low-[beta] Insertion. During this time several improvements have been made to the facility that have greatly enhanced its magnet testing capabilities. Among the upgrades have been a new rotating coil and data acquisition system for measuring magnetic fields, a controlled flow liquid helium transfer line using an electronically actuated cryo valve, and stand-alone systems for measuring AC loss and training low current Tevatron correction coil packages. A description of the Lab 2 facilities is presented.

  17. Ultra-accelerated natural sunlight exposure testing facilities

    DOEpatents

    Lewandowski, Allan A.; Jorgensen, Gary J.

    2003-08-12

    A multi-faceted concentrator apparatus for providing ultra-accelerated natural sunlight exposure testing for sample materials under controlled weathering conditions comprising: facets that receive incident natural sunlight, transmits VIS/NIR and reflects UV/VIS to deliver a uniform flux of UV/VIS onto a sample exposure plane located near a center of a facet array in chamber means that provide concurrent levels of temperature and/or relative humidity at high levels of up to 100.times. of natural sunlight that allow sample materials to be subjected to accelerated irradiance exposure factors for a significant period of time of about 3 to 10 days to provide a corresponding time of about at least a years worth representative weathering of sample materials.

  18. Ultra-Accelerated Natural Sunlight Exposure Testing Facilities

    DOEpatents

    Lewandowski, Allan A.; Jorgensen, Gary J.

    2004-11-23

    A multi-faceted concentrator apparatus for providing ultra-accelerated natural sunlight exposure testing for sample materials under controlled weathering conditions comprising: facets that receive incident natural sunlight, transmits VIS/NIR and reflects UV/VIS onto a secondary reflector that delivers a uniform flux of UV/VIS onto a sample exposure plane located near a center of a facet array in a chamber that provide concurrent levels of temperature and/or relative humidity at high levels of up to 100.times. of natural sunlight that allow sample materials to be subjected to accelerated irradiance exposure factors for a significant period of time of about 3 to 10 days to provide a corresponding time of about at least a years worth representative weathering of sample materials.

  19. Color transparency after the NE18 and E665 experiments: Outlook and perspectives at CEBAF

    SciTech Connect

    Nemchik, J.; Nikolaev, N.N.; Zakharov, B.G.

    1994-04-01

    CEBAF is a high-luminocity factory of virtual photons with variable virtuality Q{sup 2} and transverse size. This makes CEBAF, in particular after the energy upgrade to (8-12)GeV, an ideal facility for uncovering new phenomena, and opening new windows, at the interface of the perturbative and nonperturbative QCD. The authors discuss color transparency as the case for a broad program on electroproduction of vector mesons {rho}{sup 0}, {omega}{sup 0}, {phi}{sup 0} and their radial excitations {rho}{prime}, {omega}{prime}, {phi}{prime} at CEBAF. They also comment on the second generation of experiments on color transparency in {sup 4}He(e, e{prime}p) scattering, which are also feasible at CEBAF. In 1994, they can make more reliable projections into future because their understanding of the onset of color transparency has greatly been augmented by two experiments completed in 1993: (i) no effect of CT was seen in the SLAC NE18 experiment on A(e, e{prime}p) scattering at virtualities of the exchanged photon Q{sup 2} {approx_lt} 7 GeV{sup 2}, (ii) strong signal of CT was observed in the FNAL E665 experiment on exclusive {rho}{sup 0}-meson production in deep inelastic scattering in the same range of Q{sup 2}. They discuss the impact of these observations on the CEBAF experimental program. They argue they both are good news, both were anticipated theoretically, and both rule in the correct QCD mechanism of the onset of CT.

  20. The CEBAF fiber optic phase reference system

    SciTech Connect

    Crawford, K.; Simrock, S.; Hovater, C.; Krycuk, A.

    1995-12-31

    The specified phase stability of the CEBAF RF distribution system is 2.9{degree} rms per linac. Stability is achieved through the use of a temperature and pressure regulated coaxial drive line. Purpose of the fiber optic phase reference system is to monitor the relative phase at the beginning and ending of this drive line, between linacs, injector and separator to determine drift due to ambient temperature fluctuations. The system utilizes an Ortel 1310 nm single mode laser driving Sumitumo optical fiber to distribute a reference signal at 1497 MHz. Phase of this reference signal is compared to the 1427 MHz (LO) and the 70 MHz (IF) via a 360{degree} phase detector. The detected information is then routed to the CEBAF control system for display with a specified resolution of {+-}0.2{degree} over a 20{degree} phase delta.

  1. CEBAF'S New RF Separator Structure Test Results

    SciTech Connect

    Reza Kazimi; Jock Fugitt; A. Krycuk; Charles Sinclair; Larry Turlington

    1993-05-01

    Prototypes of the rf separator for CEBAF have been made and successfully beam tested. The structure is a new design which has a high transverse shunt impedance together with a small transverse dimension compared to more conventional rf deflecting structures. Five rf separators will be used at CEBAF to allow beam from any one of the five recirculation passes to be delivered to any of the three experimental halls. The authors have already described the basic design of the structure and theoretical calculations. They have also reported some results from rf measurements and beam tests. In this paper they present more beam test results, their final design parameters, and test results of coupling two 1/2 wavelength cavities together.

  2. Nucleon resonance electroproduction at high momentum transers: Results from SLAC and suggestions for CEBAF

    SciTech Connect

    Keppel, C.

    1994-04-01

    Nucleon resonance electroproduction results from SLAC Experiment E14OX are presented. A CEBAF facility with doubled energy would enable similar high momentum transfer measurements to be made with greater accuracy. Of particular interest are the Delta P{sub 33}(1232) resonance form factor and R = {sigma}{sub L}/{sigma}{sub T}, the ratio of the longitudinal and transverse components of the cross section. A suggestion is made to study these quantities in conjunction with Bloom-Gilman duality.

  3. Proton Form Factor Puzzle and the CEBAF Large Acceptance Spectrometer (CLAS) two-photon exchange experiment

    NASA Astrophysics Data System (ADS)

    Rimal, Dipak

    The electromagnetic form factors are the most fundamental observables that encode information about the internal structure of the nucleon. The electric (GE) and the magnetic ( GM) form factors contain information about the spatial distribution of the charge and magnetization inside the nucleon. A significant discrepancy exists between the Rosenbluth and the polarization transfer measurements of the electromagnetic form factors of the proton. One possible explanation for the discrepancy is the contributions of two-photon exchange (TPE) effects. Theoretical calculations estimating the magnitude of the TPE effect are highly model dependent, and limited experimental evidence for such effects exists. Experimentally, the TPE effect can be measured by comparing the ratio of positron-proton elastic scattering cross section to that of the electron-proton [R = sigma(e +p)/sigma(e+p)]. The ratio R was measured over a wide range of kinematics, utilizing a 5.6 GeV primary electron beam produced by the Continuous Electron Beam Accelerator Facility (CEBAF) at Jefferson Lab. This dissertation explored dependence of R on kinematic variables such as squared four-momentum transfer (Q2) and the virtual photon polarization parameter (epsilon). A mixed electron-positron beam was produced from the primary electron beam in experimental Hall B. The mixed beam was scattered from a liquid hydrogen (LH2) target. Both the scattered lepton and the recoil proton were detected by the CEBAF Large Acceptance Spectrometer (CLAS). The elastic events were then identified by using elastic scattering kinematics. This work extracted the Q2 dependence of R at high epsilon(epsilon > 0.8) and the $epsilon dependence of R at approx 0.85 GeV2. In these kinematics, our data confirm the validity of the hadronic calculations of the TPE effect by Blunden, Melnitchouk, and Tjon. This hadronic TPE effect, with additional corrections contributed by higher excitations of the intermediate state nucleon, largely

  4. Elastic form factors at higher CEBAF energies

    SciTech Connect

    Petratos, G.G.

    1994-04-01

    The prospects for elastic scattering from few body systems with higher beam energies at CEBAF is presented. The deuteron and{sup 3}He elastic structure functions A(Q{sup 2}) can be measured at sufficiently high momentum transfers to study the transition between the conventional meson-nucleon and the constituent quark-gluon descriptions. Possible improvements in the proton magnetic form factor data are also presented.

  5. Engineered and Administrative Safety Systems for the Control of Prompt Radiation Hazards at Accelerator Facilities

    SciTech Connect

    Liu, James C.; Vylet, Vashek; Walker, Lawrence S.; /SLAC

    2007-12-17

    The ANSI N43.1 Standard, currently in revision (ANSI 2007), sets forth the requirements for accelerator facilities to provide adequate protection for the workers, the public and the environment from the hazards of ionizing radiation produced during and from accelerator operations. The Standard also recommends good practices that, when followed, provide a level of radiation protection consistent with those established for the accelerator communities. The N43.1 Standard is suitable for all accelerator facilities (using electron, positron, proton, or ion particle beams) capable of producing radiation, subject to federal or state regulations. The requirements (see word 'shall') and recommended practices (see word 'should') are prescribed in a graded approach that are commensurate with the complexity and hazard levels of the accelerator facility. Chapters 4, 5 and 6 of the N43.1 Standard address specially the Radiation Safety System (RSS), both engineered and administrative systems, to mitigate and control the prompt radiation hazards from accelerator operations. The RSS includes the Access Control System (ACS) and Radiation Control System (RCS). The main requirements and recommendations of the N43.1 Standard regarding the management, technical and operational aspects of the RSS are described and condensed in this report. Clearly some aspects of the RSS policies and practices at different facilities may differ in order to meet the practical needs for field implementation. A previous report (Liu et al. 2001a), which reviews and summarizes the RSS at five North American high-energy accelerator facilities, as well as the RSS references for the 5 labs (Drozdoff 2001; Gallegos 1996; Ipe and Liu 1992; Liu 1999; Liu 2001b; Rokni 1996; TJNAF 1994; Yotam et al. 1991), can be consulted for the actual RSS implementation at various laboratories. A comprehensive report describing the RSS at the Stanford Linear Accelerator Center (SLAC 2006) can also serve as a reference.

  6. Potential applications of the dielectric wakefield accelerators in the SINBAD facility at DESY

    NASA Astrophysics Data System (ADS)

    Nie, Y. C.; Assmann, R.; Dorda, U.; Marchetti, B.; Weikum, M.; Zhu, J.; Hüning, M.

    2016-09-01

    Short, high-brightness relativistic electron bunches can drive ultra-high wakefields in the dielectric wakefield accelerators (DWFAs). This effect can be used to generate high power THz coherent Cherenkov radiation, accelerate a witness bunch with gradient two or three orders of magnitude larger than that in the conventional RF linear accelerators, introduce energy modulation within the driving bunch itself, etc. The paper studies potential applications of the DWFAs in the SINBAD facility at DESY. The simulations show that the ultra-short relativistic bunches from the SINBAD injector ARES can excite accelerating wakefields with peak amplitudes as high as GV/m at THz frequencies in proper DWFA structures. In addition, it illustrates that the DWFA structure can serve as a dechirper to compensate the correlated energy spread of the bunches accelerated by the laser plasma wakefield accelerator.

  7. 148-Gd cross section measurements for accelerator target facilities

    SciTech Connect

    Corzine, R. K.; Pitcher, E. J.; Devlin, M. J.; Hertel, N. E.

    2002-01-01

    In a series of experiments at LANSCE's WNR facility, 148Gdp roduction was measured for 600- and 800-MeV protons on tungsten, tantalum, and gold. These experiments used 3 pm thin W, Ta, and Au foils and 10 pm thin A1 activation foils, Spallation yields were determined for many short-lived and long-lived spallation products with these foils using gamma and alpha spectroscopy.

  8. "DIANA" - A New, Deep-Underground Accelerator Facility for Astrophysics Experiments

    SciTech Connect

    Leitner, M.; Leitner, D.; Lemut, A.; Vetter, P.; Wiescher, M.

    2009-05-28

    The DIANA project (Dakota Ion Accelerators for Nuclear Astrophysics) is a collaboration between the University of Notre Dame, University of North Carolina, Western Michigan University, and Lawrence Berkeley National Laboratory to build a nuclear astrophysics accelerator facility 1.4 km below ground. DIANA is part of the US proposal DUSEL (Deep Underground Science and Engineering Laboratory) to establish a cross-disciplinary underground laboratory in the former gold mine of Homestake in South Dakota, USA. DIANA would consist of two high-current accelerators, a 30 to 400 kV variable, high-voltage platform, and a second, dynamitron accelerator with a voltage range of 350 kV to 3 MV. As a unique feature, both accelerators are planned to be equipped with either high-current microwave ion sources or multi-charged ECR ion sources producing ions from protons to oxygen. Electrostatic quadrupole transport elements will be incorporated in the dynamitron high voltage column. Compared to current astrophysics facilities, DIANA could increase the available beam densities on target by magnitudes: up to 100 mA on the low energy accelerator and several mA on the high energy accelerator. An integral part of the DIANA project is the development of a high-density super-sonic gas-jet target which can handle these anticipated beam powers. The paper will explain the main components of the DIANA accelerators and their beam transport lines and will discuss related technical challenges.

  9. Performance of the Argonne Wakefield Accelerator facility and initial experimental results

    SciTech Connect

    Gai, W.; Conde, M.; Cox, G.; Konecny, R.; Power, J.; Schoessow, P.; Simpson, J.; Barov, N.

    1997-09-01

    The Argonne Wakefield Accelerator (AWA) facility has begun its experimental program. This unique facility is designed to address advanced acceleration research which requires very short, intense electron bunches. The facility incorporates two photo-cathode based electron sources. One produces up to 100 nC, multi-kiloamp drive bunches which are used to excite wakefields in dielectric loaded structures and in plasma. The second source produces much lower intensity witness pulses which are used to probe the fields produced by the drive. The drive and witness pulses can be precisely timed as well as laterally positioned with respect to each other. The authors discuss commissioning, initial experiments, and outline plans for a proposed 1 GeV demonstration accelerator.

  10. Operational experience from a large EPICS-based accelerator facility

    SciTech Connect

    Ciarlette, D.J.; Gerig, R.

    1995-12-31

    The Advanced Photon Source (APS) at Argonne National Laboratory is a third-generation x-ray light source which uses the Experimental Physics and Industrial Control System (EPICS) to operate its linear accelerator, positron accumulator ring, booster synchrotron, and storage ring equipment. EPICS has been used at the APS since the beginning of installation and commissioning. Currently, EPICS controls approximately 100 VME crates containing over 100,000 process variables. With this complexity, the APS has had to review some of the methods originally employed and make changes as necessary. In addition, due to commissioning and operational needs, higher-level operator software needed to be created. EPICS has been flexible enough to allow this.

  11. Evaluation and analysis of the residual radioactivity for the 15UD Pelletron accelerator facility

    SciTech Connect

    Sonkawade, R. G.

    2007-07-01

    For the assessment of radiological impact of the accelerators, it will be better to have the documented information on activation of metal parts of the accelerator components. It is very much essential to get reliable data on these subjects. During acceleration of light ion, the residual radioactivity in the accelerator facility was found near the Analyzing Magnet, single slit, Beam Profile Monitors (BPM), Faraday Cups (FC), bellows, beginning of switching magnet bellows, at the target and the ladder. Study with HPGE detector gives an insight of the formation of the short or long lived radionuclides. The different targets used in the light ion experiment were also monitored and proper decommissioning and decontamination steps were followed. This paper presents the data of residual radioactivity in the 15UD Pelletron accelerator infrastructure. (author)

  12. Ion accelerator facilities at the University of Göttingen

    NASA Astrophysics Data System (ADS)

    Uhrmacher, M.; Hofsäss, H.

    2005-10-01

    The accelerators at the II. Physikalisches Institut of the University of Göttingen were reinstalled in a new building during the summer of 2003. They cover a wide energy range and are used for many different applications. The highest energies are obtained with the 3 MV Pelletron MaRPel, which is preferentially used for ion beam analysis. Ions in the energy range from 30 keV to 1000 keV are delivered by the 500 kV heavy ion implanter IONAS which is used for analysis, implantation and ion beam modification. ADONIS and STRINGER are mass-separated ion beam deposition (MSIBD) systems which produce 30 keV mass separated beams which can be decelerated to 20 eV to synthesize isotopically pure hard coatings like cubic BN, tetrahedral bounded amorphous C (ta-C) and BxC. The low energy implanter IOSCHKA delivers ions of 10 keV maximum, which can be slowed down to a few eV. The targets can be transferred in UHV to an STM set-up to investigate surface modifications after single ion impacts or the development of surface ripple patterns.

  13. High brightness photocathode injector for BNL Accelerator Test Facility

    SciTech Connect

    Parsa, Z.; Young, L.

    1990-01-01

    An analysis of the BNL photocathode (1-1/2 cell) Gun'' operating at 2856 MHZ, is presented. The beam parameters including beam energy, and emittance are calculated. A review of the Gun parameters and full input and output of our analysis with program PARMELA, is given in Section 2, some of our results, are tabulated. The phase plots and the beam parameters, at downstream ends of the elements, from cathode through the cavity, first cell is labeled as element 2; and second cell is labeled as element to the exit of the GUN. The analysis was made for 3 cases, using three different initial values (EO) for the average accelerating gradient (MV/m), for comparison with previous works. For illustration, the field obtained with program SUPERFISH is given, and conclusion including shunt impedances obtained for the cells and the cavity are given in Section 6. PARMELA is used as a standard design program at ATF. At the request of some of the users of program PARMELA, this request of some of the users of program PARMELA, this report include and illustrates some of our data, in the input and output format of the program PARMELA. 5 refs., 7 figs., 3 tabs.

  14. ACCELERATOR PHYSICS MODEL OF EXPECTED BEAM LOSS ALONG THE SNS ACCELERATOR FACILITY DURING NORMAL OPERATION.

    SciTech Connect

    CATALAN - LASHERAS,N.; COUSINEAU,S.; GALAMBOS,J.; HOLTKAMP,N.; RAPARIA,D.; SHAFER,R.; STAPLES,J.; STOVALL,J.; TANKE,E.; WANGLER,T.; WEI,J.

    2002-06-03

    The most demanding requirement in the design of the SNS accelerator chain is to keep the accelerator complex under hands-on maintenance. This requirement implies a hard limit for residual radiation below 100 mrem/hr at one feet from the vacuum pipe and four hours after shutdown for hundred days of normal operation. It has been shown by measurements as well as simulation [l] that this limit corresponds to 1-2 Watts/meter average beam losses. This loss level is achievable all around the machine except in specific areas where remote handling will be necessary. These areas have been identified and correspond to collimation sections and dumps where a larger amount of controlled beam loss is foreseen. Even if the average level of loss is kept under 1 W/m, there are circumstances under which transient losses occur in the machine. The prompt radiation or potential damage in the accelerator components can not be deduced from an average beam loss of 1 W/m. At the same time, controlled loss areas require a dedicated study to clarify the magnitude and distribution of the beam loss. From the front end to the target, we have estimated the most probable locations for transient losses and given an estimate of their magnitude and frequency. This information is essential to calculate the necessary shielding or determine the safety procedures during machine operation. Losses in controlled areas, and the cleaning systems are the subject of Section 2. The inefficiency of each system will be taken into account for the discussion on Section 3 where n controlled loss is estimated. Section 4 summarizes our findings and presents a global view of the losses along the accelerator chain.

  15. Accelerator Stewardship Test Facility Program - Elliptical Twin Cavity for Accelerator Applications

    SciTech Connect

    Hutton, Andrew; Areti, Hari

    2015-08-01

    Funding is being requested pursuant to the proposals entitled Elliptical Twin Cavity for Accelerator Applications that was submitted and reviewed through the Portfolio Analysis and Management System (PAMS). The PAMS proposal identifier number is 0000219731. The proposed new type of superconducting cavity, the Elliptical Twin Cavity, is capable of accelerating or decelerating beams in two separate beam pipes. This configuration is particularly effective for high-current, low energy electron beams that will be used for bunched beam cooling of high-energy protons or ions. Having the accelerated beam physically separated from the decelerated beam, but interacting with the same RF mode, means that the low energy beam from the gun can be injected into to the superconducting cavity without bends enabling a small beam emittance to be maintained. A staff engineer who has been working with non-standard complicated cavity structures replaces the senior engineer (in the original budget) who is moving on to be a project leader. This is reflected in a slightly increased engineer time and in reduced costs. The Indirect costs for FY16 are lower than the previous projection. As a result, there is no scope reduction.

  16. Status and specifications of a Project X front-end accelerator test facility at Fermilab

    SciTech Connect

    Steimel, J.; Webber, R.; Madrak, R.; Wildman, D.; Pasquinelli, R.; Evans-Peoples, E.; /Fermilab

    2011-03-01

    This paper describes the construction and operational status of an accelerator test facility for Project X. The purpose of this facility is for Project X component development activities that benefit from beam tests and any development activities that require 325 MHz or 650 MHz RF power. It presently includes an H- beam line, a 325 MHz superconducting cavity test facility, a 325 MHz (pulsed) RF power source, and a 650 MHz (CW) RF power source. The paper also discusses some specific Project X components that will be tested in the facility. Fermilab's future involves new facilities to advance the intensity frontier. In the early 2000's, the vision was a pulsed, superconducting, 8 GeV linac capable of injecting directly into the Fermilab Main Injector. Prototyping the front-end of such a machine started in 2005 under a program named the High Intensity Neutrino Source (HINS). While the HINS test facility was being constructed, the concept of a new, more versatile accelerator for the intensity frontier, now called Project X, was forming. This accelerator comprises a 3 GeV CW superconducting linac with an associated experimental program, followed by a pulsed 8 GeV superconducting linac to feed the Main Injector synchrotron. The CW Project X design is now the model for Fermilab's future intensity frontier program. Although CW operation is incompatible with the original HINS front-end design, the installation remains useful for development and testing many Project X components.

  17. Proposal of the Next Incarnation of Accelerator Test Facility at KEK for the International Linear Collider

    SciTech Connect

    Araki, S.; Hayano, H.; Higashi, Y.; Honda, Y.; Kanazawa, K.; Kubo, K.; Kume, T.; Kuriki, M.; Kuroda, S.; Masuzawa, M.; Naito, T.; Okugi, T.; Sugahara, R.; Takahashi, T.; Tauchi, T.; Terunuma, N.; Toge, N.; Urakawa, J.; Vogel, V.; Yamaoka, H.; Yokoya, K.; /KEK, Tsukuba /Beijing, Inst. High Energy Phys. /Novosibirsk, IYF /Daresbury /CERN /Hiroshima U. /Orsay, LAL /LLNL, Livermore /North Carolina A-T State U. /Oxford U. /Pohang Accelerator Lab. /Queen Mary, U. of London /Royal Holloway, U. of London /DESY /SLAC /University Coll. London /Oregon U. /Tokyo U.

    2005-05-27

    To reach design luminosity, the International Linear Collider (ILC) must be able to create and reliably maintain nanometer size beams. The ATF damping ring is the unique facility where ILC emittances are possible. In this paper we present and evaluate the proposal to create a final focus facility at the ATF which, using compact final focus optics and an ILC-like bunch train, would be capable of achieving 37 nm beam size. Such a facility would enable the development of beam diagnostics and tuning methods, as well as the training of young accelerator physicists.

  18. SINBAD-The accelerator R&D facility under construction at DESY

    NASA Astrophysics Data System (ADS)

    Dorda, U.; Assmann, R.; Brinkmann, R.; Flöttmann, K.; Hartl, I.; Hüning, M.; Kärtner, F.; Fallahi, A.; Marchetti, B.; Nie, Y.; Osterhoff, J.; Schlarb, H.; Zhu, J.; Maier, A. R.

    2016-09-01

    The SINBAD facility (Short INnovative Bunches and Accelerators at DESY) is a long-term dedicated accelerator research and development facility currently under construction at DESY. It will be located in the premises of the old DORIS accelerator complex and host multiple independent experiments cost-effectively accessing the same central infrastructure like a central high power laser. With the removal of the old DORIS accelerator being completed, the refurbishment of the technical infrastructure is currently starting up. The presently ongoing conversion of the area into the SINBAD facility and the currently foreseen layout is described. The first experiment will use a compact S-band linac for the production of ultra-short bunches at hundred MeV. Once established, one of the main usages will be to externally inject electrons into a laser-driven plasma wakefield accelerator to boost the energy to GeV-level while maintaining a usable beam quality, ultimately aiming to drive an FEL. The second experiment already under planning is the setup of an attosecond radiation source with advanced technology. Further usage of the available space and infrastructure is revised and national and international collaborations are being established.

  19. Concept, implementation and commissioning of the automation system for the accelerator module test facility AMTF

    SciTech Connect

    Böckmann, Torsten A.; Korth, Olaf; Clausen, Matthias; Schoeneburg, Bernd

    2014-01-29

    The European XFEL project launched on June 5, 2007 will require about 103 accelerator modules as a main part of the XFEL linear accelerator. All superconducting components constituting the accelerator module like cavities and magnets have to be tested before the assembly. For the tests of the individual cavities and the complete modules an XFEL Accelerator Module Test Facility (AMTF) has been erected at DESY. The process control system EPICS (Experimental Physics and Industrial Control System) is used to control and operate the cryogenic plant and all its subcomponents. A complementary component of EPICS is the Open Source software suit CSS (Control System Studio). CSS is an integrated engineering, maintenance and operating tool for EPICS. CSS enables local and remote operating and monitoring of the complete system and thus represents the human machine interface. More than 250 PROFIBUS nodes work at the accelerator module test facility. DESY installed an extensive diagnostic and condition monitoring system. With these diagnostic tools it is possible to examine the correct installation and configuration of all PROFIBUS nodes in real time. The condition monitoring system based on FDT/DTM technology shows the state of the PROFIBUS devices at a glance. This information can be used for preventive maintenance which is mandatory for continuous operation of the AMTF facility. The poster will describe all steps form engineering to implementation and commissioning.

  20. Concept, implementation and commissioning of the automation system for the accelerator module test facility AMTF

    NASA Astrophysics Data System (ADS)

    Böckmann, Torsten A.; Korth, Olaf; Clausen, Matthias; Schoeneburg, Bernd

    2014-01-01

    The European XFEL project launched on June 5, 2007 will require about 103 accelerator modules as a main part of the XFEL linear accelerator. All superconducting components constituting the accelerator module like cavities and magnets have to be tested before the assembly. For the tests of the individual cavities and the complete modules an XFEL Accelerator Module Test Facility (AMTF) has been erected at DESY. The process control system EPICS (Experimental Physics and Industrial Control System) is used to control and operate the cryogenic plant and all its subcomponents. A complementary component of EPICS is the Open Source software suit CSS (Control System Studio). CSS is an integrated engineering, maintenance and operating tool for EPICS. CSS enables local and remote operating and monitoring of the complete system and thus represents the human machine interface. More than 250 PROFIBUS nodes work at the accelerator module test facility. DESY installed an extensive diagnostic and condition monitoring system. With these diagnostic tools it is possible to examine the correct installation and configuration of all PROFIBUS nodes in real time. The condition monitoring system based on FDT/DTM technology shows the state of the PROFIBUS devices at a glance. This information can be used for preventive maintenance which is mandatory for continuous operation of the AMTF facility. The poster will describe all steps form engineering to implementation and commissioning.

  1. Diagnostics for the CEBAF FEL Injector

    NASA Astrophysics Data System (ADS)

    Kehne, D.; Engwall, D.; Jordan, K.; Benson, S.; Bohn, C.; Cardman, L.; Douglas, D.; Happek, U.; Krafft, G. A.; Neil, G.; Sinclair, C.

    1996-04-01

    A test stand for the 10 MeV, 5 mA average current injector for the CEBAF FEL is currently under construction. The injector tests will progress through two phases. The first phase will be devoted to characterizing the gun transverse and longitudinal emittance performance as a function of bunch charge, beam size, and energy. The goal of the second phase is to achieve the nominal requirements of the 10 MeV injector, including bunch length, emittance, charge per bunch, and energy stability. This paper summarizes the diagnostics planned to be used in these experiments.

  2. High Gradient Operation with the CEBAF Upgrade RF Control System

    SciTech Connect

    J. Hovater; G. Davis; Hai Dong; Alicia Hofler; Lawrence King; John Musson; Tomasz Plawski

    2006-08-16

    The CEBAF Accelerator at Jefferson Lab is presently a 6 GeV five pass electron accelerator consisting of two superconducting linacs joined by independent magnetic transport arcs. Energy will be upgraded to 12 GeV with the addition of 10 new high gradient cryomodules (17+ MV/m). The higher gradients pose significant challenges beyond what the present analog low level RF (LLRF) control systems can handle reliably; therefore, a new LLRF control system is needed. A prototype system has been developed incorporating a large FPGA and using digital down and up conversion to minimize the need for analog components. The new system is more flexible and less susceptible to drifts and component nonlinearities. Because resonance control is critical to reach high gradients quickly, the new cryomodules will include a piezoelectric tuner for each cavity, and the LLRF controls must incorporate both feedback and feed-forward methods to achieve optimal resonance control performance. This paper discusses development of the new RF system, system performance for phase and amplitude stability and resonance control under Lorentz detuning measured during recent tests on a prototype cryomodule.

  3. Experimental diagnostics using optical transition radiation at CEBAF

    NASA Astrophysics Data System (ADS)

    Denard, J.-C.; Rule, D.; Fiorito, R.; Adderley, P.; Jordan, K.; Capek, K.

    1995-05-01

    Optical Transition Radiation (OTR) devices have unique properties that allow them to complement the diagnostic tools more commonly used in particle accelerators. CEBAF is designed to produce a continuous electron beam accelerated up to 4 GeV by recirculating it five times through two 400 MeV superconducting linacs. We present two OTR applications that cannot be performed with standard fluorescent screens. The goal of the first one is to provide a multiturn ``viewer'' using the backward OTR emitted from a 0.8 μm thick aluminum foil. The foil must be thin enough to keep most of the beam in the machine after each passage. Looking at the successive turns in the linacs on the same screen will provide a new diagnostic device to help tune the machine. Replacing the ceramic of the present viewers with an Al foil is relatively simple and inexpensive. The preliminary results in single pass are encouraging. The goal of the second OTR application is to measure the emittance of high current continuous beams (≊200 μA) of low emittance (5 10-9 mrad) and size (≤50 μm rms). Standard fluorescent screens or wire scanners cannot withstand such an intense beam.

  4. Facility for Advanced Accelerator Experimental Tests (FACET) at SLAC and its Radiological Considerations

    SciTech Connect

    Mao, X.S.; Leitner, M.Santana; Vollaire, J.

    2011-08-22

    Facility for Advanced Accelerator Experimental Tests (FACET) in SLAC will be used to study plasma wakefield acceleration. FLUKA Monte Carlo code was used to design a maze wall to separate FACET project and LCLS project to allow persons working in FACET side during LCLS operation. Also FLUKA Monte Carlo code was used to design the shielding for FACET dump to get optimum design for shielding both prompt and residual doses, as well as reducing environmental impact. FACET will be an experimental facility that provides short, intense pulses of electrons and positrons to excite plasma wakefields and study a variety of critical issues associated with plasma wakefield acceleration [1]. This paper describes the FACET beam parameters, the lay-out and its radiological issues.

  5. Simultaneous Four-Hall Operation for 12 GeV CEBAF

    SciTech Connect

    Kazimi, Reza

    2013-06-01

    The CEBAF accelerator at Jefferson lab will have a new experimental hall, Hall D, added to its existing three halls as a part of the ongoing 12 GeV upgrade. Under the present CEBAF design, there is no option for sending beam to all four halls simultaneously. At least one hall has to stay down during the machine operation. A new pattern for interleaving the beam bunches is introduced that allows simultaneous operation of all four halls and provide opportunity for additional future experimental beams. The new configuration presents only a minimal change to the existing CEBAF extraction system. In fact all the lower pass extractions will stay as they are and only the frequency of 5th?pass horizontal RF separator will change. In order to make room for the new Hall D beam among the existing three beams, the beam repetition rate is reduced only for the halls taking beam at the highest pass. This and other details of the new configuration and beam pattern will be presented and discussed. A separate paper in this conference will cover the implementation choices including changes to the beam source and extraction region.*

  6. The Berkeley accelerator space effects facility (BASE) - A newmission for the 88-inch cyclotron at LBNL

    SciTech Connect

    McMahan, M.A.

    2005-09-06

    In FY04, the 88-Inch Cyclotron began a new operating mode that supports a local research program in nuclear science, R&D in accelerator technology and a test facility for the National Security Space (NSS) community (the U.S. Air Force and NRO). The NSS community (and others on a cost recovery basis) can take advantage of both the light- and heavy-ion capabilities of the Cyclotron to simulate the space radiation environment. A significant portion of this work involves the testing of microcircuits for single event effects. The experimental areas within the building that are used for the radiation effects testing are now called the Berkeley Accelerator and Space Effects (BASE) facility. Improvements to the facility to provide increased reliability, quality assurance and new capabilities are underway and will be discussed. These include a 16 AMeV ''cocktail'' of beams for heavy ion testing, a neutron beam, more robust dosimetry, and other upgrades.

  7. Hurricane Isabel gives accelerators a severe test

    SciTech Connect

    Swapan Chattopadhyay

    2004-01-01

    Hurricane Isabel was at category five--the most violent on the Saffir-Simpson scale of hurricane strength--when it began threatening the central Atlantic seaboard of the US. Over the course of several days, precautions against the extreme weather conditions were taken across the Jefferson Lab site in south-east Virginia. On 18 September 2003, when Isabel struck North Carolina's Outer Banks and moved northward, directly across the region around the laboratory, the storm was still quite destructive, albeit considerably reduced in strength. The flood surge and trees felled by wind substantially damaged or even devastated buildings and homes, including many belonging to Jefferson Lab staff members. For the laboratory itself, Isabel delivered an unplanned and severe challenge in another form: a power outage that lasted nearly three-and-a-half days, and which severely tested the robustness of Jefferson Lab's two superconducting machines, the Continuous Electron Beam Accelerator Facility (CEBAF) and the superconducting radiofrequency ''driver'' accelerator of the laboratory's free-electron laser. Robustness matters greatly for science at a time when microwave superconducting linear accelerators (linacs) are not only being considered, but in some cases already being built for projects such as neutron sources, rare-isotope accelerators, innovative light sources and TeV-scale electron-positron linear colliders. Hurricane Isabel interrupted a several-week-long maintenance shutdown of CEBAF, which serves nuclear and particle physics and represents the world's pioneering large-scale implementation of superconducting radiofrequency (SRF) technology. The racetrack-shaped machine is actually a pair of 500-600 MeV SRF linacs interconnected by recirculation arc beamlines. CEBAF delivers simultaneous beams at up to 6 GeV to three experimental halls. An imminent upgrade will double the energy to 12 GeV and add an extra hall for ''quark confinement'' studies. On a smaller scale

  8. Photoproduction of Scalar Mesons Using the CEBAF Large Acceptance Spectrometer (CLAS)

    NASA Astrophysics Data System (ADS)

    Chandavar, Shloka K.

    The search for glueballs has been ongoing for several decades. The lightest glueball has been predicted by quenched lattice QCD to have mass in the range of 1.0--1.7 GeV and JPC = 0++ . The mixing of glueball states with neighbouring meson states complicates their identification and hence several experiments have been carried out over the years to study the glueball candidates. By analyzing the decay channels and production mechanisms of these candidates, their glueball content can theoretically be determined. In reality, a lot of confusion still exists about the status of these glueball candidates. The f0(1500) is one of several contenders for the lightest glueball, which has been extensively studied in several different kinds of experiments. However, there exists no photoproduction data on this particle. In the analysis presented in this dissertation, the presence of the f0(1500) in the KS 0KS0 channel is investigated in photoproduction using the CEBAF Large Acceptance Spectrometer (CLAS) at the Thomas Jefferson National Accelerator Facility, also called Jefferson Lab (JLab). This is done by studying the reaction, gammap → fJp → KS0 KS0p → 2(pi +pi-)p using data from the g12 experiment. A clear peak is seen at 1500 MeV in the background subtracted data. This is enhanced if the momentum transfer is restricted to be less than 1 GeV2. Comparing with simulations, it is seen that this peak is associated with t channel production mechanism. The f 2'(1525) has a mass of 1525 MeV and a width of 73 MeV, and hence there is a possibility of it contributing to the peak observed in our data. A moments analysis seems to suggest some presence of a D wave, however, the low acceptance at forward and backward angles prohibits a definitive conclusion.

  9. A facility for studying irradiation accelerated corrosion in high temperature water

    NASA Astrophysics Data System (ADS)

    Raiman, Stephen S.; Flick, Alexander; Toader, Ovidiu; Wang, Peng; Samad, Nassim A.; Jiao, Zhijie; Was, Gary S.

    2014-08-01

    A facility for the study of irradiation accelerated corrosion in high temperature water using in situ proton irradiation has been developed and validated. A specially designed beamline and flowing-water corrosion cell added to the 1.7 MV tandem accelerator at the Michigan Ion Beam Laboratory provide the capability to study the simultaneous effects of displacement damage and radiolysis on corrosion. A thin sample serves as both a “window” into the corrosion cell through which the proton beam passes completely, and the sample for assessing irradiation accelerated corrosion. The facility was tested by irradiating stainless steel samples at beam current densities between 0.5 and 10 μA/cm2 in 130 °C and 320 °C deaerated water, and 320 °C water with 3 wppm H2. Increases in the conductivity and dissolved oxygen content of the water varied with the proton beam current, suggesting that proton irradiation was accelerating the corrosion of the sample. Conductivity increases were greatest at 320 °C, while DO increases were highest at 130 °C. The addition of 3 wppm H2 suppressed DO below detectable levels. The facility will enable future studies into the effect of irradiation on corrosion in high temperature water with in situ proton irradiation.

  10. Accelerators for the advanced exotic beam facility in the U.S.

    SciTech Connect

    Ostroumov, P. N.; Fuerst, J. D.; Kelly, M. P.; Mustapha, B.; Nolen, J. A.; Shepard, K. W.; Physics

    2007-01-01

    The Office of Science of the Department of Energy is currently considering options for an advanced radioactive beam facility in the U.S which is a reduced scale version of the Rare Isotope Accelerator (RIA) project [1,2]. This facility will have unique capabilities compared with others both existing and planned elsewhere. As envisioned at ANL, the facility, called the Advanced Exotic Beam Laboratory (AEBL), would consist of a heavy-ion driver linac, a post-accelerator and experimental areas. Secondary beams of rare isotopes will be available as high quality reaccelerated or stopped beams from a gas catcher and high power ISOL targets, as well as, high energy beams following in-flight fragmentation or fission of heavy ions. The proposed design of the AEBL driver linac is a cw, fully superconducting, 833 MV linac capable of accelerating uranium ions up to 200 MeV/u and protons to 580 MeV with 400 kW beam power. An extensive research and development effort has resolved many technical issues related to the construction of the driver linac and other systems required for AEBL. This paper presents the status of planning, some options for such a facility, as well as, progress in related R&D.

  11. Early operating and reliability experience with the CEBAF DC magnet power supplies

    SciTech Connect

    Merz, W.; Flood, R.; Martin, E.J.; O'Sullivan, M.

    1996-08-01

    The CEBAF accelerator is a five pass, recirculating, CW electron linear accelerator. There are a total of nine recirculation arcs connecting the two linacs. Three experimental halls are serviced by the accelerator through separate transport channels. The magnet powering system for CEBAF consists of approximately 2000 independent control channels. About 1850 of these channels are low current, trim magnet power supplies. There are 28 higher power supplies used to energize the major bending elements. Over one hundred, 20 amp, active shunts are used to vary current in selected magnets in the major dipole strings. The majority of the magnetic elements are concentrated in the arcs and transport channels. The correction dipoles, quadrupoles and sextupoles are each powered individually be a dedicated trim power supply channel. The arc and extraction channel dipoles are powered in series strings by the high powered supplies, known locally at CEBAF as `box power supplies'. Arc loads consist of some 30--40 magnets in series. Transport channel, path length control doglegs and septa box power supplies have loads ranging from 1 to 10 magnets. Shunts are installed on virtually all loads where two or more magnets are in series. At this time, 95% of the power supplies are installed and commissioned. In the past twelve months, beginning in May 1994, approximately 1200 trim magnet power supplies have been checked out. During this same period approximately 22 box power supplies and 100 shunts have been made operational. Full operation of the equipment has only been under way since early 1995. While this operation is only just beginning, much has been learned based on the reliability performance seen so far. The remainder of this paper describes the systems mentioned, their reliability problems, the fixes implemented to date, and some plans for the future. 6 refs., 3 tabs.

  12. Early operating and reliability experience with the CEBAF DC magnet power supplies

    SciTech Connect

    Merz, W.; Flood, R.; Martin, E.J.; O`Sullivan, M.

    1996-08-01

    The CEBAF accelerator is a five pass, recirculating, CW electron linear accelerator. There are a total of nine recirculation arcs connecting the two linacs. Three experimental halls are serviced by the accelerator through separate transport channels. The magnet powering system for CEBAF consists of approximately 2000 independent control channels. About 1850 of these channels are low current, trim magnet power supplies. There are 28 higher power supplies used to energize the major bending elements. Over one hundred, 20 amp, active shunts are used to vary current in selected magnets in the major dipole strings. The majority of the magnetic elements are concentrated in the arcs and transport channels. The correction dipoles, quadrupoles and sextupoles are each powered individually be a dedicated trim power supply channel. The arc and extraction channel dipoles are powered in series strings by the high powered supplies, known locally at CEBAF as ``box power supplies``. Arc loads consist of some 30-40 magnets in series. Transport channel, path length control doglegs and septa box power supplies have loads ranging from 1 to 10 magnets. Shunts are installed on virtually all loads where two or more magnets are in series. At this time, 95{percent} of the power supplies are installed and commissioned. In the past twelve months, beginning in May 1994, approximately 1200 trim magnet power supplies have been checked out. During this same period approximately 22 box power supplies and 100 shunts have been made operational. Full operation of the equipment has only been under way since early 1995. While this operation is only just beginning, much has been learned based on the reliability performance seen so far. The remainder of this paper describes the systems mentioned, their reliability problems, the fixes implemented to date, and some plans for the future. 6 refs., 3 tabs.

