Sample records for riprap

  1. Rock riprap design for protection of stream channels near highway structures; Volume 2, Evaluation of Riprap design procedures

    USGS Publications Warehouse

    Blodgett, J.C.; McConaughy, C.E.

    1986-01-01

    In volume 2, seven procedures now being used for design of rock riprap installations were evaluated using data from 26 field sites. Four basic types of riprap failures were identified: Particle erosion, translational slide, modified slump, and slump. Factors associated with riprap failure include stone size , bank side slope, size gradation, thickness, insufficient toe or endwall, failure of the bank material, overtopping during floods, and geomorphic changes in the channel. A review of field data and the design procedures suggests that estimates of hydraulic forces acting on the boundary based on flow velocity rather than shear stress are more reliable. Several adjustments for local conditions, such as channel curvature, superelevation, or boundary roughness, may be unwarranted in view of the difficulty in estimating critical hydraulic forces for which the riprap is to be designed. Success of the riprap is related not only to the appropriate procedure for selecting stone size, but also to the reliability of estimated hydraulic and channel factors applicable to the site. (See also W89-04910) (Author 's abstract)

  2. Stability of rock riprap for protection at the toe of abutments located at the floodplain.

    DOT National Transportation Integrated Search

    1991-09-01

    This report presents the results of a research conducted in a hydraulic flume to : determine the stability of rock riprap protecting abutments located on flood : plains. The observed vulnerable zone for rock riprap failure is presented for : two abut...

  3. Vegetated Riprap Installation Techniques for Steambank Protection, Fish and Wildlife Habitat Creation

    NASA Astrophysics Data System (ADS)

    Raymond, Pierre

    2014-05-01

    Vegetated riprap is a cost effective alternative to conventional riprap erosion protection. Terra Erosion Control has experimented with the vegetation of riprap over the past ten years. As a result we have adapted a technique that can successfully establish vegetation during the installation of riprap structures. This presentation will demonstrate innovative ways of installing vegetated riprap for the protection of access roads on industrial sites and urban infrastructure such as storm water outfalls, bridge approaches and pedestrian pathways within public areas. This vegetation will provide additional bank protection, soften the rock appearance and enhance fish, wildlife and urban habitat along the shoreline. Vegetated riprap incorporates a combination of rock and native vegetation in the form of live cuttings. These are planted in conjunction with the placement of rock used to armour the banks of watercourses. Establishment of native vegetation will improve fish habitat by creating shade, cover and an input of small organic debris to stream banks. In most cases it will negate the need for the regulator (Canadian Department of Fisheries and Oceans) to require habitat alteration compensation. It will also provide added bank protection through the development of root mass. Adding vegetation to riprap provides a softer, more natural appearance to the installed rocks. This presentation will detail the processes involved in the installation of vegetated riprap such as the harvesting and soaking of live material, site preparation of the stream bank, placement of riprap in conjunction with live material and the use of burlap/coir fabric and soil amendments. It will also discuss the innovative method of using wooden boards to protect live cuttings during construction and to direct precipitation and/or irrigation water to the root zone during the establishment phase of the vegetation. These boards will eventually biodegrade within the rock. This approach was applied over the past seven years to the stream banks of eleven different sites on large and medium sized rivers in three Provinces of Canada. To date, the survival and growth of vegetated riprap brush layers installed along riverbanks has been assessed as good to excellent, resulting in the substantial creation of fish, wildlife and urban habitat. The survival and growth, along with early results of an excavation trial, will be presented.

  4. Analysis of root reinforcement of vegetated riprap

    NASA Astrophysics Data System (ADS)

    Tron, Stefania; Raymond, Pierre

    2014-05-01

    Riprap is a traditional engineering solution used to protect riverbanks against erosion on developed riparian corridors. However, the traditional riprap does not provide adequate fish and wildlife habitat within the riparian zone, which is normally provided by naturally vegetated stream banks. An innovative approach, which mitigates this issue and at the same time provides stream bank erosion control, is the vegetated riprap technique. This solution, which combines rocks and native vegetation in the form of live cuttings, has been designed and implemented by Terra Erosion Control Ltd for the past 7 years. The aim of this work was to study the effect of the vegetation, in particular the root system, on the stability of the riprap. This analysis was carried out in the late spring of 2013 on the vegetated riprap installation located along the Columbia River riverbank, adjacent to the Teck Metals Ltd. smelter in Trail, British Columbia, Canada. An excavation perpendicular to the river was performed in order to investigate the root system development within the vegetated riprap structure. This excavation exposed one of the Salix bebbiana cuttings installed in 2006. The cutting was 2.3 m long and was set with an inclination of 35° with respect to the horizontal plane: the first 0.3 m was exposed, 1 m was buried within the riprap rocks (which had an average diameter of 30 cm) and the remaining 1.0 m was in the soil matrix below the rocks. The diameter of the roots growing along the cutting were measured in order to obtain the root density at various depths and tensile strength tests were carried out on the Salix bebbiana roots with diameters of up to 9 mm. The aim was to quantitatively estimate the additional cohesion given by the roots. The additional root cohesion was more effective in the deeper soil layer where the soil matrix predominates. In the upper soil layer, where the particle size is significantly higher, roots do not increase the cohesion but act as a network which ties the rocks of the riprap structure together. The uprooting resistance was also tested with a pullout test, which demonstrated that the force necessary to uproot a Salix bebianna cutting, grown in the riprap along the riverbank, was higher if compared with the same species grown in a natural environment.

  5. Fish community structure in natural and engineered habitats in the Kansas River

    USGS Publications Warehouse

    White, K.; Gerken, J.; Paukert, Craig P.; Makinster, Andrew S.

    2010-01-01

    We investigated fish assemblage structure in engineered (rip-rap) and natural habitats (log jams and mud banks) in the Kansas River USA to determine if natural structures had higher abundance and diversity of fishes at a local spatial scale. A total of 439 randomly selected sites were boat electrofished from May to August 2005 and 2006. Mean species diversity and richness were significantly higher in rip-rap than log jams and mud banks. Mean relative abundance (CPUE; number of fish collected per hour electrofishing) of six of the 15 most common fishes (>1% of total catch) were most abundant in rip-rap, two were most abundant in log jams, and none in mud banks. Rip-rap had the highest relative abundance of fluvial specialist and macrohabitat generalists, whereas mean CPUE of fluvial dependents was highest in log jams. Although a discriminant function analysis indicated that nine size classes (eight species) discriminated among three habitat types, the high misclassification rate (38%) suggested a high degree of fish assemblage overlap among the habitats. Although previous work has suggested that engineered structures (rip-rap) and urbanization are linked to reduced biotic diversity or reduced growth of fish species, our results suggest that at a local scale rip-rap may not have the same negative impacts on fish assemblages.

  6. Fish community structure in natural and engineered habitats in the Kansas river

    USGS Publications Warehouse

    White, K.; Gerken, J.; Paukert, C.; Makinster, A.

    2010-01-01

    We investigated fish assemblage structure in engineered (rip-rap) and natural habitats (log jams and mud banks) in the Kansas River USA to determine if natural structures had higher abundance and diversity of fishes at a local spatial scale. A total of 439 randomly selected sites were boat electrofished from May to August 2005 and 2006. Mean species diversity and richness were significantly higher in rip-rap than log jams and mud banks. Mean relative abundance (CPUE; number of fish collected per hour electrofishing) of six of the 15 most common fishes (>1% of total catch) were most abundant in rip-rap, two were most abundant in log jams, and none in mud banks. Rip-rap had the highest relative abundance of fluvial specialist and macrohabitat generalists, whereas mean CPUE of fluvial dependents was highest in log jams. Although a discriminant function analysis indicated that nine size classes (eight species) discriminated among three habitat types, the high misclassification rate (38%) suggested a high degree of fish assemblage overlap among the habitats. Although previous work has suggested that engineered structures (rip-rap) and urbanization are linked to reduced biotic diversity or reduced growth of fish species, our results suggest that at a local scale rip-rap may not have the same negative impacts on fish assemblages.

  7. Risk Assessment on Constructors during Over-water Riprap Based on Entropy Weight and FAHP

    NASA Astrophysics Data System (ADS)

    Wu, Tongqing; Li, Liang; Liang, Zelong; Mao, Tian; Shao, Weifeng

    2017-07-01

    Being aimed at waterway regulation engineering, there exist risks of over-water riprap for constructors which keeps uncertainty and complexity. For the purpose of evaluating the possibility and consequence, this paper utilizes fuzzy analytic hierarchy process with abbreviation of FAHP to do empowerment on the related risk indicators, constructs FAHP under entropy weight and establishes relevant evaluation factor set and evaluation language for constructors during over-water riprap construction process. Through doing risk probability estimation and risk consequence size evaluation on the factor of constructors, this paper introduces this model into risk analysis on constructors during over-water riprap of Ching River waterway regulation project. Results show that evaluation of this method is so credible that it could be utilized in practical engineering.

  8. Roadway applications of vegetation and riprap for streambank protection : synthesis report , appendix.

    DOT National Transportation Integrated Search

    2002-01-01

    Riprap is commonly used for roadway protection at streams. However, vegetation is generally not a component of such protection. Environmental impacts such as increased water temperature and decreased quality of stream habitat may result from the remo...

  9. ECHETA DAM RIPRAP ON RESERVOIR SIDE OF THE DAM AT ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    ECHETA DAM RIP-RAP ON RESERVOIR SIDE OF THE DAM AT BREACH. VIEW TO NORTH-NORTHEAST. - Echeta Dam & Reservoir, 2.9 miles east of Echeta Road at Echeta Railroad Siding at County Road 293, Echeta, Campbell County, WY

  10. Roadway applications of vegetation and riprap for streambank protection : synthesis report.

    DOT National Transportation Integrated Search

    2002-01-01

    Riprap is commonly used for roadway protection at streams. However, vegetation is generally not a component of such protection. Environmental impacts such as increased water temperature and decreased quality of stream habitat may result from the remo...

  11. Failure of riprap protection : phase II (final report).

    DOT National Transportation Integrated Search

    2008-06-01

    Riprap rundowns are often used by the New Mexico Department of Transportation (NMDOT) to : capture and drain the runoff approaching or leaving bridge decks. Rundowns are generally located at : the ends of a bridge deck to transport the water down the...

  12. 13. THE SAME NORTH TRAINING WALL TOP SURFACE, LOOKING EAST ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    13. THE SAME NORTH TRAINING WALL TOP SURFACE, LOOKING EAST FROM ATOP ADJACENT RIPRAP. THE TRAINING WALL IS TO THE RIGHT OF THE JUMBLED, LIGHT TONED RIPRAP. - Oakland Harbor Training Walls, Mouth of Federal Channel to Inner Harbor, Oakland, Alameda County, CA

  13. Rock gabion, rip-rap, and culvert treatments: Successes and failures in post-fire erosion mitigation, Schultz Fire 2010

    Treesearch

    Daniel G. Neary; Karen A. Koestner

    2011-01-01

    Following the Schultz Fire in June of 2010, several erosion mitigation efforts were undertaken to reduce the impacts of post-fire flooding expected during the 2010 monsoon. One treatment consisted of the placement of large rock rip-rap on targeted fill slopes of a high elevation forest road that contains a buried pipeline supplying water to the city of Flagstaff....

  14. Environmental Assessment: PL 84-99 Levee Rehabilitation Program Lower Platte South Natural Resource District, Antelope Creek, Lincoln, Lancaster County, Nebraska

    DTIC Science & Technology

    2015-03-01

    block erosion protection, vegetated banks, rock riprap protection, a labyrinth weir, underground conduit, concrete retaining walls near bridges...erosion protection, vegetated banks, rock riprap protection, a labyrinth weir, underground conduit, concrete retaining walls near bridges, and outlet...called “criteria pollutants”. These include: ozone, carbon monoxide, nitrogen dioxide, particulate matter, sulfur dioxide, and lead. Lancaster County

  15. Big Creek Flood Control Project, Cleveland, Ohio. Phase II. General Design Memorandum. Appendix B. Alternative Studies.

    DTIC Science & Technology

    1978-11-01

    120, Engineering and Design Additional Guidance for Riprap Channel Protection. Good qual- ity stone is available in the Cleveland area; therefore, it...design life. The galvanizing is subject to abrasion and deterioration. As the gabions would be filled with stone that would have the same quality of...riprap, the PVC coated gabions would provide protection in excess of 50 years without anticipated maintenance. As the stone size for all gabions is

  16. Environmental Assessment: PL 84-99 Levee Rahabilitation Program Lower Platte South Natural Resource District Salt Creek, Lincoln, Lancaster County, Nebraska

    DTIC Science & Technology

    2015-03-01

    lost bank material with compacted, non-dispersive clay and riprap; constructing landward piggy-back levees at discrete locations if space is available...consist of approximately seven miles of levees. The levees have 3:1 side slopes that are made up of clay soil, with a two-foot minimum freeboard. The...reshaping the levee and replacing lost bank material with compacted, non-dispersive clay and riprap or building a landside piggy back levee if space is

  17. Regional Sediment Management (RSM) Principles in Flood Recovery: Incorporating RSM after the 2011 Missouri River Flood

    DTIC Science & Technology

    2013-06-01

    outer bank threatened a Fed- eral levee that protects adjacent homes and farmland. The eroded chute bank approached the toe of the levee causing...design drawing for repairing the levee toe . Approximately 30,000 tons of riprap were placed to re-establish the bank in front of the scour hole...Sediment was needed to fill and stabilize the scour hole between the riprap bank and the toe of the levee. The volume required to fill the scour hole

  18. Low Cost Shore Protection: A Guide for Engineers and Contractors.

    DTIC Science & Technology

    1981-10-31

    pieces; stones should be angular and blocky, not rounded. The toe of the revetment should be located one design wave height (but at least three feet...coefficient from Table 12. Table 12 Stability Coefficients for Stone Revetments Armor Unit KD Quarrystone Smooth rounded 2.1 Rough angular 3.5 Graded riprap...Armor Layers K______D __ K D cot 0 Quarrystone Smooth ztounded 2 2.1 1.7 1.5 to 3.0 Rough angular 2 3.5 12.9 1l.5 Graded riprap Not Recommended A major

  19. Quantifying Process-Based Mitigation Strategies in Historical Context: Separating Multiple Cumulative Effects on River Meander Migration

    PubMed Central

    Fremier, Alexander K.; Girvetz, Evan H.; Greco, Steven E.; Larsen, Eric W.

    2014-01-01

    Environmental legislation in the US (i.e. NEPA) requires defining baseline conditions on current rather than historical ecosystem conditions. For ecosystems with long histories of multiple environmental impacts, this baseline method can subsequently lead to a significantly altered environment; this has been termed a ‘sliding baseline’. In river systems, cumulative effects caused by flow regulation, channel revetment and riparian vegetation removal significantly impact floodplain ecosystems by altering channel dynamics and precluding subsequent ecosystem processes, such as primary succession. To quantify these impacts on floodplain development processes, we used a model of river channel meander migration to illustrate the degree to which flow regulation and riprap impact migration rates, independently and synergistically, on the Sacramento River in California, USA. From pre-dam conditions, the cumulative effect of flow regulation alone on channel migration is a reduction by 38%, and 42–44% with four proposed water diversion project scenarios. In terms of depositional area, the proposed water project would reduce channel migration 51–71 ha in 130 years without current riprap in place, and 17–25 ha with riprap. Our results illustrate the utility of a modeling approach for quantifying cumulative impacts. Model-based quantification of environmental impacts allow scientists to separate cumulative and synergistic effects to analytically define mitigation measures. Additionally, by selecting an ecosystem process that is affected by multiple impacts, it is possible to consider process-based mitigation scenarios, such as the removal of riprap, to allow meander migration and create new floodplains and allow for riparian vegetation recruitment. PMID:24964145

  20. Effects of grade control structures on the macroinvertebrate assemblage of an agriculturally impacted stream

    USGS Publications Warehouse

    Litvan, M.E.; Stewart, T.W.; Pierce, C.L.; Larson, C.J.

    2008-01-01

    Nearly 400 rock rip-rap grade control structures (hereafter GCS) were recently placed in streams of western Iowa, USA to reduce streambank erosion and protect bridge infrastructure and farmland. In this region, streams are characterized by channelized reaches, highly incised banks and silt and sand substrates that normally support low macroinvertebrate abundance and diversity. Therefore, GCS composed of rip-rap provide the majority of coarse substrate habitat for benthic macroinvertebrates in these streams. We sampled 20 sites on Walnut Creek, Montgomery County, Iowa to quantify macroinvertebrate assemblage characteristics (1) on GCS rip-rap and at sites located (2) 5-50 m upstream of GCS, (3) 5-50 m downstream of GCS and (4) at least 1 km from any GCS (five sites each). Macroinvertebrate biomass, numerical densities and diversity were greatest at sites with coarse substrates, including GCS sites and one natural riffle site and relatively low at remaining sites with soft substrates. Densities of macroinvertebrates in the orders Ephemeroptera, Trichoptera, Diptera, Coleoptera and Acariformes were abundant on GCS rip-rap. Increases in macroinvertebrate biomass, density and diversity at GCS may improve local efficiency of breakdown of organic matter and nutrient and energy flow, and provide enhanced food resources for aquatic vertebrates. However, lack of positive macroinvertebrate responses immediately upstream and downstream of GCS suggest that positive effects might be restricted to the small areas of streambed covered by GCS. Improved understanding of GCS effects at both local and ecosystem scales is essential for stream management when these structures are present. Copyright ?? 2007 John Wiley & Sons, Ltd.

  1. Submittal of Final Post-Closure Inspection Letter Report for Corrective Action Unit 112: Area 23 Hazardous Waste Trenches, Nevada Test Site, Nevada, Revision 0, December 2007; DOE/NV--1103

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    NSTec Environmental Restoration

    This letter serves as the post-closure monitoring letter report for the above Corrective Action Unit (CAU) for the period October 2006-September 2007. Quarterly inspections were conducted on December 20,2006; March 29,2007; June 13,2007; and September 27, 2007, to observe the condition of the gate, use restriction warning signs, monuments, fencing, trenches, soil covers, and monitoring well covers. The first inspection was conducted on December 20,2006. Signs, fencing, riprap, monuments, and monitoring well covers were in excellent condition. No cracking, erosion, or subsidence was observed on the covers. No issues or concerns were identified, and no corrective actions were recommended. Themore » second inspection was conducted on March 29,2007. Signs, fencing, riprap, monuments, and monitoring well covers were in excellent condition. No cracking, erosion, or subsidence was observed on the covers. Vegetation that was observed to be growing in several locations on the cover was the only identified concern, for which removal was recommended. Vegetation was removed on May 24,2007. The third inspection was conducted on June 13,2007. Signs, fencing, riprap, monuments, and monitoring well covers were in excellent condition. No cracking, erosion, or subsidence was observed on the covers. No issues or concerns were identified, and no corrective actions were recommended. The fourth inspection was conducted on September 27,2007. Signs, fencing, riprap, monuments, and monitoring well covers were in excellent condition. No cracking, erosion, or subsidence was observed on the covers. No issues or concerns were identified, and no corrective actions were recommended. The post-closure inspection checklists for CAU 112 are attached. Photographs and field notes taken during site inspections are maintained in the project files.« less

  2. GREEN TECHNOLOGIES SOLUTIONS-OIL RECOVERY (GTS-OR)

    EPA Pesticide Factsheets

    Technical product bulletin: this surface washing agent used in oil spill cleanups may clean oil from beaches, rocks, riprap, pilings, and seawalls. May be used in freshwater, estuarine, and marine environments.

  3. DOE Office of Scientific and Technical Information (OSTI.GOV)

    Linard, Joshua; Hall, Steve

    9.1 Compliance Summary The Lakeview, Oregon, Uranium Mill Tailings Radiation Control Act (UMTRCA) Title I Disposal Site was inspected September 16 and 17, 2015. Other than some ongoing concern with erosion-control rock riprap degradation, the disposal cell was in good condition. Some minor fence repairs and vegetation removal, and minor erosion repair work along the west site fence is planned. Inspectors identified no other maintenance needs or cause for a follow-up or contingency inspection. Disposal cell riprap is evaluated annually to ensure continued long-term protection of the cell from erosion during a severe precipitation event. Degradation of the rock riprapmore » was first observed at the site in the mid-1990s. Rock gradation monitoring of the riprap on the west side slope has been performed as part of the annual inspection since 1997 to determine the mean diameter (D 50) value. As prescribed by the monitoring procedure, the rock monitoring is routinely conducted at random locations. However, at the U.S. Nuclear Regulatory Commission’s (NRC’s) request, the 2015 rock monitoring approach deviated from the normal procedure by using a pre-established monitoring grid in a subset area of the west side slope. This changed the monitoring approach from random sampling to biased sampling. The D 50 value measured during the 2015 gradation monitoring is 2.39 inches, which falls below the original D 50 design size range of 2.7–3.9 inches for the Type B size side slope riprap. At NRC’s request, rock durability monitoring was added to the gradation monitoring in 2009 to monitor durability by rock type. Results of the 2015 durability monitoring showed that74 percent of the total rock sampled is durability class code A rock with an assigned durability class of “highly durable” or durability class code B “durable” rock, and that over 90 percent of the 3-inch or larger rock is durability class code A or B. The rock durability classifications are further explained in Section 9.4.2.2.« less

  4. 15. MASONRY DETAIL NO. 1, NORTH TRAINING WALL, LOOKING DOWN ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    15. MASONRY DETAIL NO. 1, NORTH TRAINING WALL, LOOKING DOWN UPON THE WALL SURFACE FROM THE ADJACENT RIPRAP. - Oakland Harbor Training Walls, Mouth of Federal Channel to Inner Harbor, Oakland, Alameda County, CA

  5. Application of geotextiles in Alaska : final report

    DOT National Transportation Integrated Search

    1983-08-01

    This report gives the results of the investigation of twenty projects exemplifying the use of geotextiles by the Alaska Department of Transportation and Public Facilities. These projects fall into three categories: subdrainage and riprap liners, emba...

  6. Rock stream stability structures in the vicinity of bridges.

    DOT National Transportation Integrated Search

    2014-10-01

    This report was sponsored by the Utah Department of Transportation (UDOT) to determine if rock stream stability structures could be used as : scour countermeasures and to protect streambanks. Traditional scour countermeasures, such as rock riprap, ar...

  7. Evaluating shallow-flow rock structures as scour countermeasures at bridges.

    DOT National Transportation Integrated Search

    2009-12-01

    A study to determine whether or not shallow-flow rock structures could reliably be used at bridge abutments in place of riprap. Research was conducted in a two-phase effort beginning with numerical modeling and ending with field verification of model...

  8. Development and testing of synthetic RIPRAP constructed from coal combustion products.

    DOT National Transportation Integrated Search

    2013-11-01

    Even with an increase in the amount of CCPs used in concrete construction, soil stabilization, and other applications, the coal power : industry must dispose of a significant amount of fly ash and bottom ash. One potential avenue for the material is ...

  9. Development and testing of synthetic riprap constructed from coal combustion products (CCPs).

    DOT National Transportation Integrated Search

    2014-07-01

    Even with an increase in the amount of coal combustion products (CCPs) used in concrete con-struction, soil stabilization, and other : applications, the coal power industry must dispose of a sig-nificant amount of fly ash and bottom ash. One potentia...

  10. Design procedures and field monitoring of submerged barbs for streambank protection.

    DOT National Transportation Integrated Search

    2007-06-01

    The main objective of this study was to evaluate the hydraulic performance of riprap spurs and weirs in controlling bank erosion at : the Southern part of the Raccoon River upstream U.S. Highway 169 Bridge utilizing the commercially available model F...

  11. 33 CFR 162.40 - Inland waterway from Delaware River to Chesapeake Bay, Del. and Md. (Chesapeake and Delaware Canal).

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... avoid damage by suction or wave wash to wharves, landings, riprap protection, or other boats, or injury... suction or wave wash does occur. Owners and operators of yachts, motorboats, rowboats and other craft are...

  12. 33 CFR 162.40 - Inland waterway from Delaware River to Chesapeake Bay, Del. and Md. (Chesapeake and Delaware Canal).

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... avoid damage by suction or wave wash to wharves, landings, riprap protection, or other boats, or injury... suction or wave wash does occur. Owners and operators of yachts, motorboats, rowboats and other craft are...

  13. 33 CFR 162.40 - Inland waterway from Delaware River to Chesapeake Bay, Del. and Md. (Chesapeake and Delaware Canal).

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... avoid damage by suction or wave wash to wharves, landings, riprap protection, or other boats, or injury... suction or wave wash does occur. Owners and operators of yachts, motorboats, rowboats and other craft are...

  14. 33 CFR 162.40 - Inland waterway from Delaware River to Chesapeake Bay, Del. and Md. (Chesapeake and Delaware Canal).

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... avoid damage by suction or wave wash to wharves, landings, riprap protection, or other boats, or injury... suction or wave wash does occur. Owners and operators of yachts, motorboats, rowboats and other craft are...

  15. Development of a Computational Approach to Detect Instability and Incipient Motion of Large Riprap Rocks

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Bojanowski, C.; Lottes, S. A.; Flora, K.

    2017-08-01

    Local scour at bridge piers is a potential safety hazard of major concern to transportation agencies. If it is determined that scour at bridge piers can adversely affect the stability of a bridge, scour countermeasures to protect the pier should be considered.

  16. Smart rock technology for real-time monitoring of bridge scour and riprap effectiveness - design guidelines and visualization tool.

    DOT National Transportation Integrated Search

    2016-12-31

    This study aims to further develop and demonstrate the recently-proposed smart rock technology for : scour depth and protection effectiveness monitoring. A smart rock is one or two stacked magnets encased : in a concrete sphere with a specially-desig...

  17. Remedial action plan and site design for stabilization of the inactive uranium mill tailings sites at Rifle, Colorado

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Not Available

    1990-02-01

    This volume contains appendices D6 through D8 containing laboratory test data: from MK-F investigation, 1987, Old Rifle and New Rifle sites; on bentonite amended radon barrier material; and from MK-F investigation, 1987, riprap tests.

  18. Reduction of soil erosion on forest roads

    Treesearch

    Edward R. Burroughs; John G. King

    1989-01-01

    Presents the expected reduction in surface erosion from selected treatments applied to forest road traveledways, cutslopes, fillslopes, and ditches. Estimated erosion reduction is expressed as functions of ground cover, slope gradient, and soil properties whenever possible. A procedure is provided to select rock riprap size for protection of the road ditch.

  19. 40 CFR 436.20 - Applicability; description of the crushed stone subcategory.

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... (CONTINUED) EFFLUENT GUIDELINES AND STANDARDS MINERAL MINING AND PROCESSING POINT SOURCE CATEGORY Crushed... stone and riprap. This subpart includes all types of rock and stone. Rock and stone that is crushed or broken prior to the extraction of a mineral are elsewhere covered. The processing of calcite, however, in...

  20. 40 CFR 436.20 - Applicability; description of the crushed stone subcategory.

    Code of Federal Regulations, 2012 CFR

    2012-07-01

    ... (CONTINUED) EFFLUENT GUIDELINES AND STANDARDS (CONTINUED) MINERAL MINING AND PROCESSING POINT SOURCE CATEGORY... stone and riprap. This subpart includes all types of rock and stone. Rock and stone that is crushed or broken prior to the extraction of a mineral are elsewhere covered. The processing of calcite, however, in...

  1. 40 CFR 436.20 - Applicability; description of the crushed stone subcategory.

    Code of Federal Regulations, 2013 CFR

    2013-07-01

    ... (CONTINUED) EFFLUENT GUIDELINES AND STANDARDS (CONTINUED) MINERAL MINING AND PROCESSING POINT SOURCE CATEGORY... stone and riprap. This subpart includes all types of rock and stone. Rock and stone that is crushed or broken prior to the extraction of a mineral are elsewhere covered. The processing of calcite, however, in...

  2. 40 CFR 436.20 - Applicability; description of the crushed stone subcategory.

    Code of Federal Regulations, 2011 CFR

    2011-07-01

    ... (CONTINUED) EFFLUENT GUIDELINES AND STANDARDS MINERAL MINING AND PROCESSING POINT SOURCE CATEGORY Crushed... stone and riprap. This subpart includes all types of rock and stone. Rock and stone that is crushed or broken prior to the extraction of a mineral are elsewhere covered. The processing of calcite, however, in...

  3. 40 CFR 436.20 - Applicability; description of the crushed stone subcategory.

    Code of Federal Regulations, 2014 CFR

    2014-07-01

    ... (CONTINUED) EFFLUENT GUIDELINES AND STANDARDS (CONTINUED) MINERAL MINING AND PROCESSING POINT SOURCE CATEGORY... stone and riprap. This subpart includes all types of rock and stone. Rock and stone that is crushed or broken prior to the extraction of a mineral are elsewhere covered. The processing of calcite, however, in...

  4. Control of Sediment Export From The Forest Road Prism

    Treesearch

    Johnny M. Grace

    2002-01-01

    The effectiveness of four road turn-out ditch treatments (vegetation, rip-rap, sediment fences, and settling basins) in reducing sediment export to the forest floor was evaluated. These four runoff control method are commonly prescribed to control forest road runoff and sediments. The study utilized runoff samplers, runoff diversion walls, sediment filter bags, and...

  5. Snake River fall Chinook salmon life history investigations, 1/1/2013 – 12/31/2013

    USGS Publications Warehouse

    Tiffan, Kenneth F.; Connor, William P.

    2015-01-01

    Smallmouth bass predation on subyearling fall Chinook salmon was examined in the upper portion of Lower Granite Reservoir during 2013. During the time subyearlings were present in the reservoir, smallmouth bass were collected, their stomach contents removed for diet analysis, and their abundance estimated with mark-recapture techniques. In 2013, the greatest consumption of subyearlings by smallmouth bass occurred in late May and early June—as much as 50% of their diet by weight. Sand rollers were the most common non-salmonid fish consumed by smallmouth bass. In the section of the reservoir above the confluence with the Clearwater River, the abundance of bass was higher in non-riprap habitat than in riprap, but the opposite was true in the section below the confluence. We estimated that over 168,000 subyearlings were lost to smallmouth bass predation in 2013. Given the predominance of sand rollers in the diet of smallmouth bass, we believe this species reduces predation on subyearling fall Chinook salmon. A complete report of our findings is provided in the Appendix.

  6. User s Manual for Armor Stone Evaluation Model (ARMOR): Great Lakes Armor Stone Study

    DTIC Science & Technology

    2015-08-01

    Broderick and Ahrens (1982) defined damage to an armor layer by the normalized eroded cross-section area as S = Ae/(Dn50)2, where Ae is the measured...84. Broderick , L., and J. P. Ahrens. 1982. Rip-rap stability scale effects. Technical Paper 82- 3. Vicksburg, MS: U.S. Army Engineer Waterways

  7. 18 CFR 1304.208 - Shoreline stabilization on TVA-owned residential access shoreland.

    Code of Federal Regulations, 2011 CFR

    2011-04-01

    ... planting of vegetation. (2) Tightly bound bundles of coconut fiber, logs, or other natural materials may be... stone, natural stone, or other material approved by TVA. (2) Rubber tires, concrete rubble, or other... full summer pool water. Riprap shall be placed at least two feet in depth along the footer of the...

  8. 18 CFR 1304.208 - Shoreline stabilization on TVA-owned residential access shoreland.

    Code of Federal Regulations, 2010 CFR

    2010-04-01

    ... planting of vegetation. (2) Tightly bound bundles of coconut fiber, logs, or other natural materials may be... stone, natural stone, or other material approved by TVA. (2) Rubber tires, concrete rubble, or other... full summer pool water. Riprap shall be placed at least two feet in depth along the footer of the...

  9. GREAT I. A Position Paper of the PPIWG (Public Participation and Information Work Group) Executive Board.

    DTIC Science & Technology

    1978-09-01

    Jim C. Coxe Material Placement Arnold Vogel Misc. and various topics Edward Oldenburg Material placement Allen Varo Rip-rap needs Winona Port Authority...managemnt for all reeourcee. Should costs rais . to a level unacceptable to th the raer/conabsir the burden of proof to find ways to lower costs (i.e

  10. 6. DARK CANYON SIPHON Photographic copy of historic photo, ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    6. DARK CANYON SIPHON - Photographic copy of historic photo, January 29, 1907 (original print filed in Record Group 115, National Archives, Washington, D.C.) W.J.Lubken, photographer 'RIPRAP AT THE ENTRANCE END OF DARK CANYON PRESSURE PIPE' - Carlsbad Irrigation District, Dark Canyon Siphon, On Main Canal, 1 mile South of Carlsbad, Carlsbad, Eddy County, NM

  11. Remedial action plan and site design for stabilization of the inactive uranium mill tailings sites at Rifle, Colorado. Volume 5, Addenda D6--D8 to Appendix D: Final report

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Not Available

    1990-02-01

    This volume contains appendices D6 through D8 containing laboratory test data: from MK-F investigation, 1987, Old Rifle and New Rifle sites; on bentonite amended radon barrier material; and from MK-F investigation, 1987, riprap tests.

  12. 78 FR 30298 - Alabama Power Company; Notice of Application Accepted for Filing and Soliciting Comments, Motions...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-05-22

    ... the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp . You must include your name and..., and three multi-slip boat docks to accommodate 42 watercraft. Approximately 290 feet of riprap and 158... is owned by the permittee and located outside of the project boundary. The proposed boat docks would...

  13. Boat-Wave-Induced Bank Erosion on the Kenai River, Alaska

    DTIC Science & Technology

    2008-03-01

    with coir log habitat restoration. .....................................................................75 Figure 51. Type 1 bank with willow...various types of streambank stabilization. Common stabilization techniques consist of root wads, spruce tree revetments, coir logs, and riprap...restoration. ERDC TR-08-5 75 Figure 50. Type 1 bank with coir log habitat restoration. Figure 51. Type 1 bank with willow plantings/ladder access habitat

  14. 76. Photographic copy of historic photo, ca. 1935, (original print ...

    Library of Congress Historic Buildings Survey, Historic Engineering Record, Historic Landscapes Survey

    76. Photographic copy of historic photo, ca. 1935, (original print filed in Record Group 115, National Archives, Washington, D.C.). CCC ENROLLEES PLACING ROCK RIPRAP ON UPSTREAM FACE OF DEER FLAT DAM TO PREVENT EROSION OF EARTH FILL BY WIND AND WAVE ACTION-BIOSE FEDERAL RECLAMATION PROJECT-IDAHO. - Boise Project, Deer Flat Embankments, Lake Lowell, Nampa, Canyon County, ID

  15. Stabilizing eroding streambanks in sand drift areas of the Lake States.

    Treesearch

    Edward A. Hansen

    1968-01-01

    Banks are stabilized to protect adjacent high-value items such as cabins and campgrounds, or to reduce reservoir or lake sedimentation rates. Also, bank stabilization is undertaken as one part of fish habitat improvement programs. Rock rip-rap is the best material for bank stabilization in most cases. It does not deteriorate with time and it blends in well with the...

  16. Functional and taxonomic plant diversity for riverbank protection works: bioengineering techniques close to natural banks and beyond hard engineering.

    PubMed

    Cavaillé, Paul; Ducasse, Léon; Breton, Vincent; Dommanget, Fanny; Tabacchi, Eric; Evette, André

    2015-03-15

    Erosion control is a major issue in the Prealps region since piedmont is subject to both intense flood hazards and anthropic pressure. Riverbank protections may have major impacts on local ecosystem functioning and ecological corridor continuity. This study aimed to estimate the effects of the types of riverbank protection technique (from pure riprap to pure bioengineering) on the taxonomic and ecological composition of plant communities in comparison with unmanaged riverbanks as the referential system. Thirty-eight embankments were sampled in the foothills of the French and Swiss Alps. Four distinct riverbank techniques were analyzed and natural young willow stands were chosen as the referential system. At each site, vegetation was sampled along three transects from the waterline to the top of the riverbank. Plant communities were characterized using biological group composition (growth forms and life history, life strategies and distribution in space and time) and functional diversity indices (MFAD, FDc and wFDc). We identified 177 distinct plant species on 38 sites. Higher species richness levels were observed on bioengineered banks (from an average of 12 species recorded on ripraps to 27 species recorded on bioengineered banks) strongly dominated by Salicaceae species, especially for fascine and cribwall banks. Functional analyses of plant communities highlighted significant differences among bank types (p-value: 0.001) for all selected biological groups. Competitive - ruderal strategy, rooting shoots, stems or leaves that lie down or break off, and unisexual - dioecious, as well as pioneer plants and low shrubs (<4 m tall) distinguished bioengineered bank types. Functional diversity indices confirmed these differences among bank types (MFAD: p-value: 0.002; FDc: p-value: 0.003; wFDc: p-value: 0.005). Riprap always showed the lowest levels on functional diversity indices, fascine and cribwall banks were at the medium level and finally mixed and natural banks the highest level. These results confirm the low ecological potential of purely hard engineering techniques and highlight the similarity of bioengineered techniques and unmanaged riverbanks. Copyright © 2014 Elsevier Ltd. All rights reserved.

  17. Combined effects of climate change and bank stabilization on shallow water habitats of chinook salmon.

    PubMed

    Jorgensen, Jeffrey C; McClure, Michelle M; Sheer, Mindi B; Munn, Nancy L

    2013-12-01

    Significant challenges remain in the ability to estimate habitat change under the combined effects of natural variability, climate change, and human activity. We examined anticipated effects on shallow water over low-sloped beaches to these combined effects in the lower Willamette River, Oregon, an area highly altered by development. A proposal to stabilize some shoreline with large rocks (riprap) would alter shallow water areas, an important habitat for threatened Chinook salmon (Oncorhynchus tshawytscha), and would be subject to U.S. Endangered Species Act-mandated oversight. In the mainstem, subyearling Chinook salmon appear to preferentially occupy these areas, which fluctuate with river stages. We estimated effects with a geospatial model and projections of future river flows. Recent (1999-2009) median river stages during peak subyearling occupancy (April-June) maximized beach shallow water area in the lower mainstem. Upstream shallow water area was maximized at lower river stages than have occurred recently. Higher river stages in April-June, resulting from increased flows predicted for the 2080s, decreased beach shallow water area 17-32%. On the basis of projected 2080s flows, more than 15% of beach shallow water area was displaced by the riprap. Beach shallow water area lost to riprap represented up to 1.6% of the total from the mouth to 12.9 km upstream. Reductions in shallow water area could restrict salmon feeding, resting, and refuge from predators and potentially reduce opportunities for the expression of the full range of life-history strategies. Although climate change analyses provided useful information, detailed analyses are prohibitive at the project scale for the multitude of small projects reviewed annually. The benefits of our approach to resource managers include a wider geographic context for reviewing similar small projects in concert with climate change, an approach to analyze cumulative effects of similar actions, and estimation of the actions' long-term effects. Efectos Combinados del Cambio Climático y la Estabilización de Bordes de Ríos Hábitats de Aguas Poco Profundas del Salmón Chinook. Conservation Biology © 2013 Society for Conservation Biology No claim to original US government works.

  18. Report on: Connecticut River Streambank Erosion Study, Massachusetts, New Hampshire and Vermont

    DTIC Science & Technology

    1979-11-01

    Plastic filter cloths are used with considerable success beneath tiprap and other revetment materials such as articulated concrete blocks . The...rihutior unlimited II. SUPPLEMENTARY NOTES It. KEY WORDS (Continue on fever&e elde ifneceeeery and identify by block number). alluvial channel...erosion boat waves shear stress rock riprap lower bank erosion revetments flow control vegetation 20. ABSTRACT (Continue on reverse aide if neceesary and

  19. Feasibility Study of Improved Methods for Riverbank Stabilization

    DTIC Science & Technology

    1964-11-01

    hose materials which appear to be technically feasible for such applications are listed in Tables I - 1 and I - 2. I-9 Artificial Riprap...the uncompacted asphalt pavement. Those which 1-11 show the most potential for further study are soil cement, synthetic elastomer sheeting, and...uncompated asphalt pavement. Chemical soil stabilization and metal sheeting are too exp~nsive, and the quality of chemically stabilized soil protection is

  20. A geomorphic explanation for a meander cutoff following channel relocation of a coarse-bedded river.

    PubMed

    Thompson, Douglas M

    2003-03-01

    The Veteran's Fishing section of the Blackledge River in central Connecticut was relocated in the late 1950s. The relocation resulted in an unstable channel despite extensive efforts to prevent erosion. Overbank erosion and meander cutoffs were investigated using detailed survey data, characterizations of sediment deposits, flow modeling, and a moment-stability analysis. Limited reworking of revetment boulders indicate that riprap bank material was immobile during a 1979 flood event responsible for the formation of the cutoff channel. A moment-stability analysis factor-of-safety value of 1.1 supports the conclusion that riprap was not directly eroded from the banks. Alluvial particles with d(95) values ranging up to 120 mm were deposited along a bar downstream from the cutoff channel at flows estimated to be below a 1.5-year recurrence interval flow. Development of the bar deposit resulted in locally elevated water surfaces at high flow. The resulting overbank flow across the meander neck to the adjacent downstream bend led to the creation of an upstream migrating knickpoint, the erosion of approximately 16,000-year-old sediments, and the subsequent meander cutoff. The results of the study indicate that traditional erosion-control measures cannot prevent extreme channel adjustments if the geomorphic processes that control sediment continuity also are not considered.

  1. Level II scour analysis for Bridge 23 (WODSTH00180023) on Town Highway 18, crossing North Bridgewater Brook, Woodstock, Vermont

    USGS Publications Warehouse

    Olson, Scott A.; Weber, Matthew A.

    1996-01-01

    Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. The scour analysis results are presented in tables 1 and 2 and a graph of the scour depths is presented in figure 8.

  2. Level II scour analysis for Bridge 22 (CRAFTH00180022) on Town Highway 18, crossing Black River, Craftsbury, Vermont

    USGS Publications Warehouse

    Ayotte, Joseph D.

    1996-01-01

    Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. The scour analysis results are presented in tables 1 and 2 and a graph of the scour depths is presented in figure 8.

  3. Level II scour analysis for Bridge 31 (ALBATH00380031) on Town Highway 38, crossing the Black River, Albany, Vermont

    USGS Publications Warehouse

    Boehmler, Erick M.

    1996-01-01

    Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. The scour analysis results are presented in tables 1 and 2 and a graph of the scour depths is presented in figure 8.

  4. Level II scour analysis for Bridge 25 (ALBATH00250030) on Town Highway 25, crossing the Black River, Albany, Vermont

    USGS Publications Warehouse

    Boehmler, Erick M.

    1996-01-01

    Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. The scour analysis results are presented in tables 1 and 2 and a graph of the scour depths is presented in figure 8.

