DOE Hydropower Program biennial report 1996-1997 (with an updated annotated bibliography)
DOE Office of Scientific and Technical Information (OSTI.GOV)
Rinehart, B.N.; Francfort, J.E.; Sommers, G.L.
1997-06-01
This report, the latest in a series of biennial Hydropower Program reports sponsored by the US Department of Energy, summarizes the research and development and technology transfer activities of fiscal years 1996 and 1997. The report discusses the activities in the six areas of the hydropower program: advanced hydropower turbine systems; environmental research; hydropower research and development; renewable Indian energy resources; resource assessment; and technology transfer. The report also includes an annotated bibliography of reports pertinent to hydropower, written by the staff of the Idaho National Engineering and Environmental Laboratory, Oak Ridge National Laboratory, Federal and state agencies, cities, metropolitanmore » water districts, irrigation companies, and public and independent utilities. Most reports are available from the National Technical Information Service.« less
Small Hydropower in the United States
DOE Office of Scientific and Technical Information (OSTI.GOV)
Hadjerioua, Boualem; Johnson, Kurt
Small hydropower, defined in this report as hydropower with a generating capacity of up to 10 MW typically built using existing dams, pipelines, and canals has substantial opportunity for growth. Existing small hydropower comprises about 75% of the current US hydropower fleet in terms of number of plants. The economic feasibility of developing new small hydropower projects has substantially improved recently, making small hydropower the type of new hydropower development most likely to occur. In 2013, Congress unanimously approved changes to simplify federal permitting requirements for small hydropower, lowering costs and reducing the amount of time required to receive federalmore » approvals. In 2014, Congress funded a new federal incentive payment program for hydropower, currently worth approximately 1.5 cents/kWh. Federal and state grant and loan programs for small hydropower are becoming available. Pending changes in federal climate policy could benefit all renewable energy sources, including small hydropower. Notwithstanding remaining barriers, development of new small hydropower is expected to accelerate in response to recent policy changes.« less
DOE Office of Scientific and Technical Information (OSTI.GOV)
Levine, Aaron L.; Curtis, Taylor L.; Johnson, Kurt
Energy recovery hydropower is one of the most cost-effective types of new hydropower development because it is constructed utilizing existing infrastructure, and it is typically able to complete Federal Energy Regulatory Commission (FERC) review in 60 days. Recent changes in federal and state policy have supported energy recovery hydropower. In addition, some states have developed programs and policies to support energy recovery hydropower, including resource assessments, regulatory streamlining initiatives, and grant and loan programs to reduce project development costs. This report examines current federal and state policy drivers for energy recovery hydropower, reviews market trends, and looks ahead at futuremore » federal resource assessments and hydropower reform legislation.« less
2014 Water Power Program Peer Review: Hydropower Technologies, Compiled Presentations (Presentation)
DOE Office of Scientific and Technical Information (OSTI.GOV)
Not Available
This document represents a collection of all presentations given during the EERE Wind and Water Power Program's 2014 Hydropower Peer Review. The purpose of the meeting was to evaluate DOE-funded hydropower and marine and hydrokinetic R&D projects for their contribution to the mission and goals of the Water Power Program and to assess progress made against stated objectives.
Various Assessments Utilized in California Preliminary Administrative Services Preparation Programs
ERIC Educational Resources Information Center
Erickson, Deborah E.
2016-01-01
Every two years, institutions sponsoring credentialing programs in California are required to submit a detailed biennial report, which includes data on at least four key assessments showing 1) candidate competence and/or 2) program efficacy. This article reports the types of assessments used from 25 institutions that completed biennial reports for…
DOE Office of Scientific and Technical Information (OSTI.GOV)
None
2009-09-01
September 4, 2009 presentation highlighting the Wind and Hydropower Program, addressing program goals and objectives, budgets, technology pathways, breakthroughs, and DOE solutions to market barriers.
DOE Office of Scientific and Technical Information (OSTI.GOV)
McCluer, Megan
2009-09-04
September 4, 2009 presentation highlighting the Wind and Hydropower Program, addressing program goals and objectives, budgets, technology pathways, breakthroughs, and DOE solutions to market barriers.
ERIC Educational Resources Information Center
Office of English Language Acquisition, US Department of Education, 2013
2013-01-01
This is the fourth biennial report to Congress on the implementation of the "Elementary and Secondary Education Act's" Title III State Formula Grant Program (also known as the English Language Acquisition State Grants Program). This report provides information reported by states to the U.S. Department of Education regarding services…
ERIC Educational Resources Information Center
Office of English Language Acquisition, US Department of Education, 2012
2012-01-01
This is the third biennial report to Congress on the implementation of the "Elementary and Secondary Education Act's" Title III State Formula Grant Program (also known as the English Language Acquisition State Grants Program). This report provides information regarding the U.S. Department of Education's efforts to hold states accountable…
DOE Office of Scientific and Technical Information (OSTI.GOV)
None
2015-04-02
The Water Power Program helps industry harness this renewable, emissions-free resource to generate environmentally sustainable and cost-effective electricity. Through support for public, private, and nonprofit efforts, the Water Power Program promotes the development, demonstration, and deployment of advanced hydropower devices and pumped storage hydropower applications. These technologies help capture energy stored by diversionary structures, increase the efficiency of hydroelectric generation, and use excess grid energy to replenish storage reserves for use during periods of peak electricity demand. In addition, the Water Power Program works to assess the potential extractable energy from domestic water resources to assist industry and government inmore » planning for our nation’s energy future. From FY 2008 to FY 2014, DOE’s Water Power Program announced awards totaling approximately $62.5 million to 33 projects focused on hydropower. Table 1 provides a brief description of these projects.« less
1992-01-01
dessert and snack items to increase acceptability and 31$,) UNCLASSIFIED UNCLASSIFIED AMENDED FY 1992/1993 BIENNIAL RDTE DESCRIPTIVE SUMMARY Program...Planned Program: " (U) Finalize development of non-organic and non-polluting processing bids for extruded and molded energetic materials * (U
National Hydropower Plant Dataset, Version 2 (FY18Q3)
DOE Office of Scientific and Technical Information (OSTI.GOV)
Samu, Nicole; Kao, Shih-Chieh; O'Connor, Patrick
The National Hydropower Plant Dataset, Version 2 (FY18Q3) is a geospatially comprehensive point-level dataset containing locations and key characteristics of U.S. hydropower plants that are currently either in the hydropower development pipeline (pre-operational), operational, withdrawn, or retired. These data are provided in GIS and tabular formats with corresponding metadata for each. In addition, we include access to download 2 versions of the National Hydropower Map, which was produced with these data (i.e. Map 1 displays the geospatial distribution and characteristics of all operational hydropower plants; Map 2 displays the geospatial distribution and characteristics of operational hydropower plants with pumped storagemore » and mixed capabilities only). This dataset is a subset of ORNL's Existing Hydropower Assets data series, updated quarterly as part of ORNL's National Hydropower Asset Assessment Program.« less
US hydropower resource assessment for Hawaii
DOE Office of Scientific and Technical Information (OSTI.GOV)
Francfort, J.E.
1996-09-01
US DOE is developing an estimate of the undeveloped hydropower potential in US. The Hydropower Evaluation Software (HES) is a computer model developed by INEL for this purpose. HES measures the undeveloped hydropower resources available in US, using uniform criteria for measurement. The software was tested using hydropower information and data provided by Southwestern Power Administration. It is a menu-driven program that allows the PC user to assign environmental attributes to potential hydropower sites, calculate development suitability factors for each site based on the environmental attributes, and generate reports. This report describes the resource assessment results for the State ofmore » Hawaii.« less
ERIC Educational Resources Information Center
Office of English Language Acquisition, US Department of Education, 2008
2008-01-01
The biennial report to Congress on the implementation of the Title III state formula grant program provides a snapshot of the status of the U.S. Department of Education's efforts to hold states accountable for ensuring that all limited English proficient (LEP) students attain English language proficiency (ELP) and are achieving in the content…
Hydropower, an energy source whose time has come again
NASA Astrophysics Data System (ADS)
1980-01-01
Recent price increases in imported oil demonstrate the urgency for the U.S. to rapidly develop its renewable resources. One such renewable resource for which technology is available now is hydropower. Studies indicate that hydropower potential, particularly at existing dam sites, can save the county hundreds of thousands of barrels of oil per day. But problems and constraints-economic, environmental, institutional, and operational-limit is full potential. Federal programs have had little impact on helping to bring hydro projects on line. Specifically, the Department of Energy's Small Hydro Program could do more to overcome hydro constraints and problems through an effective outreach program and more emphasis on demonstration projects.
47 CFR 74.797 - Biennial Ownership Reports.
Code of Federal Regulations, 2014 CFR
2014-10-01
... 47 Telecommunication 4 2014-10-01 2014-10-01 false Biennial Ownership Reports. 74.797 Section 74.797 Telecommunication FEDERAL COMMUNICATIONS COMMISSION (CONTINUED) BROADCAST RADIO SERVICES EXPERIMENTAL RADIO, AUXILIARY, SPECIAL BROADCAST AND OTHER PROGRAM DISTRIBUTIONAL SERVICES Low Power TV, TV Translator, and TV Booster Stations § 74.797...
47 CFR 74.797 - Biennial Ownership Reports.
Code of Federal Regulations, 2010 CFR
2010-10-01
... 47 Telecommunication 4 2010-10-01 2010-10-01 false Biennial Ownership Reports. 74.797 Section 74.797 Telecommunication FEDERAL COMMUNICATIONS COMMISSION (CONTINUED) BROADCAST RADIO SERVICES EXPERIMENTAL RADIO, AUXILIARY, SPECIAL BROADCAST AND OTHER PROGRAM DISTRIBUTIONAL SERVICES Low Power TV, TV Translator, and TV Booster Stations § 74.797...
U.S. hydropower resource assessment for Idaho
DOE Office of Scientific and Technical Information (OSTI.GOV)
Conner, A.M.; Francfort, J.E.
1998-08-01
The US Department of Energy is developing an estimate of the undeveloped hydropower potential in the US. The Hydropower Evaluation Software (HES) is a computer model that was developed by the Idaho National Engineering and Environmental Laboratory for this purpose. HES measures the undeveloped hydropower resources available in the US, using uniform criteria for measurement. The software was developed and tested using hydropower information and data provided by the Southwestern Power Administration. It is a menu-driven program that allows the personal computer user to assign environmental attributes to potential hydropower sites, calculate development suitability factors for each site based onmore » the environmental attributes present, and generate reports based on these suitability factors. This report describes the resource assessment results for the State of Idaho.« less
45 CFR 98.70 - Reporting requirements.
Code of Federal Regulations, 2014 CFR
2014-10-01
...) Biennial reports to Congress by the Secretary shall include the information listed in § 98.71(b). (c... served with CCDF funds during the preceding Federal Fiscal Year. (3) Biennial reports to Congress by the... Program Reporting Requirements § 98.70 Reporting requirements. (a) Quarterly Case-level Report— (1) State...
45 CFR 98.70 - Reporting requirements.
Code of Federal Regulations, 2010 CFR
2010-10-01
...) Biennial reports to Congress by the Secretary shall include the information listed in § 98.71(b). (c... served with CCDF funds during the preceding Federal Fiscal Year. (3) Biennial reports to Congress by the... Program Reporting Requirements § 98.70 Reporting requirements. (a) Quarterly Case-level Report— (1) State...
45 CFR 98.70 - Reporting requirements.
Code of Federal Regulations, 2012 CFR
2012-10-01
...) Biennial reports to Congress by the Secretary shall include the information listed in § 98.71(b). (c... served with CCDF funds during the preceding Federal Fiscal Year. (3) Biennial reports to Congress by the... Program Reporting Requirements § 98.70 Reporting requirements. (a) Quarterly Case-level Report— (1) State...
45 CFR 98.70 - Reporting requirements.
Code of Federal Regulations, 2011 CFR
2011-10-01
...) Biennial reports to Congress by the Secretary shall include the information listed in § 98.71(b). (c... served with CCDF funds during the preceding Federal Fiscal Year. (3) Biennial reports to Congress by the... Program Reporting Requirements § 98.70 Reporting requirements. (a) Quarterly Case-level Report— (1) State...
45 CFR 98.70 - Reporting requirements.
Code of Federal Regulations, 2013 CFR
2013-10-01
...) Biennial reports to Congress by the Secretary shall include the information listed in § 98.71(b). (c... served with CCDF funds during the preceding Federal Fiscal Year. (3) Biennial reports to Congress by the... Program Reporting Requirements § 98.70 Reporting requirements. (a) Quarterly Case-level Report— (1) State...
North Dakota Department of Public Instruction Biennial Report, 2003-2005
ERIC Educational Resources Information Center
North Dakota Department of Public Instruction, 2003
2003-01-01
The Biennial Report presents a summary of programs and services provided by the North Dakota Department of Public Instruction. The State Superintendent noted a continued decline in enrollment, a shrinking tax base, expanded educator shortages, and concerns regarding school financing as realities impacting the state's constitutional responsibility…
20 Years of the MENC Biennial Conference: A Content Analysis
ERIC Educational Resources Information Center
Palkki, Joshua; Albert, Daniel J.; Hill, Stuart Chapman; Shaw, Ryan D.
2016-01-01
The purpose of this study was to investigate the content and intended audiences for educational sessions offered at MENC biennial conferences in order to illuminate trends and topics in professional development. The researchers performed a content analysis of each session (N?= 2,593) using program booklets from conferences between 1988 and 2008,…
Development activities, challenges and prospects for the hydropower sector in Austria
NASA Astrophysics Data System (ADS)
Wagner, Beatrice; Hauer, Christoph; Habersack, Helmut
2017-04-01
This contribution intends to give an overview of hydropower development activities in Austria and deepen the knowledge on actual strategies and planning documents. Thereby, the focus is on a climate and energy policy based perspective, also analyzing economic trends at the hydropower sector due to energy market changes in the last years. This includes a comparison with other political strategies and programs dealing with hydropower exploitation based on selected countries. With respect to technology developments, a concise review on technological innovations, such as hydrokinetic energy conversion systems, and new constructive designs of conventional hydropower plants in Austria will be given. Moreover, potential impacts on environment and aquatic ecosystems are described. Finally, key challenges and prospects will be identified and discussed.
Methane emissions from a temperate agricultural reservoir
Dr. Jake Beaulieu was invited to present at the 2014 Green House Gas Emission Modeling workshop hosted by the International Energy Agency (IEA) Hydropower Implementing Agreement for Hydropower Technologies and Programs (IAHTP). The purpose of this workshop is to assemble an int...
Outline of Meeting Sessions and Workshops: 15th Biennial Conference on Chemical Education
NASA Astrophysics Data System (ADS)
Wilson, Anna M.
1998-06-01
The 15th Biennial Conference on Chemical Education (15-BCCE), sponsored by the ACS Division of Chemical Education, will be held at the University of Waterloo, Waterloo, Ontario, Canada, August 9-13, 1998. Reg Friesen is the General Chair and Anna Wilson is the Program Chair. The technical program includes more than 600 oral and poster presentations, 70 workshops, and 12 special lectures on modern perspectives in chemistry. Plenary lectures will be given by Bonnie Bracey, Katherine Coleman, David Dolphin, Ernest Eliel, Arthur Ellis, Steve Spangler and Mary Anne White. The complete program, including abstracts, is available at http://www.biochem.purdue.edu/~bcce.
NASA Astrophysics Data System (ADS)
Olivares, M. A.; Gonzalez Cabrera, J. M., Sr.; Moreno, R.
2016-12-01
Operation of hydropower reservoirs in Chile is prescribed by an Independent Power System Operator. This study proposes a methodology that integrates power grid operations planning with basin-scale multi-use reservoir operations planning. The aim is to efficiently manage a multi-purpose reservoir, in which hydroelectric generation is competing with other water uses, most notably irrigation. Hydropower and irrigation are competing water uses due to a seasonality mismatch. Currently, the operation of multi-purpose reservoirs with substantial power capacity is prescribed as the result of a grid-wide cost-minimization model which takes irrigation requirements as constraints. We propose advancing in the economic co-optimization of reservoir water use for irrigation and hydropower at the basin level, by explicitly introducing the economic value of water for irrigation represented by a demand function for irrigation water. The proposed methodology uses the solution of a long-term grid-wide operations planning model, a stochastic dual dynamic program (SDDP), to obtain the marginal benefit function for water use in hydropower. This marginal benefit corresponds to the energy price in the power grid as a function of the water availability in the reservoir and the hydrologic scenarios. This function allows capture technical and economic aspects to the operation of hydropower reservoir in the power grid and is generated with the dual variable of the power-balance constraint, the optimal reservoir operation and the hydrologic scenarios used in SDDP. The economic value of water for irrigation and hydropower are then integrated into a basin scale stochastic dynamic program, from which stored water value functions are derived. These value functions are then used to re-optimize reservoir operations under several inflow scenarios.
ERIC Educational Resources Information Center
Illinois Community Coll. Board, Springfield.
This biennial report of the Illinois Junior College Board contains data on the community college program during 1971 and 1972. The report discusses the following topics: Selected Data of Illinois Public Junior Colleges; Organization of Higher Education in Illinois; Highlights of the Activities of the Illinois Junior College Board in 1971 and 1972;…
Influence of El Niño Southern Oscillation on global hydropower production
NASA Astrophysics Data System (ADS)
Ng, Jia Yi; Turner, Sean; Galelli, Stefano
2016-04-01
Hydropower contributes significantly to meeting the world's energy demand, accounting for at least 16% of total electrical output. Its role as a mature and cost competitive renewable energy source is expected to become increasingly important as the world transits to a low-carbon economy. A key component of hydropower production is runoff, which is highly dependent on precipitation and other climate variables. As such, it becomes critical to understand how the drivers of climate variability impact hydropower production. One globally-important driver is the El Niño Southern Oscillation (ENSO). While it is known that ENSO influences hydrological processes, the potential value of its associated teleconnection in design related tasks has yet to be explored at the global scale. Our work seeks to characterize the impact of ENSO on global hydropower production so as to quantify the potential for increased production brought about by incorporating climate information within reservoir operating models. We study over 1,500 hydropower reservoirs - representing more than half the world's hydropower capacity. A historical monthly reservoir inflow time series is assigned to each reservoir from a 0.5 degree gridded global runoff dataset. Reservoir operating rules are designed using stochastic dynamic programming, and storage dynamics are simulated to assess performance under the climate conditions of the 20th century. Results show that hydropower reservoirs in the United States, Brazil, Argentina, Australia, and Eastern China are strongly influenced by ENSO episodes. Statistically significant lag correlations between ENSO indicators and hydropower production demonstrate predictive skill with lead times up to several months. Our work highlights the potential for using these indicators to increase the contribution of existing hydropower plants to global energy supplies.
Fuzzy multiobjective models for optimal operation of a hydropower system
NASA Astrophysics Data System (ADS)
Teegavarapu, Ramesh S. V.; Ferreira, André R.; Simonovic, Slobodan P.
2013-06-01
Optimal operation models for a hydropower system using new fuzzy multiobjective mathematical programming models are developed and evaluated in this study. The models use (i) mixed integer nonlinear programming (MINLP) with binary variables and (ii) integrate a new turbine unit commitment formulation along with water quality constraints used for evaluation of reservoir downstream impairment. Reardon method used in solution of genetic algorithm optimization problems forms the basis for development of a new fuzzy multiobjective hydropower system optimization model with creation of Reardon type fuzzy membership functions. The models are applied to a real-life hydropower reservoir system in Brazil. Genetic Algorithms (GAs) are used to (i) solve the optimization formulations to avoid computational intractability and combinatorial problems associated with binary variables in unit commitment, (ii) efficiently address Reardon method formulations, and (iii) deal with local optimal solutions obtained from the use of traditional gradient-based solvers. Decision maker's preferences are incorporated within fuzzy mathematical programming formulations to obtain compromise operating rules for a multiobjective reservoir operation problem dominated by conflicting goals of energy production, water quality and conservation releases. Results provide insight into compromise operation rules obtained using the new Reardon fuzzy multiobjective optimization framework and confirm its applicability to a variety of multiobjective water resources problems.
Code of Federal Regulations, 2010 CFR
2010-10-01
... Control Program Directors, and the Nuclear Energy Institute. (21) Implement and coordinate REP Program... from our REP Program Strategic Review implementation and oversight working group activities. (24) Costs...
Code of Federal Regulations, 2014 CFR
2014-10-01
... Control Program Directors, and the Nuclear Energy Institute. (21) Implement and coordinate REP Program... from our REP Program Strategic Review implementation and oversight working group activities. (24) Costs...
Code of Federal Regulations, 2013 CFR
2013-10-01
... Control Program Directors, and the Nuclear Energy Institute. (21) Implement and coordinate REP Program... from our REP Program Strategic Review implementation and oversight working group activities. (24) Costs...
Code of Federal Regulations, 2011 CFR
2011-10-01
... Control Program Directors, and the Nuclear Energy Institute. (21) Implement and coordinate REP Program... from our REP Program Strategic Review implementation and oversight working group activities. (24) Costs...
Amended FY 1988/1989 Biennial Budget Justification of Estimates Submitted to Congress
1988-02-01
will be installed in order to provide privacy for network data traffic. - Distributed systems technology will continue to be explored, including...techniques and geophysical and satellite data bases to make relevant information rapidly available to the ".fi /./ P ... . C / AMENDED FY 1988/1989...semantic model of available functions and data , %. AMENDED FV 1988/1989 BIENNIAL BUDGET RDT&E DESCRIPTIVE SUMMARY Program Element: fQ1Q0j, Title
Federal Register 2010, 2011, 2012, 2013, 2014
2010-03-11
... Awards (TPEA) Program is a biennial awards program developed by the FHWA and the Federal Transit... System Preservation Program Grant Application. Delta Region Transportation Development Program Grant...: Transportation, Community, and System Preservation Program Grant Application: Section 1117 of the Safe...
Li, Ji-Qing; Zhang, Yu-Shan; Ji, Chang-Ming; Wang, Ai-Jing; Lund, Jay R
2013-01-01
This paper examines long-term optimal operation using dynamic programming for a large hydropower system of 10 reservoirs in Northeast China. Besides considering flow and hydraulic head, the optimization explicitly includes time-varying electricity market prices to maximize benefit. Two techniques are used to reduce the 'curse of dimensionality' of dynamic programming with many reservoirs. Discrete differential dynamic programming (DDDP) reduces the search space and computer memory needed. Object-oriented programming (OOP) and the ability to dynamically allocate and release memory with the C++ language greatly reduces the cumulative effect of computer memory for solving multi-dimensional dynamic programming models. The case study shows that the model can reduce the 'curse of dimensionality' and achieve satisfactory results.
DOE Office of Scientific and Technical Information (OSTI.GOV)
Kao, Shih-Chieh
2014-04-25
The U.S. Department of Energy (DOE) Water Power Program tasked Oak Ridge National Laboratory with evaluating the new stream-reach development (NSD) resource potential of more than 3 million U.S. streams in order to help individuals and organizations evaluate the feasibility of developing new hydropower sources in the United States.
Estimating the Effects of Climate Change on Federal Hydropower and Power Marketing
DOE Office of Scientific and Technical Information (OSTI.GOV)
Sale, Michael J; Kao, Shih-Chieh; Uria Martinez, Rocio
The U.S. Department of Energy is currently preparing an assessment of the effects of climate change on federal hydropower, as directed by Congress in Section 9505 of the Secure Water Act of 2009 (P.L. 111-11). This paper describes the assessment approach being used in a Report to Congress currently being prepared by Oak Ridge National Laboratory. The 9505 assessment will examine climate change effects on water available for hydropower operations and the future power supplies marketed from federal hydropower projects. It will also include recommendations from the Power Marketing Administrations (PMAs) on potential changes in operation or contracting practices thatmore » could address these effects and risks of climate change. Potential adaption and mitigation strategies will also be identified. Federal hydropower comprises approximately half of the U.S. hydropower portfolio. The results from the 9505 assessment will promote better understanding among federal dam owners/operators of the sensitivity of their facilities to water availability, and it will provide a basis for planning future actions that will enable adaptation to climate variability and change. The end-users of information are Congressional members, their staff, the PMAs and their customers, federal dam owners/operators, and the DOE Water Power Program.« less
State Models to Incentivize and Streamline Small Hydropower Development
DOE Office of Scientific and Technical Information (OSTI.GOV)
Curtis, Taylor; Levine, Aaron; Johnson, Kurt
In 2016, the hydropower fleet in the United States produced more than 6 percent (approximately 265,829 gigawatt-hours [GWh]) of the total net electricity generation. The median-size hydroelectric facility in the United States is 1.6 MW and 75 percent of total facilities have a nameplate capacity of 10 MW or less. Moreover, the U.S. Department of Energy's Hydropower Vision study identified approximately 79 GW hydroelectric potential beyond what is already developed. Much of the potential identified is at low-impact new stream-reaches, existing conduits, and non-powered dams with a median project size of 10 MW or less. To optimize the potential andmore » value of small hydropower development, state governments are crafting policies that provide financial assistance and expedite state and federal review processes for small hydroelectric projects. This report analyzes state-led initiatives and programs that incentivize and streamline small hydroelectric development.« less
A Holistic Framework for Environmental Flows Determination in Hydropower Contexts
DOE Office of Scientific and Technical Information (OSTI.GOV)
McManamay, Ryan A; Bevelhimer, Mark S
2013-05-01
Among the ecological science community, the consensus view is that the natural flow regime sustains the ecological integrity of river systems. This prevailing viewpoint by many environmental stakeholders has progressively led to increased pressure on hydropower dam owners to change plant operations to affect downstream river flows with the intention of providing better conditions for aquatic biological communities. Identifying the neccessary magnitude, frequency, duration, timing, or rate of change of stream flows to meet ecological needs in a hydropower context is challenging because the ecological responses to changes in flows may not be fully known, there are usually a multitudemore » of competing users of flow, and implementing environmental flows usually comes at a price to energy production. Realistically, hydropower managers must develop a reduced set of goals that provide the most benefit to the identified ecological needs. As a part of the Department of Energy (DOE) Water Power Program, the Instream Flow Project (IFP) was carried out by Oak Ridge National Laboratory (ORNL), Pacific Northwest National Laboratory (PNNL), and Argon National Laboratory (ANL) as an attempt to develop tools aimed at defining environmental flow needs for hydropower operations. The application of these tools ranges from national to site-specific scales; thus, the utility of each tool will depend on various phases of the environmental flow process. Given the complexity and sheer volume of applications used to determine environmentally acceptable flows for hydropower, a framework is needed to organize efforts into a staged process dependent upon spatial, temporal, and functional attributes. By far, the predominant domain for determining environmental flows related to hydropower is within the Federal Energy Regulatory Commission (FERC) relicensing process. This process can take multiple years and can be very expensive depending on the scale of each hydropower project. The utility of such a framework is that it can expedite the environmental flow process by 1) organizing data and applications to identify predictable relationships between flows and ecology, and 2) suggesting when and where tools should be used in the environmental flow process. In addition to regulatory procedures, a framework should also provide the coordination for a comprehensive research agenda to guide the science of environmental flows. This research program has further reaching benefits than just environmental flow determination by providing modeling applications, data, and geospatial layers to inform potential hydropower development. We address several objectives within this document that highlight the limitations of existing environmental flow paradigms and their applications to hydropower while presenting a new framework catered towards hydropower needs. Herein, we address the following objectives: 1) Provide a brief overview of the Natural Flow Regime paradigm and existing environmental flow frameworks that have been used to determine ecologically sensitive stream flows for hydropower operations. 2) Describe a new conceptual framework to aid in determining flows needed to meet ecological objectives with regard to hydropower operations. The framework is centralized around determining predictable relationships between flow and ecological responses. 3) Provide evidence of how efforts from ORNL, PNNL, and ANL have filled some of the gaps in this broader framework, and suggest how the framework can be used to set the stage for a research agenda for environmental flow.« less
Federal Register 2010, 2011, 2012, 2013, 2014
2011-06-29
... Proposed Information Collection to OMB; Housing Counseling Program--Biennial Agency Performance Review... participate in the Housing Counseling Program. Specifically, the information collected is used to ensure that... to maintain an approval status. Housing counseling aids tenants and homeowners in [[Page 38198...
Optimizing Wind And Hydropower Generation Within Realistic Reservoir Operating Policy
NASA Astrophysics Data System (ADS)
Magee, T. M.; Clement, M. A.; Zagona, E. A.
2012-12-01
Previous studies have evaluated the benefits of utilizing the flexibility of hydropower systems to balance the variability and uncertainty of wind generation. However, previous hydropower and wind coordination studies have simplified non-power constraints on reservoir systems. For example, some studies have only included hydropower constraints on minimum and maximum storage volumes and minimum and maximum plant discharges. The methodology presented here utilizes the pre-emptive linear goal programming optimization solver in RiverWare to model hydropower operations with a set of prioritized policy constraints and objectives based on realistic policies that govern the operation of actual hydropower systems, including licensing constraints, environmental constraints, water management and power objectives. This approach accounts for the fact that not all policy constraints are of equal importance. For example target environmental flow levels may not be satisfied if it would require violating license minimum or maximum storages (pool elevations), but environmental flow constraints will be satisfied before optimizing power generation. Additionally, this work not only models the economic value of energy from the combined hydropower and wind system, it also captures the economic value of ancillary services provided by the hydropower resources. It is recognized that the increased variability and uncertainty inherent with increased wind penetration levels requires an increase in ancillary services. In regions with liberalized markets for ancillary services, a significant portion of hydropower revenue can result from providing ancillary services. Thus, ancillary services should be accounted for when determining the total value of a hydropower system integrated with wind generation. This research shows that the end value of integrated hydropower and wind generation is dependent on a number of factors that can vary by location. Wind factors include wind penetration level, variability due to geographic distribution of wind resources, and forecast error. Electric power system factors include the mix of thermal generation resources, available transmission, demand patterns, and market structures. Hydropower factors include relative storage capacity, reservoir operating policies and hydrologic conditions. In addition, the wind, power system, and hydropower factors are often interrelated because stochastic weather patterns can simultaneously influence wind generation, power demand, and hydrologic inflows. One of the central findings is that the sensitivity of the model to changes cannot be performed one factor at a time because the impact of the factors is highly interdependent. For example, the net value of wind generation may be very sensitive to changes in transmission capacity under some hydrologic conditions, but not at all under others.
ERIC Educational Resources Information Center
Texas Education Agency, Austin.
This biennial report presents: (1) information regarding progress under and compliance with the master plan for vocational education in Texas during the school years 1986-87 and 1987-88 and information regarding activities conducted during the 1988-89 school year where appropriate; and (2) quantitative and qualitative evaluative information on…
Pignone, Michael P; Flitcroft, Kathy L; Howard, Kirsten; Trevena, Lyndal J; Salkeld, Glenn P; St John, D James B
2011-02-21
To examine the costs and cost-effectiveness of full implementation of biennial bowel cancer screening for Australian residents aged 50-74 years. Identification of existing economic models from 1993 to 2010 through searches of PubMed and economic analysis databases, and by seeking expert advice; and additional modelling to determine the costs and cost-effectiveness of full implementation of biennial faecal occult blood test screening for the five million adults in Australia aged 50-74 years. Estimated number of deaths from bowel cancer prevented, costs, and cost-effectiveness (cost per life-year gained [LYG]) of biennial bowel cancer screening. We identified six relevant economic analyses, all of which found colorectal cancer (CRC) screening to be very cost-effective, with costs per LYG under $55,000 per year in 2010 Australian dollars. Based on our additional modelling, we conservatively estimate that full implementation of biennial screening for people aged 50-74 years would have gross costs of $150 million, reduce CRC mortality by 15%-25%, prevent 300-500 deaths from bowel cancer, and save 3600-6000 life-years annually, for an undiscounted cost per LYG of $25,000-$41,667, compared with no screening, and not taking cost savings as a result of treatment into consideration. The additional expenditure required, after accounting for reductions in CRC incidence, savings in CRC treatment costs, and existing ad-hoc colonoscopy use, is likely to be less than $50 million annually. Full implementation of biennial faecal occult blood test screening in Australia can reduce bowel cancer mortality, and is an efficient use of health resources that would require modest additional government investment.
Evaluation of Application Space Expansion for the Sensor Fish
DOE Office of Scientific and Technical Information (OSTI.GOV)
DeRolph, Christopher R.; Bevelhimer, Mark S.
The Pacific Northwest National Laboratory has developed an instrument known as the sensor fish that can be released into downstream passage routes at hydropower facilities to collect data on the physical conditions that a fish might be exposed to during passage through a turbine. The US Department of Energy Wind and Water Power Program sees value in expanding the sensor fish application space beyond large Kaplan turbines in the northwest United States to evaluate conditions to which a greater variety of fish species are exposed. Development of fish-friendly turbines requires an understanding of both physical passage conditions and biological responsesmore » to those conditions. Expanding the use of sensor fish into other application spaces will add to the knowledge base of physical passage conditions and could also enhance the use of sensor fish as a site-specific tool in mitigating potential impacts to fish populations from hydropower. The Oak Ridge National Laboratory (ORNL) National Hydropower Assessment Program (NHAAP) database contains hydropower facility characteristics that, along with national fish distribution data, were used to evaluate potential interactions between fish species and project characteristics related to downstream passage issues. ORNL developed rankings for the turbine types in the NHAAP database in terms of their potential to impact fish through injury or mortality during downstream turbine passage. National-scale fish distributions for 31 key migratory species were spatially intersected with hydropower plant locations to identify facilities where turbines with a high threat to fish injury or mortality overlap with the potential range of a sensitive fish species. A dataset was produced that identifies hydropower facilities where deployment of the sensor fish technology might be beneficial in addressing issues related to downstream fish passage. The dataset can be queried to target specific geographic regions, fish species, license expiration dates, generation capacity levels, ownership characteristics, turbine characteristics, or any combination of these metrics.« less
Implementation of the National Intelligent Transportation Systems Program : 1997 report to Congress
DOT National Transportation Integrated Search
2000-07-01
This report is the first biennial report on the status of the Federal Highway Administration's (FHWA) Value Pricing Pilot Program as required by the Intermodal Surface Transportation Efficiency Act of 1991, Section 1012(b)(5). It follows an iterim le...
40 CFR 35.3570 - Reports and audits.
Code of Federal Regulations, 2011 CFR
2011-07-01
... on-site visits as deemed necessary to perform the annual review. (d) Information management system—(1) Purpose. The purpose of the information management system is to assess the DWSRF programs, to monitor.... Information provided in the Biennial Report on other EPA programs eligible for assistance from the DWSRF...
40 CFR 35.3570 - Reports and audits.
Code of Federal Regulations, 2012 CFR
2012-07-01
... on-site visits as deemed necessary to perform the annual review. (d) Information management system—(1) Purpose. The purpose of the information management system is to assess the DWSRF programs, to monitor.... Information provided in the Biennial Report on other EPA programs eligible for assistance from the DWSRF...
40 CFR 35.3570 - Reports and audits.
Code of Federal Regulations, 2010 CFR
2010-07-01
... on-site visits as deemed necessary to perform the annual review. (d) Information management system—(1) Purpose. The purpose of the information management system is to assess the DWSRF programs, to monitor.... Information provided in the Biennial Report on other EPA programs eligible for assistance from the DWSRF...
40 CFR 35.3570 - Reports and audits.
Code of Federal Regulations, 2014 CFR
2014-07-01
... on-site visits as deemed necessary to perform the annual review. (d) Information management system—(1) Purpose. The purpose of the information management system is to assess the DWSRF programs, to monitor.... Information provided in the Biennial Report on other EPA programs eligible for assistance from the DWSRF...
40 CFR 35.3570 - Reports and audits.
Code of Federal Regulations, 2013 CFR
2013-07-01
... on-site visits as deemed necessary to perform the annual review. (d) Information management system—(1) Purpose. The purpose of the information management system is to assess the DWSRF programs, to monitor.... Information provided in the Biennial Report on other EPA programs eligible for assistance from the DWSRF...
Decision Support System for Reservoir Management and Operation in Africa
NASA Astrophysics Data System (ADS)
Navar, D. A.
2016-12-01
Africa is currently experiencing a surge in dam construction for flood control, water supply and hydropower production, but ineffective reservoir management has caused problems in the region, such as water shortages, flooding and loss of potential hydropower generation. Our research aims to remedy ineffective reservoir management by developing a novel Decision Support System(DSS) to equip water managers with a technical planning tool based on the state of the art in hydrological sciences. The DSS incorporates a climate forecast model, a hydraulic model of the watershed, and an optimization model to effectively plan for the operation of a system of cascade large-scale reservoirs for hydropower production, while treating water supply and flood control as constraints. Our team will use the newly constructed hydropower plants in the Omo Gibe basin of Ethiopia as the test case. Using the basic HIDROTERM software developed in Brazil, the General Algebraic Modeling System (GAMS) utilizes a combination of linear programing (LP) and non-linear programming (NLP) in conjunction with real time hydrologic and energy demand data to optimize the monthly and daily operations of the reservoir system. We compare the DSS model results with the current reservoir operating policy used by the water managers of that region. We also hope the DSS will eliminate the current dangers associated with the mismanagement of large scale water resources projects in Africa.
ERIC Educational Resources Information Center
Nevada System of Higher Education, 2011
2011-01-01
This report is prepared in accordance to state law requiring the Nevada System of Higher Education (NSHE) to prepare a biennial report for submission to the Nevada State Legislature that outlines a plan for new programs and expansions of existing programs of instruction, public service and research. This report highlights the strategic objectives…
Recreation and Park Education Curriculum Catalog, 1974-1975 Biennial Directory.
ERIC Educational Resources Information Center
Society of Park and Recreation Educators, Arlington, VA.
This catalog lists general, curriculum, and financial assistance information about park and recreation programs for 119 colleges and universities in the U.S. and Canada. General information includes the location and mailing address of the institution, enrollment data, and tuition and fees. Curriculum information includes the program title,…
Sustainable hydropower in Lower Mekong Countries: Technical assessment and training travel report
DOE Office of Scientific and Technical Information (OSTI.GOV)
Hadjerioua, Boualem; Witt, Adam M.
The U.S. Agency for International Development (USAID), through their partnership with the U.S. Department of the Interior (DOI), requested the support of Oak Ridge National Laboratory (ORNL) to provide specialized technical assistance as part of the Smart Infrastructure for the Mekong (SIM) Program in Thailand. Introduced in July 2013 by U.S. Secretary of State John Kerry, SIM is a U.S. Government Inter-Agency program that provides Lower Mekong partner countries with targeted, demand-driven technical and scientific assistance to support environmentally sound, climate conscious and socially equitable infrastructure, clean energy development, and water resources optimization. The U.S. Government is committed to supportingmore » sustainable economic development within the region by providing tools, best practices, technical assistance, and lessons learned for the benefit of partner countries. In response to a request from the Electricity Generating Authority of Thailand (EGAT), a SIM project was developed with two main activities: 1) to promote hydropower sustainability and efficiency through technical assessment training at two existing hydropower assets in Thailand, and 2) the design and implementation of one national and two or three regional science and policy workshops, to be co-hosted with EGAT, to build common understanding of and commitment to environmental and social safeguards for Mekong Basin hydropower projects. The U.S. Department of Energy (DOE) is leading the technical assessment (Activity 1), and has contracted ORNL to provide expert technical assistance focused on increasing efficiency at existing projects, with the goal of increasing renewable energy generation at little to no capital cost. ORNL is the leading national laboratory in hydropower analysis, with a nationally recognized and highly qualified team of scientists addressing small to large-scale systems (basin-, regional-, and national-scale) energy generation optimization analysis for DOE. The mission of the ORNL Water Power Program is to develop technologies, decision-support tools, and methods of analysis that enable holistic management of water-dependent energy infrastructure and natural resources in support of the DOE Energy Efficiency and Renewable Energy Office (DOE-EERE), Federal hydropower agencies, Federal Energy Regulatory Commission (FERC), Nuclear Regulatory Commission (NRC), energy producers, and other entities. In support of SIM, ORNL completed technical assessments of two hydropower plants owned and operated by the Electricity Generating Authority of Thailand (EGAT): Vajiralongkorn (VRK), with an installed capacity of 300 MW, and Rajjaprabha (RPB), with an installed capacity of 240MW. Technical assessment is defined as the assessment of hydropower operation and performance, and the identification of potential opportunities for performance improvement through plant optimization. At each plant, the assessment included an initial analysis of hydropower operating and performance metrics, provided by dam owners. After this analysis, ORNL engaged with the plant management team in a skills exchange, where best practices, operational methods, and technical challenges were discussed. The technical assessment process was outlined to plant management followed by a presentation of preliminary results and analysis based on 50 days of operational data. EGAT has agreed to provide a full year of operational data so a complete and detailed assessment that captures seasonal variability can be completed. The results of these assessments and discussions will be used to develop a set of best practices, training, and procedure recommendations to improve the efficiency of the two assessed plants« less
Cost-effectiveness of digital mammography screening before the age of 50 in The Netherlands.
Sankatsing, Valérie D V; Heijnsdijk, Eveline A M; van Luijt, Paula A; van Ravesteyn, Nicolien T; Fracheboud, Jacques; de Koning, Harry J
2015-10-15
In the Netherlands, routine mammography screening starts at age 50. This starting age may have to be reconsidered because of the increasing breast cancer incidence among women aged 40 to 49 and the recent implementation of digital mammography. We assessed the cost-effectiveness of digital mammography screening that starts between age 40 and 49, using a microsimulation model. Women were screened before age 50, in addition to the current programme (biennial 50-74). Screening strategies varied in starting age (between 40 and 50) and frequency (annual or biennial). The numbers of breast cancers diagnosed, life-years gained (LYG) and breast cancer deaths averted were predicted and incremental cost-effectiveness ratios (ICERs) were calculated to compare screening scenarios. Biennial screening from age 50 to 74 (current strategy) was estimated to gain 157 life years per 1,000 women with lifelong follow-up, compared to a situation without screening, and cost €3,376/LYG (3.5% discounted). Additional screening increased the number of LYG, compared to no screening, ranging from 168 to 242. The costs to generate one additional LYG (i.e., ICER), comparing a screening strategy to the less intensive alternative, were estimated at €5,329 (biennial 48-74 vs. current strategy), €7,628 (biennial 45-74 vs. biennial 48-74), €10,826 (biennial 40-74 vs. biennial 45-74) and €18,759 (annual 40-49 + biennial 50-74 vs. biennial 40-74). Other strategies (49 + biennial 50-74 and annual 45-49 + biennial 50-74) resulted in less favourable ICERs. These findings show that extending the Dutch screening programme by screening between age 40 and 49 is cost-effective, particularly for biennial strategies. © 2015 UICC.
Hardy, Bradley; Smeeding, Timothy; Ziliak, James P
2018-02-01
Refundable tax credits and food assistance are the largest transfer programs available to able-bodied working poor and near-poor families in the United States, and simultaneous participation in these programs has more than doubled since the early 2000s. To understand this growth, we construct a series of two-year panels from the 1981-2013 waves of the Current Population Survey Annual Social and Economic Supplement to estimate the effect of state labor-market conditions, federal and state transfer program policy choices, and household demographics governing joint participation in food and refundable tax credit programs. Overall, changing policy drives much of the increase in the simultaneous, biennial use of food assistance and refundable tax credits. This stands in stark contrast from the factors accounting for the growth in food assistance alone, where cyclical and structural labor market factors account for at least one-half of the growth, and demographics play a more prominent role. Moreover, since 2000, the business cycle factors as the leading determinant in biennial participation decisions in food programs and refundable tax credits, suggesting a recent strengthening in the relationship between economic conditions and transfer programs.
50 CFR 300.207 - Alternative procedures for bycatch of PLMRs.
Code of Federal Regulations, 2011 CFR
2011-10-01
... Secretary cannot reach a certification determination for that nation by the time of the next biennial report..., in the case of pelagic longline fisheries, the regulatory program of an identified nation includes...
Job Skills Program Biennial Report 1985-1987.
ERIC Educational Resources Information Center
Washington State Board for Vocational Education, Olympia.
The Washington State Job Skills Program (JSP) was established by the legislature in 1983 as an economic development incentive to provide customized, quick-start training to meet the employment needs of new or expanding businesses in the state. Funds are granted to public and private educational institutions to train people for new jobs, prepare…
van Ravesteyn, Nicolien T; van Lier, Lisanne; Schechter, Clyde B; Ekwueme, Donatus U; Royalty, Janet; Miller, Jacqueline W; Near, Aimee M; Cronin, Kathleen A; Heijnsdijk, Eveline A M; Mandelblatt, Jeanne S; de Koning, Harry J
2015-05-01
The National Breast and Cervical Cancer Early Detection Program (NBCCEDP) provides mammograms and diagnostic services for low-income, uninsured women aged 40-64 years. Mammography facilities within the NBCCEDP gradually shifted from plain-film to digital mammography. The purpose of this study is to assess the impact of replacing film with digital mammography on health effects (deaths averted, life-years gained [LYG]); costs (for screening and diagnostics); and number of women reached. NBCCEDP 2010 data and data representative of the program's target population were used in two established microsimulation models. Models simulated observed screening behavior including different screening intervals (annual, biennial, irregular) and starting ages (40, 50 years) for white, black, and Hispanic women. Model runs were performed in 2012. The models predicted 8.0-8.3 LYG per 1,000 film screens for black women, 5.9-7.5 for white women, and 4.0-4.5 for Hispanic women. For all race/ethnicity groups, digital mammography had more LYG than film mammography (2%-4%), but had higher costs (34%-35%). Assuming a fixed budget, 25%-26% fewer women could be served, resulting in 22%-24% fewer LYG if all mammograms were converted to digital. The loss in LYG could be reversed to an 8%-13% increase by only including biennial screening. Digital could result in slightly more LYG than film mammography. However, with a fixed budget, fewer women may be served with fewer LYG. Changes in the program, such as only including biennial screening, will increase LYG/screen and could offset the potential decrease in LYG when shifting to digital mammography. Copyright © 2015 American Journal of Preventive Medicine. All rights reserved.
Federal Register 2010, 2011, 2012, 2013, 2014
2010-05-03
... the NPIP program. Tentative topics for discussion at the upcoming meetings include: 1. Salmonella enteritidis in meat-type chickens. 2. Salmonella isolation and identification protocol. 3. Notifiable avian...
ERIC Educational Resources Information Center
Kao, Chen-yao
2012-01-01
This study examines the current problems affecting Taiwan's gifted education through a large-scale gifted program evaluation. Fifty-one gifted classes at 15 elementary schools and 62 gifted classes at 18 junior high schools were evaluated. The primary activities included in this biennial evaluation were document review, observation of…
PREDICTION OF TOTAL DISSOLVED GAS EXCHANGE AT HYDROPOWER DAMS
DOE Office of Scientific and Technical Information (OSTI.GOV)
Hadjerioua, Boualem; Pasha, MD Fayzul K; Stewart, Kevin M
2012-07-01
Total dissolved gas (TDG) supersaturation in waters released at hydropower dams can cause gas bubble trauma in fisheries resulting in physical injuries and eyeball protrusion that can lead to mortality. Elevated TDG pressures in hydropower releases are generally caused by the entrainment of air in spillway releases and the subsequent exchange of atmospheric gasses into solution during passage through the stilling basin. The network of dams throughout the Columbia River Basin (CRB) are managed for irrigation, hydropower production, flood control, navigation, and fish passage that frequently result in both voluntary and involuntary spillway releases. These dam operations are constrained bymore » state and federal water quality standards for TDG saturation which balance the benefits of spillway operations designed for Endangered Species Act (ESA)-listed fisheries versus the degradation to water quality as defined by TDG saturation. In the 1970s, the United States Environmental Protection Agency (USEPA), under the federal Clean Water Act (Section 303(d)), established a criterion not to exceed the TDG saturation level of 110% in order to protect freshwater and marine aquatic life. The states of Washington and Oregon have adopted special water quality standards for TDG saturation in the tailrace and forebays of hydropower facilities on the Columbia and Snake Rivers where spillway operations support fish passage objectives. The physical processes that affect TDG exchange at hydropower facilities have been studied throughout the CRB in site-specific studies and routine water quality monitoring programs. These data have been used to quantify the relationship between project operations, structural properties, and TDG exchange. These data have also been used to develop predictive models of TDG exchange to support real-time TDG management decisions. These empirically based predictive models have been developed for specific projects and account for both the fate of spillway and powerhouse flows in the tailrace channel and resultant exchange in route to the next downstream dam. Currently, there exists a need to summarize the general finding from operational and structural TDG abatement programs conducted throughout the CRB and for the development of a generalized prediction model that pools data collected at multiple projects with similar structural attributes. A generalized TDG exchange model can be tuned to specific projects and coupled with water regulation models to allow the formulation of optimal daily water regulation schedules subject to water quality constraints for TDG supersaturation. A generalized TDG exchange model can also be applied to other hydropower dams that affect TDG pressures in tailraces and can be used to develop alternative operational and structural measures to minimize TDG generation. It is proposed to develop a methodology for predicting TDG levels downstream of hydropower facilities with similar structural properties as a function of a set of variables that affect TDG exchange; such as tailwater depth, spill discharge and pattern, project head, and entrainment of powerhouse releases. TDG data from hydropower facilities located throughout the northwest region of the United States will be used to identify relationships between TDG exchange and relevant dependent variables. Data analysis and regression techniques will be used to develop predictive TDG exchange expressions for various structural categories.« less
DOE Office of Scientific and Technical Information (OSTI.GOV)
None
News stories about conventional hydropower and marine and hydrokinetic technologies from the U.S. Department of Energy, the Office of Energy Efficiency and Renewable Energy, the Wind and Water Power Program, and other federal agencies.
Code of Federal Regulations, 2012 CFR
2012-10-01
..., plume pathway EPZ biennial exercise-related component services and other services. 354.5 Section 354.5... Description of site-specific, plume pathway EPZ biennial exercise-related component services and other... will assess fees on licensees include the following: (a) Site-specific, plume pathway EPZ biennial...
Reducing Traffic Congestion: Using Market Prices to Enhance Mobility
DOT National Transportation Integrated Search
1998-01-01
This is the Department of Transportation's 1997 biennial report on the Congestion Pricing Pilot Program, as required by Section 1012(b) of the Intermodal Surface Transportation Efficiency Act of 1991, P.L. 102-240. The report highlights the significa...
49 CFR 390.203 - PRISM State registration/biennial updates.
Code of Federal Regulations, 2013 CFR
2013-10-01
... the Performance and Registration Information Systems Management (PRISM) program (authorized under... FEDERAL MOTOR CARRIER SAFETY REGULATIONS; GENERAL Unified Registration System § 390.203 PRISM State... procedures, provided the State has integrated the USDOT registration/update capability into its vehicle...
49 CFR 390.203 - PRISM State registration/biennial updates.
Code of Federal Regulations, 2014 CFR
2014-10-01
... the Performance and Registration Information Systems Management (PRISM) program (authorized under... FEDERAL MOTOR CARRIER SAFETY REGULATIONS; GENERAL Unified Registration System § 390.203 PRISM State... procedures, provided the State has integrated the USDOT registration/update capability into its vehicle...
Consistency of the New York State bridge inspection program.
DOT National Transportation Integrated Search
2013-09-01
The New York State Department of Transportation (NYSDOT) maintains an inventory of over 17,000 highway : bridges across the state. As per New York States Uniform Code of Bridge Inspections, all bridges in New York : State are inspected biennially,...
Winch, Caleb J; Sherman, Kerry A; Boyages, John
2015-01-01
This study aimed to: (1) Estimate cumulative risk of recall from breast screening where no cancer is detected (a harm) in Australia; (2) Compare women screened annually versus biennially, commencing age 40 versus 50; and (3) Compare with international findings. At the no-cost metropolitan program studied, women attended biennial screening, but were offered annual screening if regarded at elevated risk for breast cancer. The cumulative risk of at least one recall was estimated using discrete-time survival analysis. Cancer detection statistics were computed. In total, 801,636 mammograms were undertaken in 231,824 women. Over 10 years, cumulative risk of recall was 13.3 % (95 % CI 12.7-13.8) for those screened biennially, and 19.9 % (CI 16.6-23.2) for those screened annually from age 50-51. Cumulative risk of complex false positive involving a biopsy was 3.1 % (CI 2.9-3.4) and 5.0 % (CI 3.4-6.6), respectively. From age 40-41, the risk of recall was 15.1 % (CI 14.3-16.0) and 22.5 % (CI 17.9-27.1) for biennial and annual screening, respectively. Corresponding rates of complex false positive were 3.3 % (CI 2.9-3.8) and 6.3 % (CI 3.4-9.1). Over 10 mammograms, invasive cancer was detected in 3.4 % (CI 3.3-3.5) and ductal carcinoma in situ in 0.7 % (CI 0.6-0.7) of women, with a non-significant trend toward a larger proportion of Tis and T1N0 cancers in women screened annually (74.5 %) versus biennially (70.1 %), χ (2) = 2.77, p = 0.10. Cancer detection was comparable to international findings. Recall risk was equal to European estimates for women screening from 50 and lower for screening from 40. Recall risk was half of United States' rates across start age and rescreening interval categories. Future benefit/harm balance sheets may be useful for communicating these findings to women.
