Science.gov

Sample records for decommissioning update spring

  1. FLUOR HANFORD DECOMMISSIONING UPDATE

    SciTech Connect

    GERBER MS

    2008-04-21

    Fluor Hanford is completing D&D of the K East Basin at the U.S. Department of Energy's (DOE's) Hanford Site in southeastern Washington State this spring, with demolition expected to begin in June. Located about 400 yards from the Columbia River, the K East Basin is one of two indoor pools that formerly contained irradiated nuclear fuel, radioactive sludge and tons of contaminated debris. In unique and path-breaking work, workers finished removing the spent fuel from the K Basins in 2004. In May 2007, workers completed vacuuming the sludge into containers in the K East Basin, and transferring it into containers in the K West Basin. In December, they finished vacuuming the remainder of K West Basin sludge into these containers. The K East Basin was emptied of its radioactive inventory first because it was more contaminated than the K West Basin, and had leaked in the past. In October 2007, Fluor Hanford began physical D&D of the 8,400-square foot K East Basin by pouring approximately 14-inches of grout into the bottom of it. Grout is a type of special cement used for encasing waste. Two months later, Fluor Hanford workers completed sluicing contaminated sand from the large filter that had sieved contaminants from the basin water for more than 50 years. Next, they poured grout into the filter housing and the vault that surrounds the filter, as well as into ion exchange columns that also helped filter basin water. For a six-week period in February and March, personnel drained the approximately one million gallons of contaminated water from the K East Basin. The effort required more than 200 tanker truck loads that transported the water to an effluent treatment facility for treatment and then release. A thin fixative was also applied to the basin walls as the water was removed to hold residual contamination in place. As soon as the water was out of the basin, Fluor pumped in approximately 18 feet of 'controlled density fill' material (somewhat similar to sand) to shield

  2. Rancho Seco--Decommissioning Update

    SciTech Connect

    Newey, J. M.; Ronningen, E. T.; Snyder, M. W.

    2003-02-26

    The Rancho Seco Nuclear Generating Station ceased operation in June of 1989 and entered an extended period of SAFSTOR to allow funds to accumulate for dismantlement. Incremental dismantlement was begun in 1997 of steam systems and based on the successful completion of work, the Sacramento Municipal Utility District (SMUD) board of directors approved full decommissioning in July 1999. A schedule has been developed for completion of decommissioning by 2008, allowing decommissioning funds to accumulate until they are needed. Systems removal began in the Auxiliary Building in October of 1999 and in the Reactor Building in January of 2000. Systems dismantlement continues in the Reactor Building and should be completed by the end of 2003. System removal is near completion in the Auxiliary Building with removal of the final liquid waste tanks in progress. The spent fuel has been moved to dry storage in an onsite ISFSI, with completion on August 21, 2002. The spent fuel racks are currently being removed from the pool, packaged and shipped, and then the pool will be cleaned. Also in the last year the reactor coolant pumps and primary piping were removed and shipped. Characterization and planning work for the reactor vessel and internals is also in progress with various cut-up and/or disposal options being evaluated. In the year ahead the remaining systems in the Reactor Building will be removed, packaged and sent for disposal, including the pressurizer. Work will be started on embedded and underground piping and the large outdoor tanks. Building survey and decontamination will begin. RFP's for removal of the vessel and internals and the steam generators are planned to fix the cost of those components. If the costs are consistent with current estimates the work will go forward. If they are not, hardened SAFSTOR/entombment may be considered.

  3. HANFORD DECOMMISSIONING UPDATE 09/2007

    SciTech Connect

    GERBER, M.S.

    2007-08-20

    Fluor Hanford's K Basins Closure (KBC) Project tallied three major accomplishments at the U.S. Department of Energy's (DOE's) Hanford Site in Southeastern Washington State this past summer. The Project finished emptying the aging K East Basin of both sludge and the last pieces of scrap spent nuclear fuel. It also Completed vacuuming the bulk of the sludge in the K West Basin into underwater containers. The 54-year-old concrete basins once held more than four million pounds of spent nuclear fuel and sit less than 400 yards from the Columbia River. Each basin holds more than a million gallons of radioactive water. In 2004, Fluor finished removing all the spent nuclear fuel from the K Basins. Nearly 50 cubic meters of sludge remained--a combination of dirt, sand, small pieces of corroded uranium fuel and fuel cladding, corrosion products from racks and canisters, ion-exchange resin beads, polychlorinated biphenyls, and fission products that had formed during the decades that the spent nuclear fuel was stored underwater. Capturing the sludge into underwater containers in the K East Basin took more than two years, and vacuuming the much smaller volume of sludge into containers in the K West Basin required seven months. Workers stood on grating above the basin water and vacuumed the sludge through long, heavy hoses. The work was complicated by murky water and contaminated solid waste (debris). Pumping was paused several times to safely remove and package debris that totaled more than 370 tons. In October 2006, Fluor Hanford workers began pumping the sludge captured in the K East Basin containers out through a specially designed pipeline to underwater containers in the K West Basin, about a half mile away. They used a heavy but flexible, double-walled ''hose-in-hose'' system. Pumping work progressed slowly at first, but ramped up in spring 2007 and was completed on May 31. Just a week before sludge transfers finished, the KBC Project removed the last few small pieces of

  4. Cost update technology, safety, and costs of decommissioning a reference uranium hexafluoride conversion plant

    SciTech Connect

    Miles, T.L.; Liu, Y.

    1995-08-01

    The purpose of this study is to update the cost estimates developed in a previous report, NUREG/CR-1757 (Elder 1980) for decommissioning a reference uranium hexafluoride conversion plant from the original mid-1981 dollars to values representative of January 1993. The cost updates were performed by using escalation factors derived from cost index trends over the past 11.5 years. Contemporary price quotes wee used for costs that have increased drastically or for which is is difficult to find a cost trend. No changes were made in the decommissioning procedures or cost element requirements assumed in NUREG/CR-1757. This report includes only information that was changed from NUREG/CR-1757. Thus, for those interested in detailed descriptions and associated information for the reference uranium hexafluoride conversion plant, a copy of NUREG/CR-1757 will be needed.

  5. Cost update: Technology, safety, and costs of decommissioning a reference uranium fuel fabrication plant

    SciTech Connect

    Miles, T.L.; Liu, Y.

    1994-06-01

    The cost estimates originally developed in NUREG/CR-1266 for commissioning a reference low-enrichment uranium fuel fabrication plant are updated from 1978 to early 1993 dollars. During this time, the costs for labor and materials increased approximately at the rate of inflation, the cost of energy increased more slowly than the rate of inflation, and the cost of low-level radioactive waste disposal increased much more rapidly than the rate of inflation. The results of the analysis indicate that the estimated costs for the immediate dismantlement and decontamination for unrestricted facility release (DECON) of the reference plant have increased from the mid-1978 value of $3.57 million to $8.08 million in 1993 with in-compact low-level radioactive waste disposal at the US Ecoloay facility near Richland, Washington. The cost estimate rises to $19.62 million with out-of-compact radioactive waste disposal at the Chem-Nuclear facility near Barnwell, South Carolina. A methodology and a formula are presented for estimating the cost of decommissioning the reference uranium fuel fabrication plant at some future time, based on these early 1993 cost estimates. The formula contains essentially the same elements as the formula given in 10 CFR 50.75 for escalating the decommissioning costs for nuclear power reactors to some future time.

  6. FEMP (Federal Energy Management Program) Update, Spring 1989

    SciTech Connect

    Not Available

    1989-04-01

    The FEMP Update, published quarterly by the Federal Energy Management Program (FEMP), provides information that will assist federal managers in their energy management responsibilities. The Update is distributed primarily to federal facility and energy management personnel.

  7. Update on Research and Leadership, Fall 2001-Spring 2002.

    ERIC Educational Resources Information Center

    Barnett, Elisabeth, Ed.

    2001-01-01

    This issue of On Research and Leadership Update (v13 n1) focuses on the concerns surrounding dual enrollment and dual credit. "Dual Enrollment Programs: Assessing the American Dream," by Katherine Boswell, addresses the problems inherent in development of these programs when institutions fail to collaborate with one another in an effective way.…

  8. National Bioenergy Center Biochemical Platform Integration Project: Quarterly Update #28, Spring 2011

    SciTech Connect

    Schell, D. J.

    2011-04-01

    Spring 2011 edition of the National Bioenergy Center's Biochemical Platform Integration Project quarterly newsletter. Issue topics: 33rd Symposium on Biotechnology for Fuels and Chemicals program sessions and special topic sessions; assessment of waste water treatment needs; and an update on new arabinose-to-ethanol fermenting Zymomonas mobilis strains.

  9. Decommissioning Handbook

    SciTech Connect

    Cusack, J.G.; Dalfonso, P.H.; Lenyk, R.G.

    1994-12-31

    The Decommissioning Handbook provides technical guidance on conducting decommissioning projects. Information presented ranges from planning logic, regulations affecting decommissioning, technology discussion, health and safety requirements, an developing a cost estimate. The major focus of the handbook are the technologies -- decontamination technologies, waste treatment, dismantling/segmenting/demolition, and remote operations. Over 90 technologies are discussed in the handbook providing descriptions, applications, and advantages/disadvantages. The handbook was prepared to provide a compendium of available or potentially available technologies in order to aid the planner in meeting the specific needs of each decommissioning project. Other subjects presented in the Decommissioning Handbook include the decommissioning plan, characterization, final project configuration based planning, environmental protection, and packaging/transportation. These discussions are presented to complement the technologies presented in the handbook.

  10. Decommissioning Handbook

    SciTech Connect

    Not Available

    1994-03-01

    The Decommissioning Handbook is a technical guide for the decommissioning of nuclear facilities. The decommissioning of a nuclear facility involves the removal of the radioactive and, for practical reasons, hazardous materials to enable the facility to be released and not represent a further risk to human health and the environment. This handbook identifies and technologies and techniques that will accomplish these objectives. The emphasis in this handbook is on characterization; waste treatment; decontamination; dismantling, segmenting, demolition; and remote technologies. Other aspects that are discussed in some detail include the regulations governing decommissioning, worker and environmental protection, and packaging and transportation of the waste materials. The handbook describes in general terms the overall decommissioning project, including planning, cost estimating, and operating practices that would ease preparation of the Decommissioning Plan and the decommissioning itself. The reader is referred to other documents for more detailed information. This Decommissioning Handbook has been prepared by Enserch Environmental Corporation for the US Department of Energy and is a complete restructuring of the original handbook developed in 1980 by Nuclear Energy Services. The significant changes between the two documents are the addition of current and the deletion of obsolete technologies and the addition of chapters on project planning and the Decommissioning Plan, regulatory requirements, characterization, remote technology, and packaging and transportation of the waste materials.

  11. STATUS OF THE NRC'S DECOMMISSIONING PROGRAM

    SciTech Connect

    Orlando, D. A.; Camper, L. W.; Buckley, J.

    2002-02-25

    On July 21, 1997, the U.S. Nuclear Regulatory Commission published the final rule on Radiological Criteria for License Termination (the License Termination Rule) as Subpart E to 10 CFR Part 20. NRC regulations require that materials licensees submit Decommissioning Plans to support the decommissioning of its facility if it is required by license condition, or if the procedures and activities necessary to carry out the decommissioning have not been approved by NRC and these procedures could increase the potential health and safety impacts to the workers or the public. NRC regulations also require that reactor licensees submit Post-shutdown Decommissioning Activities Reports and License Termination Plans to support the decommissioning of nuclear power facilities. This paper provides an update on the status of the NRC's decommissioning program. It discusses the status of permanently shut-down commercial power reactors, complex decommissioning sites, and sites listed in the Site Decommissioning Management Plan. The paper provides the status of various tools and guidance the NRC is developing to assist licensees during decommissioning, including a Standard Review Plan for evaluating plans and information submitted by licensees to support the decommissioning of nuclear facilities and the D and D Screen software for determining the potential doses from residual radioactivity. Finally, it discusses the status of the staff's current efforts to streamline the decommissioning process.

  12. Decommissioning handbook

    SciTech Connect

    Manion, W.J.; LaGuardia, T.S.

    1980-11-01

    This document is a compilation of information pertinent to the decommissioning of surplus nuclear facilities. This handbook is intended to describe all stages of the decommissioning process including selection of the end product, estimation of the radioactive inventory, estimation of occupational exposures, description of the state-of-the-art in re decontamination, remote csposition of wastes, and estimation of program costs. Presentation of state-of-the-art technology and data related to decommissioning will aid in consistent and efficient program planning and performance. Particular attention is focused on available technology applicable to those decommissioning activities that have not been accomplished before, such as remote segmenting and handling of highly activated 1100 MW(e) light water reactor vessel internals and thick-walled reactor vessels. A summary of available information associated with the planning and estimating of a decommissioning program is also presented. Summarized in particular are the methodologies associated with the calculation and measurement of activated material inventory, distribution, and surface dose level, system contamination inventory and distribution, and work area dose levels. Cost estimating techniques are also presented and the manner in which to account for variations in labor costs as impacting labor-intensive work activities is explained.

  13. Education for Employment Update. Quarterly Newsletter. Dane County Schools. Summer 1988-Spring 1989.

    ERIC Educational Resources Information Center

    Education for Employment Update Quarterly Newsletter, 1989

    1989-01-01

    This packet contains four quarterly newsletters covering Summer 1988-Spring 1989, published by the Dane County, Wisconsin, Education for Employment project. The newsletters contain various articles about the Education for Employment project, including reports on successful school-business partnership programs and notices of upcoming…

  14. Update on Research and Leadership. Vol. 20, No. 2. Spring 2009

    ERIC Educational Resources Information Center

    Bragg, Debra D., Ed.: Khan, Sadya, Ed.; Kirby, Catherine, Ed.

    2009-01-01

    Increasing rates of remediation in college and the alignment gap between secondary and postsecondary education call for further study of policies and practices to improve college and career readiness. This issue of Update on Research and Leadership features nine articles that highlight current research and practice related to college readiness and…

  15. National FCEV Learning Demonstration: Spring 2011 All Composite Data Products With Updates Through March 29, 2011

    SciTech Connect

    Wipke, K.; Sprik, S.; Kurtz, J.; Ramsden, T.

    2011-04-01

    This presentation from the U.S. Department of Energy's National Renewable Energy Laboratory includes all the composite data products produced to date (with updates through March 29, 2011) as part of the National Fuel Cell Electric Vehicle (FCEV) Learning Demonstration.

  16. Technology, safety and costs of decommissioning a reference pressurized water reactor power station: Technical support for decommissioning matters related to preparation of the final decommissioning rule

    SciTech Connect

    Konzek, G.J.; Smith, R.I.

    1988-07-01

    Preparation of the final Decommissioning Rule by the Nuclear Regulatory Commission (NRC) staff has been assisted by Pacific Northwest Laboratory (PNL) staff familiar with decommissioning matters. These efforts have included updating previous cost estimates developed during the series of studies on conceptually decommissioning reference licensed nuclear facilities for inclusion in the Final Generic Environmental Impact Statement (FGEIS) on decommissioning; documenting the cost updates; evaluating the cost and dose impacts of post-TMI-2 backfits on decommissioning; developing a revised scaling formula for estimating decommissioning costs for reactor plants different in size from the reference pressurized water reactor (PWR) described in the earlier study; defining a formula for adjusting current cost estimates to reflect future escalation in labor, materials, and waste disposal costs; and completing a study of recent PWR steam generator replacements to determine realistic estimates for time, costs and doses associated with steam generator removal during decommissioning. This report presents the results of recent PNL studies to provide supporting information in four areas concerning decommissioning of the reference PWR: updating the previous cost estimates to January 1986 dollars; assessing the cost and dose impacts of post-TMI-2 backfits; assessing the cost and dose impacts of recent steam generator replacements; and developing a scaling formula for plants different in size than the reference plant and an escalation formula for adjusting current cost estimates for future escalation.

  17. NMSS handbook for decommissioning fuel cycle and materials licensees

    SciTech Connect

    Orlando, D.A.; Hogg, R.C.; Ramsey, K.M.

    1997-03-01

    The US Nuclear Regulatory Commission amended its regulations to set forth the technical and financial criteria for decommissioning licensed nuclear facilities. These regulations were further amended to establish additional recordkeeping requirements for decommissioning; to establish timeframes and schedules for the decommissioning; and to clarify that financial assurance requirements must be in place during operations and updated when licensed operations cease. Reviews of the Site Decommissioning Management Plan (SDMP) program found that, while the NRC staff was overseeing the decommissioning program at nuclear facilities in a manner that was protective of public health and safety, progress in decommissioning many sites was slow. As a result NRC determined that formal written procedures should be developed to facilitate the timely decommissioning of licensed nuclear facilities. This handbook was developed to aid NRC staff in achieving this goal. It is intended to be used as a reference document to, and in conjunction with, NRC Inspection Manual Chapter (IMC) 2605, ``Decommissioning Inspection Program for Fuel Cycle and Materials Licensees.`` The policies and procedures discussed in this handbook should be used by NRC staff overseeing the decommissioning program at licensed fuel cycle and materials sites; formerly licensed sites for which the licenses were terminated; sites involving source, special nuclear, or byproduct material subject to NRC regulation for which a license was never issued; and sites in the NRC`s SDMP program. NRC staff overseeing the decommissioning program at nuclear reactor facilities subject to regulation under 10 CFR Part 50 are not required to use the procedures discussed in this handbook.

  18. Technology, safety and costs of decommissioning a reference boiling water reactor power station: Technical support for decommissioning matters related to preparation of the final decommissioning rule

    SciTech Connect

    Konzek, G.J.; Smith, R.I.

    1988-07-01

    Preparation of the final Decommissioning Rule by the Nuclear Regulatory Commission (NRC) staff has been assisted by Pacific Northwest Laboratory (PNL) staff familiar with decommissioning matters. These efforts have included updating previous cost estimates developed during the series of studies of conceptually decommissioning reference licensed nuclear facilities for inclusion in the Final Generic Environmental Impact Statement (FGEIS) on decommissioning; documenting the cost updates; evaluating the cost and dose impacts of post-TMI-2 backfits on decommissioning; developing a revised scaling formula for estimating decommissioning costs for reactor plants different in size from the reference boiling water reactor (BWR) described in the earlier study; and defining a formula for adjusting current cost estimates to reflect future escalation in labor, materials, and waste disposal costs. This report presents the results of recent PNL studies to provide supporting information in three areas concerning decommissioning of the reference BWR: updating the previous cost estimates to January 1986 dollars; assessing the cost and dose impacts of post-TMI-2 backfits; and developing a scaling formula for plants different in size than the reference plant and an escalation formula for adjusting current cost estimates for future escalation.

  19. Shippingport Station Decommissioning Project decommissioning plan. Volume XII

    SciTech Connect

    Not Available

    1983-01-01

    Information is presented concerning allowable residual contamination levels in soil for decommissioning the Shippingport reactor site; draft statement of work for the decommissioning operations contractor; the Shippingport Station Decommissioning Project Change Control Board charter; the surplus facilities management program; the Shippingport Station Decommissioning Project charter; DOE-RL/DOE-PNR program management agreement; and draft occupational medical plan for the decommissioning project.

  20. A review of decommissioning considerations for new reactors

    SciTech Connect

    Devgun, J.S.Ph.D.

    2008-07-01

    At a time of 'nuclear renaissance' when the focus is on advanced reactor designs and construction, it is easy to overlook the decommissioning considerations because such a stage in the life of the new reactors will be some sixty years down the road. Yet, one of the lessons learned from major decommissioning projects has been that decommissioning was not given much thought when these reactors were designed three or four decades ago. Hence, the time to examine what decommissioning considerations should be taken into account is right from the design stage with regular updates of the decommissioning strategy and plans throughout the life cycle of the reactor. Designing D and D into the new reactor designs is necessary to ensure that the tail end costs of the nuclear power are manageable. Such considerations during the design stage will facilitate a more cost-effective, safe and timely decommissioning of the facility when a reactor is eventually retired. This paper examines the current regulatory and industry design guidance for the new reactors with respect to the decommissioning issues and provides a review of the design considerations that can help optimize the reactor designs for the eventual decommissioning. (authors)

  1. Decommissioning at AWE

    SciTech Connect

    Biles, K.; Hedges, M.; Campbell, C

    2008-07-01

    AWE (A) has been at the heart of the UK Nuclear deterrent since it was established in the early 1950's. It is a nuclear licensed site and is governed by the United Kingdoms Nuclear Installation Inspectorate (NII). AWE plc on behalf of the Ministry of Defence (MOD) manages the AWE (A) site and all undertakings including decommissioning. Therefore under NII license condition 35 'Decommissioning', AWE plc is accountable to make and implement adequate arrangements for the decommissioning of any plant or process, which may affect safety. The majority of decommissioning projects currently being undertaken are to do with Hazard category 3, 4 or 5 facilities, systems or plant that have reached the end of their operational span and have undergone Post-Operational Clean-Out (POCO). They were either built for the production of fissile components, for supporting the early reactor fuels programmes or for processing facility waste arisings. They either contain redundant contaminated gloveboxes associated process areas, process plant or systems or a combination of all. In parallel with decommissioning project AWE (A) are undertaking investigation into new technologies to aid decommissioning projects; to remove the operative from hands on operations; to develop and implement modifications to existing process and techniques used. AWE (A) is currently going thorough a sustained phase of upgrading its facilities to enhance its scientific capability, with older facilities, systems and plant being replaced, making decommissioning a growth area. It is therefore important to the company to reduce these hazards progressively and safety over the coming years, making decommissioning an important feature of the overall legacy management aspects of AWE PLC's business. This paper outlines the current undertakings and progress of Nuclear decommissioning on the AWE (A) site. (authors)

  2. Preliminary decommissioning study reports

    SciTech Connect

    Peretz, F.J.

    1984-09-01

    The Molten Salt Reactor Experiment (MSRE) is one of approximately 76 facilities currently managed by the ORNL Surplus Facilities Management Program (SFMP). This program, as part of the DOE national SFMP, is responsible for the maintenance and surveillance and the final decommissioning of radioactively-contaminated surplus ORNL facilities. A long range planning effort is being conducted that will outline the scope and objectives of the ORNL program and establish decommissioning priorities based on health and safety concerns, budget constraints, and other programmatic constraints. In support of this SFMP planning activity, preliminary engineering assessments are being conducted for each of the ORNL surplus facilities currently managed under the program. These efforts, in general, are designed to: (1) provide an initial assessment of the potential decommissioning alternatives; (2) choose a preferred alternative and provide a justification for that choice, and (3) provide a preliminary description of the decommissioning plan, including cost and schedule estimates. Because of several issues which cannot be evaluated quantitatively at this time, this report on the MSRE does not select a most probable decommissioning mode'' but rather discusses the issues and representative alternatives for disposal of the MSRE fuel salts and decommissioning of the facility. A budget and schedule representative of the types of activities likely to be required is also suggested for preliminary use in the SFMP Long Range Plan.

  3. EVALUATION OF SPRING OPERATED RELIEF VALVE MAINTENANCE INTERVALS AND EXTENSION OF MAINTENANCE TIMES USING A WEIBULL ANALYSIS WITH MODIFIED BAYESIAN UPDATING

    SciTech Connect

    Harris, S.; Gross, R.; Mitchell, E.

    2011-01-18

    The Savannah River Site (SRS) spring operated pressure relief valve (SORV) maintenance intervals were evaluated using an approach provided by the American Petroleum Institute (API RP 581) for risk-based inspection technology (RBI). In addition, the impact of extending the inspection schedule was evaluated using Monte Carlo Simulation (MCS). The API RP 581 approach is characterized as a Weibull analysis with modified Bayesian updating provided by SRS SORV proof testing experience. Initial Weibull parameter estimates were updated as per SRS's historical proof test records contained in the Center for Chemical Process Safety (CCPS) Process Equipment Reliability Database (PERD). The API RP 581 methodology was used to estimate the SORV's probability of failing on demand (PFD), and the annual expected risk. The API RP 581 methodology indicates that the current SRS maintenance plan is conservative. Cost savings may be attained in certain mild service applications that present low PFD and overall risk. Current practices are reviewed and recommendations are made for extending inspection intervals. The paper gives an illustration of the inspection costs versus the associated risks by using API RP 581 Risk Based Inspection (RBI) Technology. A cost effective maintenance frequency balancing both financial risk and inspection cost is demonstrated.

  4. Site decommissioning management plan

    SciTech Connect

    Fauver, D.N.; Austin, J.H.; Johnson, T.C.; Weber, M.F.; Cardile, F.P.; Martin, D.E.; Caniano, R.J.; Kinneman, J.D.

    1993-10-01

    The Nuclear Regulatory Commission (NRC) staff has identified 48 sites contaminated with radioactive material that require special attention to ensure timely decommissioning. While none of these sites represent an immediate threat to public health and safety they have contamination that exceeds existing NRC criteria for unrestricted use. All of these sites require some degree of remediation, and several involve regulatory issues that must be addressed by the Commission before they can be released for unrestricted use and the applicable licenses terminated. This report contains the NRC staff`s strategy for addressing the technical, legal, and policy issues affecting the timely decommissioning of the 48 sites and describes the status of decommissioning activities at the sites.

  5. Development of a Preliminary Decommissioning Plan Following the International Structure for Decommissioning Costing (ISDC) of Nuclear Installations - 13361

    SciTech Connect

    Moshonas Cole, Katherine; Dinner, Julia; Grey, Mike; Daniska, Vladimir

    2013-07-01

    The International Structure for Decommissioning Costing (ISDC) of Nuclear Installations, published by OECD/NEA, IAEA and EC is intended to provide a uniform list of cost items for decommissioning projects and provides a standard format that permits international cost estimates to be compared. Candesco and DECOM have used the ISDC format along with two costing codes, OMEGA and ISDCEX, developed from the ISDC by DECOM, in three projects: the development of a preliminary decommissioning plan for a multi-unit CANDU nuclear power station, updating the preliminary decommissioning cost estimates for a prototype CANDU nuclear power station and benchmarking the cost estimates for CANDU against the cost estimates for other reactor types. It was found that the ISDC format provides a well defined and transparent basis for decommissioning planning and cost estimating that assists in identifying gaps and weaknesses and facilitates the benchmarking against international experience. The use of the ISDC can also help build stakeholder confidence in the reliability of the plans and estimates and the adequacy of decommissioning funding. (authors)

  6. INTERNATIONAL DECOMMISSIONING SYMPOSIUM 2000

    SciTech Connect

    M.A. Ebadian, Ph.D.

    2001-01-01

    The purpose of IDS 2000 was to deliver a world-class conference on applicable global environmental issues. The objective of this conference was to publicize environmental progress of individual countries, to provide a forum for technology developer and problem-holder interaction, to facilitate environmental and technology discussions between the commercial and financial communities, and to accommodate information and education exchange between governments, industries, universities, and scientists. The scope of this project included the planning and execution of an international conference on the decommissioning of nuclear facilities, and the providing of a business forum for vendors and participants sufficient to attract service providers, technology developers, and the business and financial communities. These groups, when working together with attendees from regulatory organizations and government decision-maker groups, provide an opportunity to more effectively and efficiently expedite the decommissioning projects.

  7. The Regulatory Challenges of Decommissioning Nuclear Power Plants in Korea - 13101

    SciTech Connect

    Lee, Jungjoon; Ahn, Sangmyeon; Choi, Kyungwoo; Kim, Juyoul; Kim, Juyub

    2013-07-01

    As of 2012, 23 units of nuclear power plants are in operation, but there is no experience of permanent shutdown and decommissioning of nuclear power plant in Korea. It is realized that, since late 1990's, improvement of the regulatory framework for decommissioning has been emphasized constantly from the point of view of International Atomic Energy Agency (IAEA)'s safety standards. And it is known that now IAEA prepare the safety requirement on decommissioning of facilities, its title is the Safe Decommissioning of Facilities, General Safety Requirement Part 6. According to the result of IAEA's Integrated Regulatory Review Service (IRRS) mission to Korea in 2011, it was recommended that the regulatory framework for decommissioning should require decommissioning plans for nuclear installations to be constructed and operated and these plans should be updated periodically. In addition, after the Fukushima nuclear disaster in Japan in March of 2011, preparedness for early decommissioning caused by an unexpected severe accident became also important issues and concerns. In this respect, it is acknowledged that the regulatory framework for decommissioning of nuclear facilities in Korea need to be improved. First of all, we identify the current status and relevant issues of regulatory framework for decommissioning of nuclear power plants compared to the IAEA's safety standards in order to achieve our goal. And then the plan is to be established for improvement of regulatory framework for decommissioning of nuclear power plants in Korea. After dealing with it, it is expected that the revised regulatory framework for decommissioning could enhance the safety regime on the decommissioning of nuclear power plants in Korea in light of international standards. (authors)

  8. International Research Reactor Decommissioning Project

    SciTech Connect

    Leopando, Leonardo; Warnecke, Ernst

    2008-01-15

    Many research reactors have been or will be shut down and are candidates for decommissioning. Most of the respective countries neither have a decommissioning policy nor the required expertise and funds to effectively implement a decommissioning project. The IAEA established the Research Reactor Decommissioning Demonstration Project (R{sup 2}D{sup 2}P) to help answer this need. It was agreed to involve the Philippine Research Reactor (PRR-1) as model reactor to demonstrate 'hands-on' experience as it is just starting the decommissioning process. Other facilities may be included in the project as they fit into the scope of R{sup 2}D{sup 2}P and complement to the PRR-1 decommissioning activities. The key outcome of the R{sup 2}D{sup 2}P will be the decommissioning of the PRR-1 reactor. On the way to this final goal the preparation of safety related documents (i.e., decommissioning plan, environmental impact assessment, safety analysis report, health and safety plan, cost estimate, etc.) and the licensing process as well as the actual dismantling activities could provide a model to other countries involved in the project. It is expected that the R{sup 2}D{sup 2}P would initiate activities related to planning and funding of decommissioning activities in the participating countries if that has not yet been done.

  9. ORNL decontamination and decommissioning program

    SciTech Connect

    Bell, J. P.

    1980-01-01

    A program has been initiated at ORNL to decontaminate and decommission surplus or abandoned nuclear facilities. Program planning and technical studies have been performed by UCC-ND Engineering. A feasibility study for decommissioning the Metal Recovery Facility, a fuel reprocessing pilot plant, has been completed.

  10. Remote Decommissioning Experiences at Sellafield

    SciTech Connect

    Brownridge, M.

    2006-07-01

    British Nuclear Group has demonstrated through delivery of significant decommissioning projects the ability to effectively deploy innovative remote decommissioning technologies and deliver cost effective solutions. This has been achieved through deployment and development of off-the-shelf technologies and design of bespoke equipment. For example, the worlds first fully remotely operated Brokk was successfully deployed to enable fully remote dismantling, packaging and export of waste during the decommissioning of a pilot reprocessing facility. British Nuclear Group has also successfully implemented remote decommissioning systems to enable the decommissioning of significant challenges, including dismantling of a Caesium Extraction Facility, Windscale Pile Chimney and retrieval of Plutonium Contaminated Material (PCM) from storage cells. The challenge for the future is to continue to innovate through utilization of the supply chain and deploy off-the-shelf technologies which have been demonstrated in other industry sectors, thus reducing implementation schedules, cost and maintenance. (authors)

  11. Offshore-platform decommissioning perceptions change

    SciTech Connect

    Twachtman, R.

    1997-12-08

    The oil and gas industry has seen a change in the perceptions about decommissioning offshore facilities. Now, decommissioning projects are being planned ahead of actual field development, and new concepts derived during decommissioning often are used to provide feedback for new development projects. The current trends and concepts applicable to decommissioning can be summarized as: advanced planning; engineered solutions; research and development; reuse; expanded use of offshore reefs; and deepwater disposal. Planning the platform decommissioning ahead of time (at least 2 years before production ceases) is key to a safe, environmentally conscious, and efficient decommissioning project. The paper discusses decommissioning projects, engineered solutions, research and development; reuse of platforms, and deepwater disposal.

  12. Decontamination & decommissioning focus area

    SciTech Connect

    1996-08-01

    In January 1994, the US Department of Energy Office of Environmental Management (DOE EM) formally introduced its new approach to managing DOE`s environmental research and technology development activities. The goal of the new approach is to conduct research and development in critical areas of interest to DOE, utilizing the best talent in the Department and in the national science community. To facilitate this solutions-oriented approach, the Office of Science and Technology (EM-50, formerly the Office of Technology Development) formed five Focus AReas to stimulate the required basic research, development, and demonstration efforts to seek new, innovative cleanup methods. In February 1995, EM-50 selected the DOE Morgantown Energy Technology Center (METC) to lead implementation of one of these Focus Areas: the Decontamination and Decommissioning (D & D) Focus Area.

  13. Money Related Decommissioning and Funding Decision Making

    SciTech Connect

    Goodman, Lynne S.

    2008-01-15

    'Money makes the world go round', as the song says. It definitely influences decommissioning decision-making and financial assurance for future decommissioning. This paper will address two money-related decommissioning topics. The first is the evaluation of whether to continue or to halt decommissioning activities at Fermi 1. The second is maintaining adequacy of financial assurance for future decommissioning of operating plants. Decommissioning costs considerable money and costs are often higher than originally estimated. If costs increase significantly and decommissioning is not well funded, decommissioning activities may be deferred. Several decommissioning projects have been deferred when decision-makers determined future spending is preferable than current spending, or when costs have risen significantly. Decommissioning activity timing is being reevaluated for the Fermi 1 project. Assumptions for waste cost-escalation significantly impact the decision being made this year on the Fermi 1 decommissioning project. They also have a major impact on the estimated costs for decommissioning currently operating plants. Adequately funding full decommissioning during plant operation will ensure that the users who receive the benefit pay the full price of the nuclear-generated electricity. Funding throughout operation also will better ensure that money is available following shutdown to allow decommissioning to be conducted without need for additional funds.

  14. Recent Trends in the Adequacy of Nuclear Plant Decommissioning Funding

    SciTech Connect

    Williams, D. G.

    2002-02-26

    Concerned about the potential cost and sufficiency of funds to decommission the nation's nuclear power plants, the Congress asked the U.S. General Accounting Office (GAO) to assess the adequacy, as of December 31, 1997, of electric utilities'; funds to eventually decommission their plants. GAO's report (GAO/RCED-99-75) on this issue addressed three alternative assumption scenarios--baseline (most likely), optimistic, and pessimistic; and was issued in May 1999. This paper updates GAO's baseline assessment of fund adequacy in 1997, and extends the analysis through 2000. In 2000, we estimate that the present value cost to decommission the nation's nuclear plants is about $35 billion; utility fund balances are about $29 billion. Both our two measures of funding adequacy for utilities are on average not only much above ideal levels, but also overall have greatly improved since 1997. However, certain utilities still show less than ideal fund balances and annual contributions. We suggest that the range of these results among the individual utilities is a more important policy measure to assess the adequacy of decommissioning funding than is the funding adequacy for the industry as a whole.

  15. 77 FR 41107 - Decommissioning Planning During Operations

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-07-12

    ... Decommissioning Planning Rule (DPR) (June 17, 2011, 76 FR 33512). The DPR applies to the operational phase of a..., ``Decommissioning Planning During Operations'' (December 13, 2011, 76 FR 77431). The NRC received more than 100...; ] NUCLEAR REGULATORY COMMISSION 10 CFR Parts 20, 30, 40, 50, 70, and 72 Decommissioning Planning...

  16. 76 FR 35511 - Decommissioning Planning

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-06-17

    ... regulations in 1997 as Subpart E of 10 CFR part 20 (62 FR 39058; July 21, 1997). This set of requirements is... the January 27, 1988 (53 FR 24018), rule on planning for decommissioning require licensees to provide... contamination and the amount of funds set aside and expended on cleanup. (62 FR 39082; July 21, 1997)....

  17. Decontamination & Decommissioning Equipment Tracking System (DDETS)

    SciTech Connect

    Cook, S.

    1994-07-01

    At the request of the Department of Energy (DOE)(EM-50), the Scientific Computing Unit developed a prototype system to track information and data relevant to equipment and tooling removed during decontamination and decommissioning activities. The DDETS proof-of-concept tracking system utilizes a one-dimensional (1D) and two-dimensional (2D) bar coding technology to retain and track information such as identification number, manufacturer, requisition information, and various contaminant information, etc. The information is encoded in a bar code, printed on a label and can be attached to corresponding equipment. The DDETS was developed using a proven relational database management system which allows the addition, modification, printing, and deletion of data. In addition, communication interfaces with bar code printers and bar code readers were developed. Additional features of the system include: (a) Four different reports available for the user (REAPS, transaction, and two inventory), (b) Remote automated inventory tracking capabilities, (c) Remote automated inventory tracking capability (2D bar codes allow equipment to be scanned/tracked without being linked to the DDETS database), (d) Edit, update, delete, and query capabilities, (e) On-line bar code label printing utility (data from 2D bar codes can be scanned directly into the data base simplifying data entry), and (f) Automated data backup utility. Compatibility with the Reportable Excess Automated Property System (REAPS) to upload data from DDETS is planned.

  18. Decontamination, decommissioning, and vendor advertorial issue, 2005

    SciTech Connect

    Agnihotri, Newal

    2005-07-15

    The focus of the July-August issue is on Decontamination, decommissioning, and vendor advertorials. Major interviews, articles and reports in this issue include: Increasing momentum, by Gary Taylor, Entergy Nuclear, Inc.; An acceptable investment, by Tom Chrisopher, Areva, Inc.; Fuel recycling for the U.S. and abroad, by Philippe Knoche, Areva, France; We're bullish on nuclear power, by Dan R. Keuter, Entergy Nuclear, Inc.; Ten key actions for decommissioning, by Lawrence E. Boing, Argonne National Laboratory; Safe, efficient and cost-effective decommissioning, by Dr. Claudio Pescatore and Torsten Eng, OECD Nuclear Energy Agency (NEA), France; and, Plant profile: SONGS decommissioning.

  19. Spring Tire

    NASA Technical Reports Server (NTRS)

    Asnani, Vivake M.; Benzing, Jim; Kish, Jim C.

    2011-01-01

    The spring tire is made from helical springs, requires no air or rubber, and consumes nearly zero energy. The tire design provides greater traction in sandy and/or rocky soil, can operate in microgravity and under harsh conditions (vastly varying temperatures), and is non-pneumatic. Like any tire, the spring tire is approximately a toroidal-shaped object intended to be mounted on a transportation wheel. Its basic function is also similar to a traditional tire, in that the spring tire contours to the surface on which it is driven to facilitate traction, and to reduce the transmission of vibration to the vehicle. The essential difference between other tires and the spring tire is the use of helical springs to support and/or distribute load. They are coiled wires that deform elastically under load with little energy loss.

  20. Austin Community College Benchmarking Update.

    ERIC Educational Resources Information Center

    Austin Community Coll., TX. Office of Institutional Effectiveness.

    Austin Community College contracted with MGT of America, Inc. in spring 1999 to develop a peer and benchmark (best) practices analysis on key indicators. These indicators were updated in spring 2002 using data from eight Texas community colleges and four non-Texas institutions that represent large, comprehensive, urban community colleges, similar…

  1. STANDARD OPERATING PROTOCOLS FOR DECOMMISSIONING

    SciTech Connect

    Foss, D. L.; Stevens, J. L.; Gerdeman, F. W.

    2002-02-25

    Decommissioning projects at Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) sites are conducted under project-specific decision documents, which involve extensive preparation time, public comment periods, and regulatory approvals. Often, the decision documents must be initiated at least one year before commencing the decommissioning project, and they are expensive and time consuming to prepare. The Rocky Flats Environmental Technology Site (RFETS) is a former nuclear weapons production plant at which hazardous substances and wastes were released or disposed during operations. As a result of the releases, RFETS was placed on the National Priorities List in 1989, and is conducting cleanup activities under a federal facilities compliance agreement. Working closely with interested stakeholders and state and federal regulatory agencies, RFETS has developed and implemented an improved process for obtaining the approvals. The key to streamlining the approval process has been the development of sitewide decision documents called Rocky Flats Cleanup Agreement Standard Operating Protocols or ''RSOPs.'' RSOPs have broad applicability, and could be used instead of project-specific documents. Although no two decommissioning projects are exactly the same and they may vary widely in contamination and other hazards, the basic steps taken for cleanup are usually similar. Because of this, using RSOPs is more efficient than preparing a separate project-specific decision documents for each cleanup action. Over the Rocky Flats cleanup life cycle, using RSOPs has the potential to: (1) Save over 5 million dollars and 6 months on the site closure schedule; (2) Eliminate preparing one hundred and twenty project-specific decision documents; and (3) Eliminate writing seventy-five closure description documents for hazardous waste unit closure and corrective actions.

  2. 76 FR 3837 - Nuclear Decommissioning Funds; Correction

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-01-21

    ... 23, 2010 (75 FR 80697) relating to deductions for contributions to trusts maintained for decommissioning nuclear power plants. DATES: This correction is effective on January 21, 2011, and is applicable... Internal Revenue Service 26 CFR Part 1 RIN 1545-BF08 Nuclear Decommissioning Funds; Correction...

  3. Technology needs for decommissioning and decontamination

    SciTech Connect

    Bundy, R.D.; Kennerly, J.M.

    1993-12-01

    This report summarizes the current view of the most important decontamination and decommissioning (D & D) technology needs for the US Department of Energy facilities for which the D & D programs are the responsibility of Martin Marietta Energy Systems, Inc. The source of information used in this assessment was a survey of the D & D program managers at each facility. A summary of needs presented in earlier surveys of site needs in approximate priority order was supplied to each site as a starting point to stimulate thinking. This document reflects a brief initial assessment of ongoing needs; these needs will change as plans for D & D are finalized, some of the technical problems are solved through successful development programs, and new ideas for D and D technologies appear. Thus, this assessment should be updated and upgraded periodically, perhaps, annually. This assessment differs from others that have been made in that it directly and solely reflects the perceived need for new technology by key personnel in the D & D programs at the various facilities and does not attempt to consider the likelihood that these technologies can be successfully developed. Thus, this list of technology needs also does not consider the cost, time, and effort required to develop the desired technologies. An R & D program must include studies that have a reasonable chance for success as well as those for which there is a high need. Other studies that considered the cost and probability of successful development as well as the need for new technology are documented. However, the need for new technology may be diluted in such studies; this document focuses only on the need for new technology as currently perceived by those actually charged with accomplishing D & D.

  4. Pipeline Decommissioning Trial AWE Berkshire UK - 13619

    SciTech Connect

    Agnew, Kieran

    2013-07-01

    This Paper details the implementation of a 'Decommissioning Trial' to assess the feasibility of decommissioning the redundant pipeline operated by AWE located in Berkshire UK. The paper also presents the tool box of decommissioning techniques that were developed during the decommissioning trial. Constructed in the 1950's and operated until 2005, AWE used a pipeline for the authorised discharge of treated effluent. Now redundant, the pipeline is under a care and surveillance regime awaiting decommissioning. The pipeline is some 18.5 km in length and extends from AWE site to the River Thames. Along its route the pipeline passes along and under several major roads, railway lines and rivers as well as travelling through woodland, agricultural land and residential areas. Currently under care and surveillance AWE is considering a number of options for decommissioning the pipeline. One option is to remove the pipeline. In order to assist option evaluation and assess the feasibility of removing the pipeline a decommissioning trial was undertaken and sections of the pipeline were removed within the AWE site. The objectives of the decommissioning trial were to: - Demonstrate to stakeholders that the pipeline can be removed safely, securely and cleanly - Develop a 'tool box' of methods that could be deployed to remove the pipeline - Replicate the conditions and environments encountered along the route of the pipeline The onsite trial was also designed to replicate the physical prevailing conditions and constraints encountered along the remainder of its route i.e. working along a narrow corridor, working in close proximity to roads, working in proximity to above ground and underground services (e.g. Gas, Water, Electricity). By undertaking the decommissioning trial AWE have successfully demonstrated the pipeline can be decommissioned in a safe, secure and clean manor and have developed a tool box of decommissioning techniques. The tool box of includes; - Hot tapping - a method

  5. TA-2 Water Boiler Reactor Decommissioning Project

    SciTech Connect

    Durbin, M.E.; Montoya, G.M.

    1991-06-01

    This final report addresses the Phase 2 decommissioning of the Water Boiler Reactor, biological shield, other components within the biological shield, and piping pits in the floor of the reactor building. External structures and underground piping associated with the gaseous effluent (stack) line from Technical Area 2 (TA-2) Water Boiler Reactor were removed in 1985--1986 as Phase 1 of reactor decommissioning. The cost of Phase 2 was approximately $623K. The decommissioning operation produced 173 m{sup 3} of low-level solid radioactive waste and 35 m{sup 3} of mixed waste. 15 refs., 25 figs., 3 tabs.

  6. Modelling of nuclear power plant decommissioning financing.

    PubMed

    Bemš, J; Knápek, J; Králík, T; Hejhal, M; Kubančák, J; Vašíček, J

    2015-06-01

    Costs related to the decommissioning of nuclear power plants create a significant financial burden for nuclear power plant operators. This article discusses the various methodologies employed by selected European countries for financing of the liabilities related to the nuclear power plant decommissioning. The article also presents methodology of allocation of future decommissioning costs to the running costs of nuclear power plant in the form of fee imposed on each megawatt hour generated. The application of the methodology is presented in the form of a case study on a new nuclear power plant with installed capacity 1000 MW. PMID:25979740

  7. Modelling of nuclear power plant decommissioning financing.

    PubMed

    Bemš, J; Knápek, J; Králík, T; Hejhal, M; Kubančák, J; Vašíček, J

    2015-06-01

    Costs related to the decommissioning of nuclear power plants create a significant financial burden for nuclear power plant operators. This article discusses the various methodologies employed by selected European countries for financing of the liabilities related to the nuclear power plant decommissioning. The article also presents methodology of allocation of future decommissioning costs to the running costs of nuclear power plant in the form of fee imposed on each megawatt hour generated. The application of the methodology is presented in the form of a case study on a new nuclear power plant with installed capacity 1000 MW.

  8. Decommissioning the Research Nuclear Reactor Vvr-S Magurele - Analyze, Justification and Selection of Decommissioning Strategy

    NASA Astrophysics Data System (ADS)

    Dragusin, M.; Popa, V.; Boicu, A.; Tuca, C.; Iorga, I.; Mustata, C.

    2004-09-01

    The decommissioning of Research Nuclear Reactor VVR-S Magurele - Bucharest involves the removal of the radioactive and hazardous materials to permit the facility to be released without representing a further risk to human health and the environment [1-3]. A very important aspect of decommissioning is the analyze, justification and selection of the decommissioning strategy. Two strategies: DECON (Immediate Dismantling) and SAFSTOR (Safe Enclosure) are in study (see Table 1)... Note from Publisher: This article contains the abstract and references only.

  9. Russian nuclear-powered submarine decommissioning

    SciTech Connect

    Bukharin, O.; Handler, J.

    1995-11-01

    Russia is facing technical, economic and organizational difficulties in dismantling its oversized and unsafe fleet of nuclear powered submarines. The inability of Russia to deal effectively with the submarine decommissioning crisis increases the risk of environmental disaster and may hamper the implementation of the START I and START II treaties. This paper discusses the nuclear fleet support infrastructure, the problems of submarine decommissioning, and recommends international cooperation in addressing these problems.

  10. Safety of Decommissioning of Nuclear Facilities

    SciTech Connect

    Batandjieva, B.; Warnecke, E.; Coates, R.