  5. Level II scour analysis for Bridge 6 (IRASTH00050006) on Town Highway 5, crossing the Black River, Irasburg, Vermont

    USGS Publications Warehouse

    Olson, Scott A.

    1996-01-01

    Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. The scour analysis results are presented in tables 1 and 2 and a graph of the scour depths is presented in figure 8.

  6. Level II scour analysis for Bridge 2 (CRAFTH00590002) on Town Highway 59, crossing Black River, Craftsbury, Vermont

    USGS Publications Warehouse

    Ayotte, Joseph D.

    1996-01-01

    Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. The scour analysis results are presented in tables 1 and 2 and a graph of the scour depths is presented in figure 8.

  7. Level II scour analysis for Bridge 26 (CRAFTH00250026) on Town Highway 25, crossing Black River, Craftsbury, Vermont

    USGS Publications Warehouse

    Ayotte, Joseph D.

    1996-01-01

    Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. The scour analysis results are presented in tables 1 and 2 and a graph of the scour depths is presented in figure 8.

  8. Mississippi River, Coon Rapids Dam to Ohio River: feasibility report No. 1 for flood damage reduction, Muscatine Island Levee District, City of Muscatine, Iowa and Muscatine-Louisa County drainage district No. 13, Iowa

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Not Available

    1985-08-01

    Flood protection measures are proposed for the Muscatine Island Levee District and the Muscatine-Louisa County Drainage District No. 13 in southeastern Iowa. The project site is located between Mississippi River mile 455 and mile 442. The preferred plan would involve raising approximately 15.6 miles of the existing levee an average of two feet with hydraulic fill from the Mississippi River. The levee would be expanded on the landward side for most of its length. A 7500-foot segment in the northern section of the project area would be expanded riverward to avoid encroachment on existing industrial, commercial, and residential development. Concretemore » floodwalls would be used in four areas in the city of Muscatine, where space requirements did not allow for levee expansion. Associated features of the project would include raising and resurfacing existing road ramps, construction of a railroad closure at station 9 + 00 in Muscatine, modification of the discharge pipes at the Michael Creek pumping station, and mitigation of recreational fishing opportunities affected by the riverward levee expansion. The levee would be seeded with grasses and receive additional riprap where riprap currently exists. First costs of the project are estimated at $6.0 million.« less

  9. Channel Control Structures for Souris River, Minot, North Dakota. Hydraulic Model Investigation.

    DTIC Science & Technology

    1981-04-01

    in good agreement with other broad - and sharp - crested weirs . 19. Early testing of the typical type I structure indicated that the size of the riprap...III structure (Figure 4) will consist of a concrete weir with a crest lo- cated 10.0 ft above the channel bottom with a 1-ft-high end sill at the end...to the channel, was effective in preventing significant head differ- ential and damage to the strucLure with overbank flow conditions. The weir crest

  10. National Program for Inspection of Non-Federal Dams. Powdermill Brook Detention Dam (MA 00605) Connecticut River Basin, Westfield, Massachusetts. Phase I Inspection Report.

    DTIC Science & Technology

    1978-08-01

    Date Not Known Surface Cracks None observed Pavement Condition No Pavement Movement or Settlement of Crest None observed Lateral Movement None...Protection - Riprap Failures No riprapp ap • .• Unusual Movement or Cracking at or None observed near Toes Unusual Embankment or Downstream None...Seepage or Efflorescence None observed Joint Alignment Good Unusual Seepage or Leaks in Gate Chamber Cracks None observed . Rusting or Corrosion of

  11. Emergency Plan for Sandy Lake Dam and Reservoir

    DTIC Science & Technology

    1987-06-01

    UTFLOW 0I J" I - " -I I 0 5 I0 15 20 25 30 TIME IN DAYS p CT WITHOUT FAILURE ELEVATION HYDROGRAPHS -1235 -!230 -1225 >z DESIGN POOL ELEVATION iui LiL...harrowing, fertilizing , digging sprigs, hauling sprigs, scattering sprigs, disking, seeding and watering. Typical crew: Riprap - 1 crew leader and 6 to...LEVEL Name of Resource Type of Resource Address Phone Number Brisson Pump Company Pump Distributor 2359 E. Cowern Place (612) 777-3317 N. St. Paul, MN

  12. National Dam Safety Program. Lakeview Estates Dam (MO 11004), Mississippi - Kaskaskia - St. Louis Basin, Warren County, Missouri. Phase I Inspection Report.

    DTIC Science & Technology

    1979-09-01

    ificatiozh Distributon/ Availabilit oe LAKEVIEW ESTATES DAM WARREN COUNTY, MISSOURI MISSOURI INVENTORY NO. 11004 PHASE I INSPECTION REPORT NATIONAL DAM SAFETY...and *impounds less than 1,000 acre-feet of water . Our inspection and evaluation indicates that the spill- way of Lakeview Estates Dam does not meet...not be measured because of high reservoir level, scalloping near the crest and a berm just under the water surface. Limestone riprap in sizes from sand

  13. Approximate Upper Limit of Irregular Wave Runup on Riprap.

    DTIC Science & Technology

    1988-05-01

    MAR 8" P editon ’ayb e used utlI exhausteo SC.A’ (ASS,4CA’ON 01_’- S PA(E_ All other ed,t,os are obsolete Unclassified ;I . % ", .. , r .,., . ,C_...Manager, CERC, and Mr. C. E . Chatham, Jr., Chief, Wave Dynamics Division, CERC. COL Dwayne G. Lee, CE, was Commander and Director of WES during the 0...prevent exceedance by runup or to estimate the potential severity of wave overtopping. e PART II: SOURCES OF DATA, TEST SETUPS, AND A. TEST CONDITIONS 3

  14. Long-Term Drainage from the Riprap Side Slope of a Surface Barrier

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Zhang, Zhuanfang

    Surface barriers designed to isolate underground nuclear waste in place are expected to function for at least 1000 years. To achieve this long design life, such barriers need to be protected with side slopes against wind- and water-induced erosion and damage by natural or human activities. However, the side slopes are usually constructed with materials coarser than the barrier. Their hydrological characteristics must be understood so that any drainage from them is considered in the barrier design and will not compromise the barrier function. The Prototype Hanford Barrier, an evapotranspiration-capillary (ETC) barrier, was constructed in 1994 at the Hanford Sitemore » in southeastern Washington state, with a gravel side slope and a riprap side slope. The soil water content in the gravel side slope and drainage from both side slopes have been monitored since the completion of construction. The monitoring results show that under natural precipitation the annual drainage rates from the two types of side slopes were very similar and about 5 times the typical recharge from local soil with natural vegetation and 40 times the barrier design criterion. The higher recharge from the side slopes results in some of the drainage migrating laterally to the region beneath the ETC barrier. This edge effect of the enhanced drainage was evaluated for a period of 1000 years by numerical simulation. The edge effect was quantified by the amount of water across the barrier edges and the affecting distance of the barrier edges. These results indicate that design features can be adjusted to reduce the edge effect when necessary.« less

  15. Rock ramp design guidelines

    USGS Publications Warehouse

    Mooney, David M.; Holmquist-Johnson, Christopher L.; Broderick, Susan

    2007-01-01

    Rock ramps or roughened channels consist of steep reaches stabilized by large immobile material (riprap). Primary objectives for rock ramps include: Create adequate head for diversionMaintain fish passage during low-flow conditionsMaintain hydraulic conveyance during high-flow conditionsSecondary objectives for rock ramp design include:Emulate natural systemsMinimize costsThe rock ramp consists of a low-flow channel designed to maintain biologically adequate depth and velocity conditions during periods of small discharges. The remainder of the ramp is designed to withstand and pass large flows with minimal structural damage. The following chapters outline a process for designing rock ramps.

  16. Assessing juvenile salmon rearing habitat and associated predation risk in a lower Snake River reservoir

    USGS Publications Warehouse

    Tiffan, Kenneth F.; Hatten, James R.; Trachtenbarg, David A

    2015-01-01

    Subyearling fall Chinook salmon (Oncorhynchus tshawytscha) in the Columbia River basin exhibit a transient rearing strategy and depend on connected shoreline habitats during freshwater rearing. Impoundment has greatly reduced the amount of shallow-water rearing habitat that is exacerbated by the steep topography of reservoirs. Periodic dredging creates opportunities to strategically place spoils to increase the amount of shallow-water habitat for subyearlings while at the same time reducing the amount of unsuitable area that is often preferred by predators. We assessed the amount and spatial arrangement of subyearling rearing habitat in Lower Granite Reservoir on the Snake River to guide future habitat improvement efforts. A spatially explicit habitat assessment was conducted using physical habitat data, two-dimensional hydrodynamic modelling and a statistical habitat model in a geographic information system framework. We used field collections of subyearlings and a common predator [smallmouth bass (Micropterus dolomieu)] to draw inferences about predation risk within specific habitat types. Most of the high-probability rearing habitat was located in the upper half of the reservoir where gently sloping landforms created low lateral bed slopes and shallow-water habitats. Only 29% of shorelines were predicted to be suitable (probability >0.5) for subyearlings, and the occurrence of these shorelines decreased in a downstream direction. The remaining, less suitable areas were composed of low-probability habitats in unmodified (25%) and riprapped shorelines (46%). As expected, most subyearlings were found in high-probability habitat, while most smallmouth bass were found in low-probability locations. However, some subyearlings were found in low-probability habitats, such as riprap, where predation risk could be high. Given their transient rearing strategy and dependence on shoreline habitats, subyearlings could benefit from habitat creation efforts in the lower reservoir where high-probability habitat is generally lacking. Published 2015. This article is a U.S. Government work and is in the public domain in the USA.

  17. Delineation of tidal scour through marine geophysical techniques at Sloop Channel and Goose Creek bridges, Jones Beach State Park, Long Island, New York

    USGS Publications Warehouse

    Stumm, Frederick; Chu, Anthony; Reynolds, Richard J.

    2001-01-01

    Inspection of the Goose Creek Bridge in southeastern Nassau County in April 1998 by the New York State Department of Transportation (NYSDOT) indicated a separation of bridge piers from the road bed as a result of pier instability due to apparent seabed scouring by tidal currents. This prompted a cooperative study by the U.S. Geological Survey with the NYSDOT to delineate the extent of tidal scour at this bridge and at the Sloop Channel Bridge, about 0.5 mile to the south, through several marine- geophysical techniques. These techniques included use of a narrow-beam, 200-kilohertz, research-grade fathometer, a global positioning system accurate to within 3 feet, a 3.5 to 7-kilohertz seismic-reflection profiler, and an acoustic Doppler current profiler (ADCP). The ADCP was used only at the Sloop Channel Bridge; the other techniques were used at both bridges.Results indicate extensive tidal scour at both bridges. The fathometer data indicate two major scour holes nearly parallel to the Sloop Channel Bridge—one along the east side, and one along the west side (bridge is oriented north-south). The scour-hole depths are as much as 47 feet below sea level and average more than 40 feet below sea level; these scour holes also appear to have begun to connect beneath the bridge. The deepest scour is at the north end of the bridge beneath the westernmost piers. The east-west symmetry of scour at Sloop Channel Bridge suggests that flood and ebb tides produce extensive scour.The thickness of sediment that has settled within scour holes could not be interpreted from fathometer data alone because fathometer frequencies cannot penetrate beneath the sea-floor surface. The lower frequencies used in seismic-reflection profiling can penetrate the sea floor and underlying sediments, and indicate the amount of infilling of scour holes, the extent of riprap under the bridge, and the assemblages of clay, sand, and silt beneath the sea floor. The seismic- reflection surveys detected 2 to 5 feet of sediment filling the scour holes at both bridges; this indicates that the fathometer surveys were undermeasuring the effective depth of bridge scour by 2 to 5 feet through their inability to penetrate the infilled sediment. Several clay layers with thicknesses of 3 to 5 feet were detected beneath the sea floor at both bridges. Most of the piers beneath Sloop Channel Bridge appear to be surrounded by riprap, but, in several areas the riprap appears to be slumping or sliding into adjacent scour holes. Similar slumping was indicated at the Goose Creek Bridge. Most of the sediment underlying the sea floor at both bridges is interpreted as a fine-grained, cross-bedded sand.ADCP data from Sloop Channel indicate that the constricted flow beneath the bridge increases the horizontal current velocities from 2 to 6 feet per second. Total measured discharge beneath Sloop Channel Bridge was 41,800 cubic feet per second at flood tide and 27,600 cubic feet per second at ebb tide.

  18. 200-BP-1 Prototype Hanford Barrier Annual Monitoring Report for Fiscal Year 2004

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Ward, Andy L.; Linville, Jenifer K.; Keller, Jason M.

    2005-01-03

    In FY 2004, monitoring of the prototype Hanford barrier focused on barrier stability, vegetative cover, evidence of plant and animal intrusion, and the main components of the water balance. Monitored water-balance components included precipitation, runoff, storage, drainage, and deep percolation. Precipitation in FY 2004 was 26 percent less than in FY 2003 but was still higher than normal. The seasonal distribution in precipitation was also different from the previous year with a 43 percent reduction in spring precipitation and a 46 percent increase in summer precipitation. The cumulative amount of water received from October 1994, through September 2004, was 2,559.58more » mm on the northern half of the barrier, which is the formerly irrigated treatment, and 1,886.71 mm on the southern non-irrigated treatments. Water storage continued to show a cyclic pattern, increasing in the winter and declining in the spring and summer to a lower limit of about 100 mm in response to evapotranspiration. The 600-mm design storage has never been exceeded. Total drainage from the soil-covered plots range from 2.9E-4 mm to 0.22 mm or 0.003 6 0.004 percent of precipitation. Side-slope drainage was much higher at 20.9 6 2.3 percent of precipitation from the gravel and 18.6 6 5.1 percent from the riprap. There was no runoff from the barrier, but runoff from the BY tank farm following a thunderstorm in May eroded a 45-inch-deep channel into the structural fill at the toe of the riprap slope. Above-asphalt and below-asphalt moisture measurements show no evidence of deep percolation of water. Topographic surveys were conducted on the barrier surface, including the two settlement gauges and 12 creep gauges on the riprap slope using aerial photogrammetry (AP) and a global positioning system (GPS). Comparing the aerial photogrammetry (AP) and global positioning system (GPS) surveys with the traditional survey shows the barrier and side slopes to be stable. Both AP and GPS show potential for considerable cost savings without any loss in accuracy. A relatively high coverage of native plants still persists after the initial revegetation in 1994. The formerly irrigated treatments continue to show greater cover of grasses and litter than the non-irrigated treatments. On the formerly irrigated treatments, the mean cover class was 25 to 50 percent for both grasses and shrubs. On the non-irrigated treatments, the mean cover class was 5 to 25 percent from grasses and 25 to 50 percent for shrubs. Species diversity of the vegetative community appears to have stabilized over the past several years. In addition to 12 of 17 species present in 2003 being present in 2004, two additional species were encountered. Sagebrush continues to flourish with shrubs along the perimeter showing higher biomass yield than the interior shrubs. There is evidence of sagebrush seedlings recruitment but not of rabbitbrush; the presence of gray rabbitbrush appears is declining as the barrier surface continues to stabilize. Use of the barrier surface by insects and small mammals is also evident. Small mammal burrowing on the barrier surface has become more prevalent in recent years, suggesting that the restored barrier surface is beginning to function as a recovering ecosystem. Small-mammal burrowing on the top and sides of the barrier is most prevalent on the finer-grained and disturbed soils while active ant mounds were observed on the northern and western slopes.« less

  19. Two-Dimensional Simulation of Flow and Evaluation of Bridge Scour at Structure A-1700 on Interstate 155 over the Mississippi River near Caruthersville, Missouri

    USGS Publications Warehouse

    Huizinga, Richard J.

    2007-01-01

    The evaluation of scour at bridges throughout the State of Missouri has been ongoing since 1991, and most of these evaluations have used one-dimensional hydraulic analysis and application of conventional scour depth prediction equations. Occasionally, the complex conditions of a site dictate a more thorough assessment of the stream hydraulics beyond a one-dimensional model. This was the case for structure A-1700, the Interstate 155 bridge crossing the Mississippi River near Caruthersville, Missouri. To assess the complex hydraulics at this site, a two-dimensional hydrodynamic flow model was used to simulate flow conditions on the Mississippi River in the vicinity of the Interstate 155 structure A-1700. The model was used to simulate flow conditions for three discharges: a flood that occurred on April 4, 1975 (the calibration flood), which had a discharge of 1,658,000 cubic feet per second; the 100-year flood, which has a discharge of 1,960,000 cubic feet per second; and the project design flood, which has a discharge of 1,974,000 cubic feet per second. The project design flood was essentially equivalent to the flood that would cause impending overtopping of the mainline levees along the Mississippi River in the vicinity of structure A-1700. Discharge and river-stage readings from the flood of April 4, 1975, were used to calibrate the flow model. The model was then used to simulate the 100-year and project design floods. Hydraulic flow parameters obtained from the three flow simulations were applied to scour depth prediction equations to determine contraction, local pier, and abutment scour depths at structure A-1700. Contraction scour and local pier scour depths computed for the project design discharge generally were the greatest, whereas the depths computed for the calibration flood were the least. The maximum predicted total scour depth (contraction and local pier scour) for the calibration flood was 66.1 feet; for the 100-year flood, the maximum predicted total scour depth was 74.6 feet; for the project design flood, the maximum predicted total scour depth was 93.0 feet. If scour protection did not exist, bent 14 and piers 15 through 21 would be substantially exposed or undermined by the predicted total scour depths in all of the flood simulations. However, piers 18 through 21 have a riprap blanket around the base of each, and the riprap blanket observed on the right bank around bent 14 is thought to extend around the base of pier 15, which would limit the amount of scour that would occur at these piers. Furthermore, the footings and caissons that are not exposed by computed contraction scour may arrest local pier scour, which will limit local pier scour at several bents and piers. Nevertheless, main-channel piers 16 and 17 and all of the bents on the left (as viewed facing downstream) overbank are moderately to substantially exposed by the predicted scour depths from the three flood simulations, and there is no known scour protection at these piers or bents. Abutment scour depths were computed for structure A-1700, but abutment scour is expected to be mitigated by the presence of guidebanks upstream from the bridge abutments, as well as riprap revetment on the abutment and guidebank faces.

  20. Cibola High Levee Pond Annual Report 2003. Interim Report

    USGS Publications Warehouse

    Mueller, G.A.; Carpenter, J.; Marsh, P.C.; Minckley, C.O.

    2003-01-01

    Bonytail and razorback sucker have once again spawned and produced swim-up larvae in Cibola High Levee Pond (CHLP). CHLP continues to support annual recruitment of bonytail while recent razorback sucker recruitment remains elusive. Thus far, razorbacks have experienced intermittent years of spawning success. Both native species were observed spawning on, or near, the riprap on the river levee. Razorbacks spawned from late January until mid-March over gravel and large cobble along the levee toe (2-3 m depth) and bonytail spawned along the levee shoreline during mid-April. Razorback suckers rapidly fin during the reproductive act, which flushes fines from the substrate and leaves gravel relatively clean. Bonytail on the other hand, appear to spawn over or on substrate that has been disturbed by beaver activity. Substrate scour or disturbance appears to be an important factor in spawning site selectiona?|

  1. Enhanced Cover Assessment Project:Soil Manipulation and Revegetation Tests

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Waugh, W. Joseph; Albright, Dr. Bill; Benson, Dr. Craig

    2014-02-01

    The U.S. Department of Energy Office of Legacy Management is evaluating methods to enhance natural changes that are essentially converting conventional disposal cell covers for uranium mill tailings into water balance covers. Conventional covers rely on a layer of compacted clayey soil to limit exhalation of radon gas and percolation of rainwater. Water balance covers rely on a less compacted soil “sponge” to store rainwater, and on soil evaporation and plant transpiration (evapotranspiration) to remove stored water and thereby limit percolation. Over time, natural soil-forming and ecological processes are changing conventional covers by increasing hydraulic conductivity, loosening compaction, and increasingmore » evapotranspiration. The rock armor on conventional covers creates a favorable habitat for vegetation by slowing soil evaporation, increasing soil water storage, and trapping dust and organic matter, thereby providing the water and nutrients needed for plant germination, survival, and sustainable transpiration. Goals and Objectives Our overall goal is to determine if allowing or enhancing these natural changes could improve cover performance and reduce maintenance costs over the long term. This test pad study focuses on cover soil hydrology and ecology. Companion studies are evaluating effects of natural and enhanced changes in covers on radon attenuation, erosion, and biointrusion. We constructed a test cover at the Grand Junction disposal site to evaluate soil manipulation and revegetation methods. The engineering design, construction, and properties of the test cover match the upper three layers of the nearby disposal cell cover: a 1-foot armoring of rock riprap, a 6-inch bedding layer of coarse sand and gravel, and a 2-foot protection layer of compacted fine soil. The test cover does not have a radon barrier—cover enhancement tests leave the radon barrier intact. We tested furrowing and ripping as means for creating depressions parallel to the slope contour, bringing soil up into the rock riprap layer, and loosening and blending compacted fine soil with coarse sand and gravel layers. Objectives of these manipulations include (1) enhancing root growth, (2) increasing seed-soil contact, (3) catching runoff water for plant germination and growth, (4) increasing soil water storage capacity, and (5) enhancing deep drying by disrupting the capillary barrier at the interface of the bedding and protection layers.« less

  2. Use of a ground-penetrating radar system to detect pre-and post-flood scour at selected bridge sites in New Hampshire, 1996-98

    USGS Publications Warehouse

    Olimpio, Joseph R.

    2000-01-01

    Ground-penetrating radar was used to measure the depth and extent of existing and infilled scour holes and previous scour surfaces at seven bridges in New Hampshire from April 1996 to November 1998. Ground-penetrating-radar survey techniques initially were used by the U.S. Geological Survey to study streambed scour at 30 bridges. Sixteen of the 30 bridges were re-surveyed where floods exceeded a 2-year recurrence interval. A 300-megahertz signal was used in the ground-penetrating radar system that penetrated through depths as great as 20 feet of water and as great as 32 feet of streambed materials. Existing scour-hole dimensions, infilled thickness, previous scour surfaces, and streambed materials were detected using ground-penetrating radar. Depths to riprap materials and pier footings were identified and verified with bridge plans. Post data-collection-processing techniques were applied to assist in the interpretation of the data, and the processed data were displayed and printed as line plots. Processing included distance normalization, migration, and filtering but processing was kept to a minimum and some interference from multiple reflections was left in the record. Of the 16 post-flood bridges, 22 ground-penetrating-radar cross sections at 7 bridges were compared and presented in this report. Existing scour holes were detected during 1996 (pre-flood) data collection in nine cross sections where scour depths ranged from 1 to 3 feet. New scour holes were detected during 1998 (post-flood) data collection in four cross sections where scour depths were as great as 4 feet deep. Infilled scour holes were detected in seven cross sections, where depths of infilling ranged from less than 1 to 4 feet. Depth of infilling by means of steel rod and hammer was difficult to verify in the field because of cobble and boulder streambeds or deep water. Previous scour surfaces in streambed materials were identified in 15 cross sections and the depths to these surfaces ranged from 1 to 10 feet below the streambed. Riprap materials or pier footings were identified in all cross sections. Calculated record depths generally agree with bridge plans. Pier footings were exposed at two bridges and steel pile was exposed at one bridge. Exposures were verified by field observations.

  3. Monitoring Changes in Channel Morphology in Las Vegas Wash with Global Fiducials Program Imagery

    NASA Astrophysics Data System (ADS)

    Wheeler, D. J.

    2012-12-01

    To borrow from a popular adage, "What happens in Las Vegas [Wash], stays in Las Vegas [Wash]"—but only with a lot of help. This past decade has seen a concerted effort to curb erosion and sediment transport along the 12 mile long channel between East Las Vegas and Lake Mead. Las Vegas Wash is prototypical of an urban river in an arid environment that is being impacted by increasing urban development and impervious surface runoff within its drainage area. Rapid urbanization since the 1970s has increased the flow of water into Las Vegas Wash, causing severe channel destabilization. Within two decades millions of cubic yards of rocks and sediment were scoured out of the wash and transported downstream to Lake Mead. The wetlands that once covered over 2,000 acres within Las Vegas Wash dwindled to 200 acres in the 1990s as the channel became as much as 40 feet deeper and 300 feet wider at some points. In 1999 the Las Vegas Wash Coordination Committee (LVWCC) initiated a 20-year plan to construct erosion control structures (weirs) for channel stabilization and rock riprap for stream bank protection. The hope is to design structures that will slow down the water flow, trap sediments, and to eventually restore much of the wetland environment. Using high-resolution satellite imagery from the Global Fiducials Program Library housed at the U. S. Geological Survey, this transition is being tracked from 1999 to the present. From November 1999 to July 2008 new residential and commercial development has claimed an additional 12 square kilometers (3000 acres) of land in Henderson, NV, along the south side of Las Vegas Wash. Even with the increased volume of surface and groundwater runoff entering the wash, current sediment yields are much lower than the 1999 totals. The imagery documents the construction of 14 of the 22 LVWCC planned weirs by the year 2011. It also shows many miles of stream bank stabilization by riprap, planting of riparian vegetation and placing of obstructions in the channel. The replanting of native vegetation on storm debris flats is stabilizing some of the soil in the wash and also rejuvenating much of the wetland habitat. Las Vegas Wash is a test bed for the design and implementation of innovative methods for modifying stream morphology to achieve desirable results, as some of these methods are deemed successful and some are not as effective. The lessons learned about curbing erosion and sediment transport within Las Vegas Wash may be applied to other urban streams in arid environments.

  4. Level II scour analysis for Bridge 42 (RANDVT00120042) on State Highway 12, crossing Third Branch White River, Randolph, Vermont

    USGS Publications Warehouse

    Olson, Scott A.; Weber, Matthew A.

    1996-01-01

    bridge consisting of four concrete spans. The maximum span length is 57 ft. (Vermont Agency of Transportation, written commun., July 29, 1994). The bridge is supported by vertical, concrete abutments and three concrete piers. The toe of the left abutment is at the channel edge. The toe of the right abutment is set back on the right over-bank. The roadway centerline on the structure has a slight horizontal curve; however, the main channel is skewed approximately 5 degrees to the bridge. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. The scour analysis results are presented in tables 1 and 2 and a graph of the scour depths is presented in figure 8.

  5. Solidification/stabilization of spent abrasives and use as nonstructural concrete

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Brabrand, D.J.; Loehr, R.C.

    1993-01-01

    Tons of spent abrasives result each year from the removal of old paint from bridges. Because the spent abrasives contain metals from the paint, some spent abrasives may be considered hazardous by the Toxicity Characteristic (TC) criteria. Incorporation of the spent blasting abrasives in nonstructural concrete (rip-rap, dolphins) offers an opportunity to recycle the spent abrasives while immobilizing potentially leachable metals. This study focused on the Portland Cement Solidification/Stabilization (S/S) of spent blasting abrasives taken from a bridge located in Southeast Texas. The study examined (a) the cadmium, chromium, and lead concentrations in extracts obtained by using the Toxicity Characteristicmore » Leaching Procedure (TCLP) and (b) the compressive strengths of Portland Cement mixes that contained different amounts of the spent abrasives. Performance was measured by meeting the TC criteria as well as the requirements for compressive strength. Study results indicated that considerable quantities of these spent abrasives can be solidified/stabilized while reducing the leachability of cadmium, chromium, and lead and producing compressive strengths over 6,895 kN/m[sup 2] (1,000 psi).« less

  6. Ecology of the Sand Roller (Percopsis transmontana) in a lower Snake River Reservoir, Washington

    USGS Publications Warehouse

    Tiffan, Kenneth F.; Erhardt, John M.; Rhodes, Tobyn N.; Hemingway, Rulon J.

    2017-01-01

    The Sand Roller (Percopsis transmontana), has not been abundant in the Snake River since it was first found in the system in the 1950s, but its population has apparently increased in recent years. As a result, we initiated a study to better understand its ecology in habitats of Lower Granite Reservoir. From November 2014 to October 2015, Sand Rollers were present along shorelines, with peak abundance being observed during spring months. Logistic regression analyses showed that Sand Rollers were more likely to be present in shoreline habitats at temperatures ≤18.4°C. Fish were found over a range of substrates, with the lowest odds of fish presence being associated with riprap, which is common in hydropower reservoirs. From length-frequency analysis, we suggest that Sand Roller spawning occurs primarily in May and early June. Assessment of Sand Roller diets found dipteran (chironomid) larvae and pupae were the most important prey consumed by all sizes of Sand Rollers, but Opossum Shrimp (Neomysis mercedis) were also prominent in diets of larger fish in shoreline and offshore habitats. At a time when the populations of so many native species are in decline, the increase of the Sand Roller population in the lower Snake River represents a positive, yet curious occurrence.

  7. Stability evaluation of modernized bank protections in a culvert construction

    NASA Astrophysics Data System (ADS)

    Cholewa, Mariusz; Plesiński, Karol; Kamińska, Katarzyna; Wójcik, Izabela

    2018-02-01

    The paper presents stability evaluation of the banks of the Wilga River on a chosen stretch in Koźmice Wielkie, Małopolska Province. The examined stretch included the river bed upstream from the culvert on a district road. The culvert construction, built over four decades ago, was disassembled in 2014. The former construction, two pipes that were 1.4 m in diameter, was entirely removed. The investor decided to build a new construction in the form of insitu poured reinforced concrete with a 4 x 2 m cross section. Change of geometry and different location in relation to the river current caused increase in the flow velocity and, as a consequence, erosion of both protected and natural banks. Groundwater conditions were determined based on the geotechnical tests that were carried out on soil samples taken from the banks and the river bed. Stability calculations of natural slopes of the Wilga River and the ones protected with riprap indicate mistakes in the design project concerning construction of the river banks. The purpose of the study was to determine the stability of the Wilga River banks on a selected section adjacent to the rebuilt culvert. Stability of a chosen cross section was analysed in the paper. Presented conclusions are based on the results of geotechnical tests and numerical calculations.

  8. Level II scour analysis for Bridge 28 (BRIDTH00440028) on Town Highway 044 crossing Plymouth Brook, Bridgewater, Vermont

    USGS Publications Warehouse

    Olson, Scott A.; Ayotte, Joseph D.

    1996-01-01

    The town highway 5 crossing of the Black River is a 70-ft-long, two-lane bridge consisting of one 65-foot clear span (Vermont Agency of Transportation, written commun., August 2, 1994). The bridge is supported by vertical, concrete abutments with wingwalls. There is also a retaining wall along the upstream side of the road embankments. The channel is skewed approximately 20 degrees to the opening while the opening-skew-to-roadway is 15 degrees. A scour hole 3.0 ft deeper than the mean thalweg depth was observed along the right abutment. The scour hole was 27 feet long, 15 feet wide, and was 2.5 feet below the abutment footing at the time of the Level I assessment. This right abutment had numerous cracks and had settled. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. The scour analysis results are presented in tables 1 and 2 and a graph of the scour depths is presented in figure 8.

  9. Level II scour analysis for Bridge 38 (BETHTH00070038) on Town Highway 007, crossing Gilead Brook, Bethel, Vermont

    USGS Publications Warehouse

    Ivanoff, Michael A.; Song, Donald L.

    1996-01-01

    The town highway 5 crossing of the Black River is a 70-ft-long, two-lane bridge consisting of one 65-foot clear span (Vermont Agency of Transportation, written commun., August 2, 1994). The bridge is supported by vertical, concrete abutments with wingwalls. There is also a retaining wall along the upstream side of the road embankments. The channel is skewed approximately 20 degrees to the opening while the opening-skew-to-roadway is 15 degrees. A scour hole 3.0 ft deeper than the mean thalweg depth was observed along the right abutment. The scour hole was 27 feet long, 15 feet wide, and was 2.5 feet below the abutment footing at the time of the Level I assessment. This right abutment had numerous cracks and had settled. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. The scour analysis results are presented in tables 1 and 2 and a graph of the scour depths is presented in figure 8.

  10. Quantifying the effectiveness of shoreline armoring removal on coastal biota of Puget Sound.

    PubMed

    Lee, Timothy S; Toft, Jason D; Cordell, Jeffery R; Dethier, Megan N; Adams, Jeffrey W; Kelly, Ryan P

    2018-01-01

    Shoreline armoring is prevalent around the world with unprecedented human population growth and urbanization along coastal habitats. Armoring structures, such as riprap and bulkheads, that are built to prevent beach erosion and protect coastal infrastructure from storms and flooding can cause deterioration of habitats for migratory fish species, disrupt aquatic-terrestrial connectivity, and reduce overall coastal ecosystem health. Relative to armored shorelines, natural shorelines retain valuable habitats for macroinvertebrates and other coastal biota. One question is whether the impacts of armoring are reversible, allowing restoration via armoring removal and related actions of sediment nourishment and replanting of native riparian vegetation. Armoring removal is targeted as a viable option for restoring some habitat functions, but few assessments of coastal biota response exist. Here, we use opportunistic sampling of pre- and post-restoration data for five biotic measures (wrack % cover, saltmarsh % cover, number of logs, and macroinvertebrate abundance and richness) from a set of six restored sites in Puget Sound, WA, USA. This broad suite of ecosystem metrics responded strongly and positively to armor removal, and these results were evident after less than one year. Restoration responses remained positive and statistically significant across different shoreline elevations and temporal trajectories. This analysis shows that removing shoreline armoring is effective for restoration projects aimed at improving the health and productivity of coastal ecosystems, and these results may be widely applicable.

  11. Quantifying the effectiveness of shoreline armoring removal on coastal biota of Puget Sound

    PubMed Central

    Toft, Jason D.; Adams, Jeffrey W.

    2018-01-01

    Shoreline armoring is prevalent around the world with unprecedented human population growth and urbanization along coastal habitats. Armoring structures, such as riprap and bulkheads, that are built to prevent beach erosion and protect coastal infrastructure from storms and flooding can cause deterioration of habitats for migratory fish species, disrupt aquatic–terrestrial connectivity, and reduce overall coastal ecosystem health. Relative to armored shorelines, natural shorelines retain valuable habitats for macroinvertebrates and other coastal biota. One question is whether the impacts of armoring are reversible, allowing restoration via armoring removal and related actions of sediment nourishment and replanting of native riparian vegetation. Armoring removal is targeted as a viable option for restoring some habitat functions, but few assessments of coastal biota response exist. Here, we use opportunistic sampling of pre- and post-restoration data for five biotic measures (wrack % cover, saltmarsh % cover, number of logs, and macroinvertebrate abundance and richness) from a set of six restored sites in Puget Sound, WA, USA. This broad suite of ecosystem metrics responded strongly and positively to armor removal, and these results were evident after less than one year. Restoration responses remained positive and statistically significant across different shoreline elevations and temporal trajectories. This analysis shows that removing shoreline armoring is effective for restoration projects aimed at improving the health and productivity of coastal ecosystems, and these results may be widely applicable. PMID:29492331

  12. Design, permitting, and construction issues associated with closure of the Panna Maria uranium tailings impoundment

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Strachan, C.L.; Raabe, K.L.

    1997-12-31

    In 1992, Panna Maria Uranium Operations (PMUO) initiated licensing and engineering activities for closure of the Panna Maria mill and 150-acre tailings impoundment located in southeast Texas. Closure of the tailings impoundment is permitted by license amendment through the Texas Natural Resources Conservation Commission (TNRCC), and based on closure criteria outlined in Texas regulations. The closure plan for the Panna Maria tailings impoundment was submitted for Texas regulatory agency review in April 1993, with details of the closure plan modified in 1994, 1995, and 1996. The closure plan included a multi-layered cover over the regraded tailings surface which was designedmore » for long-term isolation of tailings, reduction of radon emanation to regulated levels, and reduction of infiltration to TNRCC-accepted levels. The cover and embankment slope surfaces and surrounding areas were designed to provide acceptable erosional stability as compared to runoff velocities from the Probable Maximum Precipitation event. Cover materials were selected from on-site materials and evaluated for suitability based on permeability, radon attenuation, and soil dispersivity characteristics. Off-site materials were used when necessary. The cover over the tailings has a maximum slope of 0.5 percent, and the regraded embankment slopes outside the perimeter of the impoundment have a maximum slope of 20 percent. All reclaimed slopes are covered with topsoil and revegetated. A riprap-lined channel is to be used to convey runoff from within the perimeter of the reclaimed impoundment to the north of the impoundment.« less

  13. Modeling Rip Channel and Mega-Cusp Migration With XBeach

    NASA Astrophysics Data System (ADS)

    Orzech, M.; Thornton, E.; Reniers, A.; Macmahan, J.; O'Reilly, B.

    2008-12-01

    The relationship between alongshore rip channel migration and sediment transport is investigated using XBeach, a recently developed 2DH coastal erosion model. XBeach solves the nonlinear shallow water equations and accounts for the effects of breaking waves, wind, turbulent dispersion, and nonlinear bottom friction. It is similar to the more widely used Delft3D but focuses on morphological change to the beach and dune and includes the action of swash on a moving shoreline. Numerics have been simplified to increase model speed and ensure stability in shallow water. XBeach is first validated by recreating a three-year time series of alongshore rip migration patterns measured with video at Fort Ord, near Monterey, CA. The model is initialized with wave spectral data at 15m depth, provided by the Coastal Data Information Program (CDIP). Flow fields and transport patterns are then examined in detail over a single rip channel and mega-cusp to better understand the small scale processes associated with migration, and a range of simulations are conducted to quantify the effects on migration rates of varying wave height, incident angle, or tidal elevation. Results are presented from a four-month period of carefully monitored, accelerated shoreline erosion at the Fort Ord site, which followed the removal of a longstanding riprap barrier that had created a sand dune peninsula extending to the water's edge. Model-predicted erosion rates along the 300m stretch of shoreline are compared with dune retreat measurements for the period.

  14. Landscape assessment of side channel plugs and associated cumulative side channel attrition across a large river floodplain.

    PubMed

    Reinhold, Ann Marie; Poole, Geoffrey C; Bramblett, Robert G; Zale, Alexander V; Roberts, David W

    2018-04-24

    Determining the influences of anthropogenic perturbations on side channel dynamics in large rivers is important from both assessment and monitoring perspectives because side channels provide critical habitat to numerous aquatic species. Side channel extents are decreasing in large rivers worldwide. Although riprap and other linear structures have been shown to reduce side channel extents in large rivers, we hypothesized that small "anthropogenic plugs" (flow obstructions such as dikes or berms) across side channels modify whole-river geomorphology via accelerating side channel senescence. To test this hypothesis, we conducted a geospatial assessment, comparing digitized side channel areas from aerial photographs taken during the 1950s and 2001 along 512 km of the Yellowstone River floodplain. We identified longitudinal patterns of side channel recruitment (created/enlarged side channels) and side channel attrition (destroyed/senesced side channels) across n = 17 river sections within which channels were actively migrating. We related areal measures of recruitment and attrition to the density of anthropogenic side channel plugs across river sections. Consistent with our hypothesis, a positive spatial relationship existed between the density of anthropogenic plugs and side channel attrition, but no relationship existed between plug density and side channel recruitment. Our work highlights important linkages among side channel plugs and the persistence and restoration of side channels across floodplain landscapes. Specifically, management of small plugs represents a low-cost, high-benefit restoration opportunity to facilitate scouring flows in side channels to enable the persistence of these habitats over time.

  15. Poplar Island Environmental Restoration Project: Challenges in waterbird restoration on an island in Chesapeake Bay

    USGS Publications Warehouse

    Erwin, R.M.; Miller, J.; Reese, J.G.

    2007-01-01

    At 460 hectares, the Paul Sarbanes Environmental Restoration Project at Poplar Island, Talbot County, Maryland, represents the largest 'beneficial use' dredged material project of the U. S. Army Corps of Engineers (a cooperative project with Maryland Port Administration). Begun in 1998, the 15-year restoration project will ultimately consist of roughly 220 ha of uplands and 220 ha of tidal wetland habitats, with limited areas of dike roads, perimeter riprap, and unvegetated mudflats. Wetland restoration began in one small section (or 'cell') in 2002, but not all cells will be filled with dredged material until at least 2013. As a major objective of the restoration, six species of waterbirds were identified as 'priority species' for Chesapeake Bay: American black duck (Anas rubripes), snowy egret (Egretta thula), cattle egret (Bubulcus ibis), osprey (Pandion haliaetus), common tern (Sterna hirundo), and least tern (S. antillarum). Monitoring of nesting activities of these species from 2002 to 2005 indicated that all species except black ducks colonized the site rapidly. More than 800 pairs of common terns nested in 2003 to 2004. Because of predation by red fox (Vulpes vulpes) and great horned owl (Bubo virginianus), reproductive success was very low for the terns. Trapping was effective in removing the foxes, and other controls have been applied to opportunistic nesting species including herring gulls (Larus argentatus) and Canada geese (Branta canadensis). An effective public education program on the island has helped address concerns about animal control.

  16. Landscape assessment of side channel plugs and associated cumulative side channel attrition across a large river floodplain

    USGS Publications Warehouse

    Reinhold, Ann Marie; Poole, Geoffrey C.; Bramblett, Robert G.; Zale, Alexander V.; Roberts, David W.

    2018-01-01

    Determining the influences of anthropogenic perturbations on side channel dynamics in large rivers is important from both assessment and monitoring perspectives because side channels provide critical habitat to numerous aquatic species. Side channel extents are decreasing in large rivers worldwide. Although riprap and other linear structures have been shown to reduce side channel extents in large rivers, we hypothesized that small “anthropogenic plugs” (flow obstructions such as dikes or berms) across side channels modify whole-river geomorphology via accelerating side channel senescence. To test this hypothesis, we conducted a geospatial assessment, comparing digitized side channel areas from aerial photographs taken during the 1950s and 2001 along 512 km of the Yellowstone River floodplain. We identified longitudinal patterns of side channel recruitment (created/enlarged side channels) and side channel attrition (destroyed/senesced side channels) across n = 17 river sections within which channels were actively migrating. We related areal measures of recruitment and attrition to the density of anthropogenic side channel plugs across river sections. Consistent with our hypothesis, a positive spatial relationship existed between the density of anthropogenic plugs and side channel attrition, but no relationship existed between plug density and side channel recruitment. Our work highlights important linkages among side channel plugs and the persistence and restoration of side channels across floodplain landscapes. Specifically, management of small plugs represents a low-cost, high-benefit restoration opportunity to facilitate scouring flows in side channels to enable the persistence of these habitats over time.

  17. Analysis of environmental variation in a Great Plains reservoir using principal components analysis and geographic information systems

    USGS Publications Warehouse

    Long, J.M.; Fisher, W.L.

