Science.gov

Sample records for stabilization project environmental

  1. Draft environmental assessment -- Test Area North pool stabilization project update

    SciTech Connect

    1997-06-01

    The purpose of this Environmental Assessment (EA) is to update the ``Test Area North Pool Stabilization Project`` EA (DOE/EA-1050) and finding of no significant impact (FONSI) issued May 6, 1996. This update analyzes the environmental and health impacts of a drying process for the Three Mile Island (TMI) nuclear reactor core debris canisters now stored underwater in a facility on the Idaho National Engineering and Environmental Laboratory (INEEL). A drying process was analyzed in the predecision versions of the EA released in 1995 but that particular process was determined to be ineffective and dropped form the Ea/FONSI issued May 6, 1996. The origin and nature of the TMI core debris and the proposed drying process are described and analyzed in detail in this EA. As did the 1996 EA, this update analyzes the environmental and health impacts of removing various radioactive materials from underwater storage, dewatering these materials, constructing a new interim dry storage facility, and transporting and placing the materials into the new facility. Also, as did the 1996 EA, this EA analyzes the removal, treatment and disposal of water from the pool, and placement of the facility into a safe, standby condition. The entire action would take place within the boundaries of the INEEL. The materials are currently stored underwater in the Test Area North (TAN) building 607 pool, the new interim dry storage facility would be constructed at the Idaho Chemical Processing Plant (ICPP) which is about 25 miles south of TAN.

  2. Environmental Assessment -- Test Area North pool stabilization project update

    SciTech Connect

    1997-08-01

    The purpose of this Environmental Assessment (EA) is to update the ``Test Area North Pool Stabilization Project`` EA (DOE/EA-1050) and finding of no significant impact (FONSI) issued May 6, 1996. This update analyzes the environmental and health impacts of a drying process for the Three Mile Island (TMI) nuclear reactor core debris canisters now stored underwater in a facility on the Idaho National Engineering and Environmental Laboratory (INEEL). A drying process was analyzed in the predecision versions of the EA released in 1995 but that particular process was determined to be ineffective and dropped from the EA/FONSI issued May 6, 1996. A new drying process was subsequently developed and is analyzed in Section 2.1.2 of this document. As did the 1996 EA, this update analyzes the environmental and health impacts of removing various radioactive materials from underwater storage, dewatering these materials, constructing a new interim dry storage facility, and transporting and placing the materials into the new facility. Also, as did the 1996 EA, this EA analyzes the removal, treatment and disposal of water from the pool, and placement of the facility into a safe, standby condition. The entire action would take place within the boundaries of the INEEL. The materials are currently stored underwater in the Test Area North (TAN) building 607 pool, the new interim dry storage facility would be constructed at the Idaho Chemical Processing Plant (ICPP) which is about 25 miles south of TAN.

  3. Test Area North Pool Stabilization Project: Environmental assessment

    SciTech Connect

    1996-05-01

    The Test Area North (TAN) Pool is located within the fenced TAN facility boundaries on the Idaho National Engineering Laboratory (INEL). The TAN pool stores 344 canisters of core debris from the March, 1979, Three Mile Island (TMI) Unit 2 reactor accident; fuel assemblies from Loss-of-Fluid Tests (LOFT); and Government-owned commercial fuel rods and assemblies. The LOFT and government owned commercial fuel rods and assemblies are hereafter referred to collectively as {open_quotes}commercial fuels{close_quotes} except where distinction between the two is important to the analysis. DOE proposes to remove the canisters of TMI core debris and commercial fuels from the TAN Pool and transfer them to the Idaho Chemical Processing Plant (ICPP) for interim dry storage until an alternate storage location other than at the INEL, or a permanent federal spent nuclear fuel (SNF) repository is available. The TAN Pool would be drained and placed in an industrially and radiologically safe condition for refurbishment or eventual decommissioning. This environmental assessment (EA) identifies and evaluates environmental impacts associated with (1) constructing an Interim Storage System (ISS) at ICPP; (2) removing the TMI and commercial fuels from the pool and transporting them to ICPP for placement in an ISS, and (3) draining and stabilizing the TAN Pool. Miscellaneous hardware would be removed and decontaminated or disposed of in the INEL Radioactive Waste Management Complex (RWMC). This EA also describes the environmental consequences of the no action alternative.

  4. DEPLOYMENT OF THE GUBKA TECHNOLOGY TO STABILIZE RADIOACTIVE STANDARD SOLUTIONS AT THE FERNALD ENVIRONMENTAL MANAGEMENT PROJECT

    SciTech Connect

    Chipman, N.A.; Knecht, D.A.; Meyer, A.; Aloy, A.; Anshits, A.G.; Tretyakov, A.A.

    2003-02-27

    This paper describes the deployment of the Gubka technology to stabilize liquid technical standards at the Fernald Environmental Management Project. Gubka, an open-cell glass crystalline porous material, was developed by a joint research program of Russian Institutes at St. Petersburg, Krasnoyarsk, and Zheleznogorsk and the Idaho National Engineering and Environmental Laboratory. Gubka technology can be applied in an active or a passive method to stabilize a solution. In both methods the result is the same, and the dried components of the solution are sorbed in the pores of the Gubka block while the liquid phase is evaporated. In this deployment Gubka blocks were passively floated in the solutions at ambient conditions. As the solutions evaporated, the non-volatile components were sorbed in the pores of the Gubka blocks. The waste-loaded Gubka blocks have been packaged for transportation and disposal at the Nevada Test site within an existing waste category.

  5. Spray combustion stability project

    NASA Technical Reports Server (NTRS)

    Jeng, San-Mou; Litchford, Ron J.

    1992-01-01

    This report summarizes research activity on the Spray Combustion Stability Project, characterizes accomplishments and current status, and discusses projected future work. The purpose is to provide a concise conceptual overview of the research effort to date so the reader can quickly assimilate the gist of the research results and place them within the context of their potential impact on liquid rocket engine design technology.

  6. Environmental Assessment for Slope Stabilization Projects at Fort MacArthur, San Pedro, California

    DTIC Science & Technology

    2012-01-01

    dewatering, earthwork, structural stabilization, and material strengthening. Page 2 of 2 Alternatives Considered: The Alternative One (Proposed Action) and a...The slopes consist mainly of fill material , so it is unlikely that archaeological resources are located within the non-native soils. An...Temporary road closures may be necessary during stabilization to allow construction equipment room to operate, while maintaining a safe perimeter

  7. Spray combustion stability project

    NASA Technical Reports Server (NTRS)

    Jeng, San-Mou; Litchford, Ron J.

    1990-01-01

    This report summarizes research activity on the Spray Combustion Stability Project, characterizes accomplishments and current status, and discusses projected future work. The purpose is to provide a concise conceptual overview of the research effort so the reader can quickly assimilate the gist of the research results and place them within the context of their potential impact on liquid rocket engine design technology. Therefore, this report does not elaborate on many of the detailed technical aspects of the research program.

  8. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-01-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source Terms, Environmental Transport, Environmental Monitoring Data, Demography, Food Consumption, and Agriculture, and Environmental Pathways and Dose Estimates.

  9. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1991-01-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source terms; environmental transport environmental monitoring data; demographics, agriculture, food habits; environmental pathways and dose estimates.

  10. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-02-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demography, food consumption, and agriculture; environmental pathways and dose estimates.

  11. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1992-10-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The independent Technical Steering Panel (TSP) provides technical direction. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates):Source Terms, Environmental Transport, Environmental Monitoring Data, Demography, Food Consumption, and Agriculture, and Environmental Pathways and Dose Estimates.

  12. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-06-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Battelle Pacific Northwest Laboratories under contract with the Centers for Disease Control. The independent Technical Steering Panel (TSP) provides technical direction. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demography, food consumption, and agriculture; environmental pathways and dose estimates.

  13. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Finch, S.M.

    1990-09-01

    This monthly report summarizes the technical progress and project status for the Hanford Environmental Dose Reconstruction (HEDR) Project being conducted at the Pacific Northwest Laboratory (PNL) under the direction of a Technical Steering Panel (TSP). The TSP is composed of experts in numerous technical fields related to this project and represents the interests of the public. The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms, environmental transport, environmental monitoring data, demographics, agriculture, food habits, environmental pathways and dose estimates. 3 figs.

  14. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1991-01-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The TSP consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included are appointed technical members representing the states of Oregon and Washington, a representative of Native American tribes, and an individual representing the public. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on human (dose estimates): Source Terms; Environmental Transport; Environmental Monitoring Data; Demographics, Agriculture, Food Habits and; Environmental Pathways and Dose Estimates.

  15. Environmental Assessment Lakeview Geothermal Project

    SciTech Connect

    Treis, Tania

    2012-04-30

    The Town of Lakeview is proposing to construct and operate a geothermal direct use district heating system in Lakeview, Oregon. The proposed project would be in Lake County, Oregon, within the Lakeview Known Geothermal Resources Area (KGRA). The proposed project includes the following elements: Drilling, testing, and completion of a new production well and geothermal water injection well; construction and operation of a geothermal production fluid pipeline from the well pad to various Town buildings (i.e., local schools, hospital, and Lake County Industrial Park) and back to a geothermal water injection well. This EA describes the proposed project, the alternatives considered, and presents the environmental analysis pursuant to the National Environmental Policy Act. The project would not result in adverse effects to the environment with the implementation of environmental protection measures.

  16. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    McMakin, A.H.; Cannon, S.D.; Finch, S.M.

    1992-07-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The TSP consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included are appointed technical members representing the states of Oregon, Washington, and Idaho, a representative of Native American tribes, and an individual representing the public. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): Source terms, environmental transport, environmental monitoring data, demography, food consumption, and agriculture, and environmental pathways and dose estimates. Progress is discussed.

  17. ENVIRONMENTAL EVALUATION FOR UTILIZATION OF ASH IN SOIL STABILIZATION

    SciTech Connect

    David J. Hassett; Loreal V. Heebink

    2001-08-01

    The Minnesota Pollution Control Agency (MPCA) approved the use of coal ash in soil stabilization, indicating that environmental data needed to be generated. The overall project goal is to evaluate the potential for release of constituents into the environment from ash used in soil stabilization projects. Supporting objectives are: (1) To ensure sample integrity through implementation of a sample collection, preservation, and storage protocol to avoid analyte concentration or loss. (2) To evaluate the potential of each component (ash, soil, water) of the stabilized soil to contribute to environmental release of analytes of interest. (3) To use laboratory leaching methods to evaluate the potential for release of constituents to the environment. (4) To facilitate collection of and to evaluate samples from a field runoff demonstration effort. The results of this study indicated limited mobility of the coal combustion fly ash constituents in laboratory tests and the field runoff samples. The results presented support previous work showing little to negligible impact on water quality. This and past work indicates that soil stabilization is an environmentally beneficial CCB utilization application as encouraged by the U.S. Environmental Protection Agency. This project addressed the regulatory-driven environmental aspect of fly ash use for soil stabilization, but the demonstrated engineering performance and economic advantages also indicate that the use of CCBs in soil stabilization can and should become an accepted engineering option.

  18. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Finch, S.M.

    1990-01-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates). The Source Terms Task develops estimates of radioactive emissions from Hanford facilities since 1944. The Environmental Transport Task reconstructs the movement of radioactive materials from the areas of release to populations. The Environmental Monitoring Data Task assembles, evaluates, and reports historical environmental monitoring data. The Demographics, Agriculture, Food Habits Task develops the data needed to identify the populations that could have been affected by the releases. In addition to population and demographic data, the food and water resources and consumption patterns for populations are estimated because they provide a primary pathway for the intake of radionuclides. The Environmental Pathways and Dose Estimates Task use the information produced by the other tasks to estimate the radiation doses populations could have received from Hanford radiation. Project progress is documented in this monthly report, which is available to the public. 3 figs., 3 tabs.

  19. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Finch, S. M.; McMakin, A. H.

    1991-09-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation dose that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into five technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (i.e., dose estimates). The Source Terms Task develops estimates of radioactive emissions from Hanford facilities since 1944. The Environmental Transport Task reconstructs the movements of radioactive particles from the areas of release to populations. The Environmental Monitoring Data Task assemblies, evaluates and reports historical environmental monitoring data. The Demographics, Agriculture and Food Habits Task develops the data needed to identify the populations that could have been affected by the releases. The Environmental Pathways and Dose Estimates Task used the information derived from the other Tasks to estimate the radiation doses individuals could have received from Hanford radiation. This document lists the progress on this project as of September 1991. 3 figs., 2 tabs.

  20. Summation by parts, projections, and stability

    NASA Technical Reports Server (NTRS)

    Olsson, Pelle

    1993-01-01

    We have derived stability results for high-order finite difference approximations of mixed hyperbolic-parabolic initial-boundary value problems (IBVP). The results are obtained using summation by parts and a new way of representing general linear boundary conditions as an orthogonal projection. By slightly rearranging the analytic equations, we can prove strict stability for hyperbolic-parabolic IBVP. Furthermore, we generalize our technique so as to yield strict stability on curvilinear non-smooth domains in two space dimensions. Finally, we show how to incorporate inhomogeneous boundary data while retaining strict stability. Using the same procedure one can prove strict stability in higher dimensions as well.

  1. Hanford Environmental Dose Reconstruction Project: Monthly Report

    SciTech Connect

    Finch, S.M.

    1990-07-01

    This monthly report summarizes the technical progress and project status for the Hanford Environmental Dose Reconstruction (HEDR) Project being conducted at the Pacific Northwest Laboratory (PNL) under the direction of a Technical Steering Panel (TSP). The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source Terms, Environmental Transport, Environmental Monitoring Data, Demographics, Agriculture, Food Habits, and Environmental Pathways and Dose Estimates. 3 figs.

  2. The Environmental Education through Filmmaking Project

    ERIC Educational Resources Information Center

    Harness, Hallie; Drossman, Howard

    2011-01-01

    The environmental education through filmmaking project, a case study at an alternative US public high school, investigates environmental literacies of "at-risk" students who produced two short documentary films, one on recycling and one on water conservation. The filmmaking project sought to promote students' awareness of environmental issues and…

  3. Environmental assessment: The Eden project

    NASA Astrophysics Data System (ADS)

    Roza, Christodoulaki

    Non domestic buildings account for about one-sixth of the U.K.'s entire C02 emissions and one-third of the building related ones 2 . Their proportion of energy consumption, particularly electricity, has also been growing 2 . New buildings are not necessarily better, with energy use often proving to be much higher than their designers anticipated 2 . Annual C02 emissions of two- and sometimes three- times design expectations are far from unusual, leaving a massive credibility gap 2 . These and other global environmental and human health related concerns have motivated an increasing number of designers, developers and building users to pursue more environmentally sustainable designs and construction strategies 5 . However, these buildings can be difficult to evaluate, since they are large in scale, complex in materials and function and temporally dynamic due to limited service life of building components and changing user requirements 5 . All of these factors make environmental assessment of the buildings challenging. Previous Post Occupancy Review of Buildings and their Engineering (PROBE) building investigations have uncovered serious shortcomings in facilities management, or at least mismatches between a building's management needs and the ability of the occupiers to provide the right level of management 1 . Consequently, large differences between energy performance expectations and outcomes can occur virtually unnoticed, while designers continue to repeat flawed descriptions 2 . This investigation attempts to evaluate the building's operation and to help achieving demonstrable improvements in terms of energy efficiency and occupant satisfaction. The scope of this study is to evaluate the actual environmental performance of a building notable for its advanced design. The Education Resource Centre at the Eden Project was selected to compare design expectations with post occupancy performance. This report contains a small-scale survey of user satisfaction with the

  4. Hanford Environmental Dose Reconstruction Project monthly report

    SciTech Connect

    Finch, S.M.

    1991-10-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doeses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source terms; environmental transport; environmental monitoring data; demographics, agriculture, food habits; environmental pathways and dose estimates.

  5. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-03-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source Terms, Environmental Transport, Environmental Monitoring Data, Demography, Food Consumption, and Agriculture, and Environmental Pathways and Dose Estimates.

  6. Hanford Environmental Dose Reconstruction Project. Monthly report

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1992-10-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The independent Technical Steering Panel (TSP) provides technical direction. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates):Source Terms, Environmental Transport, Environmental Monitoring Data, Demography, Food Consumption, and Agriculture, and Environmental Pathways and Dose Estimates.

  7. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.

    1990-05-01

    This monthly report summarizes the technical progress and project status for the Hanford Environmental Dose Reconstruction (HEDR) Project being conducted at Pacific Northwest Laboratory (PNL) under the direction of a Technical Steering Panel (TSP). The TSP is composed of experts in numerous technical fields related to this project and represents the interests of the public. The US Department of Energy (DOE) funds the project. The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks address each of the primary steps in the path from radioactive releases to dose estimates source terms, environmental transport, environmental monitoring data, demographics, agriculture, and food habits, and environmental pathways and dose estimates.

  8. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.

    1990-10-01

    This monthly report summarizes the technical progress and project status for the Hanford Environmental Dose Reconstruction (HEDR) Project being conducted at the Pacific Northwest Laboratory (PNL) under the direction of a Technical Steering Panel (TSP). The TSP is composed of experts in numerous technical fields related to this project and represents the interests of the public. The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms, environmental transport, environmental monitoring data, demographics, agriculture, food habits, and environmental pathways and dose estimates. 3 figs., 3 tabs.

  9. Environmental projects. Volume 7: Environmental resources document

    NASA Technical Reports Server (NTRS)

    Kushner, Len; Kroll, Glenn

    1988-01-01

    The Goldstone Deep Space Communications Complex (GDSCC) in Barstow, California, is part of the NASA Deep Space Network, one of the world's largest and most sensitive scientific telecommunications and radio navigation networks. Goldstone is managed, directed and operated by the Jet Propulsion Laboratory of Pasadena, California. The GDSCC includes five distinct operational sites: Echo, Venus, Mars, Apollo, and Mojave Base. Within each site is a Deep Space Station (DPS), consisting of a large dish antenna and its support facilities. As required by NASA directives concerning the implementation of the National Environmental Policy Act, each NASA field installation is to publish an Environmental Resources Document describing the current environment at the installation, including any adverse effects that NASA operations may have on the local environment.

  10. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1991-04-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from released to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demographics, agriculture, food habits; and, environmental pathways and dose estimates.

  11. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.

    1991-07-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source terms; environmental transport; environmental monitoring data; demographics, agriculture, food habits; and environmental pathways and dose estimates. 2 figs., 2 tabs.

  12. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Dennis, B.S.

    1990-04-01

    This monthly report summarizes the technical progress and project status for the Hanford Environmental Dose Reconstruction (HEDR) Project being conducted at Pacific Northwest Laboratory (PNL) under the direction of a Technical Steering Panel (TSP). The project is divided into the following technical tasks. These tasks address each of the primary steps in the path from radioactive releases to dose estimates: source terms, environmental transport, environmental monitoring data, demographics, agriculture, and food habits, and environmental pathways and dose estimates. The source terms task will develop estimates for radioactive emissions from Hanford facilities since 1944. These estimates will be based on historical measurements and production information. 1 fig., 1 tab.

  13. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.

    1990-01-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demographics; agriculture; food habits; and environmental pathways and dose estimates. 3 figs.

  14. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1991-05-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source Terms, Environmental Transport, Environmental Monitoring Data, Demographics, Agriculture, Food Habits, Environmental Pathways and Dose Estimates. 2 figs., 1 tab.

  15. Hanford Environmental Dose Reconstruction Project monthly report

    SciTech Connect

    Finch, S.M.

    1990-12-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have been have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demographics, agriculture, food habits; and environmental pathways and dose estimates. 3 figs., 3 tabs.

  16. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.

    1990-06-01

    This monthly report summarizes the technical progress and project status for the Hanford Environmental Dose Reconstruction (HEDR) Project being conducted at Pacific Northwest Laboratory (PNL) under the direction of a Technical Steering Panel (TSP). The TSP is composed of experts in numerous technical fields related to this project and represents the interests of the public. The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is divided into technical tasks which address each of the primary steps in the path from radioactive releases to dose estimates: source terms, environmental transport, environmental monitoring data, demographics, agriculture, and food habits, and environmental pathways and dose estimates.

  17. Environmental projects. Volume 3: Environmental compliance audit

    NASA Technical Reports Server (NTRS)

    1987-01-01

    The Goldstone Deep Space Communications Complex is part of NASA's Deep Space Network, one of the world's largest and most sensitive scientific telecommunications and radio navigation networks. Activities at Goldstone are carried out in support of six large parabolic dish antennas. In support of the national goal of the preservation of the environment and the protection of human health and safety, NASA, JPL and Goldstone have adopted a position that their operating installations shall maintain a high level of compliance with Federal, state, and local laws governing the management of hazardous substances, abestos, and underground storage tanks. A JPL version of a document prepared as an environmental audit of Goldstone operations is presented. Both general and specific items of noncompliance at Goldstone are identified and recommendations are provided for corrective actions.

  18. Project Management Plan for the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Shipler, D.B.

    1992-03-01

    This Project Management Plan (PMP) describes the approach that will be used to manage the Hanford Environmental Dose Reconstruction (HEDR) Project. The plan describes the management structure and the technical and administrative control systems that will be used to plan and control the HEDR Project performance. The plan also describes the relationship among key project participants: Battelle, the Centers for Disease Control (CDC), and the Technical Steering Panel (TSP).

  19. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.

    1991-03-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The project is divided into the technical tasks which correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms; environmental transport; environment monitoring data; demographics, agriculture, food habits; and environmental pathways and dose estimates. 3 figs., 2 tabs.

  20. Environmental stability of intercalated graphite fibers

    NASA Technical Reports Server (NTRS)

    Gaier, J. R.; Jaworske, D. A.

    1985-01-01

    Graphite fibers intercalated with bromine, iodine monochloride, ferric chloride, and cupric chloride were subjected to stability tests under four environments which are encountered by engineering materials in the aerospace industry: ambient laboratory conditions, as would be experienced during handling operations and terrestrial applications; high vacuum, as would be experienced in space applications; high humidity, as would be experienced in marine applications; and high temperature, as would be experienced in some processing steps and applications. Monitoring the resistance of the fibers at ambient laboratory conditions revealed that only the ferric chloride intercalated fibers were unstable, due to absorption of water from the air. All four types of intercalated fibers were unstable, due to absorption of water from the air. All four types of intercalated fibers were stable for long periods under high vacuum. Ferric chloride, cupric chloride, and iodine monochloride intercalated fibers were sensitive to high humidity conditions. All intercalated fibers began to degrade above 250 C. The order of their thermal stability, from lowest to highest, was cupric chloride, iodine monochloride, bromine, and ferric chloride. Of the four types of intercalated fibers tested, the bromine intercalated fibers appear to have the most potential for application, based on environmental stability.

  1. Environmental Control Unit Harness Project

    NASA Technical Reports Server (NTRS)

    Oliva-Buisson, Yvette J.

    2014-01-01

    Testing four new Environmental Control Unit Harnesses for improved user comfort during SCAPE operations. Phase I, testing in a lab environment, Phase II will continue testing the best candidates in a field environment.

  2. School Yard Environmental Projects: A Planning Primer.

    ERIC Educational Resources Information Center

    Megalos, Mark A.; And Others

    This guide describes how to establish successful trails, outdoor classrooms, or other environmental education improvements on rural and urban school grounds. Teachers are encouraged to promote the environmental project as a solution to an existing problem and to include all parties and stakeholders that can benefit from a coordinated environmental…

  3. Environmental audit: West Valley Demonstration Project

    SciTech Connect

    Not Available

    1992-01-01

    This report documents the results of the Environmental Audit of West Valley Demonstration Project (WVDP) located in West Valley, New York. The WVDP Environmental Audit was conducted from July 29 through August 16, 1991, by the Office of Environmental Audit (EH-24). This Audit evaluated environmental programs and activities at WVDP as well as the overall environmental management system. The scope of the Environmental Audit was comprehensive, addressing environmental media and Federal, state, and local regulations, with the exception of the National Environmental Policy Act (NEPA). Also addressed were DOE Orders, WVDP 1989 ES&H Assessment Action Plan, formalized facility or program operating procedures, and BMPS. The technical disciplines addressed by the Audit were: Air; Surface Water; Soils, Sediment and Biota; Groundwater; Waste Management; Toxic and Chemical Materials; Radiation; Quality Assurance; and Inactive Waste Sites. In addition, the Audit included a review of environmental management programs within the West Valley Project Office (WVPO). West Valley Nuclear Services (WVNS), and Subcontractor organizations. The effectiveness of environmental monitoring programs was a major component of the review conducted within each technical discipline.

  4. Environmental audit: West Valley Demonstration Project

    SciTech Connect

    Not Available

    1992-01-01

    This report documents the results of the Environmental Audit of West Valley Demonstration Project (WVDP) located in West Valley, New York. The WVDP Environmental Audit was conducted from July 29 through August 16, 1991, by the Office of Environmental Audit (EH-24). This Audit evaluated environmental programs and activities at WVDP as well as the overall environmental management system. The scope of the Environmental Audit was comprehensive, addressing environmental media and Federal, state, and local regulations, with the exception of the National Environmental Policy Act (NEPA). Also addressed were DOE Orders, WVDP 1989 ES H Assessment Action Plan, formalized facility or program operating procedures, and BMPS. The technical disciplines addressed by the Audit were: Air; Surface Water; Soils, Sediment and Biota; Groundwater; Waste Management; Toxic and Chemical Materials; Radiation; Quality Assurance; and Inactive Waste Sites. In addition, the Audit included a review of environmental management programs within the West Valley Project Office (WVPO). West Valley Nuclear Services (WVNS), and Subcontractor organizations. The effectiveness of environmental monitoring programs was a major component of the review conducted within each technical discipline.

  5. Hanford Environmental Dose Reconstruction Project. Monthly report

    SciTech Connect

    McMakin, A.H.; Cannon, S.D.; Finch, S.M.

    1992-07-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The TSP consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included are appointed technical members representing the states of Oregon, Washington, and Idaho, a representative of Native American tribes, and an individual representing the public. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): Source terms, environmental transport, environmental monitoring data, demography, food consumption, and agriculture, and environmental pathways and dose estimates. Progress is discussed.

  6. Does environmental stability stimulate species renovation?

    NASA Astrophysics Data System (ADS)

    Casellato, C.; Erba, E.

    2009-04-01

    The Tithonian-Berriasian time interval is characterized by a major calcareous nannoplankton speciation episode: several coccolith and nannolith genera and species first appear and rapidly evolve, reaching a high diversity, abundance, and calcification degree. The history of calcareous nannoplankton indicates that times of accelerated rates of radiations (or extinctions) generally correlate with global changes in the geosphere, hydrosphere and atmosphere suggesting that evolutionary patterns are intimately linked to environmental modifications (Roth, 1989; Bown et al., 2004; Erba, 2006). Nevertheless, the Tithonian-Berriasian interval provides examples of intra- and intergeneric accelerated evolutionary rates (an origination event) during a time period of general environmental stability, in absence of coeval environmental change evidence. The Tithonian - Early Berriasian can be regarded as a "quiet" interval as far as the C cycle is concerned; the _13C curve shows a gradual minor decline after the Oxfordian anomalies and prior to the Valanginian event. The Tithonian-Berriasian speciation episode provides an excellent opportunity to study modo and tempo of calcareous nannoplankton evolution relative to absent environmental change, which is believed to be instrumental for driving biological evolution. Nannofossils have been investigated in sections from the Tethys and Atlantic oceans in order to discriminate among local, regional or global causes, and to verify possible diachroneity in calcareous phytoplankton evolution and/or in response to global changes. Calcareous nannofossil species richness, first and last occurrences and relative abundance were achieved. Different evolution modes have been proposed since Darwin's Evolutionary Theory: Phyletic Gradualism (Darwin, 1859), Punctuated Equilibrium (Gould & Eldredge, 1977) and Punctuated Gradualism (Malmgren et al., 1984). Phyletic gradualism holds that new species arise from slow, steady transformation of populations

  7. Project Management Plan for the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Shipler, D.B.; McMakin, A.H.; Finch, S.M.

    1992-09-01

    This Project Management Plan (PMP) describes the approach being used to manage the Hanford Environmental Dose Reconstruction (HEDR) Project. The plan describes the management structure and the technical and administrative control systems used to plan and control HEDR Project performance. The plan also describes the relationship among key project participants: Battelle, the Centers for Disease control (CDC), and the Technical Steering Panel (TSP). Battelle`s contract with CDC only extends through May 1994 when the key technical work will be completed. There-fore, this plan is focused only on the period during which Battelle is a participant.

  8. Project Management Plan for the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Shipler, D.B.; McMakin, A.H.; Finch, S.M.

    1992-09-01

    This Project Management Plan (PMP) describes the approach being used to manage the Hanford Environmental Dose Reconstruction (HEDR) Project. The plan describes the management structure and the technical and administrative control systems used to plan and control HEDR Project performance. The plan also describes the relationship among key project participants: Battelle, the Centers for Disease control (CDC), and the Technical Steering Panel (TSP). Battelle's contract with CDC only extends through May 1994 when the key technical work will be completed. There-fore, this plan is focused only on the period during which Battelle is a participant.

  9. Hanford Environmental Dose Reconstruction Project Monthly Report

    SciTech Connect

    Finch, S.M.

    1991-02-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The TSP consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included are appointed technical members representing the states of Oregon and Washington, cultural and technical experts nominated by the regional Native American tribes, and an individual representing the public. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demographics, agriculture, food habits; and environmental pathways and dose estimates. Project reports and references used in the reports are made available to the public in a public reading room. Project progress is documented in this monthly report, which is available to the public. 3 figs., 3 tabs.

  10. Environmental Management Assessment of the Fernald Environmental Management Project (FEMP)

    SciTech Connect

    Not Available

    1993-04-01

    This report documents the results of the Environmental Management Assessment performed at the Fernald Environmental Management Project (FEMP) in Fernald, Ohio. During this assessment, the activities conducted by the assessment team included review of internal documents and reports from previous audits and assessments; interviews with US Department of Energy (DOE) and FEMP contractor personnel; and inspection and observation of selected facilities and operations. The onsite portion of the assessment was conducted from March 15 through April 1, 1993, by DOE`s Office of Environmental Audit (EH-24) located within the Office of the Assistant Secretary for Environment, Safety, and Health (EH-1). EH-24 carries out independent assessments of DOE facilities and activities as part of the EH-1 Environment, Safety, and Health (ES&H) Oversight Audit Program. The EH-24 program is designed to evaluate the status of DOE facilities and activities with respect to compliance with Federal, state, and local environmental laws and regulations; compliance with DOE Orders, Guidance and Directives; conformance with accepted industry practices and standards of performance; and the status and adequacy of management systems developed to address environmental requirements. The Environmental Management Assessment of FEMP focused on the adequacy of environmental management systems. Further, in response to requests by the Office of Environmental Restoration and Waste Management (EM) and Fernald Field Office (FN), Quality Assurance and Environmental Radiation activities at FEMP were evaluated from a programmatic standpoint. The results of the evaluation of these areas are contained in the Environmental Protection Programs section in this report.

  11. 1995 project of the year Hanford Environmental compliance project nomination

    SciTech Connect

    Kelly, J.R.

    1996-02-01

    The completion of the Hanford Environmental Compliance (HEC) Project in December 1995 brought to a successful close a long line of major contributions to environmental cleanup. Not since the early days of the Hanford Site during and shortly after World War 11 had such a large group of diverse construction activities, with a common goal, been performed at Hanford. Key to this success was the unique combination of 14 subprojects under the HEC Project which afforded the flexibility to address evolving subproject requirements. This strategy resulted in the accomplishment of the HEC Project stakeholders` objectives on an aggressive schedule, at a $33 million cost savings to the customer. The primary objectives of the HEC Project were to upgrade selected Hanford Site facilities and systems to bring them into compliance with current environmental standards and regulations. The HEC Project contributed significantly towards the Hanford site compliance with Clean Water Act, Resource Conservation and Recovery Act (RCRA) and Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) requirements. It provided, in part, those construction activities required to comply with those requirements in the areas of liquid and solid waste treatment and disposal, waste characterization, and groundwater monitoring.

  12. Hanford Environmental Dose Reconstruction Project monthly report

    SciTech Connect

    McMakin, A.H., Cannon, S.D.; Finch, S.M.

    1992-09-01

    The objective of the Hanford Environmental Dose Reconstruction MDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The TSP consists of experts in envirorunental pathways. epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering. radiation dosimetry. and cultural anthropology. Included are appointed members representing the states of Oregon, Washington, and Idaho, a representative of Native American tribes, and an individual representing the public. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): Source Terms; Environmental Transport; Environmental Monitoring Data Demography, Food Consumption, and Agriculture; and Environmental Pathways and Dose Estimates.

  13. Do environmental projects promote gender equity?

    PubMed

    Joekes, S

    1995-02-01

    In the 1980s, governments and development agencies began to recognize the need to consider gender issues in their environmental and natural resource management programs. First came the understanding that women play a vital role in the management of natural resources and often have a strong traditional and contemporary knowledge of their environment. To exclude them would damage the efficacy of any project. Next, donor agencies came to view women, in their roles as environmental managers, as vulnerable victims of and contributors to environmental degradation. When awareness grew of examples of women successfully fighting to conserve local resources, women were considered important local assets to be used in efforts toward better environmental management. New environmental projects began by asking whether the protected resource was used by men or women in order to target the crucial people. For example, when planning to preserve forests, it is useful to recognize that men typically use wood for construction and fencing, while women use it for cooking fires. It has become increasingly common for women to participate in water and sanitation committees. But good intentions have often been subverted. Community level management of environmental projects does not guarantee female participation. Sometimes involving women means that women do all the physical labor without receiving their fair share of the benefits. In areas where women's property rights are restricted, women will have little authority in resource management. Legal reforms are needed, but they must be complemented at the local level by collective action.

  14. Mounds View Environmental Education Project, Report #1.

    ERIC Educational Resources Information Center

    Budde, Duane

    Prepared for the 1971 National Science Teachers Association (NSTA) Annual Meeting, this collection of ideas, activities, and unit plans from the Mounds View Environmental Education Project would be useful for junior and senior high school teachers and curriculum planners. Content includes: (1) a senior high course outline and daily lesson plans…

  15. Project Approval, Environmental Assessment and Public Participation.

    ERIC Educational Resources Information Center

    Elder, P. S.

    1982-01-01

    Presents a case study of a heavy oil project proposed by Esso Resources Canada Limited at Cold Lake, Alberta, Canada. Focuses on the approval process, environmental and social impact assessments, and public participation. Evaluates the case and makes recommendations concerning the approval process. (DC)

  16. Genetic and Environmental Stability of Neuroticism From Adolescence to Adulthood.

    PubMed

    Nivard, Michel G; Middeldorp, Christel M; Dolan, Conor V; Boomsma, Dorret I

    2015-12-01

    Longitudinal studies of neuroticism have shown that, on average, neuroticism scores decrease from adolescence to adulthood. The heritability of neuroticism is estimated between 0.30 and 0.60 and does not seem to vary greatly as a function of age. Shared environmental effects are rarely reported. Less is known about the role of genetic and environmental influences on the rank order stability of neuroticism in the period from adolescence to adulthood. We studied the stability of neuroticism in a cohort sequential (classical) twin design, from adolescence (age 14 years) to young adulthood (age 32 years). A genetic simplex model that was fitted to the longitudinal neuroticism data showed that the genetic stability of neuroticism was relatively high (genetic correlations between adjacent age bins >0.9), and increased from adolescence to adulthood. Environmental stability was appreciably lower (environmental correlations between adjacent age bins were between 0.3 and 0.6). This low stability was largely due to age-specific environmental variance, which was dominated by measurement error. This attenuated the age-to-age environmental correlations. We constructed an environmental covariance matrix corrected for this error, under the strong assumption that all age-specific environmental variance is error variance. The environmental (co)variance matrix corrected for attenuation revealed highly stable environmental influences on neuroticism (correlations between adjacent age bins were between 0.7 and 0.9). Our results indicate that both genetic and environmental influences have enduring effects on individual differences in neuroticism.

  17. Hanford Environmental Dose Reconstruction Project. Monthly report

    SciTech Connect

    Finch, S. M.; McMakin, A. H.

    1991-09-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation dose that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into five technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (i.e., dose estimates). The Source Terms Task develops estimates of radioactive emissions from Hanford facilities since 1944. The Environmental Transport Task reconstructs the movements of radioactive particles from the areas of release to populations. The Environmental Monitoring Data Task assemblies, evaluates and reports historical environmental monitoring data. The Demographics, Agriculture and Food Habits Task develops the data needed to identify the populations that could have been affected by the releases. The Environmental Pathways and Dose Estimates Task used the information derived from the other Tasks to estimate the radiation doses individuals could have received from Hanford radiation. This document lists the progress on this project as of September 1991. 3 figs., 2 tabs.

  18. Klickitat Cogeneration Project : Final Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration; Klickitat Energy Partners

    1994-09-01

    To meet BPA`s contractual obligation to supply electrical power to its customers, BPA proposes to acquire power generated by Klickitat Cogeneration Project. BPA has prepared an environmental assessment evaluating the proposed project. Based on the EA analysis, BPA`s proposed action is not a major Federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act of 1969 for the following reasons: (1)it will not have a significant impact land use, upland vegetation, wetlands, water quality, geology, soils, public health and safety, visual quality, historical and cultural resources, recreation and socioeconomics, and (2) impacts to fisheries, wildlife resources, air quality, and noise will be temporary, minor, or sufficiently offset by mitigation. Therefore, the preparation of an environmental impact statement is not required and BPA is issuing this FONSI (Finding of No Significant Impact).

  19. A Project-Based Model for Professional Environmental Experience

    ERIC Educational Resources Information Center

    Meehan, Barry; Thomas, Ian

    2006-01-01

    The projects described in this article were designed to provide a real world situation akin to the work of environmental professionals. The projects were conducted with Australian students working on environmental issues in Vietnam. The projects demonstrated that multi-disciplinary teamwork fits well into environmental projects, and importantly…

  20. Hanford environmental dose reconstruction project: Monthly report

    SciTech Connect

    Dennis, B.S.

    1989-02-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The Technical Steering Panel consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included among the members are appointed technical members representing the States of Oregon and Washington, cultural and technical experts nominated by the Indian tribes in the region, and an individual representing the public.

  1. Annual progress Report on research related to our research projectStabilization of Plutonium in Subsurface Environments via Microbial Reduction and Biofilm Formation” funded by the Environmental Remediation Sciences Division (ERSD)

    SciTech Connect

    New, Mary

    2006-06-01

    The overarching goal of this research project is to investigate and optimize the mechanisms for in situ immobilization of Pu species by naturally-occurring bacteria. Specific research objectives are: (a) investigate the mechanism of bacterial accumulation and immobilization of plutonium species by biofilm formation under aerobic conditions and (b) to demonstrate the direct and indirect stabilization of Pu via dissimilatory reduction by Geobacter metallireducens.

  2. Environmental Evaluation of Dust Stabilizer Products

    DTIC Science & Technology

    2007-08-01

    stabilizers may cause some limited toxicity in sediments as a result of ingestion of sediment particles with sorbed product. • Data gaps for these...TR-07-13 ix available stabilizers for which data were available indicated LC50 values ranging from a low of 500 mg/L up to >10,000 mg/L, indicating...precluding their use in arid environments. Ligninsulfonate is highly water soluble, causing erosion and leaching of the lignin during exposure to

  3. Antelope-Fossil Rebuild Project : Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration.

    1992-04-01

    The Columbia Power Cooperative Association (CPCA), Monument, Oregon, proposes to upgrade a 69-kV transmission line in Wasco and Wheeler Counties, Oregon, between the Antelope Substation and the Bonneville Power Administration`s (BPA) Fossil Substation. The project involves rebuilding and reconductoring 23.2 miles of transmission line, including modifying it for future use at 115 kV. Related project activities will include setting new wood pole structures, removing and disposing of old structures, conductors, and insulators, and stringing new conductor, all within the existing right-of-way. No new access roads will be required. A Borrower`s Environmental Report was prepared for the 1992--1993 Work Plan for Columbia Power Cooperative Association in March 1991. This report investigated cultural resources, threatened or endangered species, wetlands, and floodplains, and other environmental issues, and included correspondence with appropriate Federal, state, and local agencies. The report was submitted to the Rural Electrification Administration for their use in preparing their environmental documentation for the project.

  4. Antelope-Fossil Rebuild Project : Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration.

    1992-04-01

    The Columbia Power Cooperative Association (CPCA), Monument, Oregon, proposes to upgrade a 69-kV transmission line in Wasco and Wheeler Counties, Oregon, between the Antelope Substation and the Bonneville Power Administration's (BPA) Fossil Substation. The project involves rebuilding and reconductoring 23.2 miles of transmission line, including modifying it for future use at 115 kV. Related project activities will include setting new wood pole structures, removing and disposing of old structures, conductors, and insulators, and stringing new conductor, all within the existing right-of-way. No new access roads will be required. A Borrower's Environmental Report was prepared for the 1992--1993 Work Plan for Columbia Power Cooperative Association in March 1991. This report investigated cultural resources, threatened or endangered species, wetlands, and floodplains, and other environmental issues, and included correspondence with appropriate Federal, state, and local agencies. The report was submitted to the Rural Electrification Administration for their use in preparing their environmental documentation for the project.

  5. UMTRA Project environmental, health, and safety plan

    SciTech Connect

    Not Available

    1989-02-01

    The basic health and safety requirements established in this plan are designed to provide guidelines to be applied at all Uranium Mill Tailings Remedial Action (UMTRA) Project sites. Specific restrictions are given where necessary. However, an attempt has been made to provide guidelines which are generic in nature, and will allow for evaluation of site-specific conditions. Health and safety personnel are expected to exercise professional judgment when interpreting these guidelines to ensure the health and safety of project personnel and the general population. This UMTRA Project Environmental, Health, and Safety (EH S) Plan specifies the basic Federal health and safety standards and special DOE requirements applicable to this program. In addition, responsibilities in carrying out this plan are delineated. Some guidance on program requirements and radiation control and monitoring is also included. An Environmental, Health, and Safety Plan shall be developed as part of the remedial action plan for each mill site and associated disposal site. Special conditions at the site which may present potential health hazards will be described, and special areas that should should be addressed by the Remedial Action Contractor (RAC) will be indicated. Site-specific EH S concerns will be addressed by special contract conditions in RAC subcontracts. 2 tabs.

  6. Plant ecology. Anthropogenic environmental changes affect ecosystem stability via biodiversity.

    PubMed

    Hautier, Yann; Tilman, David; Isbell, Forest; Seabloom, Eric W; Borer, Elizabeth T; Reich, Peter B

    2015-04-17

    Human-driven environmental changes may simultaneously affect the biodiversity, productivity, and stability of Earth's ecosystems, but there is no consensus on the causal relationships linking these variables. Data from 12 multiyear experiments that manipulate important anthropogenic drivers, including plant diversity, nitrogen, carbon dioxide, fire, herbivory, and water, show that each driver influences ecosystem productivity. However, the stability of ecosystem productivity is only changed by those drivers that alter biodiversity, with a given decrease in plant species numbers leading to a quantitatively similar decrease in ecosystem stability regardless of which driver caused the biodiversity loss. These results suggest that changes in biodiversity caused by drivers of environmental change may be a major factor determining how global environmental changes affect ecosystem stability.

  7. San Francisquito Creek Stabilization at Bonde Weir Project

    EPA Pesticide Factsheets

    Information about the SFBWQP San Francisquito Creek Stabilization at Bonde Weir Project, part of an EPA competitive grant program to improve SF Bay water quality focused on restoring impaired waters and enhancing aquatic resources.

  8. NPOESS Preparatory Project (NPP) Environmental Products

    NASA Astrophysics Data System (ADS)

    Grant, K. D.; Hughes, R.; Andreas, N. S.

    2010-12-01

    The National Oceanic and Atmospheric Administration (NOAA), Department of Defense (DoD), and National Aeronautics and Space Administration (NASA) are jointly acquiring the next-generation weather and environmental satellite system; the National Polar-orbiting Operational Environmental Satellite System (NPOESS). NPOESS replaces the current Polar-orbiting Operational Environmental Satellites (POES) managed by NOAA and the Defense Meteorological Satellite Program (DMSP) managed by the DoD. The NPOESS satellites carry a suite of sensors that collect meteorological, oceanographic, climatological, and solar-geophysical observations of the earth, atmosphere, and space. The ground data processing segment for NPOESS is the Interface Data Processing Segment (IDPS), developed by Raytheon Intelligence and Information Systems. The IDPS processes NPOESS satellite data to provide environmental data products (aka, Environmental Data Records or EDRs) to NOAA and DoD processing centers operated by the United States government. The IDPS will process EDRs beginning with the NPOESS Preparatory Project (NPP) and continuing through the lifetime of the NPOESS system. Northrop Grumman Aerospace Systems Algorithms and Data Products (A&DP) organization is responsible for the algorithms that produce the EDRs, including their quality aspects. Given a launch date for the NPP spacecraft on the near horizon and the need for users to become familiar with NPP environmental products, this paper will provide an overview of all the products generated by the IDPS and provided to NOAA’s Comprehensive Large Array-data Stewardship System (CLASS) for public distribution. It will discuss each of the 25 NPP EDRs in detail, including a description of the EDR, its size, coverage, measurement range, and expected uses.

  9. Single-shell tank interim stabilization project plan

    SciTech Connect

    Ross, W.E.

    1998-05-11

    This project plan establishes the management framework for conduct of the TWRS Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organizational structure, roles, responsibilities, and interfaces; and operational methods. This plan serves as the project executional baseline.

  10. Single Shell Tank (SST) Interim Stabilization Project Plan

    SciTech Connect

    VLADIMIROFF, D.T.; BOYLES, V.C.

    2000-05-22

    This project plan establishes the management framework for the conduct of the CHG Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organization structure, roles, responsibilities, and interfaces; and operational methods. This plan serves as the project executional baseline.

  11. Final rapid reactivation project environmental assessment

    SciTech Connect

    1999-02-10

    The US Department of Energy (DOE) has prepared an environmental assessment (EA) for the Rapid Reactivation Project at Sandia National Laboratories, New Mexico. The EA analyzes the potential effects of a proposal to increase production of neutron generators from the current capability of 600 units per year up to 2,000 units per year. The project would use existing buildings and infrastructure to the maximum extent possible to meet the additional production needs. The increased production levels would necessitate modifications and additions involving a total area of approximately 26,290 gross square feet at Sandia National Laboratories, New Mexico, Technical Area 1. Additional production equipment would be procured and installed. The no-action alternative would be to continue production activities at the current capability of 600 units per year. The EA analyzes effects on health, safety, and air quality, resulting from construction and operation and associated cumulative effects. A detailed description of the proposed action and its environmental consequences is presented in the EA.

  12. Stabilizing a Bicycle: A Modeling Project

    ERIC Educational Resources Information Center

    Pennings, Timothy J.; Williams, Blair R.

    2010-01-01

    This article is a project that takes students through the process of forming a mathematical model of bicycle dynamics. Beginning with basic ideas from Newtonian mechanics (forces and torques), students use techniques from calculus and differential equations to develop the equations of rotational motion for a bicycle-rider system as it tips from…

  13. Bangladesh Agro-Climatic Environmental Monitoring Project

    NASA Technical Reports Server (NTRS)

    Vermillion, C.; Maurer, H.; Williams, M.; Kamowski, J.; Moore, T.; Maksimovich, W.; Obler, H.; Gilbert, E.

    1988-01-01

    The Agro-Climatic Environmental Monitoring Project (ACEMP) is based on a Participating Agency Service Agreement (PASA) between the Agency for International Development (AID) and the National Oceanic and Atmospheric Administration (NOAA). In FY80, the Asia Bureau and Office of Federal Disaster Assistance (OFDA), worked closely to develop a funding mechanism which would meet Bangladesh's needs both for flood and cyclone warning capability and for application of remote sensing data to development problems. In FY90, OFDA provided for a High Resolution Picture Transmission (HRPT) receiving capability to improve their forecasting accuracy for cyclones, flooding and storm surges. That equipment is primarily intended as a disaster prediction and preparedness measure. The ACEM Project was designed to focus on the development applications of remote sensing technology. Through this Project, AID provided to the Bangladesh Government (BDG) the equipment, technical assistance, and training necessary to collect and employ remote sensing data made available by satellites as well as hydrological data obtained from data collection platforms placed in major rivers. The data collected will enable the BDG to improve the management of its natural resources.

  14. Public Scholarship Student Projects for Introductory Environmental Courses

    ERIC Educational Resources Information Center

    Baum, Seth D.; Aman, Destiny D.; Israel, Andrei L.

    2012-01-01

    This paper presents a model project for introductory undergraduate courses that develops students as citizens contributing scholarship to public discussions of environmental issues. In this field-based project, students actively and independently engage with an environmental issue and present their project experience to a relevant public forum. In…

  15. Single-shell tank interim stabilization project plan

    SciTech Connect

    Ross, W.E.

    1998-03-27

    Solid and liquid radioactive waste continues to be stored in 149 single-shell tanks at the Hanford Site. To date, 119 tanks have had most of the pumpable liquid removed by interim stabilization. Thirty tanks remain to be stabilized. One of these tanks (C-106) will be stabilized by retrieval of the tank contents. The remaining 29 tanks will be interim stabilized by saltwell pumping. In the summer of 1997, the US Department of Energy (DOE) placed a moratorium on the startup of additional saltwell pumping systems because of funding constraints and proposed modifications to the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) milestones to the Washington State Department of Ecology (Ecology). In a letter dated February 10, 1998, Final Determination Pursuant to Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement) in the Matter of the Disapproval of the DOE`s Change Control Form M-41-97-01 (Fitzsimmons 1998), Ecology disapproved the DOE Change Control Form M-41-97-01. In response, Fluor Daniel Hanford, Inc. (FDH) directed Lockheed Martin Hanford Corporation (LNMC) to initiate development of a project plan in a letter dated February 25, 1998, Direction for Development of an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan in Support of Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement). In a letter dated March 2, 1998, Request for an Aggressive Single-Shell Tank (SST) Interim Stabilization Completion Project Plan, the DOE reaffirmed the need for an aggressive SST interim stabilization completion project plan to support a finalized Tri-Party Agreement Milestone M-41 recovery plan. This project plan establishes the management framework for conduct of the TWRS Single-Shell Tank Interim Stabilization completion program. Specifically, this plan defines the mission needs and requirements; technical objectives and approach; organizational structure, roles, responsibilities

  16. Environmental Science: 49 Science Fair Projects. Science Fair Projects Series.

    ERIC Educational Resources Information Center

    Bonnet, Robert L.; Keen, G. Daniel

    This book contains 49 science fair projects designed for 6th to 9th grade students. Projects are organized by the topics of soil, ecology (projects in habitat and life cycles), pests and controls (projects in weeds and insects), recycling (projects in resources and conservation), waste products (projects in decomposition), microscopic organisms,…

  17. Environmentally Preferable Coatings for Structural Steel Project

    NASA Technical Reports Server (NTRS)

    Lewis, Pattie L. (Editor)

    2014-01-01

    The Ground Systems Development and Operations (GSDO) Program at NASA John F. Kennedy Space Center (KSC) has the primary objective of modernizing and transforming the launch and range complex at KSC to benefit current and future NASA programs along with other emerging users. Described a the "launch support and infrastructure modernization program" in the NASA Authorization Act of 2010, the GSDO Program will develop and implement shared infrastructure and process improvements to provide more flexible, affordable, and responsive capabilities to a multi-user community. In support of the GSDO Program, the objective of this project is to determine the feasibility of environmentally friendly corrosion resistant coatings for launch facilities and ground support equipment. The focus of the project is corrosion resistance and survivability with the goal to reduce the amount of maintenance required to preserve the performance of launch facilities while reducing mission risk. Number of facilities/structures with metallic structural and non-structural components in a highly corrosive environment. Metals require periodic maintenance activity to guard against the insidious effects of corrosion and thus ensure that structures meet or exceed design or performance life. The standard practice for protecting metallic substrates in atmospheric environments is the application of corrosion protective coating system.

  18. Hanford Environmental Dose Reconstruction Project. Monthly Technical Report, November 1987

    SciTech Connect

    Haerer, H. A.

    1987-11-01

    This monthly report for November 1987 summarizes the technical progress and project status for the Hanford Environmental Dose Reconstruction Project being conducted at Pacific Northwest Laboratory (PNL) under the direction of a Technical Steering Panel (TSP).

  19. Hanford Environmental Dose Reconstruction Project. Monthly report, January 1992

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-05-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source Terms, Environmental Transport, Environmental Monitoring Data, Demography, Food Consumption, and Agriculture, and Environmental Pathways and Dose Estimates.

  20. Hanford Environmental Dose Reconstruction Project monthly report, May 1992

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-08-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These task correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source terms, environmental transport, environmental monitoring data, demography, food consumption, and agriculture, and environmental pathways and dose estimates.

  1. Hanford Environmental Dose Reconstruction Project monthly report, May 1992

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-01-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These task correspond to the path radionuclides followed, from release to impact on humans (dose estimates): Source terms, environmental transport, environmental monitoring data, demography, food consumption, and agriculture, and environmental pathways and dose estimates.

  2. Hanford Environmental Dose Reconstruction Project monthly report, August 1992

    SciTech Connect

    McMakin, A.H.; Cannon, S.D.; Finch, S.M.