  13. The Radiological Research Accelerator Facility. Progress report, December 1, 1992--November 30, 1993

    SciTech Connect

    Hall, E.J.; Marino, S.A.

    1993-05-01

    The Radiological Research Accelerator Facility (RARAF) is based on a 4-MV Van de Graaff accelerator, which is used to generate a variety of well-characterized radiation beams for research in radiobiology, radiological physics, and radiation chemistry. It is part of the Center for Radiological Research (CRR) - formerly the Radiological Research Laboratory of Columbia University, and its operation is supported as a National Facility by the US Department of Energy (DOE). As such, RARAF is available to all potential users on an equal basis and scientists outside the CRR are encouraged to submit proposals for experiments at RARAF. The operation of the Van de Graaff is supported by the DOE, but the research projects themselves must be supported separately. This report provides a listing and brief description of experiments performed at RARAF during the May 1, 1992 through April 30, 1993.

  14. Calculating Beam Breakup in Superconducting Linear Accelerators

    SciTech Connect

    Geoffrey Krafft; Joseph Bisognano; Sharon Laubach

    1990-02-09

    As the intensity of a particle beam passing through a linear accelerator is raised, interactions between particles play an increasingly prominent role in determining the overall dynamics of the beam. These many body effects, known collectively as beam breakup, tend to degrade the quality of the transported beam, and hence they must be calculated to accurately predict the evolution of the beam as it traverses the accelerator. Several codes which compute various collective effects have been developed and used to simulate the dynamics of beams passing through superconducting accelerator structures. All the codes use the same basic algorithm: the beam is tracked through elements giving the focusing forces on the particles, and at the appropriate locations in the linac, localized forces are impressed on the particles which model the electromagnetic interactions. Here, a difficulty is that the usual ''Coulomb'' interaction between particles is changed by the electromagnetic environment of the accelerator. By such calculations it has been shown that recirculating linear accelerators such as the one being built at the Continuous Electron Beam Accelerator Facility (CEBAF) should remain stable against multipass beam breakup instability as long as the average current does not exceed about 20 mA, that the beam quality at CEBAF will be degraded when the single bunch charge approaches 10{sup 9} electrons, and that the beam quality of superconducting linacs that are optimized for high current transport begins to decrease at around 10{sup 10} electrons per bunch. The latter result is of interest to individuals who would use superconducting linacs as beam sources for free electron lasers or for superconducting colliders for high energy physics research.

  15. Performance of the Argonne Wakefield Accelerator Facility and initial experimental results

    SciTech Connect

    Gai, W.; Conde, M.; Cox, G.; Konecny, R.; Power, J.; Schoessow, P.; Simpson, J.; Barov, N.

    1996-10-01

    The Argonne Wakefield Accelerator facility has begun its experimental program. It is designed to address advanced acceleration research requiring very short, intense electron bunches. It incorporates two photocathode based electron sources. One produces up to 100 nC, multi-kiloamp `drive` bunches which are used to excite wakefields in dielectric loaded structures and in plasma. The second source produces much lower intensity `witness` pulses which are used to probe the fields produced by the drive. The drive and witness pulses can be precisely timed as well as laterally positioned with respect to each other. This paper discusses commissioning, initial experiments, and outline plans for a proposed 1 GeV demonstration accelerator.

  16. Demonstration of two-beam acceleration and 30 GHz power production in the CLIC Test Facility

    SciTech Connect

    Bossart, R.; Braun, H. H.; Carron, G.; Chanudet, M.; Chautard, F.; Delahaye, J. P.; Godot, J. C.; Hutchins, S.; Martinez, C.; Suberlucq, G.; Tenenbaum, P.; Thorndahl, L.; Trautner, H.; Valentini, M.; Wilson, I.; Wuensch, W.

    1999-05-07

    The Compact Linear Collider (CLIC) Test Facility (CTF II) at CERN has recently demonstrated Two-Beam power production and acceleration at 30 GHz. With 41 MW of 30 GHz power produced in 14 ns pulses at a repetition rate of 5 Hz, the main beam has been accelerated by 28 MeV. The 30 GHz RF power is extracted in low impedance decelerating structures from a low-energy, high-current 'drive beam' which runs parallel to the main beam. The average current in the drive-beam train is 25 A, while the peak current exceeds 2 kA. Crosschecks between measured drive-beam charge, 30 GHz power and main-beam energy gain are in good agreement. In this paper, some relevant experimental and technical issues on drive-beam generation, two-beam power production and acceleration are presented.

  17. Distributed UHV system for the folded tandem ion accelerator facility at BARC

    NASA Astrophysics Data System (ADS)

    Gupta, S. K.; Agarwal, A.; Singh, S. K.; Basu, A.; P, Sapna; Sarode, S. P.; Singh, V. P.; Subrahmanyam, N. B. V.; Bhatt, J. P.; Pol, S. S.; Raut, P. J.; Ware, S. V.; Singh, P.; Choudhury, R. K.; Kailas, S.

    2008-05-01

    The 6 MV Folded Tandem Ion Accelerator (FOTIA) Facility at the Nuclear Physics Division, BARC is operational and accelerated beams of both light and heavy ions are being used extensively for basic and applied research. An average vacuum of the order of 10-8-10-9 Torr is maintained for maximum beam transmission and minimum beam energy spreads. The FOTIA vacuum system comprises of about 55 meter long, 100 mm diameter beam lines including various diagnostic devices, two accelerating tubes and four narrow vacuum chambers. The cross sections of the vacuum chambers are 14mm × 24mm for 180°, 38mm × 60mm and 19 × 44 mm for the and 70° & 90° bending magnets and Switching chambers respectively. All the beam line components are UHV compatible, fabricated from stainless steel 304L grade material fitted with metal gaskets. The total volume ~5.8 × 105 cm3 and surface area of 4.6 × 104 cm2, interspersed with total 18 pumping stations. The accelerating tubes are subjected to very high voltage gradient, 20.4 kV/cm, which requires a hydrocarbon free and clean vacuum for smooth operation of the accelerator. Vacuum interlocks are provided to various devices for safe operation of the accelerator. Specially designed sputter ion pumps for higher environmental pressure of 8 atmospheres are used to pump the accelerating tubes and the vacuum chamber for the 180° bending magnet. Fast acting valves are provided for isolating main accelerator against accidental air rush from rest of the beam lines. All the vacuum readings are displayed locally and are also available remotely through computer interface to the Control Room. Vacuum system details are described in this paper.

  18. Estimation of thermal neutron fluences in the concrete of proton accelerator facilities from 36Cl production

    NASA Astrophysics Data System (ADS)

    Bessho, K.; Matsumura, H.; Miura, T.; Wang, Q.; Masumoto, K.; Hagura, H.; Nagashima, Y.; Seki, R.; Takahashi, T.; Sasa, K.; Sueki, K.; Matsuhiro, T.; Tosaki, Y.

    2007-06-01

    The thermal neutron fluence that poured into the shielding concrete of proton accelerator facilities was estimated from the in situ production of 36Cl. The thermal neutron fluences at concrete surfaces during 10-30 years of operation were in the range of 1012-1014 n/cm2. The maxima in thermal neutron fluences were observed at ≈5-15 cm in the depths analyzed for 36Cl/35Cl by AMS. These characteristics imply that thermalization of neutrons occurred inside the concrete. Compared to the several tens of MeV cyclotrons, secondary neutrons penetrate deeper into the concrete at the high-energy accelerators possessing acceleration energies of 400 MeV and 12 GeV. The attenuation length of neutrons reflects the energy spectra of secondary neutrons emitted by the nuclear reaction at the beam-loss points. Increasing the energy of secondary neutrons shifts the maximum in the thermal neutron fluences to deeper positions. The data obtained in this study will be useful for the radioactive waste management at accelerator facilities.

  19. Automated frequency tuning of SRF cavities at CEBAF

    SciTech Connect

    Chowdhary, M.; Doolittle, L.; Lahti, G.; Simrock, S.N.; Terrell, R.

    1995-12-31

    An automated cavity tuning procedure has been implemented in the CEBAF control system to tune the superconducting RF (SRF) cavities to their operating frequency of 1497 MHz. The capture range for coarse tuning algorithm (Burst Mode) is more than 20 cavity bandwidths (5 kHz). The fine tuning algorithm (Sweep Mode) calibrates the phase offset in the detuning angle measurement. This paper describes the implementation of these algorithms and experience of their operation in CEBAF control system. 3 refs., 5 figs.

  20. Design of 57.5 MHz cw RFQ structure for the rare isotope accelerator facility.

    SciTech Connect

    Ostroumov, P. N.; Kolomiets, A. A.; Kashinsky, D. A.; Minaev, S. A.; Pershin, V. I.; Yaramishev, S. G.; Tretyakova, T. E.

    2002-01-29

    The Rare Isotope Accelerator (RIA) facility includes a driver linac for production of 400 kW CW heavy-ion beams. The initial acceleration of heavy-ions delivered from an ECR ion source can be effectively performed by a 57.5 MHz four-meter long RFQ. The principal specifications of the RFQ are: (1) formation of extremely low longitudinal emittance; (2) stable operation over a wide range of voltage for acceleration of various ion species needed for RIA operation; (3) simultaneous acceleration of two-charge states of uranium ions. CW operation of an accelerating structure leads to a number of requirements for the resonators such as high shunt impedance, efficient water cooling of all parts of the resonant cavity, mechanical stability together with precise alignment, reliable rf contacts, a stable operating mode and fine tuning of the resonant frequency during operation. To satisfy these requirements a new resonant structure has been developed. This paper discusses beam dynamics and electrodynamics design of the RFQ cavity, as well as, some aspects of the mechanical design of this low-frequency CW RFQ.

  1. Medical Isotope Production With The Accelerator Production of Tritium (APT) Facility

    SciTech Connect

    Buckner, M.; Cappiello, M.; Pitcher, E.; O`Brien, H.

    1998-08-01

    In order to meet US tritium needs to maintain the nuclear weapons deterrent, the Department of Energy (DOE) is pursuing a dual track program to provide a new tritium source. A record of decision is planned for late in 1998 to select either the Accelerator Production of Tritium (APT) or the Commercial Light Water Reactor (CLWR) as the technology for new tritium production in the next century. To support this decision, an APT Project was undertaken to develop an accelerator design capable of producing 3 kg of tritium per year by 2007 (START I requirements). The Los Alamos National Laboratory (LANL) was selected to lead this effort with Burns and Roe Enterprises, Inc. (BREI) / General Atomics (GA) as the prime contractor for design, construction, and commissioning of the facility. If chosen in the downselect, the facility will be built at the Savannah River Site (SRS) and operated by the SRS Maintenance and Operations (M{ampersand}O) contractor, the Westinghouse Savannah River Company (WSRC), with long-term technology support from LANL. These three organizations (LANL, BREI/GA, and WSRC) are working together under the direction of the APT National Project Office which reports directly to the DOE Office of Accelerator Production which has program authority and responsibility for the APT Project.

  2. Upgrading of the AMS facility at the Koffler 14UD Pelletron accelerator

    NASA Astrophysics Data System (ADS)

    Berkovits, D.; Paul, M.; Ben-Dov, Y.; Bordeanu, C.; Ghelberg, S.; Heber, O.; Hass, M.; Shahar, Y.; Verri, G.

    2004-08-01

    The AMS facility based on a 14UD Pelletron tandem accelerator has been upgraded in recent years to support an active and diversified research program. A new dedicated AMS ion source beam line merging at 45° with the existing injection line through a 45° electrostatic deflector is in operation. The multi-sample high-intensity Cs sputter ion source stands on a separate 120 kV platform and is remote-controlled through a hybrid infrared-fiber-optics link operated either manually or by the accelerator-control computer, ensuring safe and reliable operation. Independent current preamplifiers are used in Faraday cup current readings down to the pA range. The accelerator computer-control system was upgraded to LabView 6.1, allowing a PC server to control and read out all hardware components while one or more remote PC clients run the AMS software. Ad hoc sequences of commands, written in a script macro language, are run from a client computer to perform an automated AMS measurement. The present capabilities of the facility in terms of detected radionuclides and their sensitivities are listed.

  3. NIST Accelerator Facilities And Programs In Support Of Industrial Radiation Research

    SciTech Connect

    Bateman, F.B.; Desrosiers, M.F.; Hudson, L.T.; Coursey, B.M.; Bergstrom, P.M. Jr.; Seltzer, S.M.

    2003-08-26

    NIST's Ionizing Radiation Division maintains and operates three electron accelerators used in a number of applications including waste treatment and sterilization, radiation hardness testing, detector calibrations and materials modification studies. These facilities serve a large number of governmental, academic and industrial users as well as an active intramural research program. They include a 500 kV cascaded-rectifier accelerator, a 2.5 MV electron Van de Graaff accelerator and a 7 to 32 MeV electron linac, supplying beams ranging in energy from a few keV up to 32 MeV. In response to the recent anthrax incident, NIST along with the US Postal Service and the Armed Forces Radiobiology Research Institute (AFRRI) are working to develop protocols and testing procedures for the USPS mail sanitization program. NIST facilities and personnel are being employed in a series of quality-assurance measurements for both electron- and photon-beam sanitization. These include computational modeling, dose verification and VOC (volatile organic compounds) testing using megavoltage electron and photon sources.

  4. First particle acceleration measurements for a shocked multiphase flow at a new horizontal shock tube facility

    NASA Astrophysics Data System (ADS)

    Orlicz, Greg; Martinez, Adam; Prestridge, Kathy; Extreme Fluids Team

    2013-11-01

    The horizontal shock tube at Los Alamos, used for over 20 years to study shock-driven mixing between different density gases, has been retrofitted with a new particle seeding system, test section, and diaphragmless driver to investigate the unsteady forces on particles as they are accelerated by a shock wave. Current experiments are performed to measure the acceleration of dispersed glycol droplets, with nominal 0.5 μm diameter, carried in ambient air. Measurements at this facility will be used to develop and validate empirical models implemented in numerical codes. A Particle Image Velocimetry/Accelerometry (PIVA) system is implemented at the facility using eight laser pulses and an eight-frame high speed camera. The lasers are 532 nm Nd:YAGs with pulse widths of 20 ns, and the camera is a Specialised Imaging SIMD with 1280 × 960 resolution at up to 7 million frames per second. With this PIVA arrangement, eight particle fields are collected by independently varying the interframe times. Seven velocity and six acceleration fields are used to study the unsteady drag on the particles. Initial data sets are with a size distribution of known particle diameters. Plans are to vary the particle/gas density ratio, particle diameters, and particle phase (liquid/solid).

  5. Lessons from shielding retrofits at the LAMPF/LANSCE/PSR accelerator, beam lines and target facilities

    SciTech Connect

    Macek, R.J.

    1994-07-01

    The experience in the past 7 years to improve the shielding and radiation control systems at the Los Alamos Meson Physics Facility (LAMPF) and the Manuel Lujan Jr. Neutron Scattering Center (LANSCE) provides important lessons for the design of radiation control systems at future, high beam power proton accelerator facilities. Major issues confronted and insight gained in developing shielding criteria and in the use of radiation interlocks are discussed. For accelerators and beam lines requiring hands-on-maintenance, our experience suggests that shielding criteria based on accident scenarios will be more demanding than criteria based on routinely encountered beam losses. Specification and analysis of the appropriate design basis accident become all important. Mitigation by active protection systems of the consequences of potential, but severe, prompt radiation accidents has been advocated as an alternate choice to shielding retrofits for risk management at both facilities. Acceptance of active protection systems has proven elusive primarily because of the difficulty in providing convincing proof that failure of active systems (to mitigate the accident) is incredible. Results from extensive shielding assessment studies are presented including data from experimental beam spill tests, comparisons with model estimates, and evidence bearing on the limitations of line-of-sight attenuation models in complex geometries. The scope and significant characteristics of major shielding retrofit projects at the LAMPF site are illustrated by the project to improve the shielding beneath a road over a multiuse, high-intensity beam line (Line D).

  6. The Machine Protection System for the Fermilab Accelerator Science and Technology Facility

    SciTech Connect

    Wu, Jinyuan; Warner, Arden; Liu, Ning; Neswold, Richard; Carmichael, Linden

    2015-11-15

    The Machine Protection System (MPS) for the Fermilab Accelerator Science and Technology Facility (FAST) has been implemented and tested. The system receives signals from several subsystems and devices which conveys the relevant status needed to the safely operate the accelerator. Logic decisions are made based on these inputs and some predefined user settings which in turn controls the gate signal to the laser of the photo injector. The inputs of the system have a wide variety of signal types, encoding methods and urgencies for which the system is designed to accommodate. The MPS receives fast shutdown (FSD) signals generated by the beam loss system and inhibits the beam or reduces the beam intensity within a macropulse when the beam losses at several places along the accelerator beam line are higher than acceptable values. TTL or relay contact signals from the vacuum system, toroids, magnet systems etc., are chosen with polarities that ensure safe operation of the accelerator from unintended events such as cable disconnection in the harsh industrial environment of the experimental hall. A RS422 serial communication scheme is used to interface the operation permit generator module and a large number of movable devices each reporting multi-bit status. The system also supports operations at user defined lower beam levels for system conunissioning. The machine protection system is implemented with two commercially available off-the-shelf VMEbus based modules with on board FPGA devices. The system is monitored and controlled via the VMEbus by a single board CPU

  7. Beam Based HOM Analysis of Accelerating Structures at the TESLA Test Facility Linac

    SciTech Connect

    Wendt, M.; Schreiber, S.; Castro, P.; Gossel, A.; Huning, M.; Devanz, G.; Jablonka, M.; Magne, C.; Napoly, O.; Baboi, N.; /SLAC

    2005-08-09

    The beam emittance in future linear accelerators for high energy physics and SASE-FEL applications depends highly on the field performance in the accelerating structures, i.e. the damping of higher order modes (HOM). Besides theoretical and laboratory analysis, a beam based analysis technique was established [1] at the TESLA Test Facility (TTF) linac. It uses a charge modulated beam of variable modulation frequency to excite dipole modes. This causes a modulation of the transverse beam displacement, which is observed at a downstream BPM and associated with a direct analysis of the modes at the HOM-couplers. A brief introduction of eigenmodes of a resonator and the concept of the wake potential is given. Emphasis is put on beam instrumentation and signal analysis aspects, required for this beam based HOM measurement technique.

  8. Concepts for the magnetic design of the MITICA neutral beam test facility ion accelerator

    SciTech Connect

    Chitarin, G.; Agostinetti, P.; Marconato, N.; Marcuzzi, D.; Sartori, E.; Serianni, G.; Sonato, P.

    2012-02-15

    The megavolt ITER injector concept advancement neutral injector test facility will be constituted by a RF-driven negative ion source and by an electrostatic Accelerator, designed to produce a negative Ion with a specific energy up to 1 MeV. The beam is then neutralized in order to obtain a focused 17 MW neutral beam. The magnetic configuration inside the accelerator is of crucial importance for the achievement of a good beam efficiency, with the early deflection of the co-extracted and stripped electrons, and also of the required beam optic quality, with the correction of undesired ion beamlet deflections. Several alternative magnetic design concepts have been considered, comparing in detail the magnetic and beam optics simulation results, evidencing the advantages and drawbacks of each solution both from the physics and engineering point of view.

  9. Raman distributed temperature measurement at CERN high energy accelerator mixed field radiation test facility (CHARM)

    NASA Astrophysics Data System (ADS)

    Toccafondo, Iacopo; Nannipieri, Tiziano; Signorini, Alessandro; Guillermain, Elisa; Kuhnhenn, Jochen; Brugger, Markus; Di Pasquale, Fabrizio

    2015-09-01

    In this paper we present a validation of distributed Raman temperature sensing (RDTS) at the CERN high energy accelerator mixed field radiation test facility (CHARM), newly developed in order to qualify electronics for the challenging radiation environment of accelerators and connected high energy physics experiments. By investigating the effect of wavelength dependent radiation induced absorption (RIA) on the Raman Stokes and anti-Stokes light components in radiation tolerant Ge-doped multi-mode (MM) graded-index optical fibers, we demonstrate that Raman DTS used in loop configuration is robust to harsh environments in which the fiber is exposed to a mixed radiation field. The temperature profiles measured on commercial Ge-doped optical fibers is fully reliable and therefore, can be used to correct the RIA temperature dependence in distributed radiation sensing systems based on P-doped optical fibers.

  10. Field Work Proposal: PUBLIC OUTREACH EVENT FOR ACCELERATOR STEWARDSHIP TEST FACILITY PILOT PROGRAM

    SciTech Connect

    Hutton, Andrew; Areti, Hari

    2015-03-05

    Jefferson Lab’s outreach efforts towards the goals of Accelerator Stewardship Test Facility Pilot Program consist of the lab’s efforts in three venues. The first venue, at the end of March is to meet with the members of Virginia Tech Corporate Research Center (VTCRC) (http://www.vtcrc.com/tenant-directory/) in Blacksburg, Virginia. Of the nearly 160 members, we expect that many engineering companies (including mechanical, electrical, bio, software) will be present. To this group, we will describe the capabilities of Jefferson Lab’s accelerator infrastructure. The description will include not only the facilities but also the intellectual expertise. No funding is requested for this effort. The second venue is to reach the industrial exhibitors at the 6th International Particle Accelerator Conference (IPAC’15). Jefferson Lab will host a booth at the conference to reach out to the >75 industrial exhibitors (https://www.jlab.org/conferences/ipac2015/SponsorsExhibitors.php) who represent a wide range of technologies. A number of these industries could benefit if they can access Jefferson Lab’s accelerator infrastructure. In addition to the booth, where written material will be available, we plan to arrange a session A/V presentation to the industry exhibitors. The booth will be hosted by Jefferson Lab’s Public Relations staff, assisted on a rotating basis by the lab’s scientists and engineers. The budget with IPAC’15 designations represents the request for funds for this effort. The third venue is the gathering of Southeastern Universities Research Association (SURA) university presidents. Here we plan to reach the research departments of the universities who can benefit by availing themselves to the infrastructure (material sciences, engineering, medical schools, material sciences, to name a few). Funding is requested to allow for attendance at the SURA Board Meeting. We are coordinating with DOE regarding these costs to raise the projected conference

  11. Simulation of Cascaded Longitudinal-Space-Charge Amplifier at the Fermilab Accelerator Science & Technology (Fast) Facility

    SciTech Connect

    Halavanau, A.; Piot, P.

    2015-12-01

    Cascaded Longitudinal Space Charge Amplifiers (LSCA) have been proposed as a mechanism to generate density modulation over a board spectral range. The scheme has been recently demonstrated in the optical regime and has confirmed the production of broadband optical radiation. In this paper we investigate, via numerical simulations, the performance of a cascaded LSCA beamline at the Fermilab Accelerator Science & Technology (FAST) facility to produce broadband ultraviolet radiation. Our studies are carried out using elegant with included tree-based grid-less space charge algorithm.

  12. Accelerator Test Facility for Muon Collider and Neutrino Factory R&d

    NASA Astrophysics Data System (ADS)

    Shiltsev, Vladimir

    2010-06-01

    Over the last decade there has been significant progress in developing the concepts and technologies needed to produce, capture, accelerate and collide high intensity beams of muons. At present, a high-luminosity multi-TeV muon collider presents a viable option for the next generation lepton-lepton collider, which is believed to be needed to fully explore high energy physics in the era following LHC discoveries. This article briefly reviews the needs and possibilities for a Muon Collider beam test facility to carry out the R&D program on the collider front-end and 6D cooling demonstration experiment.

  13. ECR (Electron Cyclotron Resonance) source for the HHIRF (Holifield Heavy Ion Research Facility) tandem accelerator

    SciTech Connect

    Olsen, D.K.; Alton, G.D.; Dowling, D.T.; Haynes, D.L.; Jones, C.M.; Juras, R.C.; Lane, S.N.; Meigs, M.J.; Mills, G.D.; Mosko, S.W.; Tatum, B.A.

    1990-01-01

    Electron Cyclotron Resonance, ECR, ion source technology has developed rapidly since the original pioneering work of R. Geller and his group at Grenoble in the early 1970s. These ion sources are capable of producing intense beams of highly charged positive ions and are used extensively for cyclotron injection, linac injection, and atomic physics research. In this paper, the advantages of using an ECR heavy-ion source in the terminal of the Holifield Heavy Ion Research Facility (HHIRF) 25-MV tandem accelerator is discussed. A possible ECR system for installation in the HHIRF tandem terminal is described.

  14. Evaluation of medical isotope production with the accelerator production of tritium (APT) facility

    SciTech Connect

    Benjamin, R.W.; Frey, G.D.; McLean, D.C., Jr; Spicer, K.M.; Davis, S.E.; Baron, S.; Frysinger, J.R.; Blanpied, G.; Adcock, D.

    1997-07-10

    The accelerator production of tritium (APT) facility, with its high beam current and high beam energy, would be an ideal supplier of radioisotopes for medical research, imaging, and therapy. By-product radioisotopes will be produced in the APT window and target cooling systems and in the tungsten target through spallation, neutron, and proton interactions. High intensity proton fluxes are potentially available at three different energies for the production of proton- rich radioisotopes. Isotope production targets can be inserted into the blanket for production of neutron-rich isotopes. Currently, the major production sources of radioisotopes are either aging or abroad, or both. The use of radionuclides in nuclear medicine is growing and changing, both in terms of the number of nuclear medicine procedures being performed and in the rapidly expanding range of procedures and radioisotopes used. A large and varied demand is forecast, and the APT would be an ideal facility to satisfy that demand.

  15. Early Commissioning Experience and Future Plans for the 12 GeV Continuous Electron Beam Accelerator Facility

    SciTech Connect

    Spata, Michael F.

    2014-12-01

    Jefferson Lab has recently completed the accelerator portion of the 12 GeV Upgrade for the Continuous Electron Beam Accelerator Facility. All 52 SRF cryomodules have been commissioned and operated with beam. The initial beam transport goals of demonstrating 2.2 GeV per pass, greater than 6 GeV in 3 passes to an existing experimental facility and greater than 10 GeV in 5-1/2 passes have all been accomplished. These results along with future plans to commission the remaining beamlines and to increase the performance of the accelerator to achieve reliable, robust and efficient operations at 12 GeV are presented.

  16. Selected topics in particle accelerators: Proceedings of the CAP meetings. Volume 4

    SciTech Connect

    Parsa, Z.

    1995-10-01

    This Report includes copies of transparencies and notes from the presentations made at the Center for Accelerator Physics at Brookhaven National Laboratory. Editing and changes to the authors` contributions in this Report were made only to fulfill the publication requirements. This volume includes notes and transparencies on eight presentations: ``Application of Accelerator-Driven Spallation Targets - Including Tritium Production and Nuclear Waste Transmutation``, ``BNL 5 MW Pulsed Spallation Neutron Source Study``, ``Designing and Understanding of Magnets with the Help of Conformal Mapping``, ``Laser - Electron Beam Scattering Coherent Compton X-Ray Sources``, ``The LHC Project``, ``Optimization of the Photocathode-Linac Separation for the ATF [Accelerator Test Facility] Injection System``, ``On CEBAF Commissioning: First Results``, and ``The Proposed Booster Application Facility at BNL``. An Appendix lists dates, topics, and speakers from October 1989 to December 1994.

  17. Radiation shielding and patient organ dose study for an accelerator- based BNCT Facility at LBNL

    SciTech Connect

    Costes, S.V.; Vujic, J.; Donahue, R.J.

    1996-10-24

    This study considers the radiation safety aspects of several designs discussed in a previous report of an accelerator-based source of neutrons, based on the [sup 7]Li(p,n) reaction, for a Boron Neutron Capture Therapy (BNCT) Facility at Lawrence Berkeley National Laboratory (LBNL). determines the optimal radiation shield thicknesses for the patient treatment room. Since this is an experimental facility no moderator or reflector is considered in the bulk wall shield design. This will allow the flexibility of using any postulated moderator/reflector design and assumes sufficient shielding even in the absence of a moderator/reflector. In addition the accelerator is assumed to be capable of producing 100 mA of 2.5 MeV proton beam current. The addition of 1% and 2% [sup 10]B (by weight) to the concrete is also investigated. The second part of this paper determines the radiation dose to the major organs of a patient during a treatment. Simulations use the MIRD 5 anthropomorphic phantom to calculate organ doses from a 20 mA proton beam assuming various envisioned moderator/reflector in place. Doses are tabulated by component and for a given uniform [sup 10]B loading in all organs. These are presented in for a BeO moderator and for an Al/AlF[sub 3] moderator. Dose estimates for different [sup 10]B loadings may be scaled.

  18. Accelerator mass spectrometry and radioisotope detection at the Argonne FN tandem facility

    SciTech Connect

    Henning, W.; Kutschera, W.; Paul, M.; Smither, R.K.; Stephenson, E.J.; Yntema, J.L.

    1980-01-01

    The Argonne FN tandem accelerator and standard components of its experimental heavy-ion research facility, have been used as a highly-sensitive mass spectrometer to detect several long-lived radioisotopes and measure their concentration by counting of accelerated ions. Background beams from isobaric nuclei have been eliminated by combining the dispersion from the energy loss in a uniform Al foil stack with the momentum resolution of an Enge split-pole magnetic spectrograph. Radioisotope concentrations in the following ranges have been measured: /sup 14/C//sup 12/C = 10/sup -12/ to 10/sup -13/, /sup 26/Al//sup 27/Al = 10/sup -10/ to 10/sup -12/, /sup 32/Si/Si = 10/sup -8/ to 10/sup -14/, /sup 36/Cl/Cl = 10/sup -10/ to 10/sup -11/. Particular emphasis was put on exploring to what extent the technique of identifying and counting individual ions in an accelerator beam can be conveniently used to determine nuclear quantities of interest when their measurement involves very low radioisotope concentrations. The usefulness of this method can be demonstrated by measuring the /sup 26/Mg(p,n)/sup 26/Al(7.2 x 10/sup 5/ yr) cross section at proton energies in the astrophysically interesting range just above threshold, and by determining the previously poorly known half life of /sup 32/Si.

  19. An accelerator facility for WDM, HEDP, and HIF investigations in Nazarbayev University

    NASA Astrophysics Data System (ADS)

    Kaikanov, M.; Baigarin, K.; Tikhonov, A.; Urazbayev, A.; Kwan, J. W.; Henestroza, E.; Remnev, G.; Shubin, B.; Stepanov, A.; Shamanin, V.; Waldron, W. L.

    2016-05-01

    Nazarbayev University (NU) in Astana, Kazakhstan, is planning to build a new multi-MV, ∼10 to several hundred GW/cm2 ion accelerator facility which will be used in studies of material properties at extreme conditions relevant to ion-beam-driven inertial fusion energy, and other applications. Two design options have been considered. The first option is a 1.2 MV induction linac similar to the NDCX-II at LBNL, but with modifications, capable of heating a 1 mm spot size thin targets to a few eV temperature. The second option is a 2 - 3 MV, ∼200 kA, single-gap-diode proton accelerator powered by an inductive voltage adder. The high current proton beam can be focused to ∼1 cm spot size to obtain power densities of several hundred GW/cm2, capable of heating thick targets to temperatures of tens of eV. In both cases, a common requirement to achieving high beam intensity on target and pulse length compression is to utilize beam neutralization at the final stage of beam focusing. Initial experiments on pulsed ion beam neutralization have been carried out on a 0.3 MV, 1.5 GW single-gap ion accelerator at Tomsk Polytechnic University with the goal of creating a plasma region in front of a target at densities exceeding ∼1012 cm-3.

  20. Measuring spin-dependent structure functions at CEBAF

    SciTech Connect

    Schaefer, A.

    1994-04-01

    The author analyses whether CEBAF with a 10 GeV beam could contribute significantly to the understanding of spin-dependent deep-inelastic scattering as well as semi-inclusive reactions. The main advantage of CEBAF is the much better attainable statistics, its great disadvantage its comparably low energy, which limits the accessible x-range to about 0.15 to 0.7. Within these constraints CEBAF could provide (1) high precision data which would be very valuable to understand the Q{sup 2} dependence of the spin-dependent structure functions g{sub 1}(x) and G{sub 2}(x) and (2) the by far most precise determination of the third moments of g{sub 1}(x) and g{sub 2}(x) the latter of which the author argues to be related to a fundamental property of the nucleon.

  1. Neutron source in the MCNPX shielding calculating for electron accelerator driven facility

    SciTech Connect

    Zhong, Z.; Gohar, Y.

    2012-07-01

    Argonne National Laboratory (ANL) of USA and Kharkov Inst. of Physics and Technology (KIPT) of Ukraine have been collaborating on the design development of an experimental neutron source facility. It is an accelerator driven system (ADS) utilizing a subcritical assembly driven by electron accelerator. The facility will be utilized for performing basic and applied nuclear researches, producing medical isotopes, and training young nuclear specialists. Monte Carlo code MCNPX has been utilized as a design tool due to its capability to transport electrons, photons, and neutrons at high energies. However the facility shielding calculations with MCNPX need enormous computational resources and the small neutron yield per electron makes sampling difficulty for the Monte Carlo calculations. A method, based on generating and utilizing neutron source file, was proposed and tested. This method reduces significantly the required computer resources and improves the statistics of the calculated neutron dose outside the shield boundary. However the statistical errors introduced by generating the neutron source were not directly represented in the results, questioning the validity of this methodology, because an insufficiently sampled neutron source can cause error on the calculated neutron dose. This paper presents a procedure for the validation of the generated neutron source file. The impact of neutron source statistic on the neutron dose is examined by calculating the neutron dose as a function of the number of electron particles used for generating the neutron source files. When the value of the calculated neutron dose converges, it means the neutron source has scored sufficient records and statistic does not have apparent impact on the calculated neutron dose. In this way, the validity of neutron source and the shield analyses could be verified. (authors)

  2. Facility for Advanced Accelerator Experimental Tests at SLAC (FACET) Conceptual Design Report

    SciTech Connect

    Amann, J.; Bane, K.; /SLAC

    2009-10-30

    This Conceptual Design Report (CDR) describes the design of FACET. It will be updated to stay current with the developing design of the facility. This CDR begins as the baseline conceptual design and will evolve into an 'as-built' manual for the completed facility. The Executive Summary, Chapter 1, gives an introduction to the FACET project and describes the salient features of its design. Chapter 2 gives an overview of FACET. It describes the general parameters of the machine and the basic approaches to implementation. The FACET project does not include the implementation of specific scientific experiments either for plasma wake-field acceleration for other applications. Nonetheless, enough work has been done to define potential experiments to assure that the facility can meet the requirements of the experimental community. Chapter 3, Scientific Case, describes the planned plasma wakefield and other experiments. Chapter 4, Technical Description of FACET, describes the parameters and design of all technical systems of FACET. FACET uses the first two thirds of the existing SLAC linac to accelerate the beam to about 20GeV, and compress it with the aid of two chicanes, located in Sector 10 and Sector 20. The Sector 20 area will include a focusing system, the generic experimental area and the beam dump. Chapter 5, Management of Scientific Program, describes the management of the scientific program at FACET. Chapter 6, Environment, Safety and Health and Quality Assurance, describes the existing programs at SLAC and their application to the FACET project. It includes a preliminary analysis of safety hazards and the planned mitigation. Chapter 7, Work Breakdown Structure, describes the structure used for developing the cost estimates, which will also be used to manage the project. The chapter defines the scope of work of each element down to level 3.

  3. PROPOSAL FOR A PRE-BUNCHED LASER WAKEFIELD ACCELERATION EXPERIMENT AT THE BNL DUV FEL FACILITY.

    SciTech Connect

    WANG,X.J.SHEEHY,B.WU,Z.GAI,W.TING,A.

    2003-05-12

    We propose a pre-bunched Laser Wakefield Acceleration (LWFA) experiment in a plasma channel at the BNL DUV-FEL Facility. BNL DUV-FEL facility is uniquely qualified to carry out the proposed experiment because of the high-brightness' electron beam and RF synchronized TW Ti:Sapphire laser system. The DUV-FEL is a 200 MeV linac facility equipped with a photocathode RF gun injector, a 100 fs Ti:Sapphire laser system and a magnetic bunch compressor. The proposed LWFA will inject a 150 MeV, 10 fs electron bunch into a centimeters long plasma channel. Simulation and preliminary experiment showed that, high-brightness 10 fs electron bunch with 20 pC charge could be produced using the technique of longitudinal emittance compensation. The initial experiment will be performed using the existing Ti:Sapphire laser system (50mJ, 100 fs) with 30 {micro}m spot and 4 cm channel, the maximum energy gain will be about 15 MeV. We propose to upgrade the existing SDL laser output to 500 mJ with a shorter pulse length (50 fs). For an electron beam spot size of 20 um, the expected energy gain is about 100 MeV for a 5 TW, 50 fs laser pulse.

  4. Accelerator-Based Biological Irradiation Facility Simulating Neutron Exposure from an Improvised Nuclear Device.

    PubMed

    Xu, Yanping; Randers-Pehrson, Gerhard; Turner, Helen C; Marino, Stephen A; Geard, Charles R; Brenner, David J; Garty, Guy

    2015-10-01

    We describe here an accelerator-based neutron irradiation facility, intended to expose blood or small animals to neutron fields mimicking those from an improvised nuclear device at relevant distances from the epicenter. Neutrons are generated by a mixed proton/deuteron beam on a thick beryllium target, generating a broad spectrum of neutron energies that match those estimated for the Hiroshima bomb at 1.5 km from ground zero. This spectrum, dominated by neutron energies between 0.2 and 9 MeV, is significantly different from the standard reactor fission spectrum, as the initial bomb spectrum changes when the neutrons are transported through air. The neutron and gamma dose rates were measured using a custom tissue-equivalent gas ionization chamber and a compensated Geiger-Mueller dosimeter, respectively. Neutron spectra were evaluated by unfolding measurements using a proton-recoil proportional counter and a liquid scintillator detector. As an illustration of the potential use of this facility we present micronucleus yields in single divided, cytokinesis-blocked human peripheral lymphocytes up to 1.5 Gy demonstrating 3- to 5-fold enhancement over equivalent X-ray doses. This facility is currently in routine use, irradiating both mice and human blood samples for evaluation of neutron-specific biodosimetry assays. Future studies will focus on dose reconstruction in realistic mixed neutron/photon fields. PMID:26414507

  5. Biological shield design and analysis of KIPT accelerator-driven subcritical facility.

    SciTech Connect

    Zhong, Z.; Gohar, Y.; Nuclear Engineering Division

    2009-12-01

    Argonne National Laboratory of the United States and Kharkov Institute of Physics and Technology of Ukraine have been collaborating on the conceptual design development of an electron accelerator-driven subcritical facility. The facility will be utilized for performing basic and applied nuclear research, producing medical isotopes, and training young nuclear specialists. This paper presents the design and analyses of the biological shield performed for the top section of the facility. The neutron source driving the subcritical assembly is generated from the interaction of a 100-kW electron beam with a natural uranium target. The electron energy is in the range of 100 to 200 MeV, and it has a uniform spatial distribution. The shield design and the associated analyses are presented including different parametric studies. In the analyses, a significant effort was dedicated to the accurate prediction of the radiation dose outside the shield boundary as a function of the shield thickness without geometrical approximations or material homogenization. The MCNPX Monte Carlo code was utilized for the transport calculation of electrons, photons, and neutrons. Weight window variance-reduction techniques were introduced, and the dose equivalent outside the shield can be calculated with reasonably good statistics.

  6. CEBAF Upgrade Cryomodule Component Testing in the Horizontal Test Bed (HTB)

    SciTech Connect

    I.E. Campisi; B. Carpenter; G.K. Davis; J. Delayen; M. Drury; E. Feldl; J. Fischer; A. Guerra; P. Kneisel; T. Hiatt; C. Hovater; K. Macha; J. Mammosser; V. Nguyen; L. Phillips; J. Preble

    2001-06-01

    The planned upgrade of the CEBAF electron accelerator includes the development of an improved cryomodule. Several components differ substantially from the original CEBAF cryomodule; these include: the new 7-cell, 1.5 GHz cavities with integral helium vessel, a new, backlash-free cavity tuner, the waveguide coupler with its room-temperature ceramic window, and the HOM damping filters. In order to test the design features and performance of the new components, a horizontal cryostat (Horizontal Test Bed) has been constructed which allows testing with a turn around time of less than three weeks. This cryostat provides the environment for testing one or two cavities, with associated auxiliary components, in a condition similar to that of a real cryomodule. A series of tests has been performed on a prototype 7-cell cavity and the above-mentioned systems. In this paper the results of the tests on the cryostat, on the cavity performance, on its coupler, on the tuner characteristics, and on the microphonics behavior will be reported.

  7. AGS SUPER NEUTRINO BEAM FACILITY ACCELERATOR AND TARGET SYSTEM DESIGN (NEUTRINO WORKING GROUP REPORT-II).

    SciTech Connect

    DIWAN,M.; MARCIANO,W.; WENG,W.; RAPARIA,D.

