Sample records for contractor facilities study

  1. 48 CFR 52.241-5 - Contractor's Facilities.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 2 2010-10-01 2010-10-01 false Contractor's Facilities....241-5 Contractor's Facilities. As prescribed in 41.501(c)(4), insert a clause substantially the same as the following: Contractor's Facilities (FEB 1995) (a) The Contractor, at its expense, unless...

  2. 48 CFR 42.402 - Visits to contractors' facilities.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 1 2010-10-01 2010-10-01 false Visits to contractors... contractors' facilities. (a) Government personnel planning to visit a contractor's facility in connection with... positions, and security clearances. (2) Date and duration of visit. (3) Name and address of contractor and...

  3. 48 CFR 222.101-4 - Removal of items from contractors' facilities affected by work stoppages.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... contractors' facilities affected by work stoppages. 222.101-4 Section 222.101-4 Federal Acquisition... contractors' facilities affected by work stoppages. (a) When a contractor is unable to deliver urgent and critical items because of a work stoppage at its facility, the contracting officer, before removing any...

  4. 48 CFR 47.303-2 - F.o.b. origin, contractor's facility.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 1 2010-10-01 2010-10-01 false F.o.b. origin, contractor... REGULATION CONTRACT MANAGEMENT TRANSPORTATION Transportation in Supply Contracts 47.303-2 F.o.b. origin, contractor's facility. (a) Explanation of delivery term. F.o.b. origin, contractor's facility means free of...

  5. 48 CFR 52.247-30 - F.o.b. Origin, Contractor's Facility.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 2 2010-10-01 2010-10-01 false F.o.b. Origin, Contractor... Clauses 52.247-30 F.o.b. Origin, Contractor's Facility. As prescribed in 47.303-2(c), insert the following clause in solicitations and contracts when the delivery term is f.o.b. origin, contractor's facility: F.o...

  6. 10 CFR 1004.3 - Public reading facilities and policy on contractor records.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 10 Energy 4 2012-01-01 2012-01-01 false Public reading facilities and policy on contractor records. 1004.3 Section 1004.3 Energy DEPARTMENT OF ENERGY (GENERAL PROVISIONS) FREEDOM OF INFORMATION § 1004.3 Public reading facilities and policy on contractor records. (a) The DOE Headquarters will maintain, in the public reading facilities, the...

  7. 10 CFR 1004.3 - Public reading facilities and policy on contractor records.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 10 Energy 4 2011-01-01 2011-01-01 false Public reading facilities and policy on contractor records. 1004.3 Section 1004.3 Energy DEPARTMENT OF ENERGY (GENERAL PROVISIONS) FREEDOM OF INFORMATION § 1004.3 Public reading facilities and policy on contractor records. (a) The DOE Headquarters will maintain, in the public reading facilities, the...

  8. 10 CFR 1004.3 - Public reading facilities and policy on contractor records.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 10 Energy 4 2013-01-01 2013-01-01 false Public reading facilities and policy on contractor records. 1004.3 Section 1004.3 Energy DEPARTMENT OF ENERGY (GENERAL PROVISIONS) FREEDOM OF INFORMATION § 1004.3 Public reading facilities and policy on contractor records. (a) The DOE Headquarters will maintain, in the public reading facilities, the...

  9. 10 CFR 1004.3 - Public reading facilities and policy on contractor records.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 10 Energy 4 2014-01-01 2014-01-01 false Public reading facilities and policy on contractor records. 1004.3 Section 1004.3 Energy DEPARTMENT OF ENERGY (GENERAL PROVISIONS) FREEDOM OF INFORMATION § 1004.3 Public reading facilities and policy on contractor records. (a) The DOE Headquarters will maintain, in the public reading facilities, the...

  10. 48 CFR 1422.101-4 - Removal of items from contractors' facilities affected by work stoppages.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... ACQUISITIONS Basic Labor Policies 1422.101-4 Removal of items from contractors' facilities affected by work... 48 Federal Acquisition Regulations System 5 2010-10-01 2010-10-01 false Removal of items from contractors' facilities affected by work stoppages. 1422.101-4 Section 1422.101-4 Federal Acquisition...

  11. Structured Transition of Wind Tunnel Operations Skills from Government-to Contractor-Managed

    NASA Technical Reports Server (NTRS)

    Dunn, Steven C.; Schlank, John J.

    2010-01-01

    In 2004, NASA awarded the Research, Operations, Maintenance, and Engineering (ROME) contract at NASA Langley Research Center to a team led by Jacobs Technology, Inc. A key component of the contract was the transitioning of the five large wind tunnel facilities from NASA managed and NASA or NASA/contractor workforces to fully contractor operated. The contractor would manage daily operations while NASA would continue to develop long-term strategies, make decisions regarding commitment of funds and commitment of facilities, and provide oversight of the contractor's performance. A major challenge would be the transition of knowledge of facility operations and maintenance from the incumbent civil servant workforce to the contractor workforce. While the contract has since been modified multiple times, resulting in a blended NASA/ROME workforce across the facilities, the processes developed and implemented to capture and document facility knowledge from the incumbent subject matter experts, build training and certification programs, and grow individual skills across subject areas and across facilities, are worthy of documentation. This is the purpose of this paper.

  12. 76 FR 16838 - Finding of No Significant Impact; Notice of Availability of the Finding of No Significant Impact...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-03-25

    ... Male, Non-US Citizen, Criminal Aliens at a Contractor-Owned, Contractor-Operated Correctional Facility... aliens within one existing contractor owned, contractor operated facility. Background Information Growth... criminal aliens. In response, the BOP is seeking flexibility in managing its current shortage of beds by...

  13. 41 CFR 102-74.275 - May Federal agencies authorize lessors or parking management contractors to manage, regulate and...

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... authorize lessors or parking management contractors to manage, regulate and police parking facilities? 102... contractors to manage, regulate and police parking facilities? Yes, Federal agencies, upon approval from GSA, may authorize lessors or parking management contractors to manage, regulate and police parking...

  14. 41 CFR 102-74.275 - May Federal agencies authorize lessors or parking management contractors to manage, regulate and...

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... authorize lessors or parking management contractors to manage, regulate and police parking facilities? 102... contractors to manage, regulate and police parking facilities? Yes, Federal agencies, upon approval from GSA, may authorize lessors or parking management contractors to manage, regulate and police parking...

  15. 41 CFR 102-74.275 - May Federal agencies authorize lessors or parking management contractors to manage, regulate and...

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... authorize lessors or parking management contractors to manage, regulate and police parking facilities? 102... contractors to manage, regulate and police parking facilities? Yes, Federal agencies, upon approval from GSA, may authorize lessors or parking management contractors to manage, regulate and police parking...

  16. 41 CFR 102-74.275 - May Federal agencies authorize lessors or parking management contractors to manage, regulate and...

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... authorize lessors or parking management contractors to manage, regulate and police parking facilities? 102... contractors to manage, regulate and police parking facilities? Yes, Federal agencies, upon approval from GSA, may authorize lessors or parking management contractors to manage, regulate and police parking...

  17. 41 CFR 102-74.275 - May Federal agencies authorize lessors or parking management contractors to manage, regulate and...

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... authorize lessors or parking management contractors to manage, regulate and police parking facilities? 102... contractors to manage, regulate and police parking facilities? Yes, Federal agencies, upon approval from GSA, may authorize lessors or parking management contractors to manage, regulate and police parking...

  18. Summary Report - Inspections of DoD Facilities and Military Housing and Audits of Base Operations and Support Services Contracts

    DTIC Science & Technology

    2016-10-14

    not holding contractors accountable for poor performance while constructing and maintaining facilities. These systemic problems resulted in...portfolio was about $880 billion at the end of FY 2015. Between 2003 and 2008, 18 U.S. military and contractor personnel electrocution fatalities...maintenance of DoD facilities. For instance, Report No. DODIG-2013-099 stated that installations “lacked qualified Government or contractor electricians

  19. Contractor Logistics Support in the U.S. Air Force

    DTIC Science & Technology

    2009-01-01

    limits), or it can engage in a mix of the two approaches.2 This monograph addresses CLS, which is defined as contractor sustainment of a weapon system...organic facilities; it can pay contractors to do the work (subject to some congressional limits); or it can apply a mix of the two approaches.2 Organic...levels are largely stable and represent a mix of services, including contractor operated facilities and instal- Figure 3.1 Air Force CSS for Weapon

  20. 48 CFR 252.229-7004 - Status of contractors as a direct contractor (Spain).

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ..., development, maintenance, and operation of Spanish-American installations and facilities. (b) The Contractor... this contract by reference. (c) The Contractor shall apply to the appropriate Spanish authorities for approval of status as a Direct Contractor in order to complete duty-free import of non-Spanish equipment...

  1. 48 CFR 2922.101-4 - Removal of items from contractor facilities affected by work stoppages.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... Regulations System DEPARTMENT OF LABOR SOCIOECONOMIC PROGRAMS APPLICATION OF LABOR LAWS TO GOVERNMENT ACQUISITIONS Basic Labor Policies 2922.101-4 Removal of items from contractor facilities affected by work...

  2. 48 CFR 923.102 - Applicability to contractors.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... contractors. 923.102 Section 923.102 Federal Acquisition Regulations System DEPARTMENT OF ENERGY SOCIOECONOMIC... 923.102 Applicability to contractors. Many of the Department's major facilities are operated by contractors. Provisions regarding those contracts may be found at Part 970 of this chapter. At other locations...

  3. Multiyear Procurement (MYP) and Block Buy Contracting in Defense Acquisition: Background and Issues for Congress

    DTIC Science & Technology

    2017-03-16

    principle reduce the cost of the weapons being procured in two primary ways:  Contractor optimization of workforce and production facilities. An...MYP contract gives the contractor (e.g., an airplane manufacturer or shipbuilder) confidence that a multiyear stream of business of a known volume...will very likely materialize. This confidence can permit the contractor to make investments in the firm’s workforce and production facilities that are

  4. Strategic Defense Initiative Demonstration/Validation Program Environmental Assessment. Space-Based Surveillance and Tracking System (SSTS),

    DTIC Science & Technology

    1987-08-01

    take place in both contractor and government facilities. The on-orbit evaluation could utilize modified launch facilities depending on the launch...technological issues : o Telescope Optics: Verify that the distortions associated vith large optical elements satisfy detection and tracking requirements; verify...Validation program vould be car- ried out at contractor facilities that 1’ave not been identified and at six government facilities (Arnold Engineering

  5. Depot Maintenance: Improvements to DODs Biennial Core Report Could Better Inform Oversight and Funding Decisions

    DTIC Science & Technology

    2016-11-01

    information, contact Zina Merritt at (202) 512-5257 or merrittz@gao.gov Why GAO Did This Study DOD uses both military depots and contractors to maintain...many complex weapon systems and equipment. Recognizing the key role of the depots and the risk of overreliance on contractors , Section 2464 of...military depots2—public-sector facilities that are government-owned and government-operated—and private-sector contractors . Depots have a key role

  6. Disaster Debris Recovery Database - Recovery

    EPA Pesticide Factsheets

    The US EPA Region 5 Disaster Debris Recovery Database includes public datasets of over 6,000 composting facilities, demolition contractors, transfer stations, landfills and recycling facilities for construction and demolition materials, electronics, household hazardous waste, metals, tires, and vehicles in the states of Illinois, Indiana, Iowa, Kentucky, Michigan, Minnesota, Missouri, North Dakota, Ohio, Pennsylvania, South Dakota, West Virginia and Wisconsin.In this update, facilities in the 7 states that border the EPA Region 5 states were added to assist interstate disaster debris management. Also, the datasets for composters, construction and demolition recyclers, demolition contractors, and metals recyclers were verified and source information added for each record using these sources: AGC, Biocycle, BMRA, CDRA, ISRI, NDA, USCC, FEMA Debris Removal Contractor Registry, EPA Facility Registry System, and State and local listings.

  7. Disaster Debris Recovery Database - Landfills

    EPA Pesticide Factsheets

    The US EPA Region 5 Disaster Debris Recovery Database includes public datasets of over 6,000 composting facilities, demolition contractors, transfer stations, landfills and recycling facilities for construction and demolition materials, electronics, household hazardous waste, metals, tires, and vehicles in the states of Illinois, Indiana, Iowa, Kentucky, Michigan, Minnesota, Missouri, North Dakota, Ohio, Pennsylvania, South Dakota, West Virginia and Wisconsin.In this update, facilities in the 7 states that border the EPA Region 5 states were added to assist interstate disaster debris management. Also, the datasets for composters, construction and demolition recyclers, demolition contractors, and metals recyclers were verified and source information added for each record using these sources: AGC, Biocycle, BMRA, CDRA, ISRI, NDA, USCC, FEMA Debris Removal Contractor Registry, EPA Facility Registry System, and State and local listings.

  8. 23 CFR 660.519 - Missile installations and facilities.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... facilities. Should damage occur to public highways as a result of construction activities, the contractor... the work performed. Claims shall be presented to the contractor for this extraordinary maintenance and... the contract terms, the claim with the required supporting documentation shall be presented to the...

  9. 23 CFR 660.519 - Missile installations and facilities.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... facilities. Should damage occur to public highways as a result of construction activities, the contractor... the work performed. Claims shall be presented to the contractor for this extraordinary maintenance and... the contract terms, the claim with the required supporting documentation shall be presented to the...

  10. Program Evaluation: A Consumer Evaluation of Alternative Contractor Concepts in Government Food Service

    DTIC Science & Technology

    1974-09-01

    food service facilities. The food factors (quality, variety, and quantity, in that order) were generally rated by consumers as most serious problems, in keeping with many previous survey studies of military food service system. The contractor food service concept with raw food provided by the contractor, as exemplified by Fort Myer, significantly reduced consumer problems in food service personnel, speed, hours, environment, and convenience of location, and also reduced the degree to which food variety,

  11. 48 CFR 252.239-7011 - Special construction and equipment charges.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... this clause, the Government shall have the right to terminate the service under the Cancellation or...) The Government will not directly reimburse the Contractor for the cost of constructing any facilities... the Contractor stops using facilities or equipment which the Government has, in whole or part...

  12. 48 CFR 27.404-6 - Inspection of data at the contractor's facility.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... regarding the limited rights or restricted rights status of the data, or for evaluating work performance... REGULATION GENERAL CONTRACTING REQUIREMENTS PATENTS, DATA, AND COPYRIGHTS Rights in Data and Copyrights 27.404-6 Inspection of data at the contractor's facility. Contracting officers may obtain the right to...

  13. Institutional environmental impact statement, Michoud Assembly Facility, New Orleans, Louisiana

    NASA Technical Reports Server (NTRS)

    1978-01-01

    A description and analysis of Michoud Assembly Facility as an operational base for both NASA and NASA-related programs and various government tenant-agencies and their contractors is given. Tenant-agencies are governmental agencies or governmental agency contractors which are not involved in a NASA program, but utilize office or manufacturing space at the Michoud Assembly Facility. The statements represent the full description of the likely environmental effects of the facility and are used in the process of making program and project decisions.

  14. 48 CFR 252.204-7010 - Requirement for Contractor to Notify DoD if the Contractor's Activities are Subject to Reporting...

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... of vulnerabilities to IAEA inspections or visits; (ii) Notify the Contractor of the time at which the... with DoD officials in the assessment of vulnerabilities to IAEA inspections or visits. (d) Following a...) Whether the Contractor's facility has any vulnerabilities where potentially declarable activities under...

  15. The contractor`s role in low-level waste disposal facility application review and licensing

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Serie, P.J.; Dressen, A.L.

    1991-12-31

    The California Department of Health Services will soon reach a licensing decision on the proposed Ward Valley low-level radioactive waste disposal facility. As the first regulatory agency in the country to address the 10 CFR Part 61 requirements for a new disposal facility, California`s program has broken new ground in its approach. Throughout the review process, the Department has relied on contractor support to augment its technical and administrative staff. A team consisting of Roy F. Weston, Inc., supported by ERM-Program Management Corp., Environmental Issues Management, Inc., and Rogers and Associates Engineering Corporation, has worked closely with the Department inmore » a staff extension role. The authors have been involved with the project in contractor project management roles since 1987, and continue to support the Department`s program as it proceeds to finalize its licensing process. This paper describes the selection process used to identify a contractor team with the needed skills and experience, and the makeup of team capabilities. It outlines the management, communication, and technical approaches used to assure a smooth agency-contractor function and relationship. It describes the techniques used to ensure that decisions and documents represented the Department credibly in its role as the regulatory and licensing agency under the Nuclear Regulatory Commission (NRC) Agreement State program. The paper outlines the license application review process and activities, through preparation of licensing documentation and responses to public comments. Lessons learned in coordination of an agency-contractor team effort to review and license a low-level waste disposal facility are reviewed and suggestions made for approaching a similar license application review and licensing situation.« less

  16. 27 CFR 478.132 - Dispositions of semiautomatic assault weapons and large capacity ammunition feeding devices to...

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... official use and to employees or contractors of nuclear facilities. 478.132 Section 478.132 Alcohol... and to employees or contractors of nuclear facilities. Licensed manufacturers, licensed importers, and licensed dealers in semiautomatic assault weapons, as well as persons who manufacture, import, or deal in...

  17. Capsule review of the DOE research and development and field facilities

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    None

    1980-09-01

    A description is given of the roles of DOE's headquarters, field offices, major multiprogram laboratories, Energy Technology and Mining Technology Centers, and other government-owned, contractor-operated facilities, which are located in all regions of the US. Descriptions of DOE facilities are given for multiprogram laboratories (12); program-dedicated facilities (biomedical and environmental facilities-12, fossil energy facilities-7, fusion energy facility-1, nuclear development facilities-3, physical research facilities-4, safeguards facility-1, and solar facilities-2); and Production, Testing, and Fabrication Facilities (nuclear materials production facilities-5, weapon testing and fabrication complex-8). Three appendices list DOE field and project offices; DOE field facilities by state or territory, names, addresses,more » and telephone numbers; DOE R and D field facilities by type, contractor names, and names of directors. (MCW)« less

  18. Contracting for Facilities Services. Critical Issues in Facilities Management. No. 9.

    ERIC Educational Resources Information Center

    APPA: Association of Higher Education Facilities Officers, Alexandria, VA.

    This book has been designed to provide practical information to managers on how to work with outside contractors in the higher education facilities area, and provides "real world" advice on the opportunities and pitfalls of privatization. Overviews and detailed case studies of contracting-out for services such as custodial services and…

  19. The nexus between OSH and subcontracting.

    PubMed

    Nunes, Isabel L

    2012-01-01

    Subcontracting of specialized functions to external companies (e.g. cleaning or maintenance) is actually very common within several industries. These external companies' are called contractors and their contracting is often designated as outsourcing. Frequently contractors involve other companies (the sub-contractors) to assist them in fulfilling the contract, resulting in a complex chain of organizations focused on interchange of work - the contracting chain. Therefore in the same work site can coexist workers form the client-company and workers from the contractors and/or subcontractors. Since contractors perform their job in client's facilities, they can be exposed to hazards that are unknown to them. On other hand, workers of the client company can also be exposed to hazardous situations derived from the work performed by the contractors. The paper discusses how adequate occupational safety and health conditions can be assured when dealing with this kind of dynamic labor networks. Two case-studies and several examples coming from international literature will be presented.

  20. Information Technology and the Human Research Facility

    NASA Technical Reports Server (NTRS)

    Klee, Margaret

    2002-01-01

    This slide presentation reviews how information technology supports the Human Research Facility (HRF) and specifically the uses that contractor has for the information. There is information about the contractor, the HRF, some of the experiments that were performed using the HRF on board the Shuttle, overviews of the data architecture, and software both commercial and specially developed software for the specific experiments.

  1. Functional Analysis and Preliminary Specifications for a Single Integrated Central Computer System for Secondary Schools and Junior Colleges. Interim Report.

    ERIC Educational Resources Information Center

    1968

    The present report proposes a central computing facility and presents the preliminary specifications for such a system. It is based, in part, on the results of earlier studies by two previous contractors on behalf of the U.S. Office of Education. The recommendations are based upon the present contractors considered evaluation of the earlier…

  2. 48 CFR 915.305 - Proposal evaluation.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ...) Personnel from DOE, other Government agencies, consultants, and contractors, including those who manage or... contractors who operate or manage Government-owned facilities, are to be used as evaluators or advisors...

  3. 48 CFR 915.305 - Proposal evaluation.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ...) Personnel from DOE, other Government agencies, consultants, and contractors, including those who manage or... contractors who operate or manage Government-owned facilities, are to be used as evaluators or advisors...

  4. 48 CFR 915.305 - Proposal evaluation.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ...) Personnel from DOE, other Government agencies, consultants, and contractors, including those who manage or... contractors who operate or manage Government-owned facilities, are to be used as evaluators or advisors...

  5. 48 CFR 915.305 - Proposal evaluation.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ...) Personnel from DOE, other Government agencies, consultants, and contractors, including those who manage or... contractors who operate or manage Government-owned facilities, are to be used as evaluators or advisors...

  6. 75 FR 63609 - Oil and Gas and Sulphur Operations in the Outer Continental Shelf-Safety and Environmental...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-10-15

    ... safety of the offshore facility, including ensuring that all contractors and subcontractors have safety... safety analysis (task level); (3) Procedures to verify that contractors are conducting their activities in accordance with the operator's SEMS program and an evaluation to ensure that contractors have the...

  7. Procurement and Contracting, Transportation & Public Facilities, State of

    Science.gov Websites

    Calendar Bid Opening Results Contract Award Status AASHTOWare Project Vendor List Contractor Bidding List Contractor Bidding Information Requests for Proposals Professional Services Request for Proposals

  8. 48 CFR 970.5223-7 - Sustainable acquisition program.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... Environmental Sustainability Coordinator or equivalent position. (g) The Contractor shall prepare and submit... Sustainability Coordinator at the supported facility. The Subcontractor will advise the Contractor if it is... coordinate its activities with and submit required reports through the Environmental Sustainability...

  9. 48 CFR 970.5223-7 - Sustainable acquisition program.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... Environmental Sustainability Coordinator or equivalent position. (g) The Contractor shall prepare and submit... Sustainability Coordinator at the supported facility. The Subcontractor will advise the Contractor if it is... coordinate its activities with and submit required reports through the Environmental Sustainability...

  10. 48 CFR 970.5223-7 - Sustainable acquisition program.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... Environmental Sustainability Coordinator or equivalent position. (g) The Contractor shall prepare and submit... Sustainability Coordinator at the supported facility. The Subcontractor will advise the Contractor if it is... coordinate its activities with and submit required reports through the Environmental Sustainability...

  11. 48 CFR 970.5223-7 - Sustainable acquisition program.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... Environmental Sustainability Coordinator or equivalent position. (g) The Contractor shall prepare and submit... Sustainability Coordinator at the supported facility. The Subcontractor will advise the Contractor if it is... coordinate its activities with and submit required reports through the Environmental Sustainability...

  12. 75 FR 41281 - Bridge Safety Standards

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-07-15

    ... Institute; High Speed Ground Transportation Association (HSGTA); Institute of Makers of Explosives..., manufacturer, lessor, or lessee of railroad equipment, track or facilities; any independent contractor... independent contractor; and anyone held by FRA to be responsible for compliance with this part. Paragraph (d...

  13. 20 CFR 655.310 - Attestations.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... original Form ETA 9029, containing the required attestation elements and the original signature of the... addition, (A) If the facility is a nursing contractor, the special attestation element in paragraph (j) of... nurses only through a nursing contractor, the special attestation element in paragraph (k) of this...

  14. DOE Office of Scientific and Technical Information (OSTI.GOV)

    Hobbs, R.E.

    In large facilities, successful energy management cannot be measured by a few projects, no matter how significant the energy savings. Large facilities today are comprised of extensive energy consuming systems. For every energy project developed, two more projects remain to be discovered. The successful energy manager is one who has completed ten projects, or twenty, or thirty, and is still finding more projects to do. Nothing is assumed to be as efficient as possible, and no part of any system is ignored. The successful energy manager is willing to take risks, not of being fired, but to use imagination, studymore » engineering theory, exercise common sense, develop concept designs, calculate savings, sell projects to management, control designers, study equipment performance, pre-select contractors, manage the contractor efforts, solve inherent problems along the way, and then optimize the project after acceptance when the designers and contractors all walk off. Once the successful energy manager establishes his credibility, his problem becomes finding enough time to get the projects rolling as he dreams them up. He sees what others do not. As they say in the North, only the lead dog sees new scenery.« less

  15. 41 CFR 102-74.40 - What are concession services?

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... snack services provided by a Randolph-Sheppard Act vendor, commercial contractor or nonprofit... machines; (b) Sundry facilities; (c) Prepackaged facilities; (d) Snack bars; and (e) Cafeterias. ...

  16. 50 CFR 3.3 - Discrimination by contractors and permittees prohibited.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... permittees prohibited. 3.3 Section 3.3 Wildlife and Fisheries UNITED STATES FISH AND WILDLIFE SERVICE, DEPARTMENT OF THE INTERIOR GENERAL PROVISIONS NONDISCRIMINATION-CONTRACTS, PERMITS, AND USE OF FACILITIES § 3.3 Discrimination by contractors and permittees prohibited. The provisions of part III of Executive...

  17. 50 CFR 3.3 - Discrimination by contractors and permittees prohibited.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... permittees prohibited. 3.3 Section 3.3 Wildlife and Fisheries UNITED STATES FISH AND WILDLIFE SERVICE, DEPARTMENT OF THE INTERIOR GENERAL PROVISIONS NONDISCRIMINATION-CONTRACTS, PERMITS, AND USE OF FACILITIES § 3.3 Discrimination by contractors and permittees prohibited. The provisions of part III of Executive...

  18. 50 CFR 3.3 - Discrimination by contractors and permittees prohibited.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... permittees prohibited. 3.3 Section 3.3 Wildlife and Fisheries UNITED STATES FISH AND WILDLIFE SERVICE, DEPARTMENT OF THE INTERIOR GENERAL PROVISIONS NONDISCRIMINATION-CONTRACTS, PERMITS, AND USE OF FACILITIES § 3.3 Discrimination by contractors and permittees prohibited. The provisions of part III of Executive...

  19. 50 CFR 3.3 - Discrimination by contractors and permittees prohibited.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... permittees prohibited. 3.3 Section 3.3 Wildlife and Fisheries UNITED STATES FISH AND WILDLIFE SERVICE, DEPARTMENT OF THE INTERIOR GENERAL PROVISIONS NONDISCRIMINATION-CONTRACTS, PERMITS, AND USE OF FACILITIES § 3.3 Discrimination by contractors and permittees prohibited. The provisions of part III of Executive...

  20. 50 CFR 3.3 - Discrimination by contractors and permittees prohibited.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... permittees prohibited. 3.3 Section 3.3 Wildlife and Fisheries UNITED STATES FISH AND WILDLIFE SERVICE, DEPARTMENT OF THE INTERIOR GENERAL PROVISIONS NONDISCRIMINATION-CONTRACTS, PERMITS, AND USE OF FACILITIES § 3.3 Discrimination by contractors and permittees prohibited. The provisions of part III of Executive...

  1. 48 CFR 536.271 - Project labor agreements.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... facilities to be owned by a Federal department or agency. You may use a PLA in leasehold arrangement... than $5 million. Project Labor Agreement (PLA) means an agreement between the contractor, subcontractors, and the union(s) representing workers. Under a PLA, the contractor and subcontractors on a...

  2. 29 CFR 471.1 - What definitions apply to this part?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... NOTIFICATION OF EMPLOYEE RIGHTS UNDER FEDERAL LABOR LAWS OBLIGATIONS OF FEDERAL CONTRACTORS AND SUBCONTRACTORS; NOTIFICATION OF EMPLOYEE RIGHTS UNDER FEDERAL LABOR LAWS Definitions, Requirements for Employee Notice, and... location or facility at which a contractor or subcontractor meets a demand or performs a function relating...

  3. Civilian Contractors under Military Law

    DTIC Science & Technology

    2007-01-01

    MEJAhave Autumn 2007 87 dogged the USA Patriot Act, as well; there has only been one successful prose- cution of an Afghanistan- or Iraq-based...Baghdad Central Confinement Facility in Abu Ghraib. See “Abu Ghraib Contractor Sen- tenced for Child Porn ,” Associated Press, 25 May 2007, http

  4. 48 CFR 252.239-7004 - Orders for facilities and services.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 48 Federal Acquisition Regulations System 3 2011-10-01 2011-10-01 false Orders for facilities and... of Provisions And Clauses 252.239-7004 Orders for facilities and services. As prescribed in 239.7411(a), use the following clause: Orders for Facilities and Services (NOV 2005) The Contractor shall...

  5. 48 CFR 5152.208-9001 - Industrial preparedness planning.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... in paragraph (e) of this clause. As an LFPP for the listed items, the contractor will be solicited..., i.e. by assigning workload to a government-owned facility. (b) The Contractor agrees to: (i) Update... certifies that this capacity is not shared by any other mobilization production requirements. (e) This...

  6. 48 CFR 904.7004 - Findings, determination, and contract award or termination.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... that award of a contract to an offeror(s) or continued performance of a contract by a contractor will... types of plans that a contractor can propose are: measures which provide for physical or organizational separation of the facility or organizational component containing the classified information or special...

  7. 48 CFR 9.308-1 - Testing performed by the contractor.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... ACQUISITION PLANNING CONTRACTOR QUALIFICATIONS First Article Testing and Approval 9.308-1 Testing performed by... produce the first article and the production quantity at the same facility, the contracting officer shall... material or to commence production before first article approval, the contracting officer shall use the...

  8. 48 CFR 9.308-1 - Testing performed by the contractor.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... ACQUISITION PLANNING CONTRACTOR QUALIFICATIONS First Article Testing and Approval 9.308-1 Testing performed by... produce the first article and the production quantity at the same facility, the contracting officer shall... material or to commence production before first article approval, the contracting officer shall use the...

  9. 48 CFR 9.308-1 - Testing performed by the contractor.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... ACQUISITION PLANNING CONTRACTOR QUALIFICATIONS First Article Testing and Approval 9.308-1 Testing performed by... produce the first article and the production quantity at the same facility, the contracting officer shall... material or to commence production before first article approval, the contracting officer shall use the...

  10. 48 CFR 9.308-1 - Testing performed by the contractor.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... ACQUISITION PLANNING CONTRACTOR QUALIFICATIONS First Article Testing and Approval 9.308-1 Testing performed by... produce the first article and the production quantity at the same facility, the contracting officer shall... material or to commence production before first article approval, the contracting officer shall use the...

  11. 48 CFR 9.308-1 - Testing performed by the contractor.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... ACQUISITION PLANNING CONTRACTOR QUALIFICATIONS First Article Testing and Approval 9.308-1 Testing performed by... produce the first article and the production quantity at the same facility, the contracting officer shall... material or to commence production before first article approval, the contracting officer shall use the...

  12. 77 FR 40884 - Office of the Chief Information Officer; Information Collection; Temporary Contractor Information...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-07-11

    ... Management and Budget (OMB) a request to review and approve a previously approved information collection... collection to make determinations on granting unescorted physical access to GSA-controlled facilities. The approval is critical for GSA to continue to make physical access determinations for temporary contractors...

  13. Design Criteria for Controlling Stress Corrosion Cracking

    NASA Technical Reports Server (NTRS)

    Franklin, D. B.

    1987-01-01

    This document sets forth the criteria to be used in the selection of materials for space vehicles and associated equipment and facilities so that failure resulting from stress corrosion will be prevented. The requirements established herein apply to all metallic components proposed for use in space vehicles and other flight hardware, ground support equipment, and facilities for testing. These requirements are applicable not only to items designed and fabricated by MSFC (Marshall Space Flight Center) and its prime contractors, but also to items supplied to the prime contractor by subcontractors and vendors.

  14. The role of NASA for aerospace information

    NASA Technical Reports Server (NTRS)

    Chandler, G. P., Jr.

    1980-01-01

    The NASA Scientific and Technical Information Program operations are performed by two contractor operated facilities. The NASA STI Facility, located near Baltimore, Maryland, employs about 210 people who process report literature, operate the computer complex, and provide support for software maintenance and developments. A second contractor, the Technical Information Services of the American Institute of Aeronautics and Astronautics, employs approximately 80 people in New York City and processes the open literature such as journals, magazines, and books. Features of these programs include online access via RECON, announcement services, and international document exchange.

  15. DoD Needs to Improve the Billing System for Health Care Provided to Contractors at Medical Treatment Facilities in Southwest Asia

    DTIC Science & Technology

    2012-06-27

    8866 (DSN 664-8866). Alice F. Carey Assistant Inspector General Readiness, Operations, and Support DISTRIBUTION: UNDER SECRETARY...medical or dental care is not authorized, and contractor personnel may not receive these services at MTFs unless specifically authorized under the

  16. 25 CFR 900.94 - Is contractor-purchased real property to which an Indian tribe or tribal organization holds title...

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... tribe or tribal organization holds title eligible for facilities operation and maintenance funding from... INDIAN HEALTH SERVICE, DEPARTMENT OF HEALTH AND HUMAN SERVICES CONTRACTS UNDER THE INDIAN SELF... Is contractor-purchased real property to which an Indian tribe or tribal organization holds title...

  17. 25 CFR 900.94 - Is contractor-purchased real property to which an Indian tribe or tribal organization holds title...

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... tribe or tribal organization holds title eligible for facilities operation and maintenance funding from... INDIAN HEALTH SERVICE, DEPARTMENT OF HEALTH AND HUMAN SERVICES CONTRACTS UNDER THE INDIAN SELF... Is contractor-purchased real property to which an Indian tribe or tribal organization holds title...

  18. 25 CFR 900.94 - Is contractor-purchased real property to which an Indian tribe or tribal organization holds title...

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... tribe or tribal organization holds title eligible for facilities operation and maintenance funding from... INDIAN HEALTH SERVICE, DEPARTMENT OF HEALTH AND HUMAN SERVICES CONTRACTS UNDER THE INDIAN SELF... Is contractor-purchased real property to which an Indian tribe or tribal organization holds title...

  19. 75 FR 34182 - Notice of Intent To Prepare a Programmatic Environmental Assessment for Proposed Mobile Fueling...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-06-16

    ... Mobile Fueling Operations, Nationwide AGENCY: Postal Service. ACTION: Notice of intent to prepare a...) for the use of mobile fueling contractors to fuel postal vehicles on-site at selected Postal Service... utilize mobile fueling contractors to fuel vehicles on site at selected postal facilities located...

  20. Proceedings of the Department of Energy ALARA Workshop

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Dionne, B.J.; Baum, J.W.

    1992-01-01

    The report contains summaries of papers, discussions, and operational exercises presented at the first Department of Energy ALARA Workshop held at Brookhaven National Laboratory, Upton, New York on April 21--22, 1992. The purpose of this workshop was to provide a forum for, and enhance communication among, ALARA personnel, as well as to inform DOE's field office and contractor personnel about the Office of Health's programs and expectations from the entire DOE complex efforts in the ALARA area.The two-day workshop consisted of one day dedicated to presentations on implementing various elements of a formal ALARA program at the DOE contractors' facilities,more » regulatory aspects of ALARA programs, and DOE Headquarters' ALARA expectations/initiatives. The second day was devoted to detailed discussions on ALARA improvements and problems, and operational exercises on cost-benefit analyses and on ALARA job/experiment reviews. At this workshop, 70 health physicists and radiation safety engineers from 5 DOE Headquarter Offices, 7 DOE operations/area offices, and 27 contractor facilities exchanged information, which is expected to stimulate further improvement in the DOE contractors' ALARA programs. Individual papers are indexed separately.« less

  1. Evaluation of the NASA Quality Surveillance System Pilot in Meeting Requirements for Contractor Surveillance Under Performance Based Contracting

    NASA Technical Reports Server (NTRS)

    Schmahl, Karen E.

    2002-01-01

    The use of performance-based contracting at Kennedy Space Center has necessitated a shift from intrusive oversight of contractor activities to an insight surveillance role. This paper describes the results of a pilot implementation of the NASA Quality Surveillance System (NQSS) in the Space Shuttle Main Engines Processing Facility. The NQSS is a system to sample contractor activities using documented procedures, specifications, drawings and observations of work in progress to answer the question "Is the contractor doing what they said they would do?" The concepts of the NQSS are shown to be effective in providing assurance of contractor quality. Many of the concepts proven in the pilot are being considered for incorporation into an overall KSC Quality Surveillance System.

  2. Evaluation Of The NASA Quality Surveillance System Pilot In Meeting Requirements For Contractor Surveillance Under Performance Based Contracting

    NASA Technical Reports Server (NTRS)

    Schmahl, Karen E.

    2001-01-01

    The use of performance-based contracting at Kennedy Space Center has necessitated a shift from intrusive oversight of contractor activities to an insight surveillance role. This paper describes the results of a pilot implementation of the NASA Quality Surveillance System (NQSS) in the Space Shuttle Main Engines Processing Facility. The NQSS is a system to sample contractor activities using documented procedures, specifications, drawings and observations of work in progress to answer the question "Is the contractor doing what they said they would do?" The concepts of the NQSS are shown to be effective in providing assurance of contractor quality. Many of the concepts proven in the pilot are being considered for incorporation into an overall KSC Quality Surveillance System.

  3. 48 CFR 970.3770-1 - Policy.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... REGULATIONS DOE MANAGEMENT AND OPERATING CONTRACTS Facilities Management Contracting 970.3770-1 Policy. Contractors managing Department of Energy (DOE) facilities shall be required to comply with the DOE Directives applicable to facilities management. [65 FR 81009, Dec. 22, 2000, as amended at 74 FR 36374, July 22, 2009] ...

  4. SGSLR Testing Facility at GGAO

    NASA Technical Reports Server (NTRS)

    Hoffman, Evan

    2016-01-01

    This document describes the SGSLR Test Facility at Goddards Geophysical and Astronomical Observatory (NASA Goddard area 200) and its features are described at a high level for users. This is the facility that the Contractor will be required to use for the Testing and Verification of all SGSLR systems.

  5. 48 CFR 252.239-7011 - Special construction and equipment charges.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... the Contractor stops using facilities or equipment which the Government has, in whole or part... equipment attributable to the Government's contribution. Determine the value of the facilities and equipment...— (1) Recurring charges for the services, facilities, and equipment do not include in the rate base any...