    2006-01-01

    We present a method for spatial interpretation of environmental variation in a reservoir that integrates principal components analysis (PCA) of environmental data with geographic information systems (GIS). To illustrate our method, we used data from a Great Plains reservoir (Skiatook Lake, Oklahoma) with longitudinal variation in physicochemical conditions. We measured 18 physicochemical features, mapped them using GIS, and then calculated and interpreted four principal components. Principal component 1 (PC1) was readily interpreted as longitudinal variation in water chemistry, but the other principal components (PC2-4) were difficult to interpret. Site scores for PC1-4 were calculated in GIS by summing weighted overlays of the 18 measured environmental variables, with the factor loadings from the PCA as the weights. PC1-4 were then ordered into a landscape hierarchy, an emergent property of this technique, which enabled their interpretation. PC1 was interpreted as a reservoir scale change in water chemistry, PC2 was a microhabitat variable of rip-rap substrate, PC3 identified coves/embayments and PC4 consisted of shoreline microhabitats related to slope. The use of GIS improved our ability to interpret the more obscure principal components (PC2-4), which made the spatial variability of the reservoir environment more apparent. This method is applicable to a variety of aquatic systems, can be accomplished using commercially available software programs, and allows for improved interpretation of the geographic environmental variability of a system compared to using typical PCA plots. ?? Copyright by the North American Lake Management Society 2006.

  18. Fish assemblages in a western Iowa stream modified by grade control structures

    USGS Publications Warehouse

    Litvan, M.E.; Pierce, C.L.; Stewart, T.W.; Larson, C.J.

    2008-01-01

    Over 400 riprap grade control structures (GCSs) have been built in streams of western Iowa to reduce erosion and protect bridges, roads, and farmland. In conjunction with a companion study evaluating fish passage over GCSs in Turkey Creek, we evaluated the differences in fish assemblage and habitat characteristics in reaches immediately downstream from GCSs (GCS sites) and reaches at least 1 km from any GCS (non-GCS sites). The GCS sites were characterized by greater proportions of pool habitat, maximum depths, fish biomass, and abundance of juvenile largemouth bass Micropterus salmoides than were non-GCS sites. Index of biotic integrity (IBI) scores were poor or fair (<43 on a 0-100 scale) and not significantly different between the GCS and non-GCS sites. Additionally, we investigated both the longitudinal changes in fish assemblages in this GCS-fragmented stream and the changes in fish assemblages after slope modifications of three GCSs to facilitate fish passage. Thirteen fish species were present throughout the study area, whereas another 15 species exhibited truncated distributions not extending to the most upstream sampling location. After modification of the GCSs, IBI scores increased at seven of nine sites (mean increase =4.6 points). Also, channel catfish Ictalurus punctatus were detected 7.3 km upstream at sites where, 2 years before GCS modification, they had been absent from collections. Given the number and distribution of GCSs in western Iowa streams, understanding the effects of these structures is vital to the conservation and management of fish assemblages in this and other regions where GCSs or similar structures are used. ?? Copyright by the American Fisheries Society 2008.

  19. Streambed stresses and flow around bridge piers

    USGS Publications Warehouse

    Parola, A.C.; Ruhl, K.J.; Hagerty, D.J.; Brown, B.M.; Ford, D.L.; Korves, A.A.

    1996-01-01

    Scour of streambed material around bridge foundations by floodwaters is the leading cause of catastrophic bridge failure in the United States. The potential for scour and the stability of riprap used to protect the streambed from scour during extreme flood events must be known to evaluate the likelihood of bridge failure. A parameter used in estimating the potential for scour and removal of riprap protection is the time-averaged shear stress on the streambed often referred to as boundary stress. Bridge components, such as bridge piers and abutments, obstruct flow and induce strong vortex systems that create streambed or boundary stresses significantly higher than those in unobstructed flow. These locally high stresses can erode the streambed around pier and abutment foundations to the extent that the foundation is undermined, resulting in settlement or collapse of bridge spans. The purpose of this study was to estimate streambed stresses at a bridge pier under full-scale flow conditions and to compare these stresses with those obtained previously in small-scale model studies. Two-dimensional velocity data were collected for three flow conditions around a bridge pier at the Kentucky State Highway 417 bridge over the Green River at Greensburg in Green County, Ky. Velocity vector plots and the horizontal component of streambed stress contour plots were developed from the velocity data. The streambed stress contours were developed using both a near-bed velocity and velocity gradient method. Maximum near-bed velocities measured at the pier for the three flow conditions were 1.5, 1.6, and 2.0 times the average near-bed velocities measured in the upstream approach flow. Maximum streambed stresses for the three flow conditions were determined to be 10, 15, and 36 times the streambed stresses of the upstream approach flow. Both the near-bed velocity measurements and approximate maximum streambed stresses at the full-scale pier were consistent with those observed in experiments using small-scale models in which similar data were collected, except for a single observation of the near-bed velocity data and the corresponding streambed stress determination. The location of the maximum streambed stress was immediately downstream of a 90 degree radial of the upstream cylinder (with the center of the upstream cylinder being the origin) for the three flow conditions. This location was close to the flow wake separation point at the upstream cylinder. Other researchers have observed the maximum streambed stress around circular cylinders at this location or at a location immediately upstream of the wake separation point. Although the magnitudes of the estimated streambed stresses measured at the full-scale pier were consistent with those measured in small-scale model studies, the stress distributions were significantly different than those measured in small-scale models. The most significant discrepancies between stress contours developed in this study and those developed in the small-scale studies for flow around cylindrical piers on a flat streambed were associated with the shape of the stress contours. The extent of the high stress region of the streambed around the full-scale pier was substantially larger than the diameter of the upstream cylinder, while small-scale models had small regions compared to the diameter of the model cylinders. In addition, considerable asymmetry in the stress contours was observed. The large region of high stress and asymmetry was attributed to several factors including (1) the geometry of the full-scale pier, (2) the non-planar topography of the streambed, (3) the 20 degree skew of the pier to the approaching flow, and (4) the non-uniformity of the approach flow. The extent of effect of the pier on streambed stresses was found to be larger for the full-scale site than for model studies. The results from the model studies indicated that the streambed stresses created by the obstruction of flow by the 3-foot wide pi

  20. Habitat use and population characteristics of potentially spawning shovelnose sturgeon Scaphirhynchus platorynchus (Rafinesque, 1820), blue sucker ( Cycleptus elongatus (Lesueur, 1817), and associated species in the lower Wisconsin River, USA

    DOE Office of Scientific and Technical Information (OSTI.GOV)

    Lyons, John D.; Walchak, D.; Haglund, J.

    The goal of this study was to compare the possible locations, timing, and characteristics of potentially spawning shovelnose sturgeon ( Scaphirhynchus platorynchus), blue sucker ( Cycleptus elongatus), and associated species during the spring of 2007-2015 in the 149-km-long lower Wisconsin River, Wisconsin, USA, a large, shallow, sand-dominated Mississippi River tributary. A 5-km index station of two pairs of rocky shoals surrounded by sandy areas was electrofished for shovelnose sturgeon and blue sucker in a standardized fashion a total of 40 times from late March through mid- June, the presumed spawning period. On one date in 2008 and two dates inmore » 2012, all rocky shoals and adjacent sandy areas in the lowermost 149 km of the river were also electrofished for both species. Shovelnose sturgeon and blue sucker appeared to spawn in the limited rocky areas of the river along with at least four other species: mooneye ( Hiodon tergisus), quillback ( Carpiodes cyprinus), smallmouth buffalo ( Ictiobus bubalus), and shorthead redhorse ( Moxostoma macrolepidotum), usually at depths of 0.8-2.0 m and surface velocities of 0.4–1.0 m/s. However, apparently spawning shovelnose sturgeon were found only on mid-channel cobble and coarse gravel shoals within a single 7-km segment that included the 5-km index station, whereas apparently spawning blue suckers were encountered on these same shoals but also more widely throughout the river on eroding bluff shorelines of bedrock and boulder and on artificial boulder wing dams and shoreline rip-rap. Both species showed evidence of homing to the same mid-channel shoal complexes across years.« less

  1. Habitat use and population characteristics of potentially spawning shovelnose sturgeon Scaphirhynchus platorynchus (Rafinesque, 1820), blue sucker ( Cycleptus elongatus (Lesueur, 1817), and associated species in the lower Wisconsin River, USA

    DOE PAGES

    Lyons, John D.; Walchak, D.; Haglund, J.; ...

    2016-11-07

    The goal of this study was to compare the possible locations, timing, and characteristics of potentially spawning shovelnose sturgeon ( Scaphirhynchus platorynchus), blue sucker ( Cycleptus elongatus), and associated species during the spring of 2007-2015 in the 149-km-long lower Wisconsin River, Wisconsin, USA, a large, shallow, sand-dominated Mississippi River tributary. A 5-km index station of two pairs of rocky shoals surrounded by sandy areas was electrofished for shovelnose sturgeon and blue sucker in a standardized fashion a total of 40 times from late March through mid- June, the presumed spawning period. On one date in 2008 and two dates inmore » 2012, all rocky shoals and adjacent sandy areas in the lowermost 149 km of the river were also electrofished for both species. Shovelnose sturgeon and blue sucker appeared to spawn in the limited rocky areas of the river along with at least four other species: mooneye ( Hiodon tergisus), quillback ( Carpiodes cyprinus), smallmouth buffalo ( Ictiobus bubalus), and shorthead redhorse ( Moxostoma macrolepidotum), usually at depths of 0.8-2.0 m and surface velocities of 0.4–1.0 m/s. However, apparently spawning shovelnose sturgeon were found only on mid-channel cobble and coarse gravel shoals within a single 7-km segment that included the 5-km index station, whereas apparently spawning blue suckers were encountered on these same shoals but also more widely throughout the river on eroding bluff shorelines of bedrock and boulder and on artificial boulder wing dams and shoreline rip-rap. Both species showed evidence of homing to the same mid-channel shoal complexes across years.« less

  2. Fish passage in a western Iowa stream modified by grade control structures

    USGS Publications Warehouse

    Litvan, M.E.; Pierce, C.L.; Stewart, T.W.; Larson, C.J.

    2008-01-01

    Grade control structures (GCSs) are commonly used in streams of western Iowa to control bank erosion and channel headcutting but may be barriers to fish passage. From May 2002 to May 2006, we used mark-recapture methods to evaluate fish passage over a total of five GCSs, ranging in slope (run : rise) from 13:1 to 18:1 in Turkey Creek, Cass County, Iowa. Three structures, over which limited fish movement was documented from 2002 to 2004, were modified in the winter of 2004-2005 to facilitate fish passage. Before modification, the majority of recaptured fish were recaptured at the station where they were originally marked; only 1% displayed movement between sites and either upstream or downstream over a GCS. After modification fish passage improved, 14% of recaptured fish displayed movement either upstream or downstream over a GCS. Individuals of four target species - channel catfish Ictalurus punctatus, yellow bullhead Ameiurus natalis, black bullhead A. melas, and creek chub Semotilus atromaculatus - passed over at least one modified structure. The majority of documented movements over GCSs were in the upstream direction and occurred in late spring and early summer, when streamflow was relatively high. Although we documented low numbers of fish passing both upstream and downstream over GCSs, these structures are probably barriers to fish movement during periods of low flow and when there is a structural failure, such as in-channel movement of riprap. Grade control structures are pervasive in western Iowa streams; nearly every low-order stream contains at least one instream structure. To sustain fish populations, management efforts should focus on constructing or modifying GCSs to allow fish passage. ?? Copyright by the American Fisheries Society 2008.

  3. Longitudinal patterns in flathead catfish relative abundance and length at age within a large river: Effects of an urban gradient

    USGS Publications Warehouse

    Paukert, C.P.; Makinster, A.S.

    2009-01-01

    We investigated the spatial variation of flathead catfish (Pylodictis olivaris) relative abundance and growth in the 274 km long Kansas River to determine if population dynamics of catfish are related to urbanization. Electrofishing was conducted at 462 random sites throughout the river in summer, 2005-2006 to collect fish. Relative abundance of age 1 fish (???200mm), subadult (>200-400mm) and adult fish (>400 mm) ranged from 0.34 to 14.67 fish h-1, mean length at age 1 was 165 (range: 128-195) mm total length (TL) and mean length at age 3 was 376 mm TL (range: 293-419mm TL). The proportion of land use within 200 m of the river edge was between 0 and 0.54 urban. River reaches with high relative abundance of age 1 flathead catfish had high relative abundance of subadult and adult catfish. River reaches with fast flathead catfish growth to age 1 had fast growth to age 3. High urban land use and riprap in the riparian area were evident in river reaches near the heavily populated Kansas City and Topeka, Kansas, USA. Reaches with increased number of log jams and islands had decreased riparian agriculture. Areas of low urbanization had faster flathead catfish growth (r = 0.67, p = 0.005). Relative abundance of flathead catfish was higher in more agricultural areas (r = -0.57, p = 0.02). Changes in land use in riverine environments may alter population dynamics of a fish species within a river. Spatial differences in population dynamics need to be considered when evaluating riverine fish populations. Published in 2008 by John Wiley & Sons Ltd.

  4. Optimal Site Characterization and Selection Criteria for Oyster Restoration using Multicolinear Factorial Water Quality Approach

    NASA Astrophysics Data System (ADS)

    Yoon, J.

    2015-12-01

    Elevated levels of nutrient loadings have enriched the Chesapeake Bay estuaries and coastal waters via point and nonpoint sources and the atmosphere. Restoring oyster beds is considered a Best Management Practice (BMP) to improve the water quality as well as provide physical aquatic habitat and a healthier estuarine system. Efforts include declaring sanctuaries for brood-stocks, supplementing hard substrate on the bottom and aiding natural populations with the addition of hatchery-reared and disease-resistant stocks. An economic assessment suggests that restoring the ecological functions will improve water quality, stabilize shorelines, and establish a habitat for breeding grounds that outweighs the value of harvestable oyster production. Parametric factorial models were developed to investigate multicolinearities among in situ water quality and oyster restoration activities to evaluate posterior success rates upon multiple substrates, and physical, chemical, hydrological and biological site characteristics to systematically identify significant factors. Findings were then further utilized to identify the optimal sites for successful oyster restoration augmentable with Total Maximum Daily Loads (TMDLs) and BMPs. Factorial models evaluate the relationship among the dependent variable, oyster biomass, and treatments of temperature, salinity, total suspended solids, E. coli/Enterococci counts, depth, dissolved oxygen, chlorophyll a, nitrogen and phosphorus, and blocks consist of alternative substrates (oyster shells versus riprap, granite, cement, cinder blocks, limestone marl or combinations). Factorial model results were then compared to identify which combination of variables produces the highest posterior biomass of oysters. Developed Factorial model can facilitate maximizing the likelihood of successful oyster reef restoration in an effort to establish a healthier ecosystem and to improve overall estuarine water quality in the Chesapeake Bay estuaries.

  5. Geomorphic and hydrologic assessment of erosion hazards at the Norman municipal landfill, Canadian River floodplain, central Oklahoma

    USGS Publications Warehouse

    Curtis, Jennifer A.; Whitney, John W.

    2003-01-01

    The Norman, Oklahoma, municipal landfill closed in 1985 after 63 years of operation, because it was identified as a point source of hazardous leachate composed of organic and inorganic compounds. The landfill is located on the floodplain of the Canadian River, a sand-bed river characterized by erodible channel boundaries and by large variation in mean monthly discharges. In 1986, floodwaters eroded riprap protection at the southern end of the landfill and penetrated the landfill's clay cap, thereby exposing the landfill contents. The impact of this moderate-magnitude flood event (Q12) was the catalyst to investigate erosion hazards at the Norman landfill. This geomorphic investigation analyzed floodplain geomorphology and historical channel changes, flood-frequency distributions, an erosion threshold, the geomorphic effectiveness of discharge events, and other factors that influence erosion hazards at the landfill site. The erosion hazard at the Norman landfill is a function of the location of the landfill with respect to the channel thalweg, erosional resistance of the channel margins, magnitude and duration of discrete discharge events, channel form and hydraulic geometry, and cumulative effects related to a series of discharge events. Based on current climatic conditions and historical channel changes, a minimum erosion threshold is set at bankfull discharge (Q = 572 m3/s). The annual probability of exceeding this threshold is 0.53. In addition, this analysis indicates that peak stream power is less informative than total energy expenditures when estimating the erosion potential or geomorphic effectiveness of discrete discharge events. On the Canadian River, long-duration, moderate-magnitude floods can have larger total energy expenditures than shorter-duration, high-magnitude floods and therefore represent the most serious erosion hazard to floodplain structures.

  6. Ground based interferometric radar initial look at Longview, Blue Springs, Tuttle Creek, and Milford Dams

    NASA Astrophysics Data System (ADS)

    Deng, Huazeng

    Measuring millimeter and smaller deformation has been demonstrated in the literature using RADAR. To address in part the limitations in current commercial satellite-based SAR datasets, a University of Missouri (MU) team worked with GAMMA Remote Sensing to develop a specialized (dual-frequency, polarimetric, and interferometric) ground-based real-aperture RADAR (GBIR) instrument. The GBIR device is portable with its tripod system and control electronics. It can be deployed to obtain data with high spatial resolution (i.e. on the order of 1 meter) and high temporal resolution (i.e. on the order 1 minute). The high temporal resolution is well suited for measurements of rapid deformation. From the same geodetic position, the GBIR may collect dual frequency data set using C-band and Ku-band. The overall goal of this project is to measure the deformation from various scenarios by applying the GBIR system. Initial efforts have been focusing on testing the system performance on different types of targets. This thesis details a number of my efforts on experimental and processing activities at the start of the MU GBIR imaging project. For improved close range capability, a wideband dual polarized antenna option was produced and tested. For GBIR calibration, several trihedral corner reflectors were designed and fabricated. In addition to experimental activities and site selection, I participated in advanced data processing activities. I processed GBIR data in several ways including single-look-complex (SLC) image generation, imagery registration, and interferometric processing. A number of initial-processed GBIR image products are presented from four dams: Longview, Blue Springs, Tuttle Creek, and Milford. Excellent imaging performance of the MU GBIR has been observed for various target types such as riprap, concrete, soil, rock, metal, and vegetation. Strong coherence of the test scene has been observed in the initial interferograms.

  7. Modelling the Impacts of Changing Land Cover/Land Use and Climate on Flooding in the Elk River Watershed, British Columbia

    NASA Astrophysics Data System (ADS)

    Barnes, C. C.; Byrne, J. M.; Hopkinson, C.; MacDonald, R. J.; Johnson, D. L.

    2015-12-01

    The Elk River is a mountain watershed located along the eastern border of British Columbia, Canada. The Elk River is confined by railway bridges, roads, and urban areas. Flooding has been a concern in the valley for more than a century. The most recent major flood event occurred in 2013 affecting several communities. River modifications such as riprapped dykes, channelization, and dredging have occurred in an attempt to reduce inundation, with limited success. Significant changes in land cover/land use (LCLU) such as natural state to urban, forestry practices, and mining from underground to mountaintop/valley fill have changed terrain and ground surfaces thereby altering water infiltration and runoff processes in the watershed. Future climate change in this region is expected to alter air temperature and precipitation as well as produce an earlier seasonal spring freshet potentially impacting future flood events. The objective of this research is to model historical and future hydrological conditions to identify flood frequency and risk under a range of climate and LCLU change scenarios in the Elk River watershed. Historic remote sensing data, forest management plans, and mining industry production/post-mining reclamation plans will be used to create a predictive past and future LCLU time series. A range of future air temperature and precipitation scenarios will be developed based on accepted Global Climate Modelling (GCM) research to examine how the hydrometeorological conditions may be altered under a range of future climate scenarios. The GENESYS (GENerate Earth SYstems Science input) hydrometeorological model will be used to simulate climate and LCLU to assess historic and potential future flood frequency and magnitude. Results will be used to create innovative flood mitigation, adaptation, and management strategies for the Elk River with the intent of being wildlife friendly and non-destructive to ecosystems and habitats for native species.

  8. Mitigation and enhancement techniques for the Upper Mississippi River system and other large river systems

    USGS Publications Warehouse

    Schnick, Rosalie A.; Morton, John M.; Mochalski, Jeffrey C.; Beall, Jonathan T.

    1982-01-01

    Extensive information is provided on techniques that can reduce or eliminate the negative impact of man's activities (particularly those related to navigation) on large river systems, with special reference to the Upper Mississippi River. These techniques should help resource managers who are concerned with such river systems to establish sound environmental programs. Discussion of each technique or group of techniques include (1) situation to be mitigated or enhanced; (2) description of technique; (3) impacts on the environment; (4) costs; and (5) evaluation for use on the Upper Mississippi River Systems. The techniques are divided into four primary categories: Bank Stabilization Techniques, Dredging and Disposal of Dredged Material, Fishery Management Techniques, and Wildlife Management Techniques. Because techniques have been grouped by function, rather than by structure, some structures are discussed in several contexts. For example, gabions are discussed for use in revetments, river training structures, and breakwaters. The measures covered under Bank Stabilization Techniques include the use of riprap revetments, other revetments, bulkheads, river training structures, breakwater structures, chemical soil stabilizers, erosion-control mattings, and filter fabrics; the planting of vegetation; the creation of islands; the creation of berms or enrichment of beaches; and the control of water level and boat traffic. The discussions of Dredging and the Disposal of Dredged Material consider dredges, dredging methods, and disposal of dredged material. The following subjects are considered under Fishery Management Techniques: fish attractors; spawning structures; nursery ponds, coves, and marshes; fish screens and barriers; fish passage; water control structures; management of water levels and flows; wing dam modification; side channel modification; aeration techniques; control of nuisance aquatic plants; and manipulated of fish populations. Wildlife Management Techniques include treatments of artificial nest structures, island creation or development, marsh creation or development, greentree reservoirs and mast management, vegetation control, water level control, and revegetation.

  9. Application of two- and three-dimensional computational fluid dynamics models to complex ecological stream flows

    NASA Astrophysics Data System (ADS)

    Shen, Yi; Diplas, Panayiotis

    2008-01-01

    SummaryComplex flow patterns generated by irregular channel topography, such as boulders, submerged large woody debris, riprap and spur dikes, provide unique habitat for many aquatic organisms. Numerical modeling of the flow structures surrounding these obstructions is challenging, yet it represents an important tool for aquatic habitat assessment. In this study, the ability of two- (2-D) and three-dimensional (3-D) computational fluid dynamics models to reproduce these localized complex flow features is examined. The 3-D model is validated with laboratory data obtained from the literature for the case of a flow around a hemisphere under emergent and submerged conditions. The performance of the 2-D and 3-D models is then evaluated by comparing the numerical results with field measurements of flow around several boulders located at a reach of the Smith River, a regulated mountainous stream, obtained at base and peak flows. Close agreement between measured values and the velocity profiles predicted by the two models is obtained outside the wakes behind the hemisphere and boulders. However, the results suggest that in the vicinity of these obstructions the 3-D model is better suited for reproducing the circulation flow behavior at both low and high discharges. Application of the 2-D and 3-D models to meso-scale stream flows of ecological significance is furthermore demonstrated by using a recently developed spatial hydraulic metric to quantify flow complexity surrounding a number of brown trout spawning sites. It is concluded that the 3-D model can provide a much more accurate description of the heterogeneous velocity patterns favored by many aquatic species over a broad range of flows, especially under deep flow conditions when the various obstructions are submerged. Issues pertaining to selection of appropriate models for a variety of flow regimes and potential implication of the 3-D model on the development of better habitat suitability criteria are discussed. The research suggests ways of improving the modeling practices for ecosystem management studies.

  10. Bigger Is Better: Characteristics of Round Gobies Forming an Invasion Front in the Danube River

    PubMed Central

    Brandner, Joerg; Cerwenka, Alexander F.; Schliewen, Ulrich K.; Geist, Juergen

    2013-01-01

    Few studies have systematically investigated differences in performance, morphology and parasitic load of invaders at different stages of an invasion. This study analyzed phenotype-environment correlations in a fish invasion from initial absence until establishment in the headwater reach of the second largest European river, the Danube. Here, the round goby (Neogobius melanostomus) formed 73% of the fish abundance and 58% of the fish biomass in rip-rap bank habitats after establishment. The time from invasion until establishment was only about two years, indicating rapid expansion. Founder populations from the invasion front were different from longer established round goby populations in demography, morphology, feeding behaviour, sex ratio and parasitic load, indicating that plasticity in these traits determines invasion success. Competitive ability was mostly dependent on growth/size-related traits rather than on fecundity. As revealed by stable isotope analyses, specimens at the invasion front had a higher trophic position in the food web and seem to benefit from lower food competition. Somatic performance seems to be more important than investment in reproduction during the early stages of the invasion process and upstream-directed range expansion is not caused by out-migrating weak or juvenile individuals that were forced to leave high density areas due to high competition. This mechanism might be true for downstream introductions via drift. Greater abundance and densities of acanthocephalan endoparasites were observed at the invasion front, which contradicts the expectation that invasion success is determined by lower parasitic pressure in newly invaded areas. Overall, the pronounced changes in fish and invertebrate communities with a dominance of alien species suggest invasional meltdown and a shift of the upper Danube River towards a novel ecosystem with species that have greater resistance to goby predation. This seems to contribute to overcoming biological resistance and improve rapidity of dispersal. PMID:24039854

  11. Level II scour analysis for Bridge 12 (BRAITH00230012) on Town Highway 23, crossing Ayers Brook, Braintree, Vermont

    USGS Publications Warehouse

    Olson, Scott A.

    1996-01-01

    D and E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 4.2 to 9.4 ft. The worst-case contraction scour occurred at the incipient-overtopping discharge which was less than the 100-year discharge. Abutment scour ranged from 4.3 to 17.5 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1993, p. 48). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  12. Challenges of river basin management: Current status of, and prospects for, the River Danube from a river engineering perspective.

    PubMed

    Habersack, Helmut; Hein, Thomas; Stanica, Adrian; Liska, Igor; Mair, Raimund; Jäger, Elisabeth; Hauer, Christoph; Bradley, Chris

    2016-02-01

    In the Danube River Basin multiple pressures affect the river system as a consequence of river engineering works, altering both the river hydrodynamics and morphodynamics. The main objective of this paper is to identify the effects of hydropower development, flood protection and engineering works for navigation on the Danube and to examine specific impacts of these developments on sediment transport and river morphology. Whereas impoundments are characterised by deposition and an excess of sediment with remobilisation of fine sediments during severe floods, the remaining five free flowing sections of the Danube are experiencing river bed erosion of the order of several centimetres per year. Besides the effect of interruption of the sediment continuum, river bed degradation is caused by an increase in the sediment transport capacity following an increase in slope, a reduction of river bed width due to canalisation, prohibition of bank erosion by riprap or regressive erosion following base level lowering by flood protection measures and sediment dredging. As a consequence, the groundwater table is lowered, side-arms are disconnected, instream structures are lost and habitat quality deteriorates affecting the ecological status of valuable floodplains. The lack of sediments, together with cutting off meanders, leads also to erosion of the bed of main arms in the Danube Delta and coastal erosion. This paper details the causes and effects of river engineering measures and hydromorphological changes for the Danube. It highlights the importance of adopting a basin-wide holistic approach to river management and demonstrates that past management in the basin has been characterised by a lack of integration. To-date insufficient attention has been paid to the wide-ranging impacts of river engineering works throughout the basin: from the basin headwaters to the Danube Delta, on the Black Sea coast. This highlights the importance of new initiatives that seek to advance knowledge exchange and knowledge transfer within the basin to reach the goal of integrated basin management. Copyright © 2015 Elsevier B.V. All rights reserved.

  13. Level II scour analysis for Bridge 49 (BENNCYHUNT0049) on Hunt Street, crossing the Walloomsac River, Bennington, Vermont

    USGS Publications Warehouse

    Olson, Scott A.; Medalie, Laura

    1997-01-01

    2 stone fill also protects the channel banks upstream and downstream of the bridge for a minimum distance of 17 feet from the respective bridge faces. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour computed for all modelled flows ranged from 0.9 to 5.0 ft. The worst-case contraction scour occurred at the 500-year discharge. Computed left abutment scour ranged from 15.3 to 16.5 ft. with the worst-case scour occurring at the incipient roadway-overtopping discharge. Computed right abutment scour ranged from 6.0 to 8.7 ft. with the worst-case scour occurring at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  14. Marine Tech in the Bayou City: An Experiential Education Experience

    NASA Astrophysics Data System (ADS)

    Barnard, A.; Mackay, E.; Zarate, A.; Coutts, A.; Craig, A.; Roman, R.; Max, M. D.; Detiveaux, G.; Dement, G.; Trufan, E.; Sager, W.; Wellner, J.; Stewart, R. R.; Mayer, L. A.; Coffin, R. B.; Vielstädte, L.; Skarke, A. D.; VanSumeren, H.; Cardenas, I.; Mir, R.

    2017-12-01

    Training and expertise in underwater exploration with advanced marine technology is a must for today's STEM graduates. Much of this training can be initiated in relatively inexpensive ways using local expertise and technologies. Instead of going to sea, we have previously demonstrated marine survey techniques by exploring the shallow waters of Houston's bayous. This setting has served to encourage participant's intrinsic motivation. In this study attendees were given the opportunity to fly/pilot a remotely operated vehicle (ROV), an autonomous surface vehicle (ASV), and participate in relevant lectures and data analysis. To achieve a quantitative evaluation of the training, participants provided responses to a list of focused questions before and after the survey exercises. Initially, a multibeam survey (200 m x 50 m) was conducted by Survey Equipment Services, Inc. using an Teledyne Oceanscience Z-Boat ASV with an Integrated 200 - 460 kHz Odom MB2 Multibeam System. Using the multibeam survey data research students identified acoustic targets on the bayou floor for further investigation. Target identification was achieved using a Predator II (Seatronics, Inc., an Acteon company) ROV mounted with a Teledyne BlueView Technologies M900-130 900 kHz, and 1.4 - 3 MHz Sound Metrics ARIS Explorer 3000 imaging sonars. Multibeam data delineated a 90 m long, 45 m wide, and 8 m deep hollow, interpreted as a confluence scour created at the junction of the Buffalo and White Oak Bayous. A raised bank downstream of the hollow within the main channel is attributed to rapid sedimentation in a region of post confluence flow deceleration. Targets in the imaging sonar were identified as boulder-sized transported riprap, fluvial sediment, and sand waves. Review of participant's survey results using a Wilcoxon signed rank test indicated statistically significant results across all 30 survey questions. Positive improvements were reported across the board in questions related to three focus areas; awareness, experience, and interest in/of marine geoscience activities. These encouraging results confirm the feasibility of local high-resolution studies as training activities, as well as feeding local and national graduate field programs, and producing data that could be useful to city and state engineers for bayou design.

  15. Geomorphic Effects of Gravel Augmentation and Bank Re-erosion on the Old Rhine River Downstream From The Kembs Dam (France, Germany)

    NASA Astrophysics Data System (ADS)

    Chardon, V.; Laurent, S.; Piegay, H.; Arnaud, F.; Houssier, J.; Serouilou, J.; Clutier, A.

    2017-12-01

    The Old Rhine is a 50 km by-passed reach downstream from the Kembs diversion dam in the Alsacian plain (France/Germany). It has been impacted by engineering works since the 19th century. This reach exhibits poor ecological functionalities due to severe geomorphological alterations (e.g., channel bed stabilization, narrowing, degradation and armoring, sediment deficit). In the frame of the Kembs power plant relicensing (2010), Électricité de France has undertaken two gravel augmentations (18 000 and 30 000 m3) and three controlled bank erosions following riprap protection removal over 300 m bank length to enhance bedload transport and habitat diversification. A first pilot gravel augmentation was also implemented in 2010 (23 000 m3). A geomorphological monitoring based on bedload tracking, grain size analyses and topo-bathymetric surveys has been performed on the three gravel augmentation reaches and one of the controlled bank erosion sites to assess the efficiency and sustainability of these actions (2010-2017). Results show that augmented gravels are entrained for a Q2 flood. Gravels moved several hundred meters for moderate floods and up to one kilometer for more intense floods (Q15), while sediment deposition mainly diffused within the channel. Morphological and grain size diversification, including sediment refinement, are still relatively limited following gravel augmentation. Furthermore, sediment armoring reestablished once the sediment wave moved more downstream, after only four to six years, due to the stability and the narrowness of the channel but also by the absence of upstream bedload supply. Habitat diversification was higher on the controlled bank erosion site thanks to the presence of two artificial groynes, even though eroded sediment volumes were lower than expected (less than 1500m3 for a Q15 flood). This monitoring demonstrates gravel augmentations are not sufficient to really diversify geomorphological conditions of the Old Rhine. Channel enlargements by controlled bank erosion and other actions should be carried out downstream from gravel augmentations to create channel geometry conditions promoting bar development and habitat diversification.

  16. Characterizing Physical Habitat of a Mixed-Land Use Stream of the Central U.S.

    NASA Astrophysics Data System (ADS)

    Hooper, L. W.; Hubbart, J. A.; Hosmer, G. W.; Hogan, M. L.

    2014-12-01

    Land use altered flow regime impacts on aquatic biological habitat can be quantified by means of a physical habitat assessment (PHA). PHA metrics include (but are not limited to) channel substrate, width and wetted width, bank slope, and bank height. Hinkson Creek, located in Boone County, Missouri, was placed on the Missouri Department of Natural Resources list of impaired waters (Section 303d) of the Clean Water Act in 1998. A physical habitat assessment of Hinkson Creek in 2014 provides quantitative data characterizing the current potential of Hinkson Creek to fully support aquatic life, specifically macroinvertebrates (a goal for delisting). The PHA was conducted every 100m of Hinkson Creek (56km). Results from the lower 87.9% (contiguous) of the drainage indicate channel width ranged from a maximum of 70m to a minimum of 4.6m, with a mean width of 17m and standard deviation (SD) of 7.4m. Bankfull width ranged from a maximum of 74m to a minimum of 8.8m (mean = 26.1m, SD = 8.2). Bank height ranged from a maximum of 5.8m to a minimum of 0.4m (mean = 2.9m, SD = 1m). Mean bank angle for the left and right banks was nearly equivalent (left = 33.8°, right = 34.6°). Bank height and bankfull width increased with increasing drainage distance. Trench pools were the dominant channel unit at 71.4% of the sample transects, while riffles were present at 16.6%. Analysis of stream channel bed composition was conducted using a modified Wolman pebble count survey at each site and Thalweg profile between sites. Size class results were quantified as follows: 56.1% fines (16mm or less), 36.2% intermediate (16mm to 1000mm, plus vegetation and wood), 8.7% large/bedrock (greater than 1000mm, riprap and bedrock). Study results provide science-based information to better equip land planners in Hinkson Creek watershed and similar multi-use watersheds of the central United States for future management decisions and development scenarios.

  17. Level II scour analysis for Bridge 39 (LOWETH00080039) on Town Highway 8, crossing Potter Brook, Lowell, Vermont

    USGS Publications Warehouse

    Boehmler, Erick M.; Degnan, James R.

    1997-01-01

    A scour hole 2.0 feet deeper than the mean thalweg depth was observed along the left abutment during the Level I assessment. There were no scour protection measures evident at the site. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.3 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 1.8 to 5.5 feet. The worst-case abutment scour occurred at the 100-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  18. Wave basin model tests of technical-biological bank protection

    NASA Astrophysics Data System (ADS)

    Eisenmann, J.

    2012-04-01

    Sloped embankments of inland waterways are usually protected from erosion and other negative im-pacts of ship-induced hydraulic loads by technical revetments consisting of riprap. Concerning the dimensioning of such bank protection there are several design rules available, e.g. the "Principles for the Design of Bank and Bottom Protection for Inland Waterways" or the Code of Practice "Use of Standard Construction Methods for Bank and Bottom Protection on Waterways" issued by the BAW (Federal Waterways Engineering and Research Institute). Since the European Water Framework Directive has been put into action special emphasis was put on natural banks. Therefore the application of technical-biological bank protection is favoured. Currently design principles for technical-biological bank protection on inland waterways are missing. The existing experiences mainly refer to flowing waters with no or low ship-induced hydraulic loads on the banks. Since 2004 the Federal Waterways Engineering and Research Institute has been tracking the re-search and development project "Alternative Technical-Biological Bank Protection on Inland Water-ways" in company with the Federal Institute of Hydrology. The investigation to date includes the ex-amination of waterway sections where technical- biological bank protection is applied locally. For the development of design rules for technical-biological bank protection investigations shall be carried out in a next step, considering the mechanics and resilience of technical-biological bank protection with special attention to ship-induced hydraulic loads. The presentation gives a short introduction into hydraulic loads at inland waterways and their bank protection. More in detail model tests of a willow brush mattress as a technical-biological bank protec-tion in a wave basin are explained. Within the scope of these tests the brush mattresses were ex-posed to wave impacts to determine their resilience towards hydraulic loads. Since the developing pore water pressure is significant considering the slope stability under hydraulic load, particular atten-tion is paid to the interaction of willow roots and pore water pressure. Furthermore the occurring ero-sion is determined. The methods of measurements, test conditions and executions as well as first results will be presented.

  19. Level II scour analysis for Bridge 27 (ANDOTH00290027) on Town Highway 29, crossing Middle Branch Williams River, Andover, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.; Wild, Emily C.

    1997-01-01

    2 stone fill (less than 36 inches diameter) along the upstream right bank and downstream left bank and around the upstream left and right wingwalls. Type- 3 stone fill (less than 48 inches diameter) is located along the base of the left abutment in the scour hole, at the end of the downstream left wingwall and along the upstream left bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.4 to 0.9 ft. The worst-case contraction scour occurred at the incipient-overtopping discharge and the 100-year discharge. Abutment scour ranged from 10.7 to 13.6 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  20. Bank erosion of navigation canals in the western and central Gulf of Mexico

    USGS Publications Warehouse

    Thatcher, Cindy A.; Hartley, Stephen B.; Wilson, Scott A.

    2011-01-01

    Erosion of navigation canal banks is a direct cause of land loss, but there has been little quantitative analysis to determine why certain major canals exhibit faster widening rates (indicative of erosion) than others in the coastal zones of Texas, Louisiana, Mississippi, and Alabama. We hypothesize that navigation canals exhibit varying rates of erosion based on soil properties of the embankment substrate, vegetation type, geologic region (derived from digital versions of state geologic maps), and the presence or absence of canal bank armaments (that is, rock rip-rap, concrete bulkheads, or other shoreline protection structures). The first objective of this project was to map the shoreline position and substrate along both banks of the navigation canals, which were digitized from 3 different time periods of aerial photography spanning the years of 1978/79 to 2005/06. The second objective was to quantify the erosion rates of the navigation canals in the study area and to determine whether differences in erosion rates are related to embankment substrate, vegetation type, geologic region, or soil type. To measure changes in shoreline position over time, transects spaced at 50-m (164-ft) intervals were intersected with shorelines from all three time periods, and an annual rate of change was calculated for each transect. Mean annual rates of shoreline change ranged from 1.75 m/year (5.74 ft/year) on the west side of the Atchafalaya River, La., where there was shoreline advancement or canal narrowing, to -3.29 m/year (-10.79 ft/year) on the south side of the Theodore Ship Channel, Ala., where there was shoreline retreat or erosion. Statistical analysis indicated that there were significant differences in shoreline retreat rates according to geologic region and marsh vegetation type, and a weak relationship with soil organic content. This information can be used to better estimate future land loss rates associated with navigation canals and to prioritize the location of restoration and erosion mitigation efforts. Combining all canals together, our results also showed that canal erosion rates have slowed in recent years, with an average canal widening rate of -0.99 m/year (-3.25 ft/year) for the 1996/98-2005/06 time period compared to -1.71 m/year (-5.61 ft/year) for the earlier 1978/79-1996/98 time period. Future research could focus on obtaining detailed vessel traffic information for individual canals, which is likely a factor that influences canal bank erosion rates.

  1. The effect of inundation frequency on ground beetle communities in a channelized mountain stream

    NASA Astrophysics Data System (ADS)

    Skalski, T.; Kedzior, R.; Radecki-Pawlik, A.

    2012-04-01

    Under natural conditions, river channels and floodplains are shaped by flow and sediment regime and are one of the most dynamic ecosystems. At present, European river floodplains are among the most endangered landscapes due to human modifications to river systems, including channel regulation and floodplain urbanization, and land use changes in the catchments. Situated in a transition zone between terrestrial and aquatic environments, exposed riverine sediments (ERS) play a key role in the functioning of riverine ecosystems. This study aimed to verify whether the bare granular substrate is the only factor responsible for sustaining the biota associated with ERS or the inundation frequency also plays a role, modifying the potential of particular species to colonize these habitats. Ground beetles (Col. Carabidae) were selected as the investigated group of organisms and the study was carried out in Porębianka, a Polish Carpathian stream flowing through both unconstrained channel sections and sections with varied channelization schemes (rapid hydraulic structures, concrete revetments or rip-rap of various age). In each of the distinguished channel types, four replicates of 10 pitfall traps were established in three rows varying in distance to the mean water level (at three different benches). Almost 7000 individuals belonging to 102 species were collected on 60 plots. Forward selection of redundancy analysis revealed four factors significantly describing the variation in ground beetle species data: bank modification, potential bankfull discharge, frequency of inundation and plant height. Most of the biggest species were ordered at the positive site of first axis having the highest values of periods between floods. Total biomass of ground beetles and mean biomass of individuals differed significantly between sites of various frequency of inundation, whereas the variation in abundance and species richness of ground beetles was independent of the river dynamics. The body size distribution of ground beetles is significantly right skewed on more frequently flooded areas whereas on more stable localities it becomes left skewed. Our results also demonstrated that the presence of ERS does not changes the structure of ground beetle communities if the frequency of inundation of river banks is reduced. This study indicated that not only habitat parameters but also biotic interactions between competing species from a regional pool are important for the conservation of riverine communities. Vulnerable beetles characteristic of riverine habitats are small and usually weak competitors. A reduced frequency of bank inundation creates possibilities for the colonization of ERS by species from surrounding habitats and elimination of the species well adapted to the dynamic flow conditions typifying unmodified stream sections.

  2. Level II scour analysis for Bridge 45 (CHELTH00440045) on Town Highway 44, crossing first Branch White River, Chelsea, Vermont

    USGS Publications Warehouse

    Ayotte, Joseph D.; Hammond, Robert E.

    1996-01-01

    bridge consisting of one 27-foot clear-span concrete-encased steel beam deck superstructure (Vermont Agency of Transportation, written commun., August 25, 1994). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 10 degrees to the opening while the opening-skew-to-roadway is 5 degrees. Both abutment footings were reported as exposed and the left abutment was reported to be undermined by 0.5 ft at the time of the Level I assessment. The only scour protection measure at the site was type-1 stone fill (less than 12 inches diameter) along the left abutment which was reported as failed. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.4 to 5.1 ft. with the worst-case occurring at the 500-year discharge. Abutment scour ranged from 9.9 to 20.3 ft. The worst-case abutment scour also occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1993, p. 48). Many factors, including historical performance during flood events, the geomorphic assessment, scour protection measures, and the results of the hydraulic analyses, must be considered to properly assess the validity of abutment scour results. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein, based on the consideration of additional contributing factors and experienced engineering judgement.