    1992-01-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demography; food consumption; and agriculture; and environmental pathway and dose estimates.

  3. Hanford Environmental Dose Reconstruction Project monthly report, August 1992

    SciTech Connect

    McMakin, A.H.; Cannon, S.D.; Finch, S.M.

    1992-09-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demography; food consumption; and agriculture; and environmental pathway and dose estimates.

  4. Hanford Environmental Dose Reconstruction Project monthly report, February 1993

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1993-01-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project Is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): Source Terms; Environmental Transport; Environmental Monitoring Data; Demography, Food Consumption, and Agriculture; and Environmental Pathways and Dose Estimates.

  5. Hanford Environmental Dose Reconstruction Project monthly report, February 1993

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1993-03-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project Is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): Source Terms; Environmental Transport; Environmental Monitoring Data; Demography, Food Consumption, and Agriculture; and Environmental Pathways and Dose Estimates.

  6. Environmental Impact Report, November 15, 1972. Indian Valley Colleges Project.

    ERIC Educational Resources Information Center

    Berg, Ernest H.; Fleming, Dale A.

    A study of the environmental impact of the construction of a second community college on a site adjacent to the City of Novato in Marin County, California, is presented. The five sections of the report are as follows: I. Project Description and Purpose: A. The Proposal; B. Purpose of the Project; C. Need for the Project; D. History of the Project;…

  7. Technology integration project: Environmental Restoration Technologies Department Sandia National Laboratories

    SciTech Connect

    Williams, C.V.; Burford, T.D.; Allen, C.A.

    1996-08-01

    Sandia National Laboratories Environmental Restoration Technologies Department is developing environmental restoration technologies through funding form the US Department of Energy`s (DOE`s) Office of Science and Technology. Initially, this technology development has been through the Mixed Waste Landfill Integrated Demonstration (MWLID). It is currently being developed through the Contaminant Plume containment and Remediation Focus Area, the Landfill Stabilization Focus Area, and the Characterization, Monitoring, and Sensor Cross-Cutting Program. This Technology Integration Project (TIP) was responsible for transferring MWLID-developed technologies for routine use by environmental restoration groups throughout the DOE complex and commercializing these technologies to the private sector. The MWLID`s technology transfer/commercialization successes were achieved by involving private industry in development, demonstration, and technology transfer/commercialization activities; gathering and disseminating information about MWLID activities and technologies; and promoting stakeholder and regulatory involvement. From FY91 through FY95, 30 Technical Task Plans (TTPs) were funded. From these TTPs, the MWLID can claim 15 technology transfer/commercialization successes. Another seven technology transfer/commercialization successes are expected. With the changeover to the focus areas, the TIP continued the technology transfer/commercialization efforts begun under the MWLID.

  8. Uranium Mill Tailings Remedial Action Project 1993 Environmental Report

    SciTech Connect

    Not Available

    1994-10-01

    This annual report documents the Uranium Mill Tailing Remedial Action (UMTRA) Project environmental monitoring and protection program. The UMTRA Project routinely monitors radiation, radioactive residual materials, and hazardous constituents at associated former uranium tailings processing sites and disposal sites. At the end of 1993, surface remedial action was complete at 10 of the 24 designated UMTRA Project processing sites. In 1993 the UMTRA Project office revised the UMTRA Project Environmental Protection Implementation Plan, as required by the US DOE. Because the UMTRA Project sites are in different stages of remedial action, the breadth of the UMTRA environmental protection program differs from site to site. In general, sites actively undergoing surface remedial action have the most comprehensive environmental programs for sampling media. At sites where surface remedial action is complete and at sites where remedial action has not yet begun, the environmental program consists primarily of surface water and ground water monitoring to support site characterization, baseline risk assessments, or disposal site performance assessments.

  9. Longitudinal Stability of Cognitive Ability in the Colorado Adoption Project.

    ERIC Educational Resources Information Center

    Baker, Laura A.; And Others

    1983-01-01

    Measures of general cognitive ability in one- and two-year-old adopted and nonadopted infants and their parents were subjected to path analysis to estimate the contribution of genetic and environmental factors to short-term stability of mental ability. (Author/RH)

  10. Integrated project management plan for the Plutonium Finishing Plant stabilization and deactivation project

    SciTech Connect

    SINCLAIR, J.C.

    1999-05-03

    This document sets forth the plans, organization, and control systems for managing the PFP Stabilization and Deactivation Project, and includes the top level cost and schedule baselines. The project includes the stabilization of Pu-bearing materials, storage, packaging, and transport of these and other nuclear materials, surveillance and maintenance of facilities and systems relied upon for storage of the materials, and transition of the facilities in the PFP Complex.

  11. Genetic and environmental stability differs in reactive and proactive aggression.

    PubMed

    Tuvblad, Catherine; Raine, Adrian; Zheng, Mo; Baker, Laura A

    2009-01-01

    The aim of this study was to examine stability and change in genetic and environmental influences on reactive (impulsive and affective) and proactive (planned and instrumental) aggression from childhood to early adolescence. The sample was drawn from an ongoing longitudinal twin study of risk factors for antisocial behavior at the University of Southern California (USC). The twins were measured on two occasions: ages 9-10 years (N=1,241) and 11-14 years (N=874). Reactive and proactive aggressive behaviors were rated by parents. The stability in reactive aggression was due to genetic and nonshared environmental influences, whereas the continuity in proactive aggression was primarily genetically mediated. Change in both reactive and proactive aggression between the two occasions was mainly explained by nonshared environmental influences, although some evidence for new genetic variance at the second occasion was found for both forms of aggression. These results suggest that proactive and reactive aggression differ in their genetic and environmental stability, and provide further evidence for some distinction between reactive and proactive forms of aggression.

  12. Genetic and Environmental Stability Differs in Reactive and Proactive Aggression

    PubMed Central

    Tuvblad, Catherine; Raine, Adrian; Zheng, Mo; Baker, Laura A.

    2009-01-01

    The aim of this study was to examine stability and change in genetic and environmental influences on reactive (impulsive and affective) and proactive (planned and instrumental) aggression from childhood to early adolescence. The sample was drawn from an ongoing longitudinal twin study of risk factors for antisocial behavior at the University of Southern California (USC). The twins were measured on two occasions: ages 9–10 years (N = 1,241) and 11–14 years (N = 874). Reactive and proactive aggressive behaviors were rated by parents. The stability in reactive aggression was due to genetic and nonshared environmental influences, whereas the continuity in proactive aggression was primarily genetically mediated. Change in both reactive and proactive aggression between the two occasions was mainly explained by nonshared environmental influences, although some evidence for new genetic variance at the second occasion was found for both forms of aggression. These results suggest that proactive and reactive aggression differ in their genetic and environmental stability, and provide further evidence for some distinction between reactive and proactive forms of aggression. PMID:19688841

  13. Kalispell Maintenance Headquarters Project : Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration.

    1991-01-01

    The facilities needed to maintain and repair Bonneville Power Administration (BPA's) electrical equipment in northwest Montana are currently in two locations: A maintenance headquarters at the Kalispell Substation, and a temporary leased facility south of Kalispell. The present situation is not efficient. There is not enough space to accommodate the equipment needed at each site, and coordination and communication between the two sites is difficult. Also, two sites means duplication of equipment and facilities. BPA needs a single, centralized facility that would efficiently accommodate all the area's maintenance activities and equipment. BPA proposes to build a maintenance headquarters facility consisting of 2 to 4 single-story buildings totaling about 35,000 square feet (office spaces and workshop areas); an open-ended vehicle storage building (carport style); a fenced-in storage year; a storage building for flammables, herbicides, and hazardous wastes; and a parking lot. The facility would require developing about 6 to 10 acres of land. Two sites are being considered for the proposed project (see the attached map for locations). This report is the environmental assessment of the two options.

  14. Hanford Environmental Dose Reconstruction Project: Monthly technical report

    SciTech Connect

    Not Available

    1988-05-01

    This monthly report summarizes the technical progress and project status for the Hanford Environmental Dose Reconstruction (HEDR) Project being conducted at Pacific Northwest Laboratory (PNL) under the direction of a Technical Steering Panel (TSP). The TSP is composed of experts in numerous technical fields related to this project and represents the interests of the public. The Department of Energy (DOE) funds the project and represents the interests of the federal government and the public. The organization for the project is outlined.

  15. Hanford Environmental Dose Reconstruction Project. Monthly report, June 1992

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1992-06-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Battelle Pacific Northwest Laboratories under contract with the Centers for Disease Control. The independent Technical Steering Panel (TSP) provides technical direction. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on humans (dose estimates): source terms; environmental transport; environmental monitoring data; demography, food consumption, and agriculture; environmental pathways and dose estimates.

  16. Richland Environmental Restoration Project management action process document

    SciTech Connect

    1996-04-01

    This document is the prescribed means for providing direct input to the US Department of Energy Headquarters regarding the status, accomplishments, strategy, and issues of the Richland Environmental Restoration Project. The project mission, organizational interfaces, and operational history of the Hanford Site are provided. Remediation strategies are analyzed in detail. The document includes a status of Richland Environmental Restoration project activities and accomplishments, and it presents current cost summaries, schedules, and technical baselines.

  17. South Carolina Course Alignment Project: Environmental Scan

    ERIC Educational Resources Information Center

    Educational Policy Improvement Center (NJ1), 2007

    2007-01-01

    An "environmental scan" is designed to identify key issues of policy and practice in an area of interest so that action can be taken. By definition, an environmental scan focuses upon areas of concern. However, the results of an environmental scan are not designed to be either an indictment or endorsement of the current way of doing…

  18. Hanford Environmental Dose Reconstruction Project monthly report, November 1992

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1992-01-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The TSP consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included are appointed members representing the states of Oregon, Washington. and Idaho, a representative of Native American tribes, and an individual representing the public. The project is divided into the following technical tasks: Source terms; environmental transport; environmental monitoring data; demography, food consumption and agriculture; environmental pathways and dose estimates.

  19. Hanford Environmental Dose Reconstruction Project monthly report, November 1992

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1992-12-31

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The TSP consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included are appointed members representing the states of Oregon, Washington. and Idaho, a representative of Native American tribes, and an individual representing the public. The project is divided into the following technical tasks: Source terms; environmental transport; environmental monitoring data; demography, food consumption and agriculture; environmental pathways and dose estimates.

  20. Operational Environmental Monitoring Program Quality Assurance Project Plan

    SciTech Connect

    Perkins, C.J.

    1994-08-01

    This Quality Assurance Project Plan addresses the quality assurance requirements for the activities associated with the preoperational and operational environmental monitoring performed by Westinghouse Hanford Company as it implements the Operational Environmental Monitoring program. This plan applies to all sampling and monitoring activities performed by Westinghouse Hanford Company in implementing the Operational Environmental Monitoring program at the Hanford Site.

  1. Fernald Environmental Management Project 1995 site environmental report summary

    SciTech Connect

    1996-06-01

    This report summarizes the 1995 Site Environmental Report for the Fernald site. It describes the Fernald site mission, exposure pathways, and environmental standards and guidelines. An overview is presented of the impact these activities have on the local environment and public health. Environmental monitoring activities measure and estimate the amount of radioactive and nonradioactive materials that may leave the site and enter the surrounding environment.

  2. The Field Project as a Tool for Teaching Environmental Psychology.

    ERIC Educational Resources Information Center

    Howells, Gary N.

    1978-01-01

    Describes a university class project designed to enable students to translate environmental research into action. Students focused on a conflict between state and county government over solid waste management. Outlines steps involved in such a project and discusses student involvement and the success of the project. (KC)

  3. Mars Exploration Rover (MER) Project Environmental Assurance Program

    NASA Astrophysics Data System (ADS)

    Man, Kin F.; Farguson, Christine T.; Hoffman, Alan R.

    2004-08-01

    A comprehensive prelaunch environmental assurance program was planned and implemented on NASA's Mars Exploration Rover (MER) project. This project consisted of two rovers/spacecraft launched on two separate launch vehicles. The environmental assurance program included assembly/subsystem and system-level testing in the areas of dynamics, thermal, and electromagnetic (EMC), as well as venting/pressure, dust, radiation, and micrometeoroid analyses. Due to the Martian diurnal cycles, the susceptible hardware also underwent thermal cycling qualification of their packaging designs and manufacturing processes. This paper presents a comprehensive summary of the environmental assurance program for the MER project. A series of test and analysis metrics are generated. Selections of the numerous lessons that have been learned from implementation of the MER environmental assurance program are documented in this paper. They include both technical and programmatic lessons that would be helpful in improving implementation of the environmental program for future projects.

  4. Fernald Environmental Management Project 1995 site environmental report

    SciTech Connect

    1996-06-01

    The Fernald site continues to examine the air and liquid pathways as possible routes through which pollutants from past operations and current remedial activities may leave the site. This 1995 Site Environmental Report provides the general public as well as scientists and engineers with the results from the site`s ongoing Environmental Monitoring Program. Also included in this report is information concerning the site`s progress toward achieving full compliance with requirements set forth by DOE, US Environmental Protection Agency (USEPA), and Ohio EPA.

  5. Final report Hanford environmental compliance project 89-D-172

    SciTech Connect

    Kelly, J.R.

    1996-02-08

    The Hanford Environmental Compliance (HEC) Project is unique in that it consisted of 14 subprojects which varied in project scope and were funded from more that one program. This report describes the HEC Project from inception to completion and the scope, schedule, and cost of the individual subprojects. Also provided are the individual subproject Cost closing statements and Project completion reports accompanied by construction photographs and illustrations.

  6. Environmental stability and morphologic variation in the bryozoan Homotrypa obliqua

    SciTech Connect

    Key, M.M. Jr

    1985-01-01

    Bryozoans as colonial organisms permit the separation of environmental and genetic contributions to morphologic variation. Previous analyses attempted to establish the effects of environmental stability on the partitioning of morphologic variation. Regrettably they utilized multiple species in different environments. To test this model definitively, colonies of the Ordovician bryozoan Homotrypa obliqua were sampled from paleoenvironments of different stabilities from Cincinnati. The Corryville and Fairmount beds provided ten colonies on which measures of zooecial shape and spacing on and between monticules were made. ANOVA and discriminant function analysis revealed that colonies from the deeper more stable environment of the Corryville beds exhibit more between colony variation. Colonies from the less stable Fairmount beds show relatively more within colony variation. This difference most likely results from less microenvironmental perturbation and/or greater within genotype developmental regulation in colonies from more stable environments. This is confirmed by correlation coefficient matrices that show biologically expected interdependence between characters only in the Corryville colonies. Thus, the partitioning of morphologic variation is a useful tool for predicting paleoenvironmental stability.

  7. Resource Guide, Wisconsin Environmental Education Inservice Project.

    ERIC Educational Resources Information Center

    Wisconsin State Univ., Superior.

    This interdisciplinary environmental education resource guide is designed for use in the inservice preparation of teachers in environmental education. The guide is developed around nine components: (1) perceptual awareness, (2) conceptual awareness, (3) the phenomena of the natural environment, (4) the phenomena of the man-made environment, (5)…

  8. Overview of the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Shipler, D.B.; Napier, B.A.; Ikenberry, T.A.

    1992-04-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that specific and representative individuals and populations may have received as a result of releases of radioactive materials from historical operations at the Hanford Site. These dose estimates would account for the uncertainties of information regarding facilities operations, environmental monitoring, demography, food consumption and lifestyles, and the variability of natural phenomena. Other objectives of the HEDR Project include: supporting the Hanford Thyroid Disease Study (HTDS), declassifying Hanford-generated information and making it available to the public, performing high-quality, credible science, and conducting the project in an open, public forum. The project is briefly described.

  9. Stability of volatile organics in environmental soil samples. Final report

    SciTech Connect

    Maskarinec, M.P.; Bayne, C.K.; Jenkins, R.A.; Johnson, L.H.; Holladay, S.K.

    1992-11-01

    This report focuses on data generated for the purpose of establishing the stability of 19 volatile organic compounds in environmental soil samples. The study was carried out over a 56 day (for two soils) and a 111 day (for one reference soil) time frame and took into account as many variables as possible within the constraints of budget and time. The objectives of the study were: 1) to provide a data base which could be used to provide guidance on pre-analytical holding times for regulatory purposes; and 2) to provide a basis for the evaluation of data which is generated outside of the currently allowable holding times.

  10. Stability of volatile organics in environmental soil samples

    SciTech Connect

    Maskarinec, M.P.; Bayne, C.K.; Jenkins, R.A.; Johnson, L.H.; Holladay, S.K.

    1992-11-01

    This report focuses on data generated for the purpose of establishing the stability of 19 volatile organic compounds in environmental soil samples. The study was carried out over a 56 day (for two soils) and a 111 day (for one reference soil) time frame and took into account as many variables as possible within the constraints of budget and time. The objectives of the study were: 1) to provide a data base which could be used to provide guidance on pre-analytical holding times for regulatory purposes; and 2) to provide a basis for the evaluation of data which is generated outside of the currently allowable holding times.

  11. Epigenetic regulation of ageing: linking environmental inputs to genomic stability

    PubMed Central

    Benayoun, Bérénice A.; Pollina, Elizabeth A.; Brunet, Anne

    2016-01-01

    Preface Ageing is affected by both genetic and non-genetic factors. Here, we review the chromatin-based epigenetic changes that occur during ageing, the role of chromatin modifiers in modulating lifespan and the importance of epigenetic signatures as biomarkers of ageing. We also discuss how epigenome remodeling by environmental stimuli impacts several aspects of transcription and genomic stability, with important consequences on longevity, and outline epigenetic differences between the ‘mortal soma’ and the ‘immortal germline’. Finally, we discuss the inheritance of ageing characteristics and potential chromatin-based strategies to delay or reverse hallmarks of ageing or age-related diseases. PMID:26373265

  12. Epigenetic regulation of ageing: linking environmental inputs to genomic stability.

    PubMed

    Benayoun, Bérénice A; Pollina, Elizabeth A; Brunet, Anne

    2015-10-01

    Ageing is affected by both genetic and non-genetic factors. Here, we review the chromatin-based epigenetic changes that occur during ageing, the role of chromatin modifiers in modulating lifespan and the importance of epigenetic signatures as biomarkers of ageing. We also discuss how epigenome remodelling by environmental stimuli affects several aspects of transcription and genomic stability, with important consequences for longevity, and outline epigenetic differences between the 'mortal soma' and the 'immortal germ line'. Finally, we discuss the inheritance of characteristics of ageing and potential chromatin-based strategies to delay or reverse hallmarks of ageing or age-related diseases.

  13. Criticality accident alarm system at the Fernald Environmental Management Project

    SciTech Connect

    Marble, R.C.; Brown, T.D.; Wooldridge, J.C.

    1994-12-31

    This paper describes the staus of the Fernald Environmental Management Project (FEMP) criticality alarm system. A new radiation detection alarm system was installed in 1990. The anunciation system, calibration and maintenance, and detector placement is described.

  14. Environmental Report Utah State Prison Geothermal Project

    SciTech Connect

    1980-03-01

    This environmental report assesses the potential impact of developing a geothermal resource for space heating at the Utah State Prison. Wells will be drilled on prison property for production and for injection to minimize reservoir depletion and provide for convenient disposal of cooled fluid. The most significant environmental concerns are the proper handling of drilling muds during well drilling and the disposal of produced water during well testing. These problems will be handled by following currently accepted practices to reduce the potential risks.

  15. Hanford Environmental Dose Reconstruction Project. Monthly report, December 1991

    SciTech Connect

    Finch, S.M.; McMakin, A.H.

    1991-12-31

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by the Pacific Northwest Laboratory (PNL) under the direction of an independent Technical Steering Panel (TSP). The TSP consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included are appointed technical members representing the states of Oregon and Washington, a representative of Native American tribes, and an individual representing the public. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed, from release to impact on human (dose estimates): Source Terms; Environmental Transport; Environmental Monitoring Data; Demographics, Agriculture, Food Habits and; Environmental Pathways and Dose Estimates.

  16. Environmental Studies in the Physical Sciences. Project Reports, Volume 3, The Rachel Carson Project.

    ERIC Educational Resources Information Center

    Tanner, R. Thomas

    This document is the third of seven accompanying volumes included in the Rachel Carson Project. The project attempts to introduce environmental education lessons and units into existing courses of study within a high school rather than to implement environmental education through the introduction of new courses. This volume reports the…

  17. Environmental Studies in Several Science Courses. Project Reports, Volume 4, The Rachel Carson Project.

    ERIC Educational Resources Information Center

    Tanner, R. Thomas

    This document is the fourth of seven accompanying volumes included in the Rachel Carson Project. The project attempts to introduce environmental education lessons and units into existing courses of study within a high school curriculum rather than to implement environmental education through the introduction of new courses. This volume reports the…

  18. Environmental Studies: Five Miscellaneous Reports. Project Reports, Volume 7, The Rachel Carson Project.

    ERIC Educational Resources Information Center

    Tanner, R. Thomas

    This document is the last of seven volumes included in the Rachel Carson Project. The project attempts to introduce environmental education lessons and units into existing courses of study within a high school curriculum rather than to implement environmental education through the introduction of new courses. Included in this volume is a report…

  19. Hellsgate Winter Range : Wildlife Mitigation Project. Preliminary Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration.

    1995-01-01

    The Bonneville Power Administration proposes funding the Hellsgate Winter Range Wildlife Mitigation Project in cooperation with the Colville Convederated Tribes and Bureau of Indian Affairs. This Preliminary Environmental Assessment examines the potential environmental effects of acquiring and managing property for wildlife and wildlife habitat within a large project area. The Propose action is intended to meet the need for mitigation of wildlife and wild life habitat that was adversely affected by the construction of Grand Coulee and Chief Joseph Dams and their reservoirs.

  20. Participatory Planning for Project Sustainability of Environmental Education Projects: A Case Study of the Secondary Teacher Training Environmental Education Project (St[superscript 2]eep) in Zimbabwe

    ERIC Educational Resources Information Center

    Van Ongevalle, Jan; Van Petegem, Peter; Deprez, Steff; Chimbodza, Iris Jane-Mary

    2011-01-01

    Within the first year of the Secondary Teacher Training Environmental Education Project (St[superscript 2]eep) in Zimbabwe, project stakeholders, including lecturers, college administrators, local project coordinators, and donor representatives, expressed concern about the non-sustainability of the project due to its over-reliance on its…

  1. Environmental Technology (Laboratory Analysis and Environmental Sampling) Curriculum Development Project. Final Report.

    ERIC Educational Resources Information Center

    Hinojosa, Oscar V.; Guillen, Alfonso

    A project assessed the need and developed a curriculum for environmental technology (laboratory analysis and environmental sampling) in the emerging high technology centered around environmental safety and health in Texas. Initial data were collected through interviews by telephone and in person and through onsite visits. Additional data was…

  2. A Year-Long Environmental Project for Primary Grades.

    ERIC Educational Resources Information Center

    Abrahamson, Gloria

    Increasing the opportunities for young children to become perceptive of the environment around them is the goal of a year-long environmental project for primary grade students described in this booklet. An environmental encounter approach is adopted, focusing all of one's senses on the particular environment he is experiencing at the moment,…

  3. Environmental Justice Small Grants Program Project Descriptions for 2007

    EPA Pesticide Factsheets

    Project Descriptions for the 2007 award recipients of the Environmental Justice Small Grants Program which is designed to assist recipients in building collaborative partnerships that will help them understand and address the environmental and/or public health issues in their communities.

  4. Environmentally Sound Small-Scale Energy Projects. Guidelines for Planning.

    ERIC Educational Resources Information Center

    Bassan, Elizabeth Ann; Wood, Timothy S., Ed.

    This manual is the fourth volume in a series of publications that provide information for the planning of environmentally sound small-scale projects. Programs that aim to protect the renewable natural resources that supply most of the energy used in developing nations are suggested. Considerations are made for physical environmental factors as…

  5. Environmental Justice Small Grants Program Project Descriptions for 2009

    EPA Pesticide Factsheets

    Project Descriptions for the 2009 award recipients of the Environmental Justice Small Grants Program which is designed to assist recipients in building collaborative partnerships that will help them understand and address the environmental and/or public health issues in their communities.

  6. Environmentally Sound Small-Scale Water Projects. Guidelines for Planning.

    ERIC Educational Resources Information Center

    Tillman, Gus

    This manual is the second volume in a series of publications on community development programs. Guidelines are suggested for small-scale water projects that would benefit segments of the world's urban or rural poor. Strategies in project planning, implementation and evaluation are presented that emphasize environmental conservation and promote…

  7. The Project-Based Learning Approach in Environmental Education

    ERIC Educational Resources Information Center

    Genc, Murat

    2015-01-01

    The purpose of this study is to investigate the effect of project-based learning on students' attitudes toward the environment. In the study that was performed with 39 students who take the "Environmental Education" course, attitude changes toward the environment were investigated in students who developed projects on environmental…

  8. Environmental Projects. Volume 9: Construction of hazardous materials storage facilities

    NASA Technical Reports Server (NTRS)

    1989-01-01

    Activities at the Goldstone Deep Space Communications Complex (GDSCC) are carried out in support of seven parabolic dish antennas. These activities may give rise to environmental hazards. This report is one in a series of reports describing environmental projects at GDSCC. The construction of two hazardous materials and wastes storage facilities and an acid-wash facility is described. An overview of the Goldstone complex is also presented along with a description of the environmental aspects of the GDSCC site.

  9. Trade-off analysis for environmental projects: An annotated bibliography

    SciTech Connect

    Feather, T.D.; Harrington, K.W.; Capan, D.T.

    1995-08-01

    This is a report with an attached annotated bibliography. This study explores the literature for analytical techniques that can support the complex decision-making process associated with Corps of Engineers environmental projects. The literature review focuses on opportunities for using trade-off methodologies and group processes in environmental plan formulation and evaluation. The work was conducted under the Evaluation Framework Work Unit within the Evaluation of Environmental Investments Research Program.

  10. Environmental stability of actively mode locked fibre lasers

    NASA Astrophysics Data System (ADS)

    Hill, Calum H.; Lee, Stephen T.; Reid, Derryck T.; Baili, Ghaya; Davies, John

    2016-10-01

    Lasers developed for defence related applications typically encounter issues with reliability and meeting desired specification when taken from the lab to the product line. In particular the harsh environmental conditions a laser has to endure can lead to difficulties. This paper examines a specific class of laser, namely actively mode-locked fibre lasers (AMLFLs), and discusses the impact of environmental perturbations. Theoretical and experimental results have assisted in developing techniques to improve the stability of a mode-locked pulse train for continuous operation. Many of the lessons learned in this research are applicable to a much broader category of lasers. The AMLFL consists of a fibre ring cavity containing a semiconductor optical amplifier (SOA), an isolator, an output coupler, a circulator, a bandpass filter and a modulator. The laser produces a train of 6-ps pulses at 800 nm with a repetition rate in the GHz regime and a low-noise profile. This performance is realisable in a laboratory environment. However, even small changes in temperature on the order of 0.1 °C can cause a collapse of mode-locked dynamics such that the required stability cannot be achieved without suitable feedback. Investigations into the root causes of this failure were performed by changing the temperature of components that constitute the laser resonator and observing their properties. Several different feedback mechanisms have been investigated to improve laser stability in an environment with dynamic temperature changes. Active cavity length control will be discussed along with DC bias control of the Mach-Zehnder modulator (MZM).

  11. The Environmental Management Project Manager`s Handbook for improved project definition

    SciTech Connect

    1995-02-01

    The United States Department of Energy (DOE) is committed to providing high quality products that satisfy customer needs and are the associated with this goal, DOE personnel must possess the knowledge, skills, and abilities to ensure successful job performance. In addition, there must be recognition that the greatest obstacle to proper project performance is inadequate project definition. Without strong project definition, DOE environmental management efforts are vulnerable to fragmented solutions, duplication of effort, and wastes resources. The primary means of ensuring environmental management projects meet cost and schedule milestones is through a structured and graded approach to project definition, which is the focus of this handbook.

  12. Environmental transformations of silver nanoparticles: impact on stability and toxicity.

    PubMed

    Levard, Clément; Hotze, E Matt; Lowry, Gregory V; Brown, Gordon E

    2012-07-03

    Silver nanoparticles (Ag-NPs) readily transform in the environment, which modifies their properties and alters their transport, fate, and toxicity. It is essential to consider such transformations when assessing the potential environmental impact of Ag-NPs. This review discusses the major transformation processes of Ag-NPs in various aqueous environments, particularly transformations of the metallic Ag cores caused by reactions with (in)organic ligands, and the effects of such transformations on physical and chemical stability and toxicity. Thermodynamic arguments are used to predict what forms of oxidized silver will predominate in various environmental scenarios. Silver binds strongly to sulfur (both organic and inorganic) in natural systems (fresh and sea waters) as well as in wastewater treatment plants, where most Ag-NPs are expected to be concentrated and then released. Sulfidation of Ag-NPs results in a significant decrease in their toxicity due to the lower solubility of silver sulfide, potentially limiting their short-term environmental impact. This review also discusses some of the major unanswered questions about Ag-NPs, which, when answered, will improve predictions about their potential environmental impacts. Research needed to address these questions includes fundamental molecular-level studies of Ag-NPs and their transformation products, particularly Ag(2)S-NPs, in simplified model systems containing common (in)organic ligands, as well as under more realistic environmental conditions using microcosm/mesocosm-type experiments. Toxicology studies of Ag-NP transformation products, including different states of aggregation and sulfidation, are also required. In addition, there is the need to characterize the surface structures, compositions, and morphologies of Ag-NPs and Ag(2)S-NPs to the extent possible because they control properties such as solubility and reactivity.

  13. Project Canada West. Canadian Environmental Concepts.

    ERIC Educational Resources Information Center

    Western Curriculum Project on Canada Studies, Edmonton (Alberta).

    The overall objective of the curriculum development project is to develop a general high school level interdisciplinary course on environment studies. This potential five to ten month course is outlined as follows: ecology, water pollution, air pollution, noise pollution, population, socioeconomic implications, and resource management. The general…

  14. Managing environmental issues during international electric power project development

    SciTech Connect

    Cooper, H.W.

    1998-07-01

    Responsible international project developers most often view environmental matters with quite mixed emotions. Those with whom Dynalytics has worked would certainly never contemplate jeopardizing the health of anyone in the world. But while they want their projects realized, and are willing to implement reasonable requirements, they are often asked to do more than is appropriate, more than is technologically possible, and more than is financially possible. The paper discusses the following: who is in charge of environmental matters; whose environmental standards apply; the role of technology; accelerating timetables and reducing costs; documentation and applications; and post-construction requirements.

  15. International environmental issues and requirements for new power projects

    SciTech Connect

    Newman, J.R.; Maltby, J.H.

    1997-12-31

    The purpose of this presentation was to discuss the emerging role of financial entities in determining environmental requirements for international power projects. The paper outlines the following: emerging conditions; examples of announced privatization energy projects by country; types of government and international financial entity sources; problems for IPPs; similarity and differences between the World Bank and the USEPA; comparison of the international standards and regulations for power plants; recent trends/issues involving international power project approval; and recommendations for understanding/expediting the financial entities` environmental approval process and how to expedite this process.

  16. Plume Mitigation for Mars Terminal Landing: Soil Stabilization Project

    NASA Technical Reports Server (NTRS)

    Hintze, Paul E.

    2014-01-01

    Kennedy Space Center (KSC) has led the efforts for lunar and Martian landing site preparation, including excavation, soil stabilization, and plume damage prediction. There has been much discussion of sintering but until our team recently demonstrated it for the lunar case there was little understanding of the serious challenges. Simplistic sintering creates a crumbly, brittle, weak surface unsuitable for a rocket exhaust plume. The goal of this project is to solve those problems and make it possible to land a human class lander on Mars, making terminal landing of humans on Mars possible for the first time.

  17. Environmental stability of PAH source indices in pyrogenic tars

    SciTech Connect

    Uhler, A.D.; Emsbo-Mattingly, S.D.

    2006-04-15

    Polycyclic aromatic hydrocarbons (PAHs) are widespread environmental contaminants found in soil, sediments, and airborne particulates. The majority of PAHs found in modern soils and sediments arise from myriad anthropogenic petrogenic and pyrogenic sources. Tars and tar products such as creosote produced from the industrial pyrolysis of coal or oil at former manufactured gas plants (MGPs) or in coking retorts are viscous, oily substances that contain significant concentrations of PAH, usually in excess of 30% w/w. Pyrogenic tars and tar products have unique PAH patterns (source signatures) that are a function of their industrial production. Among pyrogenic materials, certain diagnostic ratios of environmentally recalcitrant 4-, 5- and 6-ring PAHs have been identified as useful environmental markers for tracking the signature of tars and petroleum in the environment. The use of selected PAH source ratios is based on the concept that PAHs with similar properties (i.e., molecular weight, partial pressure, solubility, partition coefficients, and biotic/abiotic degradation) will weather at similar rates in the environment thereby yielding stable ratios. The stability of more than 30 high molecular weight PAH ratios is evaluated during controlled studies of tar evaporation and aerobic biodegradation. The starting materials in these experiments consisted of relatively unweathered tars derived from coal and petroleum, respectively. The PAH ratios from these laboratory studies are compared to those measured in PAH residues found in tar-contaminated soils at a former MGP that operated with a carburetted water gas process.

  18. Application of quality assurance standards to environmental projects

    SciTech Connect

    Richardson, T.L.; Lynch, J.E.; Chaudhary, T.B.

    1994-12-31

    Quality assurance (QA) is critical to every environmental project undertaken. While QA appears to be a cut-and-dried subject, it is actually an evolving issue. Environmental projects need high QA standards. The needs of the nuclear industry have driven most QA programs for the last several decades. Mom recently, the internationally accepted ISO-9000 standard, and the more recent E-4 standard (in draft), have been suggested as alternatives to achieving QA for environmental firms. These standards can be successfully integrated and implemented. However, this requires good up-front planning of the program`s purpose and function and commitments by management and staff to make it work. The purpose of this paper is to discuss how various QA standards can be appropriately applied to the demands of environmental projects.

  19. Advanced Coal Conversion Process Demonstration Project. Environmental Monitoring Plan

    SciTech Connect

    Not Available

    1992-04-01

    Western Energy Company (WECO) was selected by the Department of Energy (DOE) to demonstrate the Advanced Coal Conversion Process (ACCP) which upgrades low rank coals into high Btu, low sulfur, synthetic bituminous coal. As specified in the Corporate Agreement, RSCP is required to develop an Environmental Monitoring Plan (EMP) which describes in detail the environmental monitoring activities to be performed during the project execution. The purpose of the EMP is to: (1) identify monitoring activities that will be undertaken to show compliance to applicable regulations, (2) confirm the specific environmental impacts predicted in the National Environmental Policy Act documentation, and (3) establish an information base of the assessment of the environmental performance of the technology demonstrated by the project. The EMP specifies the streams to be monitored (e.g. gaseous, aqueous, and solid waste), the parameters to be measured (e.g. temperature, pressure, flow rate), and the species to be analyzed (e.g. sulfur compounds, nitrogen compounds, trace elements) as well as human health and safety exposure levels. The operation and frequency of the monitoring activities is specified, as well as the timing for the monitoring activities related to project phase (e.g. preconstruction, construction, commissioning, operational, post-operational). The EMP is designed to assess the environmental impacts and the environmental improvements resulting from construction and operation of the project.

  20. Healy Clean Coal Project, Healy, Alaska final Environmental Monitoring Plan

    SciTech Connect

    Not Available

    1994-06-14

    This Environmental Monitoring Plan (EMP) provides the mechanism to evaluate the integrated coal combustion/emission control system being demonstrated by the Healy Clean Coal Project (HCCP) as part-of the third solicitation of the US Department of Energy (DOE) Clean Coal Technology Demonstration Program (CCT-III). The EMP monitoring is intended to satisfy two objectives: (1) to develop the information base necessary for identification, assessment, and mitigation of potential environmental problems arising from replication of the technology and (2) to identify and quantify project-specific and site-specific environmental impacts predicted in the National Environmental Policy Act (NEPA) documents (Environmental Impact Statement and Record of Decision). The EMP contains a description of the background and history of development of the project technologies and defines the processes that will take place in the combustion and spray dryer absorber systems, including the formation of flash-calcined material (FCM) and its use in sulfur dioxide (SO{sub 2}) removal from the flue gases. It also contains a description of the existing environmental resources of the project area. The EMP includes two types of environmental monitoring that are to be used to demonstrate the technologies of the HCCP: compliance monitoring and supplemental monitoring. Compliance monitoring activities include air emissions, wastewater effluents, and visibility. Monitoring of these resources provide the data necessary to demonstrate that the power plant can operate under the required state and federal statutes, regulations, and permit requirements.

  1. Environmental training research project. Final report

    SciTech Connect

    1996-04-01

    Santa Fe Community College serves an area including the city and county of Santa Fe. The population has a high percentage of Hispanics and a Native American population of about 3%. The student body at the college generally reflects that of the service district. The college strives to recruit students from all segments of the population so there is representation among all ethnic and economic groups. The college strives to serve students and the community by offering educational opportunities that meet the needs of both elements and which will lead to gainful employment. Instruction is also offered to meets needs for retraining, upgrades, and personal enlightenment. The college started a hazardous materials management program in the fall of 1991 which has since been renamed environmental management. The purpose of this program is to prepare students for environmental careers, to provide required training such as OSHA HAZWOPER and refresher courses, and to provide educational opportunities that would make the public more environmentally aware. The program content needs to be studied to ensure we`re meeting the needs of the students and the business community. There had not been a significant opportunity to conduct this research.

  2. Griffith Energy Project Final Environmental Impact Statement

    SciTech Connect

    N /A

    1999-04-02

    Griffith Energy Limited Liability Corporation (Griffith) proposes to construct and operate the Griffith Energy Project (Project), a natural gas-fuel, combined cycle power plant, on private lands south of Kingman, Ariz. The Project would be a ''merchant plant'' which means that it is not owned by a utility and there is currently no long-term commitment or obligation by any utility to purchase the capacity and energy generated by the power plant. Griffith applied to interconnect its proposed power plant with the Western Area Power Administration's (Western) Pacific Northwest-Pacific Southwest Intertie and Parker-Davis transmission systems. Western, as a major transmission system owner, needs to provide access to its transmission system when it is requested by an eligible organization per existing policies, regulations and laws. The proposed interconnection would integrate the power generated by the Project into the regional transmission grid and would allow Griffith to supply its power to the competitive electric wholesale market. Based on the application, Western's proposed action is to enter into an interconnection and construction agreement with Griffith for the requested interconnections. The proposed action includes the power plant, water wells and transmission line, natural gas pipelines, new electrical transmission lines and a substation, upgrade of an existing transmission line, and access road to the power plant. Construction of segments of the transmission lines and a proposed natural gas pipeline also require a grant of right-of-way across Federal lands administered by the Bureau of Land Management. Public comments on the Draft EIS are addressed in the Final EIS, including addenda and modifications made as a result of the comments and/or new information.

  3. Domestic environmental requirements, new and projected

    SciTech Connect

    McLean, B.J.

    1997-12-31

    The paper outlines and/or gives data on the following: environmental concerns; goal of Title IV; national SO{sub 2} emissions; reductions in wet sulfate deposition; SO{sub 2} allowance program--benefits and costs; utility NO{sub x} emissions; NO{sub x} compliance options; cost effectiveness of NO{sub x} control; electric power regulations timeline; Clean Air power initiative; what a new approach would look like; and an analysis of NO{sub x} and SO{sub 2} cap and trade scenarios.

  4. Uranium Mill Tailings Remedial Action Project 1994 environmental report

    SciTech Connect

    1995-08-01

    This annual report documents the Uranium Mill Tailings Remedial Action (UMTRA) Project environmental monitoring and protection program. The UMTRA Project routinely monitors radiation, radioactive residual materials, and hazardous constituents at associated former uranium tailings processing sites and disposal sites. At the end of 1994, surface remedial action was complete at 14 of the 24 designated UMTRA Project processing sites: Canonsburg, Pennsylvania; Durango, Colorado; Grand Junction, Colorado; Green River Utah, Lakeview, Oregon; Lowman, Idaho; Mexican Hat, Utah; Riverton, Wyoming; Salt Lake City, Utah; Falls City, Texas; Shiprock, New Mexico; Spook, Wyoming, Tuba City, Arizona; and Monument Valley, Arizona. Surface remedial action was ongoing at 5 sites: Ambrosia Lake, New Mexico; Naturita, Colorado; Gunnison, Colorado; and Rifle, Colorado (2 sites). Remedial action has not begun at the 5 remaining UMTRA Project sites that are in the planning stage. Belfield and Bowman, North Dakota; Maybell, Colorado; and Slick Rock, Colorado (2 sites). The ground water compliance phase of the UMTRA Project started in 1991. Because the UMTRA Project sites are.` different stages of remedial action, the breadth of the UMTRA environmental protection program differs from site to site. In general, sites actively undergoing surface remedial action have the most comprehensive environmental programs for sampling media. At sites where surface remedial action is complete and at sites where remedial action has not yet begun, the environmental program consists primarily of surface water and ground water monitoring to support site characterization, baseline risk assessments, or disposal site performance assessments.

  5. Near Facility Environmental Monitoring Quality Assurance Project Plan

    SciTech Connect

    MCKINNEY, S.M.

    2000-05-01

    This Quality Assurance Project Plan addresses the quality assurance requirements for the activities associated with the preoperational and near-facility environmental monitoring directed by Waste Management Technical Services and supersedes HNF-EP-0538-4. This plan applies to all sampling and monitoring activities performed by Waste Management Technical Services in implementing near-facility environmental monitoring at the Hanford Site. This Quality Assurance Project Plan is required by U.S. Department of Energy Order 5400.1 (DOE 1990) as a part of the Environmental Monitoring Plan (DOE-RL 1997) and is used to define: Environmental measurement and sampling locations used to monitor environmental contaminants near active and inactive facilities and waste storage and disposal sites; Procedures and equipment needed to perform the measurement and sampling; Frequency and analyses required for each measurement and sampling location; Minimum detection level and accuracy; Quality assurance components; and Investigation levels. Near-facility environmental monitoring for the Hanford Site is conducted in accordance with the requirements of U.S. Department of Energy Orders 5400.1 (DOE 1990), 5400.5 (DOE 1993), 5484.1 (DOE 1990), and 435.1 (DOE 1999), and DOE/EH-O173T (DOE 1991). It is Waste Management Technical Services' objective to manage and conduct near-facility environmental monitoring activities at the Hanford Site in a cost-effective and environmentally responsible manner that is in compliance with the letter and spirit of these regulations and other environmental regulations, statutes, and standards.

  6. Environmental stability study of holographic solar spectrum splitting materials

    NASA Astrophysics Data System (ADS)

    Chrysler, Benjamin D.; Ayala Pelaez, Silvana; Wu, Yuechen; Vorndran, Shelby D.; Kostuk, Raymond K.

    2016-09-01

    In this study the impact of outdoor temperature variations and solar illumination exposure on spectral filter material and holographic optical elements is examined. Although holographic components have been shown to be useful for solar spectrum splitting designs, relatively little quantitative data exist to demonstrate the extent to which these materials can withstand outdoor conditions. As researchers seek to investigate practical spectrum splitting designs, the environmental stability of holographic materials should be considered as an important factor. In the experiment presented, two holographic materials, Covestro Bayfol HX photopolymer and dichromated gelatin, and 3M reflective polymer filter materials are exposed to outdoor conditions for a period of several months. The environmental effect on absorption, spectral and angular bandwidth, peak efficiency, and Bragg matching conditions for the holograms are examined. Spectral bandwidth and transmittance of the 3M reflective filter material are also monitored. Holographic gratings are recorded, measured, and mounted on glass substrates and then sealed with a glass cover plate. The test samples are then mounted on a photovoltaic panel to simulate realistic temperature conditions and placed at an outdoor test facility in Tucson, Arizona. A duplicate set of holograms and 3M filter material is stored as a control group and periodically compared over the test period.

  7. Yakima Fisheries Project : Final Environmental Impact Statement.

    SciTech Connect

    United States. Bonneville Power Administration; Washington . Dept. of Fish and Wildlife; Confederated Tribes and Bands of the Yakama Nation, Washington.

    1996-01-01

    BPA proposes to fund several fishery-related activities in the Yakima River Basin. These activities, known as the Yakima Fisheries Project (YFP), would be jointly managed by the State of Washington and the Yakima Indian Nation. The YFP is included in the Northwest Power Planning Council`s (Council`s) fish and wildlife program. The Council selected the Yakima River system for attention because fisheries resources are severely reduced from historical levels and because there is a significant potential for enhancement of these resources. BPA`s proposed action is to fund (1) information gathering on the implementation of supplementation techniques and on feasibility of reintroducing coho salmon in an environment where native populations have become extinct; (2) research activities based on continuous assessment, feedback and improvement of research design and activities ({open_quotes}adaptive management{close_quotes}); and (3) die construction, operation, and maintenance of facilities for supplementing populations of upper Yakima spring chinook salmon. Examined in addition to No Action are two alternatives for action: (1) supplementation of depressed natural populations of upper Yakima spring chinook and (2) that same supplementation plus a study to determine the feasibility of reestablishing naturally spawning population and a significant fall fishery for coho in the Yakima Basin. Alternative 2 is the preferred action. A central hatchery would be built for either alternative, as well as three sites with six raceways each for acclimation and release of spring chinook smolts. Major issues examined in the Revised Draft EIS include potential impacts of the project on genetic and ecological resources of existing fish populations, on water quality and quantity, on threatened and endangered species listed under the Endangered Species Act, and on the recreational fishery.

  8. Acid Pit Stabilization Project (Volume 1 - Cold Testing) and (Volume 2 - Hot Testing)

    SciTech Connect

    G. G. Loomis; A. P. Zdinak; M. A. Ewanic; J. J. Jessmore

    1998-01-01

    During the summer and fall of Fiscal Year 1997, a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Treatability Study was performed at the Idaho National Engineering and Environmental Laboratory. The study involved subsurface stabilization of a mixed waste contaminated soil site called the Acid Pit. This study represents the culmination of a successful technology development effort that spanned Fiscal Years 1994-1996. Research and development of the in situ grout stabilization technique was conducted. Hardware and implementation techniques are currently documented in a patent pending with the United States Patent and Trademark Office. The stabilization technique involved using jet grouting of an innovative grouting material to form a monolith out of the contamination zone. The monolith simultaneously provides a barrier to further contaminant migration and closes voids in the soil structure against further subsidence. This is accomplished by chemical incorporation of contaminants into less soluble species and achieving a general reduction in hydraulic conductivity within the monolith. The grout used for this study was TECT-HG, a relatively dense iron oxide-based cementitious grout. The treatability study involved cold testing followed by in situ stabilization of the Acid Pit. Volume 1 of this report discusses cold testing, performed as part of a ''Management Readiness Assessment'' in preparation for going hot. Volume 2 discusses the results of the hot Acid Pit Stabilization phase of this project. Drilling equipment was specifically rigged to reduce the spread of contamination, and all grouting was performed under a concrete block containing void space to absorb any grout returns. Data evaluation included examination of implementability of the grouting process and an evaluation of the contaminant spread during grouting. Following curing of the stabilized pit, cores were obtained and evaluated for toxicity characteristic leach ing

  9. McMinnville Area Support Transmission Project : Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration.

    1990-01-01

    This document discusses a project to provide continuing reliable electrical service to the McMinnville, Oregon, area. BPA proposes to participate with the City of McMinnville Water and Light Department in constructing a new 230-kilovolt transmission line and substation. BPA has prepared an environmental assessment evaluating the proposed project. Reasons that constructing the line and substation would not cause significant environmental impact include: consistency with local land use plans, consistency of appearance with existing transmission and manufacturing facilities in the area, only slight effect on farmland, and avoidance of wetlands and other environmentally sensitive areas. A finding is included that there is no practicable alternative to locating the project within a 100-year floodplain. 1 fig.

  10. Environmental assessment, expanded Ponnequin wind energy project, Weld County, Colorado

    SciTech Connect

    1999-02-01

    The US Department of Energy (DOE) has considered a proposal from the State of Colorado, Office of Energy Conservation (OEC), for funding construction of the Expanded Ponnequin Wind Project in Weld County, Colorado. OEC plans to enter into a contracting arrangement with Public Service Company of Colorado (PSCo) for the completion of these activities. PSCo, along with its subcontractors and business partners, are jointly developing the Expanded Ponnequin Wind Project. The purpose of this Final Environmental Assessment (EA) is to provide DOE and the public with information on potential environmental impacts associated with the Expanded Ponnequin Wind Energy Project. This EA, and public comments received on it, were used in DOE`s deliberations on whether to release funding for the expanded project under the Commercialization Ventures Program.

  11. Environmental projects. Volume 16: Waste minimization assessment

    NASA Technical Reports Server (NTRS)

    1994-01-01

    The Goldstone Deep Space Communications Complex (GDSCC), located in the MoJave Desert, is part of the National Aeronautics and Space Administration's (NASA's) Deep Space Network (DSN), the world's largest and most sensitive scientific telecommunications and radio navigation network. The Goldstone Complex is operated for NASA by the Jet Propulsion Laboratory. At present, activities at the GDSCC support the operation of nine parabolic dish antennas situated at five separate locations known as 'sites.' Each of the five sites at the GDSCC has one or more antennas, called 'Deep Space Stations' (DSS's). In the course of operation of these DSS's, various hazardous and non-hazardous wastes are generated. In 1992, JPL retained Kleinfelder, Inc., San Diego, California, to quantify the various streams of hazardous and non-hazardous wastes generated at the GDSCC. In June 1992, Kleinfelder, Inc., submitted a report to JPL entitled 'Waste Minimization Assessment.' This present volume is a JPL-expanded version of the Kleinfelder, Inc. report. The 'Waste Minimization Assessment' report did not find any deficiencies in the various waste-management programs now practiced at the GDSCC, and it found that these programs are being carried out in accordance with environmental rules and regulations.

  12. The Effect of Environmental Science Projects on Students' Environmental Knowledge and Science Attitudes

    ERIC Educational Resources Information Center

    Al-Balushi, Sulaiman M.; Al-Aamri, Shamsa S.

    2014-01-01

    The current study explores the effectiveness of involving students in environmental science projects for their environmental knowledge and attitudes towards science. The study design is a quasi-experimental pre-post control group design. The sample was 62 11th-grade female students studying at a public school in Oman. The sample was divided into…

  13. Uranium Mill Tailings Remedial Action Project. 1995 Environmental Report

    SciTech Connect

    1996-06-01

    In accordance with U.S. Department of Energy (DOE) Order 23 1. 1, Environment, Safety and Health Reporting, the DOE prepares an annual report to document the activities of the Uranium Mill Tailings Remedial Action (UMTRA) Project environmental monitoring program. This monitoring must comply with appropriate laws, regulations, and standards, and it must identify apparent and meaningful trends in monitoring results. The results of all monitoring activities must be communicated to the public. The UMTRA Project has prepared annual environmental reports to the public since 1989.

  14. Hanford Environmental Dose Reconstruction Project: Monthly report, May 1989

    SciTech Connect

    Dennis, B.S.

    1989-01-01

    The objective of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation doses that populations could have received from nuclear operations at Hanford since 1944. The project is being managed and conducted by Pacific Northwest Laboratory under the direction of independent Technical Steering Panel. The Technical Steering Panel consists of experts in environmental pathways, epidemiology, surface-water transport, ground-water transport, statistics, demography, agriculture, meteorology, nuclear engineering, radiation dosimetry, and cultural anthropology. Included among the members are appointed technical members representing the States of Oregon and Washington, cultural and technical experts nominated by the Indian tribes in the region, and an individual representing the public.

  15. Near-facility environmental monitoring quality assurance project plan

    SciTech Connect

    McKinney, S.M.

    1997-11-24

    This Quality Assurance Project Plan addresses the quality assurance requirements for the activities associated with the preoperational and near facility environmental monitoring performed by Waste Management Federal Services, Inc., Northwest Operations and supersedes WHC-EP-0538-2. This plan applies to all sampling and monitoring activities performed by waste management Federal Services, Inc., Northwest Operations in implementing facility environmental monitoring at the Hanford Site.

  16. Lower Columbia River Terminal Fisheries Research Project : Final Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration.

    1995-04-01

    This notice announces BPA`S`s decision to fund the Oregon Department of Fish and Wildlife (ODFW), the Washington Department of Fish and Wildlife (WDFW), and the Clatsop Economic Development Committee for the Lower Columbia River Terminal Fisheries Research Project (Project). The Project will continue the testing of various species/stocks, rearing regimes, and harvest options for terminal fisheries, as a means to increase lower river sport and commercial harvest of hatchery fish, while providing both greater protection of weaker wild stocks and increasing the return of upriver salmon runs to potential Zone 6 Treaty fisheries. The Project involves relocating hatchery smolts to new, additional pen locations in three bays/sloughs in the lower Columbia River along both the Oregon and Washington sides. The sites are Blind Slough and Tongue Point in Clatsop County, Oregon, and Grays Bay/Deep River, Wahkiakum County, Washington. The smolts will be acclimated for various lengths of time in the net pens and released from these sites. The Project will expand upon an existing terminal fisheries project in Youngs Bay, Oregon. The Project may be expanded to other sites in the future, depending on the results of this initial expansion. BPA`S has determined the project is not a major Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act (NEPA) of 1969. Therefore, the preparation of an environmental impact statement is not required, and BPA`S is issuing this FONSI.

