Science.gov

Sample records for interim stabilization project

  1. Single-shell tank interim stabilization project plan

    SciTech Connect

    Ross, W.E.

    1998-03-27

    Solid and liquid radioactive waste continues to be stored in 149 single-shell tanks at the Hanford Site. To date, 119 tanks have had most of the pumpable liquid removed by interim stabilization. Thirty tanks remain to be stabilized. One of these tanks (C-106) will be stabilized by retrieval of the tank contents. The remaining 29 tanks will be interim stabilized by saltwell pumping. In the summer of 1997, the US Department of Energy (DOE) placed a moratorium on the startup of additional saltwell pumping systems because of funding constraints and proposed modifications to the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) milestones to the Washington State Department of Ecology (Ecology). In a letter dated February 10, 1998, Final Determination Pursuant to Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) in the Matter of the Disapproval of the DOE`s Change Control Form M-41-97-01 (Fitzsimmons 1998), Ecology disapproved the DOE Change Control Form M-41-97-01. In response, Fluor Daniel Hanford, Inc. (FDH) directed Lockheed Martin Hanford Corporation (LNMC) to initiate development of a project plan in a letter dated February 25, 1998, Direction for Development of an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan in Support of Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement). In a letter dated March 2, 1998, Request for an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan, the DOE reaffirmed the need for an aggressive SST interim stabilization completion project plan to support a finalized Tri-Party Agreement Milestone M-41 recovery plan. This project plan establishes the management framework for conduct of the TWRS Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organizational structure, roles, responsibilities

  2. Single-shell tank interim stabilization project plan

    SciTech Connect

    Ross, W.E.

    1998-05-11

    This project plan establishes the management framework for conduct of the TWRS Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organizational structure, roles, responsibilities, and interfaces; and operational methods. This plan serves as the project executional baseline.

  3. Single Shell Tank (SST) Interim Stabilization Project Plan

    SciTech Connect

    VLADIMIROFF, D.T.; BOYLES, V.C.

    2000-05-22

    This project plan establishes the management framework for the conduct of the CHG Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organization structure, roles, responsibilities, and interfaces; and operational methods. This plan serves as the project executional baseline.

  4. Interim Report: Uranium Stabilization Through Polyphosphate Injection - 300 Area Uranium Plume Treatability Demonstration Project

    SciTech Connect

    Wellman, Dawn M.; Pierce, Eric M.; Richards, Emily L.; Butler, Bart C.; Parker, Kent E.; Glovack, Julia N.; Burton, Sarah D.; Baum, Steven R.; Clayton, Eric T.; Rodriguez, Elsa A.

    2007-07-31

    This report presents results from bench-scale treatability studies conducted under site-specific conditions to optimize the polyphosphate amendment for implementation of a field-scale technology demonstration to treat aqueous uranium within the 300 Area aquifer of the Hanford site. The general treatability testing approach consists of conducting studies with site sediment and under site conditions, in order to develop an effective chemical formulation for the polyphosphate amendments and evaluate the transport properties of these amendments under site conditions. Phosphorus-31 (31P) NMR was utilized to determine the effects of Hanford groundwater and sediment on the degradation of inorganic phosphates. Static batch tests were conducted to optimize the composition of the polyphosphate formulation for the precipitation of apatite and autunite, as well as to quantify the kinetics, loading and stability of apatite as a long-term sorbent for uranium. Dynamic column tests were used to further optimize the polyphosphate formulation for emplacement within the subsurface and the formation of autunite and apatite. In addition, dynamic testing quantified the stability of autunite and apatite under relevant site conditions. Results of this investigation provide valuable information for designing a full-scale remediation of uranium in the 300 aquifer.

  5. Engineering Task Plan for Hose In Hose Transfer Lines for the Interim Stabilization Program

    SciTech Connect

    TORRES, T.D.

    2000-08-16

    The document is the Engineering Task Plan for the engineering, design services, planning, project integration and management support for the design, modification, installation and testing of an over ground transfer (OGT) system to support the interim stabilization of S/SX and U Tank Farms.

  6. Design Analysis Report for 244-AR Interim Stabilization Exhaust Ventilation Ducting

    SciTech Connect

    RUTHERFORD, J.

    2002-11-21

    This report documents the design analysis performed for the exhaust ducting associated with the 244-AR Interim Stabilization Project. The exhaust ducting connects portable exhausters PORO5 and PORO6 to the existing east dog house of the 291-AR filter vault and the vessel ventilation system. This analysis examines loads on the ductwork and ductwork supports.

  7. Engineering Task Plan for Hose In Hose Transfer Lines for the Interim Stabilization Program

    SciTech Connect

    RUNG, M.P.

    2000-06-20

    This document is the Engineering Task Plan for the engineering, design services, planning, project integration and management support for the design, modification, installation and testing of an over ground transfer (OGT) system to support the interim stabilization of nine tanks in the 241-S/SX Tank Farms.

  8. Safety evaluation of interim stabilization of non-stabilized single-shell watch list tanks

    SciTech Connect

    Stahl, S.M.

    1994-12-30

    The report provides a summation of the status of safety issues associated with interim stabilization of Watch List SSTs (organic, ferrocyanide, and flammable gas), as extracted from recent safety analyses, including the Tank Farms Accelerated Safety Analysis efforts.

  9. SLIGHTLY IRRADIATED FUEL (SIF) INTERIM DISPOSITION PROJECT

    SciTech Connect

    NORTON SH

    2010-02-23

    CH2M HILL Plateau Remediation Company (CH2M HILL PRC) is proud to submit the Slightly Irradiated Fuel (SIF) Interim Disposition Project for consideration by the Project Management Institute as Project of the Year for 2010. The SIF Project was a set of six interrelated sub-projects that delivered unique stand-alone outcomes, which, when integrated, provided a comprehensive and compliant system for storing high risk special nuclear materials. The scope of the six sub-projects included the design, construction, testing, and turnover of the facilities and equipment, which would provide safe, secure, and compliant Special Nuclear Material (SNM) storage capabilities for the SIF material. The project encompassed a broad range of activities, including the following: Five buildings/structures removed, relocated, or built; Two buildings renovated; Structural barriers, fencing, and heavy gates installed; New roadways and parking lots built; Multiple detection and assessment systems installed; New and expanded communication systems developed; Multimedia recording devices added; and A new control room to monitor all materials and systems built. Project challenges were numerous and included the following: An aggressive 17-month schedule to support the high-profile Plutonium Finishing Plant (PFP) decommissioning; Company/contractor changeovers that affected each and every project team member; Project requirements that continually evolved during design and construction due to the performance- and outcome-based nature ofthe security objectives; and Restrictions imposed on all communications due to the sensitive nature of the projects In spite of the significant challenges, the project was delivered on schedule and $2 million under budget, which became a special source of pride that bonded the team. For years, the SIF had been stored at the central Hanford PFP. Because of the weapons-grade piutonium produced and stored there, the PFP had some of the tightest security on the Hanford

  10. Strategic defenses and crisis stability. Interim report

    SciTech Connect

    Wilkening, D.; Watman, K.; Kennedy, M.; Darilek, R.

    1989-04-01

    The effect that defenses have on crisis stability is one of the central issues in the current debate over the Strategic Defense Initiative (SDI). Crisis stability would be threatened in a situation in which either the United States or the Soviet Union feels pressure to strike first in the hope of producing a more favorable outcome to what appears to be inevitable nuclear war. This note examines various issues surrounding the question of crisis stability. In particular, it considers options for ameliorating any potential instabilities that might arise during a transition to higher levels of strategic defenses. The authors suggest that a crisis-stable transition is possible, that the mutual survivability of strategic offensive forces is crucial to maintaining crisis stability, that space-based defenses of strategic offensive forces (SOF) are potentially crisis-destabilizing unless they are backed up by terminal defenses of SOF, and that the mutual survivability of strategic defenses and defense suppression forces is also critical to crisis stability.

  11. Interim Stabilization Equipment Essential and Support Drawing Plan

    SciTech Connect

    HORNER, T.M.

    2000-10-16

    The purpose of this document is to list the Interim Stabilization equipment drawings that are classified as Essential or Support drawings. Essential Drawings are those drawings identified by the facility staff as necessary to directly support the safe operation of the facility or equipment. [CHG 2000a]. Support Drawings are those drawings identified by the facility staff that further describe the design details of structures, systems or components shown on essential drawings. [CHG 2000a].

  12. Interim Stabilization Equipment Essential and Support Drawing Plan

    SciTech Connect

    KOCH, M.R.

    1999-11-17

    The purpose of this document is to list the Interim Stabilization equipment drawings that are classified as Essential or Support drawings. Essential Drawings: Those drawings identified by the facility staff as necessary to directly support the safe operation of the facility or equipment. Support Drawings: Those drawings identified by the facility staff that further describe the design details of structures, systems or components shown on essential drawings.

  13. Interim Stabilization Equipment Essential and Support Drawing Plan

    SciTech Connect

    KOCH, M.R.

    1999-10-22

    The purpose of this document is to list the Interim Stabilization equipment drawings that are classified as Essential or Support drawings. Essential Drawings: Those drawings identified by the facility staff as necessary to directly support the safe operation of the facility or equipment. Support Drawings: Those drawings identified by the facility staff that further describe the design details of structures, systems or components shown on essential drawings.

  14. Plutonium Finishing Plant. Interim plutonium stabilization engineering study

    SciTech Connect

    Sevigny, G.J.; Gallucci, R.H.; Garrett, S.M.K.; Geeting, J.G.H.; Goheen, R.S.; Molton, P.M.; Templeton, K.J.; Villegas, A.J.; Nass, R.

    1995-08-01

    This report provides the results of an engineering study that evaluated the available technologies for stabilizing the plutonium stored at the Plutonium Finishing Plant located at the hanford Site in southeastern Washington. Further processing of the plutonium may be required to prepare the plutonium for interim (<50 years) storage. Specifically this document provides the current plutonium inventory and characterization, the initial screening process, and the process descriptions and flowsheets of the technologies that passed the initial screening. The conclusions and recommendations also are provided. The information contained in this report will be used to assist in the preparation of the environmental impact statement and to help decision makers determine which is the preferred technology to process the plutonium for interim storage.

  15. Project International Emphasis Interim Report, July 1991.

    ERIC Educational Resources Information Center

    Blois, Beverly, Ed.; Williams, Barbara

    Project International Emphasis (PIE), a curriculum development effort involving all 24 colleges in the Virginia Community College System (VCCS), focuses on the infusion of globally oriented components across the academic curriculum and in related career development programs. Activities undertaken during the project's first year included an annual…

  16. A Career Education Counseling Project. Interim Report.

    ERIC Educational Resources Information Center

    Cron, C. Thomas

    Covering the period of June 1974 to June 1975, the report and final evaluation document the second year operation of a career education counseling project in the Corpus Christi Schools. The components of the project emphasized awareness and career orientation for K-6, established career resource areas in junior high school libraries, and developed…

  17. Recommended alternative for interim stabilization of Tank 241-C-103

    SciTech Connect

    Dukelow, G.T.; Turner, D.A.; Grigsby, J.M.

    1995-04-01

    The waste in tank 241-C-103 poses several health and safety risks and potential soil contamination caused by tank leaks. To minimize the risk of contaminating the soil beneath the tank, the pumpable waste liquids are planned to be removed by salt well pumping. In addition to aqueous liquids, this tank is unique because it also contains a layer of degraded PUREX solvent floating on the aqueous liquid. The following three options for removing and storing this separable phase organic solvent have been proposed and studied: transferring the organic solvent and pumpable aqueous liquids using existing salt well pumping equipment and procedures to a double-shell tank (DST) for storage; removing most of the organic solvent using a skimmer pump, then salt well pumping the remaining pumpable liquids to a different DST for storage; removing most of the organic solvent to an aboveground storage tank for eventual treatment or offsite transfer, and then salt well pumping the remaining pumpable liquids to a DST for interim storage. As a result of evaluating these three options and a no pumping option, the recommended action is to transfer both the organic solvent and pumpable aqueous liquid to a DST for storage using existing salt well pumping equipment. The evaluation considers the following criteria: public health and safety, worker safety, environmental compliance, engineering feasibility, and cost. The options compared these factors. Two key areas drove the selection of the recommended approach: the minimization of potential soil contamination from tank leaks caused the (interim stabilization by salt well pumping) options to be rated more highly than the no pumping option; and cost and implementation factors caused the transfer and storage to DST using existing tank farm salt well pumping equipment option to rate higher than the skimming options. Other factors have only a second order effect on the selection process. Evaluation results are described in this report.

  18. Beginning Farmer Sustainable Agriculture Project. Interim Report.

    ERIC Educational Resources Information Center

    Center for Rural Affairs, Hartington, NE.

    This project increases opportunities for beginning farmers to learn about and implement sustainable farming methods through mutual-help discussion groups and continuing education opportunities. Local groups established in six areas in northeast Nebraska in 1991 constitute the Beginning Farmer Support Network (BFSN). At workshops held throughout…

  19. NCSS Peace Studies Project: An Interim Report.

    ERIC Educational Resources Information Center

    Ferber, Michael

    This preliminary report of a National Council for the Social Studies (NCSS) project briefly assesses teaching materials related to peace and nuclear warfare. Covering elementary, secondary, and higher education, the materials discussed present a variety of activities, decision-making approaches, and analytical assessments of policies of many…

  20. 244-CR Vault Interim Stabilization Project Plan

    SciTech Connect

    PARKMAN, D.B.

    2000-04-25

    The 244-CR Vault is a two-level, multi-cell structure of reinforced concrete constructed below grade. The lower cell contains four individual compartments, each containing a steel process storage tank and equipped with a concrete sump. The upper cell contains the piping and support equipment, and has two compartments for each of the tanks. The ''pump pit'' is accessed by the removal of concrete cover blocks, while the smaller ''riser pit'' is accessed by steel cover plates. The facility most recently was used as a double-contained receiver tank (DCRT). A DCRT is a type of waste transfer tank that together with its related equipment constitutes a short-term storage area for liquid waste and has a pump pit for waste transfer operations. This vault most recently was used for short-term storage and waste routing for saltwell liquid pumped from the 241-C Tank Farm in the 200 East Area. Waste transfer lines are connected inside the pump pit by a jumper installed between connecting nozzles. An active ventilation system is in operation at the 244-CR vault. Ventilation supply air enters the upper vault section through an inlet header with some leakage through the spaces between the cell cover blocks. The upper and lower vaults are connected by exhauster ports, which allow airflow between the two sections. Normal flow moves air from the upper cell to the lower cell where it is removed and routed into a filter plenum; there the air is treated by a bank of four prefilters and two banks of high-efficiency particulate air (HEPA) filters (each containing four HEPAs). The air is exhausted to the atmosphere through the 296-C-05 Stack. The stack is equipped with a record sampler and continuous air monitor. Two fans (each rated at 4,200 cubic feet per minute) installed downstream of the filtration system provide the motive force for exhausting the vaults and the tanks. As an active system, it is operated continuously with only one of the two fans required to operate at a time. A continuous beta-gamma air monitor is interlocked to the operating fan. Loss of power to the fans will activate an alarm at the 244-AR facility.

  1. 244-AR Vault Interim Stabilization Project Plan

    SciTech Connect

    LANEY, T.

    2000-03-24

    The 244-AR Vault Facility, constructed between 1966 and 1968, was designed to provide lag storage and treatment for the Plutonium-Uranium Extraction Facility (PUREX) tank farm sludges. Tank farm personnel transferred the waste from the 244-AR Vault Facility to B Plant for recovery of cesium and strontium. B Plant personnel then transferred the treatment residuals back to the tank farms for storage of the sludge and liquids. The last process operations, which transferred waste supporting the cesium/strontium recovery mission, occurred in April 1978. After the final transfer in 1978, the 244-AR facility underwent a cleanout. However, 2,271 L (600 gal) of sludge were left in Tank 004AR from an earlier transfer from Tank 241-AX-104. When the cleanout was completed, the facility was placed in a standby status. The sludge had been transferred to Tank 004AR to support Pacific Northwest National Laboratory [PNNL] vitrification work. Documentation of waste transfers suggests that a portion of the sludge may have been moved from Tank 004AR to Tank 002AR in preparation for transfer back to the AX Tank Farm; however, quantities of the sludge that were moved to Tank 002AR from that transfer must be estimated.

  2. Spray combustion stability project

    NASA Technical Reports Server (NTRS)

    Jeng, San-Mou; Litchford, Ron J.

    1990-01-01

    This report summarizes research activity on the Spray Combustion Stability Project, characterizes accomplishments and current status, and discusses projected future work. The purpose is to provide a concise conceptual overview of the research effort so the reader can quickly assimilate the gist of the research results and place them within the context of their potential impact on liquid rocket engine design technology. Therefore, this report does not elaborate on many of the detailed technical aspects of the research program.

  3. Advanced nuclear reactor public opinion project. Interim report

    SciTech Connect

    Benson, B.

    1991-07-25

    This Interim Report summarizes the findings of our first twenty in-depth interviews in the Advanced Nuclear Reactor Public Opinion Project. We interviewed 6 industry trade association officials, 3 industry attorneys, 6 environmentalists/nuclear critics, 3 state officials, and 3 independent analysts. In addition, we have had numerous shorter discussions with various individuals concerned about nuclear power. The report is organized into the four categories proposed at our April, 1991, Advisory Group meeting: safety, cost-benefit analysis, science education, and communications. Within each category, some change of focus from that of the Advisory Group has been required, to reflect the findings of our interviews. This report limits itself to describing our findings. An accompanying memo draws some tentative conclusions.

  4. PROJECT W-551 INTERIM PRETREATMENT SYSTEM TECHNOLOGY SELECTION SUMMARY DECISION REPORT AND RECOMMENDATION

    SciTech Connect

    CONRAD EA

    2008-08-12

    This report provides the conclusions of the tank farm interim pretreatment technology decision process. It documents the methodology, data, and results of the selection of cross-flow filtration and ion exchange technologies for implementation in project W-551, Interim Pretreatment System. This selection resulted from the evaluation of specific scope criteria using quantitative and qualitative analyses, group workshops, and technical expert personnel.

  5. Safety evaluation for the interim stabilization of Tank 241-C-103

    SciTech Connect

    Geschke, G.R.

    1995-03-01

    This document provides the basis for interim stabilization of tank 241-C-103. The document covers the removal of the organic liquid layer and the aqueous supernatant from tank 241-C-103. Hazards are identified, consequences are calculated and controls to mitigate or prevent potential accidents are developed.

  6. Evaluation of Hose in Hose Transfer Line Service Life for Hanford's Interim Stabilization Program

    SciTech Connect

    TORRES, T.D.

    2000-08-24

    RPP-6153, Engineering Task Plan for Hose-in-Hose Transfer System for the Interim Stabilization Program, defines the programmatic goals, functional requirements, and technical criteria for the development and subsequent installation of transfer line equipment to support Hanford's Interim Stabilization Program. RPP-6028, Specification for Hose in Hose Transfer Lines for Hanford's Interim Stabilization Program, has been issued to define the specific requirements for the design, manufacture, and verification of transfer line assemblies for specific waste transfer applications. Included in RPP-6028 are tables defining the chemical constituents of concern to which transfer lines will be exposed. Current Interim Stabilization Program planning forecasts that the at-grade transfer lines will be required to convey pumpable waste for as much as three years after commissioning. Prudent engineering dictates that the equipment placed in service have a working life in excess of this forecasted time period, with some margin to allow for future adjustments to the planned schedule. This document evaluates the effective service life of the Hose-in-Hose Transfer Lines, based on information submitted by the manufacturer and published literature. The effective service life of transfer line assemblies is a function of several factors. Foremost among these are process fluid characteristics, ambient environmental conditions, and the manufacturer's stated shelf life. This evaluation examines the manufacturer's certification of shelf life, the manufacturer's certifications of chemical compatibility with waste, and published literature on the effects of exposure to ionizing radiation on the mechanical properties of elastomeric materials to evaluate transfer line service life.

  7. Idaho Waste Vitrification Facilities Project Vitrified Waste Interim Storage Facility

    SciTech Connect

    Bonnema, Bruce Edward

    2001-09-01

    This feasibility study report presents a draft design of the Vitrified Waste Interim Storage Facility (VWISF), which is one of three subprojects of the Idaho Waste Vitrification Facilities (IWVF) project. The primary goal of the IWVF project is to design and construct a treatment process system that will vitrify the sodium-bearing waste (SBW) to a final waste form. The project will consist of three subprojects that include the Waste Collection Tanks Facility, the Waste Vitrification Facility (WVF), and the VWISF. The Waste Collection Tanks Facility will provide for waste collection, feed mixing, and surge storage for SBW and newly generated liquid waste from ongoing operations at the Idaho Nuclear Technology and Engineering Center. The WVF will contain the vitrification process that will mix the waste with glass-forming chemicals or frit and turn the waste into glass. The VWISF will provide a shielded storage facility for the glass until the waste can be disposed at either the Waste Isolation Pilot Plant as mixed transuranic waste or at the future national geological repository as high-level waste glass, pending the outcome of a Waste Incidental to Reprocessing determination, which is currently in progress. A secondary goal is to provide a facility that can be easily modified later to accommodate storage of the vitrified high-level waste calcine. The objective of this study was to determine the feasibility of the VWISF, which would be constructed in compliance with applicable federal, state, and local laws. This project supports the Department of Energy’s Environmental Management missions of safely storing and treating radioactive wastes as well as meeting Federal Facility Compliance commitments made to the State of Idaho.

  8. DQO Summary Report for 105-N/109-N Interim Safe Storage Project Waste Characterization

    SciTech Connect

    T. A. Lee

    2005-09-15

    The DQO summary report provides the results of the DQO process completed for waste characterization activities for the 105-N/109-N Reactor Interim Safe Storage Project including decommission, deactivate, decontaminate, and demolish activities for six associated buildings.

  9. PROJECT W-551 INTERIM PRETREATMENT SYSTEM PRECONCEPTUAL CANDIDATE TECHNOLOGY DESCRIPTIONS

    SciTech Connect

    MAY TH

    2008-08-12

    The Office of River Protection (ORP) has authorized a study to recommend and select options for interim pretreatment of tank waste and support Waste Treatment Plant (WTP) low activity waste (LAW) operations prior to startup of all the WTP facilities. The Interim Pretreatment System (IPS) is to be a moderately sized system which separates entrained solids and 137Cs from tank waste for an interim time period while WTP high level waste vitrification and pretreatment facilities are completed. This study's objective is to prepare pre-conceptual technology descriptions that expand the technical detail for selected solid and cesium separation technologies. This revision includes information on additional feed tanks.

  10. PLUTONIUM FINISHING PLANT (PFP) STABILIZATION & PACKAGING PROJECT

    SciTech Connect

    GERBER, M.S.

    2004-01-14

    Fluor Hanford is pleased to submit the Plutonium Finishing Plant (PFP) Stabilization and Packaging Project (SPP) for consideration by the Project Management Institute as Project of the Year for 2004. The SPP thermally stabilized and/or packaged nearly 18 metric tons (MT) of plutonium and plutonium-bearing materials left in PFP facilities from 40 years of nuclear weapons production and experimentation. The stabilization of the plutonium-bearing materials substantially reduced the radiological risk to the environment and security concerns regarding the potential for terrorists to acquire the non-stabilized plutonium products for nefarious purposes. The work was done In older facilities which were never designed for the long-term storage of plutonium, and required working with materials that were extremely radioactive, hazardous, pyrophoric, and In some cases completely unique. I n some Instances, one-of-a-kind processes and equipment were designed, installed, and started up. The SPP was completed ahead of schedule, substantially beating all Interim progress milestone dates set by the Defense Nuclear Facilities Safety Board (DNFSB) and in the Hanford Site's Federal Facility Agreement and Consent Order (Tri-Party Agreement or TPA), and finished $1-million under budget.

  11. Interim stabilization of waste sites using recycled concrete

    SciTech Connect

    Hayward, W.M.; Osborne, W.L.

    1994-12-31

    The Hanford Site, operated by the U.S. Department of Energy (DOE), occupies about 1450 km{sup 2} (560 mile{sup 2}) of the southeastern part of Washington State. The site was established in 1943 to produce plutonium for nuclear weapons using production reactors and chemical processing plants. That mission has now ended and the site is in the early stages of a several-decade cleanup program to address the legacy of retired production facilities and the radioactive and chemical wastes that remain in storage or have been placed in the soil column. One important element of this cleanup is the stabilization and maintenance of the individual soil waste sites and burial grounds until the regulatory and technical requirements for final remediation are executed. Several methods currently are used to stabilize sites that have loose surface contamination. These include stabilization with clean soil followed by revegetation; stabilization by application of shotcrete with or without a chemical biobarrier; and stabilization with soil or rock, then application of a soil sterilant herbicide. The specific method is determined on a site-by-site basis.

  12. Pupil Inquiry Behavior Analysis and Change Activity. Interim Project Report.

    ERIC Educational Resources Information Center

    Manion, Raymond C.

    This interim report discusses progress toward three major goals of the Pupil Inquiry Behavior Analysis and Change Activity: increased pupil inquiry, changed teacher behavior to facilitate pupil inquiry, and the development of a 32-week course of instruction to provide for these behavioral changes. Data currently available deals with the emotional…

  13. A Model Project in Career Education, K-12. Interim Report, December 1974.

    ERIC Educational Resources Information Center

    Wyoming State Dept. of Education, Cheyenne.

    The document presents an interim report of a project to establish career education programs for K-12 students in the Natrona County School District of Casper, Wyoming. Project activities were divided into: (1) career awareness, grades K-6; (2) career exploration, grades 7-9; (3) career preparation, grades 10-12; and (4) guidance. To meet the…

  14. Evaluation of Hose in Hose Transfer Line Service Life for Hanfords Interim Stabilization Program

    SciTech Connect

    TORRES, T.D.

    2001-03-23

    RPP-6153, Engineering Task Plan for Hose-in-Hose Transfer System for the Interim Stabilization Program (Torres, 2000a), defines the programmatic goals, functional requirements, and technical criteria for the development and subsequent installation of waste transfer line equipment to support Hanford's Interim Stabilization Program. RPP-6028, Specification for Hose in Hose Transfer Lines for Hanford's Interim Stabilization Program (Torres, 2000b), has been issued to define the specific requirements for the design, manufacture, and verification of transfer line assemblies for specific waste transfer applications associated with Interim Stabilization. Included in RPP-6028 are tables defining the chemical constituents of concern to which transfer lines will be exposed. Current Interim Stabilization Program planning forecasts that the at-grade transfer lines will be required to convey pumpable waste for as much as three years after commissioning, RPP-6028 Section 3.2.7. Performance Incentive Number ORP-05 requires that all the Single Shell Tanks be Interim Stabilized by September 30, 2003. The Tri-Party Agreement (TPA) milestone M-41-00, enforced by a federal consent decree, requires all the Single Shell Tanks to be Interim stabilized by September 30, 2004. By meeting the Performance Incentive the TPA milestone is met. Prudent engineering dictates that the equipment used to transfer waste have a life in excess of the forecasted operational time period, with some margin to allow for future adjustments to the planned schedule. This document evaluates the effective service life of the Hose-in-Hose Transfer Lines, based on information submitted by the manufacturer, published literature and calculations. The effective service life of transfer line assemblies is a function of several factors. Foremost among these are the hose material's resistance to the harmful effects of process fluid characteristics, ambient environmental conditions, exposure to ionizing radiation and the

  15. 105-H Reactor Interim Safe Storage Project Final Report

    SciTech Connect

    E.G. Ison

    2008-11-08

    The following information documents the decontamination and decommissioning of the 105-H Reactor facility, and placement of the reactor core into interim safe storage. The D&D of the facility included characterization, engineering, removal of hazardous and radiologically contaminated materials, equipment removal, decontamination, demolition of the structure, and restoration of the site. The ISS work also included construction of the safe storage enclosure, which required the installation of a new roofing system, power and lighting, a remote monitoring system, and ventilation components.

  16. Software Verification & Validation Report for the 244-AR Vault Interim Stabilization Ventilation System

    SciTech Connect

    YEH, T.

    2002-11-20

    This document reports on the analysis, testing and conclusions of the software verification and validation for the 244-AR Vault Interim Stabilization ventilation system. Automation control system will use the Allen-Bradley software tools for programming and programmable logic controller (PLC) configuration. The 244-AR Interim Stabilization Ventilation System will be used to control the release of radioactive particles to the environment in the containment tent, located inside the canyon of the 244-AR facility, and to assist the waste stabilization efforts. The HVAC equipment, ducts, instruments, PLC hardware, the ladder logic executable software (documented code), and message display terminal are considered part of the temporary ventilation system. The system consists of a supply air skid, temporary ductwork (to distribute airflow), and two skid-mounted, 500-cfm exhausters connected to the east filter building and the vessel vent system. The Interim Stabilization Ventilation System is a temporary, portable ventilation system consisting of supply side and exhaust side. Air is supplied to the containment tent from an air supply skid. This skid contains a constant speed fan, a pre-filter, an electric heating coil, a cooling coil, and a constant flow device (CFD). The CFD uses a passive component that allows a constant flow of air to pass through the device. Air is drawn out of the containment tent, cells, and tanks by two 500-cfm exhauster skids running in parallel. These skids are equipped with fans, filters, stack, stack monitoring instrumentation, and a PLC for control. The 500CFM exhaust skids were fabricated and tested previously for saltwell pumping activities. The objective of the temporary ventilation system is to maintain a higher pressure to the containment tent, relative to the canyon and cell areas, to prevent contaminants from reaching the containment tent.

  17. 78 FR 63276 - Interim Policy, FAA Review of Solar Energy System Projects on Federally Obligated Airports

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-10-23

    ... Federal Aviation Administration Interim Policy, FAA Review of Solar Energy System Projects on Federally... federally obligated airports to construct solar energy systems on airport property. FAA is adopting an... for measuring ocular impact of proposed solar energy systems which are effective upon publication....

  18. Burn site groundwater interim measures work plan.

    SciTech Connect

    Witt, Jonathan L.; Hall, Kevin A.

    2005-05-01

    This Work Plan identifies and outlines interim measures to address nitrate contamination in groundwater at the Burn Site, Sandia National Laboratories/New Mexico. The New Mexico Environment Department has required implementation of interim measures for nitrate-contaminated groundwater at the Burn Site. The purpose of interim measures is to prevent human or environmental exposure to nitrate-contaminated groundwater originating from the Burn Site. This Work Plan details a summary of current information about the Burn Site, interim measures activities for stabilization, and project management responsibilities to accomplish this purpose.

  19. Design requirements document for project W-465, immobilized low activity waste interim storage

    SciTech Connect

    Burbank, D.A.

    1997-01-27

    The scope of this design requirements document is to identify the functions and associated requirements that must be performed to accept, transport, handle, and store immobilized low-activity waste produced by the privatized Tank Waste Remediation System treatment contractors. The functional and performance requirements in this document provide the basis for the conceptual design of the Tank Waste Remediation System Immobilized low-activity waste interim storage facility project and provides traceability from the program level requirements to the project design activity.

  20. Immobilized low-activity waste interim storage facility, Project W-465 conceptual design report

    SciTech Connect

    Pickett, W.W.

    1997-12-30

    This report outlines the design and Total Estimated Cost to modify the four unused grout vaults for the remote handling and interim storage of immobilized low-activity waste (ILAW). The grout vault facilities in the 200 East Area of the Hanford Site were constructed in the 1980s to support Tank Waste disposal activities. The facilities were to serve project B-714 which was intended to store grouted low-activity waste. The existing 4 unused grout vaults, with modifications for remote handling capability, will provide sufficient capacity for approximately three years of immobilized low activity waste (ILAW) production from the Tank Waste Remediation System-Privatization Vendors (TWRS-PV). These retrofit modifications to the grout vaults will result in an ILAW interim storage facility (Project W465) that will comply with applicable DOE directives, and state and federal regulations.

  1. HARD CHROME POLLUTION PREVENTION DEMONSTRATION PROJECT - INTERIM REPORT

    EPA Science Inventory

    In the project, five chromium emission prevention/control devices were tested tha cover the spectrum of prevention/control techniques currently in use in small- and large-size hard chromium electroplating job shops. The Project results show that some of the tested devices had ch...

  2. Report on interim storage of spent nuclear fuel. Midwestern high-level radioactive waste transportation project

    SciTech Connect

    Not Available

    1993-04-01

    The report on interim storage of spent nuclear fuel discusses the technical, regulatory, and economic aspects of spent-fuel storage at nuclear reactors. The report is intended to provide legislators state officials and citizens in the Midwest with information on spent-fuel inventories, current and projected additional storage requirements, licensing, storage technologies, and actions taken by various utilities in the Midwest to augment their capacity to store spent nuclear fuel on site.

  3. BMDO: New Mexico Technology Transfer Demonstration Project. Interim final report

    SciTech Connect

    Not Available

    1993-11-01

    The BMDO-New Mexico Technology Transfer Demonstration Project(BMDO-NM) was a collaborative effort among the national laboratories to identify and evaluate the commercial potential of selected SDI-funded technologies. The project was funded by BMDO (formerly known as the Strategic Defense Initiative Office or SDIO), the Technology Enterprise Division (NM-TED) of the NM Economic Development Division, and the three National Laboratories. The project was managed and supervised by SAGE Management Partners of Albuquerque, and project funding was administered through the University of New Mexico. The BMDO-NM Demonstration Project focused on the development of a process to assist technology developers in the evaluation of selected BMDO technology programs so that commercialization decisions can be made in an accelerated manner. The project brought together BMDO, the NM-TED, the University of New Mexico, and three New Mexico Federal laboratories -- Los Alamos (DOE), Phillips (DOD) and Sandia (DOE). Each national laboratory actively participated throughout the project through its technology transfer offices. New Mexico was selected as the site for the Demonstration Program because of its three national and federal research laboratories engaged in BMDO programs, and the existing relationship among state govemment, the labs, universities and local economic development and business assistance organizations. Subsequent Commercialization and Implementation phases for the selected technologies from LANL and SNL were completed by SAGE and the Project Team. Funding for those phases was provided by the individual labs as well as BMDO and NM-TED in kind services. NM-TED played a proactive role in this New Mexico partnership. Its mandate is to promote technology-based economic development, with a commitment to facilitate the use of technology by industry and business statewide. TED assumed the role of program manager and executing agent for BMDO in this demonstration project.

  4. Stabilization of in-tank residuals and external-tank soil contamination: FY 1997 interim report

    SciTech Connect

    Becker, D.L.

    1997-10-09

    This interim report evaluates various ways to stabilize decommissioned waste tanks and contaminated soils at the AX Tank Farm as part of a preliminary evaluation of end-state options for the Hanford tanks. Five technical areas were considered: (1) emplacement of smart grouts and/or other materials, (2) injection of chemical-getters into contaminated soils surrounding tanks (soil mixing), (3) emplacement of grout barriers under and around the tanks, (4) the use of engineered barriers over the tanks, and (5) the explicit recognition that natural attenuation processes do occur. Research topics are identified in support of key areas of technical uncertainty, in each of the five technical areas. Detailed cost/benefit analyses of the recommended technologies are not provided in this evaluation, performed by Sandia National Laboratories, Albuquerque, New Mexico.

  5. Reading Between the Lines: Language Indicators Project. Interim Research Summary.

    ERIC Educational Resources Information Center

    Tyler, V. Lynn; Taylor, James S.

    This progress report describes the on-going development of a system to help Americans, especially those who have dealings abroad, to interpret accurately the meaning of messages originating in cultures other than their own. The history, rationale, and methodology of the project are described in detail. Profiles of cultural concepts are provided…

  6. The Developmental Career Guidance Project: An Interim Report.

    ERIC Educational Resources Information Center

    Leonard, George E.; And Others

    The Developmental Career Guidance Project objectives are: (1) to aid a selected group of inner-city high school students to raise and broaden their educational and occupational aspirations, (2) to develop a pilot program designated to better meet the needs of inner-city youth, (3) to involve the staffs of the participating schools in the program,…

  7. The "Project ABLE" General Woodworking Curriculum. (Interim Product).

    ERIC Educational Resources Information Center

    American Institutes for Research in the Behavioral Sciences, Pittsburgh, PA.

    A sample of student tasks and topic objectives which were developed for woodworking courses in Project ABLE are given. A larger collection of these were identified for grades 10, 11, and 12. Prior to this activity an analysis of selected occupations was made, and a frequency count of skills and knowledges was utilized to determine the necessary…

  8. Joint stabilizing projects in defense

    SciTech Connect

    Canavan, G.H.; Browne, J.C.; Joseph, R.J.

    1992-06-01

    Joint defensive projects could increase stability and decrease the alert rates of strategic forces. Areas include the defense of the US, Commonwealth of Independent States (CIS), and their allies against third world threats; protection against each other's accidental or unauthorized launches; and defense against intentional attacks. The most promising area appears to be defining interfaces for the handover of satellite warning and trajectory information, which applies to most phases of theater defense and mutual protection. 19 refs.

  9. Joint stabilizing projects in defense

    SciTech Connect

    Canavan, G.H.; Browne, J.C.; Joseph, R.J.

    1992-06-01

    Joint defensive projects could increase stability and decrease the alert rates of strategic forces. Areas include the defense of the US, Commonwealth of Independent States (CIS), and their allies against third world threats; protection against each other`s accidental or unauthorized launches; and defense against intentional attacks. The most promising area appears to be defining interfaces for the handover of satellite warning and trajectory information, which applies to most phases of theater defense and mutual protection. 19 refs.

  10. Interim report for SNL/NM environmental drilling project

    SciTech Connect

    Wemple, R.P.; Meyer, R.D.; Layne, R.R.

    1994-02-01

    Concern for the environment and cost reduction are the driving forces for a broad effort in government and the private sector to develop new, more cost-effective technologies for characterizing, monitoring and remediating environmental sites. Secondary goals of the characterization, monitoring and remediation (CMR) activity are: minimize secondary waste generation, minimize site impact, protect water tables, and develop methods/strategies to apply new technologies. The Sandia National Laboratories (SNL) project in directional boring for CMR of waste sites with enhanced machinery from the underground utility installation industry was initiated in 1990. Preliminary activities included surveying the directional drilling access needs of various DOE sites, identifying an existing class of machinery that could be enhanced for environmental work through development, and establishing a mutually beneficial working relationship with an industry partner. Since that time the project has tested a variety of prototype machinery and hardware built by the industrial partner, and SNL. The project continues to test and develop the machinery and technique refinements needed for future applications at DOE, DOD, and private sector sites. The original goal of cost-effectiveness is being met through innovation, adaptation, and application of fundamental concepts. Secondary goals are being met via a basic philosophy of ``cut/thrust and compact cuttings without adding large quantities of fluid`` to an environmental problem site. Technology transfer to the private sector is ongoing and ultimately should result in commercial availability of the machinery. Education of regulatory agencies resulting in restructuring appropriate regulatory standards for specification of the horizontal drilling techniques will be a final project goal.

  11. Interim reclamation report, Basalt Waste Isolation project: Boreholes, 1989

    SciTech Connect

    Brandt, C.A.; Rickard, W.H. Jr.; Hefty, M.G.

    1990-03-01

    In 1968, a program was started to assess the feasibility of storing Hanford Site defense waste in deep caverns constructed in basalt. This program was expanded in 1976 to include investigations of the Hanford Site as a potential location for a mined commercial nuclear waste repository. An extensive site characterization program was begun to determine the feasibility of using the basalts beneath the Hanford Site for the repository. Site research focused primarily on determining the direction and speed of groundwater movement, the uniformity of basalt layers, and tectonic stability. Some 98 boreholes were sited, drilled, deepened, or modified by BWIP between 1977 and 1988 to test the geologic properties of the Site. On December 22, 1987, President Reagan signed into law the Nuclear Waste Policy Amendments Act of 1987, which effectively stopped all repository-related activities except reclamation of disturbed lands at the Hanford Site. This report describes the development of the reclamation program for the BWIP boreholes, its implementation, and preliminary estimates of its success. The goal of the reclamation program is to return sites disturbed by the repository program as nearly as practicable to their original conditions using native plant species. 48 refs., 28 figs., 14 tabs.

  12. Interim status report of the TMI personnel-dosimetry project

    SciTech Connect

    Rich, B.L.; Alvarez, J.L.; Adams, S.R.

    1981-06-01

    The current 2-chip TLD personnel dosimeter in use at Three Mile Island (TMI) has been shown inadequate for the anticipated high beta/gamma fields during TMI recovery operations in some areas. This project surveyed the available dosimeter systems, set up an Idaho National Engineering Laboratory (INEL) prototype system, and compared this system with those commercial systems that could be made immediately available for comparison. Of the systems tested, the new INEL personnel dosimeter was found to produce the most accurate results for use in recovery operations at TMI-2. The other multiple-chip or multiple-filter systems were found less desirable at present. The most prominent deficiencies in the INEL dosimeter stem from the fact that it lacks a completely automated reader and its x-ray and thermal neutron responses require additional development. A automated prototype reader system may be in operation by the end of CY-1981. Three alternatives for operational dosimetry are discussed. A combination of a modified version of the presently used Harshaw 2-chip dosimeter and the INEL dosimeter is recommended.

  13. Dewey Decimal Classification Online Project: Interim Reports to the Council on Library Resources, April 1984, September 1984, and February 1985.

    ERIC Educational Resources Information Center

    Markey, Karen; Demeyer, Anh N.

    This research project focuses on the implementation and testing of the Dewey Decimal Classification (DDC) system as an online searcher's tool for subject access, browsing, and display in an online catalog. The research project comprises 12 activities. The three interim reports in this document cover the first seven of these activities: (1) obtain…

  14. 77 FR 55230 - Japan Lessons-Learned Project Directorate Interim Staff Guidance JLD-ISG-2012-01; Compliance With...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-09-07

    ... COMMISSION Japan Lessons-Learned Project Directorate Interim Staff Guidance JLD-ISG-2012-01; Compliance With... Beyond-Design-Basis External Events AGENCY: Nuclear Regulatory Commission (NRC). ACTION: Japan Lessons... Commission (NRC or the Commission) is issuing the Final Japan Lessons-Learned Project Directorate...

  15. Design requirements document for Project W-465, immobilized low-activity waste interim storage

    SciTech Connect

    Burbank, D.A.

    1998-05-19

    The scope of this Design Requirements Document (DRD) is to identify the functions and associated requirements that must be performed to accept, transport, handle, and store immobilized low-activity waste (ILAW) produced by the privatized Tank Waste Remediation System (TWRS) treatment contractors. The functional and performance requirements in this document provide the basis for the conceptual design of the TWRS ILAW Interim Storage facility project and provides traceability from the program level requirements to the project design activity. Technical and programmatic risk associated with the TWRS planning basis are discussed in the Tank Waste Remediation System Decisions and Risk Assessment (Johnson 1994). The design requirements provided in this document will be augmented by additional detailed design data documented by the project.

  16. PROJECT W-551 DETERMINATION DATA FOR EARLY LAW INTERIM PRETREATMENT SYSTEM SELECTION

    SciTech Connect

    TEDESCHI AR

    2008-08-11

    This report provides the detailed assessment forms and data for selection of the solids separation and cesium separation technology for project W-551, Interim Pretreatment System. This project will provide early pretreated low activity waste feed to the Waste Treatment Plant to allow Waste Treatment Plan Low Activity Waste facility operation prior to construction completion of the Pretreatment and High Level Waste facilities. The candidate solids separations technologies are rotary microfiltration and crossflow filtration, and the candidate cesium separation technologies are fractional crystallization, caustic-side solvent extraction, and ion-exchange using spherical resorcinol-formaldehyde resin. This data was used to prepare a cross-cutting technology summary, reported in RPP-RPT-37740.

  17. PROJECT W-551 SUMMARY INFORMATION FOR EARLY LAW INTERIM PRETREATMENT SYSTEM SELECTION

    SciTech Connect

    AR, TEDESCHI

    2008-08-11

    This report provides summary data for use by the decision board to assess and select the final technology for project W-551, Interim Pretreatment System. This project will provide early pretreated low activity waste feed to the Waste Treatment Plant to allow Waste Treatment Plan Low Activity Waste facility operation prior to construction completion of the Pretreatment and High Level Waste facilities. The candidate solids separations technologies are rotary microfiltration and crossflow filtration, and the candidate cesium separation technologies are fractional crystallization, caustic-side solvent extraction, and ion-exchange using spherical resorcinol-fonnaldebyde resin. This document provides a summary of comparative data against prior weighted criteria to support technology selection. Supporting details and background for this summary are documented in the separate report, RPP-RPT-37741.

  18. Environmental Assessment -- Test Area North pool stabilization project update

    SciTech Connect

    1997-08-01

    The purpose of this Environmental Assessment (EA) is to update the ``Test Area North Pool Stabilization Project`` EA (DOE/EA-1050) and finding of no significant impact (FONSI) issued May 6, 1996. This update analyzes the environmental and health impacts of a drying process for the Three Mile Island (TMI) nuclear reactor core debris canisters now stored underwater in a facility on the Idaho National Engineering and Environmental Laboratory (INEEL). A drying process was analyzed in the predecision versions of the EA released in 1995 but that particular process was determined to be ineffective and dropped from the EA/FONSI issued May 6, 1996. A new drying process was subsequently developed and is analyzed in Section 2.1.2 of this document. As did the 1996 EA, this update analyzes the environmental and health impacts of removing various radioactive materials from underwater storage, dewatering these materials, constructing a new interim dry storage facility, and transporting and placing the materials into the new facility. Also, as did the 1996 EA, this EA analyzes the removal, treatment and disposal of water from the pool, and placement of the facility into a safe, standby condition. The entire action would take place within the boundaries of the INEEL. The materials are currently stored underwater in the Test Area North (TAN) building 607 pool, the new interim dry storage facility would be constructed at the Idaho Chemical Processing Plant (ICPP) which is about 25 miles south of TAN.