  3. Level II scour analysis for Bridge 9 (BARRUSO3020009) on U.S. Route 302, crossing Jail Branch, Barre, Vermont

    USGS Publications Warehouse

    Olson, Scott A.; Ivanoff, Michael A.

    1997-01-01

    skew-to-roadway. There is evidence of channel scour along the right bank from 190 feet upstream of the bridge and extending through the bridge along the right abutment. Under the bridge, the scour depth is approximately 0.5 feet below the mean thalweg depth. Scour protection measures at the site include type-3 stone fill (less than 48 inches diameter) along the right bank extending from the bridge to 192 feet upstream. Type-2 stone fill (less than 36 inches diameter) is along the right abutment and the right downstream bank to 205 feet downtream of the bridge. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.2 to 0.5 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 4.3 to 7.5 ft. The worst-case abutment scour occurred at the 500-year discharge. Computed scour for the 100-year event does not go below the abutment footings. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  4. Effects of Urbanization on the Flow Regimes of Semi-Arid Southern California Streams

    NASA Astrophysics Data System (ADS)

    Hawley, R. J.; Bledsoe, B. P.; Stein, E. D.

    2010-12-01

    Stream channel erosion and associated habitat degradation are pervasive in streams draining urban areas in the southwestern US. The prevalence of these impacts results from the inherent sensitivity of streams in semi-arid climates to changes in flow and sediment regimes, and past inattention to management of geomorphically effective flows. Addressing this issue is difficult due to the lack of data linking ranges of flow (from small to large runoff events) to geomorphic channel response. Forty-three U. S. Geological Survey gages with record lengths greater than ~15 yrs and watershed areas less than ~250 square kilometers were used to empirically model the effects of urbanization on streams in southern California. The watersheds spanned a gradient of urban development and ranged from 0 to 23% total impervious area in 2001. With little flow control at the subdivision scale to date, most impervious area in the region is relatively well-connected to surface-drainage networks. Consequently, total impervious area was an effective surrogate for urbanization, and emerged as a significant (p < 0.05) predictor of instantaneous peak-flow rates at the 1.5- and 2-yr recurrence intervals, with decreasing significance and influence at higher return periods. For example, peak factors for a watershed with 20% imperviousness were ~10, 6, and 2 for the 1.5-, 2-, and 5-yr flows, respectively, with no discernable influence at flows greater than the 10-yr event. Most importantly with respect to geomorphic response, urbanization extent was a significant predictor of duration density functions, which integrate the magnitude and duration of mean daily discharges. This approach expands on previous scaling procedures to produce histogram-style cumulative flow duration graphs for ungaged sites based on urbanization extent and other watershed descriptors. Urbanization resulted in proportionally-longer durations of all geomorphically-effective flows, with a more pronounced effect on the durations of moderate flows. For example, an average watershed from the study domain with ~20% imperviousness could experience five times as many days of mean daily flows on the order of 100 cfs (3 cubic meters per second) and approximately three times as many days on the order of 1,000 cfs (30 cubic meters per second) relative to the undeveloped setting. Increased duration of sediment-transporting flows is a primary driver of accelerated changes in channel form that are often concurrent with urbanization throughout southern California, particularly in unconfined, fine-grained geomorphic settings. Consequently, urbanization seems to serve as a potential catalyst that can send previously functioning habitats onto degradational trajectories that are typically arrested via concrete/riprap trapezoidal flood conveyance channels with little ecological/geomorphic function.

  5. Level II scour analysis for Bridge 43 (CHESVT00110043) on State Highway 11, crossing the Middle Branch Williams River, Chester, Vermont

    USGS Publications Warehouse

    Striker, Lora K.; Burns, Ronda L.

    1997-01-01

    76-ft-long, two-lane bridge consisting of two 37-foot concrete Tee-beam spans (Vermont Agency of Transportation, written communication, March 29, 1995). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 35 degrees to the opening. The computed opening-skew-to-roadway was 30 degrees but the historical records indicate this angle is 25 degrees. Scour protection measures at the site consist of type-1 stone fill (less than 12 inches diameter) along the downstream banks and the upstream right wing wall. Type-2 (less than 36 inches diameter) stone fill protection is noted on the upstream and downstream left wingwalls and upstream along the left bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 1.5 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 7.2 to 10.7 ft. The worst-case abutment scour occurred at the 500-year discharge for the right abutment. Pier scour ranged from 7.3 to 8.6 ft. The worst-case pier scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  6. Using Braid Plain Ecology and Geomorphology to Inform Bank Erosion Management along a Braided River, Matanuska River, Alaska

    NASA Astrophysics Data System (ADS)

    Curran, J. H.; McTeague, M. L.

    2010-12-01

    Braided rivers are inherently dynamic but quantifying the nature and implications of this dynamism can contribute to more comprehensive understanding of these systems and management of the river corridor. Bank erosion along the glacial, braided Matanuska River in southcentral Alaska has challenged generations of officials and generated a host of proposed solutions such as riprapped banks, dikes, gravel mining, and trenching. Increasingly, assessment of the technical feasibility of these methods has been accompanied by consideration of ecological factors and nonstructural solutions. The Matanuska River is braided over 85 percent of its course and clearwater side channels in abandoned braid plain areas provide as much as 90 percent of the spawning habitat in the basin for chum and sockeye salmon (Oncorhynchus keta and O. nerka). An assessment of braid plain vegetation, bank erosion rates, effects of a large flood, and distribution of clearwater side channels establishes a scientific basis for ecological and geomorphological considerations and recently helped guide development of a management plan for the river corridor. A historical analysis of braid plain features, marginal positions, and vegetation patterns from 1949, 1962, and 2006 orthophotographs showed that the 2006 braid plain was 43 percent vegetated and had an average age of 16 years. Only about 4 percent of the braid plain contained vegetated islands and over 60 percent of these were young and sparsely vegetated, implying that a suite of active channels migrated frequently across the braid plain and that vegetation did not appreciably limit channel movement. Rates of erosion to the braid plain margins averaged 0.3 m/yr from 1949 to 2006 but erosion was localized, with 64 percent of the erosion at only 8 percent of the banks. Cumulative bank change was twice as great along banks consisting of Holocene fluvial deposits (fans and terraces) identified during Geographic Information System (GIS) mapping than on other features. River-long erosion rates were twice as great for 1949-62 than for 1962-2006, despite a flood with a less than 0.002 percent exceedance probability in 1971 and slightly higher average peak flood magnitudes in the latter period. Of the 20 areas with erosion greater than 70 m from 1949-2006, only 9 were eroded in both periods and only one had detectable erosion in the sub-period from 2004 to 2006. This disconnect of erosion with flooding and the variable timing of historical erosion suggests that erosion was sporadic and more related to the presence of the river against the bank and bank erodibility than to more readily monitored variables. Clearwater side channels were frequently reworked in the braid plain but the cumulative length of channels appeared to be stable within the historical time period. This dynamic nature implies that the aquatic ecosystems have evolved within a high disturbance regime.

  7. National Assessment of Shoreline Change: Part 1, Historical Shoreline Changes and Associated Coastal Land Loss Along the U.S. Gulf of Mexico

    USGS Publications Warehouse

    Morton, Robert A.; Miller, Tara L.; Moore, Laura J.

    2004-01-01

    EXECUTIVE SUMMARY Beach erosion is a chronic problem along most open-ocean shores of the United States. As coastal populations continue to grow and community infrastructures are threatened by erosion, there is increased demand for accurate information regarding past and present trends and rates of shoreline movement. There is also a need for a comprehensive analysis of shoreline movement that is consistent from one coastal region to another. To meet these national needs, the U.S. Geological Survey is conducting an analysis of historical shoreline changes along open-ocean sandy shores of the conterminous United States and parts of Hawaii and Alaska. One purpose of this work is to develop standard repeatable methods for mapping and analyzing shoreline movement so that periodic updates regarding coastal erosion and land loss can be made nationally that are systematic and internally consistent. This report on states bordering the Gulf of Mexico (Florida, Alabama, Mississippi, Louisiana, and Texas) represents the first in a series that will eventually include the Atlantic Coast, Pacific Coast, and parts of Hawaii and Alaska. The report summarizes the methods of analysis, interprets the results, provides explanations regarding the historical and present trends and rates of change, and describes how different coastal communities are responding to coastal erosion. Shoreline change evaluations are based on comparing three historical shorelines with a recent shoreline derived from lidar (Light Detection and Ranging) topographic surveys. The historical shorelines generally represent the following periods: 1800s, 1920s-1930s, and 1970s, whereas the lidar shoreline is 1998-2002. Long-term rates of change are calculated using all four shorelines (1800s to lidar shoreline), whereas short-term rates of change are calculated for the most recent period (1970s to lidar shoreline). The historical rates of change presented in this report represent past conditions and therefore are not intended for predicting future shoreline positions or rates of change. Rates of erosion for the Gulf of Mexico region are generally highest in Louisiana along barrier island and headland shores associated with the Mississippi delta. Erosion is also rapid along some barrier islands and headlands in Texas, and barrier islands in Mississippi are migrating laterally. Highest rates of erosion in Florida are generally localized around tidal inlets. The most stable Gulf beaches are along the west coast of Florida where low wave energy and frequent beach nourishment minimize erosion. Some beach segments in Texas have accreted as a result of net longshore drift convergence, and around tidal inlets that have been stabilized by long jetties. Seawalls and riprap revetments were constructed in all the Gulf Coast states as initial community responses to long-term beach erosion. Although some states, such as Florida, still permit shoreline stabilization structures, beach nourishment has become the preferred method of mitigating long-term erosion.

  8. Level II scour analysis for Bridge 51 (RANDTH00SC0051) on School Street, crossing Thayer Brook, Randolph, Vermont

    USGS Publications Warehouse

    Olson, Scott A.

    1996-01-01

    ft, an average channel top width of 36 ft and an average channel depth of 3 ft. The predominant channel bed materials are gravel and cobble (D50 is 58.2 mm or 0.191 ft). The geomorphic assessment at the time of the Level I site visits on August 4, 1994 and December 8, 1994, indicated that the reach was stable. The School Street crossing of Thayer Brook is a 39-ft-long, two-lane bridge consisting of one 35-foot concrete span (Vermont Agency of Transportation, written commun., August 2, 1994). The bridge is supported by vertical, concrete abutments with wingwalls. Type-2 stone fill (less than 36 inches diameter) along the downstream left bank was the only existing protection. The approach channel is skewed approximately 45 degrees to the bridge face; the opening-skew-to-roadway is also 45 degrees. Additional details describing conditions at the site are included in the Level II Summary, Appendix D, and Appendix E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 1.0 to 2.2 ft. with the worst-case scenario occurring at the 500-year discharge. Abutment scour ranged from 6.2 to 12.0 ft. The worst-case abutment scour also occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1993, p. 48). Many factors, including historical performance during flood events, the geomorphic assessment, scour protection measures, and the results of the hydraulic analyses, must be considered to properly assess the validity of abutment scour results. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein, based on the consideration of additional contributing factors and experienced engineering judgement.

  9. Prevention of Bridge Scour with Non-uniform Circular Piers Plane under Steady Flows

    NASA Astrophysics Data System (ADS)

    Chen, Hsing-Ting; Wang, Chuan-Yi

    2017-04-01

    River bed scour and deposit variation extremely severe because of most of rivers are steep and rapid flows, and river discharge extremely unstable and highly unsteady during different seasons in Taiwan. In addition to the obstruction of piers foundation, it causes local scour and threatens the safety of bridges. In the past, riprap, wire gabion or wrap pier works were adopted as the protections of piers foundation, but there were no effectual outcomes. The events of break off piers still happen sometimes. For example, typhoon Kalmaegi (2008) and Morakot (2009) caused heavy damages on Ho-Fon bridge in the Da-jia river and Shuang-Yuan bridge in the Kao-Ping river, respectively. Accordingly, to understand the piers scour system and propose an appropriate protection of piers foundation becomes an important topic for this study currently. This research improves the protection works of the existing uniform bridge pier (diameter D) to ensure the safety of the bridge. The non-uniform plane of circular piers (diameter D*) are placed on the top of a bridge pier foundation to reduce the down flow impacting energy and scour by its' surface roughness characteristics. This study utilize hydraulic models to simulate local scour depth and scour depth change with time for non-uniform pier diameter ratio D/D* of 0.3,0.4,0.5,0.6,0.7 and 0.8, and different type pier and initial bed level (Y) relative under the foundation top elevation under steady flows of V/Vc=0.95,0.80 and 0.65. The research results show that the scour depth increases with an increase of flow intensity (V/Vc) under different types of steady flow hydrographs. The scour depth decreases with increase of initial bed level (Y=+0.2D*,0D*and -0.2D*) relative under the foundation top elevation of the different type pier. The maximum scour depth occurred in the front of the pier for all conditions. Because of the scouring retardation by the non-uniform plane of foundation, the scour depth is reduced for the un-exposed bridge foundation (Y=+0.2D*) under any steady flows. Opposite results are found for the exposed (Y=-0.2D*) bridge foundation. For the condition non-uniform pier diameter ratio (D/D*=0.3 0.8) scours, when D/D* is equal to 0.4, because pier oncoming flow area is the smallest one so that down flow intensity is less; as non-uniform area is bigger and decrease more down flow energy so that bring smaller scour depth and effect area. Therefore, local scour depth for pier diameter ratio of 0.4 is less than other type of pier. Considering the safety of bridge structure, a non-uniform circular pier with D/D* which equals to 0.4 and initial bed level relative to Y=+0.2D* is the most ideal pier allocations.

  10. National Assessment Of Shoreline Change: Part 2, Historical Shoreline Changes And Associated Coastal Land Loss Along The U.S. Southeast Atlantic Coast

    USGS Publications Warehouse

    Morton, Robert A.; Miller, Tara L.

    2005-01-01

    EXECUTIVE SUMMARY Beach erosion is a chronic problem along most open-ocean shores of the United States. As coastal populations continue to grow and community infrastructures are threatened by erosion, there is increased demand for accurate information regarding past and present trends and rates of shoreline movement. There is also a need for a comprehensive analysis of shoreline movement that is consistent from one coastal region to another. To meet these national needs, the U.S. Geological Survey is conducting an analysis of historical shoreline changes along open-ocean sandy shores of the conterminous United States and parts of Hawaii and Alaska. One purpose of this work is to develop standard repeatable methods for mapping and analyzing shoreline movement so that periodic updates regarding coastal erosion and land loss can be made nationally that are systematic and internally consistent. This report on states comprising the Southeast Atlantic Coast (east Florida, Georgia, South Carolina, North Carolina) represents the second in a series that already includes the Gulf of Mexico and will eventually include the Northeast Atlantic Coast, Pacific Coast, and parts of Hawaii and Alaska. The report summarizes the methods of analysis, interprets the results, provides explanations regarding the historical and present trends and rates of change, and describes how different coastal communities are responding to coastal erosion. Shoreline change evaluations are based on comparing three historical shorelines with a recent shoreline derived from lidar (Light Detection and Ranging) topographic surveys. The historical shorelines generally represent the following periods: 1800s, 1920s-1930s, and 1970s, whereas the lidar shoreline is 1998-2002. Long-term rates of change are calculated using four shorelines (1800s to lidar shoreline), whereas short-term rates of change are calculated for the most recent period (1970s to lidar shoreline). The historical rates of change presented in this report represent past conditions and therefore are not intended for predicting future shoreline positions or rates of change. Rates of erosion for the Southeast Atlantic region were generally highest in South Carolina along barrier islands and headland shores associated with the Santee delta. Erosion was also rapid along some barrier islands in North Carolina. Highest rates of erosion in Florida were generally localized around tidal inlets. The most stable Southeast Atlantic beaches were along the east coast of Florida where low wave energy and frequent beach nourishment minimized erosion. Some beach segments in Florida accreted as a result of net longshore drift convergence around Cape Canaveral and around tidal inlets that were stabilized by jetties. Seawalls, riprap revetments, and groins were constructed in all the Southeast Atlantic states as initial community responses to long-term beach erosion. Although some states, such as Florida, still permit shoreline stabilization structures, beach nourishment has become the preferred method of mitigating long-term erosion. Beach nourishment is common in all of the Southeast Atlantic states except Georgia.

  11. Shoreline erosion at selected areas along Lake Sharpe on the Lower Brule Reservation in South Dakota, 1966–2015

    USGS Publications Warehouse

    Thompson, Ryan F.; Stamm, John F.

    2018-06-21

    The Lower Brule Reservation in central South Dakota is losing land because of shoreline erosion along Lake Sharpe, a reservoir on the Missouri River, which has caused detrimental effects for the Lower Brule Sioux Tribe including losses of cultural sites, recreation access points, wildlife habitat, irrigated cropland, and landmass. To better understand and quantify shoreline erosion, the Lower Brule Sioux Tribe and the U.S. Geological Survey cooperated on a series of data-collection efforts and study of shoreline erosion along Lake Sharpe. Data collected or compiled for 1966–2015 were used to describe and quantify shoreline erosion along Lake Sharpe. The progression of shoreline erosion near the community of Lower Brule, South Dakota, was tracked by comparing current or recent aerial imagery with existing historical maps. At 33 evaluation lines along a 7-mile reach of Lake Sharpe shoreline near Lower Brule, cumulative change of shoreline from 1966 to 2010 ranged from about −224 feet of deposition to 770 feet of erosion.Photographic and location data were collected for this study to understand the processes affecting erosion and estimate erosion rates. Photographs were collected only in the 7-mile reach near Lower Brule, but locations of the bank over time were collected at the 7-mile reach and two additional reaches within the Lower Brule Reservation. Global navigation satellite system equipment was used in real-time kinematic mode to collect bank locations along three reaches of interest. Reach-length data were collected four times between November 2011 and November 2012. A small, unmanned aerial system (drone) was used to capture digital video along the shoreline of the 7-mile reach.Water-level fluctuations contribute to the number of wet-dry cycles experienced by the soils at the shoreline or bank. The soils present under the current (2017) location of the reservoir are predominantly terrace alluvium, consisting of sand and silt. Detailed soils data for Lyman County indicate that the dominant soil type along the southern part of the shoreline in the 7-mile reach is Bullcreek clay. Weather within the study area can affect the erosion rate. Air temperature can potentially affect erosion rates by freezing and thawing water and soils. Mean hourly wind speeds vary somewhat throughout the year but averaged 13.3 miles per hour. The direction of prevailing winds near Lower Brule indicates that there are several miles of fetch to build large waves.Annual erosion rates calculated or measured throughout this study varied by location. Long-term annual average erosion rates of the 7-mile reach, as calculated by image analysis, ranged from −5.1 feet per year (deposition) to 17.5 feet per year (erosion). Short-term annual erosion rates measured using global navigation satellite system equipment during 2010–12 ranged from about 0 to 31.7 feet per year for the 7-mile reach. Existing scour countermeasures have been effective variably. Fieldstone rip-rap seems to have stabilized the shoreline, whereas tree strips paralleling the shoreline seem to have slowed erosion.

  12. Level II scour analysis for Bridge 37 (BARTTH00080037) on Town Highway 8, crossing Willoughby River, Barton, Vermont

    USGS Publications Warehouse

    Ayotte, Joseph D.; Boehmler, Erick M.

    1996-01-01

    of north-central Vermont in the town of Barton. The 60.4-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the banks have sparse to moderate woody vegetation coverage. In the study area, the Willoughby River is probably incised, has a sinuous channel with a slope of approximately 0.009 ft/ft, an average channel top width of 108 ft and an average channel depth of 6 ft. The predominant channel bed material is cobble (D50 is 95.1 mm or 0.312 ft). The geomorphic assessment at the time of the Level I and Level II site visit on October 20, 1994, indicated that the reach was stable. The town highway 8 crossing of the Willoughby River is a 96-ft-long, two-lane bridge consisting of one 94-foot steel-beam span (Vermont Agency of Transportation, written communication, August 4, 1994). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 15 degrees to the opening while the opening-skew-to-roadway is 10 degrees. No scour was reported in the channel or along abutments or wingwalls during the Level I assessment. Type-2 stone fill (less than 24 inches diameter) was reported at each abutment and all four wingwalls. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. Data in appendix D (Vermont Agency of Transportation, written communication, August 4, 1994) indicate that the right abutment may be founded on or near marble bedrock which may limit scour depths. Bedrock was not detected by borings in the vicinity of the left abutment. The scour analysis results are presented in tables 1 and 2 and a graph of the scour depths is presented in figure 8. Contraction scour for all modelled flows was 0 ft. Abutment scour ranged from 7.3 to 10.7 ft and the worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1993, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  13. National assessment of shoreline change part 4: historical coastal cliff retreat along the California coast

    USGS Publications Warehouse

    Hapke, Cheryl J.; Reid, David

    2007-01-01

    Coastal cliff retreat, the landward migration of the cliff face, is a chronic problem along many rocky coastlines in the United States. As coastal populations continue to grow and community infrastructures are threatened by erosion, there is increased demand for accurate information regarding trends and rates of coastal cliff retreat. There is also a need for a comprehensive analysis of cliff retreat that is consistent from one coastal region to another. To meet these national needs, the U.S. Geological Survey is conducting an analysis of historical coastal cliff retreat along open-ocean rocky coastlines of the conterminous United States and parts of Hawaii, Alaska, and the Great Lakes. One purpose of this work is to develop standard repeatable methods for mapping and analyzing coastal cliff retreat so that periodic updates of coastal erosion can be made nationally that are systematic and internally consistent. This report on the California Coast is an accompaniment to a report on long-term sandy shoreline change for California. This report summarizes the methods of analysis, interprets the results, and provides explanations regarding long-term rates of cliff retreat. Neither detailed background information on the National Assessment of Shoreline Change Project nor detailed descriptions of the geology and geomorphology of the California coastline are presented in this report. The reader is referred to the shoreline change report (Hapke et al., 2006) for this type of background information. Cliff retreat evaluations are based on comparing one historical cliff edge digitized from maps, with a recent cliff edge interpreted from lidar (Light Detection and Ranging) topographic surveys. The historical cliff edges are from a period ranging from 1920-1930, whereas the lidar cliff edges are from either 1998 or 2002. Long-term (~70-year) rates of retreat are calculated using the two cliff edges. The rates of retreat presented in this report represent conditions from the 1930s to 1998, and are not intended for predicting future cliff edge positions or rates of retreat. Due to the geomorphology of much of California's rocky coast (high-relief, steep slopes with no defined cliff edge) as well as to gaps in both the historical maps and lidar data, we were able to derive two cliff edges and therefore calculate cliff retreat rates for a total of 353 km. The average rate of coastal cliff retreat for the State of California was -0.3?0.2 m/yr, based on rates averaged from 17,653 individual transects measured throughout all areas of California's rocky coastline. The average amount of cliff retreat was 17.7 m over the 70-year time period of our analysis. Retreat rates were generally lowest in Southern California where coastal engineering projects have greatly altered the natural coastal system. California permits shoreline stabilization structures where homes, buildings or other community infrastructure are imminently threatened by erosion. While seawalls and/or riprap revetments have been constructed in all three sections of California, a larger proportion of the Southern California coast has been protected by engineering works, due, in part, to the larger population pressures in this area.

  14. Modern geomorphology in a post-glacial landscape and implications for river restoration, eastern Yosemite Valley, Yosemite National Park, USA

    NASA Astrophysics Data System (ADS)

    Minear, J. T.; Wright, S. A.; Roche, J. W.

    2011-12-01

    Yosemite National Park, USA, is one of the most popular national parks in the country with over 3.9 million visitors annually. The majority of tourists visit a relatively small area around the Merced River in scenic eastern Yosemite Valley, which has resulted in degradation to the river and streambanks. The National Park Service is updating the long-term management plan for the Merced River which includes river restoration. A key component determining the success of future river restoration efforts is the transport and supply of sediment. For this study, we investigate the modern geomorphology of the eastern Yosemite Valley region. For the watershed and reach analyses, we draw from a variety of topographic and hydrologic records, including 20-years of data from permanent cross sections, aerial and ground-based LiDAR surveys, and a nearly 100-year hydrologic record. In addition, we utilize hydraulic and sediment transport models to investigate channel velocities, bed shear stress and sediment transport at the reach scale. From the watershed-scale analysis, it is likely that large-scale remnant glacial features exert a primary control on the sediment supply to the study area with relatively small volumes of both suspended and bedload sediment being contributed to the study site. Two of the three major watersheds, Tenaya Creek and the upper Merced River, likely contribute only small amounts of bedload downstream due to low-gradient depositional reaches. Though little-known, the third major watershed, Illilouette Creek, is the only watershed capable of contributing larger amounts of bedload material, though the bedload material is likely contributed only during high flow events. High flows in the Yosemite Valley region have two different distributions: large early winter storm events above the 20-year return interval, and moderate snowmelt flows at and below the 20-year return interval. Sediment transport analyses indicate that bedload transport is dominated by relatively frequent (<2 year) snowmelt flow events and that the coarsest material in the reach (>110 mm) is mobile during these flows. The permanent cross sections record large topographic changes, including infilling at key bars, associated with the 1997 flood, the largest recorded early winter event (100-year return interval). Following snowmelt events post-1997, cross sections are returning to near pre-1997 levels. The cross section data suggest there is likely a disconnect between sediment supplied to the reach and sediment transport, with the majority of sediment supply occurring during large early winter events while the majority of sediment transport occurs during snowmelt events. An implication of our findings for river restoration in this area of the Merced River is that the ability of the channel to rebuild streambanks is relatively low, given the low suspended sediment supply. In contrast, bedload transport is relatively frequent and occurs in significant quantities, suggesting that river restoration involving bed recovery (e.g. recovery of pools formed by riprap or bridges) should be relatively rapid if obstructions are removed.

  15. Bathymetric and velocimetric surveys at highway bridges crossing the Missouri and Mississippi Rivers near St. Louis, Missouri, May 23–27, 2016

    USGS Publications Warehouse

    Huizinga, Richard J.

    2017-09-26

    Bathymetric and velocimetric data were collected by the U.S. Geological Survey, in cooperation with the Missouri Department of Transportation, near 13 bridges at 8 highway crossings of the Missouri and Mississippi Rivers in the greater St. Louis, Missouri, area from May 23 to 27, 2016. A multibeam echosounder mapping system was used to obtain channel-bed elevations for river reaches ranging from 1,640 to 1,970 feet longitudinally and extending laterally across the active channel from bank to bank during low to moderate flood flow conditions. These bathymetric surveys indicate the channel conditions at the time of the surveys and provide characteristics of scour holes that may be useful in the development of predictive guidelines or equations for scour holes. These data also may be useful to the Missouri Department of Transportation as a low to moderate flood flow comparison to help assess the bridges for stability and integrity issues with respect to bridge scour during floods.Bathymetric data were collected around every pier that was in water, except those at the edge of water, and scour holes were observed at most surveyed piers. The observed scour holes at the surveyed bridges were examined with respect to shape and depth.The frontal slope values determined for scour holes observed in the current (2016) study generally are similar to recommended values in the literature and to values determined for scour holes in previous bathymetric surveys. Several of the structures had piers that were skewed to primary approach flow, as indicated by the scour hole being longer on the side of the pier with impinging flow, and some amount of deposition on the leeward side, as typically has been observed at piers skewed to approach flow; however, at most skewed piers in the current (2016) study, the scour hole was deeper on the leeward side of the pier. At most of these piers, the angled approach flow was the result of a deflection or contraction of flow caused by a spur dike near the pier, which may affect flow differently than for a simple skew. At structure A6500 (site 33), the wide face of the pier footing and seal course would behave as a complex foundation, for which scour is computed differently.Previous bathymetric surveys exist for all the sites examined in this study. A previous survey in October 2010 at most of the sites had similar flow conditions and similar results to the 2016 surveys. A survey during flood conditions in August 2011 at the sites on the Missouri River and in May 2009 at structures A4936 and A1850 (site 35) on the Mississippi River did not always indicate more substantial scour during flood conditions. At structure A6500 (site 33) on the Mississippi River, a previous survey in 2009 was part of a habitat assessment before construction of the bridge and provides unique insight into the effects of the construction of that bridge on the channel in this reach. Substantial scour was observed near the right pier, and the riprap blanket surrounding the left pier seems to limit scour near that pier. Multiple additional surveys have been completed at structures A4936 and A1850 (site 35) on the Mississippi River, and the results of these surveys also are presented.

  16. Level II scour analysis for Bridge 7 (WALDTH00020007) on Town Highway 2, crossing Coles Brook, Walden, Vermont

    USGS Publications Warehouse

    Striker, Lora K.; Medalie, Laura

    1997-01-01

    ft, an average channel top width of 37 ft and an average bank height of 4 ft. The channel bed material ranges from sand to cobble with a median grain size (D50) of 32.9 mm (0.108 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 9, 1995, indicated that the reach was laterally unstable due to cut-banks, point bars, and loose unconsolidated bed material. The Town Highway 2 crossing of Coles Brook is a 74-ft-long, two-lane bridge consisting of one 71-foot steel-beam span (Vermont Agency of Transportation, written communication, April 5, 1995). The opening length of the structure parallel to the bridge face is 69.3 ft. The bridge is supported by spill-through abutments. The channel is skewed approximately 35 degrees to the opening while the measured opening-skew-to-roadway is 15 degrees. A scour hole 1.5 ft deeper than the mean thalweg depth was observed from 60 ft. to 100 ft. downstream during the Level I assessment. Scour protection measures at the site include: type-1 stone fill (less than 12 inches diameter) along the right bank upstream, at the downstream end of the downstream left wingwall and downstream right wingwall; and type-2 stone fill (less than 36 inches diameter) along the left bank upstream, at the upstream end of the upstream right wingwall, and along the entire base of the left and right abutments. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.8 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge. Abutment scour ranged from 5.7 to 12.9 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  17. Level II scour analysis for Bridge 12 (HUNTTH00010012) on Town Highway 001, crossing Brush Brook, Huntington, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.; Wild, Emily C.

    1997-01-01

    frequency data contained in the Flood Insurance Study for the Town of Huntington (U.S. Department of Housing and Urban Development, 1978). The site is in the Green Mountain section of the New England physiographic province in central Vermont. The 9.19-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture while the immediate banks have some woody vegetation. In the study area, the Brush Brook has a sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 62 ft and an average bank height of 5 ft. The channel bed material ranges from gravel to cobble with a median grain size (D50) of 100.0 mm (0.328 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 25, 1996, indicated that the reach was stable. The Town Highway 1 crossing of Brush Brook is a 64-ft-long, two-lane bridge consisting of one 62-foot steel-stringer span (Vermont Agency of Transportation, written communication, November 30, 1995). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 10 degrees to the opening while the opening-skew-to-roadway is 6 degrees. Channel scour 2.2 ft deeper than the mean thalweg depth was observed along the upstream right bank and along the base of the spill-through protection for the right abutment during the Level I assessment. Scour protection measured at the site was type-2 stone fill (less than 36 inches diameter) along the upstream left and right banks and in front of all four wingwalls. In front of the abutments, there was type-3 stone fill (less than 48 inches diameter) forming a spill-through slope. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. There was no computed contraction scour for any modelled flow. Abutment scour ranged from 1.4 to 2.8 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 9. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  18. Level II scour analysis for Bridge 38 (ANDOVT00110038) on State Route 11, crossing the Middle Branch Williams River, Andover, Vermont

    USGS Publications Warehouse

    Striker, Lora K.; Hammond, Robert E.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ANDOVT00110038 on State Route 11 crossing the Middle Branch Williams River, Andover, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in south central Vermont. The 5.65-mi2 drainage area is in a predominantly rural and forested basin. Upstream and downstream of the study site banks and overbanks are forested. In the study area, the Middle Branch Williams River has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 44 ft and an average bank height of 4 ft. The channel bed material ranges from gravel to boulders with a median grain size (D50) of 54.0 mm (0.177 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 5, 1996, indicated that the reach was stable. The State Route 11 crossing of the Middle Branch Williams River is a 33-ft-long, two-lane bridge consisting of one 31-foot concrete T-beam span (Vermont Agency of Transportation, written communication, March 29, 1995). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 55 degrees to the opening while the measured opening-skew-to-roadway is 45 degrees. There were no scour problems observed during the Level I assessment. Type-4 stone fill (less than 60 inches diameter) and type-3 stone fill (less than 48 inches diameter) was present on the left bank upstream and right bank upstream respectively. Type-2 stone fill (less than 36 inches diameter) was present in the upstream left wing wall area. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 1.8 to 3.4 ft. The worst-case contraction scour occurred at the 500-year flow. Abutment scour ranged from 12.0 to 14.0 ft. The worst-case abutment scour occurred at the 500-year flow at the right abutment. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  19. Level II scour analysis for Bridge 23 (GLOVTH00410023) on Town Highway 41, crossing Sherburne Brook, Glover, Vermont

    USGS Publications Warehouse

    Olson, Scott A.; Boehmler, Erick M.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure GLOVTH00410023 on Town Highway 41 crossing Sherburne Brook, Glover, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in northern Vermont. The 2.57-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is primarily forest with small areas of lawn and a home on the right overbank and a gravel roadway along the upstream left bank. In the study area, Sherburne Brook has an incised, sinuous channel with a slope of approximately 0.03 ft/ft, an average channel top width of 33 ft and an average bank height of 6 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 57.3 mm (0.188 ft). The geomorphic assessment at the time of the Level I and Level II site visit on October 24, 1994, indicated that the reach was stable. The Town Highway 41 crossing of Sherburne Brook is a 24-ft-long, one-lane bridge consisting of one 21-foot steel-beam span with a timber deck (Vermont Agency of Transportation, written communication, August 4, 1994). The opening length of the structure parallel to the bridge face is 20.3 ft. The bridge is supported by vertical, granite block abutments. The channel is skewed approximately 55 degrees to the opening while the measured opening-skew-to-roadway is 30 degrees. One foot of scour below the mean thalweg depth was observed along the right abutment undermining the abutment by 0.5 feet vertically. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.4 to 0.8 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 4.6 to 7.2 ft. The worst-case abutment scour also occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  20. Level II scour analysis for Bridge 19 (SHEFTH00440019) on Town Highway 44, crossing Trout Brook, Sheffield, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Medalie, Laura

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure SHEFTH00440019 on Town Highway 44 crossing Trout Brook, Sheffield, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the White Mountain section of the New England physiographic province in northeastern Vermont. The 3.0-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is grass on the upstream and downstream right overbanks, while the immediate banks have dense woody vegetation. The surface cover of the upstream and downstream left overbanks is shrub and brushland. In the study area, Trout Brook has an incised, sinuous channel with a slope of approximately 0.03 ft/ft, an average channel top width of 45 ft and an average bank height of 6 ft. The channel bed material ranges from sand to boulder with a median grain size (D50) of 116 mm (0.381 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 31, 1995, indicated that the reach was stable. The Town Highway 44 crossing of Trout Brook is a 24-ft-long, one-lane bridge consisting of a 22-foot steel-stringer span (Vermont Agency of Transportation, written communication, March 28, 1994). The opening length of the structure parallel to the bridge face is 19.8 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 10 degrees to the opening while the opening-skew-to-roadway is zero degrees. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was analyzed since it has the potential of being the worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows resulted in zero ft. Left abutment scour ranged from 4.4 to 5.6 ft. The worst-case left abutment scour occurred at the 500-year discharge. Right abutment scour ranged from 3.6 to 4.8 ft. The worst-case right abutment scour occurred at the incipient roadway-overtopping discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particlesize distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  1. Level II scour analysis for Bridge 42 (NEWFTH00350042) on Town Highway 35, crossing Stratton Hill Brook, Newfane, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Ivanoff, Michael A.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure NEWFTH00350042 on Town Highway 35 crossing Stratton Hill Brook, Newfane, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the New England Upland section of the New England physiographic province in southeastern Vermont. The 1.16-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forested. In the study area, Stratton Hill Brook has an incised, striaght channel with a slope of approximately 0.1 ft/ft, an average channel top width of 36 ft and an average bank height of 8 ft. The channel bed material ranges from gravel to boulders with a median grain size (D50) of 121 mm (0.396 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 20, 1996, indicated that the reach was stable. The Town Highway 34 crossing of Stratton Hill Brook is a 34-ft-long, one-lane bridge consisting of a 32-foot steel-beam span (Vermont Agency of Transportation, written communication, April 6, 1995). The opening length of the structure parallel to the bridge face is 30.8 ft. The bridge is supported by vertical, concrete abutments with upstream wingwalls. The channel is skewed approximately 20 degrees to the opening while the computed opening-skew-to-roadway is 15 degrees. During the Level I assessment, it was observed that the right abutment footing was exposed 1.5 feet. The only scour protection measure at the site was type-1 stone fill (less than 12 inches diameter) along the downstream left bank. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was zero ft. Abutment scour ranged from 2.3 to 3.3 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  2. Level II scour analysis for Bridge 17 (LYNDTH00020017) on Town Highway 2, crossing Hawkins Brook, Lyndon, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Medalie, Laura

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure LYNDTH00020017 on Town Highway 2 crossing Hawkins Brook, Lyndon, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D.The site is in the Green Mountain section of the New England physiographic province in northeastern Vermont. The 7.7-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest on the left and right upstream overbanks. The downstream left and right overbanks are brushland.In the study area, Hawkins Brook has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 78 ft and an average bank height of 7.3 ft. The channel bed material ranges from sand to boulder with a median grain size (D50) of 46.6 mm (0.153 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 4, 1995, indicated that the reach was laterally unstable with the presence of point bars and side bars.The Town Highway 2 crossing of Hawkins Brook is a 49-ft-long, two-lane bridge consisting of a 46-foot steel-stringer span (Vermont Agency of Transportation, written communication, March 27, 1995). The opening length of the structure parallel to the bridge face is 43 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 45 degrees to the opening while the computed opening-skew-to-roadway is zero degrees.A scour hole 0.75 ft deeper than the mean thalweg depth was observed along the downstream left abutment during the Level I assessment. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) at the upstream end of the downstream left wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.Contraction scour for all modelled flows ranged from 0.1 to 0.9 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 3.8 to 6.6 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  3. Level II scour analysis for Bridge 6 (MORRTH00030006) on Town Highway 3, crossing Ryder Brook, Morristown, Vermont

    USGS Publications Warehouse

    Boehmler, Erick M.; Hammond, Robert E.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure MORRTH00030006 on Town Highway 3 crossing Ryder Brook, Morristown, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in north-central Vermont. The 19.1-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover also is forested. In the study area, Ryder Brook has a straight channel with an average channel top width of 450 ft and an average bank height of 7 ft. The predominant channel bed material is silt and clay with a median grain size (D50) of 0.0719 mm (0.000236 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 18, 1996, indicated that the reach was aggraded, but the channel through the bridge was scoured. The Town Highway 3 crossing of Ryder Brook is a 72-ft-long, two-lane bridge consisting of one 70-foot steel-beam span (Vermont Agency of Transportation, written communication, January 31, 1996). The bridge is supported by vertical, concrete abutments with spill-through embankments and wingwalls. The channel is not skewed to the opening and the opening-skew-to-roadway is zero degrees. Channel scour under the bridge was evident at this site during the Level I assessment. The depth of the channel increases from 3 feet at the upstream bridge face to 10 feet at the downstream bridge face. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) on the spill-through embankments of each abutment, the upstream road embankments and the downstream left road embankment. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 20.4 to 25.8 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 8.3 to 10.5 ft. The worst-case abutment scour also occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  4. Level II scour analysis for Bridge 41 (WODSTH00750041) on Town Highway 75, crossing Happy Valley Brook, Woodstock, Vermont

    USGS Publications Warehouse

    Olson, Scott A.

