Sample records for allowable project costs

  1. 14 CFR 152.203 - Allowable project costs.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 14 Aeronautics and Space 3 2014-01-01 2014-01-01 false Allowable project costs. 152.203 Section...) AIRPORTS AIRPORT AID PROGRAM Funding of Approved Projects § 152.203 Allowable project costs. (a) Airport development. To be an allowable project cost, for the purposes of computing the amount of an airport...

  2. 14 CFR 152.203 - Allowable project costs.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 14 Aeronautics and Space 3 2012-01-01 2012-01-01 false Allowable project costs. 152.203 Section...) AIRPORTS AIRPORT AID PROGRAM Funding of Approved Projects § 152.203 Allowable project costs. (a) Airport development. To be an allowable project cost, for the purposes of computing the amount of an airport...

  3. 14 CFR 152.203 - Allowable project costs.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 14 Aeronautics and Space 3 2011-01-01 2011-01-01 false Allowable project costs. 152.203 Section...) AIRPORTS AIRPORT AID PROGRAM Funding of Approved Projects § 152.203 Allowable project costs. (a) Airport development. To be an allowable project cost, for the purposes of computing the amount of an airport...

  4. 14 CFR 152.203 - Allowable project costs.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 14 Aeronautics and Space 3 2013-01-01 2013-01-01 false Allowable project costs. 152.203 Section...) AIRPORTS AIRPORT AID PROGRAM Funding of Approved Projects § 152.203 Allowable project costs. (a) Airport development. To be an allowable project cost, for the purposes of computing the amount of an airport...

  5. 14 CFR 152.203 - Allowable project costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 14 Aeronautics and Space 3 2010-01-01 2010-01-01 false Allowable project costs. 152.203 Section...) AIRPORTS AIRPORT AID PROGRAM Funding of Approved Projects § 152.203 Allowable project costs. (a) Airport development. To be an allowable project cost, for the purposes of computing the amount of an airport...

  6. 40 CFR 35.940-1 - Allowable project costs.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 40 Protection of Environment 1 2014-07-01 2014-07-01 false Allowable project costs. 35.940-1... Allowable project costs. Allowable costs include: (a) Costs of salaries, benefits, and expendable material the grantee incurs for the project, except as provided in § 35.940-2(g); (b) Costs under construction...

  7. 40 CFR 35.940-1 - Allowable project costs.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 40 Protection of Environment 1 2012-07-01 2012-07-01 false Allowable project costs. 35.940-1... Allowable project costs. Allowable costs include: (a) Costs of salaries, benefits, and expendable material the grantee incurs for the project, except as provided in § 35.940-2(g); (b) Costs under construction...

  8. 40 CFR 35.940-1 - Allowable project costs.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 40 Protection of Environment 1 2011-07-01 2011-07-01 false Allowable project costs. 35.940-1... Allowable project costs. Allowable costs include: (a) Costs of salaries, benefits, and expendable material the grantee incurs for the project, except as provided in § 35.940-2(g); (b) Costs under construction...

  9. 40 CFR 35.940-1 - Allowable project costs.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 40 Protection of Environment 1 2013-07-01 2013-07-01 false Allowable project costs. 35.940-1... Allowable project costs. Allowable costs include: (a) Costs of salaries, benefits, and expendable material the grantee incurs for the project, except as provided in § 35.940-2(g); (b) Costs under construction...

  10. 40 CFR 35.940-1 - Allowable project costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 1 2010-07-01 2010-07-01 false Allowable project costs. 35.940-1... Allowable project costs. Allowable costs include: (a) Costs of salaries, benefits, and expendable material the grantee incurs for the project, except as provided in § 35.940-2(g); (b) Costs under construction...

  11. 14 CFR 156.5 - Project cost allowability.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 14 Aeronautics and Space 3 2013-01-01 2013-01-01 false Project cost allowability. 156.5 Section...) AIRPORTS STATE BLOCK GRANT PILOT PROGRAM § 156.5 Project cost allowability. (a) A participating State shall not use State block grant funds for reimbursement of project costs that would not be eligible for...

  12. 14 CFR 156.5 - Project cost allowability.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 14 Aeronautics and Space 3 2014-01-01 2014-01-01 false Project cost allowability. 156.5 Section...) AIRPORTS STATE BLOCK GRANT PILOT PROGRAM § 156.5 Project cost allowability. (a) A participating State shall not use State block grant funds for reimbursement of project costs that would not be eligible for...

  13. 14 CFR 156.5 - Project cost allowability.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 14 Aeronautics and Space 3 2012-01-01 2012-01-01 false Project cost allowability. 156.5 Section...) AIRPORTS STATE BLOCK GRANT PILOT PROGRAM § 156.5 Project cost allowability. (a) A participating State shall not use State block grant funds for reimbursement of project costs that would not be eligible for...

  14. 14 CFR 156.5 - Project cost allowability.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 14 Aeronautics and Space 3 2010-01-01 2010-01-01 false Project cost allowability. 156.5 Section...) AIRPORTS STATE BLOCK GRANT PILOT PROGRAM § 156.5 Project cost allowability. (a) A participating State shall not use State block grant funds for reimbursement of project costs that would not be eligible for...

  15. 14 CFR 156.5 - Project cost allowability.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 14 Aeronautics and Space 3 2011-01-01 2011-01-01 false Project cost allowability. 156.5 Section...) AIRPORTS STATE BLOCK GRANT PILOT PROGRAM § 156.5 Project cost allowability. (a) A participating State shall not use State block grant funds for reimbursement of project costs that would not be eligible for...

  16. 40 CFR 35.2205 - Maximum allowable project cost.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 40 Protection of Environment 1 2011-07-01 2011-07-01 false Maximum allowable project cost. 35.2205... project cost. (a) Grants awarded on or after the effective date of this regulation. Except as provided in... regulation, the maximum allowable project cost will be the sum of: (1) The allowable cost of the following...

  17. 40 CFR 35.2205 - Maximum allowable project cost.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 40 Protection of Environment 1 2013-07-01 2013-07-01 false Maximum allowable project cost. 35.2205... project cost. (a) Grants awarded on or after the effective date of this regulation. Except as provided in... regulation, the maximum allowable project cost will be the sum of: (1) The allowable cost of the following...

  18. 40 CFR 35.2205 - Maximum allowable project cost.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 40 Protection of Environment 1 2012-07-01 2012-07-01 false Maximum allowable project cost. 35.2205... project cost. (a) Grants awarded on or after the effective date of this regulation. Except as provided in... regulation, the maximum allowable project cost will be the sum of: (1) The allowable cost of the following...

  19. 40 CFR 35.2205 - Maximum allowable project cost.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 40 Protection of Environment 1 2014-07-01 2014-07-01 false Maximum allowable project cost. 35.2205... project cost. (a) Grants awarded on or after the effective date of this regulation. Except as provided in... regulation, the maximum allowable project cost will be the sum of: (1) The allowable cost of the following...

  20. 40 CFR 35.2205 - Maximum allowable project cost.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 1 2010-07-01 2010-07-01 false Maximum allowable project cost. 35.2205... ASSISTANCE STATE AND LOCAL ASSISTANCE Grants for Construction of Treatment Works § 35.2205 Maximum allowable... regulation, the maximum allowable project cost will be the sum of: (1) The allowable cost of the following...

  1. 34 CFR 647.30 - What are allowable costs?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 34 Education 3 2011-07-01 2011-07-01 false What are allowable costs? 647.30 Section 647.30... EDUCATION, DEPARTMENT OF EDUCATION RONALD E. MCNAIR POSTBACCALAUREATE ACHIEVEMENT PROGRAM What Conditions Must Be Met by a Grantee? § 647.30 What are allowable costs? Allowable project costs, not specifically...

  2. 34 CFR 642.30 - What are allowable costs?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 34 Education 3 2011-07-01 2011-07-01 false What are allowable costs? 642.30 Section 642.30... EDUCATION, DEPARTMENT OF EDUCATION TRAINING PROGRAM FOR FEDERAL TRIO PROGRAMS What Conditions Must Be Met by a Grantee? § 642.30 What are allowable costs? Allowable project costs may include the following...

  3. 34 CFR 379.41 - What are allowable costs?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 34 Education 2 2012-07-01 2012-07-01 false What are allowable costs? 379.41 Section 379.41... AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION PROJECTS WITH INDUSTRY What Conditions Must Be Met by a Grantee? § 379.41 What are allowable costs? In addition to those costs that are allowable in...

  4. 34 CFR 379.41 - What are allowable costs?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 34 Education 2 2013-07-01 2013-07-01 false What are allowable costs? 379.41 Section 379.41... AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION PROJECTS WITH INDUSTRY What Conditions Must Be Met by a Grantee? § 379.41 What are allowable costs? In addition to those costs that are allowable in...

  5. 36 CFR 230.6 - Project costs and cost share requirements.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 36 Parks, Forests, and Public Property 2 2013-07-01 2013-07-01 false Project costs and cost share... Project costs and cost share requirements. (a) The CFP Federal contribution cannot exceed 50 percent of the total project costs. (b) Allowable project and cost share costs will include the purchase price...

  6. 36 CFR 230.6 - Project costs and cost share requirements.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 36 Parks, Forests, and Public Property 2 2014-07-01 2014-07-01 false Project costs and cost share... Project costs and cost share requirements. (a) The CFP Federal contribution cannot exceed 50 percent of the total project costs. (b) Allowable project and cost share costs will include the purchase price...

  7. 36 CFR 230.6 - Project costs and cost share requirements.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 36 Parks, Forests, and Public Property 2 2012-07-01 2012-07-01 false Project costs and cost share... Project costs and cost share requirements. (a) The CFP Federal contribution cannot exceed 50 percent of the total project costs. (b) Allowable project and cost share costs will include the purchase price...

  8. 34 CFR 390.41 - What are allowable costs?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION REHABILITATION SHORT-TERM TRAINING What... costs established in EDGAR §§ 75.530-75.562, the following items are allowable under short-term training projects: (1) Trainee per diem costs; (2) Trainee travel in connection with a training course; (3) Trainee...

  9. 34 CFR 390.41 - What are allowable costs?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION REHABILITATION SHORT-TERM TRAINING What... costs established in EDGAR §§ 75.530-75.562, the following items are allowable under short-term training projects: (1) Trainee per diem costs; (2) Trainee travel in connection with a training course; (3) Trainee...

  10. 34 CFR 390.41 - What are allowable costs?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION REHABILITATION SHORT-TERM TRAINING What... costs established in EDGAR §§ 75.530-75.562, the following items are allowable under short-term training projects: (1) Trainee per diem costs; (2) Trainee travel in connection with a training course; (3) Trainee...

  11. Overseas Cost of Living Allowances (COLA)

    Science.gov Websites

    ) Government Meal Rate Meal Tickets Mileage Rates Overseas Cost of Living Allowances (COLA) Calculation of Reporting Procedures Station Allowance Changes Programs & Services > Allowances > Overseas Cost of Allowances Submit Questions Overseas Cost of Living Allowances (COLA) The Overseas Cost of Living Allowance

  12. 34 CFR 371.41 - What are allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 34 Education 2 2010-07-01 2010-07-01 false What are allowable costs? 371.41 Section 371.41 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF SPECIAL EDUCATION AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION VOCATIONAL REHABILITATION SERVICE PROJECTS FOR...

  13. 49 CFR 266.11 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... TRANSPORTATION ACT § 266.11 Allowable costs. Allowable costs include only the following costs which are properly allocable to the work performed: Planning and program operation costs which are allowed under Federal... 49 Transportation 4 2010-10-01 2010-10-01 false Allowable costs. 266.11 Section 266.11...

  14. 34 CFR 379.41 - What are allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 34 Education 2 2010-07-01 2010-07-01 false What are allowable costs? 379.41 Section 379.41 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF SPECIAL EDUCATION AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION PROJECTS WITH INDUSTRY What Conditions Must Be...

  15. 29 CFR 95.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... cost principles applicable to the entity incurring the costs. Thus, allowability of costs incurred by... Governments.” The allowability of costs incurred by non-profit organizations is determined in accordance with... Organizations.” The allowability of costs incurred by institutions of higher education is determined in...

  16. 24 CFR 84.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... to the entity incurring the costs. Thus, allowability of costs incurred by State, local or federally..., “Cost Principles for State and Local Governments.” The allowability of costs incurred by non-profit...-Profit Organizations.” The allowability of costs incurred by institutions of higher education is...

  17. 7 CFR 550.25 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... cost principles applicable to the entity incurring the costs. Thus, allowability of costs incurred by... at 2 CFR part 225. The allowability of costs incurred by non-profit organizations is determined in... at 2 CFR part 230. The allowability of costs incurred by institutions of higher education is...

  18. 7 CFR 3019.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... applicable to the entity incurring the costs. Thus, allowability of costs incurred by State, local or... Circular A-87, “Cost Principles for State and Local Governments.” The allowability of costs incurred by non... Principles for Non-Profit Organizations.” The allowability of costs incurred by institutions of higher...

  19. 49 CFR 19.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... applicable to the entity incurring the costs. Thus, allowability of costs incurred by State, local or... Circular A-87, “Cost Principles for State and Local Governments.” The allowability of costs incurred by non... Principles for Non-Profit Organizations.” The allowability of costs incurred by institutions of higher...

  20. 36 CFR 1210.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... applicable to the entity incurring the costs. Thus, allowability of costs incurred by State, local or... Circular A-87, “Cost Principles for State and Local Governments.” The allowability of costs incurred by non... Principles for Non-Profit Organizations.” The allowability of costs incurred by institutions of higher...

  1. 34 CFR 675.33 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... costs. An institution's share of allowable costs may be in cash or in the form of services. The... 34 Education 3 2010-07-01 2010-07-01 false Allowable costs. 675.33 Section 675.33 Education... costs. (a)(1) Allowable and unallowable costs. Except as provided in paragraph (a)(2) of this section...

  2. 42 CFR 417.534 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 42 Public Health 3 2010-10-01 2010-10-01 false Allowable costs. 417.534 Section 417.534 Public... coverage to enrollees under Part D, no costs related to the offering or provision of Part D benefits are... PLANS Medicare Payment: Cost Basis § 417.534 Allowable costs. (a) Definition—Allowable costs means the...

  3. 14 CFR 1260.127 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... incurring the costs. Thus, allowability of costs incurred by State, local or federally-recognized Indian... for State and Local Governments.” The allowability of costs incurred by non-profit organizations is... Organizations.” The allowability of costs incurred by institutions of higher education is determined in...

  4. 44 CFR 206.439 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 44 Emergency Management and Assistance 1 2010-10-01 2010-10-01 false Allowable costs. 206.439... Allowable costs. (a) General requirements for determining allowable costs are established in 44 CFR 13.22... section. (b) Administrative and management costs for major disasters will be paid in accordance with 44...

  5. 24 CFR 85.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... uniform cost accounting standards that comply with cost principles acceptable to the Federal agency. ... TRIBAL GOVERNMENTS Post-Award Requirements Financial Administration § 85.22 Allowable costs. (a... increment above allowable costs) to the grantee or subgrantee. (b) Applicable cost principles. For each kind...

  6. 36 CFR 1207.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... uniform cost accounting standards that comply with cost principles acceptable to the Federal agency. ... GOVERNMENTS Post-Award Requirements Financial Administration § 1207.22 Allowable costs. (a) Limitation on use... increment above allowable costs) to the grantee or subgrantee. (b) Applicable cost principles. For each kind...

  7. 44 CFR 13.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... uniform cost accounting standards that comply with cost principles acceptable to the Federal agency. ... STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial Administration § 13.22 Allowable costs. (a... increment above allowable costs) to the grantee or subgrantee. (b) Applicable cost principles. For each kind...

  8. 34 CFR 74.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... Procedures or uniform cost accounting standards that comply with cost principles acceptable to ED. (b) The... OF HIGHER EDUCATION, HOSPITALS, AND OTHER NON-PROFIT ORGANIZATIONS Post-Award Requirements Financial... principles for determining allowable costs. Allowability of costs are determined in accordance with the cost...

  9. 10 CFR 600.317 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... Allowable costs. (a) DOE determines allowability of costs in accordance with the cost principles applicable... OMB Circular A-122 is determined in accordance with the for-profit costs principles in 48 CFR part 31... accordance with OMB Circular A-21, “Cost Principles for Educational Institutions.” (ii) Other nonprofit...

  10. 42 CFR 405.2468 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 42 Public Health 2 2010-10-01 2010-10-01 false Allowable costs. 405.2468 Section 405.2468 Public... Allowable costs. (a) Applicability of general Medicare principles. In determining whether and to what extent a specific type or item of cost is allowable, such as interest, depreciation, bad debts and owner...

  11. 32 CFR 33.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... accounting standards that comply with cost principles acceptable to the Federal agency. ... Post-Award Requirements Financial Administration § 33.22 Allowable costs. (a) Limitation on use of... allowable costs) to the grantee or subgrantee. (b) Applicable cost principles. For each kind of organization...

  12. 45 CFR 2541.220 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... accounting standards that comply with cost principles acceptable to the Federal agency. ... the grantee or subgrantee. (b) Applicable cost principles. For each kind of organization, there is a set of Federal principles for determining allowable costs. Allowable costs will be determined in...

  13. 29 CFR 97.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... accounting standards that comply with cost principles acceptable to the Federal agency. [53 FR 8069, 8087... LOCAL GOVERNMENTS Post-Award Requirements Financial Administration § 97.22 Allowable costs. (a... increment above allowable costs) to the grantee or subgrantee. (b) Applicable cost principles. For each kind...

  14. 2 CFR 215.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... applicable to the entity incurring the costs. Thus, allowability of costs incurred by State, local or... allowability of costs incurred by non-profit organizations is determined in accordance with the provisions of 2... costs incurred by institutions of higher education is determined in accordance with the provisions of 2...

  15. 40 CFR 35.936-20 - Allowable costs.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... engineering services are allowable, even when conducted before award of the grant. Legal and engineering costs... 40 Protection of Environment 1 2012-07-01 2012-07-01 false Allowable costs. 35.936-20 Section 35... Allowable costs. (a) Incurring costs under subagreements which are not awarded or administered in compliance...

  16. 34 CFR 608.40 - What are allowable costs and what are the limitations on allowable costs?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 34 Education 3 2012-07-01 2012-07-01 false What are allowable costs and what are the limitations on allowable costs? 608.40 Section 608.40 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION STRENGTHENING HISTORICALLY...

  17. 34 CFR 608.40 - What are allowable costs and what are the limitations on allowable costs?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 34 Education 3 2014-07-01 2014-07-01 false What are allowable costs and what are the limitations on allowable costs? 608.40 Section 608.40 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION STRENGTHENING HISTORICALLY...

  18. 34 CFR 607.30 - What are allowable costs and what are the limitations on allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 34 Education 3 2010-07-01 2010-07-01 false What are allowable costs and what are the limitations on allowable costs? 607.30 Section 607.30 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION STRENGTHENING INSTITUTIONS...

  19. 34 CFR 608.40 - What are allowable costs and what are the limitations on allowable costs?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 34 Education 3 2011-07-01 2011-07-01 false What are allowable costs and what are the limitations on allowable costs? 608.40 Section 608.40 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION STRENGTHENING HISTORICALLY...

  20. 34 CFR 607.30 - What are allowable costs and what are the limitations on allowable costs?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 34 Education 3 2013-07-01 2013-07-01 false What are allowable costs and what are the limitations on allowable costs? 607.30 Section 607.30 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION STRENGTHENING INSTITUTIONS...

  1. 34 CFR 609.41 - What are allowable costs and what are the limitations on allowable costs?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 34 Education 3 2012-07-01 2012-07-01 false What are allowable costs and what are the limitations on allowable costs? 609.41 Section 609.41 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION STRENGTHENING HISTORICALLY...

  2. 34 CFR 607.30 - What are allowable costs and what are the limitations on allowable costs?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 34 Education 3 2014-07-01 2014-07-01 false What are allowable costs and what are the limitations on allowable costs? 607.30 Section 607.30 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION STRENGTHENING INSTITUTIONS...

  3. 34 CFR 609.41 - What are allowable costs and what are the limitations on allowable costs?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 34 Education 3 2011-07-01 2011-07-01 false What are allowable costs and what are the limitations on allowable costs? 609.41 Section 609.41 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION STRENGTHENING HISTORICALLY...

  4. 34 CFR 607.30 - What are allowable costs and what are the limitations on allowable costs?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 34 Education 3 2012-07-01 2012-07-01 false What are allowable costs and what are the limitations on allowable costs? 607.30 Section 607.30 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION STRENGTHENING INSTITUTIONS...

  5. 34 CFR 609.41 - What are allowable costs and what are the limitations on allowable costs?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 34 Education 3 2014-07-01 2014-07-01 false What are allowable costs and what are the limitations on allowable costs? 609.41 Section 609.41 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION STRENGTHENING HISTORICALLY...

  6. 34 CFR 609.41 - What are allowable costs and what are the limitations on allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 34 Education 3 2010-07-01 2010-07-01 false What are allowable costs and what are the limitations on allowable costs? 609.41 Section 609.41 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION STRENGTHENING HISTORICALLY...

  7. 34 CFR 608.40 - What are allowable costs and what are the limitations on allowable costs?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 34 Education 3 2013-07-01 2013-07-01 false What are allowable costs and what are the limitations on allowable costs? 608.40 Section 608.40 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION STRENGTHENING HISTORICALLY...

  8. 34 CFR 607.30 - What are allowable costs and what are the limitations on allowable costs?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 34 Education 3 2011-07-01 2011-07-01 false What are allowable costs and what are the limitations on allowable costs? 607.30 Section 607.30 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION STRENGTHENING INSTITUTIONS...

  9. 34 CFR 609.41 - What are allowable costs and what are the limitations on allowable costs?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 34 Education 3 2013-07-01 2013-07-01 false What are allowable costs and what are the limitations on allowable costs? 609.41 Section 609.41 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION STRENGTHENING HISTORICALLY...

  10. 14 CFR 151.43 - United States share of project costs.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 14 Aeronautics and Space 3 2012-01-01 2012-01-01 false United States share of project costs. 151... United States share of project costs. (a) The United States share of the allowable costs of a project is... part, the United States share of the costs of an approved project for airport development (regardless...

  11. 14 CFR 151.43 - United States share of project costs.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 14 Aeronautics and Space 3 2013-01-01 2013-01-01 false United States share of project costs. 151... United States share of project costs. (a) The United States share of the allowable costs of a project is... part, the United States share of the costs of an approved project for airport development (regardless...

  12. 14 CFR 151.43 - United States share of project costs.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 14 Aeronautics and Space 3 2011-01-01 2011-01-01 false United States share of project costs. 151... United States share of project costs. (a) The United States share of the allowable costs of a project is... part, the United States share of the costs of an approved project for airport development (regardless...

  13. 14 CFR 151.43 - United States share of project costs.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 14 Aeronautics and Space 3 2014-01-01 2014-01-01 false United States share of project costs. 151... United States share of project costs. (a) The United States share of the allowable costs of a project is... part, the United States share of the costs of an approved project for airport development (regardless...

  14. 14 CFR 151.43 - United States share of project costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 14 Aeronautics and Space 3 2010-01-01 2010-01-01 false United States share of project costs. 151... United States share of project costs. (a) The United States share of the allowable costs of a project is... part, the United States share of the costs of an approved project for airport development (regardless...

  15. 41 CFR 105-71.122 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... uniform cost accounting standards that comply with cost principles acceptable to the Federal agency. ... GOVERNMENTS 71.12-Post-Award Requirements/Financial Administration § 105-71.122 Allowable costs. (a... increment above allowable costs) to the grantee or subgrantee. (b) Applicable cost principles. For each kind...

  16. 20 CFR 633.303 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... Employees' Benefits EMPLOYMENT AND TRAINING ADMINISTRATION, DEPARTMENT OF LABOR MIGRANT AND SEASONAL FARMWORKER PROGRAMS Program Design and Administrative Procedures § 633.303 Allowable costs. (a) General. To be allowable, a cost must be necessary and reasonable for proper and efficient administration of the...

  17. 20 CFR 632.37 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... Employees' Benefits EMPLOYMENT AND TRAINING ADMINISTRATION, DEPARTMENT OF LABOR INDIAN AND NATIVE AMERICAN EMPLOYMENT AND TRAINING PROGRAMS Administrative Standards and Procedures § 632.37 Allowable costs. (a) General. To be allowable, a cost must be necessary and reasonable for proper and efficient administration...

  18. 45 CFR 2543.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... GRANTS AND AGREEMENTS WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, AND OTHER NON-PROFIT ORGANIZATIONS Post-Award Requirements Financial and Program Management § 2543.27 Allowable costs. For each kind... Organizations.” The allowability of costs incurred by institutions of higher education is determined in...

  19. 42 CFR 405.2468 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... to the limit on the all-inclusive rate for allowable costs. (3) Allowable graduate medical education.... (f) Graduate medical education. (1) Effective for that portion of cost reporting periods occurring on... receive direct graduate medical education payment for those residents. (2) Direct graduate medical...

  20. 43 CFR 12.62 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... uniform cost accounting standards that comply with cost principles acceptable to the Federal agency. ... COST PRINCIPLES FOR ASSISTANCE PROGRAMS Uniform Administrative Requirements for Grants and Cooperative... increment above allowable costs) to the grantee or subgrantee. (b) Applicable cost principles. For each kind...

  1. 22 CFR 135.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... Procedures, or uniform cost accounting standards that comply with cost principles acceptable to the Federal... AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial Administration § 135.22 Allowable... principles. For each kind of organization, there is a set of Federal principles for determining allowable...

  2. 15 CFR 14.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... GRANTS AND AGREEMENTS WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, OTHER NON-PROFIT, AND COMMERCIAL ORGANIZATIONS Post-Award Requirements Financial and Program Management § 14.27 Allowable costs. For each kind of... Organizations.” The allowability of costs incurred by institutions of higher education is determined in...

  3. 14 CFR 152.205 - United States share of project costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 14 Aeronautics and Space 3 2010-01-01 2010-01-01 false United States share of project costs. 152... share of project costs. (a) Airport development. Except as provided in paragraphs (b) and (c) of this section, the following is the United States share of the allowable cost of an airport development project...

  4. 14 CFR 152.205 - United States share of project costs.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 14 Aeronautics and Space 3 2011-01-01 2011-01-01 false United States share of project costs. 152... share of project costs. (a) Airport development. Except as provided in paragraphs (b) and (c) of this section, the following is the United States share of the allowable cost of an airport development project...

  5. 14 CFR 152.205 - United States share of project costs.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 14 Aeronautics and Space 3 2012-01-01 2012-01-01 false United States share of project costs. 152... share of project costs. (a) Airport development. Except as provided in paragraphs (b) and (c) of this section, the following is the United States share of the allowable cost of an airport development project...

  6. 14 CFR 152.205 - United States share of project costs.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 14 Aeronautics and Space 3 2013-01-01 2013-01-01 false United States share of project costs. 152... share of project costs. (a) Airport development. Except as provided in paragraphs (b) and (c) of this section, the following is the United States share of the allowable cost of an airport development project...

  7. 14 CFR 152.205 - United States share of project costs.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 14 Aeronautics and Space 3 2014-01-01 2014-01-01 false United States share of project costs. 152... share of project costs. (a) Airport development. Except as provided in paragraphs (b) and (c) of this section, the following is the United States share of the allowable cost of an airport development project...

  8. 29 CFR 1470.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... to that circular 48 CFR part 31. Contract Cost Principles and Procedures, or uniform cost accounting... Financial Administration § 1470.22 Allowable costs. (a) Limitation on use of funds. Grant funds may be used... grantee or subgrantee. (b) Applicable cost principles. For each kind of organization, there is a set of...

  9. 45 CFR 92.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... to that circular 48 CFR Part 31. Contract Cost Principles and Procedures, or uniform cost accounting... Financial Administration § 92.22 Allowable costs. (a) Limitation on use of funds. Grant funds may be used... grantee or subgrantee. (b) Applicable cost principles. For each kind of organization, there is a set of...

  10. 13 CFR 143.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... to that circular 48 CFR part 31. Contract Cost Principles and Procedures, or uniform cost accounting... Financial Administration § 143.22 Allowable costs. (a) Limitation on use of funds. Grant funds may be used... grantee or subgrantee. (b) Applicable cost principles. For each kind of organization, there is a set of...

  11. 20 CFR 631.84 - Allowable projects.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 20 Employees' Benefits 3 2010-04-01 2010-04-01 false Allowable projects. 631.84 Section 631.84... THE JOB TRAINING PARTNERSHIP ACT Disaster Relief Employment Assistance § 631.84 Allowable projects...) Shall be used exclusively to provide employment on projects that provide food, clothing, shelter and...

  12. 20 CFR 631.84 - Allowable projects.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 20 Employees' Benefits 3 2011-04-01 2011-04-01 false Allowable projects. 631.84 Section 631.84... THE JOB TRAINING PARTNERSHIP ACT Disaster Relief Employment Assistance § 631.84 Allowable projects...) Shall be used exclusively to provide employment on projects that provide food, clothing, shelter and...

  13. 20 CFR 631.84 - Allowable projects.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 20 Employees' Benefits 3 2012-04-01 2012-04-01 false Allowable projects. 631.84 Section 631.84... THE JOB TRAINING PARTNERSHIP ACT Disaster Relief Employment Assistance § 631.84 Allowable projects...) Shall be used exclusively to provide employment on projects that provide food, clothing, shelter and...

  14. 24 CFR 242.28 - Allowable costs for consultants.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 24 Housing and Urban Development 2 2011-04-01 2011-04-01 false Allowable costs for consultants... AUTHORITIES MORTGAGE INSURANCE FOR HOSPITALS Mortgage Requirements § 242.28 Allowable costs for consultants.... Allowable consulting fees include those for analysis of market demand, expected revenues, and costs; site...

  15. 24 CFR 242.28 - Allowable costs for consultants.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 24 Housing and Urban Development 2 2014-04-01 2014-04-01 false Allowable costs for consultants... AUTHORITIES MORTGAGE INSURANCE FOR HOSPITALS Mortgage Requirements § 242.28 Allowable costs for consultants.... Allowable consulting fees include those for analysis of market demand, expected revenues, and costs; site...