  17. HEDR model validation plan. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Napier, B.A.; Gilbert, R.O.; Simpson, J.C.; Ramsdell, J.V. Jr.; Thiede, M.E.; Walters, W.H.

    1993-06-01

    The Hanford Environmental Dose Reconstruction (HEDR) Project has developed a set of computational ``tools`` for estimating the possible radiation dose that individuals may have received from past Hanford Site operations. This document describes the planned activities to ``validate`` these tools. In the sense of the HEDR Project, ``validation`` is a process carried out by comparing computational model predictions with field observations and experimental measurements that are independent of those used to develop the model.

  18. Quality assurance project plan for the Chestnut Ridge Fly Ash Pond Stabilization Project at the Oak Ridge Y-12 Plant, Oak Ridge, Tennessee

    SciTech Connect

    1996-07-01

    The Chestnut Ridge Fly Ash Pond Stabilization (CRFAPS) Project will stabilize a 19-m-high (62-ft-high) earthen embankment across Upper McCoy Branch situated along the southern slope of Chestnut Ridge. This task will be accomplished by raising the crest of the embankment, reinforcing the face of the embankment, removing trees from the face and top of the embankment, and repairing the emergency spillway. The primary responsibilities of the team members are: Lockheed Martin Energy Systems, Inc., (Energy Systems) will be responsible for project integration, technical support, Title 3 field support, environmental oversight, and quality assurance (QA) oversight of the project; Foster Wheeler Environmental Corporation (FWENC) will be responsible for design and home office Title 3 support; MK-Ferguson of Oak Ridge Company (MK-F) will be responsible for health and safety, construction, and procurement of construction materials. Each of the team members has a QA program approved by the US Department of Energy (DOE) Oak Ridge Operations. This project-specific QA project plan (QAPP), which is applicable to all project activities, identifies and integrates the specific QA requirements from the participant`s QA programs that are necessary for this project.

  19. Networking environmental metadata: a pilot project for the Mediterranean Region

    NASA Astrophysics Data System (ADS)

    Bonora, N.; Benito, M.; Abou El-Magd, I.; Mazzetti, P.; Ndong, C.

    2012-04-01

    To better exploit any environmental dataset it is necessary to provide detailed information (metadata) capable to furnish the best data description. Operating environmental data and information networking requires the long-term investment of financial and human resources. As these resources are scarce, ensuring sustainability can be a struggle. Then, to use more effectively human and economic resources and to avoid duplication, it is essential to test existing models and, where appropriate, replicate strategies and experiences. For the above reasons, it has been programmed to pilot a project to implement and test a metadata catalogue's networking, involving Countries afferent the Mediterranean Region, to demonstrate that the adoption of open source and free software and international interoperability standards can contribute to the alignment of I&TC resources to achieve environmental information sharing. This pilot, planned in the frame of the EGIDA FP7 European Project, aims to support the implementation of a replication methodology for the establishment of national/regional environmental information nodes on the bases of the System of Systems architecture concept, to support the exchange of environmental information in the frame of the Barcelona Convention and to incept a Mediterranean scale joint contribution to GEOSS focusing on partnership, infrastructures and products. To establish the partnership and to conduce interoperability tests, this pilot project build on the Info-RAC (Information and Communication Activity Centre of the United Nation Environmental Programme - Mediterranean Action Plan) and GEO (Group on Earth Observations) networks.

  20. West Valley Demonstration Project site environmental report, calendar year 1999

    SciTech Connect

    None Available

    2000-06-01

    This report represents a single, comprehensive source of off-site and on-site environmental monitoring data collected during 1999 by environmental monitoring personnel for the West Valley Demonstration Project (WVDP), West Valley, New York. The environmental monitoring program and results are discussed in the body of this report. The monitoring data are presented in the appendices. The data collected provide an historical record of radionuclide and radiation levels from natural and manmade sources in the survey area and document the quality of the groundwater on and around the WVDP and the quality of the air and water discharged by the WVDP.

  1. West Valley Demonstration Project site environmental report, calendar year 1997

    SciTech Connect

    1998-06-01

    This report represents a single, comprehensive source of off-site and on-site environmental monitoring data collected during 1997 by environmental monitoring personnel for the West Valley Demonstration Project (WVDP), West Valley, New York. The environmental monitoring program and results are discussed in the body of this report. The monitoring data are presented in the appendices. The data collected provide an historical record of radionuclide and radiation levels from natural and manmade sources in the survey area and document the quality of the groundwater on and around the WVDP and the quality of the air and water discharged by the WVDP.

  2. West Valley Demonstration Project site environmental report calendar year 1998

    SciTech Connect

    1999-06-01

    This report represents a single, comprehensive source of off-site and on-site environmental monitoring data collected during 1998 by environmental monitoring personnel for the West Valley Demonstration Project (WVDP), West Valley, New York. The environmental monitoring program and results are discussed in the body of this report. The monitoring data are presented in the appendices. The data collected provide an historical record of radionuclide and radiation levels from natural and manmade sources in the survey area and document the quality of the groundwater on and around the WVDP and the quality of the air and water discharged by the WVDP.

  3. Environmental cost of using poor decision metrics to prioritize environmental projects.

    PubMed

    Pannell, David J; Gibson, Fiona L

    2016-04-01

    Conservation decision makers commonly use project-scoring metrics that are inconsistent with theory on optimal ranking of projects. As a result, there may often be a loss of environmental benefits. We estimated the magnitudes of these losses for various metrics that deviate from theory in ways that are common in practice. These metrics included cases where relevant variables were omitted from the benefits metric, project costs were omitted, and benefits were calculated using a faulty functional form. We estimated distributions of parameters from 129 environmental projects from Australia, New Zealand, and Italy for which detailed analyses had been completed previously. The cost of using poor prioritization metrics (in terms of lost environmental values) was often high--up to 80% in the scenarios we examined. The cost in percentage terms was greater when the budget was smaller. The most costly errors were omitting information about environmental values (up to 31% loss of environmental values), omitting project costs (up to 35% loss), omitting the effectiveness of management actions (up to 9% loss), and using a weighted-additive decision metric for variables that should be multiplied (up to 23% loss). The latter 3 are errors that occur commonly in real-world decision metrics, in combination often reducing potential benefits from conservation investments by 30-50%. Uncertainty about parameter values also reduced the benefits from investments in conservation projects but often not by as much as faulty prioritization metrics.

  4. Environmentally Sound Small-Scale Agricultural Projects. Guidelines for Planning.

    ERIC Educational Resources Information Center

    Mohonk Trust, New Paltz, NY.

    This publication is the first of a series of manuals that present environmental guidelines for planning and implementing ecologically sustainable projects. Attention is particularly directed to the agricultural situation and needs of developing nations. Subject areas discussed include: (1) users and uses (identifying the major purposes of the…

  5. Environmental Horticulture. Project Report Phase I with Research Findings.

    ERIC Educational Resources Information Center

    Bachler, Mike; Sappe', Hoyt

    This report provides results of Phase I of a project that researched the occupational area of environmental horticulture, established appropriate committees, and conducted task verification. These results are intended to guide development of a program designed to address the needs of the horticulture field. Section 1 contains general information:…

  6. EPA Improves U.S.-Mexico Border with Environmental Projects

    EPA Pesticide Factsheets

    DALLAS - (Nov. 10, 2015) The U.S. Environmental Protection Agency (EPA) is awarding more than $521,000 to 14 organizations in Texas, New Mexico and Mexico. The funds will support projects such as conservation, waste collection, water quality protect

  7. Environmentally Responsible Aviation Project: Infrastructure Enhancements and New Capabilities

    NASA Technical Reports Server (NTRS)

    Bezos-OConnor, Gaudy M.

    2015-01-01

    This oral presentation highlights the technical investments the NASA Environmentally Responsible Aviation Project under the Integrated Systems Research Program within ARMD made during FY10-FY14 to upgrade/enhance the NASA infrastructure/testing assets and new capabilities required to mature the ERA N=2 Portfolio of airframe and propulsion technologies to TRL 5/6.

  8. 15 CFR 291.3 - Environmental tools and techniques projects.

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... 15 Commerce and Foreign Trade 1 2011-01-01 2011-01-01 false Environmental tools and techniques projects. 291.3 Section 291.3 Commerce and Foreign Trade Regulations Relating to Commerce and Foreign Trade NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY, DEPARTMENT OF COMMERCE NIST EXTRAMURAL...

  9. 15 CFR 291.3 - Environmental tools and techniques projects.

    Code of Federal Regulations, 2014 CFR

    2014-01-01

    ... 15 Commerce and Foreign Trade 1 2014-01-01 2014-01-01 false Environmental tools and techniques projects. 291.3 Section 291.3 Commerce and Foreign Trade Regulations Relating to Commerce and Foreign Trade NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY, DEPARTMENT OF COMMERCE NIST EXTRAMURAL...

  10. Environmental Assessment Expanded Ponnequin Wind Energy Project Weld County, Colorado

    SciTech Connect

    N /A

    1999-03-02

    The U.S.Department of Energy (DOE) has considered a proposal from the State of Colorado, Office of Energy Conservation (OEC), for funding construction of the Expanded Ponnequin Wind Project in Weld County, Colorado. OEC plans to enter into a contracting arrangement with Public Service Company of Colorado (PSCO) for the completion of these activities. PSCo, along with its subcontractors and business partners, are jointly developing the Expanded Ponnequin Wind Project. DOE completed an environmental assessment of the original proposed project in August 1997. Since then, the geographic scope and the design of the project changed, necessitating additional review of the project under the National Environmental Policy Act. The project now calls for the possible construction of up to 48 wind turbines on State and private lands. PSCo and its partners have initiated construction of the project on private land in Weld County, Colorado. A substation, access road and some wind turbines have been installed. However, to date, DOE has not provided any funding for these activities. DOE, through its Commercialization Ventures Program, has solicited applications for financial assistance from state energy offices, in a teaming arrangement with private-sector organizations, for projects that will accelerate the commercialization of emerging renewable energy technologies. The Commercialization Ventures Program was established by the Renewable Energy and Energy Efficiency Technology Competitiveness Act of 1989 (P.L. 101-218) as amended by the Energy Policy Act of 1992 (P.L. 102-486). The Program seeks to assist entry into the marketplace of newly emerging renewable energy technologies, or of innovative applications of existing technologies. In short, an emerging renewable energy technology is one which has already proven viable but which has had little or no operational experience. The Program is managed by the Department of Energy, Office of Energy Efficiency and Renewable Energy. The

  11. Environmental stability and the evolution of cooperative breeding in hornbills

    PubMed Central

    Gonzalez, Juan-Carlos T.; Sheldon, Ben C.; Tobias, Joseph A.

    2013-01-01

    Reproductive cooperation in social animals has been the focus of intensive research, yet the role of environmental factors in promoting such cooperation remains uncertain. A recent global analysis suggested that cooperative breeding in birds is a ‘bet-hedging’ strategy associated with climatic uncertainty, but it is unclear whether this mechanism applies generally or is restricted to the insectivorous passerines that predominate as cooperative breeders at the global scale. Here, we use a phylogenetic framework to assess the effect of climate on the evolution of cooperation in hornbills (Bucerotidae), an avian family characterized by frugivory and carnivory. We show that, in contrast to the global pattern, cooperative reproduction is positively associated with both inter- and intra-annual climatic stability. This reversed relationship implies that hornbills are relatively insensitive to climatic fluctuations, perhaps because of their dietary niche or increased body mass, both of which may remove the need for bet-hedging. We conclude that the relationship between climatic variability and cooperative breeding is inconsistent across taxa, and potentially mediated by life-history variation. These findings help to explain the mixed results of previous studies and highlight the likely shortcomings of global datasets inherently biased towards particular categories. PMID:23926149

  12. Management of the Atmosphere Resource Recovery and Environmental Monitoring Project

    NASA Technical Reports Server (NTRS)

    Roman, Monsi; Perry, Jay; Howard, David

    2013-01-01

    The Advanced Exploration Systems Program's Atmosphere Resource Recovery and Environmental Monitoring (ARREM) project is working to further optimize atmosphere revitalization and environmental monitoring system architectures. This paper discusses project management strategies that tap into skill sets across multiple engineering disciplines, projects, field centers, and industry to achieve the project success. It is the project's objective to contribute to system advances that will enable sustained exploration missions beyond Lower Earth Orbit (LEO) and improve affordability by focusing on the primary goals of achieving high reliability, improving efficiency, and reducing dependence on ground-based logistics resupply. Technology demonstrations are achieved by infusing new technologies and concepts with existing developmental hardware and operating in a controlled environment simulating various crewed habitat scenarios. The ARREM project's strengths include access to a vast array of existing developmental hardware that perform all the vital atmosphere revitalization functions, exceptional test facilities to fully evaluate system performance, and a well-coordinated partnering effort among the NASA field centers and industry partners to provide the innovative expertise necessary to succeed.

  13. INEL Waste and Environmental Information Integration Project approach and concepts

    SciTech Connect

    Dean, L.A.; Fairbourn, P.J.; Randall, V.C.; Riedesel, A.M.

    1994-06-01

    The Idaho National Engineering, Laboratory (INEL) Waste and Environmental Information integration Project (IWEIIP) was established in December 1993 to address issues related to INEL waste and environmental information including: Data quality; Data redundancy; Data accessibility; Data integration. This effort includes existing information, new development, and acquisition activities. Existing information may not be a database record; it may be an entire document (electronic, scanned, or hard-copy), a video clip, or a file cabinet of information. The IWEIIP will implement an effective integrated information framework to manage INEL waste and environmental information as an asset. This will improve data quality, resolve data redundancy, and increase data accessibility; therefore, providing more effective utilization of the dollars spent on waste and environmental information.

  14. Work plan for the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Not Available

    1989-12-01

    The primary objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that populations could have received from nuclear operations at the Hanford Site since 1944, with descriptions of uncertainties inherent in such estimates. The secondary objective is to make project records--information that HEDR staff members used to estimate radiation doses--available to the public. Preliminary dose estimates for a limited geographic area and time period, certain radionuclides, and certain populations are planned to be available in 1990; complete results are planned to be reported in 1993. Project reports and references used in the reports are available to the public in the DOE Public Reading Room in Richland, Washington. Project progress is documented in monthly reports, which are also available to the public in the DOE Public Reading Room.

  15. 77 FR 5502 - Stuyvesant Falls Hydroelectric Project; Notice of Application Ready for Environmental Analysis...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-02-03

    ... Federal Energy Regulatory Commission Stuyvesant Falls Hydroelectric Project; Notice of Application Ready..., New York. e. Name of Project: Stuyvesant Falls Hydroelectric Project. f. Location: On Kinderhook Creek... environmental analysis. l. The existing Stuyvesant Falls Hydroelectric Project is currently being restored...

  16. Designing of an environmental assessment algorithm for surface mining projects.

    PubMed

    Mirmohammadi, Mirsaleh; Gholamnejad, Javad; Fattahpour, Vahidoddin; Seyedsadri, Pejman; Ghorbani, Yousef

    2009-06-01

    This paper depicts the method used to quantify the environmental impact of mining activities in surface mine projects. The affected environment was broken down into thirteen components, such as Human health and immunity, Surface water, Air quality, etc. The effect of twenty impacting factors from the mining and milling activities was then calculated for each Environmental Component. Environmental assessments are often performed by using matrix methods in which one dimension of the matrix is the "Impacting Factor" and the other one is the "Environmental Components". For the presented matrix method, each Impacting Factor was first given a magnitude between -10 and 10. These factors are used to set up a matrix named Impacting Factor Matrix, whose elements represent the Impacting Factor values. The effects of each Impacting Factor on each Environmental Component were then quantified by multiplying the Impacting Factor Matrix by Weighting Factor Matrix. The elements of the weighting factors matrix reflect the effects of each Impacting Factor on each Environmental Component. The outlined method was originally developed for a mining and milling operation in Iran, but it can successfully be used for mining ventures and more general industrial activities in other countries in accordance to their environmental regulations and laws.

  17. Influence of Animation-Supported Project-Based Instruction Method on Environmental Literacy and Self-Efficacy in Environmental Education

    ERIC Educational Resources Information Center

    Aslan Efe, Hulya; Yucel, Sait; Baran, Medine; Oner Sunkur, Meral

    2012-01-01

    The present study conducted to establish effective environmental education investigated the influence of the project-based environmental education method supported with computer animations and of the traditional environmental education method on students' environmental literacy and on their self-efficacy beliefs in giving environmental education.…

  18. Validation of HEDR models. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Napier, B.A.; Simpson, J.C.; Eslinger, P.W.; Ramsdell, J.V. Jr.; Thiede, M.E.; Walters, W.H.

    1994-05-01

    The Hanford Environmental Dose Reconstruction (HEDR) Project has developed a set of computer models for estimating the possible radiation doses that individuals may have received from past Hanford Site operations. This document describes the validation of these models. In the HEDR Project, the model validation exercise consisted of comparing computational model estimates with limited historical field measurements and experimental measurements that are independent of those used to develop the models. The results of any one test do not mean that a model is valid. Rather, the collection of tests together provide a level of confidence that the HEDR models are valid.

  19. Summary of Session Activities: Coordination of Environmental Education Projects

    NASA Technical Reports Server (NTRS)

    Keeler, Michael; Mahootian, Farzad

    1995-01-01

    In this session, we address four fundamental questions related to environmental fields with emphasis on education. These are: What are the goals, objectives, and practical opportunities for coordinating our projects? How can we improve awareness of, interest in, access to, and support the products of our work? How can we build relationships between projects for scientific, educational, technical, and programmatic benefit? How can we evaluate the effectiveness of coordination efforts. In this working session, we produced answers to these questions and proposed a structure for future collaboration.

  20. Environmental Audit of the Grand Junction Projects Office

    SciTech Connect

    Not Available

    1991-08-01

    The Grand Junction Projects Office (GJPO) is located in Mesa County, Colorado, immediately south and west of the Grand Junction city limits. The US Atomic Energy Commission (AEC) established the Colorado Raw Materials Office at the present-day Grand Junction Projects Office in 1947, to aid in the development of a viable domestic uranium industry. Activities at the site included sampling uranium concentrate; pilot-plant milling research, including testing and processing of uranium ores; and operation of a uranium mill pilot plant from 1954 to 1958. The last shipment of uranium concentrate was sent from GJPO in January, 1975. Since that time the site has been utilized to support various DOE programs, such as the former National Uranium Resource Evaluation (NURE) Program, the Uranium Mill Tailings Remedial Action Project (UMTRAP), the Surplus Facilities Management Program (SFMP), and the Technical Measurements Center (TMC). All known contamination at GJPO is believed to be the result of the past uranium milling, analyses, and storage activities. Hazards associated with the wastes impounded at GJPO include surface and ground-water contamination and potential radon and gamma-radiation exposure. This report documents the results of the Baseline Environmental Audit conducted at Grand Junction Projects Office (GJPO) located in Grand Junction, Colorado. The Grand Junction Baseline Environmental Audit was conducted from May 28 to June 12, 1991, by the Office of Environmental Audit (EH-24). This Audit evaluated environmental programs and activities at GJPO, as well as GJPO activities at the State-Owned Temporary Repository. 4 figs., 12 tabs.

  1. TECHNICAL RISK RATING OF DOE ENVIRONMENTAL PROJECTS - 9153

    SciTech Connect

    Cercy, M; Ronald Fayfich, R; Steven P Schneider, S

    2008-12-12

    The U.S. Department of Energy's Office of Environmental Management (DOE-EM) was established to achieve the safe and compliant disposition of legacy wastes and facilities from defense nuclear applications. The scope of work is diverse, with projects ranging from single acquisitions to collections of projects and operations that span several decades and costs from hundreds of millions to billions US$. The need to be able to manage and understand the technical risks from the project to senior management level has been recognized as an enabler to successfully completing the mission. In 2008, DOE-EM developed the Technical Risk Rating as a new method to assist in managing technical risk based on specific criteria. The Technical Risk Rating, and the criteria used to determine the rating, provides a mechanism to foster open, meaningful communication between the Federal Project Directors and DOE-EM management concerning project technical risks. Four indicators (technical maturity, risk urgency, handling difficulty and resolution path) are used to focus attention on the issues and key aspects related to the risks. Pressing risk issues are brought to the forefront, keeping DOE-EM management informed and engaged such that they fully understand risk impact. Use of the Technical Risk Rating and criteria during reviews provides the Federal Project Directors the opportunity to openly discuss the most significant risks and assists in the management of technical risks across the portfolio of DOE-EM projects. Technical Risk Ratings can be applied to all projects in government and private industry. This paper will present the methodology and criteria for Technical Risk Ratings, and provide specific examples from DOE-EM projects.

  2. Technical Risk Rating of DOE Environmental Projects - 9153

    SciTech Connect

    Cercy, Michael; Fayfich, Ronald; Schneider, Steven

    2009-02-11

    The U.S. Department of Energy's Office of Environmental Management (DOE-EM) was established to achieve the safe and compliant disposition of legacy wastes and facilities from defense nuclear applications. The scope of work is diverse, with projects ranging from single acquisitions to collections of projects and operations that span several decades and costs from hundreds of millions to billions US$. The need to be able to manage and understand the technical risks from the project to senior management level has been recognized as an enabler to successfully completing the mission. In 2008, DOE-EM developed the Technical Risk Rating as a new method to assist in managing technical risk based on specific criteria. The Technical Risk Rating, and the criteria used to determine the rating, provides a mechanism to foster open, meaningful communication between the Federal Project Directors and DOE-EM management concerning project technical risks. Four indicators (technical maturity, risk urgency, handling difficulty and resolution path) are used to focus attention on the issues and key aspects related to the risks. Pressing risk issues are brought to the forefront, keeping DOE-EM management informed and engaged such that they fully understand risk impact. Use of the Technical Risk Rating and criteria during reviews provides the Federal Project Directors the opportunity to openly discuss the most significant risks and assists in the management of technical risks across the portfolio of DOE-EM projects. Technical Risk Ratings can be applied to all projects in government and private industry. This paper will present the methodology and criteria for Technical Risk Ratings, and provide specific examples from DOE-EM projects.

  3. Environmental management compliance reengineering project, FY 1997 report

    SciTech Connect

    VanVliet, J.A.; Davis, J.N.

    1997-09-01

    Through an integrated reengineering effort, the Idaho National Engineering and Environmental Laboratory (INEEL) is successfully implementing process improvements that will permit safe and compliant operations to continue during the next 5 years, even though $80 million was removed from the Environmental Management (EM) program budget. A 2-year analysis, design, and implementation project will reengineer compliance-related activities and reduce operating costs by approximately $17 million per year from Fiscal Year (FY) 1998 through 2002, while continuing to meet the INEEL`s environment, safety, and health requirements and milestone commitments. Compliance reengineer`s focus is improving processes, not avoiding full compliance with environmental, safety, and health laws. In FY 1997, compliance reengineering used a three-phase approach to analyze, design, and implement the changes that would decrease operating costs. Implementation for seven specific improvement projects was completed in FY 1997, while five projects will complete implementation in FY 1998. During FY 1998, the three-phase process will be repeated to continue reengineering the INEEL.

  4. Willow Creek Wildlife Mitigation Project. Final Environmental Assessment.

    SciTech Connect

    1995-04-01

    Today`s notice announces BPA`s proposal to fund land acquisition or acquisition of a conservation easement and a wildlife management plan to protect and enhance wildlife habitat at the Willow Creek Natural Area in Eugene, Oregon. This action would provide partial mitigation for wildlife and wildlife habitat lost by the development of Federal hydroelectric projects in the Willamette River Basin. The project is consistent with BPA`s obligations under provisions of the Pacific Northwest Electric Power Planning and Conservation Act of 1980 as outlined by the Northwest Power Planning Council`s 1994 Columbia River Basin Fish and Wildlife Program. BPA has prepared an environmental assessment (DOE/EA-1023) evaluating the proposed project. Based on the analysis in the EA, BPA has determined that the proposed action is not a major Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act (NEPA) of 1969. Therefore, the preparation of an environmental impact statement (EIS) is not required and BPA is issuing this FONSI.

  5. Tiering strategic environmental assessment and project environmental impact assessment in highway planning in Sao Paulo, Brazil

    SciTech Connect

    Sanchez, Luis E. Silva-Sanchez, Solange S.

    2008-10-15

    Constructing highways in dense urban areas is always a challenge. In Sao Paulo Metropolitan Region, heavy truck traffic contributes to clog streets and expressways alike. As part of the traffic neither originates nor head to the region, a peripheral highway has been proposed to reduce traffic problems. This project, called Rodoanel, is an expressway approximately 175 km long. The fact that the projected south and north sections would cross catchments that supply most of the metropolis water demand was strongly disputed and made the environmental permitting process particularly difficult. The agency in charge commissioned a strategic environmental assessment (SEA) of a revamped project, and called it the Rodoanel Programme. However, the SEA report failed to satisfactorily take account of significant strategic issues. Among these, the highway potential effect of inducing urban sprawl over water protection zones is the most critical issue, as it emerged later as a hurdle to project licensing. Conclusion is that, particularly where no agreed-upon framework for SEA exists, when vertical tiering with downstream project EIA is sought, then a careful scoping of strategic issues is more than necessary. If an agreement on 'what is strategic' is not reached and not recognized by influential stakeholders, then the unsettled conflicts will be transferred to project EIA. In such a context, SEA will have added another loop to the usually long road to project approval.

  6. Hellsgate Winter Range : Wildlife Mitigation Project. Final Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration.

    1995-03-01

    Bonneville Power Administration (BPA) proposes to fund the Hellsgate Winter Range Wildlife Mitigation Project (Project) in a cooperative effort with the Colville Confederated Tribes and the Bureau of Indian Affairs (BIA). The proposed action would allow the sponsors to secure property and conduct wildlife management activities within the boundaries of the Colville Indian Reservation. This Final Environmental Assessment (EA) examines the potential environmental effects of acquiring and managing property for wildlife and wildlife habitat within a large project area. This area consists of several separated land parcels, of which 2,000 hectares (4,943 acres) have been purchased by BPA and an additional 4,640 hectares (11,466 acres) have been identified by the Colville Confederated Tribes for inclusion in the Project. Four proposed activities (habitat protection, habitat enhancement, operation and maintenance, and monitoring and evaluation) are analyzed. The proposed action is intended to meet the need for mitigation of wildlife and wildlife habitat that was adversely affected by the construction of Grand Coulee and Chief Joseph Dams and their reservoirs.

  7. Controls on project proponents and environmental impact assessment effectiveness

    SciTech Connect

    Ortolano, L. )

    1993-01-01

    The degree of effectiveness of environmental impact assessment (EIA) for particular projects is associated with the existence of mechanisms of organizational control. Five dimensions of EIA effectiveness are considered: procedural compliance, completeness of EIA documents, methods to assess impacts, influence on project decisions, and weight given to environmental factors. Six mechanisms of control are introduced and illustrated by programs and projects in several countries. Experience in the Philippines under President Marcos demonstrates that procedural control in the form of EIA regulations, when used without other control mechanisms, will lead at most to token compliance. Judicial control, as practiced in the US, yields high procedural compliance. Evaluative control can yield effective EIA, but some systems based on this form of control treat only a small fraction of the major projects proposed. Both control exerted by development assistance organizations and control by professionals have great potential for yielding effective EIA, but that potential has not been fully realized. Control exerted directly by citizens or agencies not otherwise involved in EIA is uncommon, but cases from Taiwan demonstrate that those controls can be significant. An understanding of relationships between control mechanisms and EIA effectiveness is useful in designing EIA policies and programs.

  8. Phase 1 of the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Not Available

    1990-07-20

    This report summarizes the water pathway portion of the first phase of the Hanford Environmental Dose Reconstruction (HEDR) Project, conducted by Battelle staff at the Pacific Northwest Laboratory under the direction of an independent Technical Steering Panel. The HEDR Project is estimating radiation doses that could have been received by the public from the Department of Energy's Hanford Site, in southeastern Washington State. Phase 1 of the water-pathway dose reconstruction sought to determine whether dose estimates could be calculated for populations in the area from above the Hanford Site at Priest Rapids Dam to below the site at McNary Dam from January 1964 to December 1966. Of the potential sources of radionuclides from the river, fish consumption was the most important. Later phases of the HEDR Project will address dose estimates for periods other than 1964--1966 and for populations downstream of McNary Dam. 17 refs., 20 figs., 1 tab.

  9. Estimation of food consumption. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Callaway, J.M. Jr.

    1992-04-01

    The research reported in this document was conducted as a part of the Hanford Environmental Dose Reconstruction (HEDR) Project. The objective of the HEDR Project is to estimate the radiation doses that people could have received from operations at the Hanford Site. Information required to estimate these doses includes estimates of the amounts of potentially contaminated foods that individuals in the region consumed during the study period. In that general framework, the objective of the Food Consumption Task was to develop a capability to provide information about the parameters of the distribution(s) of daily food consumption for representative groups in the population for selected years during the study period. This report describes the methods and data used to estimate food consumption and presents the results developed for Phase I of the HEDR Project.

  10. West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2004

    SciTech Connect

    West Valley Nuclear Services Company and URS Group, Inc.

    2005-09-30

    Annual Site Environmental Report for the West Valley Demonstration Project (WVDP) for Calendar Year 2004. The report summarizes the environmental protection program at the West Valley Demonstration Project for CY 2004.

  11. Student Project Work and Abstracts. Beaufort, North Carolina Environmental Studies Project, No. 2.

    ERIC Educational Resources Information Center

    Carteret County Board of Education, Beaufort, NC.

    This document contains reports of 11 environmental study projects conducted by junior and senior students in a North Carolina high school. Topics range from the construction of an artificial reef and a survey of seashore changes to surveys of past and present development of various facets of the county ecology. The emphasis is on student…

  12. Final report for SNL/NM environmental drilling project

    SciTech Connect

    Wemple, R.P.; Meyer, R.D.; Staller, G.E.; Layne, R.R.

    1994-11-01

    Concern for the environment and cost reduction are driving forces for a broad effort in government and the private sector to develop new, more cost-effective technologies for characterizing, monitoring and remediating environmental sites. Secondary goals of the characterization, monitoring and remediation (CMR) activity are: minimize secondary waste generation, minimize site impact, protect water tables, and develop methods/strategies to apply new technologies. The Sandia National Laboratories (SNL) project in directional boring for CMR of waste sites with enhanced machinery from the underground utility installation industry was initiated in 1990. The project has tested a variety of prototype machinery and hardware built by the industrial partner, Charles Machine Works (CMW), and SNL at several sites (Savannah River Site (SRS), Hanford, SNL, Kirtland AFB (KAFB), CMW), successfully installed usable horizontal environmental test wells at SRS and SNL/KAFB, and functioned as a clearing house for information regarding application of existing commercial machinery to a variety of governmental and commercial sites. The project has continued to test and develop machinery in FY 94. The original goal of cost-effectiveness is being met through innovation, adaptation, and application of fundamental concepts. Secondary goals are being met via a basic philosophy of {open_quotes}cut/thrust and compact cuttings without adding large quantities of fluid{close_quotes} to an environmental problem site. This technology will be very cost-effective where applicable. Technology transfer and commercialization by CMW is ongoing and will continue into FY 95. Technology transfer to the private sector is ongoing and reflected in increasing machinery sales to environmental contractors. Education of regulatory agencies resulting in restructuring of appropriate regulatory standards for specification of the horizontal drilling techniques continues to be a long-range goal.

  13. Environmental impacts of dispersed development from federal infrastructure projects.

    PubMed

    Southerland, Mark T

    2004-06-01

    Dispersed development, also referred to as urban growth or sprawl, is a pattern of low-density development spread over previously rural landscapes. Such growth can result in adverse impacts to air quality, water quality, human health, aquatic and terrestrial ecosystems, agricultural land, military training areas, water supply and wastewater treatment, recreational resources, viewscapes, and cultural resources. The U.S. Environmental Protection Agency (U.S. EPA) is charged with protecting public health and the environment, which includes consideration of impacts from dispersed development. Specifically, because federal infrastructure projects can affect the progress of dispersed development, the secondary impacts resulting from it must be assessed in documents prepared under the National Environmental Policy Act (NEPA). The Council on Environmental Quality (CEQ) has oversight for NEPA and Section 309 of the Clean Air Act requires that U.S. EPA review and comment on federal agency NEPA documents. The adverse effects of dispersed development can be induced by federal infrastructure projects including transportation, built infrastructure, modifications in natural infrastructure, public land conversion and redevelopment of properties, construction of federal facilities, and large traffic or major growth generation developments requiring federal permits. This paper presents an approach that U.S. EPA reviewers and NEPA practitioners can use to provide accurate, realistic, and consistent analysis of secondary impacts of dispersed development resulting from federal infrastructure projects. It also presents 24 measures that can be used to mitigate adverse impacts from dispersed development by modifying project location and design, participating in preservation or restoration activities, or informing and supporting local communities in planning.

  14. Interim report for SNL/NM environmental drilling project

    SciTech Connect

    Wemple, R.P.; Meyer, R.D.; Layne, R.R.

    1994-02-01

    Concern for the environment and cost reduction are the driving forces for a broad effort in government and the private sector to develop new, more cost-effective technologies for characterizing, monitoring and remediating environmental sites. Secondary goals of the characterization, monitoring and remediation (CMR) activity are: minimize secondary waste generation, minimize site impact, protect water tables, and develop methods/strategies to apply new technologies. The Sandia National Laboratories (SNL) project in directional boring for CMR of waste sites with enhanced machinery from the underground utility installation industry was initiated in 1990. Preliminary activities included surveying the directional drilling access needs of various DOE sites, identifying an existing class of machinery that could be enhanced for environmental work through development, and establishing a mutually beneficial working relationship with an industry partner. Since that time the project has tested a variety of prototype machinery and hardware built by the industrial partner, and SNL. The project continues to test and develop the machinery and technique refinements needed for future applications at DOE, DOD, and private sector sites. The original goal of cost-effectiveness is being met through innovation, adaptation, and application of fundamental concepts. Secondary goals are being met via a basic philosophy of ``cut/thrust and compact cuttings without adding large quantities of fluid`` to an environmental problem site. Technology transfer to the private sector is ongoing and ultimately should result in commercial availability of the machinery. Education of regulatory agencies resulting in restructuring appropriate regulatory standards for specification of the horizontal drilling techniques will be a final project goal.

  15. SOLIDIFICATION/STABILIZATION - US ENVIRONMENTAL PROTECTION AGENCY SUPERFUND PROGRAM

    EPA Science Inventory

    This presentation outlines the Superfund program approach to site cleanup, then provides information from actual insitu and exsitu solidification/stabilization remediations to illustrate technology, equipment, field implementation, performance evaluation, cleanup specifications, ...

  16. Environmental assessment of USAID housing projects in the Russian Federation

    SciTech Connect

    Loran, B.; Miller, C.

    1995-12-01

    Parsons was selected by the United States Agency for International Development (USAID) as the general contractor for construction management for the construction of 2,500 housing units within the Russian Federation. These housing units, to be occupied by Russian officers returning from the Baltic States, are under construction on 15 sites, selected from an initial list of 200, based on habitability, capability of successful final construction. Cost meeting USAID guidelines, and impacts on the environment. USAID fulfilled NEPA requirements by preparing, with assistance of Parsons Engineering Science, a Programmatic Environmental Assessment and 15 site specific Environmental Assessments for the project. The sites were scattered over the entire Russian Federation west of the Ural Mountains. The site offerors completed an environmental checklist covering a broad range of possible impacts. Significant environmental issues and concerns were further identified during scoping meetings held at the site locations. The most important issues discussed were: soil contamination; gaseous, liquid, and solid pollutants to which the site may be exposed; incompatible adjacent land uses; ready access to utilities and social services; and socioeconomic situation favorable to resettlement of Russian military officers. No major environmental issues or concerns were identified for the 15 selected sites. Certificates indicating the absence of chemical and radiological surface and subsurface contamination at the proposed sites were provided by the local environmental officers. Polynuclear aromatic hydrocarbons were found present at one of the sites considered in a preliminary selection, and later rejected due to the failure of contractual negotiations. The environmental assessments included mitigation and monitoring measures for construction and operation (occupancy) impacts.

  17. Genetic and environmental influences on personality profile stability: unraveling the normativeness problem.

    PubMed

    Bleidorn, Wiebke; Kandler, Christian; Riemann, Rainer; Angleitner, Alois; Spinath, Frank M

    2012-08-01

    The present study is the first to disentangle the genetic and environmental influences on personality profile stability. Spanning a period of 10 years, we analyzed the etiology of 3 aspects of profile stability (overall profile stability, distinctive profile stability, and profile normativeness) using self- and peer reports from 539 identical and 280 fraternal twins reared together. This 3-wave multirater twin design allowed us to estimate the genetic and environmental effects on latent true scores of the 3 aspects of profile stability while controlling for method effects and random error. Consistent biometric results were only found for profile normativeness, whereas overall and distinctive profile stability scores turned out to be biased. Over time, we found personality profile normativeness to be relatively stable. This stability was due to both stable genetic and nonshared environmental effects, whereas innovative variance was completely explained by nonshared environmental effects. Our findings emphasize the importance of distinguishing between the different aspects of profile stability, since overall and distinctive stability scores are likely biased due to the normativeness problem. Yet indicating a person's similarity to the average person, the normativeness of a personality profile itself has a psychological meaning beyond socially desirable responding.

  18. Blue Creek Winter Range : Wildlife Mitigation Project : Final Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration; United States. Bureau of Indian Affairs; Spokane Tribe of the Spokane Reservation, Washington

    1994-11-01

    Bonneville Power Administration (BPA) proposes to fund that portion of the Washington Wildlife Agreement pertaining to the Blue Creek Winter Range Wildlife Mitigation Project (Project) in a cooperative effort with the Spokane Tribe, Upper Columbia United Tribes, and the Bureau of Indian Affairs (BIA). If fully implemented, the proposed action would allow the sponsors to protect and enhance 2,631 habitat units of big game winter range and riparian shrub habitat on 2,185 hectares (5,400 acres) of Spokane Tribal trust lands, and to conduct long term wildlife management activities within the Spokane Indian Reservation project area. This Final Environmental Assessment (EA) examines the potential environmental effects of securing land and conducting wildlife habitat enhancement and long term management activities within the boundaries of the Spokane Indian Reservation. Four proposed activities (habitat protection, habitat enhancement, operation and maintenance, and monitoring and evaluation) are analyzed. The proposed action is intended to meet the need for mitigation of wildlife and wildlife habitat adversely affected by the construction of Grand Coulee Dam and its reservoir.

  19. Trace Metals in Groundwater and Vadose Zone Calcite: In Situ Containment and Stabilization of Stronthium-90 and Other Divalent Metals and Radionuclides at Arid Western DOE Sites: Final Report for Award Number DE-FG07-02ER63486 to the University of Idaho (RW Smith) Environmental Management Science Program Project Number 87016

    SciTech Connect

    Smith, Robert W.; Fujita, Yoshiko

    2007-11-07

    Radionuclide and metal contaminants are present in the vadose zone and groundwater throughout the U.S. Department of Energy (DOE) energy research and weapons complex. In situ containment and stabilization of these contaminants represents a cost-effective treatment strategy that minimizes workers’ exposure to hazardous substances, does not require removal or transport of contaminants, and generally does not generate a secondary waste stream. We have investigated an in situ bioremediation approach that immobilizes radionuclides or contaminant metals (e.g., strontium-90) by their microbially facilitated co-precipitation with calcium carbonate in groundwater and vadose zone systems. Calcite, a common mineral in many aquifers and vadose zones in the arid west, can incorporate divalent metals such as strontium, cadmium, lead, and cobalt into its crystal structure by the formation of a solid solution. Collaborative research undertaken by the Idaho National Laboratory (INL), University of Idaho, and University of Toronto as part of this Environmental Management Science Program project has focused on in situ microbially-catalyzed urea hydrolysis, which results in an increase in pH, carbonate alkalinity, ammonium, calcite precipitation, and co-precipitation of divalent cations. In calcite-saturated aquifers, microbially facilitated co-precipitation with calcium carbonate represents a potential long-term contaminant sequestration mechanism. Key results of the project include: **Demonstrating the linkage between urea hydrolysis and calcite precipitation in field and laboratory experiments **Observing strontium incorporation into calcite precipitate by urea hydrolyzers with higher distribution coefficient than in abiotic **Developing and applying molecular methods for characterizing microbial urease activity in groundwater including a quantitative PCR method for enumerating ureolytic bacteria **Applying the suite of developed molecular methods to assess the feasibility of the

  20. 78 FR 26319 - Deepwater Horizon Oil Spill; Proposal of Future Early Restoration Projects and Environmental Reviews

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-05-06

    .... Environmental Protection Agency (USEPA); State of Louisiana Coastal Protection and Restoration Authority, Oil... of Florida Department of Environmental Protection and Fish and Wildlife Conservation Commission; and... Restoration Projects and Environmental Reviews AGENCY: National Oceanic and Atmospheric...

  1. 75 FR 29359 - Draft Environmental Impact Statement for the Tamiami Trail Modifications: Next Steps Project...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-05-25

    ...) Modifications: Next Steps Project for Everglades National Park, Florida. The 2009 Omnibus Appropriations Act, H... National Park Service Draft Environmental Impact Statement for the Tamiami Trail Modifications: Next Steps Project, Everglades National Park Tamiami Trail Modifications: Next Steps Project, Draft...

  2. Project Execution Plan Project 98L-EWW-460 Plutonium Stabilization and Handling DOE 98-D-453

    SciTech Connect

    HOLSTEIN, W.A.

    1999-08-01

    This Project Execution Plan (PEP) describes the management methods and responsibilities of the project participants. Project W-460 is sufficiently large to warrant a stand alone PEP. This project specific PEP describes the relationships and responsibilities of the project team and identifies the technical, schedule, and cost baselines that have been established for the project. The Department of Energy (DOE), Hanford Works (Hanford), at Richland Wa. currently does not have a system capable of stabilizing or packaging large quantities of plutonium-bearing solids to meet DOE technical standard DOE-STD-3013-96. This project will allow Hanford to meet this standard by installing stabilization and packaging equipment (SPE). The SPE is capable of stabilizing and packaging the current inventory of greater than 50 percent plutonium-bearing materials currently stored in the Plutonium Finishing Plant's (PFP) vaults into 3013 storage containers. The scope of this project is to procure and install the SPE via a Hanford contract and coordination with the Savannah River Site. In addition, the project will modify PFP vaults and upgrade the PFP Laboratory measurement systems. The Facility infrastructure will be modified to support the new SPE system and the new standardized storage container configuration.

  3. Project Execution Plan Project 98L-EWW-460 Plutonium Stabilization and Handling DOE 98-D-453

    SciTech Connect

    MCGRATH, G.M.

    2000-06-21

    This Project Execution Plan (PEP) describes the management methods and responsibilities of the project participants. Project W-460 is sufficiently large to warrant a stand alone PEP. This project specific PEP describes the relationships and responsibilities of the project team and identifies the technical, schedule, and cost baselines that have been established for the project. The Department of Energy (DOE), Hanford Works (Hanford), at Richland, Wa. currently does not have a system capable of stabilizing or packaging large quantities of plutonium-bearing solids to meet DOE technical standard DOE-STD-3013-99. This project will allow Hanford to meet this standard by installing stabilization and packaging equipment (SPE). The SPE is capable of stabilizing and packaging the current inventory of greater than 30 percent plutonium-bearing materials currently stored in the Plutonium Finishing Plant's (PFP) vaults into 3013 storage containers. The scope of this project is to procure and install the SPE via a Hanford contract and coordination with the Savannah River Site. In addition, the project will modify PFP vaults and upgrade the PFP Laboratory measurement systems. The Facility infrastructure will be modified to support the new SPE system and the new standardized storage container configuration.

  4. Environmental Project of I.E.S. Antoni Maura

    NASA Astrophysics Data System (ADS)

    Crespi Salom, Pere

    2010-05-01

    Environmental Project of I.E.S. Antoni Maura Author(s): Pere Crespí i Salom Teacher of Department of Biology and Geology and Environmental Coordinator (2009-2010) from I.E.S. Antoni Maura . Mallorca. Illes Balears. Spain Teachers participating in the project : Myriam Fuentes Milani, Olga Ballester Nebot, Antoni Salom Ruiz, Julio René Loayza Casanova, Puy Aguirre Rémirez, Yolanda Martínez Laserna, Jaume Puppo Lama, Carme Arrom , Dolors Aguiló Segura, Marga Ordinas Boter, Angel Fernàndez Albertí , Immaculada Suau López, Antònia Florit Torrandell, Isabel Mateu Arcos, Román Piña Valls i Pere Crespí Salom. Our institute takes part since 2004 in adapting environmentally the schools in the Balearics which consists of developing activities which aim is that both teachers and students acquire habits so as to apply to their ordinary lives though different participative commissions ( 10-15 teachers): 1st commission: recycling and reusing materials. Enough bins in the classrooms and floors: yellow for plastic, blue for paper, and green for the other. We tend to use recycled materials in different celebrations such as Carnival, Christmas, Saint Jordi and Environmental day. We also organise workshops for the teachers to develop afterwards with the students and nature of environmental exposures. 2nd commission: Scatter information ( MonMaura, Maurifull, Green window and website).Throughout different means we inform the teachers and students about all the school activities and where to consult.( www.iesantonimaura.net, Playful area , environmental project ). 3rd commission: Reusing text books.( there is a students service of borrowing books and giving them back at the end of the school year if the book is in good use.) 4th commission: Improving the school surroundings, the back garden and garden with native plants. Department of Biology and Geology is responsible for caring for an organic garden and in turn improve the center's garden with native plants within the

  5. [Nuclear energy and environment: review of the IAEA environmental projects].

    PubMed

    Fesenko, S; Fogt, G

    2012-01-01

    The review of the environmental projects of the International Atomic Energy Agency is presented. Basic IAEA documents intended to protect humans and the Environment are considered and their main features are discussed. Some challenging issues in the area of protection of the Environment and man, including the impact of nuclear facilities on the environment, radioactive waste management, and remediation of the areas affected by radiological accidents, nuclear testing and sites of nuclear facilities are also discussed. The need to maintain the existing knowledge in radioecology and protection of the environment is emphasised.

  6. Environmental Restoration Disposal Facility (Project W-296) Safety Assessment

    SciTech Connect

    Armstrong, D.L.

    1994-08-01

    This Safety Assessment is based on information derived from the Conceptual Design Report for the Environmental Restoration Disposal Facility (DOE/RL 1994) and ancillary documentation developed during the conceptual design phase of Project W-296. The Safety Assessment has been prepared to support the Solid Waste Burial Ground Interim Safety Basis document. The purpose of the Safety Assessment is to provide an evaluation of the design to determine if the process, as proposed, will comply with US Department of Energy (DOE) Limits for radioactive and hazardous material exposures and be acceptable from an overall health and safety standpoint. The evaluation considered affects on the worker, onsite personnel, the public, and the environment.

  7. Environmental information volume: Liquid Phase Methanol (LPMEOH{trademark}) project

    SciTech Connect

    1996-05-01

    The purpose of this project is to demonstrate the commercial viability of the Liquid Phase Methanol Process using coal-derived synthesis gas, a mixture of hydrogen and carbon monoxide. This report describes the proposed actions, alternative to the proposed action, the existing environment at the coal gasification plant at Kingsport, Tennessee, environmental impacts, regulatory requirements, offsite fuel testing, and DME addition to methanol production. Appendices include the air permit application, solid waste permits, water permit, existing air permits, agency correspondence, and Eastman and Air Products literature.

  8. Idaho National Engineering Laboratory Sewer System Upgrade Project. Environmental Assessment

    SciTech Connect

    Not Available

    1994-04-01

    The Department of Energy (DOE) has prepared an environmental assessment for a proposed Sewer System Upgrade Project at the Idaho National Engineering Laboratory (INEL) near Idaho Falls, Idaho. The proposed action would include activities conducted at the Central Facilities Area, Test Reactor Area, and the Containment Test Facility at the Test Area North at INEL. The proposed action would consist of replacing or remodeling the existing sewage treatment plants at the Central Facilities Area, Test Reactor Area, and Containment Test Facility. Also, a new sewage testing laboratory would be constructed at the Central Facilities Area. Finally, the proposed action would include replacing, repairing, and/or adding sewer lines in areas where needed.

  9. The Rocky Flats Environmental Technology Site beryllium characterization project

    SciTech Connect

    Morrell, D.M.; Miller, J.R.; Allen, D.F.

    1999-06-01

    A site beryllium characterization project was completed at the Rocky Flats Environmental Technology Site (RFETS) in 1997. Information from historical reviews, previous sampling surveys, and a new sampling survey were used to establish a more comprehensive understanding of the locations and levels of beryllium contamination in 35 buildings. A feature of the sampling strategy was to test if process knowledge was a good predictor of where beryllium contamination could be found. Results revealed that this technique was effective at identifying where surface contamination levels might exceed the RFETS smear control level but that it was not effective in identifying where low concentrations of beryllium might be found.

  10. User instructions for the DESCARTES environmental accumulation code. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Miley, T.B.; Eslinger, P.W.; Nichols, W.E.; Lessor, K.S.; Ouderkirk, S.J.

    1994-05-01

    The purpose of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation dose that individuals could have received as a result of emissions since 1944 from the Hanford Site near Richland, Washington. The HEDR Project work is conducted under several technical and administrative tasks, among which is the Environmental Pathways and Dose Estimates task. The staff on this task have developed a suite of computer codes which are used to estimate doses to individuals in the public. This document contains the user instructions for the DESCARTES (Dynamic estimates of concentrations and Accumulated Radionuclides in Terrestrial Environments) suite of codes. In addition to the DESCARTES code, this includes two air data preprocessors, a database postprocessor, and several utility routines that are used to format input data needed for DESCARTES.

  11. WEST VALLEY DEMONSTRATION PROJECT ANNUAL SITE ENVIRONMENTAL REPORT CALENDAR YEAR 2002

    SciTech Connect

    2003-09-12

    This annual environmental monitoring report for the West Valley Demonstration Project (WVDP or Project) is published to inform those with interest about environmental conditions at the WVDP. In accordance with U.S. Department of Energy (DOE) Order 231.1, Environment, Safety, and Health Reporting, the report summarizes calendar year (CY) 2002 environmental monitoring data so as to describe the performance of the WVDP's environmental management system, confirm compliance with standards and regulations, and highlight important programs. In 2002, the West Valley Demonstration Project, the site of a DOE environmental cleanup activity operated by West Valley Nuclear Services Co. (WVNSCO), was in the final stages of stabilizing high-level radioactive waste (HLW) that remained at the site after commercial nuclear fuel reprocessing had been discontinued in the early 1970s. The Project is located in western New York State, about 30 miles south of Buffalo, within the New York State-owned Western New York Nuclear Service Center (WNYNSC). The WVDP is being conducted in cooperation with the New York State Energy Research and Development Authority (NYSERDA). Ongoing work activities at the WVDP during 2002 included: (1) completing HLW solidification and melter shutdown; (2) shipping low-level radioactive waste off-site for disposal; (3) constructing a facility where large high-activity components can be safely packaged for disposal; (4) packaging and removing spent materials from the vitrification facility; (5) preparing environmental impact statements for future activities; (6) removing as much of the waste left behind in waste tanks 8D-1 and 8D-2 as was reasonably possible; (7) removing storage racks, canisters, and debris from the fuel receiving and storage pool, decontaminating pool walls, and beginning shipment of debris for disposal; (8) ongoing decontamination in the general purpose cell and the process mechanical cell (also referred to as the head end cells); (9) planning

  12. Susitna Hydroelectric Project: terrestrial environmental workshop and preliminary simulation model

    USGS Publications Warehouse

    Everitt, Robert R.; Sonntag, Nicholas C.; Auble, Gregory T.; Roelle, James E.; Gazey, William

    1982-01-01

    The technical feasibility, economic viability, and environmental impacts of a hydroelectric development project in the Susitna River Basin are being studied by Acres American, Inc. on behalf of the Alaska Power Authority. As part of these studies, Acres American recently contracted LGL Alaska Research Associates, Inc. to coordinate the terrestrial environmental studies being performed by the Alaska Department of Fish and Game and, as subcontractors to LGL, several University of Alaska research groups. LGL is responsible for further quantifying the potential impacts of the project on terrestrial wildlife and vegetation, and for developing a plan to mitigate adverse impacts on the terrestrial environment. The impact assessment and mitigation plan will be included as part of a license application to the Federal Energy Regulatory Commission (FERC) scheduled for the first quarter of 1983. The quantification of impacts, mitigation planning, and design of future research is being organized using a computer simulation modelling approach. Through a series of workshops attended by researchers, resource managers, and policy-makers, a computer model is being developed and refined for use in the quantification of impacts on terrestrial wildlife and vegetation, and for evaluating different mitigation measures such as habitat enhancement and the designation of replacement lands to be managed by wildlife habitat. This report describes the preliminary model developed at the first workshop held August 23 -27, 1982 in Anchorage.