  6. 14 CFR 1216.302 - Definition of key terms.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... performing in-house R&D and for planning, managing, and supporting contractor and grantee R&D), and for other... related facility equipment; design of facilities projects; and advance planning related to future facilities needs. (4) Space Flight, Control and Data Communications (SFCDC). Has similar scope to R&D but...

  7. 14 CFR 1216.302 - Definition of key terms.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... performing in-house R&D and for planning, managing, and supporting contractor and grantee R&D), and for other... related facility equipment; design of facilities projects; and advance planning related to future facilities needs. (4) Space Flight, Control and Data Communications (SFCDC). Has similar scope to R&D but...

  8. 14 CFR 1216.302 - Definition of key terms.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... performing in-house R&D and for planning, managing, and supporting contractor and grantee R&D), and for other... related facility equipment; design of facilities projects; and advance planning related to future facilities needs. (4) Space Flight, Control and Data Communications (SFCDC). Has similar scope to R&D but...

  9. 47 CFR 27.1238 - Eligible costs.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... Telecommunication FEDERAL COMMUNICATIONS COMMISSION (CONTINUED) COMMON CARRIER SERVICES MISCELLANEOUS WIRELESS...) Legal fees; (5) Site acquisition fees-contractor; and (6) Arbitrator fee; (c) Transmission facility... manage the BTA conversion); and (10) Travel and Per Diem Cost. (d) Transmission facility-digital...

  10. 47 CFR 27.1238 - Eligible costs.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... Telecommunication FEDERAL COMMUNICATIONS COMMISSION (CONTINUED) COMMON CARRIER SERVICES MISCELLANEOUS WIRELESS...) Legal fees; (5) Site acquisition fees-contractor; and (6) Arbitrator fee; (c) Transmission facility... manage the BTA conversion); and (10) Travel and Per Diem Cost. (d) Transmission facility-digital...

  11. 47 CFR 27.1238 - Eligible costs.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... Telecommunication FEDERAL COMMUNICATIONS COMMISSION (CONTINUED) COMMON CARRIER SERVICES MISCELLANEOUS WIRELESS...) Legal fees; (5) Site acquisition fees-contractor; and (6) Arbitrator fee; (c) Transmission facility... manage the BTA conversion); and (10) Travel and Per Diem Cost. (d) Transmission facility-digital...

  12. 47 CFR 27.1238 - Eligible costs.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... Telecommunication FEDERAL COMMUNICATIONS COMMISSION (CONTINUED) COMMON CARRIER SERVICES MISCELLANEOUS WIRELESS...) Legal fees; (5) Site acquisition fees-contractor; and (6) Arbitrator fee; (c) Transmission facility... manage the BTA conversion); and (10) Travel and Per Diem Cost. (d) Transmission facility-digital...

  13. Outsourcing strategy and tendering methodology for the operation and maintenance of CERN’s cryogenic facilities

    NASA Astrophysics Data System (ADS)

    Serio, L.; Bremer, J.; Claudet, S.; Delikaris, D.; Ferlin, G.; Ferrand, F.; Pezzetti, M.; Pirotte, O.

    2017-12-01

    CERN operates and maintains the world largest cryogenic infrastructure ranging from ageing but well maintained installations feeding detectors, test facilities and general services, to the state-of-the-art cryogenic system serving the flagship LHC machine complex. A study was conducted and a methodology proposed to outsource to industry the operation and maintenance of the whole cryogenic infrastructure. The cryogenic installations coupled to non LHC-detectors, test facilities and general services infrastructure have been fully outsourced for operation and maintenance on the basis of performance obligations. The contractor is responsible for the operational performance of the installations based on a yearly operation schedule provided by CERN. The maintenance of the cryogenic system serving the LHC machine and its detectors has been outsourced on the basis of tasks oriented obligations, monitored by key performance indicators. CERN operation team, with the support of the contractor operation team, remains responsible for the operational strategy and performances. We report the analysis, strategy, definition of the requirements and technical specifications as well as the achieved technical and economic performances after one year of operation.

  14. KENNEDY SPACE CENTER, FLA. - The Space Life Sciences Lab (SLSL), formerly known as the Space Experiment Research and Processing Laboratory (SERPL), is nearing completion. The new lab is a state-of-the-art facility being built for ISS biotechnology research. Developed as a partnership between NASA-KSC and the State of Florida, NASA’s life sciences contractor will be the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA-sponsored research. About 20 percent of the facility will be available for use by Florida’s university researchers through the Florida Space Research Institute.

    NASA Image and Video Library

    2003-09-10

    KENNEDY SPACE CENTER, FLA. - The Space Life Sciences Lab (SLSL), formerly known as the Space Experiment Research and Processing Laboratory (SERPL), is nearing completion. The new lab is a state-of-the-art facility being built for ISS biotechnology research. Developed as a partnership between NASA-KSC and the State of Florida, NASA’s life sciences contractor will be the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA-sponsored research. About 20 percent of the facility will be available for use by Florida’s university researchers through the Florida Space Research Institute.

  15. Historic Neighborhood Schools: Success Stories. Issues and Initiatives.

    ERIC Educational Resources Information Center

    National Trust for Historic Preservation, Washington, DC.

    This document offers 19 case studies that show how people across the United States have kept historic schools as vital parts of their communities. The case studies address the most important challenges to the continued use of historic schools as educational facilities. They offer concise summaries of information that architects, contractors, and…

  16. Proceedings of the Department of Energy ALARA Workshop

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Dionne, B.J.; Baum, J.W.

    1992-12-31

    The report contains summaries of papers, discussions, and operational exercises presented at the first Department of Energy ALARA Workshop held at Brookhaven National Laboratory, Upton, New York on April 21--22, 1992. The purpose of this workshop was to provide a forum for, and enhance communication among, ALARA personnel, as well as to inform DOE`s field office and contractor personnel about the Office of Health`s programs and expectations from the entire DOE complex efforts in the ALARA area.The two-day workshop consisted of one day dedicated to presentations on implementing various elements of a formal ALARA program at the DOE contractors` facilities,more » regulatory aspects of ALARA programs, and DOE Headquarters` ALARA expectations/initiatives. The second day was devoted to detailed discussions on ALARA improvements and problems, and operational exercises on cost-benefit analyses and on ALARA job/experiment reviews. At this workshop, 70 health physicists and radiation safety engineers from 5 DOE Headquarter Offices, 7 DOE operations/area offices, and 27 contractor facilities exchanged information, which is expected to stimulate further improvement in the DOE contractors` ALARA programs. Individual papers are indexed separately.« less

  17. Managing Inventory At A Transitional Facility

    NASA Technical Reports Server (NTRS)

    Hutchins, Henry A.

    1993-01-01

    Kennedy Inventory Management System, KIMS, geared to needs of facility in transition from research and development to manufacturing. Operated jointly by several contractors at Kennedy Space Center, KIMS designed to reduce cost and increase efficiency of fabrication and maintenance of spaceflight hardware.

  18. Report on audit of Department of Energy`s contractor salary increase fund

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    NONE

    1997-04-04

    The Department of Energy (Department) uses contractors to operate its facilities and compensates contractor employees based on their skills, complexity of jobs, and work performance. Thirty-one of the Department`s major contractors reported a total payroll of $4.3 billion and $4.4 billion during 1994 and 1995, respectively. The 31 contractors also reported awarding salary increases of $18 million for 1994 and $200 million for 1995. The purpose of the audit was to review the process used to determine and approve the amount of salary increases for contractor employees. The specific audit objective was to determine whether salary increases received by contractormore » employees were in accordance with Departmental policies and procedures. The Department of Energy Acquisition Regulation (DEAR) requires that contractor salary actions be within specific limitations, supportable, and approved prior to incurrence of costs. In addition, the Secretary of Energy imposed a 1 year salary freeze on the merit portion of management and operating contractor employee salaries for each contractor`s Fiscal Year 1994 compensation year. However, a fund for promotions and adjustments was approved but limited to 0.5 percent of payroll for the year. A review of eight major contractors showed that six complied with the Department`s policies on salary increases. The other two gave salary increases that were not always in accordance with Departmental policies. This resulted in both contractors not fully complying with the pay freeze in 1994 and exceeding their salary increase fund budgets in 1995. If these two contractors had implemented Department and contract requirements and contracting officers had properly performed their contract administrative responsibilities concerning salary increase funds, both contractors would have frozen salary increases and would not have exceeded their annual budgets.« less

  19. 41 CFR 60-1.8 - Segregated facilities.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 41 Public Contracts and Property Management 1 2010-07-01 2010-07-01 true Segregated facilities. 60-1.8 Section 60-1.8 Public Contracts and Property Management Other Provisions Relating to Public... 1-OBLIGATIONS OF CONTRACTORS AND SUBCONTRACTORS Preliminary Matters; Equal Opportunity Clause...

  20. 41 CFR 60-1.8 - Segregated facilities.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 41 Public Contracts and Property Management 1 2011-07-01 2009-07-01 true Segregated facilities. 60-1.8 Section 60-1.8 Public Contracts and Property Management Other Provisions Relating to Public... 1-OBLIGATIONS OF CONTRACTORS AND SUBCONTRACTORS Preliminary Matters; Equal Opportunity Clause...

  1. Flying a College on the Computer. The Use of the Computer in Planning Buildings.

    ERIC Educational Resources Information Center

    Saint Louis Community Coll., MO.

    Upon establishment of the St. Louis Junior College District, it was decided to make use of computer si"ulation facilities of a nearby aero-space contractor to develop a master schedule for facility planning purposes. Projected enrollments and course offerings were programmed with idealized student-teacher ratios to project facility needs. In…

  2. 48 CFR 52.215-17 - Waiver of Facilities Capital Cost of Money.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... Capital Cost of Money. 52.215-17 Section 52.215-17 Federal Acquisition Regulations System FEDERAL... Provisions and Clauses 52.215-17 Waiver of Facilities Capital Cost of Money. As prescribed in 15.408(i), insert the following clause: Waiver of Facilities Capital Cost of Money (OCT 1997) The Contractor did not...

  3. 48 CFR 52.215-17 - Waiver of Facilities Capital Cost of Money.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... Capital Cost of Money. 52.215-17 Section 52.215-17 Federal Acquisition Regulations System FEDERAL... Provisions and Clauses 52.215-17 Waiver of Facilities Capital Cost of Money. As prescribed in 15.408(i), insert the following clause: Waiver of Facilities Capital Cost of Money (OCT 1997) The Contractor did not...

  4. 48 CFR 52.215-17 - Waiver of Facilities Capital Cost of Money.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... Capital Cost of Money. 52.215-17 Section 52.215-17 Federal Acquisition Regulations System FEDERAL... Provisions and Clauses 52.215-17 Waiver of Facilities Capital Cost of Money. As prescribed in 15.408(i), insert the following clause: Waiver of Facilities Capital Cost of Money (OCT 1997) The Contractor did not...

  5. 48 CFR 52.215-17 - Waiver of Facilities Capital Cost of Money.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... Capital Cost of Money. 52.215-17 Section 52.215-17 Federal Acquisition Regulations System FEDERAL... Provisions and Clauses 52.215-17 Waiver of Facilities Capital Cost of Money. As prescribed in 15.408(i), insert the following clause: Waiver of Facilities Capital Cost of Money (OCT 1997) The Contractor did not...

  6. 48 CFR 52.215-17 - Waiver of Facilities Capital Cost of Money.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... Capital Cost of Money. 52.215-17 Section 52.215-17 Federal Acquisition Regulations System FEDERAL... Provisions and Clauses 52.215-17 Waiver of Facilities Capital Cost of Money. As prescribed in 15.408(i), insert the following clause: Waiver of Facilities Capital Cost of Money (OCT 1997) The Contractor did not...

  7. Idaho National Laboratory (INL) Site Greenhouse Gas (GHG) Monitoring Plan - 40 CFR 98

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Deborah L. Layton; Kimberly Frerichs

    2011-12-01

    The purpose of this Greenhouse Gas (GHG) Monitoring Plan is to meet the monitoring plan requirements of Title 40 of the Code of Federal Regulations Part 98.3(g)(5). This GHG Monitoring Plan identifies procedures and methodologies used at the Idaho National Laboratory Site (INL Site) to collect data used for GHG emissions calculations and reporting requirements from stationary combustion and other regulated sources in accordance with 40 CFR 98, Subparts A and other applicable subparts. INL Site Contractors determined subpart applicability through the use of a checklist (Appendix A). Each facility/contractor reviews operations to determine which subparts are applicable and themore » results are compiled to determine which subparts are applicable to the INL Site. This plan is applicable to the 40 CFR 98-regulated activities managed by the INL Site contractors: Idaho National Laboratory (INL), Idaho Cleanup Project (ICP), Advanced Mixed Waste Treatment Project (AMWTP), and Naval Reactors Facilities (NRF).« less

  8. Idaho National Laboratory (INL) Site Greenhouse Gas (GHG) Monitoring Plan - 40 CFR 98

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Deborah L. Layton; Kimberly Frerichs

    2010-07-01

    The purpose of this Greenhouse Gas (GHG) Monitoring Plan is to meet the monitoring plan requirements of Title 40 of the Code of Federal Regulations Part 98.3(g)(5). This GHG Monitoring Plan identifies procedures and methodologies used at the Idaho National Laboratory Site (INL Site) to collect data used for GHG emissions calculations and reporting requirements from stationary combustion and other regulated sources in accordance with 40 CFR 98, Subparts A and other applicable subparts. INL Site Contractors determined subpart applicability through the use of a checklist (Appendix A). Each facility/contractor reviews operations to determine which subparts are applicable and themore » results are compiled to determine which subparts are applicable to the INL Site. This plan is applicable to the 40 CFR 98-regulated activities managed by the INL Site contractors: Idaho National Laboratory (INL), Idaho Cleanup Project (ICP), Advanced Mixed Waste Treatment Project (AMWTP), and Naval Reactors Facilities (NRF).« less

  9. 32 CFR 728.79 - Employees of Federal contractors and subcontractors.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... PERSONNEL MEDICAL AND DENTAL CARE FOR ELIGIBLE PERSONS AT NAVY MEDICAL DEPARTMENT FACILITIES Other Persons... nervous, mental, or contagious diseases or those requiring domiciliary care. Routine dental care, other than dental prosthesis and orthodontia, is authorized on a space available basis provided facilities...

  10. 32 CFR 728.79 - Employees of Federal contractors and subcontractors.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... PERSONNEL MEDICAL AND DENTAL CARE FOR ELIGIBLE PERSONS AT NAVY MEDICAL DEPARTMENT FACILITIES Other Persons... nervous, mental, or contagious diseases or those requiring domiciliary care. Routine dental care, other than dental prosthesis and orthodontia, is authorized on a space available basis provided facilities...

  11. 32 CFR 728.79 - Employees of Federal contractors and subcontractors.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... PERSONNEL MEDICAL AND DENTAL CARE FOR ELIGIBLE PERSONS AT NAVY MEDICAL DEPARTMENT FACILITIES Other Persons... nervous, mental, or contagious diseases or those requiring domiciliary care. Routine dental care, other than dental prosthesis and orthodontia, is authorized on a space available basis provided facilities...

  12. 32 CFR 728.79 - Employees of Federal contractors and subcontractors.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... PERSONNEL MEDICAL AND DENTAL CARE FOR ELIGIBLE PERSONS AT NAVY MEDICAL DEPARTMENT FACILITIES Other Persons... nervous, mental, or contagious diseases or those requiring domiciliary care. Routine dental care, other than dental prosthesis and orthodontia, is authorized on a space available basis provided facilities...

  13. 48 CFR 970.2672-1 - Policy.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... at a DOE Defense Nuclear Facility is necessary, DOE contractors and subcontractors at DOE Defense Nuclear Facilities shall accomplish work force restructuring or displacement so as to mitigate social and... with the objectives of section 3161 of the National Defense Authorization Act for Fiscal Year 1993, 42...

  14. 48 CFR 970.2672-1 - Policy.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... at a DOE Defense Nuclear Facility is necessary, DOE contractors and subcontractors at DOE Defense Nuclear Facilities shall accomplish work force restructuring or displacement so as to mitigate social and... with the objectives of section 3161 of the National Defense Authorization Act for Fiscal Year 1993, 42...

  15. 48 CFR 970.2672-1 - Policy.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... at a DOE Defense Nuclear Facility is necessary, DOE contractors and subcontractors at DOE Defense Nuclear Facilities shall accomplish work force restructuring or displacement so as to mitigate social and... with the objectives of section 3161 of the National Defense Authorization Act for Fiscal Year 1993, 42...

  16. 48 CFR 970.2672-1 - Policy.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... at a DOE Defense Nuclear Facility is necessary, DOE contractors and subcontractors at DOE Defense Nuclear Facilities shall accomplish work force restructuring or displacement so as to mitigate social and... with the objectives of section 3161 of the National Defense Authorization Act for Fiscal Year 1993, 42...

  17. 77 FR 780 - Procurement List Proposed Additions

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-01-06

    ... will perform management, supervision, cooking, food preparation, and baking in the two facilities. At no time will the contractor be responsible for the management and operational control of the dining facilities. These Government personnel are expected to be the food service personnel assigned to military...

  18. New Systems of Food Service Management for the Air Force

    DTIC Science & Technology

    1979-09-01

    Without good management and successful innovations to meet customer needs, institutional food systems either survive precariously, or on a...unlimited access to all base facilities as well as the innovative , profit oriented management of the contractor. The results of this analysis and its...of innovative , profit-oriented management on the part of the contractor. The results of this analysis, along with its impact on the data presented in

  19. Baseline Water Demand at Forward Operating Bases

    DTIC Science & Technology

    2013-09-15

    population, often equaling or exceeding the military population: • Brigade: 6000 soldiers • Battalion: 1000 soldiers • Company : 150 soldiers. ERDC/CERL TR...requirements for a company outpost (COP) of 120 personnel (PAX) in the format that the computer tool generates. This tool generates a basic sus...facilities world-wide through several large contractors. One contractor, Kellogg , Brown, and Root (KBR), used a minimum planning factor of 18.4

  20. Food Service Equipment. Third Edition.

    ERIC Educational Resources Information Center

    Jernigan, Anna Katherine; Ross, Lynne Nannen

    This book provides information that will help in purchasing the kind of food service equipment most useful in any given facility. Hence, it should be of value to architects, contractors, administrators, dietitians, managers, and others involved in remodeling a facility, replacing equipment, and/or improving the efficiency of food service…

  1. 48 CFR 252.239-7005 - Rates, charges, and services.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... services. (d) For nontariffed services, the Contractor shall charge the Government at the lowest rate and... customer. (e) Recurring charges for services and facilities shall, in each case, start with the... Government may stop the use of any service or facilities furnished under this agreement/contract at any time...

  2. 28 CFR 115.217 - Hiring and promotion decisions.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ..., and shall not enlist the services of any contractor who may have contact with residents, who— (1) Has engaged in sexual abuse in a prison, jail, lockup, community confinement facility, juvenile facility, or... engage in sexual activity in the community facilitated by force, overt or implied threats of force, or...

  3. 28 CFR 115.217 - Hiring and promotion decisions.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ..., and shall not enlist the services of any contractor who may have contact with residents, who— (1) Has engaged in sexual abuse in a prison, jail, lockup, community confinement facility, juvenile facility, or... engage in sexual activity in the community facilitated by force, overt or implied threats of force, or...

  4. 28 CFR 115.217 - Hiring and promotion decisions.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ..., and shall not enlist the services of any contractor who may have contact with residents, who— (1) Has engaged in sexual abuse in a prison, jail, lockup, community confinement facility, juvenile facility, or... engage in sexual activity in the community facilitated by force, overt or implied threats of force, or...

  5. 10 CFR 1706.1 - Scope; statement of policy.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 10 Energy 4 2011-01-01 2011-01-01 false Scope; statement of policy. 1706.1 Section 1706.1 Energy DEFENSE NUCLEAR FACILITIES SAFETY BOARD ORGANIZATIONAL AND CONSULTANT CONFLICTS OF INTERESTS § 1706.1... the Defense Nuclear Facilities Safety Board will follow in determining whether a contractor or offeror...

  6. 10 CFR 1706.9 - Examples.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 10 Energy 4 2014-01-01 2014-01-01 false Examples. 1706.9 Section 1706.9 Energy DEFENSE NUCLEAR... review of a safety aspect of a particular defense nuclear facility proposes to use the services of an expert who also serves on an oversight committee for a contractor of other defense nuclear facilities. (2...

  7. 10 CFR 1706.9 - Examples.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 10 Energy 4 2013-01-01 2013-01-01 false Examples. 1706.9 Section 1706.9 Energy DEFENSE NUCLEAR... review of a safety aspect of a particular defense nuclear facility proposes to use the services of an expert who also serves on an oversight committee for a contractor of other defense nuclear facilities. (2...

  8. 10 CFR 1706.5 - General rules.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... activities or research related to the Board's oversight of defense nuclear facilities, where the award would... offering to provide to DOE or to contractors or subcontractors for defense nuclear facilities; or (3) For... 10 Energy 4 2014-01-01 2014-01-01 false General rules. 1706.5 Section 1706.5 Energy DEFENSE...

  9. 10 CFR 1706.1 - Scope; statement of policy.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 10 Energy 4 2010-01-01 2010-01-01 false Scope; statement of policy. 1706.1 Section 1706.1 Energy DEFENSE NUCLEAR FACILITIES SAFETY BOARD ORGANIZATIONAL AND CONSULTANT CONFLICTS OF INTERESTS § 1706.1... the Defense Nuclear Facilities Safety Board will follow in determining whether a contractor or offeror...

  10. 10 CFR 1706.9 - Examples.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 10 Energy 4 2011-01-01 2011-01-01 false Examples. 1706.9 Section 1706.9 Energy DEFENSE NUCLEAR... review of a safety aspect of a particular defense nuclear facility proposes to use the services of an expert who also serves on an oversight committee for a contractor of other defense nuclear facilities. (2...

  11. 10 CFR 1706.1 - Scope; statement of policy.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 10 Energy 4 2013-01-01 2013-01-01 false Scope; statement of policy. 1706.1 Section 1706.1 Energy DEFENSE NUCLEAR FACILITIES SAFETY BOARD ORGANIZATIONAL AND CONSULTANT CONFLICTS OF INTERESTS § 1706.1... the Defense Nuclear Facilities Safety Board will follow in determining whether a contractor or offeror...

  12. 10 CFR 1706.1 - Scope; statement of policy.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 10 Energy 4 2012-01-01 2012-01-01 false Scope; statement of policy. 1706.1 Section 1706.1 Energy DEFENSE NUCLEAR FACILITIES SAFETY BOARD ORGANIZATIONAL AND CONSULTANT CONFLICTS OF INTERESTS § 1706.1... the Defense Nuclear Facilities Safety Board will follow in determining whether a contractor or offeror...

  13. 10 CFR 1706.9 - Examples.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 10 Energy 4 2012-01-01 2012-01-01 false Examples. 1706.9 Section 1706.9 Energy DEFENSE NUCLEAR... review of a safety aspect of a particular defense nuclear facility proposes to use the services of an expert who also serves on an oversight committee for a contractor of other defense nuclear facilities. (2...

  14. 10 CFR 1706.5 - General rules.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... activities or research related to the Board's oversight of defense nuclear facilities, where the award would... offering to provide to DOE or to contractors or subcontractors for defense nuclear facilities; or (3) For... 10 Energy 4 2012-01-01 2012-01-01 false General rules. 1706.5 Section 1706.5 Energy DEFENSE...

  15. 10 CFR 1706.1 - Scope; statement of policy.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 10 Energy 4 2014-01-01 2014-01-01 false Scope; statement of policy. 1706.1 Section 1706.1 Energy DEFENSE NUCLEAR FACILITIES SAFETY BOARD ORGANIZATIONAL AND CONSULTANT CONFLICTS OF INTERESTS § 1706.1... the Defense Nuclear Facilities Safety Board will follow in determining whether a contractor or offeror...

  16. 10 CFR 1706.5 - General rules.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... activities or research related to the Board's oversight of defense nuclear facilities, where the award would... offering to provide to DOE or to contractors or subcontractors for defense nuclear facilities; or (3) For... 10 Energy 4 2013-01-01 2013-01-01 false General rules. 1706.5 Section 1706.5 Energy DEFENSE...

  17. 23 CFR 660.519 - Missile installations and facilities.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 23 Highways 1 2014-04-01 2014-04-01 false Missile installations and facilities. 660.519 Section... OPERATIONS SPECIAL PROGRAMS (DIRECT FEDERAL) Defense Access Roads § 660.519 Missile installations and...). (1) To implement 23 U.S.C. 210(h), DOD must make the determination that a contractor for a missile...

  18. 23 CFR 660.519 - Missile installations and facilities.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 23 Highways 1 2013-04-01 2013-04-01 false Missile installations and facilities. 660.519 Section... OPERATIONS SPECIAL PROGRAMS (DIRECT FEDERAL) Defense Access Roads § 660.519 Missile installations and...). (1) To implement 23 U.S.C. 210(h), DOD must make the determination that a contractor for a missile...

  19. 29 CFR 500.1 - Purpose and scope.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... a farm labor contractor. (f) The facilities and services of the U.S. Employment Service, including... agency. See 20 CFR 658.501(a)(4). The facilities and services of the U.S. Employment Service shall be... challenge to a proposed administrative action relating to violations and summarizes the methods provided for...

  20. Ground-based plasma contractor characterization

    NASA Technical Reports Server (NTRS)

    Patterson, Michael J.; Aadland, Randall S.

    1987-01-01

    Presented are recent NASA Lewis Research Center (LeRC) plasma contractor experimental results, as well as a description of the plasma contractor test facility. The operation of a 24 cm diameter plasma source with hollow cathode was investigated in the lighted-mode regime of electron current collection from 0.1 to 7.0 A. These results are compared to those obtained with a 12 cm plasma source. Full two-dimensional plasma potential profiles were constructed from emissive probe traces of the contractor plume. The experimentally measured dimensions of the plume sheaths were then compared to those theoretically predicted using a model of a spherical double sheath. Results are consistent for currents up to approximately 1.0 A. For currents above 1.0 A, substantial deviations from theory occur. These deviations are due to sheath asphericity, and possibly volume ionization in the double-sheath region.

  1. KENNEDY SPACE CENTER, FLA. -- Sharon Edney, with Dynamac Corp., measures photosynthesis on Bibb lettuce being grown hydroponically for study in the Space Life Sciences Lab. The 100,000 square-foot facility houses labs for NASA’s ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASA’s Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASA’s Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

    NASA Image and Video Library

    2004-01-05

    KENNEDY SPACE CENTER, FLA. -- Sharon Edney, with Dynamac Corp., measures photosynthesis on Bibb lettuce being grown hydroponically for study in the Space Life Sciences Lab. The 100,000 square-foot facility houses labs for NASA’s ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASA’s Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASA’s Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

  2. KENNEDY SPACE CENTER, FLA. -- Sharon Edney, with Dynamac Corp., checks the roots of green onions being grown hydroponically for study in the Space Life Sciences Lab. The 100,000 square-foot facility houses labs for NASA’s ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASA’s Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASA’s Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

    NASA Image and Video Library

    2004-01-05

    KENNEDY SPACE CENTER, FLA. -- Sharon Edney, with Dynamac Corp., checks the roots of green onions being grown hydroponically for study in the Space Life Sciences Lab. The 100,000 square-foot facility houses labs for NASA’s ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASA’s Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASA’s Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

  3. KENNEDY SPACE CENTER, FLA. -- Sharon Edney, with Dynamac Corp., checks the growth of radishes being grown hydroponically for study in the Space Life Sciences Lab. The 100,000 square-foot facility houses labs for NASA’s ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASA’s Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASA’s Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

    NASA Image and Video Library

    2004-01-05

    KENNEDY SPACE CENTER, FLA. -- Sharon Edney, with Dynamac Corp., checks the growth of radishes being grown hydroponically for study in the Space Life Sciences Lab. The 100,000 square-foot facility houses labs for NASA’s ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASA’s Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASA’s Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

  4. Regulatory facility guide for Ohio

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Anderson, S.S.; Bock, R.E.; Francis, M.W.

    1994-02-28

    The Regulatory Facility Guide (RFG) has been developed for the DOE and contractor facilities located in the state of Ohio. It provides detailed compilations of international, federal, and state transportation-related regulations applicable to shipments originating at destined to Ohio facilities. This RFG was developed as an additional resource tool for use both by traffic managers who must ensure that transportation operations are in full compliance with all applicable regulatory requirements and by oversight personnel who must verify compliance activities.

  5. Final report of the decontamination and decommission of Building 31 at the Grand Junction Projects Office Facility

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Krabacher, J.E.

    1996-07-01

    The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the domestic uranium procurement program funded by the U.S. Atomic Energy Commission. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also was the remedial actionmore » contractor. Radiological contamination was identified in Building 31 and the building was demolished in 1992. The soil area within the footprint of the building has been remediated in accordance with the identified standards and the area can be released for unlimited exposure and unrestricted use. This area was addressed in the summary final report of the remediation of the exterior areas of the GJPO facility. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.« less

  6. 10 CFR 1004.3 - Public reading facilities and policy on contractor records.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    .... 1004.3 Section 1004.3 Energy DEPARTMENT OF ENERGY (GENERAL PROVISIONS) FREEDOM OF INFORMATION § 1004.3... Freedom of Information Office, 1000 Independence Avenue, SW, Washington, DC. A complete listing of other facilities is available from the Freedom of Information Officer at DOE Headquarters. (b) Each of the...

  7. GAO’s Views on DOE’s 1991 Budget for Addressing Problems at the Nuclear Weapons Complex

    DTIC Science & Technology

    1990-03-02

    management, and efforts by DOE to make its contractors more accountable. Also, the Defense Nuclear Facilities Safety Board mandated by the Congress became...and safety matters. 6 Finally, the Defense Nuclear Facilities Safety Board was established. Although not a DOE action, its establishment, nevertheless

  8. Final report of the decontamination and decommissioning of Building 6 at the Grand Junction Projects Office Facility

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Widdop, M.R.

    1996-07-01

    The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the domestic uranium procurement program funded by the U.S. Atomic Energy Commission. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, is also the remedial actionmore » contractor. Radiological contamination was identified in Building 6, and the building was demolished in 1992. The soil area within the footprint of the building has been remediated in accordance with the identified standards and the area can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.« less

  9. Final report of the decontamination and decommissioning of Building 34 at the Grand Junction Projects Office Facility

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Widdop, M.R.

    1996-08-01

    The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7 acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the Grand Junction Projects Office Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, was also the remedialmore » action contractor. Building 34 was radiologically contaminated and the building was demolished in 1996. The soil area within the footprint of the building was analyzed and found to be not contaminated. The area can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual closeout report for each contaminated GJPO building.« less

  10. Final report of the decontamination and decommissioning of Building 39 at the Grand Junction Projects Office Facility

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Widdop, M.R.

    1996-07-01

    The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, is also the remedial action contractor. The soilmore » beneath Building 39 was radiologically contaminated and the building was demolished in 1992. The soil area within the footprint of the building has been remediated in accordance with the identified standards and the area can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.« less

  11. Final report of the decontamination and decommissioning of Building 44 at the Grand Junction Projects Office Facility

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Widdop, M.R.

    1996-07-01

    The U.S. Department of Energy (DOE) Junction Projects Office (GJPO) occupies a 61.7 acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the Grand Junction Projects Office Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, is also the remedial actionmore » contractor. Building 44 was radiologically contaminated and the building was demolished in 1994. The soil area within the footprint of the building was not contaminated; it complies with the identified standards and the area can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.« less

  12. US Department of Energy Grand Junction Projects Office Remedial Action Project, final report of the decontamination and decommissioning of Building 36 at the Grand Junction Projects Office Facility

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Widdop, M.R.

    1996-08-01

    The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also is the remedial action contractor. Building 36more » was found to be radiologically contaminated and was demolished in 1996. The soil beneath the building was remediated in accordance with identified standards and can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.« less

  13. Final report of the decontamination and decommissioning of Building 18 at the Grand Junction Projects Office Facility

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Widdop, M.R.

    1996-08-01

    The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also is the remedial action contractor. The soilmore » beneath Building 18 was found to be radiologically contaminated; the building was not contaminated. The soil was remediated in accordance with identified standards. Building 18 and the underlying soil can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.« less

  14. Final report of the decontamination and decommissioning of Building 1 at the Grand Junction Projects Office Facility

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Widdop, M.R.

    1996-08-01

    The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also is the remedial action contractor. Building 1more » was found to be radiologically contaminated and was demolished in 1996. The soil beneath and adjacent to the building was remediated in accordance with identified standards and can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.« less

  15. Resource Conservation and Recovery Act (RCRA) Facility Presentation

    EPA Pesticide Factsheets

    The first presentation (86-slides), provided by Environmental Management Services (contractor to Cavenham Forest Industries) covers work progress being undertaken with respect to the corrective action.

  16. Analysis and comparison of five contractor safety and health manuals (EG and G, SR II, ORNL, Ashland, and MLGW)

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Crowder, C.; Hurley, T.

    1981-03-01

    An analysis is presented of five safety and health contractor manuals against the requirements of the FE OSH Manual (FE 5480.1), and a breakdown in chart form of how the manuals compare to each other is given. It is pointed out that the manuals are inadequate, but that site visits will be necessary to determine the actual comprehensiveness of the facilities' safety and health programs.

  17. Final report of the decontamination and decommissioning of the exterior land areas at the Grand Junction Projects Office facility

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Widdop, M.R.

    1995-09-01

    The US Department of Energy (DOE) Grand Junction Projects Office (GJPO) facility occupies approximately 56.4 acres (22.8 hectares) along the Gunnison River near Grand Junction, Colorado. The site was contaminated with uranium ore and mill tailings during uranium-refining activities conducted by the Manhattan Engineer District and during pilot-milling experiments conducted for the US Atomic Energy Commission`s (AEC`s) domestic uranium procurement program. The GJPO facility was the collection and assay point for AEC uranium and vanadium oxide purchases until the early 1970s. The DOE Decontamination and Decommissioning Program sponsored the Grand Junction Projects Office Remedial Action Project (GJPORAP) to remediate themore » facility lands, site improvements, and the underlying aquifer. The site contractor, Rust Geotech, was the Remedial Action Contractor for GJPORAP. The exterior land areas of the facility assessed as contaminated have been remediated in accordance with identified standards and can be released for unrestricted use. Restoration of the aquifer will be accomplished through the natural flushing action of the aquifer during the next 50 to 80 years. The remediation of the DOE-GJPO facility buildings is ongoing and will be described in a separate report.« less

  18. 24 CFR 581.2 - Applicability.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ...-owned, contractor-operated machinery, equipment, land, and other facilities reported excess for sale.... (10) Easements. (11) Property purchased in whole or in part with Federal funds if title to the...

  19. Ground Operations Aerospace Language (GOAL). Volume 1: Study overview

    NASA Technical Reports Server (NTRS)

    1973-01-01

    A series of NASA and Contractor studies sponsored by NASA/KSC resulted in a specification for the Ground Operations Aerospace Language (GOAL). The Cape Kennedy Facility of the IBM Corporation was given the responsibility, under existing contracts, to perform an analysis of the Language Specification, to design and develop a GOAL Compiler, to provide a specification for a data bank, to design and develop an interpretive code translator, and to perform associated application studies.

  20. Hanford facility dangerous waste permit application, general information portion. Revision 3

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Sonnichsen, J.C.

    1997-08-21

    For purposes of the Hanford facility dangerous waste permit application, the US Department of Energy`s contractors are identified as ``co-operators`` and sign in that capacity (refer to Condition I.A.2. of the Dangerous Waste Portion of the Hanford Facility Resource Conservation and Recovery Act Permit). Any identification of these contractors as an ``operator`` elsewhere in the application is not meant to conflict with the contractors` designation as co-operators but rather is based on the contractors` contractual status with the U.S. Department of Energy, Richland Operations Office. The Dangerous Waste Portion of the initial Hanford Facility Resource Conservation and Recovery Act Permit,more » which incorporated five treatment, storage, and/or disposal units, was based on information submitted in the Hanford Facility Dangerous Waste Permit Application and in closure plan and closure/postclosure plan documentation. During 1995, the Dangerous Waste Portion was modified twice to incorporate another eight treatment, storage, and/or disposal units; during 1996, the Dangerous Waste Portion was modified once to incorporate another five treatment, storage, and/or disposal units. The permit modification process will be used at least annually to incorporate additional treatment, storage, and/or disposal units as permitting documentation for these units is finalized. The units to be included in annual modifications are specified in a schedule contained in the Dangerous Waste Portion of the Hanford Facility Resource Conservation and Recovery Act Permit. Treatment, storage, and/or disposal units will remain in interim status until incorporated into the Permit. The Hanford Facility Dangerous Waste Permit Application is considered to be a single application organized into a General Information Portion (this document, DOE/RL-91-28) and a Unit-Specific Portion. The scope of the Unit-Specific Portion is limited to individual operating treatment, storage, and/or disposal units for which Part B permit application documentation has been, or is anticipated to be, submitted. Documentation for treatment, storage, and/or disposal units undergoing closure, or for units that are, or are anticipated to be, dispositioned through other options, will continue to be submitted by the Permittees in accordance with the provisions of the Hanford Federal Facility Agreement and Consent Order. However, the scope of the General Information Portion includes information that could be used to discuss operating units, units undergoing closure, or units being dispositioned through other options. Both the General Information and Unit-Specific portions of the Hanford Facility Dangerous Waste Permit Application address the contents of the Part B permit application guidance documentation prepared by the Washington State Department of Ecology and the U.S. Environmental Protection Agency, with additional information needs defined by revisions of Washington Administrative Code 173-303 and by the Hazardous and Solid Waste Amendments. Documentation contained in the General Information Portion is broader in nature and could be used by multiple treatment, storage, and/or disposal units (i.e., either operating units, units undergoing closure, or units being dispositioned through other options).« less

  1. 45 CFR 12a.2 - Applicability.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ..., and other facilities reported excess for sale only to the using contractor and subject to a continuing.... (9) Property interests subject to reversion. (10) Easements. (11) Property purchased in whole or in...