  16. 24 CFR 242.28 - Allowable costs for consultants.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 24 Housing and Urban Development 2 2010-04-01 2010-04-01 false Allowable costs for consultants... AUTHORITIES MORTGAGE INSURANCE FOR HOSPITALS Mortgage Requirements § 242.28 Allowable costs for consultants.... Allowable consulting fees include those for analysis of market demand, expected revenues, and costs; site...

  17. 50 CFR 85.41 - Allowable costs.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    .... Preliminary costs may include such items as feasibility surveys, engineering design, biological reconnaissance... symbols designating pumpout and dump stations, are allowable costs. (b) Grants or facilities designed to...

  18. 50 CFR 85.41 - Allowable costs.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    .... Preliminary costs may include such items as feasibility surveys, engineering design, biological reconnaissance... symbols designating pumpout and dump stations, are allowable costs. (b) Grants or facilities designed to...

  19. 50 CFR 85.41 - Allowable costs.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    .... Preliminary costs may include such items as feasibility surveys, engineering design, biological reconnaissance... symbols designating pumpout and dump stations, are allowable costs. (b) Grants or facilities designed to...

  20. 50 CFR 85.41 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    .... Preliminary costs may include such items as feasibility surveys, engineering design, biological reconnaissance... symbols designating pumpout and dump stations, are allowable costs. (b) Grants or facilities designed to...

  1. 50 CFR 85.41 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    .... Preliminary costs may include such items as feasibility surveys, engineering design, biological reconnaissance... symbols designating pumpout and dump stations, are allowable costs. (b) Grants or facilities designed to...

  2. 38 CFR 43.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... accounting standards that comply with cost principles acceptable to the Federal agency. ... Requirements Financial Administration § 43.22 Allowable costs. (a) Limitation on use of funds. Grant funds may... the grantee or subgrantee. (b) Applicable cost principles. For each kind of organization, there is a...

  3. 7 CFR 3016.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... uniform cost accounting standards that comply with cost principles acceptable to the Federal agency. ... Regulations of the Department of Agriculture (Continued) OFFICE OF THE CHIEF FINANCIAL OFFICER, DEPARTMENT OF... GOVERNMENTS Post-Award Requirements Financial Administration § 3016.22 Allowable costs. (a) Limitation on use...

  4. 34 CFR 389.41 - What are allowable costs?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 34 Education 2 2012-07-01 2012-07-01 false What are allowable costs? 389.41 Section 389.41... AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION REHABILITATION CONTINUING EDUCATION PROGRAMS What Conditions Must Be Met by a Grantee? § 389.41 What are allowable costs? In addition to those allowable costs...

  5. 34 CFR 387.41 - What are allowable costs?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 34 Education 2 2012-07-01 2012-07-01 false What are allowable costs? 387.41 Section 387.41... AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION EXPERIMENTAL AND INNOVATIVE TRAINING What Conditions Must Be Met by a Grantee? § 387.41 What are allowable costs? In addition to those allowable costs...

  6. 40 CFR 31.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... accounting standards that comply with cost principles acceptable to the Federal agency. ... Requirements Financial Administration § 31.22 Allowable costs. (a) Limitation on use of funds. Grant funds may... the grantee or sub-grantee. (b) Applicable cost principles. For each kind of organization, there is a...

  7. 34 CFR 80.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... CFR part 31. Contract Cost Principles and Procedures, or uniform cost accounting standards that comply... COOPERATIVE AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial Administration § 80.22... kind of organization, there is a set of Federal principles for determining allowable costs. For the...

  8. 34 CFR 389.41 - What are allowable costs?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 34 Education 2 2011-07-01 2010-07-01 true What are allowable costs? 389.41 Section 389.41 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF SPECIAL EDUCATION... Conditions Must Be Met by a Grantee? § 389.41 What are allowable costs? In addition to those allowable costs...

  9. 34 CFR 389.41 - What are allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 34 Education 2 2010-07-01 2010-07-01 false What are allowable costs? 389.41 Section 389.41 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF SPECIAL EDUCATION... Conditions Must Be Met by a Grantee? § 389.41 What are allowable costs? In addition to those allowable costs...

  10. 42 CFR 50.504 - Allowable cost of drugs.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 42 Public Health 1 2014-10-01 2014-10-01 false Allowable cost of drugs. 50.504 Section 50.504... APPLICABILITY Maximum Allowable Cost for Drugs § 50.504 Allowable cost of drugs. (a) The maximum amount which may be expended from program funds for the acquisition of any drug shall be the lowest of (1) The...

  11. 42 CFR 50.504 - Allowable cost of drugs.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 42 Public Health 1 2013-10-01 2013-10-01 false Allowable cost of drugs. 50.504 Section 50.504... APPLICABILITY Maximum Allowable Cost for Drugs § 50.504 Allowable cost of drugs. (a) The maximum amount which may be expended from program funds for the acquisition of any drug shall be the lowest of (1) The...

  12. 42 CFR 50.504 - Allowable cost of drugs.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 42 Public Health 1 2011-10-01 2011-10-01 false Allowable cost of drugs. 50.504 Section 50.504... APPLICABILITY Maximum Allowable Cost for Drugs § 50.504 Allowable cost of drugs. (a) The maximum amount which may be expended from program funds for the acquisition of any drug shall be the lowest of (1) The...

  13. 42 CFR 50.504 - Allowable cost of drugs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 42 Public Health 1 2010-10-01 2010-10-01 false Allowable cost of drugs. 50.504 Section 50.504... APPLICABILITY Maximum Allowable Cost for Drugs § 50.504 Allowable cost of drugs. (a) The maximum amount which may be expended from program funds for the acquisition of any drug shall be the lowest of (1) The...

  14. 21 CFR 1403.22 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 21 Food and Drugs 9 2011-04-01 2011-04-01 false Allowable costs. 1403.22 Section 1403.22 Food and Drugs OFFICE OF NATIONAL DRUG CONTROL POLICY UNIFORM ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND... the applicable cost principles. For the costs of a— Use the principles in— State, local or Indian...

  15. 32 CFR 32.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... contractor receiving a. cost-type contract under an assistance award, there is a set of Federal principles... principles applicable to the entity incurring the costs. (b) Governmental organizations. Allowability of... of OMB Circular A-87, 8 “Cost Principles for State and Local Governments.” 8 See footnote 1 to § 32.1...

  16. 40 CFR 45.145 - Allocability and allowability of costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... FEDERAL ASSISTANCE TRAINING ASSISTANCE § 45.145 Allocability and allowability of costs. (a) Allocability and allowability of costs will be determined in accordance with 40 CFR 30.410. (b) Costs incurred for... 40 Protection of Environment 1 2010-07-01 2010-07-01 false Allocability and allowability of costs...

  17. Evaluation of the Maximum Allowable Cost Program

    PubMed Central

    Lee, A. James; Hefner, Dennis; Dobson, Allen; Hardy, Ralph

    1983-01-01

    This article summarizes an evaluation of the Maximum Allowable Cost (MAC)-Estimated Acquisition Cost (EAC) program, the Federal Government's cost-containment program for prescription drugs.1 The MAC-EAC regulations which became effective on August 26, 1976, have four major components: (1) Maximum Allowable Cost reimbursement limits for selected multisource or generically available drugs; (2) Estimated Acquisition Cost reimbursement limits for all drugs; (3) “usual and customary” reimbursement limits for all drugs; and (4) a directive that professional fee studies be performed by each State. The study examines the benefits and costs of the MAC reimbursement limits for 15 dosage forms of five multisource drugs and EAC reimbursement limits for all drugs for five selected States as of 1979. PMID:10309857

  18. 40 CFR 35.936-20 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... costs. (b) Appropriate cost principles which apply to subagreements under EPA grants are identified in... engineering services are allowable, even when conducted before award of the grant. Legal and engineering costs...

  19. 40 CFR 35.936-20 - Allowable costs.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... costs. (b) Appropriate cost principles which apply to subagreements under EPA grants are identified in... engineering services are allowable, even when conducted before award of the grant. Legal and engineering costs...

  20. 40 CFR 35.936-20 - Allowable costs.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... costs. (b) Appropriate cost principles which apply to subagreements under EPA grants are identified in... engineering services are allowable, even when conducted before award of the grant. Legal and engineering costs...

  1. 40 CFR 35.936-20 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... costs. (b) Appropriate cost principles which apply to subagreements under EPA grants are identified in... engineering services are allowable, even when conducted before award of the grant. Legal and engineering costs...

  2. 75 FR 32494 - Energy Conservation for PHA-Owned or Leased Project-Audits, Utility Allowances

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-06-08

    ...-Owned or Leased Project-Audits, Utility Allowances AGENCY: Office of the Chief Information Officer, HUD... complete energy audits, benefit/cost analyses for individual vs. master metering. PHAs review tenant...-Audits, Utility Allowances. OMB Approval Number: 2577-0062. Form Numbers: HUD-50078. Description of the...

  3. 40 CFR 30.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND AGREEMENTS WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, AND OTHER...-Profit Organizations.” The allowability of costs incurred by institutions of higher education is... include transportation and subsistence costs for travel performed; recipients will pay these in accordance...

  4. 34 CFR 644.30 - What are allowable costs?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 34 Education 3 2011-07-01 2011-07-01 false What are allowable costs? 644.30 Section 644.30... EDUCATION, DEPARTMENT OF EDUCATION EDUCATIONAL OPPORTUNITY CENTERS What Conditions Must Be Met by a Grantee? § 644.30 What are allowable costs? The cost principles that apply to the Educational Opportunity Centers...

  5. 28 CFR 70.27 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... AND AGREEMENTS (INCLUDING SUBAWARDS) WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS AND OTHER NON... Organizations.” The allowability of costs incurred by institutions of higher education is determined in accordance with the provisions of OMB Circular A-21, “Cost Principles for Educational Institutions.” The...

  6. 28 CFR 70.27 - Allowable costs.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... AND AGREEMENTS (INCLUDING SUBAWARDS) WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS AND OTHER NON... Organizations.” The allowability of costs incurred by institutions of higher education is determined in accordance with the provisions of OMB Circular A-21, “Cost Principles for Educational Institutions.” The...

  7. 28 CFR 70.27 - Allowable costs.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... AND AGREEMENTS (INCLUDING SUBAWARDS) WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS AND OTHER NON... Organizations.” The allowability of costs incurred by institutions of higher education is determined in accordance with the provisions of OMB Circular A-21, “Cost Principles for Educational Institutions.” The...

  8. 28 CFR 70.27 - Allowable costs.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... AND AGREEMENTS (INCLUDING SUBAWARDS) WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS AND OTHER NON... Organizations.” The allowability of costs incurred by institutions of higher education is determined in accordance with the provisions of OMB Circular A-21, “Cost Principles for Educational Institutions.” The...

  9. 40 CFR 310.11 - What costs are allowable?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 27 2010-07-01 2010-07-01 false What costs are allowable? 310.11... HAZARDOUS SUBSTANCE RELEASES Provisions What Can Be Reimbursed? § 310.11 What costs are allowable? (a... costs are only those necessary for you to respond effectively to a specific incident that is beyond what...

  10. 40 CFR 310.11 - What costs are allowable?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 40 Protection of Environment 28 2014-07-01 2014-07-01 false What costs are allowable? 310.11... HAZARDOUS SUBSTANCE RELEASES Provisions What Can Be Reimbursed? § 310.11 What costs are allowable? (a... costs are only those necessary for you to respond effectively to a specific incident that is beyond what...

  11. 40 CFR 310.11 - What costs are allowable?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 40 Protection of Environment 29 2013-07-01 2013-07-01 false What costs are allowable? 310.11... HAZARDOUS SUBSTANCE RELEASES Provisions What Can Be Reimbursed? § 310.11 What costs are allowable? (a... costs are only those necessary for you to respond effectively to a specific incident that is beyond what...

  12. 34 CFR 390.41 - What are allowable costs?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 34 Education 2 2012-07-01 2012-07-01 false What are allowable costs? 390.41 Section 390.41... AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION REHABILITATION SHORT-TERM TRAINING What Conditions Must Be Met by a Grantee? § 390.41 What are allowable costs? (a) In addition to those allowable...

  13. 38 CFR 49.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND AGREEMENTS WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, AND OTHER NON-PROFIT ORGANIZATIONS Post-Award Requirements Financial and Program Management § 49.27 Allowable...-Profit Organizations.” The allowability of costs incurred by institutions of higher education is...

  14. 28 CFR 70.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 28 Judicial Administration 2 2010-07-01 2010-07-01 false Allowable costs. 70.27 Section 70.27 Judicial Administration DEPARTMENT OF JUSTICE (CONTINUED) UNIFORM ADMINISTRATIVE REQUIREMENTS FOR GRANTS... accordance with the provisions of OMB Circular A-21, “Cost Principles for Educational Institutions.” The...

  15. 40 CFR 35.940-5 - Disputes concerning allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 1 2010-07-01 2010-07-01 false Disputes concerning allowable costs. 35... § 35.940-5 Disputes concerning allowable costs. The grantee should seek to resolve any questions... the grant agreement). Final determinations concerning the allowability of costs shall be conclusive...

  16. 22 CFR 226.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... Relations AGENCY FOR INTERNATIONAL DEVELOPMENT ADMINISTRATION OF ASSISTANCE AWARDS TO U.S. NON-GOVERNMENTAL ORGANIZATIONS Post-award Requirements Financial and Program Management § 226.27 Allowable costs. For each kind... organizations is determined in accordance with the provisions of OMB Circular A-122, “Cost Principles for Non...

  17. 22 CFR 135.22 - Allowable costs.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 22 Foreign Relations 1 2012-04-01 2012-04-01 false Allowable costs. 135.22 Section 135.22 Foreign Relations DEPARTMENT OF STATE MISCELLANEOUS UNIFORM ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND COOPERATIVE AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial Administration § 135.22 Allowable...

  18. 22 CFR 135.22 - Allowable costs.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 22 Foreign Relations 1 2013-04-01 2013-04-01 false Allowable costs. 135.22 Section 135.22 Foreign Relations DEPARTMENT OF STATE MISCELLANEOUS UNIFORM ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND COOPERATIVE AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial Administration § 135.22 Allowable...

  19. 22 CFR 135.22 - Allowable costs.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 22 Foreign Relations 1 2014-04-01 2014-04-01 false Allowable costs. 135.22 Section 135.22 Foreign Relations DEPARTMENT OF STATE MISCELLANEOUS UNIFORM ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND COOPERATIVE AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial Administration § 135.22 Allowable...

  20. 22 CFR 135.22 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 22 Foreign Relations 1 2011-04-01 2011-04-01 false Allowable costs. 135.22 Section 135.22 Foreign Relations DEPARTMENT OF STATE MISCELLANEOUS UNIFORM ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND COOPERATIVE AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial Administration § 135.22 Allowable...

  1. 34 CFR 75.531 - Limit on total cost of a project.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 34 Education 1 2014-07-01 2014-07-01 false Limit on total cost of a project. 75.531 Section 75.531... by a Grantee? Allowable Costs § 75.531 Limit on total cost of a project. A grantee shall insure that... grant award. (Authority: 20 U.S.C. 1221e-3 and 3474) ...

  2. 34 CFR 645.40 - What are allowable costs?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... related to the objectives of the project: (a) In-service training of project staff. (b) Rental of space if... project-sponsored banquet or ceremony. (i) Tuition costs for postsecondary credit courses at the host... to a project participant while participating in a project activity; and (2) Medical insurance and...

  3. 34 CFR 645.40 - What are allowable costs?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... related to the objectives of the project: (a) In-service training of project staff. (b) Rental of space if... project-sponsored banquet or ceremony. (i) Tuition costs for postsecondary credit courses at the host... to a project participant while participating in a project activity; and (2) Medical insurance and...

  4. 34 CFR 645.40 - What are allowable costs?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... related to the objectives of the project: (a) In-service training of project staff. (b) Rental of space if... project-sponsored banquet or ceremony. (i) Tuition costs for postsecondary credit courses at the host... to a project participant while participating in a project activity; and (2) Medical insurance and...

  5. 34 CFR 645.40 - What are allowable costs?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... related to the objectives of the project: (a) In-service training of project staff. (b) Rental of space if... project-sponsored banquet or ceremony. (i) Tuition costs for postsecondary credit courses at the host... to a project participant while participating in a project activity; and (2) Medical insurance and...

  6. 34 CFR 608.40 - What are allowable costs and what are the limitations on allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... BLACK COLLEGES AND UNIVERSITIES PROGRAM What Conditions Must a Grantee Meet? § 608.40 What are allowable... classroom, library, laboratory, or other instructional facility; or (2) Use an indirect cost rate to...

  7. 34 CFR 370.40 - What are allowable costs?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 34 Education 2 2014-07-01 2013-07-01 true What are allowable costs? 370.40 Section 370.40... AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION CLIENT ASSISTANCE PROGRAM What Post-Award Conditions Must Be Met by a Designated Agency? § 370.40 What are allowable costs? (a) If the designated...

  8. 34 CFR 370.40 - What are allowable costs?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 34 Education 2 2013-07-01 2013-07-01 false What are allowable costs? 370.40 Section 370.40... AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION CLIENT ASSISTANCE PROGRAM What Post-Award Conditions Must Be Met by a Designated Agency? § 370.40 What are allowable costs? (a) If the designated...

  9. 34 CFR 370.40 - What are allowable costs?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 34 Education 2 2012-07-01 2012-07-01 false What are allowable costs? 370.40 Section 370.40... AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION CLIENT ASSISTANCE PROGRAM What Post-Award Conditions Must Be Met by a Designated Agency? § 370.40 What are allowable costs? (a) If the designated...

  10. 34 CFR 386.32 - What are allowable costs?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 34 Education 2 2012-07-01 2012-07-01 false What are allowable costs? 386.32 Section 386.32 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF SPECIAL EDUCATION... TRAINING What Conditions Must Be Met After an Award? § 386.32 What are allowable costs? In addition to...

  11. 48 CFR 1652.216-71 - Accounting and Allowable Cost.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 6 2010-10-01 2010-10-01 true Accounting and Allowable... of FEHBP Clauses 1652.216-71 Accounting and Allowable Cost. As prescribed in section 1616.7002, the...). Accounting and Allowable Cost (FEHBAR 1652.216-71) (JAN 2003) (a) Annual Accounting Statements. (1) The...

  12. Underestimation of Project Costs

    NASA Technical Reports Server (NTRS)

    Jones, Harry W.

    2015-01-01

    Large projects almost always exceed their budgets. Estimating cost is difficult and estimated costs are usually too low. Three different reasons are suggested: bad luck, overoptimism, and deliberate underestimation. Project management can usually point to project difficulty and complexity, technical uncertainty, stakeholder conflicts, scope changes, unforeseen events, and other not really unpredictable bad luck. Project planning is usually over-optimistic, so the likelihood and impact of bad luck is systematically underestimated. Project plans reflect optimism and hope for success in a supposedly unique new effort rather than rational expectations based on historical data. Past project problems are claimed to be irrelevant because "This time it's different." Some bad luck is inevitable and reasonable optimism is understandable, but deliberate deception must be condemned. In a competitive environment, project planners and advocates often deliberately underestimate costs to help gain project approval and funding. Project benefits, cost savings, and probability of success are exaggerated and key risks ignored. Project advocates have incentives to distort information and conceal difficulties from project approvers. One naively suggested cure is more openness, honesty, and group adherence to shared overall goals. A more realistic alternative is threatening overrun projects with cancellation. Neither approach seems to solve the problem. A better method to avoid the delusions of over-optimism and the deceptions of biased advocacy is to base the project cost estimate on the actual costs of a large group of similar projects. Over optimism and deception can continue beyond the planning phase and into project execution. Hard milestones based on verified tests and demonstrations can provide a reality check.

  13. 34 CFR 673.7 - Administrative cost allowance.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... EDUCATION, DEPARTMENT OF EDUCATION GENERAL PROVISIONS FOR THE FEDERAL PERKINS LOAN PROGRAM, FEDERAL WORK... Federal Perkins Loan, FWS, and FSEOG Programs § 673.7 Administrative cost allowance. (a) An institution participating in the Federal Perkins Loan, FWS, or FSEOG programs is entitled to an administrative cost...

  14. 34 CFR 673.7 - Administrative cost allowance.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... EDUCATION, DEPARTMENT OF EDUCATION GENERAL PROVISIONS FOR THE FEDERAL PERKINS LOAN PROGRAM, FEDERAL WORK... Federal Perkins Loan, FWS, and FSEOG Programs § 673.7 Administrative cost allowance. (a) An institution participating in the Federal Perkins Loan, FWS, or FSEOG programs is entitled to an administrative cost...

  15. 45 CFR 74.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... FOR AWARDS AND SUBAWARDS TO INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, OTHER NONPROFIT ORGANIZATIONS, AND COMMERCIAL ORGANIZATIONS Post-Award Requirements Financial and Program Management § 74.27... Organizations” and paragraph (b) of this section. The allowability of costs incurred by institutions of higher...

  16. 22 CFR 145.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... Relations DEPARTMENT OF STATE CIVIL RIGHTS GRANTS AND AGREEMENTS WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, AND OTHER NON-PROFIT ORGANIZATIONS Post-Award Requirements Financial and Program Management § 145...-Profit Organizations.” The allowability of costs incurred by institutions of higher education is...

  17. 20 CFR 435.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 20 Employees' Benefits 2 2010-04-01 2010-04-01 false Allowable costs. 435.27 Section 435.27 Employees' Benefits SOCIAL SECURITY ADMINISTRATION UNIFORM ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND AGREEMENTS WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, OTHER NON-PROFIT ORGANIZATIONS, AND COMMERCIAL...

  18. 50 CFR 80.15 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ...) FINANCIAL ASSISTANCE-WILDLIFE SPORT FISH RESTORATION PROGRAM ADMINISTRATIVE REQUIREMENTS, PITTMAN-ROBERTSON WILDLIFE RESTORATION AND DINGELL-JOHNSON SPORT FISH RESTORATION ACTS § 80.15 Allowable costs. (a) What are... designed to include purposes other than those eligible under either the Dingell-Johnson Sport Fish...

  19. 40 CFR 310.12 - What costs are NOT allowable?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 27 2010-07-01 2010-07-01 false What costs are NOT allowable? 310.12... PLANNING, AND COMMUNITY RIGHT-TO-KNOW PROGRAMS REIMBURSEMENT TO LOCAL GOVERNMENTS FOR EMERGENCY RESPONSE TO HAZARDOUS SUBSTANCE RELEASES Provisions What Can Be Reimbursed? § 310.12 What costs are NOT allowable? (a...

  20. 45 CFR 2543.27 - Allowable costs.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 45 Public Welfare 4 2013-10-01 2013-10-01 false Allowable costs. 2543.27 Section 2543.27 Public Welfare Regulations Relating to Public Welfare (Continued) CORPORATION FOR NATIONAL AND COMMUNITY SERVICE GRANTS AND AGREEMENTS WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, AND OTHER NON-PROFIT...

  1. 45 CFR 74.27 - Allowable costs.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 45 Public Welfare 1 2013-10-01 2013-10-01 false Allowable costs. 74.27 Section 74.27 Public Welfare DEPARTMENT OF HEALTH AND HUMAN SERVICES GENERAL ADMINISTRATION UNIFORM ADMINISTRATIVE REQUIREMENTS FOR AWARDS AND SUBAWARDS TO INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, OTHER NONPROFIT ORGANIZATIONS...

  2. 45 CFR 2543.27 - Allowable costs.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 45 Public Welfare 4 2014-10-01 2014-10-01 false Allowable costs. 2543.27 Section 2543.27 Public Welfare Regulations Relating to Public Welfare (Continued) CORPORATION FOR NATIONAL AND COMMUNITY SERVICE GRANTS AND AGREEMENTS WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, AND OTHER NON-PROFIT...

  3. 45 CFR 2543.27 - Allowable costs.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 45 Public Welfare 4 2012-10-01 2012-10-01 false Allowable costs. 2543.27 Section 2543.27 Public Welfare Regulations Relating to Public Welfare (Continued) CORPORATION FOR NATIONAL AND COMMUNITY SERVICE GRANTS AND AGREEMENTS WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, AND OTHER NON-PROFIT...

  4. 45 CFR 74.27 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 45 Public Welfare 1 2011-10-01 2011-10-01 false Allowable costs. 74.27 Section 74.27 Public Welfare DEPARTMENT OF HEALTH AND HUMAN SERVICES GENERAL ADMINISTRATION UNIFORM ADMINISTRATIVE REQUIREMENTS FOR AWARDS AND SUBAWARDS TO INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, OTHER NONPROFIT ORGANIZATIONS...

  5. 45 CFR 2543.27 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 45 Public Welfare 4 2011-10-01 2011-10-01 false Allowable costs. 2543.27 Section 2543.27 Public Welfare Regulations Relating to Public Welfare (Continued) CORPORATION FOR NATIONAL AND COMMUNITY SERVICE GRANTS AND AGREEMENTS WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, AND OTHER NON-PROFIT...

  6. 45 CFR 74.27 - Allowable costs.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 45 Public Welfare 1 2012-10-01 2012-10-01 false Allowable costs. 74.27 Section 74.27 Public Welfare DEPARTMENT OF HEALTH AND HUMAN SERVICES GENERAL ADMINISTRATION UNIFORM ADMINISTRATIVE REQUIREMENTS FOR AWARDS AND SUBAWARDS TO INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, OTHER NONPROFIT ORGANIZATIONS...

  7. 45 CFR 74.27 - Allowable costs.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 45 Public Welfare 1 2014-10-01 2014-10-01 false Allowable costs. 74.27 Section 74.27 Public Welfare Department of Health and Human Services GENERAL ADMINISTRATION UNIFORM ADMINISTRATIVE REQUIREMENTS FOR AWARDS AND SUBAWARDS TO INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, OTHER NONPROFIT ORGANIZATIONS...

  8. 34 CFR 304.21 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 34 Education 2 2011-07-01 2010-07-01 true Allowable costs. 304.21 Section 304.21 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF SPECIAL EDUCATION AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION SERVICE OBLIGATIONS UNDER SPECIAL EDUCATION-PERSONNEL...

  9. 34 CFR 74.27 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 34 Education 1 2011-07-01 2011-07-01 false Allowable costs. 74.27 Section 74.27 Education Office of the Secretary, Department of Education ADMINISTRATION OF GRANTS AND AGREEMENTS WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, AND OTHER NON-PROFIT ORGANIZATIONS Post-Award Requirements Financial...

  10. 34 CFR 304.21 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 34 Education 2 2010-07-01 2010-07-01 false Allowable costs. 304.21 Section 304.21 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF SPECIAL EDUCATION AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION SERVICE OBLIGATIONS UNDER SPECIAL EDUCATION-PERSONNEL...

  11. 49 CFR 18.22 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 49 Transportation 1 2011-10-01 2011-10-01 false Allowable costs. 18.22 Section 18.22... COOPERATIVE AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial Administration § 18.22... A-87. Private nonprofit organization other than an (1) institution of higher education, (2) hospital...

  12. 44 CFR 79.8 - Allowable costs.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 44 Emergency Management and Assistance 1 2013-10-01 2013-10-01 false Allowable costs. 79.8 Section 79.8 Emergency Management and Assistance FEDERAL EMERGENCY MANAGEMENT AGENCY, DEPARTMENT OF HOMELAND SECURITY INSURANCE AND HAZARD MITIGATION National Flood Insurance Program FLOOD MITIGATION GRANTS § 79.8...

  13. 44 CFR 79.8 - Allowable costs.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 44 Emergency Management and Assistance 1 2014-10-01 2014-10-01 false Allowable costs. 79.8 Section 79.8 Emergency Management and Assistance FEDERAL EMERGENCY MANAGEMENT AGENCY, DEPARTMENT OF HOMELAND SECURITY INSURANCE AND HAZARD MITIGATION National Flood Insurance Program FLOOD MITIGATION GRANTS § 79.8...

  14. 44 CFR 79.8 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 44 Emergency Management and Assistance 1 2011-10-01 2011-10-01 false Allowable costs. 79.8 Section 79.8 Emergency Management and Assistance FEDERAL EMERGENCY MANAGEMENT AGENCY, DEPARTMENT OF HOMELAND SECURITY INSURANCE AND HAZARD MITIGATION National Flood Insurance Program FLOOD MITIGATION GRANTS § 79.8...

  15. 44 CFR 79.8 - Allowable costs.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 44 Emergency Management and Assistance 1 2012-10-01 2011-10-01 true Allowable costs. 79.8 Section 79.8 Emergency Management and Assistance FEDERAL EMERGENCY MANAGEMENT AGENCY, DEPARTMENT OF HOMELAND SECURITY INSURANCE AND HAZARD MITIGATION National Flood Insurance Program FLOOD MITIGATION GRANTS § 79.8...

  16. The Six Cs of Managing Federal Projects: How to Avoid Cost Disallowances.

    ERIC Educational Resources Information Center

    Goeres, Ernest R.; Mancini, Cesidio G.

    1995-01-01

    To avoid embarrassment and financial cost of incurring cost disallowances on federally-sponsored projects, college and university administrators must pay particular attention to these management areas: compensation (release time, overload, and others); costs (allowable, attributable, transfers, and others); consulting; certification of time and…

  17. 22 CFR 518.27 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, AND OTHER NON-PROFIT ORGANIZATIONS Post-Award Requirements Financial and Program Management § 518.27 Allowable costs. For each kind of recipient, there is a set of... by institutions of higher education is determined in accordance with the provisions of OMB Circular A...

  18. 24 CFR 85.22 - Allowable costs.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 24 Housing and Urban Development 1 2014-04-01 2014-04-01 false Allowable costs. 85.22 Section 85.22 Housing and Urban Development Office of the Secretary, Department of Housing and Urban Development ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND COOPERATIVE AGREEMENTS TO STATE, LOCAL AND FEDERALLY RECOGNIZED INDIAN...

  19. 24 CFR 85.22 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 24 Housing and Urban Development 1 2011-04-01 2011-04-01 false Allowable costs. 85.22 Section 85.22 Housing and Urban Development Office of the Secretary, Department of Housing and Urban Development ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND COOPERATIVE AGREEMENTS TO STATE, LOCAL AND FEDERALLY RECOGNIZED INDIAN...

  20. 24 CFR 85.22 - Allowable costs.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 24 Housing and Urban Development 1 2012-04-01 2012-04-01 false Allowable costs. 85.22 Section 85.22 Housing and Urban Development Office of the Secretary, Department of Housing and Urban Development ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND COOPERATIVE AGREEMENTS TO STATE, LOCAL AND FEDERALLY RECOGNIZED INDIAN...