  13. Hanford Environmental Dose Reconstruction Project--an overview.

    PubMed

    Shipler, D B; Napier, B A; Farris, W T; Freshley, M D

    1996-10-01

    The Hanford Environmental Dose Reconstruction Project was initiated because of public interest in the historical releases of radioactive materials from the Hanford Site, located in southcentral Washington State. By 1986, over 38,000 pages of environmental monitoring documentation from the early years of Hanford operations had been released. Special committees reviewing the documents recommended initiation of the Hanford Environmental Dose Reconstruction Project, which began in October 1987, and is conducted by Battelle, Pacific Northwest Laboratories. The technical approach taken was to reconstruct releases of radioactive materials based on facility operating information; develop and/or adapt transport, pathway, and dose models and computer codes; reconstruct environmental, meteorological, and hydrological monitoring information; reconstruct demographic, agricultural, and lifestyle characteristics; apply statistical methods to all forms of uncertainty in the information, parameters, and models; and perform scientific investigations that were technically defensible. The geographic area for the study includes approximately 2 x 10(5) km2 (75,000 mi2) in eastern Washington, western Idaho, and northeastern Oregon (essentially the Mid-Columbia Basin of the Pacific Northwest). Three exposure pathways were considered: the atmosphere, the Columbia River, and ground water. the radionuclide of interest for atmospheric pathway doses was 131I. The median dose for the maximally exposed individual was approximately 2.3 Gy (230 rad) to the thyroid over the period from 1944 to 1972 with a 90% subjective confidence interval of 0.54 to 8.4 Gy (54 to 840 rad). The Columbia River was studied from Priest Rapids Dam, upstream of the Hanford Site, to the mouth of the river and nearby bays. Radionuclides of interest for river pathway doses were 24Na, 32P, 65Zn, 76As, and 239Np. The median dose from the river pathway for the maximally exposed individual was approximately 0.0015 Sv (0.15 rem

  14. A guide to environmental monitoring data, 1945--1972: Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Thiede, M.E.; Bates, D.J.; Mart, E.I.; Hanf, R.W.

    1994-03-01

    This report is a guide to the work accomplished by the Environmental Monitoring Data Task, which is one of the tasks in the Hanford Environmental Dose Reconstruction (HEDR) Project. The objective of the Environmental Monitoring Data Task was to recover, evaluate, process, and/or reconstruct the environmental monitoring data for the period 1945--1972. The period of time for which environmental monitoring data were sought was determined by the start-up and shut-down dates of the Hanford facilities that emitted the majority of radionuclides to the two major pathways: air and the Columbia River. Radionuclide emissions to the air were mainly the result of the operation of the chemical separations plants from 1944--1972 (Heeb 1994). Radionuclide emissions to the Columbia River were mainly the result of the operation of the single-pass production reactors from 1944--1971 (Heeb and Bates 1994). Therefore, the historical environmental monitoring data sought were for the period 1945--1972. Within the period of 1945--1972, specific periods of interest to the HEDR Project vary depending on the pathway. For example, 1945--1951 was the peak period for radionuclide emissions to the air and hence vegetation uptake of radionuclides, while 1956--1965 was the peak period for radionuclide emissions to the Columbia River and hence fish uptake of radionuclides. However, adequate historical data were not always available for the periods of interest. In the case of vegetation measurements, conversion and correction factors had to be developed to convert the historical measurements to modern standard measurements. Table S.1 lists the reports that explain these conversion and correction factors. In the case of Columbia River fish and waterfowl, bioconcentration factors were developed for use in any year where the river pathway data are insufficient.

  15. Modelling the relative stability of carbon nanotubes exposed to environmental adsorbates and air.

    PubMed

    Barnard, Amanda S

    2009-04-08

    In parallel with the development of technological applications for carbon nanotubes, issues related to toxicology and environmental impact are also under increased scrutiny. It is clear from the available literature that the integrity of future carbon nanotube-based devices, our ability to anticipate failure of these devices, and our ability to manage the toxicological and environmental impacts require a detailed understanding of the stability of pure and functionalized carbon nanotubes under a full range of environmental conditions. Motivated by this endeavour, the present study uses a general thermodynamic model to predict the relative stability of carbon nanotubes exposed to a variety of atmospheric adsorbates, and uses them to examine the stability of nanotubes in air, as a function of the relative humidity. In general the results indicate that the adsorption of a sparse coverage of air is thermodynamically favoured, depending on the humidity, and the stability of small diameter nanotubes may be improved by exposure to humid air.

  16. CNR LARA project, Italy: Airborne laboratory for environmental research

    NASA Technical Reports Server (NTRS)

    Bianchi, R.; Cavalli, R. M.; Fiumi, L.; Marino, C. M.; Pignatti, S.

    1995-01-01

    The increasing interest for the environmental problems and the study of the impact on the environment due to antropic activity produced an enhancement of remote sensing applications. The Italian National Research Council (CNR) established a new laboratory for airborne hyperspectral imaging, the LARA Project (Laboratorio Aero per Ricerche Ambientali - Airborne Laboratory for Environmental Research), equipping its airborne laboratory, a CASA-212, mainly with the Daedalus AA5000 MIVIS (Multispectral Infrared and Visible Imaging Spectrometer) instrument. MIVIS's channels, spectral bandwidths, and locations are chosen to meet the needs of scientific research for advanced applications of remote sensing data. MIVIS can make significant contributions to solving problems in many diverse areas such as geologic exploration, land use studies, mineralogy, agricultural crop studies, energy loss analysis, pollution assessment, volcanology, forest fire management and others. The broad spectral range and the many discrete narrow channels of MIVIS provide a fine quantization of spectral information that permits accurate definition of absorption features from a variety of materials, allowing the extraction of chemical and physical information of our environment. The availability of such a hyperspectral imager, that will operate mainly in the Mediterranean area, at the present represents a unique opportunity for those who are involved in environmental studies and land-management to collect systematically large-scale and high spectral-spatial resolution data of this part of the world. Nevertheless, MIVIS deployments will touch other parts of the world, where a major interest from the international scientific community is present.

  17. Initial findings of the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Napier, B.A. )

    1991-01-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation dose that individuals could have received as a result of emissions from nuclear operations at Hanford since their inception in 1944. The objective of phase 1 of the project was to demonstrate through calculation that adequate models and support data existed or could be developed to allow estimation of realistic doses to individuals from releases of radionuclides to the environment that occurred as long as 45 years ago. This paper presents a summary of the results calculated for phase 1 of the project. These results were made public in July of 1990. The phase 1 study area for the air pathway covers the ten countries nearest the Hanford Site. This area was selected to encompass populations nearest the releases and therefore most likely to have been in the path of the highest concentrations of radioactive materials. The radionuclide likely to have contributed most to doses to off-site populations was determined to be {sup 131}I. It was estimated that the 1944-1947 period accounts for > 90% of the {sup 131}I released since start-up of the facilities. The phase-1 air release time period was therefore selected to encompass this period. Pathways of exposure included external exposure via submersion and groundshine, inhalation, and ingestion of crops and animal products, particularly milk.

  18. Environmental Field Surveys, EMF Rapid Program, Engineering Project No.3

    SciTech Connect

    Enertech Consultants

    1996-04-01

    The EMF Research and Public Information Dissemination Program (RAPID) includes several engineering research in the area of exposure assessment and source characterization. RAPID engineering project No. 3: ''Environmental Field Surveys'' was performed to obtain information on the levels and characteristics of different environments, for which only limited data were available, especially in comparison to magnetic field data for the residential environment and for electric utility facilities, such as power lines and substations. This project was also to provide information on the contribution of various field sources in the surveyed environments. Magnetic field surveys were performed at four sites for each of five environments: schools, hospitals, office buildings, machine shops, and grocery stores. Of the twenty sites surveyed, 11 were located in the San Francisco Bay Area and 9 in Massachusetts. The surveys used a protocol based on magnetic field measurements and observation of activity patterns, designed to provide estimates of magnetic field exposure by type of people and by type of sources. The magnetic field surveys conducted by this project produced a large amount of data which will form a part of the EMF measurement database Field and exposure data were obtained separately for ''area exposure'' and ''at exposure points''. An exposure point is a location where persons engage in fixed, site specific activities near a local source that creates a significant increase in the area field. The area field is produced by ''area sources'', whose location and field distribution is in general not related to the location of the people in the area.

  19. Environmental Studies in Nine Courses at Crescent Valley High. Project Reports, Volume 6, The Rachel Carson Project.

    ERIC Educational Resources Information Center

    Tanner, R. Thomas

    This document is the sixth of seven accompanying volumes included in the Rachel Carson Project. The project attempts to introduce environmental education lessons and units into existing courses of study within a high school curriculum rather than to implement environmental education through the introduction of new courses. This volume includes…

  20. Upper Mississippi River ECO-Center Environmental Education Project. First Year Report, Project Year 72-73.

    ERIC Educational Resources Information Center

    Upper Mississippi River ECO-Center, Thomson, IL.

    The proposal describes the history of the Upper Mississippi River ECO-Center Environmental Education Project (funded by Title III, Elementary and Secondary Education Act), Carroll County, Illinois. The goal of the project, which began in July 1972, is to implement and coordinate a comprehensive environmental education program for the county's…

  1. The Security-Stability-Sustainability Nexus: Environmental Considerations

    DTIC Science & Technology

    2009-05-01

    health and environmental security are often intertwined, and while not traditionally viewed as „threats‟ to U.S. national security, they will affect ...Intelligence Community for the Senate Select Committee on Intelligence, Feb 12, 2009 Instability and Fragile States (FM 3-0) Trends Affecting Ground Force...urbanization – highest rate for decades World’s highest rate of deforestation Land degradation leading to desertification Estimated 65% of agricultural

  2. Hydraulic and Environmental Effects of Channel Stabilization, Twentymile Creek, Mississippi

    DTIC Science & Technology

    1990-12-01

    square kilomitres tons (2,000 pounds, mass) 907.1847 kilograms To obtain Celsius (C) temperi!ure readings from Fahrenheit (F) readings , use the followirg...fr!nula: C 1 (/9)(F - 32). To obtain kelvin (K) read - ings use: K = (5/9)(F - 32) - 27’.l!. 6 HYDRAULIC AND ENVIRONMENTAL EFFECTS OF CHANNEL...1981) method with the existing channel geometry and bed material gradation, an aver- age Manning roughness coefficient (n value) of 0.018 was

  3. FY 1991 project plan for the Hanford Environmental Dose Reconstruction Project, Phase 2

    SciTech Connect

    Not Available

    1991-02-01

    Phase 1 of the Hanford Environmental Dose Reconstruction Project was designed to develop and demonstrate a method for estimating radiation doses people may have received from Hanford Site operations since 1944. The method researchers developed relied on a variety of measured and reconstructed data as input to a modular computer model that generates dose estimates and their uncertainties. As part of Phase 1, researchers used the reconstructed data and computer model to calculate preliminary dose estimates for populations in a limited geographical area and time period. Phase 2, now under way, is designed to evaluate the Phase 1 data and model and improve them to calculate more accurate and precise dose estimates. Phase 2 will also be used to obtain preliminary estimates of two categories of doses: for Native American tribes and for individuals included in the pilot phase of the Hanford Thyroid Disease Study (HTDS). TSP Directive 90-1 required HEDR staff to develop Phase 2 task plans for TSP approval. Draft task plans for Phase 2 were submitted to the TSP at the October 11--12, 1990 public meeting, and, after discussions of each activity and associated budget needs, the TSP directed HEDR staff to proceed with a slate of specific project activities for FY 1991 of Phase 2. This project plan contains detailed information about those activities. Phase 2 is expected to last 15--18 months. In mid-FY 1991, project activities and budget will be reevaluated to determine whether technical needs or priorities have changed. Separate from, but related to, this project plan, will be an integrated plan for the remainder of the project. HEDR staff will work with the TSP to map out a strategy that clearly describes end products'' for the project and the work necessary to complete them. This level of planning will provide a framework within which project decisions in Phases 2, 3, and 4 can be made.

  4. Project Management Plan for the Hawaii Geothermal Project Environmental Impact Statement

    SciTech Connect

    Reed, R.M.; Saulsbury, J.W.

    1993-06-01

    In 1990, Congress appropriated $5 million (Pu 101-514) for the State of Hawaii to use in Phase 3 of the Hawaii Geothermal Project (HGP). As defined by the State in its 1990 proposal to Congress, the HGP would consist of four phases: (1) exploration and testing of the geothermal resource associated with the Kilauea Volcano on the Island of Hawaii (the Big Island), (2) demonstration of deep-water power transmission cable technology in the Alenuihaha Channel between the Big Island and Maui, (3) verification and characterization of the geothermal resource on the Big Island, and (4) construction and operation of commercial geothermal power production facilities on the Big Island, with overland and submarine transmission of electricity from the Big Island to Oahu and possibly other islands (DBED 1990). Because it considered Phase 3 to be research and not project development or construction, Congress indicated that allocation of this funding would not be considered a major federal action under NEPA and would not require an EIS. However, because the project is highly visible, somewhat controversial, and involves a particularly sensitive environment in Hawaii, Congress directed in 1991 (House Resolution 1281) that ''...the Secretary of Energy shall use such sums as are necessary from amounts previously provided to the State of Hawaii for geothermal resource verification and characterization to conduct the necessary environmental assessments and/or environmental impact statement (EIS) for the geothermal initiative to proceed''. In addition, the U.S. District Court of Hawaii (Civil No. 90-00407, June 25, 1991) ruled that the federal government must prepare an EIS for Phases 3 and 4 before any further disbursement of funds was made to the State for the HGP. This Project Management Plan (PMP) briefly summarizes the background information on the HGP and describes the project management structure, work breakdown structure, baseline budget and schedule, and reporting procedures

  5. Environmental Assessment: geothermal direct heat project, Marlin, Texas

    SciTech Connect

    Not Available

    1980-08-01

    The Federal action addressed by this Environmental Assessment (EA) is joint funding the retrofitting of a heating and hot water system in a hospital at Marlin, Texas, with a geothermal preheat system. The project will be located within the existing hospital boiler room. One supply well was drilled in an existing adjacent parking lot. It was necessary to drill the well prior to completion of this environmental assessment in order to confirm the reservoir and to obtain fluids for analysis in order to assess the environmental effects of fluid disposal. Fluid from operation will be disposed of by discharging it directly into existing street drains, which will carry the fluid to Park Lake and eventually the Brazos River. Fluid disposal activities are regulated by the Texas Railroad Commission. The local geology is determined by past displacements in the East Texas Basin. Boundaries are marked by the Balcones and the Mexia-Talco fault systems. All important water-bearing formations are in the cretaceous sedimentary rocks and are slightly to highly saline. Geothermal fluids are produced from the Trinity Group; they range from approximately 3600 to 4000 ppM TDS. Temperatures are expected to be above 64/sup 0/C (147/sup 0/F). Surface water flows southeastward as a part of the Brazos River Basin. The nearest perennial stream is the Brazos River 5.6 km (3.5 miles) away, to which surface fluids will eventually discharge. Environmental impacts of construction were small because of the existing structures and paved areas. Construction run-off and geothermal flow-test fluid passed through a small pond in the city park, lowering its water quality, at least temporarily. Construction noise was not out of character with existing noises around the hospital.

  6. Phase 1 of the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Not Available

    1991-08-01

    The work described in this report was prompted by the public's concern about potential effect from the radioactive materials released from the Hanford Site. The Hanford Environmental Dose Reconstruction (HEDR) Project was established to estimate radiation dose the public might have received from the Hanford Site since 1944, when facilities began operating. Phase 1 of the HEDR Project is a pilot'' or demonstration'' phase. The objectives of this initial phase were to determine whether enough historical information could be found or reconstructed to be used for dose estimation and develop and test conceptual and computational models for calculating credible dose estimates. Preliminary estimates of radiation doses were produced in Phase 1 because they are needed to achieve these objectives. The reader is cautioned that the dose estimates provided in this and other Phase 1 HEDR reports are preliminary. As the HEDR Project continues, the dose estimates will change for at least three reasons: more complete input information for models will be developed; the models themselves will be refined; and the size and shape of the geographic study area will change. This is one of three draft reports that summarize the first phase of the four-phased HEDR Project. This, the Summary Report, is directed to readers who want a general understanding of the Phase 1 work and preliminary dose estimates. The two other reports -- the Air Pathway Report and the Columbia River Pathway Report -- are for readers who understand the radiation dose assessment process and want to see more technical detail. Detailed descriptions of the dose reconstruction process are available in more than 20 supporting reports listed in Appendix A. 32 refs., 46 figs.

  7. Conceptual design report, plutonium stabilization and handling,project W-460

    SciTech Connect

    Weiss, E.V.

    1997-03-06

    Project W-460, Plutonium Stabilization and Handling, encompasses procurement and installation of a Stabilization and Packaging System (SPS) to oxidize and package for long term storage remaining plutonium-bearing special nuclear materials currently in inventory at the Plutonium Finishing Plant (PFP), and modification of vault equipment to allow storage of resulting packages of stabilized SNM for up to fifty years. This Conceptual Design Report (CDR) provides conceptual design details for the vault modification, site preparation and site interface with the purchased SPS. Two concepts are described for vault configuration; acceleration of this phase of the project did not allow completion of analysis which would clearly identify a preferred approach.

  8. Environmental Projects of Jewish and Arab Youth in Israel: The Adult Leaders' Views

    ERIC Educational Resources Information Center

    Alkaher, Iris; Tal, Tali

    2011-01-01

    Socio-environmental projects involving Arab and Jewish youth in Israel are uncommon. In this study, we interviewed 16 adult leaders of two projects that were carried out in the Galilee in northern Israel, to better understand the views of the leaders and their motives. The two projects focused on mutual environmental issues and dealt with social,…

  9. 77 FR 24976 - Environmental Impact Statement for the Proposed Wheatgrass Ridge Wind Project, Fort Hall Indian...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-04-26

    ... Bureau of Indian Affairs Environmental Impact Statement for the Proposed Wheatgrass Ridge Wind Project... on the Environmental Impact Statement (EIS) for the proposed Wheatgrass Ridge Wind Project on the... EIS because the proponent of the Wheatgrass Ridge Wind Project, the Wheatgrass Ridge Wind, LLC.,...

  10. 76 FR 67178 - Wells Hydroelectric Project; Notice of Availability of the Final Environmental Impact Statement...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-10-31

    ... Energy Regulatory Commission Wells Hydroelectric Project; Notice of Availability of the Final Environmental Impact Statement for the Wells Hydrolectric Project In accordance with the National Environmental... reviewed the application for license for the Wells Hydroelectric Project (FERC No. 2149), located on...

  11. Meeting Environmental Guidelines and Completing School Construction Projects on Time and Within Budget.

    ERIC Educational Resources Information Center

    Preyar, Chester F.

    2000-01-01

    Taxpayers expect school-construction projects to be managed efficiently and in accordance with environmental standards. Phases include selecting an architect and site, stating project requirements, working with the architect, considering environmental factors, getting budget estimates and reviews, and choosing a contractor and project-schedule…

  12. Systems Analysis Approach for the NASA Environmentally Responsible Aviation Project

    NASA Technical Reports Server (NTRS)

    Kimmel, William M.

    2011-01-01

    This conference paper describes the current systems analysis approach being implemented for the Environmentally Responsible Aviation Project within the Integrated Systems Research Program under the NASA Aeronautics Research Mission Directorate. The scope and purpose of these systems studies are introduced followed by a methodology overview. The approach involves both top-down and bottoms-up components to provide NASA s stakeholders with a rationale for the prioritization and tracking of a portfolio of technologies which enable the future fleet of aircraft to operate with a simultaneous reduction of aviation noise, emissions and fuel-burn impacts to our environment. Examples of key current results and relevant decision support conclusions are presented along with a forecast of the planned analyses to follow.

  13. 1995 annual epidemiologic surveillance report for Fernald Environmental Management Project

    SciTech Connect

    1995-12-31

    The US Department of Energy's (DOE) commitment to assuring the health and safety of its workers includes the conduct of epidemiologic surveillance activities that provide an early warning system for health problems among workers. During the past several years, a number of DOE sites have participated in the Epidemiologic Surveillance Program. This program monitors illnesses and health conditions that result in an absence of five or more consecutive workdays, occupational injuries and illnesses, and disabilities and deaths among current workers. This report provides a summary of epidemiologic surveillance data collected from the Fernald Environmental Management Project (FEMP) from January 1, 1995 through December 31, 1995. The data were collected by a coordinator at FEMP and submitted to the Epidemiologic Surveillance Data Center, located at Oak Ridge Institute for Science and Education, where quality control procedures and data analyses were carried out.

  14. Environmental assessment: Kotzebue Wind Installation Project, Kotzebue, Alaska

    SciTech Connect

    1998-05-01

    The DOE is proposing to provide financial assistance to the Kotzebue Electric Association to expand its existing wind installation near Kotzebue, Alaska. Like many rural Alaska towns, Kotzebue uses diesel-powered generators to produce its electricity, the high cost of which is currently subsidized by the Alaska State government. In an effort to provide a cost effective and clean source of electricity, reduce dependence on diesel fuel, and reduce air pollutants, the DOE is proposing to fund an experimental wind installation to test commercially available wind turbines under Arctic conditions. The results would provide valuable information to other Alaska communities experiencing similar dependence on diesel-powered generators. The environmental assessment for the proposed wind installation assessed impacts to biological resources, land use, electromagnetic interference, coastal zone, air quality, cultural resources, and noise. It was determined that the project does not constitute a major Federal action significantly affecting the quality of the human environment. Therefore, the preparation of an environmental impact statement is not required, and DOE has issued a Finding of No Significant Impact.

  15. Interdisciplinary environmental project probes Chesapeake Bay down to the core

    NASA Astrophysics Data System (ADS)

    Cronin, T.; Colman, S.; Willard, D.; Kerhin, R.; Holmes, C.; Karlsen, A.; Ishman, S.; Bratton, J.

    Interrelated environmental concerns about Chesapeake Bay are being addressed in an interdisciplinary project using paleoecological and geochemical records from sediment cores to investigate Holocene climate and human encroachment. The research is looking at interannual through millennial-scale variability of bay salinity,sediment accumulation, and dissolved oxygen, temperature, and faunal and floral trends. Current and planned research is expected to result in better restoration strategies by improving our understanding of the linkages between the bay's ecosystem, climate, and land use.Chesapeake Bay, the United States' largest and most productive estuary, faces several complex environmental issues, including eutrophication and anoxia in the main channel and tributaries, high turbidity and rates of sedimentation, outbreaks of the toxic dinoflagellate Pfiesteria piscicida, and coastal erosion and submergence tied to sea-level rise. Such problems often are attributed to human activities in the bay's watershed, including pollution, urbanization, and deforestation, but it now is recognized that climatic factors also strongly influence bay salinity, temperature, and water quality.

  16. Environmentally Conscious Manufacturing Project: ECM assessment guidance manual

    SciTech Connect

    Not Available

    1994-11-01

    The purpose of this document is to provide a summary of the basic tools that will be used in conducting assessments under the Environmentally Conscious Manufacturing (ECM) Project assessment program. ECM can cover a wide range of issues including: finding safer alternatives to toxic materials; changing processes to become more efficient; environmental costs and regulatory compliance; waste reduction; energy conservation; product packaging; and product reuse/recycling. The assessments performed as part of this program will try to identify opportunities to implement technologies/actions that will promote the types of results listed above. The general methodology, or sequence of events, that will be used in conducting assessments is as follows: 1. Form an Assessment Team; 2. Map Process by flow diagrams and materials accounting; 3. Identify opportunities for ECM by activity based accounting and pareto analysis; 4. Identify and evaluate ECM/pollution prevention alternatives; 5. Implement alternatives; 6. Monitor progress. All of the assessment steps listed above are addressed in this document except forming the assessment team. The tools discussed in this document are well known, widely used process analysis or quality improvement tools which have been adapted for use in evaluating opportunities for ECM/Pollution prevention.

  17. Nuclear criticality safety program for environmental restoration projects

    SciTech Connect

    Marble, R.C.; Brown, T.D.

    1994-05-01

    The Fernald Environmental Management Project (FEMP), formerly known as the Feed Materials Production Center (FMPC), is located on a 1050 acre site approximately twenty miles northwest of Cincinnati, Ohio. The production area of the site covers approximately 136 acres in the central portion of the site. Surrounding the core production area is a buffer consisting of leased grazing land, reforested land, and unused areas. The uranium processing facility was designed and constructed in the early 1950s. During the period from 1952 to 1989 the site produced uranium feed material and uranium products used in the United States weapons complex. Production at the site ended in 1989, when the site was shut down for what was expected to be a short period of time. However, the FUTC was permanently shut down in 1991, and the site`s mission was changed from production to environmental restoration. The objective of this paper is to give an update on activities at the Fernald Site and to describe the Nuclear Criticality Safety issues that are currently being addressed.

  18. Pollution prevention in environmental restoration projects: communication, innovation, and implementation

    SciTech Connect

    Wilczek, T.A.

    1996-11-01

    With the change in US Department of Energy`s (DOE) primary mission from weapons production to complex clean-up, there is an increased emphasis to utilize proven tools and techniques that, when modified, will assist in this massive remediation effort. Tools and techniques which increase process efficiency while minimizing costs are highly attractive. The introduction of formalized Pollution Prevention (P2) practices into the DOE Environmental Restoration (ER) program should be encouraged to the measurable degree of success that P2 has obtained in DOE process operations. Most notably, the integration of Pollution Prevention Opportunity Assessments (PPOAs) into the ER process is highly recommended for three reasons: waste stream generation volumes will be minimized; the results of P2 implementation will be properly measured, quantified, and documented for use on other projects; and negative impacts to human health and the environment will be lessened. the application of P2 principles is encouraged as a Best Management Practice (BMP), in addition to minimizing waste generation to achieve DOE waste reduction goals. The challenge is how to apply P2 practices to ER projects and obtain quantifiable waster reductions.

  19. Environmental assessment of the Environmental Restoration Project at Sandia National Laboratories/New Mexico

    SciTech Connect

    1996-03-01

    Sandia National Laboratories/New Mexico (SNL/NM) is managed and operated for the U.S. Department of Energy (DOE) by Sandia Corporation, a subsidiary of the Lockheed Martin Company. SNL/NM is located on land controlled by DOE within the boundaries of Kirtland Air Force Base (KAFB) in Albuquerque, New Mexico. The major responsibilities of SNL/NM are the support of national security and energy projects. This report provides an environmental assessment of proposed remedial action activities at the solid waste management units at SNL/NM. A risk assessment of health hazards is also discussed.

  20. Telephone Flat Geothermal Development Project Environmental Impact Statement Environmental Impact Report. Final: Comments and Responses to Comments

    SciTech Connect

    1999-02-01

    This document is the Comments and Responses to Comments volume of the Final Environmental Impact Statement and Environmental Impact Report prepared for the proposed Telephone Flat Geothermal Development Project (Final EIS/EIR). This volume of the Final EIS/EIR provides copies of the written comments received on the Draft EIS/EIR and the leady agency responses to those comments in conformance with the requirements of the National Environmental Policy Act (NEPA) and the California Environmental Quality Act (CEQA).

  1. Environmental assessment -- Proposed neutrino beams at the Main Injector project

    SciTech Connect

    1997-12-01

    The US Department of Energy (DOE) proposes to build a beamline on the Fermi National Accelerator Laboratory (Fermilab) site to accommodate an experimental research program in neutrino physics. The proposed action, called Neutrino Beams at the Main Injector (NuMI), is to design, construct, operate and decommission a facility for producing and studying a high flux beam of neutrinos in the energy range of 1 to 40 GeV (1 GeV is one billion or 10{sup 9} electron volts). The proposed facility would initially be dedicated to two experiments, COSMOS (Cosmologically Significant Mass Oscillations) and MINOS (Main Injector Neutrino Oscillation Search). The neutrino beam would pass underground from Fermilab to northern Minnesota. A tunnel would not be built in this intervening region because the neutrinos easily pass through the earth, not interacting, similar to the way that light passes through a pane of glass. The beam is pointed towards the MINOS detector in the Soudan Underground Laboratory in Minnesota. Thus, the proposed project also includes construction, operation and decommissioning of the facility located in the Soudan Underground Laboratory in Minnesota that houses this MINOS detector. This environmental assessment (EA) has been prepared by the US Department of Energy (DOE) in accordance with the DOE`s National Environmental Policy Act (NEPA) Implementing Procedures (10 CFR 1021). This EA documents DOE`s evaluation of potential environmental impacts associated with the proposed construction and operation of NuMI at Fermilab and its far detector facility located in the Soudan Underground Laboratory in Minnesota. Any future use of the facilities on the Fermilab site would require the administrative approval of the Director of Fermilab and would undergo a separate NEPA review. Fermilab is a Federal high-energy physics research laboratory in Batavia, Illinois operated on behalf of the DOE by Universities Research Association, Inc.

  2. Scoping session of the programmatic environmental impact statement for the uranium mill tailings remedial action project

    SciTech Connect

    Not Available

    1992-12-08

    This report contains documentation of the scoping session of the environmental impact statement for the Uranium Mill Tailings Remedial Action Project. The purpose of the meeting was to talk about the Programmatic Environmental Impact Statement on the groundwater.

  3. Sustainable Urban Waters: Opportunities to Integrate Environmental Protection in Multi-objective Projects

    EPA Science Inventory

    Abstract: Nonpoint source pollution is an ongoing challenge for environmental agencies who seek to protect waters of the U.S. Urban stream and waterfront redevelopment projects present opportunities to achieve integrated environmental, economic, and social benefits in urban water...

  4. Preoperational Environmental Survey for the Spent Nuclear Fuel (SNF) Project Facilities

    SciTech Connect

    MITCHELL, R.M.

    2000-10-12

    This document represents the report for environmental sampling of soil, vegetation, litter, cryptograms, and small mammals at the Spent Nuclear Fuel Project facilities located in 100 K and 200 East Areas in support of the preoperational environmental survey.

  5. Preoperational Environmental Survey for the Spent Nuclear Fuel (SNF) Project Facilities

    SciTech Connect

    MITCHELL, R.M.

    2000-09-28

    This document represents the report for environmental sampling of soil, vegetation, litter, cryptograms, and small mammals at the Spent Nuclear Fuel Project facilities located in 100 K and 200 East Areas in support of the preoperational environmental survey.

  6. Projects at the Western Environmental Technology Office. Quarterly technical progress report, April 1--June 30, 1995

    SciTech Connect

    1995-08-01

    This report contains brief outlines of the multiple projects under the responsibility of the Western Environmental Technology Office in Butte Montana. These projects include biomass remediation, remediation of contaminated soils, mine waste technology, and several other types of remediation.

  7. 76 FR 76121 - Revised Notice, Draft Environmental Impact Statement, Rosemont Copper Project on the Coronado...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-12-06

    ... From the Federal Register Online via the Government Publishing Office DEPARTMENT OF AGRICULTURE Forest Service Revised Notice, Draft Environmental Impact Statement, Rosemont Copper Project on the..., Coronado National Forest, published a Notice of Availability of the Rosemont Copper Project...

  8. The Department of Energy, Office of Environmental Restoration and Waste Management: Project performance study

    SciTech Connect

    Not Available

    1993-11-01

    The Office of Environmental Restoration and Waste Management (EM) of the US Department of Energy commissioned Independent Project Analysis, Inc. (IPA) to perform this Project Performance Study to provide a quantitative analysis determining how well EM develops and executes environmental remediation and waste management projects. The approach consisted of collecting detailed data on a sample of 65 completed and ongoing EM projects conducted since 1984. These data were then compared with key project characteristics and outcomes from 233 environmental remediation projects (excluding EM) in IPA`s Environmental Remediation Database and 951 projects In IPA`s Capital Projects Database. The study establishes the standing of the EM system relative to other organizations, and suggests areas and opportunities for improvement.

  9. Environmental and Mechanical Stability of Environmental Barrier Coated SA Tyrannohex SiC Composites Under Simulated Turbine Engine Environments

    NASA Technical Reports Server (NTRS)

    Zhu, Dongming; Halbig, Michael Charles; Sing, Mrityunjay

    2014-01-01

    The environmental stability and thermal gradient cyclic durability performance of SA Tyrannohex composites were investigated for turbine engine component applications. The work has been focused on investigating the combustion rig recession, cyclic thermal stress resistance and thermomechanical low cycle fatigue of uncoated and environmental barrier coated Tyrannohex SiC SA composites in simulated turbine engine combustion water vapor, thermal gradients, and mechanical loading conditions. Flexural strength degradations have been evaluated, and the upper limits of operating temperature conditions for the SA composite material systems are discussed based on the experimental results.

  10. Hanford Environmental Dose Reconstruction Project, Quarterly report, September--November 1993

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1993-12-31

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates); Source Terms, Environmental Transport, Environmental Monitoring Data, Demography, Food Consumption, and Agriculture, and Environmental Pathways and Dose Estimates.

  11. Site environmental report for the Yucca Mountain Project. Calendar Year 2005

    SciTech Connect

    None, None

    2006-10-01

    This site environmental report describes the environmental program conducted during 2005 by the U.S. Department of Energy, Office of Repository Development. The report describes the environmental laws and regulations that were applicable to the Yucca Mountain Project in 2005, the actions taken to comply with those laws and regulations, and the Project’s environmental program. The report also summarizes the data collected to monitor potential impacts of the Project on the environment.

  12. Hanford Environmental Dose Reconstruction Project. Quarterly report, December 1993--February 1994

    SciTech Connect

    Cannon, S.D.

    1994-04-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radio-nuclides followed from release to impact on humans(dose estimates): source terms; environmental transport; environmental monitoring data; demography, food consumption, agriculture; environmental pathways; and dose estimates.

  13. Hanford Environmental Dose Reconstruction Project. Quarterly report, June--August 1993

    SciTech Connect

    Cannon, S.D.; Finch, S.M.

    1993-10-01

    The objective of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate the radiation doses that individuals and populations could have received from nuclear operations at Hanford since 1944. The project is divided into the following technical tasks. These tasks correspond to the path radionuclides followed from release to impact on humans (dose estimates): Source Terms, Environmental Transport, Environmental Monitoring Data, Demography, Food Consumption, and Agriculture, and Environmental Pathways and Dose Estimates.

  14. Patterns of developmental stability of Chrysopa perla L. (Neuroptera: Chrysopidae) in response to environmental pollution

    SciTech Connect

    Clarke, G.M. )

    1993-12-01

    The level of developmental stability of Chrysopa perla L. (Neuroptera: Chrysopidae) collected from control and contaminated sites in the vicinity of an agrochemical manufacturing facility was assessed using fluctuating asymmetry and phenodeviant analysis. There were no significant differences in the level of asymmetry between control and contaminated sites for four characters. The number of phenodeviants for two characters was significantly greater at sites located in close proximity to the facility compared with a control site. Results are discussed with reference to the relationship between asymmetry and phenodeviants as indicators of stability and the use of development stability as a means of assessing environmental quality.

  15. Fluor Hanford Nuclear Material Stabilization Project Welding Manual

    SciTech Connect

    BERKEY, J.R.

    2000-10-20

    The purpose of this section of the welding manual is to: (1) Provide a general description of the major responsibilities of the organizations involved with welding. (2) Provide general guidance concerning the application of codes related to welding. This manual contains requirements for welding for all Fluor Hanford (FH) welding operators working on the W460 Project, in the Plutonium Finishing Plant (PFP) at the U. S. Department of Energy (DOE) Hanford facilities. These procedures and any additional requirements for these joining processes can be used by all FH welding operators that are qualified. The Welding Procedure Specifications (WPS) found in this document were established from Procedure Qualification Records (PQR) qualified by FH specifically for the W460 Project. PQRs are permanent records of the initial testing and qualification program and are used to backup, and support, the WPS. The identification numbers of the supporting PQR(s) are recorded on each WPS. All PQRs are permanently stored under the supervision of the Fluor Hanford Welding Engineer (FHWE). New PQRs and WPSs will continue to be developed as necessary. The qualification of welders, welding operators and welding procedures will be performed for FH under supervision and concurrent of the FHWE. All new welding procedures to be entered in this manual or welder personnel to be added to the welder qualification database, shall be approved by the FHWE.

  16. Enhancement of stability of various nZVI suspensions used in groundwater remediation with environmentally friendly organic stabilizers

    NASA Astrophysics Data System (ADS)

    Schmid, Doris; Wagner, Stephan; Velimirović, Milica; Laumann, Susanne; Micić, Vesna; Hofmann, Thilo

    2014-05-01

    The use of nanoscale zero-valent iron (nZVI) particles for in situ remediation of polluted soil and groundwater has been shown as one of the most promising techniques [1]. The success of this technology depends on the mobility, reactivity, and longevity of nZVI particles. The mobility of nZVI particles depends on the properties of the single particles, stability of the particle suspension, and the aquifer material [1,2]. In order to enhance the mobility of nZVI, the mobility-decisive properties of the nZVI particles in suspension such as concentration, size distribution, surface charge, and sedimentation rate have to be investigated and optimized. Previous studies showed that pristine nZVI particles aggregate rapidly in water, reducing the particles radius of influence after injection [3]. In order to prevent aggregation and sedimentation of the nZVI particles, and consequently improve the stability of nZVI suspension and therefore the mobility of the nZVI particles, surface stabilizers can be used to provide electrostatic repulsion and steric or electrosteric stabilization [3,4]. The objective of this lab-scale study is to investigate the potential for enhancing the stability of different nZVI suspensions by means of environmentally friendly organic stabilizers, including carboxymethyl cellulose, pectin, alginate, xanthan, and guar gum. The different nZVI particles used included pristine and polyacrylic acid-coated nZVI particles provided in suspension (Nanofer 25 and Nanofer 25S, respectively, NANOIRON s.r.o., Czech Republic), air-stable nZVI particles (Nanofer Star, (NANOIRON s.r.o., Czech Republic), and milled iron flakes (UVR-FIA, Germany). In order to study the enhancement of nZVI stability (1 g L-1 total iron) different concentrations of organic stabilizers (1-20 wt.%) were applied in these nZVI suspensions. Each nZVI suspension was freshly prepared and treated for 10 minutes with Ultra-Turrax (15 000 rpm) and 10 minutes ultrasonic bath prior to

  17. Ebola Virus RNA Stability in Human Blood and Urine in West Africa’s Environmental Conditions

    PubMed Central

    Delaune, Deborah; Poyot, Thomas; Valade, Eric; Mérens, Audrey; Rollin, Pierre E.; Foissaud, Vincent

    2016-01-01

    We evaluated RNA stability of Ebola virus in EDTA blood and urine samples collected from infected patients and stored in West Africa’s environmental conditions. In blood, RNA was stable for at least 18 days when initial cycle threshold values were <30, but in urine, RNA degradation occurred more quickly. PMID:26812135

  18. Genetic and Environmental Stability in Attention Problems across the Lifespan: Evidence from the Netherlands Twin Register

    ERIC Educational Resources Information Center

    Kan, Kees-Jan; Dolan, Conor V.; Nivard, Michel G.; Middeldorp, Christel M.; van Beijsterveldt, Catharina E. M.; Willemsen, Gonneke; Boomsma, Dorret I.

    2013-01-01

    Objective: To review findings on attention-deficit/hyperactivity disorder and attention problems (AP) in children, adolescents, and adults, as established in the database of the Netherlands Twin Register and increase the understanding of stability in AP across the lifespan as a function of genetic and environmental influences. Method: A…

  19. Use of remotely operated excavators for environmental restoration projects

    SciTech Connect

    Kruse, P.W.; Wilson, J.

    1995-12-31

    In support of the Department of Energy (DOE)`s environmental restoration program, Spar and RSI have modified a Hitachi model EX200LC for remote operation. For projects requiring the retrieval of certain types of radioactive and hazardous buried waste, the toxic nature of the material will require that remotely operated equipment be used to retrieve the waste. For the recovery of buried boxes and drums, an excavator that has been modified for remote operation provides both the high payload capacity as well as the ruggedness to safely and efficiently recover this type of material. The control system for the excavator uses coordinated control technology to assist the operator in controlling the position and movement of the bucket and end effectors. The remotely operated excavator as well as a teleoperated transport vehicle were recently demonstrated in the field as part of the first phase of the remote conveyance system and innovative end effector development program for the DOE Buried Waste Integrated Demonstration Program at the Idaho National Engineering Laboratory (INEL).

  20. Houston Environmental Aerosol Thunderstorm (HEAT) Project - 2004/2005

    NASA Astrophysics Data System (ADS)

    Orville, R. E.

    2002-12-01

    For over thirteen years the National Lightning Detection Network (NLDN) has been in operation collecting cloud-to-ground (CG) lightning data for the continental United States. Geographical areas of enhanced lightning flashes, or `hot spots', have been detected in this data set. One such observed hot spot is near the city of Houston, Texas, the most polluted city in the United States. The phenomenon has been studied with the available data and hypotheses made as to the reason for the lightning hot spot. However, more comprehensive data sets are needed in order to further examine this occurrence. The Houston Environmental Aerosol Thunderstorm (HEAT) Project will obtain the data sets necessary for further study of the hot spot near Houston and is planned for the summers of 2004/2005. The primary goals of HEAT are to examine the effects of pollution, the urban heat island, and the complex coastline on storms and lightning characteristics in the Houston area. In addition we will determine the relative amounts of lightning-produced and convectively transported NOx

  1. Bacterial lipopolysaccharide binding enhances virion stability and promotes environmental fitness of an enteric virus.

    PubMed

    Robinson, Christopher M; Jesudhasan, Palmy R; Pfeiffer, Julie K

    2014-01-15

    Enteric viruses, including poliovirus and reovirus, encounter a vast microbial community in the mammalian gastrointestinal tract, which has been shown to promote virus replication and pathogenesis. Investigating the underlying mechanisms, we find that poliovirus binds bacterial surface polysaccharides, which enhances virion stability and cell attachment by increasing binding to the viral receptor. Additionally, we identified a poliovirus mutant, VP1-T99K, with reduced lipopolysaccharide (LPS) binding. Although T99K and WT poliovirus cell attachment, replication, and pathogenesis in mice are equivalent, VP1-T99K poliovirus was unstable in feces following peroral inoculation of mice. Consequently, the ratio of mutant virus in feces is reduced following additional cycles of infection in mice. Thus, the mutant virus incurs a fitness cost when environmental stability is a factor. These data suggest that poliovirus binds bacterial surface polysaccharides, enhancing cell attachment and environmental stability, potentially promoting transmission to a new host.

  2. 75 FR 7029 - Notice of Availability of the Final Environmental Assessment for Solar Roof Project

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-02-16

    ... Geological Survey Notice of Availability of the Final Environmental Assessment for Solar Roof Project AGENCY..., the US Geological Survey (USGS) has prepared a Final Environmental Assessment for the Solar Roof... for the Solar Roof Project should immediately contact the USGS S.O. Conte Anadromous Fish...

  3. 42 CFR 137.301 - How are project and program environmental review costs identified?

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 42 Public Health 1 2010-10-01 2010-10-01 false How are project and program environmental review... HUMAN SERVICES INDIAN HEALTH SERVICE, DEPARTMENT OF HEALTH AND HUMAN SERVICES TRIBAL SELF-GOVERNANCE Construction Nepa Process § 137.301 How are project and program environmental review costs identified? (a)...

  4. Children as Community Planners: Report on an Environmental Design Project 1.

    ERIC Educational Resources Information Center

    Hanley, Gerard L.; And Others

    1981-01-01

    Describes a six-month project emphasizing participant-observation teaching strategy in which a third-grade class of 24 students employed methods of environmental design to design communities within a modern forest and more primitive tundra and desert regions. Discusses project goals, results, and implications for future use of environmental design…

  5. ECP (Environmental Conservation Project) Report, No. 8, December 1976. ECP State Bibliography.

    ERIC Educational Resources Information Center

    Dean, Norman L., Ed.

    This issue of the Environmental Conservation Project (ECP) Report contains the second supplement to the "ECP State Bibliography," a collection of state energy legislation compiled by the Energy Conservation Project at the Environmental Law Institute. Earlier publications of state legislative actions appear in the October 1975 and January 1976…

  6. 76 FR 21338 - Reopening of Scoping Period for the Northern Pass Transmission Line Project Environmental Impact...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-04-15

    ... Reopening of Scoping Period for the Northern Pass Transmission Line Project Environmental Impact Statement... (DOE) is reopening the public scoping period for the Northern Pass Transmission Line Project... environmental impacts from its proposal to grant a Presidential Permit to Northern Pass Transmission, LLC,...

  7. 76 FR 21403 - Notice of Availability of the Final Environmental Impact Statement for the Genesis Project...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-04-15

    ... Final Environmental Impact Statement (EIS) for the Newmont Mining Corporation's proposed Genesis Project...] Notice of Availability of the Final Environmental Impact Statement for the Genesis Project, Eureka County... addressed in the Draft EIS include: (1) The cumulative impacts of mining and related actions on...

  8. 41 CFR 102-80.75 - Who assesses environmental issues in Federal construction and lease construction projects?

    Code of Federal Regulations, 2011 CFR

    2011-01-01

    ... construction and lease construction projects? Federal agencies must assess required environmental issues throughout planning and project development so that the environmental impacts of a project are considered... environmental issues in Federal construction and lease construction projects? 102-80.75 Section 102-80.75...

  9. 15 CFR 291.3 - Environmental tools and techniques projects.

    Code of Federal Regulations, 2013 CFR

    2013-01-01

    ... accessible environmental information resources, environmental demonstration facilities, software tools, etc... continuous improvement of the tool. Factors that may be considered include: Thoroughness of evaluation plans... process. Factors that may be considered include: Appropriateness and authority of the governing...

  10. 15 CFR 291.3 - Environmental tools and techniques projects.

    Code of Federal Regulations, 2012 CFR

    2012-01-01

    ... accessible environmental information resources, environmental demonstration facilities, software tools, etc... continuous improvement of the tool. Factors that may be considered include: Thoroughness of evaluation plans... process. Factors that may be considered include: Appropriateness and authority of the governing...

  11. Drought Prediction for Socio-Cultural Stability Project

    NASA Technical Reports Server (NTRS)

    Peters-Lidard, Christa; Eylander, John B.; Koster, Randall; Narapusetty, Balachandrudu; Kumar, Sujay; Rodell, Matt; Bolten, John; Mocko, David; Walker, Gregory; Arsenault, Kristi; Rheingrover, Scott

    2014-01-01

    The primary objective of this project is to answer the question: "Can existing, linked infrastructures be used to predict the onset of drought months in advance?" Based on our work, the answer to this question is "yes" with the qualifiers that skill depends on both lead-time and location, and especially with the associated teleconnections (e.g., ENSO, Indian Ocean Dipole) active in a given region season. As part of this work, we successfully developed a prototype drought early warning system based on existing/mature NASA Earth science components including the Goddard Earth Observing System Data Assimilation System Version 5 (GEOS-5) forecasting model, the Land Information System (LIS) land data assimilation software framework, the Catchment Land Surface Model (CLSM), remotely sensed terrestrial water storage from the Gravity Recovery and Climate Experiment (GRACE) and remotely sensed soil moisture products from the Aqua/Advanced Microwave Scanning Radiometer - EOS (AMSR-E). We focused on a single drought year - 2011 - during which major agricultural droughts occurred with devastating impacts in the Texas-Mexico region of North America (TEXMEX) and the Horn of Africa (HOA). Our results demonstrate that GEOS-5 precipitation forecasts show skill globally at 1-month lead, and can show up to 3 months skill regionally in the TEXMEX and HOA areas. Our results also demonstrate that the CLSM soil moisture percentiles are a goof indicator of drought, as compared to the North American Drought Monitor of TEXMEX and a combination of Famine Early Warning Systems Network (FEWS NET) data and Moderate Resolution Imaging Spectrometer (MODIS)'s Normalizing Difference Vegetation Index (NDVI) anomalies over HOA. The data assimilation experiments produced mixed results. GRACE terrestrial water storage (TWS) assimilation was found to significantly improve soil moisture and evapotransportation, as well as drought monitoring via soil moisture percentiles, while AMSR-E soil moisture

  12. Phase 1 of the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Not Available

    1990-07-20

    For more than 40 years, the US government made plutonium for nuclear weapons at the Hanford Site in southeastern Washington State. Radioactive materials were released to both the air and water from Hanford. People could have been exposed to these materials, called radionuclides. The Hanford Environmental Dose Reconstruction (HEDR) Project is a multi-year scientific study to estimate the radiation doses the public may have received as a results of these releases. The study began in 1988. During the first phase, scientists began to develop and test methods for reconstructing the radiation doses. To do this, scientists found or reconstructed information about the amount and type of radionuclides that were released from Hadford facilities, where they traveled in environment, and how they reached people. Information about the people who could have been exposed was also found or reconstructed. Scientists then developed a computer model that can estimate doses from radiation exposure received many years ago. All the information that had been gathered was fed into the computer model. Then scientists did a test run'' to see whether the model was working properly. As part of its test run,'' scientists asked the computer model to generate two types of preliminary results: amounts of radionuclides in the environment (air, soil, pasture grass, food, and milk) and preliminary doses people could have received from all the routes of radiation exposure, called exposure pathways. Preliminary dose estimates were made for categories of people who shared certain characteristics and for the Phase 1 population as a whole. 26 refs., 48 figs.

  13. 42 CFR 137.329 - What environmental considerations must be included in the construction project agreement?

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... SELF-GOVERNANCE Construction Project Assumption Process § 137.329 What environmental considerations....311. (c) Identification of the environmental review procedures adopted by the Self-Governance Tribe... environmental determination in accordance with the Self-Governance Tribe's adopted procedures....

  14. West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2006

    SciTech Connect

    West Valley Nuclear Services Company and URS Group, Inc.

    2007-09-27

    Annual Site Environmental Report for the West Valley Demonstration Project (WVDP) for Calendar Year 2006. The report summarizes calendar year (CY) 2006 environmental monitoring data so as to describe the performance of the WVDP’s environmental management system (EMS), confirm compliance with standards and regulations, and highlight important programs that protect public health and safety and the environment.

  15. West Valley Demonstration Project Annual Site Environmental Report Calendard Year 2005

    SciTech Connect

    West Valley Nuclear Services Company and URS Group, Inc.

    2006-09-21

    Annual Site Environmental Report for the West Valley Demonstration Project (WVDP) for Calendar Year 2005. The report summarizes calendar year (CY) 2005 environmental monitoring data so as to describe the performance of the WVDP's environmental management system (EMS), confirm compliance with standards and regulations, and highlight important programs.

  16. 75 FR 10500 - Environmental Assessment Prepared for Proposed Cape Wind Energy Project in Nantucket Sound, MA

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-03-08

    ... Minerals Management Service Environmental Assessment Prepared for Proposed Cape Wind Energy Project in... of an Environmental Assessment (EA) and Draft Finding of No New Significant Impact (FONNSI) for... regulations that implement the National Environmental Policy Act (NEPA), announces the availability for...

  17. Final Project Summary Report Bechtel Nevada and Fiberchem Environmental, Inc., Cooperative Research and Technology Development Project

    SciTech Connect

    R. J. Pollina

    1999-04-01

    This is a report summarizing work on a small project dedicated to adapting a new chemical sensing platform for the US Department of Energy and its customers. At the same time and in the spirit of technology transfer, FCI Environmental, Inc., would receive technical support in the form of expertise from the US Department of Energy to assist in developing this product. The sensor is a hybrid integrated-circuit, optical waveguide, chemical sensor that is patented by FCI Environmental, Inc., and manufactured under license by Texas Instruments, Inc. A down-hole penetrometer probe was designed for use in hot, 60 C, hydrocarbon-saturated, saline environment at a depth of 200 feet. The probe design includes three chemical sensing, hybrid integrated-circuits with chemical reference and measurement channels, a water seal, output electronics, and a removable measurement head for replacement in the field. A hand-held chemical detector prototype--containing a hybrid integrated-circuit chemical sensor with reference channel, user alarm, and level display--was designed and constructed, and a software interface developed to operate the hand-held sensor interfaced with a laboratory data acquisition system.

  18. 75 FR 81210 - Wrangell Ranger District; Alaska; Wrangell Island Project Environmental Impact Statement

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-12-27

    ... Forest Service Wrangell Ranger District; Alaska; Wrangell Island Project Environmental Impact Statement...) for the Wrangell Island Project located on Wrangell Island, part of the Wrangell Ranger District of... to: SWCA, 317 Forest Park Drive, Ketchikan, AK 99901, Attn: Wrangell Island Project EIS. Comments...

  19. 78 FR 35630 - Martin Dam Hydroelectric Project; Notice of Availability of the Draft Environmental Impact...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-06-13

    ... Energy Regulatory Commission Martin Dam Hydroelectric Project; Notice of Availability of the Draft Environmental Impact Statement for the Martin Dam Hydroelectric Project and Intention To Hold Public Meetings In... reviewed the application for license for the Martin Dam Hydroelectric Project (FERC No. 349), located...

  20. 76 FR 20657 - Wells Hydroelectric Project; Notice of Availability of the Draft Environmental Impact Statement...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-04-13

    ... Energy Regulatory Commission Wells Hydroelectric Project; Notice of Availability of the Draft Environmental Impact Statement for the Wells Hydrolectric Project and Intention To Hold Public Meetings In... Office of Energy Projects has reviewed the application for license for the Wells Hydroelectric...

  1. 75 FR 352 - Enloe Hydroelectric Project; Notice of Application Ready for Environmental Analysis and...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-01-05

    ... Doc No: E9-31210] DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 12569-001] Enloe Hydroelectric Project; Notice of Application Ready for Environmental Analysis and Soliciting... Hydroelectric Project. f. Location: On the Similkameen River, in the Town of Oroville, Okanogan...

