Science.gov

Sample records for plant demolition project

  1. Ashtabula Environmental Management Project Main Extrusion Plant Demolition Project. Demolition of the Ashtabula Environmental Management Project's Main Extrusion Plant

    SciTech Connect

    Colborn, Kurt; Johnson, Kathryn K.

    2003-02-27

    Significant progress was made this year toward closure of the Department of Energy's Ashtabula Environmental Management Project (AEMP) with the demolition of the 9-building Main Extrusion Plant Complex. The 44,000 square foot building complex formerly housed uranium extrusion facilities and equipment. At the start of the project in October of 2001, the buildings still contained a RCRA Part B storage area, operating mixed waste treatment facilities, active waste shredding and compacting process areas, and a state EPA permitted HEPA ventilation system. This paper presents a discussion of the multidisciplinary effort to bring the building to a safe shutdown condition in just six months, including relocation of existing process areas, utility isolation, and preliminary decontamination. Also discussed is the demolition strategy in which portions of the facility remained active while demolition was proceeding in other areas. Other details of the technical approach to the demolition are also discussed, including innovative techniques for demolition, galbestos removal, contamination control, and waste minimization. These techniques contributed to the early completion of demolition in July of 2002, fully two months ahead of schedule and $1.5 million under budget.

  2. ACCELERATED PILOT PROJECT FOR U CANYON DEMOLITION

    SciTech Connect

    KEHLER KL

    2011-01-13

    At the U.S. Department of Energy's Hanford Site in southeast Washington State, CH2M HILL Plateau Remediation Company (CH2M HILL) is underway on a first-of-a-kind project with the decommissioning and demolition of the U Canyon. Following the U.S. Environmental Protection Agency's Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) Record of Decision for the final remediation of the canyon, CH2M HILL is combining old and new technology and techniques to prepare U Canyon for demolition. The selected remedial action called first for consolidating and grouting equipment currently in the canyon into lower levels of the plant (openings called cells), after which the cell galleries, hot pipe trench, ventilation tunnel, drains and other voids below the operating deck and crane-way deck levels will be filled with approximately 20,000 cubic yards of grout and the canyon roof and walls demolished down to the approximate level of the canyon deck. The remaining canyon structure will then be buried beneath an engineered barrier designed to control potential contaminant migration for a 500-year life. Methods and lessons learned from this project will set the stage for the future demolition of Hanford's four other canyon-type processing facilities.

  3. DETAIL VIEW OF BATCH BIN AFTER PLANT DEMOLITION, LOOKING EAST ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    DETAIL VIEW OF BATCH BIN AFTER PLANT DEMOLITION, LOOKING EAST TOWARD ARNOLD - Chambers Window Glass Company, Batch Plant, North of Drey (Nineteenth) Street, West of Constitution Boulevard, Arnold, Westmoreland County, PA

  4. 126. DETAIL OF NORTH PLANT AMMUNITION DEMOLITION FACILITY, WITH ASSEMBLY ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    126. DETAIL OF NORTH PLANT AMMUNITION DEMOLITION FACILITY, WITH ASSEMBLY PLANT/WAREHOUSE (BUILDING 1601/1606/1701) IN BACKGROUND, FROM GB MANUFACTURING PLANT. VIEW TO NORTHWEST. - Rocky Mountain Arsenal, Bounded by Ninety-sixth Avenue & Fifty-sixth Avenue, Buckley Road, Quebec Street & Colorado Highway 2, Commerce City, Adams County, CO

  5. 125. NORTH PLANT AMMUNITION DEMOLITION FACILITY IN FOREGROUND AND ASSEMBLY ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    125. NORTH PLANT AMMUNITION DEMOLITION FACILITY IN FOREGROUND AND ASSEMBLY PLANT/WAREHOUSE (BUILDING 1601/1606/1701) IN BACKGROUND. FROM GB MANUFACTURING PLANT. VIEW TO NORTHWEST. - Rocky Mountain Arsenal, Bounded by Ninety-sixth Avenue & Fifty-sixth Avenue, Buckley Road, Quebec Street & Colorado Highway 2, Commerce City, Adams County, CO

  6. 120. NORTH PLANT GB BULK STORAGE BUILDING AND AMMUNITION DEMOLITION ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    120. NORTH PLANT GB BULK STORAGE BUILDING AND AMMUNITION DEMOLITION FACILITY AT CENTER AND CASE FILLING PLANT/CLUSTER ASSEMBLY BUILDING (BUILDING 1601/1606) IN BACKGROUND, FROM GB MANUFACTURING PLANT. VIEW TO WEST. - Rocky Mountain Arsenal, Bounded by Ninety-sixth Avenue & Fifty-sixth Avenue, Buckley Road, Quebec Street & Colorado Highway 2, Commerce City, Adams County, CO

  7. 129. DETAIL OF NORTH PLANT AMMUNITION DEMOLITION FACILITY, SHOWING FREESTANDING ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    129. DETAIL OF NORTH PLANT AMMUNITION DEMOLITION FACILITY, SHOWING FREE-STANDING SMOKESTACK (BUILDING 1504). VIEW TO SOUTHEAST. - Rocky Mountain Arsenal, Bounded by Ninety-sixth Avenue & Fifty-sixth Avenue, Buckley Road, Quebec Street & Colorado Highway 2, Commerce City, Adams County, CO

  8. Project Management Actions Demolition of a Research Facility Building 431

    SciTech Connect

    Collins, W L

    2005-09-06

    The Demolition of B431 is required to achieve the mission of LLNL and the NNSA FIRP objectives by: (1) Supporting the NNSA Infrastructure Plan goal to ''demolish excess facilities as early as possible''; (2) Banking square footage that allows continued application of advanced science and nuclear technology to the Nation's defense; and (3) Helping maintain and enhance the safety, security, and reliability of the weapons stockpile. A significant effort has been put into the demolition concept in order to ensure that it is well thought out and represents best-value to the government for the money.

  9. HAZWOPER project documents for demolition of the Waste Evaporator Facility, Building 3506, at Oak Ridge National Laboratory, Oak Ridge, Tennessee

    SciTech Connect

    1996-03-01

    This document, in support of the Waste Evaporator Facility (WEF) demolition project and contains the Project Work Plan and the Project Health and Safety Plan for demolition and partial remediation actions by ATG at the Waste Evaporator Facility, Building 3506. Various activities will be conducted during the course of demolition, and this plan provides details on the work steps involved, the identification of hazards, and the health and safety practices necessary to mitigate these hazards. The objective of this document is to develop an approach for implementing demolition activities at the WEF. This approach is based on prior site characterization information and takes into account all of the known hazards at this facility. The Project Work Plan provides instructions and requirements for identified work steps that will be utilized during the performance of demolition, while the Health and Safety Plan addresses the radiological, hazardous material exposure, and industrial safety concerns that will be encountered.

  10. PROJECT EXPERIENCE REPORT DEMOLITION OF HANFORDS 233-S PLUTONIUM CONCENTRATION FACILITY

    SciTech Connect

    BERLIN, G.T.

    2004-06-25

    This report provides a summary of the preparation, operations, innovative work practices, and lessons learned associated with demolition of the 2334 Plutonium Concentration Facility. This project represented the first open-air demolition of a highly-contaminated plutonium facility at the Hanford Site. This project may also represent the first plutonium facility in the US. Department of Energy (DOE) complex to have been demolished without first decontaminating surfaces to near ''free release'' standards. Demolition of plutonium contaminated structures, if not properly managed, can subject cleanup personnel and the environment to significant risk. However, with proper sequencing and innovative use of commercially available equipment, materials, and services, this project demonstrated that a plutonium processing facility can be demolished while avoiding the need to perform extensive decontamination or to construct large enclosures. This project utilized an excavator with concrete shears, diamond circular saws, water misting and fogging equipment, commercially available fixatives and dust suppressants, conventional mobile crane and rigging services, and near real-time modeling of meteorological and radiological conditions. Following a significant amount of preparation, actual demolition of the 2333 Facility began in October 2003 and was completed in late April 2004. The knowledge and experience gained on this project are important to the Hanford Site as additional plutonium processing facilities are scheduled for demolition in the near future. Other sites throughout the DOE Complex may also be faced with similar challenges. Numerous innovations and effective work practices were implemented on this project. Accordingly, a series of ''Lessons Learned and Innovative Practices Fact Sheets'' were developed and are included as an appendix to this report. This collection of fact sheets is not intended to capture every innovative work practice and lesson learned, but rather to

  11. PROJECT EXPERIENCE REPORT DEMOLITION OF HANFORDS 233-S PLUTONIUM CONCENTRATION FACILITY

    SciTech Connect

    BERLIN, G.T.; ORGILL, T.K.

    2004-07-14

    This report provides a summary of the preparation, operations, innovative work practices, and lessons learned associated with demolition of the 2334 Plutonium Concentration Facility. This project represented the first open-air demolition of a highly-contaminated plutonium facility at the Hanford Site. This project may also represent the first plutonium facility in the US. Department of Energy (DOE) complex to have been demolished without first decontaminating surfaces to near ''free release'' standards. Demolition of plutonium contaminated structures, if not properly managed, can subject cleanup personnel and the environment to significant risk. However, with proper sequencing and innovative use of commercially available equipment, materials, and services, this project demonstrated that a plutonium processing facility can be demolished while avoiding the need to perform extensive decontamination or to construct large enclosures. This project utilized an excavator with concrete shears, diamond circular saws, water misting and fogging equipment, commercially available fixatives and dust suppressants, conventional mobile crane and rigging services, and near real-time modeling of meteorological and radiological conditions. Following a significant amount of preparation, actual demolition of the 233-S Facility began in October 2003 and was completed in late April 2004. The knowledge and experience gained on this project are important to the Hanford Site as additional plutonium processing facilities are scheduled for demolition in the near future. Other sites throughout the DOE Complex may also be faced with similar challenges. Numerous innovations and effective work practices were implemented on this project. Accordingly, a series of ''Lessons Learned and Innovative Practices Fact Sheets'' were developed and are included as an appendix to this report. This collection of fact sheets is not intended to capture every innovative work practice and lesson learned, but rather

  12. PLUTONIUM FINISHING PLANT (PFP) 241-Z LIQUID WASTE TREATMENT FACILITY DEACTIVATION AND DEMOLITION

    SciTech Connect

    JOHNSTON GA

    2008-01-15

    Fluor Hanford, Inc. (FH) is proud to submit the Plutonium Finishing Plant (PFP) 241-Z liquid Waste Treatment Facility Deactivation and Demolition (D&D) Project for consideration by the Project Management Institute as Project of the Year for 2008. The decommissioning of the 241-Z Facility presented numerous challenges, many of which were unique with in the Department of Energy (DOE) Complex. The majority of the project budget and schedule was allocated for cleaning out five below-grade tank vaults. These highly contaminated, confined spaces also presented significant industrial safety hazards that presented some of the most hazardous work environments on the Hanford Site. The 241-Z D&D Project encompassed diverse tasks: cleaning out and stabilizing five below-grade tank vaults (also called cells), manually size-reducing and removing over three tons of process piping from the vaults, permanently isolating service utilities, removing a large contaminated chemical supply tank, stabilizing and removing plutonium-contaminated ventilation ducts, demolishing three structures to grade, and installing an environmental barrier on the demolition site . All of this work was performed safely, on schedule, and under budget. During the deactivation phase of the project between November 2005 and February 2007, workers entered the highly contaminated confined-space tank vaults 428 times. Each entry (or 'dive') involved an average of three workers, thus equaling approximately 1,300 individual confined -space entries. Over the course of the entire deactivation and demolition period, there were no recordable injuries and only one minor reportable skin contamination. The 241-Z D&D Project was decommissioned under the provisions of the 'Hanford Federal Facility Agreement and Consent Order' (the Tri-Party Agreement or TPA), the 'Resource Conservation and Recovery Act of 1976' (RCRA), and the 'Comprehensive Environmental Response, Compensation, and Liability Act of 1980' (CERCLA). The

  13. DEMOLITION OF HANFORDS 232-Z WASTE INCINERATION FACILITY

    SciTech Connect

    LLOYD, E.R.

    2006-11-21

    The 232-Z Plutonium Incinerator Facility was a small, highly alpha-contaminated, building situated between three active buildings located in an operating nuclear complex. Approximately 500 personnel worked within 250 meters (800 ft) of the structure and expectations were that the project would neither impact plant operations nor result in any restrictions when demolition was complete. Precision demolition and tight controls best describe the project. The team used standard open-air demolition techniques to take the facility to slab-on-grade. Several techniques were key to controlling contamination and confining it to the demolition area: spraying fixatives before demolition began; using misting systems, frequently applying fixatives, and using a methodical demolition sequence and debris load-out process. Detailed air modeling was done before demolition to determine necessary facility source-term levels, establish radiological boundaries, and confirm the adequacy of the proposed demolition approach. By only removing the major source term in equipment, HEPA filters, gloveboxes, and the like, and leaving fixed contamination on the walls, ceilings and floors, the project showed considerable savings and reduced worker hazards and exposure. The ability to perform this demolition safely and without the spread of contamination provides confidence that similar operations can be performed successfully. By removing the major source terms, fixing the remaining contamination in the building, and using controlled demolition and contamination control techniques, similar structures can be demolished cost effectively and safely.

  14. Geopolymerisation of silt generated from construction and demolition waste washing plants.

    PubMed

    Lampris, C; Lupo, R; Cheeseman, C R

    2009-01-01

    Recycling plants that size, sort and wash construction and demolition waste can produce high quality aggregate. However, they also produce up to 80ton per hour of filter cake waste containing fine (<63mum) silt particles that is classified as inert waste and normally landfilled. This research investigated the potential to form geopolymers containing silt, which would allow this problematic waste to be beneficially reused as aggregate. This would significantly improve the economic viability of recycling plants that wash wastes. Silt filter cakes have been collected from a number of aggregate washing plants operating in the UK. These were found to contain similar aluminosilicate crystalline phases. Geopolymer samples were produced using silt and silt mixed with either metakaolin or pulverised fuel ash (PFA). Silt geopolymers cured at room temperature had average 7-day compressive strengths of 18.7MPa, while partial substitution of silt by metakaolin or PFA increased average compressive strengths to 30.5 and 21.9MPa, respectively. Curing specimens for 24h at 105 degrees C resulted in a compressive strength of 39.7MPa and microstructural analysis confirmed the formation of dense materials. These strengths are in excess of those required for materials to be used as aggregate, particularly in unbound applications. The implications of this research for the management of waste silt at construction and demolition waste washing plants are discussed.

  15. The Decontamination, Decommissioning, and Demolition of the Engineering Test Reactor at the Idaho Cleanup Project

    SciTech Connect

    Coyne, D.W.

    2008-07-01

    In September 2007, CH2M-WG Idaho completed the decontamination, decommissioning and demolition (D and D) of the Engineering Test Reactor (ETR) facility. The 50-year-old research reactor, located at the Idaho National Laboratory site, posed significant challenges involving regulations governing the demolition of a historical facility, the removal of a large amount of hazardous materials as well as issues associated with the removal and disposal of the 112-ton reactor vessel. Prior to commencing full scale D and D, hazardous constituents were removed including cadmium, PCB oils and electrical components, lead, asbestos and mercury among others. The reactor required isolation in order to be removed. Due to activated metal within the reactor vessel, dose rates in the core region were approximately 1100 R/hr. Subsequent dose rates outside the vessel varied from 60 mR to greater than 2 R. Due to the dose rates, the project team decided to fill the reactor vessel with grout to a level above the core region and below the discharge to the canal. To remove the reactor, access to the 17 mounting shoes was required. These shoes were encased in the high density concrete biological shield approximately 8 feet below grade. The project team used explosives to remove the biological shield. The demolition had to be controlled to prevent damaging the reactor vessel and to limit the seismic impact on a nearby operating reactor. Upon completion of the blast, the concrete was removed exposing the support shoes for the vessel. The reactor building was then demolished to accommodate the twin gantry system used to lift the reactor vessel. In September, the reactor vessel was lifted and placed onto a multi-axle trailer for transport to an onsite disposal facility. (authors)

  16. Microstructure of Concrete with Aggregates from Construction and Demolition Waste Recycling Plants.

    PubMed

    Bravo, Miguel; Santos Silva, António; de Brito, Jorge; Evangelista, Luís

    2016-02-01

    This paper intends to analyze the microstructure of concrete with recycled aggregates (RA) from construction and demolition waste from various Portuguese recycling plants. To that effect, several scanning electron microscopy (SEM) and energy-dispersive X-ray spectroscopy (EDS) analyses were performed. Various concrete mixes were evaluated in order to analyze the influence of the RA's collection point and consequently of their composition on the mixes' characteristics. Afterward all the mixes were subjected to the capillary water absorption test in order to quantitatively evaluate their porosity. Results from the SEM/EDS analysis were compared with those from capillary water absorption test. The SEM/EDS analysis showed that the bond capacity of aggregates to the new cement paste is greatly influenced by the RA's nature. On the other hand, there was an increase in porosity with the incorporation of RA. PMID:26700727

  17. Microstructure of Concrete with Aggregates from Construction and Demolition Waste Recycling Plants.

    PubMed

    Bravo, Miguel; Santos Silva, António; de Brito, Jorge; Evangelista, Luís

    2016-02-01

    This paper intends to analyze the microstructure of concrete with recycled aggregates (RA) from construction and demolition waste from various Portuguese recycling plants. To that effect, several scanning electron microscopy (SEM) and energy-dispersive X-ray spectroscopy (EDS) analyses were performed. Various concrete mixes were evaluated in order to analyze the influence of the RA's collection point and consequently of their composition on the mixes' characteristics. Afterward all the mixes were subjected to the capillary water absorption test in order to quantitatively evaluate their porosity. Results from the SEM/EDS analysis were compared with those from capillary water absorption test. The SEM/EDS analysis showed that the bond capacity of aggregates to the new cement paste is greatly influenced by the RA's nature. On the other hand, there was an increase in porosity with the incorporation of RA.

  18. Weldon Spring Site Remedial Action Project approach to building dismantlement and demolition

    SciTech Connect

    Spittler, F.J.

    1996-01-01

    When remediation began at the Weldon Spring Site Remedial Action Project (WSSRAP), there were 41 buildings on site. Twenty-nine of these buildings were ancillary structures and were not used for processing radioactive material. Most of these have been torn down. The remaining 12 buildings were used for uranium and thorium processing or were major support structures, such as the laboratory. Two of the buildings were major processing operations occurred were successfully demolished in February of this year. Demolition of all structures will be complete in September of this year. To give an understanding of the magnitude of the work, the following is a description of the physical characteristics of the green salt building. This building was used to convert brown oxide (UO3) to green salt (UF4), which is the last intermediate step in purifying the mostly yellow cake feed material into uranium metal.

  19. Deriving a Planting Medium from Solid Waste Compost and Construction, Demolition and Excavation Waste

    NASA Astrophysics Data System (ADS)

    Farajalla, Nadim; Assaf, Eleni; Bashour, Issam; Talhouk, Salma

    2014-05-01

    Lebanon's very high population density has been increasing since the end of the war in the early 1990s reaching 416.36 people per square kilometer. Furthermore, the influx of refugees from conflicts in the region has increased the resident population significantly. All these are exerting pressure on the country's natural resources, pushing the Lebanese to convert more forest and agricultural land into roads, buildings and houses. This has led to a building boom and rapid urbanization which in turn has created a demand for construction material - mainly rock, gravel, sand, etc. nearly all of which were locally acquired through quarrying to the tune of three million cubic meters annually. This boom has been followed by a war with Israel in 2006 which resulted in thousands of tonnes of debris. The increase in population has also led to an increase in solid waste generation with 1.57 million tonnes of solid waste generated in Lebanon per year. The combination of construction, demolition and excavation (CDE) waste along with the increase in solid waste generation has put a major stress on the country and on the management of its solid waste problem. Compounding this problem are the issues of quarries closure and rehabilitation and a decrease in forest and vegetative cover. The on-going research reported in this paper aims to provide an integrated solution to the stated problem by developing a "soil mix" derived from a mélange of the organic matter of the solid waste (compost), the CDE waste, and soil. In this mix, native and indicator plants are planted (in pots) from which the most productive mix will be selected for further testing at field level in later experiments. The plant species used are Matiolla, a native Lebanese plant and Zea mays, which is commonly known used as an indicator plant due to its sensitivity to environmental conditions. To ensure sustainability and environmental friendliness of the mix, its physical and chemical characteristics are monitored

  20. Environmental assessment for the salvage/demolition of 200 West Area, 200 East Area, and 300 Area steam plants

    SciTech Connect

    1996-10-01

    This environmental assessment has been prepared to assess potential environmental impacts associated with the US Department of Energy`s proposed action: the salvage/demolition of the 200 West Area, 200 East Area, and 300 Area Steam Plants and steam distribution piping. Impact information will be used by the US Department of Energy, Richland Operations Office Manager, to determine if the proposed action is a major federal action significantly affecting the quality of the human environment. If the proposed action is determined to be major and significant, an environmental impact statement will be prepared. If the proposed action is determined not to be major and significant, a Finding of No Significant Impact (FONSI) will be issued and the action can proceed. The proposed action involves the salvage and demolition of the 200 West Area, 200 East Are, and 300 Area steam plants and their associated steam distribution piping, equipment, and ancillary facilities. Activities include the salvaging and recycling of all materials, wastes, and equipment where feasible, with waste minimization efforts utilized.

  1. Nuclear Rocket Facility Decommissioning Project: Controlled Explosive Demolition of Neutron-Activated Shield Wall

    SciTech Connect

    Michael R. Kruzic

    2008-06-01

    Located in Area 25 of the Nevada Test Site (NTS), the Test Cell A (TCA) Facility (Figure 1) was used in the early to mid-1960s for testing of nuclear rocket engines, as part of the Nuclear Rocket Development Program, to further space travel. Nuclear rocket testing resulted in the activation of materials around the reactors and the release of fission products and fuel particles. The TCA facility, known as Corrective Action Unit 115, was decontaminated and decommissioned (D&D) from December 2004 to July 2005 using the Streamlined Approach for Environmental Restoration (SAFER) process, under the Federal Facility Agreement and Consent Order. The SAFER process allows environmental remediation and facility closure activities (i.e., decommissioning) to occur simultaneously, provided technical decisions are made by an experienced decision maker within the site conceptual site model. Facility closure involved a seven-step decommissioning strategy. First, preliminary investigation activities were performed, including review of process knowledge documentation, targeted facility radiological and hazardous material surveys, concrete core drilling and analysis, shield wall radiological characterization, and discrete sampling, which proved to be very useful and cost-effective in subsequent decommissioning planning and execution and worker safety. Second, site setup and mobilization of equipment and personnel were completed. Third, early removal of hazardous materials, including asbestos, lead, cadmium, and oil, was performed ensuring worker safety during more invasive demolition activities. Process piping was to be verified void of contents. Electrical systems were de-energized and other systems were rendered free of residual energy. Fourth, areas of high radiological contamination were decontaminated using multiple methods. Contamination levels varied across the facility. Fixed beta/gamma contamination levels ranged up to 2 million disintegrations per minute (dpm)/100

  2. K-25 Structural Separation and Demolition

    SciTech Connect

    Cater, Frank

    2008-01-15

    The K-25 building is a former gaseous diffusion plant, built in 1944-1945 as part of the United States Manhattan Project. The structure was the largest structure under one roof, surpassed only by the Pentagon. Together the three wings represent about 17.8 hectare (44 acres) under roof and are generally about 18.3 meters (60 ft.) high on the outside face and approximately 12.2 meters (40 ft.) high on the inside face. The entire structure was built in the shape of a 'U', with a lateral distance of approximately one mile. It was constructed in individual building units with each unit connected using expansion joint-type connection. A single unit is approximately 24.4 meters (80 ft.) across and 122 meters (400 ft.) deep. The northern structure is connected to the eastern and western structures at the upper level floors. The four-level, U-shaped building is a steel-frame structure with corrugated cement-asbestos siding. The cell level is an elevated concrete structure supported by reinforced concrete columns located in the basement, or vault area. The vault area can be accessed at grade level from the outside perimeter. Inside the courtyard, the grade level has been raised to provide entry to the second or cell floor level. An engineering evaluation of the structure was performed to determine the condition of the structure and possibility of unplanned collapse of any portion of the structure. The evaluation included physical inspections, calculations for wind, pre-demolition loads, and evaluation of failure modes. The results of the evaluation have provided guidance for the demolition plan and the development of criteria for protection of personnel performing pre-demolition activities. Challenges include degradation of the structure that necessitated repair, dealing with changes in the code revisions from both the American Concrete Institute (ACI) and the American Institute of Steel Construction (AISC), access to areas of the structure that were not necessarily designed

  3. Plant Biology Science Projects.

    ERIC Educational Resources Information Center

    Hershey, David R.

    This book contains science projects about seed plants that deal with plant physiology, plant ecology, and plant agriculture. Each of the projects includes a step-by-step experiment followed by suggestions for further investigations. Chapters include: (1) "Bean Seed Imbibition"; (2) "Germination Percentages of Different Types of Seeds"; (3)…

  4. PREPARATION OF U-PLANT FOR FINAL DEMOLITION AND DISPOSAL - 12109E

    SciTech Connect

    FARABEE OA; HERZOG B; CAMERON C

    2012-02-16

    The U-Plant is one of the five major nuclear materials processing facilities at Hanford and was chosen as a pilot project to develop the modalities for closure of the other four facilities at Hanford and the rest of the Department of Energy (DOE) complex. The remedy for this facility was determined by a Record of Decision (ROD) pursuant to the Comprehensive Environmental Response, Compensation and Liability Act of 1980 (CERCLA). That remedy was to 'Close in Place - Partially Demolished Structure'. The U-Plant facility is identified as the 221-U Building and is a large, concrete structure nominally 247m (810 ft) long, 20 M (66 ft) wide and 24 m (77 ft) high with approximately 9 m (30 ft) being below grade level. It is a robust facility with walls ranging from 0.9 m to 2.7 m (3 ft to 9 ft) thick. One large room extends the entire length of the building that provides access to 40 sub-grade processing cells containing tanks, piping and other components. The work breakdown was divided into three major deliverables: (1) Tank D-10 Removal: removal of Tank D-10, which contained TRU waste; (2) Equipment Disposition: placement of contaminated equipment in the sub-grade cells; and (3) Canyon Grouting: grouting canyon void spaces to the maximum extent practical. A large number of pieces of contaminated equipment (pumps, piping, centrifuges, tanks, etc) from other facilities that had been stored on the canyon operating floor were placed inside of the sub-grade cells as final disposition, grouted and the cell shield plug reinstalled. This action precluded a large volume of waste being transported to another burial site. Finally, {approx}19,000 m3 ({approx}25,000 yd3) of grout was placed inside of the cells (in and around the contaminated equipment), in the major galleries. the ventilation tunnel, the external ventilation duct, and the hot pipe trench to minimize the potential for void spaces and to reduce the mobility, solubility, and/or toxicity of the grouted waste. The

  5. Developing a Planting Medium from Solid Waste Compost and Construction and Demolition Rubble for Use in Quarry Rehabilitation

    NASA Astrophysics Data System (ADS)

    Assaf, E. A.

    2015-12-01

    The combination of construction, demolition and excavation (CDE) waste along with the increase in solid waste generation has put a major stress on Lebanon and on the management of its solid waste. Compounding this problem are the issues of quarries closure and rehabilitation and a decrease in forest and vegetative cover. This research aims to provide an integrated solution to the stated problem by developing a "soil mix" derived from a mélange of the organic matter of the solid waste (compost), the CDE waste, and soil. Excavation and construction debris were ground to several sizes and mixed with compost and soil at different ratios. Replicates of these mixes and a set of control (regular soil) were used. In this mix, native and indicator plants are planted (in pots). The plant species used are Mathiolla crassifolia and Zea mays (Corn). Results have shown successful growth of both corn and Mathiolla seedlings in the mixes with higher amounts of construction rubble and compost i.e. Rubble: Soil: Compost Ratio of 2:1:1 and 1:0:1. However treatments with no compost and with less quantities of rubble demonstrated the inability of the soil used to sustain plant growth alone (1:1:1 and 1:1:0). Last but not least, the control consisting of soil only ended up being the weakest mix with yellow corn leaves and small Mathiolla seedlings fifty days after planting and fertilizing. Additionally, soil analysis, rubble and compost analysis were conducted. The samples were tested for heavy metals, nutrient availability and values of pH and EC. No contamination has been reported and an abundance of macronutrients and micronutrients was documented for the soil and compost. High alkalinity is due to the presence of concrete and the high percentage of Calcium Carbonate in Lebanese soils. Accordingly, the most adequate mixes for planting are treatments A (2:1:1) and B (1:0:1) and they should be pursued for a pilot scale study to test their potential use in quarry rehabilitation and

  6. Phased Demolition of an Occupied Facility

    SciTech Connect

    Brede, Lawrence M.; Lauterbach, Merl J.; Witt, Brandon W.; McCague, James

    2008-01-15

    The U.S. government constructed the K-1401 facility in the late 1940's as a support building for various projects supporting the uranium gaseous diffusion process. In 2004 the U.S. Department of Energy authorized Bechtel Jacobs Company, LLC (BJC) to decontaminate and demolish the facility. The K-1401 facility was used for a variety of industrial purposes supporting the gaseous diffusion process. Many different substances were used to support these processes over the years and as a result different parts of the facility were contaminated with fluorine, chlorine trifluoride, uranium and technetium radiological contamination, asbestos, and mercury. The total facility area is 46,015 m{sup 2} (495,000 sf) including a 6,800 m{sup 2} basement (73,200 sf). In addition to the contamination areas in the facility, a large portion was leased to businesses for re-industrialization when the D and D activities began. The work scope associated with the facility included purging and steam cleaning the former fluorine and chlorine trifluoride systems, decontaminating loose radiologically contaminated and mercury spill areas, dismantling former radiological lines contaminated with uranium oxide compounds and technetium, abating all asbestos containing material, and demolishing the facility. These various situations contributed to the challenge of successfully conducting D and D tasks on the facility. In order to efficiently utilize the work force, demolition equipment, and waste hauling trucks the normal approach of decontaminating the facility of the hazardous materials, and then conducting demolition in series required a project schedule of five years, which is not cost effective. The entire project was planned with continuous demolition as the goal end state. As a result, the first activities, Phase 1, required to prepare sections for demolition, including steam cleaning fluorine and chlorine trifluoride process lines in basement and facility asbestos abatement, were conducted

  7. Nuclear Rocket Facility Decommissioning Project: Controlled Explosive Demolition of Neutron Activated Shield Wall

    SciTech Connect

    Michael R. Kruzic

    2007-09-16

    Located in Area 25 of the Nevada Test Site (NTS), the Test Cell A (TCA) Facility was used in the early to mid-1960s for the testing of nuclear rocket engines, as part of the Nuclear Rocket Development Program, to further space travel. Nuclear rocket testing resulted in the activation of materials around the reactors and the release of fission products and fuel particles in the immediate area. Identified as Corrective Action Unit 115, the TCA facility was decontaminated and decommissioned (D&D) from December 2004 to July 2005 using the Streamlined Approach for Environmental Restoration (SAFER) process, under the ''Federal Facility Agreement and Consent Order''. The SAFER process allows environmental remediation and facility closure activities (i.e., decommissioning) to occur simultaneously provided technical decisions are made by an experienced decision maker within the site conceptual site model, identified in the Data Quality Objective process. Facility closure involved a seven-step decommissioning strategy. Key lessons learned from the project included: (1) Targeted preliminary investigation activities provided a more solid technical approach, reduced surprises and scope creep, and made the working environment safer for the D&D worker. (2) Early identification of risks and uncertainties provided opportunities for risk management and mitigation planning to address challenges and unanticipated conditions. (3) Team reviews provided an excellent mechanism to consider all aspects of the task, integrated safety into activity performance, increase team unity and ''buy-in'' and promoted innovative and time saving ideas. (4) Development of CED protocols ensured safety and control. (5) The same proven D&D strategy is now being employed on the larger ''sister'' facility, Test Cell C.

  8. Use of filler limestone and construction and demolition residues for remediating soils contaminated with heavy metals: an assessment by means of plant uptake.

    NASA Astrophysics Data System (ADS)

    Banegas, Ascension; Martinez-Sanchez, Maria Jose; Agudo, Ines; Perez-Sirvent, Carmen

    2010-05-01

    A greenhouse trial was carried out to evaluate the assimilation of heavy metals by three types of horticultural plants (lettuce, broccoli and alfalfa), different parts of which are destined for human and animal consumption (leaves, roots, fruits). The plants were cultivated in four types of soil, one uncontaminated (T1), one soil collected in the surrounding area of Sierra Minera (T2), the third being remediated with residues coming from demolition and construction activities (T3) and the four remediated with filler limestone (T4). To determine the metal content, soil samples were first ground to a fine powder using an agate ball mill. Fresh vegetable samples were separated into root and aboveground biomass and then lyophilized. The DTPA-extractable content was also determined to calculate the bioavailable amount of metal. Finally, the translocation factor (TF) and bioconcentration factor (BCF) were calculated. Arsenic levels were obtained by using atomic fluorescence spectrometry with an automated continuous flow hydride generation (HG-AFS) spectrometer and Cd, Pb and Zn was determined by electrothermal atomization atomic absorption spectrometry (ETAAS) or flame atomic absorption spectrometry (FAAS). Samples of the leached water were also obtained and analyzed. According to our results, the retention of the studied elements varies with the type of plant and is strongly decreased by the incorporation of filler limestone and/or construction and demolition residues to the soils. This practice represents a suitable way to reduce the risk posed to the biota by the presence of high levels of heavy metal in soil.

  9. Phased Construction Completion Report for Building K-1401 of the Remaining Facilities Demolition Project at the East Tennessee Technology Park Oak Ridge, Tennessee

    SciTech Connect

    Garland S.

    2008-03-01

    This Phased Construction Completion Report documents the demolition of Bldg. K-1401, Maintenance Building, addressed in the Action Memorandum for the Remaining Facilities Demolition Project at East Tennessee Technology Park, Oak Ridge, Tennessee (DOE 2003a) as a Comprehensive Environmental Response, Compensation, and Liability Act of 1980 non-time-critical removal action. The objectives of the removal action (DOE 2003a) - to eliminate the source of potential contamination, to eliminate the threat of potential future releases, and/or to eliminate the threats to the general public and the environment - were met. The end state of this action is for the slab to remain with all penetrations sealed and grouted or backfilled. The basement and pits remain open. There is residual radiological and polychlorinated biphenyl contamination on the slab and basement. A fixative was applied to the area on the pad contaminated with polychlorinated biphenyls. Interim land-use controls will be maintained until final remediation decisions are made under the Zone 2 Record of Decision (DOE 2005a).

  10. Phased Construction Completion Report for Bldg. K-1401 of the Remaining Facilities Demolition Project at the East Tennessee Technology Park, Oak Ridge, Tennessee

    SciTech Connect

    Bechtel Jacobs

    2008-10-01

    This Phased Construction Completion Report documents the demolition of Bldg. K-1401, Maintenance Building, addressed in the Action Memorandum for the Remaining Facilities Demolition Project at East Tennessee Technology Park, Oak Ridge, Tennessee (DOE 2003a) as a Comprehensive Environmental Response, Compensation, and Liability Act of 1980 non-time-critical removal action. The objectives of the removal action (DOE 2003a) - to eliminate the source of potential contamination, to eliminate the threat of potential future releases, and/or to eliminate the threats to the general public and the environment - were met. The end state of this action is for the slab to remain with all penetrations sealed and grouted or backfilled. The basement and pits remain open. There is residual radiological and polychlorinated biphenyl contamination on the slab and basement. A fixative was applied to the area on the pad contaminated with polychlorinated biphenyls. Interim land-use controls will be maintained until final remediation decisions are made under the Zone 2 Record of Decision (DOE 2005a).

  11. 24 CFR 247.5 - Inapplicability to substantial rehabilitation or demolition.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... rehabilitation or demolition. 247.5 Section 247.5 Housing and Urban Development Regulations Relating to Housing... Projects § 247.5 Inapplicability to substantial rehabilitation or demolition. This subpart shall not apply... project to a purchaser who purchases for the purpose of substantial rehabilitation or demolition....

  12. 24 CFR 247.5 - Inapplicability to substantial rehabilitation or demolition.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... rehabilitation or demolition. 247.5 Section 247.5 Housing and Urban Development Regulations Relating to Housing... Projects § 247.5 Inapplicability to substantial rehabilitation or demolition. This subpart shall not apply... project to a purchaser who purchases for the purpose of substantial rehabilitation or demolition....

  13. Hanford Small Building Demolition Program

    SciTech Connect

    Diebel, J.A.; Douglas, L.M.; Shuck, R.G.

    1993-09-01

    Over 1,100 buildings currently exist on the Hanford Site. Many of these structures are outdated and no longer needed to support the environmental restoration mission. The Hanford Small Building Demolition Program is part of a combined effort of an Accelerated Decontamination and Decommissioning (D and D) Program and Landlord Site Preparation and Stabilization Program aimed at reducing the inventory of noncontaminated surplus facilities onsite. The reduction of surplus facilities results in reduced surveillance and maintenance (S and M) costs and eliminates the safety and environmental hazards associated with aging buildings. The project involves decommissioning up to 80 surplus facilities over the next five years.

  14. The Walls Come Tumbling Down: Decontamination and Demolition of 29 Manhattan Project and Cold War-Era Buildings and Structures at Los Alamos National Laboratory-12301

    SciTech Connect

    Chaloupka, Allan B.; Finn, Kevin P.; Parsons, Duane A.

    2012-07-01

    ,000 ft{sup 2}). The initially approved baseline for the ARRA D and D Project was to remove 22 buildings and structures that included approximately 14,680 m{sup 2} (158,000 ft{sup 2}) of footprint. By employing efficiencies during subcontracting, demolition, and waste segregation, the savings allowed an additional 1,580 m{sup 2} (17,000 ft{sup 2}) of footprint to be removed using ARRA funds. Additionally, the lessons learned from this experience were used to apply NNSA funding to the removal of six additional non-contaminated buildings and structures. In the end, 29 buildings and structures, including stacks, cooling towers and tanks, were removed from the mesa. The entire DP East area was cleared of buildings and sub-grade structures and the soils cleaned to residential standards. The total footprint reduction at TA-21 as a result of this effort was in excess of 17,650 m{sup 2} (190,000 ft{sup 2}). The use of a Laboratory self-performance team to start demolition of non-contaminated structures resulted in steady work performance early in the project while subcontracts were being put in place to perform more complicated abatement and contaminated demolition activities. Most importantly, there were no serious worker injuries and the minor injuries recorded were those common to construction type activities. Extensive monitoring along the site boundary demonstrated that no hazardous chemicals or radioactive contamination were released and radiological dose to the public was negligible. The ARRA demolition activities were completed six months in advance of the deadline for employing ARRA funds. Additionally, over 17,585 m{sup 3} (23,000 yds{sup 3}) of building demolition debris was safely removed from DP Mesa. All of the major buildings have been removed, unencumbered access to the SWMUs that are required to be cleaned up by the Consent Order with the state of New Mexico, has been achieved, and a significant portion of the mesa has been prepared to support a process that will

  15. Spatial distribution of organic pollutants in industrial construction and demolition waste and their mutual interaction on an abandoned pesticide manufacturing plant.

    PubMed

    Huang, Sheng; Zhao, Xin; Sun, Yanqiu; Ma, Jianli; Gao, Xiaofeng; Xie, Tian; Xu, Dongsheng; Yu, Yi; Zhao, Youcai

    2016-04-01

    A comprehensive field investigation of organic pollutants was examined in industrial construction and demolition waste (ICDW) inside an abandoned pesticide manufacturing plant. Concentrations of eight types of pesticides, a metabolite and two intermediates were studied. The ICDW was under severe and long-term contamination by organophosphorus, intermediates and pyrethroid pesticide with mean concentrations of 23,429, 3538 and 179.4 mg kg(-1), respectively. FT-IR analysis suggested that physical absorption and chemical bonding were their mutual interaction forms. Patterns of total pesticide spatial distribution showed good correlations with manufacturing processes spreading all over the plant both in enclosed workshops and in residues randomly dumped outside, while bricks and coatings were the most vulnerable to pollutants. Ultimately the fate of the OPPs was diversified as the immersion of ICDW in water largely transferred the pollutants into aquatic systems while exposure outside did not largely lead to pesticide degradation. The adoption of centralized collections for the disposal of wastes could only eliminate part of the contaminated ICDW, probably due to lack of knowledge and criteria. Correlation matrix and cluster analysis indicated that regulated disposal and management of polluted ICDW was effective, thus presenting the requirement for its appropriate disposal. PMID:26972868

  16. Environmental analysis of a construction and demolition waste recycling plant in Portugal--Part I: energy consumption and CO2 emissions.

    PubMed

    Coelho, André; de Brito, Jorge

    2013-05-01

    This work is a part of a wider study involving the economic and environmental implications of managing construction and demolition waste (CDW), focused on the operation of a large scale CDW recycling plant. This plant, to be operated in the Lisbon Metropolitan Area (including the Setúbal peninsula), is analysed for a 60 year period, using primary energy consumption and CO2eq emission impact factors as environmental impact performance indicators. Simplified estimation methods are used to calculate industrial equipment incorporated, and the operation and transport related impacts. Material recycling--sorted materials sent to other industries, to act as input--is taken into account by discounting the impacts related to industrial processes no longer needed. This first part focuses on calculating the selected impact factors for a base case scenario (with a 350 tonnes/h installed capacity), while a sensitivity analysis is provided in part two. Overall, a 60 year global primary energy consumption of 71.4 thousand toe (tonne of oil equivalent) and a total CO2eq emission of 135.4 thousand tonnes are expected. Under this operating regime, around 563 thousand toe and 1465 thousand tonnes CO2eq could be prevented by replacing raw materials in several construction materials industries (e.g.: ferrous and non-ferrous metals, plastics, paper and cardboard).

  17. Environmental analysis of a construction and demolition waste recycling plant in Portugal--Part I: energy consumption and CO2 emissions.

    PubMed

    Coelho, André; de Brito, Jorge

    2013-05-01

    This work is a part of a wider study involving the economic and environmental implications of managing construction and demolition waste (CDW), focused on the operation of a large scale CDW recycling plant. This plant, to be operated in the Lisbon Metropolitan Area (including the Setúbal peninsula), is analysed for a 60 year period, using primary energy consumption and CO2eq emission impact factors as environmental impact performance indicators. Simplified estimation methods are used to calculate industrial equipment incorporated, and the operation and transport related impacts. Material recycling--sorted materials sent to other industries, to act as input--is taken into account by discounting the impacts related to industrial processes no longer needed. This first part focuses on calculating the selected impact factors for a base case scenario (with a 350 tonnes/h installed capacity), while a sensitivity analysis is provided in part two. Overall, a 60 year global primary energy consumption of 71.4 thousand toe (tonne of oil equivalent) and a total CO2eq emission of 135.4 thousand tonnes are expected. Under this operating regime, around 563 thousand toe and 1465 thousand tonnes CO2eq could be prevented by replacing raw materials in several construction materials industries (e.g.: ferrous and non-ferrous metals, plastics, paper and cardboard). PMID:23422042

  18. Air Monitoring Modeling of Radioactive Releases During Proposed PFP Complex Demolition Activities

    SciTech Connect

    Napier, Bruce A.; Droppo, James G.; Rishel, Jeremy P.

    2011-01-24

    This report is part of the planning process for the demolition of the 234-5Z, 236-Z, 242-Z, and 291-Z-1 structures at the Plutonium Finishing Plant (PFP) facilities on the Hanford Site. Pacific Northwest National Laboratory (PNNL) supports the U.S. Department of Energy (DOE) and the CH2M HILL Plateau Remediation Company (CHPRC) demolition planning effort by making engineering estimates of potential releases for various potential demolition alternatives. This report documents an analysis considering open-air demolition using standard techniques. It does not document any decisions about the decommissioning approaches; it is expected that this report will be revisited as demolition plans are finalized.

  19. New Hires, Building Demolition

    ScienceCinema

    None

    2016-07-12

    Using Recovery Act funding, Department of Energy contractor CH2M HILL Plateau Remediation Company has hired hundreds of new employees to do cleanup work at the Hanford Site, including demolition of dozens of excess facilities.This video was produced by CH2M HILL on Jan. 8, 2010.

  20. Use of Source Term and Air Dispersion Modeling in Planning Demolition of Highly Alpha-Contaminated Buildings

    SciTech Connect

    Droppo, James G.; Napier, Bruce A.; Rishel, Jeremy P.; Bloom, Richard W.

    2011-06-22

    The current cleanup of structures related to cold-war production of nuclear materials includes the need to demolish a number of highly alpha-contaminated structures. The process of planning for the demolition of such structures includes unique challenges related to ensuring the protection of both workers and the public. Pre-demolition modeling analyses were conducted to evaluate potential exposures resulting from the proposed demolition of a number of these structures. Estimated emission rates of transuranic materials during demolition are used as input to an air-dispersion model. The climatological frequencies of occurrence of peak air and surface exposures at locations of interest are estimated based on years of hourly meteorological records. The modeling results indicate that downwind deposition is the main operational limitation for demolition of a highly alpha-contaminated building. The pre-demolition modeling directed the need for better contamination characterization and/or different demolition methods—and in the end, provided a basis for proceeding with the planned demolition activities. Post-demolition modeling was also conducted for several contaminated structures, based on the actual demolition schedule and conditions. Comparisons of modeled and monitoring results are shown. Recent monitoring data from the demolition of a UO3 plant shows increments in concentrations that were previously identified in the pre-demolition modeling predictions; these comparisons confirm the validity and value of the pre-demolition source-term and air dispersion computations for planning demolition activities for other buildings with high levels of radioactive contamination.

  1. Decommissioning of Active Ventilation Systems in a Nuclear R and D Facility to Prepare for Building Demolition (Whiteshell Laboratories Decommissioning Project, Canada) - 13073

    SciTech Connect

    Wilcox, Brian; May, Doug; Howlett, Don; Bilinsky, Dennis

    2013-07-01

    Whiteshell Laboratories (WL) is a nuclear research establishment owned by the Canadian government and operated by Atomic Energy of Canada Limited (AECL) since the early 1960's. WL is currently under a decommissioning license and the mandate is to remediate the nuclear legacy liabilities in a safe and cost effective manner. The WL Project is the first major nuclear decommissioning project in Canada. A major initiative underway is to decommission and demolish the main R and D Laboratory complex. The Building 300 R and D complex was constructed to accommodate laboratories and offices which were mainly used for research and development associated with organic-cooled reactors, nuclear fuel waste management, reactor safety, advanced fuel cycles and other applications of nuclear energy. Building 300 is a three storey structure of approximately 16,000 m{sup 2}. In order to proceed with building demolition, the contaminated systems inside the building have to be characterized, removed, and the waste managed. There is a significant focus on volume reduction of radioactive waste for the WL project. The active ventilation system is one of the significant contaminated systems in Building 300 that requires decommissioning and removal. The active ventilation system was designed to manage hazardous fumes and radioactivity from ventilation devices (e.g., fume hoods, snorkels and glove boxes) and to prevent the escape of airborne hazardous material outside of the laboratory boundary in the event of an upset condition. The system includes over 200 ventilation devices and 32 active exhaust fan units and high efficiency particulate air (HEPA) filters. The strategy to remove the ventilation system was to work from the laboratory end back to the fan/filter system. Each ventilation duct was radiologically characterized. Fogging was used to minimize loose contamination. Sections of the duct were removed by various cutting methods and bagged for temporary storage prior to disposition

  2. Mixing Construction, Demolition and Excavation Waste and Solid Waste Compost for the Derivation of a Planting Medium for Use in the Rehabilitation of Quarries

    NASA Astrophysics Data System (ADS)

    Assaf, Eleni

    2015-04-01

    Lebanon's very high population density has been increasing since the end of the civil war in the early 1990s reaching 416.36 people per square kilometer. Furthermore, the influx of refugees from conflicts in the region has increased the resident population significantly. All these are exerting pressure on the country's natural resources, pushing the Lebanese to convert more forest and agricultural land into roads, buildings and houses. This has led to a building boom and rapid urbanization which in turn has created a demand for construction material - mainly rock, gravel, sand, etc. nearly all of which are locally acquired through quarrying to the tune of three million cubic meters annually. This boom has been interrupted by a war with Israel in 2006 which resulted in thousands of tonnes of debris. The increase in population has also led to an increase in solid waste generation with 1.57 million tonnes of solid waste generated in Lebanon per year. The combination of construction, demolition and excavation (CDE) waste along with the increase in solid waste generation has put a major stress on the country and on the management of its solid waste. Compounding this problem are the issues of quarries closure and rehabilitation and a decrease in forest and vegetative cover. The on-going research reported in this paper aims to provide an integrated solution to the stated problem by developing a "soil mix" derived from a mélange of the organic matter of the solid waste (compost), the CDE waste, and soil. Excavation and construction debris were ground to several sizes and mixed with compost and soil at different ratios. Replicates of these mixes and a set of control (regular soil) were used. In this mix, native and indicator plants are planted (in pots) from which the most productive mix will be selected for further testing at field level in later experiments. The plant species used are Mathiolla crassifolia, a native Lebanese plant and Zea mays (Corn), which is commonly

  3. Analysis of Radioactive Releases During Proposed Demolition Activities for the 224-U and 224-UA Buildings

    SciTech Connect

    Napier, Bruce A.; Rishel, Jeremy P.; Droppo, James G.

    2009-03-31

    Atmospheric dispersion modeling has been conducted in support of the demolition of the 224-U and 224-UA buildings using estimated release rates to provide information on the location and levels of radioactive contamination that may be expected. The facilities surrounding the UO3 plant have the potential to affect dispersion patterns through various meteorological phenomena, including building wake effects. Hourly meteorological data collected over a 5-year period were used to examine the effects of wind speed, direction, and stability on projected concentrations of contaminants in air and deposited on nearby surfaces. The modeling results indicate that the radiological exposures from the planned demolition efforts will be below the designated limits for air and soil exposures.

  4. A Sandia National Laboratories decontamination and demolition success story

    SciTech Connect

    Miller, D.R.; Barber, D.S.; Lipka, G.

    1994-11-01

    Sandia National Laboratories/New Mexico (SNL/NM) has established a formal facility assessment, decontamination and demolition oversight process with the goal of ensuring that excess or contaminated facilities are managed in a cost-effective manner that is protective of human health and the environment. The decontamination and demolition process is designed so that all disciplines are consulted and have input from the initiation of a project. The committee consists of all essential Environmental, Safety and Health (ES and H) and Facilities disciplines. The interdisciplinary-team approach has provided a mechanism that verifies adequate building and site assessment activities are conducted. This approach ensures that wastes generated during decontamination and demolition activities are handled and disposed according to Department of Energy (DOE), Federal, state, and local requirements. Because of the comprehensive nature of the SNL decontamination and demolition process, the strategy can be followed for demolition, renovation and new construction projects, regardless of funding source. An overview of the SNL/NM decontamination and demolition process is presented through a case study which demonstrates the practical importance of the formal process.

  5. 24 CFR 247.10 - Inapplicability to substantial rehabilitation or demolition; right of disposition unimpaired.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... rehabilitation or demolition; right of disposition unimpaired. 247.10 Section 247.10 Housing and Urban... SUBSIDIZED AND HUD-OWNED PROJECTS HUD-Owned Projects § 247.10 Inapplicability to substantial rehabilitation... of substantial rehabilitation or demolition. Nothing in this subpart should be construed to affect...

  6. Air Dispersion Modeling of Radioactive Releases During Proposed PFP Complex Demolition Activities

    SciTech Connect

    Napier, Bruce A.; Droppo, James G.; Rishel, Jeremy P.

    2011-01-11

    This report is part of the planning process for the demolition of the 234-5Z, 236-Z, 242-Z, and 291-Z-1 structures at the Plutonium Finishing Plant (PFP) on the Hanford Site. Pacific Northwest National Laboratory (PNNL) supports the U.S. Department of Energy (DOE) and the CH2M HILL Plateau Remediation Company (CHPRC) demolition planning effort by making engineering estimates of potential releases for various potential demolition alternatives. This report documents an analysis considering open-air demolition using standard techniques. It does not document any decisions about the decommissioning approaches; it is expected that this report will be revisited as the final details of the demolition are developed.

  7. Recovery Act Weekly Video: Upper ALE Building Demolition

    ScienceCinema

    None

    2016-07-12

    CH2MHILL Plateau Remediation Company demolition of 6652C Space Science Laboratory. The largest building atop Rattlesnake Mountain, the laboratory served as a nightly radar patrol center as well as a barracks. The Recovery Act funded project is helping reduce the site footprint.

  8. 29 CFR 1926.859 - Mechanical demolition.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 29 Labor 8 2012-07-01 2012-07-01 false Mechanical demolition. 1926.859 Section 1926.859 Labor Regulations Relating to Labor (Continued) OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION, DEPARTMENT OF LABOR (CONTINUED) SAFETY AND HEALTH REGULATIONS FOR CONSTRUCTION Demolition § 1926.859 Mechanical demolition....

  9. 29 CFR 1926.859 - Mechanical demolition.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 29 Labor 8 2010-07-01 2010-07-01 false Mechanical demolition. 1926.859 Section 1926.859 Labor Regulations Relating to Labor (Continued) OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION, DEPARTMENT OF LABOR (CONTINUED) SAFETY AND HEALTH REGULATIONS FOR CONSTRUCTION Demolition § 1926.859 Mechanical demolition....

  10. 29 CFR 1926.859 - Mechanical demolition.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 29 Labor 8 2013-07-01 2013-07-01 false Mechanical demolition. 1926.859 Section 1926.859 Labor Regulations Relating to Labor (Continued) OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION, DEPARTMENT OF LABOR (CONTINUED) SAFETY AND HEALTH REGULATIONS FOR CONSTRUCTION Demolition § 1926.859 Mechanical demolition....

  11. 29 CFR 1926.859 - Mechanical demolition.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 29 Labor 8 2011-07-01 2011-07-01 false Mechanical demolition. 1926.859 Section 1926.859 Labor Regulations Relating to Labor (Continued) OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION, DEPARTMENT OF LABOR (CONTINUED) SAFETY AND HEALTH REGULATIONS FOR CONSTRUCTION Demolition § 1926.859 Mechanical demolition....

  12. 29 CFR 1926.859 - Mechanical demolition.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 29 Labor 8 2014-07-01 2014-07-01 false Mechanical demolition. 1926.859 Section 1926.859 Labor Regulations Relating to Labor (Continued) OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION, DEPARTMENT OF LABOR (CONTINUED) SAFETY AND HEALTH REGULATIONS FOR CONSTRUCTION Demolition § 1926.859 Mechanical demolition....

  13. Open air demolition of facilities highly contaminated with plutonium

    SciTech Connect

    Lloyd, E.R.; Lackey, M.B.; Stevens, J.M.; Zinsli, L.C.

    2007-07-01

    The demolition of highly contaminated plutonium buildings usually is a long and expensive process that involves decontaminating the building to near free- release standards and then using conventional methods to remove the structure. It doesn't, however, have to be that way. Fluor has torn down buildings highly contaminated with plutonium without excessive decontamination. By removing the select source term and fixing the remaining contamination on the walls, ceilings, floors, and equipment surfaces; open-air demolition is not only feasible, but it can be done cheaper, better (safer), and faster. Open-air demolition techniques were used to demolish two highly contaminated buildings to slab-on-grade. These facilities on the Department of Energy's Hanford Site were located in, or very near, compounds of operating nuclear facilities that housed hundreds of people working on a daily basis. To keep the facilities operating and the personnel safe, the projects had to be creative in demolishing the structures. Several key techniques were used to control contamination and keep it within the confines of the demolition area: spraying fixatives before demolition; applying fixative and misting with a fine spray of water as the buildings were being taken down; and demolishing the buildings in a controlled and methodical manner. In addition, detailed air-dispersion modeling was done to establish necessary building and meteorological conditions and to confirm the adequacy of the proposed methods. Both demolition projects were accomplished without any spread of contamination outside the modest buffer areas established for contamination control. Furthermore, personnel exposure to radiological and physical hazards was significantly reduced by using heavy equipment rather than 'hands on' techniques. (authors)

  14. OPEN AIR DEMOLITION OF FACILITIES HIGHLY CONTAMINATED WITH PLUTONIUM

    SciTech Connect

    LLOYD, E.R.

    2007-05-31

    The demolition of highly contaminated plutonium buildings usually is a long and expensive process that involves decontaminating the building to near free- release standards and then using conventional methods to remove the structure. It doesn't, however, have to be that way. Fluor has torn down buildings highly contaminated with plutonium without excessive decontamination. By removing the select source term and fixing the remaining contamination on the walls, ceilings, floors, and equipment surfaces; open-air demolition is not only feasible, but it can be done cheaper, better (safer), and faster. Open-air demolition techniques were used to demolish two highly contaminated buildings to slab-on-grade. These facilities on the Department of Energy's Hanford Site were located in, or very near, compounds of operating nuclear facilities that housed hundreds of people working on a daily basis. To keep the facilities operating and the personnel safe, the projects had to be creative in demolishing the structures. Several key techniques were used to control contamination and keep it within the confines of the demolition area: spraying fixatives before demolition; applying fixative and misting with a fine spray of water as the buildings were being taken down; and demolishing the buildings in a controlled and methodical manner. In addition, detailed air-dispersion modeling was done to establish necessary building and meteorological conditions and to confirm the adequacy of the proposed methods. Both demolition projects were accomplished without any spread of contamination outside the modest buffer areas established for contamination control. Furthermore, personnel exposure to radiological and physical hazards was significantly reduced by using heavy equipment rather than ''hands on'' techniques.

  15. Progressively safer, cheaper demolition of Fernald

    SciTech Connect

    Robert Nichols; Norman Pennington

    2000-09-29

    Fluor Fernald, Inc. has been progressively improving Decontamination and Dismantlement (D&D) at the Department of Energy's Fernald Environmental Management Project by applying new technologies and better methodologies to the work. Demolition issues existed in the past that necessitated new or improved solutions to maintain worker safety, protect the environment and accomplish the work in a cost effective manner. Lessons learned from D&D of 80 structures has led to a systematic approach, which can be implemented in various D&D arenas. When facility production was halted, hold-up material and process residues remained in the process piping and components. Over 500,000 pounds of material was removed by workers who completed the tasks two years ahead of schedule, $7 million under budget and with an excellent safety record. This success was the result of detailed planning and irdision of lessons learned as work progressed from facility to facility. Work sequences were developed that reduced airborne contamination. Demolition of structures has been performed at Fernald by carefully selected and qualified subcontractors. Asbestos and lead abatement, equipment, piping and conduit removal, and structural demolition have been completed to progressively higher performance specifications developed by Fluor Fernald based on lessons learned during execution. Safety continues to be the primary consideration in performing potentially hazardous work. Technologies such as hydraulic shears have been developed and used to keep workers away from danger. A new technology, ''Cool Suits,'' has been demonstrated to help prevent heat stress when anti-contamination clothing is required in elevated temperature working conditions. For tall structures, implosion technologies have been employed with progressively improved results, Several other new technologies have been evaluated by Fluor Fernald and applied by subcontractors. The improved technologies included the oxy-gas torch, which uses

  16. Construction and demolition waste indicators.

    PubMed

    Mália, Miguel; de Brito, Jorge; Pinheiro, Manuel Duarte; Bravo, Miguel

    2013-03-01

    The construction industry is one of the biggest and most active sectors of the European Union (EU), consuming more raw materials and energy than any other economic activity. Furthermore, construction waste is the commonest waste produced in the EU. Current EU legislation sets out to implement construction and demolition waste (CDW) prevention and recycling measures. However it lacks tools to accelerate the development of a sector as bound by tradition as the building industry. The main objective of the present study was to determine indicators to estimate the amount of CDW generated on site both globally and by waste stream. CDW generation was estimated for six specific sectors: new residential construction, new non-residential construction, residential demolition, non-residential demolition, residential refurbishment, and non-residential refurbishment. The data needed to develop the indicators was collected through an exhaustive survey of previous international studies. The indicators determined suggest that the average composition of waste generated on site is mostly concrete and ceramic materials. Specifically for new residential and new non-residential construction the production of concrete waste in buildings with a reinforced concrete structure lies between 17.8 and 32.9 kg m(-2) and between 18.3 and 40.1 kg m(-2), respectively. For the residential and non-residential demolition sectors the production of this waste stream in buildings with a reinforced concrete structure varies from 492 to 840 kg m(-2) and from 401 to 768 kg/m(-2), respectively. For the residential and non-residential refurbishment sectors the production of concrete waste in buildings lies between 18.9 and 45.9 kg/m(-2) and between 18.9 and 191.2 kg/m(-2), respectively. PMID:23315370

  17. Analysis of Radioactive Releases During Proposed Demolition Activities for the 224-U and 224-UA Buildings - Addendum

    SciTech Connect

    Napier, Bruce A.; Rishel, Jeremy P.; Droppo, James G.; Joyce, Kevin E.; Strom, Daniel J.