    2008-01-15

    Full text of publication follows: ensuring safety during all stages of facility life cycle is a widely recognised responsibility of the operators, implemented under the supervision of the regulatory body and other competent authorities. As the majority of the facilities worldwide are still in operation or shutdown, there is no substantial experience in decommissioning and evaluation of safety during decommissioning in majority of Member States. The need for cooperation and exchange of experience and good practices on ensuring and evaluating safety of decommissioning was one of the outcomes of the Berlin conference in 2002. On this basis during the last three years IAEA initiated a number of international projects that can assist countries, in particular small countries with limited resources. The main IAEA international projects addressing safety during decommissioning are: (i) DeSa Project on Evaluation and Demonstration of Safety during Decommissioning; (ii) R{sup 2}D{sup 2}P project on Research Reactors Decommissioning Demonstration Project; and (iii) Project on Evaluation and Decommissioning of Former Facilities that used Radioactive Material in Iraq. This paper focuses on the DeSa Project activities on (i) development of a harmonised methodology for safety assessment for decommissioning; (ii) development of a procedure for review of safety assessments; (iii) development of recommendations on application of the graded approach to the performance and review of safety assessments; and (iv) application of the methodology and procedure to the selected real facilities with different complexities and hazard potentials (a nuclear power plant, a research reactor and a nuclear laboratory). The paper also outlines the DeSa Project outcomes and planned follow-up activities. It also summarises the main objectives and activities of the Iraq Project and introduces the R{sup 2}D{sup 2} Project, which is a subject of a complementary paper.

  11. Decommissioning of the Iraq former nuclear complex

    SciTech Connect

    Abbas, Mohammed; Helou, Tuama; Ahmead, Bushra; Al-Atia, Mousa; Al-Mubarak, Mowaffak; Danneels, Jeffrey; Cochran, John; Sorenson, Ken; Coates, Roger

    2007-07-01

    Available in abstract form only. Full text of publication follows: A number of sites in Iraq have some degree of radiological contamination and require decommissioning and remediation in order to ensure radiological safety. Many of these sites in Iraq are located at the nuclear research centre at Al Tuwaitha. The International Atomic Energy Agency (IAEA) Board of Governors has approved a project to assist the Government of Iraq in the evaluation and decommissioning of former facilities that used radioactive materials. The project is divided into three phases: Phase 1: collect and analyze all available data and conduct training of the Iraqi staff, Phase 2: develop a decommissioning and remediation plan, and Phase 3: implement field activities relating to decommissioning, remediation and site selection suitable for final disposal of waste. Four working groups have been established to complete the Phase 1 work and significant progress has been made in drafting a new nuclear law which will provide the legal basis for the licensing of the decommissioning of the former nuclear complex. Work is also underway to collect and analysis existing date, to prioritize future activities and to develop a waste management strategy. This will be a long-term and costly project. (authors)

  12. Development of improved technology for decommissioning operations

    SciTech Connect

    Allen, R.P.

    1982-07-01

    This paper describes the technology development activities conducted at Pacific Northwest Laboratory under US Department of Energy sponsorship to help ensure the availability of safe, cost-effective and environmentally sound decommissioning technology for radioactively contaminated facilities. These improved decommissioning technologies include techniques for the removal of contaminated concrete surfaces and coatings, adaptation of electropolishing and vibratory finishing decontamination techniques for field decommissioning applications, development of sensitive field instrumentation and methods for the monitoring of large surface areas, techniques for the field sectioning of contaminated components, improved contamination-stabilizing coatings and application methods, and development of a small solidification system for the field solidification of liquid waste. The results of cost/benefit studies for some of these technologies are also reported.

  13. 26 CFR 1.88-1 - Nuclear decommissioning costs.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 26 Internal Revenue 2 2012-04-01 2012-04-01 false Nuclear decommissioning costs. 1.88-1 Section 1... (CONTINUED) INCOME TAXES (CONTINUED) Items Specifically Included in Gross Income § 1.88-1 Nuclear decommissioning costs. (a) In general. Section 88 provides that the amount of nuclear decommissioning...

  14. 26 CFR 1.88-1 - Nuclear decommissioning costs.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 26 Internal Revenue 2 2014-04-01 2014-04-01 false Nuclear decommissioning costs. 1.88-1 Section 1... (CONTINUED) INCOME TAXES (CONTINUED) Items Specifically Included in Gross Income § 1.88-1 Nuclear decommissioning costs. (a) In general. Section 88 provides that the amount of nuclear decommissioning...

  15. 26 CFR 1.88-1 - Nuclear decommissioning costs.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 26 Internal Revenue 2 2013-04-01 2013-04-01 false Nuclear decommissioning costs. 1.88-1 Section 1... (CONTINUED) INCOME TAXES (CONTINUED) Items Specifically Included in Gross Income § 1.88-1 Nuclear decommissioning costs. (a) In general. Section 88 provides that the amount of nuclear decommissioning...

  16. 26 CFR 1.88-1 - Nuclear decommissioning costs.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 26 Internal Revenue 2 2011-04-01 2011-04-01 false Nuclear decommissioning costs. 1.88-1 Section 1... (CONTINUED) INCOME TAXES (CONTINUED) Items Specifically Included in Gross Income § 1.88-1 Nuclear decommissioning costs. (a) In general. Section 88 provides that the amount of nuclear decommissioning...

  17. 26 CFR 1.88-1 - Nuclear decommissioning costs.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 26 Internal Revenue 2 2010-04-01 2010-04-01 false Nuclear decommissioning costs. 1.88-1 Section 1... (CONTINUED) INCOME TAXES (CONTINUED) Items Specifically Included in Gross Income § 1.88-1 Nuclear decommissioning costs. (a) In general. Section 88 provides that the amount of nuclear decommissioning...

  18. Decision framework for platform decommissioning in California.

    PubMed

    Bernstein, Brock B

    2015-10-01

    This article describes the overall decision framework for eventual decisions about decommissioning the 27 operating oil and gas platforms offshore southern California. These platforms will eventually reach the end of their useful lifetimes (estimated between 2015 and 2030, although specific dates have not been determined). Current law and regulations allow for alternative uses in lieu of the complete removal required in existing leases. To prepare for eventual decommissioning, the California Natural Resources Agency initiated an in-depth process to identify and investigate issues surrounding possible decommissioning alternatives. The detailed evaluation of alternatives focused on 2-complete removal and artificial reefing that included partial removal to 85 feet below the waterline. These were selected after a comparison of the technical and economic feasibility of several potential alternatives, availability of a legal framework for implementation, degree of interest from proponents, and relative acceptance by state and federal decision makers. Despite California's history of offshore oil and gas production, only 7 decommissioning projects have been completed and these were all relatively small and close to shore. In contrast, nearly 30% of the California platforms are in water depths (as much as 1200 feet) that exceed any decommissioning project anywhere in the world. Most earlier projects considered an artificial reefing alternative but none were implemented and all platforms were completely removed. Future decisions about decommissioning must grapple with a more complex decision context involving greater technological and logistical challenges and cost, a wider range of viable options, tradeoffs among environmental impacts and benefits, and an intricate maze of laws, regulations, and authorities. The specific engineering differences between complete and partial removal provide an explicit basis for a thorough evaluation of their respective impacts.

  19. Decision framework for platform decommissioning in California.

    PubMed

    Bernstein, Brock B

    2015-10-01

    This article describes the overall decision framework for eventual decisions about decommissioning the 27 operating oil and gas platforms offshore southern California. These platforms will eventually reach the end of their useful lifetimes (estimated between 2015 and 2030, although specific dates have not been determined). Current law and regulations allow for alternative uses in lieu of the complete removal required in existing leases. To prepare for eventual decommissioning, the California Natural Resources Agency initiated an in-depth process to identify and investigate issues surrounding possible decommissioning alternatives. The detailed evaluation of alternatives focused on 2-complete removal and artificial reefing that included partial removal to 85 feet below the waterline. These were selected after a comparison of the technical and economic feasibility of several potential alternatives, availability of a legal framework for implementation, degree of interest from proponents, and relative acceptance by state and federal decision makers. Despite California's history of offshore oil and gas production, only 7 decommissioning projects have been completed and these were all relatively small and close to shore. In contrast, nearly 30% of the California platforms are in water depths (as much as 1200 feet) that exceed any decommissioning project anywhere in the world. Most earlier projects considered an artificial reefing alternative but none were implemented and all platforms were completely removed. Future decisions about decommissioning must grapple with a more complex decision context involving greater technological and logistical challenges and cost, a wider range of viable options, tradeoffs among environmental impacts and benefits, and an intricate maze of laws, regulations, and authorities. The specific engineering differences between complete and partial removal provide an explicit basis for a thorough evaluation of their respective impacts. PMID:26259879

  20. Decontamination, decommissioning, and vendor advertorial issue, 2006

    SciTech Connect

    Agnihotri, Newal

    2006-07-15

    The focus of the July-August issue is on Decontamination, decommissioning, and vendor advertorials. Major articles/reports in this issue include: NPP Krsko revised decommissioning program, by Vladimir Lokner and Ivica Levanat, APO d.o.o., Croatia, and Nadja Zeleznik and Irena Mele, ARAO, Slovenia; Supporting the renaissance, by Marilyn C. Kray, Exelon Nuclear; Outage world an engineer's delight, by Tom Chrisopher, Areva, NP Inc.; Optimizing refueling outages with R and D, by Ross Marcoot, GE Energy; and, A successful project, by Jim Lash, FirstEnergy.

  1. Decommissioning of a tritium-contaminated laboratory

    SciTech Connect

    Harper, J.R.; Garde, R.

    1981-11-01

    A tritium laboratory facility at the Los Alamos National Laboratory, Los Alamos, New Mexico, was decommissioned in 1979. The project involved dismantling the laboratory equipment and disposing of the equipment and debris at an on-site waste disposal/storage area. The laboratory was constructed in 1953 and was in service for tritium research and fabrication of lithium tritide components until 1974. The major features of the laboratory included some 25 meters of gloveboxes and hoods, associated vacuum lines, utility lines, exhaust ducts, electrodryers, blowers, and laboratory benches. This report presents details on the decommissioning, health physics, waste management, environmental surveillance, and costs for the operation.

  2. The health risks of decommissioning nuclear facilities.

    PubMed

    Dodic-Fikfak, M; Clapp, R; Kriebel, D

    1999-01-01

    The health risks facing workers involved in decommissioning nuclear facilities are a critical concern as the nuclear weapons complex and nuclear power plants begin to be dismantled. In addition to risks from exposure to radioactive materials, there are risks from other common industrial materials like crystalline silica dust and asbestos. We discuss these issues in the context of recent research on the risk of low-level ionizing radiation, the classification of crystalline silica as a carcinogen, and early experience with decommissioning nuclear facilities in the United States. Health and safety advocates will need to be vigilant to prevent worker exposure. PMID:17208791

  3. The health risks of decommissioning nuclear facilities.

    PubMed

    Dodic-Fikfak, M; Clapp, R; Kriebel, D

    1999-01-01

    The health risks facing workers involved in decommissioning nuclear facilities are a critical concern as the nuclear weapons complex and nuclear power plants begin to be dismantled. In addition to risks from exposure to radioactive materials, there are risks from other common industrial materials like crystalline silica dust and asbestos. We discuss these issues in the context of recent research on the risk of low-level ionizing radiation, the classification of crystalline silica as a carcinogen, and early experience with decommissioning nuclear facilities in the United States. Health and safety advocates will need to be vigilant to prevent worker exposure.

  4. 75 FR 80697 - Nuclear Decommissioning Funds

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-12-23

    ...This document contains final regulations under section 468A of the Internal Revenue Code relating to deductions for contributions to trusts maintained for decommissioning nuclear power plants. These final regulations affect taxpayers that own an interest in a nuclear power plant and reflect recent statutory changes. The corresponding temporary regulations are...

  5. Halons: The hidden dangers of accelerated decommissioning

    SciTech Connect

    Dalzell, G.A.

    1996-12-31

    Many operators have introduced a decommissioning programme for halon systems following the Montreal Protocol and the cessation of production of 1211 and 1301. Some have already decommissioned all their systems. This paper questions whether rapid decommissioning, particularly when faced with external pressure or a desire to be {open_quotes}seen to be green{close_quotes} does reduce the environmental impact. It examines the lifecycle of the halon in an existing system until it is finally destroyed, used, or lost to the atmosphere. Halon is one of the most difficult gases to contain. It is more prone to leakage than almost any other gas. Fixed systems, which contain the majority of 1301 also have valve arrangements which are designed to open with the minimum of energy input. As a result they are also prone to accidental discharge. This paper examines these aspects and the potential for loss to the atmosphere when decommissioning, transporting, recycling and storing the halon. Controlling leakage and preventing accidental discharges within systems has been addressed in other work.

  6. University of Virginia Reactor Facility Decommissioning Results

    SciTech Connect

    Ervin, P. F.; Lundberg, L. A.; Benneche, P. E.; Mulder, R. U.; Steva, D. P.

    2003-02-24

    The University of Virginia Reactor Facility started accelerated decommissioning in 2002. The facility consists of two licensed reactors, the CAVALIER and the UVAR. This paper will describe the progress in 2002, remaining efforts and the unique organizational structure of the project team.

  7. Decontamination and decommissioning focus area. Technology summary

    SciTech Connect

    1995-06-01

    This report presents details of the facility deactivation, decommissioning, and material disposition research for development of new technologies sponsored by the Department of Energy. Topics discussed include; occupational safety, radiation protection, decontamination, remote operated equipment, mixed waste processing, recycling contaminated metals, and business opportunities.

  8. Sodium Reactor Experiment decommissioning. Final report

    SciTech Connect

    Carroll, J.W.; Conners, C.C.; Harris, J.M.; Marzec, J.M.; Ureda, B.F.

    1983-08-15

    The Sodium Reactor Experiment (SRE) located at the Rockwell International Field Laboratories northwest of Los Angeles was developed to demonstrate a sodium-cooled, graphite-moderated reactor for civilian use. The reactor reached full power in May 1958 and provided 37 GWh to the Southern California Edison Company grid before it was shut down in 1967. Decommissioning of the SRE began in 1974 with the objective of removing all significant radioactivity from the site and releasing the facility for unrestricted use. Planning documentation was prepared to describe in detail the equipment and techniques development and the decommissioning work scope. A plasma-arc manipulator was developed for remotely dissecting the highly radioactive reactor vessels. Other important developments included techniques for using explosives to cut reactor vessel internal piping, clamps, and brackets; decontaminating porous concrete surfaces; and disposing of massive equipment and structures. The documentation defined the decommissioning in an SRE dismantling plan, in activity requirements for elements of the decommissioning work scope, and in detailed procedures for each major task.

  9. 78 FR 663 - Decommissioning Planning During Operations

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-01-04

    ... Federal Regulations is sold by the Superintendent of Documents. #0;Prices of new books are listed in the... complying with the NRC's Decommissioning Planning Rule (DPR) (76 FR 35512; June 17, 2011). The DPR went into... available documents online in the NRC Library at http://www.nrc.gov/reading-rm/adams.html . To begin...

  10. Decontamination and decommissioning of Shippingport commercial reactor

    SciTech Connect

    Schreiber, J.

    1989-11-01

    To a certain degree, the decontamination and decommissioning (D and D) of the Shippingport reactor was a joint venture with Duquesne Light Company. The structures that were to be decommissioned were to be removed to at least three feet below grade. Since the land had been leased from Duquesne Light, there was an agreement with them to return the land to them in a radiologically safe condition. The total enclosure volume for the steam and nuclear containment systems was about 1.3 million cubic feet, more than 80% of which was below ground. Engineering plans for the project were started in July of 1980 and the final environmental impact statement (EIS) was published in May of 1982. The plant itself was shut down in October of 1982 for end-of-life testing and defueling. The engineering services portion of the decommissioning plans was completed in September of 1983. DOE moved onto the site and took over from the Navy in September of 1984. Actual physical decommissioning began after about a year of preparation and was completed about 44 months later in July of 1989. This paper describes the main parts of D and D.

  11. UPDATE: Applications of Research in Music Education. UPDATE Yearbook

    ERIC Educational Resources Information Center

    Rowman & Littlefield Education, 2005

    2005-01-01

    The Fall 2004 and Spring 2005 issues of "UPDATE: Applications of Research in Music Education," in one print volume, presents hard facts and statistical data in a style that can be easily understood and appreciated by music researchers, teachers, graduates, and undergraduates alike. Includes advice to first-year music teachers, instrument…

  12. Reactor Design and Decommissioning - An Overview of International Activities in Post Fukushima Era1 - 12396

    SciTech Connect

    Devgun, Jas S.; Laraia, Michele; Dinner, Paul

    2012-07-01

    perspective in the post Fukushima -accident era. Accidents at the Fukushima Daiichi reactors in the aftermath of the devastating earthquake and tsunami of March 11, 2011 have slowed down the nuclear renaissance world-wide and may have accelerated decommissioning either because some countries have decided to halt or reduce nuclear, or because the new safety requirements may reduce life-time extensions. Even in countries such as the UK and France that favor nuclear energy production existing nuclear sites are more likely to be chosen as sites for future NPPs. Even as the site recovery efforts continue at Fukushima and any decommissioning decisions are farther into the future, the accidents have focused attention on the reactor designs in general and specifically on the Fukushima type BWRs. The regulatory authorities in many countries have initiated a re-examination of the design of the systems, structures and components and considerations of the capability of the station to cope with beyond-design basis events. Enhancements to SSCs and site features for the existing reactors and the reactors that will be built will also impact the decommissioning phase activities. The newer reactor designs of today not only have enhanced safety features but also take into consideration the features that will facilitate future decommissioning. Lessons learned from past management and operation of reactors as well as the lessons from decommissioning are incorporated into the new designs. However, in the post-Fukushima era, the emphasis on beyond-design-basis capability may lead to significant changes in SSCs, which eventually will also have impact on the decommissioning phase. Additionally, where some countries decide to phase out the nuclear power, many reactors may enter the decommissioning phase in the coming decade. While the formal updating and expanding of existing guidance documents for accident cleanup and decommissioning would benefit by waiting until the Fukushima project has progressed

  13. 30 CFR 250.1753 - After I decommission a pipeline, what information must I submit?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 30 Mineral Resources 2 2014-07-01 2014-07-01 false After I decommission a pipeline, what... SHELF Decommissioning Activities Pipeline Decommissioning § 250.1753 After I decommission a pipeline, what information must I submit? Within 30 days after you decommission a pipeline, you must submit...

  14. 30 CFR 250.1753 - After I decommission a pipeline, what information must I submit?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 30 Mineral Resources 2 2011-07-01 2011-07-01 false After I decommission a pipeline, what... OUTER CONTINENTAL SHELF Decommissioning Activities Pipeline Decommissioning § 250.1753 After I decommission a pipeline, what information must I submit? Within 30 days after you decommission a pipeline,...

  15. 30 CFR 250.1754 - When must I remove a pipeline decommissioned in place?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 30 Mineral Resources 2 2013-07-01 2013-07-01 false When must I remove a pipeline decommissioned in... Decommissioning Activities Pipeline Decommissioning § 250.1754 When must I remove a pipeline decommissioned in place? You must remove a pipeline decommissioned in place if the Regional Supervisor determines that...

  16. 30 CFR 250.1754 - When must I remove a pipeline decommissioned in place?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 30 Mineral Resources 2 2012-07-01 2012-07-01 false When must I remove a pipeline decommissioned in... Decommissioning Activities Pipeline Decommissioning § 250.1754 When must I remove a pipeline decommissioned in place? You must remove a pipeline decommissioned in place if the Regional Supervisor determines that...

  17. 30 CFR 250.1753 - After I decommission a pipeline, what information must I submit?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 30 Mineral Resources 2 2012-07-01 2012-07-01 false After I decommission a pipeline, what... SHELF Decommissioning Activities Pipeline Decommissioning § 250.1753 After I decommission a pipeline, what information must I submit? Within 30 days after you decommission a pipeline, you must submit...

  18. 30 CFR 250.1751 - How do I decommission a pipeline in place?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 30 Mineral Resources 2 2014-07-01 2014-07-01 false How do I decommission a pipeline in place? 250... Decommissioning Activities Pipeline Decommissioning § 250.1751 How do I decommission a pipeline in place? You must do the following to decommission a pipeline in place: (a) Submit a pipeline...

  19. 30 CFR 250.1754 - When must I remove a pipeline decommissioned in place?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 30 Mineral Resources 2 2014-07-01 2014-07-01 false When must I remove a pipeline decommissioned in... Decommissioning Activities Pipeline Decommissioning § 250.1754 When must I remove a pipeline decommissioned in place? You must remove a pipeline decommissioned in place if the Regional Supervisor determines that...

  20. 30 CFR 250.1754 - When must I remove a pipeline decommissioned in place?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 30 Mineral Resources 2 2011-07-01 2011-07-01 false When must I remove a pipeline decommissioned in... SHELF Decommissioning Activities Pipeline Decommissioning § 250.1754 When must I remove a pipeline decommissioned in place? You must remove a pipeline decommissioned in place if the Regional Supervisor...

  1. 30 CFR 250.1751 - How do I decommission a pipeline in place?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 30 Mineral Resources 2 2012-07-01 2012-07-01 false How do I decommission a pipeline in place? 250... Decommissioning Activities Pipeline Decommissioning § 250.1751 How do I decommission a pipeline in place? You must do the following to decommission a pipeline in place: (a) Submit a pipeline...

  2. 30 CFR 250.1751 - How do I decommission a pipeline in place?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 30 Mineral Resources 2 2011-07-01 2011-07-01 false How do I decommission a pipeline in place? 250... Decommissioning Activities Pipeline Decommissioning § 250.1751 How do I decommission a pipeline in place? You must do the following to decommission a pipeline in place: (a) Submit a pipeline...

  3. 30 CFR 250.1751 - How do I decommission a pipeline in place?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 30 Mineral Resources 2 2010-07-01 2010-07-01 false How do I decommission a pipeline in place? 250... Pipeline Decommissioning § 250.1751 How do I decommission a pipeline in place? You must do the following to decommission a pipeline in place: (a) Submit a pipeline decommissioning application in triplicate to...

  4. 30 CFR 250.1751 - How do I decommission a pipeline in place?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 30 Mineral Resources 2 2013-07-01 2013-07-01 false How do I decommission a pipeline in place? 250... Decommissioning Activities Pipeline Decommissioning § 250.1751 How do I decommission a pipeline in place? You must do the following to decommission a pipeline in place: (a) Submit a pipeline...

  5. 30 CFR 250.1753 - After I decommission a pipeline, what information must I submit?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 30 Mineral Resources 2 2010-07-01 2010-07-01 false After I decommission a pipeline, what... Decommissioning Activities Pipeline Decommissioning § 250.1753 After I decommission a pipeline, what information must I submit? Within 30 days after you decommission a pipeline, you must submit a written report...

  6. 30 CFR 250.1750 - When may I decommission a pipeline in place?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 30 Mineral Resources 2 2013-07-01 2013-07-01 false When may I decommission a pipeline in place... Decommissioning Activities Pipeline Decommissioning § 250.1750 When may I decommission a pipeline in place? You may decommission a pipeline in place when the Regional Supervisor determines that the pipeline...

  7. 30 CFR 250.1750 - When may I decommission a pipeline in place?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 30 Mineral Resources 2 2012-07-01 2012-07-01 false When may I decommission a pipeline in place... Decommissioning Activities Pipeline Decommissioning § 250.1750 When may I decommission a pipeline in place? You may decommission a pipeline in place when the Regional Supervisor determines that the pipeline...

  8. 30 CFR 250.1750 - When may I decommission a pipeline in place?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 30 Mineral Resources 2 2014-07-01 2014-07-01 false When may I decommission a pipeline in place... Decommissioning Activities Pipeline Decommissioning § 250.1750 When may I decommission a pipeline in place? You may decommission a pipeline in place when the Regional Supervisor determines that the pipeline...

  9. 30 CFR 250.1750 - When may I decommission a pipeline in place?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 30 Mineral Resources 2 2011-07-01 2011-07-01 false When may I decommission a pipeline in place... SHELF Decommissioning Activities Pipeline Decommissioning § 250.1750 When may I decommission a pipeline in place? You may decommission a pipeline in place when the Regional Supervisor determines that...

  10. 30 CFR 250.1753 - After I decommission a pipeline, what information must I submit?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 30 Mineral Resources 2 2013-07-01 2013-07-01 false After I decommission a pipeline, what... SHELF Decommissioning Activities Pipeline Decommissioning § 250.1753 After I decommission a pipeline, what information must I submit? Within 30 days after you decommission a pipeline, you must submit...

  11. Variable stiffness torsion springs

    NASA Technical Reports Server (NTRS)

    Alhorn, Dean C. (Inventor); Polites, Michael E. (Inventor)

    1994-01-01

    In a torsion spring the spring action is a result of the relationships between the torque applied in twisting the spring, the angle through which the torsion spring twists, and the modulus of elasticity of the spring material in shear. Torsion springs employed industrially have been strips, rods, or bars, generally termed shafts, capabable of being flexed by twisting their axes. They rely on the variations in shearing forces to furnish an internal restoring torque. In the torsion springs herein the restoring torque is external and therefore independent of the shearing modulus of elasticity of the torsion spring shaft. Also provided herein is a variable stiffness torsion spring. This torsion spring can be so adjusted as to have a given spring constant. Such variable stiffness torsion springs are extremely useful in gimballed payloads such as sensors, telescopes, and electronic devices on such platforms as a space shuttle or a space station.

  12. Variable stiffness torsion springs

    NASA Technical Reports Server (NTRS)

    Alhorn, Dean C. (Inventor); Polites, Michael E. (Inventor)

    1995-01-01

    In a torsion spring the spring action is a result of the relationships between the torque applied in twisting the spring, the angle through which the torsion spring twists, and the modulus of elasticity of the spring material in shear. Torsion springs employed industrially have been strips, rods, or bars, generally termed shafts, capabable of being flexed by twisting their axes. They rely on the variations in shearing forces to furnish an internal restoring torque. In the torsion springs herein the restoring torque is external and therefore independent of the shearing modulus of elasticity of the torsion spring shaft. Also provided herein is a variable stiffness torsion spring. This torsion spring can be so adjusted as to have a given spring constant. Such variable stiffness torsion springs are extremely useful in gimballed payloads such as sensors, telescopes, and electronic devices on such platforms as a space shuttle or a space station.

  13. In Situ Decommissioning (ISD) Concepts and Approaches for Excess Nuclear Facilities Decommissioning End State - 13367

    SciTech Connect

    Serrato, Michael G.; Musall, John C.; Bergren, Christopher L.

    2013-07-01

    The United States Department of Energy (DOE) currently has numerous radiologically contaminated excess nuclear facilities waiting decommissioning throughout the Complex. The traditional decommissioning end state is complete removal. This commonly involves demolishing the facility, often segregating various components and building materials and disposing of the highly contaminated, massive structures containing tons of highly contaminated equipment and piping in a (controlled and approved) landfill, at times hundreds of miles from the facility location. Traditional demolition is costly, and results in significant risks to workers, as well as risks and costs associated with transporting the materials to a disposal site. In situ decommissioning (ISD or entombment) is a viable alternative to demolition, offering comparable and potentially more protective protection of human health and the environment, but at a significantly reduced cost and worker risk. The Savannah River Site (SRS) has completed the initial ISD deployment for radiologically contaminated facilities. Two reactor (P and R Reactors) facilities were decommissioned in 2011 using the ISD approach through the American Recovery and Reinvestment Act. The SRS ISD approach resolved programmatic, regulatory and technical/engineering issues associated with avoiding the potential hazards and cost associated with generating and disposing of an estimated 124,300 metric tons (153,000 m{sup 3}) of contaminated debris per reactor. The DOE Environmental Management Office of Deactivation and Decommissioning and Facility Engineering, through the Savannah River National Laboratory, is currently investigating potential monitoring techniques and strategies to assess ISD effectiveness. As part of SRS's strategic planning, the site is seeking to leverage in situ decommissioning concepts, approaches and facilities to conduct research, design end states, and assist in regulatory interactions in broad national and international

  14. Gnome site decontamination and decommissioning project

    SciTech Connect

    Orcutt, J.A.; Sorom, E.R.

    1982-08-01

    In July 1977, DOE/Headquarters directed DOE/NV to design a decontamination and decommissioning plan for the Gnome site, 48 kilometers southeast of Carlsbad, New Mexico. The plan incorporated three distinct phases. During Phase I, both aerial and ground radiological surveys were conducted on the site. Radiological decontamination criteria were established, and a decontamination plan was developed based on the radiological survey results. During Phase II, site preparatory and rehabilitation work was completed. The actual land area decontamination was accomplished during Phase III with conventional earthmoving equipment. A gravity water injection system deposited 36,700 metric tons of contaminated soil and salt in the Gnome cavity. After completion of the decontamination and decommissioning operations, the Gnome site was returned to the Bureau of Land Management for unrestricted surface use.

  15. Decommissioning of the Tokamak Fusion Test Reactor

    SciTech Connect

    E. Perry; J. Chrzanowski; C. Gentile; R. Parsells; K. Rule; R. Strykowsky; M. Viola

    2003-10-28

    The Tokamak Fusion Test Reactor (TFTR) at the Princeton Plasma Physics Laboratory was operated from 1982 until 1997. The last several years included operations with mixtures of deuterium and tritium. In September 2002, the three year Decontamination and Decommissioning (D&D) Project for TFTR was successfully completed. The need to deal with tritium contamination as well as activated materials led to the adaptation of many techniques from the maintenance work during TFTR operations to the D&D effort. In addition, techniques from the decommissioning of fission reactors were adapted to the D&D of TFTR and several new technologies, most notably the development of a diamond wire cutting process for complex metal structures, were developed. These techniques, along with a project management system that closely linked the field crews to the engineering staff who developed the techniques and procedures via a Work Control Center, resulted in a project that was completed safely, on time, and well below budget.

  16. Optimized nuclear plant decommissioning economics through repowering

    SciTech Connect

    Demoss, D.; Charles, R.P.

    1996-11-01

    Nuclear power has provided a significant portion of electricity produced in the US over the last 39 years. Since the first commercial nuclear plant at Shippingport, Pennsylvania, started producing power in 1957, 110 nuclear plants have been placed in service. This accounts for approximately 20% of the US electric power production. In some states the number is much higher: Illinois relies on nuclear power for approximately 70% of its electricity needs. The generation of electricity from nuclear power will start to decrease in the year 2005 due to a number of plants being taken out of service as they reach the end of their design life (EDL). As these nuclear plants approach their design basis life of 40 years, plant owners will be faced with strategic decisions concerning continued operation through license renewal, decommissioning, or repowering. Without license renewal 20 units totaling more than 14 gigawatts will reach EDL by the year 2010. Three basic options are available to nuclear utilities: (1) continued operation through nuclear license renewal beyond EDL; (2) shutdown and decommissioning at EDL; (3) continued operation through nonnuclear repowering. This paper briefly reviews license renewal and decommissioning issues. Its primary focus is on the feasibility of Option 3 by reviewing the conceptual technical requirements for nonnuclear repowering and its associated economics.

  17. Decommissioning nuclear power plants - the wave of the future

    SciTech Connect

    Griggs, F.S. Jr.

    1994-12-31

    The paper discusses the project controls developed in the decommissioning of a nuclear power plant. Considerations are given to the contaminated piping and equipment that have to be removed and the spent and used fuel that has to be disposed of. The storage issue is of primary concern here. The cost control aspects and the dynamics of decommissioning are discussed. The effects of decommissioning laws on the construction and engineering firms are mentioned. 5 refs.

  18. 30 CFR 285.904 - Can I request a departure from the decommissioning requirements?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... decommissioning requirements? 285.904 Section 285.904 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, REGULATION, AND ENFORCEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY ALTERNATE USES OF EXISTING... the decommissioning requirements under § 285.103. Decommissioning Applications...

  19. HEAVY WATER COMPONENTS TEST REACTOR DECOMMISSIONING

    SciTech Connect

    Austin, W.; Brinkley, D.

    2011-10-13

    The Heavy Water Components Test Reactor (HWCTR) Decommissioning Project was initiated in 2009 as a Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) Removal Action with funding from the American Recovery and Reinvestment Act (ARRA). This paper summarizes the history prior to 2009, the major D&D activities, and final end state of the facility at completion of decommissioning in June 2011. The HWCTR facility was built in 1961, operated from 1962 to 1964, and is located in the northwest quadrant of the Savannah River Site (SRS) approximately three miles from the site boundary. The HWCTR was a pressurized heavy water test reactor used to develop candidate fuel designs for heavy water power reactors. In December of 1964, operations were terminated and the facility was placed in a standby condition as a result of the decision by the U.S. Atomic Energy Commission to redirect research and development work on heavy water power reactors to reactors cooled with organic materials. For about one year, site personnel maintained the facility in a standby status, and then retired the reactor in place. In the early 1990s, DOE began planning to decommission HWCTR. Yet, in the face of new budget constraints, DOE deferred dismantlement and placed HWCTR in an extended surveillance and maintenance mode. The doors of the reactor facility were welded shut to protect workers and discourage intruders. In 2009 the $1.6 billion allocation from the ARRA to SRS for site footprint reduction at SRS reopened the doors to HWCTR - this time for final decommissioning. Alternative studies concluded that the most environmentally safe, cost effective option for final decommissioning was to remove the reactor vessel, both steam generators, and all equipment above grade including the dome. The transfer coffin, originally above grade, was to be placed in the cavity vacated by the reactor vessel and the remaining below grade spaces would be grouted. Once all above equipment

  20. Revised analyses of decommissioning for the reference boiling water reactor power station. Effects of current regulatory and other considerations on the financial assurance requirements of the decommissioning rule and on estimates of occupational radiation exposure - appendices. Final report

    SciTech Connect

    Smith, R.I.; Bierschbach, M.C.; Konzek, G.J.; McDuffie, P.N.

    1996-07-01

    The NRC staff is in need of decommissioning bases documentation that will assist them in assessing the adequacy of the licensee submittals, from the viewpoint of both the planned actions, including occupational radiation exposure, and the probable costs. The purpose of this reevaluation study is to update the needed bases documentation. This report presents the results of a review and reevaluation of the PNL 1980 decommissioning study of the Washington Public Power Supply System`s Washington Nuclear Plant Two (WNP-2) located at Richland, Washington, including all identifiable factors and cost assumptions which contribute significantly to the total cost of decommissioning the plant for the DECON, SAFSTOR, and ENTOMB decommissioning alternatives. These alternatives now include an initial 5-7 year period during which time the spent fuel is stored in the spent fuel pool prior to beginning major disassembly or extended safe storage of the plant. Included for information (but not presently part of the license termination cost) is an estimate of the cost to demolish the decontaminated and clear structures on the site and to restore the site to a {open_quotes}green field{close_quotes} condition. This report also includes consideration of the NRC requirement that decontamination and decommissioning activities leading to termination of the nuclear license be completed within 60 years of final reactor shutdown, consideration of packaging and disposal requirements for materials whose radionuclide concentrations exceed the limits for Class C low-level waste (i.e., Greater-Than-Class C), and reflects 1993 costs for labor, materials, transport, and disposal activities. Sensitivity of the total license termination cost to the disposal costs at different low-level radioactive waste disposal sites, to different depths of contaminated concrete surface removal within the facilities, and to different transport distances is also examined.

  1. FAMS DECOMMISSIONING END-STATE ALTERNATIVE EVALUATION

    SciTech Connect

    Grimm, B; Stephen Chostner, S; Brenda Green, B

    2006-05-25

    Nuclear Material Management (NMM) completed a comprehensive study at the request of the Department of Energy Savannah River Operations Office (DOE-SR) in 2004 (Reference 11.1). The study evaluated the feasibility of removal and/or mitigation of the Pu-238 source term in the F-Area Material Storage (FAMS) facility during on-going material storage operations. The study recommended different options to remove and/or mitigate the Pu-238 source term depending on its location within the facility. During April 2005, the Department of Energy (DOE) sent a letter of direction (LOD) to Washington Savannah River Company (WSRC) directing WSRC to implement a new program direction that would enable an accelerated shutdown and decommissioning of FAMS (Reference 11.2). Further direction in the LOD stated that effective December 1, 2006 the facility will be transitioned to begin deactivation and decommissioning (D&D) activities. To implement the LOD, Site D&D (SDD) and DOE agreed the planning end-state would be demolition of the FAMS structure to the building slab. SDD developed the D&D strategy, preliminary cost and schedule, and issued the deactivation project plan in December 2005 (Reference 11.3). Due to concerns and questions regarding the FAMS planning end-state and in support of the project's Critical Decision 1, an alternative study was performed to evaluate the various decommissioning end-states and the methods by which those end-states are achieved. This report documents the results of the alternative evaluation which was performed in a structured decision-making process as outlined in the E7 Manual, Procedure 2.15, ''Alternative Studies'' (Reference 11.4).

  2. Decommissioning considerations at a time of nuclear renaissance

    SciTech Connect

    Devgun, Jas S.

    2007-07-01

    At a time of renaissance in the nuclear power industry, when it is estimated that anywhere between 60 to 130 new power reactors may be built worldwide over the next 15 years, why should we focus on decommissioning? Yet it is precisely the time to examine what decommissioning considerations should be taken into account as the industry proceeds with developing final designs for new reactors and the construction on the new build begins. One of the lessons learned from decommissioning of existing reactors has been that decommissioning was not given much thought when these reactors were designed three or four decades ago. Even though decommissioning may be sixty years down the road from the time they go on line, eventually all reactors will be decommissioned. It is only prudent that new designs be optimized for eventual decommissioning, along with the other major considerations. The overall objective in this regard is that when the time comes for decommissioning, it can be completed in shorter time frames, with minimum generation of radioactive waste, and with better radiological safety. This will ensure that the tail end costs of the power reactors are manageable and that the public confidence in the nuclear power is sustained through the renaissance and beyond. (author)

  3. 78 FR 64028 - Decommissioning of Nuclear Power Reactors

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-10-25

    ... Register on February 14, 2012 (77 FR 8902), for a 60-day public comment period. The public comment period... COMMISSION Decommissioning of Nuclear Power Reactors AGENCY: Nuclear Regulatory Commission. ACTION... regulatory guide (RG) 1.184 ``Decommissioning of Nuclear Power Reactors.'' This guide describes a method...

  4. Decommissioning: Nuclear Power's Missing Link. Worldwatch Paper 69.

    ERIC Educational Resources Information Center

    Pollock, Cynthia

    The processes and associated dilemmas of nuclear power plant decommissioning are reviewed in this publication. Decommissioning involves the clearing up and disposal of a retired nuclear plant and its equipment of such a way as to safeguard the public from the dangers of radioactivity. Related problem areas are identified and include: (1) closure…

  5. 10 CFR 72.130 - Criteria for decommissioning.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 10 Energy 2 2010-01-01 2010-01-01 false Criteria for decommissioning. 72.130 Section 72.130 Energy NUCLEAR REGULATORY COMMISSION (CONTINUED) LICENSING REQUIREMENTS FOR THE INDEPENDENT STORAGE OF SPENT... Criteria § 72.130 Criteria for decommissioning. The ISFSI or MRS must be designed for...

  6. Nuclear facility decommissioning and site remedial actions

    SciTech Connect

    Owen, P.T.; Knox, N.P.; Ferguson, S.D.; Fielden, J.M.; Schumann, P.L.

    1989-09-01

    The 576 abstracted references on nuclear facility decommissioning, uranium mill tailings management, and site remedial actions constitute the tenth in a series of reports prepared annually for the US Department of Energy's Remedial Action Programs. Citations to foreign and domestic literature of all types--technical reports, progress reports, journal articles, symposia proceedings, theses, books, patents, legislation, and research project descriptions--have been included. The bibliography contains scientific, technical, economic, regulatory, and legal information pertinent to the US Department of Energy's Remedial Action Programs. Major sections are (1) Surplus Facilities Management Program, (2) Nuclear Facilities Decommissioning, (3) Formerly Utilized Sites Remedial Action Program, (4) Facilities Contaminated with Naturally Occurring Radionuclides, (5) Uranium Mill Tailings Remedial Action Program, (6) Uranium Mill Tailings Management, (7) Technical Measurements Center, and (8) General Remedial Action Program Studies. Within these categories, references are arranged alphabetically by first author. Those references having no individual author are listed by corporate affiliation or by publication description. Indexes are provided for author, corporate affiliation, title work, publication description, geographic location, subject category, and keywords.

  7. Nuclear facility decommissioning and site remedial actions

    SciTech Connect

    Knox, N.P.; Webb, J.R.; Ferguson, S.D.; Goins, L.F.; Owen, P.T.

    1990-09-01

    The 394 abstracted references on environmental restoration, nuclear facility decommissioning, uranium mill tailings management, and site remedial actions constitute the eleventh in a series of reports prepared annually for the US Department of Energy's Remedial Action Programs. Citations to foreign and domestic literature of all types -- technical reports, progress reports, journal articles, symposia proceedings, theses, books, patents, legislation, and research project descriptions -- have been included. The bibliography contains scientific, technical, economic, regulatory, and legal information pertinent to the US Department of Energy's Remedial Action Programs. Major sections are (1) Surplus Facilities Management Program, (2) Nuclear Facilities Decommissioning, (3) Formerly Utilized Sites Remedial Action Programs, (4) Facilities Contaminated with Naturally Occurring Radionuclides, (5) Uranium Mill Tailings Remedial Action Program, (6) Grand Junction Remedial Action Program, (7) Uranium Mill Tailings Management, (8) Technical Measurements Center, (9) Remedial Action Program, and (10) Environmental Restoration Program. Within these categories, references are arranged alphabetically by first author. Those references having no individual author are listed by corporate affiliation or by publication title. Indexes are provided for author, corporate affiliation, title word, publication description, geographic location, subject category, and keywords. This report is a product of the Remedial Action Program Information Center (RAPIC), which selects and analyzes information on remedial actions and relevant radioactive waste management technologies.

  8. Revised analyses of decommissioning for the reference boiling water reactor power station. Effects of current regulatory and other considerations on the financial assurance requirements of the decommissioning rule and on estimates of occupational radiation exposure: Appendices, draft report for comment. Volume 2

    SciTech Connect

    Smith, R.I.; Bierschbach, M.C.; Konzek, G.J.

    1994-09-01

    On June 27, 1988, the U.S. Nuclear Regulatory Commission (NRC) published in the Federal Register (53 FR 24018) the final rule for the General Requirements for Decommissioning Nuclear Facilities. With the issuance of the final rule, owners and operators of licensed nuclear power plants are required to prepare, and submit to the NRC for review, decommissioning plans and cost estimates. The NRC staff is in need of updated bases documentation that will assist them in assessing the adequacy of the licensee submittals, from the viewpoint of both the planned actions, including occupational radiation exposure, and the probable costs. The purpose of this reevaluation study is to update the needed bases documentation. This report presents the results of a review and reevaluation of the PNL 1980 decommissioning study of the Washington Public Power Supply System`s WNP-2, including all identifiable factors and cost assumptions which contribute significantly to the total cost of decommissioning the plant for the DECON, SAFSTOR, and ENTOMB decommissioning alternatives, which now include an initial 5-7 year period during which time the spent fuel is stored in the spent fuel pool prior to beginning major disassembly or extended safe storage of the plant. This report also includes consideration of the NRC requirement that decontamination and decommissioning activities leading to termination of the nuclear license be completed within 60 years of final reactor shutdown, consideration of packaging and disposal requirements for materials whose radionuclide concentrations exceed the limits for Class C low-level waste. Costs for labor, materials, transport, and disposal activities are given in 1993 dollars. Sensitivities of the total license termination cost to the disposal costs at different low-level radioactive waste disposal sites, to different depths of contaminated concrete surface removal within the facilities, and to different transport distances are also examined.

  9. 30 CFR 250.1754 - When must I remove a pipeline decommissioned in place?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 30 Mineral Resources 2 2010-07-01 2010-07-01 false When must I remove a pipeline decommissioned in... Activities Pipeline Decommissioning § 250.1754 When must I remove a pipeline decommissioned in place? You must remove a pipeline decommissioned in place if the Regional Supervisor determines that the...

  10. 30 CFR 250.1750 - When may I decommission a pipeline in place?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 30 Mineral Resources 2 2010-07-01 2010-07-01 false When may I decommission a pipeline in place... Pipeline Decommissioning § 250.1750 When may I decommission a pipeline in place? You may decommission a pipeline in place when the Regional Supervisor determines that the pipeline does not constitute a...

  11. 26 CFR 1.468A-4 - Treatment of nuclear decommissioning fund.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 26 Internal Revenue 6 2011-04-01 2011-04-01 false Treatment of nuclear decommissioning fund. 1...-4 Treatment of nuclear decommissioning fund. (a) In general. A nuclear decommissioning fund is... by the assets of the nuclear decommissioning fund. (b) Modified gross income. For purposes of...

  12. 26 CFR 1.468A-4T - Treatment of nuclear decommissioning fund (temporary).

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 26 Internal Revenue 6 2010-04-01 2010-04-01 false Treatment of nuclear decommissioning fund...-4T Treatment of nuclear decommissioning fund (temporary). (a) In general. A nuclear decommissioning... income earned by the assets of the nuclear decommissioning fund. (b) Modified gross income. For...

  13. 26 CFR 1.468A-4 - Treatment of nuclear decommissioning fund.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 26 Internal Revenue 6 2012-04-01 2012-04-01 false Treatment of nuclear decommissioning fund. 1...-4 Treatment of nuclear decommissioning fund. (a) In general. A nuclear decommissioning fund is... by the assets of the nuclear decommissioning fund. (b) Modified gross income. For purposes of...

  14. 26 CFR 1.468A-4 - Treatment of nuclear decommissioning fund.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 26 Internal Revenue 6 2013-04-01 2013-04-01 false Treatment of nuclear decommissioning fund. 1...-4 Treatment of nuclear decommissioning fund. (a) In general. A nuclear decommissioning fund is... by the assets of the nuclear decommissioning fund. (b) Modified gross income. For purposes of...

  15. 26 CFR 1.468A-4 - Treatment of nuclear decommissioning fund.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 26 Internal Revenue 6 2014-04-01 2014-04-01 false Treatment of nuclear decommissioning fund. 1...-4 Treatment of nuclear decommissioning fund. (a) In general. A nuclear decommissioning fund is... by the assets of the nuclear decommissioning fund. (b) Modified gross income. For purposes of...

  16. Water Treatment Technology - Springs.

    ERIC Educational Resources Information Center

    Ross-Harrington, Melinda; Kincaid, G. David

    One of twelve water treatment technology units, this student manual on springs provides instructional materials for two competencies. (The twelve units are designed for a continuing education training course for public water supply operators.) The competencies focus on spring basin construction and spring protection. For each competency, student…

  17. Legislative update.

    PubMed

    1999-04-01

    Updates are presented from nine States on HIV-related legislation. Legislative topics include HIV case surveillance, testing, corrections, safety of health-care workers, HIV status notification, the definition of disability, viatical settlements, and confidentiality breaches. PMID:11366638

  18. 1. LOOKING NORTH, SHOWING IODINE SPRING (FOREGROUND), SALT SULPHUR SPRING ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    1. LOOKING NORTH, SHOWING IODINE SPRING (FOREGROUND), SALT SULPHUR SPRING (LEFT BACKGROUND), AND TWIN COTTAGES (UPPER RIGHT) (4 x 5 negative; 5 x 7 print) - Salt Sulpher Springs, U.S. Route 219, Salt Sulphur Springs, Monroe County, WV

  19. Optimal policies for aggregate recycling from decommissioned forest roads.

    PubMed

    Thompson, Matthew; Sessions, John

    2008-08-01

    To mitigate the adverse environmental impact of forest roads, especially degradation of endangered salmonid habitat, many public and private land managers in the western United States are actively decommissioning roads where practical and affordable. Road decommissioning is associated with reduced long-term environmental impact. When decommissioning a road, it may be possible to recover some aggregate (crushed rock) from the road surface. Aggregate is used on many low volume forest roads to reduce wheel stresses transferred to the subgrade, reduce erosion, reduce maintenance costs, and improve driver comfort. Previous studies have demonstrated the potential for aggregate to be recovered and used elsewhere on the road network, at a reduced cost compared to purchasing aggregate from a quarry. This article investigates the potential for aggregate recycling to provide an economic incentive to decommission additional roads by reducing transport distance and aggregate procurement costs for other actively used roads. Decommissioning additional roads may, in turn, result in improved aquatic habitat. We present real-world examples of aggregate recycling and discuss the advantages of doing so. Further, we present mixed integer formulations to determine optimal levels of aggregate recycling under economic and environmental objectives. Tested on an example road network, incorporation of aggregate recycling demonstrates substantial cost-savings relative to a baseline scenario without recycling, increasing the likelihood of road decommissioning and reduced habitat degradation. We find that aggregate recycling can result in up to 24% in cost savings (economic objective) and up to 890% in additional length of roads decommissioned (environmental objective).