    1996-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure WODSTH00750041 on town highway 75 crossing Happy Valley Brook, Woodstock, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province of east-central Vermont. The 3.45-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is brush with scattered trees. In the study area, Happy Valley Brook has an incised, sinuous channel with a slope of approximately 0.03 ft/ft, an average channel top width of 23 ft and an average channel depth of 5 ft. The predominant channel bed materials are gravel and cobble with a median grain size (D50) of 82.8 mm (0.272 ft). The geomorphic assessment at the time of the Level II site visits on September 13, 1994 and December 14, 1994, indicated that the reach was degrading. Five logs are embedded across the channel under the bridge in an attempt to prevent further degradation (see Figures 5 and 6). The town highway 75 crossing of Happy Valley Brook is a 27-ft-long, two-lane bridge consisting of one 25-foot steel-beam span. The clear span is 17 ft. (Vermont Agency of Transportation, written communication, August 3, 1994). The bridge is supported by vertical, stone abutments with wingwalls. The channel is skewed approximately 40 degrees to the opening and the opening-skew-to-roadway is also 40 degrees. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 1.3 to 2.2 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 7.2 to 12.0 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  5. Level II scour analysis for Bridge 33 (HUNTTH00220033) on Town Highway 22, crossing Brush Brook, Huntington, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.; Degnan, James R.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure HUNTTH00220033 on Town Highway 22 crossing Brush Brook, Huntington, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in central Vermont. The 8.65-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest except on the downstream right overbank which is pasture. In the study area, Brush Brook has an incised, straight channel with a slope of approximately 0.04 ft/ft, an average channel top width of 42 ft and an average bank height of 3 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 76.7 mm (0.252 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 26, 1996, indicated that the reach was stable. The Town Highway 22 crossing of Brush Brook is a 40-ft-long, two-lane bridge consisting of one 23.5-foot concrete slab span (Vermont Agency of Transportation, written communication, November 30, 1995). The opening length of the structure parallel to the bridge face is 36.9 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 35 degrees to the opening while the opening-skew-to-roadway is 30 degrees. The scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the left and right banks upstream that extended through the bridge and along the downstream banks. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is analyzed since it has the potential of being the worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 1.1 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 6.5 to 14.9 ft. The worst-case abutment scour occurred at the incipient roadway-overtopping discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  6. Level II scour analysis for Bridge 25 (JAMATH00010025) on Town Highway 1, crossing Ball Mountain Brook, Jamaica, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure JAMATH00010025 on Town Highway 1 crossing Ball Mountain Brook, Jamaica, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in southern Vermont. The 29.5-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest except on the downstream right bank which is pasture with some trees along the channel. In the study area, Ball Mountain Brook has an incised, straight channel with a slope of approximately 0.021 ft/ft, an average channel top width of 86 ft and an average bank height of 9 ft. The channel bed material ranges from gravel to bedrock with a median grain size (D50) of 222 mm (0.727 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 13, 1996, indicated that the reach was stable. The Town Highway 1 crossing of Ball Mountain Brook is a 78-ft-long, two-lane bridge consisting of one 75-foot steel-beam span (Vermont Agency of Transportation, written communication, March 29, 1995). The opening length of the structure parallel to the bridge face is 73 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 30 degrees to the opening while the opening-skew-to-roadway is 30 degrees. A scour hole 1.0 ft deeper than the mean thalweg depth was observed at the upstream bridge face. The scour protection measures at the site were type-2 stone fill (less than 36 inches diameter) along the upstream banks and along both abutments, and type-3 stone fill (less than 48 inches diameter) along the downstream banks. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour only occurred at the 500-year discharge and was 0.1 ft. Abutment scour ranged from 11.2 to 15.7 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  7. Level II scour analysis for Bridge 32 (HUNTTH00220032) on Town Highway 22, crossing Brush Brook, Huntington, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure HUNTTH00220032 on Town Highway 22 crossing Brush Brook, Huntington, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in central Vermont. The 5.7-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest except on the downstream right overbank which is pasture. In the study area, Brush Brook has an incised, straight channel with a slope of approximately 0.05 ft/ft, an average channel top width of 58 ft and an average bank height of 6 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 127 mm (0.416 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 25, 1996, indicated that the reach was stable. The Town Highway 22 crossing of Brush Brook is a 36-ft-long, one-lane bridge consisting of one 34-foot steel-beam span and a timber deck (Vermont Agency of Transportation, written communication, December 12, 1995). The opening length of the structure parallel to the bridge face is 35.7 ft. The bridge is supported by vertical, concrete abutments with wingwalls on the left. The channel is skewed approximately 50 degrees to the opening while the measured opening-skew-to-roadway is 15 degrees. A scour hole 1.0 ft deeper than the mean thalweg depth was observed along the left abutment and downstream left wingwall during the Level I assessment. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the upstream right bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.2 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 6.4 to 10.2 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  8. Level II scour analysis for Bridge 39 (ANDOVT00110039) on State Route 11, crossing the Middle Branch Williams River, Andover, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.; Wild, Emily C.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ANDOVT00110039 on State Route 11 crossing the Middle Branch Williams River, Andover, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in southern Vermont. The 5.75-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest on the upstream left bank and downstream right bank. The surface cover on the upstream right and downstream left banks is brush. In the study area, the Middle Branch Williams River has an incised, sinuous channel with a slope of approximately 0.01 ft/ft, an average channel top width of 58 ft and an average bank height of 8 ft. The channel bed material ranges from sand to boulder with a median grain size (D50) of 96.8 mm (0.317 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 9, 1996, indicated that the reach was laterally unstable. The State Route 11 crossing of the Middle Branch Williams River is a 43-ft-long, two-lane bridge consisting of one 41-foot concrete-beam span and two additional steel beams on the upstream face (Vermont Agency of Transportation, written communication, March 29, 1995). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 45 degrees to the opening while the opening-skew-to-roadway is 45 degrees. The only scour protection measures at the site was type-2 stone fill (less than 36 inches diameter) at the upstream end of the upstream right wingwall and type-3 stone fill (less than 48 inches diameter) along the entire base length of the upstream left wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.8 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 8.9 to 11.2 ft. The worst-case abutment scour occurred at the incipient-overtopping discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  9. Level II scour analysis for Bridge 25 (ANDOTH00230025) on Town Highway 23, crossing Andover Branch, Andover, Vermont

    USGS Publications Warehouse

    Flynn, Robert H.; Burns, Ronda L.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ANDOTH00230025 on Town Highway 23 crossing the Andover Branch, Andover, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in south-central Vermont. The 6.74-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture on the right overbank and forest on the left overbank while the immediate banks, both upstream and downstream, are forested. In the study area, the Andover Branch has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 55 ft and an average bank height of 9 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 78.4 mm (0.257 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 27, 1996, indicated that the reach was stable. The Town Highway 23 crossing of the Andover Branch is a 25-ft-long, two-lane structure consisting of a multi-plate corrugated steel arch culvert with concrete footings (Vermont Agency of Transportation, written communication, March 29, 1995). The culvert is mitered at the inlet and outlet. The channel is skewed approximately zero degrees to the opening while the opening-skew-to-roadway is zero degrees. The footings are exposed approximately 1.25 ft, with the exception of the downstream end of the right footing which is exposed approximately 0.5 ft. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the upstream left bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for modelled flows ranged from 1.6 to 2.8 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 10.0 to 11.7 ft along the left footing and from 11.8 to 16.7 along the right footing. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A crosssection of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  10. Temporal Chemical Data for Sediment, Water, and Biological Samples from the Lava Cap Mine Superfund Site, Nevada County, California-2006-2008

    USGS Publications Warehouse

    Foster, Andrea L.; Ona-Nguema, Georges; Tufano, Kate; White, Richard III

    2010-01-01

    The Lava Cap Mine is located about 6 km east of the city of Grass Valley, Nevada County, California, at an elevation of about 900 m. Gold was hosted in quartz-carbonate veins typical of the Sierran Gold Belt, but the gold grain size was smaller and the abundance of sulfide minerals higher than in typical deposits. The vein system was discovered in 1860, but production was sporadic until the 1930s when two smaller operations on the site were consolidated, a flotation mill was built, and a 100-foot deep adit was driven to facilitate drainage and removal of water from the mine workings, which extended to 366 m. Peak production at the Lava Cap occurred between 1934 and 1943, when about 90,000 tons of ore per year were processed. To facilitate removal of the gold and accessory sulfide minerals, the ore was crushed to a very fine sand or silt grain size for processing. Mining operations at Lava Cap ceased in June 1943 due to War Production Board Order L-208 and did not resume after the end of World War II. Two tailings retention structures were built at the Lava Cap Mine. The first was a log dam located about 0.4 km below the flotation mill on Little Clipper Creek, and the second, built in 1938, was a larger earth fill and rip-rap structure constructed about 2 km downstream, which formed the water body now called Lost Lake. The log dam failed during a storm that began on December 31, 1996, and continued into January 1997; an estimated 8,000-10,000 m3 of tailings were released into Little Clipper Creek during this event. Most of the fine tailings were deposited in Lost Lake, dramatically increasing its turbidity and resulting in a temporary 1-1.5 m rise in lake level due to debris blocking the dam spillway. When the blockage was cleared, the lake level quickly lowered, leaving a ?bathtub ring? of very fine tailings deposited substantially above the water line. The U.S. Environmental Protection Agency (EPA) initiated emergency action in late 1997 at the mine site to reduce the possibility of future movement of tailings, and began an assessment of the risks posed by physical and chemical hazards at the site. The EPA's assessment identified arsenic (As) as the primary hazard of concern. Three main exposure routes were identified: inhalation/ingestion of mine tailings, dermal absorption/ingestion of As in lake water from swimming, and ingestion of As-contaminated ground water or surface water. Lost Lake is a private lake which is completely surrounded by low-density residential development. Prior to the dam failure, the lake was used by the local residents for swimming and boating. An estimated 1,776 people reside within one mile of the lake, and almost all residents of the area use potable groundwater for domestic use. Risk factors for human exposure to As derived from mine wastes were high enough to merit placement of the mine site and surrounding area on the National Priority List (commonly called ?Superfund?). The Lava Cap Mine Superfund site (LCMS) encompasses approximately 33 acres that include the mine site, the stretch of Little Clipper Creek between the mine and Lost Lake, the lake itself, and the area between the lake and the confluence of Little Clipper Creek with its parent stream, Clipper Creek. The area between the two creeks is named the ?deposition area? due to the estimated 24 m thick layer of tailings that were laid down there during and after active mining. The lobate structure of Lost Lake is also due to deposition in this area. The deposition area and Lost Lake are together estimated to contain 382,277 m3 of tailings. The primary goals of the EPA have been to minimize tailings movement downstream of Lost Lake and to ensure that residents in the area have drinking water that meets national water quality standards. EPA has officially decided to construct a public water supply line to deliver safe water to affected residences, since some residential wells in the area have As concentrations above the curr

  11. Level II scour analysis for Bridge 22 (JAY-TH00400022) on Town Highway 40, crossing Jay Branch, Jay, Vermont

    USGS Publications Warehouse

    Ivanoff, Michael A.; Song, Donald L.

    1997-01-01

    8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in northern Vermont. The 2.15-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is primarily pasture on the upstream and downstream left overbank while the immediate banks have dense woody vegetation. The downstream right overbank of the bridge is forested. In the study area, Jay Branch Tributary has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 26 ft and an average bank height of 3 ft. The channel bed material ranges from gravel to cobble with a median grain size (D50) of 40.5 mm (0.133 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 7, 1995, indicated that the reach was stable. The Town Highway 40 crossing of Jay Branch Tributary is a 27-ft-long, two-lane bridge consisting of one 25-foot steel-beam span (Vermont Agency of Transportation, written communication, March 6, 1995). The opening length of the structure parallel to the bridge face is 23.5 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel skew and the opening-skew-to-roadway are zero degrees. The scour counter-measures at the site included type-2 stone fill (less than 36 inches diameter) at the upstream end of the left and right abutments, at the upstream right wingwall, and at the downstream left wingwall. There was also type-3 stone fill (less than 48 inches diameter) at the upstream left and downstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.7 to 1.1 ft. The worst-case contraction scour occurred at the 500-year discharge. Left abutment scour ranged from 4.6 to 4.9 ft. The worst-case left abutment scour occurred at the 100-year discharge. Right abutment scour ranged from 4.0 to 5.0 ft. The worst-case right abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  12. Level II scour analysis for Bridge 29 (CRAFTH00550029) on Town Highway 55, crossing the Black River, Craftsbury, Vermont

    USGS Publications Warehouse

    Boehmler, Erick M.; Degnan, James R.

    1996-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure CRAFTH00550029 on town highway 55 crossing the Black River, Craftsbury, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province of north-central Vermont in the town of Craftsbury. The 24.7-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the banks have woody vegetation coverage except for the upstream left bank and the downstream right bank, which have more brush cover than trees. In the study area, the Black River has an incised, sinuous channel with a slope of approximately 0.01 ft/ft, an average channel top width of 41 ft and an average channel depth of 5.5 ft. The predominant channel bed material is sand and gravel (D50 is 44.7 mm or 0.147 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 7, 1995, indicated that the reach was stable. The town highway 55 crossing of the Black Riveris a 32-ft-long, one-lane bridge consisting of one 28-foot span steel stringer superstructure with a timber deck (Vermont Agency of Transportation, written communication, August 4, 1994). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 40 degrees to the opening while the opening-skew-to-roadway is 10 degrees. A scour hole 2 ft deeper than the mean thalweg depth was evident at mid-channel immediately downstream of the bridge during the Level I assessment. The only scour protection measure at the site was type-1 stone fill (less than 12 inches diameter) on the upstream right bank and road approach embankment. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.9 to 1.4 ft. The worst-case contraction scour occurred at the 100-year discharge. Abutment scour ranged from 12.1 to 15.5 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  13. Level II scour analysis for Bridge 22 (BRADTH00270022) on Town Highway 27, crossing the Waits River, Bradford, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Ivanoff, Michael A.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure BRADTH00270022 on Town Highway 27 crossing the Waits River, Bradford, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, obtained from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the New England Upland section of the New England physiographic province in east-central Vermont. The 153-mi2 drainage area is in a predominantly rural and forested basin. However, in the vicinity of the study site, the upstream and downstream left banks are suburban and the upstream and downstream right banks are shrub and brushland. In the study area, the Waits River has an incised, sinuous channel with a slope of approximately 0.0002 ft/ft, an average channel top width of 125 ft and an average bank height of 4 ft. The channel bed material ranges from silt and clay to bedrock with a median grain size (D50) of 0.393 mm (0.00129 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 7, 1995, indicated that the reach was stable. The Town Highway 27 crossing of the Waits River is a 109-ft-long, one-lane bridge consisting of a 104-ft steel-truss span (Vermont Agency of Transportation, written communication, March 16, 1995). The opening length of the structure parallel to the bridge face is 99.2 ft. The bridge is supported by vertical, laid-up stone abutments. The channel is skewed approximately 30 degrees to the opening while the opening-skew-to-roadway is zero degrees. No evidence of scour was observed during the Level I assessment. Scour protection measures at the site included type-2 stone fill (less than 36 inches diameter) along the upstream right and downstream left banks and type-3 stone fill (less than 48 inches diameter) along the left and right abutments. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 1.5 to 2.0 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 11.8 to 18.8 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results.” Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  14. Level II scour analysis for Bridge 33 (WWINTH00300033) on Town Highway 30, crossing Mill Brook, West Windsor, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Flynn, Robert H.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure WWINTH00300033 on Town Highway 30 crossing Mill Brook, West Windsor, Vermont (Figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the New England Upland section of the New England physiographic province in east-central Vermont. The 24.9-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture upstream of the bridge while the immediate banks have dense woody vegetation. Downstream of the bridge is forested. In the study area, Mill Brook has an incised, sinuous channel with a slope of approximately 0.004 ft/ft, an average channel top width of 58 ft and an average bank height of 5 ft. The channel bed material ranges from sand to boulder with a median grain size (D50) of 65.7 mm (0.215 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 5, 1996, indicated that the reach was stable. The Town Highway 30 crossing of the Mill Brook is a 46-ft-long, one-lane covered bridge consisting of a 40-foot wood-beam span (Vermont Agency of Transportation, written communication, March 23, 1995). The opening length of the structure parallel to the bridge face is 36.3 ft. The bridge is supported by vertical, concrete capped laid-up stone abutments with wingwalls. The channel is skewed approximately 10 degrees to the opening while the opening-skew-to-roadway is zero degrees. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the upstream right bank, the upstream right wingwall, the right abutment and the downstream left wingwall. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was analyzed since it had the potential of being the worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.1 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 6.0 to 16.0 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  15. Level II scour analysis for Bridge 42 (HARDELMSTR0042) on Elm Street, crossing Cooper Brook, Hardwick, Vermont

    USGS Publications Warehouse

    Olson, Scott A.

    1996-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure HARDELMSTR0042 on Elm Street crossing Cooper Brook, Hardwick, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in north-central Vermont. The 16.6-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the overbanks are primarily grass covered with some brush along the immediate channel banks except the upstream right bank and overbank which is forested and the downstream left overbank which has a lumberyard. In the study area, Cooper Brook has a sinuous channel with a slope of approximately 0.005 ft/ft, an average channel top width of 50 ft and an average channel depth of 6 ft. The predominant channel bed materials are sand and gravel with a median grain size (D50) of 1.25 mm (0.00409 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 24, 1995, indicated that the reach was stable. The Elm Street crossing of Cooper Brook is a 39-ft-long, two-lane bridge consisting of one 37-foot concrete span (Vermont Agency of Transportation, written communication, March 17, 1995). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 40 degrees to the opening while the opening-skew-to-roadway is 45 degrees. On August 17, 1995 the site was revisited to investigate the effect of the August 4-5, 1995 flood on the structure. Channel features such as scour holes and point bars were shifted by the high flow event. Details of these changes can be found in the Level I data form in Appendix E. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and G. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 3.4 ft. The worst-case contraction scour occurred at the incipient-overtopping discharge which was less than the 100-year discharge. Abutment scour ranged from 7.1 to 10.4 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1993, p. 48). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  16. Level II scour analysis for Bridge 32 (FERRTH00190032) on Town Highway 19, crossing the South Slang Little Otter Creek, Ferrisburgh, Vermont

    USGS Publications Warehouse

    Ivanoff, Michael A.; Wild, Emily C.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure FERRTH00190032 on Town Highway 19 crossing the South Slang Little Otter Creek (Hawkins Slang Brook), Ferrisburg, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Champlain section of the St. Lawrence Valley physiographic province in west-central Vermont. The 8.00-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover consists of wetlands upstream and downstream of the bridge with trees and pasture on the wide flood plains. In the study area, the South Slang Little Otter Creek has a meandering channel with essentially no channel slope, an average channel top width of 932 ft and an average bank height of 6 ft. The channel bed material ranges from clay to sand. Sieve analysis indicates that greater than 50% of the sample is coarse silt and clay and thus a medium grain size by use of sieve analysis was indeterminate. The median grain size was assumed to be a course silt with a size (D50) of 0.061mm (0.0002 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 2, 1996, indicated that the reach was stable. The Town Highway 19 crossing of the South Slang Little Otter Creek is a 45-ft-long, twolane bridge consisting of one 42-foot concrete box-beam span (Vermont Agency of Transportation, written communication, December 11, 1995). The opening length of the structure parallel to the bridge face is 41.8 ft. The bridge is supported by vertical, concrete abutments. The channel is skewed approximately 5 degrees to the opening while the opening-skew-to-roadway is zero degrees. A scour hole 3.5 ft deeper than the mean thalweg depth was observed in the upstream channel. Also a scour hole 2.0 ft deeper than the mean thalweg depth was observed along the right abutment during the Level I assessment. The scour protection measures at the site are type-1 stone fill (less than 12 inches diameter) around the left and right abutments, along the upstream and downstream road embankments, and across the entire upstream and downstream bridge face. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 14.0 to 20.2 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 3.2 to 8.3 ft. The worst-case abutment scour occurred at the 500-year discharge. The predicted scour is well above the pile bottom elevations. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. Computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  17. Level II scour analysis for Bridge 43 (BENNCYDEPO0043) on Depot Street, crossing the Walloomsac River, Bennington, Vermont

    USGS Publications Warehouse

    Olson, Scott A.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure BENNCYDEPO0043 on the Depot Street crossing of the Walloomsac River, Bennington, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in southwestern Vermont. The 30.1-mi2 drainage area is a predominantly rural and forested basin. The bridge site is located within an urban setting in the Town of Bennington with buildings and parking lots on overbanks. In the study area, the Walloomsac River has a straight channel with constructed channel banks through much of the reach. The channel is located on a delta and has a slope of approximately 0.02 ft/ft, an average channel top width of 48 ft and an average bank height of 6 ft. The predominant channel bed material is cobble with a median grain size (D50) of 108 mm (0.356 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 5, 1996, indicated that the reach was stable. The Depot Street crossing of the Walloomsac River is a 46-ft-long, two-lane bridge consisting of one 40-foot concrete span (Vermont Agency of Transportation, written communication, December 13, 1995). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 5 degrees to the opening and the opening-skew-to-roadway is 15 degrees. Scour countermeasures at the site include type-2 stone fill (less than 36 inches diameter) at the upstream end of the upstream right wing wall and type-1 stone fill (less than 12 inches diameter) along the base of the upstream left wing wall. Downstream banks are protected by concrete and stone walls. The upstream right bank is protected by alternating type-2 stone fill and masonry walls. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour computed for all modelled flows ranged from 0.0 to 4.1 ft. The worst-case contraction scour occurred at the 500-year discharge. Computed right abutment scour ranged from 2.9 to 13.4 ft. with the worst-case scour occurring at the 500-year discharge. Computed left abutment scour ranged from 5.6 to 16.3 ft. with the worst-case scour also occurring at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  18. Level II scour analysis for Bridge 46 (LINCTH00060046) on Town Highway 6, crossing the New Haven River, Lincoln, Vermont

    USGS Publications Warehouse

    Wild, Emily C.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure LINCTH00060046 on Town Highway 6 crossing the New Haven River, Lincoln, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Green Mountain section of the New England physiographic province in west-central Vermont. The 45.9-mi2 drainage area is in a predominantly suburban and forested basin. In the vicinity of the study site, the surface cover is forest upstream of the bridge. The downstream right overbank near the bridge is suburban with buildings, homes, lawns, and pavement (less than fifty percent). The downstream left overbank is brushland while the immediate banks have dense woody vegetation. In the study area, the New Haven River has an incised, sinuous channel with a slope of approximately 0.01 ft/ft, an average channel top width of 95 ft and an average bank height of 7 ft. The channel bed material ranges from sand to bedrock with a median grain size (D50) of 120.7 mm (0.396 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 13, 1996, indicated that the reach was stable. The Town Highway 34 crossing of the New Haven River is a 85-ft-long, two-lane bridge consisting of an 80-foot steel arch truss (Vermont Agency of Transportation, written communication, December 14, 1995). The opening length of the structure parallel to the bridge face is 69 feet. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 25 degrees to the opening while the opening-skew-to-roadway is 5 degrees. A scour hole 2.0 ft deeper than the mean thalweg depth was observed in the downstream channel during the Level I assessment. Protection measures at the site include type-1 stone fill (less than 12 inches diameter) at the upstream left wingwall, type-2 stone fill (less than 36 inches diameter) at the downstream end of the downstream left wingwall, and type-3 stone fill (less than 48 inches diameter) at the upstream right wingwall and the downstream end of the downstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 1.7 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge. Left abutment scour ranged from 12.9 to 17.8 ft. Right abutment scour ranged from 5.9 to 11.9 ft. The worst-case abutment scour occurred at the incipient roadway-overtopping discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  19. Level II scour analysis for Bridge 10 (BENNUS00070010) on U.S. Route 7, crossing the Walloomsac River, Bennington, Vermont

    USGS Publications Warehouse

    Olson, Scott A.; Burns, Ronda L.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure BENNUS00070010 on U.S. Route 7, also known as North Street, crossing of the Walloomsac River, Bennington, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in southwestern Vermont. The 30.1-mi2 drainage area is a predominantly rural and forested basin. The bridge site is located within an urban setting in the Town of Bennington with buildings, parking lots, lawns, and a playground on the overbank areas. In the study area, the Walloomsac River has a straight channel with constructed channel banks through much of the reach. The channel is located on a delta and has a slope of approximately 0.02 ft/ft, an average channel top width of 37 ft and an average bank height of 5 ft. The predominant channel bed material is cobble with a median grain size (D50) of 96.0 mm (0.315 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 5, 1996, indicated that the constructed reach was stable. The U.S. Route 7 crossing of the Walloomsac River is a 53-ft-long, two-lane bridge consisting of one 50-foot steel span (Vermont Agency of Transportation, written communication, September 27, 1995). The bridge is supported by vertical, concrete abutments with wingwalls. The wingwalls are angled in toward the channel because the widths of the upstream and downstream constructed channel banks are narrower than the bridge opening. The channel is skewed approximately 5 degrees to the opening and the opening-skew-to-roadway is 10 degrees. Scour countermeasures at the site include masonry and stone walls on both the upstream and downstream banks. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour computed for all modelled flows ranged from 0.0 to 0.1 ft. The worstcase contraction scour occurred at the 500-year discharge. Computed left abutment scour ranged from 5.9 to 6.8 ft. with the worst-case scour occurring at the 500-year discharge. Computed right abutment scour for all modelled flows was 6.8 ft. Total scour depths for all modelled flows did not exceed the depth of the abutment footings. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  20. Level II scour analysis for Bridge 45a (BRIDUS00040045a) on U.S. Route 4, crossing Ottauquechee River, Bridgewater, Vermont

    USGS Publications Warehouse

    Olson, Scott A.

    1996-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure BRIDUS00040045a on U.S.. Route 4 crossing the Ottauquechee River, Bridgewater, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). A Level I study is included in Appendix E of this report. A Level I study provides a qualitative geomorphic characterization of the study site. Information on the bridge available from VTAOT files was compiled prior to conducting Level I and Level II analyses and can be found in Appendix D. The site is in the Green Mountain physiographic province of central Vermont in the town of Bridgewater. The 72.1-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the overbank areas are lawn or pasture with a few residences. The immediate channel banks have moderately dense woody vegetation. In the study area, the Ottauquechee River has a sinuous channel with a slope of approximately 0.01 ft/ft, an average channel top width of 81 ft and an average channel depth of 3 ft. The predominant channel bed materials are gravel and cobble (D50 is 54.9 mm or 0.180 ft). The geomorphic assessment at the time of the Level I and Level II site visit on October 26, 1994, indicated that the reach was stable. The U.S. Route 4 crossing of the Ottauquechee Riveris a 172-ft-long, two-lane bridge consisting of three steel-beam spans supported by spill-through abutments and two concrete piers (Vermont Agency of Transportation, written commun., August 25, 1994). The abutment and road approaches are protected by type-2 stone fill (less than 36 inches diameter). The North Branch of the Ottauquechee River joins the Ottauquechee River approximately 200 feet upstream of the bridge on the main branch’s left bank. The channel approach to the bridge has a mild bend with the bridge skewed 15 degrees to flow; the opening-skew-to-roadway is 30 degrees. Additional details describing conditions at the site are included in the Level II Summary, Appendix D, and Appendix E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 3.1 to 4.0 ft. with the worst-case contraction scour occurring at the 500-year and incipient road-overflow discharges. Abutment scour ranged from 9.3 to 15.2 ft. The worst-case abutment scour also occurred at the 500-year discharge. Pier scour ranged from 11.4 to 12.4 ft. with the worst-case scenario occurring at the incipient roadway overflow discharge. The incipient roadway overflow discharge was between the 100- and 500-year discharges. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1993, p. 48). Many factors, including historical performance during flood events, the geomorphic assessment, scour protection measures, and the results of the hydraulic analyses, must be considered to properly assess the validity of abutment scour results. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein, based on the consideration of additional contributing factors and experienced engineering judgement.

  1. Level II scour analysis for Bridge 52 (CHESTH00100052) on Town Highway 10, crossing the South branch Williams River, Chester, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Ivanoff, Michael A.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure CHESTH00100052 on Town Highway 10 crossing the South Branch Williams River, Chester, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the New England Upland section of the New England physiographic province in southeastern Vermont. The 4.05-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest upstream and downstream of the bridge. In the study area, the South Branch Williams River has an incised, sinuous channel with a slope of approximately 0.03 ft/ft, an average channel top width of 35 ft and an average bank height of 4 ft. The channel bed material ranges from gravel to boulders with a median grain size (D50) of 82.1 mm (0.269 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 21, 1996, indicated that the reach was unstable, as a result of the moderate bank erosion. The Town Highway 10 crossing of the South Branch Williams River is a 32-ft-long, one-lane bridge consisting of a 29-foot steel-stringer span (Vermont Agency of Transportation, written communication, March 31, 1995). The opening length of the structure parallel to the bridge face is 27.6 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 25 degrees to the opening while the opening-skew-to-roadway is 20 degrees. A scour hole 1.0 ft deeper than the mean thalweg depth was observed at the downstream end of the right abutment during the Level I assessment. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the upstream left and right banks, the upstream end of the upstream right wingwall and the entire base length of the upstream left wingwall. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.8 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 5.2 to 10.8 ft. The worst-case abutment scour also occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  2. Level II scour analysis for Bridge 34 (ROCHTH00210034) on Town Highway 21, crossing the White River, Rochester, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Degnan, James

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ROCHTH00210034 on Town Highway 21 crossing the White River, Rochester, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, obtained from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D.The site is in the Green Mountain section of the New England physiographic province in central Vermont. The 74.8-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is suburban on the upstream and downstream left overbanks, though brush prevails along the immediate banks. On the upstream and downstream right overbanks, the surface cover is pasture with brush and trees along the immediate banks.In the study area, the White River has an incised, straight channel with a slope of approximately 0.002 ft/ft, an average channel top width of 102 ft and an average bank height of 5 ft. The channel bed material ranges from sand to cobble with a median grain size (D50) of 74.4 mm (0.244 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 23, 1996, indicated that the reach was stable.The Town Highway 21 crossing of the White River is a 72-ft-long, two-lane bridge consisting of 70-foot steel stringer span (Vermont Agency of Transportation, written communication, March 22, 1995). The opening length of the structure parallel to the bridge face is 67.0 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 15 degrees to the opening while the opening-skew-to-roadway is zero degrees.Channel scour, 1.5 ft deeper than the mean thalweg depth was observed along the left abutment and wingwalls during the Level I assessment. Scour countermeasures at the site includes type-1 stone fill (less than 12 inches diameter) along the upstream left bank and the upstream and downstream left road embankments, type-2 (less than 36 inches diameter) along the upstream end of the upstream left wingwall and downstream left bank, and type-3 (less than 48 inches diameter) along the downstream end of the downstream left wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). In addition, the incipient roadway-overtopping discharge is analyzed since it has the potential of being the worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.Contraction scour for all modelled discharges was zero. Left abutment scour ranged from 6.8 to 21.2 ft. Right abutment scour ranged from 13.9 to 18.4 ft. The worst-case abutment scour occurred at the 500-year discharge at the left and right abutments. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  3. Level II scour analysis for Bridge 29 (ROYATH00920029) on Town Highway 92, crossing the First Branch White River, Royalton, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Hammond, Robert E.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ROYATH00920029 on Town Highway 92 crossing the First Branch White River, Royalton, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in central Vermont. The 101-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture upstream and downstream of the bridge. In the study area, the First Branch White River has an incised, sinuous channel with a slope of approximately 0.001 ft/ft, an average channel top width of 81 ft and an average bank height of 9 ft. The channel bed material ranges from sand to bedrock with a median grain size (D50) of 1.18 mm (0.00347 ft). The geomorphic assessment at the time of the Level I site visit on July 23, 1996 and Level II site visit on June 2, 1995, indicated that the reach was stable. The Town Highway 92 crossing of the First Branch White River is a 59-ft-long, one-lane bridge consisting of a 57-foot steel-stringer span (Vermont Agency of Transportation, written communication, March 23, 1995). The opening length of the structure parallel to the bridge face is 52.2 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 20 degrees to the opening while the opening-skew-to-roadway is zero degrees. A scour hole 4.0 ft deeper than the mean thalweg depth was observed in the upstream channel during the Level I assessment. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the upstream left and right wingwalls, the left abutment and downstream left wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 4.1 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge, which was less than the 100-year discharge. Left abutment scour ranged from 12.9 to 15.4 ft, where the worst-case abutment scour occurred at the 500-year discharge. Right abutment scour ranged from 14.5 to 15.0 ft, where the worst-case abutment scour occurred at the 100-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  4. Level II scour analysis for Bridge 47 (PLYMTH00540047) on Town Highway 54, crossing Pinney Hollow Brook, Plymouth, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Weber, Matthew A.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure PLYMTH00540047 on Town Highway 54 crossing Pinney Hollow Brook, Plymouth, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gathered from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Green Mountain section of the New England physiographic province in south-central Vermont. The 7.9-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture upstream and downstream of the bridge while the immediate banks have dense woody vegetation. In the study area, Pinney Hollow Brook has an incised, straight channel with a slope of approximately 0.01 ft/ft, an average channel top width of 57 ft and an average bank height of 7 ft. The channel bed material ranges from sand to cobbles with a median grain size (D50) of 45.7 mm (0.150 ft). The geomorphic assessment at the time of the Level I and Level II site visit on March 30, 1995 and Level II site visit on October 2, 1995, indicated that the reach was stable. The Town Highway 54 crossing of Pinney Hollow Brook is a 30-ft-long, two-lane bridge consisting of a 27-foot steel-stringer span (Vermont Agency of Transportation, written communication, March 22, 1995). The opening length of the structure parallel to the bridge face is 25.7 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is not skewed to the opening and the opening-skew-to-roadway is zero degrees. Scour protection measures at the site included type-1 stone fill (less than 12 inches diameter) along the upstream left wingwall, the upstream right wingwall and the downstream end of the downstream left wingwall. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 2.0 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge, which was less than the 100-year discharge. Left abutment scour ranged from 3.4 to 6.7 ft. The worst-case left abutment scour occurred at the 500-year discharge. Right abutment scour ranged from 8.9 to 9.6 ft. The worst-case right abutment scour occurred at the 100-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  5. Level II scour analysis for Bridge 28 (ROCHTH00370028) on Town Highway 37, crossing Brandon Brook, Rochester, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Weber, Matthew A.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ROCHTH00370028 on Town Highway 37 crossing Brandon Brook, Rochester, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from VTAOT files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Green Mountain section of the New England physiographic province in central Vermont. The 8.0-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture on the upstream left overbank although the immediate banks have dense woody vegetation. The upstream right overbank and downstream left and right overbanks are forested. In the study area, the Brandon Brook has an incised, sinuous channel with a slope of approximately 0.01 ft/ft, an average channel top width of 44 ft and an average bank height of 7 ft. The channel bed material ranges from gravel to cobbles with a median grain size (D50) of 84.2 mm (0.276 ft). The geomorphic assessment at the time of the Level I site visit on April 12, 1995 and Level II site visit on July 8, 1996, indicated that the reach was stable. The Town Highway 37 crossing of the Brandon Brook is a 33-ft-long, one-lane bridge consisting of a 31-foot timber-stringer span (Vermont Agency of Transportation, written communication, March 22, 1995). The opening length of the structure parallel to the bridge face is 29.6 ft. The bridge is supported by vertical, timber log cribbing abutments with wingwalls. The channel is skewed approximately 5 degrees to the opening while the computed opening-skew-to-roadway is zero degrees. A scour hole 1.0 ft deeper than the mean thalweg depth was observed along the upstream left wingwall and the left abutment during the Level I assessment. The only scour protection measure at the site was type-5 protection, an artificial levee, extending along the upstream right bank to the end of the upstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was zero ft. Left abutment scour ranged from 7.1 to 9.9 ft where the worst-case scour occurred at the 500-year discharge. Right abutment scour ranged from 4.4 to 5.1 ft where the worst-case scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results.” Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein

  6. Level II scour analysis for Bridge 44 (LINCTH00330044) on Town Highway 33, crossing the New Haven River, Lincoln, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.; Wild, Emily C.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure LINCTH00330044 on Town Highway 33 crossing the New Haven River, Lincoln, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D.The site is in the Green Mountain section of the New England physiographic province in west-central Vermont. The 6.3-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest.In the study area, the New Haven River has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 56 ft and an average bank height of 6 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 101.9 mm (0.334 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 10, 1996, indicated that the reach was stable.The Town Highway 33 crossing of the New Haven River is a 33-ft-long, one-lane bridge consisting of one 31-foot timber-beam span (Vermont Agency of Transportation, written communication, December 14, 1995). The opening length of the structure parallel to the bridge face is 29.3 ft. The bridge is supported by vertical, wood-beam crib abutments with wingwalls. The channel is skewed approximately 25 degrees to the opening while the opening-skew-to-roadway is zero degrees.A scour hole 1.0 ft deeper than the mean thalweg depth was observed along the right abutment during the Level I assessment. The scour protection measures at the site included type-1 stone fill (less than 12 inches diameter) at the downstream end of the downstream left wingwall and along the downstream right bank, type-2 stone fill (less than 36 inches diameter) along the upstream right bank and type-3 stone fill (less than 48 inches diameter) at the upstream end of the upstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.Contraction scour for all modelled flows ranged from 0.0 to 1.3 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge, which was less than the 100-year discharge. Abutment scour ranged from 9.4 to 12.6 ft. The worst-case abutment scour occurred at the 100-year discharge for the left abutment and at the incipient overtopping discharge for the right abutment. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  7. Level II scour analysis for Bridge 37 (DUXBTH00120037) on Town Highway 12, crossing Ridley Brook, Duxbury, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Ivanhoff, Michael A.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure DUXBTH00120037 on Town Highway 12 crossing Ridley Brook, Duxbury, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in north central Vermont. The 10.1-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest upstream and downstream of the bridge. In the study area, Ridley Brook has an incised, straight channel with a slope of approximately 0.04 ft/ft, an average channel top width of 67 ft and an average bank height of 9 ft. The channel bed material ranges from gravel to boulders with a median grain size (D50) of 123 mm (0.404 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 1, 1996, indicated that the reach was stable. The Town Highway 12 crossing of Ridley Brook is a 33-ft-long, two-lane bridge consisting of five 30-ft steel rolled beams (Vermont Agency of Transportation, written communication, October 13, 1995). The opening length of the structure parallel to the bridge face is 30 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 50 degrees to the opening while the measured opening-skew-to-roadway is 20 degrees. A scour hole 2 ft deeper than the mean thalweg depth was observed along the right abutment and downstream right wingwall during the Level I assessment. Scour countermeasures at the site include type-2 stone fill (less than 3 feet diameter) along the upstream and downstream left road embankments, and type-3 stone fill (less than 4 feet diameter) along the upstream right bank and upstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.6 to 1.7 ft. The worst-case contraction scour occurred at the 500-year discharge. Left abutment scour ranged from 5.0 to 8.3 ft, with the worst-case occurring at the incipient-overtopping discharge. Right abutment scour ranged from 13.1 to 16.7 ft, with the worst-case occurring at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  8. Level II scour analysis for Bridge 8 (ANDOTH00010008) on Town Highway 1, crossing Andover Branch, Andover, Vermont

    USGS Publications Warehouse

    Flynn, Robert H.; Wild, Emily C.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ANDOTH00010008 on Town Highway 1 crossing the Andover Branch, Andover , Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D.The site is in the Green Mountain section of the New England physiographic province in south-central Vermont. The 5.30-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover along the immediate banks, both upstream and downstream of the bridge, is grass while farther upstream and downstream, the surface cover is primarily forest.In the study area, the Andover Branch has an incised, straight channel with a slope of approximately 0.01 ft/ft, an average channel top width of 35 ft and an average bank height of 3 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 63.6 mm (0.209 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 27, 1996, indicated that the reach was stable.The Town Highway 1 crossing of the Andover Branch is a 54-ft-long, two-lane bridge consisting of one 51-foot steel-beam span (Vermont Agency of Transportation, written communication, March 28, 1995). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 45 degrees to the opening while the opening-skew-to-roadway is 30 degrees.A scour hole 0.7 ft deeper than the mean thalweg depth was observed approximately 52 feet downstream of the downstream face of the bridge during the Level I assessment. Scour countermeasures at the site include type-2 stone fill (less than 36 inches diameter) along the entire base length of the left and right abutments and along the left bank from 65 ft to 89 ft upstream. Type-1 stone fill was found along the right bank from the bridge to 47 ft upstream and along the left bank from 40 ft to 65 ft upstream. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E.Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.Contraction scour for all modelled flows ranged from 0.0 to 0.1 ft. The worst case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 5.0 to 8.1 ft along the left abutment and from 2.1 to 4.6 ft along the right abutment. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  9. Level II scour analysis for Bridge 46 (CHESVT00110046) on Vermont State Route 11, crossing the Middle Branch Williams River, Chester, Vermont

    USGS Publications Warehouse

    Wild, Emily C.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure CHESVT00110046 on State Route 11 crossing the Middle Branch Williams River, Chester, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D.The site is in the Green Mountain and New England Upland sections of the New England physiographic province in southeastern Vermont. The 28.0-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forested on the upstream left and downstream right overbanks. The upstream right and downstream left overbanks are pasture while the immediate banks have dense woody vegetation.In the study area, the the Middle Branch Williams River has an incised, sinuous channel with a slope of approximately 0.013 ft/ft, an average channel top width of 81 ft and an average bank height of 11 ft. The channel bed material ranges from gravel to bedrock with a median grain size (D50) of 70.7 mm (0.232 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 12, 1996, indicated that the reach was stable.The State Route 11 crossing of the Middle Branch Williams River is a 118-ft-long, two-lane steel stringer type bridge consisting of a 114-foot steel plate deck (Vermont Agency of Transportation, written communication, March 29, 1995). The opening length of the structure parallel to the bridge face is 109 ft.The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 45 degrees to the opening while the opening-skew-to-roadway is 50 degrees.A scour hole 2 ft deeper than the mean thalweg depth was observed 128 feet downstream during the Level I assessment. Type-1 (less than 1 foot) stone fill protects the downstream right wingwall. Type-2 (less than 3 ft diameter) stone fill protects the upstream right wingwall, the left and right abutments, the upstream left and right road embankments. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.There was no computed contraction scour for any modelled flows. Abutment scour ranged from 7.0 to 10.3 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  10. Level II scour analysis for Bridge 8 (NEWFTH00010008) on Town Highway 1, crossing Wardsboro Brook, Newfane, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Degnan, James

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure NEWFTH00010008 on Town Highway 1 crossing Wardsboro Brook, Newfane, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (Federal Highway Administration, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the New England Upland section of the New England physiographic province in southestern Vermont. The 6.91-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest on the upstream right overbank and downstream left and right overbanks. The surface cover on the upstream left overbank is pasture. In the study area, Wardsboro Brook has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 63 ft and an average bank height of 9 ft. The channel bed material ranges from gravel to boulders with a median grain size (D50) of 95.4 mm (0.313 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 21, 1996, indicated that the reach was stable. The Town Highway 1 crossing of the Wardsboro Brook is a 32-ft-long, two-lane bridge consisting of a 26-foot concrete tee-beam span (Vermont Agency of Transportation, written communication, April 6, 1995). The opening length of the structure parallel to the bridge face is 26.7 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 45 degrees to the computed opening while the openingskew-to-roadway is 45 degrees. A scour hole 1.0 ft deeper than the mean thalweg depth was observed along the right abutment during the Level I assessment. Scour protection measures at the site included type-1 stone fill (less than 12 inches diameter) along the upstream right bank, and type-2 stone fill (less than 36 inches diameter) along the upstream left bank and the upstream ends of the upstream left and right wingwalls. A stone wall extends along the downstream right bank from the end of the downstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.1 to 3.9 ft. The worst-case contraction scour occurred at the 500-year discharge. Left abutment scour ranged from 11.1 to 12.9 ft. Right abutment scour ranged from 4.3 to 4.8 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  11. Level II scour analysis for Bridge 67 (MTHOTH00120067) on Town Highway 12, crossing Freeman Brook, Mount Holly, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Severance, Timothy

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure MTHOTH00120067 on Town Highway 12 crossing Freeman Brook, Mount Holly, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Green Mountain section of the New England physiographic province in south-central Vermont. The 11.4-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forested. In the study area, Freeman Brook has an incised, sinuous channel with a slope of approximately 0.01 ft/ft, an average channel top width of 51 ft and an average bank height of 6 ft. The channel bed material ranges from sand to boulders with a median grain size (D50) of 55.7 mm (0.183 ft). The geomorphic assessment at the time of the Level I and Level II site visit on October 5, 1995, indicated that the reach was stable. The Town Highway 12 crossing of Freeman Brook is a 34-ft-long, two-lane bridge consisting of a 30-foot prestressed concrete-slab span (Vermont Agency of Transportation, written communication, March 15, 1995). The opening length of the structure parallel to the bridge face is 29.5 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 50 degrees to the opening while the opening-skew-to-roadway is 15 degrees. Along the upstream right wingwall, the right abutment and the downstream right wingwall, a scour hole approximately 1.0 to 2.0 ft deeper than the mean thalweg depth was observed during the Level I assessment. Scour protection measures at the site included type-1 stone fill (less than 12 inches diameter) along the downstream end of the downstream right wingwall; type-2 stone fill (less than 36 inches diameter) along the upstream left wingwall, the left abutment, the downstream left wingwall and the upstream left and right banks; type- 3 stone fill (less than 48 inches diameter) along the downstream left and right banks; and type-4 stone fill (less than 60 inches diameter) along the upstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 2.6 to 3.9 ft. The worst-case contraction scour occurred at the 500-year discharge. Left abutment scour ranged from 7.9 to 10.0 ft. Right abutment scour ranged from 12.7 to 15.2 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  12. Level II scour analysis for Bridge 36 (STOWTH00430036) on Town Highway 43, crossing Miller Brook, Stowe, Vermont