    2010-12-21

    A post-demolition modeling analysis is conducted that compares during-demolition atmospheric concentration monitoring results with modeling results based on the actual meteorological conditions during the demolition activities. The 224-U and 224-UA Buildings that were located in the U-Plant UO3 complex in the 200 West Area of the Hanford Site were demolished during the summer of 2010. These facilities converted uranyl nitrate hexahydrate (UNH), a product of Hanford’s Plutonium-Uranium Extraction (PUREX) Plant, into uranium trioxide (UO3). This report is an addendum to a pre-demolition emission analysis and air dispersion modeling effort that was conducted for proposed demolition activities for these structures.

  18. Y-12 Construction/Demolition Landfill VII: Permit application: Part 1 and 2

    SciTech Connect

    Not Available

    1992-04-01

    The United States Department of Energy (DOE) has three major operating facilities on the DOE Oak Ridge Reservation (ORR) at Oak Ridge, Tennessee: the Y-12 Plant, the K-25 Site, and the Oak Ridge National Laboratory (ORNL). All facilities are managed by Martin Marietta Energy System, Inc. (Energy Systems) for the DOE. Operations associated with the DOE energy research and production facilities at Oak Ridge result in the production of several types of waste materials. Disposal of solid waste (as defined in the Solid Waste Processing and Disposal Rules for Tennessee) in disposal facilities operated by the Y-12 Plant is the responsibility of Y-12 Waste Management Division (WMD). The WMD is proposing to develop a facility that will include two new disposal units: one for construction/demolition waste and spoil and one for industrial solid waste. This report contains construction drawings for the project.

  19. AVLIS Production Plant Project Management Plan

    SciTech Connect

    Not Available

    1984-11-15

    The AVLIS Production Plant is designated as a Major System Acquisition (in accordance with DOE Order 4240.IC) to deploy Atomic Vapor Laser Isotope Separation (AVLIS) technology at the Oak Ridge, Tennessee site, in support of the US Uranium Enrichment Program. The AVLIS Production Plant Project will deploy AVLIS technology by performing the design, construction, and startup of a production plant that will meet capacity production requirements of the Uranium Enrichment Program. The AVLIS Production Plant Project Management Plan has been developed to outline plans, baselines, and control systems to be employed in managing the AVLIS Production Plant Project and to define the roles and responsibilities of project participants. Participants will develop and maintain detailed procedures for implementing the management and control systems in agreement with this plan. This baseline document defines the system that measures work performed and costs incurred. This plan was developed by the AVLIS Production Plant Project staff of Martin Marietta Energy Systems, Inc. and Lawrence Livermore National Laboratory in accordance with applicable DOE directives, orders and notices. 38 figures, 19 tables.

  20. Project Work on Plant Roots.

    ERIC Educational Resources Information Center

    Devonald, V. G.

    1986-01-01

    Methods of investigating plant root growth developed for research purposes can be adopted for student use. Investigations of the effect of water table level and of ethylene concentration are described, and techniques of measuring root growth are explained. (Author/ML)

  1. DEMOLITION OF HANFORDS 233-S PLUTONIUM CONCENTRATION FACILITY

    SciTech Connect

    BERLIN, G.T.

    2004-01-21

    This paper describes the technical approach being used to demolish a plutonium-contaminated processing facility at the Hanford Site. This project represents the first open-air demolition of a highly-contaminated plutonium facility at the Hanford Site. This project may also represent one of the first plutonium facilities in the DOE complex to be demolished without first decontaminating surfaces to near ''free release'' standards. Demolition of plutonium contamination structures, if not properly managed, can subject cleanup personnel and the environment to significant risk. However, with proper sequencing and innovative use of commercially-available equipment, materials, and services, this project is demonstrating that a plutonium processing facility can be demolished while avoiding the need to perform extensive decontamination or construct large enclosures. The project is utilizing an excavator with purpose-built concrete shears, diamond circular saws, water misting and fogging equipment, specialized fixatives and dust suppressant mixtures, conventional mobile crane and rigging services, and near real-time modeling of meteorological and radiological conditions. Between the months of October and December 2003, approximately 85 percent of the footprint of the 233-S Facility had been demolished and properly disposed. Demolition of the remaining and more technically-challenging portion of the facility is expected to be completed by April 2004.

  2. VIEW OF RBC (REFINED BICARBONATE) BUILDING LOOKING NORTHEAST. DEMOLITION IN ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    VIEW OF RBC (REFINED BICARBONATE) BUILDING LOOKING NORTHEAST. DEMOLITION IN PROGRESS. "ARM & HAMMER BAKING SODA WAS MADE HERE FOR OVER 50 YEARS AND THEN SHIPPED ACROSS THE STREET TO THE CHURCH & DWIGHT PLANT ON WILLIS AVE. (ON THE RIGHT IN THIS PHOTO). LAYING ON THE GROUND IN FRONT OF C&D BUILDING IS PART OF AN RBC DRYING TOWER. - Solvay Process Company, Refined Bicarbonate Building, Between Willis & Milton Avenues, Solvay, Onondaga County, NY

  3. Forecast Inaccuracies in Power Plant Projects From Project Managers' Perspectives

    NASA Astrophysics Data System (ADS)

    Sanabria, Orlando

    Guided by organizational theory, this phenomenological study explored the factors affecting forecast preparation and inaccuracies during the construction of fossil fuel-fired power plants in the United States. Forecast inaccuracies can create financial stress and uncertain profits during the project construction phase. A combination of purposeful and snowball sampling supported the selection of participants. Twenty project managers with over 15 years of experience in power generation and project experience across the United States were interviewed within a 2-month period. From the inductive codification and descriptive analysis, 5 themes emerged: (a) project monitoring, (b) cost control, (c) management review frequency, (d) factors to achieve a precise forecast, and (e) factors causing forecast inaccuracies. The findings of the study showed the factors necessary to achieve a precise forecast includes a detailed project schedule, accurate labor cost estimates, monthly project reviews and risk assessment, and proper utilization of accounting systems to monitor costs. The primary factors reported as causing forecast inaccuracies were cost overruns by subcontractors, scope gaps, labor cost and availability of labor, and equipment and material cost. Results of this study could improve planning accuracy and the effective use of resources during construction of power plants. The study results could contribute to social change by providing a framework to project managers to lessen forecast inaccuracies, and promote construction of power plants that will generate employment opportunities and economic development.

  4. Recycling of rubble from building demolition for low-shrinkage concretes.

    PubMed

    Corinaldesi, Valeria; Moriconi, Giacomo

    2010-04-01

    In this project concrete mixtures were prepared that were characterized by low ductility due to desiccation by using debris from building demolition, which after a suitable treatment was used as aggregate for partial replacement of natural aggregates. The recycled aggregate used came from a recycling plant, in which rubble from building demolition was selected, crushed, cleaned, sieved, and graded. Such aggregates are known to be more porous as indicated by the Saturated Surface Dry (SSD) moisture content. The recycled concrete used as aggregates were added to the concrete mixture in order to study their influence on the fresh and hardened concrete properties. They were added either after water pre-soaking or in dry condition, in order to evaluate the influence of moisture in aggregates on the performance of concrete containing recycled aggregate. In particular, the effect of internal curing, due to the use of such aggregates, was studied. Concrete behavior due to desiccation under dehydration was studied by means of both drying shrinkage test and German angle test, through which shrinkage under the restrained condition of early age concrete can be evaluated. PMID:20022737

  5. Recycling of rubble from building demolition for low-shrinkage concretes.

    PubMed

    Corinaldesi, Valeria; Moriconi, Giacomo

    2010-04-01

    In this project concrete mixtures were prepared that were characterized by low ductility due to desiccation by using debris from building demolition, which after a suitable treatment was used as aggregate for partial replacement of natural aggregates. The recycled aggregate used came from a recycling plant, in which rubble from building demolition was selected, crushed, cleaned, sieved, and graded. Such aggregates are known to be more porous as indicated by the Saturated Surface Dry (SSD) moisture content. The recycled concrete used as aggregates were added to the concrete mixture in order to study their influence on the fresh and hardened concrete properties. They were added either after water pre-soaking or in dry condition, in order to evaluate the influence of moisture in aggregates on the performance of concrete containing recycled aggregate. In particular, the effect of internal curing, due to the use of such aggregates, was studied. Concrete behavior due to desiccation under dehydration was studied by means of both drying shrinkage test and German angle test, through which shrinkage under the restrained condition of early age concrete can be evaluated.

  6. 36 CFR 401.11 - Demolition criteria.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 36 Parks, Forests, and Public Property 3 2014-07-01 2014-07-01 false Demolition criteria. 401.11 Section 401.11 Parks, Forests, and Public Property AMERICAN BATTLE MONUMENTS COMMISSION MONUMENTS AND MEMORIALS § 401.11 Demolition criteria. As authorized by the provisions of 36 U.S.C. 2106(e), the...

  7. 36 CFR 401.11 - Demolition criteria.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 36 Parks, Forests, and Public Property 3 2013-07-01 2012-07-01 true Demolition criteria. 401.11 Section 401.11 Parks, Forests, and Public Property AMERICAN BATTLE MONUMENTS COMMISSION MONUMENTS AND MEMORIALS § 401.11 Demolition criteria. As authorized by the provisions of 36 U.S.C. 2106(e), the...

  8. 36 CFR 401.11 - Demolition criteria.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 36 Parks, Forests, and Public Property 3 2010-07-01 2010-07-01 false Demolition criteria. 401.11 Section 401.11 Parks, Forests, and Public Property AMERICAN BATTLE MONUMENTS COMMISSION MONUMENTS AND MEMORIALS § 401.11 Demolition criteria. As authorized by the provisions of 36 U.S.C. 2106(e), the...

  9. 36 CFR 401.11 - Demolition criteria.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 36 Parks, Forests, and Public Property 3 2011-07-01 2011-07-01 false Demolition criteria. 401.11 Section 401.11 Parks, Forests, and Public Property AMERICAN BATTLE MONUMENTS COMMISSION MONUMENTS AND MEMORIALS § 401.11 Demolition criteria. As authorized by the provisions of 36 U.S.C. 2106(e), the...

  10. 36 CFR 401.11 - Demolition criteria.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 36 Parks, Forests, and Public Property 3 2012-07-01 2012-07-01 false Demolition criteria. 401.11 Section 401.11 Parks, Forests, and Public Property AMERICAN BATTLE MONUMENTS COMMISSION MONUMENTS AND MEMORIALS § 401.11 Demolition criteria. As authorized by the provisions of 36 U.S.C. 2106(e), the...

  11. ASBESTOS RELEASE DURING BUILDING DEMOLITION ACTIVITIES

    EPA Science Inventory

    The U.S. Environmental Protection Agency's (EPA) Risk Reduction Engineering Laboratory (RREL) monitored block-wide building demolition and debris disposal activities at Santa Cruz and Watsonsville, California following the 1989 earthquake; an implosion demolition of a 26-story bu...

  12. Recovery Act Weekly Video: 200 Area Asbestos Removal, U-Ancillary Demolition, 200 West Transfer Building Footings

    SciTech Connect

    2010-01-01

    A weekly update of the Recovery Act at work. Demolition of U-Ancillary that was contaminated with uranium and asbestos as well as removing asbestos from the Steam Generation Plant in the 200 East Area.

  13. Recovery Act Weekly Video: 200 Area Asbestos Removal, U-Ancillary Demolition, 200 West Transfer Building Footings

    ScienceCinema

    None

    2016-07-12

    A weekly update of the Recovery Act at work. Demolition of U-Ancillary that was contaminated with uranium and asbestos as well as removing asbestos from the Steam Generation Plant in the 200 East Area.

  14. Distribution of materials in construction and demolition waste in Portugal.

    PubMed

    Coelho, André; de Brito, Jorge

    2011-08-01

    It may not be enough simply to know the global volume of construction and demolition waste (CDW) generated in a certain region or country if one wants to estimate, for instance, the revenue accruing from separating several types of materials from the input entering a given CDW recycling plant. A more detailed determination of the distribution of the materials within the generated CDW is needed and the present paper addresses this issue, distinguishing different buildings and types of operation (new construction, retrofitting and demolition). This has been achieved by measuring the materials from buildings of different ages within the Portuguese building stock, and by using direct data from demolition/retrofitting sites and new construction average values reported in the literature. An attempt to establish a benchmark with other countries is also presented. This knowledge may also benefit industry management, especially that related to CDW recycling, helping to optimize procedures, equipment size and operation and even industrial plant spatial distribution. In an extremely competitive market, where as in Portugal low-tech and high environmental impact procedures remain the norm in the construction industry (in particular, the construction waste industry), the introduction of a successful recycling industry is only possible with highly optimized processes and based on a knowledge-based approach to problems. PMID:20498131

  15. Distribution of materials in construction and demolition waste in Portugal.

    PubMed

    Coelho, André; de Brito, Jorge

    2011-08-01

    It may not be enough simply to know the global volume of construction and demolition waste (CDW) generated in a certain region or country if one wants to estimate, for instance, the revenue accruing from separating several types of materials from the input entering a given CDW recycling plant. A more detailed determination of the distribution of the materials within the generated CDW is needed and the present paper addresses this issue, distinguishing different buildings and types of operation (new construction, retrofitting and demolition). This has been achieved by measuring the materials from buildings of different ages within the Portuguese building stock, and by using direct data from demolition/retrofitting sites and new construction average values reported in the literature. An attempt to establish a benchmark with other countries is also presented. This knowledge may also benefit industry management, especially that related to CDW recycling, helping to optimize procedures, equipment size and operation and even industrial plant spatial distribution. In an extremely competitive market, where as in Portugal low-tech and high environmental impact procedures remain the norm in the construction industry (in particular, the construction waste industry), the introduction of a successful recycling industry is only possible with highly optimized processes and based on a knowledge-based approach to problems.

  16. Saguaro power plant solar repowering project

    SciTech Connect

    Not Available

    1980-03-01

    The subsystem characteristics, design requirements, and system environmental requirements for the Saguaro Power Plant Solar Repowering Project are defined. The plant conceptual design, performance, and economic data to be provided for the solar additions are identified as well as certain design data for the existing plant. All of the 115 MWe net No. 1 steam-Rankine unit of the Saguaro station is to be repowered. The receiver heat transport fluid is draw salt (60% sodium nitrate and 40% potassium nitrate) that is also used to provide 4 hours of sensible heat storage. The receiver is quad-cavity type, and there is a field of 10,500 second generation heliostats. (LEW)

  17. Final Demolition and Disposition of 209-E Critical Mass Laboratory - 12267

    SciTech Connect

    Woolery, Wade; Dodd, Edwin III

    2012-07-01

    The 209-E Critical Mass Laboratory was constructed in 1960 to provide a heavy shielded reactor room where quantities of plutonium or uranium in solution could be brought to near-critical configurations under carefully controlled and monitored conditions. In the late 1980's, the responsible contractor, Pacific Northwest National Laboratory (PNNL), was directed by the Department of Energy (DOE) to prepare the facility for unoccupied status. The facility was demolished under a Removal Action Work Plan pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). The funding for this project was provided by the American Recovery and Reinvestment Act (ARRA). The primary rooms of concern with regards to contamination in 209-E facility, which is over 9,000 square feet, are the criticality assembly room (CAR), the mix room, and the change room. The CAR contained two reactor hoods (HO-140 and HO-170), which each had a high efficiency particulate air (HEPA) filter system. The CAR contained 13 tanks ranging from 38 L (10 gal) to 401 L (106 gal). Tanks TK-109 and TK-110 are below grade, and were removed as part of this demolition and disposition remedy. Nonradiological and radiological hazardous substances were removed, decontaminated, or fixed in place, prior to demolition. Except for the removal of below grade tanks TK-109 and TK-110, the facility was demolished to slab-on-grade. PNNL performed stabilization and deactivation activities that included removal of bulk fissile material and chemicals, flushing tanks, stabilizing contamination within gloveboxes and hoods, and packaging and removing waste. The removal of the contaminated plutonium equipment and materials from the 209E facility presented a number of challenges similar in nature to those associated with the inventory reduction and cleanup activities at the Plutonium Finishing Plant. Although there were no bulk fissile materials or chemicals within the facility, there were

  18. Parts of Plants. Hawaii Nature Study Project.

    ERIC Educational Resources Information Center

    Hawaii Univ., Honolulu. Curriculum Research and Development Group.

    This teaching guide is one of a series developed by the Curriculum Research and Development Group at the University of Hawaii. The program is laboratory and field oriented for elementary students. The focus of study for the project is the plant and animal life and the physical components of the Hawaiian environment, and their ecological…

  19. AVLIS production plant project schedule and milestones

    SciTech Connect

    Not Available

    1984-11-15

    An AVLIS Production Plant Deployment Schedule for the engineering, procurement, and construction for both the Initial Increment of Production and the fully Activated Plant, has been developed by the project team consisting of Lawrence Livermore National Laboratory, Martin Marietta Energy Systems, Inc. with architect-engineer support from Bechtel National, Inc., Stone and Webster Engineering Corporation, and Westinghouse Corporation. The initial deployment phase consists of six separators modules and the three laser power amplifier modules consistent with the FY84 reference design with a name plate capacity of 5 million separative work units/yr followed by a full plant activation to approximately 13 million separative work units/yr. The AVLIS Production Plant project team's strategy for deployment schedule analysis focused on three schedule options: engineering limited schedule; authorization limited schedule; and funding limited project schedule. The three deployment schedule options developed by AVLIS project team have been classified in ranges such as an optimistic, rapid/moderate, or moderate/pessimistic based on the probability of meeting the individual schedule option's major milestones or program objectives of enriching uranium by the AVLIS process in an effective cost and schedule manner. 47 figures, 7 tables.

  20. Report on Hawaii Geothermal Power Plant Project

    SciTech Connect

    Not Available

    1983-06-01

    The report describes the design, construction, and operation of the Hawaii Geothermal Generator Project. This power plant, located in the Puna District on the island of Hawaii, produces three megawatts of electricity from the steam phase of a geothermal well. (ACR)

  1. Report on Hawaii geothermal power plant project

    SciTech Connect

    Not Available

    1983-06-01

    The Hawaii Geothermal Generator Project is the first power plant in the State of Hawaii to be powered by geothermal energy. This plant, which is located in the Puna District on the Island of Hawaii, produces three (3) megawatts of electricity utilizing the steam phase from the geothermal well. This project represents the climax of the geophysical research efforts going on for two decades in the Hawaiian Islands which resulted in the discovery of a significant reservoir of geothermal energy which could be put to practical use. In 1978 the Department of Energy, in conjunction with the State of Hawaii, entered into negotiations to design and build a power plant. The purpose and objective of this plant was to demonstrate the feasibility of constructing and operating a geothermal power plant located in a remote volcanically active area. A contract was signed in mid 1978 between the Research Corporation of the University of Hawaii (RCUH) and the Department of Energy (DOE). To date, the DOE has provided 8.3 million dollars with the State of Hawaii and others contributing 2.1 million dollars. The cost of the project exceeded its original estimates by approximately 25%. These increases in cost were principally contributed to the higher cost for construction than was originally estimated. Second, the cost of procuring the various pieces of equipment exceed their estimates by 10 to 20 percent, and third, the engineering dollar per man hour rose 20 to 25 percent.

  2. 6. DEMOLITION OF HONEYWOOD MILL/ORIGINAL DAM NO. 5 POWER HOUSE. ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    6. DEMOLITION OF HONEYWOOD MILL/ORIGINAL DAM NO. 5 POWER HOUSE. DERRICK MOVING RUBBLE TO BE CRUSHED AND USED AS AGGREGATE IN CONCRETE FOR FOUNDATION OF NEW PLANT, c. 1917. - Dam No. 5 Hydroelectric Plant, On Potomac River, Hedgesville, Berkeley County, WV

  3. 24 CFR 970.15 - Specific criteria for HUD approval of demolition requests.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... environmental conditions as determined by HUD environmental review in accord with 24 CFR part 50, which... criteria for disapproval under 24 CFR 970.29. An application for the demolition of all or a portion of a public housing project must certify that the project: (1) Is obsolete as to physical condition,...

  4. OPERATIONAL LIMITATIONS FOR DEMOLITION OF A HIGHLY ALPHA CONTAMINATED BUILDING MODLES VERSUS MEASURED AIR & SURFACE ACTIVITY CONCENTRATIONS

    SciTech Connect

    LLOYD, E.R.

    2006-11-02

    The demolition of a facility historically used for processing and handling transuranic materials is considered. Residual alpha emitting radionuclide contamination poses an exposure hazard if released to the local environment during the demolition. The process of planning for the demolition of this highly alpha contaminated building, 232-Z, included a predemolition modeling analysis of potential exposures. Estimated emission rates were used as input to an air dispersion model to estimate frequencies of occurrence of peak air and surface exposures. Postdemolition modeling was also conducted, based on the actual demolition schedule and conditions. The modeling results indicated that downwind deposition is the main operational limitation for demolition of a highly alpha-contaminated building. During the demolition of 232-Z, airborne radiation and surface contamination were monitored. The resultant non-detect monitoring results indicate a significant level of conservatism in the modeled results. This comparison supports the use of more realistic assumption in the estimating emission rates. The resultant reduction in modeled levels of potential exposures has significant implications in terms of the projected costs of demolition of such structures.

  5. Proceedings of a Topical Meeting On Small Scale Geothermal Power Plants and Geothermal Power Plant Projects

    SciTech Connect

    1986-02-12

    These proceedings describe the workshop of the Topical Meeting on Small Scale Geothermal Power Plants and Geothermal Power Plant Projects. The projects covered include binary power plants, rotary separator, screw expander power plants, modular wellhead power plants, inflow turbines, and the EPRI hybrid power system. Active projects versus geothermal power projects were described. In addition, a simple approach to estimating effects of fluid deliverability on geothermal power cost is described starting on page 119. (DJE-2005)

  6. Y-12 Construction/Demolition Landfill VII: Permit application: Part 1 and 2. Volume 2 [Engineering Materials

    SciTech Connect

    Not Available

    1992-04-01

    The United States Department of Energy (DOE) has three major operating facilities on the DOE Oak Ridge Reservation (ORR) at Oak Ridge, Tennessee: the Y-12 Plant, the K-25 Site, and the Oak Ridge National Laboratory (ORNL). All facilities are managed by Martin Marietta Energy System, Inc. (Energy Systems) for the DOE. Operations associated with the DOE energy research and production facilities at Oak Ridge result in the production of several types of waste materials. Disposal of solid waste (as defined in the Solid Waste Processing and Disposal Rules for Tennessee) in disposal facilities operated by the Y-12 Plant is the responsibility of Y-12 Waste Management Division (WMD). The WMD is proposing to develop a facility that will include two new disposal units: one for construction/demolition waste and spoil and one for industrial solid waste. This report contains construction drawings for the project.

  7. Molten wax as a dust control agent for demolition of facilities

    SciTech Connect

    Carter, E.E.; Welty, B.D.

    2007-07-01

    Molten wax shows considerable promise as a fixative and dust control agent in demolition of radioactively contaminated facilities. Sticky molten wax, modified with special surfactants and wetting agents, is capable of not only coating materials but also penetrating into friable or dusty materials and making them incapable of becoming airborne during demolition. Wax also shows significant promise for stabilization of waste residuals that may be contained in buildings undergoing demolition. Some of the building materials that have been tested to date include concrete, wood, sheet rock, fiber insulation, lime, rock, and paper. Protective clothing, clay, sand, sulfur, and bentonite clay have been tested as surrogates for certain waste materials that may be encountered during building demolition. The paper describes several potential applications of molten wax for dust control in demolition of radioactive contaminated facilities. As a case-study, this paper describes a research test performed for a pipeline closure project being completed by the Idaho Cleanup Project at the Idaho National Laboratory. The project plans to excavate and remove a section of buried Duriron drain piping containing highly radioactive and friable and 'flighty' waste residuals. A full-scale pipeline mockup containing simulated waste was buried in sand to simulate the direct buried subsurface condition of the subject piping. The pipeline was pre-heated by drawing hot air through the line with a HEPA vacuum blower unit. Molten wax was pumped into the line and allowed to cool. The line was then broken apart in various places to evaluate the permeation performance of the wax. The wax fully permeated all the surrogate materials rendering them non-friable with a consistency similar to modeling clay. Based on the performance during the mockup, it is anticipated that the wax will be highly effective in controlling the spread of radiological contamination during pipe demolition activities. (authors)

  8. Leaching behaviour of hazardous demolition waste.

    PubMed

    Roussat, Nicolas; Méhu, Jacques; Abdelghafour, Mohamed; Brula, Pascal

    2008-11-01

    Demolition wastes are generally disposed of in unlined landfills for inert waste. However, demolition wastes are not just inert wastes. Indeed, a small fraction of demolition waste contains components that are hazardous to human health and the environment, e.g., lead-based paint, mercury-contained in fluorescent lamps, treated wood, and asbestos. The objective of this study is to evaluate the release potential of pollutants contained in these hazardous components when they are mixed with inert wastes in unlined landfills. After identification of the different building products which can contain hazardous elements and which can be potentially pollutant in landfill scenario, we performed leaching tests using three different lysimeters: one lysimeter containing only inert wastes and two lysimeters containing inert wastes mixed with hazardous demolition wastes. The leachates from these lysimeters were analysed (heavy metals, chlorides, sulphates fluoride, DOC (Dissolved Organic Carbon), phenol index, and PAH). Finally, we compared concentrations and cumulative releases of elements in leachates with the limits values of European regulation for the acceptance of inert wastes at landfill. Results indicate that limit values are exceeded for some elements. We also performed a percolation column test with only demolition hazardous wastes to evaluate the specific contribution of these wastes in the observed releases. PMID:18160273

  9. 24 CFR 970.27 - De minimis exception to demolition requirements.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... demolished unit must be used for meeting the service or other needs of public housing residents (use of space... DEVELOPMENT (CONTINUED) OFFICE OF ASSISTANT SECRETARY FOR PUBLIC AND INDIAN HOUSING, DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT PUBLIC HOUSING PROGRAM-DEMOLITION OR DISPOSITION OF PUBLIC HOUSING PROJECTS §...

  10. HEAVY METALS IN RECOVERED FINES FOR CONSTRUCTION AND DEMOLITION DEBRIS RECYCLING FACILITIES IN FLORIDA

    EPA Science Inventory

    A major product recovered from the processing and recycling of construction and demolition (C&D) debris is screened soil, also referred to as fines. A proposed reuse option for C&D debris fines is fill material, typically in construction projects as a substitute for natural soil....

  11. 24 CFR 969.107 - HUD approval of demolition or disposition before ACC expiration.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... expiration. This part is not intended to preclude or restrict the demolition or disposition of a project pursuant to HUD approval in accordance with 24 CFR part 970. Subject to the requirements of 24 CFR part 970... disposition before ACC expiration. 969.107 Section 969.107 Housing and Urban Development REGULATIONS...

  12. 24 CFR 969.107 - HUD approval of demolition or disposition before ACC expiration.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... expiration. This part is not intended to preclude or restrict the demolition or disposition of a project pursuant to HUD approval in accordance with 24 CFR part 970. Subject to the requirements of 24 CFR part 970... disposition before ACC expiration. 969.107 Section 969.107 Housing and Urban Development REGULATIONS...

  13. 24 CFR 969.107 - HUD approval of demolition or disposition before ACC expiration.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... expiration. This part is not intended to preclude or restrict the demolition or disposition of a project pursuant to HUD approval in accordance with 24 CFR part 970. Subject to the requirements of 24 CFR part 970... disposition before ACC expiration. 969.107 Section 969.107 Housing and Urban Development REGULATIONS...

  14. 29 CFR 1926.860 - Selective demolition by explosives.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... 29 Labor 8 2010-07-01 2010-07-01 false Selective demolition by explosives. 1926.860 Section 1926.860 Labor Regulations Relating to Labor (Continued) OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION... Selective demolition by explosives. Selective demolition by explosives shall be conducted in accordance...

  15. 29 CFR 1926.860 - Selective demolition by explosives.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... 29 Labor 8 2012-07-01 2012-07-01 false Selective demolition by explosives. 1926.860 Section 1926.860 Labor Regulations Relating to Labor (Continued) OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION... Selective demolition by explosives. Selective demolition by explosives shall be conducted in accordance...

  16. 29 CFR 1926.860 - Selective demolition by explosives.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... 29 Labor 8 2014-07-01 2014-07-01 false Selective demolition by explosives. 1926.860 Section 1926.860 Labor Regulations Relating to Labor (Continued) OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION... Selective demolition by explosives. Selective demolition by explosives shall be conducted in accordance...

  17. 29 CFR 1926.860 - Selective demolition by explosives.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... 29 Labor 8 2013-07-01 2013-07-01 false Selective demolition by explosives. 1926.860 Section 1926.860 Labor Regulations Relating to Labor (Continued) OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION... Selective demolition by explosives. Selective demolition by explosives shall be conducted in accordance...

  18. 29 CFR 1926.860 - Selective demolition by explosives.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... 29 Labor 8 2011-07-01 2011-07-01 false Selective demolition by explosives. 1926.860 Section 1926.860 Labor Regulations Relating to Labor (Continued) OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION... Selective demolition by explosives. Selective demolition by explosives shall be conducted in accordance...

  19. 26 CFR 1.280B-1 - Demolition of structures.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 26 Internal Revenue 3 2011-04-01 2011-04-01 false Demolition of structures. 1.280B-1 Section 1... (CONTINUED) INCOME TAXES (CONTINUED) Items Not Deductible § 1.280B-1 Demolition of structures. (a) In general. Section 280B provides that, in the case of the demolition of any structure, no deduction...

  20. 26 CFR 1.280B-1 - Demolition of structures.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 26 Internal Revenue 3 2014-04-01 2014-04-01 false Demolition of structures. 1.280B-1 Section 1... (CONTINUED) INCOME TAXES (CONTINUED) Items Not Deductible § 1.280B-1 Demolition of structures. (a) In general. Section 280B provides that, in the case of the demolition of any structure, no deduction...

  1. 26 CFR 1.280B-1 - Demolition of structures.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 26 Internal Revenue 3 2013-04-01 2013-04-01 false Demolition of structures. 1.280B-1 Section 1... (CONTINUED) INCOME TAXES (CONTINUED) Items Not Deductible § 1.280B-1 Demolition of structures. (a) In general. Section 280B provides that, in the case of the demolition of any structure, no deduction...

  2. PLUTONIUM FINISHING PLANT (PFP) STABILIZATION & PACKAGING PROJECT

    SciTech Connect

    GERBER, M.S.

    2004-01-14

    Fluor Hanford is pleased to submit the Plutonium Finishing Plant (PFP) Stabilization and Packaging Project (SPP) for consideration by the Project Management Institute as Project of the Year for 2004. The SPP thermally stabilized and/or packaged nearly 18 metric tons (MT) of plutonium and plutonium-bearing materials left in PFP facilities from 40 years of nuclear weapons production and experimentation. The stabilization of the plutonium-bearing materials substantially reduced the radiological risk to the environment and security concerns regarding the potential for terrorists to acquire the non-stabilized plutonium products for nefarious purposes. The work was done In older facilities which were never designed for the long-term storage of plutonium, and required working with materials that were extremely radioactive, hazardous, pyrophoric, and In some cases completely unique. I n some Instances, one-of-a-kind processes and equipment were designed, installed, and started up. The SPP was completed ahead of schedule, substantially beating all Interim progress milestone dates set by the Defense Nuclear Facilities Safety Board (DNFSB) and in the Hanford Site's Federal Facility Agreement and Consent Order (Tri-Party Agreement or TPA), and finished $1-million under budget.

  3. Bat Surveys of Retired Facilitiies Scheduled for Demolition by Washington Closure Hanford

    SciTech Connect

    Gano, K. A.; Lucas, J. G.; Lindsey, C. T.

    2011-06-30

    This project was conducted to evaluate buildings and facilities remaining in the Washington Closure Hanford (WCH) deactivation, decontamination, decommissioning, and demolition schedule for bat roost sites. The project began in spring of 2009 and was concluded in spring of 2011. A total of 196 buildings and facilities were evaluated for the presence of bat roosting sites. The schedule for the project was prioritized to accommodate the demolition schedule. As the surveys were completed, the results were provided to the project managers to facilitate planning and project completion. The surveys took place in the 300 Area, 400 Area, 100-H, 100-D, 100-N, and 100-B/C Area. This report is the culmination of all the bat surveys and summarizes the findings by area and includes recommended mitigation actions where bat roosts were found.

  4. Use of rubble from building demolition in mortars.

    PubMed

    Corinaldesi, V; Giuggiolini, M; Moriconi, G

    2002-01-01

    Because of increasing waste production and public concerns about the environment, it is desirable to recycle materials from building demolition. If suitably selected, ground, cleaned and sieved in appropriate industrial crushing plants, these materials can be profitably used in concrete. Nevertheless, the presence of masonry instead of concrete rubble is particularly detrimental to the mechanical performance and durability of recycled-aggregate concrete and the same negative effect is detectable when natural sand is replaced by fine recycled aggregate fraction. An alternative use of both masonry rubble and fine recycled material fraction could be in mortars. These could contain either recycled instead of natural sand or powder obtained by bricks crushing as partial cement substitution. In particular, attention is focused on the modification that takes place when either polypropylene or stainless steel fibers are added to these mortars. Polypropylene fibers are added in order to reduce shrinkage of mortars, stainless steel fibers for improving their flexural strength. The combined use of polypropylene fibers and fine recycled material from building demolition could allow the preparation of mortars showing good performance, in particular when coupled with bricks. Furthermore, the combined use of stainless steel fibers and mortars containing brick powder seems to be an effective way to guarantee a high flexural strength.

  5. Hanford Patrol Academy demolition sites closure plan

    SciTech Connect

    Not Available

    1993-09-30

    The Hanford Site is owned by the U.S. Government and operated by the U.S. Department of Energy, Richland Operations Office. Westinghouse Hanford Company is a major contractor to the U.S. Department of Energy, Richland Operations Office and serves as co-operator of the Hanford Patrol Academy Demolition Sites, the unit addressed in this paper. This document consists of a Hanford Facility Dangerous Waste Part A Permit Application, Form 3 (Revision 4), and a closure plan for the site. An explanation of the Part A Form 3 submitted with this closure plan is provided at the beginning of the Part A section. This Hanford Patrol Academy Demolition Sites Closure Plan submittal contains information current as of December 15, 1994.

  6. Green Residential Demolitions: Case Study of Vacant Land Reuse in Storm Water Management in Cleveland

    EPA Science Inventory

    The demolition process impacts how vacant land might be reused for storm water management. For five residential demolition sites (Cleveland, Ohio), an enhanced green demolition process was observed in 2012, and soil physical and hydrologic characteristics were measured predemolit...

  7. PERSPECTIVE VIEW OF THE STONEMASONRY STRUCTURE FOUND DURING DEMOLITION OF ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    PERSPECTIVE VIEW OF THE STONEMASONRY STRUCTURE FOUND DURING DEMOLITION OF DOUGLAS FIR INTERPRETIVE SITE, VIEW LOOKING NORTH. - Oregon State Forester's Office Complex, 2600 State Street, Salem, Marion, OR

  8. Five-megawatt geothermal-power pilot-plant project

    SciTech Connect

    Not Available

    1980-08-29

    This is a report on the Raft River Geothermal-Power Pilot-Plant Project (Geothermal Plant), located near Malta, Idaho; the review took place between July 20 and July 27, 1979. The Geothermal Plant is part of the Department of Energy's (DOE) overall effort to help commercialize the operation of electric power plants using geothermal energy sources. Numerous reasons were found to commend management for its achievements on the project. Some of these are highlighted, including: (a) a well-qualified and professional management team; (b) effective cost control, performance, and project scheduling; and (c) an effective and efficient quality-assurance program. Problem areas delineated, along with recommendations for solution, include: (1) project planning; (2) facility design; (3) facility construction costs; (4) geothermal resource; (5) drilling program; (6) two facility construction safety hazards; and (7) health and safety program. Appendices include comments from the Assistant Secretary for Resource Applications, the Controller, and the Acting Deputy Director, Procurement and Contracts Management.

  9. Electronic Leaf Project: An Innovative Method for Plant Identification.

    ERIC Educational Resources Information Center

    Hargis, Jace; Houston, Carolyn

    2000-01-01

    Explains a leaf project on the classification of plants for fifth through eighth grade students. Integrates technology into the unit and studies the subject as an electronic file. Recommends incorporation of metacognitive strategies into students' learning processes. (YDS)

  10. High Flux Isotopes Reactor (HFIR) Cooling Towers Demolition Waste Management

    SciTech Connect

    Pudelek, R. E.; Gilbert, W. C.

    2002-02-26

    This paper describes the results of a joint initiative between Oak Ridge National Laboratory, operated by UT-Battelle, and Bechtel Jacobs Company, LLC (BJC) to characterize, package, transport, treat, and dispose of demolition waste from the High Flux Isotope Reactor (HFIR), Cooling Tower. The demolition and removal of waste from the site was the first critical step in the planned HFIR beryllium reflector replacement outage scheduled. The outage was scheduled to last a maximum of six months. Demolition and removal of the waste was critical because a new tower was to be constructed over the old concrete water basin. A detailed sampling and analysis plan was developed to characterize the hazardous and radiological constituents of the components of the Cooling Tower. Analyses were performed for Resource Conservation and Recovery Act (RCRA) heavy metals and semi-volatile constituents as defined by 40 CFR 261 and radiological parameters including gross alpha, gross beta, gross gamma, alpha-emitting isotopes and beta-emitting isotopes. Analysis of metals and semi-volatile constituents indicated no exceedances of regulatory limits. Analysis of radionuclides identified uranium and thorium and associated daughters. In addition 60Co, 99Tc, 226Rm, and 228Rm were identified. Most of the tower materials were determined to be low level radioactive waste. A small quantity was determined not to be radioactive, or could be decontaminated. The tower was dismantled October 2000 to January 2001 using a detailed step-by-step process to aid waste segregation and container loading. The volume of waste as packaged for treatment was approximately 1982 cubic meters (70,000 cubic feet). This volume was comprised of plastic ({approx}47%), wood ({approx}38%) and asbestos transite ({approx}14%). The remaining {approx}1% consisted of the fire protection piping (contaminated with lead-based paint) and incidental metal from conduit, nails and braces/supports, and sludge from the basin. The waste

  11. Honey Lake Hybrid Power Plant Project. Volume 1. Executive summary

    SciTech Connect

    Not Available

    1982-03-01

    A technical and economic feasibility study of the engineering aspects of a hybrid wood-fired geothermal electrical generating plant is presented. The proposed plant location is in Lassen County, California, near the Wendel Amedee Known Geothermal Resource Area. This power plant uses moderate temperature geothermal fluid to augment the heat supplied from a wood waste fired boiler. This report defines major plant systems for implementation into the plant conceptual design and provides sufficient design information for development of budgetary cost estimates. Emphasis is placed on incorporation of geothermal heat into the power generation process. Plant systems are designed and selected based on economic justification and on proven performance. The culminating economic analysis provides the financial information to establish the incentives for construction of the plant. The study concludes that geothermal energy and energy from wood can be combined in a power generating plant to yield attractive project economics.

  12. 26 CFR 1.280B-1 - Demolition of structures.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ..., the term structure means a building, as defined in § 1.48-1(e)(1), including the structural components... 26 Internal Revenue 3 2012-04-01 2012-04-01 false Demolition of structures. 1.280B-1 Section 1... (CONTINUED) INCOME TAXES (CONTINUED) Items Not Deductible § 1.280B-1 Demolition of structures. (a) In...

  13. 253. Photocopy of drawing (1975 demolition drawing by the Ralph ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    253. Photocopy of drawing (1975 demolition drawing by the Ralph M. Parsons Company) DEMOLITION AND REMOVAL FOR LAUNCHER - SLC-3E, SHEET D-9 - Vandenberg Air Force Base, Space Launch Complex 3, Launch Pad 3 East, Napa & Alden Roads, Lompoc, Santa Barbara County, CA

  14. Approaches to Teaching Plant Nutrition. Children's Learning in Science Project.

    ERIC Educational Resources Information Center

    Leeds Univ. (England). Centre for Studies in Science and Mathematics Education.

    During the period 1984-1986, over 30 teachers from the Yorkshire (England) region have worked in collaboration with the Children's Learning in Science Project (CLIS) developing and testing teaching schemes in the areas of energy, particle theory, and plant nutrition. The project is based upon the constructivist approach to teaching. This document…

  15. Primarily Plants, A Plant Study for K-3. Project AIMS.

    ERIC Educational Resources Information Center

    Hoover, Evalyn; Mercier, Sheryl

    Project AIMS (Activities to Integrate Mathematics and Science) has as its purpose the integration of subject matter in grades K-9. Field testing of the curriculum materials produced by AIMS indicates that this interpretation produces the following beneficial results: (1) mathematics becomes more meaningful, hence more useful; (2) science is…

  16. Small-Scale Geothermal Power Plant Field Verification Projects: Preprint

    SciTech Connect

    Kutscher, C.

    2001-07-03

    In the spring of 2000, the National Renewable Energy Laboratory issued a Request for Proposal for the construction of small-scale (300 kilowatt [kW] to 1 megawatt [MW]) geothermal power plants in the western United States. Five projects were selected for funding. Of these five, subcontracts have been completed for three, and preliminary design work is being conducted. The three projects currently under contract represent a variety of concepts and locations: a 1-MW evaporatively enhanced, air-cooled binary-cycle plant in Nevada; a 1-MW water-cooled Kalina-cycle plant in New Mexico; and a 750-kW low-temperature flash plant in Utah. All three also incorporate direct heating: onion dehydration, heating for a fish hatchery, and greenhouse heating, respectively. These projects are expected to begin operation between April 2002 and September 2003. In each case, detailed data on performance and costs will be taken over a 3-year period.

  17. Demolition of the waste evaporator facility at Oak Ridge National Laboratory

    SciTech Connect

    Mandry, G.J.; Becker, C.L.

    1997-08-01

    Lockheed Martin Energy Systems, in conjunction with Allied Technology Group, Inc., successfully executed the decommissioning of a former waste evaporator facility at ONRL. This project was conducted as a non-time critical removal action under CERCLA. The decommissioning alternative selected for the Waste Evaporator Facility was partial dismantlement. This alternative provided for the demolition of all above-grade structures; concrete which did not exceed pre-established radiological levels were eligible for placement in the below-grade portion of the facility. This project demonstrated a coordinated team approach that allowed the successful completion of one of the first full-scale decommissioning projects at ORNL.

  18. Gentrification in black and white: the racial impact of public housing demolition in American cities.

    PubMed

    Goetz, Edward

    2011-01-01

    The gentrification that has transformed high-poverty neighbourhoods in US cities since the mid 1990s has been characterised by high levels of state reinvestment. Prominent among public-sector interventions has been the demolition of public housing and in some cases multimillion dollar redevelopment efforts. In this paper, the racial dimension of state-supported gentrification in large US cities is examined by looking at the direct and indirect displacement induced by public housing transformation. The data show a clear tendency towards the demolition of public housing projects with disproportionately high African American occupancy. The pattern of indirect displacement is more varied; public housing transformation has produced a number of paths of neighbourhood change. The most common, however, involve significant reductions in poverty, sometimes associated with Black to White racial turnover and sometimes not. The findings underscore the central importance of race in understanding the dynamics of gentrification in US cities. PMID:21949948

  19. The CELSS breadboard project: Plant production

    NASA Technical Reports Server (NTRS)

    Knott, William M.

    1990-01-01

    NASA's Breadboard Project for the Controlled Ecological Life Support System (CELSS) program is described. The simplified schematic of a CELSS is given. A modular approach is taken to building the CELSS Breadboard. Each module is researched in order to develop a data set for each one prior to its integration into the complete system. The data being obtained from the Biomass Production Module or the Biomass Production Chamber is examined. The other primary modules, food processing and resource recovery or waste management, are discussed briefly. The crew habitat module is not discussed. The primary goal of the Breadboard Project is to scale-up research data to an integrated system capable of supporting one person in order to establish feasibility for the development and operation of a CELSS. Breadboard is NASA's first attempt at developing a large scale CELSS.

  20. Hanford Waste Vitrification Plant Project Plan. Revision 1

    SciTech Connect

    Brown, R.W.

    1993-06-01

    A major mission of the US DOE is the permanent disposal of Hanford defense wastes by safe, environmentally acceptable, and cost effective methods which meet applicable regulations. The Hanford Waste Vitrification Plant (HWVP) Project was initiated to immobilize the Hanford high-level waste (HLW) and provide interim storage. The HWVP will vitrify the pre-treated HLW into borosilicate glass, cast the glass into stainless steel canisters, and store the canisters on site until they are shipped to a federal geologic repository. The HWVP project objective is to design, construct, and operate a facility for immobilizing defense high-level waste for storage. Technical objectives include using the Defense Waste Processing Facility designed plants systems or elements, where practical, and the exchange and review of information on plants in foreign countries. More definitive objectives for quality, reliability, environmental, and safety are provided in the HWVP Project Management Plan.

  1. A BIM-based system for demolition and renovation waste estimation and planning.

    PubMed

    Cheng, Jack C P; Ma, Lauren Y H

    2013-06-01

    Due to the rising worldwide awareness of green environment, both government and contractors have to consider effective construction and demolition (C&D) waste management practices. The last two decades have witnessed the growing importance of demolition and renovation (D&R) works and the growing amount of D&R waste disposed to landfills every day, especially in developed cities like Hong Kong. Quantitative waste prediction is crucial for waste management. It can enable contractors to pinpoint critical waste generation processes and to plan waste control strategies. In addition, waste estimation could also facilitate some government waste management policies, such as the waste disposal charging scheme in Hong Kong. Currently, tools that can accurately and conveniently estimate the amount of waste from construction, renovation, and demolition projects are lacking. In the light of this research gap, this paper presents a building information modeling (BIM) based system that we have developed for estimation and planning of D&R waste. BIM allows multi-disciplinary information to be superimposed within one digital building model. Our system can extract material and volume information through the BIM model and integrate the information for detailed waste estimation and planning. Waste recycling and reuse are also considered in our system. Extracted material information can be provided to recyclers before demolition or renovation to make recycling stage more cooperative and more efficient. Pick-up truck requirements and waste disposal charging fee for different waste facilities will also be predicted through our system. The results could provide alerts to contractors ahead of time at project planning stage. This paper also presents an example scenario with a 47-floor residential building in Hong Kong to demonstrate our D&R waste estimation and planning system. As the BIM technology has been increasingly adopted in the architectural, engineering and construction industry

  2. A BIM-based system for demolition and renovation waste estimation and planning.

    PubMed

    Cheng, Jack C P; Ma, Lauren Y H

    2013-06-01

    Due to the rising worldwide awareness of green environment, both government and contractors have to consider effective construction and demolition (C&D) waste management practices. The last two decades have witnessed the growing importance of demolition and renovation (D&R) works and the growing amount of D&R waste disposed to landfills every day, especially in developed cities like Hong Kong. Quantitative waste prediction is crucial for waste management. It can enable contractors to pinpoint critical waste generation processes and to plan waste control strategies. In addition, waste estimation could also facilitate some government waste management policies, such as the waste disposal charging scheme in Hong Kong. Currently, tools that can accurately and conveniently estimate the amount of waste from construction, renovation, and demolition projects are lacking. In the light of this research gap, this paper presents a building information modeling (BIM) based system that we have developed for estimation and planning of D&R waste. BIM allows multi-disciplinary information to be superimposed within one digital building model. Our system can extract material and volume information through the BIM model and integrate the information for detailed waste estimation and planning. Waste recycling and reuse are also considered in our system. Extracted material information can be provided to recyclers before demolition or renovation to make recycling stage more cooperative and more efficient. Pick-up truck requirements and waste disposal charging fee for different waste facilities will also be predicted through our system. The results could provide alerts to contractors ahead of time at project planning stage. This paper also presents an example scenario with a 47-floor residential building in Hong Kong to demonstrate our D&R waste estimation and planning system. As the BIM technology has been increasingly adopted in the architectural, engineering and construction industry

  3. A BIM-based system for demolition and renovation waste estimation and planning

    SciTech Connect

    Cheng, Jack C.P.; Ma, Lauren Y.H.

    2013-06-15

    Highlights: ► We developed a waste estimation system leveraging the BIM technology. ► The system can calculate waste disposal charging fee and pick-up truck demand. ► We presented an example scenario demonstrating this system. ► Automatic, time-saving and wide applicability are the features of the system. - Abstract: Due to the rising worldwide awareness of green environment, both government and contractors have to consider effective construction and demolition (C and D) waste management practices. The last two decades have witnessed the growing importance of demolition and renovation (D and R) works and the growing amount of D and R waste disposed to landfills every day, especially in developed cities like Hong Kong. Quantitative waste prediction is crucial for waste management. It can enable contractors to pinpoint critical waste generation processes and to plan waste control strategies. In addition, waste estimation could also facilitate some government waste management policies, such as the waste disposal charging scheme in Hong Kong. Currently, tools that can accurately and conveniently estimate the amount of waste from construction, renovation, and demolition projects are lacking. In the light of this research gap, this paper presents a building information modeling (BIM) based system that we have developed for estimation and planning of D and R waste. BIM allows multi-disciplinary information to be superimposed within one digital building model. Our system can extract material and volume information through the BIM model and integrate the information for detailed waste estimation and planning. Waste recycling and reuse are also considered in our system. Extracted material information can be provided to recyclers before demolition or renovation to make recycling stage more cooperative and more efficient. Pick-up truck requirements and waste disposal charging fee for different waste facilities will also be predicted through our system. The results

  4. Raft River 5-MW(e) geothermal pilot plant project

    SciTech Connect

    Rasmussen, T.L.; Whitbeck, J.F.

    1980-01-01

    The Raft River 5-MW(e) Pilot Plant Project was started in 1976. Construction is scheduled for completion in July 1980, with three years of engineering and operational testing to follow. The plant utilized a 280/sup 0/F geothermal fluid energy source and a dual boiling isobutane cycle. Developmental efforts are in progress in the areas of down hole pumps and chemical treatment of geothermal fluid for cooling tower makeup.

  5. Computer, Video, and Rapid-Cycling Plant Projects in an Undergraduate Plant Breeding Course.

    ERIC Educational Resources Information Center

    Michaels, T. E.

    1993-01-01

    Studies the perceived effectiveness of four student projects involving videotape production, computer conferencing, microcomputer simulation, and rapid-cycling Brassica breeding for undergraduate plant breeding students in two course offerings in consecutive years. Linking of the computer conferencing and video projects improved the rating of the…

  6. 6. Detail of interior bin wall section, during demolition. Shows ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    6. Detail of interior bin wall section, during demolition. Shows alternating courses of channel tile with steel bands and largers hollow tile. - Saint Anthony Elevator No. 3, 620 Malcom Avenue, Southeast, Minneapolis, Hennepin County, MN

  7. 30. VIEW OF DEMOLITION OF FOUNDRY SAND BLASTING AND CLEANING ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    30. VIEW OF DEMOLITION OF FOUNDRY SAND BLASTING AND CLEANING BUILDING FROM INSIDE FOUNDRY. - Baltimore & Ohio Railroad, Mount Clare Shops, South side of Pratt Street between Carey & Poppleton Streets, Baltimore, Independent City, MD

  8. 31. VIEW OF DEMOLITION OF FOUNDRY SAND BLASTING AND CLEANING ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    31. VIEW OF DEMOLITION OF FOUNDRY SAND BLASTING AND CLEANING BUILDING FROM INSIDE FOUNDRY. - Baltimore & Ohio Railroad, Mount Clare Shops, South side of Pratt Street between Carey & Poppleton Streets, Baltimore, Independent City, MD

  9. Senseless demolition in progress, showing destruction of perfectly decent and ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    Senseless demolition in progress, showing destruction of perfectly decent and recyclable mill building. Problem exacerbated by high value of scrap iron. - Phoenix Iron Company, Rolling Mill, North of French Creek, west of Fairview Avenue, Phoenixville, Chester County, PA

  10. Plants. Learning in Science Project. Working Paper No. 24.

    ERIC Educational Resources Information Center

    Stead, Beverley

    One area explored in the second (in-depth) phase of the Learning in Science Project was "children's science," defined as views of the world and the meanings for words that children have and bring with them to science lessons. The investigation reported focuses on the concept of "plant" held by 29 students. Data were obtained by the…

  11. Bayer Polymers: Plant Identifies Numerous Projects Following Plant-Wide Energy-Efficient Assessment

    SciTech Connect

    2003-08-01

    The Bayer Corporation undertook a plant-wide energy efficiency assessment of its New Martinsville, West Virginia, plant in 2001. The objectives were to identify energy saving projects in the utilities area. The projects, when complete, will save the company the loss of an estimated 236,000 MMBtu ($1.16 million) annually in energy from burning and leaking fossil fuels. Certain other projects will save the company 6,300,000 kWh ($219,000) of electrical energy each year. All of the projects could be duplicated in other chemical manufacturing facilities and most of the projects could be duplicated in other industries utilizing steam, pumps, and/or compressed air.

  12. Conservation and restoration of indigenous plants to improve community livelihoods: the Useful Plants Project

    NASA Astrophysics Data System (ADS)

    Ulian, Tiziana; Sacandé, Moctar; Mattana, Efisio

    2014-05-01

    Kew's Millennium Seed Bank partnership (MSBP) is one of the largest ex situ plant conservation initiatives, which is focused on saving plants in and from regions most at risk, particularly in drylands. Seeds are collected and stored in seed banks in the country of origin and duplicated in the Millennium Seed Bank in the UK. The MSBP also strengthens the capacity of local communities to successfully conserve and sustainably use indigenous plants, which are important for their wellbeing. Since 2007, high quality seed collections and research information have been gathered on ca. 700 useful indigenous plant species that were selected by communities in Botswana, Kenya, Mali, Mexico and South Africa through Project MGU - The Useful Plants Project. These communities range from various farmer's groups and organisations to traditional healers, organic cotton/crop producers and primary schools. The information on seed conservation and plant propagation was used to train communities and to propagate ca. 200 species that were then planted in local gardens, and as species reintroduced for reforestation programmes and enriching village forests. Experimental plots have also been established to further investigate the field performance (plant survival and growth rate) of indigenous species, using low cost procedures. In addition, the activities support revenue generation for local communities directly through the sustainable use of plant products or indirectly through wider environmental and cultural services. This project has confirmed the potential of biodiversity conservation to improve food security and human health, enhance community livelihoods and strengthen the resilience of land and people to the changing climate. This approach of using indigenous species and having local communities play a central role from the selection of species to their planting and establishment, supported by complementary research, may represent a model for other regions of the world, where

  13. Quantifying construction and demolition waste: an analytical review.

    PubMed

    Wu, Zezhou; Yu, Ann T W; Shen, Liyin; Liu, Guiwen

    2014-09-01

    Quantifying construction and demolition (C&D) waste generation is regarded as a prerequisite for the implementation of successful waste management. In literature, various methods have been employed to quantify the C&D waste generation at both regional and project levels. However, an integrated review that systemically describes and analyses all the existing methods has yet to be conducted. To bridge this research gap, an analytical review is conducted. Fifty-seven papers are retrieved based on a set of rigorous procedures. The characteristics of the selected papers are classified according to the following criteria - waste generation activity, estimation level and quantification methodology. Six categories of existing C&D waste quantification methodologies are identified, including site visit method, waste generation rate method, lifetime analysis method, classification system accumulation method, variables modelling method and other particular methods. A critical comparison of the identified methods is given according to their characteristics and implementation constraints. Moreover, a decision tree is proposed for aiding the selection of the most appropriate quantification method in different scenarios. Based on the analytical review, limitations of previous studies and recommendations of potential future research directions are further suggested.

  14. Quantifying construction and demolition waste: An analytical review

    SciTech Connect

    Wu, Zezhou; Yu, Ann T.W.; Shen, Liyin; Liu, Guiwen

    2014-09-15

    Highlights: • Prevailing C and D waste quantification methodologies are identified and compared. • One specific methodology cannot fulfill all waste quantification scenarios. • A relevance tree for appropriate quantification methodology selection is proposed. • More attentions should be paid to civil and infrastructural works. • Classified information is suggested for making an effective waste management plan. - Abstract: Quantifying construction and demolition (C and D) waste generation is regarded as a prerequisite for the implementation of successful waste management. In literature, various methods have been employed to quantify the C and D waste generation at both regional and project levels. However, an integrated review that systemically describes and analyses all the existing methods has yet to be conducted. To bridge this research gap, an analytical review is conducted. Fifty-seven papers are retrieved based on a set of rigorous procedures. The characteristics of the selected papers are classified according to the following criteria - waste generation activity, estimation level and quantification methodology. Six categories of existing C and D waste quantification methodologies are identified, including site visit method, waste generation rate method, lifetime analysis method, classification system accumulation method, variables modelling method and other particular methods. A critical comparison of the identified methods is given according to their characteristics and implementation constraints. Moreover, a decision tree is proposed for aiding the selection of the most appropriate quantification method in different scenarios. Based on the analytical review, limitations of previous studies and recommendations of potential future research directions are further suggested.

  15. Cedar Bay Cogeneration Project: A plant in transition

    SciTech Connect

    Perry, M.A.; Lenertz, R.P.

    1994-12-31

    The Cedar Bay Cogeneration Project was initially developed by Applied Energy Services and contracted on a turnkey basis to Multipower Associates as part of a multiple projects agreement. Multipower Associates is a joint venture including The Pritchard Company (a wholly owned subsidiary of Black and Veatch), Marubeni Corporation, and Ahlstrom Pyropower. The project changed ownership to the Cedar Bay Generating Company at the midpoint of the construction phase. The Cedar Bay Cogeneration Plant provides 250 MW net to Florida Power and Light Company while producing up to 380,000 lb/h process steam to the adjacent Seminole Kraft Papermill. Three Ahlstrom Pyropower circulating fluidized bed boilers provide steam to a Toshiba turbine. Each boiler incorporates reheat capabilities to improve cycle thermodynamic efficiency. One reverse gas fabric filter is provided for each boiler to control particulate emissions. Ammonia injection (Thermal DeNo{sub x}-SNCR) is employed to limit the NO{sub x} emissions. The plant relies on a dilute phase pneumatic ash handling system to move the byproduct to an ash pelletizing complex. The original project developers required a state-of-the-art ash pelletizing system. Appreciable research has been done in adapting this new technology for this project. The ash pelletizing system transforms the ash into pellets, allowing the ash to be loaded into open railcars and transported back to the coal mine by conventional material handling equipment.

  16. Sustainable construction: construction and demolition waste reconsidered.

    PubMed

    del Río Merino, Mercedes; Izquierdo Gracia, Pilar; Weis Azevedo, Isabel Salto

    2010-02-01

    Construction activity in Europe has increased substantially in the past decade. Likewise, there has also been a commensurate rise in the generation of construction and demolition waste (C&DW). This, together with the fact that in many European countries the rate of recycling and reuse of C&DW is still quite low has engendered a serious environmental problem and a motivation to develop strategies and management plans to solve it. Due to its composition, there is a significant potential to reuse and/or recycle C&DW, and thereby, contribute to improving the sustainability of construction and development, but practical procedures are not yet widely known or practiced in the construction industry. This article (a) summarizes the different applications that are presently practiced to optimize the recovery and/or application of C&DW for reuse, and (b) proposes various measures and strategies to improve the processing of this waste. The authors suggest that to enhance environmental effectiveness, a conscious and comprehensive C&DW management plan should be implemented in each jurisdiction. More precisely, this study presents a holistic approach towards C&DW management, through which environmental benefits can be achieved through the application of new construction methods that can contribute to sustainable growth.

  17. URBAN WOOD/COAL CO-FIRING IN THE NIOSH BOILER PLANT

    SciTech Connect

    James T. Cobb Jr.