  2. L2 -stability of haptic systems with projection-based force reflection.

    PubMed

    Polushin, Ilia G; Hasan, Mir Zayed

    2014-01-01

    The problem of stability of haptic interaction with virtual objects is addressed, where the force reflection is implemented using the projection-based principle. A stability condition is derived that generalizes some previously known results to the case of projection-based force reflection. It demonstrates that, in this case, an additional design parameter is brought in that allows to increase the admissible stiffness of the virtual wall and decrease the update rate without changing the damping of the haptic device. A passivity based interpretation of the result is given in terms of interconnection of generalized passive systems where the excess of passivity of haptic device compensates the shortage of passivity of the virtual wall. In particular, it is shown that the projection-based force reflection allows to arbitrarily increase the excess of passivity of the haptic device without changing its physical damping.

  3. In Situ Mercury Stabilization (ISMS) Treatment: Technology Maturation Project Phase I Status Report

    SciTech Connect

    Kalb,P.D.; Milian, L.

    2008-03-01

    Mercury (Hg) was used to separate lithium-6 isotope for weapons production at the Y-12 Plant in Oak Ridge in the 1950s and 1960s. As much as two million pounds of elemental mercury was 'lost' or unaccounted for and a large portion of that material is believed to have entered the environment. The DOE site office in Oak Ridge has identified Hg pollution in soils, sediments, and streams as the most significant environmental challenge currently faced. In industry, large amounts of mercury have been used to manufacture products (e.g., fluorescent light bulbs, thermometers) and for chemical processing (e.g., production of chlorine and alkali via mercury electrochemical cells) and many of these industrial sites are now polluted with mercury contaminated soil as a result of previous releases and/or inadvertent leaks. Remediation techniques for Hg contaminated soils are either based on thermal desorption and recovery of the mercury or excavation and shipping of large volumes of material to remote facilities for treatment and disposal. Both of these alternatives are extremely costly. The Brookhaven National Laboratory (BNL) Environmental Research & Technology Division (ERTD) has demonstrated, in laboratory-scale experiments, the viability of treating mercury contaminated soils by means of sulfide treatment rods inserted into the soil through a process known as In Situ Mercury Stabilization (ISMS). This approach is partly based on BNL's patented and successfully licensed ex situ process for Hg treatment, Sulfur Polymer Stabilization/Solidification (SPSS) which converts Hg to the more stable sulfide form. The original experiments showed that Hg homogeneously distributed in soil rapidly migrates to form a high concentration zone of chemically stable mercuric sulfide near the treatment rods while concentrations of Hg in surrounding areas away from the treatment rods are depleted to acceptable levels. BSA has subsequently filed for patent protection on the ISMS technology. If

  4. Environmental Friendly Coatings and Corrosion Prevention For Flight Hardware Project

    NASA Technical Reports Server (NTRS)

    Calle, Luz

    2014-01-01

    Identify, test and develop qualification criteria for environmentally friendly corrosion protective coatings and corrosion preventative compounds (CPC's) for flight hardware an ground support equipment.

  5. ANNUAL REPORT FOR ENVIRONMENTAL MANAGEMENT SCIENCE PROGRAM PROJECT NUMBER 87016 CO-PRECIPITATION OF TRACE METALS IN GROUNDWATER AND VADOSE ZONE CALCITE: IN SITU CONTAINMENT AND STABILIZATION OF STRONTIUM-90 AND OTHER DIVALENT METALS AND RADIONUCLIDES AT ARID WESTERN DOE SITES

    SciTech Connect

    Smith, Robert W.; Fujita, Yoshiko; Ferris, F. Grant; Cosgrove, Donna M.; Colwell, F. S.

    2003-06-15

    Radionuclide and metal contaminants such as 90Sr are present beneath U.S. Department of Energy (DOE) lands in both the groundwater (e.g., 100-N area at Hanford, WA) and vadose zone (e.g., Idaho Nuclear Technology and Engineering Center at the Idaho National Engineering and Environmental Laboratory). In situ containment and stabilization of these contaminants is a cost-effective treatment strategy. However, implementing in situ containment and stabilization approaches requires definition of the mechanisms that control contaminant sequestration. We are investigating the in situ immobilization of radionuclides or contaminant metals (e.g., 90Sr) by their facilitated co-precipitation with calcium carbonate in groundwater and vadose zone systems. Our facilitated approach, shown schematically in Figure 1, relies upon the hydrolysis of introduced urea to cause the acceleration of calcium carbonate precipitation (and trace metal co-precipitation) by increasing pH and alkalinity. Subsurface urea hydrolysis is catalyzed by the urease enzyme, which may be either introduced with the urea or produced in situ by ubiquitous subsurface urea hydrolyzing microorganisms. Because the precipitation process tends to be irreversible and many western aquifers are saturated with respect to calcite, the coprecipitated metals and radionuclides will be effectively removed from the aqueous phase over the long-term. Another advantage of the ureolysis approach is that the ammonium ions produced by the reaction can exchange with radionuclides sorbed to subsurface minerals, thereby enhancing the availability of the radionuclides for re-capture in a more stable solid phase (co-precipitation rather than adsorption).

  6. Environmental impact assessments of the Three Gorges Project in China: Issues and interventions

    NASA Astrophysics Data System (ADS)

    Xu, Xibao; Tan, Yan; Yang, Guishan

    2013-09-01

    The paper takes China's authoritative Environmental Impact Statement for the Yangzi (Yangtze) Three Gorges Project (TGP) in 1992 as a benchmark against which to evaluate emerging major environmental outcomes since the initial impoundment of the Three Gorges reservoir in 2003. The paper particularly examines five crucial environmental aspects and associated causal factors. The five domains include human resettlement and the carrying capacity of local environments (especially land), water quality, reservoir sedimentation and downstream riverbed erosion, soil erosion, and seismic activity and geological hazards. Lessons from the environmental impact assessments of the TGP are: (1) hydro project planning needs to take place at a broader scale, and a strategic environmental assessment at a broader scale is necessary in advance of individual environmental impact assessments; (2) national policy and planning adjustments need to react quickly to the impact changes of large projects; (3) long-term environmental monitoring systems and joint operations with other large projects in the upstream areas of a river basin should be established, and the cross-impacts of climate change on projects and possible impacts of projects on regional or local climate considered.

  7. Tiered environmental risk assessment of methyltins from heat stabilizers in rigid PVC in Sweden.

    PubMed

    van Dokkum, Henno P; Huwer, Sherri L

    2005-02-01

    The methyltins, methyltin 2-ethylhexyl mercaptoacetate and methyltin-2-mercaptoethyloleate sulfide, are used as heat stabilizers in rigid PVC. The degradation products monomethyltintrichloride (MMTTC) and dimethyltindichloride (DMTDC) may leach from the PVC, and enter the environment. A risk assessment was executed for the use of these products in Sweden, with the double aim to (a) assess the potential environmental risks, and (b) explore the possibilities of a tiered risk assessment. An initial assessment was executed with EUSES 1.0. The initial assessment showed no significant environmental risks on a regional scale. On a local scale however, emissions from a sewage treatment plant to the surface water pose a potential risk for the near proximity. In a second tier, this critical exposure route was studied in more detail; an improved exposure scenario was drawn up; and an additional sorption experiment was performed. This refinement resulted in much lower predicted environmental concentrations (stabilizers are registered, reveal concentrations ranging from < detection limit to intermediate values between concentrations predicted in the initial and refined assessment. The tiered assessment scheme proved valuable. Using this, the environmental risks due to the leaching of MMTTC and DMTDC from rigid PVC in Sweden are of no concern.

  8. Acanthamoeba polyphaga mimivirus stability in environmental and clinical substrates: implications for virus detection and isolation.

    PubMed

    Dornas, Fábio P; Silva, Lorena C F; de Almeida, Gabriel M; Campos, Rafael K; Boratto, Paulo V M; Franco-Luiz, Ana P M; La Scola, Bernard; Ferreira, Paulo C P; Kroon, Erna G; Abrahão, Jônatas S

    2014-01-01

    Viruses are extremely diverse and abundant and are present in countless environments. Giant viruses of the Megavirales order have emerged as a fascinating research topic for virologists around the world. As evidence of their ubiquity and ecological impact, mimiviruses have been found in multiple environmental samples. However, isolation of these viruses from environmental samples is inefficient, mainly due to methodological limitations and lack of information regarding the interactions between viruses and substrates. In this work, we demonstrate the long-lasting stability of mimivirus in environmental (freshwater and saline water) and hospital (ventilator plastic device tube) substrates, showing the detection of infectious particles after more than 9 months. In addition, an enrichment protocol was implemented that remarkably increased mimivirus detection from all tested substrates, including field tests. Moreover, biological, morphological and genetic tests revealed that the enrichment protocol maintained mimivirus particle integrity. In conclusion, our work demonstrated the stability of APMV in samples of environmental and health interest and proposed a reliable and easy protocol to improve giant virus isolation. The data presented here can guide future giant virus detection and isolation studies.

  9. Modeling the environmental stability of FeS2 nanorods, using lessons from biomineralization

    NASA Astrophysics Data System (ADS)

    Barnard, Amanda S; Russo, Salvy P

    2009-03-01

    Previous experimental studies have indicated that the controlled formation of anisotropic pyrite nanoparticles, such as nanorods or nanowires, is dependent on the right combination of solution chemistry and temperature. Similarly, the morphology of the individual nanocrystals during intracellular biomineralization of single nanocrystals has been attributed to the local environmental conditions, as well as the species of the micro-organism. Although there are obvious similarities, using the lessons from biomineralization to assist the laboratory synthesis of anisotropic pyrite nanostructures, and in the anticipation of environmental stability, requires a more detailed understanding of the role played by individual environmental parameters. In the present study we use a multi-scale thermodynamic model, combined with parameters obtained from first principles calculations, to investigate the formation and stability of pyrite nanorods as a function of temperature and chemical environment. The results of our systematic modeling of parameter space predict that the morphology of pyrite nanorods grown in the laboratory, or associated with biomineralization, is more likely to be a function of surface ligands and the biology of the organisms than a function of simpler environmental parameters such as temperature, pressure, concentration of sulfur and adsorption of water.

  10. Acanthamoeba polyphaga mimivirus Stability in Environmental and Clinical Substrates: Implications for Virus Detection and Isolation

    PubMed Central

    de Almeida, Gabriel M.; Campos, Rafael K.; Boratto, Paulo V. M.; Franco-Luiz, Ana P. M.; La Scola, Bernard; Ferreira, Paulo C. P.; Kroon, Erna G.; Abrahão, Jônatas S.

    2014-01-01

    Viruses are extremely diverse and abundant and are present in countless environments. Giant viruses of the Megavirales order have emerged as a fascinating research topic for virologists around the world. As evidence of their ubiquity and ecological impact, mimiviruses have been found in multiple environmental samples. However, isolation of these viruses from environmental samples is inefficient, mainly due to methodological limitations and lack of information regarding the interactions between viruses and substrates. In this work, we demonstrate the long-lasting stability of mimivirus in environmental (freshwater and saline water) and hospital (ventilator plastic device tube) substrates, showing the detection of infectious particles after more than 9 months. In addition, an enrichment protocol was implemented that remarkably increased mimivirus detection from all tested substrates, including field tests. Moreover, biological, morphological and genetic tests revealed that the enrichment protocol maintained mimivirus particle integrity. In conclusion, our work demonstrated the stability of APMV in samples of environmental and health interest and proposed a reliable and easy protocol to improve giant virus isolation. The data presented here can guide future giant virus detection and isolation studies. PMID:24498379

  11. Project Galaxy - Sustianable Resource Supply and Environmental Implications

    SciTech Connect

    Downing, Mark; Wimmer, Robert

    2012-03-01

    Understanding what it takes to move from a corn-based liquid fuels industry to one that is cellulosic-based requires a complex transition over time. This transition implies, among other things, a shift from annual cropping systems considered under United States Department of Agriculture (USDA) policy as commodity crops, to perennial lignocellulosic crops that are herbaceous and wood-based. Because of changes in land use as well as biomass and other crop supplies, land-based environmental amenities such as water quality, soil health and tilth, air quality, and animal and avian species populations and their diversity change also. Environmental effects are measured as magnitudes (how much they are impacted), and direction of the impact (either positive or negative). By developing a series of quantitative and qualitative metrics, the larger issue of defining relative sustainability may be addressed, and this can be done at a finer detail of regional (scale) and environmental amenity-specific impacts. Although much literature exists about research relevant to specific environmental variables, there is no published, documented, nor research literature on direct application of environmental over-compliance with regards a 'biorefinery.' Our three goals were to (1) understand and quantify bioenergy sustainability and some key environmental effects in a generic set of examples; (2) explain the effort and means to define and quantify specific qualitative environmental measures, and to determine a way to understand changes in these measures over time and what their implications might be; and (3) use these outcomes to evaluate potential sites in any geographic area. This would permit assessment of candidate locations, combined with an understanding of co-production of fuels, chemicals, and electric power, to interpret sustainability measures and the relationship between environmental sustainability and economic sustainability. The process of determining environmental

  12. Callous-unemotional behaviors in early childhood: Genetic and environmental contributions to stability and change.

    PubMed

    Flom, Megan; Saudino, Kimberly J

    2016-12-15

    Callous-unemotional (CU) behaviors demonstrate meaningful individual differences in early childhood, even in nonclinical samples with low mean levels of CU, but the factors underlying this variation have not been examined. This study investigated genetic and environmental contributions to individual differences and to sources of continuity and change in CU in toddler twins (145 monozygotic, 169 dizygotic) assessed at ages 2 and 3 years. CU, as assessed by the Child Behavior Checklist 1.5-5 (Achenbach & Rescorla, 2000), was moderately stable across age (r = .45, p < .0001). Longitudinal biometric analyses revealed genetic and nonshared environmental influences on CU at both ages, with no significant contribution from shared environmental factors. Stability from age 2 to 3 was due to genetic factors, whereas change was due to both genetic and nonshared environmental influences. This genetic and nonshared environmental change was substantial, suggesting malleability of CU in early childhood. Over 50% of the genetic influences and 100% of the nonshared environmental influences on CU at age 3 were independent of those that operated at age 2. Implications of novel sources of variance across age are discussed.

  13. Lessons Learned about Educator Training: A Synthesis of Grants Provided by Project Learning Tree, Project WET, and Project WILD under the Environmental Education and Training Partnership, 1995-2000.

    ERIC Educational Resources Information Center

    Heimlich, Joe E.

    This document reports on the training of partners for the Environmental Education and Training Partnership (EETAP). The three projects cited include Project Learning Tree (PLT), Project WILD, and Project WET. The main purpose of the training projects was to increase the number of individuals trained in environmental education programs. There are…

  14. Environmental permits and approvals plan for high-level waste interim storage, Project W-464

    SciTech Connect

    Deffenbaugh, M.L.

    1998-05-28

    This report discusses the Permitting Plan regarding NEPA, SEPA, RCRA, and other regulatory standards and alternatives, for planning the environmental permitting of the Canister Storage Building, Project W-464.

  15. EPA Awards $270K for Environmental and Health Projects in New England Communities

    EPA Pesticide Factsheets

    EPA has awarded 12 grants across New England under its 2016 Healthy Communities Grant Program, totaling approximately $270,566, to fund community projects addressing environmental and public health issues.

  16. 78 FR 43183 - Notice of Availability for Sharpe Permit Relinquishment Project Environmental Assessment Finding...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-07-19

    ... Availability (NOA) for Sharpe Permit Relinquishment Project Environmental Assessment (EA) Finding of No Significant Impact (FONSI). SUMMARY: On April 30, 2013, Defense Logistics Agency (DLA) published a NOA in...

  17. Environmental Assessment: Gulf Power Company Military Point Transmission Line Project

    DTIC Science & Technology

    2014-05-12

    Regulations for Implementing the Procedural Provisions of the National Environmental Policy Act (40 CFR Parts 1500-1508); Department of Defense...No significant issues were identified for any of these 23 statutes. PUBLIC NOTICE AND REVIEW PER AFI 32-7061 AND 32 CFR PART 989: The installation...CEQ) Regulations for Implementing the Procedural Provisions of the National Environmental Policy Act (NEPA) (40 CFR Parts 1500-1508). • Department of

  18. Environmental Assessment: Winnett School District Boiler Replacement Project

    SciTech Connect

    Not Available

    1994-07-01

    This environmental assessment analyzes the environmental impacts of replacing the Winnett School District complex`s existing oil-fired heating system with a new coal-fired heating system with funds provided from a grant under the Institutional Conservation Program. This Assessment has been prepared in accordance with the provisions of the National Environmental Policy Act (NEPA), the Council on Environmental Quality`s regulations; the Department`s Implementing Procedures and Guidelines Revocation; and the May 1993 ``Recommendations for the Preparation of Environmental Assessments and Environmental Impact Statements,`` by the Department`s Office of NEPA Oversight. Under the Institutional Conservation Programs, created by the National Energy Conservation Policy Act (PL 95--619), the Department is authorized to encourage energy conservation-by providing funding for up to 50 percent of the costs of installation of qualified energy conservation measures by entities such as schools, hospitals, and other buildings owned by local governments. This proposed action to fund partially the installation of a new coal-fired heating system for the Winnett School District is part of this energy conservation program.

  19. Environmental Assessment: Multiple Projects at Laughlin Air Force Base, Texas

    DTIC Science & Technology

    2006-05-17

    facilities totaling approximately 17,840 square feet. Each of the new facilities in the consolidated education complex would consist of a masonry building...addition to the primary maintenance facility, the Air Force would install two pre-cast concrete buildings, totaling 500 square feet, for the storage of...2,336 Building 255 Additional Demolition Projects dormitory 41,634 Building 256 Additional Demolition Projects dormitory 30,562 TOTAL 100,949

  20. Short Mountain Landfill Gas Recovery Project : Stage 1 Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration.

    1992-05-01

    The Bonneville Power Administration (BPA), a Federal power marketing agency, has statutory responsibilities to supply electrical power to its utility, industrial, and other customers in the Pacific Northwest. BPA`s latest load/resource balance forecast, projects the capability of existing resources to satisfy projected Federal system loads. The forecast indicates a potential resource deficit. The underlying need for action is to satisfy BPA customers` demand for electrical power.

  1. 41 CFR 102-80.75 - Who assesses environmental issues in Federal construction and lease construction projects?

    Code of Federal Regulations, 2010 CFR

    2010-07-01

    ... environmental issues in Federal construction and lease construction projects? 102-80.75 Section 102-80.75 Public... Management Assessment of Environmental Issues § 102-80.75 Who assesses environmental issues in Federal construction and lease construction projects? Federal agencies must assess required environmental...

  2. Environmental Assessment and Finding of No Significant Impact: Kalina Geothermal Demonstration Project Steamboat Springs, Nevada

    SciTech Connect

    N /A

    1999-02-22

    The Department of Energy (DOE) has prepared an Environmental Assessment (EA) to provide the DOE and other public agency decision makers with the environmental documentation required to take informed discretionary action on the proposed Kalina Geothermal Demonstration project. The EA assesses the potential environmental impacts and cumulative impacts, possible ways to minimize effects associated with partial funding of the proposed project, and discusses alternatives to DOE actions. The DOE will use this EA as a basis for their decision to provide financial assistance to Exergy, Inc. (Exergy), the project applicant. Based on the analysis in the EA, DOE has determined that the proposed action is not a major Federal action significantly affecting the quality of the human or physical environment, within the meaning of the National Environmental Policy Act (NEPA) of 1969. Therefore, the preparation of an environmental impact statement is not required and DOE is issuing this Finding of No Significant Impact (FONSI).

  3. Newberry Geothermal Pilot Project : Final Environmental Impact Statement.

    SciTech Connect

    US Forest Service; US Bureau of Land Management; US Bonneville Power Administration

    1994-09-01

    BPA has decided to acquire 20 average megawatts (aMW) of electrical power from a privately-owned geothermal power plant on the west flank of Newberry Volcano in Deschutes County, Oregon. The Newberry Project will generate 30 aMW and will be developed, owned, and operated by CE Newberry, Inc. of Portland, Oregon. In addition, BPA has decided to grant billing credits to EWEB for 10 aMW of electrical power and to provide wheeling services to EWEB for the transmission of this power to their system. BPA expects the Newberry Project to be in commercial operation by November 1997. BPA has statutory responsibilities to supply electrical power to its utility industrial and other customers in the Pacific Northwest. The Newberry Project will be used to meet the electrical power supply obligations of these customers. The Newberry Project will also demonstrate the availability of geothermal power to meet power supply needs in the Pacific Northwest and is expected to be the first commercial geothermal plant in the region. The Newberry Project was selected under the BPA Geothermal Pilot Project Program. The goal of the Program is to initiate development of the Pacific Northwest`s large, but essentially untapped, geothermal resources, and to confirm the availability of this resource to meet the energy needs of the region. The primary underlying objective of this Program is to assure the supply of alternative sources of electrical power to help meet growing regional power demands and needs.

  4. Lower Yakima Valley Wetlands and Riparian Restoration Project. Final Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration

    1994-10-01

    Bonneville Power Administration (BPA) proposes to fund that portion of the Washington Wildlife Mitigation Agreement pertaining to the Lower Yakima Valley Wetlands and Riparian Restoration Project (Project) in a cooperative effort with the Yakama Indian Nation and the Bureau of Indian Affairs (BIA). The proposed action would allow the sponsors to secure property and conduct wildlife management activities for the Project within the boundaries of the Yakama Indian Reservation. This Environmental Assessment examines the potential environmental effects of acquiring and managing property for wildlife and wildlife habitat within a large 20, 340 hectare (50, 308 acre) project area. As individual properties are secured for the Project, three site-specific activities (habitat enhancement, operation and maintenance, and monitoring and evaluation) may be subject to further site-specific environmental review. All required Federal/Tribal coordination, permits and/or approvals would be obtained prior to ground disturbing activities.

  5. The Contribution of Project Environmental Assessment to Assessing and Managing Cumulative Effects: Individually and Collectively Insignificant?

    NASA Astrophysics Data System (ADS)

    Noble, Bram; Liu, Jialang; Hackett, Paul

    2017-04-01

    This paper explores the opportunities and constraints to project-based environmental assessment as a means to support the assessment and management of cumulative environmental effects. A case study of the hydroelectric sector is used to determine whether sufficient information is available over time through project-by-project assessments to support an adequate understanding of cumulative change. Results show inconsistency from one project to the next in terms of the components and indicators assessed, limited transfer of baseline information between project assessments over time, and the same issues and concerns being raised by review panels-even though the projects reviewed are operating in the same watershed and operated by the same proponent. Project environmental assessments must be managed, and coordinated, as part of a larger system of impact assessment, if project-by-project assessments are to provide a meaningful forum for learning and understanding cumulative change. The paper concludes with recommendations for improved project-based assessment practice in support of cumulative effects assessment and management.

  6. Richland Environmental Restoration Project management action process document

    SciTech Connect

    1996-04-01

    A critical mission of the U.S. Department of Energy (DOE) is the planning, implementation, and completion of environmental restoration programs at DOE facilities. An integral part of this mission involves the safe and cost-effective environmental restoration of the Hanford Site. For over 40 years the Hanford Site supported United States national defense programs, largely through the production of nuclear materials. One legacy of historical Hanford Site operations is a significant waste inventory of radioactive and/or regulated chemical materials. Releases of these materials have, in some cases, contaminated the Hanford Site environment. The DOE Richland Operations Office (RL) is responsible for protecting human health and the environment from potential Hanford Site environmental hazards by identifying, assessing, and mitigating risks posed by contaminated sites.

  7. Effects of diverse environmental conditions on {phi}LC3 prophage stability in Lactococcus lactis.

    PubMed

    Lunde, Merete; Aastveit, Are Halvor; Blatny, Janet Martha; Nes, Ingolf F

    2005-02-01

    The effects of various growth conditions on spontaneous phiLC3 prophage induction in Lactococcus lactis subsp. cremoris IMN-C1814 was analyzed with a half fraction of a 4(4) factorial experimental design. The four factors included in the study were nutrient availability, acidity, osmolarity, and temperature, each applied at four levels. These environmental factors are related to the fermentation processes in the dairy industry, in which bacteriophage attacks on sensitive starter strains are a constant threat to successful fermentation processes. The frequency of spontaneous phiLC3 induction was determined by quantitative analyses of restored DNA attachment sites (attB) on the bacterial chromosomes in a population of lysogenic cells. Statistical analysis revealed that all four environmental factors tested affected phiLC3 prophage stability and that the environmental factors were involved in interactions (interactions exist when the effect of one factor depends on the level of another factor). The spontaneous phiLC3 induction frequency varied from 0.08 to 1.76%. In general, the induction frequency remained at the same rate or decreased when level 1 to 3 of the four environmental factors was applied. At level 4, which generally gave the least favorable growth conditions, the induction frequency was either unchanged, decreased, or increased, depending on the type of stress. It appeared that the spontaneous induction frequency was independent of the growth behavior of the host. It was the environmental growth conditions that were the decisive factor in induction frequency.

  8. Simple Assessment Techniques for Soil and Water. Environmental Factors in Small Scale Development Projects. Workshops.

    ERIC Educational Resources Information Center

    Coordination in Development, New York, NY.

    This booklet was produced in response to the growing need for reliable environmental assessment techniques that can be applied to small-scale development projects. The suggested techniques emphasize low-technology environmental analysis. Although these techniques may lack precision, they can be extremely valuable in helping to assure the success…

  9. 77 FR 23740 - Sears Point Wetland and Watershed Restoration Project, Sonoma County, CA; Final Environmental...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-04-20

    ... Fish and Wildlife Service Sears Point Wetland and Watershed Restoration Project, Sonoma County, CA; Final Environmental Impact Report and Environmental Impact Statement AGENCY: Fish and Wildlife Service, Interior. ACTION: Notice of availability. SUMMARY: We, the U.S. Fish and Wildlife Service (Service) and...

  10. The ILSI-HESI Project on Animal Alternative Needs in Environmental Risk Assessment

    EPA Science Inventory

    The ILSI Health and Environmental Sciences Institute (HESI) established a project in 2009 on Animal Alternatives in Environmental Risk Assessment (AA-ERA) following a successful two-year emerging issues assessment of the topic. The early stages of this work included the execution...

  11. Integrating Project-Based Service-Learning into an Advanced Environmental Chemistry Course

    ERIC Educational Resources Information Center

    Draper, Alison J.

    2004-01-01

    An active service-learning research work is conducted in the field of advanced environmental chemistry. Multiple projects are assigned to students, which promote individual learning skills, self-confidence as scientists, and a deep understanding of the environmental chemist's profession.

  12. West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2007

    SciTech Connect

    West Valley Environmental Services LLC and URS - Washington Division

    2008-12-17

    Annual Site Environmental Report for the West Valley Demonstration Project (WVDP) for Calendar Year 2007. The report summarizes the calendar year (CY) 2007 environmental protection program at the WVDP. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of public health and safety and the environment.

  13. Geography and Environmental Education: Meeting the Challenge through the Geography 16-19 Project.

    ERIC Educational Resources Information Center

    Naish, Michael

    1986-01-01

    Provides a brief history of the relationship between environmental education and geography. Describes the Geography 16-19 Project developed at the University of London Institute of Education, which stresses environmental issues and the quality of life instead of the kind of "academic" geography typically covered in courses at this level.…

  14. Searching for the Seventies: Photographs from the Environmental Protection Agency's DOCUMERICA Project

    ERIC Educational Resources Information Center

    Bustard, Bruce; Potter, Lee Ann

    2013-01-01

    In 1971, the newly established Environmental Protection Agency (EPA) created DOCUMERICA, a federal government photography project born out of the nation's environmental crisis. The photographers hired by the EPA took thousands of photographs depicting pollution, waste, and blight, but they were given the freedom to capture the era's…

  15. 77 FR 62257 - Draft Environmental Impact Statement for the Herring River Restoration Project, Cape Cod National...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-10-12

    ...-0081-422] Draft Environmental Impact Statement for the Herring River Restoration Project, Cape Cod... Statement (DEIS) for the Herring River Restoration Project in Cape Cod National Seashore, Massachusetts. The... scheduled, the meeting date will be announced via the Cape Cod National Seashore Web site (...

  16. A New Project-Based Lab for Undergraduate Environmental and Analytical Chemistry

    ERIC Educational Resources Information Center

    Adami, Gianpiero

    2006-01-01

    A new project-based lab was developed for third year undergraduate chemistry students based on real world applications. The experience suggests that the total analytical procedure (TAP) project offers a stimulating alternative for delivering science skills and developing a greater interest for analytical chemistry and environmental sciences and…

  17. Taking Action: An Educator's Guide to Involving Students in Environmental Projects

    ERIC Educational Resources Information Center

    Council for Environmental Education, 2012

    2012-01-01

    Developed in cooperation with the World Wildlife Fund, "Taking Action" inspires ideas and provides models for conducting effective environmental projects--projects that dynamically engage students from start to finish. From adopting species to protecting habitats to saving energy and creating publications, this guide will help educators plan,…

  18. Collaborative Environmental Projects in a Multicultural Society: Working from within Separate or Mutual Landscapes?

    ERIC Educational Resources Information Center

    Tal, Tali; Alkaher, Iris

    2010-01-01

    A multicultural socio-environmental project that is framed in the ideas of education for sustainability brought together Jew and Arab students was investigated to identify the participants' views of the program's objectives and their accomplishments. We investigated the project's strengths and weaknesses according to the participants' views and…

  19. 76 FR 34969 - Extension of Scoping Period for the Northern Pass Transmission Line Project Environmental Impact...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-06-15

    ... Extension of Scoping Period for the Northern Pass Transmission Line Project Environmental Impact Statement... (DOE) is reopening the public scoping period for the Northern Pass Transmission Line Project... being provided by Northern Pass, DOE is reopening the scoping period. DOE will determine the close...

  20. 78 FR 57372 - Northern Pass Transmission Line Project Environmental Impact Statement: Announcement of Change in...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-09-18

    ... Northern Pass Transmission Line Project Environmental Impact Statement: Announcement of Change in Public... amended Notice of Intent (NOI) to modify the scope of the Northern Pass Transmission Line Project... previously announced this change in public meeting location on both the Northern Pass EIS Web site at...

  1. Integrating Project-Based Service-Learning into an Advanced Environmental Chemistry Course

    NASA Astrophysics Data System (ADS)

    Draper, Alison J.

    2004-02-01

    In an advanced environmental chemistry course, the inclusion of semester-long scientific service projects successfully integrated the research process with course content. Each project involved a unique community-based environmental analysis in which students assessed an aspect of environmental health. The projects were due in small pieces at even intervals, and students worked independently or in pairs. Initially, students wrote a project proposal in which they chose and justified a project. Following a literature review of their topic, they drafted sampling and analysis plans using methods in the literature. Samples were collected and analyzed, and all students assembled scientific posters describing the results of their study. In the last week of the semester, the class traveled to a regional professional meeting to present the posters. In all, students found the experience valuable. They learned to be professional environmental chemists and learned the value of the discipline to community health. Students not only learned about their own project in depth, but they were inspired to learn textbook material, not for an exam, but because it helped them understand their own project. Finally, having a community to answer to at the end of the project motivated students to do careful work.

  2. Environmentally Sound Small-Scale Livestock Projects. Guidelines for Planning Series Number 5.

    ERIC Educational Resources Information Center

    Jacobs, Linda

    This document was developed in response to the need for simplified technical information for planning environmentally sound small-scale projects in third world countries. It is aimed specifically at those who are planning or managing small-scale livestock projects in less-developed areas of the tropics and sub-tropics. The guidelines included in…

  3. Environmental projects. Volume 1: Polychlorinated biphenyl (PCB) abatement program

    NASA Technical Reports Server (NTRS)

    Kushner, L.

    1987-01-01

    Six large parabolic dish antennas are located at the Goldstone Deep Space Communications Complex north of Barstow, California. Some of the ancillary electrical equipment of thes Deep Space Stations, particularly transformers and power capicitors, were filled with stable, fire-retardant, dielectric fluids containing substances called polychlorobiphenyls (PCBs). Because the Environmental Protection Agency has determined that PCBs are environmental pollutants toxic to humans, all NASA centers have been asked to participate in a PCB-abatement program. Under the supervision of JPL's Office of Telecommunications and Data Acquisition, a two-year long PCB-abatement program has eliminated PCBs from the Goldstone Complex.

  4. South Carolina: Charleston County Area Project Impact Environmental Education Program (A Former EPA CARE Project)

    EPA Pesticide Factsheets

    The Charleston County Area Project Impact is the recipient of a Level II CARE cooperative agreement. The project is under the direction of the Charleston County Building Services Department, in Charleston, S.C.

  5. Final Environmental Assessment for the Boles Wells Field Perimeter Security Improvement Project Otero County, New Mexico

    DTIC Science & Technology

    2005-10-03

    findings of the Final Environmental Assessment of the Boles Wells Field Security Improvement Project, dated 3 Oct 05, no significant impact on human health ...Other resource impacts identified in the EA were considered to determine the potential for high and adverse health and environmental impacts to human ...as necessary, to protect human health and the environment. - Noted. To be accomplished asnecesary. Final Environmental Assessment - Boles Wells

  6. Oak Ridge National Laboratory Gunite and Associated Tanks Stabilization Project-Low-Tech Approach with High-Tech Results

    SciTech Connect

    Brill, A.; Alsup, T.; Bolling, D.

    2002-02-26

    Environmental restoration of the Gunite and Associated Tanks (GAAT) at the Oak Ridge National Laboratory (ORNL) was a priority to the U. S. Department of Energy (DOE) because of their age and deteriorating structure. These eight tanks ranging up to 170,000 gallons in capacity were constructed in 1943 of a Gunite or ''sprayed concrete material'' as part of the Manhattan Project. The tanks initially received highly radioactive waste from the Graphite Reactor and associated chemical processing facilities. The waste was temporarily stored in these tanks to allow for radioactive decay prior to dilution and release into surface waters. Over time, additional wastes from ongoing ORNL operations (e.g., isotope separation and materials research) were discharged to the tanks for storage and treatment. These tanks were taken out of service in the 1970s. Based on the structure integrity of GAAT evaluated in 1995, the worst-case scenario for the tanks, even assuming they are in good condition, is to remain empty. A recently completed interim action conducted from April 1997 through September 2000 removed the tank liquids and residual solids to the extent practical. Interior video surveys of the tanks indicated signs of degradation of the Gunite material. The tanks continued to receive inleakage, which generated a relatively high volume waste stream that required periodic removal, treatment, and disposal. For these reasons, DOE chose in-place stabilization of Tanks W-3 through W-10 as a non-timecritical removal action under Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA). Tank stabilization activities involved removal of liquid from inleakage and placement of a grout mixture or ''flowable fill'' into the tanks to within 3-ft of the ground surface. Bechtel Jacobs Company, LLC (BJC) awarded Safety and Ecology Corporation (SEC) a subcontract in March 2001 to complete the documentation and fieldwork necessary to achieve tank stabilization in

  7. Reconstruction of Plasma Equilibria and Projected Stabilization of Global MHD Modes in KSTAR

    NASA Astrophysics Data System (ADS)

    Park, Y. S.; Sabbagh, S. A.; Bialek, J. M.; Berkery, J. W.; Jeon, Y. M.; Hahn, S. H.; Lee, S. G.; You, K.-. I.; Park, H. K.; Evans, T. E.; Eidietis, N.; Walker, M.; Leuer, J.

    2010-11-01

    Experimental equilibria of the KSTAR tokamak with plasma current up to 0.34 MA were reconstructed using EFIT. Vessel currents were included by fitting estimated values based on loop voltage measurements and effective resistances from 2 and 3-D vacuum model calculations including a double-walled vessel with large port penetrations and passive stabilizers. Active and passive stabilization of global MHD instabilities for operation above the no-wall beta limit is also projected. The stabilization is applied using a set of segmented internal coils called in-vessel control coils (IVCCs). Passive stability of the resistive wall mode and power requirement for its active stabilization are investigated including conductive casing structures covering the IVCC, and noise effects. The potential for ELM mitigation by resonant magnetic perturbations is also examined by using the TRIP3D code. Favorable configurations of the IVCC based on the Chirikov parameter are determined using a combination of all IVCCs (midplane and off-midplane coils) with a dominant n = 2 field configuration.

  8. Improvement in the control aspect of laser frequency stabilization for SUNLITE project

    NASA Technical Reports Server (NTRS)

    Zia, Omar

    1992-01-01

    Flight Electronics Division of Langley Research Center is developing a spaceflight experiment called the Stanford University and NASA Laser In-Space Technology (SUNLITE). The objective of the project is to explore the fundamental limits on frequency stability using an FM laser locking technique on a Nd:YAG non-planar ring (free-running linewidth of 5 KHz) oscillator in the vibration free, microgravity environment of space. Compact and automated actively stabilized terahertz laser oscillators will operate in space with an expected linewidth of less than 3 Hz. To implement and verify this experiment, NASA engineers have designed and built a state of the art, space qualified high speed data acquisition system for measuring the linewidth and stability limits of a laser oscillator. In order to achieve greater stability and better performance, an active frequency control scheme requiring the use of a feedback control loop has been applied. In the summer of 1991, the application of control theory in active frequency control as a frequency stabilization technique was investigated. The results and findings were presented in 1992 at the American Control Conference in Chicago, and have been published in Conference Proceedings. The main focus was to seek further improvement in the overall performance of the system by replacing the analogue controller by a digital algorithm.

  9. Environmental Project Provides Work Experience for Rural Youth

    ERIC Educational Resources Information Center

    Meier, Amy L.; Smith, Marilyn; Usinger, Janet

    2010-01-01

    Bootstraps is a 12-week program designed for rural youth, ages 18-21, who are not working and not in school. The program goal is for participants to develop skills and motivation to find meaningful work, which is accomplished through a combination of classroom learning and practical fieldwork. The environmental fieldwork on public lands, funded by…

  10. The Social Justice, Peace, and Environmental Education Standards Project

    ERIC Educational Resources Information Center

    Andrzejewski, Julie

    2005-01-01

    Inspired by the Alaska Native Knowledge Network's "Standards for Culturally Responsive Schools," members of fourteen social justice, peace, and environmental education (SJPEE) special interest groups (SIGs) from the American Educational Research Association (AERA) and several other prominent organizations have been involved in drafting SJPEE…

  11. Environmental Assessment and (FONSI) Winnett School District Boiler Replacement Project.

    ERIC Educational Resources Information Center

    Department of Energy, Washington, DC.

    An analysis is presented of the environmental impacts of replacing the Winnett School District's existing oil-fired heating system with a new coal-fired heating system with funds provided from a grant under the Institutional Conservation Program. The report first covers the background and need for action, along with the alternative actions…

  12. Environmental Audit, Rifle, Gunnison and Grand Junction UMTRA Project Sites

    SciTech Connect

    1991-08-01

    This report documents the results of the comprehensive baseline Environmental Audit completed for the Uranium Mill Tailings Remedial Action (UMTRA) sites at Grand Junction, Rifle, and Gunnison, Colorado. Included in the Audit were the actual abandoned mill sites, associated transportation and disposal cell facilities, and representative examples of the more than 4,000 known vicinity properties. Sites investigated include: Climax Mill Site, Truck/Train Haul Route, Cotter Transfer Station, Cheney Disposal Cell, Rifle Mill Sites (Old and New Rifle), Gunnison Mill Site, Vicinity Properties, and Estes Gulch and Proposed Landfill Site No. 1 Disposal Cells. The UMTRA Audit was a comprehensive baseline audit which considered all environmental programs and the activities associated with ongoing and planned remediation at the UMTRA sites listed above. Compliance with the National Environmental Policy Act (NEPA) was not considered during this investigation. The Audit Team looked at the following technical disciplines: air, surface water/drinking water, groundwater, soil/sediment/biota, waste management, toxic and chemical materials, quality assurance, radiation, inactive waste sites, and environmental management. 6 figs., 12 tabs.

  13. 15 CFR 291.3 - Environmental tools and techniques projects.

    Code of Federal Regulations, 2010 CFR

    2010-01-01

    ... descending order of importance: (1) Demonstrated understanding of the environmentally-related technical... resource will be integrated into and will be of service to the NIST Manufacturing Extension Centers... the MEP system; and demonstrated interest in using the tool or technique especially by MEP...

  14. Buffalo Flat Service 115-KV Transmission Project : Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration.

    1987-07-01

    The US Air Force has sited a radar transmitter at Buffalo Flat, near Christmas Valley, Oregon. This report discusses the environmental impacts of providing the electrical service for the installation. A 115 kV power transmission line will be built between LaPine and Buffalo Flat. Route alternatives as well as design alternatives are discussed. (ACR)

  15. Characterization of Environmental Stability of Pulsed Laser Deposited Oxide Ceramic Coatings

    SciTech Connect

    ADAMS, THADM

    2004-03-02

    A systematic investigation of candidate hydrogen permeation materials applied to a substrate using Pulsed Laser Deposition has been performed. The investigation focused on application of leading permeation-resistant materials types (oxide, carbides, and metals) on a stainless steel substrate. and evaluation of the stability of the applied coatings. Type 304L stainless steel substrates were coated with aluminum oxide, chromium oxide, and aluminum. Characterization of the coating-substrate system adhesion was performed using scratch adhesion testing and microindentation. Coating stability and environmental susceptibility were evaluated for two conditions-air at 350 degrees Celsius and Ar-H2 at 350 degrees Celsius for up to 100 hours. Results from this study have shown the pulsed laser deposition process to be an extremely versatile technology that is capable of producing a sound coating/substrate system for a wide variety of coating materials.

  16. Modulating conductivity, environmental stability of transparent conducting nanotube films on flexible substrates by interfacial engineering.

    PubMed

    Han, Joong Tark; Kim, Jun Suk; Jeong, Hae Deuk; Jeong, Hee Jin; Jeong, Seung Yol; Lee, Geon-Woong

    2010-08-24

    We have characterized the previously undescribed parameters for engineering the electrical properties of single-walled carbon nanotube (SWCNT) films for technological applications. First, the interfacial tension between bare SWCNT network films and a top coating passivation material was shown to dictate the variability of the films' sheet resistance (R(s)) after application of the top coating. Second, the electrical stability of the coated SWCNT films was affected by the mismatch between the CTE of the supporting substrate and the SWCNT network film. An upshift in the Raman G-band spectrum of SWCNTs on bare PET suggested that compressive strain was induced by the CTE mismatch after heating and cooling. These findings provide important guidelines for the choice of substrate and passivation coating materials that promote environmental stability in SWCNT-based transparent conductive films.

  17. The environmental control and life support system advanced automation project

    NASA Technical Reports Server (NTRS)

    Dewberry, Brandon S.

    1991-01-01

    The objective of the ECLSS Advanced Automation project includes reduction of the risk associated with the integration of new, beneficial software techniques. Demonstrations of this software to baseline engineering and test personnel will show the benefits of these techniques. The advanced software will be integrated into ground testing and ground support facilities, familiarizing its usage by key personnel.

  18. Environmentally Sound Small-Scale Forestry Projects. Guidelines for Planning.

    ERIC Educational Resources Information Center

    Ffolliott, Peter F.; Thames, John L.

    This manual, the third in a series of publications that address community development possibilities in developing nations, provides guidelines for small-scale forestry projects that are integrative and conservation-oriented. Chapters focus on: (1) users and uses (specifying targeted audience and general objectives); (2) planning process (including…

  19. Stormwater Pollution Prevention Plan (SWPPP) for Coal Storage Area Stabilization Project

    SciTech Connect

    Project and Design Engineering

    2011-03-01

    The scope of this project is to stabilize the abandoned coal storage area and redirect the storm water runoff from sanitary sewer system to the storm drain system. Currently, the existing storm water runoff is directed to a perimeter concrete drainage swale and collected in a containment basin. The collected water is then pumped to a treatment facility and after treatment, is discharged to the Y-12 sanitary sewer system. The existing drainage swale and collection basin along with silt fencing will be used during aggregate placement and grading to provide erosion and sediment control. Inlet protection will also be installed around existing structures during the storm water diversion construction. This project scope will include the installation of a non-woven geotextile fabric and compacted mineral aggregate base (paving optional) to stabilize the site. The geotextile specifications are provided on the vendor cut sheets in Appendix B. The installation of a storm water collection/retention area will also be installed on the southern side of the site in accordance with EPA Technical Guidance on Implementing the Stormwater Runoff Requirements for federal Projects under Section 438 of the Energy Independence and Security Act. The total area to be disturbed is approximately 2.5 acres. The order of activities for this Stormwater Pollution Prevention Plan (SWPPP) will be: (1) post notice of coverage (NOC) in a prominent display near entrance of the site; (2) install rain gauge on site or contact Y-12 Plant Shift Superintendent daily for Met tower rain gauge readings; (3) install stabilized construction exit on site; (4) install silt fencing along perimeter as indicated on the attached site plan; (5) regrade site; (6) install geotextile fabric and compacted mineral aggregate base; (7) install catch basin inlet protection where required; (8) excavate and lower existing catch basin tops, re-grade and asphalt to drain; and (9) when all disturbed areas are re-stabilized, remove

  20. Research on impact of the environmental factors on National Institute of Telecommunications time standards stability

    NASA Astrophysics Data System (ADS)

    Marszalec, M.; Lusawa, Marzenna

    2014-11-01

    National Institute of Telecommunications (NIT) has been operating time standards from over 15 years. They are part of worldwide and national time comparison system and are used in calculations of international and polish timescales, International Atomic Time Scale (TAI), Universal Time Coordinated (UTC), Polish Atomic Time Scale (TA(PL)) and Polish Official Time (UTC(PL)). This year the standards has been moved to new Time Standards Chamber which is precisely air conditioned and power secured. This article presents some interesting considerations on impact of the environmental factors on time standards stability.

  1. The Environmental and Molecular Sciences Laboratory project -- Continuous evolution in leadership

    SciTech Connect

    Knutson, D.E.; McClusky, J.K.

    1994-10-01

    The Environmental and Molecular Sciences Laboratory (EMSL) construction project at Pacific Northwest Laboratory (PNL) in Richland, Washington, is a $230M Major Systems Acquisition for the US Department of Energy (DOE). The completed laboratory will be a national user facility that provides unparalleled capabilities for scientists involved in environmental molecular science research. This project, approved for construction by the Secretary of Energy in October 1993, is underway. The United States is embarking on an environmental cleanup effort that dwarfs previous scientific enterprise. Using current best available technology, the projected costs of cleaning up the tens of thousands of toxic waste sites, including DOE sites, is estimated to exceed one trillion dollars. The present state of scientific knowledge regarding the effects of exogenous chemicals on human biology is very limited. Long term environmental research at the molecular level is needed to resolve the concerns, and form the building blocks for a structure of cost effective process improvement and regulatory reform.

  2. Coal to methanol feasiblity study: Beluga methanol project. Volume 4: Environmental

    NASA Astrophysics Data System (ADS)

    1981-09-01

    The major environmental issues relevant to development of a coal gasification and methanol fuels production facility and related coal mining activities and transportation systems in the west Cook Inlet area, Alaska were assessed. An extensive review into existing information on the Beluga region of west Cook Inlet was conducted and updated with the findings of land resource projects. Specific field activities then were initiated to expand the environmental data base in areas relevant to this project where there was a paucity of information. Based on these findings the project was reviewed in detail to identify significant environmental issues and to outline the state and federal permit requirements to ensure that these element are an integral component of all subsequent project planning and management decisions.

  3. Project Orion, Environmental Control and Life Support System Integrated Studies

    NASA Technical Reports Server (NTRS)

    Russell, James F.; Lewis, John F.

    2008-01-01

    Orion is the next vehicle for human space travel. Humans will be sustained in space by the Orion subystem, environmental control and life support (ECLS). The ECLS concept at the subsystem level is outlined by function and technology. In the past two years, the interface definition with other subsystems has increased through different integrated studies. The paper presents the key requirements and discusses three recent studies (e.g., unpressurized cargo) along with the respective impacts on the ECLS design moving forward.

  4. Shaw Air Force Base Infrastructure Project Environmental Assessment

    DTIC Science & Technology

    2008-09-01

    environmental impact statement (E ) is n warranted. DATE This page is intentionally blank. Final Shaw Air Force Base Infrastructure...AFB viii This page is intentionally blank. Purpose and Need EA for Infrastructure at Shaw AFB 1-1 Shaw AFB Infrastructure EA Chapter 1.0... intentionally blank. Description of the Proposed Action and Alternatives EA for Infrastructure at Shaw AFB 2-1 2.0 DESCRIPTION OF THE PROPOSED

  5. Episodes of environmental stability versus instability in Late Cenozoic lake records of Eastern Africa.

    PubMed

    Trauth, Martin H; Bergner, Andreas G N; Foerster, Verena; Junginger, Annett; Maslin, Mark A; Schaebitz, Frank

    2015-10-01

    Episodes of environmental stability and instability may be equally important for African hominin speciation, dispersal, and cultural innovation. Three examples of a change from stable to unstable environmental conditions are presented on three different time scales: (1) the Mid Holocene (MH) wet-dry transition in the Chew Bahir basin (Southern Ethiopian Rift; between 11 ka and 4 ka), (2) the MIS 5-4 transition in the Naivasha basin (Central Kenya Rift; between 160 ka and 50 ka), and (3) the Early Mid Pleistocene Transition (EMPT) in the Olorgesailie basin (Southern Kenya Rift; between 1.25 Ma and 0.4 Ma). A probabilistic age modeling technique is used to determine the timing of these transitions, taking into account possible abrupt changes in the sedimentation rate including episodes of no deposition (hiatuses). Interestingly, the stable-unstable conditions identified in the three records are always associated with an orbitally-induced decrease of insolation: the descending portion of the 800 kyr cycle during the EMPT, declining eccentricity after the 115 ka maximum at the MIS 5-4 transition, and after ∼ 10 ka. This observation contributes to an evidence-based discussion of the possible mechanisms causing the switching between environmental stability and instability in Eastern Africa at three different orbital time scales (10,000 to 1,000,000 years) during the Cenozoic. This in turn may lead to great insights into the environmental changes occurring at the same time as hominin speciation, brain expansion, dispersal out of Africa, and cultural innovations and may provide key evidence to build new hypotheses regarding the causes of early human evolution.

  6. The Radon Project: A Study in Environmental Hazard Education.

    ERIC Educational Resources Information Center

    Himes, Lori; And Others

    1996-01-01

    An extension project sold 4,000 radon kits; 46% were returned for testing and 23% of homes were at risk. Interviews with 100 of those at risk found that only 41% believed they had a problem; women and college graduates were more likely than men and high school graduates to believe it. Of those who believed they had a problem, only 63% took any…

  7. Yakima Fisheries Project : Revised Draft Environmental Impact Statement, Summary.

    SciTech Connect

    Confederated Tribes and Bands of the Yakama Nation, Washington; Washington . Dept. of Fish and Wildlife.

    1995-05-01

    The Bonneville Power Administration (BPA) proposes to fund the Yakima Fisheries Project (YFP) to undertake fishery research and enhancement activities in the Yakima River Basin. The State of Washington and the Yakima Indian Nation would jointly direct the project. The Yakima River system is a promising location for mitigation and enhancement to compensate for stock losses from development and operation of hydroelectric projects elsewhere in the Columbia Basin. The YFP would help determine the role that supplementation might play in increasing natural production of anadromous salmonids throughout the Columbia Basin. In cooperation with BPA, the project managers propose to construct, operate and maintain anadromous (e.g. salmon) fish production facilities. The goal is to conduct research activities designed to increase knowledge of supplementation techniques. These techniques would be applied to rebuild naturally spawning anadromous fish stocks historically present in the Yakima River Basin and, ultimately, those throughout the Columbia River Basin. Eventually, the YFP might involve the supplementation of all stocks of anadromous fish known to have occurred in the Yakima Basin. However, at this time only two alternatives have been proposed: Alternative 1 would supplement depressed naturally spawning populations of upper Yakima spring chinook salmon; Alternative 2 (preferred) would include all actions under Alternative 1; it would also add a study to determine the feasibility of re-establishing a naturally spawning population and a significant fall fishery for coho salmon in the Yakima Basin. (Coho smolts are currently being imported from another basin under the Columbia River Basin Fish Management Plan; the stock is now virtually eliminated from the Basin.)

  8. Improving Environmental Literacy through GO3 Citizen Science Project

    NASA Astrophysics Data System (ADS)

    Wilkening, B.

    2011-12-01

    In the Global Ozone (GO3) Project students measure ground-level ozone on a continuous basis and upload their results to a global network used by atmospheric scientists and schools. Students learn important concepts such as chemical measurement methods; instrumentation; calibration; data acquisition using computers; data quality; statistics; data analysis and graphing; posting of data to the web; the chemistry of air pollution; stratospheric ozone depletion and global climate change. Students collaborate with researchers and other students globally in the GO3 network. Wilson K-8 School is located in a suburban area in Pima County, Arizona. Throughout the year we receive high ozone alert days. Prior to joining the GO3 project, my students were unaware of air pollution alerts, risks and causes. In the past when Pima County issued alerts to the school, they were posted on signs around the school. No explanation was provided to the students and the signs were often left up for days. This discounted the potential health effects of the situation, resulting in the alerts effectively being ignored. The GO3 project is transforming both my students and our school community. Now my students are:

    • Performing science research
    • Utilizing technology and increasing their skills
    • Collaborating in a responsible manner on the global GO3 social network
    • Communicating their work to the community
    • Issuing their own ozone alerts to their school
    • Advocating for actions that will improve air quality
    My students participation in this citizen science project is creating a more cognizant and active community in regards to air pollution.