  1. 24 CFR 85.22 - Allowable costs.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 24 Housing and Urban Development 1 2013-04-01 2013-04-01 false Allowable costs. 85.22 Section 85.22 Housing and Urban Development Office of the Secretary, Department of Housing and Urban Development ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND COOPERATIVE AGREEMENTS TO STATE, LOCAL AND FEDERALLY RECOGNIZED INDIAN...

  2. 34 CFR 646.30 - What are allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... EDUCATION, DEPARTMENT OF EDUCATION STUDENT SUPPORT SERVICES PROGRAM What Conditions Must Be Met by a Grantee? § 646.30 What are allowable costs? The cost principles that apply to the Student Support Services...) Courses in English language instruction for students of limited English proficiency if these classes are...

  3. 42 CFR 413.50 - Apportionment of allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... Apportionment of allowable costs. (a) Consistent with prevailing practice in which third-party organizations pay... participate in the program. Available evidence shows that the use of services by persons age 65 and over... time by third-party purchasers of inpatient hospital care apportions a provider's total costs among...

  4. 14 CFR 151.41 - Project costs.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 14 Aeronautics and Space 3 2012-01-01 2012-01-01 false Project costs. 151.41 Section 151.41... FEDERAL AID TO AIRPORTS Rules and Procedures for Airport Development Projects § 151.41 Project costs. (a) For the purposes of subparts B and C, project costs consist of any costs involved in accomplishing a...

  5. 14 CFR 151.41 - Project costs.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 14 Aeronautics and Space 3 2014-01-01 2014-01-01 false Project costs. 151.41 Section 151.41... FEDERAL AID TO AIRPORTS Rules and Procedures for Airport Development Projects § 151.41 Project costs. (a) For the purposes of subparts B and C, project costs consist of any costs involved in accomplishing a...

  6. 14 CFR 151.41 - Project costs.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 14 Aeronautics and Space 3 2013-01-01 2013-01-01 false Project costs. 151.41 Section 151.41... FEDERAL AID TO AIRPORTS Rules and Procedures for Airport Development Projects § 151.41 Project costs. (a) For the purposes of subparts B and C, project costs consist of any costs involved in accomplishing a...

  7. 14 CFR 151.41 - Project costs.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 14 Aeronautics and Space 3 2011-01-01 2011-01-01 false Project costs. 151.41 Section 151.41... FEDERAL AID TO AIRPORTS Rules and Procedures for Airport Development Projects § 151.41 Project costs. (a) For the purposes of subparts B and C, project costs consist of any costs involved in accomplishing a...

  8. 14 CFR 151.41 - Project costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 14 Aeronautics and Space 3 2010-01-01 2010-01-01 false Project costs. 151.41 Section 151.41... FEDERAL AID TO AIRPORTS Rules and Procedures for Airport Development Projects § 151.41 Project costs. (a) For the purposes of subparts B and C, project costs consist of any costs involved in accomplishing a...

  9. 34 CFR 644.30 - What are allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... EDUCATION, DEPARTMENT OF EDUCATION EDUCATIONAL OPPORTUNITY CENTERS What Conditions Must Be Met by a Grantee? § 644.30 What are allowable costs? The cost principles that apply to the Educational Opportunity Centers... in various career fields in the target area and who can serve as role models for participants. (b...

  10. 36 CFR 64.9 - Project costs (State and local projects).

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 36 Parks, Forests, and Public Property 1 2013-07-01 2013-07-01 false Project costs (State and... RIGHTS-OF-WAY § 64.9 Project costs (State and local projects). To be eligible, acquisition and development costs must be incurred after the date of project approval and during the project period. The...

  11. 36 CFR 64.9 - Project costs (State and local projects).

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 36 Parks, Forests, and Public Property 1 2012-07-01 2012-07-01 false Project costs (State and... RIGHTS-OF-WAY § 64.9 Project costs (State and local projects). To be eligible, acquisition and development costs must be incurred after the date of project approval and during the project period. The...

  12. 36 CFR 64.9 - Project costs (State and local projects).

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 36 Parks, Forests, and Public Property 1 2014-07-01 2014-07-01 false Project costs (State and... RIGHTS-OF-WAY § 64.9 Project costs (State and local projects). To be eligible, acquisition and development costs must be incurred after the date of project approval and during the project period. The...

  13. 36 CFR 64.9 - Project costs (State and local projects).

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 36 Parks, Forests, and Public Property 1 2011-07-01 2011-07-01 false Project costs (State and... RIGHTS-OF-WAY § 64.9 Project costs (State and local projects). To be eligible, acquisition and development costs must be incurred after the date of project approval and during the project period. The...

  14. 34 CFR 690.10 - Administrative cost allowance to participating schools.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 34 Education 3 2010-07-01 2010-07-01 false Administrative cost allowance to participating schools. 690.10 Section 690.10 Education Regulations of the Offices of the Department of Education (Continued... General Definitions § 690.10 Administrative cost allowance to participating schools. (a) Subject to...

  15. 34 CFR 690.10 - Administrative cost allowance to participating schools.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 34 Education 4 2011-07-01 2011-07-01 false Administrative cost allowance to participating schools. 690.10 Section 690.10 Education Regulations of the Offices of the Department of Education (Continued..., Purpose and General Definitions § 690.10 Administrative cost allowance to participating schools. (a...

  16. 34 CFR 387.41 - What are allowable costs?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 34 Education 2 2014-07-01 2013-07-01 true What are allowable costs? 387.41 Section 387.41... AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION EXPERIMENTAL AND INNOVATIVE TRAINING What... established under EDGAR §§ 75.530-75.562, the following items are allowable under experimental and innovative...

  17. 34 CFR 387.41 - What are allowable costs?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 34 Education 2 2011-07-01 2010-07-01 true What are allowable costs? 387.41 Section 387.41... AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION EXPERIMENTAL AND INNOVATIVE TRAINING What... established under EDGAR §§ 75.530-75.562, the following items are allowable under experimental and innovative...

  18. Analysis of electric vehicle's trip cost allowing late arrival

    NASA Astrophysics Data System (ADS)

    Leng, Jun-Qiang; Liu, Wei-Yi; Zhao, Lin

    2017-05-01

    In this paper, we use a car-following model to study each electric vehicle's trip cost and the total trip cost allowing late arrival. The numerical result show that the electricity cost has great effects on each commuter's trip cost and the total trip costs and that these effects are dependent on each commuter's time headway at the origin, but the electricity cost has no prominent impacts on the minimum value of total trip cost under each commuter's different time headway at the origin.

  19. 48 CFR 52.216-26 - Payments of Allowable Costs Before Definitization.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... Costs Before Definitization. 52.216-26 Section 52.216-26 Federal Acquisition Regulations System FEDERAL... Provisions and Clauses 52.216-26 Payments of Allowable Costs Before Definitization. As prescribed in 16.603-4(c), insert the following clause: Payments of Allowable Costs Before Definitization (DEC 2002) (a...

  20. 2 CFR 200.83 - Project cost.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 2 Grants and Agreements 1 2014-01-01 2014-01-01 false Project cost. 200.83 Section 200.83 Grants... AND BUDGET GUIDANCE Reserved UNIFORM ADMINISTRATIVE REQUIREMENTS, COST PRINCIPLES, AND AUDIT REQUIREMENTS FOR FEDERAL AWARDS Acronyms and Definitions Acronyms § 200.83 Project cost. Project cost means...

  1. Department of Defense Environmental Cleanup Cost Allowability Policy.

    DTIC Science & Technology

    1994-12-01

    The environment is directly affected by the industrial requirements and manufacturing processes necessary to provide those goods and services. As...and the industrial base. To begin the process , DCMC initiated the Environmental Initiatives Task Force Pilot Cost Allowance Program at five locations...policy covering environmental cleanup costs. Information will be provided to assist in the decision making process regarding the factors affecting the

  2. 41 CFR 105-72.307 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 41 Public Contracts and Property Management 3 2010-07-01 2010-07-01 false Allowable costs. 105-72.307 Section 105-72.307 Public Contracts and Property Management Federal Property Management... Administration 72-UNIFORM ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND AGREEMENTS WITH INSTITUTIONS OF HIGHER...

  3. Solar project cost report

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Hale, H.J.

    1978-01-01

    This report provides detailed cost information for the Reedy Creek Utilities solar space heating, cooling and service water heating project located in Walt Disney World, Florida. The solar energy system cools, heats and supplies service hot water for approximately 5625 ft/sup 2/ of office space in a general office building. The system was designed as an integral part of the building at the time the building was designed. The construction costs of this solar project are presented in this report. Category costs are listed by materials, direct labor, and subcontract costs. The subcontract costs include both materials, labor, overhead andmore » profit for electrical, control and other minor subcontractors.« less

  4. Impact of Research and Development, Analysis, and Standardization on PV Project Financing Costs

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Feldman, David J; Margolis, Robert M; Jones-Albertus, Rebecca

    The technical report discusses how R and D efforts focused on removing perceived risk from cash flows to investors have the potential to lower the cost of capital and increase the amount of leverage in a solar project. It also discusses how creating business efficiencies that allow financing transactions to occur more quickly with less effort can reduce the upfront costs associated with arranging financing for a solar project or group of projects. The paper then assesses the impact that these R and D activities might have on the volatility of PV asset cash flows and asset value, as wellmore » as the upfront costs of arranging a financial transaction. Finally, we insert these assumptions into financial models to analyze their impacts on the cost of capital for equity and debt investors, project leverage, and upfront financial transaction costs.« less

  5. 42 CFR 409.46 - Allowable administrative costs.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 42 Public Health 2 2013-10-01 2013-10-01 false Allowable administrative costs. 409.46 Section 409.46 Public Health CENTERS FOR MEDICARE & MEDICAID SERVICES, DEPARTMENT OF HEALTH AND HUMAN SERVICES MEDICARE PROGRAM HOSPITAL INSURANCE BENEFITS Home Health Services Under Hospital Insurance § 409.46...

  6. 42 CFR 409.46 - Allowable administrative costs.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 42 Public Health 2 2011-10-01 2011-10-01 false Allowable administrative costs. 409.46 Section 409.46 Public Health CENTERS FOR MEDICARE & MEDICAID SERVICES, DEPARTMENT OF HEALTH AND HUMAN SERVICES MEDICARE PROGRAM HOSPITAL INSURANCE BENEFITS Home Health Services Under Hospital Insurance § 409.46...

  7. 42 CFR 409.46 - Allowable administrative costs.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 42 Public Health 2 2012-10-01 2012-10-01 false Allowable administrative costs. 409.46 Section 409.46 Public Health CENTERS FOR MEDICARE & MEDICAID SERVICES, DEPARTMENT OF HEALTH AND HUMAN SERVICES MEDICARE PROGRAM HOSPITAL INSURANCE BENEFITS Home Health Services Under Hospital Insurance § 409.46...

  8. 7 CFR 4288.11 - Eligible project costs.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 7 Agriculture 15 2013-01-01 2013-01-01 false Eligible project costs. 4288.11 Section 4288.11... Eligible Biorefineries § 4288.11 Eligible project costs. Eligible project costs will be only for project related construction costs for repowering improvements associated with the equipment, installation...

  9. 7 CFR 4288.11 - Eligible project costs.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 7 Agriculture 15 2014-01-01 2014-01-01 false Eligible project costs. 4288.11 Section 4288.11... Eligible Biorefineries § 4288.11 Eligible project costs. Eligible project costs will be only for project related construction costs for repowering improvements associated with the equipment, installation...

  10. 7 CFR 4288.11 - Eligible project costs.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 7 Agriculture 15 2012-01-01 2012-01-01 false Eligible project costs. 4288.11 Section 4288.11... Eligible Biorefineries § 4288.11 Eligible project costs. Eligible project costs will be only for project related construction costs for repowering improvements associated with the equipment, installation...

  11. 24 CFR 941.306 - Maximum project cost.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 24 Housing and Urban Development 4 2012-04-01 2012-04-01 false Maximum project cost. 941.306... DEVELOPMENT PUBLIC HOUSING DEVELOPMENT Application and Proposal § 941.306 Maximum project cost. (a) Calculation of maximum project cost. The maximum project cost represents the total amount of public housing...

  12. 24 CFR 941.306 - Maximum project cost.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 24 Housing and Urban Development 4 2013-04-01 2013-04-01 false Maximum project cost. 941.306... DEVELOPMENT PUBLIC HOUSING DEVELOPMENT Application and Proposal § 941.306 Maximum project cost. (a) Calculation of maximum project cost. The maximum project cost represents the total amount of public housing...

  13. Cost estimation: An expert-opinion approach. [cost analysis of research projects using the Delphi method (forecasting)

    NASA Technical Reports Server (NTRS)

    Buffalano, C.; Fogleman, S.; Gielecki, M.

    1976-01-01

    A methodology is outlined which can be used to estimate the costs of research and development projects. The approach uses the Delphi technique a method developed by the Rand Corporation for systematically eliciting and evaluating group judgments in an objective manner. The use of the Delphi allows for the integration of expert opinion into the cost-estimating process in a consistent and rigorous fashion. This approach can also signal potential cost-problem areas. This result can be a useful tool in planning additional cost analysis or in estimating contingency funds. A Monte Carlo approach is also examined.

  14. Cost/CYP: a bottom line that helps keep CSM projects cost-efficient.

    PubMed

    1985-01-01

    In contraceptive social marketing (CSM), the objective is social good, but project managers also need to run a tight ship, trimming costs, allocating scarce funds, and monitoring their program's progress. 1 way CSM managers remain cost-conscious is through the concept of couple-years-of-protection (CYP). Devised 2 decades ago as an administrative tool to compare the effects of different contraceptive methods, CYP's uses have multiplied to include assessing program output and cost effectiveness. Some of the factors affecting cost/CYP are a project's age, sales volume, management efficiency, and product prices and line. These factors are interconnected. The cost/CYP figures given here do not include outlays for commodities. While the Agency for International Development's commodity costs alter slightly with each new purchase contrast, the agency reports that a condom costs about 4 cents (US), an oral contraceptive (OC) cycle about 12 cents, and a spermicidal tablet about 7 cents. CSM projects have relatively high start-up costs. Within a project's first 2 years, expenses must cover such marketing activities as research, packaging, warehousing, and heavy promotion. As a project ages, sales should grow, producing revenues that gradually amortize these initial costs. The Nepal CSM project provides an example of how cost/CYP can improve as a program ages. In 1978, the year sales began, the project's cost/CYP was about $84. For some time the project struggled to get its products to its target market and gradually overcome several major hurdles. The acquisition of jeeps eased distribution and, by adding another condom brand, sales were increased still more, bringing the cost/CYP down to $8.30 in 1981. With further sales increases and resulting revenues, the cost/CYP dropped to just over $7 in 1983. When the sales volume becomes large enough, CSM projects can achieve economies of scale, which greatly improves cost-efficiency. Fixed costs shrink as a proportion of total

  15. 45 CFR 2400.50 - Allowances and Summer Institute costs.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 45 Public Welfare 4 2013-10-01 2013-10-01 false Allowances and Summer Institute costs. 2400.50 Section 2400.50 Public Welfare Regulations Relating to Public Welfare (Continued) JAMES MADISON MEMORIAL FELLOWSHIP FOUNDATION FELLOWSHIP PROGRAM REQUIREMENTS Graduate Study § 2400.50 Allowances and Summer...

  16. 45 CFR 2400.50 - Allowances and Summer Institute costs.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 45 Public Welfare 4 2012-10-01 2012-10-01 false Allowances and Summer Institute costs. 2400.50 Section 2400.50 Public Welfare Regulations Relating to Public Welfare (Continued) JAMES MADISON MEMORIAL FELLOWSHIP FOUNDATION FELLOWSHIP PROGRAM REQUIREMENTS Graduate Study § 2400.50 Allowances and Summer...

  17. 45 CFR 2400.50 - Allowances and Summer Institute costs.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 45 Public Welfare 4 2014-10-01 2014-10-01 false Allowances and Summer Institute costs. 2400.50 Section 2400.50 Public Welfare Regulations Relating to Public Welfare (Continued) JAMES MADISON MEMORIAL FELLOWSHIP FOUNDATION FELLOWSHIP PROGRAM REQUIREMENTS Graduate Study § 2400.50 Allowances and Summer...

  18. 45 CFR 2400.50 - Allowances and Summer Institute costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 45 Public Welfare 4 2010-10-01 2010-10-01 false Allowances and Summer Institute costs. 2400.50 Section 2400.50 Public Welfare Regulations Relating to Public Welfare (Continued) JAMES MADISON MEMORIAL FELLOWSHIP FOUNDATION FELLOWSHIP PROGRAM REQUIREMENTS Graduate Study § 2400.50 Allowances and Summer...

  19. 45 CFR 2400.50 - Allowances and Summer Institute costs.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 45 Public Welfare 4 2011-10-01 2011-10-01 false Allowances and Summer Institute costs. 2400.50 Section 2400.50 Public Welfare Regulations Relating to Public Welfare (Continued) JAMES MADISON MEMORIAL FELLOWSHIP FOUNDATION FELLOWSHIP PROGRAM REQUIREMENTS Graduate Study § 2400.50 Allowances and Summer...

  20. Research on the Investment Costs of IT Project

    NASA Astrophysics Data System (ADS)

    Zurong, Chen; Feng, Jingchun

    2018-02-01

    The investment costs of IT project are the basis of IT project management. The meaning and composition of the investment costs of IT project were analyzed in this paper, which involving the engineering cost of IT project, the other costs of IT project, reserve cost and financing interest of the construction period. On this basis, the composition and content of static investment costs and dynamic investment costs of IT project were also studied in the paper.

  1. 10 CFR 611.102 - Eligible project costs.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 10 Energy 4 2014-01-01 2014-01-01 false Eligible project costs. 611.102 Section 611.102 Energy... PROGRAM Direct Loan Program § 611.102 Eligible project costs. (a) Eligible costs are: (1) Those costs that.... (b) In determining the overall total cost of an Eligible Project, DOE and the applicant may include...

  2. 10 CFR 611.102 - Eligible project costs.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 10 Energy 4 2012-01-01 2012-01-01 false Eligible project costs. 611.102 Section 611.102 Energy... PROGRAM Direct Loan Program § 611.102 Eligible project costs. (a) Eligible costs are: (1) Those costs that.... (b) In determining the overall total cost of an Eligible Project, DOE and the applicant may include...

  3. 10 CFR 611.102 - Eligible project costs.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 10 Energy 4 2013-01-01 2013-01-01 false Eligible project costs. 611.102 Section 611.102 Energy... PROGRAM Direct Loan Program § 611.102 Eligible project costs. (a) Eligible costs are: (1) Those costs that.... (b) In determining the overall total cost of an Eligible Project, DOE and the applicant may include...

  4. 10 CFR 611.102 - Eligible project costs.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 10 Energy 4 2011-01-01 2011-01-01 false Eligible project costs. 611.102 Section 611.102 Energy... PROGRAM Direct Loan Program § 611.102 Eligible project costs. (a) Eligible costs are: (1) Those costs that.... (b) In determining the overall total cost of an Eligible Project, DOE and the applicant may include...

  5. 18 CFR 4.3 - Report on project cost.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 18 Conservation of Power and Water Resources 1 2012-04-01 2012-04-01 false Report on project cost... OF PROJECT COSTS Determination of Cost of Projects Constructed Under License § 4.3 Report on project..., cost records, engineering reports, and other records supporting the project's original cost. The audit...

  6. 18 CFR 4.3 - Report on project cost.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 18 Conservation of Power and Water Resources 1 2013-04-01 2013-04-01 false Report on project cost... OF PROJECT COSTS Determination of Cost of Projects Constructed Under License § 4.3 Report on project..., cost records, engineering reports, and other records supporting the project's original cost. The audit...

  7. 18 CFR 4.3 - Report on project cost.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 18 Conservation of Power and Water Resources 1 2014-04-01 2014-04-01 false Report on project cost... OF PROJECT COSTS Determination of Cost of Projects Constructed Under License § 4.3 Report on project..., cost records, engineering reports, and other records supporting the project's original cost. The audit...

  8. 18 CFR 4.3 - Report on project cost.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 18 Conservation of Power and Water Resources 1 2011-04-01 2011-04-01 false Report on project cost... OF PROJECT COSTS Determination of Cost of Projects Constructed Under License § 4.3 Report on project..., cost records, engineering reports, and other records supporting the project's original cost. The audit...

  9. 24 CFR 941.306 - Maximum project cost.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ...) project costs that are subject to the TDC limit (i.e., Housing Construction Costs and Community Renewal... project, the actual project cost is determined based upon the amount of public housing capital assistance... Community Renewal Costs in excess of the TDC limit, as determined under paragraph (b)(2) of this section...

  10. 24 CFR 941.306 - Maximum project cost.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ...) project costs that are subject to the TDC limit (i.e., Housing Construction Costs and Community Renewal... project, the actual project cost is determined based upon the amount of public housing capital assistance... Community Renewal Costs in excess of the TDC limit, as determined under paragraph (b)(2) of this section...

  11. 24 CFR 92.206 - Eligible project costs.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 24 Housing and Urban Development 1 2014-04-01 2014-04-01 false Eligible project costs. 92.206....206 Eligible project costs. HOME funds may be used to pay the following eligible costs: (a... following: (1) For new construction projects, costs to meet the new construction standards in § 92.251; (2...

  12. Data Flow in Relation to Life-Cycle Costing of Construction Projects in the Czech Republic

    NASA Astrophysics Data System (ADS)

    Biolek, Vojtěch; Hanák, Tomáš; Marović, Ivan

    2017-10-01

    Life-cycle costing is an important part of every construction project, as it makes it possible to take into consideration future costs relating to the operation and demolition phase of a built structure. In this way, investors can optimize the project design to minimize the total project costs. Even though there have already been some attempts to implement BIM software in the Czech Republic, the current state of affairs does not support automated data flow between the bill of costs and applications that support building facility management. The main aim of this study is to critically evaluate the current situation and outline a future framework that should allow for the use of the data contained in the bill of costs to manage building operating costs.

  13. 14 CFR 151.125 - Allowable advance planning costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 14 Aeronautics and Space 3 2010-01-01 2010-01-01 false Allowable advance planning costs. 151.125 Section 151.125 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION, DEPARTMENT OF TRANSPORTATION... as preliminary topographic and soil exploration; (2) Site evaluation; (3) Preliminary engineering...

  14. 14 CFR 151.125 - Allowable advance planning costs.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 14 Aeronautics and Space 3 2011-01-01 2011-01-01 false Allowable advance planning costs. 151.125 Section 151.125 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION, DEPARTMENT OF TRANSPORTATION... as preliminary topographic and soil exploration; (2) Site evaluation; (3) Preliminary engineering...

  15. 14 CFR 151.125 - Allowable advance planning costs.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 14 Aeronautics and Space 3 2014-01-01 2014-01-01 false Allowable advance planning costs. 151.125 Section 151.125 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION, DEPARTMENT OF TRANSPORTATION... as preliminary topographic and soil exploration; (2) Site evaluation; (3) Preliminary engineering...

  16. 14 CFR 151.125 - Allowable advance planning costs.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 14 Aeronautics and Space 3 2012-01-01 2012-01-01 false Allowable advance planning costs. 151.125 Section 151.125 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION, DEPARTMENT OF TRANSPORTATION... as preliminary topographic and soil exploration; (2) Site evaluation; (3) Preliminary engineering...

  17. 14 CFR 151.125 - Allowable advance planning costs.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 14 Aeronautics and Space 3 2013-01-01 2013-01-01 false Allowable advance planning costs. 151.125 Section 151.125 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION, DEPARTMENT OF TRANSPORTATION... as preliminary topographic and soil exploration; (2) Site evaluation; (3) Preliminary engineering...

  18. 7 CFR 4288.12 - Ineligible project costs.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 7 Agriculture 15 2014-01-01 2014-01-01 false Ineligible project costs. 4288.12 Section 4288.12 Agriculture Regulations of the Department of Agriculture (Continued) RURAL BUSINESS-COOPERATIVE SERVICE AND... Eligible Biorefineries § 4288.12 Ineligible project costs. Any project costs incurred by the applicant...

  19. 7 CFR 4288.12 - Ineligible project costs.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 7 Agriculture 15 2013-01-01 2013-01-01 false Ineligible project costs. 4288.12 Section 4288.12 Agriculture Regulations of the Department of Agriculture (Continued) RURAL BUSINESS-COOPERATIVE SERVICE AND... Eligible Biorefineries § 4288.12 Ineligible project costs. Any project costs incurred by the applicant...

  20. 7 CFR 4288.12 - Ineligible project costs.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 7 Agriculture 15 2012-01-01 2012-01-01 false Ineligible project costs. 4288.12 Section 4288.12 Agriculture Regulations of the Department of Agriculture (Continued) RURAL BUSINESS-COOPERATIVE SERVICE AND... Eligible Biorefineries § 4288.12 Ineligible project costs. Any project costs incurred by the applicant...

  1. 40 CFR 310.11 - What costs are allowable?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 40 Protection of Environment 28 2011-07-01 2011-07-01 false What costs are allowable? 310.11 Section 310.11 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) SUPERFUND, EMERGENCY PLANNING, AND COMMUNITY RIGHT-TO-KNOW PROGRAMS REIMBURSEMENT TO LOCAL GOVERNMENTS FOR EMERGENCY RESPONSE TO...

  2. 40 CFR 310.11 - What costs are allowable?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 40 Protection of Environment 29 2012-07-01 2012-07-01 false What costs are allowable? 310.11 Section 310.11 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) SUPERFUND, EMERGENCY PLANNING, AND COMMUNITY RIGHT-TO-KNOW PROGRAMS REIMBURSEMENT TO LOCAL GOVERNMENTS FOR EMERGENCY RESPONSE TO...

  3. 34 CFR 390.41 - What are allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 34 Education 2 2010-07-01 2010-07-01 false What are allowable costs? 390.41 Section 390.41 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF SPECIAL EDUCATION AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION REHABILITATION SHORT-TERM TRAINING What...

  4. 34 CFR 386.32 - What are allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 34 Education 2 2010-07-01 2010-07-01 false What are allowable costs? 386.32 Section 386.32 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF SPECIAL EDUCATION AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION REHABILITATION TRAINING: REHABILITATION LONG-TERM...

  5. 34 CFR 387.41 - What are allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 34 Education 2 2010-07-01 2010-07-01 false What are allowable costs? 387.41 Section 387.41 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF SPECIAL EDUCATION AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION EXPERIMENTAL AND INNOVATIVE TRAINING What...

  6. 48 CFR 831.7001 - Allowable costs under cost reimbursement vocational rehabilitation and education contracts or...

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 5 2010-10-01 2010-10-01 false Allowable costs under cost reimbursement vocational rehabilitation and education contracts or agreements. 831.7001 Section 831.7001 Federal... reimbursement vocational rehabilitation and education contracts or agreements. ...

  7. Sensitivities of projected 1980 photovoltaic system costs to major system cost drivers

    NASA Technical Reports Server (NTRS)

    Zimmerman, L. W.; Smith, J. L.

    1984-01-01

    The sensitivity of projected 1990 photovoltaic (PV) system costs to major system cost drivers was examined. It includes: (1) module costs and module efficiencies; (2) area related balance of system (BOS) costs; (3) inverter costs and efficiencies; and (4) module marketing and distribution markups and system integration fees. Recent PV system cost experiences and the high costs of electricity from the systems are reviewed. The 1990 system costs are projected for five classes of PV systems, including four ground mounted 5-MWp systems and one residential 5-kWp system. System cost projections are derived by first projecting costs and efficiencies for all subsystems and components. Sensitivity analyses reveal that reductions in module cost and engineering and system integration fees seem to have the greatest potential for contributing to system cost reduction. Although module cost is clearly the prime candidate for fruitful PV research and development activities, engineering and system integration fees seem to be more amenable to reduction through appropriate choice of system size and market strategy. Increases in inverter and module efficiency yield significant benefits, especially for systems with high area related costs.

  8. 78 FR 60173 - Federal Acquisition Regulation; Allowability of Legal Costs for Whistleblower Proceedings

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-09-30

    ... certified cost or pricing data for acquisitions that do not exceed the simplified acquisition threshold is...-AM64 Federal Acquisition Regulation; Allowability of Legal Costs for Whistleblower Proceedings AGENCY... (NDAA) for Fiscal Year (FY) 2013 that addresses the allowability of legal costs incurred by a contractor...

  9. 10 CFR 611.102 - Eligible project costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... Accounting Principles and these costs may be considered by DOE in determining the Borrower's contribution to... 10 Energy 4 2010-01-01 2010-01-01 false Eligible project costs. 611.102 Section 611.102 Energy... PROGRAM Direct Loan Program § 611.102 Eligible project costs. (a) Eligible costs are: (1) Those costs that...

  10. 34 CFR 371.41 - What are allowable costs?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 34 Education 2 2013-07-01 2013-07-01 false What are allowable costs? 371.41 Section 371.41 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF SPECIAL EDUCATION... AMERICAN INDIANS WITH DISABILITIES What Conditions Apply to a Grantee Under This Program? § 371.41 What are...

  11. 34 CFR 371.41 - What are allowable costs?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 34 Education 2 2012-07-01 2012-07-01 false What are allowable costs? 371.41 Section 371.41 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF SPECIAL EDUCATION... AMERICAN INDIANS WITH DISABILITIES What Conditions Apply to a Grantee Under This Program? § 371.41 What are...

  12. 34 CFR 371.41 - What are allowable costs?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 34 Education 2 2014-07-01 2013-07-01 true What are allowable costs? 371.41 Section 371.41 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF SPECIAL EDUCATION... AMERICAN INDIANS WITH DISABILITIES What Conditions Apply to a Grantee Under This Program? § 371.41 What are...

  13. 36 CFR 64.9 - Project costs (State and local projects).

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... appropriate conveyance. Project-related planning costs outlined in § 64.9(a)(3), may be incurred prior to...) Construction costs associated with developing the right-of-way for recreation use. (3) Project-related planning required for the acquisition, development and use of the abandoned rights-of-way including master planning...

  14. 7 CFR 1942.115 - Reasonable project costs.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 7 Agriculture 13 2013-01-01 2013-01-01 false Reasonable project costs. 1942.115 Section 1942.115...) PROGRAM REGULATIONS (CONTINUED) ASSOCIATIONS Fire and Rescue and Other Small Community Facilities Projects § 1942.115 Reasonable project costs. Applicants are responsible for determining that prices paid for...