ERIC Educational Resources Information Center
Montgomery County Public Schools, 2013
2013-01-01
In November 1996, the voters of Montgomery County (Maryland) approved by referendum an amendment to the County Charter that changed the County Council's review and approval cycle of the six-year Capital Improvements Program (CIP) from an annual to biennial cycle. The referendum specified that in odd-numbered fiscal years (on-years) the County…
ERIC Educational Resources Information Center
Montgomery County Public Schools, 2010
2010-01-01
In November 1996, the voters of Montgomery County (Maryland) approved by referendum an amendment to the County Charter that changed the County Council's review and approval cycle of the six-year Capital Improvements Program (CIP) from an annual to biennial cycle. The referendum specified that in odd-numbered fiscal years (on-years) the County…
ERIC Educational Resources Information Center
Montgomery County Public Schools, 2009
2009-01-01
In November 1996, the voters of Montgomery County approved by referendum an amendment to the County Charter that changed the County Council's review and approval cycle of the six-year Capital Improvements Program (CIP) from an annual to biennial cycle. The referendum specified that in odd-numbered fiscal years (on-years) the County Council would…
ERIC Educational Resources Information Center
Montgomery County Public Schools, 2012
2012-01-01
In November 1996, the voters of Montgomery County (Maryland) approved by referendum an amendment to the County Charter that changed the County Council's review and approval cycle of the six-year Capital Improvements Program (CIP) from an annual to biennial cycle. The referendum specified that in odd-numbered fiscal years (on years) the County…
ERIC Educational Resources Information Center
Montgomery County Public Schools, 2006
2006-01-01
In November 1996, the voters of Montgomery County (Maryland) approved by referendum an amendment to the County Charter that changed the County Council's review and approval cycle of the six-year Capital Improvements Program (CIP) from an annual to biennial cycle. The referendum specified that in odd-numbered fiscal years (on years) the County…
ERIC Educational Resources Information Center
Montgomery County Public Schools, 2007
2007-01-01
In November 1996, the voters of Montgomery County (Maryland) approved by referendum an amendment to the County Charter that changed the County Council's review and approval cycle of the six-year Capital Improvements Program (CIP) from an annual to biennial cycle. The referendum specified that in odd-numbered fiscal years (on years) the County…
Si, Yuan; Li, Xiang; Yin, Dongqin; Liu, Ronghua; Wei, Jiahua; Huang, Yuefei; Li, Tiejian; Liu, Jiahong; Gu, Shenglong; Wang, Guangqian
2018-01-01
The hydropower system in the Upper Yellow River (UYR), one of the largest hydropower bases in China, plays a vital role in the energy structure of the Qinghai Power Grid. Due to management difficulties, there is still considerable room for improvement in the joint operation of this system. This paper presents a general LINGO-based integrated framework to study the operation of the UYR hydropower system. The framework is easy to use for operators with little experience in mathematical modeling, takes full advantage of LINGO's capabilities (such as its solving capacity and multi-threading ability), and packs its three layers (the user layer, the coordination layer, and the base layer) together into an integrated solution that is robust and efficient and represents an effective tool for data/scenario management and analysis. The framework is general and can be easily transferred to other hydropower systems with minimal effort, and it can be extended as the base layer is enriched. The multi-objective model that represents the trade-off between power quantity (i.e., maximum energy production) and power reliability (i.e., firm output) of hydropower operation has been formulated. With equivalent transformations, the optimization problem can be solved by the nonlinear programming (NLP) solvers embedded in the LINGO software, such as the General Solver, the Multi-start Solver, and the Global Solver. Both simulation and optimization are performed to verify the model's accuracy and to evaluate the operation of the UYR hydropower system. A total of 13 hydropower plants currently in operation are involved, including two pivotal storage reservoirs on the Yellow River, which are the Longyangxia Reservoir and the Liujiaxia Reservoir. Historical hydrological data from multiple years (2000-2010) are provided as input to the model for analysis. The results are as follows. 1) Assuming that the reservoirs are all in operation (in fact, some reservoirs were not operational or did not collect all of the relevant data during the study period), the energy production is estimated as 267.7, 357.5, and 358.3×108 KWh for the Qinghai Power Grid during dry, normal, and wet years, respectively. 2) Assuming that the hydropower system is operated jointly, the firm output can reach 3110 MW (reliability of 100%) and 3510 MW (reliability of 90%). Moreover, a decrease in energy production from the Longyangxia Reservoir can bring about a very large increase in firm output from the hydropower system. 3) The maximum energy production can reach 297.7, 363.9, and 411.4×108 KWh during dry, normal, and wet years, respectively. The trade-off curve between maximum energy production and firm output is also provided for reference.
Si, Yuan; Liu, Ronghua; Wei, Jiahua; Huang, Yuefei; Li, Tiejian; Liu, Jiahong; Gu, Shenglong; Wang, Guangqian
2018-01-01
The hydropower system in the Upper Yellow River (UYR), one of the largest hydropower bases in China, plays a vital role in the energy structure of the Qinghai Power Grid. Due to management difficulties, there is still considerable room for improvement in the joint operation of this system. This paper presents a general LINGO-based integrated framework to study the operation of the UYR hydropower system. The framework is easy to use for operators with little experience in mathematical modeling, takes full advantage of LINGO’s capabilities (such as its solving capacity and multi-threading ability), and packs its three layers (the user layer, the coordination layer, and the base layer) together into an integrated solution that is robust and efficient and represents an effective tool for data/scenario management and analysis. The framework is general and can be easily transferred to other hydropower systems with minimal effort, and it can be extended as the base layer is enriched. The multi-objective model that represents the trade-off between power quantity (i.e., maximum energy production) and power reliability (i.e., firm output) of hydropower operation has been formulated. With equivalent transformations, the optimization problem can be solved by the nonlinear programming (NLP) solvers embedded in the LINGO software, such as the General Solver, the Multi-start Solver, and the Global Solver. Both simulation and optimization are performed to verify the model’s accuracy and to evaluate the operation of the UYR hydropower system. A total of 13 hydropower plants currently in operation are involved, including two pivotal storage reservoirs on the Yellow River, which are the Longyangxia Reservoir and the Liujiaxia Reservoir. Historical hydrological data from multiple years (2000–2010) are provided as input to the model for analysis. The results are as follows. 1) Assuming that the reservoirs are all in operation (in fact, some reservoirs were not operational or did not collect all of the relevant data during the study period), the energy production is estimated as 267.7, 357.5, and 358.3×108 KWh for the Qinghai Power Grid during dry, normal, and wet years, respectively. 2) Assuming that the hydropower system is operated jointly, the firm output can reach 3110 MW (reliability of 100%) and 3510 MW (reliability of 90%). Moreover, a decrease in energy production from the Longyangxia Reservoir can bring about a very large increase in firm output from the hydropower system. 3) The maximum energy production can reach 297.7, 363.9, and 411.4×108 KWh during dry, normal, and wet years, respectively. The trade-off curve between maximum energy production and firm output is also provided for reference. PMID:29370206
NASA Astrophysics Data System (ADS)
Rheinheimer, David Emmanuel
Hydropower systems and other river regulation often harm instream ecosystems, partly by altering the natural flow and temperature regimes that ecosystems have historically depended on. These effects are compounded at regional scales. As hydropower and ecosystems are increasingly valued globally due to growing values for clean energy and native species as well as and new threats from climate warming, it is important to understand how climate warming might affect these systems, to identify tradeoffs between different water uses for different climate conditions, and to identify promising water management solutions. This research uses traditional simulation and optimization to explore these issues in California's upper west slope Sierra Nevada mountains. The Sierra Nevada provides most of the water for California's vast water supply system, supporting high-elevation hydropower generation, ecosystems, recreation, and some local municipal and agricultural water supply along the way. However, regional climate warming is expected to reduce snowmelt and shift runoff to earlier in the year, affecting all water uses. This dissertation begins by reviewing important literature related to the broader motivations of this study, including river regulation, freshwater conservation, and climate change. It then describes three substantial studies. First, a weekly time step water resources management model spanning the Feather River watershed in the north to the Kern River watershed in the south is developed. The model, which uses the Water Evaluation And Planning System (WEAP), includes reservoirs, run-of-river hydropower, variable head hydropower, water supply demand, and instream flow requirements. The model is applied with a runoff dataset that considers regional air temperature increases of 0, 2, 4 and 6 °C to represent historical, near-term, mid-term and far-term (end-of-century) warming. Most major hydropower turbine flows are simulated well. Reservoir storage is also generally well simulated, mostly limited by the accuracy of inflow hydrology. System-wide hydropower generation is reduced by 9% with 6 °C warming. Most reductions in hydropower generation occur in the highly productive watersheds in the northern Sierra Nevada. The central Sierra Nevada sees less reduction in annual runoff and can adapt better to changes in runoff timing. Generation in southern watersheds is expected to decrease. System-wide, reservoirs adapt to capture earlier runoff, but mostly decrease in mean reservoir storage with warming due to decreasing annual runoff. Second, a multi-reservoir optimization model is developed using linear programming that considers the minimum instream flows (MIFs) and weekly down ramp rates (DRRs) in the Upper Yuba River in the northern Sierra Nevada. Weekly DRR constraints are used to mimic spring snowmelt flows, which are particularly important for downstream ecosystems in the Sierra Nevada but are currently missing due to the influence of dams. Trade-offs between MIFs, DRRs and hydropower are explored with air temperature warming (+0, 2, 4 and 6 °C). Under base case operations, mean annual hydropower generation increases slightly with 2 °C warming and decreases slightly with 6 °C warming. With 6 °C warming, the most ecologically beneficial MIF and DRR reduce hydropower generation 5.5% compared to base case operations and a historical climate, which has important implications for re-licensing the hydropower project. Finally, reservoir management for downstream temperatures is explored using a linear programming model to optimally release water from a reservoir using selective withdrawal. The objective function is to minimize deviations from desired downstream temperatures, which are specified to mimic the natural temperature regime in the river. One objective of this study was to develop a method that can be readily integrated into a basin-scale multi-reservoir optimization model using a network representation of system features. The second objective was to explore the potential use of reservoirs to maintain an ideal stream temperature regime to ameliorate the temperature effects of climate warming of air temperature. For proof-of-concept, the model is applied to Lake Spaulding in the Upper Yuba River. With selective withdrawal, the model hedges the release of cold water to decrease summer stream temperatures, but at a cost of warmer stream temperatures in the winter. Results also show that selective withdrawal can reduce, but not eliminate, the temperature effects of climate warming. The model can be extended to include other nearby reservoirs to optimally manage releases from multiple reservoirs for multiple downstream temperature targets in a highly interconnected system. While the outcomes of these studies contribute to our understanding of reservoir management and hydropower at the intersection of energy, water management, ecosystems, and climate warming, there are many opportunities to improve this work. Promising options for improving and building on the collective utility of these studies are presented.
Wind for Schools Affiliate Programs: Wind and Hydropower Technologies Program (Fact Sheet)
DOE Office of Scientific and Technical Information (OSTI.GOV)
Not Available
2009-12-01
The U.S. Department of Energy's (DOE's) Wind for Schools program is designed to raise awareness about the benefits of wind energy while simultaneously developing a wind energy knowledge base in future leaders of our communities, states, and nation. To accommodate the many stakeholders who are interested in the program, a Wind for Schools affiliate program has been implemented. This document describes the affiliate program and how interested schools may participate.
Genetic control of biennial bearing in apple
Guitton, Baptiste; Kelner, Jean-Jacques; Velasco, Riccardo; Gardiner, Susan E.; Chagné, David; Costes, Evelyne
2012-01-01
Although flowering in mature fruit trees is recurrent, floral induction can be strongly inhibited by concurrent fruiting, leading to a pattern of irregular fruiting across consecutive years referred to as biennial bearing. The genetic determinants of biennial bearing in apple were investigated using the 114 flowering individuals from an F1 population of 122 genotypes, from a ‘Starkrimson’ (strong biennial bearer)בGranny Smith’ (regular bearer) cross. The number of inflorescences, and the number and the mass of harvested fruit were recorded over 6 years and used to calculate 26 variables and indices quantifying yield, precocity of production, and biennial bearing. Inflorescence traits exhibited the highest genotypic effect, and three quantitative trait loci (QTLs) on linkage group (LG) 4, LG8, and LG10 explained 50% of the phenotypic variability for biennial bearing. Apple orthologues of flowering and hormone-related genes were retrieved from the whole-genome assembly of ‘Golden Delicious’ and their position was compared with QTLs. Four main genomic regions that contain floral integrator genes, meristem identity genes, and gibberellin oxidase genes co-located with QTLs. The results indicated that flowering genes are less likely to be responsible for biennial bearing than hormone-related genes. New hypotheses for the control of biennial bearing emerged from QTL and candidate gene co-locations and suggest the involvement of different physiological processes such as the regulation of flowering genes by hormones. The correlation between tree architecture and biennial bearing is also discussed. PMID:21963613
Federal Register 2010, 2011, 2012, 2013, 2014
2011-03-23
... social and economic consequences (poor academic performance, substance use, multiple disorders, suicides... substances, impact the whole community. Probable consequences include depression, domestic violence, child... financial resources; and Developing a biennial program plan, including specific objectives, performance...
THE ABRF MARG MICROARRAY SURVEY 2005: TAKING THE PULSE ON THE MICROARRAY FIELD
Over the past several years microarray technology has evolved into a critical component of any discovery based program. Since 1999, the Association of Biomolecular Resource Facilities (ABRF) Microarray Research Group (MARG) has conducted biennial surveys designed to generate a pr...
Niëns, Laurens M; Zelle, Sten G; Gutiérrez-Delgado, Cristina; Rivera Peña, Gustavo; Hidalgo Balarezo, Blanca Rosa; Rodriguez Steller, Erick; Rutten, Frans F H
2014-01-01
This paper reports the most cost-effective policy options to support and improve breast cancer control in Costa Rica and Mexico. Total costs and effects of breast cancer interventions were estimated using the health care perspective and WHO-CHOICE methodology. Effects were measured in disability-adjusted life years (DALYs) averted. Costs were assessed in 2009 United States Dollars (US$). To the extent available, analyses were based on locally obtained data. In Costa Rica, the current strategy of treating breast cancer in stages I to IV at a 80% coverage level seems to be the most cost-effective with an incremental cost-effectiveness ratio (ICER) of US$4,739 per DALY averted. At a coverage level of 95%, biennial clinical breast examination (CBE) screening could improve Costa Rica's population health twofold, and can still be considered very cost-effective (ICER US$5,964/DALY). For Mexico, our results indicate that at 95% coverage a mass-media awareness raising program (MAR) could be the most cost-effective (ICER US$5,021/DALY). If more resources are available in Mexico, biennial mammography screening for women 50-70 yrs (ICER US$12,718/DALY), adding trastuzumab (ICER US$13,994/DALY) or screening women 40-70 yrs biennially plus trastuzumab (ICER US$17,115/DALY) are less cost-effective options. We recommend both Costa Rica and Mexico to engage in MAR, CBE or mammography screening programs, depending on their budget. The results of this study should be interpreted with caution however, as the evidence on the intervention effectiveness is uncertain. Also, these programs require several organizational, budgetary and human resources, and the accessibility of breast cancer diagnostic, referral, treatment and palliative care facilities should be improved simultaneously. A gradual implementation of early detection programs should give the respective Ministries of Health the time to negotiate the required budget, train the required human resources and understand possible socioeconomic barriers.
Niëns, Laurens M.; Zelle, Sten G.; Gutiérrez-Delgado, Cristina; Rivera Peña, Gustavo; Hidalgo Balarezo, Blanca Rosa; Rodriguez Steller, Erick; Rutten, Frans F. H.
2014-01-01
This paper reports the most cost-effective policy options to support and improve breast cancer control in Costa Rica and Mexico. Total costs and effects of breast cancer interventions were estimated using the health care perspective and WHO-CHOICE methodology. Effects were measured in disability-adjusted life years (DALYs) averted. Costs were assessed in 2009 United States Dollars (US$). To the extent available, analyses were based on locally obtained data. In Costa Rica, the current strategy of treating breast cancer in stages I to IV at a 80% coverage level seems to be the most cost-effective with an incremental cost-effectiveness ratio (ICER) of US$4,739 per DALY averted. At a coverage level of 95%, biennial clinical breast examination (CBE) screening could improve Costa Rica's population health twofold, and can still be considered very cost-effective (ICER US$5,964/DALY). For Mexico, our results indicate that at 95% coverage a mass-media awareness raising program (MAR) could be the most cost-effective (ICER US$5,021/DALY). If more resources are available in Mexico, biennial mammography screening for women 50–70 yrs (ICER US$12,718/DALY), adding trastuzumab (ICER US$13,994/DALY) or screening women 40–70 yrs biennially plus trastuzumab (ICER US$17,115/DALY) are less cost-effective options. We recommend both Costa Rica and Mexico to engage in MAR, CBE or mammography screening programs, depending on their budget. The results of this study should be interpreted with caution however, as the evidence on the intervention effectiveness is uncertain. Also, these programs require several organizational, budgetary and human resources, and the accessibility of breast cancer diagnostic, referral, treatment and palliative care facilities should be improved simultaneously. A gradual implementation of early detection programs should give the respective Ministries of Health the time to negotiate the required budget, train the required human resources and understand possible socioeconomic barriers. PMID:24769920
Federal Register 2010, 2011, 2012, 2013, 2014
2010-10-26
... Hydropower, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments...: Inglis Hydropower, LLC. e. Name of Project: Inglis Hydropower Project. f. Location: The project would be... ready for environmental analysis at this time. l. The proposed 2.0-megawatt Inglis Hydropower Project...
Hydropower Baseline Cost Modeling
DOE Office of Scientific and Technical Information (OSTI.GOV)
O'Connor, Patrick W.; Zhang, Qin Fen; DeNeale, Scott T.
Recent resource assessments conducted by the United States Department of Energy have identified significant opportunities for expanding hydropower generation through the addition of power to non-powered dams and on undeveloped stream-reaches. Additional interest exists in the powering of existing water resource infrastructure such as conduits and canals, upgrading and expanding existing hydropower facilities, and the construction new pumped storage hydropower. Understanding the potential future role of these hydropower resources in the nation’s energy system requires an assessment of the environmental and techno-economic issues associated with expanding hydropower generation. To facilitate these assessments, this report seeks to fill the current gapsmore » in publically available hydropower cost-estimating tools that can support the national-scale evaluation of hydropower resources.« less
Hydropower Baseline Cost Modeling, Version 2
DOE Office of Scientific and Technical Information (OSTI.GOV)
O'Connor, Patrick W.
Recent resource assessments conducted by the United States Department of Energy have identified significant opportunities for expanding hydropower generation through the addition of power to non-powered dams and on undeveloped stream-reaches. Additional interest exists in the powering of existing water resource infrastructure such as conduits and canals, upgrading and expanding existing hydropower facilities, and the construction new pumped storage hydropower. Understanding the potential future role of these hydropower resources in the nation’s energy system requires an assessment of the environmental and techno-economic issues associated with expanding hydropower generation. To facilitate these assessments, this report seeks to fill the current gapsmore » in publically available hydropower cost estimating tools that can support the national-scale evaluation of hydropower resources.« less
Ergonomics program management in Tucuruí Hydropower Plant using TPM methodology.
Santos, R M; Sassi, A C; Sá, B M; Miguez, S A; Pardauil, A A
2012-01-01
This paper aims to present the benefits achieved in the ergonomics process management with the use of the TPM methodology (Total Productive Maintenance) in Tucuruí Hydropower Plant. The methodology is aligned with the corporate guidelines, moreover with the Strategic Planning of the company, it is represented in the TPM Pillars including the Health Pillar in which is inserted the ergonomics process. The results of the ergonomic actions demonstrated a 12% reduction over the absenteeism rate due to musculoskeletal disorders, solving 77,0% of ergonomic non-conformities, what favored the rise of the Organizational Climate in 44,8%, impacting on the overall performance of the company. Awards confirmed the success of the work by the achievement of the Award for TPM Excellence in 2001, Award for Excellence in Consistent TPM Commitment in 2009 and more recently the Special Award for TPM Achievement, 2010. The determination of the high rank administration and workers, allied with the involvement/dynamism of Pillars, has assured the success of this management practice in Tucuruí Hydropower Plant.
Application procedures for hydropower licenses, exemptions, and preliminary permits
DOE Office of Scientific and Technical Information (OSTI.GOV)
Not Available
1982-04-01
This document provides essential information regarding the FERC's regulations and procedures for filing an application with the Commission for hydropower licenses, exemptions and preliminary permits. Each section is page numbered with a roman numeral followed by consecutive arabic numbering. The appendices are page numbered with an alphabetical prefix and consecutve page numbering within each section. The first section of this book contains background descriptions of the Commission's authority and regulations and serves as an introduction to the Commission's hydropower licensing program. Two general tables follow this introductory text and provide a quick reference to the types of applications and themore » relationship between the Commission's orders and regulations. Following the introduction are sections which include the Commission's regulations by application type: preliminary permits; licenses; and exemptions. Each section contains an introduction describing application procedures by type of action requested. There are two appendices provided contain information on the consultation process and lists of agencies to be consulted and a section by section analyses of the Commission's orders.« less
Water Power Technologies FY 2017 Budget At-A-Glance
DOE Office of Scientific and Technical Information (OSTI.GOV)
None
2016-03-01
The Water Power Program is committed to developing and deploying a portfolio of innovative technologies and market solutions for clean, domestic power generation from water resources across the U.S. (hydropower, marine and hydrokinetics).
42 CFR 493.643 - Fee for determination of program compliance.
Code of Federal Regulations, 2013 CFR
2013-10-01
... sets the fee amounts annually on a calendar year basis. Laboratories are inspected biennially... additional fee is based on the actual resources and time necessary to perform the activities. (c..., and proficiency testing purposes). (i) (A) Schedule A Low Volume. The laboratory performs not more...
42 CFR 493.643 - Fee for determination of program compliance.
Code of Federal Regulations, 2012 CFR
2012-10-01
... sets the fee amounts annually on a calendar year basis. Laboratories are inspected biennially... additional fee is based on the actual resources and time necessary to perform the activities. (c..., and proficiency testing purposes). (i) (A) Schedule A Low Volume. The laboratory performs not more...
42 CFR 493.643 - Fee for determination of program compliance.
Code of Federal Regulations, 2014 CFR
2014-10-01
... sets the fee amounts annually on a calendar year basis. Laboratories are inspected biennially... additional fee is based on the actual resources and time necessary to perform the activities. (c..., and proficiency testing purposes). (i) (A) Schedule A Low Volume. The laboratory performs not more...
44 CFR Appendix B to Part 62 - National Flood Insurance Program
Code of Federal Regulations, 2014 CFR
2014-10-01
... quality control departments, or both, and independent Certified Public Accountant (CPA) firms. This Plan... individual State Insurance Departments, NAIC Zone examinations, and independent CPA firms. (c) Standards... company must— (A) Have a biennial audit of the flood insurance financial statements conducted by a CPA...
44 CFR Appendix B to Part 62 - National Flood Insurance Program
Code of Federal Regulations, 2013 CFR
2013-10-01
... quality control departments, or both, and independent Certified Public Accountant (CPA) firms. This Plan... individual State Insurance Departments, NAIC Zone examinations, and independent CPA firms. (c) Standards... company must— (A) Have a biennial audit of the flood insurance financial statements conducted by a CPA...
Water resources planning and management : A stochastic dual dynamic programming approach
NASA Astrophysics Data System (ADS)
Goor, Q.; Pinte, D.; Tilmant, A.
2008-12-01
Allocating water between different users and uses, including the environment, is one of the most challenging task facing water resources managers and has always been at the heart of Integrated Water Resources Management (IWRM). As water scarcity is expected to increase over time, allocation decisions among the different uses will have to be found taking into account the complex interactions between water and the economy. Hydro-economic optimization models can capture those interactions while prescribing efficient allocation policies. Many hydro-economic models found in the literature are formulated as large-scale non linear optimization problems (NLP), seeking to maximize net benefits from the system operation while meeting operational and/or institutional constraints, and describing the main hydrological processes. However, those models rarely incorporate the uncertainty inherent to the availability of water, essentially because of the computational difficulties associated stochastic formulations. The purpose of this presentation is to present a stochastic programming model that can identify economically efficient allocation policies in large-scale multipurpose multireservoir systems. The model is based on stochastic dual dynamic programming (SDDP), an extension of traditional SDP that is not affected by the curse of dimensionality. SDDP identify efficient allocation policies while considering the hydrologic uncertainty. The objective function includes the net benefits from the hydropower and irrigation sectors, as well as penalties for not meeting operational and/or institutional constraints. To be able to implement the efficient decomposition scheme that remove the computational burden, the one-stage SDDP problem has to be a linear program. Recent developments improve the representation of the non-linear and mildly non- convex hydropower function through a convex hull approximation of the true hydropower function. This model is illustrated on a cascade of 14 reservoirs on the Nile river basin.
DOE Office of Scientific and Technical Information (OSTI.GOV)
Not Available
2014-02-01
This document represents a collection of all presentations given during the EERE Wind and Water Power Program's 2014 Marine and Hydrokinetic Peer Review. The purpose of the meeting was to evaluate DOE-funded hydropower and marine and hydrokinetic R&D projects for their contribution to the mission and goals of the Water Power Program and to assess progress made against stated objectives.
Final Report on Kokes Awards for the 20th North American Catalysis Society Meeting
DOE Office of Scientific and Technical Information (OSTI.GOV)
Wong, Michael S
2008-12-31
This Final Report describes how the Kokes Awards program was carried out for the 2007 meeting with regard to selection of students and disbursement of funds received from DOE and other sources. The objective of the Richard J. Kokes Travel Award program of the American Catalysis Society is to encourage graduate students to attend and participate meaningfully in the biennial North American Catalysis Society Meeting.
Proceedings of the 13th biennial conference on carbon. Extended abstracts and program
DOE Office of Scientific and Technical Information (OSTI.GOV)
None
1977-01-01
Properties of carbon are covered including: mechanical and frictional properties; chemical reactivity and surfaces; aerospace applications; carbonization and graphitization; industrial applications; electrical and thermal properties; biomaterials applications; fibers and composites; nuclear applications; activated carbon and adsorption; advances in carbon characterization; and micromechanics and modeling. (GHT)
College Freshmen with Disabilities, 2001: A Biennial Statistical Profile.
ERIC Educational Resources Information Center
Henderson, Cathy
This report presents data describing students who reported disabilities and who enrolled in Fall 2000 as full-time freshmen at public and independent four-year colleges and universities. Data were taken from the Cooperative Institutional Research Program survey. Highlights of the survey are organized into the following categories: personal and…
UNESCO Asia and Pacific Regional Bureau for Education Annual Report, 2000-2001.
ERIC Educational Resources Information Center
United Nations Educational, Scientific and Cultural Organization, Bangkok (Thailand). Principal Regional Office for Asia and the Pacific.
This biennial report highlights the major programs and activities organized, supported, and implemented by the United Nations Educational, Scientific and Cultural Organization (UNESCO) Asian and Pacific Regional Bureau for Education, based in Bangkok, Thailand, in the fields of education, science, social and human sciences, culture, and…
Federal Register 2010, 2011, 2012, 2013, 2014
2010-06-10
... Progress Report of the Interagency Coordinating Committee on the Validation of Alternative Methods (ICCVAM... of the Biennial Progress Report 2008-2009: Interagency Coordinating Committee on the Validation of...) 919-541-0947, (e-mail) [email protected] . FOR FURTHER INFORMATION CONTACT: Dr. William S. Stokes...
40 CFR 130.8 - Water quality report.
Code of Federal Regulations, 2014 CFR
2014-07-01
... 40 Protection of Environment 22 2014-07-01 2013-07-01 true Water quality report. 130.8 Section 130.8 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) WATER PROGRAMS WATER QUALITY PLANNING AND MANAGEMENT § 130.8 Water quality report. (a) Each State shall prepare and submit biennially to...
Dimensions of the Independent Sector: A Statistical Profile. Second Edition.
ERIC Educational Resources Information Center
Hodgkinson, Virginia Ann; Weitzman, Murray S.
The second in a biennial series of statistical profiles of the independent sector (voluntary sector, third sector, or nonprofit sector) describes and charts the activities of groups and individuals associated with this sector. Included are voluntary organizations, foundations, the social responsibility programs of corporations, and people who…
NASA Astrophysics Data System (ADS)
Kim, Jinju; Kim, Kwang-Yul
2016-10-01
Temporal and spatial patterns of anomalous atmospheric circulation and precipitation over the Indo-Pacific region are analyzed in conjunction with the Tropospheric Biennial Oscillation as represented by the biennial mode of sea surface temperature anomalies (SSTA). The biennial components of key variables are identified independently of other variability via CSEOF analysis. Then, its impact on the Asian-Australian monsoon is examined. The biennial mode exhibits a seasonally distinctive atmospheric response over the tropical eastern Indo-western Pacific (EIWP) region (90°-150°E, 20°S-20°N). In boreal summer, local meridional circulation is a distinguishing characteristic over the tropical EIWP region, whereas a meridionally expanded branch of intensified zonal circulation develops in austral summer. Temporally varying evolution and distinct timing of SSTA phase transition in the Indian and Pacific Oceans is considered a main factor for this variation of circulation in the tropical EIWP region. The impact of the biennial mode is not the same between the two seasons, with different impacts over ocean areas in Asian monsoon and Australian monsoon regions.
Open-Source as a strategy for operational software - the case of Enki
NASA Astrophysics Data System (ADS)
Kolberg, Sjur; Bruland, Oddbjørn
2014-05-01
Since 2002, SINTEF Energy has been developing what is now known as the Enki modelling system. This development has been financed by Norway's largest hydropower producer Statkraft, motivated by a desire for distributed hydrological models in operational use. As the owner of the source code, Statkraft has recently decided on Open Source as a strategy for further development, and for migration from an R&D context to operational use. A current cooperation project is currently carried out between SINTEF Energy, 7 large Norwegian hydropower producers including Statkraft, three universities and one software company. Of course, the most immediate task is that of software maturing. A more important challenge, however, is one of gaining experience within the operational hydropower industry. A transition from lumped to distributed models is likely to also require revision of measurement program, calibration strategy, use of GIS and modern data sources like weather radar and satellite imagery. On the other hand, map based visualisations enable a richer information exchange between hydrologic forecasters and power market traders. The operating context of a distributed hydrology model within hydropower planning is far from settled. Being both a modelling framework and a library of plugin-routines to build models from, Enki supports the flexibility needed in this situation. Recent development has separated the core from the user interface, paving the way for a scripting API, cross-platform compilation, and front-end programs serving different degrees of flexibility, robustness and security. The open source strategy invites anyone to use Enki and to develop and contribute new modules. Once tested, the same modules are available for the operational versions of the program. A core challenge is to offer rigid testing procedures and mechanisms to reject routines in an operational setting, without limiting the experimentation with new modules. The Open Source strategy also has implications for building and maintaining competence around the source code and the advanced hydrological and statistical routines in Enki. Originally developed by hydrologists, the Enki code is now approaching a state where maintenance requires a background in professional software development. Without the advantage of proprietary source code, both hydrologic improvements and software maintenance depend on donations or development support on a case-to-case basis, a situation well known within the open source community. It remains to see whether these mechanisms suffice to keep Enki at the maintenance level required by the hydropower sector. ENKI is available from www.opensource-enki.org.
Optimizing Hydropower Day-Ahead Scheduling for the Oroville-Thermalito Project
NASA Astrophysics Data System (ADS)
Veselka, T. D.; Mahalik, M.
2012-12-01
Under an award from the U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy, Water Power Program, a team of national laboratories is developing and demonstrating a suite of advanced, integrated analytical tools to assist managers and planners increase hydropower resources while enhancing the environment. As part of the project, Argonne National Laboratory is developing the Conventional Hydropower Energy and Environmental Systems (CHEERS) model to optimize day-ahead scheduling and real-time operations. We will present the application of CHEERS to the Oroville-Thermalito Project located in Northern California. CHEERS will aid California Department of Water Resources (CDWR) schedulers in making decisions about unit commitments and turbine-level operating points using a system-wide approach to increase hydropower efficiency and the value of power generation and ancillary services. The model determines schedules and operations that are constrained by physical limitations, characteristics of plant components, operational preferences, reliability, and environmental considerations. The optimization considers forebay and afterbay implications, interactions between cascaded power plants, turbine efficiency curves and rough zones, and operator preferences. CHEERS simultaneously considers over time the interactions among all CDWR power and water resources, hydropower economics, reservoir storage limitations, and a set of complex environmental constraints for the Thermalito Afterbay and Feather River habitats. Power marketers, day-ahead schedulers, and plant operators provide system configuration and detailed operational data, along with feedback on model design and performance. CHEERS is integrated with CDWR data systems to obtain historic and initial conditions of the system as the basis from which future operations are then optimized. Model results suggest alternative operational regimes that improve the value of CDWR resources to the grid while enhancing the environment and complying with water delivery obligations for non-power uses.
49 CFR 229.29 - Biennial tests.
Code of Federal Regulations, 2010 CFR
2010-10-01
... 49 Transportation 4 2010-10-01 2010-10-01 false Biennial tests. 229.29 Section 229.29..., DEPARTMENT OF TRANSPORTATION RAILROAD LOCOMOTIVE SAFETY STANDARDS Inspections and Tests § 229.29 Biennial tests. (a) Except for the valves and valve portions on non-MU locomotives that are cleaned, repaired...
UNESCO-UNEVOC in Action: Biennial Report 2012-2013
ERIC Educational Resources Information Center
UNESCO-UNEVOC International Centre for Technical and Vocational Education and Training, 2014
2014-01-01
This biennial report provides a comprehensive overview of UNESCO-UNEVOC's activities in technical and vocational education and training in 2012-2013. It illustrates UNESCO-UNEVOC's contributions to the UNESCO 36 C/5 sectoral priorities and programmatic objectives. Specifically, UNESCO-UNEVOC contributed to the biennial sectoral priority in…
40 CFR 262.41 - Biennial report.
Code of Federal Regulations, 2010 CFR
2010-07-01
... 40 Protection of Environment 25 2010-07-01 2010-07-01 false Biennial report. 262.41 Section 262.41 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) SOLID WASTES (CONTINUED) STANDARDS APPLICABLE TO GENERATORS OF HAZARDOUS WASTE Recordkeeping and Reporting § 262.41 Biennial report. (a) A generator who ships any hazardous waste...
43 CFR 11.12 - Biennial review of regulations.
Code of Federal Regulations, 2011 CFR
2011-10-01
... 43 Public Lands: Interior 1 2011-10-01 2011-10-01 false Biennial review of regulations. 11.12 Section 11.12 Public Lands: Interior Office of the Secretary of the Interior NATURAL RESOURCE DAMAGE ASSESSMENTS Introduction § 11.12 Biennial review of regulations. The regulations and procedures included...
43 CFR 11.12 - Biennial review of regulations.
Code of Federal Regulations, 2010 CFR
2010-10-01
... 43 Public Lands: Interior 1 2010-10-01 2010-10-01 false Biennial review of regulations. 11.12 Section 11.12 Public Lands: Interior Office of the Secretary of the Interior NATURAL RESOURCE DAMAGE ASSESSMENTS Introduction § 11.12 Biennial review of regulations. The regulations and procedures included...
47 CFR 53.209 - Biennial audit.
Code of Federal Regulations, 2010 CFR
2010-10-01
... 47 Telecommunication 3 2010-10-01 2010-10-01 false Biennial audit. 53.209 Section 53.209... PROVISIONS CONCERNING BELL OPERATING COMPANIES Separate Affiliate; Safeguards § 53.209 Biennial audit. (a) A... obtain and pay for a Federal/State joint audit every two years conducted by an independent auditor to...
College Freshman with Disabilities, 1999: A Biennial Statistical Profile. Statistical Year 1998.
ERIC Educational Resources Information Center
Henderson, Cathy
This monograph presents information on college freshmen with disabilities based on data collected by the Cooperative Institutional Research Program, a longitudinal study of the American higher education system that includes 469 institutions and 275,811 students. Section 1 presents highlights of the 1998 freshman survey and includes personal and…
Manpower and Financial Resources Allocated to Academic Science and Engineering Activities, 1965-71.
ERIC Educational Resources Information Center
National Science Foundation, Washington, DC. Div. of Science Resources Studies.
This report summarizes the results of the National Science Foundation's biennial survey of manpower and financial resources for scientific engineering activities at institutions of higher education, 1971. The survey was conducted by mail questionnaires sent to 2,198 universities and colleges that maintained science and engineering programs, and…
Meeting the Challenge, 1988-89. Condition of Education in Connecticut: Elementary and Secondary.
ERIC Educational Resources Information Center
Connecticut State Board of Education, Hartford.
The condition of education in Connecticut, especially pertaining to reform efforts initiated from July 1, 1986, to June 30, 1988, is summarized in this biennial report. The document includes indepth discussions of the state's people and economy, teacher and administrator characteristics, student achievements, programs, and school finance. Text,…
ERIC Educational Resources Information Center
Journal of Chemical Education, 1985
1985-01-01
Provides highlights of lectures, workshops, papers, and symposia presented at a conference which addressed such areas of chemical education as college/high school chemistry teaching; curriculum/curriculum development; safety; two-year programs; computers; toxicology and health hazards; problem-solving; writing skills development; textbooks;…
Biennial Report of the New York State Science Service, 1977-1978.
ERIC Educational Resources Information Center
New York State Education Dept., Albany.
Contained within this report are summaries of activities of the New York State Science Service for the years 1977-1978. Within the introduction, the specific goals for the Science Service are listed. Activities within the following categories are summarized: services and advisory activities, education in honorarium and volunteer programs, grant or…
Literacy and Training: Priorities for Texas. Biennial Report to the Governor and Legislature.
ERIC Educational Resources Information Center
Texas State Council on Vocational Education, Austin.
Among the recommendations of the Texas Council on Vocational Education concerning literacy and training are the following: (1) the governor and legislature should conduct a statewide, multimedia campaign to heighten Texans' awareness of the importance of workplace literacy, dropout prevention, literacy programs, and the human and economic aspects…
Environmental Issues Related to Conventional Hydropower
DOE Office of Scientific and Technical Information (OSTI.GOV)
Deng, Zhiqun; Colotelo, Alison HA; Brown, Richard S.
Hydropower is the largest renewable electrical energy source in the world and has a total global capacity of approximately 1,010 GW from 150 countries. Although hydropower has many environmental advantages, hydropower dams have potential adverse ecological impacts such as fish passage, water quality, and habitat alterations.
Bridging the Information Gap: Remote Sensing and Micro Hydropower Feasibility in Data-Scarce Regions
NASA Astrophysics Data System (ADS)
Muller, Marc Francois
Access to electricity remains an impediment to development in many parts of the world, particularly in rural areas with low population densities and prohibitive grid extension costs. In that context, community-scale run-of-river hydropower---micro-hydropower---is an attractive local power generation option, particularly in mountainous regions, where appropriate slope and runoff conditions occur. Despite their promise, micro hydropower programs have generally failed to have a significant impact on rural electrification in developing nations. In Nepal, despite very favorable conditions and approximately 50 years of experience, the technology supplies only 4% of the 10 million households that do not have access to the central electricity grid. These poor results point towards a major information gap between technical experts, who may lack the incentives or local knowledge needed to design appropriate systems for rural villages, and local users, who have excellent knowledge of the community but lack technical expertise to design and manage infrastructure. Both groups suffer from a limited basis for evidence-based decision making due to sparse environmental data available to support the technical components of infrastructure design. This dissertation draws on recent advances in remote sensing data, stochastic modeling techniques and open source platforms to bridge that information gap. Streamflow is a key environmental driver of hydropower production that is particularly challenging to model due to its stochastic nature and the complexity of the underlying natural processes. The first part of the dissertation addresses the general challenge of Predicting streamflow in Ungauged Basins (PUB). It first develops an algorithm to optimize the use of rain gauge observations to improve the accuracy of remote sensing precipitation measures. It then derives and validates a process-based model to estimate streamflow distribution in seasonally dry climates using the stochastic nature of rainfall, and proposes a novel geostatistical method to regionalize its parameters across the stream network. Although motivated by the needs of micro hydropower design in Nepal, these techniques represent contributions to the broader international challenge of PUB and can be applied worldwide. The economic drivers of rural electrification are then considered by presenting an econometric technique to estimate the cost function and demand curve of micro hydropower in Nepal. The empirical strategy uses topography-based instrumental variables to identify price elasticities. All developed methods are assembled in a computer tool, along with a search algorithm that uses a digital elevation model to optimize the placement of micro hydropower infrastructure. The tool---Micro Hydro [em]Power---is an open source application that can be accessed and operated on a web-browser (http://mfmul.shinyapps.io/mhpower). Its purpose is to assist local communities in the design and evaluation of micro hydropower alternatives in their locality, while using cost and demand information provided by local users to generate accurate feasibility maps at the national level, thus bridging the information gap.
DOE Office of Scientific and Technical Information (OSTI.GOV)
Hou, Hongfei; Deng, Zhiqun; Martinez, Jayson
Currently, approximately 16% of the world’s electricity and over 80% of the world’s renewable electricity is generated from hydropower resources, and there is potential for development of a significant amount of new hydropower capacity. However, in practice, realizing all the potential hydropower resource is limited by various factors, including environmental effects and related mitigation requirements. That is why hydropower regulatory requirements frequently call for targets to be met regarding fish injury and mortality rates. Hydropower Biological Evaluation Toolset (HBET), an integrated suite of software tools, is designed to characterize hydraulic conditions of hydropower structures and provide quantitative estimates of fishmore » injury and mortality rates due to various physical stressors including strike, pressure, and shear. HBET enables users to design new studies, analyze data, perform statistical analyses, and evaluate biological responses. In this paper, we discuss the features of the HBET software and describe a case study that illustrates its functionalities. HBET can be used by turbine manufacturers, hydropower operators, and regulators to design and operate hydropower systems that minimize ecological impacts in a cost-effective manner.« less
Sensitivity of Regional Hydropower Generation to the Projected Changes in Future Watershed Hydrology
NASA Astrophysics Data System (ADS)
Kao, S. C.; Naz, B. S.; Gangrade, S.
2015-12-01
Hydropower is a key contributor to the renewable energy portfolio due to its established development history and the diverse benefits it provides to the electric power systems. With the projected change in the future watershed hydrology, including shift of snowmelt timing, increasing occurrence of extreme precipitation, and change in drought frequencies, there is a need to investigate how the regional hydropower generation may change correspondingly. To evaluate the sensitivity of watershed storage and hydropower generation to future climate change, a lumped Watershed Runoff-Energy Storage (WRES) model is developed to simulate the annual and seasonal hydropower generation at various hydropower areas in the United States. For each hydropower study area, the WRES model use the monthly precipitation and naturalized (unregulated) runoff as inputs to perform a runoff mass balance calculation for the total monthly runoff storage in all reservoirs and retention facilities in the watershed, and simulate the monthly regulated runoff release and hydropower generation through the system. The WRES model is developed and calibrated using the historic (1980-2009) monthly precipitation, runoff, and generation data, and then driven by a large set of dynamically- and statistically-downscaled Coupled Model Intercomparison Project Phase 5 climate projections to simulate the change of watershed storage and hydropower generation under different future climate scenarios. The results among different hydropower regions, storage capacities, emission scenarios, and timescales are compared and discussed in this study.
Dynamic analysis of a pumped-storage hydropower plant with random power load
NASA Astrophysics Data System (ADS)
Zhang, Hao; Chen, Diyi; Xu, Beibei; Patelli, Edoardo; Tolo, Silvia
2018-02-01
This paper analyzes the dynamic response of a pumped-storage hydropower plant in generating mode. Considering the elastic water column effects in the penstock, a linearized reduced order dynamic model of the pumped-storage hydropower plant is used in this paper. As the power load is always random, a set of random generator electric power output is introduced to research the dynamic behaviors of the pumped-storage hydropower plant. Then, the influences of the PI gains on the dynamic characteristics of the pumped-storage hydropower plant with the random power load are analyzed. In addition, the effects of initial power load and PI parameters on the stability of the pumped-storage hydropower plant are studied in depth. All of the above results will provide theoretical guidance for the study and analysis of the pumped-storage hydropower plant.
18 CFR 141.14 - Form No. 80, Licensed Hydropower Development Recreation Report.
Code of Federal Regulations, 2010 CFR
2010-04-01
... 18 Conservation of Power and Water Resources 1 2010-04-01 2010-04-01 false Form No. 80, Licensed Hydropower Development Recreation Report. 141.14 Section 141.14 Conservation of Power and Water Resources... Hydropower Development Recreation Report. The form of the report, Licensed Hydropower Development Recreation...
A Cost Savings Analysis of the Streamlined Military Construction Program Process
1990-04-16
program through Congressional action . Review of these two years allowed the biennial budget to be addressed from the perspective of the first year of...specifications in outline form. c. Preliminar- project design cost estimates.. d. Back-up daca as required by this Appendix. 2. The 35 percent preliminary...delayed Congressional action . A pragmatic estimate would add an additional 12-36 months to the optimistic total. How can it possibly take that long? In
National Hydropower Plant Dataset, Version 1 (Update FY18Q2)
Samu, Nicole; Kao, Shih-Chieh; O'Connor, Patrick; Johnson, Megan; Uria-Martinez, Rocio; McManamay, Ryan
2016-09-30
The National Hydropower Plant Dataset, Version 1, Update FY18Q2, includes geospatial point-level locations and key characteristics of existing hydropower plants in the United States that are currently online. These data are a subset extracted from NHAAP’s Existing Hydropower Assets (EHA) dataset, which is a cornerstone of NHAAP’s EHA effort that has supported multiple U.S. hydropower R&D research initiatives related to market acceleration, environmental impact reduction, technology-to-market activities, and climate change impact assessment.
Code of Federal Regulations, 2013 CFR
2013-10-01
... vessels are engaged in IUU fishing (1) NMFS will identify and list, in a biennial report to Congress... biennial report to Congress, the Secretary of Commerce will notify the President of such identification. Within 60 days after submission of the biennial report to Congress, the Secretary of Commerce, acting...
Federal Register 2010, 2011, 2012, 2013, 2014
2010-07-21
... Bioterrorism Preparedness and Response Act of 2002; Biennial Review and Republication of the Select Agent and... Act) requires the biennial review and republication of the HHS list of select agents and toxins. Accordingly, we are soliciting public comment on the current HHS list of select agents and toxins, including...
1992-01-01
counications between technology producer (Navy RDT&X community) and technology customer (Navy/MarLne Corps operating forces). Program technological...Additional programs as rwured by Fleet customer . 3. (U) 1t 1993 Planes Identify issues and provide link to RDT&3 community. Projects will vary according to...fleet customer requLrements. 4. (U) Program to Cmpletions This is a continuing program. D. (U) WORK pIRFORIpD l: iN-DOSE: NsWC Dahlgren, VA; AC
DOE Office of Scientific and Technical Information (OSTI.GOV)
Miller, Benjamin L.; Arntzen, Evan V.; Goldman, Amy E.
The United States is home to more than 87,000 dams, 2,198 of which are actively used for hydropower production. With the December 2015 consensus adoption of the United Nations Framework Convention on Climate Change’s Paris Agreement, it is imperative for the U.S. to accurately quantify greenhouse gas fluxes from its hydropower reservoirs. Methane ebullition, or methane bubbles originating from river or lake sediments, can account for nearly all of a reservoir’s methane emissions to the atmosphere. However, methane ebullition in hydropower reservoirs has been studied in only three temperate locations, none of which are in the United States. This studymore » measures high ebullitive methane fluxes from two hydropower reservoirs in eastern Washington, synthesizes the known information about methane ebullition from tropical, boreal, and temperate hydropower reservoirs, and investigates the implications for U.S. hydropower management and growth.« less
Federal Register 2010, 2011, 2012, 2013, 2014
2010-02-19
... List for Hydropower Licensing Study Dispute Resolution; Notice Extending Filing Date for Applications for Panel Member List for Hydropower Licensing Study Dispute Resolution February 4, 2010. On October... on a list of resource experts willing to serve as a third panel member in the Commission's hydropower...
Federal Register 2010, 2011, 2012, 2013, 2014
2010-08-19
... DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2790-055] Boott Hydropower... Hydropower, Inc. and Eldred L Field Hydroelectric Facility Trust. e. Name of Project: Lowell Hydroelectric... Affairs Coordinator, Boott Hydropower, Inc., One Tech Drive, Suite 220, Andover, MA 01810. Tel: (978) 681...
Federal Register 2010, 2011, 2012, 2013, 2014
2012-07-20
... Hydropower, LLC, Eagle Creek Land Resources, LLC, Eagle Creek Water Resources, LLC; Notice of Application...: Eagle Creek Hydropower, LLC; Eagle Creek Land Resources, LLC; and Eagle Creek Water Resources, LLC. e... Contact: Robert Gates, Senior Vice President-- Operations, Eagle Creek Hydropower, LLC, Eagle Creek Water...
Goede, S Lucas; Rabeneck, Linda; van Ballegooijen, Marjolein; Zauber, Ann G; Paszat, Lawrence F; Hoch, Jeffrey S; Yong, Jean H E; Kroep, Sonja; Tinmouth, Jill; Lansdorp-Vogelaar, Iris
2017-01-01
The ColonCancerCheck screening program for colorectal cancer (CRC) in Ontario, Canada, is considering switching from biennial guaiac fecal occult blood test (gFOBT) screening between age 50-74 years to the more sensitive, but also less specific fecal immunochemical test (FIT). The aim of this study is to estimate whether the additional benefits of FIT screening compared to gFOBT outweigh the additional costs and harms. We used microsimulation modeling to estimate quality adjusted life years (QALYs) gained and costs of gFOBT and FIT, compared to no screening, in a cohort of screening participants. We compared strategies with various age ranges, screening intervals, and cut-off levels for FIT. Cost-efficient strategies were determined for various levels of available colonoscopy capacity. Compared to no screening, biennial gFOBT screening between age 50-74 years provided 20 QALYs at a cost of CAN$200,900 per 1,000 participants, and required 17 colonoscopies per 1,000 participants per year. FIT screening was more effective and less costly. For the same level of colonoscopy requirement, biennial FIT (with a high cut-off level of 200 ng Hb/ml) between age 50-74 years provided 11 extra QALYs gained while saving CAN$333,300 per 1000 participants, compared to gFOBT. Without restrictions in colonoscopy capacity, FIT (with a low cut-off level of 50 ng Hb/ml) every year between age 45-80 years was the most cost-effective strategy providing 27 extra QALYs gained per 1000 participants, while saving CAN$448,300. Compared to gFOBT screening, switching to FIT at a high cut-off level could increase the health benefits of a CRC screening program without considerably increasing colonoscopy demand.
Transition From Film to Digital Mammography
van Ravesteyn, Nicolien T.; van Lier, Lisanne; Schechter, Clyde B.; Ekwueme, Donatus U.; Royalty, Janet; Miller, Jacqueline W.; Near, Aimee M.; Cronin, Kathleen A.; Heijnsdijk, Eveline A.M.; Mandelblatt, Jeanne S.; de Koning, Harry J.
2015-01-01
Introduction The National Breast and Cervical Cancer Early Detection Program (NBCCEDP) provides mammograms and diagnostic services for low-income, uninsured women aged 40–64 years. Mammography facilities within the NBCCEDP gradually shifted from plain-film to digital mammography. The purpose of this study is to assess the impact of replacing film with digital mammography on health effects (deaths averted, life-years gained [LYG]), costs (for screening and diagnostics), and number of women reached. Methods NBCCEDP 2010 data and data representative of the program’s target population were used in two established microsimulation models. Models simulated observed screening behavior including different screening intervals (annual, biennial, irregular) and starting ages (40, 50 years) for white, black, and Hispanic women. Model runs were performed in 2012. Results The models predicted 8.0–8.3 LYG per 1,000 film screens for black women, 5.9–7.5 for white women, and 4.0–4.5 for Hispanic women. For all race/ethnicity groups, digital mammography had more LYG than film mammography (2%–4%), but had higher costs (34%–35%). Assuming a fixed budget, 25%–26% fewer women could be served, resulting in 22%–24% fewer LYG if all mammograms were converted to digital. The loss in LYG could be reversed to an 8%–13% increase by only including biennial screening. Conclusions Digital could result in slightly more LYG than film mammography. However, with a fixed budget, fewer women may be served with fewer LYG. Changes in the program, such as only including biennial screening, will increase LYG/screen and could offset the potential decrease in LYG when shifting to digital mammography. PMID:25891052
NASA Astrophysics Data System (ADS)
Wen, X.; Lei, X.; Fang, G.; Huang, X.
2017-12-01
Extensive cascading hydropower exploitation in southwestern China has been the subject of debate and conflict in recent years. Introducing limited ecological curves, a novel approach for derivation of hydropower-ecological joint operation chart of cascaded hydropower system was proposed, aiming to optimize the general hydropower and ecological benefits, and to alleviate the ecological deterioration in specific flood/dry conditions. The physical habitat simulation model is proposed initially to simulate the relationship between streamflow and physical habitat of target fish species and to determine the optimal ecological flow range of representative reach. The ecological—hydropower joint optimization model is established to produce the multi-objective operation chart of cascaded hydropower system. Finally, the limited ecological guiding curves were generated and added into the operation chart. The JS-MDS cascaded hydropower system on the Yuan River in southwestern China is employed as the research area. As the result, the proposed guiding curves could increase the hydropower production amount by 1.72% and 5.99% and optimize ecological conservation degree by 0.27% and 1.13% for JS and MDS Reservoir, respectively. Meanwhile, the ecological deterioration rate also sees a decrease from 6.11% to 1.11% for JS Reservoir and 26.67% to 3.89% for MDS Reservoir.
Bakken, Tor Haakon; Aase, Anne Guri; Hagen, Dagmar; Sundt, Håkon; Barton, David N; Lujala, Päivi
2014-07-01
Climate change and the needed reductions in the use of fossil fuels call for the development of renewable energy sources. However, renewable energy production, such as hydropower (both small- and large-scale) and wind power have adverse impacts on the local environment by causing reductions in biodiversity and loss of habitats and species. This paper compares the environmental impacts of many small-scale hydropower plants with a few large-scale hydropower projects and one wind power farm, based on the same set of environmental parameters; land occupation, reduction in wilderness areas (INON), visibility and impacts on red-listed species. Our basis for comparison was similar energy volumes produced, without considering the quality of the energy services provided. The results show that small-scale hydropower performs less favourably in all parameters except land occupation. The land occupation of large hydropower and wind power is in the range of 45-50 m(2)/MWh, which is more than two times larger than the small-scale hydropower, where the large land occupation for large hydropower is explained by the extent of the reservoirs. On all the three other parameters small-scale hydropower performs more than two times worse than both large hydropower and wind power. Wind power compares similarly to large-scale hydropower regarding land occupation, much better on the reduction in INON areas, and in the same range regarding red-listed species. Our results demonstrate that the selected four parameters provide a basis for further development of a fair and consistent comparison of impacts between the analysed renewable technologies. Copyright © 2014 The Authors. Published by Elsevier Ltd.. All rights reserved.
ERIC Educational Resources Information Center
Kann, L.; Grunbaum, J.; McKenna, M. L.; Wechsler, H.; Galuska, D. A.
2005-01-01
School Health Profiles is conducted biennially to assess characteristics of school health programs. State and local departments of education and health select either all public secondary schools within their jurisdictions or a systematic, equal-probability sample of public secondary schools to participate in School Health Profiles. At each school,…
ERIC Educational Resources Information Center
Association for Education of the Visually Handicapped, Philadelphia, PA.
Essays on the visually handicapped are concerned with congenital rubella, an evaluation of multiply handicapped children, the use and abuse of the IQ, visual perception dysfunction, spatial perceptions in the partially sighted, programs in daily living skills, sex education needs, and physical activity as an enhancement of functioning. Other…
Biennial Conference on Chemical Education, Abstracts (11th, Atlanta, Georgia, August 5-9, 1990).
ERIC Educational Resources Information Center
Mellon, E. K.; Pulliam, E. J.
This publication includes more than 470 abstracts of papers scheduled to be presented at a chemical education conference. Topics of the papers include: (1) human impact on the environment; (2) technology; (3) forensic science; (4) paper chemistry; (5) computer interfacing, software, videodisc and graphics; (6) faculty enhancement programs; (7)…
ERIC Educational Resources Information Center
Office of English Language Acquisition, US Department of Education, 2015
2015-01-01
"Title III" of the "Elementary and Secondary Education Act" ("ESEA") provides formula grants to states to help support the educational needs of students identified as English learners (ELs). In school year (SY) 2011-12, ELs served by "Title III"-funded activities comprised approximately 9 percent of the…
Castro, Marcia C; Krieger, Gary R; Balge, Marci Z; Tanner, Marcel; Utzinger, Jürg; Whittaker, Maxine; Singer, Burton H
2016-12-20
Large-scale corporate projects, particularly those in extractive industries or hydropower development, have a history from early in the twentieth century of creating negative environmental, social, and health impacts on communities proximal to their operations. In many instances, especially for hydropower projects, the forced resettlement of entire communities was a feature in which local cultures and core human rights were severely impacted. These projects triggered an activist opposition that progressively expanded and became influential at both the host community level and with multilateral financial institutions. In parallel to, and spurred by, this activism, a shift occurred in 1969 with the passage of the National Environmental Policy Act in the United States, which required Environmental Impact Assessment (EIA) for certain types of industrial and infrastructure projects. Over the last four decades, there has been a global movement to develop a formal legal/regulatory EIA process for large industrial and infrastructure projects. In addition, social, health, and human rights impact assessments, with associated mitigation plans, were sequentially initiated and have increasingly influenced project design and relations among companies, host governments, and locally impacted communities. Often, beneficial community-level social, economic, and health programs have voluntarily been put in place by companies. These flagship programs can serve as benchmarks for community-corporate-government partnerships in the future. Here, we present examples of such positive phenomena and also focus attention on a myriad of challenges that still lie ahead.