    2003-04-21

    This document describes the design of the accelerator and target systems for the AGS Super Neutrino Beam Facility. Under the direction of the Associate Laboratory Director Tom Kirk, BNL has established a Neutrino Working Group to explore the scientific case and facility requirements for a very long baseline neutrino experiment. Results of a study of the physics merit and detector performance was published in BNL-69395 in October 2002, where it was shown that a wide-band neutrino beam generated by a 1 MW proton beam from the AGS, coupled with a half megaton water Cerenkov detector located deep underground in the former Homestake mine in South Dakota would be able to measure the complete set of neutrino oscillation parameters: (1) precise determination of the oscillation parameters {Delta}m{sub 32}{sup 2} and sin{sup 2} 2{theta}{sub 32}; (2) detection of the oscillation of {nu}{sub {mu}}-{nu}{sub e} and measurement of sin{sup 2} 2{theta}{sub 13}; (3) measurement of {Delta}m{sub 21}{sup 2} sin 2{theta}{sub 12} in a {nu}{sub {mu}} {yields} {nu}{sub e} appearance mode, independent of the value of {theta}{sub 13}; (4) verification of matter enhancement and the sign of {Delta}m{sub 32}{sup 2}; and (5) determination of the CP-violation parameter {delta}{sub CP} in the neutrino sector. This report details the performance requirements and conceptual design of the accelerator and the target systems for the production of a neutrino beam by a 1.0 MW proton beam from the AGS. The major components of this facility include a new 1.2 GeV superconducting linac, ramping the AGS at 2.5 Hz, and the new target station for 1.0 MW beam. It also calls for moderate increase, about 30%, of the AGS intensity per pulse. Special care is taken to account for all sources of proton beam loss plus shielding and collimation of stray beam halo particles to ensure equipment reliability and personal safety. A preliminary cost estimate and schedule for the accelerator upgrade and target system are also

  8. Development of a Dielectric-Loaded Accelerator Test Facility Based on an X-Band Magnicon Amplifier

    SciTech Connect

    Gold, S. H.; Fliflet, A. W.; Kinkead, A. K.; Gai, W.; Power, J. G.; Konecny, R.; Jing, C.; Tantawi, S. G.; Nantista, C. D.; Hu, Y.; Du, X.; Tang, C.; Lin, Y.; Bruce, R. W.; Bruce, R. L.; Lewis, D. III

    2006-01-03

    The Naval Research Laboratory (NRL) and Argonne National Laboratory (ANL), in collaboration with the Stanford Linear Accelerator Center (SLAC), are developing a dielectric-loaded accelerator (DLA) test facility powered by the 11.424-GHz magnicon amplifier that was developed jointly by NRL and Omega-P, Inc. Thus far, DLA structures developed by ANL have been tested at the NRL Magnicon Facility without injected electrons, including tests of alumina and magnesium calcium titanate structures at gradients up to {approx}8 MV/m. The next step is to inject electrons in order to build a compact DLA test accelerator. The Accelerator Laboratory of Tsinghua University in Beijing, China has developed a 5-MeV electron injector for the accelerator, and SLAC is developing a means to combine the two magnicon output arms, and to drive the injector and an accelerator section with separate control of the power ratio and relative phase. Also, RWBruce Associates, working with NRL, is developing a means to join ceramic tubes to produce long accelerating sections using a microwave brazing process. The installation and commissioning of the first dielectric-loaded test accelerator, including injector, DLA structure, and spectrometer, should take place within the next year.

  9. Gadolinium-148 and other spallation production cross section measurements for accelerator target facilities

    NASA Astrophysics Data System (ADS)

    Kelley, Karen Corzine

    At the Los Alamos Neutron Science Center accelerator complex, protons are accelerated to 800 MeV and directed to two tungsten targets, Target 4 at the Weapons Neutron Research facility and the 1L target at the Lujan Center. The Department of Energy requires hazard classification analyses to be performed on these targets and places limits on certain radionuclide inventories in the targets to avoid characterizing the facilities as "nuclear facilities." Gadolinium-148 is a radionuclide created from the spallation of tungsten. Allowed isotopic inventories are particularly low for this isotope because it is an alpha-particle emitter with a 75-year half-life. The activity level of Gadolinium-148 is low, but it encompasses almost two-thirds of the total dose burden for the two tungsten targets based on present yield estimates. From a hazard classification standpoint, this severely limits the lifetime of these tungsten targets. The cross section is not well-established experimentally and this is the motivation for measuring the Gadolinium-148 production cross section from tungsten. In a series of experiments at the Weapons Neutron Research facility, Gadolinium-148 production was measured for 600- and 800-MeV protons on tungsten, tantalum, and gold. These experiments used 3 mum thin tungsten, tantalum, and gold foils and 10 mum thin aluminum activation foils. In addition, spallation yields were determined for many short-lived and long-lived spallation products with these foils using gamma and alpha spectroscopy and compared with predictions of the Los Alamos National Laboratory codes CEM2k+GEM2 and MCNPX. The cumulative Gadolinium-148 production cross section measured from tantalum, tungsten, and gold for incident 600-MeV protons were 15.2 +/- 4.0, 8.31 +/- 0.92, and 0.591 +/- 0.155, respectively. The average production cross sections measured at 800 MeV were 28.6 +/- 3.5, 19.4 +/- 1.8, and 3.69 +/- 0.50 for tantalum, tungsten, and gold, respectively. These cumulative

  10. Characterization of the radiation environment at the UNLV accelerator facility during operation of the Varian M6 linac

    NASA Astrophysics Data System (ADS)

    Hodges, M.; Barzilov, A.; Chen, Y.; Lowe, D.

    2016-10-01

    The bremsstrahlung photon flux from the UNLV particle accelerator (Varian M6 model) was determined using MCNP5 code for 3 MeV and 6 MeV incident electrons. Human biological equivalent dose rates due to accelerator operation were evaluated using the photon flux with the flux-to-dose conversion factors. Dose rates were computed for the accelerator facility for M6 linac use under different operating conditions. The results showed that the use of collimators and linac internal shielding significantly reduced the dose rates throughout the facility. It was shown that the walls of the facility, in addition to the earthen berm enveloping the building, provide equivalent shielding to reduce dose rates outside to below the 2 mrem/h limit.

  11. Accelerated Discovery of Thermoelectric Materials: Combinatorial Facility and High-Throughput Measurement of Thermoelectric Power Factor.

    PubMed

    García-Cañadas, Jorge; Adkins, Nicholas J E; McCain, Stephen; Hauptstein, Bastian; Brew, Ashley; Jarvis, David J; Min, Gao

    2016-06-13

    A series of processes have been developed to facilitate the rapid discovery of new promising thermoelectric alloys. A novel combinatorial facility where elements are wire-fed and laser-melted was designed and constructed. Different sample compositions can be achieved by feeding different element wires at specific rates. The composition of all the samples prepared was tested by energy dispersive X-ray spectroscopy (EDS). Then, their thermoelectric properties (power factor) at room temperature were screened in a specially designed new high-throughput setup. After the screening, the thermoelectric properties can be mapped with the possibility of identifying compositional trends. As a proof-of-concept, a promising thermoelectric ternary system, Al-Fe-Ti, has been identified, demonstrating the capability of this accelerated approach. PMID:27186664

  12. Overview of progress on the improvement projects for the LANSCE accelerator and target facilities

    SciTech Connect

    Macek, R.J.; Browne, J.; Brun, T.; Donahue, J.B.; Fitzgerald, D.H.; Hoffman, E.; Pynn, R.; Schriber, S.; Weinacht, D.

    1997-06-01

    Three projects have been initiated since 1994 to improve the performance of the accelerator and target facilities for the Los Alamos Neutron Science Center (LANSCE). The LANSCE Reliability Improvement Project (LRIP) was separated into two phases. Phase 1, completed in 1995, targeted near-term improvements to beam reliability and availability that could be completed in one-year`s time. Phase 2, now underway and scheduled for completion in May 1998, consists of two projects: (a) implementation of direct H-injection for the Proton Storage Ring (PSR) and (b) an upgrade of the target/moderator system for the short pulse spallation neutron (SPSS) source. The latter will reduce the target change-out time from about 10 months to about three weeks. The third project, the SPSS Enhancement Project, is aimed at increasing the PSR output beam current to 200 {micro}A at 30 Hz and providing up to seven new neutron scattering instruments.

  13. A nuclear physics program at the Rare Isotope Beams Accelerator Facility in Korea

    SciTech Connect

    Moon, Chang-Bum

    2014-04-15

    This paper outlines the new physics possibilities that fall within the field of nuclear structure and astrophysics based on experiments with radioactive ion beams at the future Rare Isotope Beams Accelerator facility in Korea. This ambitious multi-beam facility has both an Isotope Separation On Line (ISOL) and fragmentation capability to produce rare isotopes beams (RIBs) and will be capable of producing and accelerating beams of wide range mass of nuclides with energies of a few to hundreds MeV per nucleon. The large dynamic range of reaccelerated RIBs will allow the optimization in each nuclear reaction case with respect to cross section and channel opening. The low energy RIBs around Coulomb barrier offer nuclear reactions such as elastic resonance scatterings, one or two particle transfers, Coulomb multiple-excitations, fusion-evaporations, and direct capture reactions for the study of the very neutron-rich and proton-rich nuclides. In contrast, the high energy RIBs produced by in-flight fragmentation with reaccelerated ions from the ISOL enable to explore the study of neutron drip lines in intermediate mass regions. The proposed studies aim at investigating the exotic nuclei near and beyond the nucleon drip lines, and to explore how nuclear many-body systems change in such extreme regions by addressing the following topics: the evolution of shell structure in areas of extreme proton to neutron imbalance; the study of the weak interaction in exotic decay schemes such as beta-delayed two-neutron or two-proton emission; the change of isospin symmetry in isobaric mirror nuclei at the drip lines; two protons or two neutrons radioactivity beyond the drip lines; the role of the continuum states including resonant states above the particle-decay threshold in exotic nuclei; and the effects of nuclear reaction rates triggered by the unbound proton-rich nuclei on nuclear astrophysical processes.

  14. Upgrade of the Drive LINAC for the AWA Facility Dielectric Two-Beam Accelerator

    SciTech Connect

    Power, John; Conde, Manoel; Gai, Wei; Li, Zenghai; Mihalcea, Daniel; /Northern Illinois U.

    2012-07-02

    We report on the design of a seven-cell, standing-wave, 1.3-GHz rf cavity and the associated beam dynamics studies for the upgrade of the drive beamline LINAC at the Argonne Wakefield Accelerator (AWA) facility. The LINAC design is a compromise between single-bunch operation (100 nC {at} 75 MeV) and minimization of the energy droop along the bunch train during bunch-train operation. The 1.3-GHz drive bunch-train target parameters are 75 MeV, 10-20-ns macropulse duration, and 16 x 60 nC microbunches; this is equivalent to a macropulse current and beam power of 80 A and 6 GW, respectively. Each LINAC structure accelerates approximately 1000 nC in 10 ns by a voltage of 11 MV at an rf power of 10 MW. Due to the short bunch-train duration desired ({approx}10 ns) and the existing frequency (1.3 GHz), compensation of the energy droop along the bunch train is difficult to accomplish by means of the two standard techniques: time-domain or frequency-domain beam loading compensation. Therefore, to minimize the energy droop, our design is based on a large stored energy rf cavity. In this paper, we present our rf cavity optimization method, detailed rf cavity design, and beam dynamics studies of the drive beamline.

  15. The proton injector for the accelerator facility of antiproton and ion research (FAIR)

    SciTech Connect

    Ullmann, C. Kester, O.; Chauvin, N.; Delferriere, O.

    2014-02-15

    The new international accelerator facility for antiproton and ion research (FAIR) at GSI in Darmstadt, Germany, is one of the largest research projects worldwide and will provide an antiproton production rate of 7 × 10{sup 10} cooled pbars per hour. This is equivalent to a primary proton beam current of 2 × 10{sup 16} protons per hour. For this request a high intensity proton linac (p-linac) will be built with an operating rf-frequency of 325 MHz to accelerate a 35 mA proton beam at 70 MeV, using conducting crossed-bar H-cavities. The repetition rate is 4 Hz with beam pulse length of 36 μs. The microwave ion source and low energy beam transport developed within a joint French-German collaboration GSI/CEA-SACLAY will serve as an injector of the compact proton linac. The 2.45 GHz ion source allows high brightness ion beams at an energy of 95 keV and will deliver a proton beam current of 100 mA at the entrance of the radio frequency quadrupole (RFQ) within an acceptance of 0.3π mm mrad (norm., rms)

  16. Nucleon Form Factors experiments with 12 GeV CEBAF

    SciTech Connect

    Wojtsekhowski, B.

    2008-10-13

    A number of precision form factor experiments at high momentum transfer will be performed with the 11 GeV electron beam of CEBAF. We review the approved proposals and the conceptual schemes of several new suggestions. Form factor data will serve as a major input for the construction of a tomographic image of the nucleon.

  17. The JLAB 12 GeV Energy Upgrade of CEBAF

    SciTech Connect

    Harwood, Leigh H.

    2013-12-01

    This presentation should describe the progress of the 12GeV Upgrade of CEBAF at Jefferson Lab. The status of the upgrade should be presented as well as details on the construction, procurement, installation and commissioning of the magnet and SRF components of the upgrade.

  18. YALINA facility a sub-critical Accelerator- Driven System (ADS) for nuclear energy research facility description and an overview of the research program (1997-2008).

    SciTech Connect

    Gohar, Y.; Smith, D. L.; Nuclear Engineering Division

    2010-04-28

    The YALINA facility is a zero-power, sub-critical assembly driven by a conventional neutron generator. It was conceived, constructed, and put into operation at the Radiation Physics and Chemistry Problems Institute of the National Academy of Sciences of Belarus located in Minsk-Sosny, Belarus. This facility was conceived for the purpose of investigating the static and dynamic neutronics properties of accelerator driven sub-critical systems, and to serve as a neutron source for investigating the properties of nuclear reactions, in particular transmutation reactions involving minor-actinide nuclei. This report provides a detailed description of this facility and documents the progress of research carried out there during a period of approximately a decade since the facility was conceived and built until the end of 2008. During its history of development and operation to date (1997-2008), the YALINA facility has hosted several foreign groups that worked with the resident staff as collaborators. The participation of Argonne National Laboratory in the YALINA research programs commenced in 2005. For obvious reasons, special emphasis is placed in this report on the work at YALINA facility that has involved Argonne's participation. Attention is given here to the experimental program at YALINA facility as well as to analytical investigations aimed at validating codes and computational procedures and at providing a better understanding of the physics and operational behavior of the YALINA facility in particular, and ADS systems in general, during the period 1997-2008.

  19. AIRIX: an induction accelerator facility developed at CEA for flash radiography in detonics

    NASA Astrophysics Data System (ADS)

    Cavailler, Claude

    1999-06-01

    AIRIX is an induction linear accelerator which will be used for flash radiography in CEA/DAM. Designed to produce an X-ray dose of more than 500 Rads at 1 meter with an X-ray focal spot size diameter of less than 2 mm (LANL-CEA DAM definition), this facility consists in a 4 MeV/3.5 kA pulsed electron injector and 16 MeV induction accelerator powered by 32 high voltage generators. A prototype of this accelerator, called PIVAIR, has been studied and realized in CEA CESTA near Bordeaux. PIVAIR is a validation step for AIRIX at 8 MeV. It includes an injector (4 MeV, 3.5 kA, 60 ns) and 16 inductor cells supplied by 8 high voltage generators (250 kV, 70 ns). Two different technologies of induction cells have been tested (rexolite insulator or ferrite under vacuum). We have chosen ferrite under vacuum cells technology after comparison of results on beam transport and reliability tests. A focusing experiment at 7.2 MeV of the electron beam as been achieved during summer 1997. We have begun to produce X-rays in October 1997. A dose level of 50 Rad at 1 meter has been achieved with an X-ray spot size diameter of 3.5 to 4 mm (LANL-CEA DAM definition). Static flash radiography of very dense object have been achieved from November 97 until February 98. We have been able to test in situ new kinds of very high sensitive X- ray detectors and to check they had reached our very ambitious goals: (1) quantum efficiency at 5 MeV greater than 50% instead of 1% for luminous screens and film; (2) sensitivity less than 10 (mu) Rad (100 time more sensitive than radiographic luminous screens and films); (3) dynamic range greater than 100; (4) resolution less than 2 mm. We will present in this communication brand new kinds of detection systems, called high stopping power detectors, such as: (1) (gamma) camera with segmented thick crystal of BGO and MCP image intensifier; (2) multistep parallel plate avalanche chamber; (3) pixellized CdTe MeV photoconductor matrix. AIRIX accelerator is being

  20. The physics of sub-critical lattices in accelerator driven hybrid systems: The MUSE experiments in the MASURCA facility

    SciTech Connect

    Chauvin, J. P.; Lebrat, J. F.; Soule, R.; Martini, M.; Jacqmin, R.; Imel, G. R.; Salvatores, M.

    1999-06-10

    Since 1991, the CEA has studied the physics of hybrid systems, involving a sub-critical reactor coupled with an accelerator. These studies have provided information on the potential of hybrid systems to transmute actinides and, long lived fission products. The potential of such a system remains to be proven, specifically in terms of the physical understanding of the different phenomena involved and their modelling, as well as in terms of experimental validation of coupled systems, sub-critical environment/accelerator. This validation must be achieved through mock-up studies of the sub-critical environments coupled to a source of external neutrons. The MUSE-4 mock-up experiment is planed at the MASURCA facility and will use an accelerator coupled to a tritium target. The great step between the generator used in the past and the accelerator will allow to increase the knowledge in hybrid physic and to decrease the experimental biases and the measurement uncertainties.

  1. Assessment of soil and ground-water activation in the underground facility of the linear accelerator at RAON

    NASA Astrophysics Data System (ADS)

    Lee, Sangjin; Nam, Shinwoo; Chung, Yonsei; Kim, Suna; Lee, Cheol Woo

    2015-10-01

    RAON is a heavy-ion accelerator complex that is being constructed in Daejeon, Korea. The superconducting linear accelerator of RAON will provide various heavy-ion beams with a maximum power of 400 kW. In order to determine the design requirements of the underground facility for the accelerator, we considered the radiation's influence on the soil and the ground-water under the condition of long-term operation of the accelerator. A source term for prompt neutrons generated by heavy-ion beams losses along the beam lines at a rate of 1 W/m was applied to obtain the activation level of nearby material outside the tunnel by using the simulation codes MCNPX and SP-FISPACT. This report presents the analysis and the result for the tunnel shielding condition obtained from the assessment.

  2. Electron-Ion Collider at CEBAF: New Insights and Conceptual Progress

    SciTech Connect

    Yaroslav Derbenev; Andrei Afanasev; Kevin Beard; Lawrence Cardman; Swapan Chattopadhyay; Pavel Degtiarenko; Jean Delayen; Rolf Ent; Andrew Hutton; Geoffrey Krafft; Rui Li; Nikolitsa Merminga; Benard Poelker; Byung Yunn; Petr Ostroumov

    2004-07-01

    We report on progress in the conceptual development of the proposed high luminosity (up to 1035 cm-2s-1) and efficient spin manipulation (using ''figure 8'' boosters and collider rings) Electron-Ion Collider at the CEBAF. This facility would use a polarized 5-7 GeV electron beam from a superconducting energy recovering linac with a kicker-operated circulator ring, and a 30-150 GeV ion beam in a storage ring (for polarized p, d, 3He, Li and unpolarized totally stripped nuclei up to Ar). Ultra-high luminosity is envisioned to be achieved with very short crab-crossing bunches at 1.5 GHz repetition rate. Our recent studies were concentrated on understanding beam-beam interaction, ion beam instabilities, luminosity lifetime due to intrabeam scatterings, ERL-ring synchronization, and ion spin control. We also proposed a preliminary conceptual design of the interaction region.

  3. Implementation of the Polarized HD target at the Thomas Jefferson National Accelerator Facility

    SciTech Connect

    Chaden Djalali; David Tedeschi

    2007-01-30

    The original goal of this proposal was to study frozen spin polarized targets (HD target and other technologies) and produce a conceptual design report for the implementation of such a target in the HALL B detector of the Thomas Jefferson National Accelerator Facility (JLab). During the first two years of the proposal, we came to the conclusion that the best suited target for JLab was a frozen spin target and helped with the design of such a target. We have not only achieved our original goal but have exceeded it by being involved in the actual building and testing of parts the target. The main reason for this success has been the hiring of a senior research associate, Dr. Oleksandr Dzyubak, who had more than 10 years of experience in the field of frozen spin polarized targets. The current grant has allowed the USC nuclear physics group to strengthen its role in the JLab collaboration and make important contribution to both the detector development and the scientific program.

  4. Linear induction accelerators at the Los Alamos National Laboratory DARHT facility

    SciTech Connect

    Nath, Subrata

    2010-09-07

    The Dual-Axis Radiographic Hydrodynamic Test Facility (DARHT) at Los Alamos National Laboratory consists of two linear induction accelerators at right angles to each other. The First Axis, operating since 1999, produces a nominal 20-MeV, 2-kA single beam-pulse with 60-nsec width. In contrast, the DARHT Second Axis, operating since 2008, produces up to four pulses in a variable pulse format by slicing micro-pulses out of a longer {approx}1.6-microseconds (flat-top) pulse of nominal beam-energy and -current of 17 MeV and 2 kA respectively. Bremsstrahlung x-rays, shining on a hydro-dynamical experimental device, are produced by focusing the electron beam-pulses onto a high-Z target. Variable pulse-formats allow for adjustment of the pulse-to-pulse doses to record a time sequence of x-ray images of the explosively driven imploding mock device. Herein, we present a sampling of the numerous physics and engineering aspects along with the current status of the fully operational dual axes capability. First successful simultaneous use of both the axes for a hydrodynamic experiment was achieved in 2009.

  5. ATTO SECOND ELECTRON BEAMS GENERATION AND CHARACTERIZATION EXPERIMENT AT THE ACCELERATOR TEST FACILITY.

    SciTech Connect

    ZOLOTOREV, M.; ZHOLENTS, A.; WANG, X.J.; BABZIEN, M.; SKARITKA, J.; RAKOWSKY, G.; YAKIMENKO, V.

    2002-02-01

    We are proposing an Atto-second electron beam generation and diagnostics experiment at the Brookhaven Accelerator Test facility (ATF) using 1 {micro}m Inverse Free Electron Laser (IFEL). The proposed experiment will be carried out by an BNL/LBNL collaboration, and it will be installed at the ATF beam line II. The proposed experiment will employ a one-meter long undulator with 1.8 cm period (VISA undulator). The electron beam energy will be 63 MeV with emittance less than 2 mm-mrad and energy spread less than 0.05%. The ATF photocathode injector driving laser will be used for energy modulation by Inverse Free Electron Laser (IFEL). With 10 MW laser peak power, about 2% total energy modulation is expected. The energy modulated electron beam will be further bunched through either a drift space or a three magnet chicane into atto-second electron bunches. The attosecond electron beam bunches will be analyzed using the coherent transition radiation (CTR).

  6. Radiograaff, a proton irradiation facility for radiobiological studies at a 4 MV Van de Graaff accelerator

    NASA Astrophysics Data System (ADS)

    Constanzo, J.; Fallavier, M.; Alphonse, G.; Bernard, C.; Battiston-Montagne, P.; Rodriguez-Lafrasse, C.; Dauvergne, D.; Beuve, M.

    2014-09-01

    A horizontal beam facility for radiobiological experiments with low-energy protons has been set up at the 4 MV Van de Graaff accelerator of the Institut de Physique Nucléaire de Lyon. A homogeneous irradiation field with a suitable proton flux is obtained by means of two collimators and two Au-scattering foils. A monitoring chamber contains a movable Faraday cup, a movable quartz beam viewer for controlling the intensity and the position of the initial incident beam and four scintillating fibers for beam monitoring during the irradiation of the cell samples. The beam line is ended by a thin aluminized Mylar window (12 μm thick) for the beam extraction in air. The set-up was simulated by the GATE v6.1 Monte-Carlo platform. The measurement of the proton energy distribution, the evaluation of the fluence-homogeneity over the sample and the calibration of the monitoring system were performed using a silicon PIPS detector, placed in air in the same position as the biological samples to be irradiated. The irradiation proton fluence was found to be homogeneous to within ±2% over a circular field of 20 mm diameter. As preliminary biological experiment, two Human Head and Neck Squamous Carcinoma Cell lines (with different radiosensitivities) were irradiated with 2.9 MeV protons. The measured survival curves are compared to those obtained after X-ray irradiation, giving a Relative Biological Efficiency between 1.3 and 1.4.

  7. Design and high order optimization of the Accelerator Test Facility lattices

    NASA Astrophysics Data System (ADS)

    Marin, E.; Tomás, R.; Bambade, P.; Kubo, K.; Okugi, T.; Tauchi, T.; Terunuma, N.; Urakawa, J.; Seryi, A.; White, G. R.; Woodley, M.

    2014-02-01

    The Accelerator Test Facility 2 (ATF2) aims to test the novel chromaticity correction scheme which is implemented in the final focus systems of future linear colliders such as the International Linear Collider (ILC) and the Compact Linear Collider (CLIC). The ATF2 nominal and ultralow β* lattices are designed to vertically focus the beam at the focal point, or usually referred to as interaction point (IP), down to 37 and 23 nm, respectively. The vertical chromaticities of the nominal and ultralow β* lattices are comparable to those of ILC and CLIC, respectively. When the measured multipole components of the ATF2 magnets are considered in the simulations, the evaluated spot sizes at the IP are well above the design values. In this paper we describe the analysis of the high order aberrations that allows identifying the sources of the observed beam size growth. In order to recover the design spot sizes three solutions are considered, namely final doublet replacement, octupole insertion, and optics modification. Concerning the future linear collider projects, the consequences of magnetic field errors of the focusing quadrupole magnet of the final doublet are also addressed.

  8. Preventing vacuum leaks in the Continuous Electron Beam Accelerator Facility cavity pair bellows

    SciTech Connect

    Henkel, D.P. ); Doolittle, L.R. )

    1994-09-01

    Occasional vacuum leaks have occurred in bellows assemblies of helium pressure vessels at the Continuous Electron Beam Accelerator Facility. The flanged stainless steel bellows assemblies are used to connect the niobium rf cavity pairs to the surrounding liquid helium pressure vessels. An investigation of the source of these leaks has revealed a through-thickness network of microcracks in the cuff weld zones. The cuff material contained a mixture of soft and very hard elongated intermetallic inclusions that were oriented parallel with the weld fusion line; these inclusions served as crack initiation sites. Surface-exposed inclusions, in contact with a chlorine residue from a postweld machining process, induced crevice corrosion during a year of storage. Residual stresses in the weld led to a combination of lamellar tearing and stress corrosion cracking. Propagation of the cracks from one inclusion to another resulted in continuous vacuum leakage paths from the primary (2 K) helium circuit to the vacuum insulation space. Additional vacuum leaks were prevented by reconfiguring the weld geometry and avoiding any processing with chlorinated substances.

  9. Preventing vacuum leaks in the Continuous Electron Beam Accelerator Facility cavity pair bellows

    SciTech Connect

    Daniel P. Henkel; Lawrence R. Doolittle

    1994-05-01

    Occasional vacuum leaks have occurred in bellows assemblies of helium pressure vessels at the Continuous Electron Beam Accelerator Facility. The flanged stainless steel bellows assemblies are used to connect the niobium rf cavity pairs to the surrounding liquid helium pressure vessels. An investigation of the source of these leaks has revealed a through-thickness network of microcracks in the cuff weld zones. The cuff material contained a mixture of soft and very hard elongated intermetallic inclusions that were oriented parallel with the weld fusion line; these inclusions served as crack initiation sites. Surface-exposed inclusions, in contact with a chlorine residue from a postweld machining process, induced crevice corrosion during a year of storage. Residual stresses in the weld led to a combination of lamellar tearing and stress corrosion cracking. Propagation of the cracks from one inclusion to another resulted in continuous vacuum leakage paths from the primary (2 K) helium circuit to the vacuum insulation space. Additional vacuum leaks were prevented by reconfiguring the weld geometry and avoiding any processing with chlorinated substances.

  10. Radiation impact caused by activation of air from the future GSI accelerator facility fair.

    PubMed

    Gutermuth, F; Wildermuth, H; Radon, T; Fehrenbacher, G

    2005-01-01

    The Gesellschaft für Schwerionenforschung in Darmstadt is planning a new accelerator Facility for Antiproton and Ion Research (FAIR). Two future experimental areas are regarded to be the most decisive points concerning the activation of air. One is the area for the production of antiprotons. A second crucial experimental area is the so-called Super Fragment Separator. The production of radioactive isotopes in air is calculated using the residual nuclei option of the Monte Carlo program FLUKA. The results are compared with the data for the activation of air given by Sullivan and in IAEA report 283. The resulting effective dose is calculated using a program package from the German Federal Office for Radiation Protection, the Bundesamt für Stranlenschutz. The results demonstrate that a direct emission of the total radioactivity produced into the air will probably conflict with the limits of the German Radiation Protection Ordinance. Special measures have to be planned in order to reduce the amount of radioactivity released into the air. PMID:16381762

  11. A VXIbus based trigger for the CLAS detector at CEBAF

    SciTech Connect

    Doughty, D.C. Jr.; Englert, J.; Hale, R.; Lemon, S. ); Leung, P. ); Cuevas, C.; Joyce, D. )

    1992-04-01

    This paper discusses a VXIbus based first level triggering system for the CLAS detector at CEBAF which has been designed and prototyped. It uses pipelining and a triple memory lookup to produce a dead-timeless trigger decision with an average latency of 110 ns and a jitter of 20 ns. The VXIbus Extended Start/Stop triggering protocols allow sub-nanosecond time synchronization.

  12. A VXIbus based trigger for the CLAS detector at CEBAF

    SciTech Connect

    D.C. Doughty, Jr.; J. Englert; R. Hale; S. Lemon; P. Leung; C. Cuevas; D. Joyce

    1992-04-01

    A VXIbus based first level triggering system for the CLAS detector at CEBAF has been designed and prototyped. It uses pipelining and a triple memory lookup to produce a dead-timeless trigger decision with an average latency of 110 nS and a jitter of 20 nS. The VXIbus Extended Start/Stop triggering protocols allow sub-nanosecond time synchronization.

  13. Polarization Measurements in Photoproduction with CEBAF Large Acceptance Spectrometer

    SciTech Connect

    E. Pasyuk

    2010-05-01

    A significant part of the experimental program in Hall-B of the Jefferson Lab is dedicated to the studies of the structure of baryons. CEBAF Large Acceptance Spectrometer (CLAS), availability of circularly and linearly polarized photon beams and recent addition of polarized targets provides remarkable opportunity for single, double and in some cases triple polarization measurements in photoproduction. An overview of the experiments will be presented.

  14. Restoration of accelerator facilities damaged by Great East Japan Earthquake at Cyclotron and Radioisotope Center, Tohoku University.

    PubMed

    Wakui, Takashi; Itoh, Masatoshi; Shimada, Kenzi; Yoshida, Hidetomo P; Shinozuka, Tsutomu; Sakemi, Yasuhiro

    2014-01-01

    The Cyclotron and Radioisotope Center (CYRIC) of Tohoku University is a joint-use institution for education and research in a wide variety of fields ranging from physics to medicine. Accelerator facilities at the CYRIC provide opportunities for implementing a broad research program, including medical research using positron emission tomography (PET), with accelerated ions and radioisotopes. At the Great East Japan Earthquake on March 11, 2011, no human injuries occurred and a smooth evacuation was made in the CYRIC, thanks to the anti-earthquake measures such as the renovation of the cyclotron building in 2009 mainly to provide seismic strengthening, fixation of shelves to prevent the falling of objects, and securement of the width of the evacuation route. The preparation of an emergency response manual was also helpful. However, the accelerator facilities were damaged because of strong shaking that continued for a few minutes. For example, two columns on which a 930 cyclotron was placed were damaged, and thereby the 930 cyclotron was inclined. All the elements of beam transport lines were deviated from the beam axis. Some peripheral devices in a HM12 cyclotron were broken. Two shielding doors fell from the carriage onto the floor and blocked the entrances to the rooms. The repair work on the accelerator facilities was started at the end of July 2011. During the repair work, the joint use of the accelerator facilities was suspended. After the repair work was completed, the joint use was re-started at October 2012, one and a half years after the earthquake. PMID:25030295

  15. The MIT HEDP Accelerator Facility for education and advanced diagnostics development for OMEGA, Z and the NIF

    NASA Astrophysics Data System (ADS)

    Petrasso, R.; Gatu Johnson, M.; Armstrong, E.; Han, H. W.; Kabadi, N.; Lahmann, B.; Orozco, D.; Rojas Herrera, J.; Sio, H.; Sutcliffe, G.; Frenje, J.; Li, C. K.; Séguin, F. H.; Leeper, R.; Ruiz, C. L.; Sangster, T. C.

    2015-11-01

    The MIT HEDP Accelerator Facility utilizes a 135-keV linear electrostatic ion accelerator, a D-T neutron source and two x-ray sources for development and characterization of nuclear diagnostics for OMEGA, Z, and the NIF. The ion accelerator generates D-D and D-3He fusion products through acceleration of D ions onto a 3He-doped Erbium-Deuteride target. Fusion reaction rates around 106 s-1 are routinely achieved, and fluence and energy of the fusion products have been accurately characterized. The D-T neutron source generates up to 6 × 108 neutrons/s. The two x-ray generators produce spectra with peak energies of 35 keV and 225 keV and maximum dose rates of 0.5 Gy/min and 12 Gy/min, respectively. Diagnostics developed and calibrated at this facility include CR-39 based charged-particle spectrometers, neutron detectors, and the particle Time-Of-Flight (pTOF) and Magnetic PTOF CVD-diamond-based bang time detectors. The accelerator is also a vital tool in the education of graduate and undergraduate students at MIT. This work was supported in part by SNL, DOE, LLE and LLNL.

  16. Physical processes at work in sub-30 fs, PW laser pulse-driven plasma accelerators: Towards GeV electron acceleration experiments at CILEX facility

    NASA Astrophysics Data System (ADS)

    Beck, A.; Kalmykov, S. Y.; Davoine, X.; Lifschitz, A.; Shadwick, B. A.; Malka, V.; Specka, A.

    2014-03-01

    Optimal regimes and physical processes at work are identified for the first round of laser wakefield acceleration experiments proposed at a future CILEX facility. The Apollon-10P CILEX laser, delivering fully compressed, near-PW-power pulses of sub-25 fs duration, is well suited for driving electron density wakes in the blowout regime in cm-length gas targets. Early destruction of the pulse (partly due to energy depletion) prevents electrons from reaching dephasing, limiting the energy gain to about 3 GeV. However, the optimal operating regimes, found with reduced and full three-dimensional particle-in-cell simulations, show high energy efficiency, with about 10% of incident pulse energy transferred to 3 GeV electron bunches with sub-5% energy spread, half-nC charge, and absolutely no low-energy background. This optimal acceleration occurs in 2 cm length plasmas of electron density below 1018 cm-3. Due to their high charge and low phase space volume, these multi-GeV bunches are tailor-made for staged acceleration planned in the framework of the CILEX project. The hallmarks of the optimal regime are electron self-injection at the early stage of laser pulse propagation, stable self-guiding of the pulse through the entire acceleration process, and no need for an external plasma channel. With the initial focal spot closely matched for the nonlinear self-guiding, the laser pulse stabilizes transversely within two Rayleigh lengths, preventing subsequent evolution of the accelerating bucket. This dynamics prevents continuous self-injection of background electrons, preserving low phase space volume of the bunch through the plasma. Near the end of propagation, an optical shock builds up in the pulse tail. This neither disrupts pulse propagation nor produces any noticeable low-energy background in the electron spectra, which is in striking contrast with most of existing GeV-scale acceleration experiments.

  17. Target design optimization for an electron accelerator driven subcritical facility with circular and square beam profiles.

    SciTech Connect

    Gohar, M. Y. A; Sofu, T.; Zhong, Z.; Belch, H.; Naberezhnev, D.; Nuclear Engineering Division

    2008-10-30

    A subcritical facility driven by an electron accelerator is planned at the Kharkov Institute of Physics and Technology (KIPT) in Ukraine for medical isotope production, materials research, training, and education. The conceptual design of the facility is being pursued through collaborations between ANL and KIPT. As part of the design effort, the high-fidelity analyses of various target options are performed with formulations to reflect the realistic configuration and the three dimensional geometry of each design. This report summarizes the results of target design optimization studies for electron beams with two different beam profiles. The target design optimization is performed via the sequential neutronic, thermal-hydraulic, and structural analyses for a comprehensive assessment of each configuration. First, a target CAD model is developed with proper emphasis on manufacturability to provide a basis for separate but consistent models for subsequent neutronic, thermal-hydraulic, and structural analyses. The optimizations are pursued for maximizing the neutron yield, streamlining the flow field to avoid hotspots, and minimizing the thermal stresses to increase the durability. In addition to general geometric modifications, the inlet/outlet channel configurations, target plate partitioning schemes, flow manipulations and rates, electron beam diameter/width options, and cladding material choices are included in the design optimizations. The electron beam interactions with the target assembly and the neutronic response of the subcritical facility are evaluated using the MCNPX code. the results for the electron beam energy deposition, neutron generation, and utilization in the subcritical pile are then used to characterize the axisymmetric heat generation profiles in the target assembly with explicit simulations of the beam tube, the coolant, the clad, and the target materials. Both tungsten and uranium are considered as target materials. Neutron spectra from tungsten

  18. Design of an XUV FEL Driven by the Laser-Plasma Accelerator at theLBNL LOASIS Facility

    SciTech Connect

    Schroeder, Carl B.; Fawley, W.M.; Esarey, Eric; Leemans, W.P.

    2006-09-01

    We present a design for a compact FEL source of ultrafast, high-peak flux, soft x-ray pulses employing a high-current, GeV-energy electron beam from the existing laser-plasma accelerator at the LBNL LOASIS laser facility. The proposed ultra-fast source would be intrinsically temporally synchronized to the drive laser pulse, enabling pump-probe studies in ultra-fast science with pulse lengths of tens of fs. Owing both to the high current ({approx} 10 kA) and reasonable charge/pulse ({approx} 0.1-0.5 nC) of the laser-plasma-accelerated electron beams, saturated output fluxes are potentially 10{sup 13}--10{sup 14} photons/pulse. We examine devices based both on SASE and high-harmonic generated input seeds to give improved coherence and reduced undulator length, presenting both analytic scalings and numerical simulation results for expected FEL performance. A successful source would result in a new class of compact laser-driven FELs in which a conventional RF accelerator is replaced by a GeV-class laser-plasma accelerator whose active acceleration region is only a few cm in length.

  19. Short-orbit spectrometer for Hall C at CEBAF

    SciTech Connect

    Jackson, H.E.; Potterveld, D.H.; Zeidman, B.

    1995-08-01

    An examination of the proposed experimental program for Hall C at CEBAF reveals a major emphasis on coincidence experiments involving a {open_quotes}core{close_quotes} spectrometer and a second arm capable of detecting particles with momenta < 2 GeV/c with moderate energy and angular resolution. In most cases, the core spectrometer serves to tag a virtual photon, which induces a reaction in a nuclear target resulting in the ejection of a hadron in the energy range (0.2-2.0 GeV) which is observed in the second spectrometer. Nuclear physics topics addressed in these experiments include color transparency, nucleon propagation, pion electroproduction, and hyperon physics. All of these programs require an acceptance in the hadron spectrometer as large as possible in solid angle and momentum to maximize operational efficiency. In addition, relatively short spectrometer drift lengths are required in experiments involving detection of pions or kaons in order to minimize decay losses. Because the requirements for energy resolution in this class of experiments is moderate, typically {approximately} 10{sup -3}, an optimized design with a short optical length less than 10 m will provide a well-matched spectrometer capability. Excellent particle discrimination will be essential for detection of pions and kaons in the presence of high backgrounds. Operation at luminosities as high as 10{sup 38}/cm{sup 2} sec will be required frequently. To provide this second-arm capability, the Argonne group has built, under contract to CEBAF, a short-orbit spectrometer, the SOS, based on a QD{bar D} design. The QD{bar D} configuration provides a large momentum acceptance, with good energy resolution and solid-angle acceptance in a very compact geometry which can meet the needs of a broad spectrum of studies appropriate for Hall C at CEBAF.

  20. Mechanical results of the CEBAF cavity series production

    SciTech Connect

    Mammosser, J.; Benesch, J.

    1993-06-01

    Interface dimensions of the full production run of 360 CEBAF cavities manufactured by Siemens are summarized. Analysis indicated that length tolerances of {plus_minus}2 mm and fundamental power coupler location tolerances of {plus_minus}0.15 mm are achievable on future procurements. Vacuum leaks were a concern early in production but have now been overcome: 2 K helium leak rates integrated over 22 vacuum seals have been measured on 84 cavity pairs and a roughly normal distribution of the log{sub 10} (leak rate) is seen, centered about a rate of 10{sup {minus}10.2} torr-1/s.

  1. Fermilab's SC Accelerator Magnet Program for Future U.S. HEP Facilities

    SciTech Connect

    Lamm, Michael; Zlobin, Alexander; /Fermilab

    2010-01-01

    The invention of SC accelerator magnets in the 1970s opened wide the possibilities for advancing the energy frontier of particle accelerators, while limiting the machine circumference and reducing their energy consumption. The successful development of SC accelerator magnets based on NbTi superconductor have made possible a proton-antiproton collider (Tevatron) at Fermilab, an electron-proton collider (HERA) at DESY, a relativistic heavy ion collider (RHIC) at BNL and recently a proton-proton collider (LHC) at CERN. Further technological innovations and inventions are required as the US HEP looks forward towards the post-LHC energy or/and intensity frontiers. A strong, goal oriented national SC accelerator magnet program must take on this challenge to provide a strong base for the future of HEP in the U.S. The results and experience obtained by Fermilab during the past 30 years will allow us to play a leadership role in the SC accelerator magnet development in the U.S., in particular, focusing on magnets for a Muon Collider/Neutrino Factory [1]-[2]. In this paper, we summarize the required Muon Collider magnet needs and challenges, summarize the technology advances in the Fermilab accelerator magnet development over the past few years, and present and discuss our vision and long-term plans for these Fermilab-supported accelerator initiatives.