    2005-02-10

    Phase I of this project began by obtaining R&D variances for permits at the NIOSH boilerplant (NBP), Emery Tree Service (ETS) and the J. A. Rutter Company (JARC) for their portions of the project. Wood for the test burn was obtained from the JARC inventory (pallets), Thompson Properties and Seven D Corporation (construction wood), and the Arlington Heights Housing Project (demolition wood). The wood was ground at ETS and JARC, delivered to the Three Rivers Terminal and blended with coal. Three one-day tests using wood/coal blends of 33% wood by volume (both construction wood and demolition wood) were conducted at the NBP. Blends using hammermilled wood were operationally successful. Emissions of SO{sub 2} and NOx decreased and that of CO increased when compared with combusting coal alone. Mercury emissions were measured and evaluated. During the first year of Phase II the principal work focused upon searching for a replacement boilerplant and developing a commercial supply of demolition wood. The NBP withdrew from the project and a search began for another stoker boilerplant in Pennsylvania to replace it on the project. Three potential commercial demolition wood providers were contacted. Two were not be able to supply wood. At the end of the first year of Phase II, discussions were continuing with the third one, a commercial demolition wood provider from northern New Jersey. During the two-and-a-third years of the contract extension it was determined that the demolition wood from northern New Jersey was impractical for use in Pittsburgh, in another power plant in central New Jersey, and in a new wood gasifier being planned in Philadelphia. However, the project team did identify sufficient wood from other sources for the gasifier project. The Principal Investigator of this project assisted a feasibility study of wood gasification in Clarion County, Pennsylvania. As a result of the study, an independent power producer in the county has initiated a small wood

  18. The Breadboard Project: a functioning CELSS plant growth system.

    PubMed

    Knott, W M

    1992-01-01

    The primary objective of the Breadboard project for the next 3-4 years is to develop, integrate and operate a Controlled Ecological Life Support System (CELSS) at a one person scale. The focus of this project over the past two years has been the development of the plant growth facility, the first module of the CELSS. The other major modules, food preparation, biomass processing, and resource recovery, have been researched at the laboratory scale during the past two years and facilities are currently under construction to scale-up these modules to an operational state. This paper will outline the design requirements for the Biomass Production Chamber (BPC), the plant growth facility for the project, and the control and monitoring subsystems which operate the chamber and will present results from both engineering and biological tests of the facility. Three production evaluations of wheat, conducted in the BPC during the past year, will be described and the data generated from these tests discussed. Future plans for the BPC will be presented along with future goals for the project as the other modules become active.

  19. Demobilization of the World's Largest Decontamination and Decommissioning Project Project Closeout of three Gaseous Diffusion Plants for Re-industrialization

    SciTech Connect

    Stevens, J.L.; Miller, JA.

    2006-07-01

    This paper describes the challenges and lessons learned from the demobilization of the world' largest, and first, successfully decontaminated and decommissioned project. These gaseous diffusion plants are the first plants to be successfully decommissioned in the United States. (authors)

  20. Expedited Demolition Notification for 2nd Quarter CY 2012 Structures

    SciTech Connect

    Juarez, Catherine L.

    2012-06-18

    The National Nuclear Security Administration and Los Alamos National Security, LLC (LANS) (collectively the Permittees) are informing the New Mexico Environment Department Hazardous Waste Bureau (NMED-HWB) of the need to expedite the demolition of structures summarized in the enclosures. These structures have been identified to receive funding and be demolished prior to the 3rd Quarter Demolition Notification (June 30, 2012). This letter is a follow up to the email that was sent to the NMED-HWB on April 17, 2012. The enclosures attached to this letter satisfy the reporting requirements as outlined in Section 1.17 of the LANL Hazardous Facility Waste Permit (Permit). Demolition of buildings that appear on this list will not occur until 30 days after NMED has received this notification.

  1. Hanford single-pass reactor fuel storage basin demolition.

    PubMed

    Armstrong, Jason A

    2003-02-01

    The Environmental Restoration Contractor at the Hanford Site is tasked with removing auxiliary reactor structures and leaving the remaining concrete structure surrounding each reactor core. This is referred to as Interim Safe Storage. Part of placing the F Reactor into Interim Safe Storage is the demolition of the fuel storage basin, which was deactivated in 1970 by placing debris material into the basin prior to back filling with soil. Besides the debris material (wooden floor decking, handrails, and monorail pieces), the fuel storage basin contents included the possibility of spent nuclear fuel, fuel buckets, fuel spacers, process tubes, and tongs. Demolition of the fuel storage basin offered many unique radiological control challenges and innovative approaches to demolition. This paper describes how the total effective dose equivalent and contamination were controlled, how the use of a remote operated excavator was employed to remove high-dose-rate material, and how wireless technology was used to monitor changing radiological conditions.

  2. Project BudBurst: People, Plants, and Climate Change

    NASA Astrophysics Data System (ADS)

    Henderson, S.; Ward, D.; Havens, K.; Gardiner, L. S.; Alaback, P.

    2010-12-01

    Providing opportunities for individuals to contribute to a better understanding of climate change is the hallmark of Project BudBurst (www.budburst.org). This highly successful, national citizen science program, now in its third year, is bringing climate change education outreach to thousands of individuals. Project BudBurst is a national citizen science initiative designed to engage the public in observations of phenological (plant life cycle) events that raise awareness of climate change, and create a cadre of informed citizen scientists. Citizen science programs such as Project BudBurst provide the opportunity for students and interested laypersons to actively participate in scientific research. Such programs are important not only from an educational perspective, but because they also enable scientists to broaden the geographic and temporal scale of their observations. The goals of Project BudBurst are to 1) increase awareness of phenology as an area of scientific study; 2) Increase awareness of the impacts of changing climates on plants; and 3) increase science literacy by engaging participants in the scientific process. From its 2008 launch in February, this on-line educational and data-entry program, engaged participants of all ages and walks of life in recording the timing of the leafing and flowering of wild and cultivated species found across the continent. Thus far, thousands of participants from all 50 states have submitted data. Project BudBurst has been the subject of almost 200 media outlets including NPR, national and regional television broadcasts, and most of the major national and regional newspapers. This presentation will provide an overview of Project BudBurst and will report on the results of the 2009 field campaign and discuss plans to expand Project BudBurst in 2010 including the use of mobile phones applications for data collection and reporting from the field. Project BudBurst co managed by the National Ecological Observatory Network and

  3. The Breadboard Project - A functioning CELSS plant growth system

    NASA Technical Reports Server (NTRS)

    Knott, W. M.

    1992-01-01

    The primary objective of the Breadboard Project for the next 3-4 years is to develop, integrate and operate a Controlled Ecological Life Support System (CELSS) at a one-person scale. The focus of this project over the past two years has been the development of the plant growth facility, the first module of the CELSS. The other major modules, food preparation, biomass processing, and resource recovery, have been researched at the laboratory scale during the past two years and facilities are currently under construction to scale-up these modules to an operational state. This paper will outline the design requirements for the Biomass Production Chamber (BPC), the plant growth facility for the project, and the control and monitoring subsystems which operate the chamber and will present results from both engineering and biological tests of the facility. Three production evaluations of wheat, conducted in the BPC during the past year, will be described and the data generated from these tests discussed.

  4. 22 CFR 121.11 - Military demolition blocks and blasting caps.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... 22 Foreign Relations 1 2013-04-01 2013-04-01 false Military demolition blocks and blasting caps... THE UNITED STATES MUNITIONS LIST Enumeration of Articles § 121.11 Military demolition blocks and blasting caps. Military demolition blocks and blasting caps referred to in Category IV(a) do not...

  5. 22 CFR 121.11 - Military demolition blocks and blasting caps.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... 22 Foreign Relations 1 2014-04-01 2014-04-01 false Military demolition blocks and blasting caps... THE UNITED STATES MUNITIONS LIST Enumeration of Articles § 121.11 Military demolition blocks and blasting caps. Military demolition blocks and blasting caps referred to in Category IV(a) do not...

  6. Ground motion measurements from the demolition of steel towers

    SciTech Connect

    Joshi, J.R.; Lee, R.C.

    1998-12-31

    Steel towers from a decommissioned heavy water plant were to be demolished. Ground motions due to the proposed felling were estimated in order to assess the structural integrity of neighboring buildings and piping systems. The extraction towers were 125 feet (38.1 m) high in two sizes: 6.5 and 11 feet (1.98 and 3.35 m) inside diameters weighing 215 X 10{sup 3} and 470 X 10{sup 3} lb (956 X 10{sup 3} and 2.1 X 10{sup 6} N). The total potential energy of the tower collapse was about 15 X 10{sup 6} and 32 X 10{sup 6} ft-lb (20.3 X 10{sup 6} and 43.4 X 10{sup 6} Nm) for the small and large towers, respectively. The ground motion predictions were based on a credible theoretical relationship with constants estimated from data available for a different location at the site for dynamic compaction with an energy input an order of magnitude less than that for the towers. Due to the uncertainty of prediction of ground motions a coefficient of variation of 2.0 was used in the structural assessment. Ground motion from the collapse of the extraction towers were monitored by several 3- and 6-components seismographs. Recorded measurements indicated that the ground motion was less than the predicted values. Peak radial motions were approximately equal to the vertical ones. Video tapes of the demolition suggested significant internal energy losses. The measurements suggested that the tower potential energy conversion to dynamic impact energy was about 25 percent. 7 figs.

  7. Projecting the success of plant restoration with population viability analysis

    USGS Publications Warehouse

    Bell, T.J.; Bowles, M.L.; McEachern, A.K.; Brigham, C.A.; Schwartz, M.W.

    2003-01-01

    Conserving viable populations of plant species requires that they have high probabilities of long-term persistence within natural habitats, such as a chance of extinction in 100 years of less than 5% (Menges 1991, 1998; Brown 1994; Pavlik 1994; Chap. 1, this Vol.). For endangered and threatened species that have been severely reduces in range and whose habitats have been fragmented, important species conservation strategies may include augmenting existing populations or restoring new viable populations (Bowles and Whelan 1994; Chap. 2, this Vol.). Restoration objectives may include increasing population numbers to reduce extinction probability, deterministic manipulations to develop a staged cohort structure, or more complex restoration of a desired genetic structure to allow outcrossing or increase effective population size (DeMauro 1993, 1994; Bowles et al. 1993, 1998; Pavlik 1994; Knapp and Dyer 1998; Chap. 2, this Vol.). These efforts may require translocation of propagules from existing (in situ) populations, or from ex situ botanic gardens or seed storage facilities (Falk et al. 1996; Guerrant and Pavlik 1998; Chap. 2, this Vol.). Population viability analysis (PVA) can provide a critical foundation for plant restoration, as it models demographic projections used to evaluate the probability of population persistence and links plant life history with restoration strategies. It is unknown how well artificially created populations will meet demographic modeling requirements (e.g., due to artificial cohort transitions) and few, if any, PVAs have been applied to restorations. To guide application of PVA to restored populations and to illustrate potential difficulties, we examine effects of planting different life stages, model initial population sizes needed to achieve population viability, and compare demographic characteristics between natural and restored populations. We develop and compare plant population restoration viability analysis (PRVA) case studies of

  8. Monticello Lead Plant License Renewal Project summary report. Final report

    SciTech Connect

    Bailey, T.L.; Pickens, T.A.; Gregor, F.E.; Stancavage, P.P.

    1996-02-01

    The Monticello Lead Plant License Renewal Project is sponsored by the Electric Power Research Institute and the Department of Energy to demonstrate the license renewal process for boiling water reactors. The initial technical tasks for the project are the subject of this summary report: Task 2, Identification of Systems, Structures, and Components Important to License Renewal; Task 3, Evaluation of Systems, Structures, and Components; and Task 4, Maintenance and Operational Practices. Task 2 identified systems, structures and components which require evaluation for license renewal. Task 3 provides an evaluation of aging mechanisms affecting structures and components. Task 3 evaluations define structure or component boundaries and identify pertinent physical features, design data, operating/maintenance history, potentially significant age-related degradation mechanisms, and degradation sites. Task 4 provides an evaluation of selected plant programs which apply to these structures and components. The capability of programs to detect and mitigate aging mechanisms and/or to maintain the required function is determined. Enhancements are recommended when required to meet program effectiveness criteria. The results of these evaluations are documented as part of Task 6 in Technical Support Documents. This 4-year effort was the first time that the Nuclear Regulatory Commission`s (NRC) license renewal evaluation criteria were applied to specific plant structures and components. Evaluations which identified potentially significant aging mechanisms were performed for most components. Other evaluation methods were developed and applied that relied on published aging investigations or inherent design and operating features of the plant. Evaluation approaches were reviewed with sponsoring organizations and representatives from other organizations and utilities. Examples of the evaluation approach and sample results were presented to the NRC staff on several occasions.

  9. Plutonium Finishing Plant Transition Project mission analysis report

    SciTech Connect

    Courson, D.B.

    1994-09-21

    This report defines the mission for the Plutonium Finishing Plant Transition Project (PFPTP) using a systems engineering approach. This mission analysis will be the basis for the functional analysis which will further define and break down the mission statement into all of the detailed functions required to accomplish the mission. The functional analysis is then used to develop requirements, allocate those requirements to functions, and eventually be used to design the system. This report: presents the problem which will be addressed, defines PFP Transition Project, defines the overall mission statement, describes the existing, initial conditions, defines the desired, final conditions, identifies the mission boundaries and external interfaces, identifies the resources required to carry out the mission, describes the uncertainties and risks, and discusses the measures which will be used to determine success.

  10. Sampling and Analysis Plan - Waste Treatment Plant Seismic Boreholes Project

    SciTech Connect

    Reidel, Steve P.

    2006-05-26

    This sampling and analysis plan (SAP) describes planned data collection activities for four entry boreholes through the sediment overlying the basalt, up to three new deep rotary boreholes through the basalt and sedimentary interbeds, and one corehole through the basalt and sedimentary interbeds at the Waste Treatment Plant (WTP) site. The SAP will be used in concert with the quality assurance plan for the project to guide the procedure development and data collection activities needed to support borehole drilling, geophysical measurements, and sampling. This SAP identifies the American Society of Testing Materials standards, Hanford Site procedures, and other guidance to be followed for data collection activities.

  11. Cultural Resource Assessment of the Test Area North Demolition Landfill at the Idaho National Engineering and Environmental Laboratory

    SciTech Connect

    Brenda R. Pace

    2003-07-01

    The proposed new demolition landfill at Test Area North on the Idaho National Engineering and Environmental Laboratory (INEEL) will support ongoing demolition and decontamination within the facilities on the north end of the INEEL. In June of 2003, the INEEL Cultural Resource Management Office conducted archival searches, field surveys, and coordination with the Shoshone-Bannock Tribes to identify all cultural resources that might be adversely affected by the project and to provide recommendations to protect those listed or eligible for listing on the National Register of Historic Places. These investigations showed that landfill construction and operation would affect two significant cultural resources. This report outlines protective measures to ensure that these effects are not adverse.

  12. Spray and dust hang in the air, as the demolition ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    Spray and dust hang in the air, as the demolition is completed. Only the southeast pier remains standing at right. View is to southeast from confluence of Trinity and South Fork Trinity Rivers - South Fork Trinity River Bridge, State Highway 299 spanning South Fork Trinity River, Salyer, Trinity County, CA

  13. 40 CFR 61.145 - Standard for demolition and renovation.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... activity begins (such as site preparation that would break up, dislodge or similarly disturb asbestos... up, dislodge, or similarly disturb asbestos material) in a demolition or renovation; planned... begins that would break up, dislodge, or similarly disturb the material or preclude access to...

  14. 40 CFR 61.145 - Standard for demolition and renovation.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... activity begins (such as site preparation that would break up, dislodge or similarly disturb asbestos... up, dislodge, or similarly disturb asbestos material) in a demolition or renovation; planned... begins that would break up, dislodge, or similarly disturb the material or preclude access to...

  15. 40 CFR 61.145 - Standard for demolition and renovation.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... activity begins (such as site preparation that would break up, dislodge or similarly disturb asbestos... up, dislodge, or similarly disturb asbestos material) in a demolition or renovation; planned... begins that would break up, dislodge, or similarly disturb the material or preclude access to...

  16. Building a (UN) condom manufacturing plant for social marketing projects.

    PubMed

    Yonese, T

    1994-12-01

    At the 10th International Conference on AIDS held in Yokohama, Japan, August 7-12, 1994, reports revealed that the social marketing of condoms has become popular and successful in developing countries. The nongovernmental organization distribution approach is very useful in providing condoms to new users, whose numbers have been increasing since the condom was identified as effective in preventing sexually transmitted diseases (STDs), including HIV. The rapid establishment of semi-commercial outlets even in remote areas enabled many people to obtain condoms more easily than from the government program and at a cheaper price. The social marketing concept has a clear advantage: condoms can be distributed with little government budget disbursement, and the project is based on self-reliance. Meanwhile, the additional free supply programs by many governments of developing countries are reportedly not functioning efficiently, since often large quantities of condoms, donated by agencies for family planning and STD programs, pile up in warehouses and do not reach those who need them. Moreover, the demand for condoms is limited because of the lack of effective campaigns to encourage their use. Quality condoms can be procured at lower costs if a special manufacturing plant could be built that produces condoms exclusively for the social marketing free supply program. Such a condom plant could be built in a developing country where good quality latex, the material used for condoms, is available. The unit production cost of condoms at the proposed plant would be lower compared to costs in developed countries because personnel expenses in latex-producing countries such as Malaysia, Thailand, Indonesia, India, and Sri Lanka, are cheaper, and the price of latex itself is lower. Mass production is possible because the demand for condoms for the social marketing projects is expected to grow even more. PMID:12319132

  17. Building a (UN) condom manufacturing plant for social marketing projects.

    PubMed

    Yonese, T

    1994-12-01

    At the 10th International Conference on AIDS held in Yokohama, Japan, August 7-12, 1994, reports revealed that the social marketing of condoms has become popular and successful in developing countries. The nongovernmental organization distribution approach is very useful in providing condoms to new users, whose numbers have been increasing since the condom was identified as effective in preventing sexually transmitted diseases (STDs), including HIV. The rapid establishment of semi-commercial outlets even in remote areas enabled many people to obtain condoms more easily than from the government program and at a cheaper price. The social marketing concept has a clear advantage: condoms can be distributed with little government budget disbursement, and the project is based on self-reliance. Meanwhile, the additional free supply programs by many governments of developing countries are reportedly not functioning efficiently, since often large quantities of condoms, donated by agencies for family planning and STD programs, pile up in warehouses and do not reach those who need them. Moreover, the demand for condoms is limited because of the lack of effective campaigns to encourage their use. Quality condoms can be procured at lower costs if a special manufacturing plant could be built that produces condoms exclusively for the social marketing free supply program. Such a condom plant could be built in a developing country where good quality latex, the material used for condoms, is available. The unit production cost of condoms at the proposed plant would be lower compared to costs in developed countries because personnel expenses in latex-producing countries such as Malaysia, Thailand, Indonesia, India, and Sri Lanka, are cheaper, and the price of latex itself is lower. Mass production is possible because the demand for condoms for the social marketing projects is expected to grow even more.

  18. JPL - Small Power Systems Applications Project. [for solar thermal power plant development and commercialization

    NASA Technical Reports Server (NTRS)

    Ferber, R. R.; Marriott, A. T.; Truscello, V.

    1978-01-01

    The Small Power Systems Applications (SPSA) Project has been established to develop and commercialize small solar thermal power plants. The technologies of interest include all distributed and central receiver technologies which are potentially economically viable in power plant sizes of one to 10 MWe. The paper presents an overview of the SPSA Project and briefly discusses electric utility involvement in the Project.

  19. Composting and bioremediation process evaluation of wood waste materials generated from the construction and demolition industry.

    PubMed

    McMahon, V; Garg, A; Aldred, D; Hobbs, G; Smith, R; Tothill, I E

    2008-04-01

    The suitability of using bioremediation and composting techniques for diverting construction and demolition (C&D) waste from landfill has been validated in this study. Different timber products from C&D waste have been composted using various composting approaches. The present work demonstrates the quality of compost produced as a result of composting of mixed board product wood waste, which is frequently obtained from the construction and demolition industry. Three compost mixes were prepared by mixing shredded chip board, medium density fibre, hardboard and melamine. Poultry manure, Eco-Bio mixture and green waste were used as nutrient supplements. The results revealed that compost produced from mixtures of poultry manure and green waste used as nutrient supplements improved the performance in plant growth trials (phytotoxicity tests). Results obtained from the experimental study clearly indicate that the composts produced comply with the criterion suggested in BSI PAS 100 (A specification for compost materials) for use in different applications. Composting can also be demonstrated to be a very practical approach to material management including transport reduction to and from the site. The economic suitability of the process will be improved with the increase in landfill tax. In the current regulatory scenario, it is recommended that these materials should be composted at a centralised facility. PMID:18325565

  20. “Everyone called me grandma”: Public housing demolition and relocation among older adults in Atlanta

    PubMed Central

    Keene, Danya E; Ruel, Erin

    2012-01-01

    Over the last few decades public and political dissatisfaction with public housing projects and an increasing emphasis on poverty deconcentration has led to the demolition of public housing in cities across the country. A significant body of literature has examined experiences of relocation from public housing and their implications for the well-being of individuals and communities. While much of this literature has focused on young or middle-aged adults and children, older adults have also been affected by demolition and relocation. The displacement of older adults raises a new set of age and life-course specific concerns for the well-being of this population. In this paper, we analyze the relocation narratives of 25 former public housing residents in Atlanta, Georgia. Our analysis focuses on the loss of geographically rooted communities of kinship, support and belonging that many participants, particularly those who have aged in place, attribute to their former developments. Participants describe many material and psychosocial benefits associated with living in communities that were “like families” and where they often held important roles as respected elders. While some were satisfied with their moves, others describe the dispersal of these “families” as a deeply felt loss. While some were able to draw on support from children and grandchildren in their new homes, others describe experiences of profound isolation after relocation. PMID:24187415

  1. "Everyone called me grandma": Public housing demolition and relocation among older adults in Atlanta.

    PubMed

    Keene, Danya E; Ruel, Erin

    2013-01-01

    Over the last few decades public and political dissatisfaction with public housing projects and an increasing emphasis on poverty deconcentration has led to the demolition of public housing in cities across the country. A significant body of literature has examined experiences of relocation from public housing and their implications for the well-being of individuals and communities. While much of this literature has focused on young or middle-aged adults and children, older adults have also been affected by demolition and relocation. The displacement of older adults raises a new set of age and life-course specific concerns for the well-being of this population. In this paper, we analyze the relocation narratives of 25 former public housing residents in Atlanta, Georgia. Our analysis focuses on the loss of geographically rooted communities of kinship, support and belonging that many participants, particularly those who have aged in place, attribute to their former developments. Participants describe many material and psychosocial benefits associated with living in communities that were "like families" and where they often held important roles as respected elders. While some were satisfied with their moves, others describe the dispersal of these "families" as a deeply felt loss. While some were able to draw on support from children and grandchildren in their new homes, others describe experiences of profound isolation after relocation.

  2. Next Generation Nuclear Plant Project Evaluation of Siting a HTGR Co-generation Plant on an Operating Commercial Nuclear Power Plant Site

    SciTech Connect

    L.E. Demick

    2011-10-01

    This paper summarizes an evaluation by the Idaho National Laboratory (INL) Next Generation Nuclear Plant (NGNP) Project of siting a High Temperature Gas-cooled Reactor (HTGR) plant on an existing nuclear plant site that is located in an area of significant industrial activity. This is a co-generation application in which the HTGR Plant will be supplying steam and electricity to one or more of the nearby industrial plants.

  3. Sampling and Analysis Plan Waste Treatment Plant Seismic Boreholes Project.

    SciTech Connect

    Brouns, Thomas M.

    2007-07-15

    This sampling and analysis plan (SAP) describes planned data collection activities for four entry boreholes through the sediment overlying the Saddle Mountains Basalt, up to three new deep rotary boreholes through the Saddle Mountains Basalt and sedimentary interbeds, and one corehole through the Saddle Mountains Basalt and sedimentary interbeds at the Waste Treatment Plant (WTP) site. The SAP will be used in concert with the quality assurance plan for the project to guide the procedure development and data collection activities needed to support borehole drilling, geophysical measurements, and sampling. This SAP identifies the American Society of Testing Materials standards, Hanford Site procedures, and other guidance to be followed for data collection activities. Revision 3 incorporates all interim change notices (ICN) that were issued to Revision 2 prior to completion of sampling and analysis activities for the WTP Seismic Boreholes Project. This revision also incorporates changes to the exact number of samples submitted for dynamic testing as directed by the U.S. Army Corps of Engineers. Revision 3 represents the final version of the SAP.

  4. Pleasant Prairie Power Plant air quality control upgrade project, Pleasant Praire, Wisconsin

    SciTech Connect

    Gebhart, S.; Pennline, D.; Brodsky, I.; Bichler, D.

    2007-10-15

    We Energies recently completed a multiyear project at its Pleasant Prairie Power Plant to add a selective catalytic reduction system to one of its two units and a scrubber to both. These projects are described. 7 figs., 1 tab.

  5. Progress in Decommissioning the Humboldt Bay Power Plant - 13604

    SciTech Connect

    Rod, Kerry; Shelanskey, Steven K.; Kristofzski, John

    2013-07-01

    Decommissioning of the Pacific Gas and Electric (PG and E) Company Humboldt Bay Power Plant (HBPP) Unit 3 nuclear facility has now, after more than three decades of SAFSTOR and initial decommissioning work, transitioned to full-scale decommissioning. Decommissioning activities to date have been well orchestrated and executed in spite of an extremely small work site with space constricted even more by other concurrent on-site major construction projects including the demolition of four fossil units, construction of a new generating station and 60 KV switchyard upgrade. Full-scale decommissioning activities - now transitioning from Plant Systems Removal (PG and E self-perform) to Civil Works Projects (contractor performed) - are proceeding in a safe, timely, and cost effective manner. As a result of the successful decommissioning work to date (approximately fifty percent completed) and the intense planning and preparations for the remaining work, there is a high level of confidence for completion of all HBPP Unit 3 decommissions activities in 2018. Strategic planning and preparations to transition into full-scale decommissioning was carried out in 2008 by a small, highly focused project team. This planning was conducted concurrent with other critical planning requirements such as the loading of spent nuclear fuel into dry storage at the Independent Spent Fuel Storage Installation (ISFSI) finishing December 2008. Over the past four years, 2009 through 2012, the majority of decommissioning work has been installation of site infrastructure and removal of systems and components, known as the Plant System Removal Phase, where work scope was dynamic with significant uncertainty, and it was self-performed by PG and E. As HBPP Decommissioning transitions from the Plant System Removal Phase to the Civil Works Projects Phase, where work scope is well defined, a contracting plan similar to that used for Fossil Decommissioning will be implemented. Award of five major work scopes

  6. Technology Assessment of Dust Suppression Techniques Applied During Structural Demolition

    SciTech Connect

    Boudreaux, J.F.; Ebadian, M.A.; Williams, P.T.; Dua, S.K.

    1998-10-20

    Hanford, Fernald, Savannah River, and other sites are currently reviewing technologies that can be implemented to demolish buildings in a cost-effective manner. In order to demolish a structure properly and, at the same time, minimize the amount of dust generated from a given technology, an evaluation must be conducted to choose the most appropriate dust suppression technology given site-specific conditions. Thus, the purpose of this research, which was carried out at the Hemispheric Center for Environmental Technology (HCET) at Florida International University, was to conduct an experimental study of dust aerosol abatement (dust suppression) methods as applied to nuclear D and D. This experimental study targeted the problem of dust suppression during the demolition of nuclear facilities. The resulting data were employed to assist in the development of mathematical correlations that can be applied to predict dust generation during structural demolition.

  7. Project plan for the background soils project for the Paducah Gaseous Diffusion Plant, Paducah, Kentucky

    SciTech Connect

    1995-09-01

    The Background Soils Project for the Paducah Gaseous Diffusion Plant (BSPP) will determine the background concentration levels of selected naturally occurring metals, other inorganics, and radionuclides in soils from uncontaminated areas in proximity to the Paducah Gaseous Diffusion Plant (PGDP) in Paducah, Kentucky. The data will be used for comparison with characterization and compliance data for soils, with significant differences being indicative of contamination. All data collected as part of this project will be in addition to other background databases established for the PGDP. The BSPP will address the variability of surface and near-surface concentration levels with respect to (1) soil taxonomical types (series) and (2) soil sampling depths within a specific soil profile. The BSPP will also address the variability of concentration levels in deeper geologic formations by collecting samples of geologic materials. The BSPP will establish a database, with recommendations on how to use the data for contaminated site assessment, and provide data to estimate the potential human and health and ecological risk associated with background level concentrations of potentially hazardous constituents. BSPP data will be used or applied as follows.

  8. Saguaro Power Plant Solar Repowering Project. Volume III. Appendices. Final technical report, September 1979-July 1980

    SciTech Connect

    Weber, E.R.

    1980-07-01

    The conceptual design of a central receiver power plant using a molten salt for repowering the No. One Unit of Arizona Public Service's Saguaro power plant is given. This volume of the report contains the appendices: (A) effect of Arizona Public Service Company's demand profile on the amount of storage; (B) receiver design drawings; (C) plant characteristics and performance data; (E) existing plant description; (F) economic data; (G) simulation models; (H) plant cost data; and (I) project control network. (WHK)

  9. Tracking photon jumps with repeated quantum non-demolition parity measurements.

    PubMed

    Sun, L; Petrenko, A; Leghtas, Z; Vlastakis, B; Kirchmair, G; Sliwa, K M; Narla, A; Hatridge, M; Shankar, S; Blumoff, J; Frunzio, L; Mirrahimi, M; Devoret, M H; Schoelkopf, R J

    2014-07-24

    Quantum error correction is required for a practical quantum computer because of the fragile nature of quantum information. In quantum error correction, information is redundantly stored in a large quantum state space and one or more observables must be monitored to reveal the occurrence of an error, without disturbing the information encoded in an unknown quantum state. Such observables, typically multi-quantum-bit parities, must correspond to a special symmetry property inherent in the encoding scheme. Measurements of these observables, or error syndromes, must also be performed in a quantum non-demolition way (projecting without further perturbing the state) and more quickly than errors occur. Previously, quantum non-demolition measurements of quantum jumps between states of well-defined energy have been performed in systems such as trapped ions, electrons, cavity quantum electrodynamics, nitrogen-vacancy centres and superconducting quantum bits. So far, however, no fast and repeated monitoring of an error syndrome has been achieved. Here we track the quantum jumps of a possible error syndrome, namely the photon number parity of a microwave cavity, by mapping this property onto an ancilla quantum bit, whose only role is to facilitate quantum state manipulation and measurement. This quantity is just the error syndrome required in a recently proposed scheme for a hardware-efficient protected quantum memory using Schrödinger cat states (quantum superpositions of different coherent states of light) in a harmonic oscillator. We demonstrate the projective nature of this measurement onto a region of state space with well-defined parity by observing the collapse of a coherent state onto even or odd cat states. The measurement is fast compared with the cavity lifetime, has a high single-shot fidelity and has a 99.8 per cent probability per single measurement of leaving the parity unchanged. In combination with the deterministic encoding of quantum information in cat

  10. BACA Project: geothermal demonstration power plant. Final report

    SciTech Connect

    Not Available

    1982-12-01

    The various activities that have been conducted by Union in the Redondo Creek area while attempting to develop the resource for a 50 MW power plant are described. The results of the geologic work, drilling activities and reservoir studies are summarized. In addition, sections discussing the historical costs for Union's involvement with the project, production engineering (for anticipated surface equipment), and environmental work are included. Nineteen geothermal wells have been drilled in the Redondo Creek area of the Valles Caldera: a prominent geologic feature of the Jemez mountains consisting of Pliocene and Pleistocene age volcanics. The Redondo Creek area is within a complex longitudinal graben on the northwest flank of the resurgent structural dome of Redondo Peak and Redondo Border. The major graben faults, with associated fracturing, are geologically plausible candidates for permeable and productive zones in the reservoir. The distribution of such permeable zones is too erratic and the locations too imprecisely known to offer an attractive drilling target. Log analysis indicates there is a preferred mean fracture strike of N31W in the upper portion of Redondo Creek wells. This is approximately perpendicular to the major structure in the area, the northeast-striking Redondo Creek graben. The geothermal fluid found in the Redondo Creek reservoir is relatively benign with low brine concentrations and moderate H/sub 2/S concentrations. Geothermometer calculations indicate that the reservoir temperature generally lies between 500/sup 0/F and 600/sup 0/F, with near wellbore flashing occurring during the majority of the wells' production.

  11. 218 E-8 Borrow Pit Demolition Site clean closure soil evaluation report

    SciTech Connect

    Korematsu-Olund, D.M.

    1995-06-12

    This report summarizes the sampling activities undertaken and the analytical results obtained in a soil sampling and analyses study performed for the 218 E-8 Borrow Pit Demolition Site (218 E-8 Demolition Site). The 218 E-8 Demolition Site is identified as a Resource Conservation and Recovery Act (RCRA) treatment unit that will be closed in accordance with the applicable laws and regulations. The site was used for the thermal treatment of discarded explosive chemical products. No constituents of concern were found in concentrations indicating contamination of the soil by 218 E-8 Demolition Site activities.

  12. Environmental assessment for Mound Plant decontamination and decommissioning projects, Mound Plant, Miamisburg, Ohio

    SciTech Connect

    1995-05-01

    The U.S. Department of Energy (DOE) has prepared an Environmental Assessment (EA) for seven decontamination and decommissioning (D&D) projects at the Mound Plant in Miamisburg, Ohio, that have not been previously addressed in the Final Environmental Impact Statement for the Mound Facility (June 1979). Based on the information presented in the EA, the DOE has determined that the proposed action is not a major Federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act (NEPA) of 1969. Therefore, the preparation of an Environmental Impact Statement (EIS) is not required and the Department is issuing this Finding of No Significant Impact (FONSI).

  13. 7 CFR 330.206 - Permits for plant pest movement associated with National Defense projects.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... REGULATIONS; GENERAL; PLANT PESTS; SOIL, STONE, AND QUARRY PRODUCTS; GARBAGE Movement of Plant Pests § 330.206... facilitate research associated with National Defense projects through issuance of permits for movement of plant pests for such research, upon receiving assurance satisfactory to him that adequate...

  14. 7 CFR 330.206 - Permits for plant pest movement associated with National Defense projects.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... REGULATIONS; GENERAL; PLANT PESTS; SOIL, STONE, AND QUARRY PRODUCTS; GARBAGE Movement of Plant Pests § 330.206... facilitate research associated with National Defense projects through issuance of permits for movement of plant pests for such research, upon receiving assurance satisfactory to him that adequate...

  15. Augusta Newsprint: Paper Mill Pursues Five Projects Following Plant-Wide Energy Efficiency Assessment

    SciTech Connect

    Not Available

    2003-07-01

    Augusta Newsprint undertook a plant-wide energy efficiency assessment of its Augusta, Georgia, plant in 2001. The assessment helped the company decide to implement five energy efficiency projects. Four of the five projects will save the company 11,000 MWh of electrical energy (about$369,000) each year. The remaining project will produce more than$300,000 annually, from sale of the byproduct turpentine. The largest annual savings,$881,000, will come from eliminating Kraft pulp by using better process control. All of the projects could be applied to other paper mills and most of the projects could be applied in other industries.

  16. Successful Demolition of Historic Cape Canaveral Air Force Station Launch Facilities: Managing the Process to Maximize Recycle Value to Fund Demolition

    SciTech Connect

    Jones, A.; Hambro, L.; Hooper, K.

    2008-07-01

    This paper will present the history of the Atlas 36 and Titan 40 Space Launch Complexes (SLC), the facility assessment process, demolition planning, recycle methodology, and actual facility demolition that resulted in a 40% reduction in baseline cost. These two SLC launched hundreds of payloads into space from Cape Canaveral Air Force Station (AFS), Florida. The Atlas-Centaur family of rockets could lift small- to medium-size satellites designed for communications, weather, or military use, placing them with near pinpoint accuracy into their intended orbits. The larger Titan family was relied upon for heavier lifting needs, including launching military satellites as well as interplanetary probes. But despite their efficiency and cost-effectiveness, the Titan rockets, as well as earlier generation Atlas models, were retired in 2005. Concerns about potential environmental health hazards from PCBs and lead-based paint chipping off the facilities also contributed to the Air Force's decision in 2005 to dismantle and demolish the Atlas and Titan missile-launching systems. Lockheed Martin secured the complex following the final launch, removed equipment and turned over the site to the Air Force for decommissioning and demolition (D and D). AMEC was retained by the Air Force to perform demolition planning and facility D and D in 2004. AMEC began with a review of historical information, interviews with past operations personnel, and 100% facility assessment of over 100 structures. There where numerous support buildings that due to their age contained asbestos containing material (ACM), PCB-impacted material, and universal material that had to be identified and removed prior to demolition. Environmental testing had revealed that the 36B mobile support tower (MST) exceeded the TSCA standard for polychlorinated biphenyls (PCB) paint (<50 ppm), as did the high bay sections of the Titan Vertical Integration Building (VIB). Thus, while most of the steel structures could be

  17. 7 CFR 1412.48 - Planting Transferability Pilot Project.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... of certain crops in certain States on base acres without violating the DCP or ACRE contract. Base... Project. (b) Producers interested in participating in the Project must first be enrolled in either a DCP... Project, crops permitted on DCP base acres are cucumbers, green peas, lima beans, pumpkins, snap...

  18. The decontamination, decommissioning, and demolition of loss-of-fluid test reactor at the Idaho National Laboratory Site

    SciTech Connect

    Floerke, J.P.; Borschel, Th.F.; Rhodes, L.K.

    2007-07-01

    resolution through the contractor (CH2M-WG Idaho), the U.S. Department of Energy, the Idaho State Historic Preservation Office (SHPO), and the Advisory Council on Historic Preservation. The project team identified multiple hazards that would result if conventional techniques were used to demolish the dome. The physical structure of the vessel containment facility reached 30 meters (98 feet) above grade, presenting significant worker safety hazards created by hoisting and rigging activities. The dome also included a polar crane, 19 meters (62 feet) above grade, that posed similar hazards to workers. The need to work on significantly elevated surfaces, and the thickness of the dome walls - 30 millimeters (1-3/16 inches) of carbon steel - would prove difficult with traditional arc plasma cutting tools. The dome's proximity to operating facilities with equipment sensitive to vibration added to the demolition challenges. To address cultural resource issues, the project team engaged all parties in negotiations and in mapping a path foreword. Open and frequent communication resulted in a Memorandum of Agreement, with stipulations that mitigated the adverse affects of the intended demolition action. The unique mitigating actions resulted in a favorable agreement being signed and issued. To mitigate hazards posed by the height of the facility, the project team had to abandon traditional D and D techniques and employ other methods to complete demolition safely. A different approach and a change in demolition sequence resulted in the safe and efficient removal of the one-of-a-kind containment facility. The approach reduced the use of aerial lifts, aboveground size reduction, and dangerous hoisting and rigging activities that could pose significant hazards to workers. (authors)

  19. 24 CFR 970.15 - Specific criteria for HUD approval of demolition requests.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... Housing and Urban Development (Continued) OFFICE OF ASSISTANT SECRETARY FOR PUBLIC AND INDIAN HOUSING, DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT PUBLIC HOUSING PROGRAM-DEMOLITION OR DISPOSITION OF PUBLIC... criteria for disapproval under 24 CFR 970.29. An application for the demolition of all or a portion of...

  20. 76 FR 32313 - Safety Zone; Chelsea St. Bridge Demolition, Chelsea River, Chelsea, MA

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-06-06

    ... SECURITY Coast Guard 33 CFR Part 165 RIN 1625-AA00 Safety Zone; Chelsea St. Bridge Demolition, Chelsea... demolition of the Chelsea St. Bridge. This safety zone is necessary to provide for the safety of life on... would occur before the rulemaking process was complete. The Chelsea Street Bridge will need to...

  1. 76 FR 35006 - Recovery Policy RP9523.4, Demolition of Private Structures

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-06-15

    ... SECURITY Federal Emergency Management Agency Recovery Policy RP9523.4, Demolition of Private Structures..., Demolition of Private Structures. DATES: Comments must be received by July 15, 2011. ADDRESSES: Comments must... private structures under the provisions of the Public Assistance Program. FEMA proposes to include...

  2. 75 FR 73962 - Safety Zone; Bridge Demolition; Illinois River, Seneca, IL

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-11-30

    ... SECURITY Coast Guard 33 CFR Part 165 RIN 1625-AA00 Safety Zone; Bridge Demolition; Illinois River, Seneca... temporary safety zone on the Illinois River near Seneca, Illinois. This zone is intended to restrict vessels from a portion of the Illinois River due to the demolition of the Seneca Highway Bridge. This...

  3. Decommissioning and Demolition of a Redundant UK Research Facility at AWE Aldermaston - 12453

    SciTech Connect

    Pritchard, Paul

    2012-07-01

    The redundant two-storey brick built research facility on the AWE Site at Aldermaston, UK is in the closing stages of decommissioning and demolition. The facility was used for a variety of purposes up to 1995 predominately involving the use of alpha-emitting isotopes. The two main areas of alpha-based contamination have been decommissioned with the removal of hot -boxes and fume cupboards on the ground floor and HEPA filter units and ventilation equipment on the first floor. Many of these activities were undertaken using both airline fed suits, (supplied via a free standing mobile unit), and full face respirators. Asbestos materials were located and cleared from the first floor by specialist contractor. All sections of active drain running from the building to the site active effluent disposal system were removed early in the program using established techniques with specialist monitoring equipment used to provide confidence in the data required for disposal of the decommissioning debris. In particular a dedicated High Resolution Gamma Spectrometer (radioactive materials scanning unit) was utilized to categorise waste drums and wrapped packages. The building has been decommissioned and the monitoring and sampling of the structure was completed in November 2011 - the results demonstrating that the building was clear of contamination in accordance with UK clearance and exemption requirements. The demolition plan was developed and implemented in December with site excavation of foundations and site clearance currently ongoing in preparation for final site backfill activities and project close. A number of useful lessons have been learnt during the operations and are set out at the rear of the main text. (authors)

  4. 10. SOUTHEAST EXTERIOR CORNER. During demolition large iron bars were ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    10. SOUTHEAST EXTERIOR CORNER. During demolition large iron bars were found embedded in the south brick walls about 11 courses above the water table. These were possibly used to secure the roof structure of a shed which housed the fire engine of the Relief Fire Company (see Articles of Agreement, 1815, papers of the Central Philadelphia Meeting), which specified that the Engine House was to be situated at the northeast corner of the lot. Perhaps at some later date the shed was moved. - Twelfth Street Meeting House, 20 South Twelfth Street, Philadelphia, Philadelphia County, PA

  5. Quantum demolition measurement of photon statistics by atomic beam deflection

    NASA Astrophysics Data System (ADS)

    Herkommer, A. M.; Akulin, V. M.; Schleich, W. P.

    1992-12-01

    We consider the deflection of a resonant two-level atom by a quantized electromagnetic field using the Jaynes-Cummings Hamiltonian. We show that a joint measurement of the atomic momentum and an appropriate field variable allows us to reconstruct the original photon statistics even for this demolition Hamiltonian. We demonstrate that the momentum distribution of atoms scattered at the nodes of the standing wave also follows the original photon statistics of the field. In this sense a recent experiment on the optical Stern-Gerlach effect [T. Sleator et al., Phys. Rev. Lett. 68, 1996 (1992)] measures the intensity fluctuations of the standing wave.

  6. Overview regarding construction and demolition waste in Spain.

    PubMed

    Rodríguez-Robles, Desirée; García-González, Julia; Juan-Valdés, Andrés; Morán-Del Pozo, Julia M; Guerra-Romero, M Ignacio

    2015-01-01

    The construction sector comprises a number of activities that may result in environmental impacts of considerable magnitude, waste generation being one of the major negative effects of this industry due to the large streams generated. Proper knowledge of the environmental problem caused by the sector is of great importance in order to achieve an effective waste management. Thus, this paper analyse the Spanish situation regarding construction and demolition waste (CDW) compared with other European Union countries; which sets out the current figures of the CDW scenario (legislation, generation, composition, treatment and market) as well as the difficulties encountered when handling this residue.

  7. Global gasification database: project statistics, news and analysis on over 300 plants worldwide

    SciTech Connect

    2000-07-01

    The database profiles over 300 gasification projects worldwide, in all stages of development, and is updated daily. The database provides investors, equipment manufacturers, technology providers, developers, and other industry personnel real-time information and in-depth analysis of gasification plants on a project-by-project basis. The database gives users detailed information to assist in technology selection and project deployment strategies and alerts them to breaking market opportunities. The database can be trialed online at www.zeuslibrary.com/Gasification.

  8. Long Frontal Projections Help Battus philenor (Lepidoptera: Papilionidae) Larvae Find Host Plants.

    PubMed

    Kandori, Ikuo; Tsuchihara, Kazuko; Suzuki, Taichi A; Yokoi, Tomoyuki; Papaj, Daniel R

    2015-01-01

    Animals sometimes develop conspicuous projections on or near their heads as, e.g., weaponry, burrowing or digging tools, and probes to search for resources. The frontal projections that insects generally use to locate and assess resources are segmented appendages, including antennae, maxillary palps, and labial palps. There is no evidence to date that arthropods, including insects, use projections other than true segmental appendages to locate food. In this regard, it is noteworthy that some butterfly larvae possess a pair of long antenna-like projections on or near their heads. To date, the function of these projections has not been established. Larvae of pipevine swallowtail butterflies Battus philenor (Papilionidae) have a pair of long frontal fleshy projections that, like insect antennae generally, can be actively moved. In this study, we evaluated the possible function of this pair of long moveable frontal projections. In laboratory assays, both frontal projections and lateral ocelli were shown to increase the frequency with which search larvae found plants. The frontal projections increased finding of host and non-host plants equally, suggesting that frontal projections do not detect host-specific chemical cues. Detailed SEM study showed that putative mechanosensillae are distributed all around the frontal as well as other projections. Taken together, our findings suggest that the frontal projections and associated mechanosensillae act as vertical object detectors to obtain tactile information that, together with visual information from lateral ocelli and presumably chemical information from antennae and mouthparts, help larvae to find host plants. Field observations indicate that host plants are small and scattered in southern Arizona locations. Larvae must therefore find multiple host plants to complete development and face significant challenges in doing so. The frontal projections may thus be an adaptation for finding a scarce resource before starving to

  9. Long Frontal Projections Help Battus philenor (Lepidoptera: Papilionidae) Larvae Find Host Plants

    PubMed Central

    Kandori, Ikuo; Tsuchihara, Kazuko; Suzuki, Taichi A.; Yokoi, Tomoyuki; Papaj, Daniel R.

    2015-01-01

    Animals sometimes develop conspicuous projections on or near their heads as, e.g., weaponry, burrowing or digging tools, and probes to search for resources. The frontal projections that insects generally use to locate and assess resources are segmented appendages, including antennae, maxillary palps, and labial palps. There is no evidence to date that arthropods, including insects, use projections other than true segmental appendages to locate food. In this regard, it is noteworthy that some butterfly larvae possess a pair of long antenna-like projections on or near their heads. To date, the function of these projections has not been established. Larvae of pipevine swallowtail butterflies Battus philenor (Papilionidae) have a pair of long frontal fleshy projections that, like insect antennae generally, can be actively moved. In this study, we evaluated the possible function of this pair of long moveable frontal projections. In laboratory assays, both frontal projections and lateral ocelli were shown to increase the frequency with which search larvae found plants. The frontal projections increased finding of host and non-host plants equally, suggesting that frontal projections do not detect host-specific chemical cues. Detailed SEM study showed that putative mechanosensillae are distributed all around the frontal as well as other projections. Taken together, our findings suggest that the frontal projections and associated mechanosensillae act as vertical object detectors to obtain tactile information that, together with visual information from lateral ocelli and presumably chemical information from antennae and mouthparts, help larvae to find host plants. Field observations indicate that host plants are small and scattered in southern Arizona locations. Larvae must therefore find multiple host plants to complete development and face significant challenges in doing so. The frontal projections may thus be an adaptation for finding a scarce resource before starving to

  10. Long Frontal Projections Help Battus philenor (Lepidoptera: Papilionidae) Larvae Find Host Plants.

    PubMed

    Kandori, Ikuo; Tsuchihara, Kazuko; Suzuki, Taichi A; Yokoi, Tomoyuki; Papaj, Daniel R

    2015-01-01

    Animals sometimes develop conspicuous projections on or near their heads as, e.g., weaponry, burrowing or digging tools, and probes to search for resources. The frontal projections that insects generally use to locate and assess resources are segmented appendages, including antennae, maxillary palps, and labial palps. There is no evidence to date that arthropods, including insects, use projections other than true segmental appendages to locate food. In this regard, it is noteworthy that some butterfly larvae possess a pair of long antenna-like projections on or near their heads. To date, the function of these projections has not been established. Larvae of pipevine swallowtail butterflies Battus philenor (Papilionidae) have a pair of long frontal fleshy projections that, like insect antennae generally, can be actively moved. In this study, we evaluated the possible function of this pair of long moveable frontal projections. In laboratory assays, both frontal projections and lateral ocelli were shown to increase the frequency with which search larvae found plants. The frontal projections increased finding of host and non-host plants equally, suggesting that frontal projections do not detect host-specific chemical cues. Detailed SEM study showed that putative mechanosensillae are distributed all around the frontal as well as other projections. Taken together, our findings suggest that the frontal projections and associated mechanosensillae act as vertical object detectors to obtain tactile information that, together with visual information from lateral ocelli and presumably chemical information from antennae and mouthparts, help larvae to find host plants. Field observations indicate that host plants are small and scattered in southern Arizona locations. Larvae must therefore find multiple host plants to complete development and face significant challenges in doing so. The frontal projections may thus be an adaptation for finding a scarce resource before starving to

  11. 24 CFR 970.7 - General requirements for HUD approval of a PHA demolition/disposition application.

    Code of Federal Regulations, 2013 CFR

    2013-04-01

    ... demolition or disposition in the PHA Annual Plan and timetable under 24 CFR part 903 (except in the case of... review of the proposed demolition or disposition in accordance with 24 CFR parts 50 or 58 for any demolition or disposition of public housing property covered under this part, as required under 24 CFR...

  12. Method for assigning sites to projected generic nuclear power plants

    SciTech Connect

    Holter, G.M.; Purcell, W.L.; Shutz, M.E.; Young, J.R.

    1986-07-01

    Pacific Northwest Laboratory developed a method for forecasting potential locations and startup sequences of nuclear power plants that will be required in the future but have not yet been specifically identified by electric utilities. Use of the method results in numerical ratings for potential nuclear power plant sites located in each of the 10 federal energy regions. The rating for each potential site is obtained from numerical factors assigned to each of 5 primary siting characteristics: (1) cooling water availability, (2) site land area, (3) power transmission land area, (4) proximity to metropolitan areas, and (5) utility plans for the site. The sequence of plant startups in each federal energy region is obtained by use of the numerical ratings and the forecasts of generic nuclear power plant startups obtained from the EIA Middle Case electricity forecast. Sites are assigned to generic plants in chronological order according to startup date.

  13. Guide for prioritizing power plant productivity improvement projects: handbook of availability improvement methodology

    SciTech Connect

    Not Available

    1981-09-15

    As part of its program to help improve electrical power plant productivity, the Department of Energy (DOE) has developed a methodology for evaluating productivity improvement projects. This handbook presents a simplified version of this methodology called the Availability Improvement Methodology (AIM), which provides a systematic approach for prioritizing plant improvement projects. Also included in this handbook is a description of data taking requirements necessary to support the AIM methodology, benefit/cost analysis, and root cause analysis for tracing persistent power plant problems. In applying the AIM methodology, utility engineers should be mindful that replacement power costs are frequently greater for forced outages than for planned outages. Equivalent availability includes both. A cost-effective ranking of alternative plant improvement projects must discern between those projects which will reduce forced outages and those which might reduce planned outages. As is the case with any analytical procedure, engineering judgement must be exercised with respect to results of purely mathematical calculations.

  14. Use of Air Modeling to Reduce Facility Demolition Costs

    SciTech Connect

    Smith, Dennis; Sanford, Peter; Parsons, Duane A.

    2003-02-26

    DOE faces the problem of decommissioning facilities contaminated with plutonium, uranium, and beryllium. The standard process has been to remove the contaminated process equipment from a facility, and then decontaminate the residual radiological and hazardous contamination from the facility structure to an ''unconditional release'' level. The facility would then be taken down as a clean demolition. Several beryllium-contaminated facilities were identified that will be particularly difficult to decontaminate to these release levels. A number of alternative decommissioning approaches were investigated that would require less decontamination, and thus reduced cost and schedule. Initial alternative approaches proposed erection of barriers (i.e. building-size tent structures with ventilation controls) to minimize the release of contamination to the environment. More recently we have investigated methods to control contamination at the structure surfaces before and during demolition, and model the risk posed to the workers, public, and the environment by the small residual material actually dispersed. This approach promises to minimize decontamination by removing only the highest contamination levels, and eliminates the need for erecting large contamination control structures along with the attendant ventilation equipment and administrative controls. The modeling has demonstrated the regulatory acceptability of this approach, and the approach is ready to be discussed with the regulators and the public.

  15. Quantum demolition filtering and optimal control of unstable systems.

    PubMed

    Belavkin, V P

    2012-11-28

    A brief account of the quantum information dynamics and dynamical programming methods for optimal control of quantum unstable systems is given to both open loop and feedback control schemes corresponding respectively to deterministic and stochastic semi-Markov dynamics of stable or unstable systems. For the quantum feedback control scheme, we exploit the separation theorem of filtering and control aspects as in the usual case of quantum stable systems with non-demolition observation. This allows us to start with the Belavkin quantum filtering equation generalized to demolition observations and derive the generalized Hamilton-Jacobi-Bellman equation using standard arguments of classical control theory. This is equivalent to a Hamilton-Jacobi equation with an extra linear dissipative term if the control is restricted to Hamiltonian terms in the filtering equation. An unstable controlled qubit is considered as an example throughout the development of the formalism. Finally, we discuss optimum observation strategies to obtain a pure quantum qubit state from a mixed one. PMID:23091216

  16. Hybrid Cooling for Geothermal Power Plants: Final ARRA Project Report

    SciTech Connect

    Bharathan, D.

    2013-06-01

    Many binary-cycle geothermal plants use air as the heat rejection medium. Usually this is accomplished by using an air-cooled condenser (ACC) system to condense the vapor of the working fluid in the cycle. Many air-cooled plants suffer a loss of production capacity of up to 50% during times of high ambient temperatures. Use of limited amounts of water to supplement the performance of ACCs is investigated. Deluge cooling is found to be one of the least-cost options. Limiting the use of water in such an application to less than one thousand operating hours per year can boost plant output during critical high-demand periods while minimizing water use in binary-cycle geothermal power plants.

  17. Pupils' Ideas about Flowering Plants. Learning in Science Project (Primary). Working Paper No. 125.

    ERIC Educational Resources Information Center

    Biddulph, Fred

    The Learning in Science Project (Primary)--LISP(P)--investigated the ideas and interests children have about flowering plants (in particular whether these plants have a life cycle). Data were obtained from: individual interviews with children, ages 7- to 14-year-old (10 students for each age level), using the "interview-about-instances" (IAI)…

  18. Plant a Planetary Pennant, and Other Art Projects

    ERIC Educational Resources Information Center

    Wilcox, Claudia; and others

    1970-01-01

    Art projects discussed include the creation of outer space flags, painting with wool, making ceramics and sculptures from inexpensive ingredients, constructing cardboard rockets, costume design, and reed representations of flowers and insects. (DB)

  19. Risk assessment of exposure to particulate output of a demolition site.

    PubMed

    Brown, A; Barrett, J E S; Robinson, H; Potgieter-Vermaak, S

    2015-08-01

    Whilst vehicular and industrial contributions to the airborne particulate budget are well explored, the input due to building demolition is relatively unknown. Air quality is of importance to human health, and it is well known that composition of airborne particles can have a significant influence on both chronic and acute health effects. Road dust (RD) was collected before and after the demolition of a large building to elucidate changes in elemental profile. Rainfall and PM10 mass concentration data aided interpretation of the elemental data. Quantification of Al, As, Ba, Ca, Cd, Cr, Cu, Fe, K, Mg, Mn, Na, Ni, Pb, Rh, S, Si, Sn, Ti, V and Zn was carried out. It was found that only Al, K, Mg, Si and S increased in concentration across all size fractions after the building demolition. Risk assessment was then carried out on elements with applicable reference dose values to assess the potential health risks due to the demolition. Significant risk to children was observed for chromium and aluminium exposure. PM10, monitored 40 metres from the demolition site, indicated no abnormal concentrations during the demolition; however, rainfall data were shown to affect the concentration of PM10. The elemental data observed in this study could possibly indicate the role of increased sulphur concentrations (in this case as a result of the demolition) on the buffer capacity of RD, hence leaching metals into rainwater. PMID:26173774

  20. Projecting labor demand and worker immigration at nuclear power plant construction sites: an evaluation of methodology

    SciTech Connect

    Herzog, H.W. Jr; Schlottmann, A.M.; Schriver, W.R.

    1981-12-01

    The study evaluates methodology employed for the projection of labor demand at, and worker migration to, nuclear power plant construction sites. In addition, suggestions are offered as to how this projection methodology might be improved. The study focuses on projection methodologies which forecast either construction worker migration or labor requirements of alternative types of construction activity. Suggested methodological improvements relate both to institutional factors within the nuclear power plant construction industry, and to a better use of craft-specific data on construction worker demand/supply. In addition, the timeliness and availability of the regional occupational data required to support, or implement these suggestions are examined.

  1. 7 CFR 1412.48 - Planting Transferability Pilot Project.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... a program of crop rotation on the farm to achieve agronomic and pest and disease management benefits... PROGRAM AND AVERAGE CROP REVENUE ELECTION PROGRAM FOR THE 2008 AND SUBSEQUENT CROP YEARS Direct and... § 1412.47, for each of the 2009 and subsequent crop years, the Planting Transferability Pilot...

  2. 7 CFR 1412.48 - Planting Transferability Pilot Project.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... a program of crop rotation on the farm to achieve agronomic and pest and disease management benefits... PROGRAM AND AVERAGE CROP REVENUE ELECTION PROGRAM FOR THE 2008 AND SUBSEQUENT CROP YEARS Direct and... § 1412.47, for each of the 2009 and subsequent crop years, the Planting Transferability Pilot...

  3. 7 CFR 1412.48 - Planting Transferability Pilot Project.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... a program of crop rotation on the farm to achieve agronomic and pest and disease management benefits... PROGRAM AND AVERAGE CROP REVENUE ELECTION PROGRAM FOR THE 2008 AND SUBSEQUENT CROP YEARS Direct and... § 1412.47, for each of the 2009 and subsequent crop years, the Planting Transferability Pilot...

  4. 7 CFR 1412.48 - Planting Transferability Pilot Project.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... a program of crop rotation on the farm to achieve agronomic and pest and disease management benefits... PROGRAM AND AVERAGE CROP REVENUE ELECTION PROGRAM FOR THE 2008 AND SUBSEQUENT CROP YEARS Direct and... § 1412.47, for each of the 2009 and subsequent crop years, the Planting Transferability Pilot...

  5. Quality assessment for recycling aggregates from construction and demolition waste: An image-based approach for particle size estimation.

    PubMed

    Di Maria, Francesco; Bianconi, Francesco; Micale, Caterina; Baglioni, Stefano; Marionni, Moreno

    2016-02-01

    The size distribution of aggregates has direct and important effects on fundamental properties of construction materials such as workability, strength and durability. The size distribution of aggregates from construction and demolition waste (C&D) is one of the parameters which determine the degree of recyclability and therefore the quality of such materials. Unfortunately, standard methods like sieving or laser diffraction can be either very time consuming (sieving) or possible only in laboratory conditions (laser diffraction). As an alternative we propose and evaluate the use of image analysis to estimate the size distribution of aggregates from C&D in a fast yet accurate manner. The effectiveness of the procedure was tested on aggregates generated by an existing C&D mechanical treatment plant. Experimental comparison with manual sieving showed agreement in the range 81-85%. The proposed technique demonstrated potential for being used on on-line systems within mechanical treatment plants of C&D.