Castro, Marcia C.; Krieger, Gary R.; Balge, Marci Z.; Tanner, Marcel; Utzinger, Jürg; Whittaker, Maxine; Singer, Burton H.
2016-01-01
Large-scale corporate projects, particularly those in extractive industries or hydropower development, have a history from early in the twentieth century of creating negative environmental, social, and health impacts on communities proximal to their operations. In many instances, especially for hydropower projects, the forced resettlement of entire communities was a feature in which local cultures and core human rights were severely impacted. These projects triggered an activist opposition that progressively expanded and became influential at both the host community level and with multilateral financial institutions. In parallel to, and spurred by, this activism, a shift occurred in 1969 with the passage of the National Environmental Policy Act in the United States, which required Environmental Impact Assessment (EIA) for certain types of industrial and infrastructure projects. Over the last four decades, there has been a global movement to develop a formal legal/regulatory EIA process for large industrial and infrastructure projects. In addition, social, health, and human rights impact assessments, with associated mitigation plans, were sequentially initiated and have increasingly influenced project design and relations among companies, host governments, and locally impacted communities. Often, beneficial community-level social, economic, and health programs have voluntarily been put in place by companies. These flagship programs can serve as benchmarks for community–corporate–government partnerships in the future. Here, we present examples of such positive phenomena and also focus attention on a myriad of challenges that still lie ahead. PMID:27791077
Code of Federal Regulations, 2011 CFR
2011-10-01
... engaged in PLMR bycatch. (1) NMFS will identify and list, in the biennial report to Congress, nations... publication of the biennial report to Congress, in fishing activities or practices either in waters beyond any... of the biennial report to Congress, in bycatch of PLMRs is a party to or maintains cooperating status...
Federal Register 2010, 2011, 2012, 2013, 2014
2010-04-09
... Illinois Hydropower, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and... No.: 12626-002. c. Date filed: March 31, 2009. d. Applicant: Northern Illinois Hydropower, LLC. e... Power Act, 16 U.S.C. 791(a)-825(r). h. Applicant Contact: Damon Zdunich, Northern Illinois Hydropower...
Federal Register 2010, 2011, 2012, 2013, 2014
2010-05-06
... Illinois Hydropower, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and... No.: 12717-002. c. Date filed: May 27, 2009. d. Applicant: Northern Illinois Hydropower, LLC. e. Name... Hydropower, LLC, 801 Oakland Avenue, Joliet, IL 60435, (312) 320-1610. i. FERC Contact: Dr. Nicholas Palso...
Federal Register 2010, 2011, 2012, 2013, 2014
2010-10-05
... Hydropower, Inc.; Notice of Intent To File License Application, Filing of Pre-Application Document, and....: 13563-001. c. Dated Filed: July 28, 2010. d. Submitted By: Juneau Hydropower, Inc. e. Name of Project... Commission's regulations. h. Potential Applicant Contact: Duff W. Mitchell, Juneau Hydropower, Inc., P.O. Box...
Federal Register 2010, 2011, 2012, 2013, 2014
2010-03-05
... Hydropower, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests... No.: P-12783-003. c. Date filed: July 22, 2009. d. Applicant: Inglis Hydropower, LLC. e. Name of Project: Inglis Hydropower Project. f. Location: The proposed project would be located at the existing...
Federal Register 2010, 2011, 2012, 2013, 2014
2010-08-02
... Hydropower, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional... License. b. Project No.: P-13637-001. c. Date filed: July 12, 2010. d. Applicant: Great River Hydropower.... 21, and would consist of the following facilities: (1) A new hydropower structure, located about 100...
Federal Register 2010, 2011, 2012, 2013, 2014
2011-02-11
... Hydropower, LLC; Notice of Scoping Meetings and Environmental Site Review and Soliciting Scoping Comments.... c. Date filed: July 12, 2010. d. Applicant: Great River Hydropower, LLC. e. Name of Project: Upper... 796-foot-long by 46-foot-wide by 25-foot-high concrete hydropower structure consisting of 30 turbine...
Federal Register 2010, 2011, 2012, 2013, 2014
2011-12-29
... Development in the United States; Notice of Small/Low-Impact Hydropower Webinar The Federal Energy Regulatory... participants to learn what types of hydropower projects qualify as a 5-megawatt (MW) exemption, how to file a... exemption. Additionally, participants have the opportunity to ask questions and learn how to get more...
2003-01-01
Sinister Software, who wrote the SALES CALL program, and to Dr. Tanja Blackstone , Program Officer at ONR who was of great support during the grant...real risk of being prey to the ecological fallacy. Indeed, those that used non-American subjects tended to accept the Hofstede categorization of the...Journalism and Mass Communication, Southeast Colloquium. New Orleans. Newspaper Coverage 180 Peach, L. J. (1996). Gender ideology in the ethics of
Conflicting hydropower development and aquatic ecosystem conservation in Bhutan
NASA Astrophysics Data System (ADS)
Wi, S.; Yang, Y. C. E.
2017-12-01
Hydropower is one of the clean energy sources that many Himalayan countries are eager to develop to solve their domestic energy deficit issue such as India, Nepal and Pakistan. Like other Himalayan countries, Bhutan also has a great potential for hydropower development. However, Bhutan is one of few countries that has a domestic energy surplus and export its hydropower generation to neighboring countries (mainly to India). Exporting hydropower is one of the major economic sources in Bhutan. However, constructions of dams and reservoirs for hydropower development inevitably involve habitat fragmentation, causing a conflict of interest with the pursuit of value in aquatic ecosystem conservation. The objectives of this study is to 1) develop a distributed hydrologic model with snow and glacier module to simulate the hydrologic regimes of seven major watersheds in Bhutan; 2) apply the hydrologic model to compute hydropower generation for all existing and potential dams; 3) evaluate cascade impacts of each individual dam on downstream regions by employing three hydro-ecological indicators: the River Connectivity Index (RCI), Dendritic Connectivity Index (DCI), total affected river stretch (ARS), and 4) analyze the tradeoffs between hydropower generation and river connectivity at the national scale by means of a multiple objective genetic algorithm. Modeling results of three Pareto Fronts between ecological indicators and hydropower generation accompany with future energy export targets from the government can inform dam selections that maximizing hydropower generation while minimizing the impact on the aquatic ecosystem (Figure 1a). The impacts of climate change on these Pareto front are also explored to identify robust dam selection under changing temperature and precipitation (Figure 1b).
DOE Office of Scientific and Technical Information (OSTI.GOV)
Sale, Michael J.; Bishop, Norman A.; Reiser, Sonya L.
2014-09-01
In Section 7 of the Hydropower Regulatory Efficiency Act (HREA) of 2013 (P.L. 113-23), Congress directed the U.S. Department of Energy (DOE) to prepare an analysis of conduit hydropower opportunities available in the United States and to present case studies that describe the potential energy generation from these types of hydropower projects. Those analyses have been included in a new DOE report to Congress, and this ORNL/TM provides additional technical details supporting that report. Conduit hydropower offers important new ways to enhance renewable energy portfolios in the United States, as well as to increase the energy efficiency of water deliverymore » systems. Conduit hydropower projects are constructed on existing water-conveyance structures, such as irrigation canals or pressurized pipelines that deliver water to municipalities, industry, or agricultural water users. Although water conveyance infrastructures are usually designed for non-power purposes, new renewable energy can often be harvested from them without affecting their original purpose and without the need to construct new dams or diversions. Conduit hydropower differs from more conventional hydropower development in that it is generally not located on natural rivers or waterways and therefore does not involve the types of environmental impacts that are associated with hydropower. The addition of hydropower to existing water conduits can provide valuable new revenue sources from clean, renewable energy. The new energy can be used within the existing water distribution systems to offset other energy demands, or it can be sold into regional transmission systems.« less
Valuing trade-offs of river ecosystem services in large hydropower development in Tibet, China
NASA Astrophysics Data System (ADS)
Yu, B.; Xu, L.
2015-12-01
Hydropower development can be considered as a kind of trade-offs of ecosystem services generated by human activity for their economic and energy demand, because it can increase some river ecosystem services but decrease others. In this context, an ecosystem service trade-off framework in hydropower development was proposed in this paper. It aims to identify the ecological cost of river ecosystem and serve for the ecological compensation during hydropower development, for the hydropower services cannot completely replace the regulating services of river ecosystem. The valuing trade-offs framework was integrated by the influenced ecosystem services identification and ecosystem services valuation, through ecological monitoring and ecological economic methods, respectively. With a case study of Pondo hydropower project in Tibet, China, the valuing trade-offs of river ecosystem services in large hydropower development was illustrated. The typical ecological factors including water, sediment and soil were analyzed in this study to identify the altered river ecosystem services by Pondo hydropower project. Through the field monitoring and valuation, the results showed that the Lhasa River ecosystem services value could be changed annually by Pondo hydropower project with the increment of 5.7E+8CNY, and decrement of 5.1E+7CNY. The ecological compensation for river ecosystem should be focus on water and soil conservation, reservoir dredging and tributaries habitat protection.
DOE Office of Scientific and Technical Information (OSTI.GOV)
Pasha, M. Fayzul K.; Yang, Majntxov; Yeasmin, Dilruba
Benefited from the rapid development of multiple geospatial data sets on topography, hydrology, and existing energy-water infrastructures, the reconnaissance level hydropower resource assessment can now be conducted using geospatial models in all regions of the US. Furthermore, the updated techniques can be used to estimate the total undeveloped hydropower potential across all regions, and may eventually help identify further hydropower opportunities that were previously overlooked. To enhance the characterization of higher energy density stream-reaches, this paper explored the sensitivity of geospatial resolution on the identification of hydropower stream-reaches using the geospatial merit matrix based hydropower resource assessment (GMM-HRA) model. GMM-HRAmore » model simulation was conducted with eight different spatial resolutions on six U.S. Geological Survey (USGS) 8-digit hydrologic units (HUC8) located at three different terrains; Flat, Mild, and Steep. The results showed that more hydropower potential from higher energy density stream-reaches can be identified with increasing spatial resolution. Both Flat and Mild terrains exhibited lower impacts compared to the Steep terrain. Consequently, greater attention should be applied when selecting the discretization resolution for hydropower resource assessments in the future study.« less
Pasha, M. Fayzul K.; Yang, Majntxov; Yeasmin, Dilruba; ...
2016-01-07
Benefited from the rapid development of multiple geospatial data sets on topography, hydrology, and existing energy-water infrastructures, the reconnaissance level hydropower resource assessment can now be conducted using geospatial models in all regions of the US. Furthermore, the updated techniques can be used to estimate the total undeveloped hydropower potential across all regions, and may eventually help identify further hydropower opportunities that were previously overlooked. To enhance the characterization of higher energy density stream-reaches, this paper explored the sensitivity of geospatial resolution on the identification of hydropower stream-reaches using the geospatial merit matrix based hydropower resource assessment (GMM-HRA) model. GMM-HRAmore » model simulation was conducted with eight different spatial resolutions on six U.S. Geological Survey (USGS) 8-digit hydrologic units (HUC8) located at three different terrains; Flat, Mild, and Steep. The results showed that more hydropower potential from higher energy density stream-reaches can be identified with increasing spatial resolution. Both Flat and Mild terrains exhibited lower impacts compared to the Steep terrain. Consequently, greater attention should be applied when selecting the discretization resolution for hydropower resource assessments in the future study.« less
NASA Astrophysics Data System (ADS)
Conway, Declan; Dalin, Carole; Landman, Willem A.; Osborn, Timothy J.
2017-12-01
Hydropower comprises a significant and rapidly expanding proportion of electricity production in eastern and southern Africa. In both regions, hydropower is exposed to high levels of climate variability and regional climate linkages are strong, yet an understanding of spatial interdependences is lacking. Here we consider river basin configuration and define regions of coherent rainfall variability using cluster analysis to illustrate exposure to the risk of hydropower supply disruption of current (2015) and planned (2030) hydropower sites. Assuming completion of the dams planned, hydropower will become increasingly concentrated in the Nile (from 62% to 82% of total regional capacity) and Zambezi (from 73% to 85%) basins. By 2030, 70% and 59% of total hydropower capacity will be located in one cluster of rainfall variability in eastern and southern Africa, respectively, increasing the risk of concurrent climate-related electricity supply disruption in each region. Linking of nascent regional electricity sharing mechanisms could mitigate intraregional risk, although these mechanisms face considerable political and infrastructural challenges.
Cui, Guannan; Wang, Xuan; Xu, Linyu; Zhang, Jin; Yu, Bing
2014-01-01
Ecological suitability evaluation for hydropower development is effective in locating the most suitable area for construction and emphasizes a clear direction for water resources governance. In this paper, water footprints and transportation connectivity were introduced to improve the existing ecological suitability evaluation application for hydropower development by revising the defects of the traditional indicator system. The following conclusions were reached. (1) Tibet was in a state of water use surplus; the prospect of further hydropower development is positive. (2) Chamdo, Lhasa and Nyingchi excelled in water use efficiency, and Ali was placed last. Nakchu was slightly superior to Ali, but it lagged behind the southern regions. Lhasa, Chamdo, Nyingchi, Xigaze and Shannan were suitable for hydropower development, which could further meet local needs and benefit other regions of China. (3) The evaluation results were in accordance with the actual eco-environmental conditions of the built hydropower projects, indicating that current hydropower development planning was basically reasonable.
Game theory competition analysis of reservoir water supply and hydropower generation
NASA Astrophysics Data System (ADS)
Lee, T.
2013-12-01
The total installed capacity of the power generation systems in Taiwan is about 41,000 MW. Hydropower is one of the most important renewable energy sources, with hydropower generation capacity of about 4,540 MW. The aim of this research is to analyze competition between water supply and hydropower generation in water-energy systems. The major relationships between water and energy systems include hydropower generation by water, energy consumption for water system operation, and water consumption for energy system. In this research, a game-theoretic Cournot model is formulated to simulate oligopolistic competition between water supply, hydropower generation, and co-fired power generation in water-energy systems. A Nash equilibrium of the competitive market is derived and solved by GAMS with PATH solver. In addition, a case study analyzing the competition among water supply and hydropower generation of De-ji and Ku-Kuan reservoirs, Taipower, Star Energy, and Star-Yuan power companies in central Taiwan is conducted.
Hydropower Resource Assessment of Brazilian Streams
DOE Office of Scientific and Technical Information (OSTI.GOV)
Douglas G. Hall
The Idaho National Laboratory (INL) in collaboration with the U.S. Geological Survey (USGS) with the assistance of the Empresa de Pesquisa Energetica (EPE) and the Agencia Nacional de Energia Electrica (ANEEL) has performed a comprehensive assessment of the hydropower potential of all Brazilian natural streams. The methodology by which the assessment was performed is described. The results of the assessment are presented including an estimate of the hydropower potential for all of Brazil, and the spatial distribution of hydropower potential thus providing results on a state by state basis. The assessment results have been incorporated into a geographic information systemmore » (GIS) application for the Internet called the Virtual Hydropower Prospector do Brasil. VHP do Brasil displays potential hydropower sites on a map of Brazil in the context of topography and hydrography, existing power and transportation infrastructure, populated places and political boundaries, and land use. The features of the application, which includes tools for finding and selecting potential hydropower sites and other features and displaying their attributes, is fully described.« less
JEDI Conventional Hydropower Model | Jobs and Economic Development Impact
Economic Development Impacts (JEDI) Conventional Hydropower Model allows users to estimate economic development impacts from conventional hydropower projects and includes default information that can be
Federal Register 2010, 2011, 2012, 2013, 2014
2010-08-20
... Hydropower, L.P.; Notice of Intent To File License Application, Filing of Pre-Application Document, and.... Project No.: 7320-040. c. Dated Filed: June 29, 2010. d. Submitted By: Erie Boulevard Hydropower, L.P. e...: John Mudre at (202) 502-8902; or e-mail at [email protected] . j. Erie Boulevard Hydropower, L.P...
DOE Office of Scientific and Technical Information (OSTI.GOV)
Uria-Martinez, Rocio; O'Connor, Patrick W.; Johnson, Megan M.
2015-04-30
The U.S. hydropower fleet has been providing clean, reliable power for more than a hundred years. However, no systematic documentation exists of the U.S. fleet and the trends influencing it in recent years. This first-ever Hydropower Market Report seeks to fill this gap and provide industry and policy makers with a quantitative baseline on the distribution, capabilities, and status of hydropower in the United States.
Optimization algorithms for large-scale multireservoir hydropower systems
DOE Office of Scientific and Technical Information (OSTI.GOV)
Hiew, K.L.
Five optimization algorithms were vigorously evaluated based on applications on a hypothetical five-reservoir hydropower system. These algorithms are incremental dynamic programming (IDP), successive linear programing (SLP), feasible direction method (FDM), optimal control theory (OCT) and objective-space dynamic programming (OSDP). The performance of these algorithms were comparatively evaluated using unbiased, objective criteria which include accuracy of results, rate of convergence, smoothness of resulting storage and release trajectories, computer time and memory requirements, robustness and other pertinent secondary considerations. Results have shown that all the algorithms, with the exception of OSDP converge to optimum objective values within 1.0% difference from one another.more » The highest objective value is obtained by IDP, followed closely by OCT. Computer time required by these algorithms, however, differ by more than two orders of magnitude, ranging from 10 seconds in the case of OCT to a maximum of about 2000 seconds for IDP. With a well-designed penalty scheme to deal with state-space constraints, OCT proves to be the most-efficient algorithm based on its overall performance. SLP, FDM, and OCT were applied to the case study of Mahaweli project, a ten-powerplant system in Sri Lanka.« less
ERIC Educational Resources Information Center
Schuster, Joseph H.
This report summarizes the results of the National Science Foundation's biennial Survey of Science Activities of Institution of Higher Education which collected information on January, 1969, employment and academic year 1967-68 financing in the sciences and engineering in 2,175 universities and colleges with such programs. The report gives special…
ERIC Educational Resources Information Center
Green, Sharon; Weber, James
2013-01-01
The paper examines if there has been an increase in the attention paid to social and environmental issues (SEI) in accounting curricula. Using schools participating in the Aspen Institute's Beyond Grey Pinstripes (BGP) program, we measure the increase in the number of accounting courses incorporating SEI across the biennial application years of…
Monitoring Birds in a Regional Landscape: Lessons from the Nicolet National Forest Bird Survey
Robert W. Howe; Amy T. Wolf; Tony Rinaldi
1995-01-01
The Nicolet National Forest Bird Survey represents one of the first systematic bird monitoring programs in a USDA National Forest. Volunteers visit approximately 500 permanently marked points biennially (250 each year) during a single weekend of mid-June. Results from the first 6 years provide a general inventory of the Forest's avifauna, documentation of...
ERIC Educational Resources Information Center
Toh, Swee-Hin
2010-01-01
From July 6th to 10th, 2010, International Peace Research Association (IPRA) held its biennial conference at the University of Sydney in Australia. Hosted by the University's Centre for Peace & Conflict Studies and coordinated by Jake Lynch and a team of dedicated staff and volunteers, the conference featured seven plenary panels and many…
Hydropower | Climate Neutral Research Campuses | NREL
how hydropower may fit into your climate action plans. Campus Options Considerations Sample Project action plan. A history of the Cornell hydropower plant is available on the university's website. Examples
Is There Really an Intermittent Biennial Oscillation in the Great Plains Low-Level Jet Over Texas?
NASA Technical Reports Server (NTRS)
Helfand, H. Mark
2002-01-01
In the 15-year GEOS-1 reanalysis data set, a maximum of interannual variance of low- level meridional flow for the warm season (May through August) occurs over southeast Texas. This variance maximum seems to be dominated by a marked biennial oscillation that occurs only during the first 6 (or possibly 8) years of the reanalysis period (1980-85 or possibly 1980-1987) and then completely disappears by the 9th year. This biennial oscillation seems to be associated with interannual fluctuations in ground wetness, surface temperature and surface pressure gradients over Texas. The periods of drier soil lead to warmer surface temperatures, lower surface pressures, stronger pressure gradients between Texas and the Gulf of Mexico and stronger southerly winds. This intermittent biennial oscillation is also evident in corresponding fields for the the NCEP/NCAR reanalysis data set for the years 1978-1985 (and possibly from 1978- 1987) and 1995-2000, but not during other periods. There are also obvious biennial oscillations evident during these periods in U.S. Climate Division records for the Palmer Drought Severity Index (PDSI) for Texas. Month-by-month correlations of this index with certain el Nino related indices are as high as .45 for the first period and as high as .55 or .6 for the second period for some regions in Texas. The seasonal cycle of the biennial signal in the PDSI and precipitation for the first period suggest that the drought in Texas and Mexico is ended (caused) by a reversal in the sign of anomalies in precipitation rate for the fall/winter season. Analysis of tropical Pacific SST patterns shows a .5 to .75 K biennial oscillation of SSTs along the precipitation-free track to the southwest of the Mexican coast during the fall and winter months of the 1978 to 1985 period that might explain the reversal in precipitation anomalies and hence the entire intermittent biennial oscillation in ground hydrology and low-level flow.
Complementing hydropower with PV and wind: optimal energy mix in a fully renewable Switzerland
NASA Astrophysics Data System (ADS)
Dujardin, Jérôme; Kahl, Annelen; Kruyt, Bert; Lehning, Michael
2017-04-01
Like several other countries, Switzerland plans to phase out its nuclear power production and will replace most or all of it by renewables. Switzerland has the chance to benefit from a large hydropower potential and has already exploited almost all of it. Currently about 60% of the Swiss electricity consumption is covered by hydropower, which will eventually leave a gap of about 40% to the other renewables mainly composed of photovoltaics (PV) and wind. With its high flexibility, storage hydropower will play a major role in the future energy mix, providing valuable power and energy balance. Our work focuses on the interplay between PV, wind and storage hydropower, to analyze the dynamics of this complex system and to identify the best PV-wind mixing ratio. Given the current electricity consumption and the currently installed pumping capacity of the storage hydropower plants, it appears that the Swiss hydropower system can completely alleviate the intermittency of PV and wind. However, some seasonal mismatch between production and demand will remain, but we show that oversizing the production from PV and wind or enlarging the reservoir capacity can be a solution to keep it to an acceptable level or even eliminate it. We found that PV, wind and hydropower performs the best together when the share of PV in the solar - wind mix is between 20 and 60%. These findings are quantitatively specific for Switzerland but qualitatively transferable to similar mountainous environments with abundant hydropower resources.
China’s rising hydropower demand challenges water sector
Liu, Junguo; Zhao, Dandan; Gerbens-Leenes, P. W.; Guan, Dabo
2015-01-01
Demand for hydropower is increasing, yet the water footprints (WFs) of reservoirs and hydropower, and their contributions to water scarcity, are poorly understood. Here, we calculate reservoir WFs (freshwater that evaporates from reservoirs) and hydropower WFs (the WF of hydroelectricity) in China based on data from 875 representative reservoirs (209 with power plants). In 2010, the reservoir WF totaled 27.9 × 109 m3 (Gm3), or 22% of China’s total water consumption. Ignoring the reservoir WF seriously underestimates human water appropriation. The reservoir WF associated with industrial, domestic and agricultural WFs caused water scarcity in 6 of the 10 major Chinese river basins from 2 to 12 months annually. The hydropower WF was 6.6 Gm3 yr−1 or 3.6 m3 of water to produce a GJ (109 J) of electricity. Hydropower is a water intensive energy carrier. As a response to global climate change, the Chinese government has promoted a further increase in hydropower energy by 70% by 2020 compared to 2012. This energy policy imposes pressure on available freshwater resources and increases water scarcity. The water-energy nexus requires strategic and coordinated implementations of hydropower development among geographical regions, as well as trade-off analysis between rising energy demand and water use sustainability. PMID:26158871
EPRI-DOE Conference on Environmentally-Enhanced Hydropower Turbines: Technical Papers
DOE Office of Scientific and Technical Information (OSTI.GOV)
Hogan, T.
2011-12-01
The EPRI-DOE Conference on Environmentally-Enhanced Hydropower Turbines was a component of a larger project. The goal of the overall project was to conduct the final developmental engineering required to advance the commercialization of the Alden turbine. As part of this effort, the conference provided a venue to disseminate information on the status of the Alden turbine technology as well as the status of other advanced turbines and research on environmentally-friendly hydropower turbines. The conference was also a product of a federal Memorandum of Understanding among DOE, USBR, and USACE to share technical information on hydropower. The conference was held inmore » Washington, DC on May 19 and 20, 2011 and welcomed over 100 attendees. The Conference Organizing Committee included the federal agencies with a vested interest in hydropower in the U.S. The Committee collaboratively assembled this conference, including topics from each facet of the environmentally-friendly conventional hydropower research community. The conference was successful in illustrating the readiness of environmentally-enhanced hydropower technologies. Furthermore, the topics presented illustrated the need for additional deployment and field testing of these technologies in an effort to promote the growth of environmentally sustainable hydropower in the U.S. and around the world.« less
China's rising hydropower demand challenges water sector.
Liu, Junguo; Zhao, Dandan; Gerbens-Leenes, P W; Guan, Dabo
2015-07-09
Demand for hydropower is increasing, yet the water footprints (WFs) of reservoirs and hydropower, and their contributions to water scarcity, are poorly understood. Here, we calculate reservoir WFs (freshwater that evaporates from reservoirs) and hydropower WFs (the WF of hydroelectricity) in China based on data from 875 representative reservoirs (209 with power plants). In 2010, the reservoir WF totaled 27.9 × 10(9) m(3) (Gm(3)), or 22% of China's total water consumption. Ignoring the reservoir WF seriously underestimates human water appropriation. The reservoir WF associated with industrial, domestic and agricultural WFs caused water scarcity in 6 of the 10 major Chinese river basins from 2 to 12 months annually. The hydropower WF was 6.6 Gm(3) yr(-1) or 3.6 m(3) of water to produce a GJ (10(9) J) of electricity. Hydropower is a water intensive energy carrier. As a response to global climate change, the Chinese government has promoted a further increase in hydropower energy by 70% by 2020 compared to 2012. This energy policy imposes pressure on available freshwater resources and increases water scarcity. The water-energy nexus requires strategic and coordinated implementations of hydropower development among geographical regions, as well as trade-off analysis between rising energy demand and water use sustainability.
DOE Office of Scientific and Technical Information (OSTI.GOV)
Kao, Shih -Chieh; Sale, Michael J.; Ashfaq, Moetasim
Federal hydropower plants account for approximately half of installed US conventional hydropower capacity, and are an important part of the national renewable energy portfolio. Utilizing the strong linear relationship between the US Geological Survey WaterWatch runoff and annual hydropower generation, a runoff-based assessment approach is introduced in this study to project changes in annual and regional hydropower generation in multiple power marketing areas. Future climate scenarios are developed with a series of global and regional climate models, and the model output is bias-corrected to be consistent with observed data for the recent past. Using this approach, the median decrease inmore » annual generation at federal projects is projected to be less than –2 TWh, with an estimated ensemble uncertainty of ±9 TWh. Although these estimates are similar to the recently observed variability in annual hydropower generation, and may therefore appear to be manageable, significantly seasonal runoff changes are projected and it may pose significant challenges in water systems with higher limits on reservoir storage and operational flexibility. Lastly, future assessments will be improved by incorporating next-generation climate models, by closer examination of extreme events and longer-term change, and by addressing the interactions among hydropower and other water uses.« less
Kao, Shih -Chieh; Sale, Michael J.; Ashfaq, Moetasim; ...
2014-12-18
Federal hydropower plants account for approximately half of installed US conventional hydropower capacity, and are an important part of the national renewable energy portfolio. Utilizing the strong linear relationship between the US Geological Survey WaterWatch runoff and annual hydropower generation, a runoff-based assessment approach is introduced in this study to project changes in annual and regional hydropower generation in multiple power marketing areas. Future climate scenarios are developed with a series of global and regional climate models, and the model output is bias-corrected to be consistent with observed data for the recent past. Using this approach, the median decrease inmore » annual generation at federal projects is projected to be less than –2 TWh, with an estimated ensemble uncertainty of ±9 TWh. Although these estimates are similar to the recently observed variability in annual hydropower generation, and may therefore appear to be manageable, significantly seasonal runoff changes are projected and it may pose significant challenges in water systems with higher limits on reservoir storage and operational flexibility. Lastly, future assessments will be improved by incorporating next-generation climate models, by closer examination of extreme events and longer-term change, and by addressing the interactions among hydropower and other water uses.« less
Present and future hydropower scheduling in Statkraft
NASA Astrophysics Data System (ADS)
Bruland, O.
2012-12-01
Statkraft produces close to 40 TWH in an average year and is one of the largest hydropower producers in Europe. For hydropower producers the scheduling of electricity generation is the key to success and this depend on optimal use of the water resources. The hydrologist and his forecasts both on short and on long terms are crucial to this success. The hydrological forecasts in Statkraft and most hydropower companies in Scandinavia are based on lumped models and the HBV concept. But before the hydrological model there is a complex system for collecting, controlling and correcting data applied in the models and the production scheduling and, equally important, routines for surveillance of the processes and manual intervention. Prior to the forecasting the states in the hydrological models are updated based on observations. When snow is present in the catchments snow surveys are an important source for model updating. The meteorological forecast is another premise provider to the hydrological forecast and to get as precise meteorological forecast as possible Statkraft hires resources from the governmental forecasting center. Their task is to interpret the meteorological situation, describe the uncertainties and if necessary use their knowledge and experience to manually correct the forecast in the hydropower production regions. This is one of several forecast applied further in the scheduling process. Both to be able to compare and evaluate different forecast providers and to ensure that we get the best available forecast, forecasts from different sources are applied. Some of these forecasts have undergone statistical corrections to reduce biases. The uncertainties related to the meteorological forecast have for a long time been approached and described by ensemble forecasts. But also the observations used for updating the model have a related uncertainty. Both to the observations itself and to how well they represent the catchment. Though well known, these uncertainties have thus far been handled superficially. Statkraft has initiated a program called ENKI to approach these issues. A part of this program is to apply distributed models for hydrological forecasting. Developing methodologies to handle uncertainties in the observations, the meteorological forecasts, the model itself and how to update the model with this information are other parts of the program. Together with energy price expectations and information about the state of the energy production system the hydrological forecast is input to the next step in the production scheduling both on short and long term. The long term schedule for reservoir filling is premise provider to the short term optimizing of water. The long term schedule is based on the actual reservoir levels, snow storages and a long history of meteorological observations and gives an overall schedule at a regional level. Within the regions a more detailed tool is used for short term optimizing of the hydropower production Each reservoir is scheduled taking into account restrictions in the water courses and cost of start and stop of aggregates. The value of the water is calculated for each reservoir and reflects the risk of water spillage. This compared to the energy price determines whether an aggregate will run or not. In a gradually more complex energy system with relatively lower regulated capacity this is an increasingly more challenging task.
Modeling Net Land Occupation of Hydropower Reservoirs in Norway for Use in Life Cycle Assessment.
Dorber, Martin; May, Roel; Verones, Francesca
2018-02-20
Increasing hydropower electricity production constitutes a unique opportunity to mitigate climate change impacts. However, hydropower electricity production also impacts aquatic and terrestrial biodiversity through freshwater habitat alteration, water quality degradation, and land use and land use change (LULUC). Today, no operational model exists that covers any of these cause-effect pathways within life cycle assessment (LCA). This paper contributes to the assessment of LULUC impacts of hydropower electricity production in Norway in LCA. We quantified the inundated land area associated with 107 hydropower reservoirs with remote sensing data and related it to yearly electricity production. Therewith, we calculated an average net land occupation of 0.027 m 2 ·yr/kWh of Norwegian storage hydropower plants for the life cycle inventory. Further, we calculated an adjusted average land occupation of 0.007 m 2 ·yr/kWh, accounting for an underestimation of water area in the performed maximum likelihood classification. The calculated land occupation values are the basis to support the development of methods for assessing the land occupation impacts of hydropower on biodiversity in LCA at a damage level.
Impacts of climate change, policy and Water-Energy-Food nexus on hydropower development
Zhang, Xiao; Li, Hong-Yi; Deng, Zhiqun Daniel; ...
2017-10-10
We report that hydropower plays an important role as the global energy system moves towards a less carbon-intensive and sustainable future as promoted under the Sustainable Development Goals (SDGs). This article provides a systematic review of the impacts from policy, climate change and Water-Energy-Food (W-E-F) nexus on hydropower development at global scale. Asia, Africa and Latin America are hotspots promoting hydropower development with capacity expansion, while Europe and North America focus on performance improvement and environment impacts mitigation. Climate change is projected to improve gross hydropower potential (GHP) at high latitude of North Hemisphere and tropical Africa and decrease thatmore » in the US, South Africa and south and central Europe. Analysis from W-E-F nexus highlights the importance of integrated approaches as well as cross-sectoral coordination so as to improve resources use efficiency and achieve sustainable hydropower development. In conclusion, these three factors together shape the future of hydropower and need to be considered for planning and operation purpose.« less
Impacts of climate change, policy and Water-Energy-Food nexus on hydropower development
DOE Office of Scientific and Technical Information (OSTI.GOV)
Zhang, Xiao; Li, Hong-Yi; Deng, Zhiqun Daniel
We report that hydropower plays an important role as the global energy system moves towards a less carbon-intensive and sustainable future as promoted under the Sustainable Development Goals (SDGs). This article provides a systematic review of the impacts from policy, climate change and Water-Energy-Food (W-E-F) nexus on hydropower development at global scale. Asia, Africa and Latin America are hotspots promoting hydropower development with capacity expansion, while Europe and North America focus on performance improvement and environment impacts mitigation. Climate change is projected to improve gross hydropower potential (GHP) at high latitude of North Hemisphere and tropical Africa and decrease thatmore » in the US, South Africa and south and central Europe. Analysis from W-E-F nexus highlights the importance of integrated approaches as well as cross-sectoral coordination so as to improve resources use efficiency and achieve sustainable hydropower development. In conclusion, these three factors together shape the future of hydropower and need to be considered for planning and operation purpose.« less
Systematic high-resolution assessment of global hydropower potential.
Hoes, Olivier A C; Meijer, Lourens J J; van der Ent, Ruud J; van de Giesen, Nick C
2017-01-01
Population growth, increasing energy demand and the depletion of fossil fuel reserves necessitate a search for sustainable alternatives for electricity generation. Hydropower could replace a large part of the contribution of gas and oil to the present energy mix. However, previous high-resolution estimates of hydropower potential have been local, and have yet to be applied on a global scale. This study is the first to formally present a detailed evaluation of the hydropower potential of each location, based on slope and discharge of each river in the world. The gross theoretical hydropower potential is approximately 52 PWh/year divided over 11.8 million locations. This 52 PWh/year is equal to 33% of the annually required energy, while the present energy production by hydropower plants is just 3% of the annually required energy. The results of this study: all potentially interesting locations for hydroelectric power plants, are available online.
Hydropower Modeling Challenges
DOE Office of Scientific and Technical Information (OSTI.GOV)
Stoll, Brady; Andrade, Juan; Cohen, Stuart
Hydropower facilities are important assets for the electric power sector and represent a key source of flexibility for electric grids with large amounts of variable generation. As variable renewable generation sources expand, understanding the capabilities and limitations of the flexibility from hydropower resources is important for grid planning. Appropriately modeling these resources, however, is difficult because of the wide variety of constraints these plants face that other generators do not. These constraints can be broadly categorized as environmental, operational, and regulatory. This report highlights several key issues involving incorporating these constraints when modeling hydropower operations in terms of production costmore » and capacity expansion. Many of these challenges involve a lack of data to adequately represent the constraints or issues of model complexity and run time. We present several potential methods for improving the accuracy of hydropower representation in these models to allow for a better understanding of hydropower's capabilities.« less
Systematic high-resolution assessment of global hydropower potential
van de Giesen, Nick C.
2017-01-01
Population growth, increasing energy demand and the depletion of fossil fuel reserves necessitate a search for sustainable alternatives for electricity generation. Hydropower could replace a large part of the contribution of gas and oil to the present energy mix. However, previous high-resolution estimates of hydropower potential have been local, and have yet to be applied on a global scale. This study is the first to formally present a detailed evaluation of the hydropower potential of each location, based on slope and discharge of each river in the world. The gross theoretical hydropower potential is approximately 52 PWh/year divided over 11.8 million locations. This 52 PWh/year is equal to 33% of the annually required energy, while the present energy production by hydropower plants is just 3% of the annually required energy. The results of this study: all potentially interesting locations for hydroelectric power plants, are available online. PMID:28178329
Biennial Environmental Compliance Report (2010-2012)
This Biennial Environmental Compliance Report (BECR) documents United States (U.S.) Department of Energy (DOE) compliance with environmental regulations applicable to the Waste Isolation Pilot Plant (WIPP) facility.
NASA Astrophysics Data System (ADS)
Stanzel, Philipp; Kling, Harald; Nicholson, Kit
2014-05-01
Hydropower is the most important energy source in Mozambique, as in many other southern African countries. In the Zambezi basin, it is one of the major economic resources, and substantial hydropower development is envisaged for the next decades. In Mozambique, the extension of the large Cahora Bassa hydropower plant and the construction of several new facilities downstream are planned. Irrigated agriculture currently plays a minor role, but has a large potential due to available land and water resources. Irrigation development, especially for the production of biofuels, is an important government policy goal in Mozambique. This contribution assesses interrelations and trade-offs between these two development options with high dependence on water availability. Potential water demand for large-scale irrigated agriculture is estimated for a mix of possible biofuel crops in three scenarios with different irrigated area sizes. Impacts on river discharge and hydropower production in the Lower Zambezi and its tributaries under two projected future climates are simulated with a hydrological model and a reservoir operation and hydropower model. Trade-offs of increasing biofuel production with decreasing hydropower generation due to diminished discharge in the Zambezi River are investigated based on potential energy production, from hydropower and biofuels, and resulting gross revenues and net benefits. Results show that the impact of irrigation withdrawal on hydropower production is rather low due to the generally high water availability in the Zambezi River. In simulations with substantial irrigated areas, hydropower generation decreases by -2% as compared to a scenario with only small irrigated areas. The economic analyses suggest that the use of water for cultivation of biofuel crops in the Zambezi basin can generate higher economic benefits than the use of water for hydroelectric power production. If world oil prices stay at more than about 80 USD/barrel, then the production of biofuels for oil import substitution will yield strong benefits except for the least efficient producers. Producing biofuels for export is more challenging and requires highly efficient production. Generally, investment in irrigated agriculture is expected to have more impact on local economy and therefore poverty reduction than investment in hydropower development.
Dos Idiomas, Un Mundo. Dual Language Project. Title VII Biennial Evaluation Report, 1995-97.
ERIC Educational Resources Information Center
Ernest, Harishini M.; Gonzalez, Rosa M.
This is an evaluation of the first 2 years of a 5-year comprehensive Bilingual Education grant funded by Title VII Part A of the Improving America's Schools Act of 1994 in the Austin Independent School District (AISD) (Texas). The grant awarded to the AISD funds a program of Developmental Bilingual Education at two elementary schools where more…
1990-01-01
effective ways of promoting U.S. interests. Finally, our Denton Amendment space-available transportation program continues assisting generous American hu... Eglin AFB, FL 9th SOS, Eglin AFB, FL 55th SOS, Eglin AFB, FL 1724th Special Tactics Squadron, Pope AFB, NC 67th SOS, RAF Woodbridge, UK 21st SOS...almost all of which were built from 1962 to 1966 - faced block obsolescence within a decade, and their missiles would not be effective against hardened
Land Systems Impacts of Hydropower Development
NASA Astrophysics Data System (ADS)
Wu, G. C.; Torn, M. S.
2016-12-01
Hydropower is often seen as the low-cost, low-carbon, and high-return technology for meeting rising electricity demand and fueling economic growth. Despite the magnitude and pace of hydropower expansion in many developing countries, the potential land use and land cover change (LULCC), particularly indirect LULCC, resulting from hydropower development is poorly understood. Hydropower-driven LULCC can have multiple impacts ranging from global and local climate modification (e.g., increased extreme precipitation events or increased greenhouse gas emissions), ecosystem degradation and fragmentation, to feedbacks on hydropower generation (e.g., increased sedimentation of the reservoir). As a result, a better understanding of both direct and indirect LULCC impacts can inform a more integrated and low-impact model for energy planning in countries with transitioning or growing energy portfolios. This study uses multi-scale remote sensing imagery (Landsat, MODIS, fine-resolution commercial imagery) to estimate LULCC from past hydropower projects intended primarily for electricity generation in 12 countries in Africa, South and Central America, South Asia, and Southeast Asia. It is important to examine multiple locations to determine how socio-political and environmental context determines the magnitude of LULCC. Previous studies have called for the need to scale-up local case studies to examine "cumulative impacts" of multiple development activities within a watershed. We use a pre-test/post-test quasi-experimental design using a time series of classified images and vegetation indices before and after hydropower plant construction as the response variable in an interrupted time series regression analysis. This statistical technique measures the "treatment" effect of hydropower development on indirect LULCC. Preliminary results show land use change and landscape fragmentation following hydropower development, primarily agricultural and urban in nature. These results suggest that indirect land use change should be considered in the energy planning process and design of environmental impact assessments. The large-scale land system impact assessment method used in this study can be extended to examine other intensive development projects such as road construction and mining.
Disappearing rivers — The limits of environmental assessment for hydropower in India
DOE Office of Scientific and Technical Information (OSTI.GOV)
Erlewein, Alexander, E-mail: erlewein@sai.uni-heidelberg.de
2013-11-15
The mountain rivers of the Indian Himalaya possess a vast potential for hydropower generation. After decades of comparatively modest development recent years have seen a major intensification in the construction of new hydropower dams. Although increasingly portrayed as a form of renewable energy generation, hydropower development may lead to extensive alterations of fluvial systems and conflicts with resource use patterns of local communities. To appraise and reduce adverse effects is the purpose of statutory Environmental Impact Assessments (EIA) and corresponding mitigation plans. However, in the light of ambitious policies for hydropower expansion conventional approaches of environmental assessment are increasingly challengedmore » to keep up with the intensity and pace of development. This paper aims to explore the systemic limitations of environmental assessment for hydropower development in the Indian state of Himachal Pradesh. Based on a qualitative methodology involving interviews with environmental experts, document reviews and field observations the study suggests that the current practice of constraining EIAs to the project level fails to address the larger effects of extensive hydropower development. Furthermore, it is critically discussed as to what extent the concept of Strategic Environmental Assessment (SEA) might have the potential to overcome existing shortcomings.« less
Hydropower Regulatory and Permitting Information Desktop (RAPID) Toolkit
DOE Office of Scientific and Technical Information (OSTI.GOV)
Levine, Aaron L
Hydropower Regulatory and Permitting Information Desktop (RAPID) Toolkit presentation from the WPTO FY14-FY16 Peer Review. The toolkit is aimed at regulatory agencies, consultants, project developers, the public, and any other party interested in learning more about the hydropower regulatory process.
Hydropower Vision: Full Report
DOE Office of Scientific and Technical Information (OSTI.GOV)
None, None
Hydropower has provided clean, affordable, reliable, and renewable electricity in the United States for more than a century. Building on hydropower’s historical significance, and to inform the continued technical evolution, energy market value, and environmental performance of the industry, the U.S. Department of Energy’s (DOE’s) Wind and Water Power Technologies Office has led a first-of-its-kind comprehensive analysis focused on a set of potential pathways for the environmentally sustainable expansion of hydropower (hydropower generation and pumped storage) in the United States.
NASA Astrophysics Data System (ADS)
Liu, D.; Wei, X.; Li, H. Y.; Lin, M.; Tian, F.; Huang, Q.
2017-12-01
In the socio-hydrological system, the ecological functions and environmental services, which are chosen to maintain, are determined by the preference of the society, which is making the trade-off among the values of riparian vegetation, fish, river landscape, water supply, hydropower, navigation and so on. As the society develops, the preference of the value will change and the ecological functions and environmental services which are chosen to maintain will change. The aim of the study is to focus on revealing the feedback relationship of water supply, hydropower and environment and the dynamical feedback mechanism at macro-scale, and to establish socio-hydrological evolution model of the watershed based on the modeling of multiple socio-natural processes. The study will aim at the Han River in China, analyze the impact of the water supply and hydropower on the ecology, hydrology and other environment elements, and study the effect on the water supply and hydropower to ensure the ecological and environmental water of the different level. Water supply and ecology are usually competitive. In some reservoirs, hydropower and ecology are synergic relationship while they are competitive in some reservoirs. The study will analyze the multiple mechanisms to implement the dynamical feedbacks of environment to hydropower, set up the quantitative relationship description of the feedback mechanisms, recognize the dominant processes in the feedback relationships of hydropower and environment and then analyze the positive and negative feedbacks in the feedback networks. The socio-hydrological evolution model at the watershed scale will be built and applied to simulate the long-term evolution processes of the watershed of the current situation. Dynamical nexus of water supply, hydropower and environment will be investigated.
Standard Modular Hydropower Technology Acceleration Workshop: Summary Report
DOE Office of Scientific and Technical Information (OSTI.GOV)
Smith, Brennan T.; DeNeale, Scott T.; Witt, Adam M.
In support of the Department of Energy (DOE) funded Standard Modular Hydropower (SMH) Technology Acceleration project, Oak Ridge National Laboratory (ORNL) staff convened with five small hydropower technology entrepreneurs on June 14 and 15, 2017 to discuss gaps, challenges, and opportunities for small modular hydropower development. The workshop was designed to walk through SMH concepts, discuss the SMH research vision, assess how each participant’s technology aligns with SMH concepts and research, and identify future pathways for mutually beneficial collaboration that leverages ORNL expertise and entrepreneurial industry experience. The goal coming out of the workshop is to advance standardized, scalable, modularmore » hydropower technologies and development approaches with sustained and open dialogue among diverse stakeholder groups.« less
CaPTC hosts the 'Biennial Science of Global Prostate Cancer Disparities in Black Men' conference to address the growing global public health problem of prostate cancer among Black men in industrialized and developing countries.
Schramm, Michael P.; Bevelhimer, Mark S.; DeRolph, Chris R.
2016-04-11
Environmental mitigation plays an important role in the environmentally sustainable development of hydropower resources. However, comprehensive data on mitigation required by the Federal Energy Regulatory Commission (FERC) at United States (US) hydropower projects is lacking. Therefore, our objective was to create a comprehensive database of mitigation required at non-federal hydropower projects and provide a synthesis of available mitigation data. Mitigation data was collated for over 300 plants licensed or relicensed from 1998 through 2013. We observed that the majority of FERC mitigation requirements deal with either hydrologic flows or recreation and that hydropower plants in the Pacific Northwest had themore » highest number of requirements. Our data indicate opportunities exist to further explore hydropower mitigation in the areas of environmental flows, fish passage, and water quality. Lastly, connecting these data with ecological outcomes, actual flow data, and larger landscape level information will be necessary to evaluate the effectiveness of mitigation and ultimately inform regulators, managers, and planners.« less
DOE Office of Scientific and Technical Information (OSTI.GOV)
Schramm, Michael P.; Bevelhimer, Mark S.; DeRolph, Chris R.
Environmental mitigation plays an important role in the environmentally sustainable development of hydropower resources. However, comprehensive data on mitigation required by the Federal Energy Regulatory Commission (FERC) at United States (US) hydropower projects is lacking. Therefore, our objective was to create a comprehensive database of mitigation required at non-federal hydropower projects and provide a synthesis of available mitigation data. Mitigation data was collated for over 300 plants licensed or relicensed from 1998 through 2013. We observed that the majority of FERC mitigation requirements deal with either hydrologic flows or recreation and that hydropower plants in the Pacific Northwest had themore » highest number of requirements. Our data indicate opportunities exist to further explore hydropower mitigation in the areas of environmental flows, fish passage, and water quality. Lastly, connecting these data with ecological outcomes, actual flow data, and larger landscape level information will be necessary to evaluate the effectiveness of mitigation and ultimately inform regulators, managers, and planners.« less
Miller, Benjamin L; Arntzen, Evan V; Goldman, Amy E; Richmond, Marshall C
2017-10-01
The United States is home to 2198 dams actively used for hydropower production. With the December 2015 consensus adoption of the United Nations Framework Convention on Climate Change Paris Agreement, it is important to accurately quantify anthropogenic greenhouse gas emissions. Methane ebullition, or methane bubbles originating from river or lake sediments, has been shown to account for nearly all methane emissions from tropical hydropower reservoirs to the atmosphere. However, distinct ebullitive methane fluxes have been studied in comparatively few temperate hydropower reservoirs globally. This study measures ebullitive and diffusive methane fluxes from two eastern Washington reservoirs, and synthesizes existing studies of methane ebullition in temperate, boreal, and tropical hydropower reservoirs. Ebullition comprises nearly all methane emissions (>97%) from this study's two eastern Washington hydropower reservoirs to the atmosphere. Summer methane ebullition from these reservoirs was higher than ebullition in six southeastern U.S. hydropower reservoirs, however it was similar to temperate reservoirs in other parts of the world. Our literature synthesis suggests that methane ebullition from temperate hydropower reservoirs can be seasonally elevated compared to tropical climates, however annual emissions are likely to be higher within tropical climates, emphasizing the possible range of methane ebullition fluxes and the need for the further study of temperate reservoirs. Possible future changes to the Intergovernmental Panel on Climate Change and UNFCCC guidelines for national greenhouse gas inventories highlights the need for accurate assessment of reservoir emissions.
NASA Astrophysics Data System (ADS)
Miller, Benjamin L.; Arntzen, Evan V.; Goldman, Amy E.; Richmond, Marshall C.
2017-10-01
The United States is home to 2198 dams actively used for hydropower production. With the December 2015 consensus adoption of the United Nations Framework Convention on Climate Change Paris Agreement, it is important to accurately quantify anthropogenic greenhouse gas emissions. Methane ebullition, or methane bubbles originating from river or lake sediments, has been shown to account for nearly all methane emissions from tropical hydropower reservoirs to the atmosphere. However, distinct ebullitive methane fluxes have been studied in comparatively few temperate hydropower reservoirs globally. This study measures ebullitive and diffusive methane fluxes from two eastern Washington reservoirs, and synthesizes existing studies of methane ebullition in temperate, boreal, and tropical hydropower reservoirs. Ebullition comprises nearly all methane emissions (>97%) from this study's two eastern Washington hydropower reservoirs to the atmosphere. Summer methane ebullition from these reservoirs was higher than ebullition in six southeastern U.S. hydropower reservoirs, however it was similar to temperate reservoirs in other parts of the world. Our literature synthesis suggests that methane ebullition from temperate hydropower reservoirs can be seasonally elevated compared to tropical climates, however annual emissions are likely to be higher within tropical climates, emphasizing the possible range of methane ebullition fluxes and the need for the further study of temperate reservoirs. Possible future changes to the Intergovernmental Panel on Climate Change and UNFCCC guidelines for national greenhouse gas inventories highlights the need for accurate assessment of reservoir emissions.
Doty, Michelle; Rustgi, Sheila D; Schoen, Cathy; Collins, Sara R
2009-01-01
As the U.S. economic downturn continues and job losses mount, more working Americans are likely to lose access to affordable health benefits subsidized by their employers. Analysis of the 2007 Commonwealth Fund Biennial Health Insurance Survey finds that two of three working adults would be eligible to extend job-based coverage, under the 1985 Consolidated Omnibus Budget Reconciliation Act (COBRA) if they became unemployed. Under COBRA, however, unemployed workers would have to pay four to six times their current contribution at a time of sharply reduced income. In fact, the latest national figures indicate that, because of high premiums, only 9 percent of unemployed workers have COBRA coverage. Substantial financial assistance of 75 percent to 85 percent of premiums could help laid-off workers maintain coverage. In addition, expansion of Medicaid and the State Children's Health Insurance Program would benefit low-income, laid-off workers and their families who are ineligible for COBRA.
Federal Register 2010, 2011, 2012, 2013, 2014
2010-02-24
... DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13618-000] Coastal Hydropower LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications February 18, 2010. On November 5, 2009, Coastal Hydropower...
Development of Sustainability Assessment Tool for Malaysian hydropower industry: A case study
NASA Astrophysics Data System (ADS)
Turan, Faiz Mohd; Johan, Kartina; Abu Sofian, Muhammad Irfan
2018-04-01
This research deals with the development of sustainability assessment tools as a medium to assess the performance of a hydropower project compliances towards sustainability practice. Since the increasing needs of implementing sustainability practice, developed countries are utilizing sustainability tools to achieve sustainable development goals. Its inception within ASEAN countries including Malaysia is still low. The problem with most tools developed from other countries is that it is not very comprehensive as well as its implementation factors are not suitable for the local environment that is not quantified. Hence, there is a need to develop a suitable sustainable assessment tool for the Malaysian hydropower industry to comply with the sustainable development goals as a bridging gap between the governor and the practitioner. The steps of achieving this goal is separated into several parts. The first part is to identify sustainable parameters from established tools as a model for comparison to enhance new parameters. The second stage is to convert equivalent quantification value from the model to the new developed tools. The last stage is to develop software program as a mean of gaining energy company feedback with systematic sustainable reporting from the surveyor so as to be able to integrate sustainability assessment, monitoring and reporting for self-improved reporting.
Rock Mass Behavior Under Hydropower Embankment Dams: A Two-Dimensional Numerical Study
NASA Astrophysics Data System (ADS)
Bondarchuk, A.; Ask, M. V. S.; Dahlström, L.-O.; Nordlund, E.
2012-09-01
Sweden has more than 190 large hydropower dams, of which about 50 are pure embankment dams and over 100 are concrete/embankment dams. This paper presents results from conceptual analyses of the response of typical Swedish rock mass to the construction of a hydropower embankment dam and its first stages of operation. The aim is to identify locations and magnitudes of displacements that are occurring in the rock foundation and grout curtain after construction of the dam, the first filling of its water reservoir, and after one seasonal variation of the water table. Coupled hydro-mechanical analysis was conducted using the two-dimensional distinct element program UDEC. Series of the simulations have been performed and the results show that the first filling of the reservoir and variation of water table induce largest magnitudes of displacement, with the greatest values obtained from the two models with high differential horizontal stresses and smallest spacing of sub-vertical fractures. These results may help identifying the condition of the dam foundation and contribute to the development of proper maintenance measures, which guarantee the safety and functionality of the dam. Additionally, newly developed dams may use these results for the estimation of the possible response of the rock foundation to the construction.