  15. 7 CFR 1942.115 - Reasonable project costs.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 7 Agriculture 13 2014-01-01 2013-01-01 true Reasonable project costs. 1942.115 Section 1942.115...) PROGRAM REGULATIONS (CONTINUED) ASSOCIATIONS Fire and Rescue and Other Small Community Facilities Projects § 1942.115 Reasonable project costs. Applicants are responsible for determining that prices paid for...

  16. 7 CFR 1942.115 - Reasonable project costs.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 7 Agriculture 13 2011-01-01 2009-01-01 true Reasonable project costs. 1942.115 Section 1942.115...) PROGRAM REGULATIONS (CONTINUED) ASSOCIATIONS Fire and Rescue and Other Small Community Facilities Projects § 1942.115 Reasonable project costs. Applicants are responsible for determining that prices paid for...

  17. 7 CFR 1942.115 - Reasonable project costs.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 7 Agriculture 13 2012-01-01 2012-01-01 false Reasonable project costs. 1942.115 Section 1942.115...) PROGRAM REGULATIONS (CONTINUED) ASSOCIATIONS Fire and Rescue and Other Small Community Facilities Projects § 1942.115 Reasonable project costs. Applicants are responsible for determining that prices paid for...

  18. 7 CFR 1942.115 - Reasonable project costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 7 Agriculture 13 2010-01-01 2009-01-01 true Reasonable project costs. 1942.115 Section 1942.115...) PROGRAM REGULATIONS (CONTINUED) ASSOCIATIONS Fire and Rescue and Other Small Community Facilities Projects § 1942.115 Reasonable project costs. Applicants are responsible for determining that prices paid for...

  19. A life cycle cost economics model for projects with uniformly varying operating costs. [management planning

    NASA Technical Reports Server (NTRS)

    Remer, D. S.

    1977-01-01

    A mathematical model is developed for calculating the life cycle costs for a project where the operating costs increase or decrease in a linear manner with time. The life cycle cost is shown to be a function of the investment costs, initial operating costs, operating cost gradient, project life time, interest rate for capital and salvage value. The results show that the life cycle cost for a project can be grossly underestimated (or overestimated) if the operating costs increase (or decrease) uniformly over time rather than being constant as is often assumed in project economic evaluations. The following range of variables is examined: (1) project life from 2 to 30 years; (2) interest rate from 0 to 15 percent per year; and (3) operating cost gradient from 5 to 90 percent of the initial operating costs. A numerical example plus tables and graphs is given to help calculate project life cycle costs over a wide range of variables.

  20. The Vital Role of Administrative Cost Allowances to Student Financial Aid Offices: Key Findings from NASFAA's Administrative Cost Allowance Survey, July 2011

    ERIC Educational Resources Information Center

    National Association of Student Financial Aid Administrators (NJ1), 2011

    2011-01-01

    The National Association of Student Financial Aid Administrators (NASFAA) recently conducted a survey on the 2009-10 award year Administrative Cost Allowances (ACA), which are funds used by colleges and universities to support operations and professional development. Specifically, ACA is often used in essential areas that support the day-to-day…

  1. 48 CFR 52.216-7 - Allowable Cost and Payment.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... last disclosure of internal audit reports to the Government. (J) Annual internal audit plan of...-contract cost allowability limitations, and billing limitations. (v) The Contractor shall update the billings on all contracts to reflect the final settled rates and update the schedule of cumulative direct...

  2. Social cost in construction projects

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Çelik, Tolga, E-mail: tolga.celik@emu.edu.tr; Kamali, Saeed, E-mail: saeedkamali2002@gmail.com; Arayici, Yusuf, E-mail: yusuf.arayici@hku.edu.tr

    Despite the fact that completion of construction projects has a direct positive impact on the growth of national and local economies as well as humans' wellbeing, construction projects, especially in the urban areas, generate serious environmental nuisances for the adjacent residents and have unintentional adverse impacts on their surrounding environment. Construction causative adverse impacts on the neighbouring communities are known as the social costs. This study aims to present a state-of-the-art overview of social costs in construction industry in terms of definition, consideration, classification and quantification. Furthermore, it is aimed to bring the construction social cost phenomenon for the agendamore » of Environmental Impact Assessors.« less

  3. Error Cost Escalation Through the Project Life Cycle

    NASA Technical Reports Server (NTRS)

    Stecklein, Jonette M.; Dabney, Jim; Dick, Brandon; Haskins, Bill; Lovell, Randy; Moroney, Gregory

    2004-01-01

    It is well known that the costs to fix errors increase as the project matures, but how fast do those costs build? A study was performed to determine the relative cost of fixing errors discovered during various phases of a project life cycle. This study used three approaches to determine the relative costs: the bottom-up cost method, the total cost breakdown method, and the top-down hypothetical project method. The approaches and results described in this paper presume development of a hardware/software system having project characteristics similar to those used in the development of a large, complex spacecraft, a military aircraft, or a small communications satellite. The results show the degree to which costs escalate, as errors are discovered and fixed at later and later phases in the project life cycle. If the cost of fixing a requirements error discovered during the requirements phase is defined to be 1 unit, the cost to fix that error if found during the design phase increases to 3 - 8 units; at the manufacturing/build phase, the cost to fix the error is 7 - 16 units; at the integration and test phase, the cost to fix the error becomes 21 - 78 units; and at the operations phase, the cost to fix the requirements error ranged from 29 units to more than 1500 units

  4. 50 CFR 86.44 - What are my allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 50 Wildlife and Fisheries 6 2010-10-01 2010-10-01 false What are my allowable costs? 86.44 Section 86.44 Wildlife and Fisheries UNITED STATES FISH AND WILDLIFE SERVICE, DEPARTMENT OF THE INTERIOR (CONTINUED) FINANCIAL ASSISTANCE-WILDLIFE SPORT FISH RESTORATION PROGRAM BOATING INFRASTRUCTURE GRANT (BIG...

  5. 34 CFR 388.31 - What are the allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 34 Education 2 2010-07-01 2010-07-01 false What are the allowable costs? 388.31 Section 388.31 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF SPECIAL EDUCATION AND REHABILITATIVE SERVICES, DEPARTMENT OF EDUCATION STATE VOCATIONAL REHABILITATION UNIT IN-SERVICE...

  6. Project Cost Estimation for Planning

    DOT National Transportation Integrated Search

    2010-02-26

    For Nevada Department of Transportation (NDOT), there are far too many projects that ultimately cost much more than initially planned. Because project nominations are linked to estimates of future funding and the analysis of system needs, the inaccur...

  7. Social cost impact assessment of pipeline infrastructure projects

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Matthews, John C., E-mail: matthewsj@battelle.org; Allouche, Erez N., E-mail: allouche@latech.edu; Sterling, Raymond L., E-mail: sterling@latech.edu

    A key advantage of trenchless construction methods compared with traditional open-cut methods is their ability to install or rehabilitate underground utility systems with limited disruption to the surrounding built and natural environments. The equivalent monetary values of these disruptions are commonly called social costs. Social costs are often ignored by engineers or project managers during project planning and design phases, partially because they cannot be calculated using standard estimating methods. In recent years some approaches for estimating social costs were presented. Nevertheless, the cost data needed for validation of these estimating methods is lacking. Development of such social cost databasesmore » can be accomplished by compiling relevant information reported in various case histories. This paper identifies eight most important social cost categories, presents mathematical methods for calculating them, and summarizes the social cost impacts for two pipeline construction projects. The case histories are analyzed in order to identify trends for the various social cost categories. The effectiveness of the methods used to estimate these values is also discussed. These findings are valuable for pipeline infrastructure engineers making renewal technology selection decisions by providing a more accurate process for the assessment of social costs and impacts. - Highlights: • Identified the eight most important social cost factors for pipeline construction • Presented mathematical methods for calculating those social cost factors • Summarized social cost impacts for two pipeline construction projects • Analyzed those projects to identify trends for the social cost factors.« less

  8. Why Don't They Just Give Us Money? Project Cost Estimating and Cost Reporting

    NASA Technical Reports Server (NTRS)

    Comstock, Douglas A.; Van Wychen, Kristin; Zimmerman, Mary Beth

    2015-01-01

    Successful projects require an integrated approach to managing cost, schedule, and risk. This is especially true for complex, multi-year projects involving multiple organizations. To explore solutions and leverage valuable lessons learned, NASA's Virtual Project Management Challenge will kick off a three-part series examining some of the challenges faced by project and program managers when it comes to managing these important elements. In this first session of the series, we will look at cost management, with an emphasis on the critical roles of cost estimating and cost reporting. By taking a proactive approach to both of these activities, project managers can better control life cycle costs, maintain stakeholder confidence, and protect other current and future projects in the organization's portfolio. Speakers will be Doug Comstock, Director of NASA's Cost Analysis Division, Kristin Van Wychen, Senior Analyst in the GAO Acquisition and Sourcing Management Team, and Mary Beth Zimmerman, Branch Chief for NASA's Portfolio Analysis Branch, Strategic Investments Division. Moderator Ramien Pierre is from NASA's Academy for Program/Project and Engineering Leadership (APPEL).

  9. 25 CFR 700.469 - Unallowable program and project costs.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 25 Indians 2 2013-04-01 2013-04-01 false Unallowable program and project costs. 700.469 Section... PROCEDURES Discretionary Funds § 700.469 Unallowable program and project costs. Costs for program or project... application for a demonstration effort under § 700.459 may include costs relating to the operation of the...

  10. 25 CFR 700.469 - Unallowable program and project costs.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 25 Indians 2 2011-04-01 2011-04-01 false Unallowable program and project costs. 700.469 Section... PROCEDURES Discretionary Funds § 700.469 Unallowable program and project costs. Costs for program or project... application for a demonstration effort under § 700.459 may include costs relating to the operation of the...

  11. 25 CFR 700.469 - Unallowable program and project costs.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 25 Indians 2 2012-04-01 2012-04-01 false Unallowable program and project costs. 700.469 Section... PROCEDURES Discretionary Funds § 700.469 Unallowable program and project costs. Costs for program or project... application for a demonstration effort under § 700.459 may include costs relating to the operation of the...

  12. 25 CFR 700.469 - Unallowable program and project costs.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 25 Indians 2 2014-04-01 2014-04-01 false Unallowable program and project costs. 700.469 Section... PROCEDURES Discretionary Funds § 700.469 Unallowable program and project costs. Costs for program or project... application for a demonstration effort under § 700.459 may include costs relating to the operation of the...

  13. Minimizing Project Cost by Integrating Subcontractor Selection Decisions with Scheduling

    NASA Astrophysics Data System (ADS)

    Biruk, Sławomir; Jaśkowski, Piotr; Czarnigowska, Agata

    2017-10-01

    Subcontracting has been a worldwide practice in the construction industry. It enables the construction enterprises to focus on their core competences and, at the same time, it makes complex project possible to be delivered. Since general contractors bear full responsibility for the works carried out by their subcontractors, it is their task and their risk to select a right subcontractor for a particular work. Although subcontractor management has been admitted to significantly affect the construction project’s performance, current practices and past research deal with subcontractor management and scheduling separately. The proposed model aims to support subcontracting decisions by integrating subcontractor selection with scheduling to enable the general contractor to select the optimal combination of subcontractors and own crews for all work packages of the project. The model allows for the interactions between the subcontractors and their impacts on the overall project performance in terms of cost and, indirectly, time and quality. The model is intended to be used at the general contractor’s bid preparation stage. The authors claim that the subcontracting decisions should be taken in a two-stage process. The first stage is a prequalification - provision of a short list of capable and reliable subcontractors; this stage is not the focus of the paper. The resulting pool of available resources is divided into two subsets: subcontractors, and general contractor’s in-house crews. Once it has been defined, the next stage is to assign them to the work packages that, bound by fixed precedence constraints, form the project’s network diagram. Each package is possible to be delivered by the general contractor’s crew or some of the potential subcontractors, at a specific time and cost. Particular crews and subcontractors can be contracted more than one package, but not at the same time. Other constraints include the predefined project completion date (the project is

  14. Why projects often fail even with high cost contingencies

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Kujawski, Edouard

    2002-02-28

    In this note we assume that the individual risks have been adequately quantified and the total project cost contingency adequately computed to ensure an agreed-to probability or confidence level that the total project cost estimate will not be exceeded. But even projects that implement such a process are likely to result in significant cost overruns and/or project failure if the project manager allocates the contingencies to the individual subsystems. The intuitive and mathematically valid solution is to maintain a project-wide contingency and to distribute it to the individual risks on an as-needed basis. Such an approach ensures cost-efficient risk management,more » and projects that implement it are more likely to succeed and to cost less. We illustrate these ideas using a simplified project with two independent risks. The formulation can readily be extended to multiple risks.« less

  15. Assessing the costs attributed to project delay during project pre-construction stages

    DOT National Transportation Integrated Search

    2016-03-01

    This project for the Texas Department of Transportation (TxDOT) developed a simple but sound : methodology for estimating the cost of delaying most types of highway projects. Researchers considered the : cost of delays during the pre-construction pha...

  16. Assessing the costs attributed to project delay during project pre-construction stages.

    DOT National Transportation Integrated Search

    2016-03-01

    This project for the Texas Department of Transportation (TxDOT) developed a simple but sound : methodology for estimating the cost of delaying most types of highway projects. Researchers considered the : cost of delays during the pre-construction pha...

  17. 23 CFR 505.13 - Federal Government's share of project cost.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 23 Highways 1 2012-04-01 2012-04-01 false Federal Government's share of project cost. 505.13... Government's share of project cost. (a) Based on engineering studies, studies of economic feasibility, and... eligible costs. (b) A FFGA for the project shall not exceed 80 percent of the eligible project cost. A...

  18. 23 CFR 505.13 - Federal Government's share of project cost.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 23 Highways 1 2014-04-01 2014-04-01 false Federal Government's share of project cost. 505.13... Government's share of project cost. (a) Based on engineering studies, studies of economic feasibility, and... eligible costs. (b) A FFGA for the project shall not exceed 80 percent of the eligible project cost. A...

  19. 23 CFR 505.13 - Federal Government's share of project cost.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 23 Highways 1 2013-04-01 2013-04-01 false Federal Government's share of project cost. 505.13... Government's share of project cost. (a) Based on engineering studies, studies of economic feasibility, and... eligible costs. (b) A FFGA for the project shall not exceed 80 percent of the eligible project cost. A...

  20. 23 CFR 505.13 - Federal Government's share of project cost.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 23 Highways 1 2011-04-01 2011-04-01 false Federal Government's share of project cost. 505.13... Government's share of project cost. (a) Based on engineering studies, studies of economic feasibility, and... eligible costs. (b) A FFGA for the project shall not exceed 80 percent of the eligible project cost. A...

  1. 15 CFR 2301.7 - Eligible and ineligible project costs.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 15 Commerce and Foreign Trade 3 2012-01-01 2012-01-01 false Eligible and ineligible project costs... TELECOMMUNICATIONS FACILITIES PROGRAM Application Requirements § 2301.7 Eligible and ineligible project costs. (a... wherever the two types of apparatus interface. (c) Total project costs do not include the value of eligible...

  2. 15 CFR 2301.7 - Eligible and ineligible project costs.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 15 Commerce and Foreign Trade 3 2011-01-01 2011-01-01 false Eligible and ineligible project costs... TELECOMMUNICATIONS FACILITIES PROGRAM Application Requirements § 2301.7 Eligible and ineligible project costs. (a... wherever the two types of apparatus interface. (c) Total project costs do not include the value of eligible...

  3. 15 CFR 2301.7 - Eligible and ineligible project costs.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 15 Commerce and Foreign Trade 3 2014-01-01 2014-01-01 false Eligible and ineligible project costs... TELECOMMUNICATIONS FACILITIES PROGRAM Application Requirements § 2301.7 Eligible and ineligible project costs. (a... wherever the two types of apparatus interface. (c) Total project costs do not include the value of eligible...

  4. 15 CFR 2301.7 - Eligible and ineligible project costs.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 15 Commerce and Foreign Trade 3 2013-01-01 2013-01-01 false Eligible and ineligible project costs... TELECOMMUNICATIONS FACILITIES PROGRAM Application Requirements § 2301.7 Eligible and ineligible project costs. (a... wherever the two types of apparatus interface. (c) Total project costs do not include the value of eligible...

  5. 15 CFR 2301.7 - Eligible and ineligible project costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 15 Commerce and Foreign Trade 3 2010-01-01 2010-01-01 false Eligible and ineligible project costs... TELECOMMUNICATIONS FACILITIES PROGRAM Application Requirements § 2301.7 Eligible and ineligible project costs. (a... wherever the two types of apparatus interface. (c) Total project costs do not include the value of eligible...

  6. Software for Tracking Costs of Mars Projects

    NASA Technical Reports Server (NTRS)

    Wong, Alvin; Warfield, Keith

    2003-01-01

    The Mars Cost Tracking Model is a computer program that administers a system set up for tracking the costs of future NASA projects that pertain to Mars. Previously, no such tracking system existed, and documentation was written in a variety of formats and scattered in various places. It was difficult to justify costs or even track the history of costs of a spacecraft mission to Mars. The present software enables users to maintain all cost-model definitions, documentation, and justifications of cost estimates in one computer system that is accessible via the Internet. The software provides sign-off safeguards to ensure the reliability of information entered into the system. This system may eventually be used to track the costs of projects other than only those that pertain to Mars.

  7. 42 CFR 413.134 - Depreciation: Allowance for depreciation based on asset costs.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 42 Public Health 2 2013-10-01 2013-10-01 false Depreciation: Allowance for depreciation based on asset costs. 413.134 Section 413.134 Public Health CENTERS FOR MEDICARE & MEDICAID SERVICES, DEPARTMENT OF HEALTH AND HUMAN SERVICES MEDICARE PROGRAM PRINCIPLES OF REASONABLE COST REIMBURSEMENT; PAYMENT...

  8. 42 CFR 413.134 - Depreciation: Allowance for depreciation based on asset costs.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 42 Public Health 2 2014-10-01 2014-10-01 false Depreciation: Allowance for depreciation based on asset costs. 413.134 Section 413.134 Public Health CENTERS FOR MEDICARE & MEDICAID SERVICES, DEPARTMENT OF HEALTH AND HUMAN SERVICES MEDICARE PROGRAM PRINCIPLES OF REASONABLE COST REIMBURSEMENT; PAYMENT...

  9. 42 CFR 413.134 - Depreciation: Allowance for depreciation based on asset costs.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 42 Public Health 2 2011-10-01 2011-10-01 false Depreciation: Allowance for depreciation based on asset costs. 413.134 Section 413.134 Public Health CENTERS FOR MEDICARE & MEDICAID SERVICES, DEPARTMENT OF HEALTH AND HUMAN SERVICES MEDICARE PROGRAM PRINCIPLES OF REASONABLE COST REIMBURSEMENT; PAYMENT...

  10. 42 CFR 413.134 - Depreciation: Allowance for depreciation based on asset costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 42 Public Health 2 2010-10-01 2010-10-01 false Depreciation: Allowance for depreciation based on asset costs. 413.134 Section 413.134 Public Health CENTERS FOR MEDICARE & MEDICAID SERVICES, DEPARTMENT OF HEALTH AND HUMAN SERVICES MEDICARE PROGRAM PRINCIPLES OF REASONABLE COST REIMBURSEMENT; PAYMENT...

  11. 42 CFR 413.134 - Depreciation: Allowance for depreciation based on asset costs.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 42 Public Health 2 2012-10-01 2012-10-01 false Depreciation: Allowance for depreciation based on asset costs. 413.134 Section 413.134 Public Health CENTERS FOR MEDICARE & MEDICAID SERVICES, DEPARTMENT OF HEALTH AND HUMAN SERVICES MEDICARE PROGRAM PRINCIPLES OF REASONABLE COST REIMBURSEMENT; PAYMENT...

  12. 44 CFR 208.23 - Allowable costs under Preparedness Cooperative Agreements.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 44 Emergency Management and Assistance 1 2011-10-01 2011-10-01 false Allowable costs under Preparedness Cooperative Agreements. 208.23 Section 208.23 Emergency Management and Assistance FEDERAL EMERGENCY MANAGEMENT AGENCY, DEPARTMENT OF HOMELAND SECURITY DISASTER ASSISTANCE NATIONAL URBAN SEARCH AND...

  13. 18 CFR 4.3 - Report on project cost.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 18 Conservation of Power and Water Resources 1 2010-04-01 2010-04-01 false Report on project cost. 4.3 Section 4.3 Conservation of Power and Water Resources FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY REGULATIONS UNDER THE FEDERAL POWER ACT LICENSES, PERMITS, EXEMPTIONS, AND DETERMINATION OF PROJECT COSTS Determination of Cost of...

  14. Improving Space Project Cost Estimating with Engineering Management Variables

    NASA Technical Reports Server (NTRS)

    Hamaker, Joseph W.; Roth, Axel (Technical Monitor)

    2001-01-01

    Current space project cost models attempt to predict space flight project cost via regression equations, which relate the cost of projects to technical performance metrics (e.g. weight, thrust, power, pointing accuracy, etc.). This paper examines the introduction of engineering management parameters to the set of explanatory variables. A number of specific engineering management variables are considered and exploratory regression analysis is performed to determine if there is statistical evidence for cost effects apart from technical aspects of the projects. It is concluded that there are other non-technical effects at work and that further research is warranted to determine if it can be shown that these cost effects are definitely related to engineering management.

  15. Costing Future Complex and Novel Projects

    DTIC Science & Technology

    2016-04-30

    qÜáêíÉÉåíÜ=^ååì~ä= ^Åèìáëáíáçå=oÉëÉ~êÅÜ= póãéçëáìã= qÜìêëÇ~ó=pÉëëáçåë= sçäìãÉ=ff= = Costing Future Complex & Novel Projects Michael Pryce, Centre for Defence ...Novel Projects Michael Pryce, Centre for Defence Acquisition, Cranfield University Controlling Costs: The 6-3-5 Method—Case Studies at NAVSEA and...a Lecturer in defence acquisition at Cranfield University. He teaches across a range of subjects, including the use of costing in acquisition and

  16. Analysis of Student Loan Special Rate Allowances and Servicing Costs.

    ERIC Educational Resources Information Center

    Technology Management, Inc., Cambridge, MA.

    This document addresses two separate, though related aspects of the operation of the Guaranteed Student Loan Program (GSLP): (1) the mechanism for setting the special rate allowance (SRA); and (2) the effect of the operating requirements of the program on lender servicing costs. The study develops recommendations for improving both aspects of the…

  17. 42 CFR 495.308 - Net average allowable costs as the basis for determining the incentive payment.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 42 Public Health 5 2010-10-01 2010-10-01 false Net average allowable costs as the basis for... Net average allowable costs as the basis for determining the incentive payment. (a) The first year of payment. (1) The incentive is intended to offset the costs associated with the initial adoption...

  18. 2 CFR Appendix A to Part 225 - General Principles for Determining Allowable Costs

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... in the financing of a particular program or project. The principles are designed to provide that..., contract, grant, or other activity for which cost data are needed and for which costs are incurred. 12... Indian tribe, band, nation, or other organized group or community (including any native village as...

  19. 2 CFR Appendix A to Part 225 - General Principles for Determining Allowable Costs

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... in the financing of a particular program or project. The principles are designed to provide that..., contract, grant, or other activity for which cost data are needed and for which costs are incurred. 12... Indian tribe, band, nation, or other organized group or community (including any native village as...

  20. Correlation of Spacecraft Mission and Project Costs

    NASA Technical Reports Server (NTRS)

    Swan, Christopher; Jarrett, Shawn

    2007-01-01

    A key component of any cost risk analysis is the level of correlation between individual elements of cost. This analysis supplements the available historical records with the cost estimates from the JPL Advanced Design Team. The costs from actual JPL flight projects are then used to validate the results, clearly indicating that, on average, the correlation between elements of cost is between 0.4 and 0.7.

  1. 24 CFR 965.406 - Benefit/cost analysis for similar projects.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 24 Housing and Urban Development 4 2010-04-01 2010-04-01 false Benefit/cost analysis for similar... Existing PHA-Owned Projects § 965.406 Benefit/cost analysis for similar projects. PHAs with more than one project of similar design and utilities service may prepare a benefit/cost analysis for a representative...

  2. 23 CFR 661.39 - How are project cost overruns funded?

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 23 Highways 1 2012-04-01 2012-04-01 false How are project cost overruns funded? 661.39 Section 661... OPERATIONS INDIAN RESERVATION ROAD BRIDGE PROGRAM § 661.39 How are project cost overruns funded? (a) A request for additional IRRBP funds for cost overruns on a specific bridge project must be submitted to...

  3. 23 CFR 661.39 - How are project cost overruns funded?

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 23 Highways 1 2013-04-01 2013-04-01 false How are project cost overruns funded? 661.39 Section 661... OPERATIONS INDIAN RESERVATION ROAD BRIDGE PROGRAM § 661.39 How are project cost overruns funded? (a) A request for additional IRRBP funds for cost overruns on a specific bridge project must be submitted to...

  4. 23 CFR 661.39 - How are project cost overruns funded?

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 23 Highways 1 2014-04-01 2014-04-01 false How are project cost overruns funded? 661.39 Section 661... OPERATIONS INDIAN RESERVATION ROAD BRIDGE PROGRAM § 661.39 How are project cost overruns funded? (a) A request for additional IRRBP funds for cost overruns on a specific bridge project must be submitted to...

  5. 23 CFR 661.39 - How are project cost overruns funded?

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 23 Highways 1 2011-04-01 2011-04-01 false How are project cost overruns funded? 661.39 Section 661... OPERATIONS INDIAN RESERVATION ROAD BRIDGE PROGRAM § 661.39 How are project cost overruns funded? (a) A request for additional IRRBP funds for cost overruns on a specific bridge project must be submitted to...

  6. 23 CFR 661.39 - How are project cost overruns funded?

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... OPERATIONS INDIAN RESERVATION ROAD BRIDGE PROGRAM § 661.39 How are project cost overruns funded? (a) A request for additional IRRBP funds for cost overruns on a specific bridge project must be submitted to... 23 Highways 1 2010-04-01 2010-04-01 false How are project cost overruns funded? 661.39 Section 661...

  7. 14 CFR 151.24 - Procedures: Application; information on estimated project costs.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... estimated project costs. 151.24 Section 151.24 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION... Development Projects § 151.24 Procedures: Application; information on estimated project costs. (a) If any part of the estimated project costs consists of the value of donated land, labor, materials, or equipment...

  8. 14 CFR 151.24 - Procedures: Application; information on estimated project costs.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... estimated project costs. 151.24 Section 151.24 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION... Development Projects § 151.24 Procedures: Application; information on estimated project costs. (a) If any part of the estimated project costs consists of the value of donated land, labor, materials, or equipment...

  9. 14 CFR 151.24 - Procedures: Application; information on estimated project costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... estimated project costs. 151.24 Section 151.24 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION... Development Projects § 151.24 Procedures: Application; information on estimated project costs. (a) If any part of the estimated project costs consists of the value of donated land, labor, materials, or equipment...

  10. 14 CFR 151.24 - Procedures: Application; information on estimated project costs.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... estimated project costs. 151.24 Section 151.24 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION... Development Projects § 151.24 Procedures: Application; information on estimated project costs. (a) If any part of the estimated project costs consists of the value of donated land, labor, materials, or equipment...

  11. 14 CFR 151.24 - Procedures: Application; information on estimated project costs.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... estimated project costs. 151.24 Section 151.24 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION... Development Projects § 151.24 Procedures: Application; information on estimated project costs. (a) If any part of the estimated project costs consists of the value of donated land, labor, materials, or equipment...

  12. Benefit-cost evaluation of ITS projects : benefit-cost summary

    DOT National Transportation Integrated Search

    2000-10-01

    Over 60 individual ITS projects were defined in four "model" cities for purposes of conducting benefit-cost evalations of deployments under the USDOT's Metrolpolitan Model Deployment Initiative (MMDI). The federal government provided funds for deploy...

  13. Influence of the economy crisis on project cost management

    NASA Astrophysics Data System (ADS)

    Simankina, Tatyana; Ćetković, Jasmina; Verstina, Natalia; Evseev, Evgeny

    2017-10-01

    Economy crisis significantly affects primarily the project cost management. The article considers the problems of project management in the field of housing under conditions of economy crisis. Project budgets are reduced, their mutual interference grows and framework of risks changes. Apparently, specific approaches are required to be developed to optimize the expenses and guarantee the project implementation within the approved budget. There is considered domestic and foreign experience in terms of project cost management with involvement of BIM technologies.

  14. The Art of Projecting: The Cost of Keeping Periodicals.

    ERIC Educational Resources Information Center

    Ketcham, Lee; Born, Kathleen

    1993-01-01

    Provides periodical prices for 1993 and projects 1994 costs. Trends and projections, cost by country of origin, the role of foreign publications, currency fluctuations, and the basis for forecasting are discussed. Cost histories are given by subject area and country of publication. Prices of interest to smaller and public libraries are also given.…

  15. 21 CFR 1403.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    .... Contract Cost Principles and Procedures, or uniform cost accounting standards that comply with cost... COOPERATIVE AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial Administration § 1403...) Applicable cost principles. For each kind of organization, there is a set of Federal principles for...

  16. An economic toolkit for identifying the cost of emergency medical services (EMS) systems: detailed methodology of the EMS Cost Analysis Project (EMSCAP).

    PubMed

    Lerner, E Brooke; Garrison, Herbert G; Nichol, Graham; Maio, Ronald F; Lookman, Hunaid A; Sheahan, William D; Franz, Timothy R; Austad, James D; Ginster, Aaron M; Spaite, Daniel W

    2012-02-01

    Calculating the cost of an emergency medical services (EMS) system using a standardized method is important for determining the value of EMS. This article describes the development of a methodology for calculating the cost of an EMS system to its community. This includes a tool for calculating the cost of EMS (the "cost workbook") and detailed directions for determining cost (the "cost guide"). The 12-step process that was developed is consistent with current theories of health economics, applicable to prehospital care, flexible enough to be used in varying sizes and types of EMS systems, and comprehensive enough to provide meaningful conclusions. It was developed by an expert panel (the EMS Cost Analysis Project [EMSCAP] investigator team) in an iterative process that included pilot testing the process in three diverse communities. The iterative process allowed ongoing modification of the toolkit during the development phase, based upon direct, practical, ongoing interaction with the EMS systems that were using the toolkit. The resulting methodology estimates EMS system costs within a user-defined community, allowing either the number of patients treated or the estimated number of lives saved by EMS to be assessed in light of the cost of those efforts. Much controversy exists about the cost of EMS and whether the resources spent for this purpose are justified. However, the existence of a validated toolkit that provides a standardized process will allow meaningful assessments and comparisons to be made and will supply objective information to inform EMS and community officials who are tasked with determining the utilization of scarce societal resources. © 2012 by the Society for Academic Emergency Medicine.