  2. 45 CFR 12a.2 - Applicability.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ..., and other facilities reported excess for sale only to the using contractor and subject to a continuing.... (9) Property interests subject to reversion. (10) Easements. (11) Property purchased in whole or in...

  3. 45 CFR 12a.2 - Applicability.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ..., and other facilities reported excess for sale only to the using contractor and subject to a continuing.... (9) Property interests subject to reversion. (10) Easements. (11) Property purchased in whole or in...

  4. Roadway sampling evaluation.

    DOT National Transportation Integrated Search

    2014-09-01

    The Florida Department of Transportation (FDOT) has traditionally required that all sampling : and testing of asphalt mixtures be at the Contractors production facility. With recent staffing cuts, as : well as budget reductions, FDOT has been cons...

  5. 25 CFR 170.473 - What happens when a construction project ends?

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... RESERVATION ROADS PROGRAM Planning, Design, and Construction of Indian Reservation Roads Program Facilities... inspection, as well as contractors and maintenance personnel. (2) All project information must be made...

  6. Construction safety program for the National Ignition Facility, July 30, 1999 (NIF-0001374-OC)

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Benjamin, D W

    1999-07-30

    These rules apply to all LLNL employees, non-LLNL employees (including contract labor, supplemental labor, vendors, personnel matrixed/assigned from other National Laboratories, participating guests, visitors and students) and contractors/subcontractors. The General Rules-Code of Safe Practices shall be used by management to promote accident prevention through indoctrination, safety and health training and on-the-job application. As a condition for contracts award, all contractors and subcontractors and their employees must certify on Form S and H A-l that they have read and understand, or have been briefed and understand, the National Ignition Facility OCIP Project General Rules-Code of Safe Practices. (An interpreter must briefmore » those employees who do not speak or read English fluently.) In addition, all contractors and subcontractors shall adopt a written General Rules-Code of Safe Practices that relates to their operations. The General Rules-Code of Safe Practices must be posted at a conspicuous location at the job site office or be provided to each supervisory employee who shall have it readily available. Copies of the General Rules-Code of Safe Practices can also be included in employee safety pamphlets.« less

  7. Safety Oversight of Decommissioning Activities at DOE Nuclear Sites

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Zull, Lawrence M.; Yeniscavich, William

    2008-01-15

    The Defense Nuclear Facilities Safety Board (Board) is an independent federal agency established by Congress in 1988 to provide nuclear safety oversight of activities at U.S. Department of Energy (DOE) defense nuclear facilities. The activities under the Board's jurisdiction include the design, construction, startup, operation, and decommissioning of defense nuclear facilities at DOE sites. This paper reviews the Board's safety oversight of decommissioning activities at DOE sites, identifies the safety problems observed, and discusses Board initiatives to improve the safety of decommissioning activities at DOE sites. The decommissioning of former defense nuclear facilities has reduced the risk of radioactive materialmore » contamination and exposure to the public and site workers. In general, efforts to perform decommissioning work at DOE defense nuclear sites have been successful, and contractors performing decommissioning work have a good safety record. Decommissioning activities have recently been completed at sites identified for closure, including the Rocky Flats Environmental Technology Site, the Fernald Closure Project, and the Miamisburg Closure Project (the Mound site). The Rocky Flats and Fernald sites, which produced plutonium parts and uranium materials for defense needs (respectively), have been turned into wildlife refuges. The Mound site, which performed R and D activities on nuclear materials, has been converted into an industrial and technology park called the Mound Advanced Technology Center. The DOE Office of Legacy Management is responsible for the long term stewardship of these former EM sites. The Board has reviewed many decommissioning activities, and noted that there are valuable lessons learned that can benefit both DOE and the contractor. As part of its ongoing safety oversight responsibilities, the Board and its staff will continue to review the safety of DOE and contractor decommissioning activities at DOE defense nuclear sites.« less

  8. KENNEDY SPACE CENTER, FLA. - Dynamac employees (from left) Larry Burns, Debbie Wells and Michelle Crouch talk in a conference room of the Space Life Sciences Lab (SLSL), formerly known as the Space Experiment Research and Processing Laboratory (SERPL). They have been transferring equipment from Hangar L. The new lab is a state-of-the-art facility being built for ISS biotechnology research. Developed as a partnership between NASA-KSC and the State of Florida, NASA’s life sciences contractor will be the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA-sponsored research. About 20 percent of the facility will be available for use by Florida’s university researchers through the Florida Space Research Institute.

    NASA Image and Video Library

    2003-09-10

    KENNEDY SPACE CENTER, FLA. - Dynamac employees (from left) Larry Burns, Debbie Wells and Michelle Crouch talk in a conference room of the Space Life Sciences Lab (SLSL), formerly known as the Space Experiment Research and Processing Laboratory (SERPL). They have been transferring equipment from Hangar L. The new lab is a state-of-the-art facility being built for ISS biotechnology research. Developed as a partnership between NASA-KSC and the State of Florida, NASA’s life sciences contractor will be the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA-sponsored research. About 20 percent of the facility will be available for use by Florida’s university researchers through the Florida Space Research Institute.

  9. KENNEDY SPACE CENTER, FLA. - Dynamac employees Debbie Wells, Michelle Crouch and Larry Burns are silhouetted as they talk inside a conference room of the Space Life Sciences Lab (SLSL), formerly known as the Space Experiment Research and Processing Laboratory (SERPL). They have been transferring equipment from Hangar L. The new lab is a state-of-the-art facility being built for ISS biotechnology research. Developed as a partnership between NASA-KSC and the State of Florida, NASA’s life sciences contractor will be the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA-sponsored research. About 20 percent of the facility will be available for use by Florida’s university researchers through the Florida Space Research Institute.

    NASA Image and Video Library

    2003-09-10

    KENNEDY SPACE CENTER, FLA. - Dynamac employees Debbie Wells, Michelle Crouch and Larry Burns are silhouetted as they talk inside a conference room of the Space Life Sciences Lab (SLSL), formerly known as the Space Experiment Research and Processing Laboratory (SERPL). They have been transferring equipment from Hangar L. The new lab is a state-of-the-art facility being built for ISS biotechnology research. Developed as a partnership between NASA-KSC and the State of Florida, NASA’s life sciences contractor will be the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA-sponsored research. About 20 percent of the facility will be available for use by Florida’s university researchers through the Florida Space Research Institute.

  10. KENNEDY SPACE CENTER, FLA. - Ivan Rodriguez, with Bionetics, and Michelle Crouch and Larry Burns, with Dynamac, carry boxes of equipment into the Space Life Sciences Lab (SLSL), formerly known as the Space Experiment Research and Processing Laboratory (SERPL). They are transferring equipment from Hangar L. The new lab is a state-of-the-art facility being built for ISS biotechnology research. Developed as a partnership between NASA-KSC and the State of Florida, NASA’s life sciences contractor will be the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA-sponsored research. About 20 percent of the facility will be available for use by Florida’s university researchers through the Florida Space Research Institute.

    NASA Image and Video Library

    2003-09-10

    KENNEDY SPACE CENTER, FLA. - Ivan Rodriguez, with Bionetics, and Michelle Crouch and Larry Burns, with Dynamac, carry boxes of equipment into the Space Life Sciences Lab (SLSL), formerly known as the Space Experiment Research and Processing Laboratory (SERPL). They are transferring equipment from Hangar L. The new lab is a state-of-the-art facility being built for ISS biotechnology research. Developed as a partnership between NASA-KSC and the State of Florida, NASA’s life sciences contractor will be the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA-sponsored research. About 20 percent of the facility will be available for use by Florida’s university researchers through the Florida Space Research Institute.

  11. KENNEDY SPACE CENTER, FLA. - Dynamac employees (from left) Larry Burns, Debbie Wells and Neil Yorio carry boxes of hardware into the Space Life Sciences Lab (SLSL), formerly known as the Space Experiment Research and Processing Laboratory (SERPL). They are transferring equipment from Hangar L. The new lab is a state-of-the-art facility being built for ISS biotechnology research. Developed as a partnership between NASA-KSC and the State of Florida, NASA’s life sciences contractor will be the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA-sponsored research. About 20 percent of the facility will be available for use by Florida’s university researchers through the Florida Space Research Institute.

    NASA Image and Video Library

    2003-09-10

    KENNEDY SPACE CENTER, FLA. - Dynamac employees (from left) Larry Burns, Debbie Wells and Neil Yorio carry boxes of hardware into the Space Life Sciences Lab (SLSL), formerly known as the Space Experiment Research and Processing Laboratory (SERPL). They are transferring equipment from Hangar L. The new lab is a state-of-the-art facility being built for ISS biotechnology research. Developed as a partnership between NASA-KSC and the State of Florida, NASA’s life sciences contractor will be the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA-sponsored research. About 20 percent of the facility will be available for use by Florida’s university researchers through the Florida Space Research Institute.

  12. Large space structures testing

    NASA Technical Reports Server (NTRS)

    Waites, Henry; Worley, H. Eugene

    1987-01-01

    There is considerable interest in the development of testing concepts and facilities that accurately simulate the pathologies believed to exist in future spacecraft. Both the Government and Industry have participated in the development of facilities over the past several years. The progress and problems associated with the development of the Large Space Structure Test Facility at the Marshall Flight Center are presented. This facility was in existence for a number of years and its utilization has run the gamut from total in-house involvement, third party contractor testing, to the mutual participation of other goverment agencies in joint endeavors.

  13. KENNEDY SPACE CENTER, FLA. -- Lanfang Levine, with Dynamac Corp., helps install a Dionex DX-500 IC/HPLC system in the Space Life Sciences Lab. The equipment will enable analysis of volatile compounds, such as from plants. The 100,000 square-foot facility houses labs for NASA’s ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASA’s Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASA’s Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

    NASA Image and Video Library

    2004-01-05

    KENNEDY SPACE CENTER, FLA. -- Lanfang Levine, with Dynamac Corp., helps install a Dionex DX-500 IC/HPLC system in the Space Life Sciences Lab. The equipment will enable analysis of volatile compounds, such as from plants. The 100,000 square-foot facility houses labs for NASA’s ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASA’s Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASA’s Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

  14. 41 CFR 50-204.34 - AEC licensees-AEC contractors operating AEC plants and facilities-AEC agreement State licensees...

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... material, or special nuclear material, as defined in the Atomic Energy Act of 1954, as amended, under a license issued by the Atomic Energy Commission and in accordance with the requirements of 10 CFR part 20... contract with the Atomic Energy Commission for the operation of AEC plants and facilities and in accordance...

  15. 41 CFR 50-204.34 - AEC licensees-AEC contractors operating AEC plants and facilities-AEC agreement State licensees...

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... material, or special nuclear material, as defined in the Atomic Energy Act of 1954, as amended, under a license issued by the Atomic Energy Commission and in accordance with the requirements of 10 CFR part 20... contract with the Atomic Energy Commission for the operation of AEC plants and facilities and in accordance...

  16. ELECTRICAL LINES ARRIVE FROM CENTRAL FACILITIES AREA, SOUTH OF MTR. ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    ELECTRICAL LINES ARRIVE FROM CENTRAL FACILITIES AREA, SOUTH OF MTR. EXCAVATION RUBBLE IN FOREGROUND. CONTRACTOR CRAFT SHOPS, CRANES, AND OTHER MATERIALS ON SITE. CAMERA FACES EAST, WITH LITTLE BUTTE AND MIDDLE BUTTE IN DISTANCE. INL NEGATIVE NO. 335. Unknown Photographer, 7/1/1950 - Idaho National Engineering Laboratory, Test Reactor Area, Materials & Engineering Test Reactors, Scoville, Butte County, ID

  17. Environmental Assessment for Proposed Demolition and Consolidation, Maxwell Air Force Base, Montgomery County, Alabama

    DTIC Science & Technology

    2013-09-01

    leadership, and management responsibilities. In addition, AU is responsible for research in designated fields of aerospace, education, leadership...County, Alabama. Designation : Final Environmental Assessment Abstract: As a result of a memorandum signed by President Obama in June 2010, the...Force Exchange Service) -ANG (Air National Guard) & Reserve facilities -Government-owned, contractor-funded facilities -RDT&E ( Research

  18. US Department of Energy Grand Junction Projects Office Remedial Action Project. Final report of the decontamination and decommissioning of Building 52 at the Grand Junction Projects Office Facility

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Krabacher, J.E.

    1996-08-01

    The U.S. Department of Energy (DOE) Grand Junction Projects Office (GJPO) occupies a 61.7-acre facility along the Gunnison River near Grand Junction, Colorado. This site was contaminated with uranium ore and mill tailings during uranium refining activities of the Manhattan Engineer District and during pilot milling experiments conducted for the U.S. Atomic Energy Commission`s domestic uranium procurement program. The DOE Defense Decontamination and Decommissioning Program established the GJPO Remedial Action Project to clean up and restore the facility lands, improvements, and the underlying aquifer. The site contractor for the facility, Rust Geotech, also was the remedial action contractor. Building 52more » was found to be radiologically contaminated and was demolished in 1994. The soil area within the footprint of the building has been remediated in accordance with the identified standards and the area can be released for unlimited exposure and unrestricted use. This document was prepared in response to a DOE request for an individual final report for each contaminated GJPO building.« less

  19. Emergency preparedness and planning

    NASA Technical Reports Server (NTRS)

    Bouvier, Kenneth

    1993-01-01

    Monsanto's emergency response plan in dealing with hazardous materials at their facilities is presented. Topics discussed include the following: CPR training; emergency medial training; incident reports; contractor injuries; hazardous materials transport; evacuation; and other industrial safety concerns.

  20. 41 CFR 102-75.1165 - What is the applicability of this subpart?

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ...-owned, contractor-operated machinery, equipment, land, and other facilities reported excess for sale... interests subject to reversion. (10) Easements. (11) Property purchased in whole or in part with Federal...

  1. 42 CFR 455.101 - Definitions.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ..., XVIII, or XX of the Act. This includes: (a) Any hospital, skilled nursing facility, home health agency... established under title V or title XX of the Act. Fiscal agent means a contractor that processes or pays...

  2. Cape Canaveral Air Force Station, Launch Complex 39, The Solid ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    Cape Canaveral Air Force Station, Launch Complex 39, The Solid Rocket Booster Assembly and Refurbishment Facility Manufacturing Building, Southeast corner of Schwartz Road and Contractors Road, Cape Canaveral, Brevard County, FL

  3. Site Environmental Report for 2016 Sandia National Laboratories California.

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Larsen, Barbara L.

    Sandia National Laboratories, California (SNL/CA) is a Department of Energy (DOE) facility. The management and operations of the facility are under a contract with the DOE’s National Nuclear Security Administration (NNSA). On May 1, 2017, the name of the management and operating contractor changed from Sandia Corporation to National Technology and Engineering Solutions of Sandia, LLC (NTESS). The DOE, NNSA, Sandia Field Office administers the contract and oversees contractor operations at the site. This Site Environmental Report for 2016 was prepared in accordance with DOE Order 231.1B, Environment, Safety and Health Reporting (DOE 2012). The report provides a summary ofmore » environmental monitoring information and compliance activities that occurred at SNL/CA during calendar year 2016, unless noted otherwise. General site and environmental program information is also included.« less

  4. KSC Headquarters Building Groundbreaking Ceremony

    NASA Image and Video Library

    2014-10-07

    Groundbreaking for the new Central Campus took place in the Industrial Area at NASA's Kennedy Space Center in Florida. Digging in with shovels during the groundbreaking ceremony, are Dan Tweed, associate director for Facilities at Kennedy Steve Belflower, vice president of HuntonBrady Architects of Orlando Nancy Bray, director of Kennedy's Center Operations Directorate Kennedy Center Director Bob Cabana Kirk Hazen, southeast district manager and vice president of Hensel Phelps, the construction contractor and Kelvin Manning, Kennedy's associate director. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees.

  5. Defense Medical Human Resources System-internet (DMHRSi): A Case Study on Compliance and Accuracy

    DTIC Science & Technology

    2009-06-02

    including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations ...military, contractor operated facilities. The hospital also houses the second oldest Family Practice Residency in the Army (DeWitt, 2008). The...collection and analysis of financial, workload, and personnel data within the organization. The MHS utilizes information managemen * systems like the

  6. A Study of Facilities and Infrastructure Planning, Prioritization, and Assessment at Federal Security Laboratories

    DTIC Science & Technology

    2012-11-01

    Research , Development, Test , and Evaluation (RDT&E) Appropriations The RDT&E appropriation consists of the mission program budgets for all... research , development, test and evaluation work performed by contractors and government installations and includes an installations and activities budget...than $4,000,000. 9 f. Research , Development, Test , and Evaluation Appropriations The Research , Development, Test , and Evaluation (RDT&E

  7. Final Report: Contractor Readiness Assessment (CRA) for TREAT Fuel Movement and Control Rod Drives Isolation

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Rowsell, David Leon

    This report documents the Contractor Readiness Assessment (CRA) for TREAT Fuel Movement and Control Rod Drives Isolation. The review followed the approved Plan of Action (POA) and Implementation Plan (IP) using the identified core requirements. The activity was limited scope focusing on the control rod drives functional isolation and fuel element movement. The purpose of this review is to ensure the facility's readiness to move fuel elements thus supporting inspection and functionally isolate the control rod drives to maintain the required shutdown margin.

  8. Space Life Sciences Lab

    NASA Image and Video Library

    2003-10-09

    The Space Life Sciences Lab (SLSL), formerly known as the Space Experiment Research and Processing Laboratory (SERPL), is a state-of-the-art facility built for ISS biotechnology research. Developed as a partnership between NASA-KSC and the State of Florida, NASA’s life sciences contractor is the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA-sponsored research. About 20 percent of the facility will be available for use by Florida’s university researchers through the Florida Space Research Institute.

  9. 48 CFR 52.222-21 - Prohibition of segregated facilities.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... rest rooms or necessary dressing or sleeping areas provided to assure privacy between the sexes. (b... Contractor agrees that a breach of this clause is a violation of the Equal Opportunity clause in this...

  10. U.S. Army Modernizes Munitions Plants

    ERIC Educational Resources Information Center

    Environmental Science and Technology, 1972

    1972-01-01

    Headquartered at Joliet, Illinois, the Army Ammunition Procurement and Supply Agency aims to mechanize and clean up its manufacturing facilities. Six go-co (government owned - contractor operated) plants involved in the modernization program are described. (BL)

  11. 41 CFR 50-204.34 - AEC licensees-AEC contractors operating AEC plants and facilities-AEC agreement State licensees...

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... Alabama, Arkansas, California, Kansas, Kentucky, Florida, Mississippi, New Hampshire, New York, North..., Florida, Mississippi, New Hampshire, New York, North Carolina, Texas, Tennessee, Oregon, Idaho, Arizona...

  12. 41 CFR 50-204.34 - AEC licensees-AEC contractors operating AEC plants and facilities-AEC agreement State licensees...

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... Alabama, Arkansas, California, Kansas, Kentucky, Florida, Mississippi, New Hampshire, New York, North..., Florida, Mississippi, New Hampshire, New York, North Carolina, Texas, Tennessee, Oregon, Idaho, Arizona...

  13. 48 CFR 952.223-78 - Sustainable acquisition program.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... activities with and submit required reports through the Environmental Sustainability Coordinator or... Prime Contractor's Environmental Sustainability Coordinator at the supported facility. The Subcontractor... reports through the Environmental Sustainability Coordinator or equivalent position. Reporting under this...

  14. 48 CFR 952.223-78 - Sustainable acquisition program.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... activities with and submit required reports through the Environmental Sustainability Coordinator or... Prime Contractor's Environmental Sustainability Coordinator at the supported facility. The Subcontractor... reports through the Environmental Sustainability Coordinator or equivalent position. Reporting under this...

  15. 48 CFR 952.223-78 - Sustainable acquisition program.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... activities with and submit required reports through the Environmental Sustainability Coordinator or... Prime Contractor's Environmental Sustainability Coordinator at the supported facility. The Subcontractor... reports through the Environmental Sustainability Coordinator or equivalent position. Reporting under this...

  16. 48 CFR 952.223-78 - Sustainable acquisition program.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... activities with and submit required reports through the Environmental Sustainability Coordinator or... Prime Contractor's Environmental Sustainability Coordinator at the supported facility. The Subcontractor... reports through the Environmental Sustainability Coordinator or equivalent position. Reporting under this...

  17. KENNEDY SPACE CENTER, FLA. - Employees check out the new chamber facilities of the Space Life Sciences Lab (SLSL), formerly known as the Space Experiment Research and Processing Laboratory (SERPL). From left are Ray Wheeler, with NASA; Debbie Wells and Larry Burns, with Dynamac; A.O. Rule, president of Environmental Growth Chambers, Inc. (ECG); Neil Yorio, with Dynamac; and John Wiezchowski, with ECG. The SLSL is a state-of-the-art facility being built for ISS biotechnology research. Developed as a partnership between NASA-KSC and the State of Florida, NASA’s life sciences contractor will be the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA-sponsored research. About 20 percent of the facility will be available for use by Florida’s university researchers through the Florida Space Research Institute.

    NASA Image and Video Library

    2003-09-10

    KENNEDY SPACE CENTER, FLA. - Employees check out the new chamber facilities of the Space Life Sciences Lab (SLSL), formerly known as the Space Experiment Research and Processing Laboratory (SERPL). From left are Ray Wheeler, with NASA; Debbie Wells and Larry Burns, with Dynamac; A.O. Rule, president of Environmental Growth Chambers, Inc. (ECG); Neil Yorio, with Dynamac; and John Wiezchowski, with ECG. The SLSL is a state-of-the-art facility being built for ISS biotechnology research. Developed as a partnership between NASA-KSC and the State of Florida, NASA’s life sciences contractor will be the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA-sponsored research. About 20 percent of the facility will be available for use by Florida’s university researchers through the Florida Space Research Institute.

  18. 48 CFR 870.112 - Telecommunications equipment.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... facility). (b) The Telecommunications Support Service must review and approve the descriptive literature... delivery or installation by the contractor. Promptly upon receipt of the descriptive literature... received, including descriptive literature and pertinent letters, and the comments and recommendations of...

  19. 48 CFR 870.112 - Telecommunications equipment.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... facility). (b) The Telecommunications Support Service must review and approve the descriptive literature... delivery or installation by the contractor. Promptly upon receipt of the descriptive literature... received, including descriptive literature and pertinent letters, and the comments and recommendations of...

  20. 48 CFR 870.112 - Telecommunications equipment.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... facility). (b) The Telecommunications Support Service must review and approve the descriptive literature... delivery or installation by the contractor. Promptly upon receipt of the descriptive literature... received, including descriptive literature and pertinent letters, and the comments and recommendations of...

  1. Get More for Your Maintenance Dollar through Contracting.

    ERIC Educational Resources Information Center

    Donahue, Ron

    1983-01-01

    The use of contractors for the performance of maintenance duties in parks and recreational facilities is recommended as a legitimate tool to improve productivity or upgrade quality. An example of the use of contracts is provided. (CJ)

  2. KSC-2014-4213

    NASA Image and Video Library

    2014-10-07

    CAPE CANAVERAL, Fla. – Groundbreaking for the new Central Campus took place in the Industrial Area at NASA's Kennedy Space Center in Florida. Digging in with shovels during the groundbreaking ceremony, are Dan Tweed, associate director for Facilities at Kennedy Steve Belflower, vice president of HuntonBrady Architects of Orlando Nancy Bray, director of Kennedy's Center Operations Directorate Kennedy Center Director Bob Cabana Kirk Hazen, southeast district manager and vice president of Hensel Phelps, the construction contractor and Kelvin Manning, Kennedy's associate director. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees. Photo credit: NASA/Kim Shiflett

  3. KSC-2014-4212

    NASA Image and Video Library

    2014-10-07

    CAPE CANAVERAL, Fla. – Groundbreaking for the new Central Campus took place in the Industrial Area at NASA's Kennedy Space Center in Florida. Digging in with shovels during the groundbreaking ceremony, are Dan Tweed, associate director for Facilities at Kennedy Steve Belflower, vice president of HuntonBrady Architects of Orlando Nancy Bray, director of Kennedy's Center Operations Directorate Kennedy Center Director Bob Cabana Kirk Hazen, southeast district manager and vice president of Hensel Phelps, the construction contractor and Kelvin Manning, Kennedy's associate director. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees. Photo credit: NASA/Kim Shiflett

  4. Installation Restoration Program Records Search for Kingsley Field, Oregon.

    DTIC Science & Technology

    1982-06-01

    Hazardous Assesment Rating Methodology (HARM), is now used for all Air Force IRP studies. To maintain consistency, AFESC had their on-call contractors review...Installation History D. Industrial Facilities E. POL Storage Tanks F. Abandoned Tanks G. Oil/Water Separators :" H. Site Hazard Rating Methodology I. Site...and implementing regulations. The pur- pose of DOD policy is to control the migration of hazardous material contaminants from DOD installations. 3

  5. Iraqi Army Facilities Under the Iraq Security Forces Fund, Diyanah and Debecha, Iraq

    DTIC Science & Technology

    2008-01-17

    reinforcement bars and cast each building’s roof flatwork and horizontal beams to complete the structural aspects of the roof system . Steel header...included a mix of new construction and renovation of existing structures and facilities. The Statement of Requirements and Specifications provided...that renovation of existing structures , when possible, was preferred. In addition, the United States government encouraged the contractor to use

  6. 7 CFR 4279.281 - Conditions precedent to issuance of loan note guarantee.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... facility and to provide the required security. For example, when a site is for major structures for utility... certify to the lender that all laborers and mechanics employed by contractors or subcontractors in the...

  7. 7 CFR 4279.281 - Conditions precedent to issuance of loan note guarantee.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... facility and to provide the required security. For example, when a site is for major structures for utility... certify to the lender that all laborers and mechanics employed by contractors or subcontractors in the...

  8. 7 CFR 4279.281 - Conditions precedent to issuance of loan note guarantee.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... facility and to provide the required security. For example, when a site is for major structures for utility... certify to the lender that all laborers and mechanics employed by contractors or subcontractors in the...

  9. 48 CFR 970.2301-1 - Policy.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 970.2301-1 Federal Acquisition Regulations System DEPARTMENT OF ENERGY AGENCY SUPPLEMENTARY REGULATIONS DOE MANAGEMENT AND OPERATING CONTRACTS Environment, Energy and Water Efficiency, Renewable Energy... http://www.hss.energy.gov/pp/epp. Contractors operating DOE facilities shall comply with the...

  10. 18 CFR 50.5 - Pre-filing procedures.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... ELECTRIC TRANSMISSION FACILITIES § 50.5 Pre-filing procedures. (a) Introduction. Any applicant seeking a... consultations, project engineering, route planning, environmental and engineering contractor engagement... proceeding. This description also must include the identification of the environmental and engineering firms...

  11. Pure Air`s Bailly scrubber: A four-year retrospective

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Manavi, G.B.; Vymazal, D.C.; Sarkus, T.A.

    1997-12-31

    Pure Air`s Advanced Flue Gas Desulfurization (AFGD) Clean Coal Project has completed four highly successful years of operation at NIPSCO`s Bailly Station. As part of their program, Pure Air has concluded a six-part study of system performance. This paper summarizes the results of the demonstration program, including AFGD performance on coals ranging from 2.0--2.4% sulfur. The paper highlights novel aspects of the Bailly facility, including pulverized limestone injection, air rotary sparger for oxidation, wastewater evaporation system and the production of PowerChip{reg_sign} gypsum. Operations and maintenance which have led to the facility`s notable 99.47% availability record are also discussed. A projectmore » company, Pure Air on the Lake Limited Partnership, owns the AFGD facility. Pure Air was the turn key contractor and Air Products and Chemicals, Inc. is the operator of the AFGD system.« less

  12. KSC-04PD-0003

    NASA Technical Reports Server (NTRS)

    2004-01-01

    KENNEDY SPACE CENTER, FLA. -- Sharon Edney, with Dynamac Corp., checks the growth of radishes being grown hydroponically for study in the Space Life Sciences Lab. The 100,000 square-foot facility houses labs for NASAs ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASAs Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASAs Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

  13. KSC-04PD-0002

    NASA Technical Reports Server (NTRS)

    2004-01-01

    KENNEDY SPACE CENTER, FLA. -- Sharon Edney, with Dynamac Corp., checks the roots of green onions being grown hydroponically for study in the Space Life Sciences Lab. The 100,000 square-foot facility houses labs for NASAs ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASAs Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASAs Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

  14. KSC-04PD-0001

    NASA Technical Reports Server (NTRS)

    2004-01-01

    KENNEDY SPACE CENTER, FLA. -- Sharon Edney, with Dynamac Corp., measures photosynthesis on Bibb lettuce being grown hydroponically for study in the Space Life Sciences Lab. The 100,000 square-foot facility houses labs for NASAs ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASAs Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASAs Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

  15. One of the criteria for selecting a contractor for high-rise construction

    NASA Astrophysics Data System (ADS)

    Tuskaeva, Zalina; Tagirov, Timur

    2018-03-01

    The mechanisms for management of the building complex used and proposed to date do not always provide the required result in the assessment of the construction organization facilities. Therefore, the development of new effective methods for such an assessment is an urgent task especially in questions related to high-rise construction. The article formally sets the task of assessing the technical facilities of a construction organization. Due to the use of expert methods, the weighted values of the coefficients of local indicators for technical facilities are identified

  16. Marshall Space Flight Center Test Capabilities

    NASA Technical Reports Server (NTRS)

    Hamilton, Jeffrey T.

    2005-01-01

    The Test Laboratory at NASA's Marshall Space Flight Center has over 50 facilities across 400+ acres inside a secure, fenced facility. The entire Center is located inside the boundaries of Redstone Arsenal, a 40,000 acre military reservation. About 150 Government and 250 contractor personnel operate facilities capable of all types of propulsion and structural testing, from small components to engine systems and structural strength, structural dynamic and environmental testing. We have tremendous engineering expertise in research, evaluation, analysis, design and development, and test of space transportation systems, subsystems, and components.

  17. Space Mechanisms Lessons Learned Study. Volume 2: Literature Review

    NASA Technical Reports Server (NTRS)

    Shapiro, Wilbur; Murray, Frank; Howarth, Roy; Fusaro, Robert

    1995-01-01

    Hundreds of satellites have been launched to date. Some have operated extremely well and others have not. In order to learn from past operating experiences, a study was conducted to determine the conditions under which space mechanisms (mechanically moving components) have previously worked or failed. The study consisted of an extensive literature review that included both government contractor reports and technical journals, communication and visits (when necessary) to the various NASA and DOD centers and their designated contractors (this included contact with project managers of current and prior NASA satellite programs as well as their industry counterparts), requests for unpublished information to NASA and industry, and a mail survey designed to acquire specific mechanism experience. The information obtained has been organized into two volumes. Volume 1 provides a summary of the lesson learned, the results of a needs analysis, responses to the mail survey, a listing of experts, a description of some available facilities, and a compilation of references. Volume 2 contains a compilation of the literature review synopsis.

  18. Space Mechanisms Lessons Learned Study. Volume 1: Summary

    NASA Technical Reports Server (NTRS)

    Shapiro, Wilbur; Murray, Frank; Howarth, Roy; Fusaro, Robert

    1995-01-01

    Hundreds of satellites have been launched to date. Some have operated extremely well and others have not. In order to learn from past operating experiences, a study was conducted to determine the conditions under which space mechanisms (mechanically moving components) have previously worked or failed. The study consisted of: (1) an extensive literature review that included both government contractor reports and technical journals; (2) communication and visits (when necessary) to the various NASA and DOD centers and their designated contractors (this included contact with project managers of current and prior NASA satellite programs as well as their industry counterparts); (3) requests for unpublished information to NASA and industry; and (4) a mail survey designed to acquire specific mechanism experience. The information obtained has been organized into two volumes. Volume 1 provides a summary of the lessons learned, the results of a needs analysis, responses to the mail survey, a listing of experts, a description of some available facilities and a compilation of references. Volume 2 contains a compilation of the literature review synopsis.

  19. A Study of Facilities and Infrastructure Planning, Prioritization, and Assessment at Federal Security Laboratories (Revised)

    DTIC Science & Technology

    2013-02-01

    or funds authorized under Section 219(a) for projects costing no more than $4M. Research , Development, Test , and Evaluation (RDT&E) Appropriations...The RDT&E appropriation consists of the mission program budgets for all research , development, test and evaluation work performed by contractors...carry out an unspecified minor military construction project costing not more than $4,000,000. 9 f. Research , Development, Test , and Evaluation

  20. Looking to the Future.

    ERIC Educational Resources Information Center

    College Planning & Management, 1997

    1997-01-01

    Ten possible trends on college campuses are examined. They include distance learning; rehabilitation of existing buildings; use of construction management firms; salaries for facilities directors; virtual universities; off-site garages; outside residence hall contractors; classrooms in residential buildings; and smart cards for entry and…

  1. 24 CFR 200.215 - Definitions.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... Officer. (See § 200.224) (e) Principal. (1) An individual, joint venture, partnership, corporation, trust... a project as sponsor, owner, prime contractor, Turnkey Developer, management agent, nursing home... or contract of assistance; (2) a hospital, group practice facility or nursing home; (3) cooperative...

  2. 10 CFR 830.1 - Scope.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 10 Energy 4 2013-01-01 2013-01-01 false Scope. 830.1 Section 830.1 Energy DEPARTMENT OF ENERGY NUCLEAR SAFETY MANAGEMENT § 830.1 Scope. This part governs the conduct of DOE contractors, DOE personnel... affect, the safety of DOE nuclear facilities. ...

  3. 48 CFR 1830.7002-1 - Definitions.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... GENERAL CONTRACTING REQUIREMENTS COST ACCOUNTING STANDARDS ADMINISTRATION Facilities Capital Employed for.... 97); or (2) The time-weighted average of such rates for each cost accounting period during which the... calculated amount considered invested by the contractor during the cost accounting period to construct...

  4. 10 CFR 830.1 - Scope.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 10 Energy 4 2010-01-01 2010-01-01 false Scope. 830.1 Section 830.1 Energy DEPARTMENT OF ENERGY NUCLEAR SAFETY MANAGEMENT § 830.1 Scope. This part governs the conduct of DOE contractors, DOE personnel... affect, the safety of DOE nuclear facilities. ...

  5. 10 CFR 830.1 - Scope.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 10 Energy 4 2011-01-01 2011-01-01 false Scope. 830.1 Section 830.1 Energy DEPARTMENT OF ENERGY NUCLEAR SAFETY MANAGEMENT § 830.1 Scope. This part governs the conduct of DOE contractors, DOE personnel... affect, the safety of DOE nuclear facilities. ...

  6. KENNEDY SPACE CENTER, FLA. -- In the Space Life Sciences Lab, Lanfang Levine, with Dynamac Corp., transfers material into a sample bottle for analysis. She is standing in front of new equipment in the lab that will provide gas chromatography and mass spectrometry. The equipment will enable analysis of volatile compounds, such as from plants. The 100,000 square-foot facility houses labs for NASA’s ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASA’s Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASA’s Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

    NASA Image and Video Library

    2004-01-05

    KENNEDY SPACE CENTER, FLA. -- In the Space Life Sciences Lab, Lanfang Levine, with Dynamac Corp., transfers material into a sample bottle for analysis. She is standing in front of new equipment in the lab that will provide gas chromatography and mass spectrometry. The equipment will enable analysis of volatile compounds, such as from plants. The 100,000 square-foot facility houses labs for NASA’s ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASA’s Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASA’s Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

  7. KENNEDY SPACE CENTER, FLA. -- In the Space Life Sciences (SLS) Lab, Jan Bauer, with Dynamac Corp., places samples of onion tissue in the elemental analyzer, which analyzes for carbon, hydrogen, nitrogen and sulfur. The 100,000 square-foot SLS houses labs for NASA’s ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASA’s Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASA’s Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

    NASA Image and Video Library

    2004-01-05

    KENNEDY SPACE CENTER, FLA. -- In the Space Life Sciences (SLS) Lab, Jan Bauer, with Dynamac Corp., places samples of onion tissue in the elemental analyzer, which analyzes for carbon, hydrogen, nitrogen and sulfur. The 100,000 square-foot SLS houses labs for NASA’s ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASA’s Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASA’s Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

  8. KENNEDY SPACE CENTER, FLA. -- In the Space Life Sciences (SLS) Lab, Jan Bauer, with Dynamac Corp., weighs samples of onion tissue for processing in the elemental analyzer behind it. The equipment analyzes for carbon, hydrogen, nitrogen and sulfur. The 100,000 square-foot SLS houses labs for NASA’s ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASA’s Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASA’s Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

    NASA Image and Video Library

    2004-01-05

    KENNEDY SPACE CENTER, FLA. -- In the Space Life Sciences (SLS) Lab, Jan Bauer, with Dynamac Corp., weighs samples of onion tissue for processing in the elemental analyzer behind it. The equipment analyzes for carbon, hydrogen, nitrogen and sulfur. The 100,000 square-foot SLS houses labs for NASA’s ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASA’s Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASA’s Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

  9. Technical publications of the NASA Wallops Flight Facility, 1980 through 1983

    NASA Technical Reports Server (NTRS)

    Foster, J. N.

    1984-01-01

    This bibliography lists the publications sponsored by the NASA Wallops Flight Center/NASA Goddard Space Flight Center, Wallops Flight Facility during the period 1980 through 1983. The compilation contains citations listed by type of publication; i.e., NASA formal report, NASA contractor report, journal article, or presentation; by contract/grant number; and by accession number. Oceanography, astrophysics, artificial satellites, fluid mechanics, and sea ice are among the topics covered.

  10. Facilities Capital as a Factor in Contract Pricing,

    DTIC Science & Technology

    1985-05-01

    resulting from new investment. Investments must provide contractors with a rate of return competitive with what they can earn on investments elsewhere...DoD’s profit objective rate (profit objective as a percentage of cost objective) is determined by the level of facilities capital employed, the mix of...business base were analyzed. These sources serve as independent checks on each other and present a consistent picture of what has occurred. In each

  11. 32 CFR 162.2 - Applicability and scope.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... National Defense Department of Defense OFFICE OF THE SECRETARY OF DEFENSE DEFENSE CONTRACTING PRODUCTIVITY... the Secretary of Defense (OSD); the Military Departments; Chairman, Joint Chiefs of Staff and the...-owned, contractor-operated (GOCO) facilities are limited to those for which the Department of Defense...