  19. Draft environmental assessment -- Test Area North pool stabilization project update

    SciTech Connect

    1997-06-01

    The purpose of this Environmental Assessment (EA) is to update the ``Test Area North Pool Stabilization Project`` EA (DOE/EA-1050) and finding of no significant impact (FONSI) issued May 6, 1996. This update analyzes the environmental and health impacts of a drying process for the Three Mile Island (TMI) nuclear reactor core debris canisters now stored underwater in a facility on the Idaho National Engineering and Environmental Laboratory (INEEL). A drying process was analyzed in the predecision versions of the EA released in 1995 but that particular process was determined to be ineffective and dropped form the Ea/FONSI issued May 6, 1996. The origin and nature of the TMI core debris and the proposed drying process are described and analyzed in detail in this EA. As did the 1996 EA, this update analyzes the environmental and health impacts of removing various radioactive materials from underwater storage, dewatering these materials, constructing a new interim dry storage facility, and transporting and placing the materials into the new facility. Also, as did the 1996 EA, this EA analyzes the removal, treatment and disposal of water from the pool, and placement of the facility into a safe, standby condition. The entire action would take place within the boundaries of the INEEL. The materials are currently stored underwater in the Test Area North (TAN) building 607 pool, the new interim dry storage facility would be constructed at the Idaho Chemical Processing Plant (ICPP) which is about 25 miles south of TAN.

  20. Evaluation of the Dwight D. Eisenhower Mathematics and Science State Curriculum Frameworks Projects: First Interim Report, 1996.

    ERIC Educational Resources Information Center

    Humphrey, Daniel C.; And Others

    The first interim report on the Eisenhower State Curriculum Frameworks Projects examines the progress grantee states have made in completing mathematics and science curriculum frameworks and developing new approaches to teacher education, certification, recertification, and professional development. In addition, the report describes many of the…

  1. Summation by parts, projections, and stability

    NASA Technical Reports Server (NTRS)

    Olsson, Pelle

    1993-01-01

    We have derived stability results for high-order finite difference approximations of mixed hyperbolic-parabolic initial-boundary value problems (IBVP). The results are obtained using summation by parts and a new way of representing general linear boundary conditions as an orthogonal projection. By slightly rearranging the analytic equations, we can prove strict stability for hyperbolic-parabolic IBVP. Furthermore, we generalize our technique so as to yield strict stability on curvilinear non-smooth domains in two space dimensions. Finally, we show how to incorporate inhomogeneous boundary data while retaining strict stability. Using the same procedure one can prove strict stability in higher dimensions as well.

  2. AMIC Project: Comparison of WRF High Resolution Dynamical Downscaling of ERA-Interim and EC-Earth for Azores Islands

    NASA Astrophysics Data System (ADS)

    Tomé, Ricardo; Miranda, Pedro; Azevedo, Eduardo; Santo, Fátima

    2013-04-01

    Project AMIC integrates the Portuguese members of the new EC-Earth climate modeling consortium. The aim is to contribute to the IPCC fifth report with a significant set of simulations with a state of the art model, while giving the group timely access to the complete ensemble of simulations for diagnostic studies, and regional downscaling. Additionally, Project AMIC will produce a new set of high resolution simulations of the Portuguese islands climate, using a state of the art model (WRF) at 6km horizontal resolution, with boundary conditions from the new ERA-Interim reanalysis (1989-2009) and from the EC-Earth decadal (20 year) runs. These simulations will allow for validation of the downscaling methodology, and will characterize both the current and near future climate. This study aims to compare two present day climate high resolution dynamical downscaling WRF simulations for the Portuguese islands of Azores using the ECMWF ERA-Interim reanalysis and the EC-Earth v2.3 boundary conditions for the period 1989-2010. In small volcanic islands the local scale climate is influenced by the regional scale climate and by the orography and orientation of air masses over the islands. In these environments the climatological conditions are a vital importance for the local agriculture and water management. With this study we aim to see how well the dynamical downscaling using EC-Earth v2.3 behaves when put against to the ERA-Interim reanalysis. To achieve this goal results from both simulations are compared against with the available observation network in both islands. This study results will show us what kind of deviations we can expect for the future scenarios runs using EC-Earth boundaries currently being made in IDL.

  3. North American Carbon Project (NACP) Regional Interim Synthesis: Terrestrial Biospheric Model Intercomparison

    SciTech Connect

    Huntzinger, Deborah; Post, W. M.; Wei, Yaxing; Michalak, A. M.; West, Tristram O.; Jacobson, Andy; Baker, Ian; Chen, Jing Ming; Davis, K. J.; Hayes, D. J.; Hoffman, F. M.; Jain, Atul K.; Liu, S.; McGuire, A. David; Neilson, R. P.; Potter, Christopher; Poulter, Benjamin; Price, David; Raczka, B. M.; Tian, Hanqin; Thornton, P.; Tomelleri, E.; Viovy, N.; Xiao, J.; Yuan, Wenping; Zeng, Ning; Zhao, M.; Cook, R. B.

    2012-05-10

    Understanding of carbon exchange between terrestrial ecosystems and the atmosphere can be improved through direct observations and experiments, as well as through modeling activities. Terrestrial biosphere models (TBMs) have become an integral tool for extrapolating local observations and understanding to much larger terrestrial regions. Although models vary in their specific goals and approaches, their central role within carbon cycle science is to provide a better understanding of the mechanisms currently controlling carbon exchange. Recently, the North American Carbon Program (NACP) organized several interim-synthesis activities to evaluate and inter-compare models and observations at local to continental scales for the years 2000 to 2005. Here, we compare the results from the TBMs collected as part of the regional and continental interim-synthesis (RCIS) activities. The primary objective of this work is to synthesize and compare the 19 participating TBMs to assess current understanding of the terrestrial carbon cycle in North America.

  4. Program Evaluations. Lessons from Experience: An Interim Review of the Youth Employment and Demonstration Projects Act. Youth Knowledge Development Report 3.19.

    ERIC Educational Resources Information Center

    Butler, Eric; Parker, Jim

    This interim review of the Youth Employment and Demonstration Projects Act (YEDPA) youth programs focuses on five topics through which were considered the universe of need, program experience, and policy recommendations. Chapter 1 is an introduction which briefly describes the law itself, including summaries of its major parts. It also discusses…

  5. Interim Particulate Matter Test Method for the Determination of Particulate Matter from Gas Turbine Engines, SERDP Project WP-1538 Final Report

    EPA Science Inventory

    Under Project No. WP-1538 of the Strategic Environmental Research and Development Program, the U. S. Air Force's Arnold Engineering Development Center (AEDC) is developing an interim test method for non-volatile particulate matter (PM) specifically for the Joint Strike Fighter (J...

  6. Glassy slags for minimum additive waste stabilization. Interim progress report, May 1993--February 1994

    SciTech Connect

    Feng, X.; Wronkiewicz, D.J.; Bates, J.K.; Brown, N.R.; Buck, E.C.; Dietz, N.L.; Gong, M.; Emery, J.W.

    1994-05-01

    Glassy slag waste forms are being developed to complement glass waste forms in implementing Minimum Additive Waste Stabilization (MAWS) for supporting DOE`s environmental restoration efforts. The glassy slag waste form is composed of various crystalline and metal oxide phases embedded in a silicate glass phase. The MAWS approach was adopted by blending multiple waste streams to achieve up to 100% waste loadings. The crystalline phases, such as spinels, are very durable and contain hazardous and radioactive elements in their lattice structures. These crystalline phases may account for up to 80% of the total volume of slags having over 80% metal loading. The structural bond strength model was used to quantify the correlation between glassy slag composition and chemical durability so that optimized slag compositions were obtained with limited crucible melting and testing. Slag compositions developed through crucible melts were also successfully generated in a pilot-scale Retech plasma centrifugal furnace at Ukiah, California. Utilization of glassy slag waste forms allows the MAWS approach to be applied to a much wider range of waste streams than glass waste forms. The initial work at ANL has indicated that glassy slags are good final waste forms because of (1) their high chemical durability; (2) their ability to incorporate large amounts of metal oxides; (3) their ability to incorporate waste streams having low contents of flux components; (4) their less stringent requirements on processing parameters, compared to glass waste forms; and (5) their low requirements for purchased additives, which means greater waste volume reduction and treatment cost savings.

  7. 13 CFR 120.890 - Source of interim financing.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 13 Business Credit and Assistance 1 2011-01-01 2011-01-01 false Source of interim financing. 120... Development Company Loan Program (504) Interim Financing § 120.890 Source of interim financing. A Project may use interim financing for all Project costs except the Borrower's contribution. Any source...

  8. Interim report

    SciTech Connect

    1985-06-01

    This Interim Report summarizes the research and development activities of the Superconducting Super Collider project carried out from the completion of the Reference Designs Study (May 1984) to June 1985. It was prepared by the SSC Central Design Group in draft form on the occasion of the DOE Annual Review, June 19--21, 1985. Now largely organized by CDG Divisions, the bulk of each chapter documents the progress and accomplishments to date, while the final section(s) describe plans for future work. Chapter 1, Introduction, provides a basic brief description of the SSC, its physics justification, its origins, and the R&D organization set up to carry out the work. Chapter 2 gives a summary of the main results of the R&D program, the tasks assigned to the four magnet R&D centers, and an overview of the future plans. The reader wishing a quick look at the SSC Phase I effort can skim Chapter 1 and read Chapter 2. Subsequent chapters discuss in more detail the activities on accelerator physics, accelerator systems, magnets and cryostats, injector, detector R&D, conventional facilities, and project planning and management. The magnet chapter (5) documents in text and photographs the impressive progress in successful construction of many model magnets, the development of cryostats with low heat leaks, and the improvement in current-carrying capacity of superconducting strand. Chapter 9 contains the budgets and schedules of the COG Divisions, the overall R&D program, including the laboratories, and also preliminary projections for construction. Appendices provide information on the various panels, task forces and workshops held by the CDG in FY 1985, a bibliography of COG and Laboratory reports on SSC and SSC-related work, and on private industrial involvement in the project.

  9. First Steps PLUS: Yakima First Steps Mobilization Project for Pregnant Substance Abusers. An Interim Evaluation Report.

    ERIC Educational Resources Information Center

    Nordlund, Daniel J.; And Others

    The Yakima First Steps Mobilization Project for Pregnant Substance Abusers, known as First Steps PLUS, is a demonstration project. The project seeks to improve the health outcomes of pregnant substance abusing women and their infants by enhancing existing perinatal services provided through Washington's First Steps Maternity Care Program and by…

  10. An Evaluation of ESEA Title III Projects, Fiscal Year 1972. Interim Report.

    ERIC Educational Resources Information Center

    Wilson, Jerusa; And Others

    This report contains descriptions and progress of five projects in the District of Columbia partially or wholly funded by ESEA Title III: (1) The Columbia Road Preschool Pilot Project, a second-year experimental effort designed to serve as a model school providing an experimental setting for early childhood educational programs; (2) The Montessori…

  11. The Social Security Administration's Youth Transition Demonstration Projects: Interim Report on Transition WORKS

    ERIC Educational Resources Information Center

    Fraker, Thomas; Black, Alison; Mamun, Arif; Manno, Michelle; Martinez, John; O'Day, Bonnie; O'Toole, Meghan; Rangarajan, Anu; Reed, Debbie

    2011-01-01

    The Social Security Administration is funding a random assignment evaluation of six demonstration projects to improve employment and other outcomes for youth ages 14 to 25 who are either receiving disability benefits or are at high risk of receiving them in the future. This report reviews the Youth Transition Demonstration (YTD) projects, located…

  12. INDEPENDENT TECHNICAL REVIEW OF THE C-400 INTERIM REMEDIAL PROJECT PHASE I RESULTS, PADUCAH, KENTUCKY

    SciTech Connect

    Looney, B.; Rossabi, J.; Stewart,L.; Richards, W.

    2010-10-29

    The groundwater and soil in the vicinity of the C-400 Building at the Paducah Gaseous Diffusion Plant (PGDP), is contaminated with substantial quantities of industrial solvents, primarily trichoroethene (TCE). This solvent 'source' is recognized as a significant challenge and an important remediation target in the overall environmental cleanup strategy for PGDP. Thus, the cleanup of the C-400 TCE Source is a principal focus for the Department of Energy (DOE) and its contractors, and for PGDP regulators and stakeholders. Using a formal investigation, feasibility study and decision process, Electrical Resistance Heating (ERH) was selected for the treatment of the soil and groundwater in the vicinity of C-400. ERH was selected as an interim action to remove 'a significant portion of the contaminant mass of TCE at the C-400 Cleaning Building area through treatment' with the longer term goal of reducing 'the period the TCE concentration in groundwater remains above its Maximum Contaminant Level (MCL).' ERH is a thermal treatment that enhances the removal of TCE and related solvents from soil and groundwater. The heterogeneous conditions at PGDP, particularly the high permeability regional gravel aquifer (RGA), are challenging to ERH. Thus, a phased approach is being followed to implement this relatively expensive and complex remediation technology. Conceptually, the phased approach encourages safety and efficiency by providing a 'lessons learned' process and allowing appropriate adjustments to be identified and implemented prior to follow-on phase(s) of treatment. More specifically, early deployment targeted portions of the challenging RGA treatment zone with relatively little contamination reducing the risk of adverse collateral impacts from underperformance in terms of heating and capture. Because of the importance and scope of the C-400 TCE source remediation activities, DOE chartered an Independent Technical Review (ITR) in 2007 to assess the C-400 ERH plans prior

  13. Test Area North Pool Stabilization Project: Environmental assessment

    SciTech Connect

    1996-05-01

    The Test Area North (TAN) Pool is located within the fenced TAN facility boundaries on the Idaho National Engineering Laboratory (INEL). The TAN pool stores 344 canisters of core debris from the March, 1979, Three Mile Island (TMI) Unit 2 reactor accident; fuel assemblies from Loss-of-Fluid Tests (LOFT); and Government-owned commercial fuel rods and assemblies. The LOFT and government owned commercial fuel rods and assemblies are hereafter referred to collectively as {open_quotes}commercial fuels{close_quotes} except where distinction between the two is important to the analysis. DOE proposes to remove the canisters of TMI core debris and commercial fuels from the TAN Pool and transfer them to the Idaho Chemical Processing Plant (ICPP) for interim dry storage until an alternate storage location other than at the INEL, or a permanent federal spent nuclear fuel (SNF) repository is available. The TAN Pool would be drained and placed in an industrially and radiologically safe condition for refurbishment or eventual decommissioning. This environmental assessment (EA) identifies and evaluates environmental impacts associated with (1) constructing an Interim Storage System (ISS) at ICPP; (2) removing the TMI and commercial fuels from the pool and transporting them to ICPP for placement in an ISS, and (3) draining and stabilizing the TAN Pool. Miscellaneous hardware would be removed and decontaminated or disposed of in the INEL Radioactive Waste Management Complex (RWMC). This EA also describes the environmental consequences of the no action alternative.

  14. Interim Status of the Accelerated Site Technology Deployment Integrated Decontamination and Decommissioning Project

    SciTech Connect

    A. M Smith; G. E. Matthern; R. H. Meservey

    1998-11-01

    The Idaho National Engineering and Environmental Laboratory (INEEL), Fernald Environmental Management Project (FEMP), and Argonne National Laboratory - East (ANL-E) teamed to establish the Accelerated Site Technology Deployment (ASTD) Integrated Decontamination and Decommissioning (ID&D) project to increase the use of improved technologies in D&D operations. The project is making the technologies more readily available, providing training, putting the technologies to use, and spreading information about improved performance. The improved technologies are expected to reduce cost, schedule, radiation exposure, or waste volume over currently used baseline methods. They include some of the most successful technologies proven in the large-scale demonstrations and in private industry. The selected technologies are the Pipe Explorer, the GammaCam, the Decontamination Decommissioning and Remediation Optimal Planning System (DDROPS), the BROKK Demolition Robot, the Personal Ice Cooling System (PICS), the Oxy-Gasoline Torch, the Track-Mounted Shear, and the Hand-Held Shear.

  15. INTERIM EPA GUIDANCE FOR GEOSPATIAL-RELATED QUALITY ASSURANCE PROJECT PLANS

    EPA Science Inventory

    This guidance supplements EPA Guidance for Quality,Assurance Project Plans (EPA QA/G-5), in that the focus here is on collection and use of geospatial rather than other environmental data (e.g., strictly chemical or biological data), including unique aspects of data storage, retr...

  16. Solar Heating/Cooling of Buildings: Current Building Community Projects. An Interim Report.

    ERIC Educational Resources Information Center

    National Academy of Sciences - National Research Council, Washington, DC. Building Research Advisory Board.

    Projects being carried out by the private sector involving the use of solar energy for heating and cooling buildings are profiled in this report. A substantial portion of the data were collected from a broad cross-section of the building community. Data collection efforts also involved the canvassing of the nearly 200 trade and professional…

  17. Interim Report on the Evaluation of the Growth Model Pilot Project

    ERIC Educational Resources Information Center

    Hoffer, Thomas B.; Hedberg, E. C.; Brown, Kevin L.; Halverson, Marie L.; McDonald, Sarah-Kathryn

    2010-01-01

    The Growth Model Pilot Project (GMPP) was initiated to allow states to experiment with adjustments to the No Child Left Behind Act (NCLB) status accountability system in order to improve the validity of AYP determinations by giving schools credit for students who are making significant growth. The pilot allowed states, districts, and schools to…

  18. Interim report on the meteorological database. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Stage, S.A.; Ramsdell, J.V.; Simonen, C.A.; Burk, K.W.

    1993-01-01

    The Hanford Environmental Dose Reconstruction (HEDR) Project is estimating radiation doses that individuals may have received from operations at Hanford from 1944 to the present. An independent Technical Steering Panel (TSP) directs the project, which is being conducted by the Battelle, Pacific Northwest Laboratories in Richland, Washington. The goals of HEDR, as approved by the TSP, include dose estimates and determination of confidence ranges for these estimates. This letter report describes the current status of the meteorological database. The report defines the meteorological data available for use in climate model calculations, describes the data collection procedures and the preparation and control of the meteorological database. This report also provides an initial assessment of the data quality. The available meteorological data are adequate for atmospheric calculations. Initial checks of the data indicate the data entry accuracy meets the data quality objectives.

  19. San Joaquin River Up-Stream DO TMDL Project Task 4: MonitoringStudy Interim Task Report #3

    SciTech Connect

    Stringfellow, William; Borglin, Sharon; Dahlgren, Randy; Hanlon,Jeremy; Graham, Justin; Burks, Remie; Hutchinson, Kathleen

    2007-03-30

    Lander Avenue.This data is specifically being collected to provide data for the Task 6Modeling effort. Task 4 provides input and calibration data for flow andWQ modeling associated with the low DO problems in the SJR watershed,including modeling on the linkage among nutrients, algae, and low DO.Task 4 is providing a higher volume of high quality and coherent data tothe modeling team than was available in the past for the upstream SJR.The monitoring and research activities under Task 4 are integrated withthe Modeling effort (Task 6) and are not designed to be a stand aloneprogram. Although, the majority of analysis of the Task 4 data isoccurring as part of the Task 6 Modeling program, analysis of Task 4 dataindependently of the modeling effort is also an important component ofthe DO TMDL Project effort. In this report, we present the results ofmonitoring and research conducted under Task 4. The major purposes ofthis report are to 1) document activities undertaken as part of theDOTMDL Project; 2) organize electronic data for delivery to Stateagencies, stakeholders and principal investigators (cooperators) on theDO TMDL Project; 3) provide a summary analysis of the data for referenceand to assist stakeholders in planning watershed activities inresponse tothe DO TMDL requirements; and 5) provide a preliminary scientificinterpretation independently of the Task 6 Modeling effort. Due to theextensive scope of theTask 4 portion of the DO TMDL Project, the Task 4March 2007 Interim Report is divided into a numbers of chapters andassociated appendixes designed to be able to stand1-3 independently ofeach other. The purpose of this chapter is to provide an overview of Task4 data collection and to explain the structure of the overallreport.

  20. High-occupancy vehicle project case studies: Historical trends and project experiences. Interim report 1989-92

    SciTech Connect

    Turnbull, K.F.

    1992-08-01

    The report presents the examination of historical trends and current experiences with high occupancy vehicle (HOV) projects in six selected case study sites. HOV facilities in Houston, Texas; Minneapolis, Minnesota; Orange County, California; Pittsburgh, Pennsylvania; Seattle, Washington; and Washington, D.C./Northern Virginia are examined. In addition, available information on other HOV projects located on freeways or in separate rights-of-way is reviewed.

  1. Interim reclamation report, Basalt Waste Isolation Project Near Surface Test Facility 1990

    SciTech Connect

    Brandt, C.A.; Rickard, W.H. Jr.; Hefty, M.G.; Cadoret, N.A.

    1991-01-01

    This report describes the development of the reclamation project for the Hanford Site Near Surface Test Facility (NSTF), its implementation, and preliminary estimates of its success. The goal of the reclamation project is to return disturbed sites as nearly as practicable to their original conditions using native species. Gable Mountain is dominated by two plant communities: a big sagebrush (Artemisia tridentata) -- Sandberg's bluegrass (Poa sandbergii) community and a stiff sagebrush (Artemisia rigida) -- Sandberg's bluegrass community. Disassembly of the site installations began on March 15, 1988, and the site was returned to original contours by December 12, 1988. Two separate revegetation methods were employed at the NSTF to meet differing site constraints. Vegetative cover and density in the revegetation plots were assessed in April 1989 and again in June 1989 and 1990. It is extremely unlikely that the sand pit, borrow pit, box cuts, generator pad area, or ventilation fan area will reach the reclamation objectives set for these areas within the next 50 years without further intervention. These areas currently support few living plants. Vegetation on revegetated native soils appears to be growing as expected. Vegetation growth on the main waterline is well below the objective. To date, no shrubs have grown on the area, growth of native grasses is well below the objective, and much of the area has been covered with the pit run material, which may not support adequate growth. Without further treatments, the areas without the pit run material will likely revert to a nearly pure cheatgrass condition. 44 refs., 13 figs., 7 tabs.

  2. Medium Truck Duty Cycle Data from Real-World Driving Environments: Project Interim Report

    SciTech Connect

    Franzese, Oscar; Lascurain, Mary Beth; Capps, Gary J

    2011-01-01

    Since the early part of the 20th century, the US trucking industry has provided a safe and economical means of moving commodities across the country. At the present time, nearly 80% of the US domestic freight movement involves the use of trucks. The US Department of Energy (DOE) is spearheading a number of research efforts to improve heavy vehicle fuel efficiencies. This includes research in engine technologies (including hybrid and fuel cell technologies), lightweight materials, advanced fuels, and parasitic loss reductions. In addition, DOE is developing advanced tools and models to support heavy vehicle truck research, and is leading the 21st Century Truck Partnership whose stretch goals involve a reduction by 50% of the fuel consumption of heavy vehicles on a ton-mile basis. This Medium Truck Duty Cycle (MTDC) Project is a critical element in DOE s vision for improved heavy vehicle energy efficiency and is unique in that there is no other national database of characteristic duty cycles for medium trucks. It involves the collection of real-world data for various situational characteristics (rural/urban, freeway/arterial, congested/free-flowing, good/bad weather, etc.) and looks at the unique nature of medium trucks drive cycles (stop-and-go delivery, power takeoff, idle time, short-radius trips), to provide a rich source of data that can contribute to the development of new tools for fuel efficiency and modeling, provide DOE a sound basis upon which to make technology investment decisions, and provide a national archive of real-world-based medium-truck operational data to support heavy vehicle energy efficiency research. The MTDC project involves a two-part field operational test (FOT). For the Part-1 FOT, three vehicles, each from two vocations (urban transit and dry-box delivery) were instrumented for one year of data collection. The Part-2 FOT will involve the towing/recovery and utility vocations. The vehicles participating in the MTDC project are doing so

  3. Measuring Adolescent Personality. Project TALENT Five Year Follow-up Studies. Interim Report One. Project Number 3051.

    ERIC Educational Resources Information Center

    Lohnes, Paul R.

    Project data is organized to provide a valid, simplified description of American adolescents which should be of use to guidance personnel. A chapter on educational achievement traits presents an overview of the factor solution for the abilities domain, and describes the compositions of the three factors that represent core achievement traits:…

  4. Stabilizing a Bicycle: A Modeling Project

    ERIC Educational Resources Information Center

    Pennings, Timothy J.; Williams, Blair R.

    2010-01-01

    This article is a project that takes students through the process of forming a mathematical model of bicycle dynamics. Beginning with basic ideas from Newtonian mechanics (forces and torques), students use techniques from calculus and differential equations to develop the equations of rotational motion for a bicycle-rider system as it tips from…

  5. National Study of Student Support Services. Interim Report: Volume 2: Profile of Freshman Participants and Project Services: 1991-92.

    ERIC Educational Resources Information Center

    Cahalan, Margaret; And Others

    An interim report on the congressionally mandated National Study of Student Support Services (SSS) focuses on the characteristics of college freshmen program participants and on the level and type of services they receive. The federally funded grant program is designed to help economically disadvantaged students achieve success at the…

  6. Leading Curriculum Innovation in Primary Schools Project: An Interim Report on School Leaders' Roles in Curriculum Development in England

    ERIC Educational Resources Information Center

    Brundrett, Mark; Duncan, Diane; Rhodes, Christopher

    2010-01-01

    This article provides an interim report on a two-phase study of curriculum innovation in primary schools in England during one of the most significant periods of change for the last two decades. More specifically, the study addresses the challenges to school leaders created by the Rose Review of the primary curriculum. This article presents and…

  7. Site 300 hazardous-waste-assessment project. Interim report: December 1981. Preliminary site reconnaissance and project work plan

    SciTech Connect

    Raber, E.; Helm, D.; Carpenter, D.; Peifer, D.; Sweeney, J.

    1982-01-20

    This document was prepared to outline the scope and objectives of the Hazardous Waste Assessment Project (HWAP) at Site 300. This project was initiated in October, 1981, to investigate the existing solid waste landfills in an effort to satisfy regulatory guidelines and assess the potential for ground-water contamination. This involves a site-specific investigation (utilizing geology, hydrology, geophysics and geochemistry) with the goal of developing an effective ground-water quality monitoring network. Initial site reconnaissance work has begun and we report the results, to date, of our geologic hydrogeologic studies. All known solid waste disposal locations are underlain by rocks of either the Late Miocene Neroly Formation or the Cierbo Formation, both of which are dominantly sandstones interbedded with shale and claystone. The existence of a regional confined (artesian) aquifer, as well as a regional water-table aquifer is postulated for Site 300. Preliminary analysis has led to an understanding of directions and depths of regional ground-water flow.

  8. NNWSI PROJECT ELEMENT WBS-1.2.6.9.4.6.1.B INTERIM REPORT ON DUST CONTROL PROPOSALS

    SciTech Connect

    D.J. Burton

    2005-09-06

    This report presents interim findings of studies conducted to evaluate dust control equipment during prototype drilling. Based on available data on silica content, type, particle size, and on proposed dry drilling operations, it is estimated that allowable exposures to free silica will range from 0.07 to 1.5 mg/cu meter. They have concluded that airborne concentrations of dust may approach or exceed these values during normal operations, based on studies conducted as part of this task.

  9. 13 CFR 120.890 - Source of interim financing.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 13 Business Credit and Assistance 1 2010-01-01 2010-01-01 false Source of interim financing. 120.890 Section 120.890 Business Credit and Assistance SMALL BUSINESS ADMINISTRATION BUSINESS LOANS Development Company Loan Program (504) Interim Financing § 120.890 Source of interim financing. A Project...

  10. Solidification/stabilization of used abrasive media for non-structural concrete using portland cement. Interim research report

    SciTech Connect

    Webster, M.T.; Carrasquillo, R.L.; Loehr, R.C.; Fowler, D.W.

    1994-11-01

    Highway bridges in the United States are painted to resist corrosion and to help maintain the structural integrity of the bridge. Periodically, it is necessary to remove the existing paint so that the surface can be repainted. Most often the removal process consists of blasting the surface with an abrasive such as sand or slag. The blast media then contains elements present in the paint, such as cadmium, chromium and lead. The spent media may be a hazardous waste as defined by EPA`s Toxicity Characteristic (TC) criterion. This criterion uses the Toxicity Characteristic Leaching Procedure (TCLP) to determine whether a waste is classified as a hazardous waste. This procedure subjects the waste to a highly acidic environment in which chemicals can leach out of the waste. The leachate enviornment is then analyzed to determine the concentration of chemical leached, which must fall within the TC criterion. Some spent blasting material has been shown to have TCLP metal concentrations exceeding the TC criterion. The Texas Department of Transportation (TxDOT) has begun to recycle spent abrasive media in portland cement-based concrete using solidification/stabilization (S/S) techniques. This technology is designed to immobilize the metals while recycling the spent abrasive media as a component in non-structural concrete. The study has revealed the effectiveness of portland cement-based S/S systems in recycling contaminated spent abrasive media in portland cement-based concrete. The long-term leaching behavior of metals from these concrete products was examined using sequential extraction leaching tests.

  11. Plume Mitigation for Mars Terminal Landing: Soil Stabilization Project

    NASA Technical Reports Server (NTRS)

    Hintze, Paul E.

    2014-01-01

    Kennedy Space Center (KSC) has led the efforts for lunar and Martian landing site preparation, including excavation, soil stabilization, and plume damage prediction. There has been much discussion of sintering but until our team recently demonstrated it for the lunar case there was little understanding of the serious challenges. Simplistic sintering creates a crumbly, brittle, weak surface unsuitable for a rocket exhaust plume. The goal of this project is to solve those problems and make it possible to land a human class lander on Mars, making terminal landing of humans on Mars possible for the first time.

  12. Louisiana Adult Education Staff Development Project. Interim Report, May 1, 1973-May31, 1974. Publication No. 1428.

    ERIC Educational Resources Information Center

    Boyet, Robert W., Comp.; And Others

    The report contains summaries and materials describing the second year of a Louisiana project to train teachers of reading for illiterate adults. Meeting a major objective, the project increased the number of State colleges and universities offering credit courses in adult education to 10, for a total of 27 courses enrolling 716 local adult…

  13. School Capital Manual. An Interim Guide for School Boards, Administrators, Facility Planners and Consultants Who Engage in School Building Projects.

    ERIC Educational Resources Information Center

    Alberta Dept. of Education, Edmonton.

    This manual is intended for use by the Alberta, Canada, school boards, administrators, consultants, education staff, and other individuals involved in school building projects. The purpose of the School Capital Plan, funding, and Alberta Education's funding framework are detailed. The school building project components of the School Capital Plan…

  14. A Process Evaluation of Project Developmental Continuity. Interim Report II, Part A: Program Case Studies. Volume I.

    ERIC Educational Resources Information Center

    Spencer, Lynn, Ed.

    These 8 case studies are part of a series of documents on the evaluation of Project Developmental Continuity (PDC), a Head Start demonstration program aimed at providing educational and developmental continuity between children's Head Start and primary school experiences. Each case study reviews the planning year at a PDC demonstration site in one…

  15. A Process Evaluation of Project Developmental Continuity. Interim Report II, Part A: Program Case Studies. Volume 2.

    ERIC Educational Resources Information Center

    Spencer, Lynn, Ed.

    These 7 case studies are part of a series of documents on the evaluation of Project Developmental Continuity (PDC), a Head Start demonstration program aimed at providing educational and developmental continuity between children's Head Start and primary school experiences. Each case study reviews the planning year at a PDC demonstration site in one…

  16. The Intentional Interim

    ERIC Educational Resources Information Center

    Nugent, Patricia A.

    2011-01-01

    The author spent years in central-office administration, most recently in an interim position. Some interim administrators simply see themselves as placeholders until the real deal is hired, giving the organization the opportunity to coast. There are others who see themselves as change agents and cannot wait to undo or redo what their predecessor…

  17. Interim response action basin F liquid incineration project final draft human health risk assessment. Volume 1. Final draft report

    SciTech Connect

    1991-07-01

    This document is a comprehensive, multiple exposure pathway, human health risk assessment prepared for the proposed Basin F Liquid Incineration Project. The submerged quench incinerator will treat Basin F liquid and hydrazine rinse water. The objective of the risk assessment is to establish chemical emission limits which are protective of human health. Average and maximum lifetime daily intakes were calculated for adults, children, and infants in four maximum exposure scenarios under base case and sensitivity case emissions condition. It was concluded that the incineration facility poses neither carcinogenic nor noncarcinogenic risk to any sensitive population. The assessment is divided into: (1) Incineration facility description; (2) Description of surrounding area; (3) Process of pollutant identification and selection; and (4) Determination of emission rates from incineration facility.

  18. Development of an EMF Measurments Database, EMF Rapid Program, Project #5, Interim Report: April 1995-December 1996

    SciTech Connect

    T. Dan Bracken, Inc.

    1998-03-01

    The EMF Measurements Database project is being implemented by T. Dan Bracken, Inc. as part of the EMF Research and Public Information Dissemination (EMF RAPID) Program. The Database is a collection of data sets that relate to measurement of electric and/or magnetic fields. This report describes activities during the period January 1997 to March 1998. Primary goals for the EMF Measurements Database are to develop a database structure that can accommodate the diversity of EMF data sets, provide guidance for production of future EMF data sets, and serve as an accessible repository of EMF measurement data. Specific objectives of the EMF Measurements Database are: o to presewe study descriptions, results and data; o to provide readily accessible, well-documented data; and - o to facilitate communication among researchers. In addition, the EMF Measurements Database will encourage additional analysis of existing data sets, facilitate analysis of data from multiple projects, support design of new studies, and permit future issues in EMF exposure assessment to be addressed with existing data. Preservation of study descriptions and data is accomplished with a formal, but open, structure. Specifications have been developed for the various elements of the database. Each data set in the database is formally described by a metadata file. The structured metadata file describes the origin, development, logical and physical structure, and distribution mechanism for each data set. The metadata for each data set is generated according to a specification developed for the EMF Measurements Database. The actual measurement data is contained in data products for each data set. The number and type of data product will vary by data set. Most of the data products available from the EMF Measurements Database can be downloaded from an Internet site. For some data sets, the data products will be maintained by other patties who may have their own access procedures.

  19. Instructional System Design for Executive Orientation and Project Management Training Packages, Technical Memorandum No. 3. Interim Report. RF Project No. 3131-A1.

    ERIC Educational Resources Information Center

    Cook, Desmond L.; And Others

    This memorandum reports on the third phase, the design, of a four-phase project to design project management training materials for local educational agencies. The first section of the memorandum explains some considerations regarding management education and the organization of the report. Section 2 presents the design specifications for the…

  20. Computer-Based Exercises in Anemia and Chest Pain Diagnosis: An Interim Evaluation of the PlanAlyzer Project

    PubMed Central

    Lyon, Harold C.; Healy, James C.; Bell, James R.; O'Donnell, Joseph F.; Hirai, Frank; Moore-West, Margaret; Cornwell, Gibbons G.; Brooks, W. Blair; Spackman, Kent A.; Beck, J. Robert

    1990-01-01

    PlanAlyzer is a microcomputer-based, self-paced, case-based, event-driven system for medical education. Aimed at the second year medical student, PlanAlyzer presents cases, elicits and critiques a student's approach to the diagnosis of two common medical disorders: anemias and chest pain. PlanAlyzer uses text, hypertext, images and critiquing theory. Students were randomized, one half becoming the experimental group who received the interactive PlanAlyzer cases in anemia, the other half becoming the controls who received the exact same content material in a text format. Later in each year there was a crossover, the controls becoming the experimentals for a similar intervention with the cardiology PlanAlyzer cases. Preliminary results at the end of the first two trials shows that the programs have achieved most of the proposed instructional objectives, plus some significant efficiency and economy gains. 96 faculty hours of classroom time were saved by using PlanAlyzer in their place, while, maintaining high student achievement. In terms of student proficiency and efficiency, the 176 students in the trial were able to accomplish the project's instructional objectives, and the experimentals accomplished this in less time than the controls. The research suggests additional inquiry in several areas: better evaluation instruments to measure the problem solving skills PlanAlyzer was designed to teach; use of hypertext PlanAlyzer cases to find if such a mode results in performance and/or efficiency differences; through the addition of interactive video, broaden PlanAlyzer to include additional behaviors subsumed under the topic of clinical problem solving, such as patient management strategies and the role of patients' affective behavior and non-verbal cues in the data gathering process.

  1. Development of an EMF Measurements Database, EMF Rapid Program, Project #5, Interim Report: April 1995-December 1996

    SciTech Connect

    T. Dan Bracken, Inc.

    1997-04-01

    The EMF measurement data sets in existence today were compiled with varying goals and techniques. Consequently, they have different information content as well as varying logical and physical structure. Future studies will continue to pursue varying goals and utilize techniques that cannot be known in advance. Primary goals for the EMF Measurements Database developed under the Department of Energy EMF RAPID Program are to develop a database structure that can accommodate the diversity of EMF data sets, provide guidance for production of future EMF data sets, and serve as an accessible repository of EMF measurement data. Specific objectives of the EMF Measurements Database are: o to preserve study descriptions, results and data; o to provide readily accessible, well-documented data; and o to facilitate communication among researchers. In addition, the EMF Measurements Database will encourage additional analysis of existing data sets, facilitate analysis of data from multiple projects, support design of new studies, and permit future issues in EMF exposure assessment to be addressed with existing data. Preservation of study descriptions and data is accomplished with a formal, but open, structure. Specifications have been developed for the various elements of the database. Each data set in the database is formally described by a metadata file. The structured metadata file describes the origin, development, logical and physical structure and distribution mechanism for each data set. The metadata for each data set is generated according to a specification developed for the EMF Measurements Database. The actual measurement data is contained in data Products for each data set. The number and type of data product will vary by data set. Most of the data products in the possession of the EMF Measurements Database are available for download from an Internet site. For some data sets, the data products will be maintained by other parties who may have their own access procedures

  2. Effects of a coal-fired power plant and other sources on southwestern visibility (interim summary of EPA'S project VISTTA)

    NASA Astrophysics Data System (ADS)

    Blumenthal, D. L.; Richards, L. W.; Macias, E. S.; Bergstrom, R. W.; Wilson, W. E.; Bhardwaja, P. S.

    ('D) was found to adequately simulate the plume chemistry for the clean dry background conditions at NGS. Participants include Meteorology Research, Inc. (MRI), Systems Applications, Inc. (SAI), Washington University (WU), U of Minnesota (UM), U of Washington (UW), U of California at Los Angeles (UCLA), Washington State U (WSU), U of Vienna (UV), Harvey Mudd College (HMC), U of California at Davis (UCD), EPA Las Vegas (EMSL) (EPA-LV), and Salt River Project (SRP).

  3. 33 CFR 385.38 - Interim goals.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    .... (ii) Improvement in water quality; including: (A) Total phosphorus concentrations in the Everglades... System and Water Availability Consistent With the Goals and Purpose of the Plan § 385.38 Interim goals... the South Florida Water Management District shall sequence and schedule projects as appropriate...

  4. 33 CFR 385.38 - Interim goals.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    .... (ii) Improvement in water quality; including: (A) Total phosphorus concentrations in the Everglades... System and Water Availability Consistent With the Goals and Purpose of the Plan § 385.38 Interim goals... the South Florida Water Management District shall sequence and schedule projects as appropriate...

  5. 33 CFR 385.38 - Interim goals.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    .... (ii) Improvement in water quality; including: (A) Total phosphorus concentrations in the Everglades... System and Water Availability Consistent With the Goals and Purpose of the Plan § 385.38 Interim goals... the South Florida Water Management District shall sequence and schedule projects as appropriate...

  6. 33 CFR 385.38 - Interim goals.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    .... (ii) Improvement in water quality; including: (A) Total phosphorus concentrations in the Everglades... System and Water Availability Consistent With the Goals and Purpose of the Plan § 385.38 Interim goals... the South Florida Water Management District shall sequence and schedule projects as appropriate...

  7. 33 CFR 385.38 - Interim goals.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    .... (ii) Improvement in water quality; including: (A) Total phosphorus concentrations in the Everglades... System and Water Availability Consistent With the Goals and Purpose of the Plan § 385.38 Interim goals... the South Florida Water Management District shall sequence and schedule projects as appropriate...

  8. Automotive Mechanics Occupational Performance Survey. Interim Report.

    ERIC Educational Resources Information Center

    Borcher, Sidney D.; Leiter, Paul B.

    The purpose of this federally-funded interim report is to present the results of a task inventory analysis survey of automotive mechanics completed by project staff within the Instructional Systems Design Program at the Center for Vocational and Technical Education. Intended for use in curriculum development for vocational education programs in…

  9. 15 CFR 908.5 - Interim reports.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... SUBMITTING REPORTS ON WEATHER MODIFICATION ACTIVITIES § 908.5 Interim reports. (a) Any person engaged in a weather modification project or activity in the United States on January 1 in any year shall submit to the... actual modification activities took place; (2) Number of days on which weather modification...

  10. Longitudinal stability of cognitive ability in the Colorado Adoption Project.

    PubMed

    Baker, L A; DeFries, J C; Fulker, D W

    1983-04-01

    Measures of general cognitive ability in 1- and 2-year-old adopted and nonadopted infants and their parents were subjected to path analysis to estimate the contribution of genetic and environmental factors to short-term stability. Although significant genetic influences were found at both 1 and 2 years of age, no significant environmental influences shared by parents and children were observed at these ages. Short-term stability of mental ability between the 2 ages was relatively independent of both between-family genetic and environmental influences. However, genetic factors may contribute importantly to long-term stability.

  11. Project Execution Plan Project 98L-EWW-460 Plutonium Stabilization and Handling DOE 98-D-453

    SciTech Connect

    HOLSTEIN, W.A.

    1999-08-01

    This Project Execution Plan (PEP) describes the management methods and responsibilities of the project participants. Project W-460 is sufficiently large to warrant a stand alone PEP. This project specific PEP describes the relationships and responsibilities of the project team and identifies the technical, schedule, and cost baselines that have been established for the project. The Department of Energy (DOE), Hanford Works (Hanford), at Richland Wa. currently does not have a system capable of stabilizing or packaging large quantities of plutonium-bearing solids to meet DOE technical standard DOE-STD-3013-96. This project will allow Hanford to meet this standard by installing stabilization and packaging equipment (SPE). The SPE is capable of stabilizing and packaging the current inventory of greater than 50 percent plutonium-bearing materials currently stored in the Plutonium Finishing Plant's (PFP) vaults into 3013 storage containers. The scope of this project is to procure and install the SPE via a Hanford contract and coordination with the Savannah River Site. In addition, the project will modify PFP vaults and upgrade the PFP Laboratory measurement systems. The Facility infrastructure will be modified to support the new SPE system and the new standardized storage container configuration.

  12. Project Execution Plan Project 98L-EWW-460 Plutonium Stabilization and Handling DOE 98-D-453

    SciTech Connect

    MCGRATH, G.M.

    2000-06-21

    This Project Execution Plan (PEP) describes the management methods and responsibilities of the project participants. Project W-460 is sufficiently large to warrant a stand alone PEP. This project specific PEP describes the relationships and responsibilities of the project team and identifies the technical, schedule, and cost baselines that have been established for the project. The Department of Energy (DOE), Hanford Works (Hanford), at Richland, Wa. currently does not have a system capable of stabilizing or packaging large quantities of plutonium-bearing solids to meet DOE technical standard DOE-STD-3013-99. This project will allow Hanford to meet this standard by installing stabilization and packaging equipment (SPE). The SPE is capable of stabilizing and packaging the current inventory of greater than 30 percent plutonium-bearing materials currently stored in the Plutonium Finishing Plant's (PFP) vaults into 3013 storage containers. The scope of this project is to procure and install the SPE via a Hanford contract and coordination with the Savannah River Site. In addition, the project will modify PFP vaults and upgrade the PFP Laboratory measurement systems. The Facility infrastructure will be modified to support the new SPE system and the new standardized storage container configuration.

  13. Local projection stabilization of equal order interpolation applied to the Stokes problem

    NASA Astrophysics Data System (ADS)

    Ganesan, Sashikumaar; Matthies, Gunar; Tobiska, Lutz

    2008-12-01

    The local projection stabilization allows us to circumvent the Babuska-Brezzi condition and to use equal order interpolation for discretizing the Stokes problem. The projection is usually done in a two-level approach by projecting the pressure gradient onto a discontinuous finite element space living on a patch of elements. We propose a new local projection stabilization method based on (possibly) enriched finite element spaces and discontinuous projection spaces defined on the same mesh. Optimal order of convergence is shown for pairs of approximation and projection spaces satisfying a certain inf-sup condition. Examples are enriched simplicial finite elements and standard quadrilateral/hexahedral elements. The new approach overcomes the problem of an increasing discretization stencil and, thus, is simple to implement in existing computer codes. Numerical tests confirm the theoretical convergence results which are robust with respect to the user-chosen stabilization parameter.

  14. Longitudinal Stability of Cognitive Ability in the Colorado Adoption Project.

    ERIC Educational Resources Information Center

    Baker, Laura A.; And Others

    1983-01-01

    Measures of general cognitive ability in one- and two-year-old adopted and nonadopted infants and their parents were subjected to path analysis to estimate the contribution of genetic and environmental factors to short-term stability of mental ability. (Author/RH)

  15. Conceptual design report, plutonium stabilization and handling,project W-460

    SciTech Connect

    Weiss, E.V.

    1997-03-06

    Project W-460, Plutonium Stabilization and Handling, encompasses procurement and installation of a Stabilization and Packaging System (SPS) to oxidize and package for long term storage remaining plutonium-bearing special nuclear materials currently in inventory at the Plutonium Finishing Plant (PFP), and modification of vault equipment to allow storage of resulting packages of stabilized SNM for up to fifty years. This Conceptual Design Report (CDR) provides conceptual design details for the vault modification, site preparation and site interface with the purchased SPS. Two concepts are described for vault configuration; acceleration of this phase of the project did not allow completion of analysis which would clearly identify a preferred approach.

