Science.gov

Sample records for interim stabilization project

  1. Single-shell tank interim stabilization project plan

    SciTech Connect

    Ross, W.E.

    1998-03-27

    Solid and liquid radioactive waste continues to be stored in 149 single-shell tanks at the Hanford Site. To date, 119 tanks have had most of the pumpable liquid removed by interim stabilization. Thirty tanks remain to be stabilized. One of these tanks (C-106) will be stabilized by retrieval of the tank contents. The remaining 29 tanks will be interim stabilized by saltwell pumping. In the summer of 1997, the US Department of Energy (DOE) placed a moratorium on the startup of additional saltwell pumping systems because of funding constraints and proposed modifications to the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) milestones to the Washington State Department of Ecology (Ecology). In a letter dated February 10, 1998, Final Determination Pursuant to Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) in the Matter of the Disapproval of the DOE`s Change Control Form M-41-97-01 (Fitzsimmons 1998), Ecology disapproved the DOE Change Control Form M-41-97-01. In response, Fluor Daniel Hanford, Inc. (FDH) directed Lockheed Martin Hanford Corporation (LNMC) to initiate development of a project plan in a letter dated February 25, 1998, Direction for Development of an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan in Support of Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement). In a letter dated March 2, 1998, Request for an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan, the DOE reaffirmed the need for an aggressive SST interim stabilization completion project plan to support a finalized Tri-Party Agreement Milestone M-41 recovery plan. This project plan establishes the management framework for conduct of the TWRS Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organizational structure, roles, responsibilities

  2. Single-shell tank interim stabilization project plan

    SciTech Connect

    Ross, W.E.

    1998-05-11

    This project plan establishes the management framework for conduct of the TWRS Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organizational structure, roles, responsibilities, and interfaces; and operational methods. This plan serves as the project executional baseline.

  3. Single Shell Tank (SST) Interim Stabilization Project Plan

    SciTech Connect

    VLADIMIROFF, D.T.; BOYLES, V.C.

    2000-05-22

    This project plan establishes the management framework for the conduct of the CHG Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organization structure, roles, responsibilities, and interfaces; and operational methods. This plan serves as the project executional baseline.

  4. Project Canada West. Interim Report.

    ERIC Educational Resources Information Center

    Western Curriculum Project on Canada Studies, Edmonton (Alberta).

    This first interim report of project Canada West, initiated in April, 1970, includes three papers. "Curriculum Development in Urbanization," by Dr. R. H. Sabey, Acting Executive Director, is an overview of the Project's history, purpose, and the 5 year plan for phases of research development. (See SO 000 283 for complete abstract.) Two…

  5. Collection Analysis Project. Interim Report.

    ERIC Educational Resources Information Center

    Collier, Carol; And Others

    This interim report of the University of Wyoming's Collection Analysis Project, whose purpose is to examine the university library's collection development process and make workable recommendations for process improvement, consists of a brief history of the library's collection, including a review of the evolution of the collection development…

  6. Interim Report: Uranium Stabilization Through Polyphosphate Injection - 300 Area Uranium Plume Treatability Demonstration Project

    SciTech Connect

    Wellman, Dawn M.; Pierce, Eric M.; Richards, Emily L.; Butler, Bart C.; Parker, Kent E.; Glovack, Julia N.; Burton, Sarah D.; Baum, Steven R.; Clayton, Eric T.; Rodriguez, Elsa A.

    2007-07-31

    This report presents results from bench-scale treatability studies conducted under site-specific conditions to optimize the polyphosphate amendment for implementation of a field-scale technology demonstration to treat aqueous uranium within the 300 Area aquifer of the Hanford site. The general treatability testing approach consists of conducting studies with site sediment and under site conditions, in order to develop an effective chemical formulation for the polyphosphate amendments and evaluate the transport properties of these amendments under site conditions. Phosphorus-31 (31P) NMR was utilized to determine the effects of Hanford groundwater and sediment on the degradation of inorganic phosphates. Static batch tests were conducted to optimize the composition of the polyphosphate formulation for the precipitation of apatite and autunite, as well as to quantify the kinetics, loading and stability of apatite as a long-term sorbent for uranium. Dynamic column tests were used to further optimize the polyphosphate formulation for emplacement within the subsurface and the formation of autunite and apatite. In addition, dynamic testing quantified the stability of autunite and apatite under relevant site conditions. Results of this investigation provide valuable information for designing a full-scale remediation of uranium in the 300 aquifer.

  7. EARLY TRAINING PROJECT. INTERIM REPORT.

    ERIC Educational Resources Information Center

    GRAY, SUSAN W.; KLAUS, RUPERT A.

    THE EARLY TRAINING PROJECT ATTEMPTED TO IMPROVE THE INTELLECTUAL FUNCTIONING AND PERSONAL ADJUSTMENT OF CULTURALLY DISADVANTAGED CHILDREN THROUGH SPECIAL EXPERIENCES IN THE 15- OR 24-MONTHS PRECEDING FIRST GRADE AND IN THE FIRST YEAR OF SCHOOL. THE PROCEDURES OF THE PROJECT CONSISTED OF TWO TRAINING SEQUENCES. THE FIRST SEQUENCE INVOLVED TWO…

  8. Engineering Task Plan for Hose In Hose Transfer Lines for the Interim Stabilization Program

    SciTech Connect

    RUNG, M.P.

    2000-06-20

    This document is the Engineering Task Plan for the engineering, design services, planning, project integration and management support for the design, modification, installation and testing of an over ground transfer (OGT) system to support the interim stabilization of nine tanks in the 241-S/SX Tank Farms.

  9. Design Analysis Report for 244-AR Interim Stabilization Exhaust Ventilation Ducting

    SciTech Connect

    RUTHERFORD, J.

    2002-11-21

    This report documents the design analysis performed for the exhaust ducting associated with the 244-AR Interim Stabilization Project. The exhaust ducting connects portable exhausters PORO5 and PORO6 to the existing east dog house of the 291-AR filter vault and the vessel ventilation system. This analysis examines loads on the ductwork and ductwork supports.

  10. Engineering Task Plan for Hose In Hose Transfer Lines for the Interim Stabilization Program

    SciTech Connect

    TORRES, T.D.

    2000-08-16

    The document is the Engineering Task Plan for the engineering, design services, planning, project integration and management support for the design, modification, installation and testing of an over ground transfer (OGT) system to support the interim stabilization of S/SX and U Tank Farms.

  11. SLIGHTLY IRRADIATED FUEL (SIF) INTERIM DISPOSITION PROJECT

    SciTech Connect

    NORTON SH

    2010-02-23

    CH2M HILL Plateau Remediation Company (CH2M HILL PRC) is proud to submit the Slightly Irradiated Fuel (SIF) Interim Disposition Project for consideration by the Project Management Institute as Project of the Year for 2010. The SIF Project was a set of six interrelated sub-projects that delivered unique stand-alone outcomes, which, when integrated, provided a comprehensive and compliant system for storing high risk special nuclear materials. The scope of the six sub-projects included the design, construction, testing, and turnover of the facilities and equipment, which would provide safe, secure, and compliant Special Nuclear Material (SNM) storage capabilities for the SIF material. The project encompassed a broad range of activities, including the following: Five buildings/structures removed, relocated, or built; Two buildings renovated; Structural barriers, fencing, and heavy gates installed; New roadways and parking lots built; Multiple detection and assessment systems installed; New and expanded communication systems developed; Multimedia recording devices added; and A new control room to monitor all materials and systems built. Project challenges were numerous and included the following: An aggressive 17-month schedule to support the high-profile Plutonium Finishing Plant (PFP) decommissioning; Company/contractor changeovers that affected each and every project team member; Project requirements that continually evolved during design and construction due to the performance- and outcome-based nature ofthe security objectives; and Restrictions imposed on all communications due to the sensitive nature of the projects In spite of the significant challenges, the project was delivered on schedule and $2 million under budget, which became a special source of pride that bonded the team. For years, the SIF had been stored at the central Hanford PFP. Because of the weapons-grade piutonium produced and stored there, the PFP had some of the tightest security on the Hanford

  12. Safety evaluation of interim stabilization of non-stabilized single-shell watch list tanks

    SciTech Connect

    Stahl, S.M.

    1994-12-30

    The report provides a summation of the status of safety issues associated with interim stabilization of Watch List SSTs (organic, ferrocyanide, and flammable gas), as extracted from recent safety analyses, including the Tank Farms Accelerated Safety Analysis efforts.

  13. Stability of laminar electron layers. Interim report

    SciTech Connect

    Chernin, D.; Lau, Y.Y.

    1984-06-22

    The stability of a finite thickness, laminar cylindrical shell of electrons rotating azimuthally and enclosed in a coaxial waveguide is considered. The equilibrium rotation of the electrons is supported either by a radial electric field, an axial magnetic field, or a combination of both. The stability problem is formulated exactly as an eigenvalue problem, including all relativistic and electromagnetic effects as well as all effects of self and applied equilibrium fields. An approximate dispersion relation, valid for thin beams, is obtained analytically and the classical results for the longitudinal modes, i.e., the negative mass, cyclotron maser and diocotron instabilities and for the transvers mode are recovered in appropriate limits. The dispersion relation is relatively simple and is valid for arbitrary values of the equilibrium electric and magnetic fields and for arbitrary bean energy. It therefore provides a ready comparison of the small signal properties of such devices as the Astron, gyrotron, orbitron, heliotron and the various cross field devices. It may also be of interest in accelerator and space physics applications. Some heretofore unnoticed effects on beam stability of equilibrium fields are reported; one such effect in particular leads to formulation of a simple, effective method either to maximize or eliminate altogether the longitudinal mode growth. Results from the dispersion relation compare favorably to results obtained from a numerical solution of the eigenvalue problem.

  14. Plutonium Finishing Plant. Interim plutonium stabilization engineering study

    SciTech Connect

    Sevigny, G.J.; Gallucci, R.H.; Garrett, S.M.K.; Geeting, J.G.H.; Goheen, R.S.; Molton, P.M.; Templeton, K.J.; Villegas, A.J.; Nass, R.

    1995-08-01

    This report provides the results of an engineering study that evaluated the available technologies for stabilizing the plutonium stored at the Plutonium Finishing Plant located at the hanford Site in southeastern Washington. Further processing of the plutonium may be required to prepare the plutonium for interim (<50 years) storage. Specifically this document provides the current plutonium inventory and characterization, the initial screening process, and the process descriptions and flowsheets of the technologies that passed the initial screening. The conclusions and recommendations also are provided. The information contained in this report will be used to assist in the preparation of the environmental impact statement and to help decision makers determine which is the preferred technology to process the plutonium for interim storage.

  15. US/USSR Textbook Study Project, Interim Report.

    ERIC Educational Resources Information Center

    Association of American Publishers, New York, NY.

    This interim report, intended to help textbook authors and publishers, describes the results of a project in which American schools critiqued Soviet textbooks and Soviet scholars critiqued American textbooks. Secondary level history and geography texts were the focus of the study. There are five chapters to the report: Background to the Study;…

  16. Project International Emphasis Interim Report, July 1991.

    ERIC Educational Resources Information Center

    Blois, Beverly, Ed.; Williams, Barbara

    Project International Emphasis (PIE), a curriculum development effort involving all 24 colleges in the Virginia Community College System (VCCS), focuses on the infusion of globally oriented components across the academic curriculum and in related career development programs. Activities undertaken during the project's first year included an annual…

  17. Beginning Farmer Sustainable Agriculture Project. Interim Report.

    ERIC Educational Resources Information Center

    Center for Rural Affairs, Hartington, NE.

    This project increases opportunities for beginning farmers to learn about and implement sustainable farming methods through mutual-help discussion groups and continuing education opportunities. Local groups established in six areas in northeast Nebraska in 1991 constitute the Beginning Farmer Support Network (BFSN). At workshops held throughout…

  18. Recommended alternative for interim stabilization of Tank 241-C-103

    SciTech Connect

    Dukelow, G.T.; Turner, D.A.; Grigsby, J.M.

    1995-04-01

    The waste in tank 241-C-103 poses several health and safety risks and potential soil contamination caused by tank leaks. To minimize the risk of contaminating the soil beneath the tank, the pumpable waste liquids are planned to be removed by salt well pumping. In addition to aqueous liquids, this tank is unique because it also contains a layer of degraded PUREX solvent floating on the aqueous liquid. The following three options for removing and storing this separable phase organic solvent have been proposed and studied: transferring the organic solvent and pumpable aqueous liquids using existing salt well pumping equipment and procedures to a double-shell tank (DST) for storage; removing most of the organic solvent using a skimmer pump, then salt well pumping the remaining pumpable liquids to a different DST for storage; removing most of the organic solvent to an aboveground storage tank for eventual treatment or offsite transfer, and then salt well pumping the remaining pumpable liquids to a DST for interim storage. As a result of evaluating these three options and a no pumping option, the recommended action is to transfer both the organic solvent and pumpable aqueous liquid to a DST for storage using existing salt well pumping equipment. The evaluation considers the following criteria: public health and safety, worker safety, environmental compliance, engineering feasibility, and cost. The options compared these factors. Two key areas drove the selection of the recommended approach: the minimization of potential soil contamination from tank leaks caused the (interim stabilization by salt well pumping) options to be rated more highly than the no pumping option; and cost and implementation factors caused the transfer and storage to DST using existing tank farm salt well pumping equipment option to rate higher than the skimming options. Other factors have only a second order effect on the selection process. Evaluation results are described in this report.

  19. 244-AR Vault Interim Stabilization Project Plan

    SciTech Connect

    LANEY, T.

    2000-03-24

    The 244-AR Vault Facility, constructed between 1966 and 1968, was designed to provide lag storage and treatment for the Plutonium-Uranium Extraction Facility (PUREX) tank farm sludges. Tank farm personnel transferred the waste from the 244-AR Vault Facility to B Plant for recovery of cesium and strontium. B Plant personnel then transferred the treatment residuals back to the tank farms for storage of the sludge and liquids. The last process operations, which transferred waste supporting the cesium/strontium recovery mission, occurred in April 1978. After the final transfer in 1978, the 244-AR facility underwent a cleanout. However, 2,271 L (600 gal) of sludge were left in Tank 004AR from an earlier transfer from Tank 241-AX-104. When the cleanout was completed, the facility was placed in a standby status. The sludge had been transferred to Tank 004AR to support Pacific Northwest National Laboratory [PNNL] vitrification work. Documentation of waste transfers suggests that a portion of the sludge may have been moved from Tank 004AR to Tank 002AR in preparation for transfer back to the AX Tank Farm; however, quantities of the sludge that were moved to Tank 002AR from that transfer must be estimated.

  20. Spray combustion stability project

    NASA Technical Reports Server (NTRS)

    Jeng, San-Mou; Litchford, Ron J.

    1992-01-01

    This report summarizes research activity on the Spray Combustion Stability Project, characterizes accomplishments and current status, and discusses projected future work. The purpose is to provide a concise conceptual overview of the research effort to date so the reader can quickly assimilate the gist of the research results and place them within the context of their potential impact on liquid rocket engine design technology.

  1. Advanced nuclear reactor public opinion project. Interim report

    SciTech Connect

    Benson, B.

    1991-07-25

    This Interim Report summarizes the findings of our first twenty in-depth interviews in the Advanced Nuclear Reactor Public Opinion Project. We interviewed 6 industry trade association officials, 3 industry attorneys, 6 environmentalists/nuclear critics, 3 state officials, and 3 independent analysts. In addition, we have had numerous shorter discussions with various individuals concerned about nuclear power. The report is organized into the four categories proposed at our April, 1991, Advisory Group meeting: safety, cost-benefit analysis, science education, and communications. Within each category, some change of focus from that of the Advisory Group has been required, to reflect the findings of our interviews. This report limits itself to describing our findings. An accompanying memo draws some tentative conclusions.

  2. PROJECT W-551 INTERIM PRETREATMENT SYSTEM TECHNOLOGY SELECTION SUMMARY DECISION REPORT AND RECOMMENDATION

    SciTech Connect

    CONRAD EA

    2008-08-12

    This report provides the conclusions of the tank farm interim pretreatment technology decision process. It documents the methodology, data, and results of the selection of cross-flow filtration and ion exchange technologies for implementation in project W-551, Interim Pretreatment System. This selection resulted from the evaluation of specific scope criteria using quantitative and qualitative analyses, group workshops, and technical expert personnel.

  3. Spray combustion stability project

    NASA Technical Reports Server (NTRS)

    Jeng, San-Mou; Litchford, Ron J.

    1990-01-01

    This report summarizes research activity on the Spray Combustion Stability Project, characterizes accomplishments and current status, and discusses projected future work. The purpose is to provide a concise conceptual overview of the research effort so the reader can quickly assimilate the gist of the research results and place them within the context of their potential impact on liquid rocket engine design technology. Therefore, this report does not elaborate on many of the detailed technical aspects of the research program.

  4. DQO Summary Report for 105-N/109-N Interim Safe Storage Project Waste Characterization

    SciTech Connect

    T. A. Lee

    2005-09-15

    The DQO summary report provides the results of the DQO process completed for waste characterization activities for the 105-N/109-N Reactor Interim Safe Storage Project including decommission, deactivate, decontaminate, and demolish activities for six associated buildings.

  5. Idaho Waste Vitrification Facilities Project Vitrified Waste Interim Storage Facility

    SciTech Connect

    Bonnema, Bruce Edward

    2001-09-01

    This feasibility study report presents a draft design of the Vitrified Waste Interim Storage Facility (VWISF), which is one of three subprojects of the Idaho Waste Vitrification Facilities (IWVF) project. The primary goal of the IWVF project is to design and construct a treatment process system that will vitrify the sodium-bearing waste (SBW) to a final waste form. The project will consist of three subprojects that include the Waste Collection Tanks Facility, the Waste Vitrification Facility (WVF), and the VWISF. The Waste Collection Tanks Facility will provide for waste collection, feed mixing, and surge storage for SBW and newly generated liquid waste from ongoing operations at the Idaho Nuclear Technology and Engineering Center. The WVF will contain the vitrification process that will mix the waste with glass-forming chemicals or frit and turn the waste into glass. The VWISF will provide a shielded storage facility for the glass until the waste can be disposed at either the Waste Isolation Pilot Plant as mixed transuranic waste or at the future national geological repository as high-level waste glass, pending the outcome of a Waste Incidental to Reprocessing determination, which is currently in progress. A secondary goal is to provide a facility that can be easily modified later to accommodate storage of the vitrified high-level waste calcine. The objective of this study was to determine the feasibility of the VWISF, which would be constructed in compliance with applicable federal, state, and local laws. This project supports the Department of Energy’s Environmental Management missions of safely storing and treating radioactive wastes as well as meeting Federal Facility Compliance commitments made to the State of Idaho.

  6. PROJECT W-551 INTERIM PRETREATMENT SYSTEM PRECONCEPTUAL CANDIDATE TECHNOLOGY DESCRIPTIONS

    SciTech Connect

    MAY TH

    2008-08-12

    The Office of River Protection (ORP) has authorized a study to recommend and select options for interim pretreatment of tank waste and support Waste Treatment Plant (WTP) low activity waste (LAW) operations prior to startup of all the WTP facilities. The Interim Pretreatment System (IPS) is to be a moderately sized system which separates entrained solids and 137Cs from tank waste for an interim time period while WTP high level waste vitrification and pretreatment facilities are completed. This study's objective is to prepare pre-conceptual technology descriptions that expand the technical detail for selected solid and cesium separation technologies. This revision includes information on additional feed tanks.

  7. Safety evaluation for the interim stabilization of Tank 241-C-103

    SciTech Connect

    Geschke, G.R.

    1995-03-01

    This document provides the basis for interim stabilization of tank 241-C-103. The document covers the removal of the organic liquid layer and the aqueous supernatant from tank 241-C-103. Hazards are identified, consequences are calculated and controls to mitigate or prevent potential accidents are developed.

  8. Evaluation of Hose in Hose Transfer Line Service Life for Hanford's Interim Stabilization Program

    SciTech Connect

    TORRES, T.D.

    2000-08-24

    RPP-6153, Engineering Task Plan for Hose-in-Hose Transfer System for the Interim Stabilization Program, defines the programmatic goals, functional requirements, and technical criteria for the development and subsequent installation of transfer line equipment to support Hanford's Interim Stabilization Program. RPP-6028, Specification for Hose in Hose Transfer Lines for Hanford's Interim Stabilization Program, has been issued to define the specific requirements for the design, manufacture, and verification of transfer line assemblies for specific waste transfer applications. Included in RPP-6028 are tables defining the chemical constituents of concern to which transfer lines will be exposed. Current Interim Stabilization Program planning forecasts that the at-grade transfer lines will be required to convey pumpable waste for as much as three years after commissioning. Prudent engineering dictates that the equipment placed in service have a working life in excess of this forecasted time period, with some margin to allow for future adjustments to the planned schedule. This document evaluates the effective service life of the Hose-in-Hose Transfer Lines, based on information submitted by the manufacturer and published literature. The effective service life of transfer line assemblies is a function of several factors. Foremost among these are process fluid characteristics, ambient environmental conditions, and the manufacturer's stated shelf life. This evaluation examines the manufacturer's certification of shelf life, the manufacturer's certifications of chemical compatibility with waste, and published literature on the effects of exposure to ionizing radiation on the mechanical properties of elastomeric materials to evaluate transfer line service life.

  9. Interim 2001-based national population projections for the United Kingdom and constituent countries.

    PubMed

    Shaw, Chris

    2003-01-01

    This article describes new 2001-based national population projections which were carried out following the publication in September 2002 of the first results of the 2001 Census. These "interim" projections, carried out by the Government Actuary in consultation with the Registrars General, take preliminary account of the results of the Census which showed that the base population used in previous projections was overestimated. The interim projections also incorporate a reduced assumption of net international migration to the United Kingdom, informed by the first results of the 2001 Census and taking account of more recent migration information. The population of the United Kingdom is now projected to increase from an estimated 58.8 million in 2001 to reach 63.2 million by 2026. The projected population at 2026 is about 1.8 million (2.8 per cent) lower than in the previous (2000-based) projections.

  10. Interim stabilization of waste sites using recycled concrete

    SciTech Connect

    Hayward, W.M.; Osborne, W.L.

    1994-12-31

    The Hanford Site, operated by the U.S. Department of Energy (DOE), occupies about 1450 km{sup 2} (560 mile{sup 2}) of the southeastern part of Washington State. The site was established in 1943 to produce plutonium for nuclear weapons using production reactors and chemical processing plants. That mission has now ended and the site is in the early stages of a several-decade cleanup program to address the legacy of retired production facilities and the radioactive and chemical wastes that remain in storage or have been placed in the soil column. One important element of this cleanup is the stabilization and maintenance of the individual soil waste sites and burial grounds until the regulatory and technical requirements for final remediation are executed. Several methods currently are used to stabilize sites that have loose surface contamination. These include stabilization with clean soil followed by revegetation; stabilization by application of shotcrete with or without a chemical biobarrier; and stabilization with soil or rock, then application of a soil sterilant herbicide. The specific method is determined on a site-by-site basis.

  11. 105-H Reactor Interim Safe Storage Project Final Report

    SciTech Connect

    E.G. Ison

    2008-11-08

    The following information documents the decontamination and decommissioning of the 105-H Reactor facility, and placement of the reactor core into interim safe storage. The D&D of the facility included characterization, engineering, removal of hazardous and radiologically contaminated materials, equipment removal, decontamination, demolition of the structure, and restoration of the site. The ISS work also included construction of the safe storage enclosure, which required the installation of a new roofing system, power and lighting, a remote monitoring system, and ventilation components.

  12. Evaluation of Hose in Hose Transfer Line Service Life for Hanfords Interim Stabilization Program

    SciTech Connect

    TORRES, T.D.

    2001-03-23

    RPP-6153, Engineering Task Plan for Hose-in-Hose Transfer System for the Interim Stabilization Program (Torres, 2000a), defines the programmatic goals, functional requirements, and technical criteria for the development and subsequent installation of waste transfer line equipment to support Hanford's Interim Stabilization Program. RPP-6028, Specification for Hose in Hose Transfer Lines for Hanford's Interim Stabilization Program (Torres, 2000b), has been issued to define the specific requirements for the design, manufacture, and verification of transfer line assemblies for specific waste transfer applications associated with Interim Stabilization. Included in RPP-6028 are tables defining the chemical constituents of concern to which transfer lines will be exposed. Current Interim Stabilization Program planning forecasts that the at-grade transfer lines will be required to convey pumpable waste for as much as three years after commissioning, RPP-6028 Section 3.2.7. Performance Incentive Number ORP-05 requires that all the Single Shell Tanks be Interim Stabilized by September 30, 2003. The Tri-Party Agreement (TPA) milestone M-41-00, enforced by a federal consent decree, requires all the Single Shell Tanks to be Interim stabilized by September 30, 2004. By meeting the Performance Incentive the TPA milestone is met. Prudent engineering dictates that the equipment used to transfer waste have a life in excess of the forecasted operational time period, with some margin to allow for future adjustments to the planned schedule. This document evaluates the effective service life of the Hose-in-Hose Transfer Lines, based on information submitted by the manufacturer, published literature and calculations. The effective service life of transfer line assemblies is a function of several factors. Foremost among these are the hose material's resistance to the harmful effects of process fluid characteristics, ambient environmental conditions, exposure to ionizing radiation and the

  13. 78 FR 63276 - Interim Policy, FAA Review of Solar Energy System Projects on Federally Obligated Airports

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-10-23

    ... Federal Aviation Administration Interim Policy, FAA Review of Solar Energy System Projects on Federally... federally obligated airports to construct solar energy systems on airport property. FAA is adopting an... for measuring ocular impact of proposed solar energy systems which are effective upon publication....

  14. Burn site groundwater interim measures work plan.

    SciTech Connect

    Witt, Jonathan L.; Hall, Kevin A.

    2005-05-01

    This Work Plan identifies and outlines interim measures to address nitrate contamination in groundwater at the Burn Site, Sandia National Laboratories/New Mexico. The New Mexico Environment Department has required implementation of interim measures for nitrate-contaminated groundwater at the Burn Site. The purpose of interim measures is to prevent human or environmental exposure to nitrate-contaminated groundwater originating from the Burn Site. This Work Plan details a summary of current information about the Burn Site, interim measures activities for stabilization, and project management responsibilities to accomplish this purpose.

  15. HARD CHROME POLLUTION PREVENTION DEMONSTRATION PROJECT - INTERIM REPORT

    EPA Science Inventory

    In the project, five chromium emission prevention/control devices were tested tha cover the spectrum of prevention/control techniques currently in use in small- and large-size hard chromium electroplating job shops. The Project results show that some of the tested devices had ch...

  16. Reading Between the Lines: Language Indicators Project. Interim Research Summary.

    ERIC Educational Resources Information Center

    Tyler, V. Lynn; Taylor, James S.

    This progress report describes the on-going development of a system to help Americans, especially those who have dealings abroad, to interpret accurately the meaning of messages originating in cultures other than their own. The history, rationale, and methodology of the project are described in detail. Profiles of cultural concepts are provided…

  17. Stabilization of in-tank residuals and external-tank soil contamination: FY 1997 interim report

    SciTech Connect

    Becker, D.L.

    1997-10-09

    This interim report evaluates various ways to stabilize decommissioned waste tanks and contaminated soils at the AX Tank Farm as part of a preliminary evaluation of end-state options for the Hanford tanks. Five technical areas were considered: (1) emplacement of smart grouts and/or other materials, (2) injection of chemical-getters into contaminated soils surrounding tanks (soil mixing), (3) emplacement of grout barriers under and around the tanks, (4) the use of engineered barriers over the tanks, and (5) the explicit recognition that natural attenuation processes do occur. Research topics are identified in support of key areas of technical uncertainty, in each of the five technical areas. Detailed cost/benefit analyses of the recommended technologies are not provided in this evaluation, performed by Sandia National Laboratories, Albuquerque, New Mexico.

  18. Interim report for SNL/NM environmental drilling project

    SciTech Connect

    Wemple, R.P.; Meyer, R.D.; Layne, R.R.

    1994-02-01

    Concern for the environment and cost reduction are the driving forces for a broad effort in government and the private sector to develop new, more cost-effective technologies for characterizing, monitoring and remediating environmental sites. Secondary goals of the characterization, monitoring and remediation (CMR) activity are: minimize secondary waste generation, minimize site impact, protect water tables, and develop methods/strategies to apply new technologies. The Sandia National Laboratories (SNL) project in directional boring for CMR of waste sites with enhanced machinery from the underground utility installation industry was initiated in 1990. Preliminary activities included surveying the directional drilling access needs of various DOE sites, identifying an existing class of machinery that could be enhanced for environmental work through development, and establishing a mutually beneficial working relationship with an industry partner. Since that time the project has tested a variety of prototype machinery and hardware built by the industrial partner, and SNL. The project continues to test and develop the machinery and technique refinements needed for future applications at DOE, DOD, and private sector sites. The original goal of cost-effectiveness is being met through innovation, adaptation, and application of fundamental concepts. Secondary goals are being met via a basic philosophy of ``cut/thrust and compact cuttings without adding large quantities of fluid`` to an environmental problem site. Technology transfer to the private sector is ongoing and ultimately should result in commercial availability of the machinery. Education of regulatory agencies resulting in restructuring appropriate regulatory standards for specification of the horizontal drilling techniques will be a final project goal.

  19. Interim reclamation report, Basalt Waste Isolation project: Boreholes, 1989

    SciTech Connect

    Brandt, C.A.; Rickard, W.H. Jr.; Hefty, M.G.

    1990-03-01

    In 1968, a program was started to assess the feasibility of storing Hanford Site defense waste in deep caverns constructed in basalt. This program was expanded in 1976 to include investigations of the Hanford Site as a potential location for a mined commercial nuclear waste repository. An extensive site characterization program was begun to determine the feasibility of using the basalts beneath the Hanford Site for the repository. Site research focused primarily on determining the direction and speed of groundwater movement, the uniformity of basalt layers, and tectonic stability. Some 98 boreholes were sited, drilled, deepened, or modified by BWIP between 1977 and 1988 to test the geologic properties of the Site. On December 22, 1987, President Reagan signed into law the Nuclear Waste Policy Amendments Act of 1987, which effectively stopped all repository-related activities except reclamation of disturbed lands at the Hanford Site. This report describes the development of the reclamation program for the BWIP boreholes, its implementation, and preliminary estimates of its success. The goal of the reclamation program is to return sites disturbed by the repository program as nearly as practicable to their original conditions using native plant species. 48 refs., 28 figs., 14 tabs.

  20. The pediatric resident training on tobacco project: interim findings.

    PubMed Central

    Hymowitz, Norman; Schwab, Joseph; Haddock, Christopher Keith; Pyle, Sara; Meshberg, Sarah

    2006-01-01

    OBJECTIVES: The Pediatric Residency Training on Tobacco Project is a four-year randomized prospective study of the efficacy of training pediatric residents to intervene on tobacco. At the start of the study (baseline), the pediatric residents uniformly agreed that environmental tobacco smoke (ETS) and tobacco use pose serious threats to the health of young people, and pediatricians should play a leadership role in the antismoking arena. However, very few went beyond advising patients and parents to modify their behavior by providing actual assistance, and many of them lacked necessary tobacco intervention skills and knowledge. We hypothesized that both standard training and special training programs would yield positive changes in intervention skills and activities, although the changes would be greater in residents exposed to the special training condition. In the present report, we present two-year outcome data from the resident tobacco surveys and objective structured clinical examinations (OSCEs) administered to independent waves of third-year residents in each experimental condition at baseline and year 2. METHODS: Fifteen pediatric residency training programs in the New York/New Jersey metropolitan area were assigned randomly to special and standard training conditions (eight to special and seven to standard training). Resident tobacco surveys and OSCEs were administered to third-year residents at the start of the training programs (baseline) and at years 1 and 2 of the study. Comparisons between sequential waves of third-year residents with no (baseline) or two-year exposure to the training programs permitted assessment of changes in resident beliefs, intervention activities and intervention skills within each experimental condition. RESULTS: By year 2, the residents associated with each training condition benefited from the training program, but the annual surveys and OSCEs revealed more significant positive changes for waves of residents in the special

  1. Interim status report of the TMI personnel-dosimetry project

    SciTech Connect

    Rich, B.L.; Alvarez, J.L.; Adams, S.R.

    1981-06-01

    The current 2-chip TLD personnel dosimeter in use at Three Mile Island (TMI) has been shown inadequate for the anticipated high beta/gamma fields during TMI recovery operations in some areas. This project surveyed the available dosimeter systems, set up an Idaho National Engineering Laboratory (INEL) prototype system, and compared this system with those commercial systems that could be made immediately available for comparison. Of the systems tested, the new INEL personnel dosimeter was found to produce the most accurate results for use in recovery operations at TMI-2. The other multiple-chip or multiple-filter systems were found less desirable at present. The most prominent deficiencies in the INEL dosimeter stem from the fact that it lacks a completely automated reader and its x-ray and thermal neutron responses require additional development. A automated prototype reader system may be in operation by the end of CY-1981. Three alternatives for operational dosimetry are discussed. A combination of a modified version of the presently used Harshaw 2-chip dosimeter and the INEL dosimeter is recommended.

  2. Interim Response Action Basin F Liquid Incineration Project Final Draft Human Health Risk Assessment. Volume 1.

    DTIC Science & Technology

    1991-07-01

    91222R02 2ND COPY Interim Response Action Basin F Liquid Incineration Project FINAL DRAFT HUMAN HEALTH RISK ASSESSMENT V olumne I Preplaced Remedial...The Use of OELs and NAAQSs for Calculating Inhalation RfJ)s 9-13 9.4.2.2 Adjustments to Inhalation RfDs 9-14 793C/FM V 7/22/91 TABLE OF CONTENTS...HENDERSON RTHOL THOL HAZELTIN A I LE-- f V , Rocky Mountain WELB DA Arsenal A"ADA AA -AIL- VIM IT RUM Doi T p- 0 Denver kl& MOR SHER DAN r go, "- V

  3. Design requirements document for Project W-465, immobilized low-activity waste interim storage

    SciTech Connect

    Burbank, D.A.

    1998-05-19

    The scope of this Design Requirements Document (DRD) is to identify the functions and associated requirements that must be performed to accept, transport, handle, and store immobilized low-activity waste (ILAW) produced by the privatized Tank Waste Remediation System (TWRS) treatment contractors. The functional and performance requirements in this document provide the basis for the conceptual design of the TWRS ILAW Interim Storage facility project and provides traceability from the program level requirements to the project design activity. Technical and programmatic risk associated with the TWRS planning basis are discussed in the Tank Waste Remediation System Decisions and Risk Assessment (Johnson 1994). The design requirements provided in this document will be augmented by additional detailed design data documented by the project.

  4. PROJECT W-551 DETERMINATION DATA FOR EARLY LAW INTERIM PRETREATMENT SYSTEM SELECTION

    SciTech Connect

    TEDESCHI AR

    2008-08-11

    This report provides the detailed assessment forms and data for selection of the solids separation and cesium separation technology for project W-551, Interim Pretreatment System. This project will provide early pretreated low activity waste feed to the Waste Treatment Plant to allow Waste Treatment Plan Low Activity Waste facility operation prior to construction completion of the Pretreatment and High Level Waste facilities. The candidate solids separations technologies are rotary microfiltration and crossflow filtration, and the candidate cesium separation technologies are fractional crystallization, caustic-side solvent extraction, and ion-exchange using spherical resorcinol-formaldehyde resin. This data was used to prepare a cross-cutting technology summary, reported in RPP-RPT-37740.

  5. PROJECT W-551 SUMMARY INFORMATION FOR EARLY LAW INTERIM PRETREATMENT SYSTEM SELECTION

    SciTech Connect

    AR, TEDESCHI

    2008-08-11

    This report provides summary data for use by the decision board to assess and select the final technology for project W-551, Interim Pretreatment System. This project will provide early pretreated low activity waste feed to the Waste Treatment Plant to allow Waste Treatment Plan Low Activity Waste facility operation prior to construction completion of the Pretreatment and High Level Waste facilities. The candidate solids separations technologies are rotary microfiltration and crossflow filtration, and the candidate cesium separation technologies are fractional crystallization, caustic-side solvent extraction, and ion-exchange using spherical resorcinol-fonnaldebyde resin. This document provides a summary of comparative data against prior weighted criteria to support technology selection. Supporting details and background for this summary are documented in the separate report, RPP-RPT-37741.

  6. Draft environmental assessment -- Test Area North pool stabilization project update

    SciTech Connect

    1997-06-01

    The purpose of this Environmental Assessment (EA) is to update the ``Test Area North Pool Stabilization Project`` EA (DOE/EA-1050) and finding of no significant impact (FONSI) issued May 6, 1996. This update analyzes the environmental and health impacts of a drying process for the Three Mile Island (TMI) nuclear reactor core debris canisters now stored underwater in a facility on the Idaho National Engineering and Environmental Laboratory (INEEL). A drying process was analyzed in the predecision versions of the EA released in 1995 but that particular process was determined to be ineffective and dropped form the Ea/FONSI issued May 6, 1996. The origin and nature of the TMI core debris and the proposed drying process are described and analyzed in detail in this EA. As did the 1996 EA, this update analyzes the environmental and health impacts of removing various radioactive materials from underwater storage, dewatering these materials, constructing a new interim dry storage facility, and transporting and placing the materials into the new facility. Also, as did the 1996 EA, this EA analyzes the removal, treatment and disposal of water from the pool, and placement of the facility into a safe, standby condition. The entire action would take place within the boundaries of the INEEL. The materials are currently stored underwater in the Test Area North (TAN) building 607 pool, the new interim dry storage facility would be constructed at the Idaho Chemical Processing Plant (ICPP) which is about 25 miles south of TAN.

  7. Environmental Assessment -- Test Area North pool stabilization project update

    SciTech Connect

    1997-08-01

    The purpose of this Environmental Assessment (EA) is to update the ``Test Area North Pool Stabilization Project`` EA (DOE/EA-1050) and finding of no significant impact (FONSI) issued May 6, 1996. This update analyzes the environmental and health impacts of a drying process for the Three Mile Island (TMI) nuclear reactor core debris canisters now stored underwater in a facility on the Idaho National Engineering and Environmental Laboratory (INEEL). A drying process was analyzed in the predecision versions of the EA released in 1995 but that particular process was determined to be ineffective and dropped from the EA/FONSI issued May 6, 1996. A new drying process was subsequently developed and is analyzed in Section 2.1.2 of this document. As did the 1996 EA, this update analyzes the environmental and health impacts of removing various radioactive materials from underwater storage, dewatering these materials, constructing a new interim dry storage facility, and transporting and placing the materials into the new facility. Also, as did the 1996 EA, this EA analyzes the removal, treatment and disposal of water from the pool, and placement of the facility into a safe, standby condition. The entire action would take place within the boundaries of the INEEL. The materials are currently stored underwater in the Test Area North (TAN) building 607 pool, the new interim dry storage facility would be constructed at the Idaho Chemical Processing Plant (ICPP) which is about 25 miles south of TAN.

  8. Assessment of marginal stability and permeability of an interim restorative endodontic material.

    PubMed

    Kazemi, R B; Safavi, K E; Spångberg, L S

    1994-12-01

    The purpose of this study was to assess the marginal stability and permeability of a new interim restorative endodontic material, Tempit (Centrix Inc., Milford, Conn.), and to compare the findings with the results of two commonly used restorative endodontic materials, Cavit (Premier Dental Products Co., Philadelphia, Pa.) and IRM (Intermediate Restorative Material Capsules, The Caulk Co., Division of Dentsply International Inc., Milford, Del.) This study was performed in several steps. First, the endodontic access cavities were prepared and restored on 80 extracted mandibular molars. The samples were exposed to methylene blue dye solution for 6 days, thermocycled, and sectioned; the dye penetration and diffusion were measured along the margins and into the body of the materials. The second experiment was a special study performed in standardized glass tubes to better evaluate the marginal and body dye penetration into the materials by increasing the length of the fillings. To eliminate the possibility of hygroscopic setting mechanisms of materials, samples were first allowed to set under water before dye was introduced. Cavit and Tempit showed a substantial amount of dye diffusion into the body of the materials. Cavit exhibited the best sealing ability at all times. The marginal and body dye penetration were significantly different for the Tempit material in all experiments than Cavit (p < 0.001). IRM demonstrated the least body penetration of all three materials (p < 0.001) but had a substantial marginal leakage not significantly different from the results of the Tempit material (p = 0.6 and p = 0.1).(ABSTRACT TRUNCATED AT 250 WORDS)

  9. Interim Principals.

    ERIC Educational Resources Information Center

    Beem, Kate

    2003-01-01

    An interim principal can buy a school district time to land a permanent successor. Also lists where to find an interim principal; the interim's steadying influence; Bob Wallace's wild ride as an interim principal in post-retirement; and Roger Prosise's rationale for turning to an interim appointment. (MLF)

  10. North American Carbon Program (NACP) Interim Synthesis Project: Regional Forward Model Intercomparision (Invited)

    NASA Astrophysics Data System (ADS)

    Post, M.; Huntzinger, D. N.; Michalak, A. M.; Wei, Y.; Jacobson, A. R.; Cook, R. B.; Regional-Interim Synthesis Participants, N.; Regional/Continental Interim-Synthesis Team

    2010-12-01

    Our understanding of how carbon is exchanged between terrestrial ecosystems and the atmosphere is gained from direct observations and experiments, as well as through modeling activities. Terrestrial biosphere models (TBMs) have become an integral tool for extrapolating local observations and understanding to larger regions. Although models vary in their specific goals and approaches, their central role within carbon cycle research is to provide a better understanding of the mechanisms currently controlling carbon exchange. Recently, the North American Carbon Program (NACP) organized several interim-synthesis activities (http://nacp.ornl.gov/ int_synthesis.shtml) to evaluate and inter-compare models and observations at local to continental scales for the time period of 2000 through 2005. Here, we present the results from the TBMs collected as part of the regional and continental interim-synthesis (RCIS) activities. The primary objective of this work is to synthesize and compare 19 TBMs to assess current understanding of the terrestrial carbon cycle in North America. Thus, the RCIS focuses on model simulations and data currently available from analyses that have been completed by ongoing NACP projects and other recently published studies. Bringing model estimates (and available data) together that incorporate a wide range of modeling approaches provides a valuable assessment of the current state of understanding of regional carbon flux across North America. The TBM flux estimates are evaluated over different land cover regions of North America, and with respect to photosynthetic formulation, soil carbon dynamics, environmental driving variables, and temporal resolution. Model estimates are also compared to spatially explicit inventory-based estimates of cropland productivity. There is significant disagreement among the models in their estimates of gross primary production (GPP), with estimates during the peak growing season differing by over 300 gC/(m2 month) in

  11. Summation by parts, projections, and stability

    NASA Technical Reports Server (NTRS)

    Olsson, Pelle

    1993-01-01

    We have derived stability results for high-order finite difference approximations of mixed hyperbolic-parabolic initial-boundary value problems (IBVP). The results are obtained using summation by parts and a new way of representing general linear boundary conditions as an orthogonal projection. By slightly rearranging the analytic equations, we can prove strict stability for hyperbolic-parabolic IBVP. Furthermore, we generalize our technique so as to yield strict stability on curvilinear non-smooth domains in two space dimensions. Finally, we show how to incorporate inhomogeneous boundary data while retaining strict stability. Using the same procedure one can prove strict stability in higher dimensions as well.

  12. Evaluation and Research Center for Project Head Start, University of South Carolina. Interim Evaluation Report.

    ERIC Educational Resources Information Center

    Friedman, Myles I.

    This document is an interim evaluation report of language development curriculums in full year Head Start programs operating in the five state area the Research and Evaluation Center serves. One experimental study in language development carried on in cooperation with the Texas and Tulane centers is reported in depth. The study was implemented in…

  13. Interim Expertise

    ERIC Educational Resources Information Center

    Anyaso, Hilary Hurd

    2009-01-01

    The Registry for College and University Presidents places former executives in interim presidential and other senior-level posts and is familiar with the challenges interim executives and institutions encounter in times of leadership transitions. However, the one big advantage interims bring to institutions, says Registry Vice President Kevin J.…

  14. 13 CFR 120.890 - Source of interim financing.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 13 Business Credit and Assistance 1 2010-01-01 2010-01-01 false Source of interim financing. 120... Development Company Loan Program (504) Interim Financing § 120.890 Source of interim financing. A Project may use interim financing for all Project costs except the Borrower's contribution. Any source...