  2. CEBAF injector achieved world's best beam quality for three simultaneous beam with a wide range of bunch charges

    SciTech Connect

    Reza Kazimi; Kevin Beard; Jay Benesch; Arne Freyberger; Joseph Grames; Tommy Hiatt; a. hutton; Geoffrey Krafft; Nikolitsa Merminga; B. Poelker; M. Spata; Michael Tiefenback; Byung Yunn; Yuhong Zhang

    2004-07-01

    The CEBAF accelerator provides interleaved 499 MHz electron beams, spanning 5 decades in beam intensity (a few nA to 200 {micro}A), to three experimental halls simultaneously. The physics program became more challenging when the G{sup 0} experiment was approved, requiring more than six times higher bunch charge than is routine. This experiment requires up to 8 million electrons per bunch at a reduced repetition rate of 31 MHz, while the lowest current hall simultaneously receives 100 electrons per bunch. A bunch destined for one hall may experience significant space charge forces, while the next bunch may have negligible space charge. This disparity in beam intensity must be maintained while delivering ''best ever'' values in rms beam quality, including relative energy spread (< 2.5 x 10{sup -5}) and normalized transverse emittance (< 1 mm-mrad). Space charge difficulties emerge in the 10 m long, 100 keV section of the CEBAF injector during initial bunch formation and spin manipulation. A series of changes was introduced to meet the new requirements, including adding new magnets, replacing photoinjector lasers, modifying typical laser parameters, stabilizing RF systems, and changing standard operating procedures. In this paper, we discuss these modifications in detail, including the agreement between the experimental results and detailed simulations.

  3. Be aware of neutrons outside short mazes from 10-MV linear accelerators X-rays in radiotherapy facilities.

    PubMed

    Brockstedt, S; Holstein, H; Jakobsson, L; Tomaszewicz, A; Knöös, T

    2015-07-01

    During the radiation survey of a reinstalled 10-MV linear accelerator in an old radiation treatment facility, high dose rates of neutrons were observed. The area outside the maze entrance is used as a waiting room where patients, their relatives and staff other than those involved in the actual treatment can freely pass. High fluence rates of neutrons would cause an unnecessary high effective dose to the staff working in the vicinity of such a system, and it can be several orders higher than the doses received due to X-rays at the same location. However, the common knowledge appears to have been that the effect of neutrons at 10-MV X-ray linear accelerator facilities is negligible and shielding calculations models seldom mention neutrons for this operating energy level. Although data are scarce, reports regarding this phenomenon are now emerging. For the future, it is advocated that contributions from neutrons are considered already during the planning stage of new or modified facilities aimed for 10 MV and that estimated dose levels are verified. PMID:25802465

  4. Nonperturbative QCD and elastic processes at CEBAF energies

    SciTech Connect

    Radyushkin, A.V. |

    1994-04-01

    The author outlines how one can approach nonperturbative aspects of the QCD dynamics studying elastic processes at energies accessible at upgraded CEBAF. The author`s point is that, in the absence of a complete theory of the nonperturbative effects, a possible way out is based on a systematic use of the QCD factorization procedure which separates theoretically understood ({open_quotes}known{close_quotes}) short-distance effects and nonperturbative ({open_quotes}unknown{close_quotes}) long-distance ones. The latter include hadronic distribution amplitudes, soft components of hadronic form factors etc. Incorporating the QCD sum rule version of the QCD factorization approach, one can relate these nonperturbative functions to more fundamental objects, vacuum condensates, which accumulate information about the nonperturbative structure of the QCD vacuum. The emerging QCD sum rule picture of hadronic form factors is characterized by a dominant role of essentially nonperturbative effects in the few GeV region, with perturbative mechanisms starting to show up for momentum transfers Q{sup 2} closer to 10 GeV{sup 2} and higher. Thus, increasing CEBAF energy provides a unique opportunity for a precision study of interplay between the perturbative and nonperturbative phenomena in the QCD description of elastic processes.

  5. Shielding design of a treatment room for an accelerator-based epithermal neutron irradiation facility for BNCT.

    PubMed

    Evans, J F; Blue, T E

    1996-11-01

    Protecting the facility personnel and the general public from radiation exposure is a primary safety concern of an accelerator-based epithermal neutron irradiation facility. This work makes an attempt at answering the questions "How much?" and "What kind?" of shielding will meet the occupational limits of such a facility. Shielding effectiveness is compared for ordinary and barytes concretes in combination with and without borated polyethylene. A calculational model was developed of a treatment room , patient "scatterer," and the epithermal neutron beam. The Monte Carlo code, MCNP, was used to compute the total effective dose equivalent rates at specific points of interest outside of the treatment room. A conservative occupational effective dose rate limit of 0.01 mSv h-1 was the guideline for this study. Conservative Monte Carlo calculations show that constructing the treatment room walls with 1.5 m of ordinary concrete, 1.2 m of barytes concrete, 1.0 m of ordinary concrete preceded by 10 cm of 5% boron-polyethylene, or 0.8 m of barytes concrete preceded by 10 cm of 5% boron-polyethylene will adequately protect facility personnel. PMID:8887513

  6. Shielding design of a treatment room for an accelerator-based epithermal neutron irradiation facility for BNCT

    SciTech Connect

    Evans, J.F.; Blue, T.E.

    1996-11-01

    Protecting the facility personnel and the general public from radiation exposure is a primary safety concern of an accelerator-based epithermal neutron irradiation facility. This work makes an attempt at answering the questions {open_quotes}How much?{close_quotes} and {open_quotes}What kind?{close_quotes} of shielding will meet the occupational limits of such a facility. Shielding effectiveness is compared for ordinary and barytes concretes in combination with and without borated polyethylene. A calculational model was developed of a treatment room, patient {open_quotes}scatterer,{close_quotes} and the epithermal neutron beam. The Monte Carlo code, MCNP, was used to compute the total effective dose equivalent rates at specific points of interest outside of the treatment room. A conservative occupational effective dose rate limit of 0.01 mSv h{sup {minus}1} was the guideline for this study. Conservative Monte Carlo calculations show that constructing the treatment room walls with 1.5 m of ordinary concrete, 1.2 m of barytes concrete, 1.0 m of ordinary concrete preceded by 10 cm of 5% boron-polyethylene, or 0.8 m of barytes concrete preceded by 10 cm of 5% boron-polyethylene will adequately protect facility personnel. 20 refs., 8 figs., 2 tabs.

  7. Monte Carlo simulations for the shielding of the future high-intensity accelerator facility FAIR at GSI.

    PubMed

    Radon, T; Gutermuth, F; Fehrenbacher, G

    2005-01-01

    The Gesellschaft für Schwerionenforschung (GSI) is planning a significant expansion of its accelerator facilities. Compared to the present GSI facility, a factor of 100 in primary beam intensities and up to a factor of 10,000 in secondary radioactive beam intensities are key technical goals of the proposal. The second branch of the so-called Facility for Antiproton and Ion Research (FAIR) is the production of antiprotons and their storage in rings and traps. The facility will provide beam energies a factor of approximately 15 higher than presently available at the GSI for all ions, from protons to uranium. The shielding design of the synchrotron SIS 100/300 is shown exemplarily by using Monte Carlo calculations with the FLUKA code. The experimental area serving the investigation of compressed baryonic matter is analysed in the same way. In addition, a dose comparison is made for an experimental area operated with medium energy heavy-ion beams. Here, Monte Carlo calculations are performed by using either heavy-ion primary particles or proton beams with intensities scaled by the mass number of the corresponding heavy-ion beam. PMID:16381714

  8. Risk-Based Decision Process for Accelerated Closure of a Nuclear Weapons Facility

    SciTech Connect

    Butler, L.; Norland, R. L.; DiSalvo, R.; Anderson, M.

    2003-02-25

    Nearly 40 years of nuclear weapons production at the Rocky Flats Environmental Technology Site (RFETS or Site) resulted in contamination of soil and underground systems and structures with hazardous substances, including plutonium, uranium and hazardous waste constituents. The Site was placed on the National Priority List in 1989. There are more than 370 Individual Hazardous Substance Sites (IHSSs) at RFETS. Accelerated cleanup and closure of RFETS is being achieved through implementation and refinement of a regulatory framework that fosters programmatic and technical innovations: (1) extensive use of ''accelerated actions'' to remediate IHSSs, (2) development of a risk-based screening process that triggers and helps define the scope of accelerated actions consistent with the final remedial action objectives for the Site, (3) use of field instrumentation for real time data collection, (4) a data management system that renders near real time field data assessment, and (5) a regulatory agency consultative process to facilitate timely decisions. This paper presents the process and interim results for these aspects of the accelerated closure program applied to Environmental Restoration activities at the Site.

  9. Data acquisition, control, and analysis for the Argonne Advanced Accelerator Test Facility (AATF)

    SciTech Connect

    Schoessow, P.

    1989-01-01

    The AATF has been used to study wakefield acceleration and focusing in plasmas and rf structures. A PC-based system is described which incorporates the functions of beamline control and acquisition, storage, and preliminary analysis of video images from luminescent screen beam diagnostics. General features of the offline analysis of wakefield data are also discussed. 4 refs., 3 figs.

  10. 10-GW CO{sub 2} laser system at the Brookhaven Accelerator Test Facility

    SciTech Connect

    Pogorelsky, I.; Fischer, J.; Fisher, A.S.

    1993-12-31

    Design and performance of a high peak-power CO{sub 2} laser system to produce subnanosecond IR pulses for electron acceleration experiment are presented. We discuss theoretical aspects of the picosecond laser pulse propagation in a molecular amplifier and a design approach towards compact Terawatt CO{sub 2} laser systems.

  11. CEBAF 200 kV Inverted Electron Gun

    SciTech Connect

    Grames, J M; Clark, J; Hansknecht, J; Poelker, M; Stutzman, M L; Suleiman, R; Surles-Law, K.E.L.; BastaniNejad, M; McCarter, J J

    2011-03-01

    Two DC high volt­age GaAs pho­to­guns have been built at Jef­fer­son Lab based on a com­pact in­vert­ed in­su­la­tor de­sign. One pho­to­gun pro­vides the po­lar­ized elec­tron beam at CEBAF and op­er­ates at 130 kV bias volt­age. The other gun is used for high av­er­age cur­rent life­time stud­ies at a ded­i­cat­ed test fa­cil­i­ty and has been op­er­at­ed at bias volt­age up to 225 kV. The ad­van­tages of high­er DC volt­age for CEBAF in­clude re­duced space-charge emit­tance growth and the po­ten­tial for pro­longed pho­to­cath­ode life­time. How­ev­er, a con­se­quence of op­er­at­ing at high­er volt­ages is the in­creased like­li­hood of field emis­sion or break­down, both of which are un­ac­cept­able. High­lights of the R&D stud­ies lead­ing to­ward a pro­duc­tion 200keV GaAs pho­to­gun for CEBAF will be pre­sent­ed.

  12. Proceedings of the Advanced Hadron Facility accelerator design workshop, February 20--25, 1989

    SciTech Connect

    Thiessen, H.A.

    1990-04-01

    The International Workshop on Hadron Facility Technology was held February 20--25, 1989, at the Study Center at Los Alamos National Laboratory. This volume (second of two) included papers on computer controls, polarized beam, rf, magnet and power supplies, experimental areas, and instabilities. Participants included groups from AHF, Brookhaven National Laboratory, European Hadron Facility, Fermilab, and the Moscow Meson Factory. The workshop was well attended by members of the Los Alamos staff. The interchange of information and the opportunity by criticism by peers was important to all who attended.

  13. LLNL/UC (Lawrence Livermore National Laboratory)/(University of California) AMS (accelerator mass spectrometry) facility and research program

    SciTech Connect

    Davis, J.C.; Proctor, I.D.; Southon, J.R.; Caffee, M.W.; Heikkinen, D.W.; Roberts, M.L.; Moore, T.L.; Turteltaub, K.W.; Nelson, D.E.; Loyd, D.H.; Vogel, J.S.

    1990-04-18

    The Lawrence Livermore National Laboratory (LLNL) and the University of California (UC) now have in operation a large AMS spectrometer built as part of a new multiuser laboratory centered on an FN tandem. AMS measurements are expected to use half of the beam time of the accelerator. LLNL use of AMS is in research on consequences of energy usage. Examples include global warming, geophysical site characterization, radiation biology and dosimetry, and study of mutagenic and carcinogenic processes. UC research activities are in clinical applications, archaeology and anthropology, oceanography, and geophysical and geochemical research. Access is also possible for researchers outside the UC system. The technological focus of the laboratory is on achieving high rates of sample through-put, unattended operation, and advances in sample preparation methods. Because of the expected growth in the research programs and the other obligations of the present accelerator, we are designing a follow-on dedicated facility for only AMS and microprobe analysis that will contain at least two accelerators with multiple spectrometers. 10 refs., 1 fig.

  14. Accelerated Clean-up of the United States Department of Energy, Mound Nuclear Weapons Facility in Miamisburg, Ohio

    SciTech Connect

    Lehew, J.G.; Bradford, J.D.; Cabbil, C.C.

    2006-07-01

    CH2M HILL is executing a performance-based contract with the United States Department of Energy to accelerate the safe closure of the nuclear facilities at the former Mound plant in Miamisburg, Ohio. The contract started in January 2003 with a target completion date of March 31, 2006. Our accelerated baseline targets completion of the project 2 years ahead of the previous baseline schedule, by spring 2006, and for $200 million less than previous estimates. This unique decommissioning and remediation project is located within the City of Miamisburg proper and is designed for transfer of the property to the Miamisburg Mound Community Improvement Corporation for industrial reuse. The project is being performed with the Miamisburg Mound Community Improvement Corporation and their tenants co-located on the site creating significant logistical, safety and stakeholder challenges. The project is also being performed in conjunction with the United States Department of Energy, United States Environmental Protection Agency, and the Ohio Environmental Protection Agency under the Mound 2000 regulatory cleanup process. The project is currently over 95% complete. To achieve cleanup and closure of the Mound site, CH2M HILL's scope includes: - Demolition of 64 nuclear, radiological and commercial facilities - Preparation for Transfer of 9 facilities (including a Category 2 nuclear facility) to the Miamisburg Mound Community Improvement Corporation for industrial reuse - Removal of all above ground utility structures and components, and preparation for transfer of 9 utility systems to Miamisburg Mound Community Improvement Corporation - Investigation, remediation, closure, and documentation of all known Potential Release Sites contaminated with radiological and chemical contamination (73 identified in original contract) - Storage, characterization, processing, packaging and shipment of all waste and excess nuclear materials - Preparation for Transfer of the 306 acre site to the

  15. Neutron Induced Reactions with the 17 Mev Facility at the Athens Tandem Accelerator NCSR 'Demokritos'

    NASA Astrophysics Data System (ADS)

    Vlastou, R.; Kalamara, A.; Serris, M.; Diakaki, M.; Kokkoris, M.; Paneta, V.; Axiotis, M.; Lagoyannis, A.

    In the 5.5 MV tandem T11/25 Accelerator Laboratory of NCSR "Demokritos" monoenergetic neutron beams have been produced in the energy range∼ 15-20 MeV using anew Ti-tritiated target of 373 GBq activity, by means of the 3H(d,n)4He reaction. The corresponding deuteron beam energies obtained from the accelerator, were in the 1.5-4.5MeV range.The maximum flux has been determined to be of the order of 106 n/cm2 s, implementing reference reactions. The 17.1MeV neutron beam has been used for the measurement of 197Au(n,2n) reaction cross section. Theoretical calculations have been performed via the statistical model code EMPIRE and compared to the experimental data of the present work and data from literature.

  16. Status report on the development of a high-power UV/IR FEL at CEBAF

    SciTech Connect

    Benson, S.; Bohn, C.; Dylla, H.F.

    1995-12-31

    Last year we presented a design for a kilowatt industrial UV FEL based on a superconducting RF accelerator delivering 5 mA of electron-beam current at 200 MeV with energy recovery to enhance efficiency. Since then, we have progressed toward resolving several issues associated with that design. More exact simulations of the injector have resulted in a more accurate estimate of the injector performance. A new injection method has reduced the longitudinal and transverse emittance at the linac entrance. A more compact lattice has been designed for the UV FEL, and a new recirculation scheme has been identified which greatly increases the threshold for longitudinal instabilities. We decided to use a wiggler from the Advanced Photon Source which leads to a robust high-gain FEL. Analysis of the stability of an RF control system based on CEBAF control modules indicates that only minor modifications will be needed to apply them to this FEL. Detailed magnet specifications, vacuum-chamber beam apertures, and diagnostic specifications have been developed for the recirculation arcs. The design of the optical cavity has been conceptualized, and control systems have been devised to regulate mirror distortion. A half-scale model of one of the end-corner cubes has been built and tested. Finally, three-dimensional simulations have been carried out which indicate that the FEL should exceed its minimum design goals with adequate performance margin.

  17. High Accuracy Beam Current Monitor System for CEBAF'S Experimental Hall A

    SciTech Connect

    J. Denard; A. Saha; G. Lavessiere

    2001-07-01

    CEBAF accelerator delivers continuous wave (CW) electron beams to three experimental Halls. In Hall A, all experiments require continuous, non-invasive current measurements and a few experiments require an absolute accuracy of 0.2 % in the current range from 1 to 180 {micro}A. A Parametric Current Transformer (PCT), manufactured by Bergoz, has an accurate and stable sensitivity of 4 {micro}A/V but its offset drifts at the muA level over time preclude its direct use for continuous measurements. Two cavity monitors are calibrated against the PCT with at least 50 {micro}A of beam current. The calibration procedure suppresses the error due to PCT's offset drifts by turning the beam on and off, which is invasive to the experiment. One of the goals of the system is to minimize the calibration time without compromising the measurement's accuracy. The linearity of the cavity monitors is a critical parameter for transferring the accurate calibration done at high currents over the whole dynamic range. The method for measuring accurately the linearity is described.

  18. A dedicated AMS (accelerator mass spectrometry) facility for sup 3 H and sup 14 C

    SciTech Connect

    Roberts, M.L.; Southon, J.R.; Davis, J.C.; Proctor, I.D.; Nelson, D.E.

    1990-09-01

    Accelerator mass spectrometry is a high sensitivity technique for the detection of numerous long-lived radionuclides at extremely low concentrations. The present use of this measurement tool is primarily in archaeology and the geosciences. However, novel applications and technological advancements that can have a significant impact on both biomedical research and clinical procedures and environmental investigations have been identified. We are studying a small spectrometer for the simultaneous injection and detection of both hydrogen and carbon radioisotopes. 8 refs., 3 figs.

  19. Neutronics analysis of three beam-filter assemblies for an accelerator-based BNCT facility

    SciTech Connect

    Bleuel, D.L.; Costes, S.V.; Donahue, R.J.; Ludewigt, B.A.

    1997-08-01

    Three moderator materials, AlF{sub 3}/Al, D{sub 2}O and LiF, have been analyzed for clinical usefulness using the reaction {sup 7}Li(p,n) as an accelerator driven neutron source. Proton energies between 2.1 MeV and 2.6 MeV have been investigated. Radiation transport in the reflector/moderator assembly is simulated using the MCNP program. Depth-dose distributions in a head phanton are calculated with the BNCT-RTPE patient treatment planning program from INEEL using the MCNP generated neutron and photon spectra as the subsequent source. Clinical efficacy is compared using the current BMRR protocol for all designs. Depth-dose distributions are compared for a fixed normal tissue tolerance dose of 12.5 Gy-Eq. Radiation analyses also include a complete anthropomorphic phantom. Results of organ and whole body dose components are presented for several designs. Results indicate that high quality accelerator beams may produce clinically favorable treatments to deep-seated tumors when compared to the BMRR beam. Also discussed are problems identified in comparing accelerator and reactor based designs using in-air figures of merit as well as some results of spectrum-averaged RBE`s.

  20. 78 FR 73144 - Acceleration of Broadband Deployment by Improving Wireless Facilities Siting Policies

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-12-05

    ...In this document, the Commission seeks comment on potential measures to expedite the environmental and historic preservation review of new wireless facilities and on rules to implement statutory provisions governing State and local review of wireless siting proposals. By this action, the Commission seeks to promote the deployment of infrastructure that is necessary to provide the public with......

  1. Feasibility and conceptual design of a C.W. positron source at CEBAF

    SciTech Connect

    Golge, Serkan

    2010-08-01

    A feasibility study of a CW positron source for the 12 GeV upgrade at Jefferson Lab (JLAB) is provided. The proposed ≥ 100 nA Continuous Wave (CW) positron source at JLAB has several unique and challenging characteristics: high current incident electron beam at 126 MeV with a high beam power (up to a MW); CW e- beam and CW e+ production. The multiple scattering is a dominant process when creating e+ in a target, which results a large phase space area of the emitted positrons. An admittance study was done at CEBAF to find the maximum phase space area, which is tolerated in the machine. The measured geometrical transverse admittance (A) were Ax =10 and Ay = 5 mm∙mrad at the injector. Energy spread measurement was also done at the ARC1. The fractional spread limit in the ARC1 was measured as δ = 3×10-3 at 653 MeV. By using the optimized results and the CEBAF parameters, three positron injector configurations are proposed; Combined Function Magnet, Two-Dipole and Microtron Dipole configurations. With the assumptions made, by using 126 MeV Ⓧ10 mA e- beam impinging on a 2 mm W target with a 100 μm spot size, we can get up to 3 μA useful e+ current at the North Linac connection. One of the biggest challenges is the target design, which the deposited power is about 60 kW. ILC designs project power deposition up to 13 kW, which would allow the creation of a e+ beam of up to 650 nA otherwise. The results of analytic and monte carlo simulations of the positron production, capture and acceleration are presented. For the target design, a review is presented of solutions for the high power production target. Portions of this dissertation work have been published in two conference proceedings.

  2. {sup 3}He target for Hall C at CEBAF

    SciTech Connect

    Zeidman, B.; Zeuli, A.

    1995-08-01

    A major fraction of the physics program for Hall C involves scattering from cryogenic targets of the lightest nuclei, i.e. H, D, and {sup 3,4}He. Argonne is constructing the He target that will consist of a 4cm cylinder, operating at a pressure of 10 atmospheres and a temperature of {approximately}5.2 degrees Kelvin. CEBAF is currently constructing a cryo-target system for liquid H and D cells and the cooled, pressurized helium targets. The He target system includes cell loop, the He supply systems, and the additional equipment needed to ensure minimum loss of {sup 3}He in the event of target rupture. Some of the major components have been completed, while the balance of the system will be ready for installation this fiscal year.

  3. Upgrade to Cryomodule Test Facility at Jefferson Lab

    SciTech Connect

    Thomas Powers; Trent Allison; G. Davis; Michael Drury; Christiana Grenoble; Lawrence King; Tomasz Plawski; Joseph Preble

    2003-09-01

    The cryomodule test facility (CMTF) was originally implemented in the late eighties for testing of a small fraction of the cryomodules during the production run for the Continuous Electron Beam Accelerator Facility [1]. The original system was built using a dedicated wiring scheme and a pair of 2 kW, 1497 MHz RF sources. This dedicated system made it difficult to test cryomodules and other RF structures of non-standard configuration. Additionally, due to a previously installed cyclotron, there were static magnetic fields in excess of 6 Gauss within the test cave, which limited the capability of the facility when measuring the quality factor of superconducting cavities. Testing of the Spallation Neutron Source cryomodules as well as future upgrades to the CEBAF accelerator necessitated that the facility be reconfigured to be flexible both with respect to RF source power and cryomodule wiring configuration. This paper will describe the implementation of a generalized wiring scheme t hat is easily adapted to different cryomodule configurations. It will also describe the capabilities of the LabView based low level RF controls and the related data acquisition systems currently being used to test cryomodules and related hardware. The high power RF source capabilities will be described. The magnetic shielding put in place in order to reduce the ambient magnetic file to levels below 50 mGauss will also be described.

  4. Development of an Electromagnetic Acceleration Facility for Impact and Fracture Studies at High Strain Rates

    NASA Astrophysics Data System (ADS)

    Pahari, S.; Suryaprasad, I. V. V.; Shiv, N.; Madhavan, S.; Sijoy, C. D.; Chaturvedi, S.

    2011-07-01

    Experimental studies of strain time history and fracture & penetration resulting from the high velocity impact of solid projectiles on solid targets have been initiated. Design, fabrication, testing and commissioning of an electromagnetic impact facility driven by a capacitor bank have been carried out in this regard. The facility presently has an induction coil gun driving a cylindrical hollow/solid projectile on to a target. 3-7 kJ capacitor banks have been used to drive the launchers. The parameters of the coil gun are in consonance with a computer code developed in-house for the validation and optimization of the coil dimension and bank parameters. Systematic studies have been carried out for validation of code and understanding and benchmarking coil performance. Reproducible velocities of the order of 100 m/s have been successfully achieved with projectiles of masses 20 gm. Preliminary impact studies carried out on Alumnium target plates have given the strain time history.

  5. Optimization of parameters for the inline-injection system at Brookhaven Accelerator Test Facility

    SciTech Connect

    Parsa, Z.; Ko, S.K.

    1995-10-01

    We present some of our parameter optimization results utilizing code PARMLEA, for the ATF Inline-Injection System. The new solenoid-Gun-Solenoid -- Drift-Linac Scheme would improve the beam quality needed for FEL and other experiments at ATF as compared to the beam quality of the original design injection system. To optimize the gain in the beam quality we have considered various parameters including the accelerating field gradient on the photoathode, the Solenoid field strengths, separation between the gun and entrance to the linac as well as the (type size) initial charge distributions. The effect of the changes in the parameters on the beam emittance is also given.

  6. Test simulation of neutron damage to electronic components using accelerator facilities

    NASA Astrophysics Data System (ADS)

    King, D. B.; Fleming, R. M.; Bielejec, E. S.; McDonald, J. K.; Vizkelethy, G.

    2015-12-01

    The purpose of this work is to demonstrate equivalent bipolar transistor damage response to neutrons and silicon ions. We report on irradiation tests performed at the White Sands Missile Range Fast Burst Reactor, the Sandia National Laboratories (SNL) Annular Core Research Reactor, the SNL SPHINX accelerator, and the SNL Ion Beam Laboratory using commercial silicon npn bipolar junction transistors (BJTs) and III-V Npn heterojunction bipolar transistors (HBTs). Late time and early time gain metrics as well as defect spectra measurements are reported.

  7. The JLab 12 GeV Energy Upgrade of CEBAF for QCD and Hadronic Physics

    SciTech Connect

    Cardman, Lawrence; Harwood, Leigh

    2007-06-25

    CEBAF at Jefferson Lab is a 5-pass, recirculating cw electron linac operating at ~6 GeV and devoted to basic research in nuclear physics. The 12 GeV Upgrade is a major project, sponsored by the DOE Office of Nuclear Physics, that will expand its research capabilities substantially by doubling the maximum energy and adding major new experimental apparatus. We anticipate that the project will receive Critical Decision 2 approval this year and begin construction in 2008. The research program motivating the Upgrade includes: the study of hybrid mesons, which involve excited states of the glue, to explore the nature of quark confinement; dramatic improvements in our understanding of the QCD structure of the hadrons through the extension of our knowledge of their parton distribution functions to high xBjorken, where they are dominated by underlying valence quark structure, and a program of nucleon “tomography” via measurements of the Generalized Parton Distributions (GPDs), a broad program of experiments in the physics of nuclei that aims to understand the QCD basis for the nucleon-nucleon force and how nucleons and mesons arise as an approximation to the underlying quark-gluon structure; and precision tests of the Standard Model through parity violating deep inelastic and Møller scattering. The Upgrade includes: doubling the accelerating voltages of the linacs by adding 10 new high-performance cryomodules; the requisite expansion of the 2K cryogenics plant and rf power systems to support these cryomodules; upgrading the beam transport system from 6 to 12 GeV through extensive re-use and/or modification of existing hardware; and the addition of one recirculation arc, a new experimental area, and the beamline to it; and the construction of major new experimental equipment for the GPD, high-xBjorken, and hybrid meson programs. The presentation will describe the science briefly and provide some details about the accelerator plans.

  8. Recent developments of the ion sources at Tri University Meson Factory/Isotope Separator and ACcelerator Facility

    SciTech Connect

    Bricault, P. G.; Ames, F.; Dombsky, M.; Labrecque, F.; Lassen, J.; Mjos, A.; Minor, G.; Tigelhoefer, A.

    2012-02-15

    This paper describes the recent progresses concerning the on-line ion source at the Tri University Meson Factory/Isotope Separator and ACcelerator (TRIUMF/ISAC) Radioactive Ion-Beam Facility; description of the new design of the surface-ion-source for improved stability of the beam intensity, description of the transport path to the east target station at ISAC, description of the new brazing techniques that solved recurrent problems with water leaks on the target/ion source assembly in the vacuum system, finally, recent developments concerning the Forced Electron Beam Induced Arc Discharge (FEBIAD) ion source are reported. In particular, a study on the effect of the plasma chamber volume on the ionization efficiency was completed.

  9. Calibration of a new experimental chamber for PIXE analysis at the Accelerator Facilities Division of Atomic Energy Centre Dhaka (AECD)

    NASA Astrophysics Data System (ADS)

    Hassan, Md. Taufique; Shariff, Md. Asad; Hossein, Amzad; Abedin, Md. Joynal; Fazlul Hoque, A. K. M.; Chowdhuri, M. S.

    2015-05-01

    A new experimental chamber has been installed at the 3 MV Van de Graaff Accelerator Facilities Division in the Atomic Energy Centre, Dhaka, to perform different Ion Beam Analysis (IBA) techniques. The calibration of this new setup for Particle Induced X-ray Emission (PIXE) technique has been done using a set of thin MicroMatter standards and GUPIX (PIXE spectrum analysis software), which is explicated in this paper. The effective thicknesses of the beryllium window of the X-ray detector and of the different absorbers used were determined. For standardization, the so called instrumental constant H (product of detector solid angle and the correction factor for the setup) as function of X-ray energy were determined and stored inside the GUPIX library for further PIXE analysis.

  10. Innovative Applications of Genetic Algorithms to Problems in Accelerator Physics

    SciTech Connect

    Hofler, Alicia; Terzic, Balsa; Kramer, Matthew; Zvezdin, Anton; Morozov, Vasiliy; Roblin, Yves; Lin, Fanglei; Jarvis, Colin

    2013-01-01

    The genetic algorithm (GA) is a relatively new technique that implements the principles nature uses in biological evolution in order to optimize a multidimensional nonlinear problem. The GA works especially well for problems with a large number of local extrema, where traditional methods (such as conjugate gradient, steepest descent, and others) fail or, at best, underperform. The field of accelerator physics, among others, abounds with problems which lend themselves to optimization via GAs. In this paper, we report on the successful application of GAs in several problems related to the existing CEBAF facility, the proposed MEIC at Jefferson Lab, and a radio frequency (RF) gun based injector. These encouraging results are a step forward in optimizing accelerator design and provide an impetus for application of GAs to other problems in the field. To that end, we discuss the details of the GAs used, including a newly devised enhancement, which leads to improved convergence to the optimum and make recommendations for future GA developments and accelerator applications.

  11. Generation of fast neutrons through deuteron acceleration at the PALS laser facility

    NASA Astrophysics Data System (ADS)

    Krása, J.; Klír, D.; Velyhan, A.; Řezáč, K.; Cikhardt, J.; Ryć, L.; Krouský, E.; Pfeifer, M.; De Marco, M.; Skála, J.; Dudžák, R.; Ullschmied, J.

    2016-03-01

    Recent experiments at the laser facility PALS focused on the laser driven fusion of deuterons are reviewed. They benefit of high reaction cross-sections and of a high number of multi-MeV deuterons from thick CD2 targets irradiated by intensity of 3× 1016 W cm-2. In the reported experiments fast fusion neutrons with energy up to 16 MeV were produced through 7Li(d, n)8Be and 11B(d, n)12C reactions in a pitcher-catcher target configuration. When using a large area CD2 foil as a secondary catcher target the total maximum neutron yield from the 2H(d, n)3He reaction increased by a factor of about 5, from 4× 108 to 2× 109. This result reveals that most of the deuterons having enough kinetic energy to enter a fusion reaction are emitted from the primary target into vacuum.

  12. Handling Radioactive Waste from the Proton Accelerator Facility at the Paul Scherrer Institut (PSI) - Always Surprising? - 13320

    SciTech Connect

    Mueth, Joachim

    2013-07-01

    The Paul Scherrer Institut (PSI) is the largest national research centre in Switzerland. Its multidisciplinary research is dedicated to a wide field in natural science and technology as well as particle physics. In this context, PSI is operating, amongst others, a large proton accelerator facility since more than 30 years. In two cyclotrons, protons are accelerated to high speeds and then guided along roughly 100 m of beam line to three different target stations to produce secondary particles like mesons and neutrons for experiments and a separately beam line for UCN. The protons induce spallation processes in the target materials, and also at other beam loss points along the way, with emission of protons, neutrons, hydrogen, tritium, helium, heavier fragments and fission processes. In particular the produced neutrons, due to their large penetration depth, will then interact also with the surrounding materials. These interactions of radiation with matter lead to activation and partly to contamination of machine components and the surrounding infrastructures. Maintenance, operation and decommissioning of installations generate inevitably substantial amounts of radioactive operational and dismantling waste like targets, magnets, collimators, shielding (concrete, steel) and of course secondary waste. To achieve an optimal waste management strategy for interim storage or final disposal, radioactive waste has to be characterized, sorted and treated. This strategy is based on radiation protection demands, raw waste properties (size, material, etc.), and requirements to reduce the volume of waste, mainly for legal and economical reasons. In addition, the radiological limitations for transportation of the waste packages to a future disposal site have to be taken into account, as well as special regulatory demands. The characterization is a task of the waste producer. The conditioning processes and quality checks for radioactive waste packages are part of an accredited

  13. Burnup calculations for KIPT accelerator driven subcritical facility using Monte Carlo computer codes-MCB and MCNPX.

    SciTech Connect

    Gohar, Y.; Zhong, Z.; Talamo, A.; Nuclear Engineering Division

    2009-06-09

    Argonne National Laboratory (ANL) of USA and Kharkov Institute of Physics and Technology (KIPT) of Ukraine have been collaborating on the conceptual design development of an electron accelerator driven subcritical (ADS) facility, using the KIPT electron accelerator. The neutron source of the subcritical assembly is generated from the interaction of 100 KW electron beam with a natural uranium target. The electron beam has a uniform spatial distribution and electron energy in the range of 100 to 200 MeV. The main functions of the subcritical assembly are the production of medical isotopes and the support of the Ukraine nuclear power industry. Neutron physics experiments and material structure analyses are planned using this facility. With the 100 KW electron beam power, the total thermal power of the facility is {approx}375 kW including the fission power of {approx}260 kW. The burnup of the fissile materials and the buildup of fission products reduce continuously the reactivity during the operation, which reduces the neutron flux level and consequently the facility performance. To preserve the neutron flux level during the operation, fuel assemblies should be added after long operating periods to compensate for the lost reactivity. This process requires accurate prediction of the fuel burnup, the decay behavior of the fission produces, and the introduced reactivity from adding fresh fuel assemblies. The recent developments of the Monte Carlo computer codes, the high speed capability of the computer processors, and the parallel computation techniques made it possible to perform three-dimensional detailed burnup simulations. A full detailed three-dimensional geometrical model is used for the burnup simulations with continuous energy nuclear data libraries for the transport calculations and 63-multigroup or one group cross sections libraries for the depletion calculations. Monte Carlo Computer code MCNPX and MCB are utilized for this study. MCNPX transports the

  14. Using Polarimetry to Determine the CEBAF Beam Energy

    SciTech Connect

    Higinbotham, Douglas W.

    2014-06-01

    As Jefferson Lab begins operations with its upgraded CEBAF a ccelerator, the lab once again needs to experimentally determine the absolute beam energy of the machine. Previously, the CE- BAF beam energy was determined using precision measurement s of the bending magnet integral fields along with beam position information. The result obta ined from this technique was cross- checked with elastic scattering from hydrogen where knowle dge of the scattering angles of the electron and proton allow the beam energy to be determined. Wh ile the field integral method will still work with the upgraded machine, the elastic cross sect ion becomes too small to make preci- sion measurements at angles that are large enough to be easil y accessible; thus a new technique for energy determination has been sought. It will be shown th at by making use of polarimetry, one can use CEBAF’s polarized electrons’ g-2 spin precessio n to determine the absolute beam energy. This can be done in a single hall if the parameters of t he machine, such as the injector energy and linac imbalance, are known or with two halls witho ut any knowledge of the machine parameters

  15. Waveguide Stub Tuner Analysis for CEBAF Machine Application

    SciTech Connect

    Haipeng Wang; Michael Tiefenback

    2004-08-01

    Three-stub WR650 waveguide tuners have been used on the CEBAF superconducting cavities for two changes of the external quality factors (Qext): increasing the Qext from 3.4-7.6 x 10{sup 6} to 8 x 10{sup 6}6 on 5-cell cavities to reduce klystron power at operating gradients and decreasing the Qext from 1.7-2.4 x 10{sup 7} to 8 x 10{sup 6} on 7-cell cavities to simplify control of Lorenz Force detuning. To understand the reactive tuning effects in the machine operations with beam current and mechanical tuning, a network analysis model was developed. The S parameters of the stub tuner were simulated by MAFIA and measured on the bench. We used this stub tuner model to study tuning range, sensitivity, and frequency pulling, as well as cold waveguide (WG) and window heating problems. Detailed experimental results are compared against this model. Pros and cons of this stub tuner application are summarized.

  16. RF System Modeling for the CEBAF Energy Upgrade

    SciTech Connect

    Tomasz Plawski, J. Hovater

    2009-05-01

    An RF system model, based on MATLAB/SIMULINK, has been developed for analyzing the basic characteristics of the low level RF (LLRF) control system being designed for the CEBAF 12 GeV Energy Upgrade. In our model, a typical passband cavity representation is simplified to in-phase and quadrature (I&Q) components. Lorentz Force and microphonic detuning are incorporated as a new quadrature carrier frequency (frequency modulation). Beam is also represented as in-phase and quadrature components and superpositioned with the cavity field vector. Signals pass through two low pass filters, where the cutoff frequency is equal to half of the cavity bandwidth, then they are demodulated using the same detuning frequency. Because only baseband I&Q signals are calculated, the simulation process is very fast when compared to other controller-cavity models. During the design process we successfully analyzed gain requirements vs. field stability for different superconducting cavity microphonic backgrounds and Lorentz Force coefficients. Moreover, we were able to evaluate different types of a LLRF system’s control algorithm: GDR (Generator Driven Resonator) and SEL (Self Excited Loop) [1] as well as klystron power requirements for different cavities and beam loads.

  17. PULSED-FOCUSING RECIRCULATING LINACS FOR MUON ACCELERATION

    SciTech Connect

    Johnson, Rolland PAUL

    2014-12-31

    Since the muon has a short lifetime, fast acceleration is essential for high-energy applications such as muon colliders, Higgs factories, or neutrino factories. The best one can do is to make a linear accelerator with the highest possible accelerating gradient to make the accelerating time as short as possible. However, the cost of such a single linear accelerator is prohibitively large due to expensive power sources, cavities, tunnels, and related infrastructure. As was demonstrated in the Thomas Jefferson Accelerator Facility (Jefferson Lab) Continuous Electron Beam Accelerator Facility (CEBAF), an elegant solution to reduce cost is to use magnetic return arcs to recirculate the beam through the accelerating RF cavities many times, where they gain energy on each pass. In such a Recirculating Linear Accelerator (RLA), the magnetic focusing strength diminishes as the beam energy increases in a conventional linac that has constant strength quadrupoles. After some number of passes the focusing strength is insufficient to keep the beam from going unstable and being lost. In this project, the use of fast pulsed quadrupoles in the linac sections was considered for stronger focusing as a function of time to allow more successive passes of a muon beam in a recirculating linear accelerator. In one simulation, it was shown that the number of passes could be increased from 8 to 12 using pulsed magnet designs that have been developed and tested. This could reduce the cost of linac sections of a muon RLA by 8/12, where more improvement is still possible. The expense of a greater number of passes and corresponding number of return arcs was also addressed in this project by exploring the use of ramped or FFAG-style magnets in the return arcs. A better solution, invented in this project, is to use combined-function dipole-quadrupole magnets to simultaneously transport two beams of different energies through one magnet string to reduce costs of return arcs by almost a factor of

  18. Safety training and safe operating procedures written for PBFA (Particle Beam Fusion Accelerator) II and applicable to other pulsed power facilities

    SciTech Connect

    Donovan, G.L.; Goldstein, S.A.

    1986-12-01

    To ensure that work in advancing pulsed power technology is performed with an acceptably low risk, pulsed power research facilities at Sandia National Laboratories must satisfy general safety guidelines established by the Department of Energy, policies and formats of the Environment, Safety, and Health (ES and H) Department, and detailed procedures formulated by the Pulsed Power Sciences Directorate. The approach to safety training and to writing safe operating procedures, and the procedures presented here are specific to the Particle Beam Fusion Accelerator II (PBFA II) Facility but are applicable as guidelines to other research and development facilities which have similar hazards.

  19. The Forward Tagger facility for low Q{sup 2} experiments at Jefferson Laboratory

    SciTech Connect

    Celentano, Andrea

    2014-06-01

    Low Q{sup 2} electron scattering is an efficient and competitive experimental technique to provide intense, quasi-real photon beams, with a high degree of linear polarization. Such a technique will be employed in Hall B at Jefferson Laboratory by having the primary 11 GeV electron beam from the CEBAF accelerator impinging on a liquid hydrogen target. Low-angle scattered electrons will be detected with the new Forward Tagger facility, while the final state hadrons will be measured with the CLAS12 spectrometer. The unique combination of the two detectors will permit to carry out a broad physics program, and to explore new possibilities for high quality physics.