  17. 34 CFR 642.40 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ...) Transportation costs for participants and training staff. (g) Lodging and subsistence costs for participants and training staff. (h) Transportation costs, lodging and subsistence costs and fees for consultants, if any..., DEPARTMENT OF EDUCATION TRAINING PROGRAM FOR FEDERAL TRIO PROGRAMS What Conditions Must Be Met by a Grantee...

  18. 45 CFR 602.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... CFR part 31. Contract Cost Principles and Procedures, or uniform cost accounting standards that comply.... (b) Applicable cost principles. For each kind of organization, there is a set of Federal principles... principles applicable to the organization incurring the costs. The following chart lists the kinds of...

  19. Low-cost Solar Array (LSA) project

    NASA Technical Reports Server (NTRS)

    1978-01-01

    Progress made by the Low-Cost Silicon Solar Array Project during the period January through March 1978 is reported. It includes task reports on silicon material processing, large-area silicon sheet development, encapsulation materials testing and development, project engineering and operations, and manufacturing techniques, plus the steps taken to integrate these efforts.

  20. Categorization of potential project cost overrun factors in construction industry

    NASA Astrophysics Data System (ADS)

    Karunakaran, P.; Abdullah, A. H.; Nagapan, S.; Sohu, S.; Kasvar, K. K.

    2018-04-01

    Cost overrun has been severely hit down the economy and reputations for many construction industry around the world. Many project management tools developed to control the budget of a project. However, the cost management is still considered poor as there are many cost overrun issues occurred in the construction industry. Thus, this paper aims to identify and cluster the potential construction project cost overrun factors according to their originating groups using the thematic approach. Basically, through literature review, all the potential factors that may cause cost overrun were screened thoroughly before they were clustered into seven (7) groups of the originating factors, namely project, contract, client, contractor, consultant, labour and external. Each potential factor was explained clearly with some examples based on the Malaysian case studies to illustrate the cost overrun scenario. These findings may aid in the future to highlight on how to mitigate the critical potential factors of cost overrun to reduce or overcome its impact on all the stakeholders involved.

  1. 34 CFR 280.41 - What are the limitations on allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 34 Education 1 2010-07-01 2010-07-01 false What are the limitations on allowable costs? 280.41 Section 280.41 Education Regulations of the Offices of the Department of Education OFFICE OF ELEMENTARY AND SECONDARY EDUCATION, DEPARTMENT OF EDUCATION MAGNET SCHOOLS ASSISTANCE PROGRAM What Conditions...

  2. 34 CFR 658.40 - What are the limitations on allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 34 Education 3 2010-07-01 2010-07-01 false What are the limitations on allowable costs? 658.40 Section 658.40 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION UNDERGRADUATE INTERNATIONAL STUDIES AND FOREIGN LANGUAGE...

  3. Improvement of the cost-benefit analysis algorithm for high-rise construction projects

    NASA Astrophysics Data System (ADS)

    Gafurov, Andrey; Skotarenko, Oksana; Plotnikov, Vladimir

    2018-03-01

    The specific nature of high-rise investment projects entailing long-term construction, high risks, etc. implies a need to improve the standard algorithm of cost-benefit analysis. An improved algorithm is described in the article. For development of the improved algorithm of cost-benefit analysis for high-rise construction projects, the following methods were used: weighted average cost of capital, dynamic cost-benefit analysis of investment projects, risk mapping, scenario analysis, sensitivity analysis of critical ratios, etc. This comprehensive approach helped to adapt the original algorithm to feasibility objectives in high-rise construction. The authors put together the algorithm of cost-benefit analysis for high-rise construction projects on the basis of risk mapping and sensitivity analysis of critical ratios. The suggested project risk management algorithms greatly expand the standard algorithm of cost-benefit analysis in investment projects, namely: the "Project analysis scenario" flowchart, improving quality and reliability of forecasting reports in investment projects; the main stages of cash flow adjustment based on risk mapping for better cost-benefit project analysis provided the broad range of risks in high-rise construction; analysis of dynamic cost-benefit values considering project sensitivity to crucial variables, improving flexibility in implementation of high-rise projects.

  4. 34 CFR 660.40 - What are the limitations on allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 34 Education 3 2010-07-01 2010-07-01 false What are the limitations on allowable costs? 660.40 Section 660.40 Education Regulations of the Offices of the Department of Education (Continued) OFFICE OF POSTSECONDARY EDUCATION, DEPARTMENT OF EDUCATION THE INTERNATIONAL RESEARCH AND STUDIES PROGRAM What Conditions...

  5. Allowing a wildfire to burn: estimating the effect on future fire suppression costs

    Treesearch

    Rachel M. Houtman; Claire A. Montgomery; Aaron R. Gagnon; David E. Calkin; Thomas G. Dietterich; Sean McGregor; Mark Crowley

    2013-01-01

    Where a legacy of aggressive wildland fire suppression has left forests in need of fuel reduction, allowing wildland fire to burn may provide fuel treatment benefits, thereby reducing suppression costs from subsequent fires. The least-cost-plus-net-value-change model of wildland fire economics includes benefits of wildfire in a framework for evaluating suppression...

  6. 28 CFR 100.11 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... Judicial Administration DEPARTMENT OF JUSTICE (CONTINUED) COST RECOVERY REGULATIONS, COMMUNICATIONS... reimbursement under section 109(e) CALEA are: (1) All reasonable plant costs directly associated with the... undergoes major modifications; (2) Additional reasonable plant costs directly associated with making the...

  7. 28 CFR 100.11 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... Judicial Administration DEPARTMENT OF JUSTICE (CONTINUED) COST RECOVERY REGULATIONS, COMMUNICATIONS... reimbursement under section 109(e) CALEA are: (1) All reasonable plant costs directly associated with the... undergoes major modifications; (2) Additional reasonable plant costs directly associated with making the...

  8. 10 CFR 600.222 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... part 31. Contract Cost Principles and Procedures, or uniform cost accounting standards that comply with... OF ENERGY (CONTINUED) ASSISTANCE REGULATIONS FINANCIAL ASSISTANCE RULES Uniform Administrative...) Applicable cost principles. For each kind of organization, there is a set of Federal principles for...

  9. Low-cost Solar Array (LSA) project

    NASA Technical Reports Server (NTRS)

    1978-01-01

    The activities of the Low-Cost Solar Array Project are described for the period April through June 1978. The Project is assigned responsibility for advancing solar array technology while encouraging industry to reduce the price of arrays to a level at which photovoltaic electric power systems will be competitive with more conventional power sources early in the next decade. Set forth are the goals and plans with which the Project intends to accomplish this and the progress that was made during the quarter.

  10. 28 CFR 66.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... part 31. Contract Cost Principles and Procedures, or uniform cost accounting standards that comply with... AND COOPERATIVE AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial...) Applicable cost principles. For each kind of organization, there is a set of Federal principles for...

  11. 20 CFR 437.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... CFR Part 31. Contract Cost Principles and Procedures, or uniform cost accounting standards that comply... COOPERATIVE AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial Administration § 437...) Applicable cost principles. For each kind of organization, there is a set of Federal principles for...

  12. 14 CFR 1273.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... CFR part 31, Contract Cost Principles and Procedures, or uniform cost accounting standards that comply... GRANTS AND COOPERATIVE AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial.... (b) Applicable cost principles. For each kind of organization, there is a set of Federal principles...

  13. 15 CFR 24.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... Part 31. Contract Cost Principles and Procedures, or uniform cost accounting standards that comply with... GRANTS AND COOPERATIVE AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial...) Applicable cost principles. For each kind of organization, there is a set of Federal principles for...

  14. 45 CFR 1174.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... Part 31. Contract Cost Principles and Procedures, or uniform cost accounting standards that comply with... COOPERATIVE AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial Administration § 1174...) Applicable cost principles. For each kind of organization, there is a set of Federal principles for...

  15. 45 CFR 1183.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... Part 31. Contract Cost Principles and Procedures, or uniform cost accounting standards that comply with... COOPERATIVE AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial Administration § 1183...) Applicable cost principles. For each kind of organization, there is a set of Federal principles for...

  16. 45 CFR 1157.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... Procedures, or uniform cost accounting standards that comply with cost principles acceptable to the Federal... AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial Administration § 1157.22... cost principles. For each kind of organization, there is a set of Federal principles for determining...

  17. 43 CFR 12.927 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 CFR part 31, Contract Principles and Procedures or uniform cost accounting standards that comply... COST PRINCIPLES FOR ASSISTANCE PROGRAMS Uniform Administrative Requirements for Grants and Agreements... Circular A-87, Cost Principles for State and Local Governments. Non-profit organization OMB Circular A-122...

  18. 49 CFR 18.22 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... Procedures, or uniform cost accounting standards that comply with cost principles acceptable to the Federal... COOPERATIVE AGREEMENTS TO STATE AND LOCAL GOVERNMENTS Post-Award Requirements Financial Administration § 18.22... cost principles. For each kind of organization, there is a set of Federal principles for determining...

  19. 23 CFR 505.13 - Federal Government's share of project cost.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... INFRASTRUCTURE MANAGEMENT PROJECTS OF NATIONAL AND REGIONAL SIGNIFICANCE EVALUATION AND RATING § 505.13 Federal Government's share of project cost. (a) Based on engineering studies, studies of economic feasibility, and... 23 Highways 1 2010-04-01 2010-04-01 false Federal Government's share of project cost. 505.13...

  20. LSA Low-cost Solar Array project

    NASA Technical Reports Server (NTRS)

    1978-01-01

    The activities of the Low-Cost Silicon Solar Array Project during the period October through December, 1977 are reported. The LSSA Project is assigned responsibility for advancing silicon solar array technology while encouraging industry to reduce the price of arrays to a level at which photovoltaic electric power systems will be competitive with more conventional power sources early in the next decade. Set forth are the goals and plans with which the Project intends to accomplish this and the progress that was made during the quarter.

  1. 50 CFR 80.83 - What is the Federal share of allowable costs?

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... ADMINISTRATIVE REQUIREMENTS, PITTMAN-ROBERTSON WILDLIFE RESTORATION AND DINGELL-JOHNSON SPORT FISH RESTORATION... costs of a grant-funded project in a program or subprogram authorized by the Dingell-Johnson Sport Fish... Mariana Islands and the territories of Guam, the U.S. Virgin Islands, and American Samoa. The Regional...

  2. 50 CFR 80.83 - What is the Federal share of allowable costs?

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... ADMINISTRATIVE REQUIREMENTS, PITTMAN-ROBERTSON WILDLIFE RESTORATION AND DINGELL-JOHNSON SPORT FISH RESTORATION... costs of a grant-funded project in a program or subprogram authorized by the Dingell-Johnson Sport Fish... Mariana Islands and the territories of Guam, the U.S. Virgin Islands, and American Samoa. The Regional...

  3. 26 CFR 1.612-1 - Basis for allowance of cost depletion.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... mineral content of deposits is a factor, see paragraphs (c), (d), (e), and (f) of § 1.611-2. In cases... allowed in respect of any mineral or timber property is the adjusted basis provided in section 1011 for... retained. (b) Special rules. (1) The basis for cost depletion of mineral or timber property does not...

  4. 26 CFR 1.612-1 - Basis for allowance of cost depletion.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... mineral content of deposits is a factor, see paragraphs (c), (d), (e), and (f) of § 1.611-2. In cases... allowed in respect of any mineral or timber property is the adjusted basis provided in section 1011 for... retained. (b) Special rules. (1) The basis for cost depletion of mineral or timber property does not...

  5. 45 CFR 1630.3 - Standards governing allowability of costs under Corporation grants or contracts.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 45 Public Welfare 4 2010-10-01 2010-10-01 false Standards governing allowability of costs under Corporation grants or contracts. 1630.3 Section 1630.3 Public Welfare Regulations Relating to Public Welfare... accordance with the relative benefits received. Costs may be allocated to Corporation funds either as direct...

  6. 24 CFR 92.301 - Project-specific assistance to community housing development organizations.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... participating jurisdiction determines to be customary and reasonable project preparation costs allowable under paragraph (a)(2) of this section. All costs must be related to a specific eligible project or projects. (2) Allowable costs. A loan may be provided to cover project costs necessary to determine project feasibility...

  7. 24 CFR 92.301 - Project-specific assistance to community housing development organizations.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... participating jurisdiction determines to be customary and reasonable project preparation costs allowable under paragraph (a)(2) of this section. All costs must be related to a specific eligible project or projects. (2) Allowable costs. A loan may be provided to cover project costs necessary to determine project feasibility...

  8. 42 CFR 413.139 - Depreciation: Optional allowance for depreciation based on a percentage of operating costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... is determined. (c) Application. If a provider has inadequate historical cost records for pre-1966... depreciable-type assets, allowance in lieu of specific recognition of other costs, or return on equity capital... either has no historical cost records or has incomplete records, the determination of historical cost may...

  9. 24 CFR 92.206 - Eligible project costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 24 Housing and Urban Development 1 2010-04-01 2010-04-01 false Eligible project costs. 92.206 Section 92.206 Housing and Urban Development Office of the Secretary, Department of Housing and Urban... participating jurisdiction and the Model Energy Code referred to in § 92.251; (2) For rehabilitation, costs: (i...

  10. 13 CFR 308.1 - Use of funds in Projects constructed under projected cost.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 13 Business Credit and Assistance 1 2010-01-01 2010-01-01 false Use of funds in Projects constructed under projected cost. 308.1 Section 308.1 Business Credit and Assistance ECONOMIC DEVELOPMENT ADMINISTRATION, DEPARTMENT OF COMMERCE PERFORMANCE INCENTIVES § 308.1 Use of funds in Projects constructed under...

  11. Healthcare Cost and Utilization Project (HCUP)

    Cancer.gov

    The Healthcare Cost and Utilization Project is a family of health care databases and related software tools and products developed through a Federal-State-Industry partnership and sponsored by the Agency for Healthcare Research and Quality.

  12. Causative factors of cost overrun in highway projects of Sindh province of Pakistan

    NASA Astrophysics Data System (ADS)

    Sohu, S.; Halid, A.; Nagapan, S.; Fattah, A.; Latif, I.; Ullah, K.

    2017-11-01

    Cost overrun is an increase of cost of project from approved budget which was signed by parties at the time of tender. Cost overrun in construction of highway projects is a common problem worldwide and construction industry of Pakistan is also facing this crucial problem of cost overrun in highway projects of Pakistan. The main objective of this research is to identify the causative factors of cost overrun in highway projects of Sindh province of Pakistan. A well designed questionnaire was developed based on 64 common factors of cost overrun from literature review. Developed questionnaire was distributed among selected 30 experts from owner/client, designer/consultant and contractor who have experience more than 20 years’ experience in highway projects. The collected data was statistical analyzed. After analysis results showed that delay process in payment by client, inadequate planning, client interference, poor contract management, delay of decision making, change of scope of project and financial problems faced by client were most causative factors of cost overrun in highway projects. This research will provide alertness to stakeholders of highway projects of Sindh province to avoid cost overrun in projects.

  13. Comprehensive Cost Planning Yields Successful Tech Projects

    ERIC Educational Resources Information Center

    Breeding, Marshall

    2006-01-01

    In this article, the author calls for librarians to find ways to implement technology projects with very limited budgets and to consider all the cost components of a technology project amidst the economic pressures. The author offers some perspective on what is involved in trying to accomplish important work with limited resources while…

  14. Cost-effectiveness of Project ADAM: a project to prevent sudden cardiac death in high school students.

    PubMed

    Berger, S; Whitstone, B N; Frisbee, S J; Miner, J T; Dhala, A; Pirrallo, R G; Utech, L M; Sachdeva, R C

    2004-01-01

    Public access defibrillation (PAD) in the adult population is thought to be both efficacious and cost-effective. Similar programs aimed at children and adolescents have not been evaluated for their cost-effectiveness. This study evaluates the potential cost-effectiveness of implementing Project ADAM, a program targeting children and adolescents in high schools in the Milwaukee Public School System. Project ADAM provides education about cardiopulmonary resuscitation (CPR) and the warning signs of sudden cardiac death (SCD) and training in the use and placement of automated external defibrillators (AEDs) in high schools. We developed decision analysis models to evaluate the cost-effectiveness of the decision to implement Project ADAM in public high schools in Milwaukee. We examined clinical model and public policy applications. Data on costs included estimates of hospital-based charges derived from a pediatric medical center where a series of patients were treated for SCD, educational programming, and the direct costs of one AED and training for 15 personnel per school. We performed sensitivity analyses to assess the variation in outputs with respect to changes to input data. The main outcome measures were Life years saved and incremental cost-effectiveness ratios. At an arbitrary societal willingness to pay $100,000 per life year saved, the policy to implement Project ADAM in schools is a cost-effective strategy at a threshold of approximately 5 patients over 5 years for the clinical model and approximately 8 patients over 5 years for the public policy model. Implementation of Project ADAM in high schools in the United States is potentially associated with an incremental cost-effectiveness ratio that is favorable.

  15. 20 CFR 627.435 - Cost principles and allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... system, including the costs of hearings and appeals, and related expenses such as lawyers' fees. Legal...) Legal expenses for the prosecution of claims against the Federal Government, including appeals to an... incurred by the SJTCC, HRIC, PIC's, and other advisory councils or committees; (3) Advertising costs; (4...

  16. 20 CFR 627.435 - Cost principles and allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... PROVISIONS GOVERNING PROGRAMS UNDER TITLES I, II, AND III OF THE ACT Administrative Standards § 627.435 Cost... the proper and efficient administration of the program, be allocable to the program, and, except as... Governor or a governmental subrecipient. Costs charged to the program shall be accorded consistent...

  17. 20 CFR 627.435 - Cost principles and allowable costs.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... PROVISIONS GOVERNING PROGRAMS UNDER TITLES I, II, AND III OF THE ACT Administrative Standards § 627.435 Cost... the proper and efficient administration of the program, be allocable to the program, and, except as... Governor or a governmental subrecipient. Costs charged to the program shall be accorded consistent...

  18. Low-cost solar array project progress and plans

    NASA Technical Reports Server (NTRS)

    Callaghan, W. T.

    1981-01-01

    The considered project is part of the DOE Photovoltaic Technology and Market Development Program. This program is concerned with the development and the utilization of cost-competitive photovoltaic systems. The project has the objective to develop, by 1986, the national capability to manufacture low-cost, long-life photovoltaic arrays at production rates that will realize economies of scale, and at a price of less than $0.70/watt. The array performance objectives include an efficiency greater than 10% and an operating lifetime longer than 20 years. The objective of the silicon material task is to establish the practicality of processes for producing silicon suitable for terrestrial photovoltaic applications at a price of $14/kg. The large-area sheet task is concerned with the development of process technology for sheet formation. Low-cost encapsulation material systems are being developed in connection with the encapsulation task. Another project goal is related to the development of economical process sequences.

  19. Examining engineering costs for development of highway projects.

    DOT National Transportation Integrated Search

    2012-12-01

    The Texas Department of Transportation (TxDOT) commissioned a research team at Texas State University-San Marcos Department of Accounting to analyze the cost of projects by determining the cost of a preliminary engineering hour necessary to develop h...

  20. 45 CFR 1351.16 - What costs are not allowable under a Runaway and Homeless Youth Program grant?

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 45 Public Welfare 4 2010-10-01 2010-10-01 false What costs are not allowable under a Runaway and... FOR CHILDREN, YOUTH AND FAMILIES, FAMILY AND YOUTH SERVICES BUREAU RUNAWAY AND HOMELESS YOUTH PROGRAM Runaway and Homeless Youth Program Grant § 1351.16 What costs are not allowable under a Runaway and...

  1. 45 CFR 1351.16 - What costs are not allowable under a Runaway and Homeless Youth Program grant?

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... FOR CHILDREN, YOUTH AND FAMILIES, FAMILY AND YOUTH SERVICES BUREAU RUNAWAY AND HOMELESS YOUTH PROGRAM Runaway and Homeless Youth Program Grant § 1351.16 What costs are not allowable under a Runaway and... 45 Public Welfare 4 2011-10-01 2011-10-01 false What costs are not allowable under a Runaway and...

  2. 45 CFR 1351.16 - What costs are not allowable under a Runaway and Homeless Youth Program grant?

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... FOR CHILDREN, YOUTH AND FAMILIES, FAMILY AND YOUTH SERVICES BUREAU RUNAWAY AND HOMELESS YOUTH PROGRAM Runaway and Homeless Youth Program Grant § 1351.16 What costs are not allowable under a Runaway and... 45 Public Welfare 4 2013-10-01 2013-10-01 false What costs are not allowable under a Runaway and...

  3. 45 CFR 1351.16 - What costs are not allowable under a Runaway and Homeless Youth Program grant?

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... FOR CHILDREN, YOUTH AND FAMILIES, FAMILY AND YOUTH SERVICES BUREAU RUNAWAY AND HOMELESS YOUTH PROGRAM Runaway and Homeless Youth Program Grant § 1351.16 What costs are not allowable under a Runaway and... 45 Public Welfare 4 2012-10-01 2012-10-01 false What costs are not allowable under a Runaway and...

  4. 45 CFR 1351.16 - What costs are not allowable under a Runaway and Homeless Youth Program grant?

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... FOR CHILDREN, YOUTH AND FAMILIES, FAMILY AND YOUTH SERVICES BUREAU RUNAWAY AND HOMELESS YOUTH PROGRAM Runaway and Homeless Youth Program Grant § 1351.16 What costs are not allowable under a Runaway and... 45 Public Welfare 4 2014-10-01 2014-10-01 false What costs are not allowable under a Runaway and...

  5. Cost analysis of a project to digitize classic articles in neurosurgery*

    PubMed Central

    Bauer, Kathleen

    2002-01-01

    In summer 2000, the Cushing/Whitney Medical Library at Yale University began a demonstration project to digitize classic articles in neurosurgery from the late 1800s and early 1900s. The objective of the first phase of the project was to measure the time and costs involved in digitization, and those results are reported here. In the second phase, metadata will be added to the digitized articles, and the project will be publicized. Thirteen articles were scanned using optical character recognition (OCR) software, and the resulting text files were carefully proofread. Time for photocopying, scanning, and proofreading were recorded. This project achieved an average cost per item (total pages plus images) of $4.12, a figure at the high end of average costs found in other studies. This project experienced high costs for two reasons. First, the articles contained many images, which required extra processing. Second, the older fonts and the poor condition of many of these articles complicated the OCR process. The average article cost $84.46 to digitize. Although costs were high, the selection of historically important articles maximized the benefit gained from the investment in digitization. PMID:11999182

  6. Cost analysis of a project to digitize classic articles in neurosurgery.

    PubMed

    Bauer, Kathleen

    2002-04-01

    In summer 2000, the Cushing/Whitney Medical Library at Yale University began a demonstration project to digitize classic articles in neurosurgery from the late 1800s and early 1900s. The objective of the first phase of the project was to measure the time and costs involved in digitization, and those results are reported here. In the second phase, metadata will be added to the digitized articles, and the project will be publicized. Thirteen articles were scanned using optical character recognition (OCR) software, and the resulting text files were carefully proofread. Time for photocopying, scanning, and proofreading were recorded. This project achieved an average cost per item (total pages plus images) of $4.12, a figure at the high end of average costs found in other studies. This project experienced high costs for two reasons. First, the articles contained many images, which required extra processing. Second, the older fonts and the poor condition of many of these articles complicated the OCR process. The average article cost $84.46 to digitize. Although costs were high, the selection of historically important articles maximized the benefit gained from the investment in digitization.

  7. Changes in Federal Water Project Repayment Policies Can Reduce Federal Costs.

    DTIC Science & Technology

    1981-08-07

    a reimburs - able purpose, the users should share in cost recovery. RECOMMENDATIONS To provide for equitable cost reimbursement on underutilized...Department of the Interior’s Bureau of Reclamation that do not ensure fair and timely recovery of water projects’ reimbursable costs. We made this...such costs for reimbursable project purposes and considering them in future water price determinations, agencies often reas- signed them to

  8. 13 CFR 120.882 - Eligible Project costs for 504 loans.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... loans. 120.882 Section 120.882 Business Credit and Assistance SMALL BUSINESS ADMINISTRATION BUSINESS LOANS Development Company Loan Program (504) Loan-Making Policies Specific to 504 Loans § 120.882 Eligible Project costs for 504 loans. Eligible Project costs which may be paid with the proceeds of 504...

  9. 13 CFR 120.882 - Eligible Project costs for 504 loans.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... loans. 120.882 Section 120.882 Business Credit and Assistance SMALL BUSINESS ADMINISTRATION BUSINESS LOANS Development Company Loan Program (504) Loan-Making Policies Specific to 504 Loans § 120.882 Eligible Project costs for 504 loans. Eligible Project costs which may be paid with the proceeds of 504...

  10. 13 CFR 120.882 - Eligible Project costs for 504 loans.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... loans. 120.882 Section 120.882 Business Credit and Assistance SMALL BUSINESS ADMINISTRATION BUSINESS LOANS Development Company Loan Program (504) Loan-Making Policies Specific to 504 Loans § 120.882 Eligible Project costs for 504 loans. Eligible Project costs which may be paid with the proceeds of 504...

  11. 13 CFR 120.882 - Eligible Project costs for 504 loans.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... loans. 120.882 Section 120.882 Business Credit and Assistance SMALL BUSINESS ADMINISTRATION BUSINESS LOANS Development Company Loan Program (504) Loan-Making Policies Specific to 504 Loans § 120.882 Eligible Project costs for 504 loans. Eligible Project costs which may be paid with the proceeds of 504...

  12. 40 CFR 35.925-18 - Limitation upon project costs incurred prior to award.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 40 Protection of Environment 1 2014-07-01 2014-07-01 false Limitation upon project costs incurred...-Clean Water Act § 35.925-18 Limitation upon project costs incurred prior to award. That project... project costs in the following cases: (1) Step 1 work begun after the date of approval by the Regional...

  13. 40 CFR 35.925-18 - Limitation upon project costs incurred prior to award.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 40 Protection of Environment 1 2011-07-01 2011-07-01 false Limitation upon project costs incurred...-Clean Water Act § 35.925-18 Limitation upon project costs incurred prior to award. That project... project costs in the following cases: (1) Step 1 work begun after the date of approval by the Regional...

  14. 40 CFR 35.925-18 - Limitation upon project costs incurred prior to award.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 40 Protection of Environment 1 2012-07-01 2012-07-01 false Limitation upon project costs incurred...-Clean Water Act § 35.925-18 Limitation upon project costs incurred prior to award. That project... project costs in the following cases: (1) Step 1 work begun after the date of approval by the Regional...

  15. 40 CFR 35.925-18 - Limitation upon project costs incurred prior to award.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 40 Protection of Environment 1 2013-07-01 2013-07-01 false Limitation upon project costs incurred...-Clean Water Act § 35.925-18 Limitation upon project costs incurred prior to award. That project... project costs in the following cases: (1) Step 1 work begun after the date of approval by the Regional...

  16. 40 CFR 35.925-18 - Limitation upon project costs incurred prior to award.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 1 2010-07-01 2010-07-01 false Limitation upon project costs incurred...-Clean Water Act § 35.925-18 Limitation upon project costs incurred prior to award. That project... project costs in the following cases: (1) Step 1 work begun after the date of approval by the Regional...

  17. 49 CFR 18.22 - Allowable costs.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... organization incurring the costs. The following chart lists the kinds of organizations and the applicable cost... the State or local public body to the extent that the proceeds of such bonds have actually been... grants to finance the leasing of facilities and equipment for use in mass transportation services...

  18. 49 CFR 18.22 - Allowable costs.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... organization incurring the costs. The following chart lists the kinds of organizations and the applicable cost... the State or local public body to the extent that the proceeds of such bonds have actually been... grants to finance the leasing of facilities and equipment for use in mass transportation services...

  19. 49 CFR 18.22 - Allowable costs.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... organization incurring the costs. The following chart lists the kinds of organizations and the applicable cost... the State or local public body to the extent that the proceeds of such bonds have actually been... grants to finance the leasing of facilities and equipment for use in mass transportation services...

  20. 78 FR 8389 - Natural Gas Pipelines; Project Cost and Annual Limits

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-02-06

    ... Director of the Office of Energy Projects. The cost limits for calendar year 2013, as published in Table I.... ACTION: Final rule. SUMMARY: Pursuant to the authority delegated by 18 CFR 375.308(x)(1), the Director of the Office of Energy Projects (OEP) computes and publishes the project cost and annual limits for...

  1. Flexible resource management and its effect on project cost and duration

    NASA Astrophysics Data System (ADS)

    Pinha, Denis C.; Ahluwalia, Rashpal S.

    2018-06-01

    In practice, most projects result in cost overruns and schedule slippage due to poor resource management. This paper presents an approach that aims at reducing project duration and costs by empowering project managers to assess different scenarios. The proposed approach addresses combinatorial modes for tasks, multi-skilled resources, and multiple calendars for resources. A case study reported in the literature is presented to demonstrate the capabilities of this method. As for practical implications, this approach enhances the decision-making process which results in improved solutions in terms of total project duration and cost. From an academic viewpoint, this paper adds empirical evidence to enrich the existing literature, as it highlights relevant issues to model properly the complexity of real-life projects.

  2. Utility-Scale Lithium-Ion Storage Cost Projections for Use in Capacity Expansion Models

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Cole, Wesley J.; Marcy, Cara; Krishnan, Venkat K.

    2016-11-21

    This work presents U.S. utility-scale battery storage cost projections for use in capacity expansion models. We create battery cost projections based on a survey of literature cost projections of battery packs and balance of system costs, with a focus on lithium-ion batteries. Low, mid, and high cost trajectories are created for the overnight capital costs and the operating and maintenance costs. We then demonstrate the impact of these cost projections in the Regional Energy Deployment System (ReEDS) capacity expansion model. We find that under reference scenario conditions, lower battery costs can lead to increased penetration of variable renewable energy, withmore » solar photovoltaics (PV) seeing the largest increase. We also find that additional storage can reduce renewable energy curtailment, although that comes at the expense of additional storage losses.« less

  3. Wind-To-Hydrogen Project: Electrolyzer Capital Cost Study

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Saur, G.