NASA Astrophysics Data System (ADS)
Peviani, Maximo; Alterach, Julio; Danelli, Andrea
2010-05-01
The three years SEE HYDROPOWER project started on June 2009, financed by the South-East Transnational Cooperation Programme (EU), aims to a sustainable exploitation of water concerning hydropower production in SEE countries, looking up to renewable energy sources development, preserving environmental quality and preventing flood risk. Hydropower is the most important renewable resource for energy production in the SEE countries but creates ecological impacts on a local scale. If on one hand, hydroelectric production has to be maintained and likely increased following the demand trend and RES-e Directive, on the other hand, hydropower utilisation often involves severe hydrological changes, damages the connectivity of water bodies and injures river ecosystems. The project gives a strong contribution to the integration between the Water Frame and the RES-e Directives in the involved countries. The SEE HYDROPOWER project promotes the optimal use of water, as multiple natural resources, in order to face the increasing regional electrical-energy demand. Furthermore, SEE HYDROPOWER defines specific needs and test methodologies & tools, in order to help public bodies to take decisions about planning and management of water and hydropower concessions, considering all multi-purposes uses, taking into account the environmental sustainability of natural resources and flooding risks. Investigations is carried on to define common strategies & methods for preserving river with particular concerns to aquatic ecosystems, considering the required Minimum Environmental Flow, macro-habitat quality, migratory fishes and related environmental issues. Other problem addressed by the Project is the contrast between Public Administration and Environmental associations on one side and the Hydropower producers on the other side, for the exploitation of water bodies. Competition between water users (for drinking, irrigation, industrial processes, power generation, etc.) is becoming a serious problem, and there is a strong need of a more accurate planning and management optimization of the resources. The partnership includes a well balance mixing of public administrations, agencies ruling hydropower development, water bodies conservation and scientific institutions having the most advanced technology applied to water management and hydropower generation. Furthermore, a permanent "consultant panel" integrated by target groups representatives from different European countries are involved in key decisions and meetings, that guaranty a concrete regional scale participation. The present work reports the overall strategy of the project and the description of the main informatic tools that are under development and implementation in five pilot regions, located in Italy, Austria, Romania, Slovenia and Greece. Keywords: WFD Directive, RES-e Directive, water multi-purpose uses, renewable energy, small hydropower production, environmental balance, minimum environmental flow, flood protection
Voluntary Green Power Procurement | Energy Analysis | NREL
state renewable portfolio standards (RPSs). Pie chart depicting the voluntary market share of non -hydropower renewable generation. And, chart depicting the voluntary market share of non-hydropower renewable generation over time, from 2006 to 2015. Voluntary market share of U.S. non-hydropower renewable generation
Assessing Hydropower in the West
Johnson, Megan M.; Uria Martinez, Rocio
2015-06-01
On April 27, the U.S. Department of Energy (DOE) released the 2014 Hydropower Market Report, which provides a quantitative baseline on the distribution, capabilities, and status of hydropower in the United States. Although the report shows many interesting trends and figures, this article focuses on those related to the western region.
Federal Register 2010, 2011, 2012, 2013, 2014
2011-02-04
... DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13954-000] Mahoning Hydropower, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments... Hydropower, LLC filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power...
Federal Register 2010, 2011, 2012, 2013, 2014
2012-08-28
... DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER12-2447-001] Brookfield Smoky Mountain Hydropower LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes... proceeding, of Brookfield Smoky Mountain Hydropower LLC's application for market- based rate authority, with...
Federal Register 2010, 2011, 2012, 2013, 2014
2011-02-11
... DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13953-000] Mahoning Hydropower, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments... Hydropower, LLC filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power...
Global analysis of a renewable micro hydro power generation plant
NASA Astrophysics Data System (ADS)
Rahman, Md. Shad; Nabil, Imtiaz Muhammed; Alam, M. Mahbubul
2017-12-01
Hydroelectric power or Hydropower means the power generated by the help of flowing water with force. It is one the best source of renewable energy in the world. Water evaporates from the earth's surface, forms clouds, precipitates back to earth, and flows toward the ocean. Hydropower is considered a renewable energy resource because it uses the earth's water cycle to generate electricity. As far as Global is concerned, only a small fraction of electricity is generated by hydro-power. The aim of our analysis is to demonstrate and observe the hydropower of the Globe in micro-scale by our experimental setup which is completely new in concept. This paper consists of all the Global and National Scenario of Hydropower. And how we can more emphasize the generation of Hydroelectric power worldwide.
Hydropower resources at risk: The status of hydropower regulation and development - 1997
DOE Office of Scientific and Technical Information (OSTI.GOV)
Hunt, R.T.; Hunt, J.A.
This report documents today`s hydropower licensing and development status based on published data as follows: (a) Federal Energy Regulatory Commission (FERC) databases, maintained by FERC`s Office of Hydropower Licensing, of: (1) operating FERC-regulated projects, federal projects, and known unlicensed projects; (2) surrendered licenses; and, (3) recent licensing and relicensing actions; (b) Energy Information Administration (EIA) data on installed capacity and generation from 1949 through 1995 for the various resources used to produce electricity in the U.S.; and, (c) FERC licensing orders, and environmental assessments or environmental impact statements for each individual project relicensed since 1980. The analysis conducted to preparemore » this paper includes the effects of all FERC hydropower licensing actions since 1980, and applies those findings to estimate the costs of hydropower licensing and development activity for the next 15 years. It also quantifies the national cost of hydropower regulation. The future estimates are quite conservative. The are presented in 1996 dollars without speculating on the effects of future inflation, license surrenders, conditions imposed through open-ended license articles, license terms greater than 30 years, or low water years. Instead, they show the most directly predictable influences on licensing outcomes using actual experiences since ECPA (after 1986).« less
1981-07-01
conditional, fault-isolation approach of the con- Data Base Requirements tent expert, photographs of normal and abnormal symp- The content-expert may...59 THE AUTOMATED INTERGRATION OF TRAINING AND AIDING INFORMATION FOR THE OPERATOR/TECHNICIAN Dr. Douglas Towne...Subsystem approach devel- until this Third Biennial Conference oped by the Air Force in the 1960’s for us to call a meeting devoted to integrate Human
ERIC Educational Resources Information Center
American Chemical Society, Easton, PA. Div. of Chemical Education.
Included in this proceedings are: (1) letters to conferees; (2) conference chairpersons; (3) symposia listing; (4) chemical demonstrations, listing and abstracts; (5) "birds-of-a-feather" sessions, listing and abstracts (informal sessions providing an opportunities for people with similar interests to meet); (6) workshop listings; (7)…
fuel cell electric vehicles must pay a biennial fee of $120, in addition to standard registration fees . Hybrid electric vehicle owners must pay a biennial fee of $60. (Reference House Bill 3516, 2017, and
Federal Register 2010, 2011, 2012, 2013, 2014
2011-08-11
... its APD to properly perform its function of marketing a limited amount of Federal hydropower. Western... the Federal reclamation program.\\4\\ The basic principle of the Reclamation Act of 1902 was the United... the power marketing functions from the Department of the Interior to Western.\\10\\ Pursuant to this...
NASA Astrophysics Data System (ADS)
Veselka, T. D.; Poch, L.
2011-12-01
Integrating high penetration levels of wind and solar energy resources into the power grid is a formidable challenge in virtually all interconnected systems due to the fact that supply and demand must remain in balance at all times. Since large scale electricity storage is currently not economically viable, generation must exactly match electricity demand plus energy losses in the system as time unfolds. Therefore, as generation from variable resources such as wind and solar fluctuate, production from generating resources that are easier to control and dispatch need to compensate for these fluctuations while at the same time respond to both instantaneous change in load and follow daily load profiles. The grid in the Western U.S. is not exempt to grid integration challenges associated with variable resources. However, one advantage that the power system in the Western U.S. has over many other regional power systems is that its footprint contains an abundance of hydropower resources. Hydropower plants, especially those that have reservoir water storage, can physically change electricity production levels very quickly both via a dispatcher and through automatic generation control. Since hydropower response time is typically much faster than other dispatchable resources such as steam or gas turbines, it is well suited to alleviate variable resource grid integration issues. However, despite an abundance of hydropower resources and the current low penetration of variable resources in the Western U.S., problems have already surfaced. This spring in the Pacific Northwest, wetter than normal hydropower conditions in combination with transmission constraints resulted in controversial wind resource shedding. This action was taken since water spilling would have increased dissolved oxygen levels downstream of dams thereby significantly degrading fish habitats. The extent to which hydropower resources will be able to contribute toward a stable and reliable Western grid is currently being studied. Typically these studies consider the inherent flexibility of hydropower technologies, but tend to fall short on details regarding grid operations, institutional arrangements, and hydropower environmental regulations. This presentation will focus on an analysis that Argonne National Laboratory is conducting in collaboration with the Western Area Power Administration (Western). The analysis evaluates the extent to which Western's hydropower resources may help with grid integration challenges via a proposed Energy Imbalance Market. This market encompasses most of the Western Electricity Coordinating Council footprint. It changes grid operations such that the real-time dispatch would be, in part, based on a 5-minute electricity market. The analysis includes many factors such as site-specific environmental considerations at each of its hydropower facilities, long-term firm purchase agreements, and hydropower operating objectives and goals. Results of the analysis indicate that site-specific details significantly affect the ability of hydropower plant to respond to grid needs in a future which will have a high penetration of variable resources.
Comparison of nonstructural carbohydrates across cranberry cultivars
USDA-ARS?s Scientific Manuscript database
explain low fruit set and biennial bearing tendencies of cranberry (Vaccinium macrocarpon). Yet, comparisons of nonstructural carbohydrate concentrations during critical phenological stages across cultivars that differ in biennial bearing tendencies and return bloom potential are lacking, particular...
Federal Register 2010, 2011, 2012, 2013, 2014
2010-09-22
...: Antrim Micro-Hydropower Project. f. Location: The proposed Antrim Micro-Hydropower Project will be..., protests, and/or motions filed. k. Description of Project: The proposed Antrim Micro-Hydropower Project... and the project will not be connected to an interstate grid. When a Declaration of Intention is filed...
Federal Register 2010, 2011, 2012, 2013, 2014
2012-05-25
... DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2790-055] Boott Hydropower, Inc.; Notice of Consulting Parties and Agenda for Section 106 Consultation Meeting On May 4, 2012, the... Hydropower, Inc. and the Eldred L. Field Hydroelectric Facility Trust (co-licensees for the Lowell...
Federal Register 2010, 2011, 2012, 2013, 2014
2011-10-27
... DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 5984-063] Erie Boulevard Hydropower, L.P.; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and....: 5984-063. c. Date Filed: May 10, 2011. d. Applicant: Erie Boulevard Hydropower, L.P. (dba Brookfield...
Federal Register 2010, 2011, 2012, 2013, 2014
2010-02-24
... Hydropower LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications February 18, 2010. On November 5, 2009, Coastal Hydropower LLC filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act...
Federal Register 2010, 2011, 2012, 2013, 2014
2013-11-18
... Hydropower LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications On August 14, 2013, Houtama Hydropower LLC filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to...
78 FR 58535 - Hydropower Regulatory Efficiency Act of 2013; Supplemental Notice of Workshop
Federal Register 2010, 2011, 2012, 2013, 2014
2013-09-24
... license for hydropower development at non-powered dams and closed-loop pumped storage projects in... for licensing hydropower development at non-powered dams and closed-loop pumped storage projects... closed- loop pumped storage) affect the steps included in a two-year process? 3.9 Should there be a...
Hydropower reservoirs: cytotoxic and genotoxic assessment using the Allium cepa root model.
Rambo, Cassiano Lazarotto; Zanotelli, Patrícia; Dalegrave, Daniela; De Nez, Dinara; Szczepanik, Jozimar; Carazek, Fábio; Franscescon, Francini; Rosemberg, Denis Broock; Siebel, Anna Maria; Magro, Jacir Dal
2017-03-01
Hydropower offers a reliable source of electricity in several countries, and Brazil supplies its energy needs almost entirely through hydropower plants. Nevertheless, hydropower plants comprise large buildings and water reservoirs and dams, resulting in huge ecological disruptions. Here, we analyzed the impact of four hydropower reservoirs construction in metals and pesticides incidence and the cytotoxic and genotoxic potential of sediment elutriate of rivers from southern Brazil. Our analyses have evidenced the elevated incidence of different metals (lead, iron, cadmium, and chrome) and pesticides (methyl parathion, atrazine, and 2,4-dichlorophenoxyacetic acid). We showed that Allium cepa exposed to sediment elutriates did not change the seed germination rate and mitotic index. However, roots from Allium cepa exposed to reservoirs sediment elutriates showed increased occurrence of chromosomal aberrations and nuclear abnormalities. Therefore, the results obtained in our study indicate that sediment from reservoirs present elevated concentration of metals and pesticides and a significant genotoxic potential. Taken together, our data support that hydropower reservoirs represent an environmental scenario that could impact surrounding wildlife and population.
DOE Office of Scientific and Technical Information (OSTI.GOV)
Not Available
2008-09-01
As part of its Native American outreach, DOE?s Wind Powering America program produces a newsletter to present Native American wind information, including projects, interviews with pioneers, issues, WPA activities, and related events. This issue features an interview with Dave Danz, a tribal planner for the Grand Portage Band of Chippewa in northeastern Minnesota, and a feature on the new turbine that powers the KILI radio station on the Pine Ridge Reservation.
Minimizing water consumption when producing hydropower
NASA Astrophysics Data System (ADS)
Leon, A. S.
2015-12-01
In 2007, hydropower accounted for only 16% of the world electricity production, with other renewable sources totaling 3%. Thus, it is not surprising that when alternatives are evaluated for new energy developments, there is strong impulse for fossil fuel or nuclear energy as opposed to renewable sources. However, as hydropower schemes are often part of a multipurpose water resources development project, they can often help to finance other components of the project. In addition, hydropower systems and their associated dams and reservoirs provide human well-being benefits, such as flood control and irrigation, and societal benefits such as increased recreational activities and improved navigation. Furthermore, hydropower due to its associated reservoir storage, can provide flexibility and reliability for energy production in integrated energy systems. The storage capability of hydropower systems act as a regulating mechanism by which other intermittent and variable renewable energy sources (wind, wave, solar) can play a larger role in providing electricity of commercial quality. Minimizing water consumption for producing hydropower is critical given that overuse of water for energy production may result in a shortage of water for other purposes such as irrigation, navigation or fish passage. This paper presents a dimensional analysis for finding optimal flow discharge and optimal penstock diameter when designing impulse and reaction water turbines for hydropower systems. The objective of this analysis is to provide general insights for minimizing water consumption when producing hydropower. This analysis is based on the geometric and hydraulic characteristics of the penstock, the total hydraulic head and the desired power production. As part of this analysis, various dimensionless relationships between power production, flow discharge and head losses were derived. These relationships were used to withdraw general insights on determining optimal flow discharge and optimal penstock diameter. For instance, it was found that for minimizing water consumption, the ratio of head loss to gross head should not exceed about 15%. Two examples of application are presented to illustrate the procedure for determining optimal flow discharge and optimal penstock diameter for impulse and reaction turbines.
NASA Astrophysics Data System (ADS)
Wang, Guihua; Fang, Qinhua; Zhang, Luoping; Chen, Weiqi; Chen, Zhenming; Hong, Huasheng
2010-02-01
Hydropower development brings many negative impacts on watershed ecosystems which are not fully integrated into current decision-making largely because in practice few accept the cost and benefit beyond market. In this paper, a framework was proposed to valuate the effects on watershed ecosystem services caused by hydropower development. Watershed ecosystem services were classified into four categories of provisioning, regulating, cultural and supporting services; then effects on watershed ecosystem services caused by hydropower development were identified to 21 indicators. Thereafter various evaluation techniques including the market value method, opportunity cost approach, project restoration method, travel cost method, and contingent valuation method were determined and the models were developed to valuate these indicators reflecting specific watershed ecosystem services. This approach was applied to three representative hydropower projects (Daguan, Xizaikou and Tiangong) of Jiulong River Watershed in southeast China. It was concluded that for hydropower development: (1) the value ratio of negative impacts to positive benefits ranges from 64.09% to 91.18%, indicating that the negative impacts of hydropower development should be critically studied during its environmental administration process; (2) the biodiversity loss and water quality degradation (together accounting for 80-94%) are the major negative impacts on watershed ecosystem services; (3) the average environmental cost per unit of electricity is up to 0.206 Yuan/kW h, which is about three quarters of its on-grid power tariff; and (4) the current water resource fee accounts for only about 4% of its negative impacts value, therefore a new compensatory method by paying for ecosystem services is necessary for sustainable hydropower development. These findings provide a clear picture of both positive and negative effects of hydropower development for decision-makers in the monetary term, and also provide a basis for further design of environmental instrument such as payment for watershed ecosystem services.
NASA Astrophysics Data System (ADS)
Forrest, K.; Tarroja, B.; AghaKouchak, A.; Chiang, F.; Samuelsen, S.
2017-12-01
Spatial and temporal shifts in hydrological regimes predicted under climate change conditions have implications for the management of reservoirs and hydropower contributions to generation and ancillary services. California relies on large hydropower plants to provide flexible electricity generation, which will be increasingly important for supporting renewable resources. This study examines the impact of climate change on large hydropower generation in California. Four climate models for Representative Concentration Pathways (RCP) 4.5 and RCP 8.5 are utilized to evaluate the impact of the climate change conditions on (1) the magnitude and profile of hydropower generation and (2) the ability of hydropower to provide spinning reserve. Under both RCP scenarios, impacts are regionally dependent, with precipitation projected to increase in northern California and decrease in southern California for the ten-year period investigated (2046-2055). The overall result is a net increase in inflow into large hydropower units as a majority of the hydropower plants studied are located in the northern part of the state. Increased inflow is primarily driven by increased runoff during the winter and does not necessarily result in increased generation, as extreme events yield greater overall spillage, up to 45% of total inflow. Increased winter hydropower generation paired with increased reservoir constraints in summer result in an 11 to 18% decrease in spinning reserve potential across the year. Under high inflow conditions there is a decreased flexibility for choosing generation versus spinning reserve as water needs to be released, regardless. During summer, hydropower units providing spinning reserve experienced decreased inflow and lower reservoir levels compared to the historical baseline, resulting in decreased spinning reserve bidding potential. Decreased bidding, especially during summer periods at peak electricity demand, can result in greater demand for other dispatchable resources, such as natural gas turbines or emerging energy storage technologies, which has implications for electricity costs and overall grid emissions.
Shah, Minesh P; Dahl, Rebecca M; Parashar, Umesh D; Lopman, Benjamin A
2018-01-01
Hospitalizations for rotavirus and acute gastroenteritis (AGE) have declined in the US with rotavirus vaccination, though biennial peaks in incidence in children aged less than 5 years occur. This pattern may be explained by lower rotavirus vaccination coverage in US children (59% to 73% from 2010-2015), resulting in accumulation of susceptible children over two successive birth cohorts. Retrospective cohort analysis of claims data of commercially insured US children aged <5 years. Age-stratified hospitalization rates for rotavirus and for AGE from the 2002-2015 rotavirus seasons were examined. Median age and rotavirus vaccination coverage for biennial rotavirus seasons during pre-vaccine (2002-2005), early post-vaccine (2008-2011) and late post-vaccine (2012-2015) years. Age-stratified hospitalization rates decreased from pre-vaccine to early post-vaccine and then to late post-vaccine years. The clearest biennial pattern in hospitalization rates is the early post-vaccine period, with higher rates in 2009 and 2011 than in 2008 and 2010. The pattern diminishes in the late post-vaccine period. For rotavirus hospitalizations, the median age and the difference in age between biennial seasons was highest during the early post-vaccine period; these differences were not observed for AGE hospitalizations. There was no significant difference in vaccination coverage between biennial seasons. These observations provide conflicting evidence that incomplete vaccine coverage drove the biennial pattern in rotavirus hospitalizations that has emerged with rotavirus vaccination in the US. As this pattern is diminishing with higher vaccine coverage in recent years, further increases in vaccine coverage may reach a threshold that eliminates peak seasons in hospitalizations.
NASA Astrophysics Data System (ADS)
Aheyeva, Viktoryia; Gruzdev, Aleksandr N.
2016-04-01
According to the results of ground-based spectrometric measurements of the stratospheric column NO2 contents (SC NO2) within the Network for the Detection of Atmospheric Composition Change (NDACC), satellite measurements of total ozone (TO) and ERA-Interim reanalysis data of temperature, seasonal and latitudinal distributions of the amplitudes of the quasi-biennial variations of these quantities are obtained. The dependence of the diurnal cycle in the SC NO2 on the phase of quasi-biennial oscillation in the equatorial stratospheric wind (QBO) is revealed. The QBO effects in the SC NO2, TO, and stratospheric temperature in the northern (NH) and southern (SH) hemispheres are most significant during the winter-spring periods. Furthermore they exhibit an essential inter-hemispheric asymmetry. The SC NO2 in the Antarctic for the west QBO phase is less than that for the east phase, and the quasi-biennial variations of the SC NO2 in the SH middle latitudes are opposite to the variations in the Antarctic. In the NH, the winter values of the SC NO2 are generally less during the west QBO phase than during the east phase, whereas in spring, on the contrary, the NO2 values for the west QBO phase exceed those for the east phase. Along with SC NO2, the features of the quasi-biennial variations of TO and stratospheric temperature are discussed. Possible mechanisms of the quasi-biennial variations of the analyzed parameters are considered for the different latitudinal zones.
NASA Astrophysics Data System (ADS)
Ageyeva, V. Yu.; Gruzdev, A. N.
2017-01-01
Seasonal and latitudinal distributions of amplitudes of quasi-biennial variations in total NO2 content (NO2 TC), total ozone content (TOC), and stratospheric temperature are obtained. NO2 TC data from ground-based spectrometric measurements within the Network for the Detection of Atmospheric Composition Change (NDACC), TOC data from satellite measurements, and stratospheric temperature data from ERA-Interim reanalysis are used for the analysis. The differences in the NO2 TC diurnal cycles are identified between the westerly and easterly phases of the quasi-biennial oscillations (QBO) of equatorial stratospheric wind. The QBO effects in the NO2 TC, TOC, and stratospheric temperature in the Northern (NH) and Southern (SH) hemispheres are most significant in the winter-spring periods, with essential differences between the NH and SH. The NO2 TC in the Antarctic is less for the westerly phase of the QBO than that for the easterly phase, and the NO2 TC quasi-biennial variations in the SH mid-latitudes are opposite of the variations in the Antarctic. In the NH, the winter values of the NO2 TC are generally less during the westerly QBO phase than during the easterly phase, whereas in spring, on the contrary, the values for the westerly QBO phase exceed those for the easterly phase. Along with NO2, the features of the quasi-biennial variations of TOC and stratospheric temperature are discussed. Possible mechanisms of the quasi-biennial variations of the analyzed parameters are considered for the different latitudinal zones.
Witt, Adam; Magee, Timothy; Stewart, Kevin; ...
2017-08-10
Managing energy, water, and environmental priorities and constraints within a cascade hydropower system is a challenging multiobjective optimization effort that requires advanced modeling and forecasting tools. Within the mid-Columbia River system, there is currently a lack of specific solutions for predicting how coordinated operational decisions can mitigate the impacts of total dissolved gas (TDG) supersaturation while satisfying multiple additional policy and hydropower generation objectives. In this study, a reduced-order TDG uptake equation is developed that predicts tailrace TDG at seven hydropower facilities on the mid-Columbia River. The equation is incorporated into a general multiobjective river, reservoir, and hydropower optimization toolmore » as a prioritized operating goal within a broader set of system-level objectives and constraints. A test case is presented to assess the response of TDG and hydropower generation when TDG supersaturation is optimized to remain under state water-quality standards. Satisfaction of TDG as an operating goal is highly dependent on whether constraints that limit TDG uptake are implemented at a higher priority than generation requests. According to the model, an opportunity exists to reduce TDG supersaturation and meet hydropower generation requirements by shifting spillway flows to different time periods. In conclusion, a coordinated effort between all project owners is required to implement systemwide optimized solutions that satisfy the operating policies of all stakeholders.« less
DOE Office of Scientific and Technical Information (OSTI.GOV)
Witt, Adam; Magee, Timothy; Stewart, Kevin
Managing energy, water, and environmental priorities and constraints within a cascade hydropower system is a challenging multiobjective optimization effort that requires advanced modeling and forecasting tools. Within the mid-Columbia River system, there is currently a lack of specific solutions for predicting how coordinated operational decisions can mitigate the impacts of total dissolved gas (TDG) supersaturation while satisfying multiple additional policy and hydropower generation objectives. In this study, a reduced-order TDG uptake equation is developed that predicts tailrace TDG at seven hydropower facilities on the mid-Columbia River. The equation is incorporated into a general multiobjective river, reservoir, and hydropower optimization toolmore » as a prioritized operating goal within a broader set of system-level objectives and constraints. A test case is presented to assess the response of TDG and hydropower generation when TDG supersaturation is optimized to remain under state water-quality standards. Satisfaction of TDG as an operating goal is highly dependent on whether constraints that limit TDG uptake are implemented at a higher priority than generation requests. According to the model, an opportunity exists to reduce TDG supersaturation and meet hydropower generation requirements by shifting spillway flows to different time periods. In conclusion, a coordinated effort between all project owners is required to implement systemwide optimized solutions that satisfy the operating policies of all stakeholders.« less
Global Potential for Hydro-generated Electricity and Climate Change Impact
NASA Astrophysics Data System (ADS)
Zhou, Y.; Hejazi, M. I.; Leon, C.; Calvin, K. V.; Thomson, A. M.; Li, H. Y.
2014-12-01
Hydropower is a dominant renewable energy source at the global level, accounting for more than 15% of the world's total power supply. It is also very vulnerable to climate change. Improved understanding of climate change impact on hydropower can help develop adaptation measures to increase the resilience of energy system. In this study, we developed a comprehensive estimate of global hydropower potential using runoff and stream flow data derived from a global hydrologic model with a river routing sub-model, along with turbine technology performance, cost assumptions, and environmental consideration (Figure 1). We find that hydropower has the potential to supply a significant portion of the world energy needs, although this potential varies substantially by regions. Resources in a number of countries exceed by multiple folds the total current demand for electricity, e.g., Russia and Indonesia. A sensitivity analysis indicates that hydropower potential can be highly sensitive to a number of parameters including designed flow for capacity, cost and financing, turbine efficiency, and stream flow. The climate change impact on hydropower potential was evaluated by using runoff outputs from 4 climate models (HadCM3, PCM, CGCM2, and CSIRO2). It was found that the climate change on hydropower shows large variation not only by regions, but also climate models, and this demonstrates the importance of incorporating climate change into infrastructure-planning at the regional level though the existing uncertainties.
Federal Register 2010, 2011, 2012, 2013, 2014
2010-06-30
... Micro-Hydropower Project. f. Location: The proposed Antrim Micro-Hydropower Project will be located on... motions filed. k. Description of Project: The proposed Antrim Micro-Hydropower Project will consist of: (1...-feet to the treatment plant, where it will be connected to the interstate grid; and (6) appurtenant...
Federal Register 2010, 2011, 2012, 2013, 2014
2010-10-21
... and walk participants through all phases of the licensing and exemption processes using the Web site. Specifically, the webinar will provide the opportunity for participants to learn about the small hydropower licensing process, find out how to get more information and assistance from FERC, and ask questions. To...
The role of hydropower in electric power integration of Asian countries
NASA Astrophysics Data System (ADS)
Belyaev, Lev; Savelyev, Vladimir; Chudinova, Lyudmila
2018-01-01
The possible role of hydropower plants in formation and operation of interstate power pools is described based on the generalization of the world experience. Peculiarities of the influence of hydropower on development of interstate electric ties in this part of the world and potential effects are showed on the example of Central and Northeast Asia.
Federal Register 2010, 2011, 2012, 2013, 2014
2011-05-27
... Development in the United States; Notice of Small/Low-Impact Hydropower Webinar The Federal Energy Regulatory... projects. Specifically, the webinar will provide the opportunity for participants to learn the differences..., learn how to get more information and assistance from FERC staff, and ask questions. To register for...
Warren B. Cohen; Sean P. Healey; Samuel Goward; Gretchen G. Moisen; Jeffrey G. Masek; Robert E. Kennedy; Scott L. Powell; Chengquan Huang; Nancy Thomas; Karen Schleeweis; Michael A. Wulder
2007-01-01
The exchange of carbon between forests and the atmosphere is a function of forest type, climate, and disturbance history, with previous studies illustrating that forests play a key role in the terrestrial carbon cycle. The North American Carbon Program (NACP) has supported the acquisition of biennial Landsat image time-series for sample locations throughout much of...
NASA Astrophysics Data System (ADS)
Kibler, K. M.; Alipour, M.
2016-12-01
Achieving the universal energy access Sustainable Development Goal will require great investment in renewable energy infrastructure in the developing world. Much growth in the renewable sector will come from new hydropower projects, including small and diversion hydropower in remote and mountainous regions. Yet, human impacts to hydrological systems from diversion hydropower are poorly described. Diversion hydropower is often implemented in ungauged rivers, thus detection of impact requires flow analysis tools suited to prediction in poorly-gauged and human-altered catchments. We conduct a comprehensive analysis of hydrologic alteration in 32 rivers developed with diversion hydropower in southwestern China. As flow data are sparse, we devise an approach for estimating streamflow during pre- and post-development periods, drawing upon a decade of research into prediction in ungauged basins. We apply a rainfall-runoff model, parameterized and forced exclusively with global-scale data, in hydrologically-similar gauged and ungauged catchments. Uncertain "soft" data are incorporated through fuzzy numbers and confidence-based weighting, and a multi-criteria objective function is applied to evaluate model performance. Testing indicates that the proposed framework returns superior performance (NSE = 0.77) as compared to models parameterized by rote calibration (NSE = 0.62). Confident that the models are providing `the right answer for the right reasons', our analysis of hydrologic alteration based on simulated flows indicates statistically significant hydrologic effects of diversion hydropower across many rivers. Mean annual flows, 7-day minimum and 7-day maximum flows decreased. Frequency and duration of flow exceeding Q25 decreased while duration of flows sustained below the Q75 increased substantially. Hydrograph rise and fall rates and flow constancy increased. The proposed methodology may be applied to improve diversion hydropower design in data-limited regions.
Regional assessment of the hydropower potential of rivers in West Africa
NASA Astrophysics Data System (ADS)
Kling, Harald; Stanzel, Philipp; Fuchs, Martin
2016-04-01
The 15 countries of the Economic Community of West African States (ECOWAS) face a constant shortage of energy supply, which limits sustained economic growth. Currently there are about 50 operational hydropower plants and about 40 more are under construction or refurbishment. The potential for future hydropower development - especially for small-scale plants in rural areas - is assumed to be large, but exact data are missing. This study supports the energy initiatives of the "ECOWAS Centre for Renewable Energy and Energy Efficiency" (ECREEE) by assessing the hydropower potential of all rivers in West Africa. For more than 500,000 river reaches the hydropower potential was computed from channel slope and mean annual discharge. In large areas there is a lack of discharge observations. Therefore, an annual water balance model was used to simulate discharge. The model domain covers 5 Mio km², including e.g. the Niger, Volta, and Senegal River basins. The model was calibrated with observed data of 410 gauges, using precipitation and potential evapotranspiration data as inputs. Historic variations of observed annual discharge between 1950 and 2010 are simulated well by the model. As hydropower plants are investments with a lifetime of several decades we also assessed possible changes in future discharge due to climate change. To this end the water balance model was driven with bias-corrected climate projections of 15 Regional Climate Models for two emission scenarios of the CORDEX-Africa ensemble. The simulation results for the river network were up-scaled to sub-areas and national summaries. This information gives a regional quantification of the hydropower potential, expected climate change impacts, as well as a regional classification for general suitability (or non-suitability) of hydropower plant size - from small-scale to large projects.
DOE Office of Scientific and Technical Information (OSTI.GOV)
Smith, Brennan T.; Welch, Tim; Witt, Adam M.
The Multi-Year Plan for Research, Development, and Prototype Testing of Standard Modular Hydropower Technology (MYRP) presents a strategy for specifying, designing, testing, and demonstrating the efficacy of standard modular hydropower (SMH) as an environmentally compatible and cost-optimized renewable electricity generation technology. The MYRP provides the context, background, and vision for testing the SMH hypothesis: if standardization, modularity, and preservation of stream functionality become essential and fully realized features of hydropower technology, project design, and regulatory processes, they will enable previously unrealized levels of new project development with increased acceptance, reduced costs, increased predictability of outcomes, and increased value to stakeholders.more » To achieve success in this effort, the MYRP outlines a framework of stakeholder-validated criteria, models, design tools, testing facilities, and assessment protocols that will facilitate the development of next-generation hydropower technologies.« less
Modelling a hydropower plant with reservoir with the micropower optimisation model (HOMER)
NASA Astrophysics Data System (ADS)
Canales, Fausto A.; Beluco, Alexandre; Mendes, Carlos André B.
2017-08-01
Hydropower with water accumulation is an interesting option to consider in hybrid systems, because it helps dealing with the intermittence characteristics of renewable energy resources. The software HOMER (version Legacy) is extensively used in research works related to these systems, but it does not include a specific option for modelling hydro with reservoir. This paper describes a method for modelling a hydropower plant with reservoir with HOMER by adapting an existing procedure used for modelling pumped storage. An example with two scenarios in southern Brazil is presented for illustrating and validating the method explained in this paper. The results validate the method by showing a direct correspondence between an equivalent battery and the reservoir. The refill of the reservoir, its power output as a function of the flow rate and installed hydropower capacity are effectively simulated, indicating an adequate representation of a hydropower plant with reservoir is possible with HOMER.
Kokes Award for the 24th North American Catalysis Society Meeting
DOE Office of Scientific and Technical Information (OSTI.GOV)
Rioux, Robert M.
The objective of the Richard. J. Kokes Travel Award program is to encourage the participation of students in the biennial North American Catalysis Society (NACS) Meetings. The Kokes Award covers a significant portion of the transportation, lodging, and conference registration costs. Eligible students must be enrolled at a North American university and need to present a paper at the meeting. The Kokes awardee will be required to contribute some time to the organizing committee to assist in meeting operations and to be present at the meeting during the entire time. Similar to the 23rd Kokes Award program, undergraduate students aremore » also eligible for the 24th Kokes Award program.« less
Efficiently approximating the Pareto frontier: Hydropower dam placement in the Amazon basin
Wu, Xiaojian; Gomes-Selman, Jonathan; Shi, Qinru; Xue, Yexiang; Garcia-Villacorta, Roosevelt; Anderson, Elizabeth; Sethi, Suresh; Steinschneider, Scott; Flecker, Alexander; Gomes, Carla P.
2018-01-01
Real–world problems are often not fully characterized by a single optimal solution, as they frequently involve multiple competing objectives; it is therefore important to identify the so-called Pareto frontier, which captures solution trade-offs. We propose a fully polynomial-time approximation scheme based on Dynamic Programming (DP) for computing a polynomially succinct curve that approximates the Pareto frontier to within an arbitrarily small > 0 on treestructured networks. Given a set of objectives, our approximation scheme runs in time polynomial in the size of the instance and 1/. We also propose a Mixed Integer Programming (MIP) scheme to approximate the Pareto frontier. The DP and MIP Pareto frontier approaches have complementary strengths and are surprisingly effective. We provide empirical results showing that our methods outperform other approaches in efficiency and accuracy. Our work is motivated by a problem in computational sustainability concerning the proliferation of hydropower dams throughout the Amazon basin. Our goal is to support decision-makers in evaluating impacted ecosystem services on the full scale of the Amazon basin. Our work is general and can be applied to approximate the Pareto frontier of a variety of multiobjective problems on tree-structured networks.
Cost-effectiveness of early detection of breast cancer in Catalonia (Spain)
2011-01-01
Background Breast cancer (BC) causes more deaths than any other cancer among women in Catalonia. Early detection has contributed to the observed decline in BC mortality. However, there is debate on the optimal screening strategy. We performed an economic evaluation of 20 screening strategies taking into account the cost over time of screening and subsequent medical costs, including diagnostic confirmation, initial treatment, follow-up and advanced care. Methods We used a probabilistic model to estimate the effect and costs over time of each scenario. The effect was measured as years of life (YL), quality-adjusted life years (QALY), and lives extended (LE). Costs of screening and treatment were obtained from the Early Detection Program and hospital databases of the IMAS-Hospital del Mar in Barcelona. The incremental cost-effectiveness ratio (ICER) was used to compare the relative costs and outcomes of different scenarios. Results Strategies that start at ages 40 or 45 and end at 69 predominate when the effect is measured as YL or QALYs. Biennial strategies 50-69, 45-69 or annual 45-69, 40-69 and 40-74 were selected as cost-effective for both effect measures (YL or QALYs). The ICER increases considerably when moving from biennial to annual scenarios. Moving from no screening to biennial 50-69 years represented an ICER of 4,469€ per QALY. Conclusions A reduced number of screening strategies have been selected for consideration by researchers, decision makers and policy planners. Mathematical models are useful to assess the impact and costs of BC screening in a specific geographical area. PMID:21605383
Environmental sustainability assessment of hydropower plant in Europe using life cycle assessment
NASA Astrophysics Data System (ADS)
Mahmud, M. A. P.; Huda, N.; Farjana, S. H.; Lang, C.
2018-05-01
Hydropower is the oldest and most common type of renewable source of electricity available on this planet. The end of life process of hydropower plant have significant environmental impacts, which needs to be identified and minimized to ensure an environment friendly power generation. However, identifying the environmental impacts and health hazards are very little explored in the hydropower processing routes despite a significant quantity of production worldwide. This paper highlight the life-cycle environmental impact assessment of the reservoir based hydropower generation system located in alpine and non-alpine region of Europe, addressing their ecological effects by the ReCiPe and CML methods under several impact-assessment categories such as human health, ecosystems, global warming potential, acidification potential, etc. The Australasian life-cycle inventory database and SimaPro software are utilized to accumulate life-cycle inventory dataset and to evaluate the impacts. The results reveal that plants of alpine region offer superior environmental performance for couple of considered categories: global warming and photochemical oxidation, whilst in the other cases the outcomes are almost similar. Results obtained from this study will take part an important role in promoting sustainable generation of hydropower, and thus towards environment friendly energy production.
North Carolina Library Association 1997 Biennial Conference.
ERIC Educational Resources Information Center
North Carolina Libraries, 1997
1997-01-01
Provides summaries of the presentations at the North Carolina Library Association's Biennial Conference, "Choose Quality, Choose Libraries," (Raleigh, NC, October 8-10, 1997). Some of the topics covered include library instruction, Internet access to public documents, outsourcing technical services, copyrights and the Internet, the…
Elimination of Cost Sharing for Screening Mammography in Medicare Advantage Plans.
Trivedi, Amal N; Leyva, Bryan; Lee, Yoojin; Panagiotou, Orestis A; Dahabreh, Issa J
2018-01-18
The Affordable Care Act (ACA) required most insurers and the Medicare program to eliminate cost sharing for screening mammography. We conducted a difference-in-differences study of biennial screening mammography among 15,085 women 65 to 74 years of age in 24 Medicare Advantage plans that eliminated cost sharing to provide full coverage for screening mammography, as compared with 52,035 women in 48 matched control plans that had and maintained full coverage. In plans that eliminated cost sharing, adjusted rates of biennial screening mammography increased from 59.9% (95% confidence interval [CI], 54.9 to 65.0) in the 2-year period before cost-sharing elimination to 65.4% (95% CI, 61.8 to 69.0) in the 2-year period thereafter. In control plans, the rates of biennial mammography were 73.1% (95% CI, 69.2 to 77.0) and 72.8% (95% CI, 69.7 to 76.0) during the same periods, yielding a difference in differences of 5.7 percentage points (95% CI, 3.0 to 8.4). The difference in differences was 9.8 percentage points (95% CI, 4.5 to 15.2) among women living in the areas with the highest quartile of educational attainment versus 4.3 percentage points (95% CI, 0.2 to 8.4) among women in the lowest quartile. As indicated by the difference-in-differences estimates, after the elimination of cost sharing, the rate of biennial mammography increased by 6.5 percentage points (95% CI, 3.7 to 9.4) for white women and 8.4 percentage points (95% CI, 2.5 to 14.4) for black women but was almost unchanged for Hispanic women (0.4 percentage points; 95% CI, -7.3 to 8.1). The elimination of cost sharing for screening mammography under the ACA was associated with an increase in rates of use of this service among older women for whom screening is recommended. The effect was attenuated among women living in areas with lower educational attainment and was negligible among Hispanic women. (Funded by the National Institute on Aging.).
Joint optimization of regional water-power systems
NASA Astrophysics Data System (ADS)
Pereira-Cardenal, Silvio J.; Mo, Birger; Gjelsvik, Anders; Riegels, Niels D.; Arnbjerg-Nielsen, Karsten; Bauer-Gottwein, Peter
2016-06-01
Energy and water resources systems are tightly coupled; energy is needed to deliver water and water is needed to extract or produce energy. Growing pressure on these resources has raised concerns about their long-term management and highlights the need to develop integrated solutions. A method for joint optimization of water and electric power systems was developed in order to identify methodologies to assess the broader interactions between water and energy systems. The proposed method is to include water users and power producers into an economic optimization problem that minimizes the cost of power production and maximizes the benefits of water allocation, subject to constraints from the power and hydrological systems. The method was tested on the Iberian Peninsula using simplified models of the seven major river basins and the power market. The optimization problem was successfully solved using stochastic dual dynamic programming. The results showed that current water allocation to hydropower producers in basins with high irrigation productivity, and to irrigation users in basins with high hydropower productivity was sub-optimal. Optimal allocation was achieved by managing reservoirs in very distinct ways, according to the local inflow, storage capacity, hydropower productivity, and irrigation demand and productivity. This highlights the importance of appropriately representing the water users' spatial distribution and marginal benefits and costs when allocating water resources optimally. The method can handle further spatial disaggregation and can be extended to include other aspects of the water-energy nexus.
DOE/PSU Graduate Student Fellowship Program for Hydropower
DOE Office of Scientific and Technical Information (OSTI.GOV)
Cimbala, John M.
The primary objective of this project is to stimulate academic interest in the conventional hydropower field by supplying research support for at least eight individual Master of Science (MS) or Doctoral (PhD) level research projects, each consisting of a graduate student supervised by a faculty member. We have completed many of the individual student research projects: 2 PhD students have finished, and 4 are still working towards their PhD degree. 4 MS students have finished, and 2 are still working towards their MS degree, one of which is due to finish this April. In addition, 4 undergraduate student projects havemore » been completed, and one is to be completed this April. These projects were supervised by 7 faculty members and an Advisory/Review Panel. Our students and faculty have presented their work at national or international conferences and have submitted several journal publications. Three of our graduate students (Keith Martin, Dan Leonard and Hosein Foroutan) have received HRF Fellowships during the course of this project. All of the remaining students are anticipated to be graduated by the end of Fall Semester 2014. All of the tasks for this project will have been completed once all the students have been graduated, although it will be another year or two until all the journal publications have been finalized based on the work performed as part of this DOE Hydropower project.« less
NASA Astrophysics Data System (ADS)
Wang, Jack C.; Tsai-Lin, Rong; Chang, Loren C.; Wu, Qian; Lin, Charles C. H.; Yue, Jia
2018-06-01
The Quasi-biennial Oscillation (QBO) is a persistent oscillation in the zonal mean zonal winds of the low latitude middle atmosphere that is driven by breaking planetary and gravity waves with a period near two years. The atmospheric tides that dominate the dynamics of the mesosphere and lower thermosphere region (MLT, between heights of 70-120 km) are excited in the troposphere and stratosphere, and propagate through QBO-modulated zonal mean zonal wind fields. This allows the MLT tidal response to also be modulated by the QBO, with implications for ionospheric/thermospheric variability. Interannual oscillations in solar radiation can also directly drive the variations in the ionosphere with similar periodicities through the photoionization. Many studies have observed the connection between the solar activity and QBO signal in ionospheric features such as total electron content (TEC). In this research, we develop an empirical model to isolate stratospheric QBO-related tidal variability in the MLT diurnal and semidiurnal tides using values from assimilated TIMED satellite data. Migrating tidal fields corresponding to stratospheric QBO eastward and westward phases, as well as with the quasi-biennial variations in solar activity isolated by the Multi-dimensional Ensemble Empirical Mode Decomposition (MEEMD) analysis from Hilbert-Huang Transform (HHT), are then used to drive the NCAR Thermosphere-Ionosphere-Electrodynamics General Circulation Model (TIE-GCM). The numerical experiment results indicate that the ionospheric QBO is mainly driven by the solar quasi-biennial variations during the solar maximum, since the solar quasi-biennial variation amplitude is directly proportionate to the solar cycle. The ionospheric QBO in the model is sensitive to both the stratospheric QBO and solar quasi-biennial variations during the solar minimum, with solar effects still playing a stronger role.
Dahl, Rebecca M.; Parashar, Umesh D.; Lopman, Benjamin A.
2018-01-01
Background Hospitalizations for rotavirus and acute gastroenteritis (AGE) have declined in the US with rotavirus vaccination, though biennial peaks in incidence in children aged less than 5 years occur. This pattern may be explained by lower rotavirus vaccination coverage in US children (59% to 73% from 2010–2015), resulting in accumulation of susceptible children over two successive birth cohorts. Methods Retrospective cohort analysis of claims data of commercially insured US children aged <5 years. Age-stratified hospitalization rates for rotavirus and for AGE from the 2002–2015 rotavirus seasons were examined. Median age and rotavirus vaccination coverage for biennial rotavirus seasons during pre-vaccine (2002–2005), early post-vaccine (2008–2011) and late post-vaccine (2012–2015) years. Results Age-stratified hospitalization rates decreased from pre-vaccine to early post-vaccine and then to late post-vaccine years. The clearest biennial pattern in hospitalization rates is the early post-vaccine period, with higher rates in 2009 and 2011 than in 2008 and 2010. The pattern diminishes in the late post-vaccine period. For rotavirus hospitalizations, the median age and the difference in age between biennial seasons was highest during the early post-vaccine period; these differences were not observed for AGE hospitalizations. There was no significant difference in vaccination coverage between biennial seasons. Conclusions These observations provide conflicting evidence that incomplete vaccine coverage drove the biennial pattern in rotavirus hospitalizations that has emerged with rotavirus vaccination in the US. As this pattern is diminishing with higher vaccine coverage in recent years, further increases in vaccine coverage may reach a threshold that eliminates peak seasons in hospitalizations. PMID:29444124
Patil, Vijay P.; Karels, Timothy J.; Hik, David S.
2015-01-01
Biennial breeding is a rare life-history trait observed in animal species living in harsh, unproductive environments. This reproductive pattern is thought to occur in 10 of 14 species in the genus Marmota, making marmots useful model organisms for studying its ecological and evolutionary implications. Biennial breeding in marmots has been described as an obligate pattern which evolved as a mechanism to mitigate the energetic costs of reproduction (Evolved Constraint hypothesis). However, recent anecdotal evidence suggests that it is a facultative pattern controlled by annual variation in climate and food availability (Environmental Constraint hypothesis). Finally, in social animals like marmots, biennial breeding could result from reproductive competition between females within social groups (Social Constraint hypothesis). We evaluated these three hypotheses using mark-recapture data from an 8-year study of hoary marmot (Marmota caligata) population dynamics in the Yukon. Annual variation in breeding probability was modeled using multi-state mark-recapture models, while other reproductive life-history traits were modeled with generalized linear mixed models. Hoary marmots were neither obligate nor facultative biennial breeders, and breeding probability was insensitive to evolved, environmental, or social factors. However, newly mature females were significantly less likely to breed than older individuals. Annual breeding did not result in increased mortality. Female survival and, to a lesser extent, average fecundity were correlated with winter climate, as indexed by the Pacific Decadal Oscillation. Hoary marmots are less conservative breeders than previously believed, and the evidence for biennial breeding throughout Marmota, and in other arctic/alpine/antarctic animals, should be re-examined. Prediction of future population dynamics requires an accurate understanding of life history strategies, and of how life history traits allow animals to cope with changes in weather and other demographic influences. PMID:25768300
A multi-scale spatial approach to address environmental effects of small hydropower development.
McManamay, Ryan A; Samu, Nicole; Kao, Shih-Chieh; Bevelhimer, Mark S; Hetrick, Shelaine C
2015-01-01
Hydropower development continues to grow worldwide in developed and developing countries. While the ecological and physical responses to dam construction have been well documented, translating this information into planning for hydropower development is extremely difficult. Very few studies have conducted environmental assessments to guide site-specific or widespread hydropower development. Herein, we propose a spatial approach for estimating environmental effects of hydropower development at multiple scales, as opposed to individual site-by-site assessments (e.g., environmental impact assessment). Because the complex, process-driven effects of future hydropower development may be uncertain or, at best, limited by available information, we invested considerable effort in describing novel approaches to represent environmental concerns using spatial data and in developing the spatial footprint of hydropower infrastructure. We then use two case studies in the US, one at the scale of the conterminous US and another within two adjoining rivers basins, to examine how environmental concerns can be identified and related to areas of varying energy capacity. We use combinations of reserve-design planning and multi-metric ranking to visualize tradeoffs among environmental concerns and potential energy capacity. Spatial frameworks, like the one presented, are not meant to replace more in-depth environmental assessments, but to identify information gaps and measure the sustainability of multi-development scenarios as to inform policy decisions at the basin or national level. Most importantly, the approach should foster discussions among environmental scientists and stakeholders regarding solutions to optimize energy development and environmental sustainability.
Addressing biogenic greenhouse gas emissions from hydropower in LCA.
Hertwich, Edgar G
2013-09-03
The ability of hydropower to contribute to climate change mitigation is sometimes questioned, citing emissions of methane and carbon dioxide resulting from the degradation of biogenic carbon in hydropower reservoirs. These emissions are, however, not always addressed in life cycle assessment, leading to a bias in technology comparisons, and often misunderstood. The objective of this paper is to review and analyze the generation of greenhouse gas emissions from reservoirs for the purpose of technology assessment, relating established emission measurements to power generation. A literature review, data collection, and statistical analysis of methane and CO2 emissions are conducted. In a sample of 82 measurements, methane emissions per kWh hydropower generated are log-normally distributed, ranging from micrograms to 10s of kg. A multivariate regression analysis shows that the reservoir area per kWh electricity is the most important explanatory variable. Methane emissions flux per reservoir area are correlated with the natural net primary production of the area, the age of the power plant, and the inclusion of bubbling emissions in the measurement. Even together, these factors fail to explain most of the variation in the methane flux. The global average emissions from hydropower are estimated to be 85 gCO2/kWh and 3 gCH4/kWh, with a multiplicative uncertainty factor of 2. GHG emissions from hydropower can be largely avoided by ceasing to build hydropower plants with high land use per unit of electricity generated.
Hofvind, Solveig; Román, Marta; Sebuødegård, Sofie; Falk, Ragnhild S
2016-12-01
To compute a ratio between the estimated numbers of lives saved from breast cancer death and the number of women diagnosed with a breast cancer that never would have been diagnosed during the woman's lifetime had she not attended screening (epidemiologic over-diagnosis) in the Norwegian Breast Cancer Screening Program. The Norwegian Breast Cancer Screening Program invites women aged 50-69 to biennial mammographic screening. Results from published studies using individual level data from the programme for estimating breast cancer mortality and epidemiologic over-diagnosis comprised the basis for the ratio. The mortality reduction varied from 36.8% to 43% among screened women, while estimates on epidemiologic over-diagnosis ranged from 7% to 19.6%. We computed the average estimates for both values. The benefit-detriment ratio, number of lives saved, and number of women over-diagnosed were computed for different scenarios of reduction in breast cancer mortality and epidemiologic over-diagnosis. For every 10,000 biennially screened women, followed until age 79, we estimated that 53-61 (average 57) women were saved from breast cancer death, and 45-126 (average 82) were over-diagnosed. The benefit-detriment ratio using average estimates was 1:1.4, indicating that the programme saved about one life per 1-2 women with epidemiologic over-diagnosis. The benefit-detriment ratio estimates of the Norwegian Breast Cancer Screening Program, expressed as lives saved from breast cancer death and epidemiologic over-diagnosis, should be interpreted with care due to substantial uncertainties in the estimates, and the differences in the scale of values of the events compared. © The Author(s) 2016.
Code of Federal Regulations, 2010 CFR
2010-10-01
... biennial fishing period's open access allocation. (B) [Reserved] (f) Catch accounting. Catch accounting... allocations in a given biennial cycle, catch of those species are counted against the limited entry/open... fisheries—(i) Catch accounting for the trawl allocation. Any groundfish caught by a vessel registered to a...
Enhanced biennial variability in the Pacific due to Atlantic capacitor effect.
Wang, Lei; Yu, Jin-Yi; Paek, Houk
2017-03-20
The El Niño-Southern Oscillation (ENSO) and the variability in the Pacific subtropical highs (PSHs) have major impacts on social and ecological systems. Here we present an Atlantic capacitor effect mechanism to suggest that the Atlantic is a key pacemaker of the biennial variability in the Pacific including that in ENSO and the PSHs during recent decades. The 'charging' (that is, ENSO imprinting the North Tropical Atlantic (NTA) sea surface temperature (SST) via an atmospheric bridge mechanism) and 'discharging' (that is, the NTA SST triggering the following ENSO via a subtropical teleconnection mechanism) processes alternate, generating the biennial rhythmic changes in the Pacific. Since the early 1990s, a warmer Atlantic due to the positive phase of Atlantic multidecadal oscillation and global warming trend has provided more favourable background state for the Atlantic capacitor effect, giving rise to enhanced biennial variability in the Pacific that may increase the occurrence frequency of severe natural hazard events.
Enhanced biennial variability in the Pacific due to Atlantic capacitor effect
Wang, Lei; Yu, Jin-Yi; Paek, Houk
2017-01-01
The El Niño-Southern Oscillation (ENSO) and the variability in the Pacific subtropical highs (PSHs) have major impacts on social and ecological systems. Here we present an Atlantic capacitor effect mechanism to suggest that the Atlantic is a key pacemaker of the biennial variability in the Pacific including that in ENSO and the PSHs during recent decades. The ‘charging' (that is, ENSO imprinting the North Tropical Atlantic (NTA) sea surface temperature (SST) via an atmospheric bridge mechanism) and ‘discharging' (that is, the NTA SST triggering the following ENSO via a subtropical teleconnection mechanism) processes alternate, generating the biennial rhythmic changes in the Pacific. Since the early 1990s, a warmer Atlantic due to the positive phase of Atlantic multidecadal oscillation and global warming trend has provided more favourable background state for the Atlantic capacitor effect, giving rise to enhanced biennial variability in the Pacific that may increase the occurrence frequency of severe natural hazard events. PMID:28317857
Enhanced biennial variability in the Pacific due to Atlantic capacitor effect
NASA Astrophysics Data System (ADS)
Wang, Lei; Yu, Jin-Yi; Paek, Houk
2017-03-01
The El Niño-Southern Oscillation (ENSO) and the variability in the Pacific subtropical highs (PSHs) have major impacts on social and ecological systems. Here we present an Atlantic capacitor effect mechanism to suggest that the Atlantic is a key pacemaker of the biennial variability in the Pacific including that in ENSO and the PSHs during recent decades. The `charging' (that is, ENSO imprinting the North Tropical Atlantic (NTA) sea surface temperature (SST) via an atmospheric bridge mechanism) and `discharging' (that is, the NTA SST triggering the following ENSO via a subtropical teleconnection mechanism) processes alternate, generating the biennial rhythmic changes in the Pacific. Since the early 1990s, a warmer Atlantic due to the positive phase of Atlantic multidecadal oscillation and global warming trend has provided more favourable background state for the Atlantic capacitor effect, giving rise to enhanced biennial variability in the Pacific that may increase the occurrence frequency of severe natural hazard events.