  12. 32 CFR 162.2 - Applicability and scope.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... National Defense Department of Defense OFFICE OF THE SECRETARY OF DEFENSE DEFENSE CONTRACTING PRODUCTIVITY... the Secretary of Defense (OSD); the Military Departments; Chairman, Joint Chiefs of Staff and the...-owned, contractor-operated (GOCO) facilities are limited to those for which the Department of Defense...

  13. 32 CFR 162.2 - Applicability and scope.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... National Defense Department of Defense OFFICE OF THE SECRETARY OF DEFENSE DEFENSE CONTRACTING PRODUCTIVITY... the Secretary of Defense (OSD); the Military Departments; Chairman, Joint Chiefs of Staff and the...-owned, contractor-operated (GOCO) facilities are limited to those for which the Department of Defense...

  14. 32 CFR 162.2 - Applicability and scope.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... National Defense Department of Defense OFFICE OF THE SECRETARY OF DEFENSE DEFENSE CONTRACTING PRODUCTIVITY... the Secretary of Defense (OSD); the Military Departments; Chairman, Joint Chiefs of Staff and the...-owned, contractor-operated (GOCO) facilities are limited to those for which the Department of Defense...

  15. Materials Evaluation in the Tri-Service Thermal Radiation Test Facility.

    DTIC Science & Technology

    1984-06-20

    CONTRACTORS (Continued) Science Applications Intl Corp Science Applications. Inc ATTN: S. Binninger ATTN: Tech Library Science Applications Intl Corp...Tech, Inc ATTN: Library Science Applications, Inc ATTN: Tech Library TRW Electronics & Defense Sector ATTN: h. Plows ATTN: B. Sussholtz ATTN: J

  16. 32 CFR 2001.46 - Transmission.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... an attention line. The following exceptions apply: (i) If the classified information is an internal... Class Mail. However, Confidential information shall not be transmitted to government contractor facilities via first class mail. When first class mail is used, the envelope or outer wrapper shall be marked...

  17. Fiscal year 1977 scientific and technical reports, articles, papers, and presentations

    NASA Technical Reports Server (NTRS)

    White, O. L. (Compiler)

    1977-01-01

    This bibliography lists 78 NASA technical memoranda, notes, papers, and reports presented by Marshall Space Flight Center personnel in FY 1977. In addition, 525 papers by contractors to that facility are cited along with 129 papers cleared for presentation.

  18. 48 CFR 242.7400 - General.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... Contractor Facilities 242.7400 General. (a) Program managers may conclude that they need technical... manager may assign technical representatives under the procedures in 242.7401. (b) A technical representative is a representative of a DoD program, project, or system office performing non-CAS technical...

  19. 48 CFR 242.7400 - General.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... Contractor Facilities 242.7400 General. (a) Program managers may conclude that they need technical... manager may assign technical representatives under the procedures in 242.7401. (b) A technical representative is a representative of a DoD program, project, or system office performing non-CAS technical...

  20. 48 CFR 9.403 - Definitions.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ...— Affiliates. Business concerns, organizations, or individuals are affiliates of each other if, directly or... management or ownership, identity of interests among family members, shared facilities and equipment, common.... Contractor means any individual or other legal entity that— (1) Directly or indirectly (e.g., through an...

  1. 48 CFR 9.403 - Definitions.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ...— Affiliates. Business concerns, organizations, or individuals are affiliates of each other if, directly or... management or ownership, identity of interests among family members, shared facilities and equipment, common.... Contractor means any individual or other legal entity that— (1) Directly or indirectly (e.g., through an...

  2. 48 CFR 9.403 - Definitions.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ...— Affiliates. Business concerns, organizations, or individuals are affiliates of each other if, directly or... management or ownership, identity of interests among family members, shared facilities and equipment, common.... Contractor means any individual or other legal entity that— (1) Directly or indirectly (e.g., through an...

  3. 48 CFR 9.403 - Definitions.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ...— Affiliates. Business concerns, organizations, or individuals are affiliates of each other if, directly or... management or ownership, identity of interests among family members, shared facilities and equipment, common.... Contractor means any individual or other legal entity that— (1) Directly or indirectly (e.g., through an...

  4. 48 CFR 9.403 - Definitions.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ...— Affiliates. Business concerns, organizations, or individuals are affiliates of each other if, directly or... management or ownership, identity of interests among family members, shared facilities and equipment, common.... Contractor means any individual or other legal entity that— (1) Directly or indirectly (e.g., through an...

  5. Balancing quality customer service with financial returns in privatized park services

    Treesearch

    Glen D. Alexander

    1998-01-01

    The privatization of public facilities continues to be an issue that impacts the bottom line of many public agencies. Choosing a concessionaire or contractor involves much more that selecting the highest bidder. Examining all the variables is a necessity.

  6. 42 CFR 9.9 - Facility staffing.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... provide appropriate care to the chimpanzees at all times, including evenings, weekends, and holidays. The... socialization techniques. In addition, the Director must have management and administrative experience; (d) The... chimpanzees is desirable; (e) The remaining staff, which may include part-time, full-time, or contractor...

  7. Comprehensive integrated planning: A process for the Oak Ridge Reservation, Oak Ridge, Tennessee

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    NONE

    1998-05-01

    The Oak Ridge Comprehensive Integrated Plan is intended to assist the US Department of Energy (DOE) and contractor personnel in implementing a comprehensive integrated planning process consistent with DOE Order 430.1, Life Cycle Asset Management and Oak Ridge Operations Order 430. DOE contractors are charged with developing and producing the Comprehensive Integrated Plan, which serves as a summary document, providing information from other planning efforts regarding vision statements, missions, contextual conditions, resources and facilities, decision processes, and stakeholder involvement. The Comprehensive Integrated Plan is a planning reference that identifies primary issues regarding major changes in land and facility use andmore » serves all programs and functions on-site as well as the Oak Ridge Operations Office and DOE Headquarters. The Oak Ridge Reservation is a valuable national resource and is managed on the basis of the principles of ecosystem management and sustainable development and how mission, economic, ecological, social, and cultural factors are used to guide land- and facility-use decisions. The long-term goals of the comprehensive integrated planning process, in priority order, are to support DOE critical missions and to stimulate the economy while maintaining a quality environment.« less

  8. When a Home is Not a Home: MultiDrug-Resistant Organism (MDRO) Colonization and Environmental Contamination in 28 Nursing Homes (NHs)

    PubMed Central

    McKinnell, James A; Miller, Loren; Singh, Raveena D; Mendez, Job; Franco, Ryan; Gussin, Gabrielle; Chang, Justin; Dutciuc, Tabitha D; Saavedra, Raheeb; Kleinman, Ken; Peterson, Ellena M; Evans, Kaye D; Heim, Lauren; Miner, Aaron; Estevez, Marlene; Custodio, Harold; Yamaguchi, Stacey; Nguyen, Jenny; Varasteh, Alex; Launer, Bryn; Agrawal, Shalini; Tjoa, Thomas; He, Jiayi; Park, Steven; Tam, Steven; Gohil, Shruti K; Stone, Nimalie D; Steinberg, Karl; Montgomery, Jocelyn; Beecham, Nancy; Huang, Susan S

    2017-01-01

    Abstract Background The majority of healthcare-associated infections due to MDROs occur in the post-discharge setting. Understanding MDRO spread and containment in NHs can help identify infection prevention activities needed to care for vulnerable patients in a medical home setting. Methods We conducted a baseline point prevalence study of MDRO colonization in residents of 28 Southern California NHs participating in a decolonization trial. In Fall 2016, residents were randomly sampled to obtain a set of 50 nares and skin (axilla/groin) swabs from each NH. Nasal swabs were processed for MRSA and skin swabs were processed for MRSA, VRE, ESBL, and CRE. In addition, environmental swabs were collected from high touch objects in resident rooms (bedrail, call button/TV remote, door knobs, light switch, bathroom) and common areas (nursing station, table, chair, railing, and drinking fountain). Results A total of 2,797 body swabs were obtained from 1400 residents. Overall, 48.6% (N = 680) of residents harbored MDROs. MRSA was found in 37% of residents (29.5% nares, 24.4% skin), followed by ESBL in 16% (Table 1). Resident MDRO status was only known for 11% of MRSA (59/518), 18% ESBL (40/228), 4% VRE (4/99), and none of the CRE (0/13) carriers. Colonization did not differ between long stay (48.8%, 534/1094) vs. post-acute (47.7%, 146/306) residents (P = NS), but bedbound residents were more likely to be MDRO colonized (58.7%, 182/310) vs. ambulatory residents (45.7%, 497/1088, P < 0.001). A total of 560 environmental swabs were obtained with 93% of common areas and 74% of resident rooms having an MDRO+ object with an average of 2.5 and 1.9 objects found to be contaminated (Table 2). Conclusion One in two NH residents are colonized with MDROs, which is largely unknown to the facility. MDRO carriage is associated with total care needs, but not long stay status. Environmental contamination in resident rooms and common areas is common. The burden of MDRO colonization and contamination is sufficiently high that universal strategies to reduce colonization and transmission are warranted. Disclosures J. A. McKinnell, Allergan: Research Contractor, Scientific Advisor and Speaker’s Bureau, Consulting fee, Research support and Speaker honorarium; Achaogen: Research Contractor, Scientific Advisor and Shareholder, Research support; Cempra: Research Contractor and Scientific Advisor, Research support; Theravance: Research Contractor, Research support; Science 37: Research Contractor, Salary; Expert Stewardship, LLC: Board Member and Employee, Salary; Thermo Fisher: Scientific Advisor, Salary; 3M: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; L. Miller, 3M: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; R. D. Singh, Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; 3M: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; J. Mendez, Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; R. Franco, Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; G. Gussin, Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; L’Oreal: Consultant, Consulting fee; J. Chang, Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; 3M: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; T. D. Dutciuc, Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; 3M: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; R. Saavedra, Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; K. Kleinman, Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Molnlycke: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; 3M: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; E. M. Peterson, Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; L. Heim, Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; 3M: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; A. Miner, Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; M. Estevez, Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; 3M: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; H. Custodio, Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; S. Yamaguchi, Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; J. Nguyen, Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; A. Varasteh, Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Sage Product: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; B. Launer, 3M: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; S. Agrawal, Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; T. Tjoa, Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; 3M: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; J. He, Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; 3M: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; S. Park, Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; S. Tam, Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; 3M: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; S. K. Gohil, Sage Products: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; Clorox: Receipt of contributed product, Conducting studies in healthcare facilities that are receiving contributed product; S. S. Huang, Sage Products: Receipt of contributed product, Conducting studies in which participating healthcare facilities are receiving contributed product (no contribution in submitted abstract), Participating healthcare facilities in my studies received contributed product; Xttrium Laboratories: Receipt of contributed product, Conducting studies in which participating healthcare facilities are receiving contributed product (no contribution in submitted abstract), Participating healthcare facilities in my studies received contributed product; Clorox: Receipt of contributed product, Conducting studies in which participating healthcare facilities are receiving contributed product (no contribution in submitted abstract), Participating healthcare facilities in my studies received contributed product; 3M: Receipt of contributed product, Conducting studies in which participating healthcare facilities are receiving contributed product (no contribution in submitted abstract), Participating healthcare facilities in my studies received contributed product; Molnlycke: Receipt of contributed product, Conducting studies in which participating healthcare facilities are receiving contributed product (no contribution in submitted abstract), Participating healthcare facilities in my studies received contributed product

  9. Sharing lessons learned and best practices in deactivation and decommissioning techniques among U.S. Department of Energy contractors

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Lackey, Michael B.; Waisley, Sandra L.; Dusek, Lansing G.

    2007-07-01

    Approximately $153.2 billion of work currently remains in the United States Department of Energy's (DOE's) Office of Environmental Management (EM) life cycle budget for United States projects. Contractors who manage facilities for the DOE have been challenged to identify transformational changes to reduce the life cycle costs and develop a knowledge management system that identifies, disseminates, and tracks the implementation of lessons learned and best practices. At the request of the DOE's EM Office of Engineering and Technology, the Energy Facility Contractors Group (EFCOG) responded to the challenge with formation of the Deactivation and Decommissioning (D and D) and Facilitymore » Engineering (DD/FE) Working Group. Since October 2006, members have already made significant progress in realizing their goals: adding new D and D best practices to the existing EFCOG Best Practices database; participating in lessons learned forums; and contributing to a DOE initiative on identifying technology needs. The group is also participating in a DOE project management initiative to develop implementation guidelines, as well as a DOE radiation protection initiative to institute a more predictable and standardized approach to approving authorized limits and independently verifying cleanup completion at EM sites. Finally, a D and D hotline to provide real-time solutions to D and D challenges is also being launched. (authors)« less

  10. Contracting for Asbestos Abatement: What You Need to Know.

    ERIC Educational Resources Information Center

    Bittle, Edgar H.; McAllister, Jane B.

    1990-01-01

    School districts are required to determine if asbestos-containing materials exist at school facilities and design and implement asbestos abatement. Reviews how to select a contractor, draft the contract, and ensure its proper implementation by complying with the law and avoiding liability. (MLF)

  11. 29 CFR 501.3 - Definitions.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... operation, management, conservation, improvement, or maintenance of such farm and its tools and equipment... operator's own agricultural operation. H-2A Labor Contractor (H-2ALC). Any person who meets the definition...: (1) Substantial continuity of the same business operations; (2) Use of the same facilities; (3...

  12. 32 CFR 644.486 - Disposal of buildings and improvements constructed under emergency plant facilities (EPF) or...

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... which the Government otherwise has no interest, such as a wing, and in which a defense contractor... address of a responsible officer of the using service to join with the DE concerned as a representative of...

  13. 32 CFR 644.486 - Disposal of buildings and improvements constructed under emergency plant facilities (EPF) or...

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... which the Government otherwise has no interest, such as a wing, and in which a defense contractor... address of a responsible officer of the using service to join with the DE concerned as a representative of...

  14. 32 CFR 644.486 - Disposal of buildings and improvements constructed under emergency plant facilities (EPF) or...

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... which the Government otherwise has no interest, such as a wing, and in which a defense contractor... address of a responsible officer of the using service to join with the DE concerned as a representative of...

  15. 32 CFR 644.486 - Disposal of buildings and improvements constructed under emergency plant facilities (EPF) or...

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... which the Government otherwise has no interest, such as a wing, and in which a defense contractor... address of a responsible officer of the using service to join with the DE concerned as a representative of...

  16. New Hires, Building Demolition

    ScienceCinema

    None

    2017-12-09

    Using Recovery Act funding, Department of Energy contractor CH2M HILL Plateau Remediation Company has hired hundreds of new employees to do cleanup work at the Hanford Site, including demolition of dozens of excess facilities.This video was produced by CH2M HILL on Jan. 8, 2010.

  17. 10 CFR 1706.5 - General rules.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... contract is likely to diminish the contractor's capacity to give impartial assistance and advice, or... activities or research related to the Board's oversight of defense nuclear facilities, where the award would... consulting or other contractual arrangements with other persons or entities, the result of which could give...

  18. 10 CFR 1706.5 - General rules.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... contract is likely to diminish the contractor's capacity to give impartial assistance and advice, or... activities or research related to the Board's oversight of defense nuclear facilities, where the award would... consulting or other contractual arrangements with other persons or entities, the result of which could give...

  19. 48 CFR 1337.110-70 - Personnel security processing requirements.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... COMMERCE SPECIAL CATEGORIES OF CONTRACTING SERVICE CONTRACTING Service Contracts-General 1337.110-70... processing for contractors performing services on or within a Department of Commerce facility or through an information technology (IT) system, as required by the Department of Commerce Security Manual and Department...

  20. 48 CFR 1337.110-70 - Personnel security processing requirements.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... COMMERCE SPECIAL CATEGORIES OF CONTRACTING SERVICE CONTRACTING Service Contracts-General 1337.110-70... processing for contractors performing services on or within a Department of Commerce facility or through an information technology (IT) system, as required by the Department of Commerce Security Manual and Department...

  1. Crystal Growth of ZnSe and Related Ternary Compound Semiconductors by Physical Vapor Transport

    NASA Technical Reports Server (NTRS)

    Cushman, Paula P.

    1997-01-01

    Preliminary definition of all of the necessary materials, labor, services, and facilities necessary to provide science requirement definition, initiate hardware development activities, and provide an update flight program proposal consistent with the NRA selection letter. The major tasks identified in this SOW are in the general category of science requirements determination, instrument definition, and updated flight program proposal. The Contractor shall define preliminary management, technical and integration requirements for the program, including improved cost/schedule estimates. The Contractor shall identify new technology requirements, define experiment accommodations and operational requirements and negotiate procurement of any long lead items, if required, with the government.

  2. Crystal Growth of ZnSe and Related Ternary Compound Semiconductors by Physical Vapor Transport

    NASA Technical Reports Server (NTRS)

    Su, Ching-Hua

    1997-01-01

    Preliminary definition of all of the necessary materials, labor, services, and facilities necessary to provide science requirement definition, initiate hardware development activities, and provide an updated flight program proposal consistent with the NRA selection letter. The major tasks identified in this SOW are in the general category of science requirements determination, instrument definition, and updated flight program proposal. The Contractor shall define preliminary management, technical and integration requirements for the program, including improved cost/schedule estimates. The Contractor shall identify new technology requirements, define experiment accommodations and operational requirements and negotiate procurement of any long lead items, if required, with the government.

  3. Evaluation of the US Department of Energy's occupational safety and health program for its government-owned contractor-operated facilities

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Not Available

    The purpose of this report is to present to Secretary of Energy James Watkins the findings and recommendations of the Occupational Safety and Health Administration's (OSHA) evaluation of the Department of Energy's (DOE) programs for worker safety and health at DOE's government-owned contractor-operated (GOCO) nuclear facilities. The OSHA evaluation is based on an intensive and comprehensive review and analysis of DOE's worker safety and health programs including: written programs; safety and health inspection programs; and the adequacy of resource, training, and management controls. The evaluation began on April 10, 1990 and involved over three staff years before its conclusion. Themore » evaluation was initiated by former Secretary of Labor Elizabeth Dole in response to Secretary of Energy James Watkins' request that OSHA assist him in determining the actions needed to assure that DOE has an exemplary safety and health program in place at its GOCOs. 6 figs.« less

  4. Methodology to Estimate the Quantity, Composition, and ...

    EPA Pesticide Factsheets

    This report, Methodology to Estimate the Quantity, Composition and Management of Construction and Demolition Debris in the US, was developed to expand access to data on CDD in the US and to support research on CDD and sustainable materials management. Since past US EPA CDD estimates have been limited to building-related CDD, a goal in the development of this methodology was to use data originating from CDD facilities and contractors to better capture the current picture of total CDD management, including materials from roads, bridges and infrastructure. This report, Methodology to Estimate the Quantity, Composition and Management of Construction and Demolition Debris in the US, was developed to expand access to data on CDD in the US and to support research on CDD and sustainable materials management. Since past US EPA CDD estimates have been limited to building-related CDD, a goal in the development of this methodology was to use data originating from CDD facilities and contractors to better capture the current picture of total CDD management, including materials from roads, bridges and infrastructure.

  5. 77 FR 3787 - Notice of Submission of Proposed Information Collection to OMB; Office of Hospital Facilities...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-01-25

    ...The proposed information collection requirement described below has been submitted to the Office of Management and Budget (OMB) for review, as required by the Paperwork Reduction Act. The Department is soliciting public comments on the subject proposal. This information is collected from OHF staff, mortgagees, mortgagors, contractors and agents to manage and monitor the application, procedure, project administration and initial/final endorsement of projects undertaken by Office of Hospital Facilities.

  6. KENNEDY SPACE CENTER, FLA. - Frank T. Brogan, president of the Florida Atlantic University, speaks at a dedication and ribbon-cutting ceremony for the Space Life Sciences Lab hosted by NASA-Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASA’s Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

    NASA Image and Video Library

    2003-11-19

    KENNEDY SPACE CENTER, FLA. - Frank T. Brogan, president of the Florida Atlantic University, speaks at a dedication and ribbon-cutting ceremony for the Space Life Sciences Lab hosted by NASA-Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASA’s Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

  7. KENNEDY SPACE CENTER, FLA. - Dignitaries, invited guests, space center employees, and the media gather for a dedication and ribbon-cutting ceremony for the Space Life Sciences Lab hosted by NASA-Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASA’s Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

    NASA Image and Video Library

    2003-11-19

    KENNEDY SPACE CENTER, FLA. - Dignitaries, invited guests, space center employees, and the media gather for a dedication and ribbon-cutting ceremony for the Space Life Sciences Lab hosted by NASA-Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASA’s Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

  8. KENNEDY SPACE CENTER, FLA. - Capt. Winston Scott, executive director of the Florida Space Authority, speaks at a dedication and ribbon-cutting ceremony for the Space Life Sciences Lab hosted by NASA-Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASA’s Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

    NASA Image and Video Library

    2003-11-19

    KENNEDY SPACE CENTER, FLA. - Capt. Winston Scott, executive director of the Florida Space Authority, speaks at a dedication and ribbon-cutting ceremony for the Space Life Sciences Lab hosted by NASA-Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASA’s Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

  9. High-Lift Flight Tunnel - Phase II Report. Phase 2 Report

    NASA Technical Reports Server (NTRS)

    Lofftus, David; Lund, Thomas; Rote, Donald; Bushnell, Dennis M. (Technical Monitor)

    2000-01-01

    The High-Lift Flight Tunnel (HiLiFT) concept is a revolutionary approach to aerodynamic ground testing. This concept utilizes magnetic levitation and linear motors to propel an aerodynamic model through a tube containing a quiescent test medium. This medium (nitrogen) is cryogenic and pressurized to achieve full flight Reynolds numbers higher than any existing ground test facility world-wide for the range of 0.05 to 0.50 Mach. The results of the Phase II study provide excellent assurance that the HiLiFT concept will provide a valuable low-speed, high Reynolds number ground test facility. The design studies concluded that the HiLiFT facility is feasible to build and operate and the analytical studies revealed no insurmountable difficulties to realizing a practical high Reynolds number ground test facility. It was determined that a national HiLiFT facility, including development, would cost approximately $400M and could be operational by 2013 if fully funded. Study participants included National Aeronautics and Space Administration Langley Research Center as the Program Manager and MSE Technology Applications, Inc., (MSE) of Butte, Montana as the prime contractor and study integrator. MSE#s subcontractors included the University of Texas at Arlington for aerodynamic analyses and the Argonne National Laboratory for magnetic levitation and linear motor technology support.

  10. Skin and surface lead contamination, hygiene programs, and work practices of bridge surface preparation and painting contractors.

    PubMed

    Virji, M Abbas; Woskie, Susan R; Pepper, Lewis D

    2009-02-01

    A 2005 regulatory review of the lead in construction standard by the Occupational Safety and Health Administration (OSHA) noted that alternative pathways of exposure can be as significant as inhalation exposure and that noncompliance with the standard pertaining to hygiene facilities and practices was the second most commonly violated section of the standard. Noncompliance with provisions of the standard and unhealthy work and hygiene practices likely increase the likelihood of take-home lead via contaminated clothing, automobiles, and skin, thus contributing to elevated blood lead levels (BLL) among construction workers and their family members. We performed a cross-sectional study of bridge painters working for small contractors in Massachusetts to investigate causes of persistent elevated BLLs and to assess lead exposures. Thirteen work sites were evaluated for a 2-week period during which surface and skin wipe samples were collected and qualitative information was obtained on personal hygiene practices, decontamination and hand wash facilities, and respiratory protection programs. Results showed lead contamination on workers' skin, respirators, personal automobiles, and the decontamination unit, indicating a significant potential for take-home lead exposure. Overall, the geometric mean (GM) skin lead levels ranged from 373 microg on workers' faces at end of shift to 814 microg on hands at break time. The overall GM lead level inside respirators was 143 microg before work and 286 microg after work. Lead contamination was also present inside workers' personal vehicles as well as on surfaces inside the clean side of the decontamination unit. Review of the respiratory protection programs, work site decontamination and hand wash facilities, and personal hygiene practices indicated that these factors had significant impact on skin and surface contamination levels and identified significant opportunities for improving work site facilities and personal practices. Elevated lead exposure and BLL can be minimized by strict adherence to the OSHA provisions for functioning decontamination and hygiene facilities and healthy personal hygiene practices.

  11. Subaru FATS (fault tracking system)

    NASA Astrophysics Data System (ADS)

    Winegar, Tom W.; Noumaru, Junichi

    2000-07-01

    The Subaru Telescope requires a fault tracking system to record the problems and questions that staff experience during their work, and the solutions provided by technical experts to these problems and questions. The system records each fault and routes it to a pre-selected 'solution-provider' for each type of fault. The solution provider analyzes the fault and writes a solution that is routed back to the fault reporter and recorded in a 'knowledge-base' for future reference. The specifications of our fault tracking system were unique. (1) Dual language capacity -- Our staff speak both English and Japanese. Our contractors speak Japanese. (2) Heterogeneous computers -- Our computer workstations are a mixture of SPARCstations, Macintosh and Windows computers. (3) Integration with prime contractors -- Mitsubishi and Fujitsu are primary contractors in the construction of the telescope. In many cases, our 'experts' are our contractors. (4) Operator scheduling -- Our operators spend 50% of their work-month operating the telescope, the other 50% is spent working day shift at the base facility in Hilo, or day shift at the summit. We plan for 8 operators, with a frequent rotation. We need to keep all operators informed on the current status of all faults, no matter the operator's location.

  12. 48 CFR 9.308-2 - Testing performed by the Government.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... ACQUISITION PLANNING CONTRACTOR QUALIFICATIONS First Article Testing and Approval 9.308-2 Testing performed by... produce the first article and the production quantity at the same facility, the contracting officer shall... purchase material or to commence production before first article approval, the contracting officer shall...

  13. 48 CFR 9.308-2 - Testing performed by the Government.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... ACQUISITION PLANNING CONTRACTOR QUALIFICATIONS First Article Testing and Approval 9.308-2 Testing performed by... produce the first article and the production quantity at the same facility, the contracting officer shall... purchase material or to commence production before first article approval, the contracting officer shall...

  14. 48 CFR 9.308-2 - Testing performed by the Government.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... ACQUISITION PLANNING CONTRACTOR QUALIFICATIONS First Article Testing and Approval 9.308-2 Testing performed by... produce the first article and the production quantity at the same facility, the contracting officer shall... purchase material or to commence production before first article approval, the contracting officer shall...

  15. 48 CFR 9.308-2 - Testing performed by the Government.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... ACQUISITION PLANNING CONTRACTOR QUALIFICATIONS First Article Testing and Approval 9.308-2 Testing performed by... produce the first article and the production quantity at the same facility, the contracting officer shall... purchase material or to commence production before first article approval, the contracting officer shall...

  16. 48 CFR 9.308-2 - Testing performed by the Government.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... ACQUISITION PLANNING CONTRACTOR QUALIFICATIONS First Article Testing and Approval 9.308-2 Testing performed by... produce the first article and the production quantity at the same facility, the contracting officer shall... purchase material or to commence production before first article approval, the contracting officer shall...

  17. 48 CFR 23.905 - Requirements.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... DRUG-FREE WORKPLACE Contractor Compliance With Toxic Chemical Release Reporting 23.905 Requirements. (a... (limited to facilities regulated under the Resource Conservation and Recovery Act, Subtitle C (42 U.S.C... (Mail Code 7408), Washington, DC 20460. (c) Award shall not be made to offerors who do not certify in...

  18. 40 CFR Appendix F to Part 112 - Facility-Specific Response Plan

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ...) Guidelines (see Appendix E to this part, section 13, for availability), which satisfy Oil Pollution Act (OPA... contracts with response contractors shall be included in this section so that the availability of resources...: ___ Direction from City: ___ Section: ____ Township: ____ Range: ____ Borough: ____ Container Type: ___ Tank Oil...

  19. Dorm Renovations: To Increase Enrollment or Maintain Status Quo?

    ERIC Educational Resources Information Center

    Stauff, William

    2001-01-01

    Explores South Carolina's Erskine College's planning and decision making process to renovate all seven of its dormitories over three summers. Discusses how the organization built a strong relationship with the contractor, successfully utilized outside architectural and consulting services, applied facilities management techniques in the process,…

  20. 48 CFR 811.602 - General.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... requirement as stated in the solicitation or offer. (6) The additional time the contractor claims is necessary... materials. (8) If applicable, a statement that the item required is for use in a construction contract that was authorized by the Director, Office of Construction and Facilities Management, to be awarded and...

  1. 48 CFR 811.602 - General.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... requirement as stated in the solicitation or offer. (6) The additional time the contractor claims is necessary... materials. (8) If applicable, a statement that the item required is for use in a construction contract that was authorized by the Director, Office of Construction and Facilities Management, to be awarded and...

  2. RCRA, Superfund and EPCRA hotline training module. Introduction to: the Superfund response program (updated February 1998); Directive

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    NONE

    1998-06-01

    This module includes the following: Regulatory Summary (Definitions; National Contingency Plan; Notification or Discovery; Response Process; Removal Process; Remedial Process; Community Involvement; State Role; Natural Resource Damage Assessments; Federal Facility Response; and Contractor Support); and Module Summary.

  3. 28 CFR 35.130 - General prohibitions against discrimination.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... disabilities. (5) A public entity, in the selection of procurement contractors, may not use criteria that..., directly or through contractual or other arrangements, utilize criteria or methods of administration: (i... determining the site or location of a facility, make selections— (i) That have the effect of excluding...

  4. Draft environmental impact statement: Space Shuttle Advanced Solid Rocket Motor Program

    NASA Technical Reports Server (NTRS)

    1988-01-01

    The proposed action is design, development, testing, and evaluation of Advanced Solid Rocket Motors (ASRM) to replace the motors currently used to launch the Space Shuttle. The proposed action includes design, construction, and operation of new government-owned, contractor-operated facilities for manufacturing and testing the ASRM's. The proposed action also includes transport of propellant-filled rocket motor segments from the manufacturing facility to the testing and launch sites and the return of used and/or refurbished segments to the manufacturing site.

  5. Orion EM-1 Crew Module Structural Test Article loaded onto Guppy

    NASA Image and Video Library

    2017-04-25

    On the tarmac at the Shuttle Landing Facility at NASA's Kennedy Space Center in Florida, NASA and contractor workers review procedures before beginning loading of the Orion Exploration Mission-1 (EM-1) structural test article in its transport container into NASA's Super Guppy aircraft. The test article will be transported to Lockheed Martin's Denver facility for testing. The Orion spacecraft will launch atop NASA’s Space Launch System rocket on EM-1, its first deep space mission.

  6. Conceptual design statement of work for the immobilized low-activity waste interim storage facility project

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Carlson, T.A., Fluor Daniel Hanford

    1997-02-06

    The Immobilized Low-Activity Waste Interim Storage subproject will provide storage capacity for immobilized low-activity waste product sold to the U.S. Department of Energy by the privatization contractor. This statement of work describes the work scope (encompassing definition of new installations and retrofit modifications to four existing grout vaults), to be performed by the Architect-Engineer, in preparation of a conceptual design for the Immobilized Low-Activity Waste Interim Storage Facility.

  7. FY 1978 scientific and technical reports, articles, papers, and presentations. [bibliography

    NASA Technical Reports Server (NTRS)

    White, O. L. (Compiler)

    1978-01-01

    Abstracts of 73 technical papers published or presented by MSFC personnel in FY-78 are presented. In addition, over 400 papers by contractors to that facility are listed along with the STAR document number for each report. Titles of 208 additional papers already cleared for publication are included.

  8. ABC's of Construction. Final Report.

    ERIC Educational Resources Information Center

    Greater Baton Rouge Chamber of Commerce, LA.

    The ABC's of Construction project was a demonstration project designed to integrate basic skills training with an industry-developed vocational-craft training program. The program was located at the central training facility of the Pelican Chapter of Associated Builders and Contractors (ABC), an organization made up of nearly 300 member companies…

  9. 14 CFR 120.1 - Applicability.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... AND OPERATORS FOR COMPENSATION OR HIRE: CERTIFICATION AND OPERATIONS DRUG AND ALCOHOL TESTING PROGRAM... part 135 of this chapter, all air traffic control facilities not operated by the FAA or by or under... implement a drug and alcohol testing program under this part. (d) All contractors who elect to implement a...

  10. 29 CFR 779.317 - Partial list of establishments lacking “retail concept.”

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... (such as operating instruments, X-ray machines, operating tables, etc.); establishments engaged in the... goods or facilities for the operation of such carriers (Idaho Sheet Metal Works v. Wirtz, 383 U.S. 190... distributors. Security dealers. Sheet metal contractors. Ship equipment, commercial; establishments engaged in...

  11. 29 CFR 779.317 - Partial list of establishments lacking “retail concept.”

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... (such as operating instruments, X-ray machines, operating tables, etc.); establishments engaged in the... goods or facilities for the operation of such carriers (Idaho Sheet Metal Works v. Wirtz, 383 U.S. 190... distributors. Security dealers. Sheet metal contractors. Ship equipment, commercial; establishments engaged in...

  12. Summary of 2017 EFCOG Training "How DOE Does Training" Survey Results

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Hanson, Todd

    Thirteen training organizations associated with the Energy Facility Contractors Group (EFCOG) Training Working Group were approached earlier this year for information on core training requirements of their organizations. Of the organizations surveyed, 85% responded, which helped create the data shown here. We thank them for their support.

  13. 10 CFR 830.121 - Quality Assurance Program (QAP).

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 10 Energy 4 2010-01-01 2010-01-01 false Quality Assurance Program (QAP). 830.121 Section 830.121 Energy DEPARTMENT OF ENERGY NUCLEAR SAFETY MANAGEMENT Quality Assurance Requirements § 830.121 Quality... the Quality Assurance criteria in § 830.122. (b) The contractor responsible for a DOE nuclear facility...

  14. 48 CFR 1322.101-4 - Removal of items from contractors' facilities affected by work stoppages.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 5 2010-10-01 2010-10-01 false Removal of items from... Regulations System DEPARTMENT OF COMMERCE SOCIOECONOMIC PROGRAMS APPLICATION OF LABOR LAWS TO GOVERNMENT... legal advice before initiating any action in accordance with FAR 22.101-4. ...

  15. 48 CFR 5145.302-3 - Other contracts.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 7 2010-10-01 2010-10-01 false Other contracts. 5145.302... REGULATIONS GOVERNMENT PROPERTY 5145.302-3 Other contracts. (S-90)(1) When it is determined that contractor... installation support services contracts, is in the best interest of the Government, the Government facilities...

  16. 76 FR 79216 - Privacy Act of 1974; System of Records

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-12-21

    ... of Prisons (Bureau) facilities, any location operated by a contractor authorized to provide computer... DEPARTMENT OF JUSTICE [CPCLO Order No. 005-2011] Privacy Act of 1974; System of Records AGENCY: Federal Bureau of Prisons, Department of Justice. ACTION: Notice of Modification of a System of Records...

  17. 76 FR 79216 - Privacy Act of 1974; System of Records

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-12-21

    ...) facilities nationwide, at any location operated by a contractor authorized to provide computer and/or... DEPARTMENT OF JUSTICE [CPCLO Order No. 006-2011] Privacy Act of 1974; System of Records AGENCY: Federal Bureau of Prisons, Department of Justice. ACTION: Notice of Modification of a System of Records...

  18. 15 CFR 760.3 - Exceptions to prohibitions.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ..., a U.S. contractor building an industrial facility in boycotting country Y is asked by B, a resident... agency of boycotting country Y to build a pipeline. Y requests A to suggest qualified engineering firms... conducts its operations, to identify qualified engineering firms to its customers so that its customers may...

  19. 15 CFR 760.3 - Exceptions to prohibitions.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ..., a U.S. contractor building an industrial facility in boycotting country Y is asked by B, a resident... agency of boycotting country Y to build a pipeline. Y requests A to suggest qualified engineering firms... conducts its operations, to identify qualified engineering firms to its customers so that its customers may...

  20. 14 CFR 120.1 - Applicability.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... AND OPERATORS FOR COMPENSATION OR HIRE: CERTIFICATION AND OPERATIONS DRUG AND ALCOHOL TESTING PROGRAM... part 135 of this chapter, all air traffic control facilities not operated by the FAA or by or under... implement a drug and alcohol testing program under this part. (d) All contractors who elect to implement a...

  1. 'Commitment' secures rooftop SSD contract.

    PubMed

    Davies, John

    2010-01-01

    John Davies, operations manager of multi-disciplinary mechanical and electrical and construction contractor cfes, describes a "turnkey" project that the company is undertaking for the Yeovil District Hospital (YDH) NHS Foundation Trust, involving both the design and construction of a new sterile services department, and substantial input into the facility's subsequent operation and management.

  2. Laundry Facility Considerations: Tips on an Often Overlooked Student Housing Issue.

    ERIC Educational Resources Information Center

    Reynolds, Rick

    1991-01-01

    Administrators making long-term decisions on campus laundry equipment and service need to consider self-ownership versus contracting. Considerations in selecting a contractor include the contract, accountability, repair services, and machine usage pricing. Laundry rooms should not be located where they pose security problems and should be arranged…

  3. 48 CFR 970.2770-4 - Contract clause.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... SUPPLEMENTARY REGULATIONS DOE MANAGEMENT AND OPERATING CONTRACTS Patents, Data, and Copyrights 970.2770-4... facility management and operating contract. (b) If the contractor is a nonprofit organization or small business eligible under 35 U.S.C. 200 et seq., to receive title to any inventions under the contract and...

  4. 44 CFR 351.24 - The Department of Energy.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 44 Emergency Management and Assistance 1 2011-10-01 2011-10-01 false The Department of Energy. 351... Assignments § 351.24 The Department of Energy. (a) Determine the appropriate planning bases for the Department of Energy (DOE) owned and contractor operated nuclear facilities (e.g., research and weapon...

  5. 44 CFR 351.24 - The Department of Energy.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 44 Emergency Management and Assistance 1 2013-10-01 2013-10-01 false The Department of Energy. 351... Assignments § 351.24 The Department of Energy. (a) Determine the appropriate planning bases for the Department of Energy (DOE) owned and contractor operated nuclear facilities (e.g., research and weapon...