  20. Optimal Policies for Aggregate Recycling from Decommissioned Forest Roads

    NASA Astrophysics Data System (ADS)

    Thompson, Matthew; Sessions, John

    2008-08-01

    To mitigate the adverse environmental impact of forest roads, especially degradation of endangered salmonid habitat, many public and private land managers in the western United States are actively decommissioning roads where practical and affordable. Road decommissioning is associated with reduced long-term environmental impact. When decommissioning a road, it may be possible to recover some aggregate (crushed rock) from the road surface. Aggregate is used on many low volume forest roads to reduce wheel stresses transferred to the subgrade, reduce erosion, reduce maintenance costs, and improve driver comfort. Previous studies have demonstrated the potential for aggregate to be recovered and used elsewhere on the road network, at a reduced cost compared to purchasing aggregate from a quarry. This article investigates the potential for aggregate recycling to provide an economic incentive to decommission additional roads by reducing transport distance and aggregate procurement costs for other actively used roads. Decommissioning additional roads may, in turn, result in improved aquatic habitat. We present real-world examples of aggregate recycling and discuss the advantages of doing so. Further, we present mixed integer formulations to determine optimal levels of aggregate recycling under economic and environmental objectives. Tested on an example road network, incorporation of aggregate recycling demonstrates substantial cost-savings relative to a baseline scenario without recycling, increasing the likelihood of road decommissioning and reduced habitat degradation. We find that aggregate recycling can result in up to 24% in cost savings (economic objective) and up to 890% in additional length of roads decommissioned (environmental objective).

  1. Optimal policies for aggregate recycling from decommissioned forest roads.

    PubMed

    Thompson, Matthew; Sessions, John

    2008-08-01

    To mitigate the adverse environmental impact of forest roads, especially degradation of endangered salmonid habitat, many public and private land managers in the western United States are actively decommissioning roads where practical and affordable. Road decommissioning is associated with reduced long-term environmental impact. When decommissioning a road, it may be possible to recover some aggregate (crushed rock) from the road surface. Aggregate is used on many low volume forest roads to reduce wheel stresses transferred to the subgrade, reduce erosion, reduce maintenance costs, and improve driver comfort. Previous studies have demonstrated the potential for aggregate to be recovered and used elsewhere on the road network, at a reduced cost compared to purchasing aggregate from a quarry. This article investigates the potential for aggregate recycling to provide an economic incentive to decommission additional roads by reducing transport distance and aggregate procurement costs for other actively used roads. Decommissioning additional roads may, in turn, result in improved aquatic habitat. We present real-world examples of aggregate recycling and discuss the advantages of doing so. Further, we present mixed integer formulations to determine optimal levels of aggregate recycling under economic and environmental objectives. Tested on an example road network, incorporation of aggregate recycling demonstrates substantial cost-savings relative to a baseline scenario without recycling, increasing the likelihood of road decommissioning and reduced habitat degradation. We find that aggregate recycling can result in up to 24% in cost savings (economic objective) and up to 890% in additional length of roads decommissioned (environmental objective). PMID:18481140

  2. DECOMMISSIONING OF A CAESIUM-137 SEALED SOURCE PRODUCTION FACILITY

    SciTech Connect

    Murray, A.; Abbott, H.

    2003-02-27

    Amersham owns a former Caesium-137 sealed source production facility. They commissioned RWE NUKEM to carry out an Option Study to determine a strategy for the management of this facility and then the subsequent decommissioning of it. The decommissioning was carried out in two sequential phases. Firstly robotic decommissioning followed by a phase of manual decommissioning. This paper describes the remote equipment designed built and operated, the robotic and manual decommissioning operations performed, the Safety Management arrangements and summarizes the lessons learned. Using the equipment described the facility was dismantled and decontaminated robotically. Some 2300kg of Intermediate Level Waste containing in the order of 4000Ci were removed robotically from the facility. Ambient dose rates were reduced from 100's of R per hour {gamma} to 100's of mR per hour {gamma}. The Telerobotic System was then removed to allow man access to complete the decommissioning. Manual decommissioning reduced ambient dose rates further to less than 1mR per hour {gamma} and loose contamination levels to less than 0.25Bq/cm2. This allowed access to the facility without respiratory protection.

  3. Safety Oversight of Decommissioning Activities at DOE Nuclear Sites

    SciTech Connect

    Zull, Lawrence M.; Yeniscavich, William

    2008-01-15

    The Defense Nuclear Facilities Safety Board (Board) is an independent federal agency established by Congress in 1988 to provide nuclear safety oversight of activities at U.S. Department of Energy (DOE) defense nuclear facilities. The activities under the Board's jurisdiction include the design, construction, startup, operation, and decommissioning of defense nuclear facilities at DOE sites. This paper reviews the Board's safety oversight of decommissioning activities at DOE sites, identifies the safety problems observed, and discusses Board initiatives to improve the safety of decommissioning activities at DOE sites. The decommissioning of former defense nuclear facilities has reduced the risk of radioactive material contamination and exposure to the public and site workers. In general, efforts to perform decommissioning work at DOE defense nuclear sites have been successful, and contractors performing decommissioning work have a good safety record. Decommissioning activities have recently been completed at sites identified for closure, including the Rocky Flats Environmental Technology Site, the Fernald Closure Project, and the Miamisburg Closure Project (the Mound site). The Rocky Flats and Fernald sites, which produced plutonium parts and uranium materials for defense needs (respectively), have been turned into wildlife refuges. The Mound site, which performed R and D activities on nuclear materials, has been converted into an industrial and technology park called the Mound Advanced Technology Center. The DOE Office of Legacy Management is responsible for the long term stewardship of these former EM sites. The Board has reviewed many decommissioning activities, and noted that there are valuable lessons learned that can benefit both DOE and the contractor. As part of its ongoing safety oversight responsibilities, the Board and its staff will continue to review the safety of DOE and contractor decommissioning activities at DOE defense nuclear sites.

  4. Springs of Florida

    USGS Publications Warehouse

    Rosenau, Jack C.; Faulkner, Glen L.; Hendry, Charles W.; Hull, Robert W.

    1977-01-01

    The first comprehensive report of Florida's springs, which contains both a story of the springs and a collection of facts about them, was published thirty years ago (Ferguson and others, 1947). Since then, much additional data on springs have been gathered and the current report, Springs of Florida, makes a wealth of information on springs available to the public. Springs of Florida, prepared by the U.S. Geological Survey in cooperation with the Bureau of Geology, Florida Department of Natural Resources, publishers, and the Bureau of Water Resources Management, Florida Department of Environmental Regulation, is intended to provide sufficient background information for a lucid understanding of the nature and occurrence of the springs in the State.

  5. Constructing Predictive Estimates for Worker Exposure to Radioactivity During Decommissioning: Analysis of Completed Decommissioning Projects - Master Thesis

    SciTech Connect

    Dettmers, Dana Lee; Eide, Steven Arvid

    2002-10-01

    An analysis of completed decommissioning projects is used to construct predictive estimates for worker exposure to radioactivity during decommissioning activities. The preferred organizational method for the completed decommissioning project data is to divide the data by type of facility, whether decommissioning was performed on part of the facility or the complete facility, and the level of radiation within the facility prior to decommissioning (low, medium, or high). Additional data analysis shows that there is not a downward trend in worker exposure data over time. Also, the use of a standard estimate for worker exposure to radioactivity may be a best estimate for low complete storage, high partial storage, and medium reactor facilities; a conservative estimate for some low level of facility radiation facilities (reactor complete, research complete, pits/ponds, other), medium partial process facilities, and high complete research facilities; and an underestimate for the remaining facilities. Limited data are available to compare different decommissioning alternatives, so the available data are reported and no conclusions can been drawn. It is recommended that all DOE sites and the NRC use a similar method to document worker hours, worker exposure to radiation (person-rem), and standard industrial accidents, injuries, and deaths for all completed decommissioning activities.

  6. Decontamination, decommissioning, and vendor advertorial issue, 2008

    SciTech Connect

    Agnihotri, Newal

    2008-07-15

    The focus of the July-August issue is on Decontamination, decommissioning, and vendor advertorials. Articles and reports in this issue include: D and D technical paper summaries; The role of nuclear power in turbulent times, by Tom Chrisopher, AREVA, NP, Inc.; Enthusiastic about new technologies, by Jack Fuller, GE Hitachi Nuclear Energy; It's important to be good citizens, by Steve Rus, Black and Veatch Corporation; Creating Jobs in the U.S., by Guy E. Chardon, ALSTOM Power; and, and, An enviroment and a community champion, by Tyler Lamberts, Entergy Nuclear Operations, Inc. The Industry Innovations article is titled Best of the best TIP achievement 2008, by Edward Conaway, STP Nuclear Operating Company.

  7. Spring joint with overstrain sensor

    NASA Technical Reports Server (NTRS)

    Phelps, Peter M. (Inventor); Gaither, Bryan W. (Inventor)

    2011-01-01

    A flexible joint may include a conductive compression spring and a pair of non-conductive spring cages disposed at opposite ends of the compression spring to support the compression spring. A conductive member disposed inside the compression spring may extend between the pair of spring cages. One end of the conductive member may be fixed for movement with one of the spring cages and another end of the conductive member may be fixed for movement with the other of the spring cages.

  8. Progress report on decommissioning activities at the Fernald Environmental Management Project (FEMP) site

    SciTech Connect

    1998-07-01

    The Fernald Environmental Management Project (FEMP), is located about 18 miles northwest of Cincinnati, Ohio. Between 1953 and 1989, the facility, then called the Feed Material Production Center or FMPC, produced uranium metal products used in the eventual production of weapons grade material for use by other US Department of Energy (DOE) sites. In 1989, FMPC`s production was suspended by the federal government in order to focus resources on environmental restoration versus defense production. In 1992, Fluor Daniel Fernald assumed responsibility for managing all cleanup activities at the FEMP under contract to the DOE. In 1990, as part of the remediation effort, the site was divided into five operable units based on physical proximity of contaminated areas, similar amounts of types of contamination, or the potential for a similar technology to be used in cleanup activities. This report continues the outline of the decontamination and decommissioning (D and D) activities at the FEMP site Operable Unit 3 (OU3) and provides an update on the status of the decommissioning activities. OU3, the Facilities Closure and Demolition Project, involves the remediation of more than 200 uranium processing facilities. The mission of the project is to remove nuclear materials stored in these buildings, then perform the clean out of the buildings and equipment, and decontaminate and dismantle the facilities.

  9. Information on Hydrologic Conceptual Models, Parameters, Uncertainty Analysis, and Data Sources for Dose Assessments at Decommissioning Sites

    SciTech Connect

    Meyer, Philip D.; Gee, Glendon W.; Nicholson, Thomas J.

    2000-02-28

    This report addresses issues related to the analysis of uncertainty in dose assessments conducted as part of decommissioning analyses. The analysis is limited to the hydrologic aspects of the exposure pathway involving infiltration of water at the ground surface, leaching of contaminants, and transport of contaminants through the groundwater to a point of exposure. The basic conceptual models and mathematical implementations of three dose assessment codes are outlined along with the site-specific conditions under which the codes may provide inaccurate, potentially nonconservative results. In addition, the hydrologic parameters of the codes are identified and compared. A methodology for parameter uncertainty assessment is outlined that considers the potential data limitations and modeling needs of decommissioning analyses. This methodology uses generic parameter distributions based on national or regional databases, sensitivity analysis, probabilistic modeling, and Bayesian updating to incorporate site-specific information. Data sources for best-estimate parameter values and parameter uncertainty information are also reviewed. A follow-on report will illustrate the uncertainty assessment methodology using decommissioning test cases.

  10. Lessons Learned from the NASA Plum Brook Reactor Facility Decommissioning

    NASA Technical Reports Server (NTRS)

    2010-01-01

    NASA has been conducting decommissioning activities at its PBRF for the last decade. As a result of all this work there have been several lessons learned both good and bad. This paper presents some of the more exportable lessons.

  11. Decommissioning the UHTREX Reactor Facility at Los Alamos, New Mexico

    SciTech Connect

    Salazar, M.; Elder, J.

    1992-08-01

    The Ultra-High Temperature Reactor Experiment (UHTREX) facility was constructed in the late 1960s to advance high-temperature and gas-cooled reactor technology. The 3-MW reactor was graphite moderated and helium cooled and used 93% enriched uranium as its fuel. The reactor was run for approximately one year and was shut down in February 1970. The decommissioning of the facility involved removing the reactor and its associated components. This document details planning for the decommissioning operations which included characterizing the facility, estimating the costs of decommissioning, preparing environmental documentation, establishing a system to track costs and work progress, and preplanning to correct health and safety concerns in the facility. Work to decommission the facility began in 1988 and was completed in September 1990 at a cost of $2.9 million. The facility was released to Department of Energy for other uses in its Los Alamos program.

  12. Progress in Decommissioning the Humboldt Bay Power Plant - 13604

    SciTech Connect

    Rod, Kerry; Shelanskey, Steven K.; Kristofzski, John

    2013-07-01

    Decommissioning of the Pacific Gas and Electric (PG and E) Company Humboldt Bay Power Plant (HBPP) Unit 3 nuclear facility has now, after more than three decades of SAFSTOR and initial decommissioning work, transitioned to full-scale decommissioning. Decommissioning activities to date have been well orchestrated and executed in spite of an extremely small work site with space constricted even more by other concurrent on-site major construction projects including the demolition of four fossil units, construction of a new generating station and 60 KV switchyard upgrade. Full-scale decommissioning activities - now transitioning from Plant Systems Removal (PG and E self-perform) to Civil Works Projects (contractor performed) - are proceeding in a safe, timely, and cost effective manner. As a result of the successful decommissioning work to date (approximately fifty percent completed) and the intense planning and preparations for the remaining work, there is a high level of confidence for completion of all HBPP Unit 3 decommissions activities in 2018. Strategic planning and preparations to transition into full-scale decommissioning was carried out in 2008 by a small, highly focused project team. This planning was conducted concurrent with other critical planning requirements such as the loading of spent nuclear fuel into dry storage at the Independent Spent Fuel Storage Installation (ISFSI) finishing December 2008. Over the past four years, 2009 through 2012, the majority of decommissioning work has been installation of site infrastructure and removal of systems and components, known as the Plant System Removal Phase, where work scope was dynamic with significant uncertainty, and it was self-performed by PG and E. As HBPP Decommissioning transitions from the Plant System Removal Phase to the Civil Works Projects Phase, where work scope is well defined, a contracting plan similar to that used for Fossil Decommissioning will be implemented. Award of five major work scopes

  13. The Decommissioning of the Trino Nuclear Power Plant

    SciTech Connect

    Brusa, L.; DeSantis, R.; Nurden, P. L.; Walkden, P.; Watson, B.

    2002-02-27

    Following a referendum in Italy in 1987, the four Nuclear Power Plants (NPPs) owned and operated by the state utility ENEL were closed. After closing the NPPs, ENEL selected a ''safestore'' decommissioning strategy; anticipating a safestore period of some 40-50 years. This approach was consistent with the funds collected during plant operation, and was reinforced by the lack of both a waste repository and a set of national free release limits for contaminated materials in Italy. During 1999, twin decisions were made to privatize ENEL and to transform the nuclear division into a separate subsidiary of the ENEL group. This group was renamed Sogin and during the following year, ownership of the company was transferred to the Italian Treasury. On formation, Sogin was asked by the Italian government to review the national decommissioning strategy. The objective of the review was to move from a safestore strategy to a prompt decommissioning strategy, with the target of releasing all of the nuclear sites by 2020. It was recognized that this target was conditional upon the availability of a national LLW repository together with interim stores for both spent fuel and HLW by 2009. The government also agreed that additional costs caused by the acceleration of the decommissioning program would be considered as stranded costs. These costs will be recovered by a levy on the kWh price of electricity, a process established and controlled by the Regulator of the Italian energy sector. Building on the successful collaboration to develop a prompt decommissioning strategy for the Latina Magnox reactor (1), BNFL and Sogin agreed to collaborate on an in depth study for the prompt decommissioning of the Sogin PWR at Trino. BNFL is currently decommissioning six NPPs and is at an advanced stage of planning for two further units, having completed a full and rigorous exercise to develop Baseline Decommissioning Plans (BDP's) for these stations. The BDP exercise utilizes the full range of

  14. Preliminary decommissioning study reports. Volume 5, Molten Salt Reactor Experiment

    SciTech Connect

    Peretz, F.J.

    1984-09-01

    The Molten Salt Reactor Experiment (MSRE) is one of approximately 76 facilities currently managed by the ORNL Surplus Facilities Management Program (SFMP). This program, as part of the DOE national SFMP, is responsible for the maintenance and surveillance and the final decommissioning of radioactively-contaminated surplus ORNL facilities. A long range planning effort is being conducted that will outline the scope and objectives of the ORNL program and establish decommissioning priorities based on health and safety concerns, budget constraints, and other programmatic constraints. In support of this SFMP planning activity, preliminary engineering assessments are being conducted for each of the ORNL surplus facilities currently managed under the program. These efforts, in general, are designed to: (1) provide an initial assessment of the potential decommissioning alternatives; (2) choose a preferred alternative and provide a justification for that choice, and (3) provide a preliminary description of the decommissioning plan, including cost and schedule estimates. Because of several issues which cannot be evaluated quantitatively at this time, this report on the MSRE does not select a ``most probable decommissioning mode`` but rather discusses the issues and representative alternatives for disposal of the MSRE fuel salts and decommissioning of the facility. A budget and schedule representative of the types of activities likely to be required is also suggested for preliminary use in the SFMP Long Range Plan.

  15. Decontamination and Decommissioning Experience at a Sellafield Uranium Purification Plant

    SciTech Connect

    Prosser, J.L.

    2006-07-01

    Built in the 1950's, this plant was originally designed to purify depleted uranyl nitrate solution arising from reprocessing operations at the Primary Separation and Head End Plant (Fig. 1). The facility was used for various purposes throughout its life cycle such as research, development and trial based processes. Test rigs were operated in the building from the 1970's until 1984 to support development of the process and equipment now used at Sellafield's Thermal Oxide Reprocessing Plant (THORP). The extensive decommissioning program for this facility began over 15 years ago. Many challenges have been overcome throughout this program such as decommissioning the four main process cells, which were very highly alpha contaminated. The cells contained vessels and pipeline systems that were contaminated to such levels that workers had to use pressurized suits to enter the cells. Since decommissioning at Sellafield was in its infancy, this project has trialed various decontamination/decommissioning methods and techniques in order to progress the project, and this has provided valuable learning for other decommissioning projects. The project has included characterization, decontamination, dismantling, waste handling, and is now ready for demolition during late 2005, early 2006. This will be the first major facility within the historic Separation Area at Sellafield to be demolished down to base slab level. The lessons learnt from this project will directly benefit numerous decommissioning projects as the cleanup at Sellafield continues. (authors)

  16. Accelerating the Whiteshell Laboratories Decommissioning Through the Implementation of a Projectized and Delivery-Focused Organization - 13074

    SciTech Connect

    Wilcox, Brian; Mellor, Russ; Michaluk, Craig

    2013-07-01

    and positive impacts on schedule and delivery. A revised organizational structure was implemented in two phases, starting 2011 April 1, to align WL staff with the common goal of decommissioning the site through the direction of the WL Decommissioning Project General Manager. On 2011 September 1, the second phase of the reorganization was implemented and WL Decommissioning staff was organized under five Divisions: Programs and Regulatory Compliance, General Site Services, Decommissioning Strategic Planning, Nuclear Facilities and Project Delivery. A new Mission, Vision and Objectives were developed for the project, and several productivity enhancements are being implemented. These include the use of an integrated and fully re-sourced Site Wide Schedule that is updated and reviewed at Plan-of-the-Week meetings, improved work distribution throughout the year, eliminating scheduling 'push' mentality, project scoreboards, work planning implementation, lean practices and various process improvement initiatives. A revised Strategic Plan is under development that reflects the improved project delivery capabilities. As a result of these initiatives, and a culture change towards a projectized approach, the decommissioning schedule will be advanced by approximately 10 years. (authors)

  17. The unit cost factors and calculation methods for decommissioning - Cost estimation of nuclear research facilities

    SciTech Connect

    Kwan-Seong Jeong; Dong-Gyu Lee; Chong-Hun Jung; Kune-Woo Lee

    2007-07-01

    Available in abstract form only. Full text of publication follows: The uncertainties of decommissioning costs increase high due to several conditions. Decommissioning cost estimation depends on the complexity of nuclear installations, its site-specific physical and radiological inventories. Therefore, the decommissioning costs of nuclear research facilities must be estimated in accordance with the detailed sub-tasks and resources by the tasks of decommissioning activities. By selecting the classified activities and resources, costs are calculated by the items and then the total costs of all decommissioning activities are reshuffled to match with its usage and objectives. And the decommissioning cost of nuclear research facilities is calculated by applying a unit cost factor method on which classification of decommissioning works fitted with the features and specifications of decommissioning objects and establishment of composition factors are based. Decommissioning costs of nuclear research facilities are composed of labor cost, equipment and materials cost. Of these three categorical costs, the calculation of labor costs are very important because decommissioning activities mainly depend on labor force. Labor costs in decommissioning activities are calculated on the basis of working time consumed in decommissioning objects and works. The working times are figured out of unit cost factors and work difficulty factors. Finally, labor costs are figured out by using these factors as parameters of calculation. The accuracy of decommissioning cost estimation results is much higher compared to the real decommissioning works. (authors)

  18. Coil spring venting arrangement

    DOEpatents

    McCugh, R.M.

    1975-10-21

    A simple venting device for trapped gas pockets in hydraulic systems is inserted through a small access passages, operated remotely, and removed completely. The device comprises a small diameter, closely wound coil spring which is pushed through a guide temporarily inserted in the access passage. The guide has a central passageway which directs the coil spring radially upward into the pocket, so that, with the guide properly positioned for depth and properly oriented, the coil spring can be pushed up into the top of the pocket to vent it. By positioning a seal around the free end of the guide, the spring and guide are removed and the passage is sealed.

  19. Update '98.

    ERIC Educational Resources Information Center

    Mock, Karen R.

    1998-01-01

    Updates cases and issues previously discussed in this regular column on human rights in Canada, including racism and anti-Semitism, laws on hate crimes, hate sites on the World Wide Web, the use of the "free speech" defense by hate groups, and legal challenges to antiracist groups by individuals criticized by them. (DSK)

  20. Revised Analyses of Decommissioning Reference Non-Fuel-Cycle Facilities

    SciTech Connect

    MC Bierschbach; DR Haffner; KJ Schneider; SM Short

    2002-12-01

    Cost information is developed for the conceptual decommissioning of non-fuel-cycle nuclear facilities that represent a significant decommissioning task in terms of decontamination and disposal activities. This study is a re-evaluation of the original study (NUREG/CR-1754 and NUREG/CR-1754, Addendum 1). The reference facilities examined in this study are the same as in the original study and include: a laboratory for the manufacture of {sup 3}H-labeled compounds; a laboratory for the manufacture of {sup 14}C-labeled compounds; a laboratory for the manufacture of {sup 123}I-labeled compounds; a laboratory for the manufacture of {sup 137}Cs sealed sources; a laboratory for the manufacture of {sup 241}Am sealed sources; and an institutional user laboratory. In addition to the laboratories, three reference sites that require some decommissioning effort were also examined. These sites are: (1) a site with a contaminated drain line and hold-up tank; (2) a site with a contaminated ground surface; and (3) a tailings pile containing uranium and thorium residues. Decommissioning of these reference facilities and sites can be accomplished using techniques and equipment that are in common industrial use. Essentially the same technology assumed in the original study is used in this study. For the reference laboratory-type facilities, the study approach is to first evaluate the decommissioning of individual components (e.g., fume hoods, glove boxes, and building surfaces) that are common to many laboratory facilities. The information obtained from analyzing the individual components of each facility are then used to determine the cost, manpower requirements and dose information for the decommissioning of the entire facility. DECON, the objective of the 1988 Rulemaking for materials facilities, is the decommissioning alternative evaluated for the reference laboratories because it results in the release of the facility for restricted or unrestricted use as soon as possible. For a

  1. An overview of U.S. decommissioning experience -- A basic introduction

    SciTech Connect

    Boing, L.E.

    1998-03-09

    This paper presents an overview of the US experiences in the decommissioning technical area. Sections included are: (1) an overview of the magnitude of the problem, (2) a review of the US decommissioning process, (3) regulation of decommissioning, (4) regulatory and funding requirements for decommissioning, and (5) a general overview of all on-going and completed decommissioning projects to date in the US. The final section presents a review of some issues in the decommissioning area currently being debated in the technical specialists community.

  2. Mineral springs and miracles.

    PubMed

    Forster, M M

    1994-04-01

    Development of hot springs in the Canadian Rockies was closely linked to their reputed medicinal value. In 1885, the federal government created a small reserve around the springs at Sulphur Mountain, an area later enlarged to become Banff National Park, in recognition of the "great sanitary and curative advantage to the public."

  3. A Magnet Spring Model

    ERIC Educational Resources Information Center

    Fay, T. H.; Mead, L.

    2006-01-01

    The paper discusses an elementary spring model representing the motion of a magnet suspended from the ceiling at one end of a vertical spring which is held directly above a second magnet fixed on the floor. There are two cases depending upon the north-south pole orientation of the two magnets. The attraction or repelling force induced by the…

  4. Mobile workstation for decontamination and decommissioning operations

    SciTech Connect

    Whittaker, W.L.; Osborn, J.F.; Thompson, B.R.

    1993-10-01

    This project is an interdisciplinary effort to develop effective mobile worksystems for decontamination and decommissioning (D&D) of facilities within the DOE Nuclear Weapons Complex. These mobile worksystems will be configured to operate within the environmental and logistical constraints of such facilities and to perform a number of work tasks. Our program is designed to produce a mobile worksystem with capabilities and features that are matched to the particular needs of D&D work by evolving the design through a series of technological developments, performance tests and evaluations. The project has three phases. In this the first phase, an existing teleoperated worksystem, the Remote Work Vehicle (developed for use in the Three Mile Island Unit 2 Reactor Building basement), was enhanced for telerobotic performance of several D&D operations. Its ability to perform these operations was then assessed through a series of tests in a mockup facility that contained generic structures and equipment similar to those that D&D work machines will encounter in DOE facilities. Building upon the knowledge gained through those tests and evaluations, a next generation mobile worksystem, the RWV II, and a more advanced controller will be designed, integrated and tested in the second phase, which is scheduled for completion in January 1995. The third phase of the project will involve testing of the RWV II in the real DOE facility.

  5. Valve-spring Surge

    NASA Technical Reports Server (NTRS)

    Marti, Willy

    1937-01-01

    Test equipment is described that includes a system of three quartz indicators whereby three different pressures could be synchronized and simultaneously recorded on a single oscillogram. This equipment was used to test the reliction of waves at ends of valve spring, the dynamical stress of the valve spring for a single lift of the valve, and measurement of the curve of the cam tested. Other tests included simultaneous recording of the stress at both ends of the spring, spring oscillation during a single lift as a function of speed, computation of amplitude of oscillation for a single lift by harmonic analysis, effect of cam profile, the setting up of resonance, and forced spring oscillation with damping.

  6. Rotary spring energy storage

    SciTech Connect

    Cooley, S.

    1981-07-01

    The goal was to design a lightweight system, for bicycles, that can level the input energy requirement (human exertion) in accordance with variations in road load (friction, wind, and grade) and/or to provide a system for regenerative braking, that is, to store energy normally lost in brake pad friction for brief periods until it required for re-acceleration or hill-climbing. The rotary spring, also called the coil, motor, spiral, or power spring is governed by the equations reviewed. Materials used in spring manufacture are briefly discussed, and justification for steel as the design choice of material is given. Torque and power requirements for a bicycle and rider are provided as well as estimated human power output levels. These criteria are examined to define spring size and possible orientations on a bicycle. Patents and designs for coupling the spring to the drive train are discussed.

  7. An equivalent spring for nonlinear springs in series

    NASA Astrophysics Data System (ADS)

    Radomirovic, Dragi; Kovacic, Ivana

    2015-09-01

    This work is concerned with nonlinear springs in series with the aim of obtaining the equivalent spring and its characteristics. The case of two linear springs in series is presented first as a basis for the extension to the cases of two purely nonlinear springs in series and two or more equal Duffing springs in series, which both allow the exact determination of the equivalent spring. Then, the most general case of two nonlinear springs with odd-power terms and different coefficients is examined. The condition is derived in terms of their characteristics for which the exact solution for the equivalent spring can be obtained.

  8. Development of Safety Assessment Code for Decommissioning of Nuclear Facilities

    NASA Astrophysics Data System (ADS)

    Shimada, Taro; Ohshima, Soichiro; Sukegawa, Takenori

    A safety assessment code, DecDose, for decommissioning of nuclear facilities has been developed, based on the experiences of the decommissioning project of Japan Power Demonstration Reactor (JPDR) at Japan Atomic Energy Research Institute (currently JAEA). DecDose evaluates the annual exposure dose of the public and workers according to the progress of decommissioning, and also evaluates the public dose at accidental situations including fire and explosion. As for the public, both the internal and the external doses are calculated by considering inhalation, ingestion, direct radiation from radioactive aerosols and radioactive depositions, and skyshine radiation from waste containers. For external dose for workers, the dose rate from contaminated components and structures to be dismantled is calculated. Internal dose for workers is calculated by considering dismantling conditions, e.g. cutting speed, cutting length of the components and exhaust velocity. Estimation models for dose rate and staying time were verified by comparison with the actual external dose of workers which were acquired during JPDR decommissioning project. DecDose code is expected to contribute the safety assessment for decommissioning of nuclear facilities.

  9. The Chernobyl NPP decommissioning: Current status and alternatives

    SciTech Connect

    Mikolaitchouk, H.; Steinberg, N.

    1996-08-01

    After the Chernobyl accident of April 26, 1986, many contradictory decisions were taken concerning the Chernobyl nuclear power plant (NPP) future. The principal source of contradictions was a deadline for a final shutdown of the Chernobyl NPP units. Alterations in a political and socioeconomic environment resulted in the latest decision of the Ukrainian Authorities about 2000 as a deadline for a beginning of the Chernobyl NPP decommissioning. The date seems a sound compromise among the parties concerned. However, in order to meet the data a lot of work should be done. First of all, a decommissioning strategy has to be established. The problem is complicated due to both site-specific aspects and an absence of proven solutions for the RBMK-type reactor decommissioning. In the paper the problem of decommissioning option selection is considered taking into account an influence of the following factors: relevant legislative and regulatory requirements; resources required to carry out decommissioning (man-power, equipment, technologies, waste management infrastructure, etc.); radiological and physical status of the plant, including structural integrity and predictable age and weather effects; impact of planned activities at the destroyed unit 4 and within the 30-km exclusion zone of the Chernobyl NPP; planed use of the site; socio-economic considerations.

  10. 30 CFR 585.904 - Can I request a departure from the decommissioning requirements?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... decommissioning requirements? 585.904 Section 585.904 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER... requirements under § 585.103. Decommissioning Applications...

  11. 30 CFR 585.904 - Can I request a departure from the decommissioning requirements?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... decommissioning requirements? 585.904 Section 585.904 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER... requirements under § 585.103. Decommissioning Applications...

  12. 30 CFR 585.904 - Can I request a departure from the decommissioning requirements?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... decommissioning requirements? 585.904 Section 585.904 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER... requirements under § 585.103. Decommissioning Applications...

  13. The shielding design process--new plants to decommissioning.

    PubMed

    Jeffries, Graham; Cooper, Andrew; Hobson, John

    2005-01-01

    BNFL have over 25 years experience of designing nuclear plant for the whole-fuel cycle. In the UK, a Nuclear Decommissioning Authority (NDA) is to be set up to ensure that Britain's nuclear legacy is cleaned up safely, securely and cost effectively. The resulting challenges and opportunities for shielding design will be substantial as the shielding design process was originally devised for the design of new plants. Although its underlying principles are equally applicable to decommissioning and remediation of old plants, there are many aspects of detailed application that need to adapt to this radically different operating environment. The paper describes both the common issues and the different challenges of shielding design at different operational phases. Sample applications will be presented of both new plant and decommissioning projects that illustrate not only the robust nature of the processes being used, but also how they lead to cost-effective solutions making a substantive and appropriate contribution to radiological protection goals. PMID:16604700

  14. Harbingers of Spring

    ERIC Educational Resources Information Center

    Serrao, John

    1976-01-01

    Emphasizing the spring migration of frogs, toads, and salamanders to their watery breeding sites, this article presents information on numerous amphibians and suggests both indoor and outdoor educational activities appropriate for elementary and/or early secondary instruction. (JC)

  15. 77 FR 75198 - Standard Format and Content for Post-Shutdown Decommissioning Activities Report

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-12-19

    ... COMMISSION Standard Format and Content for Post-Shutdown Decommissioning Activities Report AGENCY: Nuclear... Format and Content for Post-shutdown Decommissioning Activities Report.'' This guide describes a method...) 1.185, ``Standard Format and Content for Post-shutdown Decommissioning Activities Report,''...

  16. 77 FR 8902 - Draft Regulatory Guide: Issuance, Availability Decommissioning of Nuclear Power Reactors

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-02-15

    ... COMMISSION Draft Regulatory Guide: Issuance, Availability Decommissioning of Nuclear Power Reactors AGENCY... ``Decommissioning of Nuclear Power Reactors.'' This guide describes a method NRC considers acceptable for use in... Revision 1 of Regulatory Guide 1.184, ``Decommissioning of Nuclear Power Reactors,'' dated July 2000.......

  17. 30 CFR 585.905 - When must I submit my decommissioning application?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... application? 585.905 Section 585.905 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF Decommissioning Decommissioning Applications § 585.905 When must I submit my decommissioning application? You...

  18. 30 CFR 585.908 - What must I include in my decommissioning notice?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... notice? 585.908 Section 585.908 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF Decommissioning Decommissioning Applications § 585.908 What must I include in my decommissioning notice? (a)...

  19. 30 CFR 585.908 - What must I include in my decommissioning notice?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... notice? 585.908 Section 585.908 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF Decommissioning Decommissioning Applications § 585.908 What must I include in my decommissioning notice? (a)...

  20. 30 CFR 585.905 - When must I submit my decommissioning application?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... application? 585.905 Section 585.905 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF Decommissioning Decommissioning Applications § 585.905 When must I submit my decommissioning application? You...

  1. 30 CFR 585.1019 - What are the decommissioning requirements for an Alternate Use RUE?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... an Alternate Use RUE? 585.1019 Section 585.1019 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT... Facilities Decommissioning An Alternate Use Rue § 585.1019 What are the decommissioning requirements for an Alternate Use RUE? (a) Decommissioning requirements will be determined by BOEM on a case-by-case basis,...

  2. 30 CFR 285.1019 - What are the decommissioning requirements for an Alternate Use RUE?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... an Alternate Use RUE? 285.1019 Section 285.1019 Mineral Resources MINERALS MANAGEMENT SERVICE... Facilities Decommissioning An Alternate Use Rue § 285.1019 What are the decommissioning requirements for an Alternate Use RUE? (a) Decommissioning requirements will be determined by MMS on a case-by-case basis,...

  3. 30 CFR 285.1019 - What are the decommissioning requirements for an Alternate Use RUE?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... an Alternate Use RUE? 285.1019 Section 285.1019 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT... Activities Using Existing OCS Facilities Decommissioning An Alternate Use Rue § 285.1019 What are the decommissioning requirements for an Alternate Use RUE? (a) Decommissioning requirements will be determined by...

  4. 30 CFR 585.1019 - What are the decommissioning requirements for an Alternate Use RUE?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... an Alternate Use RUE? 585.1019 Section 585.1019 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT... Facilities Decommissioning An Alternate Use Rue § 585.1019 What are the decommissioning requirements for an Alternate Use RUE? (a) Decommissioning requirements will be determined by BOEM on a case-by-case basis,...

  5. 30 CFR 585.1019 - What are the decommissioning requirements for an Alternate Use RUE?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... an Alternate Use RUE? 585.1019 Section 585.1019 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT... Facilities Decommissioning An Alternate Use Rue § 585.1019 What are the decommissioning requirements for an Alternate Use RUE? (a) Decommissioning requirements will be determined by BOEM on a case-by-case basis,...

  6. ADVANTAGES, DISADVANTAGES, AND LESSONS LEARNED FROM MULTI-REACTOR DECOMMISSIONING PROJECTS

    SciTech Connect

    Morton, M.R.; Nielson, R.R.; Trevino, R.A.

    2003-02-27

    This paper discusses the Reactor Interim Safe Storage (ISS) Project within the decommissioning projects at the Hanford Site and reviews the lessons learned from performing four large reactor decommissioning projects sequentially. The advantages and disadvantages of this multi-reactor decommissioning project are highlighted.

  7. 30 CFR 250.1703 - What are the general requirements for decommissioning?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 30 Mineral Resources 2 2014-07-01 2014-07-01 false What are the general requirements for decommissioning? 250.1703 Section 250.1703 Mineral Resources BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT... Manager before decommissioning wells and from the Regional Supervisor before decommissioning platforms...

  8. 30 CFR 250.1703 - What are the general requirements for decommissioning?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 30 Mineral Resources 2 2012-07-01 2012-07-01 false What are the general requirements for decommissioning? 250.1703 Section 250.1703 Mineral Resources BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT... Manager before decommissioning wells and from the Regional Supervisor before decommissioning platforms...

  9. 26 CFR 1.468A-1T - Nuclear decommissioning costs; general rules (temporary).

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 26 Internal Revenue 6 2010-04-01 2010-04-01 false Nuclear decommissioning costs; general rules...-1T Nuclear decommissioning costs; general rules (temporary). (a) Introduction. Section 468A provides an elective method for taking into account nuclear decommissioning costs for Federal income...

  10. 26 CFR 1.468A-1 - Nuclear decommissioning costs; general rules.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 26 Internal Revenue 6 2014-04-01 2014-04-01 false Nuclear decommissioning costs; general rules. 1...-1 Nuclear decommissioning costs; general rules. (a) Introduction. Section 468A provides an elective method for taking into account nuclear decommissioning costs for Federal income tax purposes. In...

  11. 26 CFR 1.468A-1 - Nuclear decommissioning costs; general rules.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 26 Internal Revenue 6 2013-04-01 2013-04-01 false Nuclear decommissioning costs; general rules. 1...-1 Nuclear decommissioning costs; general rules. (a) Introduction. Section 468A provides an elective method for taking into account nuclear decommissioning costs for Federal income tax purposes. In...

  12. 26 CFR 1.468A-1 - Nuclear decommissioning costs; general rules.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 26 Internal Revenue 6 2011-04-01 2011-04-01 false Nuclear decommissioning costs; general rules. 1...-1 Nuclear decommissioning costs; general rules. (a) Introduction. Section 468A provides an elective method for taking into account nuclear decommissioning costs for Federal income tax purposes. In...

  13. 26 CFR 1.468A-1 - Nuclear decommissioning costs; general rules.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 26 Internal Revenue 6 2012-04-01 2012-04-01 false Nuclear decommissioning costs; general rules. 1...-1 Nuclear decommissioning costs; general rules. (a) Introduction. Section 468A provides an elective method for taking into account nuclear decommissioning costs for Federal income tax purposes. In...

  14. A costing model for offshore decommissioning in California.

    PubMed

    Bressler, Andrew; Bernstein, Brock B

    2015-10-01

    California's 27 offshore oil and gas platforms will reach the end of their useful lifetimes sometime in the near future and will require decommissioning. Although existing leases require complete removal of all platforms and associated infrastructure, the underlying laws and regulations have changed in recent years to allow a number of alternative uses after decommissioning. In particular, AB 2503, signed into law in September 2010, provides for a rigs-to-reefs program that allows the state to accept ownership of decommissioned platforms in federal waters. Decisions about whether to remove platforms completely or leave them in place as artificial reefs will depend in part on the relative cost of the 2 options. In this study, we describe the design and use of a mathematical decision model that provides detailed cost estimates of complete and partial removal (to 85 feet below the water line) for California's offshore platforms. The model, PLATFORM, is loaded with Bureau of Safety and Environmental Enforcement (BSEE) and Bureau of Ocean Energy Management (BOEM) costs for complete removal, along with costs for partial removal calculated for this study and estimates of the uncertainty associated with decommissioning cost estimates. PLATFORM allows users to define a wide range of decommissioning and costing scenarios (e.g., number of platforms, choice of heavy lift vessel, shell mound removal, reef enhancement). As a benchmark cost, complete removal of all 27 offshore platforms, grouped into the 7 decommissioning projects defined by the most recent federal cost estimates produced in 2010, would cost an estimated $1.09 billion, whereas partial removal of these platforms, grouped into the same set of projects, would cost $478 million, with avoided costs of $616 million (with minor rounding).

  15. A costing model for offshore decommissioning in California.

    PubMed

    Bressler, Andrew; Bernstein, Brock B

    2015-10-01

    California's 27 offshore oil and gas platforms will reach the end of their useful lifetimes sometime in the near future and will require decommissioning. Although existing leases require complete removal of all platforms and associated infrastructure, the underlying laws and regulations have changed in recent years to allow a number of alternative uses after decommissioning. In particular, AB 2503, signed into law in September 2010, provides for a rigs-to-reefs program that allows the state to accept ownership of decommissioned platforms in federal waters. Decisions about whether to remove platforms completely or leave them in place as artificial reefs will depend in part on the relative cost of the 2 options. In this study, we describe the design and use of a mathematical decision model that provides detailed cost estimates of complete and partial removal (to 85 feet below the water line) for California's offshore platforms. The model, PLATFORM, is loaded with Bureau of Safety and Environmental Enforcement (BSEE) and Bureau of Ocean Energy Management (BOEM) costs for complete removal, along with costs for partial removal calculated for this study and estimates of the uncertainty associated with decommissioning cost estimates. PLATFORM allows users to define a wide range of decommissioning and costing scenarios (e.g., number of platforms, choice of heavy lift vessel, shell mound removal, reef enhancement). As a benchmark cost, complete removal of all 27 offshore platforms, grouped into the 7 decommissioning projects defined by the most recent federal cost estimates produced in 2010, would cost an estimated $1.09 billion, whereas partial removal of these platforms, grouped into the same set of projects, would cost $478 million, with avoided costs of $616 million (with minor rounding). PMID:25914378

  16. Colloid update.

    PubMed

    Argalious, Maged Y

    2012-01-01

    This update aims to provide an evidence based review of natural and synthetic colloids with a special emphasis on the various generations of the synthetic colloid hydroxyethyl starch. The effect of 1(st), 2(nd) and 3(rd) generation hetastarches on bleeding, coagulopathy, acute kidney injury and mortality will be discussed. The results of randomised controlled trials addressing morbidity and mortality outcomes of colloid versus crystalloid resuscitation in critically ill patients will be described. In addition, the rationale and evidence behind early goal directed fluid therapy (EGDFT) including a practical approach to assessment of dynamic measures of fluid responsiveness will be presented.

  17. Rhabdomyolysis updated

    PubMed Central

    Efstratiadis, G; Voulgaridou, A; Nikiforou, D; Kyventidis, A; Kourkouni, E; Vergoulas, G

    2007-01-01

    Rhabdomyolysis constitutes a common cause of acute renal failure and presents paramount interest. A large variety of causes with different pathogenetic mechanisms can involve skeletal muscles resulting in rhabdomyolysis with or without acute renal failure. Crush syndrome, one of the most common causes of rhabdomyolysis presents increased clinical interest, particularly in areas often involved by earthquakes, such as Greece and Turkey. Drug abusers are another sensitive group of young patients prone to rhabdomyolysis, which attracts the clinical interest of a variety of medical specialties. We herein review the evidence extracted from updated literature concerning the data related to pathogenetic mechanisms and pathophysiology as well as the management of this interesting syndrome. PMID:19582207

  18. Web-Based Training on Reviewing Dose Modeling Aspects of NRC Decommissioning and License Termination Plans

    SciTech Connect

    LePoire, D.; Cheng, J.J.; Kamboj, S.; Arnish, J.; Richmond, P.; Chen, S.Y.; Barr, C.; McKenney, C.

    2008-01-15

    related to training, developing, and transferring knowledge to NRC staff on how to review dose-modeling portions of licensee-submitted DPs and LTPs. This project identified specific cases and examples, created easily updateable educational modules, represented material in an engaging format through animations, video, and graphics, and distributed information on how to perform these reviews in an accessible, web-based format. WBT promotes consistency in reviews and has the advantage of being able to be used as a resource to staff at any time. The WBT will provide reviewers with knowledge needed to perform risk-informed analyses (e.g., information related to development of realistic scenarios and use of probabilistic analysis). WBT on review of LTP or DP dose modeling will promote staff development, efficiency, and effectiveness in performing risk-informed, performance-based reviews of decommissioning activities at NRC-licensed facilities. One of the key advantages of this type of web-based training is that it can be loaded on-demand and can be reused indefinitely. In addition to the benefits of on-demand training, the modules can also be used for reference. The presentations are hosted on a web server that can be accessed by registered users at any time. Staff can return to a particular module to review the material long after they have completed the course.

  19. Springs of Great Britain

    NASA Astrophysics Data System (ADS)

    Day, J. B. W.

    1996-03-01

    Predictably, in a country such as Britain, with its preponderance of consolidated, sedimentary, mainly fissure-flow aquifers, there is a very large number of springs, many of which are, or have been, used for public supply. Migratory springs are a feature of the British (Ur. Cretaceous) Chalk, the most important British aquifer. The Chalk's low specific yield and high capillary moisture retention together give rise to very considerable fluctuations (more than 33 m in some areas) of the unconfined water table. Along the gentle dip slopes of the Chalk (North and South Downs of southern and southeastern England) springs may migrate laterally for several miles, giving rise to seasonal streams locally known as “bournes” or “lavants”. However, springs such as at Duncton, West Sussex, at the base of the much steeper scarp slopes of the Chalk, form point sources, the flows from which tend to be relatively steady; such springs commonly supply and are the original reason for the existence of many of the small towns and villages which nestle along the bases of the chalk scarps of Sussex and Kent. Where the Chalk forms coastal cliffs, a number of springs break out at the base of the cliff between high and low tide levels; there are major chalk coastal springs, for instance, at St. Margaret's Bay (Kent) and at Arish Mells, east of Lulworth Cove, Dorset. Such springs are not used for direct supply (their salinity is usually too high) but are indicators of the presence of local reserves of groundwater for possible future development.