  9. Yakima Fisheries Project : Final Environmental Impact Statement : Summary.

    SciTech Connect

    United States. Bonneville Power Administration; Washington . Dept. of Fish and Wildlife; Confederated Tribes and Bands of the Yakama Nation, Washington.

    1996-01-01

    The Bonneville Power Administration (BPA) proposes to fund the Yakima Fisheries Project (YFP) to undertake fishery research and mitigation activities in the Yakima River Basin. The State of Washington and the Yakama Indian Nation (YIN) would jointly direct the project. In cooperation with BPA, the project managers propose to construct, operate and maintain anadromous (e.g. salmon) fish production facilities The goal is to conduct research activities designed to increase knowledge of supplementation techniques. These techniques would be applied to rebuild naturally spawning anadromous fish stocks historically present in the Yakima River Basin and, ultimately, those throughout the Columbia River Basin. Eventually, the YFP might involve the supplementation of all stocks of anadromous fish known to have occurred in the Yakima Basin. However, at this time only two action alternatives have been proposed, in addition to the No Action alternative: Alternative (1) would supplement depressed naturally spawning populations of upper Yakima spring chinook salmon; Alternative (2) (preferred) would include all actions under Alternative 1; it would also add a study to determine the feasibility of re-establishing a naturally spawning population and a significant fall fishery for coho salmon in the Yakima Basin (Coho smolts are currently being imported from another basin under the Columbia River Basin Fish Management Plan; the stock is now virtually eliminated from the Basin.)

  10. U.S. Department of Energy Grand Junction Projects Office site environmental report for calendar year 1995

    SciTech Connect

    1996-05-01

    This report presents information pertaining to environmental activities conducted during calendar year 1995 at the US Department of Energy (DOE) Grand Junction Projects Office (GJPO) facility in Grand Junction, Colorado. Environmental activities conducted at the GJPO facility during 1995 were associated with mixed-waste treatment, site remediation, off-site dose modeling, and radiological and nonradiological monitoring. As part of the GJPO Mixed-Waste Treatment Program, on-site treatability studies were conducted in 1995 that made use of pilot-scale evaporative-oxidation and thermal-desorption units and bench-scale stabilization. DOE-GJPO used some of its own mixed-waste as well as samples received from other DOE sites for these treatability studies. These studies are expected to conclude in 1996. Removal of radiologically contaminated materials from GJPO facility buildings was conducted under the provisions of the Grand Junction Projects Office Remedial Action Project. Remediation activities included the removal of 394 metric tons of contaminated material from Buildings 18 and 28 and revegetation activities on the GJPO site; remediation was conducted in compliance with applicable permits.

  11. In-situ stabilization of TRU/mixed waste project at the INEEL

    SciTech Connect

    Milian, L.W.; Heiser, J.H.; Adams, J.W.; Rutenkroeger, S.P.

    1997-08-01

    Throughout the DOE complex, buried waste poses a threat to the environment by means of contaminant transport. Many of the sites contain buried waste that is untreated, prior to disposal, or insufficiently treated, by today`s standards. One option to remedy these disposal problems is to stabilize the waste in situ. This project was in support of the Transuranic/Mixed Buried Waste - Arid Soils product line of the Landfill Focus Area, which is managed currently by the Idaho National Engineering Laboratory (BNL) provided the analytical laboratory and technical support for the various stabilization activities that will be performed as part of the In Situ Stabilization of TRU/Mixed Waste project at the INEL. More specifically, BNL was involved in laboratory testing that included the evaluation of several grouting materials and their compatibility, interaction, and long-term durability/performance, following the encapsulation of various waste materials. The four grouting materials chosen by INEL were: TECT 1, a two component, high density cementious grout, WAXFIX, a two component, molten wax product, Carbray 100, a two component elastomeric epoxy, and phosphate cement, a two component ceramic. A simulated waste stream comprised of sodium nitrate, Canola oil, and INEL soil was used in this study. Seven performance and durability tests were conducted on grout/waste specimens: compressive strength, wet-dry cycling, thermal analysis, base immersion, solvent immersion, hydraulic conductivity, and accelerated leach testing.

  12. West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2009

    SciTech Connect

    West Valley Environmental Services LLC and URS Corporation

    2010-09-17

    The West Valley Demonstration Project (WVDP) Annual Site Environmental Report (ASER) for Calendar Year 2009. The report, prepared by the U.S. Department of Energy West Valley Demonstration Project office (DOE-WVDP), summarizes the environmental protection program at the WVDP for calendar year (CY) 2009. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of public health and safety and the environment. The report is a key component of DOE’s effort to keep the public informed of environmental conditions at the WVDP. The quality assurance protocols applied to the environmental monitoring program by the DOE ensure the validity and accuracy of the monitoring data. In addition to demonstrating compliance with environmental regulations and directives, evaluation of data collected in 2009 continued to indicate that WVDP activities pose no threat to public health or safety, or to the environment.

  13. West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2010

    SciTech Connect

    None, None

    2011-09-28

    The West Valley Demonstration Project (WVDP) Annual Site Environmental Report (ASER) for Calendar Year 2010. The report, prepared for the U.S. Department of Energy West Valley Demonstration Project office (DOE-WVDP), summarizes the environmental protection program at the WVDP for calendar year (CY) 2010. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of public health and safety and the environment. The report is a key component of DOE's effort to keep the public informed of environmental conditions at the WVDP. The quality assurance protocols applied to the environmental monitoring program ensure the validity and accuracy of the monitoring data. In addition to demonstrating compliance with environmental laws, regulations and directives, evaluation of data collected in 2010 continued to indicate that WVDP activities pose no threat to public health or safety, or to the environment.

  14. West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2012

    SciTech Connect

    Rendall, John D.; Steiner, Alison F.; Klenk, David P.

    2013-09-19

    The West Valley Demonstration Project (WVDP) Annual Site Environmental Report (ASER) for Calendar Year 2012. The report, prepared for the U.S. Department of Energy West Valley Demonstration Project office (DOE-WVDP), summarizes the environmental protection program at the WVDP for calendar year (CY) 2012. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of public health and safety and the environment. The report is a key component of DOE’s effort to keep the public informed of environmental conditions at the WVDP. The quality assurance protocols applied to the environmental monitoring program ensure the validity and accuracy of the monitoring data. In addition to demonstrating compliance with environmental laws, regulations, and directives, evaluation of data collected in 2012 continued to indicate that WVDP activities pose no threat to public health or safety, or to the environment.

  15. West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2011

    SciTech Connect

    none,

    2012-09-27

    The West Valley Demonstration Project (WVDP) Annual Site Environmental Report (ASER) for Calendar Year 2011. The report, prepared for the U.S. Department of Energy West Valley Demonstration Project office (DOE-WVDP), summarizes the environmental protection program at the WVDP for calendar year (CY) 2011. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of public health and safety and the environment. The report is a key component of DOE’s effort to keep the public informed of environmental conditions at the WVDP. The quality assurance protocols applied to the environmental monitoring program ensure the validity and accuracy of the monitoring data. In addition to demonstrating compliance with environmental laws, regulations, and directives, evaluation of data collected in 2011 continued to indicate that WVDP activities pose no threat to public health or safety, or to the environment.

  16. West Valley Demonstration Project Annual Site Environmental Report (ASER) for Calendar Year 2015

    SciTech Connect

    Rendall, John D.; Steiner, Alison F.; Pendl, Michael P.; Biedermann, Charles A.; Steiner, II, Robert E.; Fox, James R.; Hoch, Jerald J.; Wrotniak, Chester M.; Werchowski, Rebecca L.

    2016-09-15

    West Valley Demonstration Project (WVDP) Annual Site Environmental Report (ASER) for Calendar Year 2015. The report, prepared for the U.S. Department of Energy West Valley Demonstration Project office (DOE-WVDP), summarizes the environmental protection program at the WVDP for calendar year (CY) 2015. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of public health and safety and the environment. The report is a key component of DOE’s effort to keep the public informed of environmental conditions at the WVDP. The quality assurance protocols applied to the environmental monitoring program ensure the validity and accuracy of the monitoring data. In addition to demonstrating compliance with environmental laws, regulations, and directives, evaluation of data collected in 2015 continued to indicate that WVDP activities pose no threat to public health or safety, or to the environment.

  17. West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2013

    SciTech Connect

    Rendall, John D.; Steiner, Alison F.; Pendl, Michael P.

    2014-09-16

    West Valley Demonstration Project (WVDP) Annual Site Environmental Report (ASER) for Calendar Year 2013. The report, prepared for the U.S. Department of Energy West Valley Demonstration Project office (DOE-WVDP), summarizes the environmental protection program at the WVDP for calendar year (CY) 2013. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of public health and safety and the environment. The report is a key component of DOE’s effort to keep the public informed of environmental conditions at the WVDP. The quality assurance protocols applied to the environmental monitoring program ensure the validity and accuracy of the monitoring data. In addition to demonstrating compliance with environmental laws, regulations, and directives, evaluation of data collected in 2013 continued to indicate that WVDP activities pose no threat to public health or safety, or to the environment.

  18. West Valley Demonstration Project Annual Site Environmental Report (ASER) for Calendar Year 2014

    SciTech Connect

    Rendall, John D.; Steiner, Alison F.; Pendl, Michael P.; Biedermann, Charles A.; Steiner, II, Robert E.; Fox, James R.; Hoch, Jerald J.; Werchowski, Rebecca L.

    2015-09-15

    West Valley Demonstration Project (WVDP) Annual Site Environmental Report (ASER) for Calendar Year 2014. The report, prepared for the U.S. Department of Energy West Valley Demonstration Project office (DOE-WVDP), summarizes the environmental protection program at the WVDP for calendar year (CY) 2014. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of public health and safety and the environment. The report is a key component of DOE’s effort to keep the public informed of environmental conditions at the WVDP. The quality assurance protocols applied to the environmental monitoring program ensure the validity and accuracy of the monitoring data. In addition to demonstrating compliance with environmental laws, regulations, and directives, evaluation of data collected in 2014 continued to indicate that WVDP activities pose no threat to public health or safety, or to the environment.

  19. Environmental projects, volume 11. Environmental assessment: Addition to operations building, Mars site

    NASA Technical Reports Server (NTRS)

    1990-01-01

    An Environmental Assessment was performed of the proposed addition to building G-86 at the Mars Site, which will provide space for new electronic equipment to consolidate the Deep Space Network (DSN) support facilities from other Goldstone Deep Space Communication Complex (GDSCC) sites at the Mars Site, and will include a fifth telemetry and command group with its associated link monitor, control processor, and operator consoles. The addition of these facilities will increase the capability of the DSN to support future sophisticated NASA spacecraft missions such as the International Solar and Terrestrial Physics (ISTP) Program. The planned construction of this building addition requires an Environmental Assessment (EA) document that records the existing environmental conditions at the Mars Site, that analyzes the environmental effects that possibly could be expected from the construction and use of the new building addition, and that recommends measures to be taken to mitigate any possible deleterious environmental effects.

  20. Projected Distributions and Diversity of Flightless Ground Beetles within the Australian Wet Tropics and Their Environmental Correlates

    PubMed Central

    Staunton, Kyran M.; Robson, Simon K. A.; Burwell, Chris J.; Reside, April E.; Williams, Stephen E.

    2014-01-01

    With the impending threat of climate change, greater understanding of patterns of species distributions and richness and the environmental factors driving them are required for effective conservation efforts. Species distribution models enable us to not only estimate geographic extents of species and subsequent patterns of species richness, but also generate hypotheses regarding environmental factors determining these spatial patterns. Projected changes in climate can then be used to predict future patterns of species distributions and richness. We created distribution models for most of the flightless ground beetles (Carabidae) within the Wet Tropics World Heritage Area of Australia, a major component of regionally endemic invertebrates. Forty-three species were modelled and the environmental correlates of these distributions and resultant patterns of species richness were examined. Flightless ground beetles generally inhabit upland areas characterised by stable, cool and wet environmental conditions. These distribution and richness patterns are best explained using the time-stability hypothesis as this group’s primary habitat, upland rainforest, is considered to be the most stable regional habitat. Projected changes in distributions indicate that as upward shifts in distributions occur, species currently confined to lower and drier mountain ranges will be more vulnerable to climate change impacts than those restricted to the highest and wettest mountains. Distribution models under projected future climate change suggest that there will be reductions in range size, population size and species richness under all emission scenarios. Eighty-eight per cent of species modelled are predicted to decline in population size by over 80%, for the most severe emission scenario by the year 2080. These results suggest that flightless ground beetles are among the most vulnerable taxa to climate change impacts so far investigated in the Wet Tropics World Heritage Area. These

  1. Projected distributions and diversity of flightless ground beetles within the Australian Wet Tropics and their environmental correlates.

    PubMed

    Staunton, Kyran M; Robson, Simon K A; Burwell, Chris J; Reside, April E; Williams, Stephen E

    2014-01-01

    With the impending threat of climate change, greater understanding of patterns of species distributions and richness and the environmental factors driving them are required for effective conservation efforts. Species distribution models enable us to not only estimate geographic extents of species and subsequent patterns of species richness, but also generate hypotheses regarding environmental factors determining these spatial patterns. Projected changes in climate can then be used to predict future patterns of species distributions and richness. We created distribution models for most of the flightless ground beetles (Carabidae) within the Wet Tropics World Heritage Area of Australia, a major component of regionally endemic invertebrates. Forty-three species were modelled and the environmental correlates of these distributions and resultant patterns of species richness were examined. Flightless ground beetles generally inhabit upland areas characterised by stable, cool and wet environmental conditions. These distribution and richness patterns are best explained using the time-stability hypothesis as this group's primary habitat, upland rainforest, is considered to be the most stable regional habitat. Projected changes in distributions indicate that as upward shifts in distributions occur, species currently confined to lower and drier mountain ranges will be more vulnerable to climate change impacts than those restricted to the highest and wettest mountains. Distribution models under projected future climate change suggest that there will be reductions in range size, population size and species richness under all emission scenarios. Eighty-eight per cent of species modelled are predicted to decline in population size by over 80%, for the most severe emission scenario by the year 2080. These results suggest that flightless ground beetles are among the most vulnerable taxa to climate change impacts so far investigated in the Wet Tropics World Heritage Area. These

  2. Documenting cost and performance for environmental remediation projects: Department of Energy Office of Environmental Management

    SciTech Connect

    1996-08-08

    The purpose of this DOE guide is to facilitate the use of consistent procedures to document cost and performance information for projects involving the remediation of media contaminated with hazardous and radioactive wastes. It provides remedial action project managers with a standardized set of data to document completed remediation projects. Standardized reporting of data will broaden the utility of the information, increase confidence in the effectiveness of future remedial technologies, and enhance the organization, storage and retrieval of relevant information for future cleanup projects. The foundation for this guide was laid down by the Federal Remediation Technologies Roundtable (FRTR) in their publication, Guide to Documenting Cost and Performance for Remediation Projects, EPA-542-B- 95-002. Member agencies of the FRTR include the US EPA, the US DOD, the US DOE, and the US DOI. All the member agencies are involved in site remediation projects and anticipate following the guidance provided in the above reference. Therefore, there is much to be gained for DOE to be consistent with the other member agencies as it will be easier to compare projects across different agencies and also to learn from the experiences of a wider spectrum of prior completed projects.

  3. A team leadership approach to managing the transition from construction to operations for an environmental project

    SciTech Connect

    Kelly, J.W.

    1994-06-01

    This presentation describes a team approach, at the totalproject level that focused team members with common objectives, for the transition to start-up and operation of the project. The Integrated Management Team (IMT) approach has been successful for this US Department of Energy (DOE) environmental restoration project at the Hanford Site in Richland, Washington. The $53.8-million project will collect, treat, and dispose of low-level mixed waste water discharges from the Hanford Site. Construction is scheduled for completion in September 1994 and facility start-up in June 1995. The project challenge is for leadership that is committed to the transition from construction to operation of the environmental restoration project.

  4. Environmental Effects of Tennessee-Tombigbee Project Cutoff Bendways.

    DTIC Science & Technology

    1982-08-01

    34 Fisheries Management, John Wiley and Sons, New York, pp 265-295. Patriarch, M. H., and Campbell, R. S . 1958. "The Development of the Fish Population in...34Effects of By-pass Canals on Fish Populations of the Lower Alabama River," Contract Report No. DACW01- 73-C-0017, U. S . Army Engineer District, Mobile...Miscellaneous Paper E-82-4 11,/ d / - 4. TITLE (ad &ShfItle) S . TYPE OF REPORT & PERIOD COVERED ENVIRONMENTAL EFFECTS OF TENNESSEE-TOMBIGBEE Final

  5. Yakima Fisheries Project : Revised Draft Environmental Impact Statement.

    SciTech Connect

    United States. Bonneville Power Administration.

    1995-05-01

    BPA proposes to fund several fishery-related activities in the Yakima River Basin. The Yakima Fisheries Project (YFP), included in the Northwest Power Planning Council`s fish and wildlife program, would be jointly managed by the State of Washington and the Yakima Indian Nation. Fisheries resources in the Yakima River are severely reduced from historical levels and there is a significant potential for enhancement of these resources. BPA`s proposed action is to fund (1) information gathering on the implementation of supplementation techniques and on feasibility of reintroducing coho salmon in an environment where native populations have become extinct; (2) research activities based on continuous assessment, feedback and improvement of research design and activities ({open_quotes}adaptive management{close_quotes}); and (3) the construction, operation, and maintenance of facilities for supplementing populations of upper Yakima spring chinook salmon. The project has been considerably revised from the original proposal described in the first draft EIS. Examined in addition to No Action (which would leave present anadromous fisheries resources unchanged in the, Basin) are two alternatives for action: (1) supplementation of depressed natural populations of upper Yakima spring chinook and (2) that same supplementation plus a study to determine the feasibility of re-establishing (via stock imported from another basin) naturally spawning population and a significant fall fishery for coho in the Yakima Basin. Alternative 2 has been identified as the preferred action. Major issues examined in the Revised Draft EIS include potential impacts of the project on genetic and ecological resources of existing fish populations, on water quality and quantity, on threatened and endangered species listed under the Endangered Species Act, and on the recreational fishery.

  6. Accuracy and stability in incompressible SPH (ISPH) based on the projection method and a new approach

    SciTech Connect

    Xu Rui Stansby, Peter; Laurence, Dominique

    2009-10-01

    The stability and accuracy of three methods which enforce either a divergence-free velocity field, density invariance, or their combination are tested here through the standard Taylor-Green and spin-down vortex problems. While various approaches to incompressible SPH (ISPH) have been proposed in the past decade, the present paper is restricted to the projection method for the pressure and velocity coupling. It is shown that the divergence-free ISPH method cannot maintain stability in certain situations although it is accurate before instability sets in. The density-invariant ISPH method is stable but inaccurate with random-noise like disturbances. The combined ISPH, combining advantages in divergence-free ISPH and density-invariant ISPH, can maintain accuracy and stability although at a higher computational cost. Redistribution of particles on a fixed uniform mesh is also shown to be effective but the attraction of a mesh-free method is lost. A new divergence-free ISPH approach is proposed here which maintains accuracy and stability while remaining mesh free without increasing computational cost by slightly shifting particles away from streamlines, although the necessary interpolation of hydrodynamic characteristics means the formulation ceases to be strictly conservative. This avoids the highly anisotropic particle spacing which eventually triggers instability. Importantly pressure fields are free from spurious oscillations, up to the highest Reynolds numbers tested.

  7. 78 FR 26063 - Central Utah Project Completion Act; East Hobble Creek Restoration Project Final Environmental...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-05-03

    ... significant impact on the quality of the human environment, and that an environmental impact statement is not required. ADDRESSES: Copies of the Final Environmental Assessment and Finding of No Significant Impact are... Reclamation Mitigation and Conservation Commission each signed a Finding of No Significant Impact...

  8. "Engendering" environmental projects: the case of eco-timber production in the Solomon Islands.

    PubMed

    Scheyvens, R

    1998-11-01

    This article discusses the case of timber production in the Solomon Islands and links between environmental protection and gender. Many environmental projects are undertaken without regard for gender roles and relations. The Solomon Western Islands Fair Trade (SWIFT) initiative included women in only a peripheral way. This article justifies the involvement of women in environmental projects and then evaluates the operations of SWIFT. A role for women in local environmental projects should be recognized because of women's roles, knowledge, and interests. Use of natural resources is gender-based. In the Solomon Islands, women are identified as having the greater interest in the long-term sustainability of the environment and greater reliance on natural resources to fulfill their roles, but forestry is men's work. The price of tropical woods has tempted Micronesian governments to exploit forests to enhance their foreign exchange earnings. Environmental degradation from logging is particularly severe in the Solomon Islands. The population fulfills many basic needs from forests. Forests can provide cash earnings. The author conducted an evaluation of effectiveness of SWIFT in 1996. The SWIFT project allows rural people to earn cash from sustainable timber extraction without signing with logging companies. Women are affected by SWIFT due to their husbands' appropriation of their earnings, their peripheral role, and lack of representation in senior positions and use of women's forestry expertise. The article offers a model for genderizing eco-projects. Men need to be encouraged to work more as partners with women.

  9. Environmental Projects. Volume 8: Modifications of wastewater evaporation ponds

    NASA Technical Reports Server (NTRS)

    1989-01-01

    The Goldstone Deep Space Communications Complex (GDSCC), located in the Mojave Desert about 45 miles north of Barstow, California, and about 160 miles northeast of Pasadena, is part of NASA's Deep Space Network, one of the world's largest and most sensitive scientific telecommunications and radio navigation networks. The Goldstone Complex is managed, technically directed, and operated for NASA by the Jet Propulsion Laboratory (JPL) of the California Institute of Technology in Pasadena, California. Activities at the GDSCC are carried out in support of seven parabolic dish antennas. These activities may give rise to environmental hazards: use of hazardous chemicals, asbestos, and underground storage tanks as well as the generation of hazardous wastes and the disposal of wastewater. Federal, state, and local laws governing the management of hazardous substances, asbestos, underground storage tanks and wastewater disposal have become so complex there is a need to devise specific programs to comply with the many regulations that implement these laws. In support of the national goal of the preservation of the environment and the protection of human health and safety, NASA, JPL, and the GDSCC have adopted a position that their operating installations shall maintain a high level of compliance with these laws. One of the environmental problems at the GDSCC involved four active, operational, wastewater evaporation ponds designed to receive and evaporate sewage effluent from upstream septic tank systems. One pair of active wastewater evaporation ponds is located at Echo Site, while another operational pair is at Mars Site.

  10. Coastal Aquifer Response to Environmental Change - Implications for Future Projections

    NASA Astrophysics Data System (ADS)

    Post, V.

    2014-12-01

    Coastal aquifers are important resources for water supply, and are increasingly stressed by population increase and the growing water demand for irrigation and other uses. Concern exists that these current pressures will be compunded by the adverse impacts of future environmental change, in particular sea-level rise. Numerous studies have investigated the effect of the expected sea-level rise durring the 21st century on the salintiy distribution in coastal groundwater systems. In many of these studies, the predicted changes due to an increase in sea level are typically seen as a departure from a steady-state situation. But many other studies have provided abundant evidence that groundwater systems in coastal areas are not in equilibrium with the present-day boundary conditions, i.e., coastline configuration and climate. This is borne out by, for example, the salinity distribution of groundwater, which does not obey the classical configuration of an intruded wedge of seawater extending inland from the coastline. This paper will argue that coastal aquifers systems are in a continuous state of transition. The relevance of future environmental change within the context of long-term trends will be discussed and exemplified by case studies of coastal aquifers in different parts of the world. It will be argued that the conceptualization of coastal groundwater systems, and in particular the connection between their onshore and offshore parts, is a major source of uncertainty in studies that aim to quantify the impact of sea-level rise on coastal groundwater resources.

  11. Environmental projects. Volume 14: Removal of contaminated soil and debris

    NASA Technical Reports Server (NTRS)

    Kushner, Len

    1992-01-01

    Numerous diverse activities at the Goldstone Deep Space Communications Complex (GDSCC) are carried out in support of six parabolic dish antennas. Some of these activities can result in possible spills or leakages of hazardous materials and wastes stored both above ground in steel drums and below ground in underground storage tanks (UST's). These possible leaks or spills, along with the past practice of burial of solid debris and waste in trenches and pits, could cause local subsurface contamination of the soil. In 1987, the Jet Propulsion Laboratory (JPL), retained Engineering-Science, Inc. (E-S), Pasadena, California, to identify the specific local areas within the GDSCC with subsurface soil contamination. The E-S study determined that some of the soils at the Apollo Site and the Mars Site were contaminated with hydrocarbons, while soil at a nonhazardous waste dumpsite at the Mojave Base site was contaminated with copper. This volume is a JPL-expanded version of the PE209 E-S report, and it also reports that all subsurface contaminated soils at the GDSCC were excavated, removed, and disposed of in an environmentally acceptable way, and the excavations were backfilled and covered in accordance with accepted Federal, State, and local environmental rules and regulations.

  12. Mid-Columbia Coho Salmon Reintroduction Feasibility Project : Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration; Washington Department of Fish and Wildlife; Confederated Tribes and Bands of the Yakama Nation

    1999-01-01

    Before the Bonneville Power Administration (BPA) decides whether to fund a program to reintroduce coho salmon to mid-Columbia River basin tributaries, research is needed to determine the ecological risks and biological feasibility of such an effort. Since the early 1900s, the native stock of coho has been decimated in the tributaries of the middle reach of the Columbia River. The four Columbia River Treaty Tribes identified coho reintroduction in the mid-Columbia as a priority in the Tribal Restoration Plan. It is a comprehensive plan put forward by the Tribes to restore the Columbia River fisheries. In 1996, the Northwest Power Planning Council (NPPC) recommended the tribal mid-Columbia reintroduction project for funding by BPA. It was identified as one of fifteen high-priority supplementation projects for the Columbia River basin, and was incorporated into the NPPC`s Fish and Wildlife Program. The release of coho from lower Columbia hatcheries into mid-Columbia tributaries is also recognized in the Columbia River Fish Management Plan.

  13. Draft West Valley Demonstration Project Waste Management Environmental Impact Statement

    SciTech Connect

    N /A

    2003-05-16

    As part of its ongoing West Valley Demonstration Project (WVDP), and in accordance with the West Valley Demonstration Project Act and previous U.S. Department of Energy (DOE or the Department) decisions, DOE proposes to: (1) Continue onsite management of high-level radioactive waste (HLW) until it can be shipped for disposal to a geologic repository (assumed for the purposes of analysis to be the proposed Yucca Mountain Repository near Las Vegas, Nevada), (2) Ship low-level radioactive waste (LLW) and mixed (radioactive and hazardous) LLW offsite for disposal at DOE or other disposal sites, (3) Ship transuranic (TRU) radioactive waste to the Waste Isolation Pilot Plant (WIPP), and (4) Actively manage the waste storage tanks. The waste volumes that are the subject of evaluation in this EIS include only those wastes that are either currently in storage or that would be generated over the next 10 years from ongoing operations and decontamination activities. This EIS analyzes activities that would occur during a 10-year period.

  14. Eiatne and Flyklim, Two Projects Concerning Environmental Impacts From Air Transportation Over North Europe

    NASA Astrophysics Data System (ADS)

    Pålsson, A.; Moldanová, J.; Bergström, R.; Langner, J.; Wyser, K.; Lindskog, A.

    Structure and methodology of two projects concerned with regional impact of air traf- fic on the atmosphere is presented. The EIATNE project aims to develop methods and decision support for environmental adaptation of air traffic and air traffic control in en- vironmentally sensitive regions. The FLYKLIM project is closely related to EIATNE, its objective is to study the effect of air traffic on the regional climate in Northern Europe and in particular its effect on high-altitude clouds. The environmental impacts from air traffic within a geographical area are evaluated through interdisciplinary co- operation. Aircraft emissions have been extracted from a four-dimensional analysis based on model calculations of the collected air traffic over Sweden during a limited duration. The project aims to combine model simulations of aircraft performance with model simulations of the dispersion of exhausts and their reactions in the atmosphere, both at cruise altitudes and around airports, in order to evaluate the environmental im- pacts. The project involves use of results from previous research projects, which will be integrated for a qualified analysis of the large-scale environmental effects.

  15. Supplement Analysis for the Watershed Management Program EIS - Libby Creek (Lower Cleveland) Stabilization Project

    SciTech Connect

    N /A

    2004-07-29

    This project is follow-up to stream stabilization activities on Libby Creek that were initiated on the Upper Cleveland reach of Libby Creek 2 years ago. BPA now proposes to fund FWP to complete channel stabilization activities on the Lower Cleveland reach of Libby Creek, reduce sediment sources, convert overwidened portions of the stream into self-maintaining channel types, use natural stream stabilization techniques, and improve wildlife migratory corridors. This lower reach is about one river mile below the upper Cleveland Reach and the proposed activities are very similar to those conducted before. The current work would be constructed in two additional phases. The first phase of the Lower Cleveland project would be completed in the fall of 2004 (9/1/04--12/31/04), to include the upper 3,100 feet. The second phase will be constructed in the fall of 2005 (9/1/05--12/31/05), to include stabilizing the remaining 6,200 feet of stream. The Cleveland reaches are a spawning and rearing tributary for resident redband trout, and resident and fluvial bull trout migrating from the Kootenai River. The planned work at the two remaining phases calls for shaping cut banks; installing root wads and tree revetments; installing channel grade control structures; planting native vegetation; and installing cross vanes constructed from rock and trees to control channel gradient. In the past, this reach of Libby Creek has been degraded by past management practices, including road building, hydraulic and dredge mining, and riparian logging. This past activity has resulted in accelerated bank erosion along a number of meander bends, resulting in channel degradation and poor fish habitat. Currently the stream channel is over-widened and shallow having limited pool habitat. The current stream channel is over-widened and shallow, having limited pool habitat.

  16. Telephone Flat Geothermal Development Project Environmental Impact Statement Environmental Impact Report. Final

    SciTech Connect

    1999-02-01

    This Final Environmental Impact Statement and Environmental Impact Report (Final EIS/EIR) has been prepared to meet the requirements of the National Environmental Policy Act (NEPA) and the California Environmental Quality Act (CEQA). The Proposed Action includes the construction, operation, and decommissioning of a 48 megawatt (gross) geothermal power plant with ancillary facilities (10-12 production well pads and 3-5 injection well pads, production and injection pipelines), access roads, and a 230-kilovolt (kV) transmission line in the Modoc National Forest in Siskiyou County, California. Alternative locations for the power plant site within a reasonable distance of the middle of the wellfield were determined to be technically feasible. Three power plant site alternatives are evaluated in the Final EIS/EIR.

  17. Maine Environmental Priorities Project: Summary of the Reports from the Technical Working Groups to the Steering Committee.

    ERIC Educational Resources Information Center

    National Association for Environmental Education, Miami, FL.

    The Maine Environmental Priorities Project (MEPP) is a comparative risk project designed to identify, compare, and rank the most serious environmental problems facing Maine. Once the problems are analyzed and ranked according to their threat or risk to Maine's ecological health, human health, and quality of life, the project will propose…

  18. Using Theory of Learning and Awareness to Bring about Learning through a School-Based Environmental Field Project

    ERIC Educational Resources Information Center

    Kwan, Tammy; Chan, Eva

    2004-01-01

    A school-based environmental field project "What Happens Around You and Your School Area?" was designed under the School-based Curriculum Project Scheme (2001-2002) supported by the Hong Kong Education Manpower Bureau (formerly the Education Department). This school-based environmental field project, with heavy inclusion of environmental…

  19. Environmentally conscious manufacturing & technology access project: Final technical progress report, April 1, 1994--September 30, 1996

    SciTech Connect

    1997-05-01

    This final report is being submitted in fulfillment of the management obligations associated with the TRP/DOE grant which funded the Environmentally Conscious Manufacturing & Technology Access (ECM) Project. A {open_quotes}Federal Assistance Project Status Report{close_quotes} is also being submitted with this form. This report will elaborate on the successful completion of this project in achieving and in most cases exceeding its programmatic goals and fulfilling it statutory financial match obligation. A review of the Year 1 {open_quotes}Technical Progress Report{close_quotes} and the Quarterly Reports filed during the project period, clearly portray that, in all substantive areas, the Environmentally Conscious Manufacturing & Technology Access Project (ECM Project) achieved or exceeded its goals. The success of the Project is largely due to the tremendous support provided by the Center for Technology Transfer (CTT) and the Maine Metal Products Association (MMPA). Both organizations provided extensive administrative and financial support and were instrumental in promoting the work of the project within the metals industry. The programmatic oversight provided by the industry Steering Committee and the broad partnership represented on the Board of Advisors were invaluable in developing, promoting and implementing the work of the ECM Project.

  20. Environmental projects. Volume 12: Friable asbestos abatement, GDSCC

    NASA Technical Reports Server (NTRS)

    1990-01-01

    The Goldstone Deep Space Communications Complex (GDSCC) is part of the NASA Deep Space Network, one of the world's largest and most sensitive scientific telecommunications and radio navigation networks. Activities at the GDSCC are carried out in support of six large parabolic dish antennas. These activities may give rise to a variety of environmental hazards, particularly the danger of exposure of GDSCC personnel to asbestos fibers that have been shown to be responsible for such serious ailments as asbestosis, lung cancer, and mesothelioma. Asbestos-containing materials (ACM's) were used in the construction of many of the approximately 100 buildings and structures that were built at the GDSCC during a 30-year period from the 1950s through 1980s. The friable asbestos-abatement program at the GDSCC is presented which consists of text, illustrations, and tables that describe the friable asbestos abatement carried out at the GDSCC from December 21, 1988 through May 11, 1989.

  1. Improving Environmental Projections in the High Mountains of Northern Eurasia

    NASA Astrophysics Data System (ADS)

    Groisman, Pavel; Aizen, Vladimir

    2009-12-01

    International Workshop on the Northern Eurasia High Mountain Ecosystems; Bishkek, Kyrgyzstan, 9-13 September 2009; The northern Eurasia high mountains, particularly in dry regions of Central Asia, are critically important because they are the source of the water supply for the densely populated lowlands. These regions are highly vulnerable to climatic and environmental changes. Global warming, current and future expected retreat of seasonal snow cover and glaciers, and changes in precipitation pattern and type significantly affect river runoff, permafrost, and groundwater. Moreover, the majority of mountain regions in northern Eurasia are characterized by growing anthropogenic pressure that causes harmful feedback, including desertification of lowlands; wind erosion; contamination of the atmosphere, surface waters, and groundwaters; reduction in crop yield; and increasing human mortality rates.

  2. Environmental Assessment : Tumwater Dam and Dryden Dam Fish Passage Projects.

    SciTech Connect

    United States. Bonneville Power Administration.

    1986-01-01

    Existing fish passage facilities at Tumwater Dam and Dryden Dam currently do not effectively pass the anadromous fish runs in the Wenatchee River. At Tumwater Dam, the proposed action includes the construction of a new fish ladder which will improve water flow characteristics and, subsequently, fish passage. In order to improve fish passage at Dryden Dam, a new fish ladder will be constructed to replace the existing ladder and another ladder will be constructed. The proposed action will supplement mitigation of adverse hydroelectric impacts to the fisheries of the Columbia River basin. The proposal to fund the Tumwater Dam and Dryden Dam Fish Passage facilities does not appear to constitute a major Federal action significantly affecting the quality of the human environment and would not require an environmental impact statement.

  3. Use of remotely operated excavators for environmental restoration projects

    SciTech Connect

    Kruse, P.W.; Wilson, J.

    1994-12-31

    Spar Aerospace and RSI Research have modified a Hitachi model EX200LC for remote operation. For projects requiring the retrieval of certain types of radioactive and hazardous waste, the toxic nature of the material will require that remotely operated equipment be used to retrieve the waste. For the recovery of buried boxes and drums, an excavator that has been modified for remote operation provides both the high payload capacity as well as the ruggedness to safely and efficiently recover these types of material. The Hitachi model EX200LC excavator was selected because this model of excavator has the payload capacity and versatility to recover buried radioactive waste at U.S. Department of Energy sites as well as buried ordnance and toxic chemicals at Department of Defense sites.

  4. Conforth Ranch (Wanaket) Wildlife Mitigation Project : Draft Management Plan and Draft Environmental Assessment.

    SciTech Connect

    United States. Bonneville Power Administration; Confederated Tribes of the Umatilla Reservation, Oregon.

    1995-03-01

    Bonneville Power Administration (BPA) proposes to mitigate for loss of wildlife habitat caused by the development of Columbia River Basin hydroelectric projects, including McNary dam. The proposed wildlife mitigation project involves wildlife conservation on 1140 hectares (ha)(2817 acres) of land (including water rights) in Umatilla County, Oregon. BPA has prepared an Environmental Assessment (EA)(DOE/EA- 1016) evaluating the proposed project. Based on the analysis in the EA, BPA has determined that the proposed action is not a major Federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act (NEPA) of 1969. Therefore, the preparation of an Environmental Impact Statement (EIS) is not required, and BPA is issuing this Finding of No Significant Impact (FONSI).

  5. Environmental Assessment for the Warren Station externally fired combined cycle demonstration project

    SciTech Connect

    1995-04-01

    The proposed Penelec project is one of 5 projects for potential funding under the fifth solicitation under the Clean Coal Technology program. In Penelec, two existing boilers would be replaced at Warren Station, PA; the new unit would produce 73 MW(e) in a combined cycle mode (using both gas-fired and steam turbines). The project would fill the need for a full utility-size demonstration of externally fire combined cycle (EFCC) technology as the next step toward commercialization. This environmental assessment was prepared for compliance with NEPA; its purpose is to provide sufficient basis for determining whether to prepare an environmental impact statement or to issue a finding of no significant impact. It is divided into the sections: purpose and need for proposed action; alternatives; brief description of affected environment; environmental consequences, including discussion of commercial operation beyond the demonstration period.

  6. Environmental mitigation at hydroelectric projects: Volume II. Benefits and costs of fish passage and protection

    SciTech Connect

    Francfort, J. E.; Cada, G. F.; Dauble, D. D.; Hunt, R. T.; Jones, D. W.; Rinehart, B. N.; Sommers, G. L.; Costello, R. J.

    1994-01-01

    The Department of Energy, through its hydropower program, is studying environmental mitigation practices at hydroelectric projects. The study of environmental mitigation is intended to provide greater understanding of environmental problems and solutions that are associated with conventional hydroelectric projects. This volume examines upstream and downstream fish passage/protection technologies and the associated practices, benefits, and costs. Fish passage/protection mitigation technologies are investigated by three methods: (a) national, regional (Federal Energy Regulatory Commission regions), and temporal frequencies of fish passage/protection mitigation are examined at 1,825 operating and conventional (excludes pumped storage) Federal Energy Regulatory Commission (FERC) regulated hydroelectric sites in the United States; (b) general fish passage/protection mitigation costs are discussed for 50 FERC regulated hydroelectric projects; and (c) 16 case studies are used to examine specific fish passage/protection mitigation practices, benefits, and costs.

  7. A more elemental examination of factors governing PV module environmental stability

    SciTech Connect

    Jester, T.L.; Aldrich, D.; Hummel, J.; Wieting, R.D.; Galica, J.P.; Thoma, L.

    1994-12-31

    To date, photovoltaic module reliability studies have primarily focused on retention of initial power when exposed to various environmental stresses. While power of a PV module is one reliability measure, the fundamental parameters affecting photovoltaic module stability are typically not measured for baseline analysis. This study examines these questions in context of fundamental parameters, in an attempt to gain insight at a more elemental level than possible using power measurements. One of the fundamental parameters in PV module reliability is the adhesion of the encapsulant EVA to various module surfaces. The analysis of surface adhesion, both in its initial state, and as it changes with various exposures is studied here, primarily focusing on adhesion of EVA to glass, cell surfaces and the interconnect ribbon. Of particular interest is the affect of manufacturing processes and surface cleanliness on this bond strength. Measurements of EVA adhesion and how it is affected by surface contamination due to residual solder flux have also been specifically quantified. The summary analysis looked at EVA bonds as a function of environmental exposures. The results of this analysis shows that initial strength of EVA bonds are quite high, these are diminished by both surface contamination effects and environmental exposures. The ultimate bond strength and the ratio to the initial value are variable dependent upon the exposure.

  8. Environmental Compliance at the West Valley Demonstration Project: The Vitrification Permitting Program

    SciTech Connect

    L. C. Salvatori; C. B. Banzer; W. T. Watters

    1996-05-28

    The major environmental laws that apply to the West Valley Demonstration Project (WVDP) are the: Resource Conservation and Recovery Act (RCRA), Clean Air Act (CAA), Clean Water Act (CWA), Safe Drinking Water Act (SDWA), Toxic Substances Control Act (TSCA), National Environmental Policy Act (NEPA), and Emergency Planning and Community Right-To-Know Act (EPCRA). Regulations developed in accordance with these laws are administered by the New York State Department of Environmental Conservation (NYSDEC) and the U.S. Environmental Protection Agency (EPA) through state and federal programs, and regulatory requirements such as permitting. The Environmental Permits & Reports (EP&R) Group of the Environmental Affairs (EA) Department has the primary responsibility for developing a site-wide permitting program for the WVDP and obtaining the necessary permits. This report discusses the permits and the permitting process associated with the Vitrification Facility (VF).

  9. A large-scale forest fragmentation experiment: the Stability of Altered Forest Ecosystems Project.

    PubMed

    Ewers, Robert M; Didham, Raphael K; Fahrig, Lenore; Ferraz, Gonçalo; Hector, Andy; Holt, Robert D; Kapos, Valerie; Reynolds, Glen; Sinun, Waidi; Snaddon, Jake L; Turner, Edgar C

    2011-11-27

    Opportunities to conduct large-scale field experiments are rare, but provide a unique opportunity to reveal the complex processes that operate within natural ecosystems. Here, we review the design of existing, large-scale forest fragmentation experiments. Based on this review, we develop a design for the Stability of Altered Forest Ecosystems (SAFE) Project, a new forest fragmentation experiment to be located in the lowland tropical forests of Borneo (Sabah, Malaysia). The SAFE Project represents an advance on existing experiments in that it: (i) allows discrimination of the effects of landscape-level forest cover from patch-level processes; (ii) is designed to facilitate the unification of a wide range of data types on ecological patterns and processes that operate over a wide range of spatial scales; (iii) has greater replication than existing experiments; (iv) incorporates an experimental manipulation of riparian corridors; and (v) embeds the experimentally fragmented landscape within a wider gradient of land-use intensity than do existing projects. The SAFE Project represents an opportunity for ecologists across disciplines to participate in a large initiative designed to generate a broad understanding of the ecological impacts of tropical forest modification.

  10. A large-scale forest fragmentation experiment: the Stability of Altered Forest Ecosystems Project

    PubMed Central

    Ewers, Robert M.; Didham, Raphael K.; Fahrig, Lenore; Ferraz, Gonçalo; Hector, Andy; Holt, Robert D.; Kapos, Valerie; Reynolds, Glen; Sinun, Waidi; Snaddon, Jake L.; Turner, Edgar C.

    2011-01-01

    Opportunities to conduct large-scale field experiments are rare, but provide a unique opportunity to reveal the complex processes that operate within natural ecosystems. Here, we review the design of existing, large-scale forest fragmentation experiments. Based on this review, we develop a design for the Stability of Altered Forest Ecosystems (SAFE) Project, a new forest fragmentation experiment to be located in the lowland tropical forests of Borneo (Sabah, Malaysia). The SAFE Project represents an advance on existing experiments in that it: (i) allows discrimination of the effects of landscape-level forest cover from patch-level processes; (ii) is designed to facilitate the unification of a wide range of data types on ecological patterns and processes that operate over a wide range of spatial scales; (iii) has greater replication than existing experiments; (iv) incorporates an experimental manipulation of riparian corridors; and (v) embeds the experimentally fragmented landscape within a wider gradient of land-use intensity than do existing projects. The SAFE Project represents an opportunity for ecologists across disciplines to participate in a large initiative designed to generate a broad understanding of the ecological impacts of tropical forest modification. PMID:22006969

  11. Integrated Codes for Estimating Environmental Accumulation and Individual Dose from Past Hanford Atmospheric Releases: Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Ikenberry, T. A.; Burnett, R. A.; Napier, B. A.; Reitz, N. A.; Shipler, D. B.

    1992-02-01

    Preliminary radiation doses were estimated and reported during Phase I of the Hanford Environmental Dose Reconstruction (HEDR) Project. As the project has progressed, additional information regarding the magnitude and timing of past radioactive releases has been developed, and the general scope of the required calculations has been enhanced. The overall HEDR computational model for computing doses attributable to atmospheric releases from Hanford Site operations is called HEDRIC (Hanford Environmental Dose Reconstruction Integrated Codes). It consists of four interrelated models: source term, atmospheric transport, environmental accumulation, and individual dose. The source term and atmospheric transport models are documented elsewhere. This report describes the initial implementation of the design specifications for the environmental accumulation model and computer code, called DESCARTES (Dynamic EStimates of Concentrations and Accumulated Radionuclides in Terrestrial Environments), and the individual dose model and computer code, called CIDER (Calculation of Individual Doses from Environmental Radionuclides). The computations required of these models and the design specifications for their codes were documented in Napier et al. (1992). Revisions to the original specifications and the basis for modeling decisions are explained. This report is not the final code documentation but gives the status of the model and code development to date. Final code documentation is scheduled to be completed in FY 1994 following additional code upgrades and refinements. The user's guide included in this report describes the operation of the environmental accumulation and individual dose codes and associated pre- and post-processor programs. A programmer's guide describes the logical structure of the programs and their input and output files.

  12. Community Leaders' Training in Environmental Studies: A Cooperative Community Project Funded under Title I of the Higher Education Act of 1965. Warp to Environmental Education. Final Report.

    ERIC Educational Resources Information Center

    Allen, Rodney F.; LaHart, David

    This document is the final report of the Community Leaders' Training in Environmental Studies Project conducted at Florida State University. The project sought to increase community environmental awareness and to expand the educational uses of the Tallahassee Junior Museum through the cooperation of museum staff, a variety of community groups, and…

  13. Clean-coal technology by-products used in a highway embankment stabilization demonstration project. Master's thesis

    SciTech Connect

    Nodjomian, S.M.

    1994-01-01

    Clean-coal technology by-products are used in a highway embankment demonstration project. This research chronicles the procedures used in the process and analyzes the stability of a repaired highway embankment. The reconstructed slope is analyzed using an Intelligent Discussion Support System that was developed from a slope stability program. Water quality studies are performed and an instrumentation plan is suggested. The calculated factors of safety and the observed embankment performance give indications that the field demonstration project was a success. Long-term monitoring will be the best barometer for determining embankment gross movement and the future of FGD by-products as a stabilizing material.

  14. Using offsets to mitigate environmental impacts of major projects: A stakeholder analysis.

    PubMed

    Martin, Nigel; Evans, Megan; Rice, John; Lodhia, Sumit; Gibbons, Philip

    2016-09-01

    Global patterns of development suggest that as more projects are initiated, business will need to find acceptable measures to conserve biodiversity. The application of environmental offsets allows firms to combine their economic interests with the environment and society. This article presents the results of a multi-stakeholder analysis related to the design of offsets principles, policies, and regulatory processes, using a large infrastructure projects context. The results indicate that business was primarily interested in using direct offsets and other compensatory measures, known internationally as indirect offsets, to acquit their environmental management obligations. In contrast, the environmental sector argued that highly principled and scientifically robust offsets programs should be implemented and maintained for enduring environmental protection. Stakeholder consensus stressed the importance of offsets registers with commensurate monitoring and enforcement. Our findings provide instructive insights into the countervailing views of offsets policy stakeholders.

  15. Environmental Assessment of Proposed Filbert Substation and Tap Project.

    SciTech Connect

    United States. Bonneville Power Administration.

    1984-03-01

    The proposal is a cooperative (jointly funded and owned) action between Bonneville Power Administration (BPS) and FGLandP involving construction of the 115/12.5-kV Filbert Substation. BPA would also build a 0.8-mile overhead 115-kV tapline from BPA's Forest Grove-McMinnville 115-kV line to the proposed substation. The Forest Grove-McMinnville transmission line has available capacity to support the proposed substation. The FGLandP would build four underground distribution circuits to connect the substation to its existing distribution system. It is normally BPA's practice to consider several substation location alternatives as a part of its facility siting process. The proposed substation site was recommended after a preliminary field evaluation by BPA determined that building on the proposed site was preferable because available sites south of the Tualatin Valley Highway and Southern Pacific Railroad were either on presently cultivated farmland, were in a floodplain, or were inaccessible without extensive access road construction. The proposed substation site is owned by FGLandP, is designated for use as a utility substation in the Forest Grove Comprehensive Plan, and was purchased by FGLandP in anticipation of a need for its use as a substation site because of its central location in relation to existing and forecasted loads. The site is accessible from Filbert Street (city road), and is gently sloping. This report describes potential environmental impacts of the proposed actions.

  16. Environmental Test Program for the Mars Exploration Rover Project

    NASA Technical Reports Server (NTRS)

    Fisher, Terry C.; VanVelzer, Paul L.

    2004-01-01

    On June 10 and July 7, 2003 the National Aeronautics and Space Administration (NASA) launched two spacecraft from Cape Canaveral, Florida for a six (6) months flight to the Red Planet, Mars. The two Mars Exploration Rover spacecraft landed safely on the planet in January 2004. Prior to the successful launch, both of the spacecraft were involved in a comprehensive test campaign that included development, qualification, and protoflight test programs. Testing was performed to simulate the environments associated with launch, inter-planetary cruise, landing on the planet and Mars surface operations. Unique test requirements included operating the spacecraft while the chamber pressure was controlled to simulate the decent to the planet from deep space, high impact landing loads and rover operations on the surface of the planet at 8 Torr and -130 C. This paper will present an overview of the test program that included vibration, pyro-shock, landing loads, acoustic noise, thermal vacuum and solar simulation testing at the Jet Propulsion Laboratory (JPL) Environmental Test Laboratory facilities in Pasadena, California.

  17. Environmental management requirements/defensible costs project. Final report

    SciTech Connect

    1996-02-01

    Lockheed Idaho Technologies Company (LITCO) used a systems engineering approach to develop the first formal requirements baseline for Idaho National Engineering Laboratory (INEL) Environmental Management (EM) Programs. The recently signed Settlement Agreement with the State of Idaho (Batt Agreement), along with dramatically reduced EM funding targets from Department of Energy (DOE) headquarters, drove the immediacy of this effort. Programs have linked top-level requirements to work scope to cost estimates. All EM work, grouped by decision units, was scrubbed by INEL EM programs and by an independent {open_quotes}Murder Board.{close_quotes} Direct participation of upper level management from LITCO and the DOE-Idaho Operations Office ensured best information and decisions. The result is a scrubbed down, defensible budget tied to top-level requirements for use in the upcoming DOE-Headquarters` budget workout, the Internal Review Board, the FY98 Activity Data Sheets submittal, and preparation of the FY97 control accounts and out-year plans. In addition to the remarkable accomplishments during the past eight weeks, major issues were identified and documented and follow-on tasks are underway which will lead to further improvements in INEL EM program management.

  18. Proposed Fermilab upgrade main injector project. Environmental Assessment

    SciTech Connect

    Not Available

    1992-04-01

    The US Department of Energy (DOE) proposes to construct and operate a ``Fermilab Main Injector`` (FMI), a 150 GeV proton injector accelerator, at the Fermi National Accelerator Laboratory (Fermilab) in Batavia, Illinois. The purpose and need for this action are given of this Environmental Assessment (EA). A description of the proposed FMI and construction activities are also given. The proposed FMI would be housed in an underground tunnel with a circumference of approximately 2.1 miles (3.4 kilometers), and the construction would affect approximately 135 acres of the 6,800 acre Fermilab site. The purpose of the proposed FMI is to construct and bring into operation a new 150 GeV proton injector accelerator. This addition to Fermilab`s Tevatron would enable scientists to penetrate ever more deeply into the subatomic world through the detection of the super massive particles that can be created when a proton and antiproton collide head-on. The conversion of energy into matter in these collisions makes it possible to create particles that existed only an instant after the beginning of time. The proposed FMI would significantly extend the scientific reach of the Tevatron, the world`s first superconducting accelerator and highest energy proton-antiproton collider.

  19. Initial Assessment of Environmental Barrier Coatings for the Prometheus Project

    SciTech Connect

    M. Frederick

    2005-12-15

    Depending upon final design and materials selections, a variety of engineering solutions may need to be considered to avoid chemical degradation of components in a notional space nuclear power plant (SNPP). Coatings are one engineered approach that was considered. A comprehensive review of protective coating technology for various space-reactor structural materials is presented, including refractory metal alloys [molybdenum (Mo), tungsten (W), rhenium (Re), tantalum (Ta), and niobium (Nb)], nickel (Ni)-base superalloys, and silicon carbide (Sic). A summary description of some common deposition techniques is included. A literature survey identified coatings based on silicides or iridium/rhenium as the primary methods for environmental protection of refractory metal alloys. Modified aluminide coatings have been identified for superalloys and multilayer ceramic coatings for protection of Sic. All reviewed research focused on protecting structural materials from extreme temperatures in highly oxidizing conditions. Thermodynamic analyses indicate that some of these coatings may not be protective in the high-temperature, impure-He environment expected in a Prometheus reactor system. Further research is proposed to determine extensibility of these coating materials to less-oxidizing or neutral environments.