  6. 44 CFR 351.24 - The Department of Energy.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 44 Emergency Management and Assistance 1 2014-10-01 2014-10-01 false The Department of Energy. 351... Assignments § 351.24 The Department of Energy. (a) Determine the appropriate planning bases for the Department of Energy (DOE) owned and contractor operated nuclear facilities (e.g., research and weapon...

  7. 2016 Energy Awareness Day

    NASA Image and Video Library

    2016-10-20

    Cory Taylor, an energy and water conservation specialist at Kennedy Space Center, absorbs information at the Multi-Function Facility on Oct. 20. Every third Thursday of October, civil servants, contractors and several energy utilities promote the awareness of our sustainability goals at Kennedy Space Center and at home. Photo credit: Cory Huston

  8. 44 CFR 351.24 - The Department of Energy.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 44 Emergency Management and Assistance 1 2010-10-01 2010-10-01 false The Department of Energy. 351... Assignments § 351.24 The Department of Energy. (a) Determine the appropriate planning bases for the Department of Energy (DOE) owned and contractor operated nuclear facilities (e.g., research and weapon...

  9. 44 CFR 351.24 - The Department of Energy.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 44 Emergency Management and Assistance 1 2012-10-01 2011-10-01 true The Department of Energy. 351... Assignments § 351.24 The Department of Energy. (a) Determine the appropriate planning bases for the Department of Energy (DOE) owned and contractor operated nuclear facilities (e.g., research and weapon...

  10. A Principal's Guide to On-Site School Construction

    ERIC Educational Resources Information Center

    Brenner, William A.

    2009-01-01

    This paper addresses construction that takes place in or near the school building while school is in session--the most difficult kind of construction to manage. Success largely depends upon the preparation, competence, and goodwill of the school district's facility staff, the project architect/engineer, the contractor, and local school…

  11. 76 FR 68376 - Recoupment of Nonrecurring Costs (NCs) on Sales of U.S. Items

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-11-04

    ... expenditures for machine tools, capital equipment, or facilities for which contractor rental payments are made.... Major defense equipment. Any item of significant military equipment on the United States Munitions List... the major defense equipment dollar threshold for research, development, test, and evaluation shall be...

  12. Technology transfer package on seismic base isolation - Volume II

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    NONE

    1995-02-14

    This Technology Transfer Package provides some detailed information for the U.S. Department of Energy (DOE) and its contractors about seismic base isolation. Intended users of this three-volume package are DOE Design and Safety Engineers as well as DOE Facility Managers who are responsible for reducing the effects of natural phenomena hazards (NPH), specifically earthquakes, on their facilities. The package was developed as part of DOE's efforts to study and implement techniques for protecting lives and property from the effects of natural phenomena and to support the International Decade for Natural Disaster Reduction. Volume II contains the proceedings for the Shortmore » Course on Seismic Base Isolation held in Berkeley, California, August 10-14, 1992.« less

  13. Aerial Views of KSC

    NASA Image and Video Library

    2003-07-23

    The Space Experiment Research and Processing Laboratory (SERPL) is a major new research facility under construction at the International Space Research Park located on KSC. Being developed as a partnership between KSC and the State of Florida, it will serve as the primary gateway to the International Space Station for science experiments and as a world-class home to ground-based investigations in fundamental and applied biological science. NASA’s life sciences contractor will be the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA-sponsored research. About 20 percent of the facility will be available for use by Florida’s university researchers through the Florida Space Research Institute.

  14. Explosive safety criteria at a Department of Energy contractor facility

    NASA Astrophysics Data System (ADS)

    Krach, F.

    1984-08-01

    Monsanto Research Corporation (MRC) operates the Mound facility in Miamisburg, Ohio, for the Department of Energy. Small explosive components are manufactured at MRC, and stringent explosive safety criteria have been developed for their manufacturing. The goals of these standards are to reduce employee injuries and eliminate fenceline impacts resulting from accidental detonations. The manner in which these criteria were developed and what DOD standards were incorporated into MRC's own design criteria are described. These design requirements are applicable to all new construction at MRC. An example of the development of the design of a Component Test Facility is presented to illustrate the application of the criteria.

  15. DOE Fundamentals Handbook: Mathematics, Volume 1

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Not Available

    1992-06-01

    The Mathematics Fundamentals Handbook was developed to assist nuclear facility operating contractors provide operators, maintenance personnel, and the technical staff with the necessary fundamentals training to ensure a basic understanding of mathematics and its application to facility operation. The handbook includes a review of introductory mathematics and the concepts and functional use of algebra, geometry, trigonometry, and calculus. Word problems, equations, calculations, and practical exercises that require the use of each of the mathematical concepts are also presented. This information will provide personnel with a foundation for understanding and performing basic mathematical calculations that are associated with various DOE nuclearmore » facility operations.« less

  16. DOE Fundamentals Handbook: Mathematics, Volume 2

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Not Available

    1992-06-01

    The Mathematics Fundamentals Handbook was developed to assist nuclear facility operating contractors provide operators, maintenance personnel, and the technical staff with the necessary fundamentals training to ensure a basic understanding of mathematics and its application to facility operation. The handbook includes a review of introductory mathematics and the concepts and functional use of algebra, geometry, trigonometry, and calculus. Word problems, equations, calculations, and practical exercises that require the use of each of the mathematical concepts are also presented. This information will provide personnel with a foundation for understanding and performing basic mathematical calculations that are associated with various DOE nuclearmore » facility operations.« less

  17. Key aspects in managing safety when working with multiple contractors: A case study.

    PubMed

    Drupsteen, Linda; Rasmussen, Hanna B; Ustailieva, Erika; van Kampen, Jakko

    2015-01-01

    Working with multiple contractors in a shared workplace can introduce and increase safety risks due to complexity. The aim of this study was to explore how safety issues are recognized in a specific case and to identify whether clients and contractors perceive problems similarly. The safety issues are explored through a brief survey and a workshop in the maintenance department of a logistics company. The results indicate that culture and behavior are recognized differently by clients and by contractors. The contractors and client had different perceptions of involvement of contractors by the client. The contractors complained on lack of involvement, which was not fully recognized by the client. The case study used a practical approach to show differences in perception of safety within a project. The study illustrates the need for more applied studies and interventions on contractor safety.

  18. Maintenance and operations contractor plan for transition to the project Hanford management contract (PHMC)

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Waite, J.L.

    1996-04-12

    This plan has been developed by Westinghouse Hanford Company (WHC), and its subcontractors ICF Kaiser Hanford (ICF KH) and BCS Richland, Inc. (BCSR), at the direction of the US Department of Energy (DOE), Richland Operations Office (RL). WHC and its subcontractors are hereafter referred to as the Maintenance and Operations (M and O) Contractor. The plan identifies actions involving the M and O Contractor that are critical to (1) prepare for a smooth transition to the Project Hanford Management Contractor (PHMC), and (2) support and assist the PHMC and RL in achieving transition as planned, with no or minimal impactmore » to ongoing baseline activities. The plan is structured around two primary phases. The first is the pre-award phase, which started in mid-February 1996 and is currently scheduled to be completed on June 1, 1996, at which time the contract is currently planned to be awarded. The second is the follow-on four-month post-award phase from June 1, 1996, until October 1, 1996. Considering the magnitude and complexity of the scope of work being transitioned, completion in four months will require significant effort by all parties. To better ensure success, the M and O Contractor has developed a pre-award phase that is intended to maximize readiness for transition. Priority is given to preparation for facility assessments and processing of personnel, as these areas are determined to be on the critical path for transition. In addition, the M and O Contractor will put emphasis during the pre-award phase to close out open items prior to contract award, to include grievances, employee concerns, audit findings, compliance issues, etc.« less

  19. KENNEDY SPACE CENTER, FLA. - Dignitaries, invited guests, space center employees, and the media show their appreciation for the speakers at a dedication and ribbon-cutting ceremony for the Space Life Sciences Lab hosted by NASA-Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASA’s Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

    NASA Image and Video Library

    2003-11-19

    KENNEDY SPACE CENTER, FLA. - Dignitaries, invited guests, space center employees, and the media show their appreciation for the speakers at a dedication and ribbon-cutting ceremony for the Space Life Sciences Lab hosted by NASA-Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASA’s Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

  20. KSC-2010-5738

    NASA Image and Video Library

    2010-11-24

    CAPE CANAVERAL, Fla. -- Construction begins to wrap up at the Propellants North Administrative and Maintenance Facility in the Launch Complex 39 area of NASA's Kennedy Space Center in Florida. This is the facility's two-story administrative building, which will house managers, mechanics and technicians who fuel spacecraft at Kennedy. Next door is a single-story shop that will be used to store cryogenic fuel transfer equipment. The facility is striving to qualify for the U.S. Green Building Council’s Leadership in Energy and Environmental Design (LEED) Platinum certification, which is the highest of LEED ratings. The facility, set to be complete in December 2010, was designed for NASA by Jones Edmunds and Associates. H. W. Davis Construction is the construction contractor. Photo credit: NASA/Frankie Martin

  1. KSC-2010-5739

    NASA Image and Video Library

    2010-11-24

    CAPE CANAVERAL, Fla. -- Construction begins to wrap up at the Propellants North Administrative and Maintenance Facility in the Launch Complex 39 area of NASA's Kennedy Space Center in Florida. This is the facility's two-story administrative building, which will house managers, mechanics and technicians who fuel spacecraft at Kennedy. Next door is a single-story shop that will be used to store cryogenic fuel transfer equipment. The facility is striving to qualify for the U.S. Green Building Council’s Leadership in Energy and Environmental Design (LEED) Platinum certification, which is the highest of LEED ratings. The facility, set to be complete in December 2010, was designed for NASA by Jones Edmunds and Associates. H. W. Davis Construction is the construction contractor. Photo credit: NASA/Frankie Martin

  2. KSC-2010-5740

    NASA Image and Video Library

    2010-11-24

    CAPE CANAVERAL, Fla. -- Construction begins to wrap up at the Propellants North Administrative and Maintenance Facility in the Launch Complex 39 area of NASA's Kennedy Space Center in Florida. On the left is the facility's single-story shop, which will be used to store cryogenic fuel transfer equipment. On the right is a two-story administrative building that will house managers, mechanics and technicians who fuel spacecraft at Kennedy. The facility is striving to qualify for the U.S. Green Building Council’s Leadership in Energy and Environmental Design (LEED) Platinum certification, which is the highest of LEED ratings. The facility, set to be complete in December 2010, was designed for NASA by Jones Edmunds and Associates. H. W. Davis Construction is the construction contractor. Photo credit: NASA/Frankie Martin

  3. Pressure Safety Program Implementation at ORNL

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Lower, Mark; Etheridge, Tom; Oland, C. Barry

    2013-01-01

    The Oak Ridge National Laboratory (ORNL) is a US Department of Energy (DOE) facility that is managed by UT-Battelle, LLC. In February 2006, DOE promulgated worker safety and health regulations to govern contractor activities at DOE sites. These regulations, which are provided in 10 CFR 851, Worker Safety and Health Program, establish requirements for worker safety and health program that reduce or prevent occupational injuries, illnesses, and accidental losses by providing DOE contractors and their workers with safe and healthful workplaces at DOE sites. The regulations state that contractors must achieve compliance no later than May 25, 2007. According tomore » 10 CFR 851, Subpart C, Specific Program Requirements, contractors must have a structured approach to their worker safety and health programs that at a minimum includes provisions for pressure safety. In implementing the structured approach for pressure safety, contractors must establish safety policies and procedures to ensure that pressure systems are designed, fabricated, tested, inspected, maintained, repaired, and operated by trained, qualified personnel in accordance with applicable sound engineering principles. In addition, contractors must ensure that all pressure vessels, boilers, air receivers, and supporting piping systems conform to (1) applicable American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (2004) Sections I through XII, including applicable code cases; (2) applicable ASME B31 piping codes; and (3) the strictest applicable state and local codes. When national consensus codes are not applicable because of pressure range, vessel geometry, use of special materials, etc., contractors must implement measures to provide equivalent protection and ensure a level of safety greater than or equal to the level of protection afforded by the ASME or applicable state or local codes. This report documents the work performed to address legacy pressure vessel deficiencies and comply with pressure safety requirements in 10 CFR 851. It also describes actions taken to develop and implement ORNL’s Pressure Safety Program.« less

  4. Improving access to medicines through centralised dispensing in the public sector: a case study of the Chronic Dispensing Unit in the Western Cape Province, South Africa.

    PubMed

    Magadzire, Bvudzai Priscilla; Marchal, Bruno; Ward, Kim

    2015-11-17

    The Chronic Dispensing Unit (CDU) is an out-sourced, public sector centralised dispensing service that has been operational in the Western Cape Province in South Africa since 2005. The CDU dispenses medicines for stable patients with chronic conditions. The aim is to reduce pharmacists' workload, reduce patient waiting times and decongest healthcare facilities. Our objectives are to describe the intervention's scope, illustrate its interface with the health system and describe its processes and outcomes. Secondly, to quantify the magnitude of missed appointments by enrolled patients and to describe the implications thereof in order to inform a subsequent in-depth empirical study on the underlying causes. We adopted a case study design in order to elicit the programme theory underlying the CDU strategy. We consulted 15 senior and middle managers from the provincial Department of Health who were working closely with the intervention and the contractor using focus group discussions and key informant interviews. In addition, relevant literature, and policy and programme documents were reviewed and analysed. We found that the CDU scope has significantly expanded over the last 10 years owing to technological advancements. As such, in early 2015, the CDU produced nearly 300,000 parcels monthly. Medicines supply, patient enrollment processes, healthcare professionals' compliance to legislation and policies, mechanisms for medicines distribution, management of non-collected medicines (emanating from patients' missed appointments) and the array of actors involved are all central to the CDU's functioning. Missed appointments by patients are a problem, affecting an estimated 8%-12% of patients each month. However, the causes have not been investigated thoroughly. Implications of missed appointments include a cost to government for services rendered by the contractor, potential losses due to expired medicines, additional workload for the contractor and healthcare facility staff and potential negative therapeutic outcomes for patients. The CDU demonstrates innovation in a context of overwhelming demand for dispensing medicines for chronic conditions. However, it is not a panacea to address access-to-medicines related challenges. A multi-level assessment that is currently underway will provide more insights on how existing challenges can be addressed.

  5. 10 CFR 830.202 - Safety basis.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 10 Energy 4 2011-01-01 2011-01-01 false Safety basis. 830.202 Section 830.202 Energy DEPARTMENT OF ENERGY NUCLEAR SAFETY MANAGEMENT Safety Basis Requirements § 830.202 Safety basis. (a) The contractor responsible for a hazard category 1, 2, or 3 DOE nuclear facility must establish and maintain the safety basis...

  6. Semi-annual report on strategic special nuclear material inventory differences

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Not Available

    1978-01-01

    This periodic report of Inventory Differences covers the period October 1, 1976, through March 31, 1977 for Department of Energy (DOE) and DOE contractor facilities possessing significant quantities of Strategic Special Nuclear Material (SSNM). Included in this report are the low enriched uranium inventory differences for DOE's gaseous diffusion plant cascades. (LK)

  7. 48 CFR 970.2703-2 - Patent rights clause provisions for management and operating contractors.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ...-exempted areas of technology or in operation of DOE facilities primarily dedicated to naval nuclear... for-profit, large business firm and the contract does not have a technology transfer mission or if... dedicated to naval nuclear propulsion or weapons related programs. That clause provides for DOE's statutory...

  8. 48 CFR 970.2703-2 - Patent rights clause provisions for management and operating contractors.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ...-exempted areas of technology or in operation of DOE facilities primarily dedicated to naval nuclear... for-profit, large business firm and the contract does not have a technology transfer mission or if... dedicated to naval nuclear propulsion or weapons related programs. That clause provides for DOE's statutory...

  9. EOS/AMSU: A Blackbody Spacecraft Test Targets Operation and Maintenance Manual

    NASA Technical Reports Server (NTRS)

    1998-01-01

    This report describes the spacecraft test targets and readout console as described in section 5.3.3 of the performance specification S-480-80. The spacecraft targets are to be used to provide a well-known radiometric reference for testing the functionality of the AMSU-A instruments at the spacecraft contractor's facility.

  10. Analysis of 4D Modeling for Use by the Naval Facilities Engineering Command

    DTIC Science & Technology

    2004-08-01

    Use Today Today, 4D modeling is being used to build Space Mountain at the new Hong Kong Disneyland theme park. Additionally, the technology is being...used for the reconstruction of the 26-year-old Space Mountain at the Disneyland in Anaheim. Muller explains: Among the hassles: Contractors must

  11. 48 CFR 52.222-21 - Prohibition of segregated facilities.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... because of written or oral policies or employee custom. The term does not include separate or single-user rest rooms or necessary dressing or sleeping areas provided to assure privacy between the sexes. (b) The Contractor agrees that it does not and will not maintain or provide for its employees any...

  12. 48 CFR 52.222-21 - Prohibition of segregated facilities.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... because of written or oral policies or employee custom. The term does not include separate or single-user rest rooms or necessary dressing or sleeping areas provided to assure privacy between the sexes. (b) The Contractor agrees that it does not and will not maintain or provide for its employees any...

  13. 48 CFR 52.222-21 - Prohibition of segregated facilities.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... because of written or oral policies or employee custom. The term does not include separate or single-user rest rooms or necessary dressing or sleeping areas provided to assure privacy between the sexes. (b) The Contractor agrees that it does not and will not maintain or provide for its employees any...

  14. 48 CFR 52.222-21 - Prohibition of segregated facilities.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... because of written or oral policies or employee custom. The term does not include separate or single-user rest rooms or necessary dressing or sleeping areas provided to assure privacy between the sexes. (b) The Contractor agrees that it does not and will not maintain or provide for its employees any...

  15. 10 CFR 830.202 - Safety basis.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 10 Energy 4 2010-01-01 2010-01-01 false Safety basis. 830.202 Section 830.202 Energy DEPARTMENT OF ENERGY NUCLEAR SAFETY MANAGEMENT Safety Basis Requirements § 830.202 Safety basis. (a) The contractor responsible for a hazard category 1, 2, or 3 DOE nuclear facility must establish and maintain the safety basis...

  16. 2016 Energy Awareness Day

    NASA Image and Video Library

    2016-10-20

    Michelle Sipe Exaros, with Lutron Electronics Co., is seen behind pamphlets and brochures of information during Energy Awareness Day at the Multi-Function Facility on Oct. 20. Every third Thursday of October, civil servants, contractors and several energy utilities promote the awareness of our sustainability goals at Kennedy Space Center and at home. Photo credit: Cory Huston

  17. 2016 Energy Awareness Day

    NASA Image and Video Library

    2016-10-20

    Shown are some of the devices from Lutron Electronics Co., a lighting control company, during Energy Awareness Day at the Multi-Function Facility on Oct. 20. Every third Thursday of October, civil servants, contractors and several energy utilities promote the awareness of our sustainability goals at Kennedy Space Center and at home. Photo credit: Cory Huston

  18. Energy Engineering Analysis (EEA) program for Lone Star Army Ammunition Plant, Texas. Executive summary. Final report

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    NONE

    The objective of this Energy Engineering Analysis (EEA) for LSAAP is threefold: Develop a systematic plan of projects which will result in reducing energy consumption. Consider renewable energy sources with the objective of establishing an orderly procedure for reducing use of non-renewable energy sources. Determine the feasibility of Total Energy (TE), Selective Energy (SE), and Central Heating Plant (CHP) concepts using alternative fuels. In essence, an assessment of the entire energy picture at LSAAP was undertaken. This report is a summary of that effort. LSAAP was originally built during 1941 and 1942 as a shell loading plant for the Army.more » After World War II, the facility was deactivated until 1951 when it was reactivated as a Government Owned, Contractor Operated (GOCO) facility. Day and Zimmerman was selected as the operator in 1951 and has been the operating contractor ever since. Located just west of Texarkana, Texas, LSAAP encompasses an area of approximately 15,546 acres. The primary mission of LSAAP is to load, assemble and pack ammunition and ammunition components for the Army.« less

  19. NASA/FAA North Texas Research Station Overview

    NASA Technical Reports Server (NTRS)

    Borchers, Paul F.

    2012-01-01

    NTX Research Staion: NASA research assets embedded in an interesting operational air transport environment. Seven personnel (2 civil servants, 5 contractors). ARTCC, TRACON, Towers, 3 air carrier AOCs(American, Eagle and Southwest), and 2 major airports all within 12 miles. Supports NASA Airspace Systems Program with research products at all levels (fundamental to system level). NTX Laboratory: 5000 sq ft purpose-built, dedicated, air traffic management research facility. Established data links to ARTCC, TRACON, Towers, air carriers, airport and NASA facilities. Re-configurable computer labs, dedicated radio tower, state-of-the-art equipment.

  20. DOE Office of Scientific and Technical Information (OSTI.GOV)

    NONE

    Training programs at DOE facilities should prepare personnel to safely and efficiently operate and maintain the facilities in accordance with DOE requirements. This guide presents good practices for a systematic approach to on-the-job training (OJT) and OJT programs and should be used in conjunction with DOE Training Program Handbook: A Systematic Approach to Training, and with the DOE Handbook entitled Alternative Systematic Approaches to Training to develop performance-based OJT programs. DOE contractors may also use this guide to modify existing OJT programs that do not meet the systematic approach to training (SAT) objectives.

  1. Space Station Freedom media handbook

    NASA Technical Reports Server (NTRS)

    1989-01-01

    This handbook explains in lay terms, the work that is going on at the NASA Centers and contractors' plants in designing and developing the Space Station Freedom. It discusses the roles, responsibilities, and tasks required to build the Space Station Freedom's elements, systems, and components. New, required ground facilities are described, organized by NASA Center in order to provide a local angle for the media. Included are information on the historical perspective, international aspects, the utilization of the Space Station Freedom, a look at future possibilities, a description of the program, its management, program phases and milestones, and considerable information on the role of various NASA Centers, contractors and international partners. A list of abbreviations, a four-page glossary, and a list of NASA contacts are contained in the appendices.

  2. KSC Headquarters Building Groundbreaking Ceremony

    NASA Image and Video Library

    2014-10-07

    Groundbreaking for the new Central Campus will take place in the Industrial Area at NASA's Kennedy Space Center in Florida. Kennedy Center Director Bob Cabana welcomes members of the media and guests to the ceremony. To his right is Nancy Bray, director of Kennedy's Center Operations Directorate. To his left is Kirk Hazen, southeast district manager and vice president of Hensel Phelps, the construction contractor. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees.

  3. 43 CFR 404.23 - How will Reclamation determine whether you or your contractor is qualified to conduct an...

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... or your contractor is qualified to conduct an appraisal investigation or a feasibility study? 404.23... feasibility study yourself or though a contractor, Reclamation will evaluate whether you, your technical staff, or contractor are qualified to perform the appraisal investigation or feasibility study based on...

  4. KSC-03PD-2644

    NASA Technical Reports Server (NTRS)

    2003-01-01

    KENNEDY SPACE CENTER, FLA. Employees check out the new chamber facilities of the Space Life Sciences Lab (SLSL), formerly known as the Space Experiment Research and Processing Laboratory (SERPL). From left are Ray Wheeler, with NASA; Debbie Wells and Larry Burns, with Dynamac; A.O. Rule, president of Environmental Growth Chambers, Inc. (ECG); Neil Yorio, with Dynamac; and John Wiezchowski, with ECG. The SLSL is a state-of-the-art facility being built for ISS biotechnology research. Developed as a partnership between NASA-KSC and the State of Florida, NASAs life sciences contractor will be the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA- sponsored research. About 20 percent of the facility will be available for use by Floridas university researchers through the Florida Space Research Institute.

  5. KSC-04PD-0005

    NASA Technical Reports Server (NTRS)

    2004-01-01

    KENNEDY SPACE CENTER, FLA. -- Lanfang Levine, with Dynamac Corp., helps install new equipment for gas chromatography and mass spectrometry in the Space Life Sciences Lab. The equipment will enable analysis of volatile compounds, such as from plants. The 100,000 square-foot facility houses labs for NASAs ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASAs Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASAs Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

  6. DOE Office of Scientific and Technical Information (OSTI.GOV)

    Griffith, Stacy Rene; Agogino, Karen; Li, Jun

    Tonopah Test Range (TTR) in Nevada and Kauai Test Facility (KTF) in Hawaii are government-owned, contractor-operated facilities managed and operated by Sandia Corporation (Sandia), a wholly owned subsidiary of Lockheed Martin Corporation. The U.S. Department of Energy (DOE), National Nuclear Security Administration (NNSA), through the Sandia Field Office (SFO), in Albuquerque, New Mexico, administers the contract and oversees contractor operations at TTR and KTF. Sandia manages and conducts operations at TTR in support of the DOE/NNSA’s Weapons Ordnance Program and has operated the site since 1957. Navarro Research and Engineering subcontracts to Sandia in administering most of the environmental programsmore » at TTR. Sandia operates KTF as a rocket preparation launching and tracking facility. This Annual Site Environmental Report summarizes data and the compliance status of the sustainability, environmental protection, and monitoring program at TTR and KTF through Calendar Year 2013. The compliance status of environmental regulations applicable at these sites include state and federal regulations governing air emissions, wastewater effluent, waste management, terrestrial surveillance, Environmental Restoration (ER) cleanup activities, and the National Environmental Policy Act. Sandia is responsible only for those environmental program activities related to its operations. The DOE/NNSA/Nevada Field Office retains responsibility for the cleanup and management of TTR ER sites. Environmental monitoring and surveillance programs are required by DOE Order 231.1B, Environment, Safety, and Health Reporting (DOE 2012).« less

  7. 76 FR 31639 - Notice of the Availability of the Finding of No Significant Impact Concerning a Proposal To Award...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-06-01

    ... Significant Impact Concerning a Proposal To Award a Contract to House Federal, Low- Security, Criminal Aliens... aliens within one or more existing contractor-owned and operated correctional facilities. Background... Federal, low-security, adult male, non-U.S. citizen, criminal aliens within one or more existing...

  8. 75 FR 5609 - Privacy Act of 1974; Department of Homeland Security/ALL-024 Facility and Perimeter Access...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-02-03

    ..., if applicable; Date and time of entry and departure; Drivers license and other form of identification information; License plate number and state of issuance; Make and model of vehicle; Reports, files, records... name and phone number. Headquarters employees and contractors can also provide a drivers license as...

  9. Outlook on EDRS-C

    NASA Astrophysics Data System (ADS)

    Migliore, R.; Duncan, J.; Pulcino, V.; Bourne, D.; Voegt, S.; Perez, G.

    2017-09-01

    EDRS-C will operate on a geostationary orbit as the second node of the European Data Relay System (EDRS). The EDRS-C satellite, designed by OHB System as prime contractor, has been procured in the frame of a Public Private Partnership (PPP) between Airbus Defence and Space and ESA. EDRS-C is currently under assembly at OHB facilities in Bremen.

  10. 48 CFR 970.5226-2 - Workforce restructuring under section 3161 of the National Defense Authorization Act for fiscal...

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... workforce at a Department of Energy Defense Nuclear Facility is necessary, the contractor agrees to (1... under section 3161 of the National Defense Authorization Act for fiscal year 1993. 970.5226-2 Section... and Operating Contracts 970.5226-2 Workforce restructuring under section 3161 of the National Defense...

  11. 48 CFR 970.5226-2 - Workforce restructuring under section 3161 of the National Defense Authorization Act for fiscal...

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... workforce at a Department of Energy Defense Nuclear Facility is necessary, the contractor agrees to (1... under section 3161 of the National Defense Authorization Act for fiscal year 1993. 970.5226-2 Section... and Operating Contracts 970.5226-2 Workforce restructuring under section 3161 of the National Defense...

  12. 48 CFR 970.5226-2 - Workforce restructuring under section 3161 of the National Defense Authorization Act for fiscal...

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... workforce at a Department of Energy Defense Nuclear Facility is necessary, the contractor agrees to (1... under section 3161 of the National Defense Authorization Act for fiscal year 1993. 970.5226-2 Section... and Operating Contracts 970.5226-2 Workforce restructuring under section 3161 of the National Defense...

  13. 48 CFR 970.5226-2 - Workforce restructuring under section 3161 of the National Defense Authorization Act for fiscal...

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... workforce at a Department of Energy Defense Nuclear Facility is necessary, the contractor agrees to (1... under section 3161 of the National Defense Authorization Act for fiscal year 1993. 970.5226-2 Section... and Operating Contracts 970.5226-2 Workforce restructuring under section 3161 of the National Defense...

  14. Construction Management for Educational Facilities: Professional Services' Procurement and Competitive Bid Statutes.

    ERIC Educational Resources Information Center

    Goldblatt, Steven M.; Wood, R. Craig

    Construction management is utilized when a school district engages a firm to coordinate a total project. The construction management seeks to save an owner time and cost primarily through better contractor coordination and project management. These services may include the planning and design phases of the project as well as the actual…

  15. 76 FR 2762 - Proposed Information Collection (VAAR Clause 852.236.91, Special Notes) Activity: Comment Request

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-01-14

    ... support claims for price adjustment due to delay in construction caused by severe weather. DATES: Written... facilities available to perform the work. The clause also requires contractors submitting a claim for price adjustment due to severe weather delay to provide climatologically data covering the period of the claim and...

  16. Report: EPA Could Improve Physical Access and Service Continuity/Contingency Controls for Financial and Mixed-Financial Systems Located at its Research Triangle Park Campus

    EPA Pesticide Factsheets

    Report #2006-P-00005, December 14, 2005. Controls needed to be improved in areas such as visitor access to facilities, use of contractor access badges, and general physical access to the NCC, computer rooms outside the NCC, and media storage rooms.

  17. 29 CFR 37.7 - What specific discriminatory actions based on disability are prohibited by this part?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... WIA or this part. (g) A recipient, in the selection of contractors, must not use criteria that subject..., licensing, or other arrangements, use standards, procedures, criteria, or administrative methods: (1) That... site or location of facilities, a grant applicant or recipient must not make selections that have any...

  18. Integration of functional safety systems on the Daniel K. Inouye Solar Telescope

    NASA Astrophysics Data System (ADS)

    Williams, Timothy R.; Hubbard, Robert P.; Shimko, Steve

    2016-07-01

    The Daniel K. Inouye Solar Telescope (DKIST) was envisioned from an early stage to incorporate a functional safety system to ensure the safety of personnel and equipment within the facility. Early hazard analysis showed the need for a functional safety system. The design used a distributed approach in which each major subsystem contains a PLC-based safety controller. This PLC-based system complies with the latest international standards for functional safety. The use of a programmable controller also allows for flexibility to incorporate changes in the design of subsystems without adversely impacting safety. Various subsystems were built by different contractors and project partners but had to function as a piece of the overall control system. Using distributed controllers allows project contractors and partners to build components as standalone subsystems that then need to be integrated into the overall functional safety system. Recently factory testing was concluded on the major subsystems of the facility. Final integration of these subsystems is currently underway on the site. Building on lessons learned in early factory tests, changes to the interface between subsystems were made to improve the speed and ease of integration of the entire system. Because of the distributed design each subsystem can be brought online as it is delivered and assembled rather than waiting until the entire facility is finished. This enhances safety during the risky period of integration and testing. The DKIST has implemented a functional safety system that has allowed construction of subsystems in geographically diverse locations but that function cohesively once they are integrated into the facility currently under construction.

  19. KSC-2010-4698

    NASA Image and Video Library

    2010-09-20

    CAPE CANAVERAL, Fla. - Workers of Superior Solar LLC in Longwood, Fla., begin to install more than 300 solar panels on the roof of the Propellants North Administrative and Maintenance Facility at NASA's Kennedy Space Center in Florida. Each panel, built in Sharp Corp.'s Memphis, Tenn., plant, will produce 235 watts of clean energy. The green facility in Kennedy's Launch Complex 39 area will have a two-story administrative building to house managers, mechanics and technicians who fuel spacecraft at Kennedy adjacent to a single-story shop to store cryogenic fuel transfer equipment. The facility is striving to qualify for the U.S. Green Building Council’s Leadership in Energy and Environmental Design (LEED) Platinum certification. If successful, it will be the first NASA facility to achieve this highest of LEED ratings after it is completed. The facility was designed for NASA by Jones Edmunds and Associates. H. W. Davis Construction is the construction contractor. Photo credit: NASA/Jim Grossmann

  20. KSC-2010-4700

    NASA Image and Video Library

    2010-09-20

    CAPE CANAVERAL, Fla. - Workers of Superior Solar LLC in Longwood, Fla., begin to install more than 300 solar panels on the roof of the Propellants North Administrative and Maintenance Facility at NASA's Kennedy Space Center in Florida. Each panel, built in Sharp Corp.'s Memphis, Tenn., plant, will produce 235 watts of clean energy. The green facility in Kennedy's Launch Complex 39 area will have a two-story administrative building to house managers, mechanics and technicians who fuel spacecraft at Kennedy adjacent to a single-story shop to store cryogenic fuel transfer equipment. The facility is striving to qualify for the U.S. Green Building Council’s Leadership in Energy and Environmental Design (LEED) Platinum certification. If successful, it will be the first NASA facility to achieve this highest of LEED ratings after it is completed. The facility was designed for NASA by Jones Edmunds and Associates. H. W. Davis Construction is the construction contractor. Photo credit: NASA/Jim Grossmann

  1. KSC-2010-4699

    NASA Image and Video Library

    2010-09-20

    CAPE CANAVERAL, Fla. - Workers of Superior Solar LLC in Longwood, Fla., prepare to install more than 300 solar panels on the roof of the Propellants North Administrative and Maintenance Facility at NASA's Kennedy Space Center in Florida. Each panel, built in Sharp Corp.'s Memphis, Tenn., plant, will produce 235 watts of clean energy. The green facility in Kennedy's Launch Complex 39 area will have a two-story administrative building to house managers, mechanics and technicians who fuel spacecraft at Kennedy adjacent to a single-story shop to store cryogenic fuel transfer equipment. The facility is striving to qualify for the U.S. Green Building Council’s Leadership in Energy and Environmental Design (LEED) Platinum certification. If successful, it will be the first NASA facility to achieve this highest of LEED ratings after it is completed. The facility was designed for NASA by Jones Edmunds and Associates. H. W. Davis Construction is the construction contractor. Photo credit: NASA/Jim Grossmann

  2. KSC-2010-4697

    NASA Image and Video Library

    2010-09-20

    CAPE CANAVERAL, Fla. - Workers of Superior Solar LLC in Longwood, Fla., begin to install more than 300 solar panels on the roof of the Propellants North Administrative and Maintenance Facility at NASA's Kennedy Space Center in Florida. Each panel, built in Sharp Corp.'s Memphis, Tenn., plant, will produce 235 watts of clean energy. The green facility in Kennedy's Launch Complex 39 area will have a two-story administrative building to house managers, mechanics and technicians who fuel spacecraft at Kennedy adjacent to a single-story shop to store cryogenic fuel transfer equipment. The facility is striving to qualify for the U.S. Green Building Council’s Leadership in Energy and Environmental Design (LEED) Platinum certification. If successful, it will be the first NASA facility to achieve this highest of LEED ratings after it is completed. The facility was designed for NASA by Jones Edmunds and Associates. H. W. Davis Construction is the construction contractor. Photo credit: NASA/Jim Grossmann

  3. KSC-04PD-0007

    NASA Technical Reports Server (NTRS)

    2004-01-01

    KENNEDY SPACE CENTER, FLA. -- In the Space Life Sciences (SLS) Lab, Jan Bauer, with Dynamac Corp., places samples of onion tissue in the elemental analyzer, which analyzes for carbon, hydrogen, nitrogen and sulfur. The 100,000 square-foot SLS houses labs for NASAs ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASAs Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASAs Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

  4. Aeropropulsion facilities configuration control: Procedures manual

    NASA Technical Reports Server (NTRS)

    Lavelle, James J.

    1990-01-01

    Lewis Research Center senior management directed that the aeropropulsion facilities be put under configuration control. A Configuration Management (CM) program was established by the Facilities Management Branch of the Aeropropulsion Facilities and Experiments Division. Under the CM program, a support service contractor was engaged to staff and implement the program. The Aeronautics Directorate has over 30 facilities at Lewis of various sizes and complexities. Under the program, a Facility Baseline List (FBL) was established for each facility, listing which systems and their documents were to be placed under configuration control. A Change Control System (CCS) was established requiring that any proposed changes to FBL systems or their documents were to be processed as per the CCS. Limited access control of the FBL master drawings was implemented and an audit system established to ensure all facility changes are properly processed. This procedures manual sets forth the policy and responsibilities to ensure all key documents constituting a facilities configuration are kept current, modified as needed, and verified to reflect any proposed change. This is the essence of the CM program.

  5. Fluor Hanford ALARA Center is a D and D Resource

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Waggoner, L.O.