    This study is being performed as part of the U.S. Department of Energy and Xcel Energy's Wind-to-Hydrogen Project (Wind2H2) at the National Renewable Energy Laboratory. The general aim of the project is to identify areas for improving the production of hydrogen from renewable energy sources. These areas include both technical development and cost analysis of systems that convert renewable energy to hydrogen via water electrolysis. Increased efficiency and reduced cost will bring about greater market penetration for hydrogen production and application. There are different issues for isolated versus grid-connected systems, however, and these issues must be considered. The manner inmore » which hydrogen production is integrated in the larger energy system will determine its cost feasibility and energy efficiency.« less

  4. 34 CFR 21.33 - Allowable fees and expenses.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 34 Education 1 2010-07-01 2010-07-01 false Allowable fees and expenses. 21.33 Section 21.33 Education Office of the Secretary, Department of Education EQUAL ACCESS TO JUSTICE How Does One Apply for an... expenses. (3) The cost of any study, analysis, engineering report, test, or project related to the...

  5. Low Cost Rapid Response Spacecraft, (LCRRS): A Research Project in Low Cost Spacecraft Design and Fabrication in a Rapid Prototyping Environment

    NASA Technical Reports Server (NTRS)

    Spremo, Stevan; Bregman, Jesse; Dallara, Christopher D.; Ghassemieh, Shakib M.; Hanratty, James; Jackson, Evan; Kitts, Christopher; Klupar, Pete; Lindsay, Michael; Ignacio, Mas; hide

    2009-01-01

    The Low Cost Rapid Response Spacecraft (LCRRS) is an ongoing research development project at NASA Ames Research Center (ARC), Moffett Field, California. The prototype spacecraft, called Cost Optimized Test for Spacecraft Avionics and Technologies (COTSAT) is the first of what could potentially be a series of rapidly produced low-cost satellites. COTSAT has a target launch date of March 2009 on a SpaceX Falcon 9 launch vehicle. The LCRRS research system design incorporates use of COTS (Commercial Off The Shelf), MOTS (Modified Off The Shelf), and GOTS (Government Off The Shelf) hardware for a remote sensing satellite. The design concept was baselined to support a 0.5 meter Ritchey-Chretien telescope payload. This telescope and camera system is expected to achieve 1.5 meter/pixel resolution. The COTSAT team is investigating the possibility of building a fully functional spacecraft for $500,000 parts and $2,000,000 labor. Cost is dramatically reduced by using a sealed container, housing the bus and payload subsystems. Some electrical and RF designs were improved/upgraded from GeneSat-1 heritage systems. The project began in January 2007 and has yielded two functional test platforms. It is expected that a flight-qualified unit will be finished in December 2008. Flight quality controls are in place on the parts and materials used in this development with the aim of using them to finish a proto-flight satellite. For LEO missions the team is targeting a mission class requiring a minimum of six months lifetime or more. The system architecture incorporates several design features required by high reliability missions. This allows for a true skunk works environment to rapidly progress toward a flight design. Engineering and fabrication is primarily done in-house at NASA Ames with flight certifications on materials. The team currently employs seven Full Time Equivalent employees. The success of COTSATs small team in this effort can be attributed to highly cross trained

  6. The use of cluster analysis techniques in spaceflight project cost risk estimation

    NASA Technical Reports Server (NTRS)

    Fox, G.; Ebbeler, D.; Jorgensen, E.

    2003-01-01

    Project cost risk is the uncertainty in final project cost, contingent on initial budget, requirements and schedule. For a proposed mission, a dynamic simulation model relying for some of its input on a simple risk elicitation is used to identify and quantify systemic cost risk.

  7. A Project Management Approach to Using Simulation for Cost Estimation on Large, Complex Software Development Projects

    NASA Technical Reports Server (NTRS)

    Mizell, Carolyn; Malone, Linda

    2007-01-01

    It is very difficult for project managers to develop accurate cost and schedule estimates for large, complex software development projects. None of the approaches or tools available today can estimate the true cost of software with any high degree of accuracy early in a project. This paper provides an approach that utilizes a software development process simulation model that considers and conveys the level of uncertainty that exists when developing an initial estimate. A NASA project will be analyzed using simulation and data from the Software Engineering Laboratory to show the benefits of such an approach.

  8. 42 CFR 457.555 - Maximum allowable cost-sharing charges on targeted low-income children in families with income...

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... maximum amount of $11.35 for services furnished in a hospital emergency room if those services are not... 42 Public Health 4 2012-10-01 2012-10-01 false Maximum allowable cost-sharing charges on targeted... Requirements: Enrollee Financial Responsibilities § 457.555 Maximum allowable cost-sharing charges on targeted...

  9. Considering a Cost Analysis Project? A Planned Approach

    ERIC Educational Resources Information Center

    Parish, Mina; Teetor, Travis

    2006-01-01

    As resources become more constrained in the library community, many organizations are finding that they need to have a better understanding of their costs. To this end, this article will present one approach to conducting a cost analysis (including questions to ask yourself, project team makeup, organizational support, and data organization). We…

  10. Which factors affect software projects maintenance cost more?

    PubMed

    Dehaghani, Sayed Mehdi Hejazi; Hajrahimi, Nafiseh

    2013-03-01

    The software industry has had significant progress in recent years. The entire life of software includes two phases: production and maintenance. Software maintenance cost is increasingly growing and estimates showed that about 90% of software life cost is related to its maintenance phase. Extraction and considering the factors affecting the software maintenance cost help to estimate the cost and reduce it by controlling the factors. In this study, the factors affecting software maintenance cost were determined then were ranked based on their priority and after that effective ways to reduce the maintenance costs were presented. This paper is a research study. 15 software related to health care centers information systems in Isfahan University of Medical Sciences and hospitals function were studied in the years 2010 to 2011. Among Medical software maintenance team members, 40 were selected as sample. After interviews with experts in this field, factors affecting maintenance cost were determined. In order to prioritize the factors derived by AHP, at first, measurement criteria (factors found) were appointed by members of the maintenance team and eventually were prioritized with the help of EC software. Based on the results of this study, 32 factors were obtained which were classified in six groups. "Project" was ranked the most effective feature in maintenance cost with the highest priority. By taking into account some major elements like careful feasibility of IT projects, full documentation and accompany the designers in the maintenance phase good results can be achieved to reduce maintenance costs and increase longevity of the software.

  11. 23 CFR 140.608 - Reimbursable bond interest costs of Interstate projects.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 23 Highways 1 2014-04-01 2014-04-01 false Reimbursable bond interest costs of Interstate projects. 140.608 Section 140.608 Highways FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION PAYMENT PROCEDURES REIMBURSEMENT Reimbursement for Bond Issue Projects § 140.608 Reimbursable bond interest costs of...

  12. 23 CFR 140.608 - Reimbursable bond interest costs of Interstate projects.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 23 Highways 1 2010-04-01 2010-04-01 false Reimbursable bond interest costs of Interstate projects. 140.608 Section 140.608 Highways FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION PAYMENT PROCEDURES REIMBURSEMENT Reimbursement for Bond Issue Projects § 140.608 Reimbursable bond interest costs of...

  13. 23 CFR 140.608 - Reimbursable bond interest costs of Interstate projects.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 23 Highways 1 2011-04-01 2011-04-01 false Reimbursable bond interest costs of Interstate projects. 140.608 Section 140.608 Highways FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION PAYMENT PROCEDURES REIMBURSEMENT Reimbursement for Bond Issue Projects § 140.608 Reimbursable bond interest costs of...

  14. 23 CFR 140.608 - Reimbursable bond interest costs of Interstate projects.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 23 Highways 1 2013-04-01 2013-04-01 false Reimbursable bond interest costs of Interstate projects. 140.608 Section 140.608 Highways FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION PAYMENT PROCEDURES REIMBURSEMENT Reimbursement for Bond Issue Projects § 140.608 Reimbursable bond interest costs of...

  15. 24 CFR 891.545 - Completion of project, cost certification, and HUD approvals.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 24 Housing and Urban Development 4 2014-04-01 2014-04-01 false Completion of project, cost... DISABILITIES Loans for Housing for the Elderly and Persons with Disabilities Section 202 Projects for the Elderly Or Handicapped-Section 8 Assistance § 891.545 Completion of project, cost certification, and HUD...

  16. 24 CFR 891.545 - Completion of project, cost certification, and HUD approvals.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 24 Housing and Urban Development 4 2012-04-01 2012-04-01 false Completion of project, cost... DISABILITIES Loans for Housing for the Elderly and Persons with Disabilities Section 202 Projects for the Elderly Or Handicapped-Section 8 Assistance § 891.545 Completion of project, cost certification, and HUD...

  17. 24 CFR 891.545 - Completion of project, cost certification, and HUD approvals.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 24 Housing and Urban Development 4 2013-04-01 2013-04-01 false Completion of project, cost... DISABILITIES Loans for Housing for the Elderly and Persons with Disabilities Section 202 Projects for the Elderly Or Handicapped-Section 8 Assistance § 891.545 Completion of project, cost certification, and HUD...

  18. Cost Allocation of Multiagency Water Resource Projects: Game Theoretic Approaches and Case Study

    NASA Astrophysics Data System (ADS)

    Lejano, Raul P.; Davos, Climis A.

    1995-05-01

    Water resource projects are often jointly carried out by a number of communities and agencies. Participation in a joint project depends on how costs are allocated among the participants and how cost shares compare with the cost of independent projects. Cooperative N-person game theory offers approaches which yield cost allocations that satisfy rationality conditions favoring participation. A new solution concept, the normalized nucleolus, is discussed and applied to a water reuse project in southern California. Results obtained with the normalized nucleolus are compared with those derived with more traditional solution concepts, namely, the nucleolus and the Shapley value.

  19. Environmental cost of using poor decision metrics to prioritize environmental projects.

    PubMed

    Pannell, David J; Gibson, Fiona L

    2016-04-01

    Conservation decision makers commonly use project-scoring metrics that are inconsistent with theory on optimal ranking of projects. As a result, there may often be a loss of environmental benefits. We estimated the magnitudes of these losses for various metrics that deviate from theory in ways that are common in practice. These metrics included cases where relevant variables were omitted from the benefits metric, project costs were omitted, and benefits were calculated using a faulty functional form. We estimated distributions of parameters from 129 environmental projects from Australia, New Zealand, and Italy for which detailed analyses had been completed previously. The cost of using poor prioritization metrics (in terms of lost environmental values) was often high--up to 80% in the scenarios we examined. The cost in percentage terms was greater when the budget was smaller. The most costly errors were omitting information about environmental values (up to 31% loss of environmental values), omitting project costs (up to 35% loss), omitting the effectiveness of management actions (up to 9% loss), and using a weighted-additive decision metric for variables that should be multiplied (up to 23% loss). The latter 3 are errors that occur commonly in real-world decision metrics, in combination often reducing potential benefits from conservation investments by 30-50%. Uncertainty about parameter values also reduced the benefits from investments in conservation projects but often not by as much as faulty prioritization metrics. © 2016 Society for Conservation Biology.

  20. Low-cost solar array project and Proceedings of the 15th Project Integration Meeting

    NASA Technical Reports Server (NTRS)

    1980-01-01

    Progress made by the Low-Cost Solar Array Project during the period December 1979 to April 1980 is described. Project analysis and integration, technology development in silicon material, large area silicon sheet and encapsulation, production process and equipment development, engineering, and operation are included.

  1. Make-up wells drilling cost in financial model for a geothermal project

    NASA Astrophysics Data System (ADS)

    Oktaviani Purwaningsih, Fitri; Husnie, Ruly; Afuar, Waldy; Abdurrahman, Gugun

    2017-12-01

    After commissioning of a power plant, geothermal reservoir will encounter pressure decline, which will affect wells productivity. Therefore, further drilling is carried out to enhance steam production. Make-up wells are production wells drilled inside an already confirmed reservoir to maintain steam production in a certain level. Based on Sanyal (2004), geothermal power cost consists of three components, those are capital cost, O&M cost and make-up drilling cost. The make-up drilling cost component is a major part of power cost which will give big influence in a whole economical value of the project. The objective of this paper it to analyse the make-up wells drilling cost component in financial model of a geothermal power project. The research will calculate make-up wells requirements, drilling costs as a function of time and how they influence the financial model and affect the power cost. The best scenario in determining make-up wells strategy in relation with the project financial model would be the result of this research.

  2. Cost-effectiveness of the Health X Project for tuberculosis control in China.

    PubMed

    Wang, W-B; Zhang, H; Petzold, M; Zhao, Q; Xu, B; Zhao, G-M

    2014-08-01

    Between 2002 and 2008, China's National Tuberculosis Control Programme created the Health X Project, financed in part by a World Bank loan, with additional funding from the UK Department for International Development. To assess the cost-effectiveness of the Project and its impact from a financial point of view on tuberculosis (TB) control in China. A decision-analytic model was used to evaluate the cost-effectiveness of the Project. Sensitivity analysis was used to assess the impact of different scenarios and assumptions on results. The primary outcome of the study was cost per disability-adjusted life-year (DALY) saved and incremental DALYs saved. In comparison with alternative scenario 1, the Project detected 1.6 million additional cases, 44 000 deaths were prevented and a total of 18.4 million DALYs saved. The Project strategies cost approximately Chinese yuan (CNY) 953 per DALY saved (vs. CNY1140 in the control areas), and saved an estimated CNY17.5 billion in comparison with the unchanged alternative scenario (scenario 1) or CNY10.8 billion with the control scenario (scenario 2). The Project strategies were affordable and of comparable cost-effectiveness to those of other developing countries. The results also provide strong support for the existing policy of scaling up DOTS in China.

  3. Cost estimation using ministerial regulation of public work no. 11/2013 in construction projects

    NASA Astrophysics Data System (ADS)

    Arumsari, Putri; Juliastuti; Khalifah Al'farisi, Muhammad

    2017-12-01

    One of the first tasks in starting a construction project is to estimate the total cost of building a project. In Indonesia there are several standards that are used to calculate the cost estimation of a project. One of the standards used in based on the Ministerial Regulation of Public Work No. 11/2013. However in a construction project, contractor often has their own cost estimation based on their own calculation. This research aimed to compare the construction project total cost using calculation based on the Ministerial Regulation of Public Work No. 11/2013 against the contractor’s calculation. Two projects were used as case study to compare the results. The projects were a 4 storey building located in Pantai Indah Kapuk area (West Jakarta) and a warehouse located in Sentul (West Java) which was built by 2 different contractors. The cost estimation from both contractors’ calculation were compared to the one based on the Ministerial Regulation of Public Work No. 11/2013. It is found that there were differences between the two calculation around 1.80 % - 3.03% in total cost, in which the cost estimation based on Ministerial Regulation was higher than the contractors’ calculations.

  4. Analysis of the production and transaction costs of forest carbon offset projects in the USA.

    PubMed

    Galik, Christopher S; Cooley, David M; Baker, Justin S

    2012-12-15

    Forest carbon offset project implementation costs, comprised of both production and transaction costs, could present an important barrier to private landowner participation in carbon offset markets. These costs likewise represent a largely undocumented component of forest carbon offset potential. Using a custom spreadsheet model and accounting tool, this study examines the implementation costs of different forest offset project types operating in different forest types under different accounting and sampling methodologies. Sensitivity results are summarized concisely through response surface regression analysis to illustrate the relative effect of project-specific variables on total implementation costs. Results suggest that transaction costs may represent a relatively small percentage of total project implementation costs - generally less than 25% of the total. Results also show that carbon accounting methods, specifically the method used to establish project baseline, may be among the most important factors in driving implementation costs on a per-ton-of-carbon-sequestered basis, dramatically increasing variability in both transaction and production costs. This suggests that accounting could be a large driver in the financial viability of forest offset projects, with transaction costs likely being of largest concern to those projects at the margin. Copyright © 2012 Elsevier Ltd. All rights reserved.

  5. Risk Analysis of Underestimate Cost Offer to The Project Quality in Aceh Province

    NASA Astrophysics Data System (ADS)

    Rani, Hafnidar A.

    2016-11-01

    The possibility of errors in the process of offer price determination could be enormous, so it can affect the possibility of project underestimate cost which can impact and reduce the profit if being implementing. Government Equipment/Service Procurement Policy Institution (LKPP) assesses that the practices of cheaper price in the government equipment/service procurement are still highly found and can be potential to decrease the project quality. This study aimed to analyze the most dominant factors happened in underestimate cost offer practice, to analyze the relationship of underestimate cost offer risk factors to road construction project quality in Aceh Province and to analyze the most potential factors of underestimate cost offer risk affecting road construction project quality in Aceh Province. Road construction projects observed the projects which have been implemented in Aceh Province since 2013 - 2015. This study conducted by interviewing Government Budget Authority (KPA), and distributing the questionnaire to the road construction contractors with the qualification of K1, K2, K3, M1, M2 and B1. Based on the data from Construction Service Development Institution (LPJK) of Aceh Province on 2016, the populations obtained are 2,717 constructors. By using Slovin Equation, the research samples obtained are 97 contractors. The most dominant factors in underestimate cost offer risk of the road construction projects in Aceh Province is Contingency Cost Factor which the mean is 4.374.

  6. 40 CFR 35.2025 - Allowance and advance of allowance.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... advance of allowance. (a) Allowance. Step 2+3 and Step 3 grant agreements will include an allowance for facilities planning and design of the project and Step 7 agreements will include an allowance for facility... 40 Protection of Environment 1 2010-07-01 2010-07-01 false Allowance and advance of allowance. 35...

  7. 15 CFR 921.81 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... ESTUARINE RESEARCH RESERVE SYSTEM REGULATIONS General Financial Assistance Provisions § 921.81 Allowable..., the fair market value of real property allowable as match is limited to the fair market value of a real property interest equivalent to, or required to attain, the level of control over such land(s...

  8. Reflections on Evaluation Costs: Direct and Indirect. Evaluation Productivity Project.

    ERIC Educational Resources Information Center

    Alkin, Marvin; Ruskus, Joan A.

    This paper summarizes views on the costs of evaluation developed as part of CSE's Evaluation Productivity Project. In particular, it focuses on ideas about the kinds of costs associated with factors known to effect evaluation utilization. The first section deals with general issues involved in identifying and valuing cost components, particularly…

  9. Effect of a therapeutic maximum allowable cost (MAC) program on the cost and utilization of proton pump inhibitors in an employer-sponsored drug plan in Canada.

    PubMed

    Mabasa, Vincent H; Ma, Johnny

    2006-06-01

    Therapeutic maximum allowable cost (MAC) is a managed care intervention that uses reference pricing in a therapeutic class or category of drugs or an indication (e.g., heartburn). Therapeutic MAC has not been studied in Canada or the United States. The proton pump inhibitor (PPI) rabeprazole was used as the reference drug in this therapeutic MAC program based on prices for PPIs in the province of Ontario. No PPI is available over the counter in Canada. To evaluate the utilization and anticipated drug cost savings for PPIs in an employer-sponsored drug plan in Canada that implemented a therapeutic MAC program for PPIs. An employer group with an average of 6,300 covered members, which adopted the MAC program for PPIs in June 2003, was compared with a comparison group comprising the book of business throughout Canada (approximately 5 million lives) without a PPI MAC program (non-MAC group). Pharmacy claims for PPIs were identified using the first 6 characters of the generic product identifier (GPI 492700) for a 36-month period from June 1, 2002, through May 31, 2005. The primary comparison was the year prior to the intervention (from June 1, 2002, through May 31, 2003) and the first full year following the intervention (June 1, 2004, through May 31, 2005). Drug utilization was evaluated by comparing the market share of each of the PPIs for the 2 time periods and by the days of PPI therapy per patient per year (PPPY) and days of therapy per prescription (Rx). Drug cost was defined as the cost of the drug (ingredient cost), including allowable provincial pharmacy markup but excluding pharmacy dispense fee. Cost savings were calculated from the allowed drug cost per claim, allowed cost per day, and allowed cost PPPY. (All amounts are in Canadian dollars.) The MAC intervention group experienced an 11.7% reduction in the average cost per day of PPI drug therapy, from 2.14 US dollars in the preperiod to 1.89 US dollars in the postperiod, compared with a 3.7% reduction in

  10. 25 CFR 700.469 - Unallowable program and project costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... application for a demonstration effort under § 700.459 may include costs relating to the operation of the... 25 Indians 2 2010-04-01 2010-04-01 false Unallowable program and project costs. 700.469 Section 700.469 Indians THE OFFICE OF NAVAJO AND HOPI INDIAN RELOCATION COMMISSION OPERATIONS AND RELOCATION...

  11. 24 CFR 954.303 - Eligible project costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 24 Housing and Urban Development 4 2010-04-01 2010-04-01 false Eligible project costs. 954.303 Section 954.303 Housing and Urban Development Regulations Relating to Housing and Urban Development (Continued) OFFICE OF ASSISTANT SECRETARY FOR PUBLIC AND INDIAN HOUSING, DEPARTMENT OF HOUSING AND URBAN...

  12. 23 CFR 646.210 - Classification of projects and railroad share of the cost.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 23 Highways 1 2010-04-01 2010-04-01 false Classification of projects and railroad share of the... ENGINEERING AND TRAFFIC OPERATIONS RAILROADS Railroad-Highway Projects § 646.210 Classification of projects and railroad share of the cost. (a) State laws requiring railroads to share in the cost of work for...

  13. Transportation Infrastructure: Managing the Costs of Large-Dollar Highway Projects

    DOT National Transportation Integrated Search

    1997-02-01

    The General Accounting Office (GAO) was requested to assess the effectiveness of the Federal Highway Administration's (FHWA's) oversight of the costs of large-dollar highway and bridge projects (those with a total estimated cost of over $100 million)...

  14. 20 CFR 632.37 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... CFR 1-15.7. (c) Costs associated with repairs, maintenance, and capital improvements of existing... when the agreement: (1) Is for classroom training; (2) Is fixed unit price; and (3) Stipulates that...

  15. Bidding cost evaluation with fuzzy methods on building project in Jakarta

    NASA Astrophysics Data System (ADS)

    Susetyo, Budi; Utami, Tin Budi

    2017-11-01

    National construction companies today demanded to become more competitive to face increasingly competition. Every construction company especially the contractor must work better than ever. Ability to prepare cost of the work that represents the efficiency and effectiveness of the implementation of the work necessary to produce cost - competitive. The project is considered successful if the target meets the quality, cost and time. From the aspect of cost, the project has been designed in accordance with certain technical criteria to be taken into account based on standard costs. To ensure the cost efficiency of the bidding process carried out meet the rules of a fairly and competitive. The research objective is to formulate the proper way to compare several deals with the standard cost of the work. The fuzzy technique is used as a evaluation methods to decision making. The evaluation not merely based on the lowest prices. The methods is looking for the most valuable and reasonable prices. The comparison is conducted to determine the most cost-competitive and reasonable as the winner of the bidding.

  16. Methods for cost estimation in software project management

    NASA Astrophysics Data System (ADS)

    Briciu, C. V.; Filip, I.; Indries, I. I.

    2016-02-01

    The speed in which the processes used in software development field have changed makes it very difficult the task of forecasting the overall costs for a software project. By many researchers, this task has been considered unachievable, but there is a group of scientist for which this task can be solved using the already known mathematical methods (e.g. multiple linear regressions) and the new techniques as genetic programming and neural networks. The paper presents a solution for building a model for the cost estimation models in the software project management using genetic algorithms starting from the PROMISE datasets related COCOMO 81 model. In the first part of the paper, a summary of the major achievements in the research area of finding a model for estimating the overall project costs is presented together with the description of the existing software development process models. In the last part, a basic proposal of a mathematical model of a genetic programming is proposed including here the description of the chosen fitness function and chromosome representation. The perspective of model described it linked with the current reality of the software development considering as basis the software product life cycle and the current challenges and innovations in the software development area. Based on the author's experiences and the analysis of the existing models and product lifecycle it was concluded that estimation models should be adapted with the new technologies and emerging systems and they depend largely by the chosen software development method.

  17. Contractors perspective for critical factors of cost overrun in highway projects of Sindh, Pakistan

    NASA Astrophysics Data System (ADS)

    Sohu, Samiullah; Abdullah, Abd Halid; Nagapan, Sasitharan; Fattah, Abdul; Ullah, Kaleem; Kumar, Kanesh

    2017-10-01

    Construction industry of Pakistan is creating a number of opportunities in employment as well as plays a role model for economy development of the country. This construction industry has a serious issue of cost overrun in all construction projects especially in construction of highway projects. Cost overrun is a serious and critical issue in construction of highway projects which gives negative impact to construction practitioners because it is not only cross the approved budget but also approved time of the project. The main objective of this study is to find out critical factors causing cost overrun in highway projects of Sindh according to contractors' perspectives. Deep literature review was carried out and a total of 64 factors of cost overrun were identified. To achieve the objective, a questionnaire was designed and distributed among 16 selected respondents who have more than 20 years of experience in construction of highway projects. The results from analysis found that most critical factors of cost overrun in the order of importance include financial and cash flow difficulties faced by contractor, frequent changes in design, changes in price of materials, poor planning by client, change in scope of project, change in specification of materials and delay in taking decisions. This study will assist contractors to narrow down some of the critical factors that would lead to cost overrun, and therefore be prepared with the ways to mitigate these problems in construction of highway projects of Sindh province.

  18. 34 CFR 643.30 - What are allowable costs?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... agreement, or rental of computer equipment and software needed for project administration and recordkeeping... objectives of the project: (a) Transportation, meals, and, if necessary, lodging for participants and project... on behalf of a participant. (d) In-service training of project staff. (e) Rental of space if— (1...

  19. 34 CFR 643.30 - What are allowable costs?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... agreement, or rental of computer equipment and software needed for project administration and recordkeeping... objectives of the project: (a) Transportation, meals, and, if necessary, lodging for participants and project... on behalf of a participant. (d) In-service training of project staff. (e) Rental of space if— (1...

  20. 34 CFR 643.30 - What are allowable costs?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... agreement, or rental of computer equipment and software needed for project administration and recordkeeping... objectives of the project: (a) Transportation, meals, and, if necessary, lodging for participants and project... on behalf of a participant. (d) In-service training of project staff. (e) Rental of space if— (1...

  1. 34 CFR 643.30 - What are allowable costs?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... agreement, or rental of computer equipment and software needed for project administration and recordkeeping... objectives of the project: (a) Transportation, meals, and, if necessary, lodging for participants and project... on behalf of a participant. (d) In-service training of project staff. (e) Rental of space if— (1...

  2. Development of a funding, cost, and spending model for satellite projects

    NASA Technical Reports Server (NTRS)

    Johnson, Jesse P.

    1989-01-01

    The need for a predictive budget/funging model is obvious. The current models used by the Resource Analysis Office (RAO) are used to predict the total costs of satellite projects. An effort to extend the modeling capabilities from total budget analysis to total budget and budget outlays over time analysis was conducted. A statistical based and data driven methodology was used to derive and develop the model. Th budget data for the last 18 GSFC-sponsored satellite projects were analyzed and used to build a funding model which would describe the historical spending patterns. This raw data consisted of dollars spent in that specific year and their 1989 dollar equivalent. This data was converted to the standard format used by the RAO group and placed in a database. A simple statistical analysis was performed to calculate the gross statistics associated with project length and project cost ant the conditional statistics on project length and project cost. The modeling approach used is derived form the theory of embedded statistics which states that properly analyzed data will produce the underlying generating function. The process of funding large scale projects over extended periods of time is described by Life Cycle Cost Models (LCCM). The data was analyzed to find a model in the generic form of a LCCM. The model developed is based on a Weibull function whose parameters are found by both nonlinear optimization and nonlinear regression. In order to use this model it is necessary to transform the problem from a dollar/time space to a percentage of total budget/time space. This transformation is equivalent to moving to a probability space. By using the basic rules of probability, the validity of both the optimization and the regression steps are insured. This statistically significant model is then integrated and inverted. The resulting output represents a project schedule which relates the amount of money spent to the percentage of project completion.

  3. A low-cost and portable realization on fringe projection three-dimensional measurement

    NASA Astrophysics Data System (ADS)

    Xiao, Suzhi; Tao, Wei; Zhao, Hui

    2015-12-01

    Fringe projection three-dimensional measurement is widely applied in a wide range of industrial application. The traditional fringe projection system has the disadvantages of high expense, big size, and complicated calibration requirements. In this paper we introduce a low-cost and portable realization on three-dimensional measurement with Pico projector. It has the advantages of low cost, compact physical size, and flexible configuration. For the proposed fringe projection system, there is no restriction to camera and projector's relative alignment on parallelism and perpendicularity for installation. Moreover, plane-based calibration method is adopted in this paper that avoids critical requirements on calibration system such as additional gauge block or precise linear z stage. What is more, error sources existing in the proposed system are introduced in this paper. The experimental results demonstrate the feasibility of the proposed low cost and portable fringe projection system.

  4. 42 CFR 405.2468 - Allowable costs.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... physician, physician assistant, nurse practitioner, certified nurse-midwife, visiting registered...) Costs of services and supplies incident to the services of a physician, physician assistant, nurse... services of physicians and for the services of physician assistants, nurse practitioners, and nurse...

  5. Variation in hospital costs and reimbursement for endovascular aneurysm repair: A Vascular Quality Initiative pilot project.