  20. Mineral springs and miracles.

    PubMed Central

    Forster, M. M.

    1994-01-01

    Development of hot springs in the Canadian Rockies was closely linked to their reputed medicinal value. In 1885, the federal government created a small reserve around the springs at Sulphur Mountain, an area later enlarged to become Banff National Park, in recognition of the "great sanitary and curative advantage to the public." Images p730-a p731-a p732-a p733-a p734-a p736-a PMID:8199525

  1. Decommissioning of surplus facilities at Los Alamos National Laboratory

    SciTech Connect

    Stout, D.S.

    1995-03-01

    Decommissioning Buildings 3 and 4 South at Technical Area 21, Los Alamos National Laboratory, involves the decontamination, dismantlement, and demolition of two enriched-uranium processing buildings containing process equipment and ductwork holdup. The Laboratory has adopted two successful management strategies to implement this project: Rather than characterize an entire site, upfront, investigators use the ``observational approach,`` in which they collect only enough data to begin decommissioning activities and then determine appropriate procedures for further characterization as the work progresses. Project leaders augment work packages with task hazard analyses to fully define specific tasks and inform workers of hazards; all daily work activities are governed by specific work procedures and hazard analyses.

  2. Segmented tubular cushion springs and spring assembly

    NASA Technical Reports Server (NTRS)

    Haslim, L. A. (Inventor)

    1985-01-01

    A spring which includes a tube with an elliptical cross section, with the greater axial dimension extending laterally and the lesser axial dimension extending vertically is disclosed. A plurality of cuts in the form of slots passing through most of a wall of the tube extend perpendiculary to a longitudinal axis extending along the tube. An uncut portion of the tube wall extends along the tube for bonding or fastening the tube to a suitable base, such as a bottom of a seat cushion.

  3. Segmented tubular cushion springs and spring assembly

    NASA Technical Reports Server (NTRS)

    Haslim, Leonard A. (Inventor)

    1988-01-01

    A spring (10) includes a tube (12) having an elliptical cross section, with the greater axial dimension (22) extending laterally and the lesser axial dimension (24) extending vertically. A plurality of cuts (20) in the form of slots passing through most of a wall of the tube (12) extend perpendicularly to a longitudinal axis (16) extending along the tube (12). An uncut portion (26) of the tube wall extends along the tube (12) for bonding or fastening the tube to a suitable base, such as a bottom (28) of a seat cushion (30).

  4. Document Update and Compare

    NASA Technical Reports Server (NTRS)

    Knoch, C. F.; Caldwell, D. C.; Caldwell, D. L.

    1983-01-01

    Document Update and Compare programs provide simple computerized documentmaintenance system on Data General NOVA 840 computer. Document Update program allows user to update document either by batch or terminal input. Documents are modified and lists of modifications printed out.

  5. [Pharmacovigilance update].

    PubMed

    Diezi, Léonore; Renard, Delphine; Rothuizen, Laura E; Livio, Françoise

    2014-01-15

    The main pharmacovigilance updates in 2013 are reviewed. Nitrofurantoin: lower efficacy and an increased risk of adverse events when creatinine clearance is below 60 ml/min. Dabigatran: contraindicated in patients with mechanical heart valves. Azithromycin: QT prolongation and increased risk of death. Zolpidem: towards a lower dosage. Roflumilast: avoid in patients known or at risk for mood disorders. Retigabine: indication restricted to last-line use and new monitoring requirements after reports of pigment changes in retina and other tissues. Telaprevir and rituximab: severe mucocutaneous reactions. Fingolimod: rare cases of progressive multifocal leucoencephalopathy. Tolvaptan: potential for hepatotoxicity. Nicotinic acid/laropiprant: suspension of marketing authorization as benefits no longer outweigh risks. PMID:24558915

  6. Korea Research Reactor -1 & 2 Decommissioning Project in Korea

    SciTech Connect

    Park, S. K.; Chung, U. S.; Jung, K. J.; Park, J. H.

    2003-02-24

    Korea Research Reactor 1 (KRR-1), the first research reactor in Korea, has been operated since 1962, and the second one, Korea Research Reactor 2 (KRR-2) since 1972. The operation of both of them was phased out in 1995 due to their lifetime and operation of the new and more powerful research reactor, HANARO (High-flux Advanced Neutron Application Reactor; 30MW). Both are TRIGA Pool type reactors in which the cores are small self-contained units sitting in tanks filled with cooling water. The KRR-1 is a TRIGA Mark II, which could operate at a level of up to 250 kW. The second one, the KRR-2 is a TRIGA Mark III, which could operate at a level of up 2,000 kW. The decontamination and decommissioning (D & D) project of these two research reactors, the first D & D project in Korea, was started in January 1997 and will be completed to stage 3 by 2008. The aim of this decommissioning program is to decommission the KRR-1 & 2 reactors and to decontaminate the residual building structure s and the site to release them as unrestricted areas. KAERI (Korea Atomic Energy Research Institute) submitted the decommissioning plan and the environmental impact assessment reports to the Ministry of Science and Technology (MOST) for the license in December 1998, and was approved in November 2000.

  7. Decommissioning of nuclear reactor fuel channels using laser technology

    NASA Astrophysics Data System (ADS)

    Panchenko, Vladislav Y.; Zabelin, Alexandre M.; Slepokon, Yu. I.; Ryahin, V. M.; Kuznetsov, P. P.; Panasyuk, V. F.; Korotchenko, A. V.; Kislov, V. S.; Loktev, S. V.

    2000-07-01

    Decommissioning of nuclear reactors using laser remote dismounting and welding was experimentally proved at a nuclear reactor of Kursk Nuclear Power Plant. The main reason of laser beam application in this case is the marked decrease of radioactive exposure of the service personnel. The use of a high-power laser beam provided for laser cutting and welding processes realization at a distance up to 35 m between the laser and the workstation placed behind a radiation shield. By application of laser cutting gas and dust contamination is ten-fold decreased. Some results of decommissioning application of a stationary laser workstation based upon a 5 kW fast-transverse-flow discharge CW CO2 laser TL-5M installed at a nuclear reactor site are presented. A special high-beam- quality model of the laser was developed to satisfy the needs of decommissioning. Laser cutting process was applied to decommissioning of fuel channels (FC) of RBMK-1000 reactor, after their extractor from the reactor active zone during the procedure of channels replacement.

  8. Applying laser technology to decommissioning for nuclear power plant

    NASA Astrophysics Data System (ADS)

    Saishu, Sadanori; Abe, Seiji; Inoue, T.

    2000-01-01

    Laser technology has much possibility to accomplish nuclear facility decommissioning effective and the laser application to cutting technique and decontamination technique is considered in Japan. Nuclear Power Engineering Corporation had developed CO laser for cutting technique, and had developed YAG laser for decontamination.

  9. Worldwide Overview of Lessons Learned from Decommissioning Projects

    SciTech Connect

    Laraia, Michele

    2008-01-15

    With an increasing number of radioactive facilities and reactors now reaching the end of their useful life and being taken out of service, there is a growing emphasis worldwide on the safe and efficient decommissioning of such plants. There is a wealth of experience already gained in decommissioning projects for all kinds of nuclear facilities. It is now possible to compare and discuss progress and accomplishments worldwide. In particular, rather than on the factual descriptions of projects, technologies and case histories, it is important to focus on lessons learned: in this way, the return of experience is felt to effectively contribute to progress. Key issues - inevitably based on a subjective ranking - are presented in this paper. Through the exchange of lessons learned, it is possible to achieve full awareness of the need for resources for and constraints of safe and cost-effective decommissioning. What remains now is the identification of specific, remaining issues that may hinder or delay the smooth progress of decommissioning. To this end, lessons learned provide the necessary background information; this paper tries to make extensive use of practical experience gained by the international community.

  10. 18 CFR 2.24 - Project decommissioning at relicensing.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 18 Conservation of Power and Water Resources 1 2012-04-01 2012-04-01 false Project decommissioning at relicensing. 2.24 Section 2.24 Conservation of Power and Water Resources FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY GENERAL RULES GENERAL POLICY AND INTERPRETATIONS Statements of...

  11. 18 CFR 2.24 - Project decommissioning at relicensing.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 18 Conservation of Power and Water Resources 1 2014-04-01 2014-04-01 false Project decommissioning at relicensing. 2.24 Section 2.24 Conservation of Power and Water Resources FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY GENERAL RULES GENERAL POLICY AND INTERPRETATIONS Statements of...

  12. 18 CFR 2.24 - Project decommissioning at relicensing.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 18 Conservation of Power and Water Resources 1 2010-04-01 2010-04-01 false Project decommissioning at relicensing. 2.24 Section 2.24 Conservation of Power and Water Resources FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY GENERAL RULES GENERAL POLICY AND INTERPRETATIONS Statements of...

  13. 18 CFR 2.24 - Project decommissioning at relicensing.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 18 Conservation of Power and Water Resources 1 2013-04-01 2013-04-01 false Project decommissioning at relicensing. 2.24 Section 2.24 Conservation of Power and Water Resources FEDERAL ENERGY REGULATORY COMMISSION, DEPARTMENT OF ENERGY GENERAL RULES GENERAL POLICY AND INTERPRETATIONS Statements of...

  14. Damper Spring For Omega Seal

    NASA Technical Reports Server (NTRS)

    Maclaughlin, Scott T.; Montgomery, Stuart K.

    1993-01-01

    Damper spring reduces deflections of omega-cross-section seal, reducing probability of failure and extending life of seal. Spring is split ring with U-shaped cross section. Placed inside omega seal and inserted with seal into seal cavity. As omega seal compressed into cavity, spring and seal make contact near convolution of seal, and spring becomes compressed also. During operation, when seal dynamically loaded, spring limits deflection of seal, reducing stress on seal.

  15. Integration of improved decontamination and characterization technologies in the decommissioning of the CP-5 research reactor

    SciTech Connect

    Bhattacharyya, S. K.; Boing, L. E.

    2000-02-17

    The aging of research reactors worldwide has resulted in a heightened awareness in the international technical decommissioning community of the timeliness to review and address the needs of these research institutes in planning for and eventually performing the decommissioning of these facilities. By using the reactors already undergoing decommissioning as test beds for evaluating enhanced or new/innovative technologies for decommissioning, it is possible that new techniques could be made available for those future research reactor decommissioning projects. Potentially, the new technologies will result in: reduced radiation doses to the work force, larger safety margins in performing decommissioning and cost and schedule savings to the research institutes in performing the decommissioning of these facilities. Testing of these enhanced technologies for decontamination, dismantling, characterization, remote operations and worker protection are critical to furthering advancements in the technical specialty of decommissioning. Furthermore, regulatory acceptance and routine utilization for future research reactor decommissioning will be assured by testing and developing these technologies in realistically contaminated environments prior to use in the research reactors. The decommissioning of the CP-5 Research Reactor is currently in the final phase of dismantlement. In this paper the authors present results of work performed at Argonne National Laboratory (ANL) in the development, testing and deployment of innovative and/or enhanced technologies for the decommissioning of research reactors.

  16. Technology, safety, and costs of decommissioning a reference large irradiator and reference sealed sources

    SciTech Connect

    Haffner, D.R.; Villelgas, A.J.

    1996-01-01

    This report contains the results of a study sponsored by the US Nuclear Regulatory Commission (NRC) to examine the decommissioning of large radioactive irradiators and their respective facilities, and a broad spectrum of sealed radioactive sources and their respective devices. Conceptual decommissioning activities are identified, and the technology, safety, and costs (in early 1993 dollars) associated with decommissioning the reference large irradiator and sealed source facilities are evaluated. The study provides bases and background data for possible future NRC rulemaking regarding decommissioning, for evaluation of the reasonableness of planned decommissioning actions, and for determining if adequate funds are reserved by the licensees for decommissioning of their large irradiator or sealed source facilities. Another purpose of this study is to provide background and information to assist licensees in planning and carrying out the decommissioning of their sealed radioactive sources and respective facilities.

  17. Update on Law-Related Education, Spring 1977.

    ERIC Educational Resources Information Center

    American Bar Association, Chicago, IL. Special Committee on Youth Education for Citizenship.

    This is the first issue of a new journal designed to keep elementary and secondary school teachers and students up-to-date with developments in law-related education. The focus of this issue is on equal protection. Two major articles review recent Supreme Court cases and examine historical cases of segregation. Other features explain how schools…

  18. Decommissioning of U.S. uranium production facilities

    SciTech Connect

    Not Available

    1995-02-01

    From 1980 to 1993, the domestic production of uranium declined from almost 44 million pounds U{sub 3}O{sub 8} to about 3 million pounds. This retrenchment of the U.S. uranium industry resulted in the permanent closing of many uranium-producing facilities. Current low uranium prices, excess world supply, and low expectations for future uranium demand indicate that it is unlikely existing plants will be reopened. Because of this situation, these facilities eventually will have to be decommissioned. The Uranium Mill Tailings and Radiation Control Act of 1978 (UMTRCA) vests the U.S. Environmental Protection Agency (EPA) with overall responsibility for establishing environmental standards for decommissioning of uranium production facilities. UMTRCA also gave the U.S. Nuclear Regulatory Commission (NRC) the responsibility for licensing and regulating uranium production and related activities, including decommissioning. Because there are many issues associated with decommissioning-environmental, political, and financial-this report will concentrate on the answers to three questions: (1) What is required? (2) How is the process implemented? (3) What are the costs? Regulatory control is exercised principally through the NRC licensing process. Before receiving a license to construct and operate an uranium producing facility, the applicant is required to present a decommissioning plan to the NRC. Once the plan is approved, the licensee must post a surety to guarantee that funds will be available to execute the plan and reclaim the site. This report by the Energy Information Administration (EIA) represents the most comprehensive study on this topic by analyzing data on 33 (out of 43) uranium production facilities located in Colorado, Nebraska, New Mexico, South Dakota, Texas, Utah, and Washington.

  19. Atmospheric discharges from nuclear facilities during decommissioning: German experiences

    SciTech Connect

    Braun, H.; Goertz, R.; Weil, L.

    1997-08-01

    In Germany, a substantial amount of experience is available with planning, licensing and realization of decommissioning projects. In total, a number of 18 nuclear power plants including prototype facilities as well as 6 research reactors and 3 fuel cycle facilities have been shut down finally and are at different stages of decommissioning. Only recently the final {open_quotes}green field{close_quotes} stage of the Niederaichbach Nuclear Power Plant total dismantlement project has been achieved. From the regulatory point of view, a survey of the decommissioning experience in Germany is presented highlighting the aspects of production and retention of airborne radioactivity. Nuclear air cleaning technology, discharge limits prescribed in licences and actual discharges are presented. As compared to operation, the composition of the discharged radioactivity is different as well as the off-gas discharge rate. In practically all cases, there is no significant amount of short-lived radionuclides. The discussion further includes lessons learned, for example inadvertent discharges of radionuclides expected not to be in the plants inventory. It is demonstrated that, as for operation of nuclear power plants, the limits prescribed in the Ordinance on Radiological Protection can be met using existing air cleaning technology, Optimization of protection results in public exposures substantially below the limits. In the frame of the regulatory investigation programme a study has been conducted to assess the airborne radioactivity created during certain decommissioning activities like decontamination, segmentation and handling of contaminated or activated parts. The essential results of this study are presented, which are supposed to support planning for decommissioning, for LWRs, Co-60 and Cs-137 are expected to be the dominant radionuclides in airborne discharges. 18 refs., 2 figs., 1 tab.

  20. Education in nuclear decommissioning in the north of Scotland

    SciTech Connect

    Catlow, F.; Reeves, G.M.

    2007-07-01

    This paper describes the work covered and experience gained in the first two years of operation of DERC, a Centre for Decommissioning and Environmental Remediation in the Highlands of Scotland. The Centre is a unique development which was set up to teach nuclear decommissioning as a separate discipline, address the problem of a declining skills base in the field of nuclear technologies and to take advantage of the unique and exceptional innovative, technical and research opportunities offered through the decommissioning of Britain's fast reactor site at Dounreay. The Centre is an offshoot from North Highland College which is a member of UHI, the University in embryo of the Highlands and Islands. The Centre currently supports ten PhD students completing various diverse projects mainly in the field of nuclear environmental remediation. In addition there area number of full and part time MSc students who participate in NTEC (Nuclear Technology Education Consortium) a consortium of British Universities set up specifically to engender interest and skills in nuclear technology at postgraduate level. At undergraduate level, courses are offered in Nuclear Decommissioning and related subjects as part of Electrical and Mechanical degree courses. In addition to our relationship with the United Kingdom Atomic Energy Authority (UKAEA) the Dounreay site licensee, we have links with Rolls-Royce and the Ministry of Defence who also share the Dounreay site and with other stakeholders such as, the UK regulator (HSE/NII), the Scottish Environmental Protection Agency (SEPA), local and international contractors and we liaise with the newly formed Nuclear Decommissioning Authority (NDA), who provide some sponsorship and support. We possess our own equipment and laboratories for taking and analysing soil samples and for conducting environmental surveys. Recently we commissioned an aerial survey of contamination in the locality from natural sources, other background levels such as

  1. Roller belleville spring damper

    SciTech Connect

    Hebel, J.B.

    1981-07-07

    A double acting damper for use in rotary drilling includes a splined tubular telescopic joint and employs plural paralleled stacks of double acting series stacked roller belleville spring washers in an annular pocket between the inner and outer tubular members of the joint. The springs, spline and telescopic bearings are in an oil filled volume sealed from the outside by a pressure seal at the lower end of the damper and a floating seal at the upper end. Electric and magnetic means are provided to check on the condition and quantity of the lubricant.

  2. Energy Matters - Spring 2002

    SciTech Connect

    2002-03-01

    Quarterly newsletter from DOE's Industrial Technologies Program to promote the use of energy-efficient industrial systems. The focus of the Spring 2002 Issue of Energy Matters focuses on premium energy efficiency systems, with articles on new gas technologies, steam efficiency, the Augusta Newsprint Showcase, and more.

  3. Spa, springs and safety.

    PubMed

    Sukthana, Yaowalark; Lekkla, Amorn; Sutthikornchai, Chantira; Wanapongse, Paitoon; Vejjajiva, Athasit; Bovornkitti, Somchai

    2005-01-01

    Natural mineral water has long been used worldwide for bathing and health purposes. At present, Thailand is famous for health spas and natural hot springs among local people and tourists. Due to possible risks of exposure to harmful agents, we studied hazardous pollutants at 57 natural hot springs from 11 provinces in northern, central, eastern and southern Thailand. Pathogenic, free-living amebae of the genera Naegleria and Acanthamoeba, which can cause central nervous system infection, were found in 26.3% (15/57) and 15.8% (9/ 57), respectively. Dissolved radon, a soil gas with carcinogenic properties, was present in nearly all hot springs sites, with concentration ranging from 0.87-76,527 Becquerels/m3. There were 5 water samples in which radon concentration exceeded the safety limit for drinking. Legionella pneumoniphila (serogroups 1, 3, 5, 6, 7 10 and 13) were found in samples from 71.9% (41/57) of studied sites. Because spas and natural springs are popular tourist attractions, health authorities should be aware of possible hazards and provide tactful measures and guidelines to ensure safety without causing undue alarm to foreign and Thai tourists.

  4. Echoes of Spring Valley.

    ERIC Educational Resources Information Center

    Boyken, J. Clarine J.

    Designed to preserve the rich heritage of the rural school system which passed from the education scene in the 1930's and 1940's, this narrative, part history and part nostalgia, describes the author's own elementary education and the secure community life centered in the one room Spring Valley School in Hamilton County, Iowa, in the early decades…

  5. Editors' Spring Picks

    ERIC Educational Resources Information Center

    Library Journal, 2011

    2011-01-01

    While they do not represent the rainbow of reading tastes American public libraries accommodate, Book Review editors are a wildly eclectic bunch. One look at their bedside tables and ereaders would reveal very little crossover. This article highlights an eclectic array of spring offerings ranging from print books to an audiobook to ebook apps. It…

  6. A Quadratic Spring Equation

    ERIC Educational Resources Information Center

    Fay, Temple H.

    2010-01-01

    Through numerical investigations, we study examples of the forced quadratic spring equation [image omitted]. By performing trial-and-error numerical experiments, we demonstrate the existence of stability boundaries in the phase plane indicating initial conditions yielding bounded solutions, investigate the resonance boundary in the [omega]…

  7. 1981 Spring Meeting Report

    NASA Astrophysics Data System (ADS)

    Approximately 2150 participants registered for the 1981 Spring Meeting. More than 1500 papers were presented.The spaciousness of the Baltimore Convention Center provided ample opportunity for attendees to exchange ideas and interact with their colleagues. Here are some candid shots.

  8. The News. Spring 2006

    ERIC Educational Resources Information Center

    Giles, Ray, Ed.

    2006-01-01

    This Spring issue of the quarterly newsletter of the Community College League of California contains the following articles: (1) Enrollment Drops; Fees to Blame?; (2) Senate's Grad Proposal Triggers Debate on Mission, Access; (3) Compton Decision has Affected Perceptions of Commission (discussion with Barbara Beno); (4) Dynamic New Architectural…

  9. Planar torsion spring

    NASA Technical Reports Server (NTRS)

    Ihrke, Chris A. (Inventor); Parsons, Adam H. (Inventor); Mehling, Joshua S. (Inventor); Griffith, Bryan Kristian (Inventor)

    2012-01-01

    A torsion spring comprises an inner mounting segment. An outer mounting segment is located concentrically around the inner mounting segment. A plurality of splines extends from the inner mounting segment to the outer mounting segment. At least a portion of each spline extends generally annularly around the inner mounting segment.

  10. Renaissance Administrator, Spring 1998.

    ERIC Educational Resources Information Center

    Dowdy, June P., Ed.

    1998-01-01

    This spring 1998 issue of Renaissance Administrator features the following articles: (1) "Servant Leadership and Higher Education--What is Leadership?" (Richard E. Hasselbach); (2) "Teaching Writing in the 90's--Carnivorous Printers and Dying Grandmothers" (Helen Ruggieri); (3) Assignment--Journal Writing" (Lynn Muscato); and (4) "A Business…

  11. 9. CONTEXTUAL VIEW SOUTHSOUTHEAST TOWARDS SPRING SITE. SPRING LEFT CORNER. ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    9. CONTEXTUAL VIEW SOUTH-SOUTHEAST TOWARDS SPRING SITE. SPRING LEFT CORNER. - Juniata Mill Complex, 22.5 miles Southwest of Hawthorne, between Aurora Crater & Aurora Peak, Hawthorne, Mineral County, NV

  12. Preservation and Implementation of Decommissioning Lessons Learned in the United States Nuclear Regulatory Commission

    SciTech Connect

    Rodriguez, Rafael L.

    2008-01-15

    Over the past several years, the United States Nuclear Regulatory Commission (NRC) has actively worked to capture and preserve lessons learned from the decommissioning of nuclear facilities. More recently, NRC has involved industry groups, the Organization of Agreement States (OAS), and the Department of Energy (DOE) in the effort to develop approaches to capture, preserve and disseminate decommissioning lessons learned. This paper discusses the accomplishments of the working group, some lessons learned by the NRC in the recent past, and how NRC will incorporate these lessons learned into its regulatory framework. This should help ensure that the design and operation of current and future nuclear facilities will result in less environmental impact and more efficient decommissioning. In summary, the NRC will continue capturing today's experience in decommissioning so that future facilities can take advantage of lessons learned from today's decommissioning projects. NRC, both individually and collectively with industry groups, OAS, and DOE, is aggressively working on the preservation and implementation of decommissioning lessons learned. The joint effort has helped to ensure the lessons from the whole spectrum of decommissioning facilities (i.e., reactor, fuel cycle, and material facilities) are better understood, thus maximizing the amount of knowledge and best practices obtained from decommissioning activities. Anticipated regulatory activities at the NRC will make sure that the knowledge gained from today's decommissioning projects is preserved and implemented to benefit the nuclear facilities that will decommission in the future.

  13. Draft principles, policy, and acceptance criteria for decommissioning of U.S. Department of Energy contaminated surplus facilities and summary of international decommissioning programs

    SciTech Connect

    Singh, B.K. |; Gillette, J.; Jackson, J.

    1994-12-01

    Decommissioning activities enable the DOE to reuse all or part of a facility for future activities and reduce hazards to the general public and any future work force. The DOE Office of Environment, Health and Safety has prepared this document, which consists of decommissioning principles and acceptance criteria, in an attempt to establish a policy that is in agreement with the NRC policy. The purpose of this document is to assist individuals involved with decommissioning activities in determining their specific responsibilities as identified in Draft DOE Order 5820.DDD, ``Decommissioning of US Department of Energy Contaminated Surplus Facilities`` (Appendix A). This document is not intended to provide specific decommissioning methodology. The policies and principles of several international decommissioning programs are also summarized. These programs are from the IAEA, the NRC, and several foreign countries expecting to decommission nuclear facilities. They are included here to demonstrate the different policies that are to be followed throughout the world and to allow the reader to become familiar with the state of the art for environment, safety, and health (ES and H) aspects of nuclear decommissioning.

  14. Responding To Changes in the Decommissioning Plans for Demolition of a Former Active Handling Building at The United Kingdom Atomic Energy Establishment Winfrith

    SciTech Connect

    Brown, N.; Parkinson, S.J.; Cornell, R.M.; Staples, A.T.

    2006-07-01

    The full decommissioning of the former Active Handling Building A59 at Winfrith in Dorset is being carried out by RWE NUKEM Limited under contract from the site owners and nuclear site licence holder, United Kingdom Atomic Energy Authority (UKAEA). Following recent government changes, the United Kingdom's Nuclear Decommissioning Authority (NDA) has now set up contracts with UKAEA for delivery of the site clean-up programme. The building contains two heavily shielded suites of caves originally used to carry out remote examination of irradiated nuclear fuel elements together with other supporting facilities. The original intention was to demolish the caves ahead of the building but after detailed consideration it was concluded that demolition of the building in advance of the caves was more operationally effective. As a result, the original decommissioning plan had to be reworked to reflect these changes. The paper briefly explains how this situation arose and the means by which the problems experienced were overcome by a complete revision to the decommissioning programme. The updated plan has been adopted by UKAEA and work is now proceeding apace to clear the building of redundant items, to complete decontamination of all remaining areas and facilities and to carry out detailed radiological surveys to confirm that the building structure is clean and ready for demolition. Both cave lines have been completely decontaminated to low residual levels of activity and are essentially ready for controlled demolition. This paper describes some of the significant tasks undertaken during the past year with particular reference to the decommissioning techniques that gave the greatest success and the limitations of others originally considered. Some of these processes were aimed at minimising the volume of low level waste (LLW) generated by using standard off-the-shelf equipment to remove contamination from {approx}5 Ton concrete blocks recovered from both cave line structures. A

  15. Studying Springs in Series Using a Single Spring

    ERIC Educational Resources Information Center

    Serna, Juan D.; Joshi, Amitabh

    2011-01-01

    Springs are used for a wide range of applications in physics and engineering. Possibly, one of their most common uses is to study the nature of restoring forces in oscillatory systems. While experiments that verify Hooke's law using springs are abundant in the physics literature, those that explore the combination of several springs together are…

  16. Carbon-14 Bioassay for Decommissioning of Hanford Reactors

    SciTech Connect

    Carbaugh, Eugene H.; Watson, David J.

    2012-05-01

    The old production reactors at the US Department of Energy Hanford Site used large graphite piles as the moderator. As part of long-term decommissioning plans, the potential need for 14C radiobioassay of workers was identified. Technical issues associated with 14C bioassay and worker monitoring were investigated, including anticipated graphite characterization, potential intake scenarios, and the bioassay capabilities that may be required to support the decommissioning of the graphite piles. A combination of urine and feces sampling would likely be required for the absorption type S 14C anticipated to be encountered. However the concentrations in the graphite piles appear to be sufficiently low that dosimetrically significant intakes of 14C are not credible, thus rendering moot the need for such bioassay.

  17. Decontamination and Decommissioning activities photobriefing book FY 1997

    SciTech Connect

    1998-04-01

    The Decontamination and Decommissioning (D and D) Program at Argonne National Laboratory-East (ANL-E) is dedicated to the safe and cost effective D{ampersand}D of surplus nuclear facilities. There is currently a backlog of more than 7,000 contaminated US Department of Energy facilities nationwide. Added to this are 110 licensed commercial nuclear power reactors operated by utilities learning to cope with deregulation and an aging infrastructure that supports the commercial nuclear power industry, as well as medical and other uses of radioactive materials. With this volume it becomes easy to understand the importance of addressing the unique issues and objectives associated with the D{ampersand}D of surplus nuclear facilities. This photobriefing book summarizes the decontamination and decommissioning projects and activities either completed or continuing at the ANL-E site during the year.

  18. Carbon-14 bioassay for decommissioning of Hanford reactors.

    PubMed

    Carbaugh, Eugene H; Watson, David J

    2012-05-01

    The production reactors at the U.S. Department of Energy Hanford Site used large graphite piles as the moderator. As part of long-term decommissioning plans, the potential need for ¹⁴C radiobioassay of workers was identified. Technical issues associated with ¹⁴C bioassay and worker monitoring were investigated, including anticipated graphite characterization, potential intake scenarios, and the bioassay capabilities that may be required to support the decommissioning of the graphite piles. A combination of urine and feces sampling would likely be required for the absorption type S ¹⁴C anticipated to be encountered. However, the concentrations in the graphite piles appear to be sufficiently low that dosimetrically significant intakes of ¹⁴C are not credible, thus rendering moot the need for such bioassay.

  19. Carbon-14 bioassay for decommissioning of Hanford reactors.

    PubMed

    Carbaugh, Eugene H; Watson, David J

    2012-05-01

    The production reactors at the U.S. Department of Energy Hanford Site used large graphite piles as the moderator. As part of long-term decommissioning plans, the potential need for ¹⁴C radiobioassay of workers was identified. Technical issues associated with ¹⁴C bioassay and worker monitoring were investigated, including anticipated graphite characterization, potential intake scenarios, and the bioassay capabilities that may be required to support the decommissioning of the graphite piles. A combination of urine and feces sampling would likely be required for the absorption type S ¹⁴C anticipated to be encountered. However, the concentrations in the graphite piles appear to be sufficiently low that dosimetrically significant intakes of ¹⁴C are not credible, thus rendering moot the need for such bioassay. PMID:22469998

  20. MedlinePlus E-mail Updates | NIH MedlinePlus the Magazine

    MedlinePlus

    ... of this page please turn Javascript on. MedlinePlus E-mail Updates Past Issues / Spring - Summer 2010 Table ... in health and medicine? Sign up for MedlinePlus e-mail updates, and you'll receive alerts whenever ...

  1. 78 FR 46733 - Medicare Program; Inpatient Psychiatric Facilities Prospective Payment System-Update for Fiscal...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-08-01

    ... Register (69 FR 66922). In developing the IPF PPS, in order to ensure that the IPF PPS is able to account... intention to publish a notice in the Federal Register each spring to update the IPF PPS (71 FR 27041). In the May 6, 2011 IPF PPS final rule (76 FR 26432), we changed the payment rate update period to a...

  2. 77 FR 47223 - Medicare Program; Inpatient Psychiatric Facilities Prospective Payment System-Update for Fiscal...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-08-07

    ...) in a final rule that appeared in the November 15, 2004 Federal Register (69 FR 66922). In developing... publish a notice in the Federal Register each spring to update the IPF PPS (71 FR 27041). In the May 6, 2011 IPF PPS final rule (76 FR 26432), we changed the payment rate update period to a rate year...

  3. 76 FR 26431 - Medicare Program; Inpatient Psychiatric Facilities Prospective Payment System-Update for Rate...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-05-06

    ... Register (69 FR 66922). In developing the IPF PPS, in order to ensure that the IPF PPS is able to account... stated our intention to publish a notice in the Federal Register each spring to update the IPF PPS (71 FR... most recent IPF PPS annual update occurred in the April 30, 2010 Federal Register notice (75 FR...

  4. FACILITY DEACTIVATION AND DECOMMISSIONING AT THE SAVANNAH RIVER SITE

    SciTech Connect

    Gilmour, J; William Austin, W; Cathy Sizemore, C

    2007-01-31

    In February 2002, the U.S. Department of Energy initiated actions to expedite Cleanup, focus on significant and early risk reduction, and reduce costs at the Savannah River Site (SRS). In response SRS started on a project focused on completing the decommissioning of inactive facilities in T, D, and M Areas, areas that on the perimeter of the Site, by the end of 2006. In June 2003, the Department of Energy Savannah River Operations Office (DOE-SR), the South Carolina Department of Health and Environmental Control (SCDHEC), and the Environmental Protection Agency, Region 4 (EPA-4) endorsed a Memorandum of Agreement (MOA) concerning cleanup at the Savannah River Site (SRS). The vision of the Agreement is that SRS will reduce its operations footprint to establish a buffer zone at the perimeter if the Site, while the central core area of the Site will be reserved for continuing or future long-term operations. DOE-SR, EPA-4, and SCDHEC agreed that establishing this buffer zone and appropriately sequencing environmental restoration and decommissioning activities can lead to greater efficiency and accelerate completion of entire site areas. This vision is embodied in the concept of Area Completion--which integrated operations, deactivation and decommissioning (D&D), and soils and groundwater cleanup into a time-phased approach to completing all the work necessary to address the Cold War legacy. D&D addresses the ''footprint'' of the building or structure, while the soils and groundwater project addresses any environmental remediation that may be required in the underlying and surrounding soils and groundwater. Since then, {approx}250 facilities have been decommissioned at the SRS, ranging from guard stations to nuclear fuel production facilities.

  5. Reducing environmental risk associated with laboratory decommissioning and property transfer.

    PubMed

    Dufault, R; Abelquist, E; Crooks, S; Demers, D; DiBerardinis, L; Franklin, T; Horowitz, M; Petullo, C; Sturchio, G

    2000-12-01

    The need for more or less space is a common laboratory problem. Solutions may include renovating existing space, leaving or demolishing old space, or acquiring new space or property for building. All of these options carry potential environmental risk. Such risk can be the result of activities related to the laboratory facility or property (e.g., asbestos, underground storage tanks, lead paint), or the research associated with it (e.g., radioactive, microbiological, and chemical contamination). Regardless of the option chosen to solve the space problem, the potential environmental risk must be mitigated and the laboratory space and/or property must be decommissioned or rendered safe prior to any renovation, demolition, or property transfer activities. Not mitigating the environmental risk through a decommissioning process can incur significant financial liability for any costs associated with future decommissioning cleanup activities. Out of necessity, a functioning system, environmental due diligence auditing, has evolved over time to assess environmental risk and reduce associated financial liability. This system involves a 4-phase approach to identify, document, manage, and clean up areas of environmental concern or liability, including contamination. Environmental due diligence auditing includes a) historical site assessment, b) characterization assessment, c) remedial effort and d) final status survey. General practice standards from the American Society for Testing and Materials are available for conducting the first two phases. However, standards have not yet been developed for conducting the third and final phases of the environmental due diligence auditing process. Individuals involved in laboratory decommissioning work in the biomedical research industry consider this a key weakness.

  6. Reducing environmental risk associated with laboratory decommissioning and property transfer.

    PubMed Central

    Dufault, R; Abelquist, E; Crooks, S; Demers, D; DiBerardinis, L; Franklin, T; Horowitz, M; Petullo, C; Sturchio, G

    2000-01-01

    The need for more or less space is a common laboratory problem. Solutions may include renovating existing space, leaving or demolishing old space, or acquiring new space or property for building. All of these options carry potential environmental risk. Such risk can be the result of activities related to the laboratory facility or property (e.g., asbestos, underground storage tanks, lead paint), or the research associated with it (e.g., radioactive, microbiological, and chemical contamination). Regardless of the option chosen to solve the space problem, the potential environmental risk must be mitigated and the laboratory space and/or property must be decommissioned or rendered safe prior to any renovation, demolition, or property transfer activities. Not mitigating the environmental risk through a decommissioning process can incur significant financial liability for any costs associated with future decommissioning cleanup activities. Out of necessity, a functioning system, environmental due diligence auditing, has evolved over time to assess environmental risk and reduce associated financial liability. This system involves a 4-phase approach to identify, document, manage, and clean up areas of environmental concern or liability, including contamination. Environmental due diligence auditing includes a) historical site assessment, b) characterization assessment, c) remedial effort and d) final status survey. General practice standards from the American Society for Testing and Materials are available for conducting the first two phases. However, standards have not yet been developed for conducting the third and final phases of the environmental due diligence auditing process. Individuals involved in laboratory decommissioning work in the biomedical research industry consider this a key weakness. PMID:11121365

  7. TECHNOLOGY REQUIREMENTS FOR IN SITU DECOMMISSIONING WORKSHOP REPORT

    SciTech Connect

    Jannik, T.; Lee, P.; Gladden, J.; Langton, C.; Serrato, M.; Urland, C.; Reynolds, E.

    2009-06-30

    In recognition of the increasing attention being focused on In Situ Decommissioning (ISD or entombment) as an acceptable and beneficial decommissioning end state, the Department of Energy's (DOE) Office of Environmental Management (EM) is developing guidance for the implementation of ISD of excess facilities within the DOE complex. Consistent with the overarching DOE goals for increased personnel and environmental safety, reduced technical uncertainties and risks, and overall gains in efficiencies and effectiveness, EM's Office of Deactivation and Decommissioning and Facility Engineering (EM-23) initiated efforts to identify the technical barriers and technology development needs for the optimal implementation of ISD. Savannah River National Laboratory (SRNL), as the EM Corporate Laboratory, conducted an ISD Technology Needs Workshop to identify the technology needs at DOE sites. The overall goal of the workshop was to gain a full understanding of the specific ISD technical challenges, the technologies available, and those needing development. The ISD Workshop was held December 9-10, 2008 in Aiken, SC. Experienced decommissioning operations personnel from Richland Operations Office (RL), Idaho National Laboratory (INL) and Savannah River Site (SRS) along with scientists and engineers specific expertise were assembled to identify incremental and 'game changing' solutions to ISD technology challenges. The workshop and follow-up activities yielded 14 technology needs statements and the recommendation that EM-23 prioritize and pursue the following specific technology development and deployment actions. For each action, the recommended technology acquisition mechanisms (competitive solicitation (CS) or direct funding (TCR)) are provided. Activities that are time critical for ISD projects, or require unique capabilities that reside in the DOE Laboratory system will be funded directly to those institutions. Activities that have longer lead times and where the private

  8. Hot Spring Metagenomics

    PubMed Central

    López-López, Olalla; Cerdán, María Esperanza; González-Siso, María Isabel

    2013-01-01

    Hot springs have been investigated since the XIX century, but isolation and examination of their thermophilic microbial inhabitants did not start until the 1950s. Many thermophilic microorganisms and their viruses have since been discovered, although the real complexity of thermal communities was envisaged when research based on PCR amplification of the 16S rRNA genes arose. Thereafter, the possibility of cloning and sequencing the total environmental DNA, defined as metagenome, and the study of the genes rescued in the metagenomic libraries and assemblies made it possible to gain a more comprehensive understanding of microbial communities—their diversity, structure, the interactions existing between their components, and the factors shaping the nature of these communities. In the last decade, hot springs have been a source of thermophilic enzymes of industrial interest, encouraging further study of the poorly understood diversity of microbial life in these habitats. PMID:25369743

  9. Hot spring metagenomics.

    PubMed

    López-López, Olalla; Cerdán, María Esperanza; González-Siso, María Isabel

    2013-01-01

    Hot springs have been investigated since the XIX century, but isolation and examination of their thermophilic microbial inhabitants did not start until the 1950s. Many thermophilic microorganisms and their viruses have since been discovered, although the real complexity of thermal communities was envisaged when research based on PCR amplification of the 16S rRNA genes arose. Thereafter, the possibility of cloning and sequencing the total environmental DNA, defined as metagenome, and the study of the genes rescued in the metagenomic libraries and assemblies made it possible to gain a more comprehensive understanding of microbial communities-their diversity, structure, the interactions existing between their components, and the factors shaping the nature of these communities. In the last decade, hot springs have been a source of thermophilic enzymes of industrial interest, encouraging further study of the poorly understood diversity of microbial life in these habitats. PMID:25369743

  10. Improving the Identification, Dissemination and Implementation of Deactivation and Decommissioning Lessons Learned and Best Practices

    SciTech Connect

    Waisley, Sandra L.; Lackey, Michael B.; Dusek, Lansing G.

    2008-01-15

    Approximately $150 billion of work currently remains in the United States Department of Energy's (DoE's) Office of Environmental Management (EM) life cycle budget for U.S. projects. Contractors who manage facilities for the DOE have been challenged to identify transformational changes to reduce the life cycle costs and to develop a knowledge-management system that identifies, disseminates, and tracks the implementation of lessons learned and best practices. This paper discusses DoE's rationale for using lessons learned and best practices to improve safety and performance while reducing life cycle costs for Deactivation and Decommissioning (D and D) projects. It also provides an update on the Energy Facility Contractors Group's (EFCOG's) progress in supporting DoE's efforts. At this juncture the best practice efforts described are in developmental stages; however, the commitment to and the concrete nature of the work thus far is noteworthy in regard to improving the way D and D lessons learned and best practices are identified, disseminated and implemented across the DOE Complex.

  11. Spring operated accelerator and constant force spring mechanism therefor

    NASA Technical Reports Server (NTRS)

    Shillinger, G. L., Jr. (Inventor)

    1977-01-01

    A spring assembly consisting of an elongate piece of flat spring material formed into a spiral configuration and a free running spool in circumscribing relation to which this spring is disposed was developed. The spring has a distal end that is externally accessible so that when the distal end is drawn along a path, the spring unwinds against a restoring force present in the portion of the spring that resides in a transition region between a relatively straight condition on the path and a fully wound condition on the spool. When the distal end is released, the distal end is accelerated toward the spool by the force existing at the transition region which force is proportional to the cross-sectional area of the spring.

  12. Decontamination and decommissioning of the Mayaguez (Puerto Rico) facility

    SciTech Connect

    Jackson, P.K.; Freemerman, R.L.

    1989-11-01

    On February 6, 1987 the US Department of Energy (DOE) awarded the final phase of the decontamination and decommissioning of the nuclear and reactor facilities at the Center for Energy and Environmental Research (CEER), in Mayaguez, Puerto Rico. Bechtel National, Inc., was made the decontamination and decommissioning (D and D) contractor. The goal of the project was to enable DOE to proceed with release of the CEER facility for use by the University of Puerto Rico, who was the operator. This presentation describes that project and lesson learned during its progress. The CEER facility was established in 1957 as the Puerto Rico Nuclear Center, a part of the Atoms for Peace Program. It was a nuclear training and research institution with emphasis on the needs of Latin America. It originally consisted of a 1-megawatt Materials Testing Reactor (MTR), support facilities and research laboratories. After eleven years of operation the MTR was shutdown and defueled. A 2-megawatt TRIGA reactor was installed in 1972 and operated until 1976, when it woo was shutdown. Other radioactive facilities at the center included a 10-watt homogeneous L-77 training reactor, a natural uranium graphite-moderated subcritical assembly, a 200KV particle accelerator, and a 15,000 Ci Co-60 irradiation facility. Support facilities included radiochemistry laboratories, counting rooms and two hot cells. As the emphasis shifted to non-nuclear energy technology a name change resulted in the CEER designation, and plans were started for the decontamination and decommissioning effort.

  13. Aroma potential of oak battens prepared from decommissioned oak barrels.

    PubMed

    Li, Sijing; Crump, Anna M; Grbin, Paul R; Cozzolino, Daniel; Warren, Peter; Hayasaka, Yoji; Wilkinson, Kerry L

    2015-04-01

    During barrel maturation, volatile compounds are extracted from oak wood and impart aroma and flavor to wine, enhancing its character and complexity. However, barrels contain a finite pool of extractable material, which diminishes with time. As a consequence, most barrels are decommissioned after 5 or 6 years. This study investigated whether or not decommissioned barrels can be "reclaimed" and utilized as a previously untapped source of quality oak for wine maturation. Oak battens were prepared from staves of decommissioned French and American oak barrels, and their composition analyzed before and after toasting. The oak lactone glycoconjugate content of untoasted reclaimed oak was determined by liquid chromatography-tandem mass spectrometry, while the concentrations of cis- and trans-oak lactone, guaiacol, 4-methlyguaiacol, vanillin, eugenol, furfural, and 5-methylfurfural present in toasted reclaimed oak were determined by gas chromatography-mass spectrometry. Aroma potential was then evaluated by comparing the composition of reclaimed oak with that of new oak. Comparable levels of oak lactone glycoconjugates and oak volatiles were observed, demonstrating the aroma potential of reclaimed oak and therefore its suitability as a raw material for alternative oak products, i.e., chips or battens, for the maturation of wine. The temperature profiles achieved during toasting were also measured to evaluate the viability of any yeast or bacteria present in reclaimed oak. PMID:25771908

  14. Evaluating alternatives for decommissioning California's offshore oil and gas platforms.

    PubMed

    Bernstein, Brock B

    2015-10-01

    This paper introduces a series of 6 additional papers in this issue that describe an in-depth analysis of options for decommissioning oil and gas platforms offshore southern California. Although current leases require lessees in both state and federal waters to completely remove all production facilities and restore the seafloor to its pre-platform condition, other options have emerged since these leases were signed. Laws and regulations in other jurisdictions (particularly in federal waters) have evolved to allow a number of other uses such as aquaculture, alternative energy production, and artificial reefing. In response, the California Natural Resources Agency initiated an effort to investigate the issues associated with these and other decommissioning alternatives. The papers in this series are the result of the second phase in this process, a broad investigation of the engineering, economic, and environmental costs and benefits of the most feasible and likely options. In addition to the project's final report, the authors produced an interactive mathematical decision model, PLATFORM, that enables users to explore the implications of different decommissioning projects and options, as well as the effects of different approaches to valuing the associated costs and benefits.

  15. Decontamination and decommissioning surveillance and maintenance report for FY 1991

    SciTech Connect

    Gunter, David B.; Burwinkle, T. W.; Cannon, T. R.; Ford, M. K.; Holder, Jr., L.; Clotfelter, O. K.; Faulkner, R. L.; Smith, D. L.; Wooten, H. O.

    1991-12-01

    The Decontamination and Decommissioning (D D) Program has three distinct phases: (1) surveillance and maintenance (S M); (2) decontamination and removal of hazardous materials and equipment (which DOE Headquarters in Washington, D.C., calls Phase I of remediation); and (3) decommissioning and ultimate disposal, regulatory compliance monitoring, and property transfer (which DOE Headquarters calls Phase II of remediation). A large part of D D is devoted to S M at each of the sites. Our S M activities, which are performed on facilities awaiting decommissioning, are designed to minimize potential hazards to human health and the environment by: ensuring adequate containment of residual radioactive and hazardous materials; and, providing physical safety and security controls to minimize potential hazards to on-site personnel and the general public. Typically, we classify maintenance activities as either routine or special (major repairs). Routine maintenance includes such activities as painting, cleaning, vegetation control, minor structural repairs, filter changes, and building system(s) checks. Special maintenance includes Occupational Safety and Health Act facility upgrades, roof repairs, and equipment overhaul. Surveillance activities include inspections, radiological measurements, reporting, records maintenance, and security (as required) for controlling and monitoring access to facilities. This report summarizes out FY 1991 S M activities for the Tennessee plant sites, which include the K-25 Site, the Gas Centrifuge facilities, ORNL, and the Y-12 Plant.