  16. Oak Ridge National Laboratory Gunite and Associated Tanks Stabilization Project-Low-Tech Approach with High-Tech Results

    SciTech Connect

    Brill, A.; Alsup, T.; Bolling, D.

    2002-02-26

    Environmental restoration of the Gunite and Associated Tanks (GAAT) at the Oak Ridge National Laboratory (ORNL) was a priority to the U. S. Department of Energy (DOE) because of their age and deteriorating structure. These eight tanks ranging up to 170,000 gallons in capacity were constructed in 1943 of a Gunite or ''sprayed concrete material'' as part of the Manhattan Project. The tanks initially received highly radioactive waste from the Graphite Reactor and associated chemical processing facilities. The waste was temporarily stored in these tanks to allow for radioactive decay prior to dilution and release into surface waters. Over time, additional wastes from ongoing ORNL operations (e.g., isotope separation and materials research) were discharged to the tanks for storage and treatment. These tanks were taken out of service in the 1970s. Based on the structure integrity of GAAT evaluated in 1995, the worst-case scenario for the tanks, even assuming they are in good condition, is to remain empty. A recently completed interim action conducted from April 1997 through September 2000 removed the tank liquids and residual solids to the extent practical. Interior video surveys of the tanks indicated signs of degradation of the Gunite material. The tanks continued to receive inleakage, which generated a relatively high volume waste stream that required periodic removal, treatment, and disposal. For these reasons, DOE chose in-place stabilization of Tanks W-3 through W-10 as a non-timecritical removal action under Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Tank stabilization activities involved removal of liquid from inleakage and placement of a grout mixture or ''flowable fill'' into the tanks to within 3-ft of the ground surface. Bechtel Jacobs Company, LLC (BJC) awarded Safety and Ecology Corporation (SEC) a subcontract in March 2001 to complete the documentation and fieldwork necessary to achieve tank stabilization in

  17. Intel International Interim Report

    ERIC Educational Resources Information Center

    Martin, Wendy; Mandinach, Ellen; Kanaya, Tomoe; Culp, Katie McMillan

    2004-01-01

    This interim report presents preliminary data and observations from evaluations of Intel Teach to the Future being conducted around the world, and recommendations for building and refining this evaluation portfolio to ensure that findings will be instructive at the local, national and international level. The data presented here reflect the…

  18. Conceptual design report for immobilized high-level waste interim storage facility (Phase 1)

    SciTech Connect

    Burgard, K.C.

    1998-04-09

    The Hanford Site Canister Storage Building (CSB Bldg. 212H) will be utilized to interim store Phase 1 HLW products. Project W-464, Immobilized High-Level Waste Interim Storage, will procure an onsite transportation system and retrofit the CSB to accommodate the Phase 1 HLW products. The Conceptual Design Report establishes the Project W-464 technical and cost basis.

  19. Conceptual design report for immobilized high-level waste interim storage facility (Phase 1)

    SciTech Connect

    Burgard, K.C.

    1998-06-02

    The Hanford Site Canister Storage Building (CSB Bldg. 212H) will be utilized to interim store Phase 1 HLW products. Project W-464, Immobilized High-Level Waste Interim Storage, will procure an onsite transportation system and retrofit the CSB to accommodate the Phase 1 HLW products. The Conceptual Design Report establishes the Project W-464 technical and cost basis.

  20. Fluor Hanford Nuclear Material Stabilization Project Welding Manual

    SciTech Connect

    BERKEY, J.R.

    2000-10-20

    The purpose of this section of the welding manual is to: (1) Provide a general description of the major responsibilities of the organizations involved with welding. (2) Provide general guidance concerning the application of codes related to welding. This manual contains requirements for welding for all Fluor Hanford (FH) welding operators working on the W460 Project, in the Plutonium Finishing Plant (PFP) at the U. S. Department of Energy (DOE) Hanford facilities. These procedures and any additional requirements for these joining processes can be used by all FH welding operators that are qualified. The Welding Procedure Specifications (WPS) found in this document were established from Procedure Qualification Records (PQR) qualified by FH specifically for the W460 Project. PQRs are permanent records of the initial testing and qualification program and are used to backup, and support, the WPS. The identification numbers of the supporting PQR(s) are recorded on each WPS. All PQRs are permanently stored under the supervision of the Fluor Hanford Welding Engineer (FHWE). New PQRs and WPSs will continue to be developed as necessary. The qualification of welders, welding operators and welding procedures will be performed for FH under supervision and concurrent of the FHWE. All new welding procedures to be entered in this manual or welder personnel to be added to the welder qualification database, shall be approved by the FHWE.

  1. 76 FR 4369 - Interim Deputation Agreements; Interim BIA Adult Detention Facility Guidelines

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-01-25

    ... Bureau of Indian Affairs Interim Deputation Agreements; Interim BIA Adult Detention Facility Guidelines... publication of the Interim BIA Adult Detention Facility Guidelines and the Interim Model Deputation Agreements... Interim BIA Adult Detention Facility Guidelines and Interim Model Deputation Agreements are effective...

  2. CMM Interim Check (U)

    SciTech Connect

    Montano, Joshua Daniel

    2015-03-23

    Coordinate Measuring Machines (CMM) are widely used in industry, throughout the Nuclear Weapons Complex and at Los Alamos National Laboratory (LANL) to verify part conformance to design definition. Calibration cycles for CMMs at LANL are predominantly one year in length. Unfortunately, several nonconformance reports have been generated to document the discovery of a certified machine found out of tolerance during a calibration closeout. In an effort to reduce risk to product quality two solutions were proposed – shorten the calibration cycle which could be costly, or perform an interim check to monitor the machine’s performance between cycles. The CMM interim check discussed makes use of Renishaw’s Machine Checking Gauge. This off-the-shelf product simulates a large sphere within a CMM’s measurement volume and allows for error estimation. Data was gathered, analyzed, and simulated from seven machines in seventeen different configurations to create statistical process control run charts for on-the-floor monitoring.

  3. Lasic -Cavity-enhanced molecular iodine laser frequency stabilization for space projects

    NASA Astrophysics Data System (ADS)

    Turazza, Oscar; Acef, O.; Auger, G.; Halloin, H.; Duburck, F.; Plagnol, E.; Holleville, D.; Dimarcq, N.; Binetruy, P.; Brillet, A.; Lemonde, P.; Devismes, E.; Prat, P.; Lours, M.; Tuckey, P.; Argence, B.

    We present work in progress at SYRTE, APC and ARTEMIS aiming at stabilizing the frequency of a Nd:YAG laser using saturated absorption spectroscopy of molecular iodine 127I2. The novel design of the LASIC project allows for robustness and compacity while achieving high-performance phase noise suppression. The project is a follow-up of the laser stabilization work started at Artemis and continued at APC. The use of a low-finesse bow-tie optical cavity around the iodine absorber, combined with an adapted high-frequency modulation of the laser phase -NICE-OHMS technique-yields shot-noise limited saturated absorption signals with cavity-enhanced signal-to-noise ratios. Residual fractional frequency instability in terms of Allan Std. Deviation is expected below 10-14 @1s integration time and down to 10-15 over several hours. The compact iodine / cavity design, and performance well above LISA requirements make this project an interesting candidate for the space-based Gravitational Waves detector. We discuss the scientific background and outline of this project within the LISA framework, as well as its potential impact on other stringent technical requirements of the LISA project (e.g. U.S.O. clock-stability, arm-length measurements. . . ). We also present other possible applications for space projects involving interferometry, laser ranging or onboard ultrastable oscillators.

  4. Drought Prediction for Socio-Cultural Stability Project

    NASA Technical Reports Server (NTRS)

    Peters-Lidard, Christa; Eylander, John B.; Koster, Randall; Narapusetty, Balachandrudu; Kumar, Sujay; Rodell, Matt; Bolten, John; Mocko, David; Walker, Gregory; Arsenault, Kristi; Rheingrover, Scott

    2014-01-01

    The primary objective of this project is to answer the question: "Can existing, linked infrastructures be used to predict the onset of drought months in advance?" Based on our work, the answer to this question is "yes" with the qualifiers that skill depends on both lead-time and location, and especially with the associated teleconnections (e.g., ENSO, Indian Ocean Dipole) active in a given region season. As part of this work, we successfully developed a prototype drought early warning system based on existing/mature NASA Earth science components including the Goddard Earth Observing System Data Assimilation System Version 5 (GEOS-5) forecasting model, the Land Information System (LIS) land data assimilation software framework, the Catchment Land Surface Model (CLSM), remotely sensed terrestrial water storage from the Gravity Recovery and Climate Experiment (GRACE) and remotely sensed soil moisture products from the Aqua/Advanced Microwave Scanning Radiometer - EOS (AMSR-E). We focused on a single drought year - 2011 - during which major agricultural droughts occurred with devastating impacts in the Texas-Mexico region of North America (TEXMEX) and the Horn of Africa (HOA). Our results demonstrate that GEOS-5 precipitation forecasts show skill globally at 1-month lead, and can show up to 3 months skill regionally in the TEXMEX and HOA areas. Our results also demonstrate that the CLSM soil moisture percentiles are a goof indicator of drought, as compared to the North American Drought Monitor of TEXMEX and a combination of Famine Early Warning Systems Network (FEWS NET) data and Moderate Resolution Imaging Spectrometer (MODIS)'s Normalizing Difference Vegetation Index (NDVI) anomalies over HOA. The data assimilation experiments produced mixed results. GRACE terrestrial water storage (TWS) assimilation was found to significantly improve soil moisture and evapotransportation, as well as drought monitoring via soil moisture percentiles, while AMSR-E soil moisture

  5. An interim evaluation of the thermal stability of Cu--Y--/sup 85/Kr sputter deposits and plans for evantual disposal

    SciTech Connect

    McClanahan, E.D.; Bradley, E.R.

    1988-04-01

    A pilot process was developed and demonstrated for trapping and storing /sup 85/Kr from the dissolver off-gas stream of a nuclear fuel reprocessing plant. Ions produced in a low-pressure krypton discharge are implanted on the inner wall of a krypton trapping storage device (KTSD). Objectives were to measure the release of /sup 85/Kr implanted in a copper--yttrium alloy, outline the characterization work to be performed on the Cu/endash/Y/endash//sup 85/Kr waste form, and identify the options available for disposing of the remaining /sup 85/Kr. Release rates were obtained from periodic measurements of the krypton released from both radioactive and nonradioactive krypton-loaded KTSDs. Sampling is expected to continue as long as the extrapolated release rates remain acceptable for a period not to exceed one half-life (/approximately/10 y). Seven tests were performed on a nonradioactive KTSD at 180 to 450/degree/C. Three KTSDs loaded with 80 to 150 Ci of /sup 85/Kr stored at 150, 250, and 350/degree/C were sampled four times each. Proposed post-elevated-temperature storage characterization of the Cu/endash/Y/endash//sup 85/Kr waste form is outlined. Both radioactive and nonradioactive test specimens stored below 350/degree/C showed release rates less than 0.1%y/sup /minus/1/. Release rates for the radioactive specimens were obtained for storage periods of 1.6, 1.1, and 0.4 y at 150, 250 and 350/degree/C. The nonradioactive specimen has been held at temperatures between 180 and 450/degree/C, but mainly at 350/degree/C for a total storage time of 2.1 y. Tests should continue for a period not exceeding 10 y, and then the remaining Cu/endash/Y/endash//sup 85/Kr waste form should be evaluated to better predict the overall stability. Three options for the disposal of the remaining /sup 85/Kr. 3 refs., 2 figs., 2 tabs.

  6. Comprehensive Illinois Occupational Education Demonstration Center. Second Interim Report.

    ERIC Educational Resources Information Center

    Illinois State Board of Vocational Education and Rehabilitation, Springfield. Div. of Vocational and Technical Education.

    The second interim report covers the time period from July 1, 1974 to June 30, 1975, phase two of the project. The document consists of four separate reports: a report summary, reports of the two demonstration centers, and a third party evaluation by Educational Management Services, Inc. The 13-page summary describes the overall project. A 39-page…

  7. Facility stabilization project, fiscal year 1998 -- Multi-year workplan (MYWP) for WBS 1.4

    SciTech Connect

    Floberg, W.C.

    1997-09-30

    The primary Facility Stabilization mission is to provide minimum safe surveillance and maintenance of facilities and deactivate facilities on the Hanford Site, to reduce risks to workers, the public and environment, transition the facilities to a low cost, long term surveillance and maintenance state, and to provide safe and secure storage of special nuclear materials, nuclear materials, and nuclear fuel. Facility Stabilization will protect the health and safety of the public and workers, protect the environment and provide beneficial use of the facilities and other resources. Work will be in accordance with the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement), local, national, international and other agreements, and in compliance with all applicable Federal, state, and local laws. The stakeholders will be active participants in the decision processes including establishing priorities, and in developing a consistent set of rules, regulations, and laws. The work will be leveraged with a view of providing positive, lasting economic impact in the region. Effectiveness, efficiency, and discipline in all mission activities will enable Hanford Site to achieve its mission in a continuous and substantive manner. As the mission for Facility Stabilization has shifted from production to support of environmental restoration, each facility is making a transition to support the Site mission. The mission goals include the following: (1) Achieve deactivation of facilities for transfer to EM-40, using Plutonium Uranium Extraction (PUREX) plant deactivation as a model for future facility deactivation; (2) Manage nuclear materials in a safe and secure condition and where appropriate, in accordance with International Atomic Energy Agency (IAEA) safeguards rules; (3) Treat nuclear materials as necessary, and store onsite in long-term interim safe storage awaiting a final disposition decision by US Department of Energy; (4) Implement nuclear materials

  8. Interim storage study report

    SciTech Connect

    Rawlins, J.K.

    1998-02-01

    High-level radioactive waste (HLW) stored at the Idaho Chemical Processing Plant (ICPP) in the form of calcine and liquid and liquid sodium-bearing waste (SBW) will be processed to provide a stable waste form and prepare the waste to be transported to a permanent repository. Because a permanent repository will not be available when the waste is processed, the waste must be stored at ICPP in an Interim Storage Facility (ISF). This report documents consideration of an ISF for each of the waste processing options under consideration.

  9. 24 CFR 35.820 - Interim controls.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 24 Housing and Urban Development 1 2012-04-01 2012-04-01 false Interim controls. 35.820 Section 35...-Possession Multifamily Property § 35.820 Interim controls. HUD shall conduct interim controls in accordance... accordance with § 35.815. Interim controls are considered completed when clearance is achieved in...

  10. 24 CFR 35.820 - Interim controls.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 24 Housing and Urban Development 1 2010-04-01 2010-04-01 false Interim controls. 35.820 Section 35...-Possession Multifamily Property § 35.820 Interim controls. HUD shall conduct interim controls in accordance... accordance with § 35.815. Interim controls are considered completed when clearance is achieved in...

  11. Stormwater Pollution Prevention Plan (SWPPP) for Coal Storage Area Stabilization Project

    SciTech Connect

    Project and Design Engineering

    2011-03-01

    The scope of this project is to stabilize the abandoned coal storage area and redirect the storm water runoff from sanitary sewer system to the storm drain system. Currently, the existing storm water runoff is directed to a perimeter concrete drainage swale and collected in a containment basin. The collected water is then pumped to a treatment facility and after treatment, is discharged to the Y-12 sanitary sewer system. The existing drainage swale and collection basin along with silt fencing will be used during aggregate placement and grading to provide erosion and sediment control. Inlet protection will also be installed around existing structures during the storm water diversion construction. This project scope will include the installation of a non-woven geotextile fabric and compacted mineral aggregate base (paving optional) to stabilize the site. The geotextile specifications are provided on the vendor cut sheets in Appendix B. The installation of a storm water collection/retention area will also be installed on the southern side of the site in accordance with EPA Technical Guidance on Implementing the Stormwater Runoff Requirements for federal Projects under Section 438 of the Energy Independence and Security Act. The total area to be disturbed is approximately 2.5 acres. The order of activities for this Stormwater Pollution Prevention Plan (SWPPP) will be: (1) post notice of coverage (NOC) in a prominent display near entrance of the site; (2) install rain gauge on site or contact Y-12 Plant Shift Superintendent daily for Met tower rain gauge readings; (3) install stabilized construction exit on site; (4) install silt fencing along perimeter as indicated on the attached site plan; (5) regrade site; (6) install geotextile fabric and compacted mineral aggregate base; (7) install catch basin inlet protection where required; (8) excavate and lower existing catch basin tops, re-grade and asphalt to drain; and (9) when all disturbed areas are re-stabilized, remove

  12. Episodic acidification and associated fish and benthic invertebrate responses in five Northern Appalachian streams: An interim report of the episodic response project

    SciTech Connect

    DeWalle, D.R.; Gagen, C.J.; Jones, M.C.; Carline, R.F.; Sharpe, W.E.

    1991-05-01

    The report summarizes progress from October 1988 to May 1989 on an ongoing research project to investigate the chemicals and biological response of five Northern Appalachian Plateau streams to episodic changes in flow. The research described is part of the U.S. EPA Episodic Response Project (ERP), Aquatic Effects Research Program. Research includes monitoring of stream discharge, episodic stream chemistry, precipitation amounts and intensity, and snowpack chemistry and water equivalent. Biological research includes bethic invertebrate surveyss stream bioassays with brook trout and sculpins, and tracking of brook trout movement during episodes using radiotelemetry.

  13. Effectiveness Monitoring Report, MWMF Tritium Phytoremediation Interim Measures.

    SciTech Connect

    Hitchcock, Dan; Blake, John, I.

    2003-02-10

    This report describes and presents the results of monitoring activities during irrigation operations for the calendar year 2001 of the MWMF Interim Measures Tritium Phytoremediation Project. The purpose of this effectiveness monitoring report is to provide the information on instrument performance, analysis of CY2001 measurements, and critical relationships needed to manage irrigation operations, estimate efficiency and validate the water and tritium balance model.

  14. Ocotillo: Improving Learning through Instruction. Interim Report, 1989-90.

    ERIC Educational Resources Information Center

    Walters, Jim, Ed.; Jacobs, Alan, Ed.

    Continuing work begun at a 1988 conference, the Ocotillo Action/Research Groups of the Maricopa Community Colleges (Arizona) explored ways to enhance the use of educational technology and to capitalize on future developments in the field. These interim reports cover work done in 1989-90 and serve as a basis for the next projected conference. The…

  15. GNVQs 1993-94: A National Survey Report. An Interim Report of a Joint Project. The Evolution of GNVQs: Enrolment and Delivery Patterns and Their Policy Implications.

    ERIC Educational Resources Information Center

    Nuffield Foundation, London (England).

    A project examined how General National Vocational Qualifications (GNVQs) are evolving and how far their development is in line with the objectives originally set out for them by the government. Information was collected from institutions in England, Wales, and Northern Ireland, which began offering GNVQs in 1993-94. The survey examined the five…

  16. Assessment of Program Impact Through First Grade, Volume V: Impact on Children. An Evaluation of Project Developmental Continuity. Interim Report X.

    ERIC Educational Resources Information Center

    Berrueta-Clement, John; And Others

    Fifth in a series of six volumes reporting outcomes of the preliminary evaluation of an educational intervention, this report presents the findings of the effects of Project Developmental Continuity (PDC) up to the time the evaluation study's cohort of children completed grade 1. Preliminary findings concerning the relationship between variables…

  17. The High-Skilled VET Practitioner: Interim Findings from the Evaluation of the Long-Term Impacts of the Framing the Future Projects in 1999-2000.

    ERIC Educational Resources Information Center

    Mitchell, John; Wood, Sarah; Young, Susan

    Research was conducted in 2000-01 on the long-term impacts of the 200 projects funded by Australia's Framing the Future in 1999 and of the 250 conducted in 2000. Two main research methodologies (case study investigations and a survey) were used for the study. Case study investigations were conducted with the Deaf Education Network in Sydney; South…

  18. Arsenic Removal from Drinking Water by Adsorptive Media U.S. EPA Demonstration Project at Upper Bodfish in Lake Isabella, CA Interim Evaluation Report

    EPA Science Inventory

    This report documents the activities performed during and the results obtained from the first 10 months of system operation of an arsenic (As) and uranium (U) removal technology being demonstrated at Upper Bodfish in Lake Isabella, CA. The objectives of the project are to evalua...

  19. In-situ stabilization of TRU/mixed waste project at the INEEL

    SciTech Connect

    Milian, L.W.; Heiser, J.H.; Adams, J.W.; Rutenkroeger, S.P.

    1997-08-01

    Throughout the DOE complex, buried waste poses a threat to the environment by means of contaminant transport. Many of the sites contain buried waste that is untreated, prior to disposal, or insufficiently treated, by today`s standards. One option to remedy these disposal problems is to stabilize the waste in situ. This project was in support of the Transuranic/Mixed Buried Waste - Arid Soils product line of the Landfill Focus Area, which is managed currently by the Idaho National Engineering Laboratory (BNL) provided the analytical laboratory and technical support for the various stabilization activities that will be performed as part of the In Situ Stabilization of TRU/Mixed Waste project at the INEL. More specifically, BNL was involved in laboratory testing that included the evaluation of several grouting materials and their compatibility, interaction, and long-term durability/performance, following the encapsulation of various waste materials. The four grouting materials chosen by INEL were: TECT 1, a two component, high density cementious grout, WAXFIX, a two component, molten wax product, Carbray 100, a two component elastomeric epoxy, and phosphate cement, a two component ceramic. A simulated waste stream comprised of sodium nitrate, Canola oil, and INEL soil was used in this study. Seven performance and durability tests were conducted on grout/waste specimens: compressive strength, wet-dry cycling, thermal analysis, base immersion, solvent immersion, hydraulic conductivity, and accelerated leach testing.

  20. Acid Pit Stabilization Project (Volume 1 - Cold Testing) and (Volume 2 - Hot Testing)

    SciTech Connect

    G. G. Loomis; A. P. Zdinak; M. A. Ewanic; J. J. Jessmore

    1998-01-01

    During the summer and fall of Fiscal Year 1997, a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Treatability Study was performed at the Idaho National Engineering and Environmental Laboratory. The study involved subsurface stabilization of a mixed waste contaminated soil site called the Acid Pit. This study represents the culmination of a successful technology development effort that spanned Fiscal Years 1994-1996. Research and development of the in situ grout stabilization technique was conducted. Hardware and implementation techniques are currently documented in a patent pending with the United States Patent and Trademark Office. The stabilization technique involved using jet grouting of an innovative grouting material to form a monolith out of the contamination zone. The monolith simultaneously provides a barrier to further contaminant migration and closes voids in the soil structure against further subsidence. This is accomplished by chemical incorporation of contaminants into less soluble species and achieving a general reduction in hydraulic conductivity within the monolith. The grout used for this study was TECT-HG, a relatively dense iron oxide-based cementitious grout. The treatability study involved cold testing followed by in situ stabilization of the Acid Pit. Volume 1 of this report discusses cold testing, performed as part of a ''Management Readiness Assessment'' in preparation for going hot. Volume 2 discusses the results of the hot Acid Pit Stabilization phase of this project. Drilling equipment was specifically rigged to reduce the spread of contamination, and all grouting was performed under a concrete block containing void space to absorb any grout returns. Data evaluation included examination of implementability of the grouting process and an evaluation of the contaminant spread during grouting. Following curing of the stabilized pit, cores were obtained and evaluated for toxicity characteristic leach ing

  1. Episodic acidification and associated fish and aquatic invertebrate responses in four Catskill Mountain streams: An interim report of the Episodic Response Project. Open File Report

    SciTech Connect

    Murdoch, P.S.; Bonitz, C.E.; Eakin, K.W.; Ranalli, A.J.; Witt, E.C.

    1991-07-01

    The Episodic Response Project is a multidisciplinary research project designed to assess the role of storm and snowmelt runoff in stream acidification and the associated responses of fish and invertebrates. Four streams in the Catskill region of eastern New York were selected to represent the following conditions: (1) high acid-neutralizing capacity (ANC) with no acidic episodes annually, (2) high ANC with few acidic episodes, (3) moderate to low ANC with few acidic episodes, and (4) low ANC with frequent acidic episodes. Results of the first 9 months of research in the Catskill region indicate that storm and snowmelt runoff are associated with short periods of stream acidification that, if sufficiently severe, lead to fish mortality or migration away from acidic reaches. Increased discharge coincided with decreased pH and increased total aluminum concentrations in all four streams.

  2. Permitting plan for the high-level waste interim storage

    SciTech Connect

    Deffenbaugh, M.L.

    1997-04-23

    This document addresses the environmental permitting requirements for the transportation and interim storage of solidified high-level waste (HLW) produced during Phase 1 of the Hanford Site privatization effort. Solidified HLW consists of canisters containing vitrified HLW (glass) and containers that hold cesium separated during low-level waste pretreatment. The glass canisters and cesium containers will be transported to the Canister Storage Building (CSB) in a U.S. Department of Energy (DOE)-provided transportation cask via diesel-powered tractor trailer. Tri-Party Agreement (TPA) Milestone M-90 establishes a new major milestone, and associated interim milestones and target dates, governing acquisition and/or modification of facilities necessary for: (1) interim storage of Tank Waste Remediation Systems (TWRS) immobilized HLW (IHLW) and other canistered high-level waste forms; and (2) interim storage and disposal of TWRS immobilized low-activity tank waste (ILAW). An environmental requirements checklist and narrative was developed to identify the permitting path forward for the HLW interim storage (HLWIS) project (See Appendix B). This permitting plan will follow the permitting logic developed in that checklist.

  3. Supplement Analysis for the Watershed Management Program EIS - Libby Creek (Lower Cleveland) Stabilization Project

    SciTech Connect

    N /A

    2004-07-29

    This project is follow-up to stream stabilization activities on Libby Creek that were initiated on the Upper Cleveland reach of Libby Creek 2 years ago. BPA now proposes to fund FWP to complete channel stabilization activities on the Lower Cleveland reach of Libby Creek, reduce sediment sources, convert overwidened portions of the stream into self-maintaining channel types, use natural stream stabilization techniques, and improve wildlife migratory corridors. This lower reach is about one river mile below the upper Cleveland Reach and the proposed activities are very similar to those conducted before. The current work would be constructed in two additional phases. The first phase of the Lower Cleveland project would be completed in the fall of 2004 (9/1/04--12/31/04), to include the upper 3,100 feet. The second phase will be constructed in the fall of 2005 (9/1/05--12/31/05), to include stabilizing the remaining 6,200 feet of stream. The Cleveland reaches are a spawning and rearing tributary for resident redband trout, and resident and fluvial bull trout migrating from the Kootenai River. The planned work at the two remaining phases calls for shaping cut banks; installing root wads and tree revetments; installing channel grade control structures; planting native vegetation; and installing cross vanes constructed from rock and trees to control channel gradient. In the past, this reach of Libby Creek has been degraded by past management practices, including road building, hydraulic and dredge mining, and riparian logging. This past activity has resulted in accelerated bank erosion along a number of meander bends, resulting in channel degradation and poor fish habitat. Currently the stream channel is over-widened and shallow having limited pool habitat. The current stream channel is over-widened and shallow, having limited pool habitat.

  4. Characterization of materials for a reactive transport model validation experiment: Interim report on the caisson experiment. Yucca Mountain Site Characterization Project

    SciTech Connect

    Siegel, M.D.; Cheng, W.C.; Ward, D.B.; Bryan, C.R.

    1995-08-01

    Models used in performance assessment and site characterization activities related to nuclear waste disposal rely on simplified representations of solute/rock interactions, hydrologic flow field and the material properties of the rock layers surrounding the repository. A crucial element in the design of these models is the validity of these simplifying assumptions. An intermediate-scale experiment is being carried out at the Experimental Engineered Test Facility at Los Alamos Laboratory by the Los Alamos and Sandia National Laboratories to develop a strategy to validate key geochemical and hydrological assumptions in performance assessment models used by the Yucca Mountain Site Characterization Project.

  5. EMCS Retrofit Analysis - Interim Report

    SciTech Connect

    Diamond, R.C.; Salsbury, T.I.; Bell, G.C.; Huang, Y.J.; Sezgen, A.O.; Mazzucchi, R.; Romberger, J.

    1999-03-01

    This report presents the interim results of analyses carried out in the Phillip Burton Federal Building in San Francisco from 1996 to 1998. The building is the site of a major demonstration of the BACnet communication protocol. The energy management and control systems (EMCS) in the building were retrofitted with BACnet compatible controllers in order to integrate certain existing systems on one common network. In this respect, the project has been a success. Interoperability of control equipment from different manufacturers has been demonstrated in a real world environment. Besides demonstrating interoperability, the retrofits carried out in the building were also intended to enhance control strategies and capabilities, and to produce energy savings. This report presents analyses of the energy usage of HVAC systems in the building, control performance, and the reaction of the building operators. The report does not present an evaluation of the performance capabilities of the BACnet protocol. A monitoring system was installed in the building that parallels many of the EMCS sensors and data were archived over a three-year period. The authors defined pre-retrofit and post-retrofit periods and analyzed the corresponding data to establish the changes in building performance resulting from the retrofit activities. The authors also used whole-building energy simulation (DOE-2) as a tool for evaluating the effect of the retrofit changes. The results of the simulation were compared with the monitored data. Changes in operator behavior were assessed qualitatively with questionnaires. The report summarizes the findings of the analyses and makes several recommendations as to how to achieve better performance. They maintain that the full potential of the EMCS and associated systems is not being realized. The reasons for this are discussed along with possible ways of addressing this problem. They also describe a number of new technologies that could benefit systems of the type

  6. Clean-coal technology by-products used in a highway embankment stabilization demonstration project. Master's thesis

    SciTech Connect

    Nodjomian, S.M.

    1994-01-01

    Clean-coal technology by-products are used in a highway embankment demonstration project. This research chronicles the procedures used in the process and analyzes the stability of a repaired highway embankment. The reconstructed slope is analyzed using an Intelligent Discussion Support System that was developed from a slope stability program. Water quality studies are performed and an instrumentation plan is suggested. The calculated factors of safety and the observed embankment performance give indications that the field demonstration project was a success. Long-term monitoring will be the best barometer for determining embankment gross movement and the future of FGD by-products as a stabilizing material.

  7. A large-scale forest fragmentation experiment: the Stability of Altered Forest Ecosystems Project

    PubMed Central

    Ewers, Robert M.; Didham, Raphael K.; Fahrig, Lenore; Ferraz, Gonçalo; Hector, Andy; Holt, Robert D.; Kapos, Valerie; Reynolds, Glen; Sinun, Waidi; Snaddon, Jake L.; Turner, Edgar C.

    2011-01-01

    Opportunities to conduct large-scale field experiments are rare, but provide a unique opportunity to reveal the complex processes that operate within natural ecosystems. Here, we review the design of existing, large-scale forest fragmentation experiments. Based on this review, we develop a design for the Stability of Altered Forest Ecosystems (SAFE) Project, a new forest fragmentation experiment to be located in the lowland tropical forests of Borneo (Sabah, Malaysia). The SAFE Project represents an advance on existing experiments in that it: (i) allows discrimination of the effects of landscape-level forest cover from patch-level processes; (ii) is designed to facilitate the unification of a wide range of data types on ecological patterns and processes that operate over a wide range of spatial scales; (iii) has greater replication than existing experiments; (iv) incorporates an experimental manipulation of riparian corridors; and (v) embeds the experimentally fragmented landscape within a wider gradient of land-use intensity than do existing projects. The SAFE Project represents an opportunity for ecologists across disciplines to participate in a large initiative designed to generate a broad understanding of the ecological impacts of tropical forest modification. PMID:22006969

  8. Characterization of interim reference shales

    SciTech Connect

    Miknis, F.P.; Sullivan, S.; Mason, G.

    1986-03-01

    Measurements have been made on the chemical and physical properties of two oil shales designated as interim reference oil shales by the Department of Energy. One oil shale is a Green River Formation, Parachute Creek Member, Mahogany Zone Colorado oil shale from the Anvil Points mine and the other is a Clegg Creek Member, New Albany shale from Kentucky. Material balance Fischer assays, kerogen concentrates, carbon aromaticities, thermal properties, and bulk mineralogic properties have been determined for the oil shales. The measured properties of the interim reference shales are comparable to results obtained from previous studies on similar shales. The western interim reference shale has a low carbon aromaticity, high Fischer assay conversion to oil, and a dominant carbonate mineralogy. The eastern interim reference shale has a high carbon aromaticity, low Fischer assay conversion to oil, and a dominant silicate mineralogy. Chemical and physical properties, including ASTM distillations, have been determined for shale oils produced from the interim reference shales. The distillation data were used in conjunction with API correlations to calculate a large number of shale oil properties that are required for computer models such as ASPEN. The experimental determination of many of the shale oil properties was beyond the scope of this study. Therefore, direct comparison between calculated and measured values of many properties could not be made. However, molecular weights of the shale oils were measured. In this case, there was poor agreement between measured molecular weights and those calculated from API and other published correlations. 23 refs., 12 figs., 15 tabs.

  9. 19 CFR 207.106 - Interim measures.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 19 Customs Duties 3 2010-04-01 2010-04-01 false Interim measures. 207.106 Section 207.106 Customs... and Committee Proceedings § 207.106 Interim measures. (a) At any time after proceedings are initiated... that would otherwise be kept confidential, or to take other appropriate interim measures. (b)...

  10. 19 CFR 207.106 - Interim measures.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 19 Customs Duties 3 2011-04-01 2011-04-01 false Interim measures. 207.106 Section 207.106 Customs... and Committee Proceedings § 207.106 Interim measures. (a) At any time after proceedings are initiated... that would otherwise be kept confidential, or to take other appropriate interim measures. (b)...

  11. 32 CFR 776.82 - Interim suspension.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 32 National Defense 5 2011-07-01 2011-07-01 false Interim suspension. 776.82 Section 776.82... Complaint Processing Procedures § 776.82 Interim suspension. (a) Where the Rules Counsel determines there is... interim suspension, pending completion of a professional responsibility investigation. The...

  12. 22 CFR 127.8 - Interim suspension.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 22 Foreign Relations 1 2011-04-01 2011-04-01 false Interim suspension. 127.8 Section 127.8 Foreign... Interim suspension. (a) The Managing Director of the Directorate of Defense Trade Controls or the Director of the Office of Defense Trade Controls Compliance is authorized to order the interim suspension...

  13. 32 CFR 776.82 - Interim suspension.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 32 National Defense 5 2010-07-01 2010-07-01 false Interim suspension. 776.82 Section 776.82... Complaint Processing Procedures § 776.82 Interim suspension. (a) Where the Rules Counsel determines there is... interim suspension, pending completion of a professional responsibility investigation. The...

  14. 22 CFR 127.8 - Interim suspension.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 22 Foreign Relations 1 2010-04-01 2010-04-01 false Interim suspension. 127.8 Section 127.8 Foreign... Interim suspension. (a) The Managing Director of the Directorate of Defense Trade Controls or the Director of the Office of Defense Trade Controls Compliance is authorized to order the interim suspension...

  15. KSTAR Equilibrium Operating Space and Projected Stabilization at High Normalized Beta

    SciTech Connect

    Park, Y. S.; Sabbagh, S. A.; Berkery, J.W.; Bialek, J.; Jeon, Y. M.; Hahn, S. H.; Eidietis, N. W.; Evans, T. E.; Yoon, S. W.; Ahn, Joonwook; Kim, J.; Yang, H. L.; You, K. I.; Soukhanovskii, V. A.; Bae, Y. S.; Chung, J. I.; Kwon, M.; Oh, Y. K.; Kim, W. C.; Kim, J. Y.; Lee, S. G.; Park, H.; Reimerdes, H.; Leuer, J. A.; Walker, M. L.

    2011-01-01

    Along with an expanded evaluation of the equilibrium operating space of the Korea Superconducting Tokamak Advanced Research, KSTAR, experimental equilibria of the most recent plasma discharges were reconstructed using the EFIT code. In near-circular plasmas created in 2009, equilibria reached a stored energy of 54 kJ with a maximum plasma current of 0.34 MA. Highly shaped plasmas with near double-null configuration in 2010 achieved H-mode with clear edge localized mode (ELM) activity, and transiently reached a stored energy of up to 257 kJ, elongation of 1.96 and normalized beta of 1.3. The plasma current reached 0.7 MA. Projecting active and passive stabilization of global MHD instabilities for operation above the ideal no-wall beta limit using the designed control hardware was also considered. Kinetic modification of the ideal MHD n = 1 stability criterion was computed by the MISK code on KSTAR theoretical equilibria with a plasma current of 2 MA, internal inductance of 0.7 and normalized beta of 4.0 with simple density, temperature and rotation profiles. The steep edge pressure gradient of this equilibrium resulted in the need for significant plasma toroidal rotation to allow thermal particle kinetic resonances to stabilize the resistive wall mode (RWM). The impact of various materials and electrical connections of the passive stabilizing plates on RWM growth rates was analysed, and copper plates reduced the RWM passive growth rate by a factor of 15 compared with stainless steel plates at a normalized beta of 4.4. Computations of active RWM control using the VALEN code showed that the n = 1 mode can be stabilized at normalized beta near the ideal wall limit via control fields produced by the midplane in-vessel control coils (IVCCs) with as low as 0.83kW control power using ideal control system assumptions. The ELM mitigation potential of the IVCC, examined by evaluating the vacuum island overlap created by resonant magnetic perturbations, was analysed using the

  16. Report on interim storage of spent nuclear fuel

    SciTech Connect

    Not Available

    1993-04-01

    The report on interim storage of spent nuclear fuel discusses the technical, regulatory, and economic aspects of spent-fuel storage at nuclear reactors. The report is intended to provide legislators state officials and citizens in the Midwest with information on spent-fuel inventories, current and projected additional storage requirements, licensing, storage technologies, and actions taken by various utilities in the Midwest to augment their capacity to store spent nuclear fuel on site.

  17. FRACTIONAL CRYSTALLIZATION LABORATORY TESTING WITH INTERIM PRETREATMENT SYSTEM FEEDS

    SciTech Connect

    HERTING DL

    2008-09-17

    The fractional crystallization process was developed as a pretreatment method for saltcake waste retrieved from Hanford single-shell tanks (SST). The process separates the retrieved SST waste into a high-level waste stream containing the bulk of the radionuclides and a low-activity waste stream containing the bulk of the nonradioactive sodium salts. The Interim Pretreatment System project shifted the focus on pretreatment planning from SST waste to double-shell tank waste.

  18. Plutonium Surveillance Destructive Examination Requirements at Savannah River National Laboratory for K-Area Interim Surveillance

    SciTech Connect

    Stefek, T. M.

    2005-09-29

    The DOE 3013 storage standard requires nested, welded 300 series stainless steel containers to store plutonium-bearing materials for up to 50 years. Packaged contents include stabilized plutonium-bearing residues that contain chloride salts and a low (< 0.5 weight %) water content. The DOE 3013 STD requires surveillance of the packages over the 50 year lifetime. These surveillance requirements have been further defined by the Integrated Surveillance Program to include both non-destructive examination (NDE) and destructive examination (DE) of the 3013 container. The DE portion of surveillance involves examining the 3013 nested containers, analyzing the head space gas, and evaluating the plutonium oxide chemistry. At SRS, the stored 3013 containers will undergo preparation for the DE surveillance activities in facilities located in K-Area. The actual DE surveillance will be performed in SRNL. This report provides preliminary functional requirements for the destructive examination (DE) of plutonium-bearing oxide materials and containers in support of K-Area Interim Surveillance (KIS). The KIS project will install interim facilities to prepare the samples for analysis in SRNL. This document covers the requirements for the interim period beginning in 2007, and lasting until the Container Storage and Surveillance Capability (CSSC) project provides the permanent facilities in K-Area to perform sampling and repackaging operations associated with the 3013 container storage and surveillance program. Initial requirements for the CSSC project have been previously defined in WSRC-TR-2004-00584 ''Plutonium Surveillance Destructive Examination Requirements at Savannah River National Laboratory''. As part of the Plutonium Surveillance Program of 3013 Containers at the Savannah River Site (SRS), the Savannah River National Laboratory (SRNL) will receive the emptied 3013 container components, plutonium oxide samples and headspace gas samples from K-Area. The DE program scope

  19. Quality assurance project plan for the Chestnut Ridge Fly Ash Pond Stabilization Project at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    SciTech Connect

    1996-07-01

    The Chestnut Ridge Fly Ash Pond Stabilization (CRFAPS) Project will stabilize a 19-m-high (62-ft-high) earthen embankment across Upper McCoy Branch situated along the southern slope of Chestnut Ridge. This task will be accomplished by raising the crest of the embankment, reinforcing the face of the embankment, removing trees from the face and top of the embankment, and repairing the emergency spillway. The primary responsibilities of the team members are: Lockheed Martin Energy Systems, Inc., (Energy Systems) will be responsible for project integration, technical support, Title 3 field support, environmental oversight, and quality assurance (QA) oversight of the project; Foster Wheeler Environmental Corporation (FWENC) will be responsible for design and home office Title 3 support; MK-Ferguson of Oak Ridge Company (MK-F) will be responsible for health and safety, construction, and procurement of construction materials. Each of the team members has a QA program approved by the US Department of Energy (DOE) Oak Ridge Operations. This project-specific QA project plan (QAPP), which is applicable to all project activities, identifies and integrates the specific QA requirements from the participant`s QA programs that are necessary for this project.

  20. Combustion Stability Characteristics of the Project Morpheus Liquid Oxygen / Liquid Methane Main Engine

    NASA Technical Reports Server (NTRS)

    Melcher, John C.; Morehead, Robert L.

    2014-01-01

    The project Morpheus liquid oxygen (LOX) / liquid methane (LCH4) main engine is a Johnson Space Center (JSC) designed 5,000 lbf-thrust, 4:1 throttling, pressure-fed cryogenic engine using an impinging element injector design. The engine met or exceeded all performance requirements without experiencing any in- ight failures, but the engine exhibited acoustic-coupled combustion instabilities during sea-level ground-based testing. First tangential (1T), rst radial (1R), 1T1R, and higher order modes were triggered by conditions during the Morpheus vehicle derived low chamber pressure startup sequence. The instability was never observed to initiate during mainstage, even at low power levels. Ground-interaction acoustics aggravated the instability in vehicle tests. Analysis of more than 200 hot re tests on the Morpheus vehicle and Stennis Space Center (SSC) test stand showed a relationship between ignition stability and injector/chamber pressure. The instability had the distinct characteristic of initiating at high relative injection pressure drop at low chamber pressure during the start sequence. Data analysis suggests that the two-phase density during engine start results in a high injection velocity, possibly triggering the instabilities predicted by the Hewitt stability curves. Engine ignition instability was successfully mitigated via a higher-chamber pressure start sequence (e.g., 50% power level vs 30%) and operational propellant start temperature limits that maintained \\cold LOX" and \\warm methane" at the engine inlet. The main engine successfully demonstrated 4:1 throttling without chugging during mainstage, but chug instabilities were observed during some engine shutdown sequences at low injector pressure drop, especially during vehicle landing.

  1. Are stream stabilization projects reducing suspended sediment concentrations and turbidity in the New York City Water Supply Watershed?

    NASA Astrophysics Data System (ADS)

    McHale, M. R.; Siemion, J.; Davis, W. D.

    2015-12-01

    Turbidity and suspended sediment concentrations (SSCs) are primary water quality concerns in the upper Esopus Creek watershed, the main tributary to the Ashokan reservoir. The Ashokan reservoir is one of 6 surface water reservoirs that constitute about 90% of New York City's drinking water supply. This study quantified turbidity levels and SSCs at 10 locations throughout the upper Esopus Creek watershed for 3 years prior to the implementation of 2 stream stabilization projects and for 18 months after the projects were completed. More than 93 percent of the total-suspended sediment load occurred on days with flows greater than or equal to the 90th percentile of flows observed during the study period. Discharge, SSC, and turbidity were strongly related at the outlet of the upper Esopus Creek, but not at every monitoring site. In general, relations between discharge and SSC and turbidity were strongest at sites with high SSCs, with the exception of Stony Clove Creek, the largest tributary. Stony Clove Creek, consistently produced higher SSCs and turbidity than any of the other Esopus Creek tributaries. Nonetheless, there was not a strong relation between either turbidity or SSC and discharge because there was a series of eroding banks in contact with fine grained glacio-lacustrine deposits and associated hill slope failures within the Stony Clove Creek watershed that delivered elevated turbidity and SSCs to the stream during all flow conditions. Stream bank stabilization projects were completed at two of the largest bank failures. After the projects were completed there was decrease in stream SSC and turbidity however, flows during the 18 months following the projects were lower than before the projects. Nevertheless, a shift in the SSC and turbidity discharge rating curves suggests that the stream stabilization projects resulted in lower turbidity levels and SSCs for similar discharge conditions as compared to before the projects thereby reducing sediment yields

  2. AGR-1 Data Qualification Interim Report

    SciTech Connect

    Machael Abbott

    2009-08-01

    Projects for the very-high-temperature reactor (VHTR) program provide data in support of Nuclear Regulatory Commission licensing of the VHTR. Fuel and materials to be used in the reactor are tested and characterized to quantify performance in high temperature and high fluence environments. The VHTR Program has established the NGNP Data Management and Analysis System (NDMAS) to ensure that VHTR data are (1) qualified for use, (2) stored in a readily accessible electronic form, and (3) analyzed to extract useful results. This document focuses on the first NDMAS objective. It describes the data streams associated with the first Advanced Gas Reactor (AGR-1) experiment, the processing of these data within NDMAS, and reports the interim FY09 qualification status of the AGR-1 data to date. Data qualification activities within NDMAS for specific types of data are determined by the data qualification category, which is assigned by the data generator, and include: (1) capture testing, to confirm that the data stored within NDMAS are identical to the raw data supplied, (2) accuracy testing, to confirm that the data are an accurate representation of the system or object being measured, and (3) documentation that the data were collected under an NQA-1 or equivalent QA program. The interim qualification status of the following four data streams is reported in this document: (1) fuel fabrication data, (2) fuel irradiation data, (3) fission product monitoring system (FPMS) data, and (4) Advanced Test Reactor (ATR) operating conditions data. A final report giving the NDMAS qualification status of all AGR-1 data (including cycle 145A) is planned for February 2010.