  6. Forecasting of construction and demolition waste in Brazil.

    PubMed

    Paz, Diogo Hf; Lafayette, Kalinny Pv

    2016-08-01

    The objective of this article is to develop a computerised tool (software) that facilitates the analysis of strategies for waste management on construction sites through the use of indicators of construction and demolition waste generation. The development involved the following steps: knowledge acquisition, structuring the system, coding and system evaluation. The step of knowledge acquisition aims to provide subsidies for the representation of them through models. In the step of structuring the system, it was presented the structuring and formalisation of knowledge for the development of the system, and has two stages: the construction of the conceptual model and the subsequent instantiation of the model. The coding system aims to implement (code) the conceptual model developed in a model played by computer (digital). The results showed that the system is very useful and applicable in construction sites, helping to improve the quality of waste management, and creating a database that will support new research. PMID:27177555

  7. Forecasting of construction and demolition waste in Brazil.

    PubMed

    Paz, Diogo Hf; Lafayette, Kalinny Pv

    2016-08-01

    The objective of this article is to develop a computerised tool (software) that facilitates the analysis of strategies for waste management on construction sites through the use of indicators of construction and demolition waste generation. The development involved the following steps: knowledge acquisition, structuring the system, coding and system evaluation. The step of knowledge acquisition aims to provide subsidies for the representation of them through models. In the step of structuring the system, it was presented the structuring and formalisation of knowledge for the development of the system, and has two stages: the construction of the conceptual model and the subsequent instantiation of the model. The coding system aims to implement (code) the conceptual model developed in a model played by computer (digital). The results showed that the system is very useful and applicable in construction sites, helping to improve the quality of waste management, and creating a database that will support new research.

  8. Technology Assessment of Dust Suppression Techniques applied During Structural Demolition

    SciTech Connect

    Boudreaux, J.F.; Ebadian, M.A.; Dua, S.K.

    1997-08-06

    Hanford, Fernald, Savannah River, and other sites are currently reviewing technologies that can be implemented to demolish buildings in a cost-effective manner. In order to demolish a structure and, at the same time, minimize the amount of dust generated by a given technology, an evaluation must be conducted to choose the most appropriate dust suppression technology. Thus, the purpose of this research, which was conducted by the Hemispheric Center for Environmental Technology (HCET) at Florida International University (FIU), was to perform an experimental study of dust aerosol abatement (dust suppression) methods as applied to nuclear D and D. This experimental study specifically targeted the problem of dust suppression during demolition. The resulting data were used in the development of mathematical correlations that can be applied to structural demolition. In the Fiscal Year 1996 (FY96), the effectiveness of different dust suppressing agents was investigated for different types of concrete blocks. Initial tests were conducted in a broad particle size range. In Fiscal Year 1997 (FY97), additional tests were performed in the size range in which most of the particles were detected. Since particle distribution is an important parameter for predicting deposition in various compartments of the human respiratory tract, various tests were aimed at determining the particle size distribution of the airborne dust particles. The effectiveness of dust suppressing agents for particles of various size was studied. Instead of conducting experiments on various types of blocks, it was thought prudent to carry out additional tests on blocks of the same type. Several refinements were also incorporated in the test procedures and data acquisition system used in FY96.

  9. Salton Sea Project, Phase 1. [solar pond power plant

    NASA Technical Reports Server (NTRS)

    Peelgren, M. L.

    1982-01-01

    A feasibility study was made for a salt gradient solar pond power plant in or near the Salton Sea of California. The conclusions support continuance 5-MWe proof-of-concept experiment, and ultimate construction by an electric utility company of a 600-MWe plant. The Solar Pond concept would be an environmental benefit to the Salton Sea by reversing the increasing salinity trend. The greatest cost drivers are the lake dike construction and pond sealing. Problems to be resolved include method of brine production from Salton Sea water for the first unit (which requires evaporation pond area and time), the high turbidity and color content of the Salton Sea water (which requires pretreatment), and other questions related to pond permeability, bio-activity and soil/brine chemical reactions. All technical and environmental problems appear solvable and/or manageable if care is taken in mitigating impacts.

  10. New Generation Nuclear Plant (NGNP) Project, Preliminary Point Design

    SciTech Connect

    F. H. Southworth; P. E. MacDonald; A. M. Baxter; P. D. Bayless; J. M. Bolin; H. D. Gougar; R. L. Moore; A. M. Ougouag; M. B. Richards; R. L. Sant; J. W. Sterbentz; W. K. Terry

    2004-03-01

    This paper provides a preliminary assessment of two possible versions of the Next Generation Nuclear Plant (NGNP), a prismatic fuel type helium gas-cooled reactor and a pebblebed fuel helium gas reactor. Both designs will meet the three basic requirements that have been set for the NGNP: a coolant outlet temperature of 1000 C, passive safety, and a total power output consistent with that expected for commercial high-temperature gas-cooled reactors.

  11. Summary for the Next Generation Nuclear Plant Project in Review

    SciTech Connect

    L.E. Demick

    2010-08-01

    This paper reports on the major progress that the NGNP Project has made toward developing and commercializing the HTGR technology. Significant R&D progress has been made in addressing key technical issues for qualification of the HTGR fuel and graphite, codification of high temperature materials and verification and validation of design codes. Work is also progressing in heat transfer/transport design and testing and in development of the high temperature steam electrolysis hydrogen production process. A viable licensing strategy has been formulated in coordination with the NRC and DOE. White papers covering key licensing issues have been and will continue to be submitted and necessary discussions of these key issues have begun with the NRC. Continued government support is needed to complete the Project objectives as established in the 2005 Energy Policy Act.

  12. Summary for the Next Generation Nuclear Plant Project in Review

    SciTech Connect

    L.E. Demick

    2010-09-01

    This paper reports on the major progress that the NGNP Project has made toward developing and commercializing the HTGR technology. Significant R&D progress has been made in addressing key technical issues for qualification of the HTGR fuel and graphite, codification of high temperature materials and verification and validation of design codes. Work is also progressing in heat transfer/transport design and testing and in development of the high temperature steam electrolysis hydrogen production process. A viable licensing strategy has been formulated in coordination with the NRC and DOE. White papers covering key licensing issues have been and will continue to be submitted and necessary discussions of these key issues have begun with the NRC. Continued government support is needed to complete the Project objectives as established in the 2005 Energy Policy Act.

  13. Next Generation Nuclear Plant Project 2009 Status Report

    SciTech Connect

    Larry Demick; Jim Kinsey; Keith Perry; Dave Petti

    2010-05-01

    The mission of the NGNP Project is to broaden the environmental and economic benefits of nuclear energy technology to the United States and other economies by demonstrating its applicability to market sectors not served by light water reactors (LWRs). Those markets typically use fossil fuels to fulfill their energy needs, and high temperature gas-cooled reactors (HTGRs) like the NGNP can reduce this dependence and the resulting carbon footprint.

  14. Indicators to assess the recovery of natural resources contained in demolition waste.

    PubMed

    Roussat, Nicolas; Méhu, Jacques; Dujet, Christiane

    2009-03-01

    Demolition waste materials are one of the major industrial waste deposits in many countries and represent an important quantity of potential resources that are not exploited, because the major part of these wastes go to landfill. Indeed, recycling or recovery of demolition waste can reduce the need of primary natural resources. This article gives indicators and a method to analyse demolition waste management with regard to the use of resources contained in these wastes. Demolition wastes are characterized by their contents in energy and raw materials. This content is quantified on the basis of the sum of energy and raw materials necessary for the construction of the building considering the non-renewable character of materials contained in wastes. In fact, this content represents the environmental investment which was necessary to construct the building. An energy balance and a mass balance, with this concept of ;raw material and energy' content, can allow a strategy of waste management to be determined in order to salvage the most important parts of energy and raw materials contained in demolition waste, and so identify the strategy which permits a maximum fraction of the initial environmental investment to be saved. Five waste management scenarios concerning building demolition were assessed with this method and these indicators, and the results are presented in this article. PMID:19244415

  15. Influence of construction and demolition waste management on the environmental impact of buildings

    SciTech Connect

    Coelho, Andre; Brito, Jorge de

    2012-03-15

    Highlights: Black-Right-Pointing-Pointer Environmental impacts of different demolition practices. Black-Right-Pointing-Pointer 'Top-down' approach to the Life Cycle Analysis methodology. Black-Right-Pointing-Pointer Results based on real buildings measurements and demolition contractor activities. Black-Right-Pointing-Pointer Not every type of selective demolition brings about environmental benefits. - Abstract: The purpose of this study is to quantify comparable environmental impacts within a Life Cycle Analysis (LCA) perspective, for buildings in which the first (Materials) and last (End of Life) life cycle stages are adjusted to several waste/material management options. Unlike most LCAs, the approach is 'top-down' rather than 'bottom-up', which usually involves large amounts of data and the use of specific software applications. This approach is considered appropriate for a limited but expedient LCA designed to compare the environmental impacts of different life cycle options. Present results, based on real buildings measurements and demolition contractor activities, show that shallow, superficial, selective demolition may not result in reduced environmental impacts. Calculations actually show an increase (generally less than 5%) in most impact categories for the Materials and End of Life stages because of extra transportation needs. However, core material separation in demolition operations and its recycling and/or reuse does bring environmental benefits. A reduction of around 77% has been estimated in the climate change impact category, 57% in acidification potential and 81% in the summer smog impact (for the life cycle stages referred).

  16. Auxiliary feedwater system risk-based inspection guide for the South Texas Project nuclear power plant

    SciTech Connect

    Bumgardner, J.D.; Nickolaus, J.R.; Moffitt, N.E.; Gore, B.F.; Vo, T.V.

    1993-12-01

    In a study sponsored by the US Nuclear Regulatory Commission (NRC), Pacific Northwest Laboratory has developed and applied a methodology for deriving plant-specific risk-based inspection guidance for the auxiliary feedwater (AFW) system at pressurized water reactors that have not undergone probabilistic risk assessment (PRA). This methodology uses existing PRA results and plant operating experience information. Existing PRA-based inspection guidance information recently developed for the NRC for various plants was used to identify generic component failure modes. This information was then combined with plant-specific and industry-wide component information and failure data to identify failure modes and failure mechanisms for the AFW system at the selected plants. South Texas Project was selected as a plant for study. The product of this effort is a prioritized listing of AFW failures which have occurred at the plant and at other PWRs. This listing is intended for use by the NRC inspectors in preparation of inspection plans addressing AFW risk important components at the South Texas Project plant.

  17. Next Generation Nuclear Plant (NGNP) Prismatic HTGR Conceptual Design Project - Final Technical Report

    SciTech Connect

    Saurwein, John

    2011-07-15

    This report is the Final Technical Report for the Next Generation Nuclear Plant (NGNP) Prismatic HTGR Conceptual Design Project conducted by a team led by General Atomics under DOE Award DE-NE0000245. The primary overall objective of the project was to develop and document a conceptual design for the Steam Cycle Modular Helium Reactor (SC-MHR), which is the reactor concept proposed by General Atomics for the NGNP Demonstration Plant. The report summarizes the project activities over the entire funding period, compares the accomplishments with the goals and objectives of the project, and discusses the benefits of the work. The report provides complete listings of the products developed under the award and the key documents delivered to the DOE.

  18. Recycling of construction and demolition waste materials: a chemical-mineralogical appraisal.

    PubMed

    Bianchini, G; Marrocchino, E; Tassinari, R; Vaccaro, C

    2005-01-01

    Building activity is currently demanding remarkable amounts of inert materials (such as gravel and sand) that are usually provided by alluvial sediments. The EU directives and Italian Legislation are encouraging the re-use of construction and demolition waste provided by continuous urban redevelopment. The re-utilisation of building waste is a relatively new issue for Italy: unfortunately the employment of recycled inert materials is still limited to general bulk and drainage fills, while a more complete re-evaluation is generally hampered by the lack of suitable recycling plants. In this paper, chemical-mineralogical characterization of recycled inert materials was carried out after preliminary crushing and grain-size sorting. XRF and XRD analysis of the different grain-size classes allowed us to recognise particular granulometric classes that can be re-utilised as first-order material in the building activity. Specifically, the presented chemical-mineralogical appraisal indicates that the recycled grain-size fraction 0.6-0.125 mm could be directly re-employed in the preparation of new mortar and concrete, while finer fractions could be considered as components for industrial processing in the preparation of cements and bricks/tiles. PMID:15737712

  19. Recycled blocks with improved sound and fire insulation containing construction and demolition waste.

    PubMed

    Leiva, Carlos; Solís-Guzmán, Jaime; Marrero, Madelyn; García Arenas, Celia

    2013-03-01

    The environmental problem posed by construction and demolition waste (C&D waste) is derived not only from the high volume produced, but also from its treatment and disposal. Treatment plants receive C&D waste which is then transformed into a recycled mixed aggregate. The byproduct is mainly used for low-value-added applications such as land escape restoration, despite the high quality of the aggregate. In the present work, the chemical composition properties and grading curve properties of these aggregates are defined. Furthermore, the resulting recycled concrete with a high proportion of recycled composition, from 20% to 100% replacement of fine and coarse aggregate, is characterized physically and mechanically. An environmental study of the new construction material when all aggregates are substituted by C&D waste shows a low toxicity level, similar to that of other construction materials. The new material also has improved properties with respect to standard concrete such as high fire resistance, good heat insulation, and acoustic insulation. PMID:22784475

  20. Recycling of construction and demolition waste materials: a chemical-mineralogical appraisal.

    PubMed

    Bianchini, G; Marrocchino, E; Tassinari, R; Vaccaro, C

    2005-01-01

    Building activity is currently demanding remarkable amounts of inert materials (such as gravel and sand) that are usually provided by alluvial sediments. The EU directives and Italian Legislation are encouraging the re-use of construction and demolition waste provided by continuous urban redevelopment. The re-utilisation of building waste is a relatively new issue for Italy: unfortunately the employment of recycled inert materials is still limited to general bulk and drainage fills, while a more complete re-evaluation is generally hampered by the lack of suitable recycling plants. In this paper, chemical-mineralogical characterization of recycled inert materials was carried out after preliminary crushing and grain-size sorting. XRF and XRD analysis of the different grain-size classes allowed us to recognise particular granulometric classes that can be re-utilised as first-order material in the building activity. Specifically, the presented chemical-mineralogical appraisal indicates that the recycled grain-size fraction 0.6-0.125 mm could be directly re-employed in the preparation of new mortar and concrete, while finer fractions could be considered as components for industrial processing in the preparation of cements and bricks/tiles.

  1. Recycled blocks with improved sound and fire insulation containing construction and demolition waste.

    PubMed

    Leiva, Carlos; Solís-Guzmán, Jaime; Marrero, Madelyn; García Arenas, Celia

    2013-03-01

    The environmental problem posed by construction and demolition waste (C&D waste) is derived not only from the high volume produced, but also from its treatment and disposal. Treatment plants receive C&D waste which is then transformed into a recycled mixed aggregate. The byproduct is mainly used for low-value-added applications such as land escape restoration, despite the high quality of the aggregate. In the present work, the chemical composition properties and grading curve properties of these aggregates are defined. Furthermore, the resulting recycled concrete with a high proportion of recycled composition, from 20% to 100% replacement of fine and coarse aggregate, is characterized physically and mechanically. An environmental study of the new construction material when all aggregates are substituted by C&D waste shows a low toxicity level, similar to that of other construction materials. The new material also has improved properties with respect to standard concrete such as high fire resistance, good heat insulation, and acoustic insulation.

  2. Tri-State Synfuels Project Review: Volume 12. Fluor project status. [Proposed Henderson, Kentucky coal to gasoline plant; engineering

    SciTech Connect

    Not Available

    1982-06-01

    The purpose of this report is to document and summarize activities associated with Fluor's efforts on the Tri-State Synfuels Project. The proposed facility was to be coal-to-transport fuels facility located in Henderson, Kentucky. Tri-State Synfuels Company was participating in the project as a partner of the US Department of Energy per terms of a Cooperative Agreement resulting from DOE's synfuel's program solicitation. Fluor's initial work plan called for preliminary engineering and procurement services to the point of commitment for construction for a Sasol Fischer-Tropsch plant. Work proceeded as planned until October 1981 when results of alternative coal-to-methanol studies revealed the economic disadvantage of the Synthol design for US markets. A number of alternative process studies followed to determine the best process configuration. In January 1982 Tri-State officially announced a change from Synthol to a Methanol to Gasoline (MTG) design basis. Further evaluation and cost estimates for the MTG facility eventually led to the conclusion that, given the depressed economic outlook for alternative fuels development, the project should be terminated. Official announcement of cancellation was made on April 13, 1982. At the time of project cancellation, Fluor had completed significant portions of the preliminary engineering effort. Included in this report are descriptions and summaries of Fluor's work during this project. In addition location of key project data and materials is identified and status reports for each operation are presented.

  3. Checklist Model to Improve Work Practices in Small-Scale Demolition Operations with Silica Dust Exposures

    PubMed Central

    Muianga, Custodio; Rice, Carol; Lentz, Thomas; Lockey, James; Niemeier, Richard; Succop, Paul

    2012-01-01

    A systematic approach was developed to review, revise and adapt existing exposure control guidance used in developed countries for use in developing countries. One-page employee and multiple-page supervisor guidance sheets were adapted from existing documents using a logic framework and workers were trained to use the information to improve work practices. Interactive, hands-on training was delivered to 26 workers at five small-scale demolition projects in Maputo City, Mozambique, and evaluated. A pre-and-post walkthrough survey used by trained observers documented work practice changes. Worker feedback indicated that the training was effective and useful. Workers acquired knowledge (84% increase, p < 0.01) and applied the work practice guidance. The difference of proportions between use of work practice components before and after the intervention was statistically significant (p < 0.05). Changes in work practices following training included preplanning, use of wet methods and natural ventilation and end-of-task review. Respirable dust measurements indicated a reduction in exposure following training. Consistency in observer ratings and observations support the reliability and validity of the instruments. This approach demonstrated the short-term benefit of training in changing work practices; follow-up is required to determine the long-term impact on changes in work practices, and to evaluate the need for refresher training. PMID:22470296

  4. A web-based Decision Support System for the optimal management of construction and demolition waste.

    PubMed

    Banias, G; Achillas, Ch; Vlachokostas, Ch; Moussiopoulos, N; Papaioannou, I

    2011-12-01

    Wastes from construction activities constitute nowadays the largest by quantity fraction of solid wastes in urban areas. In addition, it is widely accepted that the particular waste stream contains hazardous materials, such as insulating materials, plastic frames of doors, windows, etc. Their uncontrolled disposal result to long-term pollution costs, resource overuse and wasted energy. Within the framework of the DEWAM project, a web-based Decision Support System (DSS) application - namely DeconRCM - has been developed, aiming towards the identification of the optimal construction and demolition waste (CDW) management strategy that minimises end-of-life costs and maximises the recovery of salvaged building materials. This paper addresses both technical and functional structure of the developed web-based application. The web-based DSS provides an accurate estimation of the generated CDW quantities of twenty-one different waste streams (e.g. concrete, bricks, glass, etc.) for four different types of buildings (residential, office, commercial and industrial). With the use of mathematical programming, the DeconRCM provides also the user with the optimal end-of-life management alternative, taking into consideration both economic and environmental criteria. The DSS's capabilities are illustrated through a real world case study of a typical five floor apartment building in Thessaloniki, Greece. PMID:21835602

  5. A web-based Decision Support System for the optimal management of construction and demolition waste.

    PubMed

    Banias, G; Achillas, Ch; Vlachokostas, Ch; Moussiopoulos, N; Papaioannou, I

    2011-12-01

    Wastes from construction activities constitute nowadays the largest by quantity fraction of solid wastes in urban areas. In addition, it is widely accepted that the particular waste stream contains hazardous materials, such as insulating materials, plastic frames of doors, windows, etc. Their uncontrolled disposal result to long-term pollution costs, resource overuse and wasted energy. Within the framework of the DEWAM project, a web-based Decision Support System (DSS) application - namely DeconRCM - has been developed, aiming towards the identification of the optimal construction and demolition waste (CDW) management strategy that minimises end-of-life costs and maximises the recovery of salvaged building materials. This paper addresses both technical and functional structure of the developed web-based application. The web-based DSS provides an accurate estimation of the generated CDW quantities of twenty-one different waste streams (e.g. concrete, bricks, glass, etc.) for four different types of buildings (residential, office, commercial and industrial). With the use of mathematical programming, the DeconRCM provides also the user with the optimal end-of-life management alternative, taking into consideration both economic and environmental criteria. The DSS's capabilities are illustrated through a real world case study of a typical five floor apartment building in Thessaloniki, Greece.

  6. An empirical investigation of construction and demolition waste generation rates in Shenzhen city, South China

    SciTech Connect

    Lu Weisheng; Yuan Hongping; Li Jingru; Hao, Jane J.L.; Mi Xuming; Ding Zhikun

    2011-04-15

    The construction and demolition waste generation rates (C and D WGRs) is an important factor in decision-making and management of material waste in any construction site. The present study investigated WGRs by conducting on-site waste sorting and weighing in four ongoing construction projects in Shenzhen city of South China. The results revealed that WGRs ranged from 3.275 to 8.791 kg/m{sup 2} and miscellaneous waste, timber for formwork and falsework, and concrete were the three largest components amongst the generated waste. Based on the WGRs derived from the research, the paper also discussed the main causes of waste in the construction industry and attempted to connect waste generation with specific construction practices. It was recommended that measures mainly including performing waste sorting at source, employing skilful workers, uploading and storing materials properly, promoting waste management capacity, replacing current timber formwork with metal formwork and launching an incentive reward program to encourage waste reduction could be potential solutions to reducing current WGRs in Shenzhen. Although these results were derived from a relatively small sample and so cannot justifiably be generalized, they do however add to the body of knowledge that is currently available for understanding the status of the art of C and D waste management in China.

  7. Demolition of a hospital building by controlled explosion: the impact on filamentous fungal load in internal and external air.

    PubMed

    Bouza, E; Peláez, T; Pérez-Molina, J; Marín, M; Alcalá, L; Padilla, B; Muñoz, P; Adán, P; Bové, B; Bueno, M J; Grande, F; Puente, D; Rodríguez, M P; Rodríguez-Créixems, M; Vigil, D; Cuevas, O

    2002-12-01

    The demolition of a maternity building at our institution provided us with the opportunity to study the load of filamentous fungi in the air. External (nearby streets) and internal (within the hospital buildings) air was sampled with an automatic volumetric machine (MAS-100 Air Samplair) at least daily during the week before the demolition, at 10, 30, 60, 90,120, 180, 240, 420, 540 and 660 min post-demolition, daily during the week after the demolition and weekly during weeks 2, 3 and 4 after demolition. Samples were duplicated to analyse reproducibility. Three hundred and forty samples were obtained: 115 external air, 69 'non-protected' internal air and 156 protected internal air [high efficiency particulate air (HEPA) filtered air under positive pressure]. A significant increase in the colony count of filamentous fungi occurred after the demolition. Median colony counts of external air on demolition day were significantly higher than from internal air (70.2 cfu/m(3) vs 35.8 cfu/m(3)) (P < 0.001). Mechanical demolition on day +4 also produced a significant difference between external and internal air (74.5 cfu/m(3) vs 41.7 cfu/m(3)). The counts returned to baseline levels on day +11. Most areas with a protected air supply yielded no colonies before demolition day and remained negative on demolition day. The reproducibility of the count method was good (intra-assay variance: 2.4 cfu/m(3)). No episodes of invasive filamentous mycosis were detected during the three months following the demolition. Demolition work was associated with a significant increase in the fungal colony counts of hospital external and non-protected internal air. Effective protective measures may be taken to avoid the emergence of clinical infections.

  8. GRIN-Global: An International Project to Develop a Global Plant Genebank Information Management System

    Technology Transfer Automated Retrieval System (TEKTRAN)

    The mission of the GRIN-Global Project is to create a new, scalable version of the Germplasm Resource Information System (GRIN) to provide the world’s crop genebanks with a powerful, flexible, easy-to-use plant genetic resource (PGR) information management system. The system will help safeguard PGR ...

  9. GRIN-Global: An International Project to Develop a Global Plant Genebank and Information Management System

    Technology Transfer Automated Retrieval System (TEKTRAN)

    The mission of the GRIN-Global Project is to create a new, scalable version of the Germplasm Resource Information System (GRIN) to provide the world’s crop genebanks with a powerful, flexible, easy-to-use plant genetic resource (PGR) information management system. The system will help safeguard PGR...

  10. GRIN-Global: An International Project to Develop a Global Plant Genebank and Information Management System

    Technology Transfer Automated Retrieval System (TEKTRAN)

    The mission of the GRIN-Global Project is to create a new, scalable version of the Germplasm Resource Information System (GRIN) to provide the world's crop genebanks with a powerful, flexible, easy-to-use plant genetic resource (PGR) information management system. The system will help safeguard PGR ...

  11. GRIN-Global: An International Project to Develop a Global Plant Genebank and Information Management System

    Technology Transfer Automated Retrieval System (TEKTRAN)

    The mission of the GRIN-Global Project is to create a new, scalable version of the Germplasm Resource Information System (GRIN) to provide the world’s crop genebanks with a powerful, flexible, easy-to-use plant genetic resource (PGR) information management system. The system will help safeguard PGR ...

  12. 75 FR 60405 - Lincoln National Forest, New Mexico, Integrated Non-Native Invasive Plant Project

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-09-30

    ... methods, and adaptive management. Invasive plants designated by the State of New Mexico as noxious weeds are the primary focus of this project. By definition, noxious weeds pose a potential threat to human.... Proposed Action The LNF proposes to implement an integrated weed management (IWM) strategy as defined...

  13. Teaching about Animal, Plant, Living. Part 1. Learning in Science Project. Working Paper No. 31.

    ERIC Educational Resources Information Center

    Bell, Beverley, Ed.

    Presented is a guide for teaching activities produced as a result of a Learning in Science Project investigation which showed that children often have quite different meanings for the words "animal,""plant," and "living" than do scientists. Included are: (1) focus of instruction at different educational levels; (2) a suggested teaching program;…

  14. Acceptance test report for project C-157 ``T-Plant electrical upgrade``

    SciTech Connect

    Jeppson, L.A.

    1997-08-05

    This Acceptance Test Report (ATR) documents for record purposes the field results, acceptance, and approvals of the completed acceptance test per WHC-SD-Cl57-ATP-001, Rev. 0, ``Acceptance Test Proceedure for Project C-157 `T Plant Electrical Upgrade``` The test was completed and approved without any problems or exceptions.

  15. Use of a Modern Polymerization Pilot-Plant for Undergraduate Control Projects.

    ERIC Educational Resources Information Center

    Mendoza-Bustos, S. A.; And Others

    1991-01-01

    Described is a project where students gain experience in handling large volumes of hazardous materials, process start up and shut down, equipment failures, operational variations, scaling up, equipment cleaning, and run-time scheduling while working in a modern pilot plant. Included are the system design, experimental procedures, and results. (KR)

  16. Separability studies of construction and demolition waste recycled sand.

    PubMed

    Ulsen, Carina; Kahn, Henrique; Hawlitschek, Gustav; Masini, Eldon A; Angulo, Sérgio C

    2013-03-01

    The quality of recycled aggregates from construction and demolition waste (CDW) is strictly related to the content of porous and low strength phases, and specifically to the patches of cement that remain attached to the surface of natural aggregates. This phase increases water absorption and compromises the consistency and strength of concrete made from recycled aggregates. Mineral processing has been applied to CDW recycling to remove the patches of adhered cement paste on coarse recycled aggregates. The recycled fine fraction is usually disregarded due to its high content of porous phases despite representing around 50% of the total waste. This paper focus on laboratory mineral separability studies for removing particles with a high content of cement paste from natural fine aggregate particles (quartz/feldspars). The procedure achieved processing of CDW by tertiary impact crushing to produce sand, followed by sieving and density and magnetic separability studies. The attained results confirmed that both methods were effective in reducing cement paste content and producing significant mass recovery (80% for density concentration and 60% for magnetic separation). The production of recycled sand contributes to the sustainability of the construction environment by reducing both the consumption of raw materials and disposal of CDW, particularly in large Brazilian centers with a low quantity of sand and increasing costs of this material due to long transportation distances. PMID:22835506

  17. A valuable product from a construction and demolition facility

    SciTech Connect

    McMahon, S.G.

    1997-12-31

    A Construction and Demolition (C and D) Facility in Northeast Florida produces a manufactured soil that is a by-product of recycling operations. Upon arrival at the facility, the incoming material is separated into concrete and non-concrete materials. The non-concrete material passes through several screen and conveyor line stations to remove deleterious and unsuitable materials. The remaining material becomes the final product known as recycled soil product. The consistency of the material is similar to soil mixed with some mulch. Present uses of the material include daily landfill cover and fill material (exclusive of top cover) at construction sites, road base preparation and landscaping material. In order to determine if the material was safe to be used in places where it may come in contact with the public or sensitive environments, several analytical tests for metals and volatile organic compounds were performed. The material was determined to be within applicable standards for all parameters sampled and the product is expected to be approved for unrestricted use. This former waste material has been proven to be a valuable commodity again.

  18. Study of the durability of demolition aggregates on pavements

    NASA Astrophysics Data System (ADS)

    Bachir, Melbouci; Fazia, Boudjemia

    2009-06-01

    This work is an experimental contribution to the study of durability of various materials coming from the demolition of buildings for their use in the flexible infrastructures of pavements. However, these pavements undergo traffic loading which causes, in the long time permanent deformations and settlements thus generating significant degradations of materials. Various recent works aim at characterizing these materials. This work falls under this scope and gives an approach of the mechanical behavior and the response of these last to repetitive loadings. After identification of materials and the determination of the characteristics of hardness and durability, we studied their mechanical behavior with cyclic shearing on these three materials (aggregates of concrete, brick and concrete block). These tests enabled us to analyze the mechanisms which occur through the various parameters related to loading (the amplitude and the repetition of loading, the parameters related to materials (the water content, the density and the grain size distribution). The study of the durability of these materials consists on quantifying the degradation rate of the grains after the various tests and the grain size distribution which governs the amplitude of crushing.

  19. Separability studies of construction and demolition waste recycled sand.

    PubMed

    Ulsen, Carina; Kahn, Henrique; Hawlitschek, Gustav; Masini, Eldon A; Angulo, Sérgio C

    2013-03-01

    The quality of recycled aggregates from construction and demolition waste (CDW) is strictly related to the content of porous and low strength phases, and specifically to the patches of cement that remain attached to the surface of natural aggregates. This phase increases water absorption and compromises the consistency and strength of concrete made from recycled aggregates. Mineral processing has been applied to CDW recycling to remove the patches of adhered cement paste on coarse recycled aggregates. The recycled fine fraction is usually disregarded due to its high content of porous phases despite representing around 50% of the total waste. This paper focus on laboratory mineral separability studies for removing particles with a high content of cement paste from natural fine aggregate particles (quartz/feldspars). The procedure achieved processing of CDW by tertiary impact crushing to produce sand, followed by sieving and density and magnetic separability studies. The attained results confirmed that both methods were effective in reducing cement paste content and producing significant mass recovery (80% for density concentration and 60% for magnetic separation). The production of recycled sand contributes to the sustainability of the construction environment by reducing both the consumption of raw materials and disposal of CDW, particularly in large Brazilian centers with a low quantity of sand and increasing costs of this material due to long transportation distances.

  20. Characterization of wastes from construction and demolition sector.

    PubMed

    Somasundaram, Swarnalatha; Jeon, Tae-Wan; Kang, Young-Yeul; Kim, Woo-Il; Jeong, Seong-Kyeong; Kim, Yong-Jun; Yeon, Jin-Mo; Shin, Sun Kyoung

    2015-01-01

    In Republic of Korea, construction and demolition (C&D) waste accounts for 49.9% of the total waste. In the present work, the mineralogical composition, the concentrations of 11 heavy metals, 19 PAH, and 7 polychlorinated biphenyl (PCB) congeners present in the 6 broad category (9 subcategories) of C&D hazardous waste were discussed along with their leaching characteristics. In concrete/mixed cement waste, the concentrations of As, Cr(6+), Hg, and Zn were in the range of 1.76-7.86, ND-1.63, 0.026-0.047, and 110.90-280.17 mg/kg, respectively. The asphalt waste sample A1 possessed relatively high concentrations of phenanthrene, fluoranthene, pyrene, benz(a)anthracene, benzo(a)pyrene, and indeno(1,2,3-cd)pyrene comparing to the other samples and it contains 0.08-0.1% of coal tar. Hazardous nature of the C&D wastes greatly depends on the source of the collection. Zn concentration was above 1000 mg/kg for road asphalt waste samples A4 and A5. Total PCB concentration were high in the soil waste sample S1 (130 μg/kg) as it was the excavated soil obtained from the premises of an oil station. Leaching of As, Ba, CN(-), and F(-) were observed in most of the C&D waste samples.

  1. The SNO+ Scintillator Purification Plant and Projected Sensitivity to Solar Neutrinos in the Pure Scintillator Phase

    NASA Astrophysics Data System (ADS)

    Pershing, Teal; SNO+ Collaboration

    2016-03-01

    The SNO+ detector is a neutrino and neutrinoless double-beta decay experiment utilizing the renovated SNO detector. In the second phase of operation, the SNO+ detector will contain 780 tons of organic liquid scintillator composed of 2 g/L 2,5-diphenyloxazole (PPO) in linear alkylbenzene (LAB). In this phase, SNO+ will strive to detect solar neutrinos in the sub-MeV range, including CNO production neutrinos and pp production neutrinos. To achieve the necessary detector sensitivity, a four-part scintillator purification plant has been constructed in SNOLAB for the removal of ionic and radioactive impurities. We present an overview of the SNO+ scintillator purification plant stages, including distillation, water extraction, gas stripping, and metal scavenger columns. We also give the projected SNO+ sensitivities to various solar-produced neutrinos based on the scintillator plant's projected purification efficiency.

  2. SLIGHTLY IRRADIATED FUEL (SIF) INTERIM DISPOSITION PROJECT

    SciTech Connect

    NORTON SH

    2010-02-23

    nuclear reservation. Workers had to pass through metal detectors when they arrived at the plant and materials leaving the plant had to be scanned for security reasons. Whereas other high-security nuclear materials were shipped from the PFP to Savannah River, S.C. as part ofa Department of Energy (DOE) program to consolidate weapons-grade plutonium, it was determined that the SIF should remain onsite pending disposition to a national repository. Nevertheless, the SIF still requires a high level of security that the PFP complex has always provided. With the 60-year PFP mission of producing and storing plutonium concluded, the environmental cleanup plans for Hanford call for the demolition of the 63-building PFP complex. Consequently, if the SIF remained at PFP it not only would have interfered with the environmental cleanup plans, but would have required $100 million in facility upgrades to meet increased national security requirements imposed after the 9/11 terrorist attacks. A new smaller and more cost-effective area was needed to store this material, which led to the SIF Project. Once the SIF project was successfully completed and the SIF was safely removed from PFP, the existing Protected Area at PFP could be removed, and demolition could proceed more quickly without being encumbered by restrictive security requirements that an active Protected Area requires. The lightened PFP security level brought by safely removing and storing the SIF would also yield lowered costs for deactivation and demolition, as well as reduce overall life-cycle costs.

  3. Suitable Days for Plant Growth Disappear under Projected Climate Change: Potential Human and Biotic Vulnerability.

    PubMed

    Mora, Camilo; Caldwell, Iain R; Caldwell, Jamie M; Fisher, Micah R; Genco, Brandon M; Running, Steven W

    2015-06-01

    Ongoing climate change can alter conditions for plant growth, in turn affecting ecological and social systems. While there have been considerable advances in understanding the physical aspects of climate change, comprehensive analyses integrating climate, biological, and social sciences are less common. Here we use climate projections under alternative mitigation scenarios to show how changes in environmental variables that limit plant growth could impact ecosystems and people. We show that although the global mean number of days above freezing will increase by up to 7% by 2100 under "business as usual" (representative concentration pathway [RCP] 8.5), suitable growing days will actually decrease globally by up to 11% when other climatic variables that limit plant growth are considered (i.e., temperature, water availability, and solar radiation). Areas in Russia, China, and Canada are projected to gain suitable plant growing days, but the rest of the world will experience losses. Notably, tropical areas could lose up to 200 suitable plant growing days per year. These changes will impact most of the world's terrestrial ecosystems, potentially triggering climate feedbacks. Human populations will also be affected, with up to ~2,100 million of the poorest people in the world (~30% of the world's population) highly vulnerable to changes in the supply of plant-related goods and services. These impacts will be spatially variable, indicating regions where adaptations will be necessary. Changes in suitable plant growing days are projected to be less severe under strong and moderate mitigation scenarios (i.e., RCP 2.6 and RCP 4.5), underscoring the importance of reducing emissions to avoid such disproportionate impacts on ecosystems and people.

  4. Suitable Days for Plant Growth Disappear under Projected Climate Change: Potential Human and Biotic Vulnerability

    PubMed Central

    Mora, Camilo; Caldwell, Iain R.; Caldwell, Jamie M.; Fisher, Micah R.; Genco, Brandon M.; Running, Steven W.

    2015-01-01

    Ongoing climate change can alter conditions for plant growth, in turn affecting ecological and social systems. While there have been considerable advances in understanding the physical aspects of climate change, comprehensive analyses integrating climate, biological, and social sciences are less common. Here we use climate projections under alternative mitigation scenarios to show how changes in environmental variables that limit plant growth could impact ecosystems and people. We show that although the global mean number of days above freezing will increase by up to 7% by 2100 under “business as usual” (representative concentration pathway [RCP] 8.5), suitable growing days will actually decrease globally by up to 11% when other climatic variables that limit plant growth are considered (i.e., temperature, water availability, and solar radiation). Areas in Russia, China, and Canada are projected to gain suitable plant growing days, but the rest of the world will experience losses. Notably, tropical areas could lose up to 200 suitable plant growing days per year. These changes will impact most of the world’s terrestrial ecosystems, potentially triggering climate feedbacks. Human populations will also be affected, with up to ~2,100 million of the poorest people in the world (~30% of the world’s population) highly vulnerable to changes in the supply of plant-related goods and services. These impacts will be spatially variable, indicating regions where adaptations will be necessary. Changes in suitable plant growing days are projected to be less severe under strong and moderate mitigation scenarios (i.e., RCP 2.6 and RCP 4.5), underscoring the importance of reducing emissions to avoid such disproportionate impacts on ecosystems and people. PMID:26061091

  5. Notification of Concurrence - K-25/K-27 D&D Project, ETTP - Change Number of EMWMF Waste Lots in the Waste Handling Plan for Demolition of the K-25 and K-27 Building Structures and Remaining Components Located at the ETTP, Oak Ridge, TN From Two to Three

    SciTech Connect

    Trice K.D.

    2009-02-11

    Section 5.1 of the approved Waste Handling Plan for Demolition ofthe K-25 and K-2 7 Building Structures and Remaining Components Located at the East Tennessee Technology Park, Oak Ridge, Tennessee (WHP) includes two Environmental Management Waste Management (EMWMF) waste lots: (1) Asbestos-contaminated roofing/transite; and (2) Construction debris, such as nonasbestos roofing, structural steel/miscellaneous metal/equipment, nonradiological piping, wood, and miscellaneous small quantities of concrete. This concurrence form adds an additional EMWMF waste lot 6.47 for lavatory sink drains. Based on an analysis of the building structure characterization data, the only individual building structure with either an analytic carcinogenic or Hazard Index (HI) sum-of-fractions (SOF) greater than 1 is the lavatory sink drains (Table 1). The HI SOF for the lavatory sink drains is 1.34 (Table 2). When all media are combined with the material of construction calculations, the HI SOF is 1.22 (Table 3). However, when the lavatory sink drains are segregated from all other media, the HI SOF is only 0.256, which is well below the EMWMF waste acceptance criteria SOF limit of 1 (Table 4). Given the large volume (124, 625 cubic yards) of other building structure media with a small HI SOF of 0.256 and the small volume (one cubic yard) of lavatory sink drains with a large HI SOF of 1.34, a separate waste lot for lavatory sink drains is recommended. Lead is the primary contributor to the large HI SOF in the lavatory sink drains. Lead in the lavatory sink drains was shown using the Wilcoxon rank-sum test statistically to have higher concentrations than all other building structure media combined. Other analytes having statistically different median concentrations in the lavatory sink drains compared to all other media are antimony, arsenic, boron, cadmium, selenium, solver, vanadium, zinc, mercury, strontium, and Uranium-233/234 (Table 5). A separate waste lot for the lavatory sink drains

  6. Demolition waste generation for development of a regional management chain model.

    PubMed

    Bernardo, Miguel; Gomes, Marta Castilho; de Brito, Jorge

    2016-03-01

    Even though construction and demolition waste (CDW) is the bulkiest waste stream, its estimation and composition in specific regions still faces major difficulties. Therefore new methods are required especially when it comes to make predictions limited to small areas, such as counties. This paper proposes one such method, which makes use of data collected from real demolition works and statistical information on the geographical area under study. Based on a correlation analysis between the demolition waste estimates and indicators such as population density, buildings ageing index, buildings density and land occupation type, relationships are established that can be used to determine demolition waste outputs in a given area. The derived models are presented and explained. This methodology is independent from the specific region with which it is exemplified (the Lisbon Metropolitan Area) and can therefore be applied to any region of the world, from the country to the county level. Generation of demolition waste data at the county level is the basis of the design of a systemic model for CDW management in a region. Future developments proposed include a mixed-integer linear programming formulation of such recycling network. PMID:26838607

  7. The Power Plant Mapping Student Project: Bringing Citizen Science to Schools

    NASA Astrophysics Data System (ADS)

    Tayne, K.; Oda, T.; Gurney, K. R.; O'Keeffe, D.; Petron, G.; Tans, P. P.; Frost, G. J.

    2014-12-01

    An emission inventory (EI) is a conventional tool to quantify and monitor anthropogenic emissions of greenhouse gases and air pollutants into the atmosphere. Gridded EI can visually show geographical patterns of emissions and their changes over time. These patterns, when available, are often determined using location data collected by regional governments, industries, and researchers. Datasets such as Carbon Monitoring and Action (CARMA, www.carma.org) are particularly useful for mapping emissions from large point sources and have been widely used in the EI community. The EI community is aware of potentially significant errors in the geographical locations of point sources, including power plants. The big challenge, however, is to review tens of thousands of power plant locations around the world and correct them where needed. The Power Plant Mapping Student Project (PPMSP) is a platform designed for students in 4th through 12th grade to improve the geographical location of power plants indicated in existing datasets to benefit international EI research. In PPMSP, we use VENTUS, a web-based platform (http://ventus.project.asu.edu/) that invites citizens to contribute power plant location data. Using VENTUS, students view scenes in the vicinity of reported power plant coordinates on Google Maps. Students either verify the location of a power plant or search for it within a designated radius using various indicators, an e-guide, and a power plant photo gallery for assistance. If the power plant cannot be found, students mark the plant as unverified. To assure quality for research use, the project contains multiple checkpoints and levels of review. While participating in meaningful research that directly benefits the EI research community, students are engaged in relevant science curricula designed to meet each grade level's Next Generation Science Standards. Students study energy, climate change, the atmosphere, and geographical information systems. The curricula is

  8. Project C-018H, 242-A Evaporator/PUREX Plant Process Condensate Treatment Facility, functional design criteria. Revision 3

    SciTech Connect

    Sullivan, N.

    1995-05-02

    This document provides the Functional Design Criteria (FDC) for Project C-018H, the 242-A Evaporator and Plutonium-Uranium Extraction (PUREX) Plant Condensate Treatment Facility (Also referred to as the 200 Area Effluent Treatment Facility [ETF]). The project will provide the facilities to treat and dispose of the 242-A Evaporator process condensate (PC), the Plutonium-Uranium Extraction (PUREX) Plant process condensate (PDD), and the PUREX Plant ammonia scrubber distillate (ASD).

  9. Biological sulfate removal from gypsum contaminated construction and demolition debris.

    PubMed

    Kijjanapanich, Pimluck; Annachhatre, Ajit P; Esposito, Giovanni; van Hullebusch, Eric D; Lens, Piet N L

    2013-12-15

    Construction and demolition debris (CDD) contains high levels of sulfate that can cause detrimental environmental impacts when disposed without adequate treatment. In landfills, sulfate can be converted to hydrogen sulfide under anaerobic conditions. CDD can thus cause health impacts or odor problems to landfill employees and surrounding residents. Reduction of the sulfate content of CDD is an option to overcome these problems. This study aimed at developing a biological sulfate removal system to reduce the sulfate content of gypsum contaminated CDD in order to decrease the amount of solid waste, to improve the quality of CDD waste for recycling purposes and to recover sulfur from CDD. The treatment leached out the gypsum contained in CDD by water in a leaching column. The sulfate loaded leachate was then treated in a biological sulfate reducing Upflow Anaerobic Sludge Blanket (UASB) reactor to convert the sulfate to sulfide. The UASB reactor was operated at 23 ± 3 °C with a hydraulic retention time and upflow velocity of 15.5 h and 0.1 m h(-1), respectively while ethanol was added as electron donor at a final organic loading rate of 3.46 g COD L(-1) reactor d(-1). The CDD leachate had a pH of 8-9 and sulfate dissolution rates of 526.4 and 609.8 mg L(-1) d(-1) were achieved in CDD gypsum and CDD sand, respectively. Besides, it was observed that the gypsum dissolution was the rate limiting step for the biological treatment of CDD. The sulfate removal efficiency of the system stabilized at around 85%, enabling the reuse of the UASB effluent for the leaching step, proving the versatility of the bioreactor for practical applications.

  10. Sulphate release from construction and demolition material in soils

    NASA Astrophysics Data System (ADS)

    Abel, Stefan; Wessolek, Gerd

    2013-04-01

    In Berlin and many other cities soils are heavily influenced by anthropogenic activities and deposited substrates. A widespread technical substrate in technosols is construction and demolition material from residential and industrial buildings. Existing rubble landfills without sealing facilities pose threats to ground water quality. In the central city of Berlin rising sulphate concentrations of groundwaters (up to 1200 mg/L) are measured since more than two decades. Previous studies point out that the high sulphate concentrations are mainly attributed to World War II rubble. The major part of debris was deposited in form of landfills and contains approximately 0.3 wt% gypsum. The scope of our research is to determine mechanisms of sulphate release from debris material, interactions between sulphate release, soil hydraulic properties and potential sinks of sulphur. To estimate equilibrium concentration and kinetics of sulphate release of various debris components batch and column experiments are conducted. The same method is applied to determine potential adsorptive character of common debris components. To analyse the impacts of soil hydraulic properties on sulphate leaching we carry out soil column experiments with defined upper and lower boundary conditions, varying water flow velocity and induced preferential flow. Simultaneously we monitor sulphate concentration of soil leachate in a 2 m³ lysimeter. First results of the batch experiments show that gypsum from broken stucco is the main source of sulphate in the observed technosols. Other components as mortar and slag show a quite low sulphate release. Similar results are found within the column experiments. For brigs medium and strongly time dependent sulphate release is determined. Concentrations up to 1500 mg/L are measured in the soil leachate from the lysimeter.

  11. Trend of the research on construction and demolition waste management

    SciTech Connect

    Yuan Hongping; Shen Liyin

    2011-04-15

    Research interests in addressing construction and demolition (C and D) waste management issues have resulted in a large amount of publications during the last decade. This study demonstrates that there is no systematic examination on the research development in literature in the discipline of C and D waste management. This study presents the latest research trend in the discipline through analyzing the publications from 2000 to 2009 in eight major international journals. The analysis is conducted on the number of papers published annually, main authors' contributions, research methods and data analysis methods adopted, and research topics covered. The results exhibit an increasing research interest in C and D waste management in recent years. Researchers from developed economies have contributed significantly to the development of the research in the discipline. Some developing countries such as Malaysia and China have also been making good efforts in promoting C and D waste management research. The findings from this study also indicate that survey and case study are major methods for data collection, and the data are mostly processed through descriptive analysis. It is anticipated that more future studies on C and D waste management will be led by researchers from developing economies, where construction works will remain their major economic activities. On the other hand, more sophisticated modeling and simulating techniques have been used effectively in a number of studies on C and D waste management research, and this is considered a major methodology for future research in the discipline. C and D waste management will continue to be a hot research topic in the future, in particularly, the importance of human factors in C and D waste management has emerged as a new challenging topic.

  12. SLUDGE TREATMENT PROJECT PHASE 1 SLUDGE STORAGE OPTIONS ASSESSMENT OF T PLANT VERSUS ALTERNATE STORAGE FACILITY

    SciTech Connect

    RUTHERFORD WW; GEUTHER WJ; STRANKMAN MR; CONRAD EA; RHOADARMER DD; BLACK DM; POTTMEYER JA

    2009-04-29

    The CH2M HILL Plateau Remediation Company (CHPRC) has recommended to the U.S. Department of Energy (DOE) a two phase approach for removal and storage (Phase 1) and treatment and packaging for offsite shipment (Phase 2) of the sludge currently stored within the 105-K West Basin. This two phased strategy enables early removal of sludge from the 105-K West Basin by 2015, allowing remediation of historical unplanned releases of waste and closure of the 100-K Area. In Phase 1, the sludge currently stored in the Engineered Containers and Settler Tanks within the 105-K West Basin will be transferred into sludge transport and storage containers (STSCs). The STSCs will be transported to an interim storage facility. In Phase 2, sludge will be processed (treated) to meet shipping and disposal requirements and the sludge will be packaged for final disposal at a geologic repository. The purpose of this study is to evaluate two alternatives for interim Phase 1 storage of K Basin sludge. The cost, schedule, and risks for sludge storage at a newly-constructed Alternate Storage Facility (ASF) are compared to those at T Plant, which has been used previously for sludge storage. Based on the results of the assessment, T Plant is recommended for Phase 1 interim storage of sludge. Key elements that support this recommendation are the following: (1) T Plant has a proven process for storing sludge; (2) T Plant storage can be implemented at a lower incremental cost than the ASF; and (3) T Plant storage has a more favorable schedule profile, which provides more float, than the ASF. Underpinning the recommendation of T Plant for sludge storage is the assumption that T Plant has a durable, extended mission independent of the K Basin sludge interim storage mission. If this assumption cannot be validated and the operating costs of T Plant are borne by the Sludge Treatment Project, the conclusions and recommendations of this study would change. The following decision-making strategy, which is

  13. Projected impacts of climate change on regional capacities for global plant species richness.

    PubMed

    Sommer, Jan Henning; Kreft, Holger; Kier, Gerold; Jetz, Walter; Mutke, Jens; Barthlott, Wilhelm

    2010-08-01

    Climate change represents a major challenge to the maintenance of global biodiversity. To date, the direction and magnitude of net changes in the global distribution of plant diversity remain elusive. We use the empirical multi-variate relationships between contemporary water-energy dynamics and other non-climatic predictor variables to model the regional capacity for plant species richness (CSR) and its projected future changes. We find that across all analysed Intergovernmental Panel on Climate Change emission scenarios, relative changes in CSR increase with increased projected temperature rise. Between now and 2100, global average CSR is projected to remain similar to today (+0.3%) under the optimistic B1/+1.8 degrees C scenario, but to decrease significantly (-9.4%) under the 'business as usual' A1FI/+4.0 degrees C scenario. Across all modelled scenarios, the magnitude and direction of CSR change are geographically highly non-uniform. While in most temperate and arctic regions, a CSR increase is expected, the projections indicate a strong decline in most tropical and subtropical regions. Countries least responsible for past and present greenhouse gas emissions are likely to incur disproportionately large future losses in CSR, whereas industrialized countries have projected moderate increases. Independent of direction, we infer that all changes in regional CSR will probably induce on-site species turnover and thereby be a threat to native floras.

  14. Projected impacts of climate change on regional capacities for global plant species richness.

    PubMed

    Sommer, Jan Henning; Kreft, Holger; Kier, Gerold; Jetz, Walter; Mutke, Jens; Barthlott, Wilhelm

    2010-08-01

    Climate change represents a major challenge to the maintenance of global biodiversity. To date, the direction and magnitude of net changes in the global distribution of plant diversity remain elusive. We use the empirical multi-variate relationships between contemporary water-energy dynamics and other non-climatic predictor variables to model the regional capacity for plant species richness (CSR) and its projected future changes. We find that across all analysed Intergovernmental Panel on Climate Change emission scenarios, relative changes in CSR increase with increased projected temperature rise. Between now and 2100, global average CSR is projected to remain similar to today (+0.3%) under the optimistic B1/+1.8 degrees C scenario, but to decrease significantly (-9.4%) under the 'business as usual' A1FI/+4.0 degrees C scenario. Across all modelled scenarios, the magnitude and direction of CSR change are geographically highly non-uniform. While in most temperate and arctic regions, a CSR increase is expected, the projections indicate a strong decline in most tropical and subtropical regions. Countries least responsible for past and present greenhouse gas emissions are likely to incur disproportionately large future losses in CSR, whereas industrialized countries have projected moderate increases. Independent of direction, we infer that all changes in regional CSR will probably induce on-site species turnover and thereby be a threat to native floras. PMID:20335215

  15. Projected impacts of climate change on regional capacities for global plant species richness

    PubMed Central

    Sommer, Jan Henning; Kreft, Holger; Kier, Gerold; Jetz, Walter; Mutke, Jens; Barthlott, Wilhelm

    2010-01-01

    Climate change represents a major challenge to the maintenance of global biodiversity. To date, the direction and magnitude of net changes in the global distribution of plant diversity remain elusive. We use the empirical multi-variate relationships between contemporary water-energy dynamics and other non-climatic predictor variables to model the regional capacity for plant species richness (CSR) and its projected future changes. We find that across all analysed Intergovernmental Panel on Climate Change emission scenarios, relative changes in CSR increase with increased projected temperature rise. Between now and 2100, global average CSR is projected to remain similar to today (+0.3%) under the optimistic B1/+1.8°C scenario, but to decrease significantly (−9.4%) under the ‘business as usual’ A1FI/+4.0°C scenario. Across all modelled scenarios, the magnitude and direction of CSR change are geographically highly non-uniform. While in most temperate and arctic regions, a CSR increase is expected, the projections indicate a strong decline in most tropical and subtropical regions. Countries least responsible for past and present greenhouse gas emissions are likely to incur disproportionately large future losses in CSR, whereas industrialized countries have projected moderate increases. Independent of direction, we infer that all changes in regional CSR will probably induce on-site species turnover and thereby be a threat to native floras. PMID:20335215

  16. Pilot-based assessment of the economics of recycling construction demolition waste.

    PubMed

    Srour, Issam M; Chehab, Ghassan R; El-Fadel, Mutasem; Tamraz, Sandy

    2013-11-01

    The significant amount of waste generated from construction demolition has become a chronic problem in many developing countries. Using data obtained from demolition contractors and various other sources, this paper proposes a framework for proper handling of construction demolition waste (CDW) to serve as a decision support tool in countries suffering from the lack of national CDW management guidelines. The framework is then demonstrated through a case study in the city of Beirut, Lebanon, and a sensitivity analysis is carried out to examine the economic feasibility of developing a recycling facility. The analysis showed that in order for a facility to be feasible, a gate fee should be charged in the presence of a market for recycled aggregates. The results confirm the significance of instigating and implementing legislation to control illegal dumping, constructing, and managing engineered landfills, and establishing markets for recycled CDW.

  17. WSSRAP chemical plant geotechnical investigations for the Weldon Spring Site Remedial Action Project, Weldon Spring, Missouri

    SciTech Connect

    Not Available

    1990-12-01

    This document has been prepared for the United states Department of Energy (DOE) Weldon Spring Site Remedial Action Project (WSSRAP) by the Project Management Contractor (PMC), which consists of MK-Ferguson Company (MKF) and Morrison Knudsen Corporation Environmental Services Group (MKES) with Jacobs Engineering Group (JEG) as MKF's predesignated subcontractor. This report presents the results of site geotechnical investigations conducted by the PMC in the vicinity of the Weldon Spring chemical plant and raffinate pits (WSCP/RP) and in potential on-site and off-site clayey material borrow sources. The WSCP/RP is the proposed disposal cell (DC) site. 39 refs., 24 figs., 12 tabs.

  18. Decontamination and Decommissioning Experience at a Sellafield Uranium Purification Plant

    SciTech Connect

    Prosser, J.L.

    2006-07-01

    Built in the 1950's, this plant was originally designed to purify depleted uranyl nitrate solution arising from reprocessing operations at the Primary Separation and Head End Plant (Fig. 1). The facility was used for various purposes throughout its life cycle such as research, development and trial based processes. Test rigs were operated in the building from the 1970's until 1984 to support development of the process and equipment now used at Sellafield's Thermal Oxide Reprocessing Plant (THORP). The extensive decommissioning program for this facility began over 15 years ago. Many challenges have been overcome throughout this program such as decommissioning the four main process cells, which were very highly alpha contaminated. The cells contained vessels and pipeline systems that were contaminated to such levels that workers had to use pressurized suits to enter the cells. Since decommissioning at Sellafield was in its infancy, this project has trialed various decontamination/decommissioning methods and techniques in order to progress the project, and this has provided valuable learning for other decommissioning projects. The project has included characterization, decontamination, dismantling, waste handling, and is now ready for demolition during late 2005, early 2006. This will be the first major facility within the historic Separation Area at Sellafield to be demolished down to base slab level. The lessons learnt from this project will directly benefit numerous decommissioning projects as the cleanup at Sellafield continues. (authors)

  19. Dose-projection considerations for emergency conditions at nuclear power plants

    SciTech Connect

    Stoetzel, G.A.; Ramsdell, J.V.; Poeton, R.W.; Powell, D.C.; Desrosiers, A.E.

    1983-05-01

    The purpose of this report is to review the problems and issues associated with making environmental radiation-dose projections during emergencies at nuclear power plants. The review is divided into three areas: source-term development, characterization of atmospheric dispersion and selection of appropriate dispersion models, and development of dosimetry calculations for determining thyroid dose and whole-body dose for ground-level and elevated releases. A discussion of uncertainties associated with these areas is also provided.

  20. Providing more informative projections of climate change impact on plant distribution in a mountain environment

    NASA Astrophysics Data System (ADS)

    Randin, C.; Engler, R.; Pearman, P.; Vittoz, P.; Guisan, A.

    2007-12-01

    Due to their conic shape and the reduction of area with increasing elevation, mountain ecosystems were early identified as potentially very sensitive to global warming. Moreover, mountain systems may experience unprecedented rates of warming during the next century, two or three times higher than that records of the 20th century. In this context, species distribution models (SDM) have become important tools for rapid assessment of the impact of accelerated land use and climate change on the distribution plant species. In this study, we developed and tested new predictor variables for species distribution models (SDM), specific to current and future geographic projections of plant species in a mountain system, using the Western Swiss Alps as model region. Since meso- and micro-topography are relevant to explain geographic patterns of plant species in mountain environments, we assessed the effect of scale on predictor variables and geographic projections of SDM. We also developed a methodological framework of space-for-time evaluation to test the robustness of SDM when projected in a future changing climate. Finally, we used a cellular automaton to run dynamic simulations of plant migration under climate change in a mountain landscape, including realistic distance of seed dispersal. Results of future projections for the 21st century were also discussed in perspective of vegetation changes monitored during the 20th century. Overall, we showed in this study that, based on the most severe A1 climate change scenario and realistic dispersal simulations of plant dispersal, species extinctions in the Western Swiss Alps could affect nearly one third (28.5%) of the 284 species modeled by 2100. With the less severe B1 scenario, only 4.6% of species are predicted to become extinct. However, even with B1, 54% (153 species) may still loose more than 80% of their initial surface. Results of monitoring of past vegetation changes suggested that plant species can react quickly to the

  1. Ambient exposure to coarse and fine particle emissions from building demolition

    NASA Astrophysics Data System (ADS)

    Azarmi, Farhad; Kumar, Prashant

    2016-07-01

    Demolition of buildings produce large quantities of particulate matter (PM) that could be inhaled by on-site workers and people living in the neighbourhood, but studies assessing ambient exposure at the real-world demolition sites are limited. We measured concentrations of PM10 (≤10 μm), PM2.5 (≤2.5 μm) and PM1 (≤1 μm) along with local meteorology for 54 working hours over the demolition period. The measurements were carried out at (i) a fixed-site in the downwind of demolished building, (ii) around the site during demolition operation through mobile monitoring, (iii) different distances away from the demolition site through sequential monitoring, and (iv) inside an excavator vehicle cabin and on-site temporary office for engineers. Position of the PM instrument was continuously recorded using a Global Positioning System on a second basis during mobile measurements. Fraction of coarse particles (PM2.5-10) contributed 89 (with mean particle mass concentration, PMC ≈ 133 ± 17 μg m-3), 83 (100 ± 29 μg m-3), and 70% (59 ± 12 μg m-3) of total PMC during the fixed-site, mobile monitoring and sequential measurements, respectively, compared with only 50% (mean 12 ± 6 μg m-3) during the background measurements. The corresponding values for fine particles (PM2.5) were 11, 17 and 30% compared with 50% during background, showing a much greater release of coarse particles during demolition. The openair package in R and map source software (ArcGIS) were used to assess spatial variation of PMCs in downwind and upwind of the demolition site. A modified box model was developed to determine the emission factors, which were 210, 73 and 24 μg m-2 s-1 for PM10, PM2.5 and PM1, respectively. The average respiratory deposited doses to coarse (and fine) particles inside the excavator cabin and on-site temporary office increased by 57- (and 5-) and 13- (and 2-) times compared with the local background level, respectively. The monitoring stations in downwind direction

  2. Comparative risk analysis for the Rocky Flats Plant Integrated Project Planning

    SciTech Connect

    Jones, M.E.; Shain, D.I.