  15. Interim Particulate Matter Test Method for the Determination of Particulate Matter from Gas Turbine Engines, SERDP Project WP-1538 Final Report

    EPA Science Inventory

    Under Project No. WP-1538 of the Strategic Environmental Research and Development Program, the U. S. Air Force's Arnold Engineering Development Center (AEDC) is developing an interim test method for non-volatile particulate matter (PM) specifically for the Joint Strike Fighter (J...

  16. Glassy slags for minimum additive waste stabilization. Interim progress report, May 1993--February 1994

    SciTech Connect

    Feng, X.; Wronkiewicz, D.J.; Bates, J.K.; Brown, N.R.; Buck, E.C.; Dietz, N.L.; Gong, M.; Emery, J.W.

    1994-05-01

    Glassy slag waste forms are being developed to complement glass waste forms in implementing Minimum Additive Waste Stabilization (MAWS) for supporting DOE`s environmental restoration efforts. The glassy slag waste form is composed of various crystalline and metal oxide phases embedded in a silicate glass phase. The MAWS approach was adopted by blending multiple waste streams to achieve up to 100% waste loadings. The crystalline phases, such as spinels, are very durable and contain hazardous and radioactive elements in their lattice structures. These crystalline phases may account for up to 80% of the total volume of slags having over 80% metal loading. The structural bond strength model was used to quantify the correlation between glassy slag composition and chemical durability so that optimized slag compositions were obtained with limited crucible melting and testing. Slag compositions developed through crucible melts were also successfully generated in a pilot-scale Retech plasma centrifugal furnace at Ukiah, California. Utilization of glassy slag waste forms allows the MAWS approach to be applied to a much wider range of waste streams than glass waste forms. The initial work at ANL has indicated that glassy slags are good final waste forms because of (1) their high chemical durability; (2) their ability to incorporate large amounts of metal oxides; (3) their ability to incorporate waste streams having low contents of flux components; (4) their less stringent requirements on processing parameters, compared to glass waste forms; and (5) their low requirements for purchased additives, which means greater waste volume reduction and treatment cost savings.

  17. Interim report

    SciTech Connect

    1985-06-01

    This Interim Report summarizes the research and development activities of the Superconducting Super Collider project carried out from the completion of the Reference Designs Study (May 1984) to June 1985. It was prepared by the SSC Central Design Group in draft form on the occasion of the DOE Annual Review, June 19--21, 1985. Now largely organized by CDG Divisions, the bulk of each chapter documents the progress and accomplishments to date, while the final section(s) describe plans for future work. Chapter 1, Introduction, provides a basic brief description of the SSC, its physics justification, its origins, and the R&D organization set up to carry out the work. Chapter 2 gives a summary of the main results of the R&D program, the tasks assigned to the four magnet R&D centers, and an overview of the future plans. The reader wishing a quick look at the SSC Phase I effort can skim Chapter 1 and read Chapter 2. Subsequent chapters discuss in more detail the activities on accelerator physics, accelerator systems, magnets and cryostats, injector, detector R&D, conventional facilities, and project planning and management. The magnet chapter (5) documents in text and photographs the impressive progress in successful construction of many model magnets, the development of cryostats with low heat leaks, and the improvement in current-carrying capacity of superconducting strand. Chapter 9 contains the budgets and schedules of the COG Divisions, the overall R&D program, including the laboratories, and also preliminary projections for construction. Appendices provide information on the various panels, task forces and workshops held by the CDG in FY 1985, a bibliography of COG and Laboratory reports on SSC and SSC-related work, and on private industrial involvement in the project.

  18. Development Education. A Brief Description of the Project and an Interim Definition of Development Education.

    ERIC Educational Resources Information Center

    Haarhuis, J. Mistrate; And Others

    In this five-part essay, a project concerning development education at the secondary school level in the Netherlands is discussed. The project, entitled Educational Project Development Cooperation (EPOS), will work closely with schools and develop teaching-learning packages and model core curricula to teach students about the moral responsibility…

  19. An Evaluation of ESEA Title III Projects, Fiscal Year 1972. Interim Report.

    ERIC Educational Resources Information Center

    Wilson, Jerusa; And Others

    This report contains descriptions and progress of five projects in the District of Columbia partially or wholly funded by ESEA Title III: (1) The Columbia Road Preschool Pilot Project, a second-year experimental effort designed to serve as a model school providing an experimental setting for early childhood educational programs; (2) The Montessori…

  20. An Evaluation of Jamestown Community College PROJECT HERCULES: First Stage Results. Interim Report.

    ERIC Educational Resources Information Center

    Olmstead, Joseph A.; Bushnell, David S.

    An evaluation study was conducted by Jamestown Community College (JCC) to determine the effects of PROJECT HERCULES. This demonstration project was initiated in 1974 to release selected staff members from routine tasks in order to assess community training and educational needs, communicate these needs to appropriate college personnel, and follow…

  1. The Social Security Administration's Youth Transition Demonstration Projects: Interim Report on Transition WORKS

    ERIC Educational Resources Information Center

    Fraker, Thomas; Black, Alison; Mamun, Arif; Manno, Michelle; Martinez, John; O'Day, Bonnie; O'Toole, Meghan; Rangarajan, Anu; Reed, Debbie

    2011-01-01

    The Social Security Administration is funding a random assignment evaluation of six demonstration projects to improve employment and other outcomes for youth ages 14 to 25 who are either receiving disability benefits or are at high risk of receiving them in the future. This report reviews the Youth Transition Demonstration (YTD) projects, located…

  2. Starting Right: Early Intervention Demonstration Projects, July 1989 to December 1990. Interim Report.

    ERIC Educational Resources Information Center

    Koroloff, Nancy

    This report describes four demonstration projects, funded from July 1989 to December 1990 in Oregon, on early identification and prevention of mental and emotional disorders in children. The intention of the projects was to find ways to identify children at risk of suffering emotional disorders and to intervene early enough to prevent these…

  3. INDEPENDENT TECHNICAL REVIEW OF THE C-400 INTERIM REMEDIAL PROJECT PHASE I RESULTS, PADUCAH, KENTUCKY

    SciTech Connect

    Looney, B.; Rossabi, J.; Stewart,L.; Richards, W.

    2010-10-29

    The groundwater and soil in the vicinity of the C-400 Building at the Paducah Gaseous Diffusion Plant (PGDP), is contaminated with substantial quantities of industrial solvents, primarily trichoroethene (TCE). This solvent 'source' is recognized as a significant challenge and an important remediation target in the overall environmental cleanup strategy for PGDP. Thus, the cleanup of the C-400 TCE Source is a principal focus for the Department of Energy (DOE) and its contractors, and for PGDP regulators and stakeholders. Using a formal investigation, feasibility study and decision process, Electrical Resistance Heating (ERH) was selected for the treatment of the soil and groundwater in the vicinity of C-400. ERH was selected as an interim action to remove 'a significant portion of the contaminant mass of TCE at the C-400 Cleaning Building area through treatment' with the longer term goal of reducing 'the period the TCE concentration in groundwater remains above its Maximum Contaminant Level (MCL).' ERH is a thermal treatment that enhances the removal of TCE and related solvents from soil and groundwater. The heterogeneous conditions at PGDP, particularly the high permeability regional gravel aquifer (RGA), are challenging to ERH. Thus, a phased approach is being followed to implement this relatively expensive and complex remediation technology. Conceptually, the phased approach encourages safety and efficiency by providing a 'lessons learned' process and allowing appropriate adjustments to be identified and implemented prior to follow-on phase(s) of treatment. More specifically, early deployment targeted portions of the challenging RGA treatment zone with relatively little contamination reducing the risk of adverse collateral impacts from underperformance in terms of heating and capture. Because of the importance and scope of the C-400 TCE source remediation activities, DOE chartered an Independent Technical Review (ITR) in 2007 to assess the C-400 ERH plans prior

  4. Environmental permits and approvals plan for high-level waste interim storage, Project W-464

    SciTech Connect

    Deffenbaugh, M.L.

    1998-05-28

    This report discusses the Permitting Plan regarding NEPA, SEPA, RCRA, and other regulatory standards and alternatives, for planning the environmental permitting of the Canister Storage Building, Project W-464.

  5. Interim 2003-based national population projections for the United Kingdom and constituent countries.

    PubMed

    Shaw, Chris

    2004-01-01

    The 2003-based national population projections, carried out by the Government Actuary in consultation with the Registrars General, and using essentially the same underlying assumptions as for the previous 2002-based projections, show the population of the United Kingdom rising from 59.6 million in 2003, passing 60 million during 2005, to reach 65.7 million by 2031. Longer-term projections suggest the population will peak around 2050 at nearly 67 million and then very gradually start to fall. The population will become older with the median age expected to rise from 38.4 years in 2003 to 43.3 years by 2031. In 2003, there were around 700 thousand (six per cent) more children aged under 16, than people of state pensionable age. However, from 2007, the population of pensionable age is projected to exceed the number of children.

  6. Project TALENT's Nonrespondent Follow-up Survey: The 10th Grade Special Sample. Interim Report.

    ERIC Educational Resources Information Center

    Carrel, Kathleen S.; And Others

    Described are procedures used in the location of a sample of individuals not responding to follow-up questionnaires, eleven years after they were originally interviewed in 1960 as 10th graders. The individuals in question were a subset of more than 400,000 9th, 10th, 11th and 12th grade students used in Project TALENT's longitudinal study of the…

  7. Project VEHTS (Versatile Employment of Health-Trained Servicemen). First Interim Report.

    ERIC Educational Resources Information Center

    Nathan (Robert R.) Associates, Inc., Washington, DC.

    Project VEHTS (Versatile Employment of Health Trained Servicemen) is demonstrating how civilian hospitals can employ and use more effectively the thousands of medically-trained servicemen who are released each year by the Armed Forces. A system of recruitment and placement of veterans at Cook County Hospital, Chicago, was designed and implemented.…

  8. INTERIM EPA GUIDANCE FOR GEOSPATIAL-RELATED QUALITY ASSURANCE PROJECT PLANS

    EPA Science Inventory

    This guidance supplements EPA Guidance for Quality,Assurance Project Plans (EPA QA/G-5), in that the focus here is on collection and use of geospatial rather than other environmental data (e.g., strictly chemical or biological data), including unique aspects of data storage, retr...

  9. Test Area North Pool Stabilization Project: Environmental assessment

    SciTech Connect

    1996-05-01

    The Test Area North (TAN) Pool is located within the fenced TAN facility boundaries on the Idaho National Engineering Laboratory (INEL). The TAN pool stores 344 canisters of core debris from the March, 1979, Three Mile Island (TMI) Unit 2 reactor accident; fuel assemblies from Loss-of-Fluid Tests (LOFT); and Government-owned commercial fuel rods and assemblies. The LOFT and government owned commercial fuel rods and assemblies are hereafter referred to collectively as {open_quotes}commercial fuels{close_quotes} except where distinction between the two is important to the analysis. DOE proposes to remove the canisters of TMI core debris and commercial fuels from the TAN Pool and transfer them to the Idaho Chemical Processing Plant (ICPP) for interim dry storage until an alternate storage location other than at the INEL, or a permanent federal spent nuclear fuel (SNF) repository is available. The TAN Pool would be drained and placed in an industrially and radiologically safe condition for refurbishment or eventual decommissioning. This environmental assessment (EA) identifies and evaluates environmental impacts associated with (1) constructing an Interim Storage System (ISS) at ICPP; (2) removing the TMI and commercial fuels from the pool and transporting them to ICPP for placement in an ISS, and (3) draining and stabilizing the TAN Pool. Miscellaneous hardware would be removed and decontaminated or disposed of in the INEL Radioactive Waste Management Complex (RWMC). This EA also describes the environmental consequences of the no action alternative.

  10. San Joaquin River Up-Stream DO TMDL Project Task 4: MonitoringStudy Interim Task Report #3

    SciTech Connect

    Stringfellow, William; Borglin, Sharon; Dahlgren, Randy; Hanlon,Jeremy; Graham, Justin; Burks, Remie; Hutchinson, Kathleen

    2007-03-30

    Lander Avenue.This data is specifically being collected to provide data for the Task 6Modeling effort. Task 4 provides input and calibration data for flow andWQ modeling associated with the low DO problems in the SJR watershed,including modeling on the linkage among nutrients, algae, and low DO.Task 4 is providing a higher volume of high quality and coherent data tothe modeling team than was available in the past for the upstream SJR.The monitoring and research activities under Task 4 are integrated withthe Modeling effort (Task 6) and are not designed to be a stand aloneprogram. Although, the majority of analysis of the Task 4 data isoccurring as part of the Task 6 Modeling program, analysis of Task 4 dataindependently of the modeling effort is also an important component ofthe DO TMDL Project effort. In this report, we present the results ofmonitoring and research conducted under Task 4. The major purposes ofthis report are to 1) document activities undertaken as part of theDOTMDL Project; 2) organize electronic data for delivery to Stateagencies, stakeholders and principal investigators (cooperators) on theDO TMDL Project; 3) provide a summary analysis of the data for referenceand to assist stakeholders in planning watershed activities inresponse tothe DO TMDL requirements; and 5) provide a preliminary scientificinterpretation independently of the Task 6 Modeling effort. Due to theextensive scope of theTask 4 portion of the DO TMDL Project, the Task 4March 2007 Interim Report is divided into a numbers of chapters andassociated appendixes designed to be able to stand1-3 independently ofeach other. The purpose of this chapter is to provide an overview of Task4 data collection and to explain the structure of the overallreport.

  11. Interim reclamation report, Basalt Waste Isolation Project Near Surface Test Facility 1990

    SciTech Connect

    Brandt, C.A.; Rickard, W.H. Jr.; Hefty, M.G.; Cadoret, N.A.

    1991-01-01

    This report describes the development of the reclamation project for the Hanford Site Near Surface Test Facility (NSTF), its implementation, and preliminary estimates of its success. The goal of the reclamation project is to return disturbed sites as nearly as practicable to their original conditions using native species. Gable Mountain is dominated by two plant communities: a big sagebrush (Artemisia tridentata) -- Sandberg's bluegrass (Poa sandbergii) community and a stiff sagebrush (Artemisia rigida) -- Sandberg's bluegrass community. Disassembly of the site installations began on March 15, 1988, and the site was returned to original contours by December 12, 1988. Two separate revegetation methods were employed at the NSTF to meet differing site constraints. Vegetative cover and density in the revegetation plots were assessed in April 1989 and again in June 1989 and 1990. It is extremely unlikely that the sand pit, borrow pit, box cuts, generator pad area, or ventilation fan area will reach the reclamation objectives set for these areas within the next 50 years without further intervention. These areas currently support few living plants. Vegetation on revegetated native soils appears to be growing as expected. Vegetation growth on the main waterline is well below the objective. To date, no shrubs have grown on the area, growth of native grasses is well below the objective, and much of the area has been covered with the pit run material, which may not support adequate growth. Without further treatments, the areas without the pit run material will likely revert to a nearly pure cheatgrass condition. 44 refs., 13 figs., 7 tabs.

  12. Medium Truck Duty Cycle Data from Real-World Driving Environments: Project Interim Report

    SciTech Connect

    Franzese, Oscar; Lascurain, Mary Beth; Capps, Gary J

    2011-01-01

    Since the early part of the 20th century, the US trucking industry has provided a safe and economical means of moving commodities across the country. At the present time, nearly 80% of the US domestic freight movement involves the use of trucks. The US Department of Energy (DOE) is spearheading a number of research efforts to improve heavy vehicle fuel efficiencies. This includes research in engine technologies (including hybrid and fuel cell technologies), lightweight materials, advanced fuels, and parasitic loss reductions. In addition, DOE is developing advanced tools and models to support heavy vehicle truck research, and is leading the 21st Century Truck Partnership whose stretch goals involve a reduction by 50% of the fuel consumption of heavy vehicles on a ton-mile basis. This Medium Truck Duty Cycle (MTDC) Project is a critical element in DOE s vision for improved heavy vehicle energy efficiency and is unique in that there is no other national database of characteristic duty cycles for medium trucks. It involves the collection of real-world data for various situational characteristics (rural/urban, freeway/arterial, congested/free-flowing, good/bad weather, etc.) and looks at the unique nature of medium trucks drive cycles (stop-and-go delivery, power takeoff, idle time, short-radius trips), to provide a rich source of data that can contribute to the development of new tools for fuel efficiency and modeling, provide DOE a sound basis upon which to make technology investment decisions, and provide a national archive of real-world-based medium-truck operational data to support heavy vehicle energy efficiency research. The MTDC project involves a two-part field operational test (FOT). For the Part-1 FOT, three vehicles, each from two vocations (urban transit and dry-box delivery) were instrumented for one year of data collection. The Part-2 FOT will involve the towing/recovery and utility vocations. The vehicles participating in the MTDC project are doing so

  13. Leading Curriculum Innovation in Primary Schools Project: An Interim Report on School Leaders' Roles in Curriculum Development in England

    ERIC Educational Resources Information Center

    Brundrett, Mark; Duncan, Diane; Rhodes, Christopher

    2010-01-01

    This article provides an interim report on a two-phase study of curriculum innovation in primary schools in England during one of the most significant periods of change for the last two decades. More specifically, the study addresses the challenges to school leaders created by the Rose Review of the primary curriculum. This article presents and…

  14. San Francisquito Creek Stabilization at Bonde Weir Project

    EPA Pesticide Factsheets

    Information about the SFBWQP San Francisquito Creek Stabilization at Bonde Weir Project, part of an EPA competitive grant program to improve SF Bay water quality focused on restoring impaired waters and enhancing aquatic resources.

  15. Stabilizing a Bicycle: A Modeling Project

    ERIC Educational Resources Information Center

    Pennings, Timothy J.; Williams, Blair R.

    2010-01-01

    This article is a project that takes students through the process of forming a mathematical model of bicycle dynamics. Beginning with basic ideas from Newtonian mechanics (forces and torques), students use techniques from calculus and differential equations to develop the equations of rotational motion for a bicycle-rider system as it tips from…

  16. Integrated project management plan for the Plutonium Finishing Plant stabilization and deactivation project

    SciTech Connect

    SINCLAIR, J.C.

    1999-05-03

    This document sets forth the plans, organization, and control systems for managing the PFP Stabilization and Deactivation Project, and includes the top level cost and schedule baselines. The project includes the stabilization of Pu-bearing materials, storage, packaging, and transport of these and other nuclear materials, surveillance and maintenance of facilities and systems relied upon for storage of the materials, and transition of the facilities in the PFP Complex.

  17. Grant Computer Managed Individualized Learning Project (PLAN*). The interim Evaluation Report (July 1, 1972-June 30, 1973).

    ERIC Educational Resources Information Center

    Saint Louis Board of Education, MO.

    Four instructional management programs, the Duluth Project, IGE Project, the IPI Project, and PLAN Project, were evaluated, contrasted, and compared with development of an inhouse program for the St. Louis public schools. The main criteria were: developmental and operational costs; degree of individualization; the use of behavioral objectives,…

  18. Paddys Run Streambank Stabilization Project at the Fernald Preserve, Harrison, OH

    SciTech Connect

    Hooten, Gwendolyn; Hertel, Bill; Homer, John

    2016-03-01

    The Fernald Preserve is a former uranium-processing plant that underwent extensive remediation pursuant to CERCLA and is now managed by the US DOE Office of Legacy Management. While remediation of buildings and soil contamination was completed in 2006, aquifer remediation is ongoing. Paddys Run is a second-order stream that runs to the south along the western side of the Fernald Preserve. The Paddys Run watershed encompasses nearly 41 km2 (16 mi2), including most of the Fernald site. Field personnel conducting routine site inspections in March 2014 observed that Paddys Run was migrating east via bank erosion into the “Pit 3 Swale,” an area of known surface-water contamination. The soil there was certified pursuant to site regulatory agreements and meets all final remediation levels. However, weekly surface-water monitoring is conducted from two puddles within the swale area, when water that exceeds the final remediation levels is present. Paddys Run had migrated east approximately 4 m (13 ft) in 2 years and was approximately 29 m (95 ft) from the sample location. This rapid migration threatened existing conditions that allowed for continued monitoring of the swale area and also threatened Paddys Run water quality. Therefore, DOE and regulators determined that the east bank of Paddys Run required stabilization. This was accomplished with a design that included the following components: relocation of approximately 145 m (475 ft) of streambed 9 m (30 ft) west, installation of a rock toe along the east bank, installation of two cross-vane in-stream grade-control structures, stabilization of a portion of the east bank using soil encapsulated lifts, and regrading, seeding, and planting within remaining disturbed areas. In an effort to take advantage of low-flow conditions in Paddys Run, construction was initiated in September 2014. Weather delays and subsurface flow within the Paddys Run streambed resulted in an interim shutdown of the project area in December 2014

  19. School Capital Manual. An Interim Guide for School Boards, Administrators, Facility Planners and Consultants Who Engage in School Building Projects.

    ERIC Educational Resources Information Center

    Alberta Dept. of Education, Edmonton.

    This manual is intended for use by the Alberta, Canada, school boards, administrators, consultants, education staff, and other individuals involved in school building projects. The purpose of the School Capital Plan, funding, and Alberta Education's funding framework are detailed. The school building project components of the School Capital Plan…

  20. Logical Operations Instruction in the Preschool. Interim Progress Report - Hatch Research Project 142-1769, March, 1973.

    ERIC Educational Resources Information Center

    Burke-Merkle, Ann M.; And Others

    The original task of this project, the development of a preschool curriculum based on Piagetian theory, was broadened to include the development of a teacher training program supporting the curriculum. During the first year of the project the following has been accomplished: (1) a coded card file of approximately 100 curriculum-specific…

  1. Plume Mitigation for Mars Terminal Landing: Soil Stabilization Project

    NASA Technical Reports Server (NTRS)

    Hintze, Paul E.

    2014-01-01

    Kennedy Space Center (KSC) has led the efforts for lunar and Martian landing site preparation, including excavation, soil stabilization, and plume damage prediction. There has been much discussion of sintering but until our team recently demonstrated it for the lunar case there was little understanding of the serious challenges. Simplistic sintering creates a crumbly, brittle, weak surface unsuitable for a rocket exhaust plume. The goal of this project is to solve those problems and make it possible to land a human class lander on Mars, making terminal landing of humans on Mars possible for the first time.

  2. Hydrosphere Project.

    DTIC Science & Technology

    This final report summarizes the seven foot Hydrosphere Project. During the course of this program, three Interim Reports were submitted. Interim...to the final assembly of the seven foot Hydrosphere . This final report includes a brief outline of each of the above noted Interim Reports, as well as

  3. Advanced-Level Testing of Foreign Language Proficiency: An Interim Report of the Post A-Level Spanish Project.

    ERIC Educational Resources Information Center

    Ife, Anne E.; Standish, Peter

    This is a preliminary report concerning the development of tests which measure the linguistic ability in Spanish of English students at the beginning of their post A-level courses. The Palspan (Post A-level Spanish project) pilot test battery is comprised of five sub-tests of between 45 and 90 minutes in length which test for speaking, listening,…

  4. Project TALENT Five-Year Follow-Up Studies, Predicting Development of Young Adults. Interim Report 5.

    ERIC Educational Resources Information Center

    Cooley, William W.; Lohnes, Paul R.

    The primary purpose of this monograph is to describe the relationship between adolescent personality and the educational and vocational development of young adults, criteria for the latter being developed from the Project TALENT follow-up studies. This relationship seeking is set in a context of career development theory and a concern for guidance…

  5. The Intentional Interim

    ERIC Educational Resources Information Center

    Nugent, Patricia A.

    2011-01-01

    The author spent years in central-office administration, most recently in an interim position. Some interim administrators simply see themselves as placeholders until the real deal is hired, giving the organization the opportunity to coast. There are others who see themselves as change agents and cannot wait to undo or redo what their predecessor…

  6. Interim response action basin F liquid incineration project final draft human health risk assessment. Volume 1. Final draft report

    SciTech Connect

    1991-07-01

    This document is a comprehensive, multiple exposure pathway, human health risk assessment prepared for the proposed Basin F Liquid Incineration Project. The submerged quench incinerator will treat Basin F liquid and hydrazine rinse water. The objective of the risk assessment is to establish chemical emission limits which are protective of human health. Average and maximum lifetime daily intakes were calculated for adults, children, and infants in four maximum exposure scenarios under base case and sensitivity case emissions condition. It was concluded that the incineration facility poses neither carcinogenic nor noncarcinogenic risk to any sensitive population. The assessment is divided into: (1) Incineration facility description; (2) Description of surrounding area; (3) Process of pollutant identification and selection; and (4) Determination of emission rates from incineration facility.

  7. Development of an EMF Measurments Database, EMF Rapid Program, Project #5, Interim Report: April 1995-December 1996

    SciTech Connect

    T. Dan Bracken, Inc.

    1998-03-01

    The EMF Measurements Database project is being implemented by T. Dan Bracken, Inc. as part of the EMF Research and Public Information Dissemination (EMF RAPID) Program. The Database is a collection of data sets that relate to measurement of electric and/or magnetic fields. This report describes activities during the period January 1997 to March 1998. Primary goals for the EMF Measurements Database are to develop a database structure that can accommodate the diversity of EMF data sets, provide guidance for production of future EMF data sets, and serve as an accessible repository of EMF measurement data. Specific objectives of the EMF Measurements Database are: o to presewe study descriptions, results and data; o to provide readily accessible, well-documented data; and - o to facilitate communication among researchers. In addition, the EMF Measurements Database will encourage additional analysis of existing data sets, facilitate analysis of data from multiple projects, support design of new studies, and permit future issues in EMF exposure assessment to be addressed with existing data. Preservation of study descriptions and data is accomplished with a formal, but open, structure. Specifications have been developed for the various elements of the database. Each data set in the database is formally described by a metadata file. The structured metadata file describes the origin, development, logical and physical structure, and distribution mechanism for each data set. The metadata for each data set is generated according to a specification developed for the EMF Measurements Database. The actual measurement data is contained in data products for each data set. The number and type of data product will vary by data set. Most of the data products available from the EMF Measurements Database can be downloaded from an Internet site. For some data sets, the data products will be maintained by other patties who may have their own access procedures.

  8. Computer-Based Exercises in Anemia and Chest Pain Diagnosis: An Interim Evaluation of the PlanAlyzer Project

    PubMed Central

    Lyon, Harold C.; Healy, James C.; Bell, James R.; O'Donnell, Joseph F.; Hirai, Frank; Moore-West, Margaret; Cornwell, Gibbons G.; Brooks, W. Blair; Spackman, Kent A.; Beck, J. Robert

    1990-01-01

    PlanAlyzer is a microcomputer-based, self-paced, case-based, event-driven system for medical education. Aimed at the second year medical student, PlanAlyzer presents cases, elicits and critiques a student's approach to the diagnosis of two common medical disorders: anemias and chest pain. PlanAlyzer uses text, hypertext, images and critiquing theory. Students were randomized, one half becoming the experimental group who received the interactive PlanAlyzer cases in anemia, the other half becoming the controls who received the exact same content material in a text format. Later in each year there was a crossover, the controls becoming the experimentals for a similar intervention with the cardiology PlanAlyzer cases. Preliminary results at the end of the first two trials shows that the programs have achieved most of the proposed instructional objectives, plus some significant efficiency and economy gains. 96 faculty hours of classroom time were saved by using PlanAlyzer in their place, while, maintaining high student achievement. In terms of student proficiency and efficiency, the 176 students in the trial were able to accomplish the project's instructional objectives, and the experimentals accomplished this in less time than the controls. The research suggests additional inquiry in several areas: better evaluation instruments to measure the problem solving skills PlanAlyzer was designed to teach; use of hypertext PlanAlyzer cases to find if such a mode results in performance and/or efficiency differences; through the addition of interactive video, broaden PlanAlyzer to include additional behaviors subsumed under the topic of clinical problem solving, such as patient management strategies and the role of patients' affective behavior and non-verbal cues in the data gathering process.

  9. Development of an EMF Measurements Database, EMF Rapid Program, Project #5, Interim Report: April 1995-December 1996

    SciTech Connect

    T. Dan Bracken, Inc.

    1997-04-01

    The EMF measurement data sets in existence today were compiled with varying goals and techniques. Consequently, they have different information content as well as varying logical and physical structure. Future studies will continue to pursue varying goals and utilize techniques that cannot be known in advance. Primary goals for the EMF Measurements Database developed under the Department of Energy EMF RAPID Program are to develop a database structure that can accommodate the diversity of EMF data sets, provide guidance for production of future EMF data sets, and serve as an accessible repository of EMF measurement data. Specific objectives of the EMF Measurements Database are: o to preserve study descriptions, results and data; o to provide readily accessible, well-documented data; and o to facilitate communication among researchers. In addition, the EMF Measurements Database will encourage additional analysis of existing data sets, facilitate analysis of data from multiple projects, support design of new studies, and permit future issues in EMF exposure assessment to be addressed with existing data. Preservation of study descriptions and data is accomplished with a formal, but open, structure. Specifications have been developed for the various elements of the database. Each data set in the database is formally described by a metadata file. The structured metadata file describes the origin, development, logical and physical structure and distribution mechanism for each data set. The metadata for each data set is generated according to a specification developed for the EMF Measurements Database. The actual measurement data is contained in data Products for each data set. The number and type of data product will vary by data set. Most of the data products in the possession of the EMF Measurements Database are available for download from an Internet site. For some data sets, the data products will be maintained by other parties who may have their own access procedures

  10. Elder Abuse Demonstration Project. Third Interim Report to the Illinois General Assembly on Public Acts 83-1259 and 83-1432.

    ERIC Educational Resources Information Center

    Illinois State Dept. on Aging, Springfield.

    This document contains the third annual interim report of the Illinois Elder Abuse Demonstration Program. It discusses the overall intent of the demonstration program, trends and changes in the third year of the demonstration program compared with the results from the first two years of the program, and achievements and recommendations for a…

  11. 15 CFR 908.5 - Interim reports.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... SUBMITTING REPORTS ON WEATHER MODIFICATION ACTIVITIES § 908.5 Interim reports. (a) Any person engaged in a weather modification project or activity in the United States on January 1 in any year shall submit to the... actual modification activities took place; (2) Number of days on which weather modification...

  12. Project Execution Plan Project 98L-EWW-460 Plutonium Stabilization and Handling DOE 98-D-453

    SciTech Connect

    HOLSTEIN, W.A.

    1999-08-01

    This Project Execution Plan (PEP) describes the management methods and responsibilities of the project participants. Project W-460 is sufficiently large to warrant a stand alone PEP. This project specific PEP describes the relationships and responsibilities of the project team and identifies the technical, schedule, and cost baselines that have been established for the project. The Department of Energy (DOE), Hanford Works (Hanford), at Richland Wa. currently does not have a system capable of stabilizing or packaging large quantities of plutonium-bearing solids to meet DOE technical standard DOE-STD-3013-96. This project will allow Hanford to meet this standard by installing stabilization and packaging equipment (SPE). The SPE is capable of stabilizing and packaging the current inventory of greater than 50 percent plutonium-bearing materials currently stored in the Plutonium Finishing Plant's (PFP) vaults into 3013 storage containers. The scope of this project is to procure and install the SPE via a Hanford contract and coordination with the Savannah River Site. In addition, the project will modify PFP vaults and upgrade the PFP Laboratory measurement systems. The Facility infrastructure will be modified to support the new SPE system and the new standardized storage container configuration.

  13. Project Execution Plan Project 98L-EWW-460 Plutonium Stabilization and Handling DOE 98-D-453

    SciTech Connect

    MCGRATH, G.M.

    2000-06-21

    This Project Execution Plan (PEP) describes the management methods and responsibilities of the project participants. Project W-460 is sufficiently large to warrant a stand alone PEP. This project specific PEP describes the relationships and responsibilities of the project team and identifies the technical, schedule, and cost baselines that have been established for the project. The Department of Energy (DOE), Hanford Works (Hanford), at Richland, Wa. currently does not have a system capable of stabilizing or packaging large quantities of plutonium-bearing solids to meet DOE technical standard DOE-STD-3013-99. This project will allow Hanford to meet this standard by installing stabilization and packaging equipment (SPE). The SPE is capable of stabilizing and packaging the current inventory of greater than 30 percent plutonium-bearing materials currently stored in the Plutonium Finishing Plant's (PFP) vaults into 3013 storage containers. The scope of this project is to procure and install the SPE via a Hanford contract and coordination with the Savannah River Site. In addition, the project will modify PFP vaults and upgrade the PFP Laboratory measurement systems. The Facility infrastructure will be modified to support the new SPE system and the new standardized storage container configuration.

  14. Conceptual design report for immobilized high-level waste interim storage facility (Phase 1)

    SciTech Connect

    Burgard, K.C.

    1998-06-02

    The Hanford Site Canister Storage Building (CSB Bldg. 212H) will be utilized to interim store Phase 1 HLW products. Project W-464, Immobilized High-Level Waste Interim Storage, will procure an onsite transportation system and retrofit the CSB to accommodate the Phase 1 HLW products. The Conceptual Design Report establishes the Project W-464 technical and cost basis.

  15. Conceptual design report for immobilized high-level waste interim storage facility (Phase 1)

    SciTech Connect

    Burgard, K.C.

    1998-04-09

    The Hanford Site Canister Storage Building (CSB Bldg. 212H) will be utilized to interim store Phase 1 HLW products. Project W-464, Immobilized High-Level Waste Interim Storage, will procure an onsite transportation system and retrofit the CSB to accommodate the Phase 1 HLW products. The Conceptual Design Report establishes the Project W-464 technical and cost basis.

  16. Online Education Interim Report

    ERIC Educational Resources Information Center

    Protopsaltis, Spiros, Ed.

    2007-01-01

    This interim report produced by the Colorado State Board of Education Online Education Task Force examines key issues related to online education. Task force members agree that: (1) online education has become a viable element of Colorado's public education system; (2) the role of technology in educating our children will continue to grow; and (3)…

  17. Interim Budget Plan.

    ERIC Educational Resources Information Center

    Office of Student Financial Assistance (ED), Washington, DC.

    This report provides the interim budget plan of the U.S. Department of Education's Office of Student Financial Assistance (OSFA) for fiscal year 2000. It reviews factors influencing OSFA's budget request, including legislative requirements, recent accomplishments, the need to maintain both the Direct Loan and Federal Family Education Loan…

  18. Oak Ridge National Laboratory Gunite and Associated Tanks Stabilization Project-Low-Tech Approach with High-Tech Results

    SciTech Connect

    Brill, A.; Alsup, T.; Bolling, D.

    2002-02-26

    Environmental restoration of the Gunite and Associated Tanks (GAAT) at the Oak Ridge National Laboratory (ORNL) was a priority to the U. S. Department of Energy (DOE) because of their age and deteriorating structure. These eight tanks ranging up to 170,000 gallons in capacity were constructed in 1943 of a Gunite or ''sprayed concrete material'' as part of the Manhattan Project. The tanks initially received highly radioactive waste from the Graphite Reactor and associated chemical processing facilities. The waste was temporarily stored in these tanks to allow for radioactive decay prior to dilution and release into surface waters. Over time, additional wastes from ongoing ORNL operations (e.g., isotope separation and materials research) were discharged to the tanks for storage and treatment. These tanks were taken out of service in the 1970s. Based on the structure integrity of GAAT evaluated in 1995, the worst-case scenario for the tanks, even assuming they are in good condition, is to remain empty. A recently completed interim action conducted from April 1997 through September 2000 removed the tank liquids and residual solids to the extent practical. Interior video surveys of the tanks indicated signs of degradation of the Gunite material. The tanks continued to receive inleakage, which generated a relatively high volume waste stream that required periodic removal, treatment, and disposal. For these reasons, DOE chose in-place stabilization of Tanks W-3 through W-10 as a non-timecritical removal action under Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Tank stabilization activities involved removal of liquid from inleakage and placement of a grout mixture or ''flowable fill'' into the tanks to within 3-ft of the ground surface. Bechtel Jacobs Company, LLC (BJC) awarded Safety and Ecology Corporation (SEC) a subcontract in March 2001 to complete the documentation and fieldwork necessary to achieve tank stabilization in

  19. Longitudinal Stability of Cognitive Ability in the Colorado Adoption Project.

    ERIC Educational Resources Information Center

    Baker, Laura A.; And Others

    1983-01-01

    Measures of general cognitive ability in one- and two-year-old adopted and nonadopted infants and their parents were subjected to path analysis to estimate the contribution of genetic and environmental factors to short-term stability of mental ability. (Author/RH)

  20. Conceptual design report, plutonium stabilization and handling,project W-460

    SciTech Connect

    Weiss, E.V.

    1997-03-06

    Project W-460, Plutonium Stabilization and Handling, encompasses procurement and installation of a Stabilization and Packaging System (SPS) to oxidize and package for long term storage remaining plutonium-bearing special nuclear materials currently in inventory at the Plutonium Finishing Plant (PFP), and modification of vault equipment to allow storage of resulting packages of stabilized SNM for up to fifty years. This Conceptual Design Report (CDR) provides conceptual design details for the vault modification, site preparation and site interface with the purchased SPS. Two concepts are described for vault configuration; acceleration of this phase of the project did not allow completion of analysis which would clearly identify a preferred approach.

  1. CMM Interim Check (U)

    SciTech Connect

    Montano, Joshua Daniel

    2015-03-23

    Coordinate Measuring Machines (CMM) are widely used in industry, throughout the Nuclear Weapons Complex and at Los Alamos National Laboratory (LANL) to verify part conformance to design definition. Calibration cycles for CMMs at LANL are predominantly one year in length. Unfortunately, several nonconformance reports have been generated to document the discovery of a certified machine found out of tolerance during a calibration closeout. In an effort to reduce risk to product quality two solutions were proposed – shorten the calibration cycle which could be costly, or perform an interim check to monitor the machine’s performance between cycles. The CMM interim check discussed makes use of Renishaw’s Machine Checking Gauge. This off-the-shelf product simulates a large sphere within a CMM’s measurement volume and allows for error estimation. Data was gathered, analyzed, and simulated from seven machines in seventeen different configurations to create statistical process control run charts for on-the-floor monitoring.

  2. Fluor Hanford Nuclear Material Stabilization Project Welding Manual

    SciTech Connect

    BERKEY, J.R.

    2000-10-20

    The purpose of this section of the welding manual is to: (1) Provide a general description of the major responsibilities of the organizations involved with welding. (2) Provide general guidance concerning the application of codes related to welding. This manual contains requirements for welding for all Fluor Hanford (FH) welding operators working on the W460 Project, in the Plutonium Finishing Plant (PFP) at the U. S. Department of Energy (DOE) Hanford facilities. These procedures and any additional requirements for these joining processes can be used by all FH welding operators that are qualified. The Welding Procedure Specifications (WPS) found in this document were established from Procedure Qualification Records (PQR) qualified by FH specifically for the W460 Project. PQRs are permanent records of the initial testing and qualification program and are used to backup, and support, the WPS. The identification numbers of the supporting PQR(s) are recorded on each WPS. All PQRs are permanently stored under the supervision of the Fluor Hanford Welding Engineer (FHWE). New PQRs and WPSs will continue to be developed as necessary. The qualification of welders, welding operators and welding procedures will be performed for FH under supervision and concurrent of the FHWE. All new welding procedures to be entered in this manual or welder personnel to be added to the welder qualification database, shall be approved by the FHWE.

  3. Acceleration of the remediation process through interim action

    SciTech Connect

    Clark, T.R.; Throckmorton, J.D.; Hampshire, L.H.; Dalga, D.G.; Janke, R.J.

    1993-11-01

    During the Remedial Investigation and Feasibility Study (RI/FS) phase of a CERCLA cleanup, it is possible to implement interim actions at a site ``to respond to an immediate site threat or take advantage of an opportunity to significantly reduce risk quickly.`` An interim action is a short term action that addresses threats to public health and safety and is generally followed by the RI/FS process to achieve complete long term protection of human health and the environment. Typically, an interim action is small in scope and can be implemented quickly to reduce risks, such as the addition of a security fence around a known or suspected hazard, or construction of a temporary cap to reduce run-on/run-off from a contaminant source. For more specialized situations, however, the possibility exists to apply the intent of the interim action guidance to a much larger project scope. The primary focus of this paper is the discussion of the interim action approach for streamlined remedial action and presentation of an example large-scale project utilizing this approach at the Fernald Environmental Management Project (FEMP).

  4. Treatment of patients with refractory metastatic cancer according to molecular profiling on tumor tissue in the clinical routine: an interim-analysis of the ONCO-T-PROFILE project

    PubMed Central

    Seeber, Andreas; Gastl, Guenther; Ensinger, Christian; Spizzo, Gilbert; Willenbacher, Wolfgang; Kocher, Florian; Leitner, Christoph; Willenbacher, Ella; Amann, Arno; Steiner, Normann; Eisterer, Wolfgang; Voss, Andreas; Russell, Kenneth; Zwierzina, Heinz

    2016-01-01

    Introduction Patients with refractory metastatic cancer have been shown to benefit from molecular profiling of tumor tissue. The ONCO-T-PROFILE project was launched in March 2014 at the Innsbruck Medical University. Within 2 years our project aims to recruit 110 patients with stage IV cancer refractory to standard therapy. Our data presented here are based on an interim-analysis. Methods Tumor tissue specimens were submitted for molecular profiling to the certified laboratory (Caris Life Science, USA). Druggable tumor targets were selected based on biomarker status to agents with potential clinical benefit. Clinical benefit was defined as a PFS ratio (=PFS upon treatment according to the molecular profile/ PFS upon the last prior therapy) ≥ 1.3. Results As of April 2015, tumors from 50 patients have been molecularly profiled and one or more targets were detectable in 48 specimens (98%). So far, 19 (38%) patients have been treated according to their molecular tumor profile. To date, 8 (42%) patients have reached a PFS ratio of ≥ 1.3. Conclusions We could show that molecular profiling is feasible in the clinical routine. A proportion of patients might benefit from an individualized treatment approach based on molecular profiling. As a result, we will proceed to enroll patients in ONCO-T-PROFILE. PMID:28050231

  5. PUPIL, STAFF, AND EDUCATIONAL FACILITY CHARACTERISTICS ASSOCIATED WITH PUBLIC LAW 89-10 TITLE I PROJECTS IN IOWA. INTERIM REPORT, 1 JUNE 1966-31 MAY 1967.

    ERIC Educational Resources Information Center

    FOLEY, WALTER J.

    THIS DETAILED FOUR-PART REPORT ASSESSES THE FIRST YEAR OF COMPENSATORY EDUCATION PROJECTS ESTABLISHED IN IOWA UNDER TITLE I OF THE 1965 ELEMENTARY AND SECONDARY EDUCATION ACT. OVER 95 PERCENT OF IOWA'S SCHOOL DISTRICTS, MANY OF THEM IN RURAL AREAS, PARTICIPATED IN THE PROJECT. THE MOST SIGNIFICANT SHORTCOMING OF THE LOCAL PROJECTS WAS THEIR LACK…

  6. Interim Assessments: A User's Guide

    ERIC Educational Resources Information Center

    Marshall, Kim

    2008-01-01

    Interim assessments are hot in American schools. Also called benchmark or periodic tests, these assessments are given every four to nine weeks to check on students' progress. Although interim assessments are an important tool for school improvement, they are easy to misuse. In the author's work coaching principals in a number of districts, he has…

  7. Guidance: Interim Municipal Settlement Policy

    EPA Pesticide Factsheets

    Interim guidance and fact sheets regarding settlements involving municipalities or municipal waste under Section 122 CERCLA as amended by SARA. Interim policy sets forth the criteria by which EPA generally determines whether to exercise enforcement discretion to pursue MSW generators and transporters as PRPs.

  8. Interim storage study report

    SciTech Connect

    Rawlins, J.K.

    1998-02-01

    High-level radioactive waste (HLW) stored at the Idaho Chemical Processing Plant (ICPP) in the form of calcine and liquid and liquid sodium-bearing waste (SBW) will be processed to provide a stable waste form and prepare the waste to be transported to a permanent repository. Because a permanent repository will not be available when the waste is processed, the waste must be stored at ICPP in an Interim Storage Facility (ISF). This report documents consideration of an ISF for each of the waste processing options under consideration.

  9. Facility stabilization project, fiscal year 1998 -- Multi-year workplan (MYWP) for WBS 1.4

    SciTech Connect

    Floberg, W.C.