  3. Sample Results From The Interim Salt Disposition Program Macrobatch 6 Tank 21H Qualification Samples

    SciTech Connect

    Peters, T. B.; Fink, S. D.

    2012-12-20

    Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 6 for the Interim Salt Disposition Project (ISDP). This document reports partial results of the analyses of samples of Tank 21H. No issues with the projected Salt Batch 6 strategy are identified.

  4. Sample Results from the Interim Salt Disposition Program Macrobatch 6 Tank 21H Qualification Samples

    SciTech Connect

    Peters, T. B.; Fink, S. D.

    2012-12-11

    Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 6 for the Interim Salt Disposition Project (ISDP). This document reports partial results of the analyses of samples of Tank 21H. No issues with the projected Salt Batch 6 strategy are identified.

  5. Educational Change in Rural America. An Interim Report to the Experimental Schools Program.

    ERIC Educational Resources Information Center

    Kane, Michael B.

    Covering the first 3 years of the Experimental Schools (ES) 6-year program (begun in 1971), this interim report presents: the conceptual design of the ES program; the 10 rural project sites and the 18 comparative school districts; the educational changes proposed by the ES projects; and the comprehensive evaluation design. Data presented on the…

  6. Interim onsite radwaste storage

    SciTech Connect

    Bouchard, V.F.; Roddy, F.M.

    1994-12-31

    The problems associated with state compacts for disposing of radioactive waste are well known. Presently, it appears that no compact will be capable of receiving waste by January 1996. Most compacts and independent states are essentially at ground zero. Politics, the {open_quotes}Not in MY backyard{close_quotes} (NIMBY) factor, poor public relations, public mistrust, public unawareness of engineering radwaste disposal, unfavorable media hype, and a multitude of other issues will delay projects even further. The financial burden imposed on electric utility rate payers is monumental. An economical and viable solution is onsite radwaste storage at nuclear stations. For example, the Bechtel design can store waste for $32/ft{sup 3}, whereas burial costs per cubic foot are approximately $300.00/ft{sup 3} for a LSA box, $350.00/ft{sup 3} for low-level resins, and $570.00/ft{sup 3} for high-level resins, plus transportation costs of approximately $2.00 per mile. This Bechtel onsite radwaste storage is designed for maximum radwaste storage per square foot. In the overall design, emphasis was placed upon operations, maintenance, health physics, personnel, radiation exposure, and economics. Many utility personnel were consulted for their input. The final design has encompassed most of these views to provide the optimum onsite storage facility.

  7. Interim safety basis compliance matrix for Trenches 31 and 34

    SciTech Connect

    Ames, R.R.

    1994-12-30

    The tables provided in this document identify the specific requirements and basis for the administrative controls established in the Westinghouse Hanford Company (WHC) Solid Waste Burial Ground (SWBG) Interim Safety Basis (ISB) for operation of the Project W-025, Mixed Waste Lined Landfill (Trenches 31 and 34). The tables document the necessary controls and implementing procedures to ensure compliance with the requirements of the ISB. These requirements provide a basis for future Unreviewed Safety Questions (USQ) screening of applicable procedure changes, proposed physical modifications, tests, experiments, and occurrences. Table 1 provides the SWBG interim Operational Safety Requirements administrative controls matrix. The specific assumptions and commitments used in the safety analysis documents applicable to disposal of mixed wastes in Trenches 31 and 34 are provided in Table 2. Table 3 is provided to document the potential engineered and administrative mitigating features identified in the Preliminary Hazard Analysis (PHA) for disposal of mixed waste.

  8. Combustion Stability Characteristics of the Project Morpheus Liquid Oxygen/Liquid Methane Main Engine

    NASA Technical Reports Server (NTRS)

    Melcher, J. C.; Morehead, Robert L.

    2014-01-01

    The Project Morpheus liquid oxygen (LOX) / liquid methane rocket engines demonstrated acousticcoupled combustion instabilities during sea-level ground-based testing at the NASA Johnson Space Center (JSC) and Stennis Space Center (SSC). High-amplitude, 1T, 1R, 1T1R (and higher order) modes appear to be triggered by injector conditions. The instability occurred during the Morpheus-specific engine ignition/start sequence, and did demonstrate the capability to propagate into mainstage. However, the instability was never observed to initiate during mainstage, even at low power levels. The Morpheus main engine is a JSC-designed 5,000 lbf-thrust, 4:1 throttling, pressure-fed cryogenic engine using an impinging element injector design. Two different engine designs, named HD4 and HD5, and two different builds of the HD4 engine all demonstrated similar instability characteristics. Through the analysis of more than 200 hot fire tests on the Morpheus vehicle and SSC test stand, a relationship between ignition stability and injector/chamber pressure was developed. The instability has the distinct characteristic of initiating at high relative injection pressure drop (dP) at low chamber pressure (Pc); i.e., instabilities initiated at high dP/Pc at low Pc during the start sequence. The high dP/Pc during start results during the injector /chamber chill-in, and is enhanced by hydraulic flip in the injector orifice elements. Because of the fixed mixture ratio of the existing engine design (the main valves share a common actuator), it is not currently possible to determine if LOX or methane injector dP/Pc were individual contributors (i.e., LOX and methane dP/Pc typically trend in the same direction within a given test). The instability demonstrated initiation characteristic of starting at or shortly after methane injector chillin. Colder methane (e.g., sub-cooled) at the injector inlet prior to engine start was much more likely to result in an instability. A secondary effect of LOX

  9. In Situ Mercury Stabilization (ISMS) Treatment: Technology Maturation Project Phase I Status Report

    SciTech Connect

    Kalb,P.D.; Milian, L.

    2008-03-01

    further developed it has the potential for large-scale in-situ treatment of contaminated soils that could substantially reduce the prohibitive cost of thermal desorption and/or excavation and disposal. Licensing and spin-off technology development opportunities would then be viable. Depending on performance and regulatory acceptance, the treated mercury could either be excavated for disposal elsewhere or left in place as a stable alternative. Excavated spent treatment rods could be processed by the SPSS process to reduce the potential for dispersion and lower leachability even further. The Phase I objectives of the In Situ Mercury Stabilization Treatment Process Technology Maturation Project were to: (1) replicate the original bench-scale results that formed the basis for BNL's patent application, i.e., mercury contamination in soil will migrate to and react with 'rods' containing sulfur and/or sulfur compounds, (2) provide enough information to evaluate a decision to conduct further development, and (3) establish some of the critical parameters that require further technology maturation during Phase II. The information contained in this report summarizes the work conducted in Phase I to meet these objectives.

  10. 24 CFR 35.820 - Interim controls.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... completion of the risk assessment. In units in which a child of less than 6 years of age moves in after the completion of the risk assessment, interim controls shall be completed no later than 90 days after the move... property, interim controls shall be completed no later than 12 months after completion of the...

  11. 7 CFR 1738.21 - Interim financing.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... followed: (1) Interim construction shall be conducted in accordance with RUS Bulletin 1738-2 and 7 CFR part... be covered by an Environmental Report prepared in accordance with 7 CFR part 1794 and approved by RUS... 7 Agriculture 11 2011-01-01 2011-01-01 false Interim financing. 1738.21 Section...

  12. 7 CFR 1738.21 - Interim financing.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... followed: (1) Interim construction shall be conducted in accordance with RUS Bulletin 1738-2 and 7 CFR part... be covered by an Environmental Report prepared in accordance with 7 CFR part 1794 and approved by RUS... 7 Agriculture 11 2010-01-01 2010-01-01 false Interim financing. 1738.21 Section...

  13. 45 CFR 1623.6 - Interim funding.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 45 Public Welfare 4 2013-10-01 2013-10-01 false Interim funding. 1623.6 Section 1623.6 Public Welfare Regulations Relating to Public Welfare (Continued) LEGAL SERVICES CORPORATION SUSPENSION PROCEDURES § 1623.6 Interim funding. (a) Pending the completion of suspension proceedings under this...

  14. 45 CFR 1623.6 - Interim funding.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 45 Public Welfare 4 2014-10-01 2014-10-01 false Interim funding. 1623.6 Section 1623.6 Public Welfare Regulations Relating to Public Welfare (Continued) LEGAL SERVICES CORPORATION SUSPENSION PROCEDURES § 1623.6 Interim funding. (a) Pending the completion of suspension proceedings under this...

  15. 45 CFR 1623.6 - Interim funding.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 45 Public Welfare 4 2010-10-01 2010-10-01 false Interim funding. 1623.6 Section 1623.6 Public Welfare Regulations Relating to Public Welfare (Continued) LEGAL SERVICES CORPORATION SUSPENSION PROCEDURES § 1623.6 Interim funding. (a) Pending the completion of suspension proceedings under this...

  16. 45 CFR 1623.6 - Interim funding.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 45 Public Welfare 4 2012-10-01 2012-10-01 false Interim funding. 1623.6 Section 1623.6 Public Welfare Regulations Relating to Public Welfare (Continued) LEGAL SERVICES CORPORATION SUSPENSION PROCEDURES § 1623.6 Interim funding. (a) Pending the completion of suspension proceedings under this...

  17. 45 CFR 1623.6 - Interim funding.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 45 Public Welfare 4 2011-10-01 2011-10-01 false Interim funding. 1623.6 Section 1623.6 Public Welfare Regulations Relating to Public Welfare (Continued) LEGAL SERVICES CORPORATION SUSPENSION PROCEDURES § 1623.6 Interim funding. (a) Pending the completion of suspension proceedings under this...

  18. 39 CFR 952.6 - Interim impounding.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 39 Postal Service 1 2010-07-01 2010-07-01 false Interim impounding. 952.6 Section 952.6 Postal Service UNITED STATES POSTAL SERVICE PROCEDURES RULES OF PRACTICE IN PROCEEDINGS RELATIVE TO FALSE REPRESENTATION AND LOTTERY ORDERS § 952.6 Interim impounding. In preparation for or during the pendency of...

  19. Fusion Breeder Program interim report

    SciTech Connect

    Moir, R.; Lee, J.D.; Neef, W.

    1982-06-11

    This interim report for the FY82 Fusion Breeder Program covers work performed during the scoping phase of the study, December, 1981-February 1982. The goals for the FY82 study are the identification and development of a reference blanket concept using the fission suppression concept and the definition of a development plan to further the fusion breeder application. The context of the study is the tandem mirror reactor, but emphasis is placed upon blanket engineering. A tokamak driver and blanket concept will be selected and studied in more detail during FY83.

  20. Solid waste burial grounds interim safety analysis

    SciTech Connect

    Saito, G.H.

    1994-10-01

    This Interim Safety Analysis document supports the authorization basis for the interim operation and restrictions on interim operations for the near-surface land disposal of solid waste in the Solid Waste Burial Grounds. The Solid Waste Burial Grounds Interim Safety Basis supports the upgrade progress for the safety analysis report and the technical safety requirements for the operations in the Solid Waste Burial Grounds. Accident safety analysis scenarios have been analyzed based on the significant events identified in the preliminary hazards analysis. The interim safety analysis provides an evaluation of the operations in the Solid Waste Burial Grounds to determine if the radiological and hazardous material exposures will be acceptable from an overall health and safety standpoint to the worker, the onsite personnel, the public, and the environment.

  1. Heating/daylighting prototype development. Phase I, Passive and Hybrid Solar Manufactured Building Project. Interim report and project status report No. 1, 1 October 1979-29 February 1980

    SciTech Connect

    Snyder, M.; Fraker, H.; Lindsey, L.; Braham, W.; Hallagan, W.; Huffman, J.

    1980-03-31

    Climatological data, both representative (typical) and extreme conditions, relevant to building energy use in Grandview, Missouri are presented. The energy-related characteristics of a particular building and its use are merged with ambient weather conditions. The graphs depict daily fluctuations in the major categories of building heating/cooling load for the experimental building (Roof Runner facility) at Butler Research Center. Data input include hourly weather and building occupancy schedules, the geometry and fixed thermal characteristics (component R-values, heat capacities, etc.) of the prototype structure, and variable conditions (status of moveable insulating shutters, HVAC operating modes, etc.). The prototype systems to be incorporated in the new Roof Runner building are shown. Both warehouse (no ceiling) and office (suspended ceiling) system types are included. The diagrams conceptually depict the heat flows in several representative operating modes, sampling the wide variety of operating conditions which will be evaluated during the testing phase of this project. Cost estimates for the designs selected for construction are provided. (MHR)

  2. Functional Design Criteria plutonium stabilization and handling (PUSH) project W-460

    SciTech Connect

    NELSON, D.W.

    1999-09-02

    This Functional Design Criteria (FDC) contains information to guide the design of the Stabilization and Packaging Equipment necessary to oxidize and package the remaining plutonium-bearing Special Nuclear Materials (SNM) currently in the Plutonium Finishing Plant (PFP) inventory. The FDC also guides the design of vault modifications to allow storage of 3013 packages of stabilized SNM for up to 50 years.

  3. An interim overview of LDEF materials findings

    NASA Technical Reports Server (NTRS)

    Stein, Brad A.

    1992-01-01

    The flight and retrieval of the National Aeronautics and Space Administration's Long Duration Exposure Facility (LDEF) provided an opportunity for the study of the low-Earth orbit (LEO) environment and long-duration space environmental effects (SEE) on materials that is unparalleled in the history of the U.S. Space Program. The remarkable flight attitude stability of LDEF enables specific analyses of various individual and combined effects of LEO environmental parameters on identical materials on the same space vehicle. This paper provides an overview of the interim LDEF materials findings of the Principal Investigators and the Materials Special Investigation Group. In general, the LDEF data is remarkably consistent; LDEF will provide a 'benchmark' for materials design data bases for satellites in low-Earth orbit. Some materials were identified to be encouragingly resistant to LEO SEE for 5.8 years; other 'space qualified' materials displayed significant environmental degradation. Molecular contamination was widespread; LDEF offers an unprecedented opportunity to provide a unified perspective of unmanned LEO spacecraft contamination mechanisms. New material development requirements for long-term LEO missions have been identified and current ground simulation testing methods/data for new, durable materials concepts can be validated with LDEF results. LDEF findings are already being integrated into the design of Space Station Freedom.

  4. Engineering feasibility analysis for in-situ stabilization of Canonsburg residues. [UMTRA project

    SciTech Connect

    Not Available

    1982-01-01

    The US Department of Energy is considering several methods for carrying out remedial actions in Canonsburg, Pennsylvania, at the site of an inactive uranium-processing mill. The main objective of this study is to determine the feasibility of in-situ stabilization as the remedial action. In-situ stabilization is an alternative to site decontamination and offsite disposal. The problems associated with offsite hauling of large quantities of contaminated material and with the location and development of a new disposal site could be avoided by the implementation of an in-situ stabilization concept. In addition, the in-situ approach would be more cost-effective than offsite disposal. This study will establish that a technically feasible and implementable in-situ stabilization concept can be developed that meets regulatory requirements and is cost effective. This study in no way commits the DOE to implement any specific actions described herein. 11 refs., 30 figs., 24 tabs.

  5. Hanford low-level tank waste interim performance assessment

    SciTech Connect

    Mann, F.M.

    1996-09-16

    The Hanford Low-Level Tank Waste Interim Performance Assessment examines the long-term environmental and human health effects associated with the disposal of the low-level fraction of the Hanford single- and double-shell tank waste in the Hanford Site 200 East Area. This report was prepared as a good management practice to provide needed information about the relationship between the disposal system design and its performance as early as possible in the project cycle. The calculations in this performance assessment show that the disposal of the low-level fraction can meet environmental and health performance objectives.

  6. Hanford low-level tank waste interim performance assessment

    SciTech Connect

    Mann, F.M.

    1997-09-12

    The Hanford Low-Level Tank Waste Interim Performance Assessment examines the long-term environmental and human health effects associated with the disposal of the low-level fraction of the Hanford single and double-shell tank waste in the Hanford Site 200 East Area. This report was prepared as a good management practice to provide needed information about the relationship between the disposal system design and performance early in the disposal system project cycle. The calculations in this performance assessment show that the disposal of the low-level fraction can meet environmental and health performance objectives.

  7. DOE UST interim subsurface barrier technologies workshop

    SciTech Connect

    1992-09-01

    This document contains information which was presented at a workshop regarding interim subsurface barrier technologies that could be used for underground storage tanks, particularly the tank 241-C-106 at the Hanford Reservation.

  8. Supplement Analysis for the Watershed Management Program EIS (DOE/EIS-0265/SA-95) - Libby Creek Channel Stabilization Project

    SciTech Connect

    Keller, Carl J.

    2002-10-21

    BPA proposes to fund MFWP to construct a channel stabilization project, which would restore the dimension, pattern, and profile of 3,200 feet of Libby Creek. The project calls for shaping cut banks to a 2:1 slope, installing root wads and tree revetments; and planting and restoring native grasses and riparian shrubs along the margin of the channel. Cross vanes (constructed from rock) and trees will also be established to control channel gradient within the project area. This project is one restoration phase on Libby Creek, and was identified as important by the Libby Area Conservation District, MFWP, U.S. Forest Service, and U.S. Army Corps of Engineers. Libby Creek is also the focus of restoration efforts based, in part, on the finding of the Montana Governor’s Bull Trout Restoration Technical Committee. This Committee identified Libby Creek as critical spawning and migratory habitat for the threatened bull trout. This project reach of Libby Creek is also rearing habitat for resident redband trout and resident and fluvial bull trout migrating from the Kootenai River.

  9. Study of New Youth Initiatives in Apprenticeship. Interim Report. Volume 2: Site Visit Reports.

    ERIC Educational Resources Information Center

    CSR, Inc., Washington, DC.

    This second volume of the interim report provides detailed case study reports on each of the eight Youth Apprenticeship Projects. (Volume 1, an overview of data from the site visits, is available separately as CE 032 791.) Discussion areas covered in each site visit report are local context/operational environment, administrative information,…

  10. 78 FR 5830 - Draft Environmental Assessment and Proposed Habitat Conservation Plan for the Interim Operations...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-01-28

    ... National Environmental Policy Act (NEPA) for the interim operations of the Klamath Hydroelectric Project in..., comments, new information or suggestions from the public, other concerned governmental agencies, the scientific community, Tribes, industry, or any other interested party on the applicant's permit...

  11. Atmospheric Effects of Subsonic Aircraft: Interim Assessment Report of the Advanced Subsonic Technology Program

    NASA Technical Reports Server (NTRS)

    Friedl, Randall R. (Editor)

    1997-01-01

    This first interim assessment of the subsonic assessment (SASS) project attempts to summarize concisely the status of our knowledge concerning the impacts of present and future subsonic aircraft fleets. It also highlights the major areas of scientific uncertainty, through review of existing data bases and model-based sensitivity studies. In view of the need for substantial improvements in both model formulations and experimental databases, this interim assessment cannot provide confident numerical predictions of aviation impacts. However, a number of quantitative estimates are presented, which provide some guidance to policy makers.

  12. A Project Assessment of Stabilizing System of WT Generation using Rechargeable Battery

    NASA Astrophysics Data System (ADS)

    Kojima, Yasuhiro; Takano, Tomihiro; Tanikawa, Ryoichi; Takagi, Tetsuro; Hirooka, Koutaro; Kumagai, Sadatoshi

    The expansion of the renewable energy introduction is examined as measures for controlling global warming. Wind power generation is expected as effective power resource, but the negative impact from the difficulty of an unstable output is concerned. In recent years, WT generation with contract of cut-of with shorting adjusting power and with rechargeable battery for stabilizing control are examined, but the introduction has not been accelerated yet because there is an influence in WT generation entrepreneur's business. In this paper, we make a brief summary of relation between the fluctuation of wind power generation and stability of electric power operation, and two types of approach; cut-off contract and stabilization using rechargeable battery. For the stabilization using battery, there are two methods, one is reduction control and the other is constant control. We propose a new control method for constant control based on profit optimization considering WT generation forecast and its risk of deviation. We also propose the estimation method for the .limitation of battery installation. Simulation results show the efficiency of our proposed methods.

  13. Development of the RGB LEDs color mixing mechanism for stability the color temperature at different projection distances.

    PubMed

    Hung, Chih-Ching

    2015-01-01

    In lighting application, the color mixing of the RGB LEDs can provide more color selection in correlated color temperature and color rendering. Therefore, the purpose of this study is to propose a RGB color mixing mechanism by applying the mechanism design. Three sets of lamp-type RGB LEDs are individually installed on three four-bar linkages. A crank is used to drive three groups of RGB LEDs lamp-type to project lights onto a single plane in order to mix the lights. And, simulations of the illuminance and associated color temperatures are conducted by changing the distance to the projection plane, under the assumption that the stability of the color temperature of the projected light does not change according to the projecting height. Thus, the effect of change in the color temperature on color determination by the humans' eyes was avoided. The success of the proposed method will allow medical personnel to choose suitable wavelengths and color temperatures according to the particular requirements of their medical-examination environments. PMID:26444810

  14. Development of the RGB LEDs color mixing mechanism for stability the color temperature at different projection distances.

    PubMed

    Hung, Chih-Ching

    2015-01-01

    In lighting application, the color mixing of the RGB LEDs can provide more color selection in correlated color temperature and color rendering. Therefore, the purpose of this study is to propose a RGB color mixing mechanism by applying the mechanism design. Three sets of lamp-type RGB LEDs are individually installed on three four-bar linkages. A crank is used to drive three groups of RGB LEDs lamp-type to project lights onto a single plane in order to mix the lights. And, simulations of the illuminance and associated color temperatures are conducted by changing the distance to the projection plane, under the assumption that the stability of the color temperature of the projected light does not change according to the projecting height. Thus, the effect of change in the color temperature on color determination by the humans' eyes was avoided. The success of the proposed method will allow medical personnel to choose suitable wavelengths and color temperatures according to the particular requirements of their medical-examination environments.

  15. Methods Data Qualification Interim Report

    SciTech Connect

    R. Sam Alessi; Tami Grimmett; Leng Vang; Dave McGrath

    2010-09-01

    The overall goal of the Next Generation Nuclear Plant (NGNP) Data Management and Analysis System (NDMAS) is to maintain data provenance for all NGNP data including the Methods component of NGNP data. Multiple means are available to access data stored in NDMAS. A web portal environment allows users to access data, view the results of qualification tests and view graphs and charts of various attributes of the data. NDMAS also has methods for the management of the data output from VHTR simulation models and data generated from experiments designed to verify and validate the simulation codes. These simulation models represent the outcome of mathematical representation of VHTR components and systems. The methods data management approaches described herein will handle data that arise from experiment, simulation, and external sources for the main purpose of facilitating parameter estimation and model verification and validation (V&V). A model integration environment entitled ModelCenter is used to automate the storing of data from simulation model runs to the NDMAS repository. This approach does not adversely change the why computational scientists conduct their work. The method is to be used mainly to store the results of model runs that need to be preserved for auditing purposes or for display to the NDMAS web portal. This interim report demonstrates the currently development of NDMAS for Methods data and discusses data and its qualification that is currently part of NDMAS.

  16. Collaborative Research: Robust Climate Projections and Stochastic Stability of Dynamical Systems

    SciTech Connect

    Ilya Zaliapin

    2011-10-12

    This project focused on conceptual exploration of El Nino/Southern Oscillation (ENSO) variability and sensitivity using a Delay Differential Equation developed in the project. We have (i) established the existence and continuous dependence of solutions of the model (ii) explored multiple models solutions, and the distribution of solutions extrema, and (iii) established and explored the phase locking phenomenon and the existence of multiple solutions for the same values of model parameters. In addition, we have applied to our model the concept of pullback attractor, which greatly facilitated predictive understanding of the nonlinear model's behavior.

  17. High Temperature Materials Interim Data Qualification Report

    SciTech Connect

    Nancy Lybeck

    2010-08-01

    ABSTRACT Projects for the very high temperature reactor (VHTR) Technology Development Office provide data in support of Nuclear Regulatory Commission licensing of the VHTR. Fuel and materials to be used in the reactor are tested and characterized to quantify performance in high temperature and high fluence environments. The VHTR program has established the NGNP Data Management and Analysis System (NDMAS) to ensure that VHTR data are qualified for use, stored in a readily accessible electronic form, and analyzed to extract useful results. This document focuses on the first NDMAS objective. It describes the High Temperature Materials characterization data stream, the processing of these data within NDMAS, and reports the interim FY2010 qualification status of the data. Data qualification activities within NDMAS for specific types of data are determined by the data qualification category assigned by the data generator. The High Temperature Materials data are being collected under NQA-1 guidelines, and will be qualified data. For NQA-1 qualified data, the qualification activities include: (1) capture testing, to confirm that the data stored within NDMAS are identical to the raw data supplied, (2) accuracy testing to confirm that the data are an accurate representation of the system or object being measured, and (3) documenting that the data were collected under an NQA-1 or equivalent Quality Assurance program. Currently, data from two test series within the High Temperature Materials data stream have been entered into the NDMAS vault: 1. Tensile Tests for Sm (i.e., Allowable Stress) Confirmatory Testing – 1,403,994 records have been inserted into the NDMAS database. Capture testing is in process. 2. Creep-Fatigue Testing to Support Determination of Creep-Fatigue Interaction Diagram – 918,854 records have been processed and inserted into the NDMAS database. Capture testing is in process.

  18. Quantum projection noise limited stability of a 88Sr+ atomic clock

    NASA Astrophysics Data System (ADS)

    Jian, B.; Dubé, P.; Madej, A. A.

    2016-06-01

    The evaluated accuracy of a single trapped 88Sr+ ion clock referenced to the 5s2 S 1/2 - 4d 2 D 5/2 transition at 445 THz at the National Research Council of Canada has reached 1.2 x 10-17 over recent years. On the other hand, the stability of an atomic clock determines how long the signals from two similar clocks have to be compared to reach a given level of uncertainty. Here, we report on the improvement of the stability of NRC's 88Sr+ single ion clock by reducing the Allan deviation from 1 x 10-14 to 3 x 10-15 at 1 second averaging time. This is done by the implementation of a clear out laser that transfers the ion from the metastable state to the ground state at each cycle, followed by a state-preparation step that transfers the ion to the desired ground state magnetic sublevel of the probed transition.

  19. Plutonium uranium extraction (PUREX) end state basis for interim operation (BIO) for surveillance and maintenance

    SciTech Connect

    DODD, E.N.

    1999-05-12

    This Basis for Interim Operation (BIO) was developed for the PUREX end state condition following completion of the deactivation project. The deactivation project has removed or stabilized the hazardous materials within the facility structure and equipment to reduce the hazards posed by the facility during the surveillance and maintenance (S and M) period, and to reduce the costs associated with the S and M. This document serves as the authorization basis for the PUREX facility, excluding the storage tunnels, railroad cut, and associated tracks, for the deactivated end state condition during the S and M period. The storage tunnels, and associated systems and areas, are addressed in WHC-SD-HS-SAR-001, Rev. 1, PUREX Final Safety Analysis Report. During S and M, the mission of the facility is to maintain the conditions and equipment in a manner that ensures the safety of the workers, environment, and the public. The S and M phase will continue until the final decontamination and decommissioning (D and D) project and activities are begun. Based on the methodology of DOE-STD-1027-92, Hazards Categorization and Accident Analysis Techniques for Compliance with DOE Order 5480.23, Nuclear Safety Analysis Reports, the final facility hazards category is identified as hazards category This considers the remaining material inventories, form and distribution of the material, and the energies present to initiate events of concern. Given the current facility configuration, conditions, and authorized S and M activities, there are no operational events identified resulting in significant hazard to any of the target receptor groups (e.g., workers, public, environment). The only accident scenarios identified with consequences to the onsite co-located workers were based on external natural phenomena, specifically an earthquake. The dose consequences of these events are within the current risk evaluation guidelines and are consistent with the expectations for a hazards category 2

  20. CMM Interim Check Design of Experiments (U)

    SciTech Connect

    Montano, Joshua Daniel

    2015-07-29

    Coordinate Measuring Machines (CMM) are widely used in industry, throughout the Nuclear Weapons Complex and at Los Alamos National Laboratory (LANL) to verify part conformance to design definition. Calibration cycles for CMMs at LANL are predominantly one year in length and include a weekly interim check to reduce risk. The CMM interim check makes use of Renishaw’s Machine Checking Gauge which is an off-the-shelf product simulates a large sphere within a CMM’s measurement volume and allows for error estimation. As verification on the interim check process a design of experiments investigation was proposed to test a couple of key factors (location and inspector). The results from the two-factor factorial experiment proved that location influenced results more than the inspector or interaction.

  1. Design review report FFTF interim storage cask

    SciTech Connect

    Scott, P.L.

    1995-01-03

    Final Design Review Report for the FFTF Interim Storage Cask. The Interim Storage Cask (ISC) will be used for long term above ground dry storage of FFTF irradiated fuel in Core Component Containers (CCC)s. The CCC has been designed and will house assemblies that have been sodium washed in the IEM Cell. The Solid Waste Cask (SWC) will transfer a full CCC from the IEM Cell to the RSB Cask Loading Station where the ISC will be located to receive it. Once the loaded ISC has been sealed at the RSB Cask Loading Station, it will be transferred by facility crane to the DSWC Transporter. After the ISC has been transferred to the Interim Storage Area (ISA), which is yet to be designed, a mobile crane will be used to place the ISC in its final storage location.

  2. High-stability optical components for semiconductor laser intersatellite link experiment (SILEX) project

    NASA Astrophysics Data System (ADS)

    Lepretre, Francois

    1994-09-01

    Within the framework of a MATRA MARCONI SPACE FRANC contract for the European Space Agency, MATRA DEFENSE - DOD/UAO have developed, produced and tested 9 laser diode collimators, 52 optical components (anamorphoser, mirrors, dichroic splitters, redundancy module) and 9 interferential filters. All these space equipments must be integrated into the optical head of the SILEX (Semi-conductor Laser Intersatellite Link Experiment) bench. The SILEX experiment consists in transferring data from a low altitude satellite (SPOT 4) to a satellite in geostationary orbit (ARTEMIS) via beam generated by a laser diode (60 mW Cw). Very low emitted flux and long distance between the two satellites gives rise to the following technical difficulties: high angular (1 (mu) rad) and transverse stability requirements, requirement for high transmission and high rejection narrow band filters, in order to differentiate the transmit and receive channels, necessity of a very good optical wavefront, wavelength range 815-825 nm, 843-853 nm.

  3. 200 Area Interim Storage Area Technical Safety Requirements

    SciTech Connect

    CARRELL, R.D.

    2000-03-15

    The 200 Area Interim Storage Area Technical Safety Requirements define administrative controls and design features required to ensure safe operation during receipt and storage of canisters containing spent nuclear fuel. This document is based on the 200 Area Interim Storage Area, Annex D, Final Safety Analysis Report which contains information specific to the 200 Area Interim Storage Area.

  4. 5 CFR 772.102 - Interim personnel actions.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    .... 7701(b)(2)(A)(i), determines that granting interim relief is not appropriate; (e) An interim personnel... administrative judge granting interim relief under 5 U.S.C. 7701(b)(2)(A) and a petition for review of the initial decision is filed (or will be filed) with the full Board under 5 U.S.C. 7701(e)(1)(A), the...

  5. 12 CFR 541.19 - Interim state savings association.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 12 Banks and Banking 5 2010-01-01 2010-01-01 false Interim state savings association. 541.19... REGULATIONS AFFECTING FEDERAL SAVINGS ASSOCIATIONS § 541.19 Interim state savings association. The term interim state savings association means a savings association, other than a Federal savings...

  6. 12 CFR 541.19 - Interim state savings association.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 12 Banks and Banking 5 2011-01-01 2011-01-01 false Interim state savings association. 541.19... REGULATIONS AFFECTING FEDERAL SAVINGS ASSOCIATIONS § 541.19 Interim state savings association. The term interim state savings association means a savings association, other than a Federal savings...

  7. 12 CFR 541.18 - Interim Federal savings association.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 12 Banks and Banking 5 2010-01-01 2010-01-01 false Interim Federal savings association. 541.18... REGULATIONS AFFECTING FEDERAL SAVINGS ASSOCIATIONS § 541.18 Interim Federal savings association. The term interim Federal savings association means a Federal savings association chartered by the Office...

  8. 12 CFR 541.18 - Interim Federal savings association.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 12 Banks and Banking 5 2011-01-01 2011-01-01 false Interim Federal savings association. 541.18... REGULATIONS AFFECTING FEDERAL SAVINGS ASSOCIATIONS § 541.18 Interim Federal savings association. The term interim Federal savings association means a Federal savings association chartered by the Office...

  9. 5 CFR 772.102 - Interim personnel actions.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 5 Administrative Personnel 2 2013-01-01 2013-01-01 false Interim personnel actions. 772.102 Section 772.102 Administrative Personnel OFFICE OF PERSONNEL MANAGEMENT (CONTINUED) CIVIL SERVICE REGULATIONS (CONTINUED) INTERIM RELIEF General § 772.102 Interim personnel actions. When an employee...

  10. 5 CFR 772.102 - Interim personnel actions.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 5 Administrative Personnel 2 2011-01-01 2011-01-01 false Interim personnel actions. 772.102 Section 772.102 Administrative Personnel OFFICE OF PERSONNEL MANAGEMENT (CONTINUED) CIVIL SERVICE REGULATIONS (CONTINUED) INTERIM RELIEF General § 772.102 Interim personnel actions. When an employee...

  11. 5 CFR 772.102 - Interim personnel actions.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 5 Administrative Personnel 2 2012-01-01 2012-01-01 false Interim personnel actions. 772.102 Section 772.102 Administrative Personnel OFFICE OF PERSONNEL MANAGEMENT (CONTINUED) CIVIL SERVICE REGULATIONS (CONTINUED) INTERIM RELIEF General § 772.102 Interim personnel actions. When an employee...

  12. 42 CFR 417.570 - Interim per capita payments.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 42 Public Health 3 2010-10-01 2010-10-01 false Interim per capita payments. 417.570 Section 417... PREPAYMENT PLANS Medicare Payment: Cost Basis § 417.570 Interim per capita payments. (a) Principle of payment. (1) CMS makes monthly advance payments equivalent to the HMO's or CMP's interim per capita rate...

  13. 42 CFR 417.808 - Interim per capita payments.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 42 Public Health 3 2010-10-01 2010-10-01 false Interim per capita payments. 417.808 Section 417... PREPAYMENT PLANS Health Care Prepayment Plans § 417.808 Interim per capita payments. The HCPP follows the principles specified in §§ 417.570 and 417.572 on interim per capita payments, except for the following:...

  14. 42 CFR 417.570 - Interim per capita payments.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 42 Public Health 3 2011-10-01 2011-10-01 false Interim per capita payments. 417.570 Section 417... PREPAYMENT PLANS Medicare Payment: Cost Basis § 417.570 Interim per capita payments. (a) Principle of payment. (1) CMS makes monthly advance payments equivalent to the HMO's or CMP's interim per capita rate...

  15. 42 CFR 417.808 - Interim per capita payments.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 42 Public Health 3 2011-10-01 2011-10-01 false Interim per capita payments. 417.808 Section 417... PREPAYMENT PLANS Health Care Prepayment Plans § 417.808 Interim per capita payments. The HCPP follows the principles specified in §§ 417.570 and 417.572 on interim per capita payments, except for the following:...

  16. 42 CFR 417.808 - Interim per capita payments.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 42 Public Health 3 2012-10-01 2012-10-01 false Interim per capita payments. 417.808 Section 417... HEALTH CARE PREPAYMENT PLANS Health Care Prepayment Plans § 417.808 Interim per capita payments. The HCPP follows the principles specified in §§ 417.570 and 417.572 on interim per capita payments, except for...

  17. 42 CFR 417.570 - Interim per capita payments.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 42 Public Health 3 2013-10-01 2013-10-01 false Interim per capita payments. 417.570 Section 417... HEALTH CARE PREPAYMENT PLANS Medicare Payment: Cost Basis § 417.570 Interim per capita payments. (a...) Determination of rate. The interim per capita rate of payment is equal to the estimated per capita cost...

  18. 42 CFR 417.570 - Interim per capita payments.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 42 Public Health 3 2012-10-01 2012-10-01 false Interim per capita payments. 417.570 Section 417... HEALTH CARE PREPAYMENT PLANS Medicare Payment: Cost Basis § 417.570 Interim per capita payments. (a...) Determination of rate. The interim per capita rate of payment is equal to the estimated per capita cost...

  19. 42 CFR 417.808 - Interim per capita payments.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 42 Public Health 3 2014-10-01 2014-10-01 false Interim per capita payments. 417.808 Section 417... HEALTH CARE PREPAYMENT PLANS Health Care Prepayment Plans § 417.808 Interim per capita payments. The HCPP follows the principles specified in §§ 417.570 and 417.572 on interim per capita payments, except for...

  20. 42 CFR 417.808 - Interim per capita payments.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 42 Public Health 3 2013-10-01 2013-10-01 false Interim per capita payments. 417.808 Section 417... HEALTH CARE PREPAYMENT PLANS Health Care Prepayment Plans § 417.808 Interim per capita payments. The HCPP follows the principles specified in §§ 417.570 and 417.572 on interim per capita payments, except for...

  1. 42 CFR 417.570 - Interim per capita payments.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 42 Public Health 3 2014-10-01 2014-10-01 false Interim per capita payments. 417.570 Section 417... HEALTH CARE PREPAYMENT PLANS Medicare Payment: Cost Basis § 417.570 Interim per capita payments. (a...) Determination of rate. The interim per capita rate of payment is equal to the estimated per capita cost...

  2. Transforming Writing: Interim Evaluation Report

    ERIC Educational Resources Information Center

    Rooke, Jonathan

    2012-01-01

    Transforming Writing is a two-year action research project which aims to develop a model for the teaching and learning of writing that more fully incorporates a focus on embedded formative assessment. In the first year of the project, the 12 participating schools developed a model of writing underpinned by Talk for Writing, an approach developed…

  3. Interim Land Use Control Implementation Plan

    NASA Technical Reports Server (NTRS)

    Applegate, Joseph L.

    2014-01-01

    This Interim Land Use Control Implementation Plan (LUCIP) has been prepared to inform current and potential future users of the Kennedy Space Center (KSC) Contractors Road Heavy Equipment (CRHE) Area (SWMU 055; "the Site") of institutional controls that have been implemented at the Site1. Although there are no current unacceptable risks to human health or the environment associated with the CRHE Area, an interim institutional land use control (LUC) is necessary to prevent human health exposure to volatile organic compound (VOC)-affected groundwater at the Site. Controls will include periodic inspection, condition certification, and agency notification.

  4. GULF OF MEXICO SEAFLOOR STABILITY AND GAS HYDRATE MONITORING STATION PROJECT

    SciTech Connect

    J. Robert Woolsey; Thomas M. McGee; Robin C. Buchannon

    2004-11-01

    The gas hydrates research Consortium (HRC), established and administered at the University if Mississippi's Center for Marine Research and Environmental Technology (CMRET) has been active on many fronts in FY 03. Extension of the original contract through March 2004, has allowed completion of many projects that were incomplete at the end of the original project period due, primarily, to severe weather and difficulties in rescheduling test cruises. The primary objective of the Consortium, to design and emplace a remote sea floor station for the monitoring of gas hydrates in the Gulf of Mexico by the year 2005 remains intact. However, the possibility of levering HRC research off of the Joint Industries Program (JIP) became a possibility that has demanded reevaluation of some of the fundamental assumptions of the station format. These provisions are discussed in Appendix A. Landmark achievements of FY03 include: (1) Continuation of Consortium development with new researchers and additional areas of research contribution being incorporated into the project. During this period, NOAA's National Undersea Research Program's (NURP) National Institute for Undersea Science and Technology (NIUST) became a Consortium funding partner, joining DOE and Minerals Management Service (MMS); (2) Very successful annual and semiannual meetings in Oxford Mississippi in February and September, 2003; (3) Collection of piston cores from MC798 in support of the effort to evaluate the site for possible monitoring station installation; (4) Completion of the site evaluation effort including reports of all localities in the northern Gulf of Mexico where hydrates have been documented or are strongly suspected to exist on the sea floor or in the shallow subsurface; (5) Collection and preliminary evaluation of vent gases and core samples of hydrate from sites in Green Canyon and Mississippi Canyon, northern Gulf of Mexico; (6) Monitoring of gas activity on the sea floor, acoustically and thermally

  5. Projecting climate change impacts on the stability of productivities of maize and soybean in terms of probability of concurrent failure

    NASA Astrophysics Data System (ADS)

    Yokozawa, M.; Sakurai, G.; Iizumi, T.

    2012-12-01

    The globalization of the trade of food commodities has arranged agricultural production areas in the world. Current main production areas of maize and soybean, which are major cereal crops for human food and animal diet, are localized in the United States, China and Brazil. The amounts of production of maize and soybean from these three countries reached 70% and 74% of total production in the world in 2009, respectively. These three countries are hubs for the world food supply network. Simultaneous external disturbances to the localized hubs can make the network system unstable. Here, we projected the changes in stability of the productivities of maize and soybean under climate change. We used a process-based model for evaluating crop yield at a large scale for maize and soybean. The parameters are determined based on the historical agricultural statistics issued by administrative agencies during a period of 1981 to 2006 and a reanalysis data JRA25 provided by Japan Meteorological Agency. We used the climate change scenarios from outputs of MIROC5.0 simulations. We projected the time changes in maize and soybean yields of three countries under four climate change scenarios: RCP 2.6, 4.5, 6.0 and 8.5 for a period of 2010 to 2070. The significant declining trend of maize yield with time was projected in RCP 8.5 for all countries, while the yield appeared to decrease after 2050 in other RCP scenarios. The extents to which maize yield decrease in 2060s compared to the average over 1980 to 2006 were projected to be about 20% for the United States, 10% for Brazil and China in RCP 2.6, 4.5 and 6.0; 30% for the United States and Brazil, 40% for China in RCP 8.5. On the other hand, the projected changes in soybean yield were complicated. The projected extent to which soybean yield decrease in 2060s compared to the average over 1980 to 2006 was about 30% for the United States and Brazil and 20% for China in RCP 2.6. In RCP 4.5 and 6.0, the yield was projected to be constant

  6. Verifying conventional stability in Europe: An overview. Interim report

    SciTech Connect

    Hirschfeld, T.J.

    1990-04-01

    Verifying the obligations in the prospective Conventional Forces in Europe (CFE) treaty will be far harder and more expensive than verifying those in the Intermediate-Range Nuclear Forces (INF) treaty, or in other previous arms control agreements. This Note presents a qualitative overview of conventional arms control verification issues, including (1) monitoring force levels calibrated in major items of equipment and personnel, in a large production area that makes concealment possible; (2) watching force withdrawals, restructuring, or disbandments involving removal, reexport, or destruction of thousands of heavy equipment items; (3) monitoring the post-agreement status of the largest and most complex force concentration in peacetime history; and (4) meshing these observations with the concurrent need to monitor unilateral Warsaw Pact force reductions and force changes on a massive scale.

  7. The Los Alamos National Laboratory 94/100-1 materials stabilization and deinventory project

    SciTech Connect

    Archuleta, L. P.; Gallegos, N. M.; Urbina, L.

    2004-01-01

    Special nuclear material (SNM) in the Los Alamos National Laboratory (LANL) inventory that has been declared excess to programmatic needs is comprised of a large variety of chemical and physical forms. Many of these nuclear material items have been identified by the Defense Nuclear Facilities Safety Board (DNFSB) as a potential high risk to LANL workers and have been targeted for stabilization in recommendations DNFSB 94-1 and 00-1, In addition, vault space at the LANL Plutonium Facility is at a premium due to various ongoing programmatic missions and a lack of available disposition pathways. For these reasons LANL requested, and was granted by Department of Energy (DOE), a variance to terminate safeguards on attractiveness level D SNM items meeting the variance criteria. Materials meeting these criteria have been brought from the vault to the operating floor and opened in a hood or the glovebox line. Each item is inspected by a subject matter expert to: (1) verify there is no programmatic need for the item, and (2) determine if the item should be discarded as waste or sent for recovery. Items selected for discard are inspected by waste management personnel to ensure they meet the Waste Isolation Pilot Plant (WIPP) criteria for acceptance. This includes verification of the acceptable knowledge as well as the absence of items prohibited for disposal at WIPP. The item(s) are sent to waste management for packaging and certification for final transfer to WIPP. This poster presents an overview of the LANL Plutonium Facility disposition effort and progress to date.

  8. Loss of interim status (LOIS) under RCRA. RCRA Information Brief

    SciTech Connect

    Not Available

    1992-09-01

    The Resource Conservation and Recovery Act (RCRA) requires owners and operators of facilities that treat store, or disposal of hazardous waste (TSDFs) to obtain an operating permit. Recognizing that it would take EPA many years to issue operating permits to all RCRA facilities, Congress created ``interim status`` under Section 3005(e) of the Act. Interim status allows facilities to operate under Subtitle C of RCRA until their permits are issued or denied. This information brief defines interim status and describes how failure to meet interim status requirements may lead to loss of interim status (LOIS).

  9. Collaborative Research: Robust Climate Projections and Stochastic Stability of Dynamical Systems

    SciTech Connect

    Ghil, Michael; McWilliams, James; Neelin, J. David; Zaliapin, Ilya; Chekroun, Mickael; Kondrashov, Dmitri; Simonnet, Eric

    2011-10-13

    The project was completed along the lines of the original proposal, with additional elements arising as new results were obtained. The originally proposed three thrusts were expanded to include an additional, fourth one. (i) The e ffects of stochastic perturbations on climate models have been examined at the fundamental level by using the theory of deterministic and random dynamical systems, in both nite and in nite dimensions. (ii) The theoretical results have been implemented first on a delay-diff erential equation (DDE) model of the El-Nino/Southern-Oscillation (ENSO) phenomenon. (iii) More detailed, physical aspects of model robustness have been considered, as proposed, within the stripped-down ICTP-AGCM (formerly SPEEDY) climate model. This aspect of the research has been complemented by both observational and intermediate-model aspects of mid-latitude and tropical climate. (iv) An additional thrust of the research relied on new and unexpected results of (i) and involved reduced-modeling strategies and associated prediction aspects have been tested within the team's empirical model reduction (EMR) framework. Finally, more detailed, physical aspects have been considered within the stripped-down SPEEDY climate model. The results of each of these four complementary e fforts are presented in the next four sections, organized by topic and by the team members concentrating on the topic under discussion.