    USGS Publications Warehouse

    Striker, Lora K.; Wild, Emily C.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure STOWTH00430036 on Town Highway 43 crossing the Miller Brook, Stowe, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in north central Vermont. The 5.5-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is predominantly forested. In the study area, the Miller Brook has an incised, sinuous channel with a slope of approximately 0.03 ft/ft, an average channel top width of 43 ft and an average bank height of 7 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 70.4 mm (0.231 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 15, 1996, indicated that the reach was stable. The Town Highway 43 crossing of the Miller Brook is a 24-ft-long, two-lane bridge consisting of one 21-foot steel-beam span (Vermont Agency of Transportation, written communication, October 13, 1995). The opening length of the structure parallel to the bridge face is 21.5 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 10 degrees to the opening and the computed opening-skew-to-roadway is also 10 degrees. The footing on the left abutment was exposed 2.5 ft and the footing on the right abutment was exposed 3.0 ft during the Level I assessment. Scour protection measures at the site were type-4 stone fill (less than 60 inches diameter) on the left and right bank upstream, type-3 stone fill (less than 48 inches diameter) along the entire base length of the upstream right wingwall, right abutment, and type-2 stone fill (less than 36 inches diameter) along the entire base length of the downstream right wingwall, and left and right banks downstream. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.9 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 3.1 to 6.5 ft. The worst-case abutment scour occurred at the 100-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  13. Level II scour analysis for Bridge 10 (CHESTH00030010) on Town Highway 3 (VT 35), crossing the South Branch of Williams River, Chester, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Hammond, Robert E.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure CHESTH00030010 on Town Highway 3 (VT 35) crossing the South Branch Williams River, Chester, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D.The site is in the New England Upland section of the New England physiographic province in southeastern Vermont. The 9.44-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest.In the study area, the South Branch Williams River has an incised, sinuous channel with a slope of approximately 0.03 ft/ft, an average channel top width of 67 ft and an average bank height of 5 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 69.0 mm (0.226 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 26-27, 1996, indicated that the reach was stable.The Town Highway 3 (VT 35) crossing of the South Branch Williams River is a 69-foot-long, two-lane bridge consisting of one 67-foot steel-stringer span with a concrete deck (Vermont Agency of Transportation, written communication, August 23, 1994). The opening length of the structure parallel to the bridge face is 64.5 ft. The bridge is supported by vertical, concrete abutments with spill-through embankments. The channel is skewed approximately 50 degrees to the opening while the opening-skew-to-roadway is 30 degrees.The scour protection (spill-through abutments) measured at the site was type-3 stone fill (less than 48 inches diameter) extending the entire base length and around the ends of the left and right abutments. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.Contraction scour for modelled flows ranged from 0.8 to 3.8 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge. Left abutment scour ranged from 13.3 to 14.9 ft. The worst-case scour at the left abutment occurred at the 500-year discharge. Right abutment scour ranged from 4.1 to 6.0 ft. The worst-case scour at the right abutment occurred at the incipient roadway-overtopping discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  14. Level II scour analysis for Bridge 38 (JERITH0020038) on Town Highway 20, crossing the Lee River, Jericho, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Degnan, James R.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure JERITH00200038 on Town Highway 20 crossing the Lee River, Jericho, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, obtained from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province and the Champlain section of the St. Lawrence physiographic province in northwestern Vermont. The 12.9-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover on the upstream and downstream right overbank is pasture while the immediate banks have dense woody vegetation. The surface cover on the upstream and downstream left overbank is forested. In the study area, the Lee River has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 89 ft and an average bank height of 14 ft. The channel bed material ranges from sand to boulder with a median grain size (D50) of 45.9 mm (0.151 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 2, 1996, indicated that the reach was stable. The Town Highway 20 crossing of the Lee River is a 49-ft-long, one-lane bridge consisting of a steel through truss span (Vermont Agency of Transportation, written communication, December 12, 1995). The opening length of the structure parallel to the bridge face is 44 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 10 degrees to the opening while the computed opening-skew-toroadway is 5 degrees. A scour hole 1 ft deeper than the mean thalweg depth was observed in the center of the channel during the Level I assessment. Scour countermeasures at the site include type-1 stone fill (less than 12 inches diameter) at the downstream left road embankment. Type-2 stone fill (less than 36 inches diameter) protects the upstream left wingwall, the upstream and downstream right wingwalls and the upstream end of the right abutment. Type-3 stone fill (less than 48 inches diameter) protects the left abutment. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was zero. Abutment scour ranged from 4.9 to 10.7 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  15. Level II scour analysis for Bridge 28 (STRATH00020028) on Town Highway 2, crossing the West Branch Ompompanoosuc River, Strafford, Vermont

    USGS Publications Warehouse

    Wild, Emily C.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure STRATH00020028 on Town Highway 2 crossing the West Branch Ompompanoosuc River, Strafford, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gathered from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the New England Upland section of the New England physiographic province in central Vermont. The 25.4-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture upstream and downstream of the bridge. In the study area, the West Branch Ompompanoosuc River has a sinuous channel with a slope of approximately 0.002 ft/ft, an average channel top width of 34 ft and an average bank height of 6 ft. The channel bed material ranges from silt and clay to cobbles with a median grain size (D50) of 20.4 mm (0.0669 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 24, 1996, indicated that the reach was laterally unstable, because of moderate fluvial erosion. The Town Highway 2 crossing of the West Branch Ompompanoosuc River is a 31-ft-long, twolane bridge consisting of a 26-foot concrete tee-beam span (Vermont Agency of Transportation, written communication, October 23, 1995). The opening length of the structure parallel to the bridge face is 24.6 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 45 degrees to the opening while the computed opening-skew-toroadway is 5 degrees. A scour hole 3.2 ft deeper than the mean thalweg depth was observed under the bridge along the right side of the channel during the Level I assessment. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the upstream right bank, the upstream right wingwall, the right abutment and the downstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 3.2 to 4.1 ft. The worst-case contraction scour occurred at the 500-year discharge. Left abutment scour ranged from 4.4 to 7.5 ft. Right abutment scour ranged from 7.2 to 10.1 ft.The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  16. Level II scour analysis for Bridge 36 (DUXBTH00040036) on Town Highway 4, crossing Crossett Brook, Duxbury, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Degnan, James R.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure DUXBTH00040036 on Town Highway 4 crossing the Crossett Brook, Duxbury, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D.The site is in the Green Mountain section of the New England physiographic province in north-central Vermont. The 4.9-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover on the upstream left overbank is pasture. The upstream and downstream right overbanks are forested. The downstream left overbank is brushland, while the immediate banks have dense woody vegetation.In the study area, the Crossett Brook has an incised, sinuous channel with a slope of approximately 0.006 ft/ft, an average channel top width of 55 ft and an average bank height of 9 ft. The channel bed material ranges from gravel to bedrock with a median grain size (D50) of 51.6 mm (0.169 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 1, 1996, indicated that the reach was stable.The Town Highway 4 crossing of the Crossett Brook is a 29-ft-long, two-lane bridge consisting of a 26-foot concrete slab span (Vermont Agency of Transportation, written communication, October 13, 1995). The opening length of the structure parallel to the bridge face is 26 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 35 degrees to the opening while the computed opening-skew-to-roadway is 5 degrees.A scour hole 1.5 ft deeper than the mean thalweg depth was observed along the upstream left wingwall and the right abutment during the Level I assessment. Scour countermeasures at the site includes type-2 stone fill (less than 36 inches diameter) at the upstream end of the upstream left and right wingwalls and the upstream left and right banks and road embankments. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.Contraction scour for all modelled flows ranged from 0.0 to 1.7 ft. The worst-case contraction scour occurred at the 500-year discharge. Left abutment scour ranged from 6.4 to 8.3 ft. Right abutment scour ranged from 6.0 to 7.0 ft. The worst-case left and right abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  17. Level II scour analysis for Bridge 27 (WSTOTH00070027) on Town Highway 7, crossing Jenny Coolidge Brook, Weston, Vermont

    USGS Publications Warehouse

    Wild, Emily C.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure WSTOTH00070027 on Town Highway 7 crossing Jenny Coolidge Brook, Weston, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Green Mountain section of the New England physiographic province in southwestern Vermont. The 2.9-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture downstream of the bridge while upstream of the bridge is forested. In the study area, the Jenny Coolidge Brook has an incised, sinuous channel with a slope of approximately 0.04 ft/ft, an average channel top width of 51 ft and an average bank height of 6 ft. The channel bed material ranges from sand to boulders with a median grain size (D50) of 122 mm (0.339 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 20, 1996, indicated that the reach was stable. The Town Highway 7 crossing of the Jenny Coolidge Brook is a 52-ft-long, two-lane bridge consisting of a 50-foot steel-beam span (Vermont Agency of Transportation, written communication, April 7, 1995). The opening length of the structure parallel to the bridge face is 49.2 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 5 degrees to the opening while the computed opening-skew-to-roadway is 15 degrees. The legs of the skeleton-type right abutment were exposed approximately 2 feet (vertically) and approximately 2 feet (horizontally) during the Level I assessment. Scour protection measures at the site include type-1 stone fill (less than 12 inches diameter) along the downstream right wingwall, and type-2 stone fill (less than 36 inches diameter) along the upstream banks, upstream left wingwall, left abutment, downstream left wingwall and downstream left bank. A stone wall levee extends along the downstream right bank. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was zero ft. Abutment scour ranged from 3.0 to 4.1 ft. The worst-case left abutment scour occurred at the 100-year discharge. The worst-case right abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particlesize distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  18. Level II scour analysis for Bridge 13 (LINCTH00010013) on Town Highway 1, crossing Cota Brook, Lincoln, Vermont

    USGS Publications Warehouse

    Wild, Emily C.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure LINCTH00010013 on Town Highway 1 crossing Cota Brook, Lincoln, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Green Mountain section of the New England physiographic province in west-central Vermont. The 3.0-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest along the upstream right bank and brushland along the upstream left bank. Downstream of the bridge, the surface cover is pasture along the left and right banks. In the study area, Cota Brook has an sinuous channel with a slope of approximately 0.01 ft/ ft, an average channel top width of 30 ft and an average bank height of 2 ft. The channel bed material ranges from sand to cobble with a median grain size (D50) of 34.7 mm (0.114 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 10, 1996, indicated that the reach was laterally unstable due to cut-banks and wide, vegetated point bars upstream and downstream of the bridge. The Town Highway 1 crossing of Cota Brook is a 38-ft-long, two-lane bridge consisting of a 36-foot steel-stringer span (Vermont Agency of Transportation, written communication, December 14, 1995). The opening length of the structure parallel to the bridge face is 34.4 ft. The bridge is supported by vertical, concrete abutments. The channel is skewed approximately 15 degrees to the opening while the opening-skew-to-roadway is zero degrees.A scour hole 2.0 ft deeper than the mean thalweg depth was observed along the upstream right bank during the Level I assessment. Along the right abutment, it is 0.25 ft deeper than the mean thalweg depth. Scour protection measures at the site included type-1 stone fill (less than 12 inches diameter) along the upstream right bank and type-2 stone fill (less than 36 inches diameter) along the left and right abutments and along the downstream left bank. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 1.7 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 9.1 to 11.3 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  19. Level II scour analysis for Bridge 63 (MTH0TH00120063) on Town Highway 12, crossing Russell Brook, Mount Holly, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Severance, Timothy

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure MTHOTH00120063 on Town Highway 12 crossing Russell Brook, Mount Holly, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Green Mountain section of the New England physiographic province in south-central Vermont. The 3.6-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest upstream and downstream of the bridge. In the study area, Russell Brook has an incised, sinuous channel with a slope of approximately 0.0263 ft/ft, an average channel top width of 29 ft and an average bank height of 3 ft. The channel bed material ranges from cobbles to boulders with a median grain size (D50) of 97.1 mm (0.318 ft). The geomorphic assessment at the time of the Level I and Level II site visit on October 4, 1995, indicated that the reach was stable. The Town Highway 12 crossing of Russell Brook is a 29-ft-long, one-lane bridge consisting of a 26-foot steel-stringer span (Vermont Agency of Transportation, written communication, March 21, 1995). The opening length of the structure parallel to the bridge face is 23.5 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 40 degrees to the opening while the computed opening-skew-to-roadway is 35 degrees. During the Level I assessment, it was observed that the upstream left wingwall footing was exposed 0.2 ft, in reference to the mean thalweg depth, and the upstream end of the left abutment was exposed 0.1 ft. The scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the upstream end of the upstream left wingwall. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.1 ft. The worst-case contraction scour occurred at the 100-year discharge. Left abutment scour ranged from 4.4 to 5.7 ft. Right abutment scour ranged from 11.3 to 12.2 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  20. Level II scour analysis for Bridge 13 (SHARTH00040013) on Town Highway 4, crossing Broad Brook, Sharon, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Weber, Matthew A.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure SHARTH00040013 on Town Highway 4 crossing Broad Brook, Sharon, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D.The site is in the New England Upland section of the New England physiographic province in central Vermont. The 16.6-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is brushland on the downstream left overbank and row crops on the right overbank, while the immediate banks have dense woody vegetation. Upstream of the bridge, the overbanks are forested.In the study area, Broad Brook has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 69 ft and an average bank height of 5 ft. The channel bed material ranges from sand to boulder with a median grain size (D50) of 112 mm (0.369 ft). The geomorphic assessment at the time of the Level I site visit on April 11, 1995 and Level II site visit on July 23, 1996, indicated that the reach was stable.The Town Highway 4 crossing of Broad Brook is a 34-ft-long, two-lane bridge consisting of one 31-foot concrete tee beam span (Vermont Agency of Transportation, written communication, March 23, 1995). The opening length of the structure parallel to the bridge face is 30.1 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 10 degrees to the opening while the opening-skew-to-roadway is 15 degrees.A scour hole 2.0 ft deeper than the mean thalweg depth was observed along the upstream end of the right abutment. At the downstream end of the left abutment, a 1.0 foot scour hole was observed . Scour countermeasures at the site include type-2 stone fill (less than 3 feet diameter) at each road embankment. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.Contraction scour for all modelled flows ranged from 0.7 to 1.8 ft. The worst-case contraction scour occurred at the 500-year discharge. Left abutment scour ranged from 5.6 to 9.4 ft. The worst case left abutment scour occurred at the 500-year discharge. Right abutment scour ranged from 19.0 to 19.8 ft. The worst-case right abutment scour occurred at the incipient-overtopping discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  1. Level II scour analysis for Bridge 51 (JERITH00590051) on Town Highway 59, crossing The Creek, Jericho, Vermont

    USGS Publications Warehouse

    Wild, Emily C.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure JERITH00590051 on Town Highway 59 crossing The Creek, Jericho, Vermont (figures 1– 8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (Federal Highway Administration, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Green Mountain section of the New England physiographic province and the Champlain section of the St. Lawrence physiographic province in northwestern Vermont. The 10.9-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture on the left and right overbanks, upstream and downstream of the bridge while the immediate banks have dense woody vegetation. In the study area, The Creek has a sinuous channel with a slope of approximately 0.004 ft/ft, an average channel top width of 45 ft and an average bank height of 6 ft. The channel bed material ranges from silt to cobble with a median grain size (D50) of 58.6 mm (0.192 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 3, 1996, indicated that the reach was stable. The Town Highway 59 crossing of The Creek is a 33-ft-long, two-lane bridge consisting of a 28-foot steel-stringer span (Vermont Agency of Transportation, written communication, December 11, 1995). The opening length of the structure parallel to the bridge face is 26 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 10 degrees to the opening while the computed opening-skew-toroadway is 5 degrees.A scour hole 3 ft deeper than the mean thalweg depth was observed along the right abutment during the Level I assessment. Scour countermeasures at the site included type-1 stone fill (less than 12 inches diameter) at the left and right upstream road embankments. Type-2 stone fill (less than 36 inches diameter) was along the upstream right bank and along the upstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was zero ft. Left abutment scour ranged from 2.4 to 3.2 ft. Right abutment scour ranged from 4.1 to 4.5 ft.The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  2. Level II scour analysis for Bridge 45b (BRIDTH00040045b) on Town Highway 4, crossing an unnamed Dailey Hollow Branch Tributary, Bridgewater, Vermont

    USGS Publications Warehouse

    Boehmler, Erick M.

    1996-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure BRIDTH0004045B on town highway 4 crossing an unnamed Dailey Hollow Branch Tributary, Bridgewater, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in central Vermont. The 2.47-mi2 drainage area is in a predominantly rural and forested basin. Surface cover in the vicinity of the study site is variable. A gravel road is adjacent to the left bank with the immediate upstream left bank covered by grass and the immediate downstream left bank covered by shrubs and brush. The upstream right bank is densely forested; the downstream right overbank is covered by grass with trees and brush on the immediate channel bank. In the study area, this unnamed Dailey Hollow Branch Tributary has an incised channel with a slope of approximately 0.04 ft/ft, an average channel top width of 29 ft and an average channel depth of 4 ft. The predominant channel bed material is gravel with a median grain size (D50) of 47.0 mm (0.154 ft). The geomorphic assessment at the time of the Level I and Level II site visit on November 15, 1994, indicated that the reach was stable. The town highway 4 crossing of the unnamed Dailey Hollow Branch Tributary is a 62-ft-long, corrugated steel multi-plate arch structure. It is supported by concrete footings leaving natural stream bed exposed (Vermont Agency of Transportation, written communication, January, 1996). The road embankments are protected by stone fill, however, the size is unknown due to sand and grass covering the fill except for the upstream left embankment which has type-2 stone fill (less than 36 inches diameter). The downstream left bank is protected by type-3 stone fill (less than 48 inches diameter) extending 25 feet downstream of the culvert. The channel approach to the culvert has a mild s-curve bend with the opening skewed ten degrees to flow. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1993). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 1.1 to 1.8 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 7.7 to 11.7 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1993, p. 48). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  3. Physical and vegetative characteristics of a relocated stream reach, constructed wetland, and riparian buffer, Upper Saucon Township, Lehigh County, Pennsylvania, 2000-04

    USGS Publications Warehouse

    Chaplin, Jeffrey J.; White, Kirk E.; Loper, Connie A.

    2006-01-01

    The U.S. Geological Survey, in cooperation with the Pennsylvania Department of Transportation, Engineering District 5-0, investigated physical and vegetative changes within a relocated stream reach, constructed wetland, and riparian buffer from September 2000 to October 2004. This report presents an evaluation of data collected using methods from multiple sources that have been adapted into a consistent approach. This approach is intended to satisfy a need for consistent collection of different types of data with the goal of transferring technology and findings to similar projects. Survey data indicate that adjustment of the upstream part of the relocated stream reach slowed over the monitoring period, but the downstream channel remains unstable as evidenced by excessive deposition. Upstream migration of a nick point has slowed or stopped altogether as of the 2003 assessment when this feature came in contact with the upstream-most part of the channel that is lined with riprap. Documented streambed erosion in the upstream cross sections, along with deposition downstream, has resulted in an overall decrease in slope of the stream channel over the monitoring period. Most streambed erosion took place prior to the 2002 assessment when annual mean streamflows were less than those in the final 2 years of monitoring. An abundance of fine sediment dominates the substrate of the relocated channel. Annual fluctuations of large particles within each cross section demonstrates the capacity of the relocated channel to transport the entire range of sediment. The substrate within the 0.28-acre constructed wetland (a mixture of soil from an off-site naturally occurring wetland and woodchips) supported a hydrophytic-vegetation community throughout the investigation. Eleocharis obtusa (spike rush), an obligate-wetland herb, was the most prevalent species, having a maximum areal cover of 90 percent in fall 2001 and a minimum of 23 percent in fall 2004. Drought-like conditions in water year 2002 (cumulative precipitation was 28.11 inches) allowed species like Panicum dichotomiflorum (witch grass), Salix sp. (willow), Leersia oryzoides (rice cutgrass), and Echinocloa crusgalli (barnyard grass) to become established by fall 2002. Above-average precipitation in water years 2003 and 2004 (58.55 and 53.17 inches, respectively) coincided with increased areal cover by E. obtusa in fall 2003 (56 percent) and decreased areal cover in fall 2004 (23 percent). Pond-like conditions that probably persisted throughout the 2004 growing season favored aquatic species like Alisma subcordatum (water plantain) to the detriment of many emergent species, including E. obtusa. Despite the pond-like conditions, L. oryzoides, an obligate-wetland grass, increased in areal cover (from 12 to 34 percent) between the 2003 and 2004 growing seasons because it was established in the higher elevations and the peripheral areas of the constructed wetland that were less prone to persistent inundation. Canopy development by trees and shrubs in the riparian buffer was initially (fall 2000) poor (39.7 percent), resulting in more available sunlight for the herbaceous understory than in any other growing season. As a result, areal cover of herbaceous species and trees and shrubs less than 1-meter tall was 108 percent in fall 2000 with Lolium perenne (perennial rye), Polygonum persicaria (lady's thumb), and Setaria faberi (foxtail) collectively contributing nearly half the cover (59.2 percent). Because of increases in canopy cover by trees and shrubs (39.7 percent in fall 2000 to 127 percent in fall 2004), herbaceous cover decreased to 76 percent by the fall of 2001 and varied between 72 and 77 percent for the rest of the study period. Tree density in the riparian buffer ranged from 3,078 and 4,130 plants per acre (fall 2000 and 2003, respectively) over the study period but essentially remained constant after fall 2001; computations reported each fall between fall 2001 and fall 2004 are within 10 percent of one another. When the study ended in fall 2004, Acer negundo (box elder) and Fraxinus pennsylvanica (green ash) were the most populous tree species (1,526 and 1,084 plants per acre, respectively) followed by Quercus bicolor (swamp white oak; 720 plants per acre). A. negundo, F. pennsylvanica, and Q. bicolor also contributed the greatest areal cover in fall 2004 (31.2, 24.0, and 18.5 percent,respectively). 

  4. Level II scour analysis for Bridge 11R (ROCKTH0001011R) on Town Highway 1 (VT 121 & FAS 125), crossing the Saxtons River, Rockingham, Vermont

    USGS Publications Warehouse

    Boehmler, Erick M.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ROCKTH0001011R on Town Highway 1 crossing the Saxtons River, Rockingham, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in southeastern Vermont. The 68.3-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover consists of houses, short grass, and scattered trees except along the immediate river banks, which are tree covered. In the study area, the Saxtons River has a sinuous channel with a slope of approximately 0.005 ft/ft, an average channel top width of 121 ft and an average bank height of 8 ft. The predominant channel bed materials are gravel and cobbles with a median grain size (D50) of 109 mm (0.359 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 3, 1996, indicated that the reach was laterally unstable. Lateral instability was evident with respect to a cut-bank on the left bank upstream with slip failure of bank material. Furthermore, there is a wide point bar along the right bank upstream opposite the cut-bank. The Town Highway 1 crossing of the Saxtons River is a 184-ft-long, two-lane bridge consisting of three steel-beam spans (Vermont Agency of Transportation, written communication, March 30, 1995). The bridge is supported by vertical, concrete, skeletal-style abutment walls with spill-through embankments adjacent to each wall. The channel is skewed approximately 35 degrees to the opening while the opening-skew-to-roadway is 30 degrees. The only scour protection measure at the site was type-3 stone fill (less than 48 inches diameter) on the spill-through embankments. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. There was no computed contraction scour for all modelled flows at this site. Abutment scour ranged from 9.0 to 13.4 feet. The worst-case abutment scour occurred at the 500-year discharge for the left abutment. There are two piers for which computed pier scour ranged from 9.0 to 18.4 feet. The left and right piers in this report are presented as pier 1 and pier 2, respectively. The worst-case pier scour occurred at pier 2 for the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  5. Level II scour analysis for Bridge 12 (SUNDFLR0030012) on Forest Land Road 3, crossing Roaring Branch Brook, Sunderland, Vermont

    USGS Publications Warehouse

    Flynn, Robert H.; Medalie, Laura

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure SUNDFLR0030012 on Forest Land Road (FLR) 3 (FAS 114) crossing Roaring Branch Brook, Sunderland, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in southwestern Vermont. The 4.93-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is dense forest along the left bank and primarily shrubs and trees along the right bank, both upstream and downstream of the bridge. In the study area, Roaring Branch Brook has an incised, sinuous channel with a slope of approximately 0.01 ft/ft, an average channel top width of 33 ft and an average bank height of 4 ft. The channel bed material ranges from cobble to bedrock with a median grain size (D50) of 139 mm (0.457 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 30, 1996, indicated that the reach was stable. Forest Land Road 3 (FAS 114) crossing of Roaring Branch Brook is a 37-ft-long, two-lane bridge consisting of one 35-foot steel-beam span (Vermont Agency of Transportation, written communication, December 14, 1995). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 30 degrees to the opening while the opening-skew-to-roadway is 15 degrees. The scour protection measures at the site included type-3 stone fill (less than 48 inches diameter) along the left and right abutments, along the upstream left and downstream right wing walls and along the downstream right bank. Type-4 (less than 60 inches diameter) stone fill was found along the upstream right and downstream left wingwalls and along the downstream left bank. Type-2 (less than 36 inches diameter) stone fill scour protection was found along the upstream left and right banks. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was calculated to be 0.0 ft. Abutment scour ranged from 4.3 to 10.4 ft. The worst-case abutment scour occurred at the 500-year discharge along the right abutment. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  6. Level II scour analysis for Bridge 7H (HUNTTH0001007H) on Town Highway 1, crossing Cobb Brook, Huntington, Vermont

    USGS Publications Warehouse

    Wild, Emily C.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure HUNTTH001007H on Town Highway 1 crossing the Cobb Brook, Huntington, Vermont (figures 1–10). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D.In August 1976, Hurricane Belle caused flooding at this site which resulted in road and bridge damage (figures 7-8). This was approximately a 25-year flood event (U.S. Department of Housing and Urban Development, 1978). The site is in the Green Mountain section of the New England physiographic province in central Vermont. The 4.20-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest upstream of the bridge. Downstream of the bridge is brushland and pasture.In the study area, the Cobb Brook has an incised, straight channel with a slope of approximately 0.03 ft/ft, an average channel top width of 43 ft and an average bank height of 6 ft. The channel bed material ranges from sand to boulders with a median grain size (D50) of 65.5 mm (0.215 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 24, 1996, indicated that the reach was stable. The Town Highway 1 crossing of the Cobb Brook is a 23-ft-long, two-lane bridge consisting of one 20-foot concrete slab span (Vermont Agency of Transportation, written communication, June 21, 1996). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 15 degrees to the opening while the opening-skew-to-roadway is zero degrees.A scour hole 2.8 ft deeper than the mean thalweg depth was observed along the left abutment during the Level I assessment. Protection measures at the site include type-1 stone fill (less than 12 inches diameter) at the downstream right wingwall, type-2 stone fill (less than 36 inches diameter) at the upstream right wingwall and the downstream end of the downstream left wingwall, and type-3 stone fill (less than 48 inches diameter) at the upstream left wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.Contraction scour for all modelled flows ranged from 0.2 to 1.3 ft. The worst-case contraction scour occurred at the incipient-overtopping discharge. Abutment scour ranged from 4.0 to 8.7 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 10. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  7. Level II scour analysis for Bridge 29 (HUNTTH00290029) on Town Highway 29, crossing Cobb Brook, Huntington, Vermont

    USGS Publications Warehouse

    Flynn, Robert H.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure HUNTTH00290029 on Town Highway 29 crossing Cobb Brook, Huntington, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in northwestern Vermont. The 4.16-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest upstream and downstream of the bridge. In the study area, Cobb Brook has an incised, straight channel with a slope of approximately 0.024 ft/ft, an average channel top width of 53 ft and an average bank height of 4 ft. The channel bed material ranges from gravel to bedrock with a median grain size (D50) of 112.0 mm (0.367 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 25, 1996, indicated that the reach was stable. The Town Highway 29 crossing of Cobb Brook is a 36-ft-long, one-lane bridge consisting of one 30-foot steel-beam span (Vermont Agency of Transportation, written communication, December 11, 1995) and a wooden deck. The opening length of the structure parallel to the bridge face is 27 ft.The bridge is supported by vertical, concrete abutments. The channel is skewed approximately 25 degrees to the opening while the opening-skew-to-roadway was measured to be 20 degrees. VTAOT records indicate an opening-skew-to-roadway of zero degrees. A scour hole 1.5 ft deeper than the mean thalweg depth was observed extending from 12 ft upstream of the upstream end of the left abutment to 10 ft under the bridge in the center of the channel during the Level I assessment. Another scour hole approximately 1.2 ft deeper than the mean thalweg depth was observed along the downstream end of the right abutment during the Level I assessment. The scour protection measures at the site included type-2 stone fill (less than 36 inches diameter) along the upstream end of the right abutment and type-3 stone fill (less than 48 inches diameter) along the upstream end of the upstream left retaining wall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was computed to be zero ft. Abutment scour ranged from 9.9 to 12.5 ft along the left abutment and from 6.2 to 8.6 ft along the right abutment. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  8. Level II scour analysis for Bridge 34 (CORITH0050034) on Town Highway 50, crossing the South Branch Waits River, Corinth, Vermont

    USGS Publications Warehouse

    Ivanoff, Michael A.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure CORITH00500034 on Town Highway 50 crossing the South Branch Waits River, Corinth, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in central Vermont. The 35.9-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture upstream and downstream of the bridge while the immediate banks have dense woody vegetation. In the study area, the South Branch Waits River has an incised, meandering channel with a slope of approximately 0.005 ft/ft, an average channel top width of 63 ft and an average bank height of 6 ft. The channel bed material ranges from sand to cobble with a median grain size (D50) of 23.7 mm (0.078 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 5, 1995, indicated that the reach was stable. The Town Highway 50 crossing of the South Branch Waits River is a 56-ft-long, one-lane bridge consisting of one 54-foot steel thru-truss span (Vermont Agency of Transportation, written communication, March 24, 1995). The opening length of the structure parallel to the bridge face is 51.5 ft.The bridge is supported by vertical, concrete abutments with no wingwalls. Stone fill and bank material in front of the abutments create spill-through embankments. The channel is skewed approximately 30 degrees to the opening while the opening-skew-to-roadway is 15 degrees. A scour hole 2.5 ft deeper than the mean thalweg depth was observed along the left bank through the bridge during the Level I assessment. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the left and right banks extending from upstream to downstream through the bridge. The stone fill under the bridge creates spill-through embankments. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as other potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 3.0 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge, which was less than the 100-year discharge. Abutment scour ranged from 2.4 to 6.3 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich and HIRE equations (abutment scour) give “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  9. Level II scour analysis for Bridge 5 (DUMMVT00300005) on State Route 30, crossing Stickney Brook, Dummerston, Vermont

    USGS Publications Warehouse

    Ivanoff, Michael A.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure DUMMVT00300005 on State Route 30 crossing Stickney Brook, Dummerston, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in southeastern Vermont. The 6.31-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest and brush. In the study area, Stickney Brook has an incised, straight channel with a slope of approximately 0.04 ft/ft, an average channel top width of 80 ft and an average bank height of 7 ft. The channel bed material is predominantly cobble with a median grain size (D50) of 80.3 mm (0.264 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 12, 1996, indicated that the reach was aggrading. The State Route 30 crossing of Stickney Brook is a 84-ft-long, two-lane bridge consisting of one 82-foot steel-beam span (Vermont Agency of Transportation, written communication, March 30, 1995). The opening length of the structure parallel to the bridge face is 79.7 ft. The bridge is supported by vertical, concrete abutments with spill-through embankments. The channel is skewed approximately 5 degrees to the opening while the opening-skew-to-roadway is 0 degrees. A scour hole 0.5 ft deeper than the mean thalweg depth was observed along the toe of the right spill-through slope during the Level I assessment. The scour protection measures at the site were type-2 stone fill (less than 36 inches diameter) along the left and right bank under the bridge forming a spill-through slope and type-2 stone fill from approximately 20 ft to 64 ft upstream on the right bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.2 ft. The worst-case contraction scour occurred at the 100-year discharge. Left abutment scour ranged from 5.5 to 6.3 ft. Right abutment scour ranged from 2.0 to 3.8 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  10. Level II scour analysis for Bridge 41 (ROCKTH00390041) on Town Highway 39, crossing the Saxtons River, Rockingham, Vermont

    USGS Publications Warehouse

    Boehmler, Erick M.; Degnan, James R.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ROCKTH00390041 on Town Highway 39 crossing the Saxtons River, Rockingham, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in southeastern Vermont. The 57.4-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover consists of forest on the left bank and pasture with some trees on the right bank. In the study area, the Saxtons River has an sinuous channel with a slope of approximately 0.009 ft/ft, an average channel top width of 112 ft and an average bank height of 10 ft. The channel bed material ranges from sand to cobbles with a median grain size (D50) of 103 mm (0.339 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 15, 1996, indicated that the reach was laterally unstable. There are wide point bars, cut-banks with fallen trees, and areas of localized channel scour along the left bank, where there is bedrock exposure at the surface. The Town Highway 39 crossing of the Saxtons River is an 85-ft-long, one-lane bridge consisting of one 82-foot steel-beam span (Vermont Agency of Transportation, written communication, March 31, 1995). The bridge is supported by vertical, concrete abutments without wingwalls. The channel is skewed approximately 30 degrees to the opening while the opening-skew-to-roadway is zero degrees. A scour hole 3 ft deeper than the mean thalweg depth was observed during the Level I assessment along the left side of the channel under the bridge exposing the left abutment footing 5.5 feet. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) on the left banks upstream and downstream and the left abutment wall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 2.2 to 3.8 feet. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 21.4 to 23.2 feet and 26.2 to 32.4 feet at the left and right abutments respectively. The worst-case abutment scour occurred for the right abutment at the incipient overtopping discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Bedrock was exposed at the surface in some areas of the channel and potentially is located at a shallower depth than the scour depths indicated above. Nevertheless, scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  11. Level II scour analysis for Bridge 20 (GRAFTH00010020) on Town Highway 1, crossing the Saxtons River, Grafton Vermont

    USGS Publications Warehouse

    Boehmler, Erick M.; Burns, Ronda L.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure GRAFTH00010020 on Town Highway 1 crossing the Saxtons River, Grafton, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in southeastern Vermont. The 33.9-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest upstream of the bridge and shrub and brush downstream. In the study area, the Saxtons River has an incised, sinuous channel with a slope of approximately 0.01 ft/ft, an average channel top width of 97 ft and an average bank height of 2 ft. The predominant channel bed material is gravel with a median grain size (D50) of 58.6 mm (0.192 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 21, 1996, indicated that the reach was laterally unstable due to distinctive cut bank development on the upstream right bank and point bar development on the upstream left bank and downstream right bank. The Town Highway 1 crossing of the Saxtons River is a 191-ft-long, two-lane bridge consisting of three steel-beam spans (Vermont Agency of Transportation, written communication, March 29, 1995). The bridge is supported by vertical, concrete abutments with spill-through embankments and two piers. The channel is skewed approximately 40 degrees to the opening. The opening-skew-to-roadway is 45 degrees in the VTAOT records but measured 50 degrees from surveyed points. The scour protection measures at the site were type-1 stone fill (less than 12 inches diameter) on the left abutment, type-2 stone fill (less than 36 inches diameter) on the right abutment and downstream right bank, and a stone wall is noted on the left bank downstream. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.9 feet. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 8.0 to 14.9 feet. The worst-case abutment scour occurred at the 500-year discharge for the right abutment. There are two piers for which computed pier scour ranged from 8.7 to 26.0 feet. The left and right piers in this report are presented as pier 1 and pier 2 respectively. The worst-case pier scour occurred at pier 2 for the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  12. Level II scour analysis for Bridge 68 (NFIETH00960068) on Town Highway 96, crossing the Dog River, Northfield, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure NFIETH00960068 on Town Highway 96 crossing the Dog River, Northfield, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in central Vermont. The 30.7-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover on the left bank upstream and downstream is pasture while the immediate banks have dense woody vegetation. The right bank upstream is forested and the downstream right bank is pasture. Vermont state route 12A runs parallel to the river on the right bank. In the study area, the Dog River has an incised, straight channel with a slope of approximately 0.004 ft/ft, an average channel top width of 70 ft and an average bank height of 7 ft. The channel bed material ranges from sand to cobble with a median grain size (D50) of 47.9 mm (0.157 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 25, 1996, indicated that the reach was stable. The Town Highway 96 crossing of the Dog River is a 45-ft-long, one-lane bridge consisting of one 43-foot steel-beam span with a timber deck (Vermont Agency of Transportation, written communication, October 13, 1995). The opening length of the structure parallel to the bridge face is 41.5 ft.The bridge is supported by vertical, concrete abutments with wingwalls. The channel is not skewed to the opening and the opening-skew-to-roadway is zero degrees. Channel scour 0.5 ft deeper than the mean thalweg depth, was observed under the bridge during the Level I assessment. The scour protection measures at the site included type-1 stone fill (less than 12 inches diameter) along the left bank upstream and type-2 stone fill (less than 36 inches diameter) along the upstream and downstream right banks that extends partially in front of the right wingwalls. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.8 to 1.2 ft. The worst-case contraction scour occurred at the 100-year and 500-year discharges. Abutment scour ranged from 8.5 to 12.2 ft. The worst-case abutment scour occurred at the incipient roadway-overtopping discharge for the right abutment. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  13. Level II scour analysis for Bridge 34 (HUNTTH00210034) on Town Highway 21, crossing Brush Brook, Huntington, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.; Ivanoff, Michael A.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure HUNTTH00210034 on Town Highway 21 crossing Brush Brook, Huntington, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in central Vermont. The 6.23-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest. In the study area, Brush Brook has an incised, straight channel with a slope of approximately 0.03 ft/ft, an average channel top width of 43 ft and an average bank height of 4 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 90.0 mm (0.295 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 26, 1996, indicated that the reach was stable. The Town Highway 21 crossing of Brush Brook is a 28-ft-long, one-lane bridge consisting of one 26-foot steel-beam span with a timber deck (Vermont Agency of Transportation, written communication November 30, 1995). The opening length of the structure parallel to the bridge face is 25.4 ft. The bridge is supported by vertical, concrete abutments with a wingwall on the upstream right. The channel is skewed approximately 5 degrees to the opening and the computed opening-skew-to-roadway is 5 degrees. A tributary enters Brush Brook on the right bank immediately downstream of the bridge. At the confluence, the left bank of Brush Brook is eroded and there is a small void under the downstream end of the left abutment footing which is completely exposed. The right abutment footing is also exposed. The scour countermeasures at the site include type-2 stone fill (less than 36 inches diameter) along the upstream banks and in front of the right abutment and type-3 stone fill (less than 48 inches diameter) along the entire base length of the upstream right wingwall and along the downstream right bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.7 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge, which was less than the 100-year discharge. Abutment scour ranged from 6.9 to 10.9 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  14. Level II scour analysis for Bridge 40 (ANDOVT00110040) on State Route 11, crossing Lyman Brook, Andover, Vermont

    USGS Publications Warehouse

    Ivanoff, Michael A.; Burns, Ronda L.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ANDOVT00110040 on State Route 11 crossing Lyman Brook, Andover, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in south-central Vermont. The 4.18-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture while the immediate banks have dense woody vegetation. In the study area, Lyman Brook has an incised, straight channel with a slope of approximately 0.03 ft/ft, an average channel top width of 42 ft and an average bank height of 8 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 86.0 mm (0.282 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 9, 1996, indicated that the reach was stable. The State Route 11 crossing of Lyman Brook is a 28-ft-long, two-lane bridge consisting of one 27-foot concrete tee-beam span (Vermont Agency of Transportation, written communication, March 29, 1995). The opening length of the structure parallel to the bridge face is 24.8 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 0 degrees to the opening while the opening-skew-to-roadway is 30 degrees. The scour protection measures at the site included type-2 stone fill (less than 36 inches diameter) at the upstream end of the upstream right wingwall and the downstream ends of the downstream left and right wingwalls. There was also a stone wall along the top of the left bank from 36 to 76 feet upstream. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.7 ft. The worst-case contraction scour occurred at the incipient-overtopping discharge which was more than the 100-year discharge. Left abutment scour ranged from 1.2 to 7.5 ft. The worst-case left abutment scour occurred at the 500-year discharge. Right abutment scour ranged from 5.2 to 6.7 ft. The worst-case right abutment scour occurred at the 100-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  15. Level II scour analysis for Bridge 33 (CONCTH00580033) on Town Highway 58, crossing Miles Stream, Concord, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure CONCTH00580033 on Town Highway 58 crossing Miles Stream, Concord, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in northeastern Vermont. The 17.9-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture upstream of the bridge while the immediate banks have dense woody vegetation. Downstream of the bridge, the right bank is forested and the left bank has shrubs and brush. In the study area, Miles Stream has an incised, sinuous channel with a slope of approximately 0.01 ft/ft, an average channel top width of 91 ft and an average bank height of 7 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 61.6 mm (0.188 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 15, 1995, indicated that the reach was stable. The Town Highway 58 crossing of Miles Stream is a 44-ft-long, two-lane bridge consisting of one 39-foot steel-beam span (Vermont Agency of Transportation, written communication, March 24, 1995). The opening length of the structure parallel to the bridge face is 37.4 ft. The bridge is supported by vertical, concrete abutments with stone fill in front creating spillthrough embankments. The channel is skewed approximately 20 degrees to the opening while the opening-skew-to-roadway is zero degrees. The only scour countermeasure at the site was type-3 stone fill (less than 48 inches diameter) along the left and right banks upstream, in front of the abutments forming spill through embankments, and extending along the banks downstream. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 1.8 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 4.0 to 9.7 ft. The worst-case abutment scour occurred at the 500-year discharge for the right abutment and at the incipient roadway-overtopping discharge for the left abutment. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  16. Level II scour analysis for Bridge 17 (RIPTTH00180017) on Town Highway 18, crossing the South Branch Middlebury River, Ripton, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.; Medalie, Laura