    1997-09-30

    The primary Facility Stabilization mission is to provide minimum safe surveillance and maintenance of facilities and deactivate facilities on the Hanford Site, to reduce risks to workers, the public and environment, transition the facilities to a low cost, long term surveillance and maintenance state, and to provide safe and secure storage of special nuclear materials, nuclear materials, and nuclear fuel. Facility Stabilization will protect the health and safety of the public and workers, protect the environment and provide beneficial use of the facilities and other resources. Work will be in accordance with the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement), local, national, international and other agreements, and in compliance with all applicable Federal, state, and local laws. The stakeholders will be active participants in the decision processes including establishing priorities, and in developing a consistent set of rules, regulations, and laws. The work will be leveraged with a view of providing positive, lasting economic impact in the region. Effectiveness, efficiency, and discipline in all mission activities will enable Hanford Site to achieve its mission in a continuous and substantive manner. As the mission for Facility Stabilization has shifted from production to support of environmental restoration, each facility is making a transition to support the Site mission. The mission goals include the following: (1) Achieve deactivation of facilities for transfer to EM-40, using Plutonium Uranium Extraction (PUREX) plant deactivation as a model for future facility deactivation; (2) Manage nuclear materials in a safe and secure condition and where appropriate, in accordance with International Atomic Energy Agency (IAEA) safeguards rules; (3) Treat nuclear materials as necessary, and store onsite in long-term interim safe storage awaiting a final disposition decision by US Department of Energy; (4) Implement nuclear materials

  10. Drought Prediction for Socio-Cultural Stability Project

    NASA Technical Reports Server (NTRS)

    Peters-Lidard, Christa; Eylander, John B.; Koster, Randall; Narapusetty, Balachandrudu; Kumar, Sujay; Rodell, Matt; Bolten, John; Mocko, David; Walker, Gregory; Arsenault, Kristi; Rheingrover, Scott

    2014-01-01

    The primary objective of this project is to answer the question: "Can existing, linked infrastructures be used to predict the onset of drought months in advance?" Based on our work, the answer to this question is "yes" with the qualifiers that skill depends on both lead-time and location, and especially with the associated teleconnections (e.g., ENSO, Indian Ocean Dipole) active in a given region season. As part of this work, we successfully developed a prototype drought early warning system based on existing/mature NASA Earth science components including the Goddard Earth Observing System Data Assimilation System Version 5 (GEOS-5) forecasting model, the Land Information System (LIS) land data assimilation software framework, the Catchment Land Surface Model (CLSM), remotely sensed terrestrial water storage from the Gravity Recovery and Climate Experiment (GRACE) and remotely sensed soil moisture products from the Aqua/Advanced Microwave Scanning Radiometer - EOS (AMSR-E). We focused on a single drought year - 2011 - during which major agricultural droughts occurred with devastating impacts in the Texas-Mexico region of North America (TEXMEX) and the Horn of Africa (HOA). Our results demonstrate that GEOS-5 precipitation forecasts show skill globally at 1-month lead, and can show up to 3 months skill regionally in the TEXMEX and HOA areas. Our results also demonstrate that the CLSM soil moisture percentiles are a goof indicator of drought, as compared to the North American Drought Monitor of TEXMEX and a combination of Famine Early Warning Systems Network (FEWS NET) data and Moderate Resolution Imaging Spectrometer (MODIS)'s Normalizing Difference Vegetation Index (NDVI) anomalies over HOA. The data assimilation experiments produced mixed results. GRACE terrestrial water storage (TWS) assimilation was found to significantly improve soil moisture and evapotransportation, as well as drought monitoring via soil moisture percentiles, while AMSR-E soil moisture

  11. An interim evaluation of the thermal stability of Cu--Y--/sup 85/Kr sputter deposits and plans for evantual disposal

    SciTech Connect

    McClanahan, E.D.; Bradley, E.R.

    1988-04-01

    A pilot process was developed and demonstrated for trapping and storing /sup 85/Kr from the dissolver off-gas stream of a nuclear fuel reprocessing plant. Ions produced in a low-pressure krypton discharge are implanted on the inner wall of a krypton trapping storage device (KTSD). Objectives were to measure the release of /sup 85/Kr implanted in a copper--yttrium alloy, outline the characterization work to be performed on the Cu/endash/Y/endash//sup 85/Kr waste form, and identify the options available for disposing of the remaining /sup 85/Kr. Release rates were obtained from periodic measurements of the krypton released from both radioactive and nonradioactive krypton-loaded KTSDs. Sampling is expected to continue as long as the extrapolated release rates remain acceptable for a period not to exceed one half-life (/approximately/10 y). Seven tests were performed on a nonradioactive KTSD at 180 to 450/degree/C. Three KTSDs loaded with 80 to 150 Ci of /sup 85/Kr stored at 150, 250, and 350/degree/C were sampled four times each. Proposed post-elevated-temperature storage characterization of the Cu/endash/Y/endash//sup 85/Kr waste form is outlined. Both radioactive and nonradioactive test specimens stored below 350/degree/C showed release rates less than 0.1%y/sup /minus/1/. Release rates for the radioactive specimens were obtained for storage periods of 1.6, 1.1, and 0.4 y at 150, 250 and 350/degree/C. The nonradioactive specimen has been held at temperatures between 180 and 450/degree/C, but mainly at 350/degree/C for a total storage time of 2.1 y. Tests should continue for a period not exceeding 10 y, and then the remaining Cu/endash/Y/endash//sup 85/Kr waste form should be evaluated to better predict the overall stability. Three options for the disposal of the remaining /sup 85/Kr. 3 refs., 2 figs., 2 tabs.

  12. 76 FR 4369 - Interim Deputation Agreements; Interim BIA Adult Detention Facility Guidelines

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-01-25

    ... Bureau of Indian Affairs Interim Deputation Agreements; Interim BIA Adult Detention Facility Guidelines... publication of the Interim BIA Adult Detention Facility Guidelines and the Interim Model Deputation Agreements... of 2010. Three Interim Model Deputation Agreements will be used: one agreement for tribes in...

  13. 49 CFR 1182.7 - Interim approval.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 49 Transportation 8 2010-10-01 2010-10-01 false Interim approval. 1182.7 Section 1182.7....7 Interim approval. (a) A party may request interim approval of the operation of the properties... additional filing fee is required, whether the request for interim approval is included in the application...

  14. 24 CFR 35.820 - Interim controls.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 24 Housing and Urban Development 1 2010-04-01 2010-04-01 false Interim controls. 35.820 Section 35...-Possession Multifamily Property § 35.820 Interim controls. HUD shall conduct interim controls in accordance... accordance with § 35.815. Interim controls are considered completed when clearance is achieved in...

  15. Consortium of Schools for the Future: An Interim Report of a Pilot Project Sponsored by Region 18 of the California School Administrators.

    ERIC Educational Resources Information Center

    Olivero, James

    This document reports on a pilot project called "The Consortium of Schools for the Future," designed to anticipate and make necessary adaptations for the future of public education. A section describing the project precedes a discussion of the disparity between advantaged and disadvantaged students--particularly along racial and ethnic…

  16. L2 -stability of haptic systems with projection-based force reflection.

    PubMed

    Polushin, Ilia G; Hasan, Mir Zayed

    2014-01-01

    The problem of stability of haptic interaction with virtual objects is addressed, where the force reflection is implemented using the projection-based principle. A stability condition is derived that generalizes some previously known results to the case of projection-based force reflection. It demonstrates that, in this case, an additional design parameter is brought in that allows to increase the admissible stiffness of the virtual wall and decrease the update rate without changing the damping of the haptic device. A passivity based interpretation of the result is given in terms of interconnection of generalized passive systems where the excess of passivity of haptic device compensates the shortage of passivity of the virtual wall. In particular, it is shown that the projection-based force reflection allows to arbitrarily increase the excess of passivity of the haptic device without changing its physical damping.

  17. Oral Historical, Documentary and Archaeological Investigations of Colbert, Barton, and Vinton, Mississippi: An Interim Report on Phase I of the Tombigbee Historic Townsites Project. Volume I.

    DTIC Science & Technology

    1982-05-01

    of contributing to the general field of archaeometry and to the relationship between researcher and site planner. Future reports and articles will...describes the first phase research of the Tombigbee Historic TownsitesProject, a large, multiphased investigation of the extinct nineteenth century river...Townsites Project research design and organization, the methods employed to conduct field researches , and the results thus far obtained are presented

  18. Effectiveness Monitoring Report, MWMF Tritium Phytoremediation Interim Measures.

    SciTech Connect

    Hitchcock, Dan; Blake, John, I.

    2003-02-10

    This report describes and presents the results of monitoring activities during irrigation operations for the calendar year 2001 of the MWMF Interim Measures Tritium Phytoremediation Project. The purpose of this effectiveness monitoring report is to provide the information on instrument performance, analysis of CY2001 measurements, and critical relationships needed to manage irrigation operations, estimate efficiency and validate the water and tritium balance model.

  19. Ocotillo: Improving Learning through Instruction. Interim Report, 1989-90.

    ERIC Educational Resources Information Center

    Walters, Jim, Ed.; Jacobs, Alan, Ed.

    Continuing work begun at a 1988 conference, the Ocotillo Action/Research Groups of the Maricopa Community Colleges (Arizona) explored ways to enhance the use of educational technology and to capitalize on future developments in the field. These interim reports cover work done in 1989-90 and serve as a basis for the next projected conference. The…

  20. Episodic acidification and associated fish and benthic invertebrate responses in five Northern Appalachian streams: An interim report of the episodic response project

    SciTech Connect

    DeWalle, D.R.; Gagen, C.J.; Jones, M.C.; Carline, R.F.; Sharpe, W.E.

    1991-05-01

    The report summarizes progress from October 1988 to May 1989 on an ongoing research project to investigate the chemicals and biological response of five Northern Appalachian Plateau streams to episodic changes in flow. The research described is part of the U.S. EPA Episodic Response Project (ERP), Aquatic Effects Research Program. Research includes monitoring of stream discharge, episodic stream chemistry, precipitation amounts and intensity, and snowpack chemistry and water equivalent. Biological research includes bethic invertebrate surveyss stream bioassays with brook trout and sculpins, and tracking of brook trout movement during episodes using radiotelemetry.

  1. Permitting plan for the high-level waste interim storage

    SciTech Connect

    Deffenbaugh, M.L.

    1997-04-23

    This document addresses the environmental permitting requirements for the transportation and interim storage of solidified high-level waste (HLW) produced during Phase 1 of the Hanford Site privatization effort. Solidified HLW consists of canisters containing vitrified HLW (glass) and containers that hold cesium separated during low-level waste pretreatment. The glass canisters and cesium containers will be transported to the Canister Storage Building (CSB) in a U.S. Department of Energy (DOE)-provided transportation cask via diesel-powered tractor trailer. Tri-Party Agreement (TPA) Milestone M-90 establishes a new major milestone, and associated interim milestones and target dates, governing acquisition and/or modification of facilities necessary for: (1) interim storage of Tank Waste Remediation Systems (TWRS) immobilized HLW (IHLW) and other canistered high-level waste forms; and (2) interim storage and disposal of TWRS immobilized low-activity tank waste (ILAW). An environmental requirements checklist and narrative was developed to identify the permitting path forward for the HLW interim storage (HLWIS) project (See Appendix B). This permitting plan will follow the permitting logic developed in that checklist.

  2. Arsenic Removal from Drinking Water by Adsorptive Media U.S. EPA Demonstration Project at Upper Bodfish in Lake Isabella, CA Interim Evaluation Report

    EPA Science Inventory

    This report documents the activities performed during and the results obtained from the first 10 months of system operation of an arsenic (As) and uranium (U) removal technology being demonstrated at Upper Bodfish in Lake Isabella, CA. The objectives of the project are to evalua...

  3. PROJECT VIGOR; Vocational Cluster Education, Integrated and Articulated Grades 1 through 14 with Guidance Services, Occupational Exploration and Work Experience Relevant to General Education. First Interim Report.

    ERIC Educational Resources Information Center

    McCaleb, Omer

    To change a conventional, academically oriented general education school system into one whose curriculum reflects concepts of career education at all grade levels in harmony with existing teaching/learning processes, Project VIGOR staff held a teacher orientation workshop to introduce the career education concept as envisioned by Oregon's Career…

  4. Interim dentures and treatment dentures.

    PubMed

    Smith, D E

    1984-04-01

    Improvement in the interim denture procedure in the past decade has been one of the significant advancements in prosthodontic practice. The interim denture approach is only slightly more time-consuming and expensive than the conventional immediate denture approach, yet it has many advantages. Among those advantages are the following: (1) allows rapid results; (2) results in a higher quality definitive denture; (3) allows the surgical treatment to be performed during one appointment; (4) permits duplication of the natural tooth position; and (5) provides the patient with a spare denture after the definitive denture is completed. An interim denture technique was described that utilized a flexible layered silicone mold to form the replaced teeth. The interim denture procedure is flexible and lends itself to many variations in technique to meet unusual clinical situations. An interim removable partial denture technique was described that involves block-out of undesirable undercuts and duplication of the master cast for fabrication of the partial denture. This technique results in an interim partial denture that can be placed with little or no adjustment and that will provide better service for those who require it. Three simple procedures for fabricating treatment dentures were described and the indications for each were discussed. Although treatment dentures are not often used, they are essential for the dentist who is treating difficult patients who require complete dentures.

  5. Reconstruction of Plasma Equilibria and Projected Stabilization of Global MHD Modes in KSTAR

    NASA Astrophysics Data System (ADS)

    Park, Y. S.; Sabbagh, S. A.; Bialek, J. M.; Berkery, J. W.; Jeon, Y. M.; Hahn, S. H.; Lee, S. G.; You, K.-. I.; Park, H. K.; Evans, T. E.; Eidietis, N.; Walker, M.; Leuer, J.

    2010-11-01

    Experimental equilibria of the KSTAR tokamak with plasma current up to 0.34 MA were reconstructed using EFIT. Vessel currents were included by fitting estimated values based on loop voltage measurements and effective resistances from 2 and 3-D vacuum model calculations including a double-walled vessel with large port penetrations and passive stabilizers. Active and passive stabilization of global MHD instabilities for operation above the no-wall beta limit is also projected. The stabilization is applied using a set of segmented internal coils called in-vessel control coils (IVCCs). Passive stability of the resistive wall mode and power requirement for its active stabilization are investigated including conductive casing structures covering the IVCC, and noise effects. The potential for ELM mitigation by resonant magnetic perturbations is also examined by using the TRIP3D code. Favorable configurations of the IVCC based on the Chirikov parameter are determined using a combination of all IVCCs (midplane and off-midplane coils) with a dominant n = 2 field configuration.

  6. Improvement in the control aspect of laser frequency stabilization for SUNLITE project

    NASA Technical Reports Server (NTRS)

    Zia, Omar

    1992-01-01

    Flight Electronics Division of Langley Research Center is developing a spaceflight experiment called the Stanford University and NASA Laser In-Space Technology (SUNLITE). The objective of the project is to explore the fundamental limits on frequency stability using an FM laser locking technique on a Nd:YAG non-planar ring (free-running linewidth of 5 KHz) oscillator in the vibration free, microgravity environment of space. Compact and automated actively stabilized terahertz laser oscillators will operate in space with an expected linewidth of less than 3 Hz. To implement and verify this experiment, NASA engineers have designed and built a state of the art, space qualified high speed data acquisition system for measuring the linewidth and stability limits of a laser oscillator. In order to achieve greater stability and better performance, an active frequency control scheme requiring the use of a feedback control loop has been applied. In the summer of 1991, the application of control theory in active frequency control as a frequency stabilization technique was investigated. The results and findings were presented in 1992 at the American Control Conference in Chicago, and have been published in Conference Proceedings. The main focus was to seek further improvement in the overall performance of the system by replacing the analogue controller by a digital algorithm.

  7. Characterization of materials for a reactive transport model validation experiment: Interim report on the caisson experiment. Yucca Mountain Site Characterization Project

    SciTech Connect

    Siegel, M.D.; Cheng, W.C.; Ward, D.B.; Bryan, C.R.

    1995-08-01

    Models used in performance assessment and site characterization activities related to nuclear waste disposal rely on simplified representations of solute/rock interactions, hydrologic flow field and the material properties of the rock layers surrounding the repository. A crucial element in the design of these models is the validity of these simplifying assumptions. An intermediate-scale experiment is being carried out at the Experimental Engineered Test Facility at Los Alamos Laboratory by the Los Alamos and Sandia National Laboratories to develop a strategy to validate key geochemical and hydrological assumptions in performance assessment models used by the Yucca Mountain Site Characterization Project.

  8. Stormwater Pollution Prevention Plan (SWPPP) for Coal Storage Area Stabilization Project

    SciTech Connect

    Project and Design Engineering

    2011-03-01

    The scope of this project is to stabilize the abandoned coal storage area and redirect the storm water runoff from sanitary sewer system to the storm drain system. Currently, the existing storm water runoff is directed to a perimeter concrete drainage swale and collected in a containment basin. The collected water is then pumped to a treatment facility and after treatment, is discharged to the Y-12 sanitary sewer system. The existing drainage swale and collection basin along with silt fencing will be used during aggregate placement and grading to provide erosion and sediment control. Inlet protection will also be installed around existing structures during the storm water diversion construction. This project scope will include the installation of a non-woven geotextile fabric and compacted mineral aggregate base (paving optional) to stabilize the site. The geotextile specifications are provided on the vendor cut sheets in Appendix B. The installation of a storm water collection/retention area will also be installed on the southern side of the site in accordance with EPA Technical Guidance on Implementing the Stormwater Runoff Requirements for federal Projects under Section 438 of the Energy Independence and Security Act. The total area to be disturbed is approximately 2.5 acres. The order of activities for this Stormwater Pollution Prevention Plan (SWPPP) will be: (1) post notice of coverage (NOC) in a prominent display near entrance of the site; (2) install rain gauge on site or contact Y-12 Plant Shift Superintendent daily for Met tower rain gauge readings; (3) install stabilized construction exit on site; (4) install silt fencing along perimeter as indicated on the attached site plan; (5) regrade site; (6) install geotextile fabric and compacted mineral aggregate base; (7) install catch basin inlet protection where required; (8) excavate and lower existing catch basin tops, re-grade and asphalt to drain; and (9) when all disturbed areas are re-stabilized, remove

  9. EMCS Retrofit Analysis - Interim Report

    SciTech Connect

    Diamond, R.C.; Salsbury, T.I.; Bell, G.C.; Huang, Y.J.; Sezgen, A.O.; Mazzucchi, R.; Romberger, J.

    1999-03-01

    This report presents the interim results of analyses carried out in the Phillip Burton Federal Building in San Francisco from 1996 to 1998. The building is the site of a major demonstration of the BACnet communication protocol. The energy management and control systems (EMCS) in the building were retrofitted with BACnet compatible controllers in order to integrate certain existing systems on one common network. In this respect, the project has been a success. Interoperability of control equipment from different manufacturers has been demonstrated in a real world environment. Besides demonstrating interoperability, the retrofits carried out in the building were also intended to enhance control strategies and capabilities, and to produce energy savings. This report presents analyses of the energy usage of HVAC systems in the building, control performance, and the reaction of the building operators. The report does not present an evaluation of the performance capabilities of the BACnet protocol. A monitoring system was installed in the building that parallels many of the EMCS sensors and data were archived over a three-year period. The authors defined pre-retrofit and post-retrofit periods and analyzed the corresponding data to establish the changes in building performance resulting from the retrofit activities. The authors also used whole-building energy simulation (DOE-2) as a tool for evaluating the effect of the retrofit changes. The results of the simulation were compared with the monitored data. Changes in operator behavior were assessed qualitatively with questionnaires. The report summarizes the findings of the analyses and makes several recommendations as to how to achieve better performance. They maintain that the full potential of the EMCS and associated systems is not being realized. The reasons for this are discussed along with possible ways of addressing this problem. They also describe a number of new technologies that could benefit systems of the type

  10. In-situ stabilization of TRU/mixed waste project at the INEEL

    SciTech Connect

    Milian, L.W.; Heiser, J.H.; Adams, J.W.; Rutenkroeger, S.P.

    1997-08-01

    Throughout the DOE complex, buried waste poses a threat to the environment by means of contaminant transport. Many of the sites contain buried waste that is untreated, prior to disposal, or insufficiently treated, by today`s standards. One option to remedy these disposal problems is to stabilize the waste in situ. This project was in support of the Transuranic/Mixed Buried Waste - Arid Soils product line of the Landfill Focus Area, which is managed currently by the Idaho National Engineering Laboratory (BNL) provided the analytical laboratory and technical support for the various stabilization activities that will be performed as part of the In Situ Stabilization of TRU/Mixed Waste project at the INEL. More specifically, BNL was involved in laboratory testing that included the evaluation of several grouting materials and their compatibility, interaction, and long-term durability/performance, following the encapsulation of various waste materials. The four grouting materials chosen by INEL were: TECT 1, a two component, high density cementious grout, WAXFIX, a two component, molten wax product, Carbray 100, a two component elastomeric epoxy, and phosphate cement, a two component ceramic. A simulated waste stream comprised of sodium nitrate, Canola oil, and INEL soil was used in this study. Seven performance and durability tests were conducted on grout/waste specimens: compressive strength, wet-dry cycling, thermal analysis, base immersion, solvent immersion, hydraulic conductivity, and accelerated leach testing.

  11. Acid Pit Stabilization Project (Volume 1 - Cold Testing) and (Volume 2 - Hot Testing)

    SciTech Connect

    G. G. Loomis; A. P. Zdinak; M. A. Ewanic; J. J. Jessmore

    1998-01-01

    During the summer and fall of Fiscal Year 1997, a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Treatability Study was performed at the Idaho National Engineering and Environmental Laboratory. The study involved subsurface stabilization of a mixed waste contaminated soil site called the Acid Pit. This study represents the culmination of a successful technology development effort that spanned Fiscal Years 1994-1996. Research and development of the in situ grout stabilization technique was conducted. Hardware and implementation techniques are currently documented in a patent pending with the United States Patent and Trademark Office. The stabilization technique involved using jet grouting of an innovative grouting material to form a monolith out of the contamination zone. The monolith simultaneously provides a barrier to further contaminant migration and closes voids in the soil structure against further subsidence. This is accomplished by chemical incorporation of contaminants into less soluble species and achieving a general reduction in hydraulic conductivity within the monolith. The grout used for this study was TECT-HG, a relatively dense iron oxide-based cementitious grout. The treatability study involved cold testing followed by in situ stabilization of the Acid Pit. Volume 1 of this report discusses cold testing, performed as part of a ''Management Readiness Assessment'' in preparation for going hot. Volume 2 discusses the results of the hot Acid Pit Stabilization phase of this project. Drilling equipment was specifically rigged to reduce the spread of contamination, and all grouting was performed under a concrete block containing void space to absorb any grout returns. Data evaluation included examination of implementability of the grouting process and an evaluation of the contaminant spread during grouting. Following curing of the stabilized pit, cores were obtained and evaluated for toxicity characteristic leach ing

  12. 7 CFR 15a.71 - Interim procedures.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 7 Agriculture 1 2013-01-01 2013-01-01 false Interim procedures. 15a.71 Section 15a.71 Agriculture Office of the Secretary of Agriculture EDUCATION PROGRAMS OR ACTIVITIES RECEIVING OR BENEFITTING FROM FEDERAL FINANCIAL ASSISTANCE Procedures (Interim) § 15a.71 Interim procedures. For the purposes...

  13. 7 CFR 15a.71 - Interim procedures.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 7 Agriculture 1 2012-01-01 2012-01-01 false Interim procedures. 15a.71 Section 15a.71 Agriculture Office of the Secretary of Agriculture EDUCATION PROGRAMS OR ACTIVITIES RECEIVING OR BENEFITTING FROM FEDERAL FINANCIAL ASSISTANCE Procedures (Interim) § 15a.71 Interim procedures. For the purposes...

  14. 7 CFR 15a.71 - Interim procedures.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 7 Agriculture 1 2014-01-01 2014-01-01 false Interim procedures. 15a.71 Section 15a.71 Agriculture Office of the Secretary of Agriculture EDUCATION PROGRAMS OR ACTIVITIES RECEIVING OR BENEFITTING FROM FEDERAL FINANCIAL ASSISTANCE Procedures (Interim) § 15a.71 Interim procedures. For the purposes...

  15. 7 CFR 15a.71 - Interim procedures.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 7 Agriculture 1 2011-01-01 2011-01-01 false Interim procedures. 15a.71 Section 15a.71 Agriculture Office of the Secretary of Agriculture EDUCATION PROGRAMS OR ACTIVITIES RECEIVING OR BENEFITTING FROM FEDERAL FINANCIAL ASSISTANCE Procedures (Interim) § 15a.71 Interim procedures. For the purposes...

  16. 7 CFR 1735.75 - Interim financing.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 7 Agriculture 11 2010-01-01 2010-01-01 false Interim financing. 1735.75 Section 1735.75... Involving Loan Funds § 1735.75 Interim financing. (a) A borrower may submit a written request for RUS approval of interim financing if it is necessary to close an acquisition before the loan to finance...

  17. 20 CFR 801.202 - Interim appointments.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 20 Employees' Benefits 3 2010-04-01 2010-04-01 false Interim appointments. 801.202 Section 801.202... Members of the Board § 801.202 Interim appointments. (a) Acting Chairman. In the event that the Chairman... such time as the Secretary of Labor designates an Acting Chairman. (b) Interim members. In the...

  18. 24 CFR 7.44 - Interim relief.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 24 Housing and Urban Development 1 2010-04-01 2010-04-01 false Interim relief. 7.44 Section 7.44... § 7.44 Interim relief. (a) When the Department appeals and the case involves removal, separation, or... outcome of the Department appeal. The employee may decline the offer of interim relief. (b) Service...

  19. 7 CFR 15a.71 - Interim procedures.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 7 Agriculture 1 2010-01-01 2010-01-01 false Interim procedures. 15a.71 Section 15a.71 Agriculture Office of the Secretary of Agriculture EDUCATION PROGRAMS OR ACTIVITIES RECEIVING OR BENEFITTING FROM FEDERAL FINANCIAL ASSISTANCE Procedures (Interim) § 15a.71 Interim procedures. For the purposes...

  20. 7 CFR 1738.21 - Interim financing.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 7 Agriculture 11 2010-01-01 2010-01-01 false Interim financing. 1738.21 Section 1738.21... Interim financing. (a) Upon notification by RUS that an applicant's application is considered complete, the applicant may enter into an interim financing agreement with a lender other than RUS or use...

  1. 15 CFR 904.322 - Interim action.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 15 Commerce and Foreign Trade 3 2010-01-01 2010-01-01 false Interim action. 904.322 Section 904... Sanctions and Denials Permit Sanction for Violations § 904.322 Interim action. (a) To protect marine...) The Judge will order interim action under paragraph (a) of this section, only after finding that...

  2. 15 CFR 908.5 - Interim reports.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 15 Commerce and Foreign Trade 3 2010-01-01 2010-01-01 false Interim reports. 908.5 Section 908.5... SUBMITTING REPORTS ON WEATHER MODIFICATION ACTIVITIES § 908.5 Interim reports. (a) Any person engaged in a... Administrator, not later than 45 days thereafter, an interim report setting forth as of such date...

  3. 19 CFR 207.106 - Interim measures.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 19 Customs Duties 3 2010-04-01 2010-04-01 false Interim measures. 207.106 Section 207.106 Customs... and Committee Proceedings § 207.106 Interim measures. (a) At any time after proceedings are initiated... that would otherwise be kept confidential, or to take other appropriate interim measures. (b)...

  4. 12 CFR 268.505 - Interim relief.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 12 Banks and Banking 3 2010-01-01 2010-01-01 false Interim relief. 268.505 Section 268.505 Banks... REGARDING EQUAL OPPORTUNITY Remedies and Enforcement § 268.505 Interim relief. (a)(1) When the Board appeals... offer of interim relief. (2) Service under the temporary or conditional restoration provisions...

  5. 42 CFR 417.574 - Interim settlement.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 42 Public Health 3 2010-10-01 2010-10-01 false Interim settlement. 417.574 Section 417.574 Public... PLANS Medicare Payment: Cost Basis § 417.574 Interim settlement. (a) Determination. Within 30 days following the receipt of the HMO's or CMP's final interim cost and enrollment reports, CMS will make...

  6. 19 CFR 354.8 - Interim sanctions.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 19 Customs Duties 3 2010-04-01 2010-04-01 false Interim sanctions. 354.8 Section 354.8 Customs... VIOLATION OF AN ANTIDUMPING OR COUNTERVAILING DUTY ADMINISTRATIVE PROTECTIVE ORDER § 354.8 Interim sanctions... a final decision is rendered, that interim sanctions are necessary to protect the interests of...

  7. 19 CFR 356.18 - Interim sanctions.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 19 Customs Duties 3 2010-04-01 2010-04-01 false Interim sanctions. 356.18 Section 356.18 Customs... Undertaking § 356.18 Interim sanctions. (a) If the Deputy Under Secretary concludes, after issuing a charging letter under § 356.16 and before a final decision is rendered, that interim sanctions are necessary...

  8. An Interim President Sets the Stage

    ERIC Educational Resources Information Center

    Guardo, Carol J.

    2006-01-01

    An interim president often plays a crucial role in leading a college or university. In some instances, the interim can address and resolve troublesome issues and thus clear the way for the new president to generate progress. In others, the interim stays the course so that the institution maintains its momentum and seizes strategic opportunities to…

  9. 29 CFR 1614.505 - Interim relief.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 29 Labor 4 2010-07-01 2010-07-01 false Interim relief. 1614.505 Section 1614.505 Labor Regulations... OPPORTUNITY Remedies and Enforcement § 1614.505 Interim relief. (a)(1) When the agency appeals and the case... interim relief. (2) Service under the temporary or conditional restoration provisions of paragraph...

  10. 22 CFR 127.8 - Interim suspension.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 22 Foreign Relations 1 2010-04-01 2010-04-01 false Interim suspension. 127.8 Section 127.8 Foreign... Interim suspension. (a) The Managing Director of the Directorate of Defense Trade Controls or the Director of the Office of Defense Trade Controls Compliance is authorized to order the interim suspension...

  11. 32 CFR 776.82 - Interim suspension.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 32 National Defense 5 2010-07-01 2010-07-01 false Interim suspension. 776.82 Section 776.82... Complaint Processing Procedures § 776.82 Interim suspension. (a) Where the Rules Counsel determines there is... interim suspension, pending completion of a professional responsibility investigation. The...

  12. Accuracy and stability in incompressible SPH (ISPH) based on the projection method and a new approach

    SciTech Connect

    Xu Rui Stansby, Peter; Laurence, Dominique

    2009-10-01

    The stability and accuracy of three methods which enforce either a divergence-free velocity field, density invariance, or their combination are tested here through the standard Taylor-Green and spin-down vortex problems. While various approaches to incompressible SPH (ISPH) have been proposed in the past decade, the present paper is restricted to the projection method for the pressure and velocity coupling. It is shown that the divergence-free ISPH method cannot maintain stability in certain situations although it is accurate before instability sets in. The density-invariant ISPH method is stable but inaccurate with random-noise like disturbances. The combined ISPH, combining advantages in divergence-free ISPH and density-invariant ISPH, can maintain accuracy and stability although at a higher computational cost. Redistribution of particles on a fixed uniform mesh is also shown to be effective but the attraction of a mesh-free method is lost. A new divergence-free ISPH approach is proposed here which maintains accuracy and stability while remaining mesh free without increasing computational cost by slightly shifting particles away from streamlines, although the necessary interpolation of hydrodynamic characteristics means the formulation ceases to be strictly conservative. This avoids the highly anisotropic particle spacing which eventually triggers instability. Importantly pressure fields are free from spurious oscillations, up to the highest Reynolds numbers tested.

  13. DEPLOYMENT OF THE GUBKA TECHNOLOGY TO STABILIZE RADIOACTIVE STANDARD SOLUTIONS AT THE FERNALD ENVIRONMENTAL MANAGEMENT PROJECT

    SciTech Connect

    Chipman, N.A.; Knecht, D.A.; Meyer, A.; Aloy, A.; Anshits, A.G.; Tretyakov, A.A.

    2003-02-27

    This paper describes the deployment of the Gubka technology to stabilize liquid technical standards at the Fernald Environmental Management Project. Gubka, an open-cell glass crystalline porous material, was developed by a joint research program of Russian Institutes at St. Petersburg, Krasnoyarsk, and Zheleznogorsk and the Idaho National Engineering and Environmental Laboratory. Gubka technology can be applied in an active or a passive method to stabilize a solution. In both methods the result is the same, and the dried components of the solution are sorbed in the pores of the Gubka block while the liquid phase is evaporated. In this deployment Gubka blocks were passively floated in the solutions at ambient conditions. As the solutions evaporated, the non-volatile components were sorbed in the pores of the Gubka blocks. The waste-loaded Gubka blocks have been packaged for transportation and disposal at the Nevada Test site within an existing waste category.

  14. Supplement Analysis for the Watershed Management Program EIS - Libby Creek (Lower Cleveland) Stabilization Project

    SciTech Connect

    N /A

    2004-07-29

    This project is follow-up to stream stabilization activities on Libby Creek that were initiated on the Upper Cleveland reach of Libby Creek 2 years ago. BPA now proposes to fund FWP to complete channel stabilization activities on the Lower Cleveland reach of Libby Creek, reduce sediment sources, convert overwidened portions of the stream into self-maintaining channel types, use natural stream stabilization techniques, and improve wildlife migratory corridors. This lower reach is about one river mile below the upper Cleveland Reach and the proposed activities are very similar to those conducted before. The current work would be constructed in two additional phases. The first phase of the Lower Cleveland project would be completed in the fall of 2004 (9/1/04--12/31/04), to include the upper 3,100 feet. The second phase will be constructed in the fall of 2005 (9/1/05--12/31/05), to include stabilizing the remaining 6,200 feet of stream. The Cleveland reaches are a spawning and rearing tributary for resident redband trout, and resident and fluvial bull trout migrating from the Kootenai River. The planned work at the two remaining phases calls for shaping cut banks; installing root wads and tree revetments; installing channel grade control structures; planting native vegetation; and installing cross vanes constructed from rock and trees to control channel gradient. In the past, this reach of Libby Creek has been degraded by past management practices, including road building, hydraulic and dredge mining, and riparian logging. This past activity has resulted in accelerated bank erosion along a number of meander bends, resulting in channel degradation and poor fish habitat. Currently the stream channel is over-widened and shallow having limited pool habitat. The current stream channel is over-widened and shallow, having limited pool habitat.

  15. Grabber arm mechanism for the Italian Research Interim Stage (IRIS)

    NASA Technical Reports Server (NTRS)

    Turci, Edmondo

    1987-01-01

    Two deployable arms, named grabbers, were designed and manufactured to provide lateral stability of the perigee spinning stage which will be deployed from the Space Shuttle cargo bay. The spinning stage is supported by a spin table on a cradle at its base. The Italian Research Interim Stage (IRIS) is designed to carry satellites of intermediate mass up to 900 kg. The requirements are defined and the mechanism is described. Functional test results are presented.

  16. A large-scale forest fragmentation experiment: the Stability of Altered Forest Ecosystems Project.

    PubMed

    Ewers, Robert M; Didham, Raphael K; Fahrig, Lenore; Ferraz, Gonçalo; Hector, Andy; Holt, Robert D; Kapos, Valerie; Reynolds, Glen; Sinun, Waidi; Snaddon, Jake L; Turner, Edgar C

    2011-11-27

    Opportunities to conduct large-scale field experiments are rare, but provide a unique opportunity to reveal the complex processes that operate within natural ecosystems. Here, we review the design of existing, large-scale forest fragmentation experiments. Based on this review, we develop a design for the Stability of Altered Forest Ecosystems (SAFE) Project, a new forest fragmentation experiment to be located in the lowland tropical forests of Borneo (Sabah, Malaysia). The SAFE Project represents an advance on existing experiments in that it: (i) allows discrimination of the effects of landscape-level forest cover from patch-level processes; (ii) is designed to facilitate the unification of a wide range of data types on ecological patterns and processes that operate over a wide range of spatial scales; (iii) has greater replication than existing experiments; (iv) incorporates an experimental manipulation of riparian corridors; and (v) embeds the experimentally fragmented landscape within a wider gradient of land-use intensity than do existing projects. The SAFE Project represents an opportunity for ecologists across disciplines to participate in a large initiative designed to generate a broad understanding of the ecological impacts of tropical forest modification.

  17. A large-scale forest fragmentation experiment: the Stability of Altered Forest Ecosystems Project

    PubMed Central

    Ewers, Robert M.; Didham, Raphael K.; Fahrig, Lenore; Ferraz, Gonçalo; Hector, Andy; Holt, Robert D.; Kapos, Valerie; Reynolds, Glen; Sinun, Waidi; Snaddon, Jake L.; Turner, Edgar C.

    2011-01-01

    Opportunities to conduct large-scale field experiments are rare, but provide a unique opportunity to reveal the complex processes that operate within natural ecosystems. Here, we review the design of existing, large-scale forest fragmentation experiments. Based on this review, we develop a design for the Stability of Altered Forest Ecosystems (SAFE) Project, a new forest fragmentation experiment to be located in the lowland tropical forests of Borneo (Sabah, Malaysia). The SAFE Project represents an advance on existing experiments in that it: (i) allows discrimination of the effects of landscape-level forest cover from patch-level processes; (ii) is designed to facilitate the unification of a wide range of data types on ecological patterns and processes that operate over a wide range of spatial scales; (iii) has greater replication than existing experiments; (iv) incorporates an experimental manipulation of riparian corridors; and (v) embeds the experimentally fragmented landscape within a wider gradient of land-use intensity than do existing projects. The SAFE Project represents an opportunity for ecologists across disciplines to participate in a large initiative designed to generate a broad understanding of the ecological impacts of tropical forest modification. PMID:22006969

  18. Clean-coal technology by-products used in a highway embankment stabilization demonstration project. Master's thesis

    SciTech Connect

    Nodjomian, S.M.

    1994-01-01

    Clean-coal technology by-products are used in a highway embankment demonstration project. This research chronicles the procedures used in the process and analyzes the stability of a repaired highway embankment. The reconstructed slope is analyzed using an Intelligent Discussion Support System that was developed from a slope stability program. Water quality studies are performed and an instrumentation plan is suggested. The calculated factors of safety and the observed embankment performance give indications that the field demonstration project was a success. Long-term monitoring will be the best barometer for determining embankment gross movement and the future of FGD by-products as a stabilizing material.

  19. Data breaches. Interim final rule.

    PubMed

    2007-06-22

    This document establishes regulations to address data breaches regarding sensitive personal information that is processed or maintained by the Department of Veterans Affairs (VA). The regulations implement certain provisions of Title IX of the Veterans Benefits, Health Care, and Information Technology Act of 2006, which require promulgation of these regulations as an interim final rule.

  20. Primer for the Interim Chair

    ERIC Educational Resources Information Center

    Soltys, Stephen M.

    2011-01-01

    Objective: Being successful in the role of an Interim Chair requires an approach to transitional leadership that is different from that of individuals filling the Chair role permanently. This article reviews pertinent literature on the topic. Method: The author reviewed the literature, cited pertinent articles, and supplemented with personal…

  1. FRACTIONAL CRYSTALLIZATION LABORATORY TESTING WITH INTERIM PRETREATMENT SYSTEM FEEDS

    SciTech Connect

    HERTING DL

    2008-09-17

    The fractional crystallization process was developed as a pretreatment method for saltcake waste retrieved from Hanford single-shell tanks (SST). The process separates the retrieved SST waste into a high-level waste stream containing the bulk of the radionuclides and a low-activity waste stream containing the bulk of the nonradioactive sodium salts. The Interim Pretreatment System project shifted the focus on pretreatment planning from SST waste to double-shell tank waste.

  2. 41 CFR 101-29.204 - Interim Federal specification.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 41 Public Contracts and Property Management 2 2010-07-01 2010-07-01 true Interim Federal... PRODUCT DESCRIPTIONS 29.2-Definitions § 101-29.204 Interim Federal specification. An interim Federal... agencies. Interim amendments to Federal Specifications and amendments to interim Federal specifications...

  3. Plutonium Surveillance Destructive Examination Requirements at Savannah River National Laboratory for K-Area Interim Surveillance

    SciTech Connect

    Stefek, T. M.

    2005-09-29

    The DOE 3013 storage standard requires nested, welded 300 series stainless steel containers to store plutonium-bearing materials for up to 50 years. Packaged contents include stabilized plutonium-bearing residues that contain chloride salts and a low (< 0.5 weight %) water content. The DOE 3013 STD requires surveillance of the packages over the 50 year lifetime. These surveillance requirements have been further defined by the Integrated Surveillance Program to include both non-destructive examination (NDE) and destructive examination (DE) of the 3013 container. The DE portion of surveillance involves examining the 3013 nested containers, analyzing the head space gas, and evaluating the plutonium oxide chemistry. At SRS, the stored 3013 containers will undergo preparation for the DE surveillance activities in facilities located in K-Area. The actual DE surveillance will be performed in SRNL. This report provides preliminary functional requirements for the destructive examination (DE) of plutonium-bearing oxide materials and containers in support of K-Area Interim Surveillance (KIS). The KIS project will install interim facilities to prepare the samples for analysis in SRNL. This document covers the requirements for the interim period beginning in 2007, and lasting until the Container Storage and Surveillance Capability (CSSC) project provides the permanent facilities in K-Area to perform sampling and repackaging operations associated with the 3013 container storage and surveillance program. Initial requirements for the CSSC project have been previously defined in WSRC-TR-2004-00584 ''Plutonium Surveillance Destructive Examination Requirements at Savannah River National Laboratory''. As part of the Plutonium Surveillance Program of 3013 Containers at the Savannah River Site (SRS), the Savannah River National Laboratory (SRNL) will receive the emptied 3013 container components, plutonium oxide samples and headspace gas samples from K-Area. The DE program scope

  4. Working Parents Project (WPP). Final Interim Report.

    ERIC Educational Resources Information Center

    Mason, Theresa; Espinoza, Renato

    Results are reported from a 2-year study designed to explore how the nature of women's jobs, as viewed by women and their husbands, influences the system of nuclear family relationships and affects parents' involvement with their children's schools. The research has evolved into a comparative exploratory study of the responses of 30 families to…

  5. SCSD: An Interim Report.

    ERIC Educational Resources Information Center

    Educational Facilities Labs., Inc., New York, NY.

    Following a brief history and explication of the School Construction System Development Project, descriptions of a group of standard building components developed to satisfy three objective are presented--(1) to build better schools, (2) to build them more economically, and (3) to build them more rapidly. Detailed structural and performance…

  6. KSTAR equilibrium operating space and projected stabilization at high normalized beta

    NASA Astrophysics Data System (ADS)

    Park, Y. S.; Sabbagh, S. A.; Berkery, J. W.; Bialek, J. M.; Jeon, Y. M.; Hahn, S. H.; Eidietis, N.; Evans, T. E.; Yoon, S. W.; Ahn, J.-W.; Kim, J.; Yang, H. L.; You, K.-I.; Bae, Y. S.; Chung, J.; Kwon, M.; Oh, Y. K.; Kim, W.-C.; Kim, J. Y.; Lee, S. G.; Park, H. K.; Reimerdes, H.; Leuer, J.; Walker, M.

    2011-05-01

    Along with an expanded evaluation of the equilibrium operating space of the Korea Superconducting Tokamak Advanced Research, KSTAR, experimental equilibria of the most recent plasma discharges were reconstructed using the EFIT code. In near-circular plasmas created in 2009, equilibria reached a stored energy of 54 kJ with a maximum plasma current of 0.34 MA. Highly shaped plasmas with near double-null configuration in 2010 achieved H-mode with clear edge localized mode (ELM) activity, and transiently reached a stored energy of up to 257 kJ, elongation of 1.96 and normalized beta of 1.3. The plasma current reached 0.7 MA. Projecting active and passive stabilization of global MHD instabilities for operation above the ideal no-wall beta limit using the designed control hardware was also considered. Kinetic modification of the ideal MHD n = 1 stability criterion was computed by the MISK code on KSTAR theoretical equilibria with a plasma current of 2 MA, internal inductance of 0.7 and normalized beta of 4.0 with simple density, temperature and rotation profiles. The steep edge pressure gradient of this equilibrium resulted in the need for significant plasma toroidal rotation to allow thermal particle kinetic resonances to stabilize the resistive wall mode (RWM). The impact of various materials and electrical connections of the passive stabilizing plates on RWM growth rates was analysed, and copper plates reduced the RWM passive growth rate by a factor of 15 compared with stainless steel plates at a normalized beta of 4.4. Computations of active RWM control using the VALEN code showed that the n = 1 mode can be stabilized at normalized beta near the ideal wall limit via control fields produced by the midplane in-vessel control coils (IVCCs) with as low as 0.83 kW control power using ideal control system assumptions. The ELM mitigation potential of the IVCC, examined by evaluating the vacuum island overlap created by resonant magnetic perturbations, was analysed using the

  7. KSTAR Equilibrium Operating Space and Projected Stabilization at High Normalized Beta

    SciTech Connect

    Park, Y. S.; Sabbagh, S. A.; Berkery, J.W.; Bialek, J.; Jeon, Y. M.; Hahn, S. H.; Eidietis, N. W.; Evans, T. E.; Yoon, S. W.; Ahn, Joonwook; Kim, J.; Yang, H. L.; You, K. I.; Soukhanovskii, V. A.; Bae, Y. S.; Chung, J. I.; Kwon, M.; Oh, Y. K.; Kim, W. C.; Kim, J. Y.; Lee, S. G.; Park, H.; Reimerdes, H.; Leuer, J. A.; Walker, M. L.