  16. Practitioner versus analyst methods: a nuclear decommissioning case study.

    PubMed

    Walker, Guy; Cooper, Mhairi; Thompson, Pauline; Jenkins, Dan

    2014-11-01

    A requirement arose during decommissioning work at a UK Magnox Nuclear Power Station to identify the hazards involved in removing High Dose Rate Items from a Cartridge Cooling Pond. Removing objects from the cooling pond under normal situations is a routine event with well understood risks but the situation described in this paper is not a routine event. The power station has shifted from an operational phase in its life-cycle to a decommissioning phase, and as such the risks, and procedures to deal with them, have become more novel and uncertain. This raises an important question. Are the hazard identification methods that have proven useful in one phase of the system lifecycle just as useful in another, and if not, what methods should be used? An opportunity arose at this site to put the issue to a direct test. Two methods were used, one practitioner focussed and in widespread use during the plant's operational phase (the Structured What-If method), the other was an analyst method (Cognitive Work Analysis). The former is proven on this site but might not be best suited to the novelty and uncertainty brought about by a shift in context from operations to decommissioning. The latter is not proven on this site but it is designed for novelty and uncertainty. The paper presents the outcomes of applying both methods to a real-world hazard identification task. PMID:24947001

  17. A NOVEL APPROACH TO SPENT FUEL POOL DECOMMISSIONING

    SciTech Connect

    R. L. Demmer

    2011-04-01

    The Idaho National Laboratory (INL) has been at the forefront of developing methods to reduce the cost and schedule of deactivating spent fuel pools (SFP). Several pools have been deactivated at the INL using an underwater approach with divers. These projects provided a basis for the INL cooperation with the Dresden Nuclear Power Station Unit 1 SFP (Exelon Generation Company) deactivation. It represents the first time that a commercial nuclear power plant (NPP) SFP was decommissioned using this underwater coating process. This approach has advantages in many aspects, particularly in reducing airborne contamination and allowing safer, more cost effective deactivation. The INL pioneered underwater coating process was used to decommission three SFPs with a total combined pool volume of over 900,000 gallons. INL provided engineering support and shared project plans to successfully initiate the Dresden project. This report outlines the steps taken by INL and Exelon to decommission SFPs using the underwater coating process. The rationale used to select the underwater coating process and the advantages and disadvantages are described. Special circumstances are also discussed, such as the use of a remotely-operated underwater vehicle to visually and radiologically map the pool areas that were not readily accessible. A larger project, the INTEC-603 SFP in-situ (grouting) deactivation, is reviewed. Several specific areas where special equipment was employed are discussed and a Lessons Learned evaluation is included.

  18. Evaluating alternatives for decommissioning California's offshore oil and gas platforms.

    PubMed

    Bernstein, Brock B

    2015-10-01

    This paper introduces a series of 6 additional papers in this issue that describe an in-depth analysis of options for decommissioning oil and gas platforms offshore southern California. Although current leases require lessees in both state and federal waters to completely remove all production facilities and restore the seafloor to its pre-platform condition, other options have emerged since these leases were signed. Laws and regulations in other jurisdictions (particularly in federal waters) have evolved to allow a number of other uses such as aquaculture, alternative energy production, and artificial reefing. In response, the California Natural Resources Agency initiated an effort to investigate the issues associated with these and other decommissioning alternatives. The papers in this series are the result of the second phase in this process, a broad investigation of the engineering, economic, and environmental costs and benefits of the most feasible and likely options. In addition to the project's final report, the authors produced an interactive mathematical decision model, PLATFORM, that enables users to explore the implications of different decommissioning projects and options, as well as the effects of different approaches to valuing the associated costs and benefits. PMID:25914401

  19. Technology, safety and costs of decommissioning a reference boiling water reactor power station. Appendices. Volume 2

    SciTech Connect

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Appendices are presented concerning the evaluations of decommissioning financing alternatives; reference site description; reference BWR facility description; radiation dose rate and concrete surface contamination data; radionuclide inventories; public radiation dose models and calculated maximum annual doses; decommissioning methods; generic decommissioning information; immediate dismantlement details; passive safe storage, continuing care, and deferred dismantlement details; entombment details; demolition and site restoration details; cost estimating bases; public radiological safety assessment details; and details of alternate study bases.

  20. Technology, safety and costs of decommissioning a reference boiling water reactor power station. Classification of decommissioning wastes. Addendum 2

    SciTech Connect

    Murphy, E.S.

    1984-09-01

    The radioactive wastes expected to result from decommissioning of the reference boiling water reactor power station are reviewed and classified in accordance with 10 CFR 61. The 18,949 cubic meters of waste from DECON are classified as follows: Class A, 97.5%; Class B, 2.0%; Class C, 0.3%. About 0.2% (47 cubic meters) of the waste would be generally unacceptable for disposal using near-surface disposal methods.

  1. Technology, safety and costs of decommissioning a reference pressurized water reactor power station. Classification of decommissioning wastes. Addendum 3

    SciTech Connect

    Murphy, E.S.

    1984-09-01

    The radioactive wastes expected to result from decommissioning of the reference pressurized water reactor power station are reviewed and classified in accordance with 10 CFR 61. The 17,885 cubic meters of waste from DECON are classified as follows: Class A, 98.0%; Class B, 1.2%; Class C, 0.1%. About 0.7% (133 cubic meters) of the waste would be generally unacceptable for disposal using near-surface disposal methods.

  2. Role of decommissioning plan and its progress for the PUSPATI TRIGA Reactor

    SciTech Connect

    Zakaria, Norasalwa Mustafa, Muhammad Khairul Ariff Anuar, Abul Adli Idris, Hairul Nizam Ba'an, Rohyiza

    2014-02-12

    Malaysian nuclear research reactor, the PUSPATI TRIGA Reactor, reached its first criticality in 1982, and since then, it has been serving for more than 30 years for training, radioisotope production and research purposes. Realizing the age and the need for its decommissioning sometime in the future, a ground basis of assessment and an elaborative project management need to be established, covering the entire process from termination of reactor operation to the establishment of final status, documented as the Decommissioning Plan. At international level, IAEA recognizes the absence of Decommissioning Plan as one of the factors hampering progress in decommissioning of nuclear facilities in the world. Throughout the years, IAEA has taken initiatives and drawn out projects in promoting progress in decommissioning programmes, like CIDER, DACCORD and R2D2P, for which Malaysia is participating in these projects. This paper highlights the concept of Decommissioning plan and its significances to the Agency. It will also address the progress, way forward and challenges faced in developing the Decommissioning Plan for the PUSPATI TRIGA Reactor. The efforts in the establishment of this plan helps to provide continual national contribution at the international level, as well as meeting the regulatory requirement, if need be. The existing license for the operation of PUSPATI TRIGA Reactor does not impose a requirement for a decommissioning plan; however, the renewal of license may call for a decommissioning plan to be submitted for approval in future.

  3. Role of decommissioning plan and its progress for the PUSPATI TRIGA Reactor

    NASA Astrophysics Data System (ADS)

    Zakaria, Norasalwa; Mustafa, Muhammad Khairul Ariff; Anuar, Abul Adli; Idris, Hairul Nizam; Ba'an, Rohyiza

    2014-02-01

    Malaysian nuclear research reactor, the PUSPATI TRIGA Reactor, reached its first criticality in 1982, and since then, it has been serving for more than 30 years for training, radioisotope production and research purposes. Realizing the age and the need for its decommissioning sometime in the future, a ground basis of assessment and an elaborative project management need to be established, covering the entire process from termination of reactor operation to the establishment of final status, documented as the Decommissioning Plan. At international level, IAEA recognizes the absence of Decommissioning Plan as one of the factors hampering progress in decommissioning of nuclear facilities in the world. Throughout the years, IAEA has taken initiatives and drawn out projects in promoting progress in decommissioning programmes, like CIDER, DACCORD and R2D2P, for which Malaysia is participating in these projects. This paper highlights the concept of Decommissioning plan and its significances to the Agency. It will also address the progress, way forward and challenges faced in developing the Decommissioning Plan for the PUSPATI TRIGA Reactor. The efforts in the establishment of this plan helps to provide continual national contribution at the international level, as well as meeting the regulatory requirement, if need be. The existing license for the operation of PUSPATI TRIGA Reactor does not impose a requirement for a decommissioning plan; however, the renewal of license may call for a decommissioning plan to be submitted for approval in future.

  4. Evaluation of nuclear facility decommissioning projects: summary report. Plum Brook Reactor Facility

    SciTech Connect

    Doerge, D.H.; Miller, R.L.

    1984-02-01

    This document summarizes information concerning the decommissioning of the Plum Brook Reactor Facility, which was placed in a Nuclear Regulatory Commission (NRC) approved safe storage configuration. The data were placed in a computerized information retrieval/manipulation system which permits future utilization of this information in decommissioning of similar facilities. The information is presented both in computer output form and a manually assembled summarization. Complete cost data were not readily available and decommissioning activities did not in all cases conform with current criteria for the SAFSTOR decommissioning mode, therefore no cost comparisons were made.

  5. Proceedings of the 2007 ANS Topical Meeting on Decommissioning, Decontamination, and Reutilization - DD and R 2007

    SciTech Connect

    2008-01-15

    The American Nuclear Society (ANS) Topical Meeting on Decommissioning, Decontamination, and Reutilization (DD and R 2007), 'Capturing Decommissioning Lessons Learned', is sponsored by the ANS Decommissioning, Decontamination and Reutilization; Environmental Sciences; and Fuel Cycle and Waste Management Divisions. This meeting provides a forum for an international exchange of technical knowledge and project management experience gained from the ongoing process of decommissioning nuclear facilities. Of particular note is the number of projects that are approaching completion. This document gathers 113 presentations given at this meeting.

  6. A Plutonium Finishing Plant Model for the Cercla Removal Action and Decommissioning Construction Final Report

    SciTech Connect

    Hopkins, A.

    2008-07-01

    The joint policy between the U.S. Environmental Protection Agency (EPA) and the U.S. Department of Energy (DOE) for decommissioning buildings at DOE facilities documents an agreement between the agencies to perform decommissioning activities including demolition under the Comprehensive Environmental Response Compensation and Liability Act (CERCLA). The use of removal actions for decommissioning integrates EPA oversight authority, DOE lead agency responsibility, and state authority for decommissioning activities. Once removal actions have been performed under CERCLA, a construction completion report is required to document the completion of the required action. Additionally, a decommissioning report is required under DOE guidance. No direct guidance was found for documenting completion of decommissioning activities and preparing a final report that satisfies the CERCLA requirements and the DOE requirements for decommissioning. Additional guidance was needed for the documentation of construction completion under CERCLA for D and D projects undertaken under the joint policy that addresses the requirements of both agencies. A model for the construction completion report was developed to document construction completion for CERCLA D and D activities performed under the joint EPA/DOE policy at the Plutonium Finishing Plant (PFP). The model documentation report developed at PFP integrates the DOE requirements for establishing decommissioning end-points, documenting end-point completion and preparing a final decommissioning report with the CERCLA requirements to document completion of the action identified in the Action Memorandum (AM). The model includes the required information on health and safety, data management, cost and schedule and end-points completion. (authors)

  7. Lomonosov In Spring

    NASA Technical Reports Server (NTRS)

    2004-01-01

    26 September 2004 This blue wide angle Mars Global Surveyor (MGS) Mars Orbiter Camera (MOC) image shows the frost-covered rims of Lomonosov Crater in late martian spring. At the north (top) end of the image, low, ground-hugging fog can be seen in association with the retreating seasonal polar cap. Lomonosov Crater is about 150 km (93 mi) in diameter and located at 65oN, 9oW. The image is illuminated by sunlight from the lower left.

  8. Technology, safety, and costs of decommissioning reference nuclear research and test reactors: sensitivity of decommissioning radiation exposure and costs to selected parameters

    SciTech Connect

    Konzek, G.J.

    1983-07-01

    Additional analyses of decommissioning at the reference research and test (R and T) reactors and analyses of five recent reactor decommissionings are made that examine some parameters not covered in the initial study report (NUREG/CR-1756). The parameters examined for decommissioning are: (1) the effect on costs and radiation exposure of plant size and/or type; (2) the effects on costs of increasing disposal charges and of unavailability of waste disposal capacity at licensed waste disposal facilities; and (3) the costs of and the available alternatives for the disposal of nuclear R and T reactor fuel assemblies.

  9. Facility Decontamination and Decommissioning Program Surveillance and Maintenance Plan, Revision 2

    SciTech Connect

    Poderis, Reed J.; King, Rebecca A.

    2013-09-30

    This Surveillance and Maintenance (S&M) Plan describes the activities performed between deactivation and final decommissioning of the following facilities located on the Nevada National Security Site, as documented in the Federal Facility Agreement and Consent Order under the Industrial Sites program as decontamination and decommissioning sites: ? Engine Maintenance, Assembly, and Disassembly (EMAD) Facility: o EMAD Building (Building 25-3900) o Locomotive Storage Shed (Building 25-3901) ? Test Cell C (TCC) Facility: o Equipment Building (Building 25-3220) o Motor Drive Building (Building 25-3230) o Pump Shop (Building 25-3231) o Cryogenic Lab (Building 25-3232) o Ancillary Structures (e.g., dewars, water tower, piping, tanks) These facilities have been declared excess and are in various stages of deactivation (low-risk, long-term stewardship disposition state). This S&M Plan establishes and implements a solid, cost-effective, and balanced S&M program consistent with federal, state, and regulatory requirements. A graded approach is used to plan and conduct S&M activities. The goal is to maintain the facilities in a safe condition in a cost-effective manner until their final end state is achieved. This plan accomplishes the following: ? Establishes S&M objectives and framework ? Identifies programmatic guidance for S&M activities to be conducted by National Security Technologies, LLC, for the U.S. Department of Energy, National Nuclear Security Administration Nevada Field Office (NNSA/NFO) ? Provides present facility condition information and identifies hazards ? Identifies facility-specific S&M activities to be performed and their frequency ? Identifies regulatory drivers, NNSA/NFO policies and procedures, and best management practices that necessitate implementation of S&M activities ? Provides criteria and frequencies for revisions and updates ? Establishes the process for identifying and dispositioning a condition that has not been previously identified or

  10. Demobilization of the World's Largest Decontamination and Decommissioning Project Project Closeout of three Gaseous Diffusion Plants for Re-industrialization

    SciTech Connect

    Stevens, J.L.; Miller, JA.

    2006-07-01

    This paper describes the challenges and lessons learned from the demobilization of the world' largest, and first, successfully decontaminated and decommissioned project. These gaseous diffusion plants are the first plants to be successfully decommissioned in the United States. (authors)

  11. Southern Mars: It's Spring!

    NASA Technical Reports Server (NTRS)

    1999-01-01

    August 2, 1999, marks the spring equinox for the martian southern hemisphere. It is also the start of autumn for regions north of the equator. Winter in the south has finally come to a close, and the seasonal frosts of the wintertime south polar cap are retreating. Small, local dust storms frequently occur along the margins of the polar cap, as the colder air blowing off the cap moves northward into warmer regions.

    The wide angle camera view of Mars shown here was obtained by the Mars Global Surveyor Mars Orbiter Camera in late July 1999, about 1 week before the start of southern spring. The frosty, retreating south polar cap (white) is seen in the lower quarter of the image, and wisps of dust storm clouds (grayish-orange in this view) occur just above the cap at the lower left. The southern most of the large environmental changes volcanoes, Arsia Mons, is seen at the upper left. Arsia Mons is about 350 kilometers(220 miles) across.

    Malin Space Science Systems and the California Institute of Technology built the MOC using spare hardware from the Mars Observer mission. MSSS operates the camera from its facilities in San Diego, CA. The Jet Propulsion Laboratory's Mars Surveyor Operations Project operates the Mars Global Surveyor spacecraft with its industrial partner, Lockheed Martin Astronautics, from facilities in Pasadena, CA and Denver, CO.

  12. Heavy Water Components Test Reactor Decommissioning - Major Component Removal

    SciTech Connect

    Austin, W.; Brinkley, D.

    2010-05-05

    The Heavy Water Components Test Reactor (HWCTR) facility (Figure 1) was built in 1961, operated from 1962 to 1964, and is located in the northwest quadrant of the Savannah River Site (SRS) approximately three miles from the site boundary. The HWCTR facility is on high, well-drained ground, about 30 meters above the water table. The HWCTR was a pressurized heavy water test reactor used to develop candidate fuel designs for heavy water power reactors. It was not a defense-related facility like the materials production reactors at SRS. The reactor was moderated with heavy water and was rated at 50 megawatts thermal power. In December of 1964, operations were terminated and the facility was placed in a standby condition as a result of the decision by the U.S. Atomic Energy Commission to redirect research and development work on heavy water power reactors to reactors cooled with organic materials. For about one year, site personnel maintained the facility in a standby status, and then retired the reactor in place. In 1965, fuel assemblies were removed, systems that contained heavy water were drained, fluid piping systems were drained, deenergized and disconnected and the spent fuel basin was drained and dried. The doors of the reactor facility were shut and it wasn't until 10 years later that decommissioning plans were considered and ultimately postponed due to budget constraints. In the early 1990s, DOE began planning to decommission HWCTR again. Yet, in the face of new budget constraints, DOE deferred dismantlement and placed HWCTR in an extended surveillance and maintenance mode. The doors of the reactor facility were welded shut to protect workers and discourage intruders. The $1.6 billion allocation from the American Recovery and Reinvestment Act to SRS for site clean up at SRS has opened the doors to the HWCTR again - this time for final decommissioning. During the lifetime of HWCTR, 36 different fuel assemblies were tested in the facility. Ten of these

  13. 30 CFR 585.907 - How will BOEM process my decommissioning application?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... decommissioning application with the decommissioning general concept in your approved SAP, COP, or GAP to determine what technical and environmental reviews are needed. (b) You will likely have to revise your SAP... change in the impacts previously identified and evaluated in your SAP, COP, or GAP; (2) Require...

  14. 30 CFR 585.907 - How will BOEM process my decommissioning application?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... Environmental and Safety Management, Inspections, and Facility Assessments for Activities Conducted Under SAPs... your decommissioning application with the decommissioning general concept in your approved SAP, COP, or... revise your SAP, COP, or GAP, and BOEM will begin the appropriate NEPA analysis and other...

  15. 30 CFR 285.907 - How will MMS process my decommissioning application?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... decommissioning application with the decommissioning general concept in your approved SAP, COP, or GAP to determine what technical and environmental reviews are needed. (b) You will likely have to revise your SAP... the impacts previously identified and evaluated in your SAP, COP, or GAP; (2) Require any...

  16. 30 CFR 585.907 - How will BOEM process my decommissioning application?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... decommissioning application with the decommissioning general concept in your approved SAP, COP, or GAP to determine what technical and environmental reviews are needed. (b) You will likely have to revise your SAP... change in the impacts previously identified and evaluated in your SAP, COP, or GAP; (2) Require...

  17. 30 CFR 285.907 - How will MMS process my decommissioning application?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... compare your decommissioning application with the decommissioning general concept in your approved SAP... to revise your SAP, COP, or GAP, and MMS will begin the appropriate NEPA analysis and other... a significant change in the impacts previously identified and evaluated in your SAP, COP, or GAP;...

  18. 78 FR 49603 - Gulf Gateway Deepwater Port Decommissioning and License Termination

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-08-14

    ... completed the final decommissioning process on March 14, 2013. At the end of the decommissioning process... termination of the Gulf Gateway Deepwater Port License (License), effective as of June 28, 2013. Pursuant to... licensee. For purposes of this agency action, MARAD has granted as of June 28, 2013, final clearance of...

  19. 30 CFR 585.903 - What are the requirements for decommissioning FERC-licensed hydrokinetic facilities?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 30 Mineral Resources 2 2013-07-01 2013-07-01 false What are the requirements for decommissioning FERC-licensed hydrokinetic facilities? 585.903 Section 585.903 Mineral Resources BUREAU OF OCEAN ENERGY... What are the requirements for decommissioning FERC-licensed hydrokinetic facilities? You must...

  20. 30 CFR 585.903 - What are the requirements for decommissioning FERC-licensed hydrokinetic facilities?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 30 Mineral Resources 2 2014-07-01 2014-07-01 false What are the requirements for decommissioning FERC-licensed hydrokinetic facilities? 585.903 Section 585.903 Mineral Resources BUREAU OF OCEAN ENERGY... What are the requirements for decommissioning FERC-licensed hydrokinetic facilities? You must...

  1. 30 CFR 285.903 - What are the requirements for decommissioning FERC-licensed hydrokinetic facilities?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 30 Mineral Resources 2 2011-07-01 2011-07-01 false What are the requirements for decommissioning FERC-licensed hydrokinetic facilities? 285.903 Section 285.903 Mineral Resources BUREAU OF OCEAN ENERGY... Requirements § 285.903 What are the requirements for decommissioning FERC-licensed hydrokinetic facilities?...

  2. 30 CFR 285.903 - What are the requirements for decommissioning FERC-licensed hydrokinetic facilities?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 30 Mineral Resources 2 2010-07-01 2010-07-01 false What are the requirements for decommissioning FERC-licensed hydrokinetic facilities? 285.903 Section 285.903 Mineral Resources MINERALS MANAGEMENT... the requirements for decommissioning FERC-licensed hydrokinetic facilities? You must comply with...

  3. 30 CFR 585.903 - What are the requirements for decommissioning FERC-licensed hydrokinetic facilities?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 30 Mineral Resources 2 2012-07-01 2012-07-01 false What are the requirements for decommissioning FERC-licensed hydrokinetic facilities? 585.903 Section 585.903 Mineral Resources BUREAU OF OCEAN ENERGY....903 What are the requirements for decommissioning FERC-licensed hydrokinetic facilities? You...

  4. 76 FR 65541 - Assuring the Availability of Funds for Decommissioning Nuclear Reactors

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-10-21

    ... COMMISSION Assuring the Availability of Funds for Decommissioning Nuclear Reactors AGENCY: Nuclear Regulatory... Decommissioning Nuclear Reactors.'' This guide provides guidance to applicants and licensees of nuclear power, research, and test reactors concerning methods acceptable to the staff of the U.S. Nuclear...

  5. 30 CFR 585.908 - What must I include in my decommissioning notice?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... notice? 585.908 Section 585.908 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF..., COPs and GAPs Decommissioning Applications § 585.908 What must I include in my decommissioning...

  6. 30 CFR 585.905 - When must I submit my decommissioning application?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... application? 585.905 Section 585.905 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF..., COPs and GAPs Decommissioning Applications § 585.905 When must I submit my decommissioning...

  7. 30 CFR 285.908 - What must I include in my decommissioning notice?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... notice? 285.908 Section 285.908 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, REGULATION, AND ENFORCEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF Decommissioning Decommissioning Applications § 285.908 What must I include in...

  8. 30 CFR 285.905 - When must I submit my decommissioning application?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... application? 285.905 Section 285.905 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, REGULATION, AND ENFORCEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF Decommissioning Decommissioning Applications § 285.905 When must I submit...

  9. 30 CFR 250.1703 - What are the general requirements for decommissioning?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 30 Mineral Resources 2 2011-07-01 2011-07-01 false What are the general requirements for decommissioning? 250.1703 Section 250.1703 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, REGULATION, AND... appropriate District Manager before decommissioning wells and from the Regional Supervisor...

  10. Is Entombment an Acceptable Option for Decommissioning? An International Perspective - 13488

    SciTech Connect

    Belencan, Helen; Nys, Vincent; Guskov, Andrey; Francois, Patrice; Watson, Bruce; Ljubenov, Vladan

    2013-07-01

    Selection of a decommissioning strategy is one of the key steps in the preparation for decommissioning of nuclear facilities and other facilities using radioactive material. Approaches being implemented or considered by Member States include immediate dismantling, deferred dismantling and entombment. Other options or slight modifications of these strategies are also possible. Entombment has been identified in the current International Atomic Energy Agency (IAEA) Safety Standards as one of the three basic decommissioning strategies and has been defined as a decommissioning strategy by which radioactive contaminants are encased in a structurally long lived material until radioactivity decays to a level permitting the unrestricted release of the facility, or release with restrictions imposed by the regulatory body. Although all three strategies have been considered, in principle, applicable to all facilities, their application to some facilities may not be appropriate owing to political concerns, safety or environmental requirements, technical considerations, local conditions or financial considerations. The IAEA is currently revising the decommissioning Safety Standards and one of the issues widely discussed has been the applicability of entombment in the context of decommissioning and its general objective to enable removal of regulatory control from the decommissioned facility. The IAEA recently established a consultancy to collect and discuss experience and lessons learned from entombment projects, to identify regulatory requirements and expectations for applying entombment as a decommissioning option strategy, in compliance with the internationally agreed standards. (authors)

  11. 30 CFR 250.1703 - What are the general requirements for decommissioning?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ..., DEPARTMENT OF THE INTERIOR OFFSHORE OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF... facilities are no longer useful for operations, you must: (a) Get approval from the appropriate District Manager before decommissioning wells and from the Regional Supervisor before decommissioning platforms...

  12. 75 FR 72737 - Proposed Generic Communications Reporting for Decommissioning Funding Status Reports

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-11-26

    ... Funding Status Reports AGENCY: Nuclear Regulatory Commission. ACTION: Notice of opportunity for public... present to the NRC in the Decommissioning Funding Status (DFS) reports to ensure that the NRC staff... INFORMATION: NRC Regulatory Issue Summary 2010-XXX 10 CFR 50.75 Reporting for Decommissioning Funding...

  13. 26 CFR 1.468A-0 - Nuclear decommissioning costs; table of contents.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 26 Internal Revenue 6 2014-04-01 2014-04-01 false Nuclear decommissioning costs; table of contents...-0 Nuclear decommissioning costs; table of contents. This section lists the paragraphs contained in.... (b) Definitions. (c) Special rules applicable to certain experimental nuclear facilities. §...

  14. 26 CFR 1.468A-0 - Nuclear decommissioning costs; table of contents.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 26 Internal Revenue 6 2012-04-01 2012-04-01 false Nuclear decommissioning costs; table of contents...-0 Nuclear decommissioning costs; table of contents. This section lists the paragraphs contained in.... (b) Definitions. (c) Special rules applicable to certain experimental nuclear facilities. §...

  15. 26 CFR 1.468A-0 - Nuclear decommissioning costs; table of contents.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 26 Internal Revenue 6 2011-04-01 2011-04-01 false Nuclear decommissioning costs; table of contents...-0 Nuclear decommissioning costs; table of contents. This section lists the paragraphs contained in.... (b) Definitions. (c) Special rules applicable to certain experimental nuclear facilities. §...

  16. 26 CFR 1.468A-0 - Nuclear decommissioning costs; table of contents.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 26 Internal Revenue 6 2013-04-01 2013-04-01 false Nuclear decommissioning costs; table of contents...-0 Nuclear decommissioning costs; table of contents. This section lists the paragraphs contained in.... (b) Definitions. (c) Special rules applicable to certain experimental nuclear facilities. §...

  17. Environmental restoration and decontamination & decommissioning safety documentation. Revision 2

    SciTech Connect

    Hansen, J.L.; Frauenholz, L.H.; Kerr, N.R.

    1993-05-18

    This document presents recommendations of a working group designated by the Environmental Restoration and Remediation (ER) and Decontamination and Decommissioning (D&D) subcommittees of the Westinghouse M&O (Management and Operation) Nuclear Facility Safety Committee. A commonalty of approach to safety documentation specific to ER and D&D activities was developed and is summarized below. Allowance for interpretative tolerance and documentation flexibility appropriate to the activity, graded for hazard category, duration, and complexity, was a primary consideration in development of this guidance.

  18. SAVANNAH RIVER SITE R REACTOR DISASSEMBLY BASIN IN SITU DECOMMISSIONING

    SciTech Connect

    Langton, C.; Blankenship, J.; Griffin, W.; Serrato, M.

    2009-12-03

    The US DOE concept for facility in-situ decommissioning (ISD) is to physically stabilize and isolate in tact, structurally sound facilities that are no longer needed for their original purpose of, i.e., generating (reactor facilities), processing(isotope separation facilities) or storing radioactive materials. The 105-R Disassembly Basin is the first SRS reactor facility to undergo the in-situ decommissioning (ISD) process. This ISD process complies with the105-R Disassembly Basin project strategy as outlined in the Engineering Evaluation/Cost Analysis for the Grouting of the R-Reactor Disassembly Basin at the Savannah River Site and includes: (1) Managing residual water by solidification in-place or evaporation at another facility; (2) Filling the below grade portion of the basin with cementitious materials to physically stabilize the basin and prevent collapse of the final cap - Sludge and debris in the bottom few feet of the basin will be encapsulated between the basin floor and overlying fill material to isolate if from the environment; (3) Demolishing the above grade portion of the structure and relocating the resulting debris to another location or disposing of the debris in-place; and (4) Capping the basin area with a concrete slab which is part of an engineered cap to prevent inadvertent intrusion. The estimated total grout volume to fill the 105-R Reactor Disassembly Basin is 24,424 cubic meters or 31,945 cubic yards. Portland cement-based structural fill materials were design and tested for the reactor ISD project and a placement strategy for stabilizing the basin was developed. Based on structural engineering analyses and work flow considerations, the recommended maximum lift height is 5 feet with 24 hours between lifts. Pertinent data and information related to the SRS 105-R-Reactor Disassembly Basin in-situ decommissioning include: regulatory documentation, residual water management, area preparation activities, technology needs, fill material designs

  19. Remote machine engineering applications for nuclear facilities decommissioning

    SciTech Connect

    Toto, G.; Wyle, H.R.

    1983-01-01

    Decontamination and decommissioning of a nuclear facility require the application of techniques that protect the worker and the enviroment from radiological contamination and radiation. Remotely operated portable robotic arms, machines, and devices can be applied. The use of advanced systems should enhance the productivity, safety, and cost facets of the efforts; remote automatic tooling and systems may be used on any job where job hazard and other factors justify application. Many problems based on costs, enviromental impact, health, waste generation, and political issues may be mitigated by use of remotely operated machines. The work that man can not do or should not do will have to be done by machines.

  20. Decommissioning Cost Estimating Factors And Earned Value Integration

    SciTech Connect

    Sanford, P.C.; Cimmarron, E.

    2008-07-01

    The Rocky Flats 771 Project progressed from the planning stage of decommissioning a plutonium facility, through the strip-out of highly-contaminated equipment, removal of utilities and structural decontamination, and building demolition. Actual cost data was collected from the strip-out activities and compared to original estimates, allowing the development of cost by equipment groupings and types and over time. Separate data was developed from the project control earned value reporting and compared with the equipment data. The paper discusses the analysis to develop the detailed factors for the different equipment types, and the items that need to be considered during characterization of a similar facility when preparing an estimate. The factors are presented based on direct labor requirements by equipment type. The paper also includes actual support costs, and examples of fixed or one-time start-up costs. The integration of the estimate and the earned value system used for the 771 Project is also discussed. The paper covers the development of the earned value system as well as its application to a facility to be decommissioned and an existing work breakdown structure. Lessons learned are provided, including integration with scheduling and craft supervision, measurement approaches, and verification of scope completion. In summary: The work of decommissioning the Rocky Flats 771 Project process equipment was completed in 2003. Early in the planning process, we had difficulty in identifying credible data and implementing processes for estimating and controlling this work. As the project progressed, we were able to collect actual data on the costs of removing plutonium contaminated equipment from various areas over the life of this work and associate those costs with individual pieces of equipment. We also were able to develop and test out a system for measuring the earned value of a decommissioning project based on an evolving estimate. These were elements that

  1. Waste management for Shippingport Station Decommissioning Project: Extended summary

    SciTech Connect

    Mullee, G.R.; Schulmeister, A.R.

    1987-01-01

    The Shippingport Station (SSDP) is demonstrating that the techniques and methodologies of waste management, which are currently employed by the nuclear industry, provide adequate management and control of waste activities for the decommissioning of a large scale nuclear plant. The SSDP has some unique aspects in that as part of the objective to promote technology transfer, multiple subcontractors are being utilized in the project. The interfaces resulting from multiple subcontractors require additional controls. Effective control has been accomplished by the use of a process control and inventory system, coupled with personnel training in waste management activities. This report summarizes the waste management plan and provides a status of waste management activities for SSDP.

  2. Tools for decontamination and decommissioning of nuclear facilities

    SciTech Connect

    Hermetz, R.E.

    1986-01-01

    The decontamination and decommissioning (D and D) of nuclear facilities requires many different tools. These can vary from small hand tools to the heavy equipment used to remove concrete and soil. Tools for D and D should be reliable, versatile, economical, and easily disposed of in case they become contaminated. The experiences and information used as background for this paper where gained at the Mound Facility of the Monsanto Research Corporation in Miamisburg, Ohio. In the search to find tools to do the work proficiently, many tools were considered. The scheduled D and D tasks and the tools and equipment required for them are described.

  3. 30 CFR 585.902 - What are the general requirements for decommissioning for facilities authorized under my SAP, COP...

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... decommissioning for facilities authorized under my SAP, COP, or GAP? 585.902 Section 585.902 Mineral Resources... authorized under my SAP, COP, or GAP? (a) Except as otherwise authorized by BOEM under § 585.909, within 2... decommissioning the facilities under your SAP, COP, or GAP, you must submit a decommissioning application...

  4. 30 CFR 585.902 - What are the general requirements for decommissioning for facilities authorized under my SAP, COP...

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... decommissioning for facilities authorized under my SAP, COP, or GAP? 585.902 Section 585.902 Mineral Resources... authorized under my SAP, COP, or GAP? (a) Except as otherwise authorized by BOEM under § 585.909, within 2... decommissioning the facilities under your SAP, COP, or GAP, you must submit a decommissioning application...

  5. 10 CFR 30.36 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E. The licensee shall, as... are suitable for release in accordance with the criteria for decommissioning in 10 CFR part 20... premises are suitable for release in accordance with the criteria for decommissioning in 10 CFR part...

  6. 10 CFR 30.36 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E. The licensee shall, as... are suitable for release in accordance with the criteria for decommissioning in 10 CFR part 20... premises are suitable for release in accordance with the criteria for decommissioning in 10 CFR part...

  7. 10 CFR 30.36 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E. The licensee shall, as... are suitable for release in accordance with the criteria for decommissioning in 10 CFR part 20... premises are suitable for release in accordance with the criteria for decommissioning in 10 CFR part...

  8. 10 CFR 30.36 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E. The licensee shall, as... are suitable for release in accordance with the criteria for decommissioning in 10 CFR part 20... premises are suitable for release in accordance with the criteria for decommissioning in 10 CFR part...

  9. 10 CFR 30.36 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E. The licensee shall, as... are suitable for release in accordance with the criteria for decommissioning in 10 CFR part 20... premises are suitable for release in accordance with the criteria for decommissioning in 10 CFR part...

  10. 30 CFR 585.913 - What happens if I fail to comply with my approved decommissioning application?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... approved decommissioning application? 585.913 Section 585.913 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF Decommissioning Compliance with An Approved Decommissioning...

  11. 30 CFR 585.913 - What happens if I fail to comply with my approved decommissioning application?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... approved decommissioning application? 585.913 Section 585.913 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF Decommissioning Compliance with An Approved Decommissioning...

  12. 30 CFR 285.913 - What happens if I fail to comply with my approved decommissioning application?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... approved decommissioning application? 285.913 Section 285.913 Mineral Resources MINERALS MANAGEMENT SERVICE, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF Decommissioning Compliance with An Approved Decommissioning Application § 285.913...

  13. Spring loaded thermocouple module

    DOEpatents

    McKelvey, T.E.; Guarnieri, J.J.

    1984-03-13

    A thermocouple arrangement is provided for mounting in a blind hole of a specimen. The thermocouple arrangement includes a cup-like holder member, which receives an elongated thermal insulator, one end of which is seated at an end wall of the holder. A pair of thermocouple wires, threaded through passageways in the insulator, extend beyond the insulator member, terminating in free ends which are joined together in a spherical weld bead. A spring, held captive within the holder, applies a bias force to the weld bead, through the insulator member. The outside surface of the holder is threaded for engagement with the blind hole of the specimen. When the thermocouple is installed in the specimen, the spherical contact surface of the weld bead is held in contact with the end wall of the blind hole, with a predetermined bias force.

  14. Spring loaded thermocouple module

    DOEpatents

    McKelvey, Thomas E.; Guarnieri, Joseph J.

    1985-01-01

    A thermocouple arrangement is provided for mounting in a blind hole of a specimen. The thermocouple arrangement includes a cup-like holder member, which receives an elongated thermal insulator, one end of which is seated at an end wall of the holder. A pair of thermocouple wires, threaded through passageways in the insulator, extend beyond the insulator member, terminating in free ends which are joined together in a spherical weld bead. A spring, held captive within the holder, applies a bias force to the weld bead, through the insulator member. The outside surface of the holder is threaded for engagement with the blind hole of the specimen. When the thermocouple is installed in the specimen, the spherical contact surface of the weld bead is held in contact with the end wall of the blind hole, with a predetermined bias force.

  15. Decommissioning of the high flux beam reactor at Brookhaven Lab

    SciTech Connect

    Hu, J.P.; Reciniello, R.N.; Holden, N.E.

    2011-07-01

    The high-flux beam reactor (HFBR) at the Brookhaven National Laboratory was a heavy water cooled and moderated reactor that achieved criticality on Oct. 31, 1965. It operated at a power level of 40 megawatts. An equipment upgrade in 1982 allowed operations at 60 megawatts. After a 1989 reactor shutdown to reanalyze safety impact of a hypothetical loss of coolant accident, the reactor was restarted in 1991 at 30 megawatts. The HFBR was shut down in December 1996 for routine maintenance and refueling. At that time, a leak of tritiated water was identified by routine sampling of groundwater from wells located adjacent to the reactor's spent fuel pool. The reactor remained shut down for almost three years for safety and environmental reviews. In November 1999 the United States Dept. of Energy decided to permanently shut down the HFBR. The decontamination and decommissioning of the HFBR complex, consisting of multiple structures and systems to operate and maintain the reactor, were complete in 2009 after removing and shipping off all the control rod blades. The emptied and cleaned HFBR dome, which still contains the irradiated reactor vessel, is presently under 24/7 surveillance for safety. Detailed dosimetry performed for the HFBR decommissioning during 1996-2009 is described in the paper. (authors)

  16. The AVR (HTGR) decommissioning project with new strategy

    SciTech Connect

    Sterner, Hakan; Rittscher, Dieter

    2007-07-01

    The 15-MWel prototype pilot reactor AVR is a pebble bed HTGR. It was designed in the late 50's and was connected to the grid end of 1967. After 21 y of successful operation the reactor was shut down end of 1988. In 1994 the first decommissioning license was granted and work with defueling, dismantling and preparation of a Safe Enclosure started. The primary system is contaminated with the fission products Sr{sup 90} and Cs{sup 137} and the activation products are Co{sup 60}, C{sup 14} and H{sup 3}. Due to the large amounts of Sr and Cs bound to graphite dust, the dismantling of systems connected to the pressure vessel is very tedious. In 2003 the AVR company was restructured and the strategy of the decommissioning was changed from safe enclosure to green field, i.e. the complete direct dismantling of all facilities and clean up of the site. The highlight during the dismantling is the removal of the reactor vessel (diameter ca. 7.6 m and length ca. 26 m) in one piece. Before handling the reactor vessel it will be filled with low density cellular concrete. Subsequently the reactor building will be cut open and the reactor vessel (total weight ca. 2100 Mg) lifted out and transported to an interim store. (authors)

  17. DECOMMISSIONING THE BROOKHAVEN NATIONAL LABORATORY BUILDING 830 GAMMA IRRADIATION FACILITY.

    SciTech Connect

    BOWERMAN, B.S.; SULLIVAN, P.T.

    2001-08-13

    The Building 830 Gamma Irradiation Facility (GIF) at Brookhaven National Laboratory (BNL) was decommissioned because its design was not in compliance with current hazardous tank standards and its cobalt-60 sources were approaching the end of their useful life. The facility contained 354 stainless steel encapsulated cobalt-60 sources in a pool, which provided shielding. Total cobalt-60 inventory amounted to 24,000 Curies when the sources were shipped for disposal. The decommissioning project included packaging, transport, and disposal of the sources and dismantling and disposing of all other equipment associated with the facility. Worker exposure was a major concern in planning for the packaging and disposal of the sources. These activities were planned carefully according to ALARA (As Low As Reasonably Achievable) principles. As a result, the actual occupational exposures experienced during the work were within the planned levels. Disposal of the pool water required addressing environmental concerns, since the planned method was to discharge the slightly contaminated water to the BNL sewage treatment plant. After the BNL evaluation procedure for discharge to the sewage treatment plant was revised and reviewed by regulators and BNL's Community Advisory Council, the pool water was discharged to the Building 830 sanitary system. Because the sources were sealed and the pool water contamination levels were low, most of the remaining equipment was not contaminated; therefore disposal was straightforward, as scrap metal and construction debris.

  18. Resource book: Decommissioning of contaminated facilities at Hanford

    SciTech Connect

    Not Available

    1991-09-01

    In 1942 Hanford was commissioned as a site for the production of weapons-grade plutonium. The years since have seen the construction and operation of several generations of plutonium-producing reactors, plants for the chemical processing of irradiated fuel elements, plutonium and uranium processing and fabrication plants, and other facilities. There has also been a diversification of the Hanford site with the building of new laboratories, a fission product encapsulation plant, improved high-level waste management facilities, the Fast Flux test facility, commercial power reactors and commercial solid waste disposal facilities. Obsolescence and changing requirements will result in the deactivation or retirement of buildings, waste storage tanks, waste burial grounds and liquid waste disposal sites which have become contaminated with varying levels of radionuclides. This manual was established as a written repository of information pertinent to decommissioning planning and operations at Hanford. The Resource Book contains, in several volumes, descriptive information of the Hanford Site and general discussions of several classes of contaminated facilities found at Hanford. Supplementing these discussions are appendices containing data sheets on individual contaminated facilities and sites at Hanford. Twelve appendices are provided, corresponding to the twelve classes into which the contaminated facilities at Hanford have been organized. Within each appendix are individual data sheets containing administrative, geographical, physical, radiological, functional and decommissioning information on each facility within the class. 68 refs., 54 figs., 18 tabs.

  19. Characterisation of radioactive waste products associated with plant decommissioning.

    PubMed

    Sejvar, J; Fero, A H; Gil, C; Hagler, R J; Santiago, J L; Holgado, A; Swenson, R

    2005-01-01

    The inventory of radioactivity that must be considered in the decommissioning of a typical 1000 MWe Spanish pressurised water reactor (PWR) was investigated as part of a generic plant decommissioning study. Analyses based on DORT models (in both R-Z and R-theta geometries) were used with representative plant operating history and core power distribution data in defining the expected neutron environment in regions near the reactor core. The activation analyses were performed by multiplying the DORT scalar fluxes by energy-dependent reaction cross sections (based on ENDF/B-VI data) to generate reaction rates on a per atom basis. The results from the ORIGEN2 computer code were also used for determining the activities associated with certain nuclides where multi-group cross section data were not available. In addition to the bulk material activation of equipment and structures near the reactor, the activated corrosion-product (or 'crud') deposits on system and equipment surfaces were considered. The projected activities associated with these sources were primarily based on plant data and experience from operating PWR plants. PMID:16381771

  20. Nuclear facility decommissioning and site remedial actions: a selected bibliography

    SciTech Connect

    Owen, P.T.; Knox, N.P.; Fielden, J.M.; Johnson, C.A.

    1982-09-01

    This bibliography contains 693 references with abstracts on the subject of nuclear facility decommissioning, uranium mill tailings management, and site remedial actions. Foreign, as well as domestic, literature of all types - technical reports, progress reports, journal articles, conference papers, symposium proceedings, theses, books, patents, legislation, and research project descriptions - has been included in this publication. The bibliography contains scientific (basic research as well as applied technology), economic, regulatory, and legal literature pertinent to the US Department of Energy's Remedial Action Program. Major chapters are Surplus Facilities Management Program, Nuclear Facilities Decommissioning, Formerly Utilized Sites Remedial Action Program, Uranium Mill Tailings Remedial Action Program, Grand Junction Remedial Action Program, and Uranium Mill Tailings Management. Chapter sections for chapters 1 and 2 include: Design, Planning, and Regulations; Site Surveys; Decontamination Studies; Dismantlement and Demolition; Land Decontamination and Reclamation; Waste Disposal; and General Studies. The references within each chapter are arranged alphabetically by leading author. References having no individual author are arranged by corporate author or by title. Indexes are provided for (1) author; (2) corporate affiliation; (3) title; (4) publication description; (5) geographic location; and (6) keywords. An appendix of 202 bibliographic references without abstracts or indexes has been included in this bibliography. This appendix represents literature identified but not abstracted due to time constraints.

  1. Experimenting with Inexpensive Plastic Springs

    ERIC Educational Resources Information Center

    Perez, Leander; Marques, Adriana; Sánchez, Iván

    2014-01-01

    Acommon undergraduate laboratory experience is the determination of the elastic constant of a spring, whether studying the elongation under a static load or studying the damped harmonic motion of the spring with a suspended mass. An alternative approach to this laboratory experience has been suggested by Menezes et al., aimed at studying the…

  2. Spring loaded locator pin assembly

    DOEpatents

    Groll, Todd A.; White, James P.

    1998-01-01

    This invention deals with spring loaded locator pins. Locator pins are sometimes referred to as captured pins. This is a mechanism which locks two items together with the pin that is spring loaded so that it drops into a locator hole on the work piece.

  3. Spring loaded locator pin assembly

    DOEpatents

    Groll, T.A.; White, J.P.

    1998-03-03

    This invention deals with spring loaded locator pins. Locator pins are sometimes referred to as captured pins. This is a mechanism which locks two items together with the pin that is spring loaded so that it drops into a locator hole on the work piece. 5 figs.

  4. Single-Crystal Springs For Accelerometers

    NASA Technical Reports Server (NTRS)

    Vanzandt, Thomas R.; Kaiser, William J.; Kenny, Thomas W.

    1995-01-01

    Thermal noise reduced, enabling use of smaller proof masses. Spring-and-mass accelerometers in which springs made of single-crystal material being developed. In spring-and-mass accelerometer, proof mass attached to one end of spring, and acceleration of object at other end of spring measured in terms of deflection of spring, provided frequency spectrum of acceleration lies well below resonant frequency of spring-and-proof-mass system. Use of single-crystal spring materials instead of such polycrystalline spring materials as ordinary metals makes possible to construct highly sensitive accelerometers (including seismometers) with small proof masses.

  5. Offshore scientific and technical publications, February-July, Spring 1989. Quarterly report

    SciTech Connect

    Not Available

    1989-01-01

    The catalog lists all current (1987-1989) scientific and technical publications of the Offshore Minerals Management Program. The catalog is updated and released on a quarterly basis in winter, spring, summer, and fall. Publications available after July 21, 1989, will be listed in the next issue.

  6. Mallow Springs, County Cork, Ireland

    NASA Astrophysics Data System (ADS)

    Aldwell, C. R.

    1996-03-01

    Because of its copious and reliable rainfall, Ireland has an abundance of springs. Many of the larger ones issue from the Carboniferous limestone that occurs in over 40% of the country. The spring water is mainly a calcium bicarbonate type with a temperature of about 10°C. In the 18th century, warm and cold springs were developed as spas in various parts of Ireland. The popularity of these springs was short and most were in major decline by 1850. Today only one cold spa at Lisdoonvarna, Co. Clare is still operating. Springs in Ireland were places of religious significance for the pre-Christian Druidic religion. In the Christian period they became holy wells, under the patronage of various saints. Cures for many different ailments were attributed to water from these wells.