  10. 40 CFR 1033.150 - Interim provisions.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 1033.150 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR POLLUTION CONTROLS CONTROL OF EMISSIONS FROM LOCOMOTIVES Emission Standards and Related Requirements § 1033.150 Interim... remanufacture locomotives to meet the applicable standards in 40 CFR part 92 only if no remanufacture system...

  11. 7 CFR 1735.75 - Interim financing.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... preliminary approval from RUS. See § 1735.90 (g) See 7 CFR part 1737 for regulations on interim financing for... completed RUS Form 490, “Application for Telephone Loan or Loan Guarantee.” See 7 CFR part 1737. (3) The... on any investments in nonrural areas. See 7 CFR 1737. (4) The information required in § 1735.74...

  12. 7 CFR 1735.75 - Interim financing.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... preliminary approval from RUS. See § 1735.90 (g) See 7 CFR part 1737 for regulations on interim financing for... completed RUS Form 490, “Application for Telephone Loan or Loan Guarantee.” See 7 CFR part 1737. (3) The... on any investments in nonrural areas. See 7 CFR 1737. (4) The information required in § 1735.74...

  13. 340 waste handling facility interim safety basis

    SciTech Connect

    VAIL, T.S.

    1999-04-01

    This document presents an interim safety basis for the 340 Waste Handling Facility classifying the 340 Facility as a Hazard Category 3 facility. The hazard analysis quantifies the operating safety envelop for this facility and demonstrates that the facility can be operated without a significant threat to onsite or offsite people.

  14. Diversified Satellite Occupations Program. Interim Report.

    ERIC Educational Resources Information Center

    Call, John Reed

    This interim report, covering the period of September 1970 to June 1971, describes a program conducted for elementary, junior high, and senior high grades. The elementary program was designed to help students develop an understanding of occupational competence. The prevention of dropouts and individualizing instruction were concerns of the junior…

  15. 340 Waste handling facility interim safety basis

    SciTech Connect

    Stordeur, R.T.

    1996-10-04

    This document presents an interim safety basis for the 340 Waste Handling Facility classifying the 340 Facility as a Hazard Category 3 facility. The hazard analysis quantifies the operating safety envelop for this facility and demonstrates that the facility can be operated without a significant threat to onsite or offsite people.

  16. LANDFILL BIOREACTOR PERFORMANCE, SECOND INTERIM REPORT

    EPA Science Inventory

    A bioreactor landfill is a landfill that is operated in a manner that is expected to increase the rate and extent of waste decomposition, gas generation, and settlement compared to a traditional landfill. This Second Interim Report was prepared to provide an interpretation of fie...

  17. Disposal facility data for the interim performance

    SciTech Connect

    Eiholzer, C.R.

    1995-05-15

    The purpose of this report is to identify and provide information on the waste package and disposal facility concepts to be used for the low-level waste tank interim performance assessment. Current concepts for the low-level waste form, canister, and the disposal facility will be used for the interim performance assessment. The concept for the waste form consists of vitrified glass cullet in a sulfur polymer cement matrix material. The waste form will be contained in a 2 {times} 2 {times} 8 meter carbon steel container. Two disposal facility concepts will be used for the interim performance assessment. These facility concepts are based on a preliminary disposal facility concept developed for estimating costs for a disposal options configuration study. These disposal concepts are based on vault type structures. None of the concepts given in this report have been approved by a Tank Waste Remediation Systems (TWRS) decision board. These concepts will only be used in th interim performance assessment. Future performance assessments will be based on approved designs.

  18. 15 CFR 908.5 - Interim reports.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 15 Commerce and Foreign Trade 3 2010-01-01 2010-01-01 false Interim reports. 908.5 Section 908.5 Commerce and Foreign Trade Regulations Relating to Commerce and Foreign Trade (Continued) NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION, DEPARTMENT OF COMMERCE GENERAL REGULATIONS MAINTAINING RECORDS AND SUBMITTING REPORTS ON WEATHER...

  19. 15 CFR 908.5 - Interim reports.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 15 Commerce and Foreign Trade 3 2014-01-01 2014-01-01 false Interim reports. 908.5 Section 908.5 Commerce and Foreign Trade Regulations Relating to Commerce and Foreign Trade (Continued) NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION, DEPARTMENT OF COMMERCE GENERAL REGULATIONS MAINTAINING REC-ORDS AND SUBMITTING REPORTS ON WEATHER...

  20. 15 CFR 908.5 - Interim reports.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 15 Commerce and Foreign Trade 3 2012-01-01 2012-01-01 false Interim reports. 908.5 Section 908.5 Commerce and Foreign Trade Regulations Relating to Commerce and Foreign Trade (Continued) NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION, DEPARTMENT OF COMMERCE GENERAL REGULATIONS MAINTAINING REC- ORDS AND SUBMITTING REPORTS ON WEATHER...

  1. Progress on plutonium stabilization

    SciTech Connect

    Hurt, D.

    1996-05-01

    The Defense Nuclear Facilities Safety Board has safety oversight responsibility for most of the facilities where unstable forms of plutonium are being processed and packaged for interim storage. The Board has issued recommendations on plutonium stabilization and has has a considerable influence on DOE`s stabilization schedules and priorities. The Board has not made any recommendations on long-term plutonium disposition, although it may get more involved in the future if DOE develops plans to use defense nuclear facilities for disposition activities.

  2. Reflections on Post-16 Strategies in European Countries. Interim Report of the Leonardo da Vinci/Multiplier Effect Project III.3.a. Priority 2: Forging Links between Educational Establishments and Enterprises (1997-2000) ID 27009. Working Papers, No. 9.

    ERIC Educational Resources Information Center

    Stenstrom, Marja-Leena, Ed.

    This four-part publication contains 19 papers on educational practices and promises for post-16 education in European countries. Part I, the introduction, contains these three papers: "Sharpening Post-16 Education Strategies: Building on the Results of the Previous Projects" (Johanna Lasonen); "'Parity of Esteem' and 'Integrated…

  3. PROGRAM-ORIENTED INFORMATION--A MANAGEMENT SYSTEMS COMPLEX FOR STATE EDUCATION AGENCIES. PART I, ANALYSIS AND PROPOSALS. INTERIM REPORT ON A COLLABORATIVE PROJECT "TENTATIVE GUIDES FOR A STATE EDUCATION AGENCY FISCAL, PERSONNEL, AND PROGRAM INFORMATION SYSTEM."

    ERIC Educational Resources Information Center

    FRIEDMAN, BURTON DEAN; AND OTHERS

    THIS DOCUMENT IS THE RESULT OF A PROJECT TO CONCEIVE AND ESTABLISH AN INFORMATION SYSTEM FOR FINANCIAL, PERSONNEL, AND PROGRAM ACCOUNTING OF STATE EDUCATION AGENCIES' TOTAL INTERNAL OPERATION. SUCH SYSTEMS ARE DEEMED NECESSARY NOW THAT THE AGENCIES' OPERATIONS ARE STRONGLY AFFECTED BY FEDERAL PROGRAMS AND FUNDS AND ARE THUS A MATTER OF NATIONWIDE…

  4. Joint Meeting of Allied Health Professional Projects Staff and the Board of Directors and Staff, League for Innovation in the Community College (Los Angeles, Nov. 20, 1968). Interim Report.

    ERIC Educational Resources Information Center

    Allied Health Professions Projects, Los Angeles, CA.

    Thirty-five representatives participated in a joint meeting to share information about the Allied Health Professions Projects and paramedical education at League Colleges, and to plan for cooperative work. In an informal summary, B. Lamar Johnson outlined areas of possible cooperation that he believed would emerge from an examination of the…

  5. T-TY Tank Farm Interim Surface Barrier Demonstration - Vadose Zone Monitoring FY10 Report

    SciTech Connect

    Zhang, Z. F.; Strickland, Christopher E.; Field, Jim G.; Parker, Danny L.

    2011-01-01

    The U.S. Department of Energy’s Office of River Protection has constructed interim surface barriers over a portion of the T and TY tank farms as part of the Interim Surface Barrier Demonstration Project. The interim surface barriers (hereafter referred to as the surface barriers or barriers) are designed to minimize the infiltration of precipitation into the soil zones containing radioactive contaminants and minimize the movement of the contaminants. As part of the demonstration effort, vadose zone moisture is being monitored to assess the effectiveness of the barriers at reducing soil moisture. Solar-powered systems were installed to continuously monitor soil water conditions at four locations in the T (i.e., instrument Nests TA, TB, TC, and TD) and the TY (i.e., instrument Nests TYA and TYB) Farms beneath the barriers and outside the barrier footprint as well as site meteorological conditions. Nests TA and TYA are placed in the area outside the barrier footprint and serve as controls, providing subsurface conditions outside the influence of the surface barriers. Nest TB provides subsurface measurements to assess surface-barrier edge effects. Nests TC, TD, and TYB are used to assess changes in soil-moisture conditions beneath the interim surface barriers.

  6. Dental Auxiliary Occupations. Interim Report.

    ERIC Educational Resources Information Center

    Kingston, Richard D.

    As part of a dental auxiliaries project, a Dental Auxiliary National Technical Advisory Committee was established, and its major undertaking was to assist in the development of a functional inventory for each of the three dental auxiliary occupations (dental assisting, dental hygiene, and dental laboratory technology). The analysis consisted of…

  7. Veterans Employment Pay for Success Grant Program. Interim final rule.

    PubMed

    2016-08-10

    The Department of Veterans Affairs (VA) is establishing a grant program (Veterans Employment Pay for Success (VEPFS)) under the authority of the U.S.C. to award grants to eligible entities to fund projects that are successful in accomplishing employment rehabilitation for Veterans with service-connected disabilities. VA will award grants on the basis of an eligible entity's proposed use of a Pay for Success (PFS) strategy to achieve goals. This interim final rule establishes regulations for awarding a VEPFS grant, including the general process for awarding the grant, criteria and parameters for evaluating grant applications, priorities related to the award of a grant, and general requirements and guidance for administering a VEPFS grant program. PMID:27529903

  8. Seismic stability evaluation of Ririe Dam and reservoir project. Report 2. Stability calculations, analysis and evaluation. Volume 2, Appendixes A through E

    SciTech Connect

    Sykora, D.W.; Koester, J.P.; Hynes, M.E.

    1991-09-01

    A study aimed at the evaluation of the stability of the Ririe Dam in Idaho was undertaken. The work is to be performed in two phases, the first of which is devoted to two-dimensional (2D) analyses, while the second is concerned with the investigation of the influence of the three-dimensional effects on the overall stability of the dam. This report presents results of Phase I of the program. An extensive number of effective stress stability analyses involving both circular and non-circular failure surfaces were performed using three different methods of stability analyses, namely the modified Bishop, Spencer and MIT methods. Both gravity and earthquake loadings were considered. Circular arc analyses for gravity loading were performed using the computer program STAB3D, whereas the program TSLOPE was utilized for all other analyses.

  9. 1998 interim 242-A Evaporator tank system integrity assessment report

    SciTech Connect

    Jensen, C.E.

    1998-07-02

    This Integrity Assessment Report (IAR) is prepared by Fluor Daniel Northwest (FDNW) under contract to Lockheed-Martin Hanford Company (LMHC) for Waste Management Hanford (WMH), the 242-A Evaporator (facility) operations contractor for Fluor Daniel Hanford, and the US Department of Energy, the system owner. The contract specifies that FDNW perform an interim (5 year) integrity assessment of the facility and prepare a written IAR in accordance with Washington Administrative Code (WAC) 173-303-640. The WAC 173-303 defines a treatment, storage, or disposal (TSD) facility tank system as the ``dangerous waste storage or treatment tank and its ancillary equipment and containment.`` This integrity assessment evaluates the two tank systems at the facility: the evaporator vessel, C-A-1 (also called the vapor-liquid separator), and the condensate collection tank, TK-C-100. This IAR evaluates the 242-A facility tank systems up to, but not including, the last valve or flanged connection inside the facility perimeter. The initial integrity assessment performed on the facility evaluated certain subsystems not directly in contact with dangerous waste, such as the steam condensate and used raw water subsystems, to provide technical information. These subsystems were not evaluated in this IAR. The last major upgrade to the facility was project B-534. The facility modifications, as a result of project B-534, were evaluated in the 1993 facility interim integrity assessment. Since that time, the following upgrades have occurred in the facility: installation of a process condensate recycle system, and installation of a package steam boiler to provide steam for the facility. The package boiler is not within the scope of the facility TSD.

  10. Operations and Maintenance Concept Plan for the Immobilized High Level Waste (IHLW) Interim Storage Facility

    SciTech Connect

    JANIN, L.F.

    2000-08-30

    This O&M Concept looks at the future operations and maintenance of the IHLW/CSB interim storage facility. It defines the overall strategy, objectives, and functional requirements for the portion of the building to be utilized by Project W-464. The concept supports the tasks of safety basis planning, risk mitigation, alternative analysis, decision making, etc. and will be updated as required to support the evolving design.

  11. Interim Report 1985. Working Document. European Community Action Programme. Transition of Young People from Education to Adult and Working Life.

    ERIC Educational Resources Information Center

    IFAPLAN, Brussels (Belgium). Programme Information Office.

    This document provides an interim report on 30 pilot projects that make up the European Community's second Programme on the Transition from Education to Adult and Working Life. The main part of the report consists of 10 sections reviewing activities in the 10 thematic or policy areas adopted, in consultation with national authorities, to…

  12. Nutrition and Child Growth and Development in Tunisia. Interim Progress Report, (September 1, 1972--February 28, 1973).

    ERIC Educational Resources Information Center

    Young, Harben Boutourline

    This interim report of the Yale Project describes the progress made on the nutrition and growth study of Tunisian children from September 1, 1972 through February 28, 1973. A major part of the report is devoted to the organizational and data collection problems of the longitudinal study, discussed under the following categories: biomedics,…

  13. Kennedy Space Center Press Site (SWMU 074) Interim Measure Report

    NASA Technical Reports Server (NTRS)

    Applegate, Joseph L.

    2015-01-01

    This report summarizes the Interim Measure (IM) activities conducted at the Kennedy Space Center (KSC) Press Site ("the Press Site"). This facility has been designated as Solid Waste Management Unit 074 under KSC's Resource Conservation and Recovery Act Corrective Action program. The activities were completed as part of the Vehicle Assembly Building (VAB) Area Land Use Controls Implementation Plan (LUCIP) Elimination Project. The purpose of the VAB Area LUCIP Elimination Project was to delineate and remove soil affected with constituents of concern (COCs) that historically resulted in Land Use Controls (LUCs). The goal of the project was to eliminate the LUCs on soil. LUCs for groundwater were not addressed as part of the project and are not discussed in this report. This report is intended to meet the Florida Department of Environmental Protection (FDEP) Corrective Action Management Plan requirement as part of the KSC Hazardous and Solid Waste Amendments permit and the U.S. Environmental Protection Agency's (USEPA's) Toxic Substance Control Act (TSCA) self-implementing polychlorinated biphenyl (PCB) cleanup requirements of 40 Code of Federal Regulations (CFR) 761.61(a).

  14. ECALS: loading studies interim report October 2013

    USGS Publications Warehouse

    Klymus, Katy; Richter, Cathy; Chapman, Duane; Paukert, Craig P.

    2013-01-01

    Here we follow up the loading studies interim report from July 2013 and include results from laboratory studies assessing the effects of diet on eDNA shedding rates by bigheaded carps(silver and bighead carp). In order to understand how eDNA behavesin the environment, we must understand how it enters the system. In our July interim report, we addressed three of our four hypotheses that could influence the shedding rate of eDNA by these fish (Table 1; hypotheses A, B and D). We now provide results from studies that tested the fourth hypothesis (C), cellular debris from the gut-lining shed via excrementis a major source of shed eDNA.

  15. Canadian microwaves - An interim report

    NASA Astrophysics Data System (ADS)

    Kachmar, Michael

    1987-02-01

    A survey is presented of various research programs being pursued by Canadian companies to develop microwave technologies for communications satellites. The discussion covers corporate resources and projects undertaken, e.g., the ANIK and Olympus microwave systems, the MSAT program, SARSAT, BRASILSAT and RADARSAT. Attention is given to intergovernmental, industry-government and fully commercial arrangements, and developmental efforts in the C and Ku bands, X-band SAR devices, and plans for a Shuttle-borne wide angle Michelson Doppler Imaging Interferometer for upper atmospheric research.

  16. 78 FR 38807 - Proposed Collection; Comment Request for Regulation Project

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-06-27

    ... From the Federal Register Online via the Government Publishing Office DEPARTMENT OF THE TREASURY Internal Revenue Service Proposed Collection; Comment Request for Regulation Project AGENCY: Internal... Number: 1545-2180. Regulation Project Number: TD 9491. Abstract: This document contains interim...

  17. Compilation of interim technical research memoranda. Volume I

    SciTech Connect

    Shanahan, W.R.

    1984-04-01

    Four interim technical research memoranda are presented that describe the results of numerical simulations designed to investigate the dynamics of energetic plasma beams propagating across magnetic fields.

  18. Controlled Landfill Project in Yolo County, California for Environmental Benefits of Waste Stabilization and Minimization of Greenhouse Gas Emissions

    NASA Astrophysics Data System (ADS)

    Yazdani, R.; Augenstein, D.; Kieffer, J.; Cohen, K.

    2003-12-01

    The Department of Public Works of Yolo County, California, USA has been testing an advanced approach to landfill bioreactors, controlled (or "enhanced") landfilling, at its Yolo County Central Landfill site near Davis, CA, since 1994. Overall objectives have been the management of waste landfilling for: (1) rapid completion of total gas generation; (2) maximum, high-efficiency gas capture; (3) waste volume reduction; and (4) maximum greenhouse gas and carbon sequestration benefits. Methane generation is controlled and enhanced through carefully managed moisture additions, and by taking advantage of landfill temperature elevation. The generated landfill methane, an important greenhouse gas, is recovered with high efficiency through extraction from a porous recovery layer beneath a surface geomembrane cover. Instrumentation included a total of 56 moisture and 15 temperature sensors in the two cells, gas flow monitoring by positive displacement gas meters, and accurate quantification of liquid inputs and outputs. Gas composition, waste volume reduction, base hydrostatic head, and a range of environmental compliance parameters has been monitored since 1995. Partitioning gas tracer tests using the injection of two gases at dilute concentrations in the landfill have also been initiated to compute the fraction of pore space occupied by water between the points of tracer injection and tracer measurement. There has been rapid waste volume reduction in the enhanced cell that corresponds to the solids' reduction to gas. Monitoring is planned for the next several years, until stabilization parameters are determined complete. Encouraging performance is indicated by: (1) sensor data; (2) gas generation results; (3) data from landfill cores; and (4) decomposition-related indicators including rapid volume reduction. When data are synthesized, project results have attractive implications for new approaches to landfill management. Over seven-years, methane recoveries have averaged

  19. Evaluating the accotink creek restoration project for improving water quality, in-stream habitat, and bank stability

    USGS Publications Warehouse

    Struck, S.D.; Selvakumar, A.; Hyer, K.; O'Connor, T.

    2007-01-01

    Increased urbanization results in a larger percentage of connected impervious areas and can contribute large quantities of stormwater runoff and significant quantities of debris and pollutants (e.g., litter, oils, microorganisms, sediments, nutrients, organic matter, and heavy metals) to receiving waters. To improve water quality in urban and suburban areas, watershed managers often incorporate best management practices (BMPs) to reduce the quantity of runoff as well as to minimize pollutants and other stressors contained in stormwater runoff. It is well known that land-use practices directly impact urban streams. Stream flows in urbanized watersheds increase in magnitude as a function of impervious area and can result in degradation of the natural stream channel morphology affecting the physical, chemical, and biological integrity of the stream. Stream bank erosion, which also increases with increased stream flows, can lead to bank instability, property loss, infrastructure damage, and increased sediment loading to the stream. Increased sediment loads may lead to water quality degradation downstream and have negative impacts on fish, benthic invertebrates, and other aquatic life. Accotink Creek is in the greater Chesapeake Bay and Potomac watersheds, which have strict sediment criteria. The USEPA (United States Environmental Protection Agency) and USGS (United States Geological Survey) are investigating the effectiveness of stream restoration techniques as a BMP to decrease sediment load and improve bank stability, biological integrity, and in-stream water quality in an impaired urban watershed in Fairfax, Virginia. This multi-year project continuously monitors turbidity, specific conductance, pH, and water temperature, as well as biological and chemical water quality parameters. In addition, physical parameters (e.g., pebble counts, longitudinal and cross sectional stream surveys) were measured to assess geomorphic changes associated with the restoration. Data

  20. Functions and requirements document for interim store solidified high-level and transuranic waste

    SciTech Connect

    Smith-Fewell, M.A., Westinghouse Hanford

    1996-05-17

    The functions, requirements, interfaces, and architectures contained within the Functions and Requirements (F{ampersand}R) Document are based on the information currently contained within the TWRS Functions and Requirements database. The database also documents the set of technically defensible functions and requirements associated with the solidified waste interim storage mission.The F{ampersand}R Document provides a snapshot in time of the technical baseline for the project. The F{ampersand}R document is the product of functional analysis, requirements allocation and architectural structure definition. The technical baseline described in this document is traceable to the TWRS function 4.2.4.1, Interim Store Solidified Waste, and its related requirements, architecture, and interfaces.

  1. High normalized beta plasmas exceeding the ideal stability limit and projected RWM active stabilization performance using newly installed feedback sensors in KSTAR

    NASA Astrophysics Data System (ADS)

    Park, Y. S.; Sabbagh, S. A.; Berkery, J. W.; Bialek, J. M.; Yoon, S. W.; Jeon, Y. M.; Bak, J. G.; Ko, W. H.; Hahn, S. H.; Bae, C.; Bae, Y. S.; in, Y. K.; Kim, J.; Lee, S. G.; Kwak, J. G.; Oh, Y. K.; Park, H. K.; Choi, M. J.; Yun, G. S.

    2015-11-01

    H-mode plasma operation of KSTAR has been expanded to significantly surpass the ideal MHD no-wall beta limit by achieving normalized beta up to 4.3 while reducing plasma internal inductance to near 0.7 exceeding the computed n = 1 ideal no-wall limit by a factor of 1.6. These high normalized beta values have been achieved in discharges having BT in the range 0.9-1.1 T after the plasma reached flattop current of 0.35-0.4 MA, with the highest neutral beam heating power of 4 MW. A significant conclusion of the analysis of these plasmas is that low- n global kink/ballooning or RWMs were not detected, and therefore were not the cause of the plasma termination. Advances from the 2015 run campaign aiming to achieve prolonged pulse duration at maximum normalized beta and to subsequently investigate the MHD stability of these plasmas will be reported. As KSTAR H-mode operation can now routinely surpass the ideal no-wall stability limit, n = 1 RWM active control is planned for the device. RWM active feedback using a newly installed set of poloidal magnetic field sensors mounted on the passive stabilizer plates and designed for optimal performance is analyzed using the VALEN-3D code. The advantages of the new sensors over other device sensors for RWM active control are discussed. Supported by U.S. DOE grant DE-FG02-99ER54524.

  2. Science Opportunities Enabled by NASA's Constellation System: Interim Report

    NASA Technical Reports Server (NTRS)

    2008-01-01

    on two criteria: whether the concepts offered the potential for a significant scientific advance, and whether or not the concepts would benefit from the Constellation System. The committee determined that all of the concepts offered the possibility of a significant scientific advance, but it cautions that such an evaluation ultimately must be made by the decadal survey process, and it emphasizes that this interim report s evaluation should not be considered to be an endorsement of the scientific merit of these proposals, which must of course be evaluated relative to other proposals. The committee determined that seven of these concepts would benefit from the Constellation System, whereas four would not, but it stresses that this conclusion does not reflect an evaluation of the scientific merit of the projects, but rather an assessment of whether or not new capabilities provided by the Constellation System could significantly affect them. Some of the mission concepts, such as the Advanced Compton Telescope, already offer a significant scientific advance and fit easily within the mass and volume constraints of existing launch vehicles. Other mission concepts, such as the Palmer Quest proposal to drill through the Mars polar cap, are not constrained by the launch vehicle, but rather by other technology limitations. The committee evaluated the mission concepts as presented to it, aware nevertheless that proposing a far larger and more ambitious mission with the same science goals might be possible given the capabilities of the Ares V launch vehicle. (Such proposals can be submitted in response to the committee s request for information to be evaluated in its final report.) See Table S.1 for a summary of the Vision Missions, including their cost estimates, technical maturity, and reasons that they might benefit from the Constellation System. The committee developed several findings and recommendations.

  3. The Homestake Interim Laboratory and Homestake DUSEL

    NASA Astrophysics Data System (ADS)

    Lesko, Kevin T.

    2011-12-01

    The former Homestake gold mine in Lead South Dakota is proposed for the National Science Foundation's Deep Underground Science and Engineering Laboratory (DUSEL). The gold mine provides expedient access to depths in excess of 8000 feet below the surface (>7000 mwe). Homestake's long history of promoting scientific endeavours includes the Davis Solar Neutrino Experiment, a chlorine-based experiment that was hosted at the 4850 Level for more than 30 years. As DUSEL, Homestake would be uncompromised by competition with mining interests or other shared uses. The facility's 600-km of drifts would be available for conversion for scientific and educational uses. The State of South Dakota, under Governor Rounds' leadership, has demonstrated exceptionally strong support for Homestake and the creation of DUSEL. The State has provided funding totalling $46M for the preservation of the site for DUSEL and for the conversion and operation of the Homestake Interim Laboratory. Motivated by the strong educational and outreach potential of Homestake, the State contracted a Conversion Plan by world-recognized mine-engineering contractor to define the process of rehabilitating the facility, establishing the appropriate safety program, and regaining access to the facility. The State of South Dakota has established the South Dakota Science and Technology Authority to oversee the transfer of the Homestake property to the State and the rehabilitation and preservation of the facility. The Homestake Scientific Collaboration and the State of South Dakota's Science and Technology Authority has called for Letters of Interest from scientific, educational and engineering collaborations and institutions that are interested in hosting experiments and uses in the Homestake Interim Facility in advance of the NSF's DUSEL, to define experiments starting as early as 2007. The Homestake Program Advisory Committee has reviewed these Letters and their initial report has been released. Options for

  4. Validation of ERA-Interim precipitation estimates over the Baltic Sea

    NASA Astrophysics Data System (ADS)

    Bumke, Karl

    2015-04-01

    The closing of the energy and water budgets of the Baltic Sea is only possible, when beside an accurate knowledge of the in- and outflows through the Danish Sounds, evaporation and precipitation are exactly known. Due to a lack of in-situ observations of precipitation over sea it is common to use data from numerical models or remote sensing, although e.g. Andersson et al. (2011) pointed out that even state-of-the-art satellite retrievals and reanalysis data sets still disagree with respect to amounts or variability compared to observations. In our study we validate ERA-Interim reanalysis data of total precipitation against ten years (1995-2004) of in-situ precipitation measurements onboard of ships. ERA-Interim data consist of three hourly surface forecast fields on a regular grid with a 0.75° x 0.75° resolution, which are initiated twice a day. Observations within the forecast period were collocated to the surrounding grid points of the reanalysis data. Since ship rain gauges are only suitable to measure rain, only measurements at air temperatures above 4°C were taken into account. The number of collocated data exceeds 200000. Comparing all data gives a good agreement of mean rain rates of measurements and reanalysis data. But a closer look reveals an underestimation of ERA-Interim precipitation in spring and an overestimation in autumn, related to atmospheric stability. The atmospheric stability is linked to turbulent heat fluxes and indeed it is found that ERA-Interim underestimates rain rates by up to 40 percent under situations with low latent heat fluxes and overestimates rain rates strongly up to about 150 percent under conditions with high latent heat fluxes. To ensure that this is not an artefact due to uncertainties in ERA-Interim fields of evaporation, meteorological data of ships have been extracted from the marine meteorological data archive of the Seewetteramt Hamburg, and were also collocated to the reanalysis data. These data were used to derive

  5. 17 CFR 210.10-01 - Interim financial statements.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ...-01 Interim financial statements. (a) Condensed statements. Interim financial statements shall follow... of this Regulation with the exception of inventories. Data as to raw materials, work in process and... adequacy of additional disclosure needed for a fair presentation, except in regard to...

  6. 17 CFR 210.10-01 - Interim financial statements.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... CONSERVATION ACT OF 1975 Interim Financial Statements § 210.10-01 Interim financial statements. (a) Condensed... as to raw materials, work in process and finished goods inventories shall be included either on the... presentation, except in regard to material contingencies, may be determined in that context....

  7. 28 CFR 94.41 - Interim emergency payment.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 28 Judicial Administration 2 2014-07-01 2014-07-01 false Interim emergency payment. 94.41 Section 94.41 Judicial Administration DEPARTMENT OF JUSTICE (CONTINUED) CRIME VICTIM SERVICES International Terrorism Victim Expense Reimbursement Program Payment of Claims § 94.41 Interim emergency...

  8. Into the Sunset: Reflections of an Interim Administrator.

    ERIC Educational Resources Information Center

    Marlowe, John

    2000-01-01

    One advantage to an interim administrative position is that the public cuts short-timers a little slack. Temporary administrators can learn on the job and become experts on specialized subjects. Personnel issues demand more time than interims possess. Such positions usually do not turn into long-term contracts. (MLH)

  9. 10 CFR 205.288 - Interim and ancillary orders.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 10 Energy 3 2010-01-01 2010-01-01 false Interim and ancillary orders. 205.288 Section 205.288 Energy DEPARTMENT OF ENERGY OIL ADMINISTRATIVE PROCEDURES AND SANCTIONS Special Procedures for Distribution of Refunds § 205.288 Interim and ancillary orders. The Director of the Office of Hearings...

  10. Staff Reactions to Interim Leadership in a Student Affairs Organization

    ERIC Educational Resources Information Center

    Jones, Robin D.

    2011-01-01

    Interim leadership appointments in higher education are a common strategy used to fill leadership gaps in executive positions. Because student affairs executives are particularly vulnerable to high turnover rates, interim appointments are becoming more widespread. Even with the prevalence of this trend, little attention has been given to the…

  11. Presidential Transition: The Experience of Two Community College Interim Presidents

    ERIC Educational Resources Information Center

    Thompson, Matthew D.

    2010-01-01

    The purpose of this qualitative case study was to understand the experiences of two community college interim presidents, their characteristics, and how they led institutions following an abrupt presidential departure. There were two fundamental questions framing this research study, 1. How do two interim community college presidents lead…

  12. Statistical Profile of Children and Mothers in Afghanistan. Interim Edition.

    ERIC Educational Resources Information Center

    United Nations Children's Fund, Kabul (Afghanistan).

    This interim report is an updating of the 1977 Statistical Profile of Children and Mothers in Afghanistan. The interim report reflects the significant changes in policies brought about by the Saur Revolution establishing the Democratic Republic of Afghanistan in 1978. A comprehensive revision of the report is expected when the new government's…

  13. 46 CFR 308.203 - Amount insured under interim binder.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 46 Shipping 8 2011-10-01 2011-10-01 false Amount insured under interim binder. 308.203 Section 308.203 Shipping MARITIME ADMINISTRATION, DEPARTMENT OF TRANSPORTATION EMERGENCY OPERATIONS WAR RISK INSURANCE War Risk Protection and Indemnity Insurance § 308.203 Amount insured under interim binder....

  14. 47 CFR 73.404 - Interim hybrid IBOC DAB operation.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 47 Telecommunication 4 2014-10-01 2014-10-01 false Interim hybrid IBOC DAB operation. 73.404 Section 73.404 Telecommunication FEDERAL COMMUNICATIONS COMMISSION (CONTINUED) BROADCAST RADIO SERVICES RADIO BROADCAST SERVICES Digital Audio Broadcasting § 73.404 Interim hybrid IBOC DAB operation. (a)...

  15. 47 CFR 73.404 - Interim hybrid IBOC DAB operation.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 47 Telecommunication 4 2013-10-01 2013-10-01 false Interim hybrid IBOC DAB operation. 73.404 Section 73.404 Telecommunication FEDERAL COMMUNICATIONS COMMISSION (CONTINUED) BROADCAST RADIO SERVICES RADIO BROADCAST SERVICES Digital Audio Broadcasting § 73.404 Interim hybrid IBOC DAB operation. (a)...

  16. 7 CFR 280.1 - Interim disaster procedures.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 7 Agriculture 4 2011-01-01 2011-01-01 false Interim disaster procedures. 280.1 Section 280.1... AGRICULTURE FOOD STAMP AND FOOD DISTRIBUTION PROGRAM EMERGENCY FOOD ASSISTANCE FOR VICTIMS OF DISASTERS § 280.1 Interim disaster procedures. The Secretary shall, after consultation with the official...

  17. 7 CFR 280.1 - Interim disaster procedures.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 7 Agriculture 4 2012-01-01 2012-01-01 false Interim disaster procedures. 280.1 Section 280.1... AGRICULTURE FOOD STAMP AND FOOD DISTRIBUTION PROGRAM EMERGENCY FOOD ASSISTANCE FOR VICTIMS OF DISASTERS § 280.1 Interim disaster procedures. The Secretary shall, after consultation with the official...

  18. 7 CFR 280.1 - Interim disaster procedures.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 7 Agriculture 4 2014-01-01 2014-01-01 false Interim disaster procedures. 280.1 Section 280.1... AGRICULTURE FOOD STAMP AND FOOD DISTRIBUTION PROGRAM EMERGENCY FOOD ASSISTANCE FOR VICTIMS OF DISASTERS § 280.1 Interim disaster procedures. The Secretary shall, after consultation with the official...

  19. 7 CFR 280.1 - Interim disaster procedures.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 7 Agriculture 4 2013-01-01 2013-01-01 false Interim disaster procedures. 280.1 Section 280.1... AGRICULTURE FOOD STAMP AND FOOD DISTRIBUTION PROGRAM EMERGENCY FOOD ASSISTANCE FOR VICTIMS OF DISASTERS § 280.1 Interim disaster procedures. The Secretary shall, after consultation with the official...

  20. 7 CFR 280.1 - Interim disaster procedures.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 7 Agriculture 4 2010-01-01 2010-01-01 false Interim disaster procedures. 280.1 Section 280.1... AGRICULTURE FOOD STAMP AND FOOD DISTRIBUTION PROGRAM EMERGENCY FOOD ASSISTANCE FOR VICTIMS OF DISASTERS § 280.1 Interim disaster procedures. The Secretary shall, after consultation with the official...

  1. 50 CFR 660.720 - Interim protection for sea turtles.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 50 Wildlife and Fisheries 13 2012-10-01 2012-10-01 false Interim protection for sea turtles. 660.720 Section 660.720 Wildlife and Fisheries FISHERY CONSERVATION AND MANAGEMENT, NATIONAL OCEANIC AND... Migratory Fisheries § 660.720 Interim protection for sea turtles. (a) Until the effective date of §§...

  2. 50 CFR 660.720 - Interim protection for sea turtles.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 50 Wildlife and Fisheries 13 2013-10-01 2013-10-01 false Interim protection for sea turtles. 660.720 Section 660.720 Wildlife and Fisheries FISHERY CONSERVATION AND MANAGEMENT, NATIONAL OCEANIC AND... Migratory Fisheries § 660.720 Interim protection for sea turtles. (a) Until the effective date of §§...

  3. 50 CFR 660.720 - Interim protection for sea turtles.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 50 Wildlife and Fisheries 13 2014-10-01 2014-10-01 false Interim protection for sea turtles. 660.720 Section 660.720 Wildlife and Fisheries FISHERY CONSERVATION AND MANAGEMENT, NATIONAL OCEANIC AND... Migratory Fisheries § 660.720 Interim protection for sea turtles. (a) Until the effective date of §§...

  4. 50 CFR 660.720 - Interim protection for sea turtles.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 50 Wildlife and Fisheries 9 2010-10-01 2010-10-01 false Interim protection for sea turtles. 660.720 Section 660.720 Wildlife and Fisheries FISHERY CONSERVATION AND MANAGEMENT, NATIONAL OCEANIC AND... Migratory Fisheries § 660.720 Interim protection for sea turtles. (a) Until the effective date of §§...

  5. 50 CFR 660.720 - Interim protection for sea turtles.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 50 Wildlife and Fisheries 11 2011-10-01 2011-10-01 false Interim protection for sea turtles. 660.720 Section 660.720 Wildlife and Fisheries FISHERY CONSERVATION AND MANAGEMENT, NATIONAL OCEANIC AND... Migratory Fisheries § 660.720 Interim protection for sea turtles. (a) Until the effective date of §§...

  6. 14 CFR 136.41 - Interim operating authority.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 14 Aeronautics and Space 3 2011-01-01 2011-01-01 false Interim operating authority. 136.41 Section 136.41 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION, DEPARTMENT OF TRANSPORTATION (CONTINUED... technology, as appropriate, and (9) Shall allow for modifications of the interim operating authority based...

  7. 14 CFR 136.41 - Interim operating authority.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 14 Aeronautics and Space 3 2012-01-01 2012-01-01 false Interim operating authority. 136.41 Section 136.41 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION, DEPARTMENT OF TRANSPORTATION (CONTINUED... technology, as appropriate, and (9) Shall allow for modifications of the interim operating authority based...

  8. 14 CFR 136.41 - Interim operating authority.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 14 Aeronautics and Space 3 2013-01-01 2013-01-01 false Interim operating authority. 136.41 Section 136.41 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION, DEPARTMENT OF TRANSPORTATION (CONTINUED... technology, as appropriate, and (9) Shall allow for modifications of the interim operating authority based...

  9. 14 CFR 136.41 - Interim operating authority.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 14 Aeronautics and Space 3 2014-01-01 2014-01-01 false Interim operating authority. 136.41 Section 136.41 Aeronautics and Space FEDERAL AVIATION ADMINISTRATION, DEPARTMENT OF TRANSPORTATION (CONTINUED... technology, as appropriate, and (9) Shall allow for modifications of the interim operating authority based...

  10. 28 CFR 94.41 - Interim emergency payment.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 28 Judicial Administration 2 2012-07-01 2012-07-01 false Interim emergency payment. 94.41 Section 94.41 Judicial Administration DEPARTMENT OF JUSTICE (CONTINUED) CRIME VICTIM SERVICES International Terrorism Victim Expense Reimbursement Program Payment of Claims § 94.41 Interim emergency...

  11. 28 CFR 94.41 - Interim emergency payment.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 28 Judicial Administration 2 2010-07-01 2010-07-01 false Interim emergency payment. 94.41 Section 94.41 Judicial Administration DEPARTMENT OF JUSTICE (CONTINUED) CRIME VICTIM SERVICES International Terrorism Victim Expense Reimbursement Program Payment of Claims § 94.41 Interim emergency...

  12. 28 CFR 94.41 - Interim emergency payment.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 28 Judicial Administration 2 2013-07-01 2013-07-01 false Interim emergency payment. 94.41 Section 94.41 Judicial Administration DEPARTMENT OF JUSTICE (CONTINUED) CRIME VICTIM SERVICES International Terrorism Victim Expense Reimbursement Program Payment of Claims § 94.41 Interim emergency...

  13. 28 CFR 94.41 - Interim emergency payment.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 28 Judicial Administration 2 2011-07-01 2011-07-01 false Interim emergency payment. 94.41 Section 94.41 Judicial Administration DEPARTMENT OF JUSTICE (CONTINUED) CRIME VICTIM SERVICES International Terrorism Victim Expense Reimbursement Program Payment of Claims § 94.41 Interim emergency...

  14. 47 CFR 51.611 - Interim wholesale rates.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 47 Telecommunication 3 2010-10-01 2010-10-01 false Interim wholesale rates. 51.611 Section 51.611 Telecommunication FEDERAL COMMUNICATIONS COMMISSION (CONTINUED) COMMON CARRIER SERVICES (CONTINUED) INTERCONNECTION Resale § 51.611 Interim wholesale rates. (a) If a state commission cannot, based on the...

  15. The Predictive and Instructional Value of Interim Assessments

    ERIC Educational Resources Information Center

    Pon, Kathleen

    2013-01-01

    This mixed design study investigated the predictive and instructional uses of two different types of interim mathematics assessments given in two different districts. One district administered the same summative type of assessment three times a year, while the other district administered a different interim assessment after six-week intervals of…

  16. 10 CFR 590.403 - Emergency interim orders.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... DEPARTMENT OF ENERGY (CONTINUED) NATURAL GAS (ECONOMIC REGULATORY ADMINISTRATION) ADMINISTRATIVE PROCEDURES WITH RESPECT TO THE IMPORT AND EXPORT OF NATURAL GAS Opinions and Orders § 590.403 Emergency interim... and issue an emergency interim order authorizing the import or export of natural gas. After...

  17. 10 CFR 590.403 - Emergency interim orders.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... DEPARTMENT OF ENERGY (CONTINUED) NATURAL GAS (ECONOMIC REGULATORY ADMINISTRATION) ADMINISTRATIVE PROCEDURES WITH RESPECT TO THE IMPORT AND EXPORT OF NATURAL GAS Opinions and Orders § 590.403 Emergency interim... and issue an emergency interim order authorizing the import or export of natural gas. After...

  18. 47 CFR 73.404 - Interim hybrid IBOC DAB operation.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... RADIO BROADCAST SERVICES Digital Audio Broadcasting § 73.404 Interim hybrid IBOC DAB operation. (a) The... test operation pursuant to § 73.1620, may commence interim hybrid IBOC DAB operation with digital... No. 99-325. FM stations are permitted to operate with hybrid digital effective radiated power...

  19. Interim Calibration Report for the SMMR Simulator

    NASA Technical Reports Server (NTRS)

    Gloersen, P.; Cavalieri, D.

    1979-01-01

    The calibration data obtained during the fall 1978 Nimbus-G underflight mission with the scanning multichannel microwave radiometer (SMMR) simulator on board the NASA CV-990 aircraft were analyzed and an interim calibration algorithm was developed. Data selected for the analysis consisted of in flight sky, first-year sea ice, and open water observations, as well as ground based observations of fixed targets with varied temperatures of selected instrument components. For most of the SMMR channels, a good fit to the selected data set was obtained with the algorithm.

  20. Evaluation of ERA-interim and MERRA Cloudiness in the Southern Oceans

    NASA Technical Reports Server (NTRS)

    Naud, Catherine M.; Booth, James F.; Del Genio, Anthony D.

    2014-01-01

    The Southern Ocean cloud cover modeled by the Interim ECMWF Re-Analysis (ERA-Interim) and Modern- Era Retrospective Analysis for Research and Applications (MERRA) reanalyses are compared against Moderate Resolution Imaging Spectroradiometer (MODIS) and Multiangle Imaging Spectroradiometer (MISR) observations. ERA-Interim monthly mean cloud amounts match the observations within 5%, while MERRA significantly underestimates the cloud amount. For a compositing analysis of clouds in warm season extratropical cyclones, both reanalyses show a low bias in cloud cover. They display a larger bias to the west of the cyclones in the region of subsidence behind the cold fronts. This low bias is larger for MERRA than for ERA-Interim. Both MODIS and MISR retrievals indicate that the clouds in this sector are at a low altitude, often composed of liquid, and of a broken nature. The combined CloudSat-Cloud-Aerosol Lidar and Infrared Pathfinder Satellite Observations (CALIPSO) cloud profiles confirm these passive observations, but they also reveal that low-level clouds in other parts of the cyclones are also not properly represented in the reanalyses. The two reanalyses are in fairly good agreement for the dynamic and thermodynamic characteristics of the cyclones, suggesting that the cloud, convection, or boundary layer schemes are the problem instead. An examination of the lower-tropospheric stability distribution in the cyclones from both reanalyses suggests that the parameterization of shallow cumulus clouds may contribute in a large part to the problem. However, the differences in the cloud schemes and in particular in the precipitation processes, which may also contribute, cannot be excluded.

  1. Effects of polyacrylamide on soil erosion and nutrient losses from substrate material in steep rocky slope stabilization projects.

    PubMed

    Chen, Zhang; Chen, Wenlu; Li, Chengjun; Pu, Yanpin; Sun, Haifeng

    2016-06-01

    Erosion of denuded steep rocky slopes causes increasing losses of nitrogen and phosphorus, which is a severe problem in rocky slope protection. Thus, it is important to determine the appropriate materials that can reduce the erodibility and losses of nitrogen and phosphorus of the soil. In this paper, twenty-seven simulated rainfall events were carried out in a greenhouse, in which the substrate material was artificial soil; nine types of anionic polyacrylamide (PAM) were studied, which consisted of three molecular weight (6, 12, and 18 Mg mol(-1)) and three charge density (10, 20, and 30%) formulations in a 3 by 3 factorial design. The results showed that: (1) Polyacrylamide application reduced total nitrogen losses by 35.3% to 50.0% and total phosphorus losses by 34.9% to 48.0% relative to the control group. (2) The losses of total nitrogen and total phosphorus had significant correlation with the molecular weight. Besides, the losses of total phosphorus, particulate-bound phosphorus and inorganic nitrogen (NH4-N) were significantly correlated with their molecular weight and charge density. However, the losses of dissolved organic nitrogen, inorganic nitrogen (NO3-N), dissolved organic phosphorus, inorganic phosphorus (PO4-P) were non-significantly correlated with molecular weight and charge density. (3) Particulate-bound nitrogen and phosphorus were responsible for the losses of nitrogen and phosphorus during runoff events, where particulate-bound nitrogen made up 71.7% to 73.2% of total nitrogen losses, and particulate-bound phosphorus made up 82.3% to 85.2% of total phosphorus losses. (4) Polyacrylamide treatments increased water-stable aggregates content by 32.3% to 59.1%, total porosity by 11.3% to 49.0%, final infiltrative rate by 41.3% to 72.5%, and reduced soil erosion by 18.9% to 39.8% compared with the control group. Overall, the results of this study indicated that polyacrylamide application in the steep rocky slope stabilization projects could

  2. Interim results from the characterization testing of the Engineering Development (EDM) rubidium clocks for satellite applications

    NASA Technical Reports Server (NTRS)

    Powers, Edward D., Jr.; Danzy, Fredrick

    1990-01-01

    Some interim results from the environmental testing program to evaluate the Engineering Design Model (EDM) of the EG and G Spaceborne Rubidium Clock are presented. This effort is in support of the Global Positioning System (GPS) BLOCK IIR program and is intended to characterize the performance of EG and G design for BLOCK IIR satellite applications. Two EG and G EDM units are currently under test at NRL's Clock Test Facility to measure the long-term frequency stability, drift, and frequency versus temperature characteristics.