    2011-01-01

    Along with an expanded evaluation of the equilibrium operating space of the Korea Superconducting Tokamak Advanced Research, KSTAR, experimental equilibria of the most recent plasma discharges were reconstructed using the EFIT code. In near-circular plasmas created in 2009, equilibria reached a stored energy of 54 kJ with a maximum plasma current of 0.34 MA. Highly shaped plasmas with near double-null configuration in 2010 achieved H-mode with clear edge localized mode (ELM) activity, and transiently reached a stored energy of up to 257 kJ, elongation of 1.96 and normalized beta of 1.3. The plasma current reached 0.7 MA. Projecting active and passive stabilization of global MHD instabilities for operation above the ideal no-wall beta limit using the designed control hardware was also considered. Kinetic modification of the ideal MHD n = 1 stability criterion was computed by the MISK code on KSTAR theoretical equilibria with a plasma current of 2 MA, internal inductance of 0.7 and normalized beta of 4.0 with simple density, temperature and rotation profiles. The steep edge pressure gradient of this equilibrium resulted in the need for significant plasma toroidal rotation to allow thermal particle kinetic resonances to stabilize the resistive wall mode (RWM). The impact of various materials and electrical connections of the passive stabilizing plates on RWM growth rates was analysed, and copper plates reduced the RWM passive growth rate by a factor of 15 compared with stainless steel plates at a normalized beta of 4.4. Computations of active RWM control using the VALEN code showed that the n = 1 mode can be stabilized at normalized beta near the ideal wall limit via control fields produced by the midplane in-vessel control coils (IVCCs) with as low as 0.83kW control power using ideal control system assumptions. The ELM mitigation potential of the IVCC, examined by evaluating the vacuum island overlap created by resonant magnetic perturbations, was analysed using the

  8. Stability metrics for multi-source biomedical data based on simplicial projections from probability distribution distances.

    PubMed

    Sáez, Carlos; Robles, Montserrat; García-Gómez, Juan M

    2017-02-01

    Biomedical data may be composed of individuals generated from distinct, meaningful sources. Due to possible contextual biases in the processes that generate data, there may exist an undesirable and unexpected variability among the probability distribution functions (PDFs) of the source subsamples, which, when uncontrolled, may lead to inaccurate or unreproducible research results. Classical statistical methods may have difficulties to undercover such variabilities when dealing with multi-modal, multi-type, multi-variate data. This work proposes two metrics for the analysis of stability among multiple data sources, robust to the aforementioned conditions, and defined in the context of data quality assessment. Specifically, a global probabilistic deviation and a source probabilistic outlyingness metrics are proposed. The first provides a bounded degree of the global multi-source variability, designed as an estimator equivalent to the notion of normalized standard deviation of PDFs. The second provides a bounded degree of the dissimilarity of each source to a latent central distribution. The metrics are based on the projection of a simplex geometrical structure constructed from the Jensen-Shannon distances among the sources PDFs. The metrics have been evaluated and demonstrated their correct behaviour on a simulated benchmark and with real multi-source biomedical data using the UCI Heart Disease data set. The biomedical data quality assessment based on the proposed stability metrics may improve the efficiency and effectiveness of biomedical data exploitation and research.

  9. Seismic stability evaluation of Alben Barkley Lock and Dam Project. Volume 1. Summary report. Final report

    SciTech Connect

    Wahl, R.E.; Bluhm, P.F.

    1992-09-01

    This report summarizes the results of seismological, geological, laboratory, field, and analytical investigations conducted to evaluate the seismic stability of two earth embankment sections of the Alben Barkley Lock and Dam Project, Kentucky. These represent typical sections of the powerhouse/switch-yard area and the main embankment. Detailed documentation of each of the major topical areas of this study are contained in Volumes 2 through 5 of this series of reports. The design earthquake, from the New Madrid Seismic Zone, had a body-wave magnitude of 7.5. Of particular interest in this study, was the seismic performance of silty sands in the foundation and their overall effect on the stability of these embankment sections. The results of this study indicate that large scale deformations and/or slope failure which would result in the loss of reservoir are not deformations on the order of 2 to 3 ft are expected. These deformations are relatively small in light of the fact that 28 ft of freeboard are expected to be available during the design earthquake.

  10. Sample Results From The Interim Salt Disposition Program Macrobatch 6 Tank 21H Qualification Samples

    SciTech Connect

    Peters, T. B.; Fink, S. D.

    2012-12-20

    Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 6 for the Interim Salt Disposition Project (ISDP). This document reports partial results of the analyses of samples of Tank 21H. No issues with the projected Salt Batch 6 strategy are identified.

  11. Sample Results from the Interim Salt Disposition Program Macrobatch 6 Tank 21H Qualification Samples

    SciTech Connect

    Peters, T. B.; Fink, S. D.

    2012-12-11

    Savannah River National Laboratory (SRNL) analyzed samples from Tank 21H in support of qualification of Macrobatch (Salt Batch) 6 for the Interim Salt Disposition Project (ISDP). This document reports partial results of the analyses of samples of Tank 21H. No issues with the projected Salt Batch 6 strategy are identified.

  12. Seismic imaging of a slope stability mitigation project at Newby Island Sanitary Landfill, San Jose, California

    NASA Astrophysics Data System (ADS)

    Treece, B.; Catchings, R.; Reed, D.; Goldman, M.

    2013-12-01

    Seismic reflection and refraction data were obtained along a transect through a slope stability mitigation project involving deep soil mixing at Newby Island Sanitary Landfill in San Jose, California. Deep soil mixing involves the simultaneous injection of a cement slurry while rotating augers advance vertically down through the subsurface material, resulting in groups of soil-cement columns (elements) intended to increase the strength and rigidity of the treated area. Seismic data were used to analyze the effectiveness of the mitigation procedure, approximately one month after the completion of the deep soil mixing project. Repeated accelerated-weight-drop (AWD) impacts provided the seismic source at each geophone location. Seismic arrivals were recorded with 40-Hz vertical-component geophones, spaced at 3-m intervals. All shots were recorded on all channels. This shooting geometry was designed to produce tomographic refraction (velocity) and reflection (CDP stacks) images from a yet to be mitigated area into the mitigated area, along the base of a steep slope composed of compacted landfill. The acquired data were generally of good quality, with shots propagating the entire length of the profile. An initial analysis of the data shows an increase in seismic velocity in the treated areas compared with non-treated areas, and a relative seismic velocity increase with curing time for soil-cement elements. Future surveys will be collected to further constrain strength increases with time, and to correlate calculated rates of strength with other subsurface data.

  13. Quality assurance project plan for the Chestnut Ridge Fly Ash Pond Stabilization Project at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    SciTech Connect

    1996-07-01

    The Chestnut Ridge Fly Ash Pond Stabilization (CRFAPS) Project will stabilize a 19-m-high (62-ft-high) earthen embankment across Upper McCoy Branch situated along the southern slope of Chestnut Ridge. This task will be accomplished by raising the crest of the embankment, reinforcing the face of the embankment, removing trees from the face and top of the embankment, and repairing the emergency spillway. The primary responsibilities of the team members are: Lockheed Martin Energy Systems, Inc., (Energy Systems) will be responsible for project integration, technical support, Title 3 field support, environmental oversight, and quality assurance (QA) oversight of the project; Foster Wheeler Environmental Corporation (FWENC) will be responsible for design and home office Title 3 support; MK-Ferguson of Oak Ridge Company (MK-F) will be responsible for health and safety, construction, and procurement of construction materials. Each of the team members has a QA program approved by the US Department of Energy (DOE) Oak Ridge Operations. This project-specific QA project plan (QAPP), which is applicable to all project activities, identifies and integrates the specific QA requirements from the participant`s QA programs that are necessary for this project.

  14. AGR-1 Data Qualification Interim Report

    SciTech Connect

    Machael Abbott

    2009-08-01

    Projects for the very-high-temperature reactor (VHTR) program provide data in support of Nuclear Regulatory Commission licensing of the VHTR. Fuel and materials to be used in the reactor are tested and characterized to quantify performance in high temperature and high fluence environments. The VHTR Program has established the NGNP Data Management and Analysis System (NDMAS) to ensure that VHTR data are (1) qualified for use, (2) stored in a readily accessible electronic form, and (3) analyzed to extract useful results. This document focuses on the first NDMAS objective. It describes the data streams associated with the first Advanced Gas Reactor (AGR-1) experiment, the processing of these data within NDMAS, and reports the interim FY09 qualification status of the AGR-1 data to date. Data qualification activities within NDMAS for specific types of data are determined by the data qualification category, which is assigned by the data generator, and include: (1) capture testing, to confirm that the data stored within NDMAS are identical to the raw data supplied, (2) accuracy testing, to confirm that the data are an accurate representation of the system or object being measured, and (3) documentation that the data were collected under an NQA-1 or equivalent QA program. The interim qualification status of the following four data streams is reported in this document: (1) fuel fabrication data, (2) fuel irradiation data, (3) fission product monitoring system (FPMS) data, and (4) Advanced Test Reactor (ATR) operating conditions data. A final report giving the NDMAS qualification status of all AGR-1 data (including cycle 145A) is planned for February 2010.

  15. Are stream stabilization projects reducing suspended sediment concentrations and turbidity in the New York City Water Supply Watershed?

    NASA Astrophysics Data System (ADS)

    McHale, M. R.; Siemion, J.; Davis, W. D.

    2015-12-01

    Turbidity and suspended sediment concentrations (SSCs) are primary water quality concerns in the upper Esopus Creek watershed, the main tributary to the Ashokan reservoir. The Ashokan reservoir is one of 6 surface water reservoirs that constitute about 90% of New York City's drinking water supply. This study quantified turbidity levels and SSCs at 10 locations throughout the upper Esopus Creek watershed for 3 years prior to the implementation of 2 stream stabilization projects and for 18 months after the projects were completed. More than 93 percent of the total-suspended sediment load occurred on days with flows greater than or equal to the 90th percentile of flows observed during the study period. Discharge, SSC, and turbidity were strongly related at the outlet of the upper Esopus Creek, but not at every monitoring site. In general, relations between discharge and SSC and turbidity were strongest at sites with high SSCs, with the exception of Stony Clove Creek, the largest tributary. Stony Clove Creek, consistently produced higher SSCs and turbidity than any of the other Esopus Creek tributaries. Nonetheless, there was not a strong relation between either turbidity or SSC and discharge because there was a series of eroding banks in contact with fine grained glacio-lacustrine deposits and associated hill slope failures within the Stony Clove Creek watershed that delivered elevated turbidity and SSCs to the stream during all flow conditions. Stream bank stabilization projects were completed at two of the largest bank failures. After the projects were completed there was decrease in stream SSC and turbidity however, flows during the 18 months following the projects were lower than before the projects. Nevertheless, a shift in the SSC and turbidity discharge rating curves suggests that the stream stabilization projects resulted in lower turbidity levels and SSCs for similar discharge conditions as compared to before the projects thereby reducing sediment yields

  16. Combustion Stability Characteristics of the Project Morpheus Liquid Oxygen / Liquid Methane Main Engine

    NASA Technical Reports Server (NTRS)

    Melcher, John C.; Morehead, Robert L.

    2014-01-01

    The project Morpheus liquid oxygen (LOX) / liquid methane (LCH4) main engine is a Johnson Space Center (JSC) designed 5,000 lbf-thrust, 4:1 throttling, pressure-fed cryogenic engine using an impinging element injector design. The engine met or exceeded all performance requirements without experiencing any in- ight failures, but the engine exhibited acoustic-coupled combustion instabilities during sea-level ground-based testing. First tangential (1T), rst radial (1R), 1T1R, and higher order modes were triggered by conditions during the Morpheus vehicle derived low chamber pressure startup sequence. The instability was never observed to initiate during mainstage, even at low power levels. Ground-interaction acoustics aggravated the instability in vehicle tests. Analysis of more than 200 hot re tests on the Morpheus vehicle and Stennis Space Center (SSC) test stand showed a relationship between ignition stability and injector/chamber pressure. The instability had the distinct characteristic of initiating at high relative injection pressure drop at low chamber pressure during the start sequence. Data analysis suggests that the two-phase density during engine start results in a high injection velocity, possibly triggering the instabilities predicted by the Hewitt stability curves. Engine ignition instability was successfully mitigated via a higher-chamber pressure start sequence (e.g., 50% power level vs 30%) and operational propellant start temperature limits that maintained \\cold LOX" and \\warm methane" at the engine inlet. The main engine successfully demonstrated 4:1 throttling without chugging during mainstage, but chug instabilities were observed during some engine shutdown sequences at low injector pressure drop, especially during vehicle landing.

  17. 45 CFR 1623.6 - Interim funding.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 45 Public Welfare 4 2013-10-01 2013-10-01 false Interim funding. 1623.6 Section 1623.6 Public Welfare Regulations Relating to Public Welfare (Continued) LEGAL SERVICES CORPORATION SUSPENSION PROCEDURES § 1623.6 Interim funding. (a) Pending the completion of suspension proceedings under this...

  18. 45 CFR 1623.6 - Interim funding.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 45 Public Welfare 4 2014-10-01 2014-10-01 false Interim funding. 1623.6 Section 1623.6 Public Welfare Regulations Relating to Public Welfare (Continued) LEGAL SERVICES CORPORATION SUSPENSION PROCEDURES § 1623.6 Interim funding. (a) Pending the completion of suspension proceedings under this...

  19. 45 CFR 1623.6 - Interim funding.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 45 Public Welfare 4 2011-10-01 2011-10-01 false Interim funding. 1623.6 Section 1623.6 Public Welfare Regulations Relating to Public Welfare (Continued) LEGAL SERVICES CORPORATION SUSPENSION PROCEDURES § 1623.6 Interim funding. (a) Pending the completion of suspension proceedings under this...

  20. 45 CFR 1623.6 - Interim funding.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 45 Public Welfare 4 2012-10-01 2012-10-01 false Interim funding. 1623.6 Section 1623.6 Public Welfare Regulations Relating to Public Welfare (Continued) LEGAL SERVICES CORPORATION SUSPENSION PROCEDURES § 1623.6 Interim funding. (a) Pending the completion of suspension proceedings under this...

  1. 40 CFR 94.12 - Interim provisions.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 20 2010-07-01 2010-07-01 false Interim provisions. 94.12 Section 94.12 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) AIR PROGRAMS (CONTINUED... for Compression-Ignition Marine Engines § 94.12 Interim provisions. This section contains...

  2. 45 CFR 1623.6 - Interim funding.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 45 Public Welfare 4 2010-10-01 2010-10-01 false Interim funding. 1623.6 Section 1623.6 Public Welfare Regulations Relating to Public Welfare (Continued) LEGAL SERVICES CORPORATION SUSPENSION PROCEDURES § 1623.6 Interim funding. (a) Pending the completion of suspension proceedings under this...

  3. 40 CFR 1042.145 - Interim provisions.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 32 2010-07-01 2010-07-01 false Interim provisions. 1042.145 Section... Standards and Related Requirements § 1042.145 Interim provisions. (a) General. The provisions in this section apply instead of other provisions in this part. This section describes when these...

  4. 39 CFR 952.6 - Interim impounding.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 39 Postal Service 1 2010-07-01 2010-07-01 false Interim impounding. 952.6 Section 952.6 Postal Service UNITED STATES POSTAL SERVICE PROCEDURES RULES OF PRACTICE IN PROCEEDINGS RELATIVE TO FALSE REPRESENTATION AND LOTTERY ORDERS § 952.6 Interim impounding. In preparation for or during the pendency of...

  5. Locating Interim Assessments within Teachers' Assessment Practice

    ERIC Educational Resources Information Center

    Riggan, Matthew; Olah, Leslie Nabors

    2011-01-01

    Promising research on the teaching and learning impact of classroom-embedded formative assessment has spawned interest in a broader array of assessment tools and practices, including interim assessment. Although researchers have begun to explore the impact of interim assessments in the classroom, like other assessment tools and practices, they…

  6. 20 CFR 410.234 - Interim provisions.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 20 Employees' Benefits 2 2010-04-01 2010-04-01 false Interim provisions. 410.234 Section 410.234 Employees' Benefits SOCIAL SECURITY ADMINISTRATION FEDERAL COAL MINE HEALTH AND SAFETY ACT OF 1969, TITLE IV... Evidence § 410.234 Interim provisions. (a) Notwithstanding any other provision of this subpart, a...

  7. 24 CFR 35.820 - Interim controls.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... completion of the risk assessment. In units in which a child of less than 6 years of age moves in after the completion of the risk assessment, interim controls shall be completed no later than 90 days after the move... property, interim controls shall be completed no later than 12 months after completion of the...

  8. 24 CFR 35.820 - Interim controls.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... completion of the risk assessment. In units in which a child of less than 6 years of age moves in after the completion of the risk assessment, interim controls shall be completed no later than 90 days after the move... property, interim controls shall be completed no later than 12 months after completion of the...

  9. 24 CFR 35.820 - Interim controls.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... completion of the risk assessment. In units in which a child of less than 6 years of age moves in after the completion of the risk assessment, interim controls shall be completed no later than 90 days after the move... property, interim controls shall be completed no later than 12 months after completion of the...

  10. 24 CFR 35.820 - Interim controls.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... completion of the risk assessment. In units in which a child of less than 6 years of age moves in after the completion of the risk assessment, interim controls shall be completed no later than 90 days after the move... property, interim controls shall be completed no later than 12 months after completion of the...

  11. 24 CFR 35.1330 - Interim controls.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... Development LEAD-BASED PAINT POISONING PREVENTION IN CERTAIN RESIDENTIAL STRUCTURES Methods and Standards for Lead-Paint Hazard Evaluation and Hazard Reduction Activities § 35.1330 Interim controls. Interim controls of lead-based paint hazards identified in a risk assessment shall be conducted in accordance...

  12. 24 CFR 35.1330 - Interim controls.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... Development LEAD-BASED PAINT POISONING PREVENTION IN CERTAIN RESIDENTIAL STRUCTURES Methods and Standards for Lead-Paint Hazard Evaluation and Hazard Reduction Activities § 35.1330 Interim controls. Interim controls of lead-based paint hazards identified in a risk assessment shall be conducted in accordance...

  13. 24 CFR 35.1330 - Interim controls.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... Development LEAD-BASED PAINT POISONING PREVENTION IN CERTAIN RESIDENTIAL STRUCTURES Methods and Standards for Lead-Paint Hazard Evaluation and Hazard Reduction Activities § 35.1330 Interim controls. Interim controls of lead-based paint hazards identified in a risk assessment shall be conducted in accordance...

  14. 24 CFR 35.1330 - Interim controls.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... Development LEAD-BASED PAINT POISONING PREVENTION IN CERTAIN RESIDENTIAL STRUCTURES Methods and Standards for Lead-Paint Hazard Evaluation and Hazard Reduction Activities § 35.1330 Interim controls. Interim controls of lead-based paint hazards identified in a risk assessment shall be conducted in accordance...

  15. 24 CFR 35.1330 - Interim controls.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... Development LEAD-BASED PAINT POISONING PREVENTION IN CERTAIN RESIDENTIAL STRUCTURES Methods and Standards for Lead-Paint Hazard Evaluation and Hazard Reduction Activities § 35.1330 Interim controls. Interim controls of lead-based paint hazards identified in a risk assessment shall be conducted in accordance...

  16. Mission Need Statement: Calcine Disposition Project Major Systems Acquisition Project

    SciTech Connect

    J. T. Beck

    2007-04-26

    This document identifies the need to establish the Calcine Disposition Project to determine and implement the final disposition of calcine including characterization, retrieval, treatment (if necessary), packaging, loading, onsite interim storage pending shipment to a repository or interim storage facility, and disposition of related facilities.

  17. Solid waste burial grounds interim safety analysis

    SciTech Connect

    Saito, G.H.

    1994-10-01

    This Interim Safety Analysis document supports the authorization basis for the interim operation and restrictions on interim operations for the near-surface land disposal of solid waste in the Solid Waste Burial Grounds. The Solid Waste Burial Grounds Interim Safety Basis supports the upgrade progress for the safety analysis report and the technical safety requirements for the operations in the Solid Waste Burial Grounds. Accident safety analysis scenarios have been analyzed based on the significant events identified in the preliminary hazards analysis. The interim safety analysis provides an evaluation of the operations in the Solid Waste Burial Grounds to determine if the radiological and hazardous material exposures will be acceptable from an overall health and safety standpoint to the worker, the onsite personnel, the public, and the environment.

  18. Fusion Breeder Program interim report

    SciTech Connect

    Moir, R.; Lee, J.D.; Neef, W.

    1982-06-11

    This interim report for the FY82 Fusion Breeder Program covers work performed during the scoping phase of the study, December, 1981-February 1982. The goals for the FY82 study are the identification and development of a reference blanket concept using the fission suppression concept and the definition of a development plan to further the fusion breeder application. The context of the study is the tandem mirror reactor, but emphasis is placed upon blanket engineering. A tokamak driver and blanket concept will be selected and studied in more detail during FY83.

  19. Vet Centers. Interim final rule.

    PubMed

    2015-08-04

    The Department of Veterans Affairs (VA) is amending its medical regulation that governs Vet Center services. The National Defense Authorization Act for Fiscal Year 2013 (the 2013 Act) requires Vet Centers to provide readjustment counseling services to broader groups of veterans, members of the Armed Forces, including a member of a reserve component of the Armed Forces, and family members of such veterans and members. This interim final rule amends regulatory criteria to conform to the 2013 Act, to include new and revised definitions.

  20. 40 CFR 270.73 - Termination of interim status.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 26 2010-07-01 2010-07-01 false Termination of interim status. 270.73... (CONTINUED) EPA ADMINISTERED PERMIT PROGRAMS: THE HAZARDOUS WASTE PERMIT PROGRAM Interim Status § 270.73 Termination of interim status. Interim status terminates when: (a) Final administrative disposition of...

  1. 46 CFR 309.101 - Amendment of interim binders.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 46 Shipping 8 2010-10-01 2010-10-01 false Amendment of interim binders. 309.101 Section 309.101... INSURANCE § 309.101 Amendment of interim binders. The interim binder for a vessel whose stated valuation is... after the attachment of the insurance under the interim binder to which such valuation...

  2. 40 CFR 270.71 - Operation during interim status.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 26 2010-07-01 2010-07-01 false Operation during interim status. 270... (CONTINUED) EPA ADMINISTERED PERMIT PROGRAMS: THE HAZARDOUS WASTE PERMIT PROGRAM Interim Status § 270.71 Operation during interim status. (a) During the interim status period the facility shall not: (1)...

  3. 49 CFR 106.35 - Interim final rule.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 49 Transportation 2 2010-10-01 2010-10-01 false Interim final rule. 106.35 Section 106.35... PHMSA Rulemaking Documents § 106.35 Interim final rule. An interim final rule is issued without first... requirements and their effective date. PHMSA may issue an interim final rule if it finds, for good cause,...

  4. 5 CFR 772.102 - Interim personnel actions.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 5 Administrative Personnel 2 2010-01-01 2010-01-01 false Interim personnel actions. 772.102... REGULATIONS (CONTINUED) INTERIM RELIEF General § 772.102 Interim personnel actions. When an employee or... administrative judge granting interim relief under 5 U.S.C. 7701(b)(2)(A) and a petition for review of...

  5. 33 CFR 1.05-45 - Interim rule.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 33 Navigation and Navigable Waters 1 2010-07-01 2010-07-01 false Interim rule. 1.05-45 Section 1... PROVISIONS Rulemaking § 1.05-45 Interim rule. (a) An interim rule may be issued when it is in the public... example, an interim rule may be issued in instances when normal procedures for notice and comment prior...

  6. Combustion Stability Characteristics of the Project Morpheus Liquid Oxygen/Liquid Methane Main Engine

    NASA Technical Reports Server (NTRS)

    Melcher, J. C.; Morehead, Robert L.

    2014-01-01

    The Project Morpheus liquid oxygen (LOX) / liquid methane rocket engines demonstrated acousticcoupled combustion instabilities during sea-level ground-based testing at the NASA Johnson Space Center (JSC) and Stennis Space Center (SSC). High-amplitude, 1T, 1R, 1T1R (and higher order) modes appear to be triggered by injector conditions. The instability occurred during the Morpheus-specific engine ignition/start sequence, and did demonstrate the capability to propagate into mainstage. However, the instability was never observed to initiate during mainstage, even at low power levels. The Morpheus main engine is a JSC-designed 5,000 lbf-thrust, 4:1 throttling, pressure-fed cryogenic engine using an impinging element injector design. Two different engine designs, named HD4 and HD5, and two different builds of the HD4 engine all demonstrated similar instability characteristics. Through the analysis of more than 200 hot fire tests on the Morpheus vehicle and SSC test stand, a relationship between ignition stability and injector/chamber pressure was developed. The instability has the distinct characteristic of initiating at high relative injection pressure drop (dP) at low chamber pressure (Pc); i.e., instabilities initiated at high dP/Pc at low Pc during the start sequence. The high dP/Pc during start results during the injector /chamber chill-in, and is enhanced by hydraulic flip in the injector orifice elements. Because of the fixed mixture ratio of the existing engine design (the main valves share a common actuator), it is not currently possible to determine if LOX or methane injector dP/Pc were individual contributors (i.e., LOX and methane dP/Pc typically trend in the same direction within a given test). The instability demonstrated initiation characteristic of starting at or shortly after methane injector chillin. Colder methane (e.g., sub-cooled) at the injector inlet prior to engine start was much more likely to result in an instability. A secondary effect of LOX

  7. Using a Visible Light-Polymerized Resin to Fabricate an Interim Partial Removable Dental Prosthesis.

    PubMed

    Segal, Aaron; Yu, Hui Wen; Elkassaby, Heba

    2017-02-01

    An interim partial removable dental prosthesis (RDP) is any dental prosthesis that replaces some teeth in a partially dentate arch designed to enhance esthetics, stabilization, and/or function for a limited period of time, after which it is to be replaced by a definitive dental prosthesis. This article describes a technique that uses a visible light-polymerized (VLP) resin as the base material for an interim partial RDP. This technique can be easily accomplished in a dental office or laboratory and results in a predictable dental prosthesis. This technique eliminates the need for laboratory processing.

  8. An interim overview of LDEF materials findings

    NASA Technical Reports Server (NTRS)

    Stein, Brad A.

    1992-01-01

    The flight and retrieval of the National Aeronautics and Space Administration's Long Duration Exposure Facility (LDEF) provided an opportunity for the study of the low-Earth orbit (LEO) environment and long-duration space environmental effects (SEE) on materials that is unparalleled in the history of the U.S. Space Program. The remarkable flight attitude stability of LDEF enables specific analyses of various individual and combined effects of LEO environmental parameters on identical materials on the same space vehicle. This paper provides an overview of the interim LDEF materials findings of the Principal Investigators and the Materials Special Investigation Group. In general, the LDEF data is remarkably consistent; LDEF will provide a 'benchmark' for materials design data bases for satellites in low-Earth orbit. Some materials were identified to be encouragingly resistant to LEO SEE for 5.8 years; other 'space qualified' materials displayed significant environmental degradation. Molecular contamination was widespread; LDEF offers an unprecedented opportunity to provide a unified perspective of unmanned LEO spacecraft contamination mechanisms. New material development requirements for long-term LEO missions have been identified and current ground simulation testing methods/data for new, durable materials concepts can be validated with LDEF results. LDEF findings are already being integrated into the design of Space Station Freedom.

  9. In Situ Mercury Stabilization (ISMS) Treatment: Technology Maturation Project Phase I Status Report

    SciTech Connect

    Kalb,P.D.; Milian, L.

    2008-03-01

    further developed it has the potential for large-scale in-situ treatment of contaminated soils that could substantially reduce the prohibitive cost of thermal desorption and/or excavation and disposal. Licensing and spin-off technology development opportunities would then be viable. Depending on performance and regulatory acceptance, the treated mercury could either be excavated for disposal elsewhere or left in place as a stable alternative. Excavated spent treatment rods could be processed by the SPSS process to reduce the potential for dispersion and lower leachability even further. The Phase I objectives of the In Situ Mercury Stabilization Treatment Process Technology Maturation Project were to: (1) replicate the original bench-scale results that formed the basis for BNL's patent application, i.e., mercury contamination in soil will migrate to and react with 'rods' containing sulfur and/or sulfur compounds, (2) provide enough information to evaluate a decision to conduct further development, and (3) establish some of the critical parameters that require further technology maturation during Phase II. The information contained in this report summarizes the work conducted in Phase I to meet these objectives.

  10. Space shuttle SRM interim contract, part 1

    NASA Technical Reports Server (NTRS)

    1974-01-01

    Essential studies and analyses required to integrate the SRM into the booster and overall space shuttle system. Emphasis was placed on the case, nozzle, insulation, and propellant components with resulting performance, weight, and structural load characteristics being generated. Effort conducted during the time period of this contract included studies, analyses, planning, and preliminary design activities. Technical requirements identified in the SRM Project Request for Proposal No. 8-1-4-94-98401 and Thiokol's proposed SRM design (designated Configuration 0) established the basis for this effort. The requirements were evaluated jointly with MSFC and altered where necessary to incorporate new information that evolved after issuance of the RFP and during the course of this interim contract. Revised water impact loads and load distributions were provided based on additional model test data and analytical effort conducted by NASA subsequent to the RFP release. Launch pad peaking loads into the SRM aft skirt were provided which also represented a change from RFP requirements. A modified SRM/External Tank (ET) attachment configuration with new structural load data was supplied by NASA, and direction was received to include a 2 percent inert weight contingency.

  11. Hanford low-level tank waste interim performance assessment

    SciTech Connect

    Mann, F.M.

    1997-09-12

    The Hanford Low-Level Tank Waste Interim Performance Assessment examines the long-term environmental and human health effects associated with the disposal of the low-level fraction of the Hanford single and double-shell tank waste in the Hanford Site 200 East Area. This report was prepared as a good management practice to provide needed information about the relationship between the disposal system design and performance early in the disposal system project cycle. The calculations in this performance assessment show that the disposal of the low-level fraction can meet environmental and health performance objectives.

  12. Hanford low-level tank waste interim performance assessment

    SciTech Connect

    Mann, F.M.

    1996-09-16

    The Hanford Low-Level Tank Waste Interim Performance Assessment examines the long-term environmental and human health effects associated with the disposal of the low-level fraction of the Hanford single- and double-shell tank waste in the Hanford Site 200 East Area. This report was prepared as a good management practice to provide needed information about the relationship between the disposal system design and its performance as early as possible in the project cycle. The calculations in this performance assessment show that the disposal of the low-level fraction can meet environmental and health performance objectives.

  13. The School Action Effectiveness Study: Second Interim Report, Part II. Report No. 342.

    ERIC Educational Resources Information Center

    Gottfredson, Gary D.; And Others

    This report, the second part of a longer study prepared by the Delinquency and School Environments Program, further describes interim results of the program's national evaluation of the Office of Juvenile Justice and Delinquency Prevention's (OJJDP's) Alternative Education Program. The report consists of evaluations of 14 specific projects: (1)…

  14. Improvement of the recursive projection method for linear iterative scheme stabilization based on an approximate eigenvalue problem

    NASA Astrophysics Data System (ADS)

    Renac, Florent

    2011-06-01

    An algorithm for stabilizing linear iterative schemes is developed in this study. The recursive projection method is applied in order to stabilize divergent numerical algorithms. A criterion for selecting the divergent subspace of the iteration matrix with an approximate eigenvalue problem is introduced. The performance of the present algorithm is investigated in terms of storage requirements and CPU costs and is compared to the original Krylov criterion. Theoretical results on the divergent subspace selection accuracy are established. The method is then applied to the resolution of the linear advection-diffusion equation and to a sensitivity analysis for a turbulent transonic flow in the context of aerodynamic shape optimization. Numerical experiments demonstrate better robustness and faster convergence properties of the stabilization algorithm with the new criterion based on the approximate eigenvalue problem. This criterion requires only slight additional operations and memory which vanish in the limit of large linear systems.

  15. Atmospheric Effects of Subsonic Aircraft: Interim Assessment Report of the Advanced Subsonic Technology Program

    NASA Technical Reports Server (NTRS)

    Friedl, Randall R. (Editor)

    1997-01-01

    This first interim assessment of the subsonic assessment (SASS) project attempts to summarize concisely the status of our knowledge concerning the impacts of present and future subsonic aircraft fleets. It also highlights the major areas of scientific uncertainty, through review of existing data bases and model-based sensitivity studies. In view of the need for substantial improvements in both model formulations and experimental databases, this interim assessment cannot provide confident numerical predictions of aviation impacts. However, a number of quantitative estimates are presented, which provide some guidance to policy makers.

  16. Interim Policy for Evaluation of Stereoisomeric Pesticides

    EPA Pesticide Factsheets

    An interim approach for determining data requirements for non-racemic mixtures of stereoisomeric pesticides. These data are needed in order to assess the risk posed to ecosystems and drinking water sources by these mixtures.

  17. 40 CFR 180.319 - Interim tolerances.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... TOLERANCES AND EXEMPTIONS FOR PESTICIDE CHEMICAL RESIDUES IN FOOD Specific Tolerances § 180.319 Interim... pesticide chemicals in or on the following raw agricultural commodities: Substances Uses Tolerance in...

  18. Interim Prosthesis Options for Dental Implants.

    PubMed

    Siadat, Hakimeh; Alikhasi, Marzieh; Beyabanaki, Elaheh

    2016-01-24

    Dental implants have become a popular treatment modality for replacing missing teeth. In this regard, the importance of restoring patients with function during the implant healing period has grown in recent decades. Esthetic concerns, especially in the anterior region of the maxilla, should also be considered until the definitive restoration is delivered. Another indication for such restorations is maintenance of the space required for esthetic and functional definitive restorations in cases where the implant site is surrounded by natural teeth. Numerous articles have described different types of interim prostheses and their fabrication techniques. This article aims to briefly discuss all types of implant-related interim prostheses by different classification including provisional timing (before implant placement, after implant placement in unloading and loading periods), materials, and techniques used for making the restorations, the type of interim prosthesis retention, and definitive restoration. Furthermore, the abutment torque for such restorations and methods for transferring the soft tissue from interim to definitive prostheses are addressed.

  19. The WFIRST Interim Design Reference Mission: Capabilities, Constraints, and Open Questions

    NASA Technical Reports Server (NTRS)

    Kruk, Jeffrey W.

    2012-01-01

    The Project Office and Science Definition Team for the Wide-Field Infrared Survey Telescope (WFIRST) are in the midst of a pre-Phase A study to establish a Design Reference Mission (DRM). An Interim report was released in June 2011, with a final report due later in 2012. The predicted performance of the Interim DRM Observatory will be described, including optical quality, observing efficiency, and sensitivity for representative observing scenarios. Observing constraints and other limitations on performance will also be presented, with an emphasis on potential Guest Observer programs. Finally, a brief status update will be provided on open trade studies of interest to the scientific community. The final DRM may differ from the Interim DRM presented here. However, the underlying requirements of the scientific programs are not expected to change, hence the capabilities of the IDRM are likely to be maintained even if the implementation changes in significant ways.

  20. The Interim: Until You Achieve an Operationally Responsive Ground System

    NASA Technical Reports Server (NTRS)

    Wendlandt, Bob; Clarke, Kelly; Miyamoto, Charles; Lei, Jordan; Owen-Mankovich, Kyran

    2008-01-01

    Everyone wants to achieve a 'Responsive' Ground Data System (GDS), but that takes time. What do you do in the interim? Our group, called the Integration, Test and Deployment Team (ITD), is a group of responsive engineers whose primary focus is to assist JPL projects to successfully adapt, test, integrate and deploy their ground data system. The team configures and adapts the GDS for a project, so that analysts, engineers and scientist do not need to be experts in the GDS to operate it. The team has developed a human interface to accommodate all types of users. It provides Graphical User Interfaces (GUI's) for those that want GUI's, command line interfaces for those that want control, and selection button interfaces for other users. The cornerstone of a responsive Ground Data System is responsive people. Without individuals who can be aware of a project's changing needs and requirements, how can the GDS become responsive?.

  1. The Interim : until you achieve an operationally responsive ground system

    NASA Technical Reports Server (NTRS)

    Wendlandt, Bob; Clarke, Kelly; Lei, Jordan; Miyamoto, Charles; Owen-Mankovich, Kyran

    2008-01-01

    Everyone wants to achieve a 'Responsive' Ground Data System (GDS), but that takes time. What do you do in the interim? Our group, called the Integration, Test and Deployment Team (ITD), is a group of responsive engineers whose primary focus is to assist JPL projects to successfully adapt, test, integrate and deploy their ground data system. The team configures and adapts the GDS for a project, so that analysts, engineers and scientist do not need to be experts in the GDS to operate it. The team has developed a human interface to accommodate all types of users. It provides Graphical User Interfaces (GUI's) for those that want GUI's, command line interfaces for those that want control, and selection button interfaces for other users. The cornerstone of a responsive Ground Data System is responsive people. Without individuals who can be aware of a project's changing needs and requirements, how can the GDS become responsive

  2. 78 FR 56752 - Interim Staff Guidance Specific Environmental Guidance for Integral Pressurized Water Reactors...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-09-13

    ... COMMISSION Interim Staff Guidance Specific Environmental Guidance for Integral Pressurized Water Reactors Reviews AGENCY: Nuclear Regulatory Commission. ACTION: Draft Interim Staff Guidance; request for comment... comment on, draft Interim Staff Guidance (ISG) ESP/COL-ISG-027, ``Interim Staff Guidance...

  3. Engineering feasibility analysis for in-situ stabilization of Canonsburg residues. [UMTRA project

    SciTech Connect

    Not Available

    1982-01-01

    The US Department of Energy is considering several methods for carrying out remedial actions in Canonsburg, Pennsylvania, at the site of an inactive uranium-processing mill. The main objective of this study is to determine the feasibility of in-situ stabilization as the remedial action. In-situ stabilization is an alternative to site decontamination and offsite disposal. The problems associated with offsite hauling of large quantities of contaminated material and with the location and development of a new disposal site could be avoided by the implementation of an in-situ stabilization concept. In addition, the in-situ approach would be more cost-effective than offsite disposal. This study will establish that a technically feasible and implementable in-situ stabilization concept can be developed that meets regulatory requirements and is cost effective. This study in no way commits the DOE to implement any specific actions described herein. 11 refs., 30 figs., 24 tabs.

  4. Environmental Assessment for Slope Stabilization Projects at Fort MacArthur, San Pedro, California

    DTIC Science & Technology

    2012-01-01

    dewatering, earthwork, structural stabilization, and material strengthening. Page 2 of 2 Alternatives Considered: The Alternative One (Proposed Action) and a...The slopes consist mainly of fill material , so it is unlikely that archaeological resources are located within the non-native soils. An...Temporary road closures may be necessary during stabilization to allow construction equipment room to operate, while maintaining a safe perimeter

  5. Supplement Analysis for the Watershed Management Program EIS (DOE/EIS-0265/SA-95) - Libby Creek Channel Stabilization Project

    SciTech Connect

    Keller, Carl J.

    2002-10-21

    BPA proposes to fund MFWP to construct a channel stabilization project, which would restore the dimension, pattern, and profile of 3,200 feet of Libby Creek. The project calls for shaping cut banks to a 2:1 slope, installing root wads and tree revetments; and planting and restoring native grasses and riparian shrubs along the margin of the channel. Cross vanes (constructed from rock) and trees will also be established to control channel gradient within the project area. This project is one restoration phase on Libby Creek, and was identified as important by the Libby Area Conservation District, MFWP, U.S. Forest Service, and U.S. Army Corps of Engineers. Libby Creek is also the focus of restoration efforts based, in part, on the finding of the Montana Governor’s Bull Trout Restoration Technical Committee. This Committee identified Libby Creek as critical spawning and migratory habitat for the threatened bull trout. This project reach of Libby Creek is also rearing habitat for resident redband trout and resident and fluvial bull trout migrating from the Kootenai River.

  6. Methods Data Qualification Interim Report

    SciTech Connect

    R. Sam Alessi; Tami Grimmett; Leng Vang; Dave McGrath

    2010-09-01

    The overall goal of the Next Generation Nuclear Plant (NGNP) Data Management and Analysis System (NDMAS) is to maintain data provenance for all NGNP data including the Methods component of NGNP data. Multiple means are available to access data stored in NDMAS. A web portal environment allows users to access data, view the results of qualification tests and view graphs and charts of various attributes of the data. NDMAS also has methods for the management of the data output from VHTR simulation models and data generated from experiments designed to verify and validate the simulation codes. These simulation models represent the outcome of mathematical representation of VHTR components and systems. The methods data management approaches described herein will handle data that arise from experiment, simulation, and external sources for the main purpose of facilitating parameter estimation and model verification and validation (V&V). A model integration environment entitled ModelCenter is used to automate the storing of data from simulation model runs to the NDMAS repository. This approach does not adversely change the why computational scientists conduct their work. The method is to be used mainly to store the results of model runs that need to be preserved for auditing purposes or for display to the NDMAS web portal. This interim report demonstrates the currently development of NDMAS for Methods data and discusses data and its qualification that is currently part of NDMAS.

  7. High Temperature Materials Interim Data Qualification Report

    SciTech Connect

    Nancy Lybeck

    2010-08-01

    ABSTRACT Projects for the very high temperature reactor (VHTR) Technology Development Office provide data in support of Nuclear Regulatory Commission licensing of the VHTR. Fuel and materials to be used in the reactor are tested and characterized to quantify performance in high temperature and high fluence environments. The VHTR program has established the NGNP Data Management and Analysis System (NDMAS) to ensure that VHTR data are qualified for use, stored in a readily accessible electronic form, and analyzed to extract useful results. This document focuses on the first NDMAS objective. It describes the High Temperature Materials characterization data stream, the processing of these data within NDMAS, and reports the interim FY2010 qualification status of the data. Data qualification activities within NDMAS for specific types of data are determined by the data qualification category assigned by the data generator. The High Temperature Materials data are being collected under NQA-1 guidelines, and will be qualified data. For NQA-1 qualified data, the qualification activities include: (1) capture testing, to confirm that the data stored within NDMAS are identical to the raw data supplied, (2) accuracy testing to confirm that the data are an accurate representation of the system or object being measured, and (3) documenting that the data were collected under an NQA-1 or equivalent Quality Assurance program. Currently, data from two test series within the High Temperature Materials data stream have been entered into the NDMAS vault: 1. Tensile Tests for Sm (i.e., Allowable Stress) Confirmatory Testing – 1,403,994 records have been inserted into the NDMAS database. Capture testing is in process. 2. Creep-Fatigue Testing to Support Determination of Creep-Fatigue Interaction Diagram – 918,854 records have been processed and inserted into the NDMAS database. Capture testing is in process.

  8. Plutonium uranium extraction (PUREX) end state basis for interim operation (BIO) for surveillance and maintenance

    SciTech Connect

    DODD, E.N.