  7. Technology, Safety and Costs of Decommissioning Nuclear Reactors At Multiple-Reactor Stations

    SciTech Connect

    Wittenbrock, N. G.

    1982-01-01

    Safety and cost information is developed for the conceptual decommissioning of large (1175-MWe) pressurized water reactors (PWRs) and large (1155-MWe) boiling water reactors {BWRs) at multiple-reactor stations. Three decommissioning alternatives are studied: DECON (immediate decontamination), SAFSTOR (safe storage followed by deferred decontamination), and ENTOMB (entombment). Safety and costs of decommissioning are estimated by determining the impact of probable features of multiple-reactor-station operation that are considered to be unavailable at a single-reactor station, and applying these estimated impacts to the decommissioning costs and radiation doses estimated in previous PWR and BWR decommissioning studies. The multiple-reactor-station features analyzed are: the use of interim onsite nuclear waste storage with later removal to an offsite nuclear waste disposal facility, the use of permanent onsite nuclear waste disposal, the dedication of the site to nuclear power generation, and the provision of centralized services. Five scenarios for decommissioning reactors at a multiple-reactor station are investigated. The number of reactors on a site is assumed to be either four or ten; nuclear waste disposal is varied between immediate offsite disposal, interim onsite storage, and immediate onsite disposal. It is assumed that the decommissioned reactors are not replaced in one scenario but are replaced in the other scenarios. Centralized service facilities are provided in two scenarios but are not provided in the other three. Decommissioning of a PWR or a BWR at a multiple-reactor station probably will be less costly and result in lower radiation doses than decommissioning an identical reactor at a single-reactor station. Regardless of whether the light water reactor being decommissioned is at a single- or multiple-reactor station: • the estimated occupational radiation dose for decommissioning an LWR is lowest for SAFSTOR and highest for DECON • the estimated

  8. Linear magnetic spring and spring/motor combination

    NASA Technical Reports Server (NTRS)

    Patt, Paul J. (Inventor); Stolfi, Fred R. (Inventor)

    1991-01-01

    A magnetic spring, or a spring and motor combination, providing a linear spring force characteristic in each direction from a neutral position, in which the spring action may occur for any desired coordinate of a typical orthogonal coordinate system. A set of magnets are disposed, preferably symmetrically about a coordinate axis, poled orthogonally to the desired force direction. A second set of magnets, respectively poled opposite the first set, are arranged on the sprung article. The magnets of one of the sets are spaced a greater distance apart than those of the other, such that an end magnet from each set forms a pair having preferably planar faces parallel to the direction of spring force, the faces being offset so that in a neutral position the outer edge of the closer spaced magnet set is aligned with the inner edge of the greater spaced magnet set. For use as a motor, a coil can be arranged with conductors orthogonal to both the magnet pole directions and the direction of desired spring force, located across from the magnets of one set and fixed with respect to the magnets of the other set. In a cylindrical coordinate system having axial spring force, the magnets are radially poled and motor coils are concentric with the cylinder axis.

  9. ISS Update: Suitport

    NASA Video Gallery

    ISS Update commentator Lynnette Madison interviews Mallory Jennings, Suitport Human Testing Lead, about making spacewalks easier and more efficient with the Suitport. Questions? Ask us on Twitter @...

  10. Ecological and political issues surrounding decommissioning of offshore oil facilities in the Southern California Bight

    USGS Publications Warehouse

    Schroeder, Donna M.; Love, Milton S.

    2004-01-01

    To aid legislators, resource managers, and the general public, this paper summarizes and clarifies some of the issues and options that the federal government and the state of California face in decommissioning offshore oil and gas production platforms, particularly as these relate to platform ecology. Both local marine ecology and political climate play a role in decommissioning offshore oil production platforms. Compared to the relatively supportive political climate in the Gulf of Mexico for “rigs-to-reefs” programs, conflicting social values among stakeholders in Southern California increases the need for understanding ecological impacts of various decommissioning alternatives (which range from total removal to allowing some or all of platform structure to remain in the ocean). Additional scientific needs in the decommissioning process include further assessment of platform habitat quality, estimation of regional impacts of decommissioning alternatives to marine populations, and determination of biological effects of any residual contaminants. The principal management need is a ranking of environmental priorities (e.g. species-of-interest and marine habitats). Because considerable numbers of economically important species reside near oil platforms, National Oceanic and Atmospheric Administration Fisheries should consider the consequences of decommissioning alternatives in their overall management plans. Management strategies could include designating reefed platforms as marine protected areas. The overarching conclusion from both ecological and political perspectives is that decommissioning decisions should be made on a case-by-case basis.

  11. Asset Decommissioning Risk Metrics for Floating Structures in the Gulf of Mexico.

    PubMed

    Kaiser, Mark J

    2015-08-01

    Public companies in the United States are required to report standardized values of their proved reserves and asset retirement obligations on an annual basis. When compared, these two measures provide an aggregate indicator of corporate decommissioning risk but, because of their consolidated nature, cannot readily be decomposed at a more granular level. The purpose of this article is to introduce a decommissioning risk metric defined in terms of the ratio of the expected value of an asset's reserves to its expected cost of decommissioning. Asset decommissioning risk (ADR) is more difficult to compute than a consolidated corporate risk measure, but can be used to quantify the decommissioning risk of structures and to perform regional comparisons, and also provides market signals of future decommissioning activity. We formalize two risk metrics for decommissioning and apply the ADR metric to the deepwater Gulf of Mexico (GOM) floater inventory. Deepwater oil and gas structures are expensive to construct, and at the end of their useful life, will be expensive to decommission. The value of proved reserves for the 42 floating structures in the GOM circa January 2013 is estimated to range between $37 and $80 billion for future oil prices between 60 and 120 $/bbl, which is about 10 to 20 times greater than the estimated $4.3 billion to decommission the inventory. Eni's Allegheny and MC Offshore's Jolliet tension leg platforms have ADR metrics less than one and are approaching the end of their useful life. Application of the proposed metrics in the regulatory review of supplemental bonding requirements in the U.S. Outer Continental Shelf is suggested to complement the current suite of financial metrics employed.

  12. Asset Decommissioning Risk Metrics for Floating Structures in the Gulf of Mexico.

    PubMed

    Kaiser, Mark J

    2015-08-01

    Public companies in the United States are required to report standardized values of their proved reserves and asset retirement obligations on an annual basis. When compared, these two measures provide an aggregate indicator of corporate decommissioning risk but, because of their consolidated nature, cannot readily be decomposed at a more granular level. The purpose of this article is to introduce a decommissioning risk metric defined in terms of the ratio of the expected value of an asset's reserves to its expected cost of decommissioning. Asset decommissioning risk (ADR) is more difficult to compute than a consolidated corporate risk measure, but can be used to quantify the decommissioning risk of structures and to perform regional comparisons, and also provides market signals of future decommissioning activity. We formalize two risk metrics for decommissioning and apply the ADR metric to the deepwater Gulf of Mexico (GOM) floater inventory. Deepwater oil and gas structures are expensive to construct, and at the end of their useful life, will be expensive to decommission. The value of proved reserves for the 42 floating structures in the GOM circa January 2013 is estimated to range between $37 and $80 billion for future oil prices between 60 and 120 $/bbl, which is about 10 to 20 times greater than the estimated $4.3 billion to decommission the inventory. Eni's Allegheny and MC Offshore's Jolliet tension leg platforms have ADR metrics less than one and are approaching the end of their useful life. Application of the proposed metrics in the regulatory review of supplemental bonding requirements in the U.S. Outer Continental Shelf is suggested to complement the current suite of financial metrics employed. PMID:25692712

  13. Piston and spring powered engine

    SciTech Connect

    Samodovitz, A. J.

    1985-12-10

    The invention is an improved piston engine, either two stroke or four stroke. In one, two stroke, one cylinder embodiment, the improvement comprises two springs connecting between the piston and the base of the piston. These springs are relatively relaxed when the crank is at top dead center. Then during the power/intake stroke, some of the fuel's energy is delivered to the crankshaft and some is used to compress the springs. The stored energy in the springs is delivered to the crankshaft during the exhaust/compression stroke while the springs return to their relatively relaxed condition. As a result, energy is delivered to the crankshaft during both strokes of the cycle, and the engine runs smooth. In one, four stroke, two cylinder embodiment, each cylinder has springs as described above, the cranks of each cylinder are aligned, and the cam sets one cylinder in the power stroke while the other is in the intake stroke. As a result, the engine runs smooth because energy is delivered to the crankshaft during all four strokes of the cycle, during two of the strokes by the burning fuel and during the other two by the release of energy in the springs. In both embodiments, a heavy crankshaft is not needed because of the more uniform power delivery.

  14. Decommissioning successes at Rocky Flats Environmental Technology Site

    SciTech Connect

    Crawford, A.C.; Hughes, F.P.; Trice, K.D.; Wolf, H.C.; Wheeler, M.

    1999-07-01

    Building 779, a cluster of 13 buildings located at Rocky Flats Environmental Technology Site (RFETS), was originally constructed in the early 1960s. The building was used to perform research and development associated with the nuclear weapons programs. The primary contaminants were plutonium and uranium, and these contaminants were dispersed throughout the facility. In 1998, Building 779 was selected to be the first plutonium facility at RFETS to be decommissioned. After extensive training, fieldwork was initiated with a single crew of 14 workers. Dismantling of the facility started with the removal and disposition of excess property. Today, thousands of pieces of property have been dispositioned and either recycled or disposed of as radioactive waste. The second facility at RFETS to begin D and D is Building 771. This facility was selected because of its extreme complexity and the desire to accelerate the RFETS closure to 2006. Building 771 is a 200,000-ft{sup 2}, 10-structure, multistory facility with more than 230 glove boxes and 8 miles of plutonium processing piping. Building 771 was used for processing plutonium and actinides between 1953 and 1989. The facility experienced many modifications, substantial variation in operations, and several upsets resulting in radiological contamination over its 40-yr operating history. The most significant event was a major fire in 1957. The 1994 Plutonium Working Group Report on Environmental Safety and Health Vulnerabilities Associated with the Department of Energy's Plutonium Storage determined that Building 771 was the most dangerous building in America. Since the report was issued, a significant quantity of special nuclear material (SNM) has been removed, hydrogen has been vented, and the draining of high- and low-level solutions from tanks has been completed. Although these activities have lowered the risk, numerous complex tasks still remain to take the building to its final end point of a slab. Three major areas of

  15. Groundwater flow cycling between a submarine spring and an inland fresh water spring.

    PubMed

    Davis, J Hal; Verdi, Richard

    2014-01-01

    Spring Creek Springs and Wakulla Springs are large first magnitude springs that derive water from the Upper Floridan Aquifer. The submarine Spring Creek Springs are located in a marine estuary and Wakulla Springs are located 18 km inland. Wakulla Springs has had a consistent increase in flow from the 1930s to the present. This increase is probably due to the rising sea level, which puts additional pressure head on the submarine Spring Creek Springs, reducing its fresh water flow and increasing flows in Wakulla Springs. To improve understanding of the complex relations between these springs, flow and salinity data were collected from June 25, 2007 to June 30, 2010. The flow in Spring Creek Springs was most sensitive to rainfall and salt water intrusion, and the flow in Wakulla Springs was most sensitive to rainfall and the flow in Spring Creek Springs. Flows from the springs were found to be connected, and composed of three repeating phases in a karst spring flow cycle: Phase 1 occurred during low rainfall periods and was characterized by salt water backflow into the Spring Creek Springs caves. The higher density salt water blocked fresh water flow and resulted in a higher equivalent fresh water head in Spring Creek Springs than in Wakulla Springs. The blocked fresh water was diverted to Wakulla Springs, approximately doubling its flow. Phase 2 occurred when heavy rainfall resulted in temporarily high creek flows to nearby sinkholes that purged the salt water from the Spring Creek Springs caves. Phase 3 occurred after streams returned to base flow. The Spring Creek Springs caves retained a lower equivalent fresh water head than Wakulla Springs, causing them to flow large amounts of fresh water while Wakulla Springs flow was reduced by about half.

  16. Groundwater flow cycling between a submarine spring and an inland fresh water spring

    USGS Publications Warehouse

    Davis, J. Hal; Verdi, Richard

    2014-01-01

    Spring Creek Springs and Wakulla Springs are large first magnitude springs that derive water from the Upper Floridan Aquifer. The submarine Spring Creek Springs are located in a marine estuary and Wakulla Springs are located 18 km inland. Wakulla Springs has had a consistent increase in flow from the 1930s to the present. This increase is probably due to the rising sea level, which puts additional pressure head on the submarine Spring Creek Springs, reducing its fresh water flow and increasing flows in Wakulla Springs. To improve understanding of the complex relations between these springs, flow and salinity data were collected from June 25, 2007 to June 30, 2010. The flow in Spring Creek Springs was most sensitive to rainfall and salt water intrusion, and the flow in Wakulla Springs was most sensitive to rainfall and the flow in Spring Creek Springs. Flows from the springs were found to be connected, and composed of three repeating phases in a karst spring flow cycle: Phase 1 occurred during low rainfall periods and was characterized by salt water backflow into the Spring Creek Springs caves. The higher density salt water blocked fresh water flow and resulted in a higher equivalent fresh water head in Spring Creek Springs than in Wakulla Springs. The blocked fresh water was diverted to Wakulla Springs, approximately doubling its flow. Phase 2 occurred when heavy rainfall resulted in temporarily high creek flows to nearby sinkholes that purged the salt water from the Spring Creek Springs caves. Phase 3 occurred after streams returned to base flow. The Spring Creek Springs caves retained a lower equivalent fresh water head than Wakulla Springs, causing them to flow large amounts of fresh water while Wakulla Springs flow was reduced by about half.

  17. How Does Decommissioning Forest Roads Effect Hydrologic and Geomorphic Risk?

    NASA Astrophysics Data System (ADS)

    Black, T.; Luce, C.; Cissel, R. M.; Nelson, N.; Staab, B.

    2010-12-01

    The US Forest Service is investigating road decommissioning projects to understand how treatments change hydrologic and geomorphic risks. Road treatment effect was measured using a before after control impact design (BACI), using the Geomorphic Road Analysis and Inventory Package (http://www.fs.fed.us/GRAIP). This suite of inventory and analysis tools evaluates: road-stream hydrologic connectivity, fine sediment production and delivery, shallow landslide risk, gully initiation risk, and risks associated with stream crossing failures. The Skokomish River study site is steep and wet and received a high intensity treatment including the removal of stream crossing pipes and fills, all ditch relief pipes and a full hillslope recontouring. Road to stream hydrologic connectivity was reduced by 70%. The treatments reduced fine sediment delivery by 21.8 tons or 81%. The removal of the stream crossing culverts and large associated road fills eliminated the risk of pipe plugging related failures and the eventual erosion of over 4,000 m3 of fill. The slope stability risk was assessed using a modified version of SINMAP (Pack et al, 2005). Risk below drain point locations on the original road was reduced as water was redistributed across the hillslope to waterbars and diffuse drainage. It is unclear; however, if landslide risk was reduced across the entire treated road length because treatments slightly increased risk in some areas where new concentrated drainage features were added above steep slopes. Similarly, values of a gully index ESI (Istanbulluoglu et al, 2003), were reduced at many of the original drainage points, however some new drainage was added. ESI values still exceed a predicted conservative initiation thresholds at some sites, therefore it is uncertain if gully risk will be changed. Mann Creek occupies a moderately steep mid-elevation site in Southern Idaho. The high intensity treatments removed all constructed road drainage features including stream crossing

  18. Decontamination and decommissioning experience at the Savannah River Site

    SciTech Connect

    Monson, R.W.

    1994-07-01

    A continuing concern within the DOE complex is how to address the retirement contains special of a facility which nuclear material (SNM). When the life expectancy of a facility has been reached, decisions must be made pertaining to (1) rial from the facility, removing the mate (2) accounting for the material and (3) final disposition of the material. This paper will discuss such a decontamination and decommissioning (D&D) process which we are presently dealing with at the Savannah River Site. The process must follow DOE Order 5633.3A as well as internal Company procedures regarding MC&A. In some D&D cases the material can be exempt from the DOE Order when all of the following criteria are met: (1) the material has been declared waste, (2) the material has been written off the MC&A books, and (3) the material is under the control of a waste management organization.

  19. Fusulinid biostratigraphy of Bird Spring Formation in Spring Mountains near Mountain Springs Pass, Clark County, Nevada

    SciTech Connect

    Gamache, M.T.; Webster, G.D.

    1987-05-01

    Fusulinids from a 955.16 m thick section of Chesterian into Wolfcampian rocks of the Indian Springs and Bird Spring formations exposed near Mountain Springs Pass represent the biozones of Millerella to Pseudoschwagerina. Species of Millerella, Plectofusulina, Staffella, Schubertina, Pseudostaffella, Profusulinella, Fusulinella, Beedeina, Oketaella, Pseudofusulina, Triticites, Schwagerina, Eoparafusulina, and Cuniculinella were described. One new species of Millerella and three new species of Tricities were named. The Mountain Springs section can be correlated intraregionally with other sections in Clark County using similar cherty limestones or sandstone-dominated strata in association with biozones recognized in the southern Great Basin. The thickening of strata from the Mountain Springs section to the Arrow Canyon and Lee Canyon sections demonstrated by this method reflects each section's position to the northeast-trending Las Vegas-Wasatch hinge line between thin, shallow shelf sediments and thicker sediments to the west after palinspastic reconstruction. The large diversity of fusulinid species in the Mountain Springs section relative to Arrow Canyon and Lee Canyon suggests that a fusulinid diversity index may be useful in correlating similar paleoenvironments. Fusulinid biozones of the Mountain Springs section can also be correlated regionally with fusulinid subbiozones A through G of the Shasta Lake area in northern California and with fusulinid biozones of the Mid-Continent based on similar species and occurrences.

  20. Site-characteristic and hydrologic data for selected wells and springs on Federal land in Clark County, Nevada

    USGS Publications Warehouse

    Pavelko, Michael T.

    2014-01-01

    Site-characteristic and hydrologic data for selected wells and springs on U.S. Bureau of Land Management, National Park Service, U.S. Fish and Wildlife Service, and U.S. Forest Service land in Clark County, Nevada, were updated in the U.S. Geological Survey’s National Water Information System (NWIS) to facilitate multi-agency research. Data were researched and reviewed, sites were visited, and NWIS data were updated for 231 wells and 198 springs, including 36 wells and 67 springs that were added to NWIS and 44 duplicate sites that were deleted. The site-characteristic and hydrologic data collected, reviewed, edited, and added to NWIS include locations, well water levels, spring discharges, and water chemistry. Site-characteristic and hydrologic data can be accessed from links to the NWIS web interface; data not available through the web interface are presented in appendixes to this report.

  1. Sensor Network Demonstration for In Situ Decommissioning - 13332

    SciTech Connect

    Lagos, L.; Varona, J.; Awwad, A.; Rivera, J.; McGill, J.

    2013-07-01

    Florida International University's (FIU's) Applied Research Center is currently supporting the Department of Energy's (DOE) Environmental Management Office of D and D and Facility Engineering program. FIU is supporting DOE's initiative to improve safety, reduce technical risks, and limit uncertainty within D and D operations by identifying technologies suitable to meet specific facility D and D requirements, assessing the readiness of those technologies for field deployment, and conducting feasibility studies and large scale demonstrations of promising technologies. During FY11, FIU collaborated with Savannah River National Laboratory in the development of an experimental test site for the demonstration of multiple sensor systems for potential use in the in situ decommissioning process. In situ decommissioning is a process in which the above ground portion of a facility is dismantled and removed, and the underground portion is filled with a cementious material such as grout. In such a scenario, the question remains on how to effectively monitor the structural health of the grout (cracking, flexing, and sinking), as well as track possible migration of contaminants within and out of the grouted monolith. The right types of sensors can aid personnel in better understanding the conditions within the entombed structure. Without sensors embedded in and around the monolith, it will be very difficult to estimate structural integrity and contaminant transport. Yet, to fully utilize the appropriate sensors and the provided data, their performance and reliability must be evaluated outside a laboratory setting. To this end, a large scale experimental setup and demonstration was conducted at FIU. In order to evaluate a large suite of sensor systems, FIU personnel designed and purchased a pre-cast concrete open-top cube, which served as a mock-up of an in situ DOE decommissioned facility. The inside of the cube measures 10 ft x 10 ft x 8 ft. In order to ensure that the

  2. Spring Small Grains Area Estimation

    NASA Technical Reports Server (NTRS)

    Palmer, W. F.; Mohler, R. J.

    1986-01-01

    SSG3 automatically estimates acreage of spring small grains from Landsat data. Report describes development and testing of a computerized technique for using Landsat multispectral scanner (MSS) data to estimate acreage of spring small grains (wheat, barley, and oats). Application of technique to analysis of four years of data from United States and Canada yielded estimates of accuracy comparable to those obtained through procedures that rely on trained analysis.

  3. Genomics and Health Impact Update

    MedlinePlus

    ... Genomics in Practice Newborn Screening Pharmacogenomics Reproductive Health Tools and Databases About the Genomics & Health Impact Update The Office of Public Health Genomics provides updated and credible ...

  4. Plea for realistic environmental surveillance/decommissioning criteria based on radiation dose

    SciTech Connect

    Denham, D.H.

    1982-02-01

    This paper focuses on the need for consistent and realistic dose criteria for environmental surveillance and decommissioning programs, especially the relationships between environmental detection levels and potential annual doses, as well as the need for establishing de minimis dose criteria.

  5. 78 FR 49553 - Three Mile Island, Unit 2; Post Shutdown Decommissioning Activities Report

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-08-14

    ... From the Federal Register Online via the Government Publishing Office NUCLEAR REGULATORY COMMISSION Three Mile Island, Unit 2; Post Shutdown Decommissioning Activities Report AGENCY: Nuclear...) for Three Mile Island, Unit 2 (TMI-2). The PSDAR provides an overview of GPUN's...

  6. The First Decommissioning of a Fusion Reactor Fueled by Deuterium-Tritium

    SciTech Connect

    Charles A. Gentile; Erik Perry; Keith Rule; Michael Williams; Robert Parsells; Michael Viola; James Chrzanowski

    2003-10-28

    The Tokamak Fusion Test Reactor (TFTR) at the Plasma Physics Laboratory of Princeton University (PPPL) was the first fusion reactor fueled by a mixture of deuterium and tritium (D-T) to be decommissioned in the world. The decommissioning was performed over a period of three years and was completed safely, on schedule, and under budget. Provided is an overview of the project and detail of various factors which led to the success of the project. Discussion will cover management of the project, engineering planning before the project started and during the field work as it was being performed, training of workers in the field, the novel adaptation of tools from other industry, and the development of an innovative process for the use of diamond wire to segment the activated/contaminated vacuum vessel. The success of the TFTR decommissioning provides a viable model for the decommissioning of D-T burning fusion devices in the future.

  7. 30 CFR 285.906 - What must my decommissioning application include?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... including: (1) Lease operator, ROW grant holder, or RUE grant holder; (2) Address; (3) Contact person and... decommissioning schedule for your lease, ROW grant, or RUE grant, including the expiration or relinquishment...

  8. Nuclear facility decommissioning and site remedial actions: A selected bibliography, Volume 13: Part 2, Indexes

    SciTech Connect

    Goins, L.F.; Webb, J.R.; Cravens, C.D.; Mallory, P.K.

    1992-09-01

    This is part 2 of a bibliography on nuclear facility decommissioning and site remedial action. This report contains indexes on the following: authors, corporate affiliation, title words, publication description, geographic location, subject category, and key word.

  9. Radiochemistry Lab Decommissioning and Dismantlement. AECL, Chalk River Labs, Ontario, Canada

    SciTech Connect

    Kenny, Stephen

    2008-01-15

    Atomic Energy of Canada (AECL) was originally founded in the mid 1940's to perform research in radiation and nuclear areas under the Canadian Defense Department. In the mid 50's The Canadian government embarked on several research and development programs for the development of the Candu Reactor. AECL was initially built as a temporary site and is now faced with many redundant buildings. Prior to 2004 small amounts of Decommissioning work was in progress. Many reasons for deferring decommissioning activities were used with the predominant ones being: 1. Reduction in radiation doses to workers during the final dismantlement, 2. Development of a long-term solution for the management of radioactive wastes in Canada, 3. Financial constraints presented by the number of facilities shutdown that would require decommissioning funds and the absence of an approved funding strategy. This has led to the development of a comprehensive decommissioning plan that is all inclusive of AECL's current and legacy liabilities. Canada does not have a long-term disposal site; therefore waste minimization becomes the driving factor behind decontamination for decommissioning before and during dismantlement. This decommissioning job was a great learning experience for decommissioning and the associated contractors who worked on this project. Throughout the life of the project there was a constant focus on waste minimization. This focus was constantly in conflict with regulatory compliance primarily with respect to fire regulations and protecting the facility along with adjacent facilities during the decommissioning activities. Discrepancies in historical documents forced the project to treat every space as a contaminated space until proven differently. Decommissioning and dismantlement within an operating site adds to the complexity of the tasks especially when it is being conducted in the heart of the plant. This project was very successful with no lost time accidents in over one hundred

  10. Engineering Evaluation/Cost Analysis for Decommissioning of the Engineering Test Reactor Complex

    SciTech Connect

    A. B. Culp

    2006-10-01

    Preparation of this Engineering Evaluation/Cost Analysis is consistent with the joint U.S. Department of Energy and U.S. Environmental Protection Agency Policy on Decommissioning of Department of Energy Facilities Under the Comprehensive Environmental Response, Compensation, and Liability Act, which establishes the Comprehensive Environmental Response, Compensation, and Liability Act non-time-critical removal action (NTCRA) process as an approach for decommissioning.

  11. Technology, safety, and costs of decommissioning reference nuclear research and test reactors. Main report

    SciTech Connect

    Konzek, G.J.; Ludwick, J.D.; Kennedy, W.E. Jr.; Smith, R.I.

    1982-03-01

    Safety and Cost Information is developed for the conceptual decommissioning of two representative licensed nuclear research and test reactors. Three decommissioning alternatives are studied to obtain comparisons between costs (in 1981 dollars), occupational radiation doses, potential radiation dose to the public, and other safety impacts. The alternatives considered are: DECON (immediate decontamination), SAFSTOR (safe storage followed by deferred decontamination), and ENTOMB (entombment). The study results are presented in two volumes. Volume 1 (Main Report) contains the results in summary form.

  12. Decommissioning experience: One-piece removal and transport of a LWR pressure vessel and internals

    SciTech Connect

    Closs, J.W.

    1993-12-31

    After a brief historical perspective, this document describes several key events which took place during the decommissioning of a commercial nuclear power plant. The scope of decommissioning work included: (a) the reactor building, the reactor vessel and the contents of the reactor building; (b) the fuel handling building and its contents; (c) the fuel transfer vault between the reactor building and the fuel handling building.

  13. Comparative Evaluation of Cutting Methods of Activated Concrete from Nuclear Power Plant Decommissioning - 13548

    SciTech Connect

    Kim, HakSoo; Chung, SungHwan; Maeng, SungJun

    2013-07-01

    The amount of radioactive wastes from decommissioning of a nuclear power plant varies greatly depending on factors such as type and size of the plant, operation history, decommissioning options, and waste treatment and volume reduction methods. There are many methods to decrease the amount of decommissioning radioactive wastes including minimization of waste generation, waste reclassification through decontamination and cutting methods to remove the contaminated areas. According to OECD/NEA, it is known that the radioactive waste treatment and disposal cost accounts for about 40 percentage of the total decommissioning cost. In Korea, it is needed to reduce amount of decommissioning radioactive waste due to high disposal cost, about $7,000 (as of 2010) per a 200 liter drum for the low- and intermediate-level radioactive waste (LILW). In this paper, cutting methods to minimize the radioactive waste of activated concrete were investigated and associated decommissioning cost impact was assessed. The cutting methods considered are cylindrical and volume reductive cuttings. The study showed that the volume reductive cutting is more cost-effective than the cylindrical cutting. Therefore, the volume reductive cutting method can be effectively applied to the activated bio-shield concrete. (authors)

  14. Summary report of Hanford Site well remediation and decommissioning activities for fiscal year 1994

    SciTech Connect

    Reynolds, K.D.

    1994-12-30

    Remediation and decommissioning of Hanford Site wells has become an integral part of Hanford Site Environmental Restoration (ER) and Resource Conservation and Recovery Act of 1976 (RCRA) groundwater monitoring programs. A well remediation and decommissioning program was funded and implemented in fiscal year (FY) 1993 under the RCRA and Operational Monitoring (ROM) Program. Funding for this work increased in FY 1994. In FY 1994 well decommissioning activities conducted for the ROM program were centered around the 200 West Area; activities for the ER program were centered in the Fitzner/Eberhart Arid Land Ecology (ALE) (Reserve) unit and the Wahluke Slope (North Slope) area. A total of 116 wells and test borings were decommissioned between the two programs during FY 1994. Additionally, five wells were identified as in need of remediation and were successfully brought into compliance with regulatory requirements. As Hanford Site restoration and remediation efforts increase in scope, the well decommissioning program will remain dynamic. The program will aggressively seek to fulfill the needs of the various environmental cleanup and groundwater/vadose monitoring programs. Wells that do not meet regulatory requirements for preservation will continually be identified and remediated or decommissioned accordingly.

  15. 49 CFR 230.111 - Spring rigging.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 49 Transportation 4 2012-10-01 2012-10-01 false Spring rigging. 230.111 Section 230.111... Tenders Trucks, Frames and Equalizing System § 230.111 Spring rigging. (a) Arrangement of springs and equalizers. Springs and equalizers shall be arranged to ensure the proper distribution of weight to...

  16. 49 CFR 236.822 - Switch, spring.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... Switch, spring. A switch equipped with a spring device which forces the points to their original position after being trailed through and holds them under spring compression. ... 49 Transportation 4 2014-10-01 2014-10-01 false Switch, spring. 236.822 Section...

  17. 49 CFR 236.822 - Switch, spring.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... Switch, spring. A switch equipped with a spring device which forces the points to their original position after being trailed through and holds them under spring compression. ... 49 Transportation 4 2010-10-01 2010-10-01 false Switch, spring. 236.822 Section...

  18. 49 CFR 236.822 - Switch, spring.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... Switch, spring. A switch equipped with a spring device which forces the points to their original position after being trailed through and holds them under spring compression. ... 49 Transportation 4 2011-10-01 2011-10-01 false Switch, spring. 236.822 Section...

  19. 49 CFR 236.822 - Switch, spring.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... Switch, spring. A switch equipped with a spring device which forces the points to their original position after being trailed through and holds them under spring compression. ... 49 Transportation 4 2013-10-01 2013-10-01 false Switch, spring. 236.822 Section...

  20. 49 CFR 236.822 - Switch, spring.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... Switch, spring. A switch equipped with a spring device which forces the points to their original position after being trailed through and holds them under spring compression. ... 49 Transportation 4 2012-10-01 2012-10-01 false Switch, spring. 236.822 Section...

  1. 49 CFR 229.65 - Spring rigging.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ..., except when that spring is part of a nest of three or more springs and none of the other springs in the nest has its top leaf or any other three leaves broken. An outer coil spring or saddle may not...

  2. 49 CFR 229.65 - Spring rigging.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ..., except when that spring is part of a nest of three or more springs and none of the other springs in the nest has its top leaf or any other three leaves broken. An outer coil spring or saddle may not...

  3. 49 CFR 229.65 - Spring rigging.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ..., except when that spring is part of a nest of three or more springs and none of the other springs in the nest has its top leaf or any other three leaves broken. An outer coil spring or saddle may not...

  4. 49 CFR 229.65 - Spring rigging.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ..., except when that spring is part of a nest of three or more springs and none of the other springs in the nest has its top leaf or any other three leaves broken. An outer coil spring or saddle may not...

  5. 49 CFR 229.65 - Spring rigging.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ..., except when that spring is part of a nest of three or more springs and none of the other springs in the nest has its top leaf or any other three leaves broken. An outer coil spring or saddle may not...

  6. Deactivation and Decommissioning Planning and Analysis with Geographic Information Systems

    SciTech Connect

    Bollinger, James S.; Koffman, Larry D.; Austin, William E.

    2008-01-15

    From the mid-1950's through the 1980's, the U.S. Department of Energy's Savannah River Site produced nuclear materials for the weapons stockpile, for medical and industrial applications, and for space exploration. Although SRS has a continuing defense-related mission, the overall site mission is now oriented toward environmental restoration and management of legacy chemical and nuclear waste. With the change in mission, SRS no longer has a need for much of the infrastructure developed to support the weapons program. This excess infrastructure, which includes over 1000 facilities, will be decommissioned and demolished over the forthcoming years. Dis-positioning facilities for decommissioning and deactivation requires significant resources to determine hazards, structure type, and a rough-order-of-magnitude estimate for the decommissioning and demolition cost. Geographic information systems (GIS) technology was used to help manage the process of dis-positioning infrastructure and for reporting the future status of impacted facilities. Several thousand facilities of various ages and conditions are present at SRS. Many of these facilities, built to support previous defense-related missions, now represent a potential hazard and cost for maintenance and surveillance. To reduce costs and the hazards associated with this excess infrastructure, SRS has developed an ambitious plan to decommission and demolish unneeded facilities in a systematic fashion. GIS technology was used to assist development of this plan by: providing locational information for remote facilities, identifying the location of known waste units adjacent to buildings slated for demolition, and for providing a powerful visual representation of the impact of the overall plan. Several steps were required for the development of the infrastructure GIS model. The first step involved creating an accurate and current GIS representation of the infrastructure data. This data is maintained in a Computer Aided Design

  7. Interactions between geomorphology and ecosystem processes in travertine streams: Implications for decommissioning a dam on Fossil Creek, Arizona

    NASA Astrophysics Data System (ADS)

    Marks, Jane C.; Parnell, Roderic; Carter, Cody; Dinger, Eric C.; Haden, G. Allen

    2006-07-01

    Travertine deposits of calcium carbonate can dominate channel geomorphology in streams where travertine deposition creates a distinct morphology characterized by travertine terraces, steep waterfalls, and large pools. Algae and microorganisms can facilitate travertine deposition, but how travertine affects material and energy flow in stream ecosystems is less well understood. Nearly a century of flow diversion for hydropower production has decimated the natural travertine formations in Fossil Creek, Arizona. The dam will be decommissioned in 2005. Returning carbonate-rich spring water to the natural stream channel should promote travertine deposition. How will the recovery of travertine affect the ecology of the creek? To address this question, we compared primary production, decomposition, and the abundance and diversity of invertebrates and fish in travertine and riffle/run reaches of Fossil Creek, Arizona. We found that travertine supports higher primary productivity, faster rates of leaf litter decomposition, and higher species richness of the native invertebrate assemblage. Observations from snorkeling in the stream indicate that fish density is also higher in the travertine reach. We postulate that restoring travertine to Fossil Creek will increase stream productivity, rates of litter processing, and energy flow up the food web. Higher aquatic productivity could fundamentally shift the nature of the stream from a sink to a source of energy for the surrounding terrestrial landscape.

  8. Fossilization Processes in Thermal Springs

    NASA Technical Reports Server (NTRS)

    Farmer, Jack D.; Cady, Sherry; Desmarais, David J.; Chang, Sherwood (Technical Monitor)

    1995-01-01

    To create a comparative framework for the study of ancient examples, we have been carrying out parallel studies of the microbial biosedimentology, taphonomy and geochemistry of modem and sub-Recent thermal spring deposits. One goal of the research is the development of integrated litho- and taphofacies models for siliceous and travertline sinters. Thermal springs are regarded as important environments for the origin and early evolution of life on Earth, and we seek to utilize information from the fossil record to reconstruct the evolution of high temperature ecosystems. Microbial contributions to the fabric of thermal spring sinters occur when population growth rates keep pace with, or exceed rates of inorganic precipitation, allowing for the development of continuous biofilms or mats. In siliceous thermal springs, microorganisms are typically entombed while viable. Modes of preservation reflect the balance between rates of organic matter degradation, silica precipitation and secondary infilling. Subaerial sinters are initially quite porous and permeable and at temperatures higher than about 20 C, organic materials are usually degraded prior to secondary infilling of sinter frameworks. Thus, organically-preserved microfossils are rare and fossil information consists of characteristic biofabrics formed by the encrustation and underplating of microbial mat surfaces. This probably accounts for the typically low total organic carbon values observed in thermal spring deposits. In mid-temperature, (approx. 35 - 59 C) ponds and outflows, the surface morphology of tufted Phormidium mats is preserved through mat underplating by thin siliceous: crusts. Microbial taxes lead to clumping of ceils and/or preferred filament orientations that together define higher order composite fabrics in thermal spring stromatolites (e.g. network, coniform, and palisade). At lower temperatures (less than 35 C), Calothrix mats cover shallow terracette pools forming flat carpets or pustular

  9. Application of Robotics in Decommissioning and Decontamination - 12536

    SciTech Connect

    Banford, Anthony; Kuo, Jeffrey A.; Bowen, R.A.; Szilagyi, Andrew; Kirk, Paula

    2012-07-01

    Decommissioning and dismantling of nuclear facilities is a significant challenge worldwide and one which is growing in size as more plants reach the end of their operational lives. The strategy chosen for individual projects varies from the hands-on approach with significant manual intervention using traditional demolition equipment at one extreme to bespoke highly engineered robotic solutions at the other. The degree of manual intervention is limited by the hazards and risks involved, and in some plants are unacceptable. Robotic remote engineering is often viewed as more expensive and less reliable than manual approaches, with significant lead times and capital expenditure. However, advances in robotics and automation in other industries offer potential benefits for future decommissioning activities, with the high probability of reducing worker exposure and other safety risks as well as reducing the schedule and costs required to complete these activities. Some nuclear decommissioning tasks and facility environments are so hazardous that they can only be accomplished by exclusive use of robotic and remote intervention. Less hazardous tasks can be accomplished by manual intervention and the use of PPE. However, PPE greatly decreases worker productivity and still exposes the worker to both risk and dose making remote operation preferable to achieve ALARP. Before remote operations can be widely accepted and deployed, there are some economic and technological challenges that must be addressed. These challenges will require long term investment commitments in order for technology to be: - Specifically developed for nuclear applications; - At a sufficient TRL for practical deployment; - Readily available as a COTS. Tremendous opportunities exist to reduce cost and schedule and improve safety in D and D activities through the use of robotic and/or tele-operated systems. - Increasing the level of remote intervention reduces the risk and dose to an operator. Better

  10. ISS Update: Suitport Testing

    NASA Video Gallery

    ISS Update commentator Lynnette Madison interviews Joel Maganza, Test Director, about thermal vacuum chambers and unmanned and human-testing with the Suitport. Questions? Ask us on Twitter @NASA_Jo...

  11. ISS Update: NEEMO 16

    NASA Video Gallery

    ISS Update commentator Josh Byerly interviews astronaut Stan Love about the NEEMO 16 mission from Aquarius Base. Questions? Ask us on Twitter @NASA_Johnson and include the hashtag #askStation. For ...

  12. ACS Updates Environmental Report.

    ERIC Educational Resources Information Center

    Chemical and Engineering News, 1978

    1978-01-01

    Describes a new publication of a report prepared by the American Chemical Society's Committee on Environmental Improvement. This is a new version that updates a 1969 report and contains additional material and expanded recommendations. (GA)

  13. A manual for applying the allowable residual contamination level method for decommissioning facilities on the Hanford Site

    SciTech Connect

    Napier, B.A.; Piepel, G.F.; Kennedy, W.E. Jr.; Schreckhise, R.G.

    1988-08-01

    This report describes the modifications that have been made to enhance the original Allowable Residual Contamination Level (ARCL) method to make it more applicable to site-specific analyses. This version considers the mixture of radionuclides present at the time of site characterization, the elapsed time after decommissioning when exposure to people could occur, and includes a calculation of the upper confidence limit of the potential dose based on sampling statistics that are developed during the site characterization efforts. The upper confidence limit of potential exposure can now be used for comparison against applicable radiation dose limits (i.e., 25 mrem/yr at Hanford). The level of confidence can be selected by the user. A wide range of exposure scenarios were evaluated; the rationale used to select the most limiting scenarios is explained. The radiation dose factors used for the inhalation and ingestion pathways were also updated to correspond with the radiation dosimetry methods utilized in the International Commission of Radiological Protection Publications 26 and 30 (ICRP 1977; 1979a,b, 1980, 1981, 1982a,b). This simplifies the calculations, since ''effective whole body'' doses are now calculated, and also brings the dosimetry methods used in the ARCL method in conformance with the rationale used by DOE in developing the 25 mrem/yr limit at Hanford. 46 refs., 21 figs., 15 tabs.

  14. The Dependence of the Spring Constant in the Linear Range on Spring Parameters

    ERIC Educational Resources Information Center

    Khotimah, Siti Nurul; Viridi, Sparisoma; Widayani; Khairurrijal

    2011-01-01

    In basic physics laboratories, springs are normally used to determine both spring constants and the Earth's gravitational acceleration. Students generally do not notice that the spring constant is not a universal constant, but depends on the spring parameters. This paper shows and verifies that the spring constant in the linear range is inversely…

  15. Environmental regulatory update table

    SciTech Connect

    Brown, K.J.; Langston, M.E.; Tucker, C.S.; Reed, R.M.

    1987-06-01

    The Environmental Regulatory Update Table provides information on regulatory initiatives of interest to DOE operations and contractor staff with environmental management responsibilities. The table is updated each month with information from the Federal Register and other sources, including direct contact with regulatory agencies. Each table entry provides a chronological record of the rulemaking process for that initiative with an abstract and a projection of further action.

  16. Cost Savings through Innovation in Decontamination, Decommissioning, and Dismantlement

    SciTech Connect

    Neal A. Yancey

    2003-02-27

    The United States Department of Energy (DOE) continually seeks safer and more cost effective technologies for the decontamination and decommissioning (D&D) of nuclear facilities. The Deactivation and Decommissioning Focus Area (DDFA) of the DOE's Office of Science and Technology (OST) sponsored large-scale demonstration and deployment projects (LSDDPs) to help bring new technologies into the D&D programs. The Idaho National Engineering and Environmental Laboratory (INEEL) LSDDP generated a list of needs defining specific problems where improved technologies could be incorporated into ongoing D&D tasks. The needs fell into 5 major categories--characterization, dismantlement, safety, material dispositioning, and decontamination. Technologies were carefully selected that provide a large benefit for a small investment. The technologies must provide significant improvements in cost, safety, radiation exposure, waste volume reduction, or schedule savings and widely applicable throughout the DOE complex. The LSDDP project provided training for the new technologies and worked with technology suppliers to resolve any questions that arose. Since 1998, 26 technologies have been demonstrated or deployed through the LSDDP for the D&D program at the INEEL. Of the 26 demonstrated and deployed technologies, 14 were in characterization, 3 were in decontamination, 4 were in dismantlement, 3 were in safety, and 2 were in material dispositioning. To promote the use of these technologies at other sites within the DOE complex, the LSDDP team published fact sheets, videos, technology summary reports, articles in INEEL star newspaper, posters, and maintained an internet home page on the project. As a result, additional deployments have taken place at the Hanford, Mound, Fernald, Oak Ridge, Ashtabula, and West Valley. Eight of the 26 technologies evaluated were developed in foreign countries. The technologies demonstrated have been shown to be faster, less expensive, and/or safer. The

  17. Waste Management Strategy for Dismantling Waste to Reduce Costs for Power Plant Decommissioning - 13543

    SciTech Connect

    Larsson, Arne; Lidar, Per; Bergh, Niklas; Hedin, Gunnar

    2013-07-01

    Decommissioning of nuclear power plants generates large volumes of radioactive or potentially radioactive waste. The proper management of the dismantling waste plays an important role for the time needed for the dismantling phase and thus is critical to the decommissioning cost. An efficient and thorough process for inventorying, characterization and categorization of the waste provides a sound basis for the planning process. As part of comprehensive decommissioning studies for Nordic NPPs, Westinghouse has developed the decommissioning inventories that have been used for estimations of the duration of specific work packages and the corresponding costs. As part of creating the design basis for a national repository for decommissioning waste, the total production of different categories of waste packages has also been predicted. Studsvik has developed a risk based concept for categorization and handling of the generated waste using six different categories with a span from extremely small risk for radiological contamination to high level waste. The two companies have recently joined their skills in the area of decommissioning on selected market in a consortium named 'ndcon' to further strengthen the proposed process. Depending on the risk for radiological contamination or the radiological properties and other properties of importance for waste management, treatment routes are proposed with well-defined and proven methods for on-site or off-site treatment, activity determination and conditioning. The system is based on a graded approach philosophy aiming for high confidence and sustainability, aiming for re-use and recycling where found applicable. The objective is to establish a process where all dismantled material has a pre-determined treatment route. These routes should through measurements, categorization, treatment, conditioning, intermediate storage and final disposal be designed to provide a steady, un-disturbed flow of material to avoid interruptions. Bottle

  18. Technology, safety and costs of decommissioning a Reference Boiling Water Reactor Power Station. Main report. Volume 1

    SciTech Connect

    Oak, H.D.; Holter, G.M.; Kennedy, W.E. Jr.; Konzek, G.J.

    1980-06-01

    Technology, safety and cost information is given for the conceptual decommissioning of a large (1100MWe) boiling water reactor (BWR) power station. Three approaches to decommissioning, immediate dismantlement, safe storage with deferred dismantlement and entombment, were studied to obtain comparisons between costs, occupational radiation doses, potential dose to the public and other safety impacts. It also shows the sensitivity of decommissioning safety and costs to the power rating of a BWR in the range of 200 to 1100 MWe.

  19. Regulation of an Actin Spring

    NASA Astrophysics Data System (ADS)

    Tam, Barney; Shin, Jennifer; Brau, Ricardo; Lang, Matthew; Mahadevan, L.; Matsudaira, Paul

    2006-03-01

    To produce motion, cells rely on the conversion of potential energy into mechanical work. One such example is the dramatic process involving the acrosome reaction of Limulus sperm, whereby a 60 μm-long bundle of actin filaments straightens from a coiled conformation to extend out of the cell in five seconds. This cellular engine and the motion it produces represent a third type of actin-based motility fundamentally different from polymerization or myosin-driven processes. The motive force for this extension originates from stored elastic energy in the overtwisted, pre-formed coil---much like a compressed mechanical spring. When the actin bundle untwists, this energy is converted to mechanical work powering the extension. We report on experiments probing the regulation of this actin spring by extracellular calcium. We find that extracellular calcium needs to be present for the spring to activate, and that calcium regulates the velocity of the extension.

  20. Bouncing dynamics of a spring

    NASA Astrophysics Data System (ADS)

    Hubert, M.; Ludewig, F.; Dorbolo, S.; Vandewalle, N.

    2014-04-01

    We consider the dynamics of a deformable object bouncing on an oscillating plate and we propose to model its deformations. For this purpose, we use a spring linked to a damper. Elastic properties and viscous effects are taken into account. From the bouncing spring equations of motion, we emphasize the relevant parameters of the dynamics. We discuss the range of parameters in which elastic deformations do not influence the bouncing dynamics of this object and compare this behavior with the bouncing ball dynamics. By calculating the spring bouncing threshold, we evidence the effect of resonance and prove that elastic properties can make the bounce easier. This effect is for example encountered in the case of bouncing droplets. We also consider bifurcation diagrams in order to describe the consequences of a dependence on the frequency. Finally, hysteresis in the dynamics is presented.