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure RIPTTH00180017 on Town Highway 18 crossing the South Branch Middlebury River, Ripton, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in west-central Vermont. The 15.5-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest except on the upstream left bank where it is shrubs and brush. In the study area, the South Branch Middlebury River has an incised, sinuous channel with a slope of approximately 0.03 ft/ft, an average channel top width of 86 ft and an average bank height of 10 ft. The channel bed material ranges from gravel to boulders with a median grain size (D50) of 111 mm (0.364 ft). In addition, there is a bedrock outcrop across the channel downstream of the bridge. The geomorphic assessment at the time of the Level I and Level II site visit on June 10, 1996, indicated that the reach was stable. The Town Highway 18 crossing of the South Branch Middlebury River is a 61-ft-long, one-lane bridge consisting of one 58-foot steel-beam span (Vermont Agency of Transportation, written communication, November 30, 1995). The opening length of the structure parallel to the bridge face is 56.8 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 40 degrees to the opening while the computed opening-skew-to-roadway is 30. A scour hole 1.25 ft deeper than the mean thalweg depth was observed along the right abutment and the downstream right wingwall during the Level I assessment. The scour protection measures at the site include type-2 stone fill (less than 36 inches diameter) along the left abutment and it’s wingwalls and at the upstream end of the right abutment. Also, type-3 stone fill (less than 48 inches diameter) is along the upstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.1 to 1.1 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 5.6 to 9.0 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  17. Level II scour analysis for Bridge 3 (EASTTH00010003) on Town Highway 1, crossing the East Branch Passumpsic River, East Haven, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.; Boehmler, Erick M.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure EASTTH00010003 on Town Highway 1 crossing the East Branch Passumpsic River, East Haven, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the White Mountain section of the New England physiographic province in northeastern Vermont. The 50.4-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover on the left bank upstream is forest. On the remaining three banks the surface cover is pasture while the immediate banks have dense woody vegetation. In the study area, the East Branch Passumpsic River has an incised, sinuous channel with a slope of approximately 0.003 ft/ft, an average channel top width of 62 ft and an average bank height of 5 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 61.5 mm (0.187 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 14, 1995, indicated that the reach was stable. The Town Highway 1 crossing of the East Branch Passumpsic River is a 89-ft-long, two-lane bridge consisting of one 87-foot steel-beam span (Vermont Agency of Transportation, written communication, March 17, 1995). The opening length of the structure parallel to the bridge face is 84.7 ft. The bridge is supported by vertical, concrete abutments with sloped stone fill in front that creates a spill through embankment. The channel is skewed approximately zero degrees to the opening and the opening-skew-to-roadway is also zero degrees. Channel scour 0.5 ft deeper than the mean thalweg depth was observed to the left of the center of the channel under the bridge during the Level I assessment. The scour countermeasures at the site are type-2 stone fill (less than 36 inches diameter) along the downstream left bank and type-4 stone fill (less than 60 inches diameter) in front of the abutments creating spill through slopes. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0 to 1.8 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 6.4 to 11.7 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  18. Level II scour analysis for Bridge 16 (RIPTTH00110016) on Town Highway 11, crossing the Middle Branch Middlebury River, Ripton, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure RIPTTH00110016 on Town Highway 11 crossing the Middle Branch Middlebury River, Ripton, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in west-central Vermont. The 6.6-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover consists of shrubs, brush and trees except for the upstream left bank which is completely forested. In the study area, the Middle Branch Middlebury River has an incised, sinuous channel with a slope of approximately 0.03 ft/ft, an average channel top width of 68 ft and an average bank height of 5 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 97.6 mm (0.320 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 11, 1996, indicated that the reach was stable. The Town Highway 11 crossing of the Middle Branch Middlebury River is a 44-ft-long, two-lane bridge consisting of one 42-foot steel-beam span (Vermont Agency of Transportation, written communication, December 15, 1995). The opening length of the structure parallel to the bridge face is 40.2 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 40 degrees to the opening. The opening-skew-to-roadway value from the VTAOT database is 20 degrees while 30 degrees was computed from surveyed points. A scour hole, 3 ft deeper than the mean thalweg depth, was observed along the left abutment and upstream left wingwall during the Level I assessment. In addition, 1 ft of channel scour was observed just downstream of the downstream left wingwall along the left bank. Scour countermeasures at the site included type-2 stone fill (less than 36 inches diameter) along the upstream left and right banks and along the upstream end of the downstream left wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.1 to 0.4 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 7.2 to 8.6 ft along the right abutment and from 11.7 to 13.7 ft along the left abutment. The worstcase abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  19. Level II scour analysis for Bridge 21 (MORETH00010021) on Town Highway 1, crossing Cox Brook, Moretown, Vermont

    USGS Publications Warehouse

    Striker, Lora K.; Medalie, Laura

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure MORETH00010021 on Town Highway 1 crossing Cox Brook, Moretown, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in north-central Vermont. The 2.85-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is predominantly forested. In the study area, Cox Brook has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 23 ft and an average bank height of 4 ft. The channel bed material ranges from gravel to cobble with a median grain size (D50) of 47.5 mm (0.156 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 18, 1996, indicated that the reach was stable. The Town Highway 1 crossing of Cox Brook is a 29-ft-long, two-lane bridge consisting of one 27-foot steel-beam span (Vermont Agency of Transportation, written communication, October 13, 1995). The opening length of the structure parallel to the bridge face is 24.8 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 60 degrees to the opening while the measured opening-skew-to-roadway is 40 degrees. A scour hole 1.0 ft deeper than the mean thalweg depth was observed along the left abutment downstream during the Level I assessment. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the left bank upstream. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100-year and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.2 to 0.5 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge, which was less than the 100-year discharge. Abutment scour ranged from 2.8 to 4.0 ft. The worst-case abutment scour occurred at the left abutment at the 100-year discharge and at the right abutment at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  20. Level II scour analysis for Bridge 20 (BRISTH00270020) on Town Highway 27, crossing Little Notch Brook, Bristol, Vermont

    USGS Publications Warehouse

    Boehmler, Erick M.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure BRISTH00270020 on Town Highway 27 crossing Little Notch Brook, Bristol, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in west-central Vermont. The 8.43-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover consists of pasture with trees, shrubs, and brush along the road embankments and the stream banks, except for the downstream left overbank area. Surface cover on the downstream left overbank is forest with dense undergrowth consisting of vines, shrubs, and brush. In the study area, Little Notch Brook has a sinuous channel with a slope of approximately 0.006 ft/ft, an average channel top width of 47 feet and an average bank height of 3 feet. The predominant channel bed materials are gravel and cobbles with a median grain size (D50) of 66.0 mm (0.216 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 19, 1995, indicated that the reach was stable. The Town Highway 27 crossing of Little Notch Brook is a 48-ft-long, one-lane bridge consisting of one 45-foot steel pony-truss span (Vermont Agency of Transportation, written communication, November 30, 1995). The opening length of the structure parallel to the bridge face is 42.8 feet. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 15 degrees to the opening while the opening-skew-to-roadway is zero degrees. A scour hole 1.0 feet deeper than the mean thalweg depth was observed along the upstream left wingwall and the upstream end of the left abutment during the Level I assessment. The only scour protection measure at the site was a crude, block-cut stone wall, which extended from the upstream end of the upstream left wingwall to 45 feet upstream. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.2 feet. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 12.2 to 13.4 feet at the left abutment and from 3.6 to 5.0 feet at the right abutment. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  1. Level II scour analysis for Bridge 144 (ROCHVT01000144) on State Route 100, crossing the White River, Rochester, Vermont

    USGS Publications Warehouse

    Boehmler, Erick M.; Wild, Emily C.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ROCHVT01000144 on State Route 100 crossing the White River, Rochester, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in central Vermont. The 68.9-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture with forest on the valley walls. In the study area, the White River has a meandering channel with a slope of approximately 0.003 ft/ft, an average channel top width of 119 ft and an average channel depth of 4 ft. The predominant channel bed material is gravel and cobbles with a median grain size (D50) of 72.5 mm (0.238 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 22, 1996, indicated that the reach was laterally unstable due to a cut-bank present on the upstream left bank and wide point bars upstream and downstream in the vicinity of this site. The State Route 100 crossing of the White Riveris a 103-ft-long, two-lane bridge consisting of one 101-foot steel-beam span (Vermont Agency of Transportation, written communication, March 8, 1995). The bridge is supported by vertical, concrete abutment walls with spill-through embankments in front of each abutment wall and no wingwalls. The channel is skewed approximately 10 degrees to the opening while the opening-skew-toroadway is 5 degrees. The scour protection measures at the site are type-2 stone fill (less than 36 inches diameter) on the upstream left bank, both abutment spill-through embankments, and the downstream banks. There also is type-1 stone fill (less than 12 inches diameter) on the upstream right bank. The stone fill is continuous on both sides of the river in the vicinity of the bridge. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. There was no computed contraction scour for the modelled flows. Abutment scour ranged from 6.9 to 10.9 ft. The worst-case abutment scour occurred at the incipient overtopping discharge, which was less than the 100-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particlesize distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  2. Level II scour analysis for Bridge 4 (DANVTH00010004) on Town Highway 1, crossing Joes Brook, Danville, Vermont

    USGS Publications Warehouse

    Flynn, Robert H.; Boehmler, Erick M.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure DANVTH00010004 on Town Highway 1 crossing Joes Brook, Danville, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in northeastern Vermont. The 42.5-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture along the upstream and downstream left banks with trees and brush along the immediate banks. The upstream and downstream right banks are forested. In the study area, Joes Brook has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 68 ft and an average bank height of 5 ft. The channel bed material ranges from gravel to bedrock with a median grain size (D50) of 80.1 mm (0.263 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 22, 1995, indicated that the reach was stable. The Town Highway 1 crossing of Joes Brook is a 49-ft-long, two-lane bridge consisting of one 45-foot steel-beam span (Vermont Agency of Transportation, written communication, March 17, 1995). The opening length of the structure parallel to the bridge face is 45 ft.The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 15 degrees to the opening and the computed opening-skew-to-roadway is 15 degrees. A scour hole 1.0 ft deeper than the mean thalweg depth was observed along the right abutment during the Level I assessment. The scour hole also extends upstream and downstream of the bridge, along the right side of the channel. The scour protection measures at the site include type-2 stone fill (less than 36 inches diameter) at the upstream end of the upstream left wingwall and along the entire base length of the downstream right wingwall. Type-3 stone fill (less than 48 inches diameter) is along the entire base length of the upstream right wingwall and type-5 protection (stone block wall) is along the upstream right bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was computed to be zero ft. Abutment scour ranged from 11.7 to 13.0 ft along the right abutment and from 6.6 to 9.4 ft along the left abutment. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich and Hire equations (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  3. Level II scour analysis for Bridge 38 (TOPSTH00570038) on Town Highway 57, crossing Waits River, Topsham, Vermont

    USGS Publications Warehouse

    Striker, Lora K.; Boehmler, Erick M.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure TOPSTH00570038 on Town Highway 57 crossing the Waits River, Topsham, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in east central Vermont. The 37.3-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is predominantly pasture while the left bank upstream is suburban. In the study area, the Waits River has a sinuous locally anabranched channel with a slope of approximately 0.01 ft/ft, an average channel top width of 76 ft and an average bank height of 6 ft. The channel bed material ranges from sand to cobble with a median grain size (D50) of 57.2 mm (0.188 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 28, 1995, indicated that the reach was considered laterally unstable due to cut-banks upstream, mid-channel bars and lateral migration of the channel towards the left abutment. The Town Highway 34 crossing of the Waits River is a 34-ft-long, one-lane bridge consisting of one 31-foot steel-beam span (Vermont Agency of Transportation, written communication, March 28, 1995). The opening length of the structure parallel to the bridge face is 30.4 ft. The bridge is supported by a vertical, stone abutment with concrete facing and wingwalls on the right and by a vertical, concrete abutment with wingwalls on the left. The channel is skewed approximately 0 degrees to the opening and the opening-skew-to-roadway is also zero degrees. A scour hole 2.0 ft deeper than the mean thalweg depth was observed towards the left bank underneath the bridge. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the left bank upstream, in the upstream left wing wall area, along the left abutment, at the downstream end of the right abutment, and in the downstream left wing wall area. There is type-3 stone fill (less than 48 inches diameter) in the downstream right wing wall area. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 1.6 to 5.2 ft. The worst-case contraction scour occurred at the 100-year discharge. Abutment scour ranged from 9.8 to 18.5 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  4. Level II scour analysis for Bridge 31 (HUNTTH00220031) on Town Highway 22, crossing Brush Brook, Huntington, Vermont

    USGS Publications Warehouse

    Flynn, Robert H.; Degnan, James R.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure HUNTTH00220031 on Town Highway 22 crossing Brush Brook, Huntington, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, obtained from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in west-central Vermont. The 5.01-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover consists of trees and brush. In the study area, Brush Brook has an incised, straight channel with a slope of approximately 0.06 ft/ft, an average channel top width of 44 ft and an average bank height of 4 ft. The channel bed material ranges from boulder to gravel with a median grain size (D50) of 107.0 mm (0.352 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 25, 1996, indicated that the reach was stable. The Town Highway 22 crossing of Brush Brook is a 34-ft-long, one-lane bridge consisting of one 30-foot steel I-beam span (Vermont Agency of Transportation, written communication, November 30, 1995). The opening length of the structure parallel to the bridge face is 31.2 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 15 degrees to the opening while the computed opening-skew-to-roadway is 10 degrees. The VTAOT computed opening-skewto-roadway is 2 degrees. A scour hole 1.0 ft deeper than the mean thalweg depth was observed at the downstream end of the left abutment during the Level I assessment. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the upstream right bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was computed to be zero ft. Abutment scour ranged from 7.0 to 10.5 ft. The worst-case abutment scour occurred at the 500-year discharge for the left abutment and at the incipient-overtopping discharge for the right abutment. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  5. Level II scour analysis for Bridge 28 (CAMBTH00460028) on Town Highway 46, crossing the Seymour River, Cambridge, Vermont

    USGS Publications Warehouse

    Ivanoff, Michael A.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure CAMBTH00460028 on Town Highway 46 crossing the Seymour River, Cambridge, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in northwestern Vermont. The 9.94-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture while the immediate banks have dense woody vegetation. In the study area, the Seymour River has an incised, straight channel with a slope of approximately 0.02 ft/ft, an average channel top width of 81 ft and an average bank height of 5 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 62.0 mm (0.204 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 11, 1995, indicated that the reach was stable. The Town Highway 46 crossing of the Seymour River is a 38-ft-long, one-lane bridge consisting of one 33-foot steel-beam span (Vermont Agency of Transportation, written communication, March 8, 1995). The opening length of the structure parallel to the bridge face is 30.6 ft.The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 5 degrees to the opening while the measured opening-skew-to-roadway is 10 degrees. A scour hole 0.2 ft deeper than the mean thalweg depth was observed along the upstream right wingwall and right abutment during the Level I assessment. The only scour protection measure at the site was type-1 stone fill (less than 12 inches diameter) along the upstream left road embankment. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.8 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge. Left abutment scour ranged from 4.2 to 4.9 ft. The worst-case left abutment scour occurred at the 500-year discharge. Right abutment scour ranged from 8.8 to 9.7 ft. The worst-case right abutment scour occurred at the incipient roadway-overtopping discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  6. Level II scour analysis for Bridge 16 (CHESVT01030016) on State Route 103, crossing the Williams River, Chester, Vermont

    USGS Publications Warehouse

    Ivanoff, Michael A.; Hammond, Robert E.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure CHESVT01030016 on State Route 103 crossing the Williams River, Chester, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in southeastern Vermont. The 15.1-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture except for the downstream right overbank which is forested. In the study area, the Williams River has an incised, straight channel with a slope of approximately 0.008 ft/ft, an average channel top width of 56 ft and an average bank height of 6 ft. The channel bed material ranges from gravel to cobbles with a median grain size (D50) of 67.5 mm (0.222 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 16, 1996, indicated that the reach was stable. The State Route 103 crossing of the Williams River is a 162-ft-long, two-lane bridge consisting of three steel-beam spans (Vermont Agency of Transportation, written communication, March 13, 1995). The opening length of the structure parallel to the bridge face is 157.7 ft.The bridge is supported by vertical, concrete abutments and piers with no wingwalls. The channel is skewed approximately 55 degrees to the opening while the opening-skew-to-roadway is also 55 degrees. The scour protection measures at the site included type-4 stone fill (less than 60 inches diameter) along the upstream left bank. There was type-3 stone fill (less than 48 inches diameter) along the upstream right bank and both spill-through embankments and both downstream banks. There was type-1 stone fill (less than 12 inches diameter) along the upstream right and downstream left road embankments. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was 0.0. Abutment scour ranged from 6.4 to 9.0 ft. The worst-case abutment scour occurred at the 500-year discharge. Pier scour ranged from 7.9 to 10.1 ft. The worst-case pier scour occurred at the incipient-overtopping discharge for both piers. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  7. Level II scour analysis for Bridge 32 (TUNBTH00600032) on Town Highway 60, crossing First Branch White River, Tunbridge, Vermont

    USGS Publications Warehouse

    Wild, Emily C.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure TUNBTH00600032 on Town Highway 60 crossing the First Branch White River, Tunbridge, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the New England Upland section of the New England physiographic province in central Vermont. The 92.9-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture upstream and downstream of the bridge, while woody vegetation sparsely covers the immediate banks. In the study area, the First Branch White River has a sinuous channel with a slope of approximately 0.001 ft/ft, an average channel top width of 82 ft and an average bank height of 7 ft. The channel bed material ranges from sand to gravel with a median grain size (D50) of 24.4 mm (0.08 ft). The geomorphic assessment at the time of the Level I and Level II site visit on October 18, 1995, indicated that the reach was laterally unstable, as a result of block failure of moderately eroded banks. The Town Highway 60 crossing of the First Branch White River is a 74-ft-long, one-lane bridge consisting of a 71-foot timber thru-truss span (Vermont Agency of Transportation, written communication, August 24, 1994). The opening length of the structure parallel to the bridge face is 64 ft.The bridge is supported by vertical, laid-up stone abutments with upstream wingwalls. The channel is not skewed to the opening. The computed opening-skew-to-roadway is 5 degrees. A scour hole 1.0 ft deeper than the mean thalweg depth was observed in the upstream reach during the Level I assessment. Scour countermeasures at the site includes type-1 stone fill (less than 12 inches diameter) along the upstream right bank. Type-2 stone fill (less than 36 inches diameter) is present along the upstream right wingwall, the left abutment and the right abutment. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the maximum free-surface discharge was determined and analyzed as another potential worst-case scour scenarios. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 2.2 to 6.8 ft. The worst-case contraction scour occurred at the 500-year discharge. Left abutment scour ranged from 20.6 to 30.4 ft. Right abutment scour ranged from 9.7 to 19.5 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  8. Level II scour analysis for Bridge 46 (FFIETH00470046) on Town Highway 47, crossing Black Creek, Fairfield, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Flynn, Robert H.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure FFIETH00470046 on Town Highway 47 crossing Black Creek, Fairfield, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gathered from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Green Mountain section of the New England physiographic province in northwestern Vermont. The 37.8 mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture upstream and downstream of the bridge while the immediate banks have dense woody vegetation. In the study area, Black Creek has a meandering channel with a slope of approximately 0.0005 ft/ft, an average channel top width of 51 ft and an average bank height of 6 ft. The channel bed material ranges from sand to bedrock with a median grain size (D50) of 0.189 mm (0.00062 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 12, 1995, indicated that the reach was stable. The Town Highway 47 crossing of Black Creek is a 35-ft-long, one-lane bridge consisting of one 31-ft steel-stringer span (Vermont Agency of Transportation, written communication, March 8, 1995). The opening length of the structure parallel to the bridge face is 28.0 ft. The bridge is supported by vertical, laid-up stone abutments with wingwalls. The channel is skewed approximately zero degrees to the opening and the opening-skew-toroadway is zero degrees. A scour hole 6.0 ft deeper than the mean thalweg depth was observed just downstream of the bridge during the Level I assessment. Scour protection measures at the site included type-1 stone fill (less than 12 inches diameter) along the left abutment. Type-2 stone fill (less than 36 inches diameter) extended along the upstream left and right banks, the upstream left and right wingwalls, the downstream left wingwall, and the downstream left bank. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 1.4 to 8.2 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge, which was less than the 100-year discharge. Abutment scour ranged from 5.8 to 15.6 ft. At the left abutment, the worst-case abutment scour occurred at the 100-year discharge, and at the right abutment the worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results.” Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  9. Level II scour analysis for Bridge 31 (JERITH00350031) on Town Highway 35, crossing Mill Brook, Jericho, Vermont

    USGS Publications Warehouse

    Wild, Emily C.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure JERITH00350031 on Town Highway 35 crossing Mill Brook, Jericho, Vermont (figures 1– 8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gathered from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province and the Champlain section of the St. Lawrence physiographic province in northwestern Vermont. The 15.7-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest upstream of the bridge. The downstream left overbank is pasture. The downstream right overbank is brushland. In the study area, the Mill Brook has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 117 ft and an average bank height of 11 ft. The channel bed material ranges from gravel to boulders with a median grain size (D50) of 81.1 mm (0.266 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 3, 1996, indicated that the reach was laterally unstable. The Town Highway 35 crossing of the Mill Brook is a 53-ft-long, one-lane bridge consisting of a 50-foot steel-beam span with a wooden deck (Vermont Agency of Transportation, written communication, November 30, 1995). The opening length of the structure parallel to the bridge face is 48 ft. The bridge is supported by a vertical, concrete abutment with wingwalls on the left. On the right, the abutment and wingwalls are laid-up stone with a concrete cap. The channel is not skewed to the opening. The roadway is skewed 10 degrees to the opening. A scour hole 1.5 ft deeper than the mean thalweg depth was observed along the left abutment during the Level I assessment. Scour countermeasures at the site were type-2 stone fill (less than 36 inches diameter) at the upstream and downstream left wingwalls, the upstream and downsteam left channel banks, and the downstream left road embankment. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). In addition, the incipient roadway-overtopping discharge is analyzed since it has the potential of being the worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.4 to 1.3 ft. The worst-case contraction scour occurred at the 500-year discharge. Left abutment scour ranged from 9.9 to 12.4 ft. Right abutment scour ranged from 13.8 to 17.8 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  10. Level II scour analysis for Bridge 13 (PFRDTH00030013) on Town Highway 3, crossing Furnace Brook, Pittsford, Vermont

    USGS Publications Warehouse

    Flynn, Robert H.; Medalie, Laura

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure PFRDTH00030013 on Town Highway 3 crossing Furnace Brook, Pittsford, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Taconic section of the New England physiographic province in western Vermont. The 17.1-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is grass along the downstream right bank while the remaining banks are primarily forested. In the study area, Furnace Brook has an incised, sinuous channel with a slope of approximately 0.03 ft/ft, an average channel top width of 49 ft and an average channel depth of 4 ft. The predominant channel bed material ranges from gravel to bedrock with a median grain size (D50) of 70.2 mm (0.230 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 20, 1995, indicated that the reach was stable. The Town Highway 3 crossing of Furnace Brook is a 75-ft-long, two-lane bridge consisting of one 72-ft-long steel stringer span (Vermont Agency of Transportation, written communication, March 14, 1995). The bridge is supported by vertical, concrete abutments with spill-through slopes. The channel is skewed approximately 20 degrees to the opening while the opening-skew-to-roadway is 35 degrees. The opening-skew-to-roadway was determined from surveyed data collected at the bridge although, information provided from the VTAOT files, indicates that the opening-skew-to-roadway is 30 degrees (Appendix D). The scour protection measures at the site included type-2 stone fill (less than 36 inches diameter) on the spill-through slope along each abutment. Type-2 stone fill scour protection was also found along the upstream left wingwall and downstream right wingwall. Type-1 (less than 12 inches diameter) stone fill scour protection was found along the upstream right wingwall and downstream left wingwall. No bank protection was observed downstream or upstream. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 1.2 to 2.0 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 7.8 to 13.1 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution although, bedrock outcropping is apparent both upstream and downstream of this bridge. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  11. Level II scour analysis for Bridge 4 (MAIDTH00070004) on Town Highway 7, crossing Cutler Mill Brook, Maidstone, Vermont

    USGS Publications Warehouse

    Striker, Lora K.; Medalie, Laura

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure MAIDTH00070004 on Town Highway 7 crossing the Cutler Mill Brook, Maidstone, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the White Mountain section of the New England physiographic province in northeastern Vermont. The 18.1-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is predominantly shrub and brushland. In the study area, the Cutler Mill Brook has a non-incised, meandering channel with local braiding and a slope of approximately 0.004 ft/ft, an average channel top width of 43 ft and an average bank height of 2 ft. The channel bed material ranges from sand to cobble with a median grain size (D50) of 27.6 mm (0.091 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 19, 1995, indicated that the reach was laterally unstable due to large meanders in the channel. The Town Highway 7 crossing of the Cutler Mill Brook is a 25-ft-long, one-lane bridge consisting of one 22-foot concrete span (Vermont Agency of Transportation, written communication, August 5, 1994). The opening length of the structure parallel to the bridge face is 21.7 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 20 degrees to the opening while the opening-skew-to-roadway is 0 degrees. A scour hole 2.0 ft deeper than the mean thalweg depth was observed along the left abutment during the Level I assessment. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along both banks upstream, along the entire base length of the upstream left wingwall, and along the upstream end of the upstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 2.2 to 4.2 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 5.7 to 12.4 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  12. Level II scour analysis for Bridge 6 (FAYSTH00010006) on Town Highway 1, crossing Shepard Brook, Fayston, Vermont

    USGS Publications Warehouse

    Striker, Lora K.; Flynn, Robert H.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure FAYSTH00010006 on Town Highway 1 crossing Shepard Brook, Fayston, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in central Vermont. The 16.6-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest. In the study area, Shepard Brook has an incised, sinuous channel with a slope of approximately 0.01 ft/ft, an average channel top width of 56 ft and an average bank height of 3 ft. The channel bed material ranges from sand to boulder with a median grain size (D50) of 72.6 mm (0.238 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 2, 1996, indicated that the reach was stable. The Town Highway 1 crossing of the Shepard Brook is a 42-ft-long, two-lane bridge consisting of one 40-foot concrete T-beam span (Vermont Agency of Transportation, written communication, October 13, 1995). The opening length of the structure parallel to the bridge face is 39.6 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 15 degrees to the opening while the calculated opening-skew-to-roadway is 30 degrees. Scour, 2.0 ft deeper than the mean thalweg depth, was observed along the right abutment during the Level I assessment. The left abutment is undermined along the base of the footing. In addition, 1.5 ft of scour was observed along the left abutment during the Level I assessment. The only scour protection measure at the site was type-1 stone fill (less than 12 inches diameter) along the left bank upstream and type-2 stone fill (less than 36 inches diameter) along the upstream end of the upstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.9 to 3.9 ft. The worst-case contraction scour occurred at the 500-year. Abutment scour ranged from 11.1 to 17.2 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  13. Level II scour analysis for Bridge 45 (BRNETH00070045) on Town Highway 7, crossing the Stevens River, Barnet, Vermont

    USGS Publications Warehouse

    Ivanoff, Michael A.; Hammond, Robert E.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure BRNETH00070045 on Town Highway 7 crossing the Stevens River, Barnet, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in east-central Vermont. The 41.5-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest upstream and pasture downstream of the bridge while the immediate banks have dense woody vegetation. In the study area, the Stevens River has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 100 ft and an average bank height of 17 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 105 mm (0.344 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 22, 1995, indicated that the reach was stable. The Town Highway 7 crossing of the Stevens River is a 37-ft-long, two-lane bridge consisting of one 34-foot concrete slab span (Vermont Agency of Transportation, written communication, March 16, 1995). The opening length of the structure parallel to the bridge face is 33 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 10 degrees to the opening while the opening-skew-to-roadway is 20 degrees. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the entire left and right abutments, upstream and downstream wingwalls, and upstream and downstream banks. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.8 to 5.4 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge, which was greater than the 100-year discharge. Left abutment scour ranged from 21.8 to 28.6 ft. The worst-case left abutment scour occurred at the 500-year discharge. Right abutment scour ranged from 14.6 to 17.4 ft. The worst-case right abutment scour occurred at the incipient roadway-overtopping discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  14. Level II scour analysis for Bridge 25 (ROCHTH00400025) on Town Highway 40, crossing Corporation Brook, Rochester, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Weber, Matthew A.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ROCHTH00400025 on Town Highway 40 crossing Corporation Brook, Rochester, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, from Vermont Agency of Transportation files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Green Mountain section of the New England physiographic province in central Vermont. The 4.97-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest on the upstream left and right overbanks, and the downstream left overbank. On the downstream right overbank, the surface cover is predominately brushland. In the study area, Corporation Brook has an incised, sinuous channel with a slope of approximately 0.04 ft/ft, an average channel top width of 37 ft and an average bank height of 6 ft. The channel bed material ranges from gravel to boulders with a median grain size (D50) of 101 mm (0.332 ft). The geomorphic assessment at the time of the Level I site visit on April 12, 1995 and Level I and II site visit on July 8, 1996, indicated that the reach was stable. The Town Highway 40 crossing of Corporation Brook is a 31-ft-long, one-lane bridge consisting of a 26-foot steel stringer span (Vermont Agency of Transportation, written communication, March 22, 1995). The opening length of the structure parallel to the bridge face is 24 ft. The bridge is supported by vertical, concrete abutments. The channel is skewed approximately 15 degrees to the opening while the opening-skew-to-roadway is 15 degrees. A scour hole 1.0 ft deeper than the mean thalweg depth was observed in the channel at the downstream bridge face during the Level I assessment. Additionally, it was observed that the left abutment footing was exposed 1.0 ft and the right abutment footing was exposed 2.0 ft. Scour countermeasures at the site included type-1 stone fill (less than 12 inches diameter) along the upstream left and right banks and the downstream left bank. Type-2 stone fill (less than 36 inches diameter) scour protection extended along the downstream right bank and the upstream and downstream ends of the abutments. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.1 to 1.5 ft. The worst-case contraction scour occurred at the 500-year discharge. Left abutment scour ranged from 6.5 to 7.0 ft. The worst-case left abutment scour occurred at the 500-year discharge. Right abutment scour ranged from 5.6 to 6.0 ft. The worst-case right abutment scour occurred at the incipient roadway-overtopping discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  15. California State Waters Map Series--Offshore of Ventura, California

    USGS Publications Warehouse

    Johnson, Samuel Y.; Dartnell, Peter; Cochrane, Guy R.; Golden, Nadine E.; Phillips, Eleyne L.; Ritchie, Andrew C.; Kvitek, Rikk G.; Greene, H. Gary; Krigsman, Lisa M.; Endris, Charles A.; Seitz, Gordon G.; Gutierrez, Carlos I.; Sliter, Ray W.; Erdey, Mercedes D.; Wong, Florence L.; Yoklavich, Mary M.; Draut, Amy E.; Hart, Patrick E.; Johnson, Samuel Y.; Cochran, Susan A.

    2013-01-01

    In 2007, the California Ocean Protection Council initiated the California Seafloor Mapping Program (CSMP), designed to create a comprehensive seafloor map of high-resolution bathymetry, marine benthic habitats, and geology within the 3-nautical-mile limit of California’s State Waters. The CSMP approach is to create highly detailed seafloor maps through collection, integration, interpretation, and visualization of swath sonar data, acoustic backscatter, seafloor video, seafloor photography, high-resolution seismic-reflection profiles, and bottom-sediment sampling data. The map products display seafloor morphology and character, identify potential marine benthic habitats, and illustrate both the surficial seafloor geology and shallow (to about 100 m) subsurface geology. The Offshore of Ventura map area lies within the Santa Barbara Channel region of the Southern California Bight. This geologically complex region forms a major biogeographic transition zone, separating the cold-temperate Oregonian province north of Point Conception from the warm-temperate California province to the south. The map area is in the Ventura Basin, in the southern part of the Western Transverse Ranges geologic province, which is north of the California Continental Borderland. Significant clockwise rotation—at least 90°—since the early Miocene has been proposed for the Western Transverse Ranges, and the region is presently undergoing north-south shortening. The city of Ventura is the major cultural center in the map area. The Ventura River cuts through Ventura, draining the Santa Ynez Mountains and the coastal hills north of Ventura. Northwest of Ventura, the coastal zone is a narrow strip containing highway and railway transportation corridors and a few small residential clusters. Rincon Island, an island constructed for oil and gas production, lies offshore of Punta Gorda. Southeast of Ventura, the coastal zone consists of the mouth and broad, alluvial plains of the Santa Clara River, and the region is characterized by urban and agricultural development. Ventura Harbor sits just north of the mouth of the Santa Clara River, in an area formerly occupied by lagoons and marshes. The Offshore of Ventura map area lies in the eastern part of the Santa Barbara littoral cell, whose littoral drift is to the east-southeast. Drift rates of about 700,000 to 1,150,000 tons/yr have been reported at Ventura Harbor. At the east end of the littoral cell, eastward-moving sediment is trapped by Hueneme and Mugu Canyons and then transported into the deep-water Santa Monica Basin. The largest sediment source to this littoral cell (and the largest in all of southern California) is the Santa Clara River, which has an estimated annual sediment flux of 3.1 million tons. In addition, the Ventura River yields about 270,000 tons of sediment annually. Despite the large local sediment supply, coastal erosion problems are ongoing in the map area. Riprap, revetments, and seawalls variably protect the coast within and north of Ventura. The offshore part of the map area mainly consists of relatively flat, shallow continental shelf, which dips so gently (about 0.2° to 0.4°) that water depths at the 3-nautical-mile limit of California’s State Waters are just 20 to 40 m. This part of the Santa Barbara Channel is relatively well protected from large Pacific swells from the north and west by Point Conception and the Channel Islands; long-period swells affecting the area are mainly from the south-southwest. Fair-weather wave base is typically shallower than 20-m water depth, but winter storms are capable of resuspending fine-grained sediments in 30 m of water, and so shelf sediments in the map area probably are remobilized on an annual basis. The shelf is underlain by tens of meters of interbedded upper Quaternary shelf, estuarine, and fluvial sediments deposited as sea level fluctuated up and down in the last several hundred thousand years. Seafloor habitats in the broad Santa Barbara Channel region consist of significant amounts of soft sediment and isolated areas of rocky habitat that support kelp-forest communities nearshore and rocky-reef communities in deep water. The potential marine benthic habitat types mapped in the Offshore of Ventura map area are directly related to its Quaternary geologic history, geomorphology, and active sedimentary processes. These potential habitats lie within the Shelf (continental shelf) megahabitat, dominated by a flat seafloor and substrates formed from deposition of fluvial and marine sediment during sea-level rise. This flat, fairly homogeneous seafloor, composed primarily of unconsolidated sand and mud and local deposits of gravel, cobbles, and pebbles, provides promising habitat for groundfish, crabs, shrimp, and other marine benthic organisms. The only significant interruptions to this homogeneous habitat type are exposures of hard, irregular sedimentary bedrock and coarse-grained sediment where potential habitats for rockfish and related species exist.

  16. Level II scour analysis for Bridge 24 (MANCUS00070024) on U.S. Route 7, crossing Lye Brook, Manchester, Vermont

    USGS Publications Warehouse

    Olson, Scott A.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure MANCUS00070024 on U.S. Route 7 crossing Lye Brook, Manchester, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Taconic section of the New England physiographic province in southwestern Vermont. The 8.13-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the primary surface cover consists of brush and trees. In the study area, Lye Brook has an incised, sinuous channel with a slope of approximately 0.03 ft/ft, an average channel top width of 66 ft and an average bank height of 11 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 90.0 mm (0.295 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 6, 1996, indicated that the reach was stable. Although, the immediate reach is considered stable, upstream of the bridge the Lye Brook valley is very steep (0.05 ft/ft). Extreme events in a valley this steep may quickly reveal the instability of the channel. In the Flood Insurance Study for the Town of Manchester (Federal Emergency Management Agency, January, 1985), Lye Brook’s overbanks were described as “boulder strewn” after the August 1976 flood. The U.S. Route 7 crossing of Lye Brook is a 28-ft-long, two-lane bridge consisting of one 25-foot concrete span (Vermont Agency of Transportation, written communication, September 28, 1995). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 45 degrees to the opening while the opening-skew-to-roadway is 55 degrees. At the time of construction, the downstream channel was relocated (written communication, Dan Landry, VTAOT, January 2, 1997). A levee on the downstream right bank was also constructed and is protected by type-4 stone-fill (less than 60 inches diameter) extending from the bridge to more than 300 feet downstream. Type-2 stone fill (less than 36 inches diameter) covers the downstream right bank from the bridge to more than 300 feet downstream. Type-2 stone-fill also extends from the bridge to 220 feet upstream on both upstream banks. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is analyzed since it has the potential of being the worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 1.0 to 1.6 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour computations for the left abutment ranged from 14.5 to 16.1 ft. with the worst-case occurring at the 100-year discharge. Abutment scour computations for the right abutment ranged from 6.9 to 10.4 ft. with the worst-case occurring at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  17. Level II scour analysis for Bridge 26 (WSTOTH00070026) on Town Highway 7, crossing Greendale Brook, Weston, Vermont

    USGS Publications Warehouse

    Striker, Lora K.; Hammond, Robert A.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure WSTOTH00070026 on Town Highway 7 crossing Greendale Brook, Weston, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in south central Vermont. The 3.13-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest. In the study area, the Greendale Brook has a sinuous, non-incised, non-alluvial channel with a slope of approximately 0.015 ft/ft, an average channel top width of 38 ft and an average bank height of 3 ft. The channel bed material ranges from sand to boulder with a median grain size (D50) of 64.8 mm (0.213 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 19, 1996, indicated that the reach was laterally unstable. The channel has moved to the right, however, scour countermeasures are in place along the upstream right bank. The Town Highway 7 crossing of the Greendale Brook is a 52-ft-long, two-lane bridge consisting of one 50-foot steel-beam span with a concrete deck (Vermont Agency of Transportation, written communication, April 07, 1995). The opening length of the structure parallel to the bridge face is 48.6 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 50 degrees to the opening while the opening-skew-to-roadway is 30 degrees. A scour hole 1.5 ft deeper than the mean thalweg depth was observed along the upstream right wingwall and right abutment during the Level I assessment. Scour protection measures at the site include: type-2 stone fill (less than 36 inches diameter) at the upstream end of the upstream left wingwall, along the left bank upstream, at the downstream end of the downstream left wing wall, and along the entire length of the downstream right wing wall; type 4 (less than 60 inches) and type-3 stone fill (less than 48 inches) along the right bank upstream. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was 0.0 ft. Abutment scour ranged from 3.9 to 9.9 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). The Hire equation (abutment scour) is often used when the horizontal length blocked by flow divided by the depth of flow is greater than 25 (Richardson and others, 1995 p. 49). Although the Hire equation could be applied to the left abutment more conservative scour estimates were given by the Froehlich equation on the left abutment. Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  18. Level II scour analysis for Bridge 21 (MONKTH00340021) on Town Highway 34, crossing Little Otter Creek, Monkton, Vermont

    USGS Publications Warehouse

    Boehmler, Erick M.; Medalie, Laura

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure MONKTH00340021 on Town Highway 34 crossing Little Otter Creek, Monkton, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix D of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix C. The site is in the Champlain section of the Saint Lawrence Valley physiographic province in northwestern Vermont. The 34.1-mi2 drainage area is in a predominantly rural and forested basin with pasture in the valleys. In the vicinity of the study site, the surface cover consists of pasture. The most significant tree cover is immediately adjacent to the channel on the right bank downstream. In the study area, Little Otter Creek has a sinuous channel with a slope of approximately 0.008 ft/ft, an average channel top width of 92 feet and an average bank height of 6 feet. The predominant channel bed materials are silt and clay. Sieve analysis indicates that greater than 50% of the sample is silt and clay and thus a median grain size by use of sieve analysis was indeterminate. Therefore, the median grain size was assumed to be medium silt with a size (D50) of 0.0310 mm (0.000102 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 19 and June 20, 1996, indicated that the reach was stable. The Town Highway 34 crossing of Little Otter Creek is a 50-ft-long, one-lane bridge consisting of one 26-foot concrete span and three “boiler tube” smooth metal pipe culverts through the left road approach (Vermont Agency of Transportation, written communication, December 15, 1995). The opening length of the bridge parallel to the bridge face is 25.1 feet. The bridge is supported by vertical, concrete abutments with wingwalls on the right abutment only. The channel is skewed approximately 25 degrees to the opening. The VTAOT records indicate the opening-skew-to-roadway is 20 degrees but measurement from surveyed data suggests the skew is five degrees. The scour protection measures at the site were type-1 stone fill (less than 12 inches diameter) on the upstream and downstream embankments of the left road approach and type-2 stone fill (less than 36 inches diameter) surrounding the entrance of each culvert. Additional details describing conditions at the site are included in the Level II Summary and Appendices C and D. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 10.3 to 12.3 feet. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 8.6 to 22.5 feet. The worst-case abutment scour occurred at the 500-year discharge for the left abutment and at the incipient overtopping discharge for the right abutment. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  19. Level II scour analysis for Bridge 44 (CHESVT00110044) on State Route 11, crossing Andover Brook, Chester, Vermont