    2008-01-15

    The mission at the Hanford Nuclear Reservation changed when the last reactor plant was shut down in 1989 and work was started to place all the facilities in a safe condition and begin decontamination, deactivation, decommissioning, and demolition (D and D). These facilities consisted of old shutdown reactor plants, spent fuel pools, processing facilities, and 177 underground tanks containing 53 million gallons of highly radioactive and toxic liquids and sludge. New skills were needed by the workforce to accomplish this mission. By 1995, workers were in the process of getting the facilities in a safe condition and it became obviousmore » improvements were needed in their tools, equipment and work practices. The Hanford ALARA Program looked good on paper, but did little to help contractors that were working in the field. The Radiological Control Director decided that the ALARA program needed to be upgraded and a significant improvement could be made if workers had a place they could visit that had samples of the latest technology and could talk to experienced personnel who have had success doing D and D work. Two senior health physics personnel who had many years experience in doing radiological work were chosen to obtain tools and equipment from vendors and find a location centrally located on the Hanford site. Vendors were asked to loan their latest tools and equipment for display. Most vendors responded and the Hanford ALARA Center of Technology opened on October 1, 1996. Today, the ALARA Center includes a classroom for conducting training and a mockup area with gloveboxes. Two large rooms have a containment tent, several glove bags, samples of fixatives/expandable foam, coating displays, protective clothing, heat stress technology, cutting tools, HEPA filtered vacuums, ventilation units, pumps, hydraulic wrenches, communications equipment, shears, nibblers, shrouded tooling, and several examples of innovative tools developed by the Hanford facilities. See Figures I and II. The ALARA Center staff routinely researches and tests new technology, sponsor vendor demonstrations, and redistribute tools, equipment and temporary shielding that may not be needed at one facility to another facility that needs it. The ALARA Center staff learns about new technology in several ways. This includes past radiological work experience, interaction with vendors, lessons learned, networking with other DOE sites, visits to the Hanford Technical Library, attendance at off-site conferences and ALARA Workshops. Personnel that contact the ALARA Center for assistance report positive results when they implement the tools, equipment and work practices recommended by the ALARA Center staff. This has translated to reduced exposure for workers and reduced the risk of contamination spread. For example: using a hydraulic shear on one job saved 16 Rem of exposure that would have been received if workers had used saws-all tools to cut piping in twenty-nine locations. Currently, the ALARA Center staff is emphasizing D and D techniques on size-reducing materials, decontamination techniques, use of remote tools/video equipment, capture ventilation, fixatives, using containments and how to find lessons learned. The ALARA Center staff issues a weekly report that discusses their interaction with the workforce and any new work practices, tools and equipment being used by the Hanford contractors. Distribution of this weekly report is to about 130 personnel on site and 90 personnel off site. This effectively spreads the word about ALARA throughout the DOE Complex. DOE EM-23, in conjunction with the D and D and Environmental Restoration work group of the Energy Facility Contractors Organization (EFCOG) established the Hanford ALARA Center as the D and D Hotline for companies who have questions about how D and D work is accomplished. The ALARA Center has become a resource to the nuclear industry and routinely helps contractors at other DOE Sites, power reactors, DOD sites, and sites in England, Europe and Indonesia. Other ALARA Centers are located at the Savannah River Site and Los Alamos National Lab.« less

  6. KSC-2014-4206

    NASA Image and Video Library

    2014-10-07

    CAPE CANAVERAL, Fla. – Groundbreaking for the new Central Campus will take place in the Industrial Area at NASA's Kennedy Space Center in Florida. Kennedy Center Director Bob Cabana welcomes members of the media and guests to the ceremony. To his right is Nancy Bray, director of Kennedy's Center Operations Directorate. To his left is Kirk Hazen, southeast district manager and vice president of Hensel Phelps, the construction contractor. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees. Photo credit: NASA/Kim Shiflett

  7. SRB Processing Facilities Media Event

    NASA Image and Video Library

    2016-03-01

    Members of the news media view forward booster segments (painted green) for NASA’s Space Launch System rocket boosters inside the Booster Fabrication Facility (BFF) at NASA’s Kennedy Space Center in Florida. Orbital ATK is a contractor for NASA’s Marshall Space Flight Center in Alabama, and operates the BFF to prepare aft booster segments and hardware for the SLS rocket boosters. The SLS rocket and Orion spacecraft will launch on Exploration Mission-1 in 2018. The Ground Systems Development and Operations Program is preparing the infrastructure to process and launch spacecraft for deep-space missions and the journey to Mars.

  8. KSC Headquarters Building Groundbreaking Ceremony

    NASA Image and Video Library

    2014-10-07

    Groundbreaking for the new Central Campus will take place in the Industrial Area at NASA's Kennedy Space Center in Florida. A scale model of the new facility and landscaping is on display for the ceremony. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees.

  9. KSC-00pp0503

    NASA Image and Video Library

    2000-04-14

    Center Director Roy Bridges (left) dons protective apron, gloves and face shield before the "ribbon-breaking" to open the new Cryogenic Testbed Facility. Part of the normal ceremonial ribbon was replaced with plastic tubing and frozen in liquid nitrogen for the event. Bridges hit the tubing with a small hammer to break it. The Cryogenics Testbed was built to provide cryogenics engineering development and testing services to meet the needs of industry. It will also support commercial, government and academic customers for technology development initiatives on the field of cryogenics. The facility is jointly managed by NASA and Dynacs Engineering Co. , NASA/SC's Engineering Development contractor

  10. KSC-00pp0504

    NASA Image and Video Library

    2000-04-14

    Center Director Roy Bridges (left), wearing protective apron, gloves and face shield, watches as liquid nitrogen is poured into a container to freeze the plastic tubing for a special "ribbon-breaking" to open the new Cryogenic Testbed Facility. Bridges hit the section of tubing with a small hammer to break it. The Cryogenics Testbed was built to provide cryogenics engineering development and testing services to meet the needs of industry. It will also support commercial, government and academic customers for technology development initiatives on the field of cryogenics. The facility is jointly managed by NASA and Dynacs Engineering Co. , NASA/SC's Engineering Development contractor

  11. KSC-00pp0505

    NASA Image and Video Library

    2000-04-14

    A shower of frozen plastic signifies the successful breaking of the ceremonial "ribbon" at the opening of the new Cryogenic Testbed Facility. Part of the normal ribbon was replaced with plastic tubing and frozen in liquid nitrogen for the event. Bridges hit the tubing with a small hammer to break it. The Cryogenics Testbed was built to provide cryogenics engineering development and testing services to meet the needs of industry. It will also support commercial, government and academic customers for technology development initiatives on the field of cryogenics. The facility is jointly managed by NASA and Dynacs Engineering Co. , NASA/SC's Engineering Development contractor

  12. KSC-00pp0506

    NASA Image and Video Library

    2000-04-14

    Center Director Roy Bridges (center) is congratulated for the successful breaking of the ceremonial "ribbon" and the opening of the new Cryogenic Testbed Facility. Part of the normal ribbon was replaced with plastic tubing and frozen in liquid nitrogen for the event. Bridges hit the tubing with a small hammer to break it. The Cryogenics Testbed was built to provide cryogenics engineering development and testing services to meet the needs of industry. It will also support commercial, government and academic customers for technology development initiatives on the field of cryogenics. The facility is jointly managed by NASA and Dynacs Engineering Co. , NASA/SC's Engineering Development contractor

  13. Best Practices for Optimizing DoD Contractor Safety and Occupational Health Program Performance

    DTIC Science & Technology

    2012-12-01

    such as Accident Prevention Plan (APP), Activity Hazard Analysis (AHA), Quality Assurance Surveillance Plans (QASP), etc. Contract administration...technology support, medical , and maintenance of equipment and facilities. The DoD Guidebook for the Acquisition of Services, provides acquisition...OSHA regulations and perform in accordance with an applicable accident prevention program that complies with State and Federal requirements. The

  14. Assessment of Electrical Safety in Afghanistan

    DTIC Science & Technology

    2009-07-24

    effectiveness of command efforts to ensure the electrical safety of Department of Defense occupied and constructed facilities in Afghanistan. We...March 31, 2009, we announced the Assessment of Electrical Safety in Afghanistan. The objective of this assessment was to review the effectiveness of...used contractors to review and identify electrical deficiencies to include life, health , and safety issues at FOBs. According to TF POWER

  15. U.S. Army Natick Soldier Research, Development & Engineering Center Testing Facilities And Equipment. Second Edition

    DTIC Science & Technology

    2011-04-01

    30 Freeze Dryer ................................................. 30 High-Pressure Processing ............................... 30 Microwave Digestive...PP1 Power Platform Energy Analyzer ..... 41 Quintox Gas Combustion Analyzer .................... 41 FLIR Systems SC2000 Thermacam Handheld IR ...electronically directly to the contractor or printed on plotter paper , oak tag, or on CD. alloy steel, stainless steel, aluminum, copper and copper alloys

  16. REDUCED PROTECTIVE CLOTHING DETERMINATIONS

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    BROWN, R.L.

    2003-06-13

    This technical basis document defines conditions where reduced protective clothing can be allowed, defines reduced protective clothing, and documents the regulatory review that determines the process is compliant with the Tank Farm Radiological Control Manual (TFRCM) and Title 10, Part 835, of the Code of Federal Regulations (10CFR835). The criteria, standards, and requirements contained in this document apply only to Tank Farm Contractor (TFC) facilities.

  17. Infrared Inspection of New Roofs.

    DTIC Science & Technology

    1982-12-01

    USA Cold Regions Research and Engineering Laboratory, unpublished report prepared for the Directorate of Facilities Engineering, Fort Devens , Mass...SECURITY CLASSIFICATION OF THIS PAGE (When Date Entered) READ INSTRUCTIONSREPORT DOCUMENTATION PAGE BEFORE COMPLETING FORM I. REPORT NUMBER 2. GOVT...period then the contractor will become obligated to repair it rather than the owner having to pursue expensive remedial measures a few years later

  18. SRS SWPF Construction Completion

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Craig, Jack; Sheppard, Frank; Marks, Pam

    Now that construction is complete, DOE and construction contractor Parsons, are focusing on testing the Savannah River Site’s Salt Waste Processing Facility (SWPF) systems and training the workforce to operate the plant in preparation for the start of operations. Once in operation, the SWPF will significantly increase processing rates at SRS tank farms in an effort to empty the site’s high-level radioactive waste tanks.

  19. 2016 Energy Awareness Day

    NASA Image and Video Library

    2016-10-20

    Cory Taylor, an energy and water conservation specialist at Kennedy Space Center, absorbs information from Mark Gonzalez, a sales engineer with MC2 during Energy Awareness Day at the Multi-Function Facility on Oct. 20. Every third Thursday of October, civil servants, contractors and several energy utilities promote the awareness of our sustainability goals at Kennedy Space Center and at home. Photo credit: Cory Huston

  20. IMPLEMENTATION OF DEFENSE NUCLEAR FACILITY SAFETY BOARD RECOMMENDATION 2000-2 AT WIPP

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Jackson, K.; Wu, C.

    2002-02-26

    The Defense Nuclear Safeties Board (DNFSB) issued Recommendation 2000-2 on March 8, 2000, concerning the degrading conditions of vital safety systems, or systems important to nuclear safety, at DOE sites across the nation. The Board recommended that the DOE take action to assess the condition of its nuclear systems to ensure continued operational readiness of vital safety systems that are important for safely accomplishing the DOE's mission. To verify the readiness of vital safety systems, a two-phased approach was established. Phase I consisted of a qualitative assessment to approved criteria of the defined vital safety systems by operating contractor personnel,more » overseen by Federal field office personnel. Based on Phase I Assessment results, vital safety systems with significant deficiencies would be further assessed in Phase II, a more extensive quantitative assessment, by a contractor and Federal team, using a second set of criteria. In addition, Defense Nuclear Facility Safety Board Recommendation 2000-2 concluded that the degradation of confinement ventilation systems was of major concern, and issued a separate set of criteria to perform a Phase II Assessment on confinement ventilation systems.« less

  1. Design and construction of the Discovery Channel Telescope enclosure

    NASA Astrophysics Data System (ADS)

    Marshall, Heather K.; Teran, Jose U.; Bond, Kevin

    2010-07-01

    The Discovery Channel Telescope (DCT) is a project of Lowell Observatory, undertaken with support from Discovery Communications, Inc., to design and construct a 4-meter class telescope and support facility on a site approximately 40 miles southeast of Flagstaff, Arizona. The Discovery Channel Telescope Enclosure was completed in November, 2009. The DCT Enclosure is an octagonal steel structure with insulated composite panel skin. The structure rotates on sixteen compliant bogie assemblies attached to the stationary facility. The shutter is composed of two independently actuated, bi-parting structures that provide a viewing aperture. To improve seeing, the skin is covered with adhesive aluminum foil tape and the enclosed observing area is passively ventilated via rollup doors. The observing area can also be actively ventilated using a downdraft fan, and there are provisions for upgrades to active air conditioning. The enclosure also includes operational equipment such as a bridge crane, personnel lift, and access platforms. This paper discusses some of the design trades as well as the construction challenges and lessons learned by the DCT Project, its designer M3 Engineering and Technology Corporation (M3), and its general contractor, Building and Engineering Contractors, Southwest (BEC Southwest).

  2. 3718-F Alkali Metal Treatment and Storage Facility Closure Plan

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    None

    Since 1987, Westinghouse Hanford Company has been a major contractor to the U.S. Department of Energy-Richland Operations Office and has served as co-operator of the 3718-F Alkali Metal Treatment and Storage Facility, the waste management unit addressed in this closure plan. The closure plan consists of a Part A Dangerous waste Permit Application and a RCRA Closure Plan. An explanation of the Part A Revision (Revision 1) submitted with this document is provided at the beginning of the Part A section. The closure plan consists of 9 chapters and 5 appendices. The chapters cover: introduction; facility description; process information; wastemore » characteristics; groundwater; closure strategy and performance standards; closure activities; postclosure; and references.« less

  3. Aerial Views of KSC

    NASA Image and Video Library

    2003-07-23

    The Space Experiment Research and Processing Laboratory (SERPL) is a major new research facility under construction at the International Space Research Park located on KSC. At right is S.R. 3, which leads into the Center from Merritt Island. Being developed as a partnership between KSC and the State of Florida, SERPL will serve as the primary gateway to the International Space Station for science experiments and as a world-class home to ground-based investigations in fundamental and applied biological science. NASA’s life sciences contractor will be the primary tenant of the facility, leasing space to conduct flight experiment processing and NASA-sponsored research. About 20 percent of the facility will be available for use by Florida’s university researchers through the Florida Space Research Institute.

  4. Paducah Site annual report for 1995

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Belcher, G.

    1997-01-01

    The Paducah Gaseous Diffusion Plant, located in McCracken County, Kentucky, has been producing enriched uranium since 1952. In July 1993, the US department of Energy (DOE) leased the production areas of the site to the US Enrichment Corporation (USEC). A new subsidiary of Lockheed Martin Corporation, Lockheed Martin Utility Services, manages the leased facilities for USEC. DOE maintains responsibility for the environmental restoration, waste management, and enrichment facilities activities at the plant through its management contractor, Lockheed Martin Energy Systems. The purpose of this document is to summarize calendar year 1995 environmental monitoring activities for DOE activities at the Paducahmore » Site. DOE requires all of its facilities to conduct and document such activities annually. This report does not include USEC environmental activities.« less

  5. Using Facility Condition Assessments to Identify Actions Related to Infrastructure

    NASA Technical Reports Server (NTRS)

    Rubert, Kennedy F.

    2010-01-01

    To support cost effective, quality research it is essential that laboratory and testing facilities are maintained in a continuous and reliable state of availability at all times. NASA Langley Research Center (LaRC) and its maintenance contractor, Jacobs Technology, Inc. Research Operations, Maintenance, and Engineering (ROME) group, are in the process of implementing a combined Facility Condition Assessment (FCA) and Reliability Centered Maintenance (RCM) program to improve asset management and overall reliability of testing equipment in facilities such as wind tunnels. Specific areas are being identified for improvement, the deferred maintenance cost is being estimated, and priority is being assigned against facilities where conditions have been allowed to deteriorate. This assessment serves to assist in determining where to commit available funds on the Center. RCM methodologies are being reviewed and enhanced to assure that appropriate preventive, predictive, and facilities/equipment acceptance techniques are incorporated to prolong lifecycle availability and assure reliability at minimum cost. The results from the program have been favorable, better enabling LaRC to manage assets prudently.

  6. The DOE/DHHS memorandum of understanding: The DOE perspective

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Goldsmith, R.

    1991-01-01

    On March 27, 1990, Secretary James D. Watkins established an Office of Health under the Assistant Secretary for Environment, Safety and Health. All epidemiologic activities throughout the department were consolidated into this office as part of an Office of Epidemiology and Health Surveillance (OEHS) with specific responsibilities for occupational and community health surveillance. The mission and functions of the OEHS include the conduct of epidemiologic studies at US Department of Energy (DOE) facilities, nearby communities, and other populations. These studies comprise retrospective mortality studies of DOE contractor workers, hypothesis-generating studies related to the potential health effects of energy production andmore » use, ecologic studies of off-site populations, quick-response investigations of suspected disease clusters, and others as needed. In addition, OEHS is responsible for providing procedures, technical support, and other resources for the conduct of DOE-sponsored epidemiologic research studies to be managed outside of DOE, including analytic studies to be managed by the Department of Health and Human Service (HHS) under a memorandum of understanding (MOU), dose-reconstruction studies, and studies related to DOE facilities to be conducted through state health departments.« less

  7. DOE Office of Scientific and Technical Information (OSTI.GOV)

    Agogino, Karen; Sanchez, Rebecca

    Tonopah Test Range (TTR) in Nevada and Kauai Test Facility (KTF) in Hawaii are government-owned, contractor-operated facilities operated by Sandia Corporation (Sandia), a wholly owned subsidiary of Lockheed Martin Corporation. The U.S. Department of Energy (DOE)/National Nuclear Security Administration (NNSA), through the Sandia Site Offi ce (SSO), in Albuquerque, NM, administers the contract and oversees contractor operations at TTR and KTF. Sandia manages and conducts operations at TTR in support of the DOE/NNSA’s Weapons Ordnance Program and has operated the site since 1957. Washington Group International subcontracts to Sandia in administering most of the environmental programs at TTR. Sandia operatesmore » KTF as a rocket preparation launching and tracking facility. This Annual Site Environmental Report (ASER) summarizes data and the compliance status of the environmental protection and monitoring program at TTR and KTF through Calendar Year (CY) 2007. The compliance status of environmental regulations applicable at these sites include state and federal regulations governing air emissions, wastewater effluent, waste management, terrestrial surveillance, and Environmental Restoration (ER) cleanup activities. Sandia is responsible only for those environmental program activities related to its operations. The DOE/NNSA/Nevada Site Offi ce (NSO) retains responsibility for the cleanup and management of ER TTR sites. Currently, there are no ER Sites at KTF. Environmental monitoring and surveillance programs are required by DOE Order 450.1, Environmental Protection Program (DOE 2007a) and DOE Manual 231.1-1A, Environment, Safety, and Health Reporting Manual (DOE 2007).« less

  8. Energy, Power and Thermal Research Overview

    DTIC Science & Technology

    2010-09-01

    Research Overview Rick Fingers, Ph.D. Chief Energy/Power/Thermal Division Propulsion Directorate Air Force Research ... Air Vehicles Sensors AFOSR 5 AFRL People & Facilities • 10 Major R&D Sites across US • 40 Sites World-Wide • $40B Real Property & Capital throughout... AFRL • 5,764 Government Employees – 4570 Air Force Civilian – 1194 Military • 3,844 Onsite Contractors 6 Propulsion Directorate’s Strategic

  9. Audit of Potable and Nonpotable Water in Iraq

    DTIC Science & Technology

    2008-03-07

    including hepatitis, giardiasis, and typhoid fever . Although there was no way to determine whether water provided by the contractors and military water... discovered that KBR personal hygiene facilities at Camp Q-West. KBR distributed the chlorinated wastewat rsonnel. KBR did not monitor or record the... discover resulted in KBR superchlorinating e y procedures to execute if water became unsafe. We documented three examples of potential for

  10. Environmental Compliance Assessment System (ECAS)

    DTIC Science & Technology

    1993-09-01

    hazardous waste onsite? How and where? 8. Do satellite/offpost facilitiesminstallations (i.e., USARCs) transport hazardous wastes to the installation...Contractor ? In-house personnel_ ? 3. Is waste transported off-installation for disposal: a. In landfills? b. In incinerators? c. Transfer stations? d...Does the installation dispose of PCBs or PCB items at the installation? 4. Does the facility transport PCBs? 5. Is there a working management system

  11. Vying for control of CHAMPUS funds.

    PubMed

    Kenkel, P J

    1991-04-08

    Advocating a "coordinated care" approach to healthcare for military retirees and their dependents, the Pentagon is hoping for a victory in its battle with civilian managed-care contractors for control of CHAMPUS funds. But coordinated care, which would give military hospital commanders the added responsibility of overseeing healthcare spending outside military facilities, has drawn fire from critics who say commanders lack the expertise to run such a program.

  12. Energy Efficient Window Retrofits in Historic Facilities

    DTIC Science & Technology

    2006-01-01

    possible, protect and maintain existing building fabric (Ivy, 1992). Barista (2001) states that during a time when interest in the restoration of...are the eyes of a building ( Barista , 2001). Certainly windows are an element, which if replaced or altered unsympathetically, will do the most to alter...problem area is to assure that retrofitting measures do not create moisture related deterioration problems ( Barista , 2001). Finally contractors and

  13. PBF Cooling Tower. Hot deck of Cooling Tower with fan ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    PBF Cooling Tower. Hot deck of Cooling Tower with fan motors in place. Fan's propeller blades (not in view) rotate within lower portion of vents. Inlet pipe is a left of view. Contractor's construction buildings in view to right. Photographer: Larry Page. Date: June 30, 1969. INEEL negative no. 69-3781 - Idaho National Engineering Laboratory, SPERT-I & Power Burst Facility Area, Scoville, Butte County, ID

  14. Health Care Provided by Military Treatment Facilities to Contractors in Southwest Asia

    DTIC Science & Technology

    2009-05-04

    UNIT NUMBER 7. PERFORMING ORGANIZATION NAME(S) AND ADDRESS(ES) Department of Defense Inspector General,ODIG-AUD,400 Army Navy Drive,Arlington,VA...Department of Defense Inspector General 400 Army Navy Drive (Room 801) Arlington, VA 22202-4704 Acronyms ASD(HA...Central Command USD(AT&L) Under Secretary of Defense (Acquisition, Technology, and Logistics) INSPECTOR GENERAL DEPARTMENT OF DEFENSE 400 ARMY NAVY

  15. Meteorological support for space operations: Review and recommendations

    NASA Technical Reports Server (NTRS)

    1988-01-01

    The current meteorological support provided to NASA by NOAA, Air Weather Service, and other contractors is reviewed and suggestions are offered for its improvement. These recommendations include improvement in NASA's internal management organizational structure that would accommodate continued improvement in operational weather support, installation of new observing systems, improvement in analysis and forecasting procedures, and the establishment of an Applied Research and Forecasting Facility.

  16. Program Direction FY 2017 Budget At-A-Glance

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    None

    2016-03-01

    Program Direction enables EERE to maintain and support a world-class federal workforce to accomplish its mission of creating and sustaining American leadership in the sustainable transportation, renewable power, and energy efficiency sectors. The FY 2017 Program Direction budget request provides resources for program and project management, administrative support, contract administration, human capital management, headquarters and field site non-laboratory facilities and infrastructure, and contractor support.

  17. KSC-04PD-0006

    NASA Technical Reports Server (NTRS)

    2004-01-01

    KENNEDY SPACE CENTER, FLA. -- In the Space Life Sciences Lab, Lanfang Levine, with Dynamac Corp., transfers material into a sample bottle for analysis. She is standing in front of new equipment in the lab that will provide gas chromatography and mass spectrometry. The equipment will enable analysis of volatile compounds, such as from plants. The 100,000 square-foot facility houses labs for NASAs ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASAs Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASAs Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

  18. Doing your homework

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Burr, M.T.

    1990-04-01

    Building a successful resource recovery plant requires the best technology, management and administration. But even when all the right homework is done and the best planning and design is carried out, the idea of a waste burning facility is difficult to sell to a community - especially during an era marked by not-in-my-backyard sentiment. In addition to negotiating the hurdles involved with site procurement, contractor selection, financing, and compliance with applicable laws, developers of resource recovery facilities must overcome negative popular sentiment. In Florida, all these tasks fall within the jurisdiction of the Solid Waste Authority (SWA) of Palm Beachmore » County, which facilitated the construction of the North County Regional Resource Recovery Facility. SWA built the facility as a showpiece, in hopes that other Florida counties also adopt resource recovery as an answer to their waste management problems. The history of the project and its current status are described.« less

  19. Contractor assistance in highway maintenance : state-of-the-art evaluation.

    DOT National Transportation Integrated Search

    1980-01-01

    The purpose of this study was to perform a state-of-the art evaluation of contractor assistance in Virginia's highway maintenance. The study revealed that expenditures for contractor assistance accounted for 2.79% of the total expenditure on ordinary...

  20. Calendar Year 2013 Annual Site Environmental Report for Sandia National Laboratories, Albuquerque, New Mexico

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Griffith, Stacy

    2014-09-01

    Sandia National Laboratories, New Mexico is a government-owned/contractor-operated facility. Sandia Corporation, a wholly owned subsidiary of Lockheed Martin Corporation, manages and operates the laboratory for the U.S. Department of Energy (DOE), National Nuclear Security Administration (NNSA). The DOE/NNSA, Sandia Field Office administers the contract and oversees contractor operations at the site. This annual report summarizes data and the compliance status of Sandia Corporation’s sustainability, environmental protection, and monitoring programs through December 31, 2013. Major environmental programs include air quality, water quality, groundwater protection, terrestrial surveillance, waste management, pollution prevention, environmental restoration, oil and chemical spill prevention, and implementation of themore » National Environmental Policy Act. Environmental monitoring and surveillance programs are required by DOE Order 231.1B, Environment, Safety, and Health Reporting (DOE 2012).« less

  1. KSC Headquarters Building Groundbreaking Ceremony

    NASA Image and Video Library

    2014-10-07

    Groundbreaking for the new Central Campus took place in the Industrial Area at NASA's Kennedy Space Center in Florida. Kennedy Center Director Bob Cabana speaks to members of the media and guests during the ceremony. Behind Cabana is Nancy Bray, director of Kennedy's Center Operations Directorate. From far left, are Steve Belflower, vice president of HuntonBrady Architects of Orlando, and Kirk Hazen, southeast district manager and vice president of Hensel Phelps, the construction contractor. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees.

  2. KSC Headquarters Building Groundbreaking Ceremony

    NASA Image and Video Library

    2014-10-07

    Groundbreaking for the new Central Campus took place in the Industrial Area at NASA's Kennedy Space Center in Florida. Kirk Hazen, southeast district manager and vice president of Hensel Phelps, the construction contractor, speaks to members of the media and guests during the groundbreaking ceremony. Behind him is Nancy Bray, director of Kennedy's Center Operations Directorate. To his right is Kennedy Center Director Bob Cabana. To his left is Steve Belflower, vice president of HuntonBrady Architects of Orlando. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees.

  3. KSC-2014-4207

    NASA Image and Video Library

    2014-10-07

    CAPE CANAVERAL, Fla. – Groundbreaking for the new Central Campus took place in the Industrial Area at NASA's Kennedy Space Center in Florida. Kennedy Center Director Bob Cabana speaks to members of the media and guests during the ceremony. Behind Cabana is Nancy Bray, director of Kennedy's Center Operations Directorate. From far left, are Steve Belflower, vice president of HuntonBrady Architects of Orlando, and Kirk Hazen, southeast district manager and vice president of Hensel Phelps, the construction contractor. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees. Photo credit: NASA/Kim Shiflett

  4. KSC Headquarters Building Groundbreaking Ceremony

    NASA Image and Video Library

    2014-10-07

    Groundbreaking for the new Central Campus took place in the Industrial Area at NASA's Kennedy Space Center in Florida. Kennedy Center Director Bob Cabana speaks to members of the media and guests during the groundbreaking ceremony. To his right is Nancy Bray, director of Kennedy's Center Operations Directorate. From far left, are Steve Belflower, vice president of HuntonBrady Architects of Orlando, and Kirk Hazen, southeast district manager and vice president of Hensel Phelps, the construction contractor. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees.

  5. KSC Headquarters Building Groundbreaking Ceremony

    NASA Image and Video Library

    2014-10-07

    Groundbreaking for the new Central Campus took place in the Industrial Area at NASA's Kennedy Space Center in Florida. Nancy Bray, director of Kennedy's Center Operations Directorate, speaks to members of the media and guests during the ceremony. To her right is Kennedy Center Director Bob Cabana. From far left, are Steve Belflower, vice president of HuntonBrady Architects of Orlando, and Kirk Hazen, southeast district manager and vice president of Hensel Phelps, the construction contractor. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees.

  6. KSC Headquarters Building Groundbreaking Ceremony

    NASA Image and Video Library

    2014-10-07

    Groundbreaking for the new Central Campus took place in the Industrial Area at NASA's Kennedy Space Center in Florida. Steve Belflower, vice president of HuntonBrady Architects of Orlando, speaks to members of the media and guests during the groundbreaking ceremony. Behind him is Nancy Bray, director of Kennedy's Center Operations Directorate. To his right is Kennedy Center Director Bob Cabana. To his left is Kirk Hazen, southeast district manager and vice president of Hensel Phelps, the construction contractor. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees.

  7. INDEPENDENT TECHNICAL ASSESSMENT OF MANAGEMENT OF STORMWATER AND WASTEWATER AT THE SEPARATIONS PROCESS RESEARCH UNIT (SPRU) DISPOSITION PROJECT, NEW YORK

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Abitz, R.; Jackson, D.; Eddy-Dilek, C.

    2011-06-27

    The U.S. Department of Energy (DOE) is currently evaluating the water management procedures at the Separations Process Research Unit (SPRU). The facility has three issues related to water management that require technical assistance: (1) due to a excessive rainfall event in October, 2010, contaminated water collected in basements of G2 and H2 buildings. As a result of this event, the contractor has had to collect and dispose of water offsite; (2) The failure of a sump pump at a KAPL outfall resulted in a Notice of Violation issued by the New York State Department of Environment and Conservation (NYSDEC) andmore » subsequent Consent Order. On-site water now requires treatment and off-site disposition; and (3) stormwater infiltration has resulted in Strontium-90 levels discharged to the storm drains that exceed NR standards. The contractor has indicated that water management at SPRU requires major staff resources (at least 50 persons). The purpose of this review is to determine if the contractor's technical approach warrants the large number of staff resources and to ensure that the technical approach is compliant and in accordance with federal, state and NR requirements.« less

  8. Demonstration of geophysical methods for burial ground geophysical characterization study at the DOE Savannah River site

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Hasbrouck, J.C.; MacLean, H.D.; Geotech, R.

    1996-11-01

    Rust Geotech, operating contractor at the U.S. Department of Energy Grand Junction Projects Office (DOE-GJPO), conducted a demonstration of the trench boundary and large-object location capabilities of five nonintrusive geophysical methods in the Low-Level Radioactive Waste Disposal Facility (LLRWDF) at the DOE Savannah River Site (SRS). The plan for Resource Conservation and Recovery Act (RCRA) closure of the SRS LLRWDF specifies inplace compaction of {open_quotes}B-25{close_quotes} metal boxes containing low-level radioactive wastes. The boxes are buried in Engineered Low-Level Trenches (ELLTs) at the facility. To properly guide and control the compaction operation, the coordinates of the trench boundaries must be determinedmore » to an accuracy within 5 feet and the outer edges of the metal boxes in the trenches must be determined to within 2 feet.« less

  9. Pilot-based assessment of the economics of recycling construction demolition waste.

    PubMed

    Srour, Issam M; Chehab, Ghassan R; El-Fadel, Mutasem; Tamraz, Sandy

    2013-11-01

    The significant amount of waste generated from construction demolition has become a chronic problem in many developing countries. Using data obtained from demolition contractors and various other sources, this paper proposes a framework for proper handling of construction demolition waste (CDW) to serve as a decision support tool in countries suffering from the lack of national CDW management guidelines. The framework is then demonstrated through a case study in the city of Beirut, Lebanon, and a sensitivity analysis is carried out to examine the economic feasibility of developing a recycling facility. The analysis showed that in order for a facility to be feasible, a gate fee should be charged in the presence of a market for recycled aggregates. The results confirm the significance of instigating and implementing legislation to control illegal dumping, constructing, and managing engineered landfills, and establishing markets for recycled CDW.

  10. OSHA to inspect hospitals, medical clinics for use of safer needles. Occupational Safety and Health Administration.

    PubMed

    1999-11-26

    The Occupational Safety and Health Administration (OSHA) has notified compliance officers of its intention to start imposing sanctions against health care facilities that do not use safe-needle devices. OSHA also said that facilities need to conduct yearly audits of their bloodborne pathogen programs, and must integrate new technologies wherever possible to protect their employees from exposure. Facilities affected include hospitals, home health service organizations, employment agencies, independent health care professionals, and independent contractors. About 800,000 hospital workers are accidentally punctured by needles each year. HIV is present in about 2 percent of those cases, but only a small number of workers actually contract the virus. The directive is available on the OSHA web site, and contact information is provided.

  11. Westinghouse, DOE see apples, oranges in IG staffing report

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Lobsenz, G.

    1994-03-01

    The operator of the Energy Department's Savannah River weapons plant has at least 1,800 more employees than it needs, and could save $400 million over a five-year period by cutting its staff accordingly, a DOE inspector general study says. Most of the boat - 1,206 employees - was attributed to excessive numbers of managers, with the inspector general concluding that Westinghouse Savannah River Co. had roughly twice as many layers of management than two other DOE weapons contractors. The study also concluded that Westinghouse in fiscal year 1992 significantly understated its actual staffing levels in reports to DOE, failing tomore » disclose 1,765 full-time employees or the equivalent hours worked. Through such underreporting Westinghouse was able to [open quotes]circumvent staffing ceilings established by the department,[close quotes] the study added. Overall, DOE Inspector General John Layton said Westinghouse's staff levels substantially exceeded those needed for efficient operation of the South Carolina nuclear weapons facility. Layton based his analysis on efficiency standards attained by other DOE weapons plant contractors, such as Martin Marietta Energy Systems at DOE's Oak Ridge, Tenn., plant and EG G Rocky Flats, as well as widely utilized worker performance requirements used by the Navy and private sector companies that perform work similar to that done at Savannah River.« less

  12. SRB Processing Facilities Media Event

    NASA Image and Video Library

    2016-03-01

    The right-hand aft skirt, one part of the aft booster assembly for NASA’s Space Launch System solid rocket boosters, is in view in a processing cell inside the Booster Fabrication Facility (BFF) at NASA’s Kennedy Space Center in Florida. Orbital ATK is a contractor for NASA’s Marshall Space Flight Center in Alabama, and operates the BFF to prepare aft booster segments and hardware for the SLS rocket boosters. The SLS rocket and Orion spacecraft will launch on Exploration Mission-1 in 2018. The Ground Systems Development and Operations Program is preparing the infrastructure to process and launch spacecraft for deep-space missions and the journey to Mars.

  13. SRB Processing Facilities Media Event

    NASA Image and Video Library

    2016-03-01

    Inside the Booster Fabrication Facility (BFF) at NASA’s Kennedy Space Center in Florida, members of the news media photograph a frustrum that will be stacked atop a forward skirt for one of NASA’s Space Launch System (SLS) solid rocket boosters. Orbital ATK is a contractor for NASA’s Marshall Space Flight Center in Alabama, and operates the BFF to prepare aft booster segments and hardware for the SLS solid rocket boosters. The SLS rocket and Orion spacecraft will launch on Exploration Mission-1 in 2018. The Ground Systems Development and Operations Program is preparing the infrastructure to process and launch spacecraft on deep-space missions and the journey to Mars.

  14. KSC-2009-2311

    NASA Image and Video Library

    2009-03-26

    CAPE CANAVERAL, Fla. – The first Ares I-X motor segment is in the Rotation, Processing and Surge Facility at NASA's Kennedy Space Center in Florida. It is one of four reusable motor segments and nozzle exit cone shipped by the Ares I first-stage prime contractor Alliant Techsystems Inc. for final processing and integration in the facility. The booster used for the Ares I-X launch is being modified by adding new forward structures and a fifth segment simulator. The motor is the final hardware needed for the rocket's upcoming flight test this summer. The stacking operations are scheduled to begin in the Vehicle Assembly Building in April. Photo credit: NASA/Jim Grossmann

  15. Evolution of area access safety training required for gaining access to Space Shuttle launch and landing facilities

    NASA Technical Reports Server (NTRS)

    Willams, M. C.

    1985-01-01

    Assuring personnel and equipment are fully protected during the Space Shuttle launch and landing operations has been a primary concern of NASA and its associated contractors since the inception of the program. A key factor in support of this policy has been the area access safety training requirements for badging of employees assigned to work on Space Shuttle Launch and Facilities. This requirement was targeted for possible cost savings and the transition of physical on-site walkdowns to the use of television tapes has realized program cost savings while continuing to fully satisfy the area access safety training requirements.

  16. FFRRO Program Information

    EPA Pesticide Factsheets

    This asset includes information related to Cleanups at Federal Facilities. Information is provided about contaminated federal facility sites in specific communities, with access to technical fact sheets and tools and resources to help government agencies and their contractors fulfill cleanup obligations. EPA's federal facility information is easily accessible to ensure effective stakeholder involvement and accountability at federal facilities.Multiple federal statutes establish requirements for EPA and other federal agencies to protect health and the human environment through cleanups at Federal Facilities, including the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) of 1980, which was amended by the Superfund Amendments and Reauthorization Act (SARA) in 1986; the Defense Authorization Amendments and Base Realignment and Closure Acts (BRAC) of 1998 and the Defense Base Closure and Realignment Act of 1990; and the Resource Conservation and Recovery Act (RCRA), as amended by the Hazardous and Solid Waste Amendments of 1984 (HS WA) including Subtitle C (hazardous waste), Subtitle D (solid waste), Subtitle I (underground storage tanks), and Subtitle J (Medical Waste Tracking Act of 1988).

  17. Factors and values of willingness to pay for improved construction waste management--a perspective of Malaysian contractors.

    PubMed

    Begum, Rawshan Ara; Siwar, Chamhuri; Pereira, Joy Jacqueline; Jaafar, Abdul Hamid

    2007-01-01

    Malaysia is facing an increase in the generation of waste and of accompanying problems with the disposal of this waste. In the last two decades, extensive building and infrastructure development projects have led to an increase in the generation of construction waste material. The construction industry has a substantial impact on the environment, and its environmental effects are in direct relation to the quality and quantity of the waste it generates. This paper discusses general characteristics of the construction contractors, the contractors' willingness to pay (WTP) for improved construction waste management, determining factors which affect the amount of their willingness to pay, and suggestions and policy implications in the perspective of construction waste management in Malaysia. The data in this study is based on contractors registered with the construction industry development board (CIDB) of Malaysia. Employing the open ended contingent valuation method, the study assessed the contractors' average maximum WTP for improved construction waste management to be RM69.88 (1US$=3.6 RM) per tonne of waste. The result shows that the average maximum WTP is higher for large contractors than for medium and small contractors. The highest average maximum WTP value is RM88.00 for Group A (large contractors) RM78.25 for Group B (medium-size contractors) and RM55.80 for Group C (small contractors). One of the contributions of this study is to highlight the difference of CIDB registration grade in the WTP for improved construction waste management. It is found that contractors' WTP for improved waste collection and disposal services increases with the increase in contractors' current paid up capital. The identified factors and determinants of the WTP will assist the formulation of appropriate policies in addressing the construction waste problem in Malaysia and indirectly improve the quality of construction in the country.