    1994-12-31

    The Rocky Flats Plant is developing a comprehensive planning strategy that will support transition of the Rocky Flats Plant from a nuclear weapons production facility to site cleanup and final disposition. Final disposition of the Rocky Flats Plant materials and contaminants requires consideration of the interrelated nature of sitewide problems, such as material movement and disposition, facility and land use endstates, costs, relative risks to workers and the public, and waste disposition. Comparative Risk Analysis employs both incremental risk and cumulative risk evaluations to compare risk from postulated options or endstates. Comparative Risk Analysis is an analytical tool for the Rocky Flats Plant Integrated Project Planning which can assist a decision-maker in evaluating relative risks among proposed remedial options or future endstates. It addresses the cumulative risks imposed by the Rocky Flats Plant and provides risk information, both human health and ecological, to aid in reducing unnecessary resource and monetary expenditures. Currently, there is no approved methodology that aggregates various risk estimates. Along with academic and field expert review, the Comparative Risk Analysis methodology is being reviewed and refined. A Rocky Flats Plant Risk Assessment Focus Group was established. Stakeholder involvement in the development provides an opportunity to influence the information delivered to a decision-maker. This paper discusses development of the methodology.

  3. Large-scale biomass plantings in Minnesota: Scale-up and demonstration projects in perspective

    SciTech Connect

    Kroll, T.; Downing, M.

    1995-09-01

    Scale-up projects are an important step toward demonstration and commercialization of woody biomass because simply planting extensive acreage of hybrid poplar will not develop markets. Project objectives are to document the cost to plant and establish, and effort needed to monitor and maintain woody biomass on agricultural land. Conversion technologies and alternative end-uses are examined in a larger framework in order to afford researchers and industrial partners information necessary to develop supply and demand on a local or regional scale. Likely to be determined are risk factors of crop failure and differences between establishment of research plots and agricultural scale field work. Production economics are only one consideration in understanding demonstration and scale-up. Others are environmental, marketing, industrial, and agricultural in nature. Markets for energy crops are only beginning to develop. Although information collected as a result of planting up to 5000 acres of hybrid poplar in central Minnesota will not necessarily be transferable to other areas of the country, a national perspective will come from development of regional markets for woody and herbaceous crops. Several feedstocks, with alternative markets in different regions will eventually comprise the entire picture of biofuels feedstock market development. Current projects offer opportunities to learn about the complexity and requirements that will move biomass from research and development to actual market development. These markets may include energy and other end-uses such as fiber.

  4. Data access for the 1,000 Plants (1KP) project

    PubMed Central

    2014-01-01

    The 1,000 plants (1KP) project is an international multi-disciplinary consortium that has generated transcriptome data from over 1,000 plant species, with exemplars for all of the major lineages across the Viridiplantae (green plants) clade. Here, we describe how to access the data used in a phylogenomics analysis of the first 85 species, and how to visualize our gene and species trees. Users can develop computational pipelines to analyse these data, in conjunction with data of their own that they can upload. Computationally estimated protein-protein interactions and biochemical pathways can be visualized at another site. Finally, we comment on our future plans and how they fit within this scalable system for the dissemination, visualization, and analysis of large multi-species data sets. PMID:25625010

  5. Data access for the 1,000 Plants (1KP) project.

    PubMed

    Matasci, Naim; Hung, Ling-Hong; Yan, Zhixiang; Carpenter, Eric J; Wickett, Norman J; Mirarab, Siavash; Nguyen, Nam; Warnow, Tandy; Ayyampalayam, Saravanaraj; Barker, Michael; Burleigh, J Gordon; Gitzendanner, Matthew A; Wafula, Eric; Der, Joshua P; dePamphilis, Claude W; Roure, Béatrice; Philippe, Hervé; Ruhfel, Brad R; Miles, Nicholas W; Graham, Sean W; Mathews, Sarah; Surek, Barbara; Melkonian, Michael; Soltis, Douglas E; Soltis, Pamela S; Rothfels, Carl; Pokorny, Lisa; Shaw, Jonathan A; DeGironimo, Lisa; Stevenson, Dennis W; Villarreal, Juan Carlos; Chen, Tao; Kutchan, Toni M; Rolf, Megan; Baucom, Regina S; Deyholos, Michael K; Samudrala, Ram; Tian, Zhijian; Wu, Xiaolei; Sun, Xiao; Zhang, Yong; Wang, Jun; Leebens-Mack, Jim; Wong, Gane Ka-Shu

    2014-01-01

    The 1,000 plants (1KP) project is an international multi-disciplinary consortium that has generated transcriptome data from over 1,000 plant species, with exemplars for all of the major lineages across the Viridiplantae (green plants) clade. Here, we describe how to access the data used in a phylogenomics analysis of the first 85 species, and how to visualize our gene and species trees. Users can develop computational pipelines to analyse these data, in conjunction with data of their own that they can upload. Computationally estimated protein-protein interactions and biochemical pathways can be visualized at another site. Finally, we comment on our future plans and how they fit within this scalable system for the dissemination, visualization, and analysis of large multi-species data sets. PMID:25625010

  6. One System Integrated Project Team Progress in Coordinating Hanford Tank Farms and the Waste Treatment Plant

    SciTech Connect

    Skwarek, Raymond J.; Harp, Ben J.; Duncan, Garth M.

    2013-12-18

    The One System Integrated Project Team (IPT) was formed at the Hanford Site in late 2011 as a way to improve coordination and itegration between the Hanford Tank Waste Treatment and Immobilization Plant (WTP) and the Tank Operations Contractor (TOC) on interfaces between the two projects, and to eliminate duplication and exploit opportunities for synergy. The IPT is composed of jointly staffed groups that work on technical issues of mutal interest, front-end design and project definition, nuclear safety, plant engineering system integration, commissioning, planning and scheduling, and environmental, safety, health and quality (ESH&Q) areas. In the past year important progress has been made in a number of areas as the organization has matured and additional opportunities have been identified. Areas covered in this paper include: Support for development of the Office of Envirnmental Management (EM) framework document to progress the Office of River Protection's (ORP) River Protection Project (RPP) mission; Stewardship of the RPP flowsheet; Collaboration with Savannah River Site (SRS), Savannah River National Laboratory (SRNL), and Pacific Northwest National Laboratory (PNNL); Operations programs integration; and, Further development of the waste acceptance criteria.

  7. Clinch River Breeder Reactor Plant Project. Summary edition. 1980 technical progress report, October 1979-September 1980

    SciTech Connect

    Not Available

    1980-01-01

    This technical progress report on the CRBRP Project describes the objectives, design decisions, and major accomplishments achieved in the planning, organizing, design, and execution of the Project during the period October 1, 1979, through September 30, 1980. It is a summary of the 1980 CRBRP Technical Progress Report, which was prepared by the Advanced Reactors Division of Westinghouse Electric Corporation, the Lead Reactor Manufacturer for the Clinch River Breeder Reactor Plant Project, in fulfillment of contract requirements with the United States Department of Energy. It includes inputs from the CRBRP Architect-Engineer (Burns and Roe, Inc.), from the Constructor (Stone and Webster Engineering Corporation), and from the supporting Reactor Manufacturers (Atomics International Division of the Energy Systems Group of Rockwell International Corporation, the Advanced Reactor Systems Department of General Electric Company, and the Advanced Reactors Division of Westinghouse Electric Corporation).

  8. Life cycle assessment of construction and demolition waste management

    SciTech Connect

    Butera, Stefania Christensen, Thomas H.; Astrup, Thomas F.

    2015-10-15

    Highlights: • LCA of C&DW utilisation in road vs. C&DW landfilling. • C&DW utilisation in road better than landfilling for most categories. • Transportation is the most important process in non-toxic impact categories. • Leaching of oxyanions is the critical process in toxic impact categories. • Modelling of Cr fate in the subsoil is highly influential to the results. - Abstract: Life cycle assessment (LCA) modelling of construction and demolition waste (C&DW) management was carried out. The functional unit was management of 1 Mg mineral, source separated C&DW, which is either utilised in road construction as a substitute for natural aggregates, or landfilled. The assessed environmental impacts included both non-toxic and toxic impact categories. The scenarios comprised all stages of the end-of-life management of C&DW, until final disposal of all residues. Leaching of inorganic contaminants was included, as was the production of natural aggregates, which was avoided because of the use of C&DW. Typical uncertainties related to contaminant leaching were addressed. For most impact categories, utilisation of C&DW in road construction was preferable to landfilling; however, for most categories, utilisation resulted in net environmental burdens. Transportation represented the most important contribution for most nontoxic impacts, accounting for 60–95 per cent of these impacts. Capital goods contributed with negligible impacts. Leaching played a critical role for the toxic categories, where landfilling had lower impacts than utilisation because of the lower levels of leachate per ton of C&DW reaching the groundwater over a 100-year perspective. Leaching of oxyanions (As, V and Sb) was critical with respect to leaching. Typical experimental uncertainties in leaching data did not have a pivotal influence on the results; however, accounting for Cr immobilisation in soils as part of the impact assessment was critical for modelling the leaching impacts. Compared

  9. Life cycle assessment of construction and demolition waste management.

    PubMed

    Butera, Stefania; Christensen, Thomas H; Astrup, Thomas F

    2015-10-01

    Life cycle assessment (LCA) modelling of construction and demolition waste (C&DW) management was carried out. The functional unit was management of 1 Mg mineral, source separated C&DW, which is either utilised in road construction as a substitute for natural aggregates, or landfilled. The assessed environmental impacts included both non-toxic and toxic impact categories. The scenarios comprised all stages of the end-of-life management of C&DW, until final disposal of all residues. Leaching of inorganic contaminants was included, as was the production of natural aggregates, which was avoided because of the use of C&DW. Typical uncertainties related to contaminant leaching were addressed. For most impact categories, utilisation of C&DW in road construction was preferable to landfilling; however, for most categories, utilisation resulted in net environmental burdens. Transportation represented the most important contribution for most nontoxic impacts, accounting for 60-95 per cent of these impacts. Capital goods contributed with negligible impacts. Leaching played a critical role for the toxic categories, where landfilling had lower impacts than utilisation because of the lower levels of leachate per ton of C&DW reaching the groundwater over a 100-year perspective. Leaching of oxyanions (As, V and Sb) was critical with respect to leaching. Typical experimental uncertainties in leaching data did not have a pivotal influence on the results; however, accounting for Cr immobilisation in soils as part of the impact assessment was critical for modelling the leaching impacts. Compared with the overall life cycle of building and construction materials, leaching emissions were shown to be potentially significant for toxicity impacts, compared with contributions from production of the same materials, showing that end-of-life impacts and leaching should not be disregarded when assessing environmental impacts from construction products and materials. CO2 uptake in the C

  10. Life cycle assessment of construction and demolition waste management.

    PubMed

    Butera, Stefania; Christensen, Thomas H; Astrup, Thomas F

    2015-10-01

    Life cycle assessment (LCA) modelling of construction and demolition waste (C&DW) management was carried out. The functional unit was management of 1 Mg mineral, source separated C&DW, which is either utilised in road construction as a substitute for natural aggregates, or landfilled. The assessed environmental impacts included both non-toxic and toxic impact categories. The scenarios comprised all stages of the end-of-life management of C&DW, until final disposal of all residues. Leaching of inorganic contaminants was included, as was the production of natural aggregates, which was avoided because of the use of C&DW. Typical uncertainties related to contaminant leaching were addressed. For most impact categories, utilisation of C&DW in road construction was preferable to landfilling; however, for most categories, utilisation resulted in net environmental burdens. Transportation represented the most important contribution for most nontoxic impacts, accounting for 60-95 per cent of these impacts. Capital goods contributed with negligible impacts. Leaching played a critical role for the toxic categories, where landfilling had lower impacts than utilisation because of the lower levels of leachate per ton of C&DW reaching the groundwater over a 100-year perspective. Leaching of oxyanions (As, V and Sb) was critical with respect to leaching. Typical experimental uncertainties in leaching data did not have a pivotal influence on the results; however, accounting for Cr immobilisation in soils as part of the impact assessment was critical for modelling the leaching impacts. Compared with the overall life cycle of building and construction materials, leaching emissions were shown to be potentially significant for toxicity impacts, compared with contributions from production of the same materials, showing that end-of-life impacts and leaching should not be disregarded when assessing environmental impacts from construction products and materials. CO2 uptake in the C

  11. SRC-1: coal liquefaction demonstration plant. Project Baseline assessment report supplement

    SciTech Connect

    Not Available

    1984-09-01

    ICRC issued a Revised Baseline for the SRC-I Demonstration Project in order to incorporate the results of these research activities and the changes in the design that had occurred since FY82. The Revised Baseline, prepared by ICRC, provides the necessary information for any future government or commercial decisions relating to the design, construction and operation of an SRC-I-type coal liquefaction facility. No further activities to complete the design of the demonstration plant, or to proceed with construction are planned by DOE. The Project Baseline is an ICRC-documented reference for controlling any future project work and cost. The original Baseline was issued in March 1982; this summary document is available from National Technical Information Service (NTIS) as document number DOE/ORO/030540-T13. The Revised Baseline (dated April 1984) is available as document numbers DOE/OR/03054-T14 and T16. Supporting documentation, in the main concerned with research activities undertaken in support of the design, is also available from NTIS as DOE/OR/03054-T1 through T10 and DOE/OR/03054-1 through 125. The Baseline itself is made up of a documented design configuration, a documented estimate, in First Quarter Fiscal Year 1982 Dollars (1QFY82$), and a detailed schedule of the activities required to complete the project as of 3QFY82. The Baseline design is embodied in the 26 process design packages and other support documentation identified in the Baseline, as well as preliminary engineering flow diagrams prepared for all of the major process areas of the plant. All elements of the Project Baseline were developed within the constraints of the project criteria.

  12. Decontamination and demolition of a former plutonium processing facility`s process exhaust system, firescreen, and filter plenum buildings

    SciTech Connect

    LaFrate, P.J. Jr.; Stout, D.S.; Elliott, J.W.

    1996-04-01

    The Los Alamos National Laboratory (LANL) Decommissioning Project has decontaminated, demolished, and decommissioned a process exhaust system, two filter plenum buildings, and a firescreen plenum structure at Technical Area 21 (TA-21). The project began in August 1995 and was completed in January 1996. These high-efficiency particulate air (HEPA) filter plenums and associated ventilation ductwork provided process exhaust to fume hoods and glove boxes in TA-21 Buildings 2 through 5 when these buildings were active plutonium and uranium processing and research facilities. This paper summarizes the history of TA-21 plutonium and uranium processing and research activities and provides a detailed discussion of integrated work process controls, characterize-as-you-go methodology, unique engineering controls, decontamination techniques, demolition methodology, waste minimization, and volume reduction. Also presented in detail are the challenges facing the LANL Decommissioning Project to safely and economically decontaminate and demolish surplus facilities and the unique solutions to tough problems. This paper also shows the effectiveness of the integrated work package concept to control work through all phases.

  13. Decontamination and demolition of a former plutonium processing facility`s process exhaust system, firescreen, and filter plenum buildings

    SciTech Connect

    LaFrate, P.J. Jr.; Stout, D.S.; Elliott, J.W.

    1996-03-01

    The Los Alamos National Laboratory (LANL) Decommissioning Project has decontaminated, demolished, and decommissioned a process exhaust system, two filter plenum buildings, and a firescreen plenum structure at Technical Area 21 (TA-2 1). The project began in August 1995 and was completed in January 1996. These high-efficiency particulate air (HEPA) filter plenums and associated ventilation ductwork provided process exhaust to fume hoods and glove boxes in TA-21 Buildings 2 through 5 when these buildings were active plutonium and uranium processing and research facilities. This paper summarizes the history of TA-21 plutonium and uranium processing and research activities and provides a detailed discussion of integrated work process controls, characterize-as-you-go methodology, unique engineering controls, decontamination techniques, demolition methodology, waste minimization, and volume reduction. Also presented in detail are the challenges facing the LANL Decommissioning Project to safely and economically decontaminate and demolish surplus facilities and the unique solutions to tough problems. This paper also shows the effectiveness of the integrated work package concept to control work through all phases.

  14. A&M. Outdoor turntable. Workings and design exposed during demolition. Detail ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    A&M. Outdoor turntable. Workings and design exposed during demolition. Detail of radially placed steel beams supporting rotating platform. Part of shielded locomotive at upper right. Date: February 3, 2003. INEEL negative no. HD-37-1-3 - Idaho National Engineering Laboratory, Test Area North, Scoville, Butte County, ID

  15. Quantum non demolition measurement of cyclotron excitations in a Penning trap

    NASA Technical Reports Server (NTRS)

    Marzoli, Irene; Tombesi, Paolo

    1993-01-01

    The quantum non-demolition measurement of the cyclotron excitations of an electron confined in a Penning trap could be obtained by measuring the resonance frequency of the axial motion, which is coupled to the cyclotron motion through the relativistic shift of the electron mass.

  16. Choosing a sustainable demolition waste management strategy using multicriteria decision analysis

    SciTech Connect

    Roussat, Nicolas Dujet, Christiane; Mehu, Jacques

    2009-01-15

    This paper presents an application of the ELECTRE III decision-aid method in the context of choosing a sustainable demolition waste management strategy for a case study in the city of Lyon, France. This choice of waste management strategy takes into consideration the sustainable development objectives, i.e. economic aspects, environmental consequences, and social issues. Nine alternatives for demolition waste management were compared with the aid of eight criteria, taking into account energy consumption, depletion of abiotic resources, global warming, dispersion of dangerous substances in the environment, economic activity, employment, and quality of life of the local population. The case study concerned the demolition of 25 buildings of an old military camp. Each alternative was illustrated with different waste treatments, such as material recovery, recycling, landfilling, and energy recovery. The recommended solution for sustainable demolition waste management for the case study is a selective deconstruction of each building with local material recovery in road engineering of inert wastes, local energy recovery of wood wastes, and specific treatments for hazardous wastes.

  17. Performance and durability of concrete made with demolition waste and artificial fly ash-clay aggregates

    SciTech Connect

    Zakaria, M.; Cabrera, J.G.

    1996-12-31

    Demolition aggregates and artificial aggregates made with waste materials are two alternatives being studied for replacement of natural aggregates in the production of concrete. Natural aggregate sources in Europe are increasingly scarce and subject to restrictions based on environmental regulations. In many areas of the developing world sources of good quality aggregates are very limited or practically not available and therefore it has become necessary to study alternative materials. This paper presents a laboratory study on the use of demolition bricks and artificial aggregates made from fly ash-clay as coarse aggregates to make concrete. The concretes made either with demolition bricks or artificial aggregates are compared with a control mix made with natural gravel aggregates. The strength and durability characteristics of these concretes are evaluated using as a criteria compressive strength and transport properties, such as gas and water permeability. The results show clearly that concretes of good performance and durability can be produced using aggregates from demolition rubble or using artificial aggregates made with wastes such as fly ash.

  18. The uncertainty principle in resonant gravitational wave antennae and quantum non-demolition measurement schemes

    NASA Technical Reports Server (NTRS)

    Fortini, Pierluigi; Onofrio, Roberto; Rioli, Alessandro

    1993-01-01

    A review on the current efforts to approach and to surpass the fundamental limit in the sensitivity of the Weber type gravitational wave antennae is reported. Applications of quantum non-demolition techniques to the concrete example of an antenna resonant with the transducer are discussed in detail. Analogies and differences from the framework of the squeezed states in quantum optics are discussed.

  19. Choosing a sustainable demolition waste management strategy using multicriteria decision analysis.

    PubMed

    Roussat, Nicolas; Dujet, Christiane; Méhu, Jacques

    2009-01-01

    This paper presents an application of the ELECTRE III decision-aid method in the context of choosing a sustainable demolition waste management strategy for a case study in the city of Lyon, France. This choice of waste management strategy takes into consideration the sustainable development objectives, i.e. economic aspects, environmental consequences, and social issues. Nine alternatives for demolition waste management were compared with the aid of eight criteria, taking into account energy consumption, depletion of abiotic resources, global warming, dispersion of dangerous substances in the environment, economic activity, employment, and quality of life of the local population. The case study concerned the demolition of 25 buildings of an old military camp. Each alternative was illustrated with different waste treatments, such as material recovery, recycling, landfilling, and energy recovery. The recommended solution for sustainable demolition waste management for the case study is a selective deconstruction of each building with local material recovery in road engineering of inert wastes, local energy recovery of wood wastes, and specific treatments for hazardous wastes. PMID:18572397

  20. 22 CFR 121.11 - Military demolition blocks and blasting caps.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 22 Foreign Relations 1 2010-04-01 2010-04-01 false Military demolition blocks and blasting caps. 121.11 Section 121.11 Foreign Relations DEPARTMENT OF STATE INTERNATIONAL TRAFFIC IN ARMS REGULATIONS... ones. (c) Delay electric blasting caps (including No. 6 and No. 8 millisecond ones). (d)...

  1. 22 CFR 121.11 - Military demolition blocks and blasting caps.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... 22 Foreign Relations 1 2011-04-01 2011-04-01 false Military demolition blocks and blasting caps. 121.11 Section 121.11 Foreign Relations DEPARTMENT OF STATE INTERNATIONAL TRAFFIC IN ARMS REGULATIONS... ones. (c) Delay electric blasting caps (including No. 6 and No. 8 millisecond ones). (d)...

  2. 24 CFR 970.15 - Specific criteria for HUD approval of demolition requests.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... criteria for disapproval under 24 CFR 970.29. An application for the demolition of all or a portion of a... building caused by inadequate structural fills, faulty structural design, or settlement of floors), or other design or site problems (severe erosion or flooding); (ii) As to location: physical...

  3. Asbestos Exposure among Construction Workers During Demolition of Old Houses in Tehran, Iran

    PubMed Central

    KAKOOEI, Hossein; NORMOHAMMADI, Mohhammad

    2013-01-01

    Air quality in demolition practices has seldom been evaluated in Iran. Accordingly, we evaluated asbestos exposure among Tehran construction workers during the demolition of old houses. To identify possible sources of asbestos exposure, including thermal insulations, chimney pipes and cement sheets, were all sampled. This study also were taken the personal air samples to evaluate any asbestos exposure during the demolition. The asbestos fibers found in the samples were analyzed by phase-contrast optical microscopy (PCM), scanning electron microscopy (SEM) equipped with an energy dispersive X-ray analysis, and polarized light microscopy (PLM) methods. Personal monitoring of asbestos fiber levels indicated a range from 0.01 to 0.15 PCM f/ml (0.02–0.42 SEM f/ml). The geometric mean concentrations were 0.07 PCM f/ml (0.20 SEM f/ml), which is considerably higher than the threshold limit value (TLV) proposed by American Conference of Governmental Industrial Hygienist (ACGIH), which is 0.1 f/ml. The analysis showed a presence in the bulk samples only chrysotile asbestos and an absence of the other type asbestos. Therefore, it might be expected that workers who worked in the demolition of old houses will suffer from negative effects of exposing to the asbestos fibers. PMID:24292876

  4. Overview On Alternative Asbestos Control Method Research: Alternative Methods To Demolition

    EPA Science Inventory

    The Alternative Asbestos Control Method (AACM) is an experimental approach to building demolition. Unlike the NESHAP method, the AACM allows some regulated asbestos-containing material to remain in the building and a surfactant-water solution is used to suppress asbestos fibers ...

  5. 36 CFR 72.41 - Demolition and replacement of existing recreation properties.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... existing recreation properties. 72.41 Section 72.41 Parks, Forests, and Public Property NATIONAL PARK SERVICE, DEPARTMENT OF THE INTERIOR URBAN PARK AND RECREATION RECOVERY ACT OF 1978 Grants for Recovery... recreation properties. Demolition will only be supported when rehabilitation is not feasible or prudent....

  6. 36 CFR 72.41 - Demolition and replacement of existing recreation properties.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... existing recreation properties. 72.41 Section 72.41 Parks, Forests, and Public Property NATIONAL PARK SERVICE, DEPARTMENT OF THE INTERIOR URBAN PARK AND RECREATION RECOVERY ACT OF 1978 Grants for Recovery... recreation properties. Demolition will only be supported when rehabilitation is not feasible or prudent....

  7. 36 CFR 72.41 - Demolition and replacement of existing recreation properties.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... existing recreation properties. 72.41 Section 72.41 Parks, Forests, and Public Property NATIONAL PARK SERVICE, DEPARTMENT OF THE INTERIOR URBAN PARK AND RECREATION RECOVERY ACT OF 1978 Grants for Recovery... recreation properties. Demolition will only be supported when rehabilitation is not feasible or prudent....

  8. 36 CFR 72.41 - Demolition and replacement of existing recreation properties.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... existing recreation properties. 72.41 Section 72.41 Parks, Forests, and Public Property NATIONAL PARK SERVICE, DEPARTMENT OF THE INTERIOR URBAN PARK AND RECREATION RECOVERY ACT OF 1978 Grants for Recovery... recreation properties. Demolition will only be supported when rehabilitation is not feasible or prudent....

  9. 36 CFR 72.41 - Demolition and replacement of existing recreation properties.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... existing recreation properties. 72.41 Section 72.41 Parks, Forests, and Public Property NATIONAL PARK SERVICE, DEPARTMENT OF THE INTERIOR URBAN PARK AND RECREATION RECOVERY ACT OF 1978 Grants for Recovery... recreation properties. Demolition will only be supported when rehabilitation is not feasible or prudent....

  10. A&M. Outdoor turntable. Workings and design exposed during demolition. View ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    A&M. Outdoor turntable. Workings and design exposed during demolition. View between two of the four rails of the track. Note motor and electrical conduit. Date: February 3, 2003. INEEL negative no. HD-37-1-1 - Idaho National Engineering Laboratory, Test Area North, Scoville, Butte County, ID

  11. The uncertainty principle in resonant gravitational wave antennae and quantum non-demolition measurement schemes

    NASA Technical Reports Server (NTRS)

    Fortini, Pierluigi; Onofrio, Roberto; Rioli, Alessandro

    1993-01-01

    A review of current efforts to approach and to surpass the fundamental limit in the sensitivity of the Weber type gravitational wave antennae is reported. Applications of quantum non-demolition techniques to the concrete example of an antenna resonant with the transducer are discussed in detail. Analogies and differences from the framework of the squeezed states in quantum optics are discussed.

  12. 24 CFR 970.15 - Specific criteria for HUD approval of demolition requests.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... criteria for disapproval under 24 CFR 970.29. An application for the demolition of all or a portion of a... environmental conditions as determined by HUD environmental review in accord with 24 CFR part 50, which... this section: (1) Major problems indicative of obsolescence are: (i) As to physical...

  13. 24 CFR 970.15 - Specific criteria for HUD approval of demolition requests.

    Code of Federal Regulations, 2014 CFR

    2014-04-01

    ... criteria for disapproval under 24 CFR 970.29. An application for the demolition of all or a portion of a... environmental conditions as determined by HUD environmental review in accord with 24 CFR part 50, which... this section: (1) Major problems indicative of obsolescence are: (i) As to physical...

  14. 32 CFR 644.478 - Demolition of buildings and other improvements for utilization of salvage material.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... (Continued) DEPARTMENT OF THE ARMY (CONTINUED) REAL PROPERTY REAL ESTATE HANDBOOK Disposal Disposal of... funds for the purpose are made available. Real Estate funds will not be used for such demolition...-erection at another installation is not to be accomplished as a real estate function (AR 420-70)....

  15. A&M. Outdoor turntable. Workings and design exposed during demolition. Detail ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    A&M. Outdoor turntable. Workings and design exposed during demolition. Detail of platform wheels and structural steel beams resting upon wheel. Wood deck above steel beams. Date: February 3, 2003. INEEL negative no. HD-37-4-1 - Idaho National Engineering Laboratory, Test Area North, Scoville, Butte County, ID

  16. A&M. Outdoor turntable during demolition. Concrete structural supports radiate from ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    A&M. Outdoor turntable during demolition. Concrete structural supports radiate from center towards outer edge of turntable. Detail of wheel. Date: February 3, 2003. INEEL negative no. HD-37-3-2 - Idaho National Engineering Laboratory, Test Area North, Scoville, Butte County, ID

  17. A&M. Outdoor turntable. Workings and design exposed during demolition, turntable ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    A&M. Outdoor turntable. Workings and design exposed during demolition, turntable platform traveled on concentric circular rails, this one the inner rail. Radioactive parts storage area in background. Date: February 3, 2003. INEEL negative no. HD-37-2-2 - Idaho National Engineering Laboratory, Test Area North, Scoville, Butte County, ID

  18. 48 CFR 46.313 - Contracts for dismantling, demolition, or removal of improvements.

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 1 2010-10-01 2010-10-01 false Contracts for dismantling, demolition, or removal of improvements. 46.313 Section 46.313 Federal Acquisition Regulations System FEDERAL ACQUISITION REGULATION CONTRACT MANAGEMENT QUALITY ASSURANCE Contract Clauses 46.313 Contracts for...

  19. 24 CFR 969.107 - HUD approval of demolition or disposition before ACC expiration.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... 24 Housing and Urban Development 4 2010-04-01 2010-04-01 false HUD approval of demolition or disposition before ACC expiration. 969.107 Section 969.107 Housing and Urban Development Regulations Relating to Housing and Urban Development (Continued) OFFICE OF ASSISTANT SECRETARY FOR PUBLIC AND INDIAN HOUSING, DEPARTMENT OF HOUSING AND...

  20. Data base on dose reduction research projects for nuclear power plants. Volume 5

    SciTech Connect

    Khan, T.A.; Yu, C.K.; Roecklein, A.K.

    1994-05-01

    This is the fifth volume in a series of reports that provide information on dose reduction research and health physics technology or nuclear power plants. The information is taken from two of several databases maintained by Brookhaven National Laboratory`s ALARA Center for the Nuclear Regulatory Commission. The research section of the report covers dose reduction projects that are in the experimental or developmental phase. It includes topics such as steam generator degradation, decontamination, robotics, improvements in reactor materials, and inspection techniques. The section on health physics technology discusses dose reduction efforts that are in place or in the process of being implemented at nuclear power plants. A total of 105 new or updated projects are described. All project abstracts from this report are available to nuclear industry professionals with access to a fax machine through the ACEFAX system or a computer with a modem and the proper communications software through the ACE system. Detailed descriptions of how to access all the databases electronically are in the appendices of the report.

  1. Beyond ectomycorrhizal bipartite networks: projected networks demonstrate contrasted patterns between early- and late-successional plants in Corsica

    PubMed Central

    Taudiere, Adrien; Munoz, François; Lesne, Annick; Monnet, Anne-Christine; Bellanger, Jean-Michel; Selosse, Marc-André; Moreau, Pierre-Arthur; Richard, Franck

    2015-01-01

    The ectomycorrhizal (ECM) symbiosis connects mutualistic plants and fungal species into bipartite networks. While links between one focal ECM plant and its fungal symbionts have been widely documented, systemic views of ECM networks are lacking, in particular, concerning the ability of fungal species to mediate indirect ecological interactions between ECM plant species (projected-ECM networks). We assembled a large dataset of plant–fungi associations at the species level and at the scale of Corsica using molecular data and unambiguously host-assigned records to: (i) examine the correlation between the number of fungal symbionts of a plant species and the average specialization of these fungal species, (ii) explore the structure of the plant–plant projected network and (iii) compare plant association patterns in regard to their position along the ecological succession. Our analysis reveals no trade-off between specialization of plants and specialization of their partners and a saturation of the plant projected network. Moreover, there is a significantly lower-than-expected sharing of partners between early- and late-successional plant species, with fewer fungal partners for early-successional ones and similar average specialization of symbionts of early- and late-successional plants. Our work paves the way for ecological readings of Mediterranean landscapes that include the astonishing diversity of below-ground interactions. PMID:26539201

  2. The main goals of experiments with the higher plants in the project MARS - 500.

    NASA Astrophysics Data System (ADS)

    Sychev, Vladimir; Levinskikh, Margarita; Podolsky, Igor; Gushin, Vadim; Bingham, Gail; Bates, Scott

    At the present step of development of manned flight to Mars there is a current opinion that including a greenhouse in the composition of Life Support Systems (LSS) of Martian expedition would essentially improve a spacecraft habitat conditions and also would have impact to preventing of a number of possible consequences of continuous presence of human in artificial environment. Development of design objectives of future space greenhouses applicable for conditions of Martian expedition should be based, in our opinion, not only on the results of real space experiments, conducted onboard of orbital stations, but also on the results of ground-based experiments. In connection with above considerations there is a number of technological, biological and psychological experiments is planned to be conducted in the frame of MARS-500 project to resolve questions related to incorporation of higher plants in LSS of inter-planetary flights. The questions include: testing of developed elements of the greenhouse construction and methods for cultivation of vegetables under conditions of imitation of the flight of Martian expedition; selection of breeds and species of vegetables, characterized by high speed of biomass accumulation, attractive taste and appearance; investigation of growth, development and metabolism of plants under long-term continuous cultivation in manned pressurized object; comparison of the productivity of the plants as a function of utilization of different light source; determination of maximum amount of planted biomass of the plants and number of possible vegetation under conditions of long-term utilization of vegetation chamber of the greenhouse without substrate replacement; investigation of crops dietetic preferences of crew members; estimation of quality of plant biomass using seeding of the plants by microorganisms and nitrates and vitamins content as markers; development and approbation of methodical approaches to estimation of psychological factors of

  3. Plant Response and Environmental Data from the Oldfield Community Climate and Atmospheric Manipulation (OCCAM) Project

    DOE Data Explorer

    The Oldfield Community Climate and Atmospheric Manipulation (OCCAM) project is a joint effort of ORNL and the University of Tennessee to investigate community and ecosystem response to global change, specifically looking at the interactive effects of atmospheric carbon dioxide, surface temperatures, and soil moisture. The plants studied for their response to warming temperatures, elevated carbon dioxide, and altered water availability include C3 and C4 grasses, forbs, and legumes. These plants are typical of an old-field ecosystem that establishes itself on unused agricultural land. The results of the research focus on species abundance, production, phenology, and what is going on chemically below ground. Data are currently available from 2003 through July, 2008.

  4. Marine ecological habitat: a case study on projected thermal power plant around Dharamtar Creek, India.

    PubMed

    Kulkarni, Vikrant A; Naidu, Velamala S; Jagtap, Tanaji G

    2011-03-01

    Estuaries and tidal creeks, harboring mangroves particularly, face tremendous anthropogenic pressures. Expansion of mega cities and the thermal power plants are generally proposed in the vicinity of estuaries and creek, due to the feasibility of intake and discharge of water for cooling. Discharges from such developments remain constant threat of increasing thermal pollution and affecting the quality of environment. The baseline information on prevailing quality of aquatic environment comes handy for understanding alterations due to such activities. Principle component analysis (PCA) revealed that temperature, pH, salinity, suspended solids, DO, BOD and phaeophytins are major parameters influencing the creek system. Heated effluents may have direct and adverse impacts on these parameters, altering biotic constituents. Hence, periodic and detailed observations are necessary to estimate exact response of biotic communities to changing environment. The present paper is based on case study, projecting a power plant in the vicinity of major mangrove habitats of Dharamtar creek.

  5. Marine ecological habitat: a case study on projected thermal power plant around Dharamtar Creek, India.

    PubMed

    Kulkarni, Vikrant A; Naidu, Velamala S; Jagtap, Tanaji G

    2011-03-01

    Estuaries and tidal creeks, harboring mangroves particularly, face tremendous anthropogenic pressures. Expansion of mega cities and the thermal power plants are generally proposed in the vicinity of estuaries and creek, due to the feasibility of intake and discharge of water for cooling. Discharges from such developments remain constant threat of increasing thermal pollution and affecting the quality of environment. The baseline information on prevailing quality of aquatic environment comes handy for understanding alterations due to such activities. Principle component analysis (PCA) revealed that temperature, pH, salinity, suspended solids, DO, BOD and phaeophytins are major parameters influencing the creek system. Heated effluents may have direct and adverse impacts on these parameters, altering biotic constituents. Hence, periodic and detailed observations are necessary to estimate exact response of biotic communities to changing environment. The present paper is based on case study, projecting a power plant in the vicinity of major mangrove habitats of Dharamtar creek. PMID:21882658

  6. Projected techno-economic improvements for advanced solar thermal power plants

    NASA Technical Reports Server (NTRS)

    Fujita, T.; Manvi, R.; Roschke, E. J.

    1979-01-01

    The projected characteristics of solar thermal power plants (with outputs up to 10 MWe) employing promising advanced technology subsystems/components are compared to current (or pre-1985) steam-Rankine systems. Improvements accruing to advanced technology development options are delineated. The improvements derived from advanced systems result primarily from achieving high efficiencies via solar collector systems which (1) capture a large portion of the available insolation and (2) concentrate this captured solar flux to attain high temperatures required for high heat engine/energy conversion performance. The most efficient solar collector systems employ two-axis tracking. Attractive systems include the central receiver/heliostat and the parabolic dish.

  7. Condensed listing of surface boreholes at the Waste Isolation Pilot Plant Project through 31 December 1995

    SciTech Connect

    Hill, L.R.; Aguilar, R.; Mercer, J.W.; Newman, G.

    1997-01-01

    This report contains a condensed listing of Waste Isolation Pilot Plant (WIPP) project surface boreholes drilled for the purpose of site selection and characterization through 31 December 1995. The US Department of Energy (DOE) sponsored the drilling activities, which were conducted primarily by Sandia National Laboratories. The listing provides physical attributes such as location (township, range, section, and state-plane coordinates), elevation, and total borehole depth, as well as the purpose for the borehole, drilling dates, and information about extracted cores. The report also presents the hole status (plugged, testing, monitoring, etc.) and includes salient findings and references. Maps with borehole locations and times-of-drilling charts are included.

  8. Research and Development Technology Development Roadmaps for the Next Generation Nuclear Plant Project

    SciTech Connect

    Ian McKirdy

    2011-07-01

    The U.S. Department of Energy (DOE) has selected the high temperature gas-cooled reactor (HTGR) design for the Next Generation Nuclear Plant (NGNP) Project. The NGNP will demonstrate the use of nuclear power for process heat, hydrogen and electricity production. The reactor will be graphite moderated with helium as the primary coolant and may be either prismatic or pebble-bed. Although, final design features have not yet been determined. Research and Development (R&D) activities are proceeding on those known plant systems to mature the technology, codify the materials for specific applications, and demonstrate the component and system viability in NGNP relevant and integrated environments. Collectively these R&D activities serve to reduce the project risk and enhance the probability of on-budget, on-schedule completion and NRC licensing. As the design progresses, in more detail, toward final design and approval for construction, selected components, which have not been used in a similar application, in a relevant environment nor integrated with other components and systems, must be tested to demonstrate viability at reduced scales and simulations prior to full scale operation. This report and its R&D TDRMs present the path forward and its significance in assuring technical readiness to perform the desired function by: Choreographing the integration between design and R&D activities; and proving selected design components in relevant applications.

  9. Automated chemical monitoring in new projects of nuclear power plant units

    NASA Astrophysics Data System (ADS)

    Lobanok, O. I.; Fedoseev, M. V.

    2013-07-01

    The development of automated chemical monitoring systems in nuclear power plant units for the past 30 years is briefly described. The modern level of facilities used to support the operation of automated chemical monitoring systems in Russia and abroad is shown. Hardware solutions suggested by the All-Russia Institute for Nuclear Power Plant Operation (which is the General Designer of automated process control systems for power units used in the AES-2006 and VVER-TOI Projects) are presented, including the structure of additional equipment for monitoring water chemistry (taking the Novovoronezh 2 nuclear power plant as an example). It is shown that the solutions proposed with respect to receiving and processing of input measurement signals and subsequent construction of standard control loops are unified in nature. Simultaneous receipt of information from different sources for ensuring that water chemistry is monitored in sufficient scope and with required promptness is one of the problems that have been solved successfully. It is pointed out that improved quality of automated chemical monitoring can be supported by organizing full engineering follow-up of the automated chemical monitoring system's equipment throughout its entire service life.

  10. The start-up of the DIOS pilot plant (DIOS Project)

    SciTech Connect

    Sawada, Terutoshi

    1995-12-01

    The DIOS process has been successfully developed as an 8-year project commenced in April 1988. Based on the results of the element studies reported at the previous conference and at other meetings, the pilot plant, with a designed capacity of 500 t/d, was constructed and started up in october 1993. After the starting operation with the single smelting reduction furnace in the beginning of the first campaign, the pilot plant has been principally operated in integration, that is, with the smelting reduction furnace connected with the preheating and prereduction furnaces. So far five campaigns have been successfully conducted on schedule. The operation has been improved gradually and the designed performance has been achieved. New processes are targeted at the direct use of coal and iron ore fines to eliminate not only the problematic coke ovens but also pellet and sinter plants. The direct smelting reduction processes currently at the most advanced stage of development are the DIOS in Japan, the AISI in the USA and the HIsmelt in Australia.

  11. Effect of the implosion and demolition of a hospital building on the concentration of fungi in the air.

    PubMed

    Barreiros, Gloria; Akiti, Tiyomi; Magalhães, Ana Cristina Gouveia; Nouér, Simone A; Nucci, Marcio

    2015-12-01

    Building renovations increase the concentration of Aspergillus conidia in the air. In 2010, one wing of the hospital building was imploded due to structural problems. To evaluate the impact of building implosion on the concentration of fungi in the air, the demolition was performed in two phases: mechanical demolition of 30 m of the building, followed by implosion of the wing. Patients at high risk for aspergillosis were placed in protected wards. Air sampling was performed during mechanical demolition, on the day of implosion and after implosion. Total and specific fungal concentrations were compared in the different areas and periods of sampling, using the anova test. The incidence of IA in the year before and after implosion was calculated. The mean concentration of Aspergillus increased during mechanical demolition and on the day of implosion. However, in the most protected areas, there was no significant difference in the concentration of fungi. The incidence of invasive aspergillosis (cases per 1000 admissions) was 0.9 in the 12 months before, 0.4 during, and 0.5 in the 12 months after mechanical demolition (P > 0.05). Continuous monitoring of the quality of air and effective infection control measures are important to minimize the impact of building demolition. PMID:26449634

  12. 44 CFR 80.17 - Project implementation.

    Code of Federal Regulations, 2012 CFR

    2012-10-01

    ... participation. This excludes permitted disposal of incidental demolition and household hazardous wastes. FEMA... 44 Emergency Management and Assistance 1 2012-10-01 2011-10-01 true Project implementation. 80.17 Section 80.17 Emergency Management and Assistance FEDERAL EMERGENCY MANAGEMENT AGENCY, DEPARTMENT...

  13. Stress reactions and coping strategies among Bedouin Arab adolescents exposed to demolition of houses.

    PubMed

    Braun-Lewensohn, Orna; Sagy, Shifra; Al Said, Haled

    2014-10-01

    The aim of this study was to examine emotional reactions and coping strategies of Bedouin adolescents against the backdrop of house demolitions in the unrecognized Bedouin villages in the Negev, Israel. We compared two groups of adolescents living in unrecognized Bedouin villages, teenagers whose houses had been destroyed (acute + chronic group) and their counterparts whose houses had not been destroyed (chronic group). Data were gathered during October to December 2010 from 465 Bedouin adolescents aged 13-18 years. Adolescents filled out self-report questionnaires, which included demographics, objective and subjective exposure to house demolition, state anxiety, state anger, psychological distress and Adolescent Coping Scale. Results show differences between the two groups in stress reactions as well as in objective exposure to house demolition with the acute + chronic group reporting more stress and more exposure. In addition, different variables explained stress reactions in the different groups. Whereas in the acute + chronic group, objective and subjective exposure were the most significant variables, in the chronic group, the coping strategies explained stress with more variance. Results are discussed in terms of differentiating between types of stress, chronic versus acute + chronic and in relation to the interactionist model of coping with stress.

  14. Brigham City Hydro Generation Project

    SciTech Connect

    Ammons, Tom B.

    2015-10-31

    Brigham City owns and operates its own municipal power system which currently includes several hydroelectric facilities. This project was to update the efficiency and capacity of current hydro production due to increased water flow demands that could pass through existing generation facilities. During 2006-2012, this project completed efficiency evaluation as it related to its main objective by completing a feasibility study, undergoing necessary City Council approvals and required federal environmental reviews. As a result of Phase 1 of the project, a feasibility study was conducted to determine feasibility of hydro and solar portions of the original proposal. The results indicated that the existing Hydro plant which was constructed in the 1960’s was running at approximately 77% efficiency or less. Brigham City proposes that the efficiency calculations be refined to determine the economic feasibility of improving or replacing the existing equipment with new high efficiency equipment design specifically for the site. Brigham City completed the Feasibility Assessment of this project, and determined that the Upper Hydro that supplies the main culinary water to the city was feasible to continue with. Brigham City Council provided their approval of feasibility assessment’s results. The Upper Hydro Project include removal of the existing powerhouse equipment and controls and demolition of a section of concrete encased penstock, replacement of penstock just upstream of the turbine inlet, turbine bypass, turbine shut-off and bypass valves, turbine and generator package, control equipment, assembly, start-up, commissioning, Supervisory Control And Data Acquisition (SCADA), and the replacement of a section of conductors to the step-up transformer. Brigham City increased the existing 575 KW turbine and generator with an 825 KW turbine and generator. Following the results of the feasibility assessment Brigham City pursued required environmental reviews with the DOE and

  15. Study on Evaluation of Project Management Data for Decommissioning of Uranium Refining and Conversion Plant - 12234

    SciTech Connect

    Usui, Hideo; Izumo, Sari; Tachibana, Mitsuo; Shibahara, Yuji; Morimoto, Yasuyuki; Tokuyasu, Takashi; Takahashi, Nobuo; Tanaka, Yoshio; Sugitsue, Noritake

    2012-07-01

    Some of nuclear facilities that would no longer be required have been decommissioned in JAEA (Japan Atomic Energy Agency). A lot of nuclear facilities have to be decommissioned in JAEA in near future. To implement decommissioning of nuclear facilities, it was important to make a rational decommissioning plan. Therefore, project management data evaluation system for dismantling activities (PRODIA code) has been developed, and will be useful for making a detailed decommissioning plan for an object facility. Dismantling of dry conversion facility in the uranium refining and conversion plant (URCP) at Ningyo-toge began in 2008. During dismantling activities, project management data such as manpower and amount of waste generation have been collected. Such collected project management data has been evaluated and used to establish a calculation formula to calculate manpower for dismantling equipment of chemical process and calculate manpower for using a green house (GH) which was a temporary structure for preventing the spread of contaminants during dismantling. In the calculation formula to calculate project management data related to dismantling of equipment, the relation of dismantling manpower to each piece of equipment was evaluated. Furthermore, the relation of dismantling manpower to each chemical process was evaluated. The results showed promise for evaluating dismantling manpower with respect to each chemical process. In the calculation formula to calculate project management data related to use of the GH, relations of GH installation manpower and removal manpower to GH footprint were evaluated. Furthermore, the calculation formula for secondary waste generation was established. In this study, project management data related to dismantling of equipment and use of the GH were evaluated and analyzed. The project management data, manpower for dismantling of equipment, manpower for installation and removal of GH, and secondary waste generation from GH were considered

  16. Estimating demolition cost of plutonium buildings for dummies

    SciTech Connect

    Tower, S.E.

    2000-07-01

    The primary purpose of the Rocky Flats Field Office of the US Department of Energy is to decommission the entire plant. In an effort to improve the basis and the accuracy of the future decommissioning cost, Rocky Flats has developed a powerful but easy-to-use tool to determine budget cost estimates to characterize, decontaminate, and demolish all its buildings. The parametric cost-estimating tool is called the Facilities Disposition Cost Model (FDCM).

  17. Plant Responses to Increased UV-B Radiation: A Research Project

    NASA Technical Reports Server (NTRS)

    DAntoni, H. L.; Skiles, J. W.; Armstrong, R.; Coughlan, J.; Daleo, G.; Mayoral, A.; Lawless, James G. (Technical Monitor)

    1994-01-01

    Ozone decrease implies more ultraviolet-B (UV-B) radiation reaching the surface of the Earth. Increased UV-B radiation triggers responses by living organisms. Despite the large potential impacts on vegetation, little is known about UV-B effects on terrestrial ecosystems. Long-term ecological studies are needed to quantify the effects of increased UV radiation on terrestrial ecosystems, asses the risks, and produce reliable data for prediction. Screening pigments are part of one of the protective mechanism in plants. Higher concentrations of screening pigments in leaves may be interpreted as a response to increased UV radiation. If the screening effect is not sufficient, important molecules will be disturbed by incoming radiation. Thus, genetics, photosynthesis, growth, plant and leaf shape and size, and pollen grains may be affected. This will have an impact on ecosystem dynamics, structure and productivity. It is necessary to monitor selected terrestrial ecosystems to permit detection and interpretation of changes attributable to global climate change and depleted ozone shield. The objectives of this project are: (1) To identify and measure indicators of the effects of increased solar UV-B radiation on terrestrial plants; (2) to select indicators with the greatest responses to UV-B exposure; (3) to test, adapt or create ecosystem models that use the information gathered by this project for prediction and to enhance our understanding of the effects of increased UV-B radiation on terrestrial ecosystems. As a first step to achieve these objectives we propose a three-year study of forest and steppe vegetation on the North slope of the Brooks Range (within the Arctic circle, in Alaska), in the Saguaro National Monument (near Tucson, Arizona) and in the forests and steppes of Patagonia (Argentina). We selected (1) vegetation north of the Polar Circle because at 70N there is 8% risk of plant damage due to increased UV-B radiation; (2) the foothills of Catalina Mountains

  18. The Plant Foliage Projective Coverage Change over the Northern Tibetan Plateau during 1957-2009

    NASA Astrophysics Data System (ADS)

    Cuo, L.

    2015-12-01

    Northern Tibetan Plateau is the headwater of the Yellow River, the Yangtze River and the Mekong River that support billions of the population. Vegetation change will affect the regional ecosystem and water balances through the changes in biomass and evapotranspiration. Dynamic vegetation growth is determined by physiological, morphological, bioclimatic and phenological properties. These properties are affected by climate variables such as air temperature, precipitation, soil temperature and concentration of CO2, etc. Due to climate change, some parts of the northern Tibetan Plateau are under the threat of desertification. Identifying the places of vegetation degradation and the dominant driven climatic factors will help mitigate the climate change impacts on ecosystem and water resources in this region. In this study, the changes of foliage projective coverages (FPCs) of various plant functional types (PFTs) existed in the northern Tibetan Plateau and the responses of FPCs to the four climate variables over 1957-2009 are examined. The dominant factors among the four climate variables are also identified. The Lund-Potsdam-Jena Dynamic Global Vegetation Model (LPJ-DGVM) is modified and used for the investigation. The modified LPJ-DGVM can better account for soil temperature in the top 0.4-m depth where vegetation root concentrates over the northern Tibetan Plateau. The modified model is evaluated by using monthly and annual soil temperature observed at stations across the region, and the eco-geographic maps that describe plant types and spatial distributions developed from field surveys and satellite images for this region.

  19. Evolutionary demography of iteroparous plants: incorporating non-lethal costs of reproduction into integral projection models.

    PubMed

    Miller, Tom E X; Williams, Jennifer L; Jongejans, Eelke; Brys, Rein; Jacquemyn, Hans

    2012-07-22

    Understanding the selective forces that shape reproductive strategies is a central goal of evolutionary ecology. Selection on the timing of reproduction is well studied in semelparous organisms because the cost of reproduction (death) can be easily incorporated into demographic models. Iteroparous organisms also exhibit delayed reproduction and experience reproductive costs, although these are not necessarily lethal. How non-lethal costs shape iteroparous life histories remains unresolved. We analysed long-term demographic data for the iteroparous orchid Orchis purpurea from two habitat types (light and shade). In both the habitats, flowering plants had lower growth rates and this cost was greater for smaller plants. We detected an additional growth cost of fruit production in the light habitat. We incorporated these non-lethal costs into integral projection models to identify the flowering size that maximizes fitness. In both habitats, observed flowering sizes were well predicted by the models. We also estimated optimal parameters for size-dependent flowering effort, but found a strong mismatch with the observed flower production. Our study highlights the role of context-dependent non-lethal reproductive costs as selective forces in the evolution of iteroparous life histories, and provides a novel and broadly applicable approach to studying the evolutionary demography of iteroparous organisms.

  20. Performance analysis and pilot plant test results for the Komorany fluidized bed retrofit project

    SciTech Connect

    Snow, G.C.

    1995-12-01

    Detailed heat and mass balance calculations and emission performance projections are presented for an atmospheric fluidized bed boiler bottom retrofit at the 927 MWt (steam output) Komorany power station and district heating plant in the Czech Republic. Each of the ten existing boilers are traveling grate stoker units firing a local, low-rank brown coal. This fuel, considered to be representative of much of the coal deposits in Central Europe, is characterized by an average gross calorific value of 10.5 MJ/kg (4,530 Btu/lb), an average dry basis ash content of 47 %, and a maximum dry basis sulfur content of 1.8 % (3.4 % on a dry, ash free basis). The same fuel supply, together with limestone supplied from the region will be utilized in the retrofit fluidized bed boilers. The primary objectives of this retrofit program are, (1) reduce emissions to a level at or below the new Czech Clean Air Act, and (2) restore plant capacity to the original specification. As a result of the AFBC retrofit and plant upgrade, the particulate matter emissions will be reduced by over 98 percent, SO{sub 2} emissions will be reduced by 88 percent, and NO{sub x} emissions will be reduced by 38 percent compared to the present grate-fired configuration. The decrease in SO{sub 2} emissions resulting from the fluidized bed retrofit was initially predicted based on fuel sulfur content, including the distribution among organic, pyritic, and sulfate forms; the ash alkalinity; and the estimated limestone calcium utilization efficiency. The methodology and the results of this prediction were confirmed and extended by pilot scale combustion trials at a 1.0 MWt (fuel input), variable configuration test facility in France.

  1. 7 CFR 330.206 - Permits for plant pest movement associated with National Defense projects.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... (Continued) ANIMAL AND PLANT HEALTH INSPECTION SERVICE, DEPARTMENT OF AGRICULTURE FEDERAL PLANT PEST REGULATIONS; GENERAL; PLANT PESTS; SOIL, STONE, AND QUARRY PRODUCTS; GARBAGE Movement of Plant Pests § 330.206... 7 Agriculture 5 2012-01-01 2012-01-01 false Permits for plant pest movement associated...

  2. 7 CFR 330.206 - Permits for plant pest movement associated with National Defense projects.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... (Continued) ANIMAL AND PLANT HEALTH INSPECTION SERVICE, DEPARTMENT OF AGRICULTURE FEDERAL PLANT PEST REGULATIONS; GENERAL; PLANT PESTS; SOIL, STONE, AND QUARRY PRODUCTS; GARBAGE Movement of Plant Pests § 330.206... 7 Agriculture 5 2013-01-01 2013-01-01 false Permits for plant pest movement associated...

  3. 7 CFR 330.206 - Permits for plant pest movement associated with National Defense projects.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... (Continued) ANIMAL AND PLANT HEALTH INSPECTION SERVICE, DEPARTMENT OF AGRICULTURE FEDERAL PLANT PEST REGULATIONS; GENERAL; PLANT PESTS; SOIL, STONE, AND QUARRY PRODUCTS; GARBAGE Movement of Plant Pests § 330.206... 7 Agriculture 5 2014-01-01 2014-01-01 false Permits for plant pest movement associated...

  4. An assessment of plant biointrusion at the Uranium Mill Tailings Remedial Action Project rock-covered disposal cells

    SciTech Connect

    Not Available

    1990-10-01

    This study is one of a number of special studies that have been conducted regarding various aspects of the Uranium Mill Tailings Remedial Action (UMTRA) Project. This special study was proposed following routine surveillance and maintenance surveys and observations reported in a special study of vegetative covers (DOE, 1988), in which plants were observed growing up through the rock erosion layer at recently completed disposal cells. Some of the plants observed were deep-rooted woody species, and questions concerning root intrusion into disposal cells and the need to control plant growth were raised. The special study discussed in this report was designed to address some of the ramifications of plant growth on disposal cells that have rock covers. The NRC has chosen rock covers over vegetative covers in the arid western United States because licenses cannot substantiate that the vegetative covers will be significantly greater than 30 percent and preferably 70 percent,'' which is the amount of vegetation required to reduce flow to a point of stability.'' The potential impacts of vegetation growing in rock covers are not addressed by the NRC (1990). The objectives, then, of this study were to determine the species of plants growing on two rock-covered disposal cells, study the rooting pattern of plants on these cells, and identify possible impacts of plant root penetration on these and other UMTRA Project rock-covered cells.

  5. 76 FR 6812 - Proposed Shiloh III Wind Plant Project, Solano County, CA; Proposed Habitat Conservation Plan and...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-02-08

    ... Fish and Wildlife Service Proposed Shiloh III Wind Plant Project, Solano County, CA; Proposed Habitat... Area). The Plan Area is adjacent to existing energy-producing facilities, most notably wind turbine.../California Independent System Operator power grid. Up to 59 wind turbines would be built in the Plan...

  6. Hanford Waste Simulants Created to Support the Research and Development on the River Protection Project - Waste Treatment Plant

    SciTech Connect

    Eibling, R.E.

    2001-07-26

    The development of nonradioactive waste simulants to support the River Protection Project - Waste Treatment Plant bench and pilot-scale testing is crucial to the design of the facility. The report documents the simulants development to support the SRTC programs and the strategies used to produce the simulants.

  7. The Florida citrus soil water atmosphere plant (SWAP) project: final summary of cumulative yields and tree health

    Technology Transfer Automated Retrieval System (TEKTRAN)

    The Florida Citrus Soil Water Atmosphere Plant (SWAP) Project at the Fort Pierce had three blocks each of soil tillage treatments of shallow tilled (ST), deep tilled (DT), and deep tilled plus lime (DTL) on a Spodosol (Oldsmar fine sandy loam). Each block had three adjacent submerged subsurface pla...

  8. The Florida citrus soil water atmosphere plant (SWAP) project: review and final summary of yields and tree health

    Technology Transfer Automated Retrieval System (TEKTRAN)

    The Florida Citrus Soil Water Atmosphere Plant (SWAP) Project at the UF-IFAS Indian River Research and Education Center had three blocks each of soil tillage (mixing ) treatments of shallow tilled (ST), deep tilled (DT), and deep tilled plus lime (DTL) on a Spodosol (Oldsmar fine sandy loam). Each ...

  9. A Largely Unsatisfied Need: Continuing Professional Development for Process and Process Plant Industries. A Summary. FEU/PICKUP Project Report.

    ERIC Educational Resources Information Center

    Geldhart, D.; Brown, A. S.

    This summary report outlines the aims of a project that focused on provision of short courses for technical professionals in the chemical and allied process industry and the process plant industry. Continuing education needs of both companies and individuals, as well as corporate policies and attitudes toward continuing education and constraints…

  10. Outfall 51 air stripping feasibility study for the Reduction of Mercury in Plant Effluent (RMPE) Project. Revision 1

    SciTech Connect

    1997-01-01

    Within the US Department of Energy`s Oak Ridge Y-12 Plant there are a number of industrial wastewater discharge points or outfalls that empty into East Fork Poplar Creek (EFPC). EFPC originates within and runs continuously throughout the plant site and subsequently flows out the east end of the Y-12 Plant into the City of Oak Ridge. Mercury is present in outfall discharges due to contact of water with the soils surrounding past mercury-use buildings. As a result, the Reduction of Mercury in Plant Effluent (RMPE) Project was developed to achieve and maintain environmental compliance with regards to mercury, and, in particular with the National Pollutant Discharge Elimination System permit for the Y-12 Plant. To achieve a reduction in mercury loading to EFPC, a number of options have already been studied and implemented as part of the RMPE project. With the successful implementation of these options, Outfall 51 remains as a significant contributor to mercury load to EFPC. The primary purpose of this project is to determine the feasibility of removing mercury from contaminated spring water using air stripping. In order to accomplish this goal, a number of different areas were addressed. A pilot-scale unit was tested in the field using actual mercury-contaminated source water. Properties which impact the mercury removal via air stripping were reviewed to determine their effect. Also, enhanced testing was performed to improve removal efficiencies. Finally, the variable outfall flow was studied to size appropriate processing equipment for full-scale treatment.