  20. Conceptual MEIC electron ring injection scheme using CEBAF as a full energy injector

    SciTech Connect

    Guo, Jiquan; Lin, Fanglei; Rimmer, Robert A.; Wang, Haipeng; Wang, Shaoheng; Zhang, Yuhong

    2015-09-01

    The Medium-energy Electron-Ion Collider (MEIC) proposed by Jefferson Lab is planning to use the newly upgraded 12 GeV CEBAF 1497 MHz SRF CW recirculating linac as a full-energy injector for the electron collider ring. The electron collider ring is proposed to reuse the 476 MHz PEP-II RF system to achieve high installed voltage and high beam power. The MEIC electron injection requires 3-10 (or 12) GeV beam in 3-4µs long bunch trains with low duty factor and high peak current, resulting in strong transient beam loading for the CEBAF. In this paper, we propose an injection scheme that can match the two systems' frequencies with acceptable injection time, and also address the transient beam loading issue in CEBAF. The scheme is compatible with future upgrade to 952.6 MHz SRF system in the electron ring.

  1. Environmental Assessment for US Department of Energy support of an Iowa State University Linear Accelerator Facility at Ames, Iowa

    SciTech Connect

    Not Available

    1990-05-01

    The proposed Department of Energy (DOE) action is financial and technical support of construction and initial operation of an agricultural commodity irradiator (principally for meat), employing a dual mode electron beam generator capable of producing x-rays, at the Iowa State University Linear Accelerator located at Ames, Iowa. The planned pilot commercial-scale facility would be used for the following activities: conducting irradiation research on agricultural commodities, principally meats; in the future, after the pilot phase, as schedules permit, possibly conducting research on other, non-edible materials; evaluating effects of irradiation on nutritional and sensory quality of agricultural products; demonstrating the efficiency of the process to control or eliminate pathogens, and/or to prolong the commodities' post-harvest shelf-life via control or elimination of bacteria, fungi, and/or insects; providing information to the public on the benefits, safety and risks of irradiated agricultural commodities; determining consumer acceptability of the irradiated products; providing data for use by regulatory agencies in developing protocols for various treatments of Iowa agricultural commodities; and training operators, maintenance and quality control technicians, scientists, engineers, and staff of regulatory agencies in agricultural commodity irradiation technology. 14 refs., 5 figs.

  2. Exclusive processes: Tests of coherent QCD phenomena and nucleon substructure at CEBAF

    SciTech Connect

    Brodsky, S.J.

    1994-07-01

    Measurements of exclusive processes such as electroproduction, photoproduction, and Compton scattering are among the most sensitive probes of proton structure and coherent phenomena in quantum chromodynamics. The continuous electron beam at CEBAF, upgraded in laboratory energy to 10--12 GeV, will allow a systematic study of exclusive, semi-inclusive, and inclusive reactions in a kinematic range well-tuned to the study of fundamental nucleon and nuclear substructure. I also discuss the potential at CEBAF for studying novel QCD phenomena at the charm production threshold, including the possible production of nuclear-bound quarkonium.

  3. The Workshop on Microwave-Absorbing Materials for Accelerators

    SciTech Connect

    Isidoro Campisi

    1993-05-01

    A workshop on the physics and applications of microwave-absorbing materials in accelerators and related systems was held at CEBAF February 22-24, 1993. The gathering brought together about 150 scientists and representatives of industries from all over the world. The main topics of discussion were the properties of ''absorbing'' materials and how the stringent conditions in an accelerator environment restrict the choice of usable material.

  4. Results of the Workshop on Microwave-Absorbing Materials for Accelerators (MAMA): A Personal View

    SciTech Connect

    Campisi, I E

    1993-04-01

    The first workshop on the properties and uses of special materials for absorption of microwaves in particle accelerators was held at the Continuous Electron Beam Accelerator Facility (CEBAF) in Newport News, February 22-24, 1993. The meeting's purpose was to review the advances of ceramic and materials science and to describe the accelerator projects the success of which strongly depends on the existence and availability of microwave-absorbing materials with special characteristics. Scientists from various branches of physics, materials science, microwave engineering, accelerator physics and from national and international laboratories, from universities and industries participated in this gathering. This interdisciplinary meeting brought new people and new ideas together which in the future will bloom into better understanding of general materials and of physical processes and eventually to collaborative efforts to design and produce custom made materials. This paper describes the major topics covered in the workshop and is a personal elaboration of the author on the future possibilities opened by this interaction.

  5. Investigation of the Effects of Facility Background Pressure on the Performance and Voltage-Current Characteristics of the High Voltage Hall Accelerator

    NASA Technical Reports Server (NTRS)

    Kamhawi, Hani; Huang, Wensheng; Haag, Thomas; Spektor, Rostislav

    2014-01-01

    The National Aeronautics and Space Administration (NASA) Science Mission Directorate In-Space Propulsion Technology office is sponsoring NASA Glenn Research Center to develop a 4 kW-class Hall thruster propulsion system for implementation in NASA science missions. A study was conducted to assess the impact of varying the facility background pressure on the High Voltage Hall Accelerator (HiVHAc) thruster performance and voltage-current characteristics. This present study evaluated the HiVHAc thruster performance in the lowest attainable background pressure condition at NASA GRC Vacuum Facility 5 to best simulate space-like conditions. Additional tests were performed at selected thruster operating conditions to investigate and elucidate the underlying physics that change during thruster operation at elevated facility background pressure. Tests were performed at background pressure conditions that are three and ten times higher than the lowest realized background pressure. Results indicated that the thruster discharge specific impulse and efficiency increased with elevated facility background pressure. The voltage-current profiles indicated a narrower stable operating region with increased background pressure. Experimental observations of the thruster operation indicated that increasing the facility background pressure shifted the ionization and acceleration zones upstream towards the thruster's anode. Future tests of the HiVHAc thruster are planned at background pressure conditions that are expected to be two to three times lower than what was achieved during this test campaign. These tests will not only assess the impact of reduced facility background pressure on thruster performance, voltage-current characteristics, and plume properties; but will also attempt to quantify the magnitude of the ionization and acceleration zones upstream shifting as a function of increased background pressure.

  6. W.K.H. Panofsky Prize in Experimental Particle Physics: The design, construction and performance of the B Factory accelerator facilities, PEP-II and KEKB

    NASA Astrophysics Data System (ADS)

    Dorfan, Jonathan

    2016-03-01

    The discovery and elucidation of CP violation in the B-meson system presented daunting challenges for the accelerator and detector facilities. This talk discusses how these challenges were met and overcome in the electron-positron colliding-beam accelerator facilities PEP-II (at SLAC) and KEKB (at KEK). The key challenge was to produce unprecedentedly large numbers of B-mesons in a geometry that provided high-statistics, low-background samples of decays to CP eigenstates. This was realized with asymmetric collisions at the Γ(4S) at peak luminosities in excess of 3 ×1033 /sq. cm/sec. Specialized optics were developed to generate efficient, low background, multi-bunch collisions in an energy-asymmetric collision geometry. Novel technologies for the RF, vacuum and feedback systems permitted the storage of multi-amp, multi-bunch beams of electrons and positrons, thereby generating high peak luminosities. Accelerator uptimes greater than 95 percent, combined with high-intensity injection systems, ensured large integrated luminosity. Both facilities rapidly attained their design specifications and ultimately far exceeded the projected performance expectations for both peak and integrated luminosity.

  7. Investigation of the Effects of Facility Background Pressure on the Performance and Voltage-Current Characteristics of the High Voltage Hall Accelerator

    NASA Technical Reports Server (NTRS)

    Kamhawi, Hani; Huang, Wensheng; Haag, Thomas; Spektor, Rostislav

    2014-01-01

    The National Aeronautics and Space Administration (NASA) Science Mission Directorate In-Space Propulsion Technology office is sponsoring NASA Glenn Research Center to develop a 4 kW-class Hall thruster propulsion system for implementation in NASA science missions. A study was conducted to assess the impact of varying the facility background pressure on the High Voltage Hall Accelerator (HiVHAc) thruster performance and voltage-current characteristics. This present study evaluated the HiVHAc thruster performance in the lowest attainable background pressure condition at NASA GRC Vacuum Facility 5 to best simulate space-like conditions. Additional tests were performed at selected thruster operating conditions to investigate and elucidate the underlying physics that change during thruster operation at elevated facility background pressure. Tests were performed at background pressure conditions that are three and ten times higher than the lowest realized background pressure. Results indicated that the thruster discharge specific impulse and efficiency increased with elevated facility background pressure. The voltage-current profiles indicated a narrower stable operating region with increased background pressure. Experimental observations of the thruster operation indicated that increasing the facility background pressure shifted the ionization and acceleration zones upstream towards the thrusters anode. Future tests of the HiVHAc thruster are planned at background pressure conditions that are expected to be two to three times lower than what was achieved during this test campaign. These tests will not only assess the impact of reduced facility background pressure on thruster performance, voltage-current characteristics, and plume properties; but will also attempt to quantify the magnitude of the ionization.

  8. Betatron radiation based diagnostics for plasma wakefield accelerated electron beams at the SPARC_LAB test facility

    NASA Astrophysics Data System (ADS)

    Shpakov, V.; Anania, M. P.; Biagioni, A.; Chiadroni, E.; Cianchi, A.; Curcio, A.; Dabagov, S.; Ferrario, M.; Filippi, F.; Marocchino, A.; Paroli, B.; Pompili, R.; Rossi, A. R.; Zigler, A.

    2016-09-01

    Recent progress with wake-field acceleration has shown a great potential in providing high gradient acceleration fields, while the quality of the beams remains relatively poor. Precise knowledge of the beam size at the exit from the plasma and matching conditions for the externally injected beams are the key for improvement of beam quality. Betatron radiation emitted by the beam during acceleration in the plasma is a powerful tool for the transverse beam size measurement, being also non-intercepting. In this work we report on the technical solutions chosen at SPARC_LAB for such diagnostics tool, along with expected parameters of betatron radiation.

  9. A 1 GeV Laser Wakefield Accelerator: Experimental Progress at the l'OASIS Facility of LBNL

    NASA Astrophysics Data System (ADS)

    Leemans, W. P.; Geddes, C. G. R.; Toth, C. S.; van Tilborg, J.; Nagler, B.; Michel, P.; Nakamura, K.; Esarey, E.; Schroeder, C. B.; Gonsalves, A.; Spence, D. J.; Hooker, S. M.; Filip, C.; Cowan, T.

    2004-11-01

    Experimental progress towards a 1 GeV laser-driven plasma-based accelerator will be discussed. The design of the 1 GeV accelerator module consists of two components: (1) an all-optical electron injector and (2) a plasma channel for laser guiding and electron acceleration to high energy via the laser wakefield acceleration (LWFA) mechanism. Experimental results on the injector development include the demonstration of laser guiding at relativistic intensities in preformed plasmas and production of quasi-monochromatic electron beams with energy around 100 MeV. Progress on guiding 100 TW laser pulses in capillary-discharge-based plasma channels will be discussed and integration of these channels with the all-optical injector will be reported.

  10. First attempt of at-cavity cryogenic X-ray detection in a CEBAF cryomodule for field emission monitoring

    SciTech Connect

    Geng, Rongli; Daly, Edward; Drury, Michael; Palczewski, Ari

    2015-09-01

    We report on the first result of at-cavity X-ray detection in a CEBAF cryomodule for field emission monitoring. In the 8-cavity cryomodule F100, two silicon diodes were installed near the end flange of each cavity. Each cavity was individually tested during the cryomodule test in JLab’s cryomodule test facility. The behaviors of these at-cavity cryogenic X-ray detectors were compared with those of the standard ‘in air’ Geiger-Muller (G-M) tubes. Our initial experiments establish correlation between X-ray response of near diodes and the field emission source cavity in the 8-cavity string. For two out of these eight cavities, we also carried out at-cavity X-ray detection experiment during their vertical testing. The aim is to track field emission behavior uniquely from vertical cavity testing to horizontal cavity testing in the cryomodule. These preliminary results confirmed our expectation and warrant further effort toward the establishment of permanent at-cavity cryogenic X-ray detection for SRF development and operation.

  11. Analysis of Residual Acceleration Effects on Transport and Segregation During Directional Solidification of Tin-Bismuth in the MEPHISTO Furnace Facility

    NASA Technical Reports Server (NTRS)

    Alexander, J. Iwan D.; Lizee, Arnaud

    1996-01-01

    The object of this work, started in March of 1995, is to approach the problem of determining the transport conditions (and effects of residual acceleration) during the plane-front directional solidification of a tin-bismuth alloy under low gravity conditions. The work involves using a combination of 2- and 3-D numerical models, scaling analyses, 1-D models and the results of ground-based and low-gravity experiments. The experiments conducted in the MEPHISTO furnace facility during the USMP-3 spaceflight which took place earlier this year (22 Feb. - 6 Mar. 1996). This experiment represents an unprecedented opportunity to make a quantitative correlation between residual accelerations and the response of an actual experimental solidification system

  12. Preparation and Testing of the SRF Cavities for the CEBAF 12 GeV Upgrade

    SciTech Connect

    Reilly, A. V.; Bass, T.; Burrill, A.; Davis, G. K.; Marhauser, F.; Reece, C. E.; Stirbet, M.

    2011-07-01

    Eighty new 7-cell, low-loss cell-shaped cavities are required for the CEBAF 12 GeV Upgrade project. In addition to ten pre-production units fabricated at JLab, the full set of commercially-produced cavities have been delivered. An efficient processing routine, which includes a controlled 30 micron electropolish, has been established to transform these cavities into qualified 8-cavity strings. This work began in 2010 and will run through the end of 2011. The realized cavity performance consistently exceeds project requirements and also the maximum useful gradient in CEBAF: 25 MV/m. We will describe the cavity processing and preparation protocols and summarize test results obtained to date.

  13. Optimizing the CEBAF Injector for Beam Operation with a Higher Voltage Electron Gun

    SciTech Connect

    F.E. Hannon, A.S. Hofler, R. Kazimi

    2011-03-01

    Recent developments in the DC gun technology used at CEBAF have allowed an increase in operational voltage from 100kV to 130kV. In the near future this will be extended further to 200kV with the purchase of a new power supply. The injector components and layout at this time have been designed specifically for 100kV operation. It is anticipated that with an increase in gun voltage and optimization of the layout and components for 200kV operation, that the electron bunch length and beam brightness can be improved upon. This paper explores some upgrade possibilities for a 200kV gun CEBAF injector through beam dynamic simulations.

  14. Beam Physics for the 12 GeV CEBAF Upgrade Project

    SciTech Connect

    L. Merminga; J. F. Benesch; S.A. Bogacz; Y.-C. Chao; A. Freyberger; J.M. Grames; L. Harwood; R. Kazimi; G.A. Krafft; M. Spata; M. Tiefenback; M. Wiseman; B.C. Yunn; Y. Zhang

    2005-05-16

    Beam physics aspects of the 12 GeV Upgrade of CEBAF are presented. The CEBAF Upgrade to 12 GeV is achieved via 5.5 recirculations through the linacs, and the installation of 10 new high-gradient cryomodules. A new experimental hall, Hall D, is envisioned at the end of North Linac. Simulation results for straight-through and recirculated injectors are summarized and compared. Beam transport designs are discussed and evaluated with respect to matching and beam breakup (BBU) optimization. Effects of synchrotron radiation excitation on the beam properties are calculated. BBU simulations and derived specifications for the damping of higher order modes of the new 7-cell cavities are presented. The energies that provide longitudinal polarization in multiple experimental halls simultaneously are calculated. Finally, a detailed optics design for the Hall D transport line has been obtained.

  15. Superharp — A wire scanner with absolute position readout for beam energy measurement at CEBAF

    NASA Astrophysics Data System (ADS)

    Yan, C.; Adderley, P.; Barker, D.; Beaufait, J.; Capek, K.; Carlini, R.; Dahlberg, J.; Feldl, E.; Jordan, K.; Kross, B.; Oren, W.; Wojcik, R.; VanDyke, J.

    1995-02-01

    The CEBAF superharp is an upgraded beam wire scanner which provides absolute beam position readout using a shaft encoder. Superharps allow for high precision measurements of the beam's profile and position ( Δx ˜ 10 μm). The Hall C endstation at CEBAF will use three pairs of superharps to perform beam energy measurements with 10 -3 accuracy. The three pairs are installed at the beginning, the mid-point and the end of the Hall C arc beamline. Using superharps in conjunction with a dual sensor system: the direct current pick-up and the bremsstrahlung detectors, beam profile measurements can be obtained over a wide beam current range of 1 ˜ 200 μA.

  16. Low energy highly charged ion beam facility at Inter University Accelerator Centre: Measurement of the plasma potential and ion energy distributions

    SciTech Connect

    Sairam, T. Bhatt, Pragya; Safvan, C. P.; Kumar, Ajit; Kumar, Herendra

    2015-11-15

    A deceleration lens coupled to one of the beam lines of the electron cyclotron resonance based low energy beam facility at Inter University Accelerator Centre is reported. This system is capable of delivering low energy (2.5 eV/q–1 keV/q) highly charged ion beams. The presence of plasma potential hinders the measurements of low energies (<50 eV), therefore, plasma potential measurements have been undertaken using a retarding plate analyzer in unison with the deceleration assembly. The distributions of the ion energies have been obtained and the effect of different source parameters on these distributions is studied.

  17. A photon calorimeter using lead tungstate crystals for the CEBAF HAll A Compton polarimeter

    SciTech Connect

    D. Neyret; T. Pussieux; T. Auger; M. Baylac; E. Burtin; C. Cavata; R. Chipaux; S. Escoffier; N. Falletto; J. Jardillier; S. Kerhoas; D. Lhuillier; F. Marie; C. Veyssiere; J. Ahrens; R. Beck; M. Lang

    2000-05-01

    A new Compton polarimeter is built on the CEBAF Hall A electron beam line. Performances of 10% resolution and 1% calibration are required for the photon calorimeter of this polarimeter. This calorimeter is built with lead tungstate scintillators coming from the CMS electromagnetic calorimeter R&D. Beam tests of this detector have been made using the tagged photon beam line at MAMI, Mainz, and a resolution of 1.76%+2.75%/v+0.41%/E has been measured.

  18. Asynchronous inputs and flip-flop metastability in the CLAS trigger at CEBAF

    SciTech Connect

    Doughty, D.C. Jr.; Lemon, S. ); Bonneau, P. )

    1993-08-01

    The impact of flip-flop metastability on the pipelined trigger for the CLAS detector at CEBAF has been studied. The authors find that the newest ECL flip-flops (ECLinPS) are much faster than older families (10H) at resolving the metastable condition. This will allow their use in systems with asynchronous inputs without an extra stage of synchronizing flip-flops.

  19. Evaluation and Correction of the Non-linear Distortion of CEBAF Beam Position Monitors

    SciTech Connect

    M. Spata, T.L. Allison, K.E. Cole, J. Musson, J. Yan

    2011-09-01

    The beam position monitors at CEBAF have four antenna style pickups that are used to measure the location of the beam. There is a strong nonlinear response when the beam is far from the electrical center of the device. In order to conduct beam experiments at large orbit excitation we need to correct for this nonlinearity. The correction algorithm is presented and compared to measurements from our stretched wire BPM test stand.

  20. Recent US target-physics-related research in heavy-ion inertial fusion: simulations for tamped targets and for disk experiments in accelerator test facilities

    SciTech Connect

    Mark, J.W.K.

    1982-03-22

    Calculations suggest that experiments relating to disk heating, as well as beam deposition, focusing and transport can be performed within the context of current design proposals for accelerator test-facilities. Since the test-facilities have lower ion kinetic energy and beam pulse power as compared to reactor drivers, we achieve high-beam intensities at the focal spot by using short focal distance and properly designed beam optics. In this regard, the low beam emittance of suggested multi-beam designs are very useful. Possibly even higher focal spot brightness could be obtained by plasma lenses which involve external fields on the beam which is stripped to a higher charge state by passing through a plasma cell. Preliminary results suggest that intensities approx. 10/sup 13/ - 10/sup 14/ W/cm/sup 2/ are achievable. Given these intensities, deposition experiments with heating of disks to greater than a million degrees Kelvin (100 eV) are expected.

  1. Design of a hard X-ray beamline and end-station for pump and probe experiments at Pohang Accelerator Laboratory X-ray Free Electron Laser facility

    NASA Astrophysics Data System (ADS)

    Park, Jaeku; Eom, Intae; Kang, Tai-Hee; Rah, Seungyu; Nam, Ki Hyun; Park, Jaehyun; Kim, Sangsoo; Kwon, Soonam; Park, Sang Han; Kim, Kyung Sook; Hyun, Hyojung; Kim, Seung Nam; Lee, Eun Hee; Shin, Hocheol; Kim, Seonghan; Kim, Myong-jin; Shin, Hyun-Joon; Ahn, Docheon; Lim, Jun; Yu, Chung-Jong; Song, Changyong; Kim, Hyunjung; Noh, Do Young; Kang, Heung Sik; Kim, Bongsoo; Kim, Kwang-Woo; Ko, In Soo; Cho, Moo-Hyun; Kim, Sunam

    2016-02-01

    The Pohang Accelerator Laboratory X-ray Free Electron Laser project, a new worldwide-user facility to deliver ultrashort, laser-like x-ray photon pulses, will begin user operation in 2017 after one year of commissioning. Initially, it will provide two beamlines for hard and soft x-rays, respectively, and two experimental end-stations for the hard x-ray beamline will be constructed by the end of 2015. This article introduces one of the two hard x-ray end-stations, which is for hard x-ray pump-probe experiments, and primarily outlines the overall design of this end-station and its critical components. The content of this article will provide useful guidelines for the planning of experiments conducted at the new facility.

  2. Evaluating the Potential of Commercial GIS for Accelerator Configuration Management

    SciTech Connect

    T.L. Larrieu; Y.R. Roblin; K. White; R. Slominski

    2005-10-10

    The Geographic Information System (GIS) is a tool used by industries needing to track information about spatially distributed assets. A water utility, for example, must know not only the precise location of each pipe and pump, but also the respective pressure rating and flow rate of each. In many ways, an accelerator such as CEBAF (Continuous Electron Beam Accelerator Facility) can be viewed as an ''electron utility''. Whereas the water utility uses pipes and pumps, the ''electron utility'' uses magnets and RF cavities. At Jefferson lab we are exploring the possibility of implementing ESRI's ArcGIS as the framework for building an all-encompassing accelerator configuration database that integrates location, configuration, maintenance, and connectivity details of all hardware and software. The possibilities of doing so are intriguing. From the GIS, software such as the model server could always extract the most-up-to-date layout information maintained by the Survey & Alignment for lattice modeling. The Mechanical Engineering department could use ArcGIS tools to generate CAD drawings of machine segments from the same database. Ultimately, the greatest benefit of the GIS implementation could be to liberate operators and engineers from the limitations of the current system-by-system view of machine configuration and allow a more integrated regional approach. The commercial GIS package provides a rich set of tools for database-connectivity, versioning, distributed editing, importing and exporting, and graphical analysis and querying, and therefore obviates the need for much custom development. However, formidable challenges to implementation exist and these challenges are not only technical and manpower issues, but also organizational ones. The GIS approach would crosscut organizational boundaries and require departments, which heretofore have had free reign to manage their own data, to cede some control and agree to a centralized framework.

  3. New challenges for HEP computing: RHIC and CEBAF

    SciTech Connect

    LeVine, M.J. IKFUniversity of Frankfurt, D6000 Frankfurt/Main, )

    1990-08-01

    We will look at two new facilities; one is in construction phase, the other about to begin construction. For each of them, we examine the kinds of physics measurements that motivated their construction, and the implications of these experiments for computing. Emphasis will be on one-line requirements, driven by the data rates produced by these experiments.

  4. An intrinsically safe facility for forefront research and training on nuclear technologies — An example of accelerator: the SPES cyclotron

    NASA Astrophysics Data System (ADS)

    Maggiore, M.; Lombardi, A.; Piazza, L. A. C.; Prete, G.

    2014-04-01

    The SPES project, under construction at INFN, Laboratori Nazionali di Legnaro, is a research facility for nuclear and applied physics, based on a high-current H- cyclotron with two exits. One exit will be devoted to supply an ISOL facility for the production of radioactive beams, the second one can be used as driver for the ADS system. The main characteristics of the cyclotron are described together with the main building designed to operate high-current proton beams according to radioprotection rules.

  5. Recent optimization of the beam-optical characteristics of the 6 MV van de Graaff accelerator for high brightness beams at the iThemba LABS NMP facility

    NASA Astrophysics Data System (ADS)

    Conradie, J. L.; Eisa, M. E. M.; Celliers, P. J.; Delsink, J. L. G.; Fourie, D. T.; de Villiers, J. G.; Maine, P. M.; Springhorn, K. A.; Pineda-Vargas, C. A.

    2005-04-01

    With the aim of improving the reliability and stability of the beams delivered to the nuclear microprobe at iThemba LABS, as well as optimization of the beam characteristics along the van de Graaff accelerator beamlines in general, relevant modifications were implemented since the beginning of 2003. The design and layout of the beamlines were revised. The beam-optical characteristics through the accelerator, from the ion source up to the analysing magnet directly after the accelerator, were calculated and the design optimised, using the computer codes TRANSPORT, IGUN and TOSCA. The ion source characteristics and optimal operating conditions were determined on an ion source test bench. The measured optimal emittance for 90% of the beam intensity was about 50π mm mrad for an extraction voltage of 6 kV. These changes allow operation of the Nuclear Microprobe at proton energies in the range 1 MeV-4 MeV with beam intensities of tenths of a pA at the target surface. The capabilities of the nuclear microprobe facility were evaluated in the improved beamline, with particular emphasis to bio-medical samples.

  6. New empirical formula for neutron dose level at the maze entrance of 15 MV medical accelerator facilities

    SciTech Connect

    Kim, Hong-Suk; Jang, Ki-Won; Park, Youn-Hwan; Kwon, Jeong-Wan; Choi, Ho-Sin; Lee, Jai-Ki; Kim, Jong-Kyung

    2009-05-15

    An easily applicable empirical formula was derived for use in the assessment of the photoneutron dose at the maze entrance of a 15 MV medical accelerator treatment room. The neutron dose equivalent rates around the Varian medical accelerator head calculated with the Monte Carlo code MCNPX were used as the source term in producing the base data. The dose equivalents were validated by measurements with bubble detectors. Irradiation geometry conditions expected to yield higher neutron dose rates in the maze were selected: a 20x20 cm{sup 2} irradiation field, gantry rotation plane parallel to the maze walls, and the photon beams directed to the opposite wall to the maze entrance. The neutron dose equivalents at the maze entrance were computed for 697 arbitrary single-bend maze configurations by extending the Monte Carlo calculations down to the maze entrance. Then, the empirical formula was derived by a multiple regression fit to the neutron dose equivalents at the maze entrance for all the different maze configurations. The goodness of the empirical formula was evaluated by applying it to seven operating medical accelerators of different makes. When the source terms were fixed, the neutron doses estimated from the authors' formula agreed better with the corresponding MCNPX simulations than the results of the Kersey method. In addition, compared with the Wu-McGinley formula, the authors' formula provided better estimates for the mazes with length longer than 8.5 m. There are, however, discrepancies between the measured dose rates and the estimated values from the authors' formula, particularly for the machines other than a Varian model. Further efforts are needed to characterize the neutron field at the maze entrance to reduce the discrepancies. Furthermore, neutron source terms for the machines other than a Varian model should be simulated or measured and incorporated into the formula for accurate extended application to a variety of models.

  7. In-phantom characterisation studies at the Birmingham Accelerator-Generated epIthermal Neutron Source (BAGINS) BNCT facility.

    PubMed

    Culbertson, Christopher N; Green, Stuart; Mason, Anna J; Picton, David; Baugh, Gareth; Hugtenburg, Richard P; Yin, Zaizhe; Scott, Malcolm C; Nelson, John M

    2004-11-01

    A broad experimental campaign to validate the final epithermal neutron beam design for the BNCT facility constructed at the University of Birmingham concluded in November 2003. The final moderator and facility designs are overviewed briefly, followed by a summary of the dosimetric methods and presentation of a small subset of the results from this campaign. The dual ionisation chamber technique was used together with foil activation to quantify the fast neutron, photon, and thermal neutron beam dose components in a large rectangular phantom exposed to the beam with a 12 cm diameter beam delimiter in place. After application of a normalisation factor, dose measurements agree with in-phantom MCNP4C predictions within 10% for the photon dose, within 10% for thermal neutron dose, and within 25% for the proton recoil dose along the main beam axis. PMID:15308136

  8. The wonderful world of electron accelerators

    SciTech Connect

    Leeman, C.W.

    1995-04-01

    Electrons provide clean interactions both for high energy physics (in e{sup +}e{sup {minus}} colliders) and nuclear physics (in fixed-target accelerators). However, even at only moderate energies (>1GeV), electrons challenge the accelerator builder, and so one finds that the needs of electron accelerators have pushed many accelerator concepts and technologies: most obviously the important breakthrough superconducting rf (srf) technology, but also rf generation, cavity design, manipulation of short bunches, special lattices, and vacuum chamber design. One also finds that the nuisance synchrotron radiation, tamed by the accelerator builder`s tricks, has become one of the most important applications of electron beams. Srf was proposed in the early 1960`s and tried with little success at first, was later pushed by large storage rings to some extent (LEP, HERA, Tristan), and has now been implemented on an unprecendented scale as the sole means of acceleration at CEBAF. Completed on cost and schedule, CEBAF is progressing in its commissioning and early operations phase according to plan. It has fostered key advances in srf, 2K cryogenics, and rf control, and has provided a technology basis for other accelerator applications of the future. One of these is TESLA, the TeV-scale linear accelerator project now in preliminary development centered at DESY. Another, for which industrial interest is quite high, is free-electron lasers with output adjustable through specific bands of interest in the infrared and the deep ultraviolet at average powers of 50 to 100kW. A third future possibility is intense proton beams, potentially useful for spallation neutron sources.

  9. SRF Performance of CEBAF After Thermal Cycle to Ambient Temperature

    SciTech Connect

    Robert Rimmer; Jay Benesch; Joseph Preble; Charles Reece

    2005-05-01

    In September 2003, in the wake of Hurricane Isabel, JLab was without power for four days after a tree fell on the main power lines feeding the site. This was long enough to lose insulating vacuum in the cryomodules and cryogenic systems resulting in the whole accelerator warming up and the total loss of the liquid helium inventory. This thermal cycle stressed many of the cryomodule components causing several cavities to become inoperable due to helium to vacuum leaks. At the same time the thermal cycle released years of adsorbed gas from the cold surfaces. Over the next days and weeks this gas was pumped away, the insulating vacuum was restored and the machine was cooled back down and re-commissioned. In a testament to the robustness of SRF technology, only a small loss in energy capability was apparent, although individual cavities had quite different field-emission characteristics compared to before the event. In Summer 2004 a section of the machine was again cycled to room temperature during the long maintenance shutdown. We report on the overall SRF performance of the machine after these major disturbances and on efforts to characterize and optimize the new behavior for high-energy running.

  10. The problems associated with the monitoring of complex workplace radiation fields at European high-energy accelerators and thermonuclear fusion facilities.

    PubMed

    Bilski, P; Blomgren, J; d'Errico, F; Esposito, A; Fehrenbacher, G; Fernàndez, F; Fuchs, A; Golnik, N; Lacoste, V; Leuschner, A; Sandri, S; Silari, M; Spurny, F; Wiegel, B; Wright, P

    2007-01-01

    The European Commission is funding within its Sixth Framework Programme a three-year project (2005-2007) called CONRAD, COordinated Network for RAdiation Dosimetry. The organisational framework for this project is provided by the European Radiation Dosimetry Group EURADOS. One task within the CONRAD project, Work Package 6 (WP6), was to provide a report outlining research needs and research activities within Europe to develop new and improved methods and techniques for the characterisation of complex radiation fields at workplaces around high-energy accelerators, but also at the next generation of thermonuclear fusion facilities. The paper provides an overview of the report, which will be available as CERN Yellow Report. PMID:17496292

  11. Simulation of the neutron spectrum from the 7Li(p,n) reaction with a liquid-lithium target at Soreq Applied Research Accelerator Facility

    NASA Astrophysics Data System (ADS)

    Friedman, M.; Cohen, D.; Paul, M.; Berkovits, D.; Eisen, Y.; Feinberg, G.; Giorginis, G.; Halfon, S.; Krása, A.; Plompen, A. J. M.; Shor, A.

    2013-01-01

    The 7Li(p,n)7Be reaction has been used for the last 25 years to produce quasi-Maxwellian neutrons in order to measure Maxwellian-Averaged Cross-Sections in the relevant temperatures for stellar nucleosynthesis. A liquid-lithium target at the Soreq Applied Research Accelerator Facility is expected to allow us to perform such measurements at higher neutron intensities. Here we describe a Monte Carlo tool, SimLiT, developed to evaluate neutron spectra, intensities and angular distributions resulting from this reaction. We also demonstrate the feasibility to couple SimLiT with an advanced transport code, resulting in a powerful tool for planning and analysis of experiments using the 7Li(p,n) reaction as a neutron source.

  12. Construction of. gamma pi. /sup 0/ spectrometer and photon tagging facility at Bates Linear Accelerator. Final report, July 31, 1979-July 31, 1980

    SciTech Connect

    Booth, E.C.

    1981-08-01

    The funds provided under Contract No. DE-AC02-79ER10486 were totally expended for hardware and supplies required by two related devices at the Bates Linear Accelerator. These were a photon tagging facility and a ..gamma pi../sup 0/ spectrometer in Beam Line C of the new South Experimental Hall. Construction was begun in November of 1979 and both systems became fully operational in the summer of 1981. Preliminary data was taken in 1980 with a prototype ..gamma pi../sup 0/ spectrometer will be carried out in the fall of 1981 and spring of 1982. The photon tagging system has been used successfully to calibrate the ..gamma pi../sup 0/ spectrometer for the BU - MIT collaboration and to test a lead glass detector system for Brandeis University.

  13. The non-orthogonal fixed beam arrangement for the second proton therapy facility at the National Accelerator Center

    NASA Astrophysics Data System (ADS)

    Schreuder, A. N.; Jones, D. T. L.; Conradie, J. L.; Fourie, D. T.; Botha, A. H.; Müller, A.; Smit, H. A.; O'Ryan, A.; Vernimmen, F. J. A.; Wilson, J.; Stannard, C. E.

    1999-06-01

    The medical user group at the National Accelerator Center (NAC) is currently unable to treat all eligible patients with high energy protons. Developing a second proton treatment room is desirable since the 200 MeV proton beam from the NAC separated sector cyclotron is currently under-utilized during proton therapy sessions. During the patient positioning phase in one treatment room, the beam could be used for therapy in a second room. The second proton therapy treatment room at the NAC will be equipped with two non-orthogonal beam lines, one horizontal and one at 30 degrees to the vertical. The two beams will have a common isocentre. This beam arrangement together with a versatile patient positioning system (commercial robot arm) will provide the radiation oncologist with a diversity of possible beam arrangements and offers a reasonable cost-effective alternative to an isocentric gantry.

  14. The non-orthogonal fixed beam arrangement for the second proton therapy facility at the National Accelerator Center

    SciTech Connect

    Schreuder, A. N.; Jones, D. T. L.; Conradie, J. L.; Fourie, D. T.; Botha, A. H.; Mueller, A.; Smit, H. A.; O'Ryan, A.; Vernimmen, F. J. A.; Wilson, J.; Stannard, C. E.

    1999-06-10

    The medical user group at the National Accelerator Center (NAC) is currently unable to treat all eligible patients with high energy protons. Developing a second proton treatment room is desirable since the 200 MeV proton beam from the NAC separated sector cyclotron is currently under-utilized during proton therapy sessions. During the patient positioning phase in one treatment room, the beam could be used for therapy in a second room. The second proton therapy treatment room at the NAC will be equipped with two non-orthogonal beam lines, one horizontal and one at 30 degrees to the vertical. The two beams will have a common isocentre. This beam arrangement together with a versatile patient positioning system (commercial robot arm) will provide the radiation oncologist with a diversity of possible beam arrangements and offers a reasonable cost-effective alternative to an isocentric gantry.

  15. Vibration Response Testing of the CEBAF 12GeV Upgrade Cryomodules

    SciTech Connect

    Davis, G. Kirk; Matalevich, Joseph R.; Wiseman, Mark A.; Powers, Thomas J.

    2012-09-01

    The CEBAF 12 GeV upgrade project includes 80 new 7-cell cavities to form 10 cryomodules. These cryomodules were tested during production to characterize their microphonic response in situ. For several early cryomodules, detailed (vibration) modal studies of the cryomodule string were performed during the assembly process to identify the structural contributors to the measured cryomodule microphonic response. Structural modifications were then modelled, implemented, and verified by subsequent modal testing and in-situ microphonic response testing. Interim and latest results from this multi-stage process will be reviewed.

  16. Superharp: A wire scanner with absolute position readout for beam energy measurement at CEBAF

    SciTech Connect

    Yan, C.

    1994-09-07

    Superharp is an upgrade CEBAF wire scanner with absolute position readout from shaft encoder. As high precision absolute beam position probe ({Delta}x {approximately} 10{mu}m), three pairs of superharps are installed at the entrance, the mid-point, and the exit of Hall C arc beamline in beam switch yard, which will be tuned in dispersive mode as energy spectrometer performing 10{sup {minus}3} beam energy measurement. With dual sensor system: the direct current pickup and the bremsstrahlung detection electronics, beam profile can be obtained by superharp at wide beam current range from 1 {mu}A to 100 {mu}A.

  17. Diffractive electroproduction of s{bar s} mesons off nuclei at CEBAF energies

    SciTech Connect

    Benhar, O.; Nikolaev, N.N.; Zakharov, B.G.

    1994-04-01

    The authors discuss diffractive incoherent electroproduction of s{bar s} mesons off nuclear targets at beam energies that are expected to be available at CEBAF (5-8 GeV). The Q{sup 2} and target mass dependence of the {phi} and {phi}{prime} transparency ratios has been studied within a theoretical approach in which the propagation of the s{bar s} pair through the nuclear medium is described in terms of the quantum mechanical evolution operator. The authors predict a complex pattern of nuclear effects, whose experimental study may provide information on several issues relevant to the understanding of QCD, both in the perturbative and nonperturbative regimes.

  18. A fast coherent synchrotron radiation monitor for the bunch length of the short CEBAF bunches

    NASA Astrophysics Data System (ADS)

    Wang, D. X.; Krafft, G. A.; Price, E.; Wood, P.; Porterfield, D.; Crowe, T.

    1996-04-01

    A novel bunch length monitor for short (down to subpicosecond) electron bunches has been developed in a collaboration between CEBAF and the University of Virginia (UVA), using coherent synchrotron radiation (CSR) detection techniques. The monitor employs a state of the art ``narrowband'' GaAs Schottky whisker diode developed by the UVA group, and has the following features: it is non-invasive, compact, and low cost, it has fast rise time, low noise, high sensitivity, and it operates at room temperature. In this paper, the design parameters and performance of the monitor and selected measurement results will be presented.

  19. Acceleration Studies

    NASA Technical Reports Server (NTRS)

    Rogers, Melissa J. B.

    1993-01-01

    Work to support the NASA MSFC Acceleration Characterization and Analysis Project (ACAP) was performed. Four tasks (analysis development, analysis research, analysis documentation, and acceleration analysis) were addressed by parallel projects. Work concentrated on preparation for and implementation of near real-time SAMS data analysis during the USMP-1 mission. User support documents and case specific software documentation and tutorials were developed. Information and results were presented to microgravity users. ACAP computer facilities need to be fully implemented and networked, data resources must be cataloged and accessible, future microgravity missions must be coordinated, and continued Orbiter characterization is necessary.

  20. Analysis of Residual Acceleration Effects on Transport and Segregation During Directional Solidification of Tin-Bismuth in the MEPHISTO Furnace Facility

    NASA Technical Reports Server (NTRS)

    Alexander, J. Iwan D.

    1998-01-01

    The research accomplishments summarized in this Final Report during the period from 3/95 to 3/98, which included a 12 months no-cost extension granted at the end of the nominal 2 year period of performance. The report has 5 sections, in section 1 the objectives are presented, a task description is given and the background and significance of the work is outlined. In section 2 the research accomplishments are summarized. In section 3 publications and presentations are listed. Student participation is listed in 4. The work is summarized in section 5. and references for sections 1 and 2 are supplied in section 6. The object of this work, is to approach the problem of determining the transport conditions (and effects of residual acceleration) during the plane-front directional solidification of a tin-bismuth alloy under low gravity conditions. The work involved using a combination of 2- and 3-D numerical models, scaling analyses, ID models and the results of ground-based and low-gravity experiments. The experiments conducted in the MEPHISTO furnace facility during the USW-3 space flight which took place between February 22 through March 6, 199). This experiment represents an unprecedented opportunity to make a quantitative correlation between residual accelerations and the response of an actual experimental solidification

  1. FLAME facility: The effect of obstacles and transverse venting on flame acceleration and transition on detonation for hydrogen-air mixtures at large scale

    SciTech Connect

    Sherman, M.P.; Tieszen, S.R.; Benedick, W.B.