  18. KSC-04PD-0008

    NASA Technical Reports Server (NTRS)

    2004-01-01

    KENNEDY SPACE CENTER, FLA. -- In the Space Life Sciences (SLS) Lab, Jan Bauer, with Dynamac Corp., weighs samples of onion tissue for processing in the elemental analyzer behind it. The equipment analyzes for carbon, hydrogen, nitrogen and sulfur. The 100,000 square-foot SLS houses labs for NASAs ongoing research efforts, microbiology/microbial ecology studies and analytical chemistry labs. Also calling the new lab home are facilities for space flight-experiment and flight-hardware development, new plant growth chambers, and an Orbiter Environment Simulator that will be used to conduct ground control experiments in simulated flight conditions for space flight experiments. The SLS Lab, formerly known as the Space Experiment Research and Processing Laboratory or SERPL, provides space for NASAs Life Sciences Services contractor Dynamac Corporation, Bionetics Corporation, and researchers from the University of Florida. NASAs Office of Biological and Physical Research will use the facility for processing life sciences experiments that will be conducted on the International Space Station. The SLS Lab is the magnet facility for the International Space Research Park at KSC being developed in partnership with Florida Space Authority.

  19. Petroleum and hazardous material releases from industrial facilities associated with Hurricane Katrina.

    PubMed

    Santella, Nicholas; Steinberg, Laura J; Sengul, Hatice

    2010-04-01

    Hurricane Katrina struck an area dense with industry, causing numerous releases of petroleum and hazardous materials. This study integrates information from a number of sources to describe the frequency, causes, and effects of these releases in order to inform analysis of risk from future hurricanes. Over 200 onshore releases of hazardous chemicals, petroleum, or natural gas were reported. Storm surge was responsible for the majority of petroleum releases and failure of storage tanks was the most common mechanism of release. Of the smaller number of hazardous chemical releases reported, many were associated with flaring from plant startup, shutdown, or process upset. In areas impacted by storm surge, 10% of the facilities within the Risk Management Plan (RMP) and Toxic Release Inventory (TRI) databases and 28% of SIC 1311 facilities experienced accidental releases. In areas subject only to hurricane strength winds, a lower fraction (1% of RMP and TRI and 10% of SIC 1311 facilities) experienced a release while 1% of all facility types reported a release in areas that experienced tropical storm strength winds. Of industrial facilities surveyed, more experienced indirect disruptions such as displacement of workers, loss of electricity and communication systems, and difficulty acquiring supplies and contractors for operations or reconstruction (55%), than experienced releases. To reduce the risk of hazardous material releases and speed the return to normal operations under these difficult conditions, greater attention should be devoted to risk-based facility design and improved prevention and response planning.

  20. Guide to good practices for operations and administration updates through required reading

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Not Available

    1992-12-01

    The purpose of this Guide to Good Practices is to provide Department of Energy (DOE) contractors with information that can be used to validate and/or modify existing programs relative to Conduct of Operations. This Guide to Good Practices is part of a series of guides designed to enhance the guidelines set forth in DOE Order 5480. 19, Conduct of Operations Requirements for DOE Facilities.'' (JDB)

  1. Guide to good practices for operations and administration updates through required reading

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Not Available

    1992-12-01

    The purpose of this Guide to Good Practices is to provide Department of Energy (DOE) contractors with information that can be used to validate and/or modify existing programs relative to Conduct of Operations. This Guide to Good Practices is part of a series of guides designed to enhance the guidelines set forth in DOE Order 5480. 19, ``Conduct of Operations Requirements for DOE Facilities.`` (JDB)

  2. SRS SWPF Construction Completion

    ScienceCinema

    Craig, Jack; Sheppard, Frank; Marks, Pam

    2018-01-16

    Now that construction is complete, DOE and construction contractor Parsons, are focusing on testing the Savannah River Site’s Salt Waste Processing Facility (SWPF) systems and training the workforce to operate the plant in preparation for the start of operations. Once in operation, the SWPF will significantly increase processing rates at SRS tank farms in an effort to empty the site’s high-level radioactive waste tanks.

  3. Kennedy Space Center exercise program

    NASA Technical Reports Server (NTRS)

    Hoffman, Cristy

    1993-01-01

    The Kennedy Space Center (KSC) Fitness Program began in Feb. 1993. The program is managed by the Biomedical Operations and Research Office and operated by the Bionetics Corporation. The facilities and programs are offered to civil servants, all contractors, temporary duty assignment (TDY) participants, and retirees. All users must first have a medical clearance. A computer-generated check-in system is used to monitor participant usage. Various aspects of the program are discussed.

  4. Proceeding of the 1999 Particle Accelerator Conference. Volume 2

    DTIC Science & Technology

    1999-04-02

    anill repron the enorag cat manufacturing costs for such devices are significant and a pefnces acd after vari ouroeing steps drastic reduction in...cleanroom contractors, to find one that could meet our needs. Clean Air Technology 4 THEORY OF OPERATION ( CAT ) was able to provide a modular cleanroom...that would accommodate our unusual building geometry. CAT The facility improvements were designed to be used in provided the cleanroom, a local

  5. KSC-2010-5737

    NASA Image and Video Library

    2010-11-24

    CAPE CANAVERAL, Fla. -- The finishing touches of the Propellants North Administrative and Maintenance Facility begin to take place at NASA's Kennedy Space Center in Florida. Inside the green facility is window glazing and framing from the iconic firing rooms of Kennedy's Launch Control Center (LCC). The windows are set at the same orientation and angle as they were in the LCC, looking out toward Launch Complex 39. The facility also features sustainable flooring made of polished concrete and laminated bamboo, as well as a high-efficiency roof and walls. This is the facility's two-story administrative building, which will house managers, mechanics and technicians who fuel spacecraft at Kennedy. Next door is a single-story shop that will be used to store cryogenic fuel transfer equipment. The facility is striving to qualify for the U.S. Green Building Council’s Leadership in Energy and Environmental Design (LEED) Platinum certification, which is the highest of LEED ratings. The facility, set to be complete in December 2010, was designed for NASA by Jones Edmunds and Associates. H. W. Davis Construction is the construction contractor. Photo credit: NASA/Frankie Martin

  6. 20 MW Flywheel frequency regulation plant

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Arseneaux, James

    Hazle designed, built, commissioned, and operates a utility-scale 20 MW flywheel energy storage plant in Hazle Township, Pennsylvania (the Hazle Facility) using flywheel technology developed by its affiliate, Beacon Power, LLC (Beacon Power). The Hazle Facility provides frequency regulation services to the regional transmission organization, PJM Interconnection, LLC (PJM), through its participation in PJM’s Regulation Market (a market-based system for the purchase and sale of the Regulation ancillary service). The zero emission Hazle Facility is designed for a 20 year-life over which it is capable of performing at least 100,000 full depth of discharge cycles. To achieve its 20 MWmore » capacity, the Hazle Facility is comprised of two hundred of Beacon Power’s 100 kilowatt (kW)/25 kilowatt/hour (kWh) flywheels connected in parallel. The Hazle Facility can fully respond to a signal from PJM in less than 2 seconds. The Hazle facility was constructed in an economic development zone designated by the Commonwealth of Pennsylvania and its construction relied on local contractors and labor for completion.« less

  7. Orbital transfer vehicle launch operations study. Volume 1: Executive summary

    NASA Technical Reports Server (NTRS)

    1986-01-01

    The purpose was to use the operational experience at the launch site to identify, describe and quantify the operational impacts of the various configurations on the Kennedy Space Center (KSC) and/or space station launch sites. Orbital Transfer Vehicle (OTV) configurations are being developed/defined by contractor teams. Lacking an approved configuration, the KSC Study Team defined a Reference Configuration to be used for this study. This configuration then become the baseline for the identification of the facilities, personnel and crew skills required for processing the OTV in a realistic manner that would help NASA achieve the lowest possible OTV life cycle costs. As the study progressed, researchers' initial apraisal that the vehicle, when delivered, would be a sophisticated, state-of-the-art vehicle was reinforced. It would be recovered and reused many times so the primary savings to be gained would be in the recurring-cycle of the vehicle operations--even to the point where it would be beneficial to break from tradition and make a significant expenditure in the development of processing facilities at the beginning of the program.

  8. 43 CFR 404.24 - How will Reclamation determine whether it is cost-effective for me or my contractor to conduct...

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... is cost-effective for me or my contractor to conduct the appraisal investigation or feasibility study... investigation or feasibility study? Reclamation will take the following steps to determine whether it is cost-effective for you or your contractor to conduct the appraisal investigation or feasibility study: (a...

  9. NASA X-Ray Observatory Completes Tests Under Harsh Simulated Space Conditions

    NASA Astrophysics Data System (ADS)

    1998-07-01

    NASA's most powerful X-ray observatory has successfully completed a month-long series of tests in the extreme heat, cold, and airless conditions it will encounter in space during its five-year mission to shed new light on some of the darkest mysteries of the universe. The Advanced X-ray Astrophysics Facility was put through the rigorous testing as it was alternately heated and cooled in a special vacuum chamber at TRW Space and Electronics Group in Redondo Beach, Calif., NASA's prime contractor for the observatory. "Successful completion of thermal vacuum testing marks a significant step in readying the observatory for launch aboard the Space Shuttle in January," said Fred Wojtalik, manager of the Observatory Projects Office at NASA's Marshall Space Flight Center in Huntsville, Ala. "The observatory is a complex, highly sophisticated, precision instrument," explained Wojtalik. "We are pleased with the outcome of the testing, and are very proud of the tremendous team of NASA and contractor technicians, engineers and scientists that came together and worked hard to meet this challenging task." Testing began in May after the observatory was raised into the 60-foot thermal vacuum chamber at TRW. Testing was completed on June 20. During the tests the Advanced X-ray Astrophysics Facility was exposed to 232 degree heat and 195 degree below zero Fahrenheit cold. During four temperature cycles, all elements of the observatory - the spacecraft, telescope, and science instruments - were checked out. Computer commands directing the observatory to perform certain functions were sent from test consoles at TRW to all Advanced X-ray Astrophysics Facility components. A team of contractor and NASA engineers and scientists monitored and evaluated the results. Commands were also sent from, and test data monitored at, the Advanced X-ray Astrophysics Facility Operations Control Center in Cambridge, Mass., as part of the test series. The observatory will be managed and controlled from the Operations Control Center after launch. "As is usually the case, we identified a few issues to be resolved before launch," said Wojtalik. "Overall, however, the observatory performed exceptionally well." The observatory test team discovered a mechanical problem with one of the primary science instruments, the Imaging Spectrometer. A door protecting the instrument did not function when commanded by test controllers. "We do these tests to check and double check every aspect of satellite operation that could affect the ultimate success of the science mission," said Craig Staresinich, TRW Advanced X-ray Astrophysics Facility program manager. "Discovering a problem now is a success. Discovering a problem later, after launch, would be a failure." A team of NASA and contractor engineers are studying the mechanical problem and developing a plan to correct it. The instrument will be sent back to its builder, Lockheed-Martin Astronautics in Denver, Colo., where it will be repaired while the rest of the observatory continues other testing. This should still allow an on-time delivery of the observatory to NASA's Kennedy Space Center, Fla., in August, where it will be readied for launch in January. With a resolving power 10 times greater than previous X-ray telescopes, the new X-ray observatory will provide scientists with views of previously invisible X-ray sources, including black holes, exploding stars and interstellar gasses. The third of NASA's Great Observatories, it will join the Compton Gamma Ray Observatory and the Hubble Space Telescope in orbit. The Advanced X-ray Astrophysics Facility program is managed by the Marshall Center for the Office of Space Science, NASA Headquarters, Washington, D.C. TRW Space & Electronics Group is assembling the observatory and doing verification testing. The Advanced X-ray Astrophysics Facility Operations Control Center is operated by the Smithsonian Astrophysical Observatory. Using glass purchased from Schott Glaswerke, Mainz, Germany, the telescope's mirrors were built by Raytheon Optical Systems Inc., Danbury, Conn. The mirrors were coated by Optical Coating Laboratory, Inc., Santa Rosa, Calif., and assembled by EastmanKodak Co., Rochester, N.Y. The Advanced X-ray Astrophysics Facility Charge-Coupled Device Imaging Spectrometer was developed by Pennsylvania State University, University Park, Pa., and the Massachusetts Institute of Technology (MIT), Cambridge. One diffraction grating was developed by MIT, the other by the Space Research Organization Netherlands, Utrecht, Netherlands, in collaboration with the Max Planck Institute, Garching, Germany. The High Resolution Camera was built by the Smithsonian Astrophysical Observatory. Ball Aerospace & Technologies Corporation of Boulder, Colo., developed the aspect camera and the Science Instrument Module. Note to editors: Digital images to accompany this release are available via the World Wide Web at the following URL: http://chandra.harvard.edu/press/images.html

  10. Environmental monitoring handbook for coal conversion facilities

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Salk, M.S.; DeCicco, S.G.

    1978-05-01

    The primary objectives of the Department of Energy's (DOE) coal conversion program are to demonstrate the environmental acceptability, technical feasibility, and economic viability of various technologies for gaseous, liquid, and solid fuels from coal. The Environmental Monitoring Handbook for Coal Conversion Facilities will help accomplish the objective of environmental acceptability by guiding the planning and execution of socioeconomic and environmental monitoring programs for demonstration facilities. These programs will provide information adequate to (1) predict, insofar as is possible, the potential impacts of construction and operation of a coal conversion plant, (2) verify the occurrence of these or any other impactsmore » during construction and operation, (3) determine the adequacy of mitigating measures to protect the environment, (4) develop effluent source terms for process discharges, and (5) determine the effectiveness of pollution control equipment. Although useful in a variety of areas, the handbook is intended primarily for contractors who, as industrial partners with DOE, are building coal conversion plants. For the contractor it is a practical guide on (1) the methodology for developing site- and process-specific environmental monitoring programs, (2) state-of-the-art sampling and analytical techniques, and (3) impact analyses.To correspond to the phases of project activity, the subject matter is divided into four stages of monitoring: (1) a reconnaissance or synoptic survey, (2) preconstruction or baseline, (3) construction, and (4) operation, including process monitoring (prepared by Radian Corp., McLean, Va.). For each stage of monitoring, guidelines are given on socioeconomics, aquatic and terrestrial ecology, air quality and meteorology, surface and groundwater quality, geohydrology and soil survey, and surface water hydrology.« less

  11. Advanced X-Ray Astrophysics Facility Delivery Delayed

    NASA Astrophysics Data System (ADS)

    1997-12-01

    TRW Space and Electronics Group, Redondo Beach, CA, has notified NASA that it will be unable to deliver the Advanced X-ray Astrophysics Facility (AXAF) to NASA's Kennedy Space Center, FL, on June 1, 1998, as required by contract, because it has experienced delays in assembly and testing of the facility. TRW is NASA's prime contractor for the observatory. NASA and contractor officials met at NASA Headquarters in Washington, DC, this week to discuss the issue. While no new delivery date was agreed upon, the agency has directed TRW to develop a plan of action that would show how the contractor can minimize impact to the June 1 delivery. Although a delay in delivery could delay the launch, currently scheduled for August 1998 aboard Space Shuttle Columbia's STS-93 mission, and could result in additional program costs, the exact impact is not yet known. "The delay in delivery of the observatory is unfortunate," said Fred Wojtalik, NASA Marshall Space Flight Center observatory projects office manager in Huntsville, AL. "However, our first priority is to launch a world-class observatory which has been thoroughly tested and meets all requirements. We will work closely with TRW to ensure that happens." The delay is primarily due to TRW's difficulty in configuring and programming its Integrated Spacecraft Automated Test System to test the observatory before it is delivered to NASA. The Advanced X-ray Astrophysics Facility is expected to play a vital role in answering fundamental questions about the universe, including its age and size, and will probe the nature and amounts of so-called "dark matter," providing unique insight into one of nature's great puzzles. The observatory also will allow scientists to see and measure the details of hot gas clouds in clusters of galaxies; observe X-rays generated when stars are torn apart by the incredibly strong gravity around massive black holes in the centers of galaxies; and provide images that will help understand how exploding stars create and disperse many of the elements necessary for new stars, planets and life. The Marshall Space Flight Center manages development of the observatory for the Office of Space Science at NASA Headquarters. Made of glass purchased from Schott Glaswerke, Mainz, Germany, the telescope's mirrors were built by Hughes Danbury Optical Systems, Danbury, CT, and assembled by Eastman-Kodak Company, Rochester, NY. The science instruments are being integrated into the science instrument module at Ball Aerospace and Technologies Corporation, Boulder, CO, before being tested and shipped to TRW.

  12. KSC-2014-4211

    NASA Image and Video Library

    2014-10-07

    CAPE CANAVERAL, Fla. – Groundbreaking for the new Central Campus took place in the Industrial Area at NASA's Kennedy Space Center in Florida. Steve Belflower, vice president of HuntonBrady Architects of Orlando, speaks to members of the media and guests during the groundbreaking ceremony. Behind him is Nancy Bray, director of Kennedy's Center Operations Directorate. To his right is Kennedy Center Director Bob Cabana. To his left is Kirk Hazen, southeast district manager and vice president of Hensel Phelps, the construction contractor. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees. Photo credit: NASA/Kim Shiflett

  13. KSC-2014-4216

    NASA Image and Video Library

    2014-10-07

    CAPE CANAVERAL, Fla. – Groundbreaking for the new Central Campus took place in the Industrial Area at NASA's Kennedy Space Center in Florida. Kennedy Center Director Bob Cabana speaks to members of the media and guests during the groundbreaking ceremony. To his right is Nancy Bray, director of Kennedy's Center Operations Directorate. From far left, are Steve Belflower, vice president of HuntonBrady Architects of Orlando, and Kirk Hazen, southeast district manager and vice president of Hensel Phelps, the construction contractor. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees. Photo credit: NASA/Kim Shiflett

  14. KSC-2014-4210

    NASA Image and Video Library

    2014-10-07

    CAPE CANAVERAL, Fla. – Groundbreaking for the new Central Campus took place in the Industrial Area at NASA's Kennedy Space Center in Florida. Kirk Hazen, southeast district manager and vice president of Hensel Phelps, the construction contractor, speaks to members of the media and guests during the groundbreaking ceremony. Behind him is Nancy Bray, director of Kennedy's Center Operations Directorate. To his right is Kennedy Center Director Bob Cabana. To his left is Steve Belflower, vice president of HuntonBrady Architects of Orlando. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees. Photo credit: NASA/Kim Shiflett

  15. KSC-2014-4208

    NASA Image and Video Library

    2014-10-07

    CAPE CANAVERAL, Fla. – Groundbreaking for the new Central Campus took place in the Industrial Area at NASA's Kennedy Space Center in Florida. Nancy Bray, director of Kennedy's Center Operations Directorate, speaks to members of the media and guests during the ceremony. To her right is Kennedy Center Director Bob Cabana. From far left, are Steve Belflower, vice president of HuntonBrady Architects of Orlando, and Kirk Hazen, southeast district manager and vice president of Hensel Phelps, the construction contractor. Kennedy is transforming into a multi-user, 21st century spaceport supporting both commercial and government users and operations. Central Campus Phase I includes construction of a new Headquarters Building as one of the major components of the strategy. The new Headquarters Building will be a seven-story, 200,000-square-foot facility that will house about 500 NASA civil service and contractor employees. Photo credit: NASA/Kim Shiflett

  16. Nevada State plan; final approval determination. Occupational Safety and Health Administration (OSHA), U.S. Department of Labor. Final State plan approval--Nevada.

    PubMed

    2000-04-18

    This document amends OSHA's regulations to reflect the Assistant Secretary's decision granting final approval to the Nevada State plan. As a result of this affirmative determination under section 18(e) of the Occupational Safety and Health Act of 1970, Federal OSHA's standards and enforcement authority no longer apply to occupational safety and health issues covered by the Nevada plan, and authority for Federal concurrent jurisdiction is relinquished. Federal enforcement jurisdiction is retained over any private sector maritime employment, private sector employers on Indian land, and any contractors or subcontractors on any Federal establishment where the land is exclusive Federal jurisdiction. Federal jurisdiction remains in effect with respect to Federal government employers and employees. Federal OSHA will also retain authority for coverage of the United States Postal Service (USPS), including USPS employees, contract employees, and contractor-operated facilities engaged in USPS mail operations.

  17. DOE Office of Scientific and Technical Information (OSTI.GOV)

    Ward, Anderson; Basabilvazo, George T.

    The purpose of the Waste Isolation Pilot Plant (WIPP) Annual Site Environmental Report for 2016 (ASER) is to provide the information required by U.S. Department of Energy (DOE) Order 231.1B, Environment, Safety, and Health Reporting. The DOE Carlsbad Field Office (CBFO) and the management and operating contractor (MOC) maintain and preserve the environmental resources at the WIPP facility. DOE Order 231.1B; DOE Order 436.1, Departmental Sustainability; and DOE Order 458.1, Radiation Protection of the Public and the Environment, require that the affected environment at and near DOE facilities be monitored to ensure the safety and health of the public andmore » workers, and preservation of the environment. This report was prepared in accordance with DOE Order 231.1B, which requires DOE facilities to submit an ASER to the DOE Headquarters Chief Health, Safety, and Security Officer.« less

  18. Perceived barriers to utilizing maternal and neonatal health services in contracted-out versus government-managed health facilities in the rural districts of Pakistan.

    PubMed

    Riaz, Atif; Zaidi, Shehla; Khowaja, Asif Raza

    2015-03-06

    A number of developing countries have contracted out public health facilities to the Non-Government Organizations (NGOs) in order to improve service utilization. However, there is a paucity of in-depth qualitative information on barriers to access services as a result of contracting from service users' perspective. The objective of this study was to explore perceived barriers to utilizing Maternal and Neonatal Health (MNH) services, in health facilities contracted out by government to NGO for service provision versus in those which are managed by government (non-contracted). A community-based qualitative exploratory study was conducted between April to September 2012 at two contracted-out and four matched non-contracted primary healthcare facilities in Thatta and Chitral, rural districts of Pakistan. Using semi-structured guide, the data were collected through thirty-six Focus Group Discussions (FGDs) conducted with mothers and their spouses in the catchment areas of selected facilities. Thematic analysis was performed using NVivo version 10.0 in which themes and sub-themes emerged. Key barriers reported in contracted sites included physical distance, user charges and familial influences. Whereas, poor functionality of health centres was the main barrier for non-contracted sites with other issues being comparatively less salient. Decision-making patterns for participants of both catchments were largely similar. Spouses and mother-in-laws particularly influenced the decision to utilize health facilities. Contracting out of health facility reduces supply side barriers to MNH services for the community served but distance, user charges and low awareness remain significant barriers. Contracting needs to be accompanied by measures for transportation in remote settings, oversight on user fee charges by contractor, and strong community-based behavior change strategies. © 2015 by Kerman University of Medical Sciences.

  19. Perceived barriers to utilizing maternal and neonatal health services in contracted-out versus government-managed health facilities in the rural districts of Pakistan

    PubMed Central

    Riaz, Atif; Zaidi, Shehla; Khowaja, Asif Raza

    2015-01-01

    Background: A number of developing countries have contracted out public health facilities to the Non-Government Organizations (NGOs) in order to improve service utilization. However, there is a paucity of in-depth qualitative information on barriers to access services as a result of contracting from service users’ perspective. The objective of this study was to explore perceived barriers to utilizing Maternal and Neonatal Health (MNH) services, in health facilities contracted out by government to NGO for service provision versus in those which are managed by government (non-contracted). Methods: A community-based qualitative exploratory study was conducted between April to September 2012 at two contracted-out and four matched non-contracted primary healthcare facilities in Thatta and Chitral, rural districts of Pakistan. Using semi-structured guide, the data were collected through thirty-six Focus Group Discussions (FGDs) conducted with mothers and their spouses in the catchment areas of selected facilities. Thematic analysis was performed using NVivo version 10.0 in which themes and sub-themes emerged. Results: Key barriers reported in contracted sites included physical distance, user charges and familial influences. Whereas, poor functionality of health centres was the main barrier for non-contracted sites with other issues being comparatively less salient. Decision-making patterns for participants of both catchments were largely similar. Spouses and mother-in-laws particularly influenced the decision to utilize health facilities. Conclusion: Contracting out of health facility reduces supply side barriers to MNH services for the community served but distance, user charges and low awareness remain significant barriers. Contracting needs to be accompanied by measures for transportation in remote settings, oversight on user fee charges by contractor, and strong community-based behavior change strategies. PMID:25905478

  20. Waste Management Facilities Cost Information report for Greater-Than-Class C and DOE equivalent special case waste

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Feizollahi, F.; Shropshire, D.

    This Waste Management Facility Cost Information (WMFCI) report for Greater-Than-Class C low-level waste (GTCC LLW) and DOE equivalent special case waste contains preconceptual designs and planning level life-cycle cost (PLCC) estimates for treatment, storage, and disposal facilities needed for management of GTCC LLW and DOE equivalent waste. The report contains information on 16 facilities (referred to as cost modules). These facilities are treatment facility front-end and back-end support functions (administration support, and receiving, preparation, and shipping cost modules); seven treatment concepts (incineration, metal melting, shredding/compaction, solidification, vitrification, metal sizing and decontamination, and wet/air oxidation cost modules); two storage concepts (enclosedmore » vault and silo); disposal facility front-end functions (disposal receiving and inspection cost module); and four disposal concepts (shallow-land, engineered shallow-land, intermediate depth, and deep geological cost modules). Data in this report allow the user to develop PLCC estimates for various waste management options. A procedure to guide the U.S. Department of Energy (DOE) and its contractor personnel in the use of estimating data is also included in this report.« less

  1. Freedom Star tows a barge with an SLWT into Port Canaveral for the first time

    NASA Technical Reports Server (NTRS)

    1998-01-01

    Freedom Star, one of NASA's two solid rocket booster recovery ships, tows a barge containing the third Space Shuttle super lightweight external tank (SLWT) into Port Canaveral. This SLWT will be used to launch the orbiter Discovery on mission STS-95 in October. This first-time towing arrangement, part of a cost savings plan by NASA to prudently manage existing resources, began June 12 from the Michoud Assembly Facility in New Orleans where the Shuttle's external tanks are manufactured. The barge will now be transported up the Banana River to the LC-39 turn basin using a conventional tugboat. Previously, NASA relied on an outside contractor to provide external tank towing services at a cost of about $120,000 per trip. The new plan allows NASA's Space Flight Operations contractor, United Space Alliance (USA), to provide the same service directly to NASA using the recovery ships during their downtime between Shuttle launches. Studies show a potential savings of about $50,000 per trip. The cost of the necessary ship modifications should be paid back by the fourteenth tank delivery. The other recovery ship, Liberty Star, has also undergone deck strengthening enhancements and will soon have the necessary towing winch installed.

  2. Recovery Ship Freedom Star

    NASA Technical Reports Server (NTRS)

    1998-01-01

    Freedom Star, one of NASA's two solid rocket booster recovery ships, is towing a barge containing the third Space Shuttle Super Lightweight External Tank (SLWT) into Port Canaveral. This SLWT was slated for use to launch the orbiter Discovery on mission STS-95 in October 1998. This first time towing arrangement, part of a cost saving plan by NASA to prudently manage existing resources, began June 12 from the Michoud Assembly Facility in New Orleans where the Shuttle's external tanks were manufactured. The barge was transported up Banana River to the LC-39 turn basin using a conventional tug boat. Previously, NASA relied on an outside contractor to provide external tank towing services at a cost of about $120,000 per trip. The new plan allowed NASA's Space Flight Operations contractor, United Space Alliance (USA), to provide the same service to NASA using the recovery ships during their downtime between Shuttle launches. Studies showed a potential savings of about $50,000 per trip. The cost of the necessary ship modifications would be paid back by the fourteenth tank delivery. The other recovery ship, Liberty Star, also underwent deck strengthening enhancements and had the necessary towing wench installed.

  3. Guide to good practices for operations and administration updates through required reading

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    NONE

    1998-12-01

    This Guide to Good Practices is written to enhance understanding of, and provide direction for, Required Reading, Chapter XIV of Department of Energy (DOE) Order 5480.19, Conduct of Operations Requirements for DOE Facilities. The practices in this guide should be considered when planning or reviewing programs for updating personnel with operations and administration information through required reading. Contractors are advised to adopt procedures that meet the intent of DOE Order 5480.19. Required Reading is an element of an effective Conduct of Operations program. The complexity and array of activities performed in DOE facilities dictate the necessity for a coordinated requiredmore » reading program to promote safe and efficient operations.« less

  4. KSC-03PD-3134

    NASA Technical Reports Server (NTRS)

    2003-01-01

    KENNEDY SPACE CENTER, FLA. Dignitaries, invited guests, space center employees, and the media gather for a dedication and ribbon-cutting ceremony for the Space Life Sciences Lab hosted by NASA-Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASAs Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

  5. KSC-03PD-3137

    NASA Technical Reports Server (NTRS)

    2003-01-01

    KENNEDY SPACE CENTER, FLA. Frank T. Brogan, president of the Florida Atlantic University, speaks at a dedication and ribbon- cutting ceremony for the Space Life Sciences Lab hosted by NASA- Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASAs Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

  6. KSC-03PD-3139

    NASA Technical Reports Server (NTRS)

    2003-01-01

    KENNEDY SPACE CENTER, FLA. The Honorable Toni Jennings, lieutenant governor of the state of Florida, speaks at a dedication and ribbon-cutting ceremony for the Space Life Sciences Lab hosted by NASA-Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASAs Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

  7. KSC-03PD-3132

    NASA Technical Reports Server (NTRS)

    2003-01-01

    KENNEDY SPACE CENTER, FLA. Dignitaries, invited guests, space center employees, and the media gather for a dedication and ribbon-cutting ceremony for the Space Life Sciences Lab hosted by NASA-Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASAs Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

  8. KSC-03PD-3136

    NASA Technical Reports Server (NTRS)

    2003-01-01

    KENNEDY SPACE CENTER, FLA. Capt. Winston Scott, executive director of the Florida Space Authority, speaks at a dedication and ribbon-cutting ceremony for the Space Life Sciences Lab hosted by NASA-Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASAs Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

  9. SRB Processing Facilities Media Event

    NASA Image and Video Library

    2016-03-01

    Inside the Booster Fabrication Facility (BFF) at NASA’s Kennedy Space Center in Florida, members of the news media view a forward skirt that will be used on a solid rocket booster for NASA’s Space Launch System (SLS) rocket. Orbital ATK is a contractor for NASA’s Marshall Space Flight Center in Alabama, and operates the BFF to prepare aft booster segments and hardware for the SLS solid rocket boosters. Rick Serfozo, Orbital ATK Florida site director, talks to the media. The SLS rocket and Orion spacecraft will launch on Exploration Mission-1 in 2018. The Ground Systems Development and Operations Program is preparing the infrastructure to process and launch spacecraft for deep-space missions and the journey to Mars.

  10. KSC-2009-2320

    NASA Image and Video Library

    2009-03-26

    CAPE CANAVERAL, Fla. – In the Rotation, Processing and Surge Facility at NASA's Kennedy Space Center in Florida, technicians check the fit of the end cover on the Ares I-X motor segment. It is one of four reusable motor segments and nozzle exit cone shipped by the Ares I first-stage prime contractor Alliant Techsystems Inc. for final processing and integration in the facility. The booster used for the Ares I-X launch is being modified by adding new forward structures and a fifth segment simulator. The motor is the final hardware needed for the rocket's upcoming flight test this summer. The stacking operations are scheduled to begin in the Vehicle Assembly Building in April. Photo credit: NASA/Jim Grossmann

  11. KSC-2009-2321

    NASA Image and Video Library

    2009-03-26

    CAPE CANAVERAL, Fla. – In the Rotation, Processing and Surge Facility at NASA's Kennedy Space Center in Florida, the open end of the Ares I-X motor segment is seen without the end cover. It is one of four reusable motor segments and nozzle exit cone shipped by the Ares I first-stage prime contractor Alliant Techsystems Inc. for final processing and integration in the facility. The booster used for the Ares I-X launch is being modified by adding new forward structures and a fifth segment simulator. The motor is the final hardware needed for the rocket's upcoming flight test this summer. The stacking operations are scheduled to begin in the Vehicle Assembly Building in April. Photo credit: NASA/Jim Grossmann

  12. KSC-2009-2319

    NASA Image and Video Library

    2009-03-26

    CAPE CANAVERAL, Fla. – In the Rotation, Processing and Surge Facility at NASA's Kennedy Space Center in Florida, a technician begins propellant grain inspection of the interior of the Ares I-X motor segment. It is one of four reusable motor segments and nozzle exit cone shipped by the Ares I first-stage prime contractor Alliant Techsystems Inc. for final processing and integration in the facility. The booster used for the Ares I-X launch is being modified by adding new forward structures and a fifth segment simulator. The motor is the final hardware needed for the rocket's upcoming flight test this summer. The stacking operations are scheduled to begin in the Vehicle Assembly Building in April. Photo credit: NASA/Jim Grossmann

  13. KSC-2009-2316

    NASA Image and Video Library

    2009-03-26

    CAPE CANAVERAL, Fla. – In the Rotation, Processing and Surge Facility at NASA's Kennedy Space Center in Florida, the Ares I-X motor segment waits for inspection after removal of the shipping container. It is one of four reusable motor segments and nozzle exit cone shipped by the Ares I first-stage prime contractor Alliant Techsystems Inc. for final processing and integration in the facility. The booster used for the Ares I-X launch is being modified by adding new forward structures and a fifth segment simulator. The motor is the final hardware needed for the rocket's upcoming flight test this summer. The stacking operations are scheduled to begin in the Vehicle Assembly Building in April. Photo credit: NASA/Jim Grossmann

  14. KSC-2009-2322

    NASA Image and Video Library

    2009-03-26

    CAPE CANAVERAL, Fla. – In the Rotation, Processing and Surge Facility at NASA's Kennedy Space Center in Florida, a technician performs propellant grain inspection of the inside of the Ares I-X motor segment. It is one of four reusable motor segments and nozzle exit cone shipped by the Ares I first-stage prime contractor Alliant Techsystems Inc. for final processing and integration in the facility. The booster used for the Ares I-X launch is being modified by adding new forward structures and a fifth segment simulator. The motor is the final hardware needed for the rocket's upcoming flight test this summer. The stacking operations are scheduled to begin in the Vehicle Assembly Building in April. Photo credit: NASA/Jim Grossmann

  15. KSC-2009-2314

    NASA Image and Video Library

    2009-03-26

    CAPE CANAVERAL, Fla. – In the Rotation, Processing and Surge Facility at NASA's Kennedy Space Center in Florida, the rail car cover is moved away from the first Ares I-X motor segment. It is one of four reusable motor segments and nozzle exit cone shipped by the Ares I first-stage prime contractor Alliant Techsystems Inc. for final processing and integration in the facility. The booster used for the Ares I-X launch is being modified by adding new forward structures and a fifth segment simulator. The motor is the final hardware needed for the rocket's upcoming flight test this summer. The stacking operations are scheduled to begin in the Vehicle Assembly Building in April. Photo credit: NASA/Jim Grossmann

  16. KSC-2009-2315

    NASA Image and Video Library

    2009-03-26

    CAPE CANAVERAL, Fla. – In the Rotation, Processing and Surge Facility at NASA's Kennedy Space Center in Florida, the Ares I-X motor segment is revealed after removal of the rail car cover. It is one of four reusable motor segments and nozzle exit cone shipped by the Ares I first-stage prime contractor Alliant Techsystems Inc. for final processing and integration in the facility. The booster used for the Ares I-X launch is being modified by adding new forward structures and a fifth segment simulator. The motor is the final hardware needed for the rocket's upcoming flight test this summer. The stacking operations are scheduled to begin in the Vehicle Assembly Building in April. Photo credit: NASA/Jim Grossmann

  17. KSC-2009-2313

    NASA Image and Video Library

    2009-03-26

    CAPE CANAVERAL, Fla. – In the Rotation, Processing and Surge Facility at NASA's Kennedy Space Center in Florida, the rail car cover is removed from the first Ares I-X motor segment. It is one of four reusable motor segments and nozzle exit cone shipped by the Ares I first-stage prime contractor Alliant Techsystems Inc. for final processing and integration in the facility. The booster used for the Ares I-X launch is being modified by adding new forward structures and a fifth segment simulator. The motor is the final hardware needed for the rocket's upcoming flight test this summer. The stacking operations are scheduled to begin in the Vehicle Assembly Building in April. Photo credit: NASA/Jim Grossmann

  18. KSC-2009-2312

    NASA Image and Video Library

    2009-03-26

    CAPE CANAVERAL, Fla. – In the Rotation, Processing and Surge Facility at NASA's Kennedy Space Center in Florida, the rail car cover is removed from the first Ares I-X motor segment. It is one of four reusable motor segments and nozzle exit cone shipped by the Ares I first-stage prime contractor Alliant Techsystems Inc. for final processing and integration in the facility. The booster used for the Ares I-X launch is being modified by adding new forward structures and a fifth segment simulator. The motor is the final hardware needed for the rocket's upcoming flight test this summer. The stacking operations are scheduled to begin in the Vehicle Assembly Building in April. Photo credit: NASA/Jim Grossmann

  19. SRB Processing Facilities Media Event

    NASA Image and Video Library

    2016-03-01

    Inside the Booster Fabrication Facility (BFF) at NASA’s Kennedy Space Center in Florida, Jeff Cook, a thermal protection system specialist with Orbital ATK, displays a sample of the painted thermal protection system that is being applied to booster segments. Members of the news media toured the BFF. Orbital ATK is a contractor for NASA’s Marshall Space Flight Center in Alabama, and operates the BFF to prepare aft booster segments and hardware for the SLS rocket boosters. The SLS rocket and Orion spacecraft will launch on Exploration Mission-1 in 2018. The Ground Systems Development and Operations Program is preparing the infrastructure to process and launch spacecraft for deep-space missions and the journey to Mars.