Wynoochee Hydropower/Fish Hatchery: Feasibility Report and Environmental Impact Statement.
1982-09-30
Unresolved Issues. There are no unresolved issues associated with the Wynoochee hydropower/fish hatchery plan. 4. Relationship to Environmental...Requirements.l/ The relationship of the Wynoochee hydropower/fish hatchery plan to environmental requirements is summarized in the following table...Implementation of the plan would I/The relationship of the satellite fish station to the environmental requirements is not included in this discussion. Compliance
The influence of climate change on Tanzania's hydropower sustainability
NASA Astrophysics Data System (ADS)
Sperna Weiland, Frederiek; Boehlert, Brent; Meijer, Karen; Schellekens, Jaap; Magnell, Jan-Petter; Helbrink, Jakob; Kassana, Leonard; Liden, Rikard
2015-04-01
Economic costs induced by current climate variability are large for Tanzania and may further increase due to future climate change. The Tanzanian National Climate Change Strategy addressed the need for stabilization of hydropower generation and strengthening of water resources management. Increased hydropower generation can contribute to sustainable use of energy resources and stabilization of the national electricity grid. To support Tanzania the World Bank financed this study in which the impact of climate change on the water resources and related hydropower generation capacity of Tanzania is assessed. To this end an ensemble of 78 GCM projections from both the CMIP3 and CMIP5 datasets was bias-corrected and down-scaled to 0.5 degrees resolution following the BCSD technique using the Princeton Global Meteorological Forcing Dataset as a reference. To quantify the hydrological impacts of climate change by 2035 the global hydrological model PCR-GLOBWB was set-up for Tanzania at a resolution of 3 minutes and run with all 78 GCM datasets. From the full set of projections a probable (median) and worst case scenario (95th percentile) were selected based upon (1) the country average Climate Moisture Index and (2) discharge statistics of relevance to hydropower generation. Although precipitation from the Princeton dataset shows deviations from local station measurements and the global hydrological model does not perfectly reproduce local scale hydrographs, the main discharge characteristics and precipitation patterns are represented well. The modeled natural river flows were adjusted for water demand and irrigation within the water resources model RIBASIM (both historical values and future scenarios). Potential hydropower capacity was assessed with the power market simulation model PoMo-C that considers both reservoir inflows obtained from RIBASIM and overall electricity generation costs. Results of the study show that climate change is unlikely to negatively affect the average potential of future hydropower production; it will likely make hydropower more profitable. Yet, the uncertainty in climate change projections remains large and risks are significant, adaptation strategies should ideally consider a worst case scenario to ensure robust power generation. Overall a diversified power generation portfolio, anchored in hydropower and supported by other renewables and fossil fuel-based energy sources, is the best solution for Tanzania
NASA Astrophysics Data System (ADS)
Castelletti, A.; Schmitt, R. J. P.; Bizzi, S.; Kondolf, G. M.
2017-12-01
Dams are essential to meet growing water and energy demands. While dams cumulatively impact downstream rivers on network-scales, dam development is mostly based on ad-hoc economic and environmental assessments of single dams. Here, we provide evidence that replacing this ad-hoc approach with early strategic planning of entire dam portfolios can greatly reduce conflicts between economic and environmental objectives of dams. In the Mekong Basin (800,000km2), 123 major dam sites (status-quo: 56 built and under construction) could generate 280,000 GWh/yr of hydropower. Cumulatively, dams risk interrupting the basin's sediment dynamics with severe impacts on livelihoods and eco-systems. To evaluate cumulative impacts and benefits of the ad-hoc planned status-quo portfolio, we combine the CASCADE sediment connectivity model with data on hydropower production and sediment trapping at each dam site. We couple CASCADE to a multi-objective genetic algorithm (BORG) identifying a) portfolios resulting in an optimal trade-off between cumulative sediment trapping and hydropower production and b) an optimal development sequence for each portfolio. We perform this analysis first for the pristine basin (i.e., without pre-existing dams) and then starting from the status-quo portfolio, deriving policy recommendations for which dams should be prioritized in the near future. The status-quo portfolio creates a sub-optimal trade-off between hydropower and sediment trapping, exploiting 50 % of the basin's hydro-electric potential and trapping 60 % of the sediment load. Alternative optimal portfolios could have produced equivalent hydropower for 30 % sediment trapping. Imminent development of mega-dams in the lower basin will increase hydropower production by 20 % but increase sediment trapping to >90 %. In contrast, following an optimal development sequence can still increase hydropower by 30 % with limited additional sediment trapping by prioritizing dams in upper parts of the basin. Our findings argue for reconsidering some imminent dam developments in the Mekong. With nearly 3000 dams awaiting development world-wide, results from the Mekong are of global importance, demonstrating that strategic planning and sequencing of dams is instrumental for sustainable development of dams and hydropower.
The quasi-biennial oscillation of 1.7 years in ground level enhancement events
NASA Astrophysics Data System (ADS)
Velasco Herrera, V. M.; Pérez-Peraza, J.; Soon, W.; Márquez-Adame, J. C.
2018-04-01
The so-called Ground Level Enhancement events are sporadic relativistic solar particles measured at ground level by a network of cosmic ray detectors worldwide. These sporadic events are typically assumed to occur by random chance. However, we find that by studying the last 56 ground level enhancement events reported from 1966 through 2014, these events occur preferentially in the positive phase of the quasi-biennial oscillation of 1.7 year periodicity. These discrete ground level enhancement events show that there is another type of solar emission (i.e., wavelike packets) that occurs only in a specific phase of a very particular oscillation. We interpret this empirical result to support that ground level enhancement events are not a result of purely stochastic processes. We used the Morlet wavelet to analyze the phase of each of the periodicities found by the wavelet analyses and local variations of power spectral density in these sporadic events. We found quasi-regular periodicities of 10.4, 6.55, 4.12, 2.9, 1.73, 0.86, 0.61, 0.4 and 0.24 years in ground level enhancements. Although some of these quasi-biennial oscillation periodicities (i.e., oscillations operating between 0.6 and 4 years) may be interpreted as simply harmonics and overtones of the fundamental solar cycle from the underlying sun-spot magnetism phenomenon. The sources of these periodicities are still unclear. Also there is no clear mechanism for the variability of the quasi-biennial oscillation periodicities itself. The quasi-biennial oscillation periodicities are broadly considered to be a variation of solar activity, associated with the solar dynamo process. Also, the intensity of these periodicities is more important around the years of maximum solar activity because the quasi-biennial oscillation periodicities are modulated by the solar cycle where the Sun is more energetically enhanced during activity maxima. To identify the relationships among ground level enhancement, solar, and cosmic rays indices in time-frequency framework, we apply the wavelet coherence analysis. The fingerprints of solar activity and galactic cosmic rays on these phenomena can also be discerned in terms of the prominent quasi-biennial oscillation of about 1.7 years.
Building a Bright Future. The Hydro Research Foundation's Fellowship Program
DOE Office of Scientific and Technical Information (OSTI.GOV)
Vaughn, Brenna; Linke, Deborah M.
The Hydro Fellowship Program (program) began as an experiment to discover whether the hydropower industry could find mechanisms to attract new entrants through conducting relevant research to benefit the industry. This nationwide, new-to-the-world program was started through funding from the Wind and Water Power Technologies Office of the Energy Efficiency and Renewable Energy (EERE) Office of the Department of Energy (DOE). Between 2010-2015, the Hydro Research Foundation (HRF) designed and implemented a program to conduct valuable research and attract new entrants to the hydro workforce. This historic grant has empowered and engaged industry members from 25 organizations by working withmore » 91 students and advisors at 24 universities in 19 states. The work funded answered pressing research needs in the fields of civil, mechanical, environmental, and electrical engineering, as well as law, energy engineering and materials innovation. In terms of number of individuals touched through funding, 148 individuals were supported by this work through direct research, mentorship, oversight of the work, partnerships and the day-to-day program administration. Based on the program results, it is clear that the funding achieved the hoped-for outcomes and has the capacity to draw universities into the orbit of hydropower and continue the conversation about industry research and development needs. The Foundation has fostered unique partnerships at the host universities and has continued to thrive with the support of the universities, advisors, industry and the DOE. The Foundation has demonstrated industry support through mentorships, partnerships, underwriting the costs and articulating the universities’ support through in-kind cost sharing. The Foundation recommends that future work be continued to nurture these graduate level programs using the initial work and improvements in the successor program, the Research Awards Program, while stimulating engagement of academia at the community college level for operations and maintenance workforce development.« less
1992-01-01
3 are severely deteriorated. The concrete deck and supporting wood -pile structure are nearing the end of their life cycle. Both piers are to be...PROPOSED CONSTRUCTION One-story building with concrete foundation walls, load bearing masonry walls, and concrete floors; roof with wood truss framing...concrete building addition; concrete foundation and slab on grade; wood truss roof; 750 KVA. 3 phase transformer; utilities; concrete and storm drain. 11
Federal Register 2010, 2011, 2012, 2013, 2014
2012-06-13
... Committee on the Validation of Alternative Methods (ICCVAM) AGENCY: Division of the National Toxicology... Alternative Toxicological Methods (NICEATM) announces the availability of the Biennial Progress Report 2010-2011: Interagency Coordinating Committee on the Validation of Alternative Methods. The report was...
Federal Register 2010, 2011, 2012, 2013, 2014
2011-10-31
... Coast Groundfish Fishery; Biennial Specifications and Management Measures; Inseason Adjustments AGENCY.... ACTION: Final rule; inseason adjustments to biennial groundfish management measures; request for comments. SUMMARY: This final rule announces inseason changes to management measures in the commercial Pacific Coast...
Federal Register 2010, 2011, 2012, 2013, 2014
2012-08-08
... overfished stocks by remaining within their rebuilding ACLs. Limited Entry (LE) Fixed Gear Fishery Management... Specifications and Management Measures; Inseason Adjustments AGENCY: National Marine Fisheries Service (NMFS... to biennial groundfish management measures. SUMMARY: This final rule announces inseason changes to...
Federal Register 2010, 2011, 2012, 2013, 2014
2012-04-25
... Specifications and Management Measures; Inseason Adjustments AGENCY: National Marine Fisheries Service (NMFS... to biennial groundfish management measures; request for comments. SUMMARY: This final rule announces an inseason change to management measures in the Pacific Coast groundfish fisheries. This action...
Federal Register 2010, 2011, 2012, 2013, 2014
2012-04-17
... Specifications and Management Measures; Inseason Adjustments AGENCY: National Marine Fisheries Service (NMFS... to biennial groundfish management measures; request for comments. SUMMARY: This final rule announces inseason changes to management measures in the Pacific Coast groundfish fisheries. These actions, which are...
Federal Register 2010, 2011, 2012, 2013, 2014
2012-03-01
... Specifications and Management Measures; Inseason Adjustments AGENCY: National Marine Fisheries Service (NMFS... to biennial groundfish management measures; request for comments. SUMMARY: This final rule announces inseason changes to management measures in the Pacific Coast groundfish fisheries. These actions, which are...
Transform: UNESCO-UNEVOC in Action. Biennial Report 2014-2015
ERIC Educational Resources Information Center
UNESCO-UNEVOC International Centre for Technical and Vocational Education and Training, 2016
2016-01-01
The Biennial Report presents a selection of UNESCO-UNEVOC's activities during 2014 and 2015. The activities contributed to UNESCO's sectoral priorities and programmatic objectives and assisted Member States to provide equitable, inclusive and quality education and promote lifelong learning for sustainable development. Importantly, the selected…
High-resolution assessment of global technical and economic hydropower potential
NASA Astrophysics Data System (ADS)
Gernaat, David E. H. J.; Bogaart, Patrick W.; Vuuren, Detlef P. van; Biemans, Hester; Niessink, Robin
2017-10-01
Hydropower is the most important renewable energy source to date, providing over 72% of all renewable electricity globally. Yet, only limited information is available on the global potential supply of hydropower and the associated costs. Here we provide a high-resolution assessment of the technical and economic potential of hydropower at a near-global scale. Using 15"×15" discharge and 3"×3" digital elevation maps, we built virtual hydropower installations at >3.8 million sites across the globe and calculated their potential using cost optimization methods. This way we identified over 60,000 suitable sites, which together represent a remaining global potential of 9.49 PWh yr-1 below US0.50 kWh-1. The largest remaining potential is found in Asia Pacific (39%), South America (25%) and Africa (24%), of which a large part can be produced at low cost (
DOE Office of Scientific and Technical Information (OSTI.GOV)
Witt, Adam M; Smith, Brennan T
Small hydropower plants supply reliable renewable energy to the grid, though few new plants have been developed in the Unites States over the past few decades due to complex environmental challenges and poor project economics. This paper describes the current landscape of small hydropower development, and introduces a new approach to facility design that co-optimizes the extraction of hydroelectric power from a stream with other important environmental functions such as fish, sediment, and recreational passage. The approach considers hydropower facilities as an integrated system of standardized interlocking modules, designed to sustain stream functions, generate power, and interface with the streambed.more » It is hypothesized that this modular eco-design approach, when guided by input from the broader small hydropower stakeholder community, can lead to cost savings across the facility, reduced licensing and approval timelines, and ultimately, to enhanced resiliency through improved environmental performance over the lifetime of the project.« less
Hydropower in the Southeast: Balancing Lakeview and Production Optimization
NASA Astrophysics Data System (ADS)
Engstrom, J.
2017-12-01
Hydropower is the most important source of renewable electricity in Southeastern U.S. However, the region is repeatedly struck by droughts, and there are many conflicting interests in the limited water resource. This study takes a historical perspective and investigates how hydropower production patterns have changed over time, considering both natural drivers and human dimensions. Hydropower production is strongly tied to the natural variability of large-scale atmospheric drivers (teleconnections) as they affect the water availability in the whole river system and partly also the market demand. To balance the water resource between different interests is a complex task, and the conflicting interests vary by basin, sometimes over a relatively small geographic area. Here road networks adjacent to the hydropower reservoirs are used as an indicator of human development and recreational activities. Through a network analysis of the historical development of road networks surrounding the reservoir, the local and regional conflicting interests are identified and the influence on renewable electricity production quantified.
Data-Based Performance Assessments for the DOE Hydropower Advancement Project
DOE Office of Scientific and Technical Information (OSTI.GOV)
March, Patrick; Wolff, Dr. Paul; Smith, Brennan T
2012-01-01
The U. S. Department of Energy s Hydropower Advancement Project (HAP) was initiated to characterize and trend hydropower asset conditions across the U.S.A. s existing hydropower fleet and to identify and evaluate the upgrading opportunities. Although HAP includes both detailed performance assessments and condition assessments of existing hydropower plants, this paper focuses on the performance assessments. Plant performance assessments provide a set of statistics and indices that characterize the historical extent to which each plant has converted the potential energy at a site into electrical energy for the power system. The performance metrics enable benchmarking and trending of performance acrossmore » many projects in a variety contexts (e.g., river systems, power systems, and water availability). During FY2011 and FY2012, assessments will be performed on ten plants, with an additional fifty plants scheduled for FY2013. This paper focuses on the performance assessments completed to date, details the performance assessment process, and describes results from the performance assessments.« less
Bevelhimer, Mark S.; DeRolph, Christopher R.; Schramm, Michael P.
2016-06-06
Uncertainty about environmental mitigation needs at existing and proposed hydropower projects makes it difficult for stakeholders to minimize environmental impacts. Hydropower developers and operators desire tools to better anticipate mitigation requirements, while natural resource managers and regulators need tools to evaluate different mitigation scenarios and order effective mitigation. Here we sought to examine the feasibility of using a suite of multidisciplinary explanatory variables within a spatially explicit modeling framework to fit predictive models for future environmental mitigation requirements at hydropower projects across the conterminous U.S. Using a database comprised of mitigation requirements from more than 300 hydropower project licenses, wemore » were able to successfully fit models for nearly 50 types of environmental mitigation and to apply the predictive models to a set of more than 500 non-powered dams identified as having hydropower potential. The results demonstrate that mitigation requirements have been a result of a range of factors, from biological and hydrological to political and cultural. Furthermore, project developers can use these models to inform cost projections and design considerations, while regulators can use the models to more quickly identify likely environmental issues and potential solutions, hopefully resulting in more timely and more effective decisions on environmental mitigation.« less
DeRolph, Christopher R; Schramm, Michael P; Bevelhimer, Mark S
2016-10-01
Uncertainty about environmental mitigation needs at existing and proposed hydropower projects makes it difficult for stakeholders to minimize environmental impacts. Hydropower developers and operators desire tools to better anticipate mitigation requirements, while natural resource managers and regulators need tools to evaluate different mitigation scenarios and order effective mitigation. Here we sought to examine the feasibility of using a suite of multi-faceted explanatory variables within a spatially explicit modeling framework to fit predictive models for future environmental mitigation requirements at hydropower projects across the conterminous U.S. Using a database comprised of mitigation requirements from more than 300 hydropower project licenses, we were able to successfully fit models for nearly 50 types of environmental mitigation and to apply the predictive models to a set of more than 500 non-powered dams identified as having hydropower potential. The results demonstrate that mitigation requirements are functions of a range of factors, from biophysical to socio-political. Project developers can use these models to inform cost projections and design considerations, while regulators can use the models to more quickly identify likely environmental issues and potential solutions, hopefully resulting in more timely and more effective decisions on environmental mitigation. Copyright © 2016 Elsevier B.V. All rights reserved.
DOE Office of Scientific and Technical Information (OSTI.GOV)
Bevelhimer, Mark S.; DeRolph, Christopher R.; Schramm, Michael P.
Uncertainty about environmental mitigation needs at existing and proposed hydropower projects makes it difficult for stakeholders to minimize environmental impacts. Hydropower developers and operators desire tools to better anticipate mitigation requirements, while natural resource managers and regulators need tools to evaluate different mitigation scenarios and order effective mitigation. Here we sought to examine the feasibility of using a suite of multidisciplinary explanatory variables within a spatially explicit modeling framework to fit predictive models for future environmental mitigation requirements at hydropower projects across the conterminous U.S. Using a database comprised of mitigation requirements from more than 300 hydropower project licenses, wemore » were able to successfully fit models for nearly 50 types of environmental mitigation and to apply the predictive models to a set of more than 500 non-powered dams identified as having hydropower potential. The results demonstrate that mitigation requirements have been a result of a range of factors, from biological and hydrological to political and cultural. Furthermore, project developers can use these models to inform cost projections and design considerations, while regulators can use the models to more quickly identify likely environmental issues and potential solutions, hopefully resulting in more timely and more effective decisions on environmental mitigation.« less
Framing hydropower as green energy: assessing drivers, risks and tensions in the Eastern Himalayas
NASA Astrophysics Data System (ADS)
Ahlers, R.; Budds, J.; Joshi, D.; Merme, V.; Zwarteveen, M.
2015-04-01
The culturally and ecologically diverse region of the Eastern Himalayas is the target of ambitious hydropower development plans. Policy discourses at national and international levels position this development as synergistically positive: it combines the production of clean energy to fuel economic growth at regional and national levels with initiatives to lift poor mountain communities out of poverty. Different from hydropower development in the 20th century in which development agencies and banks were important players, contemporary initiatives importantly rely on the involvement of private actors, with a prominent role of the private finance sector. This implies that hydropower development is not only financially viable but also understood as highly profitable. This paper examines the new development of hydropower in the Eastern Himalayas of Nepal and India. It questions its framing as green energy, interrogates its links with climate change, and examines its potential for investment and capital accumulation. To do this, we also review the evidence on the extent to which its construction and operation may modify existing hydrogeological processes and ecosystems, as well as its impacts on the livelihoods of diverse groups of people that depend on these. The paper concludes that hydropower development in the region is characterized by inherent contentions and uncertainties, refuting the idea that dams constitute development projects whose impacts can be simply predicted, controlled and mitigated. Indeed, in a highly complex geological, ecological, cultural and political context that is widely regarded to be especially vulnerable to the effects of climate change, hydropower as a development strategy makes for a toxic cocktail.
Framing hydropower as green energy: assessing drivers, risks and tensions in the Eastern Himalayas
NASA Astrophysics Data System (ADS)
Ahlers, R.; Budds, J.; Joshi, D.; Merme, V.; Zwarteveen, M.
2014-11-01
The culturally and ecologically diverse region of the Eastern Himalayas is the target of ambitious hydropower development plans. Policy discourses at national and international levels position this development as synergistically positive: it combines the production of clean energy to fuel economic growth at regional and national levels with initiatives to lift poor mountain communities out of poverty. Different from hydropower development in the 20th century in which development agencies and banks were important players, contemporary initiatives importantly rely on the involvement of private actors, with a prominent role of the private finance sector. This implies that hydropower development is not only financially viable but also understood as highly profitable. This paper examines the new development of hydropower in the Eastern Himalaya of Nepal and India. It questions its framing as green energy, interrogates its links with climate change, and examines its potential for investment and capital accumulation. To do this, we also review the evidence on the extent to which its construction and operation may modify existing hydrogeological processes and ecosystems, as well as its impacts on the livelihoods of diverse groups of people that depend on these. The paper concludes that hydropower development in the region is characterised by inherent contentions and uncertainties, refuting the idea that dams constitute development projects whose impacts can be simply predicted, controlled and mitigated. Indeed, in a highly complex geological, ecological, cultural and political context that is widely regarded to be especially vulnerable to the effects of climate change, hydropower as a development strategy makes for a toxic cocktail.
Greenhouse gas emissions of hydropower in the Mekong River Basin
NASA Astrophysics Data System (ADS)
Räsänen, Timo A.; Varis, Olli; Scherer, Laura; Kummu, Matti
2018-03-01
The Mekong River Basin in Southeast Asia is undergoing extensive hydropower development, but the magnitudes of related greenhouse gas emissions (GHG) are not well known. We provide the first screening of GHG emissions of 141 existing and planned reservoirs in the basin, with a focus on atmospheric gross emissions through the reservoir water surface. The emissions were estimated using statistical models that are based on global emission measurements. The hydropower reservoirs (119) were found to have an emission range of 0.2-1994 kg CO2e MWh-1 over a 100 year lifetime with a median of 26 kg CO2e MWh-1. Hydropower reservoirs facilitating irrigation (22) had generally higher emissions reaching over 22 000 kg CO2e MWh-1. The emission fluxes for all reservoirs (141) had a range of 26-1813 000 t CO2e yr-1 over a 100 year lifetime with a median of 28 000 t CO2e yr-1. Altogether, 82% of hydropower reservoirs (119) and 45% of reservoirs also facilitating irrigation (22) have emissions comparable to other renewable energy sources (<190 kg CO2e MWh-1), while the rest have higher emissions equalling even the emission from fossil fuel power plants (>380 kg CO2e MWh-1). These results are tentative and they suggest that hydropower in the Mekong Region cannot be considered categorically as low-emission energy. Instead, the GHG emissions of hydropower should be carefully considered case-by-case together with the other impacts on the natural and social environment.
A New Tool for Environmental and Economic Optimization of Hydropower Operations
NASA Astrophysics Data System (ADS)
Saha, S.; Hayse, J. W.
2012-12-01
As part of a project funded by the U.S. Department of Energy, researchers from Argonne, Oak Ridge, Pacific Northwest, and Sandia National Laboratories collaborated on the development of an integrated toolset to enhance hydropower operational decisions related to economic value and environmental performance. As part of this effort, we developed an analytical approach (Index of River Functionality, IRF) and an associated software tool to evaluate how well discharge regimes achieve ecosystem management goals for hydropower facilities. This approach defines site-specific environmental objectives using relationships between environmental metrics and hydropower-influenced flow characteristics (e.g., discharge or temperature), with consideration given to seasonal timing, duration, and return frequency requirements for the environmental objectives. The IRF approach evaluates the degree to which an operational regime meets each objective and produces a score representing how well that regime meets the overall set of defined objectives. When integrated with other components in the toolset that are used to plan hydropower operations based upon hydrologic forecasts and various constraints on operations, the IRF approach allows an optimal release pattern to be developed based upon tradeoffs between environmental performance and economic value. We tested the toolset prototype to generate a virtual planning operation for a hydropower facility located in the Upper Colorado River basin as a demonstration exercise. We conducted planning as if looking five months into the future using data for the recently concluded 2012 water year. The environmental objectives for this demonstration were related to spawning and nursery habitat for endangered fishes using metrics associated with maintenance of instream habitat and reconnection of the main channel with floodplain wetlands in a representative reach of the river. We also applied existing mandatory operational constraints for the facility during the demonstration. We compared the optimized virtual operation identified by the toolset to actual operations at the facility for the same time period to evaluate implications of the optimized operational regime on power/revenue generation and environmental performance. Argonne National Laboratory's work was part of a larger "Water-Use-Optimization" project supported by the U.S. Department of Energy Office of Energy Efficiency and Renewable Energy, Water Power Program, under Announcement DE-FOA-0000070. The submitted manuscript has been created by UChicago Argonne, LLC, Operator of Argonne National Laboratory ("Argonne"). Argonne, a U.S. Department of Energy Office of Science laboratory, is operated under Contract No. DE-AC02-06CH11357. The U.S. Government retains for itself, and others acting on its behalf, a paid-up nonexclusive, irrevocable worldwide license in said article to reproduce, prepare derivative works, distribute copies to the public, and perform publicly and display publicly, by or on behalf of the Government.
Report of Ninth Biennial Conference on Chemical Education.
ERIC Educational Resources Information Center
Journal of Chemical Education, 1987
1987-01-01
Provides a summary of the events occurring at the Ninth Biennial Conference on Chemical Education, held in Bozeman, Montana, on July 27-August 2, 1986. Contains brief descriptions of sessions on the role of chemists, demonstrations of laboratory experiences, learning chemistry with computers, teacher training, and chemistry for elementary school…
A Historical Analysis of the Biennial Budget Process
1988-04-01
commissioned In April 1974. He received a Master of Arts (MA) in Business Management from Tne University of The Philippines in 1983, and, in 1987, complitcd... tardiness there isn’t any empirical evidence to support this con- tention. To fully understand why biennial budgeting will not solve the first * three
50 CFR 648.56 - Scallop research.
Code of Federal Regulations, 2013 CFR
2013-10-01
... 50 Wildlife and Fisheries 12 2013-10-01 2013-10-01 false Scallop research. 648.56 Section 648.56... Scallop Fishery § 648.56 Scallop research. (a) At least biennially, in association with the biennial... Opportunity (FFO) that identifies research priorities for projects to be conducted by vessels using research...
50 CFR 648.56 - Scallop research.
Code of Federal Regulations, 2011 CFR
2011-10-01
... 50 Wildlife and Fisheries 10 2011-10-01 2011-10-01 false Scallop research. 648.56 Section 648.56... Scallop Fishery § 648.56 Scallop research. (a) At least biennially, in association with the biennial... Opportunity (FFO) that identifies research priorities for projects to be conducted by vessels using research...
50 CFR 648.56 - Scallop research.
Code of Federal Regulations, 2014 CFR
2014-10-01
... 50 Wildlife and Fisheries 12 2014-10-01 2014-10-01 false Scallop research. 648.56 Section 648.56... Scallop Fishery § 648.56 Scallop research. (a) At least biennially, in association with the biennial... Opportunity (FFO) that identifies research priorities for projects to be conducted by vessels using research...
50 CFR 648.56 - Scallop research.
Code of Federal Regulations, 2012 CFR
2012-10-01
... 50 Wildlife and Fisheries 12 2012-10-01 2012-10-01 false Scallop research. 648.56 Section 648.56... Scallop Fishery § 648.56 Scallop research. (a) At least biennially, in association with the biennial... Opportunity (FFO) that identifies research priorities for projects to be conducted by vessels using research...
Working Together for Student Achievement. 6th Biennial Joint Report
ERIC Educational Resources Information Center
Washington State Board of Education, 2016
2016-01-01
The Washington State Board of Education (SBE) and the Professional Educator Standards Board (PESB) submitted this 6th biennial joint report to the Governor, Legislative Education Committees, and Superintendent of Public Instruction. The report outlines the collaborative work of the Boards, highlights accomplishments, and provides goals and…
77 FR 71702 - Possession, Use, and Transfer of Select Agents and Toxins; Biennial Review
Federal Register 2010, 2011, 2012, 2013, 2014
2012-12-04
... of Select Agents and Toxins; Biennial Review AGENCY: Centers for Disease Control and Prevention (CDC... designated certain select agents and toxins as Tier 1 agents. DATES: Effective Date: Effective December 4, 2012. FOR FURTHER INFORMATION CONTACT: Robbin Weyant, Director, Division of Select Agents and Toxins...
Federal Register 2010, 2011, 2012, 2013, 2014
2010-07-26
... DEPARTMENT OF HEALTH AND HUMAN SERVICES Office of the Secretary Seeking Public Comment on Draft National Health Security Strategy Biennial Implementation Plan AGENCY: Department of Health and Human... Interim Implementation Guide for the National Health Security Strategy of the United States of America...
NASA Astrophysics Data System (ADS)
Fujii, M.; Tanabe, S.; Yamada, M.
2014-12-01
Water, food and energy is three sacred treasures that are necessary for human beings. However, recent factors such as population growth and rapid increase in energy consumption have generated conflicting cases between water and energy. For example, there exist conflicts caused by enhanced energy use, such as between hydropower generation and riverine ecosystems and service water, between shale gas and ground water, between geothermal and hot spring water. This study aims to provide quantitative guidelines necessary for capacity building among various stakeholders to minimize water-energy conflicts in enhancing energy use. Among various kinds of renewable energy sources, we target baseload sources, especially focusing on renewable energy of which installation is required socially not only to reduce CO2 and other greenhouse gas emissions but to stimulate local economy. Such renewable energy sources include micro/mini hydropower and geothermal. Three municipalities in Japan, Beppu City, Obama City and Otsuchi Town are selected as primary sites of this study. Based on the calculated potential supply and demand of micro/mini hydropower generation in Beppu City, for example, we estimate the electricity of tens through hundreds of households is covered by installing new micro/mini hydropower generation plants along each river. However, the result is based on the existing infrastructures such as roads and electric lines. This means that more potentials are expected if the local society chooses options that enhance the infrastructures to increase micro/mini hydropower generation plants. In addition, further capacity building in the local society is necessary. In Japan, for example, regulations by the river law and irrigation right restrict new entry by actors to the river. Possible influences to riverine ecosystems in installing new micro/mini hydropower generation plants should also be well taken into account. Deregulation of the existing laws relevant to rivers and further incentives for business owners of micro/mini hydropower generation along with current feed-in tariff are required if our society choose an option to enhance the renewable energy.
NASA Astrophysics Data System (ADS)
Denaro, Simona; Dinh, Quang; Bizzi, Simone; Bernardi, Dario; Pavan, Sara; Castelletti, Andrea; Schippa, Leonardo; Soncini-Sessa, Rodolfo
2013-04-01
Water management through dams and reservoirs is worldwide necessary to support key human-related activities ranging from hydropower production to water allocation, and flood risk mitigation. Reservoir operations are commonly planned in order to maximize these objectives. However reservoirs strongly influence river geomorphic processes causing sediment deficit downstream, altering the flow regime, leading, often, to process of river bed incision: for instance the variations of river cross sections over few years can notably affect hydropower production, flood mitigation, water supply strategies and eco-hydrological processes of the freshwater ecosystem. The river Po (a major Italian river) has experienced severe bed incision in the last decades. For this reason infrastructure stability has been negatively affected, and capacity to derive water decreased, navigation, fishing and tourism are suffering economic damages, not to mention the impact on the environment. Our case study analyzes the management of Isola Serafini hydropower plant located on the main Po river course. The plant has a major impact to the geomorphic river processes downstream, affecting sediment supply, connectivity (stopping sediment upstream the dam) and transport capacity (altering the flow regime). Current operation policy aims at maximizing hydropower production neglecting the effects in term of geomorphic processes. A new improved policy should also consider controlling downstream river bed incision. The aim of this research is to find suitable modeling framework to identify an operating policy for Isola Serafini reservoir able to provide an optimal trade-off between these two conflicting objectives: hydropower production and river bed incision downstream. A multi-objective simulation-based optimization framework is adopted. The operating policy is parameterized as a piecewise linear function and the parameters optimized using an interactive response surface approach. Global and local response surface are comparatively assessed. Preliminary results show that a range of potentially interesting trade-off policies exist able to better control river bed incision downstream without significantly decreasing hydropower production.
NASA Astrophysics Data System (ADS)
Santos, Ana Clara; Schaefli, Bettina; Manso, Pedro; Schleiss, Anton; Portela, Maria Manuela; Rinaldo, Andrea
2015-04-01
In its Energy Strategy 2050, Switzerland is revising its energy perspectives with a strong focus on renewable sources of energy and in particular hydropower. In this context, the Swiss Government funded a number of competence centers for energy research (SCCERs), including one on the Supply of Energy (SCCER-SoE), which develops fundamental research and innovative solutions in geoenergies and hydropower . Hydropower is already the major energy source in Switzerland, corresponding to approximately 55% of the total national electricity production (which was 69 TWh in 2014). The Energy Strategy 2050 foresees at least a net increase by 1.53 TWh/year in average hydrological conditions, in a context were almost all major river systems are already exploited and a straightforward application of recent environmental laws will impact (reduce) current hydropower production. In this contribution, we present the roadmap of the SCCER-SoE and an overview of our strategy to unravel currently non-exploited hydropower potential, in particular in river systems that are already used for hydropower production. The aim is hereby to quantify non-exploited natural flows, unnecessary water spills or storage volume deficits, whilst considering non-conventional approaches to water resources valuation and management. Such a better understanding of the current potential is paramount to justify future scenarios of adaptation of the existing hydropower infrastructure combining the increase of storage capacity with new connections between existing reservoirs, heightening or strengthening existing dams, increasing the operational volume of natural lakes (including new glacier lakes), or by building new dams. Tapping hidden potential shall also require operational changes to benefit from new flow patterns emerging under an evolving climate and in particular in the context of the ongoing glacier retreat. The paper shall present a broad view over the mentioned issues and first conclusions of ongoing research at the country scale.
Hydropower assessment of Bolivia—A multisource satellite data and hydrologic modeling approach
Velpuri, Naga Manohar; Pervez, Shahriar; Cushing, W. Matthew
2016-11-28
This study produced a geospatial database for use in a decision support system by the Bolivian authorities to investigate further development and investment potentials in sustainable hydropower in Bolivia. The study assessed theoretical hydropower of all 1-kilometer (km) stream segments in the country using multisource satellite data and a hydrologic modeling approach. With the assessment covering the 2 million square kilometer (km2) region influencing Bolivia’s drainage network, the potential hydropower figures are based on theoretical yield assuming that the systems generating the power are 100 percent efficient. There are several factors to consider when determining the real-world or technical power potential of a hydropower system, and these factors can vary depending on local conditions. Since this assessment covers a large area, it was necessary to reduce these variables to the two that can be modeled consistently throughout the region, streamflow or discharge, and elevation drop or head. First, the Shuttle Radar Topography Mission high-resolution 30-meter (m) digital elevation model was used to identify stream segments with greater than 10 km2 of upstream drainage. We applied several preconditioning processes to the 30-m digital elevation model to reduce errors and improve the accuracy of stream delineation and head height estimation. A total of 316,500 1-km stream segments were identified and used in this study to assess the total theoretical hydropower potential of Bolivia. Precipitation observations from a total of 463 stations obtained from the Bolivian Servicio Nacional de Meteorología e Hidrología (Bolivian National Meteorology and Hydrology Service) and the Brazilian Agência Nacional de Águas (Brazilian National Water Agency) were used to validate six different gridded precipitation estimates for Bolivia obtained from various sources. Validation results indicated that gridded precipitation estimates from the Tropical Rainfall Measuring Mission (TRMM) reanalysis product (3B43) had the highest accuracies. The coarse-resolution (25-km) TRMM data were disaggregated to 5-km pixels using climatology information obtained from the Climate Hazards Group Infrared Precipitation with Stations dataset. About a 17-percent bias was observed in the disaggregated TRMM estimates, which was corrected using the station observations. The bias-corrected, disaggregated TRMM precipitation estimate was used to compute stream discharge using a regionalization approach. In regionalization approach, required homogeneous regions for Bolivia were derived from precipitation patterns and topographic characteristics using a k-means clustering approach. Using the discharge and head height estimates for each 1-km stream segment, we computed hydropower potential for 316,490 stream segments within Bolivia and that share borders with Bolivia. The total theoretical hydropower potential (TTHP) of these stream segments was found to be 212 gigawatts (GW). Out of this total, 77.4 GW was within protected areas where hydropower projects cannot be developed; hence, the remaining total theoretical hydropower in Bolivia (outside the protected areas) was estimated as 135 GW. Nearly 1,000 1-km stream segments, however, were within the boundaries of existing hydropower projects. The TTHP of these stream segments was nearly 1.4 GW, so the residual TTHP of the streams in Bolivia was estimated as 133 GW. Care should be exercised to understand and interpret the TTHP identified in this study because all the stream segments identified and assessed in this study cannot be harnessed to their full capacity; furthermore, factors such as required environmental flows, efficiency, economics, and feasibility need to be considered to better identify a more real-world hydropower potential. If environmental flow requirements of 20–40 percent are considered, the total theoretical power available reduces by 60–80 percent. In addition, a 0.72 efficiency factor further reduces the estimation by another 28 percent. This study provides the base theoretical hydropower potential for Bolivia, the next step is to identify optimal hydropower plant locations and factor in the principles to appraise a real-world power potential in Bolivia.
2001-05-01
GAO United States General Accounting Office Report to Congressional Requesters May 2001 LICENSING HYDROPOWER PROJECTS Better Time and Cost Data...Dates Covered (from... to) ("DD MON YYYY") Title and Subtitle LICENSING HYDROPOWER PROJECTS: Better Time and Cost Data Needed to Reach Informed...Organization Name(s) and Address(es) General Accounting Office, PO Box 37050, Washington, DC 20013 Performing Organization Number(s) GAO-01-499
DOE Office of Scientific and Technical Information (OSTI.GOV)
Gulliver, John S.
2015-03-01
Conventional hydropower turbine aeration test-bed for computational routines and software tools for improving environmental mitigation technologies for conventional hydropower systems. In achieving this goal, we have partnered with Alstom, a global leader in energy technology development and United States power generation, with additional funding from the Initiative for Renewable Energy and the Environment (IREE) and the College of Science and Engineering (CSE) at the UMN
Study on the adverse effects of hydropower development on international shipping
NASA Astrophysics Data System (ADS)
Wang, Changhong
2017-04-01
The Lancang - Mekong river is an important international waterway to Southeast Asia and South Asia, which has important strategic significance for promoting regional economic cooperation and safeguarding national economic and security interests. On the Mekong River, the main aim is to develop hydropower resources utilization and shipping. River Hydropower Stations are in Laos and designed by foreign enterprises according to the construction of BOT. In this study, on the basis of a lot of research work and extensive collection of relevant information, and, through in-depth analysis of research, it reveals that the upper Mekong River hydropower development have many adverse effects on international shipping, put forward related suggestions for the healthy and sustainable development of international shipping.
Water-Food Nexus on Lancang-Mekong River Basin
NASA Astrophysics Data System (ADS)
Do, P.; Tian, F.; Hu, H.
2017-12-01
Water-Food-Energy nexus on Lancang-Mekong river basin In the Lancang-Mekong river basin, the connexions between climate and the water-food-energy nexus are strong. One of them can be reflected by the hydropower energy and irrigation sectors, impacted since these last years by intense droughts and increasing salinity. The purpose of this study is to understand quantitatively how the current hydropower impact on the streamflow and the irrigated crops will be influenced by the climate change for the next 30 years. A hydropower-crop model is computed to reproduce hydropower generation and revenue, revenue from crop and crop area in 2050. The outcomes will be used for water management in the region and strengthen the cooperation mechanisms between Mekong riparian countries.
The Second Assessment of the Effects of Climate Change on Federal Hydropower
DOE Office of Scientific and Technical Information (OSTI.GOV)
Kao, Shih-Chieh; Ashfaq, Moetasim; Naz, Bibi S.
Hydropower is a key contributor to the US renewable energy portfolio due to its established development history and the diverse benefits it provides to the electric power system. Ensuring the sustainable operation of existing hydropower facilities is of great importance to the US renewable energy portfolio and the reliability of electricity grid. As directed by Congress in Section 9505 of the SECURE Water Act (SWA) of 2009 (Public Law 111-11), the US Department of Energy (DOE), in consultation with the federal Power Marketing Administrations (PMAs) and other federal agencies, has prepared a second quinquennial report on examining the potential effectsmore » of climate change on water available for hydropower at federal facilities and on the marketing of power from these federal facilities. This Oak Ridge National Laboratory (ORNL) Technical Memorandum, referred to as the 9505 assessment, describes the technical basis for the report to Congress that was called for in the SWA. To evaluate the potential climate change effects on 132 federal hydropower plants across the entire US, a spatially consistent assessment approach is designed to enable an interregional comparison. This assessment uses a series of models and methods with different spatial resolutions to gradually downscale the global climate change signals into watershed-scale hydrologic projections to support hydropower impact assessment. A variety of historic meteorological and hydrologic observations, hydropower facility characteristics, and geospatial datasets is collected to support model development, calibration, and verification. Among most of the federal hydropower plants throughout the US, the most important climate change effect on hydrology is likely to be the trend toward earlier snowmelt and change of runoff seasonality. Under the projections of increasing winter/spring runoff and decreasing summer/fall runoff, water resource managers may need to consider different water use allocations. With the relatively large storage capacity in the most of the US federal hydropower reservoirs, the system is likely to be able to absorb part of the runoff variability and hence may continue to provide stable annual hydropower generation in the projected near-term and midterm future periods. Nevertheless, the findings are based on the assumption that there is no significant change in the future installed capacity and operation. The issues of aging infrastructures, competing water demand, and environmental requirements may reduce the system s ability to mitigate runoff variability and increase the difficulty of future operation. These issues are not quantitatively analyzed in this study. This study presents a regional assessment at each of the eighteen PMA study areas. This generalized approach allows for spatial consistency throughout all study areas, enabling policymakers to evaluate potential climate change impacts across the entire federal hydropower fleet. This effort is expected to promote better understanding of the sensitivity of federal power plants to water availability and provides a basis for planning future actions that will enable adaptation to climate variability and change.« less
1989-01-01
determine whether they can predict relationships between solar radio emissions and coronal mass ejections. (U) FY 1990 Planned Program: - (U) Generate...physical relationships of objects. - (U) Continue research on how humans process visual and auditory information and on cognitive functions. (U...duplication within the Air Force or DoD. (U) Other Appropriation Funds: Not Applicable. (U) International Cooperative Agreements: Contractor relationship
Sustainable NREL Biennial Report, FY 2012 - 2013 (Management Report)
DOE Office of Scientific and Technical Information (OSTI.GOV)
Slovensky, Michelle
2014-03-01
NREL's Sustainability Program plays a vital role bridging research and operations - integrating energy efficiency, water and material resource conservation and cultural change - adding depth in the fulfillment of NREL's mission. The report, per the GRI reporting format, elaborates on multi-year goals relative to executive orders, achievements, and challenges; and success stories provide specific examples. A section called "The Voice of NREL" gives an inside perspective of how to become more sustainable while at the same time addressing climate change.
DOE Office of Scientific and Technical Information (OSTI.GOV)
NONE
1996-03-01
The module explains the connection between the Pollution Prevention Act and EPCRA. It details the reporting requirements under the Pollution Prevention Act, Section 6607(b) and lists the items to be included in source reduction reporting under Section 6607(b). It outlines the availability of technical assistance grant programs for states. It describes the information included in EPA`s biennial report to congress.
1989-01-01
size, weight , power consumption, and radiation hardness, and on software algorithm validity and efficiency. 3. (U) Collection of radar, ctical, and...which have potential to achieve cooling requirements for LWIR sensors with far smaller weight and power penalties. (U) FY1989 Planned Program: o (U...two dollars for every SDI dollar. o (U) Inverted gaili--n arsenide by growing a razor-thin layer of silicon on GaAs and thus cut power loss by two
Energy Efficiency and Renewable Energy Program. Bibliography, 1993 edition
DOE Office of Scientific and Technical Information (OSTI.GOV)
Vaughan, K.H.
1993-06-01
The Bibliography contains listings of publicly available reports, journal articles, and published conference papers sponsored by the DOE Office of Energy Efficiency and Renewable Energy and published between 1987 and mid-1993. The topics of Bibliography include: analysis and evaluation; building equipment research; building thermal envelope systems and materials; district heating; residential and commercial conservation program; weatherization assistance program; existing buildings research program; ceramic technology project; alternative fuels and propulsion technology; microemulsion fuels; industrial chemical heat pumps; materials for advanced industrial heat exchangers; advanced industrial materials; tribology; energy-related inventions program; electric energy systems; superconducting technology program for electric energy systems; thermalmore » energy storage; biofuels feedstock development; biotechnology; continuous chromatography in multicomponent separations; sensors for electrolytic cells; hydropower environmental mitigation; environmental control technology; continuous fiber ceramic composite technology.« less
Army Management Views: Report of the 4th Biennial Management Instructors' Seminar July 21-26, 1968.
ERIC Educational Resources Information Center
Hancock, Chester H.; And Others
The report of the Fourth Biennial Management Instructors' Seminar (July 21-26, 1968) which deals with the improvement of management education in the Army, contains presentations of guest speakers and reports of seminar workshops. The former presents the components of management -- planning, decision-making, productivity, communication, and…
Responses of groundcover under longleaf pine to biennial seasonal burning and hardwood control
William D. Boyer
1995-01-01
Abstract.Responses of understory vegetation to season of bum were followed in young, naturally established, stands of longleaf pine (Pinus palustris Mill.). Treatments included biennial burns in winter, spring, and summer, plus a no-bum check. Groundcover biomass was measured before treatment and again 7 and 9 years later. Total...
This Special Issue contains a collection of papers presented at The Ecological Modelling Global Conference 2016: 20th Biennial International Society of Ecological Modelling (ISEM) Conference which was held at Towson University, Maryland, United States. Over the past 40+ years, E...
USDA-ARS?s Scientific Manuscript database
The Nineteenth Biennial Workshop of the International Plant Resistance to Insects (IPRI) was held 28-31 March, 2010 in Charleston, SC. This workshop was attended by 71 participants from six countries. There were 17 symposium papers, 22 submitted papers, 9 student competition papers, and 21 posters...
Federal Register 2010, 2011, 2012, 2013, 2014
2012-08-03
...] National Poultry Improvement Plan; General Conference Committee Meeting and 41st Biennial Conference AGENCY... notice of a meeting of the General Conference Committee of the National Poultry Improvement Plan (NPIP... CONTACT: Dr. C. Stephen Roney, Senior Coordinator, National Poultry Improvement Plan, VS, APHIS, 1506...
Advances in berry research: the sixth biennial berry health benefits symposium
USDA-ARS?s Scientific Manuscript database
Studies to advance the potential health benefits of berries continue to increase as was evident at the sixth biennial meeting of the Berry Health Benefits Symposium (BHBS). The two and a half-day symposium was held on October 13-15, 2015, in Madison, Wisconsin, United States. The 2015 BHBS feature...
NASA Astrophysics Data System (ADS)
Anghileri, Daniela; Castelletti, Andrea; Burlando, Paolo
2015-04-01
Alpine hydropower systems are an important source of renewable energy for many countries in Europe. In Switzerland, for instance, they represent the most important domestic source of renewable energy (around 55%). However, future hydropower production may be threatened by unprecedented challenges, such as a decreasing water availability, due to climate change (CC) and associated glacier retreat, and uncertain operating conditions, such as future power needs and highly fluctuating demand on the energy market. This second aspect has gained increasingly relevance since the massive introduction of solar and wind generating systems in the portfolios of many European countries. Because hydropower systems have the potential to provide backup storage of energy to compensate for fluctuations that are typical, for instance, of solar and wind generation systems, it is important to investigate how the increased demand for flexible operation, together with climate change challenge and fluctuating markets, can impact their operating policies. The Swiss Competence Center on Supply of Electricity (www.sccer-soe.ch) has been recently established to explore new potential paths for the development of future power generation systems. In this context, we develop modelling and optimization tools to design and assess new operation strategies for hydropower systems to increase their reliability, flexibility, and robustness to future operation conditions. In particular, we develop an advanced modelling framework for the integrated simulation of the operation of hydropower plants, which accounts for CC-altered streamflow regimes, new demand and market conditions, as well as new boundary conditions for operation (e.g., aquatic ecosystem conservation). The model construction consists of two primary components: a physically based and spatially distributed hydrological model, which describes the relevant hydrological processes at the basin scale, and an agent based decision model, which describes the behavior of hydropower operators. This integrated model allows to quantitatively explore possible trajectories of future evolution of the hydropower systems under the combined effect of climate and socio-economic drivers. In a multi-objective perspective, the model can test how different hydropower operation strategies perform in terms of power production, reliability and flexibility of supply, profitability of operation, and ecosystem conservation. This contribution presents the methodological framework designed to formulate the integrated model, its expected outcomes, and some preliminary results on a pilot study.
The Economic Benefits Of Multipurpose Reservoirs In The United States- Federal Hydropower Fleet
DOE Office of Scientific and Technical Information (OSTI.GOV)
Hadjerioua, Boualem; Witt, Adam M.; Stewart, Kevin M.
The United States is home to over 80,000 dams, of which approximately 3% are equipped with hydroelectric generating capabilities. When a dam serves as a hydropower facility, it provides a variety of energy services that range from clean, reliable power generation to load balancing that supports grid stability. In most cases, the benefits of dams and their associated reservoirs go far beyond supporting the nation s energy demand. As evidenced by the substantial presence of non-powered dams with the ability to store water in large capacities, the primary purpose of a dam may not be hydropower, but rather one ofmore » many other purposes. A dam and reservoir may support navigation, recreation, flood control, irrigation, and water supply, with each multipurpose benefit providing significant social and economic impacts on a local, regional, and national level. When hydropower is one of the services provided by a multipurpose reservoir, it is then part of an integrated system of competing uses. Operating rules, management practices, consumer demands, and environmental constraints must all be balanced to meet the multipurpose project s objectives. When federal dams are built, they are authorized by Congress to serve one or more functions. Legislation such as the Water Resources Development Act regulates the operation of the facility in order to coordinate the authorized uses and ensure the dam s intended objectives are being met. While multipurpose reservoirs account for billions of dollars in contributions to National Economic Development (NED) every year, no attempt has been made to evaluate their benefits on a national scale. This study is an on-going work conducted by Oak Ridge National Laboratory in an effort to estimate the economic benefits of multipurpose hydropower reservoirs in the United States. Given the important role that federal hydropower plays in the U.S., the first focus of this research will target the three main federal hydropower owners Tennessee Valley Authority, U.S. Army Corps of Engineers, and U.S. Bureau of Reclamation. Together these three agencies own and operate 157 powered dams which account for almost half of the total installed hydropower capacity in the U.S. Future work will include engaging publicly-owned utilities and the private sector in order to quantify the benefits of all multipurpose hydropower reservoirs in the U.S.« less
Economic implications of climate-driven trends in global hydropower generation
NASA Astrophysics Data System (ADS)
Turner, S. W. D.; Galelli, S.; Hejazi, M. I.; Clarke, L.; Edmonds, J.; Kim, S. H.
2017-12-01
Recent progress in global scale hydrological and dam modeling has allowed for the study of climate change impacts on global hydropower production. Here we explore how these impacts could affect the composition of global electricity supply, and what those changes could mean for power sector emissions and investment needs in the 21st century. Regional hydropower projections are developed for two emissions scenarios by forcing a coupled global hydrological and dam model (1593 major hydropower dams; 54% global installed capacity) with downscaled, bias-corrected climate realizations derived from sixteen General Circulation Models (GCMs). To incorporate possible non-linearity in hydropower response to climate change, dam simulations incorporate plant specifications (e.g., maximum turbine flow), reservoir storage dynamics, reservoir bathymetry, evaporation losses and bespoke, site specific operations. Consequent impacts on regional and global-level electricity generation and associated emissions and investment costs are examined using the Global Change Assessment Model (GCAM). We show that changes in hydropower generation resulting from climate change can shift power demands onto and away from carbon intensive technologies, resulting in significant impacts on CO2 emissions for several regions. Many of these countries are also highly vulnerable to investment impacts (costs of new electricity generating facilities to make up for shortfalls in hydro), which in some cases amount to tens of billions of dollars by 2100. The Balkans region—typified by weak economies in a drying region that relies heavily on hydropower—emerges as the most vulnerable. Reduced impacts of climate change on hydropower production under a low emissions scenario coincide with increased costs of marginal power generating capacity (low emissions requires greater uptake of clean generating technologies, which are more expensive). This means impacts on power sector investment costs are similar for high and low emissions scenarios.
NASA Astrophysics Data System (ADS)
Levy, M. C.; Thompson, S. E.; Cohn, A.
2014-12-01
Land use/cover change (LUCC) has occurred extensively in the Brazilian Amazon rainforest-savanna transition. Agricultural development-driven LUCC at regional scales can alter surface energy budgets, evapotranspiration (ET) and rainfall; these hydroclimatic changes impact streamflows, and thus hydropower. To date, there is only limited empirical understanding of these complex land-water-energy nexus dynamics, yet understanding is important to developing countries where both agriculture and hydropower are expanding and intensifying. To observe these changes and their interconnections, we synthesize a novel combination of ground network, remotely sensed, and empirically modeled data for LUCC, rainfall, flows, and hydropower potential. We connect the extensive temporal and spatial trends in LUCC occurring from 2000-2012 (and thus observable in the satellite record) to long-term historical flow records and run-of-river hydropower generation potential estimates. Changes in hydrologic condition are observed in terms of dry and wet season moments, extremes, and flow duration curves. Run-of-river hydropower generation potential is modeled at basin gauge points using equation models parameterized with literature-based low-head turbine efficiencies, and simple algorithms establishing optimal head and capacity from elevation and flows, respectively. Regression analyses are used to demonstrate a preliminary causal analysis of LUCC impacts to flow and energy, and discuss extension of the analysis to ungauged basins. The results are transferable to tropical and transitional forest regions worldwide where simultaneous agricultural and hydropower development potentially compete for coupled components of regional water cycles, and where policy makers and planners require an understanding of LUCC impacts to hydroclimate-dependent industries and ecosystems.