    PubMed

    Lemmon, Gary W; Neal, Dan; DeMartino, Randall R; Schneider, Joseph R; Singh, Tej; Kraiss, Larry; Scali, Salvatore; Tassiopoulos, Apostolos; Hoel, Andrew; Cronenwett, Jack L

    2017-10-01

    Comparing costs between centers is difficult because of the heterogeneity of vascular procedures contained in broad diagnosis-related group (DRG) billing categories. The purpose of this pilot project was to develop a mechanism to merge Vascular Quality Initiative (VQI) clinical data with hospital billing data to allow more accurate cost and reimbursement comparison for endovascular aneurysm repair (EVAR) procedures across centers. Eighteen VQI centers volunteered to submit UB04 billing data for 782 primary, elective infrarenal EVAR procedures performed by 108 surgeons in 2014. Procedures were categorized as standard or complex (with femoral-femoral bypass or additional arterial treatment) and without or with complications (arterial injury or embolectomy; bowel or leg ischemia; wound infection; reoperation; or cardiac, pulmonary, or renal complications), yielding four clinical groups for comparison. MedAssets, Inc, using cost to charge ratios, calculated total hospital costs and cost categories. Cost variation analyzed across centers was compared with DRG 237 (with major complication or comorbidity) and 238 (without major complication or comorbidity) coding. A multivariable model to predict DRG 237 coding was developed using VQI clinical data. Of the 782 EVAR procedures, 56% were standard and 15% had complications, with wide variation between centers. Mean total costs ranged from $31,100 for standard EVAR without complications to $47,400 for complex EVAR with complications and varied twofold to threefold among centers. Implant costs for standard EVAR without complications varied from $8100 to $28,200 across centers. Average Medicare reimbursement was less than total cost except for standard EVAR without complications. Only 9% of all procedures with complications in the VQI were reported in the higher reimbursed DRG 237 category (center range, 0%-21%). There was significant variation in hospitals' coding of DRG 237 compared with their expected rates. VQI clinical

  6. Fast Paced, Low Cost Projects at MSFC

    NASA Technical Reports Server (NTRS)

    Watson-Morgan, Lisa; Clinton, Raymond

    2012-01-01

    What does an orbiting microsatellite, a robotic lander and a ruggedized camera and telescope have in common? They are all fast paced, low cost projects managed by Marshall Space Flight Center (MSFC) teamed with successful industry partners. MSFC has long been synonymous with human space flight large propulsion programs, engineering acumen and risk intolerance. However, there is a growing portfolio/product line within MSFC that focuses on these smaller, fast paced projects. While launching anything into space is expensive, using a managed risk posture, holding to schedule and keeping costs low by stopping at egood enough f were key elements to their success. Risk is defined as the possibility of loss or failure per Merriam Webster. The National Aeronautics and Space Administration (NASA) defines risk using procedural requirement 8705.4 and establishes eclasses f to discern the acceptable risk per a project. It states a Class D risk has a medium to significant risk of not achieving mission success. MSFC, along with industry partners, has created a niche in Class D efforts. How did the big, cautious MSFC succeed on these projects that embodied the antithesis of its heritage in human space flight? A key factor toward these successful projects was innovative industry partners such as Dynetics Corporation, University of Alabama in Huntsville (UAHuntsville), Johns Hopkins Applied Physics Laboratory (JHU APL), Teledyne Brown Engineering (TBE), Von Braun Center for Science and Innovation (VCSI), SAIC, and Jacobs. Fast Affordable Satellite Technology (FastSat HSV01) is a low earth orbit microsatellite that houses six instruments with the primary scientific objective of earth observation and technology demonstration. The team was comprised of Dynetics, UAHuntsvile, SAIC, Goddard Space Flight Center (GSFC) and VCSI with the United States Air Force Space Test Program as the customer. The team completed design, development, manufacturing, environmental test and integration in

  7. Project Antares: A low cost modular launch vehicle for the future

    NASA Astrophysics Data System (ADS)

    Aarnio, Steve; Anderson, Hobie; Arzaz, El Mehdi; Bailey, Michelle; Beeghly, Jeff; Cartwright, Curt; Chau, William; Dawdy, Andrew; Detert, Bruce; Ervin, Miles

    1991-06-01

    The single stage to orbit launch vehicle Antares is based upon the revolutionary concept of modularity, enabling the Antares to efficiently launch communications satellites, as well as heavy payloads, into Earth's orbit and beyond. The basic unit of the modular system, a single Antares vehicle, is aimed at launching approximately 10,000 kg into low Earth orbit (LEO). When coupled with a Centaur upper stage it is capable of placing 3500 kg into geostationary orbit. The Antares incorporates a reusable engine, the Dual Mixture Ratio Engine (DMRE), as its propulsive device. This enables Antares to compete and excel in the satellite launch market by dramatically reducing launch costs. Antares' projected launch costs are $1340 per kg to LEO which offers a tremendous savings over launch vehicles available today. Inherent in the design is the capability to attach several of these vehicles together to provide heavy lift capability. Any number of these vehicles, up to seven, can be attached depending on the payload and mission requirements. With a seven vehicle configuration Antares's modular concept provides a heavy lift capability of approximately 70,000 kg to LEO. This expandability allows for a wider range of payload options such as large Earth satellites, Space Station Freedom support, and interplanetary spacecraft, and also offers a significant cost savings over a mixed fleet based on different launch vehicles.

  8. Project Antares: A low cost modular launch vehicle for the future

    NASA Technical Reports Server (NTRS)

    Aarnio, Steve; Anderson, Hobie; Arzaz, El Mehdi; Bailey, Michelle; Beeghly, Jeff; Cartwright, Curt; Chau, William; Dawdy, Andrew; Detert, Bruce; Ervin, Miles

    1991-01-01

    The single stage to orbit launch vehicle Antares is based upon the revolutionary concept of modularity, enabling the Antares to efficiently launch communications satellites, as well as heavy payloads, into Earth's orbit and beyond. The basic unit of the modular system, a single Antares vehicle, is aimed at launching approximately 10,000 kg into low Earth orbit (LEO). When coupled with a Centaur upper stage it is capable of placing 3500 kg into geostationary orbit. The Antares incorporates a reusable engine, the Dual Mixture Ratio Engine (DMRE), as its propulsive device. This enables Antares to compete and excel in the satellite launch market by dramatically reducing launch costs. Antares' projected launch costs are $1340 per kg to LEO which offers a tremendous savings over launch vehicles available today. Inherent in the design is the capability to attach several of these vehicles together to provide heavy lift capability. Any number of these vehicles, up to seven, can be attached depending on the payload and mission requirements. With a seven vehicle configuration Antares's modular concept provides a heavy lift capability of approximately 70,000 kg to LEO. This expandability allows for a wider range of payload options such as large Earth satellites, Space Station Freedom support, and interplanetary spacecraft, and also offers a significant cost savings over a mixed fleet based on different launch vehicles.

  9. 24 CFR 92.301 - Project-specific assistance to community housing development organizations.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... (including costs of an initial feasibility study), consulting fees, costs of preliminary financial... participating jurisdiction determines to be customary and reasonable project preparation costs allowable under paragraph (a)(2) of this section. All costs must be related to a specific eligible project or projects. (2...

  10. 42 CFR 405.2468 - Allowable costs.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... covered and reasonable: (1) Compensation for the services of a physician, physician assistant, nurse...) Costs of services and supplies incident to the services of a physician, physician assistant, nurse... and supervisory services of physicians and for the services of physician assistants, nurse...

  11. 42 CFR 405.2468 - Allowable costs.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... covered and reasonable: (1) Compensation for the services of a physician, physician assistant, nurse...) Costs of services and supplies incident to the services of a physician, physician assistant, nurse... and supervisory services of physicians and for the services of physician assistants, nurse...

  12. A new compact, cost-efficient concept for underwater range-gated imaging: the UTOFIA project

    NASA Astrophysics Data System (ADS)

    Mariani, Patrizio; Quincoces, Iñaki; Galparsoro, Ibon; Bald, Juan; Gabiña, Gorka; Visser, Andy; Jónasdóttir, Sigrun; Haugholt, Karl Henrik; Thorstensen, Jostein; Risholm, Petter; Thielemann, Jens

    2017-04-01

    Underwater Time Of Flight Image Acquisition system (UTOFIA) is a recently launched H2020 project (H2020 - 633098) to develop a compact and cost-effective underwater imaging system especially suited for observations in turbid environments. The UTOFIA project targets technology that can overcome the limitations created by scattering, by introducing cost-efficient range-gated imaging for underwater applications. This technology relies on a image acquisition principle that can extends the imaging range of the cameras 2-3 times respect to other cameras. Moreover, the system will simultaneously capture 3D information of the observed objects. Today range-gated imaging is not widely used, as it relies on specialised optical components making systems large and costly. Recent technology developments have made it possible a significant (2-3 times) reduction in size, complexity and cost of underwater imaging systems, whilst addressing the scattering issues at the same time. By acquiring simultaneous 3D data, the system allows to accurately measure the absolute size of marine life and their spatial relationship to their habitat, enhancing the precision of fish stock monitoring and ecology assessment, hence supporting proper management of marine resources. Additionally, the larger observed volume and the improved image quality make the system suitable for cost-effective underwater surveillance operations in e.g. fish farms, underwater infrastructures. The system can be integrated into existing ocean observatories for real time acquisition and can greatly advance present efforts in developing species recognition algorithms, given the additional features provided, the improved image quality and the independent illumination source based on laser. First applications of the most recent prototype of the imaging system will be provided including inspection of underwater infrastructures and observations of marine life under different environmental conditions.

  13. Meaningful Cost-Benefit Analysis for Service-Oriented Architecture Projects

    DTIC Science & Technology

    2010-05-01

    SOA to identify these activities and shows how those costs come to be commingled with other development and maintenance activities. The paper argues...affected by SOA . To be consistent with the separation suggested above, this paper suggests the following new activities: • Enterprise architecture...Government or Federal Rights License 14. ABSTRACT This paper argues that proper cost-benefit analysis of service-oriented architecture projects is not

  14. 78 FR 61227 - Public Assistance Cost Estimating Format for Large Projects

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-10-03

    ... itemized breakdown of construction costs for completing the project. For example, a typical project will... percentage factors. For example, if a Part B percentage factor is 2 percent, the estimator adds 2 percent of... specific to the project scope of work. Examples include concrete strength testing, water quality testing...

  15. [Evaluation on cost-effectiveness of snail control project by environmental modification in hilly regions].

    PubMed

    Li, Shui-Ming; Chen, Shi-Jun; Wu, Xiao-Jun; Chen, Xi-Qing; Zhang, Rong-Ping; Zhang, Jian-Rong

    2011-02-01

    To evaluate the cost-effectiveness of the snail control project by environmental modification in order to provide the evidence for quickly interrupting the transmission of schistosomiasis in hilly regions. Field investigations were carried out. The changes of the snail habitat areas were compared before and after the snail control project. The direct costs of the snail control were calculated. The reduction rates of snail area and snail density were regarded as the evaluation indexes of the effectiveness. The costs for reduction of 1% of snail area and 1% of snail density were used as the unit for cost-effectiveness analysis. After the 15 projects were implemented, there were no snails in 12 areas. The reduction rates of snail areas were 72.22% to 100%. The reduction rates of the snail area and density were both 100% in the areas with digging new ditches to fill up the old ones and building reservoirs. The total cost of 15 projects was 1 450 800 Yuan. The average cost per unit was 0.56 Yuan/m2. After the snail control project by digging new ditches to fill up the old ones was implemented, the costs of snail area and density decreased by one unit were 300 -700 Yuan, by building reservoirs, the costs were 600 -2 600 Yuan, by building fishpond, the costs were 1 200 - 1 500 Yuan, by watershed comprehensive measures, the costs were 900 - 2 700 Yuan. The cost of digging new ditches to fill up the old ones was significantly lower than that of building reservoirs or watershed comprehensive measures, but there was no significant difference between building reservoirs and watershed comprehensive measures. In hilly regions, the implementation of snail control project by environmental modification combined with construction of water conservancy is effective, and the cost-effectiveness of the snail control with digging new ditches to fill up the old ones is excellent.

  16. 13 CFR 120.882 - Eligible Project costs for 504 loans.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... expansion may be refinanced and added to the expansion cost if: (1) Substantially all (85% or more) of the...). Prepayment penalties, financing fees, and other financing costs must also be added to the amount being... current fair market value of the fixed assets serving as collateral for the Refinancing Project, including...

  17. Cost and schedule management on the quiet short-haul research aircraft project

    NASA Technical Reports Server (NTRS)

    Wilcox, D. E.; Patterakis, P.

    1979-01-01

    The Quiet Short-Haul Research Aircraft (QSRA) Project, one of the largest aeronautical programs undertaken by NASA to date, achieved a significant cost underrun. This is attributed to numerous factors, not the least of which were the contractual arrangement and the system of cost and schedule management employed by the contractor. This paper summarizes that system and the methods used for cost/performance measurement by the contractor and by the NASA project management. Recommendations are made for the use of some of these concepts in particular for future programs of a similar nature.

  18. Projecting Serials Costs: Banking on the Past to Buy for the Future.

    ERIC Educational Resources Information Center

    Ketcham, Lee; Born, Kathleen

    1994-01-01

    Reports on a survey of international periodicals' cost history, country of origin information, and currency exchange rate to assist in identifying trends in the cost of periodicals and to project costs for the coming year. Tables present cost data by subject, continent/country or origin, and type of library. (SLW)

  19. 18 CFR 2.25 - Ratemaking treatment of the cost of emissions allowances in coordination transactions.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 18 Conservation of Power and Water Resources 1 2012-04-01 2012-04-01 false Ratemaking treatment of the cost of emissions allowances in coordination transactions. 2.25 Section 2.25 Conservation of Power and Water Resources FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY GENERAL RULES GENERAL...

  20. 18 CFR 2.25 - Ratemaking treatment of the cost of emissions allowances in coordination transactions.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 18 Conservation of Power and Water Resources 1 2013-04-01 2013-04-01 false Ratemaking treatment of the cost of emissions allowances in coordination transactions. 2.25 Section 2.25 Conservation of Power and Water Resources FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY GENERAL RULES GENERAL...

  1. 18 CFR 2.25 - Ratemaking treatment of the cost of emissions allowances in coordination transactions.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 18 Conservation of Power and Water Resources 1 2014-04-01 2014-04-01 false Ratemaking treatment of the cost of emissions allowances in coordination transactions. 2.25 Section 2.25 Conservation of Power and Water Resources FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY GENERAL RULES GENERAL...

  2. 18 CFR 2.25 - Ratemaking treatment of the cost of emissions allowances in coordination transactions.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 18 Conservation of Power and Water Resources 1 2010-04-01 2010-04-01 false Ratemaking treatment of the cost of emissions allowances in coordination transactions. 2.25 Section 2.25 Conservation of Power and Water Resources FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY GENERAL RULES GENERAL...

  3. 40 CFR 30.27 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... of appendix E of 45 CFR part 74, “Principles for Determining Costs Applicable to Research and... consultants retained by recipients or by a recipient's contractors or subcontractors to the maximum daily rate... designated individuals with specialized skills who are paid at a daily or hourly rate. This rate does not...

  4. Evaluation of the Field Test of Project Information Packages: Volume III--Resource Cost Analysis.

    ERIC Educational Resources Information Center

    Al-Salam, Nabeel; And Others

    The third of three volumes evaluating the first year field test of the Project Information Packages (PIPs) provides a cost analysis study as a key element in the total evaluation. The resource approach to cost analysis is explained and the specific resource methodology used in the main cost analysis of the 19 PIP field-test projects detailed. The…

  5. 34 CFR 645.40 - What are allowable costs?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... of the project: (a) In-service training of project staff. (b) Rental of space if space is not... trips, attend educational activities, visit museums, and attend other events that have as their purpose... overnight accommodations for staff members when they are required to accompany participants in project...

  6. 20 CFR 633.303 - Allowable costs.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... and OMB Circular A-122. (c) Funds may be used for construction activities only to: (1) Provide... but may be charged entirely to training when the agreement: (1) Is for classroom training; (2) Is... occupation trained for and at not less than the wage specified in the agreement. (g) Travel costs. (1) The...

  7. An innovative time-cost-quality tradeoff modeling of building construction project based on resource allocation.

    PubMed

    Hu, Wenfa; He, Xinhua

    2014-01-01

    The time, quality, and cost are three important but contradictive objectives in a building construction project. It is a tough challenge for project managers to optimize them since they are different parameters. This paper presents a time-cost-quality optimization model that enables managers to optimize multiobjectives. The model is from the project breakdown structure method where task resources in a construction project are divided into a series of activities and further into construction labors, materials, equipment, and administration. The resources utilized in a construction activity would eventually determine its construction time, cost, and quality, and a complex time-cost-quality trade-off model is finally generated based on correlations between construction activities. A genetic algorithm tool is applied in the model to solve the comprehensive nonlinear time-cost-quality problems. Building of a three-storey house is an example to illustrate the implementation of the model, demonstrate its advantages in optimizing trade-off of construction time, cost, and quality, and help make a winning decision in construction practices. The computational time-cost-quality curves in visual graphics from the case study prove traditional cost-time assumptions reasonable and also prove this time-cost-quality trade-off model sophisticated.

  8. 50 CFR 84.49 - What if the project costs more or less than originally expected?

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 50 Wildlife and Fisheries 9 2013-10-01 2013-10-01 false What if the project costs more or less... § 84.49 What if the project costs more or less than originally expected? All requests for additional... grants. Any monies left over after the project is complete, or if the project is not completed, should be...

  9. 50 CFR 84.49 - What if the project costs more or less than originally expected?

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 50 Wildlife and Fisheries 9 2012-10-01 2012-10-01 false What if the project costs more or less... § 84.49 What if the project costs more or less than originally expected? All requests for additional... grants. Any monies left over after the project is complete, or if the project is not completed, should be...

  10. 50 CFR 84.49 - What if the project costs more or less than originally expected?

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 50 Wildlife and Fisheries 9 2014-10-01 2014-10-01 false What if the project costs more or less... § 84.49 What if the project costs more or less than originally expected? All requests for additional... grants. Any monies left over after the project is complete, or if the project is not completed, should be...

  11. A user-friendly, open-source tool to project impact and cost of diagnostic tests for tuberculosis

    PubMed Central

    Dowdy, David W; Andrews, Jason R; Dodd, Peter J; Gilman, Robert H

    2014-01-01

    Most models of infectious diseases, including tuberculosis (TB), do not provide results customized to local conditions. We created a dynamic transmission model to project TB incidence, TB mortality, multidrug-resistant (MDR) TB prevalence, and incremental costs over 5 years after scale-up of nine alternative diagnostic strategies. A corresponding web-based interface allows users to specify local costs and epidemiology. In settings with little capacity for up-front investment, same-day microscopy had the greatest impact on TB incidence and became cost-saving within 5 years if delivered at $10/test. With greater initial investment, population-level scale-up of Xpert MTB/RIF or microcolony-based culture often averted 10 times more TB cases than narrowly-targeted strategies, at minimal incremental long-term cost. Xpert for smear-positive TB had reasonable impact on MDR-TB incidence, but at substantial price and little impact on overall TB incidence and mortality. This user-friendly modeling framework improves decision-makers' ability to evaluate the local impact of TB diagnostic strategies. DOI: http://dx.doi.org/10.7554/eLife.02565.001 PMID:24898755

  12. Costs Climb on Materials for Schools: Construction Projects Delayed, Scrapped

    ERIC Educational Resources Information Center

    Sack, Joetta L.

    2004-01-01

    The rapidly rising cost of steel and other construction materials is forcing some districts that are building new schools to scramble for more money, delay work, or redesign projects. Nationwide, contractors and architects are finding it harder to give accurate estimates on projects, and some have even had to renegotiate contracts with districts.…

  13. 44 CFR 208.41 - Administrative allowance.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... $100,000 or more but less than $1,000,000, $3,000 plus 2 percent of costs included in the reimbursement claim greater than $100,000; (3) If total allowable costs are $1,000,000 or more, $21,000 plus 1 percent... administrative allowance will be equal to the following: (1) If total allowable costs are less than $100,000, 3...

  14. A life cycle cost economics model for automation projects with uniformly varying operating costs. [applied to Deep Space Network and Air Force Systems Command

    NASA Technical Reports Server (NTRS)

    Remer, D. S.

    1977-01-01

    The described mathematical model calculates life-cycle costs for projects with operating costs increasing or decreasing linearly with time. The cost factors involved in the life-cycle cost are considered, and the errors resulting from the assumption of constant rather than uniformly varying operating costs are examined. Parameters in the study range from 2 to 30 years, for project life; 0 to 15% per year, for interest rate; and 5 to 90% of the initial operating cost, for the operating cost gradient. A numerical example is presented.

  15. 44 CFR 79.8 - Allowable costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... from another source. (d) Negligence or other tortious conduct. FEMA grant funds are not available where an applicant, subapplicant, other project participant, or third party's negligence or intentional... participant suspects negligence or other tortious conduct by a third party for causing such condition, they...

  16. Fast and low-cost structured light pattern sequence projection.

    PubMed

    Wissmann, Patrick; Forster, Frank; Schmitt, Robert

    2011-11-21

    We present a high-speed and low-cost approach for structured light pattern sequence projection. Using a fast rotating binary spatial light modulator, our method is potentially capable of projection frequencies in the kHz domain, while enabling pattern rasterization as low as 2 μm pixel size and inherently linear grayscale reproduction quantized at 12 bits/pixel or better. Due to the circular arrangement of the projected fringe patterns, we extend the widely used ray-plane triangulation method to ray-cone triangulation and provide a detailed description of the optical calibration procedure. Using the proposed projection concept in conjunction with the recently published coded phase shift (CPS) pattern sequence, we demonstrate high accuracy 3-D measurement at 200 Hz projection frequency and 20 Hz 3-D reconstruction rate. © 2011 Optical Society of America

  17. 75 FR 8245 - Natural Gas Pipelines; Project Cost and Annual Limits

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-02-24

    ...] Natural Gas Pipelines; Project Cost and Annual Limits February 18, 2010. AGENCY: Federal Energy Regulatory... for natural gas pipelines blanket construction certificates for each calendar year. DATES: This final..., Natural gas, Reporting and recordkeeping requirements. Jeff C. Wright, Director, Office of Energy Projects...

  18. 44 CFR 80.9 - Eligible and ineligible costs.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... ACQUISITION AND RELOCATION FOR OPEN SPACE Requirements Prior to Award § 80.9 Eligible and ineligible costs. (a... eligible entity, compensation for the land is not an allowable cost, but compensation for development... costs for activities directly related to the development of the project proposal. These costs can only...

  19. 34 CFR 646.30 - What are allowable costs?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... participant development, project administration, or project recordkeeping. (g) Professional development travel... of the participants' academic progress and personal development. (e) Transportation and, with the...

  20. LSSA (Low-cost Silicon Solar Array) project

    NASA Technical Reports Server (NTRS)

    1976-01-01

    Methods are explored for economically generating electrical power to meet future requirements. The Low-Cost Silicon Solar Array Project (LSSA) was established to reduce the price of solar arrays by improving manufacturing technology, adapting mass production techniques, and promoting user acceptance. The new manufacturing technology includes the consideration of new silicon refinement processes, silicon sheet growth techniques, encapsulants, and automated assembly production being developed under contract by industries and universities.

  1. An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation

    PubMed Central

    2014-01-01

    The time, quality, and cost are three important but contradictive objectives in a building construction project. It is a tough challenge for project managers to optimize them since they are different parameters. This paper presents a time-cost-quality optimization model that enables managers to optimize multiobjectives. The model is from the project breakdown structure method where task resources in a construction project are divided into a series of activities and further into construction labors, materials, equipment, and administration. The resources utilized in a construction activity would eventually determine its construction time, cost, and quality, and a complex time-cost-quality trade-off model is finally generated based on correlations between construction activities. A genetic algorithm tool is applied in the model to solve the comprehensive nonlinear time-cost-quality problems. Building of a three-storey house is an example to illustrate the implementation of the model, demonstrate its advantages in optimizing trade-off of construction time, cost, and quality, and help make a winning decision in construction practices. The computational time-cost-quality curves in visual graphics from the case study prove traditional cost-time assumptions reasonable and also prove this time-cost-quality trade-off model sophisticated. PMID:24672351

  2. The Problem with the Delta Cost Project Database

    ERIC Educational Resources Information Center

    Jaquette, Ozan; Parra, Edna

    2016-01-01

    The Integrated Postsecondary Education System (IPEDS) collects data on Title IV institutions. The Delta Cost Project (DCP) integrated data from multiple IPEDS survey components into a public-use longitudinal dataset. The DCP Database was the basis for dozens of journal articles and a series of influential policy reports. Unfortunately, a flaw in…

  3. Experiences of operational costs of HPV vaccine delivery strategies in Gavi-supported demonstration projects

    PubMed Central

    Holroyd, Taylor; Nanda, Shreya; Bloem, Paul; Griffiths, Ulla K.; Sidibe, Anissa; Hutubessy, Raymond C. W.

    2017-01-01

    From 2012 to 2016, Gavi, the Vaccine Alliance, provided support for countries to conduct small-scale demonstration projects for the introduction of the human papillomavirus vaccine, with the aim of determining which human papillomavirus vaccine delivery strategies might be effective and sustainable upon national scale-up. This study reports on the operational costs and cost determinants of different vaccination delivery strategies within these projects across twelve countries using a standardized micro-costing tool. The World Health Organization Cervical Cancer Prevention and Control Costing Tool was used to collect costing data, which were then aggregated and analyzed to assess the costs and cost determinants of vaccination. Across the one-year demonstration projects, the average economic and financial costs per dose amounted to US$19.98 (standard deviation ±12.5) and US$8.74 (standard deviation ±5.8), respectively. The greatest activities representing the greatest share of financial costs were social mobilization at approximately 30% (range, 6–67%) and service delivery at about 25% (range, 3–46%). Districts implemented varying combinations of school-based, facility-based, or outreach delivery strategies and experienced wide variation in vaccine coverage, drop-out rates, and service delivery costs, including transportation costs and per diems. Size of target population, number of students per school, and average length of time to reach an outreach post influenced cost per dose. Although the operational costs from demonstration projects are much higher than those of other routine vaccine immunization programs, findings from our analysis suggest that HPV vaccination operational costs will decrease substantially for national introduction. Vaccination costs may be decreased further by annual vaccination, high initial investment in social mobilization, or introducing/strengthening school health programs. Our analysis shows that drivers of cost are dependent on

  4. Experiences of operational costs of HPV vaccine delivery strategies in Gavi-supported demonstration projects.

    PubMed

    Botwright, Siobhan; Holroyd, Taylor; Nanda, Shreya; Bloem, Paul; Griffiths, Ulla K; Sidibe, Anissa; Hutubessy, Raymond C W

    2017-01-01

    From 2012 to 2016, Gavi, the Vaccine Alliance, provided support for countries to conduct small-scale demonstration projects for the introduction of the human papillomavirus vaccine, with the aim of determining which human papillomavirus vaccine delivery strategies might be effective and sustainable upon national scale-up. This study reports on the operational costs and cost determinants of different vaccination delivery strategies within these projects across twelve countries using a standardized micro-costing tool. The World Health Organization Cervical Cancer Prevention and Control Costing Tool was used to collect costing data, which were then aggregated and analyzed to assess the costs and cost determinants of vaccination. Across the one-year demonstration projects, the average economic and financial costs per dose amounted to US$19.98 (standard deviation ±12.5) and US$8.74 (standard deviation ±5.8), respectively. The greatest activities representing the greatest share of financial costs were social mobilization at approximately 30% (range, 6-67%) and service delivery at about 25% (range, 3-46%). Districts implemented varying combinations of school-based, facility-based, or outreach delivery strategies and experienced wide variation in vaccine coverage, drop-out rates, and service delivery costs, including transportation costs and per diems. Size of target population, number of students per school, and average length of time to reach an outreach post influenced cost per dose. Although the operational costs from demonstration projects are much higher than those of other routine vaccine immunization programs, findings from our analysis suggest that HPV vaccination operational costs will decrease substantially for national introduction. Vaccination costs may be decreased further by annual vaccination, high initial investment in social mobilization, or introducing/strengthening school health programs. Our analysis shows that drivers of cost are dependent on

  5. Incentive contracts for development projects

    NASA Astrophysics Data System (ADS)

    Finley, David T.; Smith, Byron; DeGroff, B.

    2012-09-01

    Finding a contract vehicle that balances the concerns of the customer and the contractor in a development project can be difficult. The customer wants a low price and an early delivery, with as few surprises as possible as the project progresses. The contractor wants sufficient cost and schedule to cover risk. Both want to clearly define what each party will provide. Many program offices do not want to award cost plus contracts because their funding sources will not allow it, their boards do not want an open ended commitment, and they feel like they lose financial control of the project. A fixed price incentive contract, with a mutually agreed upon target cost, provides the owner with visibility into the project and input into the execution of the project, encourages both parties to save costs, and stimulates a collaborative atmosphere by aligning the respective interests of customers and contractors.

  6. A Cost-and-Benefit Study of Two Americorps Projects in the State of Washington.

    ERIC Educational Resources Information Center

    Wang, Changhua; And Others

    AmeriCorps is a national initiative that involves citizens in strengthening America's communities through community service. This document presents findings of a cost-benefit analysis of two AmeriCorps programs in Washington State--the Hoquiam Project and the Lake Chelan Project. In calculating annual costs, the study included both federal dollars…

  7. Army Corps of Engineers: Factors Contributing to Cost Increases and Schedule Delays in the Olmsted Locks and Dam Project

    DTIC Science & Technology

    2017-02-01

    to cost increases and schedule delays and (2) what is known about the costs of benefits foregone because of project delays. GAO compared the...Contributors to Cost Increases and Schedule Delays 13 Total Cost of Benefits Foregone from Project Delays at Olmsted Is Uncertain 27 Agency Comments...would take 7 years. The Corps also estimated benefits , such as transportation cost savings, associated with the project. However, once the project was

  8. Evaluation of utility relocation costs and best management practices : final report : SCDOT research project 684.

    DOT National Transportation Integrated Search

    2014-05-21

    In recent years, the SCDOT has experienced a significant variation in estimated costs for the relocation of : utilities on many projects. This has led to cost overruns and caused headaches for the district engineers : responsible for the projects. Th...