  11. Baseline survey for rare plant species and native plant communities within the Kamehameha Schools 'Lupea Safe Harbor Planning Project Area, North Kona District, Island of Hawai'i

    USGS Publications Warehouse

    Jacobi, James; F. R. Warshauer, frwvolcano@hotmail.com; Jonathan Price, jpprice@hawaii.edu

    2010-01-01

    Non-zero baseline values are proposed for the one listed plant species found within the Lupea Project area, one species that is a candidate for listing, and the four other rare species we found that may be considered for listing in the future. Additionally, a zero baseline is proposed for 23 other species that were predicted, but not found within the project area. These include 14 Endangered species, one Threatened species, two candidates for listing, and six species of concern. Subsequent monitoring of the site will be necessary to determine if the populations of these species have increased or decreased relative to their baseline values. It is presumed that the management activities Kamehameha Schools has proposed for this area, particularly removal of the ungulates and weed control, will provide a benefit to the habitat as a whole and allow for natural regeneration and maintenance of the all elements of the plant communities found there.

  12. Impacts of oil sands process water on fen plants: implications for plant selection in required reclamation projects.

    PubMed

    Pouliot, Rémy; Rochefort, Line; Graf, Martha D

    2012-08-01

    Fen plant growth in peat contaminated with groundwater discharges of oil sands process water (OSPW) was assessed in a greenhouse over two growing seasons. Three treatments (non-diluted OSPW, diluted OSPW and rainwater) were tested on five vascular plants and four mosses. All vascular plants tested can grow in salinity and naphthenic acids levels currently produced by oil sands activity in northwestern Canada. No stress sign was observed after both seasons. Because of plant characteristics, Carex species (C. atherodes and C. utriculata) and Triglochin maritima would be more useful for rapidly restoring vegetation and creating a new peat-accumulating system. Groundwater discharge of OSPW proved detrimental to mosses under dry conditions and ensuring adequate water levels would be crucial in fen creation following oil sands exploitation. Campylium stellatum would be the best choice to grow in contaminated areas and Bryum pseudotriquetrum might be interesting as it has spontaneously regenerated in all treatments.

  13. TVA coal-gasification commercial demonstration plant project. Volume 5. Plant based on Koppers-Totzek gasifier. Final report

    SciTech Connect

    Not Available

    1980-11-01

    This volume presents a technical description of a coal gasification plant, based on Koppers-Totzek gasifiers, producing a medium Btu fuel gas product. Foster Wheeler carried out a conceptual design and cost estimate of a nominal 20,000 TPSD plant based on TVA design criteria and information supplied by Krupp-Koppers concerning the Koppers-Totzek coal gasification process. Technical description of the design is given in this volume.

  14. Guide for prioritizing power plant productivity improvement projects: modification and simplification of the DOE/MRI methodology

    SciTech Connect

    Not Available

    1981-03-01

    In recent years, the subject of public utility power plant productivity and reliability has received significant attention from both federal and state agencies and from within the utilities. One study was a FEA-sponsored program that had as its purpose the development of improved techniques for assessing cause of power plant unavailability. The results of this study have become widely known as the DOE/MRI methodology for calculating increased power plant equivalent availability resulting from instituting improvement projects. To further the development of the DOE/MRI methodology for assessing and quantifying the effect of improvement projects, the DOE initiated studies with two states to demonstrate the methodology in operating plants. These studies were focused on applying the methodology to specific power plants (fossil-fueled and nuclear) and on identifying any difficulties in using the method. In the course of these investigations, several problems were uncovered. Various recommendations were made for both eliminating the identified deficiencies in the methodology and for simplifying several of the calculations needed to evaluate proposed plant improvements. The information provided here describes four major modifications to the DOE/MRI methodology which eliminate previously uncovered deficiencies and simplify calculational methods.

  15. Deployment of a Prototype Plant GFP Imager at the Arthur Clarke Mars Greenhouse of the Haughton Mars Project

    PubMed Central

    Paul, Anna-Lisa; Bamsey, Matthew; Berinstain, Alain; Braham, Stephen; Neron, Philip; Murdoch, Trevor; Graham, Thomas; Ferl, Robert J.

    2008-01-01

    The use of engineered plants as biosensors has made elegant strides in the past decades, providing keen insights into the health of plants in general and particularly in the nature and cellular location of stress responses. However, most of the analytical procedures involve laboratory examination of the biosensor plants. With the advent of the green fluorescence protein (GFP) as a biosensor molecule, it became at least theoretically possible for analyses of gene expression to occur telemetrically, with the gene expression information of the plant delivered to the investigator over large distances simply as properly processed fluorescence images. Spaceflight and other extraterrestrial environments provide unique challenges to plant life, challenges that often require changes at the gene expression level to accommodate adaptation and survival. Having previously deployed transgenic plant biosensors to evaluate responses to orbital spaceflight, we wished to develop the plants and especially the imaging devices required to conduct such experiments robotically, without operator intervention, within extraterrestrial environments. This requires the development of an autonomous and remotely operated plant GFP imaging system and concomitant development of the communications infrastructure to manage dataflow from the imaging device. Here we report the results of deploying a prototype GFP imaging system within the Arthur Clarke Mars Greenhouse (ACMG) an autonomously operated greenhouse located within the Haughton Mars Project in the Canadian High Arctic. Results both demonstrate the applicability of the fundamental GFP biosensor technology and highlight the difficulties in collecting and managing telemetric data from challenging deployment environments.

  16. Chiyoda Thoroughbred CT-121 clean coal project at Georgia Power`s Plant Yates

    SciTech Connect

    Burford, D.P.

    1997-12-31

    The Chiyoda Thoroughbred CT-121 flue gas desulfurization (FGD) process at Georgia Power`s Plant Yates completed a two year demonstration of its capabilities in late 1994 under both high- and low-particulate loading conditions. This $43 million demonstration was co-funded by Southern Company, the Electric Power Research Institute and the DOE under the auspices of the US Department of Energy`s Round II Innovative Clean Coal Technology (ICCT) program. The focus of the Yates Project was to demonstrate several cost-saving modifications to Chiyoda`s already efficient CT-121 process. These modifications included: the extensive use of fiberglass reinforced plastics (FRP) in the construction of the scrubber vessel and other associated vessels, the elimination of flue gas reheat through the use of an FRP wet chimney, and reliable operation without a spare absorber module. This paper focuses on the testing results from the last trimester of the second phase of testing (high-ash loading). Specifically, operation under elevated ash loading conditions, the effects of low- and high-sulfur coal, air toxics verification testing results and unexpected improvements in byproduct gypsum quality are discussed.

  17. Paducah Gaseous Diffusion Plant proposed pilot pump-and-treat project. Final report

    SciTech Connect

    Bodenstein, G.W.; Bonczek, R.R.; Early, T.O.; Huff, D.D.; Jones, K.S.; Nickelson, M.D.; Rightmire, C.T.

    1994-01-01

    On March 23, 1992, R.C. Sleeman of the Department of Energy, Oak Ridge Operations Office requested that a Groundwater Corrective Actions Team be assembled to evaluate the technical merit of and the need to implement a proposed groundwater pump-and-treat demonstration project for the Northwest contaminant plume at the Paducah Gaseous Diffusion Plant. In addition to other suggestions, the Team recommended that further characterization data be obtained for the plume. In the Fall of 1993 additional, temporary well points were installed so that groundwater samples from the shallow groundwater system and the Regional Gravel Aquifer (RGA) could be obtained to provide a three-dimensional view of groundwater contamination in the region of the plume. The results indicate that pure-phase DNAPL (trichloroethylene [TCE]) probably are present in the source area of the plume and extend in depth to the base of the RGA. Because the DNAPL likely will represent a source of a dissolved phase plume for decades it is essential that source containment take place. The Team recommends that although effective hydraulic containment can be achieved, other alternatives should be considered. For example, recent advances in emplacing low permeability barrier walls to depths of 100 to 150 ft make it possible to consider encirclement of the source of the Northwest plume.

  18. Considerations Associated with Reactor Technology Selection for the Next Generation Nuclear Plant Project

    SciTech Connect

    L.E. Demick

    2010-09-01

    At the inception of the Next Generation Nuclear Plant Project and during predecessor activities, alternative reactor technologies have been evaluated to determine the technology that best fulfills the functional and performance requirements of the targeted energy applications and market. Unlike the case of electric power generation where the reactor performance is primarily expressed in terms of economics, the targeted energy applications involve industrial applications that have specific needs in terms of acceptable heat transport fluids and the associated thermodynamic conditions. Hence, to be of interest to these industrial energy applications, the alternative reactor technologies are weighed in terms of the reactor coolant/heat transport fluid, achievable reactor outlet temperature, and practicality of operations to achieve the very high reliability demands associated with the petrochemical, petroleum, metals and related industries. These evaluations have concluded that the high temperature gas-cooled reactor (HTGR) can uniquely provide the required ranges of energy needs for these target applications, do so with promising economics, and can be commercialized with reasonable development risk in the time frames of current industry interest – i.e., within the next 10-15 years.

  19. Using an Ongoing Study of Terrestrial Plant Response to Ultraviolet Radiation in Project ALERT

    NASA Technical Reports Server (NTRS)

    Condon, Estelle; Skiles, J. W.; Seitz, Jeffery C.; Dantoni, Hector L.

    1998-01-01

    The ALERT (Augmented Learning Environment for Renewable Teaching) Project is a cooperative California-based program with two main partners: California State University (CSU) geoscience and education departments and two NASA Centers, the Jet Propulsion Laboratory (JPL) in Pasadena and the Ames Research Center (ARC) in Mountain View. This paper presents an example of how a NASA research effort can be used in the undergraduate classroom. A study, now in the fourth year, subjects test plants to exposures of varying solar ultraviolet (UV) radiation (280 - 340 nm); a full solar UV exposure, a solar UV exposure less about 14% of ambient UV flux, and a UV-blocked regime. This experiment is simple in that only modest amounts of expense are required yet it is elegant since only one variable, UV-flux is involved. The experiment lends itself to teaching several of the Earth Sciences because it uses information from botany, taxonomy, and ecology. Aspects of physics are inherent in the study since portions of the electromagnetic spectrum are studied. Further, since only one of many variables are manipulated, UV flux, the study demonstrates how the scientific method is used in formulating and testing hypotheses. Based on the ALERT experience this summer, this study will be implemented at a CSU campus with the expectation that it will serve as a pedagogical tool and where it will involve students in actual research.

  20. Increasing the Safety in Recycling of Construction and Demolition Waste by Using Supervised Machine Learning

    NASA Astrophysics Data System (ADS)

    Kuritcyn, P.; Anding, K.; Linß, E.; Latyev, S. M.

    2015-02-01

    This paper discusses the possibility of the optical identification of recycled aggregates of construction and demolition waste (CDW) using methods of image processing, spectral analysis and machine learning. The classification performances in colour images shown, that we have to use other added spectral information to solve the recognition task in a satisfactory manner. In addition to investigations on a large colour image dataset first investigations in visible (VIS) and infrared (IR) spectrum were done for analysing significant characteristics in spectrum, which are useful for classification the C&D aggregates.

  1. 78 FR 2616 - Safety Zone; Bridge Demolition Project; Indiana Harbor Canal, East Chicago, IN

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-01-14

    .... SUPPLEMENTARY INFORMATION: Table of Acronyms DHS Department of Homeland Security FR Federal Register NPRM Notice... Canal, East Chicago, IN AGENCY: Coast Guard, DHS. ACTION: Temporary final rule. SUMMARY: The Coast Guard is establishing a temporary safety zone on the Indiana Harbor Canal in East Chicago, Indiana....

  2. 77 FR 72957 - Safety Zone; Bridge Demolition Project; Indiana Harbor Canal, East Chicago, IN

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-12-07

    ... Department of Homeland Security FR Federal Register NPRM Notice of Proposed Rulemaking A. Regulatory History... Canal, East Chicago, IN AGENCY: Coast Guard, DHS. ACTION: Temporary final rule. SUMMARY: The Coast Guard is establishing a temporary safety zone on the Indiana Harbor Canal in East Chicago, Indiana....

  3. 77 FR 70684 - Safety Zone; Bridge Demolition Project; Indiana Harbor Canal, East Chicago, IN

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-11-27

    .... SUPPLEMENTARY INFORMATION: Table of Acronyms DHS Department of Homeland Security FR Federal Register NPRM Notice... Canal, East Chicago, IN AGENCY: Coast Guard, DHS. ACTION: Temporary final rule. SUMMARY: The Coast Guard is establishing a temporary safety zone on the Indiana Harbor Canal in East Chicago, Indiana....

  4. 77 FR 65818 - Safety Zone; Bridge Demolition Project; Indiana Harbor Canal, East Chicago, IN

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-10-31

    ... Security FR Federal Register NPRM Notice of Proposed Rulemaking ] A. Regulatory History and Information The... Canal, East Chicago, IN AGENCY: Coast Guard, DHS. ACTION: Temporary final rule. SUMMARY: The Coast Guard is establishing a temporary safety zone on the Indiana Harbor Canal in East Chicago, Indiana....

  5. 77 FR 63732 - Safety Zone; Bridge Demolition Project; Indiana Harbor Canal, East Chicago, IN

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-10-17

    .... SUPPLEMENTARY INFORMATION: Table of Acronyms DHS Department of Homeland Security FR Federal Register NPRM Notice... Canal, East Chicago, IN AGENCY: Coast Guard, DHS. ACTION: Temporary final rule. SUMMARY: The Coast Guard is establishing a temporary safety zone on the Indiana Harbor Canal in East Chicago, Indiana....

  6. Model based prognosis of contaminant leaching for reuse of demolition waste in construction projects

    NASA Astrophysics Data System (ADS)

    Beyer, C.; Konrad, W.; C. H., Park; Bauer, S.; Grathwohl, P.; Rügner, H.; Liedl, R.

    2007-06-01

    In this study, groundwater contamination from recycled demolitian waste in road constructions is assessed using predictions of leachate concentrations. Numerical transport simulations are performed for three scenarios (a parking lot, a noise protection barrier, and road), and using a number of characteristic subsoils of Germany, to estimate the breakthrough of different contaminant classes at the groundwater table. Conservative tracer breakthrough times (BTT) primarily depend on subsoil hydraulic properties, for organic pollutants KOC and subsoil OC are the controlling parameters. Significant concentration reductions from dispersion only occur when source concentrations decrease prior to contaminant breakthrough. If source concentrations remain high for long periods relative to peak BTT, concentration breakthrough is undamped. Accounting for biodegradation reduces breakthrough concentrations significantly. For the “noise protection barrier” and “road” scenarios, capillary barrier effects cause the seepage water to partially bypass the recycling material. Accounting for this bypass flow and spatial averaging across the constructions reduces concentrations by about 30-40 %.

  7. Monticello Unit 3 recovery project: The rebuild of a first generation wet flue gas desulfurization system

    SciTech Connect

    Guletsky, P.W.; Katzberger, S.M.; Jeanes, R.L.

    1995-06-01

    Since November 1993, TU Electric and Sargent & Lundy have been engaged in the repair or replacement of equipment that was damaged by the collapse of the Monticello Unit 3 chimney. In addition to the replacement of the chimney, electrostatic precipitator, and various balance-of-plant systems, the scope of the project includes the demolition, engineering and design, procurement, and construction activities to rebuild major equipment within the wet limestone flue gas desulfurization (FGD) system. This paper reviews and discusses various aspects of the design, procurement and schedule associated with the rebuild of the FGD system. The paper reviews the design selections in the areas of process technology, the absorber island, and technical enhancements to improve the operability of this 1970s-vintage system. Finally, the challenges and solutions in implementing a 17-month schedule for the design, construction, and startup of an FGD system will be discussed.

  8. Mass, energy and material balances of SRF production process. Part 2: SRF produced from construction and demolition waste.

    PubMed

    Nasrullah, Muhammad; Vainikka, Pasi; Hannula, Janne; Hurme, Markku; Kärki, Janne

    2014-11-01

    In this work, the fraction of construction and demolition waste (C&D waste) complicated and economically not feasible to sort out for recycling purposes is used to produce solid recovered fuel (SRF) through mechanical treatment (MT). The paper presents the mass, energy and material balances of this SRF production process. All the process streams (input and output) produced in MT waste sorting plant to produce SRF from C&D waste are sampled and treated according to CEN standard methods for SRF. Proximate and ultimate analysis of these streams is performed and their composition is determined. Based on this analysis and composition of process streams their mass, energy and material balances are established for SRF production process. By mass balance means the overall mass flow of input waste material stream in the various output streams and material balances mean the mass flow of components of input waste material stream (such as paper and cardboard, wood, plastic (soft), plastic (hard), textile and rubber) in the various output streams of SRF production process. The results from mass balance of SRF production process showed that of the total input C&D waste material to MT waste sorting plant, 44% was recovered in the form of SRF, 5% as ferrous metal, 1% as non-ferrous metal, and 28% was sorted out as fine fraction, 18% as reject material and 4% as heavy fraction. The energy balance of this SRF production process showed that of the total input energy content of C&D waste material to MT waste sorting plant, 74% was recovered in the form of SRF, 16% belonged to the reject material and rest 10% belonged to the streams of fine fraction and heavy fraction. From the material balances of this process, mass fractions of plastic (soft), paper and cardboard, wood and plastic (hard) recovered in the SRF stream were 84%, 82%, 72% and 68% respectively of their input masses to MT plant. A high mass fraction of plastic (PVC) and rubber material was found in the reject material

  9. Mass, energy and material balances of SRF production process. Part 2: SRF produced from construction and demolition waste.

    PubMed

    Nasrullah, Muhammad; Vainikka, Pasi; Hannula, Janne; Hurme, Markku; Kärki, Janne

    2014-11-01

    In this work, the fraction of construction and demolition waste (C&D waste) complicated and economically not feasible to sort out for recycling purposes is used to produce solid recovered fuel (SRF) through mechanical treatment (MT). The paper presents the mass, energy and material balances of this SRF production process. All the process streams (input and output) produced in MT waste sorting plant to produce SRF from C&D waste are sampled and treated according to CEN standard methods for SRF. Proximate and ultimate analysis of these streams is performed and their composition is determined. Based on this analysis and composition of process streams their mass, energy and material balances are established for SRF production process. By mass balance means the overall mass flow of input waste material stream in the various output streams and material balances mean the mass flow of components of input waste material stream (such as paper and cardboard, wood, plastic (soft), plastic (hard), textile and rubber) in the various output streams of SRF production process. The results from mass balance of SRF production process showed that of the total input C&D waste material to MT waste sorting plant, 44% was recovered in the form of SRF, 5% as ferrous metal, 1% as non-ferrous metal, and 28% was sorted out as fine fraction, 18% as reject material and 4% as heavy fraction. The energy balance of this SRF production process showed that of the total input energy content of C&D waste material to MT waste sorting plant, 74% was recovered in the form of SRF, 16% belonged to the reject material and rest 10% belonged to the streams of fine fraction and heavy fraction. From the material balances of this process, mass fractions of plastic (soft), paper and cardboard, wood and plastic (hard) recovered in the SRF stream were 84%, 82%, 72% and 68% respectively of their input masses to MT plant. A high mass fraction of plastic (PVC) and rubber material was found in the reject material

  10. Depressive symptoms among Arab Bedouin women whose houses are under threat of demolition in southern Israel: a right to housing issue.

    PubMed

    Daoud, Nihaya; Jabareen, Yousef

    2014-06-14

    Housing is a fundamental human right and a social determinant of health. According to international law, indigenous peoples are entitled to special housing and health rights and protections. In Israel, land disputes between the government and Arab Bedouins, an indigenous minority, have resulted in ongoing demolitions of Arab Bedouin homes, with thousands more homes threatened. While demolitions could expose this population to mental health problems, research linking house demolition and health is scarce. In this paper, we draw on a human rights perspective to describe this housing instability and examine the association between the threat of house demolition and depressive symptoms (DS) among 464 Arab Bedouin women. We conclude that having their house under threat of demolition is an important determinant of poor mental health among Bedouin women. Any efforts to decrease DS among these women will have to take place alongside efforts to stop this practice.

  11. Cost-benefit analysis of water-reuse projects for environmental purposes: a case study for Spanish wastewater treatment plants.

    PubMed

    Molinos-Senante, M; Hernández-Sancho, F; Sala-Garrido, R

    2011-12-01

    Water reuse is an emerging and promising non-conventional water resource. Feasibility studies are essential tools in the decision making process for the implementation of water-reuse projects. However, the methods used to assess economic feasibility tend to focus on internal costs, while external impacts are relegated to unsubstantiated statements about the advantages of water reuse. Using the concept of shadow prices for undesirable outputs of water reclamation, the current study developed a theoretical methodology to assess internal and external economic impacts. The proposed methodological approach is applied to 13 wastewater treatment plants in the Valencia region of Spain that reuse effluent for environmental purposes. Internal benefit analyses indicated that only a proportion of projects were economically viable, while when external benefits are incorporated all projects were economically viable. In conclusion, the economic feasibility assessments of water-reuse projects should quantitatively evaluate economic, environmental and resource availability.

  12. A dynamic model for assessing the effects of management strategies on the reduction of construction and demolition waste

    SciTech Connect

    Yuan Hongping; Chini, Abdol R.; Lu Yujie; Shen Liyin

    2012-03-15

    Highlights: Black-Right-Pointing-Pointer We proposes a model for projecting C and D waste reduction of construction projects. Black-Right-Pointing-Pointer The model can simulate effects of various management strategies on waste reduction. Black-Right-Pointing-Pointer The model integrates all essential variables that affect C and D waste reduction. Black-Right-Pointing-Pointer By using the model, best strategies could be identified before being implemented. - Abstract: During the past few decades, construction and demolition (C and D) waste has received increasing attention from construction practitioners and researchers worldwide. A plethora of research regarding C and D waste management has been published in various academic journals. However, it has been determined that existing studies with respect to C and D waste reduction are mainly carried out from a static perspective, without considering the dynamic and interdependent nature of the whole waste reduction system. This might lead to misunderstanding about the actual effect of implementing any waste reduction strategies. Therefore, this research proposes a model that can serve as a decision support tool for projecting C and D waste reduction in line with the waste management situation of a given construction project, and more importantly, as a platform for simulating effects of various management strategies on C and D waste reduction. The research is conducted using system dynamics methodology, which is a systematic approach that deals with the complexity - interrelationships and dynamics - of any social, economic and managerial system. The dynamic model integrates major variables that affect C and D waste reduction. In this paper, seven causal loop diagrams that can deepen understanding about the feedback relationships underlying C and D waste reduction system are firstly presented. Then a stock-flow diagram is formulated by using software for system dynamics modeling. Finally, a case study is used to

  13. Experience in Remote Demolition of the Activated Biological Shielding of the Multi Purpose Research Reactor (MZFR) on the German Karlsruhe Site - 12208

    SciTech Connect

    Eisenmann, Beata; Fleisch, Joachim; Prechtl, Erwin; Suessdorf, Werner; Urban, Manfred

    2012-07-01

    In 2009, WAK Decommissioning and Waste Management GmbH (WAK) became owner and operator of the waste treatment facilities of Karlsruhe Institute of Technology (KIT) as well as of the prototype reactors, the Compact Sodium-Cooled Fast Reactor (KNK) and Multi-Purpose Reactor (MZFR), both being in an advanced stage of dismantling. Together with the dismantling and decontamination activities of the former WAK reprocessing facility since 1990, the envisaged demolishing of the R and D reactor FR2 and a hot cell facility, all governmentally funded nuclear decommissioning projects on the Karlsruhe site are concentrated under the WAK management. The small space typical of prototype research reactors represented a challenge also during the last phase of activated dismantling, dismantling of the activated biological shield of the MZFR. Successful demolition of the biological shield required detailed planning and extensive testing in the years before. In view of the limited space and the ambient dose rate that was too high for manual work, it was required to find a tool carrier system to take up and control various demolition and dismantling tools in a remote manner. The strategy formulated in the concept of dismantling the biological shield by means of a modified electro-hydraulic demolition excavator in an adaptable working scaffolding turned out to be feasible. The following boundary conditions were essential: - Remote exchange of the dismantling and removal tools in smallest space. - Positioning of various supply facilities on the working platform. - Avoiding of interfering edges. - Optimization of mass flow (removal of the dismantled mass from the working area). - Maintenance in the surroundings of the dismantling area (in the controlled area). - Testing and qualification of the facilities and training of the staff. Both the dismantling technique chosen and the proceeding selected proved to be successful. Using various designs of universal cutters developed on the basis of

  14. Mitigation of Hexavalent Chromium in Storm Water Resulting from Demolition of Large Concrete Structure at the East Tennessee Technology Park - 12286

    SciTech Connect

    Britto, Ronnie; Brown, Bridget; Hale, Timothy B.; Hensley, Janice L.; Johnson, Robert T.; Patel, Madhu; Emery, Jerry A.; Gaston, Clyde; Queen, David C.

    2012-07-01

    American Recovery and Reinvestment Act (ARRA) funding was provided to supplement the environmental management program at several DOE sites, including the East Tennessee Technology Park (ETTP) in Oak Ridge, Tennessee. Demolition of the ETTP K-33 Building, the largest building to be demolished to date in Oak Ridge, was awarded to LSRS in FY-2010 under the ARRA program. The K-33 building was an 82 foot tall 2-story structure covering approximately 32 acres. Once this massive building was brought down to the ground, the debris was segregated and consolidated into piles of concrete rubble and steel across the remaining pad. The process of demolishing the building, tracking across concrete debris with heavy equipment, and stockpiling the concrete rubble caused it to become pulverized. During and after storm events, hexavalent chromium leached from the residual cement present in the large quantities of concrete. Storm water control measures were present to preclude migration of contaminants off-site, but these control measures were not designed to control hexavalent chromium dissolved in storm water from reaching nearby receiving water. The following was implemented to mitigate hexavalent chromium in storm water: - Steel wool was distributed around K-33 site catch basins and in water pools as an initial step in addressing hexavalent chromium. - Since the piles of concrete were too massive and unsafe to tarp, they were placed into windrows in an effort to reduce total surface area. - A Hach colorimetric field meter was acquired by the K-33 project to provide realtime results of hexavalent chromium in site surface water. - Three hexavalent chromium treatment systems were installed at three separate catch basins that receive integrated storm water flow from the K-33 site. Sodium bisulfite is being used as a reducing agent for the immobilization of hexavalent chromium while also assisting in lowering pH. Concentrations initially were 310 - 474 ppb of hexavalent chromium in

  15. Project Management Plan for the Idaho National Engineering Laboratory Waste Isolation Pilot Plant Experimental Test Program

    SciTech Connect

    Connolly, M.J.; Sayer, D.L.

    1993-11-01

    EG&G Idaho, Inc. and Argonne National Laboratory-West (ANL-W) are participating in the Idaho National Engineering Laboratory`s (INEL`s) Waste Isolation Pilot Plant (WIPP) Experimental Test Program (WETP). The purpose of the INEL WET is to provide chemical, physical, and radiochemical data on transuranic (TRU) waste to be stored at WIPP. The waste characterization data collected will be used to support the WIPP Performance Assessment (PA), development of the disposal No-Migration Variance Petition (NMVP), and to support the WIPP disposal decision. The PA is an analysis required by the Code of Federal Regulations (CFR), Title 40, Part 191 (40 CFR 191), which identifies the processes and events that may affect the disposal system (WIPP) and examines the effects of those processes and events on the performance of WIPP. A NMVP is required for the WIPP by 40 CFR 268 in order to dispose of land disposal restriction (LDR) mixed TRU waste in WIPP. It is anticipated that the detailed Resource Conservation and Recovery Act (RCRA) waste characterization data of all INEL retrievably-stored TRU waste to be stored in WIPP will be required for the NMVP. Waste characterization requirements for PA and RCRA may not necessarily be identical. Waste characterization requirements for the PA will be defined by Sandia National Laboratories. The requirements for RCRA are defined in 40 CFR 268, WIPP RCRA Part B Application Waste Analysis Plan (WAP), and WIPP Waste Characterization Program Plan (WWCP). This Project Management Plan (PMP) addresses only the characterization of the contact handled (CH) TRU waste at the INEL. This document will address all work in which EG&G Idaho is responsible concerning the INEL WETP. Even though EG&G Idaho has no responsibility for the work that ANL-W is performing, EG&G Idaho will keep a current status and provide a project coordination effort with ANL-W to ensure that the INEL, as a whole, is effectively and efficiently completing the requirements for WETP.

  16. Development of metal recycling process from decommissioned nuclear power plants

    SciTech Connect

    Ishikura, T.; Abe, S.; Sakai, H.; Takahashi, J.

    1999-07-01

    Dismantling and demolition of a nuclear power plant generates a large amount of metal waste. Recycling of such waste for resource is important because of the limited capacity of the disposal site. Authors have developed metal recycling processes. It is found that pyrometallurgical separation techniques can effectively separate nickel and cobalt, which contain main contributors of radioactivity, from iron and chromium.

  17. Otec power plant for the Marshall Islands. Feasibility study phase 2. Project implementation. Final report. Export trade information

    SciTech Connect

    1996-03-25

    This report presents the results of phase 2 of a study which was conducted to assess the economic and design feasibility of a 5-10 MW OTEC power plant to be installed at Majuro, Marshall Islands. The document is divided into (1) Introduction; (2) Executive Summary; (3) Study Highlights, Conclusions, and Recommendations; (4) Phase 2 - Project Implementation Goals; (5) Study Task 1.0 - Project Planning; (6) Study Task 2.0 - Conceptual Design/Risk Reduction; (7) Preliminary Oceanographic and Site Survey; (8) List of References; (9) List of Appendices.

  18. Saguaro Power Plant Solar Repowering Project. Volume II. System requirements specification. Final technical report, September 1979-July 1980

    SciTech Connect

    Weber, E.R.

    1980-07-01

    This specification defines the system and subsystem characteristics, design requirements, and system environmental requirements for the Saguaro Power Plant Solar Repowering Project. This project involves the solar repowering of all (120.2 MWe gross) of the 115 MWe net power No. One steam-Rankine unit of the Arizona Public Service Company's Saguaro station. The receiver heat transport fluid is draw salt (60% sodium nitrate and 40% potassium nitrate) that is also used to provide 3.8 hours of sensible heat thermal energy storage. The quad-cavity type receiver is mounted on a tower within a single surrounding collector field of 10,500 second generation heliostats.

  19. Thermal power systems small power systems application project: Siting issues for solar thermal power plants with small community applications

    NASA Technical Reports Server (NTRS)

    Holbeck, H. J.; Ireland, S. J.

    1979-01-01

    The siting issues associated with small, dispersed solar thermal power plants for utility/small community applications of less than 10 MWe are reported. Some specific requirements are refered to the first engineering experiment for the Small Power Systems Applications (SPSA) Project. The background for the subsequent issue discussions is provided. The SPSA Project and the requirements for the first engineering experiment are described, and the objectives and scope for the report as a whole. A overview of solar thermal technologies and some technology options are discussed.

  20. Feasibility study for La Paz Hydroelectric Power Plant Project. Export trade information

    SciTech Connect

    Not Available

    1991-12-01

    A feasibility study for a hydroelectric project is defined as an investigation whose purpose is to determine whether any reasonable acceptable design for a project is technically viable. Alternatives of site development are studied and various solutions for civil works and equipment sizing are evaluated. When alternatives are considered technically viable they are then evaluated for financial viability. The purpose of the study is to evaluate the viability of the La Paz Hydroelectric Project. The La Paz Feasibility Study discusses: Site Characteristics and Existing Facilities; Hydrology and Sedimentation; Alternatives and Development; Hydraulics; Project Energy Output; Environmental, Social and Institutional Impacts; Project Cost Analysis; Market Considerations; Economics; Financial Analysis; and Project Implementation.

  1. Stripping in hot mix asphalt produced by aggregates from construction and demolition waste.

    PubMed

    Pérez, I; Pasandín, A R; Gallego, J

    2012-01-01

    This paper analyses the effect of water on the durability of hot asphalt mixtures made with recycled aggregates from construction and demolition debris. Indirect tensile stress tests were carried out to evaluate stripping behaviour. The mixtures tested were fabricated with 0, 20, 40 and 60% recycled aggregates. Two types of natural aggregates were used: schist and calcite dolomite. An increase in the percentage of recycled aggregates was found to produce a decrease in the tensile stress ratio of the hot asphalt mixtures. To study this phenomenon, two and three factor analyses of variance (ANOVA) were performed with indirect tensile stress being used as the dependent variable. The factors studied were the percentage of recycled aggregates (0, 20, 40 and 60%), the moisture state (dry, wet) and the type of natural aggregate (schist, calcite). On the basis of the ANOVA results, it was found that the most important factor affecting resistance was the moisture state (dry, wet) of the specimens. The percentage of recycled aggregate also affected indirect tensile stress, especially in the dry state. The type of natural aggregate did not have a significant effect on indirect tensile stress. The hot asphalt mixture specimens made with different percentages of recycled aggregates from construction and demolition debris and of natural quarry aggregates showed poor stripping behaviour. This stripping behaviour can be related to both the poor adhesion of the recycled aggregates and the high absorption of the mortar of cement adhered to them. PMID:20627995

  2. Composition and leaching of construction and demolition waste: inorganic elements and organic compounds.

    PubMed

    Butera, Stefania; Christensen, Thomas H; Astrup, Thomas F

    2014-07-15

    Thirty-three samples of construction and demolition waste collected at 11 recycling facilities in Denmark were characterised in terms of total content and leaching of inorganic elements and presence of the persistent organic pollutants PCBs and PAHs. Samples included (i) "clean" (i.e. unmixed) concrete waste, (ii) mixed masonry and concrete, (iii) asphalt and (iv) freshly cast concrete cores; both old and newly generated construction and demolition waste was included. PCBs and PAHs were detected in all samples, generally in non-critical concentrations. Overall, PAHs were comparable to background levels in urban environments. "Old" and "new" concrete samples indicated different PCB congener profiles and the presence of PCB even in new concrete suggested that background levels in raw materials may be an issue. Significant variability in total content of trace elements, even more pronounced for leaching, was observed indicating that the number of analysed samples may be critical in relation to decisions regarding management and utilisation of the materials. Higher leaching of chromium, sulphate and chloride were observed for masonry-containing and partly carbonated samples, indicating that source segregation and management practices may be important. Generally, leaching was in compliance with available leaching limits, except for selenium, and in some cases chromium, sulphate and antimony. PMID:24910908

  3. Chemical sulphate removal for treatment of construction and demolition debris leachate.

    PubMed

    Kijjanapanich, Pimluck; Annachhatre, Ajit P; Esposito, Giovanni; Lens, Piet N L

    2014-08-01

    Construction and demolition debris (CDD) is a product of construction, renovation or demolition activities. It has a high gypsum content (52.4% of total gypsum), concentrated in the CDD sand (CDDS) fraction. To comply with the posed limit of the maximum amount of sulphate present in building sand, excess sulphate needs to be removed. In order to enable reuse of CDDS, a novel treatment process is developed based on washing of the CDDS to remove most of the gypsum, and subsequent sulphate removal from the sulphate-rich CDDS leachate. This study aims to assess chemical techniques, i.e. precipitation and adsorption, for sulphate removal from the CDDS leachate. Good sulphate removal efficiencies (up to 99.9%) from the CDDS leachate can be achieved by precipitation with barium chloride (BaCl2) and lead(II) nitrate (Pb(NO3)2). Precipitation with calcium chloride (CaCl2), calcium carbonate (CaCO3) and calcium oxide (CaO) gave less efficient sulphate removal. Adsorption of sulphate to aluminium oxide (Al2O3) yielded a 50% sulphate removal efficiency, whereas iron oxide-coated sand as adsorbent gave only poor (10%) sulphate removal efficiencies.

  4. Air quality during demolition and recovery activities in post-Katrina New Orleans.

    PubMed

    Ravikrishna, Raghunathan; Lee, Han-Woong; Mbuligwe, Stephen; Valsaraj, K T; Pardue, John H

    2010-07-01

    Air samples were collected during demolition and cleanup operations in the Lakeview district of New Orleans, Louisiana, USA, in late 2005 during the period immediately after Hurricane Katrina. Three different high-volume air samples were collected around waste collection areas that were created to temporarily hold the debris from the cleanup of residential properties in the area. Particulate concentrations were elevated and included crystalline fibers associated with asbestos. Metal concentrations on particulate matter resembled those measured in sediments deposited by floodwaters with the exception of Ba, which was elevated at all three locations. The highest organic contaminant concentration measured on particulates was the pesticide Ziram (Zinc, bis[diethylcarbamodithioato-S,S']-, [T-4]-) at 2,200 microg/g of particulate matter during sampling period 2. Ziram is used in latex paint, adhesives, caulking, and wallboard as a preservative. Fungal isolates developed from particulate air samples included species associated with disease including Aspergillus and Penicillium species. These data represent the most comprehensive assessment of demolition activities during the period immediately after Hurricane Katrina.

  5. Comparison of leaching tests to determine and quantify the release of inorganic contaminants in demolition waste.

    PubMed

    Delay, Markus; Lager, Tanja; Schulz, Horst D; Frimmel, Fritz H

    2007-01-01

    The changes in waste management policy caused by the massive generation of waste materials (e.g. construction and demolition waste material, municipal waste incineration products) has led to an increase in the reuse and recycling of waste materials. For environmental risk assessment, test procedures are necessary to examine waste materials before they can be reused. In this article, results of column and lysimeter leaching tests having been applied to inorganic compounds in a reference demolition waste material are presented. The results show a good agreement between the leaching behaviour determined with the lysimeter unit and the column units used in the laboratory. In view of less time and system requirements compared to lysimeter systems, laboratory column units can be considered as a practicable instrument to assess the time-dependent release of inorganic compounds under conditions similar to those encountered in a natural environment. The high concentrations of elements in the seepage water at the initial stage of elution are reflected by the laboratory column leaching tests. In particular, authorities or laboratories might benefit and have an easy-to-use, but nevertheless reliable, method to serve as a basis for decision-making.

  6. Stripping in hot mix asphalt produced by aggregates from construction and demolition waste.

    PubMed

    Pérez, I; Pasandín, A R; Gallego, J

    2012-01-01

    This paper analyses the effect of water on the durability of hot asphalt mixtures made with recycled aggregates from construction and demolition debris. Indirect tensile stress tests were carried out to evaluate stripping behaviour. The mixtures tested were fabricated with 0, 20, 40 and 60% recycled aggregates. Two types of natural aggregates were used: schist and calcite dolomite. An increase in the percentage of recycled aggregates was found to produce a decrease in the tensile stress ratio of the hot asphalt mixtures. To study this phenomenon, two and three factor analyses of variance (ANOVA) were performed with indirect tensile stress being used as the dependent variable. The factors studied were the percentage of recycled aggregates (0, 20, 40 and 60%), the moisture state (dry, wet) and the type of natural aggregate (schist, calcite). On the basis of the ANOVA results, it was found that the most important factor affecting resistance was the moisture state (dry, wet) of the specimens. The percentage of recycled aggregate also affected indirect tensile stress, especially in the dry state. The type of natural aggregate did not have a significant effect on indirect tensile stress. The hot asphalt mixture specimens made with different percentages of recycled aggregates from construction and demolition debris and of natural quarry aggregates showed poor stripping behaviour. This stripping behaviour can be related to both the poor adhesion of the recycled aggregates and the high absorption of the mortar of cement adhered to them.

  7. Estimating construction and demolition debris generation using a materials flow analysis approach.

    PubMed

    Cochran, K M; Townsend, T G

    2010-11-01

    The magnitude and composition of a region's construction and demolition (C&D) debris should be understood when developing rules, policies and strategies for managing this segment of the solid waste stream. In the US, several national estimates have been conducted using a weight-per-construction-area approximation; national estimates using alternative procedures such as those used for other segments of the solid waste stream have not been reported for C&D debris. This paper presents an evaluation of a materials flow analysis (MFA) approach for estimating C&D debris generation and composition for a large region (the US). The consumption of construction materials in the US and typical waste factors used for construction materials purchasing were used to estimate the mass of solid waste generated as a result of construction activities. Debris from demolition activities was predicted from various historical construction materials consumption data and estimates of average service lives of the materials. The MFA approach estimated that approximately 610-78 × 10(6)Mg of C&D debris was generated in 2002. This predicted mass exceeds previous estimates using other C&D debris predictive methodologies and reflects the large waste stream that exists.

  8. Atmospheric release advisory capability pilot project at two nuclear power plants and associated state offices of emergency preparedness. Final report

    SciTech Connect

    Rosen, L.C.

    1983-01-01

    A project to demonstrate the feasibility of utilizing Atmospheric Release Advisory Capability (ARAC) limited service with commercial nuclear power plants and their associated state offices of emergency preparedness is discussed. Preliminary planning, installation and testing of the ARAC site facilities at Indian Point Nucler Power Station, New York State; at New York State Office of Emergency Preparedness, Albany, New York; at Rancho Seco Nuclear Generating Station, California; and at the State of California Office of Emergency Services, Sacramento, California, are summarized. ARAC participation in the Robert E. Ginna nuclear generating plant accident in New York on January 25, 1982, is discussed. The ARAC system is evaluated with emphasis on communications, the suite of models contained within the ARAC system, and the staff. The implications of this project in designing the next-generation ARAC system to service federal and state needs are assessed.

  9. SOLERAS - Solar-Powered Water Desalination Project at Yanbu: Forecasting models for operating and maintenance cost of the pilot plant

    SciTech Connect

    Al-Idrisi, M.; Hamad, G.

    1987-04-01

    This study was conducted in cooperation with the Department of Industrial Engineering of King Abdulaziz University. The main objective of this study is to meet some of the goals of the Solar Energy Water Desalination Plant (SEWDP) plan in the area of economic evaluation. The first part of this project focused on describing the existing trend in the operation and maintenance (OandM) cost for the SOLERAS Solar Energy Water Desalination Plant in Yanbu. The second part used the information obtained on existing trends to find suitable forecasting models. These models, which are found here, are sensitive to changes in costs trends. Nevertheless, the study presented here has established the foundation for (OandM) costs estimating in the plant. The methodologies used in this study should continue as more data on operation and maintenance costs become available, because, in the long run, the trend in costs will help determine where cost effectiveness might be improved. 7 refs., 24 figs., 15 tabs.

  10. Comparison of the Alternative Asbestos Control Method and the NESHAP Method for Demolition of Asbestos-Containing Buildings

    EPA Science Inventory

    The Asbestos NESHAP (National Emission Standard for Hazardous Air Pollutants) requires the removal of all Regulated Asbestos-Containing Material (RACM) prior to the demolition of the buildings that fall under the auspices of the NESHAP. This removal process can be a costly and ti...

  11. 48 CFR 36.701 - Standard and optional forms for use in contracting for construction or dismantling, demolition...

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 48 Federal Acquisition Regulations System 1 2010-10-01 2010-10-01 false Standard and optional forms for use in contracting for construction or dismantling, demolition, or removal of improvements. 36.701 Section 36.701 Federal Acquisition Regulations System FEDERAL ACQUISITION REGULATION SPECIAL CATEGORIES OF CONTRACTING CONSTRUCTION AND...

  12. 48 CFR 52.249-3 - Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements).

    Code of Federal Regulations, 2011 CFR

    2011-10-01

    ... 48 Federal Acquisition Regulations System 2 2011-10-01 2011-10-01 false Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements). 52.249-3 Section 52.249-3 Federal Acquisition Regulations System FEDERAL ACQUISITION REGULATION (CONTINUED) CLAUSES AND FORMS SOLICITATION PROVISIONS AND CONTRACT CLAUSES...

  13. 41 CFR 102-75.170 - What happens to the related personal property in a structure scheduled for demolition?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... consideration should be given to designating items having possible historical or artistic value as personal... related personal property in a structure scheduled for demolition? 102-75.170 Section 102-75.170 Public... As Personal Property § 102-75.170 What happens to the related personal property in a...

  14. Methodology to Estimate the Quantity, Composition, and Management of Construction and Demolition Debris in the United States

    EPA Science Inventory

    This report, Methodology to Estimate the Quantity, Composition and Management of Construction and Demolition Debris in the US, was developed to expand access to data on CDD in the US and to support research on CDD and sustainable materials management. Since past US EPA CDD estima...

  15. An engineering assessment of the burning of the combustible fraction of construction and demolition wastes in a redundant brick kiln.

    PubMed

    Chang, N B; Lin, K S; Sun, Y P; Wang, H P

    2001-12-01

    This paper confirms both technical feasibility and economic potential via the use of redundant brick kilns as an alternative option for disposal of the combustible fractions of construction and demolition wastes by a three-stage analysis. To assess such an idea, one brick kiln was selected for performing an engineering feasibility study. First of all, field sampling and lab-analyses were carried out to gain a deeper understanding of the physical, chemical, and thermodynamic properties of the combustible fractions of construction and demolition wastes. Kinetic parameters for the oxidation of the combustible fractions of construction and demolition wastes were therefore numerically calculated from the weight loss data obtained through a practice of thermogravimetric analyzer (TGA). Secondly, an engineering assessment for retrofitting the redundant brick kiln was performed based on integrating several new and existing unit operations, consisting of waste storage, shredding, feeding, combustion, flue gas cleaning, and ash removal. Such changes were subject to the operational condition in accordance with the estimated mass and energy balances. Finally, addressing the economic value of energy recovery motivated a renewed interest to convert the combustible fractions of construction and demolition wastes into useful hot water for secondary uses.

  16. Data Gap Analysis and Damage Case Studies: Risk Analyses from Construction and Demolition Debris Landfills and Recycling Facilities

    EPA Science Inventory

    The report presents an evaluation of construction and demolition (C&D) debris management in the US to update and expand upon the previous set of data to include information on more recent cases of damage and potential impacts and expand the breadth of damages beyond groundwater a...

  17. 24 CFR 970.7 - General requirements for HUD approval of a PHA demolition/disposition application.

    Code of Federal Regulations, 2012 CFR

    2012-04-01

    ... HUD. The supporting information shall include: (1) A certification that the PHA has described the demolition or disposition in the PHA Annual Plan and timetable under 24 CFR part 903 (except in the case of... determined by HUD, as described in § 970.19(c); (10) In the case of disposition, estimates of the gross...

  18. 48 CFR 52.249-3 - Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements).

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ..., Demolition, or Removal of Improvements) (MAY 2004) (a) The Government may terminate performance of work under... clause: (1) Stop work as specified in the notice. (2) Place no further subcontracts or orders (referred... the work terminated. (4) Assign to the Government, as directed by the Contracting Officer, all...

  19. Residential demolition and its impact on vacant lot hydrology: implications for the management of stormwater and sewer system overflows

    EPA Science Inventory

    Increased residential demolitions have made vacant lots a ubiquitous feature of the contemporary urban landscape. Vacant lots may provide ecosystem services such as stormwater runoff capture, but the extent of these functions will be regulated by soil hydrology. We evaluated soil...

  20. 48 CFR 52.249-3 - Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements).

    Code of Federal Regulations, 2014 CFR

    2014-10-01

    ... 48 Federal Acquisition Regulations System 2 2014-10-01 2014-10-01 false Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements). 52.249-3 Section 52.249-3 Federal Acquisition Regulations System FEDERAL ACQUISITION REGULATION (CONTINUED) CLAUSES AND FORMS SOLICITATION PROVISIONS AND CONTRACT CLAUSES...

  1. Rohm and Haas: Furnace Replacement Project Saves Energy and Improves Production at a Chemical Plant

    SciTech Connect

    Not Available

    2006-02-01

    This DOE Industrial Technologies Program spotlight describes how Rohm and Haas's Deer Park, Texas, chemical plant reduced natural gas usage and energy costs by replacing inefficient furnace equipment.

  2. PRIAMO project: a feasibility study on Sicilian sites for sea power plants in coastal waters

    NASA Astrophysics Data System (ADS)

    Ribotti, A.; Borghini, M.; Cucco, A.; De Domenico, E.; Dibenedetto, V.; Fazioli, L.; Genovese, L.; Iaria, G.; Olita, A.; Raffa, F.; Schroeder, K.; Sorgente, R.; Spanò, N.

    2012-04-01

    The increasing demand for renewable energy sources has recently favoured the exploitation of wind energy and photovoltaic, with strong repercussions on the landscape due to the visual impact of wind turbines and of the photovoltaic panels. A policy protecting the landscape suggests to focus on innovative solutions that enable the use of renewable energy and a low visual impact. This can be done with extensive offshore diving equipment installed in the sea, formed by turbines that use ocean currents to produce electric energy. The accommodation at sea, as well as offering greater availability of sites, has the advantage of giving a better and relatively constant resource with maximum efficiency and productivity. The international scenario suggests the need to identify sites potentially suitable and safe for energy use, placed at a distance from the coast at depths with bathymetric characteristics that make the power plant installation safe and technologically and economically feasible. In this context, the project PRIAMO (Planning, Research and Innovation in a Oriented Marine Environment), funded by the European Commission through the Sicilian Regional Operational Programme (POR), aims to verify the potential suitability of two Sicilian coastal sites, i.e. the Strait of Messina and a stretch of coast near Capo Granitola (Strait of Sicily). The work is realised with a view to the exploitation of marine currents that will be studied through the use of existing or new numerical models from the open sea to the coastal scale, then evaluating its cost-effectiveness in collaboration with Atlantis Resources Corp. Pte. Ltd (UK), European manufacturer of underwater turbines. An environmental study is done through monitoring and remediation techniques to assess the potential size of the foundation structure: sedimentological and morpho-bathymetric characteristics of the bottom, depth, steepness of the seabed, benthic biocoenoses, and load-bearing capacity of the area affected

  3. Mechanical Demolition of Buildings with Concrete Asbestos Board Siding: Methodology, Precautions, and Results at the Hanford Central Plateau - 12417

    SciTech Connect

    Kehler, Kurt

    2012-07-01

    Since the start of its contract in 2008, the CH2M Hill Plateau Remediation Company (CH2M HILL) has demolished 25 buildings with concrete asbestos board (CAB) siding using mechanical means. While the asbestos contained in CAB siding is not friable in its manufactured form, concerns persist that mechanical methods of demolition have the potential to render the asbestos friable and airborne, therefore posing a health risk to demolition workers and the public. CH2M HILL's experience demonstrates that when carefully managed, mechanical demolition of CAB siding can be undertaken safely, successfully, and in compliance with regulatory requirements for the disposal of Class II Asbestos-Containing Material (ACM). While the number of buildings demolished at Hanford and the number of samples collected does not make a conclusive argument that CAB cannot be made friable with normal demolition techniques, it certainly provides a significant body of evidence for the success of the approach. Of course, there are many factors that affect how to demolish a structure and dispose of the waste. These factors will impact the success depending on each site. The most obvious factors which contribute to this success at Hanford are: 1. The availability of onsite waste disposal where the handling and cost of asbestos-containing waste is not much different than other potentially contaminated waste. Therefore, segregation of demolition debris from the potential asbestos contamination is not necessary from a debris handling or asbestos disposal aspect. 2. The space between structures is typically significant enough to allow for large exclusion zones. There are not many restrictions due to cohabitation issues or potential contamination of adjacent facilities. 3. The willingness of the regulators and client to understand the industrial safety issues associated with manual CAB removal. (authors)

  4. The plant-parasitic nematode collections of RRIP: The realization of an ISTC project

    Technology Transfer Automated Retrieval System (TEKTRAN)

    Plant-parasitic nematodes are important pests of agricultural and wild plants throughout Russia and the world. The best strategy for management of nematode damage is an integrated approach to the problem: i.e., the use of agrotechnological approaches (crop rotation, soil amendments, etc.), reasonabl...

  5. Inquiry Based Projects Using Student Ozone Measurements and the Status of Using Plants as Bio-Indicators

    NASA Astrophysics Data System (ADS)

    Ladd, I. H.; Fishman, J.; Pippin, M.; Sachs, S.; Skelly, J.; Chappelka, A.; Neufeld, H.; Burkey, K.

    2006-05-01

    Students around the world work cooperatively with their teachers and the scientific research community measuring local surface ozone levels using a hand-held optical scanner and ozone sensitive chemical strips. Through the GLOBE (Global Learning and Observations to Benefit the Environment) Program, students measuring local ozone levels are connected with the chemistry of the air they breathe and how human activity impacts air quality. Educational tools have been developed and correlated with the National Science and Mathematics Standards to facilitate integrating the study of surface ozone with core curriculum. Ozone air pollution has been identified as the major pollutant causing foliar injury to plants when they are exposed to concentrations of surface ozone. The inclusion of native and agricultural plants with measuring surface ozone provides an Earth system approach to understanding surface ozone. An implementation guide for investigating ozone induced foliar injury has been developed and field tested. The guide, Using Sensitive Plants as Bio-Indicators of Ozone Pollution, provides: the background information and protocol for implementing an "Ozone Garden" with native and agricultural plants; and, a unique opportunity to involve students in a project that will develop and increase their awareness of surface ozone air pollution and its impact on plants.

  6. Plant Biomass Leaching for Nutrient Recovery in Closed Loop Systems Project

    NASA Technical Reports Server (NTRS)

    Zeitlin, Nancy P.; Wheeler, Raymond (Compiler); Lunn, Griffin

    2015-01-01

    Plants will be important for food and O2 production during long term human habitation in space. Recycling of nutrients (e.g., from waste materials) could reduce the resupply costs of fertilizers for growing these plants. Work at NASA's Kennedy Space Center has shown that ion exchange resins can extract fertilizer (plant essential nutrients) from human waste water, after which the residual brine could be treated with electrodialysis to recover more water and produce high value chemicals (e.g., acids and bases). In habitats with significant plant production, inedible biomass becomes a major source of solid waste. To "close the loop" we also need to recover useful nutrients and fertilizer from inedible biomass. We are investigating different approaches to retrieve nutrients from inedible plant biomass, including physical leaching with water, processing the biomass in bioreactors, changing the pH of leaching processing, and/or conducting multiple leaches of biomass residues.

  7. Nuclear Rocket Test Facility Decommissioning Including Controlled Explosive Demolition of a Neutron-Activated Shield Wall

    SciTech Connect

    Michael Kruzic

    2007-09-01

    Located in Area 25 of the Nevada Test Site, the Test Cell A Facility was used in the 1960s for the testing of nuclear rocket engines, as part of the Nuclear Rocket Development Program. The facility was decontaminated and decommissioned (D&D) in 2005 using the Streamlined Approach For Environmental Restoration (SAFER) process, under the Federal Facilities Agreement and Consent Order (FFACO). Utilities and process piping were verified void of contents, hazardous materials were removed, concrete with removable contamination decontaminated, large sections mechanically demolished, and the remaining five-foot, five-inch thick radiologically-activated reinforced concrete shield wall demolished using open-air controlled explosive demolition (CED). CED of the shield wall was closely monitored and resulted in no radiological exposure or atmospheric release.

  8. Toward Quantum Non-demolition of nitrogen-vacancy centers in diamond

    NASA Astrophysics Data System (ADS)

    Hodges, Jonathan; Jiang, Liang; Maze, Jeronimo; Lukin, Mikhail

    2009-05-01

    The nitrogen-vacancy color center (NVC) in diamond, which possesses a long-lived electronic spin (S=1) ground state with optical addressability, is a promising platform for quantum networks, single-photon sources, and nanoscale magnetometers. Here, we make use of a nuclear spin based quantum memory to demonstrate quantum non-demolition measurement of a solid-state spin qubit. By entangling the electron spin with a polarized carbon-13 spin (I=1/2) in the lattice, we have repeated optical measurement of the electron spin for the polarization lifetime of the nuclear spin. We show relative improvements in signal-to-noise of greater than 300%. These techniques can be used to improve the sensitivity of NVC magnetometers.

  9. Upgrade of Compressed Air Control System Reduces Energy Costs at Michelin Tire Plant. Office of Industrial Technologies (OIT) BestPractices Project Case Study

    SciTech Connect

    Not Available

    2002-01-01

    This case study highlights the upgraded compressed air system at a Michelin tire manufacturing plant in Spartanburg, South Carolina. The controls upgrade project enabled multiple compressor operation without blow-off, and significantly reduced energy costs.

  10. Final environmental information volume for the coke oven gas cleaning project at the Bethlehem Steel Corporation Sparrows Point Plant

    SciTech Connect

    Not Available

    1990-04-24

    Bethelehem Steel Corporation (BSC) is planning to conduct a demonstration project involving an integrated system that can be retrofitted into coke oven gas handling systems to address a variety of environmental and operational factors in a more cost-effective manner. Successful application of this technology to existing US coke plants could: (1) reduce emissions of sulfur dioxide, cyanide, and volatile organic compounds (including benzene) (2) reduce the cost and handling of processing feed chemicals, (3) disposal costs of nuisance by-products and (4) increase reliability and reduce operation/maintenance requirements for coke oven gas desulfurization systems. The proposed system will remove sulfur from the coke oven gas in the form of hydrogen sulfide using the ammonia indigenous to the gas as the primary reactive chemical. Ammonia and hydrogen cyanide are also removed in this process. The hydrogen sulfide removed from the coke oven gas in routed to a modified Claus plant for conversion to a saleable sulfur by-product. Ammonia and hydrogen cyanide will be catalytically converted to hydrogen, nitrogen, carbon dioxide, and carbon monoxide. The tail gas from the sulfur recovery unit is recycled to the coke oven gas stream, upstream of the new gas cleaning system. The proposed demonstration project will be installed at the existing coke oven facilities at BSC's Sparrows Point Plant. This volume describes the proposed actions and the resulting environmental impacts. 21 refs., 19 figs., 9 tabs.

  11. A project to improve the capabilities of minorities in energy fields and a cost benefit analysis of an ethyl alcohol plant

    SciTech Connect

    Sara, T.S.; Jones, M. Jr.

    1986-08-01

    The project being reported in this document had three components: (1) a research project to carry out cost-benefit analysis of an ethyl alcohol plant at Tuskegee University, (2) seminars to improve the high-technology capabilities of minority persons, and (3) a class in energy management. The report provides a background on the three components listed above. The results from the research on the ethyl alcohol plant, are discussed, along with the seminars, and details of the energy management class.

  12. Saguaro Power Plant Solar Repowering Project. Executive summary. Final technical report, September 1979-July 1980

    SciTech Connect

    Weber, E.R.

    1980-07-01

    An executive summary describing the conceptual design, system performance, economics, development plan, and site owner's assessment of a solar thermal central receiver system for repowering the No. One unit of PPS's Saguaro power plant near Tuscon, Arizona, is presented. (WHK)

  13. Rohm and Haas: Furnace Replacement Project Saves Energy and Improves Production at a Chemical Plant

    SciTech Connect

    2006-02-01

    This DOE Industrial Technologies Program spotlight describes how Rohm and Haas’s Deer Park, Texas, chemical plant reduced natural gas usage and energy costs by replacing inefficient furnace equipment.

  14. Coyote Pumping Plant 115-kV transmission line project, Santa Clara County, California: Environmental assessment

    SciTech Connect

    Not Available

    1985-01-01

    Environmental impacts expected from the design and siting of transmission lines and the associated pumping plant station are addressed with alternative routes and actions considered, in compliance with environmental laws. (PSB)

  15. Next Generation Nuclear Plant Project Technology Development Roadmaps: The Technical Path Forward

    SciTech Connect

    John Collins

    2009-01-01

    This document presents the Next Generation Nuclear Plant (NGNP) Systems, Subsystems, and Components, establishes a baseline for the current technology readiness status, and provides a path forward to achieve increasing levels of technical maturity.

  16. Projection of distributed-collector solar-thermal electric power plant economics to years 1990-2000

    NASA Technical Reports Server (NTRS)

    Fujita, T.; Elgabalawi, N.; Herrera, G.; Turner, R. H.

    1977-01-01

    A preliminary comparative evaluation of distributed-collector solar thermal power plants was undertaken by projecting power plant economics of selected systems to the 1990 to 2000 time frame. The selected systems include: (1) fixed orientation collectors with concentrating reflectors and vacuum tube absorbers, (2) one axis tracking linear concentrator including parabolic trough and variable slat designs, and (3) two axis tracking parabolic dish systems including concepts with small heat engine-electric generator assemblies at each focal point as well as approaches having steam generators at the focal point with pipeline collection to a central power conversion unit. Comparisons are presented primarily in terms of energy cost and capital cost over a wide range of operating load factors. Sensitvity of energy costs for a range of efficiency and cost of major subsystems/components is presented to delineate critical technological development needs.

  17. Sour gas plant remediation technology research and demonstration project, Task 7.53. Topical report, January--December 1993

    SciTech Connect

    Stepan, D.J.; Kuehnel, V.; Schmit, C.R.