Alpine hydropower in a low carbon economy: Assessing the local implication of global policies
NASA Astrophysics Data System (ADS)
Anghileri, Daniela; Castelletti, Andrea; Burlando, Paolo
2016-04-01
In the global transition towards a more efficient and low-carbon economy, renewable energy plays a major role in displacing fossil fuels, meeting global energy demand while reducing carbon dioxide emissions. In Europe, Variable Renewable Sources (VRS), such as wind and solar power sources, are becoming a relevant share of the generation portfolios in many countries. Beside the indisputable social and environmental advantages of VRS, on the short medium term the VRS-induced lowering energy prices and increasing price's volatility might challenge traditional power sources and, among them, hydropower production, because of smaller incomes and higher maintenance costs associated to a more flexible operation of power systems. In this study, we focus on the Swiss hydropower sector analysing how different low-carbon targets and strategies established at the Swiss and European level might affect energy price formation and thus impact - through hydropower operation - water availability and ecosystems services at the catchment scale. We combine a hydrological model to simulate future water availability and an electricity market model to simulate future evolution of energy prices based on official Swiss and European energy roadmaps and CO2 price trends in the European Union. We use Multi-Objective optimization techniques to design alternative hydropower reservoir operation strategies, aiming to maximise the hydropower companies' income or to provide reliable energy supply with respect to the energy demand. This integrated model allows analysing to which extent global low-carbon policies impact reservoir operation at the local scale, and to gain insight on how to prioritise compensation measures and/or adaptation strategies to mitigate the impact of VRS on hydropower companies in increasingly water constrained settings. Numerical results are shown for a real-world case study in the Swiss Alps.
Water, energy and agricultural landuse trends at Shiroro hydropower station and environs
NASA Astrophysics Data System (ADS)
Adegun, Olubunmi; Ajayi, Olalekan; Badru, Gbolahan; Odunuga, Shakirudeen
2018-02-01
The study examines the interplay among water resources, hydropower generation and agricultural landuse at the Shiroro hydropower station and its environs, in north-central Nigeria. Non-parametric trend analysis, hydropower footprint estimation, reservoir performance analysis, change detection analysis, and inferential statistics were combined to study the water-energy and food security nexus. Results of Mann-Kendall test and Sen's slope estimator for the period 1960 to 2013 showed a declining rainfall trend at Jos, around River Kaduna headwaters at -2.6 mm yr-1, while rainfall at Kaduna and Minna upstream and downstream of the reservoir respectively showed no trend. Estimates of hydropower footprint varied between 130.4 and 704.1 m3 GJ-1 between 1995 and 2013. Power generation reliability and resilience of the reservoir was 31.6 and 38.5 % respectively with year 2011 being the most vulnerable and least satisfactory. In addition to poor reliability and resilience indices, other challenges militating against good performance of hydropower generation includes population growth and climate change issues as exemplified in the downward trend observed at the headwaters. Water inflow and power generation shows a weak positive relationship with correlation coefficient (r) of 0.48, indicating less than optimal power generation. Total area of land cultivated increased from 884.59 km2 in 1986 prior to the commissioning of the hydropower station to 1730.83 km2 in 2016 which signifies an increased contribution of the dam to ensuring food security. The reality of reducing upstream rainfall amount coupled with high water footprint of electricity from the reservoir, therefore requires that a long term roadmap to improve operational coordination and management have to be put in place.
NASA Astrophysics Data System (ADS)
Si, Y.; Li, X.; Li, T.; Huang, Y.; Yin, D.
2016-12-01
The cascade reservoirs in Upper Yellow River (UYR), one of the largest hydropower bases in China, play a vital role in peak load and frequency regulation for Northwest China Power Grid. The joint operation of this system has been put forward for years whereas has not come into effect due to management difficulties and inflow uncertainties, and thus there is still considerable improvement room for hydropower production. This study presents a decision support framework incorporating long- and short-term operation of the reservoir system. For long-term operation, we maximize hydropower production of the reservoir system using historical hydrological data of multiple years, and derive operating rule curves for storage reservoirs. For short-term operation, we develop a program consisting of three modules, namely hydrologic forecast module, reservoir operation module and coordination module. The coordination module is responsible for calling the hydrologic forecast module to acquire predicted inflow within a short-term horizon, and transferring the information to the reservoir operation module to generate optimal release decision. With the hydrologic forecast information updated, the rolling short-term optimization is iterated until the end of operation period, where the long-term operating curves serve as the ending storage target. As an application, the Digital Yellow River Integrated Model (referred to as "DYRIM", which is specially designed for runoff-sediment simulation in the Yellow River basin by Tsinghua University) is used in the hydrologic forecast module, and the successive linear programming (SLP) in the reservoir operation module. The application in the reservoir system of UYR demonstrates that the framework can effectively support real-time decision making, and ensure both computational accuracy and speed. Furthermore, it is worth noting that the general framework can be extended to any other reservoir system with any or combination of hydrological model(s) to forecast and any solver to optimize the operation of reservoir system.
NASA Astrophysics Data System (ADS)
Morales, Y.; Olivares, M. A.; Vargas, X.
2015-12-01
This research aims to improve the representation of stochastic water inflows to hydropower plants used in a grid-wide, power production scheduling model in central Chile. The model prescribes the operation of every plant in the system, including hydropower plants located in several basins, and uses stochastic dual dynamic programming (SDDP) with possible inflow scenarios defined from historical records. Each year of record is treated as a sample of weekly inflows to power plants, assuming this intrinsically incorporates spatial and temporal correlations, without any further autocorrelation analysis of the hydrological time series. However, standard good practice suggests the use of synthetic flows instead of raw historical records.The proposed approach generates synthetic inflow scenarios based on hydrological modeling of a few basins in the system and transposition of flows with other basins within so-called homogeneous zones. Hydrologic models use precipitation and temperature as inputs, and therefore this approach requires producing samples of those variables. Development and calibration of these models imply a greater demand of time compared to the purely statistical approach to synthetic flows. This approach requires consideration of the main uses in the basins: agriculture and hydroelectricity. Moreover a geostatistical analysis of the area is analyzed to generate a map that identifies the relationship between the points where the hydrological information is generated and other points of interest within the power system. Consideration of homogeneous zones involves a decrease in the effort required for generation of information compared with hydrological modeling of every point of interest. It is important to emphasize that future scenarios are derived through a probabilistic approach that incorporates the features of the hydrological year type (dry, normal or wet), covering the different possibilities in terms of availability of water resources. We present the results for Maule basin in Chile's Central Interconnected System (SIC).
Report to the International Global Atmospheric Chemistry Project
DOE Office of Scientific and Technical Information (OSTI.GOV)
Reisdorf, Jill; Wiedinmyer, Christine
IGAC’s mission is to facilitate atmospheric chemistry research towards a sustainable world. This is achieved through IGAC’s three focal activities: fostering community, building capacity, and providing leadership. A key component to achieving IGAC’s mission is its developing early career program. These scientists join an international network early in their career that puts the cogs in motion to further facilitate atmospheric chemistry research at an international level for years to come. IGAC’s Science Conference is a primary mechanism for IGAC to build cooperation and disseminate scientific information across its international community. The first IGAC Science Conference was held in 1993 in Eilat,more » Israel. Since then, IGAC has successfully held fourteen science conferences, consistently becoming a biennial conference starting in 2002. The biennial IGAC Science Conference is regarded as THE international conference on atmospheric chemistry and participation in the conference is typically in the range of 350-650 participants. Since 2004, IGAC has included an Early Career Scientists Program as part of the conference to foster the next generation of scientists. IGAC believes, and has seen, that by allowing scientists to form an international network of colleagues early in their career that future international collaborations in atmospheric chemistry are enhanced. The 2016 IGAC Science Conference Early Career Program consisted of numerous events throughout the week giving these scientists the opportunity to not only create a community amongst themselves, but to also engage and build relationships with senior scientists. In order to support the Early Career Scientists Program, IGAC sought funding from international, regional and local organizations to provide Travel Grants to the conference based on an assessment of both need and merit. This conference summary reports on outcomes of the 2016 IGAC Science Conference and the Early Career Program, which included early career travel grants funded by this DOE grant.« less
Climate change impacts on high-elevation hydroelectricity in California
NASA Astrophysics Data System (ADS)
Madani, Kaveh; Guégan, Marion; Uvo, Cintia B.
2014-03-01
While only about 30% of California's usable water storage capacity lies at higher elevations, high-elevation (above 300 m) hydropower units generate, on average, 74% of California's in-state hydroelectricity. In general, high-elevation plants have small man-made reservoirs and rely mainly on snowpack. Their low built-in storage capacity is a concern with regard to climate warming. Snowmelt is expected to shift to earlier in the year, and the system may not be able to store sufficient water for release in high-demand periods. Previous studies have explored the climate warming effects on California's high-elevation hydropower by focusing on the supply side (exploring the effects of hydrological changes on generation and revenues) ignoring the warming effects on hydroelectricity demand and pricing. This study extends the previous work by simultaneous consideration of climate change effects on high-elevation hydropower supply and pricing in California. The California's Energy-Based Hydropower Optimization Model (EBHOM 2.0) is applied to evaluate the adaptability of California's high-elevation hydropower system to climate warming, considering the warming effects on hydroelectricity supply and pricing. The model's results relative to energy generation, energy spills, reservoir energy storage, and average shadow prices of energy generation and storage capacity expansion are examined and discussed. These results are compared with previous studies to emphasize the need to consider climate change effects on hydroelectricity demand and pricing when exploring the effects of climate change on hydropower operations.
Value of ecosystem hydropower service and its impact on the payment for ecosystem services.
Fu, B; Wang, Y K; Xu, P; Yan, K; Li, M
2014-02-15
Hydropower is an important service provided by ecosystems. We surveyed all the hydropower plants in the Zagunao River Basin, Southwest China. Then, we assessed the hydropower service by using the InVEST (The Integrated Value and Tradeoff of Ecosystem Service Tools) model. Finally, we discussed the impact on ecological compensation. The results showed that: 1) hydropower service value of ecosystems in the Zagunao River Basin is 216.29 Euro/hm(2) on the average, of which the high-value area with more than 475.65 Euro/hm(2) is about 750.37 km(2), accounting for 16.12% of the whole watershed, but it provides 53.47% of the whole watershed service value; 2) ecosystem is an ecological reservoir with a great regulation capacity. Dams cannot completely replace the reservoir water conservation function of ecosystems, and has high economic and environmental costs that must be paid as well. Compensation for water conservation services should become an important basis for ecological compensation of hydropower development. 3) In the current PES cases, the standard of compensation is generally low. Cascade development makes the value of upstream ecosystem services become more prominent, reflecting the differential rent value, and the value of ecosystem services should be based on the distribution of differentiated ecological compensation. Copyright © 2013 Elsevier B.V. All rights reserved.
Water resources management. World Bank policy study; Ordenacion de los recursos hidricos
DOE Office of Scientific and Technical Information (OSTI.GOV)
NONE
1994-12-31
This study examines new World Bank policies that deal with scarce water resources in developing countries. The study describes key policy goals that each country program should adopt. Practical ways to modernize irrigation techniques and hydropower systems, to protect ecosystems, minimize resettlement, and maintain biodiversity are outlined. Low-cost methods of providing drinking water for the rural poor and water for industry and agriculture are recommended.
Mandelblatt, Jeanne S; Stout, Natasha K; Schechter, Clyde B; van den Broek, Jeroen J; Miglioretti, Diana L; Krapcho, Martin; Trentham-Dietz, Amy; Munoz, Diego; Lee, Sandra J; Berry, Donald A; van Ravesteyn, Nicolien T; Alagoz, Oguzhan; Kerlikowske, Karla; Tosteson, Anna N A; Near, Aimee M; Hoeffken, Amanda; Chang, Yaojen; Heijnsdijk, Eveline A; Chisholm, Gary; Huang, Xuelin; Huang, Hui; Ergun, Mehmet Ali; Gangnon, Ronald; Sprague, Brian L; Plevritis, Sylvia; Feuer, Eric; de Koning, Harry J; Cronin, Kathleen A
2016-02-16
Controversy persists about optimal mammography screening strategies. To evaluate screening outcomes, taking into account advances in mammography and treatment of breast cancer. Collaboration of 6 simulation models using national data on incidence, digital mammography performance, treatment effects, and other-cause mortality. United States. Average-risk U.S. female population and subgroups with varying risk, breast density, or comorbidity. Eight strategies differing by age at which screening starts (40, 45, or 50 years) and screening interval (annual, biennial, and hybrid [annual for women in their 40s and biennial thereafter]). All strategies assumed 100% adherence and stopped at age 74 years. Benefits (breast cancer-specific mortality reduction, breast cancer deaths averted, life-years, and quality-adjusted life-years); number of mammograms used; harms (false-positive results, benign biopsies, and overdiagnosis); and ratios of harms (or use) and benefits (efficiency) per 1000 screens. Biennial strategies were consistently the most efficient for average-risk women. Biennial screening from age 50 to 74 years avoided a median of 7 breast cancer deaths versus no screening; annual screening from age 40 to 74 years avoided an additional 3 deaths, but yielded 1988 more false-positive results and 11 more overdiagnoses per 1000 women screened. Annual screening from age 50 to 74 years was inefficient (similar benefits, but more harms than other strategies). For groups with a 2- to 4-fold increased risk, annual screening from age 40 years had similar harms and benefits as screening average-risk women biennially from 50 to 74 years. For groups with moderate or severe comorbidity, screening could stop at age 66 to 68 years. Other imaging technologies, polygenic risk, and nonadherence were not considered. Biennial screening for breast cancer is efficient for average-risk populations. Decisions about starting ages and intervals will depend on population characteristics and the decision makers' weight given to the harms and benefits of screening. National Institutes of Health.
Mandelblatt, Jeanne S.; Stout, Natasha K.; Schechter, Clyde B.; van den Broek, Jeroen J.; Miglioretti, Diana; Krapcho, Martin; Trentham-Dietz, Amy; Munoz, Diego; Lee, Sandra J.; Berry, Donald A.; van Ravesteyn, Nicolien T.; Alagoz, Oguzhan; Kerlikowske, Karla; Tosteson, Anna N.A.; Near, Aimee M.; Hoeffken, Amanda; Chang, Yaojen; Heijnsdijk, Eveline A.; Chisholm, Gary; Huang, Xuelin; Huang, Hui; Ergun, Mehmet Ali; Gangnon, Ronald; Sprague, Brian L.; Plevritis, Sylvia; Feuer, Eric; de Koning, Harry J.; Cronin, Kathleen A.
2016-01-01
Background Controversy persists about optimal mammography screening strategies. Objective To evaluate mammography strategies considering screening and treatment advances. Design Collaboration of six simulation models. Data Sources National data on incidence, risk, breast density, digital mammography performance, treatment effects, and other-cause mortality. Target Population An average-risk cohort. Time Horizon Lifetime. Perspective Societal. Interventions Mammograms from age 40, 45 or 50 to 74 at annual or biennial intervals, or annually from 40 or 45 to 49 then biennially to 74, assuming 100% screening and treatment adherence. Outcome Measures Screening benefits (vs. no screening) include percent breast cancer mortality reduction, deaths averted, and life-years gained. Harms include number of mammograms, false-positives, benign biopsies, and overdiagnosis. Results for Average-Risk Women Biennial strategies maintain 79.8%-81.3% (range across strategies and models: 68.3–98.9%) of annual screening benefits with almost half the false-positives and fewer overdiagnoses. Screening biennially from ages 50–74 achieves a median 25.8% (range: 24.1%-31.8%) breast cancer mortality reduction; annual screening from ages 40–74 years reduces mortality an additional 12.0% (range: 5.7%-17.2%) vs. no screening, but yields 1988 more false-positives and 7 more overdiagnoses per 1000 women screened. Annual screening from ages 50–74 had similar benefits as other strategies but more harms, so would not be recommended. Sub-population Results Annual screening starting at age 40 for women who have a two- to four-fold increase in risk has a similar balance of harms and benefits as biennial screening of average-risk women from 50–74. Limitations We do not consider other imaging technologies, polygenic risk, or non-adherence. Conclusion These results suggest that biennial screening is efficient for average-risk groups, but decisions on strategies depend on the weight given to the balance of harms and benefits. Primary Funding Source National Institutes of Health PMID:26756606
NASA Astrophysics Data System (ADS)
Martin, A.; Pascal, C.; Leconte, R.
2014-12-01
Stochastic Dynamic Programming (SDP) is known to be an effective technique to find the optimal operating policy of hydropower systems. In order to improve the performance of SDP, this project evaluates the impact of re-updating the policy at every time step by using Ensemble Streamflow Prediction (ESP). We present a case study of the Kemano's hydropower system on the Nechako River in British Columbia, Canada. Managed by Rio Tinto Alcan (RTA), this system is subject to large streamflow volumes in spring due to important amount of snow depth during the winter season. Therefore, the operating policy should not only maximize production but also minimize the risk of flooding. The hydrological behavior of the system is simulated with CEQUEAU, a distributed and deterministic hydrological model developed by the Institut national de la recherche scientifique - Eau, Terre et Environnement (INRS-ETE) in Quebec, Canada. On each decision time step, CEQUEAU is used to generate ESP scenarios based on historical meteorological sequences and the current state of the hydrological model. These scenarios are used into the SDP to optimize the new release policy for the next time steps. This routine is then repeated over the entire simulation period. Results are compared with those obtained by using SDP on historical inflow scenarios.
Carbon emission from global hydroelectric reservoirs revisited.
Li, Siyue; Zhang, Quanfa
2014-12-01
Substantial greenhouse gas (GHG) emissions from hydropower reservoirs have been of great concerns recently, yet the significant carbon emitters of drawdown area and reservoir downstream (including spillways and turbines as well as river reaches below dams) have not been included in global carbon budget. Here, we revisit GHG emission from hydropower reservoirs by considering reservoir surface area, drawdown zone and reservoir downstream. Our estimates demonstrate around 301.3 Tg carbon dioxide (CO2)/year and 18.7 Tg methane (CH4)/year from global hydroelectric reservoirs, which are much higher than recent observations. The sum of drawdown and downstream emission, which is generally overlooked, represents 42 % CO2 and 67 % CH4 of the total emissions from hydropower reservoirs. Accordingly, the global average emissions from hydropower are estimated to be 92 g CO2/kWh and 5.7 g CH4/kWh. Nonetheless, global hydroelectricity could currently reduce approximate 2,351 Tg CO2eq/year with respect to fuel fossil plant alternative. The new findings show a substantial revision of carbon emission from the global hydropower reservoirs.
Quadrennial Technology Review 2015: Technology Assessments--Hydropower
DOE Office of Scientific and Technical Information (OSTI.GOV)
Sam Baldwin, Gilbert Bindewald, Austin Brown, Charles Chen, Kerry Cheung, Corrie Clark, Joe Cresko,
Hydropower has provided reliable and flexible base and peaking power generation in the United States for more than a century, contributing on average 10.5% of cumulative U.S. power sector net generation over the past six and one-half decades (1949–2013). It is the nation’s largest source of renewable electricity, with 79 GW of generating assets and 22 GW of pumped-storage assets in service, with hydropower providing half of all U.S. renewable power-sector generation (50% in 2014). In addition to this capacity, the U.S. Department of Energy (DOE) has identified greater than 80 GW of new hydropower resource potential: at least 5more » GW from rehabilitation and expansion of existing generating assets, up to 12 GW of potential at existing dams without power facilities, and over 60 GW of potential low-impact new development (LIND) in undeveloped stream reaches. However, despite this growth potential, hydropower capacity and production growth have stalled in recent years, with existing assets even experiencing decreases in capacity and production from lack of sustaining investments in infrastructure and increasing constraints on water use.« less
DOE Office of Scientific and Technical Information (OSTI.GOV)
None
1979-07-01
The preliminary inventory and analysis procedures provide a comprehensive assessment of the undeveloped hydroelectric power potential in the US and determines which sites merit more thorough investigation. Over 5400 existing structures have been identified as having the physical potential to add hydropower plants or increase hydropower output thereby increasing our present hydropower capacity from a total of 64,000 MW to 158,000 MW and our energy from 280,000 GWH to 503,000 GWH. While the physical potential for this increase is clearly available, some of these projects will undoubtedly not satisfy more-detailed economic analysis as well as the institutional and environmental criteriamore » which will be imposed upon them. Summary tables include estimates of the potential capacity and energy at each site in the inventory. In some cases, individual projects may be site alternatives to others in the same general location, when only one can be considered for hydropower development. The number of sites per state is identified, but specific information is included for only the sites in Alaska, Idaho, Oregon, and Washington in this first volume.« less
21st century Himalayan hydropower: Growing exposure to glacial lake outburst floods?
NASA Astrophysics Data System (ADS)
Schwanghart, Wolfgang; Worni, Raphael; Huggel, Christian; Stoffel, Markus; Korup, Oliver
2014-05-01
Primary energy demand in China and India has increased fivefold since 1980. To avoid power shortages and blackouts, the hydropower infrastructure in the Hindu Kush-Himalaya region is seeing massive development, a strategy supported by the policy of the World Bank and in harmony with the framework of the Kyoto Protocol. The targeted investments in clean energy from water resources, however, may trigger far-reaching impacts to downstream communities given that hydropower projects are planned and constructed in close vicinity to glaciated areas. We hypothesize that the location of these new schemes may be subject to higher exposure to a broad portfolio of natural hazards that proliferate in the steep, dissected, and tectonically active topography of the Himalayas. Here we focus on the hazard from glacial lake outburst floods (GLOF), and offer an unprecedented regional analysis for the Hindu Kush-Himalaya orogen. We compiled a database of nearly 4,000 proglacial lakes that we mapped from satellite imagery; and focus on those as potential GLOF sources that are situated above several dozen planned and existing hydropower plants. We implemented a scenario-based flood-wave propagation model of hypothetic GLOFs, and compared thus simulated peak discharges with those of the local design floods at the power plants. Multiple model runs confirm earlier notions that GLOF discharge may exceed meteorological, i.e. monsoon-fed, flood peaks by at least an order of magnitude throughout the Hindu Kush-Himalaya. We further show that the current trend in hydropower development near glaciated areas may lead to a >15% increase of projects that may be impacted by future GLOFs. At the same time, the majority of the projects are to be sited where outburst flood modelling produces its maximum uncertainty, highlighting the problem of locating minimum risk sites for hydropower. Exposure to GLOFs is not uniformly distributed in the Himalayas, and is particularly high in rivers draining the Mt. Everest and Lulana regions of Nepal and Bhutan, respectively. Together with the dense, cascading sequence of hydropower stations along several river networks in these areas, the combination of GLOFs and artificial reservoirs in steep terrain may result in increasing threats to downstream communities. Hydropower stations are infrastructural investments with minimum design lives of several decades, and our results suggest that their planning should be orchestrated with projected changes in glacier response to future climate change. Our data underline the preponderance of glacial lakes in areas with high glacial retreat rates and a commensurate exposure of hydropower stations to GLOFs. To ensure sustainable water resources use at minimum risk implications for on-site downstream communities, potential changes in GLOF hazard should be taken seriously when planning hydropower stations in the Hindu Kush-Himalaya.
10 years of Elsevier/JQSRT awards
NASA Astrophysics Data System (ADS)
Stoop, José; Bernath, Peter F.; Mengüç, M. Pinar; Mishchenko, Michael I.; Rothman, Laurence S.
2017-10-01
The Elsevier award program administered by the Editorial Board of the Journal of Quantitative Spectroscopy and Radiative Transfer (JQSRT) was conceived in June of 2006 at the 9th Electromagnetic and Light Scattering Conference in St. Petersburg, Russia. Initially the program included three annual Elsevier/JQSRT awards for exceptional early-career scientists working in the main research fields covered by JQSRT: quantitative spectroscopy, radiative transfer, and electromagnetic scattering. In June of 2010 at the 12th Electromagnetic and Light Scattering Conference in Helsinki, Finland, it was decided to expand the award program to include three biennial Elsevier awards intended to celebrate fundamental life-time achievements of internationally recognized leaders in the same research fields. Finally, in 2013 the Elsevier award program was augmented to include a fourth annual early-career award in the category of atmospheric radiation and remote sensing.
Geophysical Institute. Biennial report, 1993-1994
DOE Office of Scientific and Technical Information (OSTI.GOV)
NONE
1996-01-01
The 1993-1994 Geophysical Institute Biennial Report was published in November 1995 by the Geophysical Institute of the University of Alaska Fairbanks. It contains an overview of the Geophysical Institute, the Director`s Note, and research presentations concerning the following subjects: Scientific Predictions, Space Physics, Atmospheric Sciences, Snow, Ice and Permafrost, Tectonics and Sedimentation, Seismology, Volcanology, Remote Sensing, and other projects.
Proceedings of the Ninth Biennial Southern Silvicultural Research Conference
Thomas A. Waldrop; [Editor
1998-01-01
The Ninth Biennial Southern Silvicultural Research Conference was held February 25-27, 1997 on the campus of Clemson University in Clemson, SC. This conference was the latest in a series of meetings designed to provide a forum for the exchange of research information among silviculturists and researchers in related areas, research coordination, review of research in...
ERIC Educational Resources Information Center
PEPNet 2, 2006
2006-01-01
During April 2006, educators, students, service providers and professionals from across the nation and the world gathered together at the fifth biennial PEPNet Conference in Louisville, Kentucky, to share concepts, ideas, research, technologies and successful practices that have helped individuals who are deaf and hard of hearing establish strong…
Proceedings of the Seventh Biennial Southern Silvicultural Research Conference
John Brissette
1993-01-01
This proceedings is the culmination of efforts that produced the Seventh Biennial Southern Silvicultural Research Conference. This was the latest in a series of regional conferences that began in 1980. Like the previous conferences, this meeting was designed to provide a forum for (1) the exchange of research information among silviculturists and researchers in related...
Institute of Education Sciences Biennial Report to Congress, 2005
ERIC Educational Resources Information Center
US Department of Education, 2005
2005-01-01
This, the first biennial report to Congress by the Director, as required under The Education Sciences Reform Act (ESRA), describes three goals that have guided the work of the Institute and provides an overview of progress through the end of 2004. It describes the major projects carried out within each center of the Institute over the past two…
Child Care and Development Fund: Report of State Plans FY 2002-2003.
ERIC Educational Resources Information Center
Administration on Children, Youth, and Families (DHHS), Washington, DC. Child Care Bureau.
The Personal Responsibility and Work Opportunity Reconciliation Act requires each state to submit a biennial plan to implement the Child Care and Development Fund (CCDF). This report summarizes information in the biennial plans submitted for the period October 1, 2001 to September 30, 2003. The analysis includes information from 50 states, the…
Proceedings of the 18th biennial southern silvicultural research conference
Callie Schweitzer; W.K. Clatterbuck; Christopher Oswalt
2016-01-01
At the 18th Biennial Southern Silvicultural Research Conference held in Knoxville, TN, a range of topics germane to the ecology and management of southern forests was addressed in 101 oral and 61 poster presentations. Papers are grouped into 14 topic sections and include soil and site relationships, forest threats, conservation, nutrition, fire, biometrics, biomass,...
G. Sam Foster; Alex M. Diner; [Editors
1994-01-01
This volume is the proceedings of the 1992 Southern Regional Information Exchange Group (SRIEG) Biennial Symposium on Forest Genetics. The meeting was held in Huntsville, Alabama, USA on July 8-10, 1992 and was entitled, "Applications of Vegetative Propagation in Forestry." The nine papers were divided into three sets under the headings: "Tissue Culture...
Federal Register 2010, 2011, 2012, 2013, 2014
2011-12-15
... Bioterrorism Protection Act of 2002; Biennial Review and Republication of the Select Agent and Toxin List; Amendments to the Select Agent and Toxin Regulations AGENCY: Animal and Plant Health Inspection Service, USDA... proposed rule that would amend and republish the list of select agents and toxins that have the potential...
Federal Register 2010, 2011, 2012, 2013, 2014
2010-08-17
... Bioterrorism Preparedness and Response Act of 2002: Biennial Review and Republication of the Select Agent and... public comment on the current HHS list of select agents and toxins. This document is extending the... changes to the list of select agents and toxins'' and mailed to: Centers for Disease Control and...
Federal Register 2010, 2011, 2012, 2013, 2014
2010-07-29
... Bioterrorism Protection Act of 2002; Biennial Review and Republication of the Select Agent and Toxin List; Reorganization of the Select Agent and Toxin List AGENCY: Animal and Plant Health Inspection Service, USDA... Agricultural Bioterrorism Protection Act of 2002, we are soliciting public comment regarding the list of select...
USDA-ARS?s Scientific Manuscript database
Biennial cropping is typically characterized as having 'ON' and 'OFF' years in which the 'ON' year produces an excessive crop load and the 'OFF' year has a very small crop load. Frost damage during the bloom period or winter freeze damage are another means of reducing the crop load that can initiat...
NASA Astrophysics Data System (ADS)
Razurel, Pierre; Niayifar, Amin; Perona, Paolo
2017-04-01
Hydropower plays an important role in supplying worldwide energy demand where it contributes to approximately 16% of global electricity production. Although hydropower, as an emission-free renewable energy, is a reliable source of energy to mitigate climate change, its development will increase river exploitation. The environmental impacts associated with both small hydropower plants (SHP) and traditional dammed systems have been found to the consequence of changing natural flow regime with other release policies, e.g. the minimal flow. Nowadays, in some countries, proportional allocation rules are also applied aiming to mimic the natural flow variability. For example, these dynamic rules are part of the environmental guidance in the United Kingdom and constitute an improvement in comparison to static rules. In a context in which the full hydropower potential might be reached in a close future, a solution to optimize the water allocation seems essential. In this work, we present a model that enables to simulate a wide range of water allocation rules (static and dynamic) for a specific hydropower plant and to evaluate their associated economic and ecological benefits. It is developed in the form of a graphical user interface (GUI) where, depending on the specific type of hydropower plant (i.e., SHP or traditional dammed system), the user is able to specify the different characteristics (e.g., hydrological data and turbine characteristics) of the studied system. As an alternative to commonly used policies, a new class of dynamic allocation functions (non-proportional repartition rules) is introduced (e.g., Razurel et al., 2016). The efficiency plot resulting from the simulations shows the environmental indicator and the energy produced for each allocation policies. The optimal water distribution rules can be identified on the Pareto's frontier, which is obtained by stochastic optimization in the case of storage systems (e.g., Niayifar and Perona, submitted) and by direct simulation for small hydropower ones (Razurel et al., 2016). Compared to proportional and constant minimal flows, economic and ecological efficiencies are found to be substantially improved in the case of using non-proportional water allocation rules for both SHP and traditional systems.
Hydropower Generation Performance Testing at Plants in Thailand and Laos
Kern, Jamie; Hadjerioua, Boualem; Christian, Mark H.; ...
2017-04-01
An operational assessment of four hydropower plants in Southeast Asia revealed that gains in both energy production and water conservation could be achieved with little monetary investment through operational optimization efforts.
HOMER® Energy Modeling Software 2003
DOE Office of Scientific and Technical Information (OSTI.GOV)
Lambert, Tom
2003-12-31
The HOMER® energy modeling software is a tool for designing and analyzing hybrid power systems, which contain a mix of conventional generators, cogeneration, wind turbines, solar photovoltaic, hydropower, batteries, fuel cells, hydropower, biomass and other inputs.
HOMER® Energy Modeling Software
DOE Office of Scientific and Technical Information (OSTI.GOV)
Lambert, Tom
2000-12-31
The HOMER® energy modeling software is a tool for designing and analyzing hybrid power systems, which contain a mix of conventional generators, cogeneration, wind turbines, solar photovoltaic, hydropower, batteries, fuel cells, hydropower, biomass and other inputs.
Hydropower Generation Performance Testing at Plants in Thailand and Laos
DOE Office of Scientific and Technical Information (OSTI.GOV)
Kern, Jamie; Hadjerioua, Boualem; Christian, Mark H.
An operational assessment of four hydropower plants in Southeast Asia revealed that gains in both energy production and water conservation could be achieved with little monetary investment through operational optimization efforts.
Small Hydropower Development in Rwanda: Trends, Opportunities and Challenges
NASA Astrophysics Data System (ADS)
Geoffrey, Gasore; Zimmerle, Daniel; Ntagwirumugara, Etienne
2018-04-01
The Rift Valley region of Sub-Saharan Africa represents a promising area for the development of small (<5MW) hydropower resources. This study compiles data from government and UN agency reports to analyze different development outlooks. The study found that there has been a rapid deployment of small hydropower in the last 10 years. From the current total deployed small hydro of 47.5 MW, 16.5MW (35%) were deployed from 1957 to 1984 while the remaining 31 MW (65%) were deployed from 2007 to 2017. While all systems constructed prior to 1985 are grid-connected, one third of the 24 facilities constructed after 2007 are connected to off-grid systems. The study provides an overview of the economic incentives for developing small hydropower systems in Rwanda and the potential contribution of that development to Rwanda’s electrification goals.
Organizing Environmental Flow Frameworks to Meet Hydropower Mitigation Needs
NASA Astrophysics Data System (ADS)
McManamay, Ryan A.; Brewer, Shannon K.; Jager, Henriette I.; Troia, Matthew J.
2016-09-01
The global recognition of the importance of natural flow regimes to sustain the ecological integrity of river systems has led to increased societal pressure on the hydropower industry to change plant operations to improve downstream aquatic ecosystems. However, a complete reinstatement of natural flow regimes is often unrealistic when balancing water needs for ecosystems, energy production, and other human uses. Thus, stakeholders must identify a prioritized subset of flow prescriptions that meet ecological objectives in light of realistic constraints. Yet, isolating aspects of flow regimes to restore downstream of hydropower facilities is among the greatest challenges of environmental flow science due, in part, to the sheer volume of available environmental flow tools in conjunction with complex negotiation-based regulatory procedures. Herein, we propose an organizational framework that structures information and existing flow paradigms into a staged process that assists stakeholders in implementing environmental flows for hydropower facilities. The framework identifies areas where regulations fall short of the needed scientific process, and provide suggestions for stakeholders to ameliorate those situations through advanced preparation. We highlight the strengths of existing flow paradigms in their application to hydropower settings and suggest when and where tools are most applicable. Our suggested framework increases the effectiveness and efficiency of the e-flow implementation process by rapidly establishing a knowledge base and decreasing uncertainty so more time can be devoted to filling knowledge gaps. Lastly, the framework provides the structure for a coordinated research agenda to further the science of environmental flows related to hydropower environments.
Organizing environmental flow frameworks to meet hydropower mitigation needs
McManamay, Ryan A.; Brewer, Shannon K.; Jager, Henriette; Troia, Matthew J.
2016-01-01
The global recognition of the importance of natural flow regimes to sustain the ecological integrity of river systems has led to increased societal pressure on the hydropower industry to change plant operations to improve downstream aquatic ecosystems. However, a complete reinstatement of natural flow regimes is often unrealistic when balancing water needs for ecosystems, energy production, and other human uses. Thus, stakeholders must identify a prioritized subset of flow prescriptions that meet ecological objectives in light of realistic constraints. Yet, isolating aspects of flow regimes to restore downstream of hydropower facilities is among the greatest challenges of environmental flow science due, in part, to the sheer volume of available environmental flow tools in conjunction with complex negotiation-based regulatory procedures. Herein, we propose an organizational framework that structures information and existing flow paradigms into a staged process that assists stakeholders in implementing environmental flows for hydropower facilities. The framework identifies areas where regulations fall short of the needed scientific process, and provide suggestions for stakeholders to ameliorate those situations through advanced preparation. We highlight the strengths of existing flow paradigms in their application to hydropower settings and suggest when and where tools are most applicable. Our suggested framework increases the effectiveness and efficiency of the e-flow implementation process by rapidly establishing a knowledge base and decreasing uncertainty so more time can be devoted to filling knowledge gaps. Lastly, the framework provides the structure for a coordinated research agenda to further the science of environmental flows related to hydropower environments.
Improved evaluation of the blue water footprint from hydropower in the United States
NASA Astrophysics Data System (ADS)
Zhao, G.; Gao, H.
2017-12-01
As the world's largest source of renewable energy, hydropower contributes 16.6% of the electricity production in the world. Even though it produces no waste, hydropower exhausts a considerable amount of water mostly through evaporation from the extended surface areas of the manmade lakes. The water footprint of hydropower becomes even larger with rising temperatures. To assist with the precise management of both water resources and energy production in the Contiguous United States (CONUS), 82 major dams—all with a primary purpose of producing hydroelectric power—were evaluated in terms of their blue water footprints. These dams account for 21% of the entire hydropower generation in the CONUS. Reservoir evaporation is calculated using state-of-the-art reservoir surface area and evaporation rate information. Instead of using fixed surface areas for the reservoirs—a practice which is adopted by virtually all other studies (and generally leads to over-or-under estimations)—time-variant surface areas were generated from Landsat imageries archived on Google Earth Engine (GEE) platform. Additionally, evaporation rates were calculated using an equilibrium method that incorporates the heat storage effects of the reservoirs. Results show that water consumption from hydropower is large and non-negligible. Furthermore, the differences of the blue water footprints among the dams studied are also significant. The results of this study can benefit the evaluation of existing dams (e.g. recommendation for dam removal) and the planning of future hydroelectric dams.
Organizing Environmental Flow Frameworks to Meet Hydropower Mitigation Needs.
McManamay, Ryan A; Brewer, Shannon K; Jager, Henriette I; Troia, Matthew J
2016-09-01
The global recognition of the importance of natural flow regimes to sustain the ecological integrity of river systems has led to increased societal pressure on the hydropower industry to change plant operations to improve downstream aquatic ecosystems. However, a complete reinstatement of natural flow regimes is often unrealistic when balancing water needs for ecosystems, energy production, and other human uses. Thus, stakeholders must identify a prioritized subset of flow prescriptions that meet ecological objectives in light of realistic constraints. Yet, isolating aspects of flow regimes to restore downstream of hydropower facilities is among the greatest challenges of environmental flow science due, in part, to the sheer volume of available environmental flow tools in conjunction with complex negotiation-based regulatory procedures. Herein, we propose an organizational framework that structures information and existing flow paradigms into a staged process that assists stakeholders in implementing environmental flows for hydropower facilities. The framework identifies areas where regulations fall short of the needed scientific process, and provide suggestions for stakeholders to ameliorate those situations through advanced preparation. We highlight the strengths of existing flow paradigms in their application to hydropower settings and suggest when and where tools are most applicable. Our suggested framework increases the effectiveness and efficiency of the e-flow implementation process by rapidly establishing a knowledge base and decreasing uncertainty so more time can be devoted to filling knowledge gaps. Lastly, the framework provides the structure for a coordinated research agenda to further the science of environmental flows related to hydropower environments.
NASA Astrophysics Data System (ADS)
Anghileri, Daniela; Botter, Martina; Castelletti, Andrea; Burlando, Paolo
2016-04-01
Alpine hydropower systems are experiencing dramatic changes both from the point of view of hydrological conditions, e.g., water availability and frequency of extremes events, and of energy market conditions, e.g., partial or total liberalization of the market and increasing share of renewable power sources. Scientific literature has, so far, mostly focused on the analysis of climate change impacts and associated uncertainty on hydropower operation, underlooking the consequences that socio-economic changes, e.g., energy demand and/or price changes, can have on hydropower productivity and profitability. In this work, we analyse how hydropower reservoir operation is affected by changes in both water availability and energy price. We consider stochastically downscaled climate change scenarios of precipitation and temperature to simulate reservoir inflows using a physically explicit hydrological model. We consider different scenarios of energy demand and generation mix to simulate energy prices using an electricity market model, which includes different generation sources, demand sinks, and features of the transmission lines. We then use Multi-Objective optimization techniques to design the operation of hydropower reservoirs for different purposes, e.g. maximization of revenue and/or energy production. The objective of the work is to assess how the tradeoffs between the multiple operating objectives evolve under different co-varying climate change and socio-economic scenarios and to assess the adaptive capacity of the system. The modeling framework is tested on the real-world case study of the Mattmark reservoir in Switzerland.
NASA Astrophysics Data System (ADS)
Kentel, E.; Cetinkaya, M. A.
2013-12-01
Global issues such as population increase, power supply crises, oil prices, social and environmental concerns have been forcing countries to search for alternative energy sources such as renewable energy to satisfy the sustainable development goals. Hydropower is the most common form of renewable energy in the world. Hydropower does not require any fuel, produces relatively less pollution and waste and it is a reliable energy source with relatively low operating cost. In order to estimate the average annual energy production of a hydropower plant, sufficient and dependable streamflow data is required. The goal of this study is to investigate impact of streamflow data on annual energy generation of Balkusan HEPP which is a small run-of-river hydropower plant at Karaman, Turkey. Two different stream gaging stations are located in the vicinity of Balkusan HEPP and these two stations have different observation periods: one from 1986 to 2004 and the other from 2000 to 2009. These two observation periods show different climatic characteristics. Thus, annual energy estimations based on data from these two different stations differ considerably. Additionally, neither of these stations is located at the power plant axis, thus streamflow observations from these two stream gaging stations need to be transferred to the plant axis. This requirement introduces further errors into energy estimations. Impact of different streamflow data and transfer of streamflow observations to plant axis on annual energy generation of a small hydropower plant is investigated in this study.
Mlinaric-Galinovic, Gordana; Tabain, Irena; Kukovec, Tamara; Vojnovic, Gordana; Bozikov, Jadranka; Bogovic-Cepin, Jasna; Ivkovic-Jurekovic, Irena; Knezovic, Ivica; Tesovic, Goran; Welliver, Robert C
2012-06-01
The epidemic pattern of respiratory syncytial virus (RSV) in Croatia is biennial. In order to determine if the circulation of different RSV subtypes affects the outbreak cycle, the aim of the present study was to analyze the epidemic pattern of RSV in children in Croatia (Zagreb region) over a period of 3 consecutive years. The study group consisted of 696 inpatients, aged 0-5 years, who were hospitalized with acute respiratory tract infections caused by RSV, in Zagreb, in the period 1 January 2006-31 December 2008. The virus was identified in nasopharyngeal secretions using direct immunofluorescence. The virus subtype was determined on real-time polymerase chain reaction. Of 696 RSV infections identified in children, subtype A virus caused 374 infections, and subtype B, 318. Four patients had a dual RSV infection (subtypes A and B). The period of study was characterized by four epidemic waves of RSV infections: the first, smaller, in the spring of 2006; the second, larger, in December 2006/January 2007; the third in spring 2008, followed by a fourth outbreak beginning in November of 2008. The biennial virus cycles were persistent although the predominant RSV subtype in the first two epidemic waves was subtype B, and in the second two it was subtype A. Over a 3 year period of observation, the biennial RSV cycle in Croatia cannot be explained by a difference in the predominant circulating subtype of RSV. Other unknown factors account for the biennial cycle of RSV epidemics in Croatia. © 2011 The Authors. Pediatrics International © 2011 Japan Pediatric Society.
The Quasi-Biennial Oscillation and Ross River virus incidence in Queensland, Australia.
Done, Sinead J; Holbrook, Neil J; Beggs, Paul J
2002-09-01
Ross River virus (RRV) is the most important vector-borne disease in Australia. The National Notifiable Diseases Surveillance System has confirmed that its incidence is often greatest in the state of Queensland, where there is a clear seasonal pattern as well as interannual variability. Previous studies have examined relationships between large-scale climate fluctuations (such as El Niño Southern Oscillation) and vector-borne disease. No previous study has examined such relationships with the Quasi-Biennial Oscillation (QBO), another large-scale climate fluctuation. We employ time-series analysis techniques to investigate cycles inherent in monthly RRV incidence in Queensland, Australia, from January 1991 to December 1997 inclusive. The presence of a quasi-biennial cycle in the RRV time series that is out of phase with the climatic QBO is described. Quantitative analyses using correlograms and periodograms demonstrate that the quasi-biennial cycle in the RRV time series is statistically significant, at the 95% level, above the noise. Together with the seasonal cycle, the quasi-biennial cycle accounts for 77% of the variance in Queensland RRV cases. Regression analysis of QBO and summer rainfall in three climatic zones of Queensland indicates a significant association between QBO and rainfall in the subtropical southeastern part of the state. These results suggest an indirect influence of the QBO on RRV incidence in Queensland, via its influence on climate in this region. Our findings indicate that the QBO may be a useful predictor of RRV at several months lead, and might be used by public health authorities in the management and prevention of this disease.
NASA Astrophysics Data System (ADS)
Kalumba, Mulenga; Nyirenda, Edwin
2017-12-01
The Government of the Republic Zambia (GRZ) will install a new hydropower station Kafue Gorge Lower downstream of the existing Kafue Gorge Station (KGS) and plans to start operating the Itezhi-Tezhi (ITT) hydropower facility in the Kafue Basin. The Basin has significant biodiversity hot spots such as the Luangwa National park and Kafue Flats. It is described as a Man-Biosphere reserve and the National Park is a designated World Heritage Site hosting a variety of wildlife species. All these natural reserves demand special protection, and environmental flow requirements (e-flows) have been identified as a necessary need to preserve these ecosystems. Implementation of e-flows is therefore a priority as Zambia considers to install more hydropower facilities. However before allocation of e-flows, it is necessary to first assess the river flow available for allocation at existing hydropower stations in the Kafue Basin. The river flow availability in the basin was checked by assessing the variability in low and high flows since the timing, frequency and duration of extreme droughts and floods (caused by low and high flows) are all important hydrological characteristics of a flow regime that affects e-flows. The river flows for a 41 year monthly time series data (1973-2014) were used to extract independent low and high flows using the Water Engineering Time Series Processing Tool (WETSPRO). The low and high flows were used to construct cumulative frequency distribution curves that were compared and analysed to show their variation over a long period. A water balance of each hydropower station was used to check the river flow allocation aspect by comparing the calculated water balance outflow (river flow) with the observed river flow, the hydropower and consumptive water rights downstream of each hydropower station. In drought periods about 50-100 m3/s of riverflow is available or discharged at both ITT and KGS stations while as in extreme flood events about 1300-1500 m3/s of riverflow is available. There is river flow available in the wet and dry seasons for e-flow allocation at ITT. On average per month 25 m3/s is allocated for e-flows at ITT for downstream purposes. On the other hand, it may be impossible to implement e-flows at KGS with the limited available outflow (river flow). The available river flow from ITT plays a very vital role in satisfying the current hydropower generating capacity at KGS. Therefore, the operations of KGS heavily depends on the available outflow (river flow) from ITT.
Making a Difference Through Engineer Capacity Building in Africa
2014-05-22
expense is 10 percent in Africa whereas in China energy it is only 3 percent.37 A lack of transportation infrastructure in Africa means that businesses...Africa. In 2012, China committed to provide $20 billion in loans for agriculture and infrastructure development. While this level of aid is roughly the...using wind, solar, hydropower, natural gas, and geothermal sources. This program is being executed in six sub-Saharan African nations. They are
The Rainbow School of Fundamental Physics and its Applications
NASA Astrophysics Data System (ADS)
Darve, Christine; Acharya, Bobby; Assamagan, Ketevi; Ellis, Jonathan; Muanza, Steve; African School of Fundamental Physics; its Applications Team
2011-04-01
We have established a biennial school of physics in Africa, on fundamental subatomic physics and its applications. The ``raison d'être'' of the school is to build capacity to harvest, interpret, and exploit the results of current and future physics experiments with particle accelerators, and to increase proficiency in related applications. The school is based on a close interplay between theoretical, experimental, and applied physics. The first school took place in Stellenbosch, South Africa on 1-21 August 2010, with the general aim of fostering sciences in Africa. 65 students were selected to participate to this first school edition in the rainbow country. More than 50 of them had travelled from 17 African countries, fully supported financially to attend the intensive, three-week school. This project was supported by 15 different national & international organizations and institutes. We propose the second edition of the biennial school in Ghana in 2012. The inspirational enthusiasm of the students and supporting institutions at ASP2010, give a shining hope that international Programs, Collaborations and Exchanges for the future of fundamental science and technology can be achieved. We will describe the process and the accomplishments of the first school edition, with emphasize on the lessons learned to establish the future editions.
Colorectal Cancer Screening in Average Risk Populations: Evidence Summary.
Tinmouth, Jill; Vella, Emily T; Baxter, Nancy N; Dubé, Catherine; Gould, Michael; Hey, Amanda; Ismaila, Nofisat; McCurdy, Bronwen R; Paszat, Lawrence
2016-01-01
Introduction. The objectives of this systematic review were to evaluate the evidence for different CRC screening tests and to determine the most appropriate ages of initiation and cessation for CRC screening and the most appropriate screening intervals for selected CRC screening tests in people at average risk for CRC. Methods. Electronic databases were searched for studies that addressed the research objectives. Meta-analyses were conducted with clinically homogenous trials. A working group reviewed the evidence to develop conclusions. Results. Thirty RCTs and 29 observational studies were included. Flexible sigmoidoscopy (FS) prevented CRC and led to the largest reduction in CRC mortality with a smaller but significant reduction in CRC mortality with the use of guaiac fecal occult blood tests (gFOBTs). There was insufficient or low quality evidence to support the use of other screening tests, including colonoscopy, as well as changing the ages of initiation and cessation for CRC screening with gFOBTs in Ontario. Either annual or biennial screening using gFOBT reduces CRC-related mortality. Conclusion. The evidentiary base supports the use of FS or FOBT (either annual or biennial) to screen patients at average risk for CRC. This work will guide the development of the provincial CRC screening program.
Rigor and Relevance Redux: Director's Biennial Report to Congress. IES 2009-6010
ERIC Educational Resources Information Center
Whitehurst, Grover J.
2008-01-01
The mission of the Institute of Education Sciences (IES) is to provide rigorous evidence on which to ground education practice and policy and to encourage its use. The Education Sciences Reform Act of 2002 (ESRA) requires that the Director of IES, on a biennial basis, transmit to the President, the National Board for Education Sciences, and the…
ERIC Educational Resources Information Center
Library Association of Australia, Sidney.
The fifteenth biennial Conference of the Library Association of Australia was held from August 25th to 29th, 1969, in Adelaide. This proceedings volume contains many of the papers given, and summaries of many others. Five papers were presented during the plenary sessions. Thirty-one authors presented general papers. There were nine seminars…
Support for Society for Marine Mammalogy 2015 Biennial Conference
2015-09-30
Communicating Science Speakers: • Jane Lubchenco – Distinguished Professor of Zoology and Valley Professor of Marine Biology , Oregon State University...1 DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. FINAL REPORT Support for Society for Marine Mammalogy 2015...Biennial Conference Frances Gulland The Marine Mammal Center 2000 Bunker Rd. Fort Cronkhite Sausolito, CA 94965 phone: (415) 289-7344 fax
[Biennial Survey of Education, 1926-1928. Bulletin, 1930, No. 16. Chapter I - Chapter XX
ERIC Educational Resources Information Center
Office of Education, United States Department of the Interior, 1930
1930-01-01
This document contains the first twenty chapters of the Biennial Survey of Education document, covering the years 1926-1928. The following chapters are included in this document: (1) Higher education (Arthur J. Klein); (2) Medical education (N. P. Colwell); (3) Legal education (Alfred Z. Reed); (4) Significant movements in city school systems (W.…
Biennial Survey of Education, 1916-18. Volume I. Bulletin, 1919, No. 88
ERIC Educational Resources Information Center
Bureau of Education, Department of the Interior, 1921
1921-01-01
Volume I of the 1916-18 Biennial Survey of Education includes the following chapters: (1) A survey of higher education (Samuel P. Capen and Walton C. John); (2) Medical education (N. P. Colwell); (3) Engineering education (F. L. Bishop); (4) Commercial education (Frank V. Thompson); (5) Public education in the cities of the United States: The…
Biennial Survey of Education, 1920-1922. Volume I. Bulletin, 1924, No. 13
ERIC Educational Resources Information Center
Bureau of Education, Department of the Interior, 1924
1924-01-01
Volume I of the Biennial Survey of Education for the years 1920-1922 contains the following chapters: (1) A survey of public school finance in the United States (Fletcher H. Swift); (2) Some important school legislation, 1921 and 1922 (William R. Hood); (3) Higher education (George F. Zook; (4) Significant movements in city school systems (W. S.…
5 CFR 591.226 - How does OPM apply the CPIs?
Code of Federal Regulations, 2013 CFR
2013-01-01
... survey. (1) Step 1. OPM computes the annual or biennial CPI change for the COLA area. (2) Step 2. OPM computes the annual or biennial CPI change for the DC area. (3) Step 3. OPM multiplies the COLA area price index from the last survey by the COLA area CPI change computed in step 1 divided by the DC area CPI...
5 CFR 591.226 - How does OPM apply the CPIs?
Code of Federal Regulations, 2014 CFR
2014-01-01
... survey. (1) Step 1. OPM computes the annual or biennial CPI change for the COLA area. (2) Step 2. OPM computes the annual or biennial CPI change for the DC area. (3) Step 3. OPM multiplies the COLA area price index from the last survey by the COLA area CPI change computed in step 1 divided by the DC area CPI...
5 CFR 591.226 - How does OPM apply the CPIs?
Code of Federal Regulations, 2011 CFR
2011-01-01
... survey. (1) Step 1. OPM computes the annual or biennial CPI change for the COLA area. (2) Step 2. OPM computes the annual or biennial CPI change for the DC area. (3) Step 3. OPM multiplies the COLA area price index from the last survey by the COLA area CPI change computed in step 1 divided by the DC area CPI...
5 CFR 591.226 - How does OPM apply the CPIs?
Code of Federal Regulations, 2012 CFR
2012-01-01
... survey. (1) Step 1. OPM computes the annual or biennial CPI change for the COLA area. (2) Step 2. OPM computes the annual or biennial CPI change for the DC area. (3) Step 3. OPM multiplies the COLA area price index from the last survey by the COLA area CPI change computed in step 1 divided by the DC area CPI...
5 CFR 591.226 - How does OPM apply the CPIs?
Code of Federal Regulations, 2010 CFR
2010-01-01
... survey. (1) Step 1. OPM computes the annual or biennial CPI change for the COLA area. (2) Step 2. OPM computes the annual or biennial CPI change for the DC area. (3) Step 3. OPM multiplies the COLA area price index from the last survey by the COLA area CPI change computed in step 1 divided by the DC area CPI...
James D. Haywood; Alton Martin; Henry A. Pearson; Harold E. Grelen
1998-01-01
This paper documents the results of a study to determine the effects of selectedvegetation-management treatments in loblolly pine. Vegetation in precommercially thinned, 6-year-old stands was subjected to five biennial growing season burns in either early March, May, or July coupled with hand felling of residual woody stems. Using a randomized complete block design, we...
Toward a Learning Society. Director's Biennial Report to Congress. IES 2007-6004
ERIC Educational Resources Information Center
Institute of Education Sciences, 2007
2007-01-01
The mission of the Institute of Education Sciences (IES) is to provide rigorous evidence on which to ground education practice and policy and to encourage its use. The Education Sciences Reform Act of 2002 (ESRA) requires that the Director of IES, on a biennial basis, transmit to the President, the National Board for Education Sciences, and the…
Thayer Lake Hydropower Development -- Final Report
DOE Office of Scientific and Technical Information (OSTI.GOV)
Matousek, Mark
The Thayer Lake Hydropower Development (THLD) has been under study since the late 1970’s as Angoon explored opportunities to provide lower cost renewable power to the Community and avoid the high cost of diesel generation. Kootznoowoo Inc. (Kootznoowoo), the tribal corporation for Angoon’s current and past residents, was provided the rights by Congress to develop a hydropower project within the Admiralty Island National Monument. This grant (DE-EE0002504) by the Department of Energy’s (DOE’s) Office of Indian Energy and a matching grant from the Alaska Energy Authority (AEA) were provided to Kootznoowoo to enable the design, engineering and permitting of thismore » hydropower project on Thayer Creek. Prior to the grant, the USFS had performed a final environmental impact statement (FEIS) and issued a Record of Decision (ROD) in 2009 for a 1.2 MW hydropower project on Thayer Creek that would Angoon’s needs with substantial excess capacity for growth. Kootznoowoo hired Alaska Power & Telephone (AP&T) in 2013 to manage this project and oversee its development. AP&T and its subcontractors under Kootznoowoo’s guidance performed several activities, aligned with the task plan defined in the grant.« less
Climate impacts on hydropower and consequences for global electricity supply investment needs
DOE Office of Scientific and Technical Information (OSTI.GOV)
Turner, Sean W. D.; Hejazi, Mohamad; Kim, Son H.