  1. Oak Ridge National Laboratory Technology Logic Diagram. Volume 2, Technology Logic Diagram: Part A, Decontamination and Decommissioning

    SciTech Connect

    Not Available

    1993-09-01

    This report documents activities of decontamination and decommissioning at ORNL. Topics discussed include general problems, waste types, containment, robotics automation and decontamination processes.

  2. Decontamination and Decommissioning of the Tokamak Fusion Test Reactor

    SciTech Connect

    E. Perry; J. Chrzanowski; K. Rule; M. Viola; M. Williams; R. Strykowsky

    1999-11-01

    The Tokamak Fusion Test Reactor (TFTR) is a one-of-a-kind, tritium-fueled fusion research reactor that ceased operation in April 1997. The Decontamination and Decommissioning (D and D) of the TFTR is scheduled to occur over a period of three years beginning in October 1999. This is not a typical Department of Energy D and D Project where a facility is isolated and cleaned up by ''bulldozing'' all facility and hardware systems to a greenfield condition. The mission of TFTR D and D is to: (a) surgically remove items which can be re-used within the DOE complex, (b) remove tritium contaminated and activated systems for disposal, (c) clear the test cell of hardware for future reuse, (d) reclassify the D-site complex as a non-nuclear facility as defined in DOE Order 420.1 (Facility Safety) and (e) provide data on the D and D of a large magnetic fusion facility. The 100 cubic meter volume of the donut-shaped reactor makes it the second largest fusion reactor in the world. The record-breaking deuterium-tritium experiments performed on TFTR resulted in contaminating the vacuum vessel with tritium and activating the materials with 14 Mev neutrons. The total tritium content within the vessel is in excess of 7,000 Curies while dose rates approach 75 mRem/hr. These radiological hazards along with the size and shape of the Tokamak present a unique and challenging task for dismantling.

  3. Ecological risk assessment of a decommissioned military base

    SciTech Connect

    Starodub, M.E.; Feniak, N.A.; Willes, R.F.; Moore, C.E.; Mucklow, L.; Marshall, L.

    1995-12-31

    The ecological health risks to selected terrestrial animals at a decommissioned military base in Atlantic Canada have been assessed. Areas of the base varied in terms of terrain, ground cover, as well as types and extent of contamination, dependent on former uses of the sites. Analysis of surficial soils, sediments, water and fish tissue at the base indicated contamination by metals, PCBs, and various petroleum products and their constituents. Identification of chemicals of concern was based on these analyses, in conjunction with detailed chemical selection procedures. Exposures to chemicals of concern for ecological receptors were assessed in one of two ways. The exposures of moose, snowshoe hare and meadow vole were estimated in areas with surficial contamination, based on expected exposures to environmental media via oral inhalation, and dermal routes of exposure. For two top predators (mink and bald-headed eagle), exposures to bioaccumulative chemicals (cadmium, lead, mercury and PCBs) via transport through the aquatic and/or terrestrial foodchain were estimated. A toxicological assessment was conducted for the chemicals of concern, to yield exposure limits derived from governmental regulations or developed based on no-observed-effect-levels (NOELs) reported in scientifically sound toxicological assays in relevant species. The risk evaluation of each chemical of concern was conducted as a comparison of the estimated total exposures to the exposure limits derived for the selected ecological receptors.

  4. Decommissioning of the High Flux Beam Reactor at Brookhaven Lab

    SciTech Connect

    Hu, J. P.; Reciniello, R. N.; Holden, N. E.

    2011-05-27

    The High Flux Beam Reactor at the Brookhaven National Laboratory was a heavy water cooled and moderated reactor that achieved criticality on October 31, 1965. It operated at a power level of 40 mega-watts. An equipment upgrade in 1982 allowed operations at 60 mega-watts. After a 1989 reactor shutdown to reanalyze safety impact of a hypothetical loss of coolant accident, the reactor was restarted in 1991 at 30 mega-watts. The HFBR was shutdown in December 1996 for routine maintenance and refueling. At that time, a leak of tritiated water was identified by routine sampling of ground water from wells located adjacent to the reactor’s spent fuel pool. The reactor remained shutdown for almost three years for safety and environmental reviews. In November 1999 the United States Department of Energy decided to permanently shutdown the HFBR. The decontamination and decommissioning of the HFBR complex, consisting of multiple structures and systems to operate and maintain the reactor, were complete in 2009 after removing and shipping off all the control rod blades. The emptied and cleaned HFBR dome which still contains the irradiated reactor vessel is presently under 24/7 surveillance for safety. Details of the HFBR cleanup conducted during 1999-2009 will be described in the paper.

  5. Action Memorandum for Decommissioning of TAN-607 Hot Shop Area

    SciTech Connect

    M. A. Pinzel

    2007-05-01

    The Department of Energy is documenting the selection of an alternative for the TAN-607 Hot Shop Area using a Comprehensive Environmental Response, Compensation, and Liability Act non-time-critical removal action (NTCRA). The scope of the removal action is limited to TAN-607 Hot Shop Area. An engineering evaluation/cost analysis (EE/CA) has assisted the Department of Energy Idaho Operations Office in identifuomg the most effective method for performing the decommissioning of this structure whose mission has ended. TAN-607 Hot Shop Area is located at Test Area North Technical Support Facility within the Idaho National Laboratory Site. The selected alternative consists of demolishing the TAN-607 aboveground structures and components, removing belowground noninert components (e.g. wood products), and removing the radiologically contaminated debris that does not meet remedial action objectives (RAOs), as defined in the Record of Decision Amendment for the V-Tanks and Explanation of Significant Differences for the PM-2A Tanks at Test Area North, Operable Unit 1-10.

  6. UK contractors' experience of management of tritium during decommissioning projects

    SciTech Connect

    Green, Tommy; Stevens, Keith; Heaney, John; Murray, Alan; Warwick, Phil; Croudace, Ian

    2007-07-01

    Available in abstract form only. Full text of publication follows: This paper provides an account of the tritium management experience of a UK decommissioning and remediation contracting organisation (NUKEM Limited), supported by a specialist radio-analysis organisation (GAU-Radioanalytical). This experience was gained during the execution of projects which involved the characterisation and remediation of facilities which had previously been used for tritium work and were contaminated with tritium. The emphasis of the paper is on the characterisation (sampling and analysis) of tritium. An account is given of the development of a methodology to improve the accuracy of tritium characterisation. The improved methodology evolved from recognition of the need to minimise tritium losses during sampling, storage, transport and preparation for analysis. These improvements were achieved in a variety of ways, including use of cold and dry sampling techniques in preference to hot or wet ones and freezing relevant samples during storage and transport. The major benefit was an improvement in the accuracy and reliability of the analyses results, essential for proper categorisation, sentencing and future management of tritiated waste. (authors)

  7. Geophysics: Building E5375 decommissioning, Aberdeen Proving Ground

    SciTech Connect

    McGinnis, M.G.; McGinnis, L.D.; Miller, S.F.; Thompson, M.D.

    1992-08-01

    Building E5375 was one of ten potentially contaminated sites in the Canal Creek area of the Edgewood section of Aberdeen Proving Ground examined by a geophysical team from Argonne National Laboratory in April and May 1992. Noninvasive geophysical surveys, including magnetics, electrical resistivity, and ground-penetrating radar (GPR), were conducted around the perimeter of the building to guide a sampling program prior to decommissioning and dismantling. Several anomalies wear, noted: (1) An underground storage tank located 25 ft east of Building E5375 was identified with magnetic, resistivity, and GPR profiling. (2) A three-point resistivity anomaly, 12 ft east of the northeast comer of Building E5374 (which borders Building E5375) and 5 ft south of the area surveyed with the magnetometer, may be caused by another underground storage tank. (3) A 2,500-gamma magnetic anomaly near the northeast corner of the site has no equivalent resistivity anomaly, although disruption in GPR reflectors was observed. (4) A one-point magnetic anomaly was located at the northeast comer, but its source cannot be resolved. A chaotic reflective zone to the east represents the radar signature of Building E5375 construction fill.

  8. Geophysics: Building E5440 decommissioning, Aberdeen Proving Ground

    SciTech Connect

    McGinnis, L.D.; Miller, S.F.; Thompson, M.D.; McGinnis, M.G.

    1992-11-01

    Building E5440 was one of ten potentially contaminated sites in the Canal Creek and Westwood areas of the Edgewood section of Aberdeen Proving Ground examined by a geophysical team from Argonne National Laboratory in April and May 1992. Noninvasive geophysical surveys, including magnetics, electrical resistivity, and ground-penetrating radar (GPR), were conducted around the perimeter of the building to guide a sampling program prior to decommissioning and dismantling. The results show several complex geophysical signatures. Isolated, one-point, magnetic anomalies surrounding the building may be associated with construction fill. A 10-ft-wide band of strongly magnetic positive anomalies bordering the north side of the building obliterates small magnetic sources that might otherwise be seen. A prominent magnetic nose'' extending northward from this band toward a standpipe at 100N,63E may be connected to an underground tank. The southeast corner of the site is underlain by a rectangular, magnetized source associated with strong radar images. A magnetic lineament extending south from the anomaly may be caused by a buried pipe; the anomaly itself may be caused by subsurface equipment associated with a manhole or utility access pit. A 2,500-gamma, positive magnetic anomaly centered at 0N,20E, which is also the location of a 12 [Omega]-m resistivity minimum, may be caused by a buried vault. It appears on radar imaging as a strong reflector.

  9. Geophysics: Building E5282 decommissioning, Aberdeen Proving Ground

    SciTech Connect

    Thompson, M.D.; McGinnis, M.G.; McGinnis, L.D.; Miller, S.F.

    1992-08-01

    This report discusses Building E5282 which was one of 10 potentially contaminated sites in the Canal Creek area of the Edgewood section of Aberdeen Proving Ground examined by a geophysical team from Argonne National Laboratory in April and May of 1992. Noninvasive geophysical surveys, including magnetics, electrical resistivity, and ground-penetrating radar (GPR), were conducted around the perimeter of the building to guide a sampling program prior to decommissioning and dismantling. Magnetic surveys identified small, complicated, multiple anomalies west, north, and northeast of the building that may be caused by construction fill. Two underground storage tanks, at the northeast and southeast corners, were identified. A large magnetic anomaly complex east of the building was caused by aboveground pipes and unexploded ordnance fragments scattered at the surface. Electrical resistivity profiling showed a broad, conductive terrain superimposed over magnetic anomalies on the north and west. A broad, high-resistivity, nonmagnetic area centered 25 ft east of the building has an unknown origin, but it may be due to nonconductive organic liquids, construction fill, or a buried concrete slab; GPR imaging showed this area as a highly reflective zone at a depth of about 5 ft. The GPR data also showed a small-diameter pipe oriented north-south located east of the building.

  10. Assessment of strippable coatings for decontamination and decommissioning

    SciTech Connect

    Ebadian, M.A.

    1998-01-01

    Strippable or temporary coatings were developed to assist in the decontamination of the Three Mile Island (TMI-2) reactor. These coatings have become a viable option during the decontamination and decommissioning (D and D) of both US Department of Energy (DOE) and commercial nuclear facilities to remove or fix loose contamination on both vertical and horizontal surfaces. A variety of strippable coatings are available to D and D professionals. However, these products exhibit a wide range of performance criteria and uses. The Hemispheric Center for Environmental Technology (HCET) at Florida International University (FIU) was commissioned to perform a 2-year investigation into strippable coatings. This investigation was divided into four parts: (1) identification of commercially available strippable coating products; (2) survey of D and D professionals to determine current uses of these coatings and performance criteria; (3) design and implementation of a non-radiological testing program to evaluate the physical properties of these coatings; and (4) design and implementation of a radiological testing program to determine decontamination factors and effects of exposure to ionizing radiation. Activities during fiscal year 1997 are described.

  11. Geophysics: Building E5481 decommissioning, Aberdeen Proving Ground

    SciTech Connect

    Thompson, M.D.; McGinnis, M.G.; McGinnis, L.D.; Miller, S.F.

    1992-11-01

    Building E5481 is one of ten potentially contaminated sites in the Canal Creek and Westwood areas of the Edgewood section of Aberdeen Proving Ground examined by a geophysical team from Argonne National Laboratory in April and May of 1992. Noninvasive geophysical surveys, including magnetics, electrical resistivity, and ground-penetrating radar, were conducted around the perimeter of the building to guide a sampling program prior to decommissioning and dismantling. The building is located on the northern margin of a landfill that was sited in a wetland. The large number of magnetic sources surrounding the building are believed to be contained in construction fill that had been used to raise the grade. The smaller anomalies, for the most part, are not imaged with ground radar or by electrical profiling. A conductive zone trending northwest to southeast across the site is spatially related to an old roadbed. Higher resistivity areas in the northeast and east are probably representive of background values. Three high-amplitude, positive, rectangular magnetic anomalies have unknown sources. The features do not have equivalent electrical signatures, nor are they seen with radar imaging.

  12. Geophysics: Building E5190 decommissioning, Aberdeen Proving Ground

    SciTech Connect

    Miller, S.F.; Thompson, M.D.; McGinnis, M.G.; McGinnis, L.D.

    1992-07-01

    Building E5190 is one of ten potentially contaminated sites in the Canal Creek area of the Edgewood section of Aberdeen Proving Ground examined by a geophysical team from Argonne National Laboratory in April and May 1992. A noninvasive geophysical survey, including the complementary technologies of magnetics, electrical resistivity, and ground-penetrating radar, was conducted around the perimeter as a guide to developing a sampling and monitoring program prior to decommissioning and dismantling the building. The magnetics surveys indicated that multistation, positive magnetic sources are randomly distributed north and west of the building. Two linear trends were noted: one that may outline buried utility lines and another that is produced by a steel-covered trench. The resistivity profiling indicated three conductive zones: one due to increased moisture in a ditch, one associated with buried utility lines, and a third zone associated with the steel-covered trench. Ground-penetrating radar imaging detected two significant anomalies, which were correlated with small-amplitude magnetic anomalies. The objectives of the study -- to detect and locate objects and to characterize a located object were achieved.

  13. Safety analysis factors for environmental restoration and decontamination and decommissioning

    SciTech Connect

    Ellingson, D.R.

    1993-04-01

    Environmental restoration (ER) and facility decontamination/decommissioning (D&D) operations can be grouped into two general categories. ``Nonstationary cleanup`` or simply ``cleanup`` activities are where the operation must relocate to the site of new contaminated material at the completion of each task (i.e., the operation moves to the contaminated material). ``Stationary production`` or simply ``production`` activities are where the contaminated material is moved to a centralized location (i.e., the contaminated material is moved to the operation) for analysis, sorting, treatment, storage, and disposal. This paper addresses the issue of nonstationary cleanup design. The following are the specific assigned action items: Collect and compile a list of special safety-related ER/D&D design factors, especially ones that don`t follow DOE Order 6430.1A requirements. Develop proposal of what makes sense to recommend to designers; especially consider recommendations for short-term projects. Present proposal at the January meeting. To achieve the action items, applicable US Department of Energy (DOE) design requirements, and cleanup operations and differences from production activities are reviewed and summarized; basic safety requirements influencing design are summarized; and finally, approaches, considerations, and methods for safe, cost-effective design of cleanup activities are discussed.

  14. The Windscale Advanced Gas Cooled Reactor (WAGR) Decommissioning Project A Close Out Report for WAGR Decommissioning Campaigns 1 to 10 - 12474

    SciTech Connect

    Halliwell, Chris

    2012-07-01

    The reactor core of the Windscale Advanced Gas-Cooled Reactor (WAGR) has been dismantled as part of an ongoing decommissioning project. The WAGR operated until 1981 as a development reactor for the British Commercial Advanced Gas cooled Reactor (CAGR) power programme. Decommissioning began in 1982 with the removal of fuel from the reactor core which was completed in 1983. Subsequently, a significant amount of engineering work was carried out, including removal of equipment external to the reactor and initial manual dismantling operations at the top of the reactor, in preparation for the removal of the reactor core itself. Modification of the facility structure and construction of the waste packaging plant served to provide a waste route for the reactor components. The reactor core was dismantled on a 'top-down' basis in a series of 'campaigns' related to discrete reactor components. This report describes the facility, the modifications undertaken to facilitate its decommissioning and the strategies employed to recognise the successful decommissioning of the reactor. Early decommissioning tasks at the top of the reactor were undertaken manually but the main of the decommissioning tasks were carried remotely, with deployment systems comprising of little more than crane like devices, intelligently interfaced into the existing structure. The tooling deployed from the 3 tonne capacity (3te) hoist consisted either purely mechanical devices or those being electrically controlled from a 'push-button' panel positioned at the operator control stations, there was no degree of autonomy in the 3te hoist or any of the tools deployed from it. Whilst the ATC was able to provide some tele-robotic capabilities these were very limited and required a good degree of driver input which due to the operating philosophy at WAGR was not utilised. The WAGR box proved a successful waste package, adaptable through the use of waste box furniture specific to the waste-forms generated throughout

  15. Trend of earlier spring in central Europe continued

    NASA Astrophysics Data System (ADS)

    Ungersböck, Markus; Jurkovic, Anita; Koch, Elisabeth; Lipa, Wolfgang; Scheifinger, Helfried; Zach-Hermann, Susanne

    2013-04-01

    Modern phenology is the study of the timing of recurring biological events in the animal and plant world, the causes of their timing with regard to biotic and abiotic forces, and the interrelation among phases of the same or different species. The relationship between phenology and climate explains the importance of plant phenology for Climate Change studies. Plants require light, water, oxygen mineral nutrients and suitable temperature to grow. In temperate zones the seasonal life cycle of plants is primarily controlled by temperature and day length. Higher spring air temperatures are resulting in an earlier onset of the phenological spring in temperate and cool climate. On the other hand changes in phenology due to climate change do have impact on the climate system itself. Vegetation is a dynamic factor in the earth - climate system and has positive and negative feedback mechanisms to the biogeochemical and biogeophysical fluxes to the atmosphere Since the mid of the 1980s spring springs earlier in Europe and autumn is shifting back to the end of the year resulting in a longer vegetation period. The advancement of spring can be clearly attributed to temperature increase in the months prior to leaf unfolding and flowering, the timing of autumn is more complex and cannot easily be attributed to one or some few parameters. To demonstrate that the observed advancement of spring since the mid of 1980s is pro-longed in 2001 to 2010 and the delay of fall and the lengthening of the growing season is confirmed in the last decade we picked out several indicator plants from the PEP725 database www.pep725.eu. The PEP725 database collects data from different European network operators and thus offers a unique compilation of phenological observations; the database is regularly updated. The data follow the same classification scheme, the so called BBCH coding system so they can be compared. Lilac Syringa vulgaris, birch Betula pendula, beech Fagus and horse chestnut Aesculus

  16. Spring for It: First Novels

    ERIC Educational Resources Information Center

    Hoffert, Barbara

    2010-01-01

    How do publishers describe the first novels they will be releasing this spring and summer? "Amazing," "fabulous," and "unique" are words that pop up frequently, though hats off to one publicist forthright or cheeky enough to call a work "weird Western/horror." The proof of such praise is in the reading, but why not check out this preview of first…

  17. A Breath of Spring Air

    ERIC Educational Resources Information Center

    Grady, Marilyn L.

    2009-01-01

    The most promising sights of spring in Nebraska this year were two conferences for women. One event, sponsored by Metropolitan Community College in Omaha, was a Women's History Month Tea. A second conference was the meeting of the Nebraska Women in Higher Education. These two events suggest that there is a continuing interest in women's leadership…

  18. NOVA Spring 1999 Teacher's Guide.

    ERIC Educational Resources Information Center

    Colombo, Luann; Ransick, Kristina; Recio, Belinda

    This teacher's guide complements six programs that aired on the Public Broadcasting System (PBS) in the spring of 1999. Programs include: (1) "Surviving AIDS"; (2) "Secrets of Making Money"; (3) "Escape!: Fire"; (4) "Escape!: Car Crash"; (5) "Volcanoes of the Deep"; and (6) "Odyssey of Life: Part 1. The Ultimate Journey". It provides activity…

  19. Registration of 'Rollag' spring wheat

    Technology Transfer Automated Retrieval System (TEKTRAN)

    Fusarium head blight (FHB) (caused primarily by Fusarium graminearum Schwabe) is a disease that annually threatens wheat (Triticum aestivum L.) grown in the northern plains of the United States. Resistance to this disease is a high priority trait in the University of Minnesota’s spring wheat breedi...

  20. Research Synopsis: Spring 1983 Retention.

    ERIC Educational Resources Information Center

    Peralta Community Coll. District, Oakland, CA. Office of Research, Planning and Development.

    An analysis of spring 1983 retention rates and grade distributions within the Peralta Community College District (PCCD) revealed: (1) College of Alameda had the highest successful retention rate in the PCCD, defined as the total of all students who completed the term with a grade of A, B, C, D, or CR (credit); (2) the PCCD's successful retention…

  1. Voronoi Diagrams and Spring Rain

    ERIC Educational Resources Information Center

    Perham, Arnold E.; Perham, Faustine L.

    2011-01-01

    The goal of this geometry project is to use Voronoi diagrams, a powerful modeling tool across disciplines, and the integration of technology to analyze spring rainfall from rain gauge data over a region. In their investigation, students use familiar equipment from their mathematical toolbox: triangles and other polygons, circumcenters and…

  2. NOVA Spring 2000 Teacher's Guide.

    ERIC Educational Resources Information Center

    Colombo, Luann; Gregoire, Tanya; Ransick, Kristina; Sammons, Fran Lyons; Sammons, James

    This teacher's guide complements six programs that aired on the Public Broadcasting System (PBS) in the spring of 2000. Programs include: (1) "Lost on Everest"; (2) "Lost Tribes of Israel"; (3) "Crocodiles"; (4) "Lost at Sea: The Search for Longitude"; (5) "Global Warming"; and (6) "Secrets of Lost Empires". It provides activity set-ups related to…

  3. The Forced Soft Spring Equation

    ERIC Educational Resources Information Center

    Fay, T. H.

    2006-01-01

    Through numerical investigations, this paper studies examples of the forced Duffing type spring equation with [epsilon] negative. By performing trial-and-error numerical experiments, the existence is demonstrated of stability boundaries in the phase plane indicating initial conditions yielding bounded solutions. Subharmonic boundaries are…

  4. Community Needs Assessment, Spring 1982.

    ERIC Educational Resources Information Center

    Dennis-Rounds, Jan

    In Spring 1982, a districtwide survey was conducted by Cerritos College (CC) to assess the educational needs of the surrounding community. Residents were asked to provide demographic information and respond to questions about their awareness of the college, their perception and evaluation of various CC roles, and their preferences for courses and…

  5. Finding Spring on Planet X

    ERIC Educational Resources Information Center

    Simoson, Andrew J.

    2007-01-01

    For a given orbital period and eccentricity, we determine the maximum time lapse between the winter solstice and the spring equinox on a planet. In addition, given an axial precession path, we determine the effects on the seasons. This material can be used at various levels to illustrate ideas such as periodicity, eccentricity, polar coordinates,…

  6. Carnivorous arthropods after spring flood

    Technology Transfer Automated Retrieval System (TEKTRAN)

    Spring flooding is a common practice in Wisconsin cranberries, but flooding as insect control produces variable results among marshes. This project is aimed at figuring out why it works, and why it sometimes doesn’t. We have focused on tracking arthropod populations to explain the observed patterns ...

  7. The Forced Hard Spring Equation

    ERIC Educational Resources Information Center

    Fay, Temple H.

    2006-01-01

    Through numerical investigations, various examples of the Duffing type forced spring equation with epsilon positive, are studied. Since [epsilon] is positive, all solutions to the associated homogeneous equation are periodic and the same is true with the forcing applied. The damped equation exhibits steady state trajectories with the interesting…

  8. Radioactive Waste Management and Nuclear Facility Decommissioning Progress in Iraq - 13216

    SciTech Connect

    Al-Musawi, Fouad; Shamsaldin, Emad S.; Jasim, Hadi; Cochran, John R.

    2013-07-01

    Management of Iraq's radioactive wastes and decommissioning of Iraq's former nuclear facilities are the responsibility of Iraq's Ministry of Science and Technology (MoST). The majority of Iraq's former nuclear facilities are in the Al-Tuwaitha Nuclear Research Center located a few kilometers from the edge of Baghdad. These facilities include bombed and partially destroyed research reactors, a fuel fabrication facility and radioisotope production facilities. Within these facilities are large numbers of silos, approximately 30 process or waste storage tanks and thousands of drums of uncharacterised radioactive waste. There are also former nuclear facilities/sites that are outside of Al-Tuwaitha and these include the former uranium processing and waste storage facility at Jesira, the dump site near Adaya, the former centrifuge facility at Rashdiya and the former enrichment plant at Tarmiya. In 2005, Iraq lacked the infrastructure needed to decommission its nuclear facilities and manage its radioactive wastes. The lack of infrastructure included: (1) the lack of an organization responsible for decommissioning and radioactive waste management, (2) the lack of a storage facility for radioactive wastes, (3) the lack of professionals with experience in decommissioning and modern waste management practices, (4) the lack of laws and regulations governing decommissioning or radioactive waste management, (5) ongoing security concerns, and (6) limited availability of electricity and internet. Since its creation eight years ago, the MoST has worked with the international community and developed an organizational structure, trained staff, and made great progress in managing radioactive wastes and decommissioning Iraq's former nuclear facilities. This progress has been made, despite the very difficult implementing conditions in Iraq. Within MoST, the Radioactive Waste Treatment and Management Directorate (RWTMD) is responsible for waste management and the Iraqi Decommissioning

  9. Normal crop calendars. Volume 2: The spring wheat states of Minnesota, Montana, North Dakota, and South Dakota

    NASA Technical Reports Server (NTRS)

    West, W. L., III (Principal Investigator)

    1980-01-01

    The state crop calendars for the principal spring wheat producing states within the United States are presented. These crop calendars are an update of those produced for the large area crop inventory experiment multilabeling task during 1978and are compiled for the foreign commodity production forecasting (FCPF) project of the agriculture and resources inventory surveys through aerospace remote sensing program.

  10. Archaeal Nitrification in Hot Springs

    NASA Astrophysics Data System (ADS)

    Richter, A.; Daims, H.; Reigstad, L.; Wanek, W.; Wagner, M.; Schleper, C.

    2006-12-01

    Biological nitrification, i.e. the aerobic conversion of ammonia to nitrate via nitrite, is a major component of the global nitrogen cycle. Until recently, it was thought that the ability to aerobically oxidize ammonia was confined to bacteria of the phylum Proteobacteria. However, it has recently been shown that Archaea of the phylum Crenarchaeota are also capable of ammonia oxidation. As many Crenarchaeota are thermophilic or hyperthermophilic, and at least some of them are capable of ammonia oxidation we speculated on the existence of (hyper)thermophilic ammonia-oxidizing archaea (AOA). Using PCR primers specifically targeting the archaeal ammonia monooxygenase (amoA) gene, we were indeed able to confirm the presence of such organisms in several hot springs in Reykjadalur, Iceland. These hot springs exhibited temperatures well above 80 °C and pH values ranging from 2.0 to 4.5. To proof that nitrification actually took place under these extreme conditions, we measured gross nitrification rates by the isotope pool dilution method; we added 15N-labelled nitrate to the mud and followed the dilution of the label by nitrate production from ammonium either in situ (incubation in the hot spring) or under controlled conditions in the laboratory (at 80 °C). The nitrification rates in the hot springs ranged from 0.79 to 2.22 mg nitrate-N per L of mud and day. Controls, in which microorganisms were killed before the incubations, demonstrated that the nitrification was of biological origin. Addition of ammonium increased the gross nitrification rate approximately 3-fold, indicating that the nitrification was ammonium limited under the conditions used. Collectively, our study provides evidence that (1) AOA are present in hot springs and (2) that they are actively nitrifying. These findings have major implications for our understanding of nitrogen cycling of hot environments.

  11. Implementation of the six grumbly priorities during decommissioning activities at the Idaho National Engineering Laboratory

    SciTech Connect

    Perry, E.F.; Mikkola, A.W.

    1994-12-31

    Decommissioning work continues to play an important role in the long-term activities of the Idaho National Engineering Laboratory (INEL). Recent completion of the SPERT IV waste tank project marked the 25th facility to be decommissioned at the INEL. These facilities have either been totally removed and the area restored to a natural condition, or the buildings decontaminated and returned to further use, The long-term goal for the INEL decontamination and decommissioning (D&D) program is to complete decommissioning of its surplus facilities in a safe, cost-effective, and environmentally sound manner. The INEL D&D program was established in late 1977 and has remained active since that time. The types of facilities decommissioned to date range from concrete storage pads to complex reactor and fuel-reprocessing facilities. Disassembly techniques have ranged from plasma torches, to headache balls, to linear-shaped high explosives. Late last year, Thomas P. Grumbly, Assistant Secretary for Environmental Management, U.S. Department of Energy (DOE), issued six priorities to guide the implementation of environmental management activities at DOE sites.

  12. Guide for radiological characterization and measurements for decommissioning of US Department of Energy surplus facilities

    SciTech Connect

    Denahm, D. H.; Barnes, M. G.; Jaquish, R. E.; Corley, J. P.; Gilbert, R. O.; Hoenes, G. R.; Jamison, J. D.; McMurray, B. J.; Watson, E. C.

    1983-08-01

    This Guide describes the elements of radiological characterization at DOE excess facilities in preparation for, during, and subsequent to decommissioning operations. It is the intent of this Guide and accompanying appendices to provide the reader (user) with sufficient information to carry out that task with a minimum of confusion and to provide a uniform basis for evaluating site conditions and verifying that decommissioning operations are conducted according to a specific plan. Some areas of particular interest in this Guide are: the need to involve appropriate staff from the affected states in the early planning stages of decommissioning; the need for and suggested methods of radiological site characterization to complete a decommissioning project, including: historical surveys, environmental pathway analyses, statistical sampling design, and choosing appropriate instrumentation and measurements; the need for and emphasis on quality assurance, documentation and records retention; the establishment of a Design Objective approach to applying site-specific contamination limits based on the ALARA philosophy; the establishment of a ''de minimis'' or minimum dose level of concern for decommissioning operations based on existing standards, experience and ALARA considerations.

  13. Decommissioning of a mixed oxide fuel fabrication plant at Winfrith Technolgy Centre

    SciTech Connect

    Pengelly, M.G.A.

    1994-01-01

    The Alpha Materials Laboratory (Building A52) at Winfrith contained a mixed oxide fuel fabrication plant which had a capability of producing 10 te/yr of pelleted/compacted fuel and was in operation from 1962 until 1980, when the requirement for this type of fuel in the UK diminished, and the plant became surplus to requirements. A program to develop decommissioning techniques for plutonium plants was started in 1983, addressing the following aspects of alpha plant decommissioning: (1) Re-usable containment systems, (2) Strippable coating technology, (3) Mobile air filtration plant, (4) Size reduction primarily using cold cutting, (5) techniques, (6) Waste packing, and (7) Alpha plant decommissioning methodology. The technology developed has been used to safely and efficiently decommission radioactive plant and equipment including Pu contaminated glove boxes. (63 glove boxes to date) The technology has been widely adopted in the United Kingdom and elsewhere. This paper outlines the general strategies adopted and techniques used for glove box decommissioning in building A52.

  14. 30 CFR 285.529 - Can I use a lease- or grant-specific decommissioning account to meet the financial assurance...

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... Treasury securities and their collateral value are determined in accordance with 31 CFR part 203... decommissioning account to meet the financial assurance requirements related to decommissioning? 285.529 Section... CONTINENTAL SHELF Payments and Financial Assurance Requirements Requirements for Financial...

  15. Decommissioning and PIE of the MEGAPIE spallation target

    SciTech Connect

    Latge, C.; Henry, J.; Wohlmuther, M.; Dai, Y.; Gavillet, D.; Hammer, B.; Heinitz, S.; Neuhausen, J.; Schumann, D.; Thomsen, K.; Tuerler, A.; Wagner, W.; Gessi, A.; Guertin, A.; Konstantinovic, M.; Lindau, R.; Maloy, S.; Saito, S.

    2013-07-01

    A key experiment in the Accelerated Driven Systems roadmap, the MEGAwatt PIlot Experiment (MEGAPIE) (1 MW) was initiated in 1999 in order to design and build a liquid lead-bismuth spallation target, then to operate it into the Swiss spallation neutron facility SINQ at Paul Scherrer Institute. The target has been designed, manufactured, and tested during integral tests, before irradiation carried out end of 2006. During irradiation, neutron and thermo hydraulic measurements were performed allowing deep interpretation of the experiment and validation of the models used during design phase. The decommissioning, Post Irradiation Examinations and waste management phases were defined properly. The phases dedicated to cutting, sampling, cleaning, waste management, samples preparation and shipping to various laboratories were performed by PSI teams: all these phases constitute a huge work, which allows now to perform post-irradiation examination (PIE) of structural material, irradiated in relevant conditions. Preliminary results are presented in the paper, they concern chemical characterization. The following radio-nuclides have been identified by γ-spectrometry: {sup 60}Co, {sup 101}Rh, {sup 102}Rh, {sup 108m}Ag, {sup 110m}Ag, {sup 133}Ba, {sup 172}Hf/Lu, {sup 173}Lu, {sup 194}Hg/Au, {sup 195}Au, {sup 207}Bi. For some of these nuclides the activities can be easily evaluated from γ-spectrometry results ({sup 207}Bi, {sup 194}Hg/Au), while other nuclides can only be determined after chemical separations ({sup 108m}Ag, {sup 110m}Ag, {sup 195}Au, {sup 129}I, {sup 36}Cl and α-emitting {sup 208-210}Po). The concentration of {sup 129}I is lower than expected. The chemical analysis already performed on spallation and corrosion products in the lead-bismuth eutectic (LBE) are very relevant for further applications of LBE as a spallation media and more generally as a coolant.

  16. Idaho National Engineering Laboratory decontamination and decommissioning robotics development program

    SciTech Connect

    McKay, M.D.

    1993-04-01

    As part of the Idaho National Engineering Laboratory (INEL) Robotics Technology Development Program (RTDP) Decontamination & Decommissioning (D&D) robotics program, a task was designed to integrate the plasma arc cutting technology being developed under the Waste Facility Operations (WFO) robotics program into D&D cutting applications. The plasma arc cutting technology is based upon the use of a high energy plasma torch to cut metallic objects. Traditionally, D&D workers removing equipment and processes from a facility have used plasma arc cutting to accomplish this task. The worker is required to don a protective suit to shield from the high electromagnetic energy released from the cutting operation. Additionally, the worker is required to don protective clothing to shield against the radioactive materials and contamination. This protective clothing can become restrictive and cumbersome to work in. Because some of the work areas contain high levels of radiation, the worker is not allowed to dwell in the environment for sustained periods of time. To help alleviate some of the burdens required to accomplish this task, reduce or eliminate the safety hazardous to the worker, and reduce the overall cost of remediation, a program was established though the Office of Technology Development (OTD) to design and develop a robotic system capable of performing cutting operations using a plasma arc torch. Several D&D tasks were identified having potential for use of the plasma arc cutting technology. The tasks listed below were chosen to represent common D&D type activities where the plasma arc cutting technology can be applied.

  17. Reuse of Concrete within DOE from Decontamination and Decommissioning Projects

    SciTech Connect

    Tripp, Julia Lynn; Meservey, Richard Harlan; Smith, Anthony Mactier; Chen, S. Y.; Kamboj, S.

    2000-09-01

    A protocol has been developed for use in the disposition of concrete from Decontamination and Decommissioning (D&D) projects. The purpose of this protocol is to assist U.S. Department of Energy (DOE) sites in releasing concrete for re-use within the DOE complex. Current regulations allow sites to release surface-contaminated materials if they contain very low amounts of radioactivity and to possibly release materials with volumetric contamination, or higher levels of surface contamination on a case-bycase basis. In all cases, an ALARA (as low as reasonably achievable) analysis that evaluates the risks of releasing volumetrically contaminated concrete or concrete with higher levels of surface contamination, is required. To evaluate the dose impacts of re-using radioactively contaminated material, the measured radiation levels (pCi/g or disintegrations per minute (dpm)/100 cm2) must be converted to the estimated dose (mrem/yr) that would be received by affected individuals. The dose depends on the amounts and types of isotopes present and the time, distance, and method of exposure (e.g., inhalation or external exposure). For each disposition alternative, the protocol provides a systematic method to evaluate the impact of the dose on affected individuals. The cost impacts of re-using concrete also need to be evaluated. They too depend on the disposition alternative and the extent and type of contamination. The protocol provides a method to perform a detailed analysis of these factors and evaluate the dose and cost impacts for various disposition alternatives. Once the dose and cost impacts of the various alternatives have been estimated, the protocol outlines the steps required to release and re-use the concrete material.

  18. DEVELOPMENT OF PERSONAL PROTECTIVE EQUIPMENT FOR DECONTAMINATION AND DECOMMISSIONING

    SciTech Connect

    M.A. Ebadian, Ph.D.

    1999-01-01

    The purpose of this one-year investigation is to perform a technology integration/search, thereby ensuring that the safest and most cost-effective options are developed and subsequently used during the deactivation and decommissioning (D&D) of U.S. Department of Energy Environmental Management (DOE-EM) sites. Issues of worker health and safety are the main concern, followed by cost. Two lines of action were explored: innovative Personal Cooling Systems (PCS) and Personal Monitoring Equipment (PME). PME refers to sensors affixed to the worker that warn of an approaching heat stress condition, thereby preventing it. Three types of cooling systems were investigated: Pre-Chilled or Forced-Air System (PCFA), Umbilical Fluid-Chilled System (UFCS), and Passive Vest System (PVS). Of these, the UFCS leads the way. The PVS or Gel pack vest lagged due to a limited cooling duration. And the PCFA or chilled liquid air supply was cumbersome and required an expensive and complex recharge system. The UFCS in the form of the Personal Ice Cooling System (PICS) performed exceptionally. The technology uses a chilled liquid circulating undergarment and a Personal Protective Equipment (PPE) external pump and ice reservoir. The system is moderately expensive, but the recharge is low-tech and inexpensive enough to offset the cost. There are commercially available PME that can be augmented to meet the DOE's heat stress alleviation need. The technology is costly, in excess of $4,000 per unit. Workers easily ignore the alarm. The benefit to health & safety is indirect so can be overlooked. A PCS is a more justifiable expenditure.

  19. DEACTIVATION AND DECOMMISSIONING (D AND D) TECHNOLOGY INTEGRATION

    SciTech Connect

    M.A. Ebadian, Ph.D.

    1999-01-01

    As part of the ongoing task of making Deactivation and Decommissioning (D&D) operations more efficient, this subtask has addressed the need to integrate existing characterization technologies with decontamination technologies in order to provide real-time data on the progress of contamination removal. Specifically, technologies associated with concrete decontamination and/or removal have been examined with the goal of integrating existing technologies and commercializing the resulting hybrid. The Department of Energy (DOE) has estimated that 23 million cubic meters of concrete will require disposition as 1200 buildings undergo the D&D process. All concrete removal to be performed will also necessitate extensive use of characterization techniques. The in-process characterization presents the most potential for improvement and cost-savings as compared to other types. Current methods for in-process characterization usually require cessation of work to allow for radiation surveys to assess the rate of decontamination. Combining together decontamination and characterization technologies would allow for in-process evaluation of decontamination efforts. Since the present methods do not use in-process evaluations for the progress of decontamination, they may allow for ''overremoval'' of materials (removal of contaminated along with non-contaminated materials). Overremoval increases the volume of waste and therefore the costs associated with disposal. Integrating technologies would facilitate the removal of only contaminated concrete and reduce the total volume of radioactive waste, which would be disposed of. This would eventually ensure better productivity and time savings. This project presents a general procedure to integrate the above-mentioned technologies in the form of the Technology Integration Module (TIM) along with combination lists of commercially available decontamination and characterization technologies. The scope of the project has also been expanded by FIU

  20. Mobile worksystems for decontamination and decommissioning operations. Final report

    SciTech Connect

    1997-02-01

    This project is an interdisciplinary effort to develop effective mobile worksystems for decontamination and decommissioning (D&D) of facilities within the DOE Nuclear Weapons Complex. These mobile worksystems will be configured to operate within the environmental and logistical constraints of such facilities and to perform a number of work tasks. Our program is designed to produce a mobile worksystem with capabilities and features that are matched to the particular needs of D&D work by evolving the design through a series of technological developments, performance tests and evaluations. The Phase I effort was based on a robot called the Remote Work Vehicle (RWV) that was previously developed by CMU for use in D&D operations at the Three Mile Island Unit 2 Reactor Building basement. During Phase I of this program, the RWV was rehabilitated and upgraded with contemporary control and user interface technologies and used as a testbed for remote D&D operations. We established a close working relationship with the DOE Robotics Technology Development Program (RTDP). In the second phase, we designed and developed a next generation mobile worksystem, called Rosie, and a semi-automatic task space scene analysis system, called Artisan, using guidance from RTDP. Both systems are designed to work with and complement other RTDP D&D technologies to execute selective equipment removal scenarios in which some part of an apparatus is extricated while minimally disturbing the surrounding objects. RTDP has identified selective equipment removal as a timely D&D mission, one that is particularly relevant during the de-activation and de-inventory stages of facility transitioning as a means to reduce the costs and risks associated with subsequent surveillance and monitoring. In the third phase, we tested and demonstrated core capabilities of Rosie and Artisan; we also implemented modifications and enhancements that improve their relevance to DOE`s facility transitioning mission.

  1. Portrait of a Geothermal Spring, Hunter's Hot Springs, Oregon.

    PubMed

    Castenholz, Richard W

    2015-01-27

    Although alkaline Hunter's Hot Springs in southeastern Oregon has been studied extensively for over 40 years, most of these studies and the subsequent publications were before the advent of molecular methods. However, there are many field observations and laboratory experiments that reveal the major aspects of the phototrophic species composition within various physical and chemical gradients of these springs. Relatively constant temperature boundaries demark the upper boundary of the unicellular cyanobacterium, Synechococcus at 73-74 °C (the world-wide upper limit for photosynthesis), and 68-70 °C the upper limit for Chloroflexus. The upper limit for the cover of the filamentous cyanobacterium, Geitlerinema (Oscillatoria) is at 54-55 °C, and the in situ lower limit at 47-48 °C for all three of these phototrophs due to the upper temperature limit for the grazing ostracod, Thermopsis. The in situ upper limit for the cyanobacteria Pleurocapsa and Calothrix is at ~47-48 °C, which are more grazer-resistant and grazer dependent. All of these demarcations are easily visible in the field. In addition, there is a biosulfide production in some sections of the springs that have a large impact on the microbiology. Most of the temperature and chemical limits have been explained by field and laboratory experiments.

  2. Triangular springs for modeling nonlinear membranes.

    PubMed

    Delingette, Hervé

    2008-01-01

    This paper provides a formal connexion between springs and continuum mechanics in the context of one-dimensional and two-dimensional elasticity. In a first stage, the equivalence between tensile springs and the finite element discretization of stretching energy on planar curves is established. Furthermore, when considering a quadratic strain function of stretch, we introduce a new type of springs called tensile biquadratic springs. In a second stage, we extend this equivalence to non-linear membranes (St Venant-Kirchhoff materials) on triangular meshes leading to triangular biquadratic and quadratic springs. Those tensile and angular springs produce isotropic deformations parameterized by Young modulus and Poisson ratios on unstructured meshes in an efficient and simple way. For a specific choice of the Poisson ratio, 0.3, we show that regular spring-mass models may be used realistically to simulate a membrane behavior. Finally, the different spring formulations are tested in pure traction and cloth simulation experiments.

  3. 49 CFR 230.111 - Spring rigging.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... considered the top.) Broken springs not exceeding these requirements may be repaired by applying clips providing the clips can be made to remain in place; (2) Any spring with leaves excessively shifting in...

  4. 49 CFR 230.111 - Spring rigging.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... considered the top.) Broken springs not exceeding these requirements may be repaired by applying clips providing the clips can be made to remain in place; (2) Any spring with leaves excessively shifting in...

  5. 14 CFR 23.687 - Spring devices.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... STANDARDS: NORMAL, UTILITY, ACROBATIC, AND COMMUTER CATEGORY AIRPLANES Design and Construction Control Systems § 23.687 Spring devices. The reliability of any spring device used in the control system must be... unsafe flight characteristics....

  6. 14 CFR 23.687 - Spring devices.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... STANDARDS: NORMAL, UTILITY, ACROBATIC, AND COMMUTER CATEGORY AIRPLANES Design and Construction Control Systems § 23.687 Spring devices. The reliability of any spring device used in the control system must be... unsafe flight characteristics....

  7. 14 CFR 23.687 - Spring devices.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... STANDARDS: NORMAL, UTILITY, ACROBATIC, AND COMMUTER CATEGORY AIRPLANES Design and Construction Control Systems § 23.687 Spring devices. The reliability of any spring device used in the control system must be... unsafe flight characteristics....

  8. 14 CFR 23.687 - Spring devices.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... STANDARDS: NORMAL, UTILITY, ACROBATIC, AND COMMUTER CATEGORY AIRPLANES Design and Construction Control Systems § 23.687 Spring devices. The reliability of any spring device used in the control system must be... unsafe flight characteristics....

  9. Technology, Safety and Costs of Decommissioning a Reference Uranium Hexafluoride Conversion Plant

    SciTech Connect

    Elder, H. K.

    1981-10-01

    Safety and cost information is developed for the conceptual decommissioning of a commercial uranium hexafluoride conversion (UF{sub 6}) plant. Two basic decommissioning alternatives are studied to obtain comparisons between cost and safety impacts: DECON, and passive SAFSTOR. A third alternative, DECON of the plant and equipment with stabilization and long-term care of lagoon wastes. is also examined. DECON includes the immediate removal (following plant shutdown) of all radioactivity in excess of unrestricted release levels, with subsequent release of the site for public use. Passive SAFSTOR requires decontamination, preparation, maintenance, and surveillance for a period of time after shutdown, followed by deferred decontamination and unrestricted release. DECON with stabilization and long-term care of lagoon wastes (process wastes generated at the reference plant and stored onsite during plant operation} is also considered as a decommissioning method, although its acceptability has not yet been determined by the NRC. The decommissioning methods assumed for use in each decommissioning alternative are based on state-of-the-art technology. The elapsed time following plant shutdown required to perform the decommissioning work in each alternative is estimated to be: for DECON, 8 months; for passive SAFSTOR, 3 months to prepare the plant for safe storage and 8 months to accomplish deferred decontamination. Planning and preparation for decommissioning prior to plant shutdown is estimated to require about 6 months for either DECON or passive SAFSTOR. Planning and preparation prior to starting deferred decontamination is estimated to require an additional 6 months. OECON with lagoon waste stabilization is estimated to take 6 months for planning and about 8 months to perform the decommissioning work. Decommissioning cost, in 1981 dollars, is estimated to be $5.91 million for OECON. For passive SAFSTOR, preparing the facility for safe storage is estimated to cost $0

  10. Fram Strait Spring Ice Export and September Arctic Sea Ice

    NASA Astrophysics Data System (ADS)

    Smedsrud, Lars H.; Halvorsen, Mari H.; Stroeve, Julienne; Zhang, Rong; Kloster, Kjell

    2016-04-01

    The Arctic Basin exports between 600 000 - 1 million km² of it's sea ice cover southwards through Fram Strait each year, comparing to about 10% of the ice covered area inside the basin. During winter ice export results in growth of new and relatively thin ice inside the basin, while during summer or spring export contributes directly to open water further north. A new updated time series from 1935 to 2014 of Fram Strait sea ice area export shows that the long-term annual mean export is about 880,000 km², with large annual and decadal variability and no long-term trend over the past 80 years. Nevertheless, the last decade has witnessed increased annual ice export, with several years having annual ice export exceed 1 million km². Evaluating the trend onwards from 1979, when satellite based sea ice coverage became more readily available, reveals an increase in annual export of about +6% per decade. This increase is caused by higher southward ice drift speeds due to stronger southward geostrophic winds, largely explained by increasing surface pressure over Greenland. Spring and summer area export increased more (+11% per decade) than in autumn and winter. Contrary to the last decade the 1950 - 1970 period had low export during spring and summer, and mid-September sea ice extent was consistently higher than both before and after these decades. We thus find that export anomalies during spring have a clear influence on the following September sea ice extent in general, and that for the recent decade the export may be partially responsible for the accelerating decline in Arctic sea ice extent.