  20. Air ambulance services--integrated emergency care.

    PubMed

    Ferdinand, M

    1994-10-01

    In the name of cost-conscious care, air ambulance program directors and service contractors are seeing the dawn of integrated networks as a boon to their business. As integrated networks form, facilities will become increasingly specialized in the types of services they provide. Patients will need to be moved around the system, resulting in more frequent patient transport and more points of transfer. Many programs are considering aircraft replacement and additions, rather than leasing. Financial benefits could come on depreciation and the high resale value of aircraft. Unless reimbursement levels increase, more program mergers and affiliations may take place to spread and reduce cost. Air ambulance services will increasingly become part of a facility's strategic plan.

  1. The April 1992 and November 1992 radon intercomparisons at EML

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Fisenne, I.M.; George, A.C.; Perry, P.M.

    1993-07-01

    The Environmental Measurements Laboratory hosted two intercomparison exercises in Calendar Year 1992. Thirty-two groups, including US federal facilities, US Department of Energy`s Office of Health and Environmental Research contractors, national and state laboratories, and universities and foreign institutions, participated in these exercises. The majority of the participants` results were within {plus_minus}10% of the EML value at radon concentrations of 2075 and 1650 Bq m{sup {minus}3}.

  2. U.S. Nuclear Weapons: Changes in Policy and Force Structure

    DTIC Science & Technology

    2008-01-23

    Pinellas Plant , in Clearwater, FL; and the Pantex Plant near Amarillo, TX. These facilities were also operated by industrial contractors. Finally, the...These included the Rocky Flats Plant , outside Denver, CO; the Kansas City Plant , near Kansas City, MO; the Mound Plant , near Dayton OH; the...In 1988, DOE closed the nuclear reactors at Hanford and Savannah River, in response to safety concerns. The Rocky Flats Plant , which produced the

  3. Hospital renovation projects: phased construction requires planning at its best.

    PubMed

    Cox, J C

    1986-01-01

    Building a new hospital facility is a difficult task, but adding onto and renovating an existing structure while normal activity continues is even more difficult. Project planners, designers, contractors, and hospital managers must carefully program the joint effort of construction and hospital operation. Several factors in the construction process and potential problems for hospital operations are described to help hospital managers better anticipate difficulties before plans are finalized and construction commences.

  4. Feds deed Ward Valley site

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    NONE

    1995-06-12

    This article is a review of the efforts to site a low-level waste repository in California. To resolve a long-running dispute, the US Government has agreed to deed to the state 1000 acres of land in the Mohave Desert. It was noted that environmentalists are unhappy with this action, and it was also noted by the prime contractor (US Ecology) that the facility can be finished six to nine months after the legal challenges are finished.

  5. AI in manufacturing

    NASA Astrophysics Data System (ADS)

    Gross, John E.; Minato, Rick; Smith, David M.; Loftin, R. B.; Savely, Robert T.

    1991-10-01

    AI techniques are shown to have been useful in such aerospace industry tasks as vehicle configuration layouts, process planning, tool design, numerically-controlled programming of tools, production scheduling, and equipment testing and diagnosis. Accounts are given of illustrative experiences at the production facilities of three major aerospace defense contractors. Also discussed is NASA's autonomous Intelligent Computer-Aided Training System, for such ambitious manned programs as Space Station Freedom, which employs five different modules to constitute its job-independent training architecture.

  6. ISS Logistics Hardware Disposition and Metrics Validation

    NASA Technical Reports Server (NTRS)

    Rogers, Toneka R.

    2010-01-01

    I was assigned to the Logistics Division of the International Space Station (ISS)/Spacecraft Processing Directorate. The Division consists of eight NASA engineers and specialists that oversee the logistics portion of the Checkout, Assembly, and Payload Processing Services (CAPPS) contract. Boeing, their sub-contractors and the Boeing Prime contract out of Johnson Space Center, provide the Integrated Logistics Support for the ISS activities at Kennedy Space Center. Essentially they ensure that spares are available to support flight hardware processing and the associated ground support equipment (GSE). Boeing maintains a Depot for electrical, mechanical and structural modifications and/or repair capability as required. My assigned task was to learn project management techniques utilized by NASA and its' contractors to provide an efficient and effective logistics support infrastructure to the ISS program. Within the Space Station Processing Facility (SSPF) I was exposed to Logistics support components, such as, the NASA Spacecraft Services Depot (NSSD) capabilities, Mission Processing tools, techniques and Warehouse support issues, required for integrating Space Station elements at the Kennedy Space Center. I also supported the identification of near-term ISS Hardware and Ground Support Equipment (GSE) candidates for excessing/disposition prior to October 2010; and the validation of several Logistics Metrics used by the contractor to measure logistics support effectiveness.

  7. Optical system for the Protein Crystallisation Diagnostics Facility (PCDF) on board the ISS

    NASA Astrophysics Data System (ADS)

    Joannes, Luc; Dupont, Olivier; Dewandel, Jean-Luc; Ligot, Renaud; Algrain, Hervé

    2004-06-01

    The Protein Crystallisation Diagnostic Facility (PCDF) is a multi-user facility to study the protein crystallisation under the conditions of micro-gravity onboard the International Space Station (ISS) Columbus facility. Large size protein crystals will growth under reduced gravity in thermally controlled reactors. A combination of diagnostic tools like video system, microscope, interferometer, and light scattering device shall help to understand the growth phenomena. Common methods of protein crystallisation shall be performed in PCDF: Dialysis where the protein solution and the salt solution are separated by a semi-permeable membrane. Extended Length Dialysis Batch where the saturation to get crystals is achieved by changing the concentration of the protein in the sample liquid. The overall ESA project is leaded by EADS Space Transportation, Friedrichshafen, Germany. Lambda-X is responsible for the Optical System (OS), with Verhaert Design and Development as sub-contractor for the mechanical design. The OS includes different compact parts: Original illumination systems based on LEDs of difference colours; Quantitative Mach-Zehnder interferometers to measure the concentration distribution around crystals; Imaging assemblies to visualize the protein volume with different field of views. The paper concentrates on the description of each part, and in particular on the imaging assembly which allow switching from one field of view to another by passive elements only.

  8. The interaction of spacecraft high voltage power systems with the space plasma environment

    NASA Technical Reports Server (NTRS)

    Domitz, S.; Grier, N. T.

    1974-01-01

    The development of spacecraft with electrical loads that require high voltage power is discussed. The high voltage solar array has been considered for supplying d.c. power directly to high voltage loads such as ion thrusters and communication tubes without intermediate power processing. Space power stations for transferring solar power to earth are being studied in the 40 kilovolt, multikilowatt regime. Analytical and experimental studies have determined that with the advent of high voltage power, new problems will arise through the interaction of the high voltage surfaces with the charged particle environment of space. The interactive environment has been identified and duplicated to some extent in simulation facilities at NASA-Lewis Research Center and at several contractor locations.

  9. A pattern of contractor selection for oil and gas industries in a safety approach using ANP-DEMATEL in a Grey environment.

    PubMed

    Gharedaghi, Gholamreza; Omidvari, Manouchehr

    2018-01-11

    Contractor selection is one of the major concerns of industry managers such as those in the oil industry. The objective of this study was to determine a contractor selection pattern for oil and gas industries in a safety approach. Assessment of contractors based on specific criteria and ultimately selecting an eligible contractor preserves the organizational resources. Due to the safety risks involved in the oil industry, one of the major criteria of contractor selection considered by managers today is safety. The results indicated that the most important safety criterion of contractor selection was safety records and safety investments. This represented the industry's risks and the impact of safety training and investment on the performance of other sectors and the overall organization. The output of this model could be useful in the safety risk assessment process in the oil industry and other industries.

  10. TA-55 change control manual

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Blum, T.W.; Selvage, R.D.; Courtney, K.H.

    This manual is the guide for initiating change at the Plutonium Facility, which handles the processing of plutonium as well as research on plutonium metallurgy. It describes the change and work control processes employed at TA-55 to ensure that all proposed changes are properly identified, reviewed, approved, implemented, tested, and documented so that operations are maintained within the approved safety envelope. All Laboratory groups, their contractors, and subcontractors doing work at TA-55 follow requirements set forth herein. This manual applies to all new and modified processes and experiments inside the TA-55 Plutonium Facility; general plant project (GPP) and line itemmore » funded construction projects at TA-55; temporary and permanent changes that directly or indirectly affect structures, systems, or components (SSCs) as described in the safety analysis, including Facility Control System (FCS) software; and major modifications to procedures. This manual does not apply to maintenance performed on process equipment or facility SSCs or the replacement of SSCs or equipment with documented approved equivalents.« less

  11. DOE handbook: Guide to good practices for training and qualification of maintenance personnel

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    NONE

    1996-03-01

    The purpose of this Handbook is to provide contractor training organizations with information that can be used to verify the adequacy of and/or modify existing maintenance training programs, or to develop new training programs. This guide, used in conjunction with facility-specific job analyses, provides a framework for training and qualification programs for maintenance personnel at DOE reactor and nonreactor nuclear facilities. Recommendations for qualification are made in four areas: education, experience, physical attributes, and training. The functional positions of maintenance mechanic, electrician, and instrumentation and control technician are covered by this guide. Sufficient common knowledge and skills were found tomore » include the three disciplines in one guide to good practices. Contents include: qualifications; on-the-job training; trainee evaluation; continuing training; training effectiveness evaluation; and program records. Appendices are included which relate to: administrative training; industrial safety training; fundamentals training; tools and equipment training; facility systems and component knowledge training; facility systems and component skills training; and specialized skills training.« less

  12. Payload specialist station study. Volume 3: Program study cost estimates. Part 1: Work breakdown structure

    NASA Technical Reports Server (NTRS)

    1976-01-01

    The work breakdown structure (WBS) for the Payload Specialist Station (PSS) is presented. The WBS is divided into two elements--PSS contractor and mission unique requirements. In accordance with the study ground rules, it is assumed that a single contractor, hereafter referred to as PSS Contractor will perform the following: (1) provide C and D hardware (MFDS and elements of MMSE), except for GFE; (2) identify software requirements; (3) provide GSE and ground test software; and (4) perform systems engineering and integration in support of the Aft Flight Deck (AFD) C and D concept. The PSS Contractor WBS element encompasses a core or standardized PSS concept. Payload peculiar C and D requirements identified by users will originate as a part of the WBS element mission unique requirements; these requirements will be provided to the PSS Contractor for implementation.

  13. KENNEDY SPACE CENTER, FLA. - The Honorable Toni Jennings (left), lieutenant governor of the state of Florida, and Frank T. Brogan, president of Florida Atlantic University, receive a briefing on the research that will be conducted in the Space Life Sciences Lab from Dr. Robert J. Ferl (right), director of Space Agriculture Biotechnology Research and Education (SABRE), University of Florida. Jennings and Brogan are speaking at a dedication and ribbon-cutting ceremony for the lab hosted by NASA-Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASA’s Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

    NASA Image and Video Library

    2003-11-19

    KENNEDY SPACE CENTER, FLA. - The Honorable Toni Jennings (left), lieutenant governor of the state of Florida, and Frank T. Brogan, president of Florida Atlantic University, receive a briefing on the research that will be conducted in the Space Life Sciences Lab from Dr. Robert J. Ferl (right), director of Space Agriculture Biotechnology Research and Education (SABRE), University of Florida. Jennings and Brogan are speaking at a dedication and ribbon-cutting ceremony for the lab hosted by NASA-Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASA’s Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

  14. Lessons Learned from the Puerto Rico Battery Energy Storage System

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Boyes, John D.; De Anda, Mindi Farber; Torres, Wenceslao

    1999-08-11

    The Puerto Rico Electric Power Authority (PREPA) installed a battery energy storage system in 1994 at a substation near San Juan, Puerto Rico. It was patterned after two other large energy storage systems operated by electric utilities in California and Germany. The Puerto Rico facility is presently the largest operating battery storage system in the world and has successfully provided frequency control, voltage regulation, and spinning reseme to the Caribbean island. The system further proved its usefulness to the PREPA network in the fall of 1998 in the aftermath of Hurricane Georges. However, the facility has suffered accelerated cell failuresmore » in the past year and PREPA is committed to restoring the plant to full capacity. This represents the first repowering of a large utility battery facility. PREPA and its vendors and contractors learned many valuable lessons during all phases of project development and operation, which are summarized in this paper.« less

  15. Space Shuttle wind tunnel testing program

    NASA Technical Reports Server (NTRS)

    Whitnah, A. M.; Hillje, E. R.

    1984-01-01

    A major phase of the Space Shuttle Vehicle (SSV) Development Program was the acquisition of data through the space shuttle wind tunnel testing program. It became obvious that the large number of configuration/environment combinations would necessitate an extremely large wind tunnel testing program. To make the most efficient use of available test facilities and to assist the prime contractor for orbiter design and space shuttle vehicle integration, a unique management plan was devised for the design and development phase. The space shuttle program is reviewed together with the evolutional development of the shuttle configuration. The wind tunnel testing rationale and the associated test program management plan and its overall results is reviewed. Information is given for the various facilities and models used within this program. A unique posttest documentation procedure and a summary of the types of test per disciplines, per facility, and per model are presented with detailed listing of the posttest documentation.

  16. Guide of good practices for occupational radiological protection in plutonium facilities

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    NONE

    1998-06-01

    This Technical Standard (TS) does not contain any new requirements. Its purpose is to provide guides to good practice, update existing reference material, and discuss practical lessons learned relevant to the safe handling of plutonium. the technical rationale is given to allow US Department of Energy (DOE) health physicists to adapt the recommendations to similar situations throughout the DOE complex. Generally, DOE contractor health physicists will be responsible to implement radiation protection activities at DOE facilities and DOE health physicists will be responsible for oversight of those activities. This guidance is meant to be useful for both efforts. This TSmore » replaces PNL-6534, Health Physics Manual of Good Practices for Plutonium Facilities, by providing more complete and current information and by emphasizing the situations that are typical of DOE`s current plutonium operations; safe storage, decontamination, and decommissioning (environmental restoration); and weapons disassembly.« less

  17. Health hazard evaluation report HETA 84-437-1532, Perry Nuclear Power Plant, Perry, Ohio

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Moseley, C.L.

    1984-11-01

    Breathing-zone samples were analyzed for iron, zinc, lead, nickel, and chromium fumes, quartz, cristobalite, and respirable particulates during construction of the Perry Nuclear Power facility, Perry, Ohio in August, 1984. The survey was requested by Local 210 of the Pipefitters Union to evaluate exposure of airborne contaminants to construction workers at the facility. All metal fume and respirable particulates were well below the relevant standards. The author notes that NIOSH conducted two previous surveys at the site and the concentrations of all contaminants have decreased since work has progressed at the facility. The quartz overexposure is due to residual constructionmore » dust. Each contractor should assume responsibility for the health and safety of his employees. Break areas should be vacuumed daily. Good housekeeping practices should be maintained in all areas to prevent exposure to quartz dust.« less

  18. Environmental impact statement Space Shuttle advanced solid rocket motor program

    NASA Technical Reports Server (NTRS)

    1989-01-01

    The proposed action is design, development, testing, and evaluation of Advanced Solid Rocket Motors (ASRM) to replace the motors currently used to launch the Space Shuttle. The proposed action includes design, construction, and operation of new government-owned, contractor-operated facilities for manufacturing and testing the ASRM's. The proposed action also includes transport of propellant-filled rocket motor segments from the manufacturing facility to the testing and launch sites and the return of used and/or refurbished segments to the manufacturing site. Sites being considered for the new facilities include John C. Stennis Space Center, Hancock County, Mississippi; the Yellow Creek site in Tishomingo County, Mississippi, which is currently in the custody and control of the Tennessee Valley Authority; and John F. Kennedy Space Center, Brevard County, Florida. TVA proposes to transfer its site to the custody and control of NASA if it is the selected site. All facilities need not be located at the same site. Existing facilities which may provide support for the program include Michoud Assembly Facility, New Orleans Parish, Louisiana; and Slidell Computer Center, St. Tammany Parish, Louisiana. NASA's preferred production location is the Yellow Creek site, and the preferred test location is the Stennis Space Center.

  19. Main Building (4800) at Dryden FRC

    NASA Image and Video Library

    1991-09-05

    The X-1E research aircraft provides a striking view at the entrance of NASA's Dryden Flight Research Center, Edwards, California. The X-1E, one of the three original X-1 aircraft modified with a raised cockpit canopy and an ejection seat, was flown at the facility between 1953 and 1958 to investigate speeds at twice that of sound, and also to evaluate a thin wing designed for high-speed flight. The Dryden complex was originally established in 1946 as a small high-speed flight station to support the X-1 program. The X-1 was the first aircraft to fly at supersonic speeds. The main administrative building is to the rear of the X-1E and is the center of a research installation that has grown to more than 450 government employees and nearly 400 civilian contractors. Located on the northwest "shore" of Rogers Dry Lake, the Dryden Center was built around the original administrative-hangar building constructed in 1954 at a cost of $3.8 million. Since then many additional support and operational facilities have been built including a number of unique test facilities such as the Thermalstructures Research Facility, Flow Visualization Facility, and the newest addition, the Integrated Test Facility.

  20. Cross-national research on contractor evaluation procedures in public works procurement

    NASA Astrophysics Data System (ADS)

    Kinoshita, Seiya; Sato, Naoyoshi; Matsumoto, Naoya

    Contractor evaluation methods in Japan's public works procurement, beginning with construction business licensure, going through biennial preliminary firm rating, up to project-by-project prequalification and comprehensive point rating, were developed during the period when public works were mostly procured through designated competitive bidding. It is essential to focus attention on contractor evaluation methods for introducing different types of procurement procedures which enhance the use of technological capabilities held by private businesses. An overall review of contractor evaluation procedures should be conducted in view of the present situation, where the open competitive bidding has become mainly used in combination with comprehensive evaluation, as well as to allow for further diversification of procurement methods. In Western countries, improvements have been made for the past several years in contractor evaluation procedures with more emphasis on "Value for Money." Advanced efforts made by these countries will be useful as a reference for overhauling Japan's contractor evaluation system. This study conducts a comparative review of contractor evaluation procedures for public procurement in Western countries such as the United States, the United Kingdom and France by identifying similarities and differences between those of Japan and the above mentioned countries. This reveals that a contractor's technical or professional ability is looked at separately from its economic and financial standing in those countries studied, and there is no case like Japan in which those two factors are integrated into one for evaluation.

  1. Total Quality Management in Space Shuttle Main Engine manufacturing

    NASA Technical Reports Server (NTRS)

    Ding, J.

    1992-01-01

    The Total Quality Management (TQM) philosophy developed in the Marshall Space Flight Center (MSFC) is briefly reviewed and the ongoing TQM implementation effort which is being pursued through the continuous improvement (CI) process is discussed. TQM is based on organizational excellence which integrates the new supportive culture with the technical tools necessary to identify, assess, and correct manufacturing processes. Particular attention is given to the prime contractor's change to the organizational excellence management philosophy in SSME manufacturing facilities.

  2. A Comparison of Nutrient Intakes between a Ft. Riley Contractor-Operated and a Ft. Lewis Military-Operated Garrison Dining Facility

    DTIC Science & Technology

    1987-10-01

    Meatsauce Rissole Potatoes Turkey Nuggets (I/o) Hash Browned Potatoes (I/o) Mashed Potatoes Buttered Mixed Vegetables Toasted Garlic Bread Brussels...Chicken Curry Baked Ham/P/A Sauce Parsley Buttered Potatoes Brown Gravy Hash Browned Potatoes (I/o) Steamed Rice Steamed Carrots Mashed Potatoes...Steak Mashed Potatoes Mashed Potatoes Rissole Potatoes Steamed Rice Hash Browned Potatoes (I/o) Green Beans Steamed Carrots Broccoli w/Cheese sauce

  3. NASTRAN users' experience of Avco Aerostructures Division

    NASA Technical Reports Server (NTRS)

    Blackburn, C. L.; Wilhelm, C. A.

    1973-01-01

    The NASTRAN experiences of a major structural design and fabrication subcontractor that has less engineering personnel and computer facilities than those available to large prime contractors are discussed. Efforts to obtain sufficient computer capacity and the development and implementation of auxiliary programs to reduce manpower requirements are described. Applications of the NASTRAN program for training users, checking out auxiliary programs, performing in-house research and development, and structurally analyzing an Avco designed and manufactured missile case are presented.

  4. Defense Management: Actions Needed to Improve Management of Air Force’s Food Transformation Initiative

    DTIC Science & Technology

    2011-07-01

    nonappropriated fund food and beverage operations, such as clubs and snack bars, accepted jobs with the new contractor, but their job security remains uncertain...operate the nonappropriated fund food and beverage operations, such as clubs and bowling center snack bars, because many of these facilities were...center and golf course snack bars and officers’ and enlisted members’ clubs, to Aramark in a commission-based contract.11 Table 1 lists the pilot

  5. Apollo Program Management, Kennedy Space Center, Florida. Volume 4

    NASA Technical Reports Server (NTRS)

    1968-01-01

    The evolution of the Kennedy Space Center as the launch organization for Apollo/ Saturn V involved the concurrent solution of numerous complex problems. A significant increase in manpower was involved. Large and complex checkout and launch facilities were to be designed and constructed. Expansion of operational capabilities required the establishment and integration of a Government-Contractor operational team. From an initial cadre of approximately 200 civil service personnel of the Army Ballistic Missile Agency, transferred to NASA in 1960 following its establishment, expansion to the present civil service level of 2,900 occurred in the last seven years. Established within NASA as a directorate of the Marshall Space Flight Center, KSC achieved center status in 1962. With its designation as a Center, KSC accomplished the development and staffing of an organization that could perform procurement, resources, financial, and other management requirements formerly provided by the parent organization. In addition to continuing launch operations for established programs, KSC undertook the design and construction of large, new, and unique launch facilities for Apollo/Saturn V. With the expansion of the civil service work force, KSC integrated contractor organizations employing 23,000 personnel at the Center to perform specific operational and support missions under the technical supervision and observation of the Government team. The management techniques, organizational concepts, and continuing efforts utilized to meet the Apollo goals and challenges are discussed in this document.

  6. Experimental validation of pulsed column inventory estimators

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Beyerlein, A.L.; Geldard, J.F.; Weh, R.

    Near-real-time accounting (NRTA) for reprocessing plants relies on the timely measurement of all transfers through the process area and all inventory in the process. It is difficult to measure the inventory of the solvent contractors; therefore, estimation techniques are considered. We have used experimental data obtained at the TEKO facility in Karlsruhe and have applied computer codes developed at Clemson University to analyze this data. For uranium extraction, the computer predictions agree to within 15% of the measured inventories. We believe this study is significant in demonstrating that using theoretical models with a minimum amount of process data may bemore » an acceptable approach to column inventory estimation for NRTA. 15 refs., 7 figs.« less

  7. Apparel for Cleaner Clean Rooms

    NASA Technical Reports Server (NTRS)

    1983-01-01

    In the 1960s NASA pioneered contamination control technology, providing a base from which aerospace contractors could develop control measures. NASA conducted special courses for clean room technicians and supervisors, and published a series of handbooks with input from various NASA field centers. These handbooks extended aerospace experience to the medical, pharmaceutical, electronics, and other industries where extreme cleanliness is important. American Hospital Supply Company (AHSC) felt that high technology products with increasingly stringent operating requirements in aerospace, electronics, pharmaceuticals and medical equipment manufacturing demanded improvement in contamination control techniques. After studying the NASA handbooks and visiting NASA facilities, the wealth of information gathered resulted in Micro-clean non-woven garments and testing equipment and procedures for evaluating effectiveness.

  8. TRADE ALARA for design and operations engineers

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Not Available

    1993-04-01

    This product has been developed by the Training Resources and Data Exchange (TRADE) network for use at Department of Energy (DOE) and DOE contractor facilities. The TRADE network encourages and facilitates the exchange of ideas, techniques, and resources for improving training and development and serves as a forum for the discussion of issues of interest to the DOE community. This TRADE product has been developed for DOE contractor employees who are asked to deliver training to Design and Operations Engineers on the concept of As Low As Reasonably Achievable (ALARA). The ALARA concept is an approach to radiation protection tomore » control or manage exposures as low as social, technical, economic, practical, public policy, and other considerations permit. Worldwide panels of radiation experts have concluded that it is conservative to assume that a proportional relationship exists between radiation dose (exposure) and the biological effects resulting from it. This assumption implies that every dose received, no matter how small, carries some risk: the higher the dose, the higher the risk. The federal government, including agencies such as DOE, subscribes to the concept of ALARA and requires its facilities to subscribe to it as well. This course was developed to introduce engineers to the fundamentals of radiation and contamination reduction that they will use when designing or modifying plant facilities. The course was developed by the ALARA Program group and the Radiation Protection Monitoring/Training Group of Martin Marietta Energy Systems, Inc. at Oak Ridge National Laboratory. We wish to express our appreciation to Emily Copenhaver, Scott Taylor, and Janet Westbrook at Oak Ridge National Laboratory for their willingness to share their labors with the rest of the DOE community and for technical support during the development of the TRADE ALARA for Design and Operations Engineers Course Manual.« less

  9. Assessment and Develop the Saudi's Contractors Classification System

    ERIC Educational Resources Information Center

    Almutairi, Saud

    2017-01-01

    Research has shown that construction projects in Saudi Arabia have had a perceived poor performance for the past three decades, from 1970-2016. The Saudi construction industry relies on a Contractor Classification System (CCS) to determine contractors' capabilities, and prevent underperformance. Through this study, a survey was conducted among…

  10. Fusion Safety Program annual report, fiscal year 1994

    NASA Astrophysics Data System (ADS)

    Longhurst, Glen R.; Cadwallader, Lee C.; Dolan, Thomas J.; Herring, J. Stephen; McCarthy, Kathryn A.; Merrill, Brad J.; Motloch, Chester C.; Petti, David A.

    1995-03-01

    This report summarizes the major activities of the Fusion Safety Program in fiscal year 1994. The Idaho National Engineering Laboratory (INEL) is the designated lead laboratory and Lockheed Idaho Technologies Company is the prime contractor for this program. The Fusion Safety Program was initiated in 1979. Activities are conducted at the INEL, at other DOE laboratories, and at other institutions, including the University of Wisconsin. The technical areas covered in this report include tritium safety, beryllium safety, chemical reactions and activation product release, safety aspects of fusion magnet systems, plasma disruptions, risk assessment failure rate data base development, and thermalhydraulics code development and their application to fusion safety issues. Much of this work has been done in support of the International Thermonuclear Experimental Reactor (ITER). Also included in the report are summaries of the safety and environmental studies performed by the Fusion Safety Program for the Tokamak Physics Experiment and the Tokamak Fusion Test Reactor and of the technical support for commercial fusion facility conceptual design studies. A major activity this year has been work to develop a DOE Technical Standard for the safety of fusion test facilities.

  11. Common occupational classification system - revision 3

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Stahlman, E.J.; Lewis, R.E.

    1996-05-01

    Workforce planning has become an increasing concern within the DOE community as the Office of Environmental Restoration and Waste Management (ER/WM or EM) seeks to consolidate and refocus its activities and the Office of Defense Programs (DP) closes production sites. Attempts to manage the growth and skills mix of the EM workforce while retaining the critical skills of the DP workforce have been difficult due to the lack of a consistent set of occupational titles and definitions across the complex. Two reasons for this difficulty may be cited. First, classification systems commonly used in industry often fail to cover inmore » sufficient depth the unique demands of DOE`s nuclear energy and research community. Second, the government practice of contracting the operation of government facilities to the private sector has introduced numerous contractor-specific classification schemes to the DOE complex. As a result, sites/contractors report their workforce needs using unique classification systems. It becomes difficult, therefore, to roll these data up to the national level necessary to support strategic planning and analysis. The Common Occupational Classification System (COCS) is designed to overcome these workforce planning barriers. The COCS is based on earlier workforce planning activities and the input of technical, workforce planning, and human resource managers from across the DOE complex. It provides a set of mutually-exclusive occupation titles and definitions that cover the broad range of activities present in the DOE complex. The COCS is not a required record-keeping or data management guide. Neither is it intended to replace contractor/DOE-specific classification systems. Instead, the system provides a consistent, high- level, functional structure of occupations to which contractors can crosswalk (map) their job titles.« less

  12. Organizational Considerations for Implementing Systems Engineering and Integration in the Ares Projects Office

    NASA Technical Reports Server (NTRS)

    Thomas, LeAnn; Doreswamy, Rajiv N.

    2008-01-01

    Systems Engineering and Integration (SE&I) is a critical discipline in developing new space systems. In 2005, NASA performed an internal study of 24 agency and Department of Defense (DoD) programs to evaluate methods of integrating SE&I practices and determine their effectiveness. The goal of the study was to determine the best SE&I implementation strategy for the Ares Projects Office. The study identified six SE&I organizational structures: 1. Lead systems integrator (LSI) with SE&I responsibility and government technical insight. 2a. Integration contractor with government SE&I responsibility (government insight). 2b. Integration contractor with government SE&I responsibility (government oversight). 3a. Prime contractor with SE&I responsibility (government insight). 3b. Prime contractor with SE&I responsibility (government oversight). 3c. Prime contractor with SE&I responsibility (government/industry partnership). 4a.Prime contractor with government SE&I responsibility (government insight). 4b. Prime contractor with government SE&I responsibility (government oversight). 4d.Prime contractors with total system performance responsibility (TSPR). 5. Prime contractor with government SE&I responsibility and integration products through a Federally Funded Research and Development Center (FFRDC). 6. Government/FFRDC in-house development with SE&I responsibility and function. The organizational structure used most often was number 4, using a prime contractor with government SE&I responsibility and government technical insight. However, data analyses did not establish a positive relationship between program development costs and specific SE&I organizational types, nor did it positively determine the relationship between successful programs or projects and their SE&I structure. The SE&I study reached the following conclusions: (1) Large, long-duration, technically complex programs or projects reach their technical goals, but rarely meet schedule or cost goals. NASA's recent successes have been smaller, short-duration development projects using heritage hardware/software, focused technology development, technical oversight and stable external factors. (2) Programs and projects have failed or been terminated due to lack of technical insight, relaxing of SE&I processes, and unstable external factors. (3) The study did not find a single, clear optimum SE&I organization type to fit all projects. However, while any organizational structure can be made to work, the fewer complexities in the program, the better the likelihood of success. (4) The most common successful SE&I organization structure type in the study was type 4b, where the government maintained integration responsibility, with the prime contractor providing SE&I products and the government providing technical oversight. This study was instrumental in helping the APO select organization structure 4, following the same SE&I and oversight process used during humanlund7s last voyages to the Moon.

  13. KSC00spn006

    NASA Image and Video Library

    2001-07-26

    KENNEDY SPACE CENTER, FLA. -- Day in the Life, page 3. Coming in for landing. Inside the control building at the Shuttle Landing Facility, air traffic controller Donny Linton, left, and SGS air facility manager Bob Bryen survey the SLF runway. This photograph was taken for a special color edition of Spaceport News designed to portray in photographs a single day at KSC, July 26, 2000. The special edition, published Aug. 25, 2000, was created to give readers a look at KSC’s diverse workforce and the critical roles workers play in the nation’s space program. Spaceport News is an official publication of the Kennedy Space Center and is published on alternate Fridays by the Public Affairs Office in the interest of KSC civil service and contractor employees

  14. KSC-03PD-3138

    NASA Technical Reports Server (NTRS)

    2003-01-01

    KENNEDY SPACE CENTER, FLA. Dignitaries, invited guests, space center employees, and the media show their appreciation for the speakers at a dedication and ribbon-cutting ceremony for the Space Life Sciences Lab hosted by NASA-Kennedy Space Center and the state of Florida at the new lab. Completed in August, the facility encompasses more than 100,000 square feet and was formerly known as the Space Experiment Research and Processing Laboratory or SERPL. The state, through the Florida Space Authority, built the research lab which is host to NASA, NASAs Life Sciences Services contractor Dynamac Corp., Bionetics Corp., and researchers from the University of Florida. Dynamac Corp. leases the facility. The Florida Space Research Institute is responsible for gaining additional tenants from outside the NASA community.

  15. SRB Processing Facilities Media Event

    NASA Image and Video Library

    2016-03-01

    Inside the Booster Fabrication Facility (BFF) at NASA’s Kennedy Space Center in Florida, members of the news media view the right-hand aft skirt that will be used on a solid rocket booster for NASA’s Space Launch System (SLS) rocket. Orbital ATK is contractor for NASA’s Marshall Space Flight Center in Alabama, and operates the BFF to prepare aft booster segments and hardware for the SLS solid rocket boosters. At far right, in the royal blue shirt, Rick Serfozo, Orbital ATK Florida site director, talks to the media. The SLS rocket and Orion spacecraft will launch on Exploration Mission-1 in 2018. The Ground Systems Development and Operations Program is preparing the infrastructure to process and launch spacecraft for deep-space missions and the journey to Mars.

  16. KSC-2009-2318

    NASA Image and Video Library

    2009-03-26

    CAPE CANAVERAL, Fla. –In the Rotation, Processing and Surge Facility at NASA's Kennedy Space Center in Florida, the end of the Ares I-X motor segment is removed to allow propellant grain inspection of the interior. It is one of four reusable motor segments and nozzle exit cone shipped by the Ares I first-stage prime contractor Alliant Techsystems Inc. for final processing and integration in the facility. The booster used for the Ares I-X launch is being modified by adding new forward structures and a fifth segment simulator. The motor is the final hardware needed for the rocket's upcoming flight test this summer. The stacking operations are scheduled to begin in the Vehicle Assembly Building in April. Photo credit: NASA/Jim Grossmann

  17. KSC-2009-2317

    NASA Image and Video Library

    2009-03-26

    CAPE CANAVERAL, Fla. – In the Rotation, Processing and Surge Facility at NASA's Kennedy Space Center in Florida, technicians prepare to remove the cover from the end of the Ares I-X motor segment for propellant grain inspection of the interior. It is one of four reusable motor segments and nozzle exit cone shipped by the Ares I first-stage prime contractor Alliant Techsystems Inc. for final processing and integration in the facility. The booster used for the Ares I-X launch is being modified by adding new forward structures and a fifth segment simulator. The motor is the final hardware needed for the rocket's upcoming flight test this summer. The stacking operations are scheduled to begin in the Vehicle Assembly Building in April. Photo credit: NASA/Jim Grossmann

  18. Shuttle Upgrade Using 5-Segment Booster (FSB)

    NASA Technical Reports Server (NTRS)

    Sauvageau, Donald R.; Huppi, Hal D.; McCool, A. A. (Technical Monitor)

    2000-01-01

    In support of NASA's continuing effort to improve the over-all safety and reliability of the Shuttle system- a 5-segment booster (FSB) has been identified as an approach to satisfy that overall objective. To assess the feasibility of a 5-segment booster approach, NASA issued a feasibility study contract to evaluate the potential of a 5-segment booster to improve the overall capability of the Shuttle system, especially evaluating the potential to increase the system reliability and safety. In order to effectively evaluate the feasibility of the 5-segment concept, a four-member contractor team was established under the direction of NASA Marshall Space Flight Center (MSFC). MSFC provided the overall program oversight and integration as well as program contractual management. The contractor team consisted of Thiokol, Boeing North American Huntington Beach (BNA), Lockheed Martin Michoud Space Systems (LMMSS) and United Space Alliance (USA) and their subcontractor bd Systems (Control Dynamics Division, Huntsville, AL). United Space Alliance included the former members of United Space Booster Incorporated (USBI) who managed the booster element portion of the current Shuttle solid rocket boosters. Thiokol was responsible for the overall integration and coordination of the contractor team across all of the booster elements. They were also responsible for all of the motor modification evaluations. Boeing North American (BNA) was responsible for all systems integration analyses, generation of loads and environments. and performance and abort mode capabilities. Lockheed Martin Michoud Space Systems (LMMSS) was responsible for evaluating the impacts of any changes to the booster on the external tank (ET), and evaluating any design changes on the external tank necessary to accommodate the FSB. USA. including the former USBI contingent. was responsible for evaluating any modifications to facilities at the launch site as well as any booster component design modifications.

  19. Content of system design descriptions

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    NONE

    A System Design Description (SDD) describes the requirements and features of a system. This standard provides guidance on the expected technical content of SDDs. The need for such a standard was recognized during efforts to develop SDDs for safety systems at DOE Hazard Category 2 nonreactor nuclear facilities. Existing guidance related to the corresponding documents in other industries is generally not suitable to meet the needs of DOE nuclear facilities. Across the DOE complex, different contractors have guidance documents, but they vary widely from site to site. While such guidance documents are valuable, no single guidance document has all themore » attributes that DOE considers important, including a reasonable degree of consistency or standardization. This standard is a consolidation of the best of the existing guidance. This standard has been developed with a technical content and level of detail intended to be most applicable to safety systems at DOE Hazard Category 2 nonreactor nuclear facilities. Notwithstanding that primary intent, this standard is recommended for other systems at such facilities, especially those that are important to achieving the programmatic mission of the facility. In addition, application of this standard should be considered for systems at other facilities, including non-nuclear facilities, on the basis that SDDs may be beneficial and cost-effective.« less

  20. Mitigating delay and non-payment in the Malaysian construction industry

    NASA Astrophysics Data System (ADS)

    Mohamad, N.; Suman, A. S.; Harun, H.; Hashim, H.

    2018-02-01

    Construction industry is one of the industries that have contributed towards the rapid growth of development and economics in Malaysia. However, the industry is inundated with delay and non-payment issues between the two parties in contract that is the clients and contractors Even though there are contractual and administrative provisions in the standard forms of contract in Malaysia regarding payments, delay and non-payment issues still occur between them. The aim of the study is to develop measures to mitigate delay and non-payment issues between contractors and clients in the Malaysian construction industry. Questionnaire survey was conducted with clients and contractors in Klang Valley. Results from data analysis identified significant measures to mitigate delay and non-payment issues between contractors and clients which include contractors should submit their progress work invoicing with adequate documents; contractors should follow up constantly with client regarding payment; proper understanding of requirements with regards to payment; mutual discussion of problems with client to address problems in a timely manner and proper use of payment provisions in the standard form of contract. This study is significant to contractors and clients and to other construction players in order to reduce and minimise delay and non-payment issues for the growth of economy in the Malaysian construction industry.

Top