    1999-05-12

    This Basis for Interim Operation (BIO) was developed for the PUREX end state condition following completion of the deactivation project. The deactivation project has removed or stabilized the hazardous materials within the facility structure and equipment to reduce the hazards posed by the facility during the surveillance and maintenance (S and M) period, and to reduce the costs associated with the S and M. This document serves as the authorization basis for the PUREX facility, excluding the storage tunnels, railroad cut, and associated tracks, for the deactivated end state condition during the S and M period. The storage tunnels, and associated systems and areas, are addressed in WHC-SD-HS-SAR-001, Rev. 1, PUREX Final Safety Analysis Report. During S and M, the mission of the facility is to maintain the conditions and equipment in a manner that ensures the safety of the workers, environment, and the public. The S and M phase will continue until the final decontamination and decommissioning (D and D) project and activities are begun. Based on the methodology of DOE-STD-1027-92, Hazards Categorization and Accident Analysis Techniques for Compliance with DOE Order 5480.23, Nuclear Safety Analysis Reports, the final facility hazards category is identified as hazards category This considers the remaining material inventories, form and distribution of the material, and the energies present to initiate events of concern. Given the current facility configuration, conditions, and authorized S and M activities, there are no operational events identified resulting in significant hazard to any of the target receptor groups (e.g., workers, public, environment). The only accident scenarios identified with consequences to the onsite co-located workers were based on external natural phenomena, specifically an earthquake. The dose consequences of these events are within the current risk evaluation guidelines and are consistent with the expectations for a hazards category 2

  9. A Project Assessment of Stabilizing System of WT Generation using Rechargeable Battery

    NASA Astrophysics Data System (ADS)

    Kojima, Yasuhiro; Takano, Tomihiro; Tanikawa, Ryoichi; Takagi, Tetsuro; Hirooka, Koutaro; Kumagai, Sadatoshi

    The expansion of the renewable energy introduction is examined as measures for controlling global warming. Wind power generation is expected as effective power resource, but the negative impact from the difficulty of an unstable output is concerned. In recent years, WT generation with contract of cut-of with shorting adjusting power and with rechargeable battery for stabilizing control are examined, but the introduction has not been accelerated yet because there is an influence in WT generation entrepreneur's business. In this paper, we make a brief summary of relation between the fluctuation of wind power generation and stability of electric power operation, and two types of approach; cut-off contract and stabilization using rechargeable battery. For the stabilization using battery, there are two methods, one is reduction control and the other is constant control. We propose a new control method for constant control based on profit optimization considering WT generation forecast and its risk of deviation. We also propose the estimation method for the .limitation of battery installation. Simulation results show the efficiency of our proposed methods.

  10. Development of the RGB LEDs color mixing mechanism for stability the color temperature at different projection distances.

    PubMed

    Hung, Chih-Ching

    2015-01-01

    In lighting application, the color mixing of the RGB LEDs can provide more color selection in correlated color temperature and color rendering. Therefore, the purpose of this study is to propose a RGB color mixing mechanism by applying the mechanism design. Three sets of lamp-type RGB LEDs are individually installed on three four-bar linkages. A crank is used to drive three groups of RGB LEDs lamp-type to project lights onto a single plane in order to mix the lights. And, simulations of the illuminance and associated color temperatures are conducted by changing the distance to the projection plane, under the assumption that the stability of the color temperature of the projected light does not change according to the projecting height. Thus, the effect of change in the color temperature on color determination by the humans' eyes was avoided. The success of the proposed method will allow medical personnel to choose suitable wavelengths and color temperatures according to the particular requirements of their medical-examination environments.

  11. 46 CFR 309.101 - Amendment of interim binders.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 46 Shipping 8 2011-10-01 2011-10-01 false Amendment of interim binders. 309.101 Section 309.101... INSURANCE § 309.101 Amendment of interim binders. The interim binder for a vessel whose stated valuation is established pursuant to this part shall be deemed to have been amended on the first day of the...

  12. 46 CFR 309.101 - Amendment of interim binders.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 46 Shipping 8 2013-10-01 2013-10-01 false Amendment of interim binders. 309.101 Section 309.101... INSURANCE § 309.101 Amendment of interim binders. The interim binder for a vessel whose stated valuation is established pursuant to this part shall be deemed to have been amended on the first day of the...

  13. 18 CFR 385.1113 - Interim relief (Rule 1113).

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 18 Conservation of Power and Water Resources 1 2010-04-01 2010-04-01 false Interim relief (Rule... Under the NGPA § 385.1113 Interim relief (Rule 1113). (a) The petitioner may at any time file a request for interim relief in a proceeding under this subpart, setting forth the legal and factual basis...

  14. 24 CFR 115.203 - Interim certification procedures.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 24 Housing and Urban Development 1 2010-04-01 2010-04-01 false Interim certification procedures... Certification of Substantially Equivalent Agencies § 115.203 Interim certification procedures. (a) Upon receipt of a request for interim certification filed under § 115.202, the Assistant Secretary may...

  15. 48 CFR 801.690-8 - Interim appointment provisions.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 5 2010-10-01 2010-10-01 false Interim appointment... Authority, and Responsibilities 801.690-8 Interim appointment provisions. (a) To ensure availability of procurement support, an interim appointment may be granted for a limited period of time when a candidate...

  16. 10 CFR 205.288 - Interim and ancillary orders.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 10 Energy 3 2010-01-01 2010-01-01 false Interim and ancillary orders. 205.288 Section 205.288... Distribution of Refunds § 205.288 Interim and ancillary orders. The Director of the Office of Hearings and Appeals or his designee may issue any interim or ancillary orders, or make any rulings or...

  17. 78 FR 49782 - Interim Staff Guidance on Changes During Construction

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-08-15

    ... COMMISSION Interim Staff Guidance on Changes During Construction AGENCY: Nuclear Regulatory Commission. ACTION: Draft interim staff guidance; request for comment. SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing this notice for use of, and to solicit public comment on the draft Interim...

  18. 47 CFR 51.611 - Interim wholesale rates.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 47 Telecommunication 3 2010-10-01 2010-10-01 false Interim wholesale rates. 51.611 Section 51.611... Resale § 51.611 Interim wholesale rates. (a) If a state commission cannot, based on the information... commission may elect to establish an interim wholesale rate as described in paragraph (b) of this section....

  19. An Approach for Evaluating the Technical Quality of Interim Assessments

    ERIC Educational Resources Information Center

    Li, Ying; Marion, Scott; Perie, Marianne; Gong, Brian

    2010-01-01

    Increasing numbers of schools and districts have expressed interest in interim assessment systems to prepare for summative assessments and to improve teaching and learning. However, with so many commercial interim assessments available, schools and districts are struggling to determine which interim assessment is most appropriate to their needs.…

  20. 5 CFR 1209.11 - Duration of stay; interim compliance.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 5 Administrative Personnel 3 2010-01-01 2010-01-01 false Duration of stay; interim compliance... WHISTLEBLOWING Stay Requests § 1209.11 Duration of stay; interim compliance. (a) Duration of stay. A stay becomes...) Interim compliance. An agency must immediately comply with an order granting a stay request. Although...

  1. 40 CFR 270.70 - Qualifying for interim status.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 26 2010-07-01 2010-07-01 false Qualifying for interim status. 270.70... (CONTINUED) EPA ADMINISTERED PERMIT PROGRAMS: THE HAZARDOUS WASTE PERMIT PROGRAM Interim Status § 270.70 Qualifying for interim status. (a) Any person who owns or operates an “existing HWM facility” or a...

  2. 40 CFR 66.23 - Interim recalculation of penalty.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 15 2010-07-01 2010-07-01 false Interim recalculation of penalty. 66... Penalties § 66.23 Interim recalculation of penalty. (a) The Administrator, upon concluding that a previously... respond in accordance with the provisions of § 66.51. The decision to accept the interim calculation or...

  3. 12 CFR 541.18 - Interim Federal savings association.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 12 Banks and Banking 5 2010-01-01 2010-01-01 false Interim Federal savings association. 541.18... REGULATIONS AFFECTING FEDERAL SAVINGS ASSOCIATIONS § 541.18 Interim Federal savings association. The term interim Federal savings association means a Federal savings association chartered by the Office...

  4. 12 CFR 541.19 - Interim state savings association.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 12 Banks and Banking 5 2010-01-01 2010-01-01 false Interim state savings association. 541.19... REGULATIONS AFFECTING FEDERAL SAVINGS ASSOCIATIONS § 541.19 Interim state savings association. The term interim state savings association means a savings association, other than a Federal savings...

  5. 48 CFR 301.603-3 - Interim appointments.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 4 2010-10-01 2010-10-01 false Interim appointments. 301... Interim appointments. If it is essential to appoint an individual as a Contracting Officer who does not... HCA (non-delegable) may make an interim appointment for up to 2 years. If an extension of time...

  6. 42 CFR 417.570 - Interim per capita payments.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 42 Public Health 3 2010-10-01 2010-10-01 false Interim per capita payments. 417.570 Section 417... PREPAYMENT PLANS Medicare Payment: Cost Basis § 417.570 Interim per capita payments. (a) Principle of payment. (1) CMS makes monthly advance payments equivalent to the HMO's or CMP's interim per capita rate...

  7. 5 CFR 531.414 - Interim within-grade increase.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 5 Administrative Personnel 1 2010-01-01 2010-01-01 false Interim within-grade increase. 531.414... UNDER THE GENERAL SCHEDULE Within-Grade Increases § 531.414 Interim within-grade increase. (a) An interim within-grade increase shall be granted to an employee who has: (1) Appealed a negative...

  8. 49 CFR 37.193 - Interim service requirements.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 49 Transportation 1 2010-10-01 2010-10-01 false Interim service requirements. 37.193 Section 37... WITH DISABILITIES (ADA) Over-the-Road Buses (OTRBs) § 37.193 Interim service requirements. (a) Until... of accessible OTRBs, the operator shall meet the following interim service requirements:...

  9. 28 CFR 94.41 - Interim emergency payment.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 28 Judicial Administration 2 2010-07-01 2010-07-01 false Interim emergency payment. 94.41 Section... Terrorism Victim Expense Reimbursement Program Payment of Claims § 94.41 Interim emergency payment. Claimants may apply for an interim emergency payment, prior to a determination under § 94.21(a). If...

  10. 41 CFR 101-29.206 - Interim Federal standard.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 41 Public Contracts and Property Management 2 2010-07-01 2010-07-01 true Interim Federal standard. 101-29.206 Section 101-29.206 Public Contracts and Property Management Federal Property Management... DESCRIPTIONS 29.2-Definitions § 101-29.206 Interim Federal standard. An interim Federal standard is a...

  11. 24 CFR 115.202 - Request for interim certification.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 24 Housing and Urban Development 1 2010-04-01 2010-04-01 false Request for interim certification... Certification of Substantially Equivalent Agencies § 115.202 Request for interim certification. (a) A request for interim certification under this subpart shall be filed with the Assistant Secretary by the...

  12. 40 CFR 270.72 - Changes during interim status.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 26 2010-07-01 2010-07-01 false Changes during interim status. 270.72... (CONTINUED) EPA ADMINISTERED PERMIT PROGRAMS: THE HAZARDOUS WASTE PERMIT PROGRAM Interim Status § 270.72 Changes during interim status. (a) Except as provided in paragraph (b), the owner or operator of...

  13. 7 CFR 900.70 - Applications for interim relief.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 7 Agriculture 8 2010-01-01 2010-01-01 false Applications for interim relief. 900.70 Section 900.70... Applications for interim relief. (a) Filing the application. A person who has filed a petition pursuant to... statement of the objections, if any, of the Administrator to the application for interim relief, and may...

  14. 40 CFR 264.3 - Relationship to interim status standards.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 25 2010-07-01 2010-07-01 false Relationship to interim status... FACILITIES General § 264.3 Relationship to interim status standards. A facility owner or operator who has fully complied with the requirements for interim status—as defined in section 3005(e) of RCRA...

  15. 5 CFR 772.102 - Interim personnel actions.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 5 Administrative Personnel 2 2011-01-01 2011-01-01 false Interim personnel actions. 772.102 Section 772.102 Administrative Personnel OFFICE OF PERSONNEL MANAGEMENT (CONTINUED) CIVIL SERVICE REGULATIONS (CONTINUED) INTERIM RELIEF General § 772.102 Interim personnel actions. When an employee...

  16. 5 CFR 772.102 - Interim personnel actions.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... 5 Administrative Personnel 2 2013-01-01 2013-01-01 false Interim personnel actions. 772.102 Section 772.102 Administrative Personnel OFFICE OF PERSONNEL MANAGEMENT (CONTINUED) CIVIL SERVICE REGULATIONS (CONTINUED) INTERIM RELIEF General § 772.102 Interim personnel actions. When an employee...

  17. 5 CFR 772.102 - Interim personnel actions.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... 5 Administrative Personnel 2 2012-01-01 2012-01-01 false Interim personnel actions. 772.102 Section 772.102 Administrative Personnel OFFICE OF PERSONNEL MANAGEMENT (CONTINUED) CIVIL SERVICE REGULATIONS (CONTINUED) INTERIM RELIEF General § 772.102 Interim personnel actions. When an employee...

  18. CMM Interim Check Design of Experiments (U)

    SciTech Connect

    Montano, Joshua Daniel

    2015-07-29

    Coordinate Measuring Machines (CMM) are widely used in industry, throughout the Nuclear Weapons Complex and at Los Alamos National Laboratory (LANL) to verify part conformance to design definition. Calibration cycles for CMMs at LANL are predominantly one year in length and include a weekly interim check to reduce risk. The CMM interim check makes use of Renishaw’s Machine Checking Gauge which is an off-the-shelf product simulates a large sphere within a CMM’s measurement volume and allows for error estimation. As verification on the interim check process a design of experiments investigation was proposed to test a couple of key factors (location and inspector). The results from the two-factor factorial experiment proved that location influenced results more than the inspector or interaction.

  19. Design review report FFTF interim storage cask

    SciTech Connect

    Scott, P.L.

    1995-01-03

    Final Design Review Report for the FFTF Interim Storage Cask. The Interim Storage Cask (ISC) will be used for long term above ground dry storage of FFTF irradiated fuel in Core Component Containers (CCC)s. The CCC has been designed and will house assemblies that have been sodium washed in the IEM Cell. The Solid Waste Cask (SWC) will transfer a full CCC from the IEM Cell to the RSB Cask Loading Station where the ISC will be located to receive it. Once the loaded ISC has been sealed at the RSB Cask Loading Station, it will be transferred by facility crane to the DSWC Transporter. After the ISC has been transferred to the Interim Storage Area (ISA), which is yet to be designed, a mobile crane will be used to place the ISC in its final storage location.

  20. Collaborative Research: Robust Climate Projections and Stochastic Stability of Dynamical Systems

    SciTech Connect

    Ilya Zaliapin

    2011-10-12

    This project focused on conceptual exploration of El Nino/Southern Oscillation (ENSO) variability and sensitivity using a Delay Differential Equation developed in the project. We have (i) established the existence and continuous dependence of solutions of the model (ii) explored multiple models solutions, and the distribution of solutions extrema, and (iii) established and explored the phase locking phenomenon and the existence of multiple solutions for the same values of model parameters. In addition, we have applied to our model the concept of pullback attractor, which greatly facilitated predictive understanding of the nonlinear model's behavior.

  1. Interim Control Module Extraction Strut Assembly

    NASA Technical Reports Server (NTRS)

    Hansen, Chris

    1999-01-01

    The Interim Control Module is a propulsion and attitude control module for the International Space Station developed to serve as a replacement for the Russian Service Module in the event that Russia does not deliver the hardware as expected. The hardware was developed through a joint NASA/Naval Research Laboratory program and is based on a Department of Defense payload. This paper discusses the development and testing of the Extraction Strut hardware that will be used to assist in removing the Interim Control Module from the Shuttle's payload bay.

  2. Interim Land Use Control Implementation Plan

    NASA Technical Reports Server (NTRS)

    Applegate, Joseph L.

    2014-01-01

    This Interim Land Use Control Implementation Plan (LUCIP) has been prepared to inform current and potential future users of the Kennedy Space Center (KSC) Contractors Road Heavy Equipment (CRHE) Area (SWMU 055; "the Site") of institutional controls that have been implemented at the Site1. Although there are no current unacceptable risks to human health or the environment associated with the CRHE Area, an interim institutional land use control (LUC) is necessary to prevent human health exposure to volatile organic compound (VOC)-affected groundwater at the Site. Controls will include periodic inspection, condition certification, and agency notification.

  3. Closed-loop phase stabilizing and phase stepping methods for fiber-optic projected-fringe digital interferometry.

    PubMed

    Chao, Zhang; Fa-Jie, Duan

    2011-11-01

    Closed-loop active homodyne control can be used to make an interferometer steady against phase fluctuating followed by, for example, temperature gradients. This technology is introduced to stabilize π/2 -rad phase steps in a full-field interferometer. Two beams emitted from a fiber-optic coupler are combined to form an interference fringe pattern on a diffusely reflecting object. Fresnel reflections from the distal fiber ends undergo a double pass in the fibers and interference at the fourth port of the coupler which formed a Michelson interferometer. We suggested two means of ac phase tracking (PTAC) and dc phase tracking (PTDC) to maintain the interference intensity at quadrature by feedback control. Stepping between quadrature positions forces a π/2 -rad phase step. A method based on the ratio of harmonic of the interference signal was proposed to estimate phase step accuracy. A root-mean-square phase stability of 1.5 mrad and phase step accuracy of 2.6 mrad were measured with PTAC and a root-mean-square phase stability of 2 mrad and phase step accuracy of 13.8 mrad were measured with PTDC for the fiber-optic projected-fringe digital interferometry following the same condition. It worked well in two hours without resetting the integrator.

  4. Transforming Writing: Interim Evaluation Report

    ERIC Educational Resources Information Center

    Rooke, Jonathan

    2012-01-01

    Transforming Writing is a two-year action research project which aims to develop a model for the teaching and learning of writing that more fully incorporates a focus on embedded formative assessment. In the first year of the project, the 12 participating schools developed a model of writing underpinned by Talk for Writing, an approach developed…

  5. Quantum projection noise limited stability of a 88Sr+ atomic clock

    NASA Astrophysics Data System (ADS)

    Jian, B.; Dubé, P.; Madej, A. A.

    2016-06-01

    The evaluated accuracy of a single trapped 88Sr+ ion clock referenced to the 5s2 S 1/2 - 4d 2 D 5/2 transition at 445 THz at the National Research Council of Canada has reached 1.2 x 10-17 over recent years. On the other hand, the stability of an atomic clock determines how long the signals from two similar clocks have to be compared to reach a given level of uncertainty. Here, we report on the improvement of the stability of NRC's 88Sr+ single ion clock by reducing the Allan deviation from 1 x 10-14 to 3 x 10-15 at 1 second averaging time. This is done by the implementation of a clear out laser that transfers the ion from the metastable state to the ground state at each cycle, followed by a state-preparation step that transfers the ion to the desired ground state magnetic sublevel of the probed transition.

  6. LANDFILL BIOREACTOR PERFORMANCE, SECOND INTERIM REPORT

    EPA Science Inventory

    A bioreactor landfill is a landfill that is operated in a manner that is expected to increase the rate and extent of waste decomposition, gas generation, and settlement compared to a traditional landfill. This Second Interim Report was prepared to provide an interpretation of fie...

  7. The Interim Superintendent: A Case Study

    ERIC Educational Resources Information Center

    Bigham, Gary; Nix, Susan J.

    2011-01-01

    Considering the vitally important role that the superintendent plays in the overall functioning and wellbeing of any school district, the filling of that position should never be done in haste. Due to the importance of this process and the time it requires, school districts often employ an interim superintendent. In this single case study, one…

  8. 45 CFR 83.20 - Interim procedures.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 45 Public Welfare 1 2010-10-01 2010-10-01 false Interim procedures. 83.20 Section 83.20 Public Welfare DEPARTMENT OF HEALTH AND HUMAN SERVICES GENERAL ADMINISTRATION REGULATION FOR THE ADMINISTRATION AND ENFORCEMENT OF SECTIONS 799A AND 845 OF THE PUBLIC HEALTH SERVICE ACT Procedures § 83.20...

  9. 19 CFR 356.18 - Interim sanctions.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 19 Customs Duties 3 2013-04-01 2013-04-01 false Interim sanctions. 356.18 Section 356.18 Customs Duties INTERNATIONAL TRADE ADMINISTRATION, DEPARTMENT OF COMMERCE PROCEDURES AND RULES FOR IMPLEMENTING ARTICLE 1904 OF THE NORTH AMERICAN FREE TRADE AGREEMENT Violation of a Protective Order or a...

  10. 19 CFR 356.18 - Interim sanctions.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 19 Customs Duties 3 2011-04-01 2011-04-01 false Interim sanctions. 356.18 Section 356.18 Customs Duties INTERNATIONAL TRADE ADMINISTRATION, DEPARTMENT OF COMMERCE PROCEDURES AND RULES FOR IMPLEMENTING ARTICLE 1904 OF THE NORTH AMERICAN FREE TRADE AGREEMENT Violation of a Protective Order or a...

  11. Disposal facility data for the interim performance

    SciTech Connect

    Eiholzer, C.R.

    1995-05-15

    The purpose of this report is to identify and provide information on the waste package and disposal facility concepts to be used for the low-level waste tank interim performance assessment. Current concepts for the low-level waste form, canister, and the disposal facility will be used for the interim performance assessment. The concept for the waste form consists of vitrified glass cullet in a sulfur polymer cement matrix material. The waste form will be contained in a 2 {times} 2 {times} 8 meter carbon steel container. Two disposal facility concepts will be used for the interim performance assessment. These facility concepts are based on a preliminary disposal facility concept developed for estimating costs for a disposal options configuration study. These disposal concepts are based on vault type structures. None of the concepts given in this report have been approved by a Tank Waste Remediation Systems (TWRS) decision board. These concepts will only be used in th interim performance assessment. Future performance assessments will be based on approved designs.

  12. 19 CFR 207.106 - Interim measures.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 19 Customs Duties 3 2013-04-01 2013-04-01 false Interim measures. 207.106 Section 207.106 Customs Duties UNITED STATES INTERNATIONAL TRADE COMMISSION NONADJUDICATIVE INVESTIGATIONS INVESTIGATIONS OF WHETHER INJURY TO DOMESTIC INDUSTRIES RESULTS FROM IMPORTS SOLD AT LESS THAN FAIR VALUE OR FROM...

  13. 19 CFR 207.106 - Interim measures.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... 19 Customs Duties 3 2012-04-01 2012-04-01 false Interim measures. 207.106 Section 207.106 Customs Duties UNITED STATES INTERNATIONAL TRADE COMMISSION NONADJUDICATIVE INVESTIGATIONS INVESTIGATIONS OF WHETHER INJURY TO DOMESTIC INDUSTRIES RESULTS FROM IMPORTS SOLD AT LESS THAN FAIR VALUE OR FROM...

  14. 19 CFR 207.106 - Interim measures.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 19 Customs Duties 3 2011-04-01 2011-04-01 false Interim measures. 207.106 Section 207.106 Customs Duties UNITED STATES INTERNATIONAL TRADE COMMISSION NONADJUDICATIVE INVESTIGATIONS INVESTIGATIONS OF WHETHER INJURY TO DOMESTIC INDUSTRIES RESULTS FROM IMPORTS SOLD AT LESS THAN FAIR VALUE OR FROM...

  15. 19 CFR 207.106 - Interim measures.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 19 Customs Duties 3 2014-04-01 2014-04-01 false Interim measures. 207.106 Section 207.106 Customs Duties UNITED STATES INTERNATIONAL TRADE COMMISSION NONADJUDICATIVE INVESTIGATIONS INVESTIGATIONS OF WHETHER INJURY TO DOMESTIC INDUSTRIES RESULTS FROM IMPORTS SOLD AT LESS THAN FAIR VALUE OR FROM...

  16. Diversified Satellite Occupations Program. Interim Report.

    ERIC Educational Resources Information Center

    Call, John Reed

    This interim report, covering the period of September 1970 to June 1971, describes a program conducted for elementary, junior high, and senior high grades. The elementary program was designed to help students develop an understanding of occupational competence. The prevention of dropouts and individualizing instruction were concerns of the junior…

  17. Interim Report - Grant AFOSR-85-0065.

    DTIC Science & Technology

    1985-06-30

    Option 065 Drafting Plotter 1 7475A 6 Pen Graphics Plotter Vendor: Imagen Corporation $ 11,266 1 Model 8/300 Laser Printer System, 512Kbytes memory 1... Imagen 8/300 Laser Printer 3 Interim Report Grant No. AFOSR-85-0065 was equivalent to the Versatec plotter for small plots and better for text output

  18. 340 waste handling facility interim safety basis

    SciTech Connect

    VAIL, T.S.

    1999-04-01

    This document presents an interim safety basis for the 340 Waste Handling Facility classifying the 340 Facility as a Hazard Category 3 facility. The hazard analysis quantifies the operating safety envelop for this facility and demonstrates that the facility can be operated without a significant threat to onsite or offsite people.

  19. T-TY Tank Farm Interim Surface Barrier Demonstration - Vadose Zone Monitoring FY10 Report

    SciTech Connect

    Zhang, Z. F.; Strickland, Christopher E.; Field, Jim G.; Parker, Danny L.

    2011-01-01

    The U.S. Department of Energy’s Office of River Protection has constructed interim surface barriers over a portion of the T and TY tank farms as part of the Interim Surface Barrier Demonstration Project. The interim surface barriers (hereafter referred to as the surface barriers or barriers) are designed to minimize the infiltration of precipitation into the soil zones containing radioactive contaminants and minimize the movement of the contaminants. As part of the demonstration effort, vadose zone moisture is being monitored to assess the effectiveness of the barriers at reducing soil moisture. Solar-powered systems were installed to continuously monitor soil water conditions at four locations in the T (i.e., instrument Nests TA, TB, TC, and TD) and the TY (i.e., instrument Nests TYA and TYB) Farms beneath the barriers and outside the barrier footprint as well as site meteorological conditions. Nests TA and TYA are placed in the area outside the barrier footprint and serve as controls, providing subsurface conditions outside the influence of the surface barriers. Nest TB provides subsurface measurements to assess surface-barrier edge effects. Nests TC, TD, and TYB are used to assess changes in soil-moisture conditions beneath the interim surface barriers.

  20. Multi-phase Temporal Seismic Imaging of a Slope Stability Mitigation Project at Newby Island Sanitary Landfill, San Jose, California

    NASA Astrophysics Data System (ADS)

    Treece, B. J.; Catchings, R.; Reed, D.; Goldman, M.

    2014-12-01

    Without slope stability mitigation, liquefaction-induced settlement in bay mud and Pleistocene alluvial deposits may lead to the collapse of levee walls surrounding sanitary landfills that are located adjacent to the San Francisco Bay. To analyze the effectiveness of a slope stability mitigation project involving deep soil mixing at Newby Island Sanitary Landfill in San Jose, California, we acquired P- and S-wave seismic surveys along a transect through the mitigated region during, and two years after, completion of the mitigation project. Deep soil mixing involves the injection of a cement slurry in augered holes, resulting in groups of soil-cement columns (elements) that are intended to increase the strength and rigidity of the subsurface materials. For our seismic investigations, we used accelerated-weight-drop (AWD) and hammer impacts to generate P- and S-wave seismic sources, respectively, at 57 geophone locations, spaced 5 m apart. The resulting seismic data were recorded using 40-Hz, vertical-component (P-wave) and 4.5-Hz, horizontal-component (S-wave) sensors. Initially, we developed tomographic refraction (velocity) images along a progressive transition from a yet-to-be-mitigated area into a more recently mitigated area, located along the base of a steep slope composed of compacted landfill. The initial survey revealed an increase in seismic velocity in the treated area, seismic velocity increases with curing time for soil-cement elements, and a high-velocity zone beneath the active injection zone. The influence of the mitigation was most apparent from increases in Vp/Vs and Poisson's ratios. To assess the long-term effects of the mitigation project, an identical, follow-up survey was acquired in July 2014, 23 months after the initial survey. We present a comparative analysis of the tomographic images from the two surveys, variations in Vp/Vs and Poisson's ratios over time, and a comparison of in situ, time-varying seismic parameters with laboratory

  1. Projecting climate change impacts on the stability of productivities of maize and soybean in terms of probability of concurrent failure

    NASA Astrophysics Data System (ADS)

    Yokozawa, M.; Sakurai, G.; Iizumi, T.

    2012-12-01

    The globalization of the trade of food commodities has arranged agricultural production areas in the world. Current main production areas of maize and soybean, which are major cereal crops for human food and animal diet, are localized in the United States, China and Brazil. The amounts of production of maize and soybean from these three countries reached 70% and 74% of total production in the world in 2009, respectively. These three countries are hubs for the world food supply network. Simultaneous external disturbances to the localized hubs can make the network system unstable. Here, we projected the changes in stability of the productivities of maize and soybean under climate change. We used a process-based model for evaluating crop yield at a large scale for maize and soybean. The parameters are determined based on the historical agricultural statistics issued by administrative agencies during a period of 1981 to 2006 and a reanalysis data JRA25 provided by Japan Meteorological Agency. We used the climate change scenarios from outputs of MIROC5.0 simulations. We projected the time changes in maize and soybean yields of three countries under four climate change scenarios: RCP 2.6, 4.5, 6.0 and 8.5 for a period of 2010 to 2070. The significant declining trend of maize yield with time was projected in RCP 8.5 for all countries, while the yield appeared to decrease after 2050 in other RCP scenarios. The extents to which maize yield decrease in 2060s compared to the average over 1980 to 2006 were projected to be about 20% for the United States, 10% for Brazil and China in RCP 2.6, 4.5 and 6.0; 30% for the United States and Brazil, 40% for China in RCP 8.5. On the other hand, the projected changes in soybean yield were complicated. The projected extent to which soybean yield decrease in 2060s compared to the average over 1980 to 2006 was about 30% for the United States and Brazil and 20% for China in RCP 2.6. In RCP 4.5 and 6.0, the yield was projected to be constant

  2. Reflections on Post-16 Strategies in European Countries. Interim Report of the Leonardo da Vinci/Multiplier Effect Project III.3.a. Priority 2: Forging Links between Educational Establishments and Enterprises (1997-2000) ID 27009. Working Papers, No. 9.

    ERIC Educational Resources Information Center

    Stenstrom, Marja-Leena, Ed.

    This four-part publication contains 19 papers on educational practices and promises for post-16 education in European countries. Part I, the introduction, contains these three papers: "Sharpening Post-16 Education Strategies: Building on the Results of the Previous Projects" (Johanna Lasonen); "'Parity of Esteem' and 'Integrated…

  3. GULF OF MEXICO SEAFLOOR STABILITY AND GAS HYDRATE MONITORING STATION PROJECT

    SciTech Connect

    J. Robert Woolsey; Thomas M. McGee; Robin C. Buchannon

    2004-11-01

    The gas hydrates research Consortium (HRC), established and administered at the University if Mississippi's Center for Marine Research and Environmental Technology (CMRET) has been active on many fronts in FY 03. Extension of the original contract through March 2004, has allowed completion of many projects that were incomplete at the end of the original project period due, primarily, to severe weather and difficulties in rescheduling test cruises. The primary objective of the Consortium, to design and emplace a remote sea floor station for the monitoring of gas hydrates in the Gulf of Mexico by the year 2005 remains intact. However, the possibility of levering HRC research off of the Joint Industries Program (JIP) became a possibility that has demanded reevaluation of some of the fundamental assumptions of the station format. These provisions are discussed in Appendix A. Landmark achievements of FY03 include: (1) Continuation of Consortium development with new researchers and additional areas of research contribution being incorporated into the project. During this period, NOAA's National Undersea Research Program's (NURP) National Institute for Undersea Science and Technology (NIUST) became a Consortium funding partner, joining DOE and Minerals Management Service (MMS); (2) Very successful annual and semiannual meetings in Oxford Mississippi in February and September, 2003; (3) Collection of piston cores from MC798 in support of the effort to evaluate the site for possible monitoring station installation; (4) Completion of the site evaluation effort including reports of all localities in the northern Gulf of Mexico where hydrates have been documented or are strongly suspected to exist on the sea floor or in the shallow subsurface; (5) Collection and preliminary evaluation of vent gases and core samples of hydrate from sites in Green Canyon and Mississippi Canyon, northern Gulf of Mexico; (6) Monitoring of gas activity on the sea floor, acoustically and thermally

  4. Operations and Maintenance Concept Plan for the Immobilized High Level Waste (IHLW) Interim Storage Facility

    SciTech Connect

    JANIN, L.F.

    2000-08-30

    This O&M Concept looks at the future operations and maintenance of the IHLW/CSB interim storage facility. It defines the overall strategy, objectives, and functional requirements for the portion of the building to be utilized by Project W-464. The concept supports the tasks of safety basis planning, risk mitigation, alternative analysis, decision making, etc. and will be updated as required to support the evolving design.

  5. Nutrition and Child Growth and Development in Tunisia. Interim Progress Report, (September 1, 1972--February 28, 1973).

    ERIC Educational Resources Information Center

    Young, Harben Boutourline

    This interim report of the Yale Project describes the progress made on the nutrition and growth study of Tunisian children from September 1, 1972 through February 28, 1973. A major part of the report is devoted to the organizational and data collection problems of the longitudinal study, discussed under the following categories: biomedics,…

  6. Stabilizers for GAP and GAP-based Propellants Interim Report

    DTIC Science & Technology

    2008-10-09

    the m j o r deconposit inn pathways of GAP and U P prope l lan ts i n o r d e r to i n p r o w long term storage stabi l i ty. Model c- s inw...la t i ng t h e ut ido-bear ing frmctional units of GAP ( a z i d e adjacent t o po lye ther k k b o n e , az ide sd jacent t o terminal...binder i n prope l lan t -ag ing studies has varied accord2~g t o the to t of GAP used. This v a r i a b i l i t y my k linked to residual i n p

  7. Dental Auxiliary Occupations. Interim Report.

    ERIC Educational Resources Information Center

    Kingston, Richard D.

    As part of a dental auxiliaries project, a Dental Auxiliary National Technical Advisory Committee was established, and its major undertaking was to assist in the development of a functional inventory for each of the three dental auxiliary occupations (dental assisting, dental hygiene, and dental laboratory technology). The analysis consisted of…

  8. Kennedy Space Center Press Site (SWMU 074) Interim Measure Report

    NASA Technical Reports Server (NTRS)

    Applegate, Joseph L.

    2015-01-01

    This report summarizes the Interim Measure (IM) activities conducted at the Kennedy Space Center (KSC) Press Site ("the Press Site"). This facility has been designated as Solid Waste Management Unit 074 under KSC's Resource Conservation and Recovery Act Corrective Action program. The activities were completed as part of the Vehicle Assembly Building (VAB) Area Land Use Controls Implementation Plan (LUCIP) Elimination Project. The purpose of the VAB Area LUCIP Elimination Project was to delineate and remove soil affected with constituents of concern (COCs) that historically resulted in Land Use Controls (LUCs). The goal of the project was to eliminate the LUCs on soil. LUCs for groundwater were not addressed as part of the project and are not discussed in this report. This report is intended to meet the Florida Department of Environmental Protection (FDEP) Corrective Action Management Plan requirement as part of the KSC Hazardous and Solid Waste Amendments permit and the U.S. Environmental Protection Agency's (USEPA's) Toxic Substance Control Act (TSCA) self-implementing polychlorinated biphenyl (PCB) cleanup requirements of 40 Code of Federal Regulations (CFR) 761.61(a).

  9. Collaborative Research: Robust Climate Projections and Stochastic Stability of Dynamical Systems

    SciTech Connect

    Ghil, Michael; McWilliams, James; Neelin, J. David; Zaliapin, Ilya; Chekroun, Mickael; Kondrashov, Dmitri; Simonnet, Eric

    2011-10-13

    The project was completed along the lines of the original proposal, with additional elements arising as new results were obtained. The originally proposed three thrusts were expanded to include an additional, fourth one. (i) The e ffects of stochastic perturbations on climate models have been examined at the fundamental level by using the theory of deterministic and random dynamical systems, in both nite and in nite dimensions. (ii) The theoretical results have been implemented first on a delay-diff erential equation (DDE) model of the El-Nino/Southern-Oscillation (ENSO) phenomenon. (iii) More detailed, physical aspects of model robustness have been considered, as proposed, within the stripped-down ICTP-AGCM (formerly SPEEDY) climate model. This aspect of the research has been complemented by both observational and intermediate-model aspects of mid-latitude and tropical climate. (iv) An additional thrust of the research relied on new and unexpected results of (i) and involved reduced-modeling strategies and associated prediction aspects have been tested within the team's empirical model reduction (EMR) framework. Finally, more detailed, physical aspects have been considered within the stripped-down SPEEDY climate model. The results of each of these four complementary e fforts are presented in the next four sections, organized by topic and by the team members concentrating on the topic under discussion.

  10. Space potential particles to enhance the stability of projection-based particle methods

    NASA Astrophysics Data System (ADS)

    Tsuruta, Naoki; Khayyer, Abbas; Gotoh, Hitoshi

    2015-01-01

    Particle methods have been seldom verified by a Karman vortex simulation, which is commonly performed as a typical benchmark in computational fluid dynamics. This is mainly due to a difficulty in suppression of occurrence of unphysical voids manifested usually in a strong vortex on account of definition of free surface by the Lagrangian tracking framework with inconsistency in volume conservation. This paper presents a simple and effective scheme as a free-surface boundary condition of projection-based particle methods, namely the MPS (moving particle semi-implicit) and Incompressible SPH (ISPH) methods to handle the free surface with consistency in volume conservation. The new scheme is introduced into the Poisson pressure equation (PPE) with consideration of a potential in void space as space potential particle (SPP), to reproduce physical motions of particles around free surface through a particle-void interaction. The enhancing effect of the newly proposed SPP scheme is shown by simulating a few numerical tests, including a whirling water flow, a two-phase surfacing flow, and a set of Karman vortex simulations.

  11. 78 FR 67442 - Congestion Mitigation and Air Quality Improvement Program Interim Guidance

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-11-12

    ... Federal Highway Administration Congestion Mitigation and Air Quality Improvement Program Interim Guidance... Mitigation and Air Quality Improvement (CMAQ) Program (Interim Guidance). The Interim Guidance revises CMAQ....gov/environment/air_quality/cmaq/policy_and_guidance/2008_guidance/ guidance/. DATES: This...

  12. 76 FR 15028 - Airport Improvement Program (AIP): Interim Policy Regarding Access to Airports From Residential...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-03-18

    ... Federal Aviation Administration Airport Improvement Program (AIP): Interim Policy Regarding Access to Airports From Residential Property AGENCY: Federal Aviation Administration (FAA). ACTION: Interim policy; amendment to sponsor grant assurance 5. SUMMARY: This action adopts an interim policy amending...

  13. Biocides for the Battlefield - Interim Report

    DTIC Science & Technology

    2010-09-24

    for public release; distribution is unlimited. James H . Wynne Materials Chemistry Branch Chemistry Division Preston a. Fulmer Chemical Dynamics and...b. ABSTRACT c. THIS PAGE 18. NUMBER OF PAGES 17. LIMITATION OF ABSTRACT Biocides for the Battlefield—Interim Report James H . Wynne and Preston A...distribution is unlimited. Unclassified Unclassified Unclassified SAR 25 James H . Wynne (202) 404-4010 The ability to disinfect surfaces and manufacture self

  14. Progress on plutonium stabilization

    SciTech Connect

    Hurt, D.

    1996-05-01

    The Defense Nuclear Facilities Safety Board has safety oversight responsibility for most of the facilities where unstable forms of plutonium are being processed and packaged for interim storage. The Board has issued recommendations on plutonium stabilization and has has a considerable influence on DOE`s stabilization schedules and priorities. The Board has not made any recommendations on long-term plutonium disposition, although it may get more involved in the future if DOE develops plans to use defense nuclear facilities for disposition activities.

  15. Compilation of interim technical research memoranda. Volume I

    SciTech Connect

    Shanahan, W.R.

    1984-04-01

    Four interim technical research memoranda are presented that describe the results of numerical simulations designed to investigate the dynamics of energetic plasma beams propagating across magnetic fields.

  16. Functions and requirements document for interim store solidified high-level and transuranic waste

    SciTech Connect

    Smith-Fewell, M.A., Westinghouse Hanford

    1996-05-17

    The functions, requirements, interfaces, and architectures contained within the Functions and Requirements (F{ampersand}R) Document are based on the information currently contained within the TWRS Functions and Requirements database. The database also documents the set of technically defensible functions and requirements associated with the solidified waste interim storage mission.The F{ampersand}R Document provides a snapshot in time of the technical baseline for the project. The F{ampersand}R document is the product of functional analysis, requirements allocation and architectural structure definition. The technical baseline described in this document is traceable to the TWRS function 4.2.4.1, Interim Store Solidified Waste, and its related requirements, architecture, and interfaces.

  17. Development of gridded mobile source emission estimates for Victoria county FY93, FY96, FY99, and FY07 in support of the Coast project. Interim research report, April 1992-August 1996

    SciTech Connect

    Knowles, W.E.; Dresser, G.B.

    1995-07-01

    This report documents the methodology used to develop the Victoria County gridded mobile source emissions inventories. Included in the report are an overview of the emission estimation methodology and the 24-hour traffic assignments used in the analyses; the methods used to estimate the seasonally adjusted time-of-day vehicle miles of travel and associated operating speeds; the estimation of the emission rates using the EPA`s MOBILE5a program; and an outline of the method used to develop the emission estimates using the MOBILE5a emission rates. The appendices present the MOBILE5a set-ups; the emission rates developed for the emissions inventory; and the SUMALL output tables showing VMT, VHT, and average operational speeds cross-classified by vehicle and roadway type, and pounds of VOC, CO, and NOx cross-classified by vehicle and roadway type. These emission inventories were developed in support of the Coastal Oxidant Assessment of Southeast Texas Project (COAST); a large-scale study of ozone formation being conducted by the Texas Natural Resource Conservation Commision (TNRCC).

  18. Supplement Analysis for the Watershed Management Program EIS (DOE/EIS-0265/SA-161) - Grave Creek Channel Stabilization Project – Phase II

    SciTech Connect

    Keller, Carl J.

    2004-07-22

    BPA proposes to fund MFWP to accomplish Phase II of channel stabilization along Graves Creek. The current proposal is very much the same as for Phase I (as per our Oct. 15, 2002 Memo.): stabilize about 4,800 feet of the creek by realigning and shaping the channel; install log and rock vanes, and root wads; install debris jams and cobble patches, and planting native vegetation along the riparian corridor to stabilize the banks. The Phase II work is immediately adjacent and downstream from that the Phase I work that was accomplished in 2002. The purpose of the project is to stabilize that channel, provide for floodplain function, improve rearing and adult holding habitat for westslope cutthroat trout and bull trout.

  19. Science Opportunities Enabled by NASA's Constellation System: Interim Report

    NASA Technical Reports Server (NTRS)

    2008-01-01

    on two criteria: whether the concepts offered the potential for a significant scientific advance, and whether or not the concepts would benefit from the Constellation System. The committee determined that all of the concepts offered the possibility of a significant scientific advance, but it cautions that such an evaluation ultimately must be made by the decadal survey process, and it emphasizes that this interim report s evaluation should not be considered to be an endorsement of the scientific merit of these proposals, which must of course be evaluated relative to other proposals. The committee determined that seven of these concepts would benefit from the Constellation System, whereas four would not, but it stresses that this conclusion does not reflect an evaluation of the scientific merit of the projects, but rather an assessment of whether or not new capabilities provided by the Constellation System could significantly affect them. Some of the mission concepts, such as the Advanced Compton Telescope, already offer a significant scientific advance and fit easily within the mass and volume constraints of existing launch vehicles. Other mission concepts, such as the Palmer Quest proposal to drill through the Mars polar cap, are not constrained by the launch vehicle, but rather by other technology limitations. The committee evaluated the mission concepts as presented to it, aware nevertheless that proposing a far larger and more ambitious mission with the same science goals might be possible given the capabilities of the Ares V launch vehicle. (Such proposals can be submitted in response to the committee s request for information to be evaluated in its final report.) See Table S.1 for a summary of the Vision Missions, including their cost estimates, technical maturity, and reasons that they might benefit from the Constellation System. The committee developed several findings and recommendations.

  20. Predictors of Venous Thromboembolism Recurrence, Adjusted for Treatments and Interim Exposures: A Population-based Case-cohort Study

    PubMed Central

    Heit, John A.; Lahr, Brian D.; Ashrani, Aneel A.; Petterson, Tanya M.; Bailey, Kent R.