  11. 30 CFR 250.1006 - How must I decommission and take out of service a DOI pipeline?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... a DOI pipeline? 250.1006 Section 250.1006 Mineral Resources BUREAU OF SAFETY AND ENVIRONMENTAL... SHELF Pipelines and Pipeline Rights-of-Way § 250.1006 How must I decommission and take out of service a DOI pipeline? (a) The requirements for decommissioning pipelines are listed in § 250.1750...

  12. 30 CFR 250.1006 - How must I decommission and take out of service a DOI pipeline?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... a DOI pipeline? 250.1006 Section 250.1006 Mineral Resources BUREAU OF SAFETY AND ENVIRONMENTAL... SHELF Pipelines and Pipeline Rights-of-Way § 250.1006 How must I decommission and take out of service a DOI pipeline? (a) The requirements for decommissioning pipelines are listed in § 250.1750...

  13. 30 CFR 250.1006 - How must I decommission and take out of service a DOI pipeline?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... a DOI pipeline? 250.1006 Section 250.1006 Mineral Resources BUREAU OF SAFETY AND ENVIRONMENTAL... SHELF Pipelines and Pipeline Rights-of-Way § 250.1006 How must I decommission and take out of service a DOI pipeline? (a) The requirements for decommissioning pipelines are listed in § 250.1750...

  14. 30 CFR 250.1006 - How must I decommission and take out of service a DOI pipeline?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... a DOI pipeline? 250.1006 Section 250.1006 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT... OUTER CONTINENTAL SHELF Pipelines and Pipeline Rights-of-Way § 250.1006 How must I decommission and take out of service a DOI pipeline? (a) The requirements for decommissioning pipelines are listed in §...

  15. 30 CFR 285.902 - What are the general requirements for decommissioning for facilities authorized under my SAP, COP...

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... decommissioning for facilities authorized under my SAP, COP, or GAP? 285.902 Section 285.902 Mineral Resources... SAP, COP, or GAP? (a) Except as otherwise authorized by MMS under § 285.909, within 2 years following... under your SAP, COP, or GAP, you must submit a decommissioning application and receive approval from...

  16. 30 CFR 585.902 - What are the general requirements for decommissioning for facilities authorized under my SAP, COP...

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... decommissioning for facilities authorized under my SAP, COP, or GAP? 585.902 Section 585.902 Mineral Resources..., Inspections, and Facility Assessments for Activities Conducted Under SAPs, COPs and GAPs Decommissioning... authorized under my SAP, COP, or GAP? (a) Except as otherwise authorized by BOEM under § 585.909, within...

  17. 30 CFR 285.902 - What are the general requirements for decommissioning for facilities authorized under my SAP, COP...

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... decommissioning for facilities authorized under my SAP, COP, or GAP? 285.902 Section 285.902 Mineral Resources... facilities authorized under my SAP, COP, or GAP? (a) Except as otherwise authorized by MMS under § 285.909...) Before decommissioning the facilities under your SAP, COP, or GAP, you must submit a...

  18. 30 CFR 585.517 - How will BOEM determine the amounts of the supplemental and decommissioning financial assurance...

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ...; (iii) Other monetary obligations; and (iv) The estimated cost of facility decommissioning. ... decommissioning financial assurance requirements on estimates of the cost to meet all accrued lease obligations... the Government over the next 12 months; (2) Any past due rent and other payments; (3) Other...

  19. 30 CFR 585.517 - How will BOEM determine the amounts of the supplemental and decommissioning financial assurance...

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ...; (iii) Other monetary obligations; and (iv) The estimated cost of facility decommissioning. ... decommissioning financial assurance requirements on estimates of the cost to meet all accrued lease obligations... the Government over the next 12 months; (2) Any past due rent and other payments; (3) Other...

  20. 30 CFR 585.517 - How will BOEM determine the amounts of the supplemental and decommissioning financial assurance...

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ...; (iii) Other monetary obligations; and (iv) The estimated cost of facility decommissioning. ... decommissioning financial assurance requirements on estimates of the cost to meet all accrued lease obligations... the Government over the next 12 months; (2) Any past due rent and other payments; (3) Other...

  1. 75 FR 20582 - Record of Decision: Final Environmental Impact Statement for Decommissioning and/or Long-Term...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-04-20

    ... EIS (DOE/EIS-0226) issued on January 29, 2010 (75 FR 4803); comments received on the Final EIS; and... FR 5003), NRC prescribes the requirements for decommissioning WVDP. The decommissioning criteria..., 2001, DOE and NYSERDA announced (66 FR 15447) their intent to revise their strategy for completing...

  2. 10 CFR 70.38 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... premises are suitable for release in accordance with the criteria for decommissioning in 10 CFR part 20... decommissioning in 10 CFR part 20, subpart E; or (ii) Other information submitted by the licensee is sufficient to... 10 CFR part 20, subpart E. (4) Records required by § 70.51(b)(6) have been received....

  3. 10 CFR 40.42 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E or, for uranium milling... CFR part 20, subpart E or, for (uranium and thorium recovery) facilities, Criterion 6(6) of Appendix A... the premises are suitable for release in accordance with the criteria for decommissioning in 10...

  4. 10 CFR 40.42 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E or, for uranium milling... CFR part 20, subpart E or, for (uranium and thorium recovery) facilities, Criterion 6(6) of Appendix A... the premises are suitable for release in accordance with the criteria for decommissioning in 10...

  5. 10 CFR 70.38 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... premises are suitable for release in accordance with the criteria for decommissioning in 10 CFR part 20... decommissioning in 10 CFR part 20, subpart E; or (ii) Other information submitted by the licensee is sufficient to... 10 CFR part 20, subpart E. (4) Records required by § 70.51(b)(6) have been received....

  6. 10 CFR 72.54 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 10 CFR part 20, subpart E. The licensee shall, as appropriate— (i) Report levels of gamma radiation... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E; or (ii) Other information... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E. (3) Records required by §...

  7. 10 CFR 70.38 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... premises are suitable for release in accordance with the criteria for decommissioning in 10 CFR part 20... decommissioning in 10 CFR part 20, subpart E; or (ii) Other information submitted by the licensee is sufficient to... 10 CFR part 20, subpart E. (4) Records required by § 70.51(b)(6) have been received....

  8. 10 CFR 70.38 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... premises are suitable for release in accordance with the criteria for decommissioning in 10 CFR part 20... decommissioning in 10 CFR part 20, subpart E; or (ii) Other information submitted by the licensee is sufficient to... 10 CFR part 20, subpart E. (4) Records required by § 70.51(b)(6) have been received....

  9. 10 CFR 72.54 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 10 CFR part 20, subpart E. The licensee shall, as appropriate— (i) Report levels of gamma radiation... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E; or (ii) Other information... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E. (3) Records required by §...

  10. 10 CFR 40.42 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E or, for uranium milling... CFR part 20, subpart E or, for (uranium and thorium recovery) facilities, Criterion 6(6) of appendix A... the premises are suitable for release in accordance with the criteria for decommissioning in 10...

  11. 10 CFR 40.42 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E or, for uranium milling... CFR part 20, subpart E or, for (uranium and thorium recovery) facilities, Criterion 6(6) of Appendix A... the premises are suitable for release in accordance with the criteria for decommissioning in 10...

  12. 10 CFR 72.54 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 10 CFR part 20, subpart E. The licensee shall, as appropriate— (i) Report levels of gamma radiation... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E; or (ii) Other information... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E. (3) Records required by §...

  13. 10 CFR 40.42 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E or, for uranium milling... CFR part 20, subpart E or, for (uranium and thorium recovery) facilities, Criterion 6(6) of Appendix A... the premises are suitable for release in accordance with the criteria for decommissioning in 10...

  14. 10 CFR 72.54 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 10 CFR part 20, subpart E. The licensee shall, as appropriate— (i) Report levels of gamma radiation... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E; or (ii) Other information... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E. (3) Records required by §...

  15. 10 CFR 70.38 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... premises are suitable for release in accordance with the criteria for decommissioning in 10 CFR part 20... decommissioning in 10 CFR part 20, subpart E; or (ii) Other information submitted by the licensee is sufficient to... 10 CFR part 20, subpart E. (4) Records required by § 70.51(b)(6) have been received....

  16. 10 CFR 72.54 - Expiration and termination of licenses and decommissioning of sites and separate buildings or...

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 10 CFR part 20, subpart E. The licensee shall, as appropriate— (i) Report levels of gamma radiation... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E; or (ii) Other information... accordance with the criteria for decommissioning in 10 CFR part 20, subpart E. (3) Records required by §...

  17. 30 CFR 585.913 - What happens if I fail to comply with my approved decommissioning application?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... approved decommissioning application? 585.913 Section 585.913 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON... Application § 585.913 What happens if I fail to comply with my approved decommissioning application? If...

  18. 30 CFR 285.913 - What happens if I fail to comply with my approved decommissioning application?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... approved decommissioning application? 285.913 Section 285.913 Mineral Resources BUREAU OF OCEAN ENERGY MANAGEMENT, REGULATION, AND ENFORCEMENT, DEPARTMENT OF THE INTERIOR OFFSHORE RENEWABLE ENERGY ALTERNATE USES... Decommissioning Application § 285.913 What happens if I fail to comply with my approved...

  19. 30 CFR 250.1731 - Who is responsible for decommissioning an OCS facility subject to an Alternate Use RUE?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    .... See 30 CFR part 285, subpart J, for additional information concerning the decommissioning... CFR part 256 will remain responsible for decommissioning obligations that accrued before issuance of.... (c) If a lease issued under 30 CFR part 256 is cancelled or otherwise terminated under any...

  20. 30 CFR 250.1731 - Who is responsible for decommissioning an OCS facility subject to an Alternate Use RUE?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... Alternate Use RUE issued under 30 CFR part 585 is responsible for all decommissioning obligations that... CFR part 585, subpart J, for additional information concerning the decommissioning responsibilities of an Alternate Use RUE grant holder. (b) The lessee under the lease originally issued under 30 CFR...

  1. 30 CFR 285.1018 - Who is responsible for decommissioning an OCS facility subject to an Alternate Use RUE?

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... facility subject to an Alternate Use RUE? 285.1018 Section 285.1018 Mineral Resources BUREAU OF OCEAN...- and Marine-Related Activities Using Existing OCS Facilities Decommissioning An Alternate Use Rue § 285.1018 Who is responsible for decommissioning an OCS facility subject to an Alternate Use RUE? (a)...

  2. 30 CFR 285.1018 - Who is responsible for decommissioning an OCS facility subject to an Alternate Use RUE?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... facility subject to an Alternate Use RUE? 285.1018 Section 285.1018 Mineral Resources MINERALS MANAGEMENT... Existing OCS Facilities Decommissioning An Alternate Use Rue § 285.1018 Who is responsible for decommissioning an OCS facility subject to an Alternate Use RUE? (a) The holder of an Alternate Use RUE...

  3. 30 CFR 585.1018 - Who is responsible for decommissioning an OCS facility subject to an Alternate Use RUE?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... issued under 30 CFR part 250 will remain responsible for decommissioning obligations that accrued before... facility subject to an Alternate Use RUE? 585.1018 Section 585.1018 Mineral Resources BUREAU OF OCEAN... Activities Using Existing OCS Facilities Decommissioning An Alternate Use Rue § 585.1018 Who is...

  4. 30 CFR 585.1018 - Who is responsible for decommissioning an OCS facility subject to an Alternate Use RUE?

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... issued under 30 CFR part 250 will remain responsible for decommissioning obligations that accrued before... facility subject to an Alternate Use RUE? 585.1018 Section 585.1018 Mineral Resources BUREAU OF OCEAN... Activities Using Existing OCS Facilities Decommissioning An Alternate Use Rue § 585.1018 Who is...

  5. 30 CFR 585.1018 - Who is responsible for decommissioning an OCS facility subject to an Alternate Use RUE?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... issued under 30 CFR part 250 will remain responsible for decommissioning obligations that accrued before... facility subject to an Alternate Use RUE? 585.1018 Section 585.1018 Mineral Resources BUREAU OF OCEAN... Activities Using Existing OCS Facilities Decommissioning An Alternate Use Rue § 585.1018 Who is...

  6. 30 CFR 250.1731 - Who is responsible for decommissioning an OCS facility subject to an Alternate Use RUE?

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... Alternate Use RUE issued under 30 CFR part 585 is responsible for all decommissioning obligations that... CFR part 585, subpart J, for additional information concerning the decommissioning responsibilities of an Alternate Use RUE grant holder. (b) The lessee under the lease originally issued under 30 CFR...

  7. 30 CFR 250.1731 - Who is responsible for decommissioning an OCS facility subject to an Alternate Use RUE?

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... Alternate Use RUE issued under 30 CFR part 585 is responsible for all decommissioning obligations that... CFR part 585, subpart J, for additional information concerning the decommissioning responsibilities of an Alternate Use RUE grant holder. (b) The lessee under the lease originally issued under 30 CFR...

  8. 26 CFR 1.468A-5 - Nuclear decommissioning fund qualification requirements; prohibitions against self-dealing...

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... established for the exclusive purpose of providing funds for the decommissioning of one or more nuclear power... agreement; and (B) One or more funds that are to be used for the decommissioning of a nuclear power plant... nuclear power plant with respect to which an electing taxpayer possesses a qualifying interest....

  9. 77 FR 58591 - Report on Waste Burial Charges: Changes in Decommissioning Waste Disposal Costs at Low-Level...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-09-21

    ... COMMISSION Report on Waste Burial Charges: Changes in Decommissioning Waste Disposal Costs at Low-Level Waste... document entitled: NUREG-1307 Revision 15, ``Report on Waste Burial Charges: Changes in Decommissioning Waste Disposal Costs at Low-Level Waste Burial Facilities.'' DATES: Please submit comments by October...

  10. 14 CFR 29.687 - Spring devices.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 14 Aeronautics and Space 1 2010-01-01 2010-01-01 false Spring devices. 29.687 Section 29.687... STANDARDS: TRANSPORT CATEGORY ROTORCRAFT Design and Construction Control Systems § 29.687 Spring devices. (a) Each control system spring device whose failure could cause flutter or other unsafe...

  11. 14 CFR 27.687 - Spring devices.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 14 Aeronautics and Space 1 2010-01-01 2010-01-01 false Spring devices. 27.687 Section 27.687... STANDARDS: NORMAL CATEGORY ROTORCRAFT Design and Construction Control Systems § 27.687 Spring devices. (a) Each control system spring device whose failure could cause flutter or other unsafe...

  12. 14 CFR 23.687 - Spring devices.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 14 Aeronautics and Space 1 2010-01-01 2010-01-01 false Spring devices. 23.687 Section 23.687 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION, DEPARTMENT OF TRANSPORTATION AIRCRAFT AIRWORTHINESS... Systems § 23.687 Spring devices. The reliability of any spring device used in the control system must...

  13. 14 CFR 29.687 - Spring devices.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 14 Aeronautics and Space 1 2012-01-01 2012-01-01 false Spring devices. 29.687 Section 29.687... STANDARDS: TRANSPORT CATEGORY ROTORCRAFT Design and Construction Control Systems § 29.687 Spring devices. (a) Each control system spring device whose failure could cause flutter or other unsafe...

  14. 14 CFR 27.687 - Spring devices.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 14 Aeronautics and Space 1 2013-01-01 2013-01-01 false Spring devices. 27.687 Section 27.687... STANDARDS: NORMAL CATEGORY ROTORCRAFT Design and Construction Control Systems § 27.687 Spring devices. (a) Each control system spring device whose failure could cause flutter or other unsafe...

  15. 14 CFR 27.687 - Spring devices.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 14 Aeronautics and Space 1 2012-01-01 2012-01-01 false Spring devices. 27.687 Section 27.687... STANDARDS: NORMAL CATEGORY ROTORCRAFT Design and Construction Control Systems § 27.687 Spring devices. (a) Each control system spring device whose failure could cause flutter or other unsafe...

  16. 14 CFR 29.687 - Spring devices.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 14 Aeronautics and Space 1 2011-01-01 2011-01-01 false Spring devices. 29.687 Section 29.687... STANDARDS: TRANSPORT CATEGORY ROTORCRAFT Design and Construction Control Systems § 29.687 Spring devices. (a) Each control system spring device whose failure could cause flutter or other unsafe...

  17. 14 CFR 29.687 - Spring devices.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 14 Aeronautics and Space 1 2013-01-01 2013-01-01 false Spring devices. 29.687 Section 29.687... STANDARDS: TRANSPORT CATEGORY ROTORCRAFT Design and Construction Control Systems § 29.687 Spring devices. (a) Each control system spring device whose failure could cause flutter or other unsafe...

  18. 14 CFR 27.687 - Spring devices.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 14 Aeronautics and Space 1 2011-01-01 2011-01-01 false Spring devices. 27.687 Section 27.687... STANDARDS: NORMAL CATEGORY ROTORCRAFT Design and Construction Control Systems § 27.687 Spring devices. (a) Each control system spring device whose failure could cause flutter or other unsafe...

  19. Effective Mass of an Oscillating Spring

    ERIC Educational Resources Information Center

    Rodriguez, Eduardo E.; Gesnouin, Gabriel A.

    2007-01-01

    We present an experimental method to obtain the effective mass of an unloaded oscillating spring. We measure the period "T"("n") of the partial springs that result when hanging "n" of the total "N" coils of a given spring. Data are correlated with the expectation of a simple model for "T"("n") that takes into account the effective mass of the…

  20. FOSSIL SPRINGS ROADLESS AREA, ARIZONA.

    USGS Publications Warehouse

    Beard, L.S.; Ellis, C.E.

    1984-01-01

    Based on field studies, the Fossil Springs Roadless Area in central Arizona is concluded to have little promise for the occurrence of mineral or energy resources. Rocks in the Supai Formation (Pennsylvanian-Permian) near the central part of the roadless area contain widespread but spotty copper mineralization and trace amounts of uranium. Analyses obtained during the study define geochemical anomalies in two portions of the area that remain unexplained. The suites of anomalous metals suggest the possibility of hydrothermal veins and the presence of ultramafic rocks; neither were found in the field. Although there is little promise for the occurrence of mineral resources in the Fossil Springs Roadless Area, studies to identify the source of the geochemical anomalies could have valuable implications for regional studies and mineral exploration in the surrounding area.

  1. Technical Aspects Regarding the Management of Radioactive Waste from Decommissioning of Nuclear Facilities

    SciTech Connect

    Dragolici, F.; Turcanu, C. N.; Rotarescu, G.; Paunica, I.

    2003-02-25

    The proper application of the nuclear techniques and technologies in Romania started in 1957, once with the commissioning of the Research Reactor VVR-S from IFIN-HH-Magurele. During the last 45 years, appear thousands of nuclear application units with extremely diverse profiles (research, biology, medicine, education, agriculture, transport, all types of industry) which used different nuclear facilities containing radioactive sources and generating a great variety of radioactive waste during the decommissioning after the operation lifetime is accomplished. A new aspect appears by the planning of VVR-S Research Reactor decommissioning which will be a new source of radioactive waste generated by decontamination, disassembling and demolition activities. By construction and exploitation of the Radioactive Waste Treatment Plant (STDR)--Magurele and the National Repository for Low and Intermediate Radioactive Waste (DNDR)--Baita, Bihor county, in Romania was solved the management of radioactive wastes arising from operation and decommissioning of small nuclear facilities, being assured the protection of the people and environment. The present paper makes a review of the present technical status of the Romanian waste management facilities, especially raising on treatment capabilities of ''problem'' wastes such as Ra-266, Pu-238, Am-241 Co-60, Co-57, Sr-90, Cs-137 sealed sources from industrial, research and medical applications. Also, contain a preliminary estimation of quantities and types of wastes, which would result during the decommissioning project of the VVR-S Research Reactor from IFIN-HH giving attention to some special category of wastes like aluminum, graphite and equipment, components and structures that became radioactive through neutron activation. After analyzing the technical and scientific potential of STDR and DNDR to handle big amounts of wastes resulting from the decommissioning of VVR-S Research Reactor and small nuclear facilities, the necessity of

  2. Updating: Learning versus Supposing

    ERIC Educational Resources Information Center

    Zhao, Jiaying; Crupi, Vincenzo; Tentori, Katya; Fitelson, Branden; Osherson, Daniel

    2012-01-01

    Bayesian orthodoxy posits a tight relationship between conditional probability and updating. Namely, the probability of an event "A" after learning "B" should equal the conditional probability of "A" given "B" prior to learning "B". We examine whether ordinary judgment conforms to the orthodox view. In three experiments we found substantial…

  3. ''Smart Gun'' Technology Update

    SciTech Connect

    WIRSBINSKI, JOHN W.

    2001-11-01

    This report is an update to previous ''smart gun'' work and the corresponding report that were completed in 1996. It incorporates some new terminology and expanded definitions. This effort is the product of an open source look at what has happened to the ''smart gun'' technology landscape since the 1996 report was published.

  4. Updated opal opacities

    SciTech Connect

    Iglesias, C.A.; Rogers, F.J.

    1996-06-01

    The reexamination of astrophysical opacities has eliminated gross discrepancies between a variety of observations and theoretical calculations; thus allowing for more detailed tests of stellar models. A number of such studies indicate that model results are sensitive to modest changes in the opacity. Consequently, it is desirable to update available opacity databases with recent improvements in physics, refinements of element abundance, and other such factors affecting the results. Updated OPAL Rosseland mean opacities are presented. The new results have incorporated improvements in the physics and numerical procedures as well as corrections. The main opacity changes are increases of as much as 20{percent} for Population I stars due to the explicit inclusion of 19 metals (compared to 12 metals in the earlier calculations) with the other modifications introducing opacity changes smaller than 10{percent}. In addition, the temperature and density range covered by the updated opacity tables has been extended. As before, the tables allow accurate interpolation in density and temperature as well as hydrogen, helium, carbon, oxygen, and metal mass fractions. Although a specific metal composition is emphasized, opacity tables for different metal distributions can be made readily available. The updated opacities are compared to other work. {copyright} {ital 1996 The American Astronomical Society.}

  5. SEI: An update

    NASA Technical Reports Server (NTRS)

    Peach, Lewis L., Jr.

    1991-01-01

    An update on the Space Exploration Initiative (SEI) is given in viewgraph form. Topics covered include the key prerequisites of human exploration, project planning, Mars and lunar explorations, supporting technologies, near-term strategies for SEI, human support elements, and Space Station Freedom SEI accommodations.

  6. Veterinary medicines update.

    PubMed

    2016-07-01

    The following information has been produced for Veterinary Record by the Veterinary Medicines Directorate (VMD) to provide an update for veterinary surgeons on recent changes to marketing authorisations for veterinary medicines in the UK and on other relevant issues. PMID:27365238

  7. Veterinary medicines update.

    PubMed

    2016-06-11

    The following information has been produced for Veterinary Record by the Veterinary Medicines Directorate (VMD) to provide an update for veterinary surgeons on recent changes to marketing authorisations for veterinary medicines in the UK and on other relevant issues. PMID:27288166

  8. Veterinary medicines update.

    PubMed

    2016-08-01

    The following information has been produced for Veterinary Record by the Veterinary Medicines Directorate (VMD) to provide an update for veterinary surgeons on recent changes to marketing authorisations for veterinary medicines in the UK and on other relevant issues. PMID:27493045

  9. Supreme Court Update

    ERIC Educational Resources Information Center

    Taylor, Kelley R.

    2009-01-01

    "Chief Justice Flubs Oath." "Justice Ginsburg Has Cancer Surgery." At the start of this year, those were the news headlines about the U.S. Supreme Court. But January 2009 also brought news about key education cases--one resolved and two others on the docket--of which school administrators should take particular note. The Supreme Court updates on…

  10. Community Update, 2001.

    ERIC Educational Resources Information Center

    Ashby, Nicole, Ed.

    2001-01-01

    This document consists of 10 issues (covering January through December 2000) of the newsletter, "Community Update," which features articles on community and family involvement in education. In addition to the articles, each issue (except the Special Issue) includes a preview of the month's Satellite Town Meeting; events and information discussed…

  11. Updating Older Fume Hoods.

    ERIC Educational Resources Information Center

    Saunders, G. Thomas

    1985-01-01

    Provides information on updating older fume hoods. Areas addressed include: (1) adjustment of the hood's back baffle; (2) hood air leakage; (3) light level; (4) hood location in relation to room traffic and room air; and (5) establishing and maintaining hood performance. (JN)

  12. Veterinary medicines update.

    PubMed

    2016-09-10

    The following information has been produced for Veterinary Record by the Veterinary Medicines Directorate (VMD) to provide an update for veterinary surgeons on recent changes to marketing authorisations for veterinary medicines in the UK and on other relevant issues. PMID:27609956

  13. Veterinary medicines update.

    PubMed

    2016-10-01

    The following information has been produced for Veterinary Record by the Veterinary Medicines Directorate (VMD) to provide an update for veterinary surgeons on recent changes to marketing authorisations for veterinary medicines in the UK and on other relevant issues. PMID:27687269

  14. Update: Biological Nitrogen Fixation.

    ERIC Educational Resources Information Center

    Wiseman, Alan; And Others

    1985-01-01

    Updates knowledge on nitrogen fixation, indicating that investigation of free-living nitrogen-fixing organisms is proving useful in understanding bacterial partners and is expected to lead to development of more effective symbioses. Specific areas considered include biochemistry/genetics, synthesis control, proteins and enzymes, symbiotic systems,…

  15. Technology Update-87

    SciTech Connect

    Not Available

    1987-12-01

    The five papers in this issue of Technology Update reflect improvements in equipment reliability, inspection techniques, data storage techniques, and production technology - all aimed at reducing process variations. Each paper represents an achievement by our technical staff that allows Mound to make more effective use of our resources. A separate abstract has been prepared for one of the papers.

  16. Force of an actin spring

    NASA Astrophysics Data System (ADS)

    Shin, Jennifer; Mahadevan, L.; Matsudaira, Paul

    2003-03-01

    The acrosomal process of the horseshoe crab sperm is a novel mechanochemical molecular spring that converts its elastic stain energy to mechanical work upon the chemical activation by Ca2+. Twisted and bent, the initial state of the acrosomal bundle features a high degree of complexity in its structure and the energy is believed to be stored in the highly strained actin filaments as an elastic potential energy. When activated, the bundle relaxes from the coil of the highly twisted and bent filaments to its straight conformation at a mean velocity of 15um/s. The mean extension velocity increases dramatically from 3um/s to 27um/s when temperature of the medium is changed from 9.6C to 32C (respective viscosities of 1.25-0.75cp), yet it exhibits a very weak dependence on changes in the medium viscosity (1cp-33cp). These experiments suggest that the uncoiling of the actin spring should be limited not by the viscosity of the medium but by the unlatching events of involved proteins at a molecular level. Unlike the viscosity-limited processes, where force is directly related to the rate of the reaction, a direct measurement is required to obtain the spring force of the acrosomal process. The extending acrosomal bundle is forced to push against a barrier and its elastic buckling response is analyzed to measure the force generated during the uncoiling.

  17. VGP highlights of Spring Meeting

    NASA Astrophysics Data System (ADS)

    Morse, S. A.

    Two special events of interest to Union and VGP section members will take place on Tuesday afternoon, May 25, during AGU's Spring Meeting in Baltimore.R. A. Daly Lecture: Every section of AGU has an established “Bowie Lecture” named after a distinguished scientist associated with the work of the section. These lectures are delivered by special invitation during the annual AGU Spring or Fall meetings and are highlighted in the program. The VGP lecture is named for Reginald A. Daly, but it has never been given. Its inauguration at this year's Spring Meeting celebrates the distinguished career of this famous Harvard professor and author of the seminal Igneous Rocks and the Depths of the Earth (1914, 1933). Most fittingly, the inaugural lecture will be given by David Walker of Columbia University's Lamont-Doherty Earth Observatory after a day-long Union session on discontinuities in the mantle. Dave's lecture, “Errors in Earth Evolution,” will start at 4:45 P.M. We can expect to hear an original and provocative talk that features exciting, new data.

  18. Action Memorandum for General Decommissioning Activities under the Idaho Cleanup Project

    SciTech Connect

    S. L. Reno

    2006-10-26

    This Action Memorandum documents the selected alternative to perform general decommissioning activities at the Idaho National Laboratory (INL) under the Idaho Cleanup Project (ICP). Preparation of this Action Memorandum has been performed in accordance with the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended by the "Superfund Amendments and Reauthorization Act of 1986", and in accordance with the "National Oil and Hazardous Substances Pollution Contingency Plan". An engineering evaluation/cost analysis (EE/CA) was prepared and released for public comment and evaluated alternatives to accomplish the decommissioning of excess buildings and structures whose missions havve been completed.

  19. Estimation and characterization of decontamination and decommissioning solid waste expected from the Plutonium Finishing Plant

    SciTech Connect

    Millar, J.S.; Pottmeyer, J.A.; Stratton, T.J.

    1995-01-01

    Purpose of the study was to estimate the amounts of equipment and other materials that are candidates for removal and subsequent processing in a solid waste facility when the Hanford Plutonium Finishing Plant is decontaminated and decommissioned. (Building structure and soil are not covered.) Results indicate that {approximately}5,500 m{sup 3} of solid waste is expected to result from the decontamination and decommissioning of the Pu Finishing Plant. The breakdown of the volumes and percentages of waste by category is 1% dangerous solid waste, 71% low-level waste, 21% transuranic waste, 7% transuranic mixed waste.

  20. Technology, safety, and costs of decommissioning reference nuclear research and test reactors. Appendices

    SciTech Connect

    Konzek, G.J.; Ludwick, J.D.; Kennedy, W.E. Jr.; Smith, R.I.

    1982-03-01

    Safety and Cost Information is developed for the conceptual decommissioning of two representative licensed nuclear research and test reactors. Three decommissioning alternatives are studied to obtain comparisons between costs (in 1981 dollars), occupational radiation doses, potential radiation dose to the public, and other safety impacts. The alternatives considered are: DECON (immediate decontamination), SAFSTOR (safe storage followed by deferred decontamination), and EMTOMB (entombment). The study results are presented in two volumes. Volume 2 (Appendices) contains the detailed data that support the results given in Volume 1, including unit-component data.

  1. Decontamination and decommissioning of building 889 at Rocky Flats Environmental Technology Site

    SciTech Connect

    Dorr, K.A.; Hickman, M.E.; Henderson, B.J.; Sexton, R.J.

    1997-09-01

    At the Rocky Flats site, the building 889 decommissioning project was the first large-scale decommissioning project of a radiologically contaminated facility at Rocky Flats. The scope consisted of removal of all equipment and utility systems from the interior of the building, decontamination of interior building surfaces, and the demolition of the facility to ground level. Details of the project management plan, including schedule, engineering, cost, characterization methodologies, decontamination techniques, radiological control requirements, and demolition methods, are provided in this article. 1 fig., 3 tabs.

  2. Criticality safety aspects of decontamination and decommissioning at defense nuclear facilities

    SciTech Connect

    Croucher, D.W.

    1994-02-01

    Defense nuclear facilities have operated for forty years with a well-defined mission to produce weapons components for the nation. With the end of the cold war, the facilities` missions have changed to one of decontamination and decommissioning. Off-normal operations and use of new procedures, such as will exist during these activities, have often been among the causal factors in previous criticality accidents at process facilities. This paper explores the similarities in causal factors in previous criticality accidents to the conditions existing in current defense nuclear facilities undergoing the transition to decontamination and decommissioning. Practices to reduce the risk to workers, the public, and the environment are recommended.

  3. Decommissioning of TA-21-153, a /sup 227/Ac contaminated old filter building

    SciTech Connect

    Harper, J.R.; Garde, R.

    1981-11-01

    An exhaust air filter building contaminated with /sup 227/Ac was decommissioned at the Los Alamos National Laboratory, Los Alamos, New Mexico, in 1978. The building was constructed in the late 1940s to clean exhaust air from several buildings at TA-21, DP Site. It was in service until March 1970. The project involved preliminary decontamination, dismantling the building, and burying the debris at an on-site waste disposal/storage area. This report presents the details on the decommissioning procedures, health physics, waste management, environmental surveillance, and costs for the operation.

  4. Environmental assessment of decommissioning radioisotope thermoelectric generators (RTG) in northwest Russia

    SciTech Connect

    Hosseini, A.; Standring, W.J.F.; Brown, J.E.; Dowdall, M.; Amundsen, I.B.

    2007-07-01

    This article presents some results from assessment work conducted as part of a joint Norwegian-Russian project to decommission radioisotope thermoelectric generators (RTG) in Northwest Russia. Potential worst case accident scenarios, based on the decommissioning procedures for RTGs, were assessed to study possible radiation effects to the environment. Close contact with exposed RTG sources will result in detrimental health effects. However, doses to marine biota from ingestion of radioactivity under the worst-case marine scenario studied were lower than threshold limits given in IAEA literature. (authors)

  5. Environmental, health and safety assessment of decommissioning radioisotope thermoelectric generators (RTGs) in northwest Russia.

    PubMed

    Standring, W J F; Dowdall, M; Sneve, M; Selnaes, Ø G; Amundsen, I

    2007-09-01

    This paper presents findings from public health and environmental assessment work that has been conducted as part of a joint Norwegian-Russian project to decommission radioisotope thermoelectric generators (RTG) in northwest Russia. RTGs utilise heat energy from radioactive isotopes, in this case 90Sr and its daughter nuclide 90Y, to generate electricity as a power source. Different accident scenarios based on the decommissioning process for RTGs are assessed in terms of possible radiation effects to humans and the environment. Doses to humans and biota under the worst-case scenario were lower than threshold limits given in ICRP and IAEA literature.

  6. Lessons learned from decommissioning of a research lab and how to apply these on upcoming decommissioning projects at the Studsvik site

    SciTech Connect

    Ellmark, Christoffer; Eriksson, Anders; Lindberg, Maria

    2007-07-01

    Available in abstract form only. Full text of publication follows: The clearance of material and release of buildings for unconditional use are crucial factors for the waste amounts coming from decommissioning of nuclear facilities. The possibilities for clearance is also very much dependent on the regulatory body's ability to put in place the correct regulations or legislations. During the last decade the development of new guidelines for decommissioning has taken place. The implementation of these guidelines on a national level has not been fast but in Sweden it is on its way. This paper will describe the Swedish situation from the point of view of a decommissioner, i.e. an organization in need of clear and long term regulations. (authors)

  7. 1. NORTHWEST FRONT, SOUTHWEST SIDE (SPRING HOUSE IN FOREGROUND; BATH ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    1. NORTHWEST FRONT, SOUTHWEST SIDE (SPRING HOUSE IN FOREGROUND; BATH HOUSE AT REAR) (4 x 5 negative; 5 x 7 print) - Salt Sulphur Springs, Spring House, U.S. Route 219, Salt Sulphur Springs, Monroe County, WV

  8. Volusia Blue Spring - A Hydrological Treasure

    USGS Publications Warehouse

    German, Edward R.

    2008-01-01

    Springs are natural openings in the ground through which water beneath the surface discharges into hydrologic features such as lakes, rivers, or the ocean. The beautiful springs and spring rivers are among Florida's most valued natural resources; their gemlike refreshing waters have been a focal point of life from prehistoric times to the present (2008). The steady flow of freshwater at a nearly constant water temperature attracted animals now long absent from Florida's landscape. Fossil remains and human artifacts, discovered by divers from many spring runs, attest to the importance of springs to the State's earliest inhabitants. Explorers of Florida, from Ponce de Leon to John and William Bartram and others, often mentioned the springs that were scattered across central and northern Florida. As colonists and settlers began to inhabit Florida, springs continued to be the focus of human activity, becoming sites of missions, towns, and steamboat landings.

  9. Comparative spring mechanics in mantis shrimp.

    PubMed

    Patek, S N; Rosario, M V; Taylor, J R A

    2013-04-01

    Elastic mechanisms are fundamental to fast and efficient movements. Mantis shrimp power their fast raptorial appendages using a conserved network of exoskeletal springs, linkages and latches. Their appendages are fantastically diverse, ranging from spears to hammers. We measured the spring mechanics of 12 mantis shrimp species from five different families exhibiting hammer-shaped, spear-shaped and undifferentiated appendages. Across species, spring force and work increase with size of the appendage and spring constant is not correlated with size. Species that hammer their prey exhibit significantly greater spring resilience compared with species that impale evasive prey ('spearers'); mixed statistical results show that species that hammer prey also produce greater work relative to size during spring loading compared with spearers. Disabling part of the spring mechanism, the 'saddle', significantly decreases spring force and work in three smasher species; cross-species analyses show a greater effect of cutting the saddle on the spring force and spring constant in species without hammers compared with species with hammers. Overall, the study shows a more potent spring mechanism in the faster and more powerful hammering species compared with spearing species while also highlighting the challenges of reconciling within-species and cross-species mechanical analyses when different processes may be acting at these two different levels of analysis. The observed mechanical variation in spring mechanics provides insights into the evolutionary history, morphological components and mechanical behavior, which were not discernible in prior single-species studies. The results also suggest that, even with a conserved spring mechanism, spring behavior, potency and component structures can be varied within a clade with implications for the behavioral functions of power-amplified devices. PMID:23239886

  10. Comparative spring mechanics in mantis shrimp.

    PubMed

    Patek, S N; Rosario, M V; Taylor, J R A

    2013-04-01

    Elastic mechanisms are fundamental to fast and efficient movements. Mantis shrimp power their fast raptorial appendages using a conserved network of exoskeletal springs, linkages and latches. Their appendages are fantastically diverse, ranging from spears to hammers. We measured the spring mechanics of 12 mantis shrimp species from five different families exhibiting hammer-shaped, spear-shaped and undifferentiated appendages. Across species, spring force and work increase with size of the appendage and spring constant is not correlated with size. Species that hammer their prey exhibit significantly greater spring resilience compared with species that impale evasive prey ('spearers'); mixed statistical results show that species that hammer prey also produce greater work relative to size during spring loading compared with spearers. Disabling part of the spring mechanism, the 'saddle', significantly decreases spring force and work in three smasher species; cross-species analyses show a greater effect of cutting the saddle on the spring force and spring constant in species without hammers compared with species with hammers. Overall, the study shows a more potent spring mechanism in the faster and more powerful hammering species compared with spearing species while also highlighting the challenges of reconciling within-species and cross-species mechanical analyses when different processes may be acting at these two different levels of analysis. The observed mechanical variation in spring mechanics provides insights into the evolutionary history, morphological components and mechanical behavior, which were not discernible in prior single-species studies. The results also suggest that, even with a conserved spring mechanism, spring behavior, potency and component structures can be varied within a clade with implications for the behavioral functions of power-amplified devices.

  11. Audiomagnetotelluric data from Spring, Cave, and Coyote Spring Valleys, Nevada

    USGS Publications Warehouse

    McPhee, Darcy K.; Chuchel, Bruce A.; Pellerin, Louise

    2006-01-01

    Audiomagnetotelluric (AMT) data along four profiles in Spring, Cave, and Coyote Spring Valleys are presented here. The AMT method is used to estimate the electrical resistivity of the earth over depth ranges of a few meters to greater than one kilometer. This method is a valuable tool for revealing subsurface structure and stratigraphy within the Basin and Range of eastern Nevada, therefore helping to define the geohydrologic framework in this region. We collected AMT data using the Geometrics StrataGem EH4 system, a four-channel, natural and controlled- source tensor system recording in the range of 10 to 92,000 Hz. To augment the low signal in the natural field, an unpolarized transmitter comprised of two horizontal-magnetic dipoles was used from 1,000 to 70,000 Hz. Profiles were 1.4 - 12.6 km in length with station spacing of 100-400 m. Data were recorded with the electrical (E) field parallel to and perpendicular to the regional geologic strike direction. Station locations and sounding curves, showing apparent resistivity, phase data, and coherency data, are presented here.

  12. Sequence History Update Tool

    NASA Technical Reports Server (NTRS)

    Khanampompan, Teerapat; Gladden, Roy; Fisher, Forest; DelGuercio, Chris

    2008-01-01

    The Sequence History Update Tool performs Web-based sequence statistics archiving for Mars Reconnaissance Orbiter (MRO). Using a single UNIX command, the software takes advantage of sequencing conventions to automatically extract the needed statistics from multiple files. This information is then used to populate a PHP database, which is then seamlessly formatted into a dynamic Web page. This tool replaces a previous tedious and error-prone process of manually editing HTML code to construct a Web-based table. Because the tool manages all of the statistics gathering and file delivery to and from multiple data sources spread across multiple servers, there is also a considerable time and effort savings. With the use of The Sequence History Update Tool what previously took minutes is now done in less than 30 seconds, and now provides a more accurate archival record of the sequence commanding for MRO.

  13. Sensors, Update 12

    NASA Astrophysics Data System (ADS)

    Baltes, Henry; Fedder, Gary K.; Korvink, Jan G.

    2003-04-01

    Sensors Update ensures that you stay at the cutting edge of the field. Built upon the series Sensors, it presents an overview of highlights in the field. Coverage includes current developments in materials, design, production, and applications of sensors, signal detection and processing, as well as new sensing principles. Each volume is divided into three sections. Sensor Technology, reviews highlights in applied and basic research, Sensor Applications, covers new or improved applications of sensors, Sensor Markets, provides a survey of suppliers and market trends for a particular area. With this unique combination of information in each volume, Sensors Update will be of value for scientists and engineers in industry and at universities, to sensors developers, distributors, and users.

  14. Sensors, Update 8

    NASA Astrophysics Data System (ADS)

    Baltes, Henry; Göpel, Wolfgang; Hesse, Joachim

    2001-02-01

    Sensors Update ensures that you stay at the cutting edge of the field. Built upon the series Sensors, it presents an overview of highlights in the field. Coverage includes current developments in materials, design, production, and applications of sensors, signal detection and processing, as well as new sensing principles. Each volume is divided into three sections: Sensor Technology reviews highlights in applied and basic research, while Sensor Applications covers new or improved applications of sensors, and Sensor Markets provides a survey of suppliers and market trends for a particular area. With this unique combination of information in each volume, Sensors Update will be invaluable to scientists and engineers in industry and at universities, to sensors developers, distributors, and users.

  15. Sensors, Update 2

    NASA Astrophysics Data System (ADS)

    Baltes, Henry; Göpel, Wolfgang; Hesse, Joachim

    1996-10-01

    Sensors Update ensures that you stay at the cutting edge of the field. Built upon the series Sensors, it presents an overview of highlights in the field. Coverage includes current developments in materials, design, production, and applications of sensors, signal detection and processing, as well as new sensing principles. Furthermore, the sensor market as well as peripheral aspects such as standards are covered. Each volume is divided into four sections. Sensor Technology, reviews highlights in applied and basic research, Sensor Applications, covers new or improved applications of sensors, Sensor Markets, provides a survey of suppliers and market trends for a particular area. With this unique combination of information in each volume, Sensors Update will be of value for scientists and engineers in industry and at universities, to sensors developers, distributors, and users.

  16. Sensors, Update 11

    NASA Astrophysics Data System (ADS)

    Baltes, Henry; Fedder, Gary K.; Korvink, Jan G.

    2003-03-01

    Sensors Update ensures that you stay at the cutting edge of the field, presenting the current highlights of sensor and related microelectromechanical systems technology. Coverage includes most recent developments in materials, design, production, and applications of sensors, signal detection and processing, as well as new sensing principles based on micro- and nanotechnology. Each volume is divided into three sections: Sensor Technology reviews highlights in applied and basic research, Sensor Applications covers new or improved applications of sensors and Sensor Markets provides a survey of suppliers and market trends for a particular area. With this unique combination of information in each volume, Sensors Update is of must-have value for scientists and engineers in industry and at universities, to sensors developers, distributors, and users.

  17. Sensors, Update 1

    NASA Astrophysics Data System (ADS)

    Baltes, Henry; Göpel, Wolfgang; Hesse, Joachim

    1996-12-01

    Sensors Update ensures that you stay at the cutting edge of the field. Built upon the series Sensors, it presents an overview of highlights in the field. Treatments include current developments in materials, design, production, and applications of sensors, signal detection and processing, as well as new sensing principles. Furthermore, the sensor market as well as peripheral aspects such as standards are covered. Each volume is divided into four sections. Sensor Technology, reviews highlights in applied and basic research, Sensor Applications, covers new or improved applications of sensors, Sensor Markets, provides an overview of suppliers and market trends for a particular section, and Sensor Standards, reviews recent legislation and requirements for sensors. With this unique combination of information in each volume, Sensors Update will be of value for scientists and engineers in industry and at universities, to sensors developers, distributors, and users.

  18. Sensors, Update 10

    NASA Astrophysics Data System (ADS)

    Baltes, Henry; Fedder, Gary K.; Korvink, Jan G.

    2002-04-01

    Sensors Update ensures that you stay at the cutting edge of the field. Built upon the series Sensors, it presents an overview of highlights in the field. Coverage includes current developments in materials, design, production, and applications of sensors, signal detection and processing, as well as new sensing principles. Each volume is divided into three sections. Sensor Technology, reviews highlights in applied and basic research, Sensor Applications, covers new or improved applications of sensors, Sensor Markets, provides a survey of suppliers and market trends for a particular area. With this unique combination of information in each volume, Sensors Update will be of value for scientists and engineers in industry and at universities, to sensors developers, distributors, and users.

  19. Sensors, Update 9

    NASA Astrophysics Data System (ADS)

    Baltes, Henry; Göpel, Wolfgang; Hesse, Joachim

    2001-10-01

    Sensors Update ensures that you stay at the cutting edge of the field. Built upon the series Sensors, it presents an overview of highlights in the field. Coverage includes current developments in materials, design, production, and applications of sensors, signal detection and processing, as well as new sensing principles. Each volume is divided into three sections. Sensor Technology, reviews highlights in applied and basic research, Sensor Applications, covers new or improved applications of sensors, Sensor Markets, provides a survey of suppliers and market trends for a particular area. With this unique combination of information in each volume, Sensors Update will be of value for scientists and engineers in industry and at universities, to sensors developers, distributors, and users.

  20. SIM-Lite Update

    NASA Technical Reports Server (NTRS)

    Shao, Michael

    2008-01-01

    Discussion focus on: SIM-Lite Instrument Update - 6m baseline, 50cm, approximately 900M cost; Technology Update - Systematic errors and floor; SIM-Lite terrestrial planet discovery capability; Double blind multiple planet study summary; and the changing landscape of exoplanet science and the role of SIM-Lite. Slides include technology to flight component engineering; instrumental systematic errors; ultra deep search for Earth clones; double blind test, astrometric detection of Earths in multiplanet systems; the current era of exoplanet science and where SIM-Lite fits in; the next frontier and where SIM-Lite fits in, why SIM is unique in discovering Earths; imaging planet status is uncertain without masses and ages; SIM role in establishing how planetary systems form and evolve; and SIM probes of broad planet mass range around young stars.