  9. New vaccines against otitis media: projected benefits and cost-effectiveness.

    PubMed

    O'Brien, Megan A; Prosser, Lisa A; Paradise, Jack L; Ray, G Thomas; Kulldorff, Martin; Kurs-Lasky, Marcia; Hinrichsen, Virginia L; Mehta, Jyotsna; Colborn, D Kathleen; Lieu, Tracy A

    2009-06-01

    New vaccines that offer protection against otitis media caused by nontypeable Haemophilus influenzae and by Moraxella catarrhalis are under development. However, the potential health benefits and economic effects of such candidate vaccines have not been systematically assessed. We created a computerized model to compare the projected benefits and costs of (1) the currently available 7-valent pneumococcal conjugate vaccine, (2) a candidate pneumococcal-nontypeable H influenzae vaccine that has been tested in Europe, (3) a hypothetical pneumococcal-nontypeable H influenzae-Moraxella vaccine, and (4) no vaccination. The clinical probabilities of acute otitis media and of otitis media with effusion were generated from multivariate analyses of data from 2 large health maintenance organizations and from the Pittsburgh Child Development/Otitis Media Study cohort. Other probabilities, costs, and quality-of-life values were derived from published and unpublished sources. The base-case analysis assumed vaccine dose costs of $65 for the 7-valent pneumococcal conjugate vaccine, $100 for the pneumococcal-nontypeable H influenzae vaccine, and $125 for the pneumococcal-nontypeable H influenzae-Moraxella vaccine. With no vaccination, we projected that 13.7 million episodes of acute otitis media would occur annually in US children aged 0 to 4 years, at an annual cost of $3.8 billion. The 7-valent pneumococcal conjugate vaccine was projected to prevent 878,000 acute otitis media episodes, or 6.4% of those that would occur with no vaccination; the corresponding value for the pneumococcal-nontypeable H influenzae vaccine was 3.7 million (27%) and for the pneumococcal-nontypeable H influenzae-Moraxella vaccine was 4.2 million (31%). Using the base-case vaccine costs, pneumococcal-nontypeable H influenzae vaccine use would result in net savings compared with nontypeable 7-valent pneumococcal conjugate use. Conversely, pneumococcal-nontypeable H influenzae-Moraxella vaccine use would not

  10. Application of Boosting Regression Trees to Preliminary Cost Estimation in Building Construction Projects

    PubMed Central

    2015-01-01

    Among the recent data mining techniques available, the boosting approach has attracted a great deal of attention because of its effective learning algorithm and strong boundaries in terms of its generalization performance. However, the boosting approach has yet to be used in regression problems within the construction domain, including cost estimations, but has been actively utilized in other domains. Therefore, a boosting regression tree (BRT) is applied to cost estimations at the early stage of a construction project to examine the applicability of the boosting approach to a regression problem within the construction domain. To evaluate the performance of the BRT model, its performance was compared with that of a neural network (NN) model, which has been proven to have a high performance in cost estimation domains. The BRT model has shown results similar to those of NN model using 234 actual cost datasets of a building construction project. In addition, the BRT model can provide additional information such as the importance plot and structure model, which can support estimators in comprehending the decision making process. Consequently, the boosting approach has potential applicability in preliminary cost estimations in a building construction project. PMID:26339227

  11. Application of Boosting Regression Trees to Preliminary Cost Estimation in Building Construction Projects.

    PubMed

    Shin, Yoonseok

    2015-01-01

    Among the recent data mining techniques available, the boosting approach has attracted a great deal of attention because of its effective learning algorithm and strong boundaries in terms of its generalization performance. However, the boosting approach has yet to be used in regression problems within the construction domain, including cost estimations, but has been actively utilized in other domains. Therefore, a boosting regression tree (BRT) is applied to cost estimations at the early stage of a construction project to examine the applicability of the boosting approach to a regression problem within the construction domain. To evaluate the performance of the BRT model, its performance was compared with that of a neural network (NN) model, which has been proven to have a high performance in cost estimation domains. The BRT model has shown results similar to those of NN model using 234 actual cost datasets of a building construction project. In addition, the BRT model can provide additional information such as the importance plot and structure model, which can support estimators in comprehending the decision making process. Consequently, the boosting approach has potential applicability in preliminary cost estimations in a building construction project.

  12. Urban rail transit projects : forecast versus actual ridership and costs. final report

    DOT National Transportation Integrated Search

    1989-10-01

    Substantial errors in forecasting ridership and costs for the ten rail transit projects reviewed in this report, put forth the possibility that more accurate forecasts would have led decision-makers to select projects other than those reviewed in thi...

  13. Cheap-GSHPs, an European project aiming cost-reducing innovations for shallow geothermal installations. - Geological data reinterpretation

    NASA Astrophysics Data System (ADS)

    Bertermann, David; Müller, Johannes; Galgaro, Antonio; Cultrera, Matteo; Bernardi, Adriana; Di Sipio, Eloisa

    2016-04-01

    The success and widespread diffusion of new sustainable technologies are always strictly related to their affordability. Nowadays the energy price fluctuations and the economic crisis are jeopardizing the development and diffusion of renewable technologies and sources. With the aim of both reduce the overall costs of shallow geothermal systems and improve their installation safety, an European project has took place recently, under the Horizon 2020 EU Framework Programme for Research and Innovation. The acronym of this project is Cheap-GSHPs, meaning "cheap and efficient application of reliable ground source heat exchangers and pumps"; the CHEAP-GSHPs project involves 17 partners among 9 European countries such Belgium, France, Germany, Greece, Ireland, Italy, Romania, Spain, Switzerland. In order to achieve the planned targets, an holistic approach is adopted, where all involved elements that take part of shallow geothermal activities are here integrated. In order to reduce the drilling specific costs and for a solid planning basis the INSPIRE-conformal ESDAC data set PAR-MAT-DOM ("parent material dominant") was analysed and reinterpreted regarding the opportunities for cost reductions. Different ESDAC classification codes were analysed lithologically and sedimentologically in order to receive the most suitable drilling technique within different formations. Together with drilling companies this geological data set was translated into a geotechnical map which allows drilling companies the usage of the most efficient drilling within a certain type of underground. The scale of the created map is 1: 100,000 for all over Europe. This leads to cost reductions for the final consumers. Further there will be the definition of different heat conductivity classes based on the reinterpreted PAR-MAT-DOM data set which will provide underground information. These values will be reached by sampling data all over Europe and literature data. The samples will be measured by several

  14. Investigation on the Factors Influencing Construction Time and Cost Overrun for High-Rise Building Projects In Penang

    NASA Astrophysics Data System (ADS)

    Nor Haslinda, A.; Xian, T. Wei; Norfarahayu, K.; Muhamad Hanafi, R.; Fikri, H. Muhammad

    2018-04-01

    Time and cost overruns have become one prominent issue for most construction projects around the world. Project costing and timeframe extension had been causing a lot of wastage and loss of opportunity for many parties involved. Therefore, this research was carried out to investigate the factors influencing time and cost overruns for high-rise construction projects in Penang, Malaysia. A set of questionnaires survey was distributed to the project managers who had been or currently involved in the high-rise building projects in Penang to get their input and perceptions for each factor identified as well as its frequency of occurrence. In order to rank all the factors gathered, the mean index of the most distinguishing factors and its frequency of occurrence were multiplied to get the severity index. The results revealed that for time overrun, the most predominant causes were due to design changes, inadequate planning and scheduling and poor labor productivity. Meanwhile, the predominant causes of cost overrun were poor pre-construction budget and material cost planning, inaccurate quantity take-off and materials cost increased by inflation. The significance of establishing the issues related to time and cost overruns for the high-rise building construction project is to provide a greater insight and understanding on the causes of delays, particularly among the main project players: contractors, client, and consultants.

  15. The implications of regional and national demographic projections for future GMS costs in Ireland through to 2026.

    PubMed

    Conway, Aisling; Kenneally, Martin; Woods, Noel; Thummel, Andreas; Ryan, Marie

    2014-10-21

    As the health services in Ireland have become more resource-constrained, pressure has increased to reduce public spending on community drug schemes such as General Medical Services (GMS) drug prescribing and to understand current and future trends in prescribing. The GMS scheme covers approximately 37% of the Irish population in 2011 and entitles them, inter alia, to free prescription drugs and appliances. This paper projects the effects of future changes in population, coverage, claims rates and average claims cost on GMS costs in Ireland. Data on GMS coverage, claims rates and average cost per claim are drawn from the Primary Care Reimbursement Service (PCRS) and combined with Central Statistics Office (CSO) (Regional and National Population Projections through to 2026). A Monte Carlo Model is used to simulate the effects of demographic change (by region, age, gender, coverage, claims rates and average claims cost) will have on GMS prescribing costs in 2016, 2021 and 2026 under different scenarios. The Population of Ireland is projected to grow by 32% between 2007 and 2026 and by 96% for the over 70s. The Eastern region is estimated to grow by 3% over the lifetime of the projections at the expense of most other regions. The Monte Carlo simulations project that females will be a bigger driver of GMS costs than males. Midlands region will be the most expensive of the eight old health board regions. Those aged 70 and over and children under 11 will be significant drivers of GMS costs with the impending demographic changes. Overall GMS medicines costs are projected to rise to €1.9bn by 2026. Ireland's population will experience rapid growth over the next decade. Population growth coupled with an aging population will result in an increase in coverage rates, thus the projected increase in overall prescribing costs. Our projections and simulations map the likely evolution of GMS cost, given existing policies and demographic trends. These costs can be contained by

  16. Poor Government Oversight of Anham and Its Subcontracting Procedures Allowed Questionable Costs To Go Undetected

    DTIC Science & Technology

    2011-07-30

    contractor purchasing system review of Anham. Management Comments and Audit Response The Defense Contract Mangement Agency and the U.S. Central... Introduction 1  Background 1  Government Agency Roles and Oversight Responsibilities 4  Objectives 7  Weak Government Oversight Resulted in Significant...Subcontracting Procedures Allowed Questionable Costs To Go Undetected SIGIR 11-022 July 30, 2011 Introduction Since 2003, the United States Government

  17. 45 CFR 309.150 - What start-up costs are allowable for Tribal IV-D programs carried out under § 309.65(b) of this...

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 45 Public Welfare 2 2010-10-01 2010-10-01 false What start-up costs are allowable for Tribal IV-D... ENFORCEMENT (IV-D) PROGRAM Tribal IV-D Program Funding § 309.150 What start-up costs are allowable for Tribal IV-D programs carried out under § 309.65(b) of this part? Federal funds are available for costs of...

  18. Electric vehicle life cycle cost analysis : final research project report.

    DOT National Transportation Integrated Search

    2017-02-01

    This project compared total life cycle costs of battery electric vehicles (BEV), plug-in hybrid electric vehicles (PHEV), hybrid electric vehicles (HEV), and vehicles with internal combustion engines (ICE). The analysis considered capital and operati...

  19. [Cost-effectiveness of the HIV screening program carried out in Guangxi Zhuang Autonomous Region infectious disease special demonstration project areas].

    PubMed

    Lu, Huaxiang; Luo, Liuhong; Chen, Li; Zhang, Shizhen; Liang, Yingfang; Li, Li; Chen, Zhenqiang; Huo, Xiaoxing; Wu, Xinghua

    2015-06-01

    To analyze the cost effectiveness of HIV screening project in three Guangxi infectious disease special demonstration project countries in 2013. To calculate the funds used for the HIV screening project and to study the data on HIV/AIDS and HAART. A five-tree markov model was used to evaluate the quality adjusted life year (QALY) of this HIV screening project and to analyze the related cost effectiveness of the project. The cost of HIV screening in Guangxi infectious disease special demonstration project areas was 19.205 million Yuan and having identified 1 218 HIV/AIDS patients. The average costs for HIV/AIDS positive detection in three project countries were 14.562, 18.424 and 14.042 thousand Yuan per case. The QALYs gained from finding a HIV/AIDS case were 12.736, 8.523 and 8.321 on average, with the total number of QALYs gained from the project as 5 973.184, 3 613.752 and 2 704.325. The overall cost effectiveness ratio of the project was 1.562 thousand Yuan per QALY, and 1.143, 2.162 and 1.688 thousand Yuan per QALY in these three project countries. Project country "A" showed better cost effectiveness index than country B and C. The HIV screening project in Guangxi seemed relatively cost-effective but the average cost of HIV/AIDS positive detection was expensive. To strengthen HAART work for HIV/AIDS could improve the cost-effective of the project.

  20. 42 CFR 409.46 - Allowable administrative costs.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... billable include, but are not limited to, the following: (a) Registered nurse initial evaluation visits. Initial evaluation visits by a registered nurse for the purpose of assessing a beneficiary's health needs... be an administrative cost. (b) Visits by registered nurses or qualified professionals for the...

  1. 75 FR 48365 - Solicitation for a Cooperative Agreement-NIC Cost Containment Online Resource Center Project

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-08-10

    ...--NIC Cost Containment Online Resource Center Project AGENCY: National Institute of Corrections, U.S... containment online resource center. The NIC Cost Containment Online Resource Center (CCORC) will be housed on... project's four tasks are to (1) compile a guide providing a detailed review of existing evidence-based...

  2. Alcoholism treatment and medical care costs from Project MATCH.

    PubMed

    Holder, H D; Cisler, R A; Longabaugh, R; Stout, R L; Treno, A J; Zweben, A

    2000-07-01

    This paper examines the costs of medical care prior to and following initiation of alcoholism treatment as part of a study of patient matching to treatment modality. Longitudinal study with pre- and post-treatment initiation. The total medical care costs for inpatient and outpatient treatment for patients participating over a span of 3 years post-treatment. Three treatment sites at two of the nine Project MATCH locations (Milwaukee, WI and Providence, RI). Two hundred and seventy-nine patients. Patients were randomly assigned to one of three treatment modalities: a 12-session cognitive behavioral therapy (CBT), a four-session motivational enhancement therapy (MET) or a 12-session Twelve-Step facilitation (TSF) treatment over 12 weeks. Total medical care costs declined from pre- to post-treatment overall and for each modality. Matching effects independent of clinical prognosis showed that MET has potential for medical-care cost-savings. However, patients with poor prognostic characteristics (alcohol dependence, psychiatric severity and/or social network support for drinking) have better cost-savings potential with CBT and/or TSF. Matching variables have significant importance in increasing the potential for medical-care cost-reductions following alcoholism treatment.

  3. Cost-effectiveness of environmental management for vector control in resource development projects.

    PubMed

    Bos, R

    1991-01-01

    Vector control methods are traditionally divided in chemical, biological and environmental management approaches, and this distinction also reflected in certain financial and economic aspects. This is particularly true for environmental modification, usually engineering or other structural works. It is highly capital intensive, as opposed to chemical and biological control which require recurrent expenditures, and discount rates are therefore a prominent consideration in deciding for one or the other approach. Environmental manipulation requires recurrent action, but can often be carried out with the community participation, which raises the issue of opportunity costs. The incorporation of environmental management in resource projects is generally impeded by economic considerations. The Internal Rate of Return continues to be a crucial criterion for funding agencies and development banks to support new projects; at the same time Governments of debt-riden countries in the Third World will do their best to avoid additional loans on such frills as environmental and health safeguards. Two approaches can be recommended to nevertheless ensure the incorporation of environmental management measures in resource projects in an affordable way. First, there are several examples of cases where environmental management measures either have a dual benefit (increasing both agricultural production and reducing vector-borne disease transmission) or can be implemented at zero costs. Second, the additional costs involved in structural modifications can be separated from the project development costs considered in the calculations of the Internal Rate of Return, and financial support can be sought from bilateral technical cooperation agencies particularly interested in environmental and health issues. There is a dearth of information in the cost-effectiveness of alternative vector control strategies in the developing country context. The process of integrating vector control in the

  4. Procedures and models for estimating preconstruction costs of highway projects.

    DOT National Transportation Integrated Search

    2012-07-01

    This study presents data driven and component based PE cost prediction models by utilizing critical factors retrieved from ten years of historical project data obtained from ODOT roadway division. The study used factor analysis of covariance and corr...

  5. Projections of the Cost of Cancer Care in the United States: 2010–2020

    PubMed Central

    Robin Yabroff, K.; Shao, Yongwu; Feuer, Eric J.; Brown, Martin L.

    2011-01-01

    Background Current estimates of the costs of cancer care in the United States are based on data from 2003 and earlier. However, incidence, survival, and practice patterns have been changing for the majority of cancers. Methods Cancer prevalence was estimated and projected by phase of care (initial year following diagnosis, continuing, and last year of life) and tumor site for 13 cancers in men and 16 cancers in women through 2020. Cancer prevalence was calculated from cancer incidence and survival models estimated from Surveillance, Epidemiology, and End Results (SEER) Program data. Annualized net costs were estimated from recent SEER–Medicare linkage data, which included claims through 2006 among beneficiaries aged 65 years and older with a cancer diagnosis. Control subjects without cancer were identified from a 5% random sample of all Medicare beneficiaries residing in the SEER areas to adjust for expenditures not related to cancer. All cost estimates were adjusted to 2010 dollars. Different scenarios for assumptions about future trends in incidence, survival, and cost were assessed with sensitivity analysis. Results Assuming constant incidence, survival, and cost, we projected 13.8 and 18.1 million cancer survivors in 2010 and 2020, respectively, with associated costs of cancer care of 124.57 and 157.77 billion 2010 US dollars. This 27% increase in medical costs reflects US population changes only. The largest increases were in the continuing phase of care for prostate cancer (42%) and female breast cancer (32%). Projections of current trends in incidence (declining) and survival (increasing) had small effects on 2020 estimates. However, if costs of care increase annually by 2% in the initial and last year of life phases of care, the total cost in 2020 is projected to be $173 billion, which represents a 39% increase from 2010. Conclusions The national cost of cancer care is substantial and expected to increase because of population changes alone. Our findings

  6. Current costs & projected financial needs of India's Universal Immunization Programme.

    PubMed

    Chatterjee, Susmita; Pant, Manish; Haldar, Pradeep; Aggarwal, Mahesh Kumar; Laxminarayan, Ramanan

    2016-06-01

    India's Universal Immunization Programme (UIP) is one of the largest programmes in the world in terms of quantities of vaccines administered, number of beneficiaries, number of immunization sessions, and geographical extent and diversity of areas covered. Strategic planning for the Programme requires credible information on the cost of achieving the objectives and the financial resources needed at national, State, and district levels. We present here expenditures on immunization services in India in 2012 (baseline) and projected costs for five years (2013-2017). Data were collected from the Immunization Division of the Ministry of Health and Family Welfare, Government of India, and immunization partners, such as the World Health Organization and UNICEF. The cost components were immunization personnel, vaccines and injection supplies, transportation, trainings, social mobilization, advocacy and communication activities, disease surveillance, Programme management, maintenance of cold chain and other equipment, and capital costs. Total baseline expenditure was ₹ 3,446 crore [1 crore = 10 million] (US$718 million), including shared personnel costs. In 2012, the government paid for 90 per cent of the Programme. Total resource requirements for 2013-2017 are ₹ 34,336 crore (US$ 5, 282 million). Allocations for vaccines increase from ₹ 511 crore in 2013 to ₹ 3,587 crore in 2017 as new vaccines are assumed to be introduced in the Programme. The projections show that the government immunization budget will be double in 2017 as compared to 2013. It will increase from ₹ 4,570 crore in 2013 to ₹ 9,451 crore in 2017.

  7. Methodological Approaches for Estimating the Benefits and Costs of Smart Grid Demonstration Projects

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Lee, Russell

    This report presents a comprehensive framework for estimating the benefits and costs of Smart Grid projects and a step-by-step approach for making these estimates. The framework identifies the basic categories of benefits, the beneficiaries of these benefits, and the Smart Grid functionalities that lead to different benefits and proposes ways to estimate these benefits, including their monetization. The report covers cost-effectiveness evaluation, uncertainty, and issues in estimating baseline conditions against which a project would be compared. The report also suggests metrics suitable for describing principal characteristics of a modern Smart Grid to which a project can contribute. This first sectionmore » of the report presents background information on the motivation for the report and its purpose. Section 2 introduces the methodological framework, focusing on the definition of benefits and a sequential, logical process for estimating them. Beginning with the Smart Grid technologies and functions of a project, it maps these functions to the benefits they produce. Section 3 provides a hypothetical example to illustrate the approach. Section 4 describes each of the 10 steps in the approach. Section 5 covers issues related to estimating benefits of the Smart Grid. Section 6 summarizes the next steps. The methods developed in this study will help improve future estimates - both retrospective and prospective - of the benefits of Smart Grid investments. These benefits, including those to consumers, society in general, and utilities, can then be weighed against the investments. Such methods would be useful in total resource cost tests and in societal versions of such tests. As such, the report will be of interest not only to electric utilities, but also to a broad constituency of stakeholders. Significant aspects of the methodology were used by the U.S. Department of Energy (DOE) to develop its methods for estimating the benefits and costs of its renewable and

  8. 40 CFR 35.3520 - Systems, projects, and project-related costs eligible for assistance from the Fund.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... for assistance. These include projects needed to maintain compliance with existing national primary...) Costs for restructuring systems that are in significant noncompliance with any national primary drinking...) Systems that are in significant noncompliance with any national primary drinking water regulation or...

  9. 48 CFR 52.216-7 - Allowable Cost and Payment.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... Cost and Payment (JUN 2011) (a) Invoicing. (1) The Government will make payments to the Contractor when... make interim payments for contract financing on the ____[Contracting Officer insert day as prescribed... office is not compelled to make payment by the specified due date. (b) Reimbursing costs. (1) For the...

  10. 48 CFR 52.216-7 - Allowable Cost and Payment.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... Cost and Payment (JUN 2013) (a) Invoicing. (1) The Government will make payments to the Contractor when... make interim payments for contract financing on the ____[Contracting Officer insert day as prescribed... office is not compelled to make payment by the specified due date. (b) Reimbursing costs. (1) For the...

  11. 48 CFR 52.216-7 - Allowable Cost and Payment.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... Cost and Payment (JUN 2013) (a) Invoicing. (1) The Government will make payments to the Contractor when... make interim payments for contract financing on the ____[Contracting Officer insert day as prescribed... office is not compelled to make payment by the specified due date. (b) Reimbursing costs. (1) For the...

  12. Project-based physics labs using low-cost open-source hardware

    NASA Astrophysics Data System (ADS)

    Bouquet, F.; Bobroff, J.; Fuchs-Gallezot, M.; Maurines, L.

    2017-03-01

    We describe a project-based physics lab, which we proposed to third-year university students. These labs are based on new open-source low-cost equipment (Arduino microcontrollers and compatible sensors). Students are given complete autonomy: they develop their own experimental setup and study the physics topic of their choice. The goal of these projects is to let students to discover the reality of experimental physics. Technical specifications of the acquisition material and case studies are presented for practical implementation in other universities.

  13. Initial Costs vs. Operational Costs. A Study of Building Improvement Projects in Fourteen Schools in the School District of Greenville County, South Carolina.

    ERIC Educational Resources Information Center

    Chan, Tak Cheung

    To determine whether initial facility improvement costs were paid back by the reduced operational costs resulting from the improvement projects, this study examined the relationship between initial costs and operational costs of fourteen school buildings improved during the 1978-79 school year in Greenville County, South Carolina. With energy…

  14. A bottom-up approach to estimating cost elements of REDD+ pilot projects in Tanzania

    PubMed Central

    2012-01-01

    Background Several previous global REDD+ cost studies have been conducted, demonstrating that payments for maintaining forest carbon stocks have significant potential to be a cost-effective mechanism for climate change mitigation. These studies have mostly followed highly aggregated top-down approaches without estimating the full range of REDD+ costs elements, thus underestimating the actual costs of REDD+. Based on three REDD+ pilot projects in Tanzania, representing an area of 327,825 ha, this study explicitly adopts a bottom-up approach to data assessment. By estimating opportunity, implementation, transaction and institutional costs of REDD+ we develop a practical and replicable methodological framework to consistently assess REDD+ cost elements. Results Based on historical land use change patterns, current region-specific economic conditions and carbon stocks, project-specific opportunity costs ranged between US$ -7.8 and 28.8 tCOxxxx for deforestation and forest degradation drivers such as agriculture, fuel wood production, unsustainable timber extraction and pasture expansion. The mean opportunity costs for the three projects ranged between US$ 10.1 – 12.5 tCO2. Implementation costs comprised between 89% and 95% of total project costs (excluding opportunity costs) ranging between US$ 4.5 - 12.2 tCO2 for a period of 30 years. Transaction costs for measurement, reporting, verification (MRV), and other carbon market related compliance costs comprised a minor share, between US$ 0.21 - 1.46 tCO2. Similarly, the institutional costs comprised around 1% of total REDD+ costs in a range of US$ 0.06 – 0.11 tCO2. Conclusions The use of bottom-up approaches to estimate REDD+ economics by considering regional variations in economic conditions and carbon stocks has been shown to be an appropriate approach to provide policy and decision-makers robust economic information on REDD+. The assessment of opportunity costs is a crucial first step to provide information on the

  15. (abstract) Science-Project Interaction in the Low-Cost Mission

    NASA Technical Reports Server (NTRS)

    Wall, Stephen D.

    1994-01-01

    Large, complex, and highly optimized missions have performed most of the preliminary reconnaisance of the solar system. As a result we have now mapped significant fractions of its total surface (or surface-equivalent) area. Now, however, scientific exploration of the solar system is undergoing a major change in scale, and existing missions find it necessary to limit costs while fulfilling existing goals. In the future, NASA's Discovery program will continue the reconnaisance, exploration, and diagnostic phases of planetary research using lower cost missions, which will include lower cost mission operations systems (MOS). Historically, one of the more expensive functions of MOS has been its interaction with the science community. Traditional MOS elements that this interaction have embraced include mission planning, science (and engineering) event conflict resolution, sequence optimization and integration, data production (e.g., assembly, enhancement, quality assurance, documentation, archive), and other science support services. In the past, the payoff from these efforts has been that use of mission resources has been highly optimized, constraining resources have been generally completely consumed, and data products have been accurate and well documented. But because these functions are expensive we are now challenged to reduce their cost while preserving the benefits. In this paper, we will consider ways of revising the traditional MOS approach that might save project resources while retaining a high degree of service to the Projects' customers. Pre-launch, science interaction can be made simplier by limiting numbers of instruments and by providing greater redundancy in mission plans. Post launch, possibilities include prioritizing data collection into a few categories, easing requirements on real-time of quick-look data delivery, and closer integration of scientists into the mission operation.

  16. Comparing Life-Cycle Costs of ESPCs and Appropriations-Funded Energy Projects: An Update to the 2002 Report

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Shonder, John A; Hughes, Patrick; Atkin, Erica

    2006-11-01

    A study was sponsored by FEMP in 2001 - 2002 to develop methods to compare life-cycle costs of federal energy conservation projects carried out through energy savings performance contracts (ESPCs) and projects that are directly funded by appropriations. The study described in this report follows up on the original work, taking advantage of new pricing data on equipment and on $500 million worth of Super ESPC projects awarded since the end of FY 2001. The methods developed to compare life-cycle costs of ESPCs and directly funded energy projects are based on the following tasks: (1) Verify the parity of equipmentmore » prices in ESPC vs. directly funded projects; (2) Develop a representative energy conservation project; (3) Determine representative cycle times for both ESPCs and appropriations-funded projects; (4) Model the representative energy project implemented through an ESPC and through appropriations funding; and (5) Calculate the life-cycle costs for each project.« less

  17. Parametric Cost Models for Space Telescopes

    NASA Technical Reports Server (NTRS)

    Stahl, H. Philip; Henrichs, Todd; Dollinger, Courtney

    2010-01-01

    Multivariable parametric cost models for space telescopes provide several benefits to designers and space system project managers. They identify major architectural cost drivers and allow high-level design trades. They enable cost-benefit analysis for technology development investment. And, they provide a basis for estimating total project cost. A survey of historical models found that there is no definitive space telescope cost model. In fact, published models vary greatly [1]. Thus, there is a need for parametric space telescopes cost models. An effort is underway to develop single variable [2] and multi-variable [3] parametric space telescope cost models based on the latest available data and applying rigorous analytical techniques. Specific cost estimating relationships (CERs) have been developed which show that aperture diameter is the primary cost driver for large space telescopes; technology development as a function of time reduces cost at the rate of 50% per 17 years; it costs less per square meter of collecting aperture to build a large telescope than a small telescope; and increasing mass reduces cost.

  18. Laser Atmospheric Wind Sounder (LAWS) phase 1. Volume 3: Project cost estimates

    NASA Technical Reports Server (NTRS)

    1990-01-01

    The laser atmospheric wind sounder (LAWS) cost modeling activities were initiated in phase 1 to establish the ground rules and cost model that would apply to both phase 1 and phase 2 cost analyses. The primary emphasis in phase 1 was development of a cost model for a LAWS instrument for the Japanese Polar Orbiting Platform (JPOP). However, the Space Station application was also addressed in this model, and elements were included, where necessary, to account for Space Station unique items. The cost model presented in the following sections defines the framework for all LAWS cost modeling. The model is consistent with currently available detail, and can be extended to account for greater detail as the project definition progresses.

  19. Teaching project: a low-cost swine model for chest tube insertion training.

    PubMed

    Netto, Fernando Antonio Campelo Spencer; Sommer, Camila Garcia; Constantino, Michael de Mello; Cardoso, Michel; Cipriani, Raphael Flávio Fachini; Pereira, Renan Augusto

    2016-02-01

    to describe and evaluate the acceptance of a low-cost chest tube insertion porcine model in a medical education project in the southwest of Paraná, Brazil. we developed a low-cost and low technology porcine model for teaching chest tube insertion and used it in a teaching project. Medical trainees - students and residents - received theoretical instructions about the procedure and performed thoracic drainage in this porcine model. After performing the procedure, the participants filled a feedback questionnaire about the proposed experimental model. This study presents the model and analyzes the questionnaire responses. seventy-nine medical trainees used and evaluated the model. The anatomical correlation between the porcine model and human anatomy was considered high and averaged 8.1±1.0 among trainees. All study participants approved the low-cost porcine model for chest tube insertion. the presented low-cost porcine model for chest tube insertion training was feasible and had good acceptability among trainees. This model has potential use as a teaching tool in medical education.

  20. Vulnerability in Determining the Cost of Information System Project to Avoid Loses

    NASA Astrophysics Data System (ADS)

    Haryono, Kholid; Ikhsani, Zulfa Amalia

    2018-03-01

    Context: This study discusses the priority of cost required in software development projects. Objectives: To show the costing models, the variables involved, and how practitioners assess and decide the priorities of each variable. To strengthen the information, each variable also confirmed the risk if ignored. Method: The method is done by two approaches. First, systematic literature reviews to find the models and variables used to decide the cost of software development. Second, confirm and take judgments about the level of importance and risk of each variable to the software developer. Result: Obtained about 54 variables that appear on the 10 models discussed. The variables are categorized into 15 groups based on the similarity of meaning. Each group becomes a variable. Confirmation results with practitioners on the level of importance and risk. It shown there are two variables that are considered very important and high risk if ignored. That is duration and effort. Conclusion: The relationship of variable rates between the results of literature studies and confirmation of practitioners contributes to the use of software business actors in considering project cost variables.