    2015-01-01

    Background Predictors of venous thromboembolism (VTE) recurrence are uncertain. Objective To identify predictors of VTE recurrence, adjusted for treatments and interim exposures. Materials and Methods Using Rochester Epidemiology Project resources, all Olmsted County, MN residents with objectively-diagnosed incident VTE over the 13-year period, 1988–2000, who survived ≥1 day were followed for first objectively-diagnosed VTE recurrence. For all patients with recurrence, and a random sample of all surviving incident VTE patients (n=415), we collected demographic and baseline characteristics, treatments and interim exposures. In a case-cohort study design, demographic, baseline, treatment and interim exposure characteristics were tested as potential predictors of VTE recurrence using time-dependent Cox proportional hazards modeling. Results Among 1262 incident VTE patients, 306 developed recurrence over 6,440 person-years. Five-year recurrence rates, overall and for cancer-associated, idiopathic and non-cancer secondary VTE, were 24.5%, 43.4%, 27.3% and 18.1%, respectively. In multivariable analysis, interim hospitalization, active cancer, pregnancy, central venous catheter and respiratory infection were associated with increased hazards of recurrence, and warfarin and aspirin were associated with reduced hazards. Adjusting for treatments and these interim risk factors, male sex, baseline active cancer and failure to achieve a therapeutic aPTT in the first 24 hours were independently associated with increased hazards of VTE recurrence over the entire follow-up period, while the hazards of recurrence for patient age, chronic lung disease, leg paresis, prior superficial vein thrombosis and idiopathic VTE varied over the follow-up period. Conclusions Baseline and interim exposures can stratify VTE recurrence risk and may be useful for directing secondary prophylaxis. PMID:26143712

  1. 47 CFR 73.404 - Interim hybrid IBOC DAB operation.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... RADIO BROADCAST SERVICES Digital Audio Broadcasting § 73.404 Interim hybrid IBOC DAB operation. (a) The... test operation pursuant to § 73.1620, may commence interim hybrid IBOC DAB operation with digital... Report and Order in MM Docket No. 99-325, as revised in the Media Bureau's subsequent Order in MM...

  2. 50 CFR 660.720 - Interim protection for sea turtles.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 50 Wildlife and Fisheries 11 2011-10-01 2011-10-01 false Interim protection for sea turtles. 660.720 Section 660.720 Wildlife and Fisheries FISHERY CONSERVATION AND MANAGEMENT, NATIONAL OCEANIC AND... Migratory Fisheries § 660.720 Interim protection for sea turtles. (a) Until the effective date of §§...

  3. 50 CFR 660.720 - Interim protection for sea turtles.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... 50 Wildlife and Fisheries 13 2013-10-01 2013-10-01 false Interim protection for sea turtles. 660.720 Section 660.720 Wildlife and Fisheries FISHERY CONSERVATION AND MANAGEMENT, NATIONAL OCEANIC AND... Migratory Fisheries § 660.720 Interim protection for sea turtles. (a) Until the effective date of §§...

  4. 50 CFR 660.720 - Interim protection for sea turtles.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 50 Wildlife and Fisheries 9 2010-10-01 2010-10-01 false Interim protection for sea turtles. 660.720 Section 660.720 Wildlife and Fisheries FISHERY CONSERVATION AND MANAGEMENT, NATIONAL OCEANIC AND... Migratory Fisheries § 660.720 Interim protection for sea turtles. (a) Until the effective date of §§...

  5. 50 CFR 660.720 - Interim protection for sea turtles.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 50 Wildlife and Fisheries 13 2014-10-01 2014-10-01 false Interim protection for sea turtles. 660.720 Section 660.720 Wildlife and Fisheries FISHERY CONSERVATION AND MANAGEMENT, NATIONAL OCEANIC AND... Migratory Fisheries § 660.720 Interim protection for sea turtles. (a) Until the effective date of §§...

  6. 50 CFR 660.720 - Interim protection for sea turtles.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... 50 Wildlife and Fisheries 13 2012-10-01 2012-10-01 false Interim protection for sea turtles. 660.720 Section 660.720 Wildlife and Fisheries FISHERY CONSERVATION AND MANAGEMENT, NATIONAL OCEANIC AND... Migratory Fisheries § 660.720 Interim protection for sea turtles. (a) Until the effective date of §§...

  7. 46 CFR 308.203 - Amount insured under interim binder.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 46 Shipping 8 2010-10-01 2010-10-01 false Amount insured under interim binder. 308.203 Section 308.203 Shipping MARITIME ADMINISTRATION, DEPARTMENT OF TRANSPORTATION EMERGENCY OPERATIONS WAR RISK INSURANCE War Risk Protection and Indemnity Insurance § 308.203 Amount insured under interim binder....

  8. 45 CFR 1606.13 - Interim and termination funding; reprogramming.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 45 Public Welfare 4 2010-10-01 2010-10-01 false Interim and termination funding; reprogramming. 1606.13 Section 1606.13 Public Welfare Regulations Relating to Public Welfare (Continued) LEGAL SERVICES CORPORATION TERMINATION AND DEBARMENT PROCEDURES; RECOMPETITION § 1606.13 Interim and...

  9. Presidential Transition: The Experience of Two Community College Interim Presidents

    ERIC Educational Resources Information Center

    Thompson, Matthew D.

    2010-01-01

    The purpose of this qualitative case study was to understand the experiences of two community college interim presidents, their characteristics, and how they led institutions following an abrupt presidential departure. There were two fundamental questions framing this research study, 1. How do two interim community college presidents lead…

  10. 16 CFR 1203.53 - Interim safety standards.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 16 Commercial Practices 2 2010-01-01 2010-01-01 false Interim safety standards. 1203.53 Section 1203.53 Commercial Practices CONSUMER PRODUCT SAFETY COMMISSION CONSUMER PRODUCT SAFETY ACT REGULATIONS..., Through March 10, 1999 § 1203.53 Interim safety standards. (a) Bicycle helmets must comply with one...

  11. 46 CFR 308.303 - Amounts insured under interim binder.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 46 Shipping 8 2010-10-01 2010-10-01 false Amounts insured under interim binder. 308.303 Section 308.303 Shipping MARITIME ADMINISTRATION, DEPARTMENT OF TRANSPORTATION EMERGENCY OPERATIONS WAR RISK INSURANCE Second Seamen's War Risk Insurance § 308.303 Amounts insured under interim binder. The...

  12. Optimal timing for interim analyses in clinical trials.

    PubMed

    Togo, Kanae; Iwasaki, Manabu

    2013-01-01

    In clinical trials, interim analyses are often performed before the completion of the trial. The intention is to possibly terminate the trial early or adjust the sample size. The time of conducting an interim analysis affects the probability of the early termination and the number of subjects enrolled until the interim analysis. This influences the expected total number of subjects. In this study, we examine the optimal time for conducting interim analyses with a view to minimizing the expected total sample size. It is found that regardless of the effect size, the optimal time of one interim analysis for the early termination is approximately two-thirds of the planned observations for the O'Brien-Fleming type of spending function and approximately half of the planned observations for the Pocock type when the subject enrollment is halted for the interim analysis. When the subject enrollment is continuous throughout the trial, the optimal time for the interim analysis varies according to the follow-up duration. We also consider the time for one interim analysis including the sample size adjustment in terms of minimizing the expected total sample size.

  13. Staff Reactions to Interim Leadership in a Student Affairs Organization

    ERIC Educational Resources Information Center

    Jones, Robin D.

    2011-01-01

    Interim leadership appointments in higher education are a common strategy used to fill leadership gaps in executive positions. Because student affairs executives are particularly vulnerable to high turnover rates, interim appointments are becoming more widespread. Even with the prevalence of this trend, little attention has been given to the…

  14. 7 CFR 280.1 - Interim disaster procedures.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 7 Agriculture 4 2010-01-01 2010-01-01 false Interim disaster procedures. 280.1 Section 280.1 Agriculture Regulations of the Department of Agriculture (Continued) FOOD AND NUTRITION SERVICE, DEPARTMENT OF....1 Interim disaster procedures. The Secretary shall, after consultation with the official...

  15. 40 CFR 281.23 - Schedule for interim approval.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 26 2010-07-01 2010-07-01 false Schedule for interim approval. 281.23 Section 281.23 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) SOLID WASTES... Schedule for interim approval. For a state program that must modify its statutory or...

  16. 47 CFR 51.715 - Interim transport and termination pricing.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 47 Telecommunication 3 2010-10-01 2010-10-01 false Interim transport and termination pricing. 51... Telecommunications Traffic § 51.715 Interim transport and termination pricing. (a) Upon request from a... shall provide transport and termination of telecommunications traffic immediately under an...

  17. Presidential Transition: The Experience of Two Community College Interim Presidents

    ERIC Educational Resources Information Center

    Thompson, Matthew; Cooper, Robyn; Ebbers, Larry

    2012-01-01

    The purpose of this case study was to understand the experiences of two community college interim presidents, their characteristics, and how they led institutions following an abrupt presidential departure. There were two fundamental questions framing this study: 1. How do two interim community college presidents lead community colleges during a…

  18. The Predictive and Instructional Value of Interim Assessments

    ERIC Educational Resources Information Center

    Pon, Kathleen

    2013-01-01

    This mixed design study investigated the predictive and instructional uses of two different types of interim mathematics assessments given in two different districts. One district administered the same summative type of assessment three times a year, while the other district administered a different interim assessment after six-week intervals of…

  19. 40 CFR 270.64 - Interim permits for UIC wells.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 26 2010-07-01 2010-07-01 false Interim permits for UIC wells. 270.64 Section 270.64 Protection of Environment ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) SOLID WASTES... § 270.64 Interim permits for UIC wells. The Director may issue a permit under this part to any Class...

  20. 46 CFR 308.103 - Insured amounts under interim binder.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 46 Shipping 8 2010-10-01 2010-10-01 false Insured amounts under interim binder. 308.103 Section 308.103 Shipping MARITIME ADMINISTRATION, DEPARTMENT OF TRANSPORTATION EMERGENCY OPERATIONS WAR RISK INSURANCE War Risk Hull and Disbursements Insurance § 308.103 Insured amounts under interim binder....

  1. 42 CFR 418.307 - Periodic interim payments.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 42 Public Health 3 2010-10-01 2010-10-01 false Periodic interim payments. 418.307 Section 418.307... (CONTINUED) MEDICARE PROGRAM HOSPICE CARE Payment for Hospice Care § 418.307 Periodic interim payments. Subject to the provisions of § 413.64(h) of this chapter, a hospice may elect to receive periodic...

  2. 40 CFR 155.56 - Interim registration review decision.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 23 2010-07-01 2010-07-01 false Interim registration review decision... PROGRAMS REGISTRATION STANDARDS AND REGISTRATION REVIEW Registration Review Procedures § 155.56 Interim registration review decision. The Agency may issue, when it determines it to be appropriate, an...

  3. 39 CFR 211.4 - Interim personnel regulations.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 39 Postal Service 1 2010-07-01 2010-07-01 false Interim personnel regulations. 211.4 Section 211.4 Postal Service UNITED STATES POSTAL SERVICE ORGANIZATION AND ADMINISTRATION APPLICATION OF REGULATIONS § 211.4 Interim personnel regulations. (a) Continuation of Personnel Regulations of the Post...

  4. Transuranic waste storage and assay facility (TRUSAF) interim safety basis

    SciTech Connect

    Gibson, K.D.

    1995-09-01

    The TRUSAF ISB is based upon current facility configuration and procedures. The purpose of the document is to provide the basis for interim operation or restrictions on interim operations and the authorization basis for the TRUSAF at the Hanford Site. The previous safety analysis document TRUSAF hazards Identification and Evaluation (WHC 1977) is superseded by this document.

  5. Statistical Profile of Children and Mothers in Afghanistan. Interim Edition.

    ERIC Educational Resources Information Center

    United Nations Children's Fund, Kabul (Afghanistan).

    This interim report is an updating of the 1977 Statistical Profile of Children and Mothers in Afghanistan. The interim report reflects the significant changes in policies brought about by the Saur Revolution establishing the Democratic Republic of Afghanistan in 1978. A comprehensive revision of the report is expected when the new government's…

  6. 28 CFR 94.41 - Interim emergency payment.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 28 Judicial Administration 2 2012-07-01 2012-07-01 false Interim emergency payment. 94.41 Section 94.41 Judicial Administration DEPARTMENT OF JUSTICE (CONTINUED) CRIME VICTIM SERVICES International Terrorism Victim Expense Reimbursement Program Payment of Claims § 94.41 Interim emergency...

  7. 28 CFR 94.41 - Interim emergency payment.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 28 Judicial Administration 2 2014-07-01 2014-07-01 false Interim emergency payment. 94.41 Section 94.41 Judicial Administration DEPARTMENT OF JUSTICE (CONTINUED) CRIME VICTIM SERVICES International Terrorism Victim Expense Reimbursement Program Payment of Claims § 94.41 Interim emergency...

  8. 28 CFR 94.41 - Interim emergency payment.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 28 Judicial Administration 2 2013-07-01 2013-07-01 false Interim emergency payment. 94.41 Section 94.41 Judicial Administration DEPARTMENT OF JUSTICE (CONTINUED) CRIME VICTIM SERVICES International Terrorism Victim Expense Reimbursement Program Payment of Claims § 94.41 Interim emergency...

  9. 28 CFR 94.41 - Interim emergency payment.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 28 Judicial Administration 2 2011-07-01 2011-07-01 false Interim emergency payment. 94.41 Section 94.41 Judicial Administration DEPARTMENT OF JUSTICE (CONTINUED) CRIME VICTIM SERVICES International Terrorism Victim Expense Reimbursement Program Payment of Claims § 94.41 Interim emergency...

  10. 49 CFR 37.193 - Interim service requirements.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... WITH DISABILITIES (ADA) Over-the-Road Buses (OTRBs) § 37.193 Interim service requirements. (a) Until... accessible bus, the operator has met this requirement. (2) Interim service under this paragraph (a) is not... percent of which consists of accessible buses (e.g., a small fixed-route operator who exclusively...

  11. 49 CFR 37.193 - Interim service requirements.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... WITH DISABILITIES (ADA) Over-the-Road Buses (OTRBs) § 37.193 Interim service requirements. (a) Until... accessible bus, the operator has met this requirement. (2) Interim service under this paragraph (a) is not... percent of which consists of accessible buses (e.g., a small fixed-route operator who exclusively...

  12. 49 CFR 37.193 - Interim service requirements.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... WITH DISABILITIES (ADA) Over-the-Road Buses (OTRBs) § 37.193 Interim service requirements. (a) Until... accessible bus, the operator has met this requirement. (2) Interim service under this paragraph (a) is not... percent of which consists of accessible buses (e.g., a small fixed-route operator who exclusively...

  13. 49 CFR 106.35 - Interim final rule.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... Transportation Other Regulations Relating to Transportation PIPELINE AND HAZARDOUS MATERIALS SAFETY... requirements and their effective date. PHMSA may issue an interim final rule if it finds, for good cause, that... comments, as well as any other relevant documents, PHMSA may revise the interim final rule and then issue...

  14. 49 CFR 106.35 - Interim final rule.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... Transportation Other Regulations Relating to Transportation PIPELINE AND HAZARDOUS MATERIALS SAFETY... requirements and their effective date. PHMSA may issue an interim final rule if it finds, for good cause, that... comments, as well as any other relevant documents, PHMSA may revise the interim final rule and then issue...

  15. 49 CFR 106.35 - Interim final rule.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... Transportation Other Regulations Relating to Transportation PIPELINE AND HAZARDOUS MATERIALS SAFETY... requirements and their effective date. PHMSA may issue an interim final rule if it finds, for good cause, that... comments, as well as any other relevant documents, PHMSA may revise the interim final rule and then issue...

  16. 49 CFR 106.35 - Interim final rule.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... Transportation Other Regulations Relating to Transportation PIPELINE AND HAZARDOUS MATERIALS SAFETY... requirements and their effective date. PHMSA may issue an interim final rule if it finds, for good cause, that... comments, as well as any other relevant documents, PHMSA may revise the interim final rule and then issue...

  17. 40 CFR 80.141 - Interim detergent gasoline program.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 40 Protection of Environment 17 2013-07-01 2013-07-01 false Interim detergent gasoline program. 80... (CONTINUED) REGULATION OF FUELS AND FUEL ADDITIVES Detergent Gasoline § 80.141 Interim detergent gasoline... ultimate consumer; (ii) All additized post-refinery component (PRC); and (iii) All detergent additives...

  18. 40 CFR 80.141 - Interim detergent gasoline program.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 40 Protection of Environment 17 2014-07-01 2014-07-01 false Interim detergent gasoline program. 80... (CONTINUED) REGULATION OF FUELS AND FUEL ADDITIVES Detergent Gasoline § 80.141 Interim detergent gasoline... ultimate consumer; (ii) All additized post-refinery component (PRC); and (iii) All detergent additives...

  19. Augmented Reality Mentor for Training Maintenance Procedures: Interim Assessment

    DTIC Science & Technology

    2014-08-01

    ARI Research Note 2014-04 Augmented Reality Mentor for Training Maintenance Procedures: Interim Assessment Louise...2014 4. TITLE AND SUBTITLE Augmented Reality Mentor for Training Maintenance Procedures: Interim Assessment 5a. CONTRACT OR GRANT NUMBER...Representative and Subject Matter POC: Dr. William R. Bickley 14. ABSTRACT (Maximum 200 words): The Augmented Reality Mentor is a 2-yr advanced

  20. 10 CFR 590.403 - Emergency interim orders.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... DEPARTMENT OF ENERGY (CONTINUED) NATURAL GAS (ECONOMIC REGULATORY ADMINISTRATION) ADMINISTRATIVE PROCEDURES WITH RESPECT TO THE IMPORT AND EXPORT OF NATURAL GAS Opinions and Orders § 590.403 Emergency interim... and issue an emergency interim order authorizing the import or export of natural gas. After...

  1. 10 CFR 590.403 - Emergency interim orders.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... DEPARTMENT OF ENERGY (CONTINUED) NATURAL GAS (ECONOMIC REGULATORY ADMINISTRATION) ADMINISTRATIVE PROCEDURES WITH RESPECT TO THE IMPORT AND EXPORT OF NATURAL GAS Opinions and Orders § 590.403 Emergency interim... and issue an emergency interim order authorizing the import or export of natural gas. After...

  2. 42 CFR 418.307 - Periodic interim payments.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... (CONTINUED) MEDICARE PROGRAM HOSPICE CARE Payment for Hospice Care § 418.307 Periodic interim payments. Subject to the provisions of § 413.64(h) of this chapter, a hospice may elect to receive periodic interim... PIP method unless the hospice requests a longer fixed interval (not to exceed one month)...

  3. 47 CFR 73.404 - Interim hybrid IBOC DAB operation.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... RADIO BROADCAST SERVICES Digital Audio Broadcasting § 73.404 Interim hybrid IBOC DAB operation. (a) The... test operation pursuant to § 73.1620, may commence interim hybrid IBOC DAB operation with digital... No. 99-325. FM stations are permitted to operate with hybrid digital effective radiated power...

  4. 47 CFR 73.404 - Interim hybrid IBOC DAB operation.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... RADIO BROADCAST SERVICES Digital Audio Broadcasting § 73.404 Interim hybrid IBOC DAB operation. (a) The... test operation pursuant to § 73.1620, may commence interim hybrid IBOC DAB operation with digital... No. 99-325. FM stations are permitted to operate with hybrid digital effective radiated power...

  5. 17 CFR 210.8-03 - Interim financial statements.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... filed with the interim financial statements. Interim financial statements shall include a balance sheet as of the end of the issuer's most recent fiscal quarter, a balance sheet as of the end of the... date of such balance sheet and the comparable period of the preceding fiscal year. (a) Condensed...

  6. Evaluation of ERA-interim and MERRA Cloudiness in the Southern Oceans

    NASA Technical Reports Server (NTRS)

    Naud, Catherine M.; Booth, James F.; Del Genio, Anthony D.

    2014-01-01

    The Southern Ocean cloud cover modeled by the Interim ECMWF Re-Analysis (ERA-Interim) and Modern- Era Retrospective Analysis for Research and Applications (MERRA) reanalyses are compared against Moderate Resolution Imaging Spectroradiometer (MODIS) and Multiangle Imaging Spectroradiometer (MISR) observations. ERA-Interim monthly mean cloud amounts match the observations within 5%, while MERRA significantly underestimates the cloud amount. For a compositing analysis of clouds in warm season extratropical cyclones, both reanalyses show a low bias in cloud cover. They display a larger bias to the west of the cyclones in the region of subsidence behind the cold fronts. This low bias is larger for MERRA than for ERA-Interim. Both MODIS and MISR retrievals indicate that the clouds in this sector are at a low altitude, often composed of liquid, and of a broken nature. The combined CloudSat-Cloud-Aerosol Lidar and Infrared Pathfinder Satellite Observations (CALIPSO) cloud profiles confirm these passive observations, but they also reveal that low-level clouds in other parts of the cyclones are also not properly represented in the reanalyses. The two reanalyses are in fairly good agreement for the dynamic and thermodynamic characteristics of the cyclones, suggesting that the cloud, convection, or boundary layer schemes are the problem instead. An examination of the lower-tropospheric stability distribution in the cyclones from both reanalyses suggests that the parameterization of shallow cumulus clouds may contribute in a large part to the problem. However, the differences in the cloud schemes and in particular in the precipitation processes, which may also contribute, cannot be excluded.

  7. Central waste complex interim safety basis

    SciTech Connect

    Cain, F.G.

    1995-05-15

    This interim safety basis provides the necessary information to conclude that hazards at the Central Waste Complex are controlled and that current and planned activities at the CWC can be conducted safely. CWC is a multi-facility complex within the Solid Waste Management Complex that receives and stores most of the solid wastes generated and received at the Hanford Site. The solid wastes that will be handled at CWC include both currently stored and newly generated low-level waste, low-level mixed waste, contact-handled transuranic, and contact-handled TRU mixed waste.

  8. 50 CFR 259.30 - Application for Interim Capital Construction Fund Agreement (“Interim CCF Agreement”).

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 50 Wildlife and Fisheries 7 2010-10-01 2010-10-01 false Application for Interim Capital Construction Fund Agreement (âInterim CCF Agreementâ). 259.30 Section 259.30 Wildlife and Fisheries NATIONAL... FISHERIES CAPITAL CONSTRUCTION FUND Capital Construction Fund Agreement § 259.30 Application for...

  9. Evaluating the accotink creek restoration project for improving water quality, in-stream habitat, and bank stability

    USGS Publications Warehouse

    Struck, S.D.; Selvakumar, A.; Hyer, K.; O'Connor, T.

    2007-01-01

    Increased urbanization results in a larger percentage of connected impervious areas and can contribute large quantities of stormwater runoff and significant quantities of debris and pollutants (e.g., litter, oils, microorganisms, sediments, nutrients, organic matter, and heavy metals) to receiving waters. To improve water quality in urban and suburban areas, watershed managers often incorporate best management practices (BMPs) to reduce the quantity of runoff as well as to minimize pollutants and other stressors contained in stormwater runoff. It is well known that land-use practices directly impact urban streams. Stream flows in urbanized watersheds increase in magnitude as a function of impervious area and can result in degradation of the natural stream channel morphology affecting the physical, chemical, and biological integrity of the stream. Stream bank erosion, which also increases with increased stream flows, can lead to bank instability, property loss, infrastructure damage, and increased sediment loading to the stream. Increased sediment loads may lead to water quality degradation downstream and have negative impacts on fish, benthic invertebrates, and other aquatic life. Accotink Creek is in the greater Chesapeake Bay and Potomac watersheds, which have strict sediment criteria. The USEPA (United States Environmental Protection Agency) and USGS (United States Geological Survey) are investigating the effectiveness of stream restoration techniques as a BMP to decrease sediment load and improve bank stability, biological integrity, and in-stream water quality in an impaired urban watershed in Fairfax, Virginia. This multi-year project continuously monitors turbidity, specific conductance, pH, and water temperature, as well as biological and chemical water quality parameters. In addition, physical parameters (e.g., pebble counts, longitudinal and cross sectional stream surveys) were measured to assess geomorphic changes associated with the restoration. Data

  10. The role and meaning of interim housing in housing first programs for people experiencing homelessness and mental illness.

    PubMed

    Zerger, Suzanne; Francombe Pridham, Katherine; Jeyaratnam, Jeyagobi; Connelly, Jolynn; Hwang, Stephen; O'Campo, Patricia; Stergiopoulos, Vicky

    2014-07-01

    The housing first (HF) model for individuals experiencing homelessness and mental illness differs by design from traditional models that require consumers to achieve "housing readiness" by meeting program or treatment prerequisites in transitional housing settings prior to permanent housing placement. Given a growing body of evidence for its favorable outcomes and cost effectiveness, HF is increasingly seen as an alternative to and argument against these traditional programs. As such, it is important that the elements and implementation challenges of the HF model be clearly understood and articulated. This qualitative study explored a largely unexamined aspect of the HF model-the need for and meaning of temporary residential settings (interim housing), a place to stay while waiting to secure permanent housing-using interviews and focus groups with service providers and consumers who experienced interim housing during implementation of HF in a large urban center. Although interim housing may not be necessary for all programs implementing the model, our study revealed numerous reasons and demands for safe, flexible interim housing options, and illustrated how they influence the effectiveness of consumer recovery, continuous service engagement, and housing stability.

  11. Interim results from the characterization testing of the Engineering Development (EDM) rubidium clocks for satellite applications

    NASA Technical Reports Server (NTRS)

    Powers, Edward D., Jr.; Danzy, Fredrick

    1990-01-01

    Some interim results from the environmental testing program to evaluate the Engineering Design Model (EDM) of the EG and G Spaceborne Rubidium Clock are presented. This effort is in support of the Global Positioning System (GPS) BLOCK IIR program and is intended to characterize the performance of EG and G design for BLOCK IIR satellite applications. Two EG and G EDM units are currently under test at NRL's Clock Test Facility to measure the long-term frequency stability, drift, and frequency versus temperature characteristics.

  12. Design of an interim space rescue ferry vehicle

    NASA Technical Reports Server (NTRS)

    Halsell, James D., Jr.; Widhalm, Joseph W.; Whitsett, Charles E.

    1988-01-01

    This paper proposes a stop-gap nonoptimum vehicle for transferring astronauts from a tumbling stranded spacecraft to a nearby rescue spacecraft. The design is limited to the use of available or 'soon-to-be' available flight-qualified hardware and consists of three major components: the manned maneuvering unit, the personnel rescue enclosure, and the apogee kick motor capture device. The apogee kick motor capture device is modified to serve as the connection between the manned maneuvering unit and the personnel rescue enclosure. The performance of this interim rescue vehicle is analyzed with NASA flight simulation software to test the feasibility of the design. Results show that the control system of the manned maneuvering unit adequately limits uncommanded rotations during all simulated maneuvers in the primary control mode but not during transverse translations in the backup control mode. Impingement of thruster plumes on the personnel rescue enclosure is shown to be of some importance in certain maneuvers. The satellite stabilization mode of the control system is found to have significant rotational-to-translational coupling that has associated adverse effects on flying qualities, making the mode undesirable for the rescue mission.

  13. Process safety management and interim or remedial action plans

    SciTech Connect

    Boss, M.J.; Henney, D.A.; Heitzman, V.K.; Day, D.W.

    1996-12-31

    Remedial Actions, including Interim Remedial Activities, often require the use of treatment facilities or stabilization techniques using on-site chemical processes. As such, the 29 CFR 1910.119 Process Safety Management (PSM) of Highly Hazardous Chemicals (PSM Standard) and the USEPA regulations for Risk Management Planning require that these chemicals and their attendant potential hazards be identified. A Hazard and Operation (HAZOP) study, Failure Mode and Effect Analysis (FMEA), Fault Tree Analysis, or equivalent graphic presentation of processes must be completed. These studies form a segment of the Process Hazard Analysis (PHA). HAZOP addresses each system and each element of a system that could deviate from normal operations and thus cause a hazard. A full assessment of each process is produced by looking at the hazards, consequences, causes and personnel protection needed. Many variables must be considered when choosing the appropriate PHA technique including the size of the plant, the number of processes, the types of processes, and the types of chemicals used. A mixture of these techniques may be required to adequately transmit information about the process being evaluated.

  14. Interim measure work plan/design for Agra, Kansas.

    SciTech Connect

    LaFreniere, L. M.; Environmental Science Division

    2008-11-18

    This Interim Measure Work Plan/Design (IMWP/D) is supplemental to the Argonne document Interim Measure Conceptual Design for Remediation of Source Area Contamination at Agra, Kansas. The IMWP/D includes information required by Kansas Department of Health and Environment (KDHE) Policy BER-RS-029, Policy and Scope of Work for Interim Measures. Specific to Policy BER-RS-029 is the requirement for several documents that will ensure that an adequate amount and type of data are collected for implementation of the IMWP/D and that data quality and safe conditions are prevailed. Such information is included in the IMWP/D as follows: Appendix A: Data Acquisition Plan--Design Testing Requirements; Appendix B: Basis of Design; Appendix C: Permits; Appendix D: Quality Assurance Project Plan; Appendix E: Health and Safety Plan; and Appendix F: Operations, Maintenance, and Monitoring Schedule. The proposed remedial technology for this project is the installation of five large-diameter boreholes (LDBs) in a source area that has been identified on the property formerly used for grain storage by the Commodity Credit Corporation of the U.S. Department of Agriculture (CCC/USDA). The goal of the LDB technology is the remediation of the source area by removal of mass quantities of contaminated soil from the vadose zone and treatment of any remaining contaminated soils that are adjacent to the source area to achieve a carbon tetrachloride concentration below 200 {micro}g/kg. Secondary to the soil remediation is the remediation of groundwater at and adjacent to the source areas. The LDB technology serves the following purposes: (1) The physical removal of contaminated soil from the identified source area. (2) Replacement of less permeable native materials (silty clay, clayey silt, and silty sand) with more permeable materials to facilitate the capture of volatilized contaminants in the vertical borehole. (3) Removal of contaminants volatilized by air sparging (AS) and extracted from the

  15. High normalized beta plasmas exceeding the ideal stability limit and projected RWM active stabilization performance using newly installed feedback sensors in KSTAR

    NASA Astrophysics Data System (ADS)

    Park, Y. S.; Sabbagh, S. A.; Berkery, J. W.; Bialek, J. M.; Yoon, S. W.; Jeon, Y. M.; Bak, J. G.; Ko, W. H.; Hahn, S. H.; Bae, C.; Bae, Y. S.; in, Y. K.; Kim, J.; Lee, S. G.; Kwak, J. G.; Oh, Y. K.; Park, H. K.; Choi, M. J.; Yun, G. S.

    2015-11-01

    H-mode plasma operation of KSTAR has been expanded to significantly surpass the ideal MHD no-wall beta limit by achieving normalized beta up to 4.3 while reducing plasma internal inductance to near 0.7 exceeding the computed n = 1 ideal no-wall limit by a factor of 1.6. These high normalized beta values have been achieved in discharges having BT in the range 0.9-1.1 T after the plasma reached flattop current of 0.35-0.4 MA, with the highest neutral beam heating power of 4 MW. A significant conclusion of the analysis of these plasmas is that low- n global kink/ballooning or RWMs were not detected, and therefore were not the cause of the plasma termination. Advances from the 2015 run campaign aiming to achieve prolonged pulse duration at maximum normalized beta and to subsequently investigate the MHD stability of these plasmas will be reported. As KSTAR H-mode operation can now routinely surpass the ideal no-wall stability limit, n = 1 RWM active control is planned for the device. RWM active feedback using a newly installed set of poloidal magnetic field sensors mounted on the passive stabilizer plates and designed for optimal performance is analyzed using the VALEN-3D code. The advantages of the new sensors over other device sensors for RWM active control are discussed. Supported by U.S. DOE grant DE-FG02-99ER54524.

  16. MERRA/AS: The MERRA Analytic Services Project Interim Report

    NASA Technical Reports Server (NTRS)

    Schnase, John; Duffy, Dan; Tamkin, Glenn; Nadeau, Denis; Thompson, Hoot; Grieg, Cristina; Luczak, Ed; McInerney, Mark

    2013-01-01

    MERRA AS is a cyberinfrastructure resource that will combine iRODS-based Climate Data Server (CDS) capabilities with Coudera MapReduce to serve MERRA analytic products, store the MERRA reanalysis data collection in an HDFS to enable parallel, high-performance, storage-side data reductions, manage storage-side driver, mapper, reducer code sets and realized objects for users, and provide a library of commonly used spatiotemporal operations that can be composed to enable higher-order analyses.

  17. Putting Data to Work: Interim Recommendations from The Benchmarking Project

    ERIC Educational Resources Information Center

    Miles, Marty; Maguire, Sheila; Woodruff-Bolte, Stacy; Clymer, Carol

    2010-01-01

    As public and private funders have focused on evaluating the effectiveness of workforce development programs, a myriad of data collection systems and reporting processes have taken shape. Navigating these systems takes significant time and energy and often saps frontline providers' capacity to use data internally for program improvement.…

  18. An Interim Report on the MCAT Essay Pilot Project.

    ERIC Educational Resources Information Center

    Koenig, Judith Anderson; Mitchell, Karen J.

    1988-01-01

    The results from four pilot administrations of the Medical College Admission Test essay question are reported. Analyses focused on the performance characteristics of sample groups; the relationships between essay scores and academic/demographic characteristics; and the reliability of one 45-minute versus two 30-minute essays. (Author/MLW)

  19. Interim reclamation report: Basalt Waste Isolation Project exploration shaft site

    SciTech Connect

    Brandt, C.A.; Rickard, W.H. Jr.; Hefty, M.G.

    1990-02-01

    In 1968, a program was started to assess the feasibility of storing Hanford Site defense waste in deep caverns constructed in basalt. This program was expanded in 1976 to include investigations of the Hanford Site as a potential location for a mined commercial nuclear waste repository. Extensive studies of the geotechnical aspects of the site were undertaken, including preparations for drilling a large diameter Exploratory Shaft. This report describes the development of the reclamation program for the Exploratory Shaft Facility, its implementation, and preliminary estimates of its success. The goal of the reclamation program is to return sites disturbed by the repository program as nearly as practicable to their original conditions using native plant species. 43 refs., 19 figs., 9 tabs.

  20. Technical support for the Soiltech soil washing project. Interim report

    SciTech Connect

    Tomascik, T.S.

    1994-08-01

    The organic removal ability of a surfactant solution was studied for an ``as-received`` soil sample. A 15% surfactant solution was added to an equal portion of the soil sample, by volume, and blended. The mixture was then stirred with a magnetic stirrer. A black precipitate resulted, which was then periodically skimmed off the top of the solution. This was done at both room temperature and at 150{degrees}F. The soil sample was examined before and after processing with optical microscopy, environmental scanning electron microscopy (ESEM) , energy dispersive x-ray microanalysis (EDS), and analytical chemical analysis (total oil and grease and petroleum hydrocarbons).

  1. Interim treatment: Bridging delays to opioid treatment access

    PubMed Central

    Sigmon, Stacey C.

    2015-01-01

    Objective Despite the undisputed effectiveness of agonist maintenance for opioid dependence, individuals can remain on waitlists for months, during which they are at significant risk for morbidity and mortality. To mitigate these risks, the Food and Drug Administration in 1993 approved interim treatment, involving daily medication + emergency counseling only, when only a waitlist is otherwise available. We review the published research in the 20 years since the approval of interim opioid treatment. Methods A literature search was conducted to identify all randomized trials evaluating the efficacy of interim treatment for opioid-dependent patients awaiting comprehensive treatment. Results Interim opioid treatment has been evaluated in four controlled trials to date. In three, interim treatment was compared to waitlist or placebo control conditions and produced greater outcomes on measures of illicit opioid use, retention, criminality and likelihood of entry into comprehensive treatment. In the fourth, interim treatment was compared to standard methadone maintenance and produced comparable outcomes in illicit opioid use, retention and criminal activity. Conclusions Interim treatment significantly reduces patient and societal risks when conventional treatment is unavailable. Further research is needed to examine the generality of these findings, further enhance outcomes, and identify the patient characteristics which predict treatment response. PMID:25937593

  2. The Time Needed to Implement the Blue Ribbon Commission Recommendation on Interim Storage - 13124

    SciTech Connect

    Voegele, Michael D.; Vieth, Donald

    2013-07-01

    The report of the Blue Ribbon Commission on America's Nuclear Future [1] makes a number of important recommendations to be considered if Congress elects to redirect U.S. high-level radioactive waste disposal policy. Setting aside for the purposes of this discussion any issues related to political forces leading to stopping progress on the Yucca Mountain project and driving the creation of the Commission, an important recommendation of the Commission was to institute prompt efforts to develop one or more consolidated storage facilities. The Blue Ribbon Commission noted that this recommended strategy for future storage and disposal facilities and operations should be implemented regardless of what happens with Yucca Mountain. It is too easy, however, to focus on interim storage as an alternative to geologic disposal. The Blue Ribbon Commission report does not go far enough in addressing the magnitude of the contentious problems associated with reopening the issues of relative authorities of the states and federal government with which Congress wrestled in crafting the Nuclear Waste Policy Act [2]. The Blue Ribbon Commission recommendation for prompt adoption of an interim storage program does not appear to be fully informed about the actions that must be taken, the relative cost of the effort, or the realistic time line that would be involved. In essence, the recommendation leaves to others the details of the systems engineering analyses needed to understand the nature and details of all the operations required to reach an operational interim storage facility without derailing forever the true end goal of geologic disposal. The material presented identifies a number of impediments that must be overcome before the country could develop a centralized federal interim storage facility. In summary, and in the order presented, they are: 1. Change the law, HJR 87, PL 107-200, designating Yucca Mountain for the development of a repository. 2. Bring new nuclear waste

  3. Retention of long-term interim restorations with sodium fluoride enriched interim cement

    NASA Astrophysics Data System (ADS)

    Strash, Carolyn

    Purpose: Interim fixed dental prostheses, or "provisional restorations", are fabricated to restore teeth when definitive prostheses are made indirectly. Patients undergoing extensive prosthodontic treatment frequently require provisionalization for several months or years. The ideal interim cement would retain the restoration for as long as needed and still allow for ease of removal. It would also avoid recurrent caries by preventing demineralization of tooth structure. This study aims to determine if adding sodium fluoride varnish to interim cement may assist in the retention of interim restorations. Materials and methods: stainless steel dies representing a crown preparation were fabricated. Provisional crowns were milled for the dies using CAD/CAM technology. Crowns were provisionally cemented onto the dies using TempBond NE and NexTemp provisional cements as well as a mixture of TempBond NE and Duraphat fluoride varnish. Samples were stored for 24h then tested or thermocycled for 2500 or 5000 cycles before being tested. Retentive strength of each cement was recorded using a universal testing machine. Results: TempBond NE and NexTemp cements performed similarly when tested after 24h. The addition of Duraphat significantly decreased the retention when added to TempBond NE. NexTemp cement had high variability in retention over all tested time periods. Thermocycling for 2500 and 5000 cycles significantly decreased the retention of all cements. Conclusions: The addition of Duraphat fluoride varnish significantly decreased the retention of TempBond NE and is therefore not recommended for clinical use. Thermocycling significantly reduced the retention of TempBond NE and NexTemp. This may suggest that use of these cements for three months, as simulated in this study, is not recommended.

  4. Temporary extension of attorney fee payment system to Title XVI; 5-year demonstration project extending fee withholding and payment procedures to eligible non-attorney representatives; definition of past-due benefits; and assessment for fee payment services. Interim final rules with request for comments.

    PubMed

    2007-04-05

    We are issuing these interim final rules to reflect in our regulations three self-implementing statutory provisions in the Social Security Protection Act of 2004 (SSPA) and three related self-implementing provisions in earlier legislation. These earlier provisions are in the Omnibus Budget Reconciliation Act of 1990 (OBRA), the Social Security Independence and Program Improvements Act of 1994 (SSIPIA), and the Ticket to Work and Work Incentives Improvement Act of 1999 (TWWIIA).

  5. Honeywell Cascade Distiller System Performance Testing Interim Results

    NASA Technical Reports Server (NTRS)

    Callahan, Michael R.; Sargusingh, Miriam

    2014-01-01

    The ability to recover and purify water through physiochemical processes is crucial for realizing long-term human space missions, including both planetary habitation and space travel. Because of their robust nature, distillation systems have been actively pursued as one of the technologies for water recovery. The Cascade Distillation System (CDS) is a vacuum rotary distillation system with potential for greater reliability and lower energy costs than existing distillation systems. The CDS was previously under development through Honeywell and NASA. In 2009, an assessment was performed to collect data to support down-selection and development of a primary distillation technology for application in a lunar outpost water recovery system. Based on the results of this testing, an expert panel concluded that the CDS showed adequate development maturity, TRL-4, together with the best product water quality and competitive weight and power estimates to warrant further development. The Advanced Exploration Systems (AES) Water Recovery Project (WRP) worked to address weaknesses identified by The Panel; namely bearing design and heat pump power efficiency. Testing at the NASA-JSC Advanced Exploration System Water Laboratory (AES Water Lab) using a prototype Cascade Distillation Subsystem (CDS) wastewater processor (Honeywell International, Torrance, Calif.) with test support equipment and control system developed by Johnson Space Center was performed to evaluate performance of the system with the upgrades. The CDS will also have been challenged with ISS analog waste streams and a subset of those being considered for Exploration architectures. This paper details interim results of the AES WRP CDS performance testing.

  6. Interim long-term surveillance plan for the Cheney disposal site near, Grand Junction, Colorado

    SciTech Connect

    1997-08-01

    This interim long-term surveillance plan (LTSP) describes the U.S. Department of Energy`s (DOE) long-term care program for the Uranium Mill Tailings Remedial Action (UMTRA) Project Cheney Disposal Site in Mesa County near Grand Junction, Colorado. This LSTP describes the long-term surveillance program the DOE will implement to ensure the Cheney disposal site performs as designed and is cared for in a manner that protects the public health and safety and the environment. Before each disposal site is licensed for custody and long-term care, the Nuclear Regulatory Commission (NRC) requires the DOE to submit such a site-specific LTSP.

  7. Operable Unit 3: Proposed Plan/Environmental Assessment for interim remedial action

    SciTech Connect

    Not Available

    1993-12-01

    This document presents a Proposed Plan and an Environmental Assessment for an interim remedial action to be undertaken by the US Department of Energy (DOE) within Operable Unit 3 (OU3) at the Fernald Environmental Management Project (FEMP). This proposed plan provides site background information, describes the remedial alternatives being considered, presents a comparative evaluation of the alternatives and a rationnale for the identification of DOE`s preferred alternative, evaluates the potential environmental and public health effects associated with the alternatives, and outlines the public`s role in helping DOE and the EPA to make the final decision on a remedy.

  8. The Army’s Gambit: Dislocation Theory and the Development of Doctrine for the Interim Brigade Combat Team

    DTIC Science & Technology

    2007-11-02

    Swift: Thoughts on Twenty-First Century Warfare. 2nd ed. London, England: Brassey Defense Publishing, 1986. Webster’s Third International Dictionary...Development of Doctrine for the Interim Brigade Combat Team Unclassified 5c. PROGRAM ELEMENT NUMBER 5d. PROJECT NUMBER 5e. TASK NUMBER 6. AUTHOR( S ) Adgie...Reynolds Ave. Fort Leavenworth , KS 66048 8. PERFORMING ORGANIZATION REPORT NUMBER 10. SPONSOR/MONITOR’S ACRONYM( S )9. SPONSORING/MONITORING AGENCY NAME

  9. Effects of a Universally Free, In-Classroom School Breakfast Program: Results from the Second Year of the Maryland Meals for Achievement Evaluation. Interim Report.

    ERIC Educational Resources Information Center

    Murphy, J. Michael; Rankin, Emunah; Feeney, Kelly; Kenney, Leigh; Kleinman, Ron

    Noting that many children in the United States are not well nourished despite the recent economic boom, the state of Maryland began the Maryland Meals for Achievement (MMFA) program, a demonstration project to see if providing a classroom breakfast free to all students can improve student nutrition and academic achievement. This interim report…

  10. St. Francis Rain Garden Water Quality Sampling Interim Data Report; Total Nitrogen, Total Phosphorus, Sediments or Solids, and E. Coli for the period April to June, 2014

    EPA Science Inventory

    This interim data reported is being provided per request to the Metropolitan Sewer District (MSD) to provide summary statistics on a limited set of water quality parameters as measured at the St. Francis Rain Garden site in the Lick Run Valley as it pertains to MSD's Project Grou...

  11. DOD Task Force for Business and Stability Operations: Actions Needed to Establish Project Management Guidelines and Enhance Information Sharing

    DTIC Science & Technology

    2011-07-01

    requirements to establish metrics, and monitoring and evaluation processes. As a result, the Task Force does not have the framework needed to ensure a...requirements to establish project metrics, monitoring and evaluation processes, and the type of project information that should be collected and documented...metrics, monitoring and evaluation processes, or how program managers should maintain project information. Standards for Internal Control in the

  12. Natural tooth as an interim prosthesis

    PubMed Central

    Dhariwal, Neha S.; Gokhale, Niraj S.; Patel, Punit; Hugar, Shivayogi M.