  3. Interim reclamation report: Basalt Waste Isolation Project exploration shaft site

    SciTech Connect

    Brandt, C.A.; Rickard, W.H. Jr.; Hefty, M.G.

    1990-02-01

    In 1968, a program was started to assess the feasibility of storing Hanford Site defense waste in deep caverns constructed in basalt. This program was expanded in 1976 to include investigations of the Hanford Site as a potential location for a mined commercial nuclear waste repository. Extensive studies of the geotechnical aspects of the site were undertaken, including preparations for drilling a large diameter Exploratory Shaft. This report describes the development of the reclamation program for the Exploratory Shaft Facility, its implementation, and preliminary estimates of its success. The goal of the reclamation program is to return sites disturbed by the repository program as nearly as practicable to their original conditions using native plant species. 43 refs., 19 figs., 9 tabs.

  4. Putting Data to Work: Interim Recommendations from The Benchmarking Project

    ERIC Educational Resources Information Center

    Miles, Marty; Maguire, Sheila; Woodruff-Bolte, Stacy; Clymer, Carol

    2010-01-01

    As public and private funders have focused on evaluating the effectiveness of workforce development programs, a myriad of data collection systems and reporting processes have taken shape. Navigating these systems takes significant time and energy and often saps frontline providers' capacity to use data internally for program improvement.…

  5. Interim measure work plan/design for Agra, Kansas.

    SciTech Connect

    LaFreniere, L. M.; Environmental Science Division

    2008-11-18

    This Interim Measure Work Plan/Design (IMWP/D) is supplemental to the Argonne document Interim Measure Conceptual Design for Remediation of Source Area Contamination at Agra, Kansas. The IMWP/D includes information required by Kansas Department of Health and Environment (KDHE) Policy BER-RS-029, Policy and Scope of Work for Interim Measures. Specific to Policy BER-RS-029 is the requirement for several documents that will ensure that an adequate amount and type of data are collected for implementation of the IMWP/D and that data quality and safe conditions are prevailed. Such information is included in the IMWP/D as follows: Appendix A: Data Acquisition Plan--Design Testing Requirements; Appendix B: Basis of Design; Appendix C: Permits; Appendix D: Quality Assurance Project Plan; Appendix E: Health and Safety Plan; and Appendix F: Operations, Maintenance, and Monitoring Schedule. The proposed remedial technology for this project is the installation of five large-diameter boreholes (LDBs) in a source area that has been identified on the property formerly used for grain storage by the Commodity Credit Corporation of the U.S. Department of Agriculture (CCC/USDA). The goal of the LDB technology is the remediation of the source area by removal of mass quantities of contaminated soil from the vadose zone and treatment of any remaining contaminated soils that are adjacent to the source area to achieve a carbon tetrachloride concentration below 200 {micro}g/kg. Secondary to the soil remediation is the remediation of groundwater at and adjacent to the source areas. The LDB technology serves the following purposes: (1) The physical removal of contaminated soil from the identified source area. (2) Replacement of less permeable native materials (silty clay, clayey silt, and silty sand) with more permeable materials to facilitate the capture of volatilized contaminants in the vertical borehole. (3) Removal of contaminants volatilized by air sparging (AS) and extracted from the

  6. Retention of long-term interim restorations with sodium fluoride enriched interim cement

    NASA Astrophysics Data System (ADS)

    Strash, Carolyn

    Purpose: Interim fixed dental prostheses, or "provisional restorations", are fabricated to restore teeth when definitive prostheses are made indirectly. Patients undergoing extensive prosthodontic treatment frequently require provisionalization for several months or years. The ideal interim cement would retain the restoration for as long as needed and still allow for ease of removal. It would also avoid recurrent caries by preventing demineralization of tooth structure. This study aims to determine if adding sodium fluoride varnish to interim cement may assist in the retention of interim restorations. Materials and methods: stainless steel dies representing a crown preparation were fabricated. Provisional crowns were milled for the dies using CAD/CAM technology. Crowns were provisionally cemented onto the dies using TempBond NE and NexTemp provisional cements as well as a mixture of TempBond NE and Duraphat fluoride varnish. Samples were stored for 24h then tested or thermocycled for 2500 or 5000 cycles before being tested. Retentive strength of each cement was recorded using a universal testing machine. Results: TempBond NE and NexTemp cements performed similarly when tested after 24h. The addition of Duraphat significantly decreased the retention when added to TempBond NE. NexTemp cement had high variability in retention over all tested time periods. Thermocycling for 2500 and 5000 cycles significantly decreased the retention of all cements. Conclusions: The addition of Duraphat fluoride varnish significantly decreased the retention of TempBond NE and is therefore not recommended for clinical use. Thermocycling significantly reduced the retention of TempBond NE and NexTemp. This may suggest that use of these cements for three months, as simulated in this study, is not recommended.

  7. Natural tooth as an interim prosthesis

    PubMed Central

    Dhariwal, Neha S.; Gokhale, Niraj S.; Patel, Punit; Hugar, Shivayogi M.

    2016-01-01

    A traumatic injury to primary maxillary anterior tooth is one of the common causes for problems with the succedaneous tooth leading to it noneruption. A missing anterior tooth can be psychologically and socially damaging to the patient. Despite a wide range of treatment options available, sometimes, it is inevitable to save the natural tooth. This paper describes the immediate replacement of a right central incisor using a fiber-composite resin splint with the natural tooth crown as a pontic following surgical extraction of the dilacerated impacted permanent maxillary central incisor. The abutment teeth can be conserved with minimal or no preparation, thus keeping the technique reversible and can be completed at chair side thereby avoiding laboratory costs. It can be used as an interim measure until a definitive prosthesis can be fabricated as the growth is still incomplete. PMID:27433074

  8. Honeywell Cascade Distiller System Performance Testing Interim Results

    NASA Technical Reports Server (NTRS)

    Callahan, Michael R.; Sargusingh, Miriam

    2014-01-01

    The ability to recover and purify water through physiochemical processes is crucial for realizing long-term human space missions, including both planetary habitation and space travel. Because of their robust nature, distillation systems have been actively pursued as one of the technologies for water recovery. The Cascade Distillation System (CDS) is a vacuum rotary distillation system with potential for greater reliability and lower energy costs than existing distillation systems. The CDS was previously under development through Honeywell and NASA. In 2009, an assessment was performed to collect data to support down-selection and development of a primary distillation technology for application in a lunar outpost water recovery system. Based on the results of this testing, an expert panel concluded that the CDS showed adequate development maturity, TRL-4, together with the best product water quality and competitive weight and power estimates to warrant further development. The Advanced Exploration Systems (AES) Water Recovery Project (WRP) worked to address weaknesses identified by The Panel; namely bearing design and heat pump power efficiency. Testing at the NASA-JSC Advanced Exploration System Water Laboratory (AES Water Lab) using a prototype Cascade Distillation Subsystem (CDS) wastewater processor (Honeywell International, Torrance, Calif.) with test support equipment and control system developed by Johnson Space Center was performed to evaluate performance of the system with the upgrades. The CDS will also have been challenged with ISS analog waste streams and a subset of those being considered for Exploration architectures. This paper details interim results of the AES WRP CDS performance testing.

  9. Extreme Heat Stress trends in ERA Interim 1979-2011

    NASA Astrophysics Data System (ADS)

    Buzan, J. R.; Huber, M.

    2012-12-01

    Heat stress is a function of temperature and humidity, and is therefore subject to the covariance of the two quantities. One of the robust predictions from climate change is an increase in temperatures across the planet, and therefore heat stress is projected to increase, however the covariance with humidity is less sure. It has been proposed that in future climate, significant portions of the land surface become subject to life threatening heat stress levels to humans and mammals. There are numerous methods and metrics for calculating heat stress, however, the majority use atmospheric state variables (pressure, temperature, and specific humidity), to measure the thermodynamic state of the atmosphere or estimate thermal load on humans and mammals. Here we present calculations of the evolution of heat stress for the past 3 decades using the European Centre for Medium-Range Weather Forecasts (ECMWF) ERA Interim reanalysis data product from near surface boundary layer state variables. We characterize both spatial and temporal trends with a variety of the most commonly used heat stress metrics (wet bulb temperatures, heat index, etc.). The metrics are calculated from 4x daily values to capture both the diurnal cycle and the daily peak values for these indices.

  10. The Time Needed to Implement the Blue Ribbon Commission Recommendation on Interim Storage - 13124

    SciTech Connect

    Voegele, Michael D.; Vieth, Donald

    2013-07-01

    The report of the Blue Ribbon Commission on America's Nuclear Future [1] makes a number of important recommendations to be considered if Congress elects to redirect U.S. high-level radioactive waste disposal policy. Setting aside for the purposes of this discussion any issues related to political forces leading to stopping progress on the Yucca Mountain project and driving the creation of the Commission, an important recommendation of the Commission was to institute prompt efforts to develop one or more consolidated storage facilities. The Blue Ribbon Commission noted that this recommended strategy for future storage and disposal facilities and operations should be implemented regardless of what happens with Yucca Mountain. It is too easy, however, to focus on interim storage as an alternative to geologic disposal. The Blue Ribbon Commission report does not go far enough in addressing the magnitude of the contentious problems associated with reopening the issues of relative authorities of the states and federal government with which Congress wrestled in crafting the Nuclear Waste Policy Act [2]. The Blue Ribbon Commission recommendation for prompt adoption of an interim storage program does not appear to be fully informed about the actions that must be taken, the relative cost of the effort, or the realistic time line that would be involved. In essence, the recommendation leaves to others the details of the systems engineering analyses needed to understand the nature and details of all the operations required to reach an operational interim storage facility without derailing forever the true end goal of geologic disposal. The material presented identifies a number of impediments that must be overcome before the country could develop a centralized federal interim storage facility. In summary, and in the order presented, they are: 1. Change the law, HJR 87, PL 107-200, designating Yucca Mountain for the development of a repository. 2. Bring new nuclear waste

  11. Stabilizing plutonium materials at Hanford: systems engineering for PFP transition project effort on DNFSB 94-1

    SciTech Connect

    Huber, T.E., Westinghouse Hanford

    1996-07-02

    This report discusses the basic objectives of the stabilization and packaging activities at the Plutonium Finishing Plant that satisfy the Defense Nuclear Facility Safety Board Recommendation 94-1 by transforming the plutonium materials at hanford into forms or conditions which are suitable for safe storage to appropriate storage criteria; or discard that meets appropriate waste acceptance criteria.

  12. Interim long-term surveillance plan for the Cheney disposal site near, Grand Junction, Colorado

    SciTech Connect

    1997-08-01

    This interim long-term surveillance plan (LTSP) describes the U.S. Department of Energy`s (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project Cheney Disposal Site in Mesa County near Grand Junction, Colorado. This LSTP describes the long-term surveillance program the DOE will implement to ensure the Cheney disposal site performs as designed and is cared for in a manner that protects the public health and safety and the environment. Before each disposal site is licensed for custody and long-term care, the Nuclear Regulatory Commission (NRC) requires the DOE to submit such a site-specific LTSP.

  13. Operable Unit 3: Proposed Plan/Environmental Assessment for interim remedial action

    SciTech Connect

    Not Available

    1993-12-01

    This document presents a Proposed Plan and an Environmental Assessment for an interim remedial action to be undertaken by the US Department of Energy (DOE) within Operable Unit 3 (OU3) at the Fernald Environmental Management Project (FEMP). This proposed plan provides site background information, describes the remedial alternatives being considered, presents a comparative evaluation of the alternatives and a rationnale for the identification of DOE`s preferred alternative, evaluates the potential environmental and public health effects associated with the alternatives, and outlines the public`s role in helping DOE and the EPA to make the final decision on a remedy.

  14. 46 CFR 308.303 - Amounts insured under interim binder.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... INSURANCE Second Seamen's War Risk Insurance § 308.303 Amounts insured under interim binder. The amounts insured are the amounts specified in the Second Seamen's War Risk Policy (1955) or as modified by...

  15. 46 CFR 308.303 - Amounts insured under interim binder.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... INSURANCE Second Seamen's War Risk Insurance § 308.303 Amounts insured under interim binder. The amounts insured are the amounts specified in the Second Seamen's War Risk Policy (1955) or as modified by...

  16. 46 CFR 308.303 - Amounts insured under interim binder.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... INSURANCE Second Seamen's War Risk Insurance § 308.303 Amounts insured under interim binder. The amounts insured are the amounts specified in the Second Seamen's War Risk Policy (1955) or as modified by...

  17. 46 CFR 308.303 - Amounts insured under interim binder.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... INSURANCE Second Seamen's War Risk Insurance § 308.303 Amounts insured under interim binder. The amounts insured are the amounts specified in the Second Seamen's War Risk Policy (1955) or as modified by...

  18. 46 CFR 308.303 - Amounts insured under interim binder.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... INSURANCE Second Seamen's War Risk Insurance § 308.303 Amounts insured under interim binder. The amounts insured are the amounts specified in the Second Seamen's War Risk Policy (1955) or as modified by...

  19. 40 CFR 155.56 - Interim registration review decision.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... required data, conducting the new risk assessment and completing the registration review. A FIFRA 3(c)(2)(B... registration review decision may require new risk mitigation measures, impose interim risk mitigation...

  20. 17 CFR 210.8-03 - Interim financial statements.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ...) Additional line items may be presented to facilitate the usefulness of the interim financial statements... cumulative financial information from inception. Instruction 1 to § 210.8-03: Where Article 8 is...

  1. Fuel Supply Shutdown Facility Interim Operational Safety Requirements

    SciTech Connect

    BENECKE, M.W.

    2000-09-06

    The Interim Operational Safety Requirements for the Fuel Supply Shutdown (FSS) Facility define acceptable conditions, safe boundaries, bases thereof, and management of administrative controls to ensure safe operation of the facility.

  2. TANK FARM INTERIM SURFACE BARRIER MATERIALS AND RUNOFF ALTERNATIVES STUDY

    SciTech Connect

    HOLM MJ

    2009-06-25

    This report identifies candidate materials and concepts for interim surface barriers in the single-shell tank farms. An analysis of these materials for application to the TY tank farm is also provided.

  3. Fire Hazards Analysis for the 200 Area Interim Storage Area

    SciTech Connect

    JOHNSON, D.M.

    2000-01-06

    This documents the Fire Hazards Analysis (FHA) for the 200 Area Interim Storage Area. The Interim Storage Cask, Rad-Vault, and NAC-1 Cask are analyzed for fire hazards and the 200 Area Interim Storage Area is assessed according to HNF-PRO-350 and the objectives of DOE Order 5480 7A. This FHA addresses the potential fire hazards associated with the Interim Storage Area (ISA) facility in accordance with the requirements of DOE Order 5480 7A. It is intended to assess the risk from fire to ensure there are no undue fire hazards to site personnel and the public and to ensure property damage potential from fire is within acceptable limits. This FHA will be in the form of a graded approach commensurate with the complexity of the structure or area and the associated fire hazards.

  4. 14 CFR 136.41 - Interim operating authority.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... lands; (7) Shall promote safe commercial air tour operations; (8) Shall promote the adoption of quiet technology, as appropriate, and (9) Shall allow for modifications of the interim operating authority based...

  5. Interim solar cell testing procedures for terrestrial applications

    NASA Technical Reports Server (NTRS)

    Brandhorst, H. W., Jr.; Hickey, J.; Curtis, H.

    1975-01-01

    This report presents an interim draft of procedures for testing solar cells for terrestrial applications that resulted from the terrestrial photovoltaic workshop sessions. A final version of the test procedures manual is planned for the summer of 1976.

  6. NCI Director Also to Be Interim FDA Commissioner

    Cancer.gov

    Andrew von Eschenbach, M.D., director of the NCI, was asked by President Bush on Friday, September 23, 2005, to assume the additional role of interim Commissioner of the U.S. Food and Drug Administration (FDA).

  7. St. Francis Rain Garden Water Quality Sampling Interim Data Report; Total Nitrogen, Total Phosphorus, Sediments or Solids, and E. Coli for the period April to June, 2014

    EPA Science Inventory

    This interim data reported is being provided per request to the Metropolitan Sewer District (MSD) to provide summary statistics on a limited set of water quality parameters as measured at the St. Francis Rain Garden site in the Lick Run Valley as it pertains to MSD's Project Grou...

  8. Effects of a Universally Free, In-Classroom School Breakfast Program: Results from the Second Year of the Maryland Meals for Achievement Evaluation. Interim Report.

    ERIC Educational Resources Information Center

    Murphy, J. Michael; Rankin, Emunah; Feeney, Kelly; Kenney, Leigh; Kleinman, Ron

    Noting that many children in the United States are not well nourished despite the recent economic boom, the state of Maryland began the Maryland Meals for Achievement (MMFA) program, a demonstration project to see if providing a classroom breakfast free to all students can improve student nutrition and academic achievement. This interim report…

  9. Wide-Field Infrared Survey Telescope (WFIRST) Interim Report

    NASA Technical Reports Server (NTRS)

    Green, J.; Schechter, P.; Baltay, C.; Bean, R.; Bennett, D.; Brown, R.; Conselice, C.; Donahue, M.; Gaudi, S.; Lauer, T.; Perlmutter, S.; Rauscher, B.; Rhodes, J.; Roellig, T.; Stern, D.; Sumi, T.; Gerhels, N.; Sambruna, R.; Barry, R. K.; Content, D.; Grady, K; Jackson, C.; Kruk, J.; Melton, M.; Rioux, N.

    2011-01-01

    measurements. The Infrared Astronomical Satellite (IRAS), the Cosmic Background Explorer (COBE), Herschel, Spitzer, and Wide-field Infrared Sur-vey Explorer (WISE) are all space missions that have produced stunning new scientific advances by going to space to observe in the infrared. This interim report describes progress as of June 2011 on developing a requirements flowdown and an evaluation of scientific performance. An Interim Design Reference Mission (IDRM) configuration is presented that is based on the specifications of NWNH with some refinements to optimize the design in accordance with the new scientific requirements. Analysis of this WFIRST IDRM concept is in progress to ensure the capability of the observatory is compatible with the science requirements. The SDT and Project will continue to refine the mission concept over the coming year as design, analysis and simulation work are completed, resulting in the SDT s WFIRST Design Reference Mission (DRM) by the end of 2012.

  10. TWRS HLW interim storage facility search and evaluation

    SciTech Connect

    Calmus, R.B., Westinghouse Hanford

    1996-05-16

    The purpose of this study was to identify and provide an evaluation of interim storage facilities and potential facility locations for the vitrified high-level waste (HLW) from the Phase I demonstration plant and Phase II production plant. In addition, interim storage facilities for solidified separated radionuclides (Cesium and Technetium) generated during pretreatment of Phase I Low-Level Waste Vitrification Plant feed was evaluated.

  11. K basins interim remedial action health and safety plan

    SciTech Connect

    DAY, P.T.

    1999-09-14

    The K Basins Interim Remedial Action Health and Safety Plan addresses the requirements of the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), as they apply to the CERCLA work that will take place at the K East and K West Basins. The provisions of this plan become effective on the date the US Environmental Protection Agency issues the Record of Decision for the K Basins Interim Remedial Action, currently planned in late August 1999.

  12. Interim Safety Basis for Fuel Supply Shutdown Facility

    SciTech Connect

    BENECKE, M.W.

    2000-09-07

    This ISB, in conjunction with the IOSR, provides the required basis for interim operation or restrictions on interim operations and administrative controls for the facility until a SAR is prepared in accordance with the new requirements or the facility is shut down. It is concluded that the risks associated with tha current and anticipated mode of the facility, uranium disposition, clean up, and transition activities required for permanent closure, are within risk guidelines.

  13. Retention, detention, and overland flow for pollutant removal from highway stormwater runoff: interim guidelines for management measures. Final report, September 1985-June 1987

    SciTech Connect

    Dorman, M.E.; Hartigan, H.; Johnson, F.; Maestri, B.

    1988-03-01

    This report provides interim guidelines for the design of management measures for the removal of pollutants from highway stormwater runoff. Three general types of management measures determined through previous FHWA studies to be effective in treating highway runoff: vegetative controls (overland flow and grassed channels); detention basins (wet detention basins and wetlands); and retention measures (retention basins, trenches and wells). These interim design guidelines were developed, based on experience of the project team and by a thorough review of available literature. Field and laboratory studies are currently underway to verify the design procedures and assumptions presented in the report.

  14. Projection of Stabilized Aerial Imagery Onto Digital Elevation Maps for Geo-Rectified and Jitter-Free Viewing

    NASA Technical Reports Server (NTRS)

    Ansar, Adnan I.; Brennan, Shane; Clouse, Daniel S.

    2012-01-01

    As imagery is collected from an airborne platform, an individual viewing the images wants to know from where on the Earth the images were collected. To do this, some information about the camera needs to be known, such as its position and orientation relative to the Earth. This can be provided by common inertial navigation systems (INS). Once the location of the camera is known, it is useful to project an image onto some representation of the Earth. Due to the non-smooth terrain of the Earth (mountains, valleys, etc.), this projection is highly non-linear. Thus, to ensure accurate projection, one needs to project onto a digital elevation map (DEM). This allows one to view the images overlaid onto a representation of the Earth. A code has been developed that takes an image, a model of the camera used to acquire that image, the pose of the camera during acquisition (as provided by an INS), and a DEM, and outputs an image that has been geo-rectified. The world coordinate of the bounds of the image are provided for viewing purposes. The code finds a mapping from points on the ground (DEM) to pixels in the image. By performing this process for all points on the ground, one can "paint" the ground with the image, effectively performing a projection of the image onto the ground. In order to make this process efficient, a method was developed for finding a region of interest (ROI) on the ground to where the image will project. This code is useful in any scenario involving an aerial imaging platform that moves and rotates over time. Many other applications are possible in processing aerial and satellite imagery.

  15. DEMONSTRATION OF THE DOE INTERIM ENERGY CONSERVATION STANDARDS FOR NEW FEDERAL RESIDENTIAL BUILDINGS: EXECUTIVE SUMMARY

    SciTech Connect

    Lee, A. D.; Baechler, M Di Massa, F. V.; Lucas, R. G.; Shankle, D. L.

    1992-01-01

    In accordance with federal legislation, the U.S. Department of Energy (DOE) bas conducted a project to demonstrate use of its Interim Energy Conservation Standards for New Federal Residential Buildings. The demonstration is the second step in a three-step process: development of interim standards, demonstration of the interim standards, and development of final standards. Pacific Northwest Laboratory (PNL) collected information from the demonstration project and prepared this report under a contract with DOE. The purpose of the standards is to improve the energy efficiency of federal housing and increase the use of nondepletable energy sources. In accordance with the legislation, the standards were to be performance-based rather than prescribing specific energy conservation measures. The standards use a computer software program called COSTSAFR which individualizes the standards based on climate, housing type, and fuel costs. The standards generate minimum energy-efficiency requirements by applying the life-cycle cost methodology developed for federal projects, For the demonstration, the DOE chose live federal agency housing projects: four military housing projects and one project for the Department of Health and Human Services. DOE and PNL worked with agency housing procurement officials and designers/architects to hypothetically apply the interim standards to each housing project. PNL conducted extensive interviews with the federal agencies and design contractors to determine what impacts the standards would have on the existing agency procurement process as well as on designers. Overall, PNL found that the interim standards met the basic intent of the law. Specific actions were identified, however, that DOE could take to improve the standards and encourage the agencies to implement them. Agency personnel and designers expressed similar concerns about the standards: the minimum efficiency levels established by the standards were lower than expected and the

  16. Projection of landfill stabilization period by time series analysis of leachate quality and transformation trends of VOCs.

    PubMed

    Sizirici, Banu; Tansel, Berrin

    2010-01-01

    The purpose of this study was to evaluate suitability of using the time series analysis for selected leachate quantity and quality parameters to forecast the duration of post closure period of a closed landfill. Selected leachate quality parameters (i.e., sodium, chloride, iron, bicarbonate, total dissolved solids (TDS), and ammonium as N) and volatile organic compounds (VOCs) (i.e., vinyl chloride, 1,4-dichlorobenzene, chlorobenzene, benzene, toluene, ethyl benzene, xylenes, total BTEX) were analyzed by the time series multiplicative decomposition model to estimate the projected levels of the parameters. These parameters were selected based on their detection levels and consistency of detection in leachate samples. In addition, VOCs detected in leachate and their chemical transformations were considered in view of the decomposition stage of the landfill. Projected leachate quality trends were analyzed and compared with the maximum contaminant level (MCL) for the respective parameters. Conditions that lead to specific trends (i.e., increasing, decreasing, or steady) and interactions of leachate quality parameters were evaluated. Decreasing trends were projected for leachate quantity, concentrations of sodium, chloride, TDS, ammonia as N, vinyl chloride, 1,4-dichlorobenzene, benzene, toluene, ethyl benzene, xylenes, and total BTEX. Increasing trends were projected for concentrations of iron, bicarbonate, and chlorobenzene. Anaerobic conditions in landfill provide favorable conditions for corrosion of iron resulting in higher concentrations over time. Bicarbonate formation as a byproduct of bacterial respiration during waste decomposition and the lime rock cap system of the landfill contribute to the increasing levels of bicarbonate in leachate. Chlorobenzene is produced during anaerobic biodegradation of 1,4-dichlorobenzene, hence, the increasing trend of chlorobenzene may be due to the declining trend of 1,4-dichlorobenzene. The time series multiplicative

  17. Interim Control Strategy for the Test Area North/Technical Support Facility Sewage Treatment Facility Disposal Pond - Two-year Update

    SciTech Connect

    L. V. Street

    2007-04-01

    The Idaho Cleanup Project has prepared this interim control strategy for the U.S. Department of Energy Idaho Operations Office pursuant to DOE Order 5400.5, Chapter 11.3e (1) to support continued discharges to the Test Area North/Technical Support Facility Sewage Treatment Facility Disposal Pond. In compliance with DOE Order 5400.5, a 2-year review of the Interim Control Strategy document has been completed. This submittal documents the required review of the April 2005 Interim Control Strategy. The Idaho Cleanup Project's recommendation is unchanged from the original recommendation. The Interim Control Strategy evaluates three alternatives: (1) re-route the discharge outlet to an uncontaminated area of the TSF-07; (2) construct a new discharge pond; or (3) no action based on justification for continued use. Evaluation of Alternatives 1 and 2 are based on the estimated cost and implementation timeframe weighed against either alternative's minimal increase in protection of workers, the public, and the environment. Evaluation of Alternative 3, continued use of the TSF-07 Disposal Pond under current effluent controls, is based on an analysis of four points: - Record of Decision controls will protect workers and the public - Risk of increased contamination is low - Discharge water will be eliminated in the foreseeable future - Risk of contamination spread is acceptable. The Idaho Cleanup Project recommends Alternative 3, no action other than continued implementation of existing controls and continued deactivation, decontamination, and dismantlement efforts at the Test Area North/Technical Support Facility.

  18. Minimal subspace rotation on the Stiefel manifold for stabilization and enhancement of projection-based reduced order models for the compressible Navier-Stokes equations

    NASA Astrophysics Data System (ADS)

    Balajewicz, Maciej; Tezaur, Irina; Dowell, Earl

    2016-09-01

    For a projection-based reduced order model (ROM) of a fluid flow to be stable and accurate, the dynamics of the truncated subspace must be taken into account. This paper proposes an approach for stabilizing and enhancing projection-based fluid ROMs in which truncated modes are accounted for a priori via a minimal rotation of the projection subspace. Attention is focused on the full non-linear compressible Navier-Stokes equations in specific volume form as a step toward a more general formulation for problems with generic non-linearities. Unlike traditional approaches, no empirical turbulence modeling terms are required, and consistency between the ROM and the Navier-Stokes equation from which the ROM is derived is maintained. Mathematically, the approach is formulated as a trace minimization problem on the Stiefel manifold. The reproductive as well as predictive capabilities of the method are evaluated on several compressible flow problems, including a problem involving laminar flow over an airfoil with a high angle of attack, and a channel-driven cavity flow problem.

  19. The halogen bond: an interim perspective.

    PubMed

    Legon, Anthony C

    2010-07-28

    There has been an upsurge of interest in the halogen bond during the last decade. This non-covalent interaction is less familiar than the hydrogen bond, but is similar to it in several respects. In this article, we first discuss the nature of the halogen bond in the gas phase, as established by systematic investigations of the rotational spectra of complexes B...XY, where B is a simple Lewis base and XY is a dihalogen molecule. The geometry of a given B...XY is found to be isomorphic with that of the corresponding hydrogen-bonded system B...HX, an observation that leads an interim definition of the halogen bond similar to that recently proposed for the hydrogen bond. Selected novel applications of the halogen bond made in the last decade in various areas of chemistry/materials (namely crystal engineering, liquid crystals, nano-materials, polymer chemistry and inorganic chemistry) are then reviewed. These applications generally involve molecules of the type XR (where R is an electron-withdrawing group) acting as the electron donor, rather than dihalogens XY.

  20. High Temperature Materials Interim Data Qualification Report FY 2011

    SciTech Connect

    Nancy Lybeck

    2011-08-01

    Projects for the very high temperature reactor (VHTR) Technology Development Office provide data in support of Nuclear Regulatory Commission licensing of the VHTR. Fuel and materials to be used in the reactor are tested and characterized to quantify performance in high temperature and high fluence environments. The VHTR program has established the Next Generation Nuclear Plant (NGNP) Data Management and Analysis System (NDMAS) to ensure that VHTR data are qualified for use, stored in a readily accessible electronic form, and analyzed to extract useful results. This document focuses on the first NDMAS objective. It describes the High Temperature Materials characterization data stream, the processing of these data within NDMAS, and reports the interim fiscal year (FY) 2011 qualification status of the data. Data qualification activities within NDMAS for specific types of data are determined by the data qualification category assigned by the data generator. The High Temperature Materials data are being collected under the Nuclear Quality Assurance (NQA)-1 guidelines and will be qualified data. For NQA-1 qualified data, the qualification activities include: (1) capture testing to confirm that the data stored within NDMAS are identical to the raw data supplied, (2) accuracy testing to confirm that the data are an accurate representation of the system or object being measured, and (3) documenting that the data were collected under an NQA-1 or equivalent Quality Assurance program. Currently, data from seven test series within the High Temperature Materials data stream have been entered into the NDMAS vault, including tensile tests, creep tests, and cyclic tests. Of the 5,603,682 records currently in the vault, 4,480,444 have been capture passed, and capture testing is in process for the remaining 1,123,238.

  1. Radioactive Air Emission Notice of Construction for (NOC) Plutonium Finishing Plant (PFP) Project W-460 Plutonium Stabilization and Handling

    SciTech Connect

    JANSKY, M.T.

    2000-03-01

    The following description and any attachments and references are provided to the Washington State Department of Health (WDOH), Division of Radiation Protection, Air Emissions & Defense Waste Section as a notice of construction (NOC) in accordance with Washington Administrative Code (WAC) 246-247, Radiation Protection-Air Emissions. The WAC 246-247-060, ''Applications, registration, and licensing'', states ''This section describes the information requirements for approval to construct, modify, and operate an emission unit. Any NOC requires the submittal of information listed in Appendix A,'' Appendix A (WAC 246-247-1 IO) lists the requirements that must be addressed. Additionally, the following description, attachments, and references are provided to the U.S. Environmental Protection Agency (EPA) as an NOC, in accordance with Title 40 Code of Federal Regulations (CFR), Part 61, ''National Emission Standards for Hazardous Air Pollutants.'' The information required for submittal to the EPA is specified in 40 CFR 61.07. The potential emissions from this activity are estimated to provide greater than 0.1 millirem year total effective dose equivalent (TEDE) to the hypothetical offsite maximally exposed individual (MEI) and commencement is needed within a short time. Therefore, this application also is intended to provide notification of the anticipated date of initial startup in accordance with the requirement listed in 40 CFR 61.09(a)(1), and it is requested that approval of this application also constitutes EPA acceptance of this initial startup notification. Written notification of the actual date of initial startup, in accordance with the requirement listed in 40 CFR 61.09(a)(2), will be provided later. This NOC covers the activities associated with the construction and operation activities involving stabilization and/or repackaging of plutonium in the 2736-ZB Building. An operations support trailer will be installed in the proximity of the 2736-ZB Building. A new

  2. Radioactive Air Emission Notice of Construction (NOC) for Plutonium Finishing Plant (PFP) Project W-460 Plutonium Stabilization and Handling

    SciTech Connect

    JANSKY, M.T.

    2000-05-01

    The following description and any attachments and references are provided to the Washington State Department of Health (WDOH), Division of Radiation Protection, Air Emissions & Defense Waste Section as a notice of construction (NOC) in accordance with Washington Administrative Code (WAC) 246-247, Radiation Protection-Air Emissions. The WAC 246-247-060, ''Applications, registration, and licensing'', states ''This section describes the information requirements for approval to construct, modify, and operate an emission unit. Any NOC requires the submittal of information listed in Appendix A.'' Additionally, the following description, attachments, and references are provided to the US Environmental Protection Agency (EPA) as an NOC, in accordance with Title 40 Code of Federal Regulations (CFR), Part 61, ''National Emission Standards for Hazardous Air Pollutants''. The information required for submittal to the EPA is specified in 40 CFR 61.07. The potential emissions from this activity are estimated to provide greater than 0.1 millirem year total effective dose equivalent (TEDE) to the hypothetical offsite maximally exposed individual (MEI) and commencement is needed within a short time. Therefore, this application also is intended to provide notification of the anticipated date of initial startup in accordance with the requirement listed in 40 CFR 61.09(a)(1), and it is requested that approval of this application also constitutes EPA acceptance of this initial startup notification. Written notification of the actual date of initial startup, in accordance with the requirement listed in 40 CFR 61.09(a)(2), will be provided later. This NOC covers the activities associated with the construction and operation activities involving stabilization and/or repackaging of plutonium in the 2736-ZB Building. A new exhaust stack will be built and operated at the 2736-ZB Building to handle the effluents associated with the operation of the stabilization and repackaging process

  3. Development of the chemical stabilization and solidification process for the treatment of radioactive raffinate sludges at the DOE Weldon Spring Site Remedial Action Project

    SciTech Connect

    Cole, P.M.; Kakaria, V. [Morrison Knudsen Corp., Boise, ID . Environmental Enger, J.

    1996-12-31

    Chemical Solidification and Stabilization (CSS) is the mixing of chemical reagents with waste to solidify and chemically stabilize the contaminated material. The resulting product is resistant to leaching of certain contaminants. CSS treatment using Class C fly ash and Portland cement was chosen as the most feasible method for treatment of the chemically and radioactively contaminated sludge (raffinate) contained in raffinate pits on the Weldon Spring Site Remedial Action Project (WSSRAP) located outside of St. Louis, Missouri. Due to the uniqueness of the material, substantial bench-scale testing was performed on the raffinate to better understand its properties. Similarly, due to mixed results in the application of CSS treatment to radioactive materials, a pilot-scale testing facility was built to verify bench testing results and to establish and quantify design parameters for the full-scale CSS production facility. This paper discusses the development of the pilot-scale testing facility, the testing plan, and the results of the testing activities. Particular attention has been given to the applicability of the CSS treatment method and to the value of pilot-scale testing.

  4. NEXT GENERATION MELTER OPTIONEERING STUDY - INTERIM REPORT

    SciTech Connect

    GRAY MF; CALMUS RB; RAMSEY G; LOMAX J; ALLEN H

    2010-10-19

    The next generation melter (NOM) development program includes a down selection process to aid in determining the recommended vitrification technology to implement into the WTP at the first melter change-out which is scheduled for 2025. This optioneering study presents a structured value engineering process to establish and assess evaluation criteria that will be incorporated into the down selection process. This process establishes an evaluation framework that will be used progressively throughout the NGM program, and as such this interim report will be updated on a regular basis. The workshop objectives were achieved. In particular: (1) Consensus was reached with stakeholders and technology providers represented at the workshop regarding the need for a decision making process and the application of the D{sub 2}0 process to NGM option evaluation. (2) A framework was established for applying the decision making process to technology development and evaluation between 2010 and 2013. (3) The criteria for the initial evaluation in 2011 were refined and agreed with stakeholders and technology providers. (4) The technology providers have the guidance required to produce data/information to support the next phase of the evaluation process. In some cases it may be necessary to reflect the data/information requirements and overall approach to the evaluation of technology options against specific criteria within updated Statements of Work for 2010-2011. Access to the WTP engineering data has been identified as being very important for option development and evaluation due to the interface issues for the NGM and surrounding plant. WRPS efforts are ongoing to establish precisely data that is required and how to resolve this Issue. It is intended to apply a similarly structured decision making process to the development and evaluation of LAW NGM options.

  5. Performance of concrete pavements containing recycled concrete aggregate. Interim report, October 1993-October 1996

    SciTech Connect

    Wade, M.J.; Cuttell, G.D.; Vandenbossche, J.M.; Yu, H.T.; Smith, K.D.

    1997-03-01

    This interim report documents the field performance of nine concrete pavement projects that incorporate recycled concrete aggregate (RCA) in the construction of the pavement. Multiple sections were evaluated on many of the nine projects, due to perceived differences in performance levels or variations in pavement design (such as the use of virgin aggregate or the inclusion of dowel bars). All told, a total of 17 sections (of which 12 contain RCA) were subjected to an extensive field testing program, consisting of pavement condition surveys, drainage surveys, falling weight deflectometer (FWD) testing, coring, and serviceability assessments. A minimum of eight cores were retrieved from each section for laboratory evaluation of compressive strength, split tensile strength, dynamic elastic modulus, static elastic modulus, and thermal coefficient of expansion, as well as for volumetric surface testing and petrographic analyses.

  6. WFIRST Project Science Activities

    NASA Technical Reports Server (NTRS)

    Gehrels, Neil

    2012-01-01

    The WFIRST Project is a joint effort between GSFC and JPL. The project scientists and engineers are working with the community Science Definition Team to define the requirements and initial design of the mission. The objective is to design an observatory that meets the WFIRST science goals of the Astr02010 Decadal Survey for minimum cost. This talk will be a report of recent project activities including requirements flowdown, detector array development, science simulations, mission costing and science outreach. Details of the interim mission design relevant to scientific capabilities will be presented.

  7. A review of proposed Glen Canyon Dam interim operating criteria

    SciTech Connect

    LaGory, K.; Hlohowskyj, I.; Tomasko, D.; Hayse, J.; Durham, L.

    1992-04-01

    Three sets of interim operating criteria for Glen Canyon Dam on the Colorado River have been proposed for the period of November 1991, to the completion of the record of decision for the Glen Canyon Dam environmental impact statement (about 1993). These criteria set specific limits on dam releases, including maximum and minimum flows, up-ramp and down-ramp rates, and maximum daily fluctuation. Under the proposed interim criteria, all of these parameters would be reduced relative to historical operating criteria to protect downstream natural resources, including sediment deposits, threatened and endangered fishes, trout, the aquatic food base, and riparian plant communities. The scientific bases of the three sets of proposed operating criteria are evaluated in the present report:(1) criteria proposed by the Research/Scientific Group, associated with the Glen Canyon Environmental Studies (GCES); (2) criteria proposed state and federal officials charged with managing downstream resources; and (3) test criteria imposed from July 1991, to November 1991. Data from Phase 1 of the GCES and other sources established that the targeted natural resources are affected by dam operations, but the specific interim criteria chosen were not supported by any existing studies. It is unlikely that irreversible changes to any of the resources would occur over the interim period if historical operating criteria remained in place. It is likely that adoption of any of the sets of proposed interim operating criteria would reduce the levels of sediment transport and erosion below Glen Canyon Dam; however, these interim criteria could result in some adverse effects, including the accumulation of debris at tributary mouths, a shift of new high-water-zone vegetation into more flood-prone areas, and further declines in vegetation in the old high water zone.

  8. 75 FR 35510 - License Renewal Interim Staff Guidance Process, Revision 2 Notice of Availability

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-06-22

    ... COMMISSION License Renewal Interim Staff Guidance Process, Revision 2 Notice of Availability AGENCY: Nuclear... license renewal interim staff guidance (LR-ISG) process. This revision is entitled, ``License Renewal Interim Staff Guidance Process, Revision 2'' (revised LR-ISG process). The LR-ISG process describes...

  9. 75 FR 63080 - Interim Final Rule for Reporting Pre-Enactment Swap Transactions

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-10-14

    ... COMMISSION 17 CFR Part 44 RIN 3038-AD24 Interim Final Rule for Reporting Pre-Enactment Swap Transactions AGENCY: Commodity Futures Trading Commission. ACTION: Interim final rule; request for public comment... an interim final rule to implement new statutory provisions introduced by Title VII of the...

  10. 78 FR 67442 - Congestion Mitigation and Air Quality Improvement Program Interim Guidance

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-11-12

    ... types of rail service in a January 16, 2002, Federal Register notice (67 FR 2278), and in a March 8... Federal Highway Administration Congestion Mitigation and Air Quality Improvement Program Interim Guidance... Mitigation and Air Quality Improvement (CMAQ) Program (Interim Guidance). The Interim Guidance revises...

  11. 10 CFR 431.401 - Petitions for waiver, and applications for interim waiver, of test procedure.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... Renewable Energy, U.S. Department of Energy. Each Application for Interim Waiver must reference the Petition... Renewable Energy. (e) Provisions specific to interim waivers—(1) Disposition of application. If... 10 Energy 3 2010-01-01 2010-01-01 false Petitions for waiver, and applications for interim...

  12. 10 CFR 430.27 - Petitions for waiver and applications for interim waiver.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... Conservation and Renewable Energy. (2) An Application for Interim Waiver shall be submitted in triplicate, with... Renewable Energy, U.S. Department of Energy. Each Application for Interim Waiver shall reference the... Renewable Energy will receive and consider timely written comments on the Application for Interim...

  13. 42 CFR 417.572 - Budget and enrollment forecast and interim reports.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... interim per capita rate of payment on the basis of the best available data and adjust payments on the basis of that rate until the required reports are submitted and a new interim per capita rate can be established; or (2) If there is not enough data on which to base an interim per capita rate, inform the HMO...

  14. 42 CFR 417.572 - Budget and enrollment forecast and interim reports.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... interim per capita rate of payment on the basis of the best available data and adjust payments on the basis of that rate until the required reports are submitted and a new interim per capita rate can be established; or (2) If there is not enough data on which to base an interim per capita rate, inform the HMO...

  15. 42 CFR 417.572 - Budget and enrollment forecast and interim reports.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... interim per capita rate of payment on the basis of the best available data and adjust payments on the basis of that rate until the required reports are submitted and a new interim per capita rate can be established; or (2) If there is not enough data on which to base an interim per capita rate, inform the HMO...

  16. 42 CFR 417.572 - Budget and enrollment forecast and interim reports.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... interim per capita rate of payment on the basis of the best available data and adjust payments on the basis of that rate until the required reports are submitted and a new interim per capita rate can be established; or (2) If there is not enough data on which to base an interim per capita rate, inform the HMO...

  17. 42 CFR 417.572 - Budget and enrollment forecast and interim reports.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... interim per capita rate of payment on the basis of the best available data and adjust payments on the basis of that rate until the required reports are submitted and a new interim per capita rate can be established; or (2) If there is not enough data on which to base an interim per capita rate, inform the HMO...

  18. The Challenge of Declining Enrolments. Critical Emerging Problems and Recommendations for Immediate Action. Interim Report No. 2. [La Baisse des Effectifs Scolaires. Problemes Critiques et Recommandations pour une Action Immediate. Rapport Preliminaire No. 2].

    ERIC Educational Resources Information Center

    Jackson, Robert W. B.

    This second interim report on declining enrollment in Ontario identifies the major implications of the several factors associated with declining enrollments and makes recommendations for immediate action to contribute to the stability of the system while preparing and initiating long-term policies. The first part of the report deals with…

  19. INTERIM BARRIER AT HANFORDS TY FARM TO PROTECT GROUNDWATER AT THE HANFORD SITE WASHINGTON USA

    SciTech Connect

    PARKER DL; HOLM MJ; HENDERSON JC; LOBER RW

    2011-01-13

    An innovative interim surface barrier was constructed as a demonstration project at the Hanford Site's TY Tank Farm. The purpose of the demonstration barrier is to stop rainwater and snowmelt from entering the soils within the tank farm and driving contamination from past leaks and spills toward the ground water. The interim barrier was constructed using a modified asphalt material with very low permeability developed by MatCon{reg_sign}. Approximately 2,400 cubic yards of fill material were added to the tank farm to create a sloped surface that will gravity drain precipitation to collection points where it will be routed through buried drain lines to an evapotranspiration basin adjacent to the farm. The evapotranspiration basin is a lined basin with a network of perforated drain lines covered with soil and planted with native grasses. The evapotranspiration concept was selected because it prevents the runoff from percolating into the soil column and also avoids potential monitoring and maintenance issues associated with standing water in a traditional evaporation pond. Because of issues associated with using standard excavation and earth moving equipment in the farm a number of alternate construction approaches were utilized to perform excavations and prepare the site for the modified asphalt.