    1994-02-01

    Recognizing the potential impacts of sour gas plant operations on the subsurface environment, the Canadian Association of Petroleum Producers (CAPP) and Environment Canada initiated a multiphase study focusing on research related to the development and demonstration of remedial technologies for soil and groundwater contamination at these facilities. Research performed under this project was designed to supplement and be coordinated with research activities being conducted at an operational sour gas plant located in Rocky Mountain House, Alberta, Canada. These research tasks included hydrogeological site characterization, subsurface contaminant characterization, ex situ treatment of groundwater, and subsurface remediation of residual contamination in the unsaturated zone. Ex situ treatment of groundwater included evaluations of air stripping, steam stripping, advanced oxidation, and biological treatment, as well as the development of an artificial freeze crystallization process. Soil vapor extraction was evaluated as a technique to address residual contamination in the unsaturated zone.

  18. Saguaro Power Plant Solar Repowering Project. Volume I. Conceptual design. Final technical report, September 1979-July 1980

    SciTech Connect

    Weber, E.R.

    1980-07-01

    The conceptual design of a solar thermal central receiver repowered gas/oil fired steam-Rankine electrical power generation plant based on a central receiver using a molten salt (60% NaNO/sub 3/, 40% KNO/sub 3/, by wt) for repowering the No. One Unit of APS's Saguaro power plant is described in detail. The plant is located 66 km (41 mi) north of Tucson, Arizona. The selection of both the site and the molten salt central receiver promotes a near-term feasibility demonstration and cost-effective power production from an advanced solar thermal technology. The recommended system concept is to repower the existing electric power generating system at the maximum possible level (120 MW/sub e/ gross) using a field of 10,500 second-generation (49 m/sup 2/) heliostats and a storage capacity of 3.8 hours to be used for optimum dispatch of power to the utility system. The total project construction cost is estimated to be 167 million in 1980 dollars. The plant will be capable of displacing fossil energy equivalent to 4.9 million barrels of No. 6 oil in its first 10 years of operation. Detailed subsystem characteristics, an economic analysis, and a development plan are presented in detail. (WHK)

  19. Foundation improvement techniques for heavy power plant structures at the Gilberton Power Project

    SciTech Connect

    Young, L.W. ); Lewis, M.R. ); Whitcraft, J.S. ); Pernisi, R.E. )

    1989-01-01

    In recent years, a number of small cogeneration projects have been developed in various parts of the country to make use of the economic advantages afforded by the Public Utility Regulatory Policies Act. The viability of these projects depends upon the ability of the developer, engineer and constructor to assemble a cost effective program that has the capability to produce electricity profitably. To assure success, the projects are, in many cases, constructed under lump sum contracts with relatively short schedules. For many of these projects, the site conditions are not ideal. It is usually necessary to construct the facilities n parcels of land not readily suitable for other purposes. Because of cost and schedule constraints, as well as potentially adverse soil conditions, there is a continuing need for development of innovative solutions to difficult foundation situations. This paper discusses an approach to one such problem.

  20. Dehomed: the impacts of house demolitions on the well-being of women from the unrecognized Bedouin-Arab villages in the Negev/Israel.

    PubMed

    Gottlieb, Nora; Feder-Bubis, Paula

    2014-09-01

    Thirty-five Bedouin-Arab villages in South Israel are regarded illegal settlements by the state. Consequently, the residents׳ homes are subject to demolition. Based on 12 semi-structured multiple-participant interviews, this paper examines the house demolitions׳ impacts on women, in the context of gendered constructions of social roles and space. It highlights that the marginalized position of Arab-Bedouin women - as women in a patriarchal community, as members of a minority within Israeli society, and as residents of an "invisible" settlement - contributes to the devastating effects of the house demolitions. In particular, the study׳s results show that the house demolitions inflict severe personal and collective trauma, amplified by women׳s primary role as mothers. Paradoxically, the very same role also becomes a source of resilience and political resistance, as women act to defend a sense of home and restore family life in the face of state violence.

  1. Soil-plant water status and wine quality: the case study of Aglianico wine (the ZOViSA project)

    NASA Astrophysics Data System (ADS)

    Bonfante, Antonello; Manna, Piero; Albrizio, Rossella; Basile, Angelo; Agrillo, Antonietta; De Mascellis, Roberto; Caputo, Pellegrina; Delle Cave, Aniello; Gambuti, Angelita; Giorio, Pasquale; Guida, Gianpiero; Minieri, Luciana; Moio, Luigi; Orefice, Nadia; Terribile, Fabio

    2014-05-01

    The terroir analysis, aiming to achieve a better use of environmental features with respect to plant requirement and wine production, needs to be strongly rooted on hydropedology. In fact, the relations between wine quality and soil moisture regime during the cropping season is well established. The ZOViSA Project (Viticultural zoning at farm scale) tests a new physically oriented approach to terroir analysis based on the relations between the soil-plant water status and wine quality. The project is conducted in southern Italy in the farm Quintodecimo of Mirabella Eclano (AV) located in the Campania region, devoted to quality Aglianico red wine production (DOC). The soil spatial distribution of study area (about 3 ha) was recognized by classical soil survey and geophysics scan by EM38DD; then the soil-plant water status was monitored for three years in two experimental plots from two different soils (Cambisol and Calcisol). Daily climate variables (temperature, solar radiation, rainfall, wind), daily soil water variables (through TDR probes and tensiometers), crop development (biometric and physiological parameters), and grape must and wine quality were monitored. The agro-hydrological model SWAP was calibrated and applied in the two experimental plots to estimate soil-plant water status in different crop phenological stages. The effects of crop water status on crop response and wine quality was evaluated in two different pedo-systems, comparing the crop water stress index with both: crop physiological measurements (leaf gas exchange, leaf water potential, chlorophyll content, LAI measurement), grape bunches measurements (berry weight, sugar content, titratable acidity, etc.) and wine quality (aromatic response). Finally a "spatial application" of the model was carried out and different terroirs defined.

  2. Summary Report of Geophysical Logging For The Seismic Boreholes Project at the Hanford Site Waste Treatment Plant.

    SciTech Connect

    Gardner, Martin G.; Price, Randall K.

    2007-02-01

    During the period of June through October 2006, three deep boreholes and one corehole were drilled beneath the site of the Waste Treatment Plant (WTP) at the U.S. Department of Energy (DOE) Hanford Site near Richland, Washington. The boreholes were drilled to provide information on ground-motion attenuation in the basalt and interbedded sediments underlying the WTP site. This report describes the geophysical logging of the deep boreholes that was conducted in support of the Seismic Boreholes Project, defined below. The detailed drilling and geological descriptions of the boreholes and seismic data collected and analysis of that data are reported elsewhere.

  3. WASTE TREATMENT & IMMOBILIZATION PLANT (WTP) HIGH LEVEL WASTE (HLW) CANISTER PRODUCTION ESTIMATES TO SUPPORT ANALYSES BY THE YUCCA MOUNTAIN PROJECT

    SciTech Connect

    HAMEL, W.F.

    2004-09-09

    This document summarizes estimates of the range of chemical and radiochemical compositions for the immobilized HLW (IHLW) canisters to be generated from the Waste Treatment and Immobilization Plant (WTP) that will be operated at the U.S. Department of Energy's (DOE) Hanford Site. These estimates have been derived from DOE planning, WTP Project and Hanford tank waste characterization information. The IHLW canister composition estimates include three Cases that bound the expected number of IHLW canisters to be produced in the WTP (termed the WTP Program Case, WTP Planning Case and WTP Technology Case) and production of the maximum radionuclide content IHLW canister.

  4. Characterization and environmental risk assessment of heavy metals in construction and demolition wastes from five sources (chemical, metallurgical and light industries, and residential and recycled aggregates).

    PubMed

    Gao, Xiaofeng; Gu, Yilu; Xie, Tian; Zhen, Guangyin; Huang, Sheng; Zhao, Youcai

    2015-06-01

    Total concentrations of heavy metals (Cu, Zn, Pb, Cr, Cd, and Ni) were measured among 63 samples of construction and demolition (C&D) wastes collected from chemical, metallurgical and light industries, and residential and recycled aggregates within China for risk assessment. The heavy metal contamination was primarily concentrated in the chemical and metallurgical industries, especially in the electroplating factory and zinc smelting plant. High concentrations of Cd were found in light industry samples, while the residential and recycled aggregate samples were severely polluted by Zn. Six most polluted samples were selected for deep research. Mineralogical analysis by X-ray fluorescence (XRF) spectrometry and X-ray diffraction (XRD), combined with element speciation through European Community Bureau of Reference (BCR) sequential extraction, revealed that a relatively slight corrosion happened in the four samples from electroplating plants but high transfer ability for large quantities of Zn and Cu. Lead arsenate existed in the acid extractable fraction in CI7-8 and potassium chromium oxide existed in the mobility fraction. High concentration of Cr could be in amorphous forms existing in CI9. The high content of sodium in the two samples from zinc smelter plants suggested severe deposition and erosion on the workshop floor. Large quantities of Cu existed as copper halide and most of the Zn appeared to be zinc, zinc oxide, barium zinc oxide, and zincite. From the results of the risk assessment code (RAC), the samples from the electroplating factory posed a very high risk of Zn, Cu, and Cr, a high risk of Ni, a middle risk of Pb, and a low risk of Cd. The samples from the zinc smelting plant presented a high risk of Zn, a middle risk of Cu, and a low risk of Pb, Cr, Cd, and Ni.

  5. Characterization and environmental risk assessment of heavy metals in construction and demolition wastes from five sources (chemical, metallurgical and light industries, and residential and recycled aggregates).

    PubMed

    Gao, Xiaofeng; Gu, Yilu; Xie, Tian; Zhen, Guangyin; Huang, Sheng; Zhao, Youcai

    2015-06-01

    Total concentrations of heavy metals (Cu, Zn, Pb, Cr, Cd, and Ni) were measured among 63 samples of construction and demolition (C&D) wastes collected from chemical, metallurgical and light industries, and residential and recycled aggregates within China for risk assessment. The heavy metal contamination was primarily concentrated in the chemical and metallurgical industries, especially in the electroplating factory and zinc smelting plant. High concentrations of Cd were found in light industry samples, while the residential and recycled aggregate samples were severely polluted by Zn. Six most polluted samples were selected for deep research. Mineralogical analysis by X-ray fluorescence (XRF) spectrometry and X-ray diffraction (XRD), combined with element speciation through European Community Bureau of Reference (BCR) sequential extraction, revealed that a relatively slight corrosion happened in the four samples from electroplating plants but high transfer ability for large quantities of Zn and Cu. Lead arsenate existed in the acid extractable fraction in CI7-8 and potassium chromium oxide existed in the mobility fraction. High concentration of Cr could be in amorphous forms existing in CI9. The high content of sodium in the two samples from zinc smelter plants suggested severe deposition and erosion on the workshop floor. Large quantities of Cu existed as copper halide and most of the Zn appeared to be zinc, zinc oxide, barium zinc oxide, and zincite. From the results of the risk assessment code (RAC), the samples from the electroplating factory posed a very high risk of Zn, Cu, and Cr, a high risk of Ni, a middle risk of Pb, and a low risk of Cd. The samples from the zinc smelting plant presented a high risk of Zn, a middle risk of Cu, and a low risk of Pb, Cr, Cd, and Ni. PMID:25601613

  6. Environmental Regulation of Plant Gene Expression: An Rt-qPCR Laboratory Project for an Upper-Level Undergraduate Biochemistry or Molecular Biology Course

    ERIC Educational Resources Information Center

    Eickelberg, Garrett J.; Fisher, Alison J.

    2013-01-01

    We present a novel laboratory project employing "real-time" RT-qPCR to measure the effect of environment on the expression of the "FLOWERING LOCUS C" gene, a key regulator of floral timing in "Arabidopsis thaliana" plants. The project requires four 3-hr laboratory sessions and is aimed at upper-level undergraduate…

  7. Projecting changes in annual hydropower generation using regional runoff data: An assessment of the United States federal hydropower plants

    SciTech Connect

    Kao, Shih -Chieh; Sale, Michael J.; Ashfaq, Moetasim; Uria Martinez, Rocio; Kaiser, Dale Patrick; Wei, Yaxing; Diffenbaugh, Noah S.

    2014-12-18

    Federal hydropower plants account for approximately half of installed US conventional hydropower capacity, and are an important part of the national renewable energy portfolio. Utilizing the strong linear relationship between the US Geological Survey WaterWatch runoff and annual hydropower generation, a runoff-based assessment approach is introduced in this study to project changes in annual and regional hydropower generation in multiple power marketing areas. Future climate scenarios are developed with a series of global and regional climate models, and the model output is bias-corrected to be consistent with observed data for the recent past. Using this approach, the median decrease in annual generation at federal projects is projected to be less than –2 TWh, with an estimated ensemble uncertainty of ±9 TWh. Although these estimates are similar to the recently observed variability in annual hydropower generation, and may therefore appear to be manageable, significantly seasonal runoff changes are projected and it may pose significant challenges in water systems with higher limits on reservoir storage and operational flexibility. Lastly, future assessments will be improved by incorporating next-generation climate models, by closer examination of extreme events and longer-term change, and by addressing the interactions among hydropower and other water uses.

  8. Projecting changes in annual hydropower generation using regional runoff data: An assessment of the United States federal hydropower plants

    DOE PAGES

    Kao, Shih -Chieh; Sale, Michael J.; Ashfaq, Moetasim; Uria Martinez, Rocio; Kaiser, Dale Patrick; Wei, Yaxing; Diffenbaugh, Noah S.

    2014-12-18

    Federal hydropower plants account for approximately half of installed US conventional hydropower capacity, and are an important part of the national renewable energy portfolio. Utilizing the strong linear relationship between the US Geological Survey WaterWatch runoff and annual hydropower generation, a runoff-based assessment approach is introduced in this study to project changes in annual and regional hydropower generation in multiple power marketing areas. Future climate scenarios are developed with a series of global and regional climate models, and the model output is bias-corrected to be consistent with observed data for the recent past. Using this approach, the median decrease inmore » annual generation at federal projects is projected to be less than –2 TWh, with an estimated ensemble uncertainty of ±9 TWh. Although these estimates are similar to the recently observed variability in annual hydropower generation, and may therefore appear to be manageable, significantly seasonal runoff changes are projected and it may pose significant challenges in water systems with higher limits on reservoir storage and operational flexibility. Lastly, future assessments will be improved by incorporating next-generation climate models, by closer examination of extreme events and longer-term change, and by addressing the interactions among hydropower and other water uses.« less

  9. Comparative risk analysis for the Rocky Flats Plant integrated project planning

    SciTech Connect

    Jones, M.E.; Shain, D.I.

    1994-05-01

    The Rocky Flats Plant is developing, with active stakeholder a comprehensive planning strategy that will support transition of the Rocky Flats Plant from a nuclear weapons production facility to site cleanup and final disposition. Final disposition of the Rocky Flats Plant materials and contaminants requires consideration of the interrelated nature of sitewide problems, such as material movement and disposition, facility and land use endstates, costs relative risks to workers and the public, and waste disposition. Comparative Risk Analysis employs both incremental risk and cumulative risk evaluations to compare risks from postulated options or endstates. These postulated options or endstates can be various remedial alternatives, or future endstate uses of federal agency land. Currently, there does not exist any approved methodology that aggregates various incremental risk estimates. Comparative Risk Analysis has been developed to aggregate various incremental risk estimates to develop a site cumulative risk estimate. This paper discusses development of the Comparative Risk Analysis methodology, stakeholder participation and lessons learned from these challenges.

  10. Effect of Co-Composting Cattle Manure with Construction and Demolition Waste on the Archaeal, Bacterial, and Fungal Microbiota, and on Antimicrobial Resistance Determinants.

    PubMed

    Holman, Devin B; Hao, Xiying; Topp, Edward; Yang, Hee Eun; Alexander, Trevor W

    2016-01-01

    Agricultural operations generate large quantities of manure which must be eliminated in a manner that is consistent with public health guidelines. Meanwhile, construction and demolition waste makes up about 25% of total solid municipal waste. Co-composting of manure with construction and demolition waste offers a potential means to make manure safe for soil amendment and also divert construction and demolition waste from municipal landfills. Therefore, the archaeal, bacterial, and fungal microbiota of two different types of composted cattle manure and one co-composted with construction and demolition waste, were assessed over a 99-day composting period. The microbiota of the three compost mixtures did not differ, but significant changes over time and by sampling depth were observed. Bacillus and Halocella, however, were more relatively abundant in composted manure from cattle fed dried distillers' grains and solubles. Proteobacteria and Bacteroidetes were enriched at day 0 and Firmicutes at day 99. The fungal genus Kernia was the most relatively abundant overall and was enriched at day 0. The concentration of 12 antimicrobial resistance determinants in the compost mixtures was also determined, and 10 of these determinants decreased significantly from days 0 to 99. The addition of construction and demolition waste did not affect the persistence of antimicrobial resistance genes or community structure of the compost microbiota and therefore co-composting construction and demolition waste with cattle manure offers a safe, viable way to divert this waste from landfills.

  11. Effect of Co-Composting Cattle Manure with Construction and Demolition Waste on the Archaeal, Bacterial, and Fungal Microbiota, and on Antimicrobial Resistance Determinants

    PubMed Central

    Holman, Devin B.; Hao, Xiying; Topp, Edward; Yang, Hee Eun; Alexander, Trevor W.

    2016-01-01

    Agricultural operations generate large quantities of manure which must be eliminated in a manner that is consistent with public health guidelines. Meanwhile, construction and demolition waste makes up about 25% of total solid municipal waste. Co-composting of manure with construction and demolition waste offers a potential means to make manure safe for soil amendment and also divert construction and demolition waste from municipal landfills. Therefore, the archaeal, bacterial, and fungal microbiota of two different types of composted cattle manure and one co-composted with construction and demolition waste, were assessed over a 99-day composting period. The microbiota of the three compost mixtures did not differ, but significant changes over time and by sampling depth were observed. Bacillus and Halocella, however, were more relatively abundant in composted manure from cattle fed dried distillers’ grains and solubles. Proteobacteria and Bacteroidetes were enriched at day 0 and Firmicutes at day 99. The fungal genus Kernia was the most relatively abundant overall and was enriched at day 0. The concentration of 12 antimicrobial resistance determinants in the compost mixtures was also determined, and 10 of these determinants decreased significantly from days 0 to 99. The addition of construction and demolition waste did not affect the persistence of antimicrobial resistance genes or community structure of the compost microbiota and therefore co-composting construction and demolition waste with cattle manure offers a safe, viable way to divert this waste from landfills. PMID:27300323

  12. Effect of Co-Composting Cattle Manure with Construction and Demolition Waste on the Archaeal, Bacterial, and Fungal Microbiota, and on Antimicrobial Resistance Determinants.

    PubMed

    Holman, Devin B; Hao, Xiying; Topp, Edward; Yang, Hee Eun; Alexander, Trevor W

    2016-01-01

    Agricultural operations generate large quantities of manure which must be eliminated in a manner that is consistent with public health guidelines. Meanwhile, construction and demolition waste makes up about 25% of total solid municipal waste. Co-composting of manure with construction and demolition waste offers a potential means to make manure safe for soil amendment and also divert construction and demolition waste from municipal landfills. Therefore, the archaeal, bacterial, and fungal microbiota of two different types of composted cattle manure and one co-composted with construction and demolition waste, were assessed over a 99-day composting period. The microbiota of the three compost mixtures did not differ, but significant changes over time and by sampling depth were observed. Bacillus and Halocella, however, were more relatively abundant in composted manure from cattle fed dried distillers' grains and solubles. Proteobacteria and Bacteroidetes were enriched at day 0 and Firmicutes at day 99. The fungal genus Kernia was the most relatively abundant overall and was enriched at day 0. The concentration of 12 antimicrobial resistance determinants in the compost mixtures was also determined, and 10 of these determinants decreased significantly from days 0 to 99. The addition of construction and demolition waste did not affect the persistence of antimicrobial resistance genes or community structure of the compost microbiota and therefore co-composting construction and demolition waste with cattle manure offers a safe, viable way to divert this waste from landfills. PMID:27300323

  13. EXPERIENCES IN DECONTAMINATION & DEMOLITION OF A FORMER PLUTONIUM CONCENTRATION FACILITY HANFORD RESERVATION

    SciTech Connect

    BISHOP, G.E.

    2002-06-01

    The 233-S Plutonium Concentration Facility received plutonium nitrate paste from the nearby Reduction-Oxidation (REDOX) Facility and concentrated the plutonium for shipment to Hanford's Plutonium Finishing Plant. Operations ceased in 1967 and the Facility languished in a state of minimal maintenance until the mid-1990's when a decision was made to decontaminate and demolish (D&D) it. This work is being performed as a pilot project that integrates DOE nuclear safety analysis and worker safety requirements with Environmental Protection Agency (EPA) requirements under CERCLA (Comprehensive Environmental Response, Compensation, and Liability Act, 1980). The pilot project is a CERCLA non-time critical removal action. Difficulties were encountered during D&D. These included conflict between the development of the safety basis as an EPA pilot project and DOE requirements for safety analysis reports, updating the safety analysis to keep it current with field conditions, and major difficulties with nondestructive assays (NDA) of the contaminated waste. No demonstrable benefit has been obtained by integrating the EPA and DOE safety methodologies.

  14. Borehole Summary Report for Core Hole C4998 – Waste Treatment Plant Seismic Boreholes Project

    SciTech Connect

    Barnett, D. BRENT; Garcia, Benjamin J.

    2006-12-15

    Seismic borehole C4998 was cored through the upper portion of the Columbia River Basalt Group and Ellensburg Formation to provide detailed lithologic information and intact rock samples that represent the geology at the Waste Treatment Plant. This report describes the drilling of borehole C4998 and documents the geologic data collected during the drilling of the cored portion of the borehole.

  15. Real Time Demonstration Project XRF Performance Evaluation Report for Paducah Gaseous Diffusion Plant AOC 492

    SciTech Connect

    Johnson, Robert L

    2008-04-03

    This activity was undertaken to demonstrate the applicability of market-available XRF instruments to quantify metal concentrations relative to background and risk-based action and no action levels in Paducah Gaseous Diffusion Plant (PGDP) soils. As such, the analysis below demonstrates the capabilities of the instruments relative to soil characterization applications at the PGDP.

  16. GRIN-Global: An International Project to Develop a Global Plant Genebank and Information Management System

    Technology Transfer Automated Retrieval System (TEKTRAN)

    Many of the world's national genebanks, responsible for the safeguarding and availability of their country's Plant Genetic Resource (PGR) collections, have lacked access to high quality IT needed to document and manage their collections electronically. The Germplasm Resource Information System (GRI...

  17. 78 FR 64909 - Southwestern Region: Invasive Plant Control Project, Carson and Santa Fe National Forests, New...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-10-30

    ..., the USDA Forest Service published a notice of intent (NOI) in the Federal Register (65 FR 78464) to prepare an environmental impact statement (EIS) for controlling invasive plants in the Carson and Santa Fe... Register (69 FR 42722) on July 16, 2004. A record of decision was signed on September 12, 2005 and an...

  18. Project W-340 long reach arm retrieval system balance of plant instrumentation workshop engineering study

    SciTech Connect

    Schneider, T.C.

    1994-01-01

    This engineering study documents the results of a workshop held to resolve Issue No. 26 generated at a Arm Based Retrieval Functional Analysis Value Engineering Session. The issue deals with the scope of the Balance of Plant Instrumentation needs for the LRARS.

  19. Animal, Plant, Living: Notes for Teachers. Learning in Science Project. Working Paper No. 30.

    ERIC Educational Resources Information Center

    Bell, Beverley

    The Learning in Science Project investigated the proportion of students at different ages who considered a horse, person, dolphin, worm, and spider to be animals. Although scientists would agree that they are indeed animals, findings indicate that many students of varying ages did not consider them to be animals; similar findings were reported for…

  20. Arabidopsis Ecotypes: A Model for Course Projects in Organismal Plant Biology & Evolution

    ERIC Educational Resources Information Center

    Wyatt, Sarah; Ballard, Harvey E.

    2007-01-01

    We present an inquiry-based project using readily-available seed stocks of Arabidopsis. Seedlings are grown under simulated "common garden" conditions to test evolutionary and organismal principles. Students learn scientific method by developing hypotheses and selecting appropriate data and analyses for their experiments. Experiments can be…

  1. A study of a solar central power plant with a gas turbine - Project Sirocco modelling and control

    NASA Astrophysics Data System (ADS)

    Kacim, M.

    A thermodynamics and receiver design analysis is presented for a solar tower power plant, together with a control model for operations in varying working conditions. The analysis covers the central receiver and the gas-air turbine, adapted for functioning at 820 C, such as was experienced with the 100 kW Project Sirocco test station. A heliostat field concentrates solar energy onto a central receiver traversed by compressed air, which is allowed to expand while driving a turbine generator. A combustion chamber is included in the loop to augment the thermal performance when insufficient solar energy is available. The plant can be either grid-connected or stand alone. Static and dynamic characteristics of the thermal loop are modelled, and are included in the development of control laws based on quadratic criteria. An optimized control scheme is devised which features weighting criteria matrices, and the results of simulations covering different insolation levels are reported. Finally, an adjoint state control system is produced to account for peculiarities of the power plant.

  2. Designing a transcriptome next-generation sequencing project for a nonmodel plant species.

    PubMed

    Strickler, Susan R; Bombarely, Aureliano; Mueller, Lukas A

    2012-02-01

    The application of next-generation sequencing (NGS) to transcriptomics, commonly called RNA-seq, allows the nearly complete characterization of transcriptomic events occurring in a specific tissue. It has proven particularly useful in nonmodel species, which often lack the resources available for sequenced organisms. Mainly, RNA-seq does not require a reference genome to gain useful transcriptomic information. In this review, the application of RNA-seq to nonmodel plant species will be addressed. Important experimental considerations from presequencing issues to postsequencing analysis, including sample and platform selection, and useful bioinformatics tools for assembly and data analysis, are covered. Methods of assembling RNA-seq data and analyses commonly performed with RNA-seq data, including single nucleotide polymorphism detection and analysis of differential expression, are explored. In addition, studies that have used RNA-seq to elucidate nonmodel plant transcriptomics are highlighted.

  3. Monitoring alpine plants for climate change: The North American GLORIA Project

    USGS Publications Warehouse

    Millar, C.; Fagre, Daniel B.

    2007-01-01

    Globally, alpine environments are hotspots of biodiversity, often harboring higher diversity of plant species than corresponding areas at lower elevations. These regions are also likely to experience more severe and rapid change in climate than lowlands under conditions of anthropogenic warming (Theurillat & Guisan 2001; Halloy & Mark 2003; Pickering & Armstrong 2003). Such climatic effects are already being documented by instrumental monitoring in the few places in western North America where long-term climate stations are available at high elevations. New sites are being planned (see GCOS article, pg 15). Climate Change is augmenting concern for alpine vegetation because available habitat diminishes at increasingly higher elevations. This creates an “elevational squeeze,” whereby the geometry of mountain peaks means that escape routes to cooler environments uphill are dead ends for migrating alpine species. While monitoring and modeling efforts have begun to elucidate climate of alpine environments in North America, very little is known about corresponding responses of alpine plant species to changing climate. Indeed, for many mountain regions in the West, little information exists even about alpine plant distribution and abundance.

  4. [The courses of plant biology at the Faculty of Medicine, Université libre de Bruxelles].

    PubMed

    Lauryan, S

    2014-01-01

    The recent demolition of the Capouillet house, which sheltered the Institute of Botany of the ULB is the occasion to evoke the successive holders of the courses of plant biology at the Fauclty of Medicine. Some of them were famous botanists who, as pioneers, renewed their field with dynamism and competence.

  5. Final Report for DOE Project: Climate Effects on Plant Range Distributions and Community Structure of Pacific Northwest Prairies

    SciTech Connect

    Bridgham, Scott D.; Johnson, Bart

    2013-09-26

    was negatively impacted by increased temperatures, but for species planted north of their current range, increased temperature was neutral. However, for surviving plants climate treatments and site-specific factors (e.g., nutrient availability) were the strongest predictors of plant growth and seed set. When recruitment and plant growth are considered together, increased temperatures are negative within a species current range but beyond this range they become positive. Germination was the most critical stage for plant response across all sites and climate treatments. Our results underscore the importance of including plant vital rates into models that are examining climate change effects on plant ranges. Warming altered plant community composition, decreased diversity, and increased total cover, with warmed northern communities over time becoming more like ambient communities further south. In particular, warming increased the cover of annual introduced species, suggesting that the observed biogeographic pattern of increasing invasion by this plant functional group in US West Coast prairies as one moves further south is at least in part due to climate. Our results suggest that with the projected increase in drought severity with climate change, Pacific Northwest prairies may face an increase of invasion by annuals, similar to what has been observed in California, resulting in novel species assemblages and shifts in functional composition, which in turn may alter ecosystem function. Warming generally increased nutrient availability and plant productivity across all sites. The seasonality of soil respiration responses to heating were strongly dependent on the Mediterranean climate gradient in the PNW, with heating responses being generally positive during periods of adequate soil moisture and becoming neutral to negative during periods of low soil moisture. The asynchrony between temperature and precipitation may make soils less sensitive to warming. Precipitation

  6. Microbiological Quality and Food Safety of Plants Grown on ISS Project

    NASA Technical Reports Server (NTRS)

    Wheeler, Raymond M. (Compiler)

    2014-01-01

    The goal of this project is to select and advance methods to enable real-time sampling, microbiological analysis, and sanitation of crops grown on the International Space Station (ISS). These methods would validate the microbiological quality of crops grown for consumption to ensure safe and palatable fresh foods. This would be achieved through the development / advancement of microbiological sample collection, rapid pathogen detection and effective sanitation methods that are compatible with a microgravity environment.

  7. SOLERAS - Solar Energy Water Desalination Project: Martin Marietta Corporation. Pilot plant final report

    SciTech Connect

    Not Available

    1985-01-01

    This report documents the technical effort of Martin Marietta Corporation, in association with Black and Veatch International as a subcontractor for the trade studies performed to design a Solar Desalination Pilot Plant is documented. The final system configuration utilizes existing technology to convert seawater to potable water. This technology includes the collection of solar energy, storage of this energy in a fluid heat transfer medium, generation of steam and electricity from this stored energy, utilization of low pressure turbine exhaust steam as a source of energy to distill salt water, and also generation of potable water through the use of a reverse osmosis unit.

  8. Hydrogen sulfide generation in simulated construction and demolition debris landfills: impact of waste composition.

    PubMed

    Yang, Kenton; Xu, Qiyong; Townsend, Timothy G; Chadik, Paul; Bitton, Gabriel; Booth, Matthew

    2006-08-01

    Hydrogen sulfide (H2S) generation in construction and demolition (C&D) debris landfills has been associated with the biodegradation of gypsum drywall. Laboratory research was conducted to observe H2S generation when drywall was codisposed with different C&D debris constituents. Two experiments were conducted using simulated landfill columns. Experiment 1 consisted of various combinations of drywall, wood, and concrete to determine the impact of different waste constituents and combinations on H2S generation. Experiment 2 was designed to examine the effect of concrete on H2S generation and migration. The results indicate that decaying drywall, even alone, leached enough sulfate ions and organic matter for sulfate-reducing bacteria (SRB) to generate large H2S concentrations as high as 63,000 ppmv. The codisposed wastes show some effect on H2S generation. At the end of experiment 1, the wood/drywall and drywall alone columns possessed H2S concentrations > 40,000 ppmv. Conversely, H2S concentrations were < 1 ppmv in those columns containing concrete. Concrete plays a role in decreasing H2S by increasing pH out of the range for SRB growth and by reacting with H2S. This study also showed that wood lowered H2S concentrations initially by decreasing leachate pH values. Based on the results, two possible control mechanisms to mitigate H2S generation in C&D debris landfills are suggested. PMID:16933645

  9. Ethanol production from acid hydrolysates based on the construction and demolition wood waste using Pichia stipitis.

    PubMed

    Cho, Dae Haeng; Shin, Soo-Jeong; Bae, Yangwon; Park, Chulhwan; Kim, Yong Hwan

    2011-03-01

    The feasibility of ethanol production from the construction and demolition (C&D) wood waste acid hydrolysates was investigated. The chemical compositions of the classified C&D wood waste were analyzed. Concentrated sulfuric acid hydrolysis was used to obtain the saccharide hydrolysates and the inhibitors in the hydrolysates were also analyzed. The C&D wood waste composed of lumber, plywood, particleboard, and medium density fiberboard (MDF) had polysaccharide (cellulose, xylan, and glucomannan) fractions of 60.7-67.9%. The sugar composition (glucose, xylose, and mannose) of the C&D wood wastes varied according to the type of wood. The additives used in the wood processing did not appear to be released into the saccharide solution under acid hydrolysis. Although some fermentation inhibitors were detected in the hydrolysates, they did not affect the ethanol production by Pichia stipitis. The hexose sugar-based ethanol yield and ethanol yield efficiency were 0.42-0.46 g ethanol/g substrate and 84.7-90.7%, respectively. Therefore, the C&D wood wastes dumped in landfill sites could be used as a raw material feedstock for the production of bioethanol. PMID:21251816

  10. Estimation of building-related construction and demolition waste in Shanghai.

    PubMed

    Ding, Tao; Xiao, Jianzhuang

    2014-11-01

    One methodology is proposed to estimate the quantification and composition of building-related construction and demolition (C&D) waste in a fast developing region like Shanghai, PR China. The varieties of structure types and building waste intensities due to the requirement of progressive building design and structure codes in different decades are considered in this regional C&D waste estimation study. It is concluded that approximately 13.71 million tons of C&D waste was generated in 2012 in Shanghai, of which more than 80% of this C&D waste was concrete, bricks and blocks. Analysis from this study can be applied to facilitate C&D waste governors and researchers the duty of formulating precise policies and specifications. As a matter of fact, at least a half of the enormous amount of C&D waste could be recycled if implementing proper recycling technologies and measures. The appropriate managements would be economically and environmentally beneficial to Shanghai where the per capita per year output of C&D waste has been as high as 842 kg in 2010. PMID:25164857

  11. Development of construction materials using nano-silica and aggregates recycled from construction and demolition waste.

    PubMed

    Mukharjee, Bibhuti Bhusan; Barai, Sudhirkumar V

    2015-06-01

    The present work addresses the development of novel construction materials utilising commercial grade nano-silica and recycled aggregates retrieved from construction and demolition waste. For this, experimental work has been carried out to examine the influence of nano-silica and recycled aggregates on compressive strength, modulus of elasticity, water absorption, density and volume of voids of concrete. Fully natural and recycled aggregate concrete mixes are designed by replacing cement with three levels (0.75%, 1.5% and 3%) of nano-silica. The results of the present investigation depict that improvement in early days compressive strength is achieved with the incorporation of nano-silica in addition to the restoration of reduction in compressive strength of recycled aggregate concrete mixes caused owing to the replacement of natural aggregates by recycled aggregates. Moreover, the increase in water absorption and volume of voids with a reduction of bulk density was detected with the incorporation of recycled aggregates in place of natural aggregates. However, enhancement in density and reduction in water absorption and volume of voids of recycled aggregate concrete resulted from the addition of nano-silica. In addition, the results of the study reveal that nano-silica has no significant effect on elastic modulus of concrete. PMID:25986048

  12. Ethanol production from acid hydrolysates based on the construction and demolition wood waste using Pichia stipitis.

    PubMed

    Cho, Dae Haeng; Shin, Soo-Jeong; Bae, Yangwon; Park, Chulhwan; Kim, Yong Hwan

    2011-03-01

    The feasibility of ethanol production from the construction and demolition (C&D) wood waste acid hydrolysates was investigated. The chemical compositions of the classified C&D wood waste were analyzed. Concentrated sulfuric acid hydrolysis was used to obtain the saccharide hydrolysates and the inhibitors in the hydrolysates were also analyzed. The C&D wood waste composed of lumber, plywood, particleboard, and medium density fiberboard (MDF) had polysaccharide (cellulose, xylan, and glucomannan) fractions of 60.7-67.9%. The sugar composition (glucose, xylose, and mannose) of the C&D wood wastes varied according to the type of wood. The additives used in the wood processing did not appear to be released into the saccharide solution under acid hydrolysis. Although some fermentation inhibitors were detected in the hydrolysates, they did not affect the ethanol production by Pichia stipitis. The hexose sugar-based ethanol yield and ethanol yield efficiency were 0.42-0.46 g ethanol/g substrate and 84.7-90.7%, respectively. Therefore, the C&D wood wastes dumped in landfill sites could be used as a raw material feedstock for the production of bioethanol.

  13. Mobilization of iron and arsenic from soil by construction and demolition debris landfill leachate.

    PubMed

    Wang, Yu; Sikora, Saraya; Kim, Hwidong; Dubey, Brajesh; Townsend, Timothy

    2012-05-01

    Column experiments were performed to examine (a) the potential for leachate from construction and demolition (C&D) debris landfills to mobilize naturally-occurring iron and arsenic from soils underlying such facilities and (b) the ability of crushed limestone to remove these aqueous phase pollutants. In duplicate columns, water was added to a 30-cm layer of synthetic C&D debris, with the resulting leachate serially passed through a 30-cm soil layer containing iron and arsenic and a 30-cm crushed limestone layer. This experiment was conducted for two different soil types (one high in iron (10,400mg/kg) and the second high in iron (5400mg/kg) and arsenic (70mg/kg)); also monitored were control columns for both soil types with water infiltration alone. Despite low iron concentrations in the simulated C&D debris leachate, elevated iron concentrations were observed when leachate passed through the soils; reductive dissolution was concluded to be the cause of iron mobilization. In the soil containing elevated arsenic, increased iron mobilization from the soil was accompanied by a similar but delayed arsenic mobilization. Since arsenic sorbs to oxidized iron soil minerals, reductive dissolution of these minerals results in arsenic mobilization. Crushed limestone significantly reduced iron (to values below the detection limit of 0.01mg/L in most cases); however, arsenic was not removed to any significant extent.

  14. Development of construction materials using nano-silica and aggregates recycled from construction and demolition waste.

    PubMed

    Mukharjee, Bibhuti Bhusan; Barai, Sudhirkumar V

    2015-06-01

    The present work addresses the development of novel construction materials utilising commercial grade nano-silica and recycled aggregates retrieved from construction and demolition waste. For this, experimental work has been carried out to examine the influence of nano-silica and recycled aggregates on compressive strength, modulus of elasticity, water absorption, density and volume of voids of concrete. Fully natural and recycled aggregate concrete mixes are designed by replacing cement with three levels (0.75%, 1.5% and 3%) of nano-silica. The results of the present investigation depict that improvement in early days compressive strength is achieved with the incorporation of nano-silica in addition to the restoration of reduction in compressive strength of recycled aggregate concrete mixes caused owing to the replacement of natural aggregates by recycled aggregates. Moreover, the increase in water absorption and volume of voids with a reduction of bulk density was detected with the incorporation of recycled aggregates in place of natural aggregates. However, enhancement in density and reduction in water absorption and volume of voids of recycled aggregate concrete resulted from the addition of nano-silica. In addition, the results of the study reveal that nano-silica has no significant effect on elastic modulus of concrete.

  15. Environmental risks of HBCDD from construction and demolition waste: a contemporary and future issue.

    PubMed

    Nie, Zhiqiang; Yang, Ziliang; Fang, Yanyan; Yang, Yufei; Tang, Zhenwu; Wang, Xingrun; Die, Qingqi; Gao, Xingbao; Zhang, Fengsong; Wang, Qi; Huang, Qifei

    2015-11-01

    Hexabromocyclododecane (HBCDD), as one of the most widely used brominated flame retardants (BFRs), is of great concern globally because of its persistence in the environment and negative impacts on humans and animals. HBCDD has been mainly used in flame-retarded expanded (EPS) and extruded (XPS) polystyrene foams for insulation in the construction industry. Most of these products will become a part of the construction and demolition (C&D) waste at the end of their life cycle (30-50 years) which is typically disposed of into landfills or incineration. However, the recycling of this material takes quite a low share compared with landfill and incineration. Consequently, high environmental risks will exist in these disposal approaches due to the HBCDD in C&D waste. Currently, XPS or EPS products containing HBCDD in the construction industry have not reached the end of their life cycle in most countries. Relatively little attention has been paid to this emergency issue by either the government or public. Furthermore, C&D waste is most likely disposed of by direct dumping, simple stacking, or open burning in developing countries. Therefore, this paper highlights the global environmental risks of HBCDD from C&D waste. Areas of research for key problems of HBCDD contained in C&D waste are suggested to help control and finally eliminate the impact.

  16. The Hunters Point cogeneration project: Environmental justice in power plant siting

    SciTech Connect

    Kosloff, L.H.; Varanini, E.E. III

    1997-12-31

    The recent Hunters Point, San Francisco power plant siting process in California represents the first time that environmental justice has arisen as a major power plant siting issue. Intervenors argued that the siting process was racially and economically biased and were supported by leading environmental justice activists at the Golden Gate Law School`s Environmental Justice Clinic, a leading thinker in this field. The applicant argued that environmental justice charges cannot realistically be made against a modern natural-gas energy facility with state-of-the-art environmental controls. The applicant also argued that environmental justice concerns were fully addressed through the extensive environmental and socioeconomic review carried out by California Energy Commission staff. After extensive testimony and cross-examination, the Commission agreed with the applicant. This case has important lessons for companies that could be charged with environmental justice violations and environmental justice activists who must decide where to most effectively target their efforts. This paper reviews the proceeding and its lessons and makes recommendations regarding future applicability of environmental justice issues to the power generation sector. The authors represented the applicant in the facility siting proceeding.

  17. Emergency/disaster medical support in the restoration project for the Fukushima nuclear power plant accident.

    PubMed

    Morimura, Naoto; Asari, Yasushi; Yamaguchi, Yoshihiro; Asanuma, Kazunari; Tase, Choichiro; Sakamoto, Tetsuya; Aruga, Tohru

    2013-12-01

    The Fukushima Daiichi Nuclear Power Plant (1F) suffered a series of radiation accidents after the Great East Japan Earthquake on 11 March 2011. In a situation where halting or delaying restoration work was thought to translate directly into a very serious risk for the entire country, it was of the utmost importance to strengthen the emergency and disaster medical system in addition to radiation emergency medical care for staff at the frontlines working in an environment that posed a risk of radiation exposure and a large-scale secondary disaster. The Japanese Association for Acute Medicine (JAAM) launched the 'Emergency Task Force on the Fukushima Nuclear Power Plant Accident' and sent physicians to the local response headquarters. Thirty-four physicians were dispatched as disaster medical advisors, response guidelines in the event of multitudinous injury victims were created and revised and, along with execution of drills, coordination and advice was given on transport of patients. Forty-nine physicians acted as directing physicians, taking on the tasks of triage, initial treatment and decontamination. A total of 261 patients were attended to by the dispatched physicians. None of the eight patients with external contamination developed acute radiation syndrome. In an environment where the collaboration between organisations in the framework of a vertically bound government and multiple agencies and institutions was certainly not seamless, the participation of the JAAM as the medical academic organisation in the local system presented the opportunity to laterally integrate the physicians affiliated with the respective organisations from the perspective of specialisation.

  18. Riparian Planting Projects Completed within Asotin Creek Watershed : 2000-2002 Asotin Creek Riparian Final Report of Accomplishments.

    SciTech Connect

    Johnson, B. J.

    2002-01-01

    The Asotin County Conservation District (ACCD) is the primary entity coordinating habitat projects on both private and public lands within the Asotin Creek watershed. The watershed covers approximately 325 square miles in the Blue Mountains of southeastern Washington in Water Resource Inventory Area (WRIA) 35. According to Washington Department of Fish and Wildlife's (WDFW) Priority WRIA's by ''At-Risk Stock Significance Map'', it is the highest priority WRIA in southeastern Washington. Summer steelhead, bull trout, and Snake River spring chinook salmon which are listed under the Endangered Species Act (ESA), are present in the watershed. WDFW manages it as a Wild Steelhead Reserve; no hatchery fish have been released here since 1997. The ACCD has been working with landowners, Bonneville Power Administration (BPA), Washington State Conservation Commission (WCC), Natural Resource Conservation Service (NRCS), Washington Department of Fish and Wildlife (WDFW), U.S. Forest Service, Pomeroy Ranger District (USFS), Nez Perce Tribe, Washington Department of Ecology (DOE), National Marine Fisheries Service (NMFS), and U.S. Fish and Wildlife Service (USFWS) to address habitat projects in Asotin County. Local students, volunteers and Salmon Corps members from the Nez Perce Tribe have been instrumental in the success of the Model Watershed Program on Asotin Creek. ACCD began coordinating habitat projects in 1995 with the help of BPA funding. Approximately two hundred and seventy-six projects have been implemented as of 1999. The Washington State Legislature was successful in securing funding for threatened and endangered salmon and steelhead recovery throughout the State in 1998. While these issues were new to most of the State, the ACCD has been securing and administering funding for threatened salmonids since 1994. The Asotin Creek Riparian Planting 2000-053-00 and Asotin Creek Riparian Fencing 2000-054-00 teamed BPA and the Governor's Salmon Recovery Funding to plant

  19. Preserving the Manhattan Project

    NASA Astrophysics Data System (ADS)

    Kelly, Cynthia

    2014-03-01

    When future generations look back on the 20th century, few events will rival the harnessing of nuclear energy as a turning point in world history, science and society. Yet, the Department of Energy has not always embraced its Manhattan Project origins. The presentation will focus on the progress made over the last 20 years to preserve the properties and first-hand accounts that for decades have been threatened with demolition and indifference. Since the mid-1950s, most remaining Manhattan Project properties at the Los Alamos National Laboratory had been abandoned. Among them was a cluster of wooden buildings called the ``V Site.'' This is where scientists assembled the ``Gadget,'' the world's first atomic device tested on July 16, 1945. Regardless of its significance, the ``V Site'' buildings like all the rest were slated for demolition. The Advisory Council on Historic Preservation (ACHP) toured the properties in November 1998. Most could not believe that the world's first atomic bomb was designed in such humble structures. The properties were declared to be ``monumental in their lack of monumentality.'' A Save America's Treasures grant for 700,000 was awarded to restore the properties. To raise the required matching funds, I left the Federal government and soon founded the Atomic Heritage Foundation. The presentation will trace the progress made over the last decade to generate interest and support nationwide to preserve the Manhattan Project heritage. Saving both the physical properties and first-hand accounts of the men and women have been a priority. Perhaps our most significant achievement may be legislation now under consideration by Congress to create a Manhattan Project National Historical Park. Seventy years later, the Manhattan Project is finally getting the recognition it deserves.

  20. Entry Boreholes Summary Report for the Waste Treatment Plant Seismic Boreholes Project

    SciTech Connect

    Horner, Jake A.

    2007-02-28

    This report describes the 2006 fiscal year field activities associated with the installation of four cable-tool-drilled boreholes located within the boundary of the Waste Treatment Plant (WTP), DOE Hanford site, Washington. The cable-tool-drilled boreholes extend from surface to ~20 ft below the top of basalt and were utilized as cased entry holes for three deep boreholes (approximately 1400 ft) that were drilled to support the acquisition of sub-surface geophysical data, and one deep corehole (1400 ft) that was drilled to acquire continuous core samples from underlying basalt and sedimentary interbeds. The geophysical data acquired from these boreholes will be integrated into a seismic response model that will provide the basis for defining the seismic design criteria for the WTP facilities.

  1. Emergency/disaster medical support in the restoration project for the Fukushima nuclear power plant accident

    PubMed Central

    Morimura, Naoto; Asari, Yasushi; Yamaguchi, Yoshihiro; Asanuma, Kazunari; Tase, Choichiro; Sakamoto, Tetsuya; Aruga, Tohru

    2013-01-01

    The Fukushima Daiichi Nuclear Power Plant (1F) suffered a series of radiation accidents after the Great East Japan Earthquake on 11 March 2011. In a situation where halting or delaying restoration work was thought to translate directly into a very serious risk for the entire country, it was of the utmost importance to strengthen the emergency and disaster medical system in addition to radiation emergency medical care for staff at the frontlines working in an environment that posed a risk of radiation exposure and a large-scale secondary disaster. The Japanese Association for Acute Medicine (JAAM) launched the ‘Emergency Task Force on the Fukushima Nuclear Power Plant Accident’ and sent physicians to the local response headquarters. Thirty-four physicians were dispatched as disaster medical advisors, response guidelines in the event of multitudinous injury victims were created and revised and, along with execution of drills, coordination and advice was given on transport of patients. Forty-nine physicians acted as directing physicians, taking on the tasks of triage, initial treatment and decontamination. A total of 261 patients were attended to by the dispatched physicians. None of the eight patients with external contamination developed acute radiation syndrome. In an environment where the collaboration between organisations in the framework of a vertically bound government and multiple agencies and institutions was certainly not seamless, the participation of the JAAM as the medical academic organisation in the local system presented the opportunity to laterally integrate the physicians affiliated with the respective organisations from the perspective of specialisation. PMID:23184925

  2. Preliminary analysis of projected construction employment effects of building the defense waste processing facility at the Savannah River Plant

    SciTech Connect

    Garey, R.B.; Blair, L.M.; Craig, R.L.; Stevenson, W.

    1981-09-01

    This study estimates the probable effects of constructing the DWPF on the surrounding labor markets. Analyses are based on data from the local and regional labor markets, information from experts on local construction activities, information on the labor requirements of the Vogtle Power Plant (two nuclear reactors) being built by Georgia Power Company in Burke County, Georgia, and an econometric model of the construction labor market, based on several surveys of workers building three Tennessee Valley Authority nuclear power plants. The results of this study are reported in three parts. In Part I, completed in May 1980, we describe the 1979 (base year) employment levels within the local and regional labor markets surrounding SRP, from which most DWPF construction workers are likely to be drawn. In Part II, completed in June 1980, we define the four local sources of construction employment that will compete for craftsmen when DWPF is built. Also in Part II, most of the projected impacts of the DWPF reference immobilization alternative (one of several alternatives that may be chosen) are reported. Several construction schedules and labor demand scenarios for the reference alternative are considered. In Part III, completed in January 1981, most of the estimated impacts of the DWPF alternative referred to as the staged process alternative are reported. Several construction schedules and labor demand scenarios for this alternative are considered.

  3. Impact of an Educational Hands-on Project on the Antimicrobial, Antitumor and Anti-Inflammatory Properties of Plants on Portuguese Students’ Awareness, Knowledge, and Competences

    PubMed Central

    Azevedo, Maria-Manuel; Pinheiro, Céline; Dias, Alberto C.P.; Pinto-Ribeiro, Filipa; Baltazar, Fátima

    2015-01-01

    Promoting environmental and health education is crucial to allow students to make conscious decisions based on scientific criteria. The study is based on the outcomes of an Educational Project implemented with Portuguese students and consisted of several activities, exploring pre-existent Scientific Gardens at the School, aiming to investigate the antibacterial, antitumor and anti-inflammatory properties of plant extracts, with posterior incorporation in soaps and creams. A logo and a webpage were also created. The effectiveness of the project was assessed via the application of a questionnaire (pre- and post-test) and observations of the participants in terms of engagement and interaction with all individuals involved in the project. This project increased the knowledge about autochthonous plants and the potential medical properties of the corresponding plant extracts and increased the awareness about the correct design of scientific experiments and the importance of the use of experimental models of disease. The students regarded their experiences as exciting and valuable and believed that the project helped to improve their understanding and increase their interest in these subjects and in science in general. This study emphasizes the importance of raising students’ awareness on the valorization of autochthonous plants and exploitation of their medicinal properties. PMID:25711362

  4. Impact of an educational hands-on project on the antimicrobial, antitumor and anti-inflammatory properties of plants on Portuguese students' awareness, knowledge, and competences.

    PubMed

    Azevedo, Maria-Manuel; Pinheiro, Céline; Dias, Alberto C P; Pinto-Ribeiro, Filipa; Baltazar, Fátima

    2015-02-23

    Promoting environmental and health education is crucial to allow students to make conscious decisions based on scientific criteria. The study is based on the outcomes of an Educational Project implemented with Portuguese students and consisted of several activities, exploring pre-existent Scientific Gardens at the School, aiming to investigate the antibacterial, antitumor and anti-inflammatory properties of plant extracts, with posterior incorporation in soaps and creams. A logo and a webpage were also created. The effectiveness of the project was assessed via the application of a questionnaire (pre- and post-test) and observations of the participants in terms of engagement and interaction with all individuals involved in the project. This project increased the knowledge about autochthonous plants and the potential medical properties of the corresponding plant extracts and increased the awareness about the correct design of scientific experiments and the importance of the use of experimental models of disease. The students regarded their experiences as exciting and valuable and believed that the project helped to improve their understanding and increase their interest in these subjects and in science in general. This study emphasizes the importance of raising students' awareness on the valorization of autochthonous plants and exploitation of their medicinal properties.

  5. Impact of an educational hands-on project on the antimicrobial, antitumor and anti-inflammatory properties of plants on Portuguese students' awareness, knowledge, and competences.

    PubMed

    Azevedo, Maria-Manuel; Pinheiro, Céline; Dias, Alberto C P; Pinto-Ribeiro, Filipa; Baltazar, Fátima

    2015-03-01

    Promoting environmental and health education is crucial to allow students to make conscious decisions based on scientific criteria. The study is based on the outcomes of an Educational Project implemented with Portuguese students and consisted of several activities, exploring pre-existent Scientific Gardens at the School, aiming to investigate the antibacterial, antitumor and anti-inflammatory properties of plant extracts, with posterior incorporation in soaps and creams. A logo and a webpage were also created. The effectiveness of the project was assessed via the application of a questionnaire (pre- and post-test) and observations of the participants in terms of engagement and interaction with all individuals involved in the project. This project increased the knowledge about autochthonous plants and the potential medical properties of the corresponding plant extracts and increased the awareness about the correct design of scientific experiments and the importance of the use of experimental models of disease. The students regarded their experiences as exciting and valuable and believed that the project helped to improve their understanding and increase their interest in these subjects and in science in general. This study emphasizes the importance of raising students' awareness on the valorization of autochthonous plants and exploitation of their medicinal properties. PMID:25711362

  6. Lawrence Livermore National Laboratory Pre-project Rare Plant and Wildlife Surveys For the Pit 7 Drainage Diversion and Groundwater Extraction and Treatment Facility

    SciTech Connect

    Paterson, L; Woollett, J

    2007-07-17

    In January 2007, the Department of Energy (DOE) released the final Environmental Assessment for the Proposed Environmental Remediation at the Lawrence Livermore National Laboratory (LLNL) Site 300 Pit 7 Complex. At the same time, the Department of Toxic Substances Control (DTSC) released the final Negative Declaration and Initial Study covering the Pit 7 remediation. No substantial adverse effect on wildlife species of concern was anticipated from the project. However, it was proposed that wildlife surveys should be conducted prior to construction because species locations and breeding areas could potentially change by the time construction activities began. Although no known populations of rare or endangered/threatened plant species were known to occur within the project impact area at the time these documents were released, rare plants listed by the California Native Plant Society had been observed in the vicinity. As such, both DOE and DTSC proposed that plant surveys would be undertaken at the appropriate time of year to determine if rare plants would be impacted by project construction. This document provides the results of wildlife and rare plant surveys taken prior to the start of construction at the Pit 7 Complex.

  7. Correlation of drillhole and shaft logs. Waste Isolation Pilot Plant (WIPP) project, southeastern New Mexico

    SciTech Connect

    Jarolimek, L.; Timmer, M.J.; Powers, D.W.

    1983-03-01

    This report on stratigraphic correlations from drillhole and shaft data along a generally north-south section across the potential extent of underground excavations of the Waste Isolation Pilot Plant (WIPP) facility was prepared as part of the Site Validation Field Program Plan. The results provide (1) input for the report entitled ''Results of Site Validation Experiments,'' (2) input for other WIPP-related investigations, including the Design Validation Program, and (3) a framework for further underground activities at WIPP. In general, this correlation study confirmed previous findings, including: relatively high consistency of thickness and lateral continuity of all beds within the Salado Formation, especially in the host rock interval; gentle, generally south and southeastward dips/slopes of the host rock interval strata; close correspondence between stratigraphic data obtained from the present underground excavations and data derived from the previous investigative drillholes and shafts; and depositional origin of the undulations on the top of Marker Bed (MB) 139 and relatively small variation in its thickness (1.2 to 4.1 feet).

  8. The Ohio River Valley CO2 Storage Project AEP Mountaineer Plant, West Virginia Numerical Simulation and Risk Assessment Report

    SciTech Connect

    Neeraj Gupta

    2008-03-31

    A series of numerical simulations of carbon dioxide (CO{sub 2}) injection were conducted as part of a program to assess the potential for geologic sequestration in deep geologic reservoirs (the Rose Run and Copper Ridge formations), at the American Electric Power (AEP) Mountaineer Power Plant outside of New Haven, West Virginia. The simulations were executed using the H{sub 2}O-CO{sub 2}-NaCl operational mode of the Subsurface Transport Over Multiple Phases (STOMP) simulator (White and Oostrom, 2006). The objective of the Rose Run formation modeling was to predict CO{sub 2} injection rates using data from the core analysis conducted on the samples. A systematic screening procedure was applied to the Ohio River Valley CO{sub 2} storage site utilizing the Features, Elements, and Processes (FEP) database for geological storage of CO{sub 2} (Savage et al., 2004). The objective of the screening was to identify potential risk categories for the long-term geological storage of CO{sub 2} at the Mountaineer Power Plant in New Haven, West Virginia. Over 130 FEPs in seven main classes were assessed for the project based on site characterization information gathered in a geological background study, testing in a deep well drilled on the site, and general site conditions. In evaluating the database, it was apparent that many of the items were not applicable to the Mountaineer site based its geologic framework and environmental setting. Nine FEPs were identified for further consideration for the site. These FEPs generally fell into categories related to variations in subsurface geology, well completion materials, and the behavior of CO{sub 2} in the subsurface. Results from the screening were used to provide guidance on injection system design, developing a monitoring program, performing reservoir simulations, and other risk assessment efforts. Initial work indicates that the significant FEPs may be accounted for by focusing the storage program on these potential issues. The

  9. ALARA Design Review for the Resumption of the Plutonium Finishing Plant (PFP) Cementation Process Project Activities

    SciTech Connect

    DAYLEY, L.

    2000-06-14

    The requirements for the performance of radiological design reviews are codified in 10CFR835, Occupational Radiation Protection. The basic requirements for the performance of ALARA design reviews are presented in the Hanford Site Radiological Control Manual (HSRCM). The HSRCM has established trigger levels requiring radiological reviews of non-routine or complex work activities. These requirements are implemented in site procedures HNF-PRO-1622 and 1623. HNF-PRO-1622 Radiological Design Review Process requires that ''radiological design reviews [be performed] of new facilities and equipment and modifications of existing facilities and equipment''. In addition, HNF-PRO-1623 Radiological Work Planning Process requires a formal ALARA Review for planned activities that are estimated to exceed 1 person-rem total Dose Equivalent (DE). The purpose of this review is to validate that the original design for the PFP Cementation Process ensures that the principles of ALARA (As Low As Reasonably Achievable) were included in the original project design. That is, that the design and operation of existing Cementation Process equipment and processes allows for the minimization of personnel exposure in its operation, maintenance and decommissioning and that the generation of radioactive waste is kept to a minimum.

  10. DC-SQUID Quantum Non-Demolition Readout of Superconducting Flux Qubits

    NASA Astrophysics Data System (ADS)

    Harmans, Kees

    2011-03-01

    Extracting state information from a quantum system is a central theme in quantum mechanics. As the process of state extraction by a detector implies system-detector entanglement, reverse action from the detector onto the quantum object can not be avoided. Consequently, detectors that minimise this back action are crucial. For superconducting flux qubits commonly a DC-SQUID detector is used, either in an AC dispersive scheme or in a switching mode. The latter can be by AC bifurcation or by direct DC switching. The DC approach combines simplicity in use with complexity in dynamical behaviour. This complexity results from the fast Josephson phase dynamics and the significant generation of quasi-particles in the dissipative detector ON-state. This gave rise to the long-standing belief that it can not act as a ``good'' detector. This includes it to fail as a Quantum Non-Demolition (QND) detector, i.e. the preservation of the state of the quantum object after a state readout. In a recent experiment for relatively weak qubit-SQUID interaction strength we investigated the detection properties of such a DC-switching SQUID, finding a remarkably good QND fidelity. This was achieved by shunting the SQUID by a low-value resistor, thus strongly suppressing the generation of quasi-particles. Also the detector ON-time was minimised to a few tens of ns using a nearby cryogenic amplifier. The QND-ness was obtained from measuring the correlation between two successive readouts, and found to reach 75% QND fidelity. The weak qubit-detector interaction leads to a limited readout contrast. We will discuss the results as well as its consequences, including the potential for combining high contrast and good QND fidelity.