Recent progress in global scale hydrological and dam modeling has allowed for the study of climate change impacts on global hydropower production. Here we explore the possible consequences of these impacts for the electricity supply sector. Regional hydropower projections are developed for two emissions scenarios by forcing a coupled global hydrological and dam model with downscaled, bias-corrected climate realizations derived from sixteen general circulation models. Consequent impacts on power sector composition and associated emissions and investment costs are explored using the Global Change Assessment Model (GCAM). Changes in hydropower generation resulting from climate change can shift power demands onto andmore » away from carbon intensive technologies, resulting in significant impacts on power sector CO2 emissions for certain world regions—primarily those located in Latin America, as well as Canada and parts of Europe. Reduced impacts of climate change on hydropower production under a low emissions scenario coincide with increased costs of marginal power generating capacity—meaning impacts on power sector investment costs are similar for high and low emissions scenarios. Individual countries where impacts on investment costs imply significant risks or opportunities are identified.« less
Determining the effect of key climate drivers on global hydropower production
NASA Astrophysics Data System (ADS)
Galelli, S.; Ng, J. Y.; Lee, D.; Block, P. J.
2017-12-01
Accounting for about 17% of total global electrical power production, hydropower is arguably the world's main renewable energy source and a key asset to meet Paris climate agreements. A key component of hydropower production is water availability, which depends on both precipitation and multiple drivers of climate variability acting at different spatial and temporal scales. To understand how these drivers impact global hydropower production, we study the relation between four patterns of ocean-atmosphere climate variability (i.e., El Niño Southern Oscillation, Pacific Decadal Oscillation, North Atlantic Oscillation, and Atlantic Multidecadal Oscillation) and monthly time series of electrical power production for over 1,500 hydropower reservoirs—obtained via simulation with a high-fidelity dam model forced with 20th century climate conditions. Notably significant relationships between electrical power productions and climate variability are found in many climate sensitive regions globally, including North and South America, East Asia, West Africa, and Europe. Coupled interactions from multiple, simultaneous climate drivers are also evaluated. Finally, we highlight the importance of using these climate drivers as an additional source of information within reservoir operating rules where the skillful predictability of inflow exists.
HOMER® Energy Modeling Software V2.63
DOE Office of Scientific and Technical Information (OSTI.GOV)
Lambert, Tom
2003-12-31
The HOMER® energy modeling software is a tool for designing and analyzing hybrid power systems, which contain a mix of conventional generators, cogeneration, wind turbines, solar photovoltaic, hydropower, batteries, fuel cells, hydropower, biomass and other inputs.
HOMER® Energy Modeling Software V2.64
DOE Office of Scientific and Technical Information (OSTI.GOV)
Lambert, Tom
2003-12-31
The HOMER® energy modeling software is a tool for designing and analyzing hybrid power systems, which contain a mix of conventional generators, cogeneration, wind turbines, solar photovoltaic, hydropower, batteries, fuel cells, hydropower, biomass and other inputs.
HOMER® Energy Modeling Software V2.65
DOE Office of Scientific and Technical Information (OSTI.GOV)
Lambert, Tom
2008-12-31
The HOMER® energy modeling software is a tool for designing and analyzing hybrid power systems, which contain a mix of conventional generators, cogeneration, wind turbines, solar photovoltaic, hydropower, batteries, fuel cells, hydropower, biomass and other inputs.
HOMER® Energy Modeling Software V2.0
DOE Office of Scientific and Technical Information (OSTI.GOV)
Lambert, Tom
2003-12-31
The HOMER® energy modeling software is a tool for designing and analyzing hybrid power systems, which contain a mix of conventional generators, cogeneration, wind turbines, solar photovoltaic, hydropower, batteries, fuel cells, hydropower, biomass and other inputs.
HOMER® Energy Modeling Software V2.19
DOE Office of Scientific and Technical Information (OSTI.GOV)
Lambert, Tom
2008-12-31
The HOMER® energy modeling software is a tool for designing and analyzing hybrid power systems, which contain a mix of conventional generators, cogeneration, wind turbines, solar photovoltaic, hydropower, batteries, fuel cells, hydropower, biomass and other inputs.
HOMER® Energy Modeling Software V2.67
DOE Office of Scientific and Technical Information (OSTI.GOV)
Lambert, Tom
2008-12-31
The HOMER® energy modeling software is a tool for designing and analyzing hybrid power systems, which contain a mix of conventional generators, cogeneration, wind turbines, solar photovoltaic, hydropower, batteries, fuel cells, hydropower, biomass and other inputs.
DOE Office of Scientific and Technical Information (OSTI.GOV)
Kao, Shih-Chieh; McManamay, Ryan A; Stewart, Kevin M
2014-04-01
The rapid development of multiple national geospatial datasets related to topography, hydrology, and environmental characteristics in the past decade have provided new opportunities for the refinement of hydropower resource potential from undeveloped stream-reaches. Through 2011 to 2013, the Oak Ridge National Laboratory (ORNL) was tasked by the Department of Energy (DOE) Water Power Program to evaluate the new stream-reach development (NSD) resource potential for more than 3 million US streams. A methodology was designed that contains three main components: (1) identification of stream-reaches with high energy density, (2) topographical analysis of stream-reaches to estimate inundated surface area and reservoir storage,more » and (3) environmental attribution to spatially join information related to the natural ecological systems, social and cultural settings, policies, management, and legal constraints to stream-reaches of energy potential. An initial report on methodology (Hadjerioua et al., 2013) was later reviewed and revised based on the comments gathered from two peer review workshops. After implementing the assessment across the entire United States, major findings were summarized in this final report. The estimated NSD capacity and generation, including both higher-energy-density (>1 MW per reach) and lower-energy-density (<1 MW per reach) stream-reaches is 84.7 GW, around the same size as the existing US conventional hydropower nameplate capacity (79.5 GW; NHAAP, 2013). In terms of energy, the total undeveloped NSD generation is estimated to be 460 TWh/year, around 169% of average 2002 2011 net annual generation from existing conventional hydropower plants (272 TWh/year; EIA, 2013). Given the run-of-river assumption, NSD stream-reaches have higher capacity factors (53 71%), especially compared with conventional larger-storage peaking-operation projects that usually have capacity factors of around 30%. The highest potential is identified in the Pacific Northwest Region (32%), followed by Missouri Region (15%) and California Region (9%). In terms of states, the highest potential is found in Oregon, Washington, and Idaho, the three states in the Pacific Northwest, followed by California, Alaska, Montana, and Colorado. In addition to the resource potential, abundant environmental attributes were also organized and attributed to the identified stream-reaches to support further hydropower market analysis. The prevalence of environmental variables and proportion of capacity from stream-reaches intersecting environmental variables varied according to hydrologic region. Detailed NSD findings are organized by hydrologic regions and presented in each chapter of this report.« less
Low-head hydropower assessment of the Brazilian State of São Paulo
Artan, Guleid A.; Cushing, W. Matthew; Mathis, Melissa L.; Tieszen, Larry L.
2014-01-01
This study produced a comprehensive estimate of the magnitude of hydropower potential available in the streams that drain watersheds entirely within the State of São Paulo, Brazil. Because a large part of the contributing area is outside of São Paulo, the main stem of the Paraná River was excluded from the assessment. Potential head drops were calculated from the Digital Terrain Elevation Data,which has a 1-arc-second resolution (approximately 30-meter resolution at the equator). For the conditioning and validation of synthetic stream channels derived from the Digital Elevation Model datasets, hydrography data (in digital format) supplied by the São Paulo State Department of Energy and the Agência Nacional de Águas were used. Within the study area there were 1,424 rain gages and 123 streamgages with long-term data records. To estimate average yearly streamflow, a hydrologic regionalization system that divides the State into 21 homogeneous basins was used. Stream segments, upstream areas, and mean annual rainfall were estimated using geographic information systems techniques. The accuracy of the flows estimated with the regionalization models was validated. Overall, simulated streamflows were significantly correlated with the observed flows but with a consistent underestimation bias. When the annual mean flows from the regionalization models were adjusted upward by 10 percent, average streamflow estimation bias was reduced from -13 percent to -4 percent. The sum of all the validated stream reach mean annual hydropower potentials in the 21 basins is 7,000 megawatts (MW). Hydropower potential is mainly concentrated near the Serra do Mar mountain range and along the Tietê River. The power potential along the Tietê River is mainly at sites with medium and high potentials, sites where hydropower has already been harnessed. In addition to the annual mean hydropower estimates, potential hydropower estimates with flow rates with exceedance probabilities of 40 percent, 60 percent, and 90 percent were made.
NASA Astrophysics Data System (ADS)
Anghileri, D.; Castelletti, A.; Burlando, P.
2016-12-01
European energy markets have experienced dramatic changes in the last years because of the massive introduction of Variable Renewable Sources (VRSs), such as wind and solar power sources, in the generation portfolios in many countries. VRSs i) are intermittent, i.e., their production is highly variable and only partially predictable, ii) are characterized by no correlation between production and demand, iii) have negligible costs of production, and iv) have been largely subsidized. These features result in lower energy prices, but, at the same time, in increased price volatility, and in network stability issues, which pose a threat to traditional power sources because of smaller incomes and higher maintenance costs associated to a more flexible operation of power systems. Storage hydropower systems play an important role in compensating production peaks, both in term of excess and shortage of energy. Traditionally, most of the research effort in hydropower reservoir operation has focused on modeling and forecasting reservoir inflow as well as designing reservoir operation accordingly. Nowadays, price variability may be the largest source of uncertainty in the context of hydropower systems, especially when considering medium-to-large reservoirs, whose storage can easily buffer small inflow fluctuations. In this work, we compare the effects of uncertain inflow and energy price forecasts on hydropower production and profitability. By adding noise to historic inflow and price trajectories, we build a set of synthetic forecasts corresponding to different levels of predictability and assess their impact on reservoir operating policies and performances. The study is conducted on different hydropower systems, including storage systems and pumped-storage systems, with different characteristics, e.g., different inflow-capacity ratios. The analysis focuses on Alpine hydropower systems where the hydrological regime ranges from purely ice and snow-melt dominated to mixed snow-melt and rain-dominated regimes.
DOE Office of Scientific and Technical Information (OSTI.GOV)
None
2016-07-01
Publication summarizing how the United States Army Corps of Engineers (USACE) and Federal Regulatory Energy Commission (FERC) have developed a two-phased, coordinated approach to regulating non-federal hydropower projects.
IMPLEMENTING PRACTICAL PICO-HYDROPOWER
Deliverables for this proposal will be energy output data modeled from experimental testing of the hydropower unit and monitoring of the stormwater handling infrastructure in the GIS building; along with a design and engineering plan for implementation and building integrat...
Hydropower Manufacturing and Supply Chain Analysis
DOE Office of Scientific and Technical Information (OSTI.GOV)
Cotrell, Jason R
Hydropower Manufacturing and Supply Chain Analysis presentation from the WPTO FY14-FY16 Peer Review. The project objective is to provide data and insights to inform investment strategies, policy, and other decisions to promote economic growth and manufacturing.
Freshwater ecosystems could become the biggest losers of the Paris Agreement.
Hermoso, Virgilio
2017-09-01
Securing access to energy for a growing population under the international commitment of reduction of greenhouse emissions requires increasing the contribution of renewable sources to the global share. Hydropower energy, which accounts for >80% of green energy, is experiencing a boom fostered by international investment mainly in developing countries. This boom could be further accelerated by the recent climate agreement reached in Paris. Despite its flexibility, hydropower production entails social, economic and ecological risks that need to be carefully considered before investing in the development of potentially thousands of planned hydropower projects worldwide. This is especially relevant given the weak or nonexistent legislation that regulates hydropower project approval and construction in many countries. I highlight the need for adequate policy to provide the Paris Agreement with new financial and planning mechanisms to avoid further and irreversible damage to freshwater ecosystem services and biodiversity. © 2017 John Wiley & Sons Ltd.
Regulatory Approaches for Adding Capacity to Existing Hydropower Facilities
DOE Office of Scientific and Technical Information (OSTI.GOV)
Levine, Aaron L.; Curtis, Taylor L.; Kazerooni, Borna
In 2015, hydroelectric generation accounted for more than 6 percent of total net electricity generation in the United States and 46 percent of electricity generation from all renewables. The United States has considerable hydroelectric potential beyond what is already being developed. Nearly 7 GW of this potential is found by adding capacity to existing hydropower facilities. To optimize the value of hydroelectric generation, the U.S. Department of Energy's Hydropower Vision Study highlights the importance of adding capacity to existing facilities. This report provides strategic approaches and considerations for Federal Energy Regulatory Commission licensed and exempt hydropower facilities seeking to increasemore » generation capacity, which may include increases from efficiency upgrades. The regulatory approaches reviewed for this report include capacity and non-capacity amendments, adding capacity during relicensing, and adding capacity when converting a license to a 10-MW exemption.« less
[Impacts of large hydropower station on benthic algal communities].
Jia, Xing-Huan; Jiang, Wan-Xiang; Li, Feng-Qing; Tang, Tao; Duan, Shu-Gui; Cai, Qing-Hua
2009-07-01
To investigate the impacts of large hydropower station in Gufu River on benthic algae, monthly samplings were conducted from September 2004 to June 2007 at the site GF04 which was impacted by the hydropower station, with the site GL03 in Gaolan River as reference. During sampling period, no significant differences were observed in the main physicochemical variables between GF04 and GL03, but the hydrodynamics differed significantly. GL03 was basically at a status of slow flow; while GF04, owing to the discharging from the reservoir, was at a riffle status during more than 60% of the sampling period. Such a difference in hydrodynamics induced significant differences in the community similarity of benthic algae and the relative abundance of unattached diatoms, erect diatoms, and stalked diatoms between GF04 and GL03, which could better reflect the impacts of irregular draw-off by large hydropower station on river eco-system.
NASA Astrophysics Data System (ADS)
Xiao, Jian; Zhang, Mingqiang; Tian, Haiping; Huang, Bo; Fu, Wenlong
2018-02-01
In this paper, a novel prognostics and health management system architecture for hydropower plant equipment was proposed based on fog computing and Docker container. We employed the fog node to improve the real-time processing ability of improving the cloud architecture-based prognostics and health management system and overcome the problems of long delay time, network congestion and so on. Then Storm-based stream processing of fog node was present and could calculate the health index in the edge of network. Moreover, the distributed micros-service and Docker container architecture of hydropower plants equipment prognostics and health management was also proposed. Using the micro service architecture proposed in this paper, the hydropower unit can achieve the goal of the business intercommunication and seamless integration of different equipment and different manufacturers. Finally a real application case is given in this paper.
1989-01-01
environmental review process as indicated by the County Traffic Engineers for safe and secure transport of ordnance as well as the chosen alternative...from other appropriations: None. PRVOSEDITION$ MAY SE USED ITRALDD DE 7 PG NO.DD • 391C UNTIL XHAUSTEDP N. S.PRRMELMN . CATGOR OO 7..POETNMER U JC...service. IMPACT IF NOT PROVIDED: Activity must rely r.n truck refuelers which are not Capable of handling the demand. Time delays, logisticA and safety
ERIC Educational Resources Information Center
Office of Education, United States Department of the Interior, 1932
1932-01-01
This document contains the four concluding chapters and index of the Biennial Survey of Education, covering the years 1928-1930. Chapter 4, Statistics of universities, colleges, and professional schools, 1929-30, is made up of three parts: (1) Personnel, receipts, and property (Emery M. Foster and Frederick J. Kelley); (2) Expenditures (Henry G.…
ERIC Educational Resources Information Center
Whitcomb, Emeline S.
1931-01-01
This chapter of the "Biennial Survey of Education in the United States, 1928-1930" focuses on the following topic areas as they relate to homemaking education: Part I: Present trends, contains the following: (a) Contributions rendered; (b) Philosophy changes; (c) Expansion of home economics in our public schools; (d) Home economics required; (e)…
Delayed prescribed burning in a seedling and sapling Longleaf Pine plantation in Louisiana
James D. Haywood
2002-01-01
To examine the effects of delaying prescribed burning for several years, I initiated five treatments in a 5- to 6-year-old longleaf pine stand: a check of no control; biennial hardwood control by directed chemical application; and biennial burning in either early March, May, or July. After the initial burns, longleaf pine survival decreased from 82 percent in February...
Quasi-biennial Oscillations (QBO) as seen in GPS/CHAMP Tropospheric and Ionospheric Data
NASA Technical Reports Server (NTRS)
Wu, Dong L.; Pi, Xiaoqing; Ao, Chi O.; Mannucci, Anthony J.
2006-01-01
A viewgraph presentation on Quasi-biennial Oscillations (QBO) from Global Positioning System/Challenging Mini-Satellite Payload (GPS/CHAMP) tropospheric and ionsopheric data is shown. The topics include: 1) A brief review of QBO; 2) Characteristics of small-scale oscillations in GPS/CHAMP 50-Hz raw measurements; 3) Variations of lower atmospheric variances; and 4) Variations of E-region variances.
Proceedings of the second biennial conference on research in Colorado Plateau National Parks
van Riper, Charles
1995-01-01
On 25-28 October 1993 in Flagstaff, Arizona, the National Biological Service Colorado Plateau Research Station (formerly National Park Service Cooperative Park Studies Unit) and Northern Arizona University hosted the Second Biennial Conference of Research on the Colorado Plateau. The conference theme focused on research, inventory, and monitoring on the federal, state, and private lands in the Colorado Plateau biogeographic province.
May Burns Stimulate Growth in Longleaf Pine Seedlings
Harold E. Grelen
1978-01-01
Annual and biennial fires applied around May 1 are more beneficial to the growth of young longleaf pines than March 1 fires. Four years of testing on a poorly drained silt loam soil in central Louisiana showed that more grass-stage seedlings survived. began height growth, and grew taller on plots burned in May than on March-burned plots. A biennial May burn was best...
Organizing environmental flow frameworks to meet hydropower mitigation needs
DOE Office of Scientific and Technical Information (OSTI.GOV)
McManamay, Ryan A.; Brewer, Shannon K.; Jager, Henriette I.
The global recognition of the importance of natural flow regimes to sustain the ecological integrity of river systems has led to increased societal pressure on the hydropower industry to change plant operations to improve downstream aquatic ecosystems. However, a complete reinstatement of natural flow regimes is often unrealistic when balancing water needs for ecosystems, energy production, and other human uses. Thus, stakeholders must identify a prioritized subset of flow prescriptions that meet ecological objectives in light of realistic constraints. Yet, isolating aspects of flow regimes to restore downstream of hydropower facilities is among the greatest challenges of environmental flow sciencemore » due, in part, to the sheer volume of available environmental flow tools in conjunction with complex negotiation-based regulatory procedures. Here, we propose an organizational framework that structures information and existing flow paradigms into a staged process that assists stakeholders in implementing environmental flows for hydropower facilities. The framework identifies areas where regulations fall short of the needed scientific process, and provide suggestions for stakeholders to ameliorate those situations through advanced preparation. We highlight the strengths of existing flow paradigms in their application to hydropower settings and suggest when and where tools are most applicable. In conclusion, our suggested framework increases the effectiveness and efficiency of the e-flow implementation process by rapidly establishing a knowledge base and decreasing uncertainty so more time can be devoted to filling knowledge gaps. As a result, the framework provides the structure for a coordinated research agenda to further the science of environmental flows related to hydropower environments.« less
Turner, Sean W D; Ng, Jia Yi; Galelli, Stefano
2017-07-15
An important and plausible impact of a changing global climate is altered power generation from hydroelectric dams. Here we project 21st century global hydropower production by forcing a coupled, global hydrological and dam model with three General Circulation Model (GCM) projections run under two emissions scenarios. Dams are simulated using a detailed model that accounts for plant specifications, storage dynamics, reservoir bathymetry and realistic, optimized operations. We show that the inclusion of these features can have a non-trivial effect on the simulated response of hydropower production to changes in climate. Simulation results highlight substantial uncertainty in the direction of change in globally aggregated hydropower production (~-5 to +5% change in mean global production by the 2080s under a high emissions scenario, depending on GCM). Several clearly impacted hotspots are identified, the most prominent of which encompasses the Mediterranean countries in southern Europe, northern Africa and the Middle East. In this region, hydropower production is projected to be reduced by approximately 40% on average by the end of the century under a high emissions scenario. After accounting for each country's dependence on hydropower for meeting its current electricity demands, the Balkans countries emerge as the most vulnerable (~5-20% loss in total national electricity generation depending on country). On the flipside, a handful of countries in Scandinavia and central Asia are projected to reap a significant increase in total electrical production (~5-15%) without investing in new power generation facilities. Copyright © 2017 Elsevier B.V. All rights reserved.
Turner, Sean W. D.; Ng, Jia Yi; Galelli, Stefano
2017-03-07
Here, an important and plausible impact of a changing global climate is altered power generation from hydroelectric dams. Here we project 21st century global hydropower production by forcing a coupled, global hydrological and dam model with three General Circulation Model (GCM) projections run under two emissions scenarios. Dams are simulated using a detailed model that accounts for plant specifications, storage dynamics, reservoir bathymetry and realistic, optimized operations. We show that the inclusion of these features can have a non-trivial effect on the simulated response of hydropower production to changes in climate. Simulation results highlight substantial uncertainty in the direction ofmore » change in globally aggregated hydropower production (~–5 to + 5% change in mean global production by the 2080s under a high emissions scenario, depending on GCM). Several clearly impacted hotspots are identified, the most prominent of which encompasses the Mediterranean countries in southern Europe, northern Africa and the Middle East. In this region, hydropower production is projected to be reduced by approximately 40% on average by the end of the century under a high emissions scenario. After accounting for each country's dependence on hydropower for meeting its current electricity demands, the Balkans countries emerge as the most vulnerable (~ 5–20% loss in total national electricity generation depending on country). On the flipside, a handful of countries in Scandinavia and central Asia are projected to reap a significant increase in total electrical production (~ 5–15%) without investing in new power generation facilities.« less
DOE Office of Scientific and Technical Information (OSTI.GOV)
Turner, Sean W. D.; Ng, Jia Yi; Galelli, Stefano
Here, an important and plausible impact of a changing global climate is altered power generation from hydroelectric dams. Here we project 21st century global hydropower production by forcing a coupled, global hydrological and dam model with three General Circulation Model (GCM) projections run under two emissions scenarios. Dams are simulated using a detailed model that accounts for plant specifications, storage dynamics, reservoir bathymetry and realistic, optimized operations. We show that the inclusion of these features can have a non-trivial effect on the simulated response of hydropower production to changes in climate. Simulation results highlight substantial uncertainty in the direction ofmore » change in globally aggregated hydropower production (~–5 to + 5% change in mean global production by the 2080s under a high emissions scenario, depending on GCM). Several clearly impacted hotspots are identified, the most prominent of which encompasses the Mediterranean countries in southern Europe, northern Africa and the Middle East. In this region, hydropower production is projected to be reduced by approximately 40% on average by the end of the century under a high emissions scenario. After accounting for each country's dependence on hydropower for meeting its current electricity demands, the Balkans countries emerge as the most vulnerable (~ 5–20% loss in total national electricity generation depending on country). On the flipside, a handful of countries in Scandinavia and central Asia are projected to reap a significant increase in total electrical production (~ 5–15%) without investing in new power generation facilities.« less
Organizing environmental flow frameworks to meet hydropower mitigation needs
McManamay, Ryan A.; Brewer, Shannon K.; Jager, Henriette I.; ...
2016-06-25
The global recognition of the importance of natural flow regimes to sustain the ecological integrity of river systems has led to increased societal pressure on the hydropower industry to change plant operations to improve downstream aquatic ecosystems. However, a complete reinstatement of natural flow regimes is often unrealistic when balancing water needs for ecosystems, energy production, and other human uses. Thus, stakeholders must identify a prioritized subset of flow prescriptions that meet ecological objectives in light of realistic constraints. Yet, isolating aspects of flow regimes to restore downstream of hydropower facilities is among the greatest challenges of environmental flow sciencemore » due, in part, to the sheer volume of available environmental flow tools in conjunction with complex negotiation-based regulatory procedures. Here, we propose an organizational framework that structures information and existing flow paradigms into a staged process that assists stakeholders in implementing environmental flows for hydropower facilities. The framework identifies areas where regulations fall short of the needed scientific process, and provide suggestions for stakeholders to ameliorate those situations through advanced preparation. We highlight the strengths of existing flow paradigms in their application to hydropower settings and suggest when and where tools are most applicable. In conclusion, our suggested framework increases the effectiveness and efficiency of the e-flow implementation process by rapidly establishing a knowledge base and decreasing uncertainty so more time can be devoted to filling knowledge gaps. As a result, the framework provides the structure for a coordinated research agenda to further the science of environmental flows related to hydropower environments.« less
How run-of-river operation affects hydropower generation and value.
Jager, Henriette I; Bevelhimer, Mark S
2007-12-01
Regulated rivers in the United States are required to support human water uses while preserving aquatic ecosystems. However, the effectiveness of hydropower license requirements nationwide has not been demonstrated. One requirement that has become more common is "run-of-river" (ROR) operation, which restores a natural flow regime. It is widely believed that ROR requirements (1) are mandated to protect aquatic biota, (2) decrease hydropower generation per unit flow, and (3) decrease energy revenue. We tested these three assumptions by reviewing hydropower projects with license-mandated changes from peaking to ROR operation. We found that ROR operation was often prescribed in states with strong water-quality certification requirements and migratory fish species. Although benefits to aquatic resources were frequently cited, changes were often motivated by other considerations. After controlling for climate, the overall change in annual generation efficiency across projects because of the change in operation was not significant. However, significant decreases were detected at one quarter of individual hydropower projects. As expected, we observed a decrease in flow during peak demand at 7 of 10 projects. At the remaining projects, diurnal fluctuations actually increased because of operation of upstream storage projects. The economic implications of these results, including both producer costs and ecologic benefits, are discussed. We conclude that regional-scale studies of hydropower regulation, such as this one, are long overdue. Public dissemination of flow data, license provisions, and monitoring data by way of on-line access would facilitate regional policy analysis while increasing regulatory transparency and providing feedback to decision makers.
NASA Astrophysics Data System (ADS)
Marques, G.
2015-12-01
Biofuels such as ethanol from sugar cane remain an important element to help mitigate the impacts of fossil fuels on the atmosphere. However, meeting fuel demands with biofuels requires technological advancement for water productivity and scale of production. This may translate into increased water demands for biofuel crops and potential for conflicts with incumbent crops and other water uses including domestic, hydropower generation and environmental. It is therefore important to evaluate the effects of increased biofuel production on the verge of water scarcity costs and hydropower production. The present research applies a hydro-economic optimization model to compare different scenarios of irrigated biofuel and hydropower production, and estimates the potential tradeoffs. A case study from the Araguari watershed in Brazil is provided. These results should be useful to (i) identify improved water allocation among competing economic demands, (ii) support water management and operations decisions in watersheds where biofuels are expected to increase, and (iii) identify the impact of bio fuel production in the water availability and economic value. Under optimized conditions, adoption of sugar cane for biofuel production heavily relies on the opportunity costs of other crops and hydropower generation. Areas with a lower value crop groups seem more suitable to adopt sugar cane for biofuel when the price of ethanol is sufficiently high and the opportunity costs of hydropower productions are not conflicting. The approach also highlights the potential for insights in water management from studying regional versus larger scales bundled systems involving water use, food production and power generation.
Federal Register 2010, 2011, 2012, 2013, 2014
2010-10-12
... Hydropower, LLC, 801 Oakland Avenue, Joliet, IL 60435, (312) 320-1610. i. FERC Contact: Janet Hutzel, (202) 502-8675 or janet[email protected] . j. Deadline for filing comments, recommendations, terms and...
NASA Astrophysics Data System (ADS)
Finger, David
2015-04-01
About 80% of the domestic energy production in Iceland comes from renewable energies. Hydropower accounts for about 20% this production, representing about 75% of the total electricity production in Iceland. In 2008 total electricity production from hydropower was about 12.5 TWh a-1, making Iceland a worldwide leader in hydropower production per capita. Furthermore, the total potential of hydroelectricity in Iceland is estimated to amount up to 220 TWh a-1. In this regard, hydrological modelling is an essential tool to adapt a sustainable management of water resources and estimate the potential of possible new sites for hydropower production. We used the conceptual lumped Hydrologiska Byråns Vattenbalansavdelning model (HBV) to estimate the potential of hydropower production in two remote areas in north-eastern Iceland (Leirdalshraun, a 274 km2 area above 595 m asl and Hafralónsá, a 946 km2 area above 235 m asl). The model parameters were determined by calibrating the model with discharge data from gauged sub catchments. Satellite snow cover images were used to constrain melt parameters of the model and assure adequate modelling of snow melt in the ungauged areas. This was particularly valuable to adequately estimate the contribution of snow melt, rainfall runoff and groundwater intrusion from glaciers outside the topographic boundaries of the selected watersheds. Runoff from the entire area potentially used for hydropower exploitation was estimated using the parameter sets of the gauged sub-catchments. Additionally, snow melt from the ungauged areas was validated with satellite based snow cover images, revealing a robust simulation of snow melt in the entire area. Based on the hydrological modelling the total amount of snow melt and rainfall runoff available in Leirdalshraun and Hafralónsá amounts up to 700 M m3 a-1 and 1000 M m3 a-1, respectively. These results reveal that the total hydropower potential of the two sites amounts up to 1.2 TWh a-1 hydroelectricity, accounting for about 10% of the current production in Iceland. These result are of eminent importance to embed sustainable and resilient based water management in discussions concerning future plans of national energy production.
NASA Astrophysics Data System (ADS)
Arias, M. E.; Farinosi, F.; Lee, E.; Livino, A.; Moorcroft, P. R.
2016-12-01
Brazil is the 2nd largest hydropower producer in the world, and this energy source will continue to be a priority in the country for the foreseeable decades. Yet, climate change is expected to alter the country's hydrological regime, in particular in the Amazon where most new hydropower development is occurring. In order to better assess the potential of hydropower projects in decades to come, it is important to evaluate how future hydrological regimes will affect their performance and suitability. This study quantifies the impacts of climate change and land use conversion on hydropower generation, and identifies mechanisms that could help energy planners to account for future changes. Using the largest network of dams in Brazil's national portfolio within a single watershed, the Tapaj's River, this study connects global and regional future environmental projections to daily river flows and operations of 37 dams with an overall potential capacity of 29.4 GW. We found that climate change could decrease hydropower potential by 477-665 MW (-6 to -8% from historical conditions) during the dry season, a critical loss since dams are expected to operate at only one third of capacity during this perioddue to the limited reservoir volume of most projects in the Amazon lowlands. Furthermore, deforestation is expected to increase the inter-annual variability in hydropower potential from 2,798 for baseline conditions to 3,764-3,899 (+967-1102) MW under future scenarios for the 2040s. Consideration of future hydrological conditions on individual dams showed that the magnitude and uncertainty of losses could be greater than 30 MW -equivalent to the total potential of some dams in the inventory- in 11 of the projects studied. Future hydrological conditions could also delay the period when maximum daily generation occurs by 22-29 days, which could have important implications to energy planning in Brazil because these run-of-river dams would no longer be able to meet the country's seasonal peak demand. This information on future changes to individual dams' performance could feed directly into the project selection process in order to adapt designs and operations to ensure the greatest benefits and least impacts from hydropower in the long term.
NASA Astrophysics Data System (ADS)
Olivares, M. A.
2011-12-01
Hydropower accounts for about 50% of the installed capacity in Chile's Central Interconnected System (CIS) and new developments are envisioned in the near future. Large projects involving reservoirs are perceived negatively by the general public. In terms of operations, hydropower scheduling takes place at monthly, weekly, daily and hourly intervals, and operations at each level affect different environmental processes. Due to its ability to quickly and inexpensively respond to short-term changes in demand, hydropower reservoirs often are operated to provide power during periods of peak demand. This operational scheme, known as hydropeaking, changes the hydrologic regime by altering the rate and frequency of changes in flow magnitude on short time scales. To mitigate impacts on downstream ecosystems, operational constraints -typically minimum instream flows and maximum ramping rates- are imposed on hydropower plants. These operational restrictions limit reduce operational flexibility and can reduce the economic value of energy generation by imposing additional costs on the operation of interconnected power systems. Methods to predict the degree of hydrologic alteration rely on statistical analyses of instream flow time series. Typically, studies on hydrologic alteration use historical operational records for comparison between pre- and post-dam conditions. Efforts to assess hydrologic alteration based on future operational schemes of reservoirs are scarce. This study couples two existing models: a mid-term operations planning and a short-term economic dispatch to simulate short-term hydropower reservoir operations under different future scenarios. Scenarios of possible future configurations of the Chilean CIS are defined with emphasis on the introduction of non-conventional renewables (particularly wind energy) and large hydropower projects in Patagonia. Both models try to reproduce the actual decision making process in the Chilean Central Interconnected System (CIS). Chile's CIS is structured as a mandatory pool with audited costs and therefore the economic dispatch can be formulated as a cost minimization problem. Consequently, hydropower reservoir operations are controlled by the ISO. Reservoirs with the most potential to cause short-term hydrologic alteration were identified from existing operational records. These records have also been used to validate our simulated operations. Results in terms of daily and subdaily hydrologic alteration as well as the economic performance of the CIS are presented for alternative energy matrix scenarios. Tradeoff curves representing the compromise between indicators of hydrologic alteration and economic indicators of the CIS operation are developed.
Public Participation Guide: Proposed Popa Falls Hydropower Project, Okavango River, Namibia
The proposed hydropower project at Popa Falls case study illustrates the importance of carefully considering the scope of a public participation process when an environmental assessment is preliminary and when trans-boundary project impacts are a factor.
Climate impacts on hydropower and consequences for global electricity supply investment needs
Turner, Sean W. D.; Hejazi, Mohamad; Kim, Son H.; ...
2017-11-15
Climate change is projected to increase hydropower generation in some parts of the world and decrease it in others. Here we explore the possible consequences of these impacts for the electricity supply sector at the global scale. Regional hydropower projections are developed by forcing a coupled global hydrological and dam model with downscaled, bias-corrected climate realizations. Consequent impacts on power sector composition and associated emissions and investment costs are explored using the Global Change Assessment Model (GCAM). We find that climate-driven changes in hydropower generation may shift power demands onto and away from carbon intensive technologies. This then causes significantlymore » altered power sector CO 2 emissions in several hydro-dependent regions, although the net global impact is modest. For drying regions, we estimate a global, cumulative investment need of approximately one trillion dollars (±$500 billion) this century to make up for deteriorated hydropower generation caused by climate change. Total investments avoided are of a similar magnitude across regions projected to experience increased precipitation. Investment risks and opportunities are concentrated in hydro-dependent countries for which significant climate change is expected. Various countries throughout the Balkans, Latin America and Southern Africa are most vulnerable, whilst Norway, Canada, and Bhutan emerge as clear beneficiaries.« less
Regulation of snow-fed rivers affects flow regimes more than climate change.
Arheimer, B; Donnelly, C; Lindström, G
2017-07-05
River flow is mainly controlled by climate, physiography and regulations, but their relative importance over large landmasses is poorly understood. Here we show from computational modelling that hydropower regulation is a key driver of flow regime change in snow-dominated regions and is more important than future climate changes. This implies that climate adaptation needs to include regulation schemes. The natural river regime in snowy regions has low flow when snow is stored and a pronounced peak flow when snow is melting. Global warming and hydropower regulation change this temporal pattern similarly, causing less difference in river flow between seasons. We conclude that in snow-fed rivers globally, the future climate change impact on flow regime is minor compared to regulation downstream of large reservoirs, and of similar magnitude over large landmasses. Our study not only highlights the impact of hydropower production but also that river regulation could be turned into a measure for climate adaptation to maintain biodiversity on floodplains under climate change.Global warming and hydropower regulations are major threats to future fresh-water availability and biodiversity. Here, the authors show that their impact on flow regime over a large landmass result in similar changes, but hydropower is more critical locally and may have potential for climate adaptation in floodplains.
NASA Astrophysics Data System (ADS)
Lipiński, Seweryn; Olkowski, Tomasz
2017-10-01
The estimate of the cost of electro-mechanical equipment for new small hydropower plants most often amounts to about 30-40% of the total budget. In case of modernization of existing installations, this estimation represents the main cost. This matter constitutes a research problem for at least few decades. Many models have been developed for that purpose. The aim of our work was to collect and analyse formulas that allow estimation of the cost of investment in electro-mechanical equipment for small hydropower plants. Over a dozen functions were analysed. To achieve the aim of our work, these functions were converted into the form allowing their comparison. Then the costs were simulated with respect to plants' powers and net heads; such approach is novel and allows deeper discussion of the problem, as well as drawing broader conclusions. The following conclusions can be drawn: significant differences in results obtained by using various formulas were observed; there is a need for a wide study based on national investments in small hydropower plants that would allow to develop equations based on local data; the obtained formulas would let to determinate the costs of modernization or a new construction of small hydropower plant more precisely; special attention should be payed to formulas considering turbine type.
Climate impacts on hydropower and consequences for global electricity supply investment needs
DOE Office of Scientific and Technical Information (OSTI.GOV)
Turner, Sean W. D.; Hejazi, Mohamad; Kim, Son H.
Climate change is projected to increase hydropower generation in some parts of the world and decrease it in others. Here we explore the possible consequences of these impacts for the electricity supply sector at the global scale. Regional hydropower projections are developed by forcing a coupled global hydrological and dam model with downscaled, bias-corrected climate realizations. Consequent impacts on power sector composition and associated emissions and investment costs are explored using the Global Change Assessment Model (GCAM). We find that climate-driven changes in hydropower generation may shift power demands onto and away from carbon intensive technologies. This then causes significantlymore » altered power sector CO 2 emissions in several hydro-dependent regions, although the net global impact is modest. For drying regions, we estimate a global, cumulative investment need of approximately one trillion dollars (±$500 billion) this century to make up for deteriorated hydropower generation caused by climate change. Total investments avoided are of a similar magnitude across regions projected to experience increased precipitation. Investment risks and opportunities are concentrated in hydro-dependent countries for which significant climate change is expected. Various countries throughout the Balkans, Latin America and Southern Africa are most vulnerable, whilst Norway, Canada, and Bhutan emerge as clear beneficiaries.« less
NASA Astrophysics Data System (ADS)
Izat Rashed, Ghamgeen
2018-03-01
This paper presented a way of obtaining certain operating rules on time steps for the management of a large reservoir operation with a peak hydropower plant associated to it. The rules were allowed to have the form of non-linear regression equations which link a decision variable (here the water volume in the reservoir at the end of the time step) by several parameters influencing it. This paper considered the Dokan hydroelectric development KR-Iraq, which operation data are available for. It was showing that both the monthly average inflows and the monthly power demands are random variables. A model of deterministic dynamic programming intending the minimization of the total amount of the squares differences between the demanded energy and the generated energy is run with a multitude of annual scenarios of inflows and monthly required energies. The operating rules achieved allow the efficient and safe management of the operation and it is quietly and accurately known the forecast of the inflow and of the energy demand on the next time step.
James D. Haywood
2009-01-01
To study how fire or herbicide use influences longleaf pine (Pinus palustris Mill.) overstory and understory vegetation, five treatments were initiated in a 5â6-year-old longleaf pine stand: check, biennial arborescent plant control by directed herbicide application, and biennial burning in March, May, or July. The herbicide or prescribed fire...
Rein, David B; Wittenborn, John S; Zhang, Xinzhi; Allaire, Benjamin A; Song, Michael S; Klein, Ronald; Saaddine, Jinan B
2011-01-01
Objective To determine whether biennial eye evaluation or telemedicine screening are cost-effective alternatives to current recommendations for the estimated 10 million people aged 30–84 with diabetes but no or minimal diabetic retinopathy. Data Sources United Kingdom Prospective Diabetes Study, National Health and Nutrition Examination Survey, American Academy of Ophthalmology Preferred Practice Patterns, Medicare Payment Schedule. Study Design Cost-effectiveness Monte Carlo simulation. Data Collection/Extraction Methods Literature review, analysis of existing surveys. Principal Findings Biennial eye evaluation was the most cost-effective treatment option when the ability to detect other eye conditions was included in the model. Telemedicine was most cost-effective when other eye conditions were not considered or when telemedicine was assumed to detect refractive error. The current annual eye evaluation recommendation was costly compared with either treatment alternative. Self-referral was most cost-effective up to a willingness to pay (WTP) of U.S.$37,600, with either biennial or annual evaluation most cost-effective at higher WTP levels. Conclusions Annual eye evaluations are costly and add little benefit compared with either plausible alternative. More research on the ability of telemedicine to detect other eye conditions is needed to determine whether it is more cost-effective than biennial eye evaluation. PMID:21492158
NASA Astrophysics Data System (ADS)
Mehta, V. K.; Purkey, D. R.; Young, C.; Joyce, B.; Yates, D.
2008-12-01
Rivers draining western slopes of the Sierra Nevada provide critical water supply, hydropower, fisheries and recreation services to California. Coordinated efforts are under way to better characterize and model the possible impacts of climate change on Sierra Nevada hydrology. Research suggests substantial end-of- century reductions in Sierra Nevada snowpack and a shift in the center of mass of the snowmelt hydrograph. Management decisions, land use change and population growth add further complexity, necessitating the use of scenario-based modeling tools. The Water Evaluation and Planning (WEAP) system is one of the suite of tools being employed in this effort. Unlike several models that rely on perturbation of historical runoff data to simulate future climate conditions, WEAP includes a dynamically integrated watershed hydrology module that is forced by input climate time series. This allows direct simulation of water management response to climate and land use change. This paper presents ABY2008, a WEAP application for the Yuba, Bear and American River (ABY) watersheds of the Sierra Nevada. These rivers are managed by water agencies and hydropower utilities through a complex network of reservoirs, dams, hydropower plants and water conveyances. Historical watershed hydrology in ABY2008 is driven by a 10 year weekly climate time series from 1991-2000. Land use and soils data were combined into 12 landclasses representing each of 324 hydrological response units. Hydrologic parameters were incorporated from a calibration against observed streamflow developed for the entire western Sierra. Physical reservoir data, operating rules, and water deliveries to water agencies were obtained from public documents of water agencies and power utilities that manage facilities in the watersheds. ABY2008 includes 25 major reservoirs, 39 conveyances, 33 hydropower plants and 14 transmission links to 13 major water demand points. In WEAP, decisions for transferring water at diversion points from rivers to facilities are based on assigned priorities. Priorities in ABY2008 follow Federal Energy Regulatory Commission license requirements and power purchase agreements between licensees and water/power contractors. These generally allocate water according to the following priorities - (i) maintaining minimum instream flows below diversions;(ii) irrigation and domestic consumptive water demands; and (iii) power generation. ABY2008 simulations compared well with historical annual and monthly hydropower generation. Annual hydropower for 31 hydropower plants was simulated with r2=0.85 and ste=58 GWh. Monthly hydropower for 21 power plants owned by three water agencies were simulated with r2= 0.74 and ste= 7.4 GWh. We also present early results on how climate change, manifest by increasing weekly average temperatures, translates into changes in the projected timing of runoff and patterns of snow accumulation. Consequent changes in met water supply demands and hydropower generated are discussed. Further, stakeholders in the northern Sierra seek to use ABY2008 to investigate management scenarios geared towards increased conservation flows for fish populations, and the possible tradeoffs thereof with hydropower and water supply. These applications with ABY2008 illustrate the substantial utility of scenario-based modeling with the WEAP system.
Regulatory approaches for addressing dissolved oxygen concerns at hydropower facilities
DOE Office of Scientific and Technical Information (OSTI.GOV)
Peterson, Mark J.; Cada, Glenn F.; Sale, Michael J.
Low dissolved oxygen (DO) concentrations are a common water quality problem downstream of hydropower facilities. At some facilities, structural improvements (e.g. installation of weir dams or aerating turbines) or operational changes (e.g., spilling water over the dam) can be made to improve DO levels. In other cases, structural and operational approaches are too costly for the project to implement or are likely to be of limited effectiveness. Despite improvements in overall water quality below dams in recent years, many hydropower projects are unable to meet state water quality standards for DO. Regulatory agencies in the U.S. are considering or implementingmore » dramatic changes in their approach to protecting the quality of the Nation’s waters. New policies and initiatives have emphasized flexibility, increased collaboration and shared responsibility among all parties, and market-based, economic incentives. The use of new regulatory approaches may now be a viable option for addressing the DO problem at some hydropower facilities. This report summarizes some of the regulatory-related options available to hydropower projects, including negotiation of site-specific water quality criteria, use of biological monitoring, watershed-based strategies for the management of water quality, and watershed-based trading. Key decision points center on the health of the local biological communities and whether there are contributing impacts (i.e., other sources of low DO effluents) in the watershed. If the biological communities downstream of the hydropower project are healthy, negotiation for site-specific water quality standards or biocriteria (discharge performance criteria based on characteristics of the aquatic biota) might be pursued. If there are other effluent dischargers in the watershed that contribute to low DO problems, watershed-scale strategies and effluent trading may be effective. This report examines the value of regulatory approaches by reviewing their use in other« less
Along-the-net reconstruction of hydropower potential with consideration of anthropic alterations
NASA Astrophysics Data System (ADS)
Masoero, A.; Claps, P.; Gallo, E.; Ganora, D.; Laio, F.
2014-09-01
Even in regions with mature hydropower development, requirements for stable renewable power sources suggest revision of plans of exploitation of water resources, while taking care of the environmental regulations. Mean Annual Flow (MAF) is a key parameter when trying to represent water availability for hydropower purposes. MAF is usually determined in ungauged basins by means of regional statistical analysis. For this study a regional estimation method consistent along-the-river network has been developed for MAF estimation; the method uses a multi-regressive approach based on geomorphoclimatic descriptors, and it is applied on 100 gauged basins located in NW Italy. The method has been designed to keep the estimates of mean annual flow congruent at the confluences, by considering only raster-summable explanatory variables. Also, the influence of human alterations in the regional analysis of MAF has been studied: impact due to the presence of existing hydropower plants has been taken into account, restoring the "natural" value of runoff through analytical corrections. To exemplify the representation of the assessment of residual hydropower potential, the model has been applied extensively to two specific mountain watersheds by mapping the estimated mean flow for the basins draining into each pixel of a the DEM-derived river network. Spatial algorithms were developed using the OpenSource Software GRASS GIS and PostgreSQL/PostGIS. Spatial representation of the hydropower potential was obtained using different mean flow vs hydraulic-head relations for each pixel. Final potential indices have been represented and mapped through the Google Earth platform, providing a complete and interactive picture of the available potential, useful for planning and regulation purposes.
A workshop on leadership for senior MD–PhD students
Meador, Catherine B.; Parang, Bobak; Musser, Melissa A.; Haliyur, Rachana; Owens, David A.; Dermody, Terence S.
2016-01-01
Leadership skills are essential for a successful career as a physician-scientist, yet many MD–PhD training programs do not offer formal training in leadership. The Vanderbilt Medical Scientist Training Program (MSTP) previously established a 2-day leadership workshop that has been held biennially since 2006 for students in the first and second years of the graduate school portion of combined MD and PhD training (G1/G2 students). Workshop attendees have consistently rated this workshop as a highly effective experience. However, opportunities for structured training in leadership competencies during the subsequent 3–5 years of MD–PhD training are limited. Given the success of the G1/G2 leadership workshop and the need for continuity in this model of leadership training, we developed a half-day workshop for MSTP students in the clinical years of medical school (M3/M4 students) to foster continued training in leadership. Our workshop curriculum, based in part on original cases drafted by Vanderbilt MSTP students, provides concrete strategies to manage conflict and navigate leadership transitions in the physician-scientist career path. The curriculum emphasizes both short-term competencies, such as effective participation as a member of a clinical team, and long-term competencies, such as leadership of a research team, division, or department. Our inaugural senior leadership workshop, held in August, 2015, was judged by student participants to be well organized and highly relevant to leadership concepts and skills. It will be offered biennially in our training curriculum for M3 and M4 MSTP students. PMID:27499363
A workshop on leadership for senior MD-PhD students.
Meador, Catherine B; Parang, Bobak; Musser, Melissa A; Haliyur, Rachana; Owens, David A; Dermody, Terence S
2016-01-01
Leadership skills are essential for a successful career as a physician-scientist, yet many MD-PhD training programs do not offer formal training in leadership. The Vanderbilt Medical Scientist Training Program (MSTP) previously established a 2-day leadership workshop that has been held biennially since 2006 for students in the first and second years of the graduate school portion of combined MD and PhD training (G1/G2 students). Workshop attendees have consistently rated this workshop as a highly effective experience. However, opportunities for structured training in leadership competencies during the subsequent 3-5 years of MD-PhD training are limited. Given the success of the G1/G2 leadership workshop and the need for continuity in this model of leadership training, we developed a half-day workshop for MSTP students in the clinical years of medical school (M3/M4 students) to foster continued training in leadership. Our workshop curriculum, based in part on original cases drafted by Vanderbilt MSTP students, provides concrete strategies to manage conflict and navigate leadership transitions in the physician-scientist career path. The curriculum emphasizes both short-term competencies, such as effective participation as a member of a clinical team, and long-term competencies, such as leadership of a research team, division, or department. Our inaugural senior leadership workshop, held in August, 2015, was judged by student participants to be well organized and highly relevant to leadership concepts and skills. It will be offered biennially in our training curriculum for M3 and M4 MSTP students.
Wind-Driven Ecological Flow Regimes Downstream from Hydropower Dams
NASA Astrophysics Data System (ADS)
Kern, J.; Characklis, G. W.
2012-12-01
Conventional hydropower can be turned on and off quicker and less expensively than thermal generation (coal, nuclear, or natural gas). These advantages enable hydropower utilities to respond to rapid fluctuations in energy supply and demand. More recently, a growing renewable energy sector has underlined the need for flexible generation capacity that can complement intermittent renewable resources such as wind power. While wind power entails lower variable costs than other types of generation, incorporating it into electric power systems can be problematic. Due to variable and unpredictable wind speeds, wind power is difficult to schedule and must be used when available. As a result, integrating large amounts of wind power into the grid may result in atypical, swiftly changing demand patterns for other forms of generation, placing a premium on sources that can be rapidly ramped up and down. Moreover, uncertainty in wind power forecasts will stipulate increased levels of 'reserve' generation capacity that can respond quickly if real-time wind supply is less than expected. These changes could create new hourly price dynamics for energy and reserves, altering the short-term financial signals that hydroelectric dam operators use to schedule water releases. Traditionally, hourly stream flow patterns below hydropower dams have corresponded in a very predictable manner to electricity demand, whose primary factors are weather (hourly temperature) and economic activity (workday hours). Wind power integration has the potential to yield more variable, less predictable flows at hydro dams, flows that at times could resemble reciprocal wind patterns. An existing body of research explores the impacts of standard, demand-following hydroelectric dams on downstream ecological flows; but weighing the benefits of increased reliance on wind power against further impacts to ecological flows may be a novel challenge for the environmental community. As a preliminary step in meeting this challenge, the following study was designed to investigate the potential for wind power integration to alter riparian flow regimes below hydroelectric dams. A hydrological model of a three-dam cascade in the Roanoke River basin (Virginia, USA) is interfaced with a simulated electricity market (i.e. a unit commitment problem) representing the Dominion Zone of PJM Interconnection. Incorporating forecasts of electricity demand, hydro capacity and wind availability, a mixed-integer optimization program minimizes the system cost of meeting hourly demand and reserve requirements by means of a diverse generation portfolio (e.g. nuclear, fossil, hydro, and biomass). A secondary 'balancing' energy market is executed if real-time wind generation is less than the day-ahead forecast, calling upon reserved generation resources to meet the supply shortfall. Hydropower release schedules are determined across a range of wind development scenarios (varying wind's fraction of total installed generating capacity, as well as its geographical source region). Flow regimes for each wind development scenario are compared against both historical and simulated flows under current operations (negligible wind power), as well as simulated natural flows (dam removal), in terms of ecologically relevant flow metrics. Results quantify the ability of wind power development to alter within-week stream flows downstream from hydropower dams.
Climate Change Impacts and Greenhouse Gas Mitigation Effects on U.S. Hydropower Generation
Climate change will have potentially significant effects on hydropower generation due to changes in the magnitude and seasonality of river runoff and increases in reservoir evaporation. These physical impacts will in turn have economic consequences through both producer revenues ...
77 FR 64106 - Renewable Energy and Energy Efficiency Trade Policy Mission to Chile
Federal Register 2010, 2011, 2012, 2013, 2014
2012-10-18
... competitiveness of U.S. wind, solar, geothermal, biomass, hydropower, waste-to-energy, smart grid, and energy... development. Opportunities are expected in the wind, solar, geothermal, biomass, hydropower, and energy... DEPARTMENT OF COMMERCE International Trade Administration Renewable Energy and Energy Efficiency...
DOE Office of Scientific and Technical Information (OSTI.GOV)
Kroposki, Benjamin; Johnson, Brian; Zhang, Yingchen
What does it mean to achieve a 100% renewable grid? Several countries already meet or come close to achieving this goal. Iceland, for example, supplies 100% of its electricity needs with either geothermal or hydropower. Other countries that have electric grids with high fractions of renewables based on hydropower include Norway (97%), Costa Rica (93%), Brazil (76%), and Canada (62%). Hydropower plants have been used for decades to create a relatively inexpensive, renewable form of energy, but these systems are limited by natural rainfall and geographic topology. Around the world, most good sites for large hydropower resources have already beenmore » developed. So how do other areas achieve 100% renewable grids? Variable renewable energy (VRE), such as wind and solar photovoltaic (PV) systems, will be a major contributor, and with the reduction in costs for these technologies during the last five years, large-scale deployments are happening around the world.« less
Sarasúa, José Ignacio; Elías, Paz; Martínez-Lucas, Guillermo; Pérez-Díaz, Juan Ignacio; Wilhelmi, José Román; Sánchez, José Ángel
2014-01-01
Run-of-river hydropower plants usually lack significant storage capacity; therefore, the more adequate control strategy would consist of keeping a constant water level at the intake pond in order to harness the maximum amount of energy from the river flow or to reduce the surface flooded in the head pond. In this paper, a standard PI control system of a run-of-river diversion hydropower plant with surge tank and a spillway in the head pond that evacuates part of the river flow plant is studied. A stability analysis based on the Routh-Hurwitz criterion is carried out and a practical criterion for tuning the gains of the PI controller is proposed. Conclusions about the head pond and surge tank areas are drawn from the stability analysis. Finally, this criterion is applied to a real hydropower plant in design state; the importance of considering the spillway dimensions and turbine characteristic curves for adequate tuning of the controller gains is highlighted.