    1989-04-01

    This report describes research on flame acceleration and deflagration-to-detonation transition (DDT) for hydrogen-air mixtures carried out in the FLAME facility, and describes its relevance to nuclear reactor safety. Flame acceleration and DDT can generate high peak pressures that may cause failure of containment. FLAME is a large rectangular channel 30.5 m long, 2.44 m high, and 1.83 m wide. It is closed on the ignition end and open on the far end. The three test variables were hydrogen mole fraction (12--30%), degree of transverse venting (by moving steel top plates---0%, 13%, and 50%), and the absence or presence of certain obstacles in the channel (zero or 33% blockage ratio). The most important variable was the hydrogen mole fraction. The presence of the obstacles tested greatly increased the flame speeds, overpressures, and tendency for DDT compared to similar tests without obstacles. Different obstacle configurations could have greater or lesser effects on flame acceleration and DDT. Large degrees of transverse venting reduced the flame speeds, overpressures, and possibility of DDT. For small degrees of transverse venting (13% top venting), the flame speeds and overpressures were higher than for no transverse venting with reactive mixtures (>18% H/sub 2/), but they were lower with leaner mixtures. The effect of the turbulence generated by the flow out the vents on increasing flame speed can be larger than the effect of venting gas out of the channel and hence reducing the overpressure. With no obstacles and 50% top venting, the flame speeds and overpressures were low, and there was no DDT. For all other cases, DDT was observed above some threshold hydrogen concentration. DDT was obtained at 15% H/sub 2/ with obstacles and no transverse venting. 67 refs., 62 figs.

  2. Development of site-specific synthetic accelerations for safety assessment of DOE facilities at Oak Ridge, Tennessee

    SciTech Connect

    Aramayo, G.A.; Carley, T.G.; Jones, W.D.

    1991-01-01

    Seismic analysis of US Department of Energy (DOE) facilities at Oak Ridge, TN, requires seismic accelerograms that have response spectra that are compatible with the site-specific design response spectra. The development of these accelerograms is accomplished by the application of the Fourier transform to compute the response spectrum of a beginning accelerogram and map it into the frequency domain. The Fourier spectrum is modified according to the difference between the computed spectra and the target spectra. The response spectrum is recomputed and compared again to the target. The modification is repeated until acceptable agreement is achieved. The modified Fourier spectrum is transformed to the time domain and filtered yielding the desired seismic time history. 7 refs., 5 figs.

  3. Preliminary energy-filtering neutron imaging with time-of-flight method on PKUNIFTY: A compact accelerator based neutron imaging facility at Peking University

    NASA Astrophysics Data System (ADS)

    Wang, Hu; Zou, Yubin; Wen, Weiwei; Lu, Yuanrong; Guo, Zhiyu

    2016-07-01

    Peking University Neutron Imaging Facility (PKUNIFTY) works on an accelerator-based neutron source with a repetition period of 10 ms and pulse duration of 0.4 ms, which has a rather low Cd ratio. To improve the effective Cd ratio and thus improve the detection capability of the facility, energy-filtering neutron imaging was realized with the intensified CCD camera and time-of-flight (TOF) method. Time structure of the pulsed neutron source was firstly simulated with Geant4, and the simulation result was evaluated with experiment. Both simulation and experiment results indicated that fast neutrons and epithermal neutrons were concentrated in the first 0.8 ms of each pulse period; meanwhile in the period of 0.8-2.0 ms only thermal neutrons existed. Based on this result, neutron images with and without energy filtering were acquired respectively, and it showed that detection capability of PKUNIFTY was improved with setting the exposure interval as 0.8-2.0 ms, especially for materials with strong moderating capability.

  4. The André E. Lalonde AMS Laboratory - The new accelerator mass spectrometry facility at the University of Ottawa

    NASA Astrophysics Data System (ADS)

    Kieser, W. E.; Zhao, X.-L.; Clark, I. D.; Cornett, R. J.; Litherland, A. E.; Klein, M.; Mous, D. J. W.; Alary, J.-F.

    2015-10-01

    The University of Ottawa, Canada, has installed a multi-element, 3 MV tandem AMS system as the cornerstone of their new Advanced Research Complex and the principal analytical instrument of the André E. Lalonde Accelerator Mass Spectrometry Laboratory. Manufactured by High Voltage Engineering Europa B.V., the Netherlands, it is equipped with a 200 sample ion source, a high resolution, 120° injection magnet, a 90° high energy analysis magnet (mass-energy product 350 MeV-AMU), a 65°, 1.7 m radius electric analyzer and a 2 channel gas ionization detector. It is designed to analyze isotopes ranging from tritium to the actinides and to accommodate the use of fluoride target materials. This system is being extended with a second injection line, consisting of selected components from the IsoTrace Laboratory, University of Toronto. This line will contain a pre-commercial version of the Isobar Separator for Anions, manufactured by Isobarex Corp., Bolton, Ontario, Canada. This instrument uses selective ion-gas reactions in a radio-frequency quadrupole cell to attenuate both atomic and molecular isobars. This paper discusses the specifications of the new AMS equipment, reports on the acceptance test results for 10Be, 14C, 26Al and 127I and presents typical spectra for 10Be and actinide analyses.

  5. The new external microbeam facility at the 5 MV Tandetron accelerator laboratory in Madrid: beam characterisation and first results

    NASA Astrophysics Data System (ADS)

    Enguita, Olga; Fernández-Jiménez, M. T.; García, G.; Climent-Font, A.; Calderón, T.; Grime, G. W.

    2004-06-01

    This paper describes the new external microbeam on the 15° beamline of the 5 MV Tandetron accelerator recently installed at the CMAM in Madrid. The focusing and beam extraction system was supplied by Oxford Microbeams Ltd. and consists of a high precision quadrupole doublet with an interchangeable Kapton window exit nozzle and front-viewing video microscope. The sample is positioned in the beam using a stepper motor stage. The beam current and beam profile have been determined under different experimental conditions. A simple method based on the signal processing of ion-induced luminescence from quartz targets has been used to determine the beam profile in two dimensions simultaneously, without scanning. This is the first step in the development of a real time beam profile monitoring system, which could be used as part of an automated beam focusing procedure. The beam line will be primarily devoted to archaeometry and cultural heritage studies. As an example we report the characterisation of two Tang appearance antique porcelains.

  6. A new 14 GHz Electron-Cyclotron-Resonance Ion Source (ECRIS) for the heavy ion accelerator facility ATLAS

    SciTech Connect

    Schlapp, M.; Pardo, R.C.; Vondrasek, R.C.; Billquist, P.J.; Szczech, J.

    1997-11-01

    A 14 GHz Electron-Cyclotron-Resonance Ion Source (ECRIS) has been designed and built at Argonne National Laboratory. The source is a modification of the AECR at Berkeley and incorporates the latest results from ECR developments to produce intense beams of highly charged ions, including an improved magnetic confinement of the plasma electrons with an axial mirror ratio of 3.5. The aluminum plasma chamber and extraction electrode as well as a biased disk on axis at the microwave injection side donates additional electrons to the plasma, making use of the large secondary electron yield from aluminum oxide. The source is capable of ECR plasma heating using two different frequencies simultaneously to increase the electron energy gain for the production of high charge states. The main design goal is to produce several e{mu}A of at least {sup 238}U{sup 35+} in order to accelerate the beam to coulomb-barrier energies without further stripping. First charge state distributions for gaseous elements have been measured and 210 e{mu}A {sup 16}O{sup 7+} has been achieved. A normalized 90% emittance from 0.1 to 0.2 {pi} mm{sm_bullet}mrad for krypton and oxygen beam has been found.

  7. Feasibility of Near field ODR Imaging of Multi GeV Electron Beams at CEBAF

    SciTech Connect

    A.H. Lumpkin; P. Evtushenko; Arne P. Freyberger; C. Liu

    2007-08-01

    We have evaluated the feasibility of using the optical diffraction radiation (ODR) generated as a 1- to 6-GeV CW electron beam passes nearby the edge of a single metal conducting plane as a nonintercepting (NI) relative beam size monitor for CEBAF. Previous experiments were successfully done using near-field imaging on the lower-current, 7-GeV beam at APS, and an analytical model was developed for near-field imaging. Calculations from this model indicate sufficient beam-size sensitivity in the ODR profiles for beam sizes in the 30-50 micron regime as found in the transport lines of CEBAF before the experimental targets. With anticipated beam currents of 100 microamps, the ODR signal from the charge integrated over the video field time should be ~500 times larger than in the APS case. These signal strengths will allow a series of experiments to be done on beam energy dependencies, impact parameters, polarization effects, and wavelength effects that should further elucidate the working regime of this technique and test the model. Plans for the diagnostics station that will also provide reference optical transition radiation (OTR) images will also be described.

  8. Photoproduction opportunities at CEBAF: Meson spectroscopy and the physics of flying {phi}`s

    SciTech Connect

    Dzierba, A.R.

    1994-04-01

    The availability of high-intensity photon beams with an efficient duty-factor and with energies in the range 10 to 12 GeV makes possible studies in meson spectroscopy, rare decays and possibly symmetry tests such as CP and CPT. Indeed, with a 6 GeV tagged photon beam, realizable in the near future at CEBAF, measurements of rare radiative decays of the {phi}`s will be made. At higher energies, a photon beam could be used to answer a number of questions in meson spectroscopy. An even more exciting possibility is the use of photon beams to produce an intense source of {phi}`s. The physics contemplated at e{sup +}e{sup {minus}} {phi} factories, such as CP and CPT tests, might be also studied at CEBAF with completely different and complementary systematics; e.g. having the {phi}`s decay in flight may offer distinct advantages over {phi}`s produced at rest.

  9. Characterization of the CEBAF 100 kV DC GaAs Photoelectron Gun Vacuum System

    SciTech Connect

    Stutzman, M L; Adderley, P; Brittian, J; Clark, J; Grames, J; Hansknecht, J; Myneni, G R; Poelker, M

    2007-05-01

    A vacuum system with pressure in the low ultra-high vacuum (UHV) range is essential for long photocathode lifetimes in DC high voltage GaAs photoguns. A discrepancy between predicted and measured base pressure in the CEBAF photoguns motivated this study of outgassing rates of three 304 stainless steel chambers with different pretreatments and pump speed measurements of non-evaporable getter (NEG) pumps. Outgassing rates were measured using two independent techniques. Lower outgassing rates were achieved by electropolishing and vacuum firing the chamber. The second part of the paper describes NEG pump speed measurements as a function of pressure through the lower part of the UHV range. Measured NEG pump speed is high at pressures above 5×10-11 Torr, but may decrease at lower pressures depending on the interpretation of the data. The final section investigates the pump speed of a locally produced NEG coating applied to the vacuum chamber walls. These studies represent the first detailed vacuum measurements of CEBAF photogun vacuum chambers.

  10. Characterization of the CEBAF 100 kV DC GaAs photoelectron gun vacuum system

    NASA Astrophysics Data System (ADS)

    Stutzman, M. L.; Adderley, P.; Brittian, J.; Clark, J.; Grames, J.; Hansknecht, J.; Myneni, G. R.; Poelker, M.

    2007-05-01

    A vacuum system with pressure in the low ultra-high vacuum (UHV) range is essential for long photocathode lifetimes in DC high voltage GaAs photoguns. A discrepancy between predicted and measured base pressure in the CEBAF photoguns motivated this study of outgassing rates of three 304 stainless steel chambers with different pretreatments and pump speed measurements of non-evaporable getter (NEG) pumps. Outgassing rates were measured using two independent techniques. Lower outgassing rates were achieved by electropolishing and vacuum firing the chamber. The second part of the paper describes NEG pump speed measurements as a function of pressure through the lower part of the UHV range. Measured NEG pump speed is high at pressures above 5×10 -11 Torr, but may decrease at lower pressures depending on the interpretation of the data. The final section investigates the pump speed of a locally produced NEG coating applied to the vacuum chamber walls. These studies represent the first detailed vacuum measurements of CEBAF photogun vacuum chambers.

  11. Development of a methodology to accelerate a spontaneous grass colonization in a tailings storage facility under semiarid mediterranean climate type

    NASA Astrophysics Data System (ADS)

    Ginocchio, Rosanna; Arellano, Eduardo; Morales-Ladron de Guevara, Arturo

    2016-04-01

    Phytostabilization of massive mine tailings (>400 he) under semiarid environments is challenging, particularly when no organic amendments are locally available and no irrigation is possible. Increasing tendency for reprocessing old tailings to recover valued metals further pioneer the need for simple but effective plant covers. The choice of plant species and form of management are thus very important. CODELCO-Chile chose the Cauquenes post-operational tailings storage facility (TFS; 700 ha), that will be reprocessed for copper and other elements in the near future, to evaluate efficacy of the phytostabilization technology under semiarid conditions in central Chile. Surface application of a polymer (Soiltac TM) has been used for wind control of tailings but phytostabilization is considered as a best cost-effective alternative. A field study was performed to define a management program to improve the establishment and cover of an annual native grass (Vulpia myuros var. megalura), a spontaneous colonizer of the TSF. Considered management factors were control of macro herbivores (with and without fence), macronutrient improvement (with and without application of N-rich foliar fertilizer), and improvement of seed retention in the substrate (with and without small-scale rugosity; with and without lived wind-breakers; with and without mechanical wind-breakers). Each treatment was replicated three times and established in 2 m x 2 m quadrats. Plant response variables were monitored after 1 and 2 grass growing seasons. Application of N-rich foliar fertilizer and any wind control mechanism for seed retention in the substrate were effective for significantly improving both grass cover and biomass production in time, irrespective of macro-herbivore control. Seed production was significantly improved when macro herbivores were excluded and was positively and significantly correlated to vegetative biomass production. When applying this management program for tailings

  12. Recirculating accelerator driver for a high-power free-electron laser: A design overview

    SciTech Connect

    Bohn, C.L.

    1997-06-01

    Jefferson Lab is building a free-electron laser (FEL) to produce continuous-wave (cw), kW-level light at 3-6 {mu}m wavelength. A superconducting linac will drive the laser, generating a 5 mA average current, 42 MeV energy electron beam. A transport lattice will recirculate the beam back to the linac for deceleration and conversion of about 75% of its power into rf power. Bunch charge will range up to 135 pC, and bunch lengths will range down to 1 ps in parts of the transport lattice. Accordingly, space charge in the injector and coherent synchrotron radiation in magnetic bends come into play. The machine will thus enable studying these phenomena as a precursor to designing compact accelerators of high-brightness beams. The FEL is scheduled to be installed in its own facility by 1 October 1997. Given the short schedule, the machine design is conservative, based on modifications of the CEBAF cryomodule and MIT-Bates transport lattice. This paper surveys the machine design.

  13. Review of Activities using the Pulsed Neutron Facility and 2.5-GeV Electron Linac at Pohang Accelerator Laboratory

    SciTech Connect

    Kim, Guinyun; Lee, Manwoo; Kim, Kyung Sook; Yang, Sungchul; Kim, Eunae; Shvetshov, Valery; Cho, Moo-Hyun; Naik, Haladhara

    2011-12-13

    We report on activities using a pulsed neutron facility consisting of an electron linear accelerator, a water-cooled Ta target with a water moderator, and a 12 m time-of-flight path. It is possible to measure neutron total cross sections in the neutron energy range from 0.01 eV to a few hundred eV by using the neutron time-of-flight method; photo-neutron cross sections can also measure by using the bremsstrahlung from the electron linac. A {sup 6}LiZnS(Ag) glass scintillator was used as a neutron detector. The neutron flight path from the water-cooled Ta target to the neutron detector was 12.1 m. In this paper, we report total cross sections of Nb and also resonance parameters obtained using the SAMMY fitting program. The present results are compared with the previous experimental results and the evaluated data in ENDF/B-VII. We also report on the mass-yield distribution of fission products in the 2.5-GeV bremsstrahlung-induced fission of {sup nat}Pb and {sup 209}Bi measured at the 2.5-GeV electron linac using a recoil catcher and an off-line {gamma}-ray spectrometric technique.

  14. A facile glovebox-free strategy to significantly accelerate the syntheses of well-defined polypeptides by N-carboxyanhydride (NCA) ring opening polymerizations

    PubMed Central

    Zou, Jiong; Fan, Jingwei; He, Xun; Zhang, Shiyi; Wang, Hai; Wooley, Karen L.

    2013-01-01

    A facile N2 flow-accelerated N-carboxyanhydride ring opening polymerization (NCA ROP) is demonstrated, herein, with rigorous kinetic studies to evaluate the methodology in detail. By using n-hexylamine as initiator and γ-benzyl-L-glutamate N-carboxyanhydride (BLG-NCA) as monomer, the NCA ROP via a normal amine mechanism (NAM) reached 90% conversion in 2 h under N2 flow at room temperature in a fume hood, much shorter than the time required for the same polymerization conducted in a glove box (14 h). The efficient removal of CO2 from the reaction by N2 flow drove the carbamic acid-amine equilibrium toward the formation of active nucleophilic amino termini and promoted polymerization. The detailed kinetic studies of the polymerization with different feed ratios and N2 flow rates were conducted, demonstrating the living feature of the NCA ROP and the tuning of the polymerization rate by simply changing the flow rate of N2. Maintenance of the reactivity of the amino ω-chain terminus and control during a subsequent polymerization were confirmed by performing chain extension reactions. The N2 flow method provides a new straightforward strategy to synthesize well-defined polypeptides with predictable molecular weights and narrow molecular weight distributions (PDI < 1.19). PMID:23794753

  15. Low-dose neutron dose response of zebrafish embryos obtained from the Neutron exposure Accelerator System for Biological Effect Experiments (NASBEE) facility

    NASA Astrophysics Data System (ADS)

    Ng, C. Y. P.; Kong, E. Y.; Konishi, T.; Kobayashi, A.; Suya, N.; Cheng, S. H.; Yu, K. N.

    2015-09-01

    The dose response of embryos of the zebrafish, Danio rerio, irradiated at 5 h post fertilization (hpf) by 2-MeV neutrons with ≤100 mGy was determined. The neutron irradiations were made at the Neutron exposure Accelerator System for Biological Effect Experiments (NASBEE) facility in the National Institute of Radiological Sciences (NIRS), Chiba, Japan. A total of 10 neutron doses ranging from 0.6 to 100 mGy were employed (with a gamma-ray contribution of 14% to the total dose), and the biological effects were studied through quantification of apoptosis at 25 hpf. The responses for neutron doses of 10, 20, 25, and 50 mGy approximately fitted on a straight line, while those for neutron doses of 0.6, 1 and 2.5 mGy exhibited neutron hormetic effects. As such, hormetic responses were generically developed by different kinds of ionizing radiations with different linear energy transfer (LET) values. The responses for neutron doses of 70 and 100 mGy were significantly below the lower 95% confidence band of the best-fit line, which strongly suggested the presence of gamma-ray hormesis.

  16. Experimental Investigation of Weak Non-Mesonic Decay of 10Be(Lambda)Hypernuclei at CEBAF

    SciTech Connect

    S. Majewski; L. Majling; A. Margaryan; L. Tang

    2005-08-05

    Hypernuclei are convenient laboratory to study the baryon-baryon weak interaction and associated effective Hamiltonian. The strangeness changing process, in which a Lambda hyperon converts to a neutron with a release up to 176 MeV, provides a clear signal for a conversion of an s-quark to a d-quark. We propose to perform a non-mesonic weak decay study of 10Be(Lambda)hypernuclei using the (e,eK) reaction. These investigations will fully utilize the unique parameters of the CEBAF CW electron beam and RF system and are enabled by (1) the use of new detector for alpha particles based on the recently developed RF timing technique with picosecond resolution and (2) the small angle and large acceptance kaon spectrometer-HKS in Hall C.

  17. Exploiting new electrochemical understanding of niobium electropolishing for improved performance of SRF cavities for CEBAF

    SciTech Connect

    Reece, Charles E.; Tian, Hui

    2010-09-01

    Recent incorporation of analytic electrochemistry into the development of protocols for electropolishing niobium SRF cavities has yielded new insights for optimizing this process for consistent, high-performance results. Use of reference electrodes in the electrolyte, electrochemical impedance spectroscopy (EIS), rotating disk electrodes (RDE), and controlled sample temperatures has greatly clarified the process dynamics over the empirical understanding developed via years of practice. Minimizing RF losses at high operational gradients is very valuable for CW linacs. Jefferson Lab is applying these new insights to the low-loss 7-cell cavity design developed for the CEBAF 12 GeV Upgrade. Together with controlled cleaning and assembly techniques to guard against field-emission-causing particulates, the resulting process is yielding consistent cavity performance that exceeds project requirements. Cavity tests show BCS-limited Q well above 30 MV/m. Detailed process data, interpretation, and resulting rf performance data will be presented.

  18. Issues in light meson spectroscopy: The case for meson spectroscopy at CEBAF

    SciTech Connect

    Godfrey, S.

    1994-04-01

    The author reviews some outstanding issues in meson spectroscopy. The most important qualitative issue is whether hadrons with explicit gluonic degrees of freedom exist. To answer this question requires a much better understanding of conventional q{bar q} mesons. The author therefore begins by examining the status of conventional meson spectroscopy and how the situation can be improved. The expected properties of gluonic excitations are discussed with particular emphasis on hybrids to give guidance to experimental searches. Multiquark systems are commented upon as they are likely to be important in the mass region under study and will have to be understood better. In the final section the author discusses the opportunities that CEBAF can offer for the study of meson spectroscopy.

  19. Excited baryon form-factors at high momentum transfer at CEBAF at higher energies

    SciTech Connect

    Stoler, P.

    1994-04-01

    The possibilities of measuring the properties of excited nucleons at high Q{sup 2} by means of exclusive single meson production at CEBAF with an electron energy of 8 GeV is considered. The motivation is to access short range phenomena in baryon structure, and to investigate the transition from the low Q{sup 2} non-perturbative QCD regime, where constituent quark models are valid, to higher Q{sup 2} where it is believed perturbative QCD plays an increasingly important role. It is found that high quality baryon decay angular distributions can be obtained for the most prominent states up to Q{sup 2} {approximately} 12 GeV{sup 2}/c{sup 2} using a set of moderate resolution, large solid angle magnetic spectrometers.

  20. Studies of beam halo formation in the 12GeV CEBAF design

    SciTech Connect

    Yves Roblin; Arne Freyberger

    2007-06-01

    Beam halo formation in the beam transport design for the Jefferson Lab 12GeV upgrade was investigated using 12GeV beam transport models as well as data from 6GeV CEBAF operations. Various halo sources were considered; these covered both nuclear interactions with beam gas as well as optics-related effects such as non linearities in the magnetic fields of the transport elements. Halo due to beam gas scattering was found to be less of a problem at 12GeV compared to the 6GeV machine. Halo due to non linear effects of magnetic elements was characterized as a function of beam orbit and functional forms of the distribution were derived. These functional forms were used as inputs in subsequent detector optimizations studies.

  1. SNEAP 80: symposium of Northeastern Accelerator personnel

    SciTech Connect

    Billen, J.H.

    1980-01-01

    Reports of operations are presented for twenty-seven facilities, along with reports on accelerators in progress, ion sources, insulating gases, charging systems, stripping foils, accelerating tubes, and upgraded accelerator systems. (GHT)

  2. Rare Isotope Accelerators

    NASA Astrophysics Data System (ADS)

    Savard, Guy

    2002-04-01

    The next frontier for low-energy nuclear physics involves experimentation with accelerated beams of short-lived radioactive isotopes. A new facility, the Rare Isotope Accelerator (RIA), is proposed to produce large amount of these rare isotopes and post-accelerate them to energies relevant for studies in nuclear physics, astrophysics and the study of fundamental interactions at low energy. The basic science motivation for this facility will be introduced. The general facility layout, from the 400 kW heavy-ion superconducting linac used for production of the required isotopes to the novel production and extraction schemes and the highly efficient post-accelerator, will be presented. Special emphasis will be put on a number of technical breakthroughs and recent R&D results that enable this new facility.

  3. Fabrication and Testing of the SRF cavities for the CEBAF 12 GeV Upgrade Prototype Cryomodule Renascence

    SciTech Connect

    C. E. Reece; E. F. Daly; S. Manning; R. Manus; S. Morgan; J. P. Ozelis; L. Turlington

    2005-05-01

    Twelve seven-cell niobium cavities for the CEBAF 12 GeV upgrade prototype cryomodule Renascence have been fabricated at JLab and tested individually. This set includes four of the ''Low Loss'' (LL) design and eight of the ''High Gradient'' (HG) design. The fabrication strategy was an efficient mix of batch job-shop component machining and in-house EBW, chemistry, and final-step machining to meet mechanical tolerances. Process highlights will be presented. The cavities have been tested at 2.07 K, the intended CEBAF operating temperature. Performance exceeded the tentative design requirement of 19.2 MV/m CW with less than 29 W dynamic heat dissipation. These results, as well as the HOM damping performance are presented.

  4. Fabrication and Testing of the SRF Cavities for the CEBAF 12 GeV Upgrade Prototype Cryomodule Renascence

    SciTech Connect

    Charles Reece; Edward Daly; Stephen Manning; Robert Manus; Samuel Morgan; Joseph Ozelis; Larry Turlington

    2005-05-01

    Twelve seven-cell niobium cavities for the CEBAF 12 GeV upgrade prototype cryomodule Renascence have been fabricated at JLab and tested individually. This set includes four of the ''Low Loss'' (LL) design and eight of the ''High Gradient'' (HG) design. The fabrication strategy was an efficient mix of batch job-shop component machining and in-house EBW, chemistry, and final-step machining to meet mechanical tolerances. Process highlights will be presented. The cavities have been tested at 2.07 K, the intended CEBAF operating temperature. Performance exceeded the tentative design requirement of 19.2 MV/m cw with less than 29 W dynamic heat dissipation. These results, as well as the HOM damping performance will be presented.

  5. Cavity Design, Fabrication and Commission Performance of a 750MHz, 4-rod Separator for CEBAF 4-Hall Beam Delivery System

    SciTech Connect

    Wang, Haipeng; Cheng, Guangfeng; Turlington, Larry T.; Wissmann, Mark J.

    2015-09-01

    A short version of the original CEBAF normal conducting 4-rod separator cavity has been developed into a 750MHz one * since the concept of simultaneous 4-hall operation for CEBAF is introduced **. This work has been advanced further based on the EM design optimization, bench measurement and by conducting RF-thermal coupled simulation using CST and ANSYS to confirm the cavity tuning and thermal performance. The cavity fabrication used matured technology like copper plating and machining. The cavity flanges, couplers, tuners and cooling channels adopted consistent/compatible hardware with the existing 500MHz cavities. The electromagnetic and thermal design simulations have greatly reduced the prototyping and bench tuning time of the first prototype. Four production cavities have reached a typical 1.94MV kick voltage or 3.0kW wall loss on each cavity after a minor multipactoring or no processing, 7.5% overhead power than the design specification.

  6. Color coherent effects in (e,e{prime}N) and (e,e{prime}N,N(h)) processes at CEBAF

    SciTech Connect

    Frankfurt, L.L.; Sargsyan, M.M.; Strikman, M.I. |

    1994-04-01

    The options for investigating color coherent effects and competing nuclear effects of nucleon-nucleon correlations in nuclei, nuclear shell effects in (e, e{prime}N) and (e, e{prime}NN(h)) reactions are considered. They argue that extension of CEBAF energies to reach Q{sup 2} = 10 GeV{sup 2} will allow systematical investigations of color coherent effects in nonperturbative regime of QCD and their interplay with nuclear effects.

  7. Recent Progress on Design Studies of High-Luminosity Ring-Ring Electron-Ion Collider at CEBAF

    SciTech Connect

    Zhang, Y; Bruell, A; Chevtsov, P; Derbenev, Y S; Ent, R; Krafft, G A; Li, R; Merminga, L; Yunn, B C

    2009-05-01

    The conceptual design of a ring-ring electron-ion collider based on CEBAF has been continuously optimized to cover a wide center-of-mass energy region and to achieve high luminosity and polarization to support next generation nuclear science programs. Here, we summarize the recent design improvements and R&D progress on interaction region optics with chromatic aberration compensation, matching and tracking of electron polarization in the Figure-8 ring, beam-beam simulations and ion beam cooling studies.

  8. The Alto Facility

    NASA Astrophysics Data System (ADS)

    Ibrahim, F.; Azaiez, F.; Essabaa, S.; Verney, D.; Cheikh Mhamed, M.; Franchoo, S.; Lau, C.; Li, R.; Roussière, B.; Said, A.; Tusseau-Nenez, S.; Testov, D.; Penionzhkevich, Yu.; Smirnov, V.; Sokol, E.

    2015-06-01

    The ALTO facility consists of two accelerators in the same area. A Tandem accelerator dedicated to stable (ions and cluster) beam physics and a linear electron accelerator dedicated to the production of radioactive beams. This gives a unique opportunity to have in the same place cluster beams for interdisciplinary physics and stable and radioactive beams for astrophysics and nuclear physics.

  9. Drift-Chamber Gas System Controls Development for the CEBAF Large Acceptance Spectrometer

    SciTech Connect

    M. F. Vineyard; T. J. Carroll; M. N. Lack

    1996-07-01

    The CEBAF Large Acceptance Spectrometer (CLAS) is a superconducting toroidal magnet with a large volume of drift chambers for charged particle tracking. The performance of these chambers depends on accurate monitoring and control of the mixture, flow rate, pressure, temperature, and contaminant levels of the gas. To meet these requirements, a control system is being developed with EPICS. The interface hardware consists of VME ADCs and three RS-232 low-level hardware controllers. The RS-232 instruments include MKS 647A mass flow controllers to control and monitor the gas mixture and flow, MKS 146B pressure gauge controllers to measure pressures, and a Panametrics hygrometer to monitor temperatures and the concentrations of oxygen, water vapor, and ethane. Many of the parameters are available as analog signals which will be monitored with XYCOM VME analog input cards and configured for alarms and data logging. The RS-232 interfaces will be used for remote control of the hardware and verification of the analog readings. Information will be passed quickly and efficiently to and from the user through a graphical user interface. A discussion of the requirements and design of the system is presented.

  10. Studies of Nucleon Form Factors with 12 GeV CEBAF and SuperBigBite

    SciTech Connect

    Hansen, Jens-Ole

    2012-04-01

    The elastic electromagnetic form factors are among the most fundamental quantities that describe the ground-state structure of the proton and neutron. Precision data of the form factors over a wide kinematical range provide a powerful test of current theories of hadron structure. A number of experiments aiming to measure the electric and magnetic elastic form factors of the neutron, G{sub E}{sup n} and G{sub M}{sup n}, and proton, G{sub E}{sup p}, at very high momentum transfer, up to the range of Q{sup 2} = 10-14 (GeV/c){sup 2}, are planned to be carried out with the future 11 GeV electron beam of the upgraded CEBAF at Jefferson Lab. These experiments will determine the nucleon form factors with unprecedented precision to Q{sup 2}-values up to three times higher than those of existing data. We review the approved proposals and the conceptual design of a new spectrometer, SuperBigBite, that will be used in these and other future experiments at Jefferson Lab.

  11. Source and Extraction for Simultaneous Four-hall Beam Delivery System at CEBAF

    SciTech Connect

    Kazimi, Reza; Wang, Haipeng; Spata, Mike F.; Hansknecht, John C.

    2013-06-01

    A new design for simultaneous delivery of the electron beam to all four 12 GeV CEBAF experimental halls* requires a new 750 MHz RF separator system in the 5th pass extraction region, a 250 MHz repetition rate for its beams, and addition of a fourth laser at the photo-cathode gun. The proposed system works in tandem with the existing 500 MHz RF separators and beam repetition rate on the lower passes. The new 5th pass RF separators will have the same basic design but modified to run at 750 MHz. The change to the beam repetition rate will be at the photo-cathode gun through an innovative upgrade of the seed laser driver system using electro-optic modulators. The new laser system also allows addition of the fourth laser. The new RF separators, the new laser system and other hardware changes required to implement the Four-Hall operation delivery system will be discussed in this paper.

  12. HIGH POWER TEST OF RF SEPARATOR FOR 12 GEV UPGRADE OF CEBAF AT JLAB

    SciTech Connect

    S. Ahmed, M. Wissmann, J. Mammosser, C. Hovater, M. Spata, G. Krafft, J. Delayen

    2012-07-01

    CEBAF at JLab is in the process of an energy upgrade from 6 GeV to 12 GeV. The existing setup of the RF separator cavities in the 5th pass will not be adequate to extract the highest energy (11 GeV) beam to any two existing halls (A, B or C) while simultaneously delivering to the new hall D in the case of the proposed 12 GeV upgrade of the machine. To restore this capability, we are exploring the possibility of extension of existing normal conducting 499 MHz TEM-type rf separator cavities. Detailed numerical studies suggest that six 2-cell normal conducting structures meet the requirements; each 2-cell structure will require up to 4 kW RF input power in contrast with the current nominal operating power of 1.0 to 2.0 kW. A high power test of 4 kW confirms that the cavity meet the requirement.

  13. Linear Accelerators

    NASA Astrophysics Data System (ADS)

    Sidorin, Anatoly

    2010-01-01

    In linear accelerators the particles are accelerated by either electrostatic fields or oscillating Radio Frequency (RF) fields. Accordingly the linear accelerators are divided in three large groups: electrostatic, induction and RF accelerators. Overview of the different types of accelerators is given. Stability of longitudinal and transverse motion in the RF linear accelerators is briefly discussed. The methods of beam focusing in linacs are described.

  14. Linear Accelerators

    SciTech Connect

    Sidorin, Anatoly

    2010-01-05

    In linear accelerators the particles are accelerated by either electrostatic fields or oscillating Radio Frequency (RF) fields. Accordingly the linear accelerators are divided in three large groups: electrostatic, induction and RF accelerators. Overview of the different types of accelerators is given. Stability of longitudinal and transverse motion in the RF linear accelerators is briefly discussed. The methods of beam focusing in linacs are described.

  15. Overview of accelerators in medicine

    SciTech Connect

    Lennox, A.J. |

    1993-06-01

    Accelerators used for medicine include synchrotrons, cyclotrons, betatrons, microtrons, and electron, proton, and light ion linacs. Some accelerators which were formerly found only at physics laboratories are now being considered for use in hospital-based treatment and diagnostic facilities. This paper presents typical operating parameters for medical accelerators and gives specific examples of clinical applications for each type of accelerator, with emphasis on recent developments in the field.

  16. Use of a wire scanner for monitoring residual gas ionization in Soreq Applied Research Accelerator Facility 20 keV∕u proton∕deuteron low energy beam transport beam line.

    PubMed

    Vainas, B; Eliyahu, I; Weissman, L; Berkovits, D

    2012-02-01

    The ion source end of the Soreq Applied Research Accelerator Facility accelerator consists of a proton∕deuteron ECR ion source and a low energy beam transport (LEBT) beam line. An observed reduction of the radio frequency quadrupole transmission with increase of the LEBT current prompted additional study of the LEBT beam properties. Numerous measurements have been made with the LEBT bream profiler wire biased by a variable voltage. Current-voltage characteristics in presence of the proton beam were measured even when the wire was far out of the beam. The current-voltage characteristic in this case strongly resembles an asymmetric diodelike characteristic, which is typical of Langmuir probes monitoring plasma. The measurement of biased wire currents, outside the beam, enables us to estimate the effective charge density in vacuum. PMID:22380317

  17. Longitudinal laser ion acceleration in low density targets: experimental optimization on the Titan laser facility and numerical investigation of the ultra-high intensity limit

    NASA Astrophysics Data System (ADS)

    d'Humières, E.; Chen, S.; Lobet, Mathieu; Sciscio, M.; Antici, Patrizio; Bailly-Grandvaux, Mathieu; Gangolf, Thomas; Revet, Guilhem; Santos, Joao J.; Schroer, Anna-Marie; Willi, O.; Tikhonchuk, Vladimir T.; Pepin, Henri; Fuchs, Julien

    2015-05-01

    Recent theoretical and experimental studies suggest the possibility of enhancing the efficiency and ease of laser acceleration of protons and ions using underdense or near critical plasmas through electrostatic shocks. Very promising results were recently obtained in this regime. In these experiments, a first ns pulse was focused on a thin target to explode it and a second laser with a high intensity was focused on the exploded foil. The delay between two lasers allowed to control the density gradient seen by the second laser pulse. The transition between various laser ion acceleration regimes depending on the density gradient length was studied. With a laser energy of a few Joules, protons with energies close to the energies of TNSA accelerated protons were obtained for various exploded foils configurations. In the high energy regime (~180 J), protons with energies significantly higher than the ones of TNSA accelerated protons were obtained when exploding the foil while keeping a good beam quality. These results demonstrate that low-density targets are promising candidates for an efficient proton source that can be optimized by choosing appropriate plasma conditions. New experiments were also performed in this regime with gas jets. Scaling shock acceleration in the low density regime to ultra high intensities is a challenge as radiation losses and electron positron pair production change the optimization of the shock process. Using large-scale Particle-In-Cell simulations, the transition to this regime in which intense beams of relativistic ions can be produced is investigated.

  18. Can Accelerators Accelerate Learning?

    NASA Astrophysics Data System (ADS)

    Santos, A. C. F.; Fonseca, P.; Coelho, L. F. S.

    2009-03-01

    The 'Young Talented' education program developed by the Brazilian State Funding Agency (FAPERJ) [1] makes it possible for high-schools students from public high schools to perform activities in scientific laboratories. In the Atomic and Molecular Physics Laboratory at Federal University of Rio de Janeiro (UFRJ), the students are confronted with modern research tools like the 1.7 MV ion accelerator. Being a user-friendly machine, the accelerator is easily manageable by the students, who can perform simple hands-on activities, stimulating interest in physics, and getting the students close to modern laboratory techniques.

  19. PARTICLE ACCELERATOR

    DOEpatents

    Teng, L.C.

    1960-01-19

    ABS>A combination of two accelerators, a cyclotron and a ring-shaped accelerator which has a portion disposed tangentially to the cyclotron, is described. Means are provided to transfer particles from the cyclotron to the ring accelerator including a magnetic deflector within the cyclotron, a magnetic shield between the ring accelerator and the cyclotron, and a magnetic inflector within the ring accelerator.

  20. UCLA accelerator research & development. Progress report

    SciTech Connect

    1997-09-01

    This report discusses work on advanced accelerators and beam dynamics at ANL, BNL, SLAC, UCLA and Pulse Sciences Incorporated. Discussed in this report are the following concepts: Wakefield acceleration studies; plasma lens research; high gradient rf cavities and beam dynamics studies at the Brookhaven accelerator test facility; rf pulse compression development; and buncher systems for high gradient accelerator and relativistic klystron applications.

  1. Review of ion accelerators

    SciTech Connect

    Alonso, J.

    1990-06-01

    The field of ion acceleration to higher energies has grown rapidly in the last years. Many new facilities as well as substantial upgrades of existing facilities have extended the mass and energy range of available beams. Perhaps more significant for the long-term development of the field has been the expansion in the applications of these beams, and the building of facilities dedicated to areas outside of nuclear physics. This review will cover many of these new developments. Emphasis will be placed on accelerators with final energies above 50 MeV/amu. Facilities such as superconducting cyclotrons and storage rings are adequately covered in other review papers, and so will not be covered here.

  2. Analysis of Residual Acceleration Effects on Transport and Segregation During Directional Solidification of Tin-Bismuth in the MEPHISTO Furnace Facility

    NASA Technical Reports Server (NTRS)

    Alexander J. Iwan D. (Principal Investigator)

    1996-01-01

    The objective of this work is to approach the problem of determining the transport conditions (and effects of residual acceleration) during the plane-front directional solidification of a tin-bismuth alloy under low gravity conditions. The work involves using a combination of 2- and 3-D numerical models, scaling analyses, ID models and the results of ground-based and low-gravity experiments. The latter are to be conducted during the MEPHISTO experiment scheduled for USMP-3 in early 1996. The models will be used to predict the response of the transport conditions and consequent solute segregation in directionally solidifying tin-bismuth melt. Real-time Seebeck voltage variations across a Sn-Bi melt during directional solidification in MEPHISTO on USMP-1 show a distinct variation which can be correlated with thruster firings. The Seebeck voltage measurement is related to the response of the instantaneous average melt composition at the melt-solid interface. This allows a direct comparison of numerical simulations with the Seebeck signals obtained on USMP-1. The effects of such accelerations on composition for a directionally solidifying Sn-Bi alloy have been simulated numerically. USMP-1 acceleration data was used to assist in our choice of acceleration magnitude and orientation. The results show good agreement with experimental observations. The USMP-3 experiments took place earlier this year (February 22 through March 6). There were several differences between the USMP-3 experiments as compared to USMP-1. Firstly a more concentrated alloy was solidified and, secondly, Primary Reaction Control System thruster burns were requested at particular times during four separate growth runs. This allowed us to monitor the response Seebeck response under well-characterized growth conditions. In addition, we carried out simulations during the experiment in order to interpret the Seebeck signal. Preliminary results are described here.

  3. Liquid Methane Conditioning Capabilities Developed at the NASA Glenn Research Center's Small Multi- Purpose Research Facility (SMiRF) for Accelerated Lunar Surface Storage Thermal Testing

    NASA Technical Reports Server (NTRS)

    Bamberger, Helmut H.; Robinson, R. Craig; Jurns, John M.; Grasl, Steven J.

    2011-01-01

    Glenn Research Center s Creek Road Cryogenic Complex, Small Multi-Purpose Research Facility (SMiRF) recently completed validation / checkout testing of a new liquid methane delivery system and liquid methane (LCH4) conditioning system. Facility checkout validation was conducted in preparation for a series of passive thermal control technology tests planned at SMiRF in FY10 using a flight-like propellant tank at simulated thermal environments from 140 to 350K. These tests will validate models and provide high quality data to support consideration of LCH4/LO2 propellant combination option for a lunar or planetary ascent stage.An infrastructure has been put in place which will support testing of large amounts of liquid methane at SMiRF. Extensive modifications were made to the test facility s existing liquid hydrogen system for compatibility with liquid methane. Also, a new liquid methane fluid conditioning system will enable liquid methane to be quickly densified (sub-cooled below normal boiling point) and to be quickly reheated to saturation conditions between 92 and 140 K. Fluid temperatures can be quickly adjusted to compress the overall test duration. A detailed trade study was conducted to determine an appropriate technique to liquid conditioning with regard to the SMiRF facility s existing infrastructure. In addition, a completely new roadable dewar has been procured for transportation and temporary storage of liquid methane. A new spherical, flight-representative tank has also been fabricated for integration into the vacuum chamber at SMiRF. The addition of this system to SMiRF marks the first time a large-scale liquid methane propellant test capability has been realized at Glenn.This work supports the Cryogenic Fluid Management Project being conducted under the auspices of the Exploration Technology Development Program, providing focused cryogenic fluid management technology efforts to support NASA s future robotic or human exploration missions.