    2016-01-01

    A traumatic injury to primary maxillary anterior tooth is one of the common causes for problems with the succedaneous tooth leading to it noneruption. A missing anterior tooth can be psychologically and socially damaging to the patient. Despite a wide range of treatment options available, sometimes, it is inevitable to save the natural tooth. This paper describes the immediate replacement of a right central incisor using a fiber-composite resin splint with the natural tooth crown as a pontic following surgical extraction of the dilacerated impacted permanent maxillary central incisor. The abutment teeth can be conserved with minimal or no preparation, thus keeping the technique reversible and can be completed at chair side thereby avoiding laboratory costs. It can be used as an interim measure until a definitive prosthesis can be fabricated as the growth is still incomplete. PMID:27433074

  13. Interim prediction method for jet noise

    NASA Technical Reports Server (NTRS)

    Stone, J. R.

    1974-01-01

    A method is provided for predicting jet noise for a wide range of nozzle geometries and operating conditions of interest for aircraft engines. Jet noise theory, data and existing prediction methods was reviewed, and based on this information a interim method of jet noise prediction is proposed. Problem areas are idenified where further research is needed to improve the prediction method. This method predicts only the noise generated by the exhaust jets mixing with the surrounding air and does not include other noises emanating from the engine exhaust, such as combustion and machinery noise generated inside the engine (i.e., core noise). It does, however, include thrust reverser noise. Prediction relations are provided for conical nozzles, plug nozzles, coaxial nozzles and slot nozzles.

  14. Fire Hazards Analysis for the 200 Area Interim Storage Area

    SciTech Connect

    JOHNSON, D.M.

    2000-01-06

    This documents the Fire Hazards Analysis (FHA) for the 200 Area Interim Storage Area. The Interim Storage Cask, Rad-Vault, and NAC-1 Cask are analyzed for fire hazards and the 200 Area Interim Storage Area is assessed according to HNF-PRO-350 and the objectives of DOE Order 5480 7A. This FHA addresses the potential fire hazards associated with the Interim Storage Area (ISA) facility in accordance with the requirements of DOE Order 5480 7A. It is intended to assess the risk from fire to ensure there are no undue fire hazards to site personnel and the public and to ensure property damage potential from fire is within acceptable limits. This FHA will be in the form of a graded approach commensurate with the complexity of the structure or area and the associated fire hazards.

  15. Interim Guidance: Municipal Solid Waste Exemption under Superfund

    EPA Pesticide Factsheets

    Interim guidance discusses the statutory provisions of CERCLA § 107(p) and identifies some factors to be considered by EPA and DOJ staff in exercising their enforcement discretion of MSW at an NPL site.

  16. 46 CFR 308.303 - Amounts insured under interim binder.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... INSURANCE Second Seamen's War Risk Insurance § 308.303 Amounts insured under interim binder. The amounts insured are the amounts specified in the Second Seamen's War Risk Policy (1955) or as modified by...

  17. 46 CFR 308.303 - Amounts insured under interim binder.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... INSURANCE Second Seamen's War Risk Insurance § 308.303 Amounts insured under interim binder. The amounts insured are the amounts specified in the Second Seamen's War Risk Policy (1955) or as modified by...

  18. 46 CFR 308.303 - Amounts insured under interim binder.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... INSURANCE Second Seamen's War Risk Insurance § 308.303 Amounts insured under interim binder. The amounts insured are the amounts specified in the Second Seamen's War Risk Policy (1955) or as modified by...

  19. 46 CFR 308.303 - Amounts insured under interim binder.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... INSURANCE Second Seamen's War Risk Insurance § 308.303 Amounts insured under interim binder. The amounts insured are the amounts specified in the Second Seamen's War Risk Policy (1955) or as modified by...

  20. 40 CFR 155.56 - Interim registration review decision.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... required data, conducting the new risk assessment and completing the registration review. A FIFRA 3(c)(2)(B... registration review decision may require new risk mitigation measures, impose interim risk mitigation...

  1. 40 CFR 155.56 - Interim registration review decision.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... required data, conducting the new risk assessment and completing the registration review. A FIFRA 3(c)(2)(B... registration review decision may require new risk mitigation measures, impose interim risk mitigation...

  2. 40 CFR 155.56 - Interim registration review decision.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... required data, conducting the new risk assessment and completing the registration review. A FIFRA 3(c)(2)(B... registration review decision may require new risk mitigation measures, impose interim risk mitigation...

  3. 40 CFR 155.56 - Interim registration review decision.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... required data, conducting the new risk assessment and completing the registration review. A FIFRA 3(c)(2)(B... registration review decision may require new risk mitigation measures, impose interim risk mitigation...

  4. 14 CFR 91.871 - Waivers from interim compliance requirements.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... period will be at least 14 days. ... 14 Aeronautics and Space 2 2010-01-01 2010-01-01 false Waivers from interim compliance... TRANSPORTATION (CONTINUED) AIR TRAFFIC AND GENERAL OPERATING RULES GENERAL OPERATING AND FLIGHT RULES...

  5. 45 CFR 689.8 - Interim administrative actions.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... RESEARCH MISCONDUCT § 689.8 Interim administrative actions. (a) After an inquiry or during an external or... misconduct. Such an order will normally be issued on recommendation from OIG and in consultation with...

  6. TANK FARM INTERIM SURFACE BARRIER MATERIALS AND RUNOFF ALTERNATIVES STUDY

    SciTech Connect

    HOLM MJ

    2009-06-25

    This report identifies candidate materials and concepts for interim surface barriers in the single-shell tank farms. An analysis of these materials for application to the TY tank farm is also provided.

  7. EPA's Revised Interim Financial Assistance Conflict of Interest Policy

    EPA Pesticide Factsheets

    EPA has established the following revised interim policy governing disclosure of actual and potential conflicts of interest (COI Policy) by applicants for, and recipients of, federal financial assistance awards from EPA.

  8. Wide-Field Infrared Survey Telescope (WFIRST) Interim Report

    NASA Technical Reports Server (NTRS)

    Green, J.; Schechter, P.; Baltay, C.; Bean, R.; Bennett, D.; Brown, R.; Conselice, C.; Donahue, M.; Gaudi, S.; Lauer, T.; Perlmutter, S.; Rauscher, B.; Rhodes, J.; Roellig, T.; Stern, D.; Sumi, T.; Gerhels, N.; Sambruna, R.; Barry, R. K.; Content, D.; Grady, K; Jackson, C.; Kruk, J.; Melton, M.; Rioux, N.

    2011-01-01

    measurements. The Infrared Astronomical Satellite (IRAS), the Cosmic Background Explorer (COBE), Herschel, Spitzer, and Wide-field Infrared Sur-vey Explorer (WISE) are all space missions that have produced stunning new scientific advances by going to space to observe in the infrared. This interim report describes progress as of June 2011 on developing a requirements flowdown and an evaluation of scientific performance. An Interim Design Reference Mission (IDRM) configuration is presented that is based on the specifications of NWNH with some refinements to optimize the design in accordance with the new scientific requirements. Analysis of this WFIRST IDRM concept is in progress to ensure the capability of the observatory is compatible with the science requirements. The SDT and Project will continue to refine the mission concept over the coming year as design, analysis and simulation work are completed, resulting in the SDT s WFIRST Design Reference Mission (DRM) by the end of 2012.

  9. K basins interim remedial action health and safety plan

    SciTech Connect

    DAY, P.T.

    1999-09-14

    The K Basins Interim Remedial Action Health and Safety Plan addresses the requirements of the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA), as they apply to the CERCLA work that will take place at the K East and K West Basins. The provisions of this plan become effective on the date the US Environmental Protection Agency issues the Record of Decision for the K Basins Interim Remedial Action, currently planned in late August 1999.

  10. Interim Safety Basis for Fuel Supply Shutdown Facility

    SciTech Connect

    BENECKE, M.W.

    2000-09-07

    This ISB, in conjunction with the IOSR, provides the required basis for interim operation or restrictions on interim operations and administrative controls for the facility until a SAR is prepared in accordance with the new requirements or the facility is shut down. It is concluded that the risks associated with tha current and anticipated mode of the facility, uranium disposition, clean up, and transition activities required for permanent closure, are within risk guidelines.

  11. DEMONSTRATION OF THE DOE INTERIM ENERGY CONSERVATION STANDARDS FOR NEW FEDERAL RESIDENTIAL BUILDINGS: EXECUTIVE SUMMARY

    SciTech Connect

    Lee, A. D.; Baechler, M Di Massa, F. V.; Lucas, R. G.; Shankle, D. L.

    1992-01-01

    In accordance with federal legislation, the U.S. Department of Energy (DOE) bas conducted a project to demonstrate use of its Interim Energy Conservation Standards for New Federal Residential Buildings. The demonstration is the second step in a three-step process: development of interim standards, demonstration of the interim standards, and development of final standards. Pacific Northwest Laboratory (PNL) collected information from the demonstration project and prepared this report under a contract with DOE. The purpose of the standards is to improve the energy efficiency of federal housing and increase the use of nondepletable energy sources. In accordance with the legislation, the standards were to be performance-based rather than prescribing specific energy conservation measures. The standards use a computer software program called COSTSAFR which individualizes the standards based on climate, housing type, and fuel costs. The standards generate minimum energy-efficiency requirements by applying the life-cycle cost methodology developed for federal projects, For the demonstration, the DOE chose live federal agency housing projects: four military housing projects and one project for the Department of Health and Human Services. DOE and PNL worked with agency housing procurement officials and designers/architects to hypothetically apply the interim standards to each housing project. PNL conducted extensive interviews with the federal agencies and design contractors to determine what impacts the standards would have on the existing agency procurement process as well as on designers. Overall, PNL found that the interim standards met the basic intent of the law. Specific actions were identified, however, that DOE could take to improve the standards and encourage the agencies to implement them. Agency personnel and designers expressed similar concerns about the standards: the minimum efficiency levels established by the standards were lower than expected and the

  12. Interim Control Strategy for the Test Area North/Technical Support Facility Sewage Treatment Facility Disposal Pond - Two-year Update

    SciTech Connect

    L. V. Street

    2007-04-01

    The Idaho Cleanup Project has prepared this interim control strategy for the U.S. Department of Energy Idaho Operations Office pursuant to DOE Order 5400.5, Chapter 11.3e (1) to support continued discharges to the Test Area North/Technical Support Facility Sewage Treatment Facility Disposal Pond. In compliance with DOE Order 5400.5, a 2-year review of the Interim Control Strategy document has been completed. This submittal documents the required review of the April 2005 Interim Control Strategy. The Idaho Cleanup Project's recommendation is unchanged from the original recommendation. The Interim Control Strategy evaluates three alternatives: (1) re-route the discharge outlet to an uncontaminated area of the TSF-07; (2) construct a new discharge pond; or (3) no action based on justification for continued use. Evaluation of Alternatives 1 and 2 are based on the estimated cost and implementation timeframe weighed against either alternative's minimal increase in protection of workers, the public, and the environment. Evaluation of Alternative 3, continued use of the TSF-07 Disposal Pond under current effluent controls, is based on an analysis of four points: - Record of Decision controls will protect workers and the public - Risk of increased contamination is low - Discharge water will be eliminated in the foreseeable future - Risk of contamination spread is acceptable. The Idaho Cleanup Project recommends Alternative 3, no action other than continued implementation of existing controls and continued deactivation, decontamination, and dismantlement efforts at the Test Area North/Technical Support Facility.

  13. Stabilizing plutonium materials at Hanford: systems engineering for PFP transition project effort on DNFSB 94-1

    SciTech Connect

    Huber, T.E., Westinghouse Hanford

    1996-07-02

    This report discusses the basic objectives of the stabilization and packaging activities at the Plutonium Finishing Plant that satisfy the Defense Nuclear Facility Safety Board Recommendation 94-1 by transforming the plutonium materials at hanford into forms or conditions which are suitable for safe storage to appropriate storage criteria; or discard that meets appropriate waste acceptance criteria.

  14. Mine operating accurate stability control with optical fiber sensing and Bragg grating technology: the BRITE-EURAM STABILOS project

    NASA Astrophysics Data System (ADS)

    Ferdinand, Pierre; Ferragu, Olivier; Lechien, J. L.; Lescop, B.; Marty-DeWinter, Veronique; Rougeault, S.; Pierre, Guillaume; Renouf, C.; Jarret, Bertrand; Kotrotsios, Georges; Neuman, Victor; Depeursinge, Y.; Michel, J. B.; Van Uffelen, M.; Verbandt, Yves; Voet, Marc R. H.; Toscano, D.

    1994-09-01

    Recent developments of stability control in mines, essentially based on Ge-doped Fiber Bragg Gratings (FBG) are reported including results about the different aspects of the system: accurate characterizations of FBG, sensor network topology and multiplexing method, user interface design and sensor packaging.

  15. 76 FR 62760 - Foreign-Trade Zone 277-Western Maricopa County, AZ; Application for Temporary/Interim...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-10-11

    .../Interim Manufacturing Authority; Sub-Zero, Inc.; (Refrigerators); Goodyear, AZ An application has been... County Foreign Trade Zone, Inc., grantee of FTZ 277, requesting temporary/ interim manufacturing...

  16. Projection of Stabilized Aerial Imagery Onto Digital Elevation Maps for Geo-Rectified and Jitter-Free Viewing

    NASA Technical Reports Server (NTRS)

    Ansar, Adnan I.; Brennan, Shane; Clouse, Daniel S.

    2012-01-01

    As imagery is collected from an airborne platform, an individual viewing the images wants to know from where on the Earth the images were collected. To do this, some information about the camera needs to be known, such as its position and orientation relative to the Earth. This can be provided by common inertial navigation systems (INS). Once the location of the camera is known, it is useful to project an image onto some representation of the Earth. Due to the non-smooth terrain of the Earth (mountains, valleys, etc.), this projection is highly non-linear. Thus, to ensure accurate projection, one needs to project onto a digital elevation map (DEM). This allows one to view the images overlaid onto a representation of the Earth. A code has been developed that takes an image, a model of the camera used to acquire that image, the pose of the camera during acquisition (as provided by an INS), and a DEM, and outputs an image that has been geo-rectified. The world coordinate of the bounds of the image are provided for viewing purposes. The code finds a mapping from points on the ground (DEM) to pixels in the image. By performing this process for all points on the ground, one can "paint" the ground with the image, effectively performing a projection of the image onto the ground. In order to make this process efficient, a method was developed for finding a region of interest (ROI) on the ground to where the image will project. This code is useful in any scenario involving an aerial imaging platform that moves and rotates over time. Many other applications are possible in processing aerial and satellite imagery.

  17. The EMEFS model evaluation. An interim report

    SciTech Connect

    Barchet, W.R.; Dennis, R.L.; Seilkop, S.K.; Banic, C.M.; Davies, D.; Hoff, R.M.; Macdonald, A.M.; Mickle, R.E.; Padro, J.; Puckett, K.; Byun, D.; McHenry, J.N.; Karamchandani, P.; Venkatram, A.; Fung, C.; Misra, P.K.; Hansen, D.A.; Chang, J.S.

    1991-12-01

    The binational Eulerian Model Evaluation Field Study (EMEFS) consisted of several coordinated data gathering and model evaluation activities. In the EMEFS, data were collected by five air and precipitation monitoring networks between June 1988 and June 1990. Model evaluation is continuing. This interim report summarizes the progress made in the evaluation of the Regional Acid Deposition Model (RADM) and the Acid Deposition and Oxidant Model (ADOM) through the December 1990 completion of a State of Science and Technology report on model evaluation for the National Acid Precipitation Assessment Program (NAPAP). Because various assessment applications of RADM had to be evaluated for NAPAP, the report emphasizes the RADM component of the evaluation. A protocol for the evaluation was developed by the model evaluation team and defined the observed and predicted values to be used and the methods by which the observed and predicted values were to be compared. Scatter plots and time series of predicted and observed values were used to present the comparisons graphically. Difference statistics and correlations were used to quantify model performance. 64 refs., 34 figs., 6 tabs.

  18. Alaska interim land cover mapping program

    USGS Publications Warehouse

    ,

    1987-01-01

    In order to meet the requirements of the Alaska National Interest Lands Conservation Act (ANILCA) for comprehensive resource and management plans from all major land management agencies in Alaska, the USGS has begun a program to classify land cover for the entire State using Landsat digital data. Vegetation and land cover classifications, generated in cooperation with other agencies, currently exist for 115 million acres of Alaska. Using these as a base, the USGS has prepared a comprehensive plan for classifying the remaining areas of the State. The development of this program will lead to a complete interim vegetation and land cover classification system for Alaska and allow the dissemination of digital data for those areas classified. At completion, 153 Alaska 1:250,000-scale quadrangles will be published and will include land cover from digital Landsat classifications, statistical summaries of all land cover by township, and computer-compatible tapes. An interagency working group has established an Alaska classification system (table 1) composed of 18 classes modified from "A land use and land cover classification system for use with remote sensor data" (Anderson and others, 1976), and from "Revision of a preliminary classification system for vegetation of Alaska" (Viereck and Dyrness, 1982) for the unique ecoregions which are found in Alaska.

  19. E-Area Performance Assessment Interim Measures Assessment FY2005

    SciTech Connect

    Stallings, M

    2006-01-31

    After major changes to the limits for various disposal units of the E-Area Low Level Waste Facility (ELLWF) last year, no major changes have been made during FY2005. A Special Analysis was completed which removes the air pathway {sup 14}C limit from the Intermediate Level Vault (ILV). This analysis will allow the disposal of reactor moderator deionizers which previously had no pathway to disposal. Several studies have also been completed providing groundwater transport input for future special analyses. During the past year, since Slit Trenches No.1 and No.2 were nearing volumetric capacity, they were operationally closed under a preliminary closure analysis. This analysis was performed using as-disposed conditions and data and showed that concrete rubble from the demolition of 232-F was acceptable for disposal in the STs even though the latest special analysis for the STs had reduced the tritium limits so that the inventory in the rubble exceeded limits. A number of special studies are planned during the next years; perhaps the largest of these will be revision of the Performance Assessment (PA) for the ELLWF. The revision will be accomplished by incorporating special analyses performed since the last PA revision as well as revising analyses to include new data. Projected impacts on disposal limits of more recent studies have been estimated. No interim measures will be applied during this year. However, it is being recommended that tritium disposals to the Components-in-Grout (CIG) Trenches be suspended until a limited Special Analysis (SA) currently in progress is completed. This SA will give recommendations for optimum placement of tritiated D-Area tower waste. Further recommendations for tritiated waste placement in the CIG Trenches will be given in the upcoming PA revision.

  20. High Temperature Materials Interim Data Qualification Report FY 2011

    SciTech Connect

    Nancy Lybeck

    2011-08-01

    Projects for the very high temperature reactor (VHTR) Technology Development Office provide data in support of Nuclear Regulatory Commission licensing of the VHTR. Fuel and materials to be used in the reactor are tested and characterized to quantify performance in high temperature and high fluence environments. The VHTR program has established the Next Generation Nuclear Plant (NGNP) Data Management and Analysis System (NDMAS) to ensure that VHTR data are qualified for use, stored in a readily accessible electronic form, and analyzed to extract useful results. This document focuses on the first NDMAS objective. It describes the High Temperature Materials characterization data stream, the processing of these data within NDMAS, and reports the interim fiscal year (FY) 2011 qualification status of the data. Data qualification activities within NDMAS for specific types of data are determined by the data qualification category assigned by the data generator. The High Temperature Materials data are being collected under the Nuclear Quality Assurance (NQA)-1 guidelines and will be qualified data. For NQA-1 qualified data, the qualification activities include: (1) capture testing to confirm that the data stored within NDMAS are identical to the raw data supplied, (2) accuracy testing to confirm that the data are an accurate representation of the system or object being measured, and (3) documenting that the data were collected under an NQA-1 or equivalent Quality Assurance program. Currently, data from seven test series within the High Temperature Materials data stream have been entered into the NDMAS vault, including tensile tests, creep tests, and cyclic tests. Of the 5,603,682 records currently in the vault, 4,480,444 have been capture passed, and capture testing is in process for the remaining 1,123,238.

  1. 46 CFR 308.6 - Period of interim binders, updating application information and new applications.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... with the American War Risk Agency, 14 Wall Street, New York, New York 10005. All interim binders on U.S... Wall Street, New York, New York 10005. All interim binders on foreign-flag vessels will...

  2. 46 CFR 308.6 - Period of interim binders, updating application information and new applications.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... with the American War Risk Agency, 14 Wall Street, New York, New York 10005. All interim binders on U.S... Wall Street, New York, New York 10005. All interim binders on foreign-flag vessels will...

  3. 46 CFR 308.6 - Period of interim binders, updating application information and new applications.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... with the American War Risk Agency, 14 Wall Street, New York, New York 10005. All interim binders on U.S... Wall Street, New York, New York 10005. All interim binders on foreign-flag vessels will...

  4. 76 FR 59394 - Energy Conservation Program for Consumer Products: Publication of the Extension of Interim Waiver...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-09-26

    ...: Publication of the Extension of Interim Waiver Granted to Samsung Electronics America, Inc. From the... petition for waiver and notice granting an application for interim waiver to Samsung Electronics...

  5. Performance of concrete pavements containing recycled concrete aggregate. Interim report, October 1993-October 1996

    SciTech Connect

    Wade, M.J.; Cuttell, G.D.; Vandenbossche, J.M.; Yu, H.T.; Smith, K.D.

    1997-03-01

    This interim report documents the field performance of nine concrete pavement projects that incorporate recycled concrete aggregate (RCA) in the construction of the pavement. Multiple sections were evaluated on many of the nine projects, due to perceived differences in performance levels or variations in pavement design (such as the use of virgin aggregate or the inclusion of dowel bars). All told, a total of 17 sections (of which 12 contain RCA) were subjected to an extensive field testing program, consisting of pavement condition surveys, drainage surveys, falling weight deflectometer (FWD) testing, coring, and serviceability assessments. A minimum of eight cores were retrieved from each section for laboratory evaluation of compressive strength, split tensile strength, dynamic elastic modulus, static elastic modulus, and thermal coefficient of expansion, as well as for volumetric surface testing and petrographic analyses.

  6. 46 CFR 308.6 - Period of interim binders, updating application information and new applications.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... TRANSPORTATION EMERGENCY OPERATIONS WAR RISK INSURANCE General § 308.6 Period of interim binders, updating... interim binders are required to notify the American War Risk Agency annually, by June 30th, of any change... with the American War Risk Agency, 14 Wall Street, New York, New York 10005. All interim binders on...

  7. 75 FR 10476 - Interim Change to the Military Freight Traffic Unified Rules Publication (MFTURP) No. 1

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-03-08

    ... Department of the Army Interim Change to the Military Freight Traffic Unified Rules Publication (MFTURP) No... Command (SDDC) is providing notice that it released an interim change to the MFTURP No. 1 on February 17, 2010. The interim change removes Motor Surveillance Service (MVS) from Item 107 and replaces Item...

  8. 77 FR 50016 - Extension of Interim Final Temporary Rule on Retail Foreign Exchange Transactions; Correction

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-08-20

    ... COMMISSION 17 CFR Part 240 RIN 3235-AL19 Extension of Interim Final Temporary Rule on Retail Foreign Exchange Transactions; Correction AGENCY: Securities and Exchange Commission. ACTION: Interim final temporary rule... interim final temporary Rule 15b12-1T to extend the date on which the rule will expire. That rule...

  9. 77 FR 65366 - Interim Procedures for Considering Requests From the Public for Textile and Apparel Safeguard...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-10-26

    ...)] RIN 0625-XC003 Interim Procedures for Considering Requests From the Public for Textile and Apparel... Agreements. ACTION: Notice of Interim Procedures and Request for Comments. SUMMARY: This notice sets forth the interim procedures the Committee for the Implementation of Textile Agreements (``CITA'')...

  10. 77 FR 34399 - Public Housing Assessment System (PHAS): Capital Fund Interim Scoring Notice; Request for Comment

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-06-11

    ... URBAN DEVELOPMENT Public Housing Assessment System (PHAS): Capital Fund Interim Scoring Notice; Request... PHAs for the Capital Fund Indicator under the PHAS interim rule published February 23, 2011. The award... PHAS interim rule, especially as relates to the indicator that assesses occupancy rate. The 5...

  11. 42 CFR 417.572 - Budget and enrollment forecast and interim reports.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 42 Public Health 3 2010-10-01 2010-10-01 false Budget and enrollment forecast and interim reports... forecast and interim reports. (a) Annual submittal. The HMO or CMP must submit an annual operating budget... interim per capita rate of payment on the basis of the best available data and adjust payments on...

  12. 46 CFR 308.302 - Issuance of interim binder; terms and conditions.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 46 Shipping 8 2010-10-01 2010-10-01 false Issuance of interim binder; terms and conditions. 308... OPERATIONS WAR RISK INSURANCE Second Seamen's War Risk Insurance § 308.302 Issuance of interim binder; terms and conditions. Upon acceptance of an application, an interim binder in form as set forth in §...

  13. 75 FR 63080 - Interim Final Rule for Reporting Pre-Enactment Swap Transactions

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-10-14

    ... COMMISSION 17 CFR Part 44 RIN 3038-AD24 Interim Final Rule for Reporting Pre-Enactment Swap Transactions AGENCY: Commodity Futures Trading Commission. ACTION: Interim final rule; request for public comment... an interim final rule to implement new statutory provisions introduced by Title VII of the...

  14. 46 CFR 308.202 - Issuance of interim binder; terms and conditions.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 46 Shipping 8 2010-10-01 2010-10-01 false Issuance of interim binder; terms and conditions. 308... OPERATIONS WAR RISK INSURANCE War Risk Protection and Indemnity Insurance § 308.202 Issuance of interim binder; terms and conditions. Upon acceptance of an application, an interim binder in form as set...

  15. 40 CFR 57.302 - Performance level of interim constant controls.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 40 Protection of Environment 5 2010-07-01 2010-07-01 false Performance level of interim constant... Performance level of interim constant controls. (a) Maximum feasible efficiency. Each NSO shall require: that the smelter operate its interim constant control systems at their maximum feasible...

  16. 5 CFR 1201.116 - Appellant requests for enforcement of interim relief.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... interim relief. 1201.116 Section 1201.116 Administrative Personnel MERIT SYSTEMS PROTECTION BOARD... Appellant requests for enforcement of interim relief. (a) Before a final decision is issued. If the agency files a petition for review or a cross petition for review and has not provided required interim...

  17. 75 FR 24667 - Interim Change to the Military Freight Traffic Unified Rules Publication (MFTURP) No. 1

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-05-05

    ... Department of the Army Interim Change to the Military Freight Traffic Unified Rules Publication (MFTURP) No... Command (SDDC) is providing notice that it released an interim change to the MFTURP No. 1 on April 26, 2010. The interim change adds safety requirements for Motor Carriers authorized to provide...

  18. 75 FR 60436 - Interim Change to the Military Freight Traffic Unified Rules Publication (MFTURP) No. 1

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-09-30

    ... Department of the Army Interim Change to the Military Freight Traffic Unified Rules Publication (MFTURP) No... Command (SDDC) is providing notice that it is releasing an interim change to the MFTURP No. 1 on October 1, 2010. The interim change updates Section B, Item 21, Detention: Vehicles With Power Units...

  19. 75 FR 35510 - License Renewal Interim Staff Guidance Process, Revision 2 Notice of Availability

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-06-22

    ... COMMISSION License Renewal Interim Staff Guidance Process, Revision 2 Notice of Availability AGENCY: Nuclear... license renewal interim staff guidance (LR-ISG) process. This revision is entitled, ``License Renewal Interim Staff Guidance Process, Revision 2'' (revised LR-ISG process). The LR-ISG process describes...

  20. 78 FR 20503 - Energy Conservation Program: Availability of the Interim Technical Support Document for High...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-04-05

    ... CFR Part 431 RIN 1904-AC36 Energy Conservation Program: Availability of the Interim Technical Support... interim technical support document (TSD) for high-intensity discharge (HID) lamps energy conservation... submitting comments on the interim TSD or any other aspect of the rulemaking for HID lamps. The...

  1. 76 FR 540 - National Conference on Weights and Measures 2011 Interim Meeting

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-01-05

    ... National Institute of Standards and Technology National Conference on Weights and Measures 2011 Interim... National Conference on Weights and Measures (NCWM) 2011 Interim Meeting will be held January 23 to 26, 2011... Publication 15 ``Interim Meeting Agenda'' which contains meeting agendas, registration forms and...

  2. 75 FR 15420 - Interim Change to the Military Freight Traffic Unified Rules Publication (MFTURP) NO. 1

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-03-29

    ... Department of the Army Interim Change to the Military Freight Traffic Unified Rules Publication (MFTURP) NO... Command (SDDC) is providing notice that it will release an interim change to the MFTURP No. 1 on March 29, 2010. The interim change updates Section A, Paragraph N, Fuel Surcharge, in accordance with Section...

  3. 76 FR 776 - Interim Change to the Military Freight Traffic Unified Rules Publication (MFTURP) NO. 1

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-01-06

    ... Department of the Army Interim Change to the Military Freight Traffic Unified Rules Publication (MFTURP) NO... Command (SDDC) is providing notice that it is releasing an interim change to the MFTURP No. 1 that will become effective January 1, 2011. The interim change updates the personnel security requirements for...

  4. 75 FR 45678 - Notice of Availability of Interim Staff Guidance Document for Fuel Cycle Facilities

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-08-03

    ... COMMISSION Notice of Availability of Interim Staff Guidance Document for Fuel Cycle Facilities AGENCY... . SUPPLEMENTARY INFORMATION: I. Introduction The Nuclear Regulatory Commission (NRC) prepares and issues Interim... this notice is provided in the following table. ADAMS Interim staff guidance accession No. FCSS...

  5. 26 CFR 1.848-3 - Interim rules for certain reinsurance agreements.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 26 Internal Revenue 8 2010-04-01 2010-04-01 false Interim rules for certain reinsurance agreements... (CONTINUED) INCOME TAX (CONTINUED) INCOME TAXES Other Insurance Companies § 1.848-3 Interim rules for certain... before November 15, 1991. (b) Interim rules. In determining a company's gross amount of premiums...

  6. 10 CFR 205.199G - Extension of time; Interim and Ancillary Orders.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... 10 Energy 3 2010-01-01 2010-01-01 false Extension of time; Interim and Ancillary Orders. 205.199G... Extension of time; Interim and Ancillary Orders. The Director of the Office of Hearings and Appeals or his... initiative issue any interim or ancillary Orders, reconsider any determinations, or make any rulings...

  7. 75 FR 36643 - Interim Change to the Military Freight Traffic Unified Rules Publication (MFTURP) No. 1

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-06-28

    ... Department of the Army Interim Change to the Military Freight Traffic Unified Rules Publication (MFTURP) No... Distribution Command (SDDC) is providing notice that it will release an interim change to the MFTURP No. 1 on Monday, June 28, 2010. The interim change updates Section A, Part VI, Paragraph A, Advancing Charges...

  8. 78 FR 14487 - Tetrachlorvinphos; Proposed Extension of Time-Limited Interim Pesticide Tolerances

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-03-06

    ... AGENCY 40 CFR Part 180 Tetrachlorvinphos; Proposed Extension of Time-Limited Interim Pesticide Tolerances... the extension of the time-limited interim tolerances for the combined residues of the insecticide... related to EPA's extension of the time-limited interim tolerances for the combined residues of...

  9. Minimal subspace rotation on the Stiefel manifold for stabilization and enhancement of projection-based reduced order models for the compressible Navier-Stokes equations

    NASA Astrophysics Data System (ADS)

    Balajewicz, Maciej; Tezaur, Irina; Dowell, Earl

    2016-09-01

    For a projection-based reduced order model (ROM) of a fluid flow to be stable and accurate, the dynamics of the truncated subspace must be taken into account. This paper proposes an approach for stabilizing and enhancing projection-based fluid ROMs in which truncated modes are accounted for a priori via a minimal rotation of the projection subspace. Attention is focused on the full non-linear compressible Navier-Stokes equations in specific volume form as a step toward a more general formulation for problems with generic non-linearities. Unlike traditional approaches, no empirical turbulence modeling terms are required, and consistency between the ROM and the Navier-Stokes equation from which the ROM is derived is maintained. Mathematically, the approach is formulated as a trace minimization problem on the Stiefel manifold. The reproductive as well as predictive capabilities of the method are evaluated on several compressible flow problems, including a problem involving laminar flow over an airfoil with a high angle of attack, and a channel-driven cavity flow problem.

  10. Minimal subspace rotation on the Stiefel manifold for stabilization and enhancement of projection-based reduced order models for the compressible Navier–Stokes equations

    DOE PAGES

    Balajewicz, Maciej; Tezaur, Irina; Dowell, Earl

    2016-05-25

    For a projection-based reduced order model (ROM) of a fluid flow to be stable and accurate, the dynamics of the truncated subspace must be taken into account. This paper proposes an approach for stabilizing and enhancing projection-based fluid ROMs in which truncated modes are accounted for a priori via a minimal rotation of the projection subspace. Attention is focused on the full non-linear compressible Navier–Stokes equations in specific volume form as a step toward a more general formulation for problems with generic non-linearities. Unlike traditional approaches, no empirical turbulence modeling terms are required, and consistency between the ROM and themore » Navier–Stokes equation from which the ROM is derived is maintained. Mathematically, the approach is formulated as a trace minimization problem on the Stiefel manifold. As a result, the reproductive as well as predictive capabilities of the method are evaluated on several compressible flow problems, including a problem involving laminar flow over an airfoil with a high angle of attack, and a channel-driven cavity flow problem.« less

  11. Minimal subspace rotation on the Stiefel manifold for stabilization and enhancement of projection-based reduced order models for the compressible Navier–Stokes equations

    SciTech Connect

    Balajewicz, Maciej; Tezaur, Irina; Dowell, Earl

    2016-05-25

    For a projection-based reduced order model (ROM) of a fluid flow to be stable and accurate, the dynamics of the truncated subspace must be taken into account. This paper proposes an approach for stabilizing and enhancing projection-based fluid ROMs in which truncated modes are accounted for a priori via a minimal rotation of the projection subspace. Attention is focused on the full non-linear compressible Navier–Stokes equations in specific volume form as a step toward a more general formulation for problems with generic non-linearities. Unlike traditional approaches, no empirical turbulence modeling terms are required, and consistency between the ROM and the Navier–Stokes equation from which the ROM is derived is maintained. Mathematically, the approach is formulated as a trace minimization problem on the Stiefel manifold. As a result, the reproductive as well as predictive capabilities of the method are evaluated on several compressible flow problems, including a problem involving laminar flow over an airfoil with a high angle of attack, and a channel-driven cavity flow problem.

  12. NEXT GENERATION MELTER OPTIONEERING STUDY - INTERIM REPORT

    SciTech Connect

    GRAY MF; CALMUS RB; RAMSEY G; LOMAX J; ALLEN H

    2010-10-19

    The next generation melter (NOM) development program includes a down selection process to aid in determining the recommended vitrification technology to implement into the WTP at the first melter change-out which is scheduled for 2025. This optioneering study presents a structured value engineering process to establish and assess evaluation criteria that will be incorporated into the down selection process. This process establishes an evaluation framework that will be used progressively throughout the NGM program, and as such this interim report will be updated on a regular basis. The workshop objectives were achieved. In particular: (1) Consensus was reached with stakeholders and technology providers represented at the workshop regarding the need for a decision making process and the application of the D{sub 2}0 process to NGM option evaluation. (2) A framework was established for applying the decision making process to technology development and evaluation between 2010 and 2013. (3) The criteria for the initial evaluation in 2011 were refined and agreed with stakeholders and technology providers. (4) The technology providers have the guidance required to produce data/information to support the next phase of the evaluation process. In some cases it may be necessary to reflect the data/information requirements and overall approach to the evaluation of technology options against specific criteria within updated Statements of Work for 2010-2011. Access to the WTP engineering data has been identified as being very important for option development and evaluation due to the interface issues for the NGM and surrounding plant. WRPS efforts are ongoing to establish precisely data that is required and how to resolve this Issue. It is intended to apply a similarly structured decision making process to the development and evaluation of LAW NGM options.

  13. A review of proposed Glen Canyon Dam interim operating criteria

    SciTech Connect

    LaGory, K.; Hlohowskyj, I.; Tomasko, D.; Hayse, J.; Durham, L.

    1992-04-01

    Three sets of interim operating criteria for Glen Canyon Dam on the Colorado River have been proposed for the period of November 1991, to the completion of the record of decision for the Glen Canyon Dam environmental impact statement (about 1993). These criteria set specific limits on dam releases, including maximum and minimum flows, up-ramp and down-ramp rates, and maximum daily fluctuation. Under the proposed interim criteria, all of these parameters would be reduced relative to historical operating criteria to protect downstream natural resources, including sediment deposits, threatened and endangered fishes, trout, the aquatic food base, and riparian plant communities. The scientific bases of the three sets of proposed operating criteria are evaluated in the present report:(1) criteria proposed by the Research/Scientific Group, associated with the Glen Canyon Environmental Studies (GCES); (2) criteria proposed state and federal officials charged with managing downstream resources; and (3) test criteria imposed from July 1991, to November 1991. Data from Phase 1 of the GCES and other sources established that the targeted natural resources are affected by dam operations, but the specific interim criteria chosen were not supported by any existing studies. It is unlikely that irreversible changes to any of the resources would occur over the interim period if historical operating criteria remained in place. It is likely that adoption of any of the sets of proposed interim operating criteria would reduce the levels of sediment transport and erosion below Glen Canyon Dam; however, these interim criteria could result in some adverse effects, including the accumulation of debris at tributary mouths, a shift of new high-water-zone vegetation into more flood-prone areas, and further declines in vegetation in the old high water zone.

  14. The Challenge of Declining Enrolments. Critical Emerging Problems and Recommendations for Immediate Action. Interim Report No. 2. [La Baisse des Effectifs Scolaires. Problemes Critiques et Recommandations pour une Action Immediate. Rapport Preliminaire No. 2].

    ERIC Educational Resources Information Center

    Jackson, Robert W. B.

    This second interim report on declining enrollment in Ontario identifies the major implications of the several factors associated with declining enrollments and makes recommendations for immediate action to contribute to the stability of the system while preparing and initiating long-term policies. The first part of the report deals with…

  15. INTERIM BARRIER AT HANFORDS TY FARM TO PROTECT GROUNDWATER AT THE HANFORD SITE WASHINGTON USA

    SciTech Connect

    PARKER DL; HOLM MJ; HENDERSON JC; LOBER RW

    2011-01-13

    An innovative interim surface barrier was constructed as a demonstration project at the Hanford Site's TY Tank Farm. The purpose of the demonstration barrier is to stop rainwater and snowmelt from entering the soils within the tank farm and driving contamination from past leaks and spills toward the ground water. The interim barrier was constructed using a modified asphalt material with very low permeability developed by MatCon{reg_sign}. Approximately 2,400 cubic yards of fill material were added to the tank farm to create a sloped surface that will gravity drain precipitation to collection points where it will be routed through buried drain lines to an evapotranspiration basin adjacent to the farm. The evapotranspiration basin is a lined basin with a network of perforated drain lines covered with soil and planted with native grasses. The evapotranspiration concept was selected because it prevents the runoff from percolating into the soil column and also avoids potential monitoring and maintenance issues associated with standing water in a traditional evaporation pond. Because of issues associated with using standard excavation and earth moving equipment in the farm a number of alternate construction approaches were utilized to perform excavations and prepare the site for the modified asphalt.

  16. T Tank Farm Interim Surface Barrier Demonstration - Vadose Zone Monitoring FY08 Report

    SciTech Connect

    Zhang, Z. F.; Strickland, Christopher E.; Field, Jim G.; Parker, Danny L.

    2009-02-01

    DOE’s Office of River Protection constructed a temporary surface barrier over a portion of the T Tank Farm as part of the T Farm Interim Surface Barrier Demonstration Project. The surface barrier is designed to minimize the infiltration of precipitation into the contaminated soil zone created by the Tank T-106 leak and minimize movement of the contamination. As part of the demonstration effort, vadose zone moisture is being monitored to assess the effectiveness of the barrier at reducing soil moisture. A solar-powered system was installed to continuously monitor soil water conditions at four locations (i.e., instrument Nests A, B, C, and D) beneath the barrier and outside the barrier footprint as well as site meteorological conditions. Nest A is placed in the area outside the barrier footprint and serves as a control, providing subsurface conditions outside the influence of the surface barrier. Nest B provides subsurface measurements to assess surface-barrier edge effects. Nests C and D are used to assess changes in soil-moisture conditions beneath the interim surface barrier.

  17. COMPLETION OF THE FIRST INTEGRATED SPENT NUCLEAR FUEL TRANSSHIPMENT/INTERIM STORAGE FACILITY IN NW RUSSIA

    SciTech Connect

    Dyer, R.S.; Barnes, E.; Snipes, R.L.; Hoeibraaten, S.; Gran, H.C.; Foshaug, E.; Godunov, V.

    2003-02-27

    Northwest and Far East Russia contain large quantities of unsecured spent nuclear fuel (SNF) from decommissioned submarines that potentially threaten the fragile environments of the surrounding Arctic and North Pacific regions. The majority of the SNF from the Russian Navy, including that from decommissioned nuclear submarines, is currently stored in on-shore and floating storage facilities. Some of the SNF is damaged and stored in an unstable condition. Existing Russian transport infrastructure and reprocessing facilities cannot meet the requirements for moving and reprocessing this amount of fuel. Additional interim storage capacity is required. Most of the existing storage facilities being used in Northwest Russia do not meet health and safety, and physical security requirements. The United States and Norway are currently providing assistance to the Russian Federation (RF) in developing systems for managing these wastes. If these wastes are not properly managed, they could release significant concentrations of radioactivity to these sensitive environments and could become serious global environmental and physical security issues. There are currently three closely-linked trilateral cooperative projects: development of a prototype dual-purpose transport and storage cask for SNF, a cask transshipment interim storage facility, and a fuel drying and cask de-watering system. The prototype cask has been fabricated, successfully tested, and certified. Serial production is now underway in Russia. In addition, the U.S. and Russia are working together to improve the management strategy for nuclear submarine reactor compartments after SNF removal.

  18. Progress of excimer laser development in the AMMTRA project

    NASA Astrophysics Data System (ADS)

    Nagai, Haruhiko

    1993-05-01

    Since 1986, five kinds of excimer laser technologies have been studied by five companies as part of the large-scale project `Advanced Material-Processing and Machining System,' which is one of the national R&D projects in Japan. The five kinds of excimer lasers being developed are as follows: (1) high power XeCl laser with an average power of 2 kW, (2) high repetition rate XeCl laser with a repetition rate of 5 kHz, (3) automatically power-stabilized 400 W average power XeCl laser with a stability of +/- 1% or less, (4) long-life ArF laser with a gas life of 109 shots or more, and (5) high beam-quality ArF laser with an average power of 200 W. The project passed an interim evaluation at the end of fiscal 1990, and is now ongoing toward the achievement of final targets as of the end of fiscal 1993. The present status and future prospect of the technologies are reviewed.

  19. Office of Educational Leadership Interim Legislative Report.

    ERIC Educational Resources Information Center

    Minnesota State Dept. of Education, St. Paul. Office of Educational Leadership.

    In 1989, the Minnesota Office of Educational Leadership (OEL) was directed to develop a plan for a 2-year research project to determine the effectiveness of a learner outcome-based system of education in improving pupil learning. Ten research and development project sites comprising 17 districts and 5 educational consortia received grants of…

  20. Flexible stopping boundaries when changing primary endpoints after unblinded interim analyses.

    PubMed

    Chen, Liddy M; Ibrahim, Joseph G; Chu, Haitao

    2014-01-01

    It has been widely recognized that interim analyses of accumulating data in a clinical trial can inflate type I error. Different methods, from group sequential boundaries to flexible alpha spending functions, have been developed to control the overall type I error at prespecified level. These methods mainly apply to testing the same endpoint in multiple interim analyses. In this article, we consider a group sequential design with preplanned endpoint switching after unblinded interim analyses. We extend the alpha spending function method to group sequential stopping boundaries when the parameters can be different between interim, or between interim and final analyses.