Sarasúa, José Ignacio; Elías, Paz; Wilhelmi, José Román; Sánchez, José Ángel
2014-01-01
Run-of-river hydropower plants usually lack significant storage capacity; therefore, the more adequate control strategy would consist of keeping a constant water level at the intake pond in order to harness the maximum amount of energy from the river flow or to reduce the surface flooded in the head pond. In this paper, a standard PI control system of a run-of-river diversion hydropower plant with surge tank and a spillway in the head pond that evacuates part of the river flow plant is studied. A stability analysis based on the Routh-Hurwitz criterion is carried out and a practical criterion for tuning the gains of the PI controller is proposed. Conclusions about the head pond and surge tank areas are drawn from the stability analysis. Finally, this criterion is applied to a real hydropower plant in design state; the importance of considering the spillway dimensions and turbine characteristic curves for adequate tuning of the controller gains is highlighted. PMID:25405237
Watering Down Barriers to Using Hydropower through Fisheries Research
DOE Office of Scientific and Technical Information (OSTI.GOV)
Ham, Ken
Much of our work on clean energy is targeted at improving performance of hydropower, the largest source of renewable energy in the Pacific Northwest and the nation. PNNL experts in hydropower—from computer scientists to biologists and engineers—are helping to optimize the efficiency and environmental performance of hydroelectric plants. The Columbia River is the nation’s most important hydropower resource, producing 40 percent of the nation’s hydroelectric generation and up to 70 percent of the region’s power. At PNNL, Fisheries Biologist Ken Ham and others are working with stakeholders in the Pacific Northwest, the Army Corps of Engineers and DOE to ensuremore » that this resource continues to provide its many benefits while setting a new standard for environmental sustainability. As aging turbines are replaced in existing hydropower dams, computational modeling and state-of-the-art fisheries research combine to aid the design of a next-generation hydro turbine that meets or exceeds current biological performance standards and produces more power.« less
Exemplary Design Envelope Specification for Standard Modular Hydropower Technology
DOE Office of Scientific and Technical Information (OSTI.GOV)
Witt, Adam M.; Smith, Brennan T.; Tsakiris, Achilleas
Hydropower is an established, affordable renewable energy generation technology supplying nearly 18% of the electricity consumed globally. A hydropower facility interacts continuously with the surrounding water resource environment, causing alterations of varying magnitude in the natural flow of water, energy, fish, sediment, and recreation upstream and downstream. A universal challenge in facility design is balancing the extraction of useful energy and power system services from a stream with the need to maintain ecosystem processes and natural environmental function. On one hand, hydroelectric power is a carbon-free, renewable, and flexible asset to the power system. On the other, the disruption ofmore » longitudinal connectivity and the artificial barrier to aquatic movement created by hydraulic structures can produce negative impacts that stress fresh water environments. The growing need for carbon-free, reliable, efficient distributed energy sources suggests there is significant potential for hydropower projects that can deploy with low installed costs, enhanced ecosystem service offerings, and minimal disruptions of the stream environment.« less
A new framework for sustainable hydropower development project
NASA Astrophysics Data System (ADS)
Johan, Kartina; Turan, Faiz Mohd; Gani, Nur Syazwani Abdul
2018-03-01
This project studies on the establishment of a new framework for sustainable hydropower development. A hydropower development is listed as one of the prescribed activities under the Environmental Quality Order 1987. Thus, Environmental Impact Assessment (EIA) guidelines must be referred to comply with the Department of Environment (DoE) requirements. In order to execute EIA, an assessment tool that will be utilized in the final evaluation phase must be determined. The selected assessment tool that will be used is Systematic Sustainability Assessment(SSA) which is a new integrated tool to evaluate the sustainability performance. A pilot run is conducted in five different departments within the Energy Company to validate the efficiency of the SSA tool. The parameters to be evaluated are constructed aligned with the Sustainable Development Goals (SDG) to maintain the sustainability features. Consequently, the performance level of the sustainability with respect to People, Planet and Profit (3P’s) is able to be discovered during evaluation phase in the hydropower development for continuous improvement.
Development of the cycloidal propeller StECon as a new small hydropower plant for kinetic energy
NASA Astrophysics Data System (ADS)
Schmidt, J.; Jensen, J.; Wieland, J.; Lohr, W.; Metzger, J.; Stiller, H.-L.
2016-11-01
The StECon (Stiller Energy Converter) is a promising new small hydropower plant for kinetic energy. It is an invention of Mr. Hans-Ludwig Stiller and has several advantages compared to the technologies for the use of hydropower known for millennia. It runs completely submerged forwards and backwards, with horizontal or vertical axis and has a compact design by using a single or a double-sided planetary gear with optimum alignment to the flow direction. The possible applications include mobile and stationary tide and current generators as well as hybrid solutions, either as a generator or as a propulsion system. The high expectations have to be confirmed in a research project StEwaKorad at the University of Siegen. Aim of this research project is to investigate the performance and characteristics of the StECon as an energy converter for producing renewable energy from hydropower with low fall heights including sea currents.
A geospatial assessment of mini/small hydropower potential in Sub-Saharan Africa
NASA Astrophysics Data System (ADS)
Korkovelos, Alexandros; Mentis, Dimitrios; Hussain Siyal, Shahid; Arderne, Christopher; Beck, Hylke; de Roo, Ad; Howells, Mark
2017-04-01
Sub-Saharan Africa has been the epicenter of ongoing global dialogues around energy poverty and justifiably so. More than half of the world's unserved population lives there. At the same time, a big part of the continent is privileged with plentiful renewable energy resources. Hydropower is one of them and to a large extent it remains untapped. This study focuses on the technical assessment of small-scale hydropower (0.01-10 MW) in Sub-Saharan Africa. The underlying methodology was based on open source geospatial datasets, whose combination allowed a consistent evaluation of 712,615 km of river network spanning over 44 countries. Environmental, topological and social constraints were included in the form of geospatial restrictions to help preserve the natural wealth and promote sustainable development. The results revealed that small-scale hydropower could cover 8.5-12.5% of the estimated electricity demand in 2030, thus making it a viable option to support electrification efforts in the region.
Treatise on water hammer in hydropower standards and guidelines
NASA Astrophysics Data System (ADS)
Bergant, A.; Karney, B.; Pejović, S.; Mazij, J.
2014-03-01
This paper reviews critical water hammer parameters as they are presented in official hydropower standards and guidelines. A particular emphasize is given to a number of IEC standards and guidelines that are used worldwide. The paper critically assesses water hammer control strategies including operational scenarios (closing and opening laws), surge control devices (surge tank, pressure regulating valve, flywheel, etc.), redesign of the water conveyance system components (tunnel, penstock), or limitation of operating conditions (limited operating range) that are variably covered in standards and guidelines. Little information is given on industrial water hammer models and solutions elsewhere. These are briefly introduced and discussed in the light of capability (simple versus complex systems), availability of expertise (in house and/or commercial) and uncertainty. The paper concludes with an interesting water hammer case study referencing the rules and recommendations from existing hydropower standards and guidelines in a view of effective water hammer control. Recommendations are given for further work on development of a special guideline on water hammer (hydraulic transients) in hydropower plants.
Hydropower generation, flood control and dam cascades: A national assessment for Vietnam
NASA Astrophysics Data System (ADS)
Nguyen-Tien, Viet; Elliott, Robert J. R.; Strobl, Eric A.
2018-05-01
Vietnam is a country with diverse terrain and climatic conditions and a dependency on hydropower for a significant proportion of its power needs and as such, is particularly vulnerable to changes in climate. In this paper we apply SWAT (Soil and Water Assessment Tool) derived discharge simulation results coupled with regression analysis to estimate the performance of hydropower plants for Vietnam between 1995 and mid-2014 when both power supply and demand increased rapidly. Our approach is to examine the watershed formed from three large inter-boundary basins: The Red River, the Vietnam Coast and the Lower Mekong River, which have a total area of 977,964 km2. We then divide this area into 7,887 sub-basins with an average area of 131.6 km2 (based on level 12 of HydroSHEDS/HydroBASINS datasets) and 53,024 Hydrological Response Units (HRUs). Next we simulate river flow for the 40 largest hydropower plants across Vietnam. Our validation process demonstrates that the simulated flows are significantly correlated with the gauged inflows into these dams and are able to serve as a good proxy for the inflows into hydropower dams in our baseline energy regression, which captures 87.7% of the variation in monthly power generation. In other results we estimate that large dams sacrifice on average around 18.2% of their contemporaneous production for the purpose of flood control. When we assess Vietnam's current alignment of dams we find that the current cascades of large hydropower dams appear to be reasonably efficient: each MWh/day increase in upstream generation adds 0.146 MWh/day to downstream generation. The study provides evidence for the multiple benefits of a national system of large hydropower dams using a cascade design. Such a system may help overcome future adverse impacts from changes in climate conditions. However, our results show that there is still room for improvement in the harmonization of cascades in some basins. Finally, possible adverse hydro-ecological impacts due to the proliferation of large upstream dams, including those located beyond Vietnam's border, need to be carefully considered.
NASA Astrophysics Data System (ADS)
Arias, M. E.; Piman, T.; Lauri, H.; Cochrane, T. A.; Kummu, M.
2014-12-01
River tributaries have a key role in the biophysical functioning of the Mekong Basin. Of particular interest are the Sesan, Srepok, and Sekong (3S) rivers, which contribute nearly a quarter of the total Mekong discharge. Forty two dams are proposed in the 3S, and once completed they will exceed the active storage of China's large dam cascade in the Upper Mekong. Given their proximity to the Lower Mekong floodplains, the 3S dams could alter the flood-pulse hydrology driving the productivity of downstream ecosystems. Therefore, the main objective of this study was to quantify how hydropower development in the 3S, together with definite future (DF) plans for infrastructure development through the basin, would alter the hydrology of the Tonle Sap's Floodplain, the largest wetland in the Mekong and home to one of the most productive inland fisheries in the world. We coupled results from four numerical models representing the basin's surface hydrology, water resources development, and floodplain hydrodynamics. The scale of alterations caused by hydropower in the 3S was compared with the basin's DF scenario driven by the Upper Mekong dam cascade. The DF or the 3S development scenarios could independently increase Tonle Sap's 30-day minimum water levels by 30 ± 5 cm and decrease annual water level fall rates by 0.30 ± 0.05 cm day-1. When analyzed together (DF + 3S), these scenarios are likely to eliminate all baseline conditions (1986-2000) of extreme low water levels, a particularly important component of Tonle Sap's environmental flows. Given the ongoing trends and large economic incentives in the hydropower business in the region, there is a high possibility that most of the 3S hydropower potential will be exploited and that dams will be built even in locations where there is a high risk of ecological disruption. Hence, retrofitting current designs and operations to promote sustainable hydropower practices that optimize multiple river services - rather than just maximize hydropower generation - appear to be the most feasible alternative to mitigate hydropower-related disruptions in the Mekong.
NASA Astrophysics Data System (ADS)
Arias, M. E.; Piman, T.; Lauri, H.; Cochrane, T. A.; Kummu, M.
2014-02-01
River tributaries have a key role in the biophysical functioning of the Mekong Basin. Of particular attention are the Sesan, Srepok, and Sekong (3S) rivers, which contribute nearly a quarter of the total Mekong discharge. Forty two dams are proposed in the 3S, and once completed they will exceed the active storage of China's large dam cascade in the upper Mekong. Given their proximity to the lower Mekong floodplains, the 3S dams could alter the flood-pulse hydrology driving the productivity of downstream ecosystems. Therefore, the main objective of this study was to quantify how hydropower development in the 3S would alter the hydrology of the Tonle Sap floodplain, the largest wetland in the Mekong and home to one of the most productive inland fisheries in the world. We coupled results from four numerical models representing the basin's surface hydrology, water resources development, and floodplain hydrodynamics. The scale of alterations caused by hydropower in the 3S was compared with the basin's definite future development scenario (DF) driven by the upper Mekong dam cascade. The DF or the 3S development scenarios could independently increase Tonle Sap's 30 day minimum water levels by 30 ± 5 cm and decrease annual water level fall rates by 0.30 ± 0.05 cm d-2. When analyzed together (DF + 3S), these scenarios are likely to eliminate all baseline conditions (1986-2000) of extreme low water levels, a particularly important component of Tonle Sap's environmental flows. Given the ongoing trends and large economic incentives in the hydropower business in the region, there is a high possibility that most of the 3S hydropower potential will actually be exploited and that dams would be built even in locations where there is a high risk of ecological disruptions. Hence, retrofitting current designs and operations to promote sustainable hydropower practices that optimize multiple river services - rather than just maximize hydropower generation - appear to be the most feasible alternative to mitigate hydropower-related disruptions in the Mekong.
Projected impacts of climate change on hydropower potential in China
DOE Office of Scientific and Technical Information (OSTI.GOV)
Liu, Xingcai; Tang, Qiuhong; Voisin, Nathalie
Hydropower is an important renewable energy source in China, but it is sensitive to climate change, because the changing climate may alter hydrological conditions (e.g., river flow and reservoir storage). Future changes and associated uncertainties in China's gross hydropower potential (GHP) and developed hydropower potential (DHP) are projected using simulations from eight global hydrological models (GHMs), including a large-scale reservoir regulation model, forced by five general circulation models (GCMs) with climate data under two representative concentration pathways (RCP2.6 and RCP8.5). Results show that the estimation of the present GHP of China is comparable to other studies; overall, the annual GHP is projectedmore » to change by −1.7 to 2 % in the near future (2020–2050) and increase by 3 to 6 % in the late 21st century (2070–2099). The annual DHP is projected to change by −2.2 to −5.4 % (0.7–1.7 % of the total installed hydropower capacity (IHC)) and −1.3 to −4 % (0.4–1.3 % of total IHC) for 2020–2050 and 2070–2099, respectively. Regional variations emerge: GHP will increase in northern China but decrease in southern China – mostly in south central China and eastern China – where numerous reservoirs and large IHCs currently are located. The area with the highest GHP in southwest China will have more GHP, while DHP will reduce in the regions with high IHC (e.g., Sichuan and Hubei) in the future. The largest decrease in DHP (in %) will occur in autumn or winter, when streamflow is relatively low and water use is competitive. Large ranges in hydropower estimates across GHMs and GCMs highlight the necessity of using multimodel assessments under climate change conditions. This study prompts the consideration of climate change in planning for hydropower development and operations in China, to be further combined with a socioeconomic analysis for strategic expansion.« less
NASA Astrophysics Data System (ADS)
Mainardi Fan, Fernando; Schwanenberg, Dirk; Alvarado, Rodolfo; Assis dos Reis, Alberto; Naumann, Steffi; Collischonn, Walter
2016-04-01
Hydropower is the most important electricity source in Brazil. During recent years, it accounted for 60% to 70% of the total electric power supply. Marginal costs of hydropower are lower than for thermal power plants, therefore, there is a strong economic motivation to maximize its share. On the other hand, hydropower depends on the availability of water, which has a natural variability. Its extremes lead to the risks of power production deficits during droughts and safety issues in the reservoir and downstream river reaches during flood events. One building block of the proper management of hydropower assets is the short-term forecast of reservoir inflows as input for an online, event-based optimization of its release strategy. While deterministic forecasts and optimization schemes are the established techniques for the short-term reservoir management, the use of probabilistic ensemble forecasts and stochastic optimization techniques receives growing attention and a number of researches have shown its benefit. The present work shows one of the first hindcasting and closed-loop control experiments for a multi-purpose hydropower reservoir in a tropical region in Brazil. The case study is the hydropower project (HPP) Três Marias, located in southeast Brazil. The HPP reservoir is operated with two main objectives: (i) hydroelectricity generation and (ii) flood control at Pirapora City located 120 km downstream of the dam. In the experiments, precipitation forecasts based on observed data, deterministic and probabilistic forecasts with 50 ensemble members of the ECMWF are used as forcing of the MGB-IPH hydrological model to generate streamflow forecasts over a period of 2 years. The online optimization depends on a deterministic and multi-stage stochastic version of a model predictive control scheme. Results for the perfect forecasts show the potential benefit of the online optimization and indicate a desired forecast lead time of 30 days. In comparison, the use of actual forecasts with shorter lead times of up to 15 days shows the practical benefit of actual operational data. It appears that the use of stochastic optimization combined with ensemble forecasts leads to a significant higher level of flood protection without compromising the HPP's energy production.
NASA Technical Reports Server (NTRS)
van Vliet, M. T. H.; van Beek, L. P. H.; Eisener, S.; Wada, Y.; Bierkens, M. F. P.
2016-01-01
Worldwide, 98% of total electricity is currently produced by thermoelectric power and hydropower. Climate change is expected to directly impact electricity supply, in terms of both water availability for hydropower generation and cooling water usage for thermoelectric power. Improved understanding of how climate change may impact the availability and temperature of water resources is therefore of major importance. Here we use a multi-model ensemble to show the potential impacts of climate change on global hydropower and cooling water discharge potential. For the first time, combined projections of streamflow and water temperature were produced with three global hydrological models (GHMs) to account for uncertainties in the structure and parametrization of these GHMs in both water availability and water temperature. The GHMs were forced with bias-corrected output of five general circulation models (GCMs) for both the lowest and highest representative concentration pathways (RCP2.6 and RCP8.5). The ensemble projections of streamflow and water temperature were then used to quantify impacts on gross hydropower potential and cooling water discharge capacity of rivers worldwide. We show that global gross hydropower potential is expected to increase between +2.4% (GCM-GHM ensemble mean for RCP 2.6) and +6.3% (RCP 8.5) for the 2080s compared to 1971-2000. The strongest increases in hydropower potential are expected for Central Africa, India, central Asia and the northern high-latitudes, with 18-33% of the world population living in these areas by the 2080s. Global mean cooling water discharge capacity is projected to decrease by 4.5-15% (2080s). The largest reductions are found for the United States, Europe, eastern Asia, and southern parts of South America, Africa and Australia, where strong water temperature increases are projected combined with reductions in mean annual streamflow. These regions are expected to affect 11-14% (for RCP2.6 and the shared socioeconomic pathway (SSP)1, SSP2, SSP4) and 41-51% (RCP8.5-SSP3, SSP5) of the world population by the 2080s.
A modeling tool to support decision making in future hydropower development in Chile
NASA Astrophysics Data System (ADS)
Vicuna, S.; Hermansen, C.; Cerda, J. P.; Olivares, M. A.; Gomez, T. I.; Toha, E.; Poblete, D.; Mao, L.; Falvey, M. J.; Pliscoff, P.; Melo, O.; Lacy, S.; Peredo, M.; Marquet, P. A.; Maturana, J.; Gironas, J. A.
2017-12-01
Modeling tools support planning by providing transparent means to assess the outcome of natural resources management alternatives within technical frameworks in the presence of conflicting objectives. Such tools, when employed to model different scenarios, complement discussion in a policy-making context. Examples of practical use of this type of tool exist, such as the Canadian public forest management, but are not common, especially in the context of developing countries. We present a tool to support the selection from a portfolio of potential future hydropower projects in Chile. This tool, developed by a large team of researchers under the guidance of the Chilean Energy Ministry, is especially relevant in the context of evident regionalism, skepticism and change in societal values in a country that has achieved a sustained growth alongside increased demands from society. The tool operates at a scale of a river reach, between 1-5 km long, on a domain that can be defined according to the scale needs of the related discussion, and its application can vary from river basins to regions or other spatial configurations that may be of interest. The tool addresses both available hydropower potential and the existence (inferred or observed) of other ecological, social, cultural and productive characteristics of the territory which are valuable to society, and provides a means to evaluate their interaction. The occurrence of each of these other valuable characteristics in the territory is measured by generating a presence-density score for each. Considering the level of constraint each characteristic imposes on hydropower development, they are weighted against each other and an aggregate score is computed. With this information, optimal trade-offs are computed between additional hydropower capacity and valuable local characteristics over the entire domain, using the classical knapsack 0-1 optimization algorithm. Various scenarios of different weightings and hydropower development targets are tested and compared. The results illustrate the capabilities of the tool to identify promising hydropower development strategies and to aid public policy discussions aimed at establishing incentives and regulations, and therefore provide decision makers with supporting material allowing a more informed discussion.
Climate Vulnerability of Hydro-power infrastructure in the Eastern African Power Pool
NASA Astrophysics Data System (ADS)
Sridharan, Vignesh
2017-04-01
At present there is around 6000 MW of installed hydropower capacity in the Eastern African power pool (EAPP)[1]. With countries aggressively planning to achieve the Sustainable development goal (SDG) of ensuring access to affordable electricity for all, a three-fold increase in hydropower capacity is expected by 2040 [1]. Most of the existing and planned infrastructure lie inside the Nile River Basin. The latest assessment report (AR 5) from the Intergovernmental Panel on Climate Change (IPCC) indicates a high level of climatic uncertainty in the Nile Basin. The Climate Moisture index (CMI) for the Eastern Nile region and the Nile Equatorial lakes varies significantly across the different General Circulation Models (GCM)[2]. Such high uncertainty casts a shadow on the plans to expand hydropower capacity, doubting whether hydropower expansion can contribute to the goal of improving access to electricity or end up as sunk investments. In this assessment, we analyze adaptation strategies for national energy systems in the Eastern African Power Pool (EAPP), which minimize the regret that could potentially arise from impacts of a changed climate. An energy systems model of the EAPP is developed representing national electricity supply infrastructure. Cross border transmission and hydropower infrastructure is defined at individual project level. The energy systems model is coupled with a water systems management model of the Nile River Basin that calculates the water availability at different hydropower infrastructures under a range of climate scenarios. The results suggest that a robust adaptation strategy consisting of investments in cross border electricity transmission infrastructure and diversifying sources of electricity supply will require additional investments of USD 4.2 billion by 2050. However, this leads to fuel and operational cost savings of up to USD 22.6 billion, depending on the climate scenario. [1] "Platts, 2016. World Electric Power Plants Database," World Electric Power Plants Database. [Online]. Available: http://www.platts.com/Products/worldelectricpowerplantsdatabase. [Accessed: 01-Mar-2016]. [2] Brent Boehlert, Kenneth M. Strzepek, David Groves, and Bruce Hewitson, Chris Jack, "Climate Change Projections in Africa-Chapter 3," in Enhancing the Climate Resilience of Africa's Infrastructure : The Power and Water Sectors, Washington DC: The World Bank, 2016, p. 219.
ERIC Educational Resources Information Center
Foster, Emery M.; Herlihy, Lester B.; Comstock, Lula M.; Isdell, Julia E.; Deffenbaugh, Walter S.
1933-01-01
This bulletin provides the second chapter of the Biennial Survey of Education, 1930-32, which has been published in separate chapters dealing with a segment only of the educational system. The statistics presented in this report document city public schools for the school year 1931-32. The cities are divided into four population groups on the…
ERIC Educational Resources Information Center
Broughman, Stephen P.; Swaim, Nancy L.; Keaton, Patrick W.
2009-01-01
Since 1989, the U.S. Bureau of the Census has conducted the biennial Private School Universe Survey (PSS) for the National Center for Education Statistics (NCES). The PSS is designed to generate biennial data on the total number of private schools, students, and teachers, and to build a universe of private schools in the 50 states and the District…
Haldeman, Scott; Chapman-Smith, David
2012-01-01
This editorial reviews the scientific sessions and announces the 4 award-winning scientific articles from the World Federation of Chiropractic 11th Biennial Congress held in Rio de Janeiro from April 6, to 9, 2011, that are published in this issue of the Journal of Manipulative and Physiological Therapeutics. Copyright © 2012 National University of Health Sciences. Published by Mosby, Inc. All rights reserved.
Tropical waves and the quasi-biennial oscillation in the lower stratosphere
NASA Technical Reports Server (NTRS)
Miller, A. J.; Angell, J. K.; Korshover, J.
1976-01-01
By means of spectrum analysis of 11 years of lower stratospheric daily winds and temperatures at Balboa, Ascension and Canton-Singapore, evidence is presented supporting the existence of two principal wave modes with periods of about 11-17 days (Kelvin waves) and about 4-5 days (mixed Rossby-gravity waves). The structure of the two wave modes, as well as the vertical eddy momentum flux by the waves, is shown to be related to the quasi-biennial cycle, although for the mixed Rossby-gravity waves this is obvious only at Ascension. In addition, the Coriolis term, suggested as a source of vertical easterly momentum flux for the mixed Rossby-gravity waves, is investigated and found to be of the same magnitude as the vertical eddy flux term. Finally, we have examined the mean meridional motion and the meridional eddy momentum flux for its possible association with the quasi- biennial variation.
Solar generated quasi-biennial geomagnetic variation
NASA Technical Reports Server (NTRS)
Sugiura, M.; Poros, D. J.
1977-01-01
The existence of highly correlated quasi-biennial variations in the geomagnetic field and in solar activity is demonstrated. The analysis uses a numerical filter technique applied to monthly averages of the geomagnetic horizontal component and of the Zurich relative sunspot number. Striking correlations are found between the quasi-biennial geomagnetic variations determined from several magnetic observatories located at widely different longitudes, indicating a worldwide nature of the obtained variation. The correlation coefficient between the filtered Dst index and the filtered relative sunspot number is found to be -0.79 at confidence level greater than 99% with a time-lag of 4 months, with solar activity preceding the Dst variation. The correlation between the unfiltered data of Dst and of the sunspot number is also high with a similar time-lag. Such a timelag has not been discussed in the literature, and a further study is required to establish the mode of sun-earth relationship that gives this time delay.
Dynamics of Monsoon-Induced Biennial Variability in ENSO
NASA Technical Reports Server (NTRS)
Kim, Kyu-Myong; Lau, K.-M.; Einaudi, Franco (Technical Monitor)
2000-01-01
The mechanism of the quasi-biennial tendency in El Nino Southern Oscillation (ENSO)-monsoon coupled system is investigated using an intermediate coupled model. The monsoon wind forcing is prescribed as a function of Sea Surface Temperature (SST) anomalies based on the relationship between zonal wind anomalies over the western Pacific to sea level change in the equatorial eastern Pacific. The key mechanism of quasi-biennial tendency in El Nino evolution is found to be in the strong coupling of ENSO to monsoon wind forcing over the western Pacific. Strong boreal summer monsoon wind forcing, which lags the maximum SST anomaly in the equatorial eastern Pacific approximately 6 months, tends to generate Kelvin waves of the opposite sign to anomalies in the eastern Pacific and initiates the turnabout in the eastern Pacific. Boreal winter monsoon forcing, which has zero lag with maximum SST in the equatorial eastern Pacific, tends to damp the ENSO oscillations.
1983-05-01
tigations, Clemson, S. C . 29631 and U. S. Army ED- It. REPORT DATE gineer Waterways Experiment Station, Environmental May 1983 Laboratory, P. 0. Box 631...ON eport) Washington, D. C . 20314 Unclassified I&. NMITORING AGENCY NAME & ADORVESS( Idfieuf orn o C ..,bDIMi OW~~ IS. DECkASFCTO(ONRDN W DISTRIBUTION...Reservoir Research Program, U. S. Fish and Wildlife Ser- vice, Clemson, S. C .; and Drs. John Nestler and Gary Saul, EL, WES. Preparation of this report
Lock and Dam Number 8 Hydropower Study; Mississippi River Near LaCrosse, Wisconsin. Supplement.
1985-01-01
unit used in scheme 3 is a standardized module consisting of an axial flow turbine , a speed increasing gear set, and a generator combined in a short...the flow and generating head ranges associated with specific turbine generator sizes, the program produces annual and monthly flow -duration curves and...open flume turbine passing a rated flow of 14O0 eta at a rated head of 9.75 feat. Cost estimates were made for two and four unit plants having
DOE Office of Scientific and Technical Information (OSTI.GOV)
McCoy, Gilbert A.
1992-12-01
The design, construction and operation of a hydropower project can result in many potential impacts. These potential impacts are of concern to a host of federal, state, and local authorities. Early consultation with land and water management, fish and wildlife resource protection, and health and human safety-oriented agencies should occur to determine specific concerns and study requirements for each proposed project. This Guide to Permitting and Licensing outlines the characteristic features of attractive hydropower sites; summarizes an array of developmental constraints; illustrates potential environmental impacts and concerns; and summarizes all federal, state, and local permitting and licensing requirements.
DOE Office of Scientific and Technical Information (OSTI.GOV)
McCoy, Gilbert A.
1992-12-01
The design, construction and operation of a hydropower project can result in many potential impacts. These potential impacts are of concern to a host of federal, state, and local authorities. Early consultation with land and water management, fish and wildlife resource protection, and health and human safety-oriented agencies should occur to determine specific concerns and study requirements for each proposed project. This Guide to Permitting and Licensing outlines the characteristic features of attractive hydropower sites; summarizes an array of developmental constraints; illustrates potential environmental impacts and concerns; and summarizes all federal, state, and local permitting and licensing requirements.
Simulation and Modeling Capability for Standard Modular Hydropower Technology
DOE Office of Scientific and Technical Information (OSTI.GOV)
Stewart, Kevin M.; Smith, Brennan T.; Witt, Adam M.
Grounded in the stakeholder-validated framework established in Oak Ridge National Laboratory’s SMH Exemplary Design Envelope Specification, this report on Simulation and Modeling Capability for Standard Modular Hydropower (SMH) Technology provides insight into the concepts, use cases, needs, gaps, and challenges associated with modeling and simulating SMH technologies. The SMH concept envisions a network of generation, passage, and foundation modules that achieve environmentally compatible, cost-optimized hydropower using standardization and modularity. The development of standardized modeling approaches and simulation techniques for SMH (as described in this report) will pave the way for reliable, cost-effective methods for technology evaluation, optimization, and verification.
Dynamic evolution characteristics of a fractional order hydropower station system
NASA Astrophysics Data System (ADS)
Gao, Xiang; Chen, Diyi; Yan, Donglin; Xu, Beibei; Wang, Xiangyu
2018-01-01
This paper investigates the dynamic evolution characteristics of the hydropower station by introducing the fractional order damping forces. A careful analysis of the dynamic characteristics of the generator shaft system is carried out under different values of fractional order. It turns out the vibration state of the axis coordinates has a certain evolution law with the increase of the fractional order. Significantly, the obtained law exists in the horizontal evolution and vertical evolution of the dynamical behaviors. Meanwhile, some interesting dynamical phenomena were found in this process. The outcomes of this study enrich the nonlinear dynamic theory from the engineering practice of hydropower stations.
78 FR 79433 - Mahoning Hydropower, LLC, Ohio, Notice of Availability of Environmental Assessment
Federal Register 2010, 2011, 2012, 2013, 2014
2013-12-30
... Hydropower, LLC, Ohio, Notice of Availability of Environmental Assessment In accordance with the National Environmental Policy Act of 1969 and the Federal Energy Regulatory Commission's (Commission or FERC) regulations.... Staff prepared an environmental assessment (EA), which analyzes the potential environmental effects of...
JPRS Report, Science & Technology China: Energy
1992-06-24
HYDROPOWER Speeding Up Hydropower Construction Through Improved Investment Conditions [Yang Zhirong, Qu Shiyuan , et ai; ZHONGGUO NENGYUAN, 25 Apr 92] 2...Beijing ZHONGGUO NENGYUAN [ENERGY OF CHINA] in Chinese No 4, 25 Apr 92 pp 4-7 [Article by Yang Zhirong [2799 1807 2837], Qu Shiyuan [3255 2514
Analysis on regulation strategies for extending service life of hydropower turbines
NASA Astrophysics Data System (ADS)
Yang, W.; Norrlund, P.; Yang, J.
2016-11-01
Since a few years, there has been a tendency that hydropower turbines experience fatigue to a greater extent, due to increasingly more regulation movements of governor actuators. The aim of this paper is to extend the service life of hydropower turbines, by reasonably decreasing the guide vane (GV) movements with appropriate regulation strategies, e.g. settings of PI (proportional-integral) governor parameters and controller filters. The accumulated distance and number of GV movements are the two main indicators of this study. The core method is to simulate the long-term GV opening of Francis turbines with MATLAB/Simulink, based on a sequence of one-month measurements of the Nordic grid frequency. Basic theoretical formulas are also discussed and compared to the simulation results, showing reasonable correspondence. Firstly, a model of a turbine governor is discussed and verified, based on on-site measurements of a Swedish hydropower plant. Then, the influence of governor parameters is discussed. Effects of different settings of controller filters (e.g. dead zone, floating dead zone and linear filter) are also examined. Moreover, a change in GV movement might affect the quality of the frequency control. This is also monitored via frequency deviation characteristics, determined by elementary simulations of the Nordic power system. The results show how the regulation settings affect the GV movements and frequency quality, supplying suggestions for optimizing the hydropower turbine operation for decreasing the wear and tear.
Exploring the hydropower potential of future ice-free glacier basins
NASA Astrophysics Data System (ADS)
Round, Vanessa; Farinotti, Daniel; Huss, Matthias
2017-04-01
The retreat of glaciers over the next century will present new challenges related to water availability and cause significant changes to the landscape. The construction of dams in areas becoming ice-free has previously been suggested as a mitigation measure against changes to water resources in the European Alps. In Switzerland, a number of hydropower dams already exist directly below glaciers, and the hydropower potential of natural lakes left by retreating glaciers has been recognised. We expand these concepts to the regional, and ultimately global, scale to assess the potential of creating hydropower dams in glacier basins, encouraged by advantages such as relatively low ecological and social impacts, and the possibility to replicate the water storage capabilities of glaciers. In a first order assessment, dam volumes are computed using a subglacial topography model and dam walls simulated at the terminus of each glacier. Potential power production is then estimated from projected glacier catchment runoff until 2100 based on the Global Glacier Evolution Model (GloGEM), and penstock head approximated from a global digital elevation model. Based on this, a feasibility ranking system is presented which takes into account various proxies for cost, demand and impact, such as proximity to populations and existing infrastructure, geological risks and threatened species. The ultimate objective is to identify locations of glacier retreat which could most feasibly and beneficially be used for hydropower production.
Proceedings of the First Biennial Space Biomedical Investigators' Workshop
NASA Technical Reports Server (NTRS)
1999-01-01
The First Biennial Space Biomedical Investigators' Workshop, held January 11-13, 1999, was unique in that it assembled, for the first time, a broad cross section of NASA-funded biomedical researchers to present the current status of their projects and their plans for future investigations. All principal investigators with active, or recently-completed ground-based projects in NASA's Biomedical Research and Countermeasures Program that were funded through NASA's Office of Life and Microgravity Sciences and Applications were invited. Included were individual investigators funded through NASA Research Announcements, investigators with NASA Specialized Centers of Research and Training, investigators with the recently established National Space Biomedical Research Institute (NSBRI), and NASA civil servant investigators. Seventy-seven percent of all eligible projects were presented at the workshop. Thus, these Proceedings should provide a useful snapshot of the status of NASA-funded space biomedical research as of January 1999. An important workshop objective was to achieve free and open communication among the presenting investigators. Therefore, presentation of new and incomplete results, as well as hypotheses and ideas for future research, was encouraged. Comments and constructive criticisms from the presenters' colleagues were also encouraged. These ground rules resulted in many lively and useful discussions, during both the presentation sessions and informal evening gatherings and breaks.
NASA Astrophysics Data System (ADS)
Piman, T.; Cochrane, T. A.; Arias, M. E.
2013-12-01
Water flow patterns in the Mekong River and its tributaries are changing due to water resources development, particularly as a result of on-going rapid hydropower development of tributaries for economic growth. Local communities and international observers are concerned that alterations of natural flow patterns will have great impacts on biodiversity, ecosystem services, food securing and livelihood in the basin. There is also concern that un-coordinated dam development will have an adverse impact on energy production potential of individual hydropower plants. Of immediate concern is the proposed hydropower development in the transboundary Srepok, Sesan and Srekong (3S) Basin, which contributes up to 20% of the Mekong's annual flows, has a large potential for energy production, and provides critical ecosystem services to local people and the downstream Tonle Sap Lake and the Mekong delta. To assess the magnitude of potential changes in flows and hydropower production, daily flows were simulated over 20 years (1986-2005) using the SWAT and HEC ResSim models for a range of dam development and operations scenarios. Simulations of all current and proposed hydropower development in the 3S basin (41 dams) using an operation scheme to maximize electricity production will increase average dry seasonal flows by 88.1% while average wet seasonal flows decrease by 24.7% when compared to the baseline (no dams) scenario, About 55% of dry season flows changes are caused by the seven largest proposed dams (Lower Srepok 3, Lower Srepok4, Lower Sesan 3, Lower Sesan and Srepok 2, Xekong 5, Xekong 4, and Xe Xou). The total active storage of the existing and ongoing hydropower projects is only 6,616 million m3 while the cumulative active storage of the seven large proposed dams is 17,679 million m3. The Lower Srepok 3 project causes the highest impact on seasonal flow changes. Average energy production of the existing and ongoing hydropower projects is 73.2 GWh/day. Additional benefits from energy production of the seven large proposed dams (33.0 GWh/day) are less than half compared to the cumulative benefits of the exiting and ongoing projects. In total, potential energy production of all dams is 129.1 GWh/day. Cascade dam simulations, under an independent operation regime, result in high electricity production of downstream dams, particularly of small storage dams. Hourly flow alterations, however, can be significant due to intra daily reservoir operations and warrant further study as well as impact of climate change on flows and hydropower operation. Strategic site selection and coordinated reservoir operations between countries and dam operators are necessary to achieve an acceptable level of energy production in the basin and mitigate negative impacts to seasonal flow patterns which sustain downstream ecosystem productivity and livelihoods.
Trentham-Dietz, Amy; Kerlikowske, Karla; Stout, Natasha K; Miglioretti, Diana L; Schechter, Clyde B; Ergun, Mehmet Ali; van den Broek, Jeroen J; Alagoz, Oguzhan; Sprague, Brian L; van Ravesteyn, Nicolien T; Near, Aimee M; Gangnon, Ronald E; Hampton, John M; Chandler, Young; de Koning, Harry J; Mandelblatt, Jeanne S; Tosteson, Anna N A
2016-11-15
Biennial screening is generally recommended for average-risk women aged 50 to 74 years, but tailored screening may provide greater benefits. To estimate outcomes for various screening intervals after age 50 years based on breast density and risk for breast cancer. Collaborative simulation modeling using national incidence, breast density, and screening performance data. United States. Women aged 50 years or older with various combinations of breast density and relative risk (RR) of 1.0, 1.3, 2.0, or 4.0. Annual, biennial, or triennial digital mammography screening from ages 50 to 74 years (vs. no screening) and ages 65 to 74 years (vs. biennial digital mammography from ages 50 to 64 years). Lifetime breast cancer deaths, life expectancy and quality-adjusted life-years (QALYs), false-positive mammograms, benign biopsy results, overdiagnosis, cost-effectiveness, and ratio of false-positive results to breast cancer deaths averted. Screening benefits and overdiagnosis increase with breast density and RR. False-positive mammograms and benign results on biopsy decrease with increasing risk. Among women with fatty breasts or scattered fibroglandular density and an RR of 1.0 or 1.3, breast cancer deaths averted were similar for triennial versus biennial screening for both age groups (50 to 74 years, median of 3.4 to 5.1 vs. 4.1 to 6.5 deaths averted; 65 to 74 years, median of 1.5 to 2.1 vs. 1.8 to 2.6 deaths averted). Breast cancer deaths averted increased with annual versus biennial screening for women aged 50 to 74 years at all levels of breast density and an RR of 4.0, and those aged 65 to 74 years with heterogeneously or extremely dense breasts and an RR of 4.0. However, harms were almost 2-fold higher. Triennial screening for the average-risk subgroup and annual screening for the highest-risk subgroup cost less than $100 000 per QALY gained. Models did not consider women younger than 50 years, those with an RR less than 1, or other imaging methods. Average-risk women with low breast density undergoing triennial screening and higher-risk women with high breast density receiving annual screening will maintain a similar or better balance of benefits and harms than average-risk women receiving biennial screening. National Cancer Institute.
78 FR 61999 - Hydropower Regulatory Efficiency Act of 2013; Supplemental Notice of Workshop
Federal Register 2010, 2011, 2012, 2013, 2014
2013-10-10
... DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. AD13-9-000] Hydropower Regulatory Efficiency Act of 2013; Supplemental Notice of Workshop As announced in the Notices issued on September 3, 2013 and September 18, 2013, the Federal Energy Regulatory Commission (FERC or Commission...
Hydropower Research | Water Power | NREL
facilities are available to support hydropower technology validation and design optimization. Photo of water optimized prior to expensive and time-consuming open-water validation. Photo of electric power lines at -machinery. Using these methodologies, tools, and direct industry data, they analyze the near- and long-term
Federal Register 2010, 2011, 2012, 2013, 2014
2012-05-22
... the Alternatives Process in Hydropower Licensing, OMB Control Number 1094-0001. FOR FURTHER... Interior, and Commerce collect the information covered by 1094-0001. Under FPA section 33, the Secretary of... Control Number: 1094-0001. Current Expiration Date: September 30, 2012. Type of Review: Information...
Federal Register 2010, 2011, 2012, 2013, 2014
2010-06-18
... DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13795-000] Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications; Mahoning Hydropower, LLC June 10, 2010. On May 25, 2010, Mahoning Hydropower, LLC filed an...
76 FR 46287 - Erie Boulevard Hydropower, L.P.; Notice of Availability of Environmental Assessment
Federal Register 2010, 2011, 2012, 2013, 2014
2011-08-02
... DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2047-049] Erie Boulevard Hydropower, L.P.; Notice of Availability of Environmental Assessment In accordance with the National Environmental Policy Act of 1969 and the Federal Energy Regulatory Commission's (Commission or FERC) regulations...
Federal Register 2010, 2011, 2012, 2013, 2014
2011-01-11
... DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13877-000] Mahoning Hydropower, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications January 4, 2011. On November 4, 2010, Mahoning Hydro, LLC...
1989-01-01
Center, Panama City 314 Diver Training Building Addition 4,300 4 ,300 50 180 Subtotal 4,300 4,300 Navy Experimental Diving Unit 182 Panama City 347 ...Air Force 001 Security Training Center 4,500 4,500 100 345 Subtotal .4,500 4,500 TOTAL FOR TAS 28,220 28,220 Virginia Naval SecuritY Goui Activity 347 ...Building Addition 4,300 C NEDU Panama City, FL 347 Underwater Equipment Support Complex 2,900 C NPWC Pensacola, FL 109 Wastewater Transfer System 2,100 C
1985-86 biennial report of the EML regional baseline station at Chester, New Jersey
DOE Office of Scientific and Technical Information (OSTI.GOV)
Chieco, N.
1988-10-01
The Environmental Measurements Laboratory (EML) has maintained a field station at Chester, NJ since 1976. Located 64 kilometers west of EML, the site is on the property of Bell Communications Research and is a little more than 900 square meters in area. The Chester site is a rural facility which provides us with an opportunity to carry out ''regional baseline'' research and to test field instruments. This report updates the various programs underway at Chester and presents data that have become available since the last report. Individual reports are processed separately for the data base.
NASA Technical Reports Server (NTRS)
Lastovicka, Jan (Editor); Miles, Thomas (Editor); Oneill, Alan (Editor)
1989-01-01
The proceedings of the symposium is presented. Eight different sessions were presented: (1) Papers generally related to the subject; (2) Papers on the influence of the Quasi Biennial Oscillation; (3) Papers on the influence of the solar electromagnetic radiation variability; (4) Papers on the solar wind and high energy particle influence; (5) Papers on atmospheric circulation; (6) Papers on atmospheric electricity; (7) Papers on lower ionospheric variability; and (8) Solar posters, which are not included in this compilation.
A study of quasi-biennial oscillation in the tropical stratosphere
NASA Astrophysics Data System (ADS)
Sasi, M. N.; Krishna Murthy, B. V.
1991-12-01
The characteristics of the quasi-biennial oscillation in zonal wind and temperature at Trivandrum (8.5°N, 77°E) have been studied using data covering 16 years. Similar study has been carried out for zonal wind at Balasore (21.5°N, 87°E) using data covering 9 years. The cycle to cycle variation of amplitudes, their altitude variation, periods and descent rates of the westerly and easterly regimes have been studied.
ERIC Educational Resources Information Center
Todd, John J., Ed.
This document contains the proceedings of the 9th Biennial National Conference of the Australian Association for Environmental Education and the Marine Society of Australasia. The contents provide a valuable snapshot of the state of environmental education in Australia while moving towards the end of the 20th century. Papers include: (1)…
Validation and Analysis of Microwave-Derived Rainfall Over the Tropics
1993-01-01
biennial pulse and a residual low-frequency pulse. A paper linking AC, ENSO and quasi-biennial oscilla- tion ( QBO ) in global precipitation was prepared by...Lau and Sheu (1988). Their analysis showed a nonlinear relationship between QBO and ENSO, 11 while QBO and AC were strongly phase locked, suggesting...that the phase locking between AC and ENSO may be due only to the QBO part of the ENSO signal. To further complicate matters, Gray and Shaeffer (1990
An Interactive Parallel Coordinates Technique Applied to a Tropical Cyclone Climate Analysis
2008-06-06
12). 3.4 Quasi-Biennial Oscillation Variable Research has also shown that the Quasi-Biennial Oscillation ( QBO ) is corre- lated to tropical cyclone...activity. The QBO is a stratospheric (16 to 35 km altitude) oscillation of equatorial east-west winds which vary with a period of about 26 to 30 months...again. The west phase of the QBO has been shown to provide favorable conditions for development of tropical cyclones, possibly because it reduces
ERIC Educational Resources Information Center
Bialeschki, M. Deborah, Ed.; Henderson, Karla A., Ed.; Young, Anderson B., Ed.; Andrejewski, Robert G., Ed.
This volume contains peer-reviewed research articles and abstracts based on papers presented at the sixth biennial research symposium of the Coalition for Education in the Outdoors. Introductory materials include the editors' introduction, "Milestones in Outdoor Education" (Anderson B. Young), and a tribute to the founder of the Indiana University…
ERIC Educational Resources Information Center
O'Mahony, Catherine, Ed.; Buchanan, Avril, Ed.; O'Rourke, Mary, Ed.; Higgs, Bettie, Ed.
2014-01-01
The 6th Annual Conference of the National Academy for the Integration of Research, Teaching and Learning (NAIRTL) and the 4th Biennial Threshold Concepts Conference was held at Trinity College Dublin, Ireland, on June 27-29, 2012. The NAIRTL is a collaborative initiative between University College Cork, Cork Institute of Technology, National…
Enhanced Biennial Variability in the Pacific due to Atlantic Capacitor Effect after the Early 1990s
NASA Astrophysics Data System (ADS)
WANG, L.; Yu, J. Y.; Paek, H.
2016-12-01
The El Niño-Southern Oscillation (ENSO) and Pacific subtropical highs (PSHs) have major impacts on social and ecological systems through their influences on severe natural hazards including tropical storms, coastal erosions, droughts and floods. The ability to forecast ENSO and PSHs requires an understanding of the underlying physical mechanisms that drive their variability. Here we present an Atlantic capacitor effect mechanism to suggest the Atlantic as a key pacemaker of the biennial variability in the Pacific including ENSO and PSHs in recent decades, while the pacemaker was previously considered to be mainly lied within the Pacific or Indian Oceans. The "charging" (i.e., ENSO imprinting the North Tropical Atlantic (NTA) sea surface temperature (SST) via an atmospheric bridge mechanism) and "discharging" (i.e., the NTA SST triggering the following ENSO via a subtropical teleconnection mechanism) process works alternately, generating the biennial rhythmic changes in the Pacific. After the early-1990s, the positive phase of the Atlantic Multidecadal Oscillation and global warming provides more favorable background states over the NTA that enable the Atlantic capacitor effect to operate more efficiently, giving rise to enhanced biennial variability in the Pacific which may increase the occurrence frequency of severe natural hazard events. The results highlight the increasing important role of the Atlantic-Pacific coupling as an important pacemaker of the ENSO cycle in recent decades.
Analysis and Research on the effect of the Operation of Small Hydropower in the Regional Power Grid
NASA Astrophysics Data System (ADS)
Ang, Fu; Guangde, Dong; Xiaojun, Zhu; Ruimiao, Wang; Shengyi, Zhu
2018-03-01
The analysis of reactive power balance and voltage of power network not only affects the system voltage quality, but also affects the economic operation of power grid. In the calculation of reactive power balance and voltage analysis in the past, the problem of low power and low system voltage has been the concern of people. When small hydropower stations in the wet period of low load, the analysis of reactive power surplus and high voltage for the system, if small hydropower unit the capability of running in phase is considered, it can effectively solve the system low operation voltage of the key point on the high side.
NASA Astrophysics Data System (ADS)
Li, Jiqing; Yang, Xiong
2018-06-01
In this paper, to explore the efficiency and rationality of the cascade combined generation, a cascade combined optimal model with the maximum generating capacity is established, and solving the model by the modified GA-POA method. It provides a useful reference for the joint development of cascade hydro-power stations in large river basins. The typical annual runoff data are selected to calculate the difference between the calculated results under different representative years. The results show that the cascade operation of cascaded hydro-power stations can significantly increase the overall power generation of cascade and ease the flood risk caused by concentration of flood season.
Frequencies of decision making and monitoring in adaptive resource management
Johnson, Fred A.
2017-01-01
Adaptive management involves learning-oriented decision making in the presence of uncertainty about the responses of a resource system to management. It is implemented through an iterative sequence of decision making, monitoring and assessment of system responses, and incorporating what is learned into future decision making. Decision making at each point is informed by a value or objective function, for example total harvest anticipated over some time frame. The value function expresses the value associated with decisions, and it is influenced by system status as updated through monitoring. Often, decision making follows shortly after a monitoring event. However, it is certainly possible for the cadence of decision making to differ from that of monitoring. In this paper we consider different combinations of annual and biennial decision making, along with annual and biennial monitoring. With biennial decision making decisions are changed only every other year; with biennial monitoring field data are collected only every other year. Different cadences of decision making combine with annual and biennial monitoring to define 4 scenarios. Under each scenario we describe optimal valuations for active and passive adaptive decision making. We highlight patterns in valuation among scenarios, depending on the occurrence of monitoring and decision making events. Differences between years are tied to the fact that every other year a new decision can be made no matter what the scenario, and state information is available to inform that decision. In the subsequent year, however, in 3 of the 4 scenarios either a decision is repeated or monitoring does not occur (or both). There are substantive differences in optimal values among the scenarios, as well as the optimal policies producing those values. Especially noteworthy is the influence of monitoring cadence on valuation in some years. We highlight patterns in policy and valuation among the scenarios, and discuss management implications and extensions. PMID:28800591
Frequencies of decision making and monitoring in adaptive resource management
Williams, Byron K.; Johnson, Fred A.
2017-01-01
Adaptive management involves learning-oriented decision making in the presence of uncertainty about the responses of a resource system to management. It is implemented through an iterative sequence of decision making, monitoring and assessment of system responses, and incorporating what is learned into future decision making. Decision making at each point is informed by a value or objective function, for example total harvest anticipated over some time frame. The value function expresses the value associated with decisions, and it is influenced by system status as updated through monitoring. Often, decision making follows shortly after a monitoring event. However, it is certainly possible for the cadence of decision making to differ from that of monitoring. In this paper we consider different combinations of annual and biennial decision making, along with annual and biennial monitoring. With biennial decision making decisions are changed only every other year; with biennial monitoring field data are collected only every other year. Different cadences of decision making combine with annual and biennial monitoring to define 4 scenarios. Under each scenario we describe optimal valuations for active and passive adaptive decision making. We highlight patterns in valuation among scenarios, depending on the occurrence of monitoring and decision making events. Differences between years are tied to the fact that every other year a new decision can be made no matter what the scenario, and state information is available to inform that decision. In the subsequent year, however, in 3 of the 4 scenarios either a decision is repeated or monitoring does not occur (or both). There are substantive differences in optimal values among the scenarios, as well as the optimal policies producing those values. Especially noteworthy is the influence of monitoring cadence on valuation in some years. We highlight patterns in policy and valuation among the scenarios, and discuss management implications and extensions.
78 FR 55251 - Hydropower Regulatory Efficiency Act of 2013; Notice of Workshop
Federal Register 2010, 2011, 2012, 2013, 2014
2013-09-10
... Regulatory Efficiency Act of 2013; Notice of Workshop The Federal Energy Regulatory Commission (FERC or... 6 of the Hydropower Regulatory Efficiency Act of 2013. Participants should be prepared to discuss... at https://www.ferc.gov/whats-new/registration/efficiency-act-10-02-13-form.asp by September 25, 2013...
Federal Register 2010, 2011, 2012, 2013, 2014
2012-10-16
.... 791(a)-825(r). h. Applicant Contact: Duff Mitchell, Business Manager, Juneau Hydropower, Inc., P.O... information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnline... access the document. For assistance, contact FERC Online Support. You may also register online at http...
Federal Register 2010, 2011, 2012, 2013, 2014
2013-02-21
...-diameter stream diversion tunnel that would be converted to reservoir outlet works after project... afterbay to an outlet structure on a tributary to Sweetheart Creek; and an existing tributary stream... Mitchell, Business Manager, Juneau Hydropower, Inc. P.O. Box 22775, Juneau, AK 99802; email: duff.mitchell...
Federal Register 2010, 2011, 2012, 2013, 2014
2013-01-15
...-diameter stream diversion tunnel that would be converted to reservoir outlet works after project... afterbay to an outlet structure on a tributary to Sweetheart Creek; and an existing tributary stream... Mitchell, Business Manager, Juneau Hydropower, Inc. P.O. Box 22775, Juneau, AK 99802; email: duff.mitchell...
A Student Activity for the James Bay Hydro Project. The Geography Teacher.
ERIC Educational Resources Information Center
Green-Milberg, Patricia
1999-01-01
Provides activities for grades 6 to 8 that will promote student awareness and understanding of the use of hydropower in Canada, the benefits and drawbacks to hydropower, and also the drawbacks of electricity transmission lines. Explains that the activities focus on the James Bay Hydro Project in Canada. (CMK)
Federal Register 2010, 2011, 2012, 2013, 2014
2013-10-09
...), as amended by HREA.... The facility is constructed, operated, or maintained Y for the generation of... Conduit Hydropower Facility Satisfies (Y/ Statutory provision Description N) FPA 30(a)(3)(A), as amended by HREA....... The conduit the facility uses is a tunnel, canal, Y pipeline, aqueduct, flume, ditch...
Over 50 hydropower dams in California will undergo relicensing by the Federal Energy Regulatory Commission (FERC) in the next 15 years. An interpretive framework for biological data collected by relicensing studies is lacking. This study developed a multi-metric index of biotic...
Federal Register 2010, 2011, 2012, 2013, 2014
2011-09-22
... a Federal Government facility. Depending on the economic viability of the proposed hydropower.... Identify proposed methods of financing the hydropower development. An economic analysis should be presented... and provide for long-term operation and maintenance; and (3) best share the economic benefits of the...
Federal Register 2010, 2011, 2012, 2013, 2014
2011-09-16
... Competing Applications; McKay Dam Hydropower, LLC On May 31, 2011, McKay Dam Hydropower, LLC filed an... study the feasibility of the McKay Dam Hydroelectric Project (project) to be located at the McKay dam near Pendleton in Umatilla County, [[Page 57732