  4. Plasma accelerators

    SciTech Connect

    Ruth, R.D.; Chen, P.

    1986-03-01

    In this paper we discuss plasma accelerators which might provide high gradient accelerating fields suitable for TeV linear colliders. In particular we discuss two types of plasma accelerators which have been proposed, the Plasma Beat Wave Accelerator and the Plasma Wake Field Accelerator. We show that the electric fields in the plasma for both schemes are very similar, and thus the dynamics of the driven beams are very similar. The differences appear in the parameters associated with the driving beams. In particular to obtain a given accelerating gradient, the Plasma Wake Field Accelerator has a higher efficiency and a lower total energy for the driving beam. Finally, we show for the Plasma Wake Field Accelerator that one can accelerate high quality low emittance beams and, in principle, obtain efficiencies and energy spreads comparable to those obtained with conventional techniques.

  5. Recent Advances in Plasma Acceleration

    SciTech Connect

    Hogan, Mark

    2007-03-19

    The costs and the time scales of colliders intended to reach the energy frontier are such that it is important to explore new methods of accelerating particles to high energies. Plasma-based accelerators are particularly attractive because they are capable of producing accelerating fields that are orders of magnitude larger than those used in conventional colliders. In these accelerators a drive beam, either laser or particle, produces a plasma wave (wakefield) that accelerates charged particles. The ultimate utility of plasma accelerators will depend on sustaining ultra-high accelerating fields over a substantial length to achieve a significant energy gain. More than 42 GeV energy gain was achieved in an 85 cm long plasma wakefield accelerator driven by a 42 GeV electron drive beam in the Final Focus Test Beam (FFTB) Facility at SLAC. Most of the beam electrons lose energy to the plasma wave, but some electrons in the back of the same beam pulse are accelerated with a field of {approx}52 GV/m. This effectively doubles their energy, producing the energy gain of the 3 km long SLAC accelerator in less than a meter for a small fraction of the electrons in the injected bunch. Prospects for a drive-witness bunch configuration and high-gradient positron acceleration experiments planned for the SABER facility will be discussed.

  6. First e⁻/γ Commissioning Results for the GlueX Experiment/Hall D at CEBAF

    SciTech Connect

    McCaughan, Michael D.; Satogata, Todd J.; Roblin, Yves R.; Benesch, Jay F.

    2015-09-01

    Experimental Hall D, with flagship experiment GlueX, was constructed as part of the 12 GeV CEBAF upgrade. A new magnetically extracted electron beam line was installed to support this hall. Bremsstrahlung photons from retractable radiators are delivered to the experiment through a series of collimators following a long drift to allow for beam convergence. Coherent Bremsstrahlung generated by interaction with a diamond radiator will achieve a nominal 40% linear polarization and photon energies between 8.5 and 9 GeV from 12.1 GeV electrons, which are then tagged or diverted to a medium power 60kW electron dump. The expected photon flux is 107-108 Hz. This paper discusses the experimental line design, commissioning experience gained since first beam in spring 2014, and the present results of beam commissioning by the experiment.

  7. Simulation Studies of Beam-Beam Effects of a Ring-Ring Electron-Ion Collider Based on CEBAF

    SciTech Connect

    Yuhong Zhang,Ji Qiang

    2009-05-01

    The collective beam-beam effect can potentially cause a rapid growth of beam sizes and reduce the luminosity of a collider to an unacceptably low level. The ELIC, a proposed ultra high luminosity electron-ion collider based on CEBAF, employs high repetition rate crab crossing colliding beams with very small bunch transverse sizes and very short bunch lengths, and collides them at up to 4 interaction points with strong final focusing. All of these features can make the beam-beam effect challenging. In this paper, we present simulation studies of the beam-beam effect in ELIC using a self-consistent strong-strong beam-beam simulation code developed at Lawrence Berkeley National Laboratory. This simulation study is used for validating the ELIC design and for searching for an optimal parameter set.

  8. Electromagnetic propulsion test facility

    NASA Technical Reports Server (NTRS)

    Gooder, S. T.

    1984-01-01

    A test facility for the exploration of electromagnetic propulsion concept is described. The facility is designed to accommodate electromagnetic rail accelerators of various lengths (1 to 10 meters) and to provide accelerating energies of up to 240 kiloJoules. This accelerating energy is supplied as a current pulse of hundreds of kiloAmps lasting as long as 1 millisecond. The design, installation, and operating characteristics of the pulsed energy system are discussed. The test chamber and its operation at pressures down to 1300 Pascals (10 mm of mercury) are described. Some aspects of safety (interlocking, personnel protection, and operating procedures) are included.

  9. Results from CEBAF experiment E89-012: Measurements of deuteron photo-disintegration up to 4 GeV

    SciTech Connect

    Mike Miller; David Abbott; Abdellah Ahmidouch; Chris Armstrong; John Arrington; K. A. Assamagan; Oliver K. Baker; S. P. Barrow; D. P. Beatty; D. H. Beck; S. Y. Beedoe; Elizabeth Beise; J. E. Belz; 0 C. W. Bochna; Peter Bosted; Ed Brash; Herbert Breuer; R. V. Cadman; Larry Cardman; Roger Carlini; Jinseok Cha; Nicholas Chant; G. Collins; C. Cothran; W. J. Cummings; Samuel Danagoulian; F. A. Duncan; J. A. Dunne; Dipangkar Dutta; Tom Eden; Rolf Ent; Bradley Filippone; Tony A. Forest; H. T. Fortune; Valera V. Frolov; Haiyan Gao; Donald Geesaman; Ron Gilman; Paul Gueye; Kenneth Gustafsson; Jens-Ole Hansen; M. Harvey; Wendy Hinton; R. J. Holt; Hal Jackson; Cynthia Keppel; M. A. Khandaker; Ed Kinney; Andi Klein; 0 Doug Koltenuk; Gerfried Kumbartzki; Allison Lung; David Mack; Richard Madey; Pete Markowitz; Kenneth McFarlane; Robert McKeown; David Meekins; Z-E. Meziani; J. H. Mitchell; Hamlet Mkrtchyan; R. M. Mohring; James Napolitano; Alan Nathan; Gabriel Niculescu; Ioana Niculescu; Tom O'Neill; B. R. Owen; S. Pate; Dave Potterveld; John Price; G. L. Rakness; Ronald Ransome; Juerg Reinhold; Paul Rutt; G. Savage; Ralph Segel; N. Simicevic; Paul Stoler; Riad Suleiman; Liguang Tang; B. P. Terburg; D. Van Westrum; Bill Vulcan; S. E. Williamson; Michael Witkowski; Stephen Wood; Chen Yan; Ben Zeidman

    1997-05-01

    The first measurements of differential cross sections for deuteron photo-disintegration at photon energies up to 4 GeV were performed at the Thomas Jefferson National Accelerator Facility early in 1996. Cross section results for D(gamma,p)n at proton center of mass angle of 35{sup o}, 53{sup o} and 90{sup o} will be presented. These results are in good agreement with previous measurements at low energy and extend to higher energies where data were previously unavailable. The 90{sup o} degree data show behavior consistent with the constituent counting rules up to 4 GeV and are also in fair agreement with the asymptotic meson exchange model. The 37{sup o} and 53{sup o} data do not show clear signs of counting rule behavior, although a threshold in transverse momentum for the onset of scaling cannot be excluded.

  10. Development and testing of a deuterium gas target assembly for neutron production via the H-2(d,n)He-3 reaction at a low-energy accelerator facility

    SciTech Connect

    Feautrier, D.; Smith, D.L.

    1992-03-01

    This report describes the development and testing of a deuterium gas target intended for use at a low-energy accelerator facility to produce neutrons for basic research and various nuclear applications. The principle source reaction is H-2(d,n)He-3. It produces a nearly mono-energetic group of neutrons. However, a lower-energy continuum neutron spectrum is produced by the H-2(d;n,p)H-2 reaction and also by deuterons which strike various components in the target assembly. The present target is designed to achieve the following objectives: (1) minimize unwanted background neutron production from the target assembly, (2) provide a relatively low level of residual long-term activity within the target components, (3) have the capacity to dissipate up to 150 watts of beam power with good target longevity, and (4) possess a relatively modest target mass in order to minimize neutron scattering from the target components. The basic physical principles that have to be considered in designing an accelerator target are discussed and the major engineering features of this particular target design are outlined. The results of initial performance tests on this target are documented and some conclusions concerning the viability of the target design are presented.

  11. Proposal for the study of thermophysical properties of high-energy-density matter using current and future heavy-ion accelerator facilities at GSI Darmstadt.

    PubMed

    Tahir, N A; Deutsch, C; Fortov, V E; Gryaznov, V; Hoffmann, D H H; Kulish, M; Lomonosov, I V; Mintsev, V; Ni, P; Nikolaev, D; Piriz, A R; Shilkin, N; Spiller, P; Shutov, A; Temporal, M; Ternovoi, V; Udrea, S; Varentsov, D

    2005-07-15

    The subject of high-energy-density (HED) states in matter is of considerable importance to numerous branches of basic as well as applied physics. Intense heavy-ion beams are an excellent tool to create large samples of HED matter in the laboratory with fairly uniform physical conditions. Gesellschaft für Schwerionenforschung, Darmstadt, is a unique worldwide laboratory that has a heavy-ion synchrotron, SIS18, that delivers intense beams of energetic heavy ions. Construction of a much more powerful synchrotron, SIS100, at the future international facility for antiprotons and ion research (FAIR) at Darmstadt will lead to an increase in beam intensity by 3 orders of magnitude compared to what is currently available. The purpose of this Letter is to investigate with the help of two-dimensional numerical simulations, the potential of the FAIR to carry out research in the field of HED states in matter. PMID:16090748

  12. Interfacing to accelerator instrumentation

    SciTech Connect

    Shea, T.J.

    1995-12-31

    As the sensory system for an accelerator, the beam instrumentation provides a tremendous amount of diagnostic information. Access to this information can vary from periodic spot checks by operators to high bandwidth data acquisition during studies. In this paper, example applications will illustrate the requirements on interfaces between the control system and the instrumentation hardware. A survey of the major accelerator facilities will identify the most popular interface standards. The impact of developments such as isochronous protocols and embedded digital signal processing will also be discussed.

  13. High intensity hadron accelerators

    SciTech Connect

    Teng, L.C.

    1989-05-01

    This rapporteur report consists mainly of two parts. Part I is an abridged review of the status of all High Intensity Hadron Accelerator projects in the world in semi-tabulated form for quick reference and comparison. Part II is a brief discussion of the salient features of the different technologies involved. The discussion is based mainly on my personal experiences and opinions, tempered, I hope, by the discussions I participated in in the various parallel sessions of the workshop. In addition, appended at the end is my evaluation and expression of the merits of high intensity hadron accelerators as research facilities for nuclear and particle physics.

  14. Overview of SNS accelerator shielding analyses

    SciTech Connect

    Popova, I.; Gallmeier, F. X.; Ferguson, P.; Iverson, E.; Lu, W.

    2012-07-01

    The Spallation Neutron Source is an accelerator driven neutron scattering facility for materials research. During all phases of SNS development, including design, construction, commissioning and operation, extensive neutronics work was performed in order to provide adequate shielding, to assure safe facility operation from radiation protection point of view, and to optimize performance of the accelerator and target facility. Presently, most of the shielding work is concentrated on the beam lines and instrument enclosures to prepare for commissioning, safe operation and adequate radiation background in the future. Although the accelerator is built and in operation mode, there is extensive demand for shielding and activation analyses. It includes redesigning some parts of the facility, facility upgrades, designing additional structures, storage and transport containers for accelerator structures taken out of service, and performing radiation protection analyses and studies on residual dose rates inside the accelerator. (authors)

  15. Proceedings of the international workshop on hadron facility technology

    SciTech Connect

    Thiessen, H.A.

    1987-12-01

    The conference included papers on facility plans, beam dynamics, accelerator hardware, and experimental facilities. Individual abstracts were prepared for 43 papers in the conference proceedings. (LEW)

  16. High Power Polarized Positron Source

    NASA Astrophysics Data System (ADS)

    Mikhailichenko, Alexander

    2009-09-01

    We discuss the basics of polarized positron production by low energy polarized electrons. Efficiency of conversion ˜0.1-1% might be interesting for the Continuous Electron Beam Accelerator Facility (CEBAF) and the International Linear Collider (ILC).

  17. Above scaling short-pulse ion acceleration from flat foil and ``Pizza-top Cone'' targets at the Trident laser facility

    NASA Astrophysics Data System (ADS)

    Flippo, Kirk; Hegelich, B. Manuel; Cort Gautier, D.; Johnson, J. Randy; Kline, John L.; Shimada, Tsutomu; Fernández, Juan C.; Gaillard, Sandrine; Rassuchine, Jennifer; Le Galloudec, Nathalie; Cowan, Thomas E.; Malekos, Steve; Korgan, Grant

    2006-10-01

    Ion-driven Fast Ignition (IFI) has certain advantages over electron-driven FI due to a possible large reduction in the amount of energy required. Recent experiments at the Los Alamos National Laboratory's Trident facility have yielded ion energies and efficiencies many times in excess of recent published scaling laws, leading to even more potential advantages of IFI. Proton energies in excess of 35 MeV have been observed from targets produced by the University of Nevada, Reno - dubbed ``Pizza-top Cone'' targets - at intensities of only 1x10^19 W/cm^2 with 20 joules in 600 fs. Energies in excess of 24 MeV were observed from simple flat foil targets as well. The observed energies, above any published scaling laws, are attributed to target production, preparation, and shot to shot monitoring of many laser parameters, especially the laser ASE prepulse level and laser pulse duration. The laser parameters are monitored in real-time to keep the laser in optimal condition throughout the run providing high quality, reproducible shots.

  18. Studies of thermophysical properties of high-energy-density states in matter using intense heavy ion beams at the future FAIR accelerator facilities: The HEDgeHOB collaboration

    NASA Astrophysics Data System (ADS)

    Tahir, N. A.; Shutov, A.; Lomonosov, I. V.; Gryaznov, V.; Deutsch, C.; Fortov, V. E.; Hoffmann, D. H. H.; Ni, P.; Piriz, A. R.; Udrea, S.; Varentsov, D.; Wouchuk, G.

    2006-06-01

    Intense beams of energetic heavy ions are believed to be a very efficient and novel tool to create states of High-Energy-Density (HED) in matter. This paper shows with the help of numerical simulations that the heavy ion beams that will be generated at the future Facility for Antiprotons and Ion Research (FAIR)[W.F. Henning, Nucl. Instr. Meth. B 214, 211 (2004)] will allow one to use two different experimental schemes to study HED states in matter. First scheme named HIHEX (Heavy Ion Heating and EXpansion), will generate high-pressure, high-entropy states in matter by volumetric isochoric heating. The heated material will then be allowed to expand isentropically. Using this scheme, it will be possible to study important regions of the phase diagram that are either difficult to access or are even unaccessible using traditional methods of shock compression. The second scheme would allow one to achieve low-entropy compression of a sample material like hydrogen or water to produce conditions that are believed to exist in the interiors of the giant planets. This scheme is named LAPLAS (LAboratory PLAnetary Sciences).

  19. Accelerated Reader.

    ERIC Educational Resources Information Center

    Education Commission of the States, Denver, CO.

    This paper provides an overview of Accelerated Reader, a system of computerized testing and record-keeping that supplements the regular classroom reading program. Accelerated Reader's primary goal is to increase literature-based reading practice. The program offers a computer-aided reading comprehension and management program intended to motivate…

  20. The 6 GeV TMD Program at Jefferson Lab

    SciTech Connect

    Puckett, Andrew J.

    2015-01-01

    The study of the transverse momentum dependent parton distributions (TMDs) of the nucleon in semi-inclusive deep-inelastic scattering (SIDIS) has emerged as one of the major physics motivations driving the experimental program using the upgraded 11 GeV electron beam at Jefferson Lab’s Continuous Electron Beam Accelerator Facility (CEBAF). The accelerator construction phase of the CEBAF upgrade is essentially complete and commissioning of the accelerator has begun as of April, 2014. As the new era of CEBAF operations begins, it is appropriate to review the body of published and forthcoming results on TMDs from the 6 GeV era of CEBAF operations, discuss what has been learned, and discuss the key challenges and opportunities for the 11 GeV SIDIS program of CEBAF.

  1. Accelerator structure work for NLC

    SciTech Connect

    Miller, R.H.; Adolphsen, C.; Bane, K.L.F.; Deruyter, H.; Farkas, Z.D.; Hoag, H.A.; Holtkamp, N.; Lavine, T.; Loew, G.A.; Nelson, E.M.; Palmer, R.B.; Paterson, J.M.; Ruth, R.D.; Thompson, K.A.; Vlieks, A.; Wang, J.W.; Wilson, P.B. ); Gluckstern, R. ); Ko, K.; Kroll, N. (Stanford Linear Accelerator Ce

    1992-07-01

    The NLC design achieves high luminosity with multiple bunches in each RF pulse. Acceleration of a train of bunches without emittance growth requires control of long range dipole wakefields. SLAC is pursuing a structure design which suppresses the effect of wakefields by varying the physical dimensions of successive cells of the disk-loaded traveling wave structure in a manner which spreads the frequencies of the higher mode while retaining the synchronism between the electrons and the accelerating mode. The wakefields of structures incorporating higher mode detuning have been measured at the Accelerator Test Facility at Argonne. Mechanical design and brazing techniques which avoid getting brazing alloy into the interior of the accelerator are being studied. A test facility for high-power testing of these structures is complete and high power testing has begun.

  2. LINEAR ACCELERATOR

    DOEpatents

    Colgate, S.A.

    1958-05-27

    An improvement is presented in linear accelerators for charged particles with respect to the stable focusing of the particle beam. The improvement consists of providing a radial electric field transverse to the accelerating electric fields and angularly introducing the beam of particles in the field. The results of the foregoing is to achieve a beam which spirals about the axis of the acceleration path. The combination of the electric fields and angular motion of the particles cooperate to provide a stable and focused particle beam.

  3. Acceleration switch

    DOEpatents

    Abbin, J.P. Jr.; Devaney, H.F.; Hake, L.W.

    1979-08-29

    The disclosure relates to an improved integrating acceleration switch of the type having a mass suspended within a fluid filled chamber, with the motion of the mass initially opposed by a spring and subsequently not so opposed.

  4. Acceleration switch

    DOEpatents

    Abbin, Jr., Joseph P.; Devaney, Howard F.; Hake, Lewis W.

    1982-08-17

    The disclosure relates to an improved integrating acceleration switch of the type having a mass suspended within a fluid filled chamber, with the motion of the mass initially opposed by a spring and subsequently not so opposed.

  5. ION ACCELERATOR

    DOEpatents

    Bell, J.S.

    1959-09-15

    An arrangement for the drift tubes in a linear accelerator is described whereby each drift tube acts to shield the particles from the influence of the accelerating field and focuses the particles passing through the tube. In one embodiment the drift tube is splii longitudinally into quadrants supported along the axis of the accelerator by webs from a yoke, the quadrants. webs, and yoke being of magnetic material. A magnetic focusing action is produced by energizing a winding on each web to set up a magnetic field between adjacent quadrants. In the other embodiment the quadrants are electrically insulated from each other and have opposite polarity voltages on adjacent quadrants to provide an electric focusing fleld for the particles, with the quadrants spaced sufficienily close enough to shield the particles within the tube from the accelerating electric field.

  6. LINEAR ACCELERATOR

    DOEpatents

    Christofilos, N.C.; Polk, I.J.

    1959-02-17

    Improvements in linear particle accelerators are described. A drift tube system for a linear ion accelerator reduces gap capacity between adjacent drift tube ends. This is accomplished by reducing the ratio of the diameter of the drift tube to the diameter of the resonant cavity. Concentration of magnetic field intensity at the longitudinal midpoint of the external sunface of each drift tube is reduced by increasing the external drift tube diameter at the longitudinal center region.

  7. The ISAC post-accelerator

    NASA Astrophysics Data System (ADS)

    Laxdal, R. E.; Marchetto, M.

    2014-01-01

    The acceleration chain of the ISAC facility boosts the energy of both radioactive and stable light and heavy ions for beam delivery to both a medium energy area in ISAC-I and a high energy area in ISAC-II. The post-accelerator comprises a 35.4 MHz RFQ to accelerate beams of A/q ≤ 30 from 2 keV/u to 150 keV/u and a post stripper, 106.1 MHz variable energy drift tube linac (DTL) to accelerate ions of A/q ≤ 6 to a final energy between 0.15 MeV/u to 1.5 MeV/u. A 40 MV superconducting linac further accelerates beam from 1.5 MeV/u to energies above the Coulomb barrier. All linacs operate cw to preserve beam intensity.

  8. Low Level RF System for Jefferson Lab Cryomodule Test Facility

    SciTech Connect

    Tomasz Plawski; Trent Allison; Jean Delayen; J. Hovater; Thomas Powers

    2003-05-01

    The Jefferson Lab Cryomodule Test Facility (CMTF) has been upgraded to test and commission SNS and CEBAF Energy Upgrade cryomodules. Part of the upgrade was to modernize the superconducting cavity instrumentation and control. We have designed a VXI based RF control system exclusively for the production testing of superconducting cavities. The RF system can be configured to work either in Phase Locked Loop (PLL) or Self Excited Loop (SEL) mode. It can be used to drive either SNS 805 MHz or CEBAF Energy Upgrade 1497 MHz superconducting cavities and can be operated in pulsed or continuous wave (CW) mode. The base design consists of RF-analog and digital sections. The RF-analog section includes a Voltage Control Oscillator (VCO), phase detector, I&Q modulator and ''low phase shift'' limiter. The digital section controls the analog section and includes ADC, FPGA, and DAC . We will discuss the design of the RF system and how it relates to the support of cavity testing.

  9. Accelerator Physics Working Group Summary

    NASA Astrophysics Data System (ADS)

    Li, D.; Uesugi, T.; Wildnerc, E.

    2010-03-01

    The Accelerator Physics Working Group addressed the worldwide R&D activities performed in support of future neutrino facilities. These studies cover R&D activities for Super Beam, Beta Beam and muon-based Neutrino Factory facilities. Beta Beam activities reported the important progress made, together with the research activity planned for the coming years. Discussion sessions were also organized jointly with other working groups in order to define common ground for the optimization of a future neutrino facility. Lessons learned from already operating neutrino facilities provide key information for the design of any future neutrino facility, and were also discussed in this meeting. Radiation damage, remote handling for equipment maintenance and exchange, and primary proton beam stability and monitoring were among the important subjects presented and discussed. Status reports for each of the facility subsystems were presented: proton drivers, targets, capture systems, and muon cooling and acceleration systems. The preferred scenario for each type of possible future facility was presented, together with the challenges and remaining issues. The baseline specification for the muon-based Neutrino Factory was reviewed and updated where required. This report will emphasize new results and ideas and discuss possible changes in the baseline scenarios of the facilities. A list of possible future steps is proposed that should be followed up at NuFact10.

  10. Experimental Plans to Explore Dielectric Wakefield Acceleration in the THZ Regime

    SciTech Connect

    Lemery, F.; Mihalcea, D.; Piot, P.; Behrens, C.; Elsen, E.; Flottmann, K.; Gerth, C.; Kube, G.; Schmidt, B.; Osterhoff, J.; Stoltz, P.

    2011-09-07

    Dielectric wakefield accelerators have shown great promise toward high-gradient acceleration. We investigate the performances of a possible experiment under consideration at the FLASH facility in DESY to explore wakefield acceleration with an enhanced transformer ratio. The experiment capitalizes on a unique pulse shaping capability recently demonstrated at this facility. In addition, the facility incorporates a superconducting linear accelerator that could generate bunch trains with closely spaced bunches thereby opening the exploration of potential dynamical effects in dielectric wakefield accelerators.

  11. Future HEP Accelerators: The US Perspective

    SciTech Connect

    Bhat, Pushpalatha; Shiltsev, Vladimir

    2015-11-02

    Accelerator technology has advanced tremendously since the introduction of accelerators in the 1930s, and particle accelerators have become indispensable instruments in high energy physics (HEP) research to probe Nature at smaller and smaller distances. At present, accelerator facilities can be classified into Energy Frontier colliders that enable direct discoveries and studies of high mass scale particles and Intensity Frontier accelerators for exploration of extremely rare processes, usually at relatively low energies. The near term strategies of the global energy frontier particle physics community are centered on fully exploiting the physics potential of the Large Hadron Collider (LHC) at CERN through its high-luminosity upgrade (HL-LHC), while the intensity frontier HEP research is focused on studies of neutrinos at the MW-scale beam power accelerator facilities, such as Fermilab Main Injector with the planned PIP-II SRF linac project. A number of next generation accelerator facilities have been proposed and are currently under consideration for the medium- and long-term future programs of accelerator-based HEP research. In this paper, we briefly review the post-LHC energy frontier options, both for lepton and hadron colliders in various regions of the world, as well as possible future intensity frontier accelerator facilities.

  12. Basic concepts in plasma accelerators.

    PubMed

    Bingham, Robert

    2006-03-15

    In this article, we present the underlying physics and the present status of high gradient and high-energy plasma accelerators. With the development of compact short pulse high-brightness lasers and electron and positron beams, new areas of studies for laser/particle beam-matter interactions is opening up. A number of methods are being pursued vigorously to achieve ultra-high-acceleration gradients. These include the plasma beat wave accelerator (PBWA) mechanism which uses conventional long pulse ( approximately 100 ps) modest intensity lasers (I approximately 10(14)-10(16) W cm(-2)), the laser wakefield accelerator (LWFA) which uses the new breed of compact high-brightness lasers (<1 ps) and intensities >10(18) W cm(-2), self-modulated laser wakefield accelerator (SMLWFA) concept which combines elements of stimulated Raman forward scattering (SRFS) and electron acceleration by nonlinear plasma waves excited by relativistic electron and positron bunches the plasma wakefield accelerator. In the ultra-high intensity regime, laser/particle beam-plasma interactions are highly nonlinear and relativistic, leading to new phenomenon such as the plasma wakefield excitation for particle acceleration, relativistic self-focusing and guiding of laser beams, high-harmonic generation, acceleration of electrons, positrons, protons and photons. Fields greater than 1 GV cm(-1) have been generated with monoenergetic particle beams accelerated to about 100 MeV in millimetre distances recorded. Plasma wakefields driven by both electron and positron beams at the Stanford linear accelerator centre (SLAC) facility have accelerated the tail of the beams. PMID:16483948

  13. Accelerator Technology Division progress report, FY 1992

    SciTech Connect

    Schriber, S.O.; Hardekopf, R.A.; Heighway, E.A.

    1993-07-01

    This report briefly discusses the following topics: The Ground Test Accelerator Program; Defense Free-Electron Lasers; AXY Programs; A Next Generation High-Power Neutron-Scattering Facility; JAERI OMEGA Project and Intense Neutron Sources for Materials Testing; Advanced Free-Electron Laser Initiative; Superconducting Supercollider; The High-Power Microwave (HPM) Program; Neutral Particle Beam (NPB) Power Systems Highlights; Industrial Partnering; Accelerator Physics and Special Projects; Magnetic Optics and Beam Diagnostics; Accelerator Design and Engineering; Radio-Frequency Technology; Accelerator Theory and Free-Electron Laser Technology; Accelerator Controls and Automation; Very High-Power Microwave Sources and Effects; and GTA Installation, Commissioning, and Operations.

  14. Recent Activities at Tokai Tandem Accelerator

    SciTech Connect

    Ishii, Tetsuro

    2010-05-12

    Recent activities at the JAEA-Tokai tandem accelerator facility are presented. The terminal voltage of the tandem accelerator reached 19.1 MV by replacing acceleration tubes. The multi-charged positive-ion injector was installed in the terminal of the tandem accelerator, supplying high-current noble-gas ions. A superconducting cavity for low-velocity ions was developed. Radioactive nuclear beams of {sup 8,9}Li and fission products, produced by the tandem accelerator and separated by the ISOL, were supplied with experiment. Recent results of nuclear physics experiments are reported.

  15. EM Structure Based and Vacuum Acceleration

    SciTech Connect

    Colby, E.R.; /SLAC

    2005-09-27

    The importance of particle acceleration may be judged from the number of applications which require some sort of accelerated beam. In addition to accelerator-based high energy physics research, non-academic applications include medical imaging and treatment, structural biology by x-ray diffraction, pulse radiography, cargo inspection, material processing, food and medical instrument sterilization, and so on. Many of these applications are already well served by existing technologies and will profit only marginally from developments in accelerator technology. Other applications are poorly served, such as structural biology, which is conducted at synchrotron radiation facilities, and medical treatment using proton accelerators, the machines for which are rare because they are complex and costly. Developments in very compact, high brightness and high gradient accelerators will change how accelerators are used for such applications, and potentially enable new ones. Physical and technical issues governing structure-based and vacuum acceleration of charged particles are reviewed, with emphasis on practical aspects.

  16. Plasma accelerator

    DOEpatents

    Wang, Zhehui; Barnes, Cris W.

    2002-01-01

    There has been invented an apparatus for acceleration of a plasma having coaxially positioned, constant diameter, cylindrical electrodes which are modified to converge (for a positive polarity inner electrode and a negatively charged outer electrode) at the plasma output end of the annulus between the electrodes to achieve improved particle flux per unit of power.

  17. Accelerated Achievement

    ERIC Educational Resources Information Center

    Ford, William J.

    2010-01-01

    This article focuses on the accelerated associate degree program at Ivy Tech Community College (Indiana) in which low-income students will receive an associate degree in one year. The three-year pilot program is funded by a $2.3 million grant from the Lumina Foundation for Education in Indianapolis and a $270,000 grant from the Indiana Commission…

  18. ACCELERATION INTEGRATOR

    DOEpatents

    Pope, K.E.

    1958-01-01

    This patent relates to an improved acceleration integrator and more particularly to apparatus of this nature which is gyrostabilized. The device may be used to sense the attainment by an airborne vehicle of a predetermined velocitv or distance along a given vector path. In its broad aspects, the acceleration integrator utilizes a magnetized element rotatable driven by a synchronous motor and having a cylin drical flux gap and a restrained eddy- current drag cap deposed to move into the gap. The angular velocity imparted to the rotatable cap shaft is transmitted in a positive manner to the magnetized element through a servo feedback loop. The resultant angular velocity of tae cap is proportional to the acceleration of the housing in this manner and means may be used to measure the velocity and operate switches at a pre-set magnitude. To make the above-described dcvice sensitive to acceleration in only one direction the magnetized element forms the spinning inertia element of a free gyroscope, and the outer housing functions as a gimbal of a gyroscope.

  19. Particle acceleration

    NASA Technical Reports Server (NTRS)

    Vlahos, L.; Machado, M. E.; Ramaty, R.; Murphy, R. J.; Alissandrakis, C.; Bai, T.; Batchelor, D.; Benz, A. O.; Chupp, E.; Ellison, D.

    1986-01-01

    Data is compiled from Solar Maximum Mission and Hinothori satellites, particle detectors in several satellites, ground based instruments, and balloon flights in order to answer fundamental questions relating to: (1) the requirements for the coronal magnetic field structure in the vicinity of the energization source; (2) the height (above the photosphere) of the energization source; (3) the time of energization; (4) transistion between coronal heating and flares; (5) evidence for purely thermal, purely nonthermal and hybrid type flares; (6) the time characteristics of the energization source; (7) whether every flare accelerates protons; (8) the location of the interaction site of the ions and relativistic electrons; (9) the energy spectra for ions and relativistic electrons; (10) the relationship between particles at the Sun and interplanetary space; (11) evidence for more than one acceleration mechanism; (12) whether there is single mechanism that will accelerate particles to all energies and also heat the plasma; and (13) how fast the existing mechanisms accelerate electrons up to several MeV and ions to 1 GeV.

  20. Plasma Wakefield Acceleration of Positrons

    NASA Astrophysics Data System (ADS)

    Gessner, Spencer

    2016-03-01

    Recent particle beam and laser-driven plasma wakefield experiments have produced high-quality electron beams accelerated by a GeV or more in less than a meter. Efforts are underway to put these beams to work as sources for free-electron lasers. By contrast, little work has been done to demonstrate the tractability of plasma wakefield acceleration (PWFA) of positrons beams. The reasons for this are threefold: 1) positron beams are only useful for high-energy physics experiments, whereas electron beams are also useful as light sources, 2) there is a dearth of positron sources for PWFA experiments, and 3) the dynamics of accelerating positron beams in plasma is fundamentally different than that of electron beams. This talk will focus on the physics of accelerating positrons in plasma and contrast the dynamics of electron and positron beam-driven nonlinear plasma wakes. We describe recent experiments at the FACET test facility at SLAC National Accelerator Laboratory that for the first time demonstrate high-gradient acceleration of a positron beams in plasma. We also discuss an alternative acceleration technique called hollow channel acceleration that aims to symmetrize the dynamics of electron and positron beam-driven wakes.

  1. Vacuum Brazing of Accelerator Components

    NASA Astrophysics Data System (ADS)

    Singh, Rajvir; Pant, K. K.; Lal, Shankar; Yadav, D. P.; Garg, S. R.; Raghuvanshi, V. K.; Mundra, G.

    2012-11-01

    Commonly used materials for accelerator components are those which are vacuum compatible and thermally conductive. Stainless steel, aluminum and copper are common among them. Stainless steel is a poor heat conductor and not very common in use where good thermal conductivity is required. Aluminum and copper and their alloys meet the above requirements and are frequently used for the above purpose. The accelerator components made of aluminum and its alloys using welding process have become a common practice now a days. It is mandatory to use copper and its other grades in RF devices required for accelerators. Beam line and Front End components of the accelerators are fabricated from stainless steel and OFHC copper. Fabrication of components made of copper using welding process is very difficult and in most of the cases it is impossible. Fabrication and joining in such cases is possible using brazing process especially under vacuum and inert gas atmosphere. Several accelerator components have been vacuum brazed for Indus projects at Raja Ramanna Centre for Advanced Technology (RRCAT), Indore using vacuum brazing facility available at RRCAT, Indore. This paper presents details regarding development of the above mentioned high value and strategic components/assemblies. It will include basics required for vacuum brazing, details of vacuum brazing facility, joint design, fixturing of the jobs, selection of filler alloys, optimization of brazing parameters so as to obtain high quality brazed joints, brief description of vacuum brazed accelerator components etc.

  2. 25 MV tandem accelerator at Oak Ridge

    SciTech Connect

    Jones, C.M.

    1980-01-01

    A new heavy-ion accelerator facility is under construction at the Oak Ridge National Laboratory. A brief description of the scope and status of this project is presented with emphasis on the first operational experience with the 25 MV tandem accelerator.

  3. A Survey of Hadron Therapy Accelerator Technologies.

    SciTech Connect

    PEGGS,S.; SATOGATA, T.; FLANZ, J.

    2007-06-25

    Hadron therapy has entered a new age [1]. The number of facilities grows steadily, and 'consumer' interest is high. Some groups are working on new accelerator technology, while others optimize existing designs by reducing capital and operating costs, and improving performance. This paper surveys the current requirements and directions in accelerator technology for hadron therapy.

  4. Accelerator Technology Division progress report, FY 1993

    SciTech Connect

    Schriber, S.O.; Hardekopf, R.A.; Heighway, E.A.

    1993-12-31

    This report discusses the following topics: A Next-Generation Spallation-Neutron Source; Accelerator Performance Demonstration Facility; APEX Free-Electron Laser Project; The Ground Test Accelerator (GTA) Program; Intense Neutron Source for Materials Testing; Linac Physics and Special Projects; Magnetic Optics and Beam Diagnostics; Radio-Frequency Technology; Accelerator Controls and Automation; Very High-Power Microwave Sources and Effects; and GTA Installation, Commissioning, and Operation.

  5. Compact accelerator

    DOEpatents

    Caporaso, George J.; Sampayan, Stephen E.; Kirbie, Hugh C.

    2007-02-06

    A compact linear accelerator having at least one strip-shaped Blumlein module which guides a propagating wavefront between first and second ends and controls the output pulse at the second end. Each Blumlein module has first, second, and third planar conductor strips, with a first dielectric strip between the first and second conductor strips, and a second dielectric strip between the second and third conductor strips. Additionally, the compact linear accelerator includes a high voltage power supply connected to charge the second conductor strip to a high potential, and a switch for switching the high potential in the second conductor strip to at least one of the first and third conductor strips so as to initiate a propagating reverse polarity wavefront(s) in the corresponding dielectric strip(s).

  6. Linear accelerator for tritium production

    SciTech Connect

    Garnett, R.W.; Billen, J.H.; Chan, K.C.; Genzlinger, R.; Gray, E.R.; Nath, S.; Rusnak, B.; Schrage, D.L.; Stovall, J.E.; Takeda, H.; Wood, R.; Wangler, T.P.; Young, L.M.

    1996-06-01

    For many years now, Los Alamos National Laboratory has been working to develop a conceptual design of a facility for accelerator production of tritium (APT). The APT accelerator will produce high energy protons which will bombard a heavy metal target, resulting in the production of large numbers of spallation neutrons. These neutrons will be captured by a low-{ital Z} target to produce tritium. This paper describes the latest design of a room-temperature, 1.0 GeV, 100 mA, cw proton accelerator for tritium production. The potential advantages of using superconducting cavities in the high-energy section of the linac are also discussed and a comparison is made with the baseline room-temperature accelerator. {copyright} {ital 1996 American Institute of Physics.}

  7. BICEP's acceleration

    SciTech Connect

    Contaldi, Carlo R.

    2014-10-01

    The recent Bicep2 [1] detection of, what is claimed to be primordial B-modes, opens up the possibility of constraining not only the energy scale of inflation but also the detailed acceleration history that occurred during inflation. In turn this can be used to determine the shape of the inflaton potential V(φ) for the first time — if a single, scalar inflaton is assumed to be driving the acceleration. We carry out a Monte Carlo exploration of inflationary trajectories given the current data. Using this method we obtain a posterior distribution of possible acceleration profiles ε(N) as a function of e-fold N and derived posterior distributions of the primordial power spectrum P(k) and potential V(φ). We find that the Bicep2 result, in combination with Planck measurements of total intensity Cosmic Microwave Background (CMB) anisotropies, induces a significant feature in the scalar primordial spectrum at scales k∼ 10{sup -3} Mpc {sup -1}. This is in agreement with a previous detection of a suppression in the scalar power [2].

  8. Argonne's new Wakefield Test Facility

    SciTech Connect

    Simpson, J.D.

    1992-07-20

    The first phase of a high current, short bunch length electron beam research facility, the AWA, is near completion at Argonne. At the heart of the facility is a photocathode based electron gun and accelerating sections designed to deliver 20 MeV pulses with up to 100 nC per pulse and with pulse lengths of approximately 15 ps (fw). Using a technique similar to that originated at Argonne's AATF facility, a separate weak probe pulse can be generated and used to diagnose wake effects produced by the intense pulses. Initial planned experiments include studies of plasma wakefields and dielectric wakefield devices, and expect to demonstrate large, useful accelerating gradients (> 100 MeV/m). Later phases of the facility will increase the drive bunch energy to more than 100 MeV to enable acceleration experiments up to the GeV range. Specifications, design details, and commissioning progress are presented.

  9. Accelerator Center: National symbol or white elephant?

    SciTech Connect

    1995-06-02

    This article discusses the possible future of the National Accelerator Center facility in South Africa. This state of the art facility with a 200-megaelectrol-volt proton cyclotron, carries out important nuclear physics research but takes a huge part of South Africa`s total science research budget.

  10. Performance specifications for proton medical facility

    SciTech Connect

    Chu, W.T.; Staples, J.W.; Ludewigt, B.A.; Renner, T.R.; Singh, R.P.; Nyman, M.A.; Collier, J.M.; Daftari, I.K.; Petti, P.L.; Alonso, J.R.; Kubo, H.; Verhey, L.J. |; Castro, J.R. ||

    1993-03-01

    Performance specifications of technical components of a modern proton radiotherapy facility are presented. The technical items specified include: the accelerator; the beam transport system including rotating gantry; the treatment beamline systems including beam scattering, beam scanning, and dosimetric instrumentation; and an integrated treatment and accelerator control system. Also included are treatment ancillary facilities such as diagnostic tools, patient positioning and alignment devices, and treatment planning systems. The facility specified will accommodate beam scanning enabling the three-dimensional conformal therapy deliver .

  11. Inverse Free Electron Laser accelerator

    NASA Astrophysics Data System (ADS)

    Fisher, A.; Gallardo, J.; Vansteenbergen, A.; Sandweiss, J.

    1992-09-01

    The study of the INVERSE FREE ELECTRON LASER, as a potential mode of electron acceleration, is being pursued at Brookhaven National Laboratory. Recent studies have focussed on the development of a low energy, high gradient, multi stage linear accelerator. The elementary ingredients for the IFEL interaction are the 50 MeV Linac e(-) beam and the 10(exp 11) Watt CO2 laser beam of BNL's Accelerator Test Facility (ATF), Center for Accelerator Physics (CAP) and a wiggler. The latter element is designed as a fast excitation unit making use of alternating stacks of Vanadium Permendur (VaP) ferromagnetic laminations, periodically interspersed with conductive, nonmagnetic laminations, which act as eddy current induced field reflectors. Wiggler parameters and field distribution data will be presented for a prototype wiggler in a constant period and in a approximately 1.5 percent/cm tapered period configuration. The CO2 laser beam will be transported through the IFEL interaction region by means of a low loss, dielectric coated, rectangular waveguide. Short waveguide test sections have been constructed and have been tested using a low power CW CO2 laser. Preliminary results of guide attenuation and mode selectivity will be given, together with a discussion of the optical issues for the IFEL accelerator. The IFEL design is supported by the development and use of 1D and 3D simulation programs. The results of simulation computations, including also wiggler errors, for a single module accelerator and for a multi-module accelerator will be presented.