  1. Using Mechanistic Understanding of Streambank Processes and a Deterministic Bank-Stability Model to Design and Evaluate a Reach-Scale Restoration Project

    NASA Astrophysics Data System (ADS)

    Simon, Andrew; Derrick, David; Bankhead, Natasha

    2010-05-01

    Sediment is one of the leading contributors to water-quality impairment in the United States and streambank erosion has been found to be the dominant source of sediment in many disturbed watersheds. Goodwin Creek is a typical incised channel in northeastern Mississippi, USA (4.7 m-deep) that yields about an order of magnitude more suspended sediment than stable, "reference" streams in the region. Periodic channel surveys with dating of woody vegetation in an actively eroding meander disclosed a migration rate of 0.5 m/y. Because of continued land loss by mass failure of the streambanks, a restoration project was designed to stabilize the banks. Bank retreat occurs by interactions between hydraulic forces acting at the bed and bank toe and gravitational forces acting on in situ bank material. In fact, bank-toe protection which inhibits steepening of the bank, has been found to be one of the most effective means of stabilizing the upper part of the bank. To provide a stable alternative, analysis of the restored configuration needed to mechanistically address both hydraulic erosion and geotechnical stability. This was accomplished using the Bank-Stability and Toe-Erosion Model (BSTEM). The proposed design was limited to 1:1 bank slopes due to the proximity of a road and included longitudinal stone-toe protection and bendway weirs to counter basal erosion by hydraulic shear. Worst-case conditions under the proposed design were simulated by modeling (1) typical, annual high flows (3 m-deep) to evaluate the amount of bank-toe erosion that would occur, and (2) geotechnical stability where groundwater levels were high and flow had receded to low-flow conditions in the channel (drawdown case). Stone size was selected based on a 1-D hydraulic analysis such that the stone would not be mobilized at peak flows where average boundary shear stresses can reach 60 - 80 N/m2. Calculations were made for a 3 m-deep flow at slopes between 0.002 and 0.003, resulting in recommended stone

  2. Interim Measure/Interim Action Post-Construction Report (PCR) for the Old Radioactive Waste Burial Ground (643-E)

    SciTech Connect

    Bennett, J.

    2002-06-18

    The Burial Ground Complex (BGC) occupies approximately 194 acres in the central part of Savannah River Site (SRS) in E-Area between the F and H Separations Areas. The BGC is divided into a northern area containing approximately 118 acres and a southern area containing approximately 76 acres. The southern area is the Old Radioactive Waste Burial Ground (ORWBG), 643-E, which consists of an earthen trench disposal area that began receiving waste in 1952 and was filled in 1972. This portion of the BGC is addressed by this interim measure/interim action.

  3. Integrated Application of Active Controls (IAAC) technology to an advanced subsonic transport project-longitudinal handling qualities study of a relaxed-stability airplane

    NASA Technical Reports Server (NTRS)

    1983-01-01

    The results of a piloted simulation of longitudinal handling qualities of an airplane with relaxed static stability are described. This task was performed under the Integrated Application of Active Controls (IAAC) Technology Project within the NASA Energy Efficient Transport Program. A representative medium range transport airplane, the Boeing Model 757, was simulated. Evaluations were made of the unaugmented airplane and of the airplane with an Essential Pitch Augmented Stability (PAS) System and with a Primary PAS System at various center of gravity (cg) conditions. Level 2 pilot ratings were attained with cg locations aft to about 57% mean aerodynamic chord (MAC) or 6% aft of the neutral point for unaugmented landing approach. For Mach = 0.80, unaugmented cruise Level 2 ratings were attained to 47% MAC or 5% forward of the maneuver point. The augmented airplane model provided handling qualities close to or within the Level 1 boundary at all cg locations for both Essential and Primary PAS. Analyses of the test conditions when compared with existing handling qualities criteria based on classical unaugmented airplane characteristics agreed well with the pilot ratings. The unaugmented results are comparable to those reported by both the Douglas Aircraft Company and Lockheed California Company from simulation investigations of transport configurations with roughly similar dimensional and mass characteristics.

  4. Radioactive Air Emission Notice of Construction for (NOC) Plutonium Finishing Plant (PFP) Project W-460 Plutonium Stabilization and Handling

    SciTech Connect

    JANSKY, M.T.

    2000-03-01

    The following description and any attachments and references are provided to the Washington State Department of Health (WDOH), Division of Radiation Protection, Air Emissions & Defense Waste Section as a notice of construction (NOC) in accordance with Washington Administrative Code (WAC) 246-247, Radiation Protection-Air Emissions. The WAC 246-247-060, ''Applications, registration, and licensing'', states ''This section describes the information requirements for approval to construct, modify, and operate an emission unit. Any NOC requires the submittal of information listed in Appendix A,'' Appendix A (WAC 246-247-1 IO) lists the requirements that must be addressed. Additionally, the following description, attachments, and references are provided to the U.S. Environmental Protection Agency (EPA) as an NOC, in accordance with Title 40 Code of Federal Regulations (CFR), Part 61, ''National Emission Standards for Hazardous Air Pollutants.'' The information required for submittal to the EPA is specified in 40 CFR 61.07. The potential emissions from this activity are estimated to provide greater than 0.1 millirem year total effective dose equivalent (TEDE) to the hypothetical offsite maximally exposed individual (MEI) and commencement is needed within a short time. Therefore, this application also is intended to provide notification of the anticipated date of initial startup in accordance with the requirement listed in 40 CFR 61.09(a)(1), and it is requested that approval of this application also constitutes EPA acceptance of this initial startup notification. Written notification of the actual date of initial startup, in accordance with the requirement listed in 40 CFR 61.09(a)(2), will be provided later. This NOC covers the activities associated with the construction and operation activities involving stabilization and/or repackaging of plutonium in the 2736-ZB Building. An operations support trailer will be installed in the proximity of the 2736-ZB Building. A new

  5. Radioactive Air Emission Notice of Construction (NOC) for Plutonium Finishing Plant (PFP) Project W-460 Plutonium Stabilization and Handling

    SciTech Connect

    JANSKY, M.T.

    2000-05-01

    The following description and any attachments and references are provided to the Washington State Department of Health (WDOH), Division of Radiation Protection, Air Emissions & Defense Waste Section as a notice of construction (NOC) in accordance with Washington Administrative Code (WAC) 246-247, Radiation Protection-Air Emissions. The WAC 246-247-060, ''Applications, registration, and licensing'', states ''This section describes the information requirements for approval to construct, modify, and operate an emission unit. Any NOC requires the submittal of information listed in Appendix A.'' Additionally, the following description, attachments, and references are provided to the US Environmental Protection Agency (EPA) as an NOC, in accordance with Title 40 Code of Federal Regulations (CFR), Part 61, ''National Emission Standards for Hazardous Air Pollutants''. The information required for submittal to the EPA is specified in 40 CFR 61.07. The potential emissions from this activity are estimated to provide greater than 0.1 millirem year total effective dose equivalent (TEDE) to the hypothetical offsite maximally exposed individual (MEI) and commencement is needed within a short time. Therefore, this application also is intended to provide notification of the anticipated date of initial startup in accordance with the requirement listed in 40 CFR 61.09(a)(1), and it is requested that approval of this application also constitutes EPA acceptance of this initial startup notification. Written notification of the actual date of initial startup, in accordance with the requirement listed in 40 CFR 61.09(a)(2), will be provided later. This NOC covers the activities associated with the construction and operation activities involving stabilization and/or repackaging of plutonium in the 2736-ZB Building. A new exhaust stack will be built and operated at the 2736-ZB Building to handle the effluents associated with the operation of the stabilization and repackaging process

  6. Hyaloclastites and the slope stability of Hawaiian volcanoes: Insights from the Hawaiian Scientific Drilling Project's 3-km drill core

    NASA Astrophysics Data System (ADS)

    Schiffman, Peter; Watters, Robert J.; Thompson, Nick; Walton, Anthony W.

    2006-03-01

    Core samples recovered during the Hawaiian Scientific Drilling Project (HSDP) drilling project reveal that the upper 1 km of the submarine flank of Mauna Kea is comprised mainly of hyaloclastites. Progressive, very low-temperature alteration of these hyaloclastites has been accompanied by systematic transformations in physical properties of these deposits. Hyaloclastite deposits which directly underlie ca. 1 km of subaerially-emplaced lavas are very poorly consolidated. But over a depth interval of ca. 500 m, compaction and, especially, precipitation of zeolitic, pore-filling cements associated with palagonitization of sideromelane, have eliminated porosity as well as promoted the consolidation of these hyaloclastites. The latter is reflected in unconfined compressive strengths which increase from mean values, respectively, of 2.5 and 4.6 MPa in weakly consolidated, smectite-rich hyaloclastites from the incipient (1080 to 1335 mbsl) and smectitic (1405-1573 mbsl) alteration zones, to a mean value of 10.0 MPa in the more highly consolidated hyaloclastites of the palagonitic zone of alteration (from 1573 mbsl to the bottom of the drill hole). Conversely, overlying, intercalated, and underlying lava flows are generally much less altered, and have mean compressive strengths which are 1 to 2 orders of magnitude greater then hyaloclastites at equivalent depths. The shear strengths of the hyaloclastites also increase with depth and grade of alteration, but are uniformly and substantially lower in the lavas. Those hyaloclastites exhibiting the highest grade of alteration (i.e., palagonitic) also exhibit the highest measured strengths, and thus the alteration of hyaloclastites appears to strengthen as opposed to weaken the flanks of the edifice. However, the contrast in strength between hyaloclastites and lavas may be a primary factor in localizing destabilization, and the zones of weak and poorly consolidated hyaloclastites may facilitate slumping by servings as hosts for

  7. 45 CFR 689.8 - Interim administrative actions.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ....8 Public Welfare Regulations Relating to Public Welfare (Continued) NATIONAL SCIENCE FOUNDATION RESEARCH MISCONDUCT § 689.8 Interim administrative actions. (a) After an inquiry or during an external or... taken to protect Federal resources or to guard against continuation of any suspected or alleged...

  8. President's Information Technology Advisory Committee Interim Report to the President.

    ERIC Educational Resources Information Center

    National Coordination Office for Information Technology Research and Development, Arlington, VA.

    This document is the Interim Report on future directions for Federal support of research and development in high performance computing, communications, information technology, and the Next Generation Internet. This report provides a more detailed explanation of the findings and recommendations summarized by the President's Information Technology…

  9. Engineering Standards. U.S. Metric Study Interim Report.

    ERIC Educational Resources Information Center

    National Bureau of Standards (DOC), Washington, DC.

    This report is the 11th in a series of interim reports stemming from the U.S. Metric Study, which is being conducted by the National Bureau of Standards in accordance with the Metric Study Act of 1968 (Public Law 90-472). Although it mainly concerns the relationships of measurement units to engineering standards, the issue of international…

  10. Study of the Voluntary Public School Choice Program. Interim Report

    ERIC Educational Resources Information Center

    Yin, Robert K.; Ahonen, Pirkko; Kim, Dawn

    2007-01-01

    The purpose of the Voluntary Public School Choice (VPSC) Program is to assist states and local school districts in the development of innovative strategies to expand options for students, and to encourage transfers of students from low-performing to higher-performing schools. This report presents interim findings from the National Evaluation of…

  11. Performance Criteria for the Luminous Environment. Interim Report.

    ERIC Educational Resources Information Center

    State Univ. Construction Fund, Albany, NY.

    This interim report informs the eventual user of the direction of the long-term program; specific criteria are not provided. Five current guidelines in lighting practice were disavowed as follows--(1) that low levels of illumination cause organic harm to the eyes, (2) that the footcandle is the best criterion for determining the proper…

  12. 42 CFR 417.570 - Interim per capita payments.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... rate; (2) A material variation from the costs estimated when the annual operating budget was prepared... PREPAYMENT PLANS Medicare Payment: Cost Basis § 417.570 Interim per capita payments. (a) Principle of payment... adjust the total amounts paid during the contract period to the level of incurred costs....

  13. System architecture for the Canadian interim mobile satellite system

    NASA Technical Reports Server (NTRS)

    Shariatmadar, M.; Gordon, K.; Skerry, B.; Eldamhougy, H.; Bossler, D.

    1988-01-01

    The system architecture for the Canadian Interim Mobile Satellite Service (IMSS) which is planned for commencement of commercial service in late 1989 is reviewed. The results of an associated field trial program which was carried out to determine the limits of coverage and the preliminary performance characteristics of the system are discussed.

  14. Building an Interim Assessment System: A Workbook for School Districts

    ERIC Educational Resources Information Center

    Crane, Eric W.

    2010-01-01

    As someone with a stake in a school district's systems, a person probably does not have all the answers around what is necessary to build an effective interim assessment system. Neither does this workbook. But it is intended to have the right questions. More precisely, this workbook contains the vision, infrastructure, and resource questions…

  15. 20 CFR 416.1910 - Requirements for interim assistance agreement.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... part on payment of benefits if the State cannot pay it to you (for example, you die or you move and the... effect between us and the State if we are to repay the State for interim assistance. The following requirements must be part of the agreement: (a) SSA to repay the State. We must agree to repay the State...

  16. 20 CFR 416.1910 - Requirements for interim assistance agreement.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... part on payment of benefits if the State cannot pay it to you (for example, you die or you move and the... effect between us and the State if we are to repay the State for interim assistance. The following requirements must be part of the agreement: (a) SSA to repay the State. We must agree to repay the State...

  17. 20 CFR 416.1910 - Requirements for interim assistance agreement.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... part on payment of benefits if the State cannot pay it to you (for example, you die or you move and the... effect between us and the State if we are to repay the State for interim assistance. The following requirements must be part of the agreement: (a) SSA to repay the State. We must agree to repay the State...

  18. 20 CFR 416.1910 - Requirements for interim assistance agreement.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... part on payment of benefits if the State cannot pay it to you (for example, you die or you move and the... effect between us and the State if we are to repay the State for interim assistance. The following requirements must be part of the agreement: (a) SSA to repay the State. We must agree to repay the State...

  19. 20 CFR 416.1910 - Requirements for interim assistance agreement.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... part on payment of benefits if the State cannot pay it to you (for example, you die or you move and the... effect between us and the State if we are to repay the State for interim assistance. The following requirements must be part of the agreement: (a) SSA to repay the State. We must agree to repay the State...

  20. 49 CFR 37.193 - Interim service requirements.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... WITH DISABILITIES (ADA) Over-the-Road Buses (OTRBs) § 37.193 Interim service requirements. Link to an... disability wishes to travel is already provided by an accessible bus, the operator has met this requirement... accessible buses (e.g., a small fixed-route operator who exclusively or primarily purchases or leases...

  1. Nonmanufacturing Businesses. U.S. Metric Study Interim Report.

    ERIC Educational Resources Information Center

    Cornog, June R.; Bunten, Elaine D.

    In this fifth interim report on the feasibility of a United States changeover to a metric system stems from the U.S. Metric Study, a primary stratified sample of 2,828 nonmanufacturing firms was randomly selected from 28,184 businesses taken from Social Security files, a secondary sample of 2,258 firms was randomly selected for replacement…

  2. 42 CFR 417.808 - Interim per capita payments.

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 42 Public Health 3 2011-10-01 2011-10-01 false Interim per capita payments. 417.808 Section 417.808 Public Health CENTERS FOR MEDICARE & MEDICAID SERVICES, DEPARTMENT OF HEALTH AND HUMAN SERVICES (CONTINUED) MEDICARE PROGRAM HEALTH MAINTENANCE ORGANIZATIONS, COMPETITIVE MEDICAL PLANS, AND HEALTH...

  3. 42 CFR 417.808 - Interim per capita payments.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 42 Public Health 3 2010-10-01 2010-10-01 false Interim per capita payments. 417.808 Section 417.808 Public Health CENTERS FOR MEDICARE & MEDICAID SERVICES, DEPARTMENT OF HEALTH AND HUMAN SERVICES (CONTINUED) MEDICARE PROGRAM HEALTH MAINTENANCE ORGANIZATIONS, COMPETITIVE MEDICAL PLANS, AND HEALTH...

  4. Interim Evaluation of the National Literacy Program. Final Report

    ERIC Educational Resources Information Center

    Human Resources and Social Development Canada, 2007

    2007-01-01

    The evaluation examined issues related to: (1) Rationale and Relevance; (2) Implementation; and (3) Success. In addition, the interim evaluation was intended to: (1) Determine whether sufficient data was being collected to inform the summative evaluation and identify opportunities for improvement to fill any potential gaps; (2) Assess whether the…

  5. 14 CFR 136.41 - Interim operating authority.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... AND NATIONAL PARKS AIR TOUR MANAGEMENT National Parks Air Tour Management § 136.41 Interim operating... over a national park or tribal land for which the operator is an existing commercial air tour operator... tribal lands; (6) Shall promote protection of national park resources, visitor experiences, and...

  6. Public School Finance Problems in Texas. An Interim Report.

    ERIC Educational Resources Information Center

    Texas Research League, Austin.

    The U.S. District Court ruling in Rodriguez vs San Antonio Independent School District, which struck down Texas' school finance system as inequitable and unconstitutional, provided the impetus for publishing this interim report. The report documents the growing cost of State-supported public school programs--the primary concern prior to the…

  7. Interim Sanitary Landfill Groundwater Monitoring Report (1998 Annual Report)

    SciTech Connect

    Wells, D.

    1999-03-18

    The SRS Interim Sanitary Landfill opened in Mid-1992 and operated until 1998 under Domestic Waste Permit No. 025500-1120. Several contaminants have been detected in the groundwater beneath the unit.The well sampling and analyses were conducted in accordance with Procedure 3Q5, Hydrogeologic Data Collection.

  8. 17 CFR 210.8-03 - Interim financial statements.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... presented in the annual financial statements that exceeds 20% of sales or gross revenues, provision for... accounting principles or practices. (Financial institutions should substitute net interest income for sales... 17 Commodity and Securities Exchanges 2 2010-04-01 2010-04-01 false Interim financial...

  9. Penalty Inflation Adjustments for Civil Money Penalties. Interim Final Rule.

    PubMed

    2016-06-27

    In accordance with the Federal Civil Penalties Inflation Adjustment Act of 1990, as amended by the Debt Collection Improvement Act of 1996, and further amended by the Bipartisan Budget Act of 2015, section 701: Federal Civil Penalties Inflation Adjustment Act Improvements Act of 2015, this interim final rule incorporates the penalty inflation adjustments for the civil money penalties contained in the Social Security Act

  10. "Intelligent" Computer Assisted Instruction (CAI) Applications. Interim Report.

    ERIC Educational Resources Information Center

    Brown, John Seely; And Others

    Interim work is documented describing efforts to modify computer techniques used to recognize and process English language requests to an instructional simulator. The conversion from a hand-coded to a table driven technique are described in detail. Other modifications to a simulation based computer assisted instruction program to allow a gaming…

  11. Ocotillo: Improving Learning through Instruction. Interim Report, 1988-89.

    ERIC Educational Resources Information Center

    Jacobs, Alan, Ed.; Walters, Jim, Ed.

    As a result of a Technology Retreat sponsored by the Maricopa Community Colleges (Arizona) in 1988, action/research groups were formed to explore the various challenges of implementing instructional technology effectively. This interim report reviews the work of the groups, with a summary report from each, as follows: (1) "Alternative Funding…

  12. Making the Most of Interim Assessment Data. Lessons from Philadelphia

    ERIC Educational Resources Information Center

    Christman, Jolley Bruce; Neild, Ruth Curran; Bulkley, Katrina; Blanc, Suzanne; Liu, Roseann; Mitchell, Cecily; Travers, Eva

    2009-01-01

    Under No Child Left Behind, urban school districts have increasingly turned to interim assessments, administered at regular intervals, to help gauge student progress in advance of annual state exams. These assessments have spawned growing debate among educators, assessment experts, and the testing industry: are they worth the significant…

  13. Marine Biochemistry: A New Interdisciplinary Course for the Interim

    ERIC Educational Resources Information Center

    Goldberg, Arthur S.

    1976-01-01

    Discusses an undergraduate course which includes lectures, laboratory, and field trips and is designed for the interim winter semester. The course is interdisciplinary, involving a study of the biochemistry, pharmacology, and physiological significance of compounds from marine flora and fauna. (MLH)

  14. 42 CFR 418.307 - Periodic interim payments.

    Code of Federal Regulations, 2013 CFR

    2013-10-01

    ... (CONTINUED) MEDICARE PROGRAM (CONTINUED) HOSPICE CARE Payment for Hospice Care § 418.307 Periodic interim payments. Subject to the provisions of § 413.64(h) of this chapter, a hospice may elect to receive periodic... under the PIP method unless the hospice requests a longer fixed interval (not to exceed one...

  15. 42 CFR 418.307 - Periodic interim payments.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... (CONTINUED) MEDICARE PROGRAM (CONTINUED) HOSPICE CARE Payment for Hospice Care § 418.307 Periodic interim payments. Subject to the provisions of § 413.64(h) of this chapter, a hospice may elect to receive periodic... under the PIP method unless the hospice requests a longer fixed interval (not to exceed one...

  16. 42 CFR 418.307 - Periodic interim payments.

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... (CONTINUED) MEDICARE PROGRAM (CONTINUED) HOSPICE CARE Payment for Hospice Care § 418.307 Periodic interim payments. Subject to the provisions of § 413.64(h) of this chapter, a hospice may elect to receive periodic... under the PIP method unless the hospice requests a longer fixed interval (not to exceed one...

  17. 17 CFR 210.10-01 - Interim financial statements.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... regulation may be omitted. (2) Interim balance sheets shall include only major captions (i.e., numbered... face of the balance sheet or in the notes to the financial statements, if applicable. Where any major balance sheet caption is less than 10% of total assets, and the amount in the caption has not increased...

  18. Engineering and Design: Stability Criteria for Existing Concrete Navigation Structures on Rock Foundations

    DTIC Science & Technology

    2007-11-02

    Engineering and Design STABILITY CRITERIA FOR EXISTING CONCRETE NAVIGATION STRUCTURES ON ROCK FOUNDATIONS Distribution Restriction Statement Approved...Title and Subtitle Engineering and Design: Stability Criteria for Existing Concrete Navigation Structures on Rock Foundations Contract Number Grant... CONCRETE NAVIGATION STRUCTURES ON ROCK FOUNDATIONS 1. Purpose. The purpose of this letter is to provide interim criteria and procedures for analyzing

  19. Postconstruction report for the mercury tanks interim action at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    SciTech Connect

    Voskuil, T.L.

    1993-09-01

    Three underground concrete settling tanks (tanks 2101-U, 2104-U, and 2100-U) at the Y-12 Plant on the Oak Ridge Reservation in Oak Ridge, Tennessee, contained contaminated sludges contributing mercury to the Upper East Fork Poplar Creek (UEFPC). These tanks were cleaned out as an interim action under the Comprehensive Environmental Response, Compensation, and Liability Act as part of the Reduction of Mercury in Plant Effluent subproject. Cleaning out these tanks prevented the sludge that had settled in the bottom from resuspending and carrying mercury into UEFPC. Tanks 2104-U and 2100-U were returned to service and will continue to receive effluent from buildings 9201-4 and 9201-5. Tank 2101-U had been abandoned and its effluent redirected to Tank 2100-U during previous activities. This interim action permanently sealed Tank 2101-U from the storm sewer system. Upon removal of materials and completion of cleanup, inspections determined that the project`s cleanup criteria had been met. The structural integrity of the tanks was also inspected, and minor cracks identified in tanks 2101-U and 2104-U were repaired. This project is considered to have been completed successfully because it met its performance objectives as addressed in the Interim Record of Decision and the work plan: to remove the waste from the three storage tanks; to ensure that the tanks were cleaned to the levels specified; to return tanks 2100-U and 2104-U to service; to isolate Tank 2101-U permanently; and to manage the wastes in an appropriate fashion.

  20. Interim report on updated microarray probes for the LLNL Burkholderia pseudomallei SNP array

    SciTech Connect

    Gardner, S; Jaing, C

    2012-03-27

    The overall goal of this project is to forensically characterize 100 unknown Burkholderia isolates in the US-Australia collaboration. We will identify genome-wide single nucleotide polymorphisms (SNPs) from B. pseudomallei and near neighbor species including B. mallei, B. thailandensis and B. oklahomensis. We will design microarray probes to detect these SNP markers and analyze 100 Burkholderia genomic DNAs extracted from environmental, clinical and near neighbor isolates from Australian collaborators on the Burkholderia SNP microarray. We will analyze the microarray genotyping results to characterize the genetic diversity of these new isolates and triage the samples for whole genome sequencing. In this interim report, we described the SNP analysis and the microarray probe design for the Burkholderia SNP microarray.

  1. Final decision document for other contamination sources, interim response action, shell section 36 trenches, RMA

    SciTech Connect

    1990-04-01

    The shell section 36 trenches were used from 1952 to 1966 for land disposal of liquid and solid wastes generated from pesticide manufacture. They have been shown to be a source of soil and ground water contamination for volatile and semivolatile compounds. A dense non-aqueous phase liquid (DNAPL) is also believed to have originated from the area. The objective of the interim response action is to reduce the lateral migration of contaminants emanating from the trenches. The preferred IRA alternative consists of (1) A physical barrier encircling the trenches and (2) a soil and vegetative cover to eliminate recharge. This final decision document provides summaries of: (1). Alternatives considered (2). Significant events leading to the initiation of the IRA (3). The IRA project (4). Applicable or relevant and appropriate requirements, standards.

  2. Interim radiological safety standards and evaluation procedures for subseabed high-level waste disposal

    SciTech Connect

    Klett, R.D.

    1997-06-01

    The Seabed Disposal Project (SDP) was evaluating the technical feasibility of high-level nuclear waste disposal in deep ocean sediments. Working standards were needed for risk assessments, evaluation of alternative designs, sensitivity studies, and conceptual design guidelines. This report completes a three part program to develop radiological standards for the feasibility phase of the SDP. The characteristics of subseabed disposal and how they affect the selection of standards are discussed. General radiological protection standards are reviewed, along with some new methods, and a systematic approach to developing standards is presented. The selected interim radiological standards for the SDP and the reasons for their selection are given. These standards have no legal or regulatory status and will be replaced or modified by regulatory agencies if subseabed disposal is implemented. 56 refs., 29 figs., 15 tabs.

  3. Energy conservation potential of the US Department of Energy interim commercial building standards

    SciTech Connect

    Hadley, D.L.; Halverson, M.A.

    1993-12-01

    This report describes a project conducted to demonstrate the whole-building energy conservation potential achievable from full implementation of the US Department of Energy (DOE) Interim Energy Conservation Performance Standards for New Commercial and Multi-Family High Rise Residential Buildings. DOE`s development and implementation of energy performance standards for commercial buildings were established by the Energy Conservation Standards for New Buildings Act of 1976, as amended, Public Law (PL) 94-385, 42 USC 6831 et seq., hereinafter referred to as the Act. In accordance with the Act, DOE was to establish performance standards for both federal and private sector buildings ``to achieve the maximum practicable improvements in energy efficiency and use of non-depletable resources for all new buildings``.

  4. Mobile Launch Platform Vehicle Assembly Area (SWMU 056) Biosparge Expansion Interim Measures Work Plan

    NASA Technical Reports Server (NTRS)

    Burcham, Michael S.; Daprato, Rebecca C.

    2016-01-01

    This document presents the design details for an Interim Measure (IM) Work Plan (IMWP) for the Mobile Launch Platform/Vehicle Assembly Building (MLPV) Area, located at the John F. Kennedy Space Center (KSC), Florida. The MLPV Area has been designated Solid Waste Management Unit Number 056 (SWMU 056) under KSC's Resource Conservation and Recovery Act (RCRA) Corrective Action Program. This report was prepared by Geosyntec Consultants (Geosyntec) for the National Aeronautics and Space Administration (NASA) under contract number NNK09CA02B and NNK12CA13B, project control number ENV1642. The Advanced Data Package (ADP) presentation covering the elements of this IMWP report received KSC Remediation Team (KSCRT) approval at the December 2015 Team Meeting; the meeting minutes are included in Appendix A.

  5. Final decision document for the interim response action at the lime settling basins, Rocky Mountain Arsenal, version 4.0

    SciTech Connect

    1990-03-01

    The objective of the interim response action at the lime settling basins is to mitigate the threat of releases from the basins. The proposed IRA consists of: (1) relocation of sludge material to the settling basin; (2) construction of a 360 degree subsurface barrier around the basins; (3) construction of a soil and vegetative cover over the material; and (4) installation of a ground water extraction system. This decision document provides summaries of: (1) alternative technologies considered, (2) significant events leading to the initiation of the IRA, (3) the IRA Project, and (4) applicable or relevant and appropriate requirements, standards, criteria, and limitations (ARAR`s) associated with the program.

  6. Analysis of the Cordex evaluation runs (ERA_Interim) over Southern Africa

    NASA Astrophysics Data System (ADS)

    Lennard, Chris; Kalognoumou, Liana

    2013-04-01

    The CORDEX program was instituted by the World Climate Research Program (WCRP) to develop downscaled regional climate change projections at user-relevant scales for all terrestrial regions of the world. Africa was identified as the priority domain in urgent need of attention. In light of this the Cordex-Africa Analysis campaign was initiated as a co-ordinated effort to analyse the available Era-Interim downscalings. Three regional African groups were formed (West Africa, East Africa and Southern Africa) and experts from each region tasked with the assessment of the available downscaled data. Within Africa, CORDEX has come to be viewed by many in the decision making community as the leading source of new climate change information, and expectations are high. This paper presents the analysis performed by the southern African team in which the ability of ten regional climate models (RCMs) to simulate precipitation over southern Africa within the Cordex framework was evaluated. An ensemble of ten regional climate simulations and the ensemble average is analysed to evaluate the model's ability to reproduce seasonal and interannual rainfall characteristics over regions of the sub-continent. All the RCMs use the Cordex African domain, have a spatial resolution of ~50km and are driven by the ERA-Interim reanalysis (1989- 2008). Results are compared against a number of observational datasets such as the GPCC, CRU, UDEL, TRMM etc. The spatial and temporal nature of rainfall over the Southern African region is captured by all RCMs, however, individual models exhibit wet or dry biases over particular regions of the domain. Models generally produce lower seasonal variability of precipitation compared to observations and the magnitude of the variability varies in space and time. Model biases are related to the positioning of the ITCZ as well as moisture transport. The multi-model ensemble mean generally out-performs individual models, with bias magnitudes similar to differences

  7. Verification of the new ECMWF ERA-Interim reanalysis over France

    NASA Astrophysics Data System (ADS)

    Szczypta, C.; Calvet, J.-C.; Albergel, C.; Balsamo, G.; Boussetta, S.; Carrer, D.; Lafont, S.; Meurey, C.

    2011-02-01

    An evaluation of the global ECMWF atmospheric reanalysis ERA-Interim (with a 0.5° grid) is performed over France, based on the high resolution (8 km) SAFRAN atmospheric reanalysis. The ERA-Interim precipitation, Incoming Solar Radiation (ISR), air temperature, air humidity, and wind speed, are compared with their SAFRAN counterparts. Also, interpolated in situ ISR observations are used in order to consolidate the evaluation of this variable. The daily precipitation estimates produced by ERA-Interim over France correlate very well with SAFRAN. However, the values are underestimated by 27%. A GPCP-corrected version of ERA-Interim is less biased (13%). The ERA-Interim estimates of ISR correlate very well with SAFRAN and with in situ observations on a daily basis. Whereas SAFRAN underestimates the ISR by 6 Wm-2, ERA-Interim overestimates the ISR by 10 Wm-2. In order to assess the impact of the ERA-Interim errors, simulations of the ISBA-A-gs land surface model are performed over the SMOSREX grassland site in southwestern France using ERA-Interim (with and without GPCP rescaling) and SAFRAN. Latent and sensible heat fluxes are simulated, together with carbon dioxide fluxes. The rescaled ERA-Interim performs better than the original ERA-Interim and permits to achieve flux scores similar to those obtained with SAFRAN.

  8. Verification of the new ECMWF ERA-Interim reanalysis over France

    NASA Astrophysics Data System (ADS)

    Szczypta, C.; Calvet, J.-C.; Albergel, C.; Balsamo, G.; Boussetta, S.; Carrer, D.; Lafont, S.; Meurey, C.

    2010-09-01

    An evaluation of the global ECMWF atmospheric reanalysis ERA-Interim (with a 0.5° grid) is performed over France, based on the high resolution (8 km) SAFRAN atmospheric reanalysis. The ERA-Interim precipitation, Incoming Solar Radiation (ISR), air temperature, air humidity, and wind speed, are compared with their SAFRAN counterparts. Also, interpolated in situ ISR observations are used in order to consolidate the evaluation of this variable. The daily precipitation estimates produced by ERA-Interim over France correlate very well with SAFRAN. However, the values are underestimated by 26%. A GPCP-corrected version of ERA-Interim is less biased (10-15%). The ERA-Interim estimates of ISR correlate very well with SAFRAN and with in situ observations on a daily basis. Whereas SAFRAN underestimates the ISR by 6-8 W m-2, ERA-Interim overestimates the ISR by 9-10 W m-2. In order to assess the impact of the ERA-Interim errors, simulations of the ISBA-A-gs land surface model are performed over the SMOSREX grassland site in southwestern France using ERA-Interim (with and without GPCP rescaling) and SAFRAN. Latent and sensible heat fluxes are simulated, together with carbon dioxide fluxes. The rescaled ERA-Interim performs better than the original ERA-Interim and permits to achieve flux scores similar to those obtained with SAFRAN.

  9. Aircrew Stabilization Improvement Task Windblast Tests With Tekscan Evaluation

    DTIC Science & Technology

    2005-12-01

    ARLHFE-WP-TR-2OO6-OQO5 STINFO COPY AIR FORCE RESEARCH LABORATORY Airerew Stabilization Improvement Task Windblast Tests wi Tekscan Evaluation Joseph...Interim Report APRIL 2000 - MAY 2004 4. TITLE AND SUBTITLE 5a. CONTRACT NUMBER Aircrew Stabilization Improvement Task Windblast Tests with Tekscan ...and test support to the ASIT effort during the testing of these deflector concepts, as well as an evaluation of the Tekscan pressure measurement system

  10. DEMONSTRATION OF THE DOE INTERIM ENERGY CONSERVATION STANDARDS FOR NEW FEDERAL RESIDENTIAL BUILDINGS

    SciTech Connect

    Lee, A. D.; Baechler, H. C.; Di Massa, F. V.; Lucas, R. G.; Shankle, D. L.

    1992-01-01

    In accordance with federal legislation, the U.S. Department of Energy (DOE) has sponsored a study to demonstrate use of its Interim Energy Conservation Standards for New Federal Residential Buildings. The demonstration study was conducted by DOE and the Pacific Northwest Laboratory (PNL). The demonstration is the second step in a three-step process: I) development of interim standards, 2) demonstration of the interim standards, and 3) development of final standards. The standards are mandatory for federal agency housing procurements. Nevertheless, PNL found at the start of the demonstration that agency use of the interim standards had been minimal. The purpose of the standards is to improve the energy efficiency of federal housing and increase the use of nondepletable energy sources. In accordance with the legislation, the standards were to be performance-based rather than prescribing specific energy conservation measures. To fulfill this aspect of the legislation, the standards use a computer software program called COSTSAFR which generates a point system that individualizes the standards to specific projects based on climate, housing type, and fuel costs. The standards generate minimum energy-efficiency requirements by applying the life-cycle cost methodology developed for federal projects. For the demonstration, PNL and DOE chose five federal agency housing projects which had been built in diverse geographic and climate regions. Participating agencies were the Air Force, the Army (which provided two case studies), the Navy, and the Department of Health and Human Services. PNL worked with agency housing procurement officials and designers/architects to hypothetically apply the interim standards to the procurement and design of each housing project. The demonstration started at the point in the project where agencies would establish their energyefficiency requirements for the project and followed the procurement process through the designers' use of the point

  11. Detroit MEDLINE Consortium; An Interim Report.

    ERIC Educational Resources Information Center

    DeSchryver, Victor; And Others

    The Detroit MEDLINE Consortium is an experimental pilot project which is intended to extend use of the on line retrieval system to the hospital environment. The consortium was initiated to increase the capacity for bibliographic information retrieval supportive of the delivery of patient care in the hospital environment. Secondarily, it addresses…

  12. 33 CFR 385.38 - Interim goals.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... the South Florida Water Management District shall sequence and schedule projects as appropriate to... unlikely to be met, then the Corps of Engineers and the South Florida Water Management District shall... South Florida Water Management District shall take into consideration the extent to which...

  13. Early Childhood Creative Library. Interim Report.

    ERIC Educational Resources Information Center

    East, Barbara

    To assist the early development of children in a poorly educated, rural four-county area of North Carolina, the Early Childhood Library Project trained parents and babysitters to teach preschool children by using educational games and materials supplied by the library. Equipment was purchased and made available to the community, story hours were…

  14. Interim assessment of the VAL automated guideway transit system. Interim report

    SciTech Connect

    Anagnostopoulos, G.

    1981-11-01

    This report describes an interim assessment of the VAL (Vehicules Automatiques Legers or Light Automated Vehicle) AGT system which is currently under construction in Lille, France, and which is to become fully operational in December 1983. This report contains a technical description and performance data resulting from a demonstration test program performed concurrently in August 1980. VAL is the first driverless AGT urban system application in France. The system operates at grade, elevated, and in tunnels on an exclusive concrete dual-lane guideway that is 12.7 kilometers long. The configuration of the system is a push-pull loop operating between 17 on-line stations. The system is designed to provide scheduled operation at 60-second headways and a normal one-way capacity of 7440 passengers per hour per direction with 55 percent of the passengers seated. Two pneumatic-tired vehicles are coupled into a single vehicle capable of carrying 124 passengers at line speeds of 60 km/hr. During the course of the demonstration test program, VAL demonstrated that it could achieve high levels of dependability and availability and could perform safely under all perceivable conditions.

  15. Southern Hemisphere Cloudiness In Extratropical Cyclones: An Observational Evaluation Of ERA-interim And MERRA

    NASA Astrophysics Data System (ADS)

    Naud, C. M.; Booth, J. F.; Del Genio, A. D.; Posselt, D. J.; van den Heever, S. C.

    2013-12-01

    Recently, underestimates in modeled southern oceans cloud cover were reported for most major general circulation models. However, it is unclear if reanalyses that assimilate multiple observations, and as such are deemed more reliable, also have this issue. Using MODIS, MISR and CloudSat-CALIPSO cloud cover datasets as a reference, we show that the same problem is found in both the ERA-interim and the MERRA reanalysis. We find that both reanalyses underestimate cloud cover by 5% to 20% in the 30S to 60S latitude band. Since extratropical cyclones are ubiquitous in this region, we determined whether clouds in these systems were also underestimated in both reanalyses. The MAP climatology of midlatitude storminess database is used to locate extratropical cyclones, and MODIS, MISR and CloudSat-CALIPSO provide the coincident and collocated cloud cover. An intercomparison between MODIS, MISR and CloudSat-CALIPSO cyclone-centered composites of cloud fractions was performed to provide a measure of the observational uncertainty. Uncertainty in the datasets was found to be less than the cloud cover bias in the reanalyses. It was evident that both ERA-interim and MERRA underestimate cloud cover in extratropical cyclones. Additionally, the underestimation was regime dependent, with a minimum bias in the cyclone warm sector north east of the low-pressure center and a maximum bias to the west of the low-pressure center and west of the cold front. MODIS and MISR cloud properties indicate that this maximum bias in cloud cover occurs in an area populated by low-level clouds often of broken nature. Comparison between reanalyses and CloudSat-CALIPSO vertical profiles reveal that this lack of low level clouds is also present to the east of the low-pressure centers in the warm frontal region. The cloud cover low bias is more pronounced in the MERRA reanalysis than ERA-interim, but differences between the two reanalyses in the dynamical and thermodynamical properties of the cyclones

  16. Cattail rhizome-derived alcohol interim report

    SciTech Connect

    Gabrielson, J.E.

    1981-05-30

    During the first six months of this project over 600 pounds of rhizomes, weighted wet and dirty were harvested and air dried. Average yields, on low land, were 1.9 tons/acre. Yields from areas in ponds may have been higher but it is difficult to estimate the areas. Sixteen fermentations were made. The results show that the rhizomes do not ferment well unless they are finely ground, and saccharified with acid, malt or enzymes. Grinding and screening so the feed passes a 40 mesh screen and then saccharifying with two enzymes produced the best results. Over 50% of the solids were converted to alcohol and carbon dioxide, 25% yield of alcohol based on dry weight of solids. Based on the maximum land harvest rate and the best alcohol yield production of 285 gallons of alcohol/acre of cattails are projected. This is a very good potential use of what is today marginal land.

  17. Management of the Iraqi Interim Government Fund

    DTIC Science & Technology

    2006-10-27

    Pluto Renovations 32249 06/01/05 $400,000 Renovation of Fresh Water System 32019 06/01/05 $2,133,888 Roadway Project 32238 05/21/05 $144,650 Pump...B Rehab P6 Sewage Pump Station X X X X X X X X X MND-B Renovation Rasheed Water Treatment Plant X X X X X X X X X MND-B Route Pluto Renovations X X

  18. New Hampshire Better Buildings - Final Interim Report

    SciTech Connect

    Cramton, Karen; Peters, Katherine

    2014-02-20

    With $10 million in funding from the U.S. Department of Energy's (DOE) Better Buildings Neighborhood Program, the NH Better Buildings program was established as an initiative that initially empowered the three “Beacon Communities” of Berlin, Nashua and Plymouth to achieve transformative energy savings and reductions in fossil fuel use and greenhouse gases through deep energy retrofits and complementary sustainable energy solutions. The program also enabled those Communities to provide leadership to other communities around the state as “beacons” of energy efficiency. The goal of the program was to reduce energy use by a minimum of 15% through energy efficiency upgrades in residential and commercial buildings in the communities. The program expanded statewide in April 2012 by issuing a competitive solicitation for additional commercial projects non-profit, and municipal energy efficiency projects from any community in the state, and a partnership with the state’s utility-run, ratepayer-funded residential Home Performance with ENERGY STAR® (HPwES) program. The NH Better Buildings program was administered by the New Hampshire Office of Energy and Planning (OEP) and managed by the NH Community Development Finance Authority (CDFA). The program started in July 2010 and the last projects funded with American Reinvestment and Recovery Act (ARRA) funds were completed in August 2013. The program will continue after the American Recovery and Reinvestment Act program period as a Revolving Loan Fund, enabling low-interest financing for deep energy retrofits into the future.

  19. Cascade Distiller System Performance Testing Interim Results

    NASA Technical Reports Server (NTRS)

    Callahan, Michael R.; Pensinger, Stuart; Sargusingh, Miriam J.

    2014-01-01

    The Cascade Distillation System (CDS) is a rotary distillation system with potential for greater reliability and lower energy costs than existing distillation systems. Based upon the results of the 2009 distillation comparison test (DCT) and recommendations of the expert panel, the Advanced Exploration Systems (AES) Water Recovery Project (WRP) project advanced the technology by increasing reliability of the system through redesign of bearing assemblies and improved rotor dynamics. In addition, the project improved the CDS power efficiency by optimizing the thermoelectric heat pump (TeHP) and heat exchanger design. Testing at the NASA-JSC Advanced Exploration System Water Laboratory (AES Water Lab) using a prototype Cascade Distillation Subsystem (CDS) wastewater processor (Honeywell d International, Torrance, Calif.) with test support equipment and control system developed by Johnson Space Center was performed to evaluate performance of the system with the upgrades as compared to previous system performance. The system was challenged with Solution 1 from the NASA Exploration Life Support (ELS) distillation comparison testing performed in 2009. Solution 1 consisted of a mixed stream containing human-generated urine and humidity condensate. A secondary objective of this testing is to evaluate the performance of the CDS as compared to the state of the art Distillation Assembly (DA) used in the ISS Urine Processor Assembly (UPA). This was done by challenging the system with ISS analog waste streams. This paper details the results of the AES WRP CDS performance testing.

  20. [When is enough evidence available?; interim analyses in clinical trials].

    PubMed

    van der Tweel, Ingeborg van; Roes, Kit C B

    2013-01-01

    There are ethical and economic reasons to design and conduct medical research as efficiently as possible. Clinical trials often take a long time because of the number of patients that must be included and the follow-up time in the study. Many data already become available during that time. By making interim analyses of these data it is possible to decide whether a final conclusion can be made. This may save time and may lead to a reduction in the number of patients. The statistical methodology of interim analyses is more complex than a fixed sample analysis and must be planned carefully in advance. The most important methods are sequential analysis and group sequential analysis. Both methods are aimed at a low risk of a false-positive conclusion. In this article we explain the application of these methods as well as considerations in the design of a study and interpretation of the results.