  20. Environmental Statement for Local Flood Protection Project at Three Rivers, Texas. Supplement.

    DTIC Science & Technology

    1977-02-28

    Oak County, Texas Nueces River Three Rivers Local Flood Protection Project 20. AD6TRACT (C-Iut. u m ~ "d if ne~em and ~ideif by block nutbr...Environmental impact statement/report purposes to construct a levee system to protect the city of Three Rivers, Texas from flooding of Frio and Nueces Rivers. No...Construct levee system to protect the city of Three Rivers, Texas, from flooding of Frio and Nueces Rivers. 3. a. Environmental Impacts: The project

  1. Establishing an EnvironMentors Project to Guide Minority Students into Science, Technology, and Environmental Careers

    SciTech Connect

    Montague, W. E.

    2003-01-24

    This report of the EnvironMentors Project (TEP) for the period February 1994 through December 1998, provides a summary of activities at our program sites and of our overall organizational accomplishments. Notably, the EnvironMentors Project matched 506 teens from under-resourced neighborhoods in Washington (DC), Trenton (NJ), and Baltimore (MD) with mentors, engaged more than 1,600 members of the public in informative discussions of environmental research, and presented interactive environmental education lessons to approximately 5,700 elementary and middle school children.

  2. RESOLVE (Regolith & Environmental Science Oxygen & Lunar Volatile Extraction) Project

    NASA Technical Reports Server (NTRS)

    Parker, Ray; Coan, Mary; Captain, Janine; Cryderman, Kate; Quinn, Jacqueline

    2015-01-01

    The RESOLVE Project is a lunar prospecting mission whose primary goal is to characterize water and other volatiles in lunar regolith. The Lunar Advanced Volatiles Analysis (LAVA) subsystem is comprised of a fluid subsystem that transports flow to the gas chromatograph - mass spectrometer (GC-MS) instruments that characterize volatiles and the Water Droplet Demonstration (WDD) that will capture and display water condensation in the gas stream. The LAVA Engineering Test Unit (ETU) is undergoing risk reduction testing this summer and fall within a vacuum chamber to understand and characterize component and integrated system performance. Testing of line heaters, printed circuit heaters, pressure transducers, temperature sensors, regulators, and valves in atmospheric and vacuum environments was done. Test procedures were developed to guide experimental tests and test reports to analyze and draw conclusions from the data. In addition, knowledge and experience was gained with preparing a vacuum chamber with fluid and electrical connections. Further testing will include integrated testing of the fluid subsystem with the gas supply system, near-infrared spectrometer for the Surge Tank (NIRST), WDD, Sample Delivery System, and GC-MS in the vacuum chamber. Since LAVA is a scientific subsystem, the near infrared spectrometer and GC-MS instruments will be tested during the ETU testing phase.

  3. Applicability of the "Frame of Reference" approach for environmental monitoring of offshore renewable energy projects.

    PubMed

    Garel, Erwan; Rey, Cibran Camba; Ferreira, Oscar; van Koningsveld, Mark

    2014-08-01

    This paper assesses the applicability of the Frame of Reference (FoR) approach for the environmental monitoring of large-scale offshore Marine Renewable Energy (MRE) projects. The focus is on projects harvesting energy from winds, waves and currents. Environmental concerns induced by MRE projects are reported based on a classification scheme identifying stressors, receptors, effects and impacts. Although the potential effects of stressors on most receptors are identified, there are large knowledge gaps regarding the corresponding (positive and negative) impacts. In that context, the development of offshore MRE requires the implementation of fit-for-purpose monitoring activities aimed at environmental protection and knowledge development. Taking European legislation as an example, it is suggested to adopt standardized monitoring protocols for the enhanced usage and utility of environmental indicators. Towards this objective, the use of the FoR approach is advocated since it provides guidance for the definition and use of coherent set of environmental state indicators. After a description of this framework, various examples of applications are provided considering a virtual MRE project located in European waters. Finally, some conclusions and recommendations are provided for the successful implementation of the FoR approach and for future studies.

  4. Final Definite Project Report and Final Environmental Assessment, Keystone Harbor Channel Deepening, Admiralty Inlet, Washington

    DTIC Science & Technology

    1991-10-01

    impacts are expected. DISTRIBUTION/AVAILABILITY OF ABSTRACT 21 ABSTRACT SECURITY CLASSIFICATION UNCLASSIFIED/UNLIMITED 0 SAME AS RPT. 03 DTIC USERS...would not increase the channel shoaling rate or the cost of regular maintenance dredging, o would have no significant impacts to environmental features...TABLE OF CONTENTS (cont.) ENVIRONMENTAL ASSESSMENT FINDING OF NO SIGNIFICANT IMPACT Number PLATES 1 Project Plan and Typical Cross-Section 2

  5. Lessons Learned from the Development and Implementation of the Atmosphere Resource Recovery and Environmental Monitoring Project

    NASA Technical Reports Server (NTRS)

    Roman, Monsi C.; Perry, Jay L.; Howard, David F.

    2014-01-01

    The Advanced Exploration Systems (AES) Program's Atmosphere Resource Recovery and Environmental Monitoring (ARREM) Project have been developing atmosphere revitalization and environmental monitoring subsystem architectures suitable for enabling sustained crewed exploration missions beyond low Earth orbit (LEO). Using the International Space Station state-of-the-art (SOA) as the technical basis, the ARREM Project has contributed to technical advances that improve affordability, reliability, and functional efficiency while reducing dependence on a ground-based logistics resupply model. Functional demonstrations have merged new process technologies and concepts with existing ISS developmental hardware and operate them in a controlled environment simulating various crew metabolic loads. The ARREM Project's strengths include access to a full complement of existing developmental hardware that perform all the core atmosphere revitalization functions, unique testing facilities to evaluate subsystem performance, and a coordinated partnering effort among six NASA field centers and industry partners to provide the innovative expertise necessary to succeed. A project overview is provided and the project management strategies that have enabled a multidiscipinary engineering team to work efficiently across project, NASA field center, and industry boundaries to achieve the project's technical goals are discussed. Lessons learned and best practices relating to the project are presented and discussed.

  6. Scoping session of the programmatic environmental impact statement for the Uranium Mill Tailings Remedial Action Project

    SciTech Connect

    1992-12-31

    This document is about the scoping session which was held at the Community Center in Falls City, Texas. The purpose was to obtain public comment on the Programmatic Environmental Impact Statement for the Uranium Mill Tailings Remedial Action Project (UMTRA), specifically on the ground water project. Presentations made by the manager for the entire UMTRA program, manager of the site and ground water program, comments made by two residents of Fall City are included in this document.

  7. New Waddell-Westwing 230-kV transmission project, Maricopa County, Arizona: Environmental assessment

    SciTech Connect

    Not Available

    1988-10-01

    The Western Area Power Administration (Western) proposes to construct a new 230 kilovolt (kV) transmission line in Maricopa County, Arizona, that would extend from the New Waddell Dam on the Agua Fria River, to the Westwing Substation, about 10.5 miles southwest of the dam. The project area is roughly 45 miles northwest of the Phoenix metropolitan area. Western will complete the National Environmental Policy Act of 1969 (NEPA) process for the line. A final environmental impact statement (EIS) was prepared by BuRec to describe the environmental impacts associated with alternatives for the construction and operation of the Regulatory Storage Division of the Central Arizona Project (CAP). The EIS was supported by 23 technical reports that covered planning, design, public involvement, social and environmental impact assessment, economics, and hydrological analysis. Since the proposed transmission system differs only slightly from that described in the EIS, Western incorporates by reference the EIS and its 23 supporting technical reports into this environmental assessment (EA). In August 1985, BuRec completed an EA on modifications to the New Waddell Dam Project design plans and issued a FONSI on these modifications; the EA did not cover the transmission line. The purpose of this EA is to document the potential environmental effects of the proposed construction of the transmission line and switchyards in order to determine if an EIS is needed or if a finding of no significant impact (FONSI) is indicated. 28 refs., 5 figs., 1 tab.

  8. Overview of vegetation monitoring data, 1952--1983. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Duncan, J.P.

    1994-03-01

    This report is a result of the Hanford Environmental Dose Reconstruction (HEDR) Project. The goal of the HEDR Project is to estimate the radiation dose that individuals could have received from emissions since 1944 at the Hanford Site near Richland, Washington. Members of the HEDR Project`s Environmental Monitoring Data Task have developed databases of historical environmental measurements of such emissions. The HEDR Project is conducted by Battelle, Pacific Northwest Laboratories. This report is the third in a series that documents the information available on measurements of iodine-131 concentrations in vegetation. The first two reports provide the data for 1945--1951. This report provides an overview of the historical documents, which contain vegetation data for 1952--1983. The overview is organized according to the documents available for any given year. Each section, covering one year, contains a discussion of the media sampled, the sampling locations, significant events if there were any, emission quantities, constituents measured, and a list of the documents with complete reference information. Because the emissions which affected vegetation were significantly less after 1951, the vegetation monitoring data after that date have not been used in the HEDR Project. However, access to these data may be of interest to the public. This overview is, therefore, being published.

  9. Proposed Tenaska Washington II Generation Project : Final Environmental Impact Statement. Volume 1: Environmental Analysis and Technical Appendices.

    SciTech Connect

    United States. Bonneville Power Administration.

    1994-01-01

    BPA is considering whether to purchase electrical power from a proposed privately-owned combustion-turbine electrical generation plant in Washington. The plant would be fired by natural gas and would use combined-cycle technology to generate 240 average megawatts (aMW) of energy. The plant would be developed, owned, and operated by Tenaska Washington Partners II, L.P. The project would be located about 19 kilometers (12 miles) southeast of downtown Tacoma in the Frederickson Industrial Area, Pierce County. The proposed plant would occupy about half of a 6.4-hectare (16-acre) parcel and would be consistent with the industrial character of its surroundings. The proposed site is currently undeveloped and zoned for industrial use by the county. Main environmental concerns identified in the scoping process and in comments on the Draft Environmental Impact Statement (EIS) include: (1) potential air quality impacts, such as emissions and their contribution to the {open_quotes}greenhouse{close_quotes} effect; (2) potential health and safety impacts, such as nuisance odors, plant safety, visibility and heat-emission systems which may affect low-flying planes and potential health effects of electric and magnetic fields; and (3) potential water quality and quantity impacts, such as the amount of wastewater to be discharged, the source and amount of water required for plant operation. These and other issues are discussed in detail in the EIS. The proposed project already includes many features designed to reduce environmental impacts. Based on investigations performed for the EIS, no significant unavoidable adverse environmental impacts associated with the proposed project were identified, and no evidence emerged to suggest that the proposed action is controversial. The EIS is being mailed to numerous agencies, groups, and individuals (see Section 8.0). There will be a 30-day no-action period before any decisions are made and the Record of Decision is signed.

  10. GENII: The Hanford Environmental Radiation Dosimetry Software System: Volume 2, Users' manual: Hanford Environmental Dosimetry Upgrade Project

    SciTech Connect

    Napier, B.A.; Peloquin, R.A.; Strenge, D.L.; Ramsdell, J.V.

    1988-11-01

    The Hanford Environmental Dosimetry Upgrade Project was undertaken to incorporate the internal dosimetry models recommended by the International Commission on Radiological Protection (ICRP) in updated versions of the environmental pathway analysis models used at Hanford. The resulting second generation of Hanford environmental dosimetry computer codes is compiled in the Hanford Environmental Dosimetry System (Generation II, or GENII). The purpose of this coupled system of computer codes is to analyze environmental contamination of, air, water, or soil. This is accomplished by calculating radiation doses to individuals or populations. GENII is described in three volumes of documentation. This second volume is a Users' Manual, providing code structure, users' instructions, required system configurations, and QA-related topics. The first volume describes the theoretical considerations of the system. The third volume is a Code Maintenance Manual for the user who requires knowledge of code detail. It includes logic diagrams, global dictionary, worksheets, example hand calculations, and listings of the code and its associated data libraries. 27 refs., 17 figs., 23 tabs.

  11. GENII (Generation II): The Hanford Environmental Radiation Dosimetry Software System: Volume 3, Code maintenance manual: Hanford Environmental Dosimetry Upgrade Project

    SciTech Connect

    Napier, B.A.; Peloquin, R.A.; Strenge, D.L.; Ramsdell, J.V.

    1988-09-01

    The Hanford Environmental Dosimetry Upgrade Project was undertaken to incorporate the internal dosimetry models recommended by the International Commission on Radiological Protection (ICRP) in updated versions of the environmental pathway analysis models used at Hanford. The resulting second generation of Hanford environmental dosimetry computer codes is compiled in the Hanford Environmental Dosimetry System (Generation II, or GENII). This coupled system of computer codes is intended for analysis of environmental contamination resulting from acute or chronic releases to, or initial contamination of, air, water, or soil, on through the calculation of radiation doses to individuals or populations. GENII is described in three volumes of documentation. This volume is a Code Maintenance Manual for the serious user, including code logic diagrams, global dictionary, worksheets to assist with hand calculations, and listings of the code and its associated data libraries. The first volume describes the theoretical considerations of the system. The second volume is a Users' Manual, providing code structure, users' instructions, required system configurations, and QA-related topics. 7 figs., 5 tabs.

  12. The new environmental ethics as the basis of ecosystems stability, quality of life and culture

    SciTech Connect

    Bourodimos, E.L. )

    1991-01-01

    This paper reports that the components for the quality of life pursuit and realization in modern times may be: Practical measures to control pollutions and prevent degradation and disruption in the ecosystem, i.e., an overall strategy of technological advancement in environmental sciences, management and sanitary engineering, aimed at the improvement of the environment and sustaining life and development, and; Theoretical considerations of the ecological theory and the intrinsic values in nature; its richness, stability and diversity. These values-reverence for life - are not entirely independent of the usefulness of the non-human world (ecosystems, rivers, landscapes, lakes, watersheds, oceans, forests, clean air and water in the biosphere) nor irrelevant to practical measures.

  13. Environmental Education Project for Developing Supersphere Characters in Children's Books

    NASA Astrophysics Data System (ADS)

    Vasconcelos, G. F.

    2014-12-01

    To raise awareness and provide basic knowledge about the environment, three children's books have been created to explain, in a simplified language, the basic processes of formation of the Earth, the origin of the universe, the planets and the moon, volcanism, rock formation and the appearance of water, the earliest life forms and their evolution and the main elements of Earth. These phenomena are represented through the main characters who are super heroes or designated Superspheres, such as Hydrosphere (water), Lithosphere (rocks), Biosphere (Polite, a stromatolite and Sarite, the mineral dolomite), Atmosphere (air), which are the 4 components of the Earth System, and the Pyrosphere(fire), which supplies the energy to drive the Earth System through volcanic activity. The characters have each developed super powers that evolved over geological time as they are transformed. They are the basic elements of nature and appear in a specific chronological order. With the emergence of ancient life in the seas, the Biosphere begins to use the energy of the sun, through of the photosynthetic activity of stromatolites, one of the friends of the superheroes, to produce the oxygen for the Atmosphere. Over a vast period of time, the evolution of life continues with the formation of the supercontinent Gondwana. With the arrival of man and his interaction with the Earth, the villain appears in the book as the "Homo incorrectus" (incorrect man), who abuses and tries to destroy the super heroes, the "Superspheres". The importance of these characters for the living Earth is emphasized, creating a connection between children and the characters. The aim of the story is to create a greater ecological conscience in the children and showing them that they should be helping to save the "Superspheres", who are in danger and need to be preserved. Projects for primary schools in the State of Rio de Janeiro have been designed and implemented around these characters, focusing on the rescue of

  14. FY 1992 revised task plans for the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Shipler, D.B.

    1992-04-01

    The purpose of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate radiation doses from Hanford Site operations since 1944 to populations and individuals. The primary objectives of work to be performed in FY 1992 is to determine the appropriate scope (space, time, and radionuclides, pathways and individuals/population groups) and accuracy (level of uncertainty in dose estimates) for the project. Another objective is to use a refined computer model to estimate Native American tribal doses and individual doses for the Hanford Thyroid Disease Study (HTDS). Project scope and accuracy requirements defined in FY 1992 can translated into model and data requirements that must be satisfied during FY 1993.

  15. FY 1992 revised task plans for the Hanford Environmental Dose Reconstruction Project. Revision 1

    SciTech Connect

    Shipler, D.B.

    1992-04-01

    The purpose of the Hanford Environmental Dose Reconstruction (HEDR) Project is to estimate radiation doses from Hanford Site operations since 1944 to populations and individuals. The primary objectives of work to be performed in FY 1992 is to determine the appropriate scope (space, time, and radionuclides, pathways and individuals/population groups) and accuracy (level of uncertainty in dose estimates) for the project. Another objective is to use a refined computer model to estimate Native American tribal doses and individual doses for the Hanford Thyroid Disease Study (HTDS). Project scope and accuracy requirements defined in FY 1992 can translated into model and data requirements that must be satisfied during FY 1993.

  16. Genetic and Environmental Contributions to Personality Trait Stability and Change Across Adolescence: Results From a Japanese Twin Sample.

    PubMed

    Kawamoto, Tetsuya; Endo, Toshihiko

    2015-10-01

    We examined developmental trends and sources of stability and change in adolescent personality by using twin data collected from 1981 to 2010 (273 monozygotic (MZ) and 48 dizygotic (DZ) twin pairs) from a secondary school affiliated with the University of Tokyo. Phenotypic analyses showed high rank-order stability and substantial mean-level increases in neuroticism and declines in extraversion over the adolescent years. Longitudinal bivariate genetic analyses revealed that the best-fitting model for adolescent personality includes additive genetic and non-shared environmental influences. Heritability estimates ranged approximately from 0.30 to 0.60. Additionally, three-year stability in adolescent personality was influenced mainly by genetic factors, and there were both genetic and environmental innovations in mid-adolescence. Our findings suggest that both genetic and environmental effects have significant roles in the etiology of personality development across adolescence.

  17. Phase Stability and Thermal Conductivity of Composite Environmental Barrier Coatings on SiC/SiC Ceramic Matrix Composites

    NASA Technical Reports Server (NTRS)

    Benkel, Samantha; Zhu, Dongming

    2011-01-01

    Advanced environmental barrier coatings are being developed to protect SiC/SiC ceramic matrix composites in harsh combustion environments. The current coating development emphasis has been placed on the significantly improved cyclic durability and combustion environment stability in high-heat-flux and high velocity gas turbine engine environments. Environmental barrier coating systems based on hafnia (HfO2) and ytterbium silicate, HfO2-Si nano-composite bond coat systems have been processed and their stability and thermal conductivity behavior have been evaluated in simulated turbine environments. The incorporation of Silicon Carbide Nanotubes (SiCNT) into high stability (HfO2) and/or HfO2-silicon composite bond coats, along with ZrO2, HfO2 and rare earth silicate composite top coat systems, showed promise as excellent environmental barriers to protect the SiC/SiC ceramic matrix composites.

  18. Energy and environmental research emphasizing low-rank coal -- Task 5.1, Stability issues

    SciTech Connect

    Anderson, C.M.; Musich, M.A.; Dewall, R.A.; Richter, J.J.

    1995-04-01

    Low-sulfur subbituminous and lignite coals have high moisture content and, consequently, low heating value, leading to boiler derating in US midwestern and eastern utilities as well as switching and/or blending coals to achieve SO{sub 2} compliance. In the drive to develop cost-effective coal-drying processes, coal developers have focused on heat content of the products and generally neglected the critical stability issues of friability and dusting, moisture reabsorption, and spontaneous heating. The Energy and Environmental Research Center (EERC), in an effort to establish new standards for dried products, has used established methods and has developed new ones to evaluate the propensity of lump western coals, raw and dried, to produce dust and absorb water. Three drying methods--air, hydrothermal, and saturated steam--were used to generate low-moisture upgraded products. New indices for dust generation and friability were determined to assess the effects of moisture removal and upgrading methodology on coal stability. Analysis of the dried coals using various strength tests indicated that the reduction in moisture made the lump coal unstable, yielding substantially higher dust and friability indices relative to those of the raw coals.

  19. 78 FR 2685 - Central Utah Project Completion Act; East Hobble Creek Restoration Project Draft Environmental...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-01-14

    ... effects of a proposed restoration effort on a portion of Lower Hobble Creek, near Springville, Utah. DATES... anticipated environmental effects of a proposed restoration effort on a portion of lower Hobble Creek, near Springville, Utah. This restoration effort is intended to facilitate the recovery of the June sucker,...

  20. Inventory of current environmental monitoring projects in the US-Canadian transboundary region

    SciTech Connect

    Glantz, C.S.; Ballinger, M.Y.; Chapman, E.G.

    1986-05-01

    This document presents the results of a study commissioned to survey and summarize major environmental monitoring projects in the US-Canadian transboundary region. Projects with field sites located within 400 km (250 mi) of the border and active after 1980 were reviewed. The types of projects included: ambient air-quality monitoring, ambient water-quality monitoring, deposition monitoring, forest/vegetation monitoring and research, soil studies, and ecosystem studies. Ecosystem studies included projects involving the measurement of parameters from more than one monitoring category (e.g., studies that measured both water and soil chemistry). Individual descriptions were formulated for 184 projects meeting the spatial and temporal criteria. Descriptions included the official title for the project, its common abbreviation, program emphasis, monitoring site locations, time period conducted, parameters measured, protocols employed, frequency of sample collection, data storage information, and the principal contact for the project. A summary inventory subdivided according to the six monitoring categories was prepared using a computerized data management system. Information on major centralized data bases in the field of environmental monitoring was also obtained, and summary descriptions were prepared. The inventory and data base descriptions are presented in appendices to this document.

  1. Environmental projects. Volume 6: Environmental assessment. New 34-meter antenna at Venus site

    NASA Technical Reports Server (NTRS)

    Kushner, L.

    1988-01-01

    The Jet Propulsion Lab has proposed replacing the 26-meter antenna at the Venus Station of the Goldstone Deep Space Communications Complex with a new 34-meter antenna. An environmental impact assessment of this proposed change is presented. It is concluded that the proposed antenna and its operation would not result in significant adverse impacts to the physical or human environment. It will, however, be necessary to manage electromagnetic transmissions from the antenna in such a manner as to ensure safe operation.

  2. Sulimar Queen environmental restoration project closure package Sandia environmental stewardship exemplar.

    SciTech Connect

    Tillman, Jack B.

    2008-09-01

    In March 2008, Sandia National Laboratories (Sandia), in partnership with the Bureau of Land Management, Roswell Field Office, completed its responsibilities to plug and abandon wells and restore the surface conditions for the Sulimar Queens Unit, a 2,500 acre oil field, in Chaves County, Southeast New Mexico. Sandia assumed this liability in an agreement to obtain property to create a field laboratory to perform extensive testing and experimentation on enhanced oil recovery techniques for shallow oil fields. In addition to plugging and abandoning 28 wells, the project included the removal of surface structures and surface reclamation of disturbed lands associated with all plugged and abandoned wells, access roads, and other auxiliary facilities within unit boundaries. A contracting strategy was implemented to mitigate risk and reduce cost. As the unit is an important wildlife habitat for prairie chickens, sand dune lizards, and mule deer, the criteria for the restoration and construction process were designed to protect and enhance the wildlife habitat. Lessons learned from this project include: (1) extreme caution should be exercised when entering agreements that include future liabilities, (2) partnering with the regulator has huge benefits, and (3) working with industry experts, who were familiar with the work, and subcontractors, who provided the network to complete the project cost effectively.

  3. Clay Components in Soil Dictate Environmental Stability and Bioavailability of Cervid Prions in Mice

    PubMed Central

    Wyckoff, A. Christy; Kane, Sarah; Lockwood, Krista; Seligman, Jeff; Michel, Brady; Hill, Dana; Ortega, Aimee; Mangalea, Mihnea R.; Telling, Glenn C.; Miller, Michael W.; Vercauteren, Kurt; Zabel, Mark D.

    2016-01-01

    Chronic wasting disease (CWD) affects cervids and is the only known prion disease to affect free-ranging wildlife populations. CWD spread continues unabated, and exact mechanisms of its seemingly facile spread among deer and elk across landscapes in North America remain elusive. Here we confirm that naturally contaminated soil contains infectious CWD prions that can be transmitted to susceptible model organisms. We show that smectite clay content of soil potentiates prion binding capacity of different soil types from CWD endemic and non-endemic areas, likely contributing to environmental stability of bound prions. The smectite clay montmorillonite (Mte) increased prion retention and bioavailability in vivo. Trafficking experiments in live animals fed bound and unbound prions showed that mice retained significantly more Mte-bound than unbound prions. Mte promoted rapid uptake of prions from the stomach to the intestines via enterocytes and M cells, and then to macrophages and eventually CD21+ B cells in Peyer's patches and spleens. These results confirm clay components in soil as an important vector in CWD transmission at both environmental and organismal levels. PMID:27933048

  4. Notification: Background Investigation Services Project Notification US Virgin Islands Environmental Program Evaluation

    EPA Pesticide Factsheets

    Projects #OPE-FY14-0004, OPE-FY14-0005 and OPE-FY14-0006, October 30, 2013. The EPA OIG plans to begin preliminary research on October 30, 2013 into the environmental programs the US Virgin Islands (USVI) has implemented on EPA’s behalf.

  5. Radionuclide releases to the atmosphere from Hanford Operations, 1944--1972. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Heeb, C.M.

    1994-05-01

    The purpose of the Hanford Environmental Dose Reconstruction Project is to estimate the radiation dose that individuals could have received as a result of radionuclide emissions since 1944 from the Hanford Site. The first step in determining dose is to estimate the amount and timing of radionuclide releases to air and water. This report provides the air release information.

  6. Environmental Assessment of Ground Water Compliance at the Durango, Colorado, UMTRA Project Site

    SciTech Connect

    N /A

    2002-11-29

    The U.S. Department of Energy (DOE) is proposing a ground water compliance strategy for the Uranium Mill Tailings Remedial Action (UMTRA) Project site near Durango, Colorado. DOE has prepared this environmental assessment to provide the public with information concerning the potential effects of this proposed strategy.

  7. 75 FR 44805 - Central Utah Project Completion Act; Notice of Availability, Draft Environmental Assessment...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-07-29

    ... Central Utah Project Completion Act; Notice of Availability, Draft Environmental Assessment (Draft EA... EA)--Realignment of a Portion of the Utah Lake Drainage Basin Water Delivery System. SUMMARY... risk to the pipeline associated with geologic faults. DATES: Submit written comments on the Draft EA...

  8. 77 FR 67662 - Notice of Availability of the Desert Harvest Solar Project Final Environmental Impact Statement...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2012-11-13

    ... Bureau of Land Management Notice of Availability of the Desert Harvest Solar Project Final Environmental Impact Statement, Riverside County, CA and the Proposed California Desert Conservation Area Plan... 1976, as amended, the Bureau of Land Management (BLM) has prepared a Proposed California...

  9. Environmental Education. Nevada Competency-Based Adult High School Diploma Project.

    ERIC Educational Resources Information Center

    Nevada Univ., Las Vegas. Coll. of Education.

    This document is one of ten curriculum guides developed by the Nevada Competency-Based Adult High School Diploma (CBAHSD) Project. This curriculum guide on environmental education is divided into seven topics. The topics included are Human Carrying Capacity (The Ability to Foresee and Forestall), Human Population Growth, The Atmosphere, The…

  10. Evaluation of an Action-Research Project by University Environmental Volunteers

    ERIC Educational Resources Information Center

    Raimondo, Ana Maria; Monti, Alejandro J. A.; Perales-Palacios, F. Javier; Gutiérrez-Pérez, José

    2017-01-01

    The university volunteer programs in Argentina encourage entrepreneurship culture through the development of innovative socio-environmental projects that promote a joint effort between the different administrations of the State, the universities and regional social organizations. One, called "environment and social inclusion" has been…

  11. The Student Team Project: A Long-Term Cooperative Strategy in Graduate Environmental Studies.

    ERIC Educational Resources Information Center

    Sherman, Lawrence W.; Woy-Hazleton, Sandra

    A year-long, cooperatively structured, student team strategy is described that is being used as a major component in an interdisciplinary Master of Environmental Science degree program. The general philosophy of the degree program and the rationale for including the Student Team Project (STP) are described. The most basic goal of the program is…

  12. A Service-Learning Project in Chemistry: Environmental Monitoring of a Nature Preserve

    ERIC Educational Resources Information Center

    Kammler, David C.; Truong, Triet M.; VanNess, Garrett; McGowin, Audrey E.

    2012-01-01

    A collaborative environmental service-learning project was implemented between upper-level undergraduate science majors and graduate chemistry students at a large state school and first-year students at a small private liberal arts college. Students analyzed the water quality in a nature preserve by determining the quantities of 12 trace metals,…

  13. Environmentally Sound Small-Scale Agricultural Projects: Guidelines for Planning. Revised Edition.

    ERIC Educational Resources Information Center

    Altieri, Miguel; Vukasin, Helen L., Ed.

    Environmental planning requires more than finding the right technology and a source of funds. Planning involves consideration of the social, cultural, economic, and natural environments in which the project occurs. The challenge is to develop sustainable food systems that have reasonable production but do not degrade the resource base and upset…

  14. Collaborative Projects Increase Student Learning Outcome Performance in Nonmajors Environmental Science Course

    ERIC Educational Resources Information Center

    Chace, Jameson F.

    2014-01-01

    Between 2007 and 2010, three types of semester research projects were assigned in BIO 140 Humans and Their Environment, a nonmajors introductory course at Salve Regina University. Specific environmental impact-type assessments were used to foster scientific inquiry and achieve higher scientific literacy. Quantitative and qualitative measurements…

  15. Leaders of Sustainable Development Projects: Resources Used and Lessons Learned in a Context of Environmental Education?

    ERIC Educational Resources Information Center

    Pruneau, Diane; Lang, Mathieu; Kerry, Jackie; Fortin, Guillaume; Langis, Joanne; Liboiron, Linda

    2014-01-01

    In our day, leaders involved in ingenious sustainable development projects plan spaces and implement practices that are beneficial to the environment. These initiatives represent a fertile source of information on the competences linked to environmental design that we should nurture in our students. In view of improving our understanding of the…

  16. 78 FR 25258 - Notice of Availability (NOA) for Sharpe Permit Relinquishment Project Environmental Assessment

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-04-30

    ... of the Secretary Notice of Availability (NOA) for Sharpe Permit Relinquishment Project Environmental Assessment AGENCY: Defense Logistics Agency, DoD. ACTION: Notice of Availability (NOA) for Sharpe Permit... end 30 days after publication of this NOA in the Federal Register. Comments received by the end of...

  17. Taking Action: An Educator's Guide to Involving Students in Environmental Action Projects.

    ERIC Educational Resources Information Center

    Stoner, Darlene K.; And Others

    The goal of Project WILD, a K-12 interdisciplinary conservation and environmental education program emphasizing wildlife, is to assist learners of any age in developing awareness, knowledge, skills, and commitment resulting in informed decisions, responsible behavior, and constructive actions concerning wildlife and the environment. The purpose of…

  18. Interdisciplinary Project-Based Learning through an Environmental Water Quality Study

    NASA Astrophysics Data System (ADS)

    Juhl, Lorie; Yearsley, Kaye; Silva, Andrew J.

    1997-12-01

    An interdisciplinary environmental water quality study was designed and conducted to enhance training and employability of chemical and environmental technician students in associate degree programs. Four project objectives were identified as a means to enhance the educational experience and employability of our students: provide experience on analytical instrumentation for organic compounds (gas chromatography/mass spectrometry, GC/MS), require interdisciplinary group interactions and problem solving, provide experience with Environmental Protection Agency (EPA) procedures, and require cooperation with state agencies/private organizations. Students worked in groups that included representatives from both programs to develop project objectives and a Sampling and Analysis Plan (SAP) following EPA standards. Input from personnel at Idaho's Department of Environmental Quality and Bureau of Laboratories and from volunteers in an environmental "watch dog" organization called the Henry's Fork Foundation aided students in the development and implementation of their SAP. Subsequently, groups sampled sections of the Henry's Fork River and analyzed for organic, inorganic, and fecal contaminants. Analysis included EPA method 525.2 for pesticides using GC/MS. Data from all river segments was shared and each group submitted a final report analyzing results. Surveys completed by students and instructors indicate that the project is a successful teaching method allowing introduction of new skills as well as review of important technical and employability skills.

  19. Environmental change and water-related, vector borne diseases in eastern Africa: the HEALTHY FUTURES project

    NASA Astrophysics Data System (ADS)

    Taylor, David; Kienberger, Stefan; Tompkins, Adrian

    2015-04-01

    Pathogens that spend time outside the human body, and any organisms involved in their transmission, have particular ecological requirements; as environment, including climate, conditions change, then the transmission characteristics of associated pathogens - and the diseases caused - are also likely to vary. Relationships between environment and health in many parts of the world remain poorly studied and are often overlooked, however. This is particularly the case in developing countries, because of budgetary and available expertise constraints. Moreover the relationship is often confounded by other factors. These other factors contribute to human vulnerability, and thus to the overall disease risk due to environmental change. This presentation will highlight the importance of environmental, including climate, change information to a better understanding of the risks to health of projected future environmental changes, and to the more efficient and effective use of scarce health resources in the developing world. The paper will focus on eastern Africa, and in particular the health effects of future projected environmental change impacts on water-related, vector borne diseases in the East African Community region. Moreover the paper will highlight how the EU FP7-funded project HEALTHY FUTURES is, through a broadly-based, integrative approach that distinguishes environmental change-induced health hazard from health risk aims to support the health decisions making process, thereby attempting to help mitigate negative health impacts.

  20. A synthesis of environmental and recreational mitigation requirements at hydropower projects in the United States

    SciTech Connect

    Schramm, Michael P.; Bevelhimer, Mark S.; DeRolph, Chris R.

    2016-04-11

    Environmental mitigation plays an important role in the environmentally sustainable development of hydropower resources. However, comprehensive data on mitigation required by the Federal Energy Regulatory Commission (FERC) at United States (US) hydropower projects is lacking. Therefore, our objective was to create a comprehensive database of mitigation required at non-federal hydropower projects and provide a synthesis of available mitigation data. Mitigation data was collated for over 300 plants licensed or relicensed from 1998 through 2013. We observed that the majority of FERC mitigation requirements deal with either hydrologic flows or recreation and that hydropower plants in the Pacific Northwest had the highest number of requirements. Our data indicate opportunities exist to further explore hydropower mitigation in the areas of environmental flows, fish passage, and water quality. Lastly, connecting these data with ecological outcomes, actual flow data, and larger landscape level information will be necessary to evaluate the effectiveness of mitigation and ultimately inform regulators, managers, and planners.

  1. Supplement analysis 2 of environmental impacts resulting from modifications in the West Valley Demonstration Project

    SciTech Connect

    1998-06-23

    The West Valley Demonstration Project, located in western New York, has approximately 600,000 gallons of liquid high-level radioactive waste (HLW) in storage in underground tanks. While corrosion analysis has revealed that only limited tank degradation has taken place, the failure of these tanks could release HLW to the environment. Congress requires DOE to demonstrate the technology for removal and solidification of HLW. DOE issued the Final Environmental Impact Statement (FEIS) in 1982. The purpose of this second supplement analysis is to re-assess the 1982 Final Environmental Impact Statement's continued adequacy. This report provides the necessary and appropriate data for DOE to determine whether the environmental impacts presented by the ongoing refinements in the design, process, and operations of the Project are considered sufficiently bounded within the envelope of impacts presented in the FEIS and supporting documentation.

  2. Resumption of thermal stabilization of plutonium oxide in Building 707, Rocky Flats Plant, Golden, Colorado. Environmental Assessment

    SciTech Connect

    Not Available

    1994-02-01

    The Department of Energy is proposing thermal stabilization to enhance the safe storage of plutonium at Rocky Flats Plant until decisions are made on long-term storage and disposition of the material. The proposed action is to resume thermal stabilization of pyrophoric plutonium in Building 707 at Rocky Flats Plant. Thermal stabilization would heat the pyrophoric plutonium under controlled conditions in a glovebox furnace to promote full oxidation and convert the material into stable plutonium oxide in the form of PuO{sub 2}. Other activities associated with thermal stabilization would include post-stabilization characterization of non-pyrophoric plutonium and on-site movement of pyrophoric and non-pyrophoric plutonium. This report covers; purpose and need; proposed action; alternatives to the proposed action; affected environment; environmental effects of proposed action and no action alternative; agencies and person consulted; and public participation.

  3. Chicago Clean Air, Clean Water Project: Environmental Monitoring for a Healthy, Sustainable Urban Future

    SciTech Connect

    none, none; Tuchman, Nancy

    2015-11-11

    The U.S. Department of Energy awarded Loyola University Chicago and the Institute of Environmental Sustainability (IES) $486,000.00 for the proposal entitled “Chicago clean air, clean water project: Environmental monitoring for a healthy, sustainable urban future.” The project supported the purchase of analytical instruments for the development of an environmental analytical laboratory. The analytical laboratory is designed to support the testing of field water and soil samples for nutrients, industrial pollutants, heavy metals, and agricultural toxins, with special emphasis on testing Chicago regional soils and water affected by coal-based industry. Since the award was made in 2010, the IES has been launched (fall 2013), and the IES acquired a new state-of-the-art research and education facility on Loyola University Chicago’s Lakeshore campus. Two labs were included in the research and education facility. The second floor lab is the Ecology Laboratory where lab experiments and analyses are conducted on soil, plant, and water samples. The third floor lab is the Environmental Toxicology Lab where lab experiments on environmental toxins are conducted, as well as analytical tests conducted on water, soil, and plants. On the south end of the Environmental Toxicology Lab is the analytical instrumentation collection purchased from the present DOE grant, which is overseen by a full time Analytical Chemist (hired January 2016), who maintains the instruments, conducts analyses on samples, and helps to train faculty and undergraduate and graduate student researchers.

  4. West Valley Demonstration Project site environmental report for calendar year 1996

    SciTech Connect

    1997-06-01

    The West Valley Demonstration Project (WVDP), the site of a US Department of Energy environmental cleanup activity operated by West Valley Nuclear Services Co., Inc., (WVNS), is in the process of solidifying liquid high-level radioactive waste remaining at the site after commercial nuclear fuel reprocessing was discontinued. The Project is located in Western New York State, about 30 miles south of Buffalo, within the New York State-owned Western New York Nuclear Service Center (WNYNSC). This report represents a single, comprehensive source of off-site and on-site environmental monitoring data collected during 1996 by environmental monitoring personnel. The environmental monitoring program and results are discussed in the body of this report. The monitoring data are presented in the appendices. Appendix A is a summary of the site environmental monitoring schedule. Appendix B lists the environmental permits and regulations pertaining to the WVDP. Appendices C through F contain summaries of data obtained during 1996 and are intended for those interested in more detail than is provided in the main body of the report.

  5. Norfolk Southern boxcar blocking/bracing plan for the mixed waste disposal initiative project. Environmental Restoration Program

    SciTech Connect

    Seigler, R.S.

    1994-01-01

    The US Department of Energy`s (DOE) Environmental Restoration and Waste Management programs will dispose of mixed waste no longer deemed useful. This project is one of the initial activities used to help meet this goal. The project will transport the {approximately}46,000 drums of existing stabilized mixed waste located at the Oak Ridge K-25 Site and presently stored in the K-31 and K-33 buildings to an off-site commercially licensed and permitted mixed waste disposal facility. Shipping and disposal of all {approximately}46,000 pond waste drums ({approximately}1,000,000 ft{sup 3} or 55,000 tons) is scheduled to occur over a period of {approximately}5--10 years. The first shipment of stabilized pond waste should transpire some time during the second quarter of FY 1994. Martin Marietta Energy Systems, Inc., proposes to line each of the Norfolk Southem boxcars with a prefabricated, white, 15-mm low-density polyethylene (LDPE) liner material. To avoid damaging the bottom of the polyethylene floor liner, a minimum .5 in. plywood will be nailed to the boxcars` nailable metal floor. At the end of the Mixed Waste Disposal Initiative (MWDI) Project workers at the Envirocare facility will dismantle and dispose of all the polyethylene liner and plywood materials. Envirocare of Utah, Inc., located in Clive, Utah, will perform a health physic survey and chemically and radiologically decontaminate, if necessary, each of the rail boxcars prior to them being released back to Energy Systems. Energy Systems will also perform a health physic survey and chemically and radiologically decontaminate, if necessary, each of the rail boxcars prior to them being released back to Norfolk Southem Railroad.

  6. KSTAR equilibrium operating space and projected stabilization at high normalized beta

    NASA Astrophysics Data System (ADS)

    Park, Y. S.; Sabbagh, S. A.; Berkery, J. W.; Bialek, J. M.; Jeon, Y. M.; Hahn, S. H.; Eidietis, N.; Evans, T. E.; Yoon, S. W.; Ahn, J.-W.; Kim, J.; Yang, H. L.; You, K.-I.; Bae, Y. S.; Chung, J.; Kwon, M.; Oh, Y. K.; Kim, W.-C.; Kim, J. Y.; Lee, S. G.; Park, H. K.; Reimerdes, H.; Leuer, J.; Walker, M.

    2011-05-01

    Along with an expanded evaluation of the equilibrium operating space of the Korea Superconducting Tokamak Advanced Research, KSTAR, experimental equilibria of the most recent plasma discharges were reconstructed using the EFIT code. In near-circular plasmas created in 2009, equilibria reached a stored energy of 54 kJ with a maximum plasma current of 0.34 MA. Highly shaped plasmas with near double-null configuration in 2010 achieved H-mode with clear edge localized mode (ELM) activity, and transiently reached a stored energy of up to 257 kJ, elongation of 1.96 and normalized beta of 1.3. The plasma current reached 0.7 MA. Projecting active and passive stabilization of global MHD instabilities for operation above the ideal no-wall beta limit using the designed control hardware was also considered. Kinetic modification of the ideal MHD n = 1 stability criterion was computed by the MISK code on KSTAR theoretical equilibria with a plasma current of 2 MA, internal inductance of 0.7 and normalized beta of 4.0 with simple density, temperature and rotation profiles. The steep edge pressure gradient of this equilibrium resulted in the need for significant plasma toroidal rotation to allow thermal particle kinetic resonances to stabilize the resistive wall mode (RWM). The impact of various materials and electrical connections of the passive stabilizing plates on RWM growth rates was analysed, and copper plates reduced the RWM passive growth rate by a factor of 15 compared with stainless steel plates at a normalized beta of 4.4. Computations of active RWM control using the VALEN code showed that the n = 1 mode can be stabilized at normalized beta near the ideal wall limit via control fields produced by the midplane in-vessel control coils (IVCCs) with as low as 0.83 kW control power using ideal control system assumptions. The ELM mitigation potential of the IVCC, examined by evaluating the vacuum island overlap created by resonant magnetic perturbations, was analysed using the

  7. KSTAR Equilibrium Operating Space and Projected Stabilization at High Normalized Beta

    SciTech Connect

    Park, Y. S.; Sabbagh, S. A.; Berkery, J.W.; Bialek, J.; Jeon, Y. M.; Hahn, S. H.; Eidietis, N. W.; Evans, T. E.; Yoon, S. W.; Ahn, Joonwook; Kim, J.; Yang, H. L.; You, K. I.; Soukhanovskii, V. A.; Bae, Y. S.; Chung, J. I.; Kwon, M.; Oh, Y. K.; Kim, W. C.; Kim, J. Y.; Lee, S. G.; Park, H.; Reimerdes, H.; Leuer, J. A.; Walker, M. L.

    2011-01-01

    Along with an expanded evaluation of the equilibrium operating space of the Korea Superconducting Tokamak Advanced Research, KSTAR, experimental equilibria of the most recent plasma discharges were reconstructed using the EFIT code. In near-circular plasmas created in 2009, equilibria reached a stored energy of 54 kJ with a maximum plasma current of 0.34 MA. Highly shaped plasmas with near double-null configuration in 2010 achieved H-mode with clear edge localized mode (ELM) activity, and transiently reached a stored energy of up to 257 kJ, elongation of 1.96 and normalized beta of 1.3. The plasma current reached 0.7 MA. Projecting active and passive stabilization of global MHD instabilities for operation above the ideal no-wall beta limit using the designed control hardware was also considered. Kinetic modification of the ideal MHD n = 1 stability criterion was computed by the MISK code on KSTAR theoretical equilibria with a plasma current of 2 MA, internal inductance of 0.7 and normalized beta of 4.0 with simple density, temperature and rotation profiles. The steep edge pressure gradient of this equilibrium resulted in the need for significant plasma toroidal rotation to allow thermal particle kinetic resonances to stabilize the resistive wall mode (RWM). The impact of various materials and electrical connections of the passive stabilizing plates on RWM growth rates was analysed, and copper plates reduced the RWM passive growth rate by a factor of 15 compared with stainless steel plates at a normalized beta of 4.4. Computations of active RWM control using the VALEN code showed that the n = 1 mode can be stabilized at normalized beta near the ideal wall limit via control fields produced by the midplane in-vessel control coils (IVCCs) with as low as 0.83kW control power using ideal control system assumptions. The ELM mitigation potential of the IVCC, examined by evaluating the vacuum island overlap created by resonant magnetic perturbations, was analysed using the

  8. Final programmatic environmental impact statement for the uranium mill tailings remedial action ground water project. Volume I

    SciTech Connect

    1996-10-01

    This programmatic environmental impact statement (PElS) was prepared for the Uranium Mill Tailings Remedial Action (UMTRA) Ground Water Project to comply with the National Environmental Policy Act (NEPA). This PElS provides an analysis of the potential impacts of the alternatives and ground water compliance strategies as well as potential cumulative impacts. On November 8, 1978, Congress enacted the Uranium Mill Tailings Radiation Control Act (UMTRCA) of 1978, Public Law, codified at 42 USC §7901 et seq. Congress found that uranium mill tailings " ... may pose a potential and significant radiation health hazard to the public, and that every reasonable effort should be made to provide for stabilization, disposal, and control in a safe, and environmentally sound manner of such tailings in order to prevent or minimize other environmental hazards from such tailings." Congress authorized the Secretary of Energy to designate inactive uranium processing sites for remedial action by the U.S. Department of Energy (DOE). Congress also directed the U.S. Environmental Protection Agency (EPA) to set the standards to be followed by the DOE for this process of stabilization, disposal, and control. On January 5, 1983, EPA published standards (40 CFR Part 192) for the disposal and cleanup of residual radioactive materials. On September 3, 1985, the U.S. Court of Appeals for the Tenth Circuit set aside and remanded to EPA the ground water provisions of the standards. The EPA proposed new standards to replace remanded sections and changed other sections of 40 CFR Part 192. These proposed standards were published in the Federal Register on September 24, 1987 (52 FR 36000). Section 108 of the UMTRCA requires that DOE comply with EPA's proposed standards in the absence of final standards. The Ground Water Project was planned under the proposed standards. On January 11, 1995, EPA published the final rule, with which the DOE must now comply. The PElS and the Ground Water Project are in

  9. Environmental projects. Volume 15: Environmental assessment: Proposed 1-megawatt radar transmitter at the Mars site

    NASA Technical Reports Server (NTRS)

    1992-01-01

    The Goldstone Deep Space Communications Complex (GDSCC), located in the Mojave Desert about 64.5 km (40 mi) north of Barstow, California. and about 258 km (160 mi) northeast of Pasadena, California, is part of the National Aeronautics and Space Administration's (NASA's) Deep Space Network (DSN), one of the world's larger and more sensitive scientific telecommunications and radio navigation networks. The Goldstone Complex is managed, technically directed, and operated for NASA by the Jet Propulsion Laboratory (JPL) of the California Institute of Technology in Pasadena, California. Activities at the GDSCC support the operation of six parabolic dish antennas located at five separate sites called Deep Space Stations (DSS's). Four sites, named Echo, Mars, Uranus, and Apollo, are operational for space missions, while the remaining Venus Site is devoted to research and development activities. The Mars Site at the GDSCC contains two antennas: the Uranus antenna (DSS 15, 34 m) and the Mars antenna (DSS 14, 70 m). This present volume deals solely with the DSS-14 Mars antenna. The Mars antenna not only can act as a sensitive receiver to detect signals from spacecraft, but it also can be used in radar astronomy as a powerful transmitter to send out signals to probe the solar system. At present, the Mars antenna operates as a continuous-wave microwave system at a frequency of 8.51 GHz at a power level of 0.5 MW. JPL has plans to upgrade the Mars antenna to a power level of 1 MW. Because of the anticipated increase in the ambient levels of radio frequency radiation (RFR), JPL retained Battelle Pacific Northwest Laboratories (BPNL), Richland, Washington, to conduct an environmental assessment with respect to this increased RFR. This present volume is a JPL-expanded version of the BPNL report titled Environmental Assessment of the Goldstone Solar System Radar, which was submitted to JPL in Nov. 1991. This BPNL report concluded that the operation of the upgraded Mars antenna at the

  10. Stability metrics for multi-source biomedical data based on simplicial projections from probability distribution distances.

    PubMed

    Sáez, Carlos; Robles, Montserrat; García-Gómez, Juan M

    2017-02-01

    Biomedical data may be composed of individuals generated from distinct, meaningful sources. Due to possible contextual biases in the processes that generate data, there may exist an undesirable and unexpected variability among the probability distribution functions (PDFs) of the source subsamples, which, when uncontrolled, may lead to inaccurate or unreproducible research results. Classical statistical methods may have difficulties to undercover such variabilities when dealing with multi-modal, multi-type, multi-variate data. This work proposes two metrics for the analysis of stability among multiple data sources, robust to the aforementioned conditions, and defined in the context of data quality assessment. Specifically, a global probabilistic deviation and a source probabilistic outlyingness metrics are proposed. The first provides a bounded degree of the global multi-source variability, designed as an estimator equivalent to the notion of normalized standard deviation of PDFs. The second provides a bounded degree of the dissimilarity of each source to a latent central distribution. The metrics are based on the projection of a simplex geometrical structure constructed from the Jensen-Shannon distances among the sources PDFs. The metrics have been evaluated and demonstrated their correct behaviour on a simulated benchmark and with real multi-source biomedical data using the UCI Heart Disease data set. The biomedical data quality assessment based on the proposed stability metrics may improve the efficiency and effectiveness of biomedical data exploitation and research.

  11. Seismic stability evaluation of Alben Barkley Lock and Dam Project. Volume 1. Summary report. Final report

    SciTech Connect

    Wahl, R.E.; Bluhm, P.F.

    1992-09-01

    This report summarizes the results of seismological, geological, laboratory, field, and analytical investigations conducted to evaluate the seismic stability of two earth embankment sections of the Alben Barkley Lock and Dam Project, Kentucky. These represent typical sections of the powerhouse/switch-yard area and the main embankment. Detailed documentation of each of the major topical areas of this study are contained in Volumes 2 through 5 of this series of reports. The design earthquake, from the New Madrid Seismic Zone, had a body-wave magnitude of 7.5. Of particular interest in this study, was the seismic performance of silty sands in the foundation and their overall effect on the stability of these embankment sections. The results of this study indicate that large scale deformations and/or slope failure which would result in the loss of reservoir are not deformations on the order of 2 to 3 ft are expected. These deformations are relatively small in light of the fact that 28 ft of freeboard are expected to be available during the design earthquake.

  12. Development of Distributed Research Center for monitoring and projecting regional climatic and environmental changes: first results

    NASA Astrophysics Data System (ADS)

    Gordov, Evgeny; Shiklomanov, Alexander; Okladinikov, Igor; Prusevich, Alex; Titov, Alexander

    2016-04-01

    Description and first results of the cooperative project "Development of Distributed Research Center for monitoring and projecting of regional climatic and environmental changes" recently started by SCERT IMCES and ESRC UNH are reported. The project is aimed at development of hardware and software platform prototype of Distributed Research Center (DRC) for monitoring and projecting regional climatic and environmental changes over the areas of mutual interest and demonstration the benefits of such collaboration that complements skills and regional knowledge across the northern extratropics. In the framework of the project, innovative approaches of "cloud" processing and analysis of large geospatial datasets will be developed on the technical platforms of two U.S. and Russian leading institutions involved in research of climate change and its consequences. Anticipated results will create a pathway for development and deployment of thematic international virtual research centers focused on interdisciplinary environmental studies by international research teams. DRC under development will comprise best features and functionality of earlier developed by the cooperating teams' information-computational systems RIMS (http://rims.unh.edu) and CLIMATE(http://climate.scert.ru/), which are widely used in Northern Eurasia environment studies. The project includes several major directions of research (Tasks) listed below. 1. Development of architecture and defining major hardware and software components of DRC for monitoring and projecting of regional environmental changes. 2. Development of an information database and computing software suite for distributed processing and analysis of large geospatial data hosted at ESRC and IMCES SB RAS. 3. Development of geoportal, thematic web client and web services providing international research teams with an access to "cloud" computing resources at DRC; two options will be executed: access through a basic graphical web browser and

  13. 75 FR 28602 - Bully Camp Gas Storage Project; Notice of Availability of the Environmental Assessment for the...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-05-21

    ... Energy Regulatory Commission Bully Camp Gas Storage Project; Notice of Availability of the Environmental Assessment for the Proposed Bully Camp Gas Storage Project May 14, 2010. The staff of the Federal Energy Regulatory Commission (FERC or Commission) has prepared an environmental assessment (EA) for the Bully...