    USGS Publications Warehouse

    Ivanoff, Michael A.; Hammond, Robert E.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure CHESVT00110044 on State Route 11 crossing Andover Brook, Chester, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in southeastern Vermont. The 12.6-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture with dense woody vegetation on the immediate banks except the downstream left bank of the bridge which is forested. In the study area, Andover Brook has an incised, meandering channel with a slope of approximately 0.02 ft/ft, an average channel top width of 74 ft and an average bank height of 8 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 83.6 mm (0.274 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 11, 1996, indicated that the reach was stable. The State Route 11 crossing of Andover Brook is a 58-ft-long, two-lane bridge consisting of one 56-foot concrete T-beam span (Vermont Agency of Transportation, written communication, March 29, 1995). The opening length of the structure parallel to the bridge face is 52.9 ft.The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 35 degrees to the opening while the opening-skew-to-roadway is 45 degrees. A scour hole 1.8 ft deeper than the mean thalweg depth was observed along the upstream left wingwall and left abutment during the Level I assessment. The scour protection measures at the site included type-4 stone fill (less than 60 inches diameter) along the upstream left bank between the wingwall and a concrete wall. There was type-2 stone fill (less than 36 inches diameter) along the entire base of the upstream left wingwall, and the downstream end of the downstream right wingwall. There was type-1 stone fill (less than 12 inches diameter) at the downstream end of the downstream left wingwall. There was also a concrete wall along the upstream left bank from 18 to 50 ft upstream of the bridge. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 1.2 ft. The worst-case contraction scour occurred at the incipient-overtopping discharge. The incipientovertopping discharge is 520 cfs less than the 100-year discharge. Left abutment scour ranged from 16.4 to 20.9 ft. The worst-case left abutment scour occurred at the 500-year discharge. Right abutment scour ranged from 8.4 to 9.4 ft. The worst-case right abutment scour occurred at both the 100-year and 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  20. Level II scour analysis for Bridge 23 (WOLCTH00130023) on Town Highway 13, crossing the Wild Branch of the Lamoille River, Wolcott, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Degnan, James R.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure WOLCTH00130023 on Town Highway 13 crossing the Wild Branch Lamoille River, Wolcott, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, collected from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in northcentral Vermont. The 27.7-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture on the upstream right overbank. The upstream left overbank is brushland. Downstream of the bridge, the surface cover is forested on the right overbank. The downstream left overbank is pasture while the immediate bank has dense woody vegetation. In the study area, the Wild Branch Lamoille River has an incised, straight channel with a slope of approximately 0.009 ft/ft, an average channel top width of 65 ft and an average bank height of 7 ft. The channel bed material ranges from sand to boulders with a median grain size (D50) of 85.3 mm (0.280 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 17, 1996 indicated that the reach was laterally unstable. The Town Highway 13 crossing of the Wild Branch Lamoille River is a 41-ft-long, one-lane bridge consisting of a 39-foot steel girder span (Vermont Agency of Transportation, written communication, October 13, 1995). The opening length of the structure parallel to the bridge face is 38 ft. The bridge is supported by vertical, concrete abutments. The right abutment has concrete wingwalls. The channel is skewed approximately 45 degrees to the opening while the opening-skew-to-roadway is zero degrees. A scour hole 3.5 ft deeper than the mean thalweg depth was observed in the channel during the Level I assessment. Scour countermeasures at the site includes type-2 stone fill (less than 3 feet diameter) along the banks, the right wingwalls, the right abutment and the road embankments. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 1.0 to 2.1 ft. The worst-case contraction scour occurred at the 100-year discharge. Left abutment scour ranged from 9.1 to 13.2 ft. Right abutment scour ranged from 15.7 to 22.3 ft. The worst-case abutment scour occurred at the 500- year discharge for both abutments. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. During the August 1995 flood, the Wild Branch Lamoille River overtopped the bridge deck at structure WOLCTH00130023. Debris also was caught in the upstream I-beam of the structure. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  1. Level II scour analysis for Bridge 41 (ANDOVT00110041) on State Route 11, crossing the Middle Branch Williams River, Andover, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Hammond, Robert E.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ANDOVT00110041 on State Route 11 crossing the Middle Branch Williams River, Andover, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in southeastern Vermont. The 12.1-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is grass on the upstream right overbank while the immediate banks have dense woody vegetation. The upstream left overbank and downstream right overbank are brushland. The downstream left overbank is forested. In the study area, the Middle Branch Williams River has an incised, sinuous channel with a slope of approximately 0.018 ft/ft, an average channel top width of 71 ft and an average bank height of 4 ft. The channel bed material ranges from gravel to boulders with a median grain size (D50) of 85.0 mm (0.279 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 10, 1996, indicated that the reach was laterally unstable due to a cut-bank present on the upstream right bank and a wide channel bar with vegetation in the upstream reach. The State Route 11 crossing of the Middle Branch Williams River is a 46-ft-long, two-lane bridge consisting of a concrete 44-foot tee-beam span (Vermont Agency of Transportation, written communication, March 29, 1995). The opening length of the structure parallel to the bridge face is 42 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 35 degrees to the opening while the opening-skew-toroadway is zero degrees. A scour hole 0.8 ft deeper than the mean thalweg depth was observed along the downstream end of the left abutment and downstream left wingwall during the Level I assessment. Type- 2 stone fill (less than 36 inches diameter) protects the upstream end of the upstream left wingwall, the downstream ends of the downstream left and right wingwalls and the downstream right road embankment. Type-3 stone fill protects the upstream end of the upstream right wingwall and the upstream right bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 2.1 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 11.1 to 18.7 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  2. Level II scour analysis for Bridge 33 (TUNBTH00450033) on Town Highway 45, crossing the First Branch White River, Tunbridge, Vermont

    USGS Publications Warehouse

    Wild, E.C.; Severance, Timothy

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure TUNBTH00450033 on Town Highway 45 crossing the First Branch White River, Tunbridge, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in central Vermont. The 86.4-mi 2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture upstream and downstream of the bridge, while woody vegetation sparsely covers the immediate banks. In the study area, the First Branch White River has an incised, sinuous channel with a slope of approximately 0.003 ft/ft, an average channel top width of 68 ft and an average bank height of 7 ft. The channel bed material ranges from sand to gravel with a median grain size (D50) of 27.1 mm (0.089 ft). The geomorphic assessment at the time of the Level I and Level II site visit on October 18, 1995, indicated that the reach was laterally unstable due to a cut-bank present on the upstream right bank and a wide channel bar in the upstream reach. The Town Highway 45 crossing of the First Branch White River is a 67-ft-long, one-lane bridge consisting of one 54-foot timber thru-truss span (Vermont Agency of Transportation, written communication, March 23, 1995). The opening length of the structure parallel to the bridge face is 53.5 ft. The bridge is supported on the right by a vertical, concrete abutment with an upstream wingwall, and on the left by a vertical, stone abutment. The channel is skewed approximately 20 degrees to the opening while the computed opening-skew-to-roadway is 10 degrees. A scour hole 1.5 ft deeper than the mean thalweg depth was observed along the right abutment during the Level I assessment. Scour countermeasures at the site include type-1 stone fill (less than 12 inches diameter) along the upstream right wingwall, type-2 stone fill (less than 36 inches diameter) along the right abutment, and type-3 stone fill (less than 48 inches diameter) along the upstream right bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 3.0 ft. The worst-case contraction scour occurred at the 500-year discharge. Left abutment scour ranged from 12.8 to 31.0 ft. Right abutment scour ranged from 9.8 to 19.0 ft. The worst-case left and right abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in Tables 1 and 2. A cross-section of the scour computed at the bridge is presented in Figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  3. Level II scour analysis for Bridge 18 (SHEFTH00410018) on Town Highway 41, crossing Millers Run, Sheffield, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Boehmler, Erick M.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure SHEFTH00410018 on Town Highway 41 crossing Millers Run, Sheffield, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the White Mountain section of the New England physiographic province in northeastern Vermont. The 16.2-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is grass upstream and downstream of the bridge while the immediate banks have dense woody vegetation. In the study area, Millers Run has an incised, straight channel with a slope of approximately 0.01 ft/ft, an average channel top width of 50 ft and an average bank height of 6 ft. The channel bed material ranges from sand to boulder with a median grain size (D50) of 50.9 mm (0.167 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 1, 1995, indicated that the reach was laterally unstable, which is evident in the moderate to severe fluvial erosion in the upstream reach. The Town Highway 41 crossing of the Millers Run is a 30-ft-long, one-lane bridge consisting of a 28-foot steel-stringer span (Vermont Agency of Transportation, written communication, March 28, 1995). The opening length of the structure parallel to the bridge face is 22.2 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 20 degrees to the opening. The computed opening-skewto-roadway is 5 degrees, while it is zero degrees in the historical form. A scour hole 1.0 ft deeper than the mean thalweg depth was observed along the left abutment during the Level I assessment. The scour protection measure at the site includes type-1 stone fill (less than 12 inches diameter) along the upstream right wingwall and the upstream left wingwall. Type-2 stone fill (less than 36 inches diameter) extends along the downstream end of the downstream left wingwall, the upstream right bank and the downstream left bank. The downstream right bank is protected by type-2 stone fill and a stone masonry wall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.2 to 1.8 ft. The worst-case contraction scour occurred at the 100-year and 500-year discharges. Left abutment scour ranged from 14.1 to 16.4 ft. The worst-case left abutment scour occurred at the 500-year discharge. Right abutment scour ranged from 6.9 to 9.3 ft. The worst-case right abutment scour occurred at the incipient roadway-overtopping discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  4. Level II scour analysis for Bridge 37 (PLYMTH00080037) on Town Highway 8, crossing Broad Brook, Plymouth, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Medalie, Laura

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure PLYMTH00080037 on Town Highway 8 crossing Broad Brook, Plymouth, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gathered from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Green Mountain section of the New England physiographic province in south-central Vermont. The 5.6-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest upstream and downstream of the bridge. In the study area, Broad Brook has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 46 ft and an average bank height of 5 ft. The channel bed material ranges from gravel to boulders with a median grain size (D50) of 87.5 mm (0.287 ft). The geomorphic assessment at the time of the Level I and Level II site visit on October 3, 1995, indicated that the reach was laterally unstable due to cut-banks present on the upstream left bank and the downstream left and right banks. The Town Highway 8 crossing of Broad Brook is a 31-ft-long, one-lane bridge consisting of a 28-foot steel-stringer span (Vermont Agency of Transportation, written communication, March 22, 1995). The opening length of the structure parallel to the bridge face is 27.0 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 15 degrees to the opening while the opening-skew-to-roadway is 15 degrees. During the Level I assessment, it was observed that the left abutment footing was exposed 1.25 ft at the downstream end, and the subfooting was exposed 1 ft. Scour protection measures at the site included type-1 stone fill (less than 12 inches diameter) along the upstream right wingwall, the right abutment and the downstream right wingwall. Type-2 stone fill (less than 36 inches diameter) was along the upstream left wingwall, the upstream end of the left abutment and the downstream end of the downstream left wingwall. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.5 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge, which was less than the 100-year discharge. Left abutment scour ranged from 11.1 to 12.0 ft. Right abutment scour ranged from 3.0 to 7.7 ft. The worst-case abutment scour occurred at the 500-year discharge. Pier scour ranged from 6.2 to 7.1 ft. The worst-case pier scour also occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  5. Level II scour analysis for Bridge 29 (DORSTH00100029) on Town Highway 10, crossing the Mettawee River, Dorset, Vermont

    USGS Publications Warehouse

    Wild, Emily C.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure DORSTH00100029 on Town Highway 10 crossing the Mettawee River, Dorset, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Taconic section of the New England physiographic province in southwestern Vermont. The 9.5-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest on the upstream left overbank and the upstream and downstream right overbanks. The downstream left overbank is pasture and brushland. In the study area, the Mettawee River has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 66 ft and an average bank height of 8 ft. The channel bed material ranges from gravel to boulders with a median grain size (D50) of 79.0 mm (0.259 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 5, 1996, indicated that the reach was stable. The Town Highway 10 crossing of the Mettawee River is a 26-ft-long, two-lane bridge consisting of a 24-ft steel-stringer span (Vermont Agency of Transportation, written communication, September 28, 1995). The opening length of the structure parallel to the bridge face is 24.1 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 45 degrees to the opening while the opening-skew-to-roadway is zero degrees. At the upstream end of the right abutment, there is a scour hole 1.0 ft deeper than the mean thalweg depth. Scour counter-measures at the site include type-1 stone fill (less than 12 inches diameter) along the downstream right wingwall. Type-2 stone fill (less than 36 inches diameter) is present along the downstream left and right banks. Type-3 stone fill (less than 48 inches diameter) is present along the upstream left bank and sparsely in front of the right abutment. A concrete wall (old abutment) extends along the upstream right bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.4 to 1.9 ft. The worst-case contraction scour occurred at the 500-year discharge. Left abutment scour ranged from 10.5 to 10.8 ft. The worst-case left abutment scour occurred at the 500-year discharge. Right abutment scour ranged from 11.4 to 11.9 ft. The worst-case right abutment scour occurred at the 100-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  6. Level II scour analysis for Bridge 5 (WOLCTH00150005) on Town Highway 15, crossing the Wild Branch Lamoille River, Wolcott, Vermont

    USGS Publications Warehouse

    Wild, Emily C.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure WOLCTH00150005 on Town Highway 15 crossing the Wild Branch Lamoille River, Wolcott, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D.During the August 1995 and July 1997 flood events, the left roadway was overtopped. Although there was loss of stone fill along the right abutment, the structure withstood both events.The site is in the Green Mountain section of the New England physiographic province in north- central Vermont. The 38.3-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture upstream and downstream of the bridge, while the immediate banks have dense woody vegetation.In the study area, the Wild Branch Lamoille River has an incised, sinuous channel with a slope of approximately 0.006 ft/ft, an average channel top width of 98 ft and an average bank height of 5 ft. The channel bed material ranges from gravel to bedrock with a median grain size (D50) of 89.1 mm (0.292 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 17, 1996, indicated that the reach was stable.The Town Highway 15 crossing of the Wild Branch Lamoille River is a 46-ft-long, two-lane bridge consisting of a 43-foot prestressed concrete box-beam span (Vermont Agency of Transportation, written communication, October 13, 1995). The opening length of the structure parallel to the bridge face is 42 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 10 degrees to the opening while the opening- skew-to-roadway is zero degrees.A scour hole 2.0 ft deeper than the mean thalweg depth was observed near the bridge along the left side of the channel during the Level I assessment. Scour countermeasures at the site consists of type-1 stone fill (less than 12 inches diameter) along the upstream left bank and along the left and right downstream banks, type-2 stone fill (less than 36 inches diameter) along the downstream left and right wingwalls, type-3 stone fill (less than 48 inches diameter) along the upstream left wingwall and the right abutment, and type-4 stone fill (less than 60 inches diameter) along the upstream right wingwall and the left abutment. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.Contraction scour for all modelled flows was zero ft. Left abutment scour ranged from 7.9 to 23.3 ft. The worst-case left abutment scour occurred at the 500-year discharge. Right abutment scour ranged from 21.5 to 22.8 ft. The worst-case right abutment scour occurred at the incipient roadway-overtopping discharge. Additional in formation on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross- section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  7. National Assessment of Shoreline Change Part 3: Historical Shoreline Change and Associated Coastal Land Loss Along Sandy Shorelines of the California Coast

    USGS Publications Warehouse

    Hapke, Cheryl J.; Reid, David; Richmond, Bruce M.; Ruggiero, Peter; List, Jeff

    2006-01-01

    Beach erosion is a chronic problem along many open-ocean shores of the United States. As coastal populations continue to grow and community infrastructures are threatened by erosion, there is increased demand for accurate information regarding past and present trends and rates of shoreline movement. There is also a need for a comprehensive analysis of shoreline movement that is consistent from one coastal region to another. To meet these national needs, the U.S. Geological Survey is conducting an analysis of historical shoreline changes along open-ocean sandy shores of the conterminous United States and parts of Hawaii and Alaska. One purpose of this work is to develop standard repeatable methods for mapping and analyzing shoreline movement so that periodic updates regarding coastal erosion and land loss can be made nationally that are systematic and internally consistent. In the case of this study, the shoreline being measured is the boundary between the ocean water surface and the sandy beach. This report on the California Coast represents the first of two reports on long-term sandy shoreline change for the western U.S., the second of which will include the coast of the Pacific NW, including Oregon and Washington. A report for the Gulf of Mexico shoreline was completed in 2004 and is available at: http://pubs.usgs.gov/of/2004/1043/. This report summarizes the methods of analysis, interprets the results, provides explanations regarding long-term and short-term trends and rates of change, and describes how different coastal communities are responding to coastal erosion. Shoreline change evaluations are based on comparing three historical shorelines digitized from maps, with a recent shoreline derived from lidar (Light Detection and Ranging) topographic surveys. The historical shorelines generally represent the following periods: 1800s, 1920s-1930s, and 1950s-1970s, whereas the lidar shoreline is from 1998-2002. Long-term rates of change are calculated using all four shorelines (1800s to lidar shoreline), whereas short-term rates of change are calculated for only the most recent period (1950s-1970s to lidar shoreline). The rates of change presented in this report represent past conditions and therefore are not intended for predicting future shoreline positions or rates of change. Due to the geomorphology of the California Coast (rocky coastline instead of beach) as well as to data gaps in some areas, this report presents beach erosion rates for 45% of California's 1100 km of coast. The average rate of long-term shoreline change for the State of California was 0.2?0.1 m/yr, an accretional trend. This is based on shoreline change rates averaged from 14,562 individual transects, of which 40% were eroding. Of the transects on which the shoreline was eroding, the long-term erosion rates were generally lowest in Southern California where coastal engineering projects have greatly altered the natural shoreline movement. On a regional scale, long-term accretion rates were either equal to (Central California) or greater than (Northern and Southern California) the long-term erosion rates, yielding the net accretional trend for the entire state. This accretional trend is most likely due to changes in the large volumes of sediment that are added to the system from large rivers and to the impact from coastal engineering and beach nourishment projects. The average rate of short-term shoreline change for the state was erosional. The net short-term rate as averaged along 16,142 transects was -0.2?0.4 m/yr. Of the transects used to measure short-term change, 66% had erosional trends. In addition erosion rates were higher in the short-term period, possibly related to the localized artificial nourishment that occurred over much of the 20th century but that has recently slowed or stopped (Flick, 1993; Wiegel, 1994). Short-term accretion rates were highest in Northern California where the overall magnitudes of shoreline change are systematically higher than in Central and Southern California. The most stable (low erosion and accretion rates) California beaches were most commonly found in Central California. Seawalls and/or riprap revetments have been constructed in all three sections of California, although many of these structures were built to protect houses and infrastructures from the erosion of coastal cliffs and bluffs rather than to protect against long-term beach erosion. California permits shoreline stabilization structures where homes, buildings or other community infrastructure are imminently threatened by erosion. A second California report that is following this publication will include analyses and reports on long-term coastal cliff erosion, as this hazard is of equal or greater concern to coastal communities in many areas along the California Coast.

  8. Level II scour analysis for Bridge 48 (FFIETH00300048) on Town Highway 30, crossing Wanzer Brook, Fairfield, Vermont

    USGS Publications Warehouse

    Flynn, Robert H.; Boehmler, Erick M.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure FFIETH00300048 on Town Highway 30 crossing Wanzer Brook, Fairfield, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in northwestern Vermont. The 6.78-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover upstream of the bridge and on the downstream right bank is primarily pasture. The downstream left bank is forested. In the study area, Wanzer Brook has an incised, straight channel with a slope of approximately 0.03 ft/ft, an average channel top width of 65 ft and an average bank height of 5 ft. The channel bed material is cobble with a median grain size (D50) of 111 mm (0.364 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 11, 1995, indicated that the reach was stable. The Town Highway 30 crossing of Wanzer Brook is a 31-ft-long, two-lane bridge consisting of one 28-foot steel-beam span (Vermont Agency of Transportation, written communication, March 8, 1995). The opening length of the structure parallel to the bridge face is 26 ft.The bridge is supported by vertical stone wall abutments with concrete caps and “kneewall” footings. The channel is skewed approximately 25 degrees to the opening while the measured opening-skew-to-roadway is 20 degrees. A scour hole 1.5 ft deeper than the mean thalweg depth was observed along the downstream left retaining wall (extended concrete footing) during the Level I assessment. It was also observed that the right abutment is undermined with a scour depth of 0.5 ft. The scour protection at the site was limited to four large boulders (type-4, less than 60 inches diameter) along the downstream right retaining wall. The channel under the bridge is a “corduroy” log mat floor composed of 13 logs which are parallel to the bridge face and extend from 5 ft under the bridge to the downstream bridge face. The most downstream log is approximately 0.3 to 0.4 ft higher than the other logs and controls flow at lower flows. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.3 to 0.6 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 14.1 to 16.0 ft at the left abutment and from 6.8 to 7.6 ft at the right abutment. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  9. Level II scour analysis for Bridge 25 (REDSTH00360025) on Town Highway 36, crossing the West Branch Deerfield River, Readsboro, Vermont

    USGS Publications Warehouse

    Flynn, Robert H.; Burns, Ronda L.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure REDSTH00360025 on Town Highway 36 crossing the West Branch Deerfield River, Readsboro, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the Green Mountain section of the New England physiographic province in south-central Vermont. The 14.5-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture on the upstream right bank and forest on the upstream left bank. The surface cover on the downstream right and left banks is primarily grass, shrubs and brush. In the study area, the West Branch Deerfield River has an incised, sinuous channel with a slope of approximately 0.02 ft/ft, an average channel top width of 65 ft and an average bank height of 4 ft. The channel bed material ranges from gravel to boulders, with a median grain size (D50) of 117 mm (0.383 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 1, 1996, indicated that the reach was stable. The Town Highway 36 crossing of the West Branch Deerfield River is a 59-ft-long, two-lane bridge consisting of one 57-foot concrete T-beam span (Vermont Agency of Transportation, written communication, September 28, 1995). The opening length of the structure parallel to the bridge face is 54 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 50 degrees to the opening while the opening-skew-to-roadway is 30 degrees. During the Level I assessment, a scour hole approximately 2 ft deeper than the mean thalweg depth was observed along the upstream right wingwall and a scour hole approximately 1 ft deeper than the mean thalweg depth was observed along the downstream left wingwall. The scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) at the downstream end of the downstream left wingwall, at the upstream end of the upstream right wingwall, at the downstream end of the right abutment, along the entire base length of the downstream right wingwall, along the upstream right bank and along the downstream left bank. A stone wall was noted along the upstream left bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.6 ft. The worst-case contraction scour occurred at the incipient-overtopping discharge. Abutment scour ranged from 15.1 to 16.3 ft along the left abutment and from 7.4 to 9.2 ft along the right abutment. The worst-case abutment scour occurred at the incipient-overtopping and 500-year discharges for the left abutment and at the 500-year discharge for the right abutment. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  10. Level II scour analysis for Bridge 16 (BURKTH00070016) on Town Highway 7, crossing Dish Mill Brook, Burke, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.; Severance, Tim

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure BURKTH00070016 on Town Highway 7 crossing Dish Mill Brook, Burke, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the White Mountain section of the New England physiographic province in northeastern Vermont. The 6.0-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest except on the left bank upstream which is brushland. In the study area, Dish Mill Brook has an incised, sinuous channel with a slope of approximately 0.04 ft/ft, an average channel top width of 40 ft and an average bank height of 6 ft. The channel bed material ranges from sand to boulder with a median grain size (D50) of 94.1 mm (0.309 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 7, 1995, indicated that the reach was stable. The Town Highway 7 crossing of Dish Mill Brook is a 28-ft-long, two-lane bridge consisting of one 24-foot steel-beam span (Vermont Agency of Transportation, written communication, March 24, 1995). The opening length of the structure parallel to the bridge face is 24.8 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 35 degrees to the opening while the computed opening-skew-to-roadway is 35 degrees. A scour hole 1.0 ft deeper than the mean thalweg depth was observed along the left and right abutments during the Level I assessment. In front of the upstream and downstream left wingwalls the scour depth was only 0.5 ft, while in front of the downstream right wingwall it was 0.75 ft and in front of the upstream right wingwall it was 0.3 ft. The scour countermeasures at the site include type-1 stone fill (less than 12 inches diameter) at the downstream end of the right abutment and along the downstream right wingwall. Type-2 stone fill (less than 36 inches diameter) is along the upstream left bank, the upstream and downstream left wingwalls, and at the upstream end of the upstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 0.5 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 6.7 to 9.3 ft. The worst-case abutment scour occurred at the 500-year discharge for the left abutment and at the incipient road-overtopping discharge for the right abutment. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  11. Level II scour analysis for Bridge 15 (BOLTTH00150015) on Town Highway 15, crossing Joiner Brook, Bolton, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.; Wild, Emily C.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure BOLTTH00150015 on Town Highway 15 crossing Joiner Brook, Bolton, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Green Mountain section of the New England physiographic province in north central Vermont. The 9.6-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture (lawn) downstream of the bridge and on the upstream right bank. The surface cover on the upstream left bank is shrub and brushland. In the study area, Joiner Brook has an incised, straight channel with a slope of approximately 0.01 ft/ft, an average channel top width of 61 ft and an average bank height of 7 ft. The channel bed material ranges from gravel to cobble with a median grain size (D50) of 43.6 mm (0.143 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 27, 1996, indicated that the reach was stable. The Town Highway 15 crossing of Joiner Brook is a 39-ft-long, two-lane bridge consisting of one 36-foot concrete tee-beam span (Vermont Agency of Transportation, written communication, November 3, 1995). The opening length of the structure parallel to the bridge face is 34.6 ft. The bridge is supported by nearly vertical, concrete abutments with wingwalls. The channel is skewed approximately 10 degrees to the opening while the opening-skew-to-roadway is zero degrees. A scour hole 1.5 ft deeper than the mean thalweg depth was observed at the downstream end of the right abutment and along the downstream right wingwall during the Level I assessment. A second scour hole 1.2 ft deeper than the mean thalweg depth was observed at the upstream end of the left abutment and along the upstream left wingwall. The left abutment footing is exposed in the area of the scour hole. Scour protection measures at the site included type-1 stone fill (less than 12 inches diameter) at the upstream end of the upstream left wingwall and at the downstream end of the downstream right wingwall and type-2 stone fill (less than 36 inches diameter) along the downstream left bank. There is also type-3 stone fill (less than 48 inches diameter) along the upstream left and right banks. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.8 to 3.5 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 6.9 to 15.1 ft. The worst-case abutment scour occurred at the incipient roadway-overtopping discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results.” Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  12. Level II scour analysis for Bridge 30 (NEWHTH00050030) on Town Highway 5, crossing the New Haven River, New Haven, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.; Wild, Emily C.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure NEWHTH00050030 on Town Highway 5 crossing the New Haven River, New Haven, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (Federal Highway Administration, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D.The site is in the Champlain section of the St. Lawrence Valley physiographic province in west-central Vermont. The 115-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture on the right bank upstream and downstream of the bridge while the immediate banks have dense woody vegetation. The upstream left bank is also pasture. The downstream left bank is forested.In the study area, the New Haven River has an incised, sinuous channel with a slope of approximately 0.01 ft/ft, an average channel top width of 127 ft and an average bank height of 5 ft. The channel bed material ranges from silt to cobble with a median grain size (D50) of 20.4 mm (0.067 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 19, 1996, indicated that the reach was laterally unstable. The stream bends through the bridge and impacts the left bank where there is a cut bank and scour hole.The Town Highway 5 crossing of the New Haven River is a 181-ft-long, two-lane bridge consisting of four 45-ft concrete tee-beam spans (Vermont Agency of Transportation, written communication, December 15, 1995). The opening length of the structure parallel to the bridge face is 175.9 ft. The bridge is supported by vertical, concrete abutments with stone fill spill-through embankments and three concrete piers. The channel is skewed approximately 15 degrees to the opening while the computed opening-skew-to-roadway is 10 degrees.A scour hole 4.5 ft deeper than the mean thalweg depth was observed along the downstream left bank during the Level I assessment. Also observed was a scour hole 1.5 ft deeper than the mean thalweg depth at the upstream end of the middle pier. The only scour protection measure at the site was type-3 stone fill (less than 48 inches diameter) in front of the left and right abutments creating spill through slopes. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E.Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.Contraction scour for all modelled flows ranged from 0.7 to 2.1 ft. The worst-case contraction scour occurred at the 500-year discharge. Left abutment scour ranged from 6.8 to 8.4 ft. The worst-case left abutment scour occurred at the 500-year discharge. Right abutment scour ranged from 11.2 to 14.0 ft. The worst-case right abutment scour occurred at the 500-year discharge. Pier scour ranged from 12.9 to 19.3 ft. The worst-case pier scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  13. Level II scour analysis for Bridge 35, (ANDOVT00110035) on State Route 11, crossing the Middle Branch Williams River, Andover, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.; Wild, Emily C.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ANDOVT00110035 on State Route 11 crossing the Middle Branch Williams River, Andover, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (Federal Highway Administration, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Green Mountain section of the New England physiographic province in south-central Vermont. The 4.65-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest on the left bank and small trees and brush on the right bank upstream and downstream of the bridge. In the study area, the Middle Branch Williams River has an incised, meandering channel with a slope of approximately 0.02 ft/ft, an average channel top width of 57 ft and an average bank height of 4 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 31.4 mm (0.103 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 28, 1996, indicated that the reach was laterally unstable. There are cut-banks upstream and downstream of the bridge and an island in the channel upstream. The State Route 11 crossing of the Middle Branch Williams River is a 28-ft-long, two-lane bridge consisting of one 24-ft concrete tee-beam span (Vermont Agency of Transportation, written communication, March 28, 1995). The opening length of the structure parallel to the bridge face is 23.6 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 45 degrees to the opening while the computed opening-skew-to-roadway is 25 degrees. A scour hole ranging from 1.5 to 1.75 ft deeper than the mean thalweg depth was observed along the upstream left wingwall, the left abutment, and the downstream left wingwall during the Level I assessment. The scour countermeasures at the site included type-1 stone fill (less than 12 inches diameter) at the right road approach upstream and downstream of the bridge and type-2 stone fill (less than 36 inches diameter) at the left road approach upstream and downstream of the bridge. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 2.0 to 4.3 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 14.4 to 16.5 ft at the left abutment and from 6.3 to 8.8 ft at the right abutment. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  14. Level II scour analysis for Bridge 17 (NEWHTH00200017) on Town Highway 20, crossing Little Otter Creek, New Haven, Vermont

    USGS Publications Warehouse

    Wild, Emily C.; Burns, Ronda L.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure NEWHTH00200017 on Town Highway 20 crossing Little Otter Creek, New Haven, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the Champlain section of the St. Lawrence Valley physiographic province in west-central Vermont. The 10.8-mi2 drainage area is in a predominantly rural and wetland basin. In the vicinity of the study site, the surface cover is shrubland on the downstream right overbank. The surface cover of the downstream left overbank, the upstream right overbank and the upstream left overbank is wetland and pasture. In the study area, Little Otter Creek has a meandering channel with a slope of approximately 0.0007 ft/ft, an average channel top width of 97 ft and an average bank height of 5 ft. The channel bed material ranges from silt and clay to cobble. Medium sized silt and clay is the channel material upstream of the approach cross-section and downstream of the exit cross-section. The median grain size (D50) of the silt and clay channel bed material is 1.52 mm (0.005 ft), which was used for contraction and abutment scour computations. From the approach cross-section, under the bridge, and to the exit cross-section, stone fill is the channel bed material. The median grain size (D50) of the stone fill channel bed material is 95.7 mm (0.314 ft). The stone fill median grain size was used solely for armoring computations. The geomorphic assessment at the time of the Level I and Level II site visit on June 11, 1996, indicated that the reach was stable.The Town Highway 20 crossing of Little Otter Creek is a 32-ft-long, two-lane bridge consisting of a 28-ft steel-beam span (Vermont Agency of Transportation, written communication, December 15, 1995). The opening length of the structure parallel to the bridge face is 24.9 ft. The bridge is supported by almost vertical, concrete abutments. The channel is skewed approximately 15 degrees to the opening while the opening-skew-toroadway is zero degrees. The scour countermeasures at the site consisted of type-1 stone fill (less than 12 inches diameter) along the left and right abutments, as well as along the upstream left and right banks. Type-2 stone fill (less than 36 inches diameter) was present along the downstream right bank. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 9.7 to 13.8 ft. The worst-case contraction scour occurred at the 500-year discharge. Left abutment scour ranged from 6.9 to 7.9 ft. Right abutment scour ranged from 10.5 to 11.8 ft. The worst-case left and right abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  15. Level II scour analysis for Bridge 2 (RYEGTH00020002) on Town Highway 2, crossing the Wells River, Ryegate, Vermont

    USGS Publications Warehouse

    Ivanoff, Michael A.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure RYEGTH00020002 on Town Highway 2 crossing the Wells River, Ryegate, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in east-central Vermont. The 75.7-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover consists of cut grass, trees, and brush on the flood plains while the immediate banks have dense woody vegetation. In the study area, the Wells River has an incised, sinuous channel with a slope of approximately 0.006 ft/ft, an average channel top width of 110 ft and an average bank height of 12 ft. The channel bed material ranges from sand to boulder with a median grain size (D50) of 82.3 mm (0.270 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 24, 1995, indicated that the reach was laterally unstable with moderate fluvial erosion and meandering downstream of the bridge. The Town Highway 2 crossing of the Wells River is a 79-ft-long, two-lane bridge consisting of one 75-foot steel-beam span (Vermont Agency of Transportation, written communication, March 27, 1995). The opening length of the structure parallel to the bridge face is 75.1 ft. The bridge is supported by vertical, concrete abutments, the left has a spill-through embankment, with wingwalls. The channel is not skewed to the opening and the opening-skew-to-roadway is zero degrees. A scour hole 3 ft deeper than the mean thalweg depth was observed in the channel from upstream and through the bridge during the Level I assessment. The scour protection counter-measures at the site included type-4 stone fill (less than 60 inches diameter) along the base of the left abutment forming a spill-through embankment. There was also type-2 stone fill (less than 36 inches diameter) along the entire base length of the upstream right wingwall, the upstream right bank and downstream left bank. There was a stone wall along the upstream left bank extending 130 ft from the bridge. In addition there was type-1 stone fill (less than 12 inches diameter) along the downstream right bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was zero. Abutment scour ranged from 7.1 to 11.4 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  16. Level II scour analysis for Bridge 18 (GROTTH00480018) on Town Highway 48, crossing the Wells River Groton, Vermont

    USGS Publications Warehouse

    Striker, Lora K.; Medalie, Laura

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure GROTTH00480018 on Town Highway 48 crossing the Wells River, Groton, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in eastern Vermont. The 53.6-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture on the right bank upstream and the left bank downstream while the surface cover is shrub and brushland along the left bank upstream and the right bank downstream. The immediate banks are vegetated with brush and scattered trees. In the study area, the Wells River has an incised, straight channel with a slope of approximately 0.003 ft/ft, an average channel top width of 69 ft and an average bank height of 7 ft. The channel bed material ranges from sand to cobble with a median grain size (D50) of 66.7 mm (0.219 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 28, 1995, indicated that the reach was stable. The Town Highway 48 crossing of the Wells River is a 38-ft-long, one-lane bridge consisting of one 36-foot steel-beam span (Vermont Agency of Transportation, written communication, March 24, 1995). The opening length of the structure parallel to the bridge face is 33.7 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 0 degrees to the opening and the opening-skew-toroadway is also 0 degrees. Local scour 3.25 ft deeper than the mean thalweg depth was observed underneath the bridge along the left and right abutments during the Level I assessment. In addition, a scour hole extends from 90 ft US to 50 ft DS for a total length of 115 ft with an average scour depth of 2.0 ft. The only scour protection measure at the site was type-2 stone fill (less than 36 inches diameter) along the left bank upstream, along the entire base length of the downstream right wingwall, and along the left and right banks downstream; and type-1 stone fill (less than 12 inches diameter) along the entire base length of the upstream left wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was 0.0 ft. Abutment scour ranged from 2.0 to 2.3 ft at the left abutment and 8.8 to 14.6 ft at the right abutment. The worst-case abutment scour occurred at the 500-year discharge at the right abutment. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  17. Level II scour analysis for Bridge 34 (WWINTH00370034) on Town Highway 37, crossing Mill Brook, West Windsor, Vermont

    USGS Publications Warehouse

    Boehmler, Erick M.; Wild, Emily C.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure WWINTH00370034 on Town Highway 37 crossing Mill Brook, West Windsor, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the New England Upland section of the New England physiographic province in east-central Vermont. The 16.6-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture except for the upstream left bank where there is mostly shrubs and brush. In the study area, Mill Brook has a sinuous channel with a slope of approximately 0.003 ft/ ft, an average channel top width of 52 ft and an average bank height of 5 ft. The channel bed material ranges from sand to cobbles with a median grain size (D50) of 43.4 mm (0.142 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 5, 1996, indicated that the reach was laterally unstable. Point bars were observed upstream and downstream of this site. Furthermore, slip failure of the bank material was noted downstream at a cut-bank on the left side of the channel across from a point bar. The Town Highway 37 crossing of Mill Brook is a 37-ft-long, one-lane covered bridge consisting of one 32-foot wood thru-truss span (Vermont Agency of Transportation, written communication, March 23, 1995). The opening length of the structure parallel to the bridge face is 29.6 ft. The bridge is supported by vertical, laid-up stone abutment walls with concrete facing and laid-up stone wingwalls. The channel is skewed approximately 10 degrees to the opening while the opening-skew-to-roadway is zero degrees. A scour hole 1.5 ft deeper than the mean thalweg depth was observed along the right abutment during the Level I assessment. Scour protection measures at the site included type-3 (less than 48 inches diameter) and type-4 (less than 60 inches diameter) stone fill. Type-3 stone fill was observed along the upstream right bank and along the right abutments. Type-4 stone fill was observed at the upstream end of the upstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. There was no contraction scour predicted for any of the modeled flows. Abutment scour at the left abutment ranged from 5.7 to 7.3 ft, while that at the right abutment ranged from 11.6 to 17.7 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results.” Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  18. Level II scour analysis for Bridge 26 (ROYATH00540026) on Town Highway 54, crossing Broad Brook, Royalton, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.; Weber, Matthew A.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ROYATH00540026 on Town Highway 54 crossing Broad Brook, Royalton, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in central Vermont. The 11.9-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover on the left bank upstream and downstream is pasture with trees and brush on the immediate banks. The right bank, upstream and downstream of the bridge, is forested. In the study area, Broad Brook has an incised, sinuous channel with a slope of approximately 0.01 ft/ft, an average channel top width of 37 ft and an average bank height of 4 ft. The channel bed material ranges from sand to boulders with a median grain size (D50) of 66.3 mm (0.218 ft). The geomorphic assessment at the time of the Level I site visit on April 13, 1995 and the Level II site visit on July 11, 1996, indicated that the reach was stable. The Town Highway 54 crossing of Broad Brook is a 29-ft-long, one-lane bridge consisting of one 24-foot steel-beam span with a timber deck (Vermont Agency of Transportation, written communication, March 23, 1995). The opening length of the structure parallel to the bridge face is 23.3 ft. The bridge is supported by a vertical, concrete face laid-up stone abutment with concrete wingwalls on the left and a laid-up stone abutment on the right. The channel is skewed approximately 20 degrees to the opening while the opening-skew-to-roadway is zero degrees. A scour hole 1.0 ft deeper than the mean thalweg depth was observed along the downstream end of the right abutment during the Level I assessment. Also, at the upstream end of the left abutment, the footing is exposed 0.5 ft. The scour protection measures at the site included type-2 stone fill (less than 36 inches diameter) along the upstream left bank, at the upstream end of the upstream left wingwall, along the entire length of the downstream left wingwall, and at the upstream end of the right abutment. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 1.4 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge, which was less than the 100-year discharge. Abutment scour ranged from 2.2 to 7.4 ft on the left and from 14.7 to 17.7 ft on the right. The worst-case abutment scour occurred at the incipient roadway-overtopping discharge for the left and at the 500-year discharge for the right. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  19. Level II scour analysis for Bridge 40 (ROCKTH00140040) on Town Highway 14, crossing the Williams River, Rockingham, Vermont

    USGS Publications Warehouse

    Burns, Ronda L.; Wild, Emily C.

    1998-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure ROCKTH00140040 on Town Highway 14 crossing the Williams River, Rockingham, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D. The site is in the New England Upland section of the New England physiographic province in southeastern Vermont. The 99.2-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture downstream of the bridge. Upstream of the bridge, the left bank is forested and the right bank is suburban. In the study area, the Williams River has an incised, sinuous channel with a slope of approximately 0.005 ft/ft, an average channel top width of 154 ft and an average bank height of 11 ft. The channel bed material ranges from silt and clay to cobble with a median grain size (D50) of 45.4 mm (0.149 ft). The geomorphic assessment at the time of the Level I and Level II site visit on September 4, 1996, indicated that the reach was stable. The Town Highway 14 crossing of the Williams River is a 106-ft-long, one-lane covered bridge consisting of two steel-beam spans with a maximum span length of 73 ft (Vermont Agency of Transportation, written communication, April 6, 1995). The opening length of the structure parallel to the bridge face is 94.5 ft. The bridge is supported by a vertical, concrete abutment with wingwalls on the left, a vertical, laid-up stone abutment on the right and a concrete pier. The channel is skewed approximately 10 degrees to the opening while the opening-skew-to-roadway is zero degrees. A scour hole 2.1 ft deeper than the mean thalweg depth was observed towards the left side of the channel under and just downstream of the bridge during the Level I assessment. Scour protection measures at the site included type-1 stone fill (less than 12 inches diameter) at the upstream end of the upstream left wingwall and type-2 stone fill (less than 36 inches diameter) along the upstream left bank and the left abutment. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows was zero ft. Left abutment scour ranged from 13.9 to 19.2 ft. Right abutment scour ranged from 7.0 to 11.7 ft. The worst-case abutment scour occurred at the 500-year discharge. Pier scour ranged from 18.7 to 24.7 ft and the worst case occurred at the incipient roadway-overtopping discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particlesize distribution. It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

  20. Level II scour analysis for Bridge 23 (WALDTH00060023) on Town Highway 6, crossing Stannard Brook, Walden, Vermont

    USGS Publications Warehouse

    Ivanoff, Michael A.; Hammond, Robert E.

    1997-01-01

    This report provides the results of a detailed Level II analysis of scour potential at structure WALDTH00060023 on Town Highway 6 crossing Stannard Brook, Walden, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in eastern Vermont. The 5.61-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the upstream surface cover is shrub and brushland with some trees. The downstream surface cover is forest. In the study area, Stannard Brook has an incised, straight channel with a slope of approximately 0.02 ft/ft, an average channel top width of 54 ft and an average bank height of 9 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 64.0 mm (0.210 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 8, 1995, indicated that the reach was stable. The Town Highway 6 crossing of Stannard Brook is a 59-ft-long (bottom width), two-lane pipe arch culvert consisting of one 22-foot corrugated plate pipe arch span (Vermont Agency of Transportation, written communication, March 28, 1995). The opening length of the structure parallel to the bridge face is 21.9 ft.The pipe arch is supported by vertical, concrete kneewalls. The channel is skewed approximately 10 degrees to the opening while the opening-skew-to-roadway is zero degrees. A scour hole 1.5 ft deeper than the mean thalweg depth was observed along the upstream end of the right kneewall during the Level I assessment. There was also a scour hole 0.5 ft deeper than the mean thalweg depth observed along the downstream end of the left kneewall. The scour counter measures at the site included type-3 stone fill (less than 48 inches diameter) at the upstream and downstream end of the left and right kneewall. There was also type-2 stone fill (less than 36 inches diameter) along the upstream right bank. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and kneewalls). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 2.3 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge, which was greater than the 100-year discharge. Left kneewall scour ranged from 11.7 to 16.8 ft. The worst-case left kneewall scour occurred at the 500-year discharge. Right kneewall scour ranged from 13.7 to 16.7 ft. The worst-case right kneewall scour occurred at the incipient roadway-overtopping discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution. During the Level I survey ledge was discovered at the upstream end of the right abutment. The ledge in the channel may limit scour depths. It is generally accepted that the Froehlich equation (abutment/ kneewall scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

Top