  20. COMPLETION OF THE FIRST INTEGRATED SPENT NUCLEAR FUEL TRANSSHIPMENT/INTERIM STORAGE FACILITY IN NW RUSSIA

    SciTech Connect

    Dyer, R.S.; Barnes, E.; Snipes, R.L.; Hoeibraaten, S.; Gran, H.C.; Foshaug, E.; Godunov, V.

    2003-02-27

    Northwest and Far East Russia contain large quantities of unsecured spent nuclear fuel (SNF) from decommissioned submarines that potentially threaten the fragile environments of the surrounding Arctic and North Pacific regions. The majority of the SNF from the Russian Navy, including that from decommissioned nuclear submarines, is currently stored in on-shore and floating storage facilities. Some of the SNF is damaged and stored in an unstable condition. Existing Russian transport infrastructure and reprocessing facilities cannot meet the requirements for moving and reprocessing this amount of fuel. Additional interim storage capacity is required. Most of the existing storage facilities being used in Northwest Russia do not meet health and safety, and physical security requirements. The United States and Norway are currently providing assistance to the Russian Federation (RF) in developing systems for managing these wastes. If these wastes are not properly managed, they could release significant concentrations of radioactivity to these sensitive environments and could become serious global environmental and physical security issues. There are currently three closely-linked trilateral cooperative projects: development of a prototype dual-purpose transport and storage cask for SNF, a cask transshipment interim storage facility, and a fuel drying and cask de-watering system. The prototype cask has been fabricated, successfully tested, and certified. Serial production is now underway in Russia. In addition, the U.S. and Russia are working together to improve the management strategy for nuclear submarine reactor compartments after SNF removal.

  1. T Tank Farm Interim Surface Barrier Demonstration - Vadose Zone Monitoring FY08 Report

    SciTech Connect

    Zhang, Z. F.; Strickland, Christopher E.; Field, Jim G.; Parker, Danny L.

    2009-02-01

    DOE’s Office of River Protection constructed a temporary surface barrier over a portion of the T Tank Farm as part of the T Farm Interim Surface Barrier Demonstration Project. The surface barrier is designed to minimize the infiltration of precipitation into the contaminated soil zone created by the Tank T-106 leak and minimize movement of the contamination. As part of the demonstration effort, vadose zone moisture is being monitored to assess the effectiveness of the barrier at reducing soil moisture. A solar-powered system was installed to continuously monitor soil water conditions at four locations (i.e., instrument Nests A, B, C, and D) beneath the barrier and outside the barrier footprint as well as site meteorological conditions. Nest A is placed in the area outside the barrier footprint and serves as a control, providing subsurface conditions outside the influence of the surface barrier. Nest B provides subsurface measurements to assess surface-barrier edge effects. Nests C and D are used to assess changes in soil-moisture conditions beneath the interim surface barrier.

  2. Technology status in support of refined technical baseline for the Spent Nuclear Fuel project. Revision 1

    SciTech Connect

    Puigh, R.J.; Toffer, H.; Heard, F.J.; Irvin, J.J.; Cooper, T.D.

    1995-10-20

    The Spent Nuclear Fuel Project (SNFP) has undertaken technology acquisition activities focused on supporting the technical basis for the removal of the N Reactor fuel from the K Basins to an interim storage facility. The purpose of these technology acquisition activities has been to identify technology issues impacting design or safety approval, to establish the strategy for obtaining the necessary information through either existing project activities, or the assignment of new work. A set of specific path options has been identified for each major action proposed for placing the N Reactor fuel into a ``stabilized`` form for interim storage as part of this refined technical basis. This report summarizes the status of technology information acquisition as it relates to key decisions impacting the selection of specific path options. The following specific categories were chosen to characterize and partition the technology information status: hydride issues and ignition, corrosion, hydrogen generation, drying and conditioning, thermal performance, criticality and materials accountability, canister/fuel particulate behavior, and MCO integrity. This report represents a preliminary assessment of the technology information supporting the SNFP. As our understanding of the N Reactor fuel performance develops the technology information supporting the SNFP will be updated and documented in later revisions to this report. Revision 1 represents the incorporation of peer review comments into the original document. The substantive evolution in our understanding of the technical status for the SNFP (except section 3) since July 1995 have not been incorporated into this revision.

  3. 17 CFR 210.8-03 - Interim financial statements.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... date of such balance sheet and the comparable period of the preceding fiscal year. (a) Condensed format. Interim financial statements may be condensed as follows: (1) Balance sheets should include separate... not misleading. (2) Material subsequent events and contingencies. Disclosure must be provided...

  4. 17 CFR 210.8-03 - Interim financial statements.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... date of such balance sheet and the comparable period of the preceding fiscal year. (a) Condensed format. Interim financial statements may be condensed as follows: (1) Balance sheets should include separate... not misleading. (2) Material subsequent events and contingencies. Disclosure must be provided...

  5. 17 CFR 210.8-03 - Interim financial statements.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... date of such balance sheet and the comparable period of the preceding fiscal year. (a) Condensed format. Interim financial statements may be condensed as follows: (1) Balance sheets should include separate... not misleading. (2) Material subsequent events and contingencies. Disclosure must be provided...

  6. Building an Interim Assessment System: A Workbook for School Districts

    ERIC Educational Resources Information Center

    Crane, Eric W.

    2010-01-01

    As someone with a stake in a school district's systems, a person probably does not have all the answers around what is necessary to build an effective interim assessment system. Neither does this workbook. But it is intended to have the right questions. More precisely, this workbook contains the vision, infrastructure, and resource questions…

  7. Evaluation of hardness and wear resistance of interim restorative materials

    PubMed Central

    Savabi, Omid; Nejatidanesh, Farahnaz; Fathi, Mohamad Hossein; Navabi, Amir Arsalan; Savabi, Ghazal

    2013-01-01

    Background: The interim restorative materials should have certain mechanical properties to withstand in oral cavity. The aim of this study was to evaluate the hardness and wear resistance of interim restorative materials. Materials and Methods: Fifteen identical rectangular shape specimens with dimensions of 2 mm × 10 mm × 30 mm were made from 7 interim materials (TempSpan, Protemp 3 Garant, Revotek, Unifast LC, Tempron, Duralay, and Acropars). The Vickers hardness and abrasive wear of specimens were tested in dry conditions and after 1 week storage in artificial saliva. The depth of wear was measured using surface roughness inspection device. Data were subjected to Kruskal–Wallis and Mann–Whitney tests. The Pearson correlation coefficient was used to determine the relationship between hardness and wear (α =0.05). Results: TempSpan had the highest hardness. The wear resistance of TempSpan (in dry condition) and Revotek (after conditioning in artificial saliva) was significantly higher (P < 0.05). There was no statistically significant correlation between degree of wear and hardness of the materials (P = 0.281, r = −0.31). Conclusion: Hardness and wear resistance of interim resins are material related rather than category specified. PMID:23946734

  8. 78 FR 70244 - Electronic Interim Assistance Reimbursement Program

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-11-25

    ...: November 15, 2013. Carolyn W. Colvin, Acting Commissioner of Social Security. For the reasons set out in... From the Federal Register Online via the Government Publishing Office SOCIAL SECURITY ADMINISTRATION 20 CFR Part 416 RIN 0960-AH45 Electronic Interim Assistance Reimbursement Program AGENCY:...

  9. 49 CFR 106.35 - Interim final rule.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 49 Transportation 2 2010-10-01 2010-10-01 false Interim final rule. 106.35 Section 106.35 Transportation Other Regulations Relating to Transportation PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION HAZARDOUS MATERIALS AND OIL TRANSPORTATION RULEMAKING...

  10. 48 CFR 801.690-8 - Interim appointment provisions.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 48 Federal Acquisition Regulations System 5 2011-10-01 2011-10-01 false Interim appointment provisions. 801.690-8 Section 801.690-8 Federal Acquisition Regulations System DEPARTMENT OF VETERANS AFFAIRS GENERAL DEPARTMENT OF VETERANS AFFAIRS ACQUISITION REGULATION SYSTEM Career Development,...

  11. 48 CFR 301.603-3 - Interim appointments.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 4 2010-10-01 2010-10-01 false Interim appointments. 301.603-3 Section 301.603-3 Federal Acquisition Regulations System HEALTH AND HUMAN SERVICES GENERAL HHS ACQUISITION REGULATION SYSTEM Career Development, Contracting Authority, and Responsibilities...

  12. Study of the Voluntary Public School Choice Program. Interim Report

    ERIC Educational Resources Information Center

    Yin, Robert K.; Ahonen, Pirkko; Kim, Dawn

    2007-01-01

    The purpose of the Voluntary Public School Choice (VPSC) Program is to assist states and local school districts in the development of innovative strategies to expand options for students, and to encourage transfers of students from low-performing to higher-performing schools. This report presents interim findings from the National Evaluation of…

  13. President's Information Technology Advisory Committee Interim Report to the President.

    ERIC Educational Resources Information Center

    National Coordination Office for Information Technology Research and Development, Arlington, VA.

    This document is the Interim Report on future directions for Federal support of research and development in high performance computing, communications, information technology, and the Next Generation Internet. This report provides a more detailed explanation of the findings and recommendations summarized by the President's Information Technology…

  14. 40 CFR 270.70 - Qualifying for interim status.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... the facility subject to the requirement to have a RCRA permit shall have interim status and shall be... section 3010(a) of RCRA pertaining to notification of hazardous waste activity. (2) Complied with the...) Paragraph (a) of this section shall not apply to any facility which has been previously denied a RCRA...

  15. 40 CFR 270.70 - Qualifying for interim status.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... the facility subject to the requirement to have a RCRA permit shall have interim status and shall be... section 3010(a) of RCRA pertaining to notification of hazardous waste activity. (2) Complied with the...) Paragraph (a) of this section shall not apply to any facility which has been previously denied a RCRA...

  16. 40 CFR 270.70 - Qualifying for interim status.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... the facility subject to the requirement to have a RCRA permit shall have interim status and shall be... section 3010(a) of RCRA pertaining to notification of hazardous waste activity. (2) Complied with the...) Paragraph (a) of this section shall not apply to any facility which has been previously denied a RCRA...

  17. 40 CFR 270.70 - Qualifying for interim status.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... the facility subject to the requirement to have a RCRA permit shall have interim status and shall be... section 3010(a) of RCRA pertaining to notification of hazardous waste activity. (2) Complied with the...) Paragraph (a) of this section shall not apply to any facility which has been previously denied a RCRA...

  18. 40 CFR 270.70 - Qualifying for interim status.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... the facility subject to the requirement to have a RCRA permit shall have interim status and shall be... section 3010(a) of RCRA pertaining to notification of hazardous waste activity. (2) Complied with the...) Paragraph (a) of this section shall not apply to any facility which has been previously denied a RCRA...

  19. 40 CFR 270.73 - Termination of interim status.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... RCRA permit and which is granted interim status, twelve months after the date on which the facility...) Submits a part B application for a RCRA permit for such facility before the date 12 months after the date... 8, 1989, unless the owner or operator of the facility submits a part B application for a RCRA...

  20. Performance Criteria for the Luminous Environment. Interim Report.

    ERIC Educational Resources Information Center

    State Univ. Construction Fund, Albany, NY.

    This interim report informs the eventual user of the direction of the long-term program; specific criteria are not provided. Five current guidelines in lighting practice were disavowed as follows--(1) that low levels of illumination cause organic harm to the eyes, (2) that the footcandle is the best criterion for determining the proper…

  1. 40 CFR 270.73 - Termination of interim status.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... requirements. (e) For owners or operators of any land disposal unit that is granted authority to operate under... of each land disposal facility which has been granted interim status prior to November 8, 1984, on... or operators of each land disposal facility which is in existence on the effective date of...

  2. 20 CFR 416.1910 - Requirements for interim assistance agreement.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... effect between us and the State if we are to repay the State for interim assistance. The following... part on payment of benefits if the State cannot pay it to you (for example, you die or you move and the... State must agree to the length of time that the agreement will remain in effect. (e) State to...

  3. 49 CFR 37.193 - Interim service requirements.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... WITH DISABILITIES (ADA) Over-the-Road Buses (OTRBs) § 37.193 Interim service requirements. Link to an... disability wishes to travel is already provided by an accessible bus, the operator has met this requirement... accessible buses (e.g., a small fixed-route operator who exclusively or primarily purchases or leases...

  4. 49 CFR 37.193 - Interim service requirements.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... WITH DISABILITIES (ADA) Over-the-Road Buses (OTRBs) § 37.193 Interim service requirements. (a) Until... accessible bus, the operator has met this requirement. (2) Before a date one year from the date on which this... fleet 100 percent of which consists of accessible buses (e.g., a small fixed-route operator...

  5. 45 CFR 689.8 - Interim administrative actions.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ....8 Public Welfare Regulations Relating to Public Welfare (Continued) NATIONAL SCIENCE FOUNDATION RESEARCH MISCONDUCT § 689.8 Interim administrative actions. (a) After an inquiry or during an external or... taken to protect Federal resources or to guard against continuation of any suspected or alleged...

  6. 45 CFR 689.8 - Interim administrative actions.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ....8 Public Welfare Regulations Relating to Public Welfare (Continued) NATIONAL SCIENCE FOUNDATION RESEARCH MISCONDUCT § 689.8 Interim administrative actions. (a) After an inquiry or during an external or... taken to protect Federal resources or to guard against continuation of any suspected or alleged...

  7. California School-to-Career Evaluation Study Interim Report.

    ERIC Educational Resources Information Center

    MPR Associates, Berkeley, CA.

    California's school-to-career (STC) efforts were examined in a statewide evaluation study that was initiated in December 2000 and scheduled for completion by June 2002. The study's first phase was assessed in an interim report that focused on the following major activities: (1) development of a white paper describing the STC's national and state…

  8. 16 CFR 1203.53 - Interim safety standards.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... Federal Register in accordance with 5 U.S.C. 552(a) and 1 CFR part 51. Copies of the standards may be... SAFETY STANDARD FOR BICYCLE HELMETS Requirements For Bicycle Helmets Manufactured From March 17, 1995, Through March 10, 1999 § 1203.53 Interim safety standards. (a) Bicycle helmets must comply with one...

  9. The Bigger Picture: Institutional Perspectives on Interim Assessment Technologies

    ERIC Educational Resources Information Center

    Burch, Patricia

    2010-01-01

    Drawing on a study of new forms of educational privatization, this article examines how ideas from institutional theory can be useful in analyzing the complex dynamics behind interim assessment technologies. The study was based on qualitative research methods and included interviews, a small-scale questionnaire, participant observation, and…

  10. Interim Evaluation of the National Literacy Program. Final Report

    ERIC Educational Resources Information Center

    Human Resources and Social Development Canada, 2007

    2007-01-01

    The evaluation examined issues related to: (1) Rationale and Relevance; (2) Implementation; and (3) Success. In addition, the interim evaluation was intended to: (1) Determine whether sufficient data was being collected to inform the summative evaluation and identify opportunities for improvement to fill any potential gaps; (2) Assess whether the…

  11. Department of Defnese. U.S. Metric Study Interim Report.

    ERIC Educational Resources Information Center

    National Bureau of Standards (DOC), Washington, DC.

    This is the ninth in a series of interim reports to the Congress concerning the impact of the increasing worldwide use of the metric system and to determine the advantages and disadvantages of its adoption in the United States. This report contains the Department of Defense estimates of its costs in a coordinated national changeover to the metric…

  12. Marine Biochemistry: A New Interdisciplinary Course for the Interim

    ERIC Educational Resources Information Center

    Goldberg, Arthur S.

    1976-01-01

    Discusses an undergraduate course which includes lectures, laboratory, and field trips and is designed for the interim winter semester. The course is interdisciplinary, involving a study of the biochemistry, pharmacology, and physiological significance of compounds from marine flora and fauna. (MLH)

  13. 17 CFR 210.10-01 - Interim financial statements.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... ADVISERS ACT OF 1940, AND ENERGY POLICY AND CONSERVATION ACT OF 1975 Interim Financial Statements § 210.10... financial statements, such as a statement of significant accounting policies and practices, details of... dividends declared per share applicable to common stock. The basis of the earnings per share...

  14. Penalty Inflation Adjustments for Civil Money Penalties. Interim Final Rule.

    PubMed

    2016-06-27

    In accordance with the Federal Civil Penalties Inflation Adjustment Act of 1990, as amended by the Debt Collection Improvement Act of 1996, and further amended by the Bipartisan Budget Act of 2015, section 701: Federal Civil Penalties Inflation Adjustment Act Improvements Act of 2015, this interim final rule incorporates the penalty inflation adjustments for the civil money penalties contained in the Social Security Act

  15. Ocotillo: Improving Learning through Instruction. Interim Report, 1988-89.

    ERIC Educational Resources Information Center

    Jacobs, Alan, Ed.; Walters, Jim, Ed.

    As a result of a Technology Retreat sponsored by the Maricopa Community Colleges (Arizona) in 1988, action/research groups were formed to explore the various challenges of implementing instructional technology effectively. This interim report reviews the work of the groups, with a summary report from each, as follows: (1) "Alternative Funding…

  16. Interim Sanitary Landfill Groundwater Monitoring Report (1998 Annual Report)

    SciTech Connect

    Wells, D.

    1999-03-18

    The SRS Interim Sanitary Landfill opened in Mid-1992 and operated until 1998 under Domestic Waste Permit No. 025500-1120. Several contaminants have been detected in the groundwater beneath the unit.The well sampling and analyses were conducted in accordance with Procedure 3Q5, Hydrogeologic Data Collection.

  17. System Specification for Immobilized High-Level Waste Interim Storage

    SciTech Connect

    CALMUS, R.B.

    2000-12-27

    This specification establishes the system-level functional, performance, design, interface, and test requirements for Phase 1 of the IHLW Interim Storage System, located at the Hanford Site in Washington State. The IHLW canisters will be produced at the Hanford Site by a Selected DOE contractor. Subsequent to storage the canisters will be shipped to a federal geologic repository.

  18. 50 CFR 259.30 - Application for Interim Capital Construction Fund Agreement (“Interim CCF Agreement”).

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... Construction Fund Agreement (âInterim CCF Agreementâ). 259.30 Section 259.30 Wildlife and Fisheries NATIONAL MARINE FISHERIES SERVICE, NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION, DEPARTMENT OF COMMERCE AID TO... for hire must be inspected and certified (under 46 CFR part 176) by the U.S. Coast Guard as...

  19. Postconstruction report for the mercury tanks interim action at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    SciTech Connect

    Voskuil, T.L.

    1993-09-01

    Three underground concrete settling tanks (tanks 2101-U, 2104-U, and 2100-U) at the Y-12 Plant on the Oak Ridge Reservation in Oak Ridge, Tennessee, contained contaminated sludges contributing mercury to the Upper East Fork Poplar Creek (UEFPC). These tanks were cleaned out as an interim action under the Comprehensive Environmental Response, Compensation, and Liability Act as part of the Reduction of Mercury in Plant Effluent subproject. Cleaning out these tanks prevented the sludge that had settled in the bottom from resuspending and carrying mercury into UEFPC. Tanks 2104-U and 2100-U were returned to service and will continue to receive effluent from buildings 9201-4 and 9201-5. Tank 2101-U had been abandoned and its effluent redirected to Tank 2100-U during previous activities. This interim action permanently sealed Tank 2101-U from the storm sewer system. Upon removal of materials and completion of cleanup, inspections determined that the project`s cleanup criteria had been met. The structural integrity of the tanks was also inspected, and minor cracks identified in tanks 2101-U and 2104-U were repaired. This project is considered to have been completed successfully because it met its performance objectives as addressed in the Interim Record of Decision and the work plan: to remove the waste from the three storage tanks; to ensure that the tanks were cleaned to the levels specified; to return tanks 2100-U and 2104-U to service; to isolate Tank 2101-U permanently; and to manage the wastes in an appropriate fashion.

  20. Early Childhood Creative Library. Interim Report.

    ERIC Educational Resources Information Center

    East, Barbara

    To assist the early development of children in a poorly educated, rural four-county area of North Carolina, the Early Childhood Library Project trained parents and babysitters to teach preschool children by using educational games and materials supplied by the library. Equipment was purchased and made available to the community, story hours were…

  1. Energy conservation potential of the US Department of Energy interim commercial building standards

    SciTech Connect

    Hadley, D.L.; Halverson, M.A.

    1993-12-01

    This report describes a project conducted to demonstrate the whole-building energy conservation potential achievable from full implementation of the US Department of Energy (DOE) Interim Energy Conservation Performance Standards for New Commercial and Multi-Family High Rise Residential Buildings. DOE`s development and implementation of energy performance standards for commercial buildings were established by the Energy Conservation Standards for New Buildings Act of 1976, as amended, Public Law (PL) 94-385, 42 USC 6831 et seq., hereinafter referred to as the Act. In accordance with the Act, DOE was to establish performance standards for both federal and private sector buildings ``to achieve the maximum practicable improvements in energy efficiency and use of non-depletable resources for all new buildings``.

  2. Mobile Launch Platform Vehicle Assembly Area (SWMU 056) Biosparge Expansion Interim Measures Work Plan

    NASA Technical Reports Server (NTRS)

    Burcham, Michael S.; Daprato, Rebecca C.

    2016-01-01

    This document presents the design details for an Interim Measure (IM) Work Plan (IMWP) for the Mobile Launch Platform/Vehicle Assembly Building (MLPV) Area, located at the John F. Kennedy Space Center (KSC), Florida. The MLPV Area has been designated Solid Waste Management Unit Number 056 (SWMU 056) under KSC's Resource Conservation and Recovery Act (RCRA) Corrective Action Program. This report was prepared by Geosyntec Consultants (Geosyntec) for the National Aeronautics and Space Administration (NASA) under contract number NNK09CA02B and NNK12CA13B, project control number ENV1642. The Advanced Data Package (ADP) presentation covering the elements of this IMWP report received KSC Remediation Team (KSCRT) approval at the December 2015 Team Meeting; the meeting minutes are included in Appendix A.

  3. Interim report on updated microarray probes for the LLNL Burkholderia pseudomallei SNP array

    SciTech Connect

    Gardner, S; Jaing, C

    2012-03-27

    The overall goal of this project is to forensically characterize 100 unknown Burkholderia isolates in the US-Australia collaboration. We will identify genome-wide single nucleotide polymorphisms (SNPs) from B. pseudomallei and near neighbor species including B. mallei, B. thailandensis and B. oklahomensis. We will design microarray probes to detect these SNP markers and analyze 100 Burkholderia genomic DNAs extracted from environmental, clinical and near neighbor isolates from Australian collaborators on the Burkholderia SNP microarray. We will analyze the microarray genotyping results to characterize the genetic diversity of these new isolates and triage the samples for whole genome sequencing. In this interim report, we described the SNP analysis and the microarray probe design for the Burkholderia SNP microarray.

  4. USING POLYMERIC HYDROGEN GETTERS TO PREVENT COMBUSTIBLE ATMOSPHERES DURING INTERIM SAFE STORAGE OF PLUTONIUM OXIDE

    SciTech Connect

    Woodsmall, T

    2007-05-24

    Nuclear Materials Management (NMM) of WSRC has recently installed the capability to perform both non-destructive and destructive examination of 3013 containers of Pu oxide in accordance with DOE-STD-3013. The containers will be opened and the oxide will be sampled for analysis. The remaining bulk oxide must then be safely stored in a non-3013-compliant configuration. Available processing equipment and controls cannot prevent the oxide from adsorbing moisture during this process. Subsequent radiolysis of moisture during storage may generate combustible quantities of gases while waiting final processing, and satisfying DOE Interim Safe Storage Criteria (ISSC) would require that storage containers be vented at impractical frequencies. With support from an independent National Laboratory, WSRC/NMM has demonstrated that a commercial hydrogen getter material will effectively prevent the accumulation of combustible gas concentrations. A project overview, including storage requirements and strategies, as well as getter technology, current test results, and anticipated future developments will be addressed.

  5. Opening a new era in space. [Space Transportation System utilizing Shuttle, Spacelab and Interim Upper Stage

    NASA Technical Reports Server (NTRS)

    Culbertson, P. E.; Bold, T. P.

    1977-01-01

    The overall payload planning aimed at initial projected use of the Space Transportation System (STS) which will establish a new capability for exploring and using space through operations of the Shuttle, Spacelab, and Interim Upper Stage (IUS) in the Eighties is reviewed, and the significance of this planning for science and technology is discussed. The first payloads will fly on the STS during Orbital Flight Tests (OFT) beginning in March 1979. Primary OFT objectives include verifying flight systems and the Shuttle's ability to accomodate various types of payloads in different mission modes. The STS schedule will build up to as many as 60 flights in 1984. The STS payloads will make contributions to the management on a global scale of the interrelationship of production, consumption, population growth, and pollution.

  6. Interim radiological safety standards and evaluation procedures for subseabed high-level waste disposal

    SciTech Connect

    Klett, R.D.

    1997-06-01

    The Seabed Disposal Project (SDP) was evaluating the technical feasibility of high-level nuclear waste disposal in deep ocean sediments. Working standards were needed for risk assessments, evaluation of alternative designs, sensitivity studies, and conceptual design guidelines. This report completes a three part program to develop radiological standards for the feasibility phase of the SDP. The characteristics of subseabed disposal and how they affect the selection of standards are discussed. General radiological protection standards are reviewed, along with some new methods, and a systematic approach to developing standards is presented. The selected interim radiological standards for the SDP and the reasons for their selection are given. These standards have no legal or regulatory status and will be replaced or modified by regulatory agencies if subseabed disposal is implemented. 56 refs., 29 figs., 15 tabs.

  7. Interim report on the meteorological database

    SciTech Connect

    Stage, S.A.; Ramsdell, J.V.; Simonen, C.A.; Burk, K.W.

    1993-01-01

    The Hanford Environmental Dose Reconstruction (HEDR) Project is estimating radiation doses that individuals may have received from operations at Hanford from 1944 to the present. An independent Technical Steering Panel (TSP) directs the project, which is being conducted by the Battelle, Pacific Northwest Laboratories in Richland, Washington. The goals of HEDR, as approved by the TSP, include dose estimates and determination of confidence ranges for these estimates. This letter report describes the current status of the meteorological database. The report defines the meteorological data available for use in climate model calculations, describes the data collection procedures and the preparation and control of the meteorological database. This report also provides an initial assessment of the data quality. The available meteorological data are adequate for atmospheric calculations. Initial checks of the data indicate the data entry accuracy meets the data quality objectives.

  8. DEMONSTRATION OF THE DOE INTERIM ENERGY CONSERVATION STANDARDS FOR NEW FEDERAL RESIDENTIAL BUILDINGS

    SciTech Connect

    Lee, A. D.; Baechler, H. C.; Di Massa, F. V.; Lucas, R. G.; Shankle, D. L.

    1992-01-01

    In accordance with federal legislation, the U.S. Department of Energy (DOE) has sponsored a study to demonstrate use of its Interim Energy Conservation Standards for New Federal Residential Buildings. The demonstration study was conducted by DOE and the Pacific Northwest Laboratory (PNL). The demonstration is the second step in a three-step process: I) development of interim standards, 2) demonstration of the interim standards, and 3) development of final standards. The standards are mandatory for federal agency housing procurements. Nevertheless, PNL found at the start of the demonstration that agency use of the interim standards had been minimal. The purpose of the standards is to improve the energy efficiency of federal housing and increase the use of nondepletable energy sources. In accordance with the legislation, the standards were to be performance-based rather than prescribing specific energy conservation measures. To fulfill this aspect of the legislation, the standards use a computer software program called COSTSAFR which generates a point system that individualizes the standards to specific projects based on climate, housing type, and fuel costs. The standards generate minimum energy-efficiency requirements by applying the life-cycle cost methodology developed for federal projects. For the demonstration, PNL and DOE chose five federal agency housing projects which had been built in diverse geographic and climate regions. Participating agencies were the Air Force, the Army (which provided two case studies), the Navy, and the Department of Health and Human Services. PNL worked with agency housing procurement officials and designers/architects to hypothetically apply the interim standards to the procurement and design of each housing project. The demonstration started at the point in the project where agencies would establish their energyefficiency requirements for the project and followed the procurement process through the designers' use of the point

  9. Cascade Distiller System Performance Testing Interim Results

    NASA Technical Reports Server (NTRS)

    Callahan, Michael R.; Pensinger, Stuart; Sargusingh, Miriam J.

    2014-01-01

    The Cascade Distillation System (CDS) is a rotary distillation system with potential for greater reliability and lower energy costs than existing distillation systems. Based upon the results of the 2009 distillation comparison test (DCT) and recommendations of the expert panel, the Advanced Exploration Systems (AES) Water Recovery Project (WRP) project advanced the technology by increasing reliability of the system through redesign of bearing assemblies and improved rotor dynamics. In addition, the project improved the CDS power efficiency by optimizing the thermoelectric heat pump (TeHP) and heat exchanger design. Testing at the NASA-JSC Advanced Exploration System Water Laboratory (AES Water Lab) using a prototype Cascade Distillation Subsystem (CDS) wastewater processor (Honeywell d International, Torrance, Calif.) with test support equipment and control system developed by Johnson Space Center was performed to evaluate performance of the system with the upgrades as compared to previous system performance. The system was challenged with Solution 1 from the NASA Exploration Life Support (ELS) distillation comparison testing performed in 2009. Solution 1 consisted of a mixed stream containing human-generated urine and humidity condensate. A secondary objective of this testing is to evaluate the performance of the CDS as compared to the state of the art Distillation Assembly (DA) used in the ISS Urine Processor Assembly (UPA). This was done by challenging the system with ISS analog waste streams. This paper details the results of the AES WRP CDS performance testing.

  10. New Hampshire Better Buildings - Final Interim Report

    SciTech Connect

    Cramton, Karen; Peters, Katherine

    2014-02-20

    With $10 million in funding from the U.S. Department of Energy's (DOE) Better Buildings Neighborhood Program, the NH Better Buildings program was established as an initiative that initially empowered the three “Beacon Communities” of Berlin, Nashua and Plymouth to achieve transformative energy savings and reductions in fossil fuel use and greenhouse gases through deep energy retrofits and complementary sustainable energy solutions. The program also enabled those Communities to provide leadership to other communities around the state as “beacons” of energy efficiency. The goal of the program was to reduce energy use by a minimum of 15% through energy efficiency upgrades in residential and commercial buildings in the communities. The program expanded statewide in April 2012 by issuing a competitive solicitation for additional commercial projects non-profit, and municipal energy efficiency projects from any community in the state, and a partnership with the state’s utility-run, ratepayer-funded residential Home Performance with ENERGY STAR® (HPwES) program. The NH Better Buildings program was administered by the New Hampshire Office of Energy and Planning (OEP) and managed by the NH Community Development Finance Authority (CDFA). The program started in July 2010 and the last projects funded with American Reinvestment and Recovery Act (ARRA) funds were completed in August 2013. The program will continue after the American Recovery and Reinvestment Act program period as a Revolving Loan Fund, enabling low-interest financing for deep energy retrofits into the future.

  11. ADVANTAGES, DISADVANTAGES, AND LESSONS LEARNED FROM MULTI-REACTOR DECOMMISSIONING PROJECTS

    SciTech Connect

    Morton, M.R.; Nielson, R.R.; Trevino, R.A.

    2003-02-27

    This paper discusses the Reactor Interim Safe Storage (ISS) Project within the decommissioning projects at the Hanford Site and reviews the lessons learned from performing four large reactor decommissioning projects sequentially. The advantages and disadvantages of this multi-reactor decommissioning project are highlighted.

  12. Learning Demonstration Interim Progress Report -- July 2010

    SciTech Connect

    Wipke, K.; Spirk, S.; Kurtz, J.; Ramsden, T.

    2010-09-01

    This report discusses key results based on data through December 2009 from the U.S. Department of Energy's (DOE) Controlled Hydrogen Fleet and Infrastructure Validation and Demonstration Project, also referred to as the National Fuel Cell Electric Vehicle (FCEV) Learning Demonstration. The report serves to help transfer knowledge and lessons learned within various parts of DOE's hydrogen program, as well as externally to other stakeholders. It is the fourth such report in a series, with previous reports being published in July 2007, November 2007, and April 2008.

  13. Penalty Inflation Adjustments for Civil Money Penalties. Interim Final Rule.

    PubMed

    2016-06-27

    In accordance with the Federal Civil Penalties Inflation Adjustment Act of 1990, as amended by the Debt Collection Improvement Act of 1996, and further amended by the Bipartisan Budget Act of 2015, section 701: Federal Civil Penalties Inflation Adjustment Act Improvements Act of 2015, this interim final rule incorporates the penalty inflation adjustments for the civil money penalties contained in the Social Security Act PMID:27373014

  14. Method of preparing nuclear wastes for tansportation and interim storage

    DOEpatents

    Bandyopadhyay, Gautam; Galvin, Thomas M.

    1984-01-01

    Nuclear waste is formed into a substantially water-insoluble solid for temporary storage and transportation by mixing the calcined waste with at least 10 weight percent powdered anhydrous sodium silicate to form a mixture and subjecting the mixture to a high humidity environment for a period of time sufficient to form cementitious bonds by chemical reaction. The method is suitable for preparing an interim waste form from dried high level radioactive wastes.

  15. Interim Sanitary Landfill Groundwater Monitoring Report. 1997 Annual Report

    SciTech Connect

    1998-01-01

    Eight wells of the LFW series monitor groundwater quality in the Steed Pond Aquifer (Water Table) beneath the Interim Sanitary Landfill at the Savannah River Site (SRS). These wells are sampled semiannually to comply with the South Carolina Department of Health and Environmental Control Modified Municipal Solid Waste Permit 025500-1120 (formerly dWP-087A) and as part of the SRS Groundwater Monitoring Program.

  16. Terrestrial gravity data analysis for interim gravity model improvement

    NASA Technical Reports Server (NTRS)

    1987-01-01

    This is the first status report for the Interim Gravity Model research effort that was started on June 30, 1986. The basic theme of this study is to develop appropriate models and adjustment procedures for estimating potential coefficients from terrestrial gravity data. The plan is to use the latest gravity data sets to produce coefficient estimates as well as to provide normal equations to NASA for use in the TOPEX/POSEIDON gravity field modeling program.

  17. Spent Nuclear Fuel (SNF) Project Execution Plan

    SciTech Connect

    LEROY, P.G.

    2000-11-03

    The Spent Nuclear Fuel (SNF) Project supports the Hanford Site Mission to cleanup the Site by providing safe, economic, environmentally sound management of Site spent nuclear fuel in a manner that reduces hazards by staging it to interim onsite storage and deactivates the 100 K Area facilities.

  18. A one-sided interim analysis with binary outcomes.

    PubMed

    Bristol, D R

    1988-09-01

    Wieand and Therneau (Controlled Clin Trials 8:20-28, 1987) proposed a technique for conducting a clinical trial to test the equality of response rates for two treatments using a one-sided test with an option of terminating the trial at the single interim analysis if it appears that the test treatment will offer no improvement over the control treatment. Chi, Bristol, and Castellana (Stat Med 5:387-392, 1986) considered a clinical trial with the same option when the treatments are compared with respect to the means of variables with normal distributions with a common known variance. Here a decision rule similar to the one proposed in the latter is employed for the problem examined in the former. This decision rule, a generalization of the one proposed by Wieand and Therneau, consists of a one-sided test at the final analysis with a one-sided test at the interim analysis, which is performed in the direction opposite to the one at the final analysis. It is shown that the proposed generalization may result in desirable properties regarding the probability of stopping the trial at the interim analysis in some situations.

  19. Smallpox Vaccine Injury Compensation Program: administrative implementation. Interim final rule.

    PubMed

    2003-12-16

    The Smallpox Emergency Personnel Protection Act of 2003 (SEPPA), authorizes the Secretary of Health and Human Services (the Secretary), to establish the Smallpox Vaccine Injury Compensation Program ("the Program"). This program is designed to provide benefits and/or compensation to certain persons harmed as a direct result of receiving smallpox covered countermeasures, including the smallpox vaccine, or as a direct result of contracting vaccinia through certain accidental exposures. In addition, the Secretary may provide death benefits to certain survivors of individuals who died as the direct result of these injuries. On August 27, 2003, the Secretary published an interim final rule that set out a Smallpox (Vaccinia) Vaccine Injury Table ("the Table"). The table includes adverse effects (including injuries, disabilities, conditions, and deaths) within specific time periods that shall be presumed to result from the receipt of, or exposure to, the smallpox vaccine. The Secretary will use this table, as well as the procedures set out in this regulation, in deciding whether persons are eligible to receive benefits under the program. In this interim final rule, the Secretary is setting out the administrative policies, procedures, and requirements governing the program, as authorized by the SEPPA. The Secretary is seeking public comment on this interim final rule.

  20. Interim Storage of Plutonium in Existing Facilities

    SciTech Connect

    Woodsmall, T.D.

    1999-05-10

    'In this era of nuclear weapons disarmament and nonproliferation treaties, among many problems being faced by the Department of Energy is the safe disposal of plutonium. There is a large stockpile of plutonium at the Rocky Flats Environmental Technology Center and it remains politically and environmentally strategic to relocate the inventory closer to a processing facility. Savannah River Site has been chosen as the final storage location, and the Actinide Packaging and Storage Facility (APSF) is currently under construction for this purpose. With the ability of APSF to receive Rocky Flats material an estimated ten years away, DOE has decided to use the existing reactor building in K-Area of SRS as temporary storage to accelerate the removal of plutonium from Rocky Flats. There are enormous cost savings to the government that serve as incentive to start this removal as soon as possible, and the KAMS project is scheduled to receive the first shipment of plutonium in January 2000. The reactor building in K-Area was chosen for its hardened structure and upgraded seismic qualification, both resulting from an effort to restart the reactor in 1991. The KAMS project has faced unique challenges from Authorization Basis and Safety Analysis perspectives. Although modifying a reactor building from a production facility to a storage shelter is not technically difficult, the nature of plutonium has caused design and safety analysis engineers to make certain that the design of systems, structures and components included will protect the public, SRS workers, and the environment. A basic overview of the KAMS project follows. Plutonium will be measured and loaded into DOT Type-B shipping packages at Rocky Flats. The packages are 35-gallon stainless steel drums with multiple internal containment boundaries. DOE transportation vehicles will be used to ship the drums to the KAMS facility at SRS. They will then be unloaded, stacked and stored in specific locations throughout the

  1. Immobilized high-level waste interim storage alternatives generation and analysis and decision report

    SciTech Connect

    CALMUS, R.B.

    1999-05-18

    This report presents a study of alternative system architectures to provide onsite interim storage for the immobilized high-level waste produced by the Tank Waste Remediation System (TWRS) privatization vendor. It examines the contract and program changes that have occurred and evaluates their impacts on the baseline immobilized high-level waste (IHLW) interim storage strategy. In addition, this report documents the recommended initial interim storage architecture and implementation path forward.

  2. Countermeasures Injury Compensation Program (CICP): administrative implementation, interim final rule. Interim final rule with request for comments.

    PubMed

    2010-10-15

    The Public Readiness and Emergency Preparedness Act (PREP Act) authorizes the Secretary of Health and Human Services (the Secretary) to establish the Countermeasures Injury Compensation Program (CICP or Program). The Department of Health and Human Services (HHS) is issuing this interim final rule with request for comments in order to establish administrative policies, procedures, and requirements for the CICP. This Program is designed to provide benefits to certain persons who sustain serious physical injuries or death as a direct result of administration or use of covered countermeasures identified by the Secretary in declarations issued under the PREP Act. In addition, the Secretary may provide death benefits to certain survivors of individuals who died as the direct result of such covered injuries or their health complications. The Secretary is seeking public comments on this interim final rule. PMID:20960976

  3. LDEF materials: An overview of the interim findings

    NASA Technical Reports Server (NTRS)

    Stein, Bland A.

    1992-01-01

    The flight and retrieval of the National Aeronautics and Space Administration's Long Duration Exposure Facility (LDEF) provided an opportunity for the study of the low-Earth orbit (LEO) environment and long-duration space environmental effect (SEE) on materials that are unparalleled in the history of the U.S. space program. The 5.8-year flight of LDEF greatly enhanced the potential value of materials data from LDEF to the international SEE community, compared to that of the original 1-year flight plan. The remarkable flight attitude stability of LDEF enables specific analyses of various individual and combined effects of LEO environmental parameters on identical materials of the same space vehicle. NASA recognized the potential by forming the LDEF Space Environmental Effects on Materials Special Investigation Group (MSIG) to address the greatly expanded materials and LEO space environment parameter analysis opportunities available in the LDEF structure, experiment trays, and corollary measurements, so that the combined value of all LDEF materials data to current and future space missions will be assessed and documented. This paper provides an overview of the interim LDEF materials findings of the Principal Investigators and the Materials Special Investigation Group. These revelations are based on observations of LEO environmental effects on materials made in-space during LDEF retrieval and during LDEF tray deintegration at the Kennedy Space Center, and on findings of approximately 1.5 years of laboratory analyses of LDEF materials by the LDEF materials scientists. These findings were extensively reviewed and discussed at the MSIG-sponsored LDEF Materials Workshop '91. The results are presented in a format which categorizes the revelations as 'clear findings' or 'confusing/unexplained findings' and resultant needs for new space materials developments and ground simulation testing/analytical modeling in seven categories: environmental parameters and data bases; LDEF

  4. 94-1 Research and Development Project lead laboratory support: Fiscal year 1997. Progress report

    SciTech Connect

    McKee, S.D.

    1996-12-01

    On May 26, 1994, the Defense Nuclear Facilities Safety Board (DNFSB) issued Recommendation 94-1, which expressed the board`s concern about nuclear materials left in the manufacturing pipeline after the US halted its nuclear weapons production activities. The DNFSB emphasized the need for remediation of these materials. As part of Recommendation 94-1, the DNFSB defined research objectives as follows: that a research program be established to fill any gaps in the information base needed for choosing among the alternate processes to be used in safe conversion of various types of fissile materials to optimal forms for safe interim storage and the longer-term disposition. To achieve this objective a research and technology development program with two elements is needed: a technology-specific program that is focused on treating and storing materials safety, with concomitant development of storage criteria and surveillance requirements, centered around 3- and 8-year targets; and a core technology program to augment the knowledge base about general chemical and physical processing and storage behavior and to assure safe interim material storage until disposition policies are formulated. The paper reports the progress on the following: materials identification and surveillance; stabilization process development; surveillance and monitoring; core technologies; and project management.

  5. AGR-2 Data Qualification Interim Report

    SciTech Connect

    Michael L. Abbott

    2010-09-01

    Projects for the very high temperature reactor (VHTR) Technology Development Office program provide data in support of Nuclear Regulatory Commission licensing of the VHTR. Fuel and materials to be used in the reactor are tested and characterized to quantify performance in high temperature and high fluence environments. The VHTR program established the NGNP Data Management and Analysis System (NDMAS) to manage and document VHTR data qualification, for storage of the data in a readily accessible electronic form, and to assist in the analysis and presentation of the data. This document gives the status of NDMAS processing and qualification of data associated with the initial reactor cycle (147A) of the second Advanced Gas Reactor (AGR-2) experiment which began on June 21, 2010. Because it is early in the AGR-2 experiment, data from only two AGR-2 data streams are reported on: Fuel Fabrication and Fuel Irradiation data. As of August 1, 2010, approximately 311,000 irradiation data records have been stored in NDMAS, and qualification tests are in progress. Preliminary information indicates that TC 2 in Capsule 2 failed prior to start of the experiment, and NDMAS testing has thus far identified only two invalid data values from the METSO data collection system Data from the Fission Product Monitoring System (FPMS) are not currently processed until after reactor cycle shutdown and have not yet been received. A description of the ATR operating conditions data associated with the AGR-2 experiment (e.g., power levels) are summarized in the AGR-1 data qualification report (INL/EXT-09-16460). Since ATR data are collected under ATR program data quality requirements (i.e., outside the VHTR program), the NGNP program and NDMAS do not take additional actions to qualify these data other than NDMAS capture testing. Data qualification of graphite characterization data collected under the Graphite Technology Development Project is reported in a separate status report (Hull 2010).

  6. High level waste interim storge architecture selection - decision report

    SciTech Connect

    Calmus, R.B.

    1996-09-27

    The U.S. Department of Energy (DOE) has embarked upon a course to acquire Hanford Site tank waste treatment and immobilization services using privatized facilities (RL 1996a). This plan contains a two-phased approach. Phase I is a proof-of-principle/connnercial demonstration- scale effort and Phase II is a fiill-scale production effort. In accordance with the planned approach, interim storage and disposal of various products from privatized facilities are to be DOE fumished. The high-level waste (BLW) interim storage options, or alternative architectures, were identified and evaluated to provide the framework from which to select the most viable method of Phase I BLW interim storage (Calmus 1996). This evaluation, hereafter referred to as the Alternative Architecture Evaluation, was performed to established performance and risk criteria (technical merit, cost, schedule, etc.). Based on evaluation results, preliminary architectures and path forward reconunendations were provided for consideration in the architecture decision- maldng process. The decision-making process used for selection of a Phase I solidified BLW interim storage architecture was conducted in accordance with an approved Decision Plan (see the attachment). This decision process was based on TSEP-07,Decision Management Procedure (WHC 1995). The established decision process entailed a Decision Board, consisting of Westinghouse Hanford Company (VY`HC) management staff, and included appointment of a VTHC Decision Maker. The Alternative Architecture Evaluation results and preliminary recommendations were presented to the Decision Board members for their consideration in the decision-making process. The Alternative Architecture Evaluation was prepared and issued before issuance of @C-IP- 123 1, Alternatives Generation and Analysis Procedure (WI-IC 1996a), but was deemed by the Board to fully meet the intent of WHC-IP-1231. The Decision Board members concurred with the bulk of the Alternative Architecture

  7. Krakow Clean Fossil Fuels and Energy Efficiency Project

    SciTech Connect

    Pierce, B.L.; Butcher, T.A.