  11. Challenges in automatic sorting of construction and demolition waste by hyperspectral imaging

    NASA Astrophysics Data System (ADS)

    Hollstein, Frank; Cacho, Íñigo; Arnaiz, Sixto; Wohllebe, Markus

    2016-05-01

    EU-28 countries currently generate 460 Mt/year of construction and demolition waste (C&DW) and the generation rate is expected to reach around 570 Mt/year between 2025 and 2030. There is great potential for recycling C&DW materials since they are massively produced and content valuable resources. But new C&DW is more complex than existing one and there is a need for shifting from traditional recycling approaches to novel recycling solutions. One basic step to achieve this objective is an improvement in (automatic) sorting technology. Hyperspectral Imaging is a promising candidate to support the process. However, the industrial distribution of Hyperspectral Imaging in the C&DW recycling branch is currently insufficiently pronounced due to high investment costs, still insufficient robustness of optical sensor hardware in harsh ambient conditions and, because of the need of sensor fusion, not well-engineered special software methods to perform the (on line) sorting tasks. Thereby frame rates of over 300 Hz are needed for a successful sorting result. Currently the biggest challenges with regard to C&DW detection cover the need of overlapping VIS, NIR and SWIR hyperspectral images in time and space, in particular for selective recognition of contaminated particles. In the study on hand a new approach for hyperspectral imagers is presented by exploiting SWIR hyperspectral information in real time (with 300 Hz). The contribution describes both laboratory results with regard to optical detection of the most important C&DW material composites as well as a development path for an industrial implementation in automatic sorting and separation lines. The main focus is placed on the closure of the two recycling circuits "grey to grey" and "red to red" because of their outstanding potential for sustainability in conservation of construction resources.

  12. Co-composting of Beef Cattle Feedlot Manure with Construction and Demolition Waste.

    PubMed

    Hao, Xiying; Hill, Brett; Caffyn, Pam; Travis, Greg; Olson, Andrew F; Larney, Francis J; McAllister, Tim; Alexander, Trevor

    2014-09-01

    With increased availability of dried distillers' grains with solubles (DDGS) as cattle feed and the need to recycle organic wastes, this research investigated the feasibility of co-composting DDGS cattle feedlot manure with construction and demolition (C&D) waste. Manure was collected from cattle fed a typical western Canadian finishing diet (CK) of 860 g rolled barley ( L.) grain, 100 g barley silage, and 40 g vitamin and mineral supplement kg dry matter (DM) and from cattle fed the same diet but (DG manure) with 300 g kg DM barley grain being replaced by DDGS. The CK and DG manures were co-composted with and without C&D waste in 13 m bins. Compost materials were turned on Days 14, 37, and 64, and terminated on Day 99. Adding C&D waste led to higher compost temperatures (0.4 to 16.3°C, average 7.2°C) than manure alone. Final composts had similar total C, total N, C/N ratios, and water-extractable K, Mg, and NO content across all treatments. However, adding C&D waste increased δC, δN, water-extractable SO, and Ca contents and decreased pH, total P (TP), water-extractable C, N, and P and most volatile fatty acids (VFA). The higher C&D compost temperatures should reduce pathogens while reduced VFA content should reduce odors. When using the final compost product, the increased SO and reduced TP and available N and P content in C&D waste compost should be taken into consideration. Increased S content in C&D compost may be beneficial for some crops grown on S-deficient soils. PMID:25603264

  13. Developments in life cycle assessment applied to evaluate the environmental performance of construction and demolition wastes.

    PubMed

    Bovea, M D; Powell, J C

    2016-04-01

    This paper provides a review of the literature that applies the life cycle assessment (LCA) methodology to the assessment of the environmental performance of the life cycle of construction and demolition waste (CDW) management systems. This article is focused on generating a general mapping of the literature and on identifying the best practices in compliance with LCA framework and proposing directions for future LCA studies in this field. The temporal evolution of the research in this field and the aim of the studies have grown in parallel with the legal framework related to waste and energy efficiency of buildings. Most studies have been published in Europe, followed by USA. Asia and Australia, being at an incipient application stage to the rest of the world. Topics related to "LCA of buildings, including their EoL" and "LCA of general CDW management strategies" are the most frequently analysed, followed by "LCA of EoL of construction elements" and "LCA of natural material vs recycled material". Regarding the strategies, recycling off-site and incineration, both combined with landfill for the rejected fractions, are the most commonly applied. Re-use or recycling on-site is the strategy least applied. The key aspect when LCA is applied to evaluate CDW management systems is the need to normalise which processes to include in the system boundary and the functional unit, the use of inventory data adapted to the context of the case study and the definition of a common set of appropriate impact assessment categories. Also, it is important to obtain results disaggregated by unit processes. This will allow the comparison between case studies. PMID:26919970

  14. Developments in life cycle assessment applied to evaluate the environmental performance of construction and demolition wastes.

    PubMed

    Bovea, M D; Powell, J C

    2016-04-01

    This paper provides a review of the literature that applies the life cycle assessment (LCA) methodology to the assessment of the environmental performance of the life cycle of construction and demolition waste (CDW) management systems. This article is focused on generating a general mapping of the literature and on identifying the best practices in compliance with LCA framework and proposing directions for future LCA studies in this field. The temporal evolution of the research in this field and the aim of the studies have grown in parallel with the legal framework related to waste and energy efficiency of buildings. Most studies have been published in Europe, followed by USA. Asia and Australia, being at an incipient application stage to the rest of the world. Topics related to "LCA of buildings, including their EoL" and "LCA of general CDW management strategies" are the most frequently analysed, followed by "LCA of EoL of construction elements" and "LCA of natural material vs recycled material". Regarding the strategies, recycling off-site and incineration, both combined with landfill for the rejected fractions, are the most commonly applied. Re-use or recycling on-site is the strategy least applied. The key aspect when LCA is applied to evaluate CDW management systems is the need to normalise which processes to include in the system boundary and the functional unit, the use of inventory data adapted to the context of the case study and the definition of a common set of appropriate impact assessment categories. Also, it is important to obtain results disaggregated by unit processes. This will allow the comparison between case studies.

  15. Projected range contractions of European protected oceanic montane plant communities: focus on climate change impacts is essential for their future conservation.

    PubMed

    Hodd, Rory L; Bourke, David; Skeffington, Micheline Sheehy

    2014-01-01

    Global climate is rapidly changing and while many studies have investigated the potential impacts of this on the distribution of montane plant species and communities, few have focused on those with oceanic montane affinities. In Europe, highly sensitive bryophyte species reach their optimum occurrence, highest diversity and abundance in the north-west hyperoceanic regions, while a number of montane vascular plant species occur here at the edge of their range. This study evaluates the potential impact of climate change on the distribution of these species and assesses the implications for EU Habitats Directive-protected oceanic montane plant communities. We applied an ensemble of species distribution modelling techniques, using atlas data of 30 vascular plant and bryophyte species, to calculate range changes under projected future climate change. The future effectiveness of the protected area network to conserve these species was evaluated using gap analysis. We found that the majority of these montane species are projected to lose suitable climate space, primarily at lower altitudes, or that areas of suitable climate will principally shift northwards. In particular, rare oceanic montane bryophytes have poor dispersal capacity and are likely to be especially vulnerable to contractions in their current climate space. Significantly different projected range change responses were found between 1) oceanic montane bryophytes and vascular plants; 2) species belonging to different montane plant communities; 3) species categorised according to different biomes and eastern limit classifications. The inclusion of topographical variables in addition to climate, significantly improved the statistical and spatial performance of models. The current protected area network is projected to become less effective, especially for specialised arctic-montane species, posing a challenge to conserving oceanic montane plant communities. Conservation management plans need significantly

  16. Projected range contractions of European protected oceanic montane plant communities: focus on climate change impacts is essential for their future conservation.

    PubMed

    Hodd, Rory L; Bourke, David; Skeffington, Micheline Sheehy

    2014-01-01

    Global climate is rapidly changing and while many studies have investigated the potential impacts of this on the distribution of montane plant species and communities, few have focused on those with oceanic montane affinities. In Europe, highly sensitive bryophyte species reach their optimum occurrence, highest diversity and abundance in the north-west hyperoceanic regions, while a number of montane vascular plant species occur here at the edge of their range. This study evaluates the potential impact of climate change on the distribution of these species and assesses the implications for EU Habitats Directive-protected oceanic montane plant communities. We applied an ensemble of species distribution modelling techniques, using atlas data of 30 vascular plant and bryophyte species, to calculate range changes under projected future climate change. The future effectiveness of the protected area network to conserve these species was evaluated using gap analysis. We found that the majority of these montane species are projected to lose suitable climate space, primarily at lower altitudes, or that areas of suitable climate will principally shift northwards. In particular, rare oceanic montane bryophytes have poor dispersal capacity and are likely to be especially vulnerable to contractions in their current climate space. Significantly different projected range change responses were found between 1) oceanic montane bryophytes and vascular plants; 2) species belonging to different montane plant communities; 3) species categorised according to different biomes and eastern limit classifications. The inclusion of topographical variables in addition to climate, significantly improved the statistical and spatial performance of models. The current protected area network is projected to become less effective, especially for specialised arctic-montane species, posing a challenge to conserving oceanic montane plant communities. Conservation management plans need significantly

  17. SOLERAS - Solar Energy Water Desalination Project: Catalytic. System design final report. Volume 2. Preliminary pilot plant design

    SciTech Connect

    Not Available

    1986-01-01

    The preliminary design of a solar water desalination pilot plant is presented. Pilot plant drawings and process descriptions are provided. Use of solar and wind energy are discussed. Testing, performance and cost of the pilot plant are studied. (BCS)

  18. Observation and Modeling of Infrasound Signals Generated By Rocket Motor Tests and Rocket Motor Demolitions in the Western US

    NASA Astrophysics Data System (ADS)

    Park, J.; Hayward, C.; Stump, B. W.

    2014-12-01

    Ground-truth for infrasonic sources enables the documentation of time-varying atmospheric effects on infrasound observations. The associated source and observation data provide a basis for assessing current atmospheric models and estimating their contribution to infrasound detection and location. In this study, we utilize both seismic and acoustic data recorded at USArray Transportable Array (TA) stations and additional regional infrasound arrays in Utah and Nevada. Ground truth consists of a total of 25 rocket motor tests (static rocket motor burn tests) and 6 rocket motor demolitions in Utah for the time period from 2003 to 2013. Characteristics of infrasound signals generated by the rocket motor tests and rocket body demolitions are compared. The typical signal frequency band from the rocket motor tests is 5-10 Hz with durations of up to 60 seconds, while those from rocket body demolitions have relatively shorter durations (10 seconds) and lower frequencies (1-5 Hz). The distributions of stations that detect signals are quite variable in terms of both distance and azimuth and dependent on atmospheric conditions. Infrasound amplitudes document strong energy attenuation with range that must be quantified in order to assess the source strength. Ray tracing and parabolic equation (PE) modeling were conducted utilizing the ground-to-space (G2S) atmospheric specifications at the time of each event, in order to understand the predictability of the models and assess their utility in estimating amplitudes as a function of range. This unique dataset quantifies the contribution of temporal atmospheric conditions to infrasound detection and documents the predictive capabilities of current atmospheric model.

  19. HIV prevention while the bulldozers roll: exploring the effect of the demolition of Goa's red-light area.

    PubMed

    Shahmanesh, Maryam; Wayal, Sonali; Andrew, Gracy; Patel, Vikram; Cowan, Frances M; Hart, Graham

    2009-08-01

    Interventions targeting sex-workers are pivotal to HIV prevention in India. Community mobilisation is considered by the National AIDS Control Programme to be an integral component of this strategy. Nevertheless societal factors, and specifically policy and legislation around sex-work, are potential barriers to widespread collectivisation and empowerment of sex-workers. Between November 2003 and December 2005 we conducted participatory observation and rapid ethnographic mapping with several hundred brief informant interviews, in addition to 34 semi-structured interviews with key-informants, 16 in-depth interviews with female sex-workers, and 3 focus-group-discussions with clients and mediators. This provides a detailed examination of the demolition of Baina, one of India's large red-light areas, in 2004, and one of the first accounts of the effect of dismantling the red-light area on the organisation of sex-work and sex-workers' sexual risk. The results suggest that the concentrated and homogeneous brothel-based sex-work environment rapidly evolved into heterogeneous, clandestine and dispersed modes of operation. The social context of sex-work that emerged from the dust of the demolition was higher risk and less conducive to HIV prevention. The demolition acted as a negative structural intervention; a catastrophic event that fragmented sex-workers' collective identity and agency and rendered them voiceless and marginalised. The findings suggest that an abolitionist approach to sex-work and legislation or policy that either criminalises this large group of women, or renders them as invisible victims, will increase the stigma and exclusion they experience. For the targeted HIV prevention approaches advocated by the National AIDS Control Programme to be effective, there is a need for legislation and policy that supports sex-workers' agency and self-organisation and enables them to create a safer working environment for themselves.

  20. Neighbourhood demolition, relocation and health. A qualitative longitudinal study of housing-led urban regeneration in Glasgow, UK

    PubMed Central

    Egan, Matt; Lawson, Louise; Kearns, Ade; Conway, Ellie; Neary, Joanne

    2015-01-01

    We conducted a qualitative longitudinal study to explore how adult residents of disadvantaged urban neighbourhoods (Glasgow, UK) experienced neighbourhood demolition and relocation. Data from 23 households was collected in 2011 and 2012. Some participants described moves to new or improved homes in different neighbourhoods as beneficial to their and their families’ wellbeing. Others suggested that longstanding illnesses and problems with the new home and/or neighbourhood led to more negative experiences. Individual-level contextual differences, home and neighbourhood-level factors and variations in intervention implementation influence the experiences of residents involved in relocation programmes. PMID:25814338

  1. BioProject Number PRJNA254501: Total of 190 sampled plants from Physalis philadelphica (tomatillo) genome sequencing BioSamples SAMN02904339-SAMN02904528

    Technology Transfer Automated Retrieval System (TEKTRAN)

    This BioProject consists of raw genotyping-by-sequencing data collected in 96-plex format on an Illumina HiSeq 2000 sequencing system. There were 190 sampled plants from Physalis philadelphica (tomatillo). The experiment resulted in the development of more than 77,000 single nucleotide polymorphism ...

  2. One System Integrated Project Team: Retrieval And Delivery Of The Hanford Tank Wastes For Vitrification In The Waste Treatment Plant

    SciTech Connect

    Harp, Benton J.; Kacich, Richard M.; Skwarek, Raymond J.

    2012-12-20

    The One System Integrated Project Team (IPT) was formed in late 2011 as a way for improving the efficiency of delivery and treatment of highly radioactive waste stored in underground tanks at the U.S. Department of Energy's (DOE's) 586-square-mile Hanford Site in southeastern Washington State. The purpose of the One System IPT is to improve coordination and integration between the Hanford's Waste Treatment Plant (WTP) contractor and the Tank Operations Contractor (TOC). The vision statement is: One System is a WTP and TOC safety conscious team that, through integrated management and implementation of risk-informed decision and mission-based solutions, will enable the earliest start of safe and efficient treatment of Hanford's tank waste, to protect the Columbia River, environment and public. The IPT is a formal collaboration between Bechtel National, Inc. (BNI), which manages design and construction of the WTP for the U.S. Department of Energy's Office of River Protection (DOEORP), and Washington River Protection Solutions (WRPS), which manages the TOC for ORP. More than fifty-six (56) million gallons of highly radioactive liquid waste are stored in one hundred seventy-seven (177) aging, underground tanks. Most of Hanford's waste tanks - one hundred forty-nine (149) of them - are of an old single-shell tank (SST) design built between 1944 and 1964. More than sixty (60) of these tanks have leaked in the past, releasing an estimated one million gallons of waste into the soil and threatening the nearby Columbia River. There are another twenty-eight (28) new double-shelled tanks (DSTs), built from 1968 to 1986, that provide greater protection to the environment. In 1989, DOE, the U.S. Environmental Protection Agency (EPA), and the Washington State Department of Ecology (Ecology) signed a landmark agreement that required Hanford to comply with federal and state environmental standards. It also paved the way for agreements that set deadlines for retrieving the tank

  3. One System Integrated Project Team: Retrieval and Delivery of Hanford Tank Wastes for Vitrification in the Waste Treatment Plant - 13234

    SciTech Connect

    Harp, Benton J.; Kacich, Richard M.; Skwarek, Raymond J.

    2013-07-01

    The One System Integrated Project Team (IPT) was formed in late 2011 as a way for improving the efficiency of delivery and treatment of highly radioactive waste stored in underground tanks at the U.S. Department of Energy's (DOE's) 586-square-mile Hanford Site in southeastern Washington State. The purpose of the One System IPT is to improve coordination and integration between the Hanford's Waste Treatment Plant (WTP) contractor and the Tank Operations Contractor (TOC). The vision statement is: One System is a WTP and TOC safety-conscious team that, through integrated management and implementation of risk-informed decision and mission-based solutions, will enable the earliest start of safe and efficient treatment of Hanford's tank waste, to protect the Columbia River, environment and public. The IPT is a formal collaboration between Bechtel National, Inc. (BNI), which manages design and construction of the WTP for the U.S. Department of Energy's Office of River Protection (DOEORP), and Washington River Protection Solutions (WRPS), which manages the TOC for ORP. More than fifty-six (56) million gallons of highly radioactive liquid waste are stored in one hundred seventy-seven (177) aging, underground tanks. Most of Hanford's waste tanks - one hundred forty-nine (149) of them - are of an old single-shell tank (SST) design built between 1944 and 1964. More than sixty (60) of these tanks have leaked in the past, releasing an estimated one million gallons of waste into the soil and threatening the nearby Columbia River. There are another twenty-eight (28) new double-shelled tanks (DSTs), built from 1968 to 1986, that provide greater protection to the environment. In 1989, DOE, the U.S. Environmental Protection Agency (EPA), and the Washington State Department of Ecology (Ecology) signed a landmark agreement that required Hanford to comply with federal and state environmental standards. It also paved the way for agreements that set deadlines for retrieving the tank

  4. A study of toxic emissions from a coal-fired power plant utilizing an ESP while demonstrating the ICCT CT-121 FGD Project. Final report

    SciTech Connect

    Not Available

    1994-06-16

    The US Department of Energy is performing comprehensive assessments of toxic emissions from eight selected coal-fired electric utility units. This program responds to the Clean Air Act Amendments of 1990, which require the US Environmental Protection Agency (EPA) to evaluate emissions of hazardous air pollutants (HAPs) from electric utility power plants for Potential health risks. The resulting data will be furnished to EPA utility power plants and health risk determinations. The assessment of emissions involves the collection and analysis of samples from the major input, process, and output streams of each of the eight power plants for selected hazardous Pollutants identified in Title III of the Clean Air Act. Additional goals are to determine the removal efficiencies of pollution control subsystems for these selected pollutants and the Concentrations associated with the particulate fraction of the flue gas stream as a function of particle size. Material balances are being performed for selected pollutants around the entire power plant and several subsystems to identify the fate of hazardous substances in each utility system. Radian Corporation was selected to perform a toxics assessment at a plant demonstrating an Innovative Clean Coal Technology (ICCT) Project. The site selected is Plant Yates Unit No. 1 of Georgia Power Company, which includes a Chiyoda Thoroughbred-121 demonstration project.

  5. Tritium research laboratory cleanup and transition project final report

    SciTech Connect

    Johnson, A.J.

    1997-02-01

    This Tritium Research Laboratory Cleanup and Transition Project Final Report provides a high-level summary of this project`s multidimensional accomplishments. Throughout this report references are provided for in-depth information concerning the various topical areas. Project related records also offer solutions to many of the technical and or administrative challenges that such a cleanup effort requires. These documents and the experience obtained during this effort are valuable resources to the DOE, which has more than 1200 other process contaminated facilities awaiting cleanup and reapplication or demolition.

  6. Nanomaterials in construction and demolition - how can we assess the risk if we don't know where they are?

    NASA Astrophysics Data System (ADS)

    Jones, Wendy; Gibb, Alistair; Goodier, Chris; Bust, Phil; Jin, Jie; Song, Mo

    2015-05-01

    This research, funded by the Institution of Occupational Safety and Health in the United Kingdom, has used a combination of literature review, web searching and unstructured interviews with a range of industry professionals to compile a list of products used in construction and the built environment which might contain nanomaterials. Samples of these products have been analysed using Scanning Electron Microscopy and Energy Dispersive X- Ray Spectroscopy to investigate whether nanomaterials are actually present and to what extent. Preliminary results of this testing are presented here. It is concluded that there is a discrepancy between the academic literature and the reality regarding the current application of nanomaterials in the construction industry and the built environment. There are also inaccuracies and deficiencies in the information provided by manufacturers which makes it difficult to accurately assess the location and application of nanomaterials within the industry. Further testing is planned to evaluate the risk of nanoparticle release from nano-enabled building products at their end of life by reproducing common demolition and recycling processes such as crushing, grinding, burning and melting. Results of this will form the basis of practical guidance for the construction, demolition and recycling industries to help them identify where particular protection or control measures may be appropriate as well as providing reassurance where no additional action is required.

  7. Closed-loop recycling of construction and demolition waste in Germany in view of stricter environmental threshold values.

    PubMed

    Weil, Marcel; Jeske, Udo; Schebek, Liselotte

    2006-06-01

    Recycling of construction and demolition waste contributes decisively to the saving of natural mineral resources. In Germany, processed mineral construction and demolition waste from structural engineering is used nearly exclusively in civil engineering (earthwork and road construction sector) as open-loop recycling. Due to the planned stricter limit values for the protection of soil and water, however, this recycling path in civil engineering may no longer be applicable in the future. According to some new guidelines and standards adopted recently, recycled aggregates may also be used for concrete production in the structural engineering sector (closed-loop recycling). Wastes from the structural engineering sector can thus be kept in a closed cycle, and their disposal on a landfill can be avoided. The present report focuses on the determination of maximum waste volumes that may be handled by this new recycling option. Potential adverse effects on the saving of resources and climate protection have been analysed. For this purpose, materials flow analysis and ecobalancing methods have been used.

  8. Assessing metal contamination from construction and demolition (C&D) waste used to infill wetlands: using Deroceras reticulatum (Mollusca: Gastropoda).

    PubMed

    Staunton, John A; Mc Donnell, Rory J; Gormally, Michael J; Williams, Chris D; Henry, Tiernan; Morrison, Liam

    2014-11-01

    Large quantities of construction and demolition waste (C&D) are produced globally every year, with little known about potential environmental impacts. In the present study, the slug, Deroceras reticulatum (Mollusca: Gastropoda) was used as the first biomonitor of metals (Ag, As, Ba, Cd, Co, Cr, Cu, Mn, Mo, Ni, Pb, Sb, Se, Ti, Tl, V and Zn) on wetlands post infilling with construction and demolition (C&D) waste. The bioaccumulation of As, Ba, Cd, Co, Sb, Se and Tl were found to be significantly elevated in slugs collected on C&D waste when compared to unimproved pastures (control sites), while Mo, Se and Sr had significantly higher concentrations in slugs collected on C&D waste when compared to known contaminated sites (mining locations), indicating the potential hazardous nature of C&D waste to biota. Identifying exact sources for these metals within the waste can be problematic, due to its heterogenic nature. Biomonitors are a useful tool for future monitoring and impact studies, facilitating policy makers and regulations in other countries regarding C&D waste infill. In addition, improving separation of C&D waste to allow increased reuse and recycling is likely to be effective in reducing the volume of waste being used as infill, subsequently decreasing potential metal contamination.

  9. Environmental regulation of plant gene expression: an RT-qPCR laboratory project for an upper-level undergraduate biochemistry or molecular biology course.

    PubMed

    Eickelberg, Garrett J; Fisher, Alison J

    2013-01-01

    We present a novel laboratory project employing "real-time" RT-qPCR to measure the effect of environment on the expression of the FLOWERING LOCUS C gene, a key regulator of floral timing in Arabidopsis thaliana plants. The project requires four 3-hr laboratory sessions and is aimed at upper-level undergraduate students in biochemistry or molecular biology courses. The project provides students with hands-on experience with RT-qPCR, the current "gold standard" for gene expression analysis, including detailed data analysis using the common 2-ΔΔCT method. Moreover, it provides a convenient starting point for many inquiry-driven projects addressing diverse questions concerning ecological biochemistry, naturally occurring genetic variation, developmental biology, and the regulation of gene expression in nature.

  10. Management and integration of engineering and construction activities: Lessons learned from the AP1000{sup R} nuclear power plant China project

    SciTech Connect

    McCullough, M. C.; Ebeling-Koning, D.; Evans, M. C.

    2012-07-01

    The lessons learned during the early phase of design engineering and construction activities for the AP1000 China Project can be applied to any project involving multiple disciplines and multiple organizations. Implementation of a first-of-a-kind design to directly support construction activities utilizing resources assigned to design development and design delivery creates challenges with prioritization of activities, successful closure of issues, and communication between site organizations and the home office. To ensure successful implementation, teams were assigned and developed to directly support construction activities including prioritization of activities, site communication and ensuring closure of site emergent issues. By developing these teams, the organization is better suited to meet the demands of the construction schedule while continuing with design evolution of a standard plant and engineering delivery for multiple projects. For a successful project, proper resource utilization and prioritization are key for overcoming obstacles and ensuring success of the engineering organization. (authors)

  11. Waste Management Plan for the Lower East Fork Poplar Creek Remedial Action Project Oak Ridge, Tennessee

    SciTech Connect

    1996-08-01

    The Lower East Fork Poplar Creek (LEFPC) Remedial Action project will remove mercury-contaminated soils from the floodplain of LEFPC, dispose of these soils at the Y-12 Landfill V, and restore the affected floodplain upon completion of remediation activities. This effort will be conducted in accordance with the Record of Decision (ROD) for LEFPC as a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) action. The Waste Management Plan addresses management and disposition of all wastes generated during the remedial action for the LEFPC Project Most of the solid wastes will be considered to be sanitary or construction/demolition wastes and will be disposed of at existing Y-12 facilities for those types of waste. Some small amounts of hazardous waste are anticipated, and the possibility of low- level or mixed waste exists (greater than 35 pCi/g), although these are not expected. Liquid wastes will be generated which will be sanitary in nature and which will be capable of being disposed 0214 of at the Oak Ridge Sewage Treatment Plant.

  12. Quality assurance project plan for the Chestnut Ridge Fly Ash Pond Stabilization Project at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    SciTech Connect

    1996-07-01

    The Chestnut Ridge Fly Ash Pond Stabilization (CRFAPS) Project will stabilize a 19-m-high (62-ft-high) earthen embankment across Upper McCoy Branch situated along the southern slope of Chestnut Ridge. This task will be accomplished by raising the crest of the embankment, reinforcing the face of the embankment, removing trees from the face and top of the embankment, and repairing the emergency spillway. The primary responsibilities of the team members are: Lockheed Martin Energy Systems, Inc., (Energy Systems) will be responsible for project integration, technical support, Title 3 field support, environmental oversight, and quality assurance (QA) oversight of the project; Foster Wheeler Environmental Corporation (FWENC) will be responsible for design and home office Title 3 support; MK-Ferguson of Oak Ridge Company (MK-F) will be responsible for health and safety, construction, and procurement of construction materials. Each of the team members has a QA program approved by the US Department of Energy (DOE) Oak Ridge Operations. This project-specific QA project plan (QAPP), which is applicable to all project activities, identifies and integrates the specific QA requirements from the participant`s QA programs that are necessary for this project.

  13. Automatic chemical monitoring in the composition of functions performed by the unit level control system in the new projects of nuclear power plant units

    NASA Astrophysics Data System (ADS)

    Denisova, L. G.; Khrennikov, N. N.

    2014-08-01

    The article presents information on the state of regulatory framework and development of a subsystem for automated chemical monitoring of water chemistries in the primary and secondary coolant circuits used as part of the automatic process control system in new projects of VVER reactor-based nuclear power plant units. For the strategy of developing and putting in use the water chemistry-related part of the automated process control system within the standard AES-2006 nuclear power plant project to be implemented, it is necessary to develop regulatory documents dealing with certain requirements imposed on automatic water chemistry monitoring systems in accordance with the requirements of federal codes and regulations in the field of using atomic energy.

  14. Impacts to Project from {sup 99}Tc Contamination on the K-25 / K-27 Decontamination and Decommissioning Project

    SciTech Connect

    Larson, Paul; Boris, Greg

    2008-01-15

    to quickly flow to the latter stages of the cascade (also known as the 'top of the cascade'). The removal of certain undesired lighter gases was done in the purge cascades. Technetium forms volatile fluoride compounds under the conditions used to chemically convert uranium oxide (UO{sub 2}) in reactor tails to UF{sub 6}. Thus, Tc vaporized and flowed with the process gas in the cascade. However, because Tc is much lighter than U, it rapidly migrated to the top of the cascade and into the purge cascades. Most of the Tc is thought to be located in the purge cascade equipment. The purge cascade equipment is generally located in Area 1 of K-25 and Areas 7 and 8 in K-27. Fourteen building units are now known or believed to be contaminated with {sup 99}Tc. During the demolition activities, the equipment used is expected to become contaminated. To prevent cross-contamination of other wastes with {sup 99}Tc, separate equipment will be used for the southern end of the K-25 east wing. This same demolition equipment will be employed in K-27 to help minimize equipment decontamination efforts at the end of the project. However, because of this sequential schedule, any delays for demolition of the K-25 Building will adversely impact the schedule for K-27. The {sup 99}Tc contamination of the K-25 and K-27 D and D Project is now better known, but considerable planning will still be needed to control migration of this material to meet radiological controls and waste management limits. Since {sup 99}Tc has been an emerging issue over the last decade, the measurement, controls, and ultimately the impacts (e.g., cost and schedule) to the project have caused a significant increase in the planning effort for the D and D of these facilities and are expected to increase the ultimate cost of remediation. The cost increase will not be known until the planning effort is restarted (probably in FY 08-09). The contamination controls to be put in place to minimize the spread of this contaminant

  15. Methodology of environmental diagnosis for construction and demolition waste landfills: a tool for planning and making decisions.

    PubMed

    Garrido, E; Calvo, F; Ramos, A F; Zamorano, M

    2005-11-01

    Current legislation in the European Union regarding landfills provides measures, procedures and guidance to prevent or reduce, insofar as possible, negative effects on the environment. This means that Member States must take measures so that landfills cannot operate unless the operator first presents a plan for the site, which includes the implementation of improvements considered necessary by the engineer for compliance with regulations. Researchers at the University of Granada have developed a method to ascertain the degree of environmental impact that a construction and demolition waste landfill may produce on its immediate surroundings. This methodology is based on environmental indexes; its objective is to give crucial information concerning possible environmental problems produced by a landfill. The data thus obtained will permit the elaboration of guidelines for improvements in the location, design, and operation of landfills, or in extreme cases, their dosing, sealing, and rehabilitation.

  16. Construction demolition wastes, Waelz slag and MSWI bottom ash: a comparative technical analysis as material for road construction.

    PubMed

    Vegas, I; Ibañez, J A; San José, J T; Urzelai, A

    2008-01-01

    The objective of the study is to analyze the technical suitability of using secondary materials from three waste flows (construction and demolition waste (CDW), Waelz slag and municipal solid waste incineration (MSWI) bottom ash), under the regulations and standards governing the use of materials for road construction. A detailed technical characterization of the materials was carried out according to Spanish General Technical Specifications for Road Construction (PG3). The results show that Waelz slag can be adequate for using in granular structural layers, while CDW fits better as granular material in roadbeds. Likewise, fresh MSWI bottom ash can be used as roadbed material as long as it does not contain a high concentration of soluble salts. This paper also discusses the adequacy of using certain traditional test methods for natural soils when characterizing secondary materials for use as aggregates in road construction.

  17. Programmatic agreement among the USDOE/RL Operations Office, the Advisory Council on Historic Preservation, and the WA State Historic Preservation Office for the maintenance, deactivation, alteration and demolition of the built environment on the Hanford Site, Washington

    SciTech Connect

    Lloyd, D.W.

    1997-08-01

    This Programmatic Agreement (PA) addresses the built environment (i.e., buildings and structures) constructed during the Manhattan Project and Cold War Era periods of Hanford`s operational history. As such it encompasses the years 1943 through 1990. The identification, evaluation, and treatment of buildings and historic archeological remains on the Hanford Site predating 1943 will be accomplished through Sections 800.4 through 800.6 of the Council`s regulations. This PA will be in effect from the date of signature until September 30, 2000. Completion of the Sitewide Treatment Plan established under this PA satisfies all Section 106 requirements for identification, evaluation, and treatment necessary for all undertakings, up to and including demolition which may affect Manhattan Project and Cold War Era properties. This PA may be extended if the Sitewide Treatment Plan has not been completed by the end of FY 2000. Identification, evaluation, and treatment of properties constructed on the Hanford Site after 1990 will be handled pursuant to the regulations in effect at the time such properties are eligible for review.

  18. Effects of a coal-fired power plant and other sources on southwestern visibility (interim summary of EPA'S project VISTTA)

    NASA Astrophysics Data System (ADS)

    Blumenthal, D. L.; Richards, L. W.; Macias, E. S.; Bergstrom, R. W.; Wilson, W. E.; Bhardwaja, P. S.

    VISTTA (Visibility impairment due to Sulfur Transport and Transformation in the Atmosphere) is a cooperative program involving numerous government agencies, private companies, and universities. This paper summarizes the measurements and the results to date of the summer and winter, 1979, VISTTA plume measurement programs conducted near the Navajo Generating Station (NGS), Page, Arizona. During the program, ground and airborne measurements of aerosol size distribution, chemistry and optical properties, as well as gaseous reactant concentrations were made in the plume and in background air. Extensive regional and plume telephotometer measurements, airborne measurements along telephotometer site paths, background meteorological measurements, and source aerosol and chemistry measurements were also made. Various types of visibility measurements were compared with one another and with calculations of light extinction made using aerosol and NO 2 data. The measured plume optical effects were compared to those predicted using the EPA-SAI plume visibility model (PLUVUE). The results of the study to date indicate that: For the NGS plume, under most lighting and viewing conditions, NO 2 dominates the blue light extinction and brown coloration due to the plume. For distances up to 100 km or more for power plants like NGS, secondary aerosol formation can be ignored in visibility models under the dry conditions studied. Widespread areas of elevated aerosol concentrations were documented in the southwest due to long range transport from the southern California area, and to wild fires. Other causes of regional haze are known to exist but were not documented in this study. Evaluation of the chemistry, aerosol growth, and optics components of the PLUVUE plume visibility model showed predictions to be in reasonable agreement with the measurements. More uncertainty was encountered with the diffusion component. A set of nine reactions among NO, NO 2, O 3, O 2, SO 2, OH, H 2O, and O

  19. DEMONSTRATION PROJECT FOR THE ABATEMENT OF NITROGEN OXIDES EMISSIONS USING REBURN TECHNOLOGY FOR COGENERATION PLANTS IN TAIWAN

    EPA Science Inventory

    The report summarizes the key technical results of a joint demonstration project between the U.S. Environmental Protection Agency and the Taiwan Environmental Protection Administration. The project demonstrated that coal reburning can be used to reduce nitrogen oxides (NOX) emiss...

  20. RAMI modeling of selected balance of plant systems for the proposed Accelerator Production of Tritium (APT) project

    SciTech Connect

    Radder, J.A.; Cramer, D.S.

    1997-06-01

    In order to meet Department of Energy (DOE) Defense Program requirements for tritium in the 2005-2007 time frame, new production capability must be made available. The Accelerator Production of Tritium (APT) Plant is being considered as an alternative to nuclear reactor production of tritium, which has been the preferred method in the past. The proposed APT plant will use a high-power proton accelerator to generate thermal neutrons that will be captured in {sup 3}He to produce tritium (3H). It is expected that the APT Plant will be built and operated at the DOE`s Savannah River Site (SRS) in Aiken, South Carolina. Discussion is focused on Reliability, Availability, Maintainability, and Inspectability (RAMI) modeling of recent conceptual designs for balance of plant (BOP) systems in the proposed APT Plant. In the conceptual designs for balance of plant (BOP) systems in the proposed APT Plant. In the conceptual design phase, system RAMI estimates are necessary to identify the best possible system alternative and to provide a valid picture of the cost effectiveness of the proposed system for comparison with other system alternatives. RAMI estimates in the phase must necessarily be based on generic data. The objective of the RAMI analyses at the conceptual design stage is to assist the designers in achieving an optimum design which balances the reliability and maintainability requirements among the subsystems and components.

  1. Phase 2 focused feasibility study report for the reduction of mercury in plant effluent project at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    SciTech Connect

    1994-06-01

    The purpose of this focused feasibility study (FS) is to review the alternatives that have been evaluated under the Reduction of Mercury in Plant Effluent scoping efforts and provide justification for the recommended alternative. The chosen option from this study will be executed to meet the mercury-specific requirements of the recently negotiated National Pollutant Discharge Elimination System (NPDES) Permit for the Oak Ridge Y-12 Plant. Four previous ``mercury use`` buildings at the Y-12 Plant have been identified as primary contributors to these discharges and are scheduled to undergo upgrades to mitigate them as sources. They are 9201-2, 9201-4, 9201-5, and 9204-4. These buildings contain mercury-contaminated pipes and sumps that discharge to EFPC. The current requirements for limiting mercury discharges to EFPC are defined in the draft Y-12 Plant NPDES Permit, which is expected to become effective in July 1994. The main requirement related to mercury in the permit is to reduce the downstream mercury concentration to 5 g/day or less. Three basic options are considered and estimated in this study, including treatment at the building sources with local units ({approximately}$3.8 million); a combination of local treatment and centralized treatment at the Central Pollution Control Facility ({approximately}$6.6--8.9 million); and hydraulic control of the groundwater and/or in situ soil treatment ({approximately}$120 million). As negotiated under the NPDES Permit, an ``interim`` local unit, utilizing carbon adsorption, is being placed in operation in the 9201-2 building by July 1994. Since the major uncertainties associated with meeting the NPDES permit discharge requirements for mercury are flow rates and treatment efficiency, the 9201-2 unit will provide within 6 months the data necessary to optimize a treatment design.

  2. Energetic and Environmental Impacts Related to Transport and Assembling Processes in ABiogas Production Plant from Marine Macroalgae (FP7 Project BioWALK4Biofuels)

    NASA Astrophysics Data System (ADS)

    Cappelli, Andrea; Gigli, Emanuele; Muzi, Luca; Renda, Roberto; Simoni, Silvano

    2010-01-01

    GHG emissions, eutrophication and energy dependence are problems that the EU has to face in the near future. The BioWALK4Biofuels project aims to find a common response to these challenges, taking advantage of spontaneous biological processes: the growth of algae and anaerobic digestion of biomass. This project is being built thanks to European funding under the 7th Framework Programme. To evaluate the results obtained, a first LCA study was carried out that, as regards the data on infrastructure and on the assembly of the plant, refers to data supplied by manufacturers, while the study of algal growth was made on the basis of a model of cultivation that takes account of the aspects that most affect this key process among all the ones that cooperate in the whole plant. The electricity and heat produced through a co-generator fueled by biogas produced from algal biomass, according to this study, are responsible for GHG emissions reduced by 52% compared to traditional technologies. The biogas produced during the 4 years of the project allows the substitution of 85 tonnes of oil equivalent (toe).

  3. Thermal Pollution by Nuclear Power Plants. A Learning Experience for Coastal and Oceanic Awareness Studies, No. 320. [Project COAST].

    ERIC Educational Resources Information Center

    Delaware Univ., Newark. Coll. of Education.

    This publication includes several activities regarding the use of nuclear power plants and possible effects on the environment. The materials are designed for secondary school students and include reference materials and masters for transparencies. (RH)

  4. J.R. Simplot: Burner Upgrade Project Improves Performance and Saves Energy at a Large Food Processing Plant

    SciTech Connect

    Not Available

    2005-09-01

    This DOE Industrial Program case study describes how the J.R. Simplot Company saved energy and money by increasing the efficiency of the steam system in its potato processing plant in Caldwell, Idaho.

  5. J.R. Simplot: Burner Upgrade Project Improves Performance and Saves Energy at a Large Food Processing Plant (Steam)

    SciTech Connect

    2005-09-01

    This DOE Industrial Program case study describes how the J.R. Simplot Company saved energy and money by increasing the efficiency of the steam system in its potato processing plant in Caldwell, Idaho.

  6. Final results for the EPRI-DOE-SCS Chiyoda Thoroughbred CT-121 clean coal project at Georgia Power`s Plant Yates

    SciTech Connect

    Burford, D.P.

    1997-12-31

    The Yates Clean Coal Project was a co-funded Clean Coal Technology effort, sponsored by the US Department of Energy, the Electric Power Research Institute and Southern Company Services (EPRI-DOE-SCS) to evaluate a retrofit wet-limestone-based, sulfur dioxide (SO{sub 2}) scrubbing system in treating the hot flue gases of a coal-fired, 110MW electric utility boiler. This Project tested the operational limits of Chiyoda`s CT-121 Jet Bubbling Reactor System (JBR ) at Georgia Power`s Plant Yates from 1992 through 1994. Although the original test plan called for a very conservative assessment, the CT-121 system proved robust, so it was tested at widely varying conditions. Fuel sulfur content was varied between 1.5% to 4.3%, various limestone sources at several grind sizes were used, particulate removal and air toxics performance were measured and by-product gypsum soil amendment experimentation was conducted. In all cases, the CT-121 system gave encouraging results with predictably high SO{sub 2} removals (95--99%) and particulate removals (99+%) at all conditions with high reliability. Closed loop operations (no liquids treated, none discharged) called for the extensive application of corrosion impervious, fiberglass reinforced plastics (FRP) that was also very successful. Gypsum by-product proved to be significant as a soil enhancement and was granted a plant food license by the State of Georgia. So far, the Yates Project has received several awards from industry and environmental groups for its performance including Power Plant of the Year in 1994 from Power magazine.

  7. A Plutonium Finishing Plant Model for the Cercla Removal Action and Decommissioning Construction Final Report

    SciTech Connect

    Hopkins, A.

    2008-07-01

    The joint policy between the U.S. Environmental Protection Agency (EPA) and the U.S. Department of Energy (DOE) for decommissioning buildings at DOE facilities documents an agreement between the agencies to perform decommissioning activities including demolition under the Comprehensive Environmental Response Compensation and Liability Act (CERCLA). The use of removal actions for decommissioning integrates EPA oversight authority, DOE lead agency responsibility, and state authority for decommissioning activities. Once removal actions have been performed under CERCLA, a construction completion report is required to document the completion of the required action. Additionally, a decommissioning report is required under DOE guidance. No direct guidance was found for documenting completion of decommissioning activities and preparing a final report that satisfies the CERCLA requirements and the DOE requirements for decommissioning. Additional guidance was needed for the documentation of construction completion under CERCLA for D and D projects undertaken under the joint policy that addresses the requirements of both agencies. A model for the construction completion report was developed to document construction completion for CERCLA D and D activities performed under the joint EPA/DOE policy at the Plutonium Finishing Plant (PFP). The model documentation report developed at PFP integrates the DOE requirements for establishing decommissioning end-points, documenting end-point completion and preparing a final decommissioning report with the CERCLA requirements to document completion of the action identified in the Action Memorandum (AM). The model includes the required information on health and safety, data management, cost and schedule and end-points completion. (authors)

  8. Early Implementation of Large Scale Carbon Dioxide Removal Projects through the Cement Industry

    NASA Astrophysics Data System (ADS)

    Zeman, F. S.

    2014-12-01

    The development of large-scale carbon dioxide reduction projects requires high purity CO2and a reactive cation source. A project seeking to provide both of these requirements will likely face cost barriers with current carbon prices. The cement industry is a suitable early implementation site for such projects by virtue of the properties of its exhaust gases and those of waste concrete. Cement plants are the second largest source of industrial CO2 emissions, globally. It is also the second largest commodity after water, has no ready substitute and is literally the foundation of society. Finally, half of the CO2 emissions originate from process reactions rather than fossil fuel combustion resulting in higher flue gas CO2concentrations. These properties, with the co-benefits of oxygen combustion, create a favorable environment for spatially suitable projects. Oxygen combustion involves substituting produced oxygen for air in a combustion reaction. The absence of gaseous N2 necessitates the recirculation of exhaust gases to maintain kiln temperatures, which increase the CO2 concentrations from 28% to 80% or more. Gas exit temperatures are also elevated (>300oC) and can reach higher temperatures if the multi stage pre-heater towers, that recover heat, are re-designed in light of FGR. A ready source of cations can be found in waste concrete, a by-product of construction and demolition activities. These wastes can be processed to remove cations and then reacted with atmospheric CO2 to produce carbonate minerals. While not carbon negative, they represent a demonstration opportunity for binding atmospheric CO2while producing a saleable product (precipitated calcium carbonate). This paper will present experimental results on PCC production from waste concrete along with modeling results for oxygen combustion at cement facilities. The results will be presented with a view to mineral sequestration process design and implementation.

  9. Statement of work for applied technology tasks to be performed by Pacific Northwest Laboratory in support of the Hanford Waste Vitrification Plant Project; Fiscal year 1991

    SciTech Connect

    Kruger, O.L.

    1991-02-01

    Detailed Design for the Hanford Waste Vitrification Plant (HWVP) Project was initiated during fiscal year (FY) 1990. The Project requires technology development and design support from the research and development contractor, Pacific Northwest Laboratory (PNL), while this work is in progress. This Statement of Work (SOW) addresses the PNL work funded by the US Department of Energy-Richland Operations Office (DOE-RL) during FY 1991 to accomplish applied technology, PNL project management, and quality assurance (QA) tasks in support of HWVP Project requirements. Under the HWVP integrated management scheme, PNL is responsible for performing vitrification technology development. The PNL technical responsibilities include, but are not limited to, the following activities: provide process technology development and vitrification testing; evaluate equipment adaptation for the HWVP processes; provide glass formulation development; develop waste and glass characterization technology; provide waste form qualification (WFQ) models and data development; issue and maintain the HWVP Applied Technology Handbook (to be written); and prepare preliminary cost estimates, schedules, and scope definition covering the above technology activities. Pacific Northwest Laboratory will also participate with the Westinghouse Hanford Company (WHC) in technology exchanges and design reviews related to vitrification technology with the DOE-RL and Fluor Daniel, Inc. (Fluor). 15 refs., 4 tabs.

  10. Project: "Project!"

    ERIC Educational Resources Information Center

    Grayson, Katherine

    2007-01-01

    In November 2006, the editors of "Campus Technology" launched their first-ever High-Resolution Projection Study, to find out if the latest in projector technology could really make a significant difference in teaching, learning, and educational innovation on US campuses. The author and her colleagues asked campus educators, technologists, and…

  11. Responding To Changes in the Decommissioning Plans for Demolition of a Former Active Handling Building at The United Kingdom Atomic Energy Establishment Winfrith

    SciTech Connect

    Brown, N.; Parkinson, S.J.; Cornell, R.M.; Staples, A.T.

    2006-07-01

    The full decommissioning of the former Active Handling Building A59 at Winfrith in Dorset is being carried out by RWE NUKEM Limited under contract from the site owners and nuclear site licence holder, United Kingdom Atomic Energy Authority (UKAEA). Following recent government changes, the United Kingdom's Nuclear Decommissioning Authority (NDA) has now set up contracts with UKAEA for delivery of the site clean-up programme. The building contains two heavily shielded suites of caves originally used to carry out remote examination of irradiated nuclear fuel elements together with other supporting facilities. The original intention was to demolish the caves ahead of the building but after detailed consideration it was concluded that demolition of the building in advance of the caves was more operationally effective. As a result, the original decommissioning plan had to be reworked to reflect these changes. The paper briefly explains how this situation arose and the means by which the problems experienced were overcome by a complete revision to the decommissioning programme. The updated plan has been adopted by UKAEA and work is now proceeding apace to clear the building of redundant items, to complete decontamination of all remaining areas and facilities and to carry out detailed radiological surveys to confirm that the building structure is clean and ready for demolition. Both cave lines have been completely decontaminated to low residual levels of activity and are essentially ready for controlled demolition. This paper describes some of the significant tasks undertaken during the past year with particular reference to the decommissioning techniques that gave the greatest success and the limitations of others originally considered. Some of these processes were aimed at minimising the volume of low level waste (LLW) generated by using standard off-the-shelf equipment to remove contamination from {approx}5 Ton concrete blocks recovered from both cave line structures. A

  12. The European ASAMPSA_E project : towards guidance to model the impact of high amplitude natural hazards in the probabilistic safety assessment of nuclear power plants. Information on the project progress and needs from the geosciences.

    NASA Astrophysics Data System (ADS)

    Raimond, Emmanuel; Decker, Kurt; Guigueno, Yves; Klug, Joakim; Loeffler, Horst

    2015-04-01

    The Fukushima nuclear accident in Japan resulted from the combination of two correlated extreme external events (earthquake and tsunami). The consequences, in particular flooding, went beyond what was considered in the initial engineering design design of nuclear power plants (NPPs). Such situations can in theory be identified using probabilistic safety assessment (PSA) methodology. PSA results may then lead industry (system suppliers and utilities) or Safety Authorities to take appropriate decisions to reinforce the defence-in-depth of the NPP for low probability event but high amplitude consequences. In reality, the development of such PSA remains a challenging task. Definitions of the design basis of NPPs, for example, require data on events with occurrence probabilities not higher than 10-4 per year. Today, even lower probabilities, down to 10-8, are expected and typically used for probabilistic safety analyses (PSA) of NPPs and the examination of so-called design extension conditions. Modelling the combinations of natural or man-made hazards that can affect a NPP and affecting some meaningful probability of occurrence seems to be difficult. The European project ASAMPSAE (www.asampsa.eu) gathers more than 30 organizations (industry, research, safety control) from Europe, US and Japan and aims at identifying some meaningful practices to extend the scope and the quality of the existing probabilistic safety analysis developed for nuclear power plants. It offers a framework to discuss, at a technical level, how "extended PSA" can be developed efficiently and be used to verify if the robustness of Nuclear Power Plants (NPPs) in their environment is sufficient. The paper will present the objectives of this project, some first lessons and introduce which type of guidance is being developed. It will explain the need of expertise from geosciences to support the nuclear safety assessment in the different area (seismotectonic, hydrological, meteorological and biological

  13. Soil retention of hexavalent chromium released from construction and demolition waste in a road-base-application scenario.

    PubMed

    Butera, Stefania; Trapp, Stefan; Astrup, Thomas F; Christensen, Thomas H

    2015-11-15

    We investigated the retention of Cr(VI) in three subsoils with low organic matter content in laboratory experiments at concentration levels relevant to represent leachates from construction and demolition waste (C&DW) reused as unbound material in road construction. The retention mechanism appeared to be reduction and subsequent precipitation as Cr(III) on the soil. The reduction process was slow and in several experiments it was still proceeding at the end of the six-month experimental period. The overall retention reaction fit well with a second-order reaction governed by actual Cr(VI) concentration and reduction capacity of the soil. The experimentally determined reduction capacities and second-order kinetic parameters were used to model, for a 100-year period, the one-dimensional migration of Cr(VI) in the subsoil under a layer of C&DW. The resulting Cr(VI) concentration would be negligible below 7-70 cm depth. However, in rigid climates and with high water infiltration through the road pavement, the reduction reaction could be so slow that Cr(VI) might migrate as deep as 200 cm under the road. The reaction parameters and the model can form the basis for systematically assessing under which scenarios Cr(VI) from C&DW could lead to an environmental issue for ground- and receiving surface waters.

  14. Does Disposing of Construction and Demolition Debris in Unlined Landfills Impact Groundwater Quality? Evidence from 91 Landfill Sites in Florida.

    PubMed

    Powell, Jon T; Jain, Pradeep; Smith, Justin; Townsend, Timothy G; Tolaymat, Thabet M

    2015-08-01

    More than 1,500 construction and demolition debris (CDD) landfills operate in the United States (U.S.), and U.S. federal regulations do not require containment features such as low-permeability liners and leachate collection systems for these facilities. Here we evaluate groundwater quality from samples collected in groundwater monitoring networks at 91 unlined, permitted CDD landfills in Florida, U.S. A total of 460,504 groundwater sample results were analyzed, with a median of 10 years of quarterly or semiannual monitoring data per site including more than 400 different chemical constituents. Downgradient concentrations of total dissolved solids, sulfate, chloride, iron, ammonia-nitrogen, and aluminum were greater than upgradient concentrations (p < 0.05). At downgradient wells where sulfate concentrations were greater than 150 mg/L (approximately 10% of the maximum dissolved sulfate concentration in water, which suggests the presence of leachate from the landfill), iron and arsenic were detected in 91% and 43% of samples, with median concentrations of 1,900 μg/L and 11 μg/L, respectively. These results show that although health-based standards can be exceeded at unlined CDD landfills, the magnitude of detected chemical concentrations is generally small and reflective of leached minerals from components (wood, concrete, and gypsum drywall) that comprise the bulk of discarded CDD by mass.

  15. Estimating the Additional Greenhouse Gas Emissions in Korea: Focused on Demolition of Asbestos Containing Materials in Building.

    PubMed

    Kim, Young-Chan; Hong, Won-Hwa; Zhang, Yuan-Long; Son, Byeung-Hun; Seo, Youn-Kyu; Choi, Jun-Ho

    2016-01-01

    When asbestos containing materials (ACM) must be removed from the building before demolition, additional greenhouse gas (GHG) emissions are generated. However, precedent studies have not considered the removal of ACM from the building. The present study aimed to develop a model for estimating GHG emissions created by the ACM removal processes, specifically the removal of asbestos cement slates (ACS). The second objective was to use the new model to predict the total GHG emission produced by ACM removal in the entire country of Korea. First, an input-equipment inventory was established for each step of the ACS removal process. Second, an energy consumption database for each equipment type was established. Third, the total GHG emission contributed by each step of the process was calculated. The GHG emissions generated from the 1,142,688 ACS-containing buildings in Korea was estimated to total 23,778 tonCO₂eq to 132,141 tonCO₂eq. This study was meaningful in that the emissions generated by ACS removal have not been studied before. Furthermore, the study deals with additional problems that can be triggered by the presence of asbestos in building materials. The method provided in this study is expected to contribute greatly to the calculation of GHG emissions caused by ACM worldwide. PMID:27626433

  16. Does Disposing of Construction and Demolition Debris in Unlined Landfills Impact Groundwater Quality? Evidence from 91 Landfill Sites in Florida.

    PubMed

    Powell, Jon T; Jain, Pradeep; Smith, Justin; Townsend, Timothy G; Tolaymat, Thabet M

    2015-08-01

    More than 1,500 construction and demolition debris (CDD) landfills operate in the United States (U.S.), and U.S. federal regulations do not require containment features such as low-permeability liners and leachate collection systems for these facilities. Here we evaluate groundwater quality from samples collected in groundwater monitoring networks at 91 unlined, permitted CDD landfills in Florida, U.S. A total of 460,504 groundwater sample results were analyzed, with a median of 10 years of quarterly or semiannual monitoring data per site including more than 400 different chemical constituents. Downgradient concentrations of total dissolved solids, sulfate, chloride, iron, ammonia-nitrogen, and aluminum were greater than upgradient concentrations (p < 0.05). At downgradient wells where sulfate concentrations were greater than 150 mg/L (approximately 10% of the maximum dissolved sulfate concentration in water, which suggests the presence of leachate from the landfill), iron and arsenic were detected in 91% and 43% of samples, with median concentrations of 1,900 μg/L and 11 μg/L, respectively. These results show that although health-based standards can be exceeded at unlined CDD landfills, the magnitude of detected chemical concentrations is generally small and reflective of leached minerals from components (wood, concrete, and gypsum drywall) that comprise the bulk of discarded CDD by mass. PMID:26130423

  17. Investigation on the components removed in loss on ignition test of sandy crushed construction and demolition waste.

    PubMed

    Asakura, Hiroshi; Yamada, Masato; Inoue, Yuzo; Watanabe, Yoichi; Ono, Yusaku

    2010-01-01

    Processed sandy residue generated from mixed construction and demolition waste (mixed C&D-W) was investigated for possible deposition in landfill. The basic properties and the components removed in the loss on ignition (LOI) test were examined. The target material for decreasing LOI was elucidated and the validity of LOI used as landfill standard for inert industrial solid waste was discussed. LOI of most of the samples was above 5% and therefore, in principle, processed sandy residue should not be deposited in inert-type landfill. As LOI of sandy residue was mainly due to bound water, the LOI could not be decreased to below 5% even if wood, which is the major organic matter in the sandy residue, was removed. However, decreasing the amount of wood could lead to a subsequent decrease in the amount of dissolved organic matter. Therefore, the LOI of processed mixed C&D-W used as landfill standard for inert industrial solid waste should be re-evaluated. PMID:19710117

  18. Soil retention of hexavalent chromium released from construction and demolition waste in a road-base-application scenario.

    PubMed

    Butera, Stefania; Trapp, Stefan; Astrup, Thomas F; Christensen, Thomas H

    2015-11-15

    We investigated the retention of Cr(VI) in three subsoils with low organic matter content in laboratory experiments at concentration levels relevant to represent leachates from construction and demolition waste (C&DW) reused as unbound material in road construction. The retention mechanism appeared to be reduction and subsequent precipitation as Cr(III) on the soil. The reduction process was slow and in several experiments it was still proceeding at the end of the six-month experimental period. The overall retention reaction fit well with a second-order reaction governed by actual Cr(VI) concentration and reduction capacity of the soil. The experimentally determined reduction capacities and second-order kinetic parameters were used to model, for a 100-year period, the one-dimensional migration of Cr(VI) in the subsoil under a layer of C&DW. The resulting Cr(VI) concentration would be negligible below 7-70 cm depth. However, in rigid climates and with high water infiltration through the road pavement, the reduction reaction could be so slow that Cr(VI) might migrate as deep as 200 cm under the road. The reaction parameters and the model can form the basis for systematically assessing under which scenarios Cr(VI) from C&DW could lead to an environmental issue for ground- and receiving surface waters. PMID:26148961

  19. Estimating the Additional Greenhouse Gas Emissions in Korea: Focused on Demolition of Asbestos Containing Materials in Building

    PubMed Central

    Kim, Young-Chan; Hong, Won-Hwa; Zhang, Yuan-Long; Son, Byeung-Hun; Seo, Youn-Kyu; Choi, Jun-Ho

    2016-01-01

    When asbestos containing materials (ACM) must be removed from the building before demolition, additional greenhouse gas (GHG) emissions are generated. However, precedent studies have not considered the removal of ACM from the building. The present study aimed to develop a model for estimating GHG emissions created by the ACM removal processes, specifically the removal of asbestos cement slates (ACS). The second objective was to use the new model to predict the total GHG emission produced by ACM removal in the entire country of Korea. First, an input-equipment inventory was established for each step of the ACS removal process. Second, an energy consumption database for each equipment type was established. Third, the total GHG emission contributed by each step of the process was calculated. The GHG emissions generated from the 1,142,688 ACS-containing buildings in Korea was estimated to total 23,778 tonCO2eq to 132,141 tonCO2eq. This study was meaningful in that the emissions generated by ACS removal have not been studied before. Furthermore, the study deals with additional problems that can be triggered by the presence of asbestos in building materials. The method provided in this study is expected to contribute greatly to the calculation of GHG emissions caused by ACM worldwide. PMID:27626433

  20. Cavity Exciton-Polariton mediated, Single-Shot Quantum Non-Demolition measurement of a Quantum Dot Electron Spin

    NASA Astrophysics Data System (ADS)

    Puri, Shruti; McMahon, Peter; Yamamoto, Yoshihisa

    2014-03-01

    The quantum non-demolition (QND) measurement of a single electron spin is of great importance in measurement-based quantum computing schemes. The current single-shot readout demonstrations exhibit substantial spin-flip backaction. We propose a QND readout scheme for quantum dot (QD) electron spins in Faraday geometry, which differs from previous proposals and implementations in that it relies on a novel physical mechanism: the spin-dependent Coulomb exchange interaction between a QD spin and optically-excited quantum well (QW) microcavity exciton-polaritons. The Coulomb exchange interaction causes a spin-dependent shift in the resonance energy of the polarized polaritons, thus causing the phase and intensity response of left circularly polarized light to be different to that of the right circularly polarized light. As a result the QD electron's spin can be inferred from the response to a linearly polarized probe. We show that by a careful design of the system, any spin-flip backaction can be eliminated and a QND measurement of the QD electron spin can be performed within a few 10's of nanoseconds with fidelity 99:95%. This improves upon current optical QD spin readout techniques across multiple metrics, including fidelity, speed and scalability. National Institute of Informatics, 2-1-2 Hitotsubashi, Chiyoda-ku, Tokyo 101-8430, Japan.