  14. 76 FR 12096 - McCloud-Pit Project; Notice of Availability of the Final Environmental Impact Statement for the...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2011-03-04

    ... Energy Regulatory Commission McCloud-Pit Project; Notice of Availability of the Final Environmental... reviewed the application for license for the McCloud-Pit Hydroelectric Project (FERC No. 2106), located on the McCloud and Pit Rivers in Shasta County, California and has prepared a final environmental...

  15. West Valley Demonstration Project Annual Site Environmental Report Calendar Year 2008

    SciTech Connect

    West Valley Environmental Services LLC and URS - Washington Division

    2009-09-24

    Annual Site Environmental Report for the West Valley Demonstration Project (WVDP) for Calendar Year 2008. The report summarizes the calendar year (CY) 2008 environmental monitoring program data at the WVDP so as to describe the performance of the WVDP’s environmental management system (EMS), confirm compliance with standards and regulations, and highlight important programs. Monitoring and surveillance of the facilities used by the DOE are conducted to verify protection of the environment, continual improvement, prevention and/or minimization of pollution, public outreach, and stakeholder involvement. In addition to demonstrating compliance with environmental regulations and directives, evaluation of data collected in 2008 continued to indicate that WVDP activities pose no threat to public health or safety, or to the environment.

  16. Environmental assessment for the A-01 outfall constructed wetlands project at the Savannah River Site

    SciTech Connect

    1998-10-01

    The Department of Energy (DOE) prepared this environmental assessment (EA) to analyze the potential environmental impacts associated with the proposed A-01 outfall constructed wetlands project at the Savannah River site (SRS), located near aiken, South Carolina. The proposed action would include the construction and operation of an artificial wetland to treat effluent from the A-01 outfall located in A Area at SRS. The proposed action would reduce the outfall effluent concentrations in order to meet future outfall limits before these go into effect on October 1, 1999. This document was prepared in compliance with the National Environmental Policy Act (NEPA) of 1969, as amended; the requirements of the Council on Environmental Quality Regulations for Implementing NEPA (40 CFR Parts 1500--1508); and the DOE Regulations for Implementing NEPA (10 CFR Part 1021).

  17. Environmental assessment for Mound Plant decontamination and decommissioning projects, Mound Plant, Miamisburg, Ohio

    SciTech Connect

    1995-05-01

    The U.S. Department of Energy (DOE) has prepared an Environmental Assessment (EA) for seven decontamination and decommissioning (D&D) projects at the Mound Plant in Miamisburg, Ohio, that have not been previously addressed in the Final Environmental Impact Statement for the Mound Facility (June 1979). Based on the information presented in the EA, the DOE has determined that the proposed action is not a major Federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act (NEPA) of 1969. Therefore, the preparation of an Environmental Impact Statement (EIS) is not required and the Department is issuing this Finding of No Significant Impact (FONSI).

  18. Environmental Scanning as a Public Health Tool: Kentucky’s Human Papillomavirus Vaccination Project

    PubMed Central

    Wilburn, Amanda; Knight, Jennifer R.

    2016-01-01

    Borrowing from business, quality improvement programs, and strategic planning principles, environmental scanning is gaining popularity in public health practice and research and is advocated as an assessment and data collection tool by federal funding agencies and other health-related organizations. Applicable to a range of current and emerging health topics, environmental scans — through various methods — assess multiple facets of an issue by engaging stakeholders who can ask or answer research questions, exploring related policy, critiquing published and gray literature, collecting and analyzing qualitative and quantitative data in both primary and secondary forms, disseminating findings to internal and external stakeholders, and informing subsequent planning and decision making. To illustrate the environmental scanning process in a public health setting and showcase its value to practitioners in the field, we describe a federally funded environmental scan for a human papillomavirus vaccination project in Kentucky. PMID:27536901

  19. Tracking Dissipation Reduction, Externalities, Stability and Sustainability for Environmental Management of New Orleans

    NASA Astrophysics Data System (ADS)

    McNamara, D.; Werner, B. T.

    2014-12-01

    Sustainability requires stability, but in promoting economic development, modern economies and political systems reduce stabilizing dissipation by facilitating use and management of the environment through engineered mitigation of disturbances, which externalizes dissipation over the short to medium term. To quantitatively investigate the relationship between a range of environmental management approaches and sustainability, and the implications for Earth's future, we track the impact of management strategies on dissipation within the system and its externalities in a numerical model for the coupled economic, political/management and flooding dynamics of New Orleans. The model simulates river floods, hurricane storm-surge-induced floods, subsidence, and agent-based market interactions leading to development of port services, hotels, homes and labor relations. Flood protection decisions for levee construction based on the baseline case of cost-benefit analyses designed to prevent short-term economic loss from future floods qualitatively reproduce historical expansion of New Orleans and increases in levee height. Alternative management strategies explored include majority voting, consensus-based decision-making, and variations in discounting of costs and benefits. Enhanced dissipation is measured relative to optimal economic development without floods. The focus of modern economies on commodification is exploited to track dissipation as a scalar representing value or power, but this approach might not be applicable to more complicated traditional/indigenous cultures or cultures of resistance. For the baseline case, short-to-medium-term reductions in dissipation destabilize the coupled system, resulting in episodic bursts of externalized dissipation during flooding. Comparisons of results for a range of management options and generalizations of this approach for alternative cultural systems will be discussed.

  20. Seismic imaging of a slope stability mitigation project at Newby Island Sanitary Landfill, San Jose, California

    NASA Astrophysics Data System (ADS)

    Treece, B.; Catchings, R.; Reed, D.; Goldman, M.

    2013-12-01

    Seismic reflection and refraction data were obtained along a transect through a slope stability mitigation project involving deep soil mixing at Newby Island Sanitary Landfill in San Jose, California. Deep soil mixing involves the simultaneous injection of a cement slurry while rotating augers advance vertically down through the subsurface material, resulting in groups of soil-cement columns (elements) intended to increase the strength and rigidity of the treated area. Seismic data were used to analyze the effectiveness of the mitigation procedure, approximately one month after the completion of the deep soil mixing project. Repeated accelerated-weight-drop (AWD) impacts provided the seismic source at each geophone location. Seismic arrivals were recorded with 40-Hz vertical-component geophones, spaced at 3-m intervals. All shots were recorded on all channels. This shooting geometry was designed to produce tomographic refraction (velocity) and reflection (CDP stacks) images from a yet to be mitigated area into the mitigated area, along the base of a steep slope composed of compacted landfill. The acquired data were generally of good quality, with shots propagating the entire length of the profile. An initial analysis of the data shows an increase in seismic velocity in the treated areas compared with non-treated areas, and a relative seismic velocity increase with curing time for soil-cement elements. Future surveys will be collected to further constrain strength increases with time, and to correlate calculated rates of strength with other subsurface data.

  1. Paddys Run Streambank Stabilization Project at the Fernald Preserve, Harrison, OH

    SciTech Connect

    Hooten, Gwendolyn; Hertel, Bill; Homer, John

    2016-03-01

    The Fernald Preserve is a former uranium-processing plant that underwent extensive remediation pursuant to CERCLA and is now managed by the US DOE Office of Legacy Management. While remediation of buildings and soil contamination was completed in 2006, aquifer remediation is ongoing. Paddys Run is a second-order stream that runs to the south along the western side of the Fernald Preserve. The Paddys Run watershed encompasses nearly 41 km2 (16 mi2), including most of the Fernald site. Field personnel conducting routine site inspections in March 2014 observed that Paddys Run was migrating east via bank erosion into the “Pit 3 Swale,” an area of known surface-water contamination. The soil there was certified pursuant to site regulatory agreements and meets all final remediation levels. However, weekly surface-water monitoring is conducted from two puddles within the swale area, when water that exceeds the final remediation levels is present. Paddys Run had migrated east approximately 4 m (13 ft) in 2 years and was approximately 29 m (95 ft) from the sample location. This rapid migration threatened existing conditions that allowed for continued monitoring of the swale area and also threatened Paddys Run water quality. Therefore, DOE and regulators determined that the east bank of Paddys Run required stabilization. This was accomplished with a design that included the following components: relocation of approximately 145 m (475 ft) of streambed 9 m (30 ft) west, installation of a rock toe along the east bank, installation of two cross-vane in-stream grade-control structures, stabilization of a portion of the east bank using soil encapsulated lifts, and regrading, seeding, and planting within remaining disturbed areas. In an effort to take advantage of low-flow conditions in Paddys Run, construction was initiated in September 2014. Weather delays and subsurface flow within the Paddys Run streambed resulted in an interim shutdown of the project area in December 2014

  2. Environmental monitoring for the DOE coolside and LIMB demonstration extension projects

    SciTech Connect

    White, T.; Contos, L.

    1991-09-01

    The purpose of this document is to present environmental monitoring data collected during the US Department of Energy Limestone Injection Multistage Burner (DOE LIMB) Demonstration Project Extension at the Ohio Edison Edgewater Generating Station in Lorain, Ohio. These data were collected by implementing the Environmental Monitoring Plan (EMP) for the DOE LIMB Demonstration Project Extension, dated August 1988. This document is the fifth EMP status report to be published and presents the data generated during November and December 1990, and January 1991. These reports review a three or four month period and have been published since the project's start in October 1989. The DOE project is an extension of the US Environmental Protection Agency's (EPA) original LIMB Demonstration. The program is operated under DOE's Clean Coal Technology Program of emerging clean coal technologies'' under the categories of in boiler control of oxides of sulfur and nitrogen'' as well as post-combustion clean-up.'' The objective of the LIMB program is to demonstrate the sulfur dioxide (SO{sub 2}) and nitrogen oxide (NO{sub x}) emission reduction capabilities of the LIMB system. The LIMB system is a retrofit technology to be used for existing coal-fired boilers equipped with electrostatic precipitators (ESPs). 5 figs., 12 tabs.

  3. Genetic and Environmental Mechanisms Underlying Stability and Change in Problem Behaviors at Ages 3, 7, 10, and 12

    ERIC Educational Resources Information Center

    Bartels, M.; van den Oord, E. J. C. G.; Hudziak, J. J,; Rietveld, M. J. H.; van Beijsterveldt, C. E. M.; Boomsma, D. I.

    2004-01-01

    Maternal ratings on internalizing (INT) and externalizing (EXT) behaviors were collected in a large, population-based longitudinal sample. The numbers of participating twin pairs at ages 3, 7, 10, and 12 were 5,602, 5,115, 2,956, and 1,481, respectively. Stability in both behaviors was accounted for by genetic and shared environmental influences.…

  4. Environmentally friendly synthesis of p-doped reduced graphene oxide with high dispersion stability by using red table wine.

    PubMed

    Kim, Suk-Joon; Lee, Jang Mi; Kumer, Roy Arup; Park, Sung Young; Kim, Sang Chun; In, Insik

    2015-05-01

    Reduced graphene oxide (rGO) with high dispersion stability and p-type semiconducting property was synthesized by using environmentally friendly mussel-inspired chemistry with red table wine. (+)-Catechin and tannic acid, polyphenolic model compounds present in wine, were selected and successfully utilized for the synthesis of soluble polycatechol-functionalized rGO.

  5. Implementation Plan for the Hawaii Geothermal Project Environmental Impact Statement (DOE Review Draft:)

    SciTech Connect

    1992-09-18

    The US Department of Energy (DOE) is preparing an Environmental Impact Statement (EIS) that identifies and evaluates the environmental impacts associated with the proposed Hawaii Geothermal Project (HGP), as defined by the State of Hawaii in its 1990 proposal to Congress (DBED 1990). The location of the proposed project is shown in Figure 1.1. The EIS is being prepared pursuant to the requirements of the National Environmental Policy Act of 1969 (NEPA), as implemented by the President's Council on Environmental Quality (CEQ) regulations (40 CFR Parts 1500-1508) and the DOE NEPA Implementing Procedures (10 CFR 1021), effective May 26, 1992. The State's proposal for the four-phase HGP consists of (1) exploration and testing of the geothermal resource beneath the slopes of the active Kilauea volcano on the Island of Hawaii (Big Island), (2) demonstration of deep-water power cable technology in the Alenuihaha Channel between the Big Island and Mau, (3) verification and characterization of the geothermal resource on the Big Island, and (4) construction and operation of commercial geothermal power production facilities on the Big Island, with overland and submarine transmission of electricity from the Big Island to Oahu and possibly other islands. DOE prepared appropriate NEPA documentation for separate federal actions related to Phase 1 and 2 research projects, which have been completed. This EIS will consider Phases 3 and 4, as well as reasonable alternatives to the HGP. Such alternatives include biomass coal, solar photovoltaic, wind energy, and construction and operation of commercial geothermal power production facilities on the Island of Hawaii (for exclusive use on the Big Island). In addition, the EIs will consider the reasonable alternatives among submarine cable technologies, geothermal extraction, production, and power generating technologies; pollution control technologies; overland and submarine power transmission routes; sites reasonably suited to support

  6. Effective use of environmental impact assessments (EIAs) for geothermal development projects

    SciTech Connect

    Goff, S.J.

    2000-05-28

    Both the developed and developing nations of the world would like to move toward a position of sustainable development while paying attention to the restoration of natural resources, improving the environment, and improving the quality of life. The impacts of geothermal development projects are generally positive. It is important, however, that the environmental issues associated with development be addressed in a systematic fashion. Drafted early in the project planning stage, a well-prepared Environmental Impact Assessment (EIA) can significantly add to the quality of the overall project. An EIA customarily ends with the decision to proceed with the project. The environmental analysis process could be more effective if regular monitoring, detailed in the EIA, continues during project implementation. Geothermal development EIAs should be analytic rather than encyclopedic, emphasizing the impacts most closely associated with energy sector development. Air quality, water resources and quality, geologic factors, and socioeconomic issues will invariably be the most important factors. The purpose of an EIA should not be to generate paperwork, but to enable superb response. The EIA should be intended to help public officials make decisions that are based on an understanding of environmental consequences and take proper actions. The EIA process has been defined in different ways throughout the world. In fact, it appears that no two countries have defined it in exactly the same way. Going hand in hand with the different approaches to the process is the wide variety of formats available. It is recommended that the world geothermal community work towards the adoption of a standard. The Latin American Energy Organization (OLADE) and the Inter-American Development Bank (IDB)(OLADE, 1993) prepared a guide that presents a comprehensive discussion of the environmental impacts and suggested mitigation alternatives associated with geothermal development projects. The OLADE guide

  7. Facility stabilization project, fiscal year 1998 -- Multi-year workplan (MYWP) for WBS 1.4

    SciTech Connect

    Floberg, W.C.

    1997-09-30

    The primary Facility Stabilization mission is to provide minimum safe surveillance and maintenance of facilities and deactivate facilities on the Hanford Site, to reduce risks to workers, the public and environment, transition the facilities to a low cost, long term surveillance and maintenance state, and to provide safe and secure storage of special nuclear materials, nuclear materials, and nuclear fuel. Facility Stabilization will protect the health and safety of the public and workers, protect the environment and provide beneficial use of the facilities and other resources. Work will be in accordance with the Hanford Federal Facility Agreement and Consent Order (Tri-Party Agreement), local, national, international and other agreements, and in compliance with all applicable Federal, state, and local laws. The stakeholders will be active participants in the decision processes including establishing priorities, and in developing a consistent set of rules, regulations, and laws. The work will be leveraged with a view of providing positive, lasting economic impact in the region. Effectiveness, efficiency, and discipline in all mission activities will enable Hanford Site to achieve its mission in a continuous and substantive manner. As the mission for Facility Stabilization has shifted from production to support of environmental restoration, each facility is making a transition to support the Site mission. The mission goals include the following: (1) Achieve deactivation of facilities for transfer to EM-40, using Plutonium Uranium Extraction (PUREX) plant deactivation as a model for future facility deactivation; (2) Manage nuclear materials in a safe and secure condition and where appropriate, in accordance with International Atomic Energy Agency (IAEA) safeguards rules; (3) Treat nuclear materials as necessary, and store onsite in long-term interim safe storage awaiting a final disposition decision by US Department of Energy; (4) Implement nuclear materials

  8. Environmental aspects of the proposed UCG project site in Washington state

    SciTech Connect

    Adamson, M.; Tonnessen, K.

    1980-05-29

    Lawrence Livermore National Laboratory is conducting an environmental assessment of the proposed underground coal gasification experiment in the Tono Basin near Centralia, Washington. This analysis is funded by the Department of Energy. To satisfy the provisions of the National Environmental Policy Act (NEPA), the following elements are included in the assessment: (1) description of the proposed action and alternatives; (2) description of the existing environment; (3) potential environmental impacts of the project; and (4) agencies consulted to ensure coordination in evaluating effective mitigation measures. Field reconnaissance and environmental data collected from both state and county agencies and from local individuals and organizations form the basis for an evaluation of the potential impact of the project on this riparian ecosystem. A cultural resource survey was also conducted as part of the site evaluation. Principal areas of concern include the potential for damage due to air emissions and groundwater contamination, maintenance of surface water quality and minimization of disruption of wildlife habitat. Possible mitigation measures to protect environmental quality are recommended.

  9. Environmental Contributions to the Stability of Antisocial Behavior over Time: Are They Shared or Non-shared?

    PubMed Central

    Burt, S. Alexandra; McGue, Matt; Iacono, William G.

    2010-01-01

    It has recently been argued that shared environmental influences are moderate, identifiable, and persistent sources of individual differences in most forms of child and adolescent psychopathology, including antisocial behavior. Unfortunately, prior studies examining the stability of shared environmental influences over time were limited by possible passive gene-environment correlations, shared informants effects, and/or common experiences of trauma. The current study sought to address each of these limitations. We examined adolescent self-reported antisocial behavior in a 3.5 year longitudinal sample of 610 biological and adoptive sibling pairs from the Sibling Interaction and Behavior Study (SIBS). Results revealed that 74–81% of shared environmental influences present at time 1 were also present at time 2, whereas most non-shared environmental influences (88–89%) were specific to a particular assessment period. Such results provide an important constructive replication of prior research, strongly suggesting that shared environmental contributions to antisocial behavior are systematic in nature. PMID:19904602

  10. Washington Wildlife Mitigation Projects : Final Programmatic Environmental Assessment and Finding of No Significant Impact.

    SciTech Connect

    United States. Bonneville Power Administration; Washington . Dept. of Fish and Wildlife.

    1996-08-01

    Bonneville Power Administration (BPA) proposes to fund the portion of the Washington Wildlife Mitigation Agreement (Agreement) pertaining to wildlife habitat mitigation projects to be undertaken in a cooperative effort with the Washington Department of Fish and Wildlife (WDFW). This Agreement serves to establish a monetary budget funded by BPA for projects proposed by Washington Wildlife Coalition members and approved by BPA to protect, mitigate, and improve wildlife and/or wildlife habitat within the State of Washington that has been affected by the construction of Federal dams along the Columbia River. This Environmental Assessment examines the potential environmental effects of acquiring and/or improving wildlife habitat within five different project areas. These project areas are located throughout Grant County and in parts of Okanogan, Douglas, Adams, Franklin, Kittias, Yakima, and Benton Counties. The multiple projects would involve varying combinations of five proposed site-specific activities (habitat improvement, operation and maintenance, monitoring and evaluation, access and recreation management, and cultural resource management). All required Federal, State, and tribal coordination, permits and/or approvals would be obtained prior to ground-disturbing activities.

  11. 42 CFR 137.292 - How do Self-Governance Tribes assume environmental responsibilities for construction projects...

    Code of Federal Regulations, 2010 CFR

    2010-10-01

    ... 42 Public Health 1 2010-10-01 2010-10-01 false How do Self-Governance Tribes assume environmental...-Governance Tribes assume environmental responsibilities for construction projects under section 509 of the Act ? Self-Governance Tribes assume environmental responsibilities by: (a) Adopting a resolution...

  12. Stability and resilience of seagrass meadows to seasonal and interannual dynamics and environmental stress

    NASA Astrophysics Data System (ADS)

    Carr, Joel A.; D'Odorico, Paolo; McGlathery, Karen J.; Wiberg, Patricia L.

    2012-03-01

    Shallow coastal bays provide habitat for diverse fish and invertebrate populations and are an important source of sediment for surrounding marshes. The sediment dynamics of these bays are strongly affected by seagrass meadows, which limit sediment resuspension, thereby providing a more favorable light environment for their own survival and growth. Due to this positive feedback between seagrass and light conditions, it has been suggested that bare sediment and seagrass meadows are potential alternate stable states of the benthos in shallow coastal bays. To investigate the stability and resilience of seagrass meadows subjected to variation in environmental conditions (e.g., light, temperature), a coupled model of vegetation-sediment-water flow interactions and vegetation growth was developed. The model was used to examine the effect of dynamically varying seasonal and interannual seagrass density on sediment resuspension, water column turbidity, and the subsequent light environment on hourly time steps and then run over decadal time scales. A daily growth model was designed to capture both belowground biomass and the growth and senescence of aboveground biomass structural components (e.g., leaves and stems). This allowed us to investigate how the annual and seasonal variability in shoot and leaf density within a meadow affects the strength of positive feedbacks between seagrass and their light environment. The model demonstrates both the emergence of bistable behavior from 1.6 to 1.8 m mean sea level due to the strength of the positive feedback, as well as the limited resilience of seagrass meadows within this bistable range.

  13. Rapid Analysis of Glibenclamide Using an Environmentally Benign Stability-Indicating RP-HPLC Method

    PubMed Central

    Haq, Nazrul; Alanazi, Fars Kaed; Alsarra, Ibrahim Abdullah; Shakeel, Faiyaz

    2014-01-01

    An environmentally benign RP-HPLC approach for rapid analysis of glibenclamide in pure form, developed nanoemulsion and commercial tablets was developed and validated in present investigation. The green chromatographic identification was performed on Lichrosphere 250 X 4.0 mm RP C8 column having a 5 μm packing as a stationary phase using a combination of ethanol: methanol (50:50 % v/v) as a mobile phase, at a flow rate of 1.0 mL/min with UV detection at 245 nm. The proposed method was validated for linearity, selectivity, accuracy, precision, robustness, sensitivity and specificity as per international conference on harmonization (ICH) guidelines. The utility of proposed method was verified by assay of glibenclamide in developed nanoemulsion and commercial tablets. The proposed method was found to be satisfactory in terms of selectivity, precision, accuracy, robustness, sensitivity and specificity. The content of glibenclamide in developed nanoemulsion and commercial tablets was found to be 100.50 % and 99.15 % respectively. The proposed method successfully resoled glibenclamide peak in the presence of its all type of degradation products which indicated stability-indicating property of the proposed method. These results indicated that the green chromatographic method could be successfully employed for routine analysis of glibenclamide in pure drug and various commercial formulations. PMID:25276186

  14. Rapid Analysis of Glibenclamide Using an Environmentally Benign Stability-Indicating RP-HPLC Method.

    PubMed

    Haq, Nazrul; Alanazi, Fars Kaed; Alsarra, Ibrahim Abdullah; Shakeel, Faiyaz

    2014-01-01

    An environmentally benign RP-HPLC approach for rapid analysis of glibenclamide in pure form, developed nanoemulsion and commercial tablets was developed and validated in present investigation. The green chromatographic identification was performed on Lichrosphere 250 X 4.0 mm RP C8 column having a 5 μm packing as a stationary phase using a combination of ethanol: methanol (50:50 % v/v) as a mobile phase, at a flow rate of 1.0 mL/min with UV detection at 245 nm. The proposed method was validated for linearity, selectivity, accuracy, precision, robustness, sensitivity and specificity as per international conference on harmonization (ICH) guidelines. The utility of proposed method was verified by assay of glibenclamide in developed nanoemulsion and commercial tablets. The proposed method was found to be satisfactory in terms of selectivity, precision, accuracy, robustness, sensitivity and specificity. The content of glibenclamide in developed nanoemulsion and commercial tablets was found to be 100.50 % and 99.15 % respectively. The proposed method successfully resoled glibenclamide peak in the presence of its all type of degradation products which indicated stability-indicating property of the proposed method. These results indicated that the green chromatographic method could be successfully employed for routine analysis of glibenclamide in pure drug and various commercial formulations.

  15. 78 FR 11672 - Notice of Availability of the Final Environmental Impact Statement for the Alta East Wind Project...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2013-02-19

    ... of Mojave and 11 miles east of the city of Tehachapi. The project would include wind turbines, access... East Wind Project, Kern County, CA, and Proposed Land Use Plan Amendment AGENCY: Bureau of Land... (CDCA) Plan Amendment/Final Environmental Impact Statement (EIS) for the Alta East Wind Project...

  16. DELIVERING TIMELY AIR QUALITY, TRAFFIC, AND WEATHER INFORMATION TO YOUR COMMUNITY/THE PASO DEL NORTE ENVIRONMENTAL MONITORING PROJECT

    EPA Science Inventory

    EPA has developed a technology transfer handbook for the EMPACT Paso del Norte Project. The EMPACT Paso del Norte Environmental Monitoring Project is a mobile vehicle emissions project that involves the international community of El Paso, TX; Sundland Park, NM; and Juarez, Mexico...

  17. 75 FR 48322 - McCloud-Pit Project; Notice of Availability of the Draft Environmental Impact Statement for the...

    Federal Register 2010, 2011, 2012, 2013, 2014

    2010-08-10

    ... Energy Regulatory Commission McCloud-Pit Project; Notice of Availability of the Draft Environmental Impact Statement for the McCloud-Pit Hydroelectric Project and Intention To Hold Public Meetings July 30... CFR part 380 ), the Office of Energy Projects has reviewed the application for license for the...

  18. Importance of individual and environmental variation for invasive species spread: a spatial integral projection model.

    PubMed

    Jongejans, Eelke; Shea, Katriona; Skarpaas, Olav; Kelly, Dave; Ellner, Stephen P

    2011-01-01

    Plant survival, growth, and flowering are size dependent in many plant populations but also vary among individuals of the same size. This individual variation, along with variation in dispersal caused by differences in, e.g., seed release height, seed characteristics, and wind speed, is a key determinant of the spread rate of species through homogeneous landscapes. Here we develop spatial integral projection models (SIPMs) that include both demography and dispersal with continuous state variables. The advantage of this novel approach over discrete-stage spread models is that the effect of variation in plant size and size-dependent vital rates can be studied at much higher resolution. Comparing Neubert-Caswell matrix models to SIPMs allowed us to assess the importance of including individual variation in the models. As a test case we parameterized a SIPM with previously published data on the invasive monocarpic thistle Carduus nutans in New Zealand. Spread rate (c*) estimates were 34% lower than for standard spatial matrix models and stabilized with as few as seven evenly distributed size classes. The SIPM allowed us to calculate spread rate elasticities over the range of plant sizes, showing the size range of seedlings that contributed most to c* through their survival, growth and reproduction. The annual transitions of these seedlings were also the most important ones for local population growth (lambda). However, seedlings that reproduced within a year contributed relatively more to c* than to lambda. In contrast, plants that grow over several years to reach a large size and produce many more seeds, contributed relatively more to lambda than to c*. We show that matrix models pick up some of these details, while other details disappear within wide size classes. Our results show that SIPMs integrate various sources of variation much better than discrete-stage matrix models. Simpler, heuristic models, however, remain very valuable in studies where the main goal is

  19. Stability and Change in Genetic and Environmental Influences on Well-Being in Response to an Intervention

    PubMed Central

    Haworth, Claire M. A.; Nelson, S. Katherine; Layous, Kristin; Carter, Kathryn; Jacobs Bao, Katherine; Lyubomirsky, Sonja; Plomin, Robert

    2016-01-01

    Genetic and environmental influences on complex traits can change in response to developmental and environmental contexts. Here we explore the impact of a positive activity intervention on the genetic and environmental influences on well-being and mental health in a sample of 750 adolescent twins. Twins completed a 10-week online well-being intervention, consisting of kindness and gratitude tasks and matched control activities. The results showed significant improvements both in well-being and in internalizing symptoms in response to the intervention activities. We used multivariate twin analyses of repeated measures, tracking stability and change in genetic and environmental influences, to assess the impact of this environmental intervention on these variance components. The heritability of well-being remained high both before and after the intervention, and the same genetic effects were important at each stage, even as well-being increased. The overall magnitude of environmental influences was also stable across the intervention; however, different non-shared environmental influences emerged during the intervention. Our study highlights the value of exploring the innovations in non-shared environmental influences that could provide clues to the mechanisms behind improvements in well-being. The findings also emphasize that even traits strongly influenced by genetics, like well-being, are subject to change in response to environmental interventions. PMID:27227410

  20. Uncertainty and Sensitivity Analyses Plan. Draft for Peer Review: Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Simpson, J.C.; Ramsdell, J.V. Jr.

    1993-04-01

    Hanford Environmental Dose Reconstruction (HEDR) Project staff are developing mathematical models to be used to estimate the radiation dose that individuals may have received as a result of emissions since 1944 from the US Department of Energy`s (DOE) Hanford Site near Richland, Washington. An uncertainty and sensitivity analyses plan is essential to understand and interpret the predictions from these mathematical models. This is especially true in the case of the HEDR models where the values of many parameters are unknown. This plan gives a thorough documentation of the uncertainty and hierarchical sensitivity analysis methods recommended for use on all HEDR mathematical models. The documentation includes both technical definitions and examples. In addition, an extensive demonstration of the uncertainty and sensitivity analysis process is provided using actual results from the Hanford Environmental Dose Reconstruction Integrated Codes (HEDRIC). This demonstration shows how the approaches used in the recommended plan can be adapted for all dose predictions in the HEDR Project.

  1. Environmental monitoring for the DOE coolside and LIMB demonstration extension projects

    SciTech Connect

    White, T.; Contos, L.; Adams, L. )

    1992-03-01

    The purpose of this document is to present environmental monitoring data collected during the US Department of Energy Limestone Injection Multistage Burner (DOE LIMB) Demonstration Project Extension at the Ohio Edison Edgewater Generating Station in Lorain, Ohio. The DOE project is an extension of the US Environmental Protection Agency's (EPA's) original LIMB Demonstration. The program is operated nuclear DOE's Clean Coal Technology Program of emerging clean coal technologies'' under the categories of in boiler control of oxides of sulfur and nitrogen'' as well as post-combustion clean-up.'' The objective of the LIMB program is to demonstrate the sulfur dioxide (SO{sub 2}) and nitrogen oxide (NO{sub x}) emission reduction capabilities of the LIMB system. The LIMB system is a retrofit technology to be used for existing coal-fired boilers equipped with electrostatic precipitators (ESPs).

  2. Are stream stabilization projects reducing suspended sediment concentrations and turbidity in the New York City Water Supply Watershed?

    NASA Astrophysics Data System (ADS)

    McHale, M. R.; Siemion, J.; Davis, W. D.

    2015-12-01

    Turbidity and suspended sediment concentrations (SSCs) are primary water quality concerns in the upper Esopus Creek watershed, the main tributary to the Ashokan reservoir. The Ashokan reservoir is one of 6 surface water reservoirs that constitute about 90% of New York City's drinking water supply. This study quantified turbidity levels and SSCs at 10 locations throughout the upper Esopus Creek watershed for 3 years prior to the implementation of 2 stream stabilization projects and for 18 months after the projects were completed. More than 93 percent of the total-suspended sediment load occurred on days with flows greater than or equal to the 90th percentile of flows observed during the study period. Discharge, SSC, and turbidity were strongly related at the outlet of the upper Esopus Creek, but not at every monitoring site. In general, relations between discharge and SSC and turbidity were strongest at sites with high SSCs, with the exception of Stony Clove Creek, the largest tributary. Stony Clove Creek, consistently produced higher SSCs and turbidity than any of the other Esopus Creek tributaries. Nonetheless, there was not a strong relation between either turbidity or SSC and discharge because there was a series of eroding banks in contact with fine grained glacio-lacustrine deposits and associated hill slope failures within the Stony Clove Creek watershed that delivered elevated turbidity and SSCs to the stream during all flow conditions. Stream bank stabilization projects were completed at two of the largest bank failures. After the projects were completed there was decrease in stream SSC and turbidity however, flows during the 18 months following the projects were lower than before the projects. Nevertheless, a shift in the SSC and turbidity discharge rating curves suggests that the stream stabilization projects resulted in lower turbidity levels and SSCs for similar discharge conditions as compared to before the projects thereby reducing sediment yields

  3. Assessment of Environmental Considerations in the Design and Construction of Waterway Projects.

    DTIC Science & Technology

    1982-09-01

    at producing a heavy weed- free sod with grass 2 to 12 in. high. Loss of species of plants which provide food can impact some species of birds and...control channel modification 0 include loss of valuable habitats and habitat diversity, channel instability, reduction of aesthetic value, water...meanders. t Immediate and eventual losses of backwater habitat are a major impact of navigation channel modification projects.., The major environmental

  4. 2003 Fernald Environmental Management Project Annual Illness and Injury Surveillance Report, Revised September 2007

    SciTech Connect

    U.S. Department of Energy, Office of Health, Safety and Security, Office of Illness and Injury Prevention Programs

    2007-10-04

    Annual Illness and Injury Surveillance Program report for 2003 for the Fernald Environmental Management Project. The U.S. Department of Energy’s (DOE) commitment to assuring the health and safety of its workers includes the conduct of epidemiologic surveillance activities that provide an early warning system for health problems among workers. The IISP monitors illnesses and health conditions that result in an absence of workdays, occupational injuries and illnesses, and disabilities and deaths among current workers.

  5. Atmospheric transport modeling and input data for Phase 1 of the Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Ramsdell, J.V.; Burk, K.W.

    1991-07-01

    This report summarizes the information used in modeling atmospheric transport and diffusion for Phase I of the Hanford Environmental Dose Reconstruction (HEDR) Project. It also lists the results of the atmospheric transport calculations that were provided for use in dose estimation. The report does not contain a description of the atmospheric model or an analysis of the results of the atmospheric calculations. 9 refs., 3 figs., 14 tabs.

  6. Environmental monitoring for the DOE coolside and LIMB demonstration extension projects

    SciTech Connect

    White, T.; Contos, L.; Adams, L. . Progress Center)

    1992-02-01

    The purpose of this document is to present environmental monitoring data collected during the US DOE Limestone Injection Multistage Burner (LIMB) Demonstration Project Extension. The objective of the LIMB program is to demonstrate the sulfur dioxide (SO{sub 2}) and nitrogen oxide (NO{sub x}) emission reduction capabilities of the LIMB system. The LIMB system is a retrofit technology to be used for existing coal-fired boilers equipped with electrostatic precipitators. (VC)

  7. Resource Contingency Program - Oregon : Final Environmental Impact Statement, Hermiston Power Project.

    SciTech Connect

    United States. Bonneville Power Administration.

    1995-09-01

    The Bonneville Power Administration (BPA) has statutory responsibilities to supply electrical power to its utility, industrial, and other customers in the Pacific Northwest. In 1990, to cover the outer range of potential load growth with new resources, BPA embarked upon the Resource Contingency Program (RCP). Instead of buying or building generating plants now, BPA has purchased options to acquire power later, if and when it is needed. The decision to acquire any of these option energy projects to fulfill statutory supply obligations will be influenced by Federal system load growth, the outcome of BPA`s Business Plan, required operational changes in Columbia-Snake River Hydroelectric facilities, and the loss of major generating resources. In September 1993, three option development agreements were signed with three proposed natural gas-fired, combined cycle combustion turbine CT projects near Chehalis and Satsop, Washington, and near Hermiston, Oregon. Together these three projects could supply BPA with 1,090 average megawatts (aMW) of power. Under these agreements, sponsors are obtaining permits and conducting project design work, and BPA is completing this EIS process. In September 1993, BPA published a Notice of Intent to prepare an environmental impact statement (EIS) on these three proposed gas-fired combustion turbine projects and held public scoping meetings in October 1993 at each site. In February 1994, BPA released an Implementation Plan on the proposed scope of the EIS. A draft EIS on the three proposed projects was published in February 1995. The impacts of the Chehalis and Satsop projects located in Washington State will be covered in one EIS document, while the impacts of the Hermiston project located in Oregon are covered in this final EIS document. It is BPA`s intent to continue to base the analysis of impacts on the assumption that all three projects may be constructed at some point in the future.

  8. Combustion Stability Characteristics of the Project Morpheus Liquid Oxygen / Liquid Methane Main Engine

    NASA Technical Reports Server (NTRS)

    Melcher, John C.; Morehead, Robert L.

    2014-01-01

    The project Morpheus liquid oxygen (LOX) / liquid methane (LCH4) main engine is a Johnson Space Center (JSC) designed 5,000 lbf-thrust, 4:1 throttling, pressure-fed cryogenic engine using an impinging element injector design. The engine met or exceeded all performance requirements without experiencing any in- ight failures, but the engine exhibited acoustic-coupled combustion instabilities during sea-level ground-based testing. First tangential (1T), rst radial (1R), 1T1R, and higher order modes were triggered by conditions during the Morpheus vehicle derived low chamber pressure startup sequence. The instability was never observed to initiate during mainstage, even at low power levels. Ground-interaction acoustics aggravated the instability in vehicle tests. Analysis of more than 200 hot re tests on the Morpheus vehicle and Stennis Space Center (SSC) test stand showed a relationship between ignition stability and injector/chamber pressure. The instability had the distinct characteristic of initiating at high relative injection pressure drop at low chamber pressure during the start sequence. Data analysis suggests that the two-phase density during engine start results in a high injection velocity, possibly triggering the instabilities predicted by the Hewitt stability curves. Engine ignition instability was successfully mitigated via a higher-chamber pressure start sequence (e.g., 50% power level vs 30%) and operational propellant start temperature limits that maintained \\cold LOX" and \\warm methane" at the engine inlet. The main engine successfully demonstrated 4:1 throttling without chugging during mainstage, but chug instabilities were observed during some engine shutdown sequences at low injector pressure drop, especially during vehicle landing.

  9. Grand Junction Projects Office site environmental report for calendar year 1992

    SciTech Connect

    Not Available

    1993-05-01

    This report presents information pertaining to environmental activities conducted during calendar year 1992 at the US Department of Energy Grand Junction Projects Office (DOE-GJPO) facility in Colorado. Environmental activities conducted at the GJPO facility during 1992 included those associated with environmental compliance, site remediation, off-site dose modeling, and radiological and nonradiological monitoring. Four phases of the on-site Grand Junction Projects Office Remedial Action Project were completed in 1992. Remediation activities, which included the removal of 161,589 tons of uranium-mill-tailings-contaminated material from the facility, were conducted in compliance with all applicable permits. Off-site dose modeling for the GJPO was conducted to determine compliance with current National Emission Standards for Hazardous Air Pollutants, Subpart H, and applicable DOE Orders (5400.1 and 5400.5). The total off-site EDE to the public from all sources of radiation emanating from the facility (radon, air particulates, gamma) was calculated as 9 mrem/yr, which is well below the DOE dose limit of 100 mrem/yr above background. The radiological and nonradiological monitoring program at the GJPO facility included monitoring of activities that generate potentially hazardous or toxic wastes and monitoring of ambient air, surface water, and ground water.

  10. Collaborative environmental projects in a multicultural society: working from within separate or mutual landscapes?

    NASA Astrophysics Data System (ADS)

    Tal, Tali; Alkaher, Iris

    2010-06-01

    A multicultural socio-environmental project that is framed in the ideas of education for sustainability brought together Jew and Arab students was investigated to identify the participants' views of the program's objectives and their accomplishments. We investigated the project's strengths and weaknesses according to the participants' views and the way culturally diverse students addressed the main local socio-environmental conflict related to conservation versus development of a local creek. The participants agreed that the environmental objectives were properly attained, while the social objectives were accomplished to a limited extent. All the participants emphasized the importance of multicultural knowledge and expected to learn and work together. We found different views of the Jewish and the Arab participants regarding expectations, collaboration and overall satisfaction, with higher expectations of the Arab students and leaders. The students' views of the local conflict varied but were not associated with their ethnic background. We suggest that the differences between the groups result from the different positions and needs of each community, and mainly as a consequence of the difficulties that the Arab minority faces in Israel. Overall, we found that the project allowed the expression of multiple voices of both groups, and suggested an applicable program for education for sustainability in a multicultural society. [InlineMediaObject not available: see fulltext.][InlineMediaObject not available: see fulltext.

  11. Mid-Columbia Coho Reintroduction Feasibility Project : Final Environmental Assessment and Finding of No Significant Impact.

    SciTech Connect

    United States. Bonneville Power Administration; Confederated Tribes and Bands of the Yakama Nation; Washington State Department of Fish and Wildlife

    1999-04-01

    Bonneville Power Administration (BPA) is proposing to fund research for 2 to 3 years on the feasibility of reintroducing coho salmon into mid-Columbia River basin tributaries. The research would take place in the Methow and Wenatchee river basins in Chelan and Okanogan Counties, Washington. BPA has prepared an Environmental Assessment (EA) (DOE/EA-1282) evaluating the proposed project. Based on the analysis in the EA, BPA has determined that the proposed action is not a major Federal action significantly affecting the quality of the human environment, within the meaning of the National Environmental Policy Act (NEPA) of 1969. Therefore, the preparation of an Environmental Impact Statement (EIS) is not required, and BPA is issuing this Finding of No Significant Impact.

  12. Approved CAMU equals faster, better, cheaper remediation at the Fernald Environmental Management Project

    SciTech Connect

    Dupuis-Nouille, E.M.; Goidell, L.C.; Strimbu, M.J.; Nickel, K.A.

    1996-03-01

    A 1,050 acre Corrective Action Management Unit (CAMU) was approved for the Fernald Protection Agency Environmental Management Project (FEMP) by the US Environmental Protection Agency (USEPA) to manage environmental media remediation waste in the Operable Unit 5 Record of Decision, 1995. Debris is also proposed for management as remediation waste under the CAMU Rule in the Operable Unit 3 Remedial Investigation/Feasibility Study (RI/FS) Report, as of December 1995. Application of the CAMU Rule at the FEMP will allow consolidation of low-level mixed waste and hazardous waste that presents minimal threat from these two operable units in an on-property engineered disposal facility without triggering land disposal restrictions (LDRs). The waste acceptance criteria for the on property disposal facility are based on a combination of site-specific risk-based concentration standards, as opposed to non-site-specific requirements imposed by regulatory classifications.

  13. Foundation stones for a real socio-environmental integration in projects' impact assessments

    NASA Astrophysics Data System (ADS)

    Andres Dominguez-Gomez, J.

    2015-04-01

    In the last twenty years, both the increase in academic production and the expansion of professional involvement in Environmental Impact Assessment (EIA) and Social Impact Assessment (SIA), have evidenced growing scientific and business interest in risk and impact analysis. However, this growth has not brought with it a parallel progress in addressing their main shortcomings: insufficient integration of environmental and social features into development project analyses and, in cases where the social aspects are considered, technical-methodological failings in their diagnosis and assessment. It is clear that these weaknesses carry with them substantial threats to the sustainability (social, environmental and economic) of schemes which impact on the environment, and in consequence, to the local contexts where they are carried out and to the delicate balance of the global ecosystem. This paper argue that, in a sociological context of growing complexity, four foundation-stones are required to underpin research methodologies (for both diagnosis and assessment) in the socio-environmental risks of development projects: a theoretical foundation in actor-network theory; an ethical grounding in values which are internationally recognized though not always carried through into practice; a (new) epistemological-scientific base; and a methodological foundation in social participation.

  14. Proposed IMS infrastructure improvement project, Seward, Alaska. Final environmental impact statement

    SciTech Connect

    Not Available

    1994-09-01

    This Environmental Impact Statement (EIS) examines a proposal for improvements at the existing University of Alaska, Fairbanks, Institute of Marine Science (IMS), Seward Marine Center. The Exxon Valdez Oil Spill (EVOS) Trustee Council is proposing to improve the existing research infrastructure to enhance the EVOS Trustee Council`s capabilities to study and rehabilitate marine mammals, marine birds, and the ecosystem injured by the Exxon Valdez oil spill. The analysis in this document focuses on the effects associated with construction and operation of the proposed project and its proposed alternatives. The EIS gives a detailed description of all major elements of the proposed project and its alternatives; identifies resources of major concern that were raised during the scoping process; describes the environmental background conditions of those resources; defines and analyzes the potential effects of the proposed project and its alternatives on these conditions; and identifies mitigating measures that are part of the project design as well as those proposed to minimize or reduce the adverse effects. Included in the EIS are written and oral comments received during the public comment period.

  15. Nitrate photochemistry in NaY zeolite: product formation and product stability under different environmental conditions.

    PubMed

    Gankanda, Aruni; Grassian, Vicki H

    2013-03-14

    In the atmosphere, mineral dust particles are often associated with adsorbed nitrate from heterogeneous reactions with nitrogen oxides (N2O5, HNO3, NO3, and NO2). Nitrate ions associated with mineral dust particles can undergo further reactions including those initiated by solar radiation. Although nitrate photochemistry in aqueous media is fairly well studied, much less is known about the photochemistry of nitrate adsorbed on mineral dust particles. In this study, the photochemistry of nitrate from HNO3 adsorption in NaY zeolite under different environmental conditions has been investigated using transmission FTIR spectroscopy. NaY zeolite is used as a model zeolite for studying reactions that can occur in confined space such as those found in porous materials including naturally occurring zeolites and clays. Upon nitrate photolysis under dry conditions (relative humidity, RH, < 1%), surface nitrite is formed as the major adsorbed product. Although nitrite has been proposed as a product in the photochemistry of nitrate adsorbed on metal oxide particle surfaces, such as on alumina, it has not been previously detected. The stability of adsorbed nitrite in NaY is attributed to the confined three-dimensional structure of the porous zeolite, which contains a charge compensating cation that can stabilize the nitrite ion product. Besides adsorbed nitrite, small amounts of gas phase nitrogen-containing products are observed as well including NO2, NO, and N2O at long irradiation times. The amount of nitrite formed via nitrate photochemistry decreases with increasing relative humidity, whereas gas phase NO and N2O become the only detectable products. Gas-phase NO2 does not observe at RH > 1%. In the presence of gas phase ammonia, ammonium nitrate is formed in NaY zeolite. Photochemistry of ammonium nitrate yields gas phase N2O as the sole gas phase product. Evidence for an NH2 intermediate in the formation of N2O is identified with FTIR spectroscopy for HNO3 adsorption and

  16. Distinct oxidative stabilities of char versus soot black carbon: Implications for quantification and environmental recalcitrance

    NASA Astrophysics Data System (ADS)

    Elmquist, Marie; Cornelissen, Gerard; Kukulska, Zofia; Gustafsson, Örjan

    2006-06-01

    Sequestration in sediments of black carbon (BC) from vegetation fires and fuel combustion may constitute a significant sink of otherwise rapidly cycling carbon from the atmosphere-biosphere cycle. It also has the potential to provide a historical record of atmospheric BC loadings. Previous treatments of BC as one homogeneous entity are being replaced with the growing awareness of a BC combustion continuum, a range spanning from slightly charred biomass to soot and graphite. Here the relative recalcitrance of different BC forms is evaluated, and implications for both BC quantification and environmental stability are considered. The stabilities of four BC reference materials against thermal oxidation in air were quite distinct with T50%BC values (i.e., the temperature where 50% BC remained in the residue) of 444°C (diesel soot-BC), 388°C (n-hexane soot-BC), 338°C (wood char-BC), and 266°C (grass char-BC). The implications for BC quantification have been illustrated for a thermal oxidation (the CTO-375) method commonly applied to study BC in sediments. This technique measured BC:TOC ratios of 78.3 ± 1.3% for the diesel soot-BC and 45.3 ± 6.1% for n-hexane soot-BC, whereas no CTO375-BC was detected for the two analyzed char-BC materials. The greater lability of char-BC compared to soot-BC likely reflects higher accessibility to internal microporosity in char-BC, facilitating internal O2 transfer. Decreasing the temperature cutoff below 375°C to also include char-BC is not possible as thermograms of nonpyrogenic reference materials indicated that such material would then be artifactually quantified as BC. The presence of mineral oxides in the sediment matrix may lead to a catalytically mediated lowering of the activation energy for soot-BC oxidation but not for char-BC or nonpyrogenic organic material. Several recent studies combine to challenge the proposition of complete recalcitrance of BC. Particularly, the thermal lability of char-BC from grassland fires

  17. A work bibliography on native food consumption, demography and lifestyle. Hanford Environmental Dose Reconstruction Project

    SciTech Connect

    Murray, C.E.; Lee, W.J.

    1992-12-01

    The purpose of this report is to provide a bibliography for the Native American tribe participants in the Hanford Environmental Dose Reconstruction (HEDR) Project to use. The HEDR Project`s primary objective is to estimate the radiation dose that individuals could have received as a result of emissions since 1944 from the US Department of Energy`s Hanford Site near Richland, Washington. Eight Native American tribes are responsible for estimating daily and seasonal consumption of traditional foods, demography, and other lifestyle factors that could have affected the radiation dose received by tribal members. This report provides a bibliography of recorded accounts that tribal researchers may use to verify their estimates. The bibliographic citations include references to information on the specific tribes, Columbia River plateau ethnobotany, infant feeding practices and milk consumption, nutritional studies and radiation, tribal economic and demographic characteristics (1940--1970), research methods, primary sources from the National Archives, regional archives, libraries, and museums.

  18. Los Alamos National Laboratory Environmental Restoration Project quarterly technical report, April--June 1994

    SciTech Connect

    Not Available

    1994-08-18

    This quarterly report describes the technical status of activities in the Los Alamos National Laboratory Environmental Restoration (ER) Project. Each activity is identified by an activity data sheet number, a brief title describing the activity or the technical area where the activity is located, and the name of the project leader. The Hazardous and Solid Waste Amendments (HSWA) portion of the facility operating permit requires the submission of a technical progress report on a quarterly basis. This report, submitted to fulfill the permit`s requirement, summarizes the work performed and the results of sampling and analysis in the ER Project. Suspect waste found include: Radionuclides, high explosives, metals, solvents and organics. The data provided in this report have not been validated. These data are considered ``reviewed data.``

  19. Assessing data quality for a federal environmental restoration project: Rationalizing the requirements of multiple clients

    SciTech Connect

    Kiszka, V.R.; Carlsen, T.M.

    1994-07-01

    Most environmental restoration projects at federal facilities face the difficult task of melding the quality assurance (QA) requirements of multiple clients, as well as dealing with historical data that are often of unknown quality. At Lawrence Livermore National Laboratory (LLNL), we have successfully integrated the requirements of our multiple clients by carefully developing a QA program that efficiently meets our clients` needs. The Site 300 Experimental Test Site is operated by LLNL in support of its national defense program. The responsibility for conducting environmental contaminant investigations and restoration at Site 300 is vested in the Site 300 Environmental Restoration Project (Site 300 ERP) of LLNL`s Environmental Restoration Division. LLNL Site 300 ERP must comply with the QA requirements of several clients, which include: the LLNL Environmental Protection Department, the DOE, the US Environmental Protection Agency-Region IX (EPA), the California Regional Water Quality Control Board -- Central Valley Region, and the California Department of Toxic Substances Control. This comprehensive QA program was used to determine the acceptability of historical data. The Site 300 ERP began soil and ground water investigations in 1982. However, we did not begin receiving analytical quality assurance/quality control (QA/QC) data until 1989; therefore, the pre-1989 data that were collected are of unknown quality. The US EPA QAMS-005/80 defines data quality as the totality of features and characteristics of data that bears on its ability to satisfy a given purpose. In the current context, the characteristics of major importance are accuracy, precision, completeness, representativeness, and comparability. Using our established QA program, we determined the quality of this historical data based on its comparability to the post-1989 data. By accepting this historical data, we were able to save a considerable amount of money in recharacterization costs.

  20. Audit of work force restructuring at the Fernald Environmental Management Project

    SciTech Connect

    1996-04-23

    The Department of Energy (Department) restructured its work force at the Fernald Environmental Management Project (Fernald Project) to reduce staffing levels and to modify the mix of workers` skills in response to budget cuts, facility closures, and changes in the Fernald Project`s mission. The objective of this audit was to determine whether the work force restructurings were effective in reducing staffing levels and in changing the mix of workers` skills. As of September 30, 1995, the restructurings were not effective in reducing staffing levels or in improving the mix of workers` skills. The Fernald Environmental Restoration Management Corporation (FERMCO) spent $2.9 million to separate 255 employees in October 1993. However, by September 30, 1994, all but 14 of the employees separated were either rehired or replaced by new employees with similar skills. The second restructuring began in October 1994 and is not expected to be completed until May 1996. The Department expects the second restructuring to reduce FERMCO`s work force by 476 employees at a cost of $12.9 million. However, since the second restructuring began, FERMCO has hired 265 new employees and at September 30, 1995, had open job announcements seeking 82 additional employees. Many of these new employees have essentially the same skills as employees who separated under the two restructurings. The Department`s objectives were not met because the Fernald Area Office did not (1) require FERMCO to perform the skills analysis necessary to identify which employees were needed to perform the Fernald Project`s current mission, and (2) effectively monitor FERMCO`s restructuring efforts to ensure that the Department`s objectives were met.