    1993-11-01

    Interim results are presented from testing and analytical activities for establishing the current level of emissions from existing equipment. Cost estimates for conversions or replacements are included. A public relations effort has been defined to inform the citizens of Krakow about the project and provide the means for public attitudes to be measured and incorporated into project decision-making.

  8. Interim rules amending ERISA disclosure requirements for group health plans--DoL. Interim rules with request for comments.

    PubMed

    1997-04-01

    This document contains interim rules governing the content of the summary plan description (SPD) for group health plans, the furnishing of summaries of material reductions in covered services or benefits by group health plans, and the disclosure of SPD and related information through electronic media. The rules contained in this document implement amendments to the disclosure provisions of the Employee Retirement Income Security Act of 1974 (ERISA) enacted as part of the Health Insurance Portability and Accountability Act of 1996 (HIPAA) and the Newborns' and Mothers' Health Protection Act of 1996 (NMHPA). Interested persons are invited to submit comments on the interim rules for consideration by the Department in developing final rules. The rules contained in this document are being adopted on an interim basis to accommodate statutorily established time frames intended to ensure that sponsors and administrators of group health plans, as well as participants and beneficiaries covered by such plans, have timely guidance concerning compliance with the recently enacted amendments to ERISA.

  9. Annual progress Report on research related to our research projectStabilization of Plutonium in Subsurface Environments via Microbial Reduction and Biofilm Formation” funded by the Environmental Remediation Sciences Division (ERSD)

    SciTech Connect

    New, Mary

    2006-06-01

    The overarching goal of this research project is to investigate and optimize the mechanisms for in situ immobilization of Pu species by naturally-occurring bacteria. Specific research objectives are: (a) investigate the mechanism of bacterial accumulation and immobilization of plutonium species by biofilm formation under aerobic conditions and (b) to demonstrate the direct and indirect stabilization of Pu via dissimilatory reduction by Geobacter metallireducens.

  10. Evaluation of groundwater flow and transport at the Shoal underground nuclear test: An interim report

    SciTech Connect

    Pohll, G.; Chapman, J.; Hassan, A.; Papelis, C.; Andricevic, R.; Shirley, C.

    1998-07-01

    Since 1962, all United States nuclear tests have been conducted underground. A consequence of this testing has been the deposition of large amounts of radioactive materials in the subsurface, sometimes in direct contact with groundwater. The majority of this testing occurred on the Nevada Test Site, but a limited number of experiments were conducted in other locations. One of these is the subject of this report, the Project Shoal Area (PSA), located about 50 km southeast of Fallon, Nevada. The Shoal test consisted of a 12-kiloton-yield nuclear detonation which occurred on October 26, 1963. Project Shoal was part of studies to enhance seismic detection of underground nuclear tests, in particular, in active earthquake areas. Characterization of groundwater contamination at the Project Shoal Area is being conducted by the US Department of Energy (DOE) under the Federal Facility Agreement and Consent Order (FFACO) with the State of Nevada Department of Environmental Protection and the US Department of Defense (DOD). This order prescribes a Corrective Action Strategy (Appendix VI), which, as applied to underground nuclear tests, involves preparing a Corrective Action Investigation Plan (CAIP), Corrective Action Decision Document (CADD), Corrective Action Plan, and Closure Report. The scope of the CAIP is flow and transport modeling to establish contaminant boundaries that are protective of human health and the environment. This interim report describes the current status of the flow and transport modeling for the PSA.

  11. Low cost process heat recovery. Interim report

    SciTech Connect

    Theisen, P.; McCray, J.

    1980-01-01

    The objectives of this project are to analyze waste heat recovery potential, economic analysis, heat exchanger and system design, and computer analysis programs. The heating demand and heat recovery potential at a Madison neighborhood bakery was conducted. The building has steam heat and natural gas is used in the hot water heater, the cooking stoves, and in the baking oven. Heat recovery potential was analyzed based upon fuel consumption in the baking oven, flue gas temperature, mass flow rate, and hours of oven operation. The feasibility of waste heat recovery systems is analyzed using life cycle cost and life cycle savings. For a first approximation, hand calculations were performed for air-to-air flat plate, fin-plate, and liquid-to-air tube type heat exchangers using the temperature and mass flow data from a pizza restaurant in Madison. Then a heat exchanger analysis program was written in interactive BASIC. The analysis indicates that heat recovery using the flat-plate and fin-plate exchanger designs is technically feasible and yields high effectiveness. (MCW)

  12. AES Water Architecture Study Interim Results

    NASA Technical Reports Server (NTRS)

    Sarguisingh, Miriam J.

    2012-01-01

    The mission of the Advanced Exploration System (AES) Water Recovery Project (WRP) is to develop advanced water recovery systems in order to enable NASA human exploration missions beyond low earth orbit (LEO). The primary objective of the AES WRP is to develop water recovery technologies critical to near term missions beyond LEO. The secondary objective is to continue to advance mid-readiness level technologies to support future NASA missions. An effort is being undertaken to establish the architecture for the AES Water Recovery System (WRS) that meets both near and long term objectives. The resultant architecture will be used to guide future technical planning, establish a baseline development roadmap for technology infusion, and establish baseline assumptions for integrated ground and on-orbit environmental control and life support systems (ECLSS) definition. This study is being performed in three phases. Phase I of this study established the scope of the study through definition of the mission requirements and constraints, as well as indentifying all possible WRS configurations that meet the mission requirements. Phase II of this study focused on the near term space exploration objectives by establishing an ISS-derived reference schematic for long-duration (>180 day) in-space habitation. Phase III will focus on the long term space exploration objectives, trading the viable WRS configurations identified in Phase I to identify the ideal exploration WRS. The results of Phases I and II are discussed in this paper.

  13. Overview of Materials and Power Applications of Coated Conductors Project

    NASA Astrophysics Data System (ADS)

    Shiohara, Yuh; Taneda, Takahiro; Yoshizumi, Masateru

    2012-01-01

    There are high expectations for coated conductors in electric power applications such as superconducting magnetic energy storage (SMES) systems, power cables, and transformers owing to their ability to contribute to stabilizing and increasing the capacity of the electric power supply grid as well as to reducing CO2 emission as a result of their high critical-current characteristics. Research and development has been performed on wires/tapes and electric power devices worldwide. The Materials and Power Applications of Coated Conductors (M-PACC) Project is a five-year national project in Japan started in 2008, supported by the Ministry of Economy, Trade and Industry (METI) and the New Energy and Industrial Technology Development Organization (NEDO), to develop both coated conductors that meet market requirements and basic technologies for the above-mentioned power applications using coated conductors. In this article, research and development results are reviewed and compared with the interim/final targets of the project, and future prospects are discussed.

  14. Design of Launch Vehicle Flight Control Augmentors and Resulting Flight Stability and Control (Center Director's Discretionary Fund Project 93-05, Part III)

    NASA Technical Reports Server (NTRS)

    Barret, C.

    1997-01-01

    This publication presents the control requirements, the details of the designed Flight Control Augmentor's (FCA's), the static stability and dynamic stability wind tunnel test programs, the static stability and control analyses, the dynamic stability characteristics of the experimental Launch Vehicle (LV) with the designed FCA's, and a consideration of the elastic vehicle. Dramatic improvements in flight stability have been realized with all the FCA designs; these ranged from 41 percent to 72 percent achieved by the blunt TE design. The control analysis showed that control increased 110 percent with only 3 degrees of FCA deflection. The dynamic stability results showed improvements with all FCA designs tested at all Mach numbers tested. The blunt TE FCA's had the best overall dynamic stability results. Since the lowest elastic vehicle frequency must be well separated from that of the control system, the significant frequencies and modes of vibration have been identified, and the response spectra compared for the experimental LV in both the conventional and the aft cg configuration. Although the dynamic response was 150 percent greater in the aft cg configuration, the lowest bending mode frequency decreased by only 2.8 percent.

  15. FRG sealed isotopic heat sources project (C-229) project management plan

    SciTech Connect

    Metcalf, I.L.

    1997-05-16

    This Project Management Plan defines the cost, scope, schedule, organizational responsibilities, and work breakdown structure for the removal of the Federal Republic of Germany (FRG) Sealed Isotopic Heat Sources from the 324 Building and placed in interim storage at the Central Waste Complex (CWC).

  16. Project: "Project!"

    ERIC Educational Resources Information Center

    Grayson, Katherine

    2007-01-01

    In November 2006, the editors of "Campus Technology" launched their first-ever High-Resolution Projection Study, to find out if the latest in projector technology could really make a significant difference in teaching, learning, and educational innovation on US campuses. The author and her colleagues asked campus educators, technologists, and…

  17. Evapotranspiration Cover for the 92-Acre Area Retired Mixed Waste Pits:Interim CQA Report

    SciTech Connect

    The Delphi Groupe, Inc., and J. A. Cesare and Associates, Inc.

    2011-06-20

    This Interim Construction Quality Assurance (CQA) Report is for the 92-Acre Evapotranspiration Cover, Area 5 Waste Management Division (WMD) Retired Mixed Waste Pits, Nevada National Security Site, Nevada for the period of January 20, 2011 to May 12, 2011. This Interim Construction Quality Assurance (CQA) Report is for the 92-Acre Evapotranspiration Cover, Area 5 Waste Management Division (WMD) Retired Mixed Waste Pits, Nevada National Security Site, Nevada for the period of January 20, 2011 to May 12, 2011. Construction was approved by the Nevada Division of Environmental Protection (NDEP) under the Approval of Corrective Action Decision Document/Corrective Action Plan (CADD/CAP) for Corrective Action Unit (CAU) 111: Area 5 WMD Retired Mixed Waste Pits, Nevada National Security Site, Nevada, on January 6, 2011, pursuant to Subpart XII.8a of the Federal Facility Agreement and Consent Order. The project is located in Area 5 of the Radioactive Waste Management Complex (RWMC) at the Nevada National Security Site (NNSS), formerly known as the Nevada Test Site, located in southern Nevada, approximately 65 miles northwest of Las Vegas, Nevada, in Nye County. The project site, in Area 5, is located in a topographically closed basin approximately 14 additional miles north of Mercury Nevada, in the north-central part of Frenchman Flat. The Area 5 RWMS uses engineered shallow-land burial cells to dispose of packaged waste. The 92-Acre Area encompasses the southern portion of the Area 5 RWMS, which has been designated for the first final closure operations. This area contains 13 Greater Confinement Disposal (GCD) boreholes, 16 narrow trenches, and 9 broader pits. With the exception of two active pits (P03 and P06), all trenches and pits in the 92-Acre Area had operational covers approximately 2.4 meters thick, at a minimum, in most areas when this project began. The units within the 92-Acre Area are grouped into the following six informal categories based on physical location

  18. An Interim Report on NASA's Draft Space Technology Roadmaps

    NASA Technical Reports Server (NTRS)

    2011-01-01

    NASA has developed a set of 14 draft roadmaps to guide the development of space technologies under the leadership of the NASA Office of the Chief Technologist (OCT). Each of these roadmaps focuses on a particular technology area (TA). The roadmaps are intended to foster the development of advanced technologies and concepts that address NASA's needs and contribute to other aerospace and national needs. OCT requested that the National Research Council conduct a study to review the draft roadmaps, gather and assess relevant community input, and make recommendations and suggest priorities to inform NASA's decisions as it finalizes its roadmaps. The statement of task states that "based on the results of the community input and its own deliberations, the steering committee will prepare a brief interim report that addresses high-level issues associated with the roadmaps, such as the advisability of modifying the number or technical focus of the draft NASA roadmaps." This interim report, which does not include formal recommendations, addresses that one element of the study charge. NASA requested this interim report so that it would have the opportunity to make an early start in modifying the draft roadmaps based on feedback from the panels and steering committee. The final report will address all other tasks in the statement of task. In particular, the final report will include a prioritization of technologies, will describe in detail the prioritization process and criteria, and will include specific recommendations on a variety of topics, including many of the topics mentioned in this interim report. In developing both this interim report and the final report to come, the steering committee draws on the work of six study panels organized by technical area, loosely following the organization of the 14 roadmaps, as follows: A Panel 1: Propulsion and Power TA01 Launch Propulsion Systems TA02 In-Space Propulsion Technologies TA03 Space Power and Energy Storage Systems TA13

  19. Atmospheric parameters in a subtropical cloud regime transition derived by AIRS and MODIS: observed statistical variability compared to ERA-Interim

    NASA Astrophysics Data System (ADS)

    Schreier, M. M.; Kahn, B. H.; Sušelj, K.; Karlsson, J.; Ou, S. C.; Yue, Q.; Nasiri, S. L.

    2014-04-01

    Cloud occurrence, microphysical and optical properties, and atmospheric profiles within a subtropical cloud regime transition in the northeastern Pacific Ocean are obtained from a synergistic combination of the Atmospheric Infrared Sounder (AIRS) and the MODerate resolution Imaging Spectroradiometer (MODIS). The observed cloud parameters and atmospheric thermodynamic profile retrievals are binned by cloud type and analyzed based on their probability density functions (PDFs). Comparison of the PDFs to data from the European Centre for Medium Range Weather Forecasting reanalysis (ERA-Interim) shows a strong difference in the occurrence of the different cloud types compared to clear sky. An increasing non-Gaussian behavior is observed in cloud optical thickness (τc), effective radius (re) and cloud-top temperature (Tc) distributions from stratocumulus to trade cumulus, while decreasing values of lower-tropospheric stability are seen. However, variations in the mean, width and shape of the distributions are found. The AIRS potential temperature (θ) and water vapor (q) profiles in the presence of varying marine boundary layer (MBL) cloud types show overall similarities to the ERA-Interim in the mean profiles, but differences arise in the higher moments at some altitudes. The differences between the PDFs from AIRS+MODIS and ERA-Interim make it possible to pinpoint systematic errors in both systems and help to understand joint PDFs of cloud properties and coincident thermodynamic profiles from satellite observations.

  20. Atmospheric parameters in a subtropical cloud regime transition derived by AIRS+MODIS - observed statistical variability compared to ERA-Interim

    NASA Astrophysics Data System (ADS)

    Schreier, M. M.; Kahn, B. H.; Sušelj, K.; Karlsson, J.; Ou, S. C.; Yue, Q.; Nasiri, S. L.

    2013-09-01

    Cloud occurrence, microphysical and optical properties and atmospheric profiles within a subtropical cloud regime transition in the northeastern Pacific Ocean are obtained from a synergistic combination of the Atmospheric Infrared Sounder (AIRS) and the MODerate resolution Imaging Spectroradiometer (MODIS). The observed cloud parameters and atmospheric thermodynamic profile retrievals are binned by cloud type and analyzed based on their probability density functions (PDFs). Comparison of the PDFs to data from the European Center for Medium Range Weather Forecasting Re-analysis (ERA-Interim) shows a strong difference in the occurrence of the different cloud types compared to clear sky. An increasing non-Gaussian behavior is observed in cloud optical thickness (τc), effective radius (re) and cloud top temperature (Tc) distributions from Stratocumulus to Trade Cumulus, while decreasing values of lower tropospheric stability are seen. However, variations in the mean, width and shape of the distributions are found. The AIRS potential temperature (θ) and water vapor (q) profiles in the presence of varying marine boundary layer (MBL) cloud types show overall similarities to the ERA-Interim in the mean profiles, but differences arise in the higher moments at some altitudes. The differences between the PDFs from AIRS+MODIS and ERA-Interim make it possible to pinpoint systematic errors in both systems and helps to understand joint PDFs of cloud properties and coincident thermodynamic profiles from satellite observations.

  1. Protecting the confidentiality of interim data: addressing current challenges.

    PubMed

    Fleming, Thomas R

    2015-02-01

    There is compelling evidence supporting the importance of maintaining confidentiality of interim data in clinical trials designed to reliably address the benefit-to-risk profile of interventions. While this is widely recognized, creative approaches are needed to achieve this in challenging settings where interim data are released for regulatory review and action, even though the trial would be continued to address its primary hypothesis. An illustration is the recently emerging setting of cardiovascular safety trials in type 2 diabetes mellitus. At the first stage of such trials, if large relative increases in cardiovascular major morbidity/mortality can be ruled out, data can be released solely for the purpose of allowing regulatory decision making about marketing approval. The trial is then continued in the post-marketing setting to address the primary hypothesis regarding whether smaller relative increases can be ruled out. Active rather than passive approaches are needed to protect the integrity of cardiovascular safety trials. Given the importance to trial integrity of maintaining confidentiality of interim data such as the estimated relative effect on cardiovascular risk, a Data Access Plan should be in place in these trials to ensure such data are not revealed to study participants and their caregivers, investigators involved in trial conduct, the sponsor's management team, and the public, until trial completion. A Performance Standards Document also should be developed to pre-specify targeted and minimally acceptable levels for recruitment rate, best real-world achievable adherence, avoidance of cross-ins, and retention rate. This document should specify creative approaches for achieving these targets, oversight procedures during trial conduct to monitor performance levels, and actions to be taken if emerging data indicate minimally acceptable levels are not being reached. In settings where meaningful breaches in confidentiality have occurred, such

  2. Protecting the confidentiality of interim data: addressing current challenges.

    PubMed

    Fleming, Thomas R

    2015-02-01

    There is compelling evidence supporting the importance of maintaining confidentiality of interim data in clinical trials designed to reliably address the benefit-to-risk profile of interventions. While this is widely recognized, creative approaches are needed to achieve this in challenging settings where interim data are released for regulatory review and action, even though the trial would be continued to address its primary hypothesis. An illustration is the recently emerging setting of cardiovascular safety trials in type 2 diabetes mellitus. At the first stage of such trials, if large relative increases in cardiovascular major morbidity/mortality can be ruled out, data can be released solely for the purpose of allowing regulatory decision making about marketing approval. The trial is then continued in the post-marketing setting to address the primary hypothesis regarding whether smaller relative increases can be ruled out. Active rather than passive approaches are needed to protect the integrity of cardiovascular safety trials. Given the importance to trial integrity of maintaining confidentiality of interim data such as the estimated relative effect on cardiovascular risk, a Data Access Plan should be in place in these trials to ensure such data are not revealed to study participants and their caregivers, investigators involved in trial conduct, the sponsor's management team, and the public, until trial completion. A Performance Standards Document also should be developed to pre-specify targeted and minimally acceptable levels for recruitment rate, best real-world achievable adherence, avoidance of cross-ins, and retention rate. This document should specify creative approaches for achieving these targets, oversight procedures during trial conduct to monitor performance levels, and actions to be taken if emerging data indicate minimally acceptable levels are not being reached. In settings where meaningful breaches in confidentiality have occurred, such

  3. Interim report on Landsat national archive activities

    NASA Technical Reports Server (NTRS)

    Boyd, John E.

    1993-01-01

    the tapes. An independent consulting division of a major tape manufacturer has analyzed affected tapes and is confident that restorative procedures can be applied to the HDT's to permit one pass to reproduce the data on another recording media. A system to distribute minimally processed Landsat data will be procured in 1992 and will be operational by mid-1994. Any TM or MSS data in the national archive that are not restricted by exclusive marketing rights will be reproduced directly from the archive media onto user specified computer-compatible media. TM data will be produced either at a raw level (radiometrically and geometrically uncorrected) or at an intermediate level (radiometrically corrected and geometrically indexed). MSS data will be produced to an intermediate level or to a fully corrected level (radiometrically corrected and geometrically transformed to an Oblique Mercator projection). The system will be capable of providing ordered scenes within 48 hours of receipt of order.

  4. 42 CFR 93.401 - Interaction with other offices and interim actions.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... Human Services General Information § 93.401 Interaction with other offices and interim actions. (a) ORI... 42 Public Health 1 2012-10-01 2012-10-01 false Interaction with other offices and interim actions. 93.401 Section 93.401 Public Health PUBLIC HEALTH SERVICE, DEPARTMENT OF HEALTH AND HUMAN...

  5. 42 CFR 93.401 - Interaction with other offices and interim actions.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... Human Services General Information § 93.401 Interaction with other offices and interim actions. (a) ORI... 42 Public Health 1 2014-10-01 2014-10-01 false Interaction with other offices and interim actions. 93.401 Section 93.401 Public Health PUBLIC HEALTH SERVICE, DEPARTMENT OF HEALTH AND HUMAN...

  6. 75 FR 52597 - Availability of Interim Procedures for Federal External Review and Model Notices Relating to...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-08-26

    ... Departments published interim final regulations implementing PHS Act section 2719 on July 23, 2010, at 75 FR... interim final regulations implementing section 1251 of the Affordable Care Act on June 17, 2010, at 75 FR....healthcare.gov . SUPPLEMENTARY INFORMATION: I. Background The Patient Protection and Affordable Care Act...

  7. 32 CFR 643.36 - Policy-Interim leasing of excess properties to facilitate economic readjustment.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 32 National Defense 4 2010-07-01 2010-07-01 true Policy-Interim leasing of excess properties to facilitate economic readjustment. 643.36 Section 643.36 National Defense Department of Defense (Continued) DEPARTMENT OF THE ARMY (CONTINUED) REAL PROPERTY REAL ESTATE Policy § 643.36 Policy—Interim leasing of...

  8. 40 CFR 80.156 - Liability for violations of the interim detergent program controls and prohibitions.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... CFR part 79 registration, and must also accurately identify if the detergent, at that concentration... interim detergent program controls and prohibitions. 80.156 Section 80.156 Protection of Environment... Detergent Gasoline § 80.156 Liability for violations of the interim detergent program controls...

  9. 40 CFR 80.156 - Liability for violations of the interim detergent program controls and prohibitions.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... CFR part 79 registration, and must also accurately identify if the detergent, at that concentration... interim detergent program controls and prohibitions. 80.156 Section 80.156 Protection of Environment... Detergent Gasoline § 80.156 Liability for violations of the interim detergent program controls...

  10. 40 CFR 80.156 - Liability for violations of the interim detergent program controls and prohibitions.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... CFR part 79 registration, and must also accurately identify if the detergent, at that concentration... interim detergent program controls and prohibitions. 80.156 Section 80.156 Protection of Environment... Detergent Gasoline § 80.156 Liability for violations of the interim detergent program controls...

  11. Can Interim Assessments Be Used for Instructional Change? Policy Brief. RB-51

    ERIC Educational Resources Information Center

    Goertz, Margaret E.; Olah, Leslie Nabors; Riggan, Matthew

    2009-01-01

    The purpose of this exploratory study was to examine the use of interim assessments and the policy supports that promote their use to change instruction, focusing on elementary school mathematics. The authors use the term "interim assessments" to refer to assessments that: a) evaluate student knowledge and skills, typically within a limited time…

  12. 46 CFR 308.6 - Period of interim binders, updating application information and new applications.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... with the American War Risk Agency, 14 Wall Street, New York, New York 10005. All interim binders on U.S... Wall Street, New York, New York 10005. All interim binders on foreign-flag vessels will become... information and new applications. 308.6 Section 308.6 Shipping MARITIME ADMINISTRATION, DEPARTMENT...

  13. 46 CFR 308.6 - Period of interim binders, updating application information and new applications.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... with the American War Risk Agency, 14 Wall Street, New York, New York 10005. All interim binders on U.S... Wall Street, New York, New York 10005. All interim binders on foreign-flag vessels will become... information and new applications. 308.6 Section 308.6 Shipping MARITIME ADMINISTRATION, DEPARTMENT...

  14. 46 CFR 308.6 - Period of interim binders, updating application information and new applications.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... with the American War Risk Agency, 14 Wall Street, New York, New York 10005. All interim binders on U.S... Wall Street, New York, New York 10005. All interim binders on foreign-flag vessels will become... information and new applications. 308.6 Section 308.6 Shipping MARITIME ADMINISTRATION, DEPARTMENT...

  15. 78 FR 76160 - Public Housing Assessment System (PHAS) Capital Fund Interim Scoring Notice: Reinstitution of...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-12-16

    ... by an interim rule published on February 23, 2011, at 76 FR 10136. The Capital Fund Program Indicator... Scoring Notice, also published on February 23, 2011, at 76 FR 10053. Under this indicator, PHAs can... Capital Fund by an interim notice for public comment, 77 FR 34399 (Monday, June 11, 2012), which...

  16. 31 CFR 50.7 - Special Rules for Interim Guidance Safe Harbors.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 31 Money and Finance: Treasury 1 2011-07-01 2011-07-01 false Special Rules for Interim Guidance Safe Harbors. 50.7 Section 50.7 Money and Finance: Treasury Office of the Secretary of the Treasury TERRORISM RISK INSURANCE PROGRAM General Provisions § 50.7 Special Rules for Interim Guidance Safe...

  17. 31 CFR 50.7 - Special Rules for Interim Guidance Safe Harbors.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 31 Money and Finance: Treasury 1 2012-07-01 2012-07-01 false Special Rules for Interim Guidance Safe Harbors. 50.7 Section 50.7 Money and Finance: Treasury Office of the Secretary of the Treasury TERRORISM RISK INSURANCE PROGRAM General Provisions § 50.7 Special Rules for Interim Guidance Safe...

  18. 31 CFR 50.7 - Special Rules for Interim Guidance Safe Harbors.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 31 Money and Finance: Treasury 1 2013-07-01 2013-07-01 false Special Rules for Interim Guidance Safe Harbors. 50.7 Section 50.7 Money and Finance: Treasury Office of the Secretary of the Treasury TERRORISM RISK INSURANCE PROGRAM General Provisions § 50.7 Special Rules for Interim Guidance Safe...

  19. 31 CFR 50.7 - Special Rules for Interim Guidance Safe Harbors.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 31 Money and Finance: Treasury 1 2014-07-01 2014-07-01 false Special Rules for Interim Guidance Safe Harbors. 50.7 Section 50.7 Money and Finance: Treasury Office of the Secretary of the Treasury TERRORISM RISK INSURANCE PROGRAM General Provisions § 50.7 Special Rules for Interim Guidance Safe...

  20. 10 CFR 430.27 - Petitions for waiver and applications for interim waiver.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 10 Energy 3 2013-01-01 2013-01-01 false Petitions for waiver and applications for interim waiver... Petition for Waiver, to the Assistant Secretary for Conservation and Renewable Energy, U.S. Department of Energy. Each Application for Interim Waiver shall reference the Petition for Waiver by identifying...

  1. 10 CFR 430.27 - Petitions for waiver and applications for interim waiver.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 10 Energy 3 2012-01-01 2012-01-01 false Petitions for waiver and applications for interim waiver... Petition for Waiver, to the Assistant Secretary for Conservation and Renewable Energy, U.S. Department of Energy. Each Application for Interim Waiver shall reference the Petition for Waiver by identifying...

  2. The Impact of Indiana's System of Interim Assessments on Mathematics and Reading Achievement

    ERIC Educational Resources Information Center

    Konstantopoulos, Spyros; Miller, Shazia Rafiullah; van der Ploeg, Arie

    2013-01-01

    Interim assessments are increasingly common in U.S. schools. We use high-quality data from a large-scale school-level cluster randomized experiment to examine the impact of two well-known commercial interim assessment programs on mathematics and reading achievement in Indiana. Results indicate that the treatment effects are positive but not…

  3. 78 FR 56752 - Interim Staff Guidance Specific Environmental Guidance for Integral Pressurized Water Reactors...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-09-13

    ... comment on, draft Interim Staff Guidance (ISG) ESP/COL-ISG-027, ``Interim Staff Guidance Specific..., early site permits (ESPs), and combined licenses (COLs). DATES: Submit comments by October 15, 2013... issues ESP/COL-ISGs to facilitate timely implementation of current staff guidance and to...

  4. 30 CFR 827.13 - Coal preparation plants: Interim performance standards.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 30 Mineral Resources 3 2011-07-01 2011-07-01 false Coal preparation plants: Interim performance...-COAL PREPARATION PLANTS NOT LOCATED WITHIN THE PERMIT AREA OF A MINE § 827.13 Coal preparation plants: Interim performance standards. (a) Persons operating or who have operated coal preparation plants...

  5. 30 CFR 827.13 - Coal preparation plants: Interim performance standards.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 30 Mineral Resources 3 2010-07-01 2010-07-01 false Coal preparation plants: Interim performance...-COAL PREPARATION PLANTS NOT LOCATED WITHIN THE PERMIT AREA OF A MINE § 827.13 Coal preparation plants: Interim performance standards. (a) Persons operating or who have operated coal preparation plants...

  6. 30 CFR 827.13 - Coal preparation plants: Interim performance standards.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 30 Mineral Resources 3 2012-07-01 2012-07-01 false Coal preparation plants: Interim performance...-COAL PREPARATION PLANTS NOT LOCATED WITHIN THE PERMIT AREA OF A MINE § 827.13 Coal preparation plants: Interim performance standards. (a) Persons operating or who have operated coal preparation plants...

  7. 30 CFR 827.13 - Coal preparation plants: Interim performance standards.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 30 Mineral Resources 3 2014-07-01 2014-07-01 false Coal preparation plants: Interim performance...-COAL PREPARATION PLANTS NOT LOCATED WITHIN THE PERMIT AREA OF A MINE § 827.13 Coal preparation plants: Interim performance standards. (a) Persons operating or who have operated coal preparation plants...

  8. 30 CFR 827.13 - Coal preparation plants: Interim performance standards.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 30 Mineral Resources 3 2013-07-01 2013-07-01 false Coal preparation plants: Interim performance...-COAL PREPARATION PLANTS NOT LOCATED WITHIN THE PERMIT AREA OF A MINE § 827.13 Coal preparation plants: Interim performance standards. (a) Persons operating or who have operated coal preparation plants...

  9. 40 CFR 52.243 - Interim approval of the Carbon Monoxide plan for the South Coast.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 3 2010-07-01 2010-07-01 false Interim approval of the Carbon Monoxide plan for the South Coast. 52.243 Section 52.243 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR PROGRAMS (CONTINUED) APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS California § 52.243 Interim approval of the...

  10. 40 CFR 52.243 - Interim approval of the Carbon Monoxide plan for the South Coast.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 40 Protection of Environment 3 2012-07-01 2012-07-01 false Interim approval of the Carbon Monoxide plan for the South Coast. 52.243 Section 52.243 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR PROGRAMS (CONTINUED) APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS California § 52.243 Interim approval of the...

  11. 40 CFR 52.243 - Interim approval of the Carbon Monoxide plan for the South Coast.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 40 Protection of Environment 3 2013-07-01 2013-07-01 false Interim approval of the Carbon Monoxide plan for the South Coast. 52.243 Section 52.243 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR PROGRAMS (CONTINUED) APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS California § 52.243 Interim approval of the...

  12. 42 CFR 93.401 - Interaction with other offices and interim actions.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 42 Public Health 1 2010-10-01 2010-10-01 false Interaction with other offices and interim actions. 93.401 Section 93.401 Public Health PUBLIC HEALTH SERVICE, DEPARTMENT OF HEALTH AND HUMAN SERVICES... Human Services General Information § 93.401 Interaction with other offices and interim actions. (a)...

  13. 40 CFR 52.243 - Interim approval of the Carbon Monoxide plan for the South Coast.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 40 Protection of Environment 3 2011-07-01 2011-07-01 false Interim approval of the Carbon Monoxide... § 52.243 Interim approval of the Carbon Monoxide plan for the South Coast. The Carbon Monoxide plan for... such earlier date the State has submitted as a SIP revision a demonstration that the carbon...

  14. 40 CFR 52.243 - Interim approval of the Carbon Monoxide plan for the South Coast.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 40 Protection of Environment 3 2014-07-01 2014-07-01 false Interim approval of the Carbon Monoxide... § 52.243 Interim approval of the Carbon Monoxide plan for the South Coast. The Carbon Monoxide plan for... such earlier date the State has submitted as a SIP revision a demonstration that the carbon...

  15. 40 CFR 280.11 - Interim prohibition for deferred UST systems.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... Corrosion on Metallic Buried, Partially Buried, or Submerged Liquid Storage Systems,” may be used as... systems. 280.11 Section 280.11 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) SOLID... UNDERGROUND STORAGE TANKS (UST) Program Scope and Interim Prohibition § 280.11 Interim prohibition...

  16. 40 CFR 280.11 - Interim prohibition for deferred UST systems.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... Corrosion on Metallic Buried, Partially Buried, or Submerged Liquid Storage Systems,” may be used as... systems. 280.11 Section 280.11 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) SOLID... UNDERGROUND STORAGE TANKS (UST) Program Scope and Interim Prohibition § 280.11 Interim prohibition...

  17. 40 CFR 280.11 - Interim prohibition for deferred UST systems.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... Corrosion on Metallic Buried, Partially Buried, or Submerged Liquid Storage Systems,” may be used as... systems. 280.11 Section 280.11 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) SOLID... UNDERGROUND STORAGE TANKS (UST) Program Scope and Interim Prohibition § 280.11 Interim prohibition...

  18. 40 CFR 280.11 - Interim prohibition for deferred UST systems.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... Corrosion on Metallic Buried, Partially Buried, or Submerged Liquid Storage Systems,” may be used as... systems. 280.11 Section 280.11 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) SOLID... UNDERGROUND STORAGE TANKS (UST) Program Scope and Interim Prohibition § 280.11 Interim prohibition...

  19. 40 CFR 280.11 - Interim prohibition for deferred UST systems.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... Corrosion on Metallic Buried, Partially Buried, or Submerged Liquid Storage Systems,” may be used as... systems. 280.11 Section 280.11 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) SOLID... UNDERGROUND STORAGE TANKS (UST) Program Scope and Interim Prohibition § 280.11 Interim prohibition...

  20. Interim Action Proposed Plan for the Chemicals, Metals, and Pesticides (CMP) Pits Operable Unit

    SciTech Connect

    Bradley, J.

    2002-06-18

    The purpose of this Interim Action Proposed Plan (IAPP) is to describe the preferred interim remedial action for addressing the Chemicals, Metals, and Pesticides (CMP) Pits Operable Unit and to provide an opportunity for public input into the remedial action selection process.

  1. 78 FR 40199 - Draft Spent Fuel Storage and Transportation Interim Staff Guidance

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-07-03

    ... COMMISSION Draft Spent Fuel Storage and Transportation Interim Staff Guidance AGENCY: Nuclear Regulatory... Regulatory Commission (NRC) requests public comment on Draft Spent Fuel Storage and Transportation Interim... Integrity for Continued Storage of High Burnup Fuel Beyond 20 Years.'' The draft SFST-ISG provides...

  2. 31 CFR 50.7 - Special Rules for Interim Guidance Safe Harbors.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 31 Money and Finance: Treasury 1 2010-07-01 2010-07-01 false Special Rules for Interim Guidance Safe Harbors. 50.7 Section 50.7 Money and Finance: Treasury Office of the Secretary of the Treasury TERRORISM RISK INSURANCE PROGRAM General Provisions § 50.7 Special Rules for Interim Guidance Safe...

  3. Effects of Interim Assessments across the Achievement Distribution: Evidence From an Experiment

    ERIC Educational Resources Information Center

    Konstantopoulos, Spyros; Li, Wei; Miller, Shazia R.; van der Ploeg, Arie

    2016-01-01

    We use data from a large-scale experiment conducted in Indiana in 2009-2010 to examine the impact of two interim assessment programs (mCLASS and Acuity) across the mathematics and reading achievement distributions. Specifically, we focus on whether the use of interim assessments has a particularly strong effect on improving outcomes for low…

  4. 47 CFR 73.9008 - Interim approval of authorized digital output protection technologies and authorized recording...

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 47 Telecommunication 4 2010-10-01 2010-10-01 false Interim approval of authorized digital output... COMMUNICATIONS COMMISSION (CONTINUED) BROADCAST RADIO SERVICES RADIO BROADCAST SERVICES Digital Broadcast Television Redistribution Control § 73.9008 Interim approval of authorized digital output...

  5. 40 CFR 265.352 - Interim status incinerators burning particular hazardous wastes.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 40 Protection of Environment 26 2014-07-01 2014-07-01 false Interim status incinerators burning... HAZARDOUS WASTE TREATMENT, STORAGE, AND DISPOSAL FACILITIES Incinerators § 265.352 Interim status incinerators burning particular hazardous wastes. (a) Owners or operators of incinerators subject to...

  6. 40 CFR 265.352 - Interim status incinerators burning particular hazardous wastes.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 40 Protection of Environment 27 2012-07-01 2012-07-01 false Interim status incinerators burning... HAZARDOUS WASTE TREATMENT, STORAGE, AND DISPOSAL FACILITIES Incinerators § 265.352 Interim status incinerators burning particular hazardous wastes. (a) Owners or operators of incinerators subject to...

  7. 40 CFR 265.352 - Interim status incinerators burning particular hazardous wastes.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 40 Protection of Environment 26 2011-07-01 2011-07-01 false Interim status incinerators burning... HAZARDOUS WASTE TREATMENT, STORAGE, AND DISPOSAL FACILITIES Incinerators § 265.352 Interim status incinerators burning particular hazardous wastes. (a) Owners or operators of incinerators subject to...

  8. 40 CFR 265.352 - Interim status incinerators burning particular hazardous wastes.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 40 Protection of Environment 27 2013-07-01 2013-07-01 false Interim status incinerators burning... HAZARDOUS WASTE TREATMENT, STORAGE, AND DISPOSAL FACILITIES Incinerators § 265.352 Interim status incinerators burning particular hazardous wastes. (a) Owners or operators of incinerators subject to...

  9. Shuttle/IUS performance for planetary missions. [Interim Upper Stage

    NASA Technical Reports Server (NTRS)

    Cork, M. J.; Driver, J. M.; Wright, J. L.

    1975-01-01

    Potential requirements for planetary missions in the 1980s, capabilities of the Interim Upper Stage (IUS) candidates to perform those missions, and Shuttle/IUS mission profile options for performance enhancement are examined. The most demanding planetary missions are the Pioneer Saturn/Uranus/Titan Probe and the Mariner-class orbiters of Mercury, Jupiter, and Saturn. Options available to designers of these missions will depend on the specific IUS selected for development and the programmatic phasing of the IUS and the NASA Tug. Use of Shuttle elliptic orbits as initial conditions for IUS ignition offers significant performance improvements; specific values are mission dependent.

  10. Dosimetry at an interim storage for spent nuclear fuel.

    PubMed

    Králík, M; Kulich, V; Studeny, J; Pokorny, P

    2007-01-01

    The Czech nuclear power plant Dukovany started its operation in 1985. All fuel spent from 1985 up to the end of 2005 is stored at a dry interim storage, which was designed for 60 CASTOR-440/84 casks. Each of these casks can accommodate 84 fuel assemblies from VVER 440 reactors. Neutron-photon mixed fields around the casks were characterized in terms of ambient dose equivalent measured by standard area dosemeters. Except this, neutron spectra were measured by means of a Bonner sphere spectrometer, and the measured spectra were used to derive the corresponding ambient dose equivalent due to neutrons.

  11. Performance evaluation of the JPL interim digital SAR processor

    NASA Technical Reports Server (NTRS)

    Wu, C.; Barkan, B.; Curlander, J.; Jin, M.; Pang, S.

    1983-01-01

    The performance of the Interim Digital SAR Processor (IDP) was evaluated. The IDP processor was originally developed for experimental processing of digital SEASAT SAR data. One phase of the system upgrade which features parallel processing in three peripheral array processors, automated estimation for Doppler parameters, and unsupervised image pixel location determination and registration was executed. The method to compensate for the target range curvature effect was improved. A four point interpolation scheme is implemented to replace the nearest neighbor scheme used in the original IDP. The processor still maintains its fast throughput speed. The current performance and capability of the processing modes now available on the IDP system are updated.

  12. Maryland Bridge: An Interim Prosthesis for Tooth Replacement in Adolescents

    PubMed Central

    Jyoti, Sapna; Kaul, Rupali Borkar; Sethi, Ntasha

    2011-01-01

    A space in the anterior region of the dental arch of a youngster, either due to trauma or a congenitally missing tooth, can not only lead to psychological trauma but also create a functional dilemma for the dentist, as the usual treatment options of implant, removable partial denture and fixed partial denture available for adults, are often inapplicable or inconvenient for an adolescent. In such a situation, a resin-bonded fixed partial denture (RBFPD), such as Maryland Bridge fulfills all the requirements of an ideal interim solution till growth completion is achieved and a more permanent tooth replacement option can be explored.

  13. Medicare Interim Payment System's Impact on Medicare Home Health Utilization

    PubMed Central

    Liu, Korbin; Long, Sharon K.; Dowling, Krista

    2003-01-01

    The Medicare home health interim payment system (IPS) implemented in fiscal year 1998 provided very strong incentives for home health agencies (HHAs) to reduce the number of visits provided to each Medicare user and to avoid those beneficiaries whose Medicare plan of care was likely to exceed the average beneficiary cost limit. We analyzed multiple years of data from the Medicare Current Beneficiary Survey (MCBS) to examine how the IPS affected subgroups of the Medicare population by health and socioeconomic characteristics. We found that the IPS strongly reduced overall utilization, but that few subgroups were disproportionately affected. PMID:14997695

  14. US PRACTICE FOR INTERIM WET STORAGE OF RRSNF

    SciTech Connect

    Vinson, D.

    2010-08-05

    Aluminum research reactor spent nuclear fuel is currently being stored or is anticipated to be returned to the United States and stored at Department of Energy storage facilities at the Savannah River Site and the Idaho Nuclear Technology and Engineering Center. This paper summarizes the current practices to provide for continued safe interim wet storage in the U.S. Aluminum fuel stored in poor quality water is subject to aggressive corrosion attack and therefore water chemistry control systems are essential to maintain water quality. Fuel with minor breaches are safely stored directly in the basin. Fuel pieces and heavily damaged fuel is safely stored in isolation canisters.

  15. Chesapeake Bay fall line toxics monitoring program: 1992 interim report

    SciTech Connect

    Dobler, E.; Nemura, A.

    1994-04-01

    The report provides an interim assessment of toxic substance loadings from the fall lines of three major tributaries, Susquehanna, Potomac and James Rivers, to the Chesapeake Bay. Results from the first six months of a one year sampling program conducted from March, 1992 to September, 1992 are described. Loadings are provided for trace metals; synthetic organic compounds; organonitrogen, organophosphorus, and organochlorine pesticides; polychlorinated biphenyl congeners; and polycyclic aromatic hydrocarbons. The program included sampling during both base and storm flow conditions. A key component of the report is the comparison of ultra clean versus standard U.S. Geological Survey protocol collection techniques for trace metals and organics.

  16. Dosimetry at an interim storage for spent nuclear fuel.

    PubMed

    Králík, M; Kulich, V; Studeny, J; Pokorny, P

    2007-01-01

    The Czech nuclear power plant Dukovany started its operation in 1985. All fuel spent from 1985 up to the end of 2005 is stored at a dry interim storage, which was designed for 60 CASTOR-440/84 casks. Each of these casks can accommodate 84 fuel assemblies from VVER 440 reactors. Neutron-photon mixed fields around the casks were characterized in terms of ambient dose equivalent measured by standard area dosemeters. Except this, neutron spectra were measured by means of a Bonner sphere spectrometer, and the measured spectra were used to derive the corresponding ambient dose equivalent due to neutrons. PMID:17526479

  17. Crisis Intervention Project, Boston Public Schools, December 1, 1972-May 1, 1973. Evaluation.

    ERIC Educational Resources Information Center

    Marion, David J.

    The Crisis Prevention-Intervention Project (CPI) of the Boston Public Schools is described in two parts: a six-month evaluation report and an interim report by the project director. The goals of this pilot project for the five Boston schools (three public, two parochial) were: (1) to develop an operational program of crisis intervention and…

  18. Online Monitoring Technical Basis and Analysis Framework for Large Power Transformers; Interim Report for FY 2012

    SciTech Connect

    Nancy J. Lybeck; Vivek Agarwal; Binh T. Pham; Heather D. Medema; Kirk Fitzgerald

    2012-09-01

    The Light Water Reactor Sustainability program at Idaho National Laboratory (INL) is actively conducting research to develop and demonstrate online monitoring (OLM) capabilities for active components in existing Nuclear Power Plants. A pilot project is currently underway to apply OLM to Generator Step-Up Transformers (GSUs) and Emergency Diesel Generators (EDGs). INL and the Electric Power Research Institute (EPRI) are working jointly to implement the pilot project. The EPRI Fleet-Wide Prognostic and Health Management (FW-PHM) Software Suite will be used to implement monitoring in conjunction with utility partners: the Shearon Harris Nuclear Generating Station (owned by Duke Energy for GSUs, and Braidwood Generating Station (owned by Exelon Corporation) for EDGs. This report presents monitoring techniques, fault signatures, and diagnostic and prognostic models for GSUs. GSUs are main transformers that are directly connected to generators, stepping up the voltage from the generator output voltage to the highest transmission voltages for supplying electricity to the transmission grid. Technical experts from Shearon Harris are assisting INL and EPRI in identifying critical faults and defining fault signatures associated with each fault. The resulting diagnostic models will be implemented in the FW-PHM Software Suite and tested using data from Shearon-Harris. Parallel research on EDGs is being conducted, and will be reported in an interim report during the first quarter of fiscal year 2013.

  19. 77 FR 15818 - License Renewal Interim Staff Guidance LR-ISG-2011-05: Ongoing Review of Operating Experience

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-03-16

    ... COMMISSION License Renewal Interim Staff Guidance LR-ISG-2011-05: Ongoing Review of Operating Experience AGENCY: Nuclear Regulatory Commission. ACTION: Interim staff guidance; issuance. SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing the final License Renewal Interim Staff Guidance...

  20. 75 FR 984 - Draft Recommended Interim Preliminary Remediation Goals for Dioxin in Soil at CERCLA and RCRA Sites

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-01-07

    ... AGENCY RIN 2050-ZA05 Draft Recommended Interim Preliminary Remediation Goals for Dioxin in Soil at CERCLA... announcing a 50-day public comment period for draft recommended interim preliminary remediation goals (PRGs) developed in the Draft Recommended Interim Preliminary Remediation Goals for Dioxin in Soil at...