  12. Inverse free electron laser accelerator

    NASA Astrophysics Data System (ADS)

    Fisher, A.; Gallardo, J.; Sandweiss, J.; van Steenbergen, A.

    1992-07-01

    The study of the INVERSE FREE ELECTRON LASER, as a potential mode of electron acceleration, is being pursued at Brookhaven National Laboratory. Recent studies have focussed on the development of a low energy, high gradient, multi stage linear accelerator. The elementary ingredients for the IFEL interaction are the 50 MeV Linac e- beam and the 1011 Watt CO2 laser beam of BNL's Accelerator Test Facility (ATF), Center for Accelerator Physics (CAP), and a wiggler. The latter element is designed as a fast excitation unit making use of alternating stacks of Vanadium Permendur (VaP) ferromagnetic laminations, periodically interspersed with conductive, nonmagnetic laminations, which act as eddy current induced field reflectors. Wiggler parameters and field distribution data will be presented for a prototype wiggler in a constant period and in a ≊1.5%/cm tapered period configuration. The CO2 laser beam will be transported through the IFEL interaction region by means of a low loss, dielectric coated, rectangular waveguide. Short waveguide test sections have been constructed and have been tested using a low power cw CO2 laser. Preliminary results of guide attenuation and mode selectivity will be given, together with a discussion of the optical issues for the IFEL accelerator. The IFEL design is supported by the development and use of 1D and 3D simulation programs. The results of simulation computations, including also wiggler errors, for a single module accelerator and for a multi-module accelerator will be presented.

  13. Advanced concepts for acceleration

    SciTech Connect

    Keefe, D.

    1986-07-01

    Selected examples of advanced accelerator concepts are reviewed. Such plasma accelerators as plasma beat wave accelerator, plasma wake field accelerator, and plasma grating accelerator are discussed particularly as examples of concepts for accelerating relativistic electrons or positrons. Also covered are the pulsed electron-beam, pulsed laser accelerator, inverse Cherenkov accelerator, inverse free-electron laser, switched radial-line accelerators, and two-beam accelerator. Advanced concepts for ion acceleration discussed include the electron ring accelerator, excitation of waves on intense electron beams, and two-wave combinations. (LEW)

  14. TRACKING ACCELERATOR SETTINGS.

    SciTech Connect

    D OTTAVIO,T.; FU, W.; OTTAVIO, D.P.

    2007-10-15

    Recording setting changes within an accelerator facility provides information that can be used to answer questions about when, why, and how changes were made to some accelerator system. This can be very useful during normal operations, but can also aid with security concerns and in detecting unusual software behavior. The Set History System (SHS) is a new client-server system developed at the Collider-Accelerator Department of Brookhaven National Laboratory to provide these capabilities. The SHS has been operational for over two years and currently stores about IOOK settings per day into a commercial database management system. The SHS system consists of a server written in Java, client tools written in both Java and C++, and a web interface for querying the database of setting changes. The design of the SHS focuses on performance, portability, and a minimal impact on database resources. In this paper, we present an overview of the system design along with benchmark results showing the performance and reliability of the SHS over the last year.

  15. Accelerators and the Accelerator Community

    SciTech Connect

    Malamud, Ernest; Sessler, Andrew

    2008-06-01

    In this paper, standing back--looking from afar--and adopting a historical perspective, the field of accelerator science is examined. How it grew, what are the forces that made it what it is, where it is now, and what it is likely to be in the future are the subjects explored. Clearly, a great deal of personal opinion is invoked in this process.

  16. Accelerating deactivation

    SciTech Connect

    FISHBACK, K.M.

    1999-02-01

    In recent years, the focus of the U.S. Department of Energy (DOE) complex has shifted from defense production to facility stabilization, decommissioning, and environmental restoration. This shift from production to cleanup requires a parallel shift from operations-focused management to project-focused management for an efficient facility deactivation. In the operation-focused management organization, activities are planned and executed based on production goals and are typically repetitive and cyclic. In the project-focused management environment, activities are based on a defined scope/end objective, start date, and completion date. Since the workforce used to perform production operations is also usually relied onto perform facility deactivation, it is important to shift from an operations management approach to a project management approach. It is best if the transition is accomplished quickly so the project can move forward and workers don't spend a lot of energy anticipating change. Therefore, it is essential that managers, planners, and other workers understand the key elements associated with planning a deactivation project. This paper describes a planning approach that has been used successfully to plan deactivation projects consistent with the requirements provided in DOE Order 430.1A Life Cycle Asset Management and the companion Deactivation Implementation Guide, G430. 1A-3, while exceeding schedule expectations and reducing costs. Although the planning of a deactivation project closely mirrors the classic project planning for construction projects, there are unique variations associated with facility deactivation. The key elements of planning a deactivation project are discussed relative to scope, schedule, and cost. Management tools such as project metrics and histograms are discussed as desired outputs from the planning process. In addition, lessons learned from planning deactivation projects across the DOE complex are discussed relative to making the

  17. Acceleration Environment of the International Space Station

    NASA Technical Reports Server (NTRS)

    McPherson, Kevin; Kelly, Eric; Keller, Jennifer

    2009-01-01

    Measurement of the microgravity acceleration environment on the International Space Station has been accomplished by two accelerometer systems since 2001. The Microgravity Acceleration Measurement System records the quasi-steady microgravity environment, including the influences of aerodynamic drag, vehicle rotation, and venting effects. Measurement of the vibratory/transient regime, comprised of vehicle, crew, and equipment disturbances, has been accomplished by the Space Acceleration Measurement System-II. Until the arrival of the Columbus Orbital Facility and the Japanese Experiment Module, the location of these sensors, and therefore, the measurement of the microgravity acceleration environment, has been limited to within the United States Laboratory. Japanese Aerospace Exploration Agency has developed a vibratory acceleration measurement system called the Microgravity Measurement Apparatus which will be deployed within the Japanese Experiment Module to make distributed measurements of the Japanese Experiment Module's vibratory acceleration environment. Two Space Acceleration Measurement System sensors from the United States Laboratory will be re-deployed to support vibratory acceleration data measurement within the Columbus Orbital Facility. The additional measurement opportunities resulting from the arrival of these new laboratories allows Principal Investigators with facilities located in these International Space Station research laboratories to obtain microgravity acceleration data in support of their sensitive experiments. The Principal Investigator Microgravity Services project, at NASA Glenn Research Center, in Cleveland, Ohio, has supported acceleration measurement systems and the microgravity scientific community through the processing, characterization, distribution, and archival of the microgravity acceleration data obtained from the International Space Station acceleration measurement systems. This paper summarizes the PIMS capabilities available

  18. The Fair Facility

    NASA Astrophysics Data System (ADS)

    Nilsson, Thomas

    2015-03-01

    The FAIR (Facility for Antiproton and Ion Beams), under construction at the GSI site in Darmstadt, Germany, will be addressing a wealth of outstanding questions within the realm of subatomic, atomic and plasma physics through a combination of novel accelerators, storage rings and innovative experimental setups. The envisaged programme of FAIR yields a breadth that is unprecedented at an accelerator-based infrastructure. A brief review of the FAIR infrastructure and scientific reach is made, together with an update of the status of the construction.

  19. Technology of magnetically driven accelerators

    SciTech Connect

    Birx, D.L.; Hawkins, S.A.; Poor, S.E.; Reginato, L.L.; Rogers, D. Jr.; Smith, M.W.

    1985-03-26

    The marriage of Induction Linac technology with Nonlinear Magnetic Modulators has produced some unique capabilities. It appears possible to produce electron beams with average currents measured in amperes, at gradients exceeding 1 MeV/meter, and with power efficiencies approaching 50%. A 2 MeV, 5 kA electron accelerator has been constructed at the Lawrence Livermore National Laboratory (LLNL) to demonstrate these concepts and to provide a test facility for high brightness sources. The pulse drive for the accelerator is based on state-of-the-art magnetic pulse compressors with very high peak power capability, repetition rates exceeding a kilohertz and excellent reliability. 8 figs., 1 tab.

  20. Technology of magnetically driven accelerators

    SciTech Connect

    Brix, D.L.; Hawkins, S.A.; Poor, S.E.; Reginato, L.L.; Smith, M.W.

    1985-10-01

    The marriage of Induction Linac technology with Nonlinear Magnetic Modulators has produced some unique capabilities. It appears possible to produce electron beams with average currents measured in amperes, at gradients exceeding 1 MeV/meter, and with power efficiencies approaching 50%. A 2 MeV, 5 kA electron accelerator has been constructed at the Lawrence Livermore National Laboratory (LLNL) to demonstrate these concepts and to provide a test facility for high brightness sources. The pulse drive for the accelerator is based on state-of-the-art magnetic pulse compressors with very high peak power capability, repetition rates exceeding a kilohertz and excellent reliability.

  1. Cascaded proton acceleration by collisionless electrostatic shock

    SciTech Connect

    Xu, T. J.; Shen, B. F. E-mail: zhxm@siom.ac.cn; Zhang, X. M. E-mail: zhxm@siom.ac.cn; Yi, L. Q.; Wang, W. P.; Zhang, L. G.; Xu, J. C.; Zhao, X. Y.; Shi, Y.; Liu, C.; Pei, Z. K.

    2015-07-15

    A new scheme for proton acceleration by cascaded collisionless electrostatic shock (CES) is proposed. By irradiating a foil target with a moderate high-intensity laser beam, a stable CES field can be induced, which is employed as the accelerating field for the booster stage of proton acceleration. The mechanism is studied through simulations and theoretical analysis, showing that a 55 MeV seed proton beam can be further accelerated to 265 MeV while keeping a good energy spread. This scheme offers a feasible approach to produce proton beams with energy of hundreds of MeV by existing available high-intensity laser facilities.

  2. Inverse Cerenkov laser acceleration experiment at ATF

    NASA Astrophysics Data System (ADS)

    Wang, X. J.; Pogorelsky, I.; Fernow, R.; Kusche, K. P.; Liu, Y.; Kimura, W. D.; Kim, G. H.; Romea, R. D.; Steinhauer, L. C.

    Inverse Cerenkov laser acceleration was demonstrated using an axicon optical system at the Brookhaven Accelerator Test Facility (ATF). The ATF S-band linac and a high power 10.6 MICROMETERSCO2 laser were used for the experiment. Experimental arrangement and the laser and the electron beams synchronization are discussed. The electrons were accelerated more than 0.7 MeV for a 34 MW CO2 laser power. More than 3.7 MeV acceleration was measured with 0.7 GW CO2 laser power, which is more than 20 times of the previous ICA experiment. The experimental results are compared with computer program TRANSPORT simulations.

  3. Pulse Power Supply for Plasma Dynamic Accelerator

    NASA Astrophysics Data System (ADS)

    Yang, Xuanzong; Liu, Jian; Feng, Chunhua; Wang, Long

    2008-06-01

    A new concept of a coaxial plasma dynamic accelerator with a self-energized magnetic compressor coil to simulate the effects of space debris impact is demonstrated. A brief description is presented about the pulse power supply system including the charging circuit, start switch and current transfer system along with some of the key techniques for this kind of accelerator. Using this accelerator configuration, ceramic beads of 100 fim in diameter were accelerated to a speed as high as 18 km/sec. The facility can be used in a laboratory setting to study impact phenomena on solar array materials, potential structural materials for use in space.

  4. Status and future prospects for United States accelerators and accelerator physics

    SciTech Connect

    Siemann, R.H

    1994-12-01

    The recent performance and future prospects of accelerators in the United States are reviewed. The next decade promises significant improvements and major new facilities. There is uncertainty beyond that because of the SSC cancellation and the new, enhanced importance of international accelerator projects.

  5. Accelerator system and method of accelerating particles

    NASA Technical Reports Server (NTRS)

    Wirz, Richard E. (Inventor)

    2010-01-01

    An accelerator system and method that utilize dust as the primary mass flux for generating thrust are provided. The accelerator system can include an accelerator capable of operating in a self-neutralizing mode and having a discharge chamber and at least one ionizer capable of charging dust particles. The system can also include a dust particle feeder that is capable of introducing the dust particles into the accelerator. By applying a pulsed positive and negative charge voltage to the accelerator, the charged dust particles can be accelerated thereby generating thrust and neutralizing the accelerator system.

  6. Attention's Accelerator.

    PubMed

    Reinhart, Robert M G; McClenahan, Laura J; Woodman, Geoffrey F

    2016-06-01

    How do people get attention to operate at peak efficiency in high-pressure situations? We tested the hypothesis that the general mechanism that allows this is the maintenance of multiple target representations in working and long-term memory. We recorded subjects' event-related potentials (ERPs) indexing the working memory and long-term memory representations used to control attention while performing visual search. We found that subjects used both types of memories to control attention when they performed the visual search task with a large reward at stake, or when they were cued to respond as fast as possible. However, under normal circumstances, one type of target memory was sufficient for slower task performance. The use of multiple types of memory representations appears to provide converging top-down control of attention, allowing people to step on the attentional accelerator in a variety of high-pressure situations. PMID:27056975

  7. The US Muon Accelerator Program

    SciTech Connect

    Torun, Y.; Kirk, H.; Bross, A.; Geer, Steve; Shiltsev, Vladimir; Zisman, M.; /LBL, Berkeley

    2010-05-01

    An accelerator complex that can produce ultra-intense beams of muons presents many opportunities to explore new physics. A facility of this type is unique in that, in a relatively straightforward way, it can present a physics program that can be staged and thus move forward incrementally, addressing exciting new physics at each step. At the request of the US Department of Energy's Office of High Energy Physics, the Neutrino Factory and Muon Collider Collaboration (NFMCC) and the Fermilab Muon Collider Task Force (MCTF) have recently submitted a proposal to create a Muon Accelerator Program that will have, as a primary goal, to deliver a Design Feasibility Study for an energy-frontier Muon Collider by the end of a 7 year R&D program. This paper presents a description of a Muon Collider facility and gives an overview of the proposal.

  8. Proton beam therapy facility

    SciTech Connect

    Not Available

    1984-10-09

    It is proposed to build a regional outpatient medical clinic at the Fermi National Accelerator Laboratory (Fermilab), Batavia, Illinois, to exploit the unique therapeutic characteristics of high energy proton beams. The Fermilab location for a proton therapy facility (PTF) is being chosen for reasons ranging from lower total construction and operating costs and the availability of sophisticated technical support to a location with good access to patients from the Chicago area and from the entire nation. 9 refs., 4 figs., 26 tabs.

  9. Hadron accelerators for radiotherapy

    NASA Astrophysics Data System (ADS)

    Owen, Hywel; MacKay, Ranald; Peach, Ken; Smith, Susan

    2014-04-01

    Over the last twenty years the treatment of cancer with protons and light nuclei such as carbon ions has moved from being the preserve of research laboratories into widespread clinical use. A number of choices now exist for the creation and delivery of these particles, key amongst these being the adoption of pencil beam scanning using a rotating gantry; attention is now being given to what technologies will enable cheaper and more effective treatment in the future. In this article the physics and engineering used in these hadron therapy facilities is presented, and the research areas likely to lead to substantive improvements. The wider use of superconducting magnets is an emerging trend, whilst further ahead novel high-gradient acceleration techniques may enable much smaller treatment systems. Imaging techniques to improve the accuracy of treatment plans must also be developed hand-in-hand with future sources of particles, a notable example of which is proton computed tomography.

  10. Accelerating Spectrum Sharing Technologies

    SciTech Connect

    Juan D. Deaton; Lynda L. Brighton; Rangam Subramanian; Hussein Moradi; Jose Loera

    2013-09-01

    Spectrum sharing potentially holds the promise of solving the emerging spectrum crisis. However, technology innovators face the conundrum of developing spectrum sharing technologies without the ability to experiment and test with real incumbent systems. Interference with operational incumbents can prevent critical services, and the cost of deploying and operating an incumbent system can be prohibitive. Thus, the lack of incumbent systems and frequency authorization for technology incubation and demonstration has stymied spectrum sharing research. To this end, industry, academia, and regulators all require a test facility for validating hypotheses and demonstrating functionality without affecting operational incumbent systems. This article proposes a four-phase program supported by our spectrum accountability architecture. We propose that our comprehensive experimentation and testing approach for technology incubation and demonstration will accelerate the development of spectrum sharing technologies.

  11. Acceleration modules in linear induction accelerators

    NASA Astrophysics Data System (ADS)

    Wang, Shao-Heng; Deng, Jian-Jun

    2014-05-01

    The Linear Induction Accelerator (LIA) is a unique type of accelerator that is capable of accelerating kilo-Ampere charged particle current to tens of MeV energy. The present development of LIA in MHz bursting mode and the successful application into a synchrotron have broadened LIA's usage scope. Although the transformer model is widely used to explain the acceleration mechanism of LIAs, it is not appropriate to consider the induction electric field as the field which accelerates charged particles for many modern LIAs. We have examined the transition of the magnetic cores' functions during the LIA acceleration modules' evolution, distinguished transformer type and transmission line type LIA acceleration modules, and re-considered several related issues based on transmission line type LIA acceleration module. This clarified understanding should help in the further development and design of LIA acceleration modules.

  12. Summary Report of Working Group 1: Laser-Plasma Acceleration

    SciTech Connect

    Geddes, C.G.R.; Clayton, C.; Lu, W.; Thomas, A.G.R.

    2010-06-01

    Advances in and physics of the acceleration of particles using underdense plasma structures driven by lasers were the topics of presentations and discussions in Working Group 1 of the 2010 Advanced Accelerator Concepts Workshop. Such accelerators have demonstrated gradients several orders beyond conventional machines, with quasi-monoenergetic beams at MeV-GeV energies, making them attractive candidates for next generation accelerators. Workshop discussions included advances in control over injection and laser propagation to further improve beam quality and stability, detailed diagnostics and physics models of the acceleration process, radiation generation as a source and diagnostic, and technological tools and upcoming facilities to extend the reach of laser-plasma accelerators.

  13. The deuteron accelerator preliminary design for BISOL

    NASA Astrophysics Data System (ADS)

    Peng, S. X.; Zhu, F.; Wang, Z.; Gao, Y.; Guo, Z. Y.

    2016-06-01

    BISOL, which was named as Beijing_ISOL before (Cui et al., 2013), is the abbreviation of Beijing Isotope-Separation-On-Line neutron beam facility. It is proposed jointly by Peking University (PKU) and China Institute of Atomic Energy (CIAE) for basic science study and application. It is a double driven facility that can be driven by a reactor or a deuteron accelerator. The deuteron driver accelerator should accelerate the deuteron beam up to 40 MeV with maximum beam current of 10 mA. Proton beams up to 33 MeV and He2+ beams up to 81.2 MeV can also be accelerated in this accelerator. The accelerator can be operated on either CW (continuous waveform) or pulsed mode, and the ion energy can be adjusted in a wide range. The accelerator will also allow independent operation of the RIB (Radioactive Ion Beams) system. It will be mainly charged by PKU group. Details of the deuteron accelerator preliminary design for BISOL will be given in this paper.

  14. Progress on plasma accelerators

    SciTech Connect

    Chen, P.

    1986-05-01

    Several plasma accelerator concepts are reviewed, with emphasis on the Plasma Beat Wave Accelerator (PBWA) and the Plasma Wake Field Accelerator (PWFA). Various accelerator physics issues regarding these schemes are discussed, and numerical examples on laboratory scale experiments are given. The efficiency of plasma accelerators is then revealed with suggestions on improvements. Sources that cause emittance growth are discussed briefly.

  15. A New Control Room for SLAC Accelerators

    SciTech Connect

    Erickson, Roger; Guerra, E.; Stanek, M.; Hoover, Z.Van; Warren, J.; /SLAC

    2012-06-04

    We are planning to construct a new control room at SLAC to unify and improve the operation of the LCLS, SPEAR3, and FACET accelerator facilities, and to provide the space and flexibility needed to support the LCLS-II and proposed new test beam facilities. The existing control rooms for the linac and SPEAR3 have been upgraded in various ways over the last decade, but their basic features have remained unchanged. We propose to build a larger modern Accelerator Control Room (ACR) in the new Research Support Building (RSB) which is currently under construction at SLAC. Shifting the center of control for the accelerator facilities entails both technical and administrative challenges. In this paper, we describe the history, concept, and status of this project.

  16. Health Facilities

    MedlinePlus

    Health facilities are places that provide health care. They include hospitals, clinics, outpatient care centers, and specialized care centers, ... psychiatric care centers. When you choose a health facility, you might want to consider How close it ...

  17. A single pass electron accelerator

    NASA Astrophysics Data System (ADS)

    Schuetz, Marlin N.; Vroom, David A.

    1995-02-01

    Higher volumes, increasing competition and the need to improve quality have led us to re-examine the process for irradiation of tubing and wire. Traditionallyin Raychem, product irradiation has involved the use of large multi-purpose facilities that were designed to handle relatively small volumes of a large variety of products as a separate process. Today, with larger volumes of certain products, there is an interest in combining processes to improve quality and reduce cost. We have recently designed and constructed a small, low voltage accelerator system that can be placed in-line with another manufacturing process and can uniformly irradiate a tube or wire product in a single pass. The system is comprised of two conventional accelerator systems having elongated filaments and placed on opposite sides of a linear product path. The ribbon shaped electron beams from these two accelerators are scanned, after acceleration toward the product path, in a conventional manner and 180 degrees out of phase from each other. The two accelerated electron beams then enter a third magnetic field that is synchronous with the scanning magnets and whose oscillating polarity is such that the ribbon beams are converged onto a tubular shaped window close to and around a segment of the product path. Trials with a prototype system have produced tubing having a dose concentricity of better than ± 10 percent on a single pass through the system.

  18. Overview of the IFMIF test facility

    NASA Astrophysics Data System (ADS)

    Möslang, A.; Antonnucci, C.; Daum, E.; Haines, J. R.; Jitsukawa, I.; Noda, K.; Zinkle, S.

    1998-10-01

    During the past few years, a reference design has been developed for the International Fusion Materials Irradiation Facility (IFMIF). According to the mission and specification of the general requirements, this reference design includes relevant machine parameters and conceptual designs for the major device subsystems - Test Facilities, Lithium Target Facilities and Accelerator Facilities. Major engineering efforts have been undertaken to establish a test cell design that follows closely the users requirements of the fusion materials community and allows safe and completely remote controlled handling. After a short description of the facility requirements, concepts for the two independent test cells, various test assemblies, remote handling equipment and hot cell facilities are presented.

  19. FACET: SLAC___s New User Facility

    SciTech Connect

    Clarke, C.I.; Decker, F.-J.; England, R.J.; Erickson, R.A.; Hast, C.; Hogan, M.J.; Li, S.Z.; Litos, M.D.; Nosochkov, Y.; Seeman, J.T.; Sheppard, J.; Wienands, U.; Woodley, M.; Yocky, G.; /SLAC

    2012-05-16

    FACET (Facility for Advanced Accelerator Experimental Tests) is a new User Facility at SLAC National Accelerator Laboratory. The first User Run started in spring 2012 with 20 GeV, 3 nC electron beams. The facility is designed to provide short (20 {micro}m) bunches and small (20 {micro}m wide) spot sizes, producing uniquely high power beams. FACET supports studies from many fields but in particular those of Plasma Wakefield Acceleration and Dielectric Wakefield Acceleration. The creation of drive and witness bunches and shaped bunch profiles is possible with 'Notch' Collimation. FACET is also a source of THz radiation for material studies. Positrons will be available at FACET in future user runs. We present the User Facility and the available tools and opportunities for future experiments.

  20. A new small accelerator for radiocarbon dating

    SciTech Connect

    Suter, M.; Huber, R.; Jacob, S. A. W.; Synal, H.-A.; Schroeder, J. B.

    1999-06-10

    A new small and compact radiocarbon dating facility based on a 500 kV Pelletron accelerator has been built. The novel feature is that it operates with 1{sup +} ions. The interfering molecules are destroyed by collisions in the gas stripper. The results of first test measurements demonstrate that stability, background and transmission are equal to the performance of conventional AMS systems based on larger accelerators.

  1. Accelerator and electrodynamics capability review

    SciTech Connect

    Jones, Kevin W

    2010-01-01

    Los Alamos National Laboratory (LANL) uses capability reviews to assess the science, technology and engineering (STE) quality and institutional integration and to advise Laboratory Management on the current and future health of the STE. Capability reviews address the STE integration that LANL uses to meet mission requirements. The Capability Review Committees serve a dual role of providing assessment of the Laboratory's technical contributions and integration towards its missions and providing advice to Laboratory Management. The assessments and advice are documented in reports prepared by the Capability Review Committees that are delivered to the Director and to the Principal Associate Director for Science, Technology and Engineering (PADSTE). Laboratory Management will use this report for STE assessment and planning. LANL has defined fifteen STE capabilities. Electrodynamics and Accelerators is one of the seven STE capabilities that LANL Management (Director, PADSTE, technical Associate Directors) has identified for review in Fiscal Year (FY) 2010. Accelerators and electrodynamics at LANL comprise a blend of large-scale facilities and innovative small-scale research with a growing focus on national security applications. This review is organized into five topical areas: (1) Free Electron Lasers; (2) Linear Accelerator Science and Technology; (3) Advanced Electromagnetics; (4) Next Generation Accelerator Concepts; and (5) National Security Accelerator Applications. The focus is on innovative technology with an emphasis on applications relevant to Laboratory mission. The role of Laboratory Directed Research and Development (LDRD) in support of accelerators/electrodynamics will be discussed. The review provides an opportunity for interaction with early career staff. Program sponsors and customers will provide their input on the value of the accelerator and electrodynamics capability to the Laboratory mission.

  2. Inverse Free Electron Laser accelerator

    SciTech Connect

    Fisher, A.; Gallardo, J.; van Steenbergen, A.; Sandweiss, J.

    1992-09-01

    The study of the INVERSE FREE ELECTRON LASER, as a potential mode of electron acceleration, is being pursued at Brookhaven National Laboratory. Recent studies have focussed on the development of a low energy, high gradient, multi stage linear accelerator. The elementary ingredients for the IFEL interaction are the 50 MeV Linac e{sup {minus}} beam and the 10{sup 11} Watt CO{sub 2} laser beam of BNL`s Accelerator Test Facility (ATF), Center for Accelerator Physics (CAP) and a wiggler. The latter element is designed as a fast excitation unit making use of alternating stacks of Vanadium Permendur (VaP) ferromagnetic laminations, periodically interspersed with conductive, nonmagnetic laminations, which act as eddy current induced field reflectors. Wiggler parameters and field distribution data will be presented for a prototype wiggler in a constant period and in a {approximately} 1.5 %/cm tapered period configuration. The CO{sub 2} laser beam will be transported through the IFEL interaction region by means of a low loss, dielectric coated, rectangular waveguide. Short waveguide test sections have been constructed and have been tested using a low power cw CO{sub 2} laser. Preliminary results of guide attenuation and mode selectivity will be given, together with a discussion of the optical issues for the IFEL accelerator. The IFEL design is supported by the development and use of 1D and 3D simulation programs. The results of simulation computations, including also wiggler errors, for a single module accelerator and for a multi-module accelerator will be presented.

  3. The ATLAS Facility at Argonne National Laboratory

    SciTech Connect

    1997-07-01

    The Argonne Tandem Linac Accelerator System (ATLAS) is a superconducting low-energy heavy ion accelerator. Its primary purpose is to provide beams for research in nuclear structure physics. This report begins with a brief history of ATLAS and then describes the current design of the facility. Also summarized are the experimental equipment and research programs. It concludes with a proposal for turning ATLAS into a radioactive beam facility.

  4. Technical Design of Hadron Therapy Facilities

    SciTech Connect

    Alonso, J.R.

    1993-08-01

    Radiation therapy with hadron beams now has a 40-year track record at many accelerator laboratories around the world, essentially all of these originally physics-research oriented. The great promise shown for treating cancer has led the medical community to seek dedicated accelerator facilities in a hospital setting, where more rapid progress can be made in clinical research. This paper will discuss accelerator and beam characteristics relevant to hadron therapy, particularly as applied to hospital-based facilities. A survey of currently-operating and planned hadron therapy facilities will be given, with particular emphasis on Lorna Linda (the first dedicated proton facility in a hospital) and HIMAC (the first dedicated heavy-ion medical facility).

  5. Technical design of hadron therapy facilities

    SciTech Connect

    Alonso, J.R.

    1993-08-01

    Radiation therapy with hadron beams now has a 40-year track record at many accelerator laboratories around the world, essentially all of these originally physics-research oriented. The great promise shown for treating cancer has led the medical community to seek dedicated accelerator facilities in a hospital setting, where more rapid progress can be made in clinical research. This paper will discuss accelerator and beam characteristics relevant to hadron therapy, particularly as applied to hospital-based facilities. A survey of currently-operating and planned hadron therapy facilities will be given, with particular emphasis on Loma Linda (the first dedicated proton facility in a hospital) and HIMAC (the first dedicated heavy-ion medical facility).

  6. The Argonne Wakefield Accelerator: Overview and status

    SciTech Connect

    Schoessow, P.; Chojnacki, E.; Gai, W.; Ho, C.; Konecny, R.; Power, J.; Rosing, M.; Simpson, J.

    1993-08-01

    The Argonne Wakefield Accelerator (AWA) is a new facility for advanced accelerator research, with a particular emphasis on studies of high gradient ({approximately}100 MeV/m) wakefield acceleration. A novel high current short pulse L-Band photocathode and preaccelerator will provide 100 nC electron bunches at 20 MeV to be used as a drive beam, while a second high brightness gun will be used to generate a 5 MeV witness beam for wakefield measurements. We will present an overview of the various AWA systems, the status of construction, and initial commissioning results.

  7. Community Petascale Project for Accelerator Science and Simulation: Advancing Computational Science for Future Accelerators and Accelerator Technologies

    SciTech Connect

    Spentzouris, P.; Cary, J.; McInnes, L.C.; Mori, W.; Ng, C.; Ng, E.; Ryne, R.; /LBL, Berkeley

    2011-11-14

    for software development and applications accounts for the natural domain areas (beam dynamics, electromagnetics, and advanced acceleration), and all areas depend on the enabling technologies activities, such as solvers and component technology, to deliver the desired performance and integrated simulation environment. The ComPASS applications focus on computationally challenging problems important for design or performance optimization to all major HEP, NP, and BES accelerator facilities. With the cost and complexity of particle accelerators rising, the use of computation to optimize their designs and find improved operating regimes becomes essential, potentially leading to significant cost savings with modest investment.

  8. Electroweak Physics at Jefferson Lab

    SciTech Connect

    R. D. McKeown

    2012-03-01

    The Continuous Electron Beam Accelerator Facility (CEBAF) at the Thomas Jefferson National Accelerator Facility provides CW electron beams with high intensity, remarkable stability, and a high degree of polarization. These capabilities offer new and unique opportunities to search for novel particles and forces that would require extension of the standard model. CEBAF is presently undergoing an upgrade that includes doubling the energy of the electron beam to 12 GeV and enhancements to the experimental equipment. This upgraded facility will provide increased capability to address new physics beyond the standard model.

  9. Argonne plasma wake-field acceleration experiments

    SciTech Connect

    Rosenzweig, J.B.; Cole, B.; Gai, W.; Konecny, R.; Norem, J.; Schoessow, P.; Simpson, J.

    1989-03-14

    Four years after the initial proposal of the Plasma Wake-field Accelerator (PWFA), it continues to be the object of much investigation, due to the promise of the ultra-high accelerating gradients that can exist in relativistic plasma waves driven in the wake of charged particle beams. These wake-fields are of interest both in the laboratory, for acceleration and focusing of electrons and positrons in future linear colliders, and in nature as a possible cosmic ray acceleration mechanism. The purpose of the present work is to review the recent experimental advances made in PWFA research at Argonne National Laboratory. Some of the topics discussed are: the Argonne Advanced Accelerator Test Facility; linear plasma wake-field theory; measurement of linear plasma wake-fields; review of nonlinear plasma wave theory; and experimental measurement of nonlinear plasma wake-fields. 25 refs., 11 figs.

  10. Holifield Heavy Ion Research Facility: Users handbook

    SciTech Connect

    Auble, R.L.

    1987-01-01

    The primary objective of this handbook is to provide information for those who plan to carry out research programs at the Holifield Heavy Ion Research Facility (HHIRF) at Oak Ridge National Laboratory. The accelerator systems and experimental apparatus available are described. The mechanism for obtaining accelerator time and the responsibilities of those users who are granted accelerator time are described. The names and phone numbers of ORNL personnel to call for information about specific areas are given. (LEW)

  11. Accelerators for Inertial Fusion Energy Production

    NASA Astrophysics Data System (ADS)

    Bangerter, R. O.; Faltens, A.; Seidl, P. A.

    2014-02-01

    Since the 1970s, high energy heavy ion accelerators have been one of the leading options for imploding and igniting targets for inertial fusion energy production. Following the energy crisis of the early 1970s, a number of people in the international accelerator community enthusiastically began working on accelerators for this application. In the last decade, there has also been significant interest in using accelerators to study high energy density physics (HEDP). Nevertheless, research on heavy ion accelerators for fusion has proceeded slowly pending demonstration of target ignition using the National Ignition Facility (NIF), a laser-based facility at Lawrence Livermore National Laboratory. A recent report of the National Research Council recommends expansion of accelerator research in the US if and when the NIF achieves ignition. Fusion target physics and the economics of commercial energy production place constraints on the design of accelerators for fusion applications. From a scientific standpoint, phase space and space charge considerations lead to the most stringent constraints. Meeting these constraints almost certainly requires the use of multiple beams of heavy ions with kinetic energies > 1 GeV. These constraints also favor the use of singly charged ions. This article discusses the constraints for both fusion and HEDP, and explains how they lead to the requirements on beam parameters. RF and induction linacs are currently the leading contenders for fusion applications. We discuss the advantages and disadvantages of both options. We also discuss the principal issues that must yet be resolved.

  12. Laser driven ion accelerator

    DOEpatents

    Tajima, Toshiki

    2006-04-18

    A system and method of accelerating ions in an accelerator to optimize the energy produced by a light source. Several parameters may be controlled in constructing a target used in the accelerator system to adjust performance of the accelerator system. These parameters include the material, thickness, geometry and surface of the target.

  13. Laser driven ion accelerator

    DOEpatents

    Tajima, Toshiki

    2005-06-14

    A system and method of accelerating ions in an accelerator to optimize the energy produced by a light source. Several parameters may be controlled in constructing a target used in the accelerator system to adjust performance of the accelerator system. These parameters include the material, thickness, geometry and surface of the target.

  14. Rare Isotope Accelerator (RIA) Project

    NASA Astrophysics Data System (ADS)

    York, R. C.

    2006-07-01

    The proposed Rare Isotope Accelerator (RIA) Project will provide world-class intensities of radioactive beams created by any of the known production mechanisms. A driver linac will be used to accelerate any stable isotope from protons through uranium to energies of ⩾400 MeV/u and intensities of ⩾100 kW. Lighter elements will be used to produce radioactive ion beams by the isotope separation on line (ISOL) method. Typically heavier elements will be used to produce radioactive ion beams by the particle fragmentation (PF) method. A hybrid method of stopping radioactive ion beams produced by the PF method in a gas cell will also be employed. The RIA project has strong support from the nuclear science community as evidenced by RIA being the highest priority for major new construction in the most recent Nuclear Science Advisory Committee (NSAC) Long Range Plan [2002 NSAC Long-Range Plan: Opportunities in Nuclear Science, A long-range plan for the next decade, April 2002]. In addition, RIA is tied for third position for the near term priorities of the Department of Energy (DoE) 20-year plan [DOE Office of Science, Facilities for the future of science: a twenty-year outlook. http://www.sc.doe.gov/Sub/Facilities_for_future/facilities_future.htm]. The status of the RIA design is presented.

  15. Muon Collider Progress: Accelerators

    SciTech Connect

    Zisman, Michael S.

    2011-09-10

    A muon collider would be a powerful tool for exploring the energy-frontier with leptons, and would complement the studies now under way at the LHC. Such a device would offer several important benefits. Muons, like electrons, are point particles so the full center-of-mass energy is available for particle production. Moreover, on account of their higher mass, muons give rise to very little synchrotron radiation and produce very little beamstrahlung. The first feature permits the use of a circular collider that can make efficient use of the expensive rf system and whose footprint is compatible with an existing laboratory site. The second feature leads to a relatively narrow energy spread at the collision point. Designing an accelerator complex for a muon collider is a challenging task. Firstly, the muons are produced as a tertiary beam, so a high-power proton beam and a target that can withstand it are needed to provide the required luminosity of ~1 × 10{sup 34} cm{sup –2}s{sup –1}. Secondly, the beam is initially produced with a large 6D phase space, which necessitates a scheme for reducing the muon beam emittance (“cooling”). Finally, the muon has a short lifetime so all beam manipulations must be done very rapidly. The Muon Accelerator Program, led by Fermilab and including a number of U.S. national laboratories and universities, has undertaken design and R&D activities aimed toward the eventual construction of a muon collider. Design features of such a facility and the supporting R&D program are described.

  16. University of Virginia Reactor Facility Decommissioning Results

    SciTech Connect

    Ervin, P. F.; Lundberg, L. A.; Benneche, P. E.; Mulder, R. U.; Steva, D. P.

    2003-02-24

    The University of Virginia Reactor Facility started accelerated decommissioning in 2002. The facility consists of two licensed reactors, the CAVALIER and the UVAR. This paper will describe the progress in 2002, remaining efforts and the unique organizational structure of the project team.

  17. Operation of the accelerator

    SciTech Connect

    Pardo, R.C.; Batzka, B.; Billquist, P.J.

    1995-08-01

    Fiscal Year 1994 was the first year of seven-day operation since ATLAS became a national user facility in 1985. ATLAS made the most of the opportunity this year by providing 5200 hours of beam on-target to the research program. A record number of 60 experiments were completed and the {open_quotes}facility reliability{close_quotes} remained near the 90% level. Seven-day operation was made possible with the addition to the staff of two operator positions providing single-operator coverage during the weekend period. The normally scheduled coverage was augmented by an on-call list of system experts who respond to emergencies with phone-in advice and return to the Laboratory when necessary. This staffing approach continues but we rearranged our staffing patterns so that we now have one cryogenics engineer working a shift pattern which includes 8-hour daily coverage during the weekend. ATLAS provided a beam mix to users consisting of 26 different isotopic species, 23% of which were for A>100 in FY 1994. Approximately 60% of the beam time was provided by the Positive Ion Injector, slightly less than the usage rate of FY 1993. Experiments using uranium or lead beams accounted for 16.4% of the total beam time. The ECR ion source and high-voltage platform functioned well throughout the year. A new technique for solid material production in the source was developed which uses a sputtering process wherein the sample of material placed near the plasma chamber wall is biased negatively. Plasma ions are accelerated into the sample and material is sputtered from the surface into the plasma. This technique is now used routinely for many elements. Runs of calcium, germanium, nickel, lead, tellurium, and uranium were carried out with this technique.

  18. VitisGen: accelerating grape cultivar improvement

    Technology Transfer Automated Retrieval System (TEKTRAN)

    VitisGen is a multiple institute collaborative project funded by the USDA SCRI program, with a long term goal to accelerate grape cultivar improvement by using cutting-edge molecular marker technologies, rigorous centralized facilities to characterize traits, and molecular breeding expertise. The ge...

  19. A prototype of a beam steering assistant tool for accelerator operations

    SciTech Connect

    M. Bickley; P. Chevtsov

    2006-10-24

    The CEBAF accelerator provides nuclear physics experiments at Jefferson Lab with high quality electron beams. Three experimental end stations can simultaneously receive the beams with different energies and intensities. For each operational mode, the accelerator setup procedures are complicated and require very careful checking of beam spot sizes and positions on multiple beam viewers. To simplify these procedures and make them reproducible, a beam steering assistant GUI tool has been created. The tool is implemented as a multi-window control screen. The screen has an interactive graphical object window, which is an overlay on top of a digitized live video image from a beam viewer. It allows a user to easily create and edit any graphical objects consisting of text, ellipses, and lines, right above the live beam viewer image and then save them in a file that is called a beam steering template. The template can show, for example, the area within which the beam must always be on the viewer. Later, this template can be loaded in the interactive graphical object window to help accelerator operators steer the beam to the specified area on the viewer.

  20. Capture, acceleration and bunching rf systems for the MEIC booster and storage rings

    SciTech Connect

    Wang, Shaoheng; Guo, Jiquan; Lin, Fanglei; Morozov, Vasiliy; Rimmer, Robert A.; Wang, Haipeng; Zhang, Yuhong

    2015-09-01

    The Medium-energy Electron Ion Collider (MEIC), proposed by Jefferson Lab, consists of a series of accelerators. The electron collider ring accepts electrons from CEBAF at energies from 3 to 12 GeV. Protons and ions are delivered to a booster and captured in a long bunch before being ramped and transferred to the ion collider ring. The ion collider ring accelerates a small number of long ion bunches to colliding energy before they are re-bunched into a high frequency train of very short bunches for colliding. Two sets of low frequency RF systems are needed for the long ion bunch energy ramping in the booster and ion collider ring. Another two sets of high frequency RF cavities are needed for re-bunching in the ion collider ring and compensating synchrotron radiation energy loss in the electron collider ring. The requirements from energy ramping, ion beam bunching, electron beam energy compensation, collective effects, beam loading and feedback capability, RF power capability, etc. are presented. The preliminary designs of these RF systems are presented. Concepts for the baseline cavity and RF station configurations are described, as well as some options that may allow more flexible injection